Land Acquisition and Involuntary Resettlement Due Diligence Report

Document stage: Updated Project number: 42486-016 December 2018

IND: Urban Services Improvement Project – Subproject Group Water Supply Scheme towns , , , , Patan and under District and Tendukheda under District Damoh

Package No: MPUSIP-5B

Prepared by Urban Development and Environment Department, Bhopal Government of Madhya Pradesh for the Asian Development Bank.

This updated land acquisition and involuntary resettlement due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, management, or staff, and may be preliminary in nature. Your attention is directed to the ‘terms of use’ section on ADB’s website.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

CURRENCY EQUIVALENTS (as of 12 December 2018) Currency unit = Indian rupee (₹) ₹1.00 = $0.014 $1.00 = ₹70.14

ABBREVIATIONS

ADB - Asian Development Bank BPL - Below Poverty Line GOI - Government of GOMP - Government of Madhya Pradesh HHs - Households MPUDC - Madhya Pradesh Urban Development Company OHT - Over Head Tank O&M - Operation and Maintenance PIU - Project Implementation Unit PMC - Project Management Consultant PMU - Project Management Unit R&R - Resettlement and Rehabilitation RFCTLARR - The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 ROW - right-of-way RWA - Resident Welfare Associations SCADA Supervisory Controller and Data Acquisition SPS - Safeguard Policy Statement UADD - Urban Administration and Development Directorate UDED - Urban Development and Environment Department ULBs - Urban Local Body WRD - Water Resource Department WSS - Water Supply Scheme WTP - Water Treatment Plant

2

CONTENTS I. INTRODUCTION ...... 5 A. Background ...... 5 B. Project Description ...... 6 C. Scope of this Report ...... 6 II. POLICY FRAMEWORK, AND ENTITLEMENTS ...... 7 III. SUBPROJECT DESCRIPTION ...... 7 A. Description of Subproject ...... 7 B. Proposed Group Water Supply Scheme ...... 16 IV. FIELD WORK AND PUBLIC CONSULTATION ...... 19 A. Outline of Fieldwork ...... 20 B. Field Report ...... 20 C. Public Consultation ...... 20 V. LAND AVAILABILITY AND INVOLUNTARY RESETTLEMENT IMPACTS ...... 21 VI. BUDGET ...... 29 VII. CONCLUSIONS AND RECOMMENDATIONS ...... 30 A. Summary and Conclusions ...... 30 B. Next Steps ...... 30

FIGURE Figure 1: Location of each Subproject Towns under Package 5B Figure 2: KEY PLAN (PACKAGE 5B FEEDER MAIN) Figure 3: Location of proposed components on Google map Figure 4: Site Photographs

TABLE Table 1: Subproject Towns Population & Water Demand Table 2: Salient Feature of Subproject Towns and Existing WSS Table 3: Proposed Water Supply Subproject Components Table 4: Proposed WS Components in sub project towns Katangi, Patan, Majholi, Sihora, Panagar, Bhedaghat and Tendukheda and their involuntary resettlement impact Table 6: Budget

3

APPENDIX Appendix 1: Details of Land Ownership for each Proposed Water Works Component Appendix 2: Summary of Consultation with Stakeholders Appendix 3: Photographs of Stakeholder Consultation and List of Participants during Planning Phase Appendix 4: Photographs of Stakeholder Consultation and List of Participants during Implementation Phase Appendix 5: Photographs of Informal Consultation at Subproject Towns Appendix 6: Involuntary Resettlement Screening Checklist Appendix 7: No Objection Certificate (NoC) from WRD Appendix 8: Letter to MPRDC Ltd. to obtain NoC for laying the Pipelines with the RoW of road. . Appendix 9: Letter to MP Rural Road Development Authority to obtain NoC for laying the Pipelines with the RoW. Appendix 10: No Objection Certificate (NoC) obtained from NHAI To lay the Pipelines with the RoW. Appendix 11: Letter Written to PWD (Road & Bridge) To obtain NoC for laying the Pipelines with the RoW. Appendix 12: No Objection Certificate Issued by Rani Avanti Bai Lodhi Sagar Canal Prakosht to lay the Pipelines with the RoW and crossing of the canal. Appendix 13: Letter to Forest Department to obtain NoC for laying the Pipelines with the RoW. .. Appendix 14: Land Records of Proposed Component under WSS Scheme Appendix 15: Land Status Certificate Issued by Chief Municipality Officer (CMO) Appendix 16: Letter to District Collector from Nagar Parishad-Bhedaghat for land allocation for Proposed Components under WSS Appendix 17: Letter to District Collector from Nagar Parishad (Bhedaghat) for land allocation for Proposed Components under WSS Appendix 18: Letter to District Collector from Nagar Parishad (Katangi) for land allocation for Proposed Components under WSS Appendix 19: Letter to District Collector and Tehsildar from Nagar Parishad (Majholi) for land allocation for Proposed Components under WSS Appendix 20: Letter to District Collector and Tehsildar from Nagar Parishad (Panagar) for land allocation for Proposed Components under WSS Appendix 21: Letter to District Collector from Nagar Parishad (Sihora) for land allocation for Proposed Components under WSS Appendix 22: Letter to Tehsildar (Tendukheda) from Nagar Parishad (Sihora) for land allocation for Proposed Components under WSS

4

I. INTRODUCTION

A. Background

1. Government of Madhya Pradesh (GOMP) with a sector project loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as ‘the Project’. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Housing Department (UDHD) shall be the executing agency for the Project. A project management unit (PMU) created under MPUDC is implementing MPUSIP. The Project intends to ensure:

a) Continuous, pressurized, safe and sustainable drinking water through private household metered connections in 128 towns; b) Sewage and storm water collection and treatment systems are proposed in 12 identified towns including national heritage towns Sanchi and Khajuraho & Rajnagar; and c) Project also includes component of non -physical investment (GIS, MIS, M&E and Social Safeguards) for system strengthening.

2. The Project is planned to be implemented in three periods: (i) preparatory and procurement; (ii) construction and (iii) operations and maintenance. Prior to implementation of the project, Design Consultants were hired by Implementing Agency to develop Detailed Project Report (DPR) of each subproject town along with safeguard reports.

3. The Resettlement Framework for MPUSIP outlines the objectives, policy principles and procedures for land acquisition, if any, compensation and other assistance measures for Displaced Persons1 (DPs) / affected persons, if any. This framework reflects the borrower’s law on the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act 2013, state government policies, ADB’s Safeguard Policy Statement (SPS), 2009 and other social safeguard guidelines. A detailed description of compensation measures and assistance is provided in the entitlement matrix.

4. An entitlement matrix, consistent with the existing norms and guidelines of the country and the state government, and ADB’s Safeguard Policy Statement has been prepared to cover losses identified in this Project. The matrix recognizes that the lack of title/customary rights recognized under law will not be a bar to entitlement and has special provisions for non-titled persons. The eligibility for compensation will be determined through a cut-off date. People moving into the sub- project area after the cut-off date will not be entitled to compensation or other assistance.

5. Design, build and operate (DBO) model is adopted during construction and O&M phase and this includes (i) finalization of design of each subproject components (ii) construction of water supply facilities, using DBO model in all project towns the facilities will include raw water intakes, water treatment plants (WTP), overhead tanks (OHT), transmission line, distribution networks including the metered household connections. After the construction (expected to be completed

1 In the context of involuntary resettlement, displaced persons are those who are physically displaced (relocation, loss of residential land, or loss of shelter) and/or economically displaced (loss of land, assets, access to assets, income sources, or means of livelihoods) as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas. It covers them whether such losses and involuntary restrictions are full or partial, permanent or temporary 5

in 2 years), the DBO Contractors of the civil works packages will continue to operate and provide continuous water supply service for subprojects for a period of 10 years. The DBO contractor will also ensure proper metering and volumetric billing, adequate water pressure is maintained at the consumer end and supplied water complies with national quality standards for drinking water.

B. Project Description

6. As per revised procurement plan, MPUSIP’s physical components include (a) improvements to water supply scheme (WSS) in 69 subprojects, and (b) sewage collection and treatment services proposed in four (4) identified towns namely Saikheda, Sanawad, Anjad and Badwaha under tranche I while in tranche II – water supply scheme in 59 subprojects and sewage collection and treatment services proposed in eight towns namely Sanchi, Dhamnod, Mandsaur, Nagda, Jabalpur (part-II), Maihar, Khajuraho & Rajnagar. The objective of the proposed improvements in subprojects is to achieve safe and sustainable water services both in terms of services to customers, cost recovery and conservation of precious water resources. The project proposals envisage providing 100% coverage of population with continuous, pressurized and safe drinking water services and achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency. The main objectives of the Project are as follows:

• Supplying pure drinking water. • Promote sustainable measures to increase potable water supply to the population. • Water supply through future sustainable source developments. • Water supply through improvements of safe yield of existing water sources. • Water supply through improvements to water treatment works. • Drinking water supply contributes towards a sustainable regional development. • To improve the current state of the water cycle of subproject towns through improvements in the separate components of the water supply system in investment program

C. Scope of this Report

7. This land acquisition and involuntary resettlement due diligence report (DDR) is prepared for the proposed group water supply scheme for seven towns namely Katangi, Bhedaghat, Majholi, Panagar, Patan, Sihora and Tendukheda along with detailed project report (DPR) during preparatory stage. All the towns are municipal towns locally called Nagar Parishads (NPs) located in Jabalpur and Damoh district. Proposed components of the group water supply subproject include construction of common water intake, water treatment plant (WTP), separate storage reservoirs as per demand of the towns, transmission mains and distribution system. The proposed subproject provides metered water supply for domestic, institutional and commercial users including metered connections to each household in the subproject towns. All municipal wards of the towns are covered under the Project. Thus, the total population of the town, 139,910 as per census 2011 and 221,964 projected population in the design year 2048 will be covered.

8. During preparatory stage of the Project, a due diligence process was conducted to examine the land acquisition and involuntary resettlement issues in line with ADB SPS 2009 and Involuntary Resettlement DDR was prepared and submitted to ADB. Thereafter, detailed design and detailed measurement surveys (DMS) was jointly conducted by DBO Contractor, The Indian Hume Pipe Company Limited, Bhopal, safeguard personnel of PIU Jabalpur and field engineer of Project Management Consultant (PMC) before initiation of civil works and during implementation period, in which involuntary resettlement impacts are reconfirmed and Updated Involuntary

6

Resettlement DDR (draft) is prepared. The final Involuntary Resettlement report will be reviewed and disclosed on website of urban local body (ULB), Implementing Agency and ADB. No construction work will commence before the updated social safeguard document for the package is reviewed and approved by ADB and compensation to affected persons, if any, paid. The Implementing Agency is responsible to hand over the project lands/sites to the contractor which should be free from all encumbrances.

9. This report describes the findings and provides copies of relevant documents, maps, minutes of meetings and photographs. This land acquisition and involuntary resettlement due diligence report needs to be read along with the Resettlement Framework prepared for MPUSIP.

II. POLICY FRAMEWORK, AND ENTITLEMENTS

10. The Resettlement Framework prepared for MPUSIP sets out the objectives, principles, eligibility criteria and entitlements for APs, based on ADB SPS, 2009 and LARR 2013 as well as national and state laws for protection of street vendors. Until recently, all activities related to rehabilitation and resettlement in the State of MP had been based on the Madhya Pradesh Resettlement and Rehabilitation Policy, 2002 (MPRR) and National Rehabilitation and Resettlement Policy, 2007 (NRRP-2007). GOMP adopted LARR 2013 on 3rd October 2014 with some specifications for operationalizing its implementation in the state.1 Details of policies are in the Resettlement Framework for MPUSIP, visit website - http://www.mpudc.co.in/mpusip-adb- funded.html.

III. SUBPROJECT DESCRIPTION

A. Description of Subproject

11. A group WSS for seven towns namely Katangi, Bhedaghat, Majholi, Panagar, Patan and Sihora under District Jabalpur and Tendukheda under District Damoh is framed with common water source and WTP. Location coordinates of the seven towns under this subproject are described below and Google Earth images are shown in Figures 1, 2 and 3:

(a) Katangi: Geographically, Katangi town is located at 23° 27'49’’ North Latitude and 79° 47'38’’ East Latitude, at an average elevation of 373 meters above Mean Sea Level. The town is situated on State Highway 37 connecting Jabalpur and Damoh. It is located 38 from Jabalpur towards the North-West and 22 km North of Katangi. The town area is divided in 15 wards. (b) Bhedaghat: Geographically, Bhedaghat lies between 23°08’N 79°48’E, 23°13°N 79°80°E. Bhedaghat is located at 25 kilometers. from Jabalpur and 5 kilometers. eastern side on the State Highway 12A leading towards Bhopal- Jabalpur. Presently Bhedaghat has 15 wards. (c) Majholi: Geographically Majholi town is located at 23° 30' 0’’ North Latitude and 79° 55' 12’’ East Latitude, at an altitude of 385 meters above mean sea level. The town is situated on Road connecting Sihora Gubra. The distance from Jabalpur is

1 These GOs issued separately in September 2014 (i) notifies administrative cost of land acquisition; (ii) appoints Divisional Commissioners as Commissioner for Rehabilitation & Resettlement within their respective jurisdictions; (iii) authorizes District Collectors for constituting an Expert Group separately in respect of each project, (iv) notifies the factor which the market value is to be multiplied in case of rural areas, (v) appoints Officer-in charge of Land Acquisition Section in the Office of the Collector as Administrator for Rehabilitation and Resettlement an d (vi) limits agricultural land acquisition, as required by the RTFCLARR, 2013. 7

around 47 kilometers. Majholi Town is located at distance of 30 kilometers. for Sihora. The area of the town is spread over in 629.00 Ha (6.29 Sq Kilometers) as per 2011 data. (d) Panagar: Geographically, Panagar lies between 23°9'58"N and 79°56'33" E. Panagar is situated on NH – 7 connecting Nagpur – . The distance from Jabalpur is about 16 Kilometers. Panagar is divided into total 15 Wards. (e) Patan: Geographically, this town lies between 220 31’ 48’’ north latitude and 790 25’ 12’’ east Longitude, at an altitude of 379 meters above mean sea level and is nearly 33 Kilometers. from Jabalpur. The municipal council was constituted in the year 1981, with an area of 13.06 sq. kilometers and comprising of 15 municipal wards. (f) Sihora: Geographically, Sihora town is located at Latitude 23° 28’ 48’’ N Longitude 80° 7' 12’’ E, Town is situated at average elevation of 386 m from Mean Sea Level. The year of Establishment of Sihora ULB is 1967. The area of the town is spread over in 2302.00 Ha (23.02 Sq Kilometers) as per 2011 data. The town area is divided in 18 wards. (g) Tendukheda: Geographically, Tendukheda town is located at Latitude 23° 23'59’’ N Longitude 79° 32'59’’E.It is 260 kilometers. from the state capital of Bhopal and around 52 kilometers. from district headquarter Damoh. Town is situated at average elevation of 398 m from Mean Sea Level. The area of the town is spread over in 1400.00 Ha (14.00 sq kilometers) as per 2011 data. The year of establishment of Tendukheda ULB is 1984. The town area is divided in 15 wards.

