Executive Committee Meeting Revised Agenda

#9/17 November 3, 2017 9:30 A.M. HEAD OFFICE, 101 EXCHANGE AVENUE, VAUGHAN Members:

Chair Vice Chair Jack Heath Jack Ballinger Chris Fonseca Brenda Hogg Jennifer Innis Colleen Jordan Mike Mattos Jennifer McKelvie

Pages

1. MINUTES OF MEETING #8/16, HELD ON OCTOBER 14, 2016 Link to Executive Committee Minutes

2. BUSINESS ARISING FROM THE MINUTES

3. DISCLOSURE OF PECUNIARY INTEREST AND THE GENERAL NATURE THEREOF

4. DELEGATIONS

5. PRESENTATIONS

6. CORRESPONDENCE 7. SECTION I - ITEMS FOR AUTHORITY ACTION

7.1 GREENLANDS ACQUISITION PROJECT FOR 2016-2020 5 Flood Plain and Conservation Component, Duffins Creek Watershed Cougs (Workman’s) Ltd. CFN 56096

7.2 REQUEST FOR EXCHANGE OF AND REGION CONSERVATION 8 AUTHORITY-OWNED LAND Flood Plain and Conservation Component, Humber River Watershed Davpart Inc. CFN 56150

8. SECTION II - ITEMS FOR EXECUTIVE COMMITTEE ACTION ADDED ITEM

8.1 BLACK CREEK PIONEER MILL POND CLEAN-OUT AND RESTORATION 12 PROJECT Award of Contract # 10006384 for the Disposal of Stockpiled Sediments

9. SECTION III - ITEMS FOR THE INFORMATION OF THE BOARD

10. SECTION IV - ONTARIO REGULATION 166/06, AS AMENDED PERMIT APPLICATION 10.1 IS A MAJOR APPLICATION - REGULAR

Applications that involved a more complex suite of technical studies to demonstrate consistency with policies; applications that cover a significant geographic area (e.g. subdivisions, stormwater management ponds), extensive modifications to the landscape, major infrastructure projects, emergency infrastructure works, resolution of violations/after the fact permits, trail construction.

10.1 CITY OF VAUGHAN 15 813229 ONTARIO LTD. To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units and site grade on Part Lot 19, Concession 8, (9732 Highway 27), in the City of Vaughan, Humber River Watershed as located on the property owned by 813229 Ontario Ltd. The purpose is to permit development within a Regulated Area of the Humber River Watershed to facilitate minor grading works and interior and exterior modification and renovations to an existing restaurant (formerly the Salty Dawg) at 9732 Highway No. 27, in the City of Vaughan. The grading works include a new septic system as well as a comprehensive planting plan which includes new trees and shrubs.

2 10.2 STANDARD DELEGATED PERMITS 19 Standard Permits, including Emergency Infrastructure Works permissions, are implemented by Planning and Development Division staff and are received monthly by the Executive Committee. Standard Permits , including Emergency Infrastructure Works permissions, are subject to the authorization of designated staff appointed as Enforcement Officers, as per Authority Res.#A198/13, #A199/13 and #A103/15, respectively. All standard and emergency infrastructure works are non-complex permissions consistent with TRCA approved policies and procedures and issued for a time period of two years of less.

ADDED ITEMS

PERMIT APPLICATIONS 10.3 - 10.6 ARE MAJOR APPLICATIONS - REGULAR Applications that involved a more complex suite of technical studies to demonstrate consistency with policies; applications that cover a significant geographic area (e.g. subdivisions, stormwater management ponds), extensive Modifications to the landscape, major infrastructure projects, emergency infrastructure works, resolution of violations/after the fact permits, trail construction.

10.3 CITY OF MARKHAM 40 2585231 ONTARIO INC. To site grade, temporarily or permanently place, dump or remove any material, originating on the site or elsewhere and alter a watercourse on Lot 20, Concession 8, (9999 Highway 48 (Markham Road)), in the City of Markham, Rouge River Watershed as located on the property owned by 2585231 Ontario Inc.. The purpose is to alter a waterway and conduct grading works within a Regulated Area of the Rouge river Watershed in order to realign and naturalize a stretch of Exhibition Creek at 9999 Highway 48, in the City of Markham.

10.4 TOWN OF CALEDON 44 BOLTCOL HOLDINGS NORTH INC. AND BOLTCOL HOLDINGS SOUTH INC. To construct, reconstruct, erect or place a building or structure, site grade and alter a watercourse on Part Lot 2, 3, Concession 5 ALBION Part 1, Part 2 Plan 43R33412, (0 Coleraine Drive and 12300 Coleraine Drive), in the Town of Caledon, Humber River Watershed as located on the property owned by Boltcol Holdings North Inc. and Boltcol Holdings South Inc.. The purpose is to grade, remove and place fill, and construct within a Regulated Area to facilitate the construction of a stormwater management pond associated with a large format employment land site plan application.

3 10.5 TOWN OF CALEDON 47 BOLTCOL HOLDINGS NORTH INC. AND BOLTCOL HOLDINGS SOUTH INC. To site grade, temporarily or permanently place, dump or remove any material, originating on the site or elsewhere and alter a watercourse on Part Lot 2, 3, Concession 5 ALBION Part 1, Part 2 Plan 43R33412, (0 Coleraine Drive and 12300 Coleraine Drive), in the Town of Caledon, Humber River Watershed as located on the property owned by Boltcol Holdings North Inc. and Boltcol Holdings South Inc.. The purpose is to grade, remove and place fill, and construct within a Regulated Area to facilitate site grading, watercourse realignment works and installation of a storm sewer pipe associated with a large format employment land site plan application.

10.6 TOWN OF RICHMOND HILL 50 MATTAMY HOMES (ELGIN MILLS) LIMITED To site grade, temporarily or permanently place, dump or remove any material, originating on the site or elsewhere and interfere with a wetland on Part Lot 27, 28, Concession 2, (Leslie Street and Elgin Mills Road East), in the Town of Richmond Hill, Rouge River Watershed as located on the property owned by Mattamy Homes (Elgin Mills) Limited. The purpose is to undertake works within a TRCA Regulated Area of the Rouge River Watershed in order to facilitate Phase 2 topsoil stripping, stockpiling, site alteration and grading, import large volumes of fill and implement sediment and erosion control measures in support of an approved draft plan of subdivision, associated with a municipal building permit..

11. NEW BUSINESS

NEXT MEETING OF THE EXECUTIVE COMMITTEE #10/16, TO BE HELD ON DECEMBER 9, 2016 AT 9:30 A.M. AT HEAD OFFICE, 101 EXCHANGE AVENUE, VAUGHAN

Brian Denney, Chief Executive Officer

/jr

4 Item 7.1

Section I – Items for Authority Action

TO: Chair and Members of the Executive Committee Meeting #9/17, Friday, November 03, 2017

FROM: Mike Fenning, Associate Director, Property and Risk Management

RE: GREENLANDS ACQUISITION PROJECT FOR 2016-2020 Flood Plain and Conservation Component, Duffins Creek Watershed Cougs (Workman’s) Ltd. CFN 56096 ______KEY ISSUE Acquisition of property located east of Church Street North and north of Rossland Road West, in the Town of Ajax, Regional Municipality of Durham, under the “Greenlands Acquisition Project for 2016-2020,” Flood Plain and Conservation Component, Duffins Creek watershed.

RECOMMENDATION

THE EXECUTIVE COMMITTEE RECOMMENDS THAT 11.2 hectares (27.8 acres), more or less, of vacant land, located east of Church Street North and north of Rossland Road West, said land being Part of Lot 14, Concession 3, designated Parts 1-4 on 40R-8952 Save And Except Part 1 On Plan 40R-24996 and Save And Except Part 1 on draft-M-Plan by J.D. Barnes Limited, Reference No. 14-25-888-05, dated September 28, 2017; and Blocks 4-5 on draft M-Plan by J.D. Barnes Limited, Reference No.14-25-888-03, dated September 15, 2017, in the Town of Ajax, Regional Municipality of Durham, be purchased from Cougs (Workman’s) Ltd.;

THAT the purchase price be $2.00;

THAT Toronto and Region Conservation Authority (TRCA) receive conveyance of the land free from encumbrance, subject to existing service easements;

THAT the firm Gardiner Roberts LLP, be instructed to complete the transaction at the earliest possible date. All reasonable expenses incurred incidental to the closing for land transfer tax, legal costs, and disbursements are to be paid by TRCA;

AND FURTHER THAT authorized TRCA officials be directed to take the necessary action to finalize the transaction, including obtaining any necessary approvals and the signing and execution of documents.

BACKGROUND Resolution #A161/15 at Authority Meeting #8/15, held on September 25, 2015, approved the Greenlands Acquisition Project for 2016-2020.

Negotiations have been conducted with Ian McCullough, Vice President of Land Development, Coughlan Homes, acting as agent for the owner.

Access to the subject lands will be achieved through its frontage on Church Street North.

Attached is a sketch illustrating the location of the subject lands.

5 Item 7.1

RATIONALE The subject lands fall within TRCA's approved master plan for acquisition for the Duffins Creek watershed as outlined in the approved Greenlands Acquisition Project for 2016-2020. Through the review of the Plan of Subdivision 18T-95036, TRCA staff established the limits of the open space land.

TAXES AND MAINTENANCE Based on TRCA's preliminary review of the environmental criteria for lands that are eligible to receive a property tax exemption under the provincial Conservation Land Tax Incentive Program, it would appear that the subject property should be eligible for a tax exemption. While it is expected that the subject parcel of land will not significantly impact TRCA’s maintenance costs at this location, an assessment of the aggregate acquisitions in the area will be undertaken and the results will be integrated into TRCA’s land management program and associated budgets.

FINANCIAL DETAILS Funds for the costs related to this purchase are available in the TRCA land acquisition capital account.

