Dear Contractor REQUEST FOR PROPOSALS (RFP) No. 017-007 AUTOMATED PARKING COUNT SYSTEM QUESTIONS AND ANSWERS Below are questions VRE received as of May 18, 2017 at 11:00 A.M. EST, with responses. Whenever possible, questions are presented as originally asked. Otherwise, the questions or inquiries are presented to capture the main thrust or idea. SECTION B – PROCUREMENT SCHEDULE 1. Will VRE extend the due date for Proposals by one (1) or two (2) weeks to allow Offerors more time to scout the stations and prepare their Proposals? With additional time, Offerors can put together more creative and thorough Proposals. See Addendum No. 1. SECTION D – SCOPE OF WORK 2. Will VRE share the budget allotted for this project? No. 3. Should the car counter be a simple car counter at the carpark entry/exit, or does VRE want individual sensors for each parking spot? VRE will consider all proposed car counting solutions that meet the requirements included in the RFP. Page 1 of 5 4. Is the Contractor required to attend meetings at the VRE offices? Yes. See Sections 5.2O. and 5.2R. of Attachment V.3 – Technical Specifications of the RFP. 5. Can the Contractor perform tasks required in the scope of work outside of the United States? The work and training required for the Proof of Concept (POC) location must be performed in the United States. Maintenance and support, which shall be provided by the Contractor after the POC is complete, can be performed outside the United States. However, in accordance with Section E.18 of the RFP, the Contractor shall assign a single point of contact who must be available between the hours of 8:00 A.M. and 5:00 P.M. EST, Monday through Friday, to address any critical issues that arise. 6. For the Quantico Station, delineators would be required to obtain accurate counts as the lane width is around 35’ to 45’. Is this acceptable? VRE will consider all proposed solutions to obtain accurate parking counts, to include those that do or do not include delineators. However, the Offferor shall specify the quantity, type, and placement of the delineators required for accurate counts within its Proposal. 7. For the Lorton Station, it is not clear which lot is included in the scope of work. Is the Contractor responsible for providing parking counts for all surface lots in the area of the station? See Addendum No. 1. The Contractor is responsible for providing parking counts for the surface lots highlighted in yellow. 8. At the Burke Centre Station, must the parking count system distinguish between cars parked in the surface lot and cars parked in the garage? No. 9. There are several lots that appear to serve the Manassas Station. Can VRE specifically identify which lots are included in the scope of work for this Contract? See Addendum No. 1. The Contractor is responsible for providing parking counts for the parking garage and two (2) surface lots highlighted in yellow. Page 2 of 5 RFP No. 017-007 Automated Parking Count System Virginia Railway Express 10. Can VRE provide CAD drawings for all garages and surface lots at the thirteen (13) stations listed below? - Fredericksburg Station - Leeland Road Station - Brooke Station - Quantico Station - Rippon Station - Woodbridge Station - Lorton Station - Broad Run Station - Manassas Station - Manassas Park Station - Burke Centre Station - Rolling Road Station - Backlick Road Station No. VRE does not have CAD drawings available to provide to Offerors. 11. Are any of the stations included in this Contract mixed-use? Yes. Burke Centre is a mixed-use station. Burke Centre and Lorton include bus loops for local transit providers. Additionally, Woodbridge has a bus loop for transit providers, as well as Greyhound. All parking lots included in this solicitation are commuter lots, which are not exclusively used by VRE. Therefore, other commuters, to include those that vanpool, carpool, etc., may use the lots. The purpose of this solicitation is to track parking availability within each lot. 12. Will the Contractor be responsible for installation at other stations beyond Spotsylvania Station? No. VRE is responsible for installation at all other stations. 13. Is XML the preferred format for transmitting data? Yes. The preferred format is .xml. Page 3 of 5 RFP No. 017-007 Automated Parking Count System Virginia Railway Express 14. Can VRE provide a copy of the report prepared by Verizon which indicates the strength of the cell phone signal at each station? Yes. See Attachment A hereto. 