12. Existing Water Supply System: Subproject population, water demand and existing water supply arrangements of group WSS of towns Katangi, Bhedaghat, Majholi, Panagar, Patan, Sihora and Tendukheda are detailed in Table 1 and Table 2:

Table 1: Subproject Population and Water Demand

S. No. Particulars Details 1 Town Katangi, Bhedaghat, Majholi, Panagar, Patan, Sihora and Tendukheda 2 District All subproject towns under Package 5B comes under district Jabalpur except Tendukheda (district Damoh) 3 Population of all seven 139910 towns - As per 2011 census 4 Projected Population- 4.1 In year 2018 152228 4.2 In year 2033 185462 4.3 In year 2048 221964 5 Projected Water Demand 5.1 Per Capita Demand 70 liters per capita per day (lpcd) except subproject towns Bhedaghat and Sihora @ 135 lpcd 5.2 In year 2018 16.81 MLD 5.3 In year 2033 20.53 MLD 5.4 In year 2048 24.68 MLD

8

Table 2: Subproject population, water demand and existing water supply scheme

Katangi Sl. No. Particulars Details

1 Town Katangi 2 District Jabalpur 3 Location 38 Kilometers. from Jabalpur 4 Geographical Co-ordinate Latitude 23° 27'49’’ N Longitude 79° 47'38’’ E 5 Population - As per 2011 19040 census 6 Projected Population- 6.1 In year 2016 20386 6.2 In year 2018 20924 6.3 In year 2033 24962 6.4 In year 2048 28999 7 Projected Water Demand @ 70 lpcd 7.1 Per Capita Demand 70 lpcd 7.2 In year 2016 1.70 MLD 7.3 In year 2018 1.75 MLD 7.4 In year 2033 2.08 MLD 7.5 In year 2048 2.42 MLD 8.0 Existing Water Supply System 8.1 Water Source Ground water: Tube well 10 in numbers (Nos.) Surface source: Nil

8.2 Total supply 0.60 MLD (25.00 lpcd including 20% losses) 8.3 Overhead Tank/GSR Location of Capacity in (in KL) Staging Height OHTs/GSRs

Nagar Parishad OHT 150 KL 12 m (Structurally good and it Ward no.5 is in use)

Ward no.12 OHT 200 KL 15 m (Structurally good and it is in use) Ward no.15 OHT 250 KL 12 m (Structurally good and it is in use)

9

Sl. No. Particulars Details

8.4 Distribution Network Dia. ( mm) Material 50 mm -200 mm GI, CI 8.5 Water Connection Domestic (nos.) Non-Domestic (nos.)

465 02 8.6 Water Tariff Domestic (Rs.) Non-Domestic (Rs.)

45/- 90/-

Patan SI.No. Particulars Details 1 Town Patan 2 District Jabalpur 3 Location 33 Kilometers. from Jabalpur 4 Geographical Co-ordinate Latitude 220 31’ 48’’ N Longitude 790 25’ 12’’ E 5 Population - As per 2011 14624 census 6 Projected Population- 6.1 In year 2016 15525 6.2 In year 2018 15885 6.3 In year 2033 18587 6.4 In year 2048 21289 7 Projected Water Demand @ 70 lpcd

7.1 Per Capita Demand 70 lpcd 7.2 In year 2016 1.30 MLD 7.3 In year 2018 1.33 MLD 7.4 In year 2033 1.55 MLD 7.5 In year 2048 1.78 MLD 8.0 Existing Water Supply System 8.1 Water Source Ground water: Tube well (19 Nos.) Surface source: Nil

8.2 Total supply 0.88 MLD (48.00 lpcd including 20% losses) 8.3 Overhead Tank/GSR Location of Capacity (in KL) Staging Height OHTs/GSRs

10

SI.No. Particulars Details Ward no.15 OHT 908 KL 15 m (Structurally good and it is in use)

8.4 Distribution Network Dia.(mm) Material 150-250 ACP, GI

8.5 Water Connection Domestic (nos.) Non-Domestic (nos.)

950 70

8.6 Water Tariff Domestic (Rs.) Non-Domestic (Rs.)

60/- 90/-

Majholi S. No. Particulars Details 1 Town Majholi 2 District Jabalpur 3 Location 47 Kilometers. from Jabalpur 4 Geographical Co- Latitude 23° 30' 0’’ N Longitude 79° ordinate 55' 12’’ E 5 Population - As per 2011 13210 census 6 Projected Population- 6.1 In year 2016 13959 6.2 In year 2018 14258 6.3 In year 2033 16504 6.4 In year 2048 18750 7 Projected Water Demand @ 70 lpcd

7.1 Per Capita Demand 70 lpcd 7.2 In year 2016 1.16 MLD 7.3 In year 2018 1.19 MLD 7.4 In year 2033 1.38 MLD 7.5 In year 2048 1.56 MLD 8.0 Existing Water Supply System 8.1 Water Source Ground water: Tube well (11 Nos.) Surface source: Suhar River

8.2 Total supply 0.70 MLD (42.00 lpcd including 20% losses)

11

S. No. Particulars Details 8.3 Intake well 1 no., 25 years old not in working condition 8.4 WTP 0.70 MLD not in working condition 8.5 Overhead Tank/GSR Location of Capacity (in KL) Staging Height OHTs/GSRs Ward no.1 OHT 100 KL 15 m (Structurally good and it is in use) Ward no.9 OHT 115 KL 15 m (Structurally good and it is in use)

Ward no.13 OHT 320 KL (newly 18 m constructed)

Ward no 15 180 KL (newly 18 m constructed) 8.6 Distribution Network Dia.(mm) Material

50-150 ACP, GI

8.7 Water Connection Domestic (nos.) Non-Domestic (nos.) 400 03

8.8 Water Tariff Domestic (Rs.) Non-Domestic (Rs.)

40/- 70/-

Sihora S.No. Particulars Details 1 Town Sihora 2 District Jabalpur 3 Location 42 Kilometers. from Jabalpur 4 Geographical Co-ordinate Latitude 23° 28’ 48’’ N Longitude 80° 7' 12’’ E 5 Population - As per 2011 44062 census 6 Projected Population- 6.1 In year 2016 47236 6.2 In year 2018 48541 6.3 In year 2033 58965 6.4 In year 2048 70514

12

S.No. Particulars Details 7 Projected Water @ 135 lpcd Demand 7.1 Per Capita Demand 135 lpcd 7.2 In year 2016 7.52 MLD 7.3 In year 2018 7.73 MLD 7.4 In year 2033 9.39 MLD 7.5 In year 2048 11.23 MLD 8.0 Existing Water Supply System 8.1 Water Source Ground water: Tube well (30 Nos.) Surface source: Hiran River

8.2 Total supply 2.00 MLD (36.00 lpcd including 20% losses) Intake well 1 No. 6m Dia. & 18 m height (Cons.Yr.1973) WTP 4 MLD, 42 years old 8.4 Clear water rising main Dia.(mm) Material Condition

160 PVC Not useful

8.5 Overhead Tank/GSR Location of OHTs/GSRs Capacity (in KL)

Ward no. 4 GSR 300 KL

Ward no.14 GSR 400 KL

Ward no.18 GSR 200 KL

8.6 Distribution Network Dia.(mm) Material 110 PVC, GI

8.7 Water Connection Domestic (nos.) Non-Domestic (nos.) 5488 115

8.8 Water Tariff Domestic (Rs.) Non Domestic (Rs.) 80/- 120/-

Bhedaghat S.No . Particulars Details

1 Town Bhedaghat 2 District Jabalpur 3 Location 25 Kilometers. from Jabalpur 4 Geographical Co-ordinate Latitude 23°13°N Longitude 79°80°E

13

S.No . Particulars Details

5 Population - As per 2011 6657 census 6 Projected Population- 6.1 In year 2016 5174 6.2 In year 2018 5436 6.3 In year 2033 7777 6.4 In year 2048 10784 7 Projected Water @ 135 lpcd Demand 7.1 Per Capita Demand 135 lpcd 7.2 In year 2016 0.82 MLD 7.3 In year 2018 0.87 MLD 7.4 In year 2033 1.21 MLD 7.5 In year 2048 1.24 MLD

8.0 Existing Water Supply System 8.1 Water Source Ground water: Tube well (4 Nos.) Surface source: (Direct pumping at various points (Gopalpur, Paramhans Ghat and Banerji Ghat) 8.2 Total supply 0.07 MLD from ground water 0.13 mld from surface water (44.00 lpcd including 20% losses) 8.3 Water connection Domestic 368 nos. 8.8 Water Tariff Domestic (Rs.) Non Domestic (Rs.)

30/- 60/-

Panagar S. No. Particulars Details 1 Town Panagar 2 District Jabalpur 3 Location 16 Kilometers. from Jabalpur 4 Geographical Co-ordinate Latitude 23°9'58"N Longitude 79°56'33"E

5 Population - As per 2011 27932 census 6 Projected Population-

14

S. No. Particulars Details 6.1 In year 2016 29947 6.2 In year 2018 30753 6.3 In year 2033 36798 6.4 In year 2048 42843 7 Projected Water @ 70 lpcd Demand 7.1 Per Capita Demand 70 lpcd 7.2 In year 2016 2.50 MLD 7.3 In year 2018 2.57 MLD 7.4 In year 2033 3.07 MLD 7.5 In year 2048 3.57 MLD 8.0 Existing Water Supply System 8.1 Water Source Ground water: Tube well (23 nos. working) Surface source: Nil

8.2 Total supply 0.50 MLD (39.00 lpcd including 20% losses) 8.3 Overhead Tank/GSR Location of Capacity (in KL) Staging Height OHTs/GSRs Ward no.8 OHT 200 KL 15 m (Structurally good and it is in use) Ward no.14 OHT 100 KL 12.5 m (Structurally good and it is in use)

Ward no.15 OHT 250 KL 15.0 m (Structurally good and it is in use)

8.4 Distribution Network Dia.(mm) Material 110 PVC, GI 8.5 Water Connection Domestic (nos.) Non-Domestic (nos.)

1989

8.6 Water Tariff Domestic (Rs.) Non Domestic (Rs.)

70/- 100/-

Tendukheda S.No. Particulars Details 1 Town Tendukheda

15

2 District Damoh 3 Location 52 Kilometers. from Damoh 4 Geographical Co-ordinate Latitude 23° 23'59’’ N Longitude 79° 32'59’’E

5 Population - As per 2011 14399 census 6 Projected Population-

6.1 In year 2016 15818 6.2 In year 2018 16431 6.3 In year 2033 21869 6.4 In year 2048 28785 7 Projected Water @ 70 lpcd Demand

7.1 Per Capita Demand 70 lpcd 7.2 In year 2016 1.32 MLD 7.3 In year 2018 1.37 MLD 7.4 In year 2033 1.82 MLD 7.5 In year 2048 2.40 MLD 8.0 Existing Water Supply System 8.1 Water Source Ground water: Tube well (12 Nos.) Surface source: Nil 8.2 Total supply 0.72 MLD (40.00 lpcd including 20% losses) 8.3 Distribution Network Dia.(mm) Material

110 PVC, GI

8.4 Water Connection Domestic (nos.) Non-Domestic (nos.) 2000 07 8.5 Water Tariff Domestic (Rs.) Non Domestic (Rs.) 80/- 120/-

B. Proposed Group Water Supply Scheme

13. The primary objectives of the proposed water supply subproject include:

➢ service improvements to achieve safe and sustainable water services both in terms of services to residents and cost recovery; ➢ conservation of precious water resources. The project envisages providing 100 percent coverage of population with continuous, pressurized and safe drinking

16

water services and achieving progressively increase cost recovery by expanding the coverage and increasing operating efficiency.

14. Sustainable water supply is a problem for all towns of the proposed subproject as their water source is far and currently not reliable. Water source for Panagar and Bhedaghat is river Narmada near Jabalpur. Water source of Patan is also river Narmada. Distance of each town from the other and to Jabalpur ranges approximately 16 to 56 kilometer. Sihora is approximately 25 kilometers from Panagar and Majholi is approximately 20 km from Sihora; Katangi is 20 kilometers from Majholi and Tedukheda is nearly 20 kilometers away from Patan. A common water scheme for all these towns including Tendukheda is linked to the river Narmada. If combined water scheme is prepared, storage and intake structure costs can be avoided. Feasibility and viability study is worked out through survey and investigation.

15. For this resolve, the water source for the proposed subproject is Narmada River, where intake well will be installed. Previous identified location of the proposed intake well was on left bank of river Narmada at Bhedaghat, however it was changed during visit of ADB mission. The new proposed location is on upstream of the river Narmada on right side of the bank near Lamhetaghat.

16. The proposed subproject components are described below and presented in Table 3.

17. Intake well: The common intake well of 27.93 MLD is proposed for Katangi, Patan, Majholi, Sihora, Panagar, Bhedaghat and Tendukheda Nagar Parishad at Bhedaghat near Lamhetaghat on the bank of Narmada river. There is proposed R.C.C. intake well of 10 m diameter and 35 m height to collect and lift water up to treatment works.