Report prepared by: Edlyn Wong, extension 5711, Jae Truesdell, extension 5247 Emails: [email protected], [email protected] For Information contact: Edlyn Wong, extension 5711, Jae Truesdell, extension 5247 Emails: [email protected], [email protected] Date: October 13, 2017 Attachments: 1

6 Attachment 1

Subject reek s C Property fin

CHURCH ST N uf # D st a E

ROSSLAND RD W

Legend DURHAM Watercourses YORK !!!!!! Floodline SITE^ PEEL Subject PropertySubject Regulation LimitRegulation F TORONTO TRCAProperty Lake Ontario Parcel Assessment Parcel 0 100 200 Meters 7 KeyMap © Queen’s Printer for Ontario and its licensors. [2017] May Not[2017] ReproducedbeNOT THIS ISPLANA without OFlicensors. SURVEY.Permission. and Ontario its for ©Queen’sPrinter Item 7.2

Section I – Items for Authority Action

TO: Chair and Members of the Executive Committee Meeting #9/17, Friday, November 03, 2017

FROM: Mike Fenning, Associate Director, Property and Risk Management

RE: REQUEST FOR EXCHANGE OF TORONTO AND REGION CONSERVATION AUTHORITY-OWNED LAND Flood Plain and Conservation Component, Humber River Watershed Davpart Inc. CFN 56150 ______KEY ISSUE An exchange of land located west of Keele Street and south of Sheppard Avenue West, municipally known as 111-117 Whitburn Crescent, in the City of Toronto, under the “Greenlands Acquisition Project for 2016-2020,” Flood Plain and Conservation Component, Humber River watershed.

RECOMMENDATION

THE EXECUTIVE COMMITTEE RECOMMENDS THAT WHEREAS Toronto and Region Conservation Authority (TRCA) is in receipt of a request from Davpart Inc. for TRCA to enter into an exchange of lands with Davpart Inc., the owner of 111-117 Whitburn Crescent, City of Toronto, in order to resolve an existing encroachment on the adjacent TRCA-owned lands;

AND WHEREAS it is in the best interest of TRCA in furthering its objectives as set out in Section 20 of the Conservation Authorities Act to cooperate with Davpart Inc., in this instance and proceed with the land exchange;

THEREFORE LET IT BE RESOLVED THAT TRCA enter into an exchange of lands with Davpart Inc. on the following basis:

1. Davpart Inc. will convey to TRCA a parcel of land containing 0.035 hectares (0.09 acres), more or less, of vacant valley lands, located west of Keele Street and south of Sheppard Avenue West, said land being Part Block 1, PL 4503 North York as in TB215629; designated as Part 1 on sketch created on May 13, 2016 by MacNaughton Hermsen Britton Clarkson Planning Limited, municipally known as 117 Whitburn Crescent, in the City of Toronto;

2. TRCA will convey to Davpart Inc. a parcel of land containing 0.02 hectares (0.06 acres), more or less, of table lands with existing parking spaces, located west of Keele Street and south of Sheppard Avenue West, said land being Part Block 1, PL 4503 North York as in NY666347; designated as Part 2 on sketch created on May 13, 2016 by MacNaughton Hermsen Britton Clarkson Planning Limited, municipally known as 1651 Sheppard Avenue West, in the City of Toronto;

THAT TRCA receive consideration in the sum of $275,880.00; all legal, survey and other costs to be paid by Davpart Inc.;

8 Item 7.2

THAT TRCA receive conveyance of the land free from encumbrance, subject to existing service easements;

THAT Davpart Inc., is to fully indemnify TRCA from any and all claims from injuries, damages or costs of any nature resulting in any way, either directly or indirectly, from this exchange;

THAT the firm Gardiner Roberts LLP, be instructed to complete the transaction at the earliest possible date. All reasonable expenses incurred incidental to the closing for land transfer tax, legal costs, and disbursements are to be paid by Davpart Inc.;

THAT said conveyance be subject to the approval of the Minister of Natural Resources and Forestry in accordance with Section 21(2) of the Conservation Authorities Act, R.S.O. 1990, Chapter C.27, as amended, if required;

AND FURTHER THAT authorized TRCA officials be directed to take the necessary action to finalize the transaction, including obtaining any necessary approvals and the signing and execution of documents.

BACKGROUND Resolution #A161/15 at Authority Meeting #8/15, held on September 25, 2015, approved the Greenlands Acquisition Project for 2016-2020.

The proposed land exchange would involve the transfer of TRCA lands municipally known as 1651 Sheppard Avenue West in the City of Toronto, that have been developed by Davpart Inc. with parking spaces (existing), and in exchange Davpart Inc. is proposing to convey a portion of land at the rear of 117 Whitburn Crescent which is undeveloped and predominantly valley lands as well as pay consideration in the sum of $275,880.00.

The subject TRCA-owned lands were acquired from D.B. Goodman, on January 13, 1960 under the W.C.-12 Black Creek Water Control Project.

Negotiations have been conducted with Neil Robinson, Manager, acting as agent for the owners Carmen Colafella.

Access to the subject lands will be achieved through its frontage on Sheppard Avenue West.

Attached is a plan showing the location of the subject lands.

RATIONALE The subject lands fall within TRCA's approved master plan for acquisition for the Humber River watershed as outlined in the approved Greenlands Acquisition Project for 2016-2020.

An analysis of the proposed exchange was conducted by a third party, MHBC Planning, Urban Design & Landscape Architecture on behalf of Davpart Inc. After a thorough exploration of relocating the parking spaces elsewhere within Davpart Inc. owned lands it was concluded that there was no other suitable location on the site for the parking.

It is TRCA staff opinion that the proposed exchange and consideration is beneficial to both parties.

9 Item 7.2

The market value of the lands to be exchanged is based on an appraisal prepared by D. Bottero and Associates Limited on October 19, 2016 as well as an appraisal prepared by Wagner, Andrews, Kovac Ltd. on November 21, 2016.

TAXES AND MAINTENANCE The parcel of land that is conveyed to TRCA will be turned over to the City of Toronto under the terms of the existing management agreement.

FINANCIAL DETAILS All expenses related to this land exchange are to be paid by Davpart Inc.

Report prepared by: Brandon Hester, extension 5767, Jae Truesdell, extension 5247 Emails: [email protected], [email protected] For Information contact: Brandon Hester, extension 5767, Jae Truesdell, extension 5247 Emails: [email protected], [email protected] Date: Tuesday, October 17, 2017 Attachments: 1

10 Attachment 1

SE ELE Y D R CRT EE R

T

E

L

P P

A DIANA DR M

A

R

Y

P

O

R

T

A VE Area to be

Received #

B la c k

C

r

e

e

k

Area to be # E N AV Transferred YDO BLA

D E N B T IG CR H ON RES SKIPT C

W H IT B U R N C R E S

Legend

DURHAM Area to be Receivedbeto Area YORK Area to be Transferred beto Area

Watercourses PEEL !!!!!! Floodline SITE Regulation LimitRegulation F ^TORONTO TRCAProperty Lake Ontario 0 50 100 Parcel AssessmentParcel Meters 11 KeyMap © Queen’s Printer for Ontario and its licensors. [2017] May NOTNot[2017] ReproducedbeTHIS ISPLAN A without OFlicensors. SURVEY.Permission. its andOntario for ©Queen’sPrinter Item 8.1

Section II – Items for Executive Action

TO: Chair and Members of the Executive Committee Meeting #9/17, Friday, November 03, 2017

FROM: Nick Saccone, Senior Director, Restoration and Infrastructure

RE: BLACK CREEK PIONEER MILL POND CLEAN-OUT AND RESTORATION PROJECT Award of Contract # 10006384 for the Disposal of Stockpiled Sediments ______KEY ISSUE Black Creek Pioneer Mill Pond will be dredged mechanically to remove sediment that is inhibiting the operations of the mill at Black Creek Pioneer Village and negatively impacting Black Creek downstream of the pond. Accumulated sediment will need to be hauled and disposed of using a contractor operating under a Ministry of the Environment and Climate Change Environmental Compliance Approval.

RECOMMENDATION

THAT Contract #10006384 for the disposal of industrial/commercial pond dredgeate for Black Creek Pioneer Mill Pond, in the City of Toronto, be awarded to Ground Force Environmental Inc. for a total cost not to exceed $117,674.40, plus HST, it being the lowest bid meeting Toronto and Region Conservation Authority (TRCA) specifications;

THAT TRCA staff be authorized to approve additional expenditures to a maximum of 15% of the total cost of the contract as a contingency allowance, if deemed necessary;

AND FURTHER THAT authorized TRCA staff be directed to take the action necessary to implement the contract including obtaining any approvals and the signing and execution of documents.

BACKGROUND TRCA has over 35 years of experience in the planning, design, construction, maintenance and monitoring of stormwater management pond (SWMP) projects. TRCA is ideally suited to carry out pond maintenance for the Black Creek Pioneer Village (BCPV) pond because of the full range of services and experience that can be offered internally including plan design, approvals, survey, public consultation, implementation and site restoration.

Black Creek Pioneer Mill Pond, located south east of Steeles Avenue and Jane Street, within the boundaries of BCPV, is approximately .20 ha in size and drains to Black Creek. Due to years of sedimentation it has reached its capacity where the accumulated sediment needs to be dredged to improve function of the mill, as well as, the general aesthetics and historical/heritage value of Black Creek Pioneer Village. Cleaning out this pond will improve the thermal and sediment loading impacts to Black Creek downstream of the Black Creek Pioneer Mill Pond. The sediment was tested and meets industrial/commercial Ministry of the Environment and Climate Change (MOECC) guidelines.

