Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

The 614th meeting of the State Level Environment Impact Assessment Authority was convened on 04.06.2020 at the Authority's Office in Environmental Planning and Co- Ordination Organization (EPCO), Paryavaran Parisar, Bhopal. The meeting was chaired by Shri Rakesh K. Shrivastava, Chairman, SEIAA. The following members attended the meeting:- 1 Shri R.K. Sharma Member 2. Smt. Tanvi Sundriyal Member Secretary A. Following other than mining and mining cases have been considered:-

S.No. Case No. Category No. & date of latest SEAC & SEIAA meeting 1. 5987/2019 1(a) 432th SEAC Meeting dated 18/05/2020. 2. 6299/2019 1(a) 432th SEAC Meeting dated 18/05/2020. 3. 6674/2019 1(a) 432th SEAC Meeting dated 18/05/2020 4. 6981/2020 1(a) 432th SEAC Meeting dated 18/05/2020 5. 6979/2020 1(a) 432th SEAC Meeting dated 18/05/2020 6. 6875/2020 1(a) 432th SEAC Meeting dated 18/05/2020 7. 6982/2020 1(a) 432th SEAC Meeting dated 18/05/2020 8. 6777/2020 1(a) 432th SEAC Meeting dated 18/05/2020 9. 6394/2019 5(f) 433rd SEAC Meeting dated 19/05/2020. 10. 5839/2019 5(f) 433rd SEAC Meeting dated 19/05/2020. 11. 6284/2019 5(f) 433rd SEAC Meeting dated 19/05/2020. 12. 6258/2019 1(a) 433rd SEAC Meeting dated 19/05/2020. 13. 6724/2019 5(f) 433rd SEAC Meeting dated 19/05/2020. 14. 6113/2019 1(a) 433rd SEAC Meeting dated 19/05/2020. 15. 6400/2019 1(a) 433rd SEAC Meeting dated 19/05/2020. 16. 6947/2020 1(a) 433rd SEAC Meeting dated 19/05/2020. 17. 6980/2020 1(a) 433rd SEAC Meeting dated 19/05/2020. 18. 6990/2020 1(a) 433rd SEAC Meeting dated 19/05/2020. 19. 6991/2020 1(a) 433rd SEAC Meeting dated 19/05/2020. 20. 6952/2020 1(a) 433rd SEAC Meeting dated 19/05/2020. 21. 7005/2020 1(a) 433rd SEAC Meeting dated 19/05/2020. 22. 7008/2020 1(a) 433rd SEAC Meeting dated 19/05/2020. 23. 5780/2018 8(a) 434th SEAC Meeting dated 20/05/2020. 24. 5949/2015 8(b) 434th SEAC Meeting dated 20/05/2020. 25. 6537/2019 5(f) 434th SEAC Meeting dated 20/05/2020 26. 6498/2019 5(f) 434th SEAC Meeting dated 20/05/2020 27. 5853/2019 8(a) 434th SEAC Meeting dated 20/05/2020 28. 7011/2020 1(a) 434th SEAC Meeting dated 20/05/2020 29. 7014/2020 1(a) 434th SEAC Meeting dated 20/05/2020 30. 6992/2020 1(a) 434th SEAC Meeting dated 20/05/2020 31. 6993/2020 1(a) 434th SEAC Meeting dated 20/05/2020 32. 6659/2019 1(a) 434th SEAC Meeting dated 20/05/2020 33. 6485/2019 1(a) 434th SEAC Meeting dated 20/05/2020 34. 6725/2020. 1(a) 434th SEAC Meeting dated 20/05/2020 35. 5739/2018 7(h) 434th SEAC Meeting dated 20/05/2020

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 1 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

36. 6844/2020 1(a) 432th SEAC Meeting dated 18/05/2020. 37. 6996/2020 1(c) 432th SEAC Meeting dated 18/05/2020. 38. 6941/2020 1(a) 432th SEAC Meeting dated 18/05/2020. 39. 6961/2020) 1(a) 432th SEAC Meeting dated 18/05/2020. 40. 6978/2020 1(a) 432th SEAC Meeting dated 18/05/2020. 41. 7004/2020 1(a) 432th SEAC Meeting dated 18/05/2020. 42. 7018/2020 1(a) 432th SEAC Meeting dated 18/05/2020. 43. 6999/2020 1(a) 432th SEAC Meeting dated 18/05/2020. 44. 6950/2020 1(a) 432th SEAC Meeting dated 18/05/2020. 45. 6794/2020 1(a) 433rd SEAC Meeting dated 19/05/2020. 46. 6948/2020 1(a) 433rd SEAC Meeting dated 19/05/2020. 47. 6788/2020. 8(a) 433rd SEAC Meeting dated 19/05/2020. 48. 7007/2020 1(a) 434th SEAC Meeting dated 20/05/2020. 49. 5529/2017 1(a) 434th SEAC Meeting dated 20/05/2020. 50. 5533/2017 1(a) 434th SEAC Meeting dated 20/05/2020. 51. 7010/2020 8(a) 434th SEAC Meeting dated 20/05/2020. 52. 6872/2020 8(a) 434th SEAC Meeting dated 20/05/2020. 53. 6671/2019 8(a) 434th SEAC Meeting dated 20/05/2020. 54. 7012/2020 1(a) 434th SEAC Meeting dated 20/05/2020. 55. 6546/2019 1(a) 434th SEAC Meeting dated 20/05/2020. 56. 7024/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 57. 7038/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 58. 7045/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 59. 7046/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 60. 7047/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 61. 7048/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 62. 7049/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 63. 7050/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 64. 7051/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 65. 7053/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 66. 7054/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 67. 7055/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 68. 7056/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 69. 7057/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 70. 7058/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 71. 7059/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 72. 7060/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 73. 7061/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 74. 7063/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 75. 7064/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 76. 7065/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 77. 7020/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 78. 7021/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 79. 7022/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 80. 7089/ 2020 1(a) 435th SEAC Meeting dated 29.05.2020. 81. 7090/2020 1(a) 435th SEAC Meeting dated 29.05.2020.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 2 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

th 82. 7091/2020 1(a) 435 SEAC Meeting dated 29.05.2020. 83. 7092/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 84. 7093/2020 1(a) 435th SEAC Meeting dated 29.05.2020. 85. 6940/2020 1(a) EC Transfer 86. 7029/2020 1(a) EC Transfer 87. 7030/2020 1(a) EC Transfer

88. 7031/2020 1(a) EC Transfer 89. 7032/2020 1(a) EC Transfer 90. 7033/2020 1(a) EC Transfer 91. 7034/2020 1(a) EC Transfer 92. 7035/2020 1(a) EC Transfer

93. 7036/2020 1(a) EC Transfer 94. 7037/2020 1(a) EC Transfer 95. 7026/2020 1(a) EC Transfer 96. 7107/2020 1(a) EC Transfer 97. 3005/2015 1(a) EC Transfer

98. 7067/2020 1(a) EC Transfer 99. 7068/2020 1(a) EC Transfer

1. Case No. - 5987/2019 M/s Ram Chandra Badri Prasad Gour, C/o Rajesh Jain (Partner), B.D.Agrawal ward, Civil Lines, PO & Dist. , MP – 483501 Prior Environment Clearance for Limestone Mine in an area of 12.93 Ha. (550095 tonne per annum) (Khasra No. 187, 188, 207P, 208, 210P, 211, 212P, 214, 215, 219P), Village - Amehta, Tehsil - Vijayraghogarh, Dist. Katni (MP) This case was recommended in 432nd SEAC meeting dated 18.05.2020. PP may be called for presentation. 2. Case No. – 6299/2019 M/s Swastik Builmat Pvt. Ltd, E-102, Ashok Ratan, Vidhan Sabha Road, Shankar Nagar, Dist. Raipur, CG – 492004 Prior Environment Clearance for Iron Ore Mine in an area 9.02 ha.(Mining-5.42 ha and Ancillary activity -3.60 ha;). (50,000 tonne per annum) (Khasra No. 413 Part, 423, 476/1, 476/2), Village - Pratappur, Tehsil - , Dist. (MP). EIA Consultant: Aplinka Solutions & Technologies Pvt. Ltd. This case was recommended in 432nd SEAC meeting dated 18.05.2020. PP may be called for presentation. 3. Case No. – 6674/2019 Shri Shivmangal Singh Gour, Basant Vihar, 301, Gulmohar Basant Vihar, Dist. Indore, MP - Prior Environment Clearance for Murrum and Stone Quarry in an area of 1.619 ha. (Murrum – 5,000 cum per annum, Stone – 10,000 cum per annum) (Khasra No. 22/1/1 (P)), Village - Ranipur, Tehsil - Majhgawa, Dist. Satna, (MP). This case was recommended in 432nd SEAC meeting dated 18.05.2020. PP may be called for presentation. 4. Case No 6981/2020 Shri Santosh Sahu S/o Shri Tulsiram Sahu, Mu. Po. Dhusawani, Tehsil - Tamia, Dist. , MP – 480661 Prior Environment

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 3 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

Clearance for Stone Quarry in an area of 0.882 ha. (6469 cum per annum) (Khasra No. 508/1), Village - Dhusawani, Tehsil - Tamia, Dist. Chhindwara (MP) This case was recommended in 432nd SEAC meeting dated 18.05.2020. PP may be called for presentation. 5. Case No 6979/2020 M/s Gaur Road Tarcoat Pvt. Ltd, Plot No. 2283, Sharda Chowk, Nagpur Road, Dist. Jabalpur, MP Prior Environment Clearance for Metal Stone Quarry in an area of 1.920 ha. (15000 cum per annum) (Khasra No. 321), Village - Jhanki Mal, Tehsil - Dindori, Dist. Dindori (MP) This case was recommended in 432nd SEAC meeting dated 18.05.2020. PP may be called for presentation. 6. Case No 6875/2020 M/s Atcon India Limited, House No. 413, Sector-16A, Dist. Faridabad, Haryana – 120002 Prior Environment Clearance for Murrum Quarry in an area of 3.0 ha. (138101 cum per annum) (Khasra No. 09), Village - Jamaniya, Tehsil - Mungaowli, Dist. Ashoknagar (MP) This case was recommended in 432nd SEAC meeting dated 18.05.2020. PP may be called for presentation. 7. Case No 6982/2020 Shri Piyush Bajpai S/o Shri R.K.Bajpai, 351, Ram Nagar, Jawaharganj Ward, Durga Mandir, Dist. Jabalpur, MP – 482001 Prior Environment Clearance for Stone and Murrum Quarry in an area of 1.250 ha. (12937 cum per annum) (Khasra No. 626), Village - Supawara, Tehsil - Kundam, Dist. Jabalpur (MP) This case was recommended in 432nd SEAC meeting dated 18.05.2020. PP may be called for presentation. 8. Case No 6777/2020 Shri Yashwardhan Singh, R/o Rajendra Nagar, Nishant Colony, Ward No. 26, Dist. Satna, MP – 485001 Prior Environment Clearance for Murrum Quarry in an area of 2.00 ha. (24,175 cum per annum) (Khasra No. 256/1/1 Part), Village - Kathwariya, Tehsil - Nagod, Dist. Satna (MP). This case was recommended in 432nd SEAC meeting dated 18.05.2020. PP may be called for presentation. 9. Case No. – 6394/2019 M/s Medilux Laboratories Pvt. Ltd, Plot No. 98 - 99, Sector - 1, Industrial Area, Pithampur, Dist. Dhar, MP – 454775. Prior Environment Clearance for Capacity Expansion from 400 TPA to 1,000 TPA in Bulk Drugs, Fine Chemicals, API & its Intermediates Production facility at Plot No. 98-99, Pithampur Industrial Area, Sector-1, Pithampur, Dist. Dhar , This case was recommended in 433rd SEAC meeting dated 19.05.2020. PP may be called for presentation. 10. Case No. - 5839/2019 M/s Suneeta Chemicals, Plot No. 24, Sector-A, Industrial Area, Sanwer road, Indore, MP – 452015 Prior Environment Clearance for Manufacturing of Bulk Drug & Intermediate with production capacity of 26,500

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 4 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

kg/month and 29.30 kg/day of by-product at Plot No. 16, 17, 20 & 24, Sanwer Road, Industrial Area, Sector-A, Indore .Cat. - 5(f) Project Synthetic Organic Chemicals Industry (Bulk Drug). This case was recommended in 433rd SEAC meeting dated 19.05.2020. PP may be called for presentation. 11. Case No. - 6284/2019 M/s Ripride Remedies Pvt. Ltd, 16/8/1, Race Course Road, Indore, (M.P.) Prior Environment Clearance for Proposed Manufacturing of Bulk Drug and Intermediate facility at plot no. 40, Pithampur Industrial Area, Sector-3, Sagor Village, Pithampur, Dist. Dhar (M.P.) Cat. 5 (f) Synthetic Organic Chemicals Industry.. Env. Con. – Creative Enviro Services. This case was recommended in 433rd SEAC meeting dated 19.05.2020. PP may be called for presentation. 12. Case No. – 6258/2019 M/s Jai Bhadra Kali Granite, R/o Village - Badaura Kalan, Tehsil - Gaurihar, Dist. Chhatarpur, MP Prior Environment Clearance for Crusher Stone Quarry in an area of 4.00 ha. (3,08,536 cum per annum) (Khasra No. 946 Parts), Village - Badaura Kalan, Tehsil - Gaurihar, Dist. Chhatarpur (MP). This case was recommended in 433rd SEAC meeting dated 19.05.2020. PP may be called for presentation. 13. Case No. – 6724/2019 M/s. Amir Chem Pvt. Ltd, Plot No. 41- 42, Sector III, Industrial Area, Pithampur, Dist. Dhar, MP – 454774. Prior Environment Clearance for Manufacturing of Synthetic Organic Chemicals, Bulk Drug & its Intermediates Total Plot area 9181 sq.m. Proposed Capacity- 300 MT per month (category 5(f)), at Plot No. 41-42, Sector 3, Industrial Area, Pithampur, Dist. Dhar, (MP). This case was recommended in 433rd SEAC meeting dated 19.05.2020. PP may be called for presentation. 14. Case No. – 6113/2019 Shri Malkan Singh, Haal Mukam, A.M. 111, D.D. Nagar, Dist. Gwalior, MP – 474012 Prior Environment Clearance for Stone Quarry in an area of 2.25 ha. (50,844 cum per annum) (Khasra No. 4174), Village - Parsen, Tehsil - Gwalior, Dist. Gwalior (MP). This case was recommended in 433rd SEAC meeting dated 19.05.2020. PP may be called for presentation. 15. Case No. – 6400/2019 Shri Surjeet Singh, Haal Mukam, A.M. 111, D.D. Nagar, Dist. Gwalior, MP - 474012, Email - [email protected], Mobile – 9131578376 Prior Environment Clearance for Stone Quarry in an area of 2.00 ha. (57,000 cum per annum for 1st 3 year, 41,610 cum per annum for last 2 years) (Khasra No. 4173), Village - Parsen, Tehsil - Gwalior, Dist. Gwalior (MP). This case was recommended in 433rd SEAC meeting dated 19.05.2020. PP may be called for presentation.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 5 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