18. Raw Water Rising Main (RWRM): There will be common raw water rising main for Katangi, Patan, Majholi, Sihora, Bhedaghat and Panagar. The proposed raw water rising main is 339 m long 600 mm dia. DI K9 from proposed Intake well to proposed WTP.

19. Water Treatment Plant (WTP): The common WTP for all these towns having capacity of 31.00 MLD considering 22 hours of pumping is located at Lamhetaghat.

20. Clear Water Sump well at WTP: The clear water sump is proposed to 1147 KL of sump well at WTP for storing clear water after treatment from WTP.

Table 3: Proposed Water Supply Subproject Components

Particulars Bhedaghat Katangi Majholi Panagar Patan Sihora Tendukheda Proposed system 1 From Raw water abstraction from Narmada river raw water transmission (pumping) treatment source to clear water transmission (pumping) storage distribution house connections with meters consumer supply Proposed components 1 Water The common intake well is proposed for Katangi, Patan, Majholi, Sihora, Panagar, intake Bhedaghat and Tendukheda Nagar Parishad at Lamhetaghat. At Lamhetaghat on the bank of Narmada river, there is proposed R.C.C. intake well of 10 m diameter and 35m height

17

Particulars Bhedaghat Katangi Majholi Panagar Patan Sihora Tendukheda 2 Pumping Three nos. vertical turbine type pump with 50% as standby is proposed at intake well. The stations discharge of each pump is (23.32 MLD) 269.91 LPS and head is 47 meters at intermediate stage Yr.2033. The rating of each pump is 58.92 KW (say 59.0 KW). Two nos. working and one pump will be as a standby. This will be replaced by 27.93 MLD or 323.26 LPS discharging capacity at 47 m head pumps of 71.5 KW in year 2048. The pumping is proposed for 22 hours. 3 Raw water There will be common raw water rising main for Katangi, Patan, Majholi, Sihora, Rising Main Bhedaghat, Tendukheda and Panagar. The proposed raw water rising main is 339 m long 600 mm dia. DI K9 from proposed Intake well to proposed WTP. 4 WTP A common WTP for all the towns having capacity of 31.00 MLD considering 22 hours of pumping and designed to last until 2048 is proposed at Bhedaghat. Coordinates of this component as of 4/2/2018 is 23°06'29.31" N 79°49'51.24" E elevation 1269 feet eye alt 2553 feet Process/components for all towns: Coagulation &flocculation, sedimentation, rapid gravity filtration, chlorination, wash water recovery, sludge drying beds, tube settlers & miscellaneous infra (compound wall, landscaping, lighting, rest rooms etc.) Location: On a government land (1.5 has available) in ward no. 14, near Lametaghat.

5 Sump Wells (i) At Lamhetaghat (Bhedaghat): 1147 KL of sump well at WTP for storing Clear water after treatment from WTP. Coordinates of this component as of 4/2/2018 is 23°06'29.31" N 79°49'51.24" E elevation 1269 feet eye alt 2553 feet (ii) At Sihora - 245 KL at ward no. 9, Coordinates of this component as of 4/2/2018 is 23°05'43.06" N 80°05'42.32" E elevation 1277 feet eye alt 1669 feet (iii) Majholi- 35 KL, Coordinates of this component as of 4/2/2018 is 23°29'59.06" N 79°55'03.06" E elevation 1301 feet eye alt 1686 feet (iv) Tendukhera 52 KL, Coordinates of this component as of 1/11/2018 is 23°19'17.56" N 79°39'18.60" E elevation 1226 feet eye alt 1579 feet (v) Tendukhera 52 KL (BPT) Coordinates of this component as of 1/11/2018 is 23°20'48.69" N 79°36'41.67" E elevation 1793 feet eye alt 2190 feet

Overhead Two (2) One (1) Not Three (3) Not Four (4) Two OHTs Tanks OHTs with OHT with Proposed OHTs with Proposed OHTs with with capacity (OHTs) capacity of: capacity capacity of: capacity of: 1. 200 KL of: 1. of: 1. 300 1. 9 (at 120 KL of 700 KL (at KL (at ward 00 KL (at ward staging ward No. 11, No. 09, Panagar) ward No. 04, height Tendukheda) Bhedag 12m (at No.11, 2. 600 2. 325 hat) ward No. Kl (at ward Sihora) 2. 220 KL 02, No. 4, 2. 9 KL (at ward No. 11 (at Katangi Panagar) 20 KL (at Tendukheda) ward 3. 200 ward no. No .13, Kl (at ward 4, Sihora) Bhedag No. 4, 3. 6 hat) Panagar) 30 KL (at ward No. 17, Sihora) 4. 620 KL (at ward

18

Particulars Bhedaghat Katangi Majholi Panagar Patan Sihora Tendukheda No.13, Sihora)

6 Clear water 150 to 200 100 to 500 100 to 100 to 500 150 to 200 to 450 150 to 200 200 mm mm dia DI- 600 mm mm dia transmission mm pipes mm dia mm DI-K9 dia DI-K9 K9 pipe dia DI-K9 DI-K9 pipe DI K9 and K7 dia DI- K9 pipe Belkhadu pipe Sump well pipes from pipe From Pipes sump feeder To Panagar WTP To to Sihora Nunsar to well to WTP to main from Length: Nunsar Length Belkhadu Tendukhera Bhedaghat sump well 18504 m To Patan 29458 m 5826 m to Katangi Pahari, to Majholi 31608m Length - Dia 100 Pipes 23997 m To 500 Length 31848 m 17253m

7 Distribution 21,150m 38,958m – 31,708m 54,897m – 36,228m 104,586m 40,923m – network – 110 mm 110 mm to 110 mm 110 mm to 110 mm – 110 mm to To 200 200mm to 250 315 mm to 280 110 mm to 250 mm mm dia HDPE mm HDPE mm 315mm HDPE HDPE Location: HDPE Location: HDPE HDPE Location: Along the pipes Along the Location: Along the Location: Location: public roads Location: public Along the public Along the Along roads in in the entire Along the roads in public public th the entire town. public the entire roads in roads in e public town. roads in the town. the entire the entire roads in entire town. town. town. the entire town. 8 Bulk flow Electromagnetic Bulk flow meter will be installed to monitor the bulk flow in the main meters components i.e. at the inlet of the raw water mains to know the quantity of water coming to the WTP, outlet of the clear water sump to know the quantity of water going for the distribution, outlet of the service reservoirs to know the quantity of water going in the distribution zone or DMA. This will help in maintaining the UFW in the limit and also equitable distribution of the water.

9 Consumer Approximately a total of 28284 household connections for all towns connects with meters

21. Key Plan of feeder main is shown on Figure 2 and location of the proposed components is shown on Google Earth map in Figure 3.

IV. FIELD WORK AND PUBLIC CONSULTATION

22. This involuntary resettlement document is prepared in consultation with stakeholders including local residents, beneficiaries/consumer, and Urban Local Body (ULB) officials/representatives. Informal consultations and focus group discussions (FGDs) were

19

conducted to seek feedback from local people and other important stakeholders on the proposed development interventions, perceived impacts and mitigation measures and their participation.

A. Outline of Fieldwork

23. During the visit, a field inspection of proposed subproject facility locations and pipeline alignments was undertaken. Identified proposed site facilities and pipeline alignments were inspected and stakeholder consultations were held. The land requirements including identified government lands for the proposed subproject components were also examined. The details of proposed land parcels for subproject components are given in the Appendix-1.

B. Field Report

24. Team of the Consultant met the concerned ULB officials, public representatives; stakeholders and residents of subproject towns to collect data / information for proposed subproject during various discussions/meetings.

• During meeting and discussion, data was collected about the existing water supply in the respective towns and the requirement of the stakeholders. Based on present water supply arrangements and gaps arrived are well documented. • Along with the ULB officials, visited all the possible water supply sources and identified locations for all components of proposed water supply scheme. • All the options of possible water supply source, its dependability, quality assurance of source available and the distance from the town, were studied and discussed with the stakeholders. • Water from the selected source was collected and tested in Bhopal Municipal Corporation Laboratory at Bhopal. Also test report is obtained for designing purpose. • Water security is ensured during consultation with the concerned department like WRD etc. such that best-chosen water source is made available to ULB for the purpose of water supply scheme. • Revenue authorities were contacted to ensure that the land required for facilities in the town is secured and under the ownership of government departments such as ULB or Revenue Department, Govt. of Madhya Pradesh etc. for construction of Project facilities.

C. Public Consultation

25. Stakeholder mapping was undertaken as the first step and the major potential stakeholders listed:

(a) The municipality (Nagar Parishads), its elected members and staff who will be required to oversee the construction of the distribution networks and WTP as well as be directly responsible for the maintenance of the installations (b) Concerned government departments (Water Resources Department, Revenue Department, PWD, NHAI, Irrigation department etc.) (c) Local residents who will take initiative to connect their houses with the water distribution line. (d) Local business persons and traders (e) School and College Students

20

(f) Opinion makers or prominent citizens/residents, who are intimately acquainted to and well regarded by the community. They need to be enlisted in spreading environmental awareness within the community as well as in conveying the benefits of the project.

26. Consultations were undertaken with key stakeholders in line with ADB’s requirements pertaining to environment and social considerations. Tools used for consultation were formal stakeholder meetings and focus group discussions (FGD). Extensive consultations with stakeholders (municipality, concerned government departments, community members including slum dwellers, and traders’ associations) including individual face to face interviews and public consultations were conducted. Informal meetings were also conducted during visit. No users (boatmen and washer men) were found at the intake site which is vacant and unused, hence no special consultation was conducted with them.

27. Potential impacts and mitigation measures for the proposed subproject sites and pipeline alignments were discussed with stakeholders. These consultations helped identify the felt needs/concerns, apprehensions of the communities and priorities of concerned stakeholders related to the proposed subproject. Discussions were held with people residing at and/or having businesses at/near the proposed subproject site locations. Consultations also revealed that people were aware of the problems of the existing water supply system in their towns as they were getting 35 lpcd, hence they were willing to cooperate in the proposed project. Summary of consultations held with stakeholders during planning and implementation phase is provided in Appendix 2 while photographs and list of participants are provided as Appendix 3 and 4, respectively. Informal consultations were also held during implementation phase, refer to Appendix 5.

V. LAND AVAILABILITY AND INVOLUNTARY RESETTLEMENT IMPACTS

28. No land acquisition or resettlement impacts are anticipated for any of the proposed civil works for group water supply subproject. Narmada River is selected as common water source and proposed common components such as Intake well, WTP, Raw water rising main are located at Bhedaghat. Clear water feeder main, OHTs and water distribution networks are proposed for each town.

29. Land identified for the proposed subproject components belongs to government. All the land is vacant, unused and encroachment free, therefore, there is no hurdle to start of civil works. Most of the proposed sites are under possession of concerned ULBs or proposed land parcels belongs to revenue department, proposal has been submitted to District Collector and process of land transfer is in progress. The concerned Chief Municipality Officers (CMOs) of each town has issued land status certificates and has submitted application to the office of the District Collector to allot the proposed site for construction and also transfer the proposed site/land in the name of ULB (refer to Table 4 and Appendix 15,16, 17, 18, 19, 20, 21 and 22).

30. Change of the locations of subproject components during implementation. Location of proposed subproject facilities including the (i) common intake well and WTP in Bhedaghat and (ii) OHTs at Sihora were changed during implementation phase. During visit of ADB Mission in October 2017, it was noted that the location of Intake well and WTP at Bhedaghat had very high aesthetic and scenic value and good tourism potential and construction at this site can adversely impact the tourism activities. Moreover, proposed site is located within 300 meters from Archaeological Survey of India’s (ASI) protected monument namely “Chousat Yogini Temple” notwithstanding, no objection certificate (NoC) has been obtained from ASI before start of 21

construction. An OHT site (900 KL) at Sihora was changed due to insufficient area (at the previous location) needed for construction. Another OHT site (620 KL) at Sihora was changed due to absence of the approach road to the site.

31. Common Intake well at Lamhetaghat: Location of intake well was changed from Bhedaghat to Lamhetaghat on the banks of Narmada River. The proposed R.C.C. intake well of 10 m diameter and 35 m height will collect and lift water up to treatment works. All group towns applied permission from Water Resource Department (WRD) for extraction and construction and no objection certificate (NOC) from WRD has been obtained (refer to Appendix 7).

32. Water Treatment Plant (WTP) at Lamhetaghat and OHTs at Bhedaghat. Location of WTP was changed from Bhedaghat to Lamhetaghat, with Khasra Numbers 171, 173 and 175 belonging to revenue department. Clear Water Sump well with capacity of 1147 KL is proposed within the premises of WTP for storing clear water after treatment from WTP .This site is located near the proposed new site of Intake well, about 339 m away. Two OHTs (220 KL & 200 KL) located at Bhedaghat are proposed at Khasra No. 153/2 and Khasra No. 72 respectively. These proposed land parcels belong government and under the possession of Nagar Parishad- Bhedaghat. These sites are vacant and without any settlement/ squatter /cultivation or other developments. Therefore, no involuntary resettlement impact is anticipated. The Chief Municipal Officer (CMO) of Bhedaghat issued a land status certificate (refer to Appendix 5) and has written a letter to District Collector, Jabalpur for the transfer of proposed land (refer to Appendix 16 and 17).

33. Raw water rising main (RWRM). The proposed raw water rising main is now 339 m long (from previous 330 m) with 600 mm dia. Ductile Iron K9 pipes are proposed to be installed from intake well to WTP. The land is under possession of revenue department from many years and no involuntary resettlement impact is anticipated.

34. OHTs at Katangi. There is only one proposed OHT having capacity 120 KL with staging height 12M in ward no. 2 at Katangi. Proposed land parcel belongs to Nagar Parishad Katangi and is without any settlement/ squatter /cultivation or other developments. Therefore, no involuntary resettlement impact is anticipated. The CMO Katangi issued a land status certificate (refer to Appendix 15) and has written to District Collector for the transfer of proposed land, refer to Appendix 18.

