SITE SERVICES DUE DILIGENCE REPORT Electrical Communications Fire Mechanical Hydraulics

ON BEHALF OF

Johns Group Hotel Redevelopment 3096 Marlborough Highway Miena

UNDERTAKEN BY

COORDINATED ENGINEERING SERVICES BUILDING SERVICES CONSULTING ENGINEERS Unit 1, 136 Davey Street, Hobart 7000 P: 03 6294 6033 E: [email protected]

MAY 2019

Building Services Condition Report INDEX

1.0 GENERAL ...... 1

1.1 SCOPE ...... 1

1.2 DEFINITION OF SYMBOLS AND TERMS ...... 1

2.0 INFRASTRUCTURE ...... 1

2.1 POWER SUPPLY ...... 1

2.2 COPPER TELEPHONE SERVICES ...... 3

2.3 NBN ...... 3

2.4 LPG ...... 4

2.5 FIRE DETECTION AND PROTECTION ...... 4

2.6 WATER SUPPLY ...... 6

2.7 SEWER ...... 6

2.8 STORM WATER ...... 7

3.0 BUILDING SERVICES ...... 7

3.1 GENERAL ...... 7

3.2 SWITCHBOARDS, SUBMAINS & CABLING ...... 8

3.3 INTERNAL LIGHTING ...... 9

3.4 EXTERNAL LIGHTING ...... 10

3.5 HEATING ...... 10

3.6 EMERGENCY & EXIT LIGHTING ...... 11

3.7 DATA & WI-FI...... 11

3.8 ELECTRONIC SECURITY ...... 12

3.9 MATV & FOXTEL ...... 12

3.10 AIR CONDITIONING ...... 13

3.11 LAUNDRY EQUIPMENT ...... 13

3.12 HOT WATER SYSTEMS ...... 13

3.13 MECHANICAL EXHAUST ...... 14

3.14 BUILT UP COOLROOMS AND FREEZER ROOMS ...... 16

CES196066R-A1-HA01 Great Lake Hotel Redevelopment May 2019 Miena for Johns Group (i) Building Services Condition Report

1.0 GENERAL

1.1 SCOPE

The following Building Services Due Diligence Report for both the Hotel and adjacent Shop encompasses:

• Electrical Services including Communications • Fire Detection and Alarm Systems • Mechanical Services including LP Gas Services • Hydraulics Services • Fire Fighting Services

1.2 DEFINITION OF SYMBOLS AND TERMS

Throughout this section the following terms and abbreviations are used to denote equipment and services.

CCTV Closed Circuit Television EFTPOS Electronic Funds Transfer at Point of Sales FTA Free to Air kVA Kilovolt Ampere LED Light Emitting Diode LPG Liquified Petroleum Gas MATV Master Antenna Television NBN National Broadband Network TMV Thermostatic Mixing Valve

2.0 INFRASTRUCTURE

2.1 POWER SUPPLY

There are three wood poles on the site belonging to Tasnetworks and carrying high voltage along the South Western boundary. The pole closest to the existing accommodation block (414847) has a relatively new pole mounted transformer (T72 117) which although has lost its markings, is about the size of a 200kVA unit or 260 Amps per phase.

CES196066R-A1-HA01 Great Lake Hotel Redevelopment May 2019 Miena for Johns Group (1) Building Services Condition Report

An overhead supply in ABC or insulated conductor runs to a private pole (414848) which is in good condition. At this point there are some pole mounted service fuses to protect an underground 3 phase supply to a main switchboard on the side of the shop. This is supply authority metered on one tariff and is rated at less than 40 Amps per phase.

Also from the private pole, 4 single insulated conductors are strung overhead across the internal carpark to the wall of the hotel on the second level. These then pass down the wall cavity to the Hotel main switchboard below. The switchboard is metered on three tariffs – light and power (3 phase 100 Amp), Hot water (1 phase 80 Amp) and off peak (1 phase 80? Amp).

There is a separate switch for the fire pump (1 phase 35 Amp). A non-compliance is that there are 2 points of supply for the one title but could be argued on physical separation of the Shop and Hotel that this is acceptable. Will affect future development of the site and would require a new site main switchboard.

The Hotel has no back-up generator or point of connection.

The Shop has a back-up generator but it is owned by the Lessee.

It was reported that whilst power outages are not that prevalent, they can last for extended periods. This needs to be balanced against a potential cost of $60k or so to install a back-up generator to the Hotel.

CES196066R-A1-HA01 Great Lake Hotel Redevelopment May 2019 Miena for Johns Group (2) Building Services Condition Report

2.2 COPPER TELEPHONE SERVICES

Telstra underground cables and pits exist in the road verge of the Marlborough Highway. There appears to be separate copper cables run underground to the Hotel and Shop, these could not be located but would be 10 pair based on past usage.

The services to the Shop are no longer utilised but there is a public phone box which remains operational. The services to the Hotel are only utilised for FAX and telephone landline.

2.3 NBN

Both the Hotel and Shop have independent wireless broadband services with a direct line of site to the local tower. Each has a dish on the roof.

The Hotel has two service providers over the link – one for private owners use and one for EFTPOS, KENO and Hotel Wi-Fi.

The Wi-Fi service provided free to customers has no reported limitations – the only issue is that in case of power failure at the tower site, the NBN service is lost after approximately 3 hours.

CES196066R-A1-HA01 Great Lake Hotel Redevelopment May 2019 Miena for Johns Group (3) Building Services Condition Report

2.4 LPG

There is a substantial bullet on site to provide LPG to site services. At this time that is confined to kitchen equipment (2 deep fryers, griddle and 8 burner cook top) and space heating in the second level private residence. Previous connections to gas dryers have been capped off.

2.5 FIRE DETECTION AND PROTECTION

Fire detection is limited to stand alone smoke alarms in bedrooms. There is no AS 1670.1 detection system or occupant warning system in any of the buildings.

Fire protection is afforded by a series of 4 external fire hose reels throughout the Hotel and a non-compliant hydrant adjacent the fire water tank. There are no facilities to the Shop and camping grounds.

CES196066R-A1-HA01 Great Lake Hotel Redevelopment May 2019 Miena for Johns Group (4) Building Services Condition Report

There is an above ground PVC water tank of some 20,000l capacity against the cabin accommodation block. Adjacent to this is an electric fire pump and an 80 mm stand pipe hydrant connected to the tank. From the tank to the pump is a PVC pipe that is subject to fire or physical damage (along with the tank if there was a fire in the accommodation block). From the pump, fire water is piped underground in PVC pipe to 4 external fire hose reels. These fire hose reels have been maintained but some of the enclosures require replacement. Adequate coverage from the FHR would need to be checked for compliance.

The procedure in case of fire is to go to the tank, open the valve and manually start the pump. In case of loss of power supply and without a means of advance warning via a smoke detection system, lack of any automation or provision of alarms in case of loss of water supply in the tank make the system a risk that would need to be assessed by a Fire Engineer.

There is no fire sprinkler system.

CES196066R-A1-HA01 Great Lake Hotel Redevelopment May 2019 Miena for Johns Group (5) Building Services Condition Report

2.6 WATER SUPPLY

Fresh water supply is from an on-site bore that fills an underground tank via float control on the East of the Hotel. This water is then pumped to service the Hotel and Shop.

The Shop has an external tank that gravity feeds the Shop in times of loss of power supply. Pumping to a high level tank to then gravity feed all water outlets may assist in times of power failure.

2.7 SEWER

All sewer connections including the Shop are gravity fed to a septic tank system on the East of the Hotel. The grey water is separately collected in an adjacent tank and then pumped to a primary and secondary settling pond to the West of the site.

CES196066R-A1-HA01 Great Lake Hotel Redevelopment May 2019 Miena for Johns Group (6) Building Services Condition Report

Advice was that the septic tank required pumping out every 6 to 9 months.

During Winter the public toilet adjacent the Shop is subject to freezing and requires management. The grey water pump system has been replaced recently.

2.8 STORM WATER

There is evidence that downpipes from the building also run into a second underground tank which is then utilised for site irrigation via a separate pump.

3.0 BUILDING SERVICES

3.1 GENERAL

We understand the building was constructed in 1984 and taken over by the present owner some 16 years ago. There are numerous non conformances obviously with current standards but they would only come into effect if substantial modifications were undertaken where we have noted – or else compliance with standards at the time of construction is assumed.

The owner has undertaken most maintenance of services required and has undertaken some upgrades to services such as replacement of bayonet lamps with compact fluorescent type, upgrade of grey water pump station, replacement of hot water cylinders as required, external flood lighting replacement with LED type, Freezer Room condenser upgrade.

CES196066R-A1-HA01 Great Lake Hotel Redevelopment May 2019 Miena for Johns Group (7) Building Services Condition Report

3.2 SWITCHBOARDS, SUBMAINS & CABLING

The main switchboard for the Hotel is located externally and is set up for three tariffs. Submains for light and power and hot water are extended to 5 panel boards (single phase) that service the accommodation wings.

All submain protection and subcircuit protection are circuit breakers but there are no RCD circuit breakers installed apart for the new sewer pump station.

4 of the panel boards are equipped with circuit breakers but only one subcircuit (fire pump) has RCD protection. One panel board is equipped with fuse cartridges with some circuit breaker inserts but no RCD protection.

The main switchboard for the Shop is located externally and is single tariff only. It is equipped with circuit breakers but only one is RCD protected – the recently installed air conditioner.

CES196066R-A1-HA01 Great Lake Hotel Redevelopment May 2019 Miena for Johns Group (8) Building Services Condition Report

3.3 INTERNAL LIGHTING

Hotel lighting control is from a central location BOH – straight switching and no dimming.

Luminaires date back to original construction and therefore are approaching end of life and several already have.

The original lighting would have consisted of surface mounted fluorescent battens plus surface mounted incandescent batten holders and recessed incandescent downlights.

Internally batten holders and recessed downlights have had the incandescent lamps replaced with compact fluorescent lamps. This has created a glare issue in the main.

Fluorescent battens need replacing as lamps will no longer be available and are corroded externally.

In accommodation areas there are fluorescent battens plus some incandescent wall lights – comments apply as above.

CES196066R-A1-HA01 Great Lake Hotel Redevelopment May 2019 Miena for Johns Group (9) Building Services Condition Report

3.4 EXTERNAL LIGHTING

Several building mounted flood lights have been replaced with LED type. Coverage at night is unknown but should be adequate to complement CCTV coverage. Covered walkway lighting to accommodation units consist of fluorescent battens that need maintenance plus incandescent batten holders that have no lamps.

There is no car park pole lighting as such, reliant on building mounted lighting.

Shop has some new fluorescent luminaires under driveway canopy but some original fittings remain. Similarly within Shop – surface mounted fluorescent fittings.

3.5 HEATING

Off peak power supplies feed into in slab floor heating in the Dining Rooms and Bar. These have been disconnected and no longer utilised in favour of wood heaters. Removal of this tariff should be considered.

Bedrooms are heated with wall mounted fan heaters. There is no heating in ensuites.

CES196066R-A1-HA01 Great Lake Hotel Redevelopment May 2019 Miena for Johns Group (10) Building Services Condition Report

Common areas are predominately heated with wood heaters.

Ancillary heating to the Shop is by a floor mounted LPG gas heater supplied from a dedicated bottle supply.

3.6 EMERGENCY & EXIT LIGHTING

There was no evident emergency lighting to any of the buildings including Shop and no emergency and exit light test stations to any switchboards.

There is one lit exit sign to the main entry and one to the rear entry only. Neither are operable on battery and have probably not had regular testing undertaken.

3.7 DATA & WI-FI

There is no communications rack on site as such, discrete Cat 5E links are used to interconnect NBN to shelf mounted switches and to EFTPOS, Room Booking system and the like.

CES196066R-A1-HA01 Great Lake Hotel Redevelopment May 2019 Miena for Johns Group (11) Building Services Condition Report

Similarly there are 3 Wi-Fi wireless access points within the accommodation areas to provide full coverage to the site.

3.8 ELECTRONIC SECURITY

The Hotel has a domestic type electronic intruder detection system only with limited motion detectors plus external and internal annunciators.

The Hotel has a 16 camera colour CCTV system with three monitors in BOH for monitoring.

The Shop has a 4 camera colour CCTV system with a single monitor.

There is no access control system.

3.9 MATV & FOXTEL

There are separate MATV systems to Shop and Hotel. In the Hotel there is a FTA distributed system to all bedrooms but not Foxtel.

CES196066R-A1-HA01 Great Lake Hotel Redevelopment May 2019 Miena for Johns Group (12) Building Services Condition Report

There are separate Foxtel (or equivalent) dishes to Shop and Hotel.

3.10 AIR CONDITIONING

The only unit located on site is within the Shop and is Lessees private property.

3.11 LAUNDRY EQUIPMENT

Two commercial electric washers and two commercial electric dryers in good condition.

3.12 HOT WATER SYSTEMS

There are 4 electric hot water cylinders servicing the site. They age between 2009 and 2011 so a replacement scheme has been ongoing.

CES196066R-A1-HA01 Great Lake Hotel Redevelopment May 2019 Miena for Johns Group (13) Building Services Condition Report

No evidence of TMV’s or tempering valves were located. No cylinders had drain trays with subsequent drainage to waste.

3.13 MECHANICAL EXHAUST

Most ensuites and amenities do not have mechanical exhaust and rely on natural ventilation via opening windows.

There are 6 wall mounted exhausts to the Dining and Bar areas that are individually controlled from BOH area.

CES196066R-A1-HA01 Great Lake Hotel Redevelopment May 2019 Miena for Johns Group (14) Building Services Condition Report

There are wall mounted exhausts to amenities in Bar area.

Kitchen hood is non-compliant as it has a horizontal section of canopy. The effectiveness of the fan is questionable as kitchen paper is evident in the drain tray of the hood. Testing of the fan performance and cleaning of system components upstream of filters would be recommended. Make up air is via opening window and door. Must be a major issue in Winter if no preheating is undertaken.

CES196066R-A1-HA01 Great Lake Hotel Redevelopment May 2019 Miena for Johns Group (15) Building Services Condition Report

3.14 BUILT UP COOLROOMS AND FREEZER ROOMS

There is a Kitchen Freezer, Kitchen Cold Room and Bottle Shop Cool Room on site. The Freezer is serviced by a condenser unit installed some 7 years ago. The Cold Room is serviced by a condenser unit dating back to original installation. Refrigeration gas is non-compliant. The Cool Room is serviced by a condenser unit dating back to original installation. Refrigeration gas is non-compliant.

If maintenance is continued, all units should be adequate for 5 to 10 years’ service.

All rooms are non-compliant with respect to lighting, lighting control, emergency lighting, escape facilities, monitoring and alarms.

CES196066R-A1-HA01 Great Lake Hotel Redevelopment May 2019 Miena for Johns Group (16)

Proposed Residential Development – ‘Great Lake Hotel’ 3096 Malborough Road, Miena

Bushfire Hazard Report

Applicant: Phillip Lighton Architects

September 2019 GES00017v1.0

GEO- ENVIRONMENTAL SOLUTIONS 29 Kirksway Place, Battery Point, . 7004. T|62231839 E|[email protected] www.geosolutions.net.au

Contents

1.0 Purpose ...... 3 2.0 Summary ...... 3 3.0 Introduction ...... 3 4.0 Proposal ...... 4 5.0 Bushfire Attack Level (BAL) Assessment ...... 4 6.0 Results ...... 7 6.1 Property Access ...... 7 6.2 Water supplies for fire fighting ...... 7 6.3 Hazard Management Area...... 8 7.0 Compliance ...... 9 8.0 Guidance ...... 10 9.0 Further Information ...... 10 10.0 References ...... 11 11.0 Limitations Statement...... 12 Appendix A – Site Photos ...... 13 Appendix B - Site Plan ...... 15

Attachment 1 – Bushfire Hazard Management Plan Attachment 2 - Certificate of Others (form 55)

Disclaimer

The measures contained in Australian Standard 3959-2018 cannot guarantee that a building will survive a bushfire event on every occasion. This is substantially due to the unpredictable nature and behaviour of fire and extreme weather conditions.

Reasonable steps have been taken to ensure that the information contained within this report is accurate and reflects the conditions on and around the lot at the time of assessment. The assessment has been based on the information provided by you or your designer.

Authorship This report was prepared by Mark Van den Berg BSc. (Hons.) FPO (planning) of Geo Environmental Solutions. Base data for mapping: TasMap, Digital and aerial photography: Mark Van den Berg, GoogleEarth.

Bushfire Hazard Report – 3096 Malborough Road, Miena. September 2019. GES00017v1.0 2 of 18

1.0 Purpose

This Bushfire Hazard Report is intended to provide information in relation to the proposal. It will demonstrate compliance with the Building Amendment (Bushfire-Prone Areas) Regulations 2014, and the Determination, Director of Building Control – Requirements for Building in Bushfire-Prone Areas, version 2.1 29th August 2017 (Determination). Provide a certificate of others (form 55) as specified by the Director of Building Control for bushfire hazard and give guidance by way of a certified bushfire hazard management plan which shows a means of protection from bushfires in a form approved by the Chief Fire Officer of the Tasmania Fire Service.

2.0 Summary

Site details & compliance Title reference 244058/1 PID 7148876 Address 3096 Malborough Road, Miena Applicant Phillip Lighton Architects Municipality Central Highlands Planning Scheme Central Highlands Interim Planning Scheme 2015 Zoning Local Business Land size ~2.9Ha Bushfire Attack Level BAL-12.5 Certificate of others (form 55) Complete and attached Bushfire Hazard Management Plan Certified & Attached

Alterations and additions to an existing building at 3096 Malborough Road, Miena requires demonstrated compliance with Building Amendment (Bushfire-Prone Areas) Regulations 2014, and the Determination, Director of Building Control – Requirements for Building in Bushfire-Prone Areas, version 2.1 29th August 2017, the site is located in a bushfire prone area. The Bushfire attack level has been determined as ‘BAL- 12.5’, provisions for property access and water supplies for firefighting are detailed in this report and on the Bushfire Hazard Management Plan (BHMP).

3.0 Introduction

This bushfire hazard report has been completed to form part of supporting documentation for a building permit application for the proposed development. The proposed development site has been identified as being in a bushfire prone area. A site-specific bushfire hazard management plan has been provided for compliance purposes.

Bushfire Hazard Report – 3096 Malborough Road, Miena. September 2019. GES00017v1.0 3 of 18

4.0 Proposal

The proposal is for alterations and additions to an existing building at 3096 Malborough Road, Miena (appendix B). Construction standards for buildings, property access, water supplies for firefighting and hazard management areas will be required (as appropriate) to meet the standards outlined in the ‘Director’s Determination – Requirements for Building in Bushfire-Prone Areas’ and ‘Australian Standard 3959-2018 Construction of Buildings in Bushfire-prone Areas.

5.0 Bushfire Attack Level (BAL) Assessment

5.1 Methods

The Bushfire attack level has been determined through the application of section 2 of AS3959-2018 ‘Simplified Procedure’ of AS3959-2018. Vegetation has been classified using a combination of onsite observations and remotely sensed data to be consistent with table 2.3 of AS359-2018. Slope and distances have been determined by infield measurement and/or the use of remotely sensed data (aerial/satellite photography, GIS layers from various sources) analysed with proprietary software systems. Where appropriate vegetation will be classified as low threat.

5.2 Site Description

The proposal is located at 3096 Malborough Road, Miena, in the municipality of Central Highlands and is zoned Local Business under the Central Highlands Interim Planning Scheme 2015. Access to the lot will be by an existing crossover from Malborough Road, a state-maintained road. The lot is ~ 2.9 ha is irregular in shape and is located approximately 1.8km north west of Mackersay Head (Figure 1). Adjacent lands surrounding the lot are zoned rural resource. At a landscape scale the lot occurs on the south western edge of Great Lake in a rural setting characterised by predominantly native forest vegetation. The lot has gentle slopes with a northerly aspect and is unlikely to influence fire behaviour.

Vegetation surrounding the lot was assessed (Table 1) and described as ‘Grassland and Forest’ (as per AS3959-2018). The classified vegetation potentially having the greatest impact on the site occurs on every azimuth of the site (Figure 2). The vegetation classification system as defined in AS 3959-2018 Table 2.3 and Figure 2.3 (A to G) has been used to determine vegetation types within 100 metres of the site (Table 1).

Bushfire Hazard Report – 3096 Malborough Road, Miena. September 2019. GES00017v1.0 4 of 18

Figure 1. The lot in a topographical context (lot outlined in pink).

Figure 2. Shows the approximate location of the site (pink line) in the context of the adjacent lands and classified vegetation.

Bushfire Hazard Report – 3096 Malborough Road, Miena. September 2019. GES00017v1.0 5 of 18

Table 1. Bushfire Attack Level (BAL) Assessment

Distance to Hazard Bushfire Azimuth Vegetation Classification Effective Slope Bushfire-prone management Attack Level vegetation area width Exclusion 2.2.3.2 (e, f)^^ flat 0º 0 to 46 metres Forest^ upslope 46 to >100 metres North 7 metres BAL-12.5 ------Grassland^ >0 to 5º downslope 0 to 55 metres Forest^ >0 to 5º downslope 55 to >100 metres East 16 metres BAL-12.5 ------Grassland^ upslope 0 to 80 metres Forest^ upslope 80 to >100 metres South 14 metres BAL-12.5 ------Exclusion 2.2.3.2 (e, f)^^ flat 0º 0 to >100 metres ------West 14 metres BAL-LOW ------^ Vegetation classification as per AS3959-2018 amendment 3, Table 2.3 and Figures 2.4(A) to 2.4 (G). * Low threat vegetation as per Bushfire Prone Areas Advisory Note (BHAN) No.1-2014, version 3, 8/11/2017. ^^ Exclusions as per AS3959-2018 amendment 3, section 2.2.3.2, (a) to (f).

Bushfire Hazard Report – 3096 Malborough Road, Miena. September 2019. GES00017v1.0 6 of 18

6.0 Results

The bushfire attack level for the site has been determined as BAL-12.5. While the risk is considered to be low, there is a risk of ember attack and a likelihood of low levels of radiant heat impacting the site. The construction elements are expected to be exposed to a heat flux not greater than 12.5 kW/m2. The northern azimuth requires a minimum separation distance from the bushfire prone vegetation of 32 metres to achieve a BAL of 12.5. This will be a combination of 7 metres inside the title boundary and the adjoining excluded land.

6.1 Property Access There is existing access to the site, in this circumstance there is no further requirement for the design or constructions standards for property access.

6.2 Water supplies for fire fighting Static water supplies and associated infrastructure for firefighting purposes will be provided in accordance with table 4.3B of the Determination, Director of Building Control – Requirements for Building in Bushfire- Prone Areas, version 2.1 29th August 2017. The following elements of table 4.3B as noted above will be required to meet compliance; A Distance between building area to be protected and water supply B Static water supplies C Fittings, Pipework and accessories (including tank and stands) D Signage for static water supply connections E Hardstand

Bushfire Hazard Report – 3096 Malborough Road, Miena. September 2019. GES00017v1.0 7 of 18

6.3 Hazard Management Area. The Bushfire Attack Level for this site is BAL-12.5. A hazard management area contained within the title boundaries will need to be established to achieve this outcome. Table 1 above shows the minimum separation distances (hazard management area width) for each azimuth of the site that will result in a bushfire attack level of BAL-12.5. These are the minimum separation distance between the site (house) and the bushfire prone vegetation.

The bushfire attack level for the proposed site is BAL-12.5. There is a risk of ember attack, particularly from wind borne embers from forest vegetation types in the local area. The hazard management area should have sufficient fuel removed such that the propagation or carriage of fire is significantly impeded.

Hazard management areas for alterations or additions to buildings must meet the following requirements: (a) Be located on the lot so as to be provided with an HMA which: (i) Has the separation distances required for the BAL assessed for the construction of the existing building; or (ii) In the case of a building without an existing BAL assessment, is no smaller than the separation distances required for BAL 29; and (b) Have an HMA established in accordance with a certified bushfire hazard management plan.

