Earned Value Management: APM Guidelines
©Association for Project Management 2008 ©Association for Project Management 2008 APM Guidelines Earned Value Management Value Earned ©Association for Project Management 2008 ©Association for Project Management 2008 Association for Project Management Association for Project APM Guidelines Earned Value Management Value Earned ©Association for Project Management 2008 HP27 9LE Buckinghamshire Ibis House, Regent Park Ibis House, Copy editor: Merle Read Copy ISBN 10: 1-903494-26-5 ISBN 13: 978-1-903494-26-4 Cover design by Mark Design design by Cover Typeset by RefineCatch Limited RefineCatch by Typeset Association for Project Management for Association makes no claim to these trademarks. Publishing Manager: Ingmar Folkmans Summerleys Road, Princes Risborough Summerleys ©Association for Project Management 2008 ©Association for Project British Library Cataloguing in Publication Data is available Cataloguing in Publication Data British Library All registered trademarks are hereby acknowledged and the publisher acknowledged are hereby All registered trademarks as permitted under the Copyright, Designs and Patents Act, 1988, and its Act, 1988, and Designs and Patents Copyright, as permitted under the permission in writing of the Chief Executive of the Association for Project of the of the Chief Executive permission in writing these terms and in other countries should be sent to the Publishing Rights these terms and in other countries should the Copyright Licensing Agency. Enquiries concerning reproduction outside Agency. Licensing the Copyright Readers are responsible for the correct application of the information in this Readers are responsible for the correct application licences issued by the appropriate reprographic rights organisations, such as rights organisations, such the appropriate reprographic licences issued by Management. Within the United Kingdom exceptions are allowed in respect in respect Kingdom exceptions are allowed the United Within Management. The Association for Project Management cannot accept legal responsibility or Association for Project Management The Department, of the Association for Project Management at the address above. Department, of the All rights reserved. No part of this publication may be reproduced, stored in a of this publication may No part All rights reserved. retrieval system or transmitted, in any form or by any means, without the express means, without any by form or in any system or transmitted, retrieval amendments, or in the case of reprographic reproduction in accordance with the reproduction amendments, or in the case of reprographic of fair dealing for the purposes of research or private study, or criticism or review, or review, or criticism study, or private purposes of research of fair dealing for the publication and its conformity with all relevant legal and commercial obligations. and commercial legal publication and its conformity with all relevant liability for any errors or omissions in this publication or the consequences thereof. liability for any ©Association for Project Management 2008 1 8 2 3 9 9 5 5 6 4 37 37 39 13 24 32 33 36 36 40 45 51 53 55 25 v review alue management guidelines Contents performance measurements performance collection eillance What are the benefits? Analysis, review and action Foreword Basic requirements for an earned value system value for an earned Basic requirements 6.3 Surv 5.5 Change management 5.5 Change management 5.6 Risk 6.1 baseline review (IBR) Integrated 6.2 Demonstration 5.3 Data 5.4 4.1 principles management Earned value 4.2 5.1 Definition 5.2 Planning 4.3 Using
Bibliography A –Appendix Earned v 6 System review 6 System 1 Introduction 2 Applicability 3 4 management? is earned value What Appendix B – and glossary Terminology Appendix C – and acronyms Abbreviations Appendix D – equations Earned value Index 5 Process discussion 5 Process ©Association for Project Management 2008 6 7 12 18 27 28 29 17 23 16 14 vity vi kage, and acti ork pac Budget vs actual plus earned value graph plus earned value Budget vs actual matrix Responsibility assignment Earned value graph Earned value chart Bullseye trend graphs Variance Budget elements Budget vs actual graph Budget vs Hierarchy of schedules Hierarchy effort of subcontract Integration Relationship between control account, Relationship between w BCWP calculations based on the formula methodBCWP calculations based on the calculations package Apportioned work 22 Example of projecting anticipated performanceExample of projecting anticipated 31 Figures and tables Figures Figure 5.2 Figure 4.2 Figure 5.1 Figure 5.6 Figure 5.7 Figure 5.8 Table 5.1 Table 5.2 Figure 5.5 Table 5.3 Figure 4.1 Figure 5.3 Figure 5.4 ©Association for Project Management 2008 Steve Wake Steve Specific Interest Group 1 Chairman APM Earned Value Management Value APM Earned Chairman Foreword In late 2007 the guideline was reviewed and overhauled. Particular thanks are Particular reviewed and overhauled. was In late 2007 the guideline and to improve years the over revision aimed to fix errors identified This again in 2011. Please address any guide will be formally reviewed This The first edition of this guideline was published in 2002. It was well received well It was in 2002. published was of this guideline first edition The internationally. both nationally and through to its publication. the final draft for overseeing due to Jim Malkin Standard. Value 748 Earned ANSI American It is still reciprocal with the clarity. Manage- Value APM Earned the Chairman of the to comments and feedback Group at www.apm.org.uk. ment Specific Interest ©Association for Project Management 2008 2 1 Introduction defined scope and assumptions; in logical sequence; scheduled activities (labour and materials). resources/costs the plan is; what the project has achieved; what has been spent to date. what status; measurement of project data to enable objective providing a basis for estimating final cost; providing the project will be complete; predicting when management of resources; supporting the effective change. a means of managing and controlling providing of the plan; has been achieved what the planned work; it has cost to achieve what planned; is costing more or less than was achieved if the work if the project is ahead of or behind the planned schedule. The establishment of a performance measurement baseline (PMB) is essential establishment of a performance measurement The Earned value management is a project control process based on a structured a project control process based on management is Earned value It collection and performance measurement. to planning, cost approach the and of project scope, time and cost objectives facilitates the integration (Association baseline plan for performance measurement establishment of a 2006). for Project Management, EVM and consists of: to conducting successful • • • need to know: We • • • helps us manage by: Earned value • • • • • knowing: decision making is enabled by Informed and effective • • • • infor- Good planning leads to good project execution and good management planning can lead to poor execution