San Francisco Bay Area Toll Seismic Retrofit and Regional Measure 1 Programs

2011 Second Quarter Project Progress and Financial Update

Released: August 2011

The First Back Span Catwalk Installed from the Tower of the Self- Anchored Suspension Bridge to the Deck below

A 4,000-Ton Crane Loads Roadway Box 14 West onboard Ship - The Last Steel Deck Voyage Table of Contents

Introduction 1 Summary Of Major Project Highlights, Issues, and Actions 2 Toll Bridge Seismic Retrofit Program Cost Summary 6 Toll Bridge Seismic Retrofit Program Schedule Summary 7 Regional Measure 1 Program Cost Summary 8 Regional Measure 1 Program Schedule Summary 9

Toll Bridge Seismic Retrofit Program (TBSRP) 11 -Oakland Bay Bridge Seismic Retrofit Strategy 12 San Francisco-Oakland Bay Bridge East Span Replacement Project Summary 14 Yerba Buena Island Detour (YBID) 15 Yerba Buena Island Transitions Structures (YBITS) 16 Self-Anchored Suspension (SAS) Bridge 18 SAS Construction Sequence 20 SAS Superstructure Fabrication Activities 22 SAS Superstructure Field Activities 25 SAS Superstructure Roadway and Tower Box Installation Activities 26 Skyway 30 Oakland Touchdown (OTD) 31 Other Contracts 32 Antioch Bridge Seismic Retrofit Project 34 Dumbarton Bridge Seismic Retrofit Project 36 Other Completed TBSRP Projects 38 TBSRP Risk Management Program Update 40 Program Funding Status 44 Quarterly Environmental Compliance Highlights 46

Regional Measure 1 Toll Bridge Program 49 Interstate 880/State Route 92 Interchange Reconstruction Project 50 Other Completed RM1 Projects 52

Appendices 55 Toll Bridge Program Oversight Committee

Map of Bay Area Toll

* The is owned and operated by the Golden Gate Bridge, Highway, and Transportation District.

xii 2011 Second Quarter Project Progress and Financial Update

Introduction

In July 2005, Assembly Bill (AB) 144 (Hancock) created the Toll Bridge Program Oversight Committee (TBPOC) to implement a project oversight and project control process for the new Benicia-Martinez Bridge and State Toll Bridge Seismic Retrofit Program projects. The TBPOC consists of the Director of Caltrans, the Executive Director of the Bay Area Toll Authority (BATA) and the Executive Director of the Transportation Commission (CTC). The TBPOC’s project oversight and control processes include, but are not limited to, reviewing bid specifications and documents, reviewing and approving significant change orders and claims in excess of $1 million (as defined by the Committee), and keeping the Legislature and others apprised of current project progress and status. In January 2010, Assembly Bill (AB) 1175 (Torlakson) amended the TBSRP to include the Antioch and Dumbarton Bridges seismic retrofit projects. The current Toll Bridge Seismic Retrofit Program is as follows:

Toll Bridge Seismic Retrofit Projects Seismic Safety Status Dumbarton Bridge Seismic Retrofit Construction Antioch Bridge Seismic Retrofit Construction San Francisco-Oakland Bay Bridge East Span Replacement Construction San Francisco-Oakland Bay Bridge West Approach Replacement Complete San Francisco-Oakland Bay Bridge West Span Seismic Retrofit Complete San Mateo-Hayward Bridge Seismic Retrofit Complete Richmond-San Rafael Bridge Seismic Retrofit Complete 1958 Carquinez Bridge Seismic Retrofit Complete 1962 Benicia-Martinez Bridge Seismic Retrofit Complete San Diego-Coronado Bridge Seismic Retrofit Complete Vincent Thomas Bridge Seismic Retrofit Complete

The New Benicia-Martinez Bridge is part of a larger program of toll-funded projects called the Regional Measure 1 (RM1) Toll Bridge Program under the responsibility of BATA and Caltrans. While the rest of the projects in the RM1 program are not directly under the responsibility of the TBPOC, BATA and Caltrans will continue to report on their progress as an informational item. The RM1 program includes:

Regional Measure 1 Projects Open to Traffic Status Interstate 880/State Route 92 Interchange Reconstruction Construction 1962 Benicia-Martinez Bridge Reconstruction Open New Benicia-Martinez Bridge Open Richmond-San Rafael Bridge Deck Overlay Rehabilitation Open Richmond-San Rafael Bridge Trestle, Fender & Deck Joint Rehabilitation Open Westbound Carquinez Bridge Replacement Open San Mateo-Hayward Bridge Widening Open State Route 84 Bayfront Expressway Widening Open Richmond Parkway Open

1 Toll Bridge Program Oversight Committee

SUMMARY OF MAJOR PROJECT HIGHLIGHTS, ISSUES, AND ACTIONS Toll Bridge Seismic Retrofit Program Risk Management A major element of the 2005 AB144, the law creating the TBPOC, was legislative direction to implement a more aggressive risk management program. Such a program has been implemented in stages over time to ensure development of a robust and comprehensive approach to risk management.

A comprehensive risk assessment is performed for each project in the program on a quarterly basis. Based upon those assessments, a forecast is developed using the average cost of risk. These forecasts can both increase and decrease as risks View of the SAS Back Span Catwalk Installed are identified, resolved or retired. Nonetheless, assurances have been made that the public is informed of the risks that have been identified and the possible expense they could necessitate.

As of the end of the second quarter of 2011, the 50 percent probable draw on program contingency (see graph on page 41) is $200 million. The potential draw ranges from $60 million to $300 million. The $308 million program contingency balance can be used to cover the costs of identified risks. In accordance with the approved TBSRP Risk Management Plan, risk mitigation actions are continuously developed and implemented to reduce the potential draw on the program contingency.

San Francisco-Oakland Bay Bridge (SFOBB) East Span Seismic Bike Path Installed on the Eastbound Self-Anchored Suspension Replacement Project Bridge SAS Superstructure Contract The prime contractor constructing the Self-Anchored Suspension (SAS) Bridge from the completed Skyway to Yerba Buena Island is a joint venture of American Bridge/Fluor (ABF). Significant progress is being made both in the Bay Area and around the world.

As of the end of June 2011, workers successfully hoisted the “world’s largest cable saddle” atop the Self-Anchored-Suspension (SAS) span’s tower. The structural elements of the main tower are now complete with the saddle in place. Just shy of its 525- foot apex, the signature tower will be crowned with a decorative head after the cable is installed early next year.

Roadway Box 12 West Being Lifted by the Shear-Leg Crane Barge

2 2011 Second Quarter Project Progress and Financial Update

The first 24 of 28 steel roadway boxes were installed as Yerba Buena Island Transition of the end of June 2011. The remaining four roadway boxes are in fabrication and are expected to ship in early Structures #1 Contract August 2011 and arrive in Oakland by early September. The YBITS#1 contract has been awarded to MCM Construction,Inc., the same contractor that completed These boxes, fabricated in Shanghai, China, join other the Oakland Touchdown (OTD) #1 contract. MCM bridge components that have been arriving from around mobilized in September 2010, and has had total the country and the world. All bridge components access to the area since October 1, 2010. The undergo a rigorous quality review by the fabricator, ABF, MCM contract includes completing the remaining and Caltrans to ensure that only bridge components that foundations and the bridge deck structure from the have been built in accordance to the specifications will Yerba Buena Island Tunnel to the Self-Anchored be shipped. The TBPOC‘s goal is to open the bridge to Suspension (SAS) bridge. traffic in both directions by December 2013. Work is focused on the westbound transition Yerba Buena Island Detour Contract structure’s substructure and superstructure from the tunnel to the Self-Anchored Suspension bridge as The YBI temporary detour structure contract was shown in the picture below. The first concrete pour on completed in October 2010. the westbound superstructure is scheduled for July 22, 2011.

Aerial View of YBITS #1 Westbound Falsework, Formwork and Installation in Progress and the Yerba Buena Island Detour Structure 3 Toll Bridge Program Oversight Committee

SUMMARY OF MAJOR PROJECT HIGHLIGHTS, ISSUES, AND ACTIONS

Oakland Touchdown #1 Contract The Oakland Touchdown (OTD) #1 contractor, MCM Construction, Inc. completed the work on June 8, 2010. The contract constructed the westbound approach from the toll plaza to the Skyway structure and the portion of the eastbound approach that is not in conflict with the existing bridge structure.

Oakland Detour The detour realigns the existing bridge approach to the south to allow for construction of the remaining portion of OTD #2 that was in conflict with the existing bridge. The eastbound detour was completed on May 30, 2011. The westbound detour is forecast to open at Oakland Detour - Work in Progress the beginning of spring 2012.

Oakland Touchdown #2 Contract The OTD #2 contract for construction will be advertised in October 2011 and awarded in April 2012.

Existing SFOBB Dismantling

To expedite opening of a new eastbound on ramp and the pedestrian/bicycle pathway from Yerba Buena Island, the TBPOC has decided to split the bridge dismantling project into at least two contracts. The dismantling of the superstructure of the main cantilever section of the existing bridge will be incorporated into the YBITS #2 contract, while the remaining portions of the existing bridge will be Oakland Detour - Relocated Eastbound Temporary Detour removed by separate contract or contracts yet to be determined.

Antioch Bridge Seismic Retrofit The major retrofit strategy for the bridge includes installing seismic isolation bearings at each of the 41 piers, strengthening piers 12 through 31 with steel cross-bracing between column bents and installing steel casings at all columns located at the Sherman Island approach slab bridge. See project progress on page 34.

Dumbarton Bridge Seismic Retrofit The Dumbarton bridge is a combination of three bridge types; reinforced concrete slab approaches supported on multiple pile extension columns, Dumbarton Bridge - Roughening Face of Existing Bent Cap precast - prestressed concrete girders, and steel box

4 2011 Second Quarter Project Progress and Financial Update

girders supported on reinforced concrete piers. The retrofit strategy for the bridge includes superstructure and deck modifications and installation of isolation bearings. See project progress on page 36.

TBSRP Capital Outlay Support The capital outlay support (COS) budget, originally established as a part of AB 144 in 2005, was based on a schedule that assumed bridge opening in 2012. After the SAS contract was rebid, interested contractors requested an additional year to be added to the schedule. To ensure a competitive bidding pool, the TBPOC changed the approved schedule to reflect bridge opening in 2013, but delayed increasing the COS budget to cover the project extension with Antioch Bridge - Cross Frames Installed between Bent Columns the belief that an accelerated early completion was still possible and that COS costs could be contained. Since that time, early completion has not materialized and the TBPOC has subsequently approved COS budget increases to be funded from the COS reserves set aside within the original program contingency for project extensions or delays. Opportunities to economize and reduce costs in this area will continue to be pursued. However, additional COS is forecast to be needed from the program contingency.

TBSRP Programmatic Risks This category includes risks that are not yet scoped within existing contracts and/or that spread across multiple contracts. The interdependencies between all of the contracts in the program result in the potential for one contract’s delay to impact the entire program Aerial View of the Dumbarton Bridge that are accounted for in the net programmatic risks.

Regional Measure 1 Toll Bridge Program (RM1) Interstate 880/State Route 92 Interchange Reconstruction Project The project is forecast to be substantially completed in September 2011 pending weather or unforeseen construction delays. Caltrans is scheduled to open the westbound 92 to 880 in August 2011.

92/880 NWCONN Bridge Construction

5 Toll Bridge Program Oversight Committee Toll Bridge Seismic Retrofit Program Cost Summary Contract AB 144/SB 66 TBPOC Current Cost to Date Current Cost Cost Cost Status Status Budget Approved TBPOC (June 2011) Forecast Variance (July 2005) Changes Approved (June 2011) Budget (June 2011)

a b c = a + b d e f = e - c

SFOBB East Span Seismic Replacement Capital Outlay Construction Skyway Completed 1,293.0 (38.9) 1,254.1 1,237.1 1,245.2 (8.9) SAS Marine Foundations Completed 313.5 (32.6) 280.9 274.8 278.6 (2.3) SAS Superstructure Construction 1,753.7 293.1 2,046.8 1,530.8 2,078.9 32.1 YBI Detour Completed 131.9 360.9 492.8 465.8 482.8 (10.0) YBI Transition Structures (YBITS) 299.3 (51.5) 247.8 43.0 305.1 57.3 YBITS 1 Construction 185.5 43.0 222.4 36.9 YBITS 2 Design 59.0 - 79.4 20.4 YBITS Landscaping Design 3.3 - 3.3 - Oakland Touchdown (OTD) 283.8 55.2 339.0 209.4 333.9 (5.1) OTD 1 Completed 212.0 202.9 203.3 (8.7) OTD 2 Design 62.0 - 58.6 (3.4) Detour Construction 51.0 - 58.0 7.0 OTD Electrical Systems Design 4.4 - 4.4 - Submerged Electric Cable Completed 9.6 6.5 9.6 - Existing Bridge Demolition Design 239.2 (0.1) 239.1 - 250.8 11.7 Stormwater Treatment Measures Completed 15.0 3.3 18.3 16.8 18.3 - Other Completed Contracts Completed 90.4 - 90.4 89.9 90.4 - Capital Outlay Support 959.3 218.0 1,177.3 965.5 1,275.8 98.5 Right-of-Way and Environmental Mitigation 72.4 - 72.4 51.7 80.4 8.0 Other Budgeted Capital 35.1 (3.3) 31.8 0.7 7.7 (24.1) Total SFOBB East Span Replacement 5,486.6 804.1 6,290.7 4,885.5 6,447.9 157.2 Antioch Bridge Seismic Retrofit Capital Outlay Construction and Mitigation Construction 70.0 70.0 25.6 56.9 (13.1) Capital Outlay Support 31.0 31.0 19.8 34.7 3.7 Total Antioch Bridge Seismic Retrofit - 101.0 101.0 45.4 91.6 (9.4) Dumbarton Bridge Seismic Retrofit Capital Outlay Construction and Mitigation Construction 92.7 92.7 13.2 88.8 (3.9) Capital Outlay Support 56.0 56.0 27.0 57.2 1.2 Total Dumbarton Bridge Seismic Retrofit - 148.7 148.7 40.2 146.0 (2.7) Other Program Projects 2,268.4 (64.6) 2,203.8 2,160.9 2,191.7 (12.1) Miscellaneous Program Costs 30.0 - 30.0 25.5 30.0 - Net Programmatic Risks - - - - 66.9 66.9 Program Contingency 900.0 (592.2) 307.8 - 107.9 (199.9) Total Toll Bridge Seismic Retrofit Program 2 8,685.0 397.0 9,082.0 7,157.5 9,082.0 -

Within approved schedule and budget Identified potential project risks that could significantly impact approved schedules and budgets if not mitigated Known project impacts with forthcoming changes to approved schedules and budgets 2 Figures may not sum up to totals due to rounding effects.