The attached bushfire hazard management plan is certified and provides for the above conditions to be met. Separation distances are given and will provide for a bushfire attack level of BAL-12.5 at the site.

Bushfire Hazard Report – 3096 Malborough Road, Miena. September 2019. GES00017v1.0 8 of 18

7.0 Compliance Section 4 of the Directors Determination Requirements for Building in Bushfire-prone Areas, version 2.1, 29th August 2017. Table 2. Deemed to Satisfy requirements s4. Section Requirement Compliance 4.1. Construction (1) Building work (including additions or alterations to an Requirements existing building) in a bushfire-prone area must be designed and constructed in accordance with an Acceptable Construction Manual determined by the BCA, being either: - (a) AS 3959-2018; or (b) Nash Standard - Steel Framed Construction in Bushfire Areas as appropriate for a BAL determined for that site. (2) Subclause (1)(a) is applicable to the following: (a) a Class 1, 2 or 3 building; or (b) a Class 10a building or deck Construction to associated with a Class 1, 2 or 3 building. BAL-12.5 3) Subclause (1)(b) is applicable to the following: of AS3959-2018 (a) a Class 1 building; or (b) a class 10a building or deck associated with a Class 1 building. (4) Despite subsection (1) above, variations from requirements specified in 1(a) and 1(b) are as specified in Table 4.1 below. (5) Despite subsections (1) and (4) above, performance requirements for buildings subject to BAL 40 or BAL Flame Zone (BAL-FZ) are not satisfied by compliance with subsections (1) or (4) above. 4.2. Property (1) A new building constructed in a bushfire-prone area must Access be provided with property access to the building and the fire- fighting water point, accessible by a carriageway, designed Property access and constructed as specified in subsection (2) below. specified as per (2) Vehicular access from a public road to a building must: (a) table 4.2 Meet the property access requirements described in Table

4.2; (b) Include access from a public road to within 90 metres

of the furthest

part of the building measured as a hose lay; and (c) Include access to the hardstand area for the fire-fighting water point. 4.3. Water Supply (1) A new building constructed in a bushfire-prone area, must for Fire fighting be provided with a water supply dedicated for fire-fighting purposes as specified in subsections (2) and (3) below. Water supplies for (2) Water supplies for fire-fighting must meet the fire-fighting requirements described in Tables 4.3A or 4.3B. specified as per (3) The water supply must be: table 4.3B (a) Provided from a fire hydrant or static water supply; (b)

Located within the specified distance from the building to be protected; and (c) Provided with a hardstand and suitable connections. 4.4. Hazard (1) A new building, or extension to a building, constructed in Hazard Management Areas a bushfire-prone area must be provided with a HMA of management area sufficient dimensions and which provides an area around the shown on the building which separates the building from the bushfire bushfire hazard hazard. management plan (2) The HMA must comply with Table 4.4; and (BHMP), consistent (3) The HMA for a particular BAL must have the minimum with separation for dimensions required for the separation distances specified for BAL-12.5, that BAL in Table 2.4.4 of AS 3959-2018; and requirements for (4) The HMA must be established such that fuels are reduced hazard reduction sufficiently, and other hazards are removed such that the on BHMP. fuels and other hazards do not significantly contribute to the bushfire attack.

Bushfire Hazard Report – 3096 Malborough Road, Miena. September 2019. GES00017v1.0 9 of 18

8.0 Guidance

The defendable space (hazard management area) around a building is critical for providing occupants and/or fire fighters with safe access to the building in order that fire fighting activities may be under taken. The larger the defendable space, the safer it will be for those defending the structure. Some desirable characteristics of a hazard management area are:

• The area directly adjacent to the building has a significant amount of flammable material removed such that there is little to no material available to burn around the building; • Includes non flammable areas such as paths, driveways, short cropped lawns; • Establishment of orchards, vegetable gardens, dams or waste water effluent disposal areas on the fire prone side of the building; • Creating wind breaks and radiation shields such as non combustible fences and low flammability hedges; • Removing fire hazards such as wood piles, rubbish heaps and stored fuels; • Creating and maintaining vertical as well as horizontal separation between ground fuels and tree canopies by pruning; • It is not necessary to remove all vegetation from the defendable space, trees can provide protection from wind borne embers and radiant heat in some circumstances.

9.0 Further Information

For further information on preparing yourself and your property for bushfires visit the Tasmania Fire Service website at www.fire.tas.gov.au or phone 1800 000 699 for information on: • Preparing a bushfire survival plan • Preparing yourself and your home for a bushfire • Guidelines for development in bushfire prone areas in Tasmania • Fire resisting plants for the urban fringe and rural areas • Using fire outdoors • Fire permits • Total fire bans • Bushfires burning in Tasmania

Bushfire Hazard Report – 3096 Malborough Road, Miena. September 2019. GES00017v1.0 10 of 18

10.0 References

Australian Building Codes Board, National Construction Code, Building Code of Australia, Australian Building Codes Board, Canberra.

Building Amendment (Bushfire-Prone Areas) Regulations 2016

Determination, Director of Building Control – Requirements for Building in Bushfire-Prone Areas, version 1 14th March 2016. Consumer, Building and Occupational Services, Department of Justice, Tasmania.

The Bushfire Planning Group 2005, Guidelines for development in bushfire prone areas of Tasmania – Living with fire in Tasmania, Tasmania Fire Service, Hobart.

Tasmania Fire Service 2013, Building for Bushfire – Planning and Building in Bushfire-Prone Areas for Owners and Builders.

Central Highlands Interim Planning Scheme 2015, Tasmanian Planning Commission 2015, Tasmanian Planning Commission, Hobart.

Bushfire Hazard Report – 3096 Malborough Road, Miena. September 2019. GES00017v1.0 11 of 18

11.0 Limitations Statement

This Bushfire Hazard Report has been prepared in accordance with the scope of services between Geo- Environmental Solutions Pty. Ltd. (GES) and the applicant named in section 2. To the best of GES's knowledge, the information presented herein represents the Client's requirements at the time of printing of the Report. However, the passage of time, manifestation of latent conditions or impacts of future events may result in findings differing from that described in this Report. In preparing this Report, GES has relied upon data, surveys, analyses, designs, plans and other information provided by the Client and other individuals and organisations referenced herein. Except as otherwise stated in this Report, GES has not verified the accuracy or completeness of such data, surveys, analyses, designs, plans and other information. The scope of this study does not allow for the review of every possible bushfire hazard condition and does not provide a guarantee that no loss of property or life will occur as a result of bushfire. As stated in AS3959-2018 “It should be borne in mind that the measures contained in this Standard cannot guarantee that a building will survive a bushfire event on every occasion. This is substantially due to the degree of vegetation management, the unpredictable nature and behaviour of fire, and extreme weather conditions”. In addition, no responsibility is taken for any loss which is a result of actions contrary to AS3959-2018 or the Tasmanian Planning Commission Bushfire code. This report does not purport to provide legal advice. Readers of the report should engage professional legal practitioners for this purpose as required. No responsibility is accepted for use of any part of this report in any other context or for any other purpose by third party.

Bushfire Hazard Report – 3096 Malborough Road, Miena. September 2019. GES00017v1.0 12 of 18

Appendix A – Site Photos - Figures associated with table 1.

Figure 3. Northern azimuth from site.

Figure 4. Eastern azimuth from site.

Bushfire Hazard Report – 3096 Malborough Road, Miena. September 2019. GES00017v1.0 13 of 18

Figure 5. Southern azimuth from site.

Figure 6. Western azimuth from site

Bushfire Hazard Report – 3096 Malborough Road, Miena. September 2019. GES00017v1.0 14 of 18

Appendix B - Site Plan

Bushfire Hazard Report – 3096 Malborough Road, Miena. September 2019. GES00017v1.0 15 of 18 BUSHFIRE HAZARD MANAGEMENT PLAN Bushfire Hazard Management Plan, 'Great Lake Hotel' 3096 Malborough Road. Miena. September 2019. GES00017v1.0 Standards for Property Access Central Highlands Interim Planning Scheme 2015 There are no applicable specifications for design or construction of property access in this circumstance.

4.3B Static Water Supply for Fire fighting

Static water supplies and associated infrastructure for firefighting purposes will be provided in accordance with table 4.3B of the Determination, Director of Bushfire Hazard. Building Control – Requirements for Building in Bushfire-Prone Areas, version 2.1, 29th August 2017. Malborough Road 29 Kirksway Place, Battery Point A Distance between building area to be protected and water supply T| 62231839 E| [email protected] The following requirements apply: (a) The building area to be protected must be located within 90 metres of the fire fighting water point of a static water supply; and (b) The distance must be measured as a hose lay, between the fire fighting water point and the furthest part of the building area.

B) Static Water Supplies A static water supply: (a) May have a remotely located offtake connected to the static water supply; Alteration/ (b) May be a supply for combined use (fire fighting and other uses) but the addition specified minimum quantity of fire fighting water must be available at all times; Alterations and Additions 7 metres (c) Must be a minimum of 10,000 litres per building area to be protected. This Exclusion volume of water must not be used for any other purpose including fire fighting sprinkler or spray systems; 2.2.3.2 (e, f) (d) Must be metal, concrete or lagged by non-combustible materials if above Existing ground; and 14 metres Hazard Management Area (e) If a tank can be located so it is shielded in all directions in compliance with Building Section 3.5 of AS 3959-2009, the tank may be constructed of any material provided that the lowest 400 mm of the tank exterior is protected by: Bushfire Hazard. (i) metal; (ii) non-combustible material; or Building Specifications to (iii) fibre-cement a minimum of 6 mm thickness. C) Fittings and pipework associated with a fire fighting water point for a static 16 metres BAL-12.5 water supply must: (a) Have a minimum nominal internal diameter of 50mm; (2) Be fitted with a valve with a minimum nominal internal diameter of 50mm; of AS3959-2018 (b) Be fitted with a valve with a minimum nominal internal diameter of 50mm; (c) Be metal or lagged by non-combustible materials if above ground; (d) Where buried, have a minimum depth of 300mm (compliant with AS/NZS Hazard Management Area 3500.1-2003 Clause 5.23); (e) Provide a DIN or NEN standard forged Storz 65 mm coupling fitted with a Is to be managed in a minimum fuel condition. This means there is suction washer for connection to fire fighting equipment; insufficient fuel available to significantly increase the severity of (f) Ensure the coupling is accessible and available for connection at all times; the bushfire attack. (g) Ensure the coupling is fitted with a blank cap and securing chain (minimum 14 metres 220 mm length); Guidance (h) Ensure underground tanks have either an opening at the top of not less than Title Boundary •Hazard management area to be maintained in a minimum fuel 250 mm diameter or a coupling compliant with this Table; and condition. Locate fire hazards such as wood piles, rubbish heaps (i) Where a remote offtake is installed, ensure the offtake is in a position that is: and stored fuels away from habitable buildings. (i) Visible; (ii) Accessible to allow connection by fire fighting equipment, •The area directly adjacent to the building has a significant amount (iii) At a working height of 450 – 600mm above ground level; and 16 metres of flammable material removed such that there is little to no (iv) Protected from possible damage, including damage by vehicles. material available to burn around the building; D) Signage for static water connections •Includes non flammable areas such as paths, driveways, short The fire fighting water point for a static water supply must be identified by a cropped lawns; sign permanently fixed to the exterior of the assembly in a visible location. Establishing orchards, vegetable gardens, dams or waste water The sign must comply with the Tasmania Fire Service Water Supply • Signage Guideline published by the Tasmania Fire Service effluent disposal areas on the fire prone side of the building where E) Hardstand practical; A hardstand area for fire appliances must be provided: •Create wind breaks and radiation shields such as non (a) No more than three metres from the fire fighting water point, measured as a hose lay (including the minimum combustible fences and low flammability hedges; water level in dams, swimming pools and the like); (b) No closer than six •Create and maintain vertical as well as horizontal separation metres from the building area to be protected; between ground fuels and tree canopies by pruning; (c) With a minimum width of three metres constructed to the same standard It is not necessary to remove all vegetation from the defendable as the carriageway; and 14 metres • (d) Connected to the property access by a carriageway equivalent to the space, trees can provide protection from wind borne embers and standard of the property access. radiant heat under some circumstances.

Hazard Management Area Requirements Hazard management areas for alterations or additions must comply with Bushfire Hazard. Certification No. GES00017 table 4.4 of the Determination, Director of Building Control – Requirements for Building in Bushfire-Prone Areas, version 2.1 29th August 2017. Specifically A new building must: (a) Be located on the lot so as to be provided with a HMA which: (i) Has the separation distances required for the BAL assessed for the construction of the existing building; or Mark Van den Berg (ii) In the case of a building without an existing BAL assessment, is no Acc. No. BFP-108 smaller than the separation distances required for BAL 29; and (b) Have an HMA established in accordance with a certified bushfire hazard Scope 1, 2, 3A, 3B, 3C. management plan.

Phillip Lighton Architects C.T.: 244058/1 Date: 18/09/2019 Bushfire Hazard Management Plan: 'Great Lake Hotel' 3096 Drawing Number: Sheet 1 of 1 Do not scale from these drawings. PID: 7148876 Dimensions to take precedence 49 Sandy Bay Road Malborough Road, Miena. 18th September 2019. GES00017v1.0 1.0 Prepared by: over scale. Hobart TAS 7004 Bushfire Hazard Report: 'Great Lake Hotel' 3096 Malborough Road, page scale: A3 MvdB Miena. 18th September 2019. GES00017v1.0

CERTIFICATE OF QUALIFIED PERSON – ASSESSABLE Section 321 ITEM

To: Phillip Lighton Architects Owner /Agent

49 Sandy Bay Road Address Form 55 Hobart TAS 7004 Suburb/postcode

Qualified person details:

Qualified person: Mark Van den Berg

Address: 29 Kirksway Place Phone No: 03 6223 1839

Battery Point TAS 7004 Fax No:

Licence No: Email address: [email protected]

Qualifications and (description from Column 3 of the Insurance details: Director's Determination - Certificates Accredited to report on bushfire by Qualified Persons for Assessable hazards under Part IVA of the Fire Items Service Act. BFP-108 scope 1, 2, 3a, 3b, 3c. Sterling Insurance PI policy No. 17080170

Speciality area of Analysis of bushfire hazards in (description from Column 4 of the expertise: Director's Determination - Certificates bushfire prone areas by Qualified Persons for Assessable Items)

Details of work:

Address: ‘Great Lake Hotel’ 3096 Malborough Lot No: 1 Road

Miena TAS 7030 Certificate of title No: 244058

The assessable Alterations or additions to buildings in a (description of the assessable item being item related to certified) bushfire prone area. Assessable item includes – this certificate: - a material; - a design - a form of construction - a document - testing of a component, building system or plumbing system - an inspection, or assessment, performed

Certificate details:

Certificate type: Bushfire Hazard (description from Column 1 of Schedule 1 of the Director's Determination - Certificates by Qualified Persons for Assessable Items n)

This certificate is in relation to the above assessable item, at any stage, as part of - (tick one) building work, plumbing work or plumbing installation or demolition work: X

Director of Building Control – Date Approved 1 July 2017 Building Act 2016 - Approved Form No. 55 or a building, temporary structure or plumbing installation: In issuing this certificate the following matters are relevant – Documents: Bushfire Hazard Report ‘Great Lake Hotel’ 3096 Malborough Road, Miena. 18th September 2019. GES00017v1.0 Bushfire Hazard Management Plan ‘Great Lake Hotel’ 3096 Malborough Road, Miena. 18th September 2019. GES00017v1.0 And Form 55 Relevant calculations: Not Applicable.

References: Determination, Director of Building Control Requirements for Building in Bushfire-Prone Areas, version 2.1 29th August 2017. Consumer, Building and Occupational Services, Department of Justice, Tasmania. Building Amendment (Bushfire-Prone Areas) Regulations 2014 Standards Australia 2018, Construction of buildings in bushfire prone areas, Standards Australia, Sydney.

Substance of Certificate: (what it is that is being certified) The Bushfire Attack Level for the proposed lot is BAL-12.5. All specifications of the bushfire hazard management plan and report to be implemented for compliance.

Scope and/or Limitations Scope: This report was commissioned to identify the Bushfire Attack Level for the existing property. Limitations: The inspection has been undertaken and report provided on the understanding that;-1. The report only deals with the potential bushfire risk all other statutory assessments are outside the scope of this report. 2. The report only identifies the size, volume and status of vegetation at the time the site inspection was undertaken and cannot be relied upon for any future development. 3. Impacts of future development and vegetation growth have not been considered.

I certify the matters described in this certificate.

Signed: Certificate No: Date: Qualified person: GES00017 18/09/2019

Director of Building Control – Date Approved 1 July 2017 Building Act 2016 - Approved Form No. 55 ONSITE WASTEWATER ASSESSMENT Great Lake Hotel 3096 Marlborough Road Miena September 2019

Disclaimer: The author does not warrant the information contained in this document is free from errors or omissions. The author shall not in any way be liable for any loss, damage or injury suffered by the User consequent upon, or incidental to, the existence of errors in the information.

Geo-Environmental Solutions P/L 29 Kirksway Place, Battery Point 7004. Ph 6223 1839 Geo-Environmental Solutions Pty Ltd – Site Assessment 3096 Marlborough Road

Introduction

Client: Johns Group Tasmania Date of inspection: 17/4/2019 Location: Great Lake Hotel - 3096 Marlborough Road, Miena 39Land description: Approx. 2.9ha Building type: Existing buildings Investigation: GeoProbe 540UD Inspected by: JP Cumming B.Agr.Sc (hons) PhD CPSS GAICD and G. McDonald

Background information

Map: Mineral Resources Tasmania SE Tasmania 1:250000 Rock type: Jurassic Dolerite Soil depth: Approx. 1.80m+. Planning overlays: None identified in wastewater area Local meteorology: Annual rainfall approx. 800mm Local services: Tank water and on-site wastewater required

Site conditions

Slope and aspect: Approx. 4% slope to the East Site drainage: Moderate to imperfect drainage Vegetation: Mixed bush species Weather conditions: Cloudy, approx. <10mm of rain received in preceding 7 days. Ground surface: Slightly moist surface conditions, very rocky

Investigation

A number of auger holes were completed to identify the distribution of, and variation in soil materials onsite. A representative auger hole drilled at the approximate location indicated on the site plan was chosen for testing and classification according to AS1547-2012 (see profile summary).

2

Geo-Environmental Solutions Pty Ltd – Site Assessment 3096 Marlborough Road

Profile Summary

Hole 1 Horizon Description Depth (m)

0.00 – 0.25 A1 Dark Reddish Brown Clayey SAND (SC), peaty loam, weak polyhedral structure, slightly moist, loose consistency, abundant roots, ~15% clay, rocks and cobbles, gradual boundary to 0.25 – 1.8+ B1 Brown and Strong Brown Sandy Gravelly CLAY (CL), strong sub- angular blocky structure, moist, stiff consistency, medium plasticity, common rocks and cobbles, lower boundary undefined

Soil Profile Notes The soils onsite consist of clayey sands overlying clay loam subsoils which are developing on a combination of dolerite colluvium and fractured dolerite bedrock. The significant amount of gravels throughout the profile will improve soil permeability for onsite wastewater disposal.

Wastewater Classification & Recommendations

According to AS1547-2012 (on-site waste-water management) the natural soil is classified as Clay Loam (Category 4) with a Design Irrigation Rate (DIR) of 3.5mm/day.

The proposal is to upgrade the wastewater system of the hotel and restaurant and decommission the existing lagoon system. The hotel and restaurant will be serviced by a commercial sized AWTS unit and a grease trap connected to the kitchen.

Accommodation units The existing 15x one bedroom accommodation units each have a calculated maximum wastewater loading of 240L/day. This is based on tank water supply and a maximum occupancy of 2 people per unit (120L/day/person). For further detail please see table 1.

Restaurant and Cafe The proposed restaurant will have a peak wastewater loading of 1000L/day. This based on a maximum of 100 patrons/day for the restaurant at 10L/person/day. For further detail please see table 1.

3

Geo-Environmental Solutions Pty Ltd – Site Assessment 3096 Marlborough Road

Managers residence The existing dwelling has a calculated maximum wastewater loading of 480L/day. This is based on tank water supply and a maximum occupancy of 4 people (120L/ person/day) For further detail please see table 1.

Table. 1 Wastewater and BOD loadings for accommodation units, restaurant and managers residence

People/day Loading Total loading BOD BOD Total L/person/day (L/unit/day) (grams/person/ (grams/day) day) Units 30 120 3600 80 2400

Restaurant 100 10 1000 10 1000

Managers 4 120 480 80 320 residence Total 134 5080 3070

Given a total wastewater loading of 5080L/day, and a DIR of 3.5mm/day, then 1400m2 of surface irrigation into the native bush is required to accommodate the expected flows for the accommodation units, restaurant and managers residence. Due to the low slope angle a cut- off diversion drain will not be required. The area excluded from traffic or any future building works and a 100% reserve area should be set aside for future wastewater requirements. For further detail please refer to the attached plan and Trench summary reports.

The following setback distances are required to comply with the Building Act 2016:

Upslope or level buildings: 3m

Downslope buildings: 2.5m

Upslope or level boundaries: 1.5m

Downslope boundaries: 2.5m

Downslope surface water: 100m

Compliance with Building Act 2016 Guidelines for On-site Wastewater Management Systems is outlined in the attached table.

4

Geo-Environmental Solutions Pty Ltd – Site Assessment 3096 Marlborough Road

It is recommended GES be notified of any major variation to the wastewater loading as predicted in this report.

Dr John Paul Cumming B.Agr.Sc (hons) PhD CPSS GAICD Environmental and Engineering Soil Scientist

5

Geo-Environmental Solutions Pty Ltd – Site Assessment 3096 Marlborough Road

GES P/L Land suitability and system sizing for on-site wastewater management

Assessment Report Site assessment for on-site waste water disposal

Assessment for Johns Group Tasmania Assess. Date 17-Sep-19 Ref. No. Assessed site(s) 19 Jones Road Miena Site(s) inspected 17-Apr-19 Local authority Central Highlands Council Assessed by John Paul Cumming

This report summarises wastewater volumes, climatic inputs for the site, soil characteristics and sustem sizing and design issues. Site Capability and Environmental sensitivity issues are reported separately, where 'Alert' columns flag factors w ith high (A) or very high (AA) limitations w hich probably require special consideration for system design(s). Blank spaces on this page indicateB.Agr.Sc(hons)data have not been enteredPhD into TRENCH.

Wastewater Characteristics Wastewater volume (L/day) used for this assessment = 5,080 (using a method independent of the no. of bedrooms) Septic tank wastewater volume (L/day) = 1,694 Sullage volume (L/day) = 3,386 Total nitrogen (kg/year) generated by wastewater = 45.7 Total phosphorus (kg/year) generated by wastewater = 19.2 Climatic assumptions for site (Evapotranspiration calculated using the crop factor method) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Mean rainfall (mm) 51 56 63 66 75 72 84 86 76 61 63 66 Adopted rainfall (R, mm) 51 56 63 66 75 72 84 86 76 61 63 66 Retained rain (Rr, mm) 46 50 57 59 68 65 76 77 68 55 57 59 Max. daily temp. (deg. C) Evapotrans (ET, mm) 130 110 91 63 42 29 32 42 63 84 105 126 Evapotr. less rain (mm) 84 60 34 4 -26 -35 -44 -35 -5 29 48 67 Annual evapotranspiration less retained rain (mm) = 180 Soil characterisitics Texture = Clay Loam Category = 4 Thick. (m) = 1.8 Adopted permeability (m/day) = 0.5 Adopted LTAR (L/sq m/day) = 4 Min depth (m) to water = 50 Proposed disposal and treatment methods Proportion of wastewater to be retained on site: All wastewater will be disposed of on the site The preferred method of on-site primary treatment: In a package treatment plant The preferred method of on-site secondary treatment: Above-ground The preferred type of in-ground secondary treatment: None The preferred type of above-ground secondary treatment: Surface irrigation Site modifications or specific designs: Not needed Suggested dimensions for on-site secondary treatment system Total length (m) = 295 Width (m) = 5 Depth (m) = 0.2 Total disposal area (sq m) required = 1400 comprising a Primary Area (sq m) of: 1,400 and a Secondary (backup) Area (sq m) of: Sufficient area is available on site To enter comments, click on the line below 'Comments'. (This yellow-shaded box and the buttons on this page will not be printed.)