12 Item 8.1

As part of the scope of work for this project, the industrial/commercial sediment accumulated in Black Creek Pioneer Mill Pond will be dredged, stockpiled and mixed with a polymer to make it easy to handle with machinery and taken off-site for disposal. The polymer is food grade and safe for use in aquatic environments. It has been used on multiple occasions by TRCA throughout the jurisdiction. Once the character of the sediment becomes like that of wet-cement, it is loaded into tri-axles for off-site hauling to an MOECC approved disposal facility operating with an Environmental Compliance Approval (ECA). In addition, a water control structure will be installed within the pond outlet to allow for increased water retention and improved water management within the pond.

TRCA estimated that there is an accumulation of up to 1,000 m3 of sediment to be removed from Black Creek Pioneer Mill Pond.

RATIONALE The Request for Tender (RFT) #10006384 was publically advertised on the electronic procurement website www.biddingo.com on October 20, 2017 for the haulage and disposal of industrial/commercial sediment material from Black Creek Pioneer Mill Pond. The document was downloaded for review by 20 vendors.

The quotations were received on October 27, 2017 and formally opened by TRCA staff (Lisa Moore, Judith Reda and Ryan Bolton) on the same day with the following results:

Total Bidders (Plus HST) Loc-Pave Construction Inc. $125,500.00 Ground Force Environmental Inc. $117,674.40

The two bids received were evaluated and scored based on the bidder’s price and has determined that the lowest bid is of reasonable value and also meets the requirements and deliverables as outlined on the contract documents. Ground Force Environmental Inc. is capable of undertaking the scope of work. In addition, this vendor has worked successfully with TRCA in the past for similar types of contracts.

Based on the bids received, staff recommends that Ground Force Environmental Inc. be awarded Contract #10006384 for the disposal of stockpiled sediments at Black Creek Pioneer Mill Pond at BCPV for a total cost not to exceed $117,674.40 plus 15% contingency to be expended as authorized by TRCA staff, plus HST.

This project is consistent with TRCA’s Strategic Plan, specifically strategy #2 manage our regional water resources for current and future generations.

FINANCIAL DETAILS The costs for Contract #10006384 are 100 % recoverable from the City of Toronto in account 107-24.

DETAILS OF WORK TO BE DONE Black Creek Pioneer Mill Pond will be dredged mechanically and restored upon completion. Only contractors operating under an MOECC ECA are eligible to undertake the disposal of the industrial/commercial sediment.

13 Item 8.1

TRCA will execute the contract, including: management of the awarded disposal contractor on site, certification of each load leaving the site, issuance of bills of lading to each truck, verification of the disposal site’s MOECC ECA, and random checks to follow trucks from dredging site to disposal site. These activities ensure the chain of custody of the dredged sediment from the SWMP to the licensed disposal site operating under an MOECC ECA.

Dredging is tentatively scheduled to commence in November at Black Creek Pioneer Mill Pond, upon receipt of all approvals and the availability of resources. Black Creek Pioneer Mill Pond will be de-watered during the dredging, and will be managed to ensure the pond is providing stormwater management function during this time period.

Report prepared by: Natalie Hryshko, extension 5889, Danielle Dellandrea, extension 5240 Emails: [email protected], [email protected] For Information contact: John Stille extension 5396, John DiRocco extension 5231, Ryan Bolton, extension 5950 Emails: [email protected], [email protected], [email protected] Date: October 17, 2017

14 Section IV – Ontario Regulation 166/06, As Amended

TO: Chair and Members of the Executive Committee Meeting #9/17, November 3, 2017

FROM: Carolyn Woodland, Senior Director, Planning, Greenspace and Communications

RE: APPLICATIONS FOR PERMITS PURSUANT TO ONTARIO REGULATION 166/06, AS AMENDED Development, Interference with Wetlands and Alterations to Shorelines and Watercourses ______KEY ISSUE Pursuant to Ontario Regulation 166/06, as amended, written permission from the Authority is required for: a) straightening, changing, diverting or interfering in any way with the existing channel of a river, creek, stream or watercourse, or for changing or interfering in any way with a wetland; b) development, if in the opinion of the authority, the control of flooding, erosion, dynamic beaches or pollution or the conservation of land may be affected by the development.

A permit may be refused through a Hearing Process, if in the opinion of the Authority, the control of flooding, erosion, dynamic beaches, pollution or the conservation of land is affected.

RECOMMENDATION

THAT permits be granted in accordance with Ontario Regulation 166/06, as amended, for the applications which are listed below:

PERMIT APPLICATIONS - ARE MAJOR APPLICATION - REGULAR

Applications that involved a more complex suite of technical studies to demonstrate consistency with policies; applications that cover a significant geographic area (e.g. subdivisions, stormwater management ponds), extensive modifications to the landscape, major infrastructure projects, emergency infrastructure works, resolution of violations/after the fact permits, trail construction.

15 CITY OF VAUGHAN

10.1 813229 ONTARIO LTD. To change a building or structure so that it alters its use or potential use, increases its size or increases the number of dwelling units and site grade on Part Lot 19, Concession 8, (9732 Highway 27), in the City of Vaughan, Humber River Watershed as located on the property owned by 813229 Ontario Ltd. The purpose is to permit development within a Regulated Area of the Humber River Watershed to facilitate minor grading works and interior and exterior modification and renovations to an existing restaurant (formerly the Salty Dawg) at 9732 Highway No. 27, in the City of Vaughan. The grading works include a new septic system as well as a comprehensive planting plan which includes new trees and shrubs.

The permit will be issued for the period of November 3, 2017 to November 2, 2019 in accordance with the following documents and plans which form part of this permit:

 Drawing No. A100 – Site Plan, prepared by Kohn Partnership Architects Inc., revision No. 10 issued September 7, 2017, received by TRCA on October 18, 2017;  Drawing No. N-1, General Notes, prepared by MNT Consulting Group, revision No. 3 issued July 24, 2017, received by TRCA on October 18, 2017;  Drawing No. N-2, General Notes, prepared by MNT Consulting Group, revision No. 3 issued July 24, 2017, received by TRCA on October 18, 2017;  Drawing No. L1 – Landscape Plan, prepared by MSLA Landscape Architects, revision No. 15 issued July 26, 2017, received by TRCA on October 18, 2017;  Drawing No. L2 – Landscape Details, prepared by MSLA Landscape Architects, revision No. 15 issued July 26, 2017, received by TRCA on October 18, 2017;  Drawing No. L3 – Landscape Details, prepared by MSLA Landscape Architects, revision No. 15 issued July 26, 2017, received by TRCA on October 18, 2017;  Drawing No. SS-1 – Site Servicing Plan, prepared by MNT Consulting Group, revision No. 3 issued July 24, 2017, received by TRCA on October 18, 2017;

16  Drawing No. SG-1 – Site Grading Plan, prepared by MNT Consulting Group, revision No. 3 issued July 24, 2017, received by TRCA on October 18, 2017;  Drawing No. ESC-1 – Erosion Control Plan, prepared by MNT Consulting Group, revision No. 3 issued July 24, 2017, received by TRCA on October 18, 2017;  Drawing No. SWM-1, Pre-Development Storm Drainage Plan, prepared by MNT Consulting Group, revision No. 3 issued July 24, 2016, received by TRCA on October 18, 2017;  Drawing No. SWM-2, Post-Development Storm Drainage Plan, prepared by MNT Consulting Group, revision No. 3 issued July 24, 2017, received by TRCA on October 18, 2017;  Structural Review # 9732 Highway 27, prepared by C. F. Crozier & Associates Inc., dated January 18, 2017, received by TRCA on May 11, 2017.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose of this application is to permit development within a Regulated Area of the Humber River Watershed to facilitate minor grading works and interior and exterior modification and renovations to an existing restaurant (formerly the Salty Dawg) at 9732 Highway No. 27. The grading works include a new septic system as well as a comprehensive planting plan which includes new trees and shrubs. The Main Humber River traverses the rear of the subject property which is located on the flat valley floor, entirely within the Regional Storm Flood Plain. The Regional Storm Flood Elevation for the subject property is 168.91 metres above sea level (m.a.s.l.).

We note that the existing building already contains a number of openings well below the proposed drive-through window opening elevation. The existing building is already prone to flooding (the existing finished floor elevation of the building and existing entrances are located at 167.50 m.a.s.l.) and confirmation from structural engineer confirms that the building can withstand the hydrodynamic and hydrostatic forces under the Regional Flood event and does not increase the risk to life and property.

The proposed minor grading works include modifications to the already existing paved areas to accommodate formal drive aisles and additional parking spaces. There are no proposed new parking areas or an increase in impervious areas associated with the propose works. TRCA Water Resources Engineering staff are satisfied that these works will not have an adverse impact on the storage and conveyance of flood waters.

Control of Flooding: The subject property is entirely within the Regional Storm Flood Plain. As the proposal does not involve the construction of any new structures or grading works that would impact the flood plain, impacts to flooding or the conveyance of floodwaters is not anticipated as a result of the proposed works.

Pollution: Sediment control fencing (double silt fence) will be erected and maintained for the duration of construction to prevent the transport of sediment into the adjacent Humber River.

17 Dynamic Beaches: Not applicable

Erosion: Impacts to slope stability and erosion are not anticipated as a result of the proposed works.

Conservation of Land: As the adjacent watercourse (Main Humber River will not be impacted by the proposal, no fisheries concerns will result. There are no other significant natural features on or adjacent to the site that may be negatively impacted by the project

Plantings All disturbed areas are to be rehabilitated through terra seeding and the planting of 431 native species of deciduous trees, shrubs and grasses.