6 2011 Second Quarter Project Progress and Financial Update Toll Bridge Seismic Retrofit Program Schedule Summary AB144/SB TBPOC Current TBPOC Current Schedule Schedule Remarks/Notes 66 Project Approved Approved Completion Variance Status Completion Changes Completion Forecast (Months) Schedule (Months) Schedule (June 2011) Baseline (June 2011) (July 2005) g h i = g + h j k = j - i l

SFOBB East Span Seismic Replacement Contract Completion Skyway Apr 2007 8 Dec 2007 Dec 2007 - See Page 30 SAS Marine Foundations Jun 2008 (5) Jan 2008 Jan 2008 - See Page 18 SAS Superstructure Mar 2012 29 Aug 2014 Aug 2014 - See Page 19 YBI Detour Jul 2007 41 Dec 2010 Dec 2010 - See Page 15 YBI Transition Structures (YBITS) Nov 2013 12 Nov 2014 Mar 2015 4 See Page 16 YBITS 1 Sep 2013 Dec 2013 3 YBITS 2 Nov 2014 Mar 2015 4 YBITS Landscaping TBD TBD - Oakland Touchdown Nov 2013 12 Nov 2014 Nov 2014 - See Page 31 OTD 1 Jun 2010 Jun 2010 - OTD 2 Nov 2014 Nov 2014 - OTD Electrical Systems TBD TBD - Submerged Electric Cable Jan 2008 Jan 2008 - Existing Bridge Demolition Sep 2014 12 Sep 2015 Dec 2015 3 Stormwater Treatment Measures Mar 2008 Mar 2008 Mar 2008 - SFOBB East Span Bridge Opening and Other Milestones Westbound Seismic Safety Open Sep 2011 27 Dec 2013 Dec 2013 - Eastbound Seismic Safety Open Sep 2012 15 Dec 2013 Dec 2013 - Oakland Detour Eastbound Open May 2011 May 2011 - Oakland Detour Westbound Open Feb 2012 Feb 2012 - OTD Westbound Access Aug 2009 Aug 2009 - YBI Detour Open Sep 2009 Sep 2009 - See Page 15 Antioch Bridge Seismic Retrofit Contract Completion Aug 2012 May 2012 (3) See Page 34 Dumbarton Bridge Seismic Retrofit Contract Completion Sep 2013 Sep 2013 - See Page 36

7 Toll Bridge Program Oversight Committee

Regional Measure 1 Program Cost Summary Contract BATA BATA Current BATA Cost to Date Current Cost Cost Variance Cost Status Status Baseline Approved Approved (May 2011) Forecast Budget Changes Budget (June 2011) (July 2005) (June 2011)

a b c = a + b d e f = e - c

Interstate 880/Route 92 Interchange Reconstruction

Capital Outlay Construction Construction 94.8 68.4 163.2 130.7 163.2 -

Capital Outlay Support 28.8 35.8 64.6 59.2 64.6 -

Capital Outlay Right-of-Way 9.9 7.3 17.2 14.5 17.2 -

Project Reserve 0.3 (0.3) - - - - Total I-880/SR-92 Interchange - Reconstruction 133.8 111.2 245.0 204.4 245.0

Other Completed Program Projects 1,978.8 182.6 2,161.4 2,088.1 2,161.4 - Total Regional Measure 1 Toll Bridge - Program 1 2,112.6 293.8 2,406.4 2,292.5 2,406.4

Within approved schedule and budget Identified potential project risks that could significantly impact approved schedules and budgets if not mitigated Known project impacts with forthcoming changes to approved schedules and budgets 1 Figures may not sum up to totals due to rounding effects.

8 2011 Second Quarter Project Progress and Financial Update Regional Measure 1 Program Schedule Summary BATA Baseline BATA Approved Current BATA Current Schedule Schedule Remarks/Notes Completion Changes Approved Completion Variance Status Schedule (Months) Completion Forecast (Months) (July 2005) Schedule (June 2011) (June 2011)

g h i = g + h j k = j - i l

Interstate 880/Route 92 Interchange Reconstruction

Contract Completion Interchange Reconstruction Dec 2010 9 Sep 2011 Sep 2011 - See Page 50

9

East andWest andtheSkyway The Gapbetween theSelf-AnchoredSuspension BridgeBox12

TOLL BRIDGE SEISMIC RETROFIT PROGRAM Toll Bridge Program Oversight Committee

TOLL BRIDGE SEISMIC RETROFIT PROGRAM San Francisco-Oakland Bay Bridge Seismic Retrofit Strategy

When a 250-ton section of the upper deck of the East Span collapsed during the 7.1-magnitude Loma Prieta in 1989, it was a wake-up call for the entire Bay Area. While the East Span quickly reopened within a month, a critical question lingered: How could the Bay Bridge—a vital regional lifeline structure—be strengthened to withstand the next major earthquake? Seismic experts from around the world determined that to make each separate element seismically safe on a bridge of this size, the work must be divided into numerous projects. Each project presents unique challenges. Yet there is one common challenge — the need to accommodate the more than 280,000 vehicles that cross the bridge each day. West Approach Overview West Approach Seismic Replacement Project Project Status: Completed 2009

Seismic safety retrofit work on the West Approach in San Francisco, bounded on the west by 5th Street and on the east by the anchorage of the west span at Beale Street, involved completely removing and replacing this one-mile stretch of Interstate 80, as well as six on- and off-ramps within the confines of the West Approach’s original footprint. This project was completed on April 8, 2009.

West Span Seismic Retrofit Project Project Status: Completed 2004

The West Span lies between Yerba Buena Island and San Francisco and is made up of two complete suspension spans connected at a center anchorage. Retrofit work included adding massive amounts of steel and concrete to strengthen the entire West Span, along with new seismic shock absorbers and bracing.

San Francisco-Oakland Bay Bridge West Span

12 West Approach West Span 2011 Second Quarter Project Progress and Financial Update

East Span Seismic Replacement Project Project Status: In Construction

Rather than a seismic retrofit, the two-mile long East Span The new span will feature the world’s longest is being completely rebuilt. When completed, the new Self-Anchored Suspension (SAS) bridge that will East Span will consist of several different sections, but will be connected to an elegant roadway supported appear as a single streamlined span. The eastbound and by piers (Skyway), which will gradually slope westbound lanes of the East Span will no longer include down toward the Oakland shoreline (Oakland upper and lower decks. The lanes will instead be parallel, Touchdown). A new transition structure on Yerba providing motorists with expansive views of the bay. These Buena Island (YBI) will connect the SAS to the YBI views will also be enjoyed by bicyclists and pedestrians, Tunnel and will transition the East Span’s side- thanks to a new bike path on the south side of the bridge by-side traffic to the upper and lower decks of the that will extend all the way to Yerba Buena Island. The new tunnel and West Span. span will be aligned north of the existing bridge to allow traffic to continue to flow on the existing bridge as crews When construction of the new East Span has been build the new span. completed and vehicles have been safely rerouted to it, the original East Span will be demolished.

Architectural Rendering of the New East Span of the San Francisco-Oakland Bay Bridge

Yerba Buena Island Transition SAS Skyway Oakland Touchdown 13 Toll Bridge Program Oversight Committee

TOLL BRIDGE SEISMIC RETROFIT PROGRAM San Francisco-Oakland Bay Bridge East Span Replacement Project Summary

The new East Span bridge can be split into four major components—the Skyway and the Self-Anchored Suspension bridge in the middle and the Yerba Buena Island Transition Structures and Oakland Touchdown approaches at either end. Each component is being constructed by one to three separate contracts that have been sequenced together to reduce schedule risk.

Highlighted below are the major East Span contracts and their schedules. The letter designation before each contract corresponds to contract descriptions in the report.

Overview of the San Francisco-Oakland Bay Bridge East Span Construction Progress

14 West Approach West Span 2011 Second Quarter Project Progress and Financial Update TOLL BRIDGE SEISMIC RETROFIT PROGRAM San Francisco-Oakland Bay Bridge East Span Replacement Project Yerba Buena Island Detour (YBID)

As with all of the Bay Bridge’s seismic retrofit projects, crews must build the Yerba Buena Island Transition Structures (YBITS) without disrupting traffic. To accomplish this task, YBID eastbound and westbound traffic was shifted off the existing roadway and onto a temporary detour on Labor Day weekend 2009. Drivers will use this detour, just south of the original roadway, until traffic is moved onto the new East Span.

A YBID Contract Contractor: C.C. Myers, Inc. Approved Capital Outlay Budget: $492.8 M Status: Completed October 2010

This contract was originally awarded in early 2004 to construct the detour structure for the planned 2006 opening of the new East Span. Due to the re- advertisement of the SAS Superstructure contract in 2005 because of a lack of funding at the time, the bridge opening was rescheduled to 2013. To better integrate the contract into the current East Span schedule and to improve seismic safety and mitigate future construction risks, the TBPOC has approved a number of changes to the contract, including adding the deck replacement work near the tunnel that was rolled into place over Labor Day weekend 2007, advancing future transition structure foundation work and making design enhancements to the temporary detour structure. These changes have increased the budget and forecast for the YBI East Tie-In Rolled in on Labor Day 2009 Weekend contract to cover the revised project scope and reduce project risks.

Status: Completed.

West Tie-In Phase #1 Rolled in on Labor Day Weekend 2007

Yerba Buena Island Transition SAS Skyway Oakland Touchdown 15 Toll Bridge Program Oversight Committee

TOLL BRIDGE SEISMIC RETROFIT PROGRAM San Francisco-Oakland Bay Bridge East Span Replacement Project Yerba Buena Island Transition Structures (YBITS)

The new Yerba Buena Island Transition Structures (YBITS) will connect the new SAS bridge span to the existing Yerba Buena Island Tunnel, transitioning the new side-by-side roadway decks to the upper and lower decks of the tunnel. The new structures will be cast-in-place reinforced concrete structures that will look very similar to the already constructed Skyway structures. While some YBITS foundations and columns have been advanced by the YBID contract, the remaining work will be completed under three separate YBITS contracts.

B YBITS #1 Contract Contractor: MCM Construction, Inc. Approved Capital Outlay Budget: $185.5 M YBITS #1 Westbound Frame 2 Falsework, Formwork and Rebar Status: 24% Complete as of June 2011 Installation

The YBITS #1 contract will construct the mainline roadway structure from the SAS bridge to the YBI tunnel. On February 4, 2010, Caltrans awarded the YBITS #1 Contract to MCM Construction, Inc.

Status: Construction of the eastbound and westbound footings and columns were completed in June 2011. Work continues on frames 1 and 2 westbound formwork and rebar installation. The first concrete placement is scheduled for July 22, 2011.

Rendering of Overview of Future Yerba Buena Island Transition Structures in Progress (top) with Completed Detour Viaduct (bottom)

16 West Approach West Span 2011 Second Quarter Project Progress and Financial Update

YBITS #2 Contract YBITS Landscaping Contract Contractor: TBD Contractor: TBD Approved Capital Outlay Budget: $59.0 M Approved Capital Outlay Budget $3.3M Status: In Design Status: In Design

The YBITS #2 contract will demolish the detour viaduct Upon completion of the YBITS work, a follow-on after all traffic is shifted to the new bridge and will landscaping contract will be executed to replant and construct a new eastbound on-ramp to the bridge in landscape the area. its place. The new ramp will also provide the final link for bicycle/pedestrian access off the SAS bridge onto Yerba Buena Island. To expedite opening of a new eastbound on-ramp and the pedestrian/bicycle pathway from Yerba Buena Island, the TBPOC has decided to split the bridge dismantling project into at least two contracts. The dismantling of the superstructure of the main cantilever section of the existing bridge will be incorporated into the YBITS #2 contract, while the remaining portions of the existing bridge will be removed by separate contract or contracts yet to be determined.

Yerba Buena Island Transition Structures Advanced Work Due to the re-advertisement of the SAS superstructure contract in 2005, it became necessary to temporarily suspend the detour contract and make design changes to the viaduct. To make more effective use of the extended contract duration and to reduce overall project schedule and construction risks, the TBPOC approved the advancement of foundation and column work from the YBITS contract.

Status: The YBID contractor completed the YBITS advanced substructure work in October 2010.

Yerba Buena Island Transition Structures #1 Westbound Falsework, Formwork and Rebar Installation in Progress

Yerba Buena Island Transition SAS Skyway Oakland Touchdown 17 Toll Bridge Program Oversight Committee

TOLL BRIDGE SEISMIC RETROFIT PROGRAM

San Francisco-Oakland Bay Bridge East Span Replacement Project Self-Anchored Suspension (SAS) Bridge

If one single element bestows world class status on the new Bay Bridge East Span, it is the Self-Anchored Suspension (SAS) bridge. This engineering marvel will be the world’s largest SAS span at 2,047 feet in length, as well as the first bridge of its kind built with a single tower.

The SAS was separated into three separate contracts— construction of the land-based foundations and columns at pier W2; construction of the marine-based foundations and columns at piers T1 and E2; and construction of the SAS steel superstructure, including the tower, roadway, and cabling. Construction of the foundations at pier W2 and at piers T1 and E2 was completed in 2004 and 2007, respectively.