and poor EVM information. mation. Poor plan must be maintained in accordance with authorised project changes. The not be immedi- deviations from the plan, but it may show EVM will accurately plan is being tracked. ately evident that a flawed ©Association for Project Management 2008 can be applied to projects of vary- can be applied to projects 3 2 Applicability project specific requirements; customer requirements; previous projects; lessons learnt from IT toolset requirements; and infrastructure. impact on resources Earned Value Management: APM Guidelines Management: Value Earned ing size, scope and duration to ensure that the EVM process is operated in a is operated to ensure that the EVM process duration ing size, scope and project implementing across all implementing teams. Each consistent manner should take into account: • • • • • progress and performance measurements Project managers should ensure that this guide. are realistic and are in accordance with ©Association for Project Management 2008 , the WBS and the OBS , the 4 3 define the scope (section 5.1.1); define the scope (section (section 5.1.2.2); the work structure (WBS) to define breakdown use a work accomplishment in an organ- for work establish organisational responsibility 5.1.2.3); structure (OBS) (section isation breakdown other each ensure management subsystems support (section 5.1.2.4); 5.2.4); WBS (section distribute the budget into the (section 5.2.2); using a logic-linked method all authorised work schedule 5.2.5); (section identify a method of measuring achievement (sec- for the work schedule time consistent with the spread the budget over tion 5.2.6); baseline the plan (section 5.2.6); 5.3.1); record direct and indirect costs (section on a peri- at the control account level collect and analyse performance data odic basis (section 5.4.2); 5.4.3); (section produce forecasts for remaining work controlled manner (sec- in a timely and all authorised changes incorporate tion 5.5). Basic requirements for requirements Basic an earned value system value an earned This document is a guide to the process for implementing and running an for implementing and running document is a guide to the process This list describes the fundamen- following The management system. earned value that should be undertaken: tal steps of the process • • • • • • • • • • • • • ©Association for Project Management 2008 wing: ork; , stated in the value of schedule, stated in the value 5 4 for the work actually achieved. for the work hieved should have cost, according to the cost, should have hieved management? ed actually cost. ces as necessary to meet project scope and schedule objectives. and schedule ces as necessary to meet project scope What is earned value What work to be performed, and is therefore a basis for both time and cost assess- work ment of the progress on a project. – or actual cost (AC) performed (ACWP) actual cost of work The the i.e. what achiev work It is important to understand that BCWS is a (EV) – i.e. performed (BCWP) or earned value budgeted cost of work The ac amount of work the what planned budget: the earned value development of a ‘baseline’ against which cost, schedule and technical per- and technical cost, schedule of a ‘baseline’ against which development formance can be measured; performance measurement; objective action reporting; analysis and corrective variance changes. of ‘baseline’ disciplined and timely incorporation status reports; verifiable analysis; clear objective considered reasoning; process; accountability in the decision-making and cost across the project; of impact on the schedule awareness visibility of results. (PV) – (BCWS) or planned value scheduled work budgeted cost of The i.e. of bud- for the expenditure we are going to do, the plan: the schedule what geted resour definition and authorisation of the contract scope of w definition and authorisation of the contract 2. 3. • • • • the follo provide management system (EVMS) will An earned value • • • • • • enable the measurement of the four key A system should be created that will data elements essential to EVMS, namely: 1. 4.1 PRINCIPLES MANAGEMENT EARNED VALUE the life of a project. and managing goals throughout EVM is about establishing It comprises the following: • ©Association for Project Management 2008 Budget Time 6 Time Now Time – Budget vs actual graph Figure 4.1 Figure
Actual Costs
APM Guidelines Cost The estimate at completion (EAC) of the project. This is the ACWP to date, ACWP is the This of the project. at completion (EAC) estimate The scope, requirements, of remaining estimate most knowledgeable plus the and cost. schedule hese guidelines are expressed in fundamental terms and provide flexibility and provide expressed in fundamental terms hese guidelines are for each company to optimise its system, and be fully accountable for the system, and be fully accountable to optimise its company for each as an guidelines (or criteria) are recognised These of its usage. effectiveness An EVMS that is A. Appendix at and are attached international standard, stakeholders, key intent of the criteria, will allow to meet the developed that projects are being and shareholders, to gain confidence notably customers consistent manner against and effective in an deployed managed and resources a recognised standard. 4.2 ARE THE BENEFITS? WHAT used It is traditionally budget vs. actual graph. the traditional 4.1 shows Figure to compare budget with actual spend. 4. and applying an EVMS. companies to use in establishing Guidelines exist for T Earned Value Management: Value Earned ©Association for Project Management 2008 Budget What is earned value management? value What is earned Time Earned Value 7 line. This additional line represents the pro- additional This line. Time Now Time – Budget vs actual plus earned value graph Actual Costs achievement show:
Figure 4.2 Figure
wn in Figure 4.2 is similar to the previous graph except that a to the previous graph 4.2 is similar wn in Figure Cost if the project is ahead of or behind schedule; is ahead of or if the project or underspending; over- if the project is truly money; for value if the project is getting spent on the right things; if money has been only just begun. or have over if the problems are Figure 4.2 indicates the following additional information: 4.2 indicates the following Figure measure of performance (or status value) has been included. The line included The has been included. (or status value) measure of performance or is the earned value that has actually been achieved. portion of the budget The graph does not does graph The • • • • sho graph The • ©Association for Project Management 2008 of the many criteria on of the many one of the efficiency or perform- of the efficiency 8 orse than was indicated on the traditional indicated on orse than was heduled; ver-expenditure coupled with underachievement ver-expenditure verspend is going to increase, even though the even is going to increase, verspend As such, they should be used as As such, verspent because the cost of the work completed is greater work the cost of the because verspent of planned work scope; of planned work