Initial Environmental Examination

Document Stage: Draft Project Number: 42486-016 October 2016

IND: Urban Services Improvement Program – Water Supply Improvement in , , , , Patan, and Tendukheda

Package No: MPUSIP-5B

Prepared by Madhya Pradesh Urban Development Company, Government of Madhya Pradesh for the Asian Development Bank.

This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Draft Initial Environmental Examination

October 2016

IND: Madhya Pradesh Urban Services Improvement Program –Subproject of Water Supply Improvement in Katangi, Bhedaghat, Majholi, Panagar, Patan, Sihora and Tendukheda- Package 5B

Prepared by M/s LN Malviya Infra Project Pvt. Ltd.

IEE Package 5B

CURRENCY EQUIVALENTS (As of October 01 ,2016) Currency unit = Rupee (INR)

USD 1.00 = INR 66.60

ABBREVIATIONS ADB - Asian Development Bank AP - Affected Person BPL - Below Poverty Line CWC - Central Water Commission DP - Displaced Person EA - Executive Agency GOI - Government of GOMP - Government of Madhya Pradesh HHs - Households IA - Implementing Agency IR - Involuntary Resettlement KM - Kilometer MPUDC - Madhya Pradesh Urban Development Company MPUSIP - Madhya Pradesh Services Improvement Project O&M - operation and maintenance PHED - Public Health Engineering Department PIU - Project Implementation Unit PMC - Program Monitoring Consultant PMU - Program Management Unit PO - Project Officer PWD - Public works Department R&R - Resettlement and Rehabilitation RF - Resettlement Framework RFCTLARR - The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 RP - Resettlement Plan ROW - Right of Way RWA - Resident Welfare Associations RWRM - Raw Water Rising Main SO - Safeguard Officer SPS - Safeguard Policy Statement TA - Technical Assistance UADD - Urban Administration and Development Directorate UDHD - Urban Development and Housing Department ULBs - Urban Local Bodies WRD - Water Resource Department WSS - Water Supply Scheme WTP - Water Treatment Plant

M/s LN Malviya Infra Project Pvt. Ltd. Page 2

IEE Package 5B

WEIGHTS AND MEASURES

C Degree Celsius km kilometre lpcd litres per capita per day MCM Million Cubic Meter mm milli meter m metre MLD million litres per day mm millimetre Nos Numbers sq.km Square Kilometer

M/s LN Malviya Infra Project Pvt. Ltd. Page 3

IEE Package 5B

Contents

I. EXECUTIVE SUMMARY...... 7 II. INTRODUCTION ...... 12 A. Background ...... 12 B. Purpose of this IEE Report ...... 13 C. Report Structure ...... 14 III. DESCRIPTION OF THE PROJECT ...... 15 A. Project Area ...... 15 B. Existing Water Supply Situation...... 16 C. Proposed Project...... 19 IV. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK...... 9 A. ADB Policy ...... 9 B. National Environmental Laws...... 9 V. DESCRIPTION OF THE ENVIRONMENT ...... 14 A. Methodology Used for Baseline Study ...... 14 B. Baseline Environmental Profile ...... 14 VI. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 35 A. Pre-Construction Impacts – Design & Location ...... 36 B. Construction Impacts ...... 42 C. Operation and Maintenance Impacts ...... 48 D. Project benefits ...... 49 VII. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE ...... 50 A. Overview...... 50 B. Public Consultation ...... 50 C. Information Disclosure...... 51 VIII. GRIEVANCE REDRESS MECHANISM ...... 52 A. Project Specific Grievance Redress Mechanism ...... 52 IX. ENVIRONMENTAL MANAGEMENT PLAN ...... 55 A. Implementation Arrangements ...... 55 B. Environmental Management Plan ...... 55 C. EMP Compliance Responsibilities...... 75 D. Training Needs ...... 77 E. Monitoring and Reporting ...... 78 F. EMP Implementation Cost...... 79 X. CONCLUSION AND RECOMMENDATIONS ...... 81

M/s LN Malviya Infra Project Pvt. Ltd. Page 4

IEE Package 5B

LIST OF TABLES

Table 1: Details of Rising main and Distribution network ...... 16 Table 2: Details of Distribution system...... 17 Table 3: Details of Distribution system...... 17 Table 4: Details of Distribution system...... 18 Table 5: Proposed Water Supply Subproject Components...... 1 Table 6: Applicable Environmental Regulations ...... 10 Table 7: WHO Ambient Air& Noise Quality Guidelines ...... 13 Table 8: Baseline Environmental Profile of towns ...... 15 Table 9: Site Environmental Features...... 27 Table 10: Flow of at Manot ...... 38 Table 11: Flow of Narmada river at Barmanghat...... 38 Table 12: Design Stage Environmental Management Plan...... 57 Table 13: Pre-Construction State Environmental Management Plan ...... 59 Table 14: Construction Stage Environmental Management Plan ...... 62 Table 15: Operation Stage Environmental Management Plan ...... 71 Table 16: Construction Stage Environmental Monitoring Plan...... 73 Table 17: Operation Stage Environmental Monitoring Plan ...... 74 Table 18: Outline Capacity Building Program on EMP Implementation...... 77 Table 19: Cost Estimates to Implement the EMP ...... 79

LIST OF FIGURES

Figure 1: MP State Map with subprojects local towns 15 Figure 2: Google map showing ,Panagar, Sihora, Majholi, Katangi, Patan, Tendukheda Towns and River Narmada 20 Figure 3: Key Plan of Bhedaghat Group WSS 4 Figure 4: Proposed Intake and WTP Site at Bhedaghat 5 Figure 5: Intake Well Cross section 6 Figure 6: Transmission Network of Proposed Group WSS 7 Figure 7: Schematic Diagram of Group WSS 8 Figure 8: Site Environs of Bhedaghat Town 23 Figure 9: Site Environs of Panagar, Katangi and Majholi Towns 24 Figure 10: Site Environs of Patan and Tendukheda Towns 25 Figure 11: Site Environs of Sihora Town 26 Figure 12: Transmission network and Distribution network Site Photographs 31

M/s LN Malviya Infra Project Pvt. Ltd. Page 5

IEE Package 5B

Figure 13: Narmada River Basin Map 39 Figure 14: Google map showing ASI listed monument of Bhedaghat town 41 Figure 15: Google map showing ASI listed monument of Panagar town 41 Figure 16: MPUSIP Grievance Redress Mechanism 54

LIST OF APPENDIX

Appendix 1: REA Check list ...... 83 Appendix 2: National Ambient Air Quality Standards ...... 87 Appendix 3: Vehicle Exhaust Emission Norms...... 87 Appendix 4: National Ambient Air Quality Standards In Respect Of Noise ...... 88 Appendix 5: Stakeholder Consultation photographs ...... 88 Appendix 6: Extract From Construction & Demolition Management Rules, 2016 ...... 91 Appendix 7: Salient Features Of Major Labor Laws Applicable To Establishments Engaged In Construction Of Civil Works ...... 97 Appendix 8: Sample Grievance Registration Form ...... 99 Appendix 9: Sample Outline Spoils (Construction Waste) Management Plan ...... 100 Appendix 10: Sample Outline Traffic Management Plan...... 101 Appendix 11: Drinking Water Standards...... 108 Appendix 12: Sample Environmental Site Inspection Report...... 111 Appendix 13: Quarterly Reporting Format For Assistant Safeguards Officer ...... 114

M/s LN Malviya Infra Project Pvt. Ltd. Page 6

IEE Package 5B

I. EXECUTIVE SUMMARY

1. Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as ‗the Project‘. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Housing Department (UDHD) shall be the executing agency for the Project.

2. The Project components are as follows:

(i) Component 1: Improvements to water supply and sewerage services in identified towns  Continuous, pressurized, safe and sustainable drinking water through private household metered connections to 350,000 households with about 1.7million population resident in sixty-four towns in the State of Madhya Pradesh in Central India; and  Sewage and storm water collection and treatment services proposed initially in two (2) identified towns (Khajuraho and Rajnagar) servicing about 42,000 population resident in 8000 households;

(ii) Component 2: Institutional Strengthening  Capacity Building of implementing agencies (IAs), participating Urban Local Bodies (ULBs) and service utilities in contract management and service delivery for ensuring long term sustainability of services;  Setting up of geographic information system (GIS) based water and sanitation asset management and service delivery monitoring; and  Structured behavioral change campaigns to ensure the improvement in public health and cost recovery of service delivery.

(iii) Component 3: Project Management and Administration Support. This component will support the smooth and effective implementation and operation of the Project which includes expert support in Project design and implementation (design, procurement and Contract and Project Management, safeguards etc.), and project administration through Executing and Implementing Agencies.

3. The key outcome envisaged from the project is ―effective urban water service delivery model rolled out in selective urban clusters of the State with the objective of achieving the following performance indicators by the year 2022.

4. The Subproject. Katangi, Bhedaghat, Majholi, Panagar, Patan, and Sihora are located in the and Tendukheda is located in the Damoh District in the central part of Madhya Pradesh state. These are small towns having the status of Municipal Council (Nagar Parishad) and population as per 2011 census was: Katangi- 19040, Bhedaghat-6657, Majholi- 13210, Panagar-27932, Patan-14624, Sihora- 44048 and Tendukheda- 14399. Improvement of water supply in these seven towns will be implemented under a single Design-Build- Operate (DBO) contract package. The objective of the subproject is to achieve safe and sustainable water services both in terms of services to customers, cost recovery, providing 100% coverage with continuous, pressurized and safe drinking water services and achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency. The subproject includes the following civil works.

5. Katangi, Patan, Majholi, Sihora, Bhedaghat, Panagar and Tendukheda town is having acute water problem. Reliable source for Panagar and Bhedaghat town is River Narmada near

M/s LN Malviya Infra Project Pvt. Ltd. Page 7

IEE Package 5B

Jabalpur. Reliable source for Patan town is River Narmada. Both towns are approximately 25 km from Jabalpur. Sihora is approximately 25 km from Panagar, Majholi is approximately 20 km from Sihora, Katangi is 20 km from Majholi and Tendukheda is nearly 20 km from Patan. A common scheme for all these towns is framed from the river Narmada. Due to common scheme framed; storage structure cost & intake structure is avoided.

6. There are mainly two surface sources Hiren and Narmada River near the cities. Hiren river is small stream and has not sufficient flow. Waste water of Jabalpur through Pariat nala is also discharging into it ; making Hiren River further polluted. Looking to the contour profile of the river Hiren the storage by constructing weir will not be able to fulfill the water demand of the towns included in the Group; the storage structure cost will be very high if the independent weirs are constructed for each towns. Narmada River is perennial and dependable water source and has sufficient flow to cater the total water demand of 23.32 MLD for intermediate year 2033 and 27.93 MLD of ultimate year 2048 for population of Bhedaghat, Katangi, Patan, Majholi, Panagar, Sihora and Tendukheda Nagar Parishad. A common intake well of 10 m dia. and 14m height is proposed in the bank of Narmada River at Bhedaghat to draw the total water demand 27.93 MLD for all these cities with suitable pumping arrangement. There is no Water Treatment plant in any one of the city.

7. A common WTP for all these cities having capacity of 31.00 MLD considering 22 Hrs. of pumping has been proposed for the ultimate year of 2048 at Bhedaghat. Raw water will be pumped from the Narmada River and supplied to proposed common water treatment plant by 600 mm dia. 330 m long of DI K9 pumping main, where raw water will be treated. After treatment from WTP clear water will be stored in 11nos. existing of total capacity 2,773 KL and 12 nos. proposed OHT of total capacity 5,855 KL by pumping main of 153,166 m long 100 mm- 600 mm dia. DI K9 for Katangi, Patan, Majholi, Sihora, Bhedaghat, and Panagar Nagar Parishad. Condition of existing OHTs is structurally good and is taken into account in proposed water supply scheme. Presently distribution line is not 100 % covered Distribution line is buried under existing road and it is undersized, low pressure and also have leakages problem. Therefore it is need to propose new distribution line in these cities. There are no SCADA systems. SCADA system is proposed to monitor and control entire sites or complexes of systems spread out over large areas. This will be of immense help in maintaining the operations of motor, pumps; valves and specials and maintaining the levels of service reservoirs and hence the distribution system. There is also provision of District Metered Area (DMA) in order to monitor the level of leakage etc.

8. Screening and assessment of potential impacts. ADB requires the consideration of environmental issues in all aspects of the Bank‘s operations, and the requirements for environmental assessment are described in ADB‘s Safeguard Policy Statement (SPS), 2009. As per the GoI EIA Notification, 2006, these subprojects do not require EIA study or environmental clearance. The potential environmental impacts of the subproject have been assessed using ADB Rapid Environmental Assessment Checklist for Water Supply. Then potential negative impacts were identified in relation to pre-construction, construction and operation of the improved infrastructure.

9. Categorization. Based on results of the assessment and ADB SPS, the subproject is classified as environmental Category B, i.e., the subproject is judged to be unlikely to have significant adverse environmental impacts. An initial environmental examination (IEE) is required to determine whether significant environmental impacts warranting an environmental impact assessment are likely. 10. Aim of this IEE is to (i) provide critical facts, significant findings, and recommended actions; (ii) present the national and local legal and institutional framework within which the environmental assessment has been carried out; (iii) provide information on existing geographic, ecological, social and temporal context including associated facilities within the subproject‘s area of influence; (iv) assess the subproject‘s likely positive and negative direct

M/s LN Malviya Infra Project Pvt. Ltd. Page 8

IEE Package 5B and indirect impacts to physical, biological, socioeconomic and physical cultural resources in the subproject‘s area of influence; (v) identify mitigation measures and any residual negative impacts that cannot be mitigated; (vi) describe the process undertaken during project design to engage stakeholders and the planned information disclosure measures and the process for carrying out consultation with affected people and facilitating their participation during project implementation; (vii) describe the subproject‘s grievance redress mechanism for resolving complaints about environmental performance; (viii) present the set of mitigation measures to be undertaken to avoid, reduce, mitigate, or compensate for adverse environmental impacts; (ix) to describe the monitoring measures and reporting procedures to ensure early detection of conditions that necessitate particular mitigation measures; and (x) identify indicative costs and who is responsible for carrying out the mitigation and monitoring measures.

11. Description of the Environment. Project area mostly comprises urban areas, agricultural areas of Bhedaghat, Katangi, Majholi, Panagar, Patan, Sihora and Tendukheda. Extent of forest areas in the project area is very limited, and none of the project components are located in the forest areas, except CWRM from Patan to Tendukheda towns. In Bhedaghat, Open forest areas are located near the source, but none of the proposed project components comes under forest area. These are open forests with shrubs and bushes, and trees. Flora in that area consist of mixed forest, bamboo, teak, sal etc. Katangi- Tala reserve forest located in the North-east direction of Katangi town approx. 2 km from the town, none of the project components comes under these. Majholi- There is an Open mixed forest in the South-west direction of Majholi town, Flora in that area consists of mixed forest, mainly sal etc., none of the project components comes under these. Panagar- Bohra Reserve forest and Open mixed forests are located approx. 5 km from the Panagar town, in the Southern- eastern skirts, but none of the proposed project components comes under these forests. Sihora- An area east of Sihora around villages Maragarh, Kurro etc. is occupied by the Maragarh reserved Forest. Bohra Reserve forest and Open mixed forests are located approx. 12 km from the Sihora town, in the Southern direction from the town, but none of the proposed project components comes under these forests. Patan and Tendukheda- Mahguwan and Sahajpur Reserve forest area comes between Patan and Tendukheda Towns. The Clear water Rising main from Patan to Tendukheda will be laid along a road, that comes under Forest areas. The pipeline will be laid in the road right of way, and will not encroach into the forest habitat.

12. For the proposed Group WSS water will be sourced from Narmada River, which is a largest river of MP. The requirement of towns is miniscule in comparison with the river flow. WRD permission for abstraction from the river is in process. PMU has already discussed with the WRD, and the permission is likely to be issued soon. Bhedaghat and Panagar towns comes under ASI protected monuments; Although none of the components are located within the protected monuments, WTP (in Bhedaghat town) and distribution lines works (for both the towns) will located within the 300 m around the monuments . Given the minimal excavation (0.4 m wide and 0.7 m deep), there will be no risk to any structure. Nevertheless, the works will be implemented only after due permission of ASI and also the construction methodology will be discussed with the ASI. For chance finds, works will be observed by a person with archeological background.

13. Potential environmental impacts. The subproject area will not arise any significant adverse impacts due to: (i) small size population and their water demand, (ii) components proposed in the schemes are of comparatively is of small quantities & their effect will be locally which is manageable and controllable and (iii) predicted impacts are site-specific and likely to be associated with the construction process and are produced because the process is invasive, involving excavation and earth movements.

M/s LN Malviya Infra Project Pvt. Ltd. Page 9

IEE Package 5B

14. Environmental impacts arises due to the project design or because of the locations chosen for the project components are not significant. The proposed water supply schemes include design of new water source which is the nearest surface water body. It is assessed to be unlikely to have any significant issue of source sustainability. Water quality is good and there are no potential pollution sources in the vicinity that could affect the water quality. Although none of the components are located within the forest except CWRM from Patan to Tendukheda towns, conduct of construction works and presence of workers, vehicles may damage/disturb the sensitive areas. Necessary precautionary measures are suggested to avoid any impacts.

15. By the time of execution phase, potential negative impacts may arise from disturbance of residents, businesses, increase in traffic, increase in noise level and dusts and the need to dispose moderate quantities of waste soil during construction phase and generation of sludge from the WTP during operation and maintenance phase. However, there are well-developed methods for mitigation, minimization to acceptable levels are proposed here.

16. Environmental Management Plan As a part of mitigate measures in order to achieve acceptable levels in the negative impacts, an environmental management plan (EMP) has been proposed. All the locations are selected considering the minimum adverse environmental affects. These include (i) locating facilities on government-owned land to avoid the need for land acquisition and relocation of people; and (ii) laying of pipes in RoW alongside main/access roads, to reduce acquisition of land and impacts on livelihoods specifically in densely populated areas of the towns.

17. The EMP given here includes the design measures for (i) safe disposal of sludge coming out of wash water tanks from WTP to reduce effluent (ii) energy efficient pumping equipment and (iii) quick leak detection and rectification to save the resources, etc. During execution phase, the EMP includes mitigation measures such as (i) implementation of traffic management plan in coordination with local traffic police to minimize traffic impacts (ii) awareness campaigns and consultations to inform residents and businesses of potential disturbances; (iii) provision of walkways and planks over trenches to ensure access will not be impeded; (iv) use of noise-dampening measures in areas with sensitive receptors such as hospitals, schools, places of worships and other silence-zones; (v) use of dust-suppression methods such as watering and/or covering of stockpiles; and (vi) finding beneficial use of excavated materials to extent possible to reduce the quantity that will be disposed off. As for the O&M phase, facilities will need to be repaired from time to time, but environmental impacts will be much less than those of the construction period as the work will be infrequent, affecting small areas only. The design of the WTP includes dewatering and drying areas as part of sludge management. The EMP includes mitigation measures and monitoring plan to ensure compliance to environmental standards during O&M phase.

18. The EMP will guide the environmentally-sound construction of the subproject and ensure efficient lines of communication between Madhya Pradesh Urban Development Company (MPUDC), project management unit (PMU), project implementing unit (PIU), consultants and contractors. The EMP will (i) ensure that the activities are undertaken in a responsible non-detrimental manner; (i) provide a pro-active, feasible and practical working tool to enable the measurement and monitoring of environmental performance on site; (ii) guide and control the implementation of findings and recommendations of the environmental assessment conducted for the subproject; (iii) detail specific actions deemed necessary to assist in mitigating the environmental impact of the subproject; and (iv) ensure that safety recommendations are complied with. The EMP includes a monitoring program to measure the environmental condition and effectiveness of implementation of the mitigation measures.It will include observations on- and off-site, document checks, and interviews with workers and beneficiaries.

M/s LN Malviya Infra Project Pvt. Ltd. Page 10

IEE Package 5B

19. The contractor will be required to submit to PMU, for review and approval, a site environmental plan (SEP) including (i) proposed sites/locations for construction work camps, storage areas, hauling roads, lay down areas, disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following the approved EMP; (iii) monitoring program as per SEP; and (iv) budget for SEP implementation. No works are allowed to commence prior to approval of SEP. A copy of the EMP/approved SEP will be kept on site during the construction period at all times. The EMP included in the bid and contract documents. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance. 20. Consultation, disclosure and grievance redress mechanism. The stakeholders were involved in developing the IEE through discussions on-site and public consultation at several places in the towns, after which views expressed were incorporated into the IEE and in the planning and development of the project. The IEE will be made available at public locations and will be disclosed to a wider audience via the ADB, MPUDC and PMU websites. The consultation process will be continued and expanded during project implementation to ensure that stakeholders are fully engaged in the project and have the opportunity to participate in its development and implementation. A grievance redress mechanism is described within the IEE to ensure any public grievances are addressed quickly. 21. Implementation Arrangements. Urban Development and Housing Department (UDHD) of Government of Madhya Pradesh is the Executing Agency and Madhya Pradesh Urban Development Company (MPUDC) is the Implementing Agency. Project Management Unit (PMU) attached to MPUDC is responsible for implementation, and will be supported by Program Implementation Units (PIUs). Several teams of Design Consultants, and a Program Management Consultant (PMC),will support PMU & PIUs. Infrastructure will be designed, built, and operated by DBO contractor for 10 years, after which it will be transferred to ULBs. Project Officer (Environment) at PMU and Assistant Safeguard Officer (ASO) at each of the PIU will be responsible for environment safeguards tasks, and will be supported by PMC. Contractor personnel will include an Environment, Health and Safety (EHS) supervisor. 22. Monitoring and Reporting. The PMU and PMC will be responsible for monitoring. The PMC will submit quarterly and semi-annual monitoring reports to PMU, and the PMU will review and send the semi-annual monitoring reports to ADB. ADB will post the environmental monitoring reports on its website.Conclusions and Recommendations. The subproject is therefore unlikely to cause significant adverse impacts. The potential impacts that are associated with design, construction and operation can be mitigated to standard levels without difficulty through proper engineering design and the incorporation or application of recommended mitigation measures and procedures. Based on the findings of the IEE, there are no significant impacts and the classification of the project as Category ―B‖ is confirmed. No further special study or detailed environmental impact assessment (EIA) needs to be undertaken to comply with ADB SPS (2009) or GoI EIA Notification (2006). Project will require permission of Water Resources Department (WRD) for water abstraction from Narmada River, intake construction, Forest Department for laying CWRM from Patan to Tendukheda, ASI permission for Bhedaghat and Panagar towns and consent of Madhya Pradesh Pollution Control Board (MPPCB) for WTP. These permissions/approvals shall be obtained prior to award of contracts. 23. This IEE will be updated during the detailed design stage by the DBO contractor to reflect any changes, amendments and will be reviewed and approved by PMU.

M/s LN Malviya Infra Project Pvt. Ltd. Page 11

IEE Package 5B

II. INTRODUCTION

A. Background 1. Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as ‗the Project‘. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Housing Department (UDHD) shall be the executing agency for the Project.

2. The Project components are as follows:

(i) Component 1: Improvements to water supply and sewerage services in identified towns  Continuous, pressurized, safe and sustainable drinking water through private household metered connections to 350,000 households with about 1.7million population resident in sixty-four towns in the State of Madhya Pradesh in Central India; and  Sewage and storm water collection and treatment services proposed initially in two (2) identified towns (Khajuraho and Rajnagar) servicing about 42,000 population resident in 8000 households;

(ii) Component 2: Institutional Strengthening  Capacity Building of implementing agencies (IAs), participating Urban Local Bodies (ULBs) and service utilities in contract management and service delivery for ensuring long term sustainability of services;  Setting up of geographic information system (GIS) based water and sanitation asset management and service delivery monitoring; and  Structured behavioral change campaigns to ensure the improvement in public health and cost recovery of service delivery.

(iii) Component 3: Project Management and Administration Support. This component will support the smooth and effective implementation and operation of the Project which includes expert support in Project design and implementation (design, procurement and Contract and Project Management, safeguards etc.), and project administration through Executing and Implementing Agencies.

3. The key outcome envisaged from the project is ―effective urban water service delivery model rolled out in selective urban clusters of the State with the objective of achieving the following performance indicators by the year 2022.

(i) Access to piped water supply coverage increased to 95% of the households from 33% in 2015 in 64 towns; (ii) Women's drudgery for fetching water reduced by 80% (from spending an average of 55 minutes in 2015 to 10 minutes); (iii) Coverage of households with access to improved sanitation systems increased to 80% from 30% in 2015;

M/s LN Malviya Infra Project Pvt. Ltd. Page 12

IEE Package 5B

(iv) Wastewater collection and/or safe sanitation service coverage increased to at least 80% of the households from 0% in 2015 in two towns; (v) Incidence of water logging/flooding reduced to two incidents per annum in four towns; and (vi) Women access to functioning sanitation systems increased to 95% from 25% in 2015 (in poor settlements) in four towns

4. The key outputs envisaged from the project are:

(i) Output 1: Water supply infrastructure improved in 64 project towns and flood and sanitation infrastructure improved in two project towns with the following measurable indicators:  Improved water supply capacity of 186ml/day installed in 64 towns;  4,000 km water supply networks installed in 64 towns;  350,000 households provided with metered house connections including 100 government schools;  8 MLD sewage or septage treatment plants constructed; and  Installation of 120 km sewer and drainage mains and networks.