Policy Guidelines: This proposal complies with Section 8.4 - General Regulation Policies and Section 8.5 - Valley and Stream Corridors of The Living City Policies (LCP) for Planning and Development in the Watersheds of the Toronto and Region Conservation Authority

CFN: 58722 - Application #: 1212/17/VAUG Report Prepared by: Mark Andrews 5936 [email protected] For information contact: June Little 5756 [email protected] Date: October 25, 2017

18 10.2 STANDARD DELEGATED PERMITS

Standard Permits, including Emergency Infrastructure Works permissions, are implemented by Planning and Development Division staff and are received monthly by the Executive Committee. Standard Permits , including Emergency Infrastructure Works permissions, are subject to the authorization of designated staff appointed as Enforcement Officers, as per Authority Res.#A198/13, #A199/13 and #A103/15, respectively. All standard and emergency infrastructure works are non-complex permissions consistent with TRCA approved policies and procedures and issued for a time period of two years of less.

CITY OF MARKHAM

CITY OF MARKHAM - Rouge River Watershed The purpose is to undertake restoration of a section of eroded Robinson creek bank, south of Old Wellington Road, west of Markham Road. The proposed works will include construction of cortex weirs and vegetated layering to stabilize eroding stream banks and channel down cutting in order to protect an existing sanitary line that crosses underneath Robinson Creek. The Ministry of Natural Resources and Forestry(MNRF) Redside dace timing window applies, unless otherwise specified in writing by MNRF.

CFN: 57945 - Application #: 0740/17/MARK Report Prepared by: Harsha Gammanpila, extension 5629, email [email protected] For information contact: Harsha Gammanpila, extension 5629, email [email protected] Date: October 20, 2017

104 BERNBRIDGE ROAD - Rouge River Watershed The purpose is to undertake works within TRCA's Regulated Area of the Rouge River Watershed to facilitate the construction of a walkout basement entrance and staircase located at the rear of the existing single family dwelling.

CFN: 58710 - Application #: 1196/17/MARK Report Prepared by: Aidan Pereira, extension 5723, email [email protected] For information contact: Doris Cheng, extension 5306, email [email protected] Date: October 10, 2017

REGIONAL MUNICIPALITY OF YORK - Rouge River Watershed The purpose is to construct a salt management facility at 10990 Warden Avenue in the City of Markham.

CFN: 58460 - Application #: 1171/17/MARK Report Prepared by: Scott Smith, extension 5758, email [email protected] For information contact: Scott Smith, extension 5758, email [email protected] Date: October 4, 2017

19 22 ROUGE STREET - Rouge River Watershed The purpose is to undertake works within TRCA's Regulated Area of the Rouge River Watershed to in order to facilitate the construction of a 356.06 sq. m. (3832.60 sq. ft.) two-storey replacement dwelling and a 28.71 sq. m. (309.10 sq. ft.) wooden deck on the subject property.

CFN: 58570 - Application #: 1112/17/MARK Report Prepared by: Aidan Pereira, extension 5723, email [email protected] For information contact: Doris Cheng, extension 5306, email [email protected] Date: October 18, 2017

10 COUNTRY ESTATES DRIVE - Rouge River Watershed The purpose is to undertake works within TRCA's Regulated Area to facilitate the construction of a two-storey dwelling, deck, gazebo, swimming pool and basketball court on the subject property.

CFN: 57632 - Application #: 0454/17/MARK Report Prepared by: Aidan Pereira, extension 5723, email [email protected] For information contact: Doris Cheng, extension 5306, email [email protected] Date: October 16, 2017

CITY OF PICKERING

WOODVIEW LAND DEVELOPMENT CORPORATION - Petticoat Creek Watershed The purpose is to carry out topsoil stripping and rough grading for purposes of constructing a new public roadway and associated infrastructure that will service a total of 19 new detached residential dwellings within the Woodview Homes draft approved residential plan of subdivision located on the former residential lots at 1952, 1956 and 1960 Woodview Avenue in the City of Pickering.

CFN: 58598 - Application #: 1134/17/PICK Report Prepared by: Vanessa Aubrey, extension 5662, email [email protected] For information contact: Mark Rapus, extension 5259, email [email protected] Date: October 11, 2017

CITY OF TORONTO (ETOBICOKE YORK COMMUNITY COUNCIL AREA)

82 SOUTH KINGSWAY - Humber River Watershed The purpose is to construct a two storey single family dwelling with integral garage and rear deck at 82 South Kingsway in the City of Toronto (Etobicoke York Community Council Area).

CFN: 58320 - Application #: 0905/17/TOR Report Prepared by: Anna Lim, extension 5284, email [email protected] For information contact: Mark Rapus, extension 5259, email [email protected] Date: October 18, 2017

20 CITY OF TORONTO - Humber River Watershed The purpose is to replace an existing pedestrian bridge at Rowntree Mills Park, located northwest of Islington Avenue and Finch Avenue West. Works will involve removal and replacement of the existing bridge and abutments. The warm water construction timing window of July 1 to March 31 will apply to this proposal.

CFN: 57795 - Application #: 0627/17/TOR Report Prepared by: Daniel Brent, extension 5774, email [email protected] For information contact: Daniel Brent, extension 5774, email [email protected] Date: October 13, 2017

63 KENNEDY PARK ROAD - Humber River Watershed The purpose is to construct an at grade patio and replace the existing one storey addition to the rear of the existing single family dwelling at 63 Kennedy Park Road in the City of Toronto (Etobicoke York Community Council Area).

CFN: 58407 - Application #: 1002/17/TOR Report Prepared by: Anna Lim, extension 5284, email [email protected] For information contact: Mark Rapus, extension 5259, email [email protected] Date: October 5, 2017

57 STORER DRIVE - Humber River Watershed The purpose is to construct a second storey addition above the existing single family dwelling at 57 Storer Drive in the City of Toronto (Etobicoke York Community Council Area).

CFN: 58063 - Application #: 0679/17/TOR Report Prepared by: Anna Lim, extension 5284, email [email protected] For information contact: Mark Rapus, extension 5259, email [email protected] Date: October 17, 2017

51 VAN DUSEN BOULEVARD - Waterfront Watershed The purpose is to construct an inground pool and deck to the rear of an existing single family detached dwelling municipally described as 51 Van Dusen Boulevard in the City of Toronto (Etobicoke York Community Council Area).

CFN: 58180 - Application #: 0780/17/TOR Report Prepared by: Stephanie Worron, extension 5907, email [email protected] For information contact: Mark Rapus, extension 5259, email [email protected] Date: October 19, 2017

75 VALECREST DRIVE - Humber River Watershed The purpose is to construct a two storey single family dwelling with integral garage and rear deck at 75 Valecrest Drive in the City of Toronto (Etobicoke York Community Council Area).

21 CFN: 58340 - Application #: 0919/17/TOR Report Prepared by: Anna Lim, extension 5284, email [email protected] For information contact: Mark Rapus, extension 5259, email [email protected] Date: October 5, 2017

TORONTO COMMUNITY HOUSING - Humber River Watershed The purpose is to construct an accessible ramp, new sidewalk and driveway to the existing 10 storey residential apartment building at 3725 Dundas Street West in the City of Toronto (Etobicoke York Community Council Area).

CFN: 58659 - Application #: 1168/17/TOR Report Prepared by: Anna Lim, extension 5284, email [email protected] For information contact: Mark Rapus, extension 5259, email [email protected] Date: October 13, 2017

CITY OF TORONTO (NORTH YORK COMMUNITY COUNCIL AREA)

77 CHATSWORTH DRIVE - Don River Watershed The purpose is to construct a two storey single family dwelling with integral garage, rear terrace and minor landscaping at 77 Chatsworth Drive in the City of Toronto (North York Community Council Area).

CFN: 56254 - Application #: 0730/16/TOR Report Prepared by: Anna Lim, extension 5284, email [email protected] For information contact: Mark Rapus, extension 5259, email [email protected] Date: October 16, 2017

23 TUDOR GATE - Don River Watershed The purpose is to construct a two storey single family dwelling with integral garage, rear patio and associated hardscaping at 23 Tudor Gate in the City of Toronto (North York Community Council Area).

CFN: 57815 - Application #: 0517/17/TOR Report Prepared by: Anna Lim, extension 5284, email [email protected] For information contact: Mark Rapus, extension 5259, email [email protected] Date: October 4, 2017

125 THREE VALLEY DRIVE - Don River Watershed The purpose is to construct a new single storey solarium to the rear of the existing dwelling located at 125 Three Valleys Drive in the City of Toronto (North York Community Council Area).

CFN: 56752 - Application #: 1126/16/TOR Report Prepared by: Jessica Bester, extension 5250, email [email protected] For information contact: Steve Heuchert, extension 5311, email [email protected] Date: October 13, 2017

22 CITY OF TORONTO (SCARBOROUGH COMMUNITY COUNCIL AREA)

113 SYLVAN AVENUE - Waterfront Watershed The purpose is to construct a two-storey replacement dwelling with integral garage, rear wood deck and basement walk-out at 113 Sylvan Avenue in the City of Toronto (Scarborough Community Council Area).

CFN: 56252 - Application #: 0728/16/TOR Report Prepared by: Jessica Bester, extension 5250, email [email protected] For information contact: Mark Rapus, extension 5259, email [email protected] Date: October 11, 2017

14 JANELLAN TERRACE - Highland Creek Watershed The purpose is to construct a two-storey addition and second storey addition with rear deck to the existing dwelling located at 14 Janellan Terrace in the City of Toronto (Scarborough Community Council Area).

CFN: 57732 - Application #: 0434/17/TOR Report Prepared by: Jessica Bester, extension 5250, email [email protected] For information contact: Mark Rapus, extension 5259, email [email protected] Date: October 11, 2017

1 ROSSFORD ROAD - Don River Watershed The purpose is to construct a rear two-storey addition, second storey addition and rear deck to the existing dwelling with associated landscaping located at 1 Rossford Road in the City of Toronto (Scarborough Community Council Area).