Aerial View of the Self-Anchored Suspension Bridge, the Tower and Back Span Catwalk Installed

SAS Land Foundation Contract C SAS Marine Foundations Contract Contractor: West Bay Builders, Inc. Contractor: Kiewit/FCI/Manson, Joint Venture Approved Capital Outlay Budget: $26.4 M Approved Capital Outlay Budget: $280.9 M Status: Completed October 2004 Status: Completed January 2008

The twin W2 columns on Yerba Buena Island Construction of the piers at E2 and T1 (see rendering provide essential support for the western end of the on facing page) required significant on-water resources SAS bridge, where the single main cable for the to drive the foundation support piles down, not only to suspension span will extend down from the tower bedrock, but also through the bay water and mud. and wrap around and under the western end of the roadway deck. Each of these huge columns required The T1 foundation piles extend 196 feet below the massive amounts of concrete and steel and are waterline and are anchored into bedrock with heavily anchored 80 feet into the island’s solid bedrock. reinforced concrete rock sockets that are drilled into the rock. Driven nearly 340 feet deep, the steel and concrete E2 foundation piles were driven 100 feet deeper than the deepest timber piles of the existing east span in order to get through the bay mud and reach solid bedrock.

18 West Approach West Span 2011 Second Quarter Project Progress and Financial Update

D SAS Superstructure Contract Contractor: American Bridge/Fluor Enterprises, Joint Venture Approved Capital Outlay Budget: $2.05 B Status: 73% Complete as of June 2011

The SAS bridge is not just another suspension bridge. The single-steel tower is made up of four separate Rising 525 feet above mean sea level and embedded in legs connected by shear link beams which function rock, the single-tower SAS span is designed to withstand much like a fuse in an electrical circuit. These beams a massive earthquake. Traditional main cable suspension will absorb most of the impact from an earthquake, bridges have twin cables with smaller suspender cables preventing damage to the tower legs. connected to them. While there will appear to be two main cables on the SAS, there will actually only be The next several pages highlight the construction a single continuous cable. This single cable will be sequence of the SAS and are followed by detailed anchored within the eastern end of the roadway, carried updates on specific construction activities. over the tower and then wrapped around the two side-by- side decks at the western end.

Pier E2

Pier T1 Pier W2

Architectural Rendering of New Self-Anchored Suspension Span and Skyway

Yerba Buena Island Transition SAS Skyway Oakland Touchdown 19 Toll Bridge Program Oversight Committee

TOLL BRIDGE SEISMIC RETROFIT PROGRAM Self-Anchored Suspension (SAS) Construction Sequence

STEP 1 - CONSTRUCT TEMPORARY SUPPORT STRUCTURES Temporary support structures will need to be erected from the Skyway to Yerba Buena Island to support the new SAS bridge during construction.

Status: Foundations and temporary support structures were completed in mid- September 2010.

Step 1

STEP 2 - INSTALL ROADWAYS The roadway boxes are being lifted into place by using the shear-leg crane barge. The boxes are being bolted and welded together atop the temporary support to form two continuous parallel steel roadway boxes. Status: Twenty-four of 28 roadway boxes have been erected. Seventeen crossbeams have been installed between the roadway boxes. Roadway boxes 13 and 14 east and west are in fabrication and are expected to ship in early August 2011. The bike Step 2 path deck service platforms and barrier installation continues on the eastbound roadway deck. STEP 3 - INSTALL TOWER Each of the four legs of the tower will be erected in four separate lifts. The four tower lifts, the grillage and the tower head will be installed using a temporary erection tower and lifting jacks.

Status: The tower and saddle have been installed and the tower head will be erected after the cables have been installed in early 2012.

Step 3

20 West Approach West Span 2011 Second Quarter Project Progress and Financial Update

STEP 4 - MAIN CABLE AND SUSPENDER INSTALLATION The main cable will be pulled from the east end of the SAS bridge, over the tower, and wrapped around pier W2 before returning back over the tower to the east end of the SAS bridge deck. Suspender cables will be added to lift the roadway decks off the temporary support structure.

Status: Cable installation is pending the erection of the cable temporary works and completion of roadway spans. All cables Step 4 have been fabricated, shipped and stored in the warehouse at Pier 7 in Oakland. Temporary catwalks are being installed from the tower to the deck to provide safe access for workers who will be installing the main cable.

STEP 5 - WESTBOUND AND EASTBOUND SEISMIC SAFETY OPENING The new bridge will now open simultaneously in both the westbound and eastbound directions.

Status: The westbound and eastbound opening is forecast for December 2013.

Step 5

Aerial View of Current Progress on the Self-Anchored Suspension Bridge

Yerba Buena Island Transition SAS Skyway Oakland Touchdown 21 Toll Bridge Program Oversight Committee

Self-Anchored Suspension (SAS) Superstructure Fabrication Activities Roadway and Tower Segments Like giant three-dimensional jigsaw puzzles, the roadway and tower lifts of the SAS bridge are hollow steel shells that are internally strengthened and stiffened by a highly engineered network of welded steel ribs and diaphragms. The use of steel in this manner allows for a strong and yet relatively light and flexible structure to withstand the massive loads placed on the bridge during seismic events.

All components undergo a rigorous quality review by ZPMC, ABF, and Caltrans to ensure that only bridge components that have been built according to contract specifications will be shipped.

Roadway Box Fabrication Status: As shown in the diagram to the right, roadway boxes 1 through 12 east and west have been completed. Fabrication of roadway boxes 13 and 14 east and Loading Roadway Box 14 West onto the Ship - the Last Steel west is ongoing. The roadway boxes are forecast Segment Voyage to be shipped in August 2011.

Tower Fabrication Status: The tower was completed in June 2011. The tower head was fabricated and shipped in May 2011.

Legend Shop Drawings Underway Sub-Assemblies Fabrication Segment Assembly Blast, Paint & Fit Up Ready To Ship/In Transit On Site/In Place Through June 30, 2011

Roadway Box 14 West Being Loaded onto Ship

22 West Approach West Span 2011 Second Quarter Project Progress and Financial Update

Fabrication Progress Diagram Through June 30, 2011

N

W E

Loading Roadway Box 14 West onto the Ship

Loading Roadway Box 14 West onto the Ship - the Last Steel Voyage

Yerba Buena Island Transition SAS Skyway Oakland Touchdown 23 Toll Bridge Program Oversight Committee

TOLL BRIDGE SEISMIC RETROFIT PROGRAM Self-Anchored Suspension (SAS) Superstructure Fabrication Activities (cont.)

Cables and Suspenders Status: The cable and jacking saddles and pipe beams have been fabricated and installed. Hinge A seismic One continuous main cable will be used to support expansion joint is in fabrication and is currently scheduled the roadway deck of the SAS bridge. The main for completion in December 2011. Some of the SAS cable will be anchored within the westbound traveler rails and bike path decks have been fabricated roadway box at the east end of the SAS near pier and installed and forecast for completion in September E2, then extend west over the northeast saddle 2011. The anchor rods are in fabrication and are forecast towards the tower saddle at T1. It will then loop for completion in August 2011. around pier W2 westbound deviation saddle, extend through the jacking beam saddle and extend around the eastbound deviation saddle at W2 over the tower saddle at T1 again to the south east saddle and finally anchor within the eastbound roadway box near pier E2. The main cable is made up of 137 bundles of wire strands and a number of smaller suspender ropes will connect the roadway decks to the main cable.

Status: All main cables strands have been fabricated and delivered to the job site and stored at Pier 7 in Oakland. The cable bands are in fabrication and forecast to be completed in August 2011. The suspender ropes are in fabrication and forecast to be completed in September 2011.

Saddles, Bearings, Hinges, and Other Bridge Components The mounts on which the main cable and suspender ropes will sit are solid steel castings. Castings for the main cable saddles were made by Japan Steel Works, while the cable bands and brackets are being made by Goodwin Steel in the United Kingdom. Cable Bands Ready for Painting

The bridge bearings and hinges that support, connect, and transfer loads from the Self-Anchored Suspension (SAS) Span to the adjoining sections of the new east span are being fabricated in a number of locations. Work on the bearings is being performed in Pennsylvania, USA and Hochang, South Korea, while hinge pipe beams are being fabricated in Oregon, USA.

Sample of Cable Band Compaction Testing Performed at Pier 7 in Oakland

24 West Approach West Span 2011 Second Quarter Project Progress and Financial Update

TOLL BRIDGE SEISMIC RETROFIT PROGRAM Self-Anchored Suspension (SAS) Superstructure Field Activities

Shear-Leg Crane Barge The massive shear-leg barge crane that is helping to build the SAS superstructure arrived in the on March 12, 2009 after a trans- Pacific voyage.

The crane and barge are separate units operating as a single entity named the “Left Coast Lifter.” The 400-by-100-foot barge is a U.S-flagged vessel that was custom built in Portland, Oregon by U.S. Barge, LLC and outfitted with the crane by Shanghai Zhenhua Heavy Industry Co. Ltd. (ZPMC) at a facility near Shanghai, China. The crane’s boom weighs 992 tons and is 328 feet long. The crane can lift up Shear-Leg Crane Barge in Process of Lifting Roadway Box 11 to 1,873 tons, including the deck and tower boxes for West the SAS.

Status: The shear-leg crane barge arrived at the job site March 2009. The crane has off-loaded and placed all temporary support structures and SAS roadway boxes and crossbeams.

Temporary Support Structures To erect the roadway decks and tower of the bridge, temporary support structures were first put in place. Almost a bridge in itself, the temporary support structures stretch from the end of the completed Skyway back to Yerba Buena Island. For the tower, a strand jack system is being built into the tower’s temporary frame to elevate the upper sections of the tower into place. These temporary supports are being fabricated in the Bay Area, as well as in Oregon and Temporary Support Structures with E2 Cap Beam and Completed in China at ZPMC. Skyway in background Status: The temporary support structures were completed in mid-September 2010.

Cap Beams Construction of the massive steel-reinforced concrete cap beams that link the columns at piers W2 and E2 are the responsibility of the SAS superstructure contractor and represents the only concrete portions of work on that contract. The east and west ends of the SAS roadway will rest on the cap beams and the main cable will wrap around pier W2, while anchoring into the east end of the SAS deck sections near E2.

Status: Completed in March 2009

Pier W2 and Hinge K and West Deviation Saddle on left and YBITS #1 on right

Yerba Buena Island Transition SAS Skyway Oakland Touchdown 25 Toll Bridge Program Oversight Committee

TOLL BRIDGE SEISMIC RETROFIT PROGRAM Self-Anchored Suspension (SAS) Superstructure Roadway and Tower Box Installation Activities Upon arrival in Oakland, the steel roadway and tower Status: Twenty-four of 28 roadway boxes have been sections are off-loaded directly from the transport ship erected to form a continuous roadway. Painting, onto barges to await installation atop the temporary welding and bolting continues on all roadway boxes. support structures. Steel roadway boxes will be installed All four tower legs along with the tower grillage and from west to east. Due to the shallow waters near Yerba the tower saddle have been installed as of mid-May Buena Island, the eastbound lanes on the south side of 2011. The tower head and roadway boxes 12 east the new bridge will be installed first, then to be followed and west arrived at Pier 7 in Oakland on June 3, by the westbound lanes. In total, there are 28 roadway 2011. Both boxes were lifted into place by the end of boxes (14 in each direction) that range from 560 to 1660 June 2011. tons and from 80 to 230 feet long.

The tower comprises four legs, each made up of four tower lifts that make up the majority of the height of the tower, the tower grillage, and finally the tower head.

26 West Approach West Span 2011 Second Quarter Project Progress and Financial Update

The Tower Saddle Being Installed atop the Tower of the Self-Anchored Suspension Bridge

Yerba Buena Island Transition SAS Skyway Oakland Touchdown 27 Aerial View of the Self-Anchored Suspension Bridge with the Newly Installed Back Span Catwalk Self-Anchored Suspension Bridge Tower Grillage Being Prepared for Assembly with Tower Saddle Toll Bridge Program Oversight Committee

TOLL BRIDGE SEISMIC RETROFIT PROGRAM San Francisco-Oakland Bay Bridge East Span Replacement Project Skyway

The Skyway, which comprises much of the new East Span, will drastically change the appearance of the Bay Bridge. Replacing the gray steel that currently cages drivers, a graceful, elevated roadway supported by piers will provide sweeping views of the bay.

E Skyway Contract Contractor: Kiewit/FCI/Manson, Joint Venture Approved Capital Outlay Budget: $1.25 B Status: Completed March 2008

Extending for more than a mile across Oakland mudflats, the Skyway is the longest section of the East Span. It sits between the new Self-Anchored Suspension (SAS) span and the Oakland Touchdown. In addition to incorporating the latest seismic-safety technology, the side-by-side roadway decks of the Skyway feature shoulders and lane widths built to modern standards.

The Skyway’s decks are composed of 452 pre-cast concrete segments (standing three stories high), containing approximately 200 million pounds of structural steel, 120 million pounds of reinforcing steel, 200 thousand linear feet of piling and about 450 thousand cubic yards of concrete. These are the largest segments of their kind ever cast and were lifted into place by custom-made winches.

The Skyway marine foundation consists of 160 hollow steel pipe piles measuring eight feet in diameter and dispersed among 14 sets of piers. The 365-ton piles were driven more than 300 feet into the deep bay mud. The new East Span piles were battered or driven in at an angle, rather than vertically, to obtain maximum strength and resistance.