35. Clear water sump at Majholi: There are four existing OHTs having 2 nos. 15 m staging and 2 nos. 18 m staging height, all are in good condition and considered under WSS. A huge head of pumps will be required to feed these tanks directly from the WTP. An intermediate pumping station at junction point (elevation 393.39m) and a sump well with of capacity 35KL is proposed, considering 30 minutes detention time. The land is in the possession of revenue department. The CMO Majholi issued a land status certificate (refer Appendix 15) and has written a letter to District Collector Jabalpur for the transfer of proposed land (refer Appendix 19).

36. OHTs at Panagar: There are three proposed OHTs having (1) Capacity 700 KL (2) Capacity 600 KL and (3) Capacity 200 KL. All the proposed sites are under possession of Nagar Parishad-Panagar. The CMO Panagar issued a land status certificate (refer to Appendix 15) and has written a letter to District Collector-Jabalpur for the transfer of proposed land (refer Appendix 20).

OHTs and Clear Water Sump well at Sihora. There are four proposed OHTs having (1) capacity 920 KL staging height 18 meter, (2) capacity 900 KL staging 15 meter, (3) capacity 630 KL staging

22

height 16 meter, (4) capacity 620 KL staging height 10 meter, at ground levels 397.542m, 386.398 m, 401.502 m and 415.412 m. A huge head of pumps will be required to feed these tanks directly from the intermediate pumping station has been proposed for boosting the water at required head. An Intermediate pumping station at junction point (elevation 378.88m) with a sump well of capacity 245 KL is proposed considering 30 minutes detention time. One semi-pucca (tin shed) structure is reported near sump well (245 KL) but no impact is anticipated on this structure. All the proposed sites are under possession of Nagar Parishad Sihora. The CMO Sihora issued a land status certificate (refer to Appendix 15) and has written a letter to District Collector, Jabalpur for the transfer of proposed land (refer Appendix 21).

37. Overhead tanks, Clear Water Sump well and Break Pressure Tank (BPT) at Tendukheda. There are two proposed OHTs, (1) capacity 325 KL staging height 13 meter and (2) capacity 300 KL staging height 9 meter. Both the OHT sites are government land, and are vacant and unused. Although one semi pucca (tin shed) structure is reported at site, it is owned by Nagar Parishad and is being used for parking of Nagar Parishad vehicles. No impact is anticipated on this structure. For storing clear water by direct pumping from WTP sump to overhead tanks an intermediate pumping station with a sump well of capacity 52 KL is proposed for 30 minutes detention time at junction point near Basan village (elevation 541.50 m) where a break pressure tank (BPT) on hill (capacity 52 KL) is also proposed. Proposed site for BPT is government land. A few trees are noted at the site, but no tree will be cut. Proposed land parcel belongs to Nagar Parishad Tendukheda and is without any settlement/ squatter /cultivation or other developments. Therefore, no involuntary resettlement impact is anticipated. All the proposed sites are under possession of Nagar Parishad Tendukheda. The CMO Tendukheda issued a land status certificate (refer Appendix 15) and has written a letter to Tehsildar Tendukheda for the transfer of proposed land in the name of ULB, refer Appendix 22.

38. Clear water feeder main from WTP to different overhead tanks and sump for Katangi, Patan, Majholi, Sihora, Panagar and Tendukheda Nagar Parishad and its total length is 158494 meters (for details, refer to Table 2). Pipelines will pass through existing road rights of way (RoW) which are government roads. NOC has been applied to Rani Avanti Bai Lodhi Sagar Canal Prakosht, Forest Department, railway, MP Rural Road Development Authority, MPRDC, PWD (for road and bridges), PWD (Division 1), PWD (Division 2) and NHAI to lay the feeder main (refer Appendix 8, 9, 11 and 13). NOC has been obtained from NHAI and Rani Avanti Bai Lodhi Sagar Canal Prakosht, refer to Appendix 10 and 12.

39. The distribution network design of Katangi, Patan, Majholi, Sihora, Panagar, Bhedaghat and Tendukheda Nagar Parishad is done separately and divided into different number of zones. The total length of the proposed network is around 328450 meters of diameter 110 mm to 315 mm HDPE PN 10 pipe (refer to Table 2). Temporary impacts are anticipated in during construction. The Contractor, as per environmental management plan (EMP) will ensure these impacts are mitigated.

40. Temporary impacts to pedestrians, traffic, access to shops, access to residences and possible income loss of businesses due to excavation, laying of transmission mains and distribution network pipelines are possible during construction. The Contractor will provide access to properties through provision of pedestrian planks, provision of adequate signage, and careful traffic management.

41. Mobile hawkers are assisted to move to places nearby, to ensure their earnings are not affected. The weekly market day is avoided for construction. Only mobile vendors are shifted to a nearby location during the period of construction and assistance to shift will be provided by the

23

contactor. No income loss is anticipated.

42. In case temporary shifting of vendors with temporary structures is necessary, such shifting will be undertaken on a weekly holiday, to avoid income loss on the day(s) of shifting. The vendors are assisted to shift and will be able to continue plying their trade during the construction period at the alternative location. Potential disruption of water supply to existing consumers is possible during construction, and are being mitigated through supply by water tankers.

43. House Service connections: Household survey is being conducted at each subproject town. Provision of house service connections will involve tapping from a distribution main/ sub- main including one tapping saddles, elbows, service pipe from tapping point to the chamber near property boundary or inside the property boundary. The work involves excavation and road restoration. Each connection will include a domestic water meter. Installation of automatic meter reading compatible water meters for each house service water connection is envisaged.

Table 4: Proposed Subproject Components and their involuntary resettlement impact Involuntary Land Resettlement Sl. No. Components Capacity Unit (No.) Length ownership Impact Water Supply 1 Common R.C.C. 1 Water The intake well Intake well on intake well Resource is proposed on Narmada of 10 m Department Narmada river. River diameter (WRD) Land belongs and 35 m to WRD. The height site is without any settlement/ squatter/non- title users /cultivation or other use. Therefore, no involuntary resettlement impact is anticipated. NOC has been obtained, refer to Appendix 7. 2 Common 31.0 MLD 1 Government WTP of Water land/ capacity 31.00 Treatment Revenue MLD is Plant (WTP) Department proposed at Lamethaghat. The site belongs to Revenue Department and is without any settlement/ squatter/non- title users /cultivation or other use.

24

Involuntary Land Resettlement Sl. No. Components Capacity Unit (No.) Length ownership Impact Therefore, no involuntary resettlement impact anticipated. For Khasra details and map, refer Appendix 14, 16 and 17 3 Common 1147 KL 1 Government The clear Clear Water land/ water sump at sump (within Revenue head works is the premises Department proposed of WTP) within the premises of WTP. Land belongs to Revenue Department. Therefore, no involuntary resettlement impact is anticipated. For Khasra details and map, refer Appendix 14, 16 and 17 4 Overhead (i) OHT (200 12 Nagar Proposed land Tanks KL) and (ii) Parishad is government (OHTs) and OHT (220 Land/ land belonging Sump Well KL) at Revenue to Revenue Bhedaghat Department Department and Nagar (i) OHT (120 Parishad. Land KL) at is reported Katangi vacant, unused and without (i) Sump any non-titled Well (35 KL) users at sites. at Majholi Therefore, no involuntary (i) OHT (700 resettlement KL), (ii) OHT impact (600 KL) anticipated. and (iii) OHT Refer Appendix (200 KL) at 14 and Panagar Appendix 16 to 22 for Khasra (i) OHT (900 details and KL), (ii) OHT map. (920 KL), (iii) OHT

25

Involuntary Land Resettlement Sl. No. Components Capacity Unit (No.) Length ownership Impact (630 KL) Proposed site and (iv) of sump well OHT (620 (245 KL) is KL) at reported Sihora and vacant but one Sump well semi-pucca (tin (245 KL) at shed) structure Sihora is reported near sump well (i) OHT (300 (245 KL) at KL), (ii) OHT Sihora. No (325 KL) at impact is Tendukheda anticipated on and Sump this structure well (52 KL) as sufficient & BPT (52 vacant land is KL) at available at Tendukheda site. Proposed site of OHT (325 KL) at town Tendukheda is reported vacant but one semi pucca (Tin shed) structure is reported at site, owns by Nagar Parishad and is being used for parking of Nagar Parishad vehicles. No impact is anticipated on this structure as sufficient land is available free, vacant and unused. Proposed site of BPT for town Tendukheda is vacant. Few trees are reported over there but no tree will need to be cut.

26

Involuntary Land Resettlement Sl. No. Components Capacity Unit (No.) Length ownership Impact 5 Guard cum Nagar The facility will operator Parishad be house at Land / accommodated Intake well Government within the and WTP land (WRD premised of with and revenue intake well and boundary department WTP. wall and gate lands) cultivation or others, Therefore, no involuntary resettlement impact anticipated. 6 Clear Water 158494m Government Clear Water Transmission land (refer to Transmission Line para 39 for Line from WTP (158494m) more details) to each subproject town along existing road right of way. Transmission main passes through unused /vacant/barren public lands /Road RoW belong to different departments like NHAI, MPRDC ltd., PWD, canal department etc., refer to Appendix 8, 9, 10, 11, 12 and 13. No involuntary resettlement impact is anticipated.

7 Chemical 1 Government Will be Storage and land/Revenue accommodated dosing pump Department within the WTP house premises. 8 Distribution 328450 Road RoW Pipelines pass Pipeline m m under through HDPE pipe - jurisdiction of existing road 328450 m respective RoWs

27

Involuntary Land Resettlement Sl. No. Components Capacity Unit (No.) Length ownership Impact Nagar (government parishad roads). roads of Temporary project towns impacts on (public land) traffic/access to shops and residences anticipated in some places. Contractor to provide signages indicating available alternate access route to minimize traffic disruptions. Contractor will have to ensure access to shops and residences as per EMP provisions. 9 Household Total - During connections 28284 construction with domestic approx. period, access metres House to residences connection and shops Note: Status proposed likely to be of the for all temporarily household towns affected. survey is Contractor will Bhedaghat have to ensure (876), Majholi access as per (2800), EMP Sihora provisions. (9147), Tendukheda (2602), Panagar, Katangi & Patan (going on)

44. Mitigation: The sites or locations for the subproject components have been selected carefully to avoid and minimize involuntary resettlement impacts. The following mitigation measures are proposed to avoid and/or reduce the impacts during linear pipe works:

28

(i) Provide prior advanced notice (minimum one week) to community along the construction stretch. Distribute information on project and grievance redress mechanism, (ii) Maintain access to avoid disturbance to residents and businesses by providing planks and leaving spaces for businesses and residents to maintain access, (iii) Manage traffic flows as per traffic management plan prepared by the contractor in coordination with local authorities and communities, (iv) Limit the amount of time of open trenches, and complete works quickly where business activities are located, (v) Avoid full street closure to extent possible, (vi) Contractors shall provide employment opportunity to the local residents and particularly woman where possible, and (vii) Contractors shall assist vendors and hawkers in shifting to alternative locations, if required.

45. This subproject does not have any involuntary resettlement impact as there are no physical or economic displacement. The subproject does not have adverse land acquisition impacts as the subproject components are proposed on public lands belonging to government. Identified sites does not belong to tribal community and no adverse IP impacts are envisaged. Transmission and distribution pipeline carry raw and clear water traverse only through right of way (ROW) of the government roads. Keeping in view, no involuntary resettlement impacts are likely to be envisaged; an involuntary resettlement screening checklist is prepared and attached in Appendix 6. Accordingly, the subproject is classified under ‘Category C’ for involuntary resettlement under ADB’s SPS-2009.

VI. BUDGET

46. A provisional budget for consultation, communication, grievance redress, awareness generation, and mitigation measures such as tanker supply to existing consumers if supply is affected during construction is included in the DDR for Katangi, Patan, Majholi, Tendukheda, Sihora, Bedaghat, Panagar and overall subproject costs.

Table 5: Budget

S.no Description Target group/area Estimated cost Source of fund 1 Consultation Stakeholder and INR 150,000; Included in communities subproject cost 2 Communication, awareness subproject area INR 1500,000 Included in generation and grievance (grievance cell subproject cost redress zone wise) 3 Tanker supply for areas where areas where supply INR 650,000 Included in existing water supply disrupted is disrupted subproject cost during construction 4 15% contingencies INR 345,000 Included in subproject cost Total INR 26,45,000

29

VII. CONCLUSIONS AND RECOMMENDATIONS

A. Summary and Conclusions

47. No negative involuntary resettlement impacts are assessed at identified sites for sub- project components, as adequate vacant land is available for the proposed facilities, within the compounds of government lands.

48. For the subproject towns, source of water is Narmada River. Office of the CMOs has applied to WRD for NOC and obtained. Common Intake well is being constructed at Lamhetaghat on Narmada River and NOC has been obtained from WRD. The proposed site for common WTP is at Lamhetaghat in Bhedaghat. All identified land/sites for proposed components is owned by revenue department. For linear components (pipe laying) or those proposed along government road ROWs, temporary disruption to road users, pedestrians and community members are avoided in the congested zones of Katangi, Bedaghat, Majholi, Panagar, Patan, Sihora and Tendukheda with proper traffic management with the help of local police and officials. Safety measures and simple mitigation measures are taken during construction by the DBO contractor such as provision of planks for pedestrian access to shops, avoidance of weekly haat days for construction, undertaking construction on weekly market holidays, and proper traffic management and information sharing with the public is being adopted. The subproject is classified as ‘Category C’ for Involuntary Resettlement impact as per ADB’s Safeguard Policy Statement (SPS), 2009. A budgetary provision is made for costs likely to be incurred for impact mitigation.

B. Next Steps

49. The DDR needs to be updated with the following information:

➢ Transfer of land in the name of respective Nagar Parishad/ULBs of proposed components under subproject (in progress). ➢ NOC is required to lay the transmission / distribution line (in progress). ➢ In addition to the above, in order to improve the quality of consultations, local community organizers will be appointed for Project under package; record of consultations held with local communities and other stakeholders to be included in updated/final DDR. ➢ Any unanticipated impacts during construction will be assessed and compensation paid in accordance with the Resettlement Framework.