CFN: 58105 - Application #: 0743/17/TOR Report Prepared by: Jessica Bester, extension 5250, email [email protected] For information contact: Mark Rapus, extension 5259, email [email protected] Date: October 18, 2017

SCARBORO GOLF & COUNTRY CLUB - Highland Creek Watershed The purpose is to regrade and realign the 18th tee deck and relocate an existing armour stone retaining wall located at 321 Scarborough Golf Club Road in the City of Toronto (Scarborough Community Council Area).

CFN: 58521 - Application #: 1084/17/TOR Report Prepared by: Stephanie Worron, extension 5907, email [email protected] For information contact: Mark Rapus, extension 5259, email [email protected] Date: October 6, 2017

23 CITY OF TORONTO (TORONTO AND COMMUNITY COUNCIL AREA)

2 NEVILLE PARK BOULEVARD - Waterfront Watershed The purpose is to construct an extension to the existing integral garage and a second storey deck to the existing two storey detached dwelling at 2 Neville Park Boulevard in the City of Toronto (Toronto and East York Community Council Area).

CFN: 56893 - Application #: 1202/16/TOR Report Prepared by: Anna Lim, extension 5284, email [email protected] For information contact: Mark Rapus, extension 5259, email [email protected] Date: October 20, 2017

CITY OF VAUGHAN

1834371 ONTARIO INC. - Humber River Watershed The purpose is to undertake works within TRCA's Regulated Area of the Humber River Watershed in order to facilitate site alteration involving excavation and construction of shoring walls and foundations associated with two (2) multi-unit high rise buildings and associated underground parking. The subject properties are located on lands known municipally as 2951 Highway 7 and 190 and 180 Maplecrete Road, in the City of Vaughan.

CFN: 58010 - Application #: 0686/17/VAUG Report Prepared by: Stephen Bohan, extension 5743, email [email protected] For information contact: June Little, extension 5756, email [email protected] Date: October 10, 2017

29 THORNBANK ROAD - Don River Watershed The purpose is to facilitate, within TRCA's Regulated Area of the Don River watershed, the continued development of a 731.70 sq. m. (7875 sq. ft.) two storey residential dwelling on lands known municipally as 29 Thornbank Road in the City of Vaughan. Development was previously approved under elapsed TRCA permit C-140952 with the current application proposing to complete remaining works.

CFN: 58680 - Application #: 1203/17/VAUG Report Prepared by: Anthony Syhlonyk, extension 5272, email [email protected] For information contact: Colleen Bonner, extension 5307, email [email protected] Date: October 13, 2017

TOWN OF AJAX

CLAREMONT STOREHOUSE INC. - Carruthers Creek Watershed The purpose is to undertake excavation and install site servicing infrastructure on the vacant industrial lot at 285 Achilles Road in the Town of Ajax.

CFN: 58678 - Application #: 1194/17/AJAX Report Prepared by: Vanessa Aubrey, extension 5662, email [email protected] For information contact: Steve Heuchert, extension 5311, email [email protected] Date: October 11, 2017

24 TOWN OF CALEDON

1664380 ONTARIO INCORPORATED - Humber River Watershed The purpose is to backfill the excavation site to pre-existing site conditions and stabilize the soils just south of Highway 9 and west of Glen Haffy Road as a result of the fuel spill that occurred along Highway 9 on March 7, 2017. This permit is in accordance with the TRCA Permission for Emergency Infrastructure Works Review Protocol (Authority Res. #A105/15). No in-water works are associated with this project.

CFN: 57863 - Application #: 0620/17/CAL Report Prepared by: Sharon Lingertat, extension 5717, email [email protected] For information contact: Sharon Lingertat, extension 5717, email [email protected] Date: October 4, 2017

2033665 ONTARIO LIMITED - Humber River Watershed The purpose is to undertake works within TRCA's Regulated Area of the Humber River Watershed in order to facilitate the construction of a proposed 10,930 sq. m (111,650 sq. ft.), 4- storey self storage building associated with a municipal building permit, municipal Site Plan application (Town File No.: SPA 16-0027) and municipal Zoning By-law Amendment application (Town File No.: RZ 16-05).

CFN: 57638 - Application #: 0374/17/CAL Report Prepared by: Anant Patel, extension 5618, email [email protected] For information contact: Anant Patel, extension 5618, email [email protected] Date: October 13, 2017

65 STRAWBERRY HILL COURT - Humber River Watershed The purpose is to undertake works within TRCA's Regulated Area of the Humber River Watershed in order to facilitate the construction of a 3.6 m (12 ft) by 9.1 m (30 ft) in-ground pool and patio area associated with a municipal building permit.

CFN: 58026 - Application #: 0852/17/CAL Report Prepared by: Andrea Terella, extension 5657, email [email protected] For information contact: Andrea Terella, extension 5657, email [email protected] Date: October 23, 2017

TOWN OF CALEDON - Humber River Watershed The purpose is to stabilize an embankment and reconstruct 150 m of Humber Station Road located approximately 850 m south of Castlederg Sideroad in the Town of Caledon. This permit is issued in accordance with TRCA's Permission for Emergency Infrastructure Works Review Protocol (Authority Res. #A105/15). The construction timing window of October 15 to November 30 will apply to this project as per the Ministry of Natural Resources and Forestry (MNRF).

CFN: 58542 - Application #: 1094/17/CAL Report Prepared by: Caroline Mugo, extension 5689, email [email protected] For information contact: Caroline Mugo, extension 5689, email [email protected] Date: October 4, 2017

25 TOWN OF RICHMOND HILL

COGECO PEER 1 - Rouge River Watershed The purpose is to install Cogeco conduit within the existing road right-of-way (ROW) of Leslie Street between Performance Drive and Farnham Road and along the Via Renzo Drive between Ultimate Drive and Performance Drive. The cold water construction timing window of July 1 to September 15 will apply to this proposal.

CFN: 56846 - Application #: 0170/17/RH Report Prepared by: Manirul Islam, extension 5715, email [email protected] For information contact: Manirul Islam, extension 5715, email [email protected] Date: October 16, 2017

LONG BODY HOMES INC. - Rouge River Watershed The purpose is to place and remove fill within a Regulated area to facilitate initial earthworks associated with a new residential plan of subdivision.

CFN: 55953 - Application #: 0497/16/RH Report Prepared by: Quentin Hanchard, extension 5324, email [email protected] For information contact: Quentin Hanchard, extension 5324, email [email protected] Date: October 16, 2017

REGIONAL MUNICIPALITY OF YORK - Humber River Watershed The purpose is to widen Bayview Avenue from a two lane road to a four lane road within the existing road platform, in the Town of Richmond Hill. The proposed works also include on-street bike route and a sidewalk or multi-use path as part of the Lake to Lake trail system. The Ministry of Natural Resources and Forestry (MNRF) Redside Dace timing window does apply to this proposal, unless otherwise specified in writing by MNRF.

CFN: 56822 - Application #: 0004/17/RH Report Prepared by: Harsimrat Pruthi, extension 5744, email [email protected] For information contact: Harsimrat Pruthi, extension 5744, email [email protected] Date: October 23, 2017

12 SUNBAY COURT - Humber River Watershed The purpose is to undertake works within TRCA's Regulated Area of the Humber River Watershed in order to facilitate the construction of a 334.75 sq.m (3,602.9 sq.ft) replacement dwelling associated with a municipal Site Plan application (Town File: D06-17002) and building permit.

CFN: 58707 - Application #: 1190/17/RH Report Prepared by: Nicholas Cascone, extension 5927, email [email protected] For information contact: Nicholas Cascone, extension 5927, email [email protected] Date: October 18, 2017

26 TOWN OF WHITCHURCH-STOUFFVILLE

55 ABBOTSFORD ROAD - Rouge River Watershed The purpose is to facilitate, within TRCA's Regulated Area of the Rouge River Watershed, the continued development of an 880.57 sq. m. (9472 sq. ft.) residence on an estate lot adjacent to the White Rose-Preston Lake Provincially Significant Wetland, on lands known municipally as 55 Abbotsford Road, in the Township of Whitcurch-Stouffville.

CFN: 58683 - Application #: 1209/17/WS Report Prepared by: Anthony Syhlonyk, extension 5272, email [email protected] For information contact: Jackie Burkart, extension 5304, email [email protected] Date: October 16, 2017

TOWNSHIP OF KING

6265 15TH SIDEROAD - Humber River Watershed The purpose is to facilitate, within TRCA's Regulated Area of the Humber River Watershed, the development of a new 230.9 sq. m. (2485 sq. ft.) dwelling, a new 91.5 sq. m. (984.89 sq. ft.) attached garage, and a new driveway with watercourse crossing on lands known municipally as 6265 15th Sideroad, in the Township of King.

CFN: 58705 - Application #: 1197/17/KING Report Prepared by: Anthony Syhlonyk, extension 5272, email [email protected] For information contact: Colleen Bonner, extension 5307, email [email protected] Date: October 17, 2017

TOWNSHIP OF UXBRIDGE

711371 ONTARIO CORP - Duffins Creek Watershed The purpose is to construct an eight (8) lot estate residential subdivision, municipal roadway and storm water management infrastructure.

CFN: 55579 - Application #: 0240/16/UXB Report Prepared by: Steve Heuchert, extension 5311, email [email protected] For information contact: Steve Heuchert, extension 5311, email [email protected] Date: October 13, 2017

PERMISSION FOR ROUTINE INFRASTRUCTURE WORKS

Permission for Routine Infrastructure Works Letter of Approval including Emergency Infrastructure Works permissions are subject to authorization by staff designated as Enforcement Officers as per Auth. Res. #A198/13 and #A103/15, respectively. All routine and emergency infrastructure works are located within a Regulated Area, generally within or adjacent to the hazard or natural feature and in the opinion of staff do not affect the control of flooding, erosion, dynamic beaches, pollution or the conservation of land.

