Annexure: A DETAILS OF CONTRACTS PLACED BY OPEN TENDER (For Civil Engg. /Elect. Engg. /S & T/Mech. etc works) (Status for the Month of APRIL 2017 - AUGUST 2017)

Works Awarded : APRIL 2017

Quantity Rate Scheduled S. Tender Date of LOA No. Contractor’s Name (for supply contract)/ (for supply contract)/ Value of Description of Item/ Work Estimated Cost (For Tendered Cost (For completion N. No. opening and date and address Contract Engg./Elect. /S&T/ Mech. Engg./Elect./S&T/ date etc Works) Mech. etc Works) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

1 IRCON/ME 15.12.2016 Design, Supply, Installation IRCON/MECH/10 M/s J S Industries 875 Nos Flat `1,99,27,646/- `1,99,27,646/- From the CH/1029/RE and Commissioning of 875 29/RE/MCF RBL- 16/2 Mathura Road, /MCF RBL- Pallets GAD II/ Flat Nos Flat Pallets at Modern II/ Flat Pallet/302 (Karkhana Bagh), approval- Pallet/302 Coach Factory at Lalganj, Rae /7578 Faridabad-121002 04 Month Dated Bareli, U.P. Dated 06.04.2017 Ph : 0129-2296606, 23.11.2016 4100510, Telefax : (for first 440 0129-2282345: Nos Pallets [email protected], 02 month [email protected] and balance 435 within 04 month)

2 IRCON/ 12.04.2017 Construction of Retaining IRCON/ 3017/ M/s. PMNR ` 587.62 Lakh At par ` 587.62 Lakh 06 months 3017/ Wall for PUP approach at SGTL/ Tender/ Constructions, House from the SGTL/ Tender/ Badarwa Byepass on NH-3 Retaining No. 7-58/2, Subhash date of Retaining for IRCON SGTL (Agreement Wall/339 Nagar IDA Jeedamatla issue of Wall/339 No. ISGTL/ CO/ SG/ IRCON/ Dated 12.04.2017 Hyderabad – 500 055 LOA Dated CORRES/ 02 dtd.02.09.2015) Telangana. 01.04.2017 in connection with “4-Laning Mob.+919550571711 of Shivpuri-Guna section of NH-3 Contd.../- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

3 IRCON/ 17.03.2017 Supply of 500KVA 3PH Silent IRCON/3017/ M/s. Deccan Sales & ` 8.62 Lakh 14.67% ` 7.36 Lakh 05 months 3017/ SGTL/ D.G. Set on monthly hire basis SGTL/MECH. Service (P) Ltd., 276/3, Below from the MECH./Hiring /500KVA for operation of Metso make /Hiring/500K GIDL Industrial Estate, Estimate date of D.G./NIT- 200TPH Crushing Plant at VA D.G./NIT- Makarpura – 390010, issue of 2126, Date Shivpuri-Guna Highway Project 2106/W.O., Vadodara. LOA 17.03.17 Dated Ph. 9327406915 06.04.2017

4 IRCON/207 07.03.2017 Execution Of 25kv Ohe Works IRCON/2070/ M/s KAMY , `1,59,96,599/- 18.99% ` 1,90,34,353/- 06 Months 0/NMDC/- For The Proposed Block Station NMDC/-PKG 66 1st Floor Above from the PKG IV/OHE Yard In Connection With IV/OHE Sushma Building, date of WORKS/2A Construction Of Private Railway WORKS/2A, Jaripatka Nagpur-14, issue of , 02.02.17 Siding For The Proposed 3 MTPA Dated Ph:0712-2593227, LOA Integrated Steel Plant For NMDC 13.04.2017 [email protected] At Nagarnar, Chhattisgarh State m

5 IRCON/2050/ 08.02.2017 Design, supply, installation, IRCON/2050/ M/s SS Rail Works Private ` 6.85 Crores 3.58 % ` 7,10,36,385.35 06 months BGL.JBB/S& testing and commissioning of BGL.JBB/S& Limited, H.No. 8-3- Above from the T/TENDER/0 4 Electronic Interlocking based T/TENDER/0 318/6/13/5 Flat No. 203, date of Dated signalling system at Jaynagar 4/217, Crystal Residency, Jaya issue of 10.01.2017 (Indian Custom Yard) station and Dated Prakash Nagar, Yellareddy LOA existing Jaynagar Station of ECR 26.04.2017 Guda, Hyderabad-500073 alongwith modificayion work in existing Jaynagar station and provision of 6-Quad +OFC Communication system between Inarwa - and Jaynagar

6 IRCON/ME 08.02.2017 Design, Supply, Installation and IRCON/MECH/ M/s Science tech ( India) 01 No Heating ` 1237600 ` 12,37,600/- 02 Month CH/1029/R Commissioning of 01 No Heating 1029/RE/MCF 278/39/2 ( Below Aishbagh E/MCF Oven for PVC form issue Oven for PVC Roll and 03 Nos RBL-II/ Flyover) Aishbagh, RBL-II/ Heating Oven Roll and 03 of LOA. Heating Heating Oven for SIKA at Lucknow -226004(u.p.) Oven for for PVC & Nos Heating Modern Coach Factory at Lalganj SIKA/311/RET/ Ph 0522-4113193, PVC & Rae Bareli, U.P. [email protected] Oven for SIKA SIKA/311/R 7619, ET Dated Dated 18.01.2017 26.04.2017 Contd.../- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

7 IRCON/301 12.04.2017 Construction of civil works for double IRCON/3018 Jalaram Projects Private `40.94 Crores ` 36.85 ` 36.66 Crores 15 Months 8/DFCCIL- line railway involving formation in /DFCCIL- Limited 401 Vitthal Villa , Crores from the CTP-12/e- Tender/ Embankments/ Cuttings, Bridges CTP-12/08- Near Satadhar Circle date of Infra work / and Structures. Project Chainage: 35/914 dated Thaltej, Ahmedabad issue of Package:SS 216/(23-25) to Chainage :229/(9-11), 28.04.2017 Gujarat LOA 4-B rev (Length=13.341KM)for Infra work package -SS 4 – B.

8 IRCON/301 12.04.2017 Construction of civil works for double IRCON/3018 Jalaram Projects Private ` 68.28 Crores ` 62.37 ` 62.05 Crores 15 Months 8/DFCCIL- line railway involving formation in /DFCCIL- Limited 401 Vitthal Villa , Crores from the CTP-12/e- Tender/ Embankments/ Cuttings, Bridges CTP-12/08- Near Satadhar Circle date of Infra work / and Structures. Project Chainage : 35/915 dated Thaltej, Ahmedabad issue of Package:SS 196/(15-17) to Chainage:216/(23- 28.04.2017 Gujarat LOA 4-A/rev 25), (Length=20.268KM) for Infra work package -SS 4 – A.

9 IRCON/301 22.04.2017 Hiring of Light Vehicles for Gujarat IRCON3018/ M/s Shree Sai Travels. ` 0.36 Crores ` 0.36 ` 0.39 Crores 12 Months 8/DFCCIL- Section of Western Dedicated DFCCIL- 68-75/4, Ranchhod Park Crores from the CTP-12/ST- TDR/ Freight Corridor, Phase II (Vaitarana CTP12/ST- Society,Ramnagar, Rander date of LV- – Sachin Section). TDR/218, Road,Surat 395 005 issue of HIRE/218 Dt:28.04.17 LOA Dated 31.03.2017

10 IRCON/301 12.04.2017 Construction of civil works for double IRCON/3018 Jalaram Projects Private `68.85 Crores ` 61.11 ` 60.80 Crores 15 Months 8/DFCCIL- line railway involving formation in /DFCCIL- Limited 401 Vitthal Villa , Crores from the CTP-12/e- Tender/ Embankments/ Cuttings, Bridges CTP-12/08- Near Satadhar Circle date of Infra work / and Structures. Project Chainage: 35/916 dated Thaltej, Ahmedabad issue of Package:SS 229/(9-11) to Chainage :252/(25-27), 28.04.2017 Gujarat LOA 4-C rev (Length=21.859KM) for Infra work package -SS 4 – C Works Awarded : MAY 2017

Quantity Rate Scheduled S. Tender Date of LOA No. Contractor’s Name and (for supply contract)/ (for supply contract)/ Value of Description of Item/ Work Estimated Cost (For Tendered Cost (For completion N. No. opening and date address Contract Engg./Elect. /S&T/ Mech. Engg./Elect./S&T/ date etc Works) Mech. etc Works) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

1 IRCON/CC/e 24.03.2017 Assembling, Laying and linking IRCON/CC/e- M/s Pee Pee Manda - - ` 17,70,97,296/- 09 months -TN/JBRLP of Broad gauge railway track TN/JBRLP/2050/1 Projects Pvt. Ltd, Kh no. from the /2050/17/15/ 2 for main line & loop line with 60 7/15/2/719 219 GF, Prahalad Vihar, date of Dated Kg rails & PSC sleepers with Dated 01.05.2017 Ext. Phase-z, Gupta issue of 03.03.2017 contractor's own P. Way Colony, Vill- Prahladpur LOA material (except 60 Kg rails & Banger, Delhi-110042. PSC 60 Kg sleepers) and other Tel :- 011-65825861, allied works in Nepal side Email:peepeemandal@y between Km 2+975 Jaynagar ahoo.com to Km 34+900 Kurtha in connection with New BG Rail line from Jayanagar (India) to Bardibas (Nepal). 2 IRCON/3017 04.05.2017 Supply of crushed WMM & IRCON/3017/SGT M/s. Anil Construction ` 113.13 Lakh Item Rate ` 137.50 Lakh 60 days /SGTL/eTen Asphalt aggregates as per L/eTenders Company, from the ders /Works/WMM Required Gradation & /Works/WMM & Krishan Puram, Shivpuri, date of & Asphalt Specifications Including Asphalt M.P.– 473 551, issue of Aggregates- Transportation and unloading Aggregates-2/342 Ph. +919425136466 LOA 2/342 of aggregate at IRCON’s main Dated 09.05.2017 Dated 20.04.2017 camp near Village Bamaur, A B Road (Km 276 of NH3) in connection with “4-Laning of Shivpuri - Guna section of NH- 3 Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

