Public Private Partnership in

Annuity Project

DRAFT CONCESSION AGREEMENT

VOLUME-II: SCHEDULES

FOR

RSHIP Package-2 : Development and Maintenance of Barmer -Sindari - Jalore section of State Highway -16 and Ahore- Bali- Mundra ( to Mundra) section of State Highway -16 (Total length: 178.00 Km) under Design, Build, Operate/ Maintain and Transfer on Annuity Mode.

Public Works Department Government of

1

SCHEDULE-A (See Clause 10.1)

SITE OF THE PROJECT

1 The Site

1.1 Site of Two Lane Project shall include the land, buildings, structures and road works as described in Annex-I of this Schedule-A.

1.2 An inventory of the Site including the land, buildings, structures, road works, trees and any other immovable property on, or attached to, the Site shall be prepared jointly by the Authority Representative and the Concessionaire, and such inventory shall form part of the memorandum referred to in Clause 10.3.1 of the Agreement.

1.3 Additional land required for the Project has been described in Annex-I of this Schedule-A. This land shall be acquired by the Authority, at its own cost and upon acquisition, such land shall form part of the Site and vest in the Authority.

2

Annex – I (Schedule-A) Site for Two-Laning

1. Site The Site of the Two Lane Project comprises the sections of State Highway No.16 as under:

(a) Barmer-Sindari- Jalore Section : This highway commences from km 1+650 at Junction with NH-68 (Shaheed Amar Jawan Circle in Barmer town) to km 151+400 at Junction with NH-325 near Bishangarh village in the State of Rajasthan having total existing length of 149.75 kms and; (b) Ahore-Bali- (Sanderao to Mundara) Section: This highway commences from km 224+700 at Junction with NH-62 & NH-325 (Sanderao Bypass Flyover) to km 254+200 at Mundara in the State of Rajasthan having total existing length of 29.50 kms. The road stretch from km 235+450 to 236+100 in which an ROB is proposed to be constructed across railway line by the DFCC Ltd. This stretch has been excluded from the Site.

Barmer Sindhari Bishangarh

Sanderao--Mundara

Key Map of the Project

3

The land, carriageway and structures comprising the Site are described below. 2. Land The Site of the Project comprises the land described in Table A-1(i) and Table A- 1(ii). Table A-1(i) Site of Project (a) Barmer-Sindari- Jalore Section Existing Chainages Existing S. (in km) RoW Remarks No. From To (in m) Barmer-Chawa Stretch Starts at Junction 1 1+650 1+700 40.0 with NH-68 2 1+700 2+000 35.0 -- 3 2+000 4+000 24.0 -- 4 4+000 5+500 20.0 -- 5 5+500 5+525 21.0** -- 6 5+525 6+600 24.0 -- 7 6+600 6+700 30.0 -- 8 6+700 6+800 22.0** -- 9 6+800 7+100 25.0 -- 10 7+100 7+300 24.0** -- 11 7+300 11+100 24.0 -- 12 11+100 12+425 24.0** -- 13 12+425 12+525 21.0 -- 14 12+525 15+000 27.0 -- 15 15+000 15+930 24.0** -- 16 15+930 16+030 22.0 -- 17 16+030 19+150 25.0 -- 18 19+150 19+250 22.0 -- 19 19+250 21+400 25.0 -- 20 21+400 22+500 24.0** -- 21 22+500 23+200 24.0 -- 22 23+200 25+500 25.0 -- 23 25+500 28+400 30.0 -- Chawa-Sindhari Stretch 24 0+000 1+400 25.0 -- 25 1+400 4+000 28.0 -- 26 4+000 5+400 24.0 -- 27 5+400 5+800 23.0 -- 28 5+800 6+630 28.0 -- 29 6+630 7+480 24.0** -- 30 7+480 11+800 30.0 --

4

31 11+800 12+800 29.0 -- 32 12+800 13+050 25.0 -- 33 13+050 13+480 30.0 -- 34 13+480 14+600 24.0 -- 35 14+600 14+700 21.0 -- 36 14+700 15+200 24.0** -- 37 15+200 15+600 30.0 -- 38 15+600 15+800 24.0** -- 39 15+800 16+280 24.0 -- 40 16+280 16+730 35.0 -- 41 16+730 18+675 24.0 -- 42 18+675 18+650 22.0 -- 43 18+650 21+550 28.0 -- 44 21+550 21+650 24.0 -- 45 21+650 22+430 24.0 -- 46 22+430 22+510 24.0 -- 47 22+510 22+750 25.0 -- 48 22+750 22+850 24.0 -- 49 22+850 24+000 25.0 -- 50 24+000 29+150 24.0** -- 51 29+150 32+000 32.0 -- 52 32+000 33+150 24.0 -- 53 33+150 36+000 30.0 -- 54 36+000 36+450 24.0 -- 55 36+450 37+000 26.0 -- Sindhari-Bishangarh Stretch 56 0+000 11+000 35.0 -- 57 11+000 13+100 32.0 -- 58 13+100 13+400 24.0** -- 59 13+400 16+000* 25.0 -- 60 83+000* 87+350 30.0 -- 61 87+350 87+450 30.0 -- 62 87+450 88+850 30.0 -- 63 88+850 88+950 30.0 -- 64 88+950 91+500 30.0 -- 65 91+500 94+300 22.0 -- 66 94+300 97+600 30.0 -- 67 97+600 99+520 25.0 -- 68 99+520 99+520 40.0 -- 69 99+520 99+520 28.0 -- 70 99+520 99+620 28.0 -- 71 99+620 105+320 28.0 -- 72 105+320 105+420 28.0 -- 73 105+420 108+630 28.0 -- 74 108+630 109+230 21.0 -- 75 109+230 112+805 30.0 --

5

76 112+805 112+980 26.0 -- 77 112+980 113+230 24.0** -- 78 113+230 114+780 28.0 -- 79 114+780 114+880 28.0 -- 80 114+880 117+380 28.0 -- 81 117+380 117+530 28.0 -- 82 117+530 117+730 28.0 -- 83 117+730 117+905 22.0 -- 84 117+905 118+080 24.0 -- 85 118+080 118+180 24.0 -- 86 118+180 119+230 28.0 -- 87 119+230 120+480 30.0 -- 88 120+480 121+980 28.0 -- 89 121+980 122+930 12.0** -- 90 122+930 126+180 14.0 -- 91 126+180 126+330 22.0 -- 92 126+330 126+880 24.0 -- 93 126+880 127+080 30.0 -- 94 127+080 127+380 24.0 -- 95 127+380 127+455 18.0 -- 96 127+455 127+630 17.0 -- 97 127+630 127+880 24.0 -- 98 127+880 128+030 20.0 -- 99 128+030 129+680 24.0 -- 100 129+680 129+830 18.0 -- 101 129+830 132+180 24.0 -- 102 132+180 132+330 24.0 -- 103 132+330 133+330 24.0 -- 104 133+330 133+480 16.0 -- 105 133+480 133+680 16.0 -- 106 133+680 137+280 24.0 -- 107 137+280 137+380 24.0 -- 108 137+380 137+780 24.0 -- 109 137+780 137+955 22.0 -- 110 137+955 138+205 22.0 -- 111 138+205 138+330 24.0 -- 112 138+330 138+505 22.0 -- 113 138+505 139+380 25.0 -- 114 139+380 139+680 22.0 -- 115 139+680 140+980 24.0 -- 116 140+980 141+180 24.0 -- 117 141+180 151+155 32.0 -- Ends at Junction 118 151+155 151+520 40.0 with NH-325

6

*Km 16 is changed to km 83 & subsequent chainages also which are part of the highway in + **RoW in physical possession of PWD since long but requires updating of land records of rights / transfer of land in name of the PWD+

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section

Existing Chainages ( in km) Existing RoW S. No. Remarks From To (in m) Starts at Junction with NH-62 & NH-325 (Fly 1 224+700 225+050 35 over) 2 225+050 227+900 35 -- 3 227+900 228+150 35 -- 4 228+150 228+850 35 -- 5 228+850 230+450 35 -- 6 230+450 230+550 28 -- 7 230+550 230+575 21 -- 8 230+575 230+600 19 -- 9 230+600 230+655 13 -- 10 230+655 230+705 18 -- 11 230+705 230+755 23 -- 12 230+755 231+035 28 -- 13 231+035 231+300 24 -- 14 231+300 231+640 24 -- 15 231+640 231+800 33 -- 16 231+800 231+900 31 -- 17 231+900 232+600 35 -- 18 232+600 232+800 40 -- 19 232+800 233+000 45 -- 20 233+000 233+200 36 -- 21 233+200 233+400 44 -- 22 233+400 233+600 44 -- 23 233+600 233+800 40 -- 24 233+800 234+100 33 -- 25 234+100 235+450 35 -- 26 235+450 236+100 32 -- 27 236+100 236+250 31 --

7

28 236+250 237+000 23 -- 29 237+000 237+200 23 -- 30 237+200 237+400 25 -- 31 237+400 237+650 22 -- 32 237+650 237+800 22 -- 33 237+800 238+000 21 -- 34 238+000 238+200 32 -- 35 238+200 238+400 32 -- 36 238+400 238+600 31 -- 37 238+600 238+800 27 -- 38 238+800 239+000 29 -- 39 239+000 239+200 30 -- 40 239+200 239+400 33 -- 41 239+400 239+600 27 -- 42 239+600 239+800 19 -- 43 239+800 240+000 32 -- 44 240+000 240+200 29 -- 45 240+200 240+400 30 -- 46 240+400 240+600 30 -- 47 240+600 242+850 35 -- 48 242+850 243+400 33 -- 49 243+400 243+800 12 -- 50 243+800 244+000 23 -- 51 244+000 244+200 26 -- 52 244+200 244+350 21 -- 53 244+350 244+600 16 -- 54 244+600 244+805 24 -- 55 244+805 245+005 24 -- 56 245+005 245+205 22 -- 57 245+205 245+405 25 -- 58 245+405 245+605 26 -- 59 245+605 245+805 30 -- 60 245+805 246+005 35 -- 61 246+005 246+205 32 -- 62 246+205 246+405 34 -- 63 246+405 246+605 32 -- 64 246+605 246+705 32 --

8

65 246+705 246+805 30 -- 66 246+805 247+005 29 -- 67 247+005 247+205 30 -- 68 247+205 247+405 35 -- 69 247+405 247+605 32 -- 70 247+605 247+805 35 -- 71 247+805 247+955 35 -- 72 247+955 248+205 33 -- 73 248+205 248+405 31 -- 74 248+405 248+705 31 -- 75 248+705 248+805 35 -- 76 248+805 249+025 38 -- 77 249+025 249+225 30 -- 78 249+225 249+405 32 -- 79 249+405 249+605 30 -- 80 249+605 249+825 32 -- 81 249+825 249+965 30 -- 82 249+965 250+205 35 -- 83 250+205 250+405 42 -- 84 250+405 250+605 40 -- 85 250+605 250+805 35 -- 86 250+805 251+005 35 -- 87 251+005 251+205 35 -- 88 251+205 251+405 34 -- 89 251+405 251+605 33 -- 90 251+605 251+805 40 -- 91 251+805 252+005 43 -- 92 252+005 252+205 38 -- 93 252+205 252+405 36 -- 94 252+405 252+605 32 -- 95 252+605 252+805 31 -- 96 252+805 253+005 30 -- 97 253+005 253+205 33 -- 98 253+205 253+405 40 -- 99 253+405 253+605 33 -- 100 253+605 253+805 35 -- 101 253+805 254+005 37 --

9

102 254+005 254+125 33 Ends at Mundara

Table A-1 (ii) Site of Project (Bypass +new alignment)

(a) Barmer-Sindari- Jalore Section Existing Chainage (in km) Name of Proposed ROW Sl. No. Bypass +New (in m) From To alignment Nil

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section Existing Chainage (in km) Name of Proposed ROW Sl. No. Bypass +New (in m) From To alignment Nil

3. Carriageway 3.1. Carriageway of Highway The present width of carriageway and paved shoulders of the highways are given in Table A-2.

Table A-2 Width of carriageway (a) Barmer-Sindari- Jalore Section Existing Width of Sl. Chainage(km) Type of Width of Paved Length No. From To Carriageway Carriageway Shoulders (in m) 1 1+650 28+200 26.55 BT 2L Nil 2 0+000 14+800 14.80 BT 1L Nil 3 14+800 16+800 2.00 BT 2L Nil

4 16+800 32+300 15.50 BT 1L Nil 5 32+300 34+000 1.70 BT 1.5L Nil 6 34+000 37+050 3.05 BT 2L Nil 7 0+000 16+000 16.00 BT 1.5L Nil 8 83+000 97+000 14.00 BT 1.5L Nil

10

9 97+000 99+200 2.20 BT 2L Nil 10 99+200 99+500 0.30 Rigid 2L + Nil 11 99+500 121+800 22.30 BT 2L Nil 12 121+800 122+850 1.05 Rigid 2L+ Nil 13 122+850 127+200 4.35 BT 2L Nil 14 127+200 127+800 0.60 Rigid 2L+ Nil 15 127+800 129+400 1.60 BT 2L Nil 16 129+400 130+000 0.60 Rigid 2L+ Nil 17 130+000 132+800 2.80 BT 2L Nil 18 132+800 133+200 0.40 Rigid 1L Nil 19 133+200 133+400 0.20 Rigid 2L+ Nil 20 133+400 146+000 12.60 BT 2L Nil 21 146+000 146+600 0.60 Rigid 2L+ Nil 22 147+600 151+400 4.80 BT 2L Nil (2L means “Two Lane”, 1+5L means “Intermediate Lane”, 2L+ means “Two-Lane with Paved Shoulders” & 4L Divided means “Four Lane divided Carriageway”)

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section

Existing Chainage Width of Sl. (km) Type of Width of Paved Length No. From To Carriageway Carriageway Shoulders (m) 1 224+700 225+050 0.35 BT 2L Nil 2 225+050 230+400 5.35 BT 1.5L Nil 3 230+400 230+800 0.40 BT 2L Nil 4 230+800 235+200 4.40 BT 1.5L Nil 5 235+200 235+400 0.20 Rigid 2L Nil 6 235+400 235+450 0.05 BT 4L Nil 7 235+450 236+100 0.65 Proposed ROB to be Constructed by DFCCL 8 236+100 236+600 0.50 Rigid 4L Nil 9 236+600 237+200 0.60 BT 4L Nil 10 237+200 240+900 3.70 BT 1.5L Nil 11 240+900 241+000 0.10 Rigid 2L Nil 12 241+000 243+000 2.00 BT 1.5L Nil 13 243+000 243+200 0.20 BT 4L Nil 14 243+200 243+400 0.20 BT 2L Nil

11

15 243+400 244+200 0.80 BT 4L Nil 16 244+200 248+900 4.70 BT 1.5L Nil 17 248+900 249+000 0.10 Rigid 2L Nil 18 249+000 254+200 5.20 BT 1.5L Nil (2L means “Two Lane”, 1+5L means “Intermediate Lane”, 2L+ means “Two-Lane with Paved Shoulders” & 4L Divided means “Four Lane divided Carriageway”) 4. Major Bridges The existing major bridges on the Site of the Project are given in Table A-3

Table A-3 List of major bridges (a) Barmer-Sindari- Jalore Section

Sl. No. Existing Type of No. of Spans Width (in Chainage Structure Mtrs) (in km) Nil

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section Sl. No. Existing Chainage Type of No. of Spans Width Structure (in km) (in m) 1 244+400 RCC Slab 33Spans of 4.75m 7.50 each

5. Railway Crossings 5.1. Railway Level Crossings The details of Railway level crossings on the Site are given in Table A-4.

Table A-4 List of Railway level crossings (a) Barmer-Sindari- Jalore Section Existing Chainage L.C Number + Railway Width of Sl. No. (in km) km Railway Land Nil

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section Existing Chainage (km) L.C Number+ Railway km Width of Sl. No. Railway Land

12

1 235+700 C-81* 45m *Note: ROB on this Level Crossing is proposed to be constructed by DFCC Ltd., hence the concessionaire is not required to construct the ROB. 5.2. Road Over / Under Bridges (ROB/RUB) There is no existing ROB and RUB on the Site. 6. Grade Separators The Project Site does not have any existing Grade Separators such as Interchanges, Vehicular under Pass, Vehicular Over Pass, Pedestrian Crossing, Cattle Crossing and Foot Over Bridges. 7. Minor Bridges The details of existing minor bridges on the Site are given in Table A-5

Table A-5 List of minor bridges (a) Barmer-Sindari- Jalore Section S. Existing Chainage Type of No. of Spans Width No. Structure (in km) No x span (in m) (in m) Nil

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section Sl. Existing Chainage Type of No. of Spans Width No. Structure (in km) No x span (in m) (in m)

1 230+920 RCC Slab 10 x 2.90 7.65 2 230+950 RCC Slab 7 x 6.80 7.60 3 233+900 RCC Slab 5 x 3.50 12.00 4 243+400 RCC Slab 2 x 5.50 7.50 8. Culverts

The details of existing culverts on the Site are given in Table A-6

Table A-6 List of culverts (a) Barmer-Sindari- Jalore Section Sl. No. Existing Type of Culvert Size Overall Chainage Width (in km) (in m.)

13

Barmer-Chawa Stretch 1 7+280 Pipe Culvert 3 X 900mm 12.50 2 7+740 Pipe Culvert 3 X 900mm 12.45 Chawa-Sindhari Stretch 3 15+775 Pipe Culvert 4 X 1000mm 12.10 4 17+730 Pipe Culvert 3 X 1000mm 7.60 5 23+150 Flush Causeway 30.0 m length 7.60 6 28+160 Pipe Culvert 3x 600mm 7.40 7 2 x 600mm 12.00 35+190 Vented Causeway 6 x 900mm 8 36+065 RCC Slab 1 x 2.40m 7.20 Sindhari - Bishangarh Stretch 9 1+450 Flush Causeway 36.70m length 12.40

10 1+830 Flush Causeway 25.50m length 12.30

11 3+790 RCC Slab 1X2.00m 12.20

12 4+260 Flush Causeway 25.30m length 12.20

13 10+540 Flush Causeway 24.50m length 12.00 14 13+880 RCC Slab 1 X 2.00m 8.60

15 14+530 Flush Causeway 77.60m length 12.50

16 14+830 Flush Causeway 30m length 12.50

17 18+100 Flush Causeway 45.00m length 12.50

18 27+580 Flush Causeway 50.00m length 12.50

19 32+975 RCC Slab 1 X 1.50m 11.60

20 33+630 Pipe Culvert 3 X 900mm 7.30

21 33+920 RCC Slab 1 X 1.50m 11.70

22 37+240 RCC Slab 1 X 1.50m 11.60

23 39+480 RCC Slab 1 X 1.50m 11.60

24 42+570 RCC Slab 1 X 1.50m 11.90

25 51+380 RCC Slab 1 X 4.00m 8.40

26 61+300 RCC Slab 1 X 1.50m 10.00

14

27 61+675 RCC Slab 1 X 1.50m 10.00

28 64+080 RCC Slab 1 X 3.00m 10.00

29 66+360 Skew RCC Slab 1 X 1.50m 11.80

30 69+530 RCC Slab 1 X 1.50m 11.80

31 71+080 RCC Slab 1 X 1.50m 9.90

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section Sl. No. Existing Type of Culvert Size Overall Chainage Width (in km) (in m) 1 226+500 Flush Causeway 20m length 8.10 2 228+600 RCC Slab (2 x 1.50m + 1 x 1.70m) 13.00 3 229+000 RCC Slab (1 x 0.90m +1 x 0.85m) 12.90 4 229+400 RCC Slab 2 x 0.90m 12.90 5 229+900 RCC Slab 1 x 0.95m 12.90 6 230+200 RCC Slab 1 x 0.90m 12.10 7 230+300 RCC Slab 1 x 0.90m 12.90 8 230+600 RCC Slab 3 x 1.80m 10.40 9 231+200 RCC Slab 1 x 1.50m 12.10 10 231+600 RCC Slab 1 x 0.80m 13.10 11 232+000 RCC Slab 1 x 0.80m 13.10 12 233+700 RCC Slab 3 X 1.5 m 13.10 13 234+800 RCC Slab 1 x 0.80m 12.90 14 235+800 RCC Slab 1 x 3.00m 12.50 15 236+700 RCC Slab 2 x 3.00m 13.20 16 237+800 RCC Slab 1 x 1.55m 12.10 17 243+500 RCC Slab 1 x 0.90m 6.70 18 245+400 Vented causeway 4 x 1000mm dia 8.90 19 246+100 Vented causeway 2 x 1000mm dia 8.50 20 248+400 Flush causeway 101 m length 8.10

21 249+200 Flush causeway 7.5 m length 8.10

22 249+900 Flush causeway 10.50m length 8.10 23 250+000 RCC Slab 1 x 1.00m 8.10

9. Total number of structures

15

The total number of existing structures on the Site is noted below:

(a) Barmer-Sindari- Jalore Section: (i) No. of Major Bridges - Nil (ii) No. of Railway Over Bridges - Nil (iii) No. of Grade Separators - Nil (iv) No. of Minor Bridges - Nil (v) No. of Vehicular & Non-vehicular Underpasses - Nil (vi) No.of Box Culverts - Nil (vii) No. of Pipe Culverts - 6 (viii) No. of Slab Culverts - 15

(ix) No. of Flush causeways - 9 (x) No. of Vented Causeways - 1

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section: (i) No. of Major Bridges - 1 (ii) No. of Railway Over Bridges - Nil (iii) No. of Grade Separators - Nil (iv) No. of Minor Bridges - 4 (v) No. of Vehicular & Non-vehicular Underpasses - Nil (vi) No. of Box Culverts - Nil (vii) No. of Pipe Culverts - Nil (viii) No. of Slab Culverts - 17 (ix) No. of Flush Causeways - 4 (x) No. of Vented Causeways - 2

10. Bus bays & Truck Lay byes

The total number of existing bus bays and truck lay byes on the Project Site is noted below:

(a) Barmer-Sindari- Jalore Section: (i) No. of Bus bays on LHS - Nil (ii) No. of Bus bays on RHS - Nil

16

(iii) No. of Truck lay-byes on LHS - Nil (iv) No. of Truck lay-byes on RHS - Nil

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section: (i) No. of Bus bays on LHS - Nil (ii) No. of Bus bays on RHS - Nil (iii) No. of Truck lay-byes on LHS - Nil (iv) No. of Truck lay-byes on RHS - Nil 11. Intersections The existing intersections on the Site are given in Table A-7 Table A-7 List of intersections (a) Barmer-Sindari- Jalore Section: Sl. Existing Chainage Type of Category of Cross Road No. (in km) Intersections NH+SH+MDR+ODR+VR

Barmer-Chawa Stretch 1 1+650 + NH-68

4 12+260 T VR

5 16+350 T VR

6 18+430 T VR

7 22+800 T VR

8 28+280 Y SH-40 Chawa-Sindhari Stretch 9 5+300 T VR

10 6+000 T VR

11 9+330 T VR

12 9+360 T VR

13 14+750 T VR

14 14+780 T VR

15 15+700 T VR

16 20+350 T VR

17

17 23+360 T VR

18 32+080 T VR

19 33+850 T VR

20 34+980 T VR

21 36+125 T VR

22 36+900 + SH-28 Sindhari-Bishangarh Stretch 23 6+750 Y VR 24 12+500 T SH-16A 25 13+975 + VR 26 85+200 + VR 27 96+550 T VR 28 100+450 T SH-31A 29 108+860 T VR 30 119+900 T SH-16B 31 122+040 Y MDR-16 32 133+350 T VR 33 134+030 T VR 34 138+530 T VR 35 131+280 T VR 36 151+500 T NH-325

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section Sl. No. Existing Type of Category of Cross Road Chainage Intersections NH+SH+MDR+ODR+VR (in km) 1 224+700 + NH-62 & NH-325 2 224+800 T NH-62

3 225+000 T NH-62 4 228+400 Y VR 5 231+100 Y VR 6 233+600 T VR 7 235+600 + VR 8 236+050 T VR

18

9 237+000 + VR 10 240+900 + VR 11 243+100 T VR 12 243+200 Y MDR-106 13 247+100 T VR 14 254+100 T VR

(NH: National Highway, SH: State Highway, MDR: Major District Road, ODR: Other District Road, VR: Village Road) 12. Stretches passing through abutting Forest area The Project does not pass through or abuts any forest area.

13. Stretches passing through abutting wildlife area The Project does not pass through or abuts any wildlife area.

14. Environmentally Sensitive Areas The Project does not pass through or abuts any wildlife area, environmentally sensitive areas such as mangroves, mud floors, bird sanctuaries etc.

15. Built up Area

The sections of Project passing through built-up areas are given in Table A-8. Table A-8: Sections passing through built-up areas

(a) Barmer-Sindari- Jalore Section Name of Built- Existing Chainage (in km) Length Sl. No. up Area From To (kms) 1 Barmer 1+650 4+650 3.00 2 Rawatsar 22+800 23+150 0.35 3 Chawa 27+900 28+250 0.50 0+000* 0+150 4 Sarnu Panji 14+900 15+500 0.60 5 Sindhari 35+700 37+050 2.70 0+000** 1+350 6 Sirana 88+500 89+000 0.500 7 Jeewana 99+100 100+400 1.30

19

8 Babtara 108+500 109+200 0.70 9 Balera 117+400 118+000 0.60 10 Sayla 120+200 123+000 2.80 11 Otwala 127+200 128+000 0.80 12 Kharal 129+400 130+000 0.60 13 Ummedabad 132+000 134+400 2.40 14 Ealana 137+300 138+000 0.70 15 Ratuja 143+600 144+000 0.40 16 Mandwala 146+600 147+900 1.30 *0 at Chawa **0 at Sindhari (b) Ahore-Bali-Mundara (Sanderao-Mundara) Section Name of Built- Existing Chainage Length Sl. No. up Area From To (kms) 1 Falna 234+950 237+400 2.45 2 Shri Sela 240+400 241+000 0.60 3 Bali 242+900 244+350 2.45 4 Kot-Baliyan 248+900 249+200 0.30 5 Mundara 253+800 254+200 0.40

16. Type of Terrain The types of terrain through which the Project passes are given in Table A-9. Table A-9 : Type of terrain (a) Barmer-Sindari- Jalore Section Sl. Existing Chainage Length Type of Remarks No. (in km) (km) Terrain From To 1 1+650 151+400 149.85 Plain --

(b) Barmer-Sindari- Jalore Section Sl+ Existing Chainage Length Type of Remarks No (in km) (km) Terrain From To 1 224+700 254+200 30.50 Plain --

20

17. Referencing System The relationship between the existing chainage” and design chainag for the Project is given in Table A-10. Table A-10: Relationship in referencing system

(a) Barmer-Sindari- Jalore Section Correspondin Existing g Design S. No. Chainage Chainage Remarks (in Km) (in km) Barmer-Chawa Stretch

Junction with NH-68 1 1+650 0+000 (Shaheed Amar Jawan Cricle, Barmer)

2 2 0+350 -

3 3 1+350 -

4 4 2+350 -

5 5 3+340 -

6 6 4+330 -

7 7 5+320 -

8 8 6+310 -

9 9 7+380 -

10 10 8+375 -

11 11 9+377 -

12 12 10+375 -

13 13 11+375 -

14 14 12+375 -

15 15 Missing

16 16 14+365 -

21

17 17 15+400 -

18 18 16+385 -

19 19 17+390 -

20 20 18+385 -

21 21 19+380 -

22 22 20+385 -

24 24 22+385 -

25 25 23+407 -

26 26 24+382 -

27 27 Missing

28 28 26+380 -

29 28+280 26+660 Junction with SH-40

Chawa-Sindhari Stretch 30 0 Missing Junction with SH-40

31 1 27+670 -

32 2 28+665 -

33 3 29+665 -

34 4 30+670 -

35 5 31+670 -

36 6 32+645 -

37 7 33+645 -

38 9 35+645 -

39 10 36+665 -

40 11 37+660 -

41 12 38+660 -

42 13 39+640 -

22

43 14 40+660 -

44 15 41+660 -

45 16 42+660 -

46 17 43+660 -

47 19 45+580 -

48 20 46+575 -

49 21 47+555 -

50 22 48+575 -

51 23 49+560 -

52 24 50+575 -

53 25 51+575 -

54 26 52+550 -

55 27 53+535 -

56 29 55+565 -

57 30 56+560 -

58 31 57+560 -

59 32 58+555 -

60 33 59+550 -

61 34 60+550 -

62 35 61+540 -

63 36 Missing

64 37 Missing

Mega 65 Highway (SH- 63+550 Sindhari 28) Crossing

Sindhari-Bishangarh Section

66 1 64+580 Sindhari-Bishangarh Section

23

67 2 65+580 -

68 3 66+610 -

69 4 67+625 -

70 5 68+625 -

71 6 69+655 -

72 7 70+585 -

73 8 71+585 -

74 9 72+580 -

75 10 73+595 -

76 12 75+575 -

77 14 77+620 -

78 15 78+600 -

16 Barmer-Jalore District Border 79 79+425 83 at 79+380

80 84 80+410 -

81 85 81+415 -

82 86 82+460 -

83 87 83+445 -

85 88 84+440 -

86 90 86+440 -

87 91 87+445 -

88 92 88+440 -

89 93 89+450 -

90 94 90+455 -

91 95 91+460 -

24

92 96 92+460 -

93 97 93+460 -

94 98 94+480 -

95 100 96+480 --

96 101 97+485 --

97 102 98+485 -

98 103 99+485 -

99 104 100+515 -

100 105 101+520 -

101 106 102+510 -

102 107 103+510 -

103 108 104+505 -

104 109 105+505 -

105 110 106+500 -

106 111 107+510 -

107 112 108+525 -

108 113 109+525 -

109 114 110+525 -

110 115 111+545 -

111 116 112+545 -

112 117 113+550 -

113 118 114+570 -

114 119 115+565 -

115 120 116+565 -

116 122 118+560 --

25

117 123 119+570 --

118 124 120+560 --

119 125 121+540 -

120 126 122+540 -

122 127 123+530 -

123 128 124+520 -

124 129 125+510 -

125 130 126+510 -

126 131 127+510 -

127 132 128+510 -

128 133 Missing

129 134 130+505 -

130 135 131+505 -

131 136 132+505 -

132 139 135+440 -

134 140 136+440 -

135 141 137+440 -

136 142 138+430 -

139 143 139+450 -

140 144 140+445 -

141 145 141+530 -

142 146 142+530 -

143 147 143+530 -

144 148 144+540 -

145 149 145+540 -

26

146 150 146+540 -

147 151 147+545 -

Junction with 148 148+089 Near Bishangarh village NH-325

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section S. No. Existing Corresponding

Chainage Design Chainage Remarks (in Km) (in km) 1 Junction of NH- Sanderao bypass 0+000 62 & NH-325 Flyover,

2 225 0+350 -

3 226 1+350 -

4 227 2+350 -

5 228 3+325 -

6 229 4+345 -

7 230 5+345 --

8 231 6+345 -

9 232 7+325 -

10 233 8+325 -

11 234 9+325 --

12 235 10+325 -

13 235+450 10+750 --

14 236+100 11+400 --

15 237 12+310 -

16 238 13+305 -

17 239 14+305 -

18 240 15+305 --

27

19 241 16+305 -

20 242 17+305 -

21 243 18+305 -

22 244 19+295 -

23 245 20+295 -

24 246 21+295 -

25 247 22+295 -

26 248 23+295 -

27 249 24+295 -

28 250 25+295 -

29 251 26+295 -

30 252 27+295 -

31 253 28+295 -

32 254 29+295 -

33 254+125 29+423 End point

18. Feasibility Report

The Feasibility Report of both highway sections provided in soft copy, is for the purpose of reference only. The Authority makes no representation whatsoever, express, implicit or otherwise, regarding the accuracy, adequacy, correctness, reliability and/or completeness of any assessment, assumptions, statement or information provided by it and the Concessionaire confirms that it shall have no claim whatsoever against the Authority in this regard.