Designed specifically to move during a major earthquake, the Skyway features several state-of-the-art seismic safety innovations, including 60-foot-long hinge pipe beams. These beams will allow deck segments on the Skyway to move, enabling the deck to withstand greater motion and to absorb more earthquake energy. Overview of the Skyway Looking East toward Oakland

30 West Approach West Span 2011 Second Quarter Project Progress and Financial Update

TOLL BRIDGE SEISMIC RETROFIT PROGRAM San Francisco-Oakland Bay Bridge East Span Replacement Project Oakland Touchdown

When completed, the Oakland Touchdown (OTD) G Oakland Detour structures will connect Interstate 80 in Oakland to the Contractor: MCM Construction, Inc. new side-by-side decks of the new East Span. For Approved Capital Outlay Budget: $51.0 M westbound drivers, the OTD will be their introduction to the graceful new East Span. For eastbound drivers from Status: In Construction San Francisco, this section of the bridge will carry them To ensure a simultaneous eastbound and westbound from the Skyway to the East Bay, offering unobstructed opening of the bridge by December 2013, the views of the Oakland hills. TBPOC has approved an acceleration plan that will construct a detour at the Oakland end of the bridge The Oakland Touchdown (OTD) approach structures to allow for expedited construction of the OTD #2 to the Skyway will be constructed in three phases. The contract. The detour realigns the existing bridge first phase, constructed on the OTD#1 contract, built the approach to the south to allow for construction of the new westbound approach structure. Due to physical remaining portion of OTD that was in conflict with the constraints with the existing bridge, OTD#1 was only existing bridge. able to construct a portion of the eastbound approach. To facilitate opening the bridge in both directions at the Status: The eastbound detour opened over the same time, the current phase of work, performed by 2011 Memorial Day weekend. The westbound the Oakland Detour contractor, is widening the upper detour construction is in progress and is forecast deck of the Oakland end of the existing bridge to allow to be completed in early 2012 pending weather or for a traffic shift to the north that removes the physical construction delays. The Burma Road extension constraint to completing the eastbound structure. The access and the eastbound detour were completed in third phase, to be constructed by a future OTD#2 May 2011. contract, will complete the eastbound lanes and provide the traffic switch to the new structure in both directions. This will allow the bridge to open simultaneously in both H Oakland Touchdown #2 Contract directions. Contractor: TBD Approved Capital Outlay Budget: $62.0 M F Oakland Touchdown #1 Contract Status: In Design Contractor: MCM Construction, Inc. Approved Capital Outlay Budget: $212.0 M The OTD #2 contract will complete the eastbound Status: Completed June 2010 approach structure from the end of the Skyway to Oakland. This work is critical to the eastbound opening of the new bridge by December 2013. The OTD #1 contract constructed the entire 1,000-foot- long westbound approach from the toll plaza to the Status: The TBPOC has approved an acceleration Skyway. When open to traffic, the westbound approach plan that will construct a detour at the Oakland end structure will provide direct access to the westbound of the bridge to allow for expedited construction of Skyway. In the eastbound direction, the contract will the OTD #2 contract. OTD #2 is currently in design construct a portion of the eastbound structure and all of and the contract for construction will be advertised in the eastbound foundations that are not in conflict with the October 2011 and awarded in April 2012. existing bridge.

Status: MCM Construction, Inc. completed OTD #1 westbound and eastbound phase 1 on June 8, 2010.

Yerba Buena Island Transition SAS Skyway Oakland Touchdown 31 Toll Bridge Program Oversight Committee

TOLL BRIDGE SEISMIC RETROFIT PROGRAM San Francisco-Oakland Bay Bridge East Span Replacement Project Other Contracts

A number of contracts needed to relocate utilities, clear areas of archeological artifacts, and prepare areas for future work have already been completed. The last major contract will be the eventual demolition and removal of the existing bridge, which by that time will have served the Bay Area for nearly 80 years. Following is a status of some the other East Span contracts.

East Span Interim Seismic Retrofit Contractors: 1) California Engineering 2) Balfour Beatty Approved Capital Outlay Budget: $30.8 M

Status: Completed October 2000 Archeological Investigations

After the 1989 Loma Prieta Earthquake, and before the final retrofit strategy was determined for the East Span, Caltrans completed an interim retrofit of the existing bridge to prevent a catastrophic collapse of the bridge should a similar earthquake occur before the East Span was completely replaced. The interim retrofit was performed under two separate contracts that lengthened pier seats, added some structural members, and strengthened areas of the bridge so they would be more resilient during an earthquake.

Stormwater Treatment Measures Contractor: Diablo Construction, Inc. Existing East Span of the San Francisco-Oakland Bay Bridge Approved Capital Outlay Budget: $18.3 M Status: Completed December 2008

The Stormwater Treatment Measures contract implemented a number of best practices for the management and treatment of stormwater runoff. Focused on the areas around and approaching the toll plaza, the contract added new drainage and built new bio-retention swales and other related constructs.

Stormwater Retention Basin

32 West Approach West Span 2011 Second Quarter Project Progress and Financial Update

Yerba Buena Island Substation Contractor: West Bay Builders Approved Capital Outlay Budget: $11.6 M Status: Completed May 2005

This contract relocated an electrical substation just east of the Yerba Buena Island Tunnel in preparation for the new East Span.

Pile Installation Demonstration Contractor: Manson and Dutra, Joint Venture Approved Capital Outlay Budget: $9.3 M New YBI Electrical Substation Status: Completed December 2000

While large-diameter battered piles are common in offshore drilling, the new East Span is one of the first J Electrical Cable Relocation bridges to use them in its foundations. To minimize Contractor: Manson Construction project risks and build industry knowledge, a pile installation demonstration project was initiated to Approved Capital Outlay Budget: $9.6 M prove the efficacy of the proposed technology and Status: Completed January 2008 methodology. The demonstration was highly successful and helped result in zero contract change orders or claims for pile driving on the project. A submerged cable from Oakland that is close to where the new bridge will touch down supplies electrical power to Treasure Island. To avoid any I Existing Bridge Demolition possible damage to the cable during construction, two new replacement cables were run from Oakland to Contractor: TBD Treasure Island. The extra cable was funded by the Approved Capital Outlay Budget: $239.1 M Treasure Island Development Authority. Status: In Design

Design work on the demolition of the existing bridge has started. The current plan is to complete the environmental clearance by December 2011 and obtain all permits by June 2012. To expedite opening of a new eastbound on-ramp and the pedestrian/bicycle pathway from Yerba Buena Island, the TBPOC has decided to split the bridge dismantling project into at least two contracts. The dismantling of the superstructure of the main cantilever section of the existing bridge will be incorporated into the YBITS #2 contract, while the remaining portions of the existing bridge will be removed by separate contract or contracts yet to be determined.

Yerba Buena Island Transition SAS Skyway Oakland Touchdown 33 Toll Bridge Program Oversight Committee

TOLL BRIDGE SEISMIC RETROFIT PROGRAM Antioch Bridge Seismic Retrofit Project Contractor: California Engineering Contractors, Inc. Approved Capital Outlay Budget: $70.0 M Status: 61% Complete as of June 2011

Serving the Delta region of the Bay Area, the Antioch Bridge takes State Route 160 traffic over the San Joaquin River, linking eastern Contra Costa County with Sacramento County. The current 1.8-mile-long steel plate girder bridge was opened in 1978 with one lane in each direction. The major retrofit measure for the bridge includes installing seismic isolation bearings at each of the 41 piers, strengthening piers 12 through 31 with steel cross-bracing between column bents, and installing steel casings at all columns located at the Sherman Island approach slab bridge.

Status: Fabrication and testing of all isolation bearings has been completed. Of the 82 isolation bearings, 36 have been installed at 18 of the 41 piers.

Fabrication of the cross bracing to be installed between the two column bents is 70 percent completed, (a total of 20 piers are to be retrofitted with cross bracing). Eight Down Holes Being Drilled for Seismic Monitoring Devices up to 250 Feet Below Grade pier cross frame retrofits have been installed, or 40 percent complete. Field painting of the cross bracing is the last major activity in completing the pier retrofit. Three of the 20 cross frames, or 15 percent of the total have been painted.

Fabrication of the column casing to be installed at the Sherman Island has been completed and delivered to the site. Column casing installation is scheduled to start late in the third quarter or beginning of the fourth quarter of 2011.

Application of Final Paint Coat at Cross Frames

34 2011 Second Quarter Project Progress and Financial Update

Installation of Access Scaffolding at Pier 14 35 Toll Bridge Program Oversight Committee

Dumbarton Bridge Seismic Retrofit Project Contractor: Shimmick Construction Company, Inc. Approved Capital Outlay Budget: $92.7 M Status: 22% Complete as of June 2011 The current Dumbarton Bridge was opened to traffic in 1982 linking the cities of Newark in Alameda County and East Palo Alto in San Mateo County. The 1.6-mile long bridge has six lanes (three in each direction) and an eight-foot bicycle/pedestrian pathway. The bridge is a combination of three bridge types; reinforced concrete slab approaches supported on multiple pile extension columns, precast-prestressed concrete delta girders and steel box girders supported on reinforced concrete piers. The current retrofit strategy for the bridge includes superstructure and deck modifications and installation of isolation bearings.

Status: The main bridge structure between piers 16 - 31 will be raised approximately five inches so the isolation bearings can be installed to separate the superstructure from the substructure during seismic events. In preparation, the bridge piers are being widened with reinforced concrete to accommodate the new bearings. Currently at piers 17 through 22, new reinforcing steel is being bonded and added to the piers. Dumbarton Bridge

Along the reinforced concrete slab approaches, the bent caps are being extended and tied to new 48” diameter steel piles that have been installed to strengthen the bridge. Bent cap extensions along the west trestle approach are completed and all east approach trestle bent columns have been constructed. The remaining reinforced concrete bent cap extensions at the east approach trestle are being formed and will be cast in concrete in July 2011.

Placement of Reinforcing Steel at Pier 17 Bent

36 2011 Second Quarter Project Progress and Financial Update

Forms in Place for Pump Station Walls

Core Drilling Operation Will Allow for Reinforcing Steel to Anchor into the Existing Bent Cap

37 Toll Bridge Program Oversight Committee

TOLL BRIDGE SEISMIC RETROFIT PROGRAM Other Completed Projects

In the 1990s, the State Legislature identified seven of the nine state-owned toll bridges for seismic retrofit. In addition to the San Francisco-Oakland Bay Bridge, these included the Benicia-Martinez, Carquinez, Richmond- San Rafael and San Mateo-Hayward bridges in the Bay Area, and the Vincent Thomas and Coronado bridges in Southern California. Other than the East Span of the Bay Bridge, the retrofits of all of the bridges have been completed as planned.

San Mateo-Hayward Bridge Seismic Retrofit Project Project Status: Completed 2000 High-Rise Section of San Mateo-Hayward Bridge

The San Mateo-Hayward Bridge seismic retrofit project focused on strengthening the high-rise portion of the span. The foundations of the bridge were significantly upgraded with additional piles.

1958 Carquinez Bridge Seismic Retrofit Project Project Status: Completed 2002

The eastbound 1958 Carquinez Bridge was retrofitted in 2002 with additional reinforcement of the cantilever thru- structure.

1958 Carquinez Bridge (foreground) with the 1927 Span (middle) under Demolition and the New Alfred Zampa Memo- 1962 Benicia-Martinez Bridge Seismic rial Bridge (background) Retrofit Project Project Status: Completed 2003

The southbound 1962 Benicia-Martinez Bridge was retrofitted to “Lifeline” status with the strengthening of the foundations and columns and the addition of seismic bearings that allow the bridge to move during a major seismic event. The Lifeline status means the bridge is designed to sustain minor to moderate damage after a seismic event and to reopen quickly to emergency response traffic.

1962 Benicia-Martinez Bridge (right)

38 2011 Second Quarter Project Progress and Financial Update

Richmond-San Rafael Bridge Seismic Retrofit Project Project Status: Completed 2005

The Richmond-San Rafael Bridge was retrofitted to a “No Collapse” classification to avoid catastrophic failure during a major seismic event. The foundations, columns, and truss of the bridge were strengthened, and the entire low-rise approach viaduct from Marin County was replaced.

Richmond-San Rafael Bridge Los Angeles-Vincent Thomas Bridge Seismic Retrofit Project Project Status: Completed 2000

The Vincent Thomas Bridge is a 1,500-foot long suspension bridge crossing the Los Angeles Harbor in Los Angeles that links San Pedro with Terminal Island. The bridge was one of two state-owned toll bridges in Southern California (the other being the San Diego-Coronado Bridge). Opened in 1963, the bridge was seismically retrofitted as part of the TBSRP in 2000.

Los Angeles-Vincent Thomas Bridge San Diego-Coronado Bridge Seismic Retrofit Project Project Status: Completed 2002

The San Diego-Coronado Bridge crosses over San Diego Bay and links the cities of San Diego and Coronado. Opened in 1969, the 2.1-mile long bridge was seismically retrofitted as part of the TBSRP in 2002.

San Diego-Coronado Bridge

39 Toll Bridge Program Oversight Committee

TOLL BRIDGE SEISMIC RETROFIT PROGRAM Risk Management Risk Management Program Update P lan n in g Potential Draw On Program Reserve (Program Contingency)

Assembly Bill (AB) 144 provides that Caltrans “regularly R isk reassess its reserves for potential claims and unknown Id entifica tion risks, incorporating information related to risks identified g in r and quantified through its risk assessment processes.” l R o Q t o i i r s u n t k n a o l o A i AB 144 set a $900 million Program Reserve (also M t C n a k a t i s & l v referred to as the program contingency). On October 11, i y e R s i 2009, Governor Schwarzenegger approved Assembly s Bill No. 1175 that added the Dumbarton and Antioch C yclic Bridges to the Toll Bridge Seismic Retrofit Program and this resulted in changes to program contingency. The R i sk e program contingency is currently $308 million according iv P R at is la e it s to the TBPOC approved budget. n sp t ly n o an na in n u A g s Q k e is The approved TBSRP Risk Management Plan provides R for the determination of the estimated potential draw on program contingency each quarter based on the total of all risks and the contingencies remaining from the contracts. Each contract in design has an assigned risk mitigation actions are continuously developed and contingency allowance. Each contract in construction implemented to reduce the potential draw on the program has a remaining contingency, which is the difference contingency. between its budget and the sum of bid items, state- furnished materials, contract change orders and RISK MANAGEMENT DEVELOPMENTS remaining supplemental work. Capital outlay support has no identified contingency allowance. The total of the There was an approximate $45 million decrease in the contingencies is the amount that is available to cover 50% probable remaining Program Contingency Balance the risks of all contracts, program-level risks (the risks (i.e., the approved TBPOC Program Contingency not assigned to a particular contract), and capital outlay Balance less the 50% Probable Draw) this quarter. This support risks. The amount by which the sum of all risks change is predominantly attributed to the approximate may exceed the total of all contingencies would represent $40 million decrease in the dismantling project a potential draw on the program contingency (i.e., contingency this quarter – this resulted from an increase program reserve). in the dismantling project’s cost estimate associated with proposed schedule compression, as well as a better The approved TBSRP Risk Management Plan provides understanding of the estimated costs associated with for the determination of the estimated potential draw marine access. The addition of the dismantling project’s on program contingency each quarter, and compares it cost risk numbers this quarter did not significantly to the current balance in the program contingency. The change the total dismantling project’s forecast because second quarter of 2011 potential draw curve is shown in of identified capital outlay support opportunities also Figure 1. quantified this quarter.

