Completion Report

Project Number: 44013-013 Loan Number: 2885 October 2019

People’s Republic of : Energy Efficiency and Environment Improvement Project

This document is being disclosed to the public in accordance with ADB’s Access to Information Policy.

CURRENCY EQUIVALENTS

Currency unit – yuan (CNY)

At Appraisal At Project Completion 2 August 2012 11 December 2017 CNY1.00 = $0.1570 $0.1512 $1.00 = CNY6.3698 CNY6.6152

ABBREVIATIONS

ADB – Asian Development Bank CHP – combined heat and power CMM – coal-mine methane CO2 – carbon dioxide DDR – due diligence report DHS – district heating system EIRR – economic internal rate of return EMP – environmental management plan EPB – Environmental Protection Bureau EMR – environmental monitoring report EMU – Environmental Management Unit FIRR – financial internal rate of return GAP – gender action plan HES – heating exchange station IEE – initial environmental examination NOx – nitrogen oxide O&M – operation and maintenance PIA – project implementing agency PIU – project implementation unit PMO – project management office PPMS – project performance monitoring system PRC – People’s Republic of China SCADA – supervisory control and data acquisition SDRC – Shanxi Provincial Development and Reform Commission SFD – Shanxi Provincial Finance Department SO2 – sulfur dioxide TA – technical assistance WACC – weighted average cost of capital

WEIGHTS AND MEASURES km – kilometer m2 – square meter m3 – cubic meter mu – equivalent to 666.67 square meters MW – megawatt MWt – megawatt thermal

NOTE

In this report, "$" refers to United States dollars.

Vice-President Ahmed M. Saeed, Operations 2 Director General Amy S. P. Leung, East Asia Department (EARD) Director Yolanda Fernandez Lommen, People’s Republic of China Resident Mission, EARD

Team leader Xinjian Liu, Senior Project Officer (Energy), EARD Team members Yan Dong, Associate Project Analyst, EARD Ning Li, Senior Environment Officer, EARD Fang Wang, Senior Project Officer (Financial Management), EARD Wenlong Zhu, Senior Safeguards Officer (Resettlement), EARD Ciwang Zhuoga, Associate Social Development Officer (Safeguards), EARD

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

CONTENTS Page BASIC DATA i I. PROJECT DESCRIPTION 1 II. DESIGN AND IMPLEMENTATION 1 A. Project Design and Formulation 1 B. Project Outputs 2 C. Project Costs and Financing 4 D. Disbursements 4 E. Project Schedule 5 F. Implementation Arrangements 5 G. Technical Assistance 6 H. Consultant Recruitment and Procurement 6 I. Gender Equity 6 J. Safeguards 7 K. Monitoring and Reporting 8 III. EVALUATION OF PERFORMANCE 8 A. Relevance 8 B. Effectiveness 9 C. Efficiency 9 D. Sustainability 10 E. Development Impact 11 F. Performance of the Borrower and the Executing Agency 12 G. Performance of the Asian Development Bank 12 H. Overall Assessment 12 IV. ISSUES, LESSONS, AND RECOMMENDATIONS 13 A. Issues and Lessons 13 B. Recommendations 14

APPENDIXES

1. Design and Monitoring Framework 16 2. Project Cost at Appraisal and Actual 18 3. Project Cost by Financier 23 4. Disbursement of ADB Loan Proceeds 25 5. Project Implementation Schedule 26 6. Chronology of Major Events 27 7. Project Implementation Arrangement and Fund Flow 28 8. Contract Awards of ADB Loan Proceeds 30 9. ADB-financed Contract Packages 31 10. Gender Equality Action Plan Analysis 32 11. Environmental Impact Analysis 36

12. Evaluation of Land Acquisition and Resettlement Implementation 40 13. Status of Compliance with Loan Covenants 43 14. Economic Reevaluation 54 15. Financial Reevaluation 60 16. Social Impact and Labor Retrenchment Plan 64

BASIC DATA

A. Loan Identification

1. Country People’s Republic of China 2. Loan number and financing source 2885-PRC, ordinary capital resources (OCR) 3. Project title Shanxi Energy Efficiency and Environment Improvement Project 4. Borrower People’s Republic of China 5. Executing agency Shanxi Provincial Government 6. Amount of loan $100 million 7. Financing modality Project loan

B. Loan Data 1. Appraisal – Date started 24 October 2011 – Date completed 4 November 2011 2. Loan negotiations – Date started 18 July 2012 – Date completed 19 July 2012 3. Date of Board approval 31 August 2012 4. Date of loan agreement 27 March 2013 5. Date of loan effectiveness – In loan agreement 25 June 2013 – Actual 24 April 2013 – Number of extensions 0 6. Project completion date – Appraisal 30 June 2017 – Actual 31 December 2017 7. Loan closing date – In loan agreement 31 December 2017 – Actual 31 December 2017 – Number of extensions 0 8. Financial closing date – Actual 8 June 2018 9. Terms of loan – Interest rate London interbank offered rate (LIBOR) + 0.6% less credit of 0.2% – Maturity (number of years) 20 years – Grace period (number of years) 5 years 10. Terms of relending (if any) – Interest rate LIBOR + 0.6% less credit of 0.2% – Maturity (number of years) 20 years – Grace period (number of years) 5 years – Second-step borrower Shanxi Provincial Government

ii

11. Disbursements

a. Dates Initial Disbursement Final Disbursement Time Interval 21 January 2014 4 December 2017 46 months

Effective Date Original Closing Date Time Interval 24 April 2013 31 December 2017 56 months

b. Amount ($ million) Last Net Original Revised Amount Amount Amount Undisbursed Category Allocation Allocation Canceled Available Disbursed Balance District Heating Subproject Works 1.85 1.90 1.90 1.90 0.00 Equipment 39.12 38.93 38.93 38.93 0.00 Consulting services 0.90 0.00 0.00 0.00 0.00

Licheng District Heating Subproject Works 2.30 2.17 2.17 2.17 0.00 Equipment 15.1 14.82 14.82 14.82 0.00 Consulting services 0.33 0.00 0.00 0.00 0.00

Qin District Heating Subproject Works 4.53 6.88 6.88 6.88 0.00 Equipment 17.09 17.05 17.05 17.05 0.00 Consulting services 0.46 0.00 0.00 0.00 0.00

Zhongyang District Heating Subproject Works 1.03 1.58 1.58 1.58 0.00 Equipment 3.26 3.27 3.27 3.27 0.00 Consulting services 0.08 0.00 0.00 0.00 0.00

Liulin Coal Mine Methane Subproject Equipment 10.62 10.49 10.49 10.49 0.00 Consulting services 0.23 0.00 0.00 0.00 0.00

Interest and 3.10 2.91 2.91 2.91 0.00 Commitment Charges Total 100.00 100.00 100.00 100.00 0.00 Note: Amounts may not add up precisely due to rounding. Source: Asian Development Bank.

C. Project Data

1. Project cost ($ million)

Cost Appraisal Estimate Actual Foreign exchange cost 109.85 100.00 Local currency cost 56.27 54.01 Total 166.12 154.01

iii

2. Financing plan ($ million) Cost Appraisal Estimate Actual Implementation cost Borrower financed 66.12 51.10 ADB financed 96.90 100.00 Total 163.02 151.10 Interest during construction costs Borrower financed 0 0 ADB financed 3.10 2.91 Other external financing 0 0 Total interest during construction costs 3.10 2.91 ADB = Asian Development Bank.

3. Cost breakdown by project component ($ million) Component Appraisal Estimate Actual A. Base costs Part A: District heating supply 115.62 125.50 Part B: CMM supply and distribution 15.17 15.99 Part C: Project management and capacity building 16.70 9.61 Subtotal (A) 147.49 151.10 B. Contingencies Physical contingencies 7.30 0 Price contingencies 8.24 0 Subtotal (B) 15.54 0 C. Financing charges during implementation 3.09 2.91 Total (A+B+C) 166.12 154.01 CMM = coal-mine methane.

4. Project Schedule Item Appraisal Estimate Actual Date of contract with consultants a December 2013 Completion of engineering designs December 2014 September 2015 Civil works contract Date of award January 2014 January 2014 Completion of work March 2016 November 2017 Equipment and supplies Dates First procurement December 2013 December 2013 Last procurement April 2014 June 2016 Completion of equipment installation September 2016 October 2017 Start of operations Completion of tests and commissioning October 2016 November 2017 Beginning of start-up October 2014 October 2014

a Recruitment using domestic funds.

5. Project performance report ratings Implementation Period Ratings From June 2013 to June 2015 On-track From July 2015 to September 2015 Potential problem From October 2015 to December 2017 On-track

iv

D. Data on Asian Development Bank Missions No. of No. of Specialization of Name of Mission Date Persons Person-Days Members Fact-finding 25 October– 8 30 a, c, d, e, f, g, h, n 3 November 2011 Pre-inception 21–22 March 2013 3 6 f, b, g Inception 11–13 November 2013 3 9 g, b, m Review 1 1–2 July 2014 3 6 g, a, b Review 2 18–22 September 2014 2 10 g, i Review 3 23–25 March 2015 2 4 a, b, g, i, j Midterm review 8–12 August 2016 3 11 a, b, k Review 4 11–15 September 2017 2 8 a,b Project completion review 6–14 March 2018 6 40 a,b, i, j, k, l a = senior project officer(energy), b = associate project analyst, c = senior control officer, d = senior procurement officer, e = senior counsel, f = senior financial specialist, g = energy specialist, h = young professional, i = safeguards officer (environment), j = senior safeguards officer (resettlement), k = senior project officer (financial management), l= safeguards officer (social development), m = environment specialist, n = senior operations assistant.

I. PROJECT DESCRIPTION

1. About half the carbon dioxide (CO2) emissions in the People’s Republic of China (PRC) come from generating electricity and heat. Demand for centralized heating (or district heating) is growing rapidly along with economic development and urbanization. Like in many other provinces, Shanxi's rapid urbanization is fueling demand for housing and urban infrastructure. Likewise, strong economic growth, higher incomes, and the privatization of housing are driving demand for district heating. Because locally produced coal is abundant, district heating in Shanxi relies primarily on coal. Many of the heating systems in urban areas are old, inefficient, and lack proper emission control equipment. Environmental impacts from these systems are disproportionately high for the poor and women. Urban pollution from small boilers worsens outdoor air quality and causes significant cumulative harm to public health. Inadequate coverage of district heating in low-income urban areas drives residents to use indoor coal stoves for heating, a major cause of respiratory diseases. Women and small children are particularly vulnerable to high indoor pollution, as they tend to spend more time indoors.

2. The Shanxi Energy Efficiency and Environment Improvement Project aimed to help solve heating sector issues by extending and expanding energy-efficient district heating to over 270,000 residents in five highly polluted urban areas in Shanxi. 1 The project aimed to replace small, inefficient, and polluting inner-city coal-fired boilers and coal-fired household stoves with a highly energy-efficient combined heat and power (CHP) plant and large heat boilers, with coal-mine methane (CMM) supply, thereby reducing the overall environmental footprint of district heating.2 The Asian Development Bank (ADB) Board approved a loan of $100 million from its ordinary capital resources for the project on 31 August 2012; project implementation was completed in December 2017 as scheduled.

3. The expected impact of the project was greater energy efficiency and a cleaner environment in Shanxi Province. The expected outcome was better air quality and reduced greenhouse gases emission in five urban areas in Shanxi Province. The expected outputs of the project were (i) improved district heating supply in the urban areas of four project cities; (ii) expanded CMM gas supply and distribution system in of Luliang city; and (iii) enhanced institutional capacity.

II. DESIGN AND IMPLEMENTATION

A. Project Design and Formulation

4. The project was in line with (i) the government’s high priority on shifting economic growth from relying heavily on coal to green development; (ii) the Twelfth Five-Year Plan of the PRC, 2011–2015; and (iii) ADB’s country partnership strategy for the PRC, 2011–2015, which feature managing climate change and the environment to support the government’s priorities in realizing an “ecological civilization.”3 Through the project, ADB helped the PRC government to implement

1 ADB. 2012. Report and Recommendation of the President to the Board of Directors: Proposed Loan to the People's Republic of China for the Shanxi Energy Efficiency and Environment Improvement Project. Manila. 2 Small heat-only boilers operate at 50%–60% combustion efficiency compared with 80%–90% for new large boilers. Household heating stoves have an even lower combustion efficiency at only 35%–40%. CMM refers to methane released from the coal and surrounding rock strata during mining. Methane is a nontoxic combustible greenhouse gas, about 21 times more potent than CO2. In underground mines, the methane is drained before the mining operation can take place to avoid explosions and injuries to miners. 3 ADB. 2012. Country Partnership Strategy: People’s Republic of China, 2011–2015. Manila. An “ecological civilization” refers to achieving harmony between growth, people, and nature. It includes activities to mitigate ecological damage, relieve pressures on natural resources, and improve the balance between the environment and the economy.

2

the strategic shift from coal-reliant economic growth to a green development track in Shanxi, and helped the Shanxi Provincial Government build the capacity of city and county governments to implement the energy efficiency and environment improvement project and ensure proper safeguards. The project has a very good fit and direct relevance to the PRC’s ongoing and targeted energy efficiency improvements to lower carbon intensity by 45% by 2020, compared with 2005. At the time of appraisal, the PRC government’s long-term development goal was to maintain steady economic growth and improve people’s living standards. The project supported the PRC’s Twelfth Five-Year Plan that reiterated energy efficiency improvement and pollution emission reduction.

5. ADB’s support for environment-friendly economic growth in Shanxi was relevant to the government’s programs and has remained consistent with ADB’s strategy since appraisal. To support the PRC government’s strategy, ADB’s operations focused on (i) promoting equitable and inclusive growth, (ii) making markets work better, (iii) improving the environment, and (iv) promoting regional cooperation. ADB’s country partnership strategy for the PRC, 2011–2015 also emphasized balanced and sustainable growth with more efficient uses of resources and more stringent protection of the environment. ADB aims at inclusive economic growth in an efficient, equitable, and sustainable manner. In its Long-Term Strategic Framework II, 2008–2020, ADB identified energy as a core operational sector and achieving environmental sustainability as a strategic priority.4 In line with ADB’s energy policy, the project adopted an integrated approach to improve energy efficiency. The project prioritizes energy efficiency, including district heating, and promotes access to energy for all. The project fits the ADB operational strategy for the PRC well.

6. The project design was appropriate to help achieve the outcome, and the formulation was adequate. During project implementation, minor changes in project design responded to changes in local government development plans.5 These changes did not affect project outputs, and they enhanced the project impact and outcome. The project design and monitoring framework at appraisal, along with the achievements at completion against the framework’s targets and indicators, is in Appendix 1.

B. Project Outputs

7. The project has three parts as described below.

8. Part A: District heating supply. As designed at appraisal, part A consisted of four district heating subprojects in Jinzhong city, Licheng county, , and Zhongyang county to install (i) five large, efficient coal-fired boilers with an aggregate capacity of 261 megawatt thermal (MWt), to allow closure of 232 small, inefficient coal-fired boilers with an aggregate capacity of 340 MWt and 4,000 household heating stoves with an aggregate capacity of 60 MWt; (ii) a heat transmission and distribution network with 100 heat exchange stations (HESs) and heating pipelines; and (iii) supervisory control and data acquisition (SCADA) systems.

9. At completion, the four district heating subprojects delivered the following outputs: (i) heat access from a new CHP plant of 195 megawatts (MW) of heat generation capacity connected for

4 ADB. 2008. Strategy 2020: The Long-Term Strategic Framework of the Asian Development Bank, 2008-2020. Manila. 5 During implementation, the following changes were made: (i) heat source for Zhonyang district heating supply subproject was changed from a coal-fired boiler to a gas-fired boiler; and (ii) some design changes of CMM gas supply and distribution subproject: (a) location change of CMM gas storage station; (b) change from one gas storage tank with the total capacity of 100,000 m3 to one gas storage tank of 50,000 m3 with potential expansion in future; and (c) layout changes of gas pipelines due to the change of CMM gas storage station location.

3

the Jinzhong subproject; (ii) 261 MW of heat generation capacity using large high-efficiency pulverized coal boilers (Licheng and Qin) or natural gas boiler (Zhongyang) equipped with flue gas desulfurization scrubbers and filter baghouse emission control established; (iii) 132 heat exchange stations constructed and installed or upgraded; (iv) 125.6 kilometers (km) of heat supply pipeline installed; (v) SCADA systems for the four subprojects installed; and (vi) 355 small inner- city small, inefficient coal-fired boilers with an aggregated capacity of 374 MWt and 4,000 coal- fired household stoves closed. The total service capacity of these four district heating subprojects reached 7.57 million square meters (m2) by the 2017–2018 heating season and 8.12 million m2 by the 2018–2019 heating season, supplying heating services to 297,600 residents and exceeding the original target of 6.8 million m2. Table 1 compares the scope of part A at appraisal and at completion.

Table 1: Part A Scope Comparison Heating Heating Area Heat Sourcea Pipelineb Heat Exchange Stations 2 Subprojects (million m ) (MWt) (kilometer) (No.) Appraisal Completion Appraisal Completion Appraisal Completion Appraisal Completion Jinzhong 3.0 4.27 71.2 89.9 58 92 Licheng 1.6 1.67 2x58 2x58 10.1 10.1 10 10 Qin 1.7 1.68 2x58 2x58 14.9 14.8 25 25 Zhongyang 0.5 0.50 1x29 1x29 10.8 10.8 7 5 Total 6.8 8.12 261 261 107.1 125.6 100 132 m2 = square meter, MWt = megawatt thermal, SCADA = supervisory control and data acquisition system. a The heat source for the Jinzhong subproject is a newly constructed 195 MWt combined heat and power plant. b Excludes pipeline system inside buildings and households. Sources: Project management office, Shanxi Provincial Government.

10. Part B: Coal-mine methane gas supply and distribution. At appraisal, the envisaged part B would construct a CMM gas supply and distribution system in Liulin to supply 88.8 million cubic meters (m3) of gas annually to about 30,000 households and 120 commercial customers.6 By completion, the subproject delivered CMM gas supply and distribution facilities including: (i) gas supply pipelines with total length of 10 km from the extraction points at each of the three coal mines to the storage station and gas distribution pipelines of 33 km, including 12 km low pressure and 21 km medium pressure pipelines; (ii) a gas storage station with one storage tank of 50,000 m3 capacity constructed;7 (iii) 20 pressure-regulating stations installed; and (iv) a SCADA system installed. At completion, the subproject has the capacity to supply CMM gas to about 30,000 households and 134 commercial customers, with an annual gas supply capacity of 88.6 million m3. The subproject achieved 40% of CMM gas supply capacity in 2018 and expects to achieve full gas supply capacity by 2020. It can provide heating to 1.17 million m2 of floor area, and cold water for summer air conditioning to 0.3 million m2 of building area by 2020. In addition, 43 small coal-fired boilers with the total capacity of 46 MWt have been closed.

11. Part C: Institutional strengthening. At appraisal, part C was designed to (i) provide consulting services, training, and equipment and (ii) strengthen the capacity of the executing agency, the project management office (PMO), and the five subproject implementing agencies to supervise and manage implementation of the project. The PMO and the project implementation units (PIUs) assigned full-time staff to daily management activities. With support from procurement agencies, the PMO procured civil works, equipment, and materials fully in line with ADB and domestic requirements. PIU is implementing the environmental management plan (EMP)

6 CMM gas users include households (accounting for 22. 9% of total gas volume), enterprises and institutions (11.5%), boilers (50.5%), and other contingencies (15.1%). For heating, gas-fired boilers are used and funded by those users in addition to by local government budget in coal shift to gas initiatives. 7 Although the capacity of the gas tank is reduced from the original design of 100,000 m3, the gas supply capacity can be maintained at about 88.6 million m3 annually as the sources of CMM are very stable.