30

Figure 1: Location of each Town under Package 5B

31

Figure 2: Key Plan (Package 5B feeder main)

32

Figure 3: Location of proposed subproject components on Google Earth map Feeder main from WTP to OHT

33

Location of proposed subproject components on Google map Intake Well Site

Location of Intake Well and WTP

34

Location of Proposed Subproject Components in Bhedaghat on Google Earth Map

Location of Proposed Subproject Components in Katangi on Google Earth Map

35

Location of Proposed Subproject Components in Majholi on Google Earth Map

Location of Proposed Subproject Components in Panagar on Google Earth Map

36

Location of Proposed Subproject Components in Sihora on Google Earth Map

Location of Proposed Subproject Components in Tendukheda on Google Earth Map

37

Figure 4: Site Photographs

Site Photographs

Intake Well Location Lametaghat WTP Location Lametaghat

38

Site Photographs

Sump Well Location Lametaghat OHT 1 Location Bhedaghat

OHT 1 Tendukheda

OHT 2 Location Bhedaghat

39

Site Photographs

OHT 2 Tendukheda OHT 1 Location Katangi

OHT 1 Location Panagar OHT 2 Location Panagar

40

Site Photographs

OHT3Panagar

Unloading of DI Pipe at Pipelaying Site. Pipelaying Site Clear Water Main at Katangi road

41

Site Photographs

Toolbox Talk Location WTP Toolbox Talk Location WTP

42

Labour Camp Location Bhedaghat

43

Appendix 1: Details of Land Ownership for each Proposed Water Works Component

Ownership of the Land Details Component Location Land Proposed (Khasra Number) Status of NoC Site Photographs Intake well (10m on Narmada Water Resource NoC obtained from dia and 35m river (at Department (Govt Of WRD, refer to height) Lamhetaghat MP) Appendix 7 )

WTP (31 MLD) Near Revenue Department Khasra Number NoC obtained, only and Sump well Paramhans (Govt Of MP) 171,173,175 transfer of the land (1147 KL) Ashram at in the name of ULB Lamhetaghat is to be done, refer to Appendix 16

OHT (200KL) for Dindayal Park, Government and Khasra Number 72 Under possession of town Bhedaghat Nera Nagar under possession of ULB Bhedaghat Parishad, ULB-Katangi Ward no. 4 Bhedaghat

44

Ownership of the Land Details Component Location Land Proposed (Khasra Number) Status of NoC Site Photographs OHT (220KL) for Near Old Government and Khasra Number Under possession of town Bhedaghat OHT, Ward under possession of 153/2 ULB Bhedaghat no. 13 ULB-Katangi Bhedaghat

OHT (120KL) for Near Primary Government and Khasra Number Government land town Katangi School, Ward under possession of 136/3 &137/3, Gram and under no. 2 Katangi ULB-Katangi Kudan, Katangi possession of ULB Katangi, refer to Appendix 15. NoC obtained, only transfer of the land in the name of ULB Katangi is to be done, refer to Appendix 18 Clear water sump Near Kanya Government Khasra Number Government land. well (35KL) Mahvidyalaya, 401/21 NoC obtained, only Majholi transfer of the land in the name of ULB Majholi is to be done, refer to Appendix 19

45

Ownership of the Land Details Component Location Land Proposed (Khasra Number) Status of NoC Site Photographs OHT (700KL) for Near Government and Khasra Number Under possession of town Panagar Samudayik under possession of 344/1, 344/2 ULB Panagar, so, Bhavan, Ward ULB-Panagr transfer of land in no. 11 the name of ULB Panagar Panagar is to be done, refer to Appendix 20

OHT (600KL) for Near Sarkari Same as above Khasra Number Same as above town Panagar Nursery, Ward 1112 no. 4 Panagar

OHT (200KL) for Near Stadium Same as above Khasra Number Same as above town Panagar Ground, Ward 1421/2 no. 4 Panagar

46

Ownership of the Land Details Component Location Land Proposed (Khasra Number) Status of NoC Site Photographs OHT (900KL) for Near PHE Government Khasara Number ULB has written a town Sihora workshop, 1488/2 letter to District Ward no. 11 Collector to transfer Sihora the land in the name of ULB-Sihora. NoC obtained, refer to Appendix 15

OHT (920KL) for Near Shahid Same as above Khasara Number Same as above town Sihora Baba ki Majar, 230/1 Ward no. 4 Sihora

OHT (620) for Near Danu Same as above Khasara Number Same as above town Sihora Baba ki 197/2 Pahari, Ward no. 13 Sihora

47

Ownership of the Land Details Component Location Land Proposed (Khasra Number) Status of NoC Site Photographs OHT (630KL) for Near Same as above Khasra Number Same as above town Sihora Hanuman 275/1 Gadi, Ward no. 17 Sihora

Sump Well GSR Near Same as above Khasra Number Same as above (245KL) for town government 117/2 Sihora school, Ward no. 9 Sihora

OHT (300KL) for Near Government Khasra Number ULB has written a town Tendukheda government 685/30 letter to Tehsildar- school, Ward Tendukheda to no. 9 transfer the land in Tendukheda the name of ULB- Tendukheda, refer to Appendix 22 (Part A). NoC obtained, refer to Appendix 15

48

Ownership of the Land Details Component Location Land Proposed (Khasra Number) Status of NoC Site Photographs OHT (325KL) for Near Nagar Government and Khasra Number Same as above town Tendukheda Parishad under possession of 579/1 office, Ward ULB-Tendukheda no. 11 Tendukheda

Sump well (52KL) Near State Government Khasra Number 80 ULB has written a for town highways and letter to Tehsildar Tendukheda Gramin road, Tendukheda to Tendukheda transfer the land in the name of ULB Tendukheda, refer to Appendix 22 (Part B). NoC obtained, refer to Appendix 15

BPT (52KL) for Near Jain Government Khasra Number ULB has written a town Tendukheda Dharamshal, 23/377 letter to Tehsildar Tendukheda Tendukheda to transfer the land in the name of ULB Tendukheda, refer to Appendix 22 (Part A). NoC obtained, refer to Appendix 15.

49

Appendix 2: Summary of Consultation with Stakeholders Date Location No. of Participants Topics Discussed Issues Participants During Planning Stage

2nd Nagar Parishad Total=130 Elected Present drinking Nagar Parishad is operating the April (Katangi,Bhedaghat,Majholi,Panagar,Sihora & M=94 representatives, water supply source water supply system for the town, 2016 Tendukheda)* F=36 Chairperson of ULB, and its condition but capacity to be further built. Chief Municipal Need of improvement The Chairman of the ULB Officer, Revenue of the present expressed need for the project and department, elder situation willingness to take it up; person Briefing on project The Nagar Parishads do not have objectives probable capacity or resources to be party to implementation sharing the loan repayment. procedures The prime concern and Potential positive and apprehension of the ULB Chairman negative impacts due regarding the project was whether to project it will be a financial burden on the implementation Nagar Parishad. Land use and area to Operation and maintenance of the be covered under the facilities developed under the project project and community participation; The official from revenue department gave consent of speedy allotment for required land for project. 3rd selected Ward in all towns have scarcity M=90 Community persons Briefing on project None of the people knew about the April F=50 objectives probable proposed project. On learning 2016 T=40 implementation about the project, they expressed procedures that they were happy that the entire Potential positive and community would be benefited negative impacts due from the upgraded water supply. to project Slum dwellers showed willingness implementation to take water connections but Experiences sharing demanded relaxation in user on - livelihood charges. activities, People were briefed about the Resettlement and complaint redress mechanism. Rehabilitation, women empowerment, tribal development, health, education,

50

Date Location No. of Participants Topics Discussed Issues Participants convergence with existing government social security schemes etc. Grievance Redress procedures 3rd Selected ward in all towns were supply of water through Total= 50 Slum community Knowledge of project Women had heard about the April tankers/ have scarcity F=18 ,M=32 Present water supply proposed project and welcomed it 2016 situation: only half an as women are facing many hours of supply problem in fetching water for alternate day hours.. Drinking water user Some participants did not have charge water connections. The women were happy to learn about the proposed project. Possibility of exempting the poor and vulnerable from user charge payment. 4th Selected Slum areas in all towns Total - 75 Community members Status of existing The area has insufficient and April (Female 40, (Low income group; drinking water supply inadequate drinking water supply. 2016 Male - 35) the men work as daily system; Water from two tube wells is laborers and the Need for presently supplied to the women are improvements to area/community. The area faces housewives) present system; severe water crisis during the Relevant information summer season when the ground of the upcoming water level drops. project and benefits The community welcomed the of the project. project and expressed need for it. Potential positive and However, they were apprehensive negative impacts due that their economic condition would to project prevent them from paying water implementation user charges. Ensuring no income Possibility of exempting the poor loss and vulnerable from user charge payment. 4th Selected Market areas in all towns Total= 90 Street vendors and Temporarily shifting of As excavation may not be possible April M=63,F=27 shopkeepers weekly vegetable at night as labour may not get 2016 market during agree to work in night shift, excavation. construction will be undertaken Shifting of Street with care to avoid the weekly haat vendors. day, such that no income loss takes place due the civil work.

51

Date Location No. of Participants Topics Discussed Issues Participants Shifting or adjusting Mobile vendors will be given extended potion of sufficient notice and assistance to shopkeepers. shift to nearby locations, so that they do not face income loss. Mobile street vendors agreed to the proposal. Some small restaurant/food stall owners expressed a concern that dust during excavation may fall on / spoil eatables. Mitigation measures such as spraying of water on the excavated soil particularly around such restaurants/food stalls to ensure there is no dust flying around and other appropriate measures as per IEE shall be taken during construction. During Implementation Stage

16 July Ward No. 06, Majholi Total=13 Local Community Briefing on project None of the people knew about the 2018 M=04, people objectives probable proposed project. On learning F=04 implementation about the project, they expressed procedures that they were happy that the entire Potential positive and community would be benefited negative impacts due from the upgraded water supply. to project Slum dwellers showed willingness implementation to take water connections but Experiences sharing demanded relaxation in user on - livelihood charges. activities, People were briefed about the Resettlement and complaint redress mechanism. Rehabilitation, women empowerment, tribal development, health, education, convergence with existing government social security schemes

52

Date Location No. of Participants Topics Discussed Issues Participants 03 ULB office, Panagar Total=08 Elected Present drinking Nagar Parishad is operating the May M=06, Representatives, ULB water supply source water supply system for the town, 2018 F=02 Officials, CDO/PRO, and its condition but capacity to be further built. Engineer- TCE & IHP Need of improvement The Chairman of the ULB of the present expressed need for the project and situation willingness to take it up; Briefing on project The Nagar Parishads do not have objectives probable capacity or resources to be party to implementation sharing the loan repayment. procedures The prime concern and Potential positive and apprehension of the ULB Chairman negative impacts due regarding the project was whether to project it will be a financial burden on the implementation Nagar Parishad. Land use and area to Operation and maintenance of the be covered under the facilities developed under the project project and community Objective of Door To participation; Door Survey etc. The official from revenue Grievance Redress department gave consent of procedures speedy allotment for required land for project. 06 July Patan Total=08 Local Community Knowledge of project Women had heard about the 2018 M=00, people Present water supply proposed project and welcomed it F=08 situation: only half an as women are facing many hours of supply problem in fetching water for alternate day hours.. Drinking water user Some participants did not have charge water connections. The women were happy to learn about the proposed project. Possibility of exempting the poor and vulnerable from user charge payment.

53

Date Location No. of Participants Topics Discussed Issues Participants 06 July Katangi Total=19 Local Community Existing water supply Local residents complained about 2018 M=07, people ward no. 5 status the poor water supply in the town. F=12 Component of People promise support the proposed water upcoming water supply project as it supply component will be beneficial to the community Social impact of in all aspects. project during Some people also show their construction work grievance about the delay in Social and community project. impact during People are ready to take new water operation work connection in place of old one Impact on health by People were agreeing to pay proposed project proposed water tariff. Willing to take new All people requested to select good Water connection contractor to speed up the construction process.

06 Dec Majholi Total=16 Local Community Knowledge of project Women had heard about the 2018 M=10, people ward no. 13 Present water supply proposed project and welcomed it F=06 situation: only half an as women are facing many hours of supply problem in fetching water for alternate day hours.. Drinking water user Some participants did not have charge water connections. The women were happy to learn about the proposed project. Possibility of exempting the poor and vulnerable from user charge payment.

54

Date Location No. of Participants Topics Discussed Issues Participants 08 Dec Panagar Total=17 Local Community Existing water supply The area has insufficient and 2018 M=3, people ward no. 3 status inadequate drinking water supply. F=14 Proposed subproject Water from two tube wells is components presently supplied to the Impact of subproject area/community. The area faces on community severe water crisis during the particularly ST summer season when the ground population water level drops. Impact during The community welcomed the construction work project and expressed need for it. Impact on health by However, they were apprehensive proposed subproject that their economic condition would Willingness to take prevent them from paying water new water connection user charges. they expressed that they were happy that the entire community would be benefited from the regular water supply. Slum dwellers showed willingness to take water connections but demanded relaxation in user charges. People were briefed about the complaint redress mechanism. 08 Dec Sihora Total=14 Local Community Knowledge of project Participants had heard about the 2018 M=04, people ward no. 9 Present water supply proposed project and welcomed it F=10 situation: only half an as women are facing many hours of supply problem in fetching water for hours alternate day Some of participants did not know Drinking water user about project charge Some participants did not have water connections. The women were happy to learn about the proposed project. Possibility of exempting the poor and vulnerable from user charge payment.

55

Date Location No. of Participants Topics Discussed Issues Participants 10 Dec Tendukheda Total=10 Local Community Knowledge of project Most of the women didnot hear 2018 M=00, people ward no. 9 Present water supply about the proposed project but all F=10 alternate day and are welcomed it as women are poor and ieregular facing many problem in fetching Drinking water user water for hours.. charge Some participants did not have water connections. The women were happy to learn about the proposed project. Possibility of exempting the poor and vulnerable from user charge payment.

Note: Boatmen and washer men were not observed near the proposed intake well location on Narmada river, hence need for a separate consultation with them was not perceived.