(ii) Output 2: Sustained urban infrastructure operation and management

 23 performance-based contract (PBC) operation and maintenance (O&M) water supply contracts for 64 ULBs signed and operated;  ULBs institute volumetric water charges for recovery of water service O&M costs  ULBs‘ water tariff collection ratio improved to 90% from 50% in 2014 based on the water meters‘ readings  100% operating cost recovery (excluding debt service) achieved;  GIS system established for effective O&M of water services

5. The subproject towns Katangi, Bhedaghat, Majholi, Panagar, Patan, and Sihora are located in the Jabalpur District and Tendukheda is located in the Damoh District and in the central part of Madhya Pradesh state and improvement of water supply in these four towns is one of the subprojects proposed under MPUSIP. The objective of the subproject is to achieve safe and sustainable water services both in terms of services to customers, cost recovery and conservation of precious water resources. The subproject envisages providing 100% coverage of population with continuous, pressurized and safe drinking water services and achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency. The subproject includes civil works (raw and clear water transmission, over head tanks, distribution network, consumer connections and flow meters), project implementation and management, and non-physical investments. A detailed description of the components is provided in Section III.

B. Purpose of this IEE Report

24. ADB requires the consideration of environmental issues in all aspects of the Bank‘s operations, and the requirements for environmental assessment are described in ADB‘s Safeguard Policy Statement (SPS), 2009. The potential environmental impacts of the subproject have been assessed using ADB Rapid Environmental Assessment Checklist for Water Supply (Appendix 1). Then potential negative impacts were identified in relation to pre- construction, construction and operation of the improved infrastructure, and results of the assessment show that the subproject is unlikely to cause significant adverse impacts. Thus, this initial environmental examination (IEE) has been prepared in accordance with ADB SPS‘s requirements for environment category B projects

M/s LN Malviya Infra Project Pvt. Ltd. Page 13

IEE Package 5B

25. To understand the environment-related aspects of the project, a detailed Environmental Analysis and Assessment study is required. The study will involve collection and analysis of information regarding the environmental issues related to the project and preparation of an Initial Environmental Examination (IEE) and Environmental Management Plan (EMP), to be duly integrated in the overall design of the project. The IEE study is expected to focus on the positive health and environmental benefits, through supply of safe drinking water and creation of integrated sanitary conditions in the project area/region. The proposed assessment study will suggest several environmental mitigation measures to be included in the project design, due to which the project is expected to have a net positive benefit for the people in the project area.

C. Report Structure 26. This Report contains the following nine (10) sections:

(i) Executive summary; (ii) Introduction (iii) Description of the project (iv) Policy, legal and administrative framework (v) Description of the environment; (vi) Anticipated environmental impacts and mitigation measures; (vii)Public consultation and information disclosure; (viii) Grievance redress mechanism; (ix) Environmental management plan, and (x) Conclusion and recommendation

M/s LN Malviya Infra Project Pvt. Ltd. Page 14

IEE Package 5B

III. DESCRIPTION OF THE PROJECT

A. Project Area 27. Katangi, Bhedaghat, Majholi, Panagar, Patan, and Sihora are located in the Jabalpur District and Tendukheda is located in the Damoh District in the eastern part of Madhya Pradesh state. These are small towns having the status of Municipal Council (Nagar Parishad) and population as per 2011 census was: Katangi- 19040, Bhedaghat-6657, Majholi-13210, Panagar-27932, Patan-14624, Sihora- 44048 and Tendukheda- 14399.

Figure 1: MP State Map with subprojects local towns

M/s LN Malviya Infra Project Pvt. Ltd. Page 15

IEE Package 5B

B. Existing Water Supply Situation 1. Katangi 28. Water supply is one of the most critical and important basic urban services. As water is a scarce commodity and the study area has limited water aquifer within its boundary, therefore water supply is a crucial urban service that needs special attention. In Katangi the ground water recharge is very limited and therefore very less ground water is available in the town area. Ground water supplied from tube-well is the main source of water supply in town.

29. Katangi is predominantly dependent on ground water source for water supply. Tube wells are the major source of water supply in this Town. At present there are 10 Tube wells in the town. Direct pumping is in practice for storage and distribution of water supply. Water is supplied through tankers to the areas where water supply is scarce and areas not covered with distribution network. Currently the water supply in Katangi is approximately 0.60 MLD. The details are shown in the following table.The available data only indicates the total water storage capacities at town level. However, it does not provide details on the quantity of water supplied at ward level. Thus, the analysis to understand the services at ward level is difficult. Presently there are three ELSR's available for water storage. The capacities of ELSR's are 0.15 ML and 0.2 ML and 0.25 ML.

30. The existing water distribution system in the town is very old and is connected at various places with new pipelines. A pipes with diameters ranging from 50 mm to 200 mm (50 mm, 80mm, 100 mm, 150 mm, 200 mm) form majority of the water supply network. About 16 km of length of pipeline is laid for distribution system and it accounts to 65 per cent of the existing road length. The details of the water supply distribution system given in the following table no.1 Table 1: Details of Rising main and Distribution network Pipe Distribution main details Percentage of Material coverage network GI, CI 50 mm to 200 mm (50 mm, 100 mm, 150 mm, 200 mm) 65% Source: Nagar Parishad Katangi

2. Patan 31. Patan is predominantly dependent on ground water source for water supply. Presently, water is drawn from a depth of 150 – 200 meter. Direct pumping is in practice for storage and

M/s LN Malviya Infra Project Pvt. Ltd. Page 16

IEE Package 5B distribution of water supply. As per the assessment made by the officials at Nagar Parishad of Patan, there are 19 tube wells present in the town. Out of these, 2 tube wells are directly connected to ELSR's and remaining 17 are connected to distribution network. Water is supplied through tankers to the areas where water supply is scarce and areas not covered with distribution network. Currently the water supply in Patan is approximately 0.88 MLD. The Quality of the water being supplied is as per drinking water standards. Currently the Nagar Parishad is supplying water for duration of 1hour; on the average the Nagar Parishad is able to maintain a Per Capita Supply of 48LPCD as against the requirement of 70 LPCD.

32. The existing water distribution system in the town is very old and is connected at various places with new pipelines. About 10.5 km of length of pipeline is laid for distribution system and it accounts to 47 per cent of the existing road length. The details of the water supply distribution system given in Table 2. Table 2: Details of Distribution system Pipe Material Distribution main details Percentage of coverage network ACP 200 mm - 250 mm 05% GI 150mm- 200mm 42% Source: Nagar Parishad Patan 3. Majholi 33. Tube wells are the major source of water supply in this town. There is also surface water source which is Suhar river, but this is not major source. At present there are 11 Tube wells present in the town. Direct pumping is in practice for storage and distribution of water supply. Water is supplied through tankers to the areas where water supply is scarce and areas not covered with distribution network. Currently the water supply in Majholi is approximately 0.70 MLD. The available data only indicates to total water storage capacities at town level. However, it does not provide details on the quantity of water supplied at ward level. Thus, the analysis to understand the services at ward level is difficult. Presently there are three ELSR's available for water storage of total capacity 0.625 ML. Two ESR of 3.2 lac liter & 1.8 lac liter are not in use primarily because there is no water available and also PHE department has not handed over yet officially. One of them is also leaking but it can be repaired.

34. The existing water distribution system in the town is old and is connected at various places with new pipelines. GI & ACP pipes with diameters ranging from 50 mm to 150 mm 0f 15000 m length of the water supply network. The details of the water supply distribution system given in the following Table no. 3. Table 3: Details of Distribution system Pipe Material Distribution main details Percentage of coverage network GI, ACP 50 mm to 150 mm (50 mm, 55% 80mm, 150 mm) Source: Nagar Parishad Majholi

4. Sihora 35. The current water supply to the Nagar Parishad is from the Hiran River, from an intake well cum raw water pump house situated at a distance of 180 m towards downstream of Sihora Majhgawa road Way Bridge. The diameter of intake well is 6 m and height 18.0 m above bed level. The raw water is conveyed to the water treatment plant of 4 MLD capacity located about 500m away from right bank of Hiran River. The town is being supplied with around 2.0 MLD of water every day, which is currently insufficient to address the overall requirement of the town. The Quality of the water being supplied is as per drinking water standards. Currently the Nagar Parishad is supplying water for duration of 1 hour in the

M/s LN Malviya Infra Project Pvt. Ltd. Page 17

IEE Package 5B morning and 1 hr. in the evening; on the average the Nagar Parishad Supplies only 36 LPCD water.

36. The treated water is being delivered by three Service Reservoir of 200 KL, 400 KL and 200 KL capacities which are located at ward no.14, ward no.18 and ward no.04 respectively. These reservoirs were designed for minimum residual pressure of 7.0 m. The ward 11 (625 KL) reservoir is badly damaged in earthquake 1997. With the existing system on the average the Nagar Parishad is able to maintain a Per Capita Supply of 36LPCD as against the requirement of 135 LPCD. Around 157 no. of hand pumps are functioning in the Nagar Parishad from which additional water is being tapped daily for other than drinking purpose. Table 4: Details of Distribution system Pipe Material Distribution main details Percentage of coverage network GI 40mm to 150mm CI 75 mm, 100 mm, 150 mm, 65% 200mm, 250mm Source: Nagar Parishad Parishad Sihora

5. Bhedaghat 37. Bhedaghat is dependent on both ground & surface source for water supply. The water is supplied through pipes at spot source from the tube wells. Around 0.07 MLD water is extracted from ground water. Presently, the town is drawing 30% of supplied water every day from the ground source. Direct pumping is in practice for storage and distribution of water supply. Water is supplied through tankers to the areas where water supply is scarce and areas not covered with distribution network. There are 4 tube wells, 36 hand pumps and 28 stand posts in the town.As River Narmada passing from the town, water is pumped from river at various points (Gopalpur, paramhans ghat and banerji ghat) by inserting motor. Town receives around 0.13 MLD water from surface source. At present total water supplied to the town is 0.20 MLD from both ground and surface sources at the rate of 44 LPCD.

38. The existing water distribution system in the town is very old and is connected at various places with new pipelines. GI pipes with diameters ranging from 1.5 inch to 3.0 inch form majority of the water supply network. Around 12 km of length of pipeline is laid for distribution system and it accounts to 40 per cent of the existing road length.

6. PANAGAR 39. Panagar is dependent on ground source for water supply. Most of the residents of the town obtain their water from an improved point source, such as a well or tube well. Around 1.2 MLD water is extracted from ground water. In available ground sources, town has 25 tube wells from which 23 are functioning. Apart from these, town has 118 hand pumps and 310 stand posts which are used for both drinking and non drinking purposes. The average water supply in Panagar after all transmission and distribution losses(10% ) is around 1.2 MLD at the rate of 39 LPCD. No proper scientific water treatment is being done at present. only primary informal treatment is being done at the source level (i.e. at the tube well points) the water being supplied in the distribution nearly of the same quality.

40. At present 1.20 MLD of water is being supplied in the Nagar Palika from 23 Nos. of tube wells functioning in the Nagar Palika. The water drawn from the tube wells is directly pumped to the existing tank or directly distributed to the Nagar Palika after initial disinfection. Around 112 nos. of hand pumps are functioning in the Nagar Palika from which additional water is being tapped daily for other than drinking purpose. Daily the ULB is supplying water

M/s LN Malviya Infra Project Pvt. Ltd. Page 18

IEE Package 5B for duration of 2 Hours; on the average the Nagar Palika is able to maintain a Per Capita Supply of 39 LPCD as against the requirement of 70 LPCD.

41. The existing water supply network coverage is around 68% with a network consisting of various diameter sizing pipes ranging from 150 mm dia. to 50 mm dia. GI & CI Pipes and the distribution system are also comprising of 80 mm dia. AC pipes and 50mm dia. G.I pipes

7. TENDUKHEDA 42. Sources of water supply. The main source of water supply in Tendukheda town is ground water. There are 12 tube wells in the whole town which are serving as a source of supply ground water. Total production of these deep tube wells is 0.72 MLD / day. Water is supplied for 45 minutes to 1 hour daily. Direct pumping is in practice for storage and distribution of water supply. Water is supplied through tankers to the areas where water supply is scarce and areas not covered with distribution network. The available data only indicates the total water storage capacities at town level. However, it does not provide details on the quantity of water supplied at ward level. Thus, the analysis to understand the services at ward level is difficult. Presently there is one ELSR available for water storage. The storage capacity of ELSR is 90 KL.

43. Water is partly distributed through gravity from distribution reservoir. The reason behind such distribution pattern is shortage of overhead reservoirs and inequitable pressure head, due to the undulating terrain. The total number of household service connections is 2007. There are no metered connections in the town. Apart from this, 86 hand pumps (30 nos. only working) and 150 Public Stand Posts are catering to water supply.

C. Proposed Project 44. As the water table is depleting all over, therefore, now it is not a reliable source for a permanent scheme in all the four towns. As part of this project, it is proposed to develop comprehensive water supply schemes in each of the four project towns. Proposals include new reliable water sources, water treatment plants, over head tanks, energy efficient pumping machinery, raw & clear water transmission mains and distribution network covering the whole town. Project will also provide consumer connections with flow meters. Bulk flow meters are proposed at strategic locations to monitor the system performance efficiency.

45. Sihora, Katangi, Panagar, Patan, Majholi, Bhedaghat and Tendukheda (Damoh) town is having acute water problem. Sustainable source are not available near to these towns. Reliable source for Panagar, Bhedaghat town is River Narmada near Jabalpur. Reliable source for Patan town is River Narmada. Both towns are approximately 25 km from Jabalpur. Sihora is approximately 25 km from Panagar ,Majholi is approximately 20 km from Sihora, Katangi is 20 km from Majholi and Tedukheda is nearly 20 km from Patan.

46. A common scheme for all these towns including Tendukheda can be framed from the river Narmada. If combined scheme is framed; then storage structure cost & intake structure cost can be avoided. The feasibility & viability is worked out after survey & investigation.

Hence from the above facts it is justified that Narmada River is as final and common source for Katangi, Patan, Majholi, Sihora, Panagar, Bhedaghat and Tendukheda Nagar Parishad.

47. Intake: The common intake well is proposed for Katangi, Patan, Majholi, Sihora, Panagar, Bhedaghat and Tendukheda Nagar Parishad at Bhedaghat. At Bhedaghat in the bank of Narmada River, there is proposed R.C.C. intake well of 10 m diameter and 14 m height to collect and lift water up to treatment works. H.F.L. and River bed level is 368.00m

M/s LN Malviya Infra Project Pvt. Ltd. Page 19

IEE Package 5B and 355.97 m respectively. River bed is at 355.97 m keeping the invert level of intake well 1.0 m below the bed level of the river at 353.97 m. The pump floor (370.00 m) is kept as 2.0 m above the H.F.L. (368.00 m). The suction point (354.97) is kept as 1.0 m below from the River Bed Level and difference of pump floor level and river bed level is 14.03 m. The height of intake well works out to 14.03 m say 14.00 m and diameter of intake well has been decided 10 m on the basis of space required for housing three numbers each of 59 KW pumps. Detailed survey was conducted for selection of site. The selected site is nearest, and will have required quantity of water.

Figure 2: Google map showing ,Panagar, Sihora, Majholi, Katangi, Patan, Tendukheda Towns and River Narmada

48. Following Table 5 shows the proposed water supply systems along with nature and size of components in subproject towns. Figure 3 to Figure 7 show the proposed water systems, component layouts etc.

M/s LN Malviya Infra Project Pvt. Ltd. Page 20

IEE Package 5B

M/s LN Malviya Infra Project Pvt. Ltd. Page 21

Table 5: Proposed Water Supply Subproject Components Particulars Bhedaghat Katangi Majholi Panagar Patan Sihora Tendukheda I. Water demand 1 Base year (2016) 19.14 MLD 2 Commissioning 23.32 MLD year (2018.) 3 Design year 27.93 MLD (2048) II. Source 1 Alternatives Narmada River 1. Ground Water 1. Suhar River 1. Ground Water 1.Ground Water 1. Ground Water 1. Guraiya Nala 2. Hiran River 2. Ground Water 2. Narmada 2.Hiran River 2. Hiran River 2. Nargoa Talab 3. Narmada 3. Hiran River River 3.Narmada 3. Narmada River 3. Hiren River River 4. Narmada River 4. Narmada River River 2 Selected source Narmada River III. Proposed system 1 From source to Raw water abstraction from Narmada river → raw water transmission (pumping) → treatment → clear water transmission (pumping) → consumer supply storage → distribution → house connections with meters IV. Proposed components 1 Water intake A common intake well is proposed for Katangi, Patan, Majholi, Sihora, Panagar, Bhedaghat and Tendukheda Nagar Parishad at Bhedaghat. At Bhedaghat in the bank of Narmada River, there is proposed R.C.C. intake well of 10 m diameter and 14 m height. Location: Proposed Intake well located on Narmada River at Bhedaghat, in the southern side of the town in ward no. 4. 2 Pumping stations Three nos. vertical turbine type pump with 50% as standby is proposed at intake well. The discharge of each pump is (25.53 MLD) 259.22 LPS and head is 36.56 meter at intermediate stage Yr.2033. The rating of each pump is 58.92 KW (say 59.0 KW). Two nos. working and one pump will be as a standby. This will be replaced by 31 MLD or 311.62 LPS discharging capacity at 36.73 m head pumps of 71.5 KW in year 2048. The pumping is proposed for 22 hours. Location: At proposed intake well 3 Raw water Rising There will be common raw water rising main for Katangi, Patan, Majholi, Sihora, Bhedaghat, and Panagar city. The proposed raw water rising Main main is 330 m long 600 mm dia. DI K9 from proposed Intake well to proposed WTP. Location: Raw water pipeline will be laid underground from the intake well intake to WTP site along an existing road and some kuchha road. 4 WTP A common WTP for all these cities having capacity of 31.00 MLD considering 22 Hours of pumping has been proposed for the ultimate year of 2048 at Bhedaghat. (*31=27.93x24/22 pumping is done 22 hrs. instead of 24 hrs. resulting that capacity becomes 30.47 MLD say 31.00 MLD) Process/components (same for all towns): Coagulation &flocculation, sedimentation, rapid gravity filtration, chlorination, wash water IEE Package 5B

Particulars Bhedaghat Katangi Majholi Panagar Patan Sihora Tendukheda recovery, sludge drying beds, tube settlers & miscellaneous infra (compound wall, landscaping, lighting, rest rooms etc)

Location: On a government land (approx. 6 ha available) in southern outskirts of the town near the intake. 5 Sump Wells 850 KL of sump well is proposed at WTP for storing Clear water after treatment from WTP. OHT Two OHTs Proposed OHT Not applicable Three OHTs Not applicable Four OHTs Two OHTs proposed of 120 KL of proposed of proposed proposed of 1. 920 KL 1. 200 KL staging height capacity capacity 2. 1020 KL 12m 1. 200 KL 1. 300 KL 2. 225 KL 3. 630 KL 2. 700 KL 4. 620 KL 2. 325 KL 3. 600 KL 6 Clear water R-1(WTP) to J-1(junction 1): 15816 m length and 600 mm dia. DI- K9 Pipe transmission J-1 to J-2 (Patan): 11539 m length and 200-250 mm dia DI- K9 pipe Patan to Tendukheda: 24387 m length and 150-250 mm dia DI- K9 pipe J-1 to J-4: 8576 m length and 600 mm dia DI- K9 pipe J-4 to J-5: 20401 m length and 250-300 mm dia DI- K9 pipe J-5 to Katangi OHTs: 2532 m length and 150 mm dia DI- K9 pipe J-5 to J-53 (Katangi to Majholi): 10544 m length and 250 mm dia DI- K9 pipe J-53 to Majholi OHTs: 6468 m length and 100-200 mm dia DI- K9 pipe J-4 to J-20 (towards Panagar Town) 14042 m length and 450-500 mm dia DI- K9 pipe J-20 to Clear water Sump Sihora: 25376 m length and 450 mm dia DI- K9 pipe Feeder Main for Panagar Town: 1591 m length and 150-200 mm dia DI- K9 pipe Feeder main for Sihora Town: 6253 m length and 200-300 mm dia DI- K9 pipe (for details of Junction see Figure 3), (for Location and layout details refer figure 6 and also figure 8 to 11) Total Length: 153166 m Length and 100- 600 mm dia pipe. 7 Distribution 24114 m – 110 30548 m – 110 31378 m – 110 42573 m – 110 21085 m – 110 81138 m – 110 mm 37196 m – 110 mm network mm dia HDPE mm to 250 mm mm to 250 mm mm to 250 mm mm to 280 mm to 250 mm HDPE to 250 mm HDPE pipes HDPE HDPE HDPE HDPE (75% pipes are of (79.4% pipes are of (75% pipes are (90% pipes are (79% pipes are (70% pipes are less than 110 mm less than 110 mm Location: Along of less than 110 of less than 110 of less than 110 of less than 110 dia Location: dia Location: Along the public roads in mm dia mm dia mm dia mm dia Along the public the public roads in Location: Along Location: Along Location: Along roads in the entire

M/s LN Malviya Infra Project Pvt. Ltd. Page 2

IEE Package 5B

Particulars Bhedaghat Katangi Majholi Panagar Patan Sihora Tendukheda the entire town. the public roads the public roads the public roads Location: Along town. the entire town. in the entire in the entire in the entire the public roads town. town. town. in the entire town. 8 Bulk flow meters Electromagnetic Bulk flow meter will be installed to monitor the bulk flow in the main components i.e. at the inlet of the raw water mains to know the quantity of water coming to the WTP, outlet of the clear water sump to know the quantity of water going for the distribution, outlet of the service reservoirs to know the quantity of water going in the distribution zone or DMA. This will help in maintaining the UFW in the limit and also equitable distribution of the water. 9 Consumer Domestic-21945 connects with Non-domestic- 370 meters

M/s LN Malviya Infra Project Pvt. Ltd. Page 3

Figure 3: Key Plan of Bhedaghat Group WSS

8,931m, 250 mm, J-5 to J-40 and 1,613 m, 250 mm, J-40 to J-53

3,098 m, 250 mm, J-42 to J-5

2,466 m, 250 mm, J-50 to J-41 and 2,279 m, 250 mm, J-41 to J-42 22,854 m, 450 mm

1,025 m, 250 mm J-47 to J-44 and 5,,861m 250 mm, J-44 to J-38 9,061 m, 300 mm, J-4 to J-34 and 3,497 m, 300 mm, J-37 to J-50 6,218 m, 200 mm 6,104 m, 500 mm, J-49 to J-47 J-4 to J-43 and 5,153 m, 500 mm, J-43 to J-52

1,524 m, 200 mm J-51 to J-49 1,137 m, 450 mm, J-52 to J-48 and 1,648, 450 mm, J- 3,252 m, 250 mm 8,576 m, 600 mm 48 to J-20 J-39 to J-51 J-1 to J-4

6,426 m, 250 mm J-1 to J-51

15,816 m, 600 mm R-1 to J-1

Figure 4: Proposed Intake and WTP Site at Bhedaghat

Figure 5: Intake Well Cross section

Figure 6: Transmission Network of Proposed Group WSS

Figure 7: Schematic Diagram of Jabalpur Group WSS

IEE Package 5B

IV. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK

A. ADB Policy

49. ADB requires the consideration of environmental issues in all aspects of ADB‘s operations, and the requirements for environmental assessment are described in ADB SPS, 2009. This states that ADB requires environmental assessment of all ADB investments.

50. Screening and categorization. The nature of the environmental assessment required for a project depends on the significance of its environmental impacts, which are related to the type and location of the project; the sensitivity, scale, nature, and magnitude of its potential impacts; and the availability of cost-effective mitigation measures. Projects are screened for their expected environmental impacts, and are assigned to one of the following four categories:

(i) Category A. Projects could have significant adverse environmental impacts. An EIA is required to address significant impacts. (ii) Category B. Projects could have some adverse environmental impacts, but of lesser degree or significance than those in category A. An IEE is required to determine whether significant environmental impacts warranting an EIA are likely. If an EIA is not needed, the IEE is regarded as the final environmental assessment report. (iii) Category C. Projects are unlikely to have adverse environmental impacts. No EIA or IEE is required, although environmental implications are reviewed. (iv) Category FI. Projects involve a credit line through a financial intermediary or an equity investment in a financial intermediary. The financial intermediary must apply an environmental management system, unless all projects will result in insignificant impacts.

51. Environmental management plan. An EMP, which addresses the potential impacts and risks identified by the environmental assessment, shall be prepared. The level of detail and complexity of the EMP and the priority of the identified measures and actions will be commensurate with the project‘s impact and risks.

52. Public disclosure. ADB will post the safeguard documents on its website as well as disclose relevant information in accessible manner in local communities:

(i) for environmental category A projects, draft EIA report at least 120 days before Board consideration; (ii) final or updated EIA and/or IEE upon receipt; and (iii) Environmental monitoring reports submitted by the implementing agency during project implementation upon receipt.