as it is costing more to achieve money inefficiently, the project is spending to be contained, cost problems do not appear The progress than planned. budgeted cost line; the actual cost line is greater that the since the slope of the o this indicates that line some it will intersect the budget cost line does look like earned value the cost be possible, yet may recovery schedule While time in the future. impact is unlikely to be recovered. that the budgeted cost of work completed (earned value); cost of work that the budgeted is actually w the cost performance chart because it shows an o because it shows chart the project is underachieving because the amount (value) of work completed of work amount (value) because the is underachieving the project than that sc is less (earned value) is o the project Performance measurements indicate where shortfalls are occurring or likely to indicate where measurements Performance ance of a project. • MEASUREMENTS PERFORMANCE 4.3 USING measurements of performance are indicators Any • • • which project managers should base their decisions, having interpreted the interpreted having project managers should base their decisions, which information and placed it in context. management resources, extra can be used to identify where These occur. are They problems. in order to overcome actions or other support are required happen to the might what pointers as to early indicators of problems and give project if actions are not taken. Earned Value Management: APM Guidelines APM Management: Value Earned ©Association for Project Management 2008 ork to be 9 5 vide guidelines as to the main elements contained vide guidelines as to the main elements ve structures? ve ables, for the project. It forms the basis for allocating work, ables, for the project. It forms the basis process is principally concerned with defining the w process is principally concerned with Process discussion Process definition definition; planning; data collection; action; analysis, review and management; change risk management. The extent to which the SOW fully describes the requirements of the project the SOW extent to which The Breakdown structures are essential to project management in the following Breakdown areas: 5.1.1 (SOW) scope/statement of work Project requirements, the overall can define the project scope to include A SOW including deliver requirements. budget and schedule meas- objective the ability of the EVM system to provide an impact on will have ures of performance against the original project requirement. structures breakdown 5.1.2 Project ha 5.1.2.1 Why done –WBS – as a of the project’s to specific parts and assigning that work OBS should be aligned and combined WBS and The organisation via the OBS. matrix (RAM). to produce a responsibility assignment within each process. At the end of each process, a checklist of key activities is of key activities process, a checklist At the end of each process. within each provided. 5.1 DEFINITION Organising the requirements of the project. the work and resources to achieve The Earned value management may be considered as a number of management be considered management may Earned value processes, as follows: • • • • • • sections pro following The ©Association for Project Management 2008 WBS and an OBS, and integrate the and integrate WBS and an OBS, 10 The WBS is developed by identifying high-level elements of identifying high-level by WBS is developed The ; a contract number; a contract WBS number and title; a WBSD issue number and date; the number; paragraph the contract to be produced as deliverables including all contract a statement of work element; part of the work the definition and clarification of the work to be performed; of the work and clarification the definition out the for carrying organisations responsible of tasks to the assignment work thorough planning; and control of baselines; the establishment where the plan at levels against measurement of achievement the objective is being performed; the work and the and reporting to higher management, the collection, summarising process; for use in the decision-making customer, performance measurements. alue Management: APM Guidelines alue Management: When developing a WBS, it is advisable to concentrate solely on the work solely to concentrate WBS, it is advisable a When developing structure dictionary (WBSD). breakdown to use a work choose Projects may should contain: WBS, the dictionary element of the each For two into a responsibility assignment matrix (see Figure 5.1 below). All control 5.1 below). (see Figure into a responsibility assignment matrix two steps are necessary These 5.1.2.4). accounts should be identified (see section be undertaken. measurements of performance can before any structure breakdown 5.1.2.2 Work is elements of work of a project into discrete subdivision hierarchical The WBS. as a known major elements are These necessary to meet the project requirements. work continues until breakdown This into smaller components. then broken down visibility and con- of detail deemed necessary for management level the lowest WBS can be included and the are All aspects of the contract trol is established. representation of the SOW. hierarchical viewed as a graphical content of the project. to be is to describe the entire scope of work purpose of the dictionary The scope and all contract contract the project. It must capture the undertaken by reference a ready it must provide enable this to be checked To requirements. the basis for the state- provides elements. It also WBS and contract between the Plans. included on the control account ment of work • • • • • • • • • • • • budgets are are made and the associated operating assignments Before work should establish a established, a project Earned V Earned ©Association for Project Management 2008 ve, then it ve, Process discussion 11 A fundamental requirement of a well-managed project is a of a well-managed project A fundamental requirement ork. A WBS reflects the way in which work has been subdi- work in which WBS reflects the way A ork. defined scope of work; measure of achievement; WBS; up through the traceability budget; assignment of responsibility; start and finish dates. To assign work responsibilities to appropriate organisational elements the WBS organisational elements the responsibilities to appropriate assign work To can be OBS at the control account level WBS and the of the integration The (WPs). packages a number of work A control account will normally comprise In order to clarify and define the organisation, an organisation chart or organ- chart define the organisation, an organisation In order to clarify and authorities and accountabilities will Loose definition of roles, responsibilities should be identified as a planning package within the control account –should be identified as a planning package see section 5.2.1. vided. break- work assignment of lower-level The must be interrelated with the OBS. a key control point for provides elements to responsible organisations down management purposes and cost collection. WBS axis and the as a matrix, with the OBS elements listed on one