As of the end of the second quarter of 2011, the 50 Outside of the dismantling project, the decrease in percent probable draw on program contingency is $200 program cost risks this quarter were largely offset by million. The potential draw ranges from about $60 million the increase in costs carried in the program’s Contract to $300 million. Change Order (CCO) logs. Cost risks on the SAS contract trended downward this quarter, however, the The current program contingency balance is sufficient to forecast for the SAS did not change significantly as a cover the cost of currently identified risks. In accordance result of the approximate increase of $15 million in scope with the approved TBSRP Risk Management Plan, changes/enhancements approved by the TBPOC this

40 2011 Second Quarter Project Progress and Financial Update

quarter. Additional scope changes/enhancements (e.g., Right-of-way acquisition risks, the largest risks early in schedule compression of the dismantling project) are the Oakland Detour project, were successfully resolved being considered by the TBPOC and, if approved, will be by the project team, allowing the eastbound detour to reflected in the future quarters’ potential draw to program open on time. Construction of the westbound detour contingency curve. widening structure foundations began immediately after traffic was switched to the eastbound detour. The design The SAS contractor’s updated schedule meets the of the superstructure is advancing and will be completed TBPOC’s milestones for opening the bridge in 2013. by the end of this year. However, the contractor’s schedule does not incorporate a milestone for turning over the Hinge K work area to RISK MANAGEMENT LOOK AHEAD the YBITS #1 contractor for completion of the Hinge K closures. This potentially places the YBITS #1 contract on The corridor schedule is aggressive and there are the critical path to bridge opening, possibly extending it risks to the future activities on the critical paths through by several months. The risk management team mitigated SAS orthotropic box girder delivery and erection, cable this schedule risk by re-sequencing some SAS contract installation, load transfer, and completion of mechanical, activities to after bridge opening. Discussions are electrical, and plumbing systems required for the bridge ongoing to resolve this coordination issue between the opening. Caltrans and the SAS and YBITS#1 contractors SAS and YBITS #1 contractors, and the goal is to merge are implementing a plan to enhance mutual schedule the construction activities of both contracts into one management in order to proactively identify impending schedule and use it to plan the work to provide bridge risks so that action can be taken swiftly to prevent or opening as soon as possible. mitigate potential delays. The risk management team has

Figure 1 – Potential Draw on Program Contingency* *Figure 1 Notes: 1. The Program Contingency is currently $308 million per the TBPOC Approved Budget. 2. Program Contingency may be used for other beneficial purposes than to cover risks. 3. Potential risks associated with potential out-of-scope corridor improvements are excluded. Proposed architectural enhancements and project improvements are currently under development; such proposals are excluded unless approved by the TBPOC. 4. The potential draw chart should not be construed as a forecast of the future balance of Program Contingency funds. 41 Toll Bridge Program Oversight Committee

TOLL BRIDGE SEISMIC RETROFIT PROGRAM Risk Management Program Update (cont.) assessed the risks and identified Caltrans activities The comprehensive quantitative cost and schedule that must align with the SAS and YBITS#1 contractors’ risk assessment will be refined next quarter and incentivized milestone. incorporated in the program’s quantitative cost and schedule results. The San Francisco Ramps project is scheduled to start while the YBITS#1 contractor is working on Yerba Buena Island, giving rise to coordination issues such as slope stability, traffic maintenance, and conflicts in schedule and staging. Discussions are ongoing to resolve these potential issues.

Aggressive planning for the future East Span dismantling work is underway. Project scope is being refined and an assessment to select the most prudent and efficient procurement strategy for the dismantling work is being performed. Development of project plans, specifications, schedule, and cost is ongoing. In concert with this effort, the risk management team will be updating the risk registers for the dismantling work.

SAS Looking Down at the Top of the Level 1 Tower Shafts

Aerial View of the Westbound Yerba Buena Island Transition Structure alongside the Existing Detour

42 Overview of Yerba Buena Island Transition Structure Westbound and the Self-Anchored Suspension Bridge Span Toll Bridge Program Oversight Committee

TOLL BRIDGE SEISMIC RETROFIT PROGRAM Program Funding Status

AB 144 established a funding level of $8.685 billion for the TBSRP. The bill specifies program funding sources as shown in Table 1-Program Budget. Table 1—Program Budget as of June 30, 2011 ($ Millions)

Funding Available & Budgeted Contribution Financing Seismic Surcharge Revenue AB 1171 2,282.0 2,282.0 Seismic Surcharge Revenue AB 144 2,150.0 2,150.0 Seismic Surcharge Revenue AB 1175(5) 750.0 750.0 BATA Consolidation 820.0 820.0 Subtotal - Financing 6,002.0 6,002.0

Contributions Proposition 192 790.0 789.0 San Diego Coronado Toll Bridge Revenue Fund 33.0 33.0 Vincent Thomas Bridge 15.0 6.9 State Highway Account(1)(2) 745.0 745.0 Public Transportation Account(1)(3) 130.0 130.0 ITIP/SHOPP/Federal Contingency 448.0 200.0 Federal Highway Bridge Replacement and Rehabilitation (HBRR) 642.0 642.0 SHA - East Span Demolition 300.0 - SHA - “Efficiency Savings”(4) 130.0 63.0 Redirect Spillover 125.0 125.0 Motor Vehicle Account 75.0 75.0 Subtotal - Contribution 3,433.0 2,808.9

Total Funding 9,435.0 8,810.9

Encumbered to Date 7,502.7

Remaining Unallocated 1,308.2

Expenditures : Capital Outlay 5,655.1 State Operations 1,490.1 Antioch and Dumbarton Expenditures by BATA 12.2 Total Expenditures 7,157.5

Encumbrances : (6) Capital Outlay 327.7 State Operations 17.6 Total Encumbrances 345.3

Total Expenditures and Encumbrances 7,502.7

(1) The California Transportation Commission adopted a new schedule and changed the PTA/SHA split on December 15, 2005. (2) To date $645 million has been transferred from the SHA to the TBSRP, including the full $290 million transfer scheduled by the CTC to occur in 2005-06. An additional $100 million has been expended directly from the account. (3) To date $130 million has been transferred from the PTA to the TBSRP, including the full amount of all transfers scheduled by the CTC. (4)To date $10 million has been transferred from the SHA to the TBSRP, representing the commitment of “Efficiency Savings” identified under AB 144. Approximately $120 million remains to be distributed as scheduled by the CTC. (5) As of January 1, 2010, seismic retrofitting of Antioch and Dumbarton Bridges became part of the Toll Bridge Seismic Retrofit Program with the passage of AB 1175.

44 2011 Second Quarter Project Progress and Financial Update

Summary of the Toll Bridge Oversight Committee (TBPOC) Expenses

Pursuant to Streets and Highways Code Section 30952.1 (d), expenses incurred by Caltrans, BATA, and the California Transportation Commission (CTC) for costs directly related to the duties associated with the TBPOC are to be reimbursed by toll revenues. Table 3 -Toll Bridge Program Oversight Committee Estimated Expenses: July 1, 2005 through June 30, 2011 shows expenses through June 30, 2011 for TBPOC functioning, support, and monthly and quarterly reporting. Table 2—CTC Toll Bridge Seismic Retrofit Program Contributions Adopted December 2005 Schedule of Contributions to the Toll Bridge Seismic Retrofit Program ($ Millions)

2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 Source Description Total (Actual) (Actual) (Actual) (Actual) (Actual) (Actual)

SHA 290 290 PTA 80 40 120 Highway AB Bridge Replacement 1171 100 100 100 42 342 and Rehabilitation (HBRR) Contingency 1 99 100 100 148 448 SHA* 2 8 53 50 17 130 Motor Vehicle 75 75 Account AB 144 (MVA) Spillover 125 125 SHA** 300 300 Total 547 273 100 43 99 153 150 165 300 1830 * Caltrans Efficiency Savings ** SFOBB East Span Demolition Cost

Table 3—Toll Bridge Program Oversight Committee Estimated Expenses: July 1, 2005 through June 30, 2011 ($ Millions)

Agency/Program Activity Expenses

BATA 2.0

Caltrans 2.2

CTC 1.8

Reporting 4.1

Total Program 10.1

45 Toll Bridge Program Oversight Committee

TOLL BRIDGE SEISMIC RETROFIT PROGRAM Quarterly Environmental Compliance Highlights

Overall environmental compliance for the San not visible to the monitor, suggested that Francisco Oakland-Bay Bridge (SFOBB) East juveniles were present at the site. Span project has been a success. There are • SFOBB environmental compliance and no comments from regulatory agencies. The storm water pollution prevention plan tasks for the current quarter are focused on (SWPPP) inspections were conducted mitigation monitoring. Key successes in this weekly at all active project sites. The quarter are as follows: project team continues to work closely with contractors to ensure compliance with environmental permits and regulations and • Bird monitoring was conducted weekly improve SWPPP and best management in the active construction area. Monitors practices. did not observe any indication that birds were disturbed due to the East Span construction activities. • On May 24, 2011, Caltrans submitted an amendment request letter to the San Francisco Bay Conservation and • Weekly monitoring of Canada geese Development Commission (BCDC). The along Route 80 roadway adjacent to the letter outlined Amendment No. 30 to Emeryville Crescent for the year began on San Francisco BCDC Permit No. 8-01. March 4, 2011 and will continue through Amendment No. 30 specified modifications August 2011. to the Oakland Touchdown design to include a chevron-shaped landing area and • Peregrine falcon monitoring for the provided details about other public access 2010/2011 nesting season that began on improvements. December 3, 2010 continued through June 20, 2011. The same pair of adult peregrine • On June 28, 2011, a ceremony was held falcons that successfully nested at Pier E2 to commemorate the addition of Skaggs of the existing Bay Bridge in the 2008/2009 Island to the San Pablo Bay National and 2009/2010 nesting seasons returned Wildlife Refuge, increasing the refuge’s and established a nest at the same site. current 13,190 acres of protected lands by approximately 25 percent. To facilitate this • On April 8, four eggs were observed in transfer, Caltrans provided approximately the nest and on April 20, three nestlings $9 million to fund building demolition and were observed for the first time. The three environmental remediation at the Skaggs nestlings were banded on May 5 and it Island site. was determined that there were two males and one female. On May 31, the two male • Caltrans is working with regulatory nestlings were not observed in the nest; it agencies and exploring options to meet was assumed that the two males fledged requirements for shorebird roosting habitat over Memorial Day weekend. On June 1, mitigation. one of the male fledglings was observed by the bird monitor on a crossbeam above the upper deck of the San Francisco- • Caltrans is working on the environmental Oakland Bay Bridge (SFOBB). The female phase for the dismantling of the existing nestling fledged around June 1 and was Bay Bridge. observed approximately four feet below the nest site on a platform. After June 1, the • The Office of Environmental Analysis nestlings were not observed again by the (OEA) is working with the various functional bird monitor; however, crew on the bridge units to prepare a comprehensive review reported several anecdotal sightings of the of the 2001 Final Environmental Impact juveniles. Behavior of the adult peregrines, Statement (EIS)/Statutory Exemption and including the delivery of prey to locations Final Section 4(f) Evaluation. Preliminary

46 2011 Second Quarter Project Progress and Financial Update

assessment indicates re-validation of the EIS is appropriate. The functional units are preparing technical studies and the details of dismantling are being refined to aid in this evaluation.

• On May 27, 2011 Caltrans sent the United States Army Corp of Engineers a letter requesting the modification of Permit No. 23013S, for the SFOBB East Span Project dated December 4, 2001. The modification was requested to extend the time limit allowed by the permit for work on the SFOBB project to January 1, 2019.

• On June 23, 2011 an Interagency Work Group meeting was hosted by Caltrans. The meeting was attended by representatives from the Bay Conservation and Development Commission (BCDC), National Oceanic and Atmospheric Administration (NOAA), United States Army Corps of Engineers (USACOE), Regional Water Quality Control Board (RWQCB), California Department of Fish and Game (CDFG), and the United States Coast Guard (USCG). During the meeting an SFOBB project update was provided, the scope of the existing SFOBB east span dismantling project was reviewed, all existing SFOBB east span dismantling- related permit requirements were outlined, various environmental considerations were reviewed, and agency representatives were given an opportunity to provide feedback.

• Caltrans is preparing packages to amend permits for the dismantling of the existing SFOBB east span. Currently, packages are being prepared for the following agencies: NOAA, CDFG, RWQCB, USCG, and BCDC. The Dredged Material Management Plan (DMMP) is being revisited and preparations are being made to request authorization from the Dredged Material Management Office (DMMO) for the dredging and disposal of material for the existing SFOBB east span dismantling.

Eel Grass in the San Francisco Bay 47

Richmond-San Rafael Bridge REGIONAL MEASURE 1 TOLL BRIDGE PROGRAM MEASURE 1 TOLL REGIONAL Toll Bridge Program Oversight Committee

REGIONAL MEASURE 1 PROGRAM Interstate 880/State Route 92 Interchange Reconstruction Project Project Status: In Construction

The Interstate 880/State Route 92 Interchange Reconstruction Project is the final project under the Regional Measure 1 Toll Bridge Program. Project completion fulfills a promise made to Bay Area voters in 1988 to deliver a slate of projects that help expand bridge capacity and improve safety on the bridges.

Interstate 880/State Route 92 Interchange Reconstruction Contract Contractor: Flatiron/Granite Approved Capital Outlay Budget: $163.2 M Status: 91% Complete as of June 2011

This corridor is consistently one of the Bay Area’s most congested during the evening commute. This is due in part to the lane merging and weaving that is required by the existing cloverleaf interchange. The new interchange will feature direct freeway-to-freeway connector ramps that will increase traffic SR 92/880 WSCONN On Ramp capacity and improve overall safety and traffic operations in the area. With the new direct-connector ramps, drivers coming off of the San Mateo-Hayward Bridge can access Interstate 880 without having to compete with traffic headed onto east Route 92 from south Interstate 880 (see progress photos on pages 82 and 83).