B. National Environmental Laws

53. Environmental Assessment. The GoI EIA Notification of 2006 (replacing the EIA Notification of 1994), sets out the requirement for Environmental Assessment in India. This states that Environmental Clearance (EC) is required for specified activities/projects, and EC must be obtained before any construction work or land preparation (except land acquisition) may commence. Projects are categorized as A or B1 or B2 depending on the scale of the project and the nature of its impacts. None of the components of this water supply subproject falls under the ambit of the EIA Notification 2006, and, therefore no category assigned, and thus no EIA study and EC required for the subproject.

M/s LN Malviya Infra Project Pvt. Ltd. Page 9

IEE Package 5B

54. Applicable environmental regulations. Besides EIA Notification 2006, there are various other acts, rules, policies and regulations currently in force in India that deal with environmental issues that could apply to infrastructure development. The specific regulatory compliance requirements of the subproject are shown in Table 6.

Table 6: Applicable Environmental Regulations Law Description Requirement Madhya Pradesh Prepared in accordance with the National Permission of WRD, State Water Water Policy, it states that ―for environmental GoMP: Policy, 2003 balance, skillful and planned management of  Construction of all types of developmental activities, Intake well on economic use on equitable basis and in view Narmada river of the prime importance of water for all (Bhedaghat Town) human and other living beings, an effective and sound water policy is necessary‖. Policy is detailed in 17 sections dealing with different aspects of water resources. No. 7 deals with Water Allocation Priorities, and according to which drinking water supply shall have the highest priority followed by irrigation, power, tourism, etc. Water Resource Department is nodal department for permitting different uses of water resources. Policy also states that ―clear provision for reservation of drinking water shall be made in irrigation projects‖ Water Act was enacted to provide for the prevention WTPs require CTE (Prevention and and control of water pollution and the (prior to start of Control of maintaining or restoring of wholesomeness of constriction) and CFO Pollution) Act of water, by Central and State Pollution Control (prior to start of 1974, Rules of Boards and for conferring and assigning to operation) from 1975, and CPCB/SPCBs powers &functions relating to MPPCB. amendments water pollution control. Application has to be Control of water pollution is achieved through submitted online at administering conditions imposed in consent http://www.mppcb.nic.in issued under to this Act. These conditions /xgn.html regulate the quantity and quantity of effluent, the location of discharge and the frequency of monitoring of effluents. Any component of the subproject having the potential to generate sewage or trade effluent will come under its purview. Such projects have to obtain Consent to Establish (CTE) & Consent to Operate (CTO) under Section 25 from Madhya Pradesh Pollution Control Board (MPPCB) Environment Emissions and discharges from the facilities Appendix 2 provides (Protection) Act, to be created or refurbished or augmented applicable standards for 1986 and CPCB shall comply with the notified standards ambient air quality. Environmental Appendix 3 provides Standards. vehicular emission

M/s LN Malviya Infra Project Pvt. Ltd. Page 10

IEE Package 5B

Law Description Requirement norms

Noise Pollution Rule 3 of the Act specifies ambient air quality Appendix4 provides (Regulation and standards in respect of noise for different applicable noise Control) Rules, areas/zones. standards. 2000 amended up to 2010. Municipal Solid Rules to manage municipal solid waste Solid waste generated Wastes generated; provides rules for segregation, at proposed facilities Management storage, collection, processing and disposal. shall be managed and Rules, 2016 disposed in accordance with the MSWM Rules Construction & Rules to manage construction & to waste Construction & Demolition resulting from construction, remodeling, demolition waste Waste repair and demolition of any civil structure. generated from the Management Rules define C&D waste as waste comprising project construction Rules, 2016 of building materials, debris resulting from shall be managed and construction, re-modeling, repair and disposed as per the demolition of any civil structure. rules (Appendix 6) Ancient The Act designates areas within 100 meters In the proposed Group Monuments and (m) of the ―protected monument/area‖ as WSS two towns i.e. Archaeological ―prohibited area‖ and beyond that up to 200 Bhedaghat and Sites and m as ―regulated area‖ respectively. No Panagar are famous Remains Act, ―construction‖ is permitted in the ―prohibited archeological place. 1958 and area‖ and any construction activity in the Works required for Ancient ―regulated area‖ requires prior permission of provision of public Monuments and the National Monuments Authority (NMA). water supply are Archaeological exempted from the Sites and regulated list of Remains ―construction works‖. (Amendment However, works near and Validation) the monuments (within Act, 2010 300 m) can only be conducted with prior permission of NMA. WTP site is located approx. 250 m away from Protected monument. Application has been submitted to ASI for NOC. The site selected is best suitable for proposed WTP and no other suitable government land is available in the town. Proposed land parcel is approx. 10.21 Ha, half of this area comes under 300 m dia and half comes outside the 300 dia. Hence, as mitigation measures during construction, it will ensured that only boundary wall of WTP is

M/s LN Malviya Infra Project Pvt. Ltd. Page 11

IEE Package 5B

Law Description Requirement constructed under 300 m and other components of WTP are constructed on the outer skirts of the plot. Forest Act, 1927 Acts empower the government to declare CWRM from Patan to and Forest forest area ( reserve,protected and village Tendukheda laying (Conservation) forest area) and regulation of activities within along the RoW of road, Act, 1980, the forests. Use of forest land for any non- but road comes under amended 1988 forest purpose and forest land conservation Forest department will follow the guidelines for ―Diversion of therefore prior forest lands for non-forest purpose‖ under permission from forest Forest (Conservation) Act 1980 department required for laying the pipe lines.

Labor Laws The contractor shall not make employment Appendix 7 provides decisions based upon personal applicable labor laws characteristics unrelated to job requirements. including amendments The contractor shall base the employment issued from time to time relationship upon equal opportunity and fair applicable to treatment, and shall not discriminate with establishments respect to aspects of the employment engaged in construction relationship, including recruitment and hiring, of civil works. compensation (including wages and benefits), working conditions and terms of employment or retirement, and discipline. The contractor shall provide equal wages and benefits to men and women for work of equal value or type.

55. ADB SPS Requirements. During the design, construction, and operation of the project the PMU and PIUs are required to apply pollution prevention and control technologies and practices consistent with international good practice, as reflected in internationally recognized standards such as the World Bank Group‘s Environment, Health and Safety Guidelines. These standards contain performance levels and measures that are normally acceptable and applicable to projects. When Government of India regulations differ from these levels and measures, the PMU and PIUs will achieve whichever is more stringent. If less stringent levels or measures are appropriate in view of specific project circumstances, the PMU and PIUs will provide full and detailed justification for any proposed alternatives that are consistent with the requirements presented in ADB SPS. International acceptable air and noise quality guidelines are provided below:

M/s LN Malviya Infra Project Pvt. Ltd. Page 12

IEE Package 5B

Table 7: WHO Ambient Air& Noise Quality Guidelines

M/s LN Malviya Infra Project Pvt. Ltd. Page 13

IEE Package 5B

V. DESCRIPTION OF THE ENVIRONMENT

A. Methodology Used for Baseline Study

56. Data collection and stakeholder consultations. Focused Group Discussion, field visits, site surveys and social surveys were conducted through the different wards covering every section of society was conducted and data collected and analyzed accordingly with respect to the proposed subproject sites and the with respect to the need of water supply in all the Seven towns here.

57. The survey broadly covered the following:

(i) Project details, reports, maps, and other documents prepared by technical experts of design consultant team. (ii) Discussions with technical experts, municipal authorities and relevant government agencies like WRD, Revenue Department, Forest Department, MPPCB, etc. (iii) Secondary data from previous project reports & published articles, if any, and (iv) Literature on land use, soil, geology, hydrology, climate, socioeconomic, and planning documents collected from Government agencies and websites.

58. Ocular inspection. Several visits to the project sites were made during IEE preparation period in 2016 to assess the existing environment (physical, biological, and socioeconomic) and gather information with regard to the proposed sites and scale of the proposed project. A separate socioeconomic study was conducted to determine the demographic information, existing service levels, stakeholder needs and priorities.

B. Baseline Environmental Profile

59. Following details presents the baseline environmental profile of subproject towns of Package 5B. It is organized in terms of physical, ecological, economical, and socio cultural resources.

M/s LN Malviya Infra Project Pvt. Ltd. Page 14

Table 8: Baseline Environmental Profile of towns

Baseline Bhedaghat Katangi Majholi Panagar Patan Sihora Tendukheda characteristic Location Bhedaghat is a Katangi town is a Majholi town is a Panagar is a city Patan town is a Sihora town is a Tendukheda a town with Nagar sub Tehsil sub Tehsil and a municipality Tehsil head Tehsil small town of Parishad status in headquarters in Headquarters in in Jabalpur quarter of Patan headquarters of Damoh district. Jabalpur district Katangi Tehsil of Sihora tehsil of district in the Tehsil of Jabalpur Jabalpur district in Tendukheda is in the state of Jabalpur district in Jabalpur district in Indian state of district in Madhya Madhya Pradesh. located on State Madhya Pradesh. Madhya Pradesh. Madhya Pradesh. Madhya Pradesh. Pradesh State. Geographically Highway number Bhedaghat town Geographically Geographically Geographically, Patan Sihora town is 12. It lies at is situated by the Katangi town is Majholi town is geographically lies located at 23° 28‘ latitudes 23° 23'59‘‘ Panagar lies 0 side of river located at 23° located at 23° 30' between 22 31‘ 48‘‘ North Latitude north, and Narmada. 27'49‘‘ North 0‘‘ North Latitude between 48‘‘ north latitude and 80° 7' 12‘‘ East longitudes 79° 23°9'58"N and 0 Geographically, Latitude and 79° and 79° 55' 12‘‘ and 79 25‘ 12‘‘ Latitude. 32'59‘‘east. 47'38‘‘ East East Latitude. 79°56'33"E. east Longitude. Bhedaghat lies Latitude. between 23°08‘N 79°48‘E, 23°13°N 79°80°E.

Connectivity Bhedaghat is The town is The town is Panagar is It is nearly 33 Km Sihora is well Tendukheda is situated on State situated on Road from Jabalpur and connected by Road connected to located at 25 km Highway 37 connecting Sihora situated on NH – around 285 Km and Rail. It is 42 district via State from Jabalpur connecting Gubra. The 7 connecting from the state Km from away from Highway 37, which and 5 km Jabalpur and distance from Nagpur – . Headquarter Jabalpur, located passes through the eastern side on Damoh. It is Jabalpur is around The distance Bhopal. The city is on the NH-7 and is town, and other the State located 38 km 47 km. Majholi from Jabalpur is well connected also connected by major district roads. Highway 12A from Jabalpur Town is located at about 16 Km. with Road. State railway section on Nearest Railway leading towards towards the North- distance of 30 The nearest Highway main Allahabad - Station is Jabalpur Bhopal- West and 22 km kmsfor Sihora. railway station is connecting Damoh Itarsi sector of at a distance of Jabalpur. North of Katangi. The nearest Deori which is — Jabalpur 37A WCR. 47.9 km. The Jabalpur (near to The nearest railway station is 1.6 km from the passes through nearest Airport is at railway station is Jabalpur, which is the city. The Jabalpur located at Bhedaghat) is Jabalpur, which is also a zonal head town on main nearest railway a distance of 57 well connected Allahabad – IEE Package 5B

Baseline Bhedaghat Katangi Majholi Panagar Patan Sihora Tendukheda characteristic by roads, rails also a zonal head quarter of central Itarsi sector of station is Jabalpur, km. and airways. quarter of Central west railways. The WCR. which is also a West Railways. nearest Airport is Zonal head National Highway-7 The nearest Jabalpur. quarter of Central passing through airport is around West Railways 50 km, which is the city links it located at with important Jabalpur City. neighboring cities like Nagpur, Raipur, Bhopal, Allahabad, Sagar etc.

Area & The area of the The area of the The area of the The area of the The municipal The area of the The area of the Population town is spread town is spread town is spread over town is spread over over in 16.44 Sq over in 1237.00 town is spread town is spread council was in 2302.00 Ha 10.00 Sq Km as Km as per 2011 Ha (12.37Sq Kms over in 629.00 over in 10.26 Sq constituted in the (23.02 Sq Km) as per 2011 data. data and mainly ) as per 2011 data Ha (6.29 Sq Km as per 2011 year 1981, with per 2011 data. Population of town divided in 15 and mainly divided Kms ) as per data. an area of 13.06 Population of town as per 2011 census wards. Population in three 2011 data. Population of sq. km and as per 2011 census was 14399. of town as per settlements. Population of town as per comprising of 15 was 44048. 2011 census was Population of town municipal wards. 6657. as per 2011 town as per 2011 census census was 2011 census was 27932. Population of 19040. was 13218. town as per 2011 census was 14324.

Topography Bhedaghat is Katangi Town Majholi Town is The topography In general Patan The remaining The topography of surrounded by which is located located on the of the town is flat. town has a Plain maximum area of the town is flat. It low, rocky and on the banks of Western bank of It is a plain area topography. The Tehsil all around is a plain area barren hillocks. Hiran River has a Suhar River and is situated between rich black cotton Sihora town is flat situated between Bhedaghat town hilly topography. surrounded by the Vindhya soil with its and cultivation the Vindhya

M/s LN Malviya Infra Project Pvt. Ltd. Page 16

IEE Package 5B

Baseline Bhedaghat Katangi Majholi Panagar Patan Sihora Tendukheda characteristic is encircled by Physio-graphically Hills. Kshetra and embanked fields land. Kshetra and hills. The red Jabalpur district Mahadev and which is the The slope is Mahadev and colour soil can be can be divided in 5 Mekal hills. The predominant towards South - Mekal hills. seen and shows natural regions. slope is towards feature of region. East to North - presence of Katangi lies in South-western Patan is situated West direction. laterite in the Haveli situated direction and the in a tract town. between Hiran drainage from consisting of most River and local Nalas fertile land and Bombay-Hawrah reaches Moti thickly populated railway line. Nala. in the District.

Soils & The red colour The soil strata in The soil strata in The soil strata in The soil strata in The soil strata in The soil strata in geology soil can be seen the town are the town are the town are mostly the town are mostly and shows mostly rich black the town are mostly rich black the town are rich black cotton rich black cotton presence of cotton soil with its mostly rich black cotton soil with its mostly rich soil with its soil with its laterite in the embanked fields cotton soil. embanked fields alluvial deposit embanked fields embanked fields town. Soil. Soil. black cotton soil. Soil. Soil.

Climate The climate of Jabalpur District M.P. characterized by a hot summer and general dryness except during the south west monsoon. The year may divided into four seasons. The cold season. December to February is followed by the hot season from march to about the middle of June. The period the middle of June to September is the south west monsoon season. October and November form the post mons oon or transition period. The average annual rainfall of Jabalpur District is 1279.50mm. Jabalpur received maximum rainfall received during south west monsoon period i.e. June to September. About 90% of the annual rainfall received during monsoon season. Only 10% of the annual rainfall takes place between October to May period. Thus surplus water for ground water recharge is available only during the south west monsoon period. The normal maximum temperature received during the month of December is 90C. The normal annual means maximum and minimum temperature of Jabalpur District is 32.10C & 18.30C respectively. During the south west monsoon season the relative humidity generally exceeds 87% (August month). In the rest of the year is drier. The driest part of the year is the summer season. When relative humidity‘s are less 27%. May is the driest month of the year. The wind velocity is higher during the pre-monsoon period as compared to post monsoon period. The maximum wind velocity 8.6 km/hr observed during the month of annual wind velocity of Jabalpur district is 5.3 km/hr.

M/s LN Malviya Infra Project Pvt. Ltd. Page 17

IEE Package 5B

Baseline Bhedaghat Katangi Majholi Panagar Patan Sihora Tendukheda characteristic Surface water The river Narmada Hiren River is Suhar is small There is Narmada Within the This area falls in Guraiya Nala is passes from the approximately 3 stream near the River municipality limit the Narmada basin. shallow and small town. It is km from the Majholi town. Flow approximately 25 there is no surface The Hiran is the stream. Flow of the Perennial River. Katangi town. in this stream km from the water source in main river, draining stream ceases in No storage River is shallow ceases after the Panagar town. It is Nagri. in this area. The the month of structure will be and small. Flow of rains are over. Perennial River. It is approximately slope of the river October & required. There is the river ceases in It is approximately 3 km from the bed is about 1 in November. already water the month of 18 km from the Patan town. River 1000, and it mostly Nargoa Talab:- supply from river November & Majholi. Hiren is a is shallow and flows through Recently WRD has Narmada. But December. There much bigger small. Flow of the alluvium deposits. constructed this there is no intake is Narmada River stream than the river ceases in the Besides these dam. The nalla well , water approximately 45 Suhar. month of there are number of closure for this dam treatment plant km from the There is Narmada November & streams flowing has been done on and a dedicated Katangi town. It River December. nearby the Sihora 2014-15. PWSS. is Perennial River. approximately 60 There is Narmada town some of the There is Narmada Singhada Lake km from the River important ones are River comes under Majholi town. It is approximately 25 Barne Nalla, approximately 45 municipality limits Perennial River km from the Patan Bafhela Nalla, km from the it is located in the town. It is Magni Nalla and Tendukheda town. southern skirts of Perennial River. Mabbaria Nalla It is Perennial the town. which are all River. tributaries of Hiran. Sihora lake located in the centre of the town. Groundwater Central ground water board has been carrying out water level monitoring of 26 no. of ground water monitoring wells in the district. Water levels of these monitoring wells are being monitored four times in a year during the month of January, May, August & November. To study ground water regime of the area, pre monsoon & post monsoon depth to water level maps of the district has been prepared. Eastern past of the district is highly undulating & forested. Pre-monsoon (May, 2012) : In general depth to water level in the district, ranges between 0.37m-14.20mbgl Post-monsoon (November, 2012) : In general depth to water level in the district, ranges between 2.30m-16.80mbgl Long Term Water level trend in last 10 years (2003-2013) – Fall -0.02-0.2 m/year and Rise of 0.01-0.14 m/year during Pre-monsoon. Jabalpur district is underlain by Alluvium, Archaean granite, Basaltic lava flows of Deccan trap Bijawar and Vindhyan sandstone. Dynamic ground water resources of the district have been estimated for base year -2008/09 on block-wise basis. Out of 5,26,693 ha of geographical area, 4,43,866 ha ( 84 %) is ground water recharge worthy area and 82,827 ha (16%) is hilly area. There are seven number of assessment units

M/s LN Malviya Infra Project Pvt. Ltd. Page 18

IEE Package 5B

Baseline Bhedaghat Katangi Majholi Panagar Patan Sihora Tendukheda characteristic (block) in the district which fall under non-command (86 %-Kundam and Majholi) and command (14.%) sub units. All the blocks except, Patan is categorized as safe. Non command area of Patan block of the district is categorized as semi critical (safe in 2003/04). The highest stage of ground water development is computed as 64% in Shahpur block. The net ground water availability in the district is 55,679 ham and ground water draft for all uses is 28,184 ham, making stage of ground water development 51 % (42 % in 2003/04) as a whole for district. The EC value ranges from 505-1603,NO3 value ranges from 8-81,Fluoride value ranges from 0.02-2.35. The total hardness of the groundwater in the district is under safe limit as per BIS standards. Air quality There is no data on ambient air quality in all the seven towns, which are not subject to monitoring by the Madhya Pradesh Pollution Control Board (MPPCB) as there are no major industries. No field monitoring (environmental) survey was conducted however, the environmental monitoring program developed as part of the environmental management plan (EMP) will require the contractors to establish the baseline environmental conditions prior to commencement of civil works. The results will be reported as part of the environmental monitoring report and will be the basis to ensure no degradation will happen during subproject implementation. Ecological Project area mostly comprises urban areas, agricultural areas of Bhedaghat, Katangi, Majholi, Panagar, Patan, Sihora and Tendukheda. Extent of forest areas in the project area is very limited, and none of the project components are located in the forest areas , except CWRM from Patan to Tendukheda towns. In Bhedaghat, Open forest areas are located near the source, but none of the proposed project components comes under forest area. These are open forests with shrubs and bushes, and trees. Flora in that area consist of mixed forest, bamboo, teak, sal etc. Katangi- Tala reserve forest located in the North-east direction of Katangi town approx. 2 km from the town, none of the project components comes under these. Majholi- There is an Open mixed forest in the South-west direction of Majholi town, Flora in that area consists of mixed forest, mainly sal etc., none of the project components comes under these. Panagar- Bohra Reserve forest and Open mixed forests are located approx. 5 km from the Panagar town, in the Southern- eastern skirts, but none of the proposed project components comes under these forests. Sihora- An area east of Sihora around villages Maragarh, Kurro etc. is occupied by the Maragarh reserved Forest. Bohra Reserve forest and Open mixed forests are located approx. 12 km from the Sihora town, in the Southern direction from the town, but none of the propos ed project components comes under these forests. Patan and Tendukheda- Mahguwan and Sahajpur Reserve forest area comes between Patan and Tendukheda Towns. The Clear water Rising main from Patan to Tendukheda will be laid along a road, that comes under Forest areas. The pipeline will be laid in the road right of way, and will not encroach into the forest. As road comes under forest department therefore NoC from Forest department required before award of contract.

Economic The main The main The main The town is sub Patan is one of the Sihora in spite of The main economic development economic base of economic base of economic base of tehsil headquarter important green plenty of natural base of Bhedaghat town is Katangi town is Majholi town is of the district and pea cultivation resources and Tendukheda town Land use Tourism and mainly bedi mainly bedi hence performs all areas of Jabalpur located in the main is mainly bedi agriculture. On an manufacturing and manufacturing and the administrative region. The line has negligible manufacturing and

M/s LN Malviya Infra Project Pvt. Ltd. Page 19

IEE Package 5B

Baseline Bhedaghat Katangi Majholi Panagar Patan Sihora Tendukheda characteristic Agriculture & average, twenty to Agriculture in Agriculture in functions of sub hinterland of the industries. Agriculture in industry twenty five particular. Nearly particular. Nearly hehsil. The town is Economy of Sihora particular. Nearly thousand people 50 percent of 60 percent of hinterland of the predominantly town is mainly 50 percent of visit Bhedghat on population is population is town is agricultural in based on small population is weekdays and on engaged in bedi engaged in bedi predominantly nature. Patan soil scale industries in engaged in bedi weekend it may manufacturing manufacturing agricultural in is good for general and manufacturing reach sixty works. works. nature Panagar cultivation of agriculture in works. thousand. Many has a reasonable wheat which is particular, some skilled labours industrial base, exported to minor industries engaged in self- constituted different parts in like saw mill, oil employed work on primarily of small India. mill, dal mill Bidi stone designing of scale industries. making etc. the locally There are a available soft sizeable number stone. Potential of small scale agriculture land industries which facilitates double are engaged in the cropping due to manufacturing of a present of variety of products perennial river including Bidi Narmada. making etc. Infrastructure - Bhedaghat is well Katangi town is The total road Within the Nagar Patan is well Sihora is well The town area of transport accessed by road. connected with the length in Katangi Parishad the accessed by road. accessed by road. Tendukheda is The total road region through is 30 km out of roads are very The total road The total road characterized by length in State Highway- which 27.0 km is narrow and length in Patan is length in Sihora is very narrow roads Bhedaghat is 24.6 37, which maintained by the maintained 22.00 km out of approx. 80.00 km is that are km is maintained connects the town nagar Parishad properly. which 19.5 km is maintained by the frequently by the Nagar to Jabalpur. The and remaining 3.0 maintained by the Nagar Parishad. Parishad. Around total road length in km by the PWD. nagar Parishad Around 30 percent congested with 19 percent of the Katangi is 28.8 km Around 33 % of and remaining 2.5 of the roads laid by traffic and roads laid by out of which 25.0 the total roads are km by the PWD. cement concrete. pedestrians. In cement concrete. km is maintained laid by cement Around 47 % of contrast the The share of WBM by the nagar concrete. the total roads are remainder of the roads is 47 Parishad and The share of WBM laid by cement town has a percent and remaining 3.8 km roads is 30% and concrete. The relatively good remsining 34 by the PWD. remaining 37% share of WBM road system,

M/s LN Malviya Infra Project Pvt. Ltd. Page 20

IEE Package 5B

Baseline Bhedaghat Katangi Majholi Panagar Patan Sihora Tendukheda characteristic percent are Around 43 % of are earthen roads. roads is 30% and particularly in the earthen roads. the total roads are remaining 12% outer areas, laid by cement are earthen roads. where streets are concrete. wide and not heavily used by traffic. Roads are surface either with bitumen or concrete, and roads in the outer areas are mostly unpaved.

Sewerage, There is no sewerage collection and treatment system in any of the subproject towns. Households mainly depend on individual s anitation systems sanitation & like pit latrines, septic tanks etc. Open defecation is also prevalent in the subproject area. Open drains are provided along the roads, which carry both drainage wastewater and rainwater during the rains. Drains dispose the water directly into natural water bodies. Solid waste There is no proper solid waste management system in the towns. Respective municipal councils are responsible for SWM services in their areas. management Waste generated in the towns are collected and disposed by crude open dumping method in the outskirts of the towns.