Comments The calculated LTAR for the category 4 soil present is 3.5mm/day with a minimum irrigation area of 1400m2. Therefore the system will have the capacity to cope with the expected climatic and laoding conditions.

6

Geo-Environmental Solutions Pty Ltd – Site Assessment 3096 Marlborough Road

GES P/L Land suitability and system sizing for on-site wastewater management

Site Capability Report Site assessment for on-site waste water disposal

Assessment for Johns Group Tasmania Assess. Date 17-Sep-19 Ref. No. Assessed site(s) 19 Jones Road Miena Site(s) inspected 17-Apr-19 Local authority Central Highlands Council Assessed by John Paul Cumming

This report summarises data relating to the physical capability of the assessed site(s) to accept wastewater. Environmental sensitivity and system design issues are reported separately. The 'Alert' column flags factors w ith high (A) or very high (AA) site limitations w hich probably require special consideration in site acceptability or for systemdesign(s). Blank spaces indicate data have not beenB.Agr.Sc(hons)entered into TRENCH .PhD

Limitation

Expected design area sq m 2,000 V. high Low Density of disposal systems /sq km 10 Mod. Very low Slope angle degrees 2 High Very low Slope form Straight simple High Low Surface drainage Imperfect High Moderate Flood potential Site floods <1:100 yrs High Very low Heavy rain events Infrequent High Moderate Aspect (Southern hemi.) Faces E or W V. high Moderate Frequency of strong winds Common High Low AA Wastewater volume L/day 5,080 High Very high SAR of septic tank effluent 1.4 High Low SAR of sullage 2.5 High Moderate Soil thickness m 1.8 V. high Very low Depth to bedrock m 2.0 V. high Low A Surface rock outcrop % 5 V. high High Cobbles in soil % 5 V. high Low Soil pH 5.5 High Low Soil bulk density gm/cub. cm 1.5 High Low Soil dispersion Emerson No. 7 V. high Very low Adopted permeability m/day 0.5 Mod. Moderate A Long Term Accept. Rate L/day/sq m 4 High High

To enter comments, click on the line below 'Comments' . (This yellow-shaded box and the buttons on this page will not be printed.)

Comments The sandy clay loam soils on site have a good capacity to accept wastewater flows, with a moderate CEC for retention of nutrients.

7

Geo-Environmental Solutions Pty Ltd – Site Assessment 3096 Marlborough Road

GES P/L Land suitability and system sizing for on-site wastewater management

Environmental Sensitivity Report Site assessment for on-site waste water disposal

Assessment for Johns Group Tasmania Assess. Date 17-Sep-19 Ref. No. Assessed site(s) 19 Jones Road Miena Site(s) inspected 17-Apr-19 Local authority Central Highlands Council Assessed by John Paul Cumming

This report summarises data relating to the environmental sensitivity of the assessed site(s) in relation to applied w astewater. Physical capability and system design issues are reported separately. The 'Alert' column flags factors with high (A) or very high (AA) limitations w hich probably require special consideration in site acceptability or for system design(s). Blank spaces indicate dataB.Agr.Sc(hons)have not been entered PhDinto TRENCH.

Limitation

Cation exchange capacity mmol/100g 75 High Moderate Phos. adsorp. capacity kg/cub m 0.6 High Moderate Annual rainfall excess mm -180 High Very low Min. depth to water table m 50 High Very low AA Annual nutrient load kg 64.9 High Very high G'water environ. value Agric non-sensit V. high Low Min. separation dist. required m 5 High Very low Risk to adjacent bores Very low V. high Very low A Surf. water env. value Recreational V. high High Dist. to nearest surface water m 130 V. high Moderate A Dist. to nearest other feature m 20 V. high High Risk of slope instability Low V. high Low A Distance to landslip m 50 V. high High

To enter comments, click on the line below 'Comments'. (This yellow-shaded box and the buttons on this page will not be printed.)

Comments The clay soils on site have a good CEC and P absorption capacity, and given the land area available and use of vegetation nutrient retention should notbe an issue.

8

Demonstration of wastewater system compliance to Building Act 2016 Guidelines for On-site Wastewater Disposal

Acceptable Solutions Performance Criteria Compliance

A1 P1 Complies with A1 (b) (i) Horizontal separation distance from a building to a a) The land application area is located so that Land application area will be located with a land application area must comply with one of the minimum separation distance of 3m from an following: (i) the risk of wastewater reducing the upslope or level building. bearing capacity of a building’s a) be no less than 6m; or foundations is acceptably low.; and b) be no less than: (ii) is setback a sufficient distance from a

(i) 3m from an upslope building or level downslope excavation around or building; under a building to prevent (ii) If primary treated effluent to be no less than inadequately treated wastewater 4m plus 1m for every degree of average seeping out of that excavation gradient from a downslope building; (iii) If secondary treated effluent and subsurface application, no less than 2m plus 0.25m for every degree of average gradient from a downslope building. A2 P2 Complies with A2 (a) Horizontal separation distance from downslope Horizontal separation distance from downslope Land application area located > 100m from surface water to a land application area must comply surface water to a land application area must downslope surface water with (a) or (b) comply with all of the following:

(a) be no less than 100m; or a) Setbacks must be consistent with AS/NZS 1547 Appendix R; (b) be no less than the following: b) A risk assessment in accordance with (i) if primary treated effluent 15m plus 7m for Appendix A of AS/NZS 1547 has been every degree of average gradient to completed that demonstrates that the risk is downslope surface water; or acceptable. (ii) if secondary treated effluent and subsurface application, 15m plus 2m for every degree of average gradient to down slope surface water. A3 P3 Horizontal separation distance from a property Horizontal separation distance from a property Complies with A3 (b) (i) boundary to a land application area must comply with boundary to a land application area must comply Land application area will be located with a either of the following: with all of the following: minimum separation distance of 1.5m from an upslope or level property boundary (a) be no less than 40m from a property boundary; (a) Setback must be consistent with AS/NZS or 1547 Appendix R; and Complies with A3 (b) (iii) Land application area will be located with a (b) be no less than: (b) A risk assessment in accordance with minimum separation distance of 2.5m of Appendix A of AS/NZS 1547 has been downslope property boundary (i) 1.5m from an upslope or level property completed that demonstrates that the risk is boundary; and acceptable.

(ii) If primary treated effluent 2m for every degree of average gradient from a downslope property boundary; or

(iii) If secondary treated effluent and subsurface application, 1.5m plus 1m for every degree of average gradient from a downslope property boundary. A4 P4 Complies with A4 Horizontal separation distance from a downslope Horizontal separation distance from a downslope No bore or well identified within 50m bore, well or similar water supply to a land bore, well or similar water supply to a land application area must be no less than 50m and not be application area must comply with all of the within the zone of influence of the bore whether up or following: down gradient. (a) Setback must be consistent with AS/NZS 1547 Appendix R; and

(b) A risk assessment completed in accordance with Appendix A of AS/NZS 1547 demonstrates that the risk is acceptable A5 P5 Complies with A5 (b) Vertical separation distance between groundwater Vertical separation distance between and a land application area must be no less than: groundwater and a land application area must No groundwater encountered comply with the following: (a) 1.5m if primary treated effluent; or (a) Setback must be consistent with AS/NZS (b) 0.6m if secondary treated effluent 1547 Appendix R; and

(b) A risk assessment completed in accordance with Appendix A of AS/NZS 1547 that demonstrates that the risk is acceptable A6 P6 Complies with A6 (b) Vertical separation distance between a limiting layer Vertical setback must be consistent with and a land application area must be no less than: AS/NZS1547 Appendix R. No limiting layer identified (a) 1.5m if primary treated effluent; or

(b) 0.5m if secondary treated effluent

A7 P7 nil A wastewater treatment unit must be located a Complies sufficient distance from buildings or neighbouring properties so that emissions (odour, noise or aerosols) from the unit do not create an environmental nuisance to the residents of those properties

AS1547:2012 – Loading Certificate – AWTS Design

This loading certificate sets out the design criteria and the limitations associated with use of the system.

Site Address: Great Lake Hotel – 3096 Marlborough Road, Miena

System Capacity: 5080L/day

Summary of Design Criteria

DIR: 3.5mm/day.

Irrigation area: 1400m2

Reserve area location /use: assigned – more than 100% available

Water saving features fitted: Standard fixtures

Signage: Suitable warning signs to be displayed around the disposal area indicating that reclaimed water is being used i.e. “Recycled Water, Avoid Contact, Do Not Drink”

Allowable variation from design flows: 1 event @ 200% daily loading per quarter

Typical loading change consequences: Expected to be minimal due to use of AWTS and large land area

Overloading consequences: Continued overloading may cause hydraulic failure of the irrigation area and require upgrading/extension of the area. Risk considered acceptable due to monitoring through quarterly maintenance reports.

Underloading consequences: Lower than expected flows will have minimal consequences on system operation unless the house has long periods of non occupation. Under such circumstances additional maintenance of the system may be required. Long term under loading of the system may also result in vegetation die off in the irrigation areas and additional watering may be required. Risk considered acceptable due to monitoring through quarterly maintenance reports.

Lack of maintenance / monitoring consequences: Issues of underloading/overloading and condition of the irrigation area require monitoring and maintenance, if not completed system failure may result in unacceptable health and environmental risks. Monitoring and regulation by the permit authority required to ensure compliance.

Other considerations: Owners/occupiers must be made aware of the operational requirements and limitations of the system by the installer/maintenance contractor.

Section 94 Section 106 CERTIFICATE OF THE RESPONSIBLE DESIGNER Section 129 Section 155

To: Johns Group Tasmania Owner name

C/- Great Lake Hotel – 3096 Marlborough Rd Address Form 35 Miena 7030 Suburb/postcode

Designer details:

Name: Category: Bld. Srvcs. Dsgnr. - John-Paul Cumming Hydraulic

Business name: Geo-Environmental Solutions Phone No: 03 6223 1839

Business 29 Kirksway Place address:

Battery Point 7004 Fax No: N/A

Licence No: CC774A Email address: [email protected]

Details of the proposed work:

Owner/Applicant Johns Group Tasmania Designer’s project 2019/19 reference No.

Address: 3096 Marlborough Rd Lot No: 1

Miena 7030

Type of work: Building work Plumbing work X (X all applicable)

Description of work: On-site wastewater management system - design (new building / alteration / addition / repair / removal / re-erection water / sewerage / stormwater / on-site wastewater management system / backflow prevention / other)

Description of the Design Work (Scope, limitations or exclusions): (X all applicable certificates) Certificate Type: Certificate Responsible Practitioner  Building design Architect or Building Designer  Structural design Engineer or Civil Designer  Fire Safety design Fire Engineer  Civil design Civil Engineer or Civil Designer  Hydraulic design Building Services Designer  Fire service design Building Services Designer  Electrical design Building Services Designer  Mechanical design Building Service Designer  Plumbing design Plumber-Certifier; Architect, Building Designer or Engineer  Other (specify)

Deemed-to-Satisfy: ☒ Performance Solution: ☐ (X the appropriate box) Other details:

AWTS and irrigation

Design documents provided:

Director of Building Control - date approved: 2 August 2017 Building Act 2016 - Approved Form No 35 The following documents are provided with this Certificate – Document description: Drawing numbers: Prepared by: Geo-Environmental Solutions Date: Sep-19

Schedules: Prepared by: Date:

Specifications: Prepared by: Geo-Environmental Solutions Date: Sep-19

Computations: Prepared by: Date:

Performance solution proposals: Prepared by: Date:

Test reports: Prepared by: Geo-Environmental Solutions Date: Sep-19

Standards, codes or guidelines relied on in design process: AS1547-2012 On-site domestic wastewater management.

AS3500 (Parts 0-5)-2013 Plumbing and drainage set.

Any other relevant documentation:

Onsite Wastewater Assessment – 3096 Marlborough Rd, Miena – Sept 19 - GES

Attribution as designer: I John-Paul Cumming, am responsible for the design of that part of the work as described in this certificate; The documentation relating to the design includes sufficient information for the assessment of the work in accordance with the Building Act 2016 and sufficient detail for the builder or plumber to carry out the work in accordance with the documents and the Act; This certificate confirms compliance and is evidence of suitability of this design with the requirements of the National Construction Code.

Name: (print) Signed Date Designer: John-Paul Cumming 17/09/2019

Licence No: CC774A

Director of Building Control - date approved: 2 August 2017 Building Act 2016 - Approved Form No 35 Assessment of Certifiable Works: (TasWater)

Note: single residential dwellings and outbuildings on a lot with an existing sewer connection are not considered to increase demand and are not certifiable. If you cannot check ALL of these boxes, LEAVE THIS SECTION BLANK. TasWater must then be contacted to determine if the proposed works are Certifiable Works. I confirm that the proposed works are not Certifiable Works, in accordance with the Guidelines for TasWater CCW Assessments, by virtue that all of the following are satisfied:

X The works will not increase the demand for water supplied by TasWater

X The works will not increase or decrease the amount of sewage or toxins that is to be removed by, or discharged into, TasWater’s sewerage infrastructure

X The works will not require a new connection, or a modification to an existing connection, to be made to TasWater’s infrastructure

X The works will not damage or interfere with TasWater’s works

X The works will not adversely affect TasWater’s operations

X The work are not within 2m of TasWater’s infrastructure and are outside any TasWater easement

X I have checked the LISTMap to confirm the location of TasWater infrastructure

X If the property is connected to TasWater’s water system, a water meter is in place, or has been applied for to TasWater.

Certification:

I ...... John-Paul Cumming...... being responsible for the proposed work, am satisfied that the works described above are not Certifiable Works, as defined within the Water and Sewerage Industry Act 2008, that I have answered the above questions with all due diligence and have read and understood the Guidelines for TasWater CCW Assessments. Note: the Guidelines for TasWater Certification of Certifiable Works Assessments are available at: www.taswater.com.au

Name: (print) Signed Date Designer: John-Paul Cumming 17/09/2019

Director of Building Control - date approved: 2 August 2017 Building Act 2016 - Approved Form No 35 THIS DRAWING MUST ONLY BE DISTRIBUTED IN FULL COLOUR. ALDANMARK CONSULTING ENGINEERS ACCEPTS NO LIABILITY ARISING FROM FAILURE TO

COMPLY WITH THIS REQUIREMENT. 1056.00

M A R L B O R O U G H H I G H W A Y 1057.00

VIKING P9BG 250 LITRE THIN SKIN GREASE RETAIN EXISTING DN300

ARRESTOR WITH CHECKER PLATE COVER . CULVERT 1058.00 TOP OF GREASE ARRESTOR TO BE FINISHED 150mm ABOVE FINISHED GROUND LEVEL AND CONNECTED TO EXISTING SEWER LINE.

DECOMMISSIONED SETTLEMENT PONDS TO REFER 'H' SERIES DRAWINGS FOR INTERNAL BE BACKFILLED TO AS PER AS 3798 AND DRAINAGE AND HYDRAULICS

ENGINEERS APPROVAL 1056.00 RURAL ENDWALL TO SUIT 1055.00 DN150 STORMWATER LINE

1057.00 I.O. TO SURFACE RETAIN EXISTING SEWER LINE

PROVIDE NEW 3KL PROVIDE NEW DN150 UPVC SN8 OVERFLOW RELIEF ABOVE-GROUND GREASE TRAP FROM PROPOSED 20KL BORE WATER STORAGE FOR HOTEL OPERATIONS AND TANK TO EXISTING ROADSIDE TABLE DRAIN 1ST FLOOR RESIDENCE

AWTS CONNECTED TO IRRIGATION / ABORBTION BEDS

NEW AWTS SYSTEM AS PER GES REPORT

20KL BORE WATER HOLDING TANK WITH PUMPS AND FILTERS

1056.00 CONNECTED TO EXISTING BORE AS PER GES REPORT

1055.00 EXISTING SEWER CONNECTION TO BE LOCATED

AND PLUMBED TO NEW AWTS SYSTEM 1055.00 AWTS IRRIGATION AREA SHOWN RED DASHED (1,500m2)

Hole 1 PROVIDE NEW DN50 (ID) BOREWATER 1052.00 SUPPLY TO 20KL HOLDING TANK. PROVIDE DN50 CONDUIT IN SAME TRENCH WITH DRAW WIRE FOR BORE

LEGEND 1053.00 PUMP CONTROL LINE.

NEW STORMWATER Wastewater system: 1054.00 NEW SEWER NEW BORE WATER AWTS unit

NEW WATER 1055.00 AWTS DISPERSAL BOUNDARY Subsurface Irrigation area 1400m2

EXISTING STORMWATER CULVERT 1056.00 2.5 m EXISTING STORMWATER

EXISTING SEWER Surface diversion drain EXISTING SEWER RISING MAIN 1057.00 EXISTING BORE WATER Min 3m from upslope or level buildings EXISTING WATER Min 1.5m from upslope and side boundaries Surface irrigation into EXISTING FENCE Min 2.5m from downslope boundary native bush 1400m2 Min 100m from downslope surface water

Refer to GES report HALF SCALE PRINT

BEWARE OF UNDERGROUND SERVICES 17/9/2019 THE LOCATION OF UNDER GROUND SERVICES ARE THESE DRAWINGS MUST BE APPROVED BY DETAIL PLAN APPROXIMATE ONLY AND THEIR EXACT LOCATION SHOULD BE PROVEN ON SITE BY THE RELEVANT AUTHORITIES. NO COUNCIL PRIOR TO CONSTRUCTION SCALE 1:500 (A1) GUARANTEE IS GIVEN THAT ALL SERVICES ARE SHOWN.

CLIENT: SHEET: DRAWN: DESIGNED: VERIFIED: DATE: JOHNS GROUP TASMANIA PROPOSED HYDRAULIC REFURBISHMENT PLAN MB MB MG 13/09/2019 Lower Ground SCALE: SIZE: TOTAL ADDRESS: PROJECT: 1:500 A1 SHEETS: 4 199 Macquarie Street MIENA VILLAGE EARLY WORKS Hobart TAS 7000 3096 MARLBOROUGH HIGHWAY, PROJECT No. SHEET No. REV No. 03 6234 8666 0 PLUMBING APPROVAL 13/09/2019 MIENA, TAS 7030 ISSUE: [email protected] REV. DESCRIPTION DATE REV. DESCRIPTION DATE www.aldanmark.com.au PLUMBING APPROVAL 19E66-5 C1.02 0

Figure 1 - AWTS

AWTS –surface irrigation

To be used in conjunction with site evaluation report for construction of irrigation areas for use with aerated wastewater treatment systems (AWTS). On dispersive soils gypsum should be added to tilled natural soil at 1Kg/5m2. For irrigation areas larger than 500m2 the irrigation area should be split into multiples of at least 100m2 with flow automatically switched between each area by a k-rain valve. On steep sites pressure check valves should be utilized on each sprinkler row to ensure even distribution.

Irrigation Area Cross Section

Irrigation line (25-32mm poly) with wobbler sprinklers at 5m centers

Natural leaf litter)

Soil depth Natural Soil as per description

• The irrigation lines should be scratched into the ground surface and/or covered with gum mulch to added as required • The area should have a minimum of 1 native plant per 5m2, and supplementary planting maybe required

Irrigation Area Plan View Flush return to WWTS or trench

Manual or automatic control valve

25-32mm line with wobbler sprinklers at approx 5m longitudinal spacing

Manual or automatic control valve

25-32 mm inlet line from WWTS

Design specifications: 1. Manufacturer’s recommendations for spacing of irrigation lines and sprinklers should be followed (i.e. wobbler® 5.56 mm sprinklers) with a longitudinal spacing of approx 5m centers. 2. Typical sprinkler flow rates are 0.3-0.8L/sec per 5.56 mm emitter dependant pressure. 3. Sprinklers to be placed on secure staked risers with sufficient height to clear undergrowth such as grass and sedges 4. A flush line must be installed at the lowest point/bottom of the irrigation area with a return valve for flushing back into the treatment chamber of the system (not into the primary chamber as it may affect the performance of the microbial community) or to a dedicated absorption trench. 5. The minimum irrigation pumping capacity should be a 12m head or 120 kpa measured at the highest point of the irrigation area. 6. Pressure check valves to be used on steep sites on each sprinkler line to ensure even distribution

Great Lake General Store

PRELIMINARY SITE INVESTIGATION Great Lakes Hotel, 3096 Marlborough Highway, Miena JUNE 2019 Report for The Johns Group P/L

Geo-Environmental Solutions P/L 29 Kirksway Place, Battery Point, 7004. Ph 6223 1839 E: [email protected] Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

DOCUMENT CONTROL

Title Version Date Author Reviewed By

Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Version 1 5 June 2019 Sarah Joyce JP Cumming Highway, Miena.

Geo Environmental Solutions – GES Page i Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

EXECUTIVE SUMMARY This report presents the findings from Preliminary Site Investigation (PSI) undertaken by Geo- Environmental Solutions Pty. Ltd. (GES) at Great Lakes Hotel, 3096 Marlborough Highway, Miena - hereby referred to as ‘The Site’. GES was engaged by The Johns Group P/L to conduct this investigation. This report is a requirement for the potential sale of land is it has been prepared by a suitably qualified and experience practitioner in accordance with procedures and practices detailed in NEPM (2013) guidelines and key regulations and policies. The objective of the PSI was to determine the following for the potential sale/purchase of land: • Conduct a desktop assessment the suitability of the site for the intended use; • Confirm if contamination is likely and the likely extent of the contamination at the site; • Complete a preliminary assessment of site wastewater infrastructure; • Consider impact on human health and the environment in a conceptual site model (CSM); • Provide recommendations on what measures may need to be put in place to address any potential data gaps and to further assess contamination remediation and/or management (if required). The scope of works of this PSI was to: • Conduct a desktop assessment, site history including WorkSafe Tasmanian Search, Environmental Protection Authority (EPA) Tasmania and The LIST data base search. • Site visit; photographs of site conditions, limited sample collection. • Limited soil testing; one soil sample was collected from the effluent pond wall. The sample was analysed for Total Recoverable Hydrocarbons (TRH), Benzene Toluene Ethylbenzene Xylene Naphthalene (BTEXN), Polynuclear Aromatic Hydrocarbons (PAHs);a suite of 15 Metals plus OC/OP Pesticides. • The analytical results against were compared against NEPM ASC (2013) guidelines as well as other relevant guidelines for assessing hydrocarbon vapour and soil dermal contact risks; and • Present the findings of the site investigation, conduct a risk assessment and develop a conceptual site model (CSM) plus present future investigation recommendations. • Undertake preliminary assessment of site wastewater and bore water supply infrastructure. The following conclusions were made from the desktop assessment: • The site is zoned Local Business on the eastern half of the site and Rural Resource on the western half of the site under the Central Highlands Interim Planning Scheme of 2015 • WorkSafe Tasmania confirmed the following information for the site; it has hosted fuel storage and sales since the mid-1980 and has three underground storage tanks of diesel, unleaded petrol and leaded petrol (super). The site has also held LPG on site for sales and cooking purposes. This investigation is not concerned with the LPG storage as contamination from this is unlikely. • The site is underlain with Jurassic Dolerite. The site is approximately 1060m above sea level. Groundwater is inferred to be directed towards the east to Swan Bay on Great Lake with the same aspect as the surface topography. This is the closest ecological receptor. The edge of the lake is 450m east from the UPSS infrastructure. • The historical aerial photographs confirm the following: There are numerous buildings on site associated with the hotel activities. The two sewage settling ponds have been onsite since the hotel facilities were constructed. There appear to be two informal rubbish dumps on the site. There was a wildfire in that area summer of 2019, as seen in the 2019 aerial photograph. • GES is aware of the following report for the site: Site Services Due Diligence Report for Johns Group Great Lake Hotel Redevelopment by Coordinated Engineering Services (CES). CES confirmed that the site has hosted a commercial shop front and hotel accommodation since 1984. • The Environmental Protection Authority (EPA) Tasmania is aware that the site has three active registered underground petroleum storage systems with a total volume of 40,000L which is considered as a potentially contaminating activity. • There appear to be no monitoring records for the fuel infrastructure, and it also appears that no formal loss monitoring and reporting (SIRA) has been completed; • The shop and refuelling area has no spill containment or loss control in place with only an open stormwater drain present, therefore any surface spills during operations since the 1980’s are likely to have impacted soil and possibly groundwater in the area;

Geo Environmental Solutions – GES Page ii Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

• Conceptual Site Model o As determined in this desktop assessment, areas of potential concern (AOPC) on site relate to the activities relating to fuel storage and sales; including: ▪ Back-up generator operated by the shop – diesel powered unknown but assumed; ▪ UPSS infrastructure adjacent to the shop – diesel, ULP and Super petrol stored in underground tanks plus, 2 bowsers 1 x single electric pump and 1 x duel electric pump; and ▪ Informal rubbish dumps – house-hold waste in two localised areas ▪ The effluent ponds o The following contaminants of potential concern (COPC) associated with underground fuel storage, dispensing infrastructure and other activities have been identified on site: ▪ Total Petroleum/Recoverable Hydrocarbons (TPH/TRH); ▪ Mono Aromatic hydrocarbons: Benzene, Toluene, Ethylbenzene, Xylene (BTEX); ▪ Polycyclic Aromatic Hydrocarbons (PAH) including Benzo(a)pyrene (B(a)p) and ▪ Lead; plus ▪ Heavy Metals and hydrocarbons from informal waste dumps and accumulation in sewerage sludge.