28

Annex – II (Schedule-A) Details of Proposed ROW

1. Proposed ROW Details of proposed ROW for the Project are given below:

(a) Barmer-Sindhari-Jalore Section Design Chainages Proposed S. No. (in km) RoW Remarks From To (in m) 1 0+000 0+050 40.0 -- 2 0+050 0+350 35.0 -- 3 0+350 2+350 24.0 -- 4 2+350 3+850 20.0 -- 5 3+850 3+875 24.0 -- 6 3+875 4+950 24.0 -- 7 4+950 5+050 30.0 -- 8 5+050 5+150 24.0 -- 9 5+150 5+450 25.0 -- 10 5+450 5+650 24.0 -- 11 5+650 9+450 24.0 -- 12 9+450 10+775 24.0 -- 13 10+775 10+875 24.0 -- 14 10+875 13+350 27.0 -- 15 13+350 14+280 24.0 -- 16 14+280 14+380 26.0 -- 17 14+380 17+500 25.0 -- 18 17+500 17+600 26.0 -- 19 17+600 19+750 25.0 -- 20 19+750 20+850 24.0 -- 21 20+850 21+550 24.0 -- 22 21+550 23+850 25.0 -- 23 23+850 26+750 30.0 -- 24 26+750 28+150 25.0 -- 25 28+150 30+750 28.0 -- 26 30+750 32+150 24.0 -- 27 32+150 32+550 23.0 --

29

28 32+550 33+380 28.0 -- 29 33+380 34+230 24.0 -- 30 34+230 38+550 30.0 -- 31 38+550 39+550 29.0 -- 32 39+550 39+800 55.0 -- 33 39+800 40+230 30.0 -- 34 40+230 41+350 24.0 -- 35 41+350 41+450 29.0 -- 36 41+450 41+950 24.0 -- 37 41+950 42+350 30.0 -- 38 42+350 42+550 30.0 -- 39 42+550 43+030 24.0 -- 40 43+030 43+480 35.0 -- 41 43+480 45+425 24.0 -- 42 45+425 45+400 26.0 -- 43 45+400 48+300 28.0 -- 44 48+300 48+400 29.0 -- 45 48+400 49+180 24.0 -- 46 49+180 49+260 30.0 -- 47 49+260 49+500 25.0 -- 48 49+500 49+600 34.0 -- 49 49+600 50+750 25.0 -- 50 50+750 55+900 24.0 -- 51 55+900 58+750 32.0 -- 52 58+750 59+900 24.0 -- 53 59+900 62+750 30.0 -- 54 62+750 63+200 24.0 -- 55 63+200 63+750 26.0 -- 56 63+750 74+750 35.0 -- 57 74+750 76+850 32.0 -- 58 76+850 77+150 54.0 -- 59 77+150 79+750 25.0 -- 60 79+750 84+100 30.0 -- 61 84+100 84+200 34.0 -- 62 84+200 85+600 30.0 -- 63 85+600 85+700 33.0 -- 64 85+700 88+250 30.0 --

30

65 88+250 91+050 22.0 -- 66 91+050 94+350 30.0 -- 67 94+350 95+100 25.0 -- 68 95+100 95+450 40.0 -- 69 96+000 97+250 28.0 -- 70 97+250 97+350 33.0 -- 71 97+350 101+840 28.0 -- 72 101+840 101+940 33.0 -- 73 101+940 105+150 28.0 -- 74 105+150 105+750 21.0 -- 75 105+750 109+325 30.0 -- 76 109+325 109+500 29.0 -- 77 109+500 109+750 24.0 -- 78 109+750 111+300 28.0 -- 79 111+300 111+400 31.5 -- 80 111+400 113+900 28.0 -- 81 113+900 114+050 35.5 -- 82 114+050 114+250 28.0 -- 83 114+250 114+425 31.0 -- 84 114+425 114+600 24.0 -- 85 114+600 114+700 31.0 -- 86 114+700 115+750 28.0 -- 87 115+750 117+000 30.0 -- 88 117+000 118+500 28.0 -- 89 118+500 119+500 12.0 -- 90 119+500 122+750 14.0 -- 91 122+750 122+900 32.0 -- 92 122+900 123+450 24.0 -- 93 123+450 123+650 42.0 -- 94 123+650 123+950 35.0 -- 95 123+950 124+025 23.0 -- 96 124+025 124+200 21.0 -- 97 124+200 124+450 24.0 -- 98 124+450 124+600 38.0 -- 99 124+600 126+250 24.0 -- 100 126+250 126+400 24.0 -- 101 126+400 128+750 24.0 -- 102 128+750 128+900 32.0 -- 103 128+900 129+900 24.0 -- 104 129+900 130+050 20.0 -- 105 130+050 130+250 20.0 -- 106 130+250 133+850 24.0 --

31

107 133+850 133+950 28.0 -- 108 133+950 134+350 24.0 -- 109 134+350 134+525 29.0 -- 110 134+525 134+775 52.0 -- 111 134+775 134+900 24.0 -- 112 134+900 135+075 48.0 -- 113 135+075 135+950 25.0 -- 114 135+950 136+250 52.0 -- 115 136+250 137+550 24.0 -- 116 137+550 137+750 31.0 -- 117 137+750 147+725 32.0 -- 118 147+725 148+090 40.0 --

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section

Design Chainages Proposed S. No. ( in km) RoW Remarks From To (in m) 1 0+000 0+350 35 -- 2 0+350 3+200 35 -- 3 3+200 3+500 65 TP1 4 3+500 4+200 35 -- 5 4+200 5+800 35 -- 6 5+800 5+900 28 -- 7 5+900 5+925 21 -- 8 5+925 5+950 19 -- 9 5+950 6+000 17 -- 10 6+000 6+050 18 -- 11 6+050 6+100 23 -- 12 6+100 6+380 28 -- 13 6+380 6+600 46 -- 14 6+600 6+940 24 -- 15 6+940 7+100 33 -- 16 7+100 7+200 31 -- 17 7+200 7+900 35 -- 18 7+900 8+100 40 -- 19 8+100 8+300 45 -- 20 8+300 8+500 36 -- 21 8+500 8+700 44 --

32

-- 22 8+700 8+900 44 23 8+900 9+100 40 -- -- 24 9+100 9+400 33 25 9+400 10+750 35 -- 26 10+750 11+400 32 -- 27 11+400 11+550 31 -- 28 11+550 12+300 23 -- 29 12+300 12+500 23 -- 30 12+500 12+700 25 -- 31 12+700 12+950 22 -- 32 12+950 13+100 22 -- 33 13+100 13+300 21 -- 34 13+300 13+500 32 -- 35 13+500 13+700 32 -- 36 13+700 13+900 31 -- 37 13+900 14+100 27 -- 38 14+100 14+300 29 -- 39 14+300 14+500 30 -- 40 14+500 14+700 33 -- 41 14+700 14+900 27 -- 42 14+900 15+100 19 -- 43 15+100 15+300 32 -- 44 15+300 15+500 29 -- 45 15+500 15+700 30 -- 46 15+700 15+900 30 -- 47 15+900 18+150 35 -- 48 18+150 18+700 33 -- 49 18+700 19+100 22 -- 50 19+100 19+300 23 -- 51 19+300 19+500 26 -- 52 19+500 19+650 21 -- 53 19+650 19+900 16 -- 54 19+900 20+100 24 -- 55 20+100 20+300 24 -- 56 20+300 20+500 22 -- 57 20+500 20+700 25 --

33

58 20+700 20+900 26 -- 59 20+900 21+100 30 -- 60 21+100 21+300 35 -- 61 21+300 21+500 32 -- 62 21+500 21+700 34 -- 63 21+700 21+900 32 -- 64 21+900 22+000 32 -- 65 22+000 22+100 30 -- 66 22+100 22+300 29 -- 67 22+300 22+500 30 -- 68 22+500 22+700 35 -- 69 22+700 22+900 32 -- 70 22+900 23+100 35 -- 71 23+100 23+250 35 -- 72 23+250 23+500 33 -- 73 23+500 23+700 31 -- 74 23+700 24+000 31 -- 75 24+000 24+100 35 -- 76 24+100 24+320 38 -- 77 24+320 24+520 30 -- 78 24+520 24+700 32 -- 79 24+700 24+900 30 -- 80 24+900 25+120 32 -- 81 25+120 25+260 30 -- 82 25+260 25+500 35 -- 83 25+500 25+700 42 -- 84 25+700 25+900 40 -- 85 25+900 26+100 35 -- 86 26+100 26+300 35 -- 87 26+300 26+500 35 -- 88 26+500 26+700 34 -- 89 26+700 26+900 33 -- 90 26+900 27+100 40 -- 91 27+100 27+300 43 -- 92 27+300 27+500 38 -- 93 27+500 27+700 36 -- 94 27+700 27+900 32 --

34

95 27+900 28+100 31 -- 96 28+100 28+300 30 -- 97 28+300 28+500 33 -- 98 28+500 28+700 40 -- 99 28+700 28+900 33 -- 100 28+900 29+100 35 -- 101 29+100 29+300 37 -- 102 29+300 29+423 33 --

2. Details of Additional Land Required Details of additional land required for the Project is given below: (a) Barmer-Sindhari-Jalore Section

Design Chainages Width of Additional Land S. (in km) Required (in m) Remarks No. From To LHS RHS Total 1 3+850 3+875 3.00 0.00 3.00 Curve LHS 2 5+050 5+150 2.00 2.00 Curve RHS 3 10+775 10+875 3.00 3.00 Curve RHS 4 14+280 14+380 4.00 4.00 Curve LHS 5 17+500 17+600 4.00 4.00 Curve RHS 6 39+550 39+800 15.00 15.00 30.00 TP1 7 41+350 41+450 8.00 8.00 Curve RHS 8 42+350 42+550 6.00 6.00 Curve RHS 9 45+425 45+400 4.00 4.00 Curve LHS 10 48+300 48+400 5.00 5.00 Curve LHS 11 49+180 49+260 6.00 6.00 Curve RHS 12 49+500 49+600 10.00 10.00 Curve RHS 13 76+850 77+150 15.00 15.00 30.00 TP2 14 84+100 84+200 4.00 4.00 Curve LHS 15 85+600 85+700 3.00 3.00 Curve RHS 16 97+250 97+350 5.00 5.00 Curve LHS 17 101+840 101+940 5.00 5.00 Curve RHS 18 109+325 109+500 3.00 3.00 Curve LHS 19 111+300 111+400 3.50 3.50 Curve RHS 20 113+900 114+050 7.50 7.50 Curve RHS 21 114+250 114+425 9.00 9.00 Curve LHS

35

22 114+600 114+700 7.00 7.00 Curve RHS 23 122+750 122+900 10.00 10.00 Curve RHS 24 123+450 123+650 12.00 12.00 Curve RHS 25 123+650 123+950 11.00 11.00 Curve LHS & realignment 26 123+950 124+025 5.00 5.00 Curve RHS 27 124+025 124+200 4.00 4.00 Curve LHS & realignment 28 124+450 124+600 18.00 18.00 Curve LHS 29 126+250 126+400 6.00 6.00 Curve RHS 30 128+750 128+900 8.00 8.00 Curve LHS 31 129+900 130+050 4.00 4.00 Curve RHS 32 130+050 130+250 4.00 4.00 Curve LHS 33 130+250 133+850 34 133+850 133+950 4.00 4.00 Curve LHS 35 134+350 134+525 7.00 7.00 Curve LHS 36 134+525 134+775 30.00 30.00 Curve RHS & Realignment 37 134+900 135+075 26.00 26.00 Curve LHS 38 135+950 136+250 15.00 15.00 30.00 TP3 39 137+550 137+750 7.00 7.00 Curve RHS

(a) Ahore-Bali-Mundara (Sanderao-Mundara) Section

Width of Additional Land Design Chainages ( in km) Required S. No. Remarks (in m) From To LHS RHS Total 1 3+200 3+500 15.0 15.0 30.0 TP1 2 5+950 6+000 2.0 2.0 4.0 -- 3 6+380 6+600 22.0 22.0 Realignment 4 18+700 19+100 6.0 4.0 10.0 Widening

36

SCHEDULE - B (See Clause 2.1)

DEVELOPMENT OF THE PROJECT

1. Development of the Project

Development of the Project shall include construction of the Project as described in this Schedule-B and in Schedule-C.

2. Two-Laning

2.1. Two Laning shall mean Two Laning of the Project, including a wider carriageway in specified sections, as described in Annex-I of this Schedule-B and Annex-I of Schedule-C.

2.2. Two Laning shall be completed by the Concessionaire in conformity with the Specifications and Standards set forth in Annex-I of schedule-D and stipulations in Schedule-S.

37

Annex – I

(Schedule – B) Description of Project

1. Width of Carriageway 1.1. The roadway width shall be 12m and carriageway shall be 7m wide. Provided that in the following built up stretches the width of carriageway shall be: (a) Barmer-Sindari- Jalore Section Name of Location Carriageway Remarks Township Width (Design Chainages) Sr.No. (in m) (in km) From To 1 Barmer 0+000 4+800 2 x 7.50 4L Divided 2 Rawatsar 21+200 21+600 2 x 7.50 4L Divided 3+ Chawa 26+200 26+850 2 x 7.50 4L Divided 4 Sindhari 62+300 65+000 2 x 7.50 4L Divided 5 Jeewana 96+500 97+800 2 x 7.50 4L Divided 6 Balera 114+000 114+600 2 x 7.50 4L Divided 7 Sayala 116+600 118+300 2 x 7.50 4L Divided 8 Sayala 118+300 119+450 10.00 2L + 8 Sayala 119+450 120+700 2 x 7.50 4L Divided

9 Otwala 123+800 124+400 10.00 2L +

10 Khural 126+200 126+800 10.00 2L +

11 Umedabad 128+900 130+300 10.00 2L +

12 Elana 133+500 133+950 10.00 2L +

13 Mandwala 142+500 143+250 10.00 2L +

38

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section Name of Location Carriageway Remarks Township Width Sr.No. (Design Chainages) (in Mtrs) From To

1 Falna 9+400 10+750 2 x 7.50 4L Divided 2 Falna 11+400 12+300 2 x 7.50 4L Divided 3+ Falna 12+300 12+950 2 x 7.50 4L Divided 4 Bali 17+000 18+600 2 x 7.50 4L Divided 5 Bali 18+600 18+900 10.00 2L + 6 Bali 18+900 19+650 2 x 7.50 4L Divided

1.2. Except as otherwise provided in this Agreement, the width of carriageway shall confirm to clause 1.1 above.

2. Project Facilities

Project Facilities shall be constructed in conformity with Annex-I of Schedule-C. 3. Specifications and Standards

The Project shall be constructed in conformity with the Specifications and Standards specified in Annex-I of Schedule – D.

4. Other Features of the Project 4.1. Alignment Plan and Longitudinal Section

An alignment plan of the Project are provided at Appendix B-I.

4.2. Road Stretches requiring Raising

In accordance with para 4.2.2 of the Manual, the stretches of the existing road requiring raising are given in Appendix B-II

4.3. Reconstruction Stretches

The road stretches required to be reconstructed are given in Appendix B-III

4.4. Bypasses and Realignments

39

The details of bypasses and realignments to be carried out in the Project are given in Appendix B-IV

4.5. Service Road and Slip Roads

Service roads and slip roads shall be provided in stretches indicated in Appendix B-V.

4.6. Type of Pavement

Type of pavement shall be flexible pavements, except for the sections given in Appendix B-VI, wherein the type of pavement shall be as specified therein. Further the pavement type at all Toll Plazas including tapering zone shall be rigid.

4.7. Pavement Design 4.7.1. Flexible pavements shall be designed for a minimum design period of 15 years subjected to the condition that design traffic shall be 10 (ten) msa. 4.7.2. Rigid Pavements shall be designed for a minimum design period of 30 years in accordance with the Manual. 4.8. Intersections

In accordance with the para 3.1.1 & 3.1.2 of the Manual, all existing intersections, which are deficient with respect to minimum requirements shall be improved to the prescribed standards.

4.9. Major Bridges

As per the list given in Appendix B-VII, the major bridges shall be constructed, widened, reconstructed, rehabilitated or extended as specified therein.

4.10. Minor Bridges

As per the list given in Appendix B-VIII, the minor bridges shall be constructed, widened, reconstructed, rehabilitated or extended as specified therein.

4.11. Culverts

As per the list given in Appendix B-IX, the culverts shall be constructed, widened, reconstructed, rehabilitated or extended as specified therein.

4.12. ROBs/RUBs

No ROB / RUB is required to be constructed under this Project.

40

4.13. Roadside Drainage

Efficient drainage system shall be provided for entire stretch of the Project in accordance with Section 6 of the Manual. Provided that in built up sections, the drains shall be provided with RCC cover having strength commensurate with footpath loading.

4.14. Typical Cross Sections (TCS)

The typical cross sections to be used for the Project are detailed in Appendix B-X.

41

Appendix B-I

Alignment plan, longitudinal profile and TCS including bypasses & realignment for the Project are provided in soft copy.

42

Appendix B-II Details of Stretches Requiring Raising (a) Barmer-Sindari- Jalore Section Design Chainage (in km) Sl. No. Length (in km) From To 1 27+000 59+200 32.20 2 60+800 62+300 1.50 3 65+000 79+600 14.60 4 79+600 96+000 16.40 5 96+200 96+500 0.30 6 97+800 100+800 3.00 7 113+850 114+050 0.20 8 114+600 114+750 0.15 9 122+750 123+000 0.25 10 123+300 123+600 0.30 11 123+650 123+800 0.15 12 124+400 124+650 0.25 13 128+700 128+950 0.25 14 129+300 129+700 0.40 15 134+350 135+100 0.75 Total 70.70

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section Design Chainage (in km) Sl. No. Length(in km) From To 1 4+200 6+380 2.180 2 6+380 6+600 0.220 3 6+600 9+400 2.800 4 23+250 24+000 0.750 Total 5.950

43

Appendix B-III Details of stretches for reconstruction

(a) Barmer-Sindari- Jalore Section

Design Chainage ( in km) SL. No. From To Length (km) Barmer-Chawa Stretch 1 4+800 21+200 16.40 2 21+200 21+600 0.40

3 21+600 26+200 4.60 Chawa-Sindari Stretch

4 26+850 27+000 0.15

5 59+200 60+800 1.60

6 62+300 63+610 1.31 Sindari- Bishangarh Stretch

7 63+610 65+000 1.39

8 100+800 113+850 13.05

9 114+750 116+600 1.85

10 142+600 148+090 5.49

Total Length 46.24

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section Sl. No. Design Chainage (in km) From To Length (km) 1 1+800 1+920 0.12

2 5+080 5+180 0.10

3 5+360 5+420 0.06

4 21+320 21+500 0.18

5 24+320 24+520 0.20

44

6 25+040 25+300 0.26

0.92 Total Length

45

Appendix B-IV

Details of bypasses and realignments

1. Bypasses

(a) Barmer-Sindari- Jalore Section Existing Design Chainage Chainage Sl. No. Length Name of Bypass From To From To (km)

Nil

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section

Existing Design Sl. No. Chainage Chainage Length Name of Bypass From To From To (km)

Nil

2. Realignments

(a) Barmer-Sindari- Jalore Section Design Chainage (in km) Length (km) Sl. No. From To 1 113+850 114+050 0.200 2 114+600 114+750 0.150 3 122+750 123+000 0.250 4 123+300 123+600 0.300 5 123+650 123+800 0.150 6 124+400 124+650 0.250 7 128+700 128+950 0.250 8 129+300 129+700 0.400 9 134+350 135+100 0.750

46

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section Sl. Design Chainage (in km) Length (km) No. From To

1 6+380 6+600 0.220

47

Appendix B-V

Details of service road and slip road

Service Road and Slip Road

(a) Barmer-Sindari- Jalore Section Existing Design Sl. Carriageway Chainage Chainage Length No. Width Side From To From To Nil

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section Existing Sl. Design Chainage Carriageway Chainage Length No. Width Side From To From To Nil

48

Appendix B-VI

Type of pavement (a) Barmer-Sindari- Jalore Section Design Chainage Sl. (in km) Length Name of Type of No. (in km) Habitation Pavement From To 1 96+500 97+800 1.300 Jiwana Rigid

2 118+200 119+500 1.300 Sayela Rigid

3 123+900 124+400 0.500 Aotwara Rigid

4 126+200 126+800 0.600 khural Rigid

5 128+900 130+200 1.300 Ummedabad Rigid

6 142+000 142+600 0.600 Mandawla Rigid

Total Length 5.600

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section Sl. Design Chainage Name of Type of No. (in km) Length Habitation Pavement (in km) From To 1 10+500 10+700 0.200 Falna Rigid 2 11+400 12+300 0.900 Falna Rigid Total Length 1.100

49

Appendix B-VII

Details of new major bridges and rehabilitation ,repair & widening Scheme for existing major bridges

A. Construction of New Major Bridges

(a) Barmer-Sindari- Jalore Section

Existing Design Minimum Utilities Name of Total Width of Chainage Chainage Linear Water to be Remarks Sl. Bridge Structure (in km) (in km) way Carried No. Luni Water 1 35+190 61+850 12.00 160m Bridge Pipe Line

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section Sl. Name of Existing Design Total Width Minimum Utilities No. Bridge Chainage Chainage of Structure Linear Water to be Remarks way Carried 1 Nimbeshwar 230+950 6+250 12.00 110m Water -- Pipe line 2 Kot Baliyan 248+300 23+316 12.00 100m Water -- Pipe line

B. Widening of Existing Major Bridges

(a) Barmer-Sindari- Jalore Section S. Name of Existing Design Side Proposed Remarks No. Bridge Chainage Chainage (LHS/RHS/Both) Width

Nil

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section S. Name Existing Design Side Proposed Remarks No. of Chainage Chainage (LHS/RHS/Both) Width Bridge

Nil

50

C. Rehabilitation and Repair of Existing Major bridges (a) Barmer-Sindari- Jalore Section S. Name Existing Design Side Details of Details No. of Chainage Chainage (LHS/RHS/Both) Rehabilitation of Bridge Repair

Nil

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section S. Name of Existing Design Details of Details of No. Bridge Chainage Chainage Rehabilitation Repair

1 Bali 244+400 19+700 (c) & (e) (a), (b) & (f) River

(a) Repair and replacement of damaged railings and parapets, provision of crash barriers (b) Replacement of wearing coat (c) Replacement of expansion joints (d) Replacement of bearings (e) Structural repairs to sub-structure +superstructure, including replacement of substructure and superstructure if require (f) Repair to flooring and protection works

51

Appendix B-VIII

Details of new minor bridges and rehabilitation, repair & widening scheme for existing minor bridges

A. Construction of New Minor Bridges

(a) Barmer-Sindari- Jalore Section

Sl. Name of Existing Design Total Linear Utilities to be Remarks No. Bridge Chainage Chainage Width of Water way Carried Structure 1 -- 17+730 44+380 12.00 8.0m Water Pipe Line -- 2 - 23+150 49+810 12.00 16.0m Water Pipe Line -- 3 - 28+160 54+815 12.00 8.0m Water Pipe Line -- 4 - 28+490 55+140 12.00 8.0m Water Pipe Line -- 5 - 4+260 67+860 12.00 12.0m Water Pipe Line -- 6 - 10+540 74+140 12.00 12.0m Water Pipe Line -- 7 - 14+530 78+125 12.00 8.0m Water Pipe Line -- 8 - 18+110 81+700 12.00 8.0m Water Pipe Line -- 9 - 27+580 91+150 12.00 16.0m Water Pipe Line -- 10 - 33+630 97+210 19.50 9.0m Water Pipe Line --

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section Sl. Name of Existing Design Total Linear Utilities to be Remarks No. Bridge Chainage Chainage Width of Water Carried Structure way 1 - 236+700 12+040 12.00 8.00 Water Pipe Line -- 2 - 243+400 18+700 12.00 12.00 Water Pipe Line --

B. Widening of Existing Minor Bridges (a) Barmer-Sindari- Jalore Section S. Name Existing Design Side Proposed Remarks No. of Chainage Chainage (LHS/RHS/Both) Width Bridge

Nil

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section

52

S. Name Existing Design Side Proposed Remarks No. of Chainage Chainage (LHS/RHS/Both) Width Bridge

Nil

C. Rehabilitation / Repair to Minor Bridges

(a) Barmer-Sindari- Jalore Section S. Name of Existing Design Side Details of Details No. Bridge Chainage Chainage (LHS/RHS/Both) Rehabilitation of Repair Nil

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section

S. No. Name of Existing Design Side Details of Details Bridge Chainage Chainage (LHS/RHS/Both) Rehabilitation of Repair 1 - 233+900 9+230 Both (a), (e) (f)

(a) Repair +replacement of damaged railings and parapets, provision of crash barriers (b) Replacement of wearing coat (c) Replacement of expansion joints (d) Replacement of bearings (e) Structural repairs to sub-structure +superstructure, including replacement of substructure +superstructure if required (f) Repair to flooring and protection works

53

Appendix B-IX

Culverts A. Reconstruction of Culverts (a) Barmer-Sindari- Jalore Section Sl. Existing Existing Design Type of Span Arrangement No. CD No. Chainage Chainage Proposed + No. x Dia Structure 1 8/1 7+280 5+640 Pipe Culvert 3 x 1200mm 2 8/2 7+740 6+090 Pipe Culvert 3 x 1200mm 3 17/1 15+775 42+440 Pipe Culvert 4 x 1000mm 4 37/1 36+065 62+715 RCC Box Culvert 1 x 3.0m x 3.0m 5 -- 1+450 65+040 RCC Box Culvert 1x2.0m x 2.0m 6 -- 1+830 65+430 RCC Box Culvert 1x2.0m x 2.0m 6 4/1 3+790 67+380 Slab Culvert 1 x 3.0m 7 -- 10+540 74+140 RCC Box Culvert 1 x 3.0m x 3.0m 8 14/1 13+380 77+450 Slab Culvert 1 x 3.0m 9 - 14+530 78+125 RCC Box Culvert 2 x 3.0m x 3.0m 10 - 14+830 78+430 Pipe Culvert 1x1.2m 11 33/1 32+975 96+560 Slab Culvert 1 x 2.0m 12 34/1 33+630 97+210 Pipe Culvert 3 x 1200mm 13 34/2 33+920 97+490 Slab Culvert 1 x 2.0m 14 - 51+380 114+940 Slab Culvert 1x4.0m 15 67/1 66+360 129+860 Slab Culvert 1 x 3.00m 16 70/1 69+530 133+030 Slab Culvert 1 x 3.00m

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section Sl. Existing Existing Design Type of proposed Span No. CD No. Chainage Chainage Structure Arrangement + No. x Dia 1 227/1 226+600 1+850 Slab 1 x 6.00m 2 229/1 228+600 3+900 Slab 1 x 6.00m

54

3 230/1 229+000 4+350 RCC Box Culvert 1 x 3.0m x 3.0m 4 230/2 229+400 4+750 RCC Box Culvert 1 x 3.0m x 3.0m 5 230/3 229+900 5+250 RCC Box Culvert 1 x 2.0m x 2.0m 6 231/1 230+200 5+550 RCC Box Culvert 1 x 2.0m x 2.0m 7 231/2 230+300 5+650 RCC Box Culvert 1 x 2.0m x 2.0m 8 231/3 230+600 5+950 Slab 1 x 6.00m 9 232/1 231+600 6+923 Slab 1 x 2.00m 10 233/1 232+000 7+323 RCC Box Culvert 1 x 2.0m x 2.0m 11 235/1 234+800 10+130 RCC Box Culvert 1 x 2.0m x 2.0m 12 238/1 237+800 13+110 Slab 1 x 3.00m 13 246/1 245+400 20+700 RCC Box Culvert 1 x 3.0m x 3.0m 14 247/1 256+100 21+400 RCC Box Culvert 1 x 2.0m x 2.0m 15 250/1 249+200 24+435 RCC Box Culvert 1 x 3.0m x 3.0m 16 250/2 249+900 25+200 RCC Box Culvert 1 x 2.0m x 2.0m