Power supply: Thermal power is the main source of energy in Madhya Pradesh, contributing nearly 90% of the electricity, compared to hydropower, whi ch produces the remainder. Power supply situation. Demographic Population of the Population of the Population of the Population of the Population of the Population of the Population of the characteristic town as per 2011 town as per 2011 town as per 2011 town as per 2011 town as per 2011 town as per 2011 town as per 2011 census was 6657 census was 19040 census was census was 27932 census was census was census was 14339. increased from increased from 13218, increased , increased from 14324, increased 44,048, increased Average HH size: 5423 in 2001. 17062 in 2001. from 11318 in 25199 in 2001 from 13213 in from 37870 in 2001 4.9 Growth rate 2001- Growth rate 2001- 2001 Growth rate 200- 2001 Growth rate 200-11 SC population – 2011:22.7 % 2011:11.6% Growth rate 200- 11 – 10.85% Growth rate 200- – 16.31% 1833 (State average Average HH size: 11 – 16.8% Average HH size: 11 – 8.46 % ST population – 20.3%) 4.9 Average HH size: 4.04 SC population – SC population – 795 Sex ratio – Sex ratio – 920 4.91 Sex ratio – 923 2197 5503 885(State 931), Literacy rate (total) Sex ratio – 967 Literacy rate (T) – ST population – ST population – Literacy rate (total) – 78% Literacy rate (T) – 78.5 % 938 5509 – 62.28% (State 87% SC population – 69.32%) SC population – SC population – 3595

M/s LN Malviya Infra Project Pvt. Ltd. Page 21

IEE Package 5B

Baseline Bhedaghat Katangi Majholi Panagar Patan Sihora Tendukheda characteristic SC population – 2208 1750 ST population – 903 ST population – ST population – 243 ST population – 1129 487 1174 History, culture The town is of There are no There are no The town is of There are no The name Sihora There are no & tourism historical and protected or protected or historical and protected or was derived from protected or archeological notable historical, notable historical, archeological notable historical, the Singorgarh fort notable historical, importance cultural or tourism cultural or tourism importance cultural or tourism which was located cultural or tourism because of the places in the town places in the town because of the places in the town in the north of the places in the town Chausath Yogini ancient Vishnu town. One of the temple. The Varaha temple. important place in temple is a This temple was the town is the protected built in 11 B.C and Jwala mukhi temple monument of had a beautiful existing to the east archeological idol of god Vishnu of the city which is department of in Varaha located on a India incarnations. The shanku type hillock. (figure 14 shows temple is a During Navaratri location and protected festival , mela is prohibited and monument of organized at this regulated area of archeological site. monument w.r.t department of proposed water India . works component) (figure 15 shows location and prohibited and regulated area of monument)

M/s LN Malviya Infra Project Pvt. Ltd. Page 22

Figure 8: Site Environs of Bhedaghat Town

IEE Package 5B

Figure 9: Site Environs of Panagar, Katangi and Majholi Towns

M/s LN Malviya Infra Project Pvt. Ltd. Page 24

IEE Package 5B

Figure 10: Site Environs of Patan and Tendukheda Towns

M/s LN Malviya Infra Project Pvt. Ltd. Page 25

IEE Package 5B

Figure 11: Site Environs of Sihora Town

M/s LN Malviya Infra Project Pvt. Ltd. Page 26

IEE Package 5B

Table 9: Site Environmental Features Infrastructure Location & Environmental Features Site Photograph Intake Well Intake well cum pump house will be built in the Narmada River, under the control of Water Resources Department, GoMP.

Aquatic life in the river is limited to local specifies of fishes, and aquatic plants. There are no notable sensitive features. The major fish abundance was noticed viz. major carps, minor carps and cat fishes. Raw water pipeline will be laid underground from the intake well to WTP site along an existing road.

Raw Water Raw water rising main will be laid along the Rising Main main road. Pipes will be laid Underground. The RWRM leading to Intake well to WTP, the land owned by Govt; this land is vacant, and pipeline will be laid with the permission of ULB. There is no forest land within the prescribed limit of the town.

WTP site WTP site is located adjacent to the local Haat Market ; site is currently vacant, and covered with shrubs and bushes

OHTs at Two OHTs proposed for Bhedaghat NP. Bhedaghat 200 KL capacity is proposed at Lametha Ghat, proposed site is vacant and under possession of GoMP. 225 KL OHT is proposed at Dendayal Park, Site is vacant and one end portion of the park is utilized for the construction of OHT. Site is located within the town. Site is covered with rock out crops. There are small trees in the site.

M/s LN Malviya Infra Project Pvt. Ltd. Page 27

IEE Package 5B

Sump well for Sump well of 52 KL capacity is proposed. Tendukheda Site is located near Basan village . Site is Town covered with rock out crops. There are no trees in the site.

M/s LN Malviya Infra Project Pvt. Ltd. Page 28

IEE Package 5B

OHTs at Two OHTs of 325 KL and 300 KL capacity are Tendukheda proposed for Tendukheda town. OHT at ward no 10: Site is located within the town in ward no 10. Site is vacant with no tree cover and owned by GoMP OHT at ward no. 9 Selected site is adjacent to the existing water tank facility in the town. Site is currently

vacant and owned by ULB.

OHT at Panagar Three OHTs of 700 KL, 600 KL and 200 KL Town capacities are proposed for Panagar town water supply scheme. OHT at Gurunanak Ward Site is located within the town. Site is vacant with no tree cover and owned by GoMP.

OHT at Maulana Ward Site is currently vacant and owned by ULB. Site is surrounded by Agriculture fields. Proposed Site is not a water body, it‘s a vacant land and adjacent to road (under construction site)

OHT at Aazad Ward Site is currently vacant and owned by ULB. Site is surrounded by Agriculture fields.

M/s LN Malviya Infra Project Pvt. Ltd. Page 29

IEE Package 5B

OHT at Sihora Four OHTs of 620 KL, 630 KL, 920 KL and Town 1020 KL are proposed for Sihora town water supply scheme OHT at ward no 11 OHT is proposed at behind SDM office , land is vacant and free of vegetation. Land owned by GoMP.

OHT at Ward no 4

Land is under possession of GoMP and vacant.

OHT at Ward no. 13 OHT is proposed at ward no 13 Danav Baba Toriya , land is vacant and free of vegetation. Land owned by GoMP.

OHT at ward no 9 Site is located within the town. Site is vacant with no tree cover and owned by GoMP.

M/s LN Malviya Infra Project Pvt. Ltd. Page 30

IEE Package 5B

Figure 12: Transmission network Site Photographs 1. From Bhedaghat to Nunsar (J-1)

2. From J-1 to Katangi

Distribution Main

M/s LN Malviya Infra Project Pvt. Ltd. Page 31

IEE Package 5B

Majholi

Panagar

M/s LN Malviya Infra Project Pvt. Ltd. Page 32

IEE Package 5B

Patan

Sihora

M/s LN Malviya Infra Project Pvt. Ltd. Page 33

IEE Package 5B

M/s LN Malviya Infra Project Pvt. Ltd. Page 34

IEE Package 5B

VI. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

60. Potential environmental impacts of the proposed infrastructure components are presented in this section. Measures to minimize/mitigate negative impacts, if any, are recommended along with the agency responsible for implementation. Monitoring actions to be conducted during the implementation phase is also recommended.

61. Screening of potential environmental impacts are categorized into four categories considering subproject phases: location impacts and design impacts (pre-construction phase), construction phase impacts and operations and maintenance phase impacts.

a. Location impacts include impacts associated with site selection and include loss of on-site biophysical array and encroachment either directly or indirectly on adjacent environments. It also includes impacts on people who will lose their livelihood or any other structures by the development of that site. b. Design impacts include impacts arising from Investment Program design, including technology used, scale of operation/throughput, waste production, discharge specifications, pollution sources and ancillary services. c. Construction impacts include impacts caused by site clearing, earthworks, machinery, vehicles and workers. Construction site impacts include erosion, dust, noise, traffic congestion and waste production. d. O&M impacts include impacts arising from the operation and maintenance activities of the infrastructure facility. These include routine management of operational waste streams, and occupational health and safety issues.

62. Screening of environmental impacts has been based on the impact magnitude (negligible/moderate/severe – in the order of increasing degree) and impact duration (temporary/permanent).

63. This section of the IEE reviews possible project-related impacts, in order to identify issues requiring further attention and screen out issues of no relevance. ADB SPS (2009) require that impacts and risks will be analyzed during pre-construction, construction, and operational stages in the context of the project‘s area of influence.

64. The ADB Rapid Environmental Assessment Checklist in http://www.adb.org/documents/guidelines/environmental_assessment/eaguidelines002 .aspis used to screen project for environmental impacts and to determine the scope of the IEE.

65. In the case of this project (i) most of the individual elements are relatively small and involve straightforward construction and operation, so impacts will be mainly localized and not greatly significant;(ii) proposed water abstraction from the sources is very small compared to overall water availability; (iii) most of the predicted impacts are associated with the construction process, and are produced because that process is invasive, involving excavation and earth movements; and some works are located in the reservoir and (iv) being mostly located in an urban area, will not cause direct impact on biodiversity values. The proposed project components locations are belongs to the government property and existing roads, hence land acquisition and encroachment on private property will not happen in this case.

M/s LN Malviya Infra Project Pvt. Ltd. Page 35

IEE Package 5B

A. Pre-Construction Impacts – Design & Location

66. Design of the Proposed Components. Technical design of the (i) intake well, , (ii) water treatment plant; (iii) raw water and clear water transmissions mains (iv) over head tanks, and (v) distribution network, connections, flow meters, etc., follows the relevant national planning and design guidelines, focusing on providing a robust system which is easy to operate, sustainable, efficient and economically viable. Besides, the project also included the following environmental considerations:

(i) Recovering backwash water from treatment process. (ii) Treatment and disposal management of sludge from treatment process. (iii) Minimizing water losses from pipelines by perfect jointing and alignments using appropriate techniques (iv) Designing the entire system to maintain optimal flow and terminal pressure, and optimising the overall energy usage (v) Reducing the incidence of water borne diseases by providing 100% population including urban poor with potable water supplies (vi) Improve water use efficiency and reduce water wastage at household level by recording and monitoring the water usage, and charging the consumers as per usage; due consideration to urban poor (vii) Minimize unaccounted for water (UFW) losses using district metered area approach with flow meter and pressure logging arrangements to identify and rectify the leaks, and unauthorized connections (viii) Using low-noise and energy efficient pumping systems

67. Water Source & Sustainability. As the subproject towns are located near to each other (approx. 50-60 km maximum) there was possibility of a combined source/ bulk water scheme. Therefore, combined water supply schemes are proposed for 7 towns based on the most feasible water source (Narmada River) considering techno- economic and environmental considerations as elucidated below.

Salient Feature of River Narmada 68. Location: The Narmada is the largest west flowing and seventh largest river of India. It drains an area of 98,796 sq.kms. out of which nearly 87% lies in Madhya Pradesh besides some areas in the states of Maharashtra and . The Narmada basin lies between east longitudes 720 32' to 810 45' and north latitudes 21020' to 23045'. It flows through Deccan trap in between Vindhya and Satpura ranges of hills before falling into the gulf of Cambay in the Arabian Sea. 69. The Narmada rises from a Kund (spring) at an elevation of 1057m. at Amarkantak in the Maikal hill in Shahdol district of Madhya Pradesh and flows through Madhya Pradesh, Maharashtra and Gujarat between Vindhya and Satpura hill ranges before falling into the gulf of Cambay in the Arabian Sea about 10 km north of Bharuch district of Gujarat. The total length of this west flowing river from its origin to its outfall into the Sea is 1,312 kms. For the first 1,079 kms. it runs in Madhya Pradesh and thereafter it forms the common boundary between Madhya Pradesh and Maharashtra for 35 kms., and Maharashtra and Gujarat for 35 kms. In Gujarat State it stretches for 159 km.

M/s LN Malviya Infra Project Pvt. Ltd. Page 36

IEE Package 5B

73. 70. It is bounded by the Vindhyas on the north, by the Maikala range on the east, by the Satpuras on the south and by the Arabian Sea on the west. The hilly regions are in the upper part of the basin, and lower middle reaches are broad and fertile areas well suited for cultivation. Narmada is the largest west flowing river of the peninsular India. It rises from Maikala range near Amarkantak in Anuppur district of Madhya Pradesh, at an elevation of about 1057 m. The total length of the river is 1,312 km and for the first 1079 km it flows in Madhya Pradesh and there after forms the common boundary between Madhya Pradesh and Maharashtra for 35 km, and Maharashtra and Gujarat for 39 km. In Gujarat State it stretches for 159 km. Its important tributaries are the Burhner, the Banjar, the Sher, the Shakkar, the Dudhi, the Tawa , the Ganjal, the Kundi, the Goi and the Karjan which joins from left whereas the Hiran, the Tendoni, the Barna, the Kolar, the Man, the Uri, the Hatni and the Orsang joins from right. Narmada drains into the Arabian Sea through the . The major part of basin is covered with agriculture accounting to 56.90%. Water bodies cover 2.95% of the total basin area. The basin spreads over 20 parliamentary constituencies (2009) comprising 15 of Madhya Pradesh, 3 of Gujarat, and 1 each of Chhattisgarh and Maharashtra. The Narmada Water Disputes Tribunal has allocated the Narmada water amongst the States as below: Madhya Pradesh – 18.25 Million Acre Feet Gujarat - 9.0 Million Acre Feet Rajasthan –0.5 Million Acre Feet Maharashtra – 28.0 Million Acre Feet Salient Features of Narmada Basin

Basin Extent Longitude 72° 38‘ to 81° 43‘ E Latitude 21° 27‘ to 23° 37‘ N

Length of Narmada River (Km) 1312

Catchment Area (Sq.km.) 98796

Average Water Resource Potential (MCM) 45639

Utilizable Surface Water Resource(MCM) 34500

Live Storage Capacity of Completed Projects (MCM) 17806.0

Live Storage Capacity of Projects Under Construction (MCM) 6835.00

Total Live Storage Capacity of Projects (MCM) 24641.0

No. of Hydrological Observation Stations of CWC 26 (including 8 Gauge site)

No. of Flood Forecasting Stations of CWC 4

M/s LN Malviya Infra Project Pvt. Ltd. Page 37

IEE Package 5B

Table 10: Volume of Narmada river at Manot (Manot is located approx. 90 km upstream from proposed intake location) Unit - MCM Season 2002-03 03-04 04-05 05-06 06-07 07-08 08-09 09-10 10-11 11-12 Monsoon 1856.8 4153.6 3186.0 4629.3 2668.0 1297.9 2091.8 1108.9 1917.5 3711.2

Non- 85.64 195.75 180.14 139.99 159.07 97.06 82.64 114.07 105.88 165.84 Monsoon

Annual 1942.4 4349.3 3366.1 4769.3 2827.0 1394.9 2174.4 1223.0 2023.3 3876.9

Source: Integrated Hydrological Data Book (2015), CWC

Table 11: Volume of Narmada river at Barmanghat (Barmanghat is located approx. 80 km downstream from proposed intake location) Season 2002-03 03-04 04-05 05-06 06-07 07-08 08-09 09-10 10-11 11-12

Monsoon 5944.82 13912.82 7756.30 16753.7 6092.2 3340.8 5608.3 4004.5 5724.6 14990.4

Non- 2874.3 3794.69 2987.59 3818.02 3000.2 2730.2 2795.0 1113.2 2063.9 2845.55 Monsoon

Annual 8819.20 17707.51 10743.8 20571.7 9092.4 6071.0 8403.3 5717.7 7788.5 17835.9

Source: Integrated Hydrological Data Book (2015), CWC 74. From the above river Discharge Guage analysis it is observed that minimum volume in Narmada River in last 10 years was 82.64 MCM at Manot and 1113.2 MCM at Barmanghat while the estimated requirement of Group WSS for the ultimate design year (2048) is 11.31 MCM, considering 22 hour pumping. Hence the Narmada River is adopted as sustainable water source for the proposed group water supply scheme. If we compare upstream and downstream data then downstream flow is much higher than the upstream flow it is because of Bargi dam which is located approx. 30 km upstream from the proposed intake well. 72. Water quality. Existing water quality of Narmada River is good, as per MPPCB Narmada river water quality comes under category ―B‖ river and is suitable for domestic supply after conventional treatment and disinfection. There is Jabalpur city approx. 10 km upstream from proposed intake well location, but under Narmada Clean mission a STP is proposed for the Jabalpur city . Therefore no impacts envisaged.

M/s LN Malviya Infra Project Pvt. Ltd. Page 38

Figure 13: Narmada River Basin Map

75. Sensitive project locations. The subproject towns are surrounded by forest areas, which are of open mixed or dense mixed type jungles that are under reserved, protected or unclassified categories. None of the subproject components except CWRM from Patan to Tendukheda town comes under the forest areas. Since the proposed CWRM laid along the existing road RoW, but appropriate steps should be taken according to the nature of the risk. This should involve:

a. No construction material storage/ancillary works shall be conducted in the forest area; this shall be limited to actual construction area and the access roads b. No labour camps shall be located near forests (maintain minimum 1km buffer) c. Limit the work to daylight hours only; no work after sunset d. No workers /personnel shall enter forest areas; it is the DBOC responsibility to take necessary precautions & prevent workers removing/damaging trees/vegetation, hunting animals e. Create awareness among workers on environment & safety f. No high noisy works shall be conducted Barricade the construction area properly so that no wild animals entre the work area 76. Social and Cultural Resources. Bhedaghat and Panagar are historical town, and any work involving ground disturbance can uncover and damage archaeological and historical remains. For this project, excavation will occur in project sites, which are spread over entire towns, so it could make high risk of such impacts if the sites contain any archeological and historical remains. Some proposed project sites (of WTP, transmission and distribution lines) are located within 300 m, which require prior permission of ASI. Besides this, the entire town is archeologically rich and the local enquiries indicate that there are instances of unearthing archeological remains especially in old town area during excavation for foundations of houses constructed by local people. Appropriate steps should be taken according to the nature of the risk. This should involve: (i) Obtain permission for construction of WTP and laying of water pipelines within 300 m of protected monuments (ii) Include ASI as project stakeholder, Bhedaghat and Panagar local representative of ASI should be included in the town level committee (iii) Develop a protocol for use by the construction contractors in conducting any excavation work, to ensure that any chance finds are recognised and measures are taken to ensure they are protected and conserved. This should involve: o Having excavation observed by a person with archaeological field training; contractor should employee a person with a formal certification course in archaeology from recognized (such as Institute of Archaeology, ASI, Delhi) during the ground excavation activities o Conduct awareness training to contractor & supervision staff prior to start of excavation o Stopping work immediately to allow further investigation if any finds are suspected; o Calling in the ASI if a find is suspected, and taking any action they require to ensure its removal or protection in situ (iii) WTP site is located approx. 250 m away from Protected monument. Application has been submitted to ASI for NOC. The site selected is best suitable for proposed WTP and no other suitable government land is available in the town. Proposed land parcel is approx. 10.21 Ha, half of this area comes under 300 m dia and half comes outside the 300 dia. Hence, as mitigation measures during construction, it will ensured that only boundary wall of WTP is constructed under 300 m and other components of WTP are constructed on the outer skirts of the plot. IEE Package 5B

Figure 14: Google map showing ASI listed monument of Bhedaghat town

Figure 15: Google map showing ASI listed monument of Panagar town

M/s LN Malviya Infra Project Pvt. Ltd. Page 41

IEE Package 5B

77. Similarly proposed works in the river bed (for intake) may damage the river bed, lead to degradation of water quality due to increase in turbidity and contamination from fuels and lubricant used in construction work. Increase in silt content and water turbidity, chemical quality can affect the aquatic life. Measures are included in the EMP to avoid, minimize these impacts. 78. Removal of trees and vegetation will be minimize by best alignment and layout planning of facilities, however, this cannot be avoided fully. Appropriate measures in terms of compensatory tree plantation are included in the EMP. 79. Utilities. Telephone lines, electric poles and wires, water lines within the proposed project locations may require to be shifted in few cases. To mitigate the adverse impacts due to relocation of the utilities, the contractor, in collaboration with ULB will be required to implement appropriate measures. These are given in the EMP. 80. Site selection of construction work camps, stockpile areas, storage areas, and disposal areas. Priority is to locate these near the project location. However, if it is deemed necessary to locate elsewhere, sites to be considered will not promote instability and result in destruction of property, vegetation, irrigation, and drinking water supply systems. Residential areas will not be considered for setting up construction camps to protect the human environment (i.e., to curb accident risks, health risks due to air and water pollution and dust, and noise, and to prevent social conflicts, shortages of amenities, and crime). Extreme care will be taken to avoid disposals near forest areas, water bodies, or in areas which will 81. Site selection of sources of materials. Significant quantities of coarse aggregate and fine aggregate will be required for construction works. Requirement of gravel is limited. Contractor should procure these materials only from the quarries permitted/licensed by Mines and Geology Department. Contractor should, to the maximum extent possible, procure material from existing quarries, and creation of new quarry areas should be avoid as far as possible. It will be the construction contractor‘s responsibility to verify the suitability of all material sources and to obtain the approval of Department of Mines & Geology and local revenue administration.

B. Construction Impacts

82. Construction works. Civil works in the project include linear excavation for laying pipes along the roads, placing pipes in the trench and refilling with the excavated soil. The trenches will be of 0.4 m – 0.7 m wide and 0.8 to 1 m depth. Subsequent to completion of works, road reinstatement will be undertaken by the contractor as part of the civil works. The roads in the core city area of all the towns are very narrow and congested with pedestrians and vehicles (mainly 2-wheelers), while the roads in outer areas are wide.

83. Earth work excavation will be undertaken by machine (backhoe excavator) or manually and include danger lighting and using barricades at every 100 m.. Sufficient care will be taken while laying so that existing utilities and cables are not damaged and pipes are not thrown into the trenches or dragged, but carefully laid in the trenches. As trenches are a maximum of 1.2 m, there is no risk of collapse of trenches or risk to surrounding buildings. Once they are laid, pipes will be joined as per specification and then tested for any cracks of leakages. The minimum working hours will be 8 hours daily, the total duration of each stage depends on the soil condition and other local features. About 95% of the excavated soil will be used for refilling the refilling the trench after placing the pipe and therefore residual soil after pipe laying and refilling is not significant. This excel soil shall be used for construction.

M/s LN Malviya Infra Project Pvt. Ltd. Page 42

IEE Package 5B

84. Although construction of these project components involves quite simple techniques of civil work, the invasive nature of excavation and the project locations in the built-up areas of the town where there are a variety of human activities, will result in impacts to the environment and sensitive receptors such as residents, businesses, and the community in general. The following are anticipated impacts, which are temporary and for short duration:

(i) Dust and air emissions from construction activities and equipment / vehicles affecting the ambient air quality (ii) Impacts on natural drainage, surface water bodies due to disposal of construction waste and silt / chemical laden run off from work areas (iii) Impacts on river eco-system due to river bed construction (iv) Impacts due to disposal of surplus soil, construction waste, debris etc., (v) Impacts due to noise and vibration from consultation activities (vi) Impacts due to collection of groundwater in trenches & disposal of the same (vii) Impact/public inconvenience/ accessibility issues due to excavation on public roads (narrow old town roads), movement of trucks carrying construction material (viii) Impacts on business, activities, people due to loss/restricted access to public/private/business/sensitive areas (schools, hospitals), etc., (ix) Occupation health and safety impacts on workers (x) Health Impacts due to removal of existing AC (asbestos cement) pipes (xi) Community health and safety impacts due to construction in an urban area (xii) Impacts due to establishment/operation of temporary construction camps

85. Construction of intake well in the river may lead to degradation of water quality due to increase in turbidity and chemical contamination from fuels and lubricant used in construction work. Increase in silt content and water turbidity, chemical quality can affect the aquatic life, silting/chocking of spill ways/ canals etc., Though there are no notable aquatic life, to ensure that any negative impacts are mitigation, the contractor will be required to: o Select a construction methodology that is least disturbing, and appropriate for the in-situ soil condition o Schedule the construction works during low water level period – late winter months to pre monsoon (February – June/July); ensure that works are completed during the same period to prior to onset of monsoon; confirm with Bargi dam authorities on release of water; avoid scheduling the works during water release period. o Erect temporary barriers to form enclosed construction area with least disturbance o Allow adequate time settle the distributed solids to prior to pumping out water; only clear/clarified water shall be pumped back into the reservoir; any silt laden water should be pumped to a silt pond o Avoid/minimize use of fuels, chemicals and lubricants; ensure no spillage

86. Generation of Construction Wastes. Solid wastes generated from the construction activities are excess excavated earth (spoils), discarded construction materials, cement bags, wood, steel, oils, fuels and other similar items. Domestic solid wastes may also be generated from the workers‘ camp. Improper waste management could cause odor and vermin problems, pollution and flow obstruction of nearby watercourses and could negatively impact the landscape. The following mitigation measures to minimize impacts from waste generation shall be implemented by the contractor:

o Prepare and implement a Construction Waste Management Plan

M/s LN Malviya Infra Project Pvt. Ltd. Page 43

IEE Package 5B

o Stockpiles, lubricants, fuels, and other materials should be located away from steep slopes and water bodies; o Avoid stockpiling any excess spoils. Excess excavated soils should be dispose to approved designated areas; o Domestic solid wastes should be properly segregated in biodegradable and non-biodegradable for collection and disposal to designated solid waste disposal site; o Residual and hazardous wastes such as oils, fuels, and lubricants shall be disposed in disposal sites approved by local authorities; o Prohibit burning of construction and domestic waste; o Ensure that wastes are not haphazardly dumped within the project site and adjacent areas. o Get approval of PIU in writing that the necessary environmental restoration work has been adequately performed before acceptance of work.

