PROPOSED WORKS UNDER THE PROJECT FOR TRAFFIC IMPROVEMENT AND DECONGESTION OF CITY

JUNCTION IMPROVEMENT AND DUELLING

A; JUNCTIONS

Estimated Estimated Required Cost No Junction Connecting Roads Division Traffic Status of Design Intervention (million (vpd) US$) Masiro Rd- Rd- 1 Sabalagala Junction Signalisation 16,700 1.5 Not Ready Sabalagala Rd

Pride Theatre Namirembe Rd-Mwanga 2- 2 Central Signalisation 29,300 1.5 Complete Junction Rubaga Road

3 Kabira Junction -Kisasi -Kira road Signalisation 24,500 2.0 Complete

4 Junction Tankhill/Gaba road Signalisation 35,000 1.7 Not ready

Haji Kasule Rd-Yusuf Lule Rd, 5 Junction Central Signalisation 40,000 1.5 Not ready kira road, Binaisa road

Masaka Road, Kalinda, Grade separation/ 6 Junction Lubaga 44,000 6.0 Not ready Weraga road in Ndeeba Signalisation

Kabaka Anjagala Rd/Lubaga 7 Kabaka round about Lubaga Signalisation 32,000 1.6 Not Ready Road Kivebulaya Junction Canon Apollo Kivebulya Rd/ 8 Lubaga Signalisation 32,000 1.6 Not Ready (Lubaga Road) Lubaga Road

Nabunya Road-Kabuusu 9 Nabunya Junction Lubaga Signalisation 30,000 1.6 Not Ready Road Wankulukuku Road, Masaka 10 Kabuusu Junction Lubaga Signalisation 38,000 2.2 Not ready road, Kabusu road

Hanlon Nsambya Estate Road, Gaba 11 Makindye Signalisation 31,000 1.5 Not ready Junction Road, Hanlon Road

LuwumStrt/Namirembe Rd, 12 Mini Price Junction Central Signalisation 25,000 1.4 Not ready Ben Kiwanuka Strt

13 Junction 1 Kayemba Road- Katwe Road Central Signalisation 30,000 2.0 Not Ready

14 Katwe Junction 2 Mutesi Road- Katwe Road Central Signalisation 30,000 2.0 Not Ready

Kayemba Road- Lukuli Road 15 Kayemba Junction Makindye Signalisation 10,000 1.7 Not Ready and Wamala Road

Lugogo Bypass 16 Lugogo Bypass-Naguru Road Central Signalisation 28,000 1.4 Not Ready Junction 2

Spring Road 17 Spring Road-Fifth Street Nakawa Signalisation 21,000 1.4 Not Ready Junction

Shell Bugolobi 18 Spring Road-Luthuli Avenue Nakawa Signalisation 21,000 1.4 Not Ready Junction Mutungo Tank Road-New 19 Mutungo Junction Nakawa Signalisation 21,000 1.4 Not Ready Portbell Road Albert Cook Road- Sentema 20 Junction Lubaga Signalisation 39,000 1.7 Not Ready Road-Balintumwa Road Balintumwa Road-Kitakule Balintumwa 21 Road-Nabulagala Road-Willis Lubaga Signalisation 24,000 1.7 Junction Road Construction of a traffic control centre at City 22 Central 3.5 Not ready Hall, KCCA linking all signlalized intersections 42.3

Total for Lot 1 42.3