B. New Culverts (a) Barmer-Sindari- Jalore Section Sl. Existing Design Type of proposed Span Arrangement No. Chainage Chainage Structure + No. x Dia 1 3+770 2+120 RCC Box Culvert 1 x 2.0m x 2.0m 2 4+290 2+640 Pipe Culvert 1 x 1200mm 3 5+150 3+500 RCC Box Culvert 1x2.0mx 2.0m 4 6+030 4+380 Pipe Culvert 1 x 1200mm 5 8+510 6+860 RCC Box Culvert 1 x 2.0m x 2.0m 6 9+730 8+080 Pipe Culvert 1 x 1200mm 7 10+470 8+820 Pipe Culvert 1 x 1200mm 8 11+150 9+500 Pipe Culvert 1 x 1200mm 9 12+350 10+700 RCC Box Culvert 1 x 2.0m x 2.0m 10 13+010 11+360 Pipe Culvert 1 x 1200mm 11 13+550 11+900 Pipe Culvert 1 x 1200mm

55

12 14+000 12+350 Pipe Culvert 1 x 1200mm 13 16+130 14+480 RCC Box Culvert 1 x 2.0m x 2.0m 14 19+130 17+480 Pipe Culvert 1 x 1200mm 15 22+710 21+060 RCC Box Culvert 1 x 2.0m x 2.0m 16 23+950 22+300 Pipe Culvert 1 x 1200mm 17 24+830 23+180 Pipe Culvert 1 x 1200mm 18 27+690 26+040 RCC Box Culvert 1 x 2.0m x 2.0m 19 1+140 27+740 Pipe Culvert 1 x 1200mm 20 2+620 29+220 Pipe Culvert 1 x 1200mm 21 5+320 31+920 RCC Box Culvert 1 x 2.0m x 2.0m 22 6+240 32+640 Pipe Culvert 1 x 1200mm 23 6+850 33+250 RCC Box Culvert 1 x 2.0m x 2.0m 24 8+460 35+060 Pipe Culvert 1 x 1200mm 25 9+500 36+100 RCC Box Culvert 1 x 2.0m x 2.0m 26 11+340 37+940 Pipe Culvert 1 x 1200mm 27 12+600 39+200 Pipe Culvert 1 x 1200mm 28 13+780 40+380 Pipe Culvert 1 x 1200mm 29 14+760 41+360 RCC Box Culvert 1 x 2.0m x 2.0m 30 17+300 43+900 Pipe Culvert 1 x 1200mm 31 18+300 44+900 Pipe Culvert 1 x 1200mm 32 19+800 46+400 Pipe Culvert 1 x 1200mm 33 20+940 47+540 Pipe Culvert 1 x 1200mm 34 22+400 49+00 Pipe Culvert 1 x 1200mm 35 24+500 51+100 Pipe Culvert 1 x 1200mm 36 27+100 53+700 Pipe Culvert 1 x 1200mm 37 28+540 55+140 Pipe Culvert 1 x 1200mm 38 31+760 58+360 Pipe Culvert 1 x 1200mm 39 33+880 60+480 Pipe Culvert 1 x 1200mm

56

40 2+800 66+400 Pipe Culvert 1 x 1200mm 41 7+280 70+880 Pipe Culvert 1 x 1200mm 42 9+540 73+140 Pipe Culvert 1 x 1200mm 43 10+140 73+740 Pipe Culvert 1 x 1200mm 44 11+640 75+240 Pipe Culvert 1 x 1200mm 45 12+300 75+900 Pipe Culvert 1 x 1200mm 46 14+830 78+430 Pipe Culvert 1 x 1200mm 47 16+140 79+740 Pipe Culvert 1 x 1200mm 48 17+120 80+720 Pipe Culvert 1 x 1200mm 49 19+300 82+900 Pipe Culvert 1 x 1200mm 50 20+200 83+800 Pipe Culvert 1 x 1200mm 51 22+960 86+560 Pipe Culvert 1 x 1200mm 52 25+760 89+360 Pipe Culvert 1 x 1200mm 53 26+840 90+440 Pipe Culvert 1 x 1200mm 54 29+360 92+960 Pipe Culvert 1 x 1200mm 55 32+260 95+860 Pipe Culvert 1 x 1200mm 56 34+420 98+020 Pipe Culvert 1 x 1200mm 57 34+70 98+300 Pipe Culvert 1 x 1200mm 58 35+000 98+760 Pipe Culvert 1 x 1200mm 59 35+760 99+360 Pipe Culvert 1 x 1200mm 60 36+220 99+820 Pipe Culvert 1 x 1200mm 61 36+760 100+360 Pipe Culvert 1 x 1200mm 62 37+540 101+140 Pipe Culvert 1 x 1200mm 63 38+800 102+400 Pipe Culvert 1 x 1200mm 64 39+900 103+500 Pipe Culvert 1 x 1200mm 65 40+160 103+760 Pipe Culvert 1 x 1200mm 66 41+160 104+760 Pipe Culvert 1 x 1200mm 67 41+660 105+260 Pipe Culvert 1 x 1200mm

57

68 42+120 105+720 Pipe Culvert 1 x 1200mm 69 44+000 107+600 Pipe Culvert 1 x 1200mm 70 44+560 108+160 Pipe Culvert 1 x 1200mm 71 46+160 109+760 Pipe Culvert 1 x 1200mm 72 46+760 110+360 Pipe Culvert 1 x 1200mm 74 47+380 110+980 Pipe Culvert 1 x 1200mm 75 48+700 112+300 Pipe Culvert 1 x 1200mm 76 49+840 113+440 Pipe Culvert 1 x 1200mm 77 53+000 116+600 Pipe Culvert 1 x 1200mm 78 60+100 123+700 Pipe Culvert 1 x 1200mm 79 70+680 134+280 Pipe Culvert 1 x 1200mm 80 70+980 134+580 Box Culvert 1 x 3.0m x 3.0m 81 72+540 136+140 Pipe Culvert 1 x 1200mm 82 73+100 136+700 Pipe Culvert 1 x 1200mm 83 74+060 137+660 Pipe Culvert 1 x 1200mm

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section Existing Design Type of Span Sl. No. Chainage Chainage Structure Arrangement + No. x Dia 1 230+850 6+150 RCC Slab 1 x 3.00m

C. New Culverts at the location of Intersections The Concessionaire shall ensure adequate road side drainage all along the Project. All roads approaching / intersecting the Project shall be provided with a minimum of single row 900mm dia NP-4 pipe culvert.

D. Widening of Culverts (a) Barmer-Sindari- Jalore Section Sl. Existing CD Existing Design Existing Structure Proposed No No. Chainage Chainage Type Width (m) Width (m) 1 52/1 51+380 114+940 RCC Slab 8.50 12.00

58

2 62/1 61+300 124+820 RCC Slab 10.0 12.00 3 62/1 61+675 125+180 RCC Slab 10.0 12.00 4 65/1 64+080 127+590 RCC Slab 10.0 12.00

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section

Sl. Existing CD Existing Design Existing Structure Proposed No No. Chainage Chainage Type Width Width Nil

59

Appendix B-X

Typical Cross Section (TCS) of the Project

Cross-Sections to be adopted for different stretches of the Project are given in table below. Typical CROSS SECTIONS are also attached herewith.

(a) Barmer-Sindari-Jalore Section Design Chainage (in km) Sr. No. Length (in km) TCS Type From To

1 0+000 4+800 4.800 TCS-5 2 4+800 21+200 16.40 TCS-7 3 21+200 21+600 0.400 TCS-5 4 21+600 26+200 4.600 TCS-7 5 26+200 26+850 0.650 TCS-5 6 26+850 27+000 0.150 TCS-7 7 27+000 59+200 32.200 TCS-1 8 59+200 60+800 1.600 TCS-7 9 60+800 62+300 1.500 TCS-1 10 62+300 63+610 1.310 TCS-5 11 63+610 65+000 1.390 TCS-5 12 65+000 96+000 31.000 TCS-1 13 96+000 96+200 0.200 TCS-9 14 96+200 96+500 0.300 TCS-1 15 96+500 97+800 1.300 TCS-5 16 97+800 100+800 3.000 TCS-1 17 100+800 113+850 13.050 TCS-7 19 113+850 114+050 0.200 TCS-6

60

20 114+050 114+600 0.550 TCS-5 21 114+600 114+750 0.150 TCS-6 22 114+750 116+600 1.850 TCS-7 23 116+600 118+300 1.700 TCS-5 24 118+300 118+600 0.300 TCS-4 25 118+600 119+600 1.000 TCS-10 26 119+600 120+700 1.100 TCS-5 27 120+700 122+750 2.050 TCS-3 28 122+750 123+000 0.250 TCS-6 29 123+000 123+300 0.300 TCS-3 30 123+300 123+600 0.300 TCS-6 31 123+600 123+650 0.050 TCS-3 32 123+650 123+800 0.150 TCS-6 33 123+800 124+400 0.600 TCS-10 34 124+400 124+650 0.250 TCS-6 35 124+650 124+800 0.150 TCS-4 36 124+800 126+200 1.400 TCS-3 37 126+200 126+800 0.600 TCS-10 38 126+800 128+700 1.900 TCS-3 39 128+700 128+950 0.250 TCS-6 40 128+950 129+300 0.350 TCS-3 41 129+300 129+700 0.400 TCS-6 42 129+700 130+000 0.300 TCS-4 43 130+000 134+350 4.350 TCS-3 44 134+350 135+100 0.750 TCS-6 45 135+100 142+000 6.900 TCS-3 46 142+000 142+600 0.600 TCS-10 47 142+600 148+090 5.490 TCS-8

61

Total Length 148.09

(b) Ahore-Bali-Mundara (Sanderao to Mundara) Section Design Chainage (in km) Sr. No. Length ( in km) TCS Type From To

1 0+000 0+350 0.350 TCS-3 2 0+350 4+200 3.850 TCS-2 3 4+200 6+380 2.180 TCS-1 4 6+380 6+600 0.220 TCS-6 5 6+600 9+400 2.800 TCS-1 6 9+400 10+750 1.350 TCS-5 7 10+750 11+400 0.650 -- 8 11+400 12+300 0.900 TCS-13 9 12+300 12+950 0.650 TCS-5 10 12+950 18+150 5.200 TCS-13 11 18+150 19+650 1.500 TCS-5 12 19+650 23+250 3.600 TCS-2 13 23+250 24+000 0.750 TCS-1 14 24+000 24+320 0.320 TCS-2 15 24+320 24+520 0.200 TCS-1 16 24+520 25+120 0.400 TCS-2 17 25+120 25+260 0.140 TCS-1 18 25+260 29+423 4.163 TCS-2 Total Length 29.423

62

63

64

65

66

67

68

69

70

71

72

73

74

75

76

77

78

SCHEDULE - C (See Clause 2.1)

PROJECT FACILITIES

1+ Project Facilities

The Concessionaire shall construct the Project Facilities in accordance with the provisions of this Agreement. Such Project Facilities shall include:

(a) Toll plazas

(b) roadside furniture;

(c) pedestrian facilities;

(d) tree plantations;

(e) truck lay-bys;

(f) bus-bays and bus shelters;

(g) buildings for Traffic Aid Posts;

(h) buildings for Medical Aid Posts and

(i) utility ducts

2 Project Facilities for Two-Laning Project Facilities to be completed on or before the COD have been described in Annex-I of this Schedule-C.

ANNEX-I (Schedule-C) Project Facilities 1. Project Facilities The Concessionaire shall construct the Project Facilities described in this Annex-I to form part of the Two-Lane Project. The Project Facilities shall include:

(a) Toll Plazas;

(b) roadside furniture;

(c) pedestrian facilities;

(d) tree plantations;

(e) truck lay-bys;

(f) bus-bays and bus shelters;

(g) buildings for Traffic Aid Posts;

(h) buildings for Medical Aid Posts and

(i) utility ducts

2. Description of Project Facilities

Each of the Project Facility is briefly described below. a) Toll Plazas

The Toll Plazas shall be constructed in accordance with the provisions of this Agreement and Section 10 of the Manual, at locations given in Table C-1.

Table C-1 Location of Toll Plazas

(a) Barmer-Sindari- Jalore Section

Sl. No. Existing Chainage (in km) Design Chainage (in km) 1 13+000 (0 at Chawa) 39+650 2 12+000 (0 at Sindari) 77+000 139+500 3 136+100 (Sayala-Bishangarh Section)

80

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section

Sl. No. Existing Chainage (in km) Design Chainage (in km)

1 228+000 3+350

The Toll Plaza shall include an office building, a Traffic Aid Post, a Medical Aid Post and paved yard for parking and unloading of vehicles. b) Roadside furniture:

(i) Road side furniture comprising road signs, road markings, object markers, hazard marker, studs, delineators, safety barriers, pedestrian guard rails, boundary stones, kilometer stone etc. shall be provided as stipulated in Section 11 of the Manual.

(ii) The overhead traffic signs shall be provided as per numbers given below, at the locations to be finalized in consultation with Independent Engineer.

(1) Full width Overhead signs : 8 nos.

(2) Cantilever Overhead signs : 16 nos.

c) Pedestrian Facilities

The pedestrian facilities shall be provided in accordance with Paragraph 13.2 of the Manual. d) Tree Plantation

In pursuance of Paragraph 12.1 of the Manual, 2500 (Two thousand five hundred) shall be planted by the Concessionaire as compensatory afforestation. The Concessionaire shall also maintain all the trees on the Project in good condition. e) Truck Lay-byes

As stipulated in Paragraph 13.4 of the Manual, truck lay-byes shall be constructed at locations given in Table C-4

81

Table C-4 Location of Truck Lay-byes

(a) Barmer-Sindari- Jalore Section

Existing Design Straight

Sl+ No+ Chainage Chainage Side Length

1 98+750 95+250 Right Side 225m

2+ 151+00 147+700 Left Side 250m

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section

Existing Design Straight

Sl+ No+ Chainage Chainage Side Length

Nil

f) Bus Bays and Bus Shelters

Bus bays and bus shelters shall be provided in accordance with Paragraph 13.5 of the Manual at locations given in Table C-5.

Table C-5 Bus bays and Bus Shelters

(a) Barmer-Sindari- Jalore Section

Existing Chainage Design Chainage Sl. No. Side Straight Length (in km) (in km)

1 22+400 20+750 Left 15m

82

2 22+600 20+950 Right 15m

3 27+550 25+900 Left 15m

4 27+750 26+100 Right 15m

5 14+450 41+050 Left 15m

6 14+600 41+200 Right 15m

7 106+450 105+000 Left 15m

8 106+650 105+200 Right 15m

9 114+750 113+300 Left 15m

10 115+000 113+550 Right 15m

11 117+800 116+350 Left 15m

12 118+000 116+550 Right 15m

13 124+500 123+050 Left 15m

14 124+650 123+200 Right 15m

15 131+250 126+750 Left 15m

16 131+400 126+900 Right 15m

17 132+000 127+500 Left 15m

18 132+250 127+750 Right 15m

19 135+900 132+400 Left 15m

20 136+050 132+550 Right 15m

21 142+300 138+800 Left 15m

22 142+450 138+950 Right 15m

23 148+300 144+800 Left 15m

24 148+500 145+000 Right 15m

83

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section

Existing Chainage Straight Length Design Chainage (in Sl. No. Side km) (in km) 1 225+150 0+450 Left 15m 2 225+250 0+550 Right 15m 3 230+600 5+900 Left 15m 4 230+650 5+950 Right 15m

5 233+750 9+050 Left 15m

6 233+725 9+025 Right 15m

7 236+400 11+700 Left 15m

8 236+600 11+900 Right 15m

Note: The location in the list is indicative which may be finalized in consultation with the Independent Engineer prior to their execution. g) Buildings for Traffic Aid Posts

The Traffic Aid Posts shall be provided at each Toll Plaza in accordance with Concession Agreement. The Concessionaire shall construct at its costs, building not exceeding 25 (twenty five) square metres of plinth area, for each of the Traffic Aid Posts and hand them over to the Authority no later than 30 (thirty) days prior to the Scheduled Completion Date. The Traffic Aid Posts shall be deemed to be part of the Site and shall vest in the Authority. h) Buildings for Medical Aid Posts

Medical Aid Posts shall be provided at each Toll Plaza in accordance with Concession Agreement. The Concessionaire shall, at its cost, construct an aid post building and hand them over to the Authority no later than 30 (thirty) days prior to the COD. The Medical Aid Posts shall be deemed to be part of the Site and shall vest in the Authority

84

i) Utilities Duct

The Concessionaire shall provide 300mm dia NP-4 pipe as utility duct for crossing of underground utilities in buildup areas, bypasses & realignments across the Project along with inspection box. Chamber at a spacing of 500m shall be provided.

85

SCHEDULE – D

(See Clause 2.1)

SPECIFICATIONS AND STANDARDS

1. Specifications and Standards for the Project

The Concessionaire shall comply with the Specifications and Standards set forth in Annex-I of this Schedule-D for construction of the Project.

86

Annex - I

Schedule-D

Specifications and Standards for the Project

1. Manual of Specifications and Standards to apply

Subject to the provisions of Paragraph 2 of this Annex-I, Two-Laning of the Project shall conform to the Manual of Specifications and Standards for Two- Laning of Highways through Public Private Partnership published by IRC (IRC No. IRC: SP: 73-2007). (An Authentic copy of the Manual has been provided to the Concessionaire as part of bid documents.)

2. Deviations from the Manual

Notwithstanding anything to the contrary contained in the aforesaid Manual, the following Specifications and Standards shall apply to the Project, and for purposes of this Agreement, the aforesaid Manual shall be deemed to be amended to the extent set forth below:

2.1. The minimum design speed given in Table 2.1 of the Manual applicable for plain terrain is amended to the extent for the road stretches described below owing to the restrictive site conditions. Various geometric design features of the road stretch shall be designed accordingly and appropriate traffic safety measures shall be adopted.

(a) Barmer-Sindari- Jalore Section Design Chainage (in km) Design Speed S. No. From To (km/hr) 1 3+780 3+870 65 2 10+770 10+880 65 4 42+370 42+550 65 5 62+600 62+670 65 6 70+330 70+360 75

87

7 118+230 118+250 30 8 118+460 118+490 40 9 119+100 119+180 50 10 119+260 119+320 45 11 119+500 119+540 45 12 119+590 119+640 70 13 119+780 119+860 65 14 123+470 123+560 65 15 123+700 123+800 50 16 123+920 123+960 65 17 126+240 126+300 55 18 126+340 126+430 50 19 129+670 129+690 65 20 137+550 137+750 65

(b) Ahore-Bali-Mundara (Sanderao-Mundara) Section

Design Chainage (in km) Design Speed S. No. From To (km/hr)

1 0+200 0+250 30 2 0+325 0+365 30 3 5+850 5+950 60 4 6+400 6+500 65 5 11+350 11+450 30 6 18+850 18+950 30 7 20+790 20+800 65

88

89

.

SCHEDULE –E (See Clause 4.1.3)

APPLICABLE PERMITS

1 Applicable Permits

1.1 The Concessionaire shall obtain, as required under Applicable Laws, the following Applicable Permits on or before the Appointed Date, save and except to the extent of a waiver granted by the Authority in accordance with Clause 4.1.3 of the Agreement:

Part-I

(a) Permission of the State Government for extraction of boulders from quarries for and in respect of at least 20% (twenty per cent) of the total length of the Project; and

Part-II

(a) Permission of Village Panchayat and the Pollution Control Board for installation of crushers;

(b) Licence for use of explosives;

(c) Permission of the State Government for drawing water from river/ reservoir; and.

(d) Any other permits or clearances required under Applicable Laws.

1.2 Unless otherwise specified in this Agreement Applicable Permits, as required relating to environmental protection and conservation shall have been procured by the Authority as a Condition Precedent.

Schedule-E Page - 91

SCHEDULE –F (See Clause 9.1)

PERFORMANCE SECURITY

The Additional Chief Secretary, Public Works Department, Government of Rajasthan Jaipur

WHEREAS: (A) …………………(the “Concessionaire”) and Public Works Department, Government of Rajasthan represented by its Additional Chief Secretary (the “Authority”) have entered into a Concession Agreement dated ………………. (the “Agreement”) whereby the Authority has agreed to the Concessionaire undertaking the Development and Maintenance of Barmer -Sindari -Jalore section of State Highway -16 and n Ahore- Bali- Mundra (Sanderao to Mundra) section of State Highway -16 (Total length: 178.00 Km) on design, build, operate and transfer (the “DBOT”) basis on annuity mode, subject to and in accordance with the provisions of the Agreement.

(B) The Agreement requires the Concessionaire to furnish a Performance Security to the Authority in a sum of Rs. 19.7 crore (Rupees nineteen crore and seventy lakh ) (the “Guarantee Amount”) as security for due and faithful performance of its obligations, under and in accordance with the Agreement, during the Construction Period (as defined in the Agreement).

(C) We, ………………………through our Branch at ……………….(the “Bank”) have agreed to furnish this Bank Guarantee by way of Performance Security.

NOW, THEREFORE, the Bank hereby, unconditionally and irrevocably, guarantees and affirms as follows:

1. The Bank here by unconditionally and irrevocably guarantees and undertakes to pay to the Authority upon occurrence of any failure or default in the due and faithful performance of all or any of the Concessionaire‟s obligations, under and in accordance with the provisions of the Agreement, on its mere first written demand, and without any demur, reservation, recourse, contest or protest, and without any reference to the Concessionaire, such sum or sums upto an aggregate sum of the Guarantee Amount as the Authority shall claim, without the Authority being required to prove or to show grounds or reasons for its demand and/ or for the sum specified therein.

2. A letter from the Authority, under the hand of an Officer not below the rank of Deputy Secretary to the Government that the Concessionaire has committed default in the due and faithful performance of all or any of its obligations under and in accordance with the Schedule-F Page - 93

Agreement shall be conclusive, final and binding on the Bank. The Bank further agrees that the Authority shall be the sole judge as to whether the Concessionaire is in default in due and faithful performance of its obligations during the Construction Period under the Agreement and its decision that the Concessionaire is in default shall be final, and binding on the Bank, notwithstanding any differences between the Authority and the Concessionaire, or any dispute between them pending before any court, tribunal, arbitrators or any other authority or body, or by the discharge of the Concessionaire for any reason whatsoever. 3. In order to give effect to this Guarantee, the Authority shall be entitled to act as if the Bank were the principal debtor and any change in the constitution of the Concessionaire and/or the Bank, whether by their absorption with any other body or corporation or otherwise, shall not in any way or manner affect the liability or obligation of the Bank under this Guarantee.

4. It shall not be necessary, and the Bank hereby waives any necessity, for the Authority to proceed against the Concessionaire before presenting to the Bank its demand under this Guarantee.

5. The Authority shall have the liberty, without affecting in any manner the liability of the Bank under this Guarantee, to vary at any time, the terms and conditions of the Agreement or to extend the time or period for the compliance with, fulfilment and/or performance of all or any of the obligations of the Concessionaire contained in the Agreement or to postpone for any time, and from time to time, any of the rights and powers exercisable by the Authority against the Concessionaire, and either to enforce or forbear from enforcing any of the terms and conditions contained in the Agreement and/or the securities available to the Authority, and the Bank shall not be released from its liability and obligation under these presents by any exercise by the Authority of the liberty with reference to the matters aforesaid or by reason of time being given to the Concessionaire or any other forbearance, indulgence, act or omission on the part of the Authority or of any other matter or thing whatsoever which under any law relating to sureties and guarantors would but for this provision have the effect of releasing the Bank from its liability and obligation under this Guarantee and the Bank hereby waives all of its rights under any such law.

6. This Guarantee is in addition to and not in substitution of any other guarantee or security now or which may hereafter be held by the Authority in respect of or relating to the Agreement or for the fulfilment, compliance and/or performance of all or any of the obligations of the Concessionaire under the Agreement.

Schedule-F Page - 94

7 Notwithstanding anything contained hereinbefore, the liability of the Bank under this Guarantee is restricted to the Guarantee Amount and this Guarantee will remain in force until the expiry of 730 (seven hundred and thirty) days from the Appointed Date and compliance of the conditions specified in paragraph 8 below and unless a demand or claim in writing is made by the Authority on the Bank under this Guarantee, no later than issuance of the Completion Certificate, all rights of the Authority under this Guarantee shall be forfeited and the Bank shall be relieved from its liabilities hereunder.

8. The Performance Security shall cease to be in force and effect when the Completion Certificate (as defined in the Agreement) is issued and provided the Concessionaire is not in breach of this Agreement. Upon request made by the Concessionaire for release of the Performance Security along with the particulars required hereunder, duly certified by the Independent Engineer, the Authority shall release the Performance Security forthwith.

9. The Bank undertakes not to revoke this Guarantee during its currency, except with the previous express consent of the Authority in writing, and declares and warrants that it has the power to issue this Guarantee and the undersigned has full powers to do so on behalf of the Bank.

10. Any notice by way of request, demand or otherwise hereunder may be sent by post addressed to the Bank at its above referred Branch, which shall be deemed to have been duly authorised to receive such notice and to effect payment thereof forthwith, and if sent by post it shall be deemed to have been given at the time when it ought to have been delivered in due course of post and in proving such notice, when given by post, it shall be sufficient to prove that the envelope containing the notice was posted and a certificate signed by an officer of the Authority that the envelope was so posted shall be conclusive.

11. This Guarantee shall come into force with immediate effect and shall remain in force and effect till issuance of Completion Certificate or until it is released by the Authority pursuant to the provisions of the Agreement.

Signed and sealed this………………day of ………………, 20 ……………at……………..

SIGNED, DEALED AND DELIVERED For and on behalf of The BANK by:

(Signature) (Name) (Designation) (Code Number) (Address)

Schedule-F Page - 95

NOTE: (i) The bank guarantee should contain the name, designation and code number of the officer (s) signing the guarantee.

(ii) The address, telephone number and other details of the Head Office of the Bank as well as of issuing Branch should be mentioned on the covering letter of issuing Branch.

Schedule-F Page - 96

SCHEDULE –G (See clause 12.1)

PROJECT COMPLETION SCHEDULE

1 Project Completion Schedule

During Construction Period, the Concessionaire shall comply with the requirements set forth in this Schedule-G for each of the Project Milestones and the Scheduled Completion Date (the “Project Completion Schedule”) Within 15 (fifteen) days of the date of each Project Milestone, the Concessionaire shall notify the Authority of such compliance along with necessary particulars thereof.

2 Project Milestone-I

2.1 Project Milestone-I shall occur on the date falling on the 150th (one hundred and fiftieth) day from the Appointed Date (the “Project Milestone-I”)

2.2 Prior to the occurrence of Project Milestone-I, the Concessionaire shall have commenced construction of the Project and expended not less than 20% (twenty per cent) of the total capital cost set forth in the Financial Package.

2.3 Prior to the occurrence of Project Milestone-I, the Concessionaire shall have commenced construction of the Project and achieved 20% (twenty per cent) physical progress.

3 Project Milestone-II

3.1 Project Milestone-II shall occur on the date falling on the 365th (three hundred and sixty fifth) day from the Appointed Date (the “Project Milestone-II”)

3.2 Prior to the occurrence of Project Milestone-II, the Concessionaire shall have expended not less than 35% (thirty five per cent) of the total capital cost set forth in the Financial Package. Provided, however, that at least 70% (seventy per cent) of the expenditure referred to herein above shall have been incurred on physical works which shall not include advances of any kind to any person or expenditure of any kind on plant and machinery.

3.3 Prior to the occurrence of Project Milestone-II, the Concessionaire shall have commenced construction of the Project and achieved 35% (thirty five per cent) physical progress.

4 Project Milestone-III

Schedule-G Page - 97

4.1 Project Milestone-III shall occur on the date falling on the 480th (four hundred and eightieth) day from the Appointed Date (the “Project Milestone-III”)

4.2 Prior to the occurrence of Project Milestone-III, the Concessionaire shall have commenced construction of all Project Facilities and expended not less than 75% (seventy five per cent) of the total capital cost set forth in the Financial Package.

4.3 Prior to the occurrence of Project Milestone-III, the Concessionaire shall have commenced construction of the Project and achieved 75% (seventy five per cent) physical progress.

5 Scheduled Completion Date

5.1 The Scheduled Completion Date shall be the 730th (seven hundred and thirtieth) day from the Appointed Date.

5.2 On or before the Scheduled Completion Date, the Concessionaire shall have completed the Project in accordance with this Agreement.

6 Extension of period

Upon extension of any or all of the aforesaid Project Milestones or the Scheduled Completion Date, as the case may be, under and in accordance with the provisions of this Agreement, the Project Completion Schedule shall be deemed to have been amended accordingly.

Schedule-G Page - 98

SCHEDULE –H (See clause 12.2)

DRAWINGS

1 Drawings

In compliance of the obligations set forth in Clause 12.2 of this Agreement, the Concessionaire shall furnish to the Independent Engineer, free of cost, all Drawings listed in Annex-I of this Schedule-H

2 Additional drawings

If the Independent Engineer determines that for discharging its duties and functions under this Agreement, it requires any drawings other than those listed in Annex-I, it may by notice require the Concessionaire to prepare and furnish such drawings forthwith. Upon receiving a requisition to this effect, the Concessionaire shall promptly prepare and furnish such drawings to the independent Engineer, as if such drawings formed part of Annex-I of this Schedule-H

Schedule-H Page - 99

Annex –I (Schedule –H)

List of Drawings

1. Horizontal and Vertical Alignment with details of reference pillars, horizontal intersection points, vertical intersection points, elements of curves and sight distances. 2. Cross-section at 50 m interval along the alignment within ROW 3. Typical cross-section with details of pavement structures 4. Detailed drawings of individual bridges and structures 5. Detailed drawings for individual culverts 6. Detailed layout drawings for intersections and interchanges 7. Drawings for road signs, markings, Toll Plazas, Bus bays, parking areas and drainage system. 8. Drawings of street lighting 9. Drawings of landscaping & tree plantation 10. Drawings of Traffic Aid Post and Medical Aid Post 11. Drawings for general arrangement of base camp and administrative block 12. Traffic management drawing for safety in construction zones 13. Detailed drawings of road side furniture and safety structures 14. Any other drawings for completion of work and safety of fast & slow vehicles and pedestrians and cattle.