3 IRCON/3018 26.04.2017 Construction of civil works for IRCON/3018/DFC Raghuvir Buildcon ` 69.74 Crores ` 62.77 Crores ` 58.98 Crores 15 Months /DFCCIL- double line railway involving CIL-CTP-12/08- Private Limited from the CTP-12/e- Tender/ Infra formation in Embankments/ 35/956 201 Jalaram House date of nd work / Cuttings, Bridges and Dated 11.05.2017 2 Floor issue of Package:SS Structures. Project Near Atmajyoti LOA S3 A/08-37, Chainage:176+240 to Ashram Ellorapark, Dated 24.03.2017 Chainage195+420 for Infra Vadodara Gujarat work package -SS 3 – A 390023. 4 IRCON/3018 26.04.2017 Construction of civil works for IRCON/3018/DFC Raghuvir Buildcon ` 53.85 Crores ` 48.47 Crores ` 45.54 Crores 15 Months /DFCCIL- double line railway involving CIL-CTP-12/08- Private Limited 201 from the CTP-12/e- nd Tender/ Infra formation in Embankments/ 35/955 Jalaram House 2 date of work / Cuttings, Bridges and Dated 11.05.2017 floor Near Atmajyoti issue of Package:SS Structures. Project Chainage: Ashram Ellorapark, LOA 3 -B/08-38, 1+083 to Chainage :19+813, Vadodara Gujarat 24.03.2017 forInfra work package -SS3– B. 390023. 5 IRCON/S&T/ 03.04.2017 Supply of Railway Signalling & IRCON/S&T/2059C M/s Sriram Cables Pvt. ` 6,88,72333.71/- Item rate ` 6,74,78,280/- 4 Months 2059C/CGR Telecom Cable as per Latest /EC. Ltd. A-524, RIICO from the P.EC.Execu./ TENDER/PK RDSO Specification for EXECU./TENDER/ Industrial Area, date of G-II/1 Kharsia-Gharghoda section of PKG-II/I Chopanki (Bhiwadi)- issue of Dated CERL Project (Package-II) Dated 12.05.2017 301707, Distt., LOA 11.03.2017 (Chhattisgarh). Alwar,Rajasthan 6 IRCON/S&T/ 03.04.2017 Supply of Railway Signalling & IRCON/S&T/2059C M/s Tirupati ` 12,90,720,32/- ` 10,91,939.88/- 4 Months 2059C/CGR Telecom Cable as per Latest /EC.EXECU./TEND Plastomatics Pvt. Ltd. from the P.Ec.Execu./ TENDER/PK RDSO Specification for ER/PKG-II / I B-141(A00000000), date of G-II/I Kharsia-Gharghoda of CERL Dated 12.05.2017 Road No. -9-D, V.K.I. issue of Dated Project (Package-II) Area, Jaipur-302013, LOA 11.03.2017 (Chhattisgarh). Rajasthan (India) 7 e.Tender- 27.02.2017 Design, Supply, Installation, IRCON/S&T/2059C M/s Angelique ` 13,74,45,090/- ` 13,00,00,879/- 10 Months IRCON/2059 Testing & Commissioning of /CGRP.EC.EXECU International Limited, from the /S&T/TENDE R/PKG-I/I Electronic Interlocking based ./Tender/PKG-I/I 104-107 Hemkunt date of Dated Signalling System at Three Dated 12.05.2017 Tower Ist Floor,98 issue of 02.02.2017 Stations between Kharsia- Nehru Place, LOA Gharghoda for CERL Project New Delhi -110019 Chhattisgarh (Package-I). Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 8 IRCON/2048 24.03.2017 Supply, Installation, Testing & IRCON/2048/ISC- M/s Godrej & Boyce ` 5.12 Crores ` 5.12 Crores ` 62754850.07 05 months /ISC- Commissioning Accoustic , BEHALA/TENDE Mfg. Co. Ltd., from the BEHALA/TE NDER/ACO Audio, and video, telephone R/ACOUSTICS/G Plot No. 30, Block GN, date of USTICS/201 and LAN including interior ODREJ/25422/18 Sector V, Salt Lake City issue of 7/39 Dated system for New sports 3 Kolkata-700091 LOA 17.02.2017 Complex of Eastern Railway at Dated 18.05.2017 Ghoslapur Behala, Kolkata, W.B 9 IRCON/S&T/ 23.03.2017 Supply of Signalling & Telecom IRCON/S&T/2050 M/s Vindhya Telelinks ` 59,62,722/- Item Rate ` 58,95,693.75 4 Months 2050/BGL.JB Cable for Jaynagar-Bardibas /S&T/TENDER/09 Ltd. OFC Unit, Plot from the B/S&T/TEND ER/09/ Section (Indian Portion) as per /1252 No.1-C & 1-D, Udyog date of Dated Latest RDSO Specification. Lot Dated 19.05.2017 Vihar, P.O. Chorata, issue of 01.03.2017 No-1&3 Rewa-486006,MP(India) LOA 10 IRCON/S&T/ 23.03.2017 Supply of Signalling & Telecom IRCON/S&T/2050 M/s CMI Ltd. 501- ` 1,00,25,260/- Item Rate ` 1,04,63,775/- 4 Months 20 Cable for Jaynagar-Bardibas //BGL.JBB/S&T/T 503,New Delhi House, from the 50/BGL.JBB/ S&T/TENDE section (Indian Portion) as per ENDER/09/1253 27,Barakhamba Road, date of R / 09/ Latest RDSO Specification-Lot Dated19.05.2017 New Delhi-110001. issue of Dated No-2 LOA 01.03.2017 11 IRCON/S&T/ 23.03.2017 Supply of Signalling & Telecom IRCON/S&T/2050 M/s Tirupati ` 13,16,948/- Item Rate ` 12,72,950.56/- 4 Months 2050/BGL.JB Cable forJaynagar-Bardibas /BGL.JBB/S&T/TE Plastomatics Pvt.Ltd. B- from the B/S&T/TEND ER/09 Section (Indian Portion) as per NDER/9/1254 141(A),Road No.9-D, date of Dated Latest RDSO Specificatation. Dated 19.05.2017 V.K.I Area,Jaipur- issue of 01.03.2017 Lot No-1&4 302013,Rajasthan(India) LOA 12 IRCON/ 22.04.2017 Supply, Installation, Testing, IRCON/ 3017/ M/s. Comvision India ` 430 Lakh Item Rate ` 321.79 Lakh 05 months 3017/ SGTL/ Commissioning, Training, SGTL/ eTender/ Pvt. Ltd., 39, Hartron from the eTender/ Toll Plaza Warranty and Comprehensive Toll Plaza Complex, Electronic date of Equipment/ Maintenance of 12 Lane toll Equipment/ 336 City, Sector – 18, issue of 336 Plaza (2x6) Equipment on NH- Dated 20.05.2017 Gurgaon–122015( India) LOA Dated 3 for IRCON SGTLin Mob: +919971999056 06.03.2017 connection with “4-Laning of Shivpuri-Guna section of NH-3 from Km.236+000 to Km. 332+100 (Ch.0+000 to Ch.85+310) in the State of Madhya Pradesh (Stage-I) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 13 IRCON/2015/ 13.05.17 Construction of One nos. of IRCON/3015/ROB M/s.Shree Karni Traders, `3,76,59,816/- 2.21% Above- `3,84,92,098/- 11 Months ROB-RAJ/e- Low Height Subway (LHS) of -RAJ/JP/LHS- C-171, Kanta Kathuria from the TEBDER/LHS- NKT/TN- clear size 4.0 m x 2.5 m with NKT/LC-76/4814 Colony, Bikaner date of 62/2017/02 Approaches and other Dated 20.05.2017 issue of Dated associate activities as per LOA 07.03.2017 Specification, design & drawings etc. complete as per safety norms of Railways at LC no. 76, Neem ka Thana using Cut & Cover technique with Relieving Girders as well as box pushing technique in Rajasthan State. 14 IRCON/S&T/ 23.03.2017 Supply of Signalling Cables IRCON/S&T M/s Vindhya Telelinks ` 2,36,02,693/- Item Rate ` 2,25,74,100/- 6 Months 2050/BGL.JB for Jaynagar-Bardibas /2050/BGL.JBB/S Ltd. OFC Unit, Plot No- from the B/S&T/TEND ER/10 dated section (Nepal Portion Part- &T/TENDER/10/1 1C & 1-D, Udyog Vihar, date of 01.03.2017 1). Lot No-1&3 258 Dt:.22.05.17 P.O.Chorhata,Rewa issue of PIN: 486 006 M.P.(India) LOA 15 IRCON/S&T/ 23.03.2017 Supply of Signalling Cables IRCON/S&T/2050 M/s Tirupati ` 46,27,067/- Item Rate ` 43,22,048.79/- 6 Months 2050/BGL.JB for Jaynagar-Bardibas /BGL.JBB/S&T/TE Plastomatics Pvt.Ltd. from the B/S&T/TEND ER/10 dated section (Nepal Portion Part- NDER/10/1257 B-141 (A), Road No-9-D, date of 01.03.2017 1). Lot No-1&4 Dtd.22.05.2017 V.K.1 Area,Jaipur- issue of 302013,Rajasthan(India) LOA 16 IRCON/S&T/ 23.03.2017 Supply of Signalling cables IRCON/S&T/2050 M/S Sriram Cables Pvt. `1,89,62,100/- Item Rate `1,89,75,000.00 6 Months 2050/BGL.JB for Jaynagar –Bardibas /BGL.JBB/S&T/TE Ltd. A-524,RIICO, from the B/S&T/TEND ER/10 dated Section( Nepal Portion Part- NDER/10/1256 Industrial Area, date of 01.03.2017 1). Lot No-2 Dtd. 22.05.2017 Chopanki (Bhlwadi)- issue of 301707,Alwar Rajasthan LOA 17 IRCON/3018 10.04.2017 Construction of Engineers IRCON/3018/DFC Uni Construction B/29 ` 0.66 Crore ` 0.66 Crore ` 0.79 Crore 180 days /DFCCIL- office at valsad CIL-CTP-12/ST- shyam Shundar Society from the CTP-12/ST- TDR/ENG- TDR/ENG- Near Swamy Narayn date of OFF/217 OFF/217/337, School Ramanagar issue of dt:10.04.17 Dtd. 25.05.17 Surat 395005 LOA Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 18 IRCON/3018 17.05.2017 Supply of Equipment for IRCON M/s EIE Instruments Pvt ` 12.47 lakh Item Rate ` 12.31 Lakh 60 days /DFCCIL- Laboratory. /3018/DFCCIL- Ltd,B-14 Zaveri Industrial from issue CTP-12/08 /Lab CTP-12/lab Estate Opposite Shyam of LOA Equip/08-49, Eqipment/08-49 Villa Singarva Kathwada Dt:16.05.17 /991Dt:22.05.17 Road Kathwada Ahmedabad 19 IRCON/1034 09.03.2017 Transportation of Bulk Bitumen IRCON/1034/BPH M/s Shri Vijyalakshmi 750 MT for Camp- 750MT @ ` 12645820/- 12 months /BPHP/TN/Tr Emulsion slow setting (SS-1) P/TN/Transport of Transports, No. 54 1 & 350MT for `11382.80 from the ansport of Bitu Emul from IOCL Chennai refinery to Bitu Emul SS- Shastri Nagar (Extn.), Camp -2, Estt. 350MT@ date of SS-1/NIT IRCON HMP site at Km 1/NIT ET-116/337 Kolathur Chennai- Cost – `11739.20 issue of ET-116, 45+600 to Km 127+000 on NH- Dtd. 24.05.2017 600099, Mob: `1,20,16,450/- LOA Dtd. 15 of Bikaner-Phalodi Section 9444004599, email: 14.02.2017 of NH-15 in the State of [email protected] Rajasthan. 20 IRCON/J&K 27.04.2017 Strengthening and Upgrading IRCON/J&K M/s TRG Industries Pvt. ` 41,64,48,700.89 19.08% ` 33,69,90,288.76 14-months Cell/JAT/14/10 of Access Road from Harog to Cell/JAT/14/1014/K Ltd., E-461, Greater below from the 14/K-B/Pkg:T- 48 Road- Sumber via Meghdar Kohli -B/Pkg:T-48 Road- Kailash-II, New Delhi- date of R/359/ Approx. 