displayed each assignment matrix, where is the responsibility This elements on the other. with a control account manager (CAM) element is a control account (CA) responsible for its completion to budget. work Each package. work be a single In some cases, a control account may attributes: lowing the fol should have package • • • • • • to the detail noted abo package If it is not possible to define a work clear people organisation. Where matrix management structures are used, this Where matrix management structures clear people organisation. definition is particularly important. clarity in organisational and Roles, responsibilities should be developed. structure isation breakdown communicated across be clearly defined for all staff and accountabilities should a clear should have Staff being introduced into the project the project team. they are responsible. work to and for what they report of whom knowledge the management of the project. lead to ambiguities and confusion in accounts 5.1.2.4 Control the project has organised the people who in which An OBS reflects the way the w will achieve The WBS dictionary should include all elements to be subcontracted and be subcontracted all elements to should include WBS dictionary The WBS element. the undertaking the subcontractor identify should specifically structure breakdown 5.1.2.3 Organisation functions and departments of a variety people from Projects usually involve across a company. ©Association for Project Management 2008 Planning Packages Work Packages Work CA = Control Account (OBS)
Structure CA Breakdown Organisation
CA 12
CA – Responsibility assignment matrix
CA Figure 5.1 Figure Once the WBS (and the dictionary, if used) has been completed, it should be completed, it should if used) has been (and the dictionary, WBS Once the The area. work each the control account is identified for It is important that level system is the lowest management control account in an integrated The control that has been established. If of the level 5.1) shows RAM (Figure The reconciled back to the requirement and other formal agreements to ensure that to ensure other formal agreements the requirement and to back reconciled been included. of the project have all aspects and control of project the main action point for the planning control account is control responsibility for the individual management It is the point where work. control accounts, responsible for many be may A manager accounts is assigned. only one manager. have may but a control account costs between actual costs and budgeted comparisons in the structure at which analysis will also be done at However, management. by are normally required taken at control. Most management actions as required for local levels, lower control problems identified at the significant by are triggered higher levels selected for the establishment of the the levels this reason, For account level. should be carefully considered at the organisation and the control accounts outset of the project. they or too few, or too small, too many the accounts identified are too big accordingly. should be reconsidered and changed RAM Work Work Breakdown Structure (WBS) Earned Value Management: APM Guidelines APM Management: Value Earned ©Association for Project Management 2008 APM Process discussion processes are Management: planning The 13 kages and planning packages). wing: y whom and by when? y whom and by in any subcontract. Reporting requirements should be consistent Reporting requirements should subcontract. in any budgets; schedules; forecasts; assignments; work cost collection; progress assessment; problem identification; actions. corrective a plan of logically scheduled activities that reflect the project objectives, activities a plan of logically scheduled goals and milestones; Determine and agree requirements for flowdown of EVM requirements into flowdown Determine and agree requirements for subcontracts. Review the project requirements and establish key deliverables. Review the project requirements and WBS. a Develop an OBS. Develop a RAM identifying control accounts. Generate the lowest to WBS element down WBSD statements for each Produce pac (e.g. work appropriate level The following aspects of the project come together at the control account: together at the of the project come aspects following The Processes should be in place to ensure that subcontractor’s plans are repre- plans that subcontractor’s Processes should be in place to ensure • • • • • • • • management 5.1.2.5 Subcontract of Earned Value It is appropriate to reflect the requirements primarily concerned with establishing a baseline for performance measurement that encompasses the follo • 6. 5.2 PLANNING b What needs to be done, Guidelines other factors. with project risk, size, complexity and a view of total proj- to derive in order sented within the project plans/schedules large and complex, very for a project can be ect performance. Plans derived be incorporated of detail to to be taken as to the level and so decisions have maintenance of the plan becomes detail, the into the plans. If there is too much the exact status of if there is insufficient detail, while a burdensome overhead, the project is difficult to ascertain. 5.1.3 in definition activities Key 1. 2. 3. 4. 5. ©Association for Project Management 2008 h the project will be h the project will hic 14 ycle lengths, and to consider when and how to earn and how consider when ycle lengths, and to YEAR2 YEAR3 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M1 Figure 5.2 –Figure Relationship between control account, work package, and activity. budgets/resources agreed and assigned to these activities; agreed and assigned budgets/resources measures defined. achievement objective Planning packages (PPs) represent work that cannot yet be planned as work that cannot yet (PPs) represent work Planning packages Each work package comprises a number of activities to be performed. Each to be performed. comprises a number of activities package work Each packages because of a lack of detailed information. Normally this is future because of a lack packages to be started for at least three full months from the that is not scheduled work packages in the near future that cannot be planned in work Work current date. definition. problem of work indicate a may ‘value’. Each work package must have a clearly defined start condition and a clearly defined start condition must have package work Each ‘value’. package work of each scope The defined. finish point, with all deliverables identified. the procedures to be followed must be unambiguously defined with is a step- activity Each package. can be assigned to only a single work activity a 5.2 shows Figure package. completion of its parent work ping stone towards and packages planning packages, of the relationship between work schematic and costs are estimated; resources duration, is where activity The activities. between activities. dependencies are shown monitored and controlled throughout its life cycle, and will allow the achieve- and will allow throughout its life cycle, monitored and controlled business success criteria. ment of project