The following conclusions have been made from the assessment of the wastewater and bore water infrastructure: • Np grease trap is installed for the commercial kitchen on site • The two effluent ponds are unlined, in poor condition, with an open outlet to the ground surface • The effluent ponds are considered to be non-compliant with health and environmental standards and will require decommissioning and replacement with a suitable new system as part of any site redevelopment • Soil testing shows the pond walls to have low level heavy metal contamination (level 2 according to EPA IB105) which will require appropriate management • The bore water supply appears to be in a dolerite aquifer with low to moderate yield, and preliminary screening of water samples showed a positive to bacterial contamination • The bore system has inadequate storage, filtration, and treatment • The bore system requires more detailed investigation and testing, and will require upgrading of infrastructure as part of any site redevelopment

GES recommends the following: • An Environmental Site Assessment (ESA) should be completed to understand if the existing UPSS infrastructure has been compromised overtime. This must include invasive soil investigation in the vicinity of the underground storage tanks plus the area surrounding the generator where hydrocarbon containing fuels may have been spilt. Soil surrounding the informal waste dumps should also be tested. The ESA could be completed as part of any development application package for the site. • The bore water system should be testing for yield, plus draw down, and further tested for quality parameters including bacteria to determine if the effluent ponds, surface contamination from animals or other sources are impacting water quality.

Geo Environmental Solutions – GES Page iii Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Table of Contents

DOCUMENT CONTROL I

EXECUTIVE SUMMARY II

ABREVIATIONS VII

1 INTRODUCTION 9

1.1 GENERAL 9 1.2 SITE DETAILS 10 1.3 INVESTIGATION OBJECTIVES 10 1.4 SCOPE OF WORKS 10 1.5 ASSESSMENT TRIGGER 10

2 PRELIMINARY INVESTIGATION - DESKTOP 11

2.1 PLANNING - ZONING 11 2.2 MRT GEOLOGY MAPPING 11 2.3 SITE TOPOGRAPHY, DRAINAGE & HYDROGEOLOGY 11 2.4 HISTORICAL SITE INVESTIGATIONS 13 2.5 HISTORICAL AERIAL PHOTOGRAPHY INTERPRETATION 14 2.6 DANGEROUS GOODS RECORDS (WORKSAFE TASMANIA) 16 2.7 ENVIRONMENTAL PROTECTION AUTHORITY - PROPERTY INFORMATION REQUEST 20 2.8 GROUNDWATER 20 2.8.1 POTENTIAL UP-GRADIENT CONTAMINATION SOURCES 20 2.8.2 DOWNGRADIENT ECOLOGICAL RECEPTORS 20 2.8.3 WATER BORE USERS 20 2.9 FLORA & FAUNA 20

3 PREMIMINARY CONCEPTUAL SITE MODEL 21

3.1.1 AREAS OF POTENTIAL CONCERN 21 3.1.2 CONTAMINANTS OF POTENTIAL CONCERN 21 3.1.3 POTENTIAL RECEPTORS 21

4 FIELD INVESTIGATION FINDINGS 24

4.1 WORKS SUMMARY 24 4.2 SURFACE COVERINGS 24 4.3 SIGNS OF CONTAMINATION 24 4.4 GEOLOGICAL INTERPRETATION 24

5 SOIL ECOLOGICAL IMPACT ASSESSMENT 24

5.1 NEPM ASC (2013) GUIDELINES 24 5.2 FINDINGS 25 5.2.1 ECOLOGICAL SCREENING LEVELS 25 5.2.2 ECOLOGICAL INVESTIGATION LEVELS 25

6 SOIL HUMAN HEALTH DIRECT CONTACT ASSESSMENT 26

Geo Environmental Solutions – GES Page iv Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

6.1 GUIDELINES 26 6.1.1 LAND USE CLASSIFICATION 26 6.1.2 ADOPTED LAND USE CLASSIFICATION 26 6.2 FINDINGS 26 6.2.1 DERMAL CONTACT - PETROLEUM HYDROCARBONS 26 6.2.2 DUST INHALATION & SOIL INGESTION 27

7 SOIL DISPOSAL ASSESSSMENT 29

7.1 GUIDELINES 29 7.2 FINDINGS 29

8 PRELIMINARY ASSESSMENT OF WASTEWATER AND BORE WATER INFRASTURCTURE 31

8.1 WASTEWATER 31 8.2 BORE WATER 32

9 CONCLUSIONS 34

9.1 DESKTOP ASSESSMENT 34 9.2 LIMITED WASTEWATER AND BORE WATER ASSESSMENT FINDINGS 35

10 RECOMMENDATIONS 35

REFERENCES 36

LIMITATIONS STATEMENT 37

APPENDIX 1 GES STAFF 38

APPENDIX 2 SITE PHOTOGRAPHS 39

APPENDIX 3 DANGEROUS GOODS RECORDS 47

APPENDIX 4 EPA RTI 59

APPENDIX 5 GROUNDWATER BORE DATA 61

APPENDIX 6 LABORATORY CHAIN OF CUSTODY 67

APPENDIX 7 LABORATORY SAMPLE RECEIPT NOTIFICATION 68

APPENDIX 8 QUALITY ASSURANCE AND QUALITY CONTROL DOCUMENTATION 71

APPENDIX 9 CERTIFICATE OF ANALYSIS 88

Plates

PLATE 1 2019 HISTORICAL AERIAL PHOTOGRAPH THE SITE (16 MARCH 2019; POST LARGE WILDFIRES) ...... 14 PLATE 2 2019 HISTORICAL AERIAL PHOTOGRAPH THE SITE (16 JANUARY 2016) ...... 15

Geo Environmental Solutions – GES Page v Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

PLATE 3 2008 HISTORICAL AERIAL PHOTOGRAPH THE SITE (28 AUGUST 2006) – CLOSE UP OF HOTEL AREA ...... 15 PLATE 4 2008 HISTORICAL AERIAL PHOTOGRAPH THE SITE (28 AUGUST 2006) ...... 16 PLATE 5 GENERAL STORE – UNDERGROUND TANK LOCATION AND BOWSER (NOTE FUEL STAINING) ...... 23

Figures

FIGURE 1 SITE LOCATION (IMAGE SOURCED FROM THE LIST) ...... 9 FIGURE 2 CURRENT SITE LAYOUT ...... 9 FIGURE 3 COUNCIL PLANNING ZONES (2015) UNDER THE TASMANIAN INTERIM PLANNING SCHEME ...... 11 FIGURE 4 MINERAL RESOURCES TASMANIA 1:25000 SCALE MAPPING (THE LIST)...... 11 FIGURE 5 SURFACE TOPOGRAPHY AND INFERRED GROUNDWATER FLOW ...... 12 FIGURE 6 SITE PLAN SHOWING UPSS INFRASTRUCTURE (OCTOBER 2006) ...... 18 FIGURE 7 SITE PLAN SHOWING UPSS INFRASTRUCTURE (MAY 1990) ...... 19 FIGURE 8 GROUNDWATER BORE LOCATIONS ON SITE ...... 20 FIGURE 9 TASVEG 3.0 MAPPING (THE LIST)...... 21 FIGURE 10 PRELIMINARY CSM ...... 22 FIGURE 11 UPSS INFRASTRUCTURE ...... 23

Tables

TABLE 1 SITE DETAILS ...... 10 TABLE 2 RELEVANT DANGEROUS GOODS RECORDS ...... 17 TABLE 3 SUMMARY OF SITE INVESTIGATION WORK DATES ...... 24 TABLE 4 SUMMARY OF SOIL INVESTIGATION LIMITS CONSIDERED AT THE SITE BASED IN NEPM ASC (2013) ...... 24 TABLE 5 SUMMARY OF SOIL ANALYTICAL RESULTS COMPARED WITH ECOLOGICAL SCREENING LEVEL’S FOR COMMERCIAL / INDUSTRIAL LAND USE ...... 25 TABLE 6 SOIL ANALYTICAL RESULTS COMPARED AGAINST ECOLOGICAL INVESTIGATION LEVELS FOR URBAN RESIDENTIAL/ PUBLIC OPEN SPACES ...... 25 TABLE 7 SUMMARY OF LAND USE SPATIAL AND TEMPORAL SETTING FOR DETERMINING EXPOSURE RISK ...... 26 TABLE 8 SOIL ANALYTICAL RESULTS COMPARED AGAINST CRC CARE GUIDELINES FOR DERMAL CONTACT – BH01-BH04 ...... 26 TABLE 9 SOIL ANALYTICAL RESULTS COMPARED AGAINST NEPM (2013) HEALTH INVESTIGATION LIMIT GUIDELINES – METALS AND PAHS ...... 28 TABLE 10 SOIL ANALYTICAL RESULTS COMPARED AGAINST NEPM (2013) HEALTH INVESTIGATION LIMIT GUIDELINES – OC/OPS ...... 28 TABLE 11 SUMMARY OF IB105 CLASSIFICATION GUIDELINES ...... 29 TABLE 12 SOIL ANALYTICAL RESULTS COMPARED AGAINST IB105 INVESTIGATION LIMITS FOR SOIL DISPOSAL ...... 30

Geo Environmental Solutions – GES Page vi Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

ABREVIATIONS AEC Areas of Environmental Concern AHD Australian Height Datum ALS Analytical Laboratory Services ANZECC Australia and New Zealand Environment and Conservation Council BGS Below Ground Surface BH Borehole BTEX Benzene Toluene Ethylbenzene Xylene CMP Contamination Management Plan COA Certificate of Analysis COC Chain of Custody COPC Contaminant of Potential Concern CRC CARE Corporative Research Centre for Contamination Assessment and Remediation of the Environment CSM Conceptual Site Model DQO Data Quality Objectives EOH End Of Hole EIL Ecological Investigation Levels ESL Ecological Screening Levels EPA Environmental Protection Authority ESA Environmental Site Assessment GDA94 Geocentric Datum of Australia 1994 GES Geo-Environmental Solutions Pty. Ltd. HIL Health Investigation Levels HSL Health Screening Levels IL Investigation Levels LiDAR Light Detection And Ranging LOR Limits of Reporting MCRWBA Minimum Construction Requirements for Water Bores in Australia MDL Mean Detection Limit NATA National Association of Testing Authorities NEPM ASC National Environmental Protection (Assessment of Site Contamination) Measure NHMRC National Health and Medical Research Council NRMMC Natural Resource Management Ministerial Council NL Non Limiting NRMMC Natural Resource Management Ministerial Council PAH Polynuclear Aromatic Hydrocarbons PCP Physico-Chemical Parameters PEV Protected Environmental Values PHC Petroleum Hydrocarbons PID Photo-Ionisation Detector PPA Preferential (PVI) Pathways Assessment Geo Environmental Solutions – GES Page vii Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

PSH Phase Separated Hydrocarbons PVI Petroleum Vapour Intrusion Redox Reduction / Oxidation Potential SCA Site Contamination Assessment SCM Site Contamination Model TPH Total Petroleum Hydrocarbons TRH Total Recoverable Hydrocarbons UPSS Underground Petroleum Storage Systems USCS Unified Soil Classification System WRG Water Resource Group

Geo Environmental Solutions – GES Page viii Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

1 INTRODUCTION

1.1 General

This report presents the findings from Preliminary Site Investigation (PSI) undertaken by Geo- Environmental Solutions Pty. Ltd. (GES) at Great Lakes Hotel, 3096 Marlborough Highway, Miena - hereby referred to as ‘The Site’. GES was engaged by The Johns Group P/L to conduct this investigation. The Site location is presented in Figure 1 and the current site aerial photograph is presented in Figure 2. The Client is proposing to purchase the property. This report has been prepared by a suitably qualified and experience practitioner in accordance with procedures and practices detailed in NEPM (2013) guidelines and key regulations and policies identified in the References section of this document. Personnel engaged in preparing this PSI are listed in Appendix 1 along with their relevant qualifications and years of experience.

Great Lake

The Site

Miena

Figure 1 Site Location (image sourced from the LIST)

Figure 2 Current Site Layout

Geo Environmental Solutions – GES Page 9 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

1.2 Site Details

Site details are presented in Table 1. Table 1 Site Details Site Address 3096 Marlborough Highway, Miena Current Title identification details PID 7148876 Title Reference 21355/1 (western parcel & 244058/1 (eastern parcel with current buildings) Current land use Hotel and General Store Current Ownership (as per current certificates of title; the LIST) Great Lake Hotel P/L Zoning Local Business on the eastern half of the site and Rural Resource on the western half of the site under the Central Highlands Interim Planning Scheme of 2015 Local Council Central Highlands Council Proposed Site Use Continue as Commercial hotel accommodation, camping and amenities. Requirement for current Investigation Proposed sale of land

1.3 Investigation Objectives

The objective of the PSI was to determine the following for the potential sale/purchase of land: • Conduct a desktop assessment the suitability of the site for the intended use; • Confirm if contamination is likely and the extent of the contamination at the site • Consider impact on human health and the environment in a conceptual site model (CSM); • Provide recommendations on what measures may need to be put in place to address any potential data gaps and to further assess contamination remediation and/or management (if required). • Complete a preliminary assessment of site wastewater and bore water infrastructure;

1.4 Scope of Works

The scope of works of this PSI was to: • Conduct a desktop assessment, site history including WorkSafe Tasmanian Search, Environmental Protection Authority (EPA) Tasmania and The LIST data base search. • Site visit; photographs of site conditions, limited sample collection. • Limited soil testing; one soil sample was collected from the pond wall. The sample was analysed for Total Recoverable Hydrocarbons (TRH), Benzene Toluene Ethylbenzene Xylene Naphthalene (BTEXN), Polynuclear Aromatic Hydrocarbons (PAHs);a suite of 15 Metals plys OC/OP Pesticides. The soil sample was sent to a National Association of Testing Authorities (NATA) accredited laboratory to determine the presence/ absence of contamination and at what level; • The analytical results against were compared against NEPM ASC (2013) guidelines as well as other relevant guidelines for assessing hydrocarbon vapour and soil dermal contact risks; and • Present the findings of the site investigation, conduct a risk assessment and develop a conceptual site model (CSM) plus present future investigation recommendations.

1.5 Assessment Trigger

The need for the assessment is a requirement for the potential purchase of Land.

Geo Environmental Solutions – GES Page 10 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

2 PRELIMINARY INVESTIGATION - DESKTOP

2.1 Planning - Zoning

The site is zoned Local Business on the eastern half of the site and Rural Resource on the western half of the site under the Central Highlands Interim Planning Scheme of 2015 (Figure 3) and is surrounded by similar uses plus Utilities.

The Site

Figure 3 Council planning zones (2015) under the Tasmanian Interim Planning Scheme

2.2 MRT Geology Mapping

The geology of the site has been mapped by Mineral Resources Tasmania (Figure 4). The site is inferred to be underlain with Jurassic Dolerite. The surrounding geology comprises of quaternary sediments and basalt to the north.

Tb - Basalt

Qh – undifferentiated Quaternary sediments

Jd - Dolerite and related rocks

Site

Figure 4 Mineral Resources Tasmania 1:25000 Scale Mapping (The LIST).

2.3 Site Topography, Drainage & Hydrogeology

Based on the Hillshade Colour Basemap (2019; the LIST), the site is approximately 1060m above sea level. Groundwater is inferred to be directed towards the east to Swan Bay on Great Lake with the same aspect as the surface topography (Figure 5).

Geo Environmental Solutions – GES Page 11 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

The Site Swan Bay – Great Lake

Figure 5 Surface Topography and Inferred Groundwater Flow

Geo Environmental Solutions – GES Page 12 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

2.4 Historical Site Investigations

GES is aware of one report that was written for the site in May this year: Site Services Due Diligence Report for Johns Group Great Lake Hotel Redevelopment by Coordinated Engineering Services (CES), May 2019. The following items in this report are relevant to this investigation: • The Hotel has no back-up generator or point of connections • The Shop has a back-up generator but owned by the lessee. • LPG used for the kitchen equipment • The report confirms the use of bore water, see below

• The buildings were constructed around 1984 • Image for the shop forecourt with the two bowsers depictured (page 10. of CES, 2019)

Geo Environmental Solutions – GES Page 13 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

2.5 Historical Aerial Photography Interpretation

Historical aerial photographs of the site and surrounding areas were reviewed on Google Earth. The individual aerial photos are presented in Plate 1 (2019) to Plate 4 (2006). In summary, the site has hosted a commercial shop front and hotel accommodation since 1984 (CES, 2019). There are numerous buildings on site associated with the hotel activities. The two sewage settling ponds have been onsite since the hotel facilities were constructed. There appear to be two informal rubbish dumps on the site. There was a wildfire in that area summer of 2019, as seen in the 2019 aerial photograph.

Plate 1 2019 Historical Aerial Photograph the Site (16 March 2019; post large wildfires)

Geo Environmental Solutions – GES Page 14 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Informal rubbish dumps

Plate 2 2019 Historical Aerial Photograph the Site (16 January 2016)

Plate 3 2008 Historical Aerial Photograph the Site (28 August 2006) – Close up of Hotel Area

Geo Environmental Solutions – GES Page 15 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Plate 4 2008 Historical Aerial Photograph the Site (28 August 2006)

2.6 Dangerous Goods Records (WorkSafe Tasmania)

Dangerous goods records for the site were provided by WorkSafe Tasmania on the 17 May 2019. Table 2 summarises the relevant documents and these documents in their entirety are provided in Appendix 3. Figure 6 is a site plan for the underground petroleum storage systems (UPSS) in October 2006 and Figure 7 is a site plan in May 1990. In summary the site has hosted fuel storage and has three underground storage tanks used for the storage of diesel, unleaded petrol and leaded petrol (super). site has also held LPG on site for sales and cooking purposes. This investigation is not concerned with the LPG storage as contamination from this is unlikely.

Geo Environmental Solutions – GES Page 16 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Table 2 Relevant Dangerous Goods Records Date Details 31 October Application for storing dangerous goods. Site Manifest included the following: 2006

13 September Dangerous goods inspectorate - Great Lake General Store – Supplier: Tas Fuel 1993

14 July 1989 Inspection Report – 001 Keeping Dangerous Goods – Great Lake General Store – Fuel supplier BP. Tank details as above. 19 December Approval of Site and Construction of Premises for keeping flammable liquids or dangerous 1988 commodities or the alteration thereof

6 January 1988 Inspection Report – 001 Keeping Dangerous Goods – Compleat Angler Hotel

19 April 1984 Inspection Report for Keeping Dangerous Goods

Geo Environmental Solutions – GES Page 17 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Figure 6 Site Plan showing UPSS infrastructure (October 2006)

Geo Environmental Solutions – GES Page 18 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Figure 7 Site Plan showing UPSS infrastructure (May 1990)

Geo Environmental Solutions – GES Page 19 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

2.7 Environmental Protection Authority - Property Information Request

A property information request response was provided by the Environmental Protection Authority (EPA) Tasmania on the 29th May 2019. The full letter report is presented in Appendix 4. Below is the relevant excerpt from the letter.

2.8 Groundwater

2.8.1 Potential Up-Gradient Contamination Sources Given the rural setting there are not likely to be up gradient sources of contamination.

2.8.2 Downgradient Ecological Receptors The closest down gradient ecological receptor is the waters of Great Lake at Swan Bay. The edge of the lake is 450m east from the UPSS infrastructure.

2.8.3 Water Bore Users There are two functioning groundwater bore registered on the site. For full reports see Appendix 5.

Figure 8 Groundwater bore locations on site

2.9 Flora & Fauna

According to TASVEG 3.0 mapping, the following vegetation communities are present at the site: • Agricultural, urban and exotic vegetation (FUR), Urban areas; • Eastern Alpine Healthland (HHE) – Highland and treeless vegetation; • Eucalyptus Coccifera Forest and Woodland (DCO) – Dry eucalypt forest and woodland.

Geo Environmental Solutions – GES Page 20 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Due to the previous disturbance at the site and the surrounding area, there is no significant flora or fauna values within or surrounding the site. A review of the Natural Values Atlas (NVA) (DPIPWE) accessed at 11:18 on Thursday 30th May 2019 identified no threatened flora or fauna species within 50 m of the site. The closest threatened native vegetation community is Highland Grassy Sedgeland which is 650m to the northwest of the site.

HHE

FUR

DCO

Figure 9 TASVEG 3.0 Mapping (The LIST).

3 PREMIMINARY CONCEPTUAL SITE MODEL

3.1.1 Areas of Potential Concern As determined in this desktop assessment, areas of potential concern (AOPC) on site relate to the activities relating to fuel storage and sales, see Figure 10 and Figure 11. Areas of potential concern (AOPC) onsite relate to: • Back-up generator owned by the Lessee of the shop – diesel powered unknown but assumed; • UPSS infrastructure adjacent to the shop – diesel, ULP and Super petrol stored in underground tanks plus, 2 bowsers 1 x single electric pump and 1 x duel electric pump; and • Informal rubbish dumps – house-hold waste in to localised areas • Effluent ponds on site potential accumulation in the pond sludge/walls

3.1.2 Contaminants of Potential Concern The following contaminants of potential concern (COPC) associated with underground fuel storage and dispensing infrastructure have been identified on site: • Total Petroleum/Recoverable Hydrocarbons (TPH/TRH); • Mono Aromatic hydrocarbons: Benzene, Toluene, Ethylbenzene, Xylene (BTEX); • Polycyclic Aromatic Hydrocarbons (PAH) including Benzo(a)pyrene (B(a)p) and • Lead (leaded fuels) and • Heavy Metals (house-hold waste dumps and effluent sludge)

3.1.3 Potential Receptors The following potential receptor has been identified: • Ecological receptor – Swan Bay – Great Lake

Geo Environmental Solutions – GES Page 21 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Figure 10 Preliminary CSM

Geo Environmental Solutions – GES Page 22 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Figure 11 UPSS infrastructure

Plate 5 General Store – underground tank location and bowser (note fuel staining)

Geo Environmental Solutions – GES Page 23 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

4 FIELD INVESTIGATION FINDINGS

4.1 Works Summary

A total of 1 site visit was conducted to complete the PSI see details in Table 3; Photographs of site visits are presented in Appendix 2. Table 3 Summary of Site Investigation Work Dates Scope Data Lab Report Details Pond wall grab 17th April EM1905863 Pond Wall. Please see the following reports: Chain of sample 2019 Custody documentation is presented in Appendix 6. Sample Receipt Notification is presented in Appendix 7. Quality Assurance and Quality Control in Appendix 8 and Certificate of Analysis in Appendix 9.