15. Does VRE want the automated parking count system to monitor the use and availability of ADA parking spaces at each station? No. VRE requires only a total parking count. 16. Does VRE want the automated parking count system to interface with its existing mobile ticketing application? No. 17. Does VRE require one (1) spare of each part at each station location? No. In accordance with Section 2.5 of Attachment V.3 – Technical Specifications, VRE requires one (1) spare unit of each Parking Count System (PCS) equipment type only. SECTION M – SUBMISSION OF PROPOSAL 18. Can Proposals be submitted to VRE via email? No. In accordance with Section M.6E. of the RFP, electronic, facsimile or verbal Proposals shall not be accepted. 19. Can companies outside the United States submit a Proposal in response to this solicitation? Yes. However, Offerors must comply with Section H.12 – Buy America Provision of the RFP. Page 4 of 5 RFP No. 017-007 Automated Parking Count System Virginia Railway Express ATTACHMENT V.3 – TECHNICAL SPECIFICATIONS 20. With respect to Section 1.3H., can VRE clarify what it means by the statement that a count solution shall not require a field hardware controller in each lane? Is there a specific reason for this requirement? The solution may include these components, excluding gates, but they are not required. VRE will not provide power or internet connection for the proposed solution. 21. Section 1.4B.8. requires that vehicles entering and exiting through the delineated lanes be detected with 98% accuracy. What is the method for making this calculation? Is this a turnover calculation or simply the number of cars vs. spaces? Ninety-eight percent (98%) accuracy is based on accurately counting the number of valid vehicles entering and exiting a parking facility based on the spaces available while accommodating invalid counts as described in the technical specifications. 22. Section 1.5D. indicates that the Contractor shall allow for interfacing with future VRE signage requirements. What are the future sign requirements? Would such requirements include a sign indicating the lot is full? Signage is not a requirement of this RFP. In collaboration with the respective county, VRE may in the future look to install parking signage such as a monument sign at the Burke Centre multi-story parking garage or a lot full/empty sign at a surface lot. 23. Section 4.2C.9. states that all reports require 100% accuracy. Can VRE clarify this requirement? It is VRE's requirement that all data captured in the Contractor’s reports shall be 100% accurate based on the count data received from the lanes. Entry counts/date/time, exit counts/date/time and any totals/sub-totals shall be 100% accurate. Page 5 of 5 RFP No. 017-007 Automated Parking Count System Virginia Railway Express .
Recommended publications
  • Virginia Railway Express Strategic Plan 2004-2025
    VRE STRATEGIC PLAN Contents EXECUTIVE SUMMARY .......................................................................................................................V Current State of the Railroad ..............................................................................................................v The Strategic Planning Process..........................................................................................................vi The VRE Ridership Market................................................................................................................vii Strategic Plan Scenarios and Recommendations .............................................................................viii Core Network Needs...........................................................................................................................ix Potential Network Expansion ..............................................................................................................x Phased Service Improvement and Capital Investment Plan ..............................................................xii Financial, Institutional and Organizational Issues ..........................................................................xiii VRE Moving Forward ......................................................................................................................xiv 1. CURRENT STATE OF THE RAILROAD..........................................................................................1 VRE SYSTEM OVERVIEW .........................................................................................................................1