and 5.2.1 and activities planning packages packages, Work performance data is normally at which level is the lowest package work The and scope of the work important to balance the length analysed. It is therefore against reporting c package • • baseline against w will constitute the project These Activity 4 Activity 5 Activity 6 Milestone 2 Activity 1 Activity 2 Activity 3 Milestone 1 Planning Package 1 Planning Package Work Package 2 Package Work Work Package 1 Package Work Control Account 1 Task Name Task Earned Value Management: APM Guidelines APM Management: Value Earned ©Association for Project Management 2008 Process discussion hedule logic spec- 15 Schedules can be created to reflect various elements of the WBS, from the the elements of can be created to reflect various Schedules from the within the schedule milestones should be included All contractual critical path are iden- on the current EVMS that activities It is essential in any planning of project process permits the integrated scheduling overall The PPs are structured below the control account level, have a defined scope of have account level, the control below PPs are structured before work packages into work be converted must Planning packages to work package from planning requirement for a periodic conversion, The ifies when an activity should start or end on the basis of duration, predecessors, duration, should start or end on the basis of an activity ifies when a For or target dates. availability external predecessor relationships, resource Appendix B. see definition of a schedule the lowest containing schedules package plan to detailed work highest-level and form the basis for assessing actual progress schedules These of activity. level performed. comparing actual cost against work should be logically linked to milestones contractual These start of the project. applied through- to forecast dates are changes so that any appropriate activities out the schedule. to be appropriately categorised from the plan will enable variances This tified. – pre- To path’. e.g. ‘late but float remains’ as opposed to ‘late and on critical to exclude choose on large projects, a project may workload clude excessive used for critical path analyses. from the network of schedules the lower-levels support the summary-level always must schedules level the lower However, the same basis. so that all analyses have schedule a of the project, and provides objectives with the cost and schedule resources and work means of measuring progress against planned effort. Scheduling scope definition are prerequisites for basic project management and effective cost control. work and are allocated a time-phased budget. They have scheduled start and scheduled have They budget. a time-phased and are allocated work and scope. a defined budget and (hence a duration) finish dates or have achievement, them, i.e. before they can ‘earn’ can commence upon the planning from budget is withdrawn The them. costs booked against as their start date nears and packages work and is used to establish package will packages resulting work The tasks become clearer. the details of the and achievement logic, milestones, resources activities, contain the detailed measures. planning, wave up the project using rolling is the result of setting package, future a project is planned in detail and only the current phase of whereby process is a fundamental aspect conversion The phases are planned in outline. in a more controlled project baseline. of project control using EVM and results 5.2.2 Schedules will take place activities project is the process of determining when Scheduling Sc activities. and preceding depending on defined durations ©Association for Project Management 2008 Master Levels Schedule Schedules Schedules Schedules Integrated Contractor Work Package Work Subcontractor Control Account Summarisation Schedule Milestones Work Package
CA
Team 2
Functional Work Package
16
CA
ack and manage progress. These activities These manage progress. and ack – Hierarchy of schedules Project Level Key Milestones Key Work
Package
CA Team 1
Functional Figure 5.3 Figure Work Package
CA Work Package The baseline should respect all key milestones: the agreed contractual the agreed contractual all key milestones: should respect baseline The to be performed and resources for activities the time frame provide Schedules for requirements, it is common practice individual project has Although each Plan Master will be shown in the project schedule as either work packages/planning packages/planning as either work in the project schedule will be shown 5.2.3 baseline relationship and schedule Subcontractor plans should detail an appropriate number of activities/ supplier’s The tr milestones required to effectively delivery milestones and appropriate internal indicator milestones. The key The indicator milestones. appropriate internal milestones and delivery control. for measurement and should be used milestones to be utilised. series data set consisting of a a single schedule by the project to be supported all data set covers This network. into an integrated built of detailed schedules can be schedule The the requirements of the project. necessary to meet work of levels various of detail to accommodate the levels summarised to different 5.3). criteria required (Figure visibility and selection Stages Milestone Handover Schedules Schedules Milestones Integration Subcontractor Control Account Earned Value Management: APM Guidelines APM Management: Value Earned ©Association for Project Management 2008 Control Account Process discussion Sub- Major contractor Sub- Minor contractor 17 – Integration of subcontract effort Sub- Minor contractor Figure 5.4 Figure Sub- Major Control Account Control Account Control Account contractor The resourcing/budgeting of the work should reflect the value of the item or the value should reflect of the work resourcing/budgeting The into the baseline (Figure effort is integrated subcontractor in which way The accounts, should be structured as single control major subcontractors Ideally, packages/PPs, within single work should be structured Minor subcontractors packages or as individual control accounts, depending on the level of detail to of level on the accounts, depending control or as individual packages to provide sufficient detail of incorporation, the level Whatever be reported. is problems and issues of potential early warning of actual status and visibility to packages to structure the control accounts/work vital. It is also important effort and spe- of both ‘in-house’ supplier management enable the recording effort. cific subcontractor service – – as agreed in the contract profile or a realistic expenditure to allow ‘mile- Furthermore, there should be a discrete to be generated. budget curve of the measurement reporting period to allow in every stone’ identified should be expected to the supplier However, on a regular basis. achievement of the detail of irrespective report (or equivalent), a monthly progress provide be used report can This the project schedule. contained within their schedule (or otherwise). as the basis for claiming achievement distinction The to the project. 