4.2 Surface Coverings

The surface of across the site is road gravels which is in good condition. There is localised concreted surfaces around some of the buildings including the general store and the hotel building complex.

4.3 Signs of Contamination

The site surface is generally clean and free from oily stains or spills with the exception of localised staining around the bowers at the general store.

4.4 Geological Interpretation

In general, the Mineral Resources Tasmania (MRT) geological mapping was consistent with the ground conditions encountered during the investigation. The site is underlain with Jurassic Dolerite.

5 SOIL ECOLOGICAL IMPACT ASSESSMENT

5.1 NEPM ASC (2013) Guidelines

The following ecological investigation guidelines are to be addressed to assess acceptable levels of risk to terrestrial ecosystems: • NEPM ASC (2013) Ecological Investigation Levels (EIL’s) – have been developed for selected metal and organic substances. EIL’s depend on specific soil and physicochemical properties and land use scenarios and generally apply to the top two (2) metres of the soil profile (NEPM 2013); • NEPM ASC (2013) Ecological Screening Levels (ESL’s) – have been developed for selected petroleum hydrocarbon compounds and total petroleum hydrocarbon fractions. ESL’s broadly apply to coarse- and fine-grained soils and various land use scenarios within the top two (2) metres of the soil profile (NEPM ASC 2013).

Soil analytical results are compared against Ecological Screening Levels (ESL’s) and Ecological Investigation Levels (EIL’s) limits presented in Table 4. Table 4 Summary of Soil Investigation Limits Considered at the Site based in NEPM ASC (2013) Analytes Investigated Investigation Hydrocarbons Metals Levels (IL) TRH Benzo(a) pyrene Naphthalene Zn, Cu, Cr(III), DDT BTEX Lead (F1 to F4) (PAH) (PAH) Ni & As ESL’s Analysed Analysed Analysed EIL’s Analysed Analysed Analysed Not Analysed

Geo Environmental Solutions – GES Page 24 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

5.2 Findings

5.2.1 Ecological Screening Levels Laboratory analytical results for soil are presented in Appendix 9. Table 5 summaries all soil analytical results against relevant ESLs guideline limits for commercial/ industrial land use. Concentrations which exceed laboratory limits of reporting (LOR) would be highlighted in bold. ESL exceedances would be highlighted with a coloured cell. Samples within the proposed excavation zone are marked with an X; note no excavated is currently proposed. There were no hydrocarbon detections and therefore no risk identified to ecological receptors in relation to potential hydrocarbons. Table 5 Summary of Soil Analytical Results Compared with Ecological Screening Level’s for commercial / industrial land use

NEPM Ecological Screening Levels for Soil BTEX PAH TRH

Bold - Indicates LOR Exceedances X - Indicates Sample has been Excavated

Colour Shading - Indicates ESL Exceedances:

>1 x, * 2-5 x, ** 5-20 x, *** 20-50 x, **** >50 x

Benzene Toluene Ethylbenzene Xylenes Benzo(a)pyrene F1 (C6 - C10) F2 (>C10 - C16) F3 (>C16 - C34) F4 (>C34 - C40)

mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg

Land UseLand

Sample ID

Sample Date

(fine /coarse)

Soil ClassTexture

LOR 0.2 LOR 0.5 LOR 0.5 LOR 0.5 LOR 0.5 LOR 10 LOR 50 LOR 100 LOR 100 Pond Wall 17/4/19 F COM/IND <0.2 <0.5 <0.5 <0.5 <0.5 <10 <50 <100 <100

5.2.2 Ecological Investigation Levels Laboratory analytical results are presented in Appendix 9. Table 6 compares all soil analytical results against relevant ecological investigation limits (EIL’s) for commercial/ industrial land use. Concentrations which exceeded laboratory LOR are detailed in the table. EIL exceedances would be highlighted with a coloured cell and samples within the proposed excavation zone are marked with an X; note no proposed excavation. There were no EIL guideline exceedances. No risk to ecological receptors in terms of EILs has been identified. Table 6 Soil Analytical Results Compared Against Ecological Investigation Levels for urban residential/ public open spaces NEPM Ecological Investigation Levels for Soil Bold - Indicates LOR Exceedances X - Indicates Sample Withiin Inferred Excavation Colour Shading - Indicates ESL Exceedances:

>1 x, * 2-5 x, ** 5-20 x, *** 20-50 x, **** >50 x

Copper (CEC) Copper (pH) Copper Nickel Zinc III Chromium Lead Arsenic DDT Naphthalene

Sample ID Sample Date EIL UseLand Sensitivity Class Soil (cmolc/kg) CEC Soil pH Soil Class Texture (fine /coarse)

mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg Pond Wall 17/4/19 COM/IND 35 6 (3) F 91 91 55 37 144 7 <5 <0.2 <1 pH Designation: 1) Using 0.01M CaCl2 extract. Rayment, G.E. and Lyons, D.J. (2011). “Soil Chemical Methods – Australasia”. 495+20 pp. CSIRO Publishing, Melbourne. 2) pHF (1:5). Adjusted by subtracting 0.75 with +/- 0.25 error to calibrate to the CaCl2 method (per comm. ALS Brisbane Acid Sulphate Soils Laboratory). Methods in accordance with Ahern, C.R., Stone Y., and Blunden B. (1998b). ‘Acid Sulphate Soils

Geo Environmental Solutions – GES Page 25 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Assessment Guidelines’. Acid Sulphate Soils Management Advisory Committee, Wollongbar, NSW, Australia. 3) Classified in accordance with parent material typical soil pH as per the Tasmanian soils database / or on-site testing

6 SOIL HUMAN HEALTH DIRECT CONTACT ASSESSMENT

6.1 Guidelines

6.1.1 Land Use Classification The NEPM (2013) guidelines have been referenced to ensure that the correct land use and density category has been adopted for the site and the surrounding properties (where applicable). As per NEPM (2013) guidelines, the adopted land use class is dependent on the building density and the opportunity for soil access by site occupants (exposure to potentially impacted soil). Aspects needing to be considered include: • Whether the site is of sensitive land use such as a childcare centre, preschool, primary school or aged care facility in which case land use Class A is applicable; • The proportion of paved area to determine direct contact exposure risk and therefore classification as low or high density; and • Classification based on residential, recreational or commercial/industrial setting.

6.1.2 Adopted Land Use Classification The adopted land use class is presented in Table 7. Table 7 Summary of Land Use Spatial and Temporal Setting for Determining Exposure Risk Soil Location Land Use Pathway* Land Use Class Bores All Site Commercial workers ALL D * Pathways: DC – Dermal Contact – HSL Trench Worker Guidelines (CRC CARE 2013) DI – Dust Inhalation - HIL Guidelines (NEPM ASC 2013) SI – Soil Ingestion - HIL Guidelines (NEPM ASC 2013) ALL – All of above

6.2 Findings

6.2.1 Dermal Contact - Petroleum Hydrocarbons Laboratory analytical results are presented in Appendix 9. Table 8 presents soil hydrocarbon analytical results compared against CRC CARE (Friebel & Nadebaum, 2011) Health Screening Levels (HSL) guidelines for assessing dermal contact risk HSL D and Trench workers. Concentrations which exceeded laboratory LOR would be highlighted in bold. HSL exceedances would be highlighted with a coloured cell indicating the highest HSL land used class which is exceeded. There were no detections of hydrocarbons and there were guideline exceedances for dermal contact risk to workers current commercial workers. Table 8 Soil Analytical Results Compared Against CRC CARE Guidelines for Dermal Contact – BH01-BH04 EP080: BTEXN EP080/071: TRH CRC CARE Health Screening Level

Dermal Contact Hazard from Soil

Hydrocarbons'

Benzene Toluene Ethylbenzene Xylenes Total Naphthalene C10-C6Fraction >C10C16-Fraction >C16C34-Fraction >C34C40-Fraction Units mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg LOR 0.2 0.5 0.5 0.5 1 10 50 100 100 HSL D Commercial/Industrial 430 99000 27000 81000 11000 26000 20000 27000 38000 Intrusive Maintenance Worker 1100 120000 85000 130000 29000 82000 62000 85000 120000 Date Sample 17/04/2019 Pond Wall <0.2 <0.5 <0.5 <0.5 <1 <10 <50 <100 <100

Geo Environmental Solutions – GES Page 26 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

6.2.2 Dust Inhalation & Soil Ingestion Laboratory analytical results are presented in Appendix 9. Table 9 presents the soil analytical results compared against combined dust inhalation and soil ingestion risk is assessed through the application of NEPM (2013) Health Investigation Levels (HILs) for exposure to soil contaminants. Concentrations which exceeded laboratory LOR would be highlighted in bold, metals are simply reported. HIL exceedances would be highlighted with a coloured cell indicating the highest HIL land used class which is exceeded. Samples within the proposed excavation zone are marked with an X; note no excavation planned. There were no detections of polynuclear aromatic hydrocarbons, organochlorine pesticides or organophosphorus pesticides. Metals detected were below HIL D guideline levels for commercial land use

Geo Environmental Solutions – GES Page 27 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Table 9 Soil Analytical Results Compared Against NEPM (2013) Health Investigation Limit Guidelines –EG035 Metals and PAHs Bold - Indicates LOR Exceedance in Non EA055: T: Moisture Total Metalic Compounds Content EG005T: Total Metals by ICP-AES Recov EP075(SIM)B: Polynuclear Aromatic Hydrocarbons

NEPM Health Investigation Levels (HIL's)

Dust Inhalation and Soil Ingestion Assessment

X - Indicates Sample Within Proposed

Excavation Zone

Moisture Content Moisture Arsenic Barium Beryllium Boron Cadmium Chromium Total Cobalt Copper Lead Manganese Nickel Selenium Vanadium Zinc Mercury Naphthalene Acenaphthylene Acenaphthene Fluorene Phenanthrene Anthracene Fluoranthene Pyrene Benz(a)anthracene Chrysene Benzo(b)fluoranthene Benzo(k)fluoranthene Benzo(a)pyrene Indeno(1.2.3.cd)pyrene Dibenz(a.h)anthracene Benzo(g.h.i)perylene PAHs (WHO) TEQ Benzo(a)pyrene

Units

% mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg 5 LOR 1 5 10 1 50 1 2 2 5 5 5 2 5 5 0.1 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 HIL D Commerial/Industrial HILHILTRUE A CDB 3000 500 3E+05 900 4000 240000 1500 60000 6000 10000 400000 730 4000 40 Sample date: Sample ID 17/04/2019 Pond Wall 37.2 <5 210 1 <50 1 144 56 91 7 408 55 <5 323 37 <0.1 <0.5 <0.5 <0.5 <0.5 <0.5 <0.5 <0.5 <0.5 <0.5 <0.5 <0.5 <0.5 <0.5 <0.5 <0.5 <0.5 <0.5 <0.5

Table 10 Soil Analytical Results Compared Against NEPM (2013) Health Investigation Limit Guidelines – OC/OPs Bold - Indicates LOR Exceedance in Non Metalic Compounds EP068A: Organochlorine Pesticides (OC) EP068B: Organophosphorus Pesticides (OP)

NEPM Health Investigation Levels (HIL's)

Dust Inhalation and Soil Ingestion Assessment

X - Indicates Sample Within Proposed

Excavation Zone

alpha-BHC (HCB) Hexachlorobenzene beta-BHC gamma-BHC delta-BHC Heptachlor ofSum Aldrin + Dieldrin Heptachlor epoxide trans-Chlordane alpha-Endosulfan cis-Chlordane Dieldrin 4.4`-DDE Endrin beta-Endosulfan 4.4`-DDD Endrin aldehyde Endosulfan (sum) 4.4`-DDT Endrin ketone Methoxychlor Chlordane DDD DDT DDE Dichlorvos Demeton-S-methyl Monocrotophos Dimethoate Diazinon Chlorpyrifos-methyl Parathion-methyl Malathion Fenthion Chlorpyrifos Parathion Pirimphos-ethyl Chlorfenvinphos Bromophos-ethyl Fenamiphos Prothiofos Ethion Carbophenothion Azinphos Methyl

Units

mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg LOR 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.2 0.05 0.2 0.05 0.05 0.05 0.05 0.2 0.05 0.05 0.05 0.2 0.05 0.05 0.05 0.2 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 HIL D Commerial/Industrial HILHILTRUE A CDB 80 50 45 2000 45 100 2000 2000 2500 530 3600 2000 HIDE ROW D 80 50 45 2000 45 100 2000 2000 2500 530 3600 2000 Sample date: Sample ID 17/04/2019 Pond Wall <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.2 <0.05 <0.2 <0.05 <0.05 <0.05 <0.05 <0.2 <0.05 <0.05 <0.05 <0.2 <0.05 <0.05 <0.05 <0.2 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05

Geo Environmental Solutions – GES Page 28 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

7 SOIL DISPOSAL ASSESSSMENT

7.1 Guidelines

Soil which is excavated from the site for landfill disposal is to be assessed against Information Bulletin 105 (IB105) for Classification and Management of Contaminated Soil for Disposal. The Environmental Protection Authority (EPA) uses 4 categories to classify contaminated soil as per Table 11: • (Level 1) Fill Material; • (Level 2) Low Level Contaminated Soil; • (Level 3) Contaminated Soil; and • (Level 4) Contaminated Soil.

Fixed numerical values are presented for soil concentrations and leachable fraction concentrations. Table 11 Summary of IB105 Classification Guidelines

7.2 Findings

The soil samples were compared against IB105 guidelines for soil disposal, see Table 12. There were no hydrocarbon detections. Some elevated metals were detected, and Chromium exceeded the Level 1 Material classification. It is likely that the chromium is naturally derived from either the dolerite or basalt found in the area.

Geo Environmental Solutions – GES Page 29 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Table 12 Soil Analytical Results Compared Against IB105 Investigation Limits for soil Disposal

Information Bulletin 105

Classification and Management of Contaminated Soil For

Disposal

Arsenic Barium Beryllium Cadmium Chromium Total Copper Cobalt Lead Manganese Mercury Nickel Selenium Zinc Aldrin + Dieldrin +DDT DDD + DDE Benzo(a)pyrene C6 - C9 Fraction C10 - C36 Fraction (sum) ofSum polycyclic aromatic hydrocarbons Benzene Toluene Ethylbenzene Xylenes Total Unit mg/kg mg/kg mg/kgmg/kgmg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg mg/kg LOR 5 10 1 1 2 5 2 5 5 0.1 2 5 5 0.05 0.05 0.5 10 50 0.5 0.2 0.5 0.5 0.5 Investigation Level Selected IB105 Level 1 <20 <300 <2 <3 <50 <100 <100 <300 <500 <1 <60 <10 <200 <2 <2 <0.08 <65 <1000 <20 <1 <1 <3 <14 IB105 Level 2 20 300 2 3 50 100 100 300 500 1 60 10 200 2 2 0.08 65 1000 20 1 1 3 14 IB105 Level 3 200 3000 40 40 500 2000 200 1200 5000 30 600 50 14000 20 200 2 650 5000 40 5 100 100 180 IB105 Level 4 750 30000 400 400 5000 7500 1000 3000 25000 110 3000 200 50000 50 1000 20 1000 10000 200 50 1000 1080 1800

17/04/2019 Pond Wall <5 210 1 1 144 91 56 7 408 <0.1 55 <5 37 <0.05 <0.05 <0.5 <10 <50 <0.5 <0.2 <0.5 <0.5 <0.5

Geo – Environmental Solutions GES Page 30 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

8 Preliminary Assessment of Wastewater and Bore water Infrasturcture

8.1 Wastewater

The site is currently serviced by a basic septic tank/pump well system which sewerage to effluent treatment ponds located at the rear of the site (see plate 6 & 7). The system consists of two ponds, linked by a gravity line, and the ponds are both unlined, with effluent a bright green colour of low quality. The second treatment pond also has an outfall to the ground surface with no cover or absorption drain. The effluent pond area is also unfenced, and has open access for animals or public wandering around the site. The current system is considered non-compliant and would constitute a potential environmental and health hazard. It is also possible that the un-lined effluent ponds are leaching into the groundwater aquifer at the site, and potentially impacting the bore water supply. The presence of the ponds on site has also resulted in a planning attenuation overlay on the site which currently limits site development potential. It is assume that if the ponds are decommissioned and a new treatment system installed that the attenuation overlay will be removed.

It is recommended that the wastewater infrastructure be upgraded as part of any site development including the following: • Decommissioning of the existing effluent ponds • Review of the current primary pumping infrastructure and replacement or upgrading as required depending upon capacity requirements • Installation of appropriate grease trap for the hotel (min 3000L suggested to be required) • Design and installation of an appropriate treatment system for the site, with indications that a commercial aerated wastewater treatment system (AWTS) with irrigation of treated effluent on site would be suitable • Preliminary estimates suggest that a budget of approximately $100-150K should be allowed for decommissioning and replacement works

Plate 6 wastewater primary tank and pump station

Geo Environmental Solutions – GES Page 31 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Plate 7 wastewater effluent ponds (note effluent colour and unlined pond)

8.2 Bore water

The site is currently serviced by a groundwater bore drilled to a depth of approximately 18m into the fractured dolerite underlying the site (see appendix 5). The standing water level is approximately 6m, although it is not known how this fluctuates with pumping draw down or seasonal rainfalls and recharge. The bore head has been excavated and a large concrete man hole installed for mounting of the pump, see plate 8 below. There does not appear to be any pre treatment or disinfection equipment installed for the bore water supply. The water quality appears to be good, with a clear colour and no odour. However, a presumptive sample for bacteria returned a positive result, suggesting some contamination is represent in the system. This could possibly be in the aquifer from effluent contamination or other sources. This could also be in the infrastructure on site or in the well head from animal droppings or other bacteria growing on delivery lines (water was tap sampled).

It is recommended that the bore water infrastructure be investigated upgraded as part of any site development including the following: • Pump testing of drawn down and yield • Thorough testing of the water quality from a number of points in the system including bacterial testing • The bore water and roof water supply be evaluated to ensure sustainable supply • An appropriate treatment system for metal removal and disinfection be designed and installed • Preliminary estimates suggest that a budget of approximately $25-50K should be allowed for upgrade works

Geo Environmental Solutions – GES Page 32 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Plate 8 Water bore head with manhole and pump infrastructure

Geo Environmental Solutions – GES Page 33 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

9 CONCLUSIONS

9.1 Desktop Assessment

The following conclusions were made from the desktop assessment: • The site is zoned Local Business on the eastern half of the site and Rural Resource on the western half of the site under the Central Highlands Interim Planning Scheme of 2015 • WorkSafe Tasmania confirmed the following information for the site; it has hosted fuel storage and sales since the mid-1980 and has three underground storage tanks of diesel, unleaded petrol and leaded petrol (super). The site has also held LPG on site for sales and cooking purposes. This investigation is not concerned with the LPG storage as contamination from this is unlikely. • The site is underlain with Jurassic Dolerite. The site is approximately 1060m above sea level. Groundwater is inferred to be directed towards the east to Swan Bay on Great Lake with the same aspect as the surface topography. This is the closest ecological receptor. The edge of the lake is 450m east from the UPSS infrastructure. • The historical aerial photographs confirm the following: There are numerous buildings on site associated with the hotel activities. The two sewage settling ponds have been onsite since the hotel facilities were constructed. There appear to be two informal rubbish dumps on the site. There was a wildfire in that area summer of 2019, as seen in the 2019 aerial photograph. • GES is aware of the following report for the site: Site Services Due Diligence Report for Johns Group Great Lake Hotel Redevelopment by Coordinated Engineering Services (CES). CES confirmed that the site has hosted a commercial shop front and hotel accommodation since 1984. • The Environmental Protection Authority (EPA) Tasmania is aware that the site has three active registered underground petroleum storage systems with a total volume of 40,000L which is considered as a potentially contaminating activity. • There appear to be no monitoring records for the fuel infrastructure, and it also appears that no formal loss monitoring and reporting (SIRA) has been completed; • The shop and refuelling area has no spill containment or loss control in place with only an open stormwater drain present, therefore any surface spills during operations since the 1980’s are likely to have impacted soil and possibly groundwater in the area; • Conceptual Site Model o As determined in this desktop assessment, areas of potential concern (AOPC) on site relate to the activities relating to fuel storage and sales; including: ▪ Back-up generator operated by the shop – diesel powered unknown but assumed; ▪ UPSS infrastructure adjacent to the shop – diesel, ULP and Super petrol stored in underground tanks plus, 2 bowsers 1 x single electric pump and 1 x duel electric pump; and ▪ Informal rubbish dumps – house-hold waste in two localised areas ▪ The effluent ponds o The following contaminants of potential concern (COPC) associated with underground fuel storage, dispensing infrastructure and other activities have been identified on site: ▪ Total Petroleum/Recoverable Hydrocarbons (TPH/TRH); ▪ Mono Aromatic hydrocarbons: Benzene, Toluene, Ethylbenzene, Xylene (BTEX); ▪ Polycyclic Aromatic Hydrocarbons (PAH) including Benzo(a)pyrene (B(a)p) and ▪ Lead; plus ▪ Heavy Metals and hydrocarbons from informal waste dumps and accumulation in sewerage sludge.

Geo Environmental Solutions – GES Page 34 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

9.2 Limited Wastewater and Bore Water Assessment Findings

The following conclusions have been made from the assessment of the wastewater and bore water infrastructure: • No grease trap is installed for the commercial kitchen on site • The two effluent ponds are unlined, in poor condition, with an open outlet to the ground surface • The effluent ponds are considered to be non-compliant with health and environmental standards and will require decommissioning and replacement with a suitable new system as part of any site redevelopment • Soil testing shows the pond walls to have low level heavy metal contamination (level 2 according to EPA IB105) which will require appropriate management • The bore water supply appears to be in a dolerite aquifer with low to moderate yield, and preliminary screening of water samples showed a positive to bacterial contamination • The bore system has inadequate storage, filtration, and treatment • The bore system requires more detailed investigation and testing, and will require upgrading of infrastructure as part of any site redevelopment

10 RECOMMENDATIONS GES recommends the following: • An Environmental Site Assessment (ESA) should be completed to understand if the existing UPSS infrastructure has been compromised overtime. This must include invasive soil investigation in the vicinity of the underground storage tanks plus the area surrounding the generator where hydrocarbon containing fuels may have been spilt. Soil surrounding the informal waste dumps should also be tested. The ESA could be completed as part of any development application package for the site. • The bore water system should be testing for yield, plus draw down, and further tested for quality parameters including bacteria to determine if the effluent ponds, surface contamination from animals or other sources are impacting water quality.