87. Noise and Vibration Levels. Except water intake and WTP, all the construction works will be conducted at selected sites and along the roads in all the seven towns‘ urban area and surroundings, where there are houses, schools and hospitals, religious & historical places and small-scale businesses. The sensitive receptors are the general population in these areas. Increase in noise level may be caused by excavation, particularly breaking of cement concrete or bitumen roads, operation of construction equipment like concrete mixers, and the transportation of equipment, materials, and people. Vibration generated from construction activity, for instance from the use of pneumatic drills, will have impact on nearby buildings and monuments. This impact is negative but short-term, and reversible by mitigation measures. The construction contractor will be required to:

o Plan activities in consultation with PIU so that activities with the greatest potential to generate noise are conducted during periods of the day which will result in least disturbance; o Horns should not be used unless it is necessary to warn other road users or animals of the vehicle‘s approach; o Minimize noise from construction equipment by using vehicle silencers, fitting jackhammers with noise-reducing mufflers, and use portable street barriers to minimise sound impact to surrounding sensitive receptor; and o Maintain maximum sound levels not exceeding 80 decibels (dBA) when measured at a distance of 10 m or more from the vehicle/s. o Identify any buildings at risk from vibration damage and avoiding any use of pneumatic drills or heavy vehicles in the vicinity;

88. Surface and Groundwater Quality. Another physical impact that is often associated with excavation is the effect on drainage and the local water table if groundwater and surface water collect in the voids. In all the towns groundwater is deeper than the proposed excavation depths, and rains are limited to short duration during monsoon. However, to ensure that water will not pond in pits and voids near project location, the construction contractor will be required to conduct excavation works in non-monsoon season to the maximum extent possible.

89. Accessibility. Excavation along the roads, hauling of construction materials and operation of equipment on-site can cause traffic problems. Roads in the core/old town area is very narrow. However, most of the roads are used by pedestrians and two wheelers, and four wheelers vehicles are very limited. Potential impact is negative but

M/s LN Malviya Infra Project Pvt. Ltd. Page 44

IEE Package 5B

short term and reversible by mitigation measures. The construction contractor will be required to:

o Confine work areas along the roads to the minimum possible extent; all the activities, including material & waste/surplus soil stocking should be confined to this area. Proper barricading should be provided; avoid material/surplus soil stocking in congested areas – immediately removed from site/ or brought to the as and when required o Leave spaces for access between mounds of soil; o Provide walkways and metal sheets where required to maintain access across for people and vehicles; o Plan transportation routes so that heavy vehicles do not use narrow local roads, except in the immediate vicinity of delivery sites; o Schedule transport and hauling activities during non-peak hours; o Locate entry and exit points in areas where there is low potential for traffic congestion; o Keep the site free from all unnecessary obstructions; o Drive vehicles in a considerate manner; o Coordinate with Traffic Police for temporary road diversions, where necessary, and for provision of traffic aids if transportation activities cannot be avoided during peak hours o Notify affected public by public information notices, providing sign boards informing nature and duration of construction works and contact numbers for concerns/complaints. 90. Wherever road width is minimal, there will be temporary loss of access to pedestrians and vehicular traffic including 2 wheelers during the laying of pipes. Under those circumstances, contractor shall adopt following measures:

o Inform the affected local population 1-week in advance about the work schedule o Plan and execute the work in such a way that the period of disturbance/ loss of access is minimum. o Provide pedestrian access in all the locations until normalcy is restored. Provide wooden/metal planks over the open trenches at each house to maintain the access.

91. Socio-Economic – Income. The project components will be located in government land and there is no requirement for land acquisition or any resettlement. Construction works will impede the access of residents to specific site in limited cases. The potential impacts are negative and moderate but short-term and temporary. The construction contractor will be required to:

o Leave spaces for access between mounds of soil; o Provide walkways and metal sheets where required to maintain access across for people and vehicles; o Increase workforce in the areas with predominantly institutions, place of worship, business establishment, hospitals, and schools; o Consult businesses and institutions regarding operating hours and factoring this in work schedules; and o Provide sign boards for pedestrians to inform nature and duration of

M/s LN Malviya Infra Project Pvt. Ltd. Page 45

IEE Package 5B

construction works and contact numbers for concerns/complaints. o Notify community/ water users in advance about likely interruptions in water supply. o Provide alternate sources of clean water until water supply is restored.

92. Socio-Economic – Employment. Manpower will be required during the 24-months construction stage. This can result in generation of temporary employment and increase in local revenue. Thus potential impact is positive and long-term. The construction contractor will be required to:

o Employ at least 50% of the labour force, or to the maximum extent;

93. Occupational Health and Safety. Workers need to be mindful of the occupational hazards which can arise from working in height and excavation works. Potential impacts are negative and long-term but reversible by mitigation measures. The construction contractor will be required to:

o Comply with all national, state and local labour laws (see Appendix 9); o Develop and implement site-specific occupational health and safety (OH&S) Plan which will include measures such as: (a) excluding public from the site; (b) ensuring all workers are provided with and use personal protective equipment; (c) OH&S Training1 for all site personnel; (d) documented procedures to be followed for all site activities; and (e) documentation of work-related accidents; o Ensure that qualified first-aid is provided at all times. Equipped first-aid stations shall be easily accessible throughout the site; o Provide medical insurance coverage for workers; o Secure all installations from unauthorized intrusion and accident risks; o Provide supplies of potable drinking water; o Provide clean eating areas where workers are not exposed to hazardous or noxious substances; o Provide H&S orientation training to all new workers to ensure that they are apprised of the basic site rules of work at the site, personal protective protection, and preventing injuring to fellow workers; o Provide visitor orientation if visitors to the site can gain access to areas where hazardous conditions or substances may be present. Ensure also that visitor/s do not enter hazard areas unescorted; o Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas; o Ensure moving equipment is outfitted with audible back-up alarms; o Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment,

1 Some of the key areas that may be covered during training as they relate to the primary causes of accidents include (i) slips, trips and falls; (ii) personal protective equipment; (iii) ergonomics, repetitive motion, and manual handling; (iv) workplace transport; and (v) legislation and responsibilities. Training can provide the foundations of competence but it does not necessarily result in a competent worker. Therefore, it is essential to assess staff competence to ensure that the training provided is relevant and effective. Supervision and monitoring arrangements shall be in place to ensure that training has been effective and the worker is competent at their job. The level of supervision and monitoring required is a management decision that shall be based on the risks associated with the job, the level of competence required, the experience of the individual and whether the worker works as part of a team or is a lone worker.

M/s LN Malviya Infra Project Pvt. Ltd. Page 46

IEE Package 5B

and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and o Disallow worker exposure to noise level greater than 85 dBA for duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively.

94. Asbestos Materials. Existing water distribution network is mostly asbestos cement (AC) pipes, and because of the health risks these will be left in situ and replaced by new pipes. Plan pipeline alignments carefully to avoid any conflict or damage.

95. Community Health and Safety. Hazards posed to the public, specifically in high- pedestrian areas may include traffic accidents and vehicle collision with pedestrians. Potential impact is negative but short-term and reversible by mitigation measures. The construction contractor will be required to:

o Plan routes to avoid times of peak-pedestrian activities. o Liaise with PIU in identifying risk areas on route cards/maps. o Maintain regularly the vehicles and use of manufacturer-approved parts to minimize potentially serious accidents caused by equipment malfunction or premature failure. o Provide road signs and flag persons to warn of on-going trenching activities.

96. Work Camps. Operation of work camps can cause temporary air and noise pollution from machine operation, water pollution from storage and use of fuels, oils, solvents, and lubricants. Potential impacts are negative but short-term and reversible by mitigation measures. The construction contractor will be required to:

o Consult PIU before locating project offices, sheds, and construction plants; o Minimize removal of vegetation and disallow cutting of trees; o Provide drinking water, water for other uses, and sanitation facilities for employees; o Ensure conditions of liveability at work camps are maintained at the highest standards possible at all times; o Prohibit employees from poaching wildlife and cutting of trees for firewood; o Train employees in the storage and handling of materials which can potentially cause soil contamination; o Recover used oil and lubricants and reuse or remove from the site; o Manage solid waste according to the following preference hierarchy: reuse, recycling and disposal to designated areas; o Remove all wreckage, rubbish, or temporary structures which are no longer required; and o Confirm to PMU report in writing that the camp has been vacated and restored to pre-project conditions before acceptance of work.

97. Debris disposal. Prior to the commencement of works, contractor shall identify a debris disposal site in consultation with the PIU and adhering to following criteria:

o The site shall be selected preferably from barren, infertile lands. In case

M/s LN Malviya Infra Project Pvt. Ltd. Page 47

IEE Package 5B

agricultural land needs to be selected, top-soil stripping, stacking and preservation should be undertaken prior to initiation of any activities. o Debris disposal site shall be at least 200 m away from surface water bodies2. o No residential areas shall be located within 100 m downwind side of the site. o The site is minimum 250 m. away from sensitive locations like hospitals, religious places, ponds/lakes or other water bodies. The local governing body and community shall be consulted while selecting the site

98. The above impacts are typical for construction in urban areas, and therefore are common to all the seven subproject towns. These are negative but short-term and reversible by mitigation measures. There are well-developed and proven measures and construction practices to avoid, mitigate and/or minimize these impacts to acceptable levels. These measures are given in the construction phase EMP applicable to all seven towns.

C. Operation and Maintenance Impacts 99. Operation and Maintenance of the water supply system will be carried out by the DBO Contractor for 10 years, and after which the respective municipalities will operate and maintain the infrastructure. During the system design life (15/30 years for mechanical/civil components),it shall not require major repairs or refurbishments and should operate with little maintenance beyond routine actions required to keep the equipment in working order. The stability and integrity of the system will be monitored periodically to detect any problems and allow remedial action if required. Any repairs will be small-scale involving manual, temporary, and short-term works involving regular checking and recording of performance for signs of deterioration, servicing and replacement of parts.

100. Recurrence of pipe bursting and leakage problems can be managed by the leak detection and water auditing surveys. The ULBs will be required to ensure that the leak detection and rectification time is minimized.

101. Provision for recirculation system for filter backwash – backwash water from filter beds will be sent to a storage tank, and after allowing adequate time for settlement of solids, clarified water will be pumped to WTP inlet. This arrangement will avoid pollution and also minimize wastage of water. Water treatment process will generate sludge from sedimentation of particulate matter in raw water, flocculated and precipitated material resulting from chemical coagulation, residuals of excess chemical dosage, plankton etc; and waste from rinsing and back washing of filter media containing debris, chemical precipitates, straining of organic debris and plankton. Accumulated sludge from Tube Settler, filter backwash etc., will be disposed-off at sludge drying beds for natural drying. Dried sludge will be disposed off in a land fill or used as soil conditioner if it is suitable

2 In the absence of site meeting the stipulated criteria, an alternate site can be selected specifying the reasons. In such a case, the construction camp management plan should incorporate additional measures specific to the site as suggested by the Construction Manager.

M/s LN Malviya Infra Project Pvt. Ltd. Page 48

IEE Package 5B

D. Project benefits 102. During the construction phase, there are likely to be positive impacts through employment generation, increase in local revenue from the project activities. During the operation phase also, there is potential for employment generation, though limited, as the improved and expanded water infrastructure requires additional workforce. 103. The citizens of Package 5B towns will be the major beneficiaries of the improved water supply system, as they will be provided with a constant supply of better quality water, piped into their homes at an appropriate pressure. The project will improve the over-all health condition of the towns as water borne diseases will be reduced, so people should spend less on healthcare and lose fewer working days due to illness, so their economic status should also improve, as well as their overall health. This should also improve the environment of these areas, should deliver major improvements in individual and community health and well-being.

M/s LN Malviya Infra Project Pvt. Ltd. Page 49

IEE Package 5B

VII. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

A. Overview

104. The active participation of stakeholders including local community, NGOs/CBOs, and the media in all stages of project preparation and implementation is essential for successful implementation of the project. It will ensure that the subprojects are designed, constructed, and operated with utmost consideration to local needs, ensures community acceptance, and will bring maximum benefits to the people. Public consultation and information disclosure is a must as per the ADB policy.

105. Most of the main stakeholders have already been identified and consulted during preparation of this IEE, and any others that are identified during project implementation will be brought into the process in the future. Primary stakeholders of the subproject are: residents, shopkeepers and businesspeople who live and work alongside the roads in which network improvements will be provided and near sites where facilities will be built (WTP and water tanks), and government and utility agencies responsible for provision of services in all the seven towns ,WRD, ASI (for Bhedaghat and Panagar NPs) and MPPCB, etc.,. Secondary stakeholder are: NGOs and CBOs working in the area, community representatives, beneficiary community in general, government agencies, the executing and implementing agencies (MPUDC, PMU and PIUs), Government of India and the ADB.

B. Public Consultation

106. The public consultation and disclosure program is a continuous process throughout the project implementation, including project planning, design and construction.

1. Consultation during Project Preparation

107. Institutional consultations were conducted with the relevant Governmental Departments such as WRD, PHED, MPPCB etc. The subproject proposals are formulated in consultation with Sagar municipal Corporation and Makronia Nagar Parishad to suit the requirements of the respective towns.

108. Focus-group discussions with affected persons and other stakeholders were conducted to learn their views and concerns. A socio economic household survey has been conducted in the town, covering sample households, to understand the household characteristics, health status, and the infrastructure service levels, and also the demand for infrastructure services. General public and the people residing along the project activity areas were also consulted during visits to the project sites. Formal town-level consultation meetings were conducted in January 2016 in all the three subproject towns. Besides, several other meetings also conducted at ward-level with communities, and at market with street vendors and hawkers. The details of consultation are provided in Appendix 5. 109. The people are willing to extend their cooperation as the activities are proposed to improve the water supply service levels and the living standards. Stakeholder expressed their concern regarding water charges, affordability, disturbance and loss of business due to the work in market area(dust, road closure etc.). The project team explained the proposed mitigation measures to mitigate / minimize such issues.

M/s LN Malviya Infra Project Pvt. Ltd. Page 50

IEE Package 5B

2. Consultation during construction

110. Prior to start of construction, ULB and PIU with the assistance of PMC will conduct information dissemination sessions at various places and solicit the help of the local community, leaders/prominent for the project work. At each ward/neighborhood level, focus group meetings will be conducted to discuss and plan construction work with local communities to reduce disturbance and other impacts.

111. A constant communication will be established with the affected communities to redress the environmental issues likely to surface during construction phases and also regarding the grievance redress mechanism. ULB/PIU and PMC will organize public meetings and will appraise the communities about the progress on the implementation of EMP. Meeting will also be organized at the potential hotspots/sensitive locations before and during the construction.

C. Information Disclosure

112. Executive summary of the IEE will be translated in Hindi and made available at the offices of PMU, PIU, Nagar Parishad offices, and also displayed on their notice boards. Hard copies of the IEE will be accessible to citizens as a means to disclose the document and at the same time creating wider public awareness. Electronic version of the IEE in English and Executive Summary in Hindi will be placed in the official website of the MPUDC, PMU after approval of the IEE by Government and ADB. Stakeholders will also be made aware of grievance register and redress mechanism.

113. Public information campaigns to explain the project details to a wider population will be conducted. Public disclosure meetings will be conducted at key project stages to inform the public of progress and future plans. Prior to start of construction, the PMU/PIU will issue Notification on the start date of implementation in local newspapers A board showing the details of the project will be displayed at the construction site for the information of general public.

114. Local communities will be continuously consulted regarding location of construction camps, access and hauling routes and other likely disturbances during construction. The road closure together with the proposed detours will be communicated via advertising, pamphlets, radio broadcasts, road signage, etc.

M/s LN Malviya Infra Project Pvt. Ltd. Page 51

IEE Package 5B

VIII. GRIEVANCE REDRESS MECHANISM

A. Project Specific Grievance Redress Mechanism

115. A program-specific grievance redress mechanism (GRM) shall be established to receive, evaluate, and facilitate the resolution of AP‘s concerns, complaints, and grievances about the social and environmental performance at the level of the project. The following GRM provides a time-bound and transparent mechanism to voice and resolve social and environmental concerns linked to the project.

116. A common GRM will be in place for social, environmental, or any other grievances related to the project. The GRM will provide an accessible and trusted platform for receiving and facilitating resolution of affected persons‘ grievances related to the program. The multi-tier GRM for the project is outlined below, each tier having time-bound schedules and with responsible persons identified to address grievances and seek appropriate persons‘ advice at each stage, as required. ULB-wide public awareness campaigns will ensure that awareness on grievance redress procedures is generated through the campaign.

117. Who can complain: A complaint may be brought by persons who are, or could be, ―directly, indirectly, materially, and adversely‖ affected by the project. A complaint can be submitted on behalf of the affected person/people by a representative, provided that he or she identifies the affected person/people and includes evidence of the authority to act on their behalf. 118. What the Grievance/Complain should contain: Any concerns pertaining to safeguard compliance - environment, involuntary resettlement, indigenous people, design related issues, compensation, service delivery or any other issues or concerns related to the project. The complaint must contain name, date, address/contact details of the complainant, location of the problem area, along with the problem. In addition, online filing using the state‘s existing grievance redress mechanism or telephone helpline will also be open to use by affected persons3. 119. Where to file a Complaint: Complainants will have the flexibility of conveying grievances/suggestions by dropping or reporting grievance redress/suggestion forms in complaints/suggestion boxes to be installed by project at respective Nagar Parishad Offices, CM (Chief Minister) Helpline, PIU offices or by e-mail or by writing in a complaints register in the PIU offices or at construction site offices. 120. How to file a Complaint: The application should be precise and specific. The application can be sent either by post or through electronic means or deliver personally. A sample grievance form is at Appendix 8. (i) Offline System - The application can be made on the application form available at all accessible places (NPs/ Office of PIUs/ construction site offices). The application should have the name and complete postal address of the applicant.

3 Government of Madhya Pradesh has a special program called Chief Minis ter‘s Monitoring Programme, which monitors development programs in the state and provides for online registration of complaints. The Public Grievance Redressal Department of GoMP clearly displays the Chief Minister‘s Helpline Number, through which persons may lodge complaints directly to the highest authority in the state. The website of the Public Grievance Redressal Department also provides a kiosk locator for district level grievance redress kiosks. http://www.mp.gov.in/web/guest/home.

M/s LN Malviya Infra Project Pvt. Ltd. Page 52

IEE Package 5B

(ii) Online System - Grievances pertaining to the implementation of the project can also be filed online at the website of MPUDC/PMU or by e-mails.

121. Documentation: Documentation of the complaints is important and must contain name of the complainant, date of receipt of the complaint, address/contact details of the person, location of the problem area, and how the problem was resolved. PMU with the support of PIU will have the overall responsibility for timely grievance redress, and for registration of grievances, related disclosure, and communication with the aggrieved party. All the documents made available to the public at the community level (at ward offices) and will include information on the contact number, address and contact person for registering grievances, and will be disseminated throughout the project area by the PIU.

122. Grievance/Problem Redress through Participatory Process: Efforts must be made by the PIU with the support of safeguard consultants to resolve problems amicably, conflicts through participatory process with the community and the Nagar Parishads. In case of grievances that are immediate and urgent in the perception of the complainant, the Contractor, and supervision personnel from the PIU will provide the most easily accessible or first level of contact for the quick resolution of grievances. Contact phone numbers and names of the concerned staff and contractors, will be posted at all construction sites at visible locations.

123. Following process will be followed: (i) 1st level grievance. In case of grievances that are immediate and urgent in the perception of the complainant, PMC supervising staff will direct the contractor to and ensures that it is resolved. If the grievance is not under the contractor scope, but under the program, PMC (field office) will resolve this issue. All the grievances should be resolved within 3 days of receipt of a complaint/grievance. The complaints/grievances received in the CM helpline that are related to MPUSIP will be referred to project GRM at this first level. CM helpline staff will be included in the GRM training so that they can identify the related grievances and forward to this project GRM. (ii) 2nd level grievance. All grievances that cannot be redressed at first level within 3 days will be brought to the notice of PIU and PMC Assistant Environmental Specialist. PIU will review the grievance and act appropriately to resolve it within 10 days of receipt. (iii) 3rd level grievance. All the grievances that are not addressed at 2nd level by PIU within in 10 days of receipt will be brought to the notice of notice of the Grievance Redressal Committee (GRC)4. GRC will meet twice a month and determine the merit of each grievance brought to the committee. The GRC will resolve the grievance within 1 month of receiving the complaint. All decisions taken by the GRC will be communicated to complainant by the Nodal Officer.

4 Grievance redress committee (GRC) will be formed at town-level with members composed of: ULB Chairperson, ULB CMO, Environmental Specialist of PMC, PIU Dy.PM and PIU Community Development Officer. In case of any complaints by IP or members of scheduled tribes, the PIU will include as special member, a representative of an independent local NGO involved in tribal welfare. Special invitees to hearing of IP complaints will include two representatives from affected IP community and the project IP NGO, if appointed for IPP implementation.

M/s LN Malviya Infra Project Pvt. Ltd. Page 53

IEE Package 5B

124. In case of any inter-departmental or inter-jurisdictional coordination required for resolution of specific grievances, the PIU will refer the matter directly to the PMU for state- level or inter-departmental coordination and resolution, instead of the town-level GRC. The project GRM notwithstanding, an aggrieved person shall have access to the country's legal system at any stage, and accessing the country's legal system can run parallel to accessing the GRM and is not dependent on the negative outcome of the GRM. Alternatively, if the grievance is related to land acquisition, resettlement & rehabilitation5, the APs can approach the Land Acquisition, Rehabilitation and Resettlement Authority (LARRA) of Madhya Pradesh, established under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation, and Resettlement Act, 2013.

125. Record-keeping. PIU will keep records of grievances received, corrective actions taken and the final outcome. The number of grievances recorded and resolved and the outcomes will be displayed/disclosed in the PIU office, ULB offices, and on the web.

Figure 16: MPUSIP Grievance Redress Mechanism

Affected person

Yes Field level within 3 days Grievance 1st Level Responsible: Contractor, PMC, and redressed and Grievance PIU field staff record keeping

No Yes PIU Grievance Redress Unit within 10 days Grievance 2nd Level PIU ASO, PMC RS in consultation redressed and Grievance with Project Engineer record keeping

No Yes Grievance Redress Committee rd within 30 days 3 Level GRC at town level. In case of IP Grievance Grievance complaints, independent IP NGO, IP redressed and community representatives to be record keeping involved. No

Court of Law

Note: ASO=Assistant Safeguard Officer, GRC = Grievance Redressal Committee; PMC = Project Management Consultants, PMU = Project Management Unit

5 the Authority admits grievance only with reference to the LA and R&R issues under the new Act

M/s LN Malviya Infra Project Pvt. Ltd. Page 54

IEE Package 5B

IX. ENVIRONMENTAL MANAGEMENT PLAN

A. Implementation Arrangements

126. Urban Development and Housing Department (UDHD) of Government of Madhya Pradesh will be the Executing Agency for the Program, responsible for management, coordination and execution of all activities funded under the loan. Implementing Agency will be the recently established Madhya Pradesh Urban Development Company (MPUDC), a wholly owned subsidiary of GoMP. A central Project Management Unit (PMU) attached to MPUDC will be responsible for implementing the MPUSIP. The PMU will be supported by Program Implementation Units (PIUs) with flexibility to redeployment depending upon the implementation requirements.

127. The PMU and PIUs will be supported by several teams of Design Consultants in preparation of preliminary engineering designs.

128. Water Resource Review Committee (WRRC) is constituted to undertake a thorough review of the source when recommended by the Design Consultant in regard to techno- economic feasibility and sustainability especially ensuring climate change resilience, and Technical Review Committee (TRC) to review and approve the preliminary designs developed by the Design Consultants.

129. Program Management Consultant (PMC) centrally located in PMU and with field teams located in PIUs shall be responsible for implementation of the Program. All infrastructure contracts will be procured through performance-based contracts (PBCs) and include build- operate (BO) framework. Based on the preliminary designs prepared by Design Consultants, the DBO (design-build-operate) Contractor will design, construct, commission and operate for 10 years, after which it will be transferred to the respective ULB.

130. Two Committees - an Empowered Committee cum Executive Committee and a Technical Clearance and Tender Committee have been constituted by the Government to be responsible for effective and timely implementation of the Program. 131. Safeguards. At PMU, there will be two safeguard specialists: (i) Project Officer (Environment) and (ii) Social & Gender Offer, who will responsible for compliance with the environmental and social safeguards in program implementation. PO (Environment) will have overall responsibility in implementation of the investment program as per the Environmental Assessment & Review Framework (EARF) agreed between ADB and the government. At individual subproject level, PO will ensure that environmental assessment is conducted, and a project-specific is prepared and implemented, and the compliance, and corrective actions, if any are reported as required.

B. Environmental Management Plan

132. An environmental management plan (EMP) has been developed to provide mitigation measures to reduce all negative impacts to acceptable levels.