24.00km Long R/359/1913 110048 issue of Dated: Connecting Harog Meghdhar Dated: 24.05.2017 LOA 22.03.2017 Kohli Sumber on Katra Section of Rail Link Project and Kashmir 21 IRCON/3018 10.04.2017 Hiring of Light Vehicles for IRCON3018/DFC M/s Ramakrishna ` 0.51 Crore ` 0.51 Crore ` 0.58 Crore 12 months /DFCCIL- Gujarat Section of Western CIL-CTP12/Hiring Rajaram Tiwari 104/B from the CTP- 12/Hiring of Dedicated Freight Corridor, of Vehicle , Sukhasagar Co Op date of Vehicle Phase II (Vaitarana – Sachin Dtd.27.05.2017 Housing Society Jui issue of Section).-Maharastra Section Nagar Navi Mumbai LOA 22 IRCON/2053 28.04.2017 Construction of Pit line, IRCON/2053/SHM M/s Sudarshan ` 17.54 Crores ` 16.34Crores ` 20.97Crores 12 months /TN/SHM Stabling Line including Supply /SHM /PIT LINE & Sengupta & Sons, PO- from the /PIT LINE AND Fixing Spreading of P. Way PF/SS/213, Inda Kharagpur-721305, date of PF/2017/40 materials and Ballast, Linking Dated 27.05.2017 Dist. Paschim Midnapur, issue of Dated of Track, RCC Pit etc. and W.B. LOA 06.04.2017 Refurbishing of existing Platforms at Shalimar near Howrah for SE Rly in WB. Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 23 IRCON/ME 22.12.2016 Supply, Erection, Testing, IRCON/MECH/10 M/s Gostel TST d.d. Full Set of `23.86 Crores ` 23.86 Crores 270 Days CH/1029/RE Commissioning & Prove Out 29/RE/MCFRBL- Ciginj 63, SL-5220 /MCF/RBL- Blasting Plant from II/Basting of Stainless Steel CutwIRE II/Blasting Tolmin, Slovennia opening of Plant/314 Blasting Plant for Railway Plant/314/7770 LC Dated Coaches for Modern Coach Dated 29.05.2017 10.11.2016 Factory at Rae Bareli 24 IRCON/103 24.01.2017 Supply of Blue/Black Hard IRCON/1034/BPH M/s Shri Balaji Minerals, 146383 MTof I ` 118876960/- 12 months 4/BPHP/TN/ stone Trap/ Basalt or P/TN/NITET110/ 106 Ashoka Apartment, from the NITET110, different sizes/ Dated equivalent quality angular Supply of Road No. 2, Maan Naga, Estimated Cost – date of 21.12.2016 quality crushed aggregate aggregate/345, Jhunjhunu, issue of ` 8,95,56,185/- from three stage Crushing Dated 29.05.17 Mob:09829525725 LOA Plant fitted with VSI and materials confirming to the MORTH Specification (5th Revision) for Asphalt work at IRCON’s Camp-1 at Km 45+600 of NH-15 near Techri Phanta, Kolayat in connection with “Widening and Strengthening of existing Bikaner-Phalodi Section to of NH-15 in the State of Rajasthan” 25 IRCON/ 06.05.2017 Fabrication, supply & erection IRCON/ 3017/ M/s Indian Construction, ` 69.24 Lakhs Sch. A = ` 82.34 Lakh 06 Months 3017/ of Toll Plaza Canopy (Space SGTL/ Tender/ Flat No. 30,Rail Vihar, 24.10% above from the SGTL/ Tender/ Toll Frame) and Bus Shelters on Toll Plaza Canopy Sector - 33,NOIDA (UP), Sch. B = date of Plaza NH-3 for IRCON SGTL & Bus Shelter/ Ph. +919873011640 14.20% above issue of Canopy & (Agreement No. ISGTL/ CO/ 338, LOA Bus SG/ IRCON/ CORRES/ 02 Dated 29.05.2017 Shelter/338 Dated dtd.02.09.2015) in connection 05.04.2017 with “4-Laning of Shivpuri- Guna section of NH-3 from Km.236+000 to Km. 332+100 (Ch.0+000 to Ch.85+310) in the State of Madhya Pradesh( Stage-I) Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 26 IRCON/J&K 28.04.2017 Construction of Foundation IRCON/J&K Cell M/s TRG Industries Pvt. ` 23,57,24,862.55 47.20% ` 34,69,86,997.67 16 months Cell/JAT/14/10 Substructure and /JAT/14/1014/K- Ltd.,E-461, above from the 14/K-B/Br. 138-R/ 365/ Superstructure including Civil B/Br. 138-R/ Greater Kailash-II, date of Dated: Works Supply Fabrication 365/1924, New Delhi – 110 048 issue of 22.03.2017 Assembly, Erection and Dated: 29.05.2017 LOA Launching of Superstructure for Railway Bridge No. 138 and Road Bailey Bridge between T 74 and T 77 on Katra Banihal Section of Udhampur Srinagar Baramulla Rail Link Project Jammu and Kashmir. 27 IRCON/1014/J 27.04.2017 Construction of 16 units of IRCON/1014/J&K/ M/s Mohammad ` 3,57,68,150.00 14.00% ` 4,07,75,691.00 15 months &K/K- Type-III ( Double Storied) K-B/USBRL/Pkg- Shahnawaz Beigh, above form the B/USBRL/Pkg- SQ-7 residential accommodation SQ-7/320, Mandibal, Nowshera, date of Dated: (including other allied works ) Dated: 29.05.2017 Srinagar-190005, J&K issue of 28.03.2017 at Sangaldan in IRCON LOA campus in connection with Katra-Banihal section of USBRL project (J&K) 28 IRCON/J&K 27.04.2017 Strengthening and IRCON/J&K Cell/ M/s SRM Contractor Pvt. ` 18,04,16,843.35 15.03% ` 15,33,00,191.79 12 months Cell/JAT/14/10 improvements to the existing JAT/14/1014/K- Ltd., below form the 14/K-B/T15 &T48 Adit approach road from Ch 0/390 B/T15 &T48 Adit A-1, Hill View, date of Road/A.Road/ km to 7/360 km Sangaldan to Road/A.Road/360/ Near Govt. H.S.S.S., issue of 360/ Barala for the part of approach 319, Bahu Fort, LOA Dated: road from Sangaldan to Tatsun Dated: 29.05.2017 Jammu – 180 006 (J&K) 22.03.2017 Nalah P2 of Tunnel T14 and P1 of Tunnel T15 approx. 25.47 km long and Access Road from Kanta Morh to Adit 1 T_48 Dhadam approx. 9.50 km long on Katra Banihal Section of Udhampur Srinagar Baramulla Rail Link Project Jammu and Kashmir. Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 29 IRCON/J&K- 28.05.2017 Construction of Residential & IRCON/J&K-Cell/ M/s ACE Engineering `7,97,94,466.08 5.95% ` 8,43,30,336.81 9 months Cell/JAT/14/10 Office Complex (Pre- JAT/14/1014/K- Infratech (I) Pvt. Ltd., above form the 14/K-B/Base Camp engineered building) for B/Base Camp Lane No. SIDCO date of /366/ Northern Railway and IRCON Reasi/366/502, Industries Area, Badi issue of Dated: at Reasi in connection with Dated: 30.05.2017 Brahmna, Jammu (J&K)- LOA 28.03.2017 execution of Udhampur – 180001 Srinagar – Baramulla Rail Link Project, Jammu & Kashmir. (Pkg:CampConstruction Reasi) 30 IRCON/J&K- 06.04.2017 Hiring of inspection vehicles for IRCON/J&K-Cell/ M/s Friends Sumo Taxi ` 2,77,37,327.00 11.00% above ` 3,06,92,336,97 24 months Cell/BNL/14/1 officers and Staff of Northern BNL/14/1014/K- Owners Union, Main form the 014/K- B/Vehicle- Railway associated with the B/Vehicle-NR/VH- office Near PHE date of NR/VH-23/ Project Works in connection 23/337, OFFICE, Banihal, issue of Dated: with the Construction of Katra Dated: 31.05.2017 Chareel, Distt Ramban- LOA 24.03.2017 Banihal Section of USBRL 182146(J&K) New Rail Link Project J and K. 31 IRCON/2048 15.03.2017 Supply, installation, testing, IRCON/2048/ISC- M/s KAMY India, ` 2.76 Crores ` 2.76 Crores ` 2,33,77,200/- 04 Months /ISC- commissioning including BEHALA/TENDE 66 1st Floor Sushma from the BEHALA /TENDER/EL design manufacturing of R/Electrical/KAMY Building, Jaripatka date of EC./2017/37 various Electrical Panel Boards /25423/215. Nagpur-14, Ph:0712- issue of Dated: with accessories, Internal and Dated: 2593227, LOA 08.02.2017 External Electrical wiring, LT/ 31.05.2017 [email protected] LV/ MV cables, Earthing, special lighting etc. for New sports Complex of Eastern Railway at Gholsapur Behala, Kolkata, W.B 32 IRCON/2065 24.03.17 Providing Consultancy services IRCON/2065/PPP M/s Geo Design & ` 1.67 Crore Below 20% `1.34 Crore 06 Months /PPP/Katni- for preparing GADs for /Katni-Singrauli Research Pvt. Ltd., B- from the Singrauli/Ten der-GAD- Bridges, Detailed design & /Tender-GAD- 10, Krishna Industrial date of Design drawings and other allied work Design Estate, Opp. B.I.D.C. issue of Consultancy/ as per schedule in connection Consultancy/42, Gorwa Estate, LOA 42, Dated with Proposed doubling of Dated 31.05.2017 Vadodara-390016, 23.02.2017 existing railway line between Ph: 0265-2290222, Katni-Singrauli 261 Km long of Email: West Central Railway. [email protected] Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 33 IRCON/2048 15.03.2017 Supply, installation, testing, IRCON/2048/ISC- M/s KAMY India, ` 2.76 Crores ` 2.76 Crores ` 2,33,77,200/- 04 Months /ISC- commissioning including BEHALA/TENDE 66 1st Floor Sushma from the BEHALA /TENDER/EL design manufacturing of R/Electrical/KAMY Building, Jaripatka date of EC./2017/37 various Electrical Panel Boards /25423/215 Nagpur-14, Ph:0712- issue of Dated with accessories, Internal and Dated 31.05.2017 2593227, LOA 08.02.2017 External Electrical wiring, LT/ [email protected] LV/ MV cables, Earthing, special lighting etc. for New sports Complex of Eastern Railway at Gholsapur Behala, Kolkata, W.B 34 IRCON/2065 24.03.2017 Providing Consultancy services IRCON/2065/PPP M/s Geo Design & `1.67 Crore Below 20% `1.34 Crore 06 Months /PPP/Katni- for preparing GADs for /Katni-Singrauli Research Pvt. Ltd., B- from the Singrauli/Ten der-GAD- Bridges, Detailed design & /Tender-GAD- 10, Krishna Industrial date of Design drawings and other allied work Design Estate, Opp. B.I.D.C. issue of Consultancy/ as per schedule in connection Consultancy/42, Gorwa Estate, LOA 42, Dated with Proposed doubling of Dated 31.05.2017 Vadodara-390016, Ph: 23.02.2017 existing railway line between 0265-2290222, Email: Katni-Singrauli 261 Km long of [email protected] West Central Railway. Works Awarded : JUNE 2017

