Environmental Monitoring Report India: Mumbai Metro Rail Systems Project
Total Page:16
File Type:pdf, Size:1020Kb
Environmental Monitoring Report Semiannual Report (September 2019–February 2020) Project Number: 49469-007 Loan Number: 3775 February 2021 India: Mumbai Metro Rail Systems Project Mumbai Metro Rail Line-7 Prepared by Mumbai Metropolitan Region Development Authority for the Government of India and the Asian Development Bank. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. ABBREVATION ADB : Asian Development Bank AICA-GC : Consortium of Ayesa Inginieria Arquitectura SAV, Italfer SPA and Consulting Engineer Group Ltd AIDS : Acquired Immune Deficiency Syndrome CAP : Corrective Action Plan C&D : Construction and Demolition CO : Carbon Monoxide COC : Condition of Contracts CPCB : Central Pollution Control Board CRZ : Coastal Regulation Zone CTE : Consent to Establish CTO : Consent to Operate CGWA : Central Ground Water Authority DPR : Detail Project Report EA : Execution agency EIA : Environmental Impact Assessment EARF : Environmental assessment and Review framework EMC : Environmental Management Cell EMP : Environmental Management Plan EMoP : Environmental Monitoring Plan EMR : Environmental Monitoring Report EMS : Environmental Management System E&S : Environment and Social GC : General Consultant GCC : General Condition of Contract GOI : Government of India GRM : Grievance Redressal Mechanism HIV : Human Immune Virus IEE : Initial Environmental Examination IND : India KV : Kilo Volt Line 07 : Mumbai Metro Rail Line 07 MCGM : Municipal Corporation of Greater Mumbai MMRDA : Mumbai Metropolitan Region Development Authority MoUD : Ministry of Urban Department MoEF&CC : Ministry of Environment Forest and Climate Change MPCB : Maharashtra Pollution Control Board NOC : No Objection Certificate NOX Oxides of Nitrogen PAM : Project Administration Manual PIU : Project Implementation Unit PM : Particulate Matters PUC : Pollution Under Control SHE : Safety Health & Environment STP Sewage Treatment Plant WEH : Western Express Highway TABLE OF CONTENTS 1. Introduction 1 1.1 Purpose of Report 1 1.2 Project Description 1 1.3 Scope of the Project & Packages 8 1.4 Progress & Achievements 9 1.5 Project Implementation Progress 11 2. Compliance of Safeguards Provisions Under Loan Agreements 18 A. Environmental safeguards (category B) 18 B. Compliance to the Loan Agreement 19 3. Compliance to Project Administration Manual (Pam) 23 4. Compliance to The Civil Works Contract Agreement 28 5. Compliance to The Environmental Management Plan (Emp) 30 6. Summary of Environmental Monitoring 53 7. Conclusion 72 8. Problems Identified and Actions Recommended 70 LIST OF CHART Chart: 1 Salient Features of Metro Line 2A, 2B & 7 2 LIST OF TABLES Table 1 – Station Details 2 Table 2: Employment in Different Areas of Greater Mumbai (in Millions) 2 Table 3: Status of Award of Civil work and System Work Contract of Line-07 11 Table 4: Status of Construction Works as of February 2020 15 Table 5: Status of ADB Funded System Works progress of Line 07 18 Table 6: Status of Compliance to Loan Agreement 20 Table 7: Status of Safeguard requirement Compliance to PAM 23 Table 8: Compliance of clauses of the GCC, SCC and SHE conditions for Civil Work 28 Table 9: Status of Compliance of EMP Implementation as per EIA Report 31 Table 10: Status of Compliance of EMP Implementation as per Initial Env. Examination 44 Table 11: Summary of field Inspections during reporting period 53 Table 12: Noise Monitoring Results September 54 Table 13: Noise Monitoring Results October 2019 56 Table 14: Noise Monitoring Results November 2019 58 Table 15: Noise Monitoring Results December 2019 59 Table 16: Noise Monitoring Results January 2020 62 Table 17: Noise Monitoring Results February 2020 63 Table 18: Ambient Air Quality Monitoring Results 64 Table 19: Water Quality Monitoring Result 65 Table 20: Corrective Action Plan on SHE Safeguards MML-07 70 LIST OF ANNEXURES Appendix 1: Photolog Work Progress 73 Appendix 2: Environmental Monitoring Photographs 76 Appendix 3: Record of SHE Training 76 Appendix 4: Sample Monthly SHE Report 87 Appendix 5: Sample Drinking Water Quality Monitoring Report 96 Appendix 6: Sample Checklist Weekly Environmental Inspection report 97 Appendix 7: Exemption of Environmental Clearance of Mumbai Metro Line 07 from MoEF&CC 99 Appendix 8: Consent Letters from MPCB for Operating Batching Plant 100 Appendix 9: Rout map of Muck disposal THANE W (Manjhiwada, Balkumbpada, Sainath Nagar) 111 Appendix 10: Sample Tree Transplantation Detail 114 Appendix 11: A. Land allotment