4

in order and furnished monitoring reports on EMP and social related plans implementation to the ADB on a regular basis. The PMO submitted five semiannual or annual progress reports, seven environmental monitoring reports, three social monitoring reports, and a domestic project completion report to ADB.

12. The subproject organized and implemented five project management staff training courses for overall project management, environmental management, and land acquisition and resettlement. The subproject carried out one session on health, safety, and energy conservation awareness campaign and knowledge-sharing.8 The plan to engage an ADB-financed consulting firm to provide assistance and advice for the PMO and PIUs, using the quality- and cost-based selection procedure as designed at appraisal, experienced recruitment delays (para. 22). In early 2016, the executing agency engaged individual consultants using domestic counterpart funds to provide the required assistance and advice for project implementation.

C. Project Costs and Financing

13. At appraisal, the project cost was estimated at $166.12 million equivalent, comprising $109.85 million of foreign exchange costs (66.1%) and $56.27 million equivalent of local currency costs (33.9%). At the project completion, project costs totaled $154.01 million, including $100.00 million of foreign exchange (64.9%) and $54.01 million equivalent of local currency (35.1%). The total amount ADB loan of $100.00 million was fully used. The project costs and financing plans are in Appendix 2. A detailed cost breakdown, by project component, is in Appendix 3.

14. Compared to the appraisal estimate, the costs for land acquisition and resettlement, project management, and capacity development decreased, but the costs for civil works, equipment, and materials increased. As a whole, total project expenditures decreased by 7.3% compared to the appraisal estimate, and the project did not use contingencies budgeted at appraisal.

D. Disbursements

15. Loan proceeds totaling $100.00 million were disbursed from January 2014 to December 2017 in accordance with the provisions in the loan agreement and ADB’s Loan Disbursement Handbook (2012, as amended from time to time). The Shanxi Provincial Finance Department (SFD) adopted advance fund and direct payment procedures.9 The interval between initial and final disbursements was 46 months against the 56 months between the actual effective date and the loan closing date. Of the amount disbursed, $12.53 million was for civil works, $84.56 million for equipment and materials, and $2.91 million for interest during construction and commitment charges.

16. SFD used the advance fund procedure for most withdrawals of loan proceeds, and made some withdrawals of loan proceeds through the direct payment procedure. SFD was responsible for setting up and maintaining the advance fund. SFD reported no problems on the use of the advance fund procedure and observed regular replenishments to the advance fund during the project implementation period, although with varying frequency. The external auditors provided an unqualified opinion on the project financial statements during the entire project implementation

8 The participants included staff from all five project companies as the PIUs, PMO, and relevant government authorities at the provincial and county levels, including the development and reform committee, financial bureaus, and environment protection bureaus. 9 All references to advance fund and advance account refers to formerly called imprest fund and imprest account.

5

period and raised no significant issues on the management of the advance fund. The initial advance fund ceiling for the project was set at $10 million, based on a six-month estimate of expenditures submitted from the Shanxi Provincial Government to ADB after loan effectiveness. As a whole, the utilization efficiency of the ADB loan is comparatively satisfactory. The projected and actual disbursements are in Appendix 4.

E. Project Schedule

17. The project was approved on 31 August 2012. The loan and project agreements were signed on 27 March 2013 and the loan became effective on 24 April 2013. The original and actual loan closing date was 31 December 2017, without extensions. The financial closing date was 8 June 2018. Overall project implementation generally followed the project implementation schedule at appraisal, with some delays for subproject implementation (mainly the Liulin subproject) (para. 28). The planned and actual implementation schedules are in Appendix 5. A chronology of major events is in Appendix 6.

F. Implementation Arrangements

18. The project was implemented following the arrangements outlined at appraisal and did not require changes in the implementation arrangement. The Shanxi Provincial Government was the executing agency and the five participating cities and counties were the implementing agencies (PIAs), including Jinzhong city, Licheng county, Qin county, Zhongyang county, and Liulin county. To oversee and coordinate project implementation, the provincial government established a project leading group headed by the vice governor of Shanxi and comprising the Shanxi Provincial Development and Reform Commission (SDRC), SFD, and the Shanxi Environment Protection Department. Established within the Shanxi Provincial Foreign Loan Project Management Services Center under the SDRC, the PMO is responsible for daily project management with SFD support and also functions as the secretariat for the leading group. Five project entities—Jinzhong Ruiyang CHP Heat Supply Company, Licheng County Wantong Heat Supply Company, Qin County Huayang Heat Supply Company, Zhongyang Heating and Gas Supply Center, and Liulin County Gasification Company—serve as the PIUs that undertake specific implementation activities. Appendix 7 shows the project implementation arrangements and fund flow.

19. The PMO had overall responsibility for project management. It coordinated and directed subproject implementation by directing subproject implementing activities, assisting PIUs in planning and managing their subproject works, setting up and managing finances, conducting necessary coordination for monitoring land acquisition and resettlement and environment management, and establishing project monitoring systems. The PMO regularly reported project progress and issues to the project leading group, which met as required when there were key issues to discuss and resolve.

20. The project was implemented in a generally satisfactory manner in line with the arrangements agreed at project appraisal. There were no changes in the implementation arrangements.

6

G. Technical Assistance

21. A project preparatory technical assistance (TA) helped formulate the project.10 The TA helped the Shanxi Provincial Government (i) review, assess, and identify cost-effective district heating systems and CMM gas supply and distribution system in five cities; and (ii) formulate an improved and integrated energy efficiency improvement investment project with environmental impact assessment and resettlement plans consistent with ADB’s policy and guidelines. The TA provided all the inputs needed to prepare the project for ADB financing. Stakeholders were consulted during planning, design, and implementation to determine the project’s scope and implementation arrangements.

H. Consultant Recruitment and Procurement

22. In order to support project implementation and management, ADB-financed consulting services were designed at appraisal to assist and advise the executing and implementing agencies and the PMO in undertaking their responsibilities. Using quality- and cost-based selection, the recruitment of the consulting firm experienced substantial delays and could not keep pace with the rapid progress of project implementation, so in early 2016 PMO employed the required consulting services using local counterpart funds instead of the ADB loan. In addition to these consultants, the PMO and PIUs engaged the following agencies and experts with local counterpart funds in line with PRC regulations: (i) five design institutes for preliminary and engineering designs, (ii) two procurement agencies, (iii) procurement and bidding advisory experts randomly selected from national or provincial databases, and (iv) construction supervision firms for civil works contracts (financed by ADB and local counterpart funds) under the five subprojects.

23. The contract awards of ADB loan proceeds are shown in Appendix 8. The project awarded nine goods or works contracts for ADB financing, comprising: (i) five goods contracts through international competitive bidding for the supply and installation of boilers and auxiliary equipment, heating exchange station equipment, heat supply and distribution networks pipelines, CMM gas storage station equipment, pressure-regulating station equipment, and gas supply and distribution network pipelines; and (ii) four civil works contracts through national competitive bidding for constructing boiler houses and installing pipelines. All packages financed by ADB were procured in accordance with ADB’s Procurement Guidelines (2010, as amended from time to time), without major deviations or misprocurement cases. Appendix 9 shows the ADB-financed contract packages. PIAs incorporated relevant sections of ADB's Anticorruption Policy (1998, as amended to date) into bidding documents and contracts, and implemented them. In addition, the project widely applied domestically prevailing anticorruption practices in civil works construction. PMO and PIAs found no serious issues or difficulties that significantly constrained the project implementation in the packaging of contracts, preparation of bidding documents and evaluation of bids. The bidders issued no complaints or dissents during procurement.

I. Gender Equity

24. The project is classified effective gender mainstreaming for gender equity category and a gender action plan was prepared to ensure women equally benefited from the project. The project successfully achieved the gender actions and targets. The five subprojects achieved most of their gender actions and targets. A gender equality action plan analysis is in Appendix 10.

10 ADB. 2010. Technical Assistance to the People’s Republic of China for Preparing the Shanxi Energy Efficiency and Environment Improvement Project. Manila.

7

J. Safeguards

25. The project is classified as environment category B, in accordance with the ADB environmental categorization. The Shanxi Provincial Environmental Protection Bureau (EPB) and the relevant municipal EPBs prepared and approved the domestic environmental impact assessment documents for all subprojects under part A and part B in 2009–2012. PMO prepared the initial environmental examination (IEE) in accordance with the ADB Safeguard Policy Statement (2009) and submitted it to ADB in 2012. PMO also prepared an environment and social due diligence report in accordance with the Safeguard Policy Statement (2009) and submitted it to ADB in 2014; the report took into account the minor project changes to accommodate relocating the CMM gas storage station in the Liulin subproject and substituting natural gas-fired boiler for coal-fired boiler in the Zhongyang subproject, as well as the domestic environmental impact assessment document approval by the Luliang Municipal Environment Protection Bureau in 2014.

26. The PMO established under the SDRC was responsible for managing, coordinating, and supervising EMP implementation. Each PIA established an environmental management unit responsible for EMP implementation and monitoring during subproject construction and operation. The PMO designated environmental staff to coordinate with each environmental management unit, undertake environmental management of subprojects, and oversee EMP implementation and monitoring for all subprojects, with assistance from consultant. Regularly submitted EMRs confirmed that the project addressed key environmental impacts—including soil erosion and contamination, wastewater disposal, noise and dust generation during construction—in accordance with mitigation measures in the EMP. During operation for part A and part B, the project also addressed mitigation measures in the EMP such as compliance with the boiler emission standard and natural gas leakage detection (Appendix 11). As required under national laws and regulations, the Shanxi provincial and municipal EPBs will review all subprojects (part A and part B) in the environment protection completion audit by 2019, excluding the Licheng subproject, which was completed in 2017.

27. The project was category B for involuntary resettlement safeguards during project preparation. At appraisal, the Liulin CMM subproject involved land acquisition and resettlement; the four other subprojects entailed no land acquisition, restriction in land use, or structure demolition because they were implemented on government land or existing premises. In the draft resettlement plan, based on a feasibility study report in 2012, the Liulin CMM subproject would permanently acquire 24.7 mu, including 15 mu of cultivated land that would affect 17 people from 4 households.11 In 2015, the Liulin CMM subproject’s scope changed, moving the CMM storage station from Jiajiayuan village to Hechang village. An updated resettlement plan appended to a due diligence report (DDR) for the scope change was prepared and submitted to ADB in 2016. The DDR concludes that (i) 12.6 mu used for the CMM storage station is part of the land acquired for Hechang central heating plant, (ii) 45 mu was acquired for the plant in 2013 and transferred to state-owned land, (iii) the acquired land was not contracted by households so that land acquisition did not affect individuals, and (iv) land compensation was fully paid to Hechang village and use of land compensation fund was transparent. In addition, 20 gas pressure adjustment stations did not acquire any land because these stations are in existing boiler houses. Construction of heating pipelines temporarily used existing state-owned roads. The cost for digging and recovering roads for the pipeline installation was included in the pipeline civil works. The resettlement completion report prepared by the PMO indicates that all the temporarily affected state-owned roads were rehabilitated. A detailed evaluation of land acquisition and resettlement implementation is provided in Appendix 12.

11 A mu is a Chinese unit of measurement, the equivalent of 666.67 m2.

8

K. Monitoring and Reporting

28. The loan covenants were considered adequate, and the project complied with majority of the covenants, except for partial compliance on the timing for mobilizing local counterpart funds and financial performance indicators of project entities. The implementation arrangement was adequately set up and the ADB loan was appropriately used and disbursed. The PMO submitted the necessary reports, audited project accounts, and financial statements to the ADB as required in the loan agreement. The reports were generally acceptable to ADB, albeit with some delays during the initial periods of project implementation. In general, project financial management is satisfactory, with timely submissions of annual project financial statements audited by the Shanxi Provincial Auditing Department. The auditor issued unqualified auditor’s opinion every year. Except for the Liulin subproject, the local counterpart funds for the subprojects were generally mobilized on time as required for the project implementation, which fully complied with the loan covenant on local counterpart funds. However, the counterpart funds for the Liulin subproject were not mobilized on time to meet the project construction demands, to some extent causing the Liulin subproject to fall behind the planned schedule, but this partial compliance with the loan covenants did not materially impact project performance.

29. According to the project agreement, in each fiscal year beginning 2 years after project operations, the PIA for the each of five subprojects would maintain (a) a minimum debt–service coverage ratio of 1.2:1, (b) a maximum debt–equity ratio of 70:30, and (c) a minimum ratio of current assets to current liabilities of 1:1. The Jinzhong subproject demonstrated strong financial performance and satisfied all the covenanted ratios, but the other PIAs did not satisfy the covenanted ratios. A summary of compliance with loan covenants is in Appendix 13.

30. The project design required the Shanxi Provincial Government, through the PMO, to ensure that the PIAs use a project performance monitoring system (PPMS) to monitor and evaluate project outcomes and outputs. The project preparatory TA prepared the PPMS, including a set of measurable indicators based on the project design, impact, and risks. The consultants supervising implementation were required to help the provincial government monitor project impacts and prepare periodic reports. However, because the designed ADB-financed consulting services were not recruited as scheduled and local counterpart funds-supported consulting services were in place only in early 2016, there was inadequate project management support during early project implementation (para. 22). The PPMS was not established in time or operated effectively. In addition, some targeted indicators of project performance did not fit well with routine statistics issued by government authorities. 12 There were delays in submitting the project progress and monitoring reports during early stages of project implementation.

III. EVALUATION OF PERFORMANCE

A. Relevance

31. The project’s expected impact at appraisal, greater energy efficiency and a cleaner environment in Shanxi, remained relevant at completion. Overall, the project is rated highly relevant. The project was fully aligned with (i) the government’s high priority on shifting economic growth from heavy reliance on coal to green development; (ii) the Twelfth and Thirteenth Five-

12 For example, the targeted indicator related to impact, “energy intensity of Shanxi economy reduced by 0.7% compared with 2010 due to improved district heating system,” is difficult to collect as the data reflecting this indicator published by the statistic authority is unavailable.

9

Year Plans of the PRC, 2011–2015 and 2016–2020; and (iii) ADB’s country partnership strategies for the PRC, 2011–2015 and 2016–2020.13 The project helped improve energy efficiency and was in line with ADB’s energy policy and Energy Operational Plan, 2011–2020, which prioritize promoting energy efficiency. The minor changes during project implementation (para. 6) were not foreseeable during project preparation and did not affect achievement of the project outcome. The project helped develop the first use of gas-fired boiler for district heating for a county-level urban area in Shanxi, which the provincial government showcased as an environmentally friendly, sustainable approach for clean energy heating in Shanxi.

B. Effectiveness

32. Overall, the project was effective in achieving the intended outcome: greater energy efficiency and a cleaner environment in Shanxi. The project largely achieved its envisaged outcomes at appraisal. As of 2018 the project heated floor area of 7.57 million m2, benefited 297,600 residents with adequate and reliable heat from the district heating systems, and installed a CMM gas supply and distribution network capable of transporting 88.6 million m3 of CMM gas and servicing an additional 30,000 urban households and 134 commercial customers. Operation of the project facilities created 306 permanent jobs. By 2018, the project’s energy savings from district heating systems reached 73,063 tons of standard coal annually. The operation of project heating facilities reduced annual emissions of CO2 by 194,025 tons, sulfur dioxide (SO2) by 3,195 tons, nitrogen oxide (NOx) by 2,121 tons and total suspended particulates by 12,588 tons. The project helped improve air quality in the five urban areas by increasing 16% to 27% of the record in meeting Class II air quality standard in 2017–2018 heating season compared with 2011–2012 heating season.14

C. Efficiency

33. The project is rated efficient both as an investment and in implementation. The project’s overall economic internal rate of return (EIRR) was estimated at 15.9% at completion, over the appraisal estimate of 15.0%, demonstrating economic viability at completion. The five subprojects were economically viable as well, with completion EIRR estimates in the range of 12.9%–24.4%, without significant differences from the appraisal estimates. The slight differences between the appraisal and completion EIRRs resulted principally from (i) changes in capital and operation and maintenance (O&M) costs and (ii) changes in economic benefits because the district heating areas of the Jinzhong subproject increased by 42% as a result of its higher operation efficiency. Sensitivity analyses found that all five subprojects and the project overall would remain economically viable in any scenario, indicating robust economic viability at completion. The detailed economic reevaluation is in Appendix 14. The project is rated highly efficient for implementation because it was generally completed within the planned implementation period without extending the loan closing date.

13 ADB. 2016. Transforming Partnership: People’s Republic of China and Asian Development Bank, 2016–2020. Manila. 14 The Ambient Air Quality Standards that are currently effective, GB 3095-2012, were released by the then Ministry of Environmental Protection on February 29, 2012. The Standards set mandatory limits for the primary pollutants— SO2, nitrogen dioxide (NO2), carbon monoxide (CO), O3, PM10, and PM2.5—and took effect nationwide on January 1, 2016. The Standards set two classes of limit values: Class I standards apply to regions that need special protection such as natural reserves and natural scenic areas, while Class II standards apply to all other areas including residential, mixed-use, industrial, and rural areas.

10

D. Sustainability

34. The project is likely sustainable overall considering its (i) operational sustainability, (ii) financial sustainability, and (iii) environmental and social sustainability.

35. District heating and gas supply are two essential public services, and demand for them in urban areas is expected to multiply as the public becomes increasingly aware of the need for a cleaner environment. The operating parameters of the subprojects suggest that they are sustainable. The operating facilities were designed and installed properly, and function well. The five PIUs, which are key agencies responsible for the O&M of the district heating systems and CMM gas supply facilities, possess the institutional capability and expertise required to manage and operate the facilities effectively and efficiently, and are quite stable in their human resources, finance, organizational arrangements, and governance.

36. The financial viability of five subprojects was reevaluated at completion (Appendix 15). The financial internal rates of return (FIRRs) for the five subprojects ranged from 2.83% to 8.67%, while the FIRR for the overall project was 6.24%. The FIRRs for the five subprojects and the overall project exceeded the weighted average cost of capital (WACC) at completion, indicating their financial viability. The Jinzhong subproject’s FIRR at completion was higher than at appraisal mainly because of its higher operation efficiency. The four other subprojects and the overall project had lower FIRRs, mainly because of higher O&M costs, longer construction periods, and lower tariffs at completion than anticipated at appraisal. Despite concerns over inadequate heating and gas tariffs, projected net revenue flows for each subproject are positive. Higher heating and CMM gas tariffs will improve the sustainability of the subprojects. The revenues for all the subprojects can cover full capital investment and operating costs during the operational period.