Quantity Rate Scheduled S. Tender Date of LOA No. Contractor’s Name and (for supply contract)/ (for supply contract)/ Value of Description of Item/ Work Estimated Cost (For Tendered Cost (For completion N. No. opening and date address Contract Engg./Elect. /S&T/ Mech. Engg./Elect./S&T/ date etc Works) Mech. etc Works) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

1 IRCON/Civil/ 17.05.17 Construction of Eco Park / 18 IRCON/Civil/e- M/s Continental `11,73,72,986/- Schedule A : 05 `11,17,43,963.42 24 Months e-Tender hole Golf course (GC) Tender/1029/MCF Fairways, 2A – Wing, % Below of the from the /1029/RCF- BOQ Rates i.e. RBL/Golf including Earthwork, leveling, -RBL/Golf Krishna Heights, Upper date of Course/ Greenery, Plantation, water Course/OT/19/102 Govind Nagar, Near `100122067.50 issue of OT/19 bodies etc. in Prashanti 15, Raheja Township, Malad LOA Dt:01.05.17 Parisar, Township of MCF/RBL Dt. 02.06.2017 East, Mumbai -400097. Schedule B : 03 % Below of the BOQ Rates i.e. `9692133.30

Schedule C : 03 % Below of the BOQ Rates i.e. `1929762.62

2 IRCON/PO/T 28.03.17 Assembling, Laying and linkingIRCON/PO/TN/JAY M/s Sunil Kumar `2,91,51,813.08 55.0 % Above `4,51,85,310.28 6 months N/JAYNAGA of Broad gauge railway track NAGAR-2050/ At+PO-Bihat, Dist.- from the date R-2050/17 /46 for main line & loop line with 60 /17/46/178 Begusarai-851135 (Bihar) of issue of Dt:06.03.17 Kg rails & PSC sleepers with Dt.: 02.06.2017 LOA contractor's own P. Way material (except 60 Kg rails & PSC 60 Kg sleepers) and other allied works between Km (-) 0+105 Jaynagar to Km 2+975 in connection with New BG Rail line from Jayanagar (India) to Bardibas (Nepal).Pkg-Track- 01(India) Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 3 IRCON/ELE 10.04.17 Supply, installation, testing and IRCON/ELECT/TE M/s Technisys, Plot No- `1,83,78,528.00 `16540675.20 `1,45,55,794/- 04 Months CT/TENDER/ commissioning of Electrical NDER/ELECTRIC 239, Gurukul Industrial from the ELECTRICA L WORKS works for commercial complex AL WORKS FOR area, Anangpur road date of FOR Sec 48 Noida. COMMERCIAL Faridabad Haryana issue of COMMERCI COMPLEX SEC LOA AL 48 NOIDA, dated COMPLEX SEC 48 15.06.2017 NOIDA, dated 20.03.17 4 IRCON/ 12.06.17 Production of Asphalt material IRCON/ 3017/ M/s.Ved Prakash ` 84.49 Lakh Item rate ` 84.85 Lakh 06 months 3017/ SGTL/ for Bituminous concrete as per SGTL/ eTenders/ Sharma, Kotwali Road, from the eTenders/ Works/ Required Gradation & Works/ Asphalt Shivpuri, M.P. – 473 date of Asphalt Mix/ Specifications with contractor’s Mix/ 344, Date 551,Ph: +919039436999 issue of 344, Date Plant and machinery in 15.06.2017 LOA 07.06.2017 connection with “4-Laning of Shivpuri - Guna section of NH- 3. 5 IRCON/Civil/ 19.04.17 Irrigation system for Eco Park/ IRCON/Civil/e- M/s JAIN IRRIGATION `40,964,327/- 11 % Below of `3,64,58,251.03 24 Months e-Tender Golf Course in township of Tender/1029/MCF SYSTEM LIMITED, JAIN the BOQ Rates from the /1029/MCF- RBL/ MCF/RBL -RBL/ Irrigation PLASTIC PARK, N.H. i.e. ` date of Irrigation system for Eco No.6, BAMBHORI- 3,64,58,251.03 issue of system for Park JALGAON-425001, LOA Eco /OT/14/10299, Maharashtra Park/OT/14, Dt. Dt. 17.06.2017 09.03.2017. 6 IRCON/ELE 28.04.17 Design, Supply, Installation, IRCON/ELECT/50 M/s KEI Industries Ltd ` 18,38,89,562.60 `183889562.60 ` 17,77,49,803 15 Months CT/5030/MT Testing& Commissioning of 30/MT J-KAP/ D-90, Okhla Industrial from the J-KAP/ TSS/4, dt. Traction sub- station work for TSS/4, Area, Phase-1, New date of 24.03.17 Lot-1 ( Mendu & Kasganj) in Dt. 19.06.17 Delhi-110020, issue of Mathura- Kasganj- Kalyanpur [email protected] LOA section of North Eastern Railway. Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 7 'IRCON/ 3017/ 08.05.17 Providing and Fixing Retro IRCON/ 3017/ M/s. Nagar Builders, ` 277.75 Lakh 20.50% below ` 220.81 Lakh 06 months SGTL/ Tender/ Reflective Sign Boards, SGTL/ Tender/ C-25/A, Jagat Puri Extn. from the Sign Boards/ OT/ 340 dated Delineators and Road Studs on Sign Boards/ OT/ Shahdra, Delhi, date of 13.04.2017 NH-3 for IRCON SGTL 340 Dt, 20.06.17 Ph. +919810080989 issue of (Agreement No. ISGTL/ CO/ LOA SG/ IRCON/ CORRES/ 02 dtd. 02.09.2015) in connection with “4-Laning of Shivpuri-Guna section of NH-3 8 'IRCON/ 08.05.17 Providing and Laying Hot IRCON/ 3017/ M/s. Automark Industries ` 374.62 Lakh 18.90% below ` 303.82 Lakh 06 months 3017/ SGTL/ applied Thermoplastic Paint for SGTL/ Tender/ (India)Limited,'Gurukripa from the Tender/ Road road marking on NH-3 for Road Marking/ Datta Square Yavatmal - date of Marking/ OT/ IRCON SGTL (Agreement No. OT/ 341 dated 445001 Maharashtra, issue of 341 dated ISGTL/ CO/ SG/ IRCON/ 21.06.2017 Ph. +919326024188 LOA 13.04.2017 CORRES/ 02 dtd. 02.09.2015) in connection with “4-Laning of Shivpuri-Guna section of NH-3.

9 IRCON/2046 09.06.17 Hiring of vehicles for officers IRCON/2046/NFR- M/s Golden Life, ` 18,24,000.00 `18,24,000.00 ` 19,13,558.00 30.06.2018 /NFR-SRRP/ and staff working in the office SRRP/e- Anita Lodge Building, E-Tender- Vehicle-2017- of AGM/PH of Sivok Rangpo Tender/Vehicle/20 Ground Floor, Hill Cart 126 dated Rail Project 17/126/2425 dt. Road Siliguri- 734001 10.05.2017 21.06.2017 Ph: 34070730 10IRCON/ELECT 15.05.17 Design, Supply, Installation, IRCON/ELECT/50 M/s Sterlite Power Grid `49,39,94,651 `44,45,95,173/- `49,82,02,911/- 18 Months /5030/MTJ- Testing& Commissioning of 30/MTJ-KAP Venture Limited KAP/OHE/(PK from the G-I)5, dt. Railway electrification work /OHE/(PKG-I)5, F-1, Mira Corporate date of 06.04.17 between Mathura (Excl.)- dt. 23.06.17 Suits 1& 2 Ishwar Nagar, issue of Kasganj( Incl.) section of North Okhla Crossing Mathura LOA Eastern Railway. Road New Delhi-110065 satyagopal.mohanty@st erlite.com Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 11 IRCON/MEC 09.02.17 Supply, Erection, Testing & IRCON/MECH/10 M/s Omega Construction 01 No `11,10,225/- `11,10,225.00 02 Month H/1029/RE/ Commissioning of 01 Nos (10 29/RE/MCF RBL- Equipment Pvt Ltd., Plot MCF RBL- from the II/Hydraulic T) Hydraulic Crane for Modern II/Hydraulic Crane No 262-M, Sector- issue of Crane/318/R Coach Factory Project Rae /318/RET/7847 24,Faridabad Haryana- LOA ET/ Dated Bareli Dated 27.06.17 121005 18.01.2017 12 IRCON/ELE 02.05.17 Design, Supply, Installation, IRCON/ELECT/50 M/s HYT Engineering `68,18,967.00 `68,18,967/- `79,76,711.96 06 Months CT/5019/SE testing & Commissioning of 19/SELS.BNDM/T Company Pvt Ltd, Plot from the LS.BNDM/ T&P/105/UA Universal Multipurpose &P/105/UAM/ 02, No 29/10, 29/10/1, date of M/02, dated Armature Machine including dated 28.06.17 29/10/2 D-2, Block issue of 30.03.17 comprehensive (Preventive & MIDC, Chinchwad Pune- LOA Breakdown ) Maintenance and 411019 AMC in New Electric Loco Shed at Bondamunda 13 IRCON/Civil/ 20.04.17 Construction of Coach Blast IRCON/Civil/e- M/s Niagara Metals India ` 62196074.56 Sch A : 11.57% `5,49,99, 988.73 06 Months e-Tender shop and Paint store in factory Tender/1029/MCF Limited, Village Laton Below of the from the /1029/MCF- BOQ Rates i.e. RBL/Coach of MCF/RBL at Lalganj, Rae -RBL/ Coach Blast Dana, Katani Kalan, date of `26568648.93 Blast shop Bareli, U.P including shop /OT/15/ Chandigarh Road, issue of /OT/15, Architectural, Structural design, 10339, Ludhiana(Punjab)141113 LOA Dt. 21.03.17 Sch B : 11.57% Fabrication, Supply and Dt.28.06.17 Below of the erection of Pre-Engineered BOQ Rates i.e. Steel Building. `28431339.81