Schedule-H Page - 100

SCHEDULE –I (See clause 14.1.2)

TESTS

1 Schedule for Tests

1.1 The Concessionaire shall, no later than 30 (thirty) days prior to the expected completion date of the Project, notify the Independent Engineer and the Authority of its intent to subject the Project to Tests, and no later than 7 (seven) days prior to the actual date of Tests, furnish to the Independent Engineer and the Authority detailed inventory and particulars of all works and equipment forming part of the Project.

1.2 The Concessionaire shall notify the Independent Engineer of its readiness to subject the Project to Tests at any time after 7 (seven) days from the date of such notice, and upon receipt of such notice, the Independent Engineer shall, in consultation with the Concessionaire, determine the date and time for each Test and notify the same to the Authority who may designate its representative to witness the Tests. The Independent Engineer shall thereupon conduct the Tests itself or cause any of the Tests to be conducted in accordance with Article 14 and this Schedule-I

2 Test

2.1 In pursuance of the provisions of Clause 14.1.2 of this Agreement, the Independent Engineer shall conduct, or cause to be conducted, the Tests specified in this Paragraph 2.

2.2 Visual and physical Test: The Independent Engineer shall conduct a visual and physical check of the Project to determine that all works and equipment forming part thereof conform to the provisions of this Agreement.

2.3 Test drive: The Independent Engineer shall undertake a test drive of the Project by a Car and by a fully loaded Truck to determine that the quality of service conforms to the provisions of the Agreement.

2.4 Riding quality Test: Riding quality of each lane of the carriageway shall be checked with the help of a calibrated bump integrator and the maximum permissible roughness for purposes of this Test shall be 1,900 (one thousand and nine hundred) mm for each kilometre.

2.5 Pavement Composition Test: The thickness and composition of the pavement structure shall be checked on a sample basis by digging pits to determine conformity of such pavement structure with Specifications and Standards. The sample shall consist of one pit Schedule-I Page - 101

in each direction of travel to be chosen at random in each stretch of 5 (five) kilometres of the Project. The first pit for the sample shall be selected by the Independent Engineer through an open draw of lots and every fifth kilometre from such first pit shall form part of the sample for this pavement quality Test. 2.6 Cross-section Test: The cross-sections of the Project shall be checked on a sample basis through physical measurement of their dimensions for determining the conformity thereof with Specifications and Standards. For the road portion, the sample shall consist of one spot to be selected at random in each stretch of 1 (one) kilometre of the Project. The first spot for the sample shall be selected by the Independent Engineer through an open draw of lots and the spots located at every one kilometre from such first spot shall form part of the sample. For the bridge portion, one spot shall be selected at random by the Independent Engineer in each span of the bridge.

2.7 Structural Test for bridges: All major and minor bridges, including overbridges, underpasses and flyovers, constructed by the Concessionaire shall be subjected to the Rebound Hammer and Ultrasonic Pulse Velocity tests, to be conducted in accordance with the procedure described in Special Report No. 17: 1996 of the IRC Highway Research Board on Non-destructive Testing Techniques, at two spots in every span, to be chosen at random by the Independent Engineer. Bridges with a span of 15 (fifteen) meters or more shall also be subjected to load testing.

2.8 Other Tests: The Independent Engineer may require the Concessionaire to carry out or cause to be carried additional Tests, in accordance with Good Industry Practice, for determining the compliance of the Project with Specifications and Standards.

2.9 Environmental audit: The Independent Engineer shall carry out a check to determine conformity of the Project with the environmental requirements set forth in Applicable Laws and Applicable Permits.

2.10 Safety review: Safety audit of the Project shall have been undertaken by the Safety Consultant as set forth in Schedule-L, and on the basis of such audit, the Independent Engineer shall determine conformity of the Project with the provisions of this Agreement.

3 Agency for conducting Tests

All Tests set forth in this Schedule-I shall be conducted by the Independent Engineer or such other agency or person as it may specify in consultation with the Authority.

4 Completion/Provisional Certificate

Schedule-I Page - 102

Upon successful completion of Tests, the Independent Engineer shall issue the Completion Certificate or the Provisional Certificate, as the case may be, in accordance with the provisions of Article 14.

5 Tests during construction

Without prejudice to the provisions of this Schedule-I, tests during construction shall be conducted in accordance with the provisions of Clause 13.3.1.

Schedule-I Page - 103

SCHEDULE –J (See clause 14.2 & 14.3)

COMPLETION CERTIFICATE

I/We, ………………..(Name of the Independent Engineer), acting as Independent Engineer, under and in accordance with the Concession Agreement dated …………….(the “Agreement”), for development and operation of Barmer -Sindari -Jalore section of State Highway -16 and Ahore- Bali- Mundra (Sanderao to Mundra) section of State Highway -16 (Total length: 178.00 Km) (the “Project”) on design, build, operate and transfer (the “DBOT”) basis on Annuity mode, through …………………………(Name of Concessionaire), hereby certify that the Tests specified in Article 14 and Schedule-I of the Agreement have been successfully undertaken to determine compliance of the Project with the provisions of the Agreement, and I/We am/are satisfied that the Project can be safely and reliably placed in commercial service of the Users thereof.

1. It is certified that, in terms of the aforesaid Agreement, all works forming part of the Project have been completed, and the Project is hereby declared fit for entry into commercial operation on this the ………..day of ………….20………..

SIGNED, SEALED AND DELIVERED For and on behalf of INDEPENDENT ENGINEER by:

(Signature) (Name) (Designation) (Address)

Schedule-J Page - 105

PROVISIONAL CERTIFICATE 1 I/We, ……………………………..(Name of the Independent Engineer), acting as Independent Engineer, under and in accordance with the Concession Agreement dated ………. …………….(the “Agreement”), for development and operation Barmer - Sindari -Jalore section of State Highway -16 and Ahore- Bali- Mundra (Sanderao to Mundra) section of State Highway -16 (Total length: 178.00 Km) (the “Project”) on design, build, operate and transfer (the “DBOT”) basis on Annuity mode, through …………………………(Name of Concessionaire), hereby certify that the Tests specified in Article 14 and Schedule-I of the Agreement have been successfully undertaken for the Project/section…………of the Project to determine compliance thereof with the provisions of the Agreement. 2 Construction Works forming part of the Project/section………of the Project that were found to be incomplete and /or deficient have been specified in the Punch List appended hereto, and the Concessionaire has agreed and accepted that it shall complete and/or rectify all such works in the time and manner set forth in the Agreement. Some of the incomplete works have been delayed as a result of reasons attributable to the Authority or due to Force Majeure and the Provisional Certificate cannot be withheld on this account. Though the remaining incomplete works have been delayed as a result of reasons attributable to the Concessionaire, $1 I/We am/are satisfied that having regard to the nature and extent of such incomplete works, it would not be prudent to withhold commercial operation of the Project/section……. of the Project, pending completion thereof. 3 In view of the foregoing, I/We am/are satisfied that the Project/section……………of the Project can be safely and reliably placed in commercial service of the Users thereof, and in terms of the Agreement, the Project/section…………of the Project is hereby provisionally declared fit entry into commercial operation on this the …………….day of ……………20 ……………….

ACCEPTED, SIGNED, SEALED SIGNED, SEALED AND AND DELIVERED DELIVERD For and on behalf of For and on behalf of CONCESSIONAIRE by: INDEPENDENT ENGINEER by:

(Signature) (Signature (Name and Designation) (Name and Designation) (Address) (Address)

$ May be struck out if not applicable. Also strike out other parts which are not applicable. Schedule-J Page - 106

SCHEDULE–K (See clause 17.2)

MAINTENANCE REQUIREMENTS

1 Maintenance Requirements

1.1 The Concessionaire shall, at all times, operate and maintain the Project in accordance with the provisions of the Agreement, Applicable Laws and Applicable Permits. In particular, the Concessionaire shall, at all times during the Operation Period, conform to the maintenance requirements set forth in this Schedule-K (the “Maintenance Requirements”)

1.2 The Concessionaire shall repair or rectify any defect or deficiency set forth in Paragraph 2 of this Schedule-K within the time limit specified therein and any failure in this behalf shall constitute a breach of the Agreement. Upon occurrence of any breach hereunder, the Authority shall be entitled to recover Damages as set forth in Clause 17.8 of the Agreement, without prejudice to the rights of the Authority under the Agreement, including Termination thereof.

2 Repair/rectification of defects and deficiencies

2.1 The obligations of the Concessionaire in respect of Maintenance Requirements shall include repair and rectification of the defects and deficiencies specified in Annex-I of this Schedule – K within the time limit set forth therein.

2.2 The Concessionaire shall at all times maintain an adequate inventory of spares and consumables to meet the Maintenance Requirements.

3 Other defects and deficiencies

3.1 In respect of any defect or deficiency not specified in Annex – I of this Schedule-K, the Concessionaire shall undertake repair or rectification in accordance with Good Industry Practice and within the time limit specified by the Independent Engineer.

3.2 In respect of any defect or deficiency not specified in Annex-I of this Schedule-K the Independent Engineer may, in conformity with Good Industry Practice, specify the permissible limit of deviation or deterioration with reference to the Specifications and Standards, and any deviation or deterioration beyond the permissible limit shall be repaired or rectified by the Concessionaire in accordance with Good Industry Practice and within the time limit specified by the Independent Engineer.

4 Extension of time limit

Schedule-K Page - 107

Notwithstanding anything to the contrary specified in this Schedule-K, if the nature and extent of any defect or deficiency justifies more time for its repair or rectification than the time specified herein, the Concessionaire shall be entitled to additional time in conformity with Good Industry Practice. Such additional time shall be determined by the Independent Engineer and conveyed to the Concessionaire and the Authority with reasons thereof. 5 Emergency repairs/restoration

Notwithstanding anything to the contrary contained in this Schedule-K, if any defect, deficiency or deterioration in the Project poses a hazard to safety or risk of damage to property, the Concessionaire shall promptly take all reasonable measures for eliminating or minimising such danger.

6 Daily Inspection by the Concessionaire

The Concessionaire shall, through its engineer, undertake a daily visual inspection of the Project and maintain a record thereof in a register to be kept in such form and manner as the Independent Engineer may specify. Such record shall be kept in safe custody of the Concessionaire and shall be open to inspection by the Authority and the Independent Engineer at any time during office hours.

7 Divestment Requirements

All defects and deficiencies specified in this Schedule-K shall be repaired and rectified by the Concessionaire so that the Project conforms to the Maintenance Requirements on the Transfer Date.

8 Display of Schedule-K

The Concessionaire shall display a copy of this Schedule-K at the Site along with the Complaint Register stipulated in Article 40.

Schedule-K Page - 108

Annex –I (Schedule –K)

Repair/Rectification of Defects and Deficiencies

The Concessionaire shall repair and rectify the defects and deficiencies specified in this Annex-I of Schedule-K within the time limit set forth herein.

Nature of defect or deficiency Time limit for repair/rectification

ROADS

(a) Carriageway and paved shoulders

(i) Breach or blockade - Temporary Restoration Of traffic within 24 hours; permanent Restoration within 15 Days

(ii) Roughness value exceeding 2,750 mm in a stretch - 180 days of 1 km (as measured by a standardized roughometer/bump integrator)

(iii) Pot holes - 48 hours

(iv) Cracking in more than 5% of road surface in a - 30 days stretch of 1 km

(v) Rutting exceeding 10 mm in more than2% of road - 30 days surface in a stretch of 1 km (measured with 3m straight edge)

(vi) Bleeding/skidding - 7 days

Schedule-K Page - 109

(vii) Ravelling/Stripping of bitumen surface exceeding - 15 days

(viii) Damage to pavement edges exceeding 10 sq m - 15 days

(ix) Removal of debris - 6 hours

(b) Hard/earth shoulders, side slope, drains and culverts

(i) Variation by more than 2% in the prescribed slope - 30 days of camber/cross fall

(ii) Edge drop at shoulder exceeding 40 mm - 7 days

(iii) Variation by more than 15% in the prescribed side - 30 days (embankment) slope

(iv) Rain cuts/gullies in slope - 7 days

(v) Damage to or silting of culverts and side drains - 7days during and immediately preceding the rainy Season

(vi) Desilting of drains in urban/semi-urban areas - 48 hours

(c) Road side furniture including road signs and pavement marking

(i) Damage to shape or position; - 48 hours Poor visibility of loss of retro-reflectivity

(d) Street lighting and telecom (ATMS)

(i) Any major failure of the system - 24 hours

(ii) Faults and minor failures - 8 hours

Schedule-K Page - 110

(e) Trees and plantation

(i) Obstruction in a minimum head-room of 5 m above - 24 hours carriageway of obstruction in visibility of road signs

(ii) Deterioration in health of trees and bushes - Timely watering and treatment

(iii) Replacement of trees and bushes - 90 days

(iv) Removal of vegetation affecting sight line and road - 15 days structures

(f) Rest areas

(i) Cleaning of toilets - Every 4 hours

(ii) Defects in electrical, water and sanitary - 24 hours installations

(g) Toll Plazas

(i) Failure of toll collection equipment of lighting - 8 hours

(ii) Damage to Toll Plaza - 7 days

(h) Other Project Facilities and pproach roads

(i) Damage or deterioration in approach roads, - 15 days pedestrian facilities, bus-bays, bus-shelters, Traffic Aid Posts, Medical Aid Posts and other works

Schedule-K Page - 111

BRIDGES

(a) Superstructure of bridges

(i) Cracks Temporary measures - within 48 hours Permanent measures - within 45 days

(ii) Spalling/scaling - 15 days

(b) Foundation of bridges

(i) Scouring and/or cavitation - 15 days

(c) Piers, abutments, return walls and wing walls of bridges

(i) Cracks and damages including - 30 days settlement and tilting

(d) Bearings (metallic) of bridges

(i) Deformation - 15 days

(e) Joints in bridges

(i) Loosening and malfunctioning of joints - 15 days

(f) Other items relating to bridges

(i) Deforming of pads in elastomeric bearings - 7 days

(ii) Gathering of dirt in bearings and joints: or - 3 days clogging of spouts, weep holes and vent-holes

(iii) Damage or deterioration in parapets and handrails - 3 days

(iv) Rain-cuts or erosion of banks of the side slopes of - 15 days approaches

(v) Damage to wearing coat - 15 days

Schedule-K Page - 112

(vi) Damage or deterioration in approach slabs, - 30 days pitching, apron, toes, floor or guide bunds

(vii) Growth of vegetation affecting the structure or - 15 days obstructing the waterway

Schedule-K Page - 113

SCHEDULE –L (See clause 18.1.1 )

SAFETY REQUIREMENTS

1. Guiding principles 1.1 Safety Requirements aim at reduction in injuries, loss of life and damage to property resulting from accidents on or about the Project, irrespective of the person(s) at fault. 1.2 Users of the Project include motorised and non-motorised vehicles as well as pedestrians and animals involved in, or associated with accidents. Vulnerable Road Users (VRU) include pedestrians as well as riders of motorised two-wheelers, bicycles and other vehicles which do not provide adequate occupant protection. 1.3 Safety Requirements apply to all phases of construction, operation and maintenance with emphasis on identification of factors associated with accidents, consideration of the same, and implementation of appropriate remedial measures. 1.4 Safety Requirements include measures associated with traffic management and regulation such as road signs, pavement marking, traffic control devices, roadside furniture, highway design elements, enforcement and emergency response. 2 Obligations of the Concessionaire The Concessionaire shall abide by the following insofar as they relate to safety of the Users: (a) Applicable Laws and Applicable Permits;

(b) Manual for Safety in Road Design, issued by MoRTH;

(c) relevant Standards/Guidelines of IRC relating to safety, road geometrics, bridges culverts, road signs, pavement marking and roadside furniture;

(d) provisions of this Agreement; and

(e) Good Industry Practice.

3 Appointment of Safety Consultant

For carrying out safety audit of the Project under and in a accordance with this Schedule- L, the Authority shall appoint from time to time, one or more qualified firms or organizations as its consultants (the “Safety Consultant”) The Safety Consultant shall employ a team comprising, without limitation, one road safety expert and one traffic planner to undertake safety audit of the Project. Schedule-L Page - 115

4 Safety measures during Development Period

4.1 No later than 90 (ninety) days from the date of this Agreement, the Authority shall appoint a Safety Consultant for carrying out safety audit at the design stage of the Project. The Safety Consultant shall collect data on all fatal crashes and other road accidents which occurred on the Project in the Preceding two years by obtaining copies of the relevant First Information Reports (FIRs) from the police stations having jurisdiction. The information contained in such FIRs shall be summarised in the form prescribed by the Authority for this purpose and the data shall be analysed for the type of victims killed or injured, impacting vehicles, location of accidents and other relevant factors.

4.2 The Concessionaire shall provide to the Safety Consultant, in four copies, the relevant drawings containing the design details that have a bearing on safety of Users (the “Safety Drawings”) Such design details shall include horizontal and vertical alignments; sightlines; layouts of intersections; interchanges; road cross-section; bridges and culverts; side drains; provision for parked vehicles, slow moving vehicles (tractors, bullock carts, bicycles) and pedestrians; bus bays; truck lay-byes; and other incidental or consequential information. The Safety Consultant shall review the design details and forward 3 (three) copies of the Safety Drawings with its recommendations, if any, to the Independent Engineer who shall record its comments, if any, and forward one copy each to the Authority and the Concessionaire.

4.3 The accident data and the design details shall be compiled, analysed and used by the Safety Consultant for evolving a package of recommendations consisting of safety related measures for the Project. The safety audit shall be completed in a period of three months and report thereof (the “Safety Report”) shall be submitted to the Authority, in 5 (five) copies. One copy each of the Safety Report shall be forwarded by the Authority to the Concessionaire and the Independent Engineer forthwith.

4.4 The Concessionaire shall incorporate the recommendations of the Safety Report in the design of the Project, in accordance with Applicable Laws, Applicable Permits, Manuals and Guidelines of the Authority, Specifications and Standards, and Good Industry Practice If the Concessionaire does not agree with any or all of such recommendations, it shall state the reasons thereof and convey them to the Authority forthwith In the event that any or all of the works and services recommended in the Safety Report fall beyond the scope of Schedule-B, Schedule-C or Schedule-D, the Concessionaire shall make a report thereon and seek the instructions of the Authority for funding such works in accordance with the provisions of Article 18.

4.5 Without prejudice to the provisions of Paragraph 4.4, the Concessionaire and the Independent Engineer shall, within 15 (fifteen) days of receiving the Safety Report, send their respective comments thereon to the Authority, and no later than 15 (fifteen) days of Schedule-L Page - 116

receiving such comments, the Authority shall review the same alongwith the Safety Report and by notice direct the Concessionaire to carry out any or all of the recommendations contained therein with such modifications as the Authority may specify; provided that any works or services required to be undertaken hereunder shall be governed by the provisions of Article 18.

5 Safety measures during Construction Period

5.1 A Safety Consultant shall be appointed by the Authority, no later than 4 (four) months prior to the expected COD, for carrying out a safety audit of the completed Construction Works.

5.2 The Safety Consultant shall collect and analyse the accident data for the preceding two years in the manner specified in Paragraph 4.1 of this Schedule-L. It shall study the Safety Report for the Development Period and inspect the Project to assess the adequacy of safety measures. The Safety Consultant shall complete the safety audit within a period of 4 (four) months and submit a Safety Report recommending a package of additional road safety measures, if any, that are considered essential for reducing accident hazards on the Project. Such recommendations shall be processed, mutatis mutandis, and acted upon in the manner set forth in Paragraphs 4.3, 4.4 and 4.5 of this Schedule-L

5.3 The Concessionaire shall make adequate arrangements during the Construction Period for the safety of workers and road Users in accordance with the guidelines of IRC for safety in construction zones, and notify the Authority and the Independent Engineer about such arrangements.

6 Safety measures during Operation Period

6.1 The Concessionaire shall develop, implement and administer a surveillance and safety programme for Users, including correction of safety violations and deficiencies and all other actions necessary to provide a safe environment in accordance with this Agreement

6.2 The Concessionaire shall keep a copy of every FIR recorded by the Police with respect to any accident occurring on the Project. In addition, the Concessionaire shall also collect data for all cases of accidents not recorded by the Police but where a vehicle rolled over or had to be towed away. The information so collected shall be summarised in the form prescribed by the Authority for this purpose. The Concessionaire shall also record the exact location of each accident on a road map. The aforesaid data shall be submitted to the Authority at the conclusion of every quarter and to the Safety Consultant as and when appointed.

6.3 The Concessionaire shall submit to the Authority before the 31st (thirty first) May of each year, an annual report (in ten copies) containing, without limitation, a detailed listing and

Schedule-L Page - 117

analysis of all accidents of the preceding Accounting Year and the measures taken by the Concessionaire pursuant to the provisions of Paragraph 6.1 of his Schedule-L for averting or minimising such accidents in future.

6.4 Once in every Accounting Year, a safety audit shall be carried out by the Safety Consultant to be appointed by the Authority. It shall review and analyse the annual report and accident data of the preceding year, an undertake and inspection of the Project. The Safety Consultant shall complete the safety audit within a period of 1 (one) month and submit a Safety Report recommending specific improvements, if any, required to be made to the road, bridges, culverts, markings, signs, road furniture and Project Facilities, including cattle crossings and pedestrian crossings. Such recommendations shall be processed, mutatis mutandis, and acted upon in the manner set forth in Paragraphs 4.3, 4.4 and 4.5 of this Schedule-L.

7 Costs and expenses

Costs and expenses incurred in connection with the Safety Requirements set forth herein, including the provisions of Paragraph 2 of this Schedule-L, shall be met in accordance with Article 18, and in particular, the remuneration of the Safety Consultant, safety audit, and costs incidental thereto, shall be met by the Concessionaire

Schedule-L Page - 118

SCHEDULE –M (See clause 21.1)

SELECTION OF INDEPENDENT ENGINEER

1 Selection of Independent Engineer

1.1 The provisions of the Model Request for Proposals for Selection of Technical Consultants, issued by the Ministry of Finance, GOI vide OM 24(23)/PF-II/2008 dated 21 May 2009, or any substitute thereof shall apply for selection of an experienced firm to discharge the functions and duties of an Independent Engineer Provided, however, that no entity which is owned or controlled by the Authority shall be eligible for appointment as the Independent Engineer hereunder.

1.2 In the event of termination of an Independent Engineer appointed in accordance with the provisions of Paragraph 1.1, the Authority shall appoint another firm of Technical Consultants forthwith or may engage a government-owned entity in accordance with the provisions of Paragraph 5 of this Schedule-M.

1.3 The Concessionaire may, in its discretion, nominate a representative to participate in the process of selection to be undertaken by the Authority under this Schedule-M.

2 Terms of Reference

The Terms of Reference for the Independent Engineer shall substantially conform with Schedule-N

3 Fee and expenses

3.1 In determining the nature and quantum of duties and services to be performed by the Independent Engineer during the Development Period and Construction Period, the Authority shall endeavour that payments to the Independent Engineer on account of fee and expenses do not exceed 3% (three percent) of the Total project Cost. Payments not exceeding such 3% (three percent) shall be borne equally by the Authority and the Concessionaire in accordance with the provisions of this Agreement and any payments in excess thereof shall be borne entirely by the Authority.

3.2 The nature and quantum of duties and services to be performed by the Independent Engineer during the Operation Period shall be determined by the Authority in conformity with the provisions of this Agreement and with due regard for economy in expenditure. All payments made to the Independent Engineer on account of fee and expenses during the Operation Period shall be borne equally by the Authority and the Concessionaire.

Schedule-M Page - 119

4 Selection every three years

No later than 3 (three) years from the date of appointment of Independent Engineer pursuant to the provisions of Paragraph 1 of this Schedule-M, and every 3 (three) years thereafter, the Authority shall engage another firm in accordance with the criteria set forth in this Schedule-M

5 Appointment of government entity as Independent Engineer

Notwithstanding anything to the contrary contained in this Schedule, the Authority may in its discretion appoint a government-owned entity as the Independent Engineer; provided that such entity shall be a body corporate having as one of its primary function the provision of consulting, advisory and supervisory services for engineering projects; provided further that a government-owned entity which is owned or controlled by the Authority shall not be eligible for appointment as Independent Engineer.

Schedule-M Page - 120

SCHEDULE –N (See clause 21.2.1)

TERMS OF REFERENCE FOR INDEPENDENT ENGINEER

1 Scope

These Terms of Reference for the Independent Engineer (the “TOR” ) are being specified pursuant to the Concession Agreement dated ……………. (the “Agreement”) which has been entered into between the Authority and ………….. (the “Concessionaire” ) for Two-Laning of Barmer -Sindari -Jalore section of State Highway -16 and Ahore- Bali- Mundra (Sanderao to Mundra) section of State Highway -16 (Total length: 178.00 Km) (the “Project”) on design, build, operate and transfer (the “DBOT”) basis on Annuity mode, and a copy of which is annexed hereto and marked as Annex-A to form part of this TOR.

2 Definitions and interpretation

2.1 The words and expressions beginning with or in capital letters used in this TOR and not defined herein but defined in the Agreement shall have, unless repugnant to the context, the meaning respectively assigned to them in the Agreement.

2.2 References to Articles, Clauses and Schedules in this TOR shall, except where the context otherwise requires, be deemed to be references to the Articles, Clauses and Schedules of the Agreement, and references to Paragraphs shall be deemed to be references to Paragraphs of this TOR

2.3 The rules of interpretation stated in Clauses 1.2, 1.3 and 1.4 of the Agreement shall apply, mutatis mutandis, to this TOR.

3 Role and functions of the Independent Engineer

3.1 The role and functions of the Independent Engineer shall include the following:

(i) review of the Drawings and Documents as set forth in Paragraph 4;

(ii) review, inspection and monitoring of Construction Works as set forth in Paragraph 5;

(iii) conducting Tests on completion of construction and issuing Completion /Provisional Certificate as set forth in Paragraph 5:

(iv) review, inspection and monitoring of O&M as set forth in Paragraph 6; Schedule-N Page - 121

(v) review, inspection and monitoring of Divestment Requirements as set forth in Paragraph 7:

(vi) review, inspection and monitoring of Environmental Management Plan:

(vii) determining, as required under the Agreement, the costs of any works or services and/ or their reasonableness;

(viii) determining, as required under the Agreement, the period or any extension thereof, for performing any duty or obligation;

(ix) assisting the Parties in resolution of Disputes as set forth in Paragraph 9; and

(x) undertaking all other duties and functions in accordance with the Agreement.

(xi) The role & functions of Independent Engineer and reporting schedule is as under :- Period Function Days required Construction Review of drawings 15 Review of modified drawings 07 Safety reports 15 EPC contracts 07 Construction Period Monthly progress 07 Remedial safety measures 03 Operation Period Annual maintains programs 15 Monthly Statues Reports 07 O&M Reports 07

3.2 The Independent Engineer shall discharge its duties in a fair, impartial and efficient manner, consistent with the highest standards of professional integrity and Good Industry Practice.

4 Development Period

4.1 During the Development Period, the Independent Engineer shall undertake a detailed review of the Drawings to be furnished by the Concessionaire along with supporting data, Schedule-N Page - 122

including the geo-technical and hydrological investigations, characteristics of materials from borrow areas and quarry sites, topographical surveys and traffic surveys. The Independent Engineer shall complete such review and send its comments/observations to the Authority and the Concessionaire within 15 (fifteen) days of receipt of such Drawings. In particular, such comments shall specify the conformity of otherwise of such Drawings with the Scope of the Project and Specifications and Standards.

4.2 The Independent Engineer shall review any modified Drawings or supporting Documents sent to it by the Concessionaire and furnish its comments within 7 (seven) days of receiving such Drawings or Documents.

4.3 The Independent Engineer shall review the Drawings sent to it by the Safety Consultant in accordance with Schedule-L and furnish its comments thereon to the Authority and the Concessionaire within 7 (seven) days of receiving such Drawings. The Independent Engineer shall also review the Safety Report and furnish its comments thereon to the Authority within 15 (fifteen) days of receiving such report.

4.4 The Independent Engineer shall review the detailed design, construction methodology, quality assurance procedures and the procurement, engineering and construction time schedule sent to it by the Concessionaire and furnish its comments within 15 (fifteen) days of receipt thereof.

4.5 The Independent Engineer shall review the Environmental Management Plan and monitoring plans, and revise appropriately given the detailed Drawings and sire investigation reports provided by the Concessionaire. Pro-forma environmental monitoring reports will be prepared and provided to the Concessionaire before the start of the Construction Period.

4.6 Upon reference by the Authority, the Independent Engineer shall review and comment on the EPC Contract or any other contract for construction, operation and maintenance of the Project, and furnish its comments within 7 (seven) days from receipt of such reference from the Authority.

5 Construction Period

5.1 In respect of the Drawings, Documents and Safety Report received by the Independent Engineer for its review and comments during the Construction Period, the Provisions of Paragraph 4 shall apply, mutatis mutandis.

5.2 The Independent Engineer shall review the monthly progress report furnished by the Concessionaire and send its comments thereon to the Authority and the Concessionaire within 7 (seven) days of receipt of such report.

5.3 The Independent Engineer shall inspect the Construction Works and the Project once every month, preferably after receipt of the monthly progress report from the Schedule-N Page - 123

Concessionaire, but before the 20th (twentieth) day of each month in any case, and make out a report of such inspection (the “Inspection Report”) setting forth an overview of the status, progress, quality and safety of construction, including the work methodology adopted, the materials used and their sources, and conformity of Construction Works with the Scope of the Project, the Specifications and Standards and Environmental Management Plan . In a separate section of the Inspection Report, the Independent Engineer shall describe in reasonable detail the lapses, defects or deficiencies observed by it in the construction of the Project. The Inspection Report shall also contain a review of the maintenance of the existing lanes in conformity with the provisions of the Agreement. The Independent Engineer shall send a copy of its Inspection Report to the Authority and the Concessionaire within 7 (seven) days of the inspection.

5.4 The Independent Engineer may inspect the Project more than once in a month if any lapses, defects or deficiencies require such inspections.

5.5 In the event during Construction Period that unanticipated environmental impacts become apparent, the Independent Engineer shall advise the Authority and Concessionaire on additional mitigation or corrective measures to be be implemented to avoid adverse environmental effects.