37. The financial performance of the five project PIAs were assessed at completion based on their respective agencies’ entity financial statements for fiscal year 2017. According to the project agreement, in each fiscal year starting 2 years after project operations, the PIA for the each of five subprojects would maintain (a) a minimum debt–service coverage ratio of 1.2:1, (b) a maximum debt–equity ratio of 70:30, and (c) a minimum ratio of current assets to current liabilities of 1:1. Jinzhong Ruiyang CHP Heat Supply company demonstrated strong financial performance and satisfied all the covenanted ratios, but the other PIAs did not satisfy the covenanted ratios, mainly because of high debt ratios and operating losses from low heat tariffs, high coal costs, and low operational efficiency. To improve the situation, their immediate task is to increase the tariff collection ratio (currently under 80%) and install heat measuring devices at client level to the support consumption-based billing system. Because of the project’s benefits to public welfare, local governments have committed to support these companies through debt restructuring and subsidies to help meet debt service obligations and fill the gap between tariff collection and recurring operating costs. County governments could periodically review the heat tariff and gas supply price and initiate timely tariff adjustment to ensure cost recovery as well as debt payment. Based on current assumptions and forecast, the financial performance will improve in the long term.

38. The project operations will have no adverse environmental or social impacts, and will continue to service people in the project area, including people affected by land acquisition and resettlement under the project and vulnerable people.

11

E. Development Impact

39. The development impacts of the project are positive, while the performance of related agencies, including ADB, the borrower, and the executing agency, that provided guidance and assistance for project implementation is satisfactory.

40. The project created significant social and environmental benefits in the project area and helped reduce poverty. Adverse environmental impacts during construction were minor and adequately mitigated. The project effectively implemented safeguard measures for land acquisition and resettlement and generated positive social development and gender impacts.

41. Environment impact. The project’s development impact is considered satisfactory because it achieved its intended impact of an improved environment resulting from reduced atmospheric pollution. The project is improving energy efficiency of the district heating in the project area by 30%, resulting in an estimated energy savings of 104,960 tons of coal equivalent per year. It is delivering substantial environment benefits by avoiding annual net emissions from part A and part B: 315,046 tons of CO2 (254,379 tons at appraisal); 4,611 tons of SO2 ( 4,121 tons at appraisal), 18,288 tons of total suspended particulates (16,234 tons at appraisal), 7,300 tons of particulate matter (6,494 tons at appraisal), 3,181 tons of NOx (1,942 tons at appraisal), and 134,417 tons of coal stove ash and slag.

42. Gender impacts. The gender action plan (GAP) implementation had positive impacts on the lives of women in project areas, who are more exposed to the hazards of using coal in district heating and cooking and more vulnerable to the environmental impacts. The project benefited over 143,961 women by changing heating from household stoves to the district heating system. A total of 52,800 women benefited from switching from coal to natural gas, avoiding indoor air pollution. Women and children benefit more from the heating service and use of CMM gas for cooking than men, as women spend more time at home and take more responsibility for household activities. The project provided 134 temporary jobs to women during construction and 107 regular jobs to women during operation. Women filled over 50% of heating bill collector positions. The project is also expected to support poor, female-headed households by providing heating assistance from the local government and implementing agencies at the full development of the project.

43. Social impact. The project social impact is assessed successful, because the project directly benefited (i) over 297,600 residents in five highly polluted urban areas of Shanxi by providing safer, cleaner, and more reliable heating services and (ii) an additional 30,000 urban households and 134 commercial customers by installing the CMM gas supply and distribution network (Appendix 16). The project improved energy efficiency and reduced emission of greenhouse gases and other pollutants. The expanded district heating systems and increased use of CMM reduced the use of raw coal, wood, and coal briquettes for indoor heating and cooking and benefited public health, particularly the health of the poor and women, through better quality of indoor and outdoor air. The incidence of respiratory diseases and other air pollution related health risks in the project areas are expected decrease at the full development of the project. The project also achieved the following social benefits: (i) improved residents’ living conditions, especially in schools and hospitals during winter for children, patients, and medical staff; (ii) reduced heating costs from switching to centralized, energy-efficient heating systems; and (iii) job opportunities created during construction and operation. The project demonstrated the benefits of improving energy efficiency, created jobs, and helped reduce poverty, which contribute to the economic development of Shanxi.

12

F. Performance of the Borrower and the Executing Agency

44. The borrower, the executing agency, and the PIAs performed the obligations in the loan agreement and the project agreement. The borrower, represented by the Ministry of Finance, signed the loan agreement on 27 March 2013, almost 7 months after ADB Board approval, and completed the requirements for loan effectiveness on 24 April 2013. The Ministry of Finance fulfilled its responsibilities, including submitting an official request to ADB to reallocate ADB loan proceeds and increase the ADB disbursement percentage for some civil works contracts to fully use ADB loan proceeds. In general, the Shanxi Provincial Government had a strong institutional setup and provided adequate funds and policies to ensure successful project implementation. The PMO took proactive measures to address project implementation issues, and helped successfully implement project procurement, construction, and completion by the loan closing date without extensions by coordinating, directing, and providing necessary support to the PIUs. The project leading group also resolved various issues in project implementation. Overall, the performance of the borrower and the executing agency is rated satisfactory.

45. All contractors fulfilled their contractual responsibilities and organized construction activities well. They completed the assigned civil construction and mechanical and electrical installation works satisfactorily in accordance with the contract requirements, albeit with some delays. The PIUs generally rated most of the contractors’ performance as satisfactory. Similarly, the performance of the suppliers of equipment and materials was satisfactory: they delivered equipment and materials on time, installed them properly, and provided necessary technical trainings and services in accordance with the terms and conditions of their respective contracts. During implementation, there were a few minor disputes or contractual difficulties and they were mostly resolved amicably.

46. The performance of the agencies and experts engaged by the PMO or PIUs by self- funding (para. 22) was also satisfactory. The performance of the domestic consultants involved in detailed engineering design, tendering, and construction supervision was generally satisfactory as well.

G. Performance of the Asian Development Bank

47. ADB’s performance is rated satisfactory. ADB conducted seven review missions during implementation, including the midterm review mission. These missions addressed various requirements for project implementation such as procurement, disbursements, loan reallocation, monitoring and evaluation of land acquisition and resettlement, improvement of environmental management, and monitoring of project progress. The PMO viewed ADB’s review and supervision of project implementation as adequate. Disbursement of funds was managed efficiently and there were no disagreements with the executing agency. ADB responded promptly and constructively to PMO and PIU inquiries and requests. The PMO and PIUs expressed appreciation for ADB’s advice and timing in resolving implementation issues. There was no significant problem with ADB procedures.

H. Overall Assessment

48. The project is rated successful overall based on its ratings on the four core evaluation criteria following the methodology provided in the Guidelines for the Evaluation of Public Sector Operations.15 It was highly relevant, effective, efficient, and likely sustainable. All five subprojects

15 ADB. 2016. Guidelines for the Evaluation of Public Sector Operations. Manila.

13

were implemented and are operating satisfactorily. It was rated highly relevant because the project fully aligned with the Government of the PRC’s high priority on improving energy efficiency, its five-year plans, and ADB’s country partnership strategies for the PRC, energy policy, and energy operational plan. The project was rated effective because it achieved its intended outcome and substantially achieved the output targets. It was rated efficient because of the efficient investment and highly efficient implementation process. The project’s likely sustainable rating relied on several factors: the positive results of the financial sustainability analysis, adequate staff capacity for and continuing training on project facilities operation, and the absence of adverse environmental and social impacts. The project has had a strong and positive environmental and developmental impact.

49. Due to its highly satisfactory performance, the project was selected as the 2016 best performing project in the PRC, awarded at the ADB–PRC Country Portfolio Review Meeting in December 2017.16 In addition, the project actively played a leading and demonstrating role in transforming and developing Shanxi Province. The Jinzhong district heating subproject became a pioneer in innovating and constructing international, advanced level heat-exchanger units and box-type heat stations to improve energy efficiency and reduce energy consumption; and the Zhongyang district heating subproject developed the first district heating supply with gas-fired boiler as the heat source for a county-level urban area in Shanxi, which the Shanxi Provincial Government showcased as an environmentally-friendly, sustainable approach using clean energy for heating.

Table 2: Overall Ratings Criteria Rating Relevance Highly relevant Effectiveness Effective Efficiency Efficient Sustainability Likely sustainable Overall Assessment Successful Development impact Satisfactory Borrower and executing agency Satisfactory Performance of ADB Satisfactory ADB = Asian Development Bank. Source: Asian Development Bank.

IV. ISSUES, LESSONS, AND RECOMMENDATIONS

A. Issues and Lessons

50. A key factor in project’s success was the strong commitment of the project proponents. Because project’s targets—greater energy efficiency and a cleaner environment in Shanxi, with reliable heat services for more people—fully aligned with the government’s high priority socioeconomic development strategy, the provincial and local governments attached high importance to project implementation by listing it in the priority project pipelines and practical projects for civilian affairs. The provincial and county governments provided policy, moral, technical, and financial support for the project. All concerned parties demonstrated ownership of the project. With the firm commitment of the governments, all the participants (both project

16 On 4-5 December 2017, ADB-PRC 2017 country portfolio review workshop was jointly organized by MOF and ADB in Beijing, PRC. Loan 2885-PRC was awarded 2016 Best Performing Project in the PRC by ADB during the workshop. The award recognizes projects that demonstrated effective institutional setup, timely start-up of implementation, smooth disbursement and procurement, strict compliance of loan covenants, and effective delivery of scheduled project outputs.

14

proponents and management staff) felt a greater sense of responsibility in ensuring that the subprojects were implemented successfully.

51. Meticulous surveys and studies thoroughly analyzed problems during project preparation, and the project design had feasible technical scenarios that fully fit the actual local demands. All project preparation activities, including the approval of project documents required by PRC regulations, were in place before the loan effectiveness, which facilitated the rapid start of project implementation after loan effectiveness. The major procurement activities were completed within 2 years of loan effectiveness. During implementation, no significant contract variations, disputes or difficulties occurred. Furthermore, the project did not require significant design changes and implementation followed the planned schedule.

52. Executing agency set up effective organization and procedures to ensure adequate guidance from management and proper monitoring of field implementation. On-the-job training also helped project staff fully understand PRC and ADB requirements for the project implementation and improved staff project management skills. PMO and relevant project management authorities effectively supervised, monitored, and controlled costs of project implementation. The PMO and relevant project management authorities intensified project implementation supervision for each of subprojects to identify and address the issues and difficulties during the implementation in a timely manner to keep project implementation on schedule.

53. The consulting services to be financed by the ADB loan, as designed at appraisal, were not recruited successfully as planned, so project management support could not keep pace with the rapid project implementation. Without the project management consulting service support, during early implementation there were gaps in project implementation management compared to the requirements at appraisal: in particular, the PPMS was not established in time and operated effectively, and progress reports were not always submitted in a timely fashion. In addition, some targeted indicators of project performance did not fit well with the routine statistics issued by the government authorities.

B. Recommendations

54. Project completion settlement. It is recommended that the Shanxi Provincial Government should ensure the relevant PIAs carry out the activities of the project completion settlement in line with the PRC’s relevant regulations.

55. Heating and coal-mine methane gas tariff. The Shanxi Provincial Government should ensure county and city governments monitor the financial position of the project entities and take necessary measures to reduce the debt ratio for the Licheng, Qin, and Zhongyang subprojects. Through a regular review, the Shanxi Provincial Government should monitor heating and CMM gas tariffs to determine if they can meet normal full cost recovery criteria for sustainable heating and gas supply services, and consider increasing the tariff and gas tariff as needed.

56. General. Recommendations for the design and implementation of future projects are:

(i) During project preparation, ADB and executing agency should fully analyze the needs for project implementation support to design reasonable consulting services. For well-prepared projects that can start quickly, individual consultants should support project implementation and management, because they can be recruited easily and more quickly through the individual consultant selection procedure, and

15

their qualifications will more likely meet the requirements of project implementation and management support. (ii) During project preparation, targeted indicators of project performance should be easily accessible and designed to make use of routine statistics from government authorities, which will help accurate monitoring and evaluating of project results.

57. Future monitoring. To ensure the sustainability of project facilities, the Shanxi Provincial Government and/or local governments should ensure the respective operators operate and maintain the completed district heating and CMM gas supply facilities in accordance with sound administrative, financial, engineering, environmental, and O&M practices at all times. Monitoring should ensure that they are properly maintained and remain operational. The provincial and/or local governments should assess the project’s effect on energy efficiency and environment using statistics on energy consumption and emissions, as well as its impact on income and poverty.

58. Covenants. It is recommended that the covenants in the loan and project agreements for operations of project facilities be maintained in their existing form during operation.

59. Timing of the project performance evaluation report. A project performance review should be conducted in 2021 or later. By that time, all subprojects should have been in operation for over four years, and this will allow proper evaluation of the project’s impact on energy efficiency and environment improvement in the Shanxi based on accumulated statistics.

16 Appendix 1

DESIGN AND MONITORING FRAMEWORK Performance Targets and Design Summary Achievements Indicators with Baseline Impact Greater energy efficiency By 2020, energy intensity of In 2017, energy intensity of Shanxi and cleaner environment in Shanxi economy reduced by 0.7% economy was 1.29 tons standard Shanxi province compared with 2010, due to coal per CNY10,000, which has improved district heating system. reduced by 38% compared with 2010.

By 2020, emission of SO2 is In 2017, emission of SO2 and reduced by at least 12% and NOx NOx has been reduced by 20% by 15%, compared with 2010. and 25%, respectively, compared with 2010. Outcome Better air quality and By 2018, district heating in the five By 2018, district heating in the five reduced greenhouse gases urban areas reduces aggregate urban areas reduced aggregate emission in five urban areas annual coal consumption by annual coal consumption by in Shanxi province 53,493 tons, thereby avoiding 73,063 tons, which has avoided annual emissions of 133,358 tons annual emissions of 194,025 tons of CO2, 2,677 tons of SO2, 802 of CO2, 3,195 tons of SO2, 2,129 tons of NOx, 10,534 tons of TSP, tons of NOx, 12,588 tons of TSP, compared with 2012. compared with 2012.

By 2018, the CMM distribution By 2018, the CMM distribution system in Liulin city reduces system in Liulin city reduced annual coal consumption by annual coal consumption by 31,897 tons, thereby avoiding 31,897 tons, which has avoided annual emissions of 121,021 tons annual emissions of 121,021 tons of CO2, 1,444 tons of SO2, 1,140 of CO2, 1,426 tons of SO2, 1,052 tons of NOx, and 5,700 tons of tons of NOx, and 5,700 tons of TSP, compared with 2012. TSP, compared with 2012.b

By 2018, the five urban areas By 2018, the five urban areas had improve their record, by at least improved their records, by 20%, in meeting class IIa air quality 16%~27%, in meeting class II air standards (2012 baseline – days quality standards (days standards are met during heating standards were met during 2017- season: Jinzhong-69, Licheng- 68, 2018 heating season: Jinzhong- Qin- 73, Zhongyang- 70, Liulin-70) 82(+19%), Licheng- 80(+18%), Qin- 88(+21%), Zhongyang-89 (+27%), Liulin-81 (+16%).

Appendix 1 17

Performance Targets and Design Summary Achievements Indicators with Baseline Outputs 1. Energy-efficient district By 2017, modern district heating By 2017, modern district heating heating in five urban covering 8.2 million m2, servicing covering 7.57 million m2 servicing areas 270,000 urban residents (83,300 297,600 urban residents (82,186 urban households, 5,300 of which urban households, 490 of which are poor including 703 households are poor including 207 headed by women), and households headed by women), employing 50% women as heating and 58 out of 93 heating bill bill collectors is implemented collectors were women which represents over 62%.

2. Expanded CMM By 2017, CMM gas supply and By 2017, CMM gas supply and distribution network in distribution network are installed, distribution network are installed, Liulin capable of transporting 88.8 capable of transporting 88.6 million m3 of CMM and servicing million m3 of CMM and servicing an additional 30,000 urban an additional 30,000 urban households and 120 commercial households and 134 commercial customers customers

3.Institutional strengthening By 2017, at least 150 staff of By 2017, 150 staff of executing and capacity building executing and implementing and implementing agencies have agencies are trained, including all been trained, including all female female staff directly involving the staff directly involved in project project management, through six management, through six workshops workshops. In total, 61 female staff (100%) directly involved with the project attended training on capacity building.

By 2017, at least one health, By 2017, one health, safety, and safety, and energy conservation energy conservation awareness awareness campaign and campaign and knowledge-sharing knowledge-sharing session session has been conducted. 2 ADB = Asian Development Bank, CMM = coal-mine methane, CO2 = carbon dioxide, km = kilometer, m = square 3 meter, m = cubic meter, NOx = nitrogen oxide, SO2 = sulfur dioxide, TSP = total suspended particulates. a As provided under the Ambient Air Quality Standards GB 3095-1996, class I standards apply to especially protected areas such as natural conservation areas, scenic spots, and historical sites; class II standards apply to residential areas, mixed commercial–residential areas, and cultural, industrial, and rural areas; and class III standards apply to special industrial areas. b The discrepancies of SO2 and NOx emissions are due to different emission factors were used (at completion: 0.313kg 3 3 3 3 SO2/kNm methane, 0.994kg NOx/kNm methane; versus at appraisal: 0kg SO2/kNm methane, 0kg NO2/kNm methane), referring to actual monitoring data in Zhongyang district heating subproject.

18 Appendix 2

PROJECT COST AT APPRAISAL AND ACTUAL

Table A2.1: Cost Estimates by Financier at Appraisal ADB Loan Equity Total Amount Amount Amount ($ million) ($ million) ($ million) Item % % A. Jinzhong District Heating Supply 1 Base cost a. Civil works 1.85 8.83 19.11 91.17 20.96 b. Equipment and materials 39.12 100.00 0.00 0.00 39.12 c. Land acquisition 0.00 0.00 0.00 0.00 0.00 d. Project management/ Others 0.00 0.00 5.40 100.00 5.40 e. Capacity building 0.90 100.00 0.00 0.00 0.90 2 Contingencies a. Physical 0.00 0.00 3.31 100.00 3.31 b. Price 0.00 0.00 3.54 100.00 3.54 Subtotal 41.87 57.18 31.36 42.82 73.23 B. Licheng District Heating Supply 1 Base cost a. Civil works 2.30 42.67 3.22 58 5.52 b. Equipment and materials 15.11 100.00 0.00 0.00 15.11 c. Land acquisition 0.00 0.00 0.22 100 0.22 d. Project management/ Others 0.00 0.00 3.11 100 3.11 e. Capacity building 0.33 100.00 0.00 0.00 0.33 2 Contingencies a. Physical 0.00 0.00 1.17 100 1.17 b. Price 0.00 0.00 1.51 100 1.51 Subtotal 17.74 65.78 9.23 34.22 26.97 C. Qin District Heating Supply 1 Base cost a. Civil works 4.53 40.74 6.59 59.26 11.12 b. Equipment and materials 17.09 100.00 0.00 0.00 17.09 c. Land acquisition 0.00 0.00 1.16 100.00 1.16 d. Project management/ Others 0.00 0.00 3.82 100.00 3.82 e. Capacity building 0.46 100.00 0.00 0.00 0.46 2 Contingencies a. Physical 0.00 0.00 1.67 100.00 1.67 b. Price 0.00 0.00 2.05 100.00 2.05 Subtotal 22.08 59.08 15.29 40.92 37.37 D. Qin District Heating Supply 1 Base cost a. Civil works 1.03 50.24 1.02 49.76 2.05 b. Equipment and materials 3.26 100.00 0.00 0.00 3.26 c. Land acquisition 0.00 0.00 0.00 0.00 0.00 d. Project management/ Others 0.00 0.00 0.64 100.00 0.64 e. Capacity building 0.08 100.00 0.00 0.00 0.08 2 Contingencies a. Physical 0.00 0.00 0.30 100.00 0.30 b. Price 0.00 0.00 0.38 100.00 0.38 Subtotal 4.37 65.13 2.34 34.87 6.71 E. Liulin Coal Mine Methane Gas Distribution 1 Base cost a. Civil works 0.00 0.00 4.19 100.00 4.19 b. Equipment and materials 10.62 100.00 0.00 0.00 10.62

Appendix 2 19

ADB Loan Equity Total Amount Amount Amount ($ million) ($ million) ($ million) Item % % c. Land acquisition 0.00 0.00 0.36 100.00 0.36 d. Project management/ Others 0.00 0.00 1.72 100.00 1.72 e. Capacity building 0.23 100.00 0.00 0.00 0.23 2 Contingencies a. Physical 0.00 0.00 0.85 100.00 0.85 b. Price 0.00 0.00 0.76 100.00 0.76 Subtotal 10.85 57.92 7.88 42.07 18.73 F. Total Investment Cost 1 Base cost a. Civil works 9.71 22.15 34.14 77.85 43.84 b. Equipment and materials 85.20 100.00 0.00 0.00 85.20 c. Land acquisition 0.00 0.00 1.74 100.00 1.74 d. Project management/ Others 0.00 0.00 14.70 100.00 14.70 e. Capacity building 2.00 100.00 0.00 0.00 2.00 Subtotal 96.91 65.72 50.58 34.38 147.49 2 Contingencies 0.00 0.00 15.54 100.00 15.54 3 Interest During Construction and Commitment Charges 3.09 100.00 0.00 0.00 3.09 Total 100.00 60.20 66.12 39.80 166.12 ADB = Asian Development Bank. a ADB financing percentage for civil works categories are different from the disbursement percentages stated in the loan agreement as some of the civil work contracts will be procured based on the government procedures and totally financed by the equity, as shown in Table 10 of the project administration manual. Sources: Project implementing agencies and Asian Development Bank estimates.

