The Use of Earned Value As Trend Analysis Tool for Construction Projects in South Africa
1R(0 ve-R,T THE USE OF EARNED VALUE AS TREND ANALYSIS TOOL FOR CONSTRUCTION PROJECTS IN SOUTH AFRICA
THE USE OF EARNED VALUE AS TREND ANALYSIS TOOL FOR CONSTRUCTION PROJECTS IN SOUTH AFRICA By MICHAEL VERTENTEN
A DISSERTATION SUBMITTED IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE DEGREE MAGISTER PHILOSOPHY (ENGINEERING MANAGEMENT) IN THE
FACULTY OF ENGINEERING AND THE BUILT ENVIRIONMENT
OF THE
UNIVERSITY OF JOHANNESBURG
SUPERVISOR: PROF. J.H.C. PRETORIUS CO-SUPERVISOR: PROF. L. PRETORIUS
NOVEMBER 2008
MICI 'AFL VERTENTEN NOVEMBER 2008
THE USE OF EARNED VALUE AS TREND ANALYSIS TOOL FOR CONSTRUCTION PROJECTS IN SOUTH AFRICA
ABSTRACT
The foundation of Earned Value Performance Management (EVPM) was the Cost/Schedule Control Systems Criteria originally defined in the USA in 1967. Earned Value Performance Management has traditionally been used in Defense projects with budgets in excess of R100M. Private industry is now implementing EVPM for major projects, which are large, complex or geographically dispersed. It is the objective of this dissertation to determine whether the Earned Value concept as developed over the years to the form it is in today is being used in the South African construction industry or not. As part of this dissertation the author devised and distributed a questionnaire to a limited and targeted demographic of Project Management practitioners. The results found that the concept of Earned value is being used in some form or other in selected few companies within the South African Construction industry. While it has been recognized, it's benefits are not being fully utilized. The benefit of the Earned Value concept contributing to the successful completion of a project is being acknowledged and more and more construction companies are slowly making Earned Value an intricate part of their Project Management system
NIICHAEL VERIENTEN NOVEMBER 2008 11 THE USE OF EARNED VALUE AS TREND ANALYSIS TOOL FOR CONSTRUCTION PROJECTS IN SOUTH AFRICA
TABLE OF CONTENTS
ABSTRACT II
TABLE OF CONTENTS IIY
LIST OF FIGURES V
LIST OF TABLES V
LIST OF ACRONYMS AND ABBREVIATION V
APPENDIX VI
CHAPTER 1: INTRODUCTION 1 1.1 PROLOGUE 1 1.2 THE PROBLEM 2 1.3 RESEARCH OBJECTIVES 3 1.4 RESEARCH DESIGN 3 1.5 CONCLUSION 4
CHAPTER 2 : CONSTRUCTION INDUSTRY 5 2.1 INTRODUCTION 5 2.2 MEASURING PERFORMANCE 5 2.3 PROJECT IMPLEMENTATION 7 2.4 PROJECT PRODUCTIVITY 9 2.5 CONCLUSION Error! Bookmark not defined.