14 IRCON/ELE 16.05.17 Design Supply Installation IRCON/ELECT/20 M/s. JK Engineers, Hall `18,53,83,437 3.48% Below- `17,89,32,093/- 15 Months CT/2065/KT Testing and Commissioning of 65/KTE-SGRL No.112-B2, 1st floor, from the E-SGRL /TSS/01, 132/25 kV 21.6/30.24 MVA, /TSS/Pkg-I/153 South Block, Bahu date of Dt:13/04/17 ONAN/ONAF Double dated. 29.06.17 Plaza, Jammu-180012. issue of Transformer Traction Sub- jk_engineers@rediffmail. LOA Station complete in all respect com. Mob:9419100744, at Khanna Banjari and Beohari 9596844908 in connection with Electrification of existing BG Line of Katni-Singrauli section in Jabalpur division of West Central Railway Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 15 IRCON/Civil/ 12.05.17 Construction of Embedded IRCON/Civil/e- M/s Vishnu Saran & Co. `4,58,78,617.52 Sch A: 10.15 % `4,12,21,937.84 06 Months e-Tender Tracks, Scrap Store, R.C.C Tender/1029/MCF 113/163, Swaroop below of the from the /1029/MCF- BOQ Rates i.e. RBL/Coach Flooring, approach roads for -RBL/Coach Blast Nagar,Kanpur-208002 date of `2,42,82,205.88 Blast shop Coach Blast shop of Modern shop/OT/17/1034, issue of balance Coach Factory of Lalganj, Dt. 29.06.2017 LOA Sch B: 10.15 % work/OT/17, Raebareli Dt. 28.03.17 below of the BOQ Rates i.e. `1,69,39,731.97

16 IRCON/ELE 18.04.17 Design, Supply, Installation, IRCON/ELECT/50 M/s Sumesh Petroleum, `57,13,904/- `57,13,904/- `75,12,936/- 06 Months CT/5019/SE testing & Commissioning of 19/SELS.BNDM/T 226, G.I.D.C., Estate , from the LS.BNDM/T & P/105/ High Vacuum type Transformer & P/105/OFP/01, Makarpura Vadodara- date of OFP/01, oil filtration Plant (Cap.1200 Dt 29.06.2017 390010 (Gujrat) issue of Dt27.03.17 LPH & 3000 LPH) including LOA comprehensive (Preventive & Breakdown ) Maintenance and AMC in New Electric Loco Shed at Bondamunda 17 IRCON/MEC 06.04.17 02 Nos Industrial Sweeper with IRCON/MECH/10 M/s Suryajyoti Hi-Tech 02 Nos Industrial `17,82,000/- `35,64,000/- 03 Month H/1029/ RE/ Wet Mopping 29/ RE/ MCF. Engineers, J-12/16 D Sweeper With from the MCF.RBL-II/ IVS Wet RBL-II/ IVS Wet Bauliya Bagh Ram Wet Mopping issue of Mopping/316 Mopping/316/RET Katora Varanasi-221001 LOA /RET-1 -1 /7870, U.P.,suryas.jyoti2012@g Dt:17.03.17 Dt:29.06.17 mail.com 18 IRCON/ELE 05.04.17 Supply, installation, testing and IRCON/ELECT/TE M/s Variscon `1,25,67,071/- `11310363.90 ` 1,01,15,989/- 4 Months CT/TENDER/ commissioning of Electrical NDER/ELECTRIC Engineering Service Pvt from the ELECTRICA L WORKS works for commercial complex AL WORKS FOR Ltd, A-55, FIEE Complex date of FOR Sec 01 Noida. COMMERCIAL Okhala, Industrial Area – issue of COMMERCI COMPLEX SEC II, New Delhi-110020 LOA AL 01 NOIDA/338, COMPLEX SEC 01 Dt 30.06.17 NOIDA/338, Dt:16.03.17 Works Awarded : JULY 2017

Quantity Rate Scheduled S. Tender Date of LOA No. Contractor’s Name and (for supply contract)/ (for supply contract)/ Value of Description of Item/ Work Estimated Cost (For Tendered Cost (For completion N. No. opening and date address Contract Engg./Elect. /S&T/ Mech. Engg./Elect./S&T/ date etc Works) Mech. etc Works) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 1 IRCON/3018 22.05.17 Construction of civil works up to IRCON/3018/DFC M/s M H Khanusiya 1st ` 45.88 Crores `41.29 Crores ` 53.50 Crores 30.09.2018 /DFCCIL- formation including earthworks, CIL-CTP-12/08- floor Divine India CTP-12/e- Tender/ Infra blanketing, minor bridges, 40/1101 dated Building Near RTO work / retaining walls, drains, ground 01.07.2017 Office By pass Road Package:SS improvement works, relocation Post Savgadh (Panpur) S3 A/08-40 of existing roads etc. from Himmatnagar Dist S K Ch.138 to Ch.151 for Infra work Gujarat package - SS2 - A 2 IRCON/J&K/ 26.05.17 Works Contract for Maintenance IRCON/K-B/14/ M/s Gh. Nabi Giri & ` 2,69,54,170.32 3.40 % Above ` 2,78,70,612.11 30.06.2018 K-B/14/ of IRCON/NR establishments 1014/ Utility Sons, Head office, Near 1014/Utility Works/ M- office and camp up keeping and Works/ M-42/ 469 Tehsil Office, Banihal, 42/ dated other misc and assisting IRCON Dt: 01.07.2017 Distt. Ramban (J&K) 04.05.2017 Engineers during supervision of works and survey works as required at various locations along the project alignment from Katra to Banihal covering Ramban Sangaldan Sumber Kohli Dharam Khari Banihal also including Barala Reasi Khanikote Dugga and Katra etc in connection with Katra_ Banihal section of USBRL Project J & K (Package M-42) 3 IRCON/3018 11.05.17 Construction of civil works up to IRCON/3018/DFC M/s Raghuvir Buildcon ` 42.41 Crores `38.17 Crores ` 48.48 Crores 30.09.2018 /DFCCIL- formation including earthworks, CIL-CTP-12/08- Private Limited 201 CTP-12/e- Tender/ Infra blanketing, minor bridges, 42/1102 dated Jalaram House 2nd floor work / retaining walls, drains, ground 01.07.2017 Near Atmajyoti Ashram Package:SS improvement works, relocation Ellorapark, Vadodara S3 A/08-42 of existing roads etc.from Gujarat 390023. Ch.138 to Ch.151 for Infra work package - SS2 - C (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