Yours faithfully,

Sarah Joyce BSc (Hons) Environmental Geologist

Geo Environmental Solutions – GES Page 35 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

REFERENCES ANZECC, 2000. Australian and New Zealand Guidelines for the Assessment and Management of Contaminated Sites. Australian and New Zealand Environment and Conservation Council and National Health and Medical Research Council. AS/NZS 1726:1993. Geotechnical Site Investigations. Standards Australia, 1993. AS 4482:2005 Guide to the sampling and investigation of potentially contaminated soil – Part 1: Non-volatile and semi-volatile compounds, Standards Australia, 2005. AS/NZS 5667.1:1998 Water quality – Sampling, Part 1: Guidance on the design of sampling programs, sampling techniques and the preservation and handling of samples, Standards Australia, 1998. Coordinated Engineering Services (CES), May 2019; Site Services Due Diligence Report for Johns Group Great Lake Hotel Redevelopment. CRC CARE 2013, Petroleum Vapour Intrusion assessment: Australian guidance, CRC CARE Technical Report no. 23, CRC for Contamination Assessment and Remediation of the Environment, Adelaide, Australia. Davis, GB, Merrick, NP & McLaughlan, RG 2006, Protocols and techniques for characterising sites with subsurface petroleum hydrocarbons – a review, Technical Report no. 2, CRC for Contamination Assessment and Remediation of the Environment, Adelaide, Australia. Davis, GB, Patterson, BM & Trefry, MG 2009a, Biodegradation of petroleum hydrocarbon vapours, Technical Report no. 12, CRC for Contamination Assessment and Remediation of the Environment, Adelaide, Australia. Davis, GB, Wright, J & Patterson, BM 2009, Field assessment of vapours, CRC CARE Technical Report no. 13, CRC for Contamination Assessment and Remediation of the Environment, Adelaide, Australia. Freeze, R.A., and Cherry, J.A., 1979, Groundwater: Englewood Cliffs, NJ, Prentice-Hall, 604 p. Friebel, E & Nadebaum, 2011, ‘Health screening levels for petroleum hydrocarbons in soil and groundwater. Part 1: Technical development document’, CRC for Contamination Assessment and Remediation of the Environment, CRC CARE Technical Report no. 10, Adelaide. LIST (2019). Land Information System Tasmania Online Database. Department of Primary Industries, Parks, Water and Environment. 2019. https://www.thelist.tas.gov.au/app/content/home NEPC, 1999. Guideline on Data Collection, Sample Design and Reporting Schedule B (2), National Environmental Protection Measure (Assessment of Site Contamination), National Environment Protection Council, 1999. Measures as amended, taking into account amendments up to National Environment Protection (Assessment of Site Contamination) Amendment Measure 2013 (No. 1) NEPM, 1999.Guideline on Investigation Levels for Soil and Groundwater, Schedule B (1), National Environment Protection (Assessment of Site Contamination) Measure, National Environment Protection Council, 1999. Measures as amended, taking into account amendments up to National Environment Protection (Assessment of Site Contamination) Amendment Measure 2013 (No. 1) Queensland Government Natural Resources and Water ‘Land Series’ bulletin, Measuring Salinity. 2007. Managing Queensland’s natural resources for today and tomorrow.

Geo Environmental Solutions – GES Page 36 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

LIMITATIONS STATEMENT This PSI Report has been prepared in accordance with the scope of services between Geo-Environmental Solutions Pty. Ltd. (GES) and The Johns Group P/L (‘the Client’) on behalf of their client. To the best of GES's knowledge, the information presented herein represents the Client's requirements at the time of printing of the Report. However, the passage of time, manifestation of latent conditions or impacts of future events may result in findings differing from that described in this Report. In preparing this Report, GES has relied upon data, surveys, analyses, designs, plans and other information provided by the Client and other individuals and organisations referenced herein. Except as otherwise stated in this Report, GES has not verified the accuracy or completeness of such data, surveys, analyses, designs, plans and other information. The scope of this study does not allow for the review of every possible soil and groundwater contaminant over the whole area of the site. Samples collected from the investigation area are assumed to be representative of the areas from where they were collected and indicative of the contamination status of the site at that point in time. The conclusions described within this report are based on these samples, the results of their analysis and an assessment of their contamination status. This report does not purport to provide legal advice. Readers of the report should engage professional legal practitioners for this purpose as required. No responsibility is accepted for use of any part of this report in any other context or for any other purpose by third party.

Geo Environmental Solutions – GES Page 37 of 95 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 1 GES Staff GES is a specialist geotechnical and environmental consultancy providing advice on all aspects of soils, geology, hydrology, and soil and groundwater contamination across a diverse range of industries. Geo Environmental Solutions Pty Ltd: • ACN – 115 004 834 • ABN – 24 115 004 834

GES STAFF - ENGAGED IN SITE INVESTIGATION WORKS Dr John Paul Cumming B.Agr.Sc (Hons) Phd CPSS GAICD • Principle Author and Principle Environmental Consultant • PhD in Environmental Soil Chemistry from the University of Tasmania in 2007 • 12 years’ experience in environmental contamination assessment and site remediation.

Ms Sarah Joyce BSc (Hons) • Environmental Geologist • Honours in Geography and Environmental Science at the University of Tasmania in 2003; • Undergraduate Degree Double Major in Geology and Geography & Environmental Science • 15 years professional work experience and 7 years contaminated site assessment Mr Grant McDonald (Adv. cert. hort.) • Soil Technician • 10 years’ experience in hydrocarbon and heavy metal contamination sampling of soils and groundwater.

GES STAFF – WITH CONTAMINATED SITES EXPERIENCE Mr Kris Taylor Bsc (Hons) • Senior Environmental & Engineering Geologist • Honours in Environmental Geology at the University of Tasmania in 1998 20 years’ experience in environmental contamination assessments and hydrogeology (including honours in mine site tailing pollution assessment). Including 15 years’ experience in asbestos assessment. Mr Aaron Plummer (Cert. IV) • Soil Technician • 5 years’ experience in hydrocarbon and heavy metal contamination sampling of soils and groundwater. Mr Mark Downie B.Agr.Sc (Hons) • Soil Scientist • 8 Year experience in contamination assessment and reporting of soils and groundwater. Ms Peri Lucas B.Agr.Sc (Hons) • Soil Scientist • 2 Year experience in contamination assessment and reporting of soils and groundwater.

Appendix 1 GES Staff Page 38 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 2 Site Photographs

Appendix 2 Site Photographs Page 39 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 2 Site Photographs Page 40 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

General Store – underground tank locations

Appendix 2 Site Photographs Page 41 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 2 Site Photographs Page 42 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Hotel cabins and the surrounding bush to the south

Hotel cabins and surrounding bush to the north

Appendix 2 Site Photographs Page 43 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Groundwater bore infrastructure

View to the east towards Great Lake.

Appendix 2 Site Photographs Page 44 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Water infrastructure relating to the hotel

Settling pond

Appendix 2 Site Photographs Page 45 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Edge of sewage settling pond and surrounding vegetation

Sewage settling pond

Appendix 2 Site Photographs Page 46 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 3 Dangerous Goods records

Appendix 3 Dangerous Goods Records. Page 47 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 3 Dangerous Goods Records. Page 48 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 3 Dangerous Goods Records. Page 49 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 3 Dangerous Goods Records. Page 50 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 3 Dangerous Goods Records. Page 51 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 3 Dangerous Goods Records. Page 52 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 3 Dangerous Goods Records. Page 53 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 3 Dangerous Goods Records. Page 54 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 3 Dangerous Goods Records. Page 55 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 3 Dangerous Goods Records. Page 56 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 3 Dangerous Goods Records. Page 57 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 3 Dangerous Goods Records. Page 58 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019 Appendix 4 EPA RTI

Appendix 4 EPA Page 59 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 4 EPA Page 60 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 5 Groundwater bore data

Appendix 5 Groundwater bore information Page 61 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 5 Groundwater bore information Page 62 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 5 Groundwater bore information Page 63 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 5 Groundwater bore information Page 64 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 5 Groundwater bore information Page 65 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 5 Groundwater bore information Page 66 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019 Appendix 6 Laboratory Chain of Custody

Appendix 6 Laboratory Chain of Custody Page 67 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 7 Laboratory Sample Receipt Notification

Appendix 7 SRN Page 68 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 7 SRN Page 69 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 7 SRN Page 70 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 8 Quality Assurance and Quality Control Documentation

Appendix 8 QA/QC Page 71 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 8 QA/QC Page 72 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 8 QA/QC Page 73 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 8 QA/QC Page 74 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 8 QA/QC Page 75 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 8 QA/QC Page 76 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 8 QA/QC Page 77 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 8 QA/QC Page 78 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 8 QA/QC Page 79 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 8 QA/QC Page 80 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 8 QA/QC Page 81 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 8 QA/QC Page 82 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 8 QA/QC Page 83 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 8 QA/QC Page 84 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 8 QA/QC Page 85 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 8 QA/QC Page 86 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 8 QA/QC Page 87 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 9 Certificate of Analysis

Appendix 9 Certificate of Analysis Page 88 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 9 Certificate of Analysis Page 89 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 9 Certificate of Analysis Page 90 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 9 Certificate of Analysis Page 91 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 9 Certificate of Analysis Page 92 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 9 Certificate of Analysis Page 93 Preliminary Site Investigation. Great Lakes Hotel, 3096 Marlborough Highway, Miena. June 2019

Appendix 9 Certificate of Analysis Page 94 DECOMMISSIONING MANAGEMENT PLAN

Wastewater Lagoons – Great Lake Hotel Miena

September 2019

Geo-Environmental Solutions P/L 29 Kirksway Place Battery point TAS 7004. Ph 6223 1839 WASTEWATER LAGOONS – DECOMMISSIONING MANAGEMENT PLAN

1. CONTACTS REGISTER

Key Contacts

The Johns Group Site Owners GPO Box 479 Hobart TAS 7001 Great Lake Hotel Phone: 03 6259 8163

Environmental Consultants Geo Environmental Solutions – GES 29 Kirksway Place Battery Point TAS 7004 Contact: John Paul Cumming T: (03) 6223 1839 M: 0413 541 531

Emergency Procedure

Immediately after a person causes, or becomes aware of an environmental incident relating to activities described in this Management Plan they should:

1. Ensure the site is safe First, consider personal safety, and if safe to do so, prevent any further environmental impact from occurring.

2. Notify Emergency Services if required on 000

3. Inform Regulator & Council Inform EPA TAS of incident (1800 005 171) Inform Central Highlands Council (03 6259 5503)

Any significant environmental incidents/accidents or major breaches of undertakings during site operations must be reported to EPA TAS as soon as possible.

DOCUMENT CONTROL Title Version Date Author Reviewed By

Great Lake Wastewater Lagoons Decommissioning Management Plan. 3096 Version 1 25/09/19 Sarah Joyce JP Cumming Marlborough Highway Miena TAS 7030

1

WASTEWATER LAGOONS – DECOMMISSIONING MANAGEMENT PLAN

1. CONTACTS REGISTER ...... 1 Key Contacts...... 1 Emergency Procedure ...... 1 DOCUMENT CONTROL ...... 1 2. EXECUTIVE SUMMARY ...... 3 3. SITE DESCRIPTION ...... 4 3.1. Location ...... 4 3.2. Background ...... 4 4. ENVIRONMENTAL MANAGEMENT ...... 6 4.1. Potential Environmental Impacts ...... 6 4.1.1. Surface Water ...... 6 4.1.2. Groundwater ...... 6 4.1.3. Noise ...... 6 4.1.4. Dust ...... 7 4.1.5. Odour...... 7 4.1.6. Imported materials ...... 7 4.1.7. Wastewater ...... 7 4.1.8. Sludge ...... 7 4.1.9. Potentially contaminated soil ...... 8 5. COMPLAINTS HANDLING SYSTEM...... 8 5.1. Objectives ...... 8 5.2. Management Strategy ...... 8 5.2.1. General ...... 8 6. SUMMARY OF COMMITMENTS ...... 9 Appendix 1 – Site Plan ...... 10

Table 1 – Summary of Commitments ...... 9

2

WASTEWATER LAGOONS – DECOMMISSIONING MANAGEMENT PLAN

2. EXECUTIVE SUMMARY This document has been prepared for the Johns Group in response to the request for a Decommissioning Management Plan (EMP) to be developed for the decommissioning of two existing wastewater lagoons at the Great Lake Hotel situated at 3090 Marlborough Highway Miena.

This plan primarily covers the management of environmental risks from the required works to decommission the lagoons. A complaint handling system is recommended for the management of any issues arising from the operations on the site.

A basic overview of commitments arising from this plan are as follows: • The contractors and site owners must eliminate the offsite movement of uncontrolled wastewater in stormwater or groundwater, by removing any remaining wastewater in the lagoons prior to excavation • The environmental consultant must ensure sludge in the lagoons is tested for classification according to EPA bulletin 105 and NEPM 2013 • Excess sludge in the lagoons not suitable to treatment and retention on site must be transported to an approved waste facility by a licensed contractor • The contractor must ensure all directions relating to site rehabilitation are followed including lime amendment of sludge, soil cover, and revegetation • A chain of custody must be kept by the contractor and endorsed by the environmental consultant for all wastewater and sludge leaving the site • The contractor must ensure all traffic management recommendations are followed to minimise odor and noise generation, and to ensure a safe working environment for all staff. • Maintain a complaints and enquiries register including but not limited to, any complaints regarding noise, odor, water management or potentially contaminating issues.

It should be noted that this document is only valid for the management of operations as currently understood by GES and any changes to site management, site infrastructure, or major changes to operations will require amendments to the plan and invalidate this document.

3

WASTEWATER LAGOONS – DECOMMISSIONING MANAGEMENT PLAN

3. SITE DESCRIPTION

3.1. Location The Great Lake Hotel is located at 3096 Marlborough Highway, Miena - hereby referred to as ‘The Site’. The site is zoned Local Business on the eastern half of the site and Rural Resource on the western half of the site under the Central Highlands Interim Planning Scheme of 2015.

The Site location is presented in Figure 1.

The Site

Figure 1 -site location

3.2. Background The Johns Group is intending to install a new wastewater system and decommission the existing wastewater infrastructure at the site, including the two wastewater lagoons on the property (see figure 2&3). The two lagoons have been in place for some time and the operation of the lagoons is not compliant with current environmental standards. The primary and secondary lagoons have an area of approximately 450m2 and 300m2 respectively, and an estimated total working volume of approximately 1ML. The lagoons have several environmental hazards that must be managed during the decommissioning process:

1. Wastewater in the lagoons will contain bacteria and other pathogens.

2. Sludge in the lagoons will be anaerobic, contain bacteria, pathogens, and potentially be contaminated with heavy metals and other substances.

3. Soil on the lagoon base and walls may also be potentially contaminated with heavy metals and other substances.

4

WASTEWATER LAGOONS – DECOMMISSIONING MANAGEMENT PLAN

Figure 2 - Aerial image of the lagoons

Figure 3 – Close up view of the lagoons

5

WASTEWATER LAGOONS – DECOMMISSIONING MANAGEMENT PLAN

4. ENVIRONMENTAL MANAGEMENT

A series of management impacts parameters have been assessed as part of this plan. They include management actions associated with the disposal of hard infrastructure in the lagoons, wastewater, residual sludge, and any contaminated soil that maybe encountered. A daily site checklist is attached as appendix 1.

4.1. Potential Environmental Impacts

4.1.1. Surface Water

There is potential for localized surface water contamination during the works. In particular uncontrolled release of wastewater or sludge from the lagoons must be managed.

Management Actions: • Access to be provided for pump truck in close proximity to the lagoons, a gravel pad or staging area maybe required for inclement weather • A SWMS to be prepared prior to all pumping operations and endorsed by all personnel on site and the environmental consultant • Any spare pumping equipment fittings and spare parts to be stored on racking or appropriate containers • Additional bunding and spill kits will be made available for the management of any localized fluid spills that may occur from the trucks

4.1.2. Groundwater

The groundwater at the site is unlikely to be affected by the works. Groundwater flow direction is expected to mirror the surface contours. If the soil underlying the site does become contaminated during works, then surface water could potentially leach contaminates into the groundwater, however if the plan is followed correctly this is unlikely to occur.

Management Action: • Effort should be taken to ensure minimal ground spillage of fluids during the operation of the site. • If there is a significant spill of fluids or other contaminants on the site immediate clean up action must be taken

4.1.3. Noise The nearby hotel has accommodation such that operators of machinery must be aware of potential nuisance noise. Noise generated by normal operations include traffic entering and exiting the site (i.e. truck brakes, starting of motors) and use of pumps, excavators and other machinery. During daily works, noise generation is considered unavoidable. Management Action: • Works will comply with all council regulations in regards to operating times. • Maintain a complaints register including any associated noise issues. Review the register on a regular basis in order to determine key characteristics and any requirement for further investigation and corrective actions

6

WASTEWATER LAGOONS – DECOMMISSIONING MANAGEMENT PLAN

4.1.4. Dust

During works at the site, particularly in the summer months, dust production is considered unavoidable. Where dust is produced there is some potential that it will contain contaminating materials.

Management Action: • There are unlikely to produce excessive amounts of dust, except in dry and windy conditions. • Where dust production is considered excessive, dust mitigation though watering would be required.

4.1.5. Odour

The dewatered lagoons have the potential to produce offensive odors from the anaerobic sludge and impact guests of the hotel.

Management Action: • The moisture status and odor of the sludge must be monitored upon dewatering and a bulk supply of lime available onsite for immediate stabilization of the sludge • The bulk supply of lime should be equivalent to a 1:2 ratio for mixing with the estimated sludge volume

4.1.6. Imported materials

Any imported fill material used in the management of the site will undergo validation sampling and be documented (it is not envisaged any imported fill will be required).

4.1.7. Wastewater

It is anticipated that a significant volume of the wastewater in the lagoons will evaporate following disconnection of the rising sewer main. Any wastewater remaining in the lagoons not able to be evaporated or discharged to the existing outfall will require removal from site and disposal in an approved wastewater treatment plant.

Management Action: • Residual wastewater to be disposed of at an approved wastewater plant by a licensed contractor (chain of custody to be kept)

4.1.8. Sludge

The lagoons will have a sludge layer that must be adequately managed. The sludge material has the potential to contain pathogens, and contaminates such as heavy metals.

Management Action: • Sludge in the lagoons must be tested by the environmental consultant in a NATA approved laboratory and classified according to Tasmanian biosolids guidelines, EPA IB105, and NEPM 2013 • Pending results sludge can be lime amended and incorporated into the soil on site

7

WASTEWATER LAGOONS – DECOMMISSIONING MANAGEMENT PLAN

• Any sludge not suitable for lime stabilization and reuse on site must be transported to an approved site by a licensed contractor • A chain of custody is to be kept for all testing, classification, and any disposal

4.1.9. Potentially contaminated soil

Soil forming the base and walls of the lagoon has potential to be contaminated, as a result the area must be adequately tested once sludge has been removed and prior to any spreading or removal of soil. Management Action: • Soil in the area of the lagoons must be tested by the environmental consultant in a NATA approved laboratory and classified according to and NEPM 2013 • If any soil dos not comply with the NEPM land use guidelines it must also be classified according to EPA IB105 and if off site disposal is required the appropriate approvals sought from EPA Tasmania (regulation 12) • Any removal or transport of contaminated soil must be undertaken by a licensed contractor to an approved facility and chain of custody to be kept

5. COMPLAINTS HANDLING SYSTEM A complaints handling system is recommended for the management of any issues arising from the operations of the site.

5.1. Objectives To ensure effective communication between nearby commercial occupants, residents and Site Management; by recording any complaints and responding directly to the complainant until the source of the incident is verified and resolved as far as is practicable.

5.2. Management Strategy

5.2.1. General To effectively manage community health, safety and environment concerns, the contractor will implement a complaints handling system. Complaints and enquires will be recorded in a complaints and enquiries register. The register will record the date, nature, and resolution of any action from a complaint.

Within two working days of a complaint being made, the complaint will be recorded on the complaints and enquiries register, investigated by the Operations Manager and a response sent to the complainant if necessary. Actions will then be taken to resolve the point of conflict.

8

WASTEWATER LAGOONS – DECOMMISSIONING MANAGEMENT PLAN

6. SUMMARY OF COMMITMENTS Table 1 – Summary of Commitments Number Commitment Document Section Number 1 Key Contacts: Contacts Register The Johns Group Great Lake Hotel Ph: 03 6259 8163

John Paul Cumming – Geo-Environmental Solutions T: (03) 6223 1839 M: 0413 541 531 2. Emergency Procedure – Notify: Contacts Register

Emergency Services if required on 000 Inform EPA TAS of incident (1800 005 171) Inform Central Highlands Council (03 6259 5503) 3. The site is to be managed according to this Plan, with particular 3 reference to potentially contaminating materials. 4. Noise, dust, and odour pollution is to be monitored and managed to 4 reduce any significant effect the operation of the site has on the surrounding land uses. 5. Dewatering of the lagoons to be carefully monitored and lime 4 stabilization of sludge employed as required 6. All sludge and soil in the area of the lagoons to be adequately tested and classified prior to management on site or transport off site 7. All transport and disposal of residual wastewater by licensed contractors 4 to approved facilities with adequate chain of custody 8. All transport and disposal of residual sludge by licensed contractors to 4 approved facilities with adequate chain of custody 9. Maintain a complaints register including but not limited to, any 5 complaints regarding noise, dust, odour or potentially contaminating issues.

9

WASTEWATER LAGOONS – DECOMMISSIONING MANAGEMENT PLAN

Appendix 1 – Site Plans (Aldanmark)

10

WASTEWATER LAGOONS – DECOMMISSIONING MANAGEMENT PLAN

11

24/09/19

Mark Kukola PhilpLighton Architects 49 Sandy Bay Road Sandy Bay TAS 7005

RE: Great Lake Hotel – Proposed Water Treatment System

Mark, following our discussions regarding the water treatment system at the property I can provide the following additional information.

I have held discussions around the required specifications of the system with Nigel Vincent from water solutions Tasmania. A copy of the water quality results is attached, which indicates that the water quality is generally good and only requires filtration, minor pH correction and disinfection. As a result, he has provided the following information regarding the recommended filtration and treatment. • pH correction – a pH neutralising system is recommended to minimise copper corrosion (eg two NTS4000 cylinders in series) • General filtration – a general twin filter arrangement would be recommended to remove fine suspended sediment and organic material which can affect taste and odour (eg EM2 series) • Disinfection – to remove bacteria a UV filter is recommended to ensure adequate health standards (eg puretec radfire RI series commercial filters) • The filtration and disinfection will require fine tuning according to the flow rates and pumping arrangement as detailed below • A pump system will be required to deliver clean potable water to the building with a maximum estimated flow rate requirement (From Aldanmark) of 5.8L/Sec or approximately 350lpm. • To accommodate the peak flow rate a series of variable speed pumps are recommended, and a system such a DAB Esybox 3 pump arrangement capable of 360lpm would be suitable

I have attached copies of the water test results and the product information to this letter and I would nominate Water Solutions Tasmania as the preferred subcontractor.

Kind regards,

Dr John Paul Cumming B.Agr.Sc (hons) PhD CPSS GAICD Environmental and Engineering Soil Scientist

Geo-Environmental Solutions Pty Ltd. 29 Kirksway Place Battery Point 7004. Ph 6223 1839. 0 0.00 True

Environmental CERTIFICATE OF ANALYSIS Work Order : EM1912087 Page : 1 of 4 Client : GEO-ENVIRONMENTAL SOLUTIONS Laboratory : Environmental Division Melbourne Contact : DR JOHN PAUL CUMMING Contact : Shirley LeCornu Address : 29 KIRKSWAY PLACE Address : 4 Westall Rd Springvale VIC Australia 3171 BATTERY POINT TASMANIA, AUSTRALIA 7004 Telephone : +61 03 6223 1839 Telephone : +6138549 9630 Project : Great Lake Date Samples Received : 30-Jul-2019 14:00 Order number : Date Analysis Commenced : 30-Jul-2019 C-O-C number : ---- Issue Date : 06-Aug-2019 15:35 Sampler : JOHN PAUL CUMMING Site : ---- Quote number : EN/222 No. of samples received : 3 No. of samples analysed : 3 This report supersedes any previous report(s) with this reference. Results apply to the sample(s) as submitted. This document shall not be reproduced, except in full. This Certificate of Analysis contains the following information: l General Comments l Analytical Results Additional information pertinent to this report will be found in the following separate attachments: Quality Control Report, QA/QC Compliance Assessment to assist with Quality Review and Sample Receipt Notification. Signatories This document has been electronically signed by the authorized signatories below. Electronic signing is carried out in compliance with procedures specified in 21 CFR Part 11. Signatories Position Accreditation Category Bronwyn Sheen Assistant Laboratory Manager WRG Subcontracting, Springvale, VIC Dilani Fernando Senior Inorganic Chemist Melbourne Inorganics, Springvale, VIC Nikki Stepniewski Senior Inorganic Instrument Chemist Melbourne Inorganics, Springvale, VIC

R I G H T S O L U T I O N S | R I G H T P A R T N E R Page : 2 of 4 Work Order : EM1912087 Client : GEO-ENVIRONMENTAL SOLUTIONS Project : Great Lake General Comments

The analytical procedures used by the Environmental Division have been developed from established internationally recognized procedures such as those published by the USEPA, APHA, AS and NEPM. In house developed procedures are employed in the absence of documented standards or by client request. Where moisture determination has been performed, results are reported on a dry weight basis. Where a reported less than (<) result is higher than the LOR, this may be due to primary sample extract/digestate dilution and/or insufficient sample for analysis.