5.6 For determining that the Construction Works conform to Specifications and Standards, the Independent Engineer shall require the Concessionaire to carry out, or cause to be carried out, tests on a sample basis, to be specified by the Independent Engineer in accordance with Good Industry Practice for quality assurance. For purposes of this Paragraph 5.5, the tests specified in the IRC Special Publication-11 (Handbook of Quality Control for Construction of Roads and Runways) and the Specifications for Road and Bridge Works issued by the Authority (the “Quality Control Manuals”) or any modification/substitution thereof shall be deemed to be tests conforming to Good Industry Practice for quality assurance. The Independent Engineer shall issue necessary directions to the Concessionaire for ensuring that the tests are conducted in a fair and efficient manner, and shall monitor and review the results thereof.

5.7 The sample size of the tests, to be specified by the Independent Engineer under Paragraph 5.5, shall comprise 10% (ten percent) of the quantity or number of tests prescribed for each category or type of tests in the Quality Control Manuals; provided that the Independent Engineer may, for reasons to be recorded in writing, increase the aforesaid sample size by up to 10% (ten percent) for certain categories or types of tests.

5.8 The timing of tests referred to in Paragraph 5.5, and the criteria for acceptance/rejection of their results shall be determined by the Independent Engineer in accordance with the Quality Control Manuals. The tests shall be undertaken on a random sample basis and shall be in addition to, and independent of, the tests that may be carried out by the Concessionaire for its own quality assurance in accordance with Good Industry Practice.

Schedule-N Page - 124

5.9 In the event that the Concessionaire carries out any remedial works for removal or rectification of any defects or deficiencies, the Independent Engineer shall require the Concessionaire to carry out, or cause to be carried out, tests to determine that such remedial works have brought the Construction Works into conformity with the Specifications and Standards, and the provisions of this Paragraph 5 shall apply to such tests.

5.10 In the event that the Concessionaire fails to achieve any of the Project Milestones, the Independent Engineer shall undertake a review of the progress of construction and identify potential delays, if any. If the Independent Engineer shall determine that completion of the Project is not feasible within the time specified in the Agreement, it shall require the Concessionaire to indicate within 15 (fifteen) days the steps proposed to be taken to expedite progress, and the period within which COD shall be achieved Upon receipt of a report from the Concessionaire, the Independent Engineer shall review the same and send its comments to the Authority and the Concessionaire forthwith.

5.11 If at any time during the Construction Period, the Independent Engineer determines that the Concessionaire has not made adequate arrangements for the safety of workers and Users in the zone of construction or that any work is being carried out in a manner that threatens the safety of the workers and the Users, it shall make a recommendation to the Authority forthwith, identifying the whole or part of the Construction Works that should be suspended for ensuring safety in respect thereof.

5.12 In the event that the Concessionaire carries out any remedial measures to secure the safety of suspended works and Users, it may, by notice in writing, require the Independent Engineer to inspect such works, and within 3 (three) days of receiving such notice, the Independent Engineer shall inspect the suspended works and make a report to the Authority forthwith, recommending whether or not such suspension may be revoked by the Authority.

5.13 If suspension of Construction Works is for reasons not attributable to the Concessionaire, the Independent Engineer shall determine the extension of dates set forth in the Project Completion Schedule, to which the Concessionaire is reasonably entitled, and shall notify the Authority and the Concessionaire of the same.

5.14 The Independent Engineer shall carry out, or cause to be carried out, all the Tests specified in Schedule-I and issue a Completion Certificate or Provisional Certificate, as the case may be. For carrying out its functions under this Paragraph 5.13 and all matters incidental thereto, the Independent Engineer shall act under and in accordance with the provisions of Article 14 and Schedule-I.

5.15 Upon reference from the Authority, the Independent Engineer shall make a fair and reasonable assessment of the costs of providing information, works and services as set forth in Article 16 and certify the reasonableness of such costs for payment by the Authority to the Concessionaire. Schedule-N Page - 125

5.16 The Independent Engineer shall aid and advise the Concessionaire in preparing the Maintenance Manual.

6 Operation Period

6.1 In respect of the Drawings, Documents and Safety Report received by the Independent Engineer for its review and comments during the Operation Period, the provisions of Paragraph 4 shall apply, mutatis mutandis.

6.2 The Independent Engineer shall review the annual Maintenance Programme furnished by the Concessionaire and send its comments thereon to the Authority and the Concessionaire within 15 (fifteen) days of receipt of the Maintenance Programme.

6.3 The Independent Engineer shall review the monthly status report furnished by the Concessionaire and send its comments thereon to the Authority and the Concessionaire within 7 (seven) days of receipt of such report.

6.4 The Independent Engineer shall inspect the Project once every month, preferably after receipt of the monthly status report from the Concessionaire, but before the 20th (twentieth) day of each month in any case, and make out an O&M Inspection Report setting forth an overview of the status, quality and safety of O&M including its conformity with the Maintenance Requirements, Safety Requirements and Environmental Management Plan. In a separate section of the O&M Inspection Report, the Independent Engineer shall describe in reasonable detail the lapses, defects or deficiencies observed by it in O&M of the Project. The Independent Engineer shall send a copy of its O&M Inspection Report to the Authority and the Concessionaire within 7 (seven) days of the inspection.

6.5 The Independent Engineer may inspect the Project more than once in a month, if any lapses, defects or deficiencies require such inspections.

6.6 The Independent Engineer shall in its O&M Inspection Report specify the tests, if any, that the Concessionaire shall carry out, or cause to be carried out, for the purpose of determining that the Project is in conformity with the Maintenance Requirements. It shall monitor and review the results of such tests and the remedial measures, if any, taken by the Concessionaire in this behalf.

6.7 In respect of any defect or deficiency referred to in Paragraph 3 of Schedule-K, the Independent Engineer shall, in conformity with Good Industry Practice, specify the permissible limit of deviation or deterioration with reference to the Specifications and

Schedule-N Page - 126

Standards and shall also specify the time limit for repair or rectification of any deviation or deterioration beyond the permissible limit.

6.8 The Independent Engineer shall determine if any delay has occurred in completion of repair or remedial works in accordance with the Agreement, and shall also determine the Damages, if any, payable by the Concessionaire to the Authority for such delay.

6.9 The Independent Engineer shall examine the request of the Concessionaire for closure of any lane (s) of the carriageway for undertaking maintenance/repair thereof, keeping in view the need to minimise disruption in traffic and the time required for completing such maintenance/repair in accordance with Good Industry Practice. It shall grant permission with such modifications, as it may deem necessary, within 3 (three) days of receiving a request from the Concessionaire. Upon expiry of the permitted period of closure, the Independent Engineer shall monitor the re-opening of such lane(s), and in case of delay, determine the Damages payable by the Concessionaire to the Authority under Clause 17.7.

6.10 The Independent Engineer shall monitor and review the curing of defects and deficiencies by the Concessionaire as set forth in Clause 19.4.

6.11 In the event that the Concessionaire notifies the Independent Engineer of any modifications that it proposes to make to the Project, the Independent Engineer shall review the same and send its comments to the Authority and the Concessionaire within 15 (fifteen) days of receiving the proposal.

6.12 The Independent Engineer shall undertake traffic sampling, as and when required by the Authority, under and in accordance with the provisions of this Agreement.

7 Termination

7.1 At any time, not earlier than 90 (ninety) days prior to Termination but not later than 15 (fifteen) days prior to such Termination, the Independent Engineer shall, in the presence of a representative of the Concessionaire, inspect the Project for determining compliance by the Concessionaire with the Divestment Requirements set forth in Clause 32.1 and, if required, cause tests to be carried out at the Concessionaire‟s cost for determining such compliance. If the Independent Engineer determines that the status of the Project is such that its repair and rectification would require a larger amount than the sum set forth in Clause 33.2, it shall recommend retention of the required amount in the Escrow Account and the period of retention thereof.

7.2 The Independent Engineer shall inspect the Project once in every 15 (fifteen) days during a period of 90 (ninety) days after Termination for determining the liability of the Concessionaire under Article 33, in respect of the defects or deficiencies specified therein. If any such defect or deficiency is found by the Independent Engineer, it shall

Schedule-N Page - 127

make a report in reasonable detail and send it forthwith to the Authority and the Concessionaire.

8 Determination of costs and time 8.1 The Independent Engineer shall determine the costs, and/or their reasonableness, that are required to be determined by it under the Agreement.

8.2 The Independent Engineer shall determine the period, or any extension thereof, that is required to be determined by it under the Agreement.

9 Assistance in Dispute resolution

9.1 When called upon by either Party in the event of any Dispute, the Independent Engineer shall mediate and assist the Parties in arriving at an amicable settlement.

9.2 In the event of any disagreement between the Parties regarding the meaning, scope and nature of Good Industry Practice, as set forth in any provision of the Agreement, the Independent Engineer shall specify such meaning, scope and nature by issuing a reasoned written statement relying on good industry practice and authentic literature.

10 Other duties and function

The Independent Engineer shall perform all other duties and functions specified in the Agreement.

11 Miscellaneous

11.1 The Independent Engineer shall notify its programme of inspection to the Authority and to the Concessionaire, who may, in their discretion, depute their respective representatives to be present during the inspection.

11.2 A copy of all communications, comments, instructions, Drawings or Documents sent by the Independent Engineer to the Concessionaire pursuant to this TOR, and a copy of all the test results with comments of the Independent Engineer thereon shall be furnished by the Independent Engineer to the Authority forthwith.

11.3 The Independent Engineer shall obtain, and the Concessionaire shall furnish in 2 (two) copies thereof all communications and reports required to be submitted, under this Agreement, by the Concessionaire to the Independent Engineer whereupon the Independent Engineer shall send 1 (one) of the copies to the Authority along with its comments thereon.

11.4 The Independent Engineer shall retain at least one copy each of all Drawings and Documents received by it, including „as-built‟ Drawings, and keep them in its safe custody.

Schedule-N Page - 128

11.5 Upon completion of its assignment hereunder, the Independent Engineer shall duly classify and list all Drawings, Documents, results of tests and other relevant records, and hand them over to the Authority or such other person as the Authority may specify, and obtain written receipt thereof. Two copies of the said documents shall also be furnished in their editable digital format or in such other medium or manner as may be acceptable to the Authority.

11.6 Wherever no period has been specified for delivery of services by the independent Engineer, the Independent Engineer shall act with the efficiency and urgency necessary for discharging its functions in accordance with Good Industry Practice.

Schedule-N Page - 129

SCHEDULE-O (See Clause 25.1.2)

ESCROW AGREEMENT

THIS ESCROW AGREEMENT is entered into on this the ………………..…day of ……….20……..

AMONGST

1 …………….Limited, a company incorporated under the provisions of the Companies Act, 2013 and having its registered office at ……………………(hereinafter referred to as the “Concessionaire” which expression shall, unless repugnant to the context or meaning thereof, include its successors, permitted assigns and substitutes);

2 ……………….(insert name and particulars of Lenders‟ Representative) and having its registered office at………………….acting for and on behalf of the Senior Lenders as their duly authorised agent with regard to matters arising out of or in relation to this Agreement (hereinafter referred to as the “Lenders’ Representative” which expression shall, unless repugnant to the context or meaning thereof, include its successors and substitutes);

3 ……………….. (Insert name and particulars of the Escrow Bank) and having its registered office at …………………………………… (Hereinafter referred to as the “Escrow Bank” which expression shall, unless repugnant to the context or meaning thereof, include its administrators, successors and substitutes); and

4 The Governor of Rajasthan, represented by Additional Chief Secretary, Public Works Department, Government of Rajasthan and having its principal officers at Jacob Road, Civil Lines, Jaipur – 302006 (hereinafter referred to as the “Authority” which expression shall, unless repugnant to the context or meaning thereof, include its administrators, successors and assigns).

WHEREAS:

(A) The Authority has entered into a Concession Agreement dated……………….with the Concessionaire (the “Concession Agreement”) for development and operation of Barmer -Sindari -Jalore section of State Highway -16 and Ahore- Bali- Mundra (Sanderao to Mundra) section of State Highway -16 (Total length: 178.00 Km) (the “Project”) on design, build, operate and transfer (the “DBOT”) basis on Annuity mode, and a copy of which is annexed hereto and marked as Annex-A to form part of this Agreement.

Schedule-O Page - 130

(B) Senior Lenders have agreed to finance the Project in accordance with the terms and conditions set forth in the Financing Agreements.

(C) The Concession Agreement requires the Concessionaire to establish an Escrow Account, inter alia, on the terms and conditions stated therein

NOW, THEREFORE, in consideration of the foregoing and the respective covenants and agreements set forth in this Agreement, the receipt and sufficiency of which is hereby acknowledged, and intending to be legally bound hereby, the Parties agree as follows:

1 DEFINITIONS AND INTERPRETATION

1.1 Definitions

In this Agreement, the following words and expressions shall, unless repugnant to the context or meaning thereof, have the meaning hereinafter respectively assigned to them:

“Agreement” means this Escrow Agreement and any amendment thereto made in accordance with the provisions contained herein;

“Concession Agreement” means the Concession Agreement referred to in Recital (A) above and annexed hereto as Annex-A, and shall include all of its Recitals and Schedules and any amendments made thereto in accordance with the provisions contained in this behalf therein;

“Cure Period” means the period specified in this Agreement for curing any breach or default of any provision of this Agreement by the Concessionaire, and shall commence from the date on which a notice is delivered by the Authority or the Lenders‟ Representative, as the case may be, to the Concessionaire asking the latter to cure the breach or default specified in such notice;

"Escrow Default" shall have the meaning ascribed thereto in Clause 6.1;

“Escrow Account” means an escrow account established in terms of and under this Agreement, and shall include the Sub- Accounts;

“Lenders Representative” means the person referred to as the Lenders Representative in the foregoing Recitals;

“Parties” means the parties to this Agreement collectively and “Party” shall mean any of the Parties to this Agreement individually;

“Payment Date” means, in relation to any payment specified in Clause 4.1, the date(s) specified for such payment; and Schedule-O Page - 131

“Sub-Accounts” means the respective sub-accounts of the Escrow Account, into which the monies specified in Clause 4.1 would be credited every month and paid out if due, and if not due in month then appropriated proportionately in such month and retained in the respective sub-accounts and paid out there from on the Payment Date(s).

1.2 Interpretation

1.2.1 References to Lenders‟ Representative shall, unless repugnant to the context or meaning thereof, mean references to the Lenders‟ Representative, acting for and on behalf of Senior Lenders.

1.2.2 The words and expressions beginning with capital letters and defined in this Agreement shall have the meaning ascribed thereto herein, and the words and expressions used in this Agreement and not defined herein but defined in the Concession Agreement shall, unless repugnant to the context, have the meaning ascribed thereto in the Concession Agreement.

1.2.3 References to Clauses are, unless stated otherwise, references to Clauses of this Agreement.

1.2.4 The rules of interpretation stated in Clauses 1.2, 1.3 and 1.4 of the Concession Agreement shall apply, mutatis mutandis, to this Agreement.

2 ESCROW ACCOUNT

2.1 Escrow Bank to act as trustee

2.1.1 The Concessionaire hereby appoints the Escrow Bank to act as trustee for the Authority, the Lenders‟ Representative and the Concessionaire in connection herewith and authorises the Escrow Bank to exercise such rights, powers, authorities and discretion as are specifically delegated to the Escrow Bank by the terms hereof together with all such rights, powers, authorities and discretion as are reasonably incidental hereto, and the Escrow Bank accepts such appointment pursuant to the terms hereof.

2.1.2 The Concessionaire hereby declares that all rights, title and interest in and to the Escrow Account shall be vested in the Escrow Bank and held in trust for the Authority, the Lenders‟ Representative and the Concessionaire, and applied in accordance with the terms of this Agreement. No person other than the Authority, the Lenders‟ Representative and the Concessionaire shall have any rights hereunder as the beneficiaries of, or as third party beneficiaries under this Agreement.

2.2 Acceptance of Escrow Bank

Schedule-O Page - 132

The Escrow Bank hereby agrees to act as such and to accept all payments and other amounts to be delivered to and held by the Escrow Bank pursuant to the provisions of this Agreement. The Escrow Bank shall hold and safeguard the Escrow Account during the term of this Agreement and shall treat the amount in the Escrow Account as monies deposited by the Concessionaire, Senior Lenders or the Authority with the Escrow Bank. In performing its functions and duties under this Agreement, the Escrow Bank shall act in trust for the benefit of, and as agent for, the Authority, the Lenders‟ Representative and the Concessionaire or their nominees, successors or assigns, in accordance with the provisions of this Agreement.

2.3 Establishment and operation of Escrow Account

2.3.1 Within 30 (thirty) days from the date of this Agreement, and in any case prior to the Appointed Date, the Concessionaire shall open and establish the Escrow Account with the ……………………… (name of Branch) Branch of the Escrow Bank. The Escrow Account shall be denominated in Rupees.

2.3.2 The Escrow Bank shall maintain the Escrow Account in accordance with the terms of this Agreement and its usual practices and applicable regulations, and pay the maximum rate of interest payable to similar customers on the balance in the said account from time to time.

2.3.3 The Escrow Bank and the Concessionaire shall, after consultation with the Lenders Representative, agree on the detailed mandates, terms and conditions, and operating procedures for the Escrow Account, but in the event of any conflict or inconsistency between this Agreement and such mandates, terms and conditions, or procedures, this Agreement shall prevail.

2.4 Escrow Bank’s fee

The Escrow Bank shall be entitled to receive its fee and expenses in an amount, and at such times, as may be agreed between the Escrow Bank and the Concessionaire. For the avoidance of doubt, such fee and expenses shall form part of the O&M Expenses and shall be appropriated from the Escrow Account in accordance with Clause 4.1

2.5 Rights of the Parties

Save and except as otherwise provided in the Concession Agreement, the rights of the Authority, the Lenders‟ Representative and the Concessionaire in the monies held in the Escrow Account are set forth in their entirety in this Agreement and the Authority, the Lenders‟ Representative and the Concessionaire shall have no other rights against or to the monies in the Escrow Account.

2.6 Substitution of the Concessionaire

Schedule-O Page - 133

The Parties hereto acknowledge and agree that upon substitution of the Concessionaire with the Nominated Company, pursuant to the Substitution Agreement, it shall be deemed for the purposes of this Agreement that the Nominated Company is a Party hereto and the Nominated Company shall accordingly be deemed to have succeeded to the rights and obligations of the Concessionaire under this Agreement on and with effect from the date of substitution of the Concessionaire with the Nominated Company. 3 DEPOSITS INTO ESCROW ACCOUNT

3.1 Deposits by the Concessionaire

3.1.1 The Concessionaire agrees and undertakes that it shall deposit into and/or credit the Escrow Account with:

(a) All monies received in relation to the Project from any source, including the Senior Lenders, lenders of Subordinated Debt and the Authority;

(b) all funds received by the Concessionaire from its share-holders, in any manner or form;

(c) any other revenues, rentals, deposits or capital receipts, as the case may be, from or in respect of the Project; and

(d) all proceeds received pursuant to any insurance claims.

3.1.2 The Concessionaire may at any time make deposits of its other funds into the Escrow Account, provided that the provisions of this Agreement shall apply to such deposits.

3.2 Deposits by the Authority

The Authority agrees and undertakes that, as and when due and payable, it shall deposit into and/or credit the Escrow Account with:

(a) Grant and any other monies disbursed by the Authority to the Concessionaire;

(b) all revenues collected by the Authority in exercise of its rights under the Concession Agreement; and

(c) termination Payments:

Provided that, notwithstanding the provisions of Clause 4.1.1, the Authority shall be entitled to appropriate from the aforesaid amounts, any amounts due and payable to it by the Concessionaire, and the balance remaining shall be deposited into the Escrow Account.

3.3 Deposits by Senior Lenders Schedule-O Page - 134

The Lenders‟ Representative agrees, confirms and undertakes that the Senior Lenders shall deposit into and/or credit the Escrow Account with all disbursements made by them in relation to or in respect of the Project; provided that notwithstanding anything to the contrary contained in this Agreement, the Senior Lenders shall be entitled to make direct payments to the EPC Contractor under and in accordance with the express provisions contained in this behalf in the Financing Agreements.

3.4 Interest on deposits

The Escrow Bank agrees and undertakes that all interest accruing on the balances of the Escrow Account shall be credited to the Escrow Account; provided that the Escrow Bank shall be entitled to appropriate therefrom the fee and expenses due to it from the Concessionaire in relation to the Escrow Account and credit the balance remaining to the Escrow Account.

4 WITHDRAWALS FROM ESCROW ACCOUNT

4.1 Withdrawals during Concession Period

4.1.1 At the beginning of every month, or at such shorter intervals as the Lenders‟ Representative and the Concessionaire may by written instructionsdetermine, the Escrow Bank shall withdraw amounts from the Escrow Account and appropriate them in the following order by depositing such amounts in the relevant Sub-Accounts for making due payments, and if such payments are not due in any month, then retain such monies in such Sub-Accounts and pay out therefrom on the Payment Date(s).

(a) all taxes due and payable by the Concessionaire for and in respect of the Project;

(b) all payments relating to construction of the Project, subject to and in accordance with the conditions, if any, set forth in the Financing Agreements;

(c) O&M Expenses, subject to the ceiling, if any, set forth in the Financing Agreements;

(d) O&M Expenses and other costs and expenses incurred by the Authority in accordance with the provisions of the Concession Agreement, and certified by the Authority as due and payable to it;

(e) any amounts due and payable to the Authority;

(f) monthly proportionate provision of Debt Service due in an Accounting Year;

(g) all payments and Damages certified by the Authority as due and payable to it by the Concessionaire pursuant to the Concession Agreement;

Schedule-O Page - 135

(h) monthly proportionate provision of debt service payments due in an Accounting Year in respect of Subordinated Debt;

(i) any reserve requirements set forth in the Financing Agreements; and

(j) balance, if any, in accordance with the instructions of the Concessionaire.

4.1.2 No later than 60 (sixty) days prior to the commencement of each Accounting Year, the Concessionaire shall provide to the Escrow Bank, with prior written approval of the Lenders‟ Representative, details of the amounts likely to be required for each of the payment obligations set forth in this Clause 4.1; provided that such amounts may be subsequently modified, with prior written approval of the Lenders‟ Representative, if fresh information received during the course of the year makes such modification necessary.

4.2 Withdrawals upon Termination

Upon Termination of the Concession Agreement, all amounts standing to the credit of the Escrow Account shall, notwithstanding anything in this Agreement, be appropriated and dealt with in the following order:

(a) all taxes due and payable by the Concessionaire for and in respect of the Project;

(b) 90% (ninety percent) of Debt Due excluding Subordinated Debt;

(c) all payments and Damages certified by the Authority as due and payable to it by the Concessionaire pursuant to the Concession Agreement, including any claims in connection with or arising out of Termination;

(d) retention and payments arising out of, or in relation to, liability for defects and deficiencies set forth in Article 33 of the Concession Agreement;

(e) outstanding Debt Service including the balance of Debt Due;

(f) outstanding Subordinated Debt;

(g) incurred or accrued O&M Expenses;

(h) any other payments required to made under the Concession Agreement; and

(i) balance, if any , in accordance with the instructions of the Concessionaire:

Provided that the disbursements specified in Sub- clause (i) of this Clause 4.2 shall be undertaken only after the Vesting Certificate has been issued by the Authority.

Schedule-O Page - 136

4.3 Application of insufficient funds

Funds in the Escrow Account shall be applied in the serial order of priority set forth in Clauses 4.1 and 4.2, as the case may be. If the funds available are not sufficient to meet all the requirements, the Escrow Bank shall apply such funds in the serial order of priority until exhaustion thereof.

4.4 Application of insurance proceeds Notwithstanding anything in this Agreement, the proceeds from all insurance claims, except life and injury, shall be deposited into and/or credited to the Escrow Account and utilised for any necessary repair, reconstruction, reinstatement, replacement, improvement, delivery or installation of the Project, and the balance remaining, if any, shall be applied in accordance with the provisions contained in this behalf in the Financing Agreements.

4.5 Withdrawals during Suspension

Notwithstanding anything to the contrary contained in this Agreement, the Authority may exercise all or any of the rights of the Concessionaire during the period of Suspension under Article 30 of the Concession Agreement. Any instructions given by the Authority to the Escrow Bank during such period shall be complied with as if such instructions were given by the Concessionaire under this Agreement and all actions of the Authority hereunder shall be deemed to have been taken for and on behalf of the Concessionaire.

5 OBLIGATIONS OF THE ESCROW BANK

5.1 Segregation of funds

Monies and other property received by the Escrow Bank under this Agreement shall, until used or applied in accordance with this Agreement, be held by the Escrow Bank in trust for the purposes for which they were received, and shall be segregated from other funds and property of the Escrow Bank.

5.2 Notification of balances

7 (seven) business days prior to each Payment Date (and for this purpose of the Escrow Bank shall be entitled to rely on an affirmation by the Concessionaire and/or the Lenders‟ Representative as to the relevant Payment Dates), the Escrow Bank shall notify the Lenders‟ Representative of the balances in the Escrow Account and Sub-Accounts as at the close of business on the immediately preceding business day.

5.3 Communication and notices

In discharge of its duties and obligations hereunder, the Escrow Bank:

Schedule-O Page - 137

(a) may, in the absence of bad faith or gross negligence on its part, rely as to any matters of fact which might reasonably be expected to be within the knowledge of the Concessionaire upon a certificate signed by or on behalf of the Concessionaire;

(b) may, in the absence of bad faith or gross negligence on its part, rely upon the authenticity of any communication or document believed by it to be authentic;

(c) shall, within 5 (five) business days after receipt, deliver a copy to the Lenders‟ Representative of any notice or document received by it in its capacity as the Escrow Bank from the Concessionaire or any other person hereunder or in connection herewith; and

(d) shall, within 5 (five) business days after receipt, deliver a copy to the Concessionaire of any notice or document received by it from the Lenders‟ Representative in connection herewith.

5.4 No set off

The Escrow Bank agrees not to claim or exercise any right of set off, banker‟s lien or other right or remedy with respect to amounts standing to the credit of the Escrow Account. For the avoidance of doubt, it is hereby acknowledged and agreed by the Escrow Bank that the monies and properties held by the Escrow Bank in the Escrow Account shall not be considered as part of the assets of the Escrow Bank and being trust property, shall in the case of bankruptcy or liquidation of the Escrow Bank, be wholly excluded from the assets of the Escrow Bank in such bankruptcy or liquidation.

5.5 Regulatory approvals

The Escrow Bank shall use its best efforts to procure, and thereafter maintain and comply with, all regulatory approvals required for it to establish and operate the Escrow Account. The Escrow Bank represents and warrants that it is not aware of any reason why such regulatory approvals will not ordinarily be granted to the Escrow Bank.

6 ESCROW DEFAULT

6.1 Escrow Default

6.1.1 Following events shall constitute an event of default by the Concessionaire (an “Escrow Default”) unless such event of default has occurred as a result of Force Majeure or any act or omission of the Authority or the Lenders‟ Representative:

(a) the Concessionaire commits breach of this Agreement by failing to deposit any receipts into the Escrow Account as provided herein and fails to cure such breach

Schedule-O Page - 138

by depositing the same into the Escrow Account within a Cure Period of 5 (five) business days:

(b) the Concessionaire causes the Escrow Bank to transfer funds to any account of the Concessionaire in breach of the terms of this Agreement and fails to cure such breach by depositing the relevant funds into the Escrow Account or any Sub- Account in which such transfer should have been made, within a Cure Period of 5 (five) business days; or

(c) the Concessionaire commits or causes any other breach of the provisions of this Agreement and fails to cure the same within a Cure Period of 5 (five) business days.

6.1.2 Upon occurrence of an Escrow Default, the consequences thereof shall be dealt with under and in accordance with the provisions of the Concession Agreement.

7 TERMINATION OF ESCROW AGREEMENT

7.1 Duration of the Escrow Agreement

This Agreement shall remain in full force and effect so long as any sum remains to be advanced or is outstanding from the Concessionaire in respect of the debt, guarantee or financial assistance received by it from the Senior Lenders, or any of its obligations to the Authority remain to be discharged, unless terminated earlier by consent of all the Parties or otherwise in accordance with the provisions of this Agreement.

7.2 Substitution of Escrow Bank

The Concessionaire may, by not less than 45 (forty five) days prior notice to the Escrow Bank, the Authority and the Lenders‟ Representative, terminate this Agreement and appoint a new Escrow Bank, provided that the new Escrow Bank is acceptable to the Lenders‟ Representative and arrangements are made satisfactory to the Lenders‟ Representative for transfer of amounts deposited in the Escrow Account to a new Escrow Account established with the successor Escrow Bank.

The termination of this Agreement shall take effect only upon coming into force of an Escrow Agreement with the substitute Escrow Bank.

7.3 Closure of Escrow Account

The Escrow Bank shall, at the request of the Concessionaire and the Lenders‟ Representative made on or after the payment by the Concessionaire of all outstanding amounts under the Concession Agreement and the Financing Agreements including the

Schedule-O Page - 139

payments specified in Clause 4.2, and upon confirmation of receipt of such payments, close the Escrow Account and Sub-Accounts and pay any amount standing to the credit thereof to the Concessionaire Upon closure of the Escrow Account hereunder, the Escrow Agreement shall be deemed to be terminated.

8 SUPPLEMENTARY ESCROW AGREEMENT

8.1 Supplementary escrow agreement

The Lenders‟ Representative and the Concessionaire shall be entitled to enter into a supplementary escrow agreement with the Escrow Bank providing, inter alia, for detailed procedures and documentation for withdrawals from Sub-Accounts pursuant to Clause 4.1.1 and for matters not covered under this Agreement such as the rights and obligations of the Senior Lenders and lenders of Subordinated Debt, investment of surplus funds, restrictions on withdrawals by the Concessionaire in the event of breach of this Agreement or upon occurrence of an Escrow Default, procedures relating to operation of the Escrow Account and withdrawal therefrom, reporting requirements and any matters incidental thereto; provided that such supplementary escrow agreement shall not contain any provision which is inconsistent with this Agreement and in the event of any conflict or inconsistency between provisions of this Agreement and such supplementary escrow agreement, the provisions of this Agreement shall prevail.