M/s LN Malviya Infra Project Pvt. Ltd. Page 55

IEE Package 5B

133. The EMP will guide the environmentally-sound construction of the subproject and ensure efficient lines of communication between MPUDC, project management unit (PMU), project implementing unit (PIU), consultants and contractors. The EMP will (i) ensure that the activities are undertaken in a responsible non-detrimental manner; (i) provide a pro-active, feasible and practical working tool to enable the measurement and monitoring of environmental performance on site; (ii) guide and control the implementation of findings and recommendations of the environmental assessment conducted for the subproject; (iii) detail specific actions deemed necessary to assist in mitigating the environmental impact of the subproject; and (iv) ensure that safety recommendations are complied with. The EMP includes a monitoring program to measure the environmental condition and effectiveness of implementation of the mitigation measures. It will include observations on- and off-site, document checks, and interviews with workers and beneficiaries.

134. The contractor will be required to submit to PIU, for review and approval, a site environmental plan (SEP) including (i) proposed sites/locations for construction work camps, storage areas, hauling roads, lay down areas, disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following the approved EMP; (iii) monitoring program as per SEP; and (iv) budget for SEP implementation. No works are allowed to commence prior to approval of SEP.

135. A copy of the EMP/approved SEP will be kept on site during the construction period at all times. The EMP included in the bid and contract documents. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance.

136. For civil works, the contractor will be required to (i) carry out all of the mitigation and monitoring measures set forth in the approved SEP; and (ii) implement any corrective or preventative actions set out in safeguards monitoring reports that the employer will prepare from time to time to monitor implementation of this IEE and SEP. The contractor shall allocate budget for compliance with these SEP measures, requirements and actions.

137. The following tables show the potential environmental impacts, proposed mitigation measures and responsible agencies for implementation and monitoring.

M/s LN Malviya Infra Project Pvt. Ltd. Page 56

Table 12: Design Stage Environmental Management Plan Field Anticipated Mitigation Measures Responsible for Cost and Source of Impact Implementation Funds Design of Unsustainable  Recovering wash water from treatment process These measures are Part of project costs water supply source;  Treatment and reuse of sludge from treatment process already included in system resource &  Minimizing water losses from pipelines by perfect jointing and the preliminary energy use alignments using appropriate techniques designs.  Designing the entire system to maintain optimal flow and terminal pressure, and optimizing the overall energy usage DBO Contractor  Reducing the incidence of water borne diseases by providing 100% (DBOC)to follow, population including urban poor with potable water supplies enhance where  Improve water use efficiency and reduce water wastage at household possible. level by recording and monitoring the water usage, and charging the consumers as per usage; due consideration to urban poor PMU to ensure  Minimize unaccounted for water (UFW) losses using district metered compliance. area approach with flow meter and pressure logging arrangements to identify and rectify the leaks, and unauthorized connections  Using low-noise and energy efficient pumping systems Water Project  Obtain permission from Water resources department, GoMP PMU & respective No costs; scope of abstraction sustainability Nagar Parishads IA from & water use (process already Narmada conflicts initiated) River Waste Environmental  Obtain consent from MPPCB for WTP at Bhedaghat town prior to PMU / Nagar No costs; scope of generation pollution start of construction Parishad; DBOC to IA & DBO from WTP prepare application, operations and assist as required Chlorine Chlorine  Provide the following measure at the chlorine application unit: These measures are Project Costs usage as handling & o Chlorine neutralization pit with a lime slurry feeder already included in disinfectant application o Proper ventilation, lighting, entry and exit facilities the preliminary at WTPs risk – health o Facility for isolation in the event of major chlorine leakage (if designs. &safety risk to needed) workers and o Personal protection and safety equipment for the operators in the DBOC to follow, general public chlorine plant enhance where

57

Field Anticipated Mitigation Measures Responsible for Cost and Source of Impact Implementation Funds o Provide training to the staff in safe handling and application of possible. chlorine; this shall be included in the contract of Chlorinator supplier PMU to ensure o Supplier of Chlorinator equipment shall provide standard compliance. operating manual for safe operation and as well as maintenance and repairs; preferably these shall be provided both in English and Hindi Languages Socio Encroachment (i) Obtain ASI permission for laying of water pipelines within 300 m of PMU & Nagar Project Cost cultural / damage protected monuments prior to start of bidding Parishad resource to protected (ii) Include ASI as project stakeholder, local representative of ASI should monuments be included in the town level committee and chance (iii) Proper procedures (protocol) shall be used by the construction finds contractors in conducting any excavation work, to ensure that any chance finds are recognised and measures are taken to ensure they are protected and conserved. This should involve:  Having excavation observed by a person with archaeological field training; contractor should employee a person with a formal certification course in archaeology from recognized (such as Institute of Archaeology, ASI, Delhi) during the ground excavation activities  Conduct awareness training to contractor & supervision staff prior to start of excavation Stopping work immediately to allow further  investigation if any finds are suspected;  Calling in the ASI if a find is suspected, and taking any action they require to ensure its removal or protection in situ  WTP site in Bhedaghat is located approx. 250 m away from Protected monument. Application has been submitted to ASI for NOC. The site selected is best suitable for proposed WTP and no other suitable government land is available in the town. Proposed land parcel is approx. 10.21 Ha, half of this area comes under 300 m dia and half comes outside the 300 dia. Hence, as mitigation measures during construction, it will ensured that only boundary wall of WTP is constructed under 300 m and other components of WTP are constructed on the outer skirts of the plot.

M/s LN Malviya Infra Project Pvt. Ltd. Page 58

Table 13: Pre-Construction State Environmental Management Plan Field Anticipated Impact Mitigation Measures Responsible for Cost and Implementation Source of Funds EMP Unsatisfactory  Appoint EHS supervisor and designate 1 EHS DBO contractor Cost for Implementation compliance to EMP coordinator (among the technical staff) in each town implementation & reporting  Ensure that all pre-construction activities are complete of mitigation prior to start of construction work measures  Ensure timely submission of monitoring reports responsibility of contractor. Utilities Damage/  Identify and include locations of utilities in the detailed DBOC with PIU Project costs – disturbance to designs/drawings to prevent unnecessary disruption of collaboration. general telephone lines, services PMU to ensure construction electric lines, water  Prepare a contingency plan to include actions to be compliance practice lines in project area taken in case of unintentional interruption of services. Construction Disturbance /  No construction material storage/ancillary works shall DBOC with PIU Project costs – works near damage to forest be conducted in the forest area; this shall be limited to collaboration. general forest areas areas, wildlife actual construction area and the access roads construction  No labour camps shall be located near forests PIU/ PMU to practice (maintain minimum 1km buffer) ensure  Limit the work to daylight hours only; no work after compliance sunset  No workers /personnel shall enter forest areas; it is the DBOC responsibility to take necessary precautions & prevent workers removing/damaging trees/vegetation, hunting animals  Create awareness among workers on environment & safety  No high noisy works shall be conducted  Barricade the construction area properly so that no wild

M/s LN Malviya Infra Project Pvt. Ltd. Page 59

Field Anticipated Impact Mitigation Measures Responsible for Cost and Implementation Source of Funds EMP Unsatisfactory  Appoint EHS supervisor and designate 1 EHS DBO contractor Cost for Implementation compliance to EMP coordinator (among the technical staff) in each town implementation & reporting  Ensure that all pre-construction activities are complete of mitigation prior to start of construction work measures  Ensure timely submission of monitoring reports responsibility of contractor. animals entre the work area Construction Degradation of  Do not disturb river bed except the actual work area; no DBOC to follow Project costs – works on river river course and equipment, machinery shall be operated outside the general bed (intake pollution work area PIU/ PMU to construction well)  Avoid use of fuels, chemicals & lubricants; ensure no ensure practice spillage compliance  Clean up the area after the completion & prior to the onset of monsoon flow Construction Conflicts with local  Prioritize barren, waste, infertile, vacant lands within the DBOC to identify Part of project work camps, community; area, locations costs stockpile disruption to traffic  Shall not be located in productive agricultural lands, following the areas, storage flow and sensitive water bodies, natural drainage channels, flood plains & criteria areas and receptors groundwater recharge areas, forests, vegetative lands, waste disposal etc. PIU to ensure areas  Locate at sites that will not promote instability, flooding compliance and and result in destruction of natural drainage, vegetation, approve irrigation, & drinking water supply;  For private lands, obtain land owner‘s (not lessees) written consent; indicate the requirement for reinstatement to original  Site should have a minimum buffer of 0.5 – 1 km from all socially, environmentally sensitive areas (eg., residential, socio-cultural areas & water bodies (0.5 km), forests (1km), etc.,)  Take extreme care in selecting sites to avoid direct

M/s LN Malviya Infra Project Pvt. Ltd. Page 60

Field Anticipated Impact Mitigation Measures Responsible for Cost and Implementation Source of Funds EMP Unsatisfactory  Appoint EHS supervisor and designate 1 EHS DBO contractor Cost for Implementation compliance to EMP coordinator (among the technical staff) in each town implementation & reporting  Ensure that all pre-construction activities are complete of mitigation prior to start of construction work measures  Ensure timely submission of monitoring reports responsibility of contractor. disposal to water body which will inconvenience the community.  Document site‘s pre-project conditions Sources of Extraction of  Obtain material only existing borrow sites/quarries DBOC to identify Part of project Materials materials can already permitted by the Department of Mines and sources that costs disrupt natural land Geology; have all permits, contours and  If new quarries sites/quarries are necessary, contractor if required, vegetation resulting shall be obtain all necessary permissions as per the law obtain permits, in accelerated in force. and submit to erosion,  Contractor to obtain construction materials only after PIU disturbance in written permission / approval of PIU for respective natural drainage sources PIU to check patterns, ponding  Maintain a construction material register at the site and approve and water logging, and water pollution.

Consents, Failure to obtain  Obtain all necessary consents, permits, clearance, PMU / PIU to Part of project permits, necessary NOCs, etc required for the project prior to award of obtain project costs clearances, consents, permits, contact or start of civil works, as necessary. clearances; NOCs, etc. NOCs, etc. can DBOC to provide result to design  Include in detailed designs, drawings and documents necessary revisions and/or all regulatory conditions and provisions, where required assistance stoppage of works  Contractor to identify & obtain all necessary approvals, including in compliance with labour laws, before start of DBOC to obtain

M/s LN Malviya Infra Project Pvt. Ltd. Page 61

Field Anticipated Impact Mitigation Measures Responsible for Cost and Implementation Source of Funds EMP Unsatisfactory  Appoint EHS supervisor and designate 1 EHS DBO contractor Cost for Implementation compliance to EMP coordinator (among the technical staff) in each town implementation & reporting  Ensure that all pre-construction activities are complete of mitigation prior to start of construction work measures  Ensure timely submission of monitoring reports responsibility of contractor. construction; construction permits &  Contractor to acknowledge in writing to PIU and provide copies of all obtained permits, clearance, NOCs, etc. PIU to ensure

Health risk due to  Obtain details from PHED/NPs on location of DBOC in Part of project Asbestos exposure to underground AC pipes coordination with costs Cement Pipes asbestos materials  Locate the new piper carefully to avoid encountering PIU and ULB AC pipes  Leave the AC pipes undisturbed in the ground.

Table 14: Construction Stage Environmental Management Plan Field: Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation EMP Implementation Irreversible impact to  Project manager and all key workers will be DBOC Cost of EMP Implementation Training the environment, required to undergo training on EMP Orientation Training to workers, and implementation including spoils/waste PMC Construction contractor is responsibility of community management, Standard operating and Environmental PMU. procedures (SOP) for construction works; Specialists to occupational health and safety (OH&S), conduct the training Other costs responsibility of core labor laws, applicable environmental contractor. laws, etc. Air Quality Emissions from  Control dust by water sprinkling on DBO Contractor Cost for implementation of construction vehicles, exposed soil, stock stockpiled material on mitigation measures

M/s LN Malviya Infra Project Pvt. Ltd. Page 62

Field: Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation equipment, and site responsibility of contractor. machinery used for  Barricade area, provide wind sheets installation of  Use tarpaulins to cover sand and other Air quality monitoring costs pipelines resulting to loose material when transported by trucks; are included in the EMP dusts and increase in  Clean wheels and undercarriage of haul costs of project concentration of trucks prior to leaving construction site vehicle-related  Prevent entry of traffic, public in pollutants such as construction area carbon monoxide,  Fit all heavy equipment, and machinery sulfur oxides, with air pollution control devices which are particulate matter, operating correctly; all the vehicle shall nitrous oxides, and meet the emission norms and shall have hydrocarbons. valid pollution under control (PUC) certificate.  Conduct air quality monitoring as per the monitoring plan. Surface water quality Mobilization of settled  Avoid earthworks during the rainy season DBO Contractor Cost for implementation of silt materials, and  Avoid stockpiling of earth fill especially mitigation measures chemical during the monsoon season unless responsibility of contractor. contamination from covered by tarpaulins or plastic sheets; fuels and lubricants  Reuse excess spoils & materials in the Water quality monitoring during installation of construction as far a possible costs are included in the pipelines can  Identify disposal sites prior to construction EMP costs of project contaminate nearby & dispose construction waste only at surface water quality. designated areas  Install temporary silt traps basins along the drainage leading to the water bodies;  Place storage areas for fuels and lubricants away from any drainage leading to water bodies;  Conduct surface quality inspection according to the Environmental

M/s LN Malviya Infra Project Pvt. Ltd. Page 63

Field: Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation Management Plan (EMP). Noise Levels Increase in noise  Conduct noise generating activities (eg, cc DBO Contractor Cost for implementation of level due to earth- road cutting) during day time mitigation measures moving and  Minimize noise from construction responsibility of contractor. excavation equipment (by using vehicle silencers, equipment, and the fitting jackhammers with noise-reducing transportation of mufflers, and use portable street barriers to equipment, materials, minimize sound impact to surrounding and people sensitive receptor;  Maintain maximum sound level not exceeding 80 decibels (DBA) when measured at a distance of 10 m or more from the vehicle/s.  Identify any buildings at risk from vibration damage and avoiding any use of pneumatic drills or heavy vehicles in the vicinity;  Consult local communities in advance to avoid working at sensitive times, such as religious and cultural festivals. Landscape and Impacts due to  Stockpiles, lubricants, fuels, and other DBO Contractor Cost for implementation of aesthetics excess excavated materials should be located away from mitigation measures earth, excess steep slopes and water bodies; responsibility of contractor. construction  Avoid stockpiling any excess spoils; materials, and solid dispose immediately to designated areas waste such as  Domestic solid waste generated at removed concrete, construction camps and work sites shall be wood, packaging properly managed (collected, segregated, materials, empty disposed properly); waste should not containers, spoils, burned oils, lubricants, and  Residual and hazardous wastes such as other similar items. oils, fuels, and lubricants shall be disposed

M/s LN Malviya Infra Project Pvt. Ltd. Page 64

Field: Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation through approved recyclers  Environmentally restore the work sites to at least pre-project conditions; PIU to approve in writing that site is restored Ecological Resources – Loss of vegetation  Avoid removal of vegetation / tree cutting DBO Contractor Cost for implementation of Terrestrial and tree cover  If unavoidable, minimize as far as possible, mitigation measures and obtain tree-cutting permit responsibility of contractor.  Plant 10 trees for every one cut Land use Environmental Issues  The impact due to change in land use will Not applicable Not applicable due to land use be negligible due to this project. change Accessibility Traffic problems and  Confine work areas along the roads to the DBO Contractor Cost for implementation of conflicts near project minimum possible extent; all the activities, mitigation measures locations and haul including material & waste/surplus soil responsibility of contractor. road stocking should be confined to this area. Proper barricading should be provided; avoid material/surplus soil stocking in congested areas – immediately remove from site/ or brought to the as and when required  Leave spaces for access between mounds of soil;  Provide walkways and metal sheets where required to maintain access across for people and vehicles;  Plan transportation routes so that heavy vehicles do not use narrow local roads, except in the immediate vicinity of delivery sites;  Schedule transport and hauling activities during non-peak hours;  Keep the site free from all unnecessary

M/s LN Malviya Infra Project Pvt. Ltd. Page 65

Field: Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation obstructions;  Drive vehicles in a considerate manner;  Coordinate with Traffic Police for temporary road diversions, where necessary, and for provision of traffic aids  Notify affected area by public information notices, providing sign boards informing nature and duration of construction works and contact numbers for concerns/complaints.  For works in very narrow roads o Inform the affected local population 1- week in advance about the work schedule o Plan and execute the work in such a way that the period of disturbance/ loss of access is minimum. o Provide pedestrian access in all the locations until normalcy is restored. Provide wooden/metal planks over the open trenches at each house to maintain the access. Socio-Economic – Impede the access of  Do not obstruct access; provide temporary DBO Contractor Cost for implementation of Income. residents and access, by leaving spaces in excavation, mitigation measures customers to nearby provide walkways and metal sheets for responsibility of contractor. shops people and vehicles where necessary to continue business  Increase workforce in the areas with predominantly institutions, place of worship, business establishment, hospitals, and schools;  Consult businesses and institutions

M/s LN Malviya Infra Project Pvt. Ltd. Page 66

Field: Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation regarding operating hours and factoring this in work schedules Socio-Economic – Generate temporary  Employ local persons in construction work DBO Contractor Cost for implementation of Employment employment and if manpower is available mitigation measures increase in local responsibility of contractor. revenue Social and Risk of  No components of WTP will be located in the DBO Contractor Cost for Cultural archaeological 300 m boundary of the monument, and implementation of Resources chance finds boundary wall will be constructed with prior mitigation measures permission of ASI. responsibility of  Excavation work shall be supervised by a contractor. person with archaeological training  Stop work immediately to allow further investigation if any finds are suspected;  Call the ASI if a find I suspected, and taking any action they require to ensure its removal or protection in situ Occupational Health Occupational hazards  Comply with all national, state and local DBO Contractor Cost for implementation of and Safety which can arise core labor laws (see Appendix 7 of this mitigation measures during work IEE) responsibility of contractor.  Implement site-specific occupational health and safety (OH&S) measures, such as the following  Provided personal protective equipment (PPE) to workers(like helmet, gumboot, safety belt, gloves, nose musk and ear plugs), and ensure that they are used  Conduct OH&S training workers/staff  Do no employ ad-hoc work procedures, follow best & acceptable work practices  Document work-related accidents  Provide qualified & easily accessible first-

M/s LN Malviya Infra Project Pvt. Ltd. Page 67

Field: Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation aid facilities all times at all sites  Secure all installations from unauthorized intrusion and accident risks;  Provide potable drinking water;  Provide clean eating areas where workers are not exposed to hazardous or noxious substances;  Provide H&S orientation training to all workers to ensure that they are apprised of the basic site rules of work at the site, PPEs, and preventing injuring to fellow workers;  Ensure that visitor/s do not enter hazard areas unescorted  Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas;  Ensure moving equipment is outfitted with audible back-up alarms;  Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and  Disallow worker exposure to noise level greater than 85 dBA for a duration of more than 8 hours per day without hearing

M/s LN Malviya Infra Project Pvt. Ltd. Page 68

Field: Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation protection. The use of hearing protection shall be enforced actively. Community Health and Traffic accidents and  Plan routes to avoid times of peak- DBO Contractor Cost for implementation of Safety. vehicle collision with pedestrian activities and high risk areas. mitigation measures pedestrians during  Prevent public entry in to work areas responsibility of contractor. material and waste through barricading and security guards transportation  Maintain regularly the vehicles and minimize potentially serious accidents caused by equipment malfunction or premature failure.  Provide road signs and flag persons to warn of on-going trenching activities.  In very narrow streets, conduct work section-wise (~100 m), and complete excavation, pipe laying and backfilling in minimum possible time (1 day preferably) Work Camps and Temporary air and  Establish camps only after site approval DBO Contractor Cost for implementation of worksites noise pollution from  Avoid cutting of trees/ clearing bushes mitigation measures machine operation,  Provide adequate drinking water, water for responsibility of contractor. water pollution from other uses, and sanitation facilities storage and use of  Ensure conditions of livability at work fuels, oils, solvents, camps are maintained at the highest and lubricants standards possible at all times;  Prohibit employees from poaching wildlife Unsanitary and poor and cutting of trees for firewood; living conditions for  Train employees in the storage and workers handling of materials which can potentially cause soil contamination;  Recover used oil and lubricants and reuse or remove from the site;  Manage solid waste according to the preference hierarchy: reuse, recycling and

M/s LN Malviya Infra Project Pvt. Ltd. Page 69

Field: Anticipated Impact Mitigation Measures Responsible for Cost and Source of Funds Mitigation disposal to designated areas;  Ensure unauthorized persons specially children are not allowed in any worksite Post-construction Damage due to  Remove all spoils wreckage, rubbish, or DBO Contractor Cost for implementation of clean-up debris, spoils, excess temporary structures (such as buildings, mitigation measures construction materials shelters, and latrines) which are no longer responsibility of contractor. required  All excavated roads shall be reinstated to original condition.  All disrupted utilities restored  All affected structures rehabilitated/compensated  The area that previously housed the construction camp is to be checked for spills of substances such as oil, paint, etc. and these shall be cleaned up.  All hardened surfaces within the construction camp area shall be ripped, all imported materials removed, and the area shall be top soiled and regressed  The contractor must arrange the cancellation of all temporary services.  Restore the work sites to pre-project conditions; PIU to approve in writing that site is restored

M/s LN Malviya Infra Project Pvt. Ltd. Page 70

Table 15: Operation Stage Environmental Management Plan Field Anticipated Impact Mitigation Measures Responsible for Monitoring of Cost and Mitigation Mitigation Source of Funds Check for Loss of water,  Effective leak detection and water DBO Contractor PIU and Operating blockage and increased demand auditing to reduce the water losses respective costs leakage and inconvenience Nagar problems to consumers & Parishads of reducing the general public Package 5B water losses Water Impacts on public  Ensure protection of water source Respective PMU in Operating contamination – health quality (Narmada), any entry of Nagar Parishads coordination costs raw water wastewater into the river upstream of of Package 5B with WRD contamination sites should be prevented. at source and  Contamination of treated water during DBO Contractor PIU and treated water transmission and distribution should respective during be prevented by quickly identifying, Nagar transmission isolating and repairing the leak Parishads of section. Develop a system of leak Package 5B detection and rectification.  Conduct regular monitoring of raw & treated water and ensure that water supplied at all times meets the drinking water standards (Appendix 11) Discharge the Pollution of  Backwash water will be recirculated DBO Contractor PIU and Operating impurities and streams /drains so no wastewater generated from respective costs other solids WTPs Nagar collected due to  Maintain the mechanical parts as per Parishads of filtration and the maintenance plan to avoid any Package 5B back wash hazards Sludge Land and water  Collect the sludge from WTP units, DBO Contractor PIU and Operating generation pollution, impacts dry in sludge drying beds, and reuse / respective costs

M/s LN Malviya Infra Project Pvt. Ltd. Page 71

Field Anticipated Impact Mitigation Measures Responsible for Monitoring of Cost and Mitigation Mitigation Source of Funds on health & dispose safely as per the design Nagar environment Parishads Increased in Water pollution,  Sanitation facilities needs to be Respective PMU To be sewage and impacts on improved at community level and at Nagar Parishads identified generation public health and the town level to meet the increased of Package 5B - environment sewage demand respective NPs Generation of Impacts on public  Collect solid wastes and dispose to DBO Contractor PIU and Operating waste materials health and approved disposal yards respective costs environment Nagar Parishads Occupational Health, social and  Provide appropriate PPE to workers & DBO Contractor PIU and Operating health and economic impacts training on its proper use respective costs safety on the workers  Use fall protection equipment when Nagar working at heights. Parishads of  Maintain work areas to minimize Package 5B slipping and tripping hazards.  Implement a training program for operators who work with chlorine regarding safe handling practices and emergency response procedures.  Prepare escape plans from areas where there might be a chlorine emission.  Install safety showers and eye wash stations near the chlorine equipment and other areas where hazardous chemicals are stored or used.  Prohibit eating, smoking, and drinking except in designated areas.