56

Appendix 3: Photographs of Stakeholder Consultation and List of Participants during Planning Phase

Katangi

Panagar

Community consultation

57

Majholi

Patan

58

Sihora

Tendukheda

59

Bhedaghat

60

List of Participants

English Translation S.N. Name of Participants 1 Banti rajpoot 2 Shrikant Thakur 3 Deepak varma 4 Jetendra jhadiya 5 Baddu barman 6 Deepak prashad pradhan 7 Lagus Pradhan 8 Vijay Pradhan

61

Appendix 4: Photographs of Stakeholder Consultation and List of Participants during Implementation Phase

Stakeholder Consultation at Majholi with Local Community in Ward No. – 06

English Translation: S.N. Name of Participant S.N. Name of Participant 1 Smt.Swati shahu 8 Smt.Yashodhra Misra 2 Ku.kanchan shahu 9 Ku. Pooja misra 3 Ku.Nisaha shahu 10 Rajendra singh 4 Ku. Sraddha shahu 11 Kuldeep singh chohan 5 Smt. Deepa chodhri 12 Pankaj dixit 6 Smt.Manisha chodhri 13 C.P. panday 7 Smt. Sheela chodhri

62

Photographs of Stakeholder Consultation and List of Participants during Implementation Phase at Panagar with ULB officials and Elected Representatives of ULB during Implementation Phase

English Translation Name of Designation Name of Participant Designation Participant Dilip patel Ward Rohit viskarma Engineer councilor (TCE) Ramkumar Ward Nidhi tiwari SSSVO councilor Surendra varma Engineer(IHP) Aparajeta CDO/RRO Sourabh singh Engineer 8

63

Photographs of Stakeholder Consultation and List of Participants during Implementation Phase at Patan with Local Community

English Translation S. No. Name of Participant S. No. Name of Participant 1 Koshilya 5 Manisha 2 Rani 6 Rekha 3 Geeta 7 Gori 4 Rajkumari 8 Pooja

64

Photographs of Stakeholder Consultation and List of Participants during Implementation Phase at Katangi with Local Community

English Translation S. No. Name of Participant S. No. Name of Participant 1 Sarju 11 Laxmi 2 Mahendra kumar 12 Mamta 3 Rukhsar 13 Ramakol 4 Sahnaj 14 Rajni 5 Sabana 15 Balveer 6 Gudda 16 Balvan 7 Sabina 17 Sayra 8 Rukhsana 18 Jamuna bai 9 Sahjadi 19 Ajeet 10 Pooja

65

Photographs of Stakeholder Consultation and List of Participants during Implementation Phase at Majholi with Local Community (Ward No. 13)

English Translation S. No. Name of Participant S. No. Name of Participant 1 Babu Ram 9 Mamta bai 2 Laxmi bai 10 Mohini yadav 3 Gudda barman 11 Suresh singh 4 Supal Rani 12 Asha raikwar 5 Santram 13 Ravindra kuswah 6 Ram 14 Umakant kuswah 7 Radha barman 15 Shivam seni 8 Laxmi Bai 16 Laxni bai raikwar

66

Photographs of Stakeholder Consultation and List of Participants during Implementation Phase at Panagar with Local Community (Ward No. 3)

English Translation S. No. Name of Participant S. No. Name of Participant 1 Bishram shrivastava 10 Sunita 2 Bhatula koriy 11 Mute nai 3 Rani bai 12 Sunit kori 4 Keshar bai 13 Kiran kori 5 Abhilasha bai 14 Raju 6 Sudha dubey 15 Krishna 7 Parbati bai 16 Rani 8 Munni bai 17 Kamal 9 Shiya bai

67

Photographs of Stakeholder Consultation and List of Participants during Implementation Phase at Patan with Local Community (Ward No. 2)

English Translation S. No. Name of Participant S. No. Name of Participant 1 Sekh jamin 6 Geeta 2 Kanija 7 Sagar mati 3 Bablu 8 Dhani bai 4 Munni 9 Doura 5 Anita 10 Preeti

68

Photographs of Stakeholder Consultation and List of Participants during Implementation Phase at Sihora with Local Community (Ward No. 9)

English Translation Name of Participant Mobile No. Name of Participant Mobile No. Shila bai Sona bai Kosilya bai viskarma Santi bai Kappi bai Badri prashad viskarma Ramkali bai namdev Rajendra patel 9165933640 Gori bai Kamlesh viskarma 8817366157 Arti bai 9669905051 Kamlesh kumar namdev 7747993631 Gori bai viskarma Radha bai kori

69

Photographs of Stakeholder Consultation and List of Participants during Implementation Phase at Tendukheda with Local Community (Ward No. 5)

English Translation S. No. Name of Participant S. No. Name of Participant 1 Mamta bai 6 Bati bai 2 Aneeta 7 Sangeeta Bai 3 Rambai 8 Rohan bai 4 Parvati bai 9 Deksha lodhi 5 Bhavani bai 10 Shivani Thakur

70

Photographs of Stakeholder Consultation and List of Participants during Implementation Phase Informal Consultation at Bhedaghat with CMO-Bhedaghat in April 2018

Informal Consultation at Katangi with Ward Parshads in May 2018

71

Appendix 5: Photographs of Informal Consultation

Informal Consultation at Sihora with CMO in May 2018

72

Photographs of Informal Consultation Consultation at Sihora with MLA during inauguration along with Chairperson- ULB & Local people in Oct 2018

73

Photographs of Informal Consultations Informal Consultation at Tendukheda with Local community in June 2018

74

Photographs of Informal Consultation Consultation with Local Residents at Bhedaghat

75

Appendix 6: Involuntary Resettlement Screening Checklist

A. Introduction 1. Each project/subproject/component needs to be screen for any involuntary resettlement impacts and indigenous people impacts which will occur or already occurred. This screening determines the necessary action to be done by the project team.

B. Information on project/subproject/component: a. District/ Administrative Name:Jabalpur and Damoh b. Location (km): Katangi (38 Kilometers from Jabalpur), Bhedaghat (25 Kilometers from Jabalpur), Majholi (56 Kilometers from Jabalpur), Panagar (16 Kilometers from Jabalpur), Patan (33 Kilometers from Jabalpur), Sihora (42 Kilometers from Jabalpur), Tendukheda (56 Kilometers from Damoh) c. Civil work dates: Date of Award is 04th September 2017 d. Technical Description: Group Water Supply Scheme of seven towns namely Katangi, Bhedaghat, Majholi, Panagar, Patan & Sihora under District Jabalpur and Tendukheda under District Damoh. Pumping water from intake wells to WTP, laying of raw water rising main of length 339 m, clear water rising main of length 158494 m from WTP to the OHTs, Construction of two number of Overhead tank (OHT) of size 200 KL and 220 KL for Bhedaghat, Construction of one overhead tank (OHT) of size 120 KL for Katangi, Construction of three number of Overhead tank (OHT) of size 700 KL, 600 KL and 200 KL for Panagar, Construction of four number of Overhead tank (OHT) of size 900 KL, 920 KL, 630 KL and 620 KL for Sihora and Construction of two number of Overhead tank (OHT) of size 300 KL and 325 KL for Tendukheda and further distribution to end users by various distribution networks through gravitation with length 328450 m.

C. Screening Questions for Involuntary Resettlement Impact 2. Below is the initial screening for involuntary resettlement impacts and due diligence exercise. Both permanent and temporary impacts must be considered and reported in the screening process.

Involuntary Resettlement Impacts Yes No Not Remarks known

Will the project include any physical ✓ Construction of common Intake well and construction work? WTP, OHTs and laying of transmission line and distribution network proposed. Does the proposed activity include ✓ No. for the existing OHT which will be upgrading or rehabilitation of existing integrated into the proposed system, no physical facilities? rehabilitation work is proposed. Only Supervisory Controller and Data Acquisition (SCADA) will be installed on the existing OHT. Will there be permanent land acquisition? ✓ Only government revenue land sites selected for project facilities Will it require temporary land acquisition? ✓

76

Is the ownership status and current usage ✓ All identified sites belong to either WRD of the land known? or revenue department and it is vacant, free of any structures and encumbrances. Are there any non-titled people who live or ✓ Land is vacant and unused and free earn their livelihood at the site or within from any non-titled people. the corridor of impact (COI) / Right of Way (ROW)?

Will there be loss of housing? ✓

Will there be loss of agricultural plots? ✓

Will there be losses of crops, trees, and ✓ As transmission lines are to be laid with fixed assets (i.e. fences, pumps, etc.)? in the right of way of existing roads belong to PWD, MPRDC and NHAI etc. and distribution lines are proposed along roads within the town (within available road). And, no losses to crops, trees and fixed assets are envisaged. In case of any damage to property (of titleholders or non- titleholders) during construction, the Contractor directed to reconstruct

Will there be loss of businesses or ✓ During laying of distribution lines in enterprises? congested lanes temporary arrangements will be made, pipeline will be located in unused government lands alongside the existing roads (within RoW) and can be constructed without causing disturbance to houses and commercial establishments Will there be loss of incomes and ✓ livelihoods?

Will people lose access to facilities, ✓ Any disruption of public facilities or services, or natural resources? services will be taken care of during excavation. Grievance redress mechanism has already been established at town level to settle the grievances shortly. Will any social or economic activities be ✓ affected by land use-related changes?

Will people lose access to natural ✓ resources, or common property resources, or communal facilities and/or services?

77

If land use is changed will it have an ✓ adverse impact on social and economic activities?

Will access to land and resources own ✓ communally or by the state be restricted?

Are any of the affected persons (AP) from ✓ indigenous or ethnic minority groups?

D. Involuntary Resettlement Impact

3. After reviewing the answers above, EA/ Safeguard Team confirms that the proposed subsection/ section/ subproject/component (tick as appropriate): [ N ] Has involuntary resettlement impact, a resettlement plan (or corrective action plan) is required [ Y ] Has No involuntary resettlement impact, no resettlement plan is required.

Prepared By: DBO Contractor namely Indian Hume Verified by: Safeguard Cell at PMU-Bhopal under Pies Limited MPUSIP Signature: Signature: Name: Anup

Position: EHS Supervisor Name: Position:

Date: 17.12.2018 Date: 22.12.2018

78

Appendix 7: No Objection Certificate (NoC) from WRD For Katangi

English Translation: Letter from Chief Engineer, Bodhi to Chief Engineer, Benganga Kachhar on dated 16.10.2017 Subject; NOC Issued to abstract water 0.83 mcm from Narmada River for WSS Katangi

Under the chairmanship of Chief Engineer, Water Resources Department, on 23.09.2017, 18th meeting of the Water Allocation Committee was held and decision was taken to allow ULB Katangi to abstract water (0.63 MCM) from river Narmada from year 2018. Annual water allocation is provided at the following conditions.:-

79

1) Authorized officer of Nagar parishad Katangi will sign the contract with Executive Engineer, Water Resource Department, Division Jabalpur in the prescribed format 7 (a). 2) Nagar parishad Katangi for the quantity of allocated water, 0.63 mcm per year and pay the water tax as per order of government to Executive Engineer, Jabalpur. Payment of water tax will be effective from the date of contract. 3) Nagar parishad Katangi will prepare the necessary design of civil and mechanical works for the use of water on its own expenditure. It is necessary to get the approval from the concerned Chief Engineer, WRD 4) Permission is granted for water supply purpose only and if Nagar parishad -Katangi violates the contract than contract will be cancelled. 5) Nagar parishad Katangi will install automatic equipment to measure the quantity of water abstracted from Source at his own cost and prior approval is required from Executive Engineer-Jabalpur for installation and upkeeping 6) In case of non-availability of the water at Source during summer season, Department is not bound to release water from upstream. 7) WRD under Government of Madhya Pradesh will not bear any financial burden for drinking water scheme

80

No Objection Certificate (NoC) from WRD For Bhedaghat

English Translation:

Letter from Chief Engineer, Bodhi to Chief Engineer, Benganga Kachhar on dated 16.10.2017 Subject; NOC Issued to abstract water 0.32 mcm from Narmada River for WSS Bhedaghat

Under the chairmanship of Chief Engineer, Water Resources Department, on 23.09.2017, 18th meeting of the Water Allocation Committee was held and decision was taken to allow ULB Bhedaghat to abstract water (0.32 MCM) from river Narmada from year 2018. Annual water allocation is provided at the following conditions.:-

1) Authorized officer of Nagar parishad Bhedaghat will sign the contract with Executive Engineer, Water Resource Department, Bhedaghat in the prescribed format 7 (a).

81

2) Nagar parishad Bhedaghat for the quantity of allocated water, 0.32 mcm per year and pay the water tax as per order of government to Executive Engineer, Jabalpur. Payment of water tax will be effective from the date of contract. 3) Nagar parishad Bhedaghat will prepare the necessary design of civil and mechanical works for the use of water on its own expenditure. It is necessary to get the approval from the concerned Chief Engineer, WRD 4) Permission is granted for water supply purpose only and if Nagar parishad -Bhedaghat violates the contract than contract will be cancelled. 5) Nagar parishad Bhedaghat will install automatic equipment to measure the quantity of water abstracted from Source at his own cost and prior approval is required from Executive Engineer-Jabalpur for installation and upkeeping 6) In case of non-availability of the water at Source during summer season, Department is not bound to release water from upstream. 7) WRD under Government of Madhya Pradesh will not bear any financial burden for drinking water scheme

82

No Objection Certificate (NoC) from WRD For Majholi

English Translation:

Letter from Chief Engineer, Bodhi to Chief Engineer, Benganga Kachhar on dated 16.10.2017 Subject; NOC Issued to abstract water 0.489 mcm from Narmada River for WSS Majholi

Under the chairmanship of Chief Engineer, Water Resources Department, on 23.09.2017, 18th meeting of the Water Allocation Committee was held and decision was taken to allow ULB Majholi to abstract water (0.489 MCM) from river Narmada from year 2018. Annual water allocation is provided at the following conditions.:-

1) Authorized officer of Nagar parishad Majholi will sign the contract with Executive Engineer, Water Resource Department, Majholi in the prescribed format 7 (a).