27 CITY OF BRAMPTON

2193914 CANADA LIMITED To undertake sewer, watermain or utility installation or maintenance on the west side of Heart Lake Road south of Sandalwood Parkway, in the City of Brampton, Etobicoke Creek Watershed as located on the property owned by TransCanada Pipelines, who has assigned rights to 2193914 Canada Limited. The purpose is to perform an integrity dig and repair works on an existing gas pipeline. No in-water works are associated with this project.

CFN: 58166 - Application #: 0979/17/BRAM Report Prepared by: Tony To, extension 5798, email [email protected] For information contact: Tony To, extension 5798, email [email protected] Date: October 6, 2017

ROGERS COMMUNICATIONS CANADA INC. To undertake sewer, watermain, utility installation or maintenance within an existing roadway along Queen Street East, west of Airport Road, in the City of Brampton, Mimico Creek Watershed as located on property owned by the City of Brampton. The purpose is to install a 100 mm diameter conduit for Rogers Communication Canada Inc. along Queen Street East, approximately 50 m west of Airport Road, in the City of Brampton. No in-water works are associated with this project.

CFN: 58092 - Application #: 0916/17/BRAM Report Prepared by: Leila Sotoudeh, extension 5925, email [email protected] For information contact: Leila Sotoudeh, extension 5925, email [email protected] Date: October 5, 2017

CITY OF MARKHAM

ENBRIDGE GAS DISTRIBUTION INC. To undertake sewer and watermain or utility installation or maintenance within an existing roadway on the west side of Woodbine Avenue, near 19th Avenue, in the City of Markham, Rouge River Watershed as located on property owned by TransCanada Pipelines, who has assigned rights to Enbridge Gas Distribution Inc. The purpose is to perform an integrity dig and repair works on an existing gas pipeline. No in-water work is associated with this project.

CFN: 58167 - Application #: 0975/17/MARK Report Prepared by: Tony To, extension 5798, email [email protected] For information contact: Tony To, extension 5798, email [email protected] Date: October 5, 2017

28 REGIONAL MUNICIPALITY OF YORK To undertake sewer, watermain or utility watercourse crossing by trenchless technology near 184 Bullock Drive, in the City of Markham, Rouge River Watershed as located on the property owned by City of Markham. The purpose is to replace the existing 600mm Ductile Iron (D.I.) substandard watermain with a new 600mm watermain crossing under the closed bottom culvert through a steel casing near 184 Bullock Drive, in the City of Markham. The existing watermain is proposed to be capped, filled with grout and abandoned. The warm water timing window will apply to this project.

CFN: 58423 - Application #: 0983/17/MARK Report Prepared by: Harsimrat Pruthi, extension 5744, email [email protected] For information contact: Harsimrat Pruthi, extension 5744, email [email protected] Date: October 16, 2017

CITY OF PICKERING

ENBRIDGE PIPELINES INC. To undertake structure maintenance at an Enbridge Pipelines Inc. site, located south of Taunton Road and east of Brock Road, in the City of Pickering, Duffins Creek Watershed as located on property owned by Her Majesty The Queen In Right Of Ontario As Represented By The Minister Of Public Infrastructure with whom Enbridge Pipelines has an easement agreement. The purpose is to undertake two integrity digs to conduct repairs on an existing pipeline at two Enbridge Pipelines Inc. sites (MP1931.6799 and MP1931.7651), located south of Taunton Road and east of Brock Road, in the City of Pickering. The Redside Dace construction timing window applies to this project unless otherwise specified in writing by the Ministry of Natural Resources and Forestry (MNRF).

CFN: 58466 - Application #: 1019/17/PICK Report Prepared by: Leila Sotoudeh, extension 5925, email [email protected] For information contact: Leila Sotoudeh, extension 5925, email [email protected] Date: October 5, 2017

ENBRIDGE PIPELINES INC. To undertake structure maintenance at an Enbridge Pipelines Inc. site, located north of Taunton Road and west of Church Street North, in the City of Pickering, Duffins Creek Watershed as located on property owned by Ontario Land Corporation with whom Enbridge Pipelines has an easement agreement. The purpose is to undertake an integrity dig to conduct repairs on an existing pipeline at an Enbridge Pipelines Inc. site (MP1932.3136), located north of Taunton Road and west of Church Street North, in the City of Pickering. No in-water works are associated with this project.

CFN: 58470 - Application #: 1087/17/PICK Report Prepared by: Leila Sotoudeh, extension 5925, email [email protected] For information contact: Leila Sotoudeh, extension 5925, email [email protected] Date: October 5, 2017

29 CITY OF TORONTO (ETOBICOKE YORK COMMUNITY COUNCIL AREA)

BELL CANADA To undertake sewer, watermain or utility installation or maintenance within an existing roadway on Taysham Crescent, Kipling Avenue, Farr Avenue, 1 Farr Avenue and 143 Taysham Crescent, in the City of Toronto (Etobicoke York Community Council Area), Humber River Watershed, as located on City of Toronto and private property with permission obtained. The purpose is to place conduit. No in-water works are within the scope of this project.

CFN: 56866 - Application #: 1218/16/TOR Report Prepared by: Heather Wright, extension 5766, email [email protected] For information contact: Heather Wright, extension 5766, email [email protected] Date: October 11, 2017

CITY OF TORONTO To undertake road/pathway resurfacing or reconstruction on The Queensway from Etobicoke Creek to Sherway Gardens Road, near The West Mall, in the City of Toronto (Etobicoke York Community Council Area), Etobicoke Creek Watershed as located on property owned by the City of Toronto. The purpose is to undertake road resurfacing and sidewalk construction on The Queensway from Etobicoke Creek to Sherway Gardens Road. The warm water construction timing window of July 1st to March 31st will apply to this proposal.

CFN: 57657 - Application #: 0448/17/TOR Report Prepared by: Heather Wright, extension 5766, email [email protected] For information contact: Heather Wright, extension 5766, email [email protected] Date: October 16, 2017

CITY OF TORONTO To undertake road/pathway resurfacing or reconstruction in High Park located at 1873 Bloor Street West near Keele Street, in the City of Toronto (Etobicoke York Community Council Area), Humber River Watershed as located on property owned by the City of Toronto. The purpose is to undertake repaving of existing pathways in High Park. No in-water work is within the scope of this project.

CFN: 58265 - Application #: 1058/17/TOR Report Prepared by: Heather Wright, extension 5766, email [email protected] For information contact: Heather Wright, extension 5766, email [email protected] Date: October 11, 2017

ROGERS COMMUNICATIONS CANADA INC. To undertake sewer and watermain or utility installation or maintenance within an existing roadway on Albion Road from Golfdown Drive to Omagh Avenue and Omagh Avenue - near Weston Road, in the City of Toronto (Etobicoke York Community Council Area), Humber River Watershed as located on the property owned by City of Toronto. The purpose is to install conduit. No in-water work is within the scope of this project.

30 CFN: 57679 - Application #: 0750/17/TOR Report Prepared by: Heather Wright, extension 5766, email [email protected] For information contact: Heather Wright, extension 5766, email [email protected] Date: October 11, 2017

ROGERS COMMUNICATIONS CANADA INC. To undertake sewer and watermain or utility installation or maintenance within an existing roadway on Dixon Road, west of Islington Avenue, in the City of Toronto (Etobicoke York Community Council Area), Humber River Watershed as located on the property owned by City of Toronto. The purpose is to install conduit. No in-water work is within the scope of this project.

CFN: 58256 - Application #: 1020/17/TOR Report Prepared by: Heather Wright, extension 5766, email [email protected] For information contact: Heather Wright, extension 5766, email [email protected] Date: October 16, 2017

ROGERS COMMUNICATIONS CANADA INC. To undertake sewer, watermain or utility installation or maintenance within an existing roadway on Old Burnhamthorpe Road from Elmcrest Road to Melbert Road in the City of Toronto (Etobicoke York Community Council Area), Etobicoke Creek Watershed as located on property owned by the City of Toronto. The purpose is to install conduit and a vault. No in-water work is within the scope of this project.

CFN: 58263 - Application #: 1022/17/TOR Report Prepared by: Heather Wright, extension 5766, email [email protected] For information contact: Heather Wright, extension 5766, email [email protected] Date: October 6, 2017

CITY OF TORONTO (NORTH YORK COMMUNITY COUNCIL AREA)

CITY OF TORONTO To undertake drainage structure general maintenance on Dufferin Street, located south of Finch Avenue West, in the City of Toronto (North York Community Council Area), Don River Watershed as located on property owned by the City of Toronto. The purpose is to repair cracks in a concrete culvert. The warm water construction timing window of July 1 to March 31 will apply to this project.

CFN: 58261 - Application #: 0992/17/TOR Report Prepared by: Heather Wright, extension 5766, email [email protected] For information contact: Heather Wright, extension 5766, email [email protected] Date: October 17, 2017

31 CITY OF TORONTO (TORONTO AND EAST YORK COMMUNITY COUNCIL AREA)

ROGERS COMMUNICATIONS CANADA INC. To undertake sewer, watermain or utility installation or maintenance within an existing roadway on Lumsden Avenue and Eastdale Avenue, in the City of Toronto (Toronto and East York Community Council Area), Don River Watershed as located on property owned by the City of Toronto. The purpose is to install conduit. No in-water work is within the scope of this project.

CFN: 58255 - Application #: 0861/17/TOR Report Prepared by: Heather Wright, extension 5766, email [email protected] For information contact: Heather Wright, extension 5766, email [email protected] Date: October 6, 2017

CITY OF VAUGHAN

BELL CANADA To undertake sewer and watermain or utility installation or maintenance within an existing roadway on Centre Street, in the City of Vaughan, Don River Watershed as located on the property owned by Regional Municipality of York. The purpose is to undertake installation of Bell conduits within TRCA regulated area along Centre Street, east of Dufferin Street, west of Concord Road, in the City of Vaughan. The installation is required as part of the road widening of Centre Street in order to accommodate the VIVA Bus Rapid Transit (BRT) Project. Installation of the conduits will be carried via open trench and horizontal directional boring.