Aerial View of Construction Progress Future Interstate 880/State Route 92 Interchange (as simulated) Looking West toward San Mateo

50 2011 Second Quarter Project Progress and Financial Update

Stage 1 – Construct East Route 92 to North Interstate 880 Connector The new east Route 92 to north Interstate 880 connector (ENCONN) is the most critical fly-over structure for relieving congestion in the corridor. The ENCONN will be first used as a detour to allow for future stages of work, while keeping traffic flowing. Status: ENCONN was completed and opened to detour traffic on May 16, 2009.

Stage 1 - Construct East Route 92 to North Interstate Stage 2 – Replace South Side of Route 92 880 Direct Connector Separation Structure By detouring eastbound Route 92 traffic onto ENCONN, the existing separation structure that carries SR92 over I-880 can be replaced. The existing structure will be cut lengthwise, and then demolished and replaced separately. In this stage, the south side of the structure will be replaced, while west Route 92 and south Interstate 880 to east Route 92 traffic will stay on the remaining structure. Status: Work on the south side of the separation structure is complete. Stage 2 - Demolish and Replace South Side of Route 92 Separation Structure Stage 3 – Replace North Side of Route 92 Separation Structure Upon completion of Stage 2, the existing north side of the separation structure will be demolished and replaced. Its traffic will then be shifted onto the newly reconstructed south side. Status: The north side of the structure opened to traffic in February 2011. Stage 4 – Final Realignment and Other Work

In addition to ENCONN and the separation structure, Stage 3 - Demolish and Replace North Side of Route 92 direct north 880 to west 92 connector (NWCONN) and Separation Structure west 92 to south 880 connector (WSCONN) remain to be completed. The new Eldridge Avenue pedestrian overcrossing is now complete.

Status: The NWCONN structure opened to traffic in October 2010. The WSCONN structure is scheduled to be fully opened in August 2011.

Stage 4 - Final Realignment and Other Work

51 Toll Bridge Program Oversight Committee

REGIONAL MEASURE 1 PROGRAM Other Completed Projects

San Mateo-Hayward Bridge-Widening Project Project Status: Completed 2003

This project expanded the low-rise concrete trestle section of the San Mateo-Hayward Bridge to allow for three lanes in each direction to match the existing configuration of the high-rise steel section of the bridge.

Widening of the San Mateo-Hayward Bridge Trestle on Left

Richmond-San Rafael Bridge Rehabilitation Projects Project Status: Completed 2006

Two major rehabilitation projects for the Richmond-San Rafael Bridge were funded and completed: (1) replacement of the western concrete approach trestle and ship-collision protection fender system; and (2) rehabilitation of deck joints and resurfacing of the bridge deck.

In 2005, along with the seismic retrofit of the bridge, the trestle and fender replacement work was completed as part of the same project. Under a separate contract in 2006, the bridge was resurfaced with a polyester concrete overlay along with the repair of numerous deck joints.

New Richmond-San Rafael Bridge West Approach Trestle under Construction

Richmond Parkway Construction Project Project Status: Completed 2001

The final connections to the Richmond Parkway from Interstate 580 near the Richmond-San Rafael Bridge were completed in May 2001.

52 2011 Second Quarter Project Progress and Financial Update

New Alfred Zampa Memorial (Carquinez) Bridge Project Project Status: Completed 2003

The new western span of the Carquinez Bridge, which replaced the original 1927 span, is a twin-towered suspension bridge with three mixed-flow lanes, a new carpool lane, shoulders and a bicycle/pedestrian pathway.

New Alfred Zampa Memorial (Carquinez) Bridge Soon after Opening to Traffic, with Crockett Interchange Still under Construction Benicia-Martinez Bridge Project Project Status: Completed 2009

A two-year project to rehabilitate and reconfigure the original Benicia-Martinez Bridge began shortly after the opening of the new Congressman George Miller Bridge. The existing 1.2-mile roadway surface on the steel deck truss bridge was modified to carry four lanes of southbound traffic (one more than before)—with shoulders on both sides—plus a bicycle/pedestrian path on the west side of the span that connects to Park Road in Benicia and to Marina Vista Boulevard in Martinez. Reconstruction of the east side of the bridge and approaches was completed in August 2008. Reconstruction of the west side of the bridge and its approaches and construction of the bicycle/pedestrian pathway were completed in August 2009.

Benicia-Martinez Bridge Bicycle/Pedestrian Pathway Opened to the Public in August 2009

Bayfront Expressway (State Route 84) Widening Project Project Status: Completed 2004

This project expanded and improved the roadway from the Dumbarton Bridge touchdown to the US 101/ Marsh Road interchange by adding additional lanes and turn pockets and improving bicycle/pedestrian access in the area.

53

APPENDICES

A. TBSRP AB 144/SB 66 Baseline Budget, Forecasts and Expenditures through June 30, 2011 (A-1 and A-2)…....…...... 56

B. TBSRP (SFOBB East Span Only) AB 144/SB 66 Baseline Budget, Forecasts and Expenditures through June 30, 2011 …….....…...... …....…...... 61

C. Regional Measure 1 Program Cost Detail………………..……...... 64

D. Project Progress Diagrams ...... 68

E. Project Photos…….…………..…………...... 73

F. Glossary of Terms…………..………..…...... 90

Ladder Providing Access from a Roadway Box to the Floor Beam and down to the Temporary Truss Structure Toll Bridge Program Oversight Committee Appendix A-1: TBSRP AB 144/SB 66 Baseline Budget, Forecasts and Expenditures through June 30, 2011 ($ Millions)

Current AB 144 / SB Approved Cost At- 66 Budget Approved Budget Cost to Date Forecast Completion Contract (07/2005) Changes (06/2011) (06/2011) (06/2011) Variance a c d e = c + d f g h = g - e

SFOBB East Span Replacement Project Capital Outlay Support 959.3 218.0 1,177.3 965.5 1,275.8 98.5 Capital Outlay Construction 4,492.2 589.4 5,081.6 3,919.3 5,164.4 82.8 Other Budgeted Capital 35.1 (3.3) 31.8 0.7 7.7 (24.1) Total 5,486.6 804.1 6,290.7 4,885.5 6,447.9 157.2 SFOBB West Approach Replacement Capital Outlay Support 120.0 (2.0) 118.0 118.3 118.5 0.5 Capital Outlay Construction 309.0 41.7 350.7 329.6 338.1 (12.6) Total 429.0 39.7 468.7 447.9 456.6 (12.1) SFOBB West Span Retrofit - Capital Outlay Support 75.0 (0.2) 74.8 74.9 74.8 - Capital Outlay Construction 232.9 (5.5) 227.4 227.4 227.4 - Total 307.9 (5.7) 302.2 302.3 302.2 - Richmond-San Rafael Bridge Retrofit Capital Outlay Support 134.0 (7.0) 127.0 126.8 127.0 - Capital Outlay Construction 780.0 (90.5) 689.5 667.5 689.5 - Total 914.0 (97.5) 816.5 794.3 816.5 - Benicia-Martinez Bridge Retrofit - Capital Outlay Support 38.1 - 38.1 38.1 38.1 - Capital Outlay Construction 139.7 - 139.7 139.7 139.7 - Total 177.8 - 177.8 177.8 177.8 - Carquinez Bridge Retrofit Capital Outlay Support 28.7 0.1 28.8 28.8 28.8 - Capital Outlay Construction 85.5 (0.1) 85.4 85.4 85.4 - Total 114.2 - 114.2 114.2 114.2 - San Mateo-Hayward Retrofit - Capital Outlay Support 28.1 - 28.1 28.1 28.1 - Capital Outlay Construction 135.4 (0.1) 135.3 135.3 135.3 - Total 163.5 (0.1) 163.4 163.4 163.4 - Vincent Thomas Bridge Retrofit (Los Angeles) Capital Outlay Support 16.4 - 16.4 16.4 16.4 - Capital Outlay Construction 42.1 (0.1) 42.0 42.0 42.0 - Total 58.5 (0.1) 58.4 58.4 58.4 - San Diego-Coronado Bridge Retrofit Capital Outlay Support 33.5 (0.3) 33.2 33.2 33.2 - Capital Outlay Construction 70.0 (0.6) 69.4 69.4 69.4 - Total 103.5 (0.9) 102.6 102.6 102.6 -

56 2011 Second Quarter Project Progress and Financial Update Appendix A-1: TBSRP AB 144/SB 66 Baseline Budget, Forecasts and Expenditures through June 30, 2011 ($ Millions) Cont.

Current AB 144 / SB Approved Cost At- 66 Budget Approved Budget Cost to Date Forecast Completion Contract (07/2005) Changes (06/2011) (06/2011) (06/2011) Variance a c d e = c + d f g h = g - e

Antioch Bridge Capital Outlay Support - 31.0 31.0 13.6 34.7 3.7 Capital Outlay Support by BATA 6.2 Capital Outlay Construction - 70.0 70.0 25.6 56.9 (13.1) Total - 101.0 101.0 45.4 91.6 (9.4) Dumbarton Bridge Capital Outlay Support - 56.0 56.0 21.0 57.2 1.2 Capital Outlay Support by BATA 6.0 Capital Outlay Construction - 92.7 92.7 13.2 88.8 (3.9) Total - 148.7 148.7 40.2 146.0 (2.7)

Subtotal Capital Outlay Support 1,433.1 295.6 1,728.7 1,476.9 1,832.6 103.9 Subtotal Capital Outlay 6,286.8 696.9 6,983.7 5,654.4 7,036.9 53.2 Subtotal Other Budgeted Capital 35.1 (3.3) 31.8 0.7 7.7 (24.1) Miscellaneous Program Costs 30.0 - 30.0 25.5 30.0 - Subtotal Toll Bridge Seismic Retrofit Program 7,785.0 989.2 8,774.2 7,157.5 8,907.2 133.0 Net Programmatic Risks* - - - - 66.9 66.9 Program Contingency 900.0 (592.2) 307.8 - 107.9 (199.9)

Total Toll Bridge Seismic Retrofit Program 1 8,685.0 397.0 9,082.0 7,157.5 9,082.0 -

1 Figures may not sum up to totals due to rounding effects.

57 Toll Bridge Program Oversight Committee Appendix A-2: TBSRP AB 144/SB 66 Baseline Budget, Forecasts and Expenditures through June 30, 2011 ($ Millions)

Expenditures to date and Estimated costs Encumbrances not yet spent or Total as of June Encumbered as Forecast AB 144 Baseline TBPOC Current 2011 of June 2011 as of June Bridge Budget Approved Budget see Note (1) 2011 a b c d e f = d + e Other Completed Projects Capital Outlay Support 144.9 144.6 144.6 - 144.6 Capital Outlay 472.6 471.9 472.6 (0.8) 471.8 Total 617.5 616.5 617.2 (0.8) 616.4 Richmond-San Rafael Capital Outlay Support 134.0 127.0 126.8 0.2 127.0 Capital Outlay 698.0 689.5 667.8 21.7 689.5 Project Reserves 82.0 - - - - Total 914.0 816.5 794.6 21.9 816.5 West Span Retrofit Capital Outlay Support 75.0 74.8 74.8 - 74.8 Capital Outlay 232.9 227.4 232.9 (5.5) 227.4 Total 307.9 302.2 307.7 (5.5) 302.2 West Approach Capital Outlay Support 120.0 118.0 118.2 0.3 118.5 Capital Outlay 309.0 350.7 345.7 (7.6) 338.1 Total 429.0 468.7 463.9 (7.3) 456.6 SFOBB East Span - Skyway Capital Outlay Support 197.0 181.2 181.2 - 181.2 Capital Outlay 1,293.0 1,254.1 1,345.7 (100.5) 1,245.2 Total 1,490.0 1,435.3 1,526.9 (100.5) 1,426.4 SFOBB East Span - SAS - Superstructure Capital Outlay Support 214.6 375.5 331.5 144.7 476.2 Capital Outlay 1,753.7 2,046.8 1,532.6 546.3 2,078.9 Total 1,968.3 2,422.3 1,864.1 691.0 2,555.1 SFOBB East Span - SAS - Foundations Capital Outlay Support 62.5 37.6 37.6 - 37.6 Capital Outlay 339.9 307.3 309.3 (4.3) 305.0 Total 402.4 344.9 346.9 (4.3) 342.6 Small YBI Projects Capital Outlay Support 10.6 10.6 10.2 0.4 10.6 Capital Outlay 15.6 15.6 15.5 0.2 15.7 Total 26.2 26.2 25.7 0.6 26.3 YBI Detour Capital Outlay Support 29.5 90.7 87.4 0.8 88.2 Capital Outlay 131.9 492.8 492.7 (9.9) 482.8 Total 161.4 583.5 580.1 (9.1) 571.0 YBI- Transition Structures Capital Outlay Support 78.7 106.4 50.2 66.9 117.1 Capital Outlay 299.4 247.8 130.2 174.9 305.1 Total 378.1 354.2 180.4 241.8 422.2

58 2011 Second Quarter Project Progress and Financial Update Appendix A-2: TBSRP AB 144/SB 66 Baseline Budget, Forecasts and Expenditures through June 30, 2011 ($ Millions) Cont.