16. Case No 6947/2020 Shri Akil Hussain, R/o Pir Gali, Pansemal, Dist. Barwani, MP - 451770, Prior Environment Clearance for Stone Quarry in an area of 1.0 ha. (2470 cum per annum) (Khasra No. 131/4, 133/2), Village - Dondwada, Tehsil - Pansemal, Dist. Barwani This case was recommended in 433rd SEAC meeting dated 19.05.2020. PP may be called for presentation. 17. Case No 6980/2020 Shri Pradeep Kumar Keshari, Village - Raghunathgarh, Tehsil - Hanumana, Dist. Rewa, MP Prior Environment Clearance for Stone Quarry in an area of 3.0 ha. (As per Mine Plan 42134 cum per annum) (Khasra No. 239/2), Village - Raghunathgarh, Tehsil - Hanumana, Dist. Rewa (MP) This case was recommended in 433rd SEAC meeting dated 19.05.2020. PP may be called for presentation. 18. Case No 6990/2020 M/s S.R.Traders, Shri Subodh Dwivedi, Kusum Kunj, Suncity, Choubey Colony, Dist. Chhatarpur, MP – 471001 Prior Environment Clearance for Stone Quarry in an area of 1.450 ha. (79235 cum per annum) (Khasra No. 366/1/Ka), Village - Jhinna, Tehsil - Lavkhush Nagar, Dist. Chhatarpur (MP) This case was recommended in 433rd SEAC meeting dated 19.05.2020. PP may be called for presentation. 19. Case No 6991/2020 Shri Abhishek Singh S/o Shri Awadh Singh, R/o H.No. 17, Ward No. 23, Shital Homes, Mandideep, Dist. Raisen, MP – 462042 Prior Environment Clearance for Murrum Quarry in an area of 2.0 ha. (11628 cum per annum) (Khasra No. 31, 32 Parts), Village - Pipaliya Kesho, Tehsil - Kolar, Dist. Bhopal (MP) This case was recommended in 433rd SEAC meeting dated 19.05.2020. PP may be called for presentation. 20. Case No 6952/2020 Shri Sunil Kumar, Village - Sothar, Tehsil - Goharganj, Dist. Raisen, MP – 464551 Prior Environment Clearance for Murrum Quarry in an area of 1.0 ha. (5767 cum per annum) (Khasra No. 84/2/1), Village - Sothar, Tehsil - Gouharganj, Dist. Raisen (MP) This case was recommended in 433rd SEAC meeting dated 19.05.2020. PP may be called for presentation. 21. Case No 7005/2020 Shri Narayan Singh Thakur, Tehsil - Banda, Dist. Sagar, MP - 480001, Prior Environment Clearance for Stone Quarry in an area of 1.21 ha. (1641 cum per annum) (Khasra No. 294, 303), Village - Ratanpur, Tehsil - Shahgarh, Dist. Sagar (MP) This case was recommended in 433rd SEAC meeting dated 19.05.2020. PP may be called for presentation. 22. Case No 7008/2020 Smt. Kiran Mishra, Village - Rampur, Tehsil - Rampur Nakin, Dist. Sidhi, MP – 486661 Prior Environment Clearance for Earth Quarry in an area

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 6 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

of 2.0 ha. (10000 cum per annum) (Khasra No. 298/1, 298/2), Village - Rampur, Tehsil - Rampur Naikin, Dist. Sidhi (MP) This case was recommended in 433rd SEAC meeting dated 19.05.2020. PP may be called for presentation. 23. Case No. - 5780/2018 M/s. Fortune Soumya Santoza, C/o Fortune Soumya Housing, Bagli, Behind C-21 Mall, Bhopal, MP – 462016. Prior Environment Clearance for Construction of Group Housing Project "Fortune Soumya Heritage" Khasra No. – 99/2, 122, 123, 132, 133, 134, 135/2, 136 to 162, at Village - Bhairopur, Tehsil - Huzur & Dist. -Bhopal, (M.P.). Total Project Area = 43981.27 sqm., Built up Area = 59892.30 sqm). Category: 8(a) Building & Construction Project. Env. Con. – ENV DAS India Pvt. Ltd., Lucknow (U.P.). This case was recommended in 434th SEAC meeting dated 20.05.2020. PP may be called for presentation. 24. Case No.5949/2015 M/s Aarone Developers Pvt. Ltd, 6th floor, Office Tower Select City Walk, A-3 District Center Saket, New Delhi – 110017 Prior Environment Clearance for Proposed Area Development and Township Project "County Walk" (Total Plot Area: 8,08,110 sqm, Total Planning Area: 7,81,340.0 sqm) at Khasra no 12/3, 12/7, 12/4, 12/5, 46/1/2/3, 12/6 (P), 12/8, 14, 15/1, 17/1, 17/2, 19, 18/1, 36, 37, 38, 39, 48, 49,40/1, 46/1/1(P), 46/1/1/2, 46/1/2/1, Village - Jalariya, Tehsil & Dist. Indore, MP.Environment Consultant-ENV DAS (India) Pvt. Ltd. This case was recommended in 434th SEAC meeting dated 20.05.2020. PP may be called for presentation. 25. Case No. 6537/2019 M/s Ipca Laboratories Ltd., Shri Manoj Kumar Mittal, Vice President, C-89 to C-95, MIDC Area, MIDC Mahad, Dist. Raigad, Mah. Prior Environment Clearance for Proposed in production capacity of intermediates, API, API-Oncology and R&D Products at Plot No. 19A, 19-B, 20-A, 20-B, 21-A, 21-B, & 22, Industrial Area No. 1, Dist. Dewas, MP. This case was recommended in 434th SEAC meeting dated 20.05.2020. PP may be called for presentation. 26. Case No. 6498/2019 M/s Goyal Resins & Polymers, 414/5, Khatipura, Sukhliya Gram, Link Road, Dist. Indore, (M.P.) - 452010. Prior Environment Clearance for Proposed Expansion of Alkyd Resin, Hard Oil, Process Oil and Stand Oil Unit at Plot No. 414/5, Khatipura, Sukhliya Gram, Link Road, Near Industrial Area, Indore, (M.P.). Existing Capacity – 130 MTPA, Proposed Capacity – 3,200 MTPA., Land Area – 1171.73 sqm, Cat. – 5 (f) Synthetic organic chemicals. This case was recommended in 434th SEAC meeting dated 20.05.2020. PP may be called for presentation. 27. Case No. - 5853/2019 M/s. Sakar Builders, 118, Rafael Towers, 8/2 Old Palasia, Dist. Indore, MP – 452001 Prior Environment Clearance for Construction of Residential Cum Commercial Project "Elite Apex" (Total Plot Area = 13,930.0 sqm., Total Built-up Area = 59,977.20 sqm) at Khasra no 161/1/2, 161/1/3, 161/1/4,

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 7 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

161/1/5, 161/1/6, 162/1, 162/2, 161/1/1, 161/2, Village - Pipaliya Kumar, Tehsil - Indore & Dist. Indore, MP. (Building Construction).Env. Con. – This case was recommended in 434th SEAC meeting dated 20.05.2020. PP may be called for presentation. 28. Case No 7011/2020 Shri Jai Jaiswal S/o Shri Vinod Jaiswal, Ekta Colony, Akbar Ward, Dist. Seoni, MP - 480661, Prior Environment Clearance for Stone Quarry in an area of 1.40 ha. (12000 cum per annum) (Khasra No. 234/1, 239/1), Village - Ghatpipariya, Tehsil - Seoni, Dist. Seoni (MP) This case was recommended in 434th SEAC meeting dated 20.05.2020. PP may be called for presentation. 29. Case No 7014/2020 M/s Jaiswal Stone Crusher, Partner - Shri Shyamlal Jaiswal, Village & Post - Jhara, Tehsil - Sarai, Dist. Singrauli, MP - 486881 Prior Environment Clearance for Stone Quarry in an area of 4.6560 ha. (139147 cum per annum) (Khasra No. 2898/2, 2927/2, 2927/3, 2927/4, 2927/5, 2928, 3112, 3113, 3114), Village - Jhara, Tehsil - Sarai, Dist. Singrauli (MP) This case was recommended in 434th SEAC meeting dated 20.05.2020. PP may be called for presentation. 30. Case No 6992/2020 Shri Ashok Kumar Kushwaha S/o Shri Jairam Kushwaha, R/o Sunoniya, Tehsil - Prathvipur, Dist. Niwari, MP – 472336 Prior Environment Clearance for Stone Mine in an area of 2.0 ha. (32000 cum per annum) (Khasra No. 2 Part), Village - Kunwarpura, Tehsil - Prathvipur, Dist. Niwari (MP) This case was recommended in 434th SEAC meeting dated 20.05.2020. PP may be called for presentation. 31. Case No 6993/2020 Shri Naeem Khan S/o Shri Salim Khan, Village - Nargudakhas, Tehsil & Dist. Tikamgarh, MP – 472001 Prior Environment Clearance for Murrum Quarry in an area of 3.0 ha. (10000 cum per annum) (Khasra No. 333/1), Village - Nargudakhas, Tehsil - Tikamgarh, Dist. Tikamgarh (MP) This case was recommended in 434th SEAC meeting dated 20.05.2020. PP may be called for presentation. 32. Case No. – 6659/2019 Shri Shivmangal Singh Gour, Basant Vihar, 301, Gulmohar Basant Vihar, Dist. Indore, MP – 452010 Prior Environment Clearance for Murrum and Stone Quarry in an area of 1.810 ha. (Murrum – 5,000 cum per annum, Stone – 10,000 cum per annum) (Khasra No. 154 (P)), Village - Rampur Khurd, Tehsil - Majhgawa, Dist. Satna, (MP). This case was recommended in 434th SEAC meeting dated 20.05.2020. PP may be called for presentation. 33. Case No. – 6485/2019 Smt. Sunayana Pandey W/o Shri Vinod Kumar Pandey, Village - Mahadeva, Post - Deora 1, Tehsil - Kotar, Dist. Satna, MP. Prior

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 8 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

Environment Clearance for Murrum Quarry in an area of 1.60 ha. (10,000 cum per annum) (Khasra No. 02), Village - Bihara, Tehsil - Kotar, Dist. Satna (MP). This case was recommended in 434th SEAC meeting dated 20.05.2020. PP may be called for presentation. 34. Case No. – 6725/2020 Shri Rameshwar Gupta S/o Shri Rambarosilal Gupta, Approach Road, Kolaras, Dist. Shivpuri, MP – 473770. Prior Environment Clearance for Stone and Murrum Quarry in an area of 2.870 ha. (Stone – 21,095 cum per annum, Murrum – 10,905 cum per annum) (Khasra No. 1767, 1768, 1769, 1770/1, 1771/1, 1796/1, 1797), Village - Bamor, Tehsil - Badarwas, Dist. Shivpuri (MP). This case was recommended in 434th SEAC meeting dated 20.05.2020. PP may be called for presentation. 35. Case No. - 5739/2018 The Executive Engineer, Municipal Corporation, Pragati Nagar, Rastipura Colony, Burhanpur, (M.P.) 450331. Prior Environment Clearance for Proposed 4.5 MLD Common Effluent Treatment Plant at Khasra No. 364/1, Near Sindhi Basti Shamshan Ghat, Burhanpur, Distt. - Burhanpur (M.P.) Category - 7(h) Infrastructure and Miscellaneos Project. This case was recommended in 434th SEAC meeting dated 20.05.2020. PP may be called for presentation. 36. Case No 6844/2020 Shri Vinod Patidar S/o Shri Dhartilal Patidar, Manawar, Tehsil - Manawar, Dist. Dhar, MP – 454446 Prior Environment Clearance for Stone Quarry in an area of 4.00 ha. (28,500 cum per annum) (Khasra No. 01), Village - Nigrani, Tehsil - Manawar, Dist. Dhar (MP). This case was discussed in 432nd SEAC meeting dated 18.05.2020 and it was recorded that......

The case was scheduled for presentation but neither the Project Proponent (PP) nor his representative was present to explain the query which might be raised or to make any commitment which may be desired by the committee during the deliberation. Earlier PP was also absent in 430th SEAC meeting dated 17/3/2020 and in 428th SEAC meeting dated 29/02/2020. Committee decided that since sufficient opportunities has been given to the PP for appraisal of their case but PP remains absent thus committee decided that case shall be returned to SEIAA for delisting assuming that PP is not interested to continue with the project. As per above observation of SEAC, it has been decided to delist the case on the condition that if PP intends to present the case in SEIAA, it will then be relisted for appraisal. Copy to PP and all concerned. 37. Case No 6996/2020 Executive Engineer, Narmada Development Div. No. 28, Punasa, Dist. Khandwa, MP Prior Environment Clearance for ISP - Parwati Phase III & IV - Lift Micro Irrigation Project, Village - Dhamapuri, Tehsil - Ichhawar, Dist. Sehore, Pumping locations 2,3 and 4 district Dewas, pumping location 5 is in district Sehore; command area in district Sehore, Shajapur and Tehsil - Shujalpur, Dist. Shajapur (MP)

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 9 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

This case was discussed in 432nd SEAC meeting dated 18.05.2020, ToR recommended by SEAC is hereby approved 38. Case No 6941/2020 Shri Ajay Kumar Pathak, Semariya Chowk, Chanakyapuri, PO & DIst. Satna, MP Prior Environment Clearance for Expansion of Limestone Mine in an area of 8.094 ha. (Limestone & Reject Stone – 50,000 to 7,00,000 TPA) (Khasra No. 1317/13), Village - Rampur Chourasi, Tehsil - Raghuraj Nagar, Dist. Satna (MP) This case was discussed in 432nd SEAC meeting dated 18.05.2020, ToR recommended by SEAC is hereby approved 39. Case No 6961/2020 M/s Nirmala Minerals, Pathak Ward, Dist. Katni, MP – 483501 Prior Environment Clearance for Expansion of Iron ore Mine in an area of 32.374 ha. (2,00,000 to 6,00,000 Tonne per annum) (Khasra No. 440/1 (New), 628/1 (old)), Village - Dubiyara, Tehsil - Sihora, Dist. Jabalpur (MP) This case was discussed in 432nd SEAC meeting dated 18.05.2020, ToR recommended by SEAC is hereby approved 40. Case No 6978/2020 M/s Nirmala Minerals, Pathak Ward, Dist. Katni, MP – 483501 Prior Environment Clearance for Expansion of Iron ore Mine in an area of 20.141 ha. (50,000 to 500000 Tonne per annum) (Khasra No. 1093P (New), 680P (old)), Village - Agaria, Tehsil - Sihora, Dist. Jabalpur (MP) This case was discussed in 432nd SEAC meeting dated 18.05.2020, ToR recommended by SEAC is hereby approved 41. Case No 7004/2020 M/s Shree Anand Khanij Udyog, 110, Bhasin Residency, South Civil Lines, Dist. Jabalpur, MP – 482001 Prior Environment Clearance for Expansion of Bauxite, Laterite and Fire Clay Mine in an area of 5.22 ha. (50,000 to 1,00000 Tonne per annum) (Khasra No. 49 Part), Village - Rousara, Tehsil - Majholi, Dist. Jabalpur (MP) This case was discussed in 432nd SEAC meeting dated 18.05.2020, ToR recommended by SEAC is hereby approved 42. Case No 7018/2020 Shri Avinash Agarwal, PO - Jaitwara, Dist. Satna, MP – 485221 Prior Environment Clearance for Laterite Quarry in an area of 11.915 ha. (30000 Tonne per annum) (Khasra No. 33/1, 33/2, 33/3, 34, 35, 36, 37/1, 37/2, 38, 39/1, 39/2, 41P, 59/1 Ka, 59/1 Kha, 60, 61/1, 61/2, 61/3), Village - Gamiraha, Tehsil - Majhgawan, Dist. Satna (MP) This case was discussed in 432nd SEAC meeting dated 18.05.2020, ToR recommended by SEAC is hereby approved 43. Case No 6999/2020 M/s A.W. and Sons Marble, 907/1, Badi Omti, Dist. Jabalpur, MP – 482002 Prior Environment Clearance for Marble Mine in an area of 10.79 ha (Marble - 2218 cum per annum, Waste - 8870 cum per annum) (Khasra No. 807, 808/1, 808/2, 808/3, 812/1, 812/2, 813, 816, 817, 818/1, 818/2, 818/3), Village - Nimas, Tehsil - , Dist. Katni (MP)

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 10 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

This case was discussed in 432nd SEAC meeting dated 18.05.2020, ToR recommended by SEAC is hereby approved 44. Case No 6950/2020 M/s Mahak Agro India Limited, Pathak Bhawan, Nai Abadi, Dist. Mandsaur, MP Prior Environment Clearance for Laterite Mine in an area of 12.838 ha. (50000 MT per annum) (Khasra No. 141/1), Village - Jamunia Meena, Tehsil - Mandsaur, Dist. Mandsaur (MP) This case was discussed in 432nd SEAC meeting dated 18.05.2020, ToR recommended by SEAC is hereby approved 45. Case No 6794/2020 Shri Santosh Nayak, Village - Gudali, Tehsil - Meghnagar, Dist. Jhabua, MP – 457772 Prior Environment Clearance for Stone Quarry in an area of 4.00 ha. (24,832 cum per annum) (Khasra No. 68), Village - Tejpura, Tehsil - Thandla, Dist. Jhabua This case was discussed in 433rd SEAC meeting dated 19.05.2020 and it was recorded that......