4 IRCON/2059 12.04.17 Construction of Station Building, IRCON/2059/CGR M/s. Ravi Shanker `12,54,52,284/- 12.79%Above `14,15,01,689/- 09 Months /CGRP/ e- Platform, Platform shelter, P-e-Tender/ EC17 Tripathi, H-2/11, Tender (including EC17/17/Bld Circulating area, Approach / 18 / Bldg & Narmada Nagar, monsoon g & Platform, Road and other Miscellaneous Platform / 880, Bilaspur (C.G.) - 495001 period) from Dt: 22.03.17 work at Gurda, Chhal & Dt: 05.07.17 the date of Gharghoda from Km.00.00 to issue of LOA Km.35.00 (3nos.) in connection with new BG Electrified Double Line Railway track in the State of Chhattisgarh over South East Central Railway between Kharsia and Dharmjaygarh 5 IRCON/ELE 02.06.17 Drone Survey, Design & IRCON/ELECT/5 M/s Skylark Designer & 108 RKM `61,60,337.68 `62,25,316.54 24 Months CT/5030/MT Drawing of OHE work including 030/MT J- Engineers Pvt Ltd, B-48, ( 126 TKM) from the J-KAP/ nd DESIGN SP & SSP of existing BG line in KAP/DESIGN 2 Floor, sector-63, date of DRAWING & between Kasganj (Excl.)- DRAWING & Noida-201302, Distt. issue of SURVEY /3A Farrukhabad (Excl.) sub station Gautam Budh Nagar LOA Dt:03.05.17 SURVEY/3A, dt. of Mathura- Kasgnaj-Kalyanpur 05.07.17 section of North Eastern Railway. 6 IRCON/PO/T 14.06.17 Supply, Erection, Testing &IRCON/PO/TN/JAY M/s Asha Electronics `59,39,975.36 18.38% Below `48,48,413.23 04 months N/JAYNAGA Commissioning of Modification NAGAR-2050/ Construction Co., from the R-2050 /17/50 of Electrical Crossings Up to 33 /17/50/220 At+PO-Bihat, Tola- date of Dt:24.05.17 KV by Underground Cables Dt.:10.07.2017 Sundarvan, Dist.- issue of including shifting/dismantling of Begusarai-851135 LOA existing 33KV & 11 KV line and (Bihar) associated works in India Portion from Ch. KM 0+000 to Ch. KM 2+975 in connection with Gauge conversion of New Broad Gauge Railway Line from JAYNAGAR (INDIA) to BARDIBAS (NEPAL). Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 7 IRCON/CO/ 23.06.17 Providing Consultancy Services IRCON/CO/ 2056/ M/s Geo Designs and `1,31,80,389/- 25.10% Below ` 98,72,111.36 10.11.2017 2056/ for preparing General Arra- PPP/Agartala- Research Pvt. Ltd. PPP/Agartal a- Akhaura/ ngement Drawing, Detailed De- Akhaura/ Detailed B-10, Krishna Industrial Detailed sign and Drawings for viaduct, Design & Estate, Op. BIDC Grwa Design & Minor Bridges, Box Culverts in Consultancy/ 49/ Estate, Vadodara- Consultancy Railway alignment and Road 03, Dt:11.07.17 390016 /49 dated 07.04.2017 over Bridges on Road crossings and other allied consultancy works as per schedule in connection with the construction of a new dual gauge Agartala- Akhaura Rail Link Project. 8 IRCON/3018 08.06.17 Construction of civil works up to IRCON/3018/DFC M/s S A Yadav 213-214 ` 36.95 Crores `33.25 Crores ` 41.84 Crores 11.10.2018 /DFCCIL- formation including earthworks, CIL-CTP-12/SS1 Second Floor Decision CTP-12/e- Tender/ Infra blanketing, minor bridges, A/08-51/1156, Tower Pune Satara work / retaining walls, drains, ground Dt:12.07.2017 Road Near City Pride Package:SS improvement works, relocation Theatre Bibewadi Pune S3 A/08-52 of existing roads etc. for Infra 411037 work package-SS1 - B 9 IRCON/CC/e 12.05.17 Supplying and stacking of 50 IRCON/CC/e-TN M/s. Pee Pee Mandal 18525 cum `3,531.59/m3 ` 6,54,22,704.75 4 months -TN/ JBRLP mm size machine crushed track /JBRLP/2050/Ball Projects Pvt. Ltd, Kh no. from the /2050/17/2, Dt:12.05.17 ballast for New B.G. Line from ast supply/761, 219 GF, Prahalad Vihar, date of issue Jaynagar (India) to Bardibas Dt:12.07.2017 Ext. Phase-z, Gupta of LOA (Nepal) Railway project for Colony, Vill- Prahladpur Indian portion only from Km Banger,Delhi-110042. 0+000 to Km 2+975. Tel :- 011-65825861 10 IRCON/1014/J 31.05.17 Detailed Design Consultancy of IRCON/1014/J&K- M/s Lombardi `26,96,39,044.22 11.29% Above `30,00,77,599.86 12.07.2020 &K-DQ/ E&M works and Construction DQ/ Consultancy Engineering Ltd., Consultancy Tunnels Km Supervision of Tunnels inclu- Tunnels Km 110- CH 6648, Minusio 110-125/T-49 ding 3-D monitoring, and ass- 125/T-49/DDC/ Locarno, Switzerland via /DDC/ dated ociated works between km 110 8678,Dt:13.07.17 R Simen 19. 25.04.2017 & km 125 in connection with P.O. Box 1535 Locarno, Construction of Dharam-Qazi- Ticino, Switzerland gund Section of Udhampur-Srin- agar-Baramulla New BG Rail- way Line Project (Balance Wo- rk)(Pkg:DDC/T-49 Km110-125). (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 11IRCON/3018/D 08.06.17 Construction of civil works up to IRCON/3018/DFC M/s GHV India Private ` 60.24 Crores `54.22 Crores ` 70.27 Crores 16.10.2018 FCCIL-CTP- formation including earthworks, CIL-CTP-12/SS1 Limited, AML Centre 1 8 12/e-Tender/ Infra work / blanketing, minor bridges, A/08-51/1156, Mahal Industrial Area, Package:SSS retaining walls, drains, ground Dt:17.07.2017 Mahakali Caves Road, 3 A/08-51 improvement works, relocation Andheri ( E ) Mumbai-93 of existing roads etc. for Infra work package - SS1 - A 12 IRCON/3018 08.06.17 Construction of civil works up to IRCON/3018/DFC M/s GHV India Private ` 59.02 Crores `53.12 Crores ` 68.20 Crores 16.10.2018 /DFCCIL- formation including earthworks, CIL-CTP-12/SS1 Limited, AML Centre 1 8 CTP-12/e- Tender/ Infra blanketing, minor bridges, A/08- Mahal Industrial Area, work / retaining walls, drains, ground 51/1156dated Mahakali Caves Road, Package:SS improvement works, relocation 17.07.2017 Andheri ( E ) Mumbai-93 S3 A/08-53 of existing roads e for Infra work package - SS1 – C 13 IRCON/MEC 14.07.17 Supply of 02nos RF Tube Tube IRCON/MECH/10 M/s Techno Enterprises ` 0.37 Crores Item Rate ` 0.37 Crores 06 Weeks H/1029/e Triode CTK25 4 Part No 704217 29/e- tender/ H-3, Industrial Area-I, from the tender/MCF RBL II/ for Laser Cutting Machines at MCF.RBL-II/ LCM/ Sultanpur Road issue of LCM/spare/ MCF RBL Lalganj Rae Bareli spare/ Dated Distt. Raebareli, U.P. – LOA Dt:07.07.17 UP 18.07.2017 229010 14 IRCON/5030 19.05.17 Design, Supply, Installation, IRCON/5030/MTJ M/s. Angelique ` 14.94 Crores `13.45Crores ` 15.04 Crores 18 Months /MTJ-KAP Testing & Commissioning of -KAP /S&T/ International Ltd., 104- from the /S&T/TENDE st R/PKG-I/02 Indoor & Outdoor Signalling TENDER/PKG- 107 Hemkunt Tower, 1 date of Dt. 27.04.17 System Between Mathura I/02/1320 Dt. Floor Nehru Place Delhi- issue of Cantt. To Rudain in connection 20.07.17 110019 LOA with RE work between Mathura- Kasganj-Kalyanpur 15 IRCON/Civil/ 15.05.17 Construction of Hockey IRCON/Civil/e- M/s Balajee Developers, ` 8.37 Crores Schedule A - ` 7.47 Crores 15 Months e Tender Football/ Atheletics and Cricket Tender/1029/MCF C-119/S2 second Floor, (Including /1029/RCF 06% below, RBL/Outdoor field and Electromechanical -RBL/OSA/OT/ Ramprastha Colony, Schedule B - Monsoon Sports Fields work of swimimg poolin outdoor 18/10400, Ghaziabad, Uttar Period) from 15% below, /OT/18, sports area of Prashanti Parisar Dt. 21.07.2017 Pradesh – 201011 the date of Dt:11.04.17 of MCF/RBL Schedule C - issuance of 5% below LOA

Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 16 IRCON/Civil/ 27.04.17 Consultancy services for IRCON/CIVIL/501 M/s GOMA Engineering ` 0.11 Crores 7.57% Above ` 12,20,910.60 24 months 50174./NELS Detailed Engineering, 7/NELS.DD/e- & Consultancy from the .DD/e- Tender/OT/2 Architectural, Structural and Tender/OT-21/ Joshi Estate, Opp.-Ankur date of 1, 28.03.17 other services for Drainage, LOA/169, Oil Mill, Sarkjej –Bawla issue of Water supply arrangement, Dt:21.07.17 Highway, Changodar, LOA. Sewerage, Roads, Track, STP, Ahmedabad-382212. Fire fighting with related structures and External services related to construction of New Electric Loco Shed at Daund, Pune (Maharashtra). 17 IRCON/ 31.05.17 Supply, installation & IRCON/ 2048/ M/s Paul Builders Pvt. ` 4.30 Crores ` 4.30Crores `5,08,33,812.43 05 months 2048/TN/ commissioning of Internal & ISC-BEHALA/ Ltd., P-2 CIT Scheme-VI from the PLUMBING- ROOF- External Plumbing; Structural Balance Civil (M), Ramdeo Tower date of ROAD/ Steel Curved Roof in Cricket Works/ Paul Phoolbagan, Kolkata- issue of 2017/45 Pavilion and construction of Builders25425/31 70032 LOA dated Peripheral Road for Indoor 0A, Dt:21.07.17 10.05.17 Sports Complex at Gholsapur, Behala, West Bengal for Eastern Railway. 18 IRCON/3017/ 10.07.17 Supply of Hard Stone Boulders IRCON/3017/SGT M/s. Shree Balaji ` 215.10 Lakh Item rate ` 237.00 Lakh 04 Months SGTL/eTend and Crusher Operation at L/eTenders Borewells, A-1 from the ers /Works/Bould Ircon’s Crusher Camp near /Works/Boulder Panchawati Colony, date of er Crushing- Village BAMAUR, Tehsil Crushing-2/346, Airport Road, Bhopal issue of 2/346, BADARWAS, District SHIVPURI 22.07.2017 Mob. - 9981644599 LOA 24.06.2017 (MP); for Production of Aggregate Material as per Required Gradation & Specifications By Operating and Maintaining IRCON’s Crusher Including Loading, Transportation and Unloading of aggregate at Ircon’s Main Camp near Village Bamaur Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 19 IRCON/Civil/ 06.06.17 Construction of Hockey, IRCON/Civil/e- M/s Balajee Developers, ` 18.90 Crores Schedule A- ` 16.84 Crores 18 Months e Tender Football/ Atheletics Cricket , Tender/1029/MCF C-119/S2 second Floor, 11.5% Below, (Including /1029/RCF- RBL/Stadium swimimg pool stadium Building -RBL/ Stadium Ramprastha Colony, Schedule B - Monsoon Building/OT/ maintenance including Building/OT/20 Ghaziabad, Uttar 12% Below, Period) from 20, 05.05.17 electrical, fire fighting and /10413, Pradesh – 201011 Schedule-C - the date of HVAC workin outdoor sports Dt:25.07.17 6% Below, issuance of area of Prashanti Parisar of Schedule-D - LOA. MCF/RBL 12% Below, Schedule-E - 1% Below, Schedule-F - 5 % Below 20 IRCON/J&K 22.06.17 Strengthening and Improvement IRCON/J&K M/s. ECI Engineering `35,59,65,217.47 16.20% Below `29,82,98,852/- 14 months Cell/JAT/1 to the existing approach road Cell/JAT/1 and Construction Co. from the 4/1014/K-B/ PKG: T-15 from Ch 0/000 Kms to Ch 4/1014/K-B/ PKG: Ltd, Plot No. A12 & A13, date of ROAD/367/6 18/500 Kms from Barala to Ind- T-15 ROAD/ Panchvati Township, issue of 01/ Dated Tatsun Nala part of approach 367/601/3004, Manikonda, Hydrabad, LOA 24.05.2017 road from Sangaldan to Tatsun Dt 31.07.2017 Telangana-500089 Nala P2 of Tunnel T14 and P1 of Tunnel T15 on the Katra- Dharam section of the USBRL. PKG-T-15 ROAD 21 IRCON/J&K 15.03.17 Design, manufacture, supply, IRCON/J&K- M/s. Sharika Enterprises `85,38,750/- 2.39% Above ` 87,42,937/- 06 months Cell/JAT/15/1 Installation, Testing , Commiss- Cell/JAT/15/ Pvt Ltd., House No. 105, from the 014/Package Solar PP-01/ ioning and Handover of Grid 1014/Package Sector-5, Trikuta Nagar, date of dated Connected Roof Top Solar Solar PP-01/ 585, Jammu-180012 issue of 20.02.2017 Power plant of 110kWp capacity Dt: 31.07.2017 LOA with all the electrical and associated equipments including civil works at Sangaldan Office/Residential camp's Block A,B,C,D & E with Comprehensive AMC for five years" under USBRL Project in Katra- Banihal Section of USBRL Project (J&K). (Package: Solar PP-01) Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 22 IRCON/J&K- 14.06.17 Consultancy services for Proof IRCON/J&K- M/s Lombardi `33,90,000/- 3.00% Above ` 34,91,700/- 06 months Cell/JAT/15/ Checking of Design of Cell/JAT/15/ Engineering Ltd., via R from the 1014/T- 74R/Package Ventilation, Fire Escape, 1014/T-74R/ Simen 19. P.O. Box date of PCD -01/ Emergency Rescue and other Package PCD - 1535 CH 6648, Minusio issue of dated related electro-mechanical 01/ 584, Locarno, Switzerland LOA 24.05.2017 system for T-74R (Main Tunnel, Dt:31.07.2017 Locarno, Ticino, Escape Tunnel and Adit) on Switzerland Dharam- Banihal Section of USBRL Project (J&K). INDIA. (Package: PCD -01) 23 IRCON/2065/ 11.05.17 Supply of Signalling & Telecom IRCON/2065/S&T M/s Sriram Cable Pvt. ` 2,31,39,877/- 6.04% Below `2,17,41,711/- 04 months SnT/KTE Cables for Gondwali Station of /KTE-SGRL/ Ltd. A-524,RIICO from the SGRL/TEND ER/04, Katni Singrauli section TENDER/04/1325 Industrial Area,Chopanki date of dt:19.04.17 , Dt:31.07.2017 (Bhiwadi) – 301707, issue of Distt.-Alwar, Rajasthan LOA 24 IRCON/2057 05.06.17 Procurement of Rly. Sig. & IRCON/2057/NST M/s Sriram Cable Pvt. `1,12,30,609.89 1.21% Above `1,13,66,902.50 04 months /NSTP/S&T/ Telecom Cables as per latest P/S&T/TENDER/P Ltd. A-524, RIICO from the TENDER/PK G-I, RDSO specs for NPGC, KG-I/04/S dated Industrial Area,Chopanki date of Dt:12.05.17 Nabinagar, Aurangabad 31.07.2017 (Bhiwadi) – 301707, issue of Districtt, Bihar Distt. – Alwar, Rajasthan LOA IRCON/2057/NST M/s Tirupati `1,13,35,950/- 4.03% Above `1,17,93,589.47 04 months P/S&T/TENDER/P Plastomatics Pvt. Ltd. B- from the KG-I/04/T dated 141(A), Road No. 9-D, date of 31.07.2017 V.K.I Area, Jaipur- issue of 302013, Rajasthan LOA Works Awarded : AUGUST 2017