20 Appendix 2

Table A2.2: Cost Estimates by Financier at Completion

ADB Loan Equity Total Amount Amount Amount Item ($ million) % ($ million) % ($ million) A. Jinzhong District Heating Supply 1 Base cost a. Civil works 1.90 9.63 17.84 90.37 19.74 b. Equipment and materials 38.93 80.68 9.32 19.32 48.25 c. Land acquisition 0.00 0.00 0.00 0.00 0.00 d. Project management/ Others 0.00 0.00 6.33 100.00 6.33 e. Capacity building 0.00 0.00 0.00 0.00 0.00 2 Contingencies a. Physical 0.00 0.00 0.00 0.00 0.00 b. Price 0.00 0.00 0.00 0.00 0.00 Interest During Construction and 3 Commitment Charges 1.31 100.00 0.00 0.00 1.31 Subtotal 42.14 55.72 33.49 44.28 75.63 B. Licheng District Heating Supply 1 Base cost a. Civil works 2.17 30.43 4.96 69.57 7.13 b. Equipment and materials 14.82 90.92 1.48 9.08 16.30 c. Land acquisition 0.00 0.00 0.00 0.00 0.00 d. Project management/ Others 0.00 0.00 1.29 100.00 1.29 e. Capacity building 0.00 0.00 0.00 0.00 0.00 2 Contingencies a. Physical 0.00 0.00 0.00 0.00 0.00 b. Price 0.00 0.00 0.00 0.00 0.00 Interest During Construction and 3 Commitment Charges 0.53 100 0.00 0.00 0.53 Subtotal 17.52 69.39 7.73 30.61 25.25 C. Qin District Heating Supply 1 Base cost a. Civil works 6.88 58.90 4.80 41.10 11.68 b. Equipment and materials 17.05 100.00 0.00 0.00 17.05 c. Land acquisition 0.00 0.00 0.24 100.00 0.24 d. Project management/ Others 0.00 0.00 0.38 100.00 0.38 e. Capacity building 0.00 0.00 0.00 0.00 0.00 2 Contingencies a. Physical 0.00 0.00 0.00 0.00 0.00 b. Price 0.00 0.00 0.00 0.00 0.00 Interest During Construction and 3 Commitment Charges 0.48 100 0.00 0.00 0.48 Subtotal 24.41 81.83 5.42 18.17 29.83

Appendix 2 21

ADB Loan Equity Total Amount Amount Amount Item ($ million) % ($ million) % ($ million) D. Zhongyang District Heating Supply 1 Base cost a. Civil works 1.58 76.33 0.49 23.67 2.07 b. Equipment and materials 3.27 100.00 0.01 0.00 3.28 c. Land acquisition 0.00 0.00 0.00 0.00 0.00 d. Project management/ Others 0.00 0.00 0.44 100.00 0.44 e. Capacity building 0.00 0.00 0.00 0.00 0.00 2 Contingencies a. Physical 0.00 0.00 0.00 0.00 0.00 b. Price 0.00 0.00 0.00 0.00 0.00 Interest During Construction and 3 Commitment Charges 0.16 100.00 0.00 0.00 0.16 Subtotal 5.01 84.20 0.94 15.80 5.95 E. Liulin Coal Mine Methane Gas Distribution 1 Base cost a. Civil works 0.00 0.00 5.50 100.00 5.50 b. Equipment and materials 10.49 100.00 0.00 0.00 10.49 c. Land acquisition 0.00 0.00 0.17 100.00 0.17 d. Project management/ Others 0.00 0.00 0.76 100.00 0.76 e. Capacity building 0.00 0.00 0.00 0.00 0.00 2 Contingencies a. Physical 0.00 0.00 0.00 0.00 0.00 b. Price 0.00 0.00 0.00 0.00 0.00 Interest During Construction and 3 Commitment Charges 0.43 100.00 0.00 0.00 0.43 Subtotal 10.92 62.94 6.43 37.06 17.35 F. Total Investment Cost 1 Base Cost a. Civil works 12.53 19 33.59 81 46.12 b. Equipment and materials 84.56 86 10.81 14 95.37 c. Land acquisition 0.00 0.00 0.41 100.00 0.41 d. Project management/ Others 0.00 0.00 9.20 100.00 9.20 e. Capacity building 0.00 0.00 0.00 0.00 0.00 Subtotal 97.09 60 54.01 40 151.10 2 Contingencies 0.00 0.00 0.00 0.00 0.00 Interest During Construction and 3 Commitment Charges 2.91 100.00 0.00 0.00 2.91 Total 100.00 64.93 54.01 35.07 154.01 Sources: Asian Development Bank. Project completion report prepared by the executing agency.

22 Appendix 2

Table A2.3: Project Financing at Appraisal and Completion ($ million) Source At Appraisal At Completion Total % Total % A. Asian Development Bank 100.0 60.2 100.0 64.9 B. Equity 66.1 39.8 54.0 35.1 Total (A+B) 166.1 100.00 154.0 100.00 Sources: Asian Development Bank. Project completion report prepared by the executing agency.

Appendix 3 23

PROJECT COST BY FINANCIER ($ million)

Appraisal Actual % Increase (Decrease) Amount Amount Item ($ million) ($ million) A. Jinzhong District Heating Supply 1 Base cost a. Civil works 20.96 19.74 (5.82) b. Equipment and materials 39.12 48.25 23.34 c. Land acquisition 0.00 0.00 0.00 d. Project management/ Others 5.40 6.33 17.22 e. Capacity building 0.90 0.00 (100.00) 2 Contingencies 6.85 0.00 (100.00) 3 Interest During Construction and Commitment Charges 1.35 1.31 (2.96) Subtotal 74.59 75.63 1.39 B. Licheng District Heating Supply 1 Base cost a. Civil works 5.52 7.13 29.17 b. Equipment and materials 15.11 16.30 7.88 c. Land acquisition 0.22 0.00 (100.00) d. Project management/ Others 3.11 1.29 (58.52) e. Capacity building 0.33 0.00 (100.00) 2 Contingencies 2.68 0.00 (100.00) Interest During Construction and 3 Commitment Charges 0.64 0.53 (17.19) Subtotal 27.62 25.25 (8.58) C. Qin District Heating Supply 1 Base cost a. Civil works 11.12 11.68 5.04 b. Equipment and materials 17.09 17.05 (0.00) c. Land acquisition 1.16 0.24 (79.31) d. Project management/ Others 3.82 0.38 (90.05) e. Capacity building 0.46 0.00 (100.00) 2 Contingencies 3.72 0.00 (100.00) Interest During Construction and 3 Commitment Charges 0.67 0.48 (28.36) Subtotal 38.04 29.83 (21.58) D. Zhongyang District Heating Supply 1 Base cost a. Civil works 2.05 2.07 0.00 b. Equipment and materials 3.26 3.28 0.00 c. Land acquisition 0.00 0.00 0.00 d. Project management/ Others 0.64 0.44 (31.25) e. Capacity building 0.08 0.00 (100.00) 2 Contingencies 0.68 0.00 (100.00) Interest During Construction and 3 Commitment Charges 0.14 0.16 14.29 Subtotal 6.86 5.95 (13.28) E. Liulin Coal Mine Methane Gas Distribution 1 Base cost a. Civil works 4.19 5.50 31.26

24 Appendix 3

Appraisal Actual % Increase (Decrease) Amount Amount Item ($ million) ($ million) b. Equipment and materials 10.62 10.49 (1.22) c. Land acquisition 0.36 0.17 (52.78) d. Project management/ Others 1.72 0.76 (55.81) e. Capacity building 0.23 0.00 (100.00) 2 Contingencies 1.61 0.00 (100.00) Interest During Construction and 3 Commitment Charges 0.29 0.43 48.28 Subtotal 19.01 17.35 (8.73) F. Total Investment Cost 1 Base Cost

a. Civil works 43.84 46.12 520 b. Equipment and materials 85.20 95.37 11.94 c. Land acquisition 1.74 0.41 (91.95) d. Project management/ Others 14.69 9.20 (36.70) e. Capacity building 2.00 0.00 (100.00) 2 Contingencies 15.54 0.00 (100.00) Interest During Construction and 3 Commitment Charges 3.09 2.91 (5.83) Total 166.12 154.01 (7.29)

Appendix 4 25

DISBURSEMENT OF ADB LOAN PROCEEDS

Table A4.1: Annual and Cumulative Disbursement of ADB Loan Proceeds ($ million) Annual Disbursementa,b Cumulative Disbursementa,b Amount Amount Year ($ million) % of Total ($ million) % of Total 2013 0.03 0 0.03 0 2014 56.80 57 56.83 57 2015 23.06 23 79.89 80 2016 14.93 15 94.82 95 2017 5.17 5 99.99 100 2018 0.00 0 99.99 100 Total 100.00 100 100.00 100 Note: Numbers may not sum precisely because of rounding. a Includes disbursements to advance account, formerly called imprest account. b From eOps after actualization. Source: Asian Development Bank.

Figure 4.1: Projection and Cumulative Disbursement of ADB Loan Proceeds ($ million)

26 Appendix 5

PROJECT IMPLEMENTATION SCHEDULE

2013 2014 2015 2016 2017 Activities Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

A Jinzhong DH System Development

1. Design and tender documentation

2 Tender invitation, assessment, and contract award

3 Civil works construction of HESs

4 Equipment and pipeline installation (HES and SCADA)

5 Testing and commissioning

B Licheng DH System Development

1. Design and tender documentation

2 Tender invitation, assessment, and contract award

3 Civil works construction of HESs

4 Equipment and pipeline installation (HES and SCADA)

5 Testing and commissioning

C Qin DH System Development

1. Design and tender documentation

2 Tender invitation, assessment, and contract award

3 Civil works construction of HESs

4 Equipment and pipeline installation (HES and SCADA)

5 Testing and commissioning

D Zhongyang DH System Development

1. Design and tender documentation

2 Tender invitation, assessment, and contract award

3 Civil works construction of HESs

4 Equipment and pipeline installation (HES and SCADA) 5 Testing and commissioning E Liuling CMM Gas Supply and Distribution

1. Design and tender documentation

2 Tender invitation, assessment, and contract award

3 Civil works of valve stations, office buildings

4 Pipelines layout

5 Equipment installation and commissioning

Implementation Schedule Planned at Appraisal

Actual Implementation Schedule Up to the PCR

Appendix 6 27

CHRONOLOGY OF MAJOR EVENTS

Date Events 2010 24 Nov Project concept paper and categorizatin meeting held 2011 25 Oct – 3 Nov Loan Fact-Finding Mission fielded 2012 17 Jan The revised environment categorization form endorsed 28 Feb Staff review committee meeting held 28-29 Mar Loan negotiations 1 Aug Board circulation 31 Aug Loan approved 2013 21-22 Mar Pre-Inception mission fielded 27 Mar Loan signing 24 Apr Loan effectiveness 15 Aug First disbursement 11-13 Nov Inception mission fileded 24 Dec First ICB goods contract under Licheng subproject awarded 29 Dec First NCB Civil Works contract under Licheng subproject awarded 2014 04 Apr Goods contract under Jinzhong subproject awarded 19 Jul Goods contract under Qin subproject awarded 23 Sept Civil works contract under Qin subproject awarded 20 Oct Goods contract under Liulin subproject awarded 2015 20 Mar Goods contract under Zhongyang subproject awarded 15 May Civil works contract under Zhongyang suproject awarded 1 Jun Project administration delegated to ADB Resident Mission in the People’s Republic of China 2016 14 Jun Civil works contract under Jinzhong subproject awarded 8-12 Aug Midterm review missioned feilded 2017 31 Aug Reallocation of loan proceeds and adjustment of disbursemen percentage 2018 6-13 Mar Porject completion review mission fielded 7 Jun Last disbursement 8 Jun Actual financial closing

ADB = Asian Development Bank, ICB = international competitive bidding, NCB = national competitive bidding. Sources: Asian Development Bank and Hebei Provincial Project Management Office.

28 Appendix 7

PROJECT IMPLEMENTATION ARRANGEMENT AND FUND FLOW

The Asian Development Bank

Shanxi Provincial Government - Executing Agency (Project Leading Group)

Shanxi Provincial DRC Shanxi Provincial Finance (Project Management Office) Bureau

Consultants

Project County/City Governments - Implementation Agencies (County/City DRCs/Finance Bureaus)

Project Implementation Units

Contractors/Suppliers

Coordinating and guiding Providing guidance

Managing and overseeing Implementing

Appendix 7 29

Chart of Fund Flows

PRC/Borrower Asian Development Bank (Ministry of Finance)

Shanxi Provincial Finance Advance/Replenishment for Imprest Account Bureau Provincial PMO

Project County/City Government (Finance Bureau)

Project Implementation Units

Contractors/Suppliers

Lending/relending Claim for payment/withdrawal application

Repayment Disbursement

30 Appendix 8

CONTRACT AWARDS OF ADB LOAN PROCEEDS

Table A8.1: Annual and Cumulative Contract Awards of ADB Loan Proceeds ($ million) Annual Contract Awardsa,b Cumulative Contract Awardsa,b Amount Amount Year ($ million) % of Total ($ million) % of Total 2013 16.99 17 16.99 17 2014 73.35 76 90.34 93 2015 4.85 5 95.19 97 2016 1.90 2 97.09 100 2017 0.00 0 97.09 100 2018 0.00 0 97.09 0 Total 97.09 100 97.09 100 Note: Numbers may not sum precisely because of rounding. a Classified by PCSS dates. b From eOps after actualization. Source: Asian Development Bank.

Figure 8.1: Projection and Cumulative Contract Awards of ADB Loan Proceeds ($ million)

Appendix 9 31

ADB-FINANCED CONTRACT PACKAGES ($ million)

Contr- Procure- Contract ADB ADB act PCSS ment Date Contract Value Financing Financing No. Nos. Contract Description Mode Approved Date Contractor/Supplier ($/CNY) (CNY) ($) A-LC-02 0001 Licheng DHS, ICB 24-Dec-13 20-Dec-13 China Textile Industrial 92,081,385.30 92,081,385.30 14,820,261.86 Equipment for boiler Corporation for Foreign house, auxiliaries, HESs Economic and Technical and pipeline Cooperation A-LC-01 0002 Licheng DHS, Civil NCB 29-Dec-13 20-Dec-13 Linzhou Changhong 19,980,105 13,385,993.96 2,165,113.70 Works of boiler house Construction Engg.Co. Ltd. and auxiliaries 13CN01GT 0003 Jinzhong DHS, ICB 28-Jan-14 20-Feb-14 China IPPR International 46,420,672.99 - 38,934,976.81 F31 Equipment for heating Engineering Co. Ltd. WD0004 exchange stations (HESs) and pipelines A-QX-02 0004 Qin DHS, Equipment for ICB 14-Jul-14 16-Jun-14 Shanghai Golden 17,053,330.79 - 17,053,330.79 boiler houses, Construction Group Co. auxiliaries, HESs and Ltd. pipeline A-QX-01 0005 Qin DHS, Civil Works of NCB 23-Sep-14 20-Aug-14 Shanxi Construction Eng’g 48,285,590.96 43,939,887.77 6,879,511.90 boiler house and HESs Group Corporation A-LL-01 0006 Liulin CMM, ICB 29-Jul-14 29-Aug-14 JV: Shanghai Electric Int. 10,488,000.00 - 10,488,000.00 procurement of medium Eco&Trading Co. Ltd. and and low gas pipelines, Gas Design Inst. of resource gas pipelines, compressors and pressure regulation cabinets 14CN01GT 0007 Zhongyang DHS, ICB 6-Jan-15 22-Jan-15 Huaxia Hanhua Chemical 3,270,000.00 - 3,270,000.00 F31WD004 Equipment for boiler Equipment house and HESs, and pipelines ZHY-04.2 0008 Zhongyang DHS, Civil NCB 24-Nov-14 22-Jan-15 Luliang Municipal 13,120,411.97 10,225,440.74 1,579,617.41 Works for HESs and Construction and pipeline Installation Co. ZJH01.2 0009 Jinzhong DHS, Civil NCB 17-Feb-16 15-Apr-16 No. 1 Construction 18,089,294.29 11,913,818.40 1,895,809.22 Works for HESs and Engineering Group Co. auxiliary building 1 Ltd. Total 97,086,621.69 Source: Asian Development Bank.

32 Appendix 10

GENDER EQUALITY ACTION PLAN ANALYSIS

A. Narrative Analysis

1. The project improved the energy efficiency and reduced emission of greenhouse gases and other pollutants in Shanxi province by introducing and expanding energy efficient district heating systems and expanding a coal-mine methane (CMM) gas supply and distribution system in the project areas. Poor quality of the previous heating method using domestic household stove had a disproportionate impact on women as they take more responsibility for household activities, such as collecting fuel and operating domestic household stoves. Women were also predisposed to high indoor air pollution that may cause respiratory sickness during winter season, carbon monoxide poisoning and fire accidents caused by household stoves. The project closed 398 small inefficient coal-fired boilers and around 4,000 household heating stoves. 196,761 women, representing 48% of direct beneficiaries benefited from the project by switching to centralized heating system and CMM gas for cooking. The project had positive impact on women including (i) access to cleaner, safer, and reliable heating system; (ii) reduced domestic chores workload and time spent for space heating; (iii) reduced incidence of respiratory diseases related to indoor air pollution; and (iv) avoiding carbon monoxide poisoning and fire accidents caused by household stoves. The project also assisted poor female-headed households by providing heating assistance from the local government and implementing agencies. Employment opportunities for women were also prioritized in the delivery of centralized district heating services. The detailed implementation results of GAP activities and targets are in Table A10.1.