The case was scheduled for presentation, but neither the Project Proponent (PP) nor his representative was present to explain the query which might be raised or to make any commitment which may be desired by the committee during the deliberation. Earlier PP was also absent in SEAC meeting 426th SEAC meeting dated 27/2/2020 & 424th SEAC meeting dated 12/02/2020. Committee decided that since sufficient opportunities has been given to the PP for appraisal of their case but PP remains absent thus committee decided that case shall be returned to SEIAA for delisting assuming that PP is not interested to continue with the project. As per above observation of SEAC, it has been decided to delist the case on the condition that if PP intends to present the case in SEIAA, it will then be relisted for appraisal. Copy to PP and all concerned. 46. Case No 6948/2020 Ku. Meenal Solanki D/o Shree Hirendra Singh, R/o 97, Ward No. 7, Bada Rawla, Tehsil - Alote, Dist. Ratlam, MP Prior Environment Clearance for Stone Quarry and Sealable Murrum in an area of 2.0 ha. (Stone - 3395 cum per annum, Sealable Murrum - 1750 cum per annum) (Khasra No. 4), Village - Khamariya, Tehsil –Alote, Dist. Ratlam (MP) This case was discussed in 433rd SEAC meeting dated 19.05.2020, ToR recommended by SEAC is hereby approved 47. Case No 6788/2020 M/s Nakoda Construction Company, Partner - Shri Ahhay Jain, 3-4, Diamond Colony, Dist. Indore, MP – 452001 Prior Environment Clearance for Construction of Proposed "Golden Palm" (Total Plot Area – 30,687.30 sqm, Total Proposed Built up Area – 50,765.88 sqm) at Khasra No. – 200/1, 201, 203, 204, 206, 207, 214/1, 214/2, Village - Niranjanpur, Tehsil - Indore, Dist. Indore, MP.Category: 8(a) Building & Construction Project. This case was discussed in 433rd SEAC meeting dated 19.05.2020, ToR recommended by SEAC is hereby approved

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 11 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

48. Case No 7007/2020 M/s ANS Construction Pvt. Ltd, Director - Shri Prashant Hashmukhlal Shah, 206 - Iskan Plaza, Bhulka Bhawan School Adzaan, Surat City, Navyuk College, Gujarat – 486331 Prior Environment Clearance for Stone Quarry in an area of 1.0 ha. (As per Mine Plan 48640 cum 1st Year after that 2939 Cum/Year) (Khasra No. 152/3), Village - Gujran, Tehsil - Mauganj, Dist. Rewa This case was discussed in 434th SEAC meeting dated 20.05.2020 and it was recorded that......

The case was presented by the PP and their consultant wherein as per Google image based on coordinates provided by PP, committee observed that the most parts of the lease is in close proximity of huge water body in the north side and nearby water channel in the eastern side of the lease. The proposed depth of mining is 18 meters in 1.00 ha land and possibility of water inundation can not be ruled out considering blasting for production of 48640 cum of stone. Thus, committee after deliberation recommends that this case can not be considered for grant EC and file may be sent to SEIAA for onward necessary action. As per above observation of SEAC, it has been decided to reject the case as EC can not be considered looking to environmental sensitivity. Copy to PP and all concerned. 49. Case No. 5529/17 Shri Raghav Chandak, 203, G Blockm Sri Ganga Nagar, Rajasthan Prior Environment Clearance for River Sand quarry in an area of 20.0 ha. (160000 cum per annum) (Khasra no. 181 part) at Village- Bhadaura , Tehsil - , Dist. Katni (MP) This case was discussed in 434th SEAC meeting dated 20.05.2020 and it was recorded that......

ToR Validity was up to 11.04.2020. Since PP neither submitted EIA report, case may be delisted.. As per above observation of SEAC, it has been decided to delist the case on the condition that if PP intends to present the case in SEIAA, it will then be relisted for appraisal. Copy to PP and all concerned. 50. Case No. 5533/17 M/s Shri Krishnadas Tikaram, Civil Line, Katni, MP Prior Environment Clearance for Bauxite and Fireclay Mine in an area of 1.04 ha. (5879 TPA) (Khasra no. 1193, 1194, 1195) at Village- Naikin , Tehsil - Rampur Naikin, Dist. Sidhi (MP) This case was discussed in 434th SEAC meeting dated 20.05.2020 and it was recorded that......

ToR Validity was up to 09.04.2020. Since PP neither submitted EIA report, case may be delisted. As per above observation of SEAC, it has been decided to delist the case on the condition that if PP intends to present the case in SEIAA, it will then be relisted for appraisal. Copy to PP and all concerned.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 12 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

51. Case No 7010/2020 M/s Ultimate Builders, G-2/G-17, Kamdhenu Tower, E-2/21, Arera Colony, Bhopal, MP Prior Environment Clearance for Proposed Housing Development Project "Ultimate English Vilas" (Total Land Area = 69851.60 sqm, Net Plot Area = 64971.95 sqm Total Built up Area = 86905.23 sqm) at Village - Borda, PH No. 29, Tehsil - Huzur, Kolar Road, Dist. Bhopal , (MP). This case was discussed in 434th SEAC meeting dated 20.05.2020, ToR recommended by SEAC is hereby approved 52. Case No 6872/2020 M/s Ujjwala Housing & Finance Pvt. Ltd, Shri Sunderlal Maran, Director, Aamra Vihar Colony, Near Aamra Vihar Bus Stop, Nayapura, Kolar Road, Dist. Bhopal, MP – 462042 Prior Environment Clearance for Construction of "AAMRA VALLEY" (Total Plot Area = 18,000.00 sqm, Total Built-up Area = 36,377.03 sqm) at Village - Sankhedi, Tehsil - Huzur, Dist. Bhopal, (MP). This case was discussed in 434th SEAC meeting dated 20.05.2020, ToR recommended by SEAC is hereby approved 53. Case No. – 6671/2019 Avneedra Singh, Division Project Engineer, Public Works Department Project Implementation Unit, Divisional Office, Chhindwara. Prior Environment Clearance for Proposed Development of CIMS Hospital and Other Allied Buildings, at Khasra No. 13/2, 14/2, 12, 1/3, 21, 10/13, 11/2, 11/4, ½, ¼, 13/1, 14/1, 18/2 & 19/2 Chhindwara MP, Total Land area – 2,42,524.94 Sq.m. (59.92 Acre) Total Built up area 2,95,174.0 Sq.M (FAR+Non FAR). Total Ground Coverage – 26337.37 Sq.m

This case was discussed in 434th SEAC meeting dated 20.05.2020, revised ToR recommended by SEAC is hereby approved 54. Case No 7012/2020 M/s Yashstar Stones Pvt. Ltd, Opp AM, 95 Bhagat Singh Nagar, DD Nagar, Dist. Gwalior, MP – 474020 Prior Environment Clearance for Stone Quarry in an area of 4.80 ha. (207584 cum per annum) (Khasra No. 1057, 1058, 1059, 1060, 1061, 1122/1, 1122/2, 1123/1, 1123/2), Village - Dirman, Tehsil - Gohad, Dist. Bhind (MP) This case was discussed in 434th SEAC meeting dated 20.05.2020, ToR recommended by SEAC is hereby approved 55. Case No. – 6546/2019 Ms. Sangeeta Gupta, R/o Village - Kabrai, Dist. Mahoba, UP – 210424. Prior Environment Clearance for Stone Quarry in an area of 1.80 ha. (81,56 cum per annum) (Khasra No. 151(P)), Village - Dhujaura, Tehsil - Gaurihar, Dist. Chhatarpur (MP) This case was discussed in 434th SEAC meeting dated 20.05.2020, revised ToR recommended by SEAC is hereby approved. 56. Case No. 7024/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 3.80 ha. (39710 cum per annum) (Khasra No. 01,), Village - Basi, Tehsil - , Dist. - (MP) by Shri Rajesh Pathak, Ward No. 15, Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 13 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory, as per revised surface plan now, available area for mining is 31,500 sq.m., with average depth of the area 1.5 meters, the total available volume for mining of sand is 47,250 m3. Hence, the desired quantity of sand is easily obtainable. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 4536 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of total Rs. 2.10 lakh/year under CER: 1st Year - Basi (~ 120): - Installation of a hand pump with proper drainage system at a

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 14 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

government land - Deepening and cleaning of two village common dug wells and construction of their parapets. - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

2nd Year - Bakera (~ 250): - Installation of a hand pump with proper drainage system at a government land - Establishment of a library in village school. - Repair and white wash of village school building including construction of its new toilet. - Deepening and cleaning of one village common dug well and construction of its parapet. - Deepening and cleaning of two nearby ponds managed by Panchayat - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

3rd Year - Narwanjpar (~ 100): - Installation of a hand pump with proper drainage system at a government land - Deepening and cleaning of two village common dug wells and construction of their parapets. - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

4th Year - Bodalkasa (~ 150): - Installation of a hand pump with proper drainage system at a government land - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 15 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

- Deepening and cleaning of one village common dug well and construction of its parapet. - Deepening and cleaning of two nearby ponds managed by Panchayat - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 3.80 ha. (39710 cum per annum) (Khasra No. 01,), Village - Basi, Tehsil - Waraseoni, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 57. Case No. 7038/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 4.90 ha. (44100 cum per annum) (Khasra No. 208,), Village - Gajpur, Tehsil - Khairlanji, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 16 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 5832 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 2.30 lakh/year under CER: 1st Year - Gajpur (~ 250): - Repair and whitewash of village Anganwadi building - Establishment of a library in village school including repair and white wash of village - School building in addition to construction of a new toilet. - Deepening and cleaning/desilting of a nearby pond managed by village Panchayat. - Installation of the earthen/clay water filter in village school - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

2nd Year - Panjra (~ 150): - Establishment of a library in village school including repair and white wash of village school building in addition to construction of its new toilet. - Installation of a hand pump with bore well and concreting around it for the proper drainage at a government land

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 17 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

- Repair and maintenance of village drainage system - Installation of the earthen/clay water filter in village school - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

3rd Year - Tateksha (~ 100): - Establishment of a library in village school including repair and white wash of school building in addition to Installation of the earthen/clay water filter - Deepening and cleaning of village common dug well and construction of parapet around it. - Repair and whitewash of village Anganwadi building - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

4th Year - Bahakal (~ 100): - Establishment of a library in village school including repair and white wash of village school building in addition to construction of a new toilet. - Installation of a hand pump with bore well and concreting around it for the proper drainage at a government land - Repair and maintenance of village drainage system - Installation of the earthen/clay water filter in village school - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 18 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 4.90 ha. (44100 cum per annum) (Khasra No. 208,), Village - Gajpur, Tehsil - Khairlanji, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 58. Case No. 7045/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 4.30 ha. (96750 cum per annum) (Khasra No. 457), Village - Jaramohgaon, Tehsil - , Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 5112 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 19 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 4.70 lakh/year under CER: 1st Year - Jaramohgaon (~ 300): - Development of smart classes and establishment of a library in a village school - Construction of hand pump in the village common area with bore well & concreting the surface with proper drainage - Erection of slides, seesaw at village school premises and distribution of sports kit in addition to repair and whitewash of school building - Deepening and cleaning of two ponds/reservoirs in the village - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of the grassland using prosobis seeds on a nearby suitable government land

2nd Year - Dorli (~ 100): - Development of smart classes and establishment of a library in a village school - Construction of hand pump in the village common area with bore well & concreting the surface with proper drainage - Erection of slides, seesaw at village school premises and distribution of sports kit in addition to repair and whitewash of school building - Deepening and cleaning of village common dug well and construction of parapet around it. - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of the grassland using prosobis seeds on a nearby suitable government land

3rd Year - Ansera (~ 200): - Development of smart classes and establishment of a library in a village school - Deepening and cleaning of two ponds/reservoirs in the village - Construction of hand pump in the village common area with bore well & concreting the surface with proper drainage - Erection of slides, seesaw at village school premises and

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 20 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

distribution of sports kit in addition to repair and whitewash of school building - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road)

4th Year - Gatapailli: - Development of smart classes and establishment of a library in a village school - Construction of hand pump in the village common area with bore well & concreting the surface with proper drainage - Erection of slides, seesaw at village school premises and distribution of sports kit in addition to repair and whitewash of school building - Deepening and cleaning of two ponds/reservoirs in the village - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of the grassland using prosobis seeds on a nearby suitable government land The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 4.30 ha. (96750 cum per annum) (Khasra No. 457), Village - Jaramohgaon, Tehsil - Katangi, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 59. Case No. 7046/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 4.50 ha. (64125 cum per annum) (Khasra No. 21), Village - Chandori, Tehsil - Waraseoni, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 21 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 5346 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 3.20 lakh/year under CER: 1st Year - Chandori (~ 150): - Development of smart class and Establishment of a library in village school. - Deepening and cleaning/desilting of a nearby pond managed by Panchayat.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 22 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

- -Repair and maintenance of village drainage system - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

2nd Year - Murjhad (~ 150): - Development of smart class and Establishment of a library in village school. - Repair and white wash of village school building and levelling of its playground - Conducting traffic awareness program (safety campaign on road) in consultation with - Repair of village road at selected points - Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

3rd Year - Khandwa (~ 150): - Development of smart class and Establishment of a library in village school. - Repair and white wash of village school building and levelling of its playground - Repair and maintenance of village drainage system - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

4th Year - Sikandra (~ 150): - Development of smart class and Establishment of a library in village school. - Repair and white wash of village school building and levelling of its playground - Conducting traffic awareness program (safety campaign on road) in consultation with - Repair of village road at selected points - Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land The modification to the above activities can be made with the permission of the district administration and need based activity for the

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 23 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 4.50 ha. (64125 cum per annum) (Khasra No. 21), Village - Chandori, Tehsil - Waraseoni, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 60. Case No. 7047/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 2.50 ha. (26125 cum per annum) (Khasra No. 185), Village - Kalgaon, Tehsil - Katangi, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 24 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 2970 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 1.35 lakh/year under CER: 1st Year - Kalgaon (~ 100): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Repair and maintenance of village drainage system - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

2nd Year - Bahakal (~ 100): - Establishment of a library in village school. - Installation of a hand pump with bore well and concreting around it for the proper drainage at a government land - Repair of village road at selected points - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

3rd Year - Arjuni (~ 100): - Distribution of the nutrients pulses & grains to the women/ mother through the village aanganwadi. - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Distribution of masks and sanitisers to villagers and conducting an

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 25 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

awareness program through Panchayat for the protection from the spread of Corona virus (COVID 19 Pandemic) - Development of grassland using prosobis seeds on a nearby suitable government land

4th Year - Atri (~ 100): - Establishment of a library in village school. - Installation of a hand pump with bore well and concreting around it for the proper drainage at a government land - Repair of village road at selected points - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 2.50 ha. (26125 cum per annum) (Khasra No. 185), Village - Kalgaon, Tehsil - Katangi, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 61. Case No. 7048/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 4.0 ha. (41800 cum per annum) (Khasra No. 625), Village - Sawangi, Tehsil - Waraseoni, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’:

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 26 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 4752 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 2.0 lakh/year under CER: 1st Year - Sawangi (~ 100): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet and installation of earthen/clay water filter. - Repair of village road at selected points - Installation of a hand pump with bore well and concreting around it for the proper drainage at a government land - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 27 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

2nd Year - Sarandi (~ 150): - Establishment of a library in village school. - Deepening and cleaning/desilting of the village pond/reservoir - Repair and white wash of village school building including construction of a new toilet. - Repair and maintenance of village drainage system - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

3rd Year - Lohara (~ 100): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet and installation of earthen/clay water filter. - Repair of village road at selected points - Installation of a hand pump with bore well and concreting around it for the proper drainage at a government land - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

4th Year - Tekdi (~ 150): - Establishment of a library in village school. - Deepening and cleaning/desilting of the village pond/reservoir - Repair and white wash of village school building including construction of a new toilet. - Repair and maintenance of village drainage system - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 28 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 4.0 ha. (41800 cum per annum) (Khasra No. 625), Village - Sawangi, Tehsil - Waraseoni, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 62. Case No. 7049/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 4.50 ha. (68400 cum per annum) (Khasra No. 332/1), Village - Temni, Tehsil - Khairlanji, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory , as per revised surface plan now, available area for mining is 18,600 sq.m. so as per average depth of the area 1.6 meters, the total available volume for mining of sand is reduced to 29,760 m3. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 29 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