    [Show full text]
  • Appendix O: Hazardous Materials Site Information
    HAZARDOUS MATERIALS SITE O INFORMATION D.C. TO RICHMOND SOUTHEAST HIGH SPEED RAIL FALLS CHURCH CITY BEGIN ALTERNATIVE AREA 1 ! CFP 110 (!(! (!(! (! BEGIN ALTERNATIVE AREA 2 (!I3(! CRYSTAL CITY STATION (! (! (((!!! ARLINGTON COUNTY (! (! ¨¦§395 ¨¦§295 [ ALEXANDRIACITY OF Washington, D.C. (!(! ¨¦§66 (!(! ALEXANDRIA (! ! ( ¨¦§395 STATION (!! (!( ¨¦§95 (! (!(! (! (! (!(!(! (! !! I3(!(!(! (!(! (!(((! (!! (!I (!(! (!(!(! (!(! CFP 105 (!(! ¨¦§95 (! ! O-1(! (!(!(! (!( (!(!(!(!(! (! (! (!(!(!(!( \\cltsmain\gis_data\GIS\Projects\011545_VADeptofRails-PublicTransportation\0239056_RAPS-4AltDev-ConceptEng\map_docs\mxd\DEIS\Tech Reports\Hazardous Materials\DC2RVA_AppO_FigO-1_Hazmat_8.5x11_DEIS_BW.mxd | Last Updated: 06.16.2017 CFP 100 ! 495 ¨¦§ ¨¦§195 ¨¦§295 Richmond 0 Richmond ¨¦§95 FAIRFAX Colonial Heights 0.5 COUNTY ¨¦§64 Mile State Projection:Plane Virginia@ Lambert8.5 1North inch x Conformal 11FIPS = inches4501 1 mile FeetConic Basemap: 2015 USGS Topographic Map Data Source:North VDOT American CEDAR; Datum ERIS, of 2016. 1983 Legend 1 (! Potential HAZMAT or [ Petroleum Contamination (! SUPERFUND/ CERCLA/ (! NPL Known HAZMAT Release (! Hazmat Facility I3(! (! Potential Petroleum IFRANCONIA-SPRINGFIELD Contamination (! I3 Petroleum Facility (! STATION I3 Amtrak Station II3 VRE Station II3 Amtrak/VRE Station ! VRE/WMATA Station CSXT Mileposts DC2RVA Project Corridor Alternative Area Limits Virginia Rail Lines 1,000-foot Study Area County/City Boundaries Hazardous Materials (! Figure O-1 ((!! Sites Sheet 1 of 15 !( !(!( !( ! !(( ¨¦§495 !( !!((!(!( !(( !!(!(!(!( !( !(!(!(!((( ! ¨¦§395 !( !( I3!( IFRANCONIA-SPRINGFIELD !(!( STATION [ Washington, D.C. ¨¦§66 ¨¦§395 !( ¨¦§95 !!(( !( CFP 095 !( ! ! ¨¦§95 ( !( !( !( I3 ¨¦§295 LORTON STATION ¨¦§195 Richmond !( LORTON AUTO 0 ¨¦§64 I3 ¨¦§95 TRAIN STATION Colonial Heights !( 0.5 !( Mile !( 1 inch = 1 mile 1 !( Projection:@ 8.5Lambert x 11 Conformal inches Conic !( State Plane Virginia North FIPS 4501 Feet Basemap:North 2015 American USGS Datum Topographic of 1983 Map !( Data Source: VDOT CEDAR; ERIS, 2016.
    [Show full text]
  • Ceo Report November 2015 Our Mission
    CEO REPORT NOVEMBER 2015 OUR MISSION The Virginia Railway Express, a joint project of the Northern Virginia Transportation Commission and the Potomac Rappahannock Transportation Commission, will provide safe, cost effective, accessible, reliable, convenient, and customer responsive commuter-oriented rail passenger service. VRE contributes to the economic vitality of its member jurisdictions as an integral part of a balanced, intermodal regional transportation system. MESSAGE FROM THE CEO – DOUG ALLEN This fall, VRE has been completing major improvement and safety projects including final preparation for the opening of Spotsylvania Station. This will become the new end-of-the-line station on the Fredericksburg Line and the first extension of VRE service since operations began in 1992. Commencement of VRE service in Spotsylvania will begin the morning of November 16. The station has 1,500 parking spaces and should considerably ease parking congestion at the Fredericksburg Station. To provide increased capacity on the Fredericksburg Line, an additional morning and evening train is planned to begin operating prior to the end of 2015. The station would not have been possible without the vision, dedication and leadership of Gary Skinner, VRE’s current Vice-Chairman and Spotsylvania County Supervisor. In anticipation of the commencement of VRE service at the Spotsylvania Station, VRE staff, Spotsylvania County Fire and Rescue, CSX and the Federal Railroad Administration have been involved to provide first responders a number of training OUR opportunities to ensure they are not only prepared in the event of an emergency, but know how to ensure their own safety if called upon. A full-scale emergency simulation at the new Spotsylvania Station platform occurred on October 31.