Expenditures to date Estimated Costs and not yet spent or AB 144 Encumbrances Encumbered as Total Forecast Baseline TBPOC Current as of June 2011 of June 2011 as of June Contract Budget Approved Budget see Note (1) 2011 a b c d e f = d + e

Oakland Touchdown Capital Outlay Support 74.4 108.9 86.0 31.2 117.2 Capital Outlay 283.8 339.0 216.0 117.9 333.9 Total 358.2 447.9 302.0 149.1 451.1 East Span Other Small Projects Capital Outlay Support 212.3 206.5 197.9 8.7 206.6 Capital Outlay 170.8 170.8 118.9 35.7 154.6 Total 383.1 377.3 316.8 44.4 361.2 Existing Bridge Demolition Capital Outlay Support 79.7 59.9 0.7 40.4 41.1 Capital Outlay 239.2 239.1 - 250.8 250.8 Total 318.9 299.0 0.7 291.2 291.9 Antioch Bridge Capital Outlay Support - 31.0 13.8 14.7 28.5 Capital Outlay Support by BATA 6.2 - 6.2 Capital Outlay - 70.0 47.4 9.5 56.9 Total - 101.0 67.4 24.2 91.6 Dumbarton Bridge Capital Outlay Support - 56.0 21.3 29.9 51.2 Capital Outlay Support by BATA 6.0 - 6.0 Capital Outlay - 92.7 55.5 33.3 88.8 Total - 148.7 82.8 63.2 146.0

Miscellaneous Program Costs 30.0 30.0 25.5 4.5 30.0 Total Capital Outlay Support 1,463.2 1,758.7 1,519.9 342.7 1,862.6 Total Capital Outlay 6,321.8 7,015.5 5,982.8 1,061.8 7,044.6 Program Total 1 7,785.0 8,774.2 7,502.7 1,404.5 8,907.2

(1). Funds allocated to project or contract for Capital Outlay and Support needs includes Capital Outlay Support total allocation for FY 06/07. (2). BSA provided a distribution of program contingency in December 2004 based in Bechtel Infrastructure Corporation input. This Column is subject to revision upon completion of Department’s risk assessment update. (3) Total Capital Outlay Support includes program indirect costs.

1 Figures may not sum up to totals due to rounding effects.

59 Toll Bridge Program Oversight Committee Appendix B: TBSRP (SFOBB East Span Only) AB 144/SB 66 Baseline Budget, Forecasts and Expenditures through June 30, 2011 ($ Millions)

Current AB 144 / SB Approved Cost At- 66 Budget Approved Budget Cost to Date Forecast Completion Contract (07/2005) Changes (06/2011) (06/2011) (06/2011) Variance a c d e = c + d f g h = g - e

San Francisco-Oakland Bay Bridge East Span Replacement Project East Span - SAS Superstructure Capital Outlay Support 214.6 160.9 375.5 317.9 476.2 100.7 Capital Outlay Construction 1,753.7 293.1 2,046.8 1,530.8 2,078.9 32.1 Total 1,968.3 454.0 2,422.3 1,848.7 2,555.1 132.8 SAS W2 Foundations Capital Outlay Support 10.0 (0.8) 9.2 9.2 9.2 - Capital Outlay Construction 26.4 - 26.4 26.5 26.4 - Total 36.4 (0.8) 35.6 35.7 35.6 - YBI South/South Detour Capital Outlay Support 29.4 61.3 90.7 86.9 88.2 (2.5) Capital Outlay Construction 131.9 360.9 492.8 465.8 482.8 (10.0) Total 161.3 422.2 583.5 552.7 571.0 (12.5) East Span - Skyway Capital Outlay Support 197.0 (15.8) 181.2 181.2 181.2 - Capital Outlay Construction 1,293.0 (38.9) 1,254.1 1,237.1 1,245.2 (8.9) Total 1,490.0 (54.7) 1,435.3 1,418.3 1,426.4 (8.9) East Span - SAS E2/T1 Foundations - Capital Outlay Support 52.5 (24.1) 28.4 28.4 28.4 - Capital Outlay Construction 313.5 (32.6) 280.9 274.8 278.6 (2.3) Total 366.0 (56.7) 309.3 303.2 307.0 (2.3) YBI Transition Structures (see notes below) Capital Outlay Support 78.7 27.7 106.4 47.9 117.1 10.7 Capital Outlay Construction 299.3 (51.5) 247.8 43.0 305.1 57.3 Total 378.0 (23.8) 354.2 90.9 422.2 68.0 * YBI- Transition Structures Capital Outlay Support 16.4 16.4 16.5 0.1 Capital Outlay Construction - - - - Total 16.4 16.4 16.5 0.1 * YBI- Transition Structures Contract No. 1 Capital Outlay Support 57.0 23.4 67.1 10.1 Capital Outlay Construction 185.5 43.0 222.4 36.9 Total 242.5 66.4 289.5 47.0 * YBI- Transition Structures Contract No. 2 Capital Outlay Support 32.0 8.1 32.5 0.5 Capital Outlay Construction 59.0 - 79.4 20.4 Total 91.0 8.1 111.9 20.9 * YBI- Transition Structures Contract No. 3 Landscape Capital Outlay Support 1.0 - 1.0 - Capital Outlay Construction 3.3 - 3.3 - Total 4.3 - 4.3 -

60 2011 Second Quarter Project Progress and Financial Update Appendix B: TBSRP (SFOBB East Span Only) AB 144/SB 66 Baseline Budget, Forecasts and Expenditures through June 30, 2011 ($ Millions) Cont.

Current AB 144 / SB Approved Cost At- 66 Budget Approved Budget Cost to Date Forecast Completion Contract (07/2005) Changes (06/2011) (06/2011) (06/2011) Variance a c d e = c + d f g h = g - e Oakland Touchdown (see notes below) Capital Outlay Support 74.4 34.5 108.9 85.2 117.2 8.3 Capital Outlay Construction 283.8 55.2 339.0 209.4 333.9 (5.1) Total 358.2 89.7 447.9 294.6 451.1 3.2 *OTD Prior-to-Split Costs Capital Outlay Support 21.7 20.1 21.7 - Capital Outlay Construction - - - - Total 21.7 20.1 21.7 - *OTD Submarine Cable Capital Outlay Support 0.9 0.9 0.9 - Capital Outlay Construction 9.6 6.5 9.6 - Total 10.5 7.4 10.5 - *OTD No.1 (Westbound) Capital Outlay Support 47.3 50.9 51.7 4.4 Capital Outlay Construction 212.0 202.9 203.3 (8.7) Total 259.3 253.8 255.0 (4.3) *OTD No.2 (Eastbound) Capital Outlay Support 22.5 10.8 26.4 3.9 Capital Outlay Construction 62.0 - 58.6 (3.4) Total 84.5 10.8 85.0 0.5 * Oakland Detour Capital Outlay Support 15.0 1.8 15.0 - Capital Outlay Construction 51.0 - 58.0 7.0 Total 66.0 1.8 73.0 7.0 *OTD Electrical Systems Capital Outlay Support 1.5 0.8 1.5 - Capital Outlay Construction 4.4 - 4.4 - Total 5.9 0.8 5.9 - Existing Bridge Demolition Capital Outlay Support 79.7 (19.8) 59.9 0.7 41.1 (18.8) Capital Outlay Construction 239.2 (0.1) 239.1 - 250.8 11.7 Total 318.9 (19.9) 299.0 0.7 291.9 (7.1) YBI/SAS Archeology Capital Outlay Support 1.1 - 1.1 1.1 1.1 - Capital Outlay Construction 1.1 - 1.1 1.1 1.1 - Total 2.2 - 2.2 2.2 2.2 - YBI - USCG Road Relations Capital Outlay Support 3.0 - 3.0 2.7 3.0 - Capital Outlay Construction 3.0 - 3.0 2.8 3.0 - Total 6.0 - 6.0 5.5 6.0 - YBI - Substation and Viaduct Capital Outlay Support 6.5 - 6.5 6.4 6.5 - Capital Outlay Construction 11.6 - 11.6 11.3 11.6 - Total 18.1 - 18.1 17.7 18.1 -

61 Toll Bridge Program Oversight Committee Appendix B: TBSRP (SFOBB East Span Only) AB 144/SB 66 Baseline Budget, Forecasts and Expenditures through June 30, 2011 ($ Millions) Cont.

Current AB 144 / SB Approved Cost At- 66 Budget Approved Budget Cost to Date Forecast Completion Contract (07/2005) Changes (06/2011) (06/2011) (06/2011) Variance a c d e = c + d f g h = g - e Oakland Geofill Capital Outlay Support 2.5 - 2.5 2.5 2.5 - Capital Outlay Construction 8.2 - 8.2 8.2 8.2 - Total 10.7 - 10.7 10.7 10.7 - Pile Installation Demonstration Project Capital Outlay Support 1.8 - 1.8 1.8 1.8 - Capital Outlay Construction 9.3 - 9.3 9.2 9.3 - Total 11.1 - 11.1 11.0 11.1 - Stormwater Treatment Measures Capital Outlay Support 6.0 2.2 8.2 8.2 8.2 - Capital Outlay Construction 15.0 3.3 18.3 16.8 18.3 - Total 21.0 5.5 26.5 25.0 26.5 - Right-of-Way and Environmental Mitigation Capital Outlay Support ------Capital Outlay & Right-of-Way 72.4 - 72.4 51.7 80.4 8.0 Total 72.4 - 72.4 51.7 80.4 8.0 Sunk Cost - Existing East Span Retrofit Capital Outlay Support 39.5 - 39.5 39.5 39.5 - Capital Outlay Construction 30.8 - 30.8 30.8 30.8 - Total 70.3 - 70.3 70.3 70.3 - Other Capital Outlay Support Environmental Phase 97.7 - 97.7 97.8 97.7 - Pre-Split Project Expenditures 44.9 - 44.9 44.9 44.9 - Non-project Specific Costs 20.0 (8.0) 12.0 3.2 12.0 - Total 162.6 (8.0) 154.6 145.9 154.6 -

Subtotal Capital Outlay Support 959.3 218.0 1,177.3 965.5 1,275.8 98.5 Subtotal Capital Outlay Construction 4,492.2 589.4 5,081.6 3,919.3 5,164.4 82.8 Other Budgeted Capital 35.1 (3.3) 31.8 0.7 7.7 (24.1) - Total SFOBB East Span Replacement Project 1 5,486.6 804.1 6,290.7 4,885.5 6,447.9 157.2

1 Figures may not sum up to totals due to rounding effects.

62 2011 Second Quarter Project Progress and Financial Update Appendix C: Regional Measure 1 Program Cost Detail ($ Millions)

Current AB 144 / SB Approved Cost At- 66 Budget Approved Budget Cost to Date Forecast Completion Contract (07/2005) Changes (06/2011) (05/2011) (06/2011) Variance a c d e = c + d f g h = g - e

New Benicia-Martinez Bridge Project New Bridge Capital Outlay Support BATA Funding 84.9 7.2 92.1 91.9 92.1 - Non-Bata Funding - 0.1 0.1 0.1 0.1 - Subtotal 84.9 7.3 92.2 92.0 92.2 - Capital Outlay Construction - - BATA Funding 661.9 94.6 756.5 753.7 756.5 - Non-Bata Funding 10.1 - 10.1 10.1 10.1 - Subtotal 672.0 94.6 766.6 763.8 766.6 - Total 756.9 101.9 858.8 855.8 858.8 - I-680/I-780 Interchange Reconstruction Capital Outlay Support BATA Funding 24.9 5.2 30.1 30.1 30.1 - Non-Bata Funding 1.4 5.2 6.6 6.3 6.6 - Subtotal 26.3 10.4 36.7 36.4 36.7 - Capital Outlay Construction BATA Funding 54.7 26.9 81.6 77.1 81.6 - Non-Bata Funding 21.6 - 21.6 21.7 21.7 0.1 Subtotal 76.3 26.9 103.2 98.8 103.3 0.1 Total 102.6 37.3 139.9 135.2 140.0 0.1 I-680/Marina Vista Interchange Reconstruction Capital Outlay Support 18.3 1.9 20.2 20.2 20.2 - Capital Outlay Construction 51.5 4.9 56.4 56.1 56.4 - Total 69.8 6.8 76.6 76.3 76.6 - New Toll Plaza and Administration Building Capital Outlay Support 11.9 3.8 15.7 15.7 15.7 - Capital Outlay Construction 24.3 2.0 26.3 25.1 26.3 - Total 36.2 5.8 42.0 40.8 42.0 - Existing Bridge & Interchange Modifications Capital Outlay Support BATA Funding 4.3 13.7 18.0 18.0 18.0 - Non-Bata Funding - 0.9 0.9 0.8 0.9 - Subtotal 4.3 14.6 18.9 18.8 18.9 - Capital Outlay Construction BATA Funding 17.2 32.8 50.0 37.2 50.0 - Non-Bata Funding - 9.5 9.5 - 9.5 - Subtotal 17.2 42.3 59.5 37.2 59.5 - Total 21.5 56.9 78.4 56.0 78.4 - Other Contracts Capital Outlay Support 11.4 (0.9) 10.5 9.5 10.5 - Capital Outlay Construction 20.3 3.3 23.6 18.5 23.6 - Capital Outlay Right-of-Way 20.4 (0.1) 20.3 17.0 20.3 - Total 52.1 2.3 54.4 45.0 54.4 -

63 Toll Bridge Program Oversight Committee Appendix C: Regional Measure 1 Program Cost Detail ($ Millions) Cont.

Current AB 144 / SB Approved Cost At- 66 Budget Approved Budget Cost to Date Forecast Completion Contract (07/2005) Changes (06/2011) (05/2011) (06/2011) Variance a c d e = c + d f g h = g - e

New Benicia-Martinez Bridge Project continued... Subtotal BATA Capital Outlay Support 155.7 30.9 186.6 185.4 186.6 - Subtotal BATA Capital Outlay Construction 829.9 164.5 994.4 967.7 994.4 - Subtotal Capital Outlay Right-of-Way 20.4 (0.1) 20.3 17.0 20.3 - Subtotal Non-BATA Capital Outlay Support 1.4 6.2 7.6 7.2 7.6 - Subtotal Non-BATA Capital Outlay Construction 31.7 9.5 41.2 31.8 41.3 0.1 Project Reserves 20.8 1.6 22.4 - 22.3 (0.1)

Total New Benicia-Martinez Bridge Project 1,059.9 212.6 1,272.5 1,209.1 1,272.5 - Notes: Includes EA’s 00601_,00603_,00605_,00606_,00608_,00609_,0060A_,0060C_,0060E_, 0060F_,0060G_,0060H_, and all Project Right-of-Way

Carquinez Bridge Replacement Project New Bridge Capital Outlay Support 60.5 (0.3) 60.2 60.2 60.2 - Capital Outlay Construction 253.3 2.7 256.0 255.9 256.0 - Total 313.8 2.4 316.2 316.1 316.2 - Crockett Interchange Reconstruction Capital Outlay Support 32.0 (0.1) 31.9 31.9 31.9 - Capital Outlay Construction 73.9 (1.9) 72.0 71.9 72.0 - Total 105.9 (2.0) 103.9 103.8 103.9 - Existing 1927 Bridge Demolition Capital Outlay Support 16.1 (0.3) 15.8 15.7 15.8 - Capital Outlay Construction 35.2 - 35.2 34.8 35.2 - Total 51.3 (0.3) 51.0 50.5 51.0 - Other Contracts Capital Outlay Support 15.8 0.9 16.7 16.4 16.7 - Capital Outlay Construction 18.8 (1.2) 17.6 16.4 17.6 - Capital Outlay Right-of-Way 10.5 (0.1) 10.4 9.9 10.4 - Total 45.1 (0.4) 44.7 42.7 44.7 -

Subtotal BATA Capital Outlay Support 124.4 0.2 124.6 124.2 124.6 - Subtotal BATA Capital Outlay Construction 381.2 (0.4) 380.8 379.0 380.8 - Subtotal Capital Outlay Right-of-Way 10.5 (0.1) 10.4 9.9 10.4 - Project Reserves 12.1 (9.7) 2.4 - 2.4 -

Total Carquinez Bridge Replacement Project 1 528.2 (10.0) 518.2 513.1 518.2 -

Notes Other Contracts include EAs 01301_,01302_,01303_,01304_,01305_,01306_,01307_,01308_,01309_,0130A_,0130C _,0130D_,0130F_,0130G_,0130H_,0130J_,00453_,00493_,04700_,00607_,2A270_,and 29920_ and all Project Right-of-Way

1 Figures may not sum up to totals due to rounding effects.

64 2011 Second Quarter Project Progress and Financial Update Appendix C: Regional Measure 1 Program Cost Detail ($ Millions) Cont.