IX. Total 5364 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 3.45 lakh/year under CER: 1st Year - Temni (~ 100): - Development of smart classes and establishment of a library in a village school - Construction of hand pump with proper drainage system in the village common area with bore well & concreting the surface with proper drainage - Repair and maintenance of village drainage system - Distribution of sports kit in addition to repair and whitewash of school building - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of grassland using prosobis seeds on a nearby suitable government land

2nd Year - Bhougarh (~ 300): - Development of smart classes and establishment of a library in a village school - Construction of hand pump with proper drainage system in the village common area with bore well & concreting the surface with proper drainage - Repair of village road at selected points - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of grassland using prosobis seeds on a nearby suitable government land

3rd Year - Khairi (~ 250): - Development of smart classes and establishment of a library in a village school - Construction of hand pump with proper drainage system in the village common area with bore well & concreting the surface with proper drainage

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 30 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

- Repair and maintenance of village drainage system - Distribution of sports kit in addition to repair and whitewash of school building - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of grassland using prosobis seeds on a nearby suitable government land

4th Year - Khairlani (~ 200): - Development of smart classes and establishment of a library in a village school - Construction of hand pump with proper drainage system in the village common area with bore well & concreting the surface with proper drainage - Repair of village road at selected points - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of grassland using prosobis seeds on a nearby suitable government land The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 4.50 ha. (68400 cum per annum) (Khasra No. 332/1), Village - Temni, Tehsil - Khairlanji, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 63. Case No. 7050/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 4.0 ha. (41800 cum per annum) (Khasra No. 442/1), Village - Seoni, Tehsil - Waraseoni, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 31 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory , as per revised surface plan now, available area for mining is 36,500 sq.m. so as per average depth of the area 1.1 meters, the total available volume for mining of sand is reduced to 40,150 m3. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 4752 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 2.0 lakh/year under CER: 1st Year - Seoni (> 350): - Establishment of a library in village school. - Repair and white wash of village school building including

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 32 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

construction of a new toilet. - Deepening and cleaning of two nearby ponds managed by Panchayat - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

2nd Year - Sikandra (~ 100): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Installation of a hand pump with bore well at a government land - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

3rd Year - Seoni (~ 350): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Deepening and cleaning of two nearby ponds managed by Panchayat - Repair and maintenance of village drainage system - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

4th Year - baraseoni (~ 250): - Repair and white wash of village school building including construction of a new toilet. - Installation of a hand pump with proper drainage system at a government land - Conducting traffic awareness program (safety campaign on road) in consultation with Gram - Repair of village road at selected points - Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land The modification to the above activities can be made with the permission of the district administration and need based activity for the

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 33 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 4.0 ha. (41800 cum per annum) (Khasra No. 442/1), Village - Seoni, Tehsil - Waraseoni, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 64. Case No. 7051/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 3.50 ha. (69825 cum per annum) (Khasra No. 735), Village - Kauliwada, Tehsil - Waraseoni, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 34 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 4158 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 3.45 lakh/year under CER: 1st Year - Kauliwada (~ 100): - Distribution of Pulses to mothers through Aaganbadi. - Development of smart classes and establishment of a library in a village school - Construction of hand pump in the village common area with bore well & concreting the surface with proper drainage - Repair and white wash of village school building including construction of a new toilet. - Distribution of sports kit in addition to repair and whitewash of school building - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of grassland using prosobis seeds on a nearby suitable government land

2nd Year - Murdada (~ 300): - Development of smart classes and establishment of a library in a village school - Deepening and cleaning of village common dug well and construction of its parapet as needed around them at each village - Repair of village road at selected points - Distribution of sports kit in addition to repair and whitewash of school building - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of grassland using prosobis seeds on a nearby

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 35 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

suitable government land

3rd Year - Ghoti (~ 200): - Distribution of Pulses to mothers through Aaganbadi. - Development of smart classes and establishment of a library in a village school - Construction of hand pump in the village common area with bore well & concreting the surface with proper drainage - Repair and white wash of village school building including construction of a new toilet. - Distribution of sports kit in addition to repair and whitewash of school building - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of grassland using prosobis seeds on a nearby suitable government land

4th Year - Sonawani (~ 200): - Development of smart classes and establishment of a library in a village school - Deepening and cleaning of village common dug well and construction of its parapet as needed around them at each village - Repair of village road at selected points - Distribution of sports kit in addition to repair and whitewash of school building - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of grassland using prosobis seeds on a nearby suitable government land The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 36 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 3.50 ha. (69825 cum per annum) (Khasra No. 735), Village - Kauliwada, Tehsil - Waraseoni, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 65. Case No. 7053/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 4.480 ha. (63840 cum per annum) (Khasra No. 456), Village - Hardoli, Tehsil –, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 5328 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 37 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 3.20 lakh/year under CER: 1st Year - Hardouli (~ 150): - Development of smart classes and establishment of a library in a village school - Distribution of sports kit in addition to repair and whitewash of school building - Repair and white wash of village school building including construction of a new toilet. - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of grassland using prosobis seeds on a nearby suitable government land

2nd Year - Chitewani (~ 250): - Development of smart classes and establishment of a library in a village school - Deepening and cleaning/desilting of village pond - Repair of village road at selected points - Distribution of sports kit in addition to repair and whitewash of school building - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of grassland using prosobis seeds on a nearby suitable government land

3rd Year - Pathari (~ 200): - Development of smart classes and establishment of a library in a village school - Distribution of sports kit in addition to repair and whitewash of school building - Repair and white wash of village school building including construction of a new toilet. - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 38 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of grassland using prosobis seeds on a nearby suitable government land

4th Year - wanhani (~ 250): - Development of smart classes and establishment of a library in a village school - Deepening and cleaning/desilting of village pond - Repair of village road at selected points - Distribution of sports kit in addition to repair and whitewash of school building - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of grassland using prosobis seeds on a nearby suitable government land The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 4.480 ha. (63840 cum per annum) (Khasra No. 456), Village - Hardoli, Tehsil –Tirodi, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 66. Case No. 7054/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 4.806 ha. (68485 cum per annum) (Khasra No. 05), Village - Chichgaon, Tehsil - Khairlanji, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 39 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

satisfactory , as per revised surface plan now, available area for mining is 47,660 sq.m. so as per average depth of the area 1.5 meters, the total available volume for mining of sand is 71,490 m3. Hence, the desired quantity of sand is easily obtainable. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 5724 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 3.40 lakh/year under CER: 1st Year - Chichgaon (~ 150): - Distribution of Pulses to mothers through Aaganbadi. - Development of smart classes and establishment of a library in a village school - Construction of hand pump in the village common area with bore well & concreting the surface with proper drainage - Distribution of sports kit in addition to repair and whitewash of

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 40 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

school building - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Distribution of masks and sanitisers to villagers and conducting an awareness program through Panchayat for the protection from the spread of Corona virus (COVID 19 Pandemic) - Development of grassland using prosobis seeds on a nearby suitable government land

2nd Year - Satona (~ 100): - Distribution of Pulses to mothers through Aaganbadi. - Development of smart classes and establishment of a library in a village school - Construction of hand pump in the village common area with bore well & concreting the surface with proper drainage - Distribution of sports kit in addition to repair and whitewash of school building - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Distribution of masks and sanitisers to villagers and conducting an awareness program through Panchayat for the protection from the spread of Corona virus (COVID 19 Pandemic) - Development of grassland using prosobis seeds on a nearby suitable government land

3rd Year - Khara (~ 250): - Development of smart classes and establishment of a library in a village school - Deepening and cleaning/desilting of village ponds - Distribution of sports kit in addition to repair and whitewash of school building - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Distribution of masks and sanitisers to villagers and conducting an awareness program through Panchayat for the protection from the spread of Corona virus (COVID 19 Pandemic) - Development of grassland using prosobis seeds on a nearby suitable government land

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 41 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 4.806 ha. (68485 cum per annum) (Khasra No. 05), Village - Chichgaon, Tehsil - Khairlanji, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 67. Case No. 7055/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 3.0 ha. (28673 cum per annum) (Khasra No. 144), Village - Dhapewada, Tehsil - Balaghat, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory , as per revised surface plan now, available area for mining is 18,200 sq.m. so as per average depth of the area 2.0 meters, the total available volume for mining of sand is 36,400 m3. Hence, the desired quantity of sand is easily obtainable. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 42 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 3564 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 1.60 lakh/year under CER: 1st Year - Dhapewada (~ 150): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Repair of village road at selected points - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

2nd Year - Kumhari (~ 200): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Conducting traffic awareness program (safety campaign on road) in consultation - Development of grassland using prosobis seeds on a nearby suitable government land at both villages

3rd Year - & Dhapera (~ 200): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Repair of village road at selected points - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 43 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

4th Year - Patharwada (~ 200): - Establishment of a library in village school. - Repair and white wash of village school building including construction of its new toilet at Kumhari - Repair and white wash of village school building including construction of a new toilet. - Conducting traffic awareness program (safety campaign on road) in consultation - Development of grassland using prosobis seeds on a nearby suitable government land at both villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 3.0 ha. (28673 cum per annum) (Khasra No. 144), Village - Dhapewada, Tehsil - Balaghat, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 68. Case No. 7056/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 4.90 ha. (29697 cum per annum) (Khasra No. 397), Village - Dadia, Tehsil – , Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory , as per revised surface plan now, available area for mining is 20,000 sq.m. so as per average depth of the area 1.5 meters, the total available volume for mining of sand is 30,000 m3. Hence, the desired quantity of sand is easily obtainable. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 44 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 5832 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 1.60 lakh/year under CER: 1st Year - Dadia (~ 120): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land.

2nd Year - (~ 200):

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 45 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

- Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

3rd Year - Khamghat & Orma (~ 150): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Repair and white wash of village school building including construction of its new toilet. - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

4th Year - Dorli (~ 200): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Repair of village road at selected points - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 4.90 ha. (29697 cum per annum) (Khasra No. 397), Village - Dadia, Tehsil – Lalbarra, Dist. - Balaghat (MP) for the lease

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 46 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 69. Case No. 7057/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 4.50 ha. (51300 cum per annum) (Khasra No. 12), Village - Gunai, Tehsil - Khairlanji, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 5364 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 47 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

XII. PP must ensure the implementation of following activities with separate budget provision of total Rs. 2.50 lakh/year under CER: 1st Year - Gunai (~ 100): - Development of smart class in the village school. - Repair and white wash of village school building. - Repair of village road at selected points - Installation of a hand pump with bore well at a government land - Distribution of helmets to villagers and traffic signage for encouraging safe driving campaign via Gram Panchayat - Installation of earthen water filter in village primary school - Development of the grassland on a suitable nearby government land.

2nd Year - Ghoti (~ 100): - Construction of the Yatri Shed in the village with sitting facility at Panjra - Installation of one hand pump each with bore wells at a government land in each village - Repair and maintenance of village drainage system - Deepening and cleaning of village common dug well and construction of its parapet as needed around them at each village - Distribution of helmets to villagers and traffic signage for encouraging safe driving campaign via at each Gram Panchayat - Installation of the earthen water filter in village primary school in both village - Development of the grassland on a suitable nearby government land in both villages

3rd Year - Lavani & Futara (~ 180): - Development of smart class in the village school. - Repair and white wash of village school building. - Repair of village road at selected points - Installation of a hand pump with bore well at a government land - Distribution of helmets to villagers and traffic signage for encouraging safe driving campaign via Gram Panchayat - Installation of earthen water filter in village primary school - Development of the grassland on a suitable nearby government land.

4th Year - Chutia (~ 100): - Construction of the Yatri Shed in the village with sitting facility at Panjra - Installation of one hand pump each with bore wells at a government land in each village - Repair and maintenance of village drainage system - Deepening and cleaning of village common dug well and construction of its parapet as needed around them at each village

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 48 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

- Distribution of helmets to villagers and traffic signage for encouraging safe driving campaign via at each Gram Panchayat - Installation of the earthen water filter in village primary school in both village - Development of the grassland on a suitable nearby government land in both villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 4.50 ha. (51300 cum per annum) (Khasra No. 12), Village - Gunai, Tehsil - Khairlanji, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 70. Case No. 7058/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 4.0 ha. (54000 cum per annum) (Khasra No. 455), Village - Atri, Tehsil - Khairlanji, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory , as per revised surface plan now, available area for mining is 32,000 sq.m. so as per average depth of the area 2.0 meters, the total available volume for mining of sand is 64,000 m3. Hence, the desired quantity of sand is easily obtainable. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 49 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 4752 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 2.70 lakh/ year under CER: 1st Year - Atri (~ 200): - Development of smart class and establishment of a library in village school. - Repair and maintenance of village drainage system - Repair and white wash of village school building including construction of a new toilet. - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

2nd Year - Khursipar (~ 250): - Development of smart class and establishment of a library in village school. - Deepening and cleaning of pond/reservoir in the village. - Repair of village road at selected points - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 50 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

- Development of grassland using prosobis seeds on a nearby suitable government land

3rd Year - Aramba (~ 250): - Development of smart class and establishment of a library in village school. - Repair and maintenance of village drainage system - Repair and white wash of village school building including construction of a new toilet. - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

4th Year - Katangi (~ 150): - Development of smart class and establishment of a library in village school. - Deepening and cleaning of pond/reservoir in the village. - Repair of village road at selected points - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 4.0 ha. (54000 cum per annum) (Khasra No. 455), Village - Atri, Tehsil - Khairlanji, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 71. Case No. 7059/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 1.328 ha. (25232 cum per annum) (Khasra No. 1/1), Village - , Tehsil - Balaghat, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 51 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 1584 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 1.35 lakh/year under CER: 1st Year - Bhamodi (~ 100): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Repair and maintenance of village drainage system

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 52 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

- Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

2nd Year - Hudkitola (~ 150): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Repair of village road at selected points - Development of grassland using prosobis seeds on a nearby suitable government land

3rd Year - Jagpur (~ 100): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Repair and maintenance of village drainage system - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

4th Year - Pipariya (~ 150): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Repair of village road at selected points - Development of grassland using prosobis seeds on a nearby suitable government land The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 53 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 1.328 ha. (25232 cum per annum) (Khasra No. 1/1), Village - Bhamodi, Tehsil - Balaghat, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 72. Case No. 7060/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 4.50 ha. (51300 cum per annum) (Khasra No. 164), Village - Kesha, Tehsil - Kirnapur, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory , as per revised surface plan now, available area for mining is 24,000 sq.m. so as per average depth of the area 1.5 meters, the total available volume for mining of sand is reduced to 36,000 m3. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 54 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

IX. Total 5364 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 2.60 lakh/year under CER: 1st Year - Kesha (~ 150): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Deepening and cleaning of two nearby ponds managed by Panchayat - Repair and maintenance of village drainage system - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

2nd Year - Datt (~ 150): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Repair of village road at selected points - Deepening and cleaning common village dugwell and construction of parapet around it - Conducting traffic awareness program (safety campaign on road) in consultation with - Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

3rd Year - Rattapayali (~ 150): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Deepening and cleaning of two nearby ponds managed by Panchayat - Repair and maintenance of village drainage system - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 55 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

suitable government land

4th Year - Murri (~ 200): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Repair of village road at selected points - Deepening and cleaning common village dugwell and construction of parapet around it - Conducting traffic awareness program (safety campaign on road) in consultation with - Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 4.50 ha. (51300 cum per annum) (Khasra No. 164), Village - Kesha, Tehsil - Kirnapur, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 73. Case No. 7061/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 3.220 ha. (45885 cum per annum) (Khasra No. 45), Village - Barkheda, Tehsil - Balaghat, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’:

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 56 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 3852 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 2.30 lakh/year under CER: 1st Year - Barkheda (~ 100): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Deepening and cleaning of a pond managed by Panchayat - Repair of village road at selected points - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

2nd Year - Mohgaon (~ 150): - Establishment of a library in village school.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 57 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

- Repair and white wash of village school building including construction of a new toilet. - Deepening and cleaning of a pond managed by Panchayat - Repair and maintenance of village drainage system - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