5.4) will differ according to their importance as be based upon factors such should between major and minor subcontractor supply) (e.g. single source criticality (risk) to the project equipment value, they are an ‘off the shelf’ supplier. and/or whether the ability to to provide importance but also not only because of their relative status. clearly monitor their overall minor subcontractors. containing several with a control account conceivably visibility of performance, but not at the lower for appropriate still allows This baseline. within the integrated levels Subcontractor Detailed Programme Integrated Baseline ©Association for Project Management 2008 Margin The hierarchy of hierarchy The hole. Management Reserve Undistributed Budget As work packages are subdivisions of are subdivisions packages As work 18 – Budget elements ailable for expenditure in the accomplish- v Figure 5.5 Figure Planning Packages Control Account Budgets Packages Work Contract Price Contract Budget Baseline Measurement Baseline Performance Distributed Budget Budget cannot be spent; it is the funds that are consumed. Funds are autho- Budget cannot be spent; it is the funds the project with provides formulation of estimates at completion (EACs) The ment of the effort. Budgets are established for the relevant elements of the work for the relevant ment of the effort. Budgets are established structure and are time-phased. breakdown on a total or periodic basis. the company the customer or by rised by forecasting the actual visibility of the anticipated/out turn funds required by element. statement of work approved funding requirements for any 5.2.4.2 Budget cost types and rates different types of costs that need to be sum- many Projects usually involve of detail. levels marised through various 5.2.4.1 Budget versus funds versus 5.2.4.1 Budget is different from the concept of an EVM system the concept of budgets Within the cost performance target for a specific While a budget represents funds. effort, funds represent the money a budget elements is shown in Figure 5.5. This illustrates how the intermediate how illustrates This 5.5. in Figure shown budget elements is budget baseline. leading to the contract summations are defined 5.2.4 Setting budgets 5.2.4 Setting to individual cost targets distributing or allocating is the process of Budgeting must exist at all times in Strict budget element relationships segments of work. w the sum of the parts is equal to the order to ensure that Earned Value Management: APM Guidelines APM Management: Value Earned ©Association for Project Management 2008 Process discussion ork-scope require- ork for the contract DB UB 19 PMB , section 5.2.4.7). ation of the project. It is equal to the total allocated budget less distributed budget Management reserve must never be used to eliminate past or current cost or be used to eliminate must never Management reserve scope originat- in work changes should not be used for Management reserve Generally, the CBB is fixed throughout the duration of the project, unless of the project, the CBB is fixed throughout the duration Generally, the further dissection of the CBB results in Project baseline budgeting activity Budgets (in terms of pounds, hours or other measurable units) should be of pounds, hours or other measurable Budgets (in terms It is the summation of all budgeted work that forms the performance meas- that forms the performance of all budgeted work It is the summation management reserve, and is represented as the BCWS. The PMB consists of The and is represented as the BCWS. management reserve, undistributed budget (UB) and distributed budget (DB): ments due to any unforeseen changes that fall within the overall scope of the scope the overall that fall within unforeseen changes ments due to any contract. to future efforts of reserve does not preclude allocation This variances. schedule agrees there is due cause. in problem areas if the project manager agreed amendments with contract by are covered These ing from the customer. scope and in work to reflect the changes CBB is then increased The prices. budget. baseline measurement 5.2.4.5 Performance PMB is the time-phased budget plan, representing all budgets against which The spread across the is measured, performance (cost and schedule) the contract planned dur comprising the management reserve (MR) and PMB. This should equal the sum This and PMB. (MR) comprising the management reserve of the authorised budgets. change. amended through contractual with a PMB and a management reserve. reserve 5.2.4.4 Management allocation to control for future It is held separately MR is a portion of the CBB. increased w to cover accounts and will be used, if required, work, then each work package will comprise a number of differing types of of differing types a number will comprise package work then each work, types. for different cost raised should not be packages work costs. Separate to denote terms are used systems, specific management earned value Within area of the budget has specific inclusions/exclusions. each types of budgets, and account. Budgets should control each within package work allocated to every other direct costs and any subcontract material, identify labour, separately (see urement baseline. baseline budget 5.2.4.3 Contract minus the mar- value contract budget baseline (CBB) is the total contract The w CBB represents the total budget of all authorised The gin. ©Association for Project Management 2008 y or the cus- y be subject to et started. 20 et been allocated to control accounts. As work is defined As work to control accounts. et been allocated issues h has not y amount available; time-phasing of funding availability. Changes to projected funding may include: Changes to projected funding may measurement problem, since these presents no performance Completed work then the activities, and is tied to schedule If the earning method is objective Undistributed Budget is allocated primarily to accommodate temporary temporary is allocated primarily to accommodate Undistributed Budget aside for specific but be in place to ensure that UB set Procedures should tomer, and as such is subject to external commercial constraints. is subject to external commercial and as such tomer, • • ma and schedule work In these cases, the budget and associated change. 