B. Gender Action Plan Achievements and Outcome

2. Given women are more exposed to hazards of using coal in district heating and cooking, education in safety measures and energy conservation are required. To ensure that women receive more benefits of heating service and use of CMM, a gender action plan (GAP) was prepared for the project and gender specific measures were developed to ensure that targets are met, women are given opportunity to fully participate in, and enjoy project benefits and adverse effects upon women are avoided or mitigated. Regular monitoring has been done during project implementation by Asian Development Bank (ADB) and executing agency staff.

3. The project was successful in achieving the GAP targets and outputs. Women in project area engaged predominantly in domestic chores and cooking, the increased use of CMM and the expanded district heating reduced the use of raw coal, wood, and coal briquettes as fuels for indoor heating and cooking, and benefited women significantly who spend most of the time indoors. With closure of small polluting neighborhood boilers and supply heat through cleaner centralized district heating systems, a total of 143,961 women and 101,564 children in 61 schools including patients and medical staff in 18 hospitals have benefited from centralized heating services. 52,800 women have benefited from fuel switching (from coal to natural gas) in terms of improved health and avoiding carbon monoxide poisoning and fire accidents.151 poor women-headed households were given pro- poor tariff assistance in Jinzhong County and Zhongyang County while the rest of project counties will eventually develop heating subsidy systems. The connection fee was waived by the heating companies to all women-headed households.

4. The project prioritized women for employment for physical work. It generated a total of 134 temporary jobs to women during project construction and 107 fixed jobs to women during operation. Female bill collectors were promoted in each subproject for gender responsive customer services. Over 50% (58 out of 93) of heating bill collectors were women by 2017 in the project area. CMM was made available for cooking, heating and other domestic users, which disproportionally benefited

Appendix 10 33 women who take more responsibilities of housework activities. More than one hour was reduced in time spent on domestic chores, whereas an average of two and half hours were spent in the past. Women were relieved from reduced domestic chores workload and time spent for space heating, fire cooking, coal shoveling, and handling ash, etc.

5. Joint sessions among heating companies and women’s federation on ‘gender responsive district heating’ were organized in Jinzhong City, Qin County, Licheng and Zhongyang County. More than 210 women participated and benefited from the sessions. Additionally, joint knowledge sharing awareness campaigns have been conducted in the project areas by heating companies and relevant government agencies to benefit all the population including female beneficiaries of 196,761.

C. Lessons Learned

6. In terms of affordability, the target of providing subsidy by the local governments to poor female headed households has not been fully achieved. It is partially due to the inefficient analysis and monitoring of local financial situation and policy availability during project preparation. The respective local governments currently have challenges in developing such policy to provide subsidy which is equivalent to 70% of heating tariff to poor women-headed households in the short term. Adequate funds for government subsidies for poor women-headed households are currently not available in Licheng county since the government has been facing financial difficulties. The government has plan to develop fiscal system that is more beneficial towards poor, especially women-headed households once there is adequate budget. Specific measures have been undertaken in Qin County since 2018 by identifying the target groups and developing pro-poor policies which are expected to implement in 2019.

34 Appendix 10

Table A10.1: GENDER ACTION PLAN RESULTS

Project Output Activity Indicators and Targets Achievements at Project Completion Decommission small polluting 133,000 women, 100,400 Achieved. A total of 143,961 women,101,564 children in 61 schools, neighborhood boilers and children in 51 schools, and and patients and medical staff in 18 hospitals were provided heating supply heat through cleaner patients and medical staff in 17 services by 2017. centralized district heating hospitals are provided heating systems. services by 2017.

Ensure heating assistance to At least 703 women-headed Not achieved. 151 poor women-headed households were provided poor women-headed households are given heating assistance by 2017 in Jinzhong County and Zhongyang households (70% subsidy of assistance by 2017. County. Adequate funds for government subsidies for poor women- Expanded coverage and heating tariff by the local headed households are not available in Licheng county since the government and 100% waiver government has been facing financial difficulties. The government has improved district heating in of connection fee from the plan and political will to support poor households once there is enough project cities and towns heating company). budget. Specific measures have been undertaken in Qin County since 2018 by identifying the target group and developing pro-poor policies which are expected to implement in 2019.The connection fee was waived for all women-headed households. Job opportunities for women 50% of heating bill collectors Achieved. A total of 134 temporary jobs were provided to women are created and women are (from the current 20%) are during project construction and 107 regular jobs to women during given equal opportunity for women by 2017. project operation. Over 50% of heating bill collectors were women by employment (e.g., promoting 2017. 58 out of 93 heating bill collectors were women which represents women as heating bill over 62%. Relevant training was provided to women. collectors) CMM gas is made available for One-hour reduction in time Achieved. CMM was made available for cooking, heating and other cooking, heating and other spent on domestic chores by domestic users. 52,800 women have benefited from CMM supply domestic uses 2017; baseline information service. More than one hour was reduced in time spent on domestic Expanded CMM gas was collected during the chores, whereas an average of two and half hours were spent daily in distribution network survey and will be monitored in the past. Women were relieved from reduced domestic chores project documentation. workload and time spent for space heating, fire cooking, coal shoveling, and handling ash, etc.

Appendix 10 35

Project Output Activity Indicators and Targets Achievements at Project Completion Expanded CMM gas CMM gas is made available for Cases of carbon monoxide Implemented. Carbon monoxide poisoning cases and fire accidents distribution network cooking, heating and other poisoning and fire accidents report was zero in the project areas by 2017. domestic uses caused by household stoves reported zero by 2017 Promote capacity building of 100% of female staff directly Achieved. A total of 61 female staff (100%) directly involved with the female staff involved with the project will project attended training on capacity building. attend training. Organize a joint session among At least one session with Achieved. Joint sessions among heating companies and women’s heating companies on “gender participation from female federation on “gender responsive district heating” were organized in responsive district heating” and representatives and heat users Jinzhong City, Qin County, Licheng and Zhongyang County. More than service delivery feedback from each subproject area by 210 women participated and benefited from the sessions. Institutional strengthening and mechanism in partnership with 2017. capacity building women’s federation. Conduct community level Joint knowledge sharing/ Achieved. Joint knowledge sharing awareness campaigns have been knowledge sharing sessions/ awareness campaigns will target conducted in the project areas by heating companies and relevant energy conservation awareness entire female population of government agencies to benefit all the population including female campaigns for each subproject 133,000 female beneficiaries in beneficiaries of 196,761. area. subproject areas by 2017.

Source: PMO Project Completion Report.

36 Appendix 11

ENVIRONMENTAL IMPACT ANALYSIS

A. Introduction

1. The project mainly consisted of (i) urban districting heating supply (Part A) in four subproject counties (Jinzhong, Licheng, Qin and Zhongyang), comprising, comprising construction of 261 megawatt (MW) of heat generation capacity using large high-efficiency pulverized coal (PC)-fired or natural gas-fired boilers equipped with flue gas desulfurization scrubbers and filter baghouse emission control, 132 heat exchange stations, 125.6 kilometers (km) of heat supply pipeline, and closure of 398 small inner-city boilers (with an aggregated capacity of 442 MW previously used for district heating) besides 4,000 coal-fired household stoves during 2014 to 2017; (ii) coal-mine methane (CMM) gas supply and distribution (Part B) in Liulin county, comprising construction and installation of a CMM gas supply and distribution network (including 50,000 cubic meters (m3) of storage tanks, gas distribution pipelines of low (12 km) and medium pressure (21 km) and 20 pressure regulating stations (to deliver gas to the end-users) for domestic and commercial use year round, and district heating in winter, at a total capture capacity of 88.6 million m3 CMM gas per year.

2. The project is classified as category B for environment in accordance with the Asian Development Bank (ADB) environmental categorization. Domestic environmental impact assessment documents were prepared for all five subprojects under Part A and Part B, and approved by the Shanxi Provincial Environmental Protection Bureau (EPB) and the relevant city EPBs in 2009~2012. The initial environmental examination (IEE) was prepared in accordance with the ADB Safeguard Policy Statement (SPS, 2009) and submitted to ADB in 2012. In response to a minor change in scope in 2014 to accommodate (i) the relocation of CMM gas storage station under the Liulin subproject, and (ii) change from coal-fired boiler to natural gas boiler under the Zhongyang subproject, and approval of the domestic Tabular Environmental Impact Assessment Report by Luliang Municipal Environment Protection Bureau in 2014. An environment and social due diligence report was prepared in accordance with the ADB Safeguard Policy Statement (2009) and submitted to ADB in 2014. As required under national laws and regulations of the People’s Republic of China (PRC), all subprojects in Part A and Part B will be reviewed through the environment protection completion audit by the Shanxi provincial and municipal environmental protection bureaus by 2019, excluding Licheng subproject already completed in 2017. The demolition of boilers was carried out in accordance with the applicable environmental and safety standards of the PRC.

B. Institutional Setup and Environmental Management

3. The Shanxi Provincial Government had overall responsibility for ensuring the environmental management plan (EMP) was implemented in accordance with the domestic environment impact assessments and IEE. The project management office (PMO) was established in the Shanxi Provincial Development and Reform Commission and was responsible for managing, coordinating, and supervising EMP implementation. A grievance redress committee was established inside the PMO. Each project implementing agency (PIA) established an environmental management unit responsible for implementation and monitoring of the EMP during subproject construction and operation. The PMO designated environmental staff to coordinate with each environmental management unit, conduct environmental management of subprojects, and oversee EMP implementation and monitoring for all subprojects, with assistance from the consultant engaged under the Part C: Institutional strengthening.

4. During the construction phase, all contractors kept daily and weekly environmental records,

Appendix 11 37 and prepared environmental monitoring reports that were submitted to the PIAs. During operations, the PIAs were responsible for implementing the mitigation measures contained in the domestic environment impact assessment and IEE, and reported to provincial and municipal environment protection bureaus and the PMO. The PMO submitted seven environmental monitoring reports (EMRs) to ADB, at twice per year during construction and once per year for 2 years following completion of construction. Public opinion surveys including at least 191 people in five subproject area at completion indicated that people were generally satisfied with project performance during construction and operation, and that no formal complaint was received during project implementation.

C. Environmental Impacts and Mitigation Measures Undertaken

5. The IEE contained information on likely environmental impacts, mitigation measures, and monitoring requirements during construction and operation. The responsible parties carried out all mitigation measures needed to reduce adverse environmental impacts in accordance with the IEE. Table A11.1 presents the implementation status of mitigation measures during construction and operation.

Table A11.1: Environmental impacts, mitigation measures, and implementation status

Issue Major Impacts, Mitigation Measures Responsible party and and Monitoring Frequency compliance status

Construction Phase Soil erosion Temporary soil stockpiles were covered, excavated trenches re- Contractors, construction compacted, sediment fences installed to minimize sediment runoff, supervision companies and disturbed surfaces revegetated to minimize erosion. and EMUs,

Fully complied with.

Implementation of soil erosion mitigation measures was monitored by the EMUs and construction supervision companies. Soil All hazardous and non-hazardous waste from subproject Contractors, contamin construction and demolition of small, inner-city coal-fired boilers was construction supervision ation by collected, stored onsite in designated storage facilities, and companies, EMUs, and hazardou transported offsite to approved disposal facilities. Spill cleanup local EPBs. s waste equipment was provided. No contaminated land legacy issues due to and demolition of small coal-fired boilers were reported. Fully complied with. materials, including Implementation of soil pollution prevention measures was monitored hydrocar by the EMUs and construction supervision companies. bons Water To mitigate siltation of water bodies and dispose of wastewater Contractors, appropriately, (i) sediment fences were installed to minimize construction supervision sediment runoff, (ii) wastewater was treated using septic tanks, and (iii) companies, EMUs, and all construction equipment washdown areas were fitted with water local EPBs. collection basins equipped with oil separators and sediment traps. Fully complied with. Implementation of wastewater mitigation measures was monitored by the EMUs and construction supervision companies. Air quality To mitigate generation and emission of dust from construction Contractors, machinery, transportation routes and material handling sites were construction supervision sprayed with water, and materials were covered during companies, EMUs, and transportation. Local EPBs confirmed that the air quality of subproject local EPBs. construction sites met the Class II air quality standard (GB3095- 2012). Fully complied with.

Implementation of air pollution mitigation measures was monitored by the EMUs, construction supervision companies, and the local EPBs.

38 Appendix 11

Issue Major Impacts, Mitigation Measures Responsible party and and Monitoring Frequency compliance status

Noise Construction-related noise from vehicles and construction machinery Contractors, construction did not exceed noise levels in the Emission Standard of supervision companies, Environmental Noise for Boundary of Construction Site (GB12523- EMUs, and local EPBs. 2011). Construction works were prohibited between 7 pm and 6 am. Implementation of noise mitigation measures monitored by EMU, Fully complied with. construction supervision companies, and local EPBs.

Operation phase District The heat source plants were completed with (i) some 80 meters of EMUs and local EPBs’ Heating high stacks to minimize direct impacts on adjacent areas, (ii) filter mitigation measures were baghouse emission control systems with 95~98% efficiency, and (iii) also applicable to the dual alkali flue gas desulfurization (FGD) scrubbers with more than district heating 85% efficiency. Each subproject under Part A was also equipped with subprojects in Jinzhong, soundproof covers and walls for noise mitigation, and coal and fly- Licheng, Qin and ash stockyards with clay and synthetic liners to avoid groundwater Zhongyang. contamination. All industrial wastewater was fully recycled, without discharge outside, excluding seasonal tail wastewater from desulfuration unit further treated by local wastewater treatment plant. Domestic wastewater was collected and pretreated by septic tank Fully complied with. before being discharged into municipal network. Each subproject under Part A prepared and is implementing an operations manual that Reported annual emission includes spraying water on coal and fly- ash, and covering coal yards from the constructed heat to minimize airborne dust dispersion. Wastewater is used for water plants was below the spraying. All coal stove ash and slag were fully sold out and 100% government and the EHS recycled for building material. guideline standard maximum emission values. The heat source plants under Part A fully complied with the Emission standard of air pollutants for boiler (GB13271-2014). Hourly emission monitoring from each heat source plant is required. Currently all heat source plants under Part A are equipped with emission monitoring devices that are also connected to the environment monitoring system of local EPBs. CMM supply Domestic wastewater from CMM storage station and PRSs is being EMU and treated with station-specific septic tanks and used for watering trees distribution and grass, and for road spraying. CMM gas transmission, storage and distribution systems under Part B were fully equipped with gas leakage monitoring devices for early detection and warning.

Regular daily inspection for transmission and distribution routes is Fully complied with. being implemented. Quarterly revegetation inspection along the pipeline route has been carried out since 2017. Source: Information were collected by Loan Implementation Environment Consultant.

6. All project components were constructed and are operated in accordance with the EMP. The total actual cost of environmental protection measures at completion was CNY58.69 million, accounting for 5.74% of total project cost. Ongoing environmental monitoring during operation is estimated at CNY45,000 per annum. Monitoring stations to measure annual emissions from newly installed boilers under the project were installed around the heating plants and the surrounding residential quarters and are linked with the air quality monitoring system under local EPBs. Emissions of particulate matter smaller than 10 micrometers (PM10), sulfur dioxide (SO2), and 1 nitrogen oxide (NOx) from newly installed boilers under Part A were measured and verified by

1 For three coal burning heating source plant, selective catalytic reduction (SCR) denitrification technology is used by Jinzhong subproject (Ruiguang CHP) and Qin subproject; while selective non-catalytic reduction (SNCR) is used by Licheng subproject, all fully funded domestically.

Appendix 11 39 local EPBs, and the results met Emission standard of air pollutants for boiler (GB13271-2014),2 and the WHO guidelines.

D. Environmental Benefits

7. Overall the project improves the energy efficiency of district heating in the project area by 30%, resulting in an estimated energy savings of 104,960 tce per year. The project delivers substantial environment benefits through avoided annual net emissions associated with Part A and Part B, specifically 315,046 tons of carbon dioxide (CO2), 4,611 tons of sulfur dioxide (SO2), 18,288 tons of total suspended particulates, 7,300 tons of particulate matter (PM10), 3,181 tons of 3 NOx, and 134,417 tons of coal stove ash and slag.

8. At appraisal in heating season of 2012/2013, the project area in the five subproject city/county urban areas fell between categories II and III in terms of ambient air quality standards (Ambient air quality standards, GB3095-2012). The air pollutants were mainly SO2 and total suspended particulates, caused by numerous small, inner-city coal-fired boilers. Although the targeted air quality record of the five urban areas’ days standards met during heating season improved by at least 20% has not been achieved so far, this project serves as important part of five subproject city/county governments’ initiatives combatting Beijing-Tianjin-Hebei regional air pollution.

E. Conclusion

9. The project met the initial objectives and delivered substantial environmental benefits to improve ambient air quality in targeted areas of Shanxi Province in PRC. Environmental management and associated mitigation measures were properly implemented during construction and operation. Environment monitoring was implemented by environmental management units of the PMO and each PIA. No environmental complaints were received during the construction and operation stages of all subprojects under Part A and Part B.

2 For Licheng and Qin subprojects, the special limitation for air pollutants (more stringent requirements than usual heating supply plant, equivalent to Special limitations of air pollutants of Emission standard of air pollutants for thermal power plants (GB 13223-2011) are applicable. 3 This considers the NOx reduction by FGD and Particulate Emission Control Systems, so is much higher than the estimated reduction of NOx,1,942 tons at appraisal when denitrification by FGD and Particulate Emission Control Systems is not counted on.

40 Appendix 12

EVALUATION OF LAND ACQUISITION AND RESETTLEMENT IMPLEMENTATION

A. Background

1. The project was category B for involuntary resettlement safeguard during project preparation. Among five subprojects, Liulin county coal-mine methane (CMM) subproject would involve land acquisition and resettlement, the other subprojects entail no land acquisition, restriction in land use, or structure demolition, as they will be implemented on government land or existing premises. A draft resettlement plan was prepared for Liulin CMM subproject based on feasibility study report. According to the draft resettlement plan, the Liulin CMM subproject would permanently acquire 24.7 mu1, of which 15 mu is cultivated land and would affect 17 people from 4 households. Of the remaining land, 7.7 mu is wasteland and 2 mu is forestry land and will not affect any people. The total budget for the land acquisition of the subproject was estimated at CNY2.326 million.

B. Scope Change and Due Diligences

2. Liulin CMM subproject experienced a scope change in 2015 since the site of CMM storage station was decided to shift from Jiajiayuan village to Hechang village. An updated resettlement plan appended by a due diligence report (DDR) for the scope change was prepared and submitted to the Asian Development Bank (ADB) in 2016. The DDR concludes that (i) 12.6 mu land used for the CMM storage station is part of the land acquired for central heating plant (CHP), (ii) 45 mu land was acquired for Hechang CHP in 2013 and transferred to state-owned land, (iii) the acquired land was not contracted by households so that land acquisition did not affect individuals, and (iv) land compensation has been fully paid to Hechang village and use of land compensation fund was transparent. In addition, the updated resettlement plan also indicates that no houses will be affected, and construction of pipelines will only temporarily use exiting state-owned roads. A total of CNY3.118 million road restoration cost is included in project budget.