3rd Year - Thakurtola (< 100): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Deepening and cleaning of a pond managed by Panchayat - Repair of village road at selected points - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

4th Year - Khairgaon (~ 150): - Establishment of a library in village school. - Repair and white wash of village school building including construction of a new toilet. - Deepening and cleaning of a pond managed by Panchayat - Repair and maintenance of village drainage system - Conducting traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 3.220 ha. (45885 cum per annum) (Khasra No.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 58 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

45), Village - Barkheda, Tehsil - Balaghat, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 74. Case No. 7063/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 3.80 ha. (78300 cum per annum) (Khasra No. 434), Village - Gatapayali, Tehsil - Waraseoni, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory , as per revised surface plan now, available area for mining is 25,000 sq.m. so as per average depth of the area 2.5 meters, the total available volume for mining of sand is reduced to 62,500 m3. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 4536 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 59 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 3.80 lakh/year under CER: 1st Year - Gatapayali (~ 150): - Development of smart classes and establishment of a library in a village school - Construction of hand pump in the village common area with bore well & concreting the surface with proper drainage - Distribution of sports kit in addition to repairing and whitewash of school building - Repairing of village road at selected points - To conduct traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of grassland using prosobis seeds on a nearby suitable government land

2nd Year - Ansera (~ 100): - Development of smart classes and establishment of a library in a village school - Construction of hand pump in the village common area with bore well & concreting the surface with proper drainage - Distribution of sports kit in addition to repairing and whitewash of school building - To conduct traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Repairing and maintenance of village drainage system - Distribution of masks and sanitizers to villagers and conducting an awareness program - Development of the grassland on a suitable nearby government land in both villages

3rd Year - Dorli (~ 250): - Development of smart classes and establishment of a library in a village school - Construction of hand pump in the village common area with bore well & concreting the surface with proper drainage - Distribution of sports kit in addition to repair and whitewash of school building - Repair of village road at selected points

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 60 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

- Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of grassland using prosobis seeds on a nearby suitable government land

4th Year - Narwanjapar (~ 100): - Development of smart classes and establishment of a library in a village school - Construction of hand pump in the village common area with bore well & concreting the surface with proper drainage - Distribution of sports kit in addition to repair and whitewash of school building - Conducting traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Repair and maintenance of village drainage system - Distribution of masks and sanitisers to villagers and conducting an awareness program through - Development of the grassland on a suitable nearby government land in both villages The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 3.80 ha. (78300 cum per annum) (Khasra No. 434), Village - Gatapayali, Tehsil - Waraseoni, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 61 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

75. Case No. 7064/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 4.920 ha. (110700 cum per annum) (Khasra No. 795), Village - Sawari, Tehsil - Khairlanji, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 5868 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 5.40 lakh/year under CER:

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 62 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

1st Year - Sawari (~ 150): - Development of smart classes and establishment of a library in a village school - Construction of hand pump in village common area with bore well & concreting of surface with proper drainage - Erection of slides, seesaw at village school premises and distribution of sports kit in addition to repair and whitewash of school building - Repairing of village road at selected points - Deepening and cleaning of two ponds/reservoirs in the village - To conduct traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of the grassland using prosobis seeds on a nearby suitable government land

2nd Year - Murdada (~ 100): - Development of smart classes and establishment of a library in a village school - Construction of hand pump in village common area with bore well & concreting of surface with proper drainage - Erection of slides, seesaw at village school premises and distribution of sports kit in addition to repair and whitewash of school building - Repairing of village road at selected points - Deepening and cleaning of two ponds/reservoirs in the village - To conduct traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of the grassland using prosobis seeds on a nearby suitable government land

3rd Year - Kindgipar (~ 100): - Development of smart classes and establishment of a library in a village school - Construction of hand pump in village common area with bore well & concreting of surface with proper drainage - Erection of slides, seesaw at village school premises and distribution of sports kit in addition to repair and whitewash of school building - Repairing of village road at selected points - Deepening and cleaning of two ponds/reservoirs in the village - To conduct traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 63 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of the grassland using prosobis seeds on a nearby suitable government land

4th Year - Mahalgaon (~ 200): - Development of smart classes and establishment of a library in a village school - Construction of hand pump in village common area with bore well & concreting of surface with proper drainage - Erection of slides, seesaw at village school premises and distribution of sports kit in addition to repair and whitewash of school building - Repairing of village road at selected points - Deepening and cleaning of two ponds/reservoirs in the village - To conduct traffic awareness program (safety campaign on road) with briefing on PUC vehicles in combating the pollution in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers through Panchayat (under safety campaign on road) - Development of the grassland using prosobis seeds on a nearby suitable government land The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 4.920 ha. (110700 cum per annum) (Khasra No. 795), Village - Sawari, Tehsil - Khairlanji, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 76. Case No. 7065/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 4.90 ha. (44895 cum per annum) (Khasra No. 117), Village - Kaudiya, Tehsil - Lalbarra, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 64 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory , as per revised surface plan now, available area for mining is 27,000 sq.m. so as per average depth of the area 1.0 meters, the total available volume for mining of sand is reduced to 27,000 m3. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 5832 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 2.40 lakh/year under CER: 1st Year - Kaudiya (~ 100): - Establishment of a library in village school. - Repairing and white wash of village school building including

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 65 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

construction of a new toilet. - Installation of a hand pump with bore well at a government land. - To conduct traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers. - Development of grassland using prosobis seeds on a nearby suitable government land.

2nd Year - Newargaon (~ 100): - Establishment of a library in village school. - Repairing and white wash of village school building including construction of a new toilet. - Deepening and cleaning/desilting of a small pond in the village for better storage of water. - To conduct traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers. - Development of grassland using prosobis seeds on a nearby suitable government land.

3rd Year - Roshna (~ 100): - Establishment of a library in village school. - Repairing and white wash of village school building including construction of a new toilet. - Repairing of village road at selected points - Installation of a hand pump with bore well at government land - To conduct traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land

4th Year - Chutia (~ 150): - Establishment of a library in village school. - Repairing and white wash of village school building including construction of a new toilet. - Repairing and maintenance of village drainage system - Deepening and cleaning/desilting of a small pond in the village for better storage of water - To conduct traffic awareness program (safety campaign on road) in consultation with Gram Panchayat and local Authority and distribution of helmets to selected villagers - Development of grassland using prosobis seeds on a nearby suitable government land The modification to the above activities can be made with the permission of the district administration and need based activity for the

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 66 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 4.90 ha. (44895 cum per annum) (Khasra No. 117), Village - Kaudiya, Tehsil - Lalbarra, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 77. Case No. 7020/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 4.80 ha. (80352 cum per annum) (Khasra No. 326,), Village - Mehandiwada, Tehsil - Waraseoni, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 67 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 6912 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 2.10 lakh/year under CER: a) SC/ST hostels or in nomadic tribes’ hostels. b) Pipes for water supply to household those are not having any water supply. c) Plantation program on a single land piece as suggested by Gram Panchayat as well as collector in the coming 2 year. d) Basic facilities to Primary Health Centres. e) Wall and roof repairing in Schools as well as repairing of damaged furniture like tables and chairs. f) Common infrastructure upgradation as suggested by Gram Panchayat as well as the Collector. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 4.80 ha. (80352 cum per annum) (Khasra No. 326,), Village - Mehandiwada, Tehsil - Waraseoni, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 68 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

78. Case No. 7021/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 3.239 ha. (21540 cum per annum) (Khasra No. 01, 231, 255,), Village - Bahkal, Tehsil - Katangi, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 4656 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 1.80 lakh/year under CER:

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 69 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

a) SC/ST hostels or in nomadic tribes’ hostels. b) Pipes for water supply to household those are not having any water supply. c) Plantation program on a single land piece as suggested by Gram Panchayat as well as collector in the coming 2 year. d) Basic facilities to Primary Health Centres. e) Wall and roof repairing in Schools as well as repairing of damaged furniture like tables and chairs. f) Common infrastructure upgradation as suggested by Gram Panchayat as well as the Collector. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 3.239 ha. (21540 cum per annum) (Khasra No. 01, 231, 255,), Village - Bahkal, Tehsil - Katangi, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 79. Case No. 7022/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 2.90 ha. (30305 cum per annum) (Khasra No. 1/1), Village - Ghoti, Tehsil - Khairlanji, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 70 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 4080 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 1.50 lakh/year under CER: a) SC/ST hostels or in nomadic tribes’ hostels. b) Pipes for water supply to household those are not having any water supply. c) Plantation program on a single land piece as suggested by Gram Panchayat as well as collector in the coming 2 year. d) Basic facilities to Primary Health Centres. e) Wall and roof repairing in Schools as well as repairing of damaged furniture like tables and chairs. f) Common infrastructure upgradation as suggested by Gram Panchayat as well as the Collector. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 71 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 2.90 ha. (30305 cum per annum) (Khasra No. 1/1), Village - Ghoti, Tehsil - Khairlanji, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 80. Case No. 7089/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 4.50 ha. (47025 cum per annum) (Khasra No. 1), Village - Roshna, Tehsil - Balaghat, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 72 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 6480 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 1.80 lakh/year under CER: a) SC/ST hostels or in nomadic tribes’ hostels. b) Pipes for water supply to household those are not having any water supply. c) Plantation program on a single land piece as suggested by Gram Panchayat as well as collector in the coming 2 year. d) Basic facilities to Primary Health Centres. e) Wall and roof repairing in Schools as well as repairing of damaged furniture like tables and chairs. f) Common infrastructure upgradation as suggested by Gram Panchayat as well as the Collector. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 4.50 ha. (47025 cum per annum) (Khasra No. 1), Village - Roshna, Tehsil - Balaghat, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 81. Case No. 7090/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 2.0 ha. (28500 cum per annum) (Khasra No. 957), Village - Dhapera, Tehsil - Lalbarra, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 73 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 2880 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 1.50 lakh/year under CER: a) SC/ST hostels or in nomadic tribes’ hostels. b) Pipes for water supply to household those are not having any water supply. c) Plantation program on a single land piece as suggested by Gram Panchayat as well as collector in the coming 2 year.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 74 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

d) Basic facilities to Primary Health Centres. e) Wall and roof repairing in Schools as well as repairing of damaged furniture like tables and chairs. f) Common infrastructure upgradation as suggested by Gram Panchayat as well as the Collector. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 2.0 ha. (28500 cum per annum) (Khasra No. 957), Village - Dhapera, Tehsil - Lalbarra, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 82. Case No. 7091/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 1.0 ha. (26600 cum per annum) (Khasra No. 1), Village - Magardarra, Tehsil - Balaghat, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 75 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 1440 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 2.10 lakh/year under CER: a) SC/ST hostels or in nomadic tribes’ hostels. b) Pipes for water supply to household those are not having any water supply. c) Plantation program on a single land piece as suggested by Gram Panchayat as well as collector in the coming 2 year. d) Basic facilities to Primary Health Centres. e) Wall and roof repairing in Schools as well as repairing of damaged furniture like tables and chairs. f) Common infrastructure upgradation as suggested by Gram Panchayat as well as the Collector. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 76 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 1.0 ha. (26600 cum per annum) (Khasra No. 1), Village - Magardarra, Tehsil - Balaghat, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 83. Case No. 7092/2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 2.0 ha. (19000 cum per annum) (Khasra No. 207), Village - Bhalewada, Tehsil - Balaghat, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’: PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 2880 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 77 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 1.50 lakh/year under CER: a) SC/ST hostels or in nomadic tribes’ hostels. b) Pipes for water supply to household those are not having any water supply. c) Plantation program on a single land piece as suggested by Gram Panchayat as well as collector in the coming 2 year. d) Basic facilities to Primary Health Centres. e) Wall and roof repairing in Schools as well as repairing of damaged furniture like tables and chairs. f) Common infrastructure upgradation as suggested by Gram Panchayat as well as the Collector. The modification to the above activities can be made with the permission of the district administration and need based activity for the development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 2.0 ha. (19000 cum per annum) (Khasra No. 207), Village - Bhalewada, Tehsil - Balaghat, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 84. Case No. 7093 /2020: Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 1.011 ha. (10450 cum per annum) (Khasra No. 01), Village - Salhe, Tehsil - Lalbarra, Dist. - Balaghat (MP) by Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. This case was recommended in 435th SEAC meeting dated 29.05.2020 and it was recorded that......

“------PP has submitted the response of above quarries same date vide letter dated 29.05.2020, which was placed before the committee and the same found satisfactory. The EMP and other submissions made by the PP were found to be satisfactory and acceptable, hence committee decided to recommend the case for grant of prior EC subject to the following special conditions in addition to the standard conditions at annexure ‘B’:

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 78 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

PP/Consultant made a presentation on all aspects of the project and all concerned issues were discussed in detail. After detailed discussions and perusal of recommendations of 435th SEAC meeting dated 29.05.2020, presentation made by the PP in SEIAA, it was decided to accept the recommendation of SEAC for grant of prior EC to the project subject to the following specific conditions:-

I. PP shall not start mining activity before execution of lease agreement. II. The production capacity shall be limited to the quantity as recommended by SEAC. III. No ramp will be allowed within the river basin to transport sand to the other bank. Transportation will be allowed on the bank side where the mineral is being excavated. IV. The entire lease area should be properly fenced and boundary stones marked at the site. V. No in-stream mining shall be allowed. The local authorities should ensure that the mining activity is confined only in the dry portion where sand is exposed. VI. The depth of the pit shall be as per Approved Mining Plan. VII. No transportation shall be permitted within the village. VIII. Alternate transportation route should be decided in consultation with the local Gram Panchayat. IX. Total 1236 saplings shall be planted in first three years under plantation programme in consultation with DM at identified revenue land of the district. PP shall also explore and identify the chunk of land in the area from revenue record to carry out plantation programme as proposed. X. Over loading will be strictly prohibited. XI. Water sprinkling will be done on the approach road on the regular basis. XII. PP must ensure the implementation of following activities with separate budget provision of Rs. 1.50 lakh/year under CER: a) SC/ST hostels or in nomadic tribes’ hostels. b) Pipes for water supply to household those are not having any water supply. c) Plantation program on a single land piece as suggested by Gram Panchayat as well as collector in the coming 2 year. d) Basic facilities to Primary Health Centres. e) Wall and roof repairing in Schools as well as repairing of damaged furniture like tables and chairs. f) Common infrastructure upgradation as suggested by Gram Panchayat as well as the Collector. The modification to the above activities can be made with the permission of the district administration and need based activity for the