    [Show full text]
  • Fairfax County Transportation Status Report August 2017
    Attachment 1 Fairfax County Transportation Status Report Prepared by: Department of Transportation Capital Projects and Traffic Engineering Division August 2017 T!LE OF ONTENTS Department of Transportation Summary of Activities and Highlights March 2017 through August 2017 Projects ompleted and Under onstruction _____________________________________ 1 icycle and Pedestrian Programs _______________________________________________ 2 apital Projects and Traffic Engineering Division __________________________________ 4 apital Projects Section ____________________________________________________ 4 Traffic Engineering Section __________________________________________________ 5 oordination and Funding Division _____________________________________________ 5 Marketing, ommunications, and Fairfax ounty ommuter Services ________________ 12 Special Projects Division (Dulles Rail Phases 1 & 2) _______________________________ 14 Transit Services Division _____________________________________________________ 15 Transportation Design Division _______________________________________________ 19 Site !nalysis and Transportation Planning Division _______________________________ 20 Site !nalysis Section ______________________________________________________ 20 Transportation Planning Section ____________________________________________ 22 ounty Transportation Priorities Plan __________________________________________ 25 Transportation Priorities Plan: FY2018 – FY2020 Projects ________________________ 25 Legend L-1 Project Status Report – New Format P-i
    [Show full text]
  • Ceo Report February 2021
    CEO REPORT FEBRUARY 2021 FEBRUARY 2021 The Virginia Railway Express, a joint project of the Northern Virginia Transportation Commission and the Potomac Rappahannock Transportation Commission, will provide safe, cost‐effective, accessible, reliable, convenient, and customer responsive commuter‐oriented rail passenger service. VRE contributes to the economic vitality of its member jurisdictions as an integral part of a balanced, intermodal regional transportation system. FEBRUARY 2021 TABLE OF CONTENTS CEO REPORT I FEBRUARY 2021 TABLE OF CONTENTS SUCCESS AT A GLANCE ....................................................................................................................................... 3 ON‐TIME PERFORMANCE ................................................................................................................................... 4 AVERAGE DAILY RIDERSHIP ................................................................................................................................ 6 SUMMONSES ISSUED ......................................................................................................................................... 7 TRAIN UTILIZATION ............................................................................................................................................ 8 PARKING UTILIZATION ....................................................................................................................................... 9 FINANCIAL REPORT FOR DECEMBER 2020 .........................................................................................................
    [Show full text]
  • VRE Summer 2018 Intern Presentation Reinaldo
    MULTIMODAL ACCESSIBILITY TO VRE STATIONS REINALDO GERMANO PLANNING INTERN VIRGINIA RAILWAY EXPRESS 1 MULTIMODAL ACCESSIBILITY TO VRE STATIONS 1. BACKGROUND a. Why should multimodal accessibility to VRE stations be improved? b. What are the benefits of multimodal accessibility? c. How can we encourage multimodal accessibility? 2. CASE STUDY a. How and from where users access VRE? b. How different stations compare? c. How to boost active and public transportation as a way to access VRE stations? 3. FUTURE STUDIES AND LESSONS LEARNED VIRGINIA RAILWAY EXPRESS 2 THE EASIER IT IS TO ACCESS THE SYSTEM, THE MORE LIKELY PEOPLE ARE TO USE IT TRIP FIRST MILE VRE LAST MILE 4% 4% 7% 5% 4% 6% 20% 62% 87% VIRGINIA RAILWAY EXPRESS 2017 VRE Master Agreement Survey 3 WHY SHOULD MULTIMODAL ACCESSIBILITY TO VRE STATIONS BE IMPROVED? • Although the streets and infrastructure that comprise the first and last mile fall outside the boundaries of VRE jurisdiction and control, they remain critical components of an effective service. • It is possible to increase ridership without increasing the need to provide more parking if fewer people drive alone to stations and more people carpool, take the bus, bike, or walk to stations. • Federal, state, regional, and local policies support increased use of public transportation as a means to ease roadway congestion, reduce greenhouse gas emissions, and support economic and physical health in communities. VIRGINIA RAILWAY EXPRESS 4 BENEFITS OF MULTIMODAL ACCESSIBILITY VRE + Multimodal accessibility = User Economic Ridership
    [Show full text]
  • BURKE CENTRE NOW an AMTRAK STOP Tickets May Be Booked on Amtrak.Com
    FOR IMMEDIATE RELEASE ATK-10-007 January 14, 2009 Contact: Jennifer Pickett DRPT 804 786.7432 [email protected] Karina Romero Amtrak 202 906.3860 [email protected] BURKE CENTRE NOW AN AMTRAK STOP Tickets may be booked on Amtrak.com RICHMOND & WASHINGTON, D.C. – Beginning January 18, Amtrak Virginia passengers have one more option when traveling on Amtrak’s Northeast Regional service from Lynchburg as the Burke Centre station becomes an Amtrak stop. Previously the station only provided connecting service for Virginia Railway Express passengers. With this new designation, passengers may now book travel to and from Burke Centre on Amtrak.com. “By adding Burke Centre to the Amtrak system, the rail travel possibilities from central Virginia are significantly enhanced,” said Jay McArthur of Amtrak’s Policy and Development Department, noting that passengers may now book travel to and from Burke Centre to any of the more than 500 stations Amtrak serves. “With this new stop in Fairfax County, we’re providing better access to Amtrak service in one of the most densely populated counties in Virginia,” said Charles M. Badger, Director of the Virginia Department of Rail and Public Transportation. The Northeast Regional service between Lynchburg and the Northeast Corridor now has Virginia stops in Charlottesville, Culpeper, Manassas, Burke Centre and Alexandria. The stop at L’Enfant Plaza will continue to provide connecting service for Virginia Railway Express passengers. With the new rail service, which began October, 1, 2009, a passenger can now travel directly from Lynchburg to destinations as far north as Boston and never have to change trains.