Current AB 144 / SB Approved Cost At- 66 Budget Approved Budget Cost to Date Forecast Completion Contract (07/2005) Changes (06/2011) (05/2011) (06/2011) Variance a c d e = c + d f g h = g - e

Richmond-San Rafael Bridge Trestle. Fender, and Deck Joint Rehabilitation Capital Outlay Support BATA Funding 2.2 (0.8) 1.4 1.4 1.4 - Non-BATA Funding 8.6 1.8 10.4 10.4 10.4 - Subtotal 10.8 1.0 11.8 11.8 11.8 - Capital Outlay Construction BATA Funding 40.2 (6.8) 33.4 33.3 33.4 - Non-BATA Funding 51.1 - 51.1 51.1 51.1 - Subtotal 91.3 (6.8) 84.5 84.4 84.5 - Project Reserves - 0.8 0.8 - 0.8 - Total 102.1 (5.0) 97.1 96.2 97.1 - Richmond-San Rafael Bridge Deck Overlay Rehabilitation Capital Outlay Support BATA Funding 4.0 (0.7) 3.3 3.3 3.3 - Non-BATA Funding 4.0 (4.0) - - - - Subtotal 8.0 (4.7) 3.3 3.3 3.3 - Capital Outlay Construction 16.9 (0.6) 16.3 16.3 16.3 - Project Reserves 0.1 0.3 0.4 - 0.4 - Total 25.0 (5.0) 20.0 19.6 20.0 - Richmond Parkway Project (RM 1 Share Only) Capital Outlay Support ------Capital Outlay Construction 5.9 - 5.9 4.3 5.9 - Total 5.9 - 5.9 4.3 5.9 - San Mateo-Hayward Bridge Widening Capital Outlay Support 34.6 (0.5) 34.1 34.1 34.1 - Capital Outlay Construction 180.2 (6.1) 174.1 174.1 174.1 - Capital Outlay Right-of-Way 1.5 (0.9) 0.6 0.5 0.6 - Project Reserves 1.5 (0.5) 1.0 - 1.0 - Total 217.8 (8.0) 209.8 208.7 209.8 - I-880/SR-92 Interchange Reconstruction Capital Outlay Support 28.8 35.8 64.6 59.2 64.6 - Capital Outlay Construction BATA Funding 85.2 68.4 153.6 130.7 153.6 - Non-BATA Funding 9.6 - 9.6 - 9.6 - Subtotal 94.8 68.4 163.2 130.7 163.2 - Capital Outlay Right-of-Way 9.9 7.3 17.2 14.5 17.2 - Project Reserves 0.3 (0.3) - - - - Total 133.8 111.2 245.0 204.4 245.0 - Bayfront Expressway Widening Capital Outlay Support 8.6 (0.2) 8.4 8.3 8.4 - Capital Outlay Construction 26.5 (1.5) 25.0 24.9 25.0 - Capital Outlay Right-of-Way 0.2 - 0.2 0.2 0.2 - Project Reserves 0.8 (0.3) 0.5 - 0.5 - Total 36.1 (2.0) 34.1 33.4 34.1 -

65 Toll Bridge Program Oversight Committee Appendix C: Regional Measure 1 Program Cost Detail ($ Millions) Cont.

Current AB 144 / SB Approved Cost At- 66 Budget Approved Budget Cost to Date Forecast Completion Contract (07/2005) Changes (06/2011) (05/2011) (06/2011) Variance a c d e = c + d f g h = g - e

US 101/University Avenue Interchange Modification Capital Outlay Support ------Capital Outlay Construction 3.8 - 3.8 3.7 3.8 - Total 3.8 - 3.8 3.7 3.8 -

Subtotal BATA Capital Outlay Support 358.3 64.7 423.0 415.9 423.0 - Subtotal BATA Capital Outlay Construction 1,569.8 217.5 1,787.3 1,734.0 1,787.3 - Subtotal Capital Outlay Right-of-Way 42.5 6.2 48.7 42.1 48.7 - Subtotal Non-BATA Capital Outlay Support 14.0 4.0 18.0 17.6 18.0 - Subtotal Non-BATA Capital Outlay Construction 92.4 9.5 101.9 82.9 102.0 0.1 Project Reserves 35.6 (8.1) 27.5 - 27.4 (0.1) Total RM1 Program 2,112.6 293.8 2,406.4 2,292.5 2,406.4 -

1 Richmond-San Rafael Bridge Trestle, Fender, and Deck Joint Rehabilitation Notes: Includes Non-TBSRP Expenses for EA 0438U_ and 04157_ 2 San Mateo-Hayward Bridge Widening includes EAs 00305_,04501_,04503_,04504_, 04504_,04505_,04506_,04507_,04508_,04509_,27740_,27790_,04860_

66 Yerba Buena Island Tranistion Structures Looking East at the Tower of the Self-Anchored Suspension Bridge and Back Span Installed Catwalks Toll Bridge Program Oversight Committee

Appendix D: Progress Diagrams Yerba Buena Island Transition Structures

68 2011 Second Quarter Project Progress and Financial Update

Appendix D: Progress Diagrams (cont.) Antioch Bridge

69 Toll Bridge Program Oversight Committee

Appendix D: Progress Diagrams Dumbarton Bridge

70 2011 Second Quarter Project Progress and Financial Update

Aerial View of the Newly Installed Westbound Back Span Cat- walk for Installation of Cables

71 The Tower Saddle Being Lifted onto the Tower Top Position and View of the Skyway and the Existing Bridge from the top of the Tower

Toll Bridge Program Oversight Committee

72 2011 Second Quarter Project Progress and Financial Update

Project Photos

73 Toll Bridge Program Oversight Committee Appendix E: Project Progress Photographs Self-Anchored Suspension Bridge Fabrication

Self-Anchored Suspension Bridge Roadway Box Being Inspected before Shipment

Self-Anchored Suspension Bridge Roadway Box 14 East Bay

74 2011 Second Quarter Project Progress and Financial Update

Self-Anchored Suspension Bridge Roadway Box Being Inspected before Shipment San Francicso-Oakland Bridge Bike Path Rails

Self-Anchored Suspension Bridge Roadway Box 14 East Bay Self-Anchored Suspension Bridge Lifting Attachments for the Roadway Boxes

75

Workers Installing the Traveller Rail on the Eastbound Roadway Box Toll Bridge Program Oversight Committee Appendix E: Project Progress Photographs Self-Anchored Suspension Bridge Field Work

Cable Catwalk Installation for the Westbound Backspan

78 2011 Second Quarter Project Progress and Financial Update

Self-Anchored Suspension Bridge Bike Path Deck Installation in Progress

79 Toll Bridge Program Oversight Committee Appendix E: Project Progress Photographs Self-Anchored Suspension Bridge Field Work

Tower Saddle Being Lowered next to the Grillage

80 2011 Second Quarter Project Progress and Financial Update

Tower Saddle Installed on Grillage Looking West from the top of the Tower are the Installed Roadway Boxes, the Yerba Buena Island Transition Structure and the Downtown San Francisco Skyline 81 Toll Bridge Program Oversight Committee Appendix E: Project Progress Photographs 92/880 Interchange

Under Drain Installation in Progress along J-7 LIne

WSCONN Bridge Construction in Progress

82 2011 Second Quarter Project Progress and Financial Update

Simulation of SR 880 Looking South

SR-92 Eldridge Avenue Pedestrian Over-Crossing WSCONN Bridge Construction in Progress

83 Toll Bridge Program Oversight Committee Appendix E: Project Progress Photographs Antioch Bridge

Antioch Bridge - Samples from Seismic Monitoring Down Hole

Antioch Bridge - Painting of Cross Frame

84 2011 Second Quarter Project Progress and Financial Update

Appendix E: Project Progress Photographs Dumbarton Bridge

Dumbarton Bridge - Forming Pump Station Walls

Antioch Bridge - Painting of Cross Frame Dumbarton Bridge - Welding of New Cross-Frame Connection Pier 17

85 Toll Bridge Program Oversight Committee Appendix E: Project Progress Photographs Oakland Detour

Newly Opened Eastbound Oakland Detour - Temporary Westbound Piles Being Prepared for Installation Oakland Touchdown Detour

Oakland Detour - Relocated Eastbound Temporary Detour

86 2011 Second Quarter Project Progress and Financial Update

Relocated Clear Channel Westbound Sign Oakland Detour under Construction

Newly Opened Eastbound Oakland Detour Newly Opened Eastbound Oakland Touchdown Detour

EBMUD Outfall Crossing Structure

Aerial View of the Newly Opened Eastbound Oakland Detour with the EBMUD Outfall Crossing Structure on the right, the Relo- cated Clear Channel Sign and the Westbound Oakland Detour under Construction Oakland Touchdown Detour Progress 87 Toll Bridge Program Oversight Committee Appendix E: Project Progress Photographs Yerba Buena Island Transition Structure #1 Westbound

Yerba Buena Island Transition Structures #1 Westbound Concrete Pour

Yerba Buena Island Transition Structures #1 Westbound Concrete Pour with Newly Installed Catwalks to Tower in Background 88 2011 Second Quarter Project Progress and Financial Update

View from the top of the Self-Anchored Suspension Bridge’s Tower Looking Down on the Yerba Buena Island Transition Structures #1 Westbound Falsework, Formwork and Rebar Installation in Progress Oakland Touchdown Detour Progress 89 Toll Bridge Program Oversight Committee Appendix F: Glossary of Terms

Glossary of Terms

AB144/SB 66 BUDGET: The planned allocation of resources for the Toll Bridge Seismic Retrofit Program, or subordinate projects or contracts, as provided in Assembly Bill 144 and Senate Bill 66, signed into law by Governor Schwarzenegger on July 18, 2005 and September 29, 2005, respectively.

BATA BUDGET: The planned allocation of resources for the Regional Measure 1 Program, or subordinate projects or contracts as authorized by the Bay Area Toll Authority as of June 2005.

APPROVED CHANGES: For cost, changes to the AB144/SB 66 Budget or BATA Budget as approved by the Bay Area Toll Authority Commission. For schedule, changes to the AB 144/SB 66 Project Complete Baseline approved by the Toll Bridge Program Oversight Committee, or changes to the BATA Project Complete Baseline approved by the Bay Area Toll Authority Commission.

CURRENT APPROVED BUDGET: The sum of the AB144/SB66 Budget or BATA Budget and Approved Changes.

COST TO DATE: The actual expenditures incurred by the program, project or contract as of the month and year shown.

COST FORECAST: The current forecast of all of the costs that are projected to be expended so as to complete the given scope of the program, project, or contract.

AT COMPLETION VARIANCE or VARIANCE (cost): The mathematical difference between the Cost Forecast and the Current Approved Budget.

AB 144/SB 66 PROJECT COMPLETE BASELINE: The planned completion date for the Toll Bridge Seismic Retrofit Program or subordinate projects or contracts.

BATA PROJECT COMPLETE BASELINE: The planned completion date for the Regional Measure 1 Program or subordinate projects or contracts.

PROJECT COMPLETE CURRENT APPROVED SCHEDULE: The sum of the AB144/SB66 Project Complete Baseline or BATA Project Complete Baseline and Approved Changes.

PROJECT COMPLETE SCHEDULE FORECAST: The current projected date for the completion of the program, project, or contract.

SCHEDULE VARIANCE or VARIANCE (schedule): The mathematical difference expressed in months between the Project Complete Schedule Forecast and the Project Complete Current Approved Schedule.

% COMPLETE: % Complete is based on an evaluation of progress on the project, expenditures to date, and schedule.

90 100% Recyclable This document, including the coil binding, is 100% recyclable

The information in this report is provided in accordance with California Government code Section 755. This document is one of a series of reports prepared for the Bay Area Toll Authority (BATA)/Metropolitan Transportation Commission (MTC) for the Toll Bridge Seismic Retrofit and Regional Measure 1 Programs. The contract value for the monitoring efforts, technical analysis, and field site works that contribute to these reports, as well as the report preparation and production is $1,574,873.73.

Bay Area Management Consultants An Association of URS Corporation and Hatch Mott Macdonald

Self-Anchored Suspension Bridge - Back Span Catwalks Installed