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 79 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

development of nearby villages shall be implemented by PP in consultation with the District Collector and Gram Panchayat. XIII. PP should ensure to submit half yearly compliance report, Plantation and CER activity report along with photographs of all activities in MP-SEIAA. If PP is failed to upload or submit two consecutive half yearly compliance reports of EC conditions to concerned authority (SEIAA and Regional Office, MoEF&CC,GoI,Bhopal) than prior environmental clearance issued to PP will automatically be treated as cancelled/ revoked as per OM No. 930/SEIAA/2019 dated 30.05.2019 issued by MPSEIAA. Hence, Prior Environmental Clearance is granted for Sand Quarry (Opencast Manual Method) in an area of 1.011 ha. (10450 cum per annum) (Khasra No. 01), Village - Salhe, Tehsil - Lalbarra, Dist. - Balaghat (MP) for the lease period to Shri Rajesh Pathak, Ward No. 15, Baihar Road, Dist. - Balaghat, MP - 481331, Email – [email protected], Mobile – 7987236307. 85. Case No.6940/2020:- Prior Environmental Clearance for Sand Quarry (Open cast manual method) in an area of 4.00 ha. for production capacity of 46000 cum/year at Khasra No. 49 at Village- Bhasunda, Tehsil - Maheswar, Dist. Khargone (MP) by M.P. State Mining Corporation Ltd., Shri Rajeev Saxena, OIC, Sub Off.-Dhamnod, Tehsil-Dharampuri, Dhar (MP)-454552. - Regarding transfer of EC in the name of R.K.Gupta Contractors and Engineers Private Ltd. Shri Rajendra Kumar Gupta ,B-72, Shahpura Bhopal,M.P – 462039.. (1) It was noted that the PP had applied in Form-IM in DEIAA (Case no. 26/2016) for Prior Environmental Clearance of 4.00 ha. for production capacity of 46000 cum/year at Khasra No. 49 at Village- Bhasunda, Tehsil - Maheswar, Dist. Khargone (MP) by M.P. State Mining Corporation Ltd., Shri Rajeev Saxena, OIC, Sub Off.-Dhamnod, Tehsil-Dharampuri, Dhar (MP)-454552.. (2) The Prior Environmental Clearance letter was issued DEIAA vide L.No. 09/DEIAA/2016 dated 30.05.2016 in the name M.P. State Mining Corporation Ltd., Shri Rajeev Saxena, OIC, Sub Off.-Dhamnod, Tehsil- Dharampuri, Dhar (MP)-454552." (3) It is noted that PP has requested vide .L no nil dtd. 04.03.2020 received in SEIAA Office dtd. 06.03.2020 to make amendment in the Prior EC letter by changing the name of PP of the mining project namely " R.K.Gupta Contractors and Engineers Private Ltd. Shri Rajendra Kumar Gupta ,B- 72, Shahpura Bhopal,M.P – 462039 in place of M.P. State Mining Corporation Ltd., Shri Rajeev Saxena, OIC, Sub Off.-Dhamnod, Tehsil- Dharampuri, Dhar (MP)-454552.. (4) It is noted that in support of his request the PP has submitted the following documents i. No objection letter of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of R.K.Gupta Contractors and Engineers Private Ltd. Shri Rajendra Kumar Gupta ,B-72, Shahpura Bhopal,M.P – 462039.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 80 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

ii. Notarised affidavit of Shri Sanjeev Gadkari, OIC, M.P. State Mining Corporation Ltd." mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued. iii. Copy of Prior EC issued by DEIAA, vide L.No. 09 DEIAA/2016 dated 30.05.2016 in the name of M.P. State Mining Corporation Ltd., Shri Rajeev Saxena, OIC, Sub Off.-Dhamnod, Tehsil-Dharampuri, Dhar (MP)-454552. iv. Copy of Environmental Management Plan of R.K.Gupta Contractors and Engineers Private Ltd. Shri Rajendra Kumar Gupta ,B-72, Shahpura Bhopal,M.P – 462039 v. Copy of Mining Plan & Replenishment Plan transfered to R.K.Gupta Contractors and Engineers Private Ltd. Shri Rajendra Kumar Gupta ,B-72, Shahpura Bhopal,M.P – 462039. vi. Lease transfer order issued by Mineral Resource Department order to R.K.Gupta Contractors and Engineers Private Ltd. Shri Rajendra Kumar Gupta ,B-72, Shahpura Bhopal,M.P – 462039 vide letter No. 871/132/2020/12/1 dated 17.02.2020. (5) It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC. Para-11 :- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases. In context of above it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued by DEIAA, (Case no. 26/2016) Khargone on 30.05.2016 in the name of " M.P. State Mining Corporation Ltd., Shri Rajeev Saxena, OIC, Sub Off.- Dhamnod, Tehsil-Dharampuri, Dhar (MP)-454552." is hereby transferred to “R.K.Gupta Contractors and Engineers Private Ltd. Shri Rajendra Kumar Gupta ,B-72, Shahpura Bhopal,M.P – 462039". for Sand Quarry (Open cast manual method) in an area of 4.00 ha. for production capacity of 46000 cum/year at Khasra No. 49 at Village- Bhasunda, Tehsil - Maheswar, Dist. Khargone (MP." on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. All concerned be informed accordingly. 86. Case No.7029/2020 Prior Environmental Clearance for Sand Quarry (Open cast manual method) in an area of 4.50 ha. for production capacity of 1,200 cum/year at Khasra No. 938 at Village- Gopalpura, Tehsil - Sitamau, Dist. Mandsaur (MP) by Sarpanch/ Sachiv, Gram Panchayat Gopalpura , Tehsil Sitamau, Dist. Mandsaur (MP). - Regarding transfer of EC in the name of Regarding transfer of EC in

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 81 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

the name of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 . (1) It was noted that the PP had applied in Form-IM in DEIAA (Case no. 120/2018) for Prior Environmental Clearance of 4.50 ha. for production capacity of 1,200 cum/year at Khasra No. 938 at Village- Gopalpura, Tehsil - Sitamau, Dist. Mandsaur (MP) by Sarpanch/ Sachiv, Gram Panchayat Gopalpura , Tehsil Sitamau, Dist. Mandsaur (MP). (2) The Prior Environmental Clearance letter was issued DEIAA vide L.No. 44/DEIAA/2018 dated 24.09.2018 in the name of ” Sarpanch/ Sachiv, Gram Panchayat Gopalpura , Tehsil Sitamau, Dist. Mandsaur (MP)." (3) It is noted that PP has requested vide .L no nil dtd. 23.03.2020 received in SEIAA Office dtd. 11.05.2020 to make amendment in the Prior EC letter by changing the name of PP of the mining project namely " M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 in place of Sarpanch/ Sachiv, Gram Panchayat Gopalpura , Tehsil Sitamau, Dist. Mandsaur . (4) It is noted that in support of his request the PP has submitted the following documents i. No objection letter of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883. ii. Notarised affidavit of CEO- Shri Gowardhan Lal Malviya, Janpad Panchyat Gopalpura , Tehsil Sitamau, Dist. Mandsaur " mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued. iii. Copy of Prior EC issued by DEIAA, vide L.No. 44/DEIAA/2018 dated 24.09.2018 in the name of Sarpanch/ Sachiv, Gram Panchayat Gopalpura , Tehsil Sitamau, Dist. Mandsaur. iv. Copy of Environmental Management Plan of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 v. Copy of Mining Plan & Replenishment Plan transfered to M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 vi. Lease transfer order issued by Mineral Resource Department order to M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 vide.letter No. 924/132/2020/12/1 dated 18.02.2020.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 82 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

(5) It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC. Para-11 :- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases. In context of above it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued by DEIAA, Tikamgarh (Case no. 119/2018) on 24.09.2018 in the name of " Sarpanch/ Sachiv, Gram Panchayat Gopalpura , Tehsil Sitamau, Dist. Mandsaur." is hereby transferred to “M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 ". for Sand Quarry (Open cast manual method) in an area of 4.50 ha. for production capacity of 1,200 cum/year at Khasra No. 938 at Village- Gopalpura, Tehsil - Sitamau, Dist. Mandsaur (MP)." on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. All concerned be informed accordingly.. 87. Case No.7030/2020 Prior Environmental Clearance for Sand Quarry (Open cast manual method) in an area of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 845 at Village- Dhaturiya, Tehsil - Sitamau, Dist. Mandsaur (MP) by Sarpanch/ Sachiv, Gram Panchayat Dhaturiya , Tehsil Sitamau, Dist. Mandsaur (MP). - Regarding transfer of EC in the name of Regarding transfer of EC in the name of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 . (1) It was noted that the PP had applied in Form-IM in DEIAA (Case no. 118/2018) for Prior Environmental Clearance of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 845 at Village- Dhaturiya, Tehsil - Sitamau, Dist. Mandsaur (MP) by Sarpanch/ Sachiv, Gram Panchayat Dhaturiya , Tehsil Sitamau, Dist. Mandsaur (MP). (2) The Prior Environmental Clearance letter was issued DEIAA vide L.No. 46/DEIAA/2018 dated 24.09.2018 in the name of ” Sarpanch/ Sachiv, Gram Panchayat Dhaturiya , Tehsil Sitamau, Dist. Mandsaur (MP)." (3) It is noted that PP has requested vide .L no nil dtd. 23.03.2020 received in SEIAA Office dtd. 11.05.2020 to make amendment in the Prior EC letter by changing the name of PP of the mining project namely " M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 in place of Sarpanch/ Sachiv, Gram Panchayat Dhaturiya , Tehsil Sitamau, Dist. Mandsaur (MP). (4) It is noted that in support of his request the PP has submitted the following documents

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 83 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

i. No objection letter of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883. ii. Notarised affidavit of CEO- Shri Gowardhan Lal Malviya, Janpad Panchyat Sitamau, Dist. Mandsaur " mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued. iii. Copy of Prior EC issued by DEIAA, vide L.No. 46/DEIAA/2018 dated 24.09.2018 in the name of Sarpanch/ Sachiv, Gram Panchayat Dhaturiya , Tehsil Sitamau, Dist. Mandsaur. iv. Copy of Environmental Management Plan of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 v. Copy of Mining Plan & Replenishment Plan transfered to M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 vi. Lease transfer order issued by Mineral Resource Department order to M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 vide.letter No. 926/132/2020/12/1 dated 18.02.2020. (5) It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC. Para-11 :- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases. In context of above it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued by DEIAA, Tikamgarh (Case no. 118/2018) on 24.09.2018 in the name of " Sarpanch/ Sachiv, Gram Panchayat Dhaturiya , Tehsil Sitamau, Dist. Mandsaur." is hereby transferred to “M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 ". for Sand Quarry (Open cast manual method) in an area of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 845 at Village- Dhaturiya, Tehsil - Sitamau, Dist. Mandsaur (MP)." on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. All concerned be informed accordingly..

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 84 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

88. Case No.7031/2020 Prior Environmental Clearance for Sand Quarry (Open cast manual method) in an area of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 346 at Village- Mamatkhera, Tehsil - Sitamau, Dist. Mandsaur (MP) by Sarpanch/ Sachiv, Gram Panchayat Gopalpura , Tehsil Sitamau, Dist. Mandsaur (MP). - Regarding transfer of EC in the name of Regarding transfer of EC in the name of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 . (1) It was noted that the PP had applied in Form-IM in DEIAA (Case no. 120/2018) for Prior Environmental Clearance of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 346 at Village- Mamatkhera, Tehsil - Sitamau, Dist. Mandsaur (MP) by Sarpanch/ Sachiv, Gram Panchayat Gopalpura , Tehsil Sitamau, Dist. Mandsaur (MP). (2) The Prior Environmental Clearance letter was issued DEIAA vide L.No. 42/DEIAA/2018 dated 24.09.2018 in the name of ” Sarpanch/ Sachiv, Gram Panchayat Gopalpura , Tehsil Sitamau, Dist. Mandsaur (MP)." (3) It is noted that PP has requested vide .L no nil dtd. 23.03.2020 received in SEIAA Office dtd. 11.05.2020 to make amendment in the Prior EC letter by changing the name of PP of the mining project namely " M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 in place of Sarpanch/ Sachiv, Gram Panchayat Gopalpura , Tehsil Sitamau, Dist. Mandsaur . (4) It is noted that in support of his request the PP has submitted the following documents i. No objection letter of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883. ii. Notarised affidavit of CEO- Shri Gowardhan Lal Malviya, Janpad Panchyat Gopalpura , Tehsil Sitamau, Dist. Mandsaur " mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued. iii. Copy of Prior EC issued by DEIAA, vide L.No. 42/DEIAA/2018 dated 24.09.2018 in the name of Sarpanch/ Sachiv, Gram Panchayat Gopalpura , Tehsil Sitamau, Dist. Mandsaur. iv. Copy of Environmental Management Plan of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 v. Copy of Mining Plan & Replenishment Plan transfered to M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh,

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 85 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 vi. Lease transfer order issued by Mineral Resource Department order to M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 vide.letter No. 938/132/2020/12/1 dated 18.02.2020. (5) It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC. Para-11 :- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases. In context of above it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued by DEIAA, Tikamgarh (Case no. 120/2018) on 24.09.2018 in the name of " Sarpanch/ Sachiv, Gram Panchayat Gopalpura , Tehsil Sitamau, Dist. Mandsaur." is hereby transferred to “M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 ". for Sand Quarry (Open cast manual method) in an area of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 346 at Village- Mamatkhera, Tehsil - Sitamau, Dist. Mandsaur." on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. All concerned be informed accordingly. 89. Case No.7032/2020 Prior Environmental Clearance for Sand Quarry (Open cast manual method) in an area of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 578 at Village- Tatka, Tehsil - Sitamau, Dist. Mandsaur (MP) by Sarpanch/ Sachiv, Gram Panchayat Meriya Kheri , Tehsil Sitamau, Dist. Mandsaur (MP). - Regarding transfer of EC in the name of Regarding transfer of EC in the name of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 . (1) It was noted that the PP had applied in Form-IM in DEIAA (Case no. 117/2018) for Prior Environmental Clearance of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 578 at Village- Tatka, Tehsil - Sitamau, Dist. Mandsaur (MP) by Sarpanch/ Sachiv, Gram Panchayat Meriya Kheri , Tehsil Sitamau, Dist. Mandsaur (MP). (2) The Prior Environmental Clearance letter was issued DEIAA vide L.No. 50/DEIAA/2018 dated 24.09.2018 in the name of ” Sarpanch/ Sachiv, Gram Panchayat Meriya Kheri , Tehsil Sitamau, Dist. Mandsaur (MP)" (3) It is noted that PP has requested vide .L no nil dtd. 23.03.2020 received in SEIAA Office dtd. 11.05.2020 to make amendment in the Prior EC letter by

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 86 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

changing the name of PP of the mining project namely " M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 in place of Sarpanch/ Sachiv, Gram Panchayat Meriya Kheri , Tehsil Sitamau, Dist. Mandsaur (MP). (4) It is noted that in support of his request the PP has submitted the following documents i. No objection letter of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883. ii. Notarised affidavit of CEO- Shri Gowardhan Lal Malviya, Janpad Panchyat Sitamau, Dist. Mandsaur " mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued. iii. Copy of Prior EC issued by DEIAA, vide L.No. 50/DEIAA/2018 dated 24.09.2018 in the name of Sarpanch/ Sachiv, Gram Panchayat Meriya Kheri , Tehsil Sitamau, Dist. Mandsaur (MP). iv. Copy of Environmental Management Plan of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 v. Copy of Mining Plan & Replenishment Plan transfered to M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 vi. Lease transfer order issued by Mineral Resource Department order to M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 vide.letter No. 929/132/2020/12/1 dated 18.02.2020. (5) It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC. Para-11 :- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases. In context of above it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued by DEIAA, Tikamgarh (Case no. 117/2018) on 24.09.2018 in the name of " Sarpanch/ Sachiv, Gram Panchayat Meriya Kheri , Tehsil Sitamau, Dist.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 87 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

Mandsaur " is hereby transferred to “M/s Maa Bhagwati Construction Chandwasa, Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 ". for Sand Quarry (Open cast manual method) in an area of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 578 at Village- Tatka, Tehsil - Sitamau, Dist. Mandsaur (MP)" on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. All concerned be informed accordingly. 90. Case No.7033/2020 Prior Environmental Clearance for Sand Quarry (Open cast manual method) in an area of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 624 at Village- Parsi, Tehsil - Sitamau, Dist. Mandsaur (MP) by Sarpanch/ Sachiv, Gram Panchayat Karandiya , Tehsil Sitamau, Dist. Mandsaur (MP). - Regarding transfer of EC in the name of Regarding transfer of EC in the name of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 . (1) It was noted that the PP had applied in Form-IM in DEIAA (Case no. 122/2018) for Prior Environmental Clearance of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 624 at Village- Parsi, Tehsil - Sitamau, Dist. Mandsaur (MP) by Sarpanch/ Sachiv, Gram Panchayat Karandiya , Tehsil Sitamau, Dist. Mandsaur (MP). (2) The Prior Environmental Clearance letter was issued DEIAA vide L.No. 38/DEIAA/2018 dated 24.09.2018 in the name of ” Sarpanch/ Sachiv, Gram Panchayat Karandiya , Tehsil Sitamau, Dist. Mandsaur (MP)." (3) It is noted that PP has requested vide .L no nil dtd. 23.03.2020 received in SEIAA Office dtd. 11.05.2020 to make amendment in the Prior EC letter by changing the name of PP of the mining project namely " M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 in place of Sarpanch/ Sachiv, Gram Panchayat Karandiya , Tehsil Sitamau, Dist. Mandsaur (MP) (4) It is noted that in support of his request the PP has submitted the following documents i. No objection letter of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883. ii. Notarised affidavit of CEO- Shri Govardhan Lal Malviya, Janpad Panchyat Sitamau, Dist. Mandsaur." mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued. iii. Copy of Prior EC issued by DEIAA, vide L.No. 38/DEIAA/2018 dated 24.09.2018 in the name of Sarpanch/ Sachiv, Gram Panchayat Karandiya , Tehsil Sitamau, Dist. Mandsaur (MP).