CFN: 58143 - Application #: 0890/17/VAUG Report Prepared by: Harsha Gammanpila, extension 5629, email [email protected] For information contact: Harsha Gammanpila, extension 5629, email [email protected] Date: October 23, 2017

BELL CANADA To undertake sewer and watermain or utility installation or maintenance within an existing roadway south of Highway 7, east of Highway 400, in the City of Vaughan, Don River Watershed as located on the property owned by the Regional Municipality of York. The purpose is to undertake installation of Bell conduits along the south side of Highway 7, east of Highway 400 in the City of Vaughan. The installation is required as part of the road widening of Highway 7 in order to accommodate the VIVA Rapid Bus Transit Project. Installation of the conduits will be carried out via open trench and horizontal directional boring.

CFN: 58144 - Application #: 0891/17/VAUG Report Prepared by: Harsha Gammanpila, extension 5629, email [email protected] For information contact: Harsha Gammanpila, extension 5629, email [email protected] Date: October 20, 2017

32 ENBRIDGE GAS DISTRIBUTION INC. To undertake sewer, watermain or utility installation or maintenance within an existing right-of- way located at the end of Forest Heights Boulevard, south of Old Humber Crescent, in the City of Vaughan, Humber River Watershed as located on property owned by TransCanada Pipelines, who has assigned rights to Enbridge Gas Distribution Inc. The purpose is to perform an integrity dig in order to inspect an existing natural gas pipeline. No in-water work is associated with this project.

CFN: 57952 - Application #: 0804/17/VAUG Report Prepared by: Tony To, extension 5798, email [email protected] For information contact: Tony To, extension 5798, email [email protected] Date: October 6, 2017

TOWN OF AJAX

ENBRIDGE GAS DISTRIBUTION INC. To undertake sewer, watermain or utility installation or maintenance within a new subdivision at 1870 Altona Road, located south of Pine Grove Avenue and west of Altona Road, in the Town of Ajax, Petticoat Creek Watershed as located on property owned by a private landowner, from whom Enbridge Gas Distribution Inc. is obtaining easements. The purpose is to install NPS 1 1/4 PE IP and NPS 2 PE IP gas header services in order to service a new subdivision, which was approved under a separate TRCA permit (C-170037). No in-water work is associated with this project.

CFN: 58455 - Application #: 1159/17/AJAX Report Prepared by: Tony To, extension 5798, email [email protected] For information contact: Tony To, extension 5798, email [email protected] Date: October 5, 2017

TOWN OF AJAX To undertake structure maintenance on pedestrian bridge 109 located just east of Westney Road near Noake Crescent and pedestrian bridge 107 located east of Westney Road near Cornwall Drive, in the Town of Ajax, Duffins Creek Watershed as located on the property owned by Town of Ajax. The purpose is to rehabilitate two pedestrian bridges in the Town of Ajax. The first bridge (109) is located just east of Westney Road near Noake Crescent and the second bridge (107) is located east of Westney Road near Cornwall Drive. The warm water construction timing window will be applied to this project.

CFN: 58439 - Application #: 1059/17/AJAX Report Prepared by: Caroline Mugo, extension 5689, email [email protected] For information contact: Caroline Mugo, extension 5689, email [email protected] Date: October 24, 2017

33 TRANS-NORTHERN PIPELINES INC. (TNPI) To undertake structure maintenance on an existing pipeline at a Trans-Northern Pipeline Inc. (TNPI) site (MP-312.86-2017), located south of 5th Concession Road and west of Salem Road North, in the Town of Ajax, Duffins Creek Watershed as located on property owned by a private landowner with access granted through a permission to enter. The purpose is to undertake an integrity dig to conduct repairs on an existing pipeline at a Trans-Northern Pipeline Inc. (TNPI) site (MP-312.86-2017), located south of 5th Concession Road and west of Salem Road, in the Town of Ajax. No in-water work is associated with this project.

CFN: 58469 - Application #: 1076/17/AJAX Report Prepared by: Leila Sotoudeh, extension 5925, email [email protected] For information contact: Leila Sotoudeh, extension 5925, email [email protected] Date: October 6, 2017

TOWN OF RICHMOND HILL

ROGERS COMMUNICATIONS CANADA INC. To undertake sewer and watermain or utility watercourse crossing by trenchless technology on Major Mackenzie Drive East crossing Beaver Creek near Spadina Road, in the Town of Richmond Hill, Rouge River Watershed as located on the property owned by the Regional Municipality of York. The purpose is to install two 4 inch underground conduits on the south side of Major Mackenzie Drive East near Spadina Road in the Town of Richmond Hill. The warm water construction timing window will apply to this project..

CFN: 58160 - Application #: 0971/17/RH Report Prepared by: Christine Furtado, extension 5310, email [email protected] For information contact: Christine Furtado, extension 5310, email [email protected] Date: October 6, 2017

TOWN OF WHITCHURCH-STOUFFVILLE

TOWN OF WHITCHURCH-STOUFFVILLE To undertake sewer and watermain or utility installation or maintenance within an existing roadway on 8 Park Drive, from Main Street and Mill Street, in the Town of Whitchurch- Stouffville, Duffins Creek Watershed as located on the property owned by Town of Whitchurch- Stouffville. The purpose is to install a conduit adjacent to 8 Park Drive in the Town of Whitchuch-Stouffville, Duffins Creek watershed on property owned by the Town of Whitchurch- Stouffville.

CFN: 58158 - Application #: 0993/17/WS Report Prepared by: Christine Furtado, extension 5310, email [email protected] For information contact: Christine Furtado, extension 5310, email [email protected] Date: October 16, 2017

34 TOWN OF WHITCHURCH-STOUFFVILLE To undertake sewer and watermain or utility crossing by trenchless technology on 6240 Main Street, near Park Drive and Mill Street, in the Town of Whitchurch-Stouffville, Duffins Creek Watershed as located on the property owned by Town of Whitchurch-Stouffville. The purpose is to install an underground conduit at 6240 Main Street in the Town of Whitchurch-Stouffville..

CFN: 58159 - Application #: 0994/17/WS Report Prepared by: Christine Furtado, extension 5310, email [email protected] For information contact: Christine Furtado, extension 5310, email [email protected] Date: October 24, 2017

MINOR WORKS LETTER OF APPROVAL

Permission for Minor Works Letter of Approval are implemented by Planning and Development Division staff and are received monthly by the Executive Committee. The permission of minor works is subject to authorization by the Director, Planning and Development and signed by an appointed enforcement officer. All minor works are located within a Regulated Area, outside of the flood plain and in the opinion of staff do not affect the control of flooding, erosion, dynamic beaches, pollution or the conservation of land.

CITY OF BRAMPTON

25 FORESTGROVE CIRCLE To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 24, Plan, 25 Forestgrove Circle, in the City of Brampton, Etobicoke Creek Watershed.

CFN: 58602 - Application #: 1145/17/BRAM Report Prepared by: Andrea Terella, extension 5657, email [email protected] For information contact: Andrea Terella, extension 5657, email [email protected] Date: October 4, 2017

CITY OF MARKHAM

11 ROCKINGHAM COURT To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on , (11 Rockingham Court), in the City of Markham, Don River Watershed.

CFN: 58691 - Application #: 1228/17/MARK Report Prepared by: Aidan Pereira, extension 5723, email [email protected] For information contact: Doris Cheng, extension 5306, email [email protected] Date: October 19, 2017

CITY OF PICKERING

2306 SOUTHCOTT ROAD To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 10, Plan 40M-2344, (2306 Southcott Road), in the City of Pickering, Duffins Creek Watershed.

35 CFN: 58574 - Application #: 1115/17/PICK Report Prepared by: Stephanie Worron, extension 5907, email [email protected] For information contact: Steve Heuchert, extension 5311, email [email protected] Date: October 10, 2017

CITY OF TORONTO (ETOBICOKE YORK COMMUNITY COUNCIL AREA)

33 EDGEHILL ROAD To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Part Lot 12, Concession C, (33 Edgehill Road), in the City of Toronto (Etobicoke York Community Council Area), Humber River Watershed as located on the property owned by Gareth and Celeste Brennan.

CFN: 58739 - Application #: 1236/17/TOR Report Prepared by: Anna Lim, extension 5284, email [email protected] For information contact: Mark Rapus, extension 5259, email [email protected] Date: October 20, 2017

53 THICKET ROAD To undertake minor landscaping involving the placement, removal or regrading of material of less than 30 cubic metres (equivalent to 3 truckloads) and construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 66, Plan M-1097, (53 Thicket Road), in the City of Toronto (Etobicoke York Community Council Area), Etobicoke Creek Watershed.

CFN: 58706 - Application #: 1191/17/TOR Report Prepared by: Anna Lim, extension 5284, email [email protected] For information contact: Mark Rapus, extension 5259, email [email protected] Date: October 17, 2017

48 RIDGEVALLEY CRESCENT To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 22, Plan 258, (48 Ridgevalley Crescent), in the City of Toronto (Etobicoke York Community Council Area), Humber River Watershed.

CFN: 58543 - Application #: 1093/17/TOR Report Prepared by: Anna Lim, extension 5284, email [email protected] For information contact: Steve Heuchert, extension 5311, email [email protected] Date: October 10, 2017

CITY OF TORONTO (TORONTO AND EAST YORK COMMUNITY COUNCIL AREA)

17 BERKSHIRE AVENUE To change the use, size, or number of dwelling units of a structure, or undertake work that does not change the footprint of the existing structure on Lot 78, 79, Plan M-445, (17 Berkshire Avenue), in the City of Toronto (Toronto and East York Community Council Area), Don River Watershed.