9 INDEMNITY

9.1 General indemnity

9.1.1 The Concessionaire will indemnify, defend and hold the Authority, Escrow Bank and the Senior Lenders, acting through the Lenders‟ Representative, harmless against any and all proceedings, actions and third party claims for any loss, damage, cost and expense arising out of any breach by the Concessionaire of any of its obligations under this Agreement or on account of failure of the Concessionaire to comply with Applicable Laws and Applicable Permits.

9.1.2 The Authority will indemnify, defend and hold the Concessionaire harmless against any and all proceedings, actions and third party claims for any loss, damage, cost and expense arising out of failure of the Authority to fulfil any of its obligations under this Agreement materially and adversely affecting the performance of the Concessionaire‟s obligations under the Concession Agreement or this Agreement other than any loss, damage, cost and expense arising out of acts done in discharge of their lawful functions by the Authority, its officers, servants and agents.

9.1.3 The Escrow Bank will indemnify, defend and hold the Concessionaire harmless against any and all proceedings, actions and third party claims for any loss, damage, cost and expense arising out of failure of the Escrow Bank to fulfil its obligations under this Schedule-O Page - 140

Agreement materially and adversely affecting the performance of the Concessionaire‟s obligations under the Concession Agreement other than any loss, damage, cost and expense, arising out of acts done in discharge of their lawful functions by the Escrow Bank, its officers, servants and agents.

9.2 Notice and contest of claims

In the event that any Party hereto receives a claim from a third party in respect of which it is entitled to the benefit of an indemnity under Clause 9.1 or in respect of which it is entitled to reimbursement (the “Indemnified Party”), it shall notify the other Party responsible for indemnifying such claim hereunder (the “Indemnifying Party”) within 15 (fifteen) days of receipt of the claim and shall not settle or pay the claim without the prior approval of the Indemnifying Party, which approval shall not be unreasonably withheld or delayed. In the event that the Indemnifying Party wishes to contest or dispute the claim, it may conduct the proceedings in the name of the Indemnified Party and shall bear all costs involved in contesting the same. The Indemnified Party shall provide all cooperation and assistance in contesting any claim and shall sign all such writings and documents as the Indemnifying Party may reasonably require.

10 DISPUTE RESOLUTION

10.1 Dispute resolution

10.1.1 Any dispute, difference or claim arising out of or in connection with this Agreement, which is not resolved amicably, shall be decided finally by reference to arbitration to a Board of Arbitrators comprising one nominee of each Party to the dispute, and where the number of such nominees is an even number, the nominees shall elect another person to such Board. Such arbitration shall be held in accordance with the Rules of Arbitration of the International Centre for Alternative Dispute Resolution, New Delhi (the “Rules”) or such other rules as may be mutually agreed by the Parties, and shall be subject to the provisions of the Arbitration and Conciliation Act, 1996.

10.1.2 The Arbitrators shall issue a reasoned award and such award shall be final and binding on the Parties. The place of arbitration shall be the capital of the State and the language of arbitration shall be English.

11 MISCELLANEOUS PROVISIONS

11.1 Governing law and jurisdiction

This Agreement shall be construed and interpreted in accordance with and governed by the laws of , and the courts in the State shall have jurisdiction over all matters arising out of or relating to this Agreement. Schedule-O Page - 141

11.2 Waiver of sovereign immunity

The Authority unconditionally and irrevocably:

(a) agrees that the execution, delivery and performance by it of this Agreement constitute commercial acts done and performed for commercial purpose;

(b) agrees that, should any proceedings be brought against it or its assets, property or revenues in any jurisdiction in relation to this Agreement or any transaction contemplated by this Agreement, no immunity (whether by reason of sovereignty or otherwise) from such proceedings shall be claimed by or on behalf of the Authority with respect to its assets;

(c) waives any right of immunity which it or its assets, property or revenues now has, may acquire in the future or which may be attributed to it in any jurisdiction; and

(d) consents generally in respect of the enforcement of any judgement or award against it in any such proceedings to the giving of any relief or the issue of any process in any jurisdiction in connection with such proceedings (including the making, enforcement or execution against it or in respect of any assets, property or revenues whatsoever irrespective of their use or intended use of any order or judgement that may be made or given in connection therewith).

11.3 Priority of agreements

In the event of any conflict between the Concession Agreement and this Agreement, the provisions contained in the Concession Agreement shall prevail over this Agreement.

11.4 Alteration of terms

All additions, amendments, modifications and variations to this Agreement shall be effectual and binding only if in writing and signed by the duly authorised representatives of the Parties.

11.5 Waiver

11.5.1 Waiver by any Party of a default by another Party in the observance and performance of any provision of or obligations under this Agreement:

(a) shall not operate or be construed as a waiver of any other or subsequent default hereof or of other provisions of or obligations under this Agreement;

(b) shall not be effective unless it is in writing and executed by a duly authorised representative of the Party; and

Schedule-O Page - 142

(c) shall not affect the validity or enforceability of this Agreement in any manner.

11.5.2 Neither the failure by any Party to insist on any occasion upon the performance of the terms, conditions and provisions of this Agreement or any obligation thereunder nor time or other indulgence granted by any Party to another Party shall be treated or deemed as waiver of such breach or acceptance of any variation or the relinquishment of any such right hereunder.

11.6 No third party beneficiaries

This Agreement is solely for the benefit of the Parties and no other person or entity shall have any rights hereunder.

11.7 Survival

11.7.1 Termination of this Agreement:

(a) shall not relieve the Parties of any obligations hereunder which expressly or by implication survive termination hereof; and

(b) except as otherwise provided in any provision of this Agreement expressly limiting the liability of either Party, shall not relieve either Party of any obligations or liabilities for loss or damage to the other Party arising out of, or caused by, acts or omissions of such Party prior to the effectiveness of such termination or arising out of such termination.

11.7.2 All obligations surviving the cancellation, expiration or termination of this Agreement shall only survive for a period of 3 (three) years following the date of such termination or expiry of this Agreement.

11.8 Severability

If for any reason whatever any provision of this Agreement is or becomes invalid, illegal or unenforceable or is declared by any court of competent jurisdiction or any other instrumentality to be invalid, illegal or unenforceable, the validity, legality or enforceability of the remaining provisions shall not be affected in any manner, and the Parties will negotiate in good faith with a view to agreeing to one or more provisions which may be substituted for such invalid, unenforceable or illegal provisions, as nearly as is practicable to such invalid, illegal or unenforceable provision. Failure to agree upon any such provisions shall not be subject to dispute resolution under Clause 10.1 of this Agreement or otherwise.

Schedule-O Page - 143

11.9 Successors and assigns

This Agreement shall be binding on and shall inure to the benefit of the Parties and their respective successors and permitted assigns.

11.10 Notices

All notices or other communications to be given or made under this Agreement shall be in writing and shall either be delivered personally or sent by courier or registered post with an additional copy to be sent by facsimile or e-mail. The address for service of each Party, its facsimile number and e-mail are set out under its name on the signing pages hereto. A notice shall be effective upon actual receipt thereof, save that where it is received after 5.30 (five thirty) p.m. on a business day, or on a day that is not a business day, the notice shall be deemed to be received on the first business day following the date of actual receipt. Without prejudice to the foregoing a Party giving or making a notice or communication by facsimile or e-mail shall promptly deliver a copy thereof personally, or send it by courier or registered post to the addressee of such notice or communication. It is hereby agreed and acknowledged that any Party may by notice change the address to which such notices and communications to it are to be delivered or mailed. Such change shall be effective when all the Parties have notice of it.

11.11 Language

All notices, certificates, correspondence and proceedings under or in connection with this Agreement shall be in English.

11.12 Authorised representatives

Each of the Parties shall, by notice in writing, designate their respective authorised representatives through whom only all communications shall be made. A Party hereto shall be entitled to remove and/or substitute or make fresh appointment of such authorised representative by similar notice.

11.13 Original Document

This Agreement may be executed in four counterparts, each of which when executed and delivered shall constitute an original of this Agreement.

Schedule-O Page - 144

IN WITNESS WHEREOF THE PARTIES HAVE EXECUTED AND DELIVERED THIS AGREEMENT AS OF THE DATE FIRST ABOVE WRITTEN.

THE COMMON SEAL OF SIGNED, SEALED AND DELIVERED CONCESSIONAIRE has been affixed For and on behalf of pursuant to the resolution passed by the SENIOR LENDERS by the Board of Directors of the Concessionaire at Lenders‟ Representative:

Its meeting held on the ...... day of...... 20...... hereunto affixed in the presence of ...... , Director, who has signed these Presents in token thereof and ...... , Company Secretary / Authorised Officer Who has countersigned the same in token thereof£2:

(Signature) (Signature) (Name) (Name) (Designation) (Designation) (Address) (Address) (Fax No.) (Fax No.) (E-mail address) (E-mail address)

SIGNED, SEALED AND SIGNED, SEALED AND DELIVERED DELIVERED For and on behalf of For and on behalf of ESCROW BANK by: THE AUTHORITY by:

(Signature) (Signature) (Name) (Name) (Designation) (Designation) (Address) (Address) (Fax No.) (Fax No.) (E-mail address) (E-mail address)

In the presence of:

1. 2.

£ To be affixed in accordance with the articles of association of the Concessionaire and the resolution passed by its Board of Directors. Schedule-O Page - 145

SCHEDULE-P (See Clause 27.2.1)

PANEL OF CHARTERED ACCOUNTANTS

1 Panel of Chartered Accountants

Pursuant to the provisions of Clause 27.2.1 of the Agreement, the Authority and the Concessionaire shall prepare a mutually agreed panel of 5 (five) reputable firms of Chartered Accountants having their registered offices in India (the “Panel of Chartered Accountants”). The criteria for preparing such Panel and the procedure to be adopted in this behalf shall be as set forth in this Schedule-P.

2 Invitation for empanelment

2.1 The Authority shall invite offers from all reputed firms of Chartered Accountants who fulfil the following eligibility criteria, namely:

(a) the firm should have conducted statutory audit of the annual accounts of at least one hundred companies registered under the Companies Act, 1956, including any re-enactment or amendment thereof, of which at least ten should have been public sector undertakings:

(b) the firm should have at least 5 (five) practising Chartered Accountants on its rolls, each with a minimum experience of ten years in the profession;

(c) the firm or any of its partners should not have been disqualified or black-listed by the Comptroller and Auditor General of India or the Authority; and

(d) The firm should have an office in the State or in an adjacent State with at least 2 (two) practising Chartered Accountants on its rolls in such State.

2.2 Interested firms meeting the eligibility criteria shall be required to submit a statement of their capability including the bio-data of all the practising Chartered Accountants on its rolls. In particular, each firm shall be required to furnish year-wise information relating to the names of all the companies with an annual turnover exceeding Rs. 25,00,00,000 (Rs. twenty five Crore) whose annual accounts were audited by such firm in any of the preceding 5 (five) Accounting Years.

3 Evaluation and selection

3.1 The information furnished by each firm shall be scrutinised and evaluated by the Authority and 1 (one) point shall be awarded for each annual audit of the companies Schedule-P Page - 146

specified in Paragraph 2.2 above. (For the avoidance of doubt and by way of illustration, a firm which has conducted audit of the annual accounts of any such company for 5(five) years shall be awarded 5 (five) points).

3.2 The Authority shall prepare a list of all the eligible firms along with the points scored by each such firm and 5 (five) firms scoring the highest points shall be identified and included in the draft Panel of Chartered Accountants.

4 Consultation with the Concessionaire

The Authority shall convey the aforesaid panel of firms to the Concessionaire for scrutiny and comments, if any. The Concessionaire shall be entitled to scrutinise the relevant records of the Authority to ascertain whether the selection of firms has been undertaken in accordance with the prescribed procedure and it shall send its comments, if any, to the Authority within 15 (fifteen) days of receiving the aforesaid panel.

5 Mutually agreed panel

5.1 The Authority shall, after considering all relevant factors including the comments, if any, of the Concessionaire, finalise and constitute a panel of 5 (five) firms which shall be deemed to be the mutually agreed Panel of Chartered Accountants.

5.2 After completion of every 5 (five) years from the date of preparing the mutually agreed Panel of Chartered Accountants, or such earlier period as may be agreed between the Authority and the Concessionaire, a new panel shall be prepared in accordance with the provisions of this Schedule-P.

Schedule-P Page - 147

Schedule-P Page - 148

SCHEDULE-Q (See Clause 32.4)

VESTING CERTIFICATE

1 The Governor of Rajasthan, represented by Additional Chief Secretary Public Works Department, Government of Rajasthan (the “Authority) refers to the Concession Agreement dated...... (the “ Agreement”) entered into between the Authority and ...... (the “Concessionaire”) for development and operation of Barmer - Sindari -Jalore section of State Highway -16 and Ahore- Bali- Mundra (Sanderao to Mundra) section of State Highway -16 (Total length: 178.00 Km) (the “Project”) on design, build, operate and transfer (the “DBOT”) basis on Annuity mode.

2 The Authority hereby acknowledges compliance and fulfilment by the Concessionaire of the Divestment Requirements set forth in Clause 32.1 of the Agreement on the basis that upon issue of this Vesting Certificate, the Authority shall be deemed to have acquired, and all title and interest of the Concessionaire in or about the Project shall be deemed to have vested unto the Authority, free from any encumbrances, charges and liens whatsoever.

3 Notwithstanding anything to the contrary contained hereinabove, it shall be a condition of this Vesting Certificate that nothing contained herein shall be construed or interpreted as waiving the obligation of the Concessionaire to rectify and remedy any defect or deficiency in any of the Divestment Requirements and/ or relieving the Concessionaire in any manner of the same.

Signed this...... day of ...... , 20 ...... at...... AGREED, ACCEPTED AND SIGNED, SEALED AND DELIVERED SIGNED

For and on behalf of for and on behalf of CONCESSIONAIRE AUTHORITY by: by:

(Signature) (Signature) (Name) (Name) (Designation) (Designation) (Address) (Address)

In the presence of:

1. 2.

Schedule-Q Page - 149

Schedule-Q Page - 150

SCHEDULE-R (See Clause 34.3.1)

SUBSTITUTION AGREEMENT

THIS SUBSTITUTION AGREEMENT is entered into on this the ...... day of ...... 20......

AMONGST

1 The Governor of Rajasthan, represented by Additional Chief Secretary, Public Works Department, Government of Rajasthan and having its principal offices at Jacob Road, Civil Lines, Jaipur-302006 (hereinafter referred to as the “Authority” which expression shall unless repugnant to the context or meaning thereof include its administrators, successors and assigns):

2 ...... Limited, a company incorporated under the provisions of the Companies Act, 2013 and having its registered office at ...... , (hereinafter referred to as the “Concessionaire” which expression shall unless repugnant to the context or meaning thereof include its successors and permitted assigns and substitutes);

3 ...... (insert name and particulars of Lenders‟ Representative) and having its registered office at ...... , acting for and on behalf of the Senior Lenders as their duly authorised agent with regard to matters arising out of or in relation to this Agreement (hereinafter referred to as the “Lenders Representative”, which expression shall unless repugnant to the context or meaning thereof include its successors and substitutes);

WHEREAS:

(A) The Authority has entered into a Concession Agreement dated ...... with the Concessionaire (the “Concession Agreement”) for development and operation of of Barmer -Sindari -Jalore section of State Highway -16 and Ahore- Bali- Mundra (Sanderao to Mundra) section of State Highway -16 (Total length: 178.00 Km) (the “Project”) on design, build, operate and transfer (the “DBOT”) basis on Annuity mode, and a copy of which is annexed hereto and marked as Annex-A to form part of this Agreement.

(B) Senior Lenders have agreed to finance the Project in accordance with the terms and conditions set forth in the Financing Agreements.

(C) Senior Lenders have requested the Authority to enter into this Substitution Agreement for securing their interests through assignment, transfer and substitution

Schedule-R Page - 151

of the Concession to a Nominated Company in accordance with the provisions of this Agreement and the Concession Agreement.

(D) In order to enable implementation of the Project including its financing, construction, operation and maintenance, the Authority has agreed and undertaken to transfer and assign the Concession to a Nominated Company in accordance with the terms and conditions set forth in this Agreement and the Concession Agreement.

NOW, THEREFORE, in consideration of the foregoing and the respective covenants and agreements set forth in this Agreement, the receipt and sufficiency of which is hereby acknowledged, and intending to be legally bound hereby, the Parties agree as follows:

1 DEFINITIONS AND INTERPRETATION

1.1 Definitions

In this Substitution Agreement, the following words and expressions shall, unless repugnant to the context or meaning thereof, have the meaning hereinafter respectively assigned to them:

“Agreement” means this Substitution Agreement and any amendment thereto made in accordance with the provisions contained in this Agreement;

“Financial Default” means occurrence of a material breach of the terms and conditions of the Financing Agreements or a continuous default in Debt Service by the Concessionaire for a minimum period of 3 (three) months;

“Lenders’ Representative” means the person referred to as the Lenders‟ Representative in the foregoing Recitals;

“Nominated Company” means a company, incorporated under the provisions of the Companies Act, 1956, including any re-enactment or amendment thereof, selected by the Lenders‟ Representative, on behalf of Senior Lenders, and proposed to the Authority for assignment/transfer of the Concession as provided in this Agreement;

“Notice of Financial Default” shall have the meaning ascribed thereto in Clause 3.2.1; and

“Parties” means the parties on this Agreement collectively and “Party” shall mean any of the Parties to this Agreement individually.

Schedule-R Page - 152

1.2 Interpretation

1.2.1 References to Lenders‟ Representative shall, unless repugnant to the context or meaning thereof, mean references to the Lenders‟ Representative, acting for and on behalf of Senior Lenders.

1.2.2 References to Clauses are, unless stated otherwise, references to Clauses of this Agreement.

1.2.3 The words and expressions beginning with capital letters and defined in this Agreement shall have the meaning ascribed thereto herein and the words and expressions used in this Agreement and not defined herein but defined in the Concession Agreement shall, unless repugnant to the context , have the meaning ascribed thereto in the Concession Agreement.

1.2.4 The rules of interpretation stated in Clauses 1.2, 1.3 and 1.4 of the Concession Agreement shall apply, mutatis mutandis, to this Agreement

2 ASSIGNMENT

2.1 Assignment of rights and title

The Concessionaire hereby agrees to assign the rights, title and interest in the Concession to, and in favour of, the Lenders‟ Representative pursuant to and in accordance with the provisions of this Agreement and the Concession Agreement by way of security in respect of financing by the Senior Lenders under the Financing Agreements.

3 SUBSTITUTION OF THE CONCESSIONAIRE

3.1 Rights to substitution

3.1.1 Pursuant to the rights, title and interest assigned under Clause 2.1, the Lenders‟ Representative shall be entitled to substitute the Concessionaire by a Nominated Company under and in accordance with the provisions of this Agreement and the Concession Agreement.

3.1.2 The Authority hereby agrees to substitute the Concessionaire by endorsement on the Concession Agreement in favour of the Nominated Company selected by the Lenders‟ Representative in accordance with this Agreement. For the avoidance of doubt, the Senior Lenders or the Lenders‟ Representative shall not be entitled to operate and maintain the Project as Concessionaire either individually or collectively.

3.2 Substitution upon occurrence of Financial Default

Schedule-R Page - 153

3.2.1 Upon occurrence of a Financial Default, the Lenders‟ Representative may issue a notice to the Concessionaire (the “Notice of Financial Default”) along with particulars thereof, and send a copy to the Authority for its information and record. A Notice of Financial Default under this Clause 3 shall be conclusive evidence of such Financial Default and it shall be final and binding upon the Concessionaire for the purposes of this Agreement.

3.2.2 Upon issue of a Notice of Financial Default hereunder, the Lenders‟ Representative may, without prejudice to any of its rights or remedies under this Agreement or the Financing Agreements, substitute the Concessionaire by a Nominated Company in accordance with the provisions of this Agreement.

3.2.3 At any time after the Lenders‟ Representative has issued a Notice of Financial Default, it may by notice require the Authority to suspend all the rights of the Concessionaire and undertake the operation and maintenance of the Project in accordance with the provisions of Article 30 of the Concession Agreement, and upon receipt of such notice, the Authority shall undertake Suspension under and in accordance with the provisions of the Concession Agreement .The aforesaid Suspension shall be revoked upon substitution of the Concessionaire by a Nominated Company, and in the event such substitution is not completed within 180 (one hundred and eighty) days from the date of such Suspension, the Authority may terminate the Concession Agreement forthwith by issuing a Termination Notice in accordance with the provisions of the Concession

Agreement; provided that upon written request from the Lenders‟ Representative and the Concessionaire, the Authority may extend the aforesaid period of 180 (one hundred and eighty) days by a period not exceeding 90 (ninety) days. For the avoidance of doubt, the Authority expressly agrees and undertakes to terminate the Concession Agreement forthwith, upon receipt of a written request from the Lenders‟ Representative at any time after 240 (two hundred and forty) days from the date of Suspension hereunder.

3.3 Substitution upon occurrence of Concessionaire Default

3.3.1 Upon occurrences of a Concessionaire Default, the Authority shall by a notice inform the Lenders‟ Representative of its intention to issue a Termination Notice and grant 15 (fifteen) days time to the Lenders‟ Representative to make a representation, stating the intention to substitute the Concessionaire by a Nominated Company.

3.3.2 In the event that the Lenders‟ Representative makes a representation to the Authority within the period of 15 (fifteen) days specified in Clause 3.3.1, stating that it intends to substitute the Concessionaire by a Nominated Company, the Lenders‟ Representative shall be entitled to undertake and complete the substitution of the Concessionaire by a Nominated Company in accordance with the provisions of this Agreement within a period of 180 (one hundred and eighty) days from the date of such representation, and the Authority shall either withhold Termination or undertake Suspension for the aforesaid period of 180 (one hundred and eighty) days; provided that upon written request from the Lenders‟ Representative and the Concessionaire, the Authority shall extend the aforesaid Schedule-R Page - 154

period of 180 (one hundred and eighty) days by a period not exceeding 90 (ninety) days; provided further that the Lenders‟ Representative may at any time withdraw its representation hereunder and upon such withdrawal, the Authority may terminate this Agreement in accordance with the provisions hereof.

3.4 Procedure for substitution

3.4.1 The Authority and the Concessionaire hereby agree that on or after the date of Notice of Financial Default or the date of representation to the Authority under Clause 3.3.2, as the case may be, the Lenders‟ Representative may, without prejudice to any of the other rights or remedies of the Senior Lenders, invite, negotiate and procure offers, either by private negotiations or public auction or tenders for the take over and transfer of the Project including the Concession to the Nominated Company upon such Nominated Company‟s assumption of the liabilities and obligations of the Concessionaire towards the Authority under the Concession agreement and towards the Senior Lenders under the Financing Agreements.

3.4.2 To be eligible for substitution in place of the Concessionaire, the Nominated Company shall be required to fulfil the eligibility criteria that were laid down by the Authority for shortlisting the qualified applicants for award of the Concession; provided that the Lenders‟ Representative may represent to the Authority that all or any of such criteria may be waived in the interest of the Project, and if the Authority determines that such waiver shall not have any material adverse effect on the Project, it may waive all or any of such eligibility criteria.

3.4.3 Upon selection of a Nominated Company, the Lenders‟ Representative shall request the Authority to:

(a) accede to transfer to the Nominated Company the right to construct, operate and maintain the Project in accordance with the provisions of the Concession Agreement;

(b) endorse and transfer the Concession to the Nominated Company, on the same terms and conditions, for the residual Concession Period; and

(c) enter into a Substitution Agreement with the Lenders‟ Representative and the Nominated Company on the same terms as are contained in this Agreement.

3.4.4 If the Authority has any objection to the transfer of Concession in favour of the Nominated Company in accordance with this Agreement, it shall within 15 (fifteen) days from the date of proposal made by the Lenders‟ Representative, give a reasoned order after hearing the Lenders‟ Representative. If no such objection is raised by the Authority, the Nominated Company shall be deemed to have been accepted. The Authority shall thereupon transfer and endorse the Concession within 15 (fifteen) days of its acceptance/ deemed acceptance of the Nominated Company; provided that in the event of such Schedule-R Page - 155

objection by the Authority, the Lenders‟ Representative may propose another Nominated Company whereupon the procedure set forth in this Clause 3.4 shall be followed for substitution of such Nominated Company in place of the Concessionaire.

3.4.5 The transfer of Concession hereunder to a Nominated Company may, notwithstanding anything to the contrary in this Agreement and the Concession Agreement, be undertaken by transfer of no less than 75% (seventy five percent) of the equity of the Concessionaire to the Nominated Company, and upon such transfer hereunder, the Concessionaire shall be deemed to be the Nominated Company under and in accordance with the provisions of this Agreement and the Concession Agreement.

3.5 Selection to be binding

The decision of the Lenders‟ Representative and the Authority in selection of the Nominated Company shall be final and binding on the Concessionaire. The Concessionaire irrevocably agrees and waives any right to challenge the actions of the Lenders‟ Representative or the Senior Lenders or the Authority taken pursuant to this Agreement including the transfer/assignment of the Concession in favour of the Nominated Company. The Concessionaire agrees and confirms that it shall not have any right to seek revaluation of assets of the Project or the Concessionaire‟s shares. It is hereby acknowledged by the Parties that the rights of the Lenders‟ Representative are irrevocable and shall not be contested in any proceedings before any court or Authority and the Concessionaire shall have no right or remedy to prevent, obstruct or restrain the Authority or the Lenders‟ Representative from effecting or causing the transfer by substitution and endorsement of the Concession as requested by the Lenders‟ Representative.

4 PROJECT AGREEMENTS

4.1 Substitution of Nominated Company in Project Agreements

The Concessionaire shall ensure and procure that each Project Agreement contains provisions that entitle the Nominated Company to step into such Project Agreement, in its discretion, in place and substitution of the Concessionaire in the event of such Nominated Company‟s assumption of the liabilities and obligations of the Concessionaire under the Concession Agreement.

5 TERMINATION OF CONCESSION AGREEMENT

5.1 Termination upon occurrence of Financial Default

At any time after issue of a Notice of Financial Default, the Lenders‟ Representative may by a notice in writing require the Authority to terminate the Concession Agreement

Schedule-R Page - 156

forthwith, and upon receipt of such notice, the Authority shall undertake Termination under and in accordance with the provisions of Article 31 of the Concession Agreement.

5.2 Termination when no Nominated Company is selected

In the event that no Nominated Company acceptable to the Authority is selected and recommended by the Lenders‟ Representative within the period of 180 (one hundred and eighty) days or any extension thereof as set forth in Clause 3.3.2, the Authority may terminate the Concession Agreement forthwith in accordance with the provisions thereof.

5.3 Realisation of Debt Due

The Authority and the Concessionaire hereby acknowledge and agree that, without prejudice to their any other right or remedy, the Lenders‟ Representative is entitled to receive from the Concessionaire, without any further reference to or consent of the Concessionaire, the Debt Due upon Termination of the Concession Agreement. For realisation of the Debt Due, the Lenders‟ Representative shall be entitled to make its claim from the Escrow Account in accordance with the provisions of the Concession Agreement and the Escrow Agreement.

6 DURATION OF THE AGREEMENT

6.1 Duration of the Agreement

This Agreement shall come into force from the date hereof and shall expire at the earliest to occur of the following events:

(a) termination of the Agreement; or

(b) no sum remains to be advanced and no sum is outstanding to the Senior Lenders, under the Financing Agreements.

7 INDEMNITY

7.1 General indemnity

7.1.1 The Concessionaire will indemnify, defend and hold the Authority and the Lenders‟ Representative harmless against any and all proceedings, actions and third party claims for any loss, damage, cost and expense of whatever kind and nature arising out of any breach by the Concessionaire of any of its obligations under this Agreement or on account of failure of the Concessionaire to comply with Applicable Laws and Applicable Permits.

Schedule-R Page - 157

7.1.2 The Authority will indemnify, defend and hold the Concessionaire harmless against any and all proceedings, actions and third party claims for any loss, damage, cost and expense arising out of failure of the Authority to fulfil any of its obligations under this Agreement, materially and adversely affecting the performance of the Concessionaire‟s obligations under the Concession Agreement or this Agreement, other than any loss, damage, cost and expense, arising out of acts done in discharge of their lawful functions by the Authority, its officers, servants and agents.

7.1.3 The Lenders‟ Representative will indemnify, defend and hold the Concessionaire harmless against any and all proceedings, actions and third party claims for any loss, damage , cost and expense arising out of failure of the Lenders‟ Representative to fulfil its obligations under this Agreement, materially and adversely affecting the performance of the Concessionaire‟s obligations under the Concession Agreement, other than any loss, damage, cost and expense, arising out of acts done in discharge of their lawful functions by the Lenders‟ Representative, its officers, servants and agents.

7.2 Notice and contest of claims

In the event that any Party hereto receives a claim from a third party in respect of which it is entitled to the benefit of an indemnity under Clause 7.1 or in respect of which it is entitled to reimbursement (the “Indemnified Party”), it shall notify the other Party responsible for indemnifying such claim hereunder (the “ Indemnifying Party”) within 15 (fifteen) days of receipt of the claim and shall not settle or pay the claim without the prior approval of the Indemnifying Party, such approval not to be unreasonably withheld or delayed. In the event that the Indemnifying Party wishes to contest or dispute the claim, it may conduct the proceedings in the name of the Indemnified Party and shall bear all costs involved in contesting the same. The Indemnified Party shall provide all cooperation and assistance in contesting any claim and shall sign all such writings and documents as the Indemnifying Party may reasonably require.

8 DISPUTE RESOLUTION

8.1 Dispute resolution

8.1.1 Any dispute, difference or claim arising out of or in connection with this Agreement which is not resolved amicably shall be decided by reference to arbitration to a Board of Arbitrators comprising one nominee each of the Authority, Concessionaire and the Lenders‟ Representative. Such arbitration shall be held in accordance with the Rules of Arbitration of the International Centre for Alternative Dispute Resolution, New Delhi (the “Rules”) or such other rules as may be mutually agreed by the Parties, and shall be subject to provisions of the Arbitration and Conciliation Act, 1996.

Schedule-R Page - 158

8.1.2 The Arbitrators shall issue a reasoned award and such award shall be final and binding on the Parties. The place of arbitration shall be the capital of the State and the language of arbitration shall be English.