5.2.5 of progress measures Objective in assessment of work measurement is the objective key to performance The progress or not y is completed, in All work progress. will not be measured until the been closed. Future work have packages work to be concerned about are those packages only work The gets under way. work that are planned to be or are actually in progress at the end of the reporting will lie largely in the difficulty of assessment of those packages The period. of detail and the earnings method that has been selected. level and can be automated. If the earnings method is job is straightforward completion, then a manual denoting a percentage to events or tied subjective is in progress (also referred package a work assessment will be necessary while to as being ‘open’). The difference between funds and budget has been described above (section funds and budget has been described above difference between The from the compan available 5.2.4.1). Funding represents the money and assigned to control accounts, the UB should be reduced accordingly. accounts, the UB should be reduced and assigned to control requirements contract accounts can be agreed, or where situations until control terms. general in very can be defined only distributed elsewhere. is not unallocated work budget 5.2.4.7 Distributed will form the majority is allocated to control accounts and Distributed budget of budgets within the PMB. 5.2.4.8 Funding 5.2.4.6 Undistributed Budget Undistributed 5.2.4.6 scope of work, to a defined is identified PMB which within the UB is an amount but whic Earned Value Management: APM Guidelines APM Management: Value Earned ©Association for Project Management 2008 Process discussion 21 vities with duration spanning three or more vities with duration The method used is dependent on the type of method used is dependent on the type The hniques (EVTs). hieved, that proportion of the budget has been earned. This method This been earned. that proportion of the budget has hieved, Judgements have to be made every reporting cycle from analysis by the proj- analysis by from cycle reporting be made every to have Judgements Assignment of the EVT should be made at the work package level and consol- level package EVT should be made at the work Assignment of the some of the commonly used methods. It sections highlight following The the mile- the budget, and when milestone is assigned a proportion of Each ect team on aspects of achievement, risk status and work to complete. Short to complete. status and work risk on aspects of achievement, ect team but do not easier, of achievement the assessment will make packages work the work to shorten in job planning and scheduling breaks introduce arbitrary goal of EVM. the objectiveness as this goes against duration package value earned 5.2.5.1 Measuring as known value, or methods of measuring earned approaches are several There tec earned value of calculating earned value works best when there are a large number of fre- there are a large best when works of calculating earned value milestone completion. If the is only taken on quent milestones. Earned value becomes too coarse then the measuring process number of milestones is low, manager. and is no longer useful to the project complete 5.2.5.3 Percentage This in progress. assessment of work the CAM’s is determined by Earned value be applied to acti may technique for determining per- basis exists reporting periods and where an objective centage complete for the work package. units 5.2.5.4 Equivalent been method is based on measuring the number of units or items that have This items completed and comparing the result with the total number of units or to be completed. that have work being performed. Although a mixture of methods can be used on a single a mixture of methods can be used Although being performed. work assigned only a single method. Once can be or activity package project, a work the method should not be changed. has been opened, package the work Measurement of total project level. WBS and OBS up to the idated through the to support the EVT. level practicable performance should be taken at the lowest as long as they can be developed, methods should be remembered that hybrid is planned to be that the work of the way and representative are objective, undertaken. complete 5.2.5.2 Milestones of mile- the achievement is measured by package of the work Achievement stones. stone is ac ©Association for Project Management 2008 C) to the A ve a specific end result ve C/EAC BA 22 ACWP ACWP Table 5.1 provides examples of BCWP after examples of BCWP 5.1 provides Table BCWP BCWP calculations based on the formula method Table 5.1 Table MonthACWP 1EAC 200 1000 2 400 1000 700 1200 3 1000 1300 4 1400 1400 5 BCWP 200 400 583 769 1000 Since LoE earned value is measured by the passage of time, it is important to is measured by Since LoE earned value (CV), and recorded a cost variance can generate packages LoE work However, This approach is normally used in manufacturing, where the BCWP is the manufacturing, where used in is normally approach This This relies on a monthly update of the EAC to be accurate. It is useful in to be accurate. update of the EAC relies on a monthly This directly related to spend – progress can genuinely be situations where e.g. consumables, direct line feed. or product and are not directly related to the generation of a specific result or to the generation or product and are not directly related include some aspects of project activities of such examples product. Possible of these activities, many However, administration. management and contract should use the appor- management, and configuration e.g. quality assurance (section 5.2.5.7). technique tioned effort earned value of the baseline ensure that the time-phased budget distribution is representative set equal to the BCWS, is always of the BCWP the achievement Thus schedule. never variances means schedule This has not started. package if the work even schedule meaningful earned value and hence LoE tasks do not allow occur, analysis to be carried out. be meaningfully compared to the BCWP. can still ACWP 5.2.5.6 Level of effort of 5.2.5.6 Level are neces- which are those within a project packages of effort (LoE) work Level ha do not but which sary for the project to be successful, applying the formula method based on a BAC value of 1000 units. value on a BAC applying the formula method based EAC: measured as the number of units produced – as the number of measured of if large quantities for example, suited method is not particularly This produced. item are being a particular element. has a repetitive unless it activity to development method 5.2.5.5 Formula for low-value/non-critical performance formula method is used where The on the basis of actual direct cost categories can be earned material and other (B relationship of the budget at completion the cost, multiplied by Earned Value Management: APM Guidelines APM Management: Value Earned ©Association for Project Management 2008 Process discussion AF AF 0.33 ork package BCWS ork package 60 120 210 23 en by the base account. en by reference work package BCWP package work reference reference w reference actual cost incurred from accounting system actual cost incurred from accounting ACWP 0 30 70 120 250 ACWP 0 10 40 50 65 BCWP 0 0 60 120 210 Apportioned work package calculations based on AF kage. Actual costs are directly recorded and reported against the Actual costs are directly recorded 0.33 BCWP 0 0 20 40 70 ACWP ACWP ork pac Table 5.2 Table apportioned BCWS apportioned BCWP package AF package LoE work packages should be separately defined from other work packages to packages from other work defined be separately should packages LoE work no recovery where for those activities be used only should LoE technique The The use of apportioned effort is demonstrated in Table 5.2. Table in effort is demonstrated use of apportioned The Apportioned effort is normally