83

2) Nagar parishad Majholi for the quantity of allocated water, 0.489 mcm per year and pay the water tax as per order of government to Executive Engineer, Jabalpur. Payment of water tax will be effective from the date of contract. 3) Nagar parishad, Majholi will prepare the necessary design of civil and mechanical works for the use of water on its own expenditure. It is necessary to get the approval from the concerned Chief Engineer, WRD 4) Permission is granted for water supply purpose only and if Nagar parishad - Majholi violates the contract than contract will be cancelled. 5) Nagar parishad Majholi will install automatic equipment to measure the quantity of water abstracted from Source at his own cost and prior approval is required from Executive Engineer-Jabalpur for installation and upkeeping 6) In case of non-availability of the water at Source during summer season, Department is not bound to release water from upstream. 7) WRD under Government of Madhya Pradesh will not bear any financial burden for drinking water scheme

84

No Objection Certificate (NoC) from WRD For Panagar

English Translation:

Letter from Chief Engineer, Bodhi to Chief Engineer, Benganga Kachhar on dated 16.10.2017 Subject; NOC Issued to abstract water 1.789 mcm from Narmada River for WSS Panagar

85

Under the chairmanship of Chief Engineer, Water Resources Department, on 23.09.2017, 18th meeting of the Water Allocation Committee was held and decision was taken to allow ULB Panagar to abstract water (1.789 MCM) from river Narmada from year 2018. Annual water allocation is provided at the following conditions.:-

1) Authorized officer of Nagar parishad Panagar will sign the contract with Executive Engineer, Water Resource Department, Panagar in the prescribed format 7 (a). 2) Nagar parishad Panagar for the quantity of allocated water, 1.789 mcm per year and pay the water tax as per order of government to Executive Engineer, Jabalpur. Payment of water tax will be effective from the date of contract. 3) Nagar parishad, Panagar will prepare the necessary design of civil and mechanical works for the use of water on its own expenditure. It is necessary to get the approval from the concerned Chief Engineer, WRD 4) Permission is granted for water supply purpose only and if Nagar parishad - Panagar violates the contract than contract will be cancelled. 5) Nagar parishad - Panagar will install automatic equipment to measure the quantity of water abstracted from Source at his own cost and prior approval is required from Executive Engineer-Jabalpur for installation and upkeeping 6) In case of non-availability of the water at Source during summer season, Department is not bound to release water from upstream. 7) WRD under Government of Madhya Pradesh will not bear any financial burden for drinking water scheme

86

No Objection Certificate (NoC) from WRD For Patan

English Translation:

Letter from Chief Engineer, Bodhi to Chief Engineer, Benganga Kachhar on dated 16.10.2017 Subject; NOC Issued to abstract water 0.49 mcm from Narmada River for WSS Patan

Under the chairmanship of Chief Engineer, Water Resources Department, on 23.09.2017, 18th meeting of the Water Allocation Committee was held and decision was taken to allow ULB Patan to abstract water (0.49 MCM) from river Narmada from year 2018. Annual water allocation is provided at the following conditions.:-

87

1) Authorized officer of Nagar parishad Patan will sign the contract with Executive Engineer, Water Resource Department, Patan in the prescribed format 7 (a). 2) Nagar parishad Patan for the quantity of allocated water, 0.49 mcm per year and pay the water tax as per order of government to Executive Engineer, Jabalpur. Payment of water tax will be effective from the date of contract. 3) Nagar parishad, Patan will prepare the necessary design of civil and mechanical works for the use of water on its own expenditure. It is necessary to get the approval from the concerned Chief Engineer, WRD 4) Permission is granted for water supply purpose only and if Nagar parishad - Patan violates the contract than contract will be cancelled. 5) Nagar parishad Patan will install automatic equipment to measure the quantity of water abstracted from Source at his own cost and prior approval is required from Executive Engineer-Jabalpur for installation and upkeeping 6) In case of non-availability of the water at Source during summer season, Department is not bound to release water from upstream. 7) WRD under Government of Madhya Pradesh will not bear any financial burden for drinking water scheme

88

No Objection Certificate (NoC) from WRD For Sihora

English Translation:

Letter from Chief Engineer, Bodhi to Chief Engineer, Benganga Kachhar on dated 16.10.2017 Subject; NOC Issued to abstract water 2.82 mcm from Narmada River for WSS Sihora

Under the chairmanship of Chief Engineer, Water Resources Department, on 23.09.2017, 18th meeting of the Water Allocation Committee was held and decision was taken to allow ULB Sihora to abstract water (2.89 MCM) from river Narmada from year 2018. Annual water allocation is provided at the following conditions.:-

89

1) Authorized officer of Nagar parishad Sihora will sign the contract with Executive Engineer, Water Resource Department, Sihora in the prescribed format 7 (a). 2) Nagar parishad Sihora for the quantity of allocated water 2.82 mcm per year and pay the water tax as per order of government to Executive Engineer, Jabalpur. Payment of water tax will be effective from the date of contract. 3) Nagar parishad, Sihora will prepare the necessary design of civil and mechanical works for the use of water on its own expenditure. It is necessary to get the approval from the concerned Chief Engineer, WRD 4) Permission is granted for water supply purpose only and if Nagar parishad Sihora violates the contract than contract will be cancelled. 5) Nagar parishad Sihora will install automatic equipment to measure the quantity of water abstracted from Source at his own cost and prior approval is required from Executive Engineer-Jabalpur for installation and upkeeping 6) In case of non-availability of the water at Source during summer season, Department is not bound to release water from upstream. 7) WRD under Government of Madhya Pradesh will not bear any financial burden for drinking water scheme

90

No Objection Certificate (NoC) from WRD For Tendukheda

English Translation:

Letter from Chief Engineer, Bodhi to Chief Engineer, Benganga Kachhar on dated 16.10.2017 Subject; NOC Issued to abstract water 0.50 mcm from Narmada River for WSS Tendukheda

Under the chairmanship of Chief Engineer, Water Resources Department, on 23.09.2017, 18th meeting of the Water Allocation Committee was held and decision was taken to allow ULB Tendukheda to abstract water (0.50 MCM) from river Narmada from year 2018. Annual water allocation is provided at the following conditions.:-

91

1) Authorized officer of Nagar parishad Tendukheda will sign the contract with Executive Engineer, Water Resource Department, Tendukheda in the prescribed format 7 (a). 2) Nagar parishad Tendukheda for the quantity of allocated water 0.50 mcm per year and pay the water tax as per order of government to Executive Engineer, Jabalpur. Payment of water tax will be effective from the date of contract. 3) Nagar parishad, Tendukheda will prepare the necessary design of civil and mechanical works for the use of water on its own expenditure. It is necessary to get the approval from the concerned Chief Engineer, WRD 4) Permission is granted for water supply purpose only and if Nagar parishad Tendukheda violates the contract than contract will be cancelled. 5) Nagar parishad Tendukheda will install automatic equipment to measure the quantity of water abstracted from Source at his own cost and prior approval is required from Executive Engineer-Jabalpur for installation and upkeeping 6) In case of non-availability of the water at Source during summer season, Department is not bound to release water from upstream. 7) WRD under Government of Madhya Pradesh will not bear any financial burden for drinking water scheme

92

Appendix 8: Letter to MPRDC Ltd. to obtain NoC for laying the Pipelines with the RoW of road.

English Translation: Date 20.02.2018 Letter from Project Manager MPUDC (PIU-Jabalpur) to Divisional Managar MPRDC on dated 20-02-2018

Subject:-Laying of the pipeline of water supply scheme for seven towns under package 5B within the right of way (RoW) of the MPRDC roads.

Subject mentioned above, MP Urban Administration and Environment Department, the works is being done by the MPUDC with financial assistance from ADB. The Contractor of the works is IHP Company Limited, Mumbai. The main components Water Treatment Plant of this scheme is under construction of the at Lamhetaghat (Bhedaghat). From there water is to be supplied through the pipeline to Bhedaghat. Patan, Katanji, Panagar , Tendukheda, Majholi and Sihora. All the subproject components are being constructed at government land Therefore, You are requested to issue no objection certificate for above said activities under project. If there will be any damage to property during laying of pipeline it will be repaired/resorted by the contractor. It will be paid to contactor according to BOQ. therefore, you are requested to direct your town engineer to allow us the laying of pipelines within RoW of the road under your jurisdiction It is mentioned that the operation and maintenance (O&M) work will be conducted by the construction agency for the next 10 years.

93

Letter to MPRDC Ltd. to obtain NoC for laying the Pipelines with the RoW of road.

English Translation: Date 20.03.2018 Letter from Project Manager MPUDC (PIU-Jabalpur) to Divisional Managar MPRDC on dated 20-03-2018

Subject:-Laying of the pipeline of water supply scheme for seven towns under package 5B within the right of way (RoW) of the MPRDC roads.

Subject mentioned above, MP Urban Administration and Environment Department, the works is being done by the MPUDC with financial assistance from ADB. The Contractor of the works is IHP Company Limited, Mumbai. The main components Water Treatment Plant of this scheme is under construction of the at Lamhetaghat (Bhedaghat). From there water is to be supplied through the pipeline to Bhedaghat. Patan, Katanji, Panagar , Tendukheda, Majholi and Sihora. All the subproject components are being constructed at government land Therefore, You are requested to issue no objection certificate for above said activities under project. If there will be any damage to property during laying of pipeline it will be repaired/resorted by the contractor. It will be paid to contactor according to BOQ. Laying of the pipeline is to be commenced within row of SH-15 from Patan sump well to Tendukheda which is under your jurisdiction. Therefore, you are requested to direct your town engineer to allow us the laying of pipelines within RoW of the road under your jurisdiction (Patan Tendukheda Rehli road)

It is mentioned that the operation and maintenance (O&M) work will be conducted by the construction agency for the next 10 years.

94

Letter Written to MPRRD to obtain NoC for laying the Pipelines with the RoW of road.

95

Appendix 9: Letter to MP Rural Road Development Authority to obtain NoC for laying the Pipelines with the RoW.

English Translation: Date 06.09.2018 Letter from Project Manager MPUDC (PIU-Jabalpur) to General Manager MP Rural Road Development Authority on dated 06.09.2018

Subject:-Laying of the pipeline of water supply scheme for seven towns under package 5B within the right of way (RoW) of the MPRRDA roads.

Subject mentioned above, MP Urban Administration and Environment Department, the works is being done by the MPUDC with financial assistance from ADB. The Contractor of the works is IHP Company Limited, Mumbai. The main components Water Treatment Plant of this scheme is under construction of the at Lamhetaghat (Bhedaghat). From there water is to be supplied through the pipeline to Bhedaghat. Patan, Katanji, Panagar , Tendukheda, Majholi and Sihora.

All the subproject components are being constructed at government land Therefore, You are requested to issue no objection certificate for above said activities under project. If there will be any damage to property during laying of pipeline it will be repaired/resorted by the contractor. It will be paid to contactor according to BOQ. Laying of the pipeline is to be commenced, therefore, you are requested to direct your town engineer to allow us the laying of pipelines within RoW of the road under your jurisdiction.

It is mentioned that the operation and maintenance (O&M) work will be conducted by the construction agency for the next 10 years.

96

Appendix 10: No Objection Certificate (NoC) obtained from NHAI To lay the Pipelines with the RoW. Page 1 of 4

97

Page 2 of 4

98

Page 3 of 4

99

Page 4 of 4

100

Appendix 11: Letter Written to PWD (Road & Bridge) To obtain NoC for laying the Pipelines with the RoW.

English Translation: Date 20.02.2018 Letter from Project Manager MPUDC (PIU-Jabalpur) to Executive Engineer, PWD (Road and Bridges) on dated 20.02.2018

Subject:-Laying of the pipeline of water supply scheme for seven towns under package 5B within the right of way (RoW) of the PWD roads.

101

Subject mentioned above, MP Urban Administration and Environment Department, the works is being done by the MPUDC with financial assistance from ADB. The Contractor of the works is IHP Company Limited, Mumbai. The main components Water Treatment Plant of this scheme is under construction of the at Lamhetaghat (Bhedaghat). From there water is to be supplied through the pipeline to Bhedaghat. Patan, Katanji, Panagar , Tendukheda, Majholi and Sihora.

All the subproject components are being constructed at government land Therefore, You are requested to issue no objection certificate for above said activities under project. If there will be any damage to property during laying of pipeline it will be repaired/resorted by the contractor. It will be paid to contactor according to BOQ. Laying of the pipeline is to be commenced, therefore, you are requested to direct your town engineer to allow us the laying of pipelines within RoW of the road under your jurisdiction.

It is mentioned that the operation and maintenance (O&M) work will be conducted by the construction agency for the next 10 years.

102

Letter Written to PWD, Division-1 To obtain NoC for laying the Pipelines with the RoW.

103

Letter Written to PWD Division-2 To obtain NoC for laying the Pipelines with the RoW.

104

Appendix 12: No Objection Certificate Issued by Rani Avanti Bai Lodhi Sagar Canal Prakosht to lay the Pipelines with the RoW and crossing of the canal.

English Translation: Date 06.09.2018 Letter from Superintendent Engineer, Rani Avanti Bai Lodhi Sagar Project (RABLSP) to Chief Engineer, (RABLSP) on dated 06.09.2018

Subject:- Canal Crossing for Laying of the pipeline of water supply scheme for seven towns under package 5B.

105

Subject mentioned above, MP Urban Administration and Environment Department, the works is being done by the MPUDC with financial assistance from ADB. The main components Water Treatment Plant of this scheme is under construction of the at Lamhetaghat (Bhedaghat). From there water is to be supplied through the pipeline to Bhedaghat. Patan, Katanji, Panagar , Tendukheda, Majholi and Sihora and canal to be crossed under alignment of Clear Water. Permission is granted with respect to the following conditions:

1) Pipe crossing will not disrupt the water drift of canal. 2) Any kind of damage due to project activity will be borne by the Company. 3) For each crossing it is necessary to deposit a security of Rs 5000/- (refundable) and other deposit of Rs. 5000/- for supervision charge (Non-refundable). 4) Service road of the canal should not be obstructed by laying of pipeline. During the period of the canal maintenance work, if there will be any damage to the pipeline done or interruption of water supply in the pipeline then it will be the responsibility of the company. 5) Ensure the approval of drawing of pipeline crossing on each canal crossing from the undersigned. 6) It is necessary to inform and get the permission prior to commencement of work on each canal crossing, and during construction, if the flow of canal is necessary to close than pre information is required.