    [Show full text]
  • 9401 Burke Road Burke, VA 22015
    The train carrying Amtrak BurkeBurke officials on their ‘Whistle Stop’ tour arrives at Burke Centre Station. Classified, Page 16 Classified, ❖ BurkeBurke CentreCentre Calendar, Page 10 Calendar, ❖ ExpressExpress News,News, PagePage 33 Sports, Page 12 online at www.connectionnewspapers.com Quick Thinking Recognized News, Page 3 Requested in home 10-9-09 home in Requested Time sensitive material. sensitive Time 37th District Postmaster: Attention PERMIT #86 PERMIT House Race WV Martinsburg, PAID News, Page 4 Postage U.S. PRSRT STD PRSRT Photo by Justin Fanizzi/The Connection October 8-14, 2009 Volume XXIII, Number 40 www.ConnectionNewspapers.com Burke Connection ❖ October 8-14, 2009 ❖ 1 Clifton Day Open House Tour • Oct. 11, 1–4 11451 Quailwood Manor Dr., Fairfax Station 7780 Kelly Ann Court, Fairfax Station $1,195,000 $1,175,000 Wonderful move-up home with room for everyone! This home features grand room sizes, dramatic 10-ft ceilings, and gleaming hardwood floors! A gorgeous sunroom with vaulted ceilings and a spacious main level library will make working at home seem like fun! The renovated kitchen is a true gourmet’s delight: from the granite counters, to the professional stainless appliances, to the custom cherry cabinetry, you will love cooking for the family! Upstairs, find a romantic master with fireplace and sitting room, 3 additional bedrooms and 3 full baths. Each room in this house is super sized! Use your imagination to complete the full walk- 5 Minutes to Fairfax County Parkway. One of Fairfax Station’s out basement. Set on 5 private acres on a quiet private court. Welcome home! prettiest neighborhoods.
    [Show full text]
  • Monthly Commission Materials
    MONTHLY COMMISSION MATERIALS September 2018 MEETING OVERVIEW – September 6, 2018 Action Items Include: • Resolution of Support of CTB’s Policy and Guidelines for Implementation of Governance and Funding Reforms for WMATA • Letter to WMATA Regarding Parking Pilots and Other Parking Programs • Testimony to CTB on DRPT’s Proposed Prioritization Approach for State Transit Capital Funding and Transit Strategic Plans • Office Lease Amendment Other Meeting Highlights: • Discussion with WMATA Board Chairman Jack Evans • Reports from the Interim WMATA Committee and the Virginia WMATA Board Members • Proposed Changes to the NVTC By-Laws • Updates on the I-66 Commuter Choice Program, the Northern Virginia Transit Response Coordination Program, Transit Ridership, and VRE TABLE OF CONTENTS NVTC September 6, 2018 Commission Agenda ............................................................. 3 Agenda Item 1 Opening Remarks Agenda Item 2 Oath of Office for New Commissioners .............................................. 5 Agenda Item 3 Minutes of the July 5, 2018 Meeting .................................................... 7 Agenda Item 4 Washington Metropolitan Area Transit Authority (WMATA) ............ 23 Agenda Item 5 Proposed Changes to the NVTC By-Laws ....................................... 41 Agenda Item 6 Testimony to the CTB ......................................................................... 53 Agenda Item 7 Office Lease Amendment ................................................................... 57 Agenda Item 8 I-66 Commuter Choice
    [Show full text]
  • Ceo Report October 2020
    CEO REPORT OCTOBER 2020 OCTOBER 2020 The Virginia Railway Express, a joint project of the Northern Virginia Transportation Commission and the Potomac Rappahannock Transportation Commission, will provide safe, cost‐effective, accessible, reliable, convenient, and customer responsive commuter‐oriented rail passenger service. VRE contributes to the economic vitality of its member jurisdictions as an integral part of a balanced, intermodal regional transportation system. OCTOBER 2020 TABLE OF CONTENTS CEO REPORT I OCTOBER 2020 TABLE OF CONTENTS SUCCESS AT A GLANCE ....................................................................................................................................... 3 ON‐TIME PERFORMANCE ................................................................................................................................... 4 AVERAGE DAILY RIDERSHIP ................................................................................................................................ 6 SUMMONSES ISSUED ......................................................................................................................................... 7 TRAIN UTILIZATION ............................................................................................................................................ 8 PARKING UTILIZATION ....................................................................................................................................... 9 FINANCIAL REPORT FOR MARCH 2020 ..............................................................................................................