used for tasks such as inspection (during man- as inspection is normally used for tasks such Apportioned effort calculated from the an apportioned factor (AF) is determined by Earned value Apportioned work BCWS 0 20 40 70 avoid distorting any earned value analysis. value earned any distorting avoid were not undertaken. the work be taken if action would effort 5.2.5.7 Apportioned pack- into short itself is not readily divisible is effort that by Apportioned effort progress within related to, and dependent upon measurable ages but is directly another w There is no similar apportionment of ACWP values for apportioned effort type for values ACWP of is no similar apportionment There packages. work work package, resulting in the generation of cost variances where they exist. where of cost variances resulting in the generation package, work Hence: The control account manager of the apportioned account still controls the control account The but the time-phasing of that budget and assignment of budget to the account, of earnings are driv the percentage ufacturing). The link between an apportioned account and a base account is a link between an apportioned account The ufacturing). is in the apportioned account that the schedule link: this means schedule of the base account, and the earnings schedule analogy to the work by derived accomplished analogy to the work by in the apportioned account are derived in the base account. BCWS apportioned The package. for the apportioned and reference work BAC the apportionment factor as applying by and apportioned BCWP is calculated follows: Reference work BCWS 0 ©Association for Project Management 2008 a collec- ork pack- dat The ve or financial events ve ati 24 his PMB forms the basis for measuring all future progress and per- his PMB forms the basis for measuring processes are concerned with ensuring that complete and accurate cost processes are concerned with ensuring that complete and accurate ages. control. Establish performance measurement baseline under configuration Identify master milestones and deliverables. and durations. with logic dependencies, activities/milestones Develop and planning packages. packages to work Group activities costs) to activi- other direct material, subcontracts, (labour, Apply resources ties. and planning packages the work Distribute the appropriate budget across contained within the control account. packages type for the w Determine and assign the appropriate earned value The plan should include all elements of the project. The PMB consists of an The all elements of the project. plan should include The should be used to record progress, not to update progress updates Periodic plan, should to an established additional plans, or significant changes Any system is to ensure that the baseline a proper management key to having The tion 7. COLLECTION 5.3 DATA What is the cost to the organisation of the project activities? formance, and consequently allows the project to be managed. the project formance, and consequently allows for all and EVTs schedules set of baseline data, including all DB, approved together with UB. and planning packages, packages work using and be actively All project team members should the plan. and change reporting against a common plan. a baseline plan. process before they become undergo a formal approval be achieved may This for the project. plan represents the authorised execution – baseline review (IBR) conducting an integrated by see section 6.1. 5.2.7 in planning activities Key 1. 2. 3. 4. 5. 6. (e.g. booking of actual costs or invoice payment). Therefore, BCWS should nor- Therefore, payment). costs or invoice (e.g. booking of actual should be and BCWP with a project event in accordance mally be scheduled be used may events or financial Administrative occurs. the event earned when occur in the same report- indicators such when events as indicators for contract events. ing period as the contract project the 5.2.6 Baselining and agreed as and stable, it is frozen sufficiently developed When the plan is T the PMB. 5.2.5.8 typesfor material items: value Earned element of other any is measured like for material measurement Earned value that reflect progress in to permit assessment of events cost. It is thus intended not measurement of administr project performance, Earned Value Management: APM Guidelines APM Management: Value Earned ©Association for Project Management 2008 Process discussion i.e. the correct numbering ACWP should be recorded in a man- ACWP 25 This section is concerned with the evaluation of the measured section is concerned with the evaluation This ANALYSIS, REVIEW AND ACTION ANALYSIS, erify actual costs to ensure only valid costs are booked to valid book- costs are booked to valid erify actual costs to ensure only valid ing/charge numbers. ing/charge system is set up (based upon the WBS) and correct booking/charge correct booking/charge WBS) and system is set up (based upon the to book to as required. numbers are available required to ensure that there are no Use the estimated actuals process as lag. due to payment variances V Ensure that procedures are in place to protect the integrity of bookings to Ensure that procedures are in place – accounts and soon packages/control work labour costs (direct costs and indirect costs); labour costs (direct direct expenses; material costs; done. costs of work subcontractor Ensure that BCWS, BCWP and ACWP are created in the same time frame. are created in the ACWP Ensure that BCWS, BCWP and not for material. It may measurement Section 5.2.5.8 discussed earned value during a period, it is recommended or mis-booked As costs can be transferred How well are we performing against the baseline plan, and what actions are and well are we performing against the baseline plan, How required? 5.4 2. 3. ner consistent with the budget and should include all expenditure. ner consistent with the budget and should in the same period that is claimed be possible to ensure that earned value use esti- to choose may the company actual costs are applied. In these cases, management system, and earned value mated actual costs (or accruals) in the the process, be in place to cover A procedure should the associated reports. ‘real’ costs. and the subsequent replacement with the period should calculations. Costs for costs be used in any that cumulative costs last between the cumulative therefore be calculated as the difference costs. period and the current cumulative 5.3.2. COLLECTION ACTIVITIES IN DATA KEY 1. information is collected in a timely manner to enable the transfer of actual cost of actual enable the transfer timely manner to is collected in a information system. management value into the earned information 5.3.1 and committed costs Measuring costs calculations include: value used in the earned ACWP The • • • • the cost elements that will identify be collected at a level Actual costs should to cost variance. and factors contributing ©Association for Project Management 2008 100 100 100 ACWP BCWS EAC (VAC/BAC) (VAC/BAC) y comparing how much time the much y comparing how (CV/BCWP) (SV/BCWS) BAC BCWP BCWP – far behind or an indication of how