Where the LOR of a reported result differs from standard LOR, this may be due to high moisture content, insufficient sample (reduced weight employed) or matrix interference.

When sampling time information is not provided by the client, sampling dates are shown without a time component. In these instances, the time component has been assumed by the laboratory for processing purposes. Where a result is required to meet compliance limits the associated uncertainty must be considered. Refer to the ALS Contact for details.

Key : CAS Number = CAS registry number from database maintained by Chemical Abstracts Services. The Chemical Abstracts Service is a division of the American Chemical Society. LOR = Limit of reporting ^ = This result is computed from individual analyte detections at or above the level of reporting ø = ALS is not NATA accredited for these tests. ~ = Indicates an estimated value. l EA010-P: Electrical Conductivity @ 25°C was analysed by manual method (EA010). l E.Coli & FC (MM696) is conducted by ALS Scoresby NATA accreditation no. 992, site no. 989. NATA accreditation does not cover performance of this method. l TC & E.Coli (MM698) is conducted by ALS Scoresby NATA accreditation no. 992, site no. 989. NATA accreditation does not cover performance of this method. l ED037-P: Poor duplicate precision observed carbonate alkalinity for sample #1. Insufficient sample remains to confirm results. l Ionic balances were calculated using: major anions - chloride, alkalinity and sulfate; and major cations - calcium, magnesium, potassium and sodium. l ED045G: The presence of thiocyanate can positively contribute to the chloride result, thereby may bias results higher than expected. Results should be scrutinised accordingly. l EA016: Calculated TDS is determined from Electrical conductivity using a conversion factor of 0.65. l HPC @ 22C and 36C (MM524) is conducted by ALS Scoresby NATA accreditation no. 992, site no. 989. l E.coli & Total Coliforms by MPN (MM514) is conducted by ALS Scoresby NATA accreditation no. 992, site no. 989. l Sodium Adsorption Ratio (where reported): Where results for Na, Ca or Mg are

Sub-Matrix: WATER Client sample ID S Tank N Tank Bore ------(Matrix: WATER) Client sampling date / time 29-Jul-2019 00:00 29-Jul-2019 00:00 29-Jul-2019 00:00 ------Compound CAS Number LOR Unit EM1912087-001 EM1912087-002 EM1912087-003 ------Result Result Result ------EA005P: pH by PC Titrator pH Value ---- 0.01 pH Unit 6.69 6.43 7.12 ------EA010P: Conductivity by PC Titrator Electrical Conductivity @ 25°C ---- 1 µS/cm 49 47 67 ------EA016: Calculated TDS (from Electrical Conductivity) Total Dissolved Solids (Calc.) ---- 1 mg/L 32 30 44 ------EA045: Turbidity Turbidity ---- 0.1 NTU ---- 2.2 3.9 ------ED037P: Alkalinity by PC Titrator Hydroxide Alkalinity as CaCO3 DMO-210-001 1 mg/L <1 <1 <1 ------Carbonate Alkalinity as CaCO3 3812-32-6 1 mg/L <1 <1 <1 ------Bicarbonate Alkalinity as CaCO3 71-52-3 1 mg/L 12 11 25 ------Total Alkalinity as CaCO3 ---- 1 mg/L 12 11 25 ------ED041G: Sulfate (Turbidimetric) as SO4 2- by DA Sulfate as SO4 - Turbidimetric 14808-79-8 1 mg/L <1 <1 2 ------ED045G: Chloride by Discrete Analyser Chloride 16887-00-6 1 mg/L 7 8 6 ------ED093F: Dissolved Major Cations Calcium 7440-70-2 1 mg/L 2 3 5 ------Magnesium 7439-95-4 1 mg/L 1 1 2 ------Sodium 7440-23-5 1 mg/L 3 3 3 ------Potassium 7440-09-7 1 mg/L <1 <1 <1 ------EG020T: Total Metals by ICP-MS Aluminium 7429-90-5 0.01 mg/L 0.11 0.14 0.12 ------Antimony 7440-36-0 0.001 mg/L <0.001 <0.001 <0.001 ------Arsenic 7440-38-2 0.001 mg/L <0.001 <0.001 <0.001 ------Barium 7440-39-3 0.001 mg/L 0.001 0.002 0.002 ------Cadmium 7440-43-9 0.0001 mg/L <0.0001 <0.0001 <0.0001 ------Chromium 7440-47-3 0.001 mg/L <0.001 <0.001 <0.001 ------Copper 7440-50-8 0.001 mg/L 0.001 <0.001 0.002 ------Nickel 7440-02-0 0.001 mg/L <0.001 <0.001 <0.001 ------Lead 7439-92-1 0.001 mg/L <0.001 <0.001 <0.001 ------Zinc 7440-66-6 0.005 mg/L 0.017 0.015 0.007 ------Manganese 7439-96-5 0.001 mg/L 0.001 0.002 0.004 ------Molybdenum 7439-98-7 0.001 mg/L <0.001 <0.001 <0.001 ------Page : 4 of 4 Work Order : EM1912087 Client : GEO-ENVIRONMENTAL SOLUTIONS Project : Great Lake Analytical Results

Sub-Matrix: WATER Client sample ID S Tank N Tank Bore ------(Matrix: WATER) Client sampling date / time 29-Jul-2019 00:00 29-Jul-2019 00:00 29-Jul-2019 00:00 ------Compound CAS Number LOR Unit EM1912087-001 EM1912087-002 EM1912087-003 ------Result Result Result ------EG020T: Total Metals by ICP-MS - Continued Selenium 7782-49-2 0.01 mg/L <0.01 <0.01 <0.01 ------Silver 7440-22-4 0.001 mg/L <0.001 <0.001 <0.001 ------Boron 7440-42-8 0.05 mg/L 0.05 <0.05 <0.05 ------Iron 7439-89-6 0.05 mg/L 0.06 0.10 0.18 ------EG035T: Total Recoverable Mercury by FIMS Mercury 7439-97-6 0.0001 mg/L <0.0001 <0.0001 <0.0001 ------EN055: Ionic Balance ø Total Anions ---- 0.01 meq/L 0.44 0.44 0.71 ------ø Total Cations ---- 0.01 meq/L 0.31 0.36 0.54 ------MM524: Heterotrophic (Total) Plate Count @ 22C and 36C Heterotrophic Plate Count (22°C) ---- 1 orgs/mL 530 590 0 ------Heterotrophic Plate Count (36°C) ---- 1 orgs/mL 120 160 0 ------MM696: E. coli & Faecal Coliforms by MF (Chromogenic) Faecal Coliforms ---- 1 CFU/100mL 0 0 0 ------MM698: Total Coliforms and E. coli by MF (Chromogenic) Escherichia coli ---- 1 CFU/100mL 0 0 160 ------Total Coliforms by MF ---- 1 CFU/100mL 0 0 70 ------JET - JET INOX - EUROINOX M-P PREPARED CENTRIFUGAL ELECTRIC PUMPS

TECHNICAL DATA Operating range: from 0.4 to 10.5 m3/h with head up to 62 metres. Liquid quality requirements: clean, free from solid or abrasive contaminants, non-viscous, non-aggressive, uncrystallised and chemically neutral, close to the properties of water. JET M-P Liquid temperature range: from 0°C to +35°C for domestic use (EN 60335-2-41). For other use: from 0°C to +40°C Maximum ambient temperature: +40°C Maximum operating pressure: 8 bar (800 kPa) Installation: fixed in a horizontal position. Special executions on request: different frequencies and/or voltage. Motor protection rating: IP 44 Terminal block protection rating: IP 55 JET 151-251 T-P Insulation class: F

Standard input voltage: single phase 220/240 V / 50 Hz CENTRIFUGAL PUMPS SELF-PRIMING AND MULTISTAGE three phase 230/400 V - 50 Hz

APPLICATIONS Self priming centrifugal pump with excellent suction capacity even in the presence of air bubbles. Suitable for pumping water with low levels of sandy impurities. Especially used in domestic water supply installations. Suitable for small farms and gardening, small scale industrial services and where self priming is necessary.

CONSTRUCTIONAL FEATURES OF THE PUMP Pump body in cast iron for jet pumps and in stainless steel for the jetinox and euroinox pumps Motor support in die cast aluminium. Impeller, diffuser, venturi tube and sand guard in technopolymer Stainless steel wear ring. Carbon/ceramic mechanical seal. SINGLE PHASE VERSION: electric pump set up with pressure gauge, pressure switch, power cord with plug and three-way brass fitting for use when connecting to a tank THREE-PHASE VERSION: electric pumpa set up with pressure gauge, pressure switch, remote overload protection and three-way brass fitting for use when connecting to a tank

CONSTRUCTIONAL FEATURES OF THE MOTOR Asynchronous type, closed, with external air cooling. Rotor mounted on oversized greased-for-life ball bearings, to guarantee low noise and long life. Incorporated thermo-amperometric protection and permanently inserted capacitor in the single phase version. It is recommended to use overload protection for three phase motor protection, in compliance with current legislation. Manufactured pursuant to CEI 2-3 and CEI 61-69 (EN 60335-2-41).

MATERIALS 1 4 16

N° PARTS * MATERIALS

200 UNI ISO 185 CAST IRON (FOR JET) 1 PUMP BODY AISI 304 STAINLESS STEEL (FOR JETINOX AND EUROINOX) EUROINOX 3 FRAME DIE CAST ALUMINIUM 7 28 3 4 IMPELLER TECHNOPOLYMER A 1 4 28 7 AISI 416 STAINLESS STEEL X12 CrS13 - 7 SHAFT WITH ROTOR UNI 6900/71

16 MECHANICAL SEAL CARBON/CERAMIC

28 OR GASKET NBR RUBBER

160 VENTURI DIFFUSER NOZZEL GROUP TECHNOPOLYMER A

* In contact with liquid JET - JETINOX 160 16 3

DAB PUMPS reserve the right to make modifications without prior notice 59 JET 62-82-102-112-132-MP - CENTRIFUGAL ELECTRIC PUMPS FOR DOMESTIC WATER SUPPLY Liquid temperature range pumped: from 0 °C to +35 °C - Maximum ambient temperature: +40°C

0 2 4 6 8 10 12 Q US gpm 0 2 4 6 8 10 12 14 16 Q US gpm 0 2 4 6 8 10 Q IMP gpm 0 2 4 6 8 10 12 14 Q IMP gpm P H H P H kPa m H kPa m ft 50 ft 400 40 120 160 400 40 300 30 100 120 JET 62 JET 82 80 300 30 100

200 20 80 Hs 9 60 8 200 20 Hs 9 60 7 8 6 40 5 4 7 6 100 10 3 5 40 2 100 10 4 20 3 2 20

0 0 0 0 0 0 3 3 0 0,5 1 1,5 2 2,5 3 Q m /h 0 0,5 1 1,5 2 2,5 3 3,5 4 Q m /h 0 0,2 0,4 0,6 0,8 Q l/s 0 0,2 0,4 0,6 0,8 1 Q l/s 0 10 20 30 40 50 Q l/min 0 10 20 30 40 50 60 Q l/min

0 2 4 6 8 10 12 14 16 Q US gpm 0 2 4 6 8 10 12 14 16 Q US gpm SELF-PRIMING AND MULTISTAGE CENTRIFUGAL PUMPS SELF-PRIMING AND MULTISTAGE 0 2 4 6 8 10 12 14 Q IMP gpm 0 2 4 6 8 10 12 14 Q IMP gpm P H P H kPa m H kPa m H 50 ft ft 600 60 200 160 400 40 500 50 160 JET 102 120 JET 112 400 300 100 40 30 120 Hs 9 80 Hs 9 8 8 300 30 7 7 200 20 6 6 60 80 5 5 4 4 200 20 3 3 2 2 40 100 10 40 100 10 20

0 0 0 0 0 0 0 0,5 1 1,5 2 2,5 3 3,5 4 Q m3/h 0 0,5 1 1,5 2 2,5 3 3,5 4 Q m3/h 0 0,2 0,4 0,6 0,8 1 Q l/s 0 0,2 0,4 0,6 0,8 1 Q l/s 0 10 20 30 40 50 60 Q l/min 0 10 20 30 40 50 60 Q l/min

A 0 2 4 6 8 10 12 14 16 18 20 22 24 Q US gpm D 0 2 4 6 8 10 12 14 16 18 20 Q IMP gpm A1 P H H C kPa m ft 140 DNM 400 40 JET 132 120 DNM

300 30 100

80

200 20 60 H

Hs 9 H1 H2 DNA 8 7 40 6 H3 100 10 5 4 3 20 2 0 0 0 E F I 0 1 2 3 4 5 Q m3/h 0 0,2 0,4 0,6 0,8 1 1,2 1,4 Q l/s G 0 10 20 30 40 50 60 70 80 90 Q l/min B

The performance curves are based on kinematic viscosity values = 1 mm2/s and density equivalent to 1000 kg/m3. Curve tolerance according to ISO 9906.

ELECTRICAL DATA MODEL POWER SUPPLY P1 MAX P2 NOMINAL In CAPACITOR 50 Hz KW kW HP A μF Vc JET 62 MP 1x220-400 V ~ 0.72 0.44 0.6 3.12 12.5 450 JET 82 MP 1x220-400 V ~ 0.85 0.6 0.8 3.8 12.5 450 JET 102 MP 1x220-400 V ~ 1.13 0.75 1 5.1 16 450 JET 112 MP 1x220-400 V ~ 1.4 1 1.36 6.2 25 450 JET 132 MP 1x220-400 V ~ 1.49 1 1.36 6.6 25 450

PACK DIMENSIONS GROSS MODEL A A1 B C D E F G I Ø H H1 H2 H3 I Ø DNA DNM VOLUME WEIGHT GAS GAS L/A L/B H (mc) Kg JET 62 MP 395 390 263 108 177 192 14 111 – 239 209 193 144 9 1” 1” 440 295 235 0.031 11.9 JET 82 MP 395 390 263 108 177 192 14 111 – 239 209 193 144 9 1” 1” 440 295 235 0.031 12.1 JET 102 MP 414 390 263 108 177 192 14 111 – 239 209 203 144 9 1” 1” 440 295 235 0.031 13.9 JET 112 MP 414 390 263 108 177 192 14 111 – 239 209 203 144 9 1” 1” 440 295 235 0.031 14.9 JET 132 MP 414 390 263 108 177 192 14 111 – 239 209 203 144 9 1” 1” 440 295 235 0.031 14.9

DAB PUMPS reserve the right to make modifications without prior notice 60 JET 200-300-151-251-MP - CENTRIFUGAL ELECTRIC PUMPS FOR DOMESTIC WATER SUPPLY Liquid temperature range pumped: from 0 °C to +35 °C - Maximum ambient temperature: +40°C

0 5 10 15 20 25 30 35 40 45 50 Q US gpm 0 5 10 15 20 25 30 35 40 Q IMP gpm P H H kPa m 50 ft JET 300 JET 200 160 400 40 120

300 30 100

80 200 20 60

Hs 8 7 6 40 100 10 5 4 3 20 2 1

0 0 0 0 1 2 3 4 5 6 7 8 9 10 11 12 Q m3/h 0 0,5 1 1,5 2 2,5 3 Q l/s 0 20 40 60 80 100 120 140 160 180 200 Q l/min

0 2 4 6 8 10 12 14 16 18 20 22 24 Q US gpm 0 5 10 15 20 25 30 35 40 Q US gpm 0 2 4 6 8 10 12 14 16 18 20 Q IMP gpm 0 5 10 15 20 25 30 Q IMP gpm P P H H H H kPa kPa m m ft ft 200 200 600 60 600 60 SELF-PRIMING AND MULTISTAGE CENTRIFUGAL PUMPS SELF-PRIMING AND MULTISTAGE

500 500 50 160 50 160 JET 151 JET 251 400 40 400 40 120 120

300 30 300 30 80 80 Hs 8 200 20 200 20 Hs 8 7 6 7 5 6 4 40 5 40 100 10 100 10 4 3 2 3 2 1 1 0 0 0 0 0 0 0 1 2 3 4 5 Q m3/h 0 1 2 3 4 5 6 7 8 9 Q m3/h 0 0,2 0,4 0,6 0,8 1 1,2 1,4 Q l/s 0 0,5 1 1,5 2 2,5 Q l/s 0 10 20 30 40 50 60 70 80 90 Q l/min 0 20 40 60 80 100 120 140 Q l/min

The performance curves are based on kinematic viscosity values = 1 mm2/s and density equivalent to 1000 kg/m3. Curve tolerance according to ISO 9906.

A D A1 C DNM DNM H H1 H2 DNA H3

E F I G B

ELECTRICAL DATA MODEL POWER SUPPLY P1 MAX P2 NOMINAL In CAPACITOR 50 Hz KW kW HP A μF Vc JET 200 MP 1x220-240 V ∼ 2 1.5 2 9 31.5 450 JET 200 TP 3x400 V ∼ 2 1.5 2 3.9 – – JET 300 MP 1x220-240 V ∼ 2.7 2.2 3 12 40 450 JET 300 TP 3x400 V ∼ 2.7 2.2 3 8.5-4.9 – – JET 151 MP 1x220-240 V ∼ 1.6 1.1 1.5 7.2 31.5 450 JET 151 TP 3x400 V ∼ 1.6 1.1 1.5 5.2-3 – – JET 251 MP 1x220-240 V ∼ 2.2 1.85 2.5 10 40 450 JET 251 TP 3x400 V ∼ 2.2 1.85 2.5 6.9-4 – –

PACK DIMENSIONS GROSS MODEL A A1 B C D E F G I Ø H H1 H2 H3 I DNA DNM VOLUME WEIGHT GAS GAS L/A L/B H (mc) Kg

1 1 JET 200 MP 521 – 294 151 – 282 20 160 11 275 175 – – 11 1 /2” 1 /4” 600 236 267 0.038 27.5 1 1 JET 200 TP 521 – 294 151 – 282 20 160 11 275 175 – – 11 1 /2” 1 /4” 600 236 267 0.038 28 1 1 JET 300 MP 595 – 294 151 – 282 20 160 11 275 175 – – 11 1 /2” 1 /4” 660 236 267 0.042 31.5 1 1 JET 300 TP 521 – 294 151 – 282 20 160 11 275 175 – – 11 1 /2” 1 /4” 600 236 267 0.038 30 1 JET 151 MP 558 – 290 220 – 367 15 145 11 305 165 – – 11 1 /4” 1” 600 236 267 0.038 31.5 1 JET 151 TP 558 – 290 220 – 367 15 145 11 305 165 – – 11 1 /4” 1” 600 236 267 0.038 33 1 JET 251 MP 632 – 290 220 – 367 15 145 11 305 165 – – 11 1 /4” 1” 645 236 267 0.040 36 1 JET 251 TP 558 – 290 220 – 367 15 145 11 305 165 – – 11 1 /4” 1” 600 236 267 0.038 34

DAB PUMPS reserve the right to make modifications without prior notice 61 JETINOX 82-102 -112 -132-MP - CENTRIFUGAL ELECTRIC PUMPS FOR DOMESTIC WATER SUPPLY Liquid temperature range pumped: from 0 °C to +35 °C - Maximum ambient temperature: +50°C

0 2 4 6 8 10 12 14 16 Q US gpm 0 2 4 6 8 10 12 14 16 Q US gpm 0 2 4 6 8 10 12 14 Q IMP gpm 0 2 4 6 8 10 12 14 Q IMP gpm P H P H kPa m H kPa m H 50 ft 50 ft

160 160 400 40 400 40 120 JET 102 120 JETINOX 82 300 30 100 300 30 100 Hs 9 80 80 8 7 200 20 Hs 9 200 20 60 6 60 8 5 4 3 7 6 5 40 2 40 100 10 4 100 10 3 2 20 20

0 0 0 0 0 0 0 0,5 1 1,5 2 2,5 3 3,5 4 Q m3/h 0 0,5 1 1,5 2 2,5 3 3,5 4 Q m3/h 0 0,2 0,4 0,6 0,8 1 Q l/s 0 0,2 0,4 0,6 0,8 1 Q l/s 0 10 20 30 40 50 60 Q l/min 0 10 20 30 40 50 60 Q l/min

0 2 4 6 8 10 12 14 16 Q US gpm 0 2 4 6 8 10 12 14 16 18 20 22 24 Q US gpm

SELF-PRIMING AND MULTISTAGE CENTRIFUGAL PUMPS SELF-PRIMING AND MULTISTAGE 0 2 4 6 8 10 12 14 16 18 20 Q IMP gpm 0 2 4 6 8 10 12 14 Q IMP gpm P P H H H kPa m H kPa m ft ft 600 60 200 140 400 40 JETINOX 132 120 500 50 160 JETINOX 112 300 30 100 400 40 120 80 9 300 Hs 8 30 200 7 6 20 80 60 5 4 Hs 9 200 20 3 2 8 7 6 40 40 100 10 5 100 10 4 3 20 2 0 0 0 3 0 0 0 0 0,5 1 1,5 2 2,5 3 3,5 4 Q m /h 0 1 2 3 4 5 Q m3/h 0 0,2 0,4 0,6 0,8 1 Q l/s 0 0,2 0,4 0,6 0,8 1 1,2 1,4 Q l/s 0 10 20 30 40 50 60 Q l/min 0 10 20 30 40 50 60 70 80 90 Q l/min

The performance curves are based on kinematic viscosity values = 1 mm2/s and density equivalent to 1000 kg/m3. Curve tolerance according to ISO 9906.