    [Show full text]
  • VRE OPERATIONS BOARD MEETING April 16, 2021 – 9:00 A.M
    VRE OPERATIONS BOARD MEETING April 16, 2021 – 9:00 A.M. Finance Committee Meeting – Follows Adjournment of Operations Board Meeting VIA WebEx 1. Roll Call 2. Consent Agenda A. Resolution Finding Need to Conduct April 16, 2021 Meeting Electronically B. Approval of Agenda C. Authorization to Issue an Invitation for Bids for Repair and Overhaul of Air Brake Equipment D. Authorization to Issue an Invitation for Bids for Rehabilitation of Wheelsets and Traction Motor Assemblies 3. Approval of Minutes from the March 19, 2021 VRE Operations Board Meeting 4. Chair’s Comments 5. Chief Executive Officer’s Report 6. Virginia Railway Express Riders’ and Public Comment 7. Action Items: A. Authorization to Exercise a Contract Option and Amend a Task Order for Maintenance Services for VRE Facilities B. Authorization to Exercise a Contract Option for Custodial and Seasonal Services for VRE Facilities C. Authorization to Execute a Right of Entry Agreement for MCBQ Construction Activities Adjacent to the VRE Quantico Station Parking Lot D. Recommend Authorization to Execute the Amended and Restated Operating Access and Amended Master Lease Agreements with CSX Transportation 8. Information Items: A. Spending Authority Report B. Construction Manager/General Contractor (CM/GC) Alternative Delivery Method C. Use of Federal Relief Funds in the FY 2022 Operating Budget 9. Closed Session 10. Operations Board Member’s Time The Next VRE Operations Board Meeting will be on May 21, 2021- 9:00 A.M. 2 Virginia Railway Express Operations Board Resolution 2A-04-2021 Resolution Finding Need to Conduct April 16, 2021 Meeting Electronically WHEREAS, on March 12, 2020, the Governor of Virginia declared a state of emergency in Virginia in response to the spread of novel coronavirus, or COVID-19, a communicable disease of public health threat as so declared by the State Health Commissioner on March 7, 2020 (“COVID-19”); and, WHEREAS, in subsequent Executive Orders, particularly Executive Order Nos.
    [Show full text]
  • Ceo Report December 2020
    CEO REPORT DECEMBER 2020 DECEMBER 2020 The Virginia Railway Express, a joint project of the Northern Virginia Transportation Commission and the Potomac Rappahannock Transportation Commission, will provide safe, cost‐effective, accessible, reliable, convenient, and customer responsive commuter‐oriented rail passenger service. VRE contributes to the economic vitality of its member jurisdictions as an integral part of a balanced, intermodal regional transportation system. DECEMBER 2020 TABLE OF CONTENTS CEO REPORT I DECEMBER 2020 TABLE OF CONTENTS SUCCESS AT A GLANCE ....................................................................................................................................... 3 ON‐TIME PERFORMANCE ................................................................................................................................... 4 AVERAGE DAILY RIDERSHIP ................................................................................................................................ 6 SUMMONSES ISSUED ......................................................................................................................................... 7 TRAIN UTILIZATION ............................................................................................................................................ 8 PARKING UTILIZATION ....................................................................................................................................... 9 FACILITIES UPDATE ...........................................................................................................................................
    [Show full text]