Maintaining Traffic During the Gerald Desmond Bridge Replacement Project Long Beach CA  Prepare the Detour Plans for multiple stages of construction  Prepare the Traffic Impact Study which identified impacts of detoured traffic during construction  Prepare design plans for temporary traffic signals and temporary lighting  Provide Traffic Control Manager services until project completion

 The 4.5 Square Mile Island lies on San Pedro Bay, approximately 20 Miles south of Downtown LA  Primary Land Uses are Port of Long Beach (POLB), Port of (POLA) and a Federal Prison  Supports 50% of POLB and POLA Terminal Capacity and 60% of the On Dock Intermodal Capacity  Containers are either loaded on trucks (85%) or on rail cars (15%)

◦ Three Vehicle Bridges Provide Access

◦ Gerald Desmond-direct connections to the Long Beach Freeway (I-710) and to Downtown Long Beach

◦ Schuyler Heim-connection to the Alameda Corridor and San Diego Freeway (I-405)

◦ Vincent Thomas-direct connection to the Harbor Freeway (I-110)

Gerald Desmond Schuyler Heim

Vincent Thomas

Vincent Thomas Bridge Existing Schuyler Heim Bridge New Schuyler Heim Bridge

 Opened in 1968  Originally a 4 lane bridge with a pedestrian walkway  Later modified to accommodate 5 lanes-3 climbing lanes merge to 2 lanes near the top of the bridge in both directions  Provides 155 feet of vertical clearance over the Cerritos Channel to the Back Bay  PM Peak Hour volumes of up to 3,400 vehicles and 850 trucks (both directions) Gerald Desmond Bridge-Looking West

Gerald Desmond Bridge-Looking East

 Design-Build Project began in 2012  Will have 6 lanes, a bike path/pedestrian walkway and scenic overlooks  Will provide 205 feet of vertical clearance over the Cerritos Channel  Currently planned to open in March 2018  Current estimated cost is $1.4 B New Gerald Desmond Bridge Bike Path, Pedestrian Walkway & Scenic Overlooks Progress as of June 30, 2015-West End

East End

 Began in September 2012  Used counts taken in 2010 factored to 2012  Converted trucks to PCE’s  Assumed no diversions to alternate routes  Calculated AM/PM Peak Hour LOS at 4 intersections on the west side for existing and 10 stage construction scenarios  LOS E acceptable (LOS F with POLB approval)  Mitigations were primarily signal timing changes  Still expect 10 Separate LOS F Scenarios

 Calculated AM/PM Peak Hour LOS at 6 existing intersections and 1 future temporary intersection on the east side for existing and 6 stage construction scenarios  Mitigations were primarily temporary signals and signal timing changes  Were able to mitigate all locations to LOS E or better  TMP with MOT Traffic Analysis approved in November 2013 Study Intersections

Detour W1  Began in early 2014  Expected duration: 15 months  Estimated AM/PM Peak Hour traffic volumes being detoured - 275/140  Calculated worse case peak hour operating conditions was LOS E Pier T Off Ramp Demo

Detour E1

 Provided a second free right turn lane from the SB I-710 Off Ramp to Pico Avenue  Restriped Pico Ave from 4 to 5 lanes (to provide 3 SB lanes) and installed a temporary signal at Pico Avenue/Pier D Street  Installed wireless interconnect on Pico Avenue between the existing signal at Pier C Street and the temporary signal at Pier D Street  Implemented signal timing changes to favor the SB through movement on Pico Avenue

 Went in effect in May 2014  Expected duration: 23 months  Estimated AM/PM peak hour traffic volumes being detoured onto Pico Avenue - 1225/1000  Calculated worse case peak hour operating conditions was LOS D  Based on a recent peak hour count of vehicles SB on Pico Avenue at Pier C Street, there has been negligible diversion of the detour traffic to other routes SB I-710 to WB Ocean Blvd Connector Demo

Detour E2

 Expected duration: 6 months  Estimated volume of AM/PM Peak Hour traffic being detoured - 960/990  Calculated worse case peak hour operating conditions was LOS D Detour E3

 Expected duration: 6 months  Estimated volume of AM/PM Peak Hour traffic being detoured – 1200/1575  Calculated worse case peak hour operating conditions was LOS E Detour E4

 Expected duration: 9 months  Estimated volume of AM/PM Peak Hour traffic being detoured – 1925/1750  Calculated worse case peak hour operating conditions was LOS E Detour W4

 Expected duration: 2 months  Estimated volume of AM/PM Peak Hour traffic being detoured – 2130/2570  Calculated worse case peak hour operating conditions was LOS F Detour Experience to Date Detour E1

Pico Avenue SB Ramp to WB Ocean Blvd

After After Before After After Pontoon Bridge-1944 to 1968