letter for transplantation of trees and new plantation 122 Appendix 12: Sample Tree felling permission letter from MCGM 125 Appendix 13: Condition of Contract related to Environmental Management/ Monitoring 127 Appendix 14: A. Sample Traffic Diversion Permission Letter 129 Appendix 15: A. Sample Traffic Diversion Plan 132 Appendix 16: Vibration Monitoring along alignment of Line 07 133 List of Annexure Annexure 1: Site Safety Plan & Safety Assurance Plan for MRS1, MS01 & MS03 136 Annexure 2: Site Specific Environmental Management Plan for MRS1, MS01 & MS03 137 EXECUTIVE SUMMARY 1. This report is the second semi-annual report on environmental safeguards compliance of the Mumbai Metropolitan Region Authority for Line 07 Project. It covers the period from September 2019 to February 2020. 2. Mumbai does have a very good transportation system but has not been able to keep pace with the increasing demand. The carrying capacity of the Rail and bus-based system has been increased considerably over the last 4 – 5 decades but traffic has increased much faster. Due to various constraints of existing system as also the limitations in increasing their carrying capacity, a new Mass Rapid Transit System is essential to take care for the next few decades. 3. A master plan has been prepared and various corridors finalized. The master plan includes a total length of 338 kms. The 07 network will cover Andheri East to Dahisar East for providing seamless transportation for the Citizens of Mumbai. 4. Mumbai Metro Line – 07 route length is 16.475 Km & is designed completely on elevated corridor comprising of 13 stations. It will provide interconnectivity among the existing Western Express Highway, Eastern Express Highway, Western Railway, Central Railway, Monorail, Metro Line 1 (Ghatkopar to Versova) and Metro Line 2A (Dahisar to D N Nagar), Metro Line 4 (Wadala to Kasarvadavali) & Metro Line 3 (Colaba to SEEPZ) under implementation & also provide connectivity between the Eastern & Western Suburban Mumbai. 5. Implementation of Andheri-E to Dahisar-E corridor of Mumbai Metro Project, including all the works mentioned in the DPR for a length of 16.475 KM will be Executed by MMRDA for which consortium of Ayesa Ingenieria, Italfer, Consulting Engineering Group & Ayesa India Ltd (AICA) appointed as General Consultant. 6. The environmental safeguards of the project are being implemented in compliance with the loan covenants, project agreement and contractors are complying with the proposed mitigation measures described in the Environmental Management Plan (EMP); Safety, Health and Environment (SHE) Manual and the contract specifications. The implementation of environmental safeguards is being monitored at Mumbai Metropolitan Regional Development Authority level. With exception of few issues the project is being implemented in compliance with project requirement. 7. The construction works are proceeding in accordance with the provisions of the EMP such as review of monitoring reports, regulatory compliance action plan and approval by MMRDA. 8. Civil Administration, MMRDA and AICA GC has ensured round the clock availability of Rescue team consisting of Ambulance, Civil defence, Earth moving Machines & Crane. This is to ensure quick response to any problem which may arise during construction. 9. MMRDA and AICA GC officials have regularly been meeting with the local people and business associations in the project area to inform them about the construction works. Measures have been taken to address concerns of the local businesses such as stopping of work and providing proper pathways for customers during festivals. All reports and information on the project are disclosed on the MMRDA website. In addition, MMRDA has a full-time Public Relation Officer dealing with media/press issues and also maintains a Facebook page and twitter account for disclosing project information and responding to queries and concerns from the general public. 10. Various proactive measures are being taken to implement project in compliance with requirements, prevent damages, coordination with relevant agencies, communicate with the public and address grievances of the local public. Chart: 1 Salient Features of Metro Line 2A, 2B & 7 Project Features Description Line No. 2A Line No. 2B Line No. 7 From-To Dahisar (E) to DN D. N. Nagar - Dahisar (East)- Nagar Mandale Andheri (East) Elevated Route (km) 18.6 23.6 16.475 Stations (All Elevated) 17 20 13 Total Capital Cost (in crores) 6410 10,986 6,208 Financial Internal Rate of Return 10.91% 10.78% 8.43% Economical Internal Rate of 25.33% 25.20% 22.54% Return