CHAPTER 3 : PROJECT MANAGEMENT AND PROJECT CONTROLS 13 3.1 INTRODUCTION 13 3.2 PROJECT MANAGEMENT 14 3.3 PROJECT CONTROLS 16 3.4 BASIC COST AND SCHEDULE CONTROL SYSTEM 17 3.5 PROJECT CONTROL ORGANIZATION 17 3.6 PROJECT MANAGEMENT CONTROL SYSTEM (PMCS) 18 3.7 CONCLUSION 20
CHAPTER 4 : EARNED VALUE 21 4.1 INRODUCTION 21 4.2 HISTORY 22 4.3 WHAT IS EARNED VALUE 22 4.4 USING EARNED VALUE 24 4.5 HOW DO WE USE EARNED VALUE? 25 4.6 PRIMARY MEASURES 32 4.7 CONCLUSION 33
CHAPTER 5: RESEARCH QUESTIONNAIRE 36 5.1 INTRODUCTION 36
MICHAEL VERTENTEN NOVEMBER 2008 III THE USE OF EARNED VALUE AS TREND ANALYSIS TOOL FOR CONSTRUCTION PROJECTS IN SOUTH AFRICA
5.2 QUESTIONNAIRE SAMPLE 37 5.3 RESULTS 37 5.4 DISCUSSION ON RESULTS 40 5.5 CONCLUSION 41
CHAPTER 6 : CONCLUSION 42 6.1 SUMMARY 42 6.2 CONCLUSION 42 6.3 RECOMMENDATION FOR FUTURE WORK 43
REFERENCES 44
NBC! IAEL VERTENTEN NOVEMBER 2008 I V THE USE OF EARNED VALUE AS TREND ANALYSIS TOOL FOR CONSTRUCTION PROJECTS IN SOUTI-I AFRICA
LIST OF FIGURES
FIGURE 1 - WORK BREAKDOWN STRUCTURE 26
FIGURE 2 - RESOURCE LOADING THE ACTIVITIES 28
FIGURE 3 - TRADITIONAL COST ANALYSIS 31
FIGURE 4 - EARNED VALUE ELEMENT 31
LIST OF TABLES
Results of Earned Value Questionnaire 44
LIST OF ACRONYMS AND ABBREVIATION
ACWP Actual Cost of Work Performed BAC Budget at Completion BCWP Budgeted Cost of Work Performed BCWS Budget Cost of Work Scheduled C/SCSC Cost/Schedule Control Systems Criteria CBP Center for Business Practices CBP Center for Business Practices CPI Cost Performance Index CV Cost Variance DETR Department of the Environment, Transport, and the Regions DPW Department of Public Works EAC Estimate at Complete ETC Estimate to Complete EVM Earned Value Management EVMS Earned Value Management System EVPM Earned Value Performance Management
MICHAEL VERTENTEN NOVEMBER 2008 V THE USE OF EARNED VALUE AS TREND ANALYSIS TOOL FOR CONSTRUCTION PROJECTS IN SOUTH AFRICA
OBS Organizational Breakdown Structure PERT Program Evaluation and Review Technique PIP Productivity Improvement Processes PMCS Project Management Control System PMI Project Management Institute PMP® Project Management Professional QMS Quality Management Systems SAFCEC South African Federation of Civil Engineering Consultants SPI Schedule Performance Index SV Schedule Variance NVB S Work Breakdown Structure
APPENDIX
Appendix A — Example of Questionnaire
MICHAEL VEICIT:NTLIN NOVEMBER 2008 VI THE USE OF EARNED VALUE AS TREND ANALYSIS TOOL FOR CONSTRUCTION PROJECTS IN SOUTH AFRICA
CHAPTER 1: INTRODUCTION
1.1 PROLOGUE
Earned Value Performance Management (EVPM) is designed to give senior management an accurate overview of Programme/Project performance. It builds on information provided by traditional scheduling techniques to plan and measure the overall productivity of a system or project. On an industry wide basis, there are many "project management" successes reported. Unfortunately, most serious studies indicate there are significantly more failures than successes. Some industries such as software, electronics and administration experience project failure rates as high as 90% with projects completed late and/or over budget or failing to meet client expectations or requirements. So the answer is a resounding NO — most projects don't succeed. EVPM is used to facilitate responsible decision-making by providing a valid, timely and auditable control system, which is capable of: reporting work progress; properly relating cost, schedule and technical accomplishments; supplying managers with practical summary information; establishing management systems and procedures, which effectively meet requirements and control performance; providing a basis for continuous improvement in management control systems leading to better internal operations. There are three reasons to use EVPM. Firstly, when there is a need to improve the quality of the project management process. Secondly, to establish accountability for project completion and ensure progress requirements are being achieved. Thirdly, to open up the project information flow so that all parties know what is happening. The construction industry is a very competitive and highly project orientated environment where time and money is of the essence and the challenge of getting every project within schedule and budget is of great importance. A project sponsors and stakeholders main aim is to see that a project is completed within time and budget, therefore Project Control is of great importance and any tool available to achieve greater control should be used. Traditionally a form of Earned Value is being used in the construction industry in the form of the old Cost/Schedule Control Systems Criteria (C/SCSC) originally defined in the USA in 1967.