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 88 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

iv. Copy of Environmental Management Plan of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 v. Copy of Mining Plan & Replenishment Plan transfered to M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 vi. Lease transfer order issued by Mineral Resource Department order to M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 vide.letter No. 930/132/2020/12/1 dated 18.02.2020. (5) It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC. Para-11 :- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases. In context of above it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued by DEIAA, Tikamgarh (Case no. 122/2018) on 24.09.2018 in the name of " Sarpanch/ Sachiv, Gram Panchayat Karandiya , Tehsil Sitamau, Dist. Mandsaur (MP)." is hereby transferred to “M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 ". for Sand Quarry (Open cast manual method) in an area of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 624 at Village- Parsi, Tehsil - Sitamau, Dist. Mandsaur (MP)." on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. All concerned be informed accordingly. 91. Case No.7034/2020 - Prior Environmental Clearance for Sand Quarry (Open cast manual method) in an area of 4.50 ha. for production capacity of 1,200 cum/year at Khasra No. 1039 at Village- Meriya Kheri, Tehsil - Sitamau, Dist. Mandsaur (MP) by Sarpanch/ Sachiv, Gram Panchayat Meriya Kheri , Tehsil Sitamau, Dist. Mandsaur (MP). - Regarding transfer of EC in the name of Regarding transfer of EC in the name of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 . (1) It was noted that the PP had applied in Form-IM in DEIAA (Case no. 116/2018) for Prior Environmental Clearance of 4.50 ha. for production capacity of 1,200 cum/year at Khasra No. 1039 at Village- Meriya Kheri, Tehsil - Sitamau, Dist. Mandsaur (MP) by Sarpanch/ Sachiv, Gram Panchayat Meriya Kheri , Tehsil Sitamau, Dist. Mandsaur (MP)..

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 89 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

(2) The Prior Environmental Clearance letter was issued DEIAA vide L.No. 48/DEIAA/2018 dated 24.09.2018 in the name of ” Sarpanch/ Sachiv, Gram Panchayat Meriya Kheri , Tehsil Sitamau, Dist. Mandsaur (MP)." (3) It is noted that PP has requested vide .L no nil dtd. 23.03.2020 received in SEIAA Office dtd. 11.05.2020 to make amendment in the Prior EC letter by changing the name of PP of the mining project namely " M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 in place of Sarpanch/ Sachiv, Gram Panchayat Meriya Kheri , Tehsil Sitamau, Dist. Mandsaur (MP) (4) It is noted that in support of his request the PP has submitted the following documents i. No objection letter of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883. ii. Notarised affidavit of CEO- Shri Govardhan Lal Malviya, Janpad Panchyat Sitamau, Dist. Mandsaur." mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued. iii. Copy of Prior EC issued by DEIAA, vide L.No. 48/DEIAA/2018 dated 24.09.2018 in the name of Sarpanch/ Sachiv, Gram Panchayat Meriya Kheri , Tehsil Sitamau, Dist. Mandsaur (MP). iv. Copy of Environmental Management Plan of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 v. Copy of Mining Plan & Replenishment Plan transfered to M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 vi. Lease transfer order issued by Mineral Resource Department order to M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 vide.letter No. 922/132/2020/12/1 dated 18.02.2020. (5) It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC. Para-11 :- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 90 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases. In context of above it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued by DEIAA, Tikamgarh (Case no. 116/2018) on 24.09.2018 in the name of " Sarpanch/ Sachiv, Gram Panchayat Meriya Kheri , Tehsil Sitamau, Dist. Mandsaur (MP). " is hereby transferred to “M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 ". for Sand Quarry (Open cast manual method) in an area of 4.50 ha. for production capacity of 1,200 cum/year at Khasra No. 1039 at Village- Meriya Kheri, Tehsil - Sitamau, Dist. Mandsaur (MP)." on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. All concerned be informed accordingly. 92. Case No.7035/2020:- Prior Environmental Clearance for Sand Quarry (Open cast manual method) in an area of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 122 at Village- Jetpura, Tehsil - Sitamau, Dist. Mandsaur (MP) by Sarpanch/ Sachiv, Gram Panchayat Dipakhera , Tehsil Sitamau, Dist. Mandsaur (MP). - Regarding transfer of EC in the name of Regarding transfer of EC in the name of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 . (1) It was noted that the PP had applied in Form-IM in DEIAA (Case no. 123/2018) for Prior Environmental Clearance of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 122 at Village- Jetpura, Tehsil - Sitamau, Dist. Mandsaur (MP) by Sarpanch/ Sachiv, Gram Panchayat Dipakhera , Tehsil Sitamau, Dist. Mandsaur (MP).. (2) The Prior Environmental Clearance letter was issued DEIAA vide L.No. 36/DEIAA/2018 dated 24.09.2018 in the name of ” Sarpanch/ Sachiv, Gram Panchayat Dipakhera , Tehsil Sitamau, Dist. Mandsaur (MP)." (3) It is noted that PP has requested vide .L no nil dtd. 23.03.2020 received in SEIAA Office dtd. 11.05.2020 to make amendment in the Prior EC letter by changing the name of PP of the mining project namely " M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 in place of Sarpanch/ Sachiv, Gram Panchayat Dipakhera , Tehsil Sitamau, Dist. Mandsaur (MP) (4) It is noted that in support of his request the PP has submitted the following documents i. No objection letter of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883. ii. Notarised affidavit of CEO- Shri Govardhan Lal Malviya, Janpad Panchyat Sitamau, Dist. Mandsaur." mentioning that no legal action/

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 91 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued. iii. Copy of Prior EC issued by DEIAA, vide L.No. 36/DEIAA/2018 dated 24.09.2018 in the name of Sarpanch/ Sachiv, Gram Panchayat Dipakhera , Tehsil Sitamau, Dist. Mandsaur (MP). iv. Copy of Environmental Management Plan of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 v. Copy of Mining Plan & Replenishment Plan transfered to M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 vi. Lease transfer order issued by Mineral Resource Department order to M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 vide.letter No. 932/132/2020/12/1 dated 18.02.2020. (5) It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC. Para-11 :- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases. In context of above it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued by DEIAA, Tikamgarh (Case no. 123/2018) on 24.09.2018 in the name of " Sarpanch/ Sachiv, Gram Panchayat Dipakhera , Tehsil Sitamau, Dist. Mandsaur (MP)." is hereby transferred to “M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 ". for Sand Quarry (Open cast manual method) in an area of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 122 at Village- Jetpura, Tehsil - Sitamau, Dist. Mandsaur (MP)." on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. All concerned be informed accordingly. 93. Case No.7036/2020 Prior Environmental Clearance for Sand Quarry (Open cast manual method) in an area of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 202 & 333 at Village- Basgon, Tehsil - Garoth, Dist. Mandsaur (MP) by Sarpanch/ Sachiv, Gram Panchayat Basgon , Tehsil Garoth, Dist. Mandsaur (MP). - Regarding transfer of EC in the name of Regarding transfer of EC in the name of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 .

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 92 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

(1) It was noted that the PP had applied in Form-IM in DEIAA (Case no. 121/2018) for Prior Environmental Clearance of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 202 & 333 at Village- Basgon, Tehsil - Garoth, Dist. Mandsaur (MP) by Sarpanch/ Sachiv, Gram Panchayat Basgon , Tehsil Garoth, Dist. Mandsaur (MP).. (2) The Prior Environmental Clearance letter was issued DEIAA vide L.No. 40/DEIAA/2018 dated 24.09.2018 in the name of ” Sarpanch/ Sachiv, Gram Panchayat Basgon , Tehsil Garoth, Dist. Mandsaur (MP)." (3) It is noted that PP has requested vide .L no nil dtd. 23.03.2020 received in SEIAA Office dtd. 11.05.2020 to make amendment in the Prior EC letter by changing the name of PP of the mining project namely " M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 in place of Sarpanch/ Sachiv, Gram Panchayat Basgon , Tehsil Garoth, Dist. Mandsaur (MP) (4) It is noted that in support of his request the PP has submitted the following documents i. No objection letter of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883. ii. Notarised affidavit of CEO- Shri Ramswaroopji Sahu, Janpad Panchyat Basgon , Tehsil Garoth, Dist. Mandsaur (MP)." mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued. iii. Copy of Prior EC issued by DEIAA, vide L.No. 40/DEIAA/2018 dated 24.09.2018 in the name of Sarpanch/ Sachiv, Gram Panchayat Basgon , Tehsil Garoth, Dist. Mandsaur (MP). iv. Copy of Environmental Management Plan of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 v. Copy of Mining Plan & Replenishment Plan transfered to M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 vi. Lease transfer order issued by Mineral Resource Department order to M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 vide.letter No. 936/132/2020/12/1 dated 18.02.2020. (5) It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 93 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

Para-11 :- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases. In context of above it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued by DEIAA, Tikamgarh (Case no. 121/2018) on 24.09.2018 in the name of " Sarpanch/ Sachiv, Gram Panchayat Basgon , Tehsil Garoth, Dist. Mandsaur (MP)." is hereby transferred to “M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 ". for Sand Quarry (Open cast manual method) in an area of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 202 & 333 at Village- Basgon, Tehsil - Garoth, Dist. Mandsaur (MP)." on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. All concerned be informed accordingly. 94. Case No.7037/2020:- Prior Environmental Clearance for Sand Quarry (Open cast manual method) in an area of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 617 at Village- Ekalgarh, Tehsil - Sitamau, Dist. Mandsaur (MP) by Sarpanch/ Sachiv, Gram Panchayat Satakheri , Tehsil Sitamau, Dist. Mandsaur (MP). - Regarding transfer of EC in the name of Regarding transfer of EC in the name of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 . (1) It was noted that the PP had applied in Form-IM in DEIAA (Case no. 124/2018) for Prior Environmental Clearance of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 617 at Village- Ekalgarh, Tehsil - Sitamau, Dist. Mandsaur (MP) by Sarpanch/ Sachiv, Gram Panchayat Satakheri , Tehsil Sitamau, Dist. Mandsaur (MP). (2) The Prior Environmental Clearance letter was issued DEIAA vide L.No. 34/DEIAA/2018 dated 24.09.2018 in the name of ” Sarpanch/ Sachiv, Gram Panchayat Satakheri , Tehsil Sitamau, Dist. Mandsaur (MP)." (3) It is noted that PP has requested vide .L no nil dtd. 23.03.2020 received in SEIAA Office dtd. 11.05.2020 to make amendment in the Prior EC letter by changing the name of PP of the mining project namely " M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 in place of Sarpanch/ Sachiv, Gram Panchayat Satakheri , Tehsil Sitamau, Dist. Mandsaur (MP) (4) It is noted that in support of his request the PP has submitted the following documents i. No objection letter of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of M/s Maa Bhagwati

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 94 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883. ii. Notarised affidavit of CEO- Shri Govardhan Lal Malviya, Janpad Panchyat Sitamau, Dist. Mandsaur." mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued. iii. Copy of Prior EC issued by DEIAA, vide L.No. 34/DEIAA/2018 dated 24.09.2018 in the name of Sarpanch/ Sachiv, Gram Panchayat Satakheri , Tehsil Sitamau, Dist. Mandsaur (MP). iv. Copy of Environmental Management Plan of M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 v. Copy of Mining Plan & Replenishment Plan transfered to M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 vi. Lease transfer order issued by Mineral Resource Department order to M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 vide.letter No. 932/132/2020/12/1 dated 18.02.2020. (5) It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC. Para-11 :- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases. In context of above it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued by DEIAA, Tikamgarh (Case no. 124/2018) on 24.09.2018 in the name of " Sarpanch/ Sachiv, Gram Panchayat Satakheri , Tehsil Sitamau, Dist. Mandsaur (MP)." is hereby transferred to “M/s Maa Bhagwati Construction Chandwasa,Prop. Shri Govind Singh, House No. 23, Kilagari, Tehsil Shamgarh, Dist. Mandsaur M.P- 458883 ". for Sand Quarry (Open cast manual method) in an area of 4.00 ha. for production capacity of 1,200 cum/year at Khasra No. 617 at Village- Ekalgarh, Tehsil - Sitamau, Dist. Mandsaur (MP)." on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. All concerned be informed accordingly.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 95 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

95. Case No. 7026/20 (DEIAA Case) Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 5.0 ha. (76031 cum per annum) (Khasra No. 176), Village - Nidhipuri, Tehsil - Majhuli, Dist. - Sidhi (MP) by Sarpanch, Gram Panchayat, Dhuadol, Tehsil - Majhuli, Dist. - Sidhi (MP) - Regarding transfer of EC in the name of M/s Sainik Industries Pvt.Ltd., Authorized person Shri Litesh Jha, 201-202, Vikas Plaza Building No. 2, Local Shopping Center Kalkaji New Delhi-110019. i. It was noted that the PP had applied in Form-I for Prior Environmental Clearance of 5.0 ha. for production capacity of 76031 cum/year at khasra no. 176 at Village - Nidhipuri, Tehsil - Majhuli, Dist. - Sidhi (MP) by Sarpanch, Gram Panchayat, Dhuadol, Tehsil - Majhuli, Dist. - Sidhi (MP). ii. The Prior Environmental Clearance letter was issued by DEIAA, Dist. - Sidhi vide L.No. 64/DEIAA/E.C./2018 dated 18.09.18 in the name of “Sarpanch, Gram Panchayat, Dhuadol, Tehsil - Majhuli, Dist. - Sidhi (MP)”. iii. It is noted that PP has requested vide letter no. nil dtd. 08.05.2020 to make amendment in Prior EC letter by changing the name of PP in mining project namely M/s Sainik Industries Pvt.Ltd., Authorized person Shri Litesh Jha, 201-202, Vikas Plaza Building No. 2, Local Shopping Center Kalkaji New Delhi-110019 in place of Sarpanch, Gram Panchayat, Dhuadol, Tehsil - Majholi, Dist. - Sidhi (MP). iv. It is noted that in support of his request the PP has submitted the following documents: a) No objection letter of previous Project Proponent (to whom prior EC was granted) issued by "CEO, Janpad Panchayat Majhuli, Dist. - Sidhi MP" for transfer of prior EC on behalf of Sarpanch, Gram Panchayat, Dhuadol, Tehsil - Majhuli, Dist. - Sidhi (MP). b) Notarised affidavit of M/s Sainik Industries Pvt.Ltd. Authorized person Shri Litesh Jha, 201-202, Vikas Plaza Building No. 2, Local Shopping Center Kalkaji New Delhi-110019, mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued. c) Copy of Prior EC issued by DEIAA, Dist. - Sidhi vide L.No. 64/DEIAA/E.C./2018 dated 18.09.18 d) Copy of Environmental Management Plan of M/s Sainik Industries Pvt.Ltd. Authorized person Shri Litesh Jha, 201-202, Vikas Plaza Building No. 2, Local Shopping Center Kalkaji New Delhi-110019. e) Copy of Approved Mining Plan has been transfered by Collector, Sidhi vide L.No. 229@[kfutz@2020 dated 07.03.2020 to M/s Sainik Industries Pvt.Ltd., Authorized person Shri Litesh Jha, 201-202, Vikas Plaza Building No. 2, Local Shopping Center Kalkaji New Delhi-110019.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 96 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

f) Copy of Approved Replenishment Plan of M/s Sainik Industries Pvt.Ltd. Authorized person Shri Litesh Jha, 201-202, Vikas Plaza Building No. 2, Local Shopping Center Kalkaji New Delhi-110019. g) Lease transfer order issued by Mineral Resource Department to M/s Sainik Industries Pvt.Ltd., Authorized person Shri Litesh Jha, 201-202, Vikas Plaza Building No. 2, Local Shopping Center Kalkaji New Delhi- 110019 vide letter No. 1658/132/2020/12/1/ dated 16.03.2020. v. It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC. Para-11:- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases. In context of above, it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued by DEIAA, Sidhi MP on 18.09.18 in the name of “Sarpanch, Gram Panchayat, Dhuadol, Tehsil - Majhuli, Dist. - Sidhi (MP)” is hereby transferred to “M/s Sainik Industries Pvt.Ltd., Authorized person Shri Litesh Jha, 201-202, Vikas Plaza Building No. 2, Local Shopping Center Kalkaji New Delhi-110019” for Sand Quarry in an area of 5.0 ha. for production capacity of 76031 cum/year at khasra no. 176 at Village - Nidhipuri, Tehsil - Majhuli, Dist. - Sidhi (MP) on the same terms & conditions, production capacity and validity period under which the prior Environmental Clearance was initially granted. 96. Case No. 7107/20 (DEIAA Case) Prior Environmental Clearance for Sand Quarry (Opencast Manual Method) in an area of 4.680 ha. (42120 cum per annum) (Khasra No. 404, 1215), Village – Bajranggarh, Tehsil - Rampur Naikin, Dist. - Sidhi (MP) by Sarpanch, Gram Panchayat Pepkhara, Tehsil - Rampur Naikin, Dist. - Sidhi (MP) - Regarding transfer of EC in the name of M/s Sainik Industries Pvt.Ltd., Authorized person Shri Litesh Jha, 201-202, Vikas Plaza Building No. 2, Local Shopping Center Kalkaji New Delhi-110019. i. It was noted that the PP had applied in Form-I for Prior Environmental Clearance of 4.680 ha. for production capacity of 42120 cum/year at khasra no. 404, 1215 at Village - Bajranggarh, Tehsil - Rampur Naikin, Dist. - Sidhi (MP) by Sarpanch, Gram Panchayat Pepkhara, Tehsil - Rampur Naikin, Dist. - Sidhi (MP). ii. The Prior Environmental Clearance letter was issued by DEIAA, Dist. - Sidhi vide L.No. 55/DEIAA/E.C./2018 dated 04.08.18 in the name of “Sarpanch, Gram Panchayat Pepkhara, Tehsil - Rampur Naikin, Dist. - Sidhi (MP)”. iii. It is noted that PP has requested vide letter no. nil dtd. 27.05.2020 to make amendment in Prior EC letter by changing the name of PP in mining project namely M/s Sainik Industries Pvt.Ltd., Authorized person Shri Litesh Jha,