9 MISCELLANEOUS PROVISIONS

9.1 Governing law and jurisdiction

This Agreement shall be construed and interpreted in accordance with and governed by the laws of India, and the courts in the State shall have jurisdiction over all matters arising out of or relating to this Agreement.

9.2 Waiver of sovereign immunity

The Authority unconditionally and irrevocably:

(a) agrees that the execution, delivery and performance by it of this Agreement constitute commercial acts done and performed for commercial purpose;

(b) agrees that, should any proceedings be brought against it or its assets, property or revenues in any jurisdiction in relation to this Agreement or any transaction contemplated by this Agreement, no immunity (whether by reason of sovereignty or otherwise) from such proceedings shall be claimed by or on behalf of the Authority with respect to its assets;

(c) waives any right of immunity which it or its assets, property or revenues now has, may acquire in the future or which may be attributed to it in any jurisdiction; and

(d) consents generally in respect of the enforcement of any judgement or award against it in any such proceedings to the giving of any relief or the issue of any process in any jurisdiction in connection with such proceedings (including the making, enforcement or execution against it or in respect of any assets, property or revenues whatsoever irrespective of their use or intended use of any order or judgement that may be made or given in connection therewith).

9.3 Priority of agreements

In the event of any conflict between the Concession Agreement and this Agreement, the provisions contained in the Concession Agreement shall prevail over this Agreement.

9.4 Alteration of terms

Schedule-R Page - 159

All additions, amendments, modifications and variations to this Agreement shall be effectual and binding only if in writing and signed by the duly authorised representatives of the Parties.

9.5 Waiver 9.5.1 Waiver by any Party of a default by another Party in the observance and performance of any provision of or obligations under this Agreement:

(a) shall not operate or be construed as a waiver of any other or subsequent default hereof or of other provisions of or obligations under this Agreement;

(b) shall not be effective unless it is in writing and executed by a duly authorised representative of the Party; and

(c) shall not affect the validity or enforceability of this Agreement in any manner.

9.5.2 Neither the failure by either Party to insist on any occasion upon the performance of the terms, conditions and provisions of this Agreement or any obligation thereunder nor time or other indulgence granted by a Party to another Party shall be treated or deemed as waiver of such breach or acceptance of any variation or the relinquishment of any such right hereunder.

9.6 No third party beneficiaries

This Agreement is solely for the benefit of the Parties and no other person or entity shall have any rights hereunder.

9.7 Survival

9.7.1 Termination of this Agreement:

(a) shall not relieve the Parties of any obligations hereunder which expressly or by implication survive termination hereof; and

(b) except as otherwise provided in any provision of this Agreement expressly limiting the liability of either Party, shall not relieve either Party of any obligations or liabilities for loss or damage to the other Party arising out of or caused by acts or omissions of such Party prior to the effectiveness of such termination or arising out of such termination

Schedule-R Page - 160

9.7.2 all obligations surviving the cancellation, expiration or termination of this Agreement shall only survive for a period of 3 (three) years following the date of such termination or expiry of this Agreement.

9.8 Severability

If for any reason whatever any provision of this Agreement is or becomes invalid, illegal or unenforceable or is declared by any court of competent jurisdiction or any other instrumentality to be invalid, illegal or unenforceable, the validity, legality or enforceability of the remaining provisions shall not be affected in any manner, and the Parties will negotiate in good faith with a view to agreeing to one or more provisions which may be substituted for such invalid, unenforceable or illegal provisions, as nearly as is practicable to such invalid, illegal or unenforceable provision. Failure to agree upon any such provisions shall not be subject to dispute resolution under Clause 8 of this Agreement or otherwise.

9.9 Successors and assigns This Agreement shall be binding on and shall inure to the benefit of the Parties and their respective successors and permitted assigns.

9.10 Notices

All notices or other communications to be given or made under this Agreement shall be in writing, shall either be delivered personally or sent by courier or registered post with an additional copy to be sent by facsimile or e-mail. The address for service of each Party, its facsimile number and e-mail address are set out under its name on the signing pages hereto. A notice shall be effective upon actual receipt thereof, save that where it is received after 5.30 (five thirty) p.m. on any day, or on a day that is a public holiday, the notice shall be deemed to be received on the first working day following the date of actual receipt. Without prejudice to the foregoing, a Party giving or making a notice or communication by facsimile or e-mail shall promptly deliver a copy thereof personally, or send it by courier or registered post to the addressee of such notice or communication. It is hereby agreed and acknowledged that any Party may by notice change the address to which such notices and communications to it are to be delivered or mailed. Such change shall be effective when all the Parties have notice of it.

9.11 Language All notices, certificates, correspondence and proceedings under or in connection with this Agreement shall be in English.

Schedule-R Page - 161

9.12 Authorised representatives

Each of the Parties shall by notice in writing designate their respective authorised representatives through whom only all communications shall be made. A Party hereto shall be entitled to remove and/or substitute or make fresh appointment of such authorised representative by similar notice.

9.13 Original Document This Agreement may be executed in three counterparts, each of which when executed and delivered shall constitute an original of this Agreement.

Schedule-R Page - 162

IN WITNESS WHEREOF THE PARTIES HAVE EXECUTED AND DELIVERED THIS AGREEMENT AS OF THE DATE FIRST ABOVE WRITTEN

THE COMMON SEAL OF SIGNED, SEALED AND DELIVERED CONCESSIONAIRE has been affixed for and on behalf of THE AUTHORITY pursuant to the resolution passed by the by: Board of Directors of the Concessionaire at its meeting held on the...... day of ...... 20 ...... hereunto affixed in the presence of...... Director, who has Signed these presents in token thereof and...... , Company Secretary/ Authorised Officer who has countersigned the same in Token therefof£3:

(Signature) (Signature) (Name) (Name) (Designation) (Designation) (Address) (Address) (Fax No.) (Fax No.) (E-mail address) (E-mail address)

SIGNED, SEALED AND DELIVERED

For and on behalf of SENIOR LENDERS by the Lenders‟ Representative

(Signature) (Name) (Designation) (Address) (Fax No.) (E-mail address)

In the presence of: 1. 2.

£To be affixed in accordance with the articles of association of the Concessionaire and the resolution passed by its Board of Directors. Schedule-R Page - 163

Schedule-R Page - 164

SCHEDULE-S

Environmental Management Plan & Environmental Monitoring Plan

Road Specific Environmental Management and Monitoring Plans

Page - 165 166

ENVIRONMENTAL MONITORING PLAN FOR JALORE-BARMER (SH-16)

Env. Project Stage Parameters Method/ Location Frequency and Standards Approximate Implementation Supervision Indicators Guidelines Duration cost (Rs) Air Quality Construction PM 10 PM2.5 High volume 2 sampling per km of built Monthly Air quality 36x9000 =Rs Concessionaire RPWD /CSC stage SO2, NOX, CO sampler to be up area during active standard by 324,000 through approved located 50 m from construction in built up CPCB monitoring agency the selected area: (Barmer 4, Chawa 2, locations in the Sindari, Madwala 2, downwind Ratuya 2, direction. Use Dangara 2) per month for method specified by 3 months CPCB Batching and hotmix plants sampling part of SPCB annual renewal of permits Operation Representative sample 24 hr continuous, Air quality 3X9000x3 RPWD through RPWD stage each for residential, 3/year for 1 year standard by =Rs 81,000 approved commercial and (Total 3 times in a CPCB monitoring agency sensitive/forest area year baring (3 Locations)- monsoon)

Water Quality Construction Ground water: Grab sample Groundwater at Monthly for 3 years, Water quality 36x 5000x3x2 Concessionaire RPWD /SC stage (IS: 10500:1991) collected from Construction Camps 3 camps with 2 standard by = Rs 1,080,000 through approved and source and analyse borewells each CPCB monitoring agency Operation Surface water as per standard Groundwater at 2 3/year for 1 year Water quality 3X4X5000 RPWD through RPWD stage criteria for methods for locations and surface standard by =Rs 45, 000 approved freshwater examination of water at 2 locations CPCB monitoring agency classification water and wastewater Noise levels Construction Equivalent Noise IS:4954-1968 as Same as air quality National 36x3000x Concessionaire RPWD/CSC stage levels on dB (A) adopted by CPCB Ambient Noise =Rs.108,000 through approved scale for day and for Identified Study Standard monitoring agency Operation night Area Built-up areas 2/year for 1 year specified in 2x3000x48 RPWD through RPWD stage CPCB/IS:4954- Environment =Rs 288,000 approved 1968Using Noise Protection Act, monitoring agency level meter 1986

Soil Quality Construction NPK (ICAR As specified by the Camp, dumping/storage Once during whole ICAR standard 14,000 Concessionaire RPWD/CSC Stage standard ) and site engineer RPWD areas and HMP sites construction stage through approved heavy metals / supervision (2 locations) monitoring agency consultant Operation Oil and grease At oil spillage locations Once for the first CPCB 28000 RPWD through RPWD stage and other probable soil year of operation standard approved agency contamination location Soil Erosion Construction Visual check for Throughout the Project After first rain Visual Checks Included in Concessionaire RPWD/CSC Stage Soil erosion and corridor especially at engineering cost Operation siltation River banks, bridge Once during Visual Checks Routine Engineering Team of RPWD Stage locations and river operation of 1st year engineering training structures work

Page - 166

167

Env. Project Stage Parameters Method/ Location Frequency and Standards Approximate Implementation Supervision Indicators Guidelines Duration cost (Rs) Drainage Construction Visual Checks Throughout the Project Once in a year Included in Concessionaire' RPWD/CSC None Specific Congestion stage corridor especially before rainy season engineering cost Operation probable drainage Once in a year Routine RPWD Stage congestion areas before rainy season None Specific engineering work Borrow Construction Visual Checks IRC guidelines Borrow areas to be Once in a month IRC guidelines Part of the Concessionaire RPWD/CSC Areas Stage operated + Concessionaire‟ with approval from Compliance s quote RPWD Operation Visual Checks Rehabilitation as Closed Borrow Areas Quarterly for 1 year conditions of RPWD Stage per IRC guidelines SEIAA Construction Construction Hygiene, Rapid audit as per Construction Sites and Quarterly during IRC guidelines Part of the Concessionaire RPWD/CSC Sites and stage drainage Medical reporting format Camp construction period regular with approval from Labor Facilities Etc. monitoring RPWD, RPWD Camp Construction Surveillance monitoring of trees felling Throughout the Project During site As suggested Compensatory: Compensatory: RPWD/Local Forest Tree Plantation Stage section clearance in by Forest RPWD Departments construction phase Dept. Additional Plantation: Additional Concessionaire Operation Audit for survival rate of trees plantation Throughout the Project Once in a year for Plantation: The Independent Engineer will be stage section years Provisional sum responsible for monitoring up to the under Civil Cost Defect Liability Period in any particular stretch. After this period RPWD through Concessionaire will be responsible for monitoring Record of Construction Type, nature and cause of accidents. Throughout the stretch occurrence of As suggested Part of the Concessionaire RPWD/CSC Accident Stage Methodology as suggested by CSC and including construction accidents by PMC/SC regular approved by RPWD sites, crusher, diversions, monitoring HMP, earthwork, demolition site etc. Operation Throughout the stretch occurrence of Road Safety unit of RPWD with - - stage accidents support from local police Wildlife Construction Nature and cause of collision, season, Animal crossing locations occurrence of As suggested Civil Cost Concessionaire RPWD/CSC Vehicle Stage Month and time of collision. as identified in IEE collision by forest Collisions Operation 1. Success of road furnitures viz. rumble Animal crossing Random all through department Operation and RPWD in coordination with forest stage strip, cautionary signages etc. designed Locations as identified in the year Maintenance department or through an for safe movement IEE Cost specialized wildlife expert team 2. Nature and cause of collision, season, Month and time of collision 3. Monitoring of movement path based on informations available with forest department and local people. Monitoring Costs Construction Phase: INR 1.526 Million RPWD: Rajasthan State Public Works Department, NPK: Nitrogen, Phosphorous and Potassium, CSC: Construction Supervision Consultant, PMC: Project Management Consultant, IEE: Initial Environmental Examination, IRC: Indian Road Congress, SEIAA: State Environmental Impact Assessment Authority, CPCB: Central Pollution Control Board, IS: Indian Standard Environment Management Plan for Ahore –Bali- Mundara

Environmental Remedial Measure Reference to laws Location Monitoring Monitoring Mitigation Institutional Responsibility Issue/ Component /guidelines indicators Methods Costs Implementation Supervision A. Pre-construction and Design Stage Page - 167

168

1. Alignment 1.1 Pavement  Constructionof concrete pavementin habitat Design requirement All habitat Design of both Review of Included in Design PWD, damage and inadequate areas considering alignment level and drainage. areas throughout cross & side drains detail design construction Consultant RAJASTHAN drainage provisions in  Raiseroadlevelabove the nearby areas with the alignment ,no. of slab/box documents cost (SQC) habitat areas provision of adequate side drains to evacuate culverts & drawings the rain water an domestic discharges (drained ,no & size of by habitats occasionally to prevent damage to Hume pipes road and rain water entry to habitats‟ houses.  Provisionofadequateno.ofcross drainage structures based on drainage pattern around the alignment

1.2 Safety along  Make provisionsof crash barriers at accident Design requirement Places where No. of accident & Field Included in Design Consultant PWD, the proposed alignment prone areas as identified in the road safety height of Vehicle collision observation construction RAJASTHAN studies embankment is ,interview of cost (SQC)  Provision of rumblestripsinhabitat areas to more than 3.0 m. locals regulate speed.  Provision of retro-reflective warning sign boards nears school, hospital,religiousplaces and forests areas  Provision of proper side-walks /pedestrian zone along the road near habitat areas, school, hospital, religiousplacesand forests  Compliancewithnormsspecifiedin IRC codes for state highway for curvature and grading  Provision of safety kerb at all bridges  The design should attempt to equalize cut and fill.  Minimize the cutting in hill areas. Incorporate slope stabilization measurestopreventanyland slide situation.

2. Natural Hazards 2.1 Protection for  Design considering relevant IRC guidelines for Throughout the Incorporation of Review of Project Design Consultant PWD, damage from earthquakes in bridges stretch IRC guidelines for bridge design preparation RAJASTHAN Earthquake earthquake in bridge cost (SQC) design

Environmental Remedial Measure Reference to laws Location Monitoring Monitoring Mitigation Institutional Responsibility Issue/ Component /guidelines indicators Methods Costs Implementation Supervision

Page - 168

169

2.2 Protection of Raiseembankmentheightabovethe IRC:34 All the existing Design of both Included in Design Consultant PWD, road embankment in HFL levels in the flood prone areas. Recommendations for culverts/bridges. cross & side drains construction RAJASTHAN Flood prone Areas Provision of adequate balancing culverts. road construction in , no. of slab/box cost (SQC) Improvement in existing culverts/ Bridges waterlogged area and culverts ,no & size to increase their carrying capacity. IRC: 75 and of Hume pipes MORT&H guidelines for Design of High Embankments 3. Shifting of utility structures 3.1 Disruption of All telephone and electrical poles/wires and Project Throughout Utility shifting plan Interaction Included in Concessionaire/Cont PWD, utility services to underground cables should be shifted before requirement the corridor with concerned construction ractor r/SQ C RAJASTHAN local community start of construction Complaints from utility . (SQC)/CSC Necessary permission and payments local people authorities and should be made to relevant utility service local public agencies to allow quick shifting and restoration Status of local utility of utility services services Local people must be informed through appropriate means about the time of shifting of utility structures and potential disruption of services if any 4. Eccentric widening of road on selected green tunnels 4.1 Minimize the Green avenues where old trees are located on Location of Inventory of trees to Overlay of Part of design Design Consultant PWD, number of old trees both sides will be preserved where to the extent Project requirement green tunnels be felled green RAJASTHAN that will be cleared possible through minor geometric re-alignment or along the project tunnels and (SQC)/CSC eccentric widening particularlt where the existing road where existing PWD RoW is >=35 m, these sections are as eccentric PWD ROW follow: i) 15/000-19/000, ii) 21/000-21/400, iii) widening is 21/600-21/800, iv) 24/400-24/600, v) 25/200- possible on 27/600 PWD land

B. Construction Stage 1. Preparatory Activities Preparatory . Submit appointment letter and resume of the Project requirem ent All Contractors Approvals, PMC Part Concessionaire/Cont RPWD /CSC activities Concessionaire‟s/Contractor‟s Environmental and sub- attendance accompplish construction ractor / Focal Person (EFP) to PMU contractors ment report cost for RPWD/utility . EFP will engage PMC Environment Specialist Concessionai company and PMU Safeguard Officer-Environment to a re/Contractor meeting to discuss in detail the EMP, seek and PMC clarification and recommend corresponding Contract revisions if necessary . EFC will prepare Contractors Environmental Implementation Plan based on the approved EMP, EMOP, and agreements reach during the meeting with PMC-ES and PMU-SOE . request PMC-ES copy of monthly monitoring formats and establish deadlines for submission. . EFC will submit for PMC-ES approval an action plan to secure all permits and approvals needed to be secured during construction stage which include but not limited to: i) operation of crushers and hot mix plants, ii) transport and storage of hazardous materials (e.g. fuel, lubricants, explosives), iii) waste disposal sites, iv) temporary storage location, iv) water use, and v) emission compliance of all vehicles. Arrangements to link with government health Page - 169 programs on hygiene, sanitation, and prevention of communicable diseases will also be included in the action plan. 170

Site induction . No works will be initiated by the Project requirem ent All Contractors Approvals, PMC Part Concessionaire/Cont RPWD /CSC Concessionaire/Contractor until the site and sub- attendance accompplish construction ractor / induction training is carried out by the PMC contractors ment report cost for RPWD/utility Site induction training includes but not limited Concessionai company to: i) discussion and review of EMP and EMoP re/Contractor detailing how specific environmental risks and PMC associated with their Scope of Work will be Contract managed legal compliance, inspection and audits, and progress tracking and reporting; ii) environmental training and awareness needs shall be determined and documented via a training needs analysis prior to commencement; iii) Health and Safety Awareness Course, which details general environmental awareness and specific performance requirements expected on site; and iv) GRM. 2. Air Quality

2.1 Dust Generation Transport, loading and unloading of loose and MORT&H Along major PM10 level Standards Included in Concessionaire/Contr PWD, due to construction fine materials through covered vehicles. Specifications for habitation: measurements Dust CPCB project cost. actor RAJASTHAN activities and Paved approach roads. Road and Bridge Falna Chauraha, pollution or methods Estimated (SQC)/CSC transport, storage and Storage areas to be located downwind of the works Kamal Vihar, complain of locals Observations cost. handling of habitation area. Air (P and CP) Act Nimbeshwarnat Public construction Water spraying on earthworks, unpaved 1981and Central h, Paryawar consultation 3,230 materials haulage roads and other dust prone Motor and Vehicle Circle, Falna, truckloads areas. Act 1988 Falna Gaon, water@INR Provision of PPEs to workers. Shri Sela, Bali, 1,000= Radawa, Kot INR Baliya, 3,230,000 Mundara

Borrow areas and crushers are 2.2 Emission of air Regular maintenanceof machinery and The Air (Prevention Amonitoredsphalt mixing Monitoring of Standards Included in Concessionaire/Contr PWD, pollutants (HC, equipment. and Control of pannuallylants, by ambient air quality CPCB project cost actor RAJASTHAN SO2, NOX, CO etc) Batching, asphalt mixing plants and Pollution) Act, cSPCBrushe rs, DG & methods (SQC)/CSC from vehicles due crushersat downwind(1km) direction 1981(Amended sets locations checking PUC to traffic congestion from the nearest settlement. 1987) and Rules certificates and use of equipment Only crusherslicensedby the PCB 1982 and shall be used machinery DG sets with stacks of adequate height and use of low sulphur diesel as fuel. Ambient air quality monitoring Follow traffic management plan as given in Section 8. 3. Noise

Page - 170

171

Environmental Remedial Measure Reference to laws Location Monitoring Monitoring Mitigation Institutional Responsibility Issue/ Component /guidelines indicators Methods Costs Implementation Supervision 3.1 Noise from All equipment to be timely serviced and Legal requirement Community Noise levels As per 320 units Concessionaire/Contra PWD, construction vehicle, properly maintained. Noise Pollution areas of Falna Measurements in Noise rule, @3x3 ctor RAJASTHAN equipment and Bottlenecks to be removed. (Regulation and (2.5kmm), Bali built-up areas: 2000 movable noise (SQC)/CSC machinery. Construction equipment and machinery to be Control) Rules, 2000 (1.5 km), and shields@INR fitted with silencers and amendments Mundra (1.2km) Falna Chauraha, Consultation 15,000 = INR and maintained properly. thereof Kamal Vihar, with local 4,800,000 Only IS approved equipmentshall be usedfor + Nimbeshwarnath, people construction activities. Clause No 501.8.6. Paryawar Circle, Timing of noisy construction activities shall MORT&H Falna, Falna Gaon, be done during night time and Specifications for Shri Sela, Bali, weekends near schools and selected suitable Road and Bridge Radawa, Kot Baliya, times near temples when there works Mundara. are no visitors, concurrent noisy operations may be separatedtoreduce thetotal noise generated, and if possible re-route Complaints from traffic during construction to avoid the local people accumulationofnoisebeyond standards. Else provision of temporary noisebarrier at sensitive locations or near sources. Timeregulationnearresidential, built upand forest areas construction shallberestrictedtodaylight hours. Initiation ofmultilayered plantation, to serve as mitigation option for operation phase Honkingrestrictions near sensitive areas PPEs to workers Noise monitoring as per EMoP.

4. Land and Soil 4.1 Land use Non-agricultural areas to be used as borrow Project requirement Throughout the Borrow pit Review Included in Concessionaire/Contra PWD, Change and Loss of areas to the extent possible. Project section and locations borrow area construction ctor RAJASTHAN productive/top soil If using agricultural land, top soil to be borrow areas plan, site visits cost (SQC)/CSC preserved and laid over either on the Top soil storage area embankment slope for growing vegetation to protect soil erosion.

Page - 171

172

Environmental Remedial Measure Reference to laws Location Monitoring Monitoring Mitigation Institutional Responsibility Issue/ Component /guidelines indicators Methods Costs Implementation Supervision 4.2 Slope failure Bio-turfing of embankments to protect IRC: 56 -1974 Throughout the Occurrence of Review of Included in Design consultant PWD, and Soil erosion slopes. recommended entire Project road slope failure or design Construction and RAJASTHAN due to Construction Slope protection by providing frames, dry stone practice for treatment especially along erosion issues documents and cost Concessionaire/Contra (SQC)/CSC activities, pitching, masonry retaining walls, planting of of embankment slopes hilly areas site ctor earthwork, and cut and grass and trees. for erosion control observation fill, stockpiles The side slopes of all cut and fill areas will Clause No. etc. be graded and covered with stone pitching,grass 306 and 305.2.2 and shrub as per design MORT&H specifications.Careshouldbe taken Specifications for thattheslopegradient shall not be greater than Road and Bridge 2:1. works Guidelines IX The earth stockpiles to be providedwith gentle for Soil erosion slopes to prevent soil erosion.

4.3 Borrow area Non-productive, barren lands, upland IRCGuidelines Borrow sites Existence of Review of Included in Design consultant PWD, management shall be used for borrowing earth with the on borrow areas and Location based borrow areas in design Construction and Contractor, RAJASTHAN necessary permissions/consents. for quarries on F/S: i) stone inappropriate documents and cost (SQC)/CSC Depths of borrow pits to be regulated and sides (Environmental crusher, 225/0 unauthorized site not steeper than 25%. ProtectionAct chainage, 7.0km locations. observation Topsoil to be stockpiled and protected for use at and Rules, 1986; lead to Project, ii) the rehabilitation stage. Water Act, Air Act) stone crusher, Poor borrow area Transportation of earth materials through + Clause No. 225/10, management covered vehicles. 305.2.2 MORT&H , practices. IRC recommended practice for borrow pits Specifications for 38kms lead, iii) (IRC 10: 1961). Road and Bridge borrow area, Incidents of Borrow areas not to be dug continuously. works Guidelines V 225/0, 7kms lead, accidents. To the extent borrow areas shall be sited away for Borrow Areas iv) Jawai River from habitated areas. Borrow areas shall be management near , Complaints from leveled with salvaged material or other filling 225/0, 18 kms, v) local people. materials which do not pose contamination of Mithdi River near soil. Else, it shall be converted into fishpond in Nimbeshwar, consultation with fishery department and land 231/4, 0.5km lead owner/community.Rehabilitation ofthe borrow areas as per Guidelinesfor redevelopment of Borrow Areas.

4.4 Quarry Aggregates will be sourced from existing Clause No. Existence of Review of Included in Concessionaire/Contra PWD, Operations licensed quarries. 111.3 MORT&H licenses for all design Construction ctor RAJASTHAN Copies of consent/ approval / rehabilitation plan Specifications for quarry areas from documents, cost (SQC)/CSC for a new quarry or use of existing source will be Road and Bridge which materials are Concessionaire submitted to EO, PWD, RAJASTHAN. works Guidelines VI being sourced /Contractor The Concessionaire/Contractor will develop a for Quarry Areas documents and Quarry Redevelopment plan, as per the Mining Management Existence of a site Rules of the state and submit a copy of the quarry observation approval to EA. redevelopment plan

Page - 172

173

Environmental Remedial Measure Reference to laws Location Monitoring Monitoring Mitigation Institutional Responsibility Issue/ Component /guidelines indicators Methods Costs Implementation Supervision Complaints from local people. 4.5 Compaction of Construction vehicles, machinery, and Design Parking Location of Site Included in Concessionaire/Contra PWD, soil and impact on equipment to be stationed in the designated requirement areas, Haulage approach and haulage observation construction ctor RAJASTHAN quarry haul roads due ROW to avoid compaction. roads and roads cost (SQC)/CSC to movement of Approach roads/haulage roads shall be construction vehicles and designed along the barren and hard soil area to yards. Presence of equipment reduce the compaction. destroyed/compac ted Transportation of quarry material to the agricultural land or dumping site through heavy vehicles shall be land which has not be done through existing major roads to the extent restored to its original possible to restrict wear and tear to the condition village/minor roads. Land taken for construction camp and other temporary facility shall be restored to its original conditions. 4.6 Contamination Construction vehiclesand equipment Design Fuelling Quality of soil near Site Included in Concessionaire/Contra PWD, of soil due to leakage/ will be maintained and refueled in such a fashion requirement station, storage area observation construction ctor RAJASTHAN spillage of oil, that oil/diesel spillage does not contaminate the construction cost. (SQC)/CSC bituminous and soil. sites,and Presence of spilled oil non bituminous Fuel storage and refueling sites to be kept construction or bitumen in Project debris generated from away from drainage channels. camps and area demolition and road Unusable debrisshall be dumped in ditches and disposal location. construction low lying areas. To avoid soil contamination Oil-Interceptors shall be provided at wash down and refueling areas. Waste oil and oil soaked cotton/ cloth shall be stored in containers labeled „Waste Oil‟ and „Hazardous‟ sold off to MoEF/SPCB authorized vendors Non-bituminous wastes to be dumped in borrow pits with the concurrence of landowner and covered with a layer of topsoil conserved from opening the pit. Bituminous wastes will be disposed off in an identified dumping site approved by the State Pollution Control Board 5. Water Resources 5.1 Sourcing of water Requisite permission shall be obtained for - Throughout the Approval from Checking of Included in Concessionaire/Contra PWD, during abstraction of groundwater from Central Project competent documentation construction ctor RAJASTHAN Construction Groundwater Authority section authority cost (SQC)/CSC Arrangements shall be made by Talk to local Concessionaire/ Contractor that the water Complaints from people availability and supply to nearby communities local people on water remain unaffected. availability

Page - 173

174

Environmental Remedial Measure Reference to laws Location Monitoring Monitoring Mitigation Institutional Responsibility Issue/ Component /guidelines indicators Methods Costs Implementation Supervision 5.2 Disposal of  Provisions shall be made to connect roadside Clause No. 1010 Throughout Design of road Standards Included in Concessionaire/Contr PWD, water during drains with exiting nearby ponds otherwise EP Act 1986 the Project side drains methods Site construction actor RAJASTHAN construction make provision of water harvest ingpits MORT&H section observation cost (SQC)/CSC intermittently. Specifications for Existence of proper and review of Road and Bridge drainage system for documents works disposal of waste water

5.3 Alteration in Existing drainage system to be maintained Design Near all Design of road Review of Included in Concessionaire/Cont PWD, surface water andfurther enhanced. requirement, Clause drainage side drains design construction ractor RAJASTHAN hydrology due to Provision shall be made for adequate size and No channels, documents cost (SQC)/CSC embankment number of cross drainage structures esp. in the 501.8.6. MORT&H river crossings areas where land is sloping towards road Specifications etc. Site alignment. observation Road level shall be raised above HFL level wherever road level is lesser than HFL. 5.4 Siltation in water Embankment slopes to be modified Design Near all water Siltation of rivers, Field Included in Concessionaire/Cont PWD, bodies due to suitably to restrict the soil debris entering water requirement , Clause bodies, river streams, ponds and observation construction ractor RAJASTHAN construction activities/ bodies. No embankment other water bodies in cost (SQC)/CSC earthwork Provision of Silt fencing shall be made at water 501.8.6. MORT&H slopes. Project area bodies. Specifications for Silt/sediment should be collected and stockpiled RoadandBridge for possible reuse as surfacing of works slopes where they have to be re-vegetated. (CP and CP) and Earthworks and stone works to be prevented worldwide best from impeding natural flow of rivers, streams practices and water canals or existing drainage system.