M/s LN Malviya Infra Project Pvt. Ltd. Page 72

Table 16: Construction Stage Environmental Monitoring Plan Monitoring field Monitoring location Monitoring parameters Frequency Responsibility Cost & Source of Funds Construction All work sites Implementation of dust Regularly as required Supervising Part of TOR of PIU, PMC and disturbances, nuisances, control, noise control, during construction; staff and PMU public & worker safety, traffic management, & checklist to be filled safeguards safety measures. monthly once specialists Site inspection checklist to review implementation is appended at Appendix 12 Ambient air quality 8 locations  PM10, PM2.5 NO2, Once before start of DBO Cost for implementation of (1 locations in SO2, CO construction Contractor monitoring measures each town at Quarterly (yearly 4- responsibility of contractor distribution work times) during (72 samples x 5000 per site: and at WTP construction (2 year sample = 3,60,000) site) period considered)

Ambient noise 8 locations  Day time and night Once before start of DBO Cost for implementation of (1 locations in time noise levels (24 construction Contractor monitoring measures each town and one hours) Quarterly (yearly 4- responsibility of contractor at combined WTP) times) during (72 samples x 1500 per construction (2 year sample = 1,08,000) period considered) Surface water quality 1 locations (down  pH, Oil & grease, Cl, Once before start of DBO Cost for implementation of Stream of work site F, NO3, TC, FC, construction and Contractor monitoring measures in Narmada) Hardness, Turbidity monthly during responsibility of contractor BOD, COD, DO, construction (12 (13 samples x 4000 per Total Alkalnity months period sample = 52,000) considered)

M/s LN Malviya Infra Project Pvt. Ltd. Page 73

Table 17: Operation Stage Environmental Monitoring Plan Monitoring field Monitoring location Monitoring parameters Frequency Responsibility Cost & Source of Funds Source water quality Near intake point pH, Cl, F, NO3, TC, FC, Hardness, Turbidity Yearly DBO O&M costs in Narmada river BOD, COD, DO, Total Alkalnity twice (pre & Contractor heavy metals & pesticides post monsoon) Monitoring of quality Consumer end- pH, Nitrite, Nitrate, Turbidity, Total Alkalnity, Total Monthly DBO O&M costs of water supplied to random sampling coliform and Feacal coliform once Contractor consumers in all zones Sludge quality and WTP Analysis for concentration of heavy metals and Yearly once DBO O&M costs suitability as manure confirm that value are within the following limits Contractor (all units are in mg/kg dry, except pH)  Arsenic - 10.00,  Cadmium - 5.00  Chromium - 50.00  Copper - 300.00  Lead - 100.00  Mercury - 0.15  Nickel - 50.00  Zinc - 1000.00  PH - 5.5-8.5

M/s LN Malviya Infra Project Pvt. Ltd. Page 74

IEE- Package 5B

C. EMP Compliance Responsibilities

138. PMU Responsibilities. PO (Environment) will be supported by PMC, which will be staffed with an Environmental Specialist, and Environmental Coordinators. Key tasks and responsibilities of the PO (Environment) for this sub project include the following: Bidding stage:

(i) Prior to invitation of bids for civil works contract, ensure that

a. Water Resources Department (WRD) permission is obtained for sourcing water from Narmada River. b. Consent for establishment (CFE) is obtained from MPPCB for WTP construction.

(ii) Ensure that EMP is included in bidding documents and civil works contracts. (iii) Ensure that the bid/contract documents include specific provisions requiring contractors to comply with all applicable labour laws and core labour standards including:

a. Labour welfare measures and provision of amenities b. prohibition of child labour as defined in national legislation for construction and maintenance activities; c. equal pay for equal work of equal value regardless of gender, ethnicity, or caste; d. elimination of forced labour; e. The requirement to disseminate information on sexually transmitted diseases, including HIV/AIDS, to employees and local communities surrounding the project sites. (iv) Ensure that staff required for implementation of EMP is included in the bid requirements (v) Ensure that EMP cost is included in the project cost (vi) In the pre-bid meeting, provide insight into the EARF requirements, IEE update, EMP measures, and overall compliance requirements to the bidders

Construction stage:

(i) Facilitate and ensure that all necessary environmental clearances/permissions, including that of contractor‘s are in place prior to start of construction (ii) Organize an induction course for the training of contractors, preparing them on EMP implementation, environmental monitoring, and on taking immediate action to remedy unexpected adverse impacts or ineffective mitigation measures found during the course of implementation. (iii) provide oversight on environmental management aspects of subprojects and ensure EMPs are implemented by PIU and contractors (iv) Supervise and provide guidance to the PIUs to properly carry out the environmental monitoring as per the EMP (v) Oversee grievance redress mechanism to address any grievances brought about in a timely manner; ensure that records are properly maintained (vi) Consolidate monthly environmental monitoring reports from PIU and submit semi-annual monitoring reports to ADB (vii) Oversee site closures to ensure that all work / facility sites are restored properly prior to issuing work completion certificate to the contractor

Operation stage:

75

(i) Ensure and consent for operation (CFO) is obtained from MPPCB for WTP prior to start of operation

139. PIU Responsibilities. PIU will be headed by a Project Manager and supported by PMC. An Assistant Project Manager of PIU will be given additional responsibilities of safeguard tasks and will be designated as Assistant Environmental Officer (ASO). ASO will be supported by PDMC Environmental Specialist and Environmental Coordinator. Key tasks and responsibilities of the ASO for this subproject include the following: (i) Provide necessary support to PIU and Nagar Parishads in obtaining permission from WRD and MPPCB; liaison with PMU and regulatory agencies (ii) Oversee day-to-day implementation of EMPs by contractors, including compliance with all government rules and regulations, take necessary action for obtaining rights of way (iii) Oversee environmental monitoring by contractors (iv) Take corrective actions when necessary to ensure no environmental impacts (v) Submit monthly environmental monitoring reports to PMU (vi) Conduct continuous public consultation and awareness (vii) Address any grievances brought about through the grievance redress mechanism in a timely manner as per the EMP

140. Contractor‘s responsibilities. Bidding stage:

(i) Understand the EMP requirements and allocate necessary resources (budget, staff, etc.,) (ii) Understand the regulatory compliance requirements related to labour welfare, safety, environment etc.,

Design stage:

(i) Review the IEE Report including the REA checklist, category and the EMP, and conduct site visits to understand the environmental sensitivity of the project sites. (ii) Update the REA checklist, confirm the category, and update/revise the IEE Report of the project reflecting the changes /amendments /additions that are effected in the project during the detailed design (iii) Update / revise and finalize the EMP (iv) Provide all necessary technical assistance to PIU / ULB in obtaining regulatory clearances/approvals. (v) Ensure that all design-related measures of the EMP, and conditions, if any, of government regulatory agencies (like MPPCB consent conditions) are duly included in the final designs.

Construction stage:

(i) Ensure that all regulatory clearances (both project related and contractor related) are in place before start of the construction work. (ii) Mobilize EHS officer and Archaeological supervisor prior to start of work (iii) Confirm with PIU availability of rights of way at all project sites prior to start of work. (iv) Prepare and submit: a. Construction waste management (CWM) plan b. Traffic management (TM) plan

76

(v) Implement the mitigation measures as per the EMP including CWM & TM Plans (vi) Follow the EMP measures/guidelines for establishment of temporary construction camps, construction waste disposal sites, and material borrow areas, etc., (vii) Implement EMP and ensure compliance with all the mitigation and enhancement measures (viii) Conduct environmental monitoring (air, noise, water etc.,) as per the EMP (ix) Undertake immediate action as suggested by PIU / PMU / PMC to remedy unexpected adverse impacts or ineffective mitigation measures found during the course of implementation (x) Submit monthly compliance reports on EMP implementation (xi) Act promptly on public complaints and grievances related to construction work and redress in a timely manner in coordination with PIU (xii) Comply with applicable government rules and regulations

Operation stage:

(i) Obtain CFO from MPPCB in coordination with the ULB, and comply with MPPCB conditions, if any, during the operation phase (ii) Implement the operation phase EMP including the monitoring plan (iii) Submit quarterly EMP implementation report

D. Training Needs

141. The following Table 18 presents the outline of capacity building program to ensure EMP implementation. The estimated cost is Rs.275,000 (excluding trainings of contractors which will be part of EMP implementation cost during construction) to be covered by the project‘s capacity building program. The detailed cost and specific modules will be customized for the available skill set after assessing the capabilities of the target participants and the requirements of the project by the ES of PDMC. Table 18: Outline Capacity Building Program on EMP Implementation Description Target Participants& Estimate Cost and Source Venue (INR) of Funds 1. Introduction and Sensitization to All staff and - Included in the Environmental Issues (1 day) consultants involved overall program - ADB Safeguards Policy Statement in the project cost - Government of India and Madhya Pradesh applicable safeguard laws, At PMU, Bhopal regulations and policies including but (combined program not limited to core labor standards, for all subprojects) OH&S, etc. - Incorporation of EMP into the project design and contracts - Monitoring, reporting and corrective action planning

77

Description Target Participants& Estimate Cost and Source Venue (INR) of Funds 2. EMP implementation (1/2 day) All PIU staff, - Part of overall - EMP mitigation & monitoring measures contractor staff and program costs – -Roles and responsibilities consultants involved PMC will conduct - Public relations, - Consultations in the Package 5B at PIU office - Grievance redress townssubproject - Monitoring and corrective action Part of scope of planning At PIU work of PMU, - Reporting and disclosure PIU, PMC & - Construction site standard operating DBOC procedures (SOP) - AC pipe protocol - Traffic management plan - Waste management plan - Site clean-up & restoration 3. Contractors Orientation to Workers Once before start of - Contractors cost (1/2 day) work, and thereafter - Environment, health and safety in regular briefing project construction every month once. Daily briefing on safety prior to start of work

All workers (including unskilled laborers)

E. Monitoring and Reporting

142. During the detailed design stage, DBO Contractor should confirm PMU the mobilization of Environmental Expert for IEE update and integrating design stage EMP into designs. 143. Prior to commencement of the works, the contractor will submit a compliance report to PIU that all identified pre-construction mitigation measures as detailed in the EMP are undertaken. Contractor should confirm EHS supervisor is mobilized and EHS coordinators are designated for each town for effective implementation of the EMU. PMU with the assistance of the PMC will review the report and permit commencement of works. 144. During construction, results from internal monitoring by the contractor will be reflected in their monthly EMP implementation reports to the PIU. PMU will review and advise contractors for corrective actions if necessary. Quarterly report summarizing compliance and corrective measures taken will be prepared by PMC field team at PIU and submitted to PMU (Appendix 13). During operation, the contractor will conduct management and monitoring actions as per the operation stage EMP, and submit to PMU and ULB a quarterly report on EMP implementation and compliance.

78

145. Based on monthly & quarterly reports and measurements, PMU will submit to ADB, semi-annual (6-monthly) Environmental Monitoring Reports (EMR).Once concurrence from the ADB is received the report will be disclosed on the MPUDC and PMU websites. 146. ADB will review project performance against the MPUSIP commitments as agreed in the legal documents. The extent of ADB‘s monitoring and supervision activities will be commensurate with the project‘s risks and impacts. Monitoring and supervising of social and environmental safeguards will be integrated into the project performance management system F. EMP Implementation Cost

147. Most of the mitigation measures require the contractors to adopt good site practice, which should be part of their normal procedures already, so there are unlikely to be major costs associated with compliance. The costs which are specific to EMP implementation and are not covered elsewhere in the projects are given below. The total costs are estimated at INR 37.45 million, which are to be covered by contractor costs. Table 19: Cost Estimates to Implement the EMP Particulars Stages Unit Total Rate Cost Costs Numb (INR) (INR) Covered er By A Implementation staff . 1 Environmental Design & pre Per 0.5 150,000 75,000 DBO Specialist construction month Contract 2 EHS Supervisor Construction per 24 50,000 1,200,000 DBO month contract 3 Archeological Construction per 12 75,000 9,00,000 Supervisor month Subtotal (A) 21,75,000 B Mitigation Measures . 1 Consent for Pre Lump 150,000 Project establishments & construction sum costs consent for operation from MPPCB 2 Provision for tree Construction Per tree 100 1,000 100,000 DBO cutting & contract compensatory plantation measures 3 Traffic management Construction Lump - - 700,000 DBO at work sites sum – 7 contract (Pavement Markings, towns Channelizing Devices, Arrow Panels and Warning Lights) Subtotal (B) 950,000 C Monitoring Measures . 1 Air quality monitoring Construction / sample 72 5,000 360,000 DBOC

79

Particulars Stages Unit Total Rate Cost Costs Numb (INR) (INR) Covered er By 2 Noise levels Construction / sample 72 1,500 108,000 DBOC monitoring 3 Surface water Construction / sample 13 4,000 52,000 DBOC monitoring 4 Water and sludge Operation LS / yr - - 100,000 DBO Subtotal (C) 620,000 Subtotal (D) - Total (A+B+C) INR 3,745,000

80

IEE- Package 5B

X. CONCLUSION AND RECOMMENDATIONS

148. The process described in this document has assessed the environmental impacts of all elements of the Package 5B towns water supply improvement subproject. All potential impacts were identified in relation to pre-construction, construction, and operation phases. Planning principles and design considerations have been reviewed and incorporated into the site planning and design process wherever possible; thus, environmental impacts as being due to the project design or location were not significant. 149. Project area mostly comprises urban areas, agricultural areas of Bhedaghat, Katangi, Majholi, Panagar, Patan, Sihora and Tendukheda. Extent of forest areas in the project area is very limited, and none of the project components are located in the forest areas, except CWRM from Patan to Tendukheda towns. In Bhedaghat, Open forest areas are located near the source, but none of the proposed project components comes under forest area. These are open forests with shrubs and bushes, and trees. Flora in that area consist of mixed forest, bamboo, teak, sal etc. Katangi- Tala reserve forest located in the North-east direction of Katangi town approx. 2 km from the town, none of the project components comes under these. Majholi- There is an Open mixed forest in the South-west direction of Majholi town, Flora in that area consists of mixed forest, mainly sal etc., none of the project components comes under these. Panagar- Bohra Reserve forest and Open mixed forests are located approx. 5 km from the Panagar town, in the Southern- eastern skirts, but none of the proposed project components comes under these forests. Sihora- An area east of Sihora around villages Maragarh, Kurro etc. is occupied by the Maragarh reserved Forest. Bohra Reserve forest and Open mixed forests are located approx. 12 km from the Sihora town, in the Southern direction from the town, but none of the proposed project components comes under these forests. Patan and Tendukheda- Mahguwan and Sahajpur Reserve forest area comes between Patan and Tendukheda Towns. The Clear water Rising main of approx. 10 km from Patan to Tendukheda will be laid along a road, that comes under Forest areas. The pipeline will be laid in the road right of way, and will not encroach into the forest habitat. Process have been started for obtain NOC from Forest department, under these application have been applied (annexed in appendix 14) by the design consultant to the DFO, Damoh. 150. For the proposed Group WSS water will be sourced from Narmada River, which is a largest river of MP. The requirement of towns is miniscule in comparison with the river flow. WRD permission for abstraction from the river is in process. PMU has already discussed with the WRD, and the permission is likely to be issued soon. Bhedaghat and Panagar towns comes under ASI protected monuments; Although none of the components are located within the protected monuments, WTP (in Bhedaghat town) and distribution lines works (for both the towns) will located within the 300 m around the monuments . Given the minimal excavation (0.4 m wide and 0.7 m deep), there will be no risk to any structure. Nevertheless, the works will be implemented only after due permission of ASI and also the construction methodology will be discussed with the ASI. For chance finds, works will be observed by a person with archeological background. 151. During the construction phase, impacts mainly arise from the construction dust and noise, the need to dispose of large quantities of waste soil and import of construction material, and from the disturbance of residents, businesses, traffic and important buildings by the construction work. The social impacts (access disruptions) due to construction activities are unavoidable, as the residential and commercial establishments exist along the roads where pipes will be laid. As some of the works are conducted in rive, there is a risk of water contamination, river bed damage, etc.. Appropriate measures are suggested.

M/s LN Malviya Infra Pvt. Ltd. Page 81

152. Anticipated impacts of water supply during operation and maintenance will be related to detection and repair of leaks, pipe bursts. These are, however, likely to be minimal, as proper design and selection of good quality pipe material shall mean that leaks are minimal. Leak repair work will be similar to the pipe-laying work. Appropriate measures to deal with backwash water and sludge from WTP is included in the project design. Application and handling of chlorine gas will involve certain risks, and appropriate measures are suggested for safe application. The DBO Contractor will implement the operation stage EMP during contract period. 153. The public participation processes undertaken during project design ensured stakeholders are engaged during the preparation of the IEE. The planned information disclosure measures and process for carrying out consultation with affected people will facilitate their participation during project implementation. 154. The project‘s grievance redress mechanism will provide the citizens with a platform to redress of their grievances, and describes the informal and formal channels, time frame, and mechanisms for resolving complaints about environmental performance. 155. The EMP will assist the PMU, PIU, PMC and DBO contractor in mitigating the environmental impacts, and guide them in the environmentally sound execution of the proposed project. 156. A copy of the EMP/approved SEP shall be kept on-site during the construction period at all times. The EMP shall be made binding on all contractors operating on the site, and will be included in the contractual clauses. Non-compliance with, or any deviation from, the conditions set out in this document shall constitute a failure in compliance. 157. The project will benefit the general public by contributing to the long-term improvement of water supply systems and community liability in Package 5B towns . 158. Therefore, as per ADB SPS, the project is classified as environmental category B and does not require further environmental impact assessment. However, to conform to government guidelines, the project requires (i) permission of WRD, GoMP for water abstraction from Narmada River, and (ii) Consent for Establishment (CFE) and Consent for Operation (CFO) for WTPs from MPPCB; and (iii) ASI and Forest department permission. These permissions/approvals shall be obtained. 159. This IEE shall be updated during the detailed design stage by the DBO contractor to reflect any changes, amendments and will be reviewed and approved by PMU.

82

Appendix 1: REA Check list

Instructions:  This checklist is to be prepared to support the environmental classification of a project. It is to be attached to the environmental categorization form that is to be prepared and submitted to the Chief Compliance Officer of the Regional and Sustainable Development Department.  This checklist is to be completed with the assistance of an Environment Specialist in a Regional Department.  This checklist focuses on environmental issues and concerns. To ensure that social dimensions are adequately considered, refer also to ADB checklists and handbooks on (i) involuntary resettlement, (ii) indigenous peoples planning, (iii) poverty reduction, (iv) participation, and (v) gender and development.  Answer the questions assuming the ―without mitigation‖ case. The purpose is to identify potential impacts. Use the ―remarks‖ section to discuss any anticipated mitigation measures.

Country/Project Title: India / Madhya Pradesh Urban Services Improvement Program – Group WSS- Package 5B towns Water Supply Subproject Sector Division: Urban Development

SCREENING QUESTIONS Yes No REMARKS Water Supply A. Project Siting Is the project area… . Densely populated?  Subproject activities extend to the entire towns including the densely populated areas. There are no major negative impacts envisaged, because pipeline will be located in unused government lands alongside the existing roads and can be constructed without causing disturbance to, houses, and commercial establishments. In narrow streets, disruption to road users is likely, and measure like best activity scheduling, alternative routes, prior information to road users, houses and shops will minimize the impact to acceptable levels. . Heavy with development  - activities? . Adjacent to or within any  environmentally sensitive areas?  Out of Seven towns, two Towns have ASI listed monuments But  Cultural heritage site none of the components are located within the monuments or protected areas.  Protected Area   Wetland   Mangrove   Estuarine   Buffer zone of protected area   Special area for protecting  biodiversity  Bay 

83

B. Potential Environmental Impacts Will the Project cause…  Pollution of raw water supply  There are no significant water pollution sources in the catchment. from upstream wastewater Raw water quality is tested and found that it is suitable for discharge from communities, domestic use industries, agriculture, and soil erosion runoff?  Impairment of  Bhedaghat and Panagar are ASI site. However, project works do historical/cultural not impair any monument or sites monuments/areas and loss/damage to these sites?  Hazard of land subsidence  Not applicable; subproject does not involve groundwater caused by excessive ground abstraction water pumping?  Social conflicts arising from  Project does not involve land acquisition /displacement. No social displacement of conflicts envisaged communities?  Conflicts in abstraction of raw  No; the water will be abstracted only with due permission of water for water supply with government and allocation of water from Narmada River for water other beneficial water uses supply of Group WSS. Drinking water is priority as per the MP for surface and ground water policy. Moreover, water abstraction is just about 3% of gross waters? storage.  Unsatisfactory raw water  Raw water quality is tested and found that it is suitable for supply (e.g. excessive domestic use. Bacteriological contamination is noticed, and water pathogens or mineral will be subjected for treatment prior to s upply constituents)?  Delivery of unsafe water to  Water will be treated and disinfected prior to supply distribution system?  Inadequate protection of  Water is abstracted from Narmada River. There are no major intake works or wells, leading polluting sources in the catchment. to pollution of water supply?  Over pumping of ground  - water, leading to salinization and ground subsidence?  Excessive algal growth in  Regular cleaning of storage tanks will be conducted during storage reservoir? operation  Increase in production of  Sewerage system is also being planned for project towns under sewage beyond capabilities different schemes. of community facilities?  Inadequate disposal of  Appropriate provisions for sludge drying and disposal is included sludge from water treatment in the project plants?  Inadequate buffer zone  - around pumping and treatment plants to alleviate noise and other possible nuisances and protect facilities?  Impairments associated with  - transmission lines and access roads?  Health hazards arising from  Measures for safe handling of chlorine are included inadequate design of facilities for receiving, storing, and handling of chlorine and other hazardous chemicals.  Health and safety hazards to  Measures for safe handling of chlorine are included

84

workers from the management of chlorine used for disinfection and other contaminants?  Dislocation or involuntary  There is no resettlement of people for project implementation. resettlement of people  Social conflicts between  The contractor will be utilizing the local labour force as far as construction workers from possible; in case if it is unavoidable,labour camps and facilities will other areas and community be provided appropriately. No conflicts envisaged workers?  Noise and dust from  All the construction machineries employed will comply with noise construction activities? emission standards of Central Pollution Control Board. Dust suppression measures such as water sprinkling will be employed  Increased road traffic due to  Excavation and laying pipelines along public roads will interfere interference of construction with the traffic. Construction material transport will increase traffic activities? within city. Proper traffic management and construction planning will be ensured to minimize the interference  Continuing soil erosion/silt  Construction work during monsoon shall be carried out with due runoff from construction care so that silt run off due to construction operation is prevented. operations? No construction will be allowed during rains.  Delivery of unsafe water due  No; appropriate O&M will conducted to poor O&M treatment processes (especially mud accumulations in filters) and inadequate chlorination due to lack of adequate monitoring of chlorine residuals in distribution systems?  Delivery of water to  Not envisaged distribution system, which is corrosive due to inadequate attention to feeding of corrective chemicals?  Accidental leakage of  Measures for safe handling of chlorine are included chlorine gas?  Excessive abstraction of  Water abstraction will be limited to the allocated quantity for Group water affecting downstream WSS water users?  Competing uses of water?  Water abstraction will be limited to the allocated quantity for Group WSS  Increased sewage flow due  Water Demand calculation of all the town are taken as 70 LPCD, to increased water supply except Sihora  Increased volume of sullage  Water Demand calculation of all the town are taken as 70 LPCD, (wastewater from cooking except Sihora and washing) and sludge from wastewater treatment plant

85

Climate Change and Disaster Risk Questions Yes No Remarks The following questions are not for environmental categorization. They are included in this checklist to help identify potential climate and disaster risks. Is the Project area subject to hazards such as earthquakes, √ Semi-arid zone, unreliable rainfall, floods, landslides, tropical cyclone winds, storm surges, tsunami less vegetation cover. Promote or volcanic eruptions and climate changes? more efficient use of water by reducing losses and wastage to counter increased demands due to higher temperatures. Could changes in temperature, precipitation, or extreme events √ Reduction in rainfall may affect the patterns over the Project lifespan affect technical or financial water availability from dam. Given sustainability (e.g., changes in rainfall patterns disrupt reliability the priority for drinking water supply, of water supply; sea level rise creates salinity intrusion into dead storage will be utilized in case proposed water supply source)? of low rain fall years Are there any demographic or socio-economic aspects of the √ No Project area that are already vulnerable (e.g.,high incidence of marginalized populations, rural-urban migrants, illegal settlements, ethnic minorities, women or children)? Could the Project potentially increase the climate or disaster √ No vulnerability of the surrounding area (e.g., by using water from a vulnerable source that is relied upon by many user groups, or encouraging settlement in earthquake zones)?

86

Appendix 2: National Ambient Air Quality Standards

Sl Pollutants Time Concentration in ambient air Method of No: weighted measurement Industrial, Ecologically average Residential, Sensitive Rural & Other Areas Areas 1 Sulphur Dioxide Annual 50 20 Improved West and (SO2) 24 hours 80 80 Geake-Ultraviolet µg/m3 fluorescence 2 Nitrogen Dioxide Annual 40 30 Modified Jacob 3 (NO2) µg/m 24 hours 80 80 &Hochheiser (Na- Arsenite) Chemiluminescence 3 Particulate Annual 60 60 Gravimetric Matter (Size 24 hours 100 100 -TOEM less than 10 µm) -Beta attenuation or PM10 µg/m3 4 Particulate Annual 40 40 Gravimetric Matter (Size 24 hours 60 60 -TOEM less than 2.5 -Beta attenuation µm) or PM2.5 µg/m3 5 Carbon 8 hours 02 02 Non Dispersive Infra Monoxide (CO) 1 hours 04 04 Red (NDIR) mg/m3 Spectroscopy

Appendix 3: Vehicle Exhaust Emission Norms 1. Passenger Cars Norms CO( g/km) HC+ NOx(g/km) 1991Norms 14.3-27.1 2.0(Only HC) 1996 Norms 8.68-12.40 3.00-4.36 1998Norms 4.34-6.20 1.50-2.18 India stage 2000 norms 2.72 0.97 Bharat stage-II 2.2 0.5 Bharat Stage-III 2.3 0.35 (combined) Bharat Stage-IV 1.0 0.18 (combined)

2. Heavy Diesel Vehicles Norms CO( g/kmhr) HC (g/kmhr) NOx (g/kmhr) PM(g/kmhr) 1991Norms 14 3.5 18 - 1996 Norms 11.2 2.4 14.4 - India stage 2000 norms 4.5 1.1 8.0 0.36 Bharat stage-II 4.0 1.1 7.0 0.15 Bharat Stage-III 2.1 1.6 5.0 0.10

87

Bharat Stage-IV 1.5 0.96 3.5 0.02 Source: Central Pollution Control Board CO = Carbon Monixide; g/kmhr = grams per kilometer-hour; HC = Hydrocarbons; NOx = oxides of nitrogen; PM = Particulates Matter

Appendix 4: National Ambient Air Quality Standards In Respect Of Noise

Area code Category of area/zone Limit in dB (A) Day time Night time A Industrial area 75 70 B Commercial area 65 55 C Residential area 55 45 D Silence zone 50 40

Appendix 5: Stakeholder Consultation photographs

Stakeholder Consultation

Katangi

88

Community consultation

Majholi

89

Patan

90

Appendix 6: Extract From Construction & Demolition Management Rules, 2016

91

92

93

94

95

96

Appendix 7: Salient Features Of Major Labor Laws Applicable To Establishments Engaged In Construction Of Civil Works

(i) Workmen Compensation Act, 1923 - The Act provides for compensation in case of injury by accident arising out of and during the course of employment.