A D C DNM H H1 DNA H2

E F I G L B

ELECTRICAL DATA MODEL POWER SUPPLY P1 MAX P2 NOMINAL In CAPACITOR 50 Hz KW kW HP A μF Vc JETINOX 82 MP 1x220-240 V ~ 0.85 0.6 0.8 3.8 12.5 450 JETINOX 102 MP 1x220-240 V ~ 1.13 0.75 1 5.1 16 450 JETINOX 112 MP 1x220-240 V ~ 1.4 1 1.36 6.2 25 450 JETINOX 132 MP 1x220-240 V ~ 1.49 1 1.36 6.6 25 450

PACK DIMENSIONS GROSS MODEL A B C D E F G H H1 H2 I L DNA DNM VOLUME WEIGHT GAS GAS L/A L/B H (mc) Kg JETINOX 82 MP 406 232 122 145 207 14 111 276 244 144 9 174 1” 1” 450 276 320 0.031 13.6 JETINOX 102 MP 424 232 122 145 207 14 111 276 244 144 9 174 1” 1” 450 276 320 0.031 14.8 JETINOX 112 MP 424 232 122 145 207 14 111 276 244 144 9 174 1” 1” 450 276 320 0.031 15.8 JETINOX 132 MP 424 232 122 145 207 14 111 276 244 144 9 174 1” 1” 450 276 320 0.031 15.8

DAB PUMPS reserve the right to make modifications without prior notice 62 EUROINOX 30-50-80-MP -CENTRIFUGAL ELECTRIC PUMPS FOR DOMESTIC WATER SUPPLY Liquid temperature range pumped: from 0 °C to +35 °C - Maximum ambient temperature: +40°C

0 2 4 6 8 10 12 14 Q US gpm 0 2 4 6 8 10 12 14 16 18 20 Q US gpm

0 2 4 6 8 10 12 Q IMP gpm 0 2 4 6 8 10 12 14 16 Q IMP gpm P H H P H H kPa m ft kPa m ft 55 180 260 700 70 500 50 EUROINOX 40/30 160 45 600 60 EUROINOX 50/50 200 140 400 40 500 50 EUROINOX 30/30 120 160 35 EUROINOX 40/50

300 30 100 400 40 EUROINOX 25/30 120 25 80 EUROINOX 30/50 300 30 200 20 *EUROINOX 15/30 60 80 15 200 20

*EUROINOX 20/50 CENTRIFUGAL PUMPS SELF-PRIMING AND MULTISTAGE 40 100 10 40 100 10 20 5

0 0 0 0 0 0 0 0,5 1 1,5 2 2,5 3 3,5 Q m3/h 0 1 2 3 4 5 Q m3/h NPSH NPSH NPSH NPSH kPa m kPa m ft ft 40 30 3 4 12 8 30 10 20 2 0 4 8 12 16 20 24 28 Q US gpm 3 8 10 4 2 1 0 4 8 12 16 20 24 Q IMP gpm 6 P0 H0 0H 10 1 4 3 0 1 2 3 4 5 3 kPa m0 0,511,5 2 2,5 3 3,5 Q m ft/h Q m /h 550 0,2 0,4 0,6 0,8 1 Q l/s180 0 0,2 0,4 0,6 0,8 1 1,2 1,4 Q l/s 0 EUROINOX10 40/8020 30 40 50 60 Q l/min 0 10 20 30 40 50 60 70 80 Q l/min 500 50 160 45 140 400 40 EUROINOX 30/80 120 35

300 30 100

25 80

200 20 60 15 40 100 10

20 5

0 0 0 0 1 2 3 4 5 6 7 Q m3/h NPSH NPSH kPa m 2 ft 3 The performance50 5 curves are based on kinematic viscosity values = 1 mm /s and density16 equivalent to 1000 kg/m . Curve tolerance according to ISO 9906. 40 4 12 30 3 ELECTRICAL DATA 8 20 MODEL2 POWER SUPPLY P1 MAX P2 NOMINAL In CAPACITOR 3 0 1 2 3 50 Hz4 5 6 KW 7 Q m /h kW HP A μF Vc 0 0,4 0,8 1,2 1,6 2 Q l/s 1x220-240 V ∼ 0.88 0.55 0.75 3.9 12.5 450 EUROINOX 40/300 MP 20 40 60 80 100 120 Q l/min EUROINOX 30/50 MP 1x220-240 V ∼ 0.88 0.55 0.75 3.9 12.5 450 EUROINOX 40/50 MP 1x220-240 V ∼ 1.2 0.8 1.1 5.3 25 450 EUROINOX 30/80 MP 1x220-240 V ∼ 1.2 0.75 1 5.3 25 450 EUROINOX 40/80 MP 1x220-240 V ∼ 1.48 1 1.36 6.3 25 450

GROSS MODEL A B C E F G I Ø H H1 H2 DNA DNM WEIGHT GAS GAS Kg EUROINOX 40/30 MP 439 226 108 241 13.5 111 9 300 268 143 1” 1” 15.5 EUROINOX 30/50 MP 384 226 108 186 13.5 111 9 300 268 143 1” 1” 11.4 EUROINOX 40/50 MP 458 226 108 241 13.5 111 9 300 268 143 1” 1” 14.5 EUROINOX 30/80 MP 458 226 108 241 13.5 111 9 300 268 143 1” 1” 14.5 EUROINOX 40/80 MP 458 226 108 241 13.5 111 9 300 268 143 1” 1” 17.5

DAB PUMPS reserve the right to make modifications without prior notice 63 EM2 Series

A

B

A B (Depth)

EM2-60 390 mm 465 mm 200

EM2-75 390 mm 465 mm 200

EM2-110 390 mm 730 mm 200

EM2-150 390 mm 730 mm 200

GENERAL INFO DESIGNED FOR RAINWATER SUPPLIES

Whole House Dual Water Filtration Systems

The Puretec EM2 Series filtration systems are the appropriate choice for providing safe, clean, healthy water throughout the house or the office. Providing maximum filtration with minimal flow restriction these high flow systems, ensure that your home is free of sludge and sediment. Some models additionally reduce bad taste and odours.

SPECIFICATIONS

Models: EM2-60 EM2-75 EM2-110 EM2-150

Replacement Cartridges:

Stage 1 PL05MP1 PL20MP1 PL05MP2 PL20MP2

Stage 2 DP10MP1 PX01MP1 DP10MP2 PX01MP2

Max Flow: 60 Lpm 75 Lpm 110 Lpm 150 Lpm

Min/Max Temperature: 0 - 52°C (Protect from freezing)

Min/Max Pressure: 0 - 875 kPa

Connection: 1” BSP [25mm] 1” BSP [25mm] 1 ½” BSP [40mm] 1 ½” BSP [40mm]

Warranty: 10 years^

Important Note: Use only genuine Puretec replacement cartridge. ^Warranty is 10 years parts, 1 year parts and labour, excludes cartridges.

For more information contact your local stockist or visit us at puretecgroup.com Australia 1300 140 140 | New Zealand 0800 130 140 Page 1 of 2

FEBRUARY.2019 EM2 Series

FEATURES & BENEFITS

• Able to operate on gravity feed pressure • Designed specifically for rain water • Can also be used on mains, river, dam and bore water • Dual stage filtration for longer filter life • Washable sediment cartridge that removes dirt, rust and algae in water • Suitable for UV system pre-filtration • 10 Year Warranty

ADDITIONAL INFORMATION

Whole House Protection These systems provide peace-of-mind throughout the house protecting appliances from sediment and sludge build-up and extending the service life of ceramic disc tapware. The EM2-60 and EM2-110 additionally reduce taste, odours and chemicals. Enjoy purified water at every outlet in the house.

Easy To Maintain, No Power Required The Puretec EM2 Series systems are designed for the budget-conscious householder, giving good general purpose filtration. These systems do not require power to operate, and are easily maintained yourself by simply replacing the filter cartridges.

Longer Filter Life The Ecotrol™ EM2 incorporates Puretec’s long life filter technology, so you can go longer between filter replacements, and comes with our 10 Year Platinum Protection Warranty^.

For more information contact your local stockist or visit us at puretecgroup.com Australia 1300 140 140 | New Zealand 0800 130 140 Page 2 of 2

FEBRUARY.2019 NTS Series

A

B

NTS Series A B

NTS2000 245 mm 1,400 mm

NTS3000 270 mm 1,500 mm

NTS4000 320 mm 1,600 mm

NTS70-C 450 mm 2,100 mm

GENERAL INFO NEUTRALISING TREATMENT SYSTEMS

The Puretec NTS Series neutralising treatment systems are designed to correct the pH (acidity) of the water supply. Acidic water can cause corrosion of pipe-work and seals in the water line, causing costly damage.

The Puretec NTS Series reduces green/blue staining commonly noticed on plumbing fixtures meaning that corrosion of the pipe-work has possibly started. These units effectively utilise a calcium carbonate media, which slowly dissolves into the water to lift the pH, protecting the plumbing system from corrosion.

Knowing the pH level of your water can help you prevent secondary effects. If the acidity of your water is too high, corrosion can leach out lead and copper from pipes and plumbing as well as damage your water supply system and water heater.

SPECIFICATIONS FEATURES & BENEFITS

• Neutralise potentially corrosive water with a low pH Model NTS Series • Utilise calcium carbonate media to lift the pH pH range 5.0 - 7.0 • Slow reacting for controlled pH correctors Operating Pressures 200 - 600 kPa • Media fll port for easy maintenance Operating Temperature Ranges 5 - 40°C • Utilise calcium carbonate media to lift the pH Inlet/Outlet Fitting Connections 1” Male Inlet/Outlet • 1” connections means minimum pressure loss • No Power required

For more information contact your local stockist or visit us at puretecgroup.com Australia 1300 140 140 | New Zealand 0800 130 140 Page 1 of 2

JULY.2018 NTS Series

SYSTEM SPECIFICATIONS AND PERFORMANCE DATA

Max Flow Ordering Code Application Backwash Service Flow Lpm Lpm

NTS2000 Small to medium building / residence in/out head 20 70

NTS3000 Medium building / residence in/out head 40 90

NTS4000 Medium to large building / residence in/out head 60 100

NTS70-C Commercial building / residence in/out head 70 150

Operating Conditions: 1. Neutralising media is consumed according to pH level and needs to be replaced periodically. Speak with one of the Puretec specialists to confrm this product selection.

For more information contact your local stockist or visit us at puretecgroup.com Australia 1300 140 140 | New Zealand 0800 130 140 Page 2 of 2

JULY.2018 RI Series (Commercial)

RI-6K RI-10K RI-17K

See dimensions on page 2

GENERAL INFO COMMERCIAL ULTRAVIOLET WATER TREATMENT SYSTEMS

Looking for a feature-laden premium UV system, then Puretec Radfire’s RI Series of UV systems should be your choice. In looking at this line, one easily sees how this product is truly different from everything else in the market. Puretec Radfire’s state-of-the-art controller is a constant current electronic power source housed in a splash-proof case and comes standard with a “future-proof” expandability port for future upgrades or options. A colour user interface allows for easy visual identification of remaining lamp life and any error or fault codes.

Rugged stainless steel, single-end reactors come with an integral port to allow for a future upgrade to a UV monitored system. If a monitor is not required, an integral visual glow plug is provided as an extra way to ensure that your UV lamp is illuminated. The single-end design allows for lamp change without the need to drain the reactor chamber. Reliable, industry proven, high quality low pressure (LP) coated UV lamps are used offering a consistent output over their life.

Typical POE Installations OPTIONAL UPGRADE MODULES FEATURES & BENEFITS Typical POE Installations Optional Upgrade Modules Optional Upgrade Modules • Colour user interface with full diagnostics and warnings Typical POE InstallationsCOLD WATER HOT WATER Solenoid Connection PIPES PIPES OptionalSolenoid Module Upgrade Modules COLD WATER HOT WATER PIPES PIPES Solenoid ModuleUsed to power a remote normally closed solenoid • “Future-proof” expandability port for future upgrades and options COLD WATER HOT WATER Used to power a remote normally closed solenoid PIPES PIPES Solenoid ModulevalveUsed to(not power included). a remote Solenoid normally will closeclosed on solenoid lamp • Axial flow, 316 stainless steel reactor, polished reactors with integral valvevalve (not (notincluded). included). Solenoid Solenoid will close will on lamp close on lamp Usedfailure to or power when alow remote UV conditions normally closedare detected solenoid by sensor port to allow for sensor upgradeability in the future CONT ROLLER valvethefailurefailure sensor. (not or when included). orAvailable when low UV Solenoid inlow conditions110V. UV (MOD-SOL1) will conditions closeare detected on or lamp are 230V. by detected by CONT ROLLER failure(MOD-SOL2)thethe sensor. orsensor. when Available low Order UV in conditions 110V.RI-SOL (MOD-SOL1) are detected or 230V. by • Universal input, constant current electronic controller (one controller BY-PASS ASSEMB LY * BY-PASS ASSEMB LY * CONT ROLLER BY-PASS ASSEMB LY * the(MOD-SOL2) sensor. Available in 110V. (MOD-SOL1) or 230V. BY-PASS ASSEMB LY * BY-PASS for all systems) in a splash-proof case SOLENOID BY-PASS ASSEMB LY * ASSEMB LY * VALVE * (MOD-SOL2) SEDIMENT SOLENOID BY-PASS ASSEMB LY * BY-PASS FILTER * VALVE * 4-20m Module ASSEMB LY * BY-PASS ASSEMB LY * Volt Free Connection • 10,000 hour lamp life SEDIMENT OPTIONAL FILTER * CARBON SOLENOID 4-20m Module FILTER VALVE * Used for signal transfer to a remote device such as a OPTIONAL WATER SEDIMENT CARBON METER FILTER * FILTER 4-20m ModuledataUsedUsed logger for signalfor or signal computer. transfer transfer to Order a remote MOD-420 to adevice remote such device as a such WATER OPTIONAL METER SOLENOID CARBON MODULE * data logger or computer. Order MOD-420 FILTER Usedas fora datasignal loggertransfer orto acomputer. remote device Order such RI-VFC as a SOLENOID Solenoid WATER Module LUMINOR METER MODULEE N V I R O N M E N T A L * data logger or computer. Order MOD-420

Solenoid Module LUMINOR SOLENOIDE N V I R O N M E N T A L UV Sensor Module MODULE * TO DRAIN

Solenoid Module LUMINOR E N V I R O N M E N T A L UV Sensor AllowsModule the 254nm UV wavelength to be measured TO DRAIN * OPTIONAL COMPONENT UVUV Sensor Sensor Module andAllowsModule displayed the 254nm via theUV BLACKCOMB-HOwavelength to be 5.0measured contoller.

* OPTIONAL COMPONENT WATER TO DRAIN 5.0 SOFTENER * AllowsandTheAllows displayedsensor the 254nm theplugs via 254nm directlytheUV BLACKCOMB-HOwavelength intoUV thewavelength contollerto be measured contoller. and to be measured WATER * OPTIONAL COMPONENT SOFTENER * andisThe mounted displayedsensor inplugs the via sensordirectlythe BLACKCOMB-HO port into locatedthe contoller on5.0 all contoller. and and displayed5.0 via the Radfire contoller. The sensor WATER is mounted in the sensor port located on all SOFTENER * TheBLACKCOMB-HO sensor plugs directly reactors. into Orderthe contoller RSHO-B3.5 and for allisBLACKCOMB-HO mounted plugsHO systems. directly in the sensor5.0 intoreactors. portthe Orderlocatedcontoller RSHO-B3.5 on alland is for mounted in 5.0 allBLACKCOMB-HO theHO systems. sensor port5.0 reactors. located Order on allRSHO-B3.5 Radfire for reactors. BLACKCOMB-HO5.0 - Equipment Specifications all OrderHO systems. RI-SEN BLACKCOMB-HO5.0 - Equipment Specifications BLACKCOMB-HOBLACKCOMB-HO5.0, Residential Crossover - Equipment UV Systems, Non-Monitored Specifications 5.0 Manufacturer’s Warranty BLACKCOMB-HO , Residential Crossover UV Systems, Non-Monitored Manufacturer’s Warranty BLACKCOMB-HO5.0, Residential Crossover UV Systems, Non-Monitored Model LB5-251 LB5-252 LB5-401 LB5-402 Manufacturer’sFor more information contact your Warrantylocal stockist or visit us at puretecgroup.com Model LB5-251 LB5-252 LB5-401 LB5-402 47 GPM 78 GPM AustraliaLUMINOR 1300 UV 140 systems 140 | New are Zealand covered 0800 by 130 the 140 Page 1 of 2 FlowModel Rate LB5-251 47 GPM LB5-252 LB5-401 78 GPM LB5-402 2 180 lpm 290 lpm LUMINOR UV systems are covered by the (@16mJ/cmFlow Rate ) following warranty: (@16mJ/cm2) 1147180 mGPM lpm3/hr. 1878290 mGPM lpm3/hr. JULY.2019followingLUMINOR warranty: UV systems are covered by the Flow Rate 11 m3/hr. 18 m3/hr. (@16mJ/cm2) 25180 GPM lpm 40290 GPM lpm following warranty: Flow Rate 3 3 REACTORS - Ten (10) year Limited Warranty 112595 mGPM lpm/hr. 1840160 mGPM lpm/hr. (@30mJ/cmFlow Rate 2 ) REACTORS - Ten (10) year Limited Warranty 95 lpm3 160 lpm3 (@30mJ/cm2) 5.725 mGPM/hr. 9.140 mGPM/hr. ELECTRONICS - Three (3) year Limited Warranty Flow Rate REACTORS - Ten (10) year Limited Warranty 5.795 m lpm3/hr. 9.1160 m lpm3/hr. ELECTRONICS - Three (3) year Limited Warranty (@30mJ/cm2) 19 GPM 31 GPM UV LAMPS - One (1) year Limited Warranty Flow Rate 3 3 ELECTRONICS - Three (3) year Limited Warranty 5.71971 mGPM lpm/hr. 9.131120 mGPM lpm/hr. UV LAMPS - One (1) year Limited Warranty (@40mJ/cmFlow Rate 2 ) QUARTZ SLEEVES - One (1) year Limited Warranty 71 lpm3 120 lpm3 (@40mJ/cm2) 4.219 mGPM/hr. 7.131 mGPM/hr. QUARTZUV LAMPS SLEEVES - One (1)- One year (1) Limited year Limited Warranty Warranty Flow Rate 4.2 m3/hr. 7.1 m3/hr. Port Size 2 1"71 MNPT lpm 1½"120 MNPT lpm QUARTZ SLEEVES - One (1) year Limited Warranty (@40mJ/cm ) Please refer to LUMINOR’s complete warranty ElectricalPort Size 4.21" MNPT m3/hr. 110-220V / 50-60Hz 1½"7.1 MNPTm3/hr. Please refer to LUMINOR’s complete warranty Electrical 110-220V / 50-60Hz document for specific details, including conditions PlugPort TypeSize American, Nema 5/15, 3 1" MNPTEuropean, 2-pin (CEE 7/7) American, Nema 5/15, 31½" MNPTEuropean, 2-pin (CEE 7/7) documentPlease refer for to specific LUMINOR’s details, complete including warranty conditions PlugElectrical Type American,prong groundedNema 5/15, 3 European,"Schuko" 2-pin (CEE110-220V 7/7) / 50-60HzAmerican,prong groundedNema 5/15, 3 European,"Schuko" 2-pin (CEE 7/7) and exclusions. This document may be found on the Lamp Watts prong grounded 67 "Schuko" prong grounded 101 "Schuko" anddocument exclusions. for specific This document details, including may be found conditions on the Plug Type American, Nema 5/15, 3 European, 2-pin (CEE 7/7) American, Nema 5/15, 3 European, 2-pin (CEE 7/7) web or by contacting LUMINOR directly. PowerLamp (Watts)Watts prong grounded73 67 "Schuko"72 prong 115grounded 101 "Schuko"108 weband exclusions.or by contacting This document LUMINOR may directly. be found on the PowerLampChamber (Watts)Watts 73 67 72 115 101 108 316L Stainless Steel, A249 Pressure Rated Tubing, Polished & Passivated web or by contacting LUMINOR directly. PowerChamberMaterial (Watts) 73 72 115 108 Material 316L Stainless Steel, A249 Pressure Rated Tubing, Polished & Passivated ChamberReactor 3.5 x 26.9" 3.5 x 40.7" 316L Stainless Steel, A249 Pressure Rated Tubing, Polished & Passivated Replacement Parts DimensionsMaterialReactor (8.93.5 x x68.3 26.9" cm) (8.93.5 x 103.4x 40.7" cm) Replacement Parts DimensionsController (8.9 x 68.3 cm) (8.9 x 103.4 cm) Reactor 3.5 x 26.9" 8.6 x 4.2 x 3.5” (21.7 x 108 x 8.9 cm) 3.5 x 40.7" DimensionsController (8.9 x 68.3 cm) (8.9 x 103.4 cm) Replacement Parts 8.6 x 4.2 x 3.5” (21.7 x 108 x 8.9 cm) System Lamps Sleeves Controller MaximumDimensions Operating Controller 10.3 bar (150 psi) System Lamps Sleeves Controller MaximumDimensionsPressure Operating 8.6 x 4.2 x 3.5” (21.7 x 108 x 8.9 cm) 10.3 bar (150 psi) LB5-251 RL-600HO RQ-600 RCHO-56.12 OperatingPressure System Lamps Sleeves Controller Maximum Operating 2-40° C (36-104° F) LB5-251 RL-600HO RQ-600 RCHO-56.12 TemperatureOperating Range 10.3 bar (150 psi) Pressure 2-40° C (36-104° F) LB5-252 RL-600HO RQ-600 RCHO-56.12 TemperatureUV Monitoring Range Port LB5-251 RL-600HO RQ-600 RCHO-56.12 Operating Yes, includes visual glow plug LB5-252 RL-600HO RQ-600 RCHO-56.12 UV(Upgradeability) Monitoring Port 2-40° C (36-104° F) Temperature Range Yes, includes visual glow plug RL-950HO RQ-950 RCHO-56.12 (Upgradeability) LB5-252LB5-401 RL-600HO RQ-600 RCHO-56.12 UVSolenoid Monitoring Output Port Optional Yes, includes visual glow plug LB5-401 RL-950HO RQ-950 RCHO-56.12 Solenoid(Upgradeability)4-20mA Output Output Optional LB5-401LB5-402 RL-950HO RQ-950 RCHO-56.12 Lamp ChangeSolenoid4-20mA Reminder Output Output (audible Optional LB5-402 RL-950HO RQ-950 RCHO-56.12 Yes Lamp Change& visual)Reminder (audible 4-20mA Output OptionalYes LB5-402 RL-950HO RQ-950 RCHO-56.12 & visual) LampLamp Change Out Indicator Reminder (audible (audible Yes Lamp Out& Indicator visual) (audible Yes & visual) 6.5 kg 8.0 kg Lamp ShippingOut Indicator Weight (audible (14.36.5 kglbs) Yes (17.78.0 kglbs) Shipping& visual) Weight (14.3 lbs) (17.7 lbs) 6.5 kg 8.0 kg Shipping Weight (14.3 lbs) (17.7 lbs)

Twitter.com/LuminorUV Facebook.com/LuminorUV Twitter.com/LuminorUV Facebook.com/LuminorUV Twitter.com/LuminorUV Facebook.com/LuminorUV

290 Southgate Drive, Unit 2 Guelph,290 Southgate Ontario, Drive, CANADA Unit 2 N1G 4P5 290 Southgate Drive, Unit 2 P:Guelph, 519.837.380 Ontario,0 CANADA N1G 4P5 Guelph, Ontario, CANADA N1G 4P5 TF:P: 519.837.380 855.837.38010 P: 519.837.3800 F:TF: 519.837.3808 855.837.3801 F:TF: 519.837.3808 855.837.3801 F: 519.837.3808 [email protected] [email protected] [email protected] Printed in Canada Printed in Canada Printed in Canada RI Series (Commercial)

SPECIFICATIONS & PERFORMANCE DATA MANUFACTURER’S WARRANTY

Model RI-6K RI-10K RI-17K System 2 Years*

Flow Rate @ 16 mJ/cm2 106 Lpm 180 Lpm 290 Lpm UV Lamp 1 Year Pro-rata

Flow Rate @ 30 mJ/cm2 56 Lpm 95 Lpm 151 Lpm Quartz Sleeve 1 Year Pro-rata

Flow Rate @ 40 mJ/cm2 45 Lpm 72 Lpm 120 Lpm

Port Size 1” 1” 1½”

Electrical 110-220V / 50-60Hz

Plug Type Australian AS/NZ 3112

Lamp (Watts) 50 67 101

Power (Watts) 62 73 115

Replacement Lamp RL6K RL10K RL17K

Hot Water Lamp (optional) - RL10K-HW RL17K-HW

Replacement Sleeve RQ6K RQ10K RQ17K

Chamber Material 304 Stainless 316 Stainless Steel, 316 Stainless Steel, A249 A249 Pressure Rated Steel, A249 Pressure Rated Tubing, Polished & Pressure Rated Tubing, Polished & Passivated Tubing, Polished & Passivated Passivated

Chamber Dimensions

Chamber Length 1060 mm 674mm 1023 mm

Diameter [2.50] Ø 63.5 [3.50] Ø 88.9 [3.50] Ø 88.9

Controller Dimensions 171.8 mm H x 89 217.4 mm H x 107 217.4 mm H x 107 mm W mm W mm W

Maximum Operating Pressure

Operating Temperature 2-40°C 2-40°C (2-70°C with 2-40°C (2-70°C with Range optional Hot Water optional Hot Water Lamp) Lamp)

UV Monitoring Port Optional Upgradeable, includes Upgradeable, visual glow plug includes visual glow plug

Solenoid Output Optional Optional Optional

Volt Free Output Optional Optional Optional

Lamp Change Reminder Yes Yes Yes (audible & visual)

Lamp-Out Indicator Yes Yes Yes (audible & visual)

Shipping Weight 8.0 kg 6.5 kg 8.0 kg (17.6 lbs) (14.3 lbs) (17.6 lbs)

Lamp Life (hours) 9,000 10,000 10,000

Lamp Style Low Pressure Low Pressure HO Low Pressure HO Standard

For more information contact your local stockist or visit us at puretecgroup.com Australia 1300 140 140 | New Zealand 0800 130 140 Page 2 of 2

JULY.2019