Quantity Rate Scheduled S. Tender Date of LOA No. Contractor’s Name and (for supply contract)/ (for supply contract)/ Value of Description of Item/ Work Estimated Cost (For Tendered Cost (For completion N. No. opening and date address Contract Engg./Elect. /S&T/ Mech. Engg./Elect./S&T/ date etc Works) Mech. etc Works) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 1 IRCON/3018 08.06.17 Construction of civil works up to IRCON/3018/DFC M/s M H Khanusiya, 1st `56.14 Crores ` 50.53Crores ` 58.07 Crores 15 Months /DFCCIL- formation including earthworks, CIL-CTP-12/SS3- floor Divine India from date of CTP-12/e- Tender/ Infra blanketing, minor bridges, C/08-39/1194, Building Near RTO Issue work / retaining walls, drains, ground Dt:02.08.2017 Office By pass Road Package:SS improvement works, relocation Post Savgadh (Panpur) 3- C/08- of existing roads etc from Himmatnagar Dist S K 39/Rev, Dt:15.05.17 Ch:19.813(IR 178/21-23) to Ch. Gujarat 37.532(IR 196/11-13) for Infra work package – SS3 - C 2 IRCON/CC/e 24.04.17 Manufacturing, supplying, IRCON/CC/e-TN/ M/s PCM Cement 19820 Nos ` 7.85 Crores ` 6,63,23,120.36 4 Months -TN/JBRLP/ transportation & stacking of JBNRL/2051/17/22 Concrete Private Limited from the 2051/17/22/1 nd Dt:24.03.17 various sizes of 60Kg UIC Rail /1/775, PCM Tower, 2 Mile date of PSC Mono Block Sleepers for Dt:04.08.2017 Stone, Sevoke Road issue of B.G. Main Line, Loop Line, Siliguri:- 734001, West LOA Turnouts, Derailing Switch, Bengal Switch Expansion Joints (SEJ) and Level Crossings from Km 0+000 to km 5+445 for Indian Portion of Jogbani (India) – Biratnagar (Nepal) New Rail Line Project. 3 IRCON/3018 02.06.17 Design, Manufacture, IRCON/3018/DFC M/s PCM Strescon ` 139.17 Crores `125.25Crores ` 148.60 Crores 10.03.2020 /DFCCIL- Transportation & Delivery of CIL-CTP-12/ Overseas Ventures CTP-12/e- rd Tender/08- PSC Sleepers as per Sleeper/08-48/ Limited, PCM tower, 3 nd 48, specification for Western 1207, floor, 2 Mile, Sevoke Dt:26.04.17 Dedicated Freight Corridor Dt:05.08.2017 Road, Siliguri,West project CTP-12 between Sachin Bengal and Vaitarna (Supply in Ancheli Depot, Gujarat & Palghar Depot Near Vangaon station of Western Railway Maharashtra) Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 4 IRCON/MEC 23.03.17 Design and Supply of 2496 Nos IRCON/MECH/102 M/s J S Industries, 16/2 2496 Nos `3,69,85,818/- ` 3,69,85,818/- 180 days H/1029/RE/M Box Pallets at Modern Coach 9/RE/MCG.RBL- Mathura Road Box Pallets from the CG.RBL- II/Box Factory at Lalgang Rae Bareli II/Box Pallets/ 328 (Karkhana Bagh) issue of Pallets/308, U.P. /7945, Faridabad-121002 Purchase Dt:01.03.17 Dt:09.08.2017 Ph : 0129-2296606, Order 4100510, Telefax : 0129- 2282346 5 IRCON/3018 09.06.17 Fabrication, Supply, Installation IRCON/3018/DFC M/s M H Khanusiya, 1st ` 2.41 Crores ` 2.41 Crores ` 2.72 Crores 10.01.2018 /DFCCIL- and Commissioning of Portal CIL-CTP-12/ST- floor Divine India CTP-12/ST- TDR/Gantry/ Gantries and rail/sleeper TDR/Gantry/211/1 Building Near RTO 211, movement system, excluding 232, Office By pass Road Dt:28.02.17 hoists, motors, electric & Dt:10.08.2017 Post Savgadh (Panpur), electronic parts, at Ancheli Main Himmatnagar Dist S K Depot of Vaitarana – Sachin Gujarat Section in connection with construction of Western Dedicated Freight Corridor, Phase II