106

Appendix 13: Letter to Forest Department to obtain NoC for laying the Pipelines with the RoW.

English Translation: Date 22.03.2018 Letter from Project Manager MPUDC (PIU-Jabalpur) to Division Forest Officer on dated 22.03.2018

Subject:-Laying of the pipeline of water supply scheme for seven towns under package 5B within the right of way (RoW) of the PWD roads.

Subject mentioned above, MP Urban Administration and Environment Department, the works is being done by the MPUDC with financial assistance from ADB. The Contractor of the works is IHP Company Limited, Mumbai. The main

107

components Water Treatment Plant of this scheme is under construction of the at Lamhetaghat (Bhedaghat). From there water is to be supplied through the pipeline to Bhedaghat. Patan, Katanji, Panagar , Tendukheda, Majholi and Sihora.

All the subproject components are being constructed at government land Therefore, You are requested to issue no objection certificate for above said activities under project. If there will be any damage to property during laying of pipeline it will be repaired/resorted by the contractor. It will be paid to contactor according to BOQ. Laying of the pipeline is to be commenced, therefore, you are requested to permit us the laying of pipelines within RoW of the road of SH-15 (Patan sump well to Tendukheda) under your jurisdiction.

It is mentioned that the operation and maintenance (O&M) work will be conducted by the construction agency for the next 10 years.

108

Appendix 14: Land Records of Proposed Component under WSS Scheme Khasra .no.171, 173, 175 for Proposed WTP (31 MLD) common for all 7 Towns at Bhedaghat

109

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for WTP (31 MLD) is owned by Government and survey number is 171, with an area of 1.480 hectares

110

Khasra .no.171, 173, 175 for Proposed WTP (31 MLD) common for all 7 Towns at Bhedaghat

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for WTP (31 MLD) is owned by Government and survey number is 173, with an area of 0.310 hectares

111

Khasra .no.171, 173, 175 for Proposed WTP (31 MLD) common for all 7 Towns at Bhedaghat

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for WTP (31 MLD) is owned by Government and survey number is 175, with an area of 0.120 hectares

112

Land Records of Proposed Component under WSS Scheme Land detail of Proposed OHT (220 KL) at Bhedaghat Khasra No 153/2

113

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for OHT (220 KL) is owned by Government and survey number is 153/2, with an area of 0.800 hectares

114

Land Records of Proposed Component under WSS Scheme Land detail of Proposed OHT (200 KL) at Bhedaghat Khasra No 72

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for OHT (200 KL) is owned by Government and survey number is 72, with an area of 20.950 hectares

115

Land Records of Proposed Component under WSS Scheme Land detail of Proposed OHT (120 KL) at Katangi Khasra No 136/3 and 137/3 ,

116

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for OHT (120 KL) is owned by Government and survey number is 136/ and 137/3, with an area of 4.415 and 1.255 hectares respectively

117

Land Records of Proposed Component under WSS Scheme Land detail of Proposed Clear water sump well (35 KL) at Majholi with Khasra No 401 ,

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for sump well (35 KL) is owned by Government and survey number is 401, with an area of 0.615 hectares

118

Land Records of Proposed Component under WSS Scheme Land detail of Proposed Clear water sump well (35 KL) at Majholi with Khasra No 401 ,

119

Land Records of Proposed Component under WSS Scheme Land detail Proposed OHT (700 KL) at Panagar Khasra No 344/1 and 344/2 ,

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for OHT (700 KL) is owned by Government and survey number is 344/1 with an area of 0.7290 hectares

120

Land Records of Proposed Component under WSS Scheme Land detail Proposed OHT (700 KL) at Panagar Khasra No 344/1 and 344/2 ,

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for OHT (700 KL) is owned by Government and survey number is 344/2 with an area of 0.1380 hectares

121

Land Records of Proposed Component under WSS Scheme Land detail Proposed OHT (600 KL) at Panagar Khasra No 1112

122

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for OHT (600 KL) is owned by Government and survey number is 1112 with an area of 2.0630 hectares

123

Land Records of Proposed Component under WSS Scheme Land detail Proposed OHT (200 KL) at Panagar Khasra No 1421/2

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for OHT (200 KL) is owned by Government and survey number is 1421/2 with an area of 0.350 hectares

124

Land Records of Proposed Component under WSS Scheme Land detail Proposed OHT (900 KL) at Sihora Khasra No 1488/2

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for OHT (900 KL) is owned by Government and survey number is 1488/2 with an area of 0.4050hectares

125

Land Records of Proposed Component under WSS Scheme Land detail Proposed OHT (920 KL) at Sihora Khasra No 230/1

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for OHT (920 KL) is owned by Government and survey number is 230/1 with an area of 13.921 hectares

126

Land Records of Proposed Component under WSS Scheme Land detail Proposed OHT (620 KL) at Sihora Khasra No 197/2

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for OHT (620 KL) is owned by Government and survey number is 197/2 with an area of 18.767 hectares

127

Land Records of Proposed Component under WSS Scheme Land detail Proposed OHT (630 KL) at Sihora Khasra No 275/1

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for OHT (630 KL) is owned by Government and survey number is 275/1 with an area of 61.691 hectares

128

129

Land Records of Proposed Component under WSS Scheme Land detail Proposed Sump Well (245 KL) at Sihora Khasra No 117/2

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for OHT (245 KL) is owned by Government and survey number is 117/2 with an area of 0.020 hectares

130

Land Records of Proposed Component under WSS Scheme Land detail Proposed OHT (300 KL) at Tendukheda Khasra No 685/30

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for OHT (300 KL) is owned by Government and survey number is 685/3 with an area of 4.00 hectares

131

Land Records of Proposed Component under WSS Scheme Land detail Proposed OHT (325 KL) at Tendukheda Khasra No 579/1

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for OHT (325 KL) is owned by Government and survey number is 579/1 with an area of 4.824 hectares

132

Land Records of Proposed Component under WSS Scheme Land detail Proposed Sump Well (52 KL) at Tendukheda Khasra No. 80

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for sump well (52 KL) is owned by Government and survey number is 80 with an area of 1.740 hectares

133

Land Records of Proposed Component under WSS Scheme Land detail Proposed BPT (52 KL) at Tendukheda Khasra No 23/377

English Translation Note: P Form is land record of survey number maintained by the state government (Government of Madhya Pradesh), which depicts the survey number, ownership and area. The Khasra/land record is usually accompanied by as called map. The above record depicts that the proposed site for BPT (52 KL) is owned by Government and survey number is 23/377 with an area of 1.250 hectares

134

Appendix 15: Land Status Certificate Issued by Chief Municipality Officer (CMO)

Certificate Issued by CMO, town Bhedaghat

135

Land Status Certificate Issued by Chief Municipality Officer (CMO)

Certificate Issued by CMO, town Katangi

Certified by CMO-Katangi that proposed land for OHT is government land and under possession of Urban Local Body (ULB)-Katangi and handed over for construction.

136

Land Status Certificate Issued by Chief Municipality Officer (CMO)

Certificate Issued by CMO, town Majholi

Certified by CMO-Majholi that proposed land for sump well is government land and under possession of Urban Local Body (ULB)- Majholi and handed over for construction.

137

Land Status Certificate Issued by concerned Chief Municipal Officer (CMO)

Certificate Issued by CMO, town Panagar

S.No. Proposed Component Khasra No. Area Name of Halka No. Sub District District Ward 01 OHT-1 344/1, 344/2 Gurunank Panagar Jabalpur Ward 02 OHT-2 1112 Azad Ward Panagar Jabalpur 03 OHT-3 1421/2 Moulana Panagar Jabalpur Ward

Certified by CMO-Panagar that proposed land for subproject WSS components is government land and under possession of Urban Local Body (ULB)-Panagar and handed over to MPUDC for construction.

138

Land Status Certificate Issued by concerned Chief Municipal Officer (CMO)

Certificate Issued by CMO, town Sihora

S.No. Proposed Khasra No. Area Name of Ward Halka Sub District District Component No. 01 OHT-1 197/2 Ward 13 Danav Sihora Jabalpur Baba Pahadi 02 OHT-2 230/1 Ward 04 Saiyad Sihora Jabalpur Baba Soriya 03 Sump Well 117/2 Ward 09 Pahrewa Sihora Jabalpur Nka 04 OHT-4 275/7 Ward 17 Hanuman Sihora Jabalpur Garhi 05 OHT-3 Proposed

Certified by CMO-Sihora that proposed land for OHTs and Sump well is government land and under possession of Urban Local Body (ULB)-Sihora and handed over to MPUDC for construction.

139

Land Status Certificate Issued by concerned Chief Municipal Officer (CMO)

Certificate Issued by CMO, town Sihora

S.No. Proposed Khasra No. Area Name of Halka No. Sub District District Component Ward 05 Over Head Tank 1488 Ward 11 Sihora Jabalpur Near Girls School

Certified by CMO-Sihora that proposed land for OHT (900 KL) is government land with survey number 1488 and under possession of Urban Local Body (ULB)-Sihora and handed over to MPUDC for construction.

140

Land Status Certificate Issued by concerned Chief Municipal Officer (CMO)

Certificate Issued by CMO, town Tendukheda

Certified by CMO-Tendukheda that proposed land for OHTs, BPT and sump well is government land and OHT-325 KL is under possession of Urban Local Body (ULB)-Tendukheda

141

Appendix 16: Letter to District Collector from Nagar Parishad-Bhedaghat for land allocation for Proposed Components under WSS

English Translation: Letter to District Collector-Jabalpur from CMO-Bhedaghat on dated 16th January 2018 Reference to the subject for allotment of the identified land for subproject components; Proposed lands under WSS, according to the proposal passed in the meeting dated 12.01.2018 of the council town Bhedaghat, therefore, you are requested to allot the lands parcels and transfer the land in the name of Nagar Parishad- Bhedaghat.

142

Appendix 17: Letter to District Collector from Nagar Parishad (Bhedaghat) for land allocation for Proposed Components under WSS

English Translation: Letter to District Collector-Jabalpur from CMO-Bhedaghat on dated 17th April 2018 Reference to the subject for allotment of the identified land for subproject components; Intake Well and WTP is proposed under WSS town Bhedaghat, therefore, you are requested to allot the lands parcels and transfer the land in the name of Nagar Parishad-Bhedaghat. Identified land survey number 171, 173, 175 and 176 and allot the 1.50 ha for WSS components. You are requested to issue no objection certificate and transfer of the land of above mentioned survey number to ULB-Bhedaghat.

143

Appendix 18: Letter to District Collector from Nagar Parishad (Katangi) for land allocation for Proposed Components under WSS

English Translation: Letter to District Collector-Jabalpur from CMO-Katangi on dated 11th January 2018 Reference to the subject for allotment of the identified land for subproject components; Two OHTs are proposed under WSS town Katangi, therefore, you are requested to allot the lands parcels and transfer the land in the name of Nagar Parishad-Katangi. Identified land 0.619 Hectare in survey number 136/3, and survey number 137/3, land area is 1.255 Hectare. You are requested to issue no objection certificate and transfer of the land of above mentioned survey number to ULB-Katangi.

144

Appendix 19: Letter to District Collector and Tehsildar from Nagar Parishad (Majholi) for land allocation for Proposed Components under WSS

English Translation: Letter to Tehsildar from CMO-Majholi on dated 25th June 2018 Reference to the subject for demarcation and allotment of the identified land for subproject components; Pump House is proposed under WSS town Majholi, therefore, you are requested to allot the land and transfer the land in the name of Nagar Parishad-Majholi. Identified land survey number for Pump House, survey number 401, area 0.651hectare in Patwari Halka No. 21,.

145

Appendix 20: Letter to District Collector and Tehsildar from Nagar Parishad (Panagar) for land allocation for Proposed Components under WSS

English Translation: Letter to District Collector-Jabalpur from CMO-Panagar on dated 22 December 2018 Reference to the subject for allotment of the identified land for subproject components; OHTs is proposed under WSS town Panagar, therefore, you are requested to allot the lands parcels and transfer the land in the name of Nagar Parishad-Panagar. Identified lands survey number is (OHT-1) 344/1, 344/2.(OHT-2) 8/1112 and (OHT-3) 1421/2. Above mentioned survey numbers are under possession of ULB-Panagar, so, Please transfer of the land of above mentioned survey number in the name of ULB- Panagar.

146

Appendix 21: Letter to District Collector from Nagar Parishad (Sihora) for land allocation for Proposed Components under WSS

English Translation: Letter to District Collector-Jabalpur from CMO-Sihora on dated 22 December 2018 Reference to the subject for allotment of the identified land for subproject components; Four OHTs and One Sump Well is proposed under WSS town Sihora, therefore, you are requested to allot the lands parcels and transfer the land in the name of Nagar Parishad-Sihora. Land is required in each Identified land is 200 x 200 Sq. feet and survey number 197/2, 230/1, 1488 & 275/1 for OHTs and in survey number 117/2 for Sump Well. You are requested to issue no objection certificate and transfer of the land of above mentioned survey number to ULB-Sihora.

147

Appendix 22: Letter to Tehsildar (Tendukheda) from Nagar Parishad (Sihora) for land allocation for Proposed Components under WSS Part A

English Translation: Letter to Tehsildar from CMO-Tendukheda on dated 07 January 2019 Reference to the subject for allotment of the identified land for subproject components; BPT and OHTs are proposed under WSS town Tendukheda and these sites bolng to government, therefore, you are requested to allot the lands parcels and transfer the land in the name of Nagar Parishad- Tendukheda.

148

Letter to Tehsildar (Tendukheda) from Nagar Parishad (Sihora) for land allocation for Proposed Components under WSS

Part B

English Translation: Letter to Tehsildar from CMO-Tendukheda on dated 07 January 2019 Reference to the subject for allotment of the identified land for subproject components; One sump well is also proposed under WSS town Tendukheda and this site is located near state highway and village road. Identified Khasra number is 80 and belongs to government. You are requested to allot the land and transfer the land in the name of Nagar Parishad- Tendukheda.

149