C. Land Acquisition and Resettlement Impacts

3. Liulin CMM subproject consists of three components: (i) one gas storage and distribution station; (ii) 20 gas pressure adjustment stations distributed in the project area; and (iii) 43.1 km of gas pipeline to connect between the gas storage and distribution station and gas pressure adjustment stations. According to the updated resettlement plan and DDR, the proposed new site of CMM storage station is located at Yushuta Ditch, Hechang village, Liulin Town. A total of 45 mu collective lands in Yushuta Ditch were permanently acquired from Hechang village in 2013 for construction of Liulin CHP. Since there still have available space after construction of CHP plant, Liulin county government decided to allocate 12.6 mu land for CMM storage station. In addition, 20 gas pressure adjustment stations did not acquire any land because these stations were located in existing boiler houses. Construction of 43.1 km heating pipelines temporarily used existing state- owned roads. The cost for digging and recovering roads for the pipeline installation was included in the pipeline civil works.

D. Compensation Rates and Resettlement Cost

4. The DDR indicates that 45 mu of land acquired for Liulin CHP belonged to non-cultivated lands in Hechang Village. The acquired land was not contracted to individual households but managed by the Hechang village collective. In December 2013, Liulin county land and resources

1 A mu is a Chinese unit of measurement, the equivalent of 666.67 square meters.

Appendix 12 41

bureau issued land acquisition announcement on its as well as Hechang village committee. In March 2014, Liulin county land and resources bureau entered into land acquisition and compensation agreement with Hechang village.

5. According to Notice of the Shanxi Provincial Government on Adjusting Uniform Average Annual Output Value (AAOV) Rates (SPG [2013] No.22), land compensation rates in Liulin county are provided in Table A12.1.

Table A12.1: Land Compensation Rates in Liulin County

Compensation Uniform Compensation multiple rates (CNY/mu) Tier Areas AAOV Land Resettlement (CNY/mu) Total compensation subsidy Industrial and I 1,590 24 7 17 38,160 mining areas II Valley areas 1,890 25 6 19 47,250 III Forest areas 1,402 24 8 16 33,648 IV Hilly areas 1,187 23 8 15 27,301 Source: Updated Resettlement Plan and Due Diligence Report 2016.

6. The acquired 45 mu sloped land in Hechang Village is located in Tier-I area, the actual land compensation rate is CNY38,160/mu, which is higher than CNY31,000/mu specified in the original resettlement plan. A total of CNY1.717 million land compensation funds has been fully paid to Hechang village before end 2014.

E. Status of Affected village and income restoration

7. Hechang village has a total of 2,901 households with 8,349 persons, owns 1,617 mu cultivated land and 2,000 mu sloped land. In 2015, the village’s food crop output was 70.75 tons, total rural economic income was CNY340.22 million, and the rural residents’ per capita net income reached CNY9,288. Commerce and logistics are becoming the village’s pillar industries. Since land acquisition has not directly affected individuals, the village committee used land compensation to broaden a village road with the consent of villagers.

F. Monitoring and Reporting

8. Since the impact on land acquisition is not significant, engaging an external monitor was not required in the resettlement plan. Internal resettlement monitoring and reporting system was established by Shanxi provincial project management office (PMO) and implementing agencies. Shanxi provincial PMO submitted social development and resettlement progress reports to ADB during project implementation. The information of land acquisition and resettlement includes (i) subproject construction progress, (ii) resettlement progress and updated resettlement impacts, and (iii) evaluation of resettlement progress and adjustment. In addition, Shanxi provincial PMO prepared a brief resettlement completion report and concludes that (i) the resettlement works of the project is generally satisfactory, (ii) all temporarily occupied land or road have been restored, and (iii) there is no remaining resettlement problems in this project.

42 Appendix 12

G. Actions to Be Taken

9. Except Liulin CMM subproject, the other subprojects were implemented on either government land or existing premises. However, some subprojects have still not obtained official certificate for existing land use due to either changes in approval procedures or lack of land use right transfer document for those state-owned lands. ADB project completion review mission expressed concerns on the remaining issue and urged that the project implementation agencies of Qin county subproject and Licheng county subproject should close coordinate with local land departments to speed up application progress of land use official certificates and obtain them in a timely manner, no later than end 2019.

Appendix 13 43

STATUS OF COMPLIANCE WITH LOAN COVENANTS

Project Specific Covenants Reference in Compliance Status Legal Agreement 1. The Borrower shall, through the SPG LA, Art. IV, Complied with. cause the Project to be carried out with due Section 4.01 (a) diligence and efficiency and in conformity (b) The SPG fulfilled its obligations with sound applicable technical, financial, PA, Art. II, as covenanted and implemented business, and development practices. Section 2.01 (b) the project effectively. (c) 2. In the carrying out of the Project and operation of the Project facilities, the Borrower shall perform, or cause to be performed, all obligations set forth in Schedule 5 to this Loan Agreement and Schedule to the Project Agreement. 3. The Borrower shall, through the SPG, LA, Art. IV, Complied with. make available, or cause to be made available, Section 4.02 promptly as needed, the funds, facilities, PA, Art. II, Section The required funds, facilities, services, land and other resources, as 2.02 services, land and other required, in addition to the proceeds of the resources were generally timely Loan, for the carrying out of the Project. provided. 4. The Borrower shall ensure that the LA, Art. IV, Complied with. activities of its departments and agencies Section 4.03 with respect to the carrying out of the Project The PIAs implemented the and operation of the Project facilities are project in accordance with sound conducted and coordinated in accordance with administration procedures. sound administrative policies and procedures. 5. The Borrower shall cause the SPG to LA, Art. IV, Complied with. enable ADB's representatives to inspect the Section 4.04 Project, the Goods and Works, and any PA. Art. II, The PMO arranged, coordinated relevant records and documents relating to the Section 2.10 and cooperated with ADB’s Project. representatives to enable them to inspect the project, the Goods, and any relevant records and documents. 6. The Borrower shall take all actions which LA, Art. IV, Complied with. shall be necessary on its part to enable the Section 4.05 SPG to perform its obligations under the The SPG fully performed its Project Agreement, and shall not take or permit obligations under the Project any action which would interfere with the Agreement. performance of such obligations. 7. The SPG shall make the proceeds of the PA, Art. II, Complied with. Loan available to the Project Implementing Section 2.01 (a) Agencies through the respective onlending The SPG provided full agreement upon terms and conditions cooperation on the onlending of acceptable to ADB. Except as ADB may proceeds of the loan to PIAs. otherwise agree, the terms for the proceeds of the Loan made available to the Project Implementing Agencies shall include (i) commitment charge and interest at the rates identical to those applied to the Loan; (ii) a repayment period including a grace period identical to those applied to the Loan; and (iii) each Project Implementing Agency bearing the foreign exchange and interest rate variation

44 Appendix 13

Project Specific Covenants Reference in Compliance Status Legal Agreement risks of the proceeds of the Loan made available thereto. 8. In carrying out of the Project, the SPG PA, Art. II, Complied with. shall employ competent and qualified Section 2.03 (a) consultants and contractors, acceptable to (b) PMO engaged qualified ADB, to an extent and upon terms and consultants with the domestic conditions acceptable to ADB. counterpart funds instead of the ADB loan due to substantial delay 9. Except as ADB may otherwise agree, the and prolonged process in the SPG shall procure, or cause the Project recruitment of ADB-financed Implementing Agencies to procure, all items of project implementation consulting expenditures to be financed out of the proceeds of the Loan in accordance with the firm using the quality- and cost- provisions of Schedule 4 to the Loan based selection procedure. Agreement. ADB may refuse to finance a contract where any such item has not been Complied with. All packages procured under procedures substantially in financed by ADB were procured accordance with those agreed between the in accordance with ADB’s Borrower and ADB or where the terms and Procurement Guidelines and the conditions of the contract are not acceptable to provisions of schedule 4 of the ADB. Loan Agreement. 10. The SPG shall carry out, or cause the PA, Art. II, Complied with. Project Implementing Agencies to carry out, the Section 2.04 Project in accordance with plans, design The project was carried out standards, specifications, work schedules and following the requirements, construction methods acceptable to ADB. The standards, technical SPG shall furnish, or cause to be furnished, to specifications and met the PRC’s ADB, promptly after their preparation, such construction quality criteria. plans, design standards, specifications and work schedules, and any material modifications subsequently made therein, in such detail as ADB shall reasonably request. 11. The SPG shall cause the Project PA, Art. II, Complied with. Implementing Agencies to take out and Section 2.05 (a) maintain with responsible insurers, or make (b) other arrangements acceptable to ADB for, insurance against such risks and in such amounts as shall be consistent with sound practice.

Complied with. 12. Without limiting the generality of the foregoing, the SPG undertakes to insure, or cause to be insured, the Goods to be imported for the Project against hazards incident to the acquisition, transportation and delivery thereof to the place of use or installation, and for such insurance any indemnity shall be payable in a currency freely usable to replace or repair such Goods. 13. The SPG shall maintain, or cause to be PA, Art. II, Complied with. maintained, records and accounts adequate to Section 2.06 identify the items of expenditure financed out of The PMO has submitted the the proceeds of the Loan, to disclose the use required reports, audited project thereof in the Project, to record the progress of accounts and financial

Appendix 13 45

Project Specific Covenants Reference in Compliance Status Legal Agreement the Project (including the cost thereof) and to statements to the ADB as reflect, in accordance with consistently stipulated in the Loan Agreement. maintained sound accounting principles, its The ADB loan was appropriately operations and financial condition. utilized and disbursed. 14. ADB and the SPG shall cooperate PA, Art. II, Complied with. fully to ensure that the purposes of the Loan will Section 2.07 (a) be accomplished. (b) (c)

15. The SPG shall promptly inform ADB of Complied with. any condition which interferes with, or SPG fulfilled its obligations as threatens to interfere with, the progress of the covenanted. Project, the performance of its obligations

under this Project Agreement, or the

accomplishment of the purposes of the Loan.

16. ADB and the SPG shall from time to time, Complied with. at the request of either party, exchange views through their representatives with regard to any The PMO regularly reported matters relating to the Project, the SPG and the project progress and issues to Loan. ADB and the project leading group. The meetings were required when there were key issues to discuss and resolve. 17. The SPG shall furnish to ADB all such PA, Art. II, Complied with. reports and information as ADB shall Section 2.08 (a) reasonably request concerning (i) the Loan and (b) (c) The PMO submitted annual the expenditure of the proceeds thereof; (ii) the project financial statement items of expenditure financed out of such audited by Shanxi Provincial proceeds; (iii) the Project; (iv) the Auditing Department timely. The administration, operations and financial auditor issues unqualified condition of the SPG relating to the Project; and auditor’s opinion every year. (v) any other matters relating to the purposes

of the Loan.

18. Without limiting the generality of the Complied with. The PMO foregoing, the SPG shall furnish to ADB provided progress reports to ADB periodic reports on the execution of the Project on semi-annual basis. and on the operation and management of the Project facilities. Such reports shall be submitted in such form and in such detail and within such a period as ADB shall reasonably request, and shall indicate, among other things, progress made and problems encountered during the period under review, steps taken or proposed to be taken to remedy these problems, and proposed program of activities and expected progress during the following period.

Complied with. The report was 19. Promptly after physical completion of the Project, but in any event not later than 3 submitted to ADB on 18 January months thereafter or such later date as ADB 2018. may agree for this purpose, the SPG shall prepare and furnish to ADB a report, in such

46 Appendix 13

Project Specific Covenants Reference in Compliance Status Legal Agreement form and in such detail as ADB shall reasonably request, on the execution and initial operation of the Project, including its cost, the performance by the SPG of its obligations under this Project Agreement and the accomplishment of the purposes of the Loan. 20. The SPG shall (i) maintain separate PA, Art. II, Complied with. accounts and records for the Project; (ii) Section 2.09 (a) prepare annual financial statements for the (b) (c) The PMO maintained financial Project in accordance with financial reporting accounts effectively, which were standards acceptable to ADB; (iii) have such audited as per the PA financial statements audited annually by requirements. All audited reports independent auditors whose qualifications, were generally submitted on experience and terms of reference are schedule. acceptable to ADB, in accordance with

international standards for auditing or the national equivalent acceptable to ADB; (iv) as part of each such audit, have the auditors prepare a report (which includes the auditors’ opinion on the financial statements, use of the Loan proceeds and compliance with the financial covenants of this Loan Agreement as well as on the use of the procedures for the imprest account and statement of expenditures) and management letter; and (v) furnish to ADB, no later than 6 months after the end of each fiscal year, copies of such audited financial statements, audit report and management letter, all in the English language, and such other information concerning these documents and the audit thereof as ADB shall

from time to time reasonably request.

21. ADB shall disclose on its website, the Complied with. annual audited financial statements for the All Audited Financial Statements Project and the opinion of the auditors on the were disclosed. financial statements within 30 days of the date of their receipt.

22. The SPG shall enable ADB, upon ADB’s Complied with. request, to discuss the SPG’s financial statements for the Project and its financial affairs where they relate to the Project with the auditors appointed pursuant to subsection (a)(iii) hereinabove, and shall authorize and require any representative of such auditors to participate in any such discussions requested by ADB. This is provided that such discussion shall be conducted only in the presence of an authorized officer of the SPG unless the SPG shall otherwise agree. 23. Except as ADB may otherwise agree, PA, Art. II, Complied with. the SPG shall apply, or cause the Project Section 2.11 Implementing Agencies to apply, the proceeds

Appendix 13 47

Project Specific Covenants Reference in Compliance Status Legal Agreement of the Loan to the financing of expenditures on The PMO maintained financial the Project in accordance with the provisions of accounts effectively, which were the Loan Agreement and this Project audited as per the PA Agreement, and shall ensure that all items of requirements. expenditures financed out of such proceeds are used exclusively in the carrying out of the Project. 24. Implementation Arrangements PA, Schedule, Complied with. The SPG shall ensure that the PMO is para. 2 equipped with professionally skilled staff, The PMO was in place and reasonable office space, equipment, and functioned well during project adequate financial resources required for implementation. implementation of the project throughout Project implementation. 25. Environment PA, Schedule, Complied with. The SPG shall ensure and cause the PIAs para. 3 to ensure that the preparation, design, All PIAs fulfilled their construction, implementation, operation and responsibility as covenanted. decommissioning of the project and all Project facilities comply with (a) all applicable laws and regulations of the Borrower relating to environment, health and safety; (b) the Environmental Safeguards; and (c) all measures and requirements set forth in the IEE, the EMP and any corrective or preventive actions that may subsequently be agreed upon with ADB. 26. Land Acquisition and Resettlement PA, Schedule, Complied with. The SPG shall ensure and cause the PIAs para. 4 The updated RP for the new to ensure that all land and all rights-of-way location of Liulin subproject and required for the project are made available to due diligence report on land the Works contractor in accordance with the acquisition for Qin subproject schedule agreed under the related Works were furnished to the ADB in contract and all land acquisition and October 2016. resettlement activities are implemented in compliance with (a) all applicable laws and regulations of the Borrower relating to land acquisition and involuntary resettlement; (b) the Involuntary Resettlement Safeguards; and (c) all measures and requirements set forth in the RP, and any corrective or preventative actions that may subsequently be agreed upon with ADB. 27. Safeguards-Related Provisions in PA Schedule, Complied with. Bidding Documents and Works para. 8 PIAs performed the obligation Contracts and undertakings. The SPG shall ensure and cause the PIAs to ensure that all bidding documents and contracts for Works contain provisions that require contractors to: (a) comply with the measures relevant to the contractor set forth in the IEE, the EMP and the RP, and any corrective or preventive actions set forth in a Safeguards Monitoring Report; (b) make

48 Appendix 13

Project Specific Covenants Reference in Compliance Status Legal Agreement available a budget for all such environmental and social measures; and (c) provide the SPG, through the PIAs, with a written notice of any unanticipated environmental or resettlement risks or impacts that arise during construction, implementation or operation of the project that were not considered in the IEE, the EMP and the RP. 28. Safeguards Monitoring and Reporting PA, Schedule, Complied with. The SPG shall do, and cause the PIA to para. 9 do, the following: The PMO submitted 5 semi- (a) submit (i) semi-annual Safeguards annual/annual progress reports Monitoring Reports during construction, to the ADB during the project and (ii) annual Safeguards Monitoring implementation. Reports during operation of Project facilities to ADB for review and disclose

relevant information from such reports

to the Affected Persons promptly upon submission; (b) if any unanticipated environmental Complied with. and/or social risks and impacts arise during construction, implementation or The location change for the Liulin operation of the project that were not CMM gas storage station and considered in the IEE, the EMP and the change of Zhongyang subproject RP, promptly inform ADB of the from coal-fired boiler to natural occurrence of such risks or impacts, with gas -fired boiler had detailed description of the event and unanticipated environmental proposed corrective action plan; and implication compared to those at (c) report any actual or potential breach of project appraisal. Safeguards compliance with the measures and due diligence was conducted in requirements set forth in the EMP and 2014 and approved by ADB in the RP promptly after becoming aware January 2015, accordingly the of the breach. EMP was updated.

Complied with. Not applicable in the environmental safeguard aspect. 29. Gender and Development PA, Schedule, Complied with. SPG shall ensure that the PlAs follow the para. 11 principles of the ADB's Policy on Gender and A total of 134 temporary jobs Development (1998) during implementation of were provided to women during the project, including taking all necessary project construction and 107 actions to encourage women living in the regular jobs to women during project area to participate in planning and project operation. Over 50% of implementing Project activities. SPG shall heating bill collectors were cause the PIAs to implement in full the Gender women by 2017. Action Plan as agreed for the project and to annually report the progress thereto ADB. 30. Health and Social Risks PA, Schedule, Complied with. SPG shall ensure that the PIAs, together with para. 12 the appropriate government authorities, require With support from CDC, contractors employed under the project to HIV/AIDS and communicable disseminate information (in local languages) diseases safety education were on the risks of sexually-transmitted infections,

Appendix 13 49

Project Specific Covenants Reference in Compliance Status Legal Agreement including HIV/AIDS, in health and safety required, and information were programs to those employed during Project disseminated to contractors implementation. Specific provisions to this employed under the project. effect shall be included in bidding documents and Works contracts, and compliance shall be strictly monitored by SPG and the PIAs. 31. Labor and Employment PA, Schedule, Complied with. SPG shall ensure and cause the PIAs to para. 13 ensure that contractors financed under the A total of 787 temporary jobs project: (a) are encouraged to use local labor in were provided to local people particular the poor and vulnerable people including 134 female workers. (b) and local materials in Works; (b) provide equal pay was ensured to men equal pay to men and women for work of and women for work of equal equal type; (c) provide safe working conditions type; (c) safe working conditions for both male and female workers; (d) were provided for both male and maximize employment for the Affected Persons with equal access to women, female workers and monitored by including disadvantage women; (e) comply review missions; (d) women were with applicable labor laws; and (f) abstain from prioritized for job opportunities. child, involuntary or forced labor in Out of 93 bill collectors as construction, operation and maintenance permeant jobs, 58 (62%) were activities on Project facilities; (g) semi- women. (e) labor laws were annually report the implementation status of complied with; (f) no child, subparagraphs 13(a) to (f) to ADB. involuntary or forced labor in construction, operation and maintenance activities on Project facilities; (g) semi-annual report of the implementation status were submitted to ADB. annually report of the implementation status were submitted to ADB.