(ii) Payment of Gratuity Act, 1972 - Gratuity is payable to an employee under the Act on satisfaction of certain conditions on separation if an employee has completed 5 years‘ service or more or on death at the rate of 15 days wages for every completed year of service. The Act is applicable to all establishments employing 10 or more employees.

(iii) Employees‘ PF and Miscellaneous Provisions Act, 1952 - The Act provides for monthly contributions by the employer plus workers @10 % or 8.33 %. The benefits payable under the Act are: (a) Pension or family pension on retirement or death as the case may be; (b) deposit linked insurance on the death in harness of the worker; (c) payment of PF accumulation on retirement/death etc.

(iv) Maternity Benefit Act, 1951 - The Act provides for leave and some other benefits to women employees in case of confinement or miscarriage etc.

(v) Contract Labour (Regulation and Abolition) Act, 1970 - The Act provides for certain welfare measures to be provided by the Contractor to contract labor and in case the Contractor fails to provide, the same are required to be provided by the Principal Employer by Law. The principal employer is required to take Certificate of Registration and the Contractor is required to take a License from the designated Officer. The Act is applicable to the establishments or Contractor of principal employer if they employ 20 or more contract labor.

(vi) Minimum Wages Act, 1948 - The employer is supposed to pay not less than the Minimum Wages fixed by appropriate Government as per provisions of the Act if the employment is a scheduled employment. Construction of Buildings, Roads, Runways are scheduled employment.

(vii) Payment of Wages Act, 1936 - It lays down as to by what date the wages are to be paid, when it will be paid and what deductions can be made from the wages of the workers.

(viii) Equal Remuneration Act, 1979 - The Act provides for payment of equal wages for work of equal nature to Male and Female workers and not for making discrimination against Female employees in the matters of transfers, training and promotions etc.

(ix) Payment of Bonus Act, 1965 - The Act is applicable to all establishments employing 20 or more workmen. The Act provides for payments of annual bonus subject to a minimum of 8.33 % of wages and maximum of 20 % of wages to employees drawing Rs. 3,500/- per month or less. The bonus to be paid to employees getting Rs. 2,500/- per month or above up to Rs.3,500/- per month shall be worked out by taking wages as Rs.2,500/- per month only. The Act does not apply to certain establishments. The newly set up establishments are exempted for five years in certain circumstances. Some of the State Governments have reduced the employment size from 20 to 10 for the purpose of applicability of the Act.

97

(x) Industrial Disputes Act, 1947 - The Act lays down the machinery and procedure for resolution of industrial disputes, in what situations a strike or lock-out becomes illegal and what are the requirements for laying off or retrenching the employees or closing down the establishment.

(xi) Industrial Employment (Standing Orders) Act, 1946 - It is applicable to all establishments employing 100 or more workmen (employment size reduced by some of the States and Central Government to 50). The Act provides for laying down rules governing the conditions of employment by the employer on matters provided in the Act and get the same certified by the designated Authority.

(xii) Trade Unions Act, 1926 - The Act lays down the procedure for registration of trade unions of workmen and employees. The trade unions registered under the Act have been given certain immunities from civil and criminal liabilities.

(xiii) Child Labor (Prohibition and Regulation) Act, 1986 - The Act prohibits employment of children below 14 years of age in certain occupations and processes and provides for regulation of employment of children in all other occupations and processes. Employment of child labor is prohibited in Building and Construction Industry.

(xiv) Inter-State Migrant Workmen's (Regulation of Employment and Conditions of Service) Act, 1979 - The Act is applicable to an establishment which employs 5 or more inter-state migrant workmen through an intermediary (who has recruited workmen in one state for employment in the establishment situated in another state). The inter-state migrant workmen, in an establishment to which this Act becomes applicable, are required to be provided certain facilities such as housing, medical aid, traveling expenses from home up to the establishment and back, etc

(xv) The Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 and the Cess Act of 1996 - All the establishments who carry on any building or other construction work and employ 10 or more workers are covered under this Act. All such establishments are required to pay Cess at rate not exceeding 2% of the cost of construction as may be notified by the Government. The employer of the establishment is required to provide safety measures at the building or construction work and other welfare measures, such as canteens, first-aid facilities, ambulance, housing accommodation for workers near the workplace etc. The employer to whom the Act applies has to obtain a registration certificate from the Registering Officer appointed by the Government.

98

Appendix 8: Sample Grievance Registration Form (To be available in Hindi and English)

The ______Project welcomes complaints, suggestions, queries, and comments regarding project implementation. We encourage persons with grievance to provide their name and contact information to enable us to get in touch with you for clarification and feedback. Should you choose to include your personal details but want that information to remain confidential, please inform us by writing/typing *(CONFIDENTIAL)* above your name. Thank you.

Date Place of registration Project Town

Project: Contact information/personal details Name Gender * Male Age * Female Home address Place Phone no. E-mail Complaint/suggestion/comment/question Please provide the details (who, what, where, and how) of your grievance below:

If included as attachment/note/letter, please tick here: How do you want us to reach you for feedback or update on your comment/grievance?

FOR OFFICIAL USE ONLY Registered by: (Name of official registering grievance)

Mode of communication: Note/letter E-mail Verbal/telephonic Reviewed by: (Names/positions of officials reviewing grievance)

Action taken:

Whether action taken disclosed: Yes No

99

Appendix 9: Sample Outline Spoils (Construction Waste) Management Plan

 The Spoil Management Plan should be site specific and be part of the monthly Construction Management Plan.  The contractor, in consultation with the PIU, has to find out appropriate location/s for the disposal of the excess soil generated. The spoils should be deposited only at these sites.  Further precautions need to be taken in case of the contaminated spoils  The vehicle carrying the spoil should be covered properly.  The spoils generating from each site should be removed on the same day or immediately after the work is complete. The site / road should be restored to the original condition.

I. Spoils information The spoil information contains the details like a) The type / material, b) Potential contamination by that type, c) Expected volume (site / component specific), d) Spoil Classification etc.

II. Spoils management The Spoil Management section gives the details of a) Transportation of spoil b) disposal site details c) Precautions taken d) Volume of contaminated spoil, if present, d) Suggested reuse of disposal of the spoil

III. Documentation The volume of spoil generated (site specific, date wise), site disposed, reuse / disposal details should be documented properly.

100

101

Appendix 10: Sample Outline Traffic Management Plan

A. Principles for TMP around the Water Pipes Construction Sites

1. One of the prime objectives of this TMP is to ensure the safety of all the road users along the work zone, and to address the following issues: (i) the safety of pedestrians, bicyclists, and motorists travelling through the construction zone; (ii) protection of work crews from hazards associated with moving traffic; (iii) mitigation of the adverse impact on road capacity and delays to the road users; (iv) maintenance of access to adjoining properties; and (v) addressing issues that may delay the project.

B. Operating Policies for TMP

2. The following principles will help promote safe and efficient movement for all road users (motorists, bicyclists, and pedestrians, including persons with disabilities) through and around work zones while reasonably protecting workers and equipment. (i) Make traffic safety and temporary traffic control an integral and high-priority element of project from planning through design, construction, and maintenance. (ii) Inhibit traffic movement as little as possible. (iii) Provide clear and positive guidance to drivers, bicyclists, and pedestrians as they approach and travel through the temporary traffic control zone. (iv) Inspect traffic control elements routinely, both day and night, and make modifications when necessary. (v) Pay increased attention to roadside safety in the vicinity of temporary traffic control zones. (vi) Train all persons that select, place, and maintain temporary traffic control devices. (vii) Keep the public well informed. (viii) Make appropriate accommodation for abutting property owners, residents, businesses, emergency services, railroads, commercial vehicles, and transit operations.

3. Figure A2 to Figure A12illustrates the operating policy for TMP for the construction of water pipes and the sewers along various types of roads.

C. Analyze the impact due to street closure

4. Apart from the capacity analysis, a final decision to close a particular street and divert the traffic should involve the following steps:

(i) approval from the ULB/Public Works Department (PWD) to use the local streets as detours; (ii) consultation with businesses, community members, traffic police, PWD, etc, regarding the mitigation measures necessary at the detours where the road is diverted during the construction; (iii) determining of the maximum number of days allowed for road closure, and incorporation of such provisions into the contract documents;

(iv) determining if additional traffic control or temporary improvements are needed along the detour route; (v) considering how access will be provided to the worksite; (vi) contacting emergency service, school officials, and transit authorities to determine if there are impacts to their operations; and (vii) developing a notification program to the public so that the closure is not a surprise. As part of this program, the public should be advised of alternate routes that commuters can take or will have to take as result of the traffic diversion.

5. If full road-closure of certain streets within the area is not feasible due to inadequate capacity of the detour street or public opposition, the full closure can be restricted to weekends with the construction commencing on Saturday night and ending on Monday morning prior to the morning peak period.

Figure A1: Policy Steps for the TMP

D. Public awareness and notifications

6. As per discussions in the previous sections, there will be travel delays during the constructions, as is the case with most construction projects, albeit on a reduced scale if utilities and traffic management are properly coordinated. There are additional grounds for travel delays in the area, as most of the streets lack sufficient capacity to accommodate additional traffic from diverted traffic as a result of street closures to accommodate the works.

102

6. The awareness campaign and the prior notification for the public will be a continuous activity which the project will carry out to compensate for the above delays and minimize public claims as result of these problems. These activities will take place sufficiently in advance of the time when the roadblocks or traffic diversions take place at the particular streets. The reason for this is to allow sufficient time for the public and residents to understand the changes to their travel plans. The project will notify the public about the roadblocks and traffic diversion through public notices, ward level meetings and city level meeting with the elected representatives.

7. The PIU will also conduct an awareness campaign to educate the public about the following issues:

(i) traffic control devices in place at the work zones (signs, traffic cones, barriers, etc.); (ii) defensive driving behaviour along the work zones; and (iii) reduced speeds enforced at the work zones and traffic diversions.

8. It may be necessary to conduct the awareness programs/campaigns on road safety during construction.

9. The campaign will cater to all types of target groups i.e. children, adults, and drivers. Therefore, these campaigns will be conducted in schools and community centres. In addition, the project will publish a brochure for public information. These brochures will be widely circulated around the area and will also be available at the PIU, and the contractor's site office. The text of the brochure should be concise to be effective, with a lot of graphics. It will serve the following purpose:

(i) explain why the brochure was prepared, along with a brief description of the project; (ii) advise the public to expect the unexpected; (iii) educate the public about the various traffic control devices and safety measures adopted at the work zones; (iv) educate the public about the safe road user behaviour to emulate at the work zones; (v) tell the public how to stay informed or where to inquire about road safety issues at the work zones (name, telephone, mobile number of the contact person; and (vi) indicate the office hours of relevant offices.

E. Install traffic control devices at the work zones and traffic diversion routes

10. The purpose of installing traffic control devices at the work zones is to delineate these areas to warn, inform, and direct the road users about a hazard ahead, and to protect them as well as the workers. As proper delineation is a key to achieve the above objective, it is important to install good traffic signs at the work zones. The following traffic control devices are used in work zones:

 Signs  Pavement Markings  Channelizing Devices  Arrow Panels  Warning Lights

103

11. Procedures for installing traffic control devices at any work zone vary, depending on road configuration, location of the work, construction activity, duration, traffic speed and volume, and pedestrian traffic. Work will take place along major roads, and the minor internal roads. As such, the traffic volume and road geometry vary. The main roads carry considerable traffic; internal roads in the new city areas are wide but in old city roads very narrow and carry considerable traffic. However, regardless of where the construction takes place, all the work zones should be cordoned off, and traffic shifted away at least with traffic cones, barricades, and temporary signs (temporary ―STOP‖ and ―GO‖).

12. Figure A2 to Figure A6 illustrates a typical set-up for installing traffic control devices at the work zone of the area, depending on the location of work on the road way, and road geometrics:  Work on shoulder or parking lane  Shoulder or parking lane closed on divided road  Work in Travel lane  Lane closure on road with low volume  Street closure with detour

13. The work zone should take into consideration the space required for a buffer zone between the workers and the traffic (lateral and longitudinal) and the transition space required for delineation, as applicable. For the works, a 30 cm clearance between the traffic and the temporary STOP and GO signs should be provided. In addition, at least 60 cm is necessary to install the temporary traffic signs and cones.

14. Traffic police should regulate traffic away from the work zone and enforce the traffic diversion result from full street closure in certain areas during construction. Flagggers/ personnel should be equipped with reflective jackets at all times and have traffic control batons (preferably the LED type) for regulating the traffic during night time.

16. In addition to the delineation devices, all the construction workers should wear fluorescent safety vests and helmets in order to be visible to the motorists at all times. There should be provision for lighting beacons and illumination for night constructions.

104

Figure A2 & A3: Work on shoulder or parking lane & Shoulder or parking lane closed on divided road

105

Figure A4 & A5: Work in Travel lane & Lane closure on road with low volume

106

Figure A6: Street closure with detour

107

Appendix 108

Appendix 11: Drinking Water Standards

No Substance or Requireme Undesirable effect Permissible Remarks . characteristic nt outside the desirable limit in the Desirable absence of limit alternate Source Essential Characteristic 1. Colour Hazen 5 Above 5, consumer 25 Extended to 25 Units, Max acceptance decreases only if toxic Substance are not suspect in absence of alternate sources 2. Odour Unobjectio - - a) test cold and nable when heated b) test are several dilutions 3. Taste Agreeable - - Test to be conducted only after safely has been established 4. Turbidity (NTU) 5 Above 5, consumer 10 - Max acceptance decreases 5. pH value 6.5 to 8.5 Beyond this range the No - water will after the relaxation mucous membrane and/or water supply system 6. Total 300 Encrustation in water 600 - Hardness supply structure and (mg/L) adverse effects on CaCO3 domestic use 7. Iron (mg/L, Fe) 0.3 Beyond this limit 1.0 - Max taste/appearance are affected; has adverse effects on domestic uses and water supply structure and promotes iron bacteria 8. Chlorides 250 250 Beyond effects 1000 - (mg/L, Cl) Max outside the desirable limit 9. Residual free 0.2 - - To be applicable Chlorine only when water is (mg/L), Max chlorinated. Tested at customer end. When protection against viral

108

Appendix 109

infection is required, it should be min. 0.5 mg/L. Desirable Characteristics 10 Dissolved 500 Beyond this, 2000 - . solids mg/L. palatability decreases Max and may cause gastrointestinal irritation. 11 Calcium (mg/L, 75 Encrustation in water 200 - . Ca) Max. supply structure and adverse effects on domestic use. 12 Magnesium 30 Encrustation in water 100 - . (mg/L, Mg) supply structure and Max adverse effects on domestic use. 13 Copper (mg/L, 0.05 Astringent taste dis 1.5 - . Cu) Max coloration and corrosion of pipes fittings and utensils will be caused beyond this. 14 Manganese 0.1 Beyond this limit 0.3 - . (mg/L, Mn) taste/appearance are Max affected, has advers effect on domestic use and water supply structure 15 Sulphate 200 Beyond this causes 400 May be extended . (mg/L, SO4) gastro intestinal upto 400 provided Max. irritation when magnesium (as magnesium or sodium Mg) does not are present exceed 30 16 Nitrate (mg/L, 45 Beyond this 100 - . NO3) Max. methaemoglobinemia takes place. 17 Fluoride (mg/L, 1.0 Fluoride may be kept 1.5 - . F) Max. as low as possible. High fluoride may cause fluorosis. 18 Phenolic 0.001 Beyond this, it may 0.002 - . Compounds cause objectionable (mg/L taste and odour C6H5OH) Max. 19 Mercury (mg/L 0.001 Beyond this the water No To be tested when . Hg) Max becomes toxic Relaxation. pollution is suspected 20 Cadmium 0.01 Beyond this the water No To be tested when (mg/L, Cd) becomes toxic Relaxation. pollution is

109

Appendix 110

Max suspected 21 Selenium 0.01 Beyond this the water No To be tested when . (mg/L, Se) Max becomes toxic. Relaxation. pollution is suspected 22 Arsenic 0.05 Beyond this the water No To be tested when . (mg/L, As) becomes toxic Relaxation pollution is Max. suspected 23 Cyanide 0.05 Beyond this the water No To be tested when . becomes toxic Relaxation pollution is suspected 24 Lead (mg/L 0.05 Beyond this the water No To be tested when . Pb) Max. becomes toxic Relaxation pollution is suspected 25 Zinc (mg/L, Zn) 5 Beyond this limit it can 15 To be tested when . Max. cause astringent taste pollution is and an opalescence in suspected water 26 Anionic 0.2 Beyond this limit it can 1.0 To be tested when . detergents cause a light froth in pollution is (mg/L, MBAS) water suspected Max 27 Chromium 0.05 May be carcinogenic - - . (mg/L, Cr6+ above this limit 28 Polynuclear - May be carcinogenic - - . Aromatic Hydrocarbons (mg/l, PAH) Max 29 Mineral oil 0.01 Beyond this limit, 0.03 To be tested when . (mg/L) undesirable taste and pollution is odour after suspected chlorination takes place 30 Pesticides Absent Toxic 0.001 - . (mg/L) max Radioactive materials 31 Alpha emitters - - 0.1 - . Bq/L Max 32 Beta emitters - - 1.0 - . Pci/L Max 33 Alkalinity 200 Beyond this limit, taste 600 - . (mg/L,) Max becomes unpleasant 34 Aluminum 0.03 Cumulative effect is 0.2 . (mg/L, Al) Max reported to cause dementia 35 Boron (mg/L) 1.0 - 5.0 - . Max

110

Appendix 111

Appendix 12: Sample Environmental Site Inspection Report

Project Name Contract Number

NAME: ______DATE: ______TITLE: ______DMA: ______LOCATION: ______GROUP: ______

WEATHER: Project Survey Activity Design Stage Implementation Pre-Commissioning Guarantee Period

Monitoring Items Compliance Compliance marked as Yes / No / Not applicable (NA) / Partially Implemented (PI) EHS supervisor appointed by contractor and available on site Archaeological Supervisor appointed by contractor and available on site Construction site management plan (spoils, safety, schedule, equipment etc.,) prepared Traffic management plan prepared Dust is under control Excavated soil properly placed within minimum space Construction area is confined; no traffic/pedestrian entry observed Surplus soil/debris/waste is disposed without delay Construction material (sand/gravel/aggregate) brought to site as & when required only Tarpaulins used to cover sand & other loose material when transported by vehicles After unloading , wheels & undercarriage of vehicles cleaned prior to leaving the site No AC pipes disturbed/removed during excavation No chance finds encountered during excavation Work is planned in consultation with traffic police Work is not being conducted during heavy traffic Work at a stretch is completed within a day (excavation, pipe laying & backfilling) Pipe trenches are not kept open unduly Road is not completely closed; work is conducted on edge; at least one line is kept open Road is closed; alternative route provided & public informed, information board provided Pedestrian access to houses is not blocked due to pipe laying Spaces left in between trenches for access Wooden planks/metal sheets provided across trench for pedestrian No public/unauthorized entry observed in work site Children safety measures (barricades, security) in place at works in residential areas Prior public information provided about the work, schedule and disturbances Caution/warning board provided on site Guards with red flag provided during work at busy roads Workers using appropriate PPE (boots, gloves, helmets, ear muffs etc) Workers conducting or near heavy noise work is provided with ear muffs

111

Appendix 112

Contractor is following standard & safe construction practices Deep excavation is conducted with land slip/protection measures First aid facilities are available on site and workers informed Drinking water provided at the site Toilet facility provided at the site Separate toilet facility is provided for women workers Workers camps are maintained cleanly Adequate toilet & bath facilities provided Contractor employed local workers as far as possible Workers camp set up with the permission of PIU Adequate housing provided Sufficient water provided for drinking/washing/bath No noisy work is conducted in the nights Local people informed of noisy work No blasting activity conducted Pneumatic drills or other equipment creating vibration is not used near old/risky buildings

Signature ______

Sign off

______Name Name Position Position

112

Appendix 113

113

Appendix 114

Appendix 13: Quarterly Reporting Format For Assistant Safeguards Officer

1. Introduction  Overall project description and objectives  Description of sub-projects  Environmental category of the sub-projects  Details of site personnel and/or consultants responsible for environmental monitoring  Overall project and sub-project progress and status

Status of Sub-Project No Sub-Project List of Progress Desig Pre- Construction Operational . Name Works of Works n Construction Phase            

2. Compliance status with National/ State/ Local statutory environmental requirements No. Sub-Project Name Statutory Environmental Status of Action Required Requirements Compliance

3. Compliance status with environmental loan covenants No. (List schedule Covenant Status of Compliance Action Required and paragraph number of Loan Agreement)

4. Compliance status with the environmental management and monitoring plan  Provide the monitoring results as per the parameters outlined in the EMP. Append supporting documents where applicable, including Environmental Site Inspection Reports.  There should be reporting on the following items which can be incorporated in the checklist of routine Environmental Site Inspection Report followed with a summary in the semi-annual report send to ADB. Visual assessment and review of relevant site documentation during routine site inspection needs to note and record the following: o What are the dust suppression techniques followed for site and if any dust was noted to escape the site boundaries; o If muddy water was escaping site boundaries or muddy tracks were seen on adjacent roads; o adequacy of type of erosion and sediment control measures installed on site, condition of erosion and sediment control measures including if these were intact following heavy rain; o Are their designated areas for concrete works, and refuelling;

114

Appendix 115 o Are their spill kits on site and if there are site procedure for handling emergencies; o Is there any chemical stored on site and what is the storage condition? o Is there any dewatering activities if yes, where is the water being discharged; o How are the stockpiles being managed; o How is solid and liquid waste being handled on site; o Review of the complaint management system; o Checking if there are any activities being under taken out of working hours and how that is being managed.

115

116 Summary Monitoring Table Impacts Mitigation Parameters Method of Location Date of Name of (List from Measures Monitored (As a Monitoring of Monitoring Person IEE) (List from minimum those Monitoring Conducted Who IEE) identified in the Conducted IEE should be the monitored) Monitoring Design Phase

Pre-Construction Phase

Construction Phase

Operational Phase

Overall Compliance with CEMP/ EMP No. Sub-Project EMP/ CEMP CEMP/ EMP Status of Action Name Part of Being Implementation Proposed and Contract Implemented (Excellent/ Satisfactory/ Additional Documents (Y/N) Partially Satisfactory/ Measures (Y/N) Below Satisfactory) Required

5. Approach and methodology for environmental monitoring of the project  Brief description on the approach and methodology used for environmental monitoring of each sub-project

6. Monitoring of environmental impacts on project surroundings (ambient air, water quality and noise levels)  Brief discussion on the basis for monitoring  Indicate type and location of environmental parameters to be monitored  Indicate the method of monitoring and equipment to be used  Provide monitoring results and an analysis of results in relation to baseline data and statutory requirements

As a minimum the results should be presented as per the tables below.

Air Quality Results Parameters (Government Site No. Date of Testing Site Location Standards)

Appendix 117

PM10 SO2 NO 2 µg/m3 µg/m3 µg/m3

Parameters (Monitoring Results) Site No. Date of Testing Site Location PM10 SO2 NO 2 µg/m3 µg/m3 µg/m3

Water Quality Results Parameters (Government Standards) Site Date of Sampling Site Location pH Conductivity BOD TSS TN TP No. µS/cm mg/L mg/L mg/L mg/L

Parameters (Monitoring Results) Site Date of Sampling Site Location pH Conductivity BOD TSS TN TP No. µS/cm mg/L mg/L mg/L mg/L

Noise Quality Results LA (dBA) (Government Standard) Site No. Date of Testing Site Location eq Day Time Night Time

LA (dBA) (Monitoring Results) Site No. Date of Testing Site Location eq Day Time Night Time

7. Summary of key issues and remedial actions  Summary of follow up time-bound actions to be taken within a set timeframe.

8. Appendixes  Photos  Summary of consultations  Copies of environmental clearances and permits  Sample of environmental site inspection report  Other

117

Appendix 118

Appendix 14: Application to the DFO for NOC for laying water pipeline between Patan to Tandukheda

118