6 IRCON/MEC 30.03.17 Design and Supply of 200 Nos IRCON/MECH/102 M/s Saraswati 200 Nos ` 23,56,084/- ` 23,56,084/- 120 days H/1029/RE/ Hand Trolley at Modern Coach 9/RE/MCG.RBL- Engineering Limited, D- Hand Trolley from the MCG.RBL- II/Hand Factory at Lalgang Rae Bareli II/Hand Trolley/ 13 Site-1 Panki Industrial issue of Trolley/327 , U.P. 327/7949, Estate, Kanpur-208022, Purchase Dt:01.03.17 Dt:14.08.2017 [email protected] Order 7 IRCON/ 29.05.17 Construction of Subway by Box IRCON/2052/ M/s. ITD Cementation (I) ` 35.32 Crores `29.52 Crores `39,57,15,587.78 15 Months 2052/TN/ Pushing method, Circulating SRC/SW/ITD- Ltd., Godrej Waterside, from the SRC/ th SUBWAY/ Road, Elevated Parking & CEM/25428/ 517 803. 8 floor, Salt Lake date of 2017/41, Substation Building on pile dated 14.08.2017 City, Kolkata – 91. issue of Dt: 23.04.17 foundation at Santragachi LOA Station in connection with Station Development work of Santragachi Station for South Eastern Railway. Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 8 IRCON/ 30.05.17 Construction of Additional two IRCON/953A/KAS M/s. Construct ` 67.25 Lakhs ` 67.25 Lakhs ` 72,39,977/- 12 Months 953A/ floors on newly constructed BA/ OFFICE Engineering, from the TENDER/ OFFICE/ (G+1) IRCON office building at BLDG./CE/ 25426 P-539, Raja Basanta date of KASBA/ Prantik Pally, Kasba, Kolkata. /419, Roy Road, Kolkata - issue of 2017/44, Dt:14.08.2017 700029 LOA Dt: 09.05.17 9 IRCON/ 20.07.17 Supply of Vehicle on monthly IRCON/K-RO/ M/s. Aparnna Travel, ` 77.47 Lakhs ` 77.47 Lakhs ` 87,44,400/- 36 Months 953A/OT/ hire charge basis for official use HIRED-VEHICLE/ 69A, Alipore Road, from the VEHICLE/ 2017/47 in various offices of IRCON/ 25272/522A Kolkata – 700027. date of Dt:29.06.17 S.E. Rly. in Kolkata & Project dt.14.08.2017 issue of Offices in/around Kolkata. LOA 10 IRCON/ELE 23.06.17 Design, Supply, Installation, IRCON/ELECT/50 M/s Angelique 156 TKM `60,10,99,750/- `63,93,80,105/- 15 Months CT/5030/MT Testing & Commissioning of 30/MT J-KAP/ International Limited from the J-KAP/OHE/ Railway electrification work OHE/ (Pkg-Ii)/9, 104-107, Hemkunt date of (Pkg-Ii)/9, st Dt:18.05.17 between Farrrukhabad (Incl.) - Dt:16.08.2017 Tower, 1 floor, 98, issue of Kalyanpur (Excl.) section of Nehru Place New Delhi- LOA North Eastern Railway. 110019,info@angelique- india.com & mchand@angelique- india.com , Mob: 8130313672, Phone 011-26413873 to 75 11 IRCON / J&K 24.07.17 Providing Consultancy Services IRCON / J&K Cell M/s Lombardi ` 6,54,50,000/- 31.00% Below ` 4,51,60,500/- 30 months Cell / K-B / for preparing GADs, detailed / K-B / 14 / 1014 / Engineering Ltd., CH from the 14 / 1014 / DDC / Br. 2, design & drawings for Bridge DDC / Br. 2 ,3, 4 6648, Minusio Locarno, date of 3, 4 & 5, No.2, 3, 4 & 5, Arpinchala & 5, Arpinchala & Switzerland issue of Arpinchala & Station Yard & Sumber Station Sumber Yard/368 via R Simen 19, P.O. LOA Sumber Yard including allied buildings /721, Box 1535, Locarno, Yard/368, Dt:14.06.17 and other structures as per the Dt:22.08.2017 Ticino, Switzerland scope of works between km 110.096 To 125.121 of Katra - Banihal section of USBRL Project, J&K. (PACKAGE: DDC/BR. 2, 3, 4 & 5) Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 12 IRCON 10.07.17 Pkg. 1 - Superstructure works IRCON /2065/ M/s PSL ENGINEERING ` 3195.37 Lakhs Sch. A @ ` 2981.33 Lakhs 15 months /2065/ including supply, fabrication and PPP /Katni- PVT. LTD.,B-10/1, Okhla 5.75% below from the PPP/Katni- Singrauli/Ten erection of steel girders, Singrauli/Tender- Industrial Area, Phase-II, and, date of der-Steel bearings, steel channel Steel Girder New Delhi – 110 020 Sch. B @ issue of Girder sleepers, chequered plates, G. Bridges/Pkg.1/53 Ph. 011-32574430, 13.25% below LOA Bridges/Pkg. I. Pipe railing, access ladders, Dt: 22.08.2017 65974459, 1/53, Dt:10.06.17 trolley refuges, cleaning & [email protected], painting, bed plate, load testing [email protected] of one or more spans of selected bridges, etc., for important bridges nos. 1112/2 (Maha nadi), 1116/1 ( Umrar) and 1158/1 (son river) in connection with the proposed railway doubling project from katni to Singrauli over West Central Railway, Jabalpur (M.P.) 13 IRCON/3017/ 10.07.17 Supply of crushed WMM & IRCON/3017/ M/s. Anil Construction ` 137.50 Lakh Item rate ` 141.75 Lakh 04 Months SGTL/eTend Asphalt aggregates as per SGTL/eTenders/ Company, Krishnapuram from the ers /Works/ WMM & Required Gradation & Works/WMM & Shivpuri MP. Mob. - date of Asphalt Specifications Including Asphalt 9425136466 issue of Aggregates- Transportation and unloading of Aggregates-3/347, LOA 3/347, aggregate at IRCON’s main Dt. 24.08.2017 Dt:24.06.17 camp near Village Bamaur, A B Road (Km 276 of NH3) in connection with “4-Laning of Shivpuri - Guna section of NH-3 from Km 236.000 TO Km 332.100 in the State of Madhya Pradesh” (STAGE-I) Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 14 IRCON/CC/e 04.08.17 Manufacturing, Supplying, IRCON/CC/e- M/s PCM Cement 68,969 Nos Item Rate ` 16,67,06,363/- 3 months -TN/JBRLP transportation & Stacking of TN/JBRLP/2050/1 Concrete Private Limited from the /2050/17/sle various sizes of 60 Kg UIC Rail 7/sleepers/3/791, PCM Tower, 2nd Mile date of epers/3, PSC Mono Block Sleepers for Dt: 28.08.2017 issue of Dt:20.07.17 Stone, Sevoke Road B.G. Main Line, Loop Line, from LOA Km 2+975 to Km 34+800 for Siliguri:- 734001 Nepal Portion of Jaynagar West Bengal (India) to Bardibas (Nepal) New Rail Line Project 15 IRCON 10.07.17 Pkg. 2 - Superstructure works IRCON/2065/ M/s PSL ENGINEERING ` 2935.28 Lakhs Sch. A @ ` 2760.18 Lakhs 15 months /2065/ including supply, fabrication and PPP/Katni- PVT. LTD.,B-10/1, Okhla 4.82% below from the PPP/Katni- Singrauli/Ten erection of steel girders, Singrauli/Tender- Industrial Area, Phase-II, and, date of der-Steel bearings, steel channel Steel Girder New Delhi – 110 020 Sch. B @ issue of Girder sleepers, chequered plates, G. Bridges/Pkg.2/54 Ph. 011-32574430, 14.49% below LOA Bridges/Pkg. I. Pipe railing, access ladders, Dt:28.08.2017 65974459, 2/54, Dt:10.06.17 trolley refuges, cleaning & [email protected], painting, bed plate, load testing [email protected] of one or more spans of selected bridges, etc., for important bridges nos. 1201/1 (Jhapar), 1205/1 (Banas) and 1253/1 (Gopad) in connection with the proposed railway doubling project from katni to Singrauli over West Central Railway, Jabalpur (M.P.) 16 IRCON 14.07.17 Pkg.3-Supplying, Fabrication & IRCON/2065/PPP M/s SPACECHEM ` 2118.23 Lakhs Sch. A @ ` 2063.78 Lakhs 15 months /2065/ Transporting of Composite Plate /Katni-Singrauli/ ENTERPRISES, 2.6% below from the PPP/Katni- Singrauli/Ten Girders to respective bridges for Tender - Steel C-120, Bulandshahar and, date of der-Steel Important bridges (3 nos.) & Girder Bridges/ Road, Industrial Area, Sch. B 'At par' issue of Girder Major Bridges (35 nos.) Pkg.3/55, Ghaziabad – 201 009 LOA Bridges/Pkg. between Km 0.0 to Km 260.584 Dt:29.08.2017 Ph. 0120-2700602, 3/55, Dt:15.06.17 in connection with the proposed 2704459, railway doubling project from [email protected] katni to Singrauli over West garg@spacechemgroup. Central Railway, Jabalpur com (M.P.) Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 17 IRCON/3018 21.08.17 Construction of civil works up to IRCON/3018/DFC M/s Jugalkishor ` 40.94 Crores ` 36.85Crore ` 38.84 Crores 15 months /DFCCIL- formation including earthworks, CIL-CTP-12/SS4- Ramkishan Agrawal from date of CTP-12/e- Tender/ Infra blanketing, minor bridges, B/08-63/1265 Infrastructure Pvt Ltd. Issue of work / retaining walls, drains, ground Dt: 30.08.2017 Address: Ashok Villa LOA Package:SS improvement works, relocation Near Axis Bank, 4-B/08-63, of existing roads etc from Opposite Old Adarsh Dt:31.07.17 Ch:57+800(IR 216/23-25)to Ch. School, 71+141.5(IR 229/9-11 for Deesa Gujarat Infra work package – SS4 - B 18 IRCON/J&K 07.08.17 Risk & Cost tender for IRCON/J&K M/s. Gammon Engineers ` 6,76,83,28,229/- 72.91% Above `11,70,32,24,627 39 months CELL/JAT/ 14/ construction of balance works of CELL/ JAT/ 14/ & Contractors Pvt Ltd., from the 1014/ K-B/ Pkg: Tunnel T- Tunnel T-48 (between Km 1014/ K-B/ Pkg: Gammon House, Veer date of 48R/369, 100.000 to 110.200 approx.) on Tunnel T-48R/ Savarkar Marg, issue of Dt:20.06.17 Katra – Banihal Section of 369/8704, Prabhadevi, Mumbai- LOA. Udhampur –Srinagar-Baramulla Dt: 30.08.2017 400025 New BG Railway Line Project (Package: Tunnel T48R) 19 IRCON/3018/ 06.07.17 Supply Installation and IRCON/3018/DFC M/s Acrotech Scientific ` 18.04 Lakh ` 18.04 Lakh ` 16,01,313/- 29.10.17 DFCCIL-CTP- Comissioning of Laboratory CIL-CTP-12/Lab Industries A-27C 12/e-Tender /Lab Eqip / 8- Equipment at IRCON's Site Equipment/08- Mansarovar Garden 55, Camp at Palghar 55/1265A, Near Kirti Nagar Timber Dt:13.06.17 Dt:30.08.2017 Market New Delhi 20 IRCON/J&K- 13.07.17 Consultancy services for Proof IRCON/J&K- M/s Lombardi ` 63,84,112/- AT PAR ` 63,84,112/- 09 months Cell/JAT/15/ Checking of Design of Cell/JAT/15/ Engineering Ltd., via R from the 1014/T-14 & T-15/ Ventilation, Fire Escape, 1014/T-14 & T-15/ Simen 19,P.O. Box 1535 date of Package Emergency Rescue and other Package PCD- CH 6648, Minusio issue of PCD-05, related electro-mechanical 05/765 Locarno, Switzerland LOA. Dt:22.06.17 system for Tunnel No. T-14 Dt: 31.08.2017 Locarno,Ticino, (Main Tunnel & Escape Tunnel) Switzerland & T-15 (Main Tunnel, Escape Tunnel & Adit) on Katra- Dharam- Section of USBRL Project (J&K). INDIA .(Package: PCD -05) Cont/- (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 21 IRCON/ELE 04.08.17 Design, Supply, Installation, IRCON/ELECT/ M/s S K & S Build- Tech 3 Nos. TSS `21,04,99,831/- ` 19,9399,678/- 15 Months CT/5030/MT Testing& Commissioning of Civil 5030/MT J- (P) Ltd, 113/17, 1st Floor, from the J-KAP/TSS /4A, & electrical works complete in KAP/TSS/4A, Navyug Market date of Dt: 25.05.17 all respect of 132/25 KV, 21.6 Dt:31.08.2017 Ghaziabad-201001 (UP) issue of MVA/30.24 MVA ONAN/ONAF Email Id- LOA. Traction sub- station work in skbuildsbuildtech@gmail Mathura- Kasganj- Kalyanpur .com & section of North Eastern [email protected] Railway. Mob.No.- 9458852424