32. Counterpart Funding PA, Schedule, Partially complied with. The SPG shall cause the respective para. 14 municipal and county governments to ensure Counterpart funds were that all financing (other than from the Loan earmarked and timely provided proceeds) including cash injection and equity for each subproject except for contributions are provided on a timely basis to Liulin subproject. The counterpart enable the full and timely completion of the funds for Liulin subproject were project. In the event of any shortfall or not mobilized timely to meet the disruption in the financing of the project due project construction demands, to, inter alia, the lack of inadequacy of funding of, or delay in financing by, or change of which caused some delay of the control within, any of the project Implementing subproject implementation. Agencies, the SPG shall promptly inform the Borrower and ADB and cause the respective municipal and county governments to provide additional funds as may be necessary for successful implementation of the project. 33. Change in Ownership and Operation PA. Schedule, Complied with. In the event of (a) any change in ownership para. 15 of the project facilities or (b) any sale, transfer Ownership remained unchanged. or assignment of shares or interest or other change of control in any PIA is anticipated,

50 Appendix 13

Project Specific Covenants Reference in Compliance Status Legal Agreement SPG consult and cause the concerned PIAs to consult with ADB at least 6 months prior to the implementation of such change. The SPG shall ensure and cause the concerned PIA to ensure that such change be carried out in a lawful and transparent matter. 34. Closure of Small Coal-fired Heat PA, Schedule, Complied with. Boilers/Displaced Boiler Workers para. 16 The SPG shall ensure that the PIAs complete By project completion, a total of the closure of about 286 small coal-fired heat 398 small boilers were closed in boilers identified for closure under the project four sub-projects (Zhongyang by 2016. The demolition of boilers in particular County District Heating, Licheng the handling and disposal of wastes including County District Heating, Qin asbestos or asbestos contaminated materials, County District Heating and Liulin if any, shall be carried out in accordance with City). 468 affected boiler workers the provisions set forth in the IEE and EMP. The cost associated with the handling, (30 formal employees and 438 transport and disposal of asbestos or asbestos seasonal temporary workers) contaminated materials shall be included in the were trained and reemployed by project. The SPG shall ensure that before the PIAs and local government. Project completion, site investigation of Employment training was contaminated land has been conducted, and arranged for the remaining site- specific remedial measures have been unemployed seasonal workers; developed, reviewed and cleared by the adequate staff, resources and concerned local environment protection budget were committed for bureaus and ADB. The SPG shall cause the monitoring and supervision of the PIA to ensure that (a) all permanent employees Labor Retrenchment Plan; and affected by the closure of such small boilers implementation of the Labor under the Project are reemployed in a timely Retrenchment Plan was reported manner and in accordance with the Labor through semi- annual progress Retrenchment Plan, so that they shall be at reports, and Project completion least as well off as they would have been in reports. the absence of the project; (b) casual workers are reemployed where possible; (c) employment training is arranged for the remaining unemployed seasonal workers; (d) adequate staff, resources and budget are committed for monitoring and supervision of the Labor Retrenchment Plan; and (e) implementation of the Labor Retrenchment Plan is reported to the SPG and ADB through semi- annual progress reports, and Project completion reports. 35. Implementation of Heating-Tariff PA Schedule, Complied with. Reforms para. 17 The SPG shall cause the PIAs to By project completion a total of progressively implement at the city level and 124,000 m2 heating area have applicable to newly built facilities, key heating been tariffed in heat metering. tariff reforms including: (a) installation of lock valves in individual apartment units in buildings to improve tariff collection; (b) installation of radiator control valves in apartment units in buildings to encourage heat conservation; (c) provision of two-part heating

Appendix 13 51

Project Specific Covenants Reference in Compliance Status Legal Agreement tariff structure that the variable charge shall be based on heat consumption, under which the overall heating tariff level is cost-reflective and promote economic efficiency; (d) installation of heat measuring devices at client level to support consumption- based billing systems; and (e) conversion from enterprise-based tariff payment system to individual-based system. 36. Heating Assistance to the Poor PA, Schedule, Complied with. The SPG shall ensure that the PIAs implement para. 18 the pro-poor programs that provide heating Up to project completion, about tariff discounts to the poor based on the cost 3,000 poor have been granted savings from efficiency improvement under the heating tariff reduction. project. The SPG shall further ensure that the government- funded heating assistance programs to assist the poor and those with incomes marginally higher than the poverty level to pay heating bills are established in the project area. The SPG shall monitor, and cause to be monitored, implementation of such pro- poor programs and government-funded heating assistance programs, and shall report such implementation annually to ADB. 37. Financing Performance of PIAs PA. Schedule, Partially complied with. In each fiscal year commencing from 2 years para. 19 after Project operations, the SPG shall ensure Except Jinzhong Ruiyang CHP that PIAs maintain a debt-service coverage Heat Supply company which ratio of at least 1.2 times; and a current ratio demonstrated strong financial of greater than 1:1 and thereafter, and a debt- performance and satisfied all the equity ratio of not greater than 70:30. covenanted ratios, other PIAs did not satisfy the covenanted ratios.

The main reasons include high debt ratios and the operating losses resulted from the low heat tariff, high coal costs, and low operational efficiency. It has been noted the local governments have committed to support these companies considering the nature of the project which concerns the welfare of the public through debt restructuring and providing subsidies to meet the debt services obligations and the gap between the tariff collection and the recurrent operating cost of the company. 38. Institutional Strengthening PA, Schedule, Complied with. The SPG shall ensure that the project para. 21 The relevant activities are carried Implementing Agencies implement the out by using the local counterpart recommendations for financial and institutional fund. strengthening to be developed under Part C in

52 Appendix 13

Project Specific Covenants Reference in Compliance Status Legal Agreement accordance with the implementation plan agreed upon between the SPG and ADB. In particular such recommendation shall include improving financial management and reporting, corporate governance, budgeting, management administration and staff incentive schemes. 39. Gas and Heating Supply Agreements PA. Schedule, Complied with. The SPG shall cause the project Implementing para. 21 Agencies to sign and execute long-term gas and heating supply agreements with large prospective customers to ensure the demand of the gas and heating. For subprojects under Part B, the SPG shall cause the project Implementing Agencies to ensure that the respective supply of coal mine methane gas contracts with appropriate suppliers are all the time in place during and after Project implementation. 40. Grievance Redress Mechanism PA. Schedule, Complied with. The SPG shall ensure that within 2 months para. 22 of the Effective Date, grievance redress A grievance redress committee mechanism, acceptable to ADB and in was established inside the PMO accordance with the project administration and there were no formal manual, shall have been established and complaints received. functioning effectively to (a) review and document eligible complaints of Project stakeholders; (b) proactively address grievances; (c) provide the complainants with notice of the chosen mechanism/action; and (d) prepare periodic reports to summarize (i) number of complaints received and resolved, (ii) chosen actions, and (iii) final outcomes of the grievances and make these reports available to ADB. Eligible complaints shall include (a) those related to the project; (b) any of the service providers; (c) any person responsible for carrying out the project; (d) complaints on misuse of funds and other irregularities; and (e) grievances due to any safeguards and gender issues. 41. Governance and Anticorruption PA. Schedule, Complied with The SPG (a) acknowledges ADB’s right para. 23 to investigate, directly or through its agents, any ADB Anti-corruption alleged corrupt, fraudulent, collusive or requirements were complied with coercive practices relating to the project; and and incorporated into bidding (b) agrees to cooperate, and shall cause the documents. Domestic prevailing PIAs, and all other government offices, anti-corruption measures were organizations and entities involved in adopted during project implementing the project to cooperate, fully with implementation. any such investigation and to extend all necessary assistance, including providing access to all relevant books and records, as may be necessary for the satisfactory

Appendix 13 53

Project Specific Covenants Reference in Compliance Status Legal Agreement completion of any such investigation. In particular, the SPG shall ensure that (a) periodic inspections of the project contractors’ activities related to fund withdrawals and settlements are carried out; (b) relevant provisions of ADB’s Anticorruption Policy (1998, as amended to date) are included in all bidding documents for the project; and (c) contracts, financed under the project, include provisions specifying the right of ADB to audit and examine the records and accounts, and other service providers as they relate to the project. 42. Monitoring and Evaluation PA, Schedule, Partially complied with. The SPG, through the PMO, shall ensure and para. 24 cause the PIA to ensure that Project outcomes As the planned ADB-financed and outputs are monitored and evaluated consulting services were not through a Project performance monitoring recruited as scheduled, there was system, as agreed to by the SPG and ADB in inadequate project management accordance with the project administration support during the early period of manual. the project implementation, and the PPMS was not established on time. ADB = Asian Development Bank, EMP = environmental management plan, FSR = feasibility study report, SPG = Shanxi Provincial Government, IEE = initial environmental examination, LA = Loan Agreement, PMO = project management office, M&E = monitoring and evaluation, NCB = national competitive bidding, PA = Project Agreement, PPR = Project performance report, PPTA = project preparatory technical assistance, PRC = People’s Republic of China.

54 Appendix 14

ECONOMIC REEVALUATION

1. The economic reevaluation was undertaken following the same methodologies and major assumptions as at appraisal in accordance with the Asian Development Bank’s (ADB) Guidelines for the Economic Analysis of Project (1997). The analysis was conducted for the four district heating subprojects under Part A and one coal-mine methane (CMM) gas supply and distribution subproject under Part B, as well as the overall project.

A. Methodology and Basic Assumptions

2. As at appraisal, incremental costs and benefits are estimated by comparing with-project and without- project scenarios for each subproject and the project as a whole. Basic assumptions as at appraisal/design used in the economic analysis include:

(i) The project life is assumed 25 years, including an implementation period of 3-7 years. The residual value at the end of the project life is assumed to be zero. All prices and costs are expressed in 2017 prices and in the domestic currency; (ii) Transfer payments such as taxes, duties, and subsidies are excluded from the economic evaluation of the individual subprojects and the project as a whole; (iii) Economic costs and benefits are derived by adjusting financial costs by a standard conversion factor of 0.987 used at appraisal. This is consistent with the standard conversion factor used in the ADB projects for the People’s Republic of China (PRC); (iv) The real opportunity cost of capital employed in the analysis is assumed at 9% per annum, and represents the opportunity cost of capital for the PRC.

B. Economic Costs

3. The capital costs of district heating include costs related to boilers, pipelines, heat exchange stations, other associated costs, and physical contingency. The capital costs of CMM supply include costs related to the construction and installation of the gas supply system and gas storage station, gas distribution pipelines, and other capital investments. The financial capital costs are converted to the relevant economic values after deducting taxes, subsidies, and price contingencies, then applying the respective conversion factors as specified above. The operation and maintenance (O&M) costs comprising of costs for maintenance, raw materials, energy inputs, salaries, overhead, and administration expenses that were updated for the subprojects that have started to operate based on the initial operation data, while O&M costs that were estimated at appraisal for the normal operation periods assumed to remain constant in real terms, The O&M costs occur throughout the lifespan of each subproject.

C Economic Benefits

4. Following the methodologies adopted at appraisal, the economic benefits for the four district heating subprojects include (i) improvements in energy efficiency from coal savings after conversion from small boilers and single-family stoves to large boilers, multiplied by the economic coal price, for the existing heating area; (ii) incremental heating revenues (willingness to pay) due to expansion of the district heating area; and (iii) environmental benefits, which are reflected in the reduction of environmental costs from the new boilers relative to the old boiler system (the baseline scenario).

5. Up to the 2017-2018 heating season, about 7.57 million square meters (m2) buildings have been serviced by the project Part A subprojects, exceeding the original targeted total district heat supply area of 6.8 million m2. The total district heating service capacity reached to 8.12 million m2 including the new service areas of 4.0 million m2 by the 2018-2019 heating

Appendix 14 55

season. According to the project management office (PMO) and interviews with project beneficiaries, even for the heating area existing before the project where small boilers or household coal boilers were used, the residents had strong willingness to pay for the district heating service because of the significantly better reliability and quality of service, cleaner air condition, and less labor used. For this reason, willingness to pay were applied to the all service areas under the project. For Part B, the original economic benefits estimated at appraisal included reduction of coal consumption for the existing heating area, incremental CMM use for new heating areas, cooking and space cooling in buildings, and environmental improvement through reduction of environmental costs from pollutant emissions. At completion, it was noted that the main output was realized through selling gas to residential, commercial and public users, and the heating area was realized through using household gas-fired boilers. Without the project, such supply of gas would be impossible in view of the shortage of nature gas situation in the region, thus the associated benefits were considered as incremental, thus the valuation is based on the willingness to pay of gas in the project area. To avoid double-counting of benefits, cooling, cooking benefits were not considered.

6. The environment benefits reflected in the reduction costs from accruing under the project in the reduction of environmental costs from new boilers relative to the old boiler system in case of Part A subprojects and from pollutants emission in case of Part B subproject. By 2017, district heating in the project area reduced aggregate annual coal consumption by 69,663 tons of standard coal equivalent per year, which has avoided annual emissions of 185,549 tons of carbon dioxide (CO2), 3,017 tons of sulfur dioxide (SO2), 1,725 tons of nitrogen oxide (NOx), 10,196 tons of total suspended particulates, as compared with 2012. By 2018, district heating in the five urban areas reduced aggregate annual coal consumption by 73,063 tons, which has avoided annual emissions of 194,025 tons of CO2, 3,195 tons of SO2, 2,129 tons of NOx, 12,588 tons of total suspended particulates, as compared with 2012. The marginal abatement cost estimate for CO2 (CNY30/ton) is based on the prevailing market price for Clean Development Mechanism credits and the marginal abatement cost of SO2 (CNY1,100/ton) is based on the domestic market price for SO2 abatement in PRC.

D. Results of the Economic Analysis

7. Economic internal rates of returns (EIRRs) were computed to re-examine the economic viability of the five subprojects and the consolidated five subprojects at the completion. The overall project economic analysis was based on an aggregation of the economic benefits of five subprojects and economic costs of five subprojects plus the costs of other components mainly for project management and capacity development. Table 1 shows the EIRRs and economic net present value (ENPV) at the prevailing capital opportunity cost of 9% for all the subprojects at the completion compared with those at appraisal and overall project at the completion.

8. The EIRRs of the individual subprojects at the completion ranged from 12.9% to 24.4% without environment benefits and 13.8% to 26.9% with environment benefits, and the consolidated EIRR for five subprojects was 15.9% without environment benefits and 17.4% with environment benefits, showing that the project investment in district heating and CMM is still economically viable at the completion. Because of similar outputs produced, EIRRs of subprojects and overall project were close to those estimated at appraisal, while Jinzhong subproject registered a better result benefiting from higher operation efficiency. The steam of combined economic benefits and costs of the overall project, Part A, and Part B are in Tables 2-4.

56 Appendix 14

Table A14.1: Summary Results of Economic Analysis at the Completion At Appraisal At the Completion without with without with Environmental Environmental Environmental Environmental Subprojects Benefit Benefit Benefit Benefit EIRR ENPV EIRR ENPV EIRR ENPV EIRR ENPV (%) @12% (%) @12% (%) @9% (%) @9% Part A Jingzhong 14.4 52.4 15.6 77.8 16.1 176.94 17.7 214.68 Licheng 15.6 25.4 19.3 51.3 15.0 77.16 16.3 95.56 Qin Xian 13.0 12.4 14.4 30.2 12.9 48.35 13.8 60.65 Zhongyang 22.6 21.7 24.6 25.8 24.4 33.51 26.9 39.26 Part B Liulin 18.3 34.2 31.3 103.7 18.4 101.74 20.4 130.08 Overall Project 15.0 146.1 17.9 288.6 15.9 437.71 17.4 540.23 Source: Report and Recommendation of the President to the Board of Directors and Economic analysis reevaluated at completion.

Table A14.2: Economic Internal Rate of Return for Overall Project at Completion (CNY million) Net Increment Net Increment Economic Environmental Benefits without Benefits with Year Capital Cost O&M cost Benefits Benefits Environmental Environmental Benefits Benefits 2013 19.71 0.00 0.00 0.00 (19.71) (19.71) 2014 462.35 47.08 84.23 3.56 (413.77) (410.20) 2015 221.32 52.08 124.98 5.32 (140.46) (135.14) 2016 123.97 61.78 164.23 6.95 (10.86) (3.92) 2017 171.95 85.39 203.68 8.88 (64.91) (56.02) 2018 96.82 237.75 11.41 140.92 152.33 2019 100.92 237.10 12.45 136.18 148.62 2020 109.04 273.23 14.52 164.19 178.71 2021 109.04 273.23 14.52 164.19 178.71 2022 109.04 273.23 14.52 164.19 178.71 2023 109.04 273.23 14.52 164.19 178.71 2024 109.04 273.23 14.52 164.19 178.71 2025 109.04 273.23 14.52 164.19 178.71 2026 109.04 273.23 14.52 164.19 178.71 2027 109.04 273.23 14.52 164.19 178.71 2028 109.04 273.23 14.52 164.19 178.71 2029 109.04 273.23 14.52 164.19 178.71 2030 109.04 273.23 14.52 164.19 178.71 2031 109.04 273.23 14.52 164.19 178.71 2032 109.04 273.23 14.52 164.19 178.71 2033 109.04 273.23 14.52 164.19 178.71 2034 109.04 273.23 14.52 164.19 178.71 2035 109.04 273.23 14.52 164.19 178.71 2036 109.04 273.23 14.52 164.19 178.71 2037 109.04 273.23 14.52 164.19 178.71 2038 109.04 273.23 14.52 164.19 178.71 ENPV@9% 437.71 540.23 EIRR without environment benefits 15.9% EIRR with environment benefits 17.4% Source: Economic analysis reevaluated at completion.

Appendix 14 57

Table A14.3: Economic Internal Rate of Return for Part A at Completion (CNY million) Net Increment Net Increment Benefits Economic Environmental Benefits with Year Capital Cost O&M cost without Benefits Benefits Environmental Environmental Benefits Benefits 2013 19.71 0.00 0.00 0.00 (19.71) (19.71) 2014 13.40 0.00 0.00 0.00 (13.40) (13.40) 2015 437.81 47.08 84.23 3.56 (400.66) (397.10) 2016 168.20 52.08 124.98 5.32 (95.30) (89.98) 2017 94.75 61.78 164.23 6.95 7.70 14.64 2018 154.69 85.39 203.68 8.88 (36.40) (27.52) 2019 85.39 214.10 9.33 128.71 138.04 2020 85.39 214.10 9.33 128.71 138.04 2021 85.39 214.10 9.33 128.71 138.04 2022 85.39 214.10 9.33 128.71 138.04 2023 85.39 214.10 9.33 128.71 138.04 2024 85.39 214.10 9.33 128.71 138.04 2025 85.39 214.10 9.33 128.71 138.04 2026 85.39 214.10 9.33 128.71 138.04 2027 85.39 214.10 9.33 128.71 138.04 2028 85.39 214.10 9.33 128.71 138.04 2029 85.39 214.10 9.33 128.71 138.04 2030 85.39 214.10 9.33 128.71 138.04 2031 85.39 214.10 9.33 128.71 138.04 2032 85.39 214.10 9.33 128.71 138.04 2033 85.39 214.10 9.33 128.71 138.04 2034 85.39 214.10 9.33 128.71 138.04 2035 85.39 214.10 9.33 128.71 138.04 2036 85.39 214.10 9.33 128.71 138.04 2037 85.39 214.10 9.33 128.71 138.04 2038 85.39 214.10 9.33 128.71 138.04 ENPV@9% 335.97 410.15 EIRR without environment benefits 16.8% EIRR with environment benefits 15.4% Source: Economic analysis reevaluated at completion.