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 97 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

201-202, Vikas Plaza Building No. 2, Local Shopping Center Kalkaji New Delhi-110019 in place of Sarpanch, Gram Panchayat Pepkhara, Tehsil - Rampur Naikin, Dist. - Sidhi. iv. It is noted that in support of his request the PP has submitted the following documents: a) No objection letter of previous Project Proponent (to whom prior EC was granted) issued by “CEO, Janpad Panchayat Rampur Naikin, Dist. - Sidhi MP” for transfer of prior EC on behalf of Sarpanch, Gram Panchayat Pepkhara, Tehsil - Rampur Naikin, Dist. - Sidhi (MP). b) Notarised affidavit of M/s Sainik Industries Pvt. Ltd. Authorized person Shri Litesh Jha, 201-202, Vikas Plaza Building No. 2, Local Shopping Center Kalkaji New Delhi-110019, mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued. c) Copy of Prior EC issued by DEIAA, Dist. - Sidhi vide L.No. 55/DEIAA/E.C./2018 dated 04.08.18. d) Copy of Environmental Management Plan of M/s Sainik Industries Pvt. Ltd. Authorized person Shri Litesh Jha, 201-202, Vikas Plaza Building No. 2, Local Shopping Center Kalkaji New Delhi-110019. e) Copy of Approved Mining Plan has been transfered by Collector, Sidhi vide L.No. 237@[kfutz@2020 dated 07.03.2020 to M/s Sainik Industries Pvt.Ltd., Authorized person Shri Litesh Jha, 201-202, Vikas Plaza Building No. 2, Local Shopping Center Kalkaji New Delhi-110019. f) Copy of Approved Replenishment Plan of M/s Sainik Industries Pvt. Ltd. Authorized person Shri Litesh Jha, 201-202, Vikas Plaza Building No. 2, Local Shopping Center Kalkaji New Delhi-110019. g) Lease transfer order issued by Mineral Resource Department to M/s Sainik Industries Pvt.Ltd., Authorized person Shri Litesh Jha, 201-202, Vikas Plaza Building No. 2, Local Shopping Center Kalkaji New Delhi- 110019 vide letter No. 1660/132/2020/12/1/ dated 16.03.2020. v. It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC. Para-11:- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases. In context of above, it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 98 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

EC issued by DEIAA, Sidhi MP on 04.08.18 in the name of “Sarpanch, Gram Panchayat Pepkhara, Tehsil - Rampur Naikin, Dist. - Sidhi (MP)” is hereby transferred to “M/s Sainik Industries Pvt.Ltd., Authorized person Shri Litesh Jha, 201-202, Vikas Plaza Building No. 2, Local Shopping Center Kalkaji New Delhi-110019” for Sand Quarry in an area of 4.680 ha. for production capacity of 42120 cum/year at khasra no. 404, 1215 at Village - Bajranggarh, Tehsil - Rampur Naikin, Dist. - Sidhi (MP) on the same terms & conditions, production capacity and validity period under which the prior Environmental Clearance was initially granted.

97. Case No.3005/2015 Prior Environment Clearance for Sand Quarry (Opencast Manual Method) in an area of 2.00 ha. (56,000 cum/year) at Village-Veerpura, Tehsil-Lidhora, District-Tikamgarh (MP) by Shri Nagendra Singh, OIC, M.P. State Mining Corporation Ltd., Civil Line, Tikamgarh (MP)- 472001, Regarding transfer of EC in the name of Shri Virendra Singh Jadoun, E-7/ M-708, Arera Colony, Bhopal M.P. 462016 (1) It was noted that the PP had applied in Form-I for Prior Environmental Clearance of 2.0 ha. for production capacity of 56000 cum /year at Khasra no. 759 at Village- Village-Veerpura, Tehsil-Lidhora, District-Tikamgarh by Shri Nagendra Singh, OIC, M.P. State Mining Corporation Ltd., Civil Line, Tikamgarh (MP)- 472001. (2) The Prior Environmental Clearance letter was issued SEIAA vide L.No. 7031/SEIAA/15 dtd.31.10.2015 in the name of " Shri Nagendra Singh, OIC, M.P. State Mining Corporation Ltd., Civil Line, Tikamgarh (MP)- 472001. (3) It is noted that PP has requested vide no nil dtd.05.05.2020 received in SEIAA office 05.05.2020 to make amendment in the Prior EC letter by changing the name of PP of the mining project namely " Shri VIrendra Singh Jadon, E-7/ M-708, Arera Colony, Bhopal M.P. 462016.” in place of “Shri Nagendra Singh, OIC, M.P. State Mining Corporation Ltd., Civil Line, Tikamgarh (MP)- 472001". (4) It is noted that in support of his request the PP has submitted the following documents i. No objection letter of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of Shri VIrendra Singh Jadon, E-7/ M-708, Arera Colony, Bhopal M.P. 462016. ii. Notarised affidavit of “Shri Nagendra Singh, OIC, M.P. State Mining Corporation Ltd. Civil Line, Tikamgarh " mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued iii. Copy of Prior EC issued by SEIAA. vide L.No. 7031/SEIAA/15 dtd.31.10.2015 iv. Copy of Environmental Management Plan of Shri VIrendra Singh Jadon, E-7/ M-708, Arera Colony, Bhopal M.P. 462016.

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 99 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

v. Copy of Approved Mining Plan with Replenishment Plan of Shri VIrendra Singh Jadon, E-7/ M-708, Arera Colony, Bhopal M.P. 462016 vi. Lease transfer order issued by Mineral Resource Department order to of Shri VIrendra Singh Jadon, E-7/ M-708, Arera Colony, Bhopal M.P. 462016, vide endt. letter No. 1579/132/2020/12/1 dated 13.03.2020. (5) It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC. Para-11 :- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases. In context of above it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued SEIAA on 31.10.2015 in the name of " Shri Nagendra Singh, OIC, M.P. State Mining Corporation Ltd. Civil Line, Tikamgarh." is hereby transferred to Shri VIrendra Singh Jadon, E-7/ M-708, Arera Colony, Bhopal M.P. 462016- ". for Sand Quarry (Open cast manual method) in an area of 2.0 ha. for production capacity of 56000 cum /year at Khasra no. 759 at Village- Veerpura, Tehsil-Lidhora, District-Tikamgarh (MP) ." on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. All concerned be informed accordingly. 98. Case No.:- 7067/2020 Prior Environmental Clearance for Sand Quarry (Open cast manual method) in an area of 3.00 ha. for production capacity of 85,000 cum/year at Khasra No. 1 at Village- Larkhurd Parai Nadi, Tehsil - Jatara, Dist. Tikamgarh (MP) by Gram Panchayat , Larkhurd, Tehsil Jatara, District Tikamgarh (MP). - Regarding transfer of EC in the name of Regarding transfer of EC in the name of Shri Virendra Singh Jadoun, E-7/ M-708, Arera Colony, Bhopal M.P. 462016. (1) It was noted that the PP had applied in Form-IM in DEIAA (Case no. 2992/2015) for Prior Environmental Clearance of 3.00 ha. for production capacity of 85,000 cum/year at Khasra No. 1 at Village- Larkhurd Parai Nadi, Tehsil - Jatara, Dist. Tikamgarh (MP) by Gram Panchayat , Larkhurd, Tehsil Jatara, District Tikamgarh (MP).. (2) The Prior Environmental Clearance letter was issued DEIAA vide L.No. 167/DEIAA/2018 dated 29.01.2018 in the name of ” Gram Panchayat , Larkhurd, Tehsil Jatara, District Tikamgarh (MP)." (3) It is noted that PP has requested vide .L no nil dtd. nil received in SEIAA Office dtd. 22.05.2020 to make amendment in the Prior EC letter by changing the

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 100 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

name of PP of the mining project namely " Shri Virendra Singh Jadoun, E-7/ M-708, Arera Colony, Bhopal M.P. 462016 in place of Gram Panchayat , Larkhurd, Tehsil Jatara, District Tikamgarh (MP). (4) It is noted that in support of his request the PP has submitted the following documents i. No objection letter of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of Shri Virendra Singh Jadoun, E-7/ M-708, Arera Colony, Bhopal M.P. 462016. ii. Notarised affidavit of Sarpanch Gram Panchayat , Smt Deepshika Tiwari , Larkhurd, Tehsil Jatara, District Tikamgarh." mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued. iii. Copy of Prior EC issued by DEIAA, vide L.No. 167 DEIAA/2018 dated 29.01.2018 in the name of Gram Panchayat , Larkhurd, Tehsil Jatara, District Tikamgarh (MP). iv. Copy of Environmental Management Plan of Shri Virendra Singh Jadoun, E-7/ M-708, Arera Colony, Bhopal M.P. 462016 v. Copy of Mining Plan & Replenishment Plan transfered to Shri Virendra Singh Jadoun, E-7/ M-708, Arera Colony, Bhopal M.P. 462016. vi. Lease transfer order issued by Mineral Resource Department order to Shri Virendra Singh Jadoun, E-7/ M-708, Arera Colony, Bhopal M.P. 462016 vide endt.letter No. 1306/132/2020/12/1 dated 04.03.2020. (5) It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC. Para-11 :- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases. In context of above it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued by DEIAA, Tikamgarh (Case no. 2992/2015) on 29.01.2018 in the name of " Gram Panchayat , Larkhurd, Tehsil Jatara, District Tikamgarh (MP)." is hereby transferred to “Shri Virendra Singh Jadoun, E-7/ M-708, Arera Colony, Bhopal M.P. 462016". for Sand Quarry (Open cast manual method) in an area of 3.00 ha. for production capacity of 85,000 cum/year at Khasra No. 1 at Village- Larkhurd Parai Nadi, Tehsil - Jatara, Dist. Tikamgarh (MP)." on the same terms &

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 101 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

conditions and validity period under which the prior environmental clearance was initially granted. All concerned be informed accordingly 99. Case no. 7068/2020 Prior Environmental Clearance for Sand Quarry (Open cast manual method) in an area of 3.00 ha. for production capacity of 18,838 cum/year at Khasra No. 45 at Village- Dantgora, Tehsil - Palera, Dist. Tikamgarh (MP) by The M.P. State Mining Corporation Ltd., Sub Off., Tikamgarh (MP). - Regarding transfer of EC in the name of Regarding transfer of EC in the name of Shri Virendra Singh Jadoun, E-7/ M-708, Arera Colony, Bhopal M.P. 462016. (1) It was noted that the PP had applied in Form-IM in DEIAA (Case no. 2837/2015) for Prior Environmental Clearance of 3.00 ha. for production capacity of 18,838 cum/year at Khasra No. 45 at Village- Dantgora, Tehsil - Palera, Dist. Tikamgarh (MP) by The M.P. State Mining Corporation Ltd., Sub Off., Tikamgarh (MP). (2) The Prior Environmental Clearance letter was issued DEIAA vide L.No. 13/DEIAA/2016 dated 26.05.2016 in the name of ” The M.P. State Mining Corporation Ltd., Sub Off., Tikamgarh (MP)." (3) It is noted that PP has requested vide .L no nil dtd. nil received in SEIAA Office dtd. 22.05.2020 to make amendment in the Prior EC letter by changing the name of PP of the mining project namely " Shri Virendra Singh Jadoun, E-7/ M-708, Arera Colony, Bhopal M.P. 462016 in place of The M.P. State Mining Corporation Ltd., Sub Off., Tikamgarh (MP). (4) It is noted that in support of his request the PP has submitted the following documents i. No objection letter of previous Project Proponent (to whom prior EC was granted) for transfer of prior EC in the name of Shri Virendra Singh Jadoun, E-7/ M-708, Arera Colony, Bhopal M.P. 462016. ii. Notarised affidavit of of Shri Nagendra Singh, OIC, M.P. State Mining Corporation Ltd." mentioning that no legal action/ credible action has been initiated against the mine till date and commitment to comply all the standard and specific conditions stipulated in the prior EC issued. iii. Copy of Prior EC issued by DEIAA, vide L.No. 13 DEIAA/2016 dated 26.05.2016 in the name of The M.P. State Mining Corporation Ltd., Sub Off., Tikamgarh (MP). iv. Copy of Environmental Management Plan of Shri Virendra Singh Jadoun, E-7/ M-708, Arera Colony, Bhopal M.P. 462016 v. Copy of Mining Plan & Replenishment Plan transfered to Shri Virendra Singh Jadoun, E-7/ M-708, Arera Colony, Bhopal M.P. 462016. vi. Lease transfer order issued by Mineral Resource Department order to Shri Virendra Singh Jadoun, E-7/ M-708, Arera Colony,

(Tanvi Sundriyal) (R.K. Sharma) (Rakesh K. Shrivastava) Member Secretary Member Chairman

614th SEIAA Meeting dtd. 04.06.2020 Page 102 of 103

Minutes of the 614th Meeting of SEIAA dated. 04.06.2020

Bhopal M.P. 462016 vide endt.letter No. 1582/132/2020/12/1 dated 13.03.2020. (5) It is noted that in EIA Notification 2006 as per Para-11 Transferability of Environmental Clearance (EC) there is a provision of transferring the EC. Para-11 :- A prior environmental clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor, or by the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. No reference to the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned is necessary in such cases. In context of above it seems that PP has submitted adequate documents to make the change in the name of PP as per EIA Notification 2006 (Para-11). Hence, prior EC issued by DEIAA, Tikamgarh (Case no. 2837/2015) on 26.05.2016 in the name of " The M.P. State Mining Corporation Ltd., Sub Off., Tikamgarh (MP)." is hereby transferred to “Shri Virendra Singh Jadoun, E-7/ M-708, Arera Colony, Bhopal M.P. 462016". for Sand Quarry (Open cast manual method) in an area of 3.00 ha. for production capacity of 18,838 cum/year at Khasra No. 45 at Village- Dantgora, Tehsil - Palera, Dist. Tikamgarh (MP)." on the same terms & conditions and validity period under which the prior environmental clearance was initially granted. All concerned be informed accordingly

Meeting ended with a vote of thanks to the Chair.