5.5 Deterioration in No vehicles or equipment should be parked The Water Water bodies, Water quality of Conduction Included in Concessionaire/Cont PWD, Surface water quality or refuelled near water-bodies, so as to avoid (Prevention and refuelling ponds, streams, of water construction ractor RAJASTHAN due to leakage from contamination from fuel and lubricants. Control of Pollution) stations, rivers and other quality tests cost (SQC)/CSC vehicles and Oil and grease traps and fuelling platforms to be Act, construction water bodies in as per the equipments and waste provided at re-fuelling locations. 1974 and camps. Project monitoring from construction All chemicals and oil shall be stored away from amendments plan camps. water and concreted platform with thereof. Presence of oil catchment pit for spills collection. floating in water Field All equipment operators, drivers, and warehouse bodies in the Project observation personnel will be trained in immediate response area for spill containment and eventual clean-up. Readily available, simple to understand and preferably written in the local language emergency response procedure, including reporting, willbe providedby the Concessionaire/Contractors

Page - 174

175

Environmental Remedial Measure Reference to laws Location Monitoring Monitoring Mitigation Institutional Issue/ Component /guidelines indicators Methods Costs ImpReslemponentatsibiionlit Supervision Construction camp to be sited away from y water bodies. Wastes must be collected, stored and taken to approve disposal site only. Water quality shall be monitored periodically 6. Flora and Fauna 6.1 Vegetation loss Minimize tree cutting to the extent possible. Forest Throughout ROW width Review of Road side Relevant agency PWD, due to site preparation Roadside trees to be removed with prior Conservation Act Project corridor relevant Plantation cost specialized in RAJASTHAN and construction approval of competent authority. 1980 Number of trees for documents is included in afforestation (SQC)/CSC activities and Compensatory plantation at 1:10 basis and + felling – tree cutting project costs. additional plantation as per the IRC IRC SP: 21 and permit, guidelines in consultation with Forest IRC SP:66 Compensatory compensato Department. plantation plan ry plantation Regular maintenance of all trees planted. plan Provision of LPG in construction camp as fuel Number of trees source to avoid tree cutting, wherever possible. replanted Field Plantation of trees on both sides of the road. observation s Integrate vegetation management (IVM) with the carriage way completely clear of vegetation. From the edge of the road to the boundary of ROW, vegetation structuredwith smaller plants near the line and larger trees further away to avoid costly and provide habitats for a wide variety of plants and animals. Additional plantation near river banks to check erosion aspart of compensatory plantation. In the event of design changes during the construction stages additional assessments including the possibility to save trees shall be made by the EA. Road side Plantation Strategy as per IRC specifications including manuring. Control led use of pesticides/ Fertilizers

7. Construction Camps 7.1 Impact All camps should maintain Design All Location of On site Included in Concessionaire/C PWD, associated with minimum distancefrom following: Requirement construction campsites and observation construction ontractor and RAJASTHAN location # 500 m from habitation camps distance from cost EO (SQC)/CSC # 500 m from forest areas where possible habitation, forest Interaction with # 500 m from water bodies where possible areas, water workers and # 500 m from through traffic route where possible bodies, through traffic local community The average distance between two camps route and should be 50 km other construction camps

Page - 175

176

Environmental Remedial Measure Reference to laws Location Monitoring Monitoring Mitigation Institutional Responsibility Issue/ Component /guidelines indicators Methods Costs Implementation Supervision 7.2 Worker‟s Health The location, layout and basic facility The Building All Camp health Camp Part of the Concessionaire/Cont PWD, in construction camp provision of each labor camp will be submitted and Other construction records records Concessionaire ractor RAJASTHAN to SQC prior to their construction. The Construction camps /Contractors (SQC)/CSC construction shall commence only after workers (Regulation Existence of proper Site costs approval of SQC. of Employment and first aid kit in camp observation The Concessionaire/Contractor will maintain Conditions of site necessary living accommodation and ancillary Service)Act Consultation facilities in functional and hygienic manner as 1996 and The Water Complaints from with local approved by the EA. (Prevention local people people living Adequate water and sanitary latrines with and Control of nearby septic tanks attached to soak pits shall be Pollution) Act, provided. 1974 and Preventive medical care to be provided to amendments thereof workers including a First-Aid kit that must be available in the camp. Waste disposal facilities such as dust bins must be provided in the camps and regular disposal of waste must be carried out . The Concessionaire/ Contractor will take all precautions to protect the workers from insect and pest to reduce the risk to health. This includes the use of insecticides which should comply with local regulations. No alcoholic liquor or prohibited drugs will be imported to, sell, give, barter to the workers of host community. Awareness raising to immigrant workers/local community on communicable andsexually transmitted diseases. 8. Management of Construction Waste/Debris 8.1 Selection of Unproductive/wastelands shall be selected for Design At all Location of Field survey Included in Concessionaire/Co PWD, Dumping Sites dumping sites. Requirement and Dumping dumping sites and interaction construction ntractor. RAJASTHAN Away from residential areas and water bodies MORT&H Sites with local cost. (SQC)/CSC Dumping sites have adequate capacity equal guidelines Public complaints people to the amount of debris generated. Public perception and consent from the village Panchayats has to be obtained before finalizing the location.

Page - 176

177

Environmental Remedial Measure Reference to laws Location Monitoring Monitoring Mitigation Institutional Issue/ Component /guidelines indicators Methods Costs ImpReslemponentatsibiionlity Supervision 8.2 Reuse and The existing bitumen surface shall be utilized MORT&H Throughout Percentage of Concessionaire/ Included in Concessionaire/C PWD, disposal of construction for paving of cross roads, access roads, and guidelines the Project reuse of existing Contractor construction ontractor. RAJASTHAN and dismantled waste paving works in construction sites and camps, corridor surface material records cost. (SQC)/CSC temporary traffic diversions, and haulage routes. Method and location Field All excavated materials from roadway, of disposal site of observation shoulders, verges, drains, cross drainage will be construction debris used for backfilling embankments, filling pits, Interaction with and landscaping. local people Unusable and non-bituminous debris materials should be suitably disposed off at pre- designated disposal locations, with approval of the concerned authority. The bituminous wastes shall be disposed in secure landfill sites only in environmentally accepted manner. For removal of debris, wastes and its disposal MOSRTH guidelines should be followed. Unusable and surplus materials, as determined by the Independent Engineer, will be removed and disposed off-site.

9. Traffic Management and Safety 9.1 Management of Temporary traffic diversion shall be planned Falna, Bali, and Traffic Review Included in Concessionaire/C PWD, existing traffic and by the Concessionaire/Contractor and approved Design requirement Mundara built- management plan traffic construction ontractor RAJASTHAN safety by the Independent Engineer‟ for Falna, Bali, and IRC SP:55 up aeas. management cost. (SQC)/CSC and Mundara no later than 30 days before the Safety signs on site plan start of civil works in these areas Field The traffic control plans shall contain details of Number of traffic observation of diversions; traffic safety arrangements during accidents traffic construction; safety measures for night time management and traffic and precautions for transportation of safety system hazardous materials.  Traffic control plans shall be prepared in line Interaction with with requirements of IRC‟s SP 55 document‟. people in The Concessionaire/Contractor will ensure that vehicles using the diversion/detour is always maintained in the road running condition, particularly during the monsoon to avoid disruption to traffic flow. On stretches where it is not possible to pass the traffic on the part width of existing carriageway, temporary paved diversions will be constructed. Restriction of construction activity to only one side of the existing road. The Concessionaire/Contractor shall inform local community of changes to traffic routes, and pedestrian access arrangements with assistance from “Engineer”.

Page - 177

178

Environmental Remedial Measure Reference to laws Location Monitoring Monitoring Mitigation Institutional Responsibility Issue/ Component /guidelines indicators Methods Costs Implementation Supervision Use of adequate signages to ensure traffic management and safety. Conduct of regular safety audit on safety measures. 9.2 Pedestrians, Temporary access and diversion, with Design requirement Near Road signage& Field Included in Concessionaire/Contra PWD, animal movement proper drainage facilities. and habitation on both drainageasper observation construction ctor RAJASTHAN Access to the schools, temples and other public IRC: SP: 27 -1984 sides of schools, IRC guideline Interaction cost. (SQC)/CSC places must be maintained when construction IRC:SP:32 -1988 temples, with local takes place near them. Road Safety for hospitals, Complaints from local people Fencing wherever cattle movement is expected. Children(5-12 graveyards, people To avoid the need for cattle underpasses, Years Old) construction sites, some of the proposed culverts `near habitations IRC:SP:44 -1994 haulage roads, may be widened to facilitate cattle movement. Highway Safety diversion Code sites. IRC: SP: 55 -2001 Guidelines for The Building and other Construction workers Act 1996 and Cess Act of 1996 Factories Act 1948 9.3 Safety of Concessionaire/ Contractors to adopt Construction Availability of Site Included in Obligation of PWD, Workers and accident and maintain safe working practices. sites Safety gears to observation construction Concessionaire/ RAJASTHAN risk from construction Usage of fluorescent and retroflectory workers cost Contractor (SQC)/CSC activities signage, in local language at the construction Review sites Safety signage records on Training to workers on safety procedures and Training records on safety training precautions. safety and accidents Mandatory appointment of safety officer. All regulations regarding safe Number of safety Interact with scaffolding,ladders, working platforms, related accidents construction gangway, stairwells, excavations, trenches workers and safe means of entry and egress shall be complied with. Provision of PPEs to workers. Provision of a readily availablefirst aid unit including an adequate supply of dressing materials. The Concessionaire/Contractor will not employ any person below the age of 18 years for any work Use of hazardous material should be minimized and/or restricted. Emergency plan (to be approved by Independent Engineer) shall be prepared to respond to any accidents or emergencies.

Page - 178

179

Environmental Remedial Measure Reference to laws Location Monitoring Monitoring Mitigation Institutional Issue/ Component /guidelines indicators Methods Costs ImpReslemponentatsibiionlit Supervision Accident Prevention Officer must be y appointed by the Concessionaire/Contractor r. 9.4 Accident risk to Restrict access to construction sites to Construction Safety signs and Site Included in Concessionaire/C PWD, local community authorized personnel. sites their location inspection construction ontractor RAJASTHAN Physical separation must be provided for cost (SQC)/CSC movement of vehicular and human traffic. Incidents of Consultation Adequate signage must be provided for safe accidents with local people traffic movement Complaints from local people 10. Site restoration and rehabilitation 10.1 Clean-up Contractor/Concessionaire will prepare site Project requirement Throughout the Clean and restored Site observation Included in Concessionaire/ PWD, Operations, Restoration restoration plans, which will be approved by the Project camp construction Contractor RAJASTHAN and Independent Enginee‟. corridor, sites Interaction with cost. (SQC)/CSC Rehabilitation The clean-up and restoration operations are to construction locals be implemented by the camp sites and Presence/absence of Concessionaire/Contractor prior to borrow construction Issue completion demobilization. areas material/debris after certificate after All construction zones including river-beds, completion of restoration of all culverts, road-side areas, camps, hot mix plant construction works sites are found sites, crushers, batching plant sites and any on construction site satisfactory other area used/affected by the project will be left clean and tidy, at the Concessionaire/Contractor's expense, to the satisfaction of the Environmental officer. All the opened borrow areas will be rehabilitated and „Independent Engineer‟ will C.Operation stage certify in this regard. 1.Air quality 1.1 Air pollution due Roadside tree plantations shall be maintained. Environmental Throughout Ambient air quality As per Included in PWD, RAJASTHAN (SQC) to due to vehicular Regular maintenance of the road will be Protection Act, the Corridor (PM10, CO, NOx) CPCB Operation/ done to ensure good surface condition movement Vehicular air pollution will be managed and 1986; The Air requirements Maintenance monitored. (Prevention and Control Survival rate of trees cost Ambient air quality monitoring. If monitored of Pollution) planted parameters are above the prescribed limit, Act, 1981 Site inspection suitable control measures must be taken. Technological and behavioural changes Road signs shall be provided reminding themotoristto properly maintain their vehicles to economize on fuel consumption and protect the environment.

2.Noise

Page - 179

180

Environmental Remedial Measure Reference to laws Location Monitoring Monitoring Mitigation Institutional Responsibility Issue/ Component /guidelines indicators Methods Costs Implementation Supervision 2.1 Noise due to Effective traffic management and good riding Noise Pollution Sensitive Noise levels Noise Included in PWD, RAJASTHAN (SQC) movement of traffic conditions shall be maintainedto (Regulation and receptors monitoring as Operation/ reducethe noise level throughout the stretch Control) Rules, 2000 per noise rules Maintenance and speed limitation and and amendments ,2000 cost honking restrictions maybe enforced near thereof sensitive locations. The effectiveness of the multilayered Discussion plantationshould be monitored and if with people in need be, solidnoisebarriershallbe sensitive placed. receptor sites Create awareness amongst the residents about likely noise levels from road operationat differentdistances, the safe ambient noise limits and easy to implementnoisereduction measures while constructing a building close to the road.

3.Land and Soil 3.1 Soil erosion at Periodic checking to be carried to assess the Project At bridge Existence of soil On site Included in PWD, RAJASTHAN (SQC) embankment during effectiveness of the requirement locationsand erosion sites observation Operation/ heavy rain fall. stabilization measures viz. turfing, embankment Maintenance stone pitching, river training structures etc. slopes and Number of soil cost Necessary measures to be followed other erosion sites whereverthereare failures probable soil erosion areas. 4.Water resources/Flooding and Inundation 4.1 Siltation Regular checks shall be made forsoil erosion Project Near Water quality Site Included in PWD, RAJASTHAN (SQC) and turfing conditions of river requirement surface Water observation Operation/ training structures for its effective bodies Maintenance maintenance. cost 4.2 Water logging Regular visual checks and cleaning of drains Project Near Presence of Site Included in PWD, RAJASTHAN (SQC) due to blockage of shall be done along the requirement surface Water flooded areas or areas observation Operation/ drains, culverts or alignment to ensure that flow of water is bodies with water stagnation Maintenance streams maintained through cross drains and cost other channels/streams. Monitoring of waterborne diseases due to stagnant water bodies 4.3 Road inundation due PWD, RAJASTHANwillensurethatall drains Project requirement Flood prone Incidents of flooding Field Included in PWD, RAJASTHAN (SQC) to choking of (side drains and all cross drainages) are sections and road observation Operation/ drainage channels periodically cleared especially before inundation with details Interaction Maintenance monsoonseasontofacilitate the quick passage of on with local cost rainwater and avoid flooding. chainage community

5.Flora

Page - 180

181

Environmental Remedial Measure Reference to laws Location Monitoring Monitoring Mitigation Institutional Responsibility Issue/ Component /guidelines indicators Methods Costs Implementation Supervision 5.1 Vegetation Planted trees, shrubs, and grasses to be Forest Project tree Minimum of 70% Records Operation PWD, RAJASTHAN (SQC) properly maintained. Conservation Act plantation sites of tree survival and fields and The tree survivalist audit to be conducted at 1980 observation s Maintenance least once in a year to assess the effectiveness Cost

6.Maintenance of Right of Way and Safety 6.1 Accident Risk Efforts shall be made to make shoulder Project Throughout Presence of and Visual Included in PWD, RAJASTHAN (SQC) due to uncontrolled completely clear of vegetation. requirement the Project route extent of vegetation inspection operation/ growth of vegetation Regular maintenance of plantation along the growth on either side Maintenance roadside of road Accident cost Invasive plant not to be planted near the road. records Accident data

6.2 Accident risks Traffic control measures, including speed IRC:SP:55 Throughout Police records on Review Included in associated with traffic limits, will be enforced strictly. the Project route accident accident operation/ movement. Further encroachment of squatters within the records Maintenance PWD, RAJASTHAN (SQC) ROW will be prevented. Condition and cost No school or hospital will be allowed to be existence of safety Site established beyond the stipulated signs, rumble observation s planning line as per relevant local law strips etc. on the road Monitor/ensure that all safety provisions included in design and construction phase are Presence/absence of properly maintained sensitive receptor Highway patrol unit(s) for round the clock structures inside the patrolling. Phone booths for accidental stipulated planning reporting and ambulance services with line as per minimum response time for rescue of any relevant local law accident victims, if possible. Tow-away facility for the break down vehicles if possible. 6.3 Transport of Existence of spill prevention and control and Throughout Status of Review of Included in PWD, RAJASTHAN (SQC) Dangerous Goods/ emergency responsive system the project stretch emergency system – spill prevention operation/ hazardous Material Emergency plan for vehicles carrying whether operational or and emergency Maintenance hazardous material not response cost. system

Notes: EA: Executing Agency, PWD, RAJASTHAN: Madhya Pradesh Road Development Corporation, SQC: Supervision Quality Controller, EO: Environmental Officer, IRC: Indian Road Congress a. The “Independent Engineer” is the team of construction supervision consultants (CSC) responsible for approving the plans, engineering drawing, release of payments to The Concessionaire/Contractor etc. on behalf of the Authority. It is usually the team leader of the CSC that takes the responsibility of signing approval documents on behalf of the CSC team. b.The “environmental officer” is the environmental specialist under the CSC who is responsible for providing recommendations to the CSC team leader for approving activities specific to environment safeguards on behalf of “the Independent Engineer”.

Page - 181

Appendix Table 1. Location of Villages along the Project Road PWD Chainage Village/Town

From To

225/0 225/2 Falna Chauraha

225/4 225/6 Kamal Vihar

230/4 230/8 Nimbeshwarnath

233/4 234/0 Paryawar Circle

234/4 237/6 Falna

238/0 238/2 Falna Gaon

240/2 241/0 Shri Sela

241/4 244/2 Bali

244/6 245/0 Radawa

248/8 251/2 Kot Baliyan

253/8 254/2 Mundara

Appendix Table 2 Source of Construction Materials S.N. Source Chainage Side of Project Lead to Project Remarks Road Road

1 Stone Crusher 225/0 RHS 7.0 km Aggregate

2 Stone Crusher 225/10 Takhatgarh 38.0 km Aggregate

Schedule T Page - 182

3 Borrow Area 225/0 RHS 7.0 km Subpgrade/GSB

4 Jawai River near 225/0 RHS 18.0km Fine Aggregate Sumerpur

5 Mithdi River near 231/4 LHS 0.50 km Fine Aggregate Nimbeshwar Mahadev

6 Mithdi River near 254/2 To 6.2 km Fine Aggregate Nimbeshwar Mahadev

Schedule T Page - 183

ENVIRONMENTAL MONITORING PLAN FOR AHORE-BALI-MUNDARA (SH-22)

Env. Project Stage Parameters Method/ Location Frequency and Standards Approximate Implementation Supervision Indicators Guidelines Duration cost (Rs) Air Quality Construction PM 10 PM2.5 High volume 2 sampling per km of built Monthly Air quality 42x9000 =Rs Concessionaire RPWD /CSC stage SO2, NOX, CO sampler to be up area during active standard by 378,000 through approved located 50 m from construction: CPCB monitoring agency the selected Falna Chauraha (2), locations in the Kamal Vihar (2), downwind Nimbeshwarnath (2), direction. Use Paryawar Circle (2), Falna method specified by (6), Falna Gaon (2), Shri CPCB Sela (2), Bali (6), Radawa (2), Kot Baliya (6), Mundara (2)

Batching and hotmix plants sampling part of SPCB annual renewal of permits Operation Representative sample 24 hr continuous, Air quality 3X9000x3 RPWD through RPWD stage each for residential, 3/year for 1 year standard by =Rs 81,000 approved commercial and (Total 3 times in a CPCB monitoring agency sensitive/forest area year baring (3 Locations)- monsoon)

Water Quality Construction Ground water: Grab sample Groundwater at Monthly for 3 years, Water quality 36x 5000x3x2 Concessionaire RPWD /SC stage (IS: 10500:1991) collected from Construction Camps 3 camps with 2 standard by = Rs 1,080,000 through approved and source and analyse borewells each CPCB monitoring agency Operation Surface water as per Standard Groundwater at 2 3/year for 1 year Water quality 3X4X5000 RPWD through RPWD stage criteria for Methods for locations and surface standard by =Rs 45, 000 approved freshwater Examination of water at 2 locations CPCB monitoring agency classification Water and Wastewater Noise levels Construction Equivalent Noise IS:4954-1968 as Same as air quality National 42x3000x Concessionaire RPWD/CSC stage levels on dB (A) adopted by CPCB Ambient Noise =Rs.126,000 through approved scale for day and for Identified Study Standard monitoring agency Operation night Area Built-up areas 2/year for 1 year specified in 2x3000x48 RPWD through RPWD stage CPCB/IS:4954- Environment =Rs 288,000 approved 1968Using Noise Protection Act, monitoring agency level meter 1986

Schedule T Page - 184

Env. Project Stage Parameters Method/ Location Frequency and Standards Approximate Implementation Supervision Indicators Guidelines Duration cost (Rs) Soil Quality Construction NPK (ICAR As specified by the Camp, Dumping/storage Once during whole ICAR standard 14,000 Concessionaire RPWD/CSC Stage standard ) and site engineer RPWD areas and HMP sites construction stage through approved heavy metals / supervision (2 locations) monitoring agency consultant Operation Oil and grease At oil spillage locations Once for the first CPCB 28000 RPWD through RPWD stage and other probable soil year of operation standard approved agency contamination location Soil Erosion Construction Visual check for Throughout the Project After first rain Visual Checks Included in Concessionaire RPWD/CSC Stage Soil erosion and corridor especially at engineering cost Operation siltation River banks, bridge Once during Visual Checks routine Engineering team of RPWD Stage locations and river operation of 1st year engineering training structures work Drainage Construction Visual Checks Throughout the Project Once in a year included in Concessionaire' RPWD/CSC None Specific Congestion stage corridor especially before rainy season engineering cost Operation probable drainage Once in a year routine RPWD Stage congestion areas before rainy season None Specific engineering work Borrow Construction Visual Checks IRC guidelines Borrow areas to be Once in a month IRC guidelines Part of the Concessionaire RPWD/CSC Areas Stage operated + Concessionaire‟ with approval from Compliance s quote RPWD Operation Visual Checks Rehabilitation as Closed borrow areas Quarterly for 1 year conditions of RPWD Stage per IRC guidelines SEIAA Construction Construction Hygiene, Rapid audit as per Construction sites and Quarterly during IRC guidelines Part of the Concessionaire RPWD/CSC Sites and stage drainage Medical reporting format camp construction period regular with approval from Labor Facilities Etc. monitoring RPWD, RPWD Camp Construction Surveillance monitoring of trees felling Throughout the Project During site As suggested Compensatory: Compensatory: RPWD/Local Forest Tree Plantation Stage ection clearance in by Forest RPWD Departments construction phase Dept. Additional Plantation: Additional Concessionaire Operation Audit for survival rate of trees plantation Throughout the Project Once in a year for plantation: The Independent Engineer will be stage section years provisional sum responsible for monitoring up to the under civil cost Defect Liability Period in any particular stretch. After this period RPWD through Concessionaire will be responsible for monitoring Record of Construction Type, nature and cause of accidents. Throughout the stretch occurrence of As suggested Part of the Concessionaire RPWD/CSC Accident Stage Methodology as suggested by CSC and including construction accidents by PMC/SC regular approved by RPWD sites, crusher, diversions, monitoring HMP, earthwork, demolition site etc. Operation Throughout the stretch occurrence of Road Safety unit of RPWD with - - stage accidents support from local police Schedule T Page - 185

Env. Project Stage Parameters Method/ Location Frequency and Standards Approximate Implementation Supervision Indicators Guidelines Duration cost (Rs) Wildlife Construction Nature and cause of collision, season, Animal crossing locations occurrence of As suggested Civil Cost Concessionaire RPWD/CSC Vehicle Stage Month and time of collision. as identified in IEE collision by forest Collisions Operation 1. Success of road furnitures viz. rumble Animal crossing Random all through department Operation and RPWD in coordination with forest stage strip, cautionary signages etc. designed Locations as identified in the year Maintenance department or through an for safe movement IEE Cost specialized wildlife expert team 2. Nature and cause of collision, season, Month and time of collision 3. Monitoring of movement path based on informations available with forest department and local people. Monitoring Costs Construction Phase: INR 1.598 Million RPWD: Rajasthan State Public Works Department, NPK: Nitrogen, Phosphorous and Potassium, CSC: Construction Supervision Consultant, PMC: Project Management Consultant, IEE: Initial Environmental Examination, IRC: Indian Road Congress, SEIAA: State Environmental Impact Assessment Authority, CPCB: Central Pollution Control Board, IS: Indian Standard

Schedule T Page - 186

Schedule T Page - 187

SCHEDULE-T

ADB’s Safeguards Policy Statement Requirements

Protection of the The Concessionaire shall ensure that its Contractor/s comply with all Environment applicable national, provincial, and local environmental laws and regulations. The Concessionaire shall ensure that its Contractor/s shall (a) establish an operational system for managing environmental impacts, (b) carry out all of the monitoring and mitigation measures set forth in the Environmental Management Planattached hereto as Schedule -S and (c) allocate the budget required to ensure that such measures are carried out. The Contractor shall submit [quarterly][semi-annual] reports on the carrying out of such measures to the Concessionaire . More particularly, the Concessionaire shall ensure that its Contractor/s shall comply with (i) the measures and requirements set forth in the Environmental Management Plan attached hereto as Schedule-S and (ii) any corrective or preventative actions set out in safeguards monitoring reports that the Concessionaire will prepare from time to time to monitor implementation of the the Environmental Management Plan. The Concessionaire shall ensure that its Contractor/s shall allocate a budget for compliance with these measures, requirements and actions.”

Labour Laws The Concessionaire shall ensure that its Contractor shall not make employment decisions based upon personal characteristics unrelated to job requirements. The Contractor shall base the employment relationship upon equal opportunity and fair treatment, and shall not discriminate with respect to aspects of the employment relationship, including recruitment and hiring, compensation (including wages and benefits), working conditions and terms of employment or retirement, and discipline.

The Concessionaire shall ensure that its Contractor shall (a) provide equal wages and benefits to men and women for work of equal value or type.”

Health and Safety The Concessionaire shall ensure that its Contractor shall conduct health and safety programs for workers employed under the Project, and shall include information on the trafficking of women and the risk of sexually transmitted diseases, including HIV/AIDs in such programs

Page - 189

Child Labour The Concessionaire shall ensure that its Contractor shall not employ any child to perform any work, including work that is economically exploitative, or is likely to be hazardous to, or to interfere with, the child‟s education, or to be harmful to the child‟s health or physical, mental, spiritual, moral, or social development. “Child” means a child below the statutory minimum age of ____specified under Applicable Law.

“The Concessionaire shall ensure that the Contractor shall adequately record the condition of roads, agricultural land and other infrastructure prior to the start of transporting materials, goods and equipment, and construction.”

“ The Concessionaire shall ensure that the Contractor shall provide the Independent Engineer with a written notice of any unanticipated environmental or resettlement risks or impacts that arise during construction, implementation or operation of the plant or Permanent Works, which were not considered in the initialthe Environmental Management Plan

“Upon the completion of construction, the Concessionaire shall ensure that the Contractor shall fully reinstate pathways, other local infrastructure, and agricultural land to at least their pre-Project condition as recorded by the Contractor.”

Page - 190

ANNEXURE-I

List of ADB Member countries

Regional members Regional members Non regional members

1 Afghanistan 25 Micronesia, Federated 1 Austria States of

2 Armenia 26 Mongolia 2 Belgium

3 Australia 27 Myanmar 3 Canada

4 Azerbaijan 28 Nauru 4 Denmark

5 Bangladesh 29 Nepal 5 Finland

6 Bhutan 30 New Zealand 6 France

7 Brunei Darussalam 31 Pakistan 7 Germany

8 Cambodia 32 Palau 8 Ireland

9 China, People's Republic 33 Papua New Guinea 9 Italy of

10 Cook Islands 34 Philippines 10 Luxembourg

11 Fiji 35 Samoa 11 The Netherlands

12 Georgia 36 Singapore 12 Norway

13 Hong Kong, China 37 Solomon Islands 13 Portugal

14 India 38 Sri Lanka 14 Spain

15 Indonesia 39 Taipei,China 15 Sweden

16 Japan 40 Tajikistan 16 Switzerland

17 Kazakhstan 41 Thailand 17 Turkey

18 Kiribati 42 Timor-Leste 18 United Kingdom

19 Korea, Republic of 43 Tonga 19 United States

20 Kyrgyz Republic 44 Turkmenistan

21 Lao PDR 45 Tuvalu

22 Malaysia 46 Uzbekistan

23 Maldives 47 Vanuatu

Page - 191

24 Marshall Islands 48 Viet Nam

Page - 192

Appendices

Page - 193

Page - 194

APPENDIX-I LIST OF BID-SPECIFIC PROVISIONS£4

A. Provisions with currency-based footnotes

Footnotes with “£” sign

1. Clause 23.1: Project Cost. 2. Concession Agreement: Signature page. 3. Schedule-O: Escrow Agreement: Signature page. 4. Schedule-R: Substitution Agreement: Signature page. 5. Appendix-I: List of Bid-specific provisions.

Note: The above footnotes marked “£” shall be removed prior to execution of the Concession Agreement.

Footnotes with “$” sign

1. Heading of the Concession Agreement. 2. Clause 16.5.1: Power of the Authority to undertake words. 3. Schedule-J: Completion Certificate: Provisional Certificate.

Note: Non-numerical footnotes marked “$” shall not be deleted. They shall remain in the Concession Agreement to be executed between the Parties.

B. Provisions where curly brackets are used

1. Recitals: Recitals B, D, E, F and G. 2. Clause 4.1.3 (g): Conditions Precedent. 3. Clause 7.1 (c), (g), (k), (I) and (p): Representations and warranties of the Concessionaire. 4. Clause 8.1.2: Disclaimer. 5. Clause 41.14(a) and (b): Notices. 6. Clause 42.1: Definitions of Associate, Bid, Change in Ownership, Joint Venture and Joint Venture Member.

C. Provisions with blank spaces

1. Recitals: First line, Recitals 2, B, D and F. 2. Clause 23.1: Project Cost. 3. Concession Agreement: Signature page.

£ This Appendix-I contains a list of provisions that would need to be suitably modified for reflecting bid-specific provisions after the Concessionaire has been selected. This Appendix-I may be included in the draft Concession Agreement forming part of the bid documents. It may however, be deleted when the Concession Agreement is to be executed.

Appendix-II Page - 195

Note: All blank spaces in Schedules shall be retained in the Concession Agreement to be executed between the Parties. These shall be filled up as and when the format of the respective Schedule is used. Note: The Table of the Contents may also be suitably modified to reflect omission(s) and/or re- numbering of Bid-specific provisions.

Appendix-II Page - 196