MICHAEL VERTENTEN NOVEMBER 2008 "ITIE USE OF EARNED VALUE AS TREND ANALYSIS TOOL FOR CONSTRUCTION PROJECTS IN SOUTH AFRICA
Earned Value Management (EVM) is a proven process that has become widely recognized and accepted for managing projects. It provides early insight into developing trends, indicative of both problems and opportunities within a project and allows Project Managers to focus attention where it is needed and to develop corrective action where necessary. [2] There have been many misconceptions about Earned Value, namely: "Earned Value is useful only on large government-funded contracts." "Earned Value is useful only on cost-reimbursable type projects." "Earned Value has no utility in the management of lump-sum or firm fixed-price work." "Earned Value does nothing for construction projects." The basic utility of Earned Value is to contain the cost risks associated with projects. Bad news never gets better with time. The earlier one knows that there is a problem on a project, the better chance there will be to mitigate that problem. [1] Although the concept of Earned Value has been around for many years, the application thereof here in South Africa has not been widely implemented. Companies are becoming more aware of its capabilities in determining early warning signs to problems on projects and are therefore insisting more and more on the use of EVM on projects. Although it is being used by Management and Engineers to control projects, Contractors seem to be shying away from using it because of the time needed to set it up properly and also because not very many contractors are aware of the concept of Earned Value. 1.2 THE PROBLEM
A project has a beginning and an end and every Project Manager wants his project to come in on time and within budget but very often the projects falter by either coming in over time or over budget, the trick is to be able to control the project effectively. Every Project Manger believes they have put into place the best controls methods but yet their projects still fail - enter Earned value Management. Many Construction Project Manager's do not recognize the benefit of using Earned Value to pinpoint the problem areas at an early stage in the life of the project. An interesting phenomenon exists in the construction industry. The industry probably uses parts of Earned Value management about as well as any industry, but what makes it interesting is that in construction work, the term "Earned Value" is rarely used. Often, they do not even realize that they are in fact using a form of Earned Value. Anytime a construction cost engineer puts a project baseline plan in place, this is Earned Value in its purest form. But ask cost engineers if they use Earned Value management and often you will get a negative response. The practice today for Project Managers is to manage Cost Control in a Microsoft Excel spreadsheet format or to use some Cost Control software package for managing project cost and to use the Gantt
MICHAEL VERTENTEN NOVEMBER 2008 2 IE USE OF EARNED VALUE AS TREND ANALYSIS TOOL FOR CONSTRUCTION PROJECTS IN SOUTH AFRICA
Chart via a Scheduling software package for managing schedule performance. Seemingly, they are managed as separate, independent, depaitnients and entities. It is a known fact that project cost and schedule are interrelated, but we have no facility to make direct connection between the two. [3]
1.3 RESEARCH OBJECTIVES
The most important aspect of this research is to determine whether the concept of Earned Value, as it is known today, is being used within the South African construction industry or not. A questionnaire was developed and circulated to Project Managers and those involved in Project Controls within the industry with the aim of the questionnaire being to determine whether or not the concept of Earned Value is used in determining the status of projects and if it is used for reporting purposes or not. This dissertation is a combination of research based on various websites and publications, case studies of problems experienced on projects (highlighted during discussions with Project Managers, Project Control Managers, Cost Engineers and Schedulers involved in the Engineering, Building and Mining Construction and Consulting industry) and 15 years experience in the consulting and construction industry of which 8 are involved with Project Controls. It is the objective of this dissertation not to criticize the manner in which the construction industry manages projects and it is not to say that the construction industry does not use the Earned Value concept but to merely determine whether the concept of Earned Value is being used properly within the construction industry. 1.4 RESEARCH DESIGN