58 Appendix 14

Table A14.4: Economic Internal Rate of Return for Part B at Completion (CNY million) Net Increment Net Increment Benefits Economic Environmental Benefits with Year Capital Cost O&M cost without Benefits Benefits Environmental Environmental Benefits Benefits 2013 6.31 - - (6.31) (6.31) 2014 13.10 - - (13.10) (13.10) 2015 45.15 - - (45.15) (45.15) 2016 18.56 - - - (18.56) (18.56) 2017 28.51 - - - (28.51) (28.51) 2018 11.43 23.65 2.08 12.22 14.29 2019 15.53 23.00 3.11 7.47 10.58 2020 23.65 59.13 5.19 35.48 40.67 2021 23.65 59.13 5.19 35.48 40.67 2022 23.65 59.13 5.19 35.48 40.67 2023 23.65 59.13 5.19 35.48 40.67 2024 23.65 59.13 5.19 35.48 40.67 2025 23.65 59.13 5.19 35.48 40.67 2026 23.65 59.13 5.19 35.48 40.67 2027 23.65 59.13 5.19 35.48 40.67 2028 23.65 59.13 5.19 35.48 40.67 2029 23.65 59.13 5.19 35.48 40.67 2030 23.65 59.13 5.19 35.48 40.67 2031 23.65 59.13 5.19 35.48 40.67 2032 23.65 59.13 5.19 35.48 40.67 2033 23.65 59.13 5.19 35.48 40.67 2034 23.65 59.13 5.19 35.48 40.67 2035 23.65 59.13 5.19 35.48 40.67 2036 23.65 59.13 5.19 35.48 40.67 2037 23.65 59.13 5.19 35.48 40.67 2038 23.65 59.13 5.19 35.48 40.67 ENPV@9% 101.74 130.08 EIRR without environment benefits 20.4% EIRR with environment benefits 18.4% Source: Economic analysis reevaluated at completion.

9. The sensitivity analysis tested the robustness of the economic viability of the five subprojects and overall project, using three scenarios: (i) a 10% benefit decline, (ii) a 10% O&M cost increase, and (iii) a combination of both. The results (Table A14.5) shows that all five subprojects and overall project would remain economically viable in any scenario. The economic viability of all the subprojects and overall project has proven to be robust in general at the project completion.

Appendix 14 59

Table 14.5: Results of Sensitivity Analysis

Case 1: Case 2: Case 3: Switch Value (%) Base with Economic Economic Subprojects Environmental O&M Economic Benefit- O&M Benefits - Benefit Benefits +10% 10% and O&M +10% Increase 10% Reduction

Part A Jingzhong 17.7 16.0 13.8 12.2 53.2 -22.7 Licheng 16.3 15.2 13.6 12.4 62.1 -25.5 Qin Xian 13.8 13.1 11.6 10.9 64.1 -21.3 Zhongyang 26.9 25.0 22.3 20.4 91.8 -37.8 Part B Liulin 20.4 19.5 18.2 17.1 99.2 -41.1 Overall Project 17.4 16.1 14.3 13.1 59.0 -24.0 Source: Economic analysis reevaluated at completion.

60 Appendix 15

FINANCIAL REEVALUATION

1. The project aimed to improve energy efficiency and air quality of project cities through extending and expanding energy-efficient district heating and coal-mine methane (CMM) gas supply to 407,600 residents in five highly polluted urban areas of Shanxi, with the three components including district heating supply, the CMM gas supply and distribution system, and project management and capacity development. The main project benefits were generated from the four subprojects under Part A for district heating supply and one subproject under Part B for CMM gas supply and distribution. The financial reevaluation covered all the five subprojects and the overall project.

A. Methodology and Major Assumptions

2. The financial reevaluation for 5 subprojects and overall project was carried out by applying the same methodologies and major assumptions as at appraisal. The analysis was performed in accordance with the Guidelines on Financial Management and Analysis of Projects of the Asian Development Bank (ADB). This reevaluation assessed the financial viability of each subproject by using the information and data updated at completion. The specific assumptions applied in the analysis are as follows:

(i) Financial viability was assessed by calculating individual financial internal rates of return (FIRRs) of each subproject. The weighted average cost of capital (WACC) of each subproject re-estimated based on the actual capital costs and funding sources was used as the benchmark to determine the financial viability and as the discount rate to estimate the financial net present value (FNPV); (ii) Subproject FIRRs were based on project incremental revenues derived from tariff charges or gas fee related to district heating and CMM gas supply, and incremental costs incurred in subproject investment and operation and maintenance. A projection period of 25 years including the construction period was assumed with no residual value; (iii) The capital investments were derived from the project actual expenditures incurred during the project implementation period. The project costs were expressed in the prices of the year that they were actually incurred. Costs and revenues after project completion were expressed in constant 2017 prices to exclude inflation, and the data on capital cost, incremental revenue income, and operation and maintenance (O&M) costs were provided by project implementing agencies (PIAs); (iv) No increase in tariffs and charges in real terms were assumed; (v) All heating subprojects are expected to achieve full capacity by 2018-2019 heating season; (vi) Subproject-specific FIRRs are calculated after taxes. The income tax rates are assumed at 25%; and (vii) Sensitivity analysis has been undertaken to assess the impact of potential adverse changes in key project variables operating costs and revenues.

B. Weighted Average Costs of Capital

3. The WACC was estimated based on the cost of the ADB loan of the current London interbank offered rate (LIBOR) on 10-year fixed-rate swap (3.06% per annum) plus the ADB loan spread of 0.50%, and the cost of equity assumed to be 8.0% per annum. The resulting WACCs of revenue-generating subprojects are from 1.85% to 3.25%, varying by subproject (presented in Table A15.1), with the aggregated WACC of these subprojects of 3.05% as compared with 2.51% estimated at appraisal. The changes in WACC were due to higher ADB loan interest rate, different capital composition, and the impact of lower inflation rate.

Appendix 15 61

C. Results of the Financial Reevaluation

4. FIRRs for 5 subprojects ranged from 2.83% to 8.67%, while FIRR for overall project was 6.24%. FIRRs for 5 subprojects and overall project exceeded the WACCs at the completion indicating their financial viability. Jinzhong subproject had a FIRR higher than the estimate at appraisal mainly because of its higher operation efficiency. All other subprojects indicated lower FIRR results, so as the overall project. This was mainly due to the higher O&M costs, longer construction period, and lower tariff prevailing at completion than that anticipated at appraisal. Table A15.1 shows the results in detail. Consolidated cash flows of all subprojects are shown in Table A15.2.

Table A15.1: Financial Reevaluation Results At Appraisal At the Completion Subproject FNPV FNPV WACC(%) FIRR(%) (CNY WACC(%) FIRR(%) (CNY million) million) Part A Jinzhong 2.55 7.08 226.8 3.25 7.97 205.41 Licheng 2.39 6.39 68.70 3.15 3.62 8.96 Qin 2.52 6.04 92.7 2.75 3.34 11.68 Zhongyang 2.41 7.24 22.7 1.85 2.83 3.80 Part B Liulin 2.54 19.75 236.2 2.98 8.67 86.86 Overall Project 2.51 8.18 670.1 3.05 6.18 319.12 FIRR = financial internal rate of return, NPV = net present value, WACC = weighted average cost of capital , Sources: Report and Recommendation of the President to the Board of Directors and Asian Development Bank estimates.

Table A15.2: Consolidated Cash Flows for the Overall Project (CNY million) Year Capital Cost O&M cost Revenues Income Tax Net Cashflow after Tax 2013 21.68 - - - (21.68) 2014 463.04 47.70 71.96 - (438.91) 2015 218.91 52.77 96.75 - (175.26) 2016 117.54 62.60 120.10 - (60.57) 2017 188.12 86.52 152.67 4.14 (126.81) 2018 - 102.95 180.91 4.69 72.56 2019 - 107.11 189.34 5.44 76.09 2020 - 115.33 206.22 7.60 82.58 2021 - 115.33 206.22 7.60 82.58 2022 - 115.33 206.22 7.60 82.58 2023 - 115.33 206.22 7.60 82.58 2024 - 115.33 206.22 7.60 82.58 2025 - 115.33 206.22 7.60 82.58 2026 - 115.33 206.22 7.60 82.58 2027 - 115.33 206.22 7.60 82.58 2028 - 115.33 206.22 7.60 82.58 2029 - 115.33 206.22 7.60 82.58 2030 - 115.33 206.22 7.60 82.58 2031 - 115.33 206.22 7.60 82.58 2032 - 115.33 206.22 7.60 82.58 2033 - 115.33 206.22 7.60 82.58 2034 - 115.33 206.22 7.60 82.58

62 Appendix 15

Year Capital Cost O&M cost Revenues Income Tax Net Cashflow after Tax 2035 - 115.33 206.22 7.60 82.58 2036 - 115.33 206.22 7.60 82.58 2037 - 115.33 206.22 7.60 82.58 2038 - 115.33 206.22 7.60 82.58 FIRR= 6.18% NPV at WACC = 319.12 ( ) = negative, % = percentage, FIRR = financial internal rate of return, NPV = net present value, O&M = operation and maintenance, WACC = weighted average cost of capital. Source: Asian Development Bank estimates.

5. Jinzhong subproject started operation in 2014 and has been able to expand steadily the heating supply area from the 2.34 million square meters (m2) in 2014, to 2.75 million m2 in 2015, 4.11 million m2 in 2016, and 4.27 million m2 in 2017 which exceeded the design capacity by 42%. The subproject has achieved very promising financial results benefiting from the efficiency gains through adoption of advanced technologies which saved heat consumption by 10%, electricity cost by 40%, and labor cost by 70%. The reevaluated FIRR indicates strong financial viability of the subproject. The advantage of using the heat supply from the combined heat and power (CHP) plant is obvious in this subproject.

6. Qin County subproject started operation in 2016 with initial heat supply area of 0.74 million m2, increasing to 1.298 million m2 in 2017, with the full capacity of 1.68 million m2 expected to be reached in 2018-2019 heating season. The reevaluated FIRR is only marginally higher than WACC, and significantly lower than the appraisal estimate. This is due to the much lower actual tariff as compared with that anticipated at appraisal plus low tariff collection ratio, higher O&M costs mainly due to increased coal price, and longer time taken to reach the full design capacity.

7. Licheng subproject started trial operation in 2014 with heat supply area of 0.4 million m2, 0.7 million m2 in 2015, and 1.5 million m2 in 2017. The reevaluated FIRR is only marginally higher than the WACC, and significantly lower than the appraisal estimates due to the low tariff and high O&M cost and additional capital inputs and additional operating cost for facilities for the heating plant to reach the environmental standards.

8. Zhongyang subproject started operation in the heating season in 2017 with heat supply area of 0.5 million m2. The cost of consumption of gas has caused significantly higher operation cost as compared with the heating plant using coal. This, together with the low collection ratio of tariff, makes the FIRR the lowest among the subprojects, though still marginally higher than its WACC. However, as the first heating plant using gas in the project area and the short period of operation, the O&M cost figures may become stable only after more heating seasons. Close monitoring will continue.

9. Liulin subproject started operation in December 2017. Based on the initial operating results, the reevaluated FIRR of the subproject will be much higher than the WACC, indicating strong financial viability of the subproject. This mainly benefits from the low price of CMM gas supply as compared with sale price to consumers. However, compared with the appraisal estimates, the FIRR will be significantly reduced because of the lower CMM gas supply amount in 2018 with delayed achievement in the full capacity by 2020 and the lower unit sale price.

10. The sensitivity analysis tested the robustness of the financial viability of the 5 subprojects, using three scenarios: (i) a 10% revenue decline, (ii) a 10% O&M cost increase, and (iii) a combination of both. The results indicated that Jinzhong subproject would remain viable in scenarios (i) and (ii) but not in (iii); Liulin subproject will remain viable in all scenarios; all other

Appendix 15 63

subjects will become inviable in any of the unfavorite scenarios. Benefiting from the Jingzhong and Liulin subprojects, the overall project will remain viable in scenarios (i) and (ii) but not in (iii). The sensitivity analysis is in Table A15.3.

Table A15.3: Results of the Sensitivity Analysis at the Completion FIRR (%) Subprojects Base Revenue O&M Cost Combined -10% (i) +10% (ii) (i) and (ii) Jinzhong 7.97 4.67 6.29 2.85 Licheng 3.62 0.90 1.97 -1.14 Qin 3.34 0.80 1.92 -0.91 Zhongyang 2.83 -1.31 -0.04 -5.35 Liulin 8.67 5.49 6.92 3.28 Overall Project 6.18 3.28 4.65 1.38 FIRR = financial internal rate of return, O&M = operation and maintenance Source: Asian Development Bank estimates.

D. Financial Performance of Project Implementing Agencies

11. According to the project agreement, in each fiscal year commencing from 2 years after Project operations, the project entity for the each of five subprojects shall maintain (a) minimum debt-service coverage ratio of 1.2:1, (b) maximum debt–equity ratio of 70:30, and (c) minimum ratio of current assets to current liabilities of 1:1. Table 4 shows these ratios based on the entity financial statements of fiscal year 2017 of respective agencies, which was the latest financial statements available at time of completion review.

Table A15.4: Financial Indicators of PIAs in 2017 Current PIA DSCR Debt Ratio Ratio Jinzhong Ruiyang CHP Heat Supply company 3.07 69% 1.28 Licheng County Wantong Heat Supply Company n/a 100% 0.80 Qin County Huayang Heat Supply Company n/a 109% 0.34 Zhongyang Heating and Gas Supply Center n/a 114% 0.74 Liulin County Coal Gasification Company n/a 54% 0.71 DSCR= debt-service coverage ratio, PIA= project implementing agency, n/a refers to the situation that the ratio is not applicable due to the debt service requirement. Sources: Annual entity financial statements provided by the project implementing agencies.

12. Except Jinzhong Ruiyang CHP Heat Supply company which demonstrated strong financial performance and satisfied all the covenanted ratios, other PIAs did not satisfy the covenanted ratios. The main reasons include high debt ratios and the operating losses resulted from the low heat tariff, high coal costs, and low operational efficiency. The immediate task for these companies is to improve the tariff collection ratio (currently less than 80%) and installation of heat measuring devices at client level to support consumption-based billing system which would be helpful to improve the situation. It has been noted the local governments have committed to support these companies considering the nature of the project which concerns the welfare of the public through debt restructuring and providing subsidies to meet the debt services obligations and the gap between the tariff collection and the recurrent operating cost of the company. County governments should also periodically review the heat tariff and gas supply price and initiate tariff adjustment timely to ensure cost recovery as well as debt payment.

64 Appendix 16

SOCIAL IMPACT AND LABOR RETRENCHMENT PLAN

A. Introduction

1. The project benefited directly about 112,186 urban households in five highly polluted urban areas of Shanxi Province including 490 of which are poor (including 207 households headed by women) by reducing air pollution through cleaner district heating and natural gas supply. The project supported in preparation and implementation of heating reforms, including a pro-poor tariff design and providing free heating connection to ensure an affordable heating supply for the poor. By reducing consumption of coal and providing cleaner and more reliable heating services and coal-mine methane (CMM) supply, the project has reduced the threat of coal emissions posed to public health, freed up resources, and lowered safety risks associated with respiratory diseases, coal mining and transportation. The improvements in energy security and environmental quality have benefited local communities, the poor in particular, because they are more vulnerable than the general population to the health risks. The project has made desirable contributions in the improvements of air quality in the five urban areas by increasing 16% to 27% of the record in meeting Class II air quality standard in 2017-2018 heating season compared with 2011-2012 heating season.1 The poor, the elderly, children, and women who are more vulnerable to the effects of air pollution benefit disproportionately from the project. It is expected that at the project full development, the improved air quality will reduce the morbidity and mortality rates from air-related diseases and the associated medical costs in local communities in the project areas.

B. Labor and Employment

2. The project helped create a number of jobs during project construction as well as in the energy efficiency sector during operation. A total of 787 temporary jobs were provided to local people including 134 female workers (Table A16.1). The project has demonstrated the benefits of improving energy efficiency through use of energy efficiency technologies in the subprojects. This creates more technical and vocational job opportunities in energy efficiency sector. A total of 306 jobs were created during project operation including 107 female workers. Overall, the project has promoted energy efficiency improvement, created employment, and helped reduce poverty, thereby contributing to the economic development of Shanxi Province.

Table A16.1: Employment Opportunity Created by the Project Number of Temporary Jobs Number of Fixed Jobs during Subproject during Construction Operation Total Female Total Female Jinzhong County 550 74 28 11 Licheng County 73 40 121 59 Liulin City 38 5 14 5 Qin County 105 10 106 19 Zhongyang County 21 5 37 13 Total 787 134 306 107 Source: Project Management Office Project Completion Report.

1 The Ambient Air Quality Standards that are currently effective, GB 3095-2012, were released by the then Ministry of Environmental Protection on February 29, 2012. The Standards set mandatory limits for the primary pollutants— SO2, nitrogen dioxide (NO2), carbon monoxide (CO), O3, PM10, and PM2.5—and took effect nationwide on January 1, 2016. The Standards set two classes of limit values: Class I standards apply to regions that need special protection such as natural reserves and natural scenic areas, while Class II standards apply to all other areas including residential, mixed-use, industrial, and rural areas.

Appendix 16 65

C. Labor Retrenchment Plan Implementation

3. The Shanxi Energy Efficiency and Environmental Improvement Project consists of five subprojects including: (i) Jinzhong Urban District Heating Network; (ii) Licheng County District Heating; (iii) Qin County District Heating; (iv) Zhongyang County District Heating; and (v) Liulin CMM/CBM Transmission and Distribution. By the project completion, a total of 398 small boilers were closed in four sub-projects (Zhongyang County District Heating, Licheng County District Heating, Qin County District Heating and Liulin City). 468 affected boiler workers (30 formal employees and 438 seasonal temporary workers) were trained and reemployed by the PIAs and local government. The number of boiler closures and affected workers by sub-project are summarized in Table A16.2.

Table A16.2: Boiler Closures and Affected Workers

Reemployment of the Affected Workers Number of affected workers Subproject boiler houses closed Formal Seasonal Total Female (female) (female) Licheng 132 0 130 (59) 121 59 County Liulin City 43 24 (5) 37 (10) 61 15 Qin County 200 0 250 (0) 250 0 Zhongyang 23 6 (0) 21(0) 27 0 County Subtotal 398 30 (5) 438 (69) 459 74 Sources: Project Management Office project completion report and Government Working Reports.

4. The labor retrenchment plan was prepared to safeguard the livelihoods of affected workers who were working in the small boiler houses to be closed by the project. Reemployment of the affected boiler workers was arranged by each project implementation agency (PIA) upon completion of each subproject. The PIAs provided training to affected workers and training topics included pipe maintenance, stoker, laboratory technician, machine maintenance, heating relay station equipment maintenance, etc. 30 regular workers were reassigned to the heat exchange stations and heating companies with no changes in the level of their wages and benefits. The local government and PIAs jointly arranged the re-employment of the 429 seasonal boiler workers with job skills training and they were prioritized of job opportunities. Based on the project completion report, they are satisfied with the rearrangement and benefits. To date, no complaints from the retrenched boiler workers were reported.