In order to fulfill the needs of a research proposal, one has to follow a structured research design plan. This plan usually constitutes the different phases of the research and how it should be implemented. In chapter one the research proposal and the introduction to the dissertation are discussed. Chapter two discusses the construction industry, the way the industry has developed and the future of the industry. This chapter also discuses the way the construction industry controls and manages its projects. Chapter three discusses Project Management and Project Control. A brief history of Project Management and its importance in managing projects as well as the effects and importance of a well defined and managed Project control system. Chapter four will discuss the concept of Earned Value. A brief history of how it evolved, its use in effectively controlling projects and its concept. Chapter five will discuss the results of the research to this dissertation, the questionnaire put out to the various Project personnel and the results of those questionnaires received back. Chapter six will discuss the conclusion to the dissertation and will determine whether or not the concept
MICHAEL VERT{ IVTEN NOVEMBER 2008 3 THE USE OF EARNED VALUE AS TREND ANALYSIS TOOL FOR CONSTRUCTION PROJECTS IN SOUTH AFRICA of Earned Value as determined in Chapter four is being used in the construction industry or not. 1.5 CONCLUSION
This dissertation will mainly focus on the concept of Earned Value and its importance in controlling a project within the South African construction industry. It focuses mainly on the construction industry to determine whether the Earned Value concept is being used to effectively control projects and to point out the importance of using the Earned Value concept in controlling projects. In the next chapter, the construction industry will be discussed and how the construction industry controls its projects. Various references to literature will be made in order to establish what the current norm is when it comes to project control.
MICHAEL VERTENTEN NOVEMBER 2008 4 CI IE USE OF EARNED VALUE AS TREND ANALYSIS TOOL FOR CONSTRUCTION PROJECTS IN SOUTH AFRICA
CHAPTER 2: CONSTRUCTION INDUSTRY
2.1 INTRODUCTION
Construction covers the preparation of sites and the construction of buildings and civil engineering structures, including heavy infrastructure and essential services. The construction sector spans a wide range of activities, from the building of a single domestic unit to the construction of a highway, dam or harbour silo. Site preparation includes the demolition of buildings or structures, and excavating, leveling or test drilling or new structures. Building covers the erection of family housing and residential buildings, as well as office blocks, shopping complexes, schools, hospitals and industrial buildings. Civil engineering works include steel, mechanical and electrical construction needed in the development of transport infrastructure, water storage, reticulation and sewage systems, power lines, fuel tanks, mine headgears and bins, bunkers or silos. Economic and population growth are the most important indicators of construction patterns. They point both to a country's increasing needs and to its ability to provide for those needs. The construction economy has short cyclical fluctuations from peak to peak, as well as long "waves." Comparative studies of developing economies show that construction works represent a steadily growing share of gross domestic expenditure over time, and as levels of development improve. However development patterns can be disturbed by specific factors. Studies in South Africa, for example, have identified four key drivers of future construction activity: economic growth, savings, government economic policies and institutional health - namely the degree to which organizations and state institutions function and are able to implement state policies and spend allocated state expenditure budgets. In addition, state policy in South Africa is to promote the emergence of new contracting and consulting capacity, with the result that many large construction projects are split into numerous small contracts and awarded to select emerging firms. Work in Latin America has identified unsustainable macro-economic policies and bureaucratic or institutional deficiencies as the main reasons for the failure of developing economies — and difficulties in the construction sector. Construction companies increasingly seek international opportunities when local economies contract. [4] 2.2 MEASURING PERFORMANCE
With increasing higher users' requirements, higher customers' requirements, environmental awareness and limited or merger resources on one side, and high competition for construction business marketplace on the other side, contractors have to be capable of continuously improving their performance. However, effective and efficient management of contractors' organizational performance requires commitment to