36 CFN: 58401 - Application #: 0965/17/TOR Report Prepared by: Anna Lim, extension 5284, email [email protected] For information contact: Steve Heuchert, extension 5311, email [email protected] Date: October 16, 2017

CITY OF VAUGHAN

51 GLEN SHIELD AVENUE To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on , (51 Glen Shield Avenue), in the City of Vaughan, Don River Watershed.

CFN: 58716 - Application #: 1202/17/VAUG Report Prepared by: Anthony Syhlonyk, extension 5272, email [email protected] For information contact: Colleen Bonner, extension 5307, email [email protected] Date: October 17, 2017

166 HEINTZMAN CRESCENT To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 55, Plan 65M-4266, (166 Heintzman Crescent), in the City of Vaughan, Don River Watershed.

CFN: 58686 - Application #: 1211/17/VAUG Report Prepared by: Anthony Syhlonyk, extension 5272, email [email protected] For information contact: Colleen Bonner, extension 5307, email [email protected] Date: October 20, 2017

166 FARRELL ROAD To install a swimming pool, undertake minor landscaping involving the placement, removal or regrading of material of less than 30 cubic metres (equivalent to 3 truckloads) and construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 90, Plan 65M-4425, (166 Farrell Road), in the City of Vaughan, Don River Watershed.

CFN: 57980 - Application #: 1166/17/VAUG Report Prepared by: Anthony Syhlonyk, extension 5272, email [email protected] For information contact: Colleen Bonner, extension 5307, email [email protected] Date: October 5, 2017

TOWN OF AJAX

29 ANGIER CRESCENT To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Part Block 9, Plan 40M2136, (29 Angier Crescent), in the Town of Ajax, Carruthers Creek Watershed.

CFN: 58585 - Application #: 1096/17/AJAX Report Prepared by: Stephanie Worron, extension 5907, email [email protected] For information contact: Steve Heuchert, extension 5311, email [email protected] Date: October 10, 2017

37 4 DUCKFIELD CRESCENT To undertake minor landscaping involving the placement, removal or regrading of material of less than 30 cubic metres (equivalent to 3 truckloads) and construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 2, Plan 40M02239, (4 Duckfield Crescent), in the Town of Ajax, Carruthers Creek Watershed.

CFN: 58577 - Application #: 1119/17/AJAX Report Prepared by: Stephanie Worron, extension 5907, email [email protected] For information contact: Steve Heuchert, extension 5311, email [email protected] Date: October 19, 2017

35 ANGIER CRESCENT To undertake minor landscaping involving the placement, removal or regrading of material of less than 30 cubic metres (equivalent to 3 truckloads) and construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 1067, PART 43, Block 10, Plan 40M-2136, (35 Angier Crescent), in the Town of Ajax, Carruthers Creek Watershed.

CFN: 58594 - Application #: 1136/17/AJAX Report Prepared by: Stephanie Worron, extension 5907, email [email protected] For information contact: Steve Heuchert, extension 5311, email [email protected] Date: October 6, 2017

59 ANGIER CRESCENT To undertake minor landscaping involving the placement, removal or regrading of material of less than 30 cubic metres (equivalent to 3 truckloads) and construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 31, Plan 40M2136, (59 Angier Crescent), in the Town of Ajax, Carruthers Creek Watershed.

CFN: 57981 - Application #: 1183/17/AJAX Report Prepared by: Stephanie Worron, extension 5907, email [email protected] For information contact: Steve Heuchert, extension 5311, email [email protected] Date: October 12, 2017

TOWN OF CALEDON

135 CONNAUGHT CRESCENT To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 37, Plan 887, 135 Connaught Crescent, in the Town of Caledon, Humber River Watershed.

CFN: 58596 - Application #: 1132/17/CAL Report Prepared by: Anant Patel, extension 5618, email [email protected] For information contact: Anant Patel, extension 5618, email [email protected] Date: October 11, 2017

38 TOWNSHIP OF KING

24 RICHARD SERRA COURT To install a swimming pool, undertake minor landscaping involving the placement, removal or regrading of material of less than 30 cubic metres (equivalent to 3 truckloads), construct a non- habitable accessory structure up to 50 sq. m (538 sq. ft) and construct a ground floor addition or structure greater than 50 sq. m (538 sq. ft) but less than 150 sq. m (1614 sq. ft) on Lot 9, Plan 65M-4271, (24 Richard Serra Court), in the Township of King, Humber River Watershed.

CFN: 58674 - Application #: 1180/17/KING Report Prepared by: Anthony Syhlonyk, extension 5272, email [email protected] For information contact: Colleen Bonner, extension 5307, email [email protected] Date: October 10, 2017

1196 - 15TH SIDEROAD To construct a non-habitable accessory structure up to 50 sq. m (538 sq. ft) on Lot 5, Plan 522, (1196 - 15th Sideroad), in the Township of King, Humber River Watershed.

CFN: 58668 - Application #: 1189/17/KING Report Prepared by: Anthony Syhlonyk, extension 5272, email [email protected] For information contact: Colleen Bonner, extension 5307, email [email protected] Date: October 13, 2017

10 SIM HILL CRESCENT To install a swimming pool and undertake minor landscaping involving the placement, removal or regrading of material of less than 30 cubic metres (equivalent to 3 truckloads) on Lot 32, Plan 65M-4277, (10 Sim Hill Crescent), in the Township of King, Humber River Watershed.

CFN: 58658 - Application #: 1163/17/KING Report Prepared by: Anthony Syhlonyk, extension 5272, email [email protected] For information contact: Colleen Bonner, extension 5307, email [email protected] Date: October 5, 2017

39 PERMIT APPLICATIONS 10.3 – 10.6 ARE MAJOR APPLICATION - REGULAR

Applications that involved a more complex suite of technical studies to demonstrate consistency with policies; applications that cover a significant geographic area (e.g. subdivisions, stormwater management ponds), extensive modifications to the landscape, major infrastructure projects, emergency infrastructure works, resolution of violations/after the fact permits, trail construction.

CITY OF MARKHAM

10.3 2585231 ONTARIO INC. To site grade, temporarily or permanently place, dump or remove any material, originating on the site or elsewhere and alter a watercourse on Lot 20, Concession 8, (9999 Highway 48 (Markham Road)), in the City of Markham, Rouge River Watershed as located on the property owned by 2585231 Ontario Inc.. The purpose is to alter a waterway and conduct grading works within a Regulated Area of the Rouge river Watershed in order to realign and naturalize a stretch of Exhibition Creek at 9999 Highway 48, in the City of Markham.

The permit will be issued for the period of November 3, 2017 to November 2, 2019 in accordance with the following documents and plans which form part of this permit:

 Drawing 1 of 6, General Construction Design, prepared by Greck and Associates Limited, dated July 15, 2015, revised March 31, 2016, stamped received by TRCA Planning and Development October 23, 2017;  Drawing 2 of 6, Erosion and Sediment Control Details, prepared by Greck and Associates Limited, dated July 15, 2015, revised March 31, 2016, stamped received by TRCA Planning and Development October 23, 2017;  Drawing 3 of 6, Construction and ESC Plan Phase 1, prepared by Greck and Associates Limited, dated July 15, 2015, revised March 31, 2016, stamped received by TRCA Planning and Development October 23, 2017;

40  Drawing 4 of 6, Construction and ESC Plan Phase 2, prepared by Greck and Associates Limited, dated July 15, 2015, revised March 31, 2016, stamped received by TRCA Planning and Development October 23, 2017;  Drawing 5 of 6, Construction and ESC Plan Phase 3, prepared by Greck and Associates Limited, dated July 15, 2015, revised March 31, 2016, stamped received by TRCA Planning and Development October 23, 2017;  Drawing 6 of 6, ESC Plan and Demobilization Phase 4, prepared by Greck and Associates Limited, dated July 15, 2015, revised March 31, 2016, stamped received by TRCA Planning and Development October 23, 2017;  Sheet No. LD-100, Landscape Details, prepared by Terraplan Landscape Architects, dated December 1, 2011, revised April 4, 2016, stamped received by TRCA Planning and Development October 23, 2017;  Sheet No. LD-101, Landscape Details, prepared by Terraplan Landscape Architects, dated December 1, 2011, revised April 4, 2016, stamped received by TRCA Planning and Development October 23, 2017;  Sheet No. LS-100, Creek Restoration Landscape Plan, prepared by Terraplan Landscape Architects, dated December 1, 2011, revised April 4, 2016, stamped received by TRCA Planning and Development October 23, 2017;  Sheet No. LS-101, Creek Restoration Sections, prepared by Terraplan Landscape Architects, dated December 1, 2011, revised April 4, 2016, stamped received by TRCA Planning and Development October 23, 2017.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The purpose is to alter the alignment of a portion of Exhibition Creek to attenuate flooding issues affecting the subject property and significantly improve flood water conveyance, storage, and the overall ecology of the creek, associated with a municipal site alteration and grading permit. The subject property is located at the south east corner of Highway 48 (Markham Road) and Major Mackenzie Drive East. The site contains a highly degraded and altered portion of Exhibition Creek.

Based upon updated floodplain modeling of the Rouge River Watershed, it was determined that due to the highly constrained channel of Exhibition Creek, the channel does not contain the Regional Floodplain. Furthermore, due to the perched culvert downstream of the site, the flood waters overtops the banks of the existing channel, resulting in approximately 4 hectares of the 12.9 hectare property to be encumbered by flood waters during a Regional Flood event.

In 2011, in preparation for redevelopment, the previous landowner authorized the demolition of the structures on the site and filled in an on-site stormwater management pond, and placed various fill piles on the property within regulated areas. TRCA issued a violation on the property on October 31, 2011 (Violation #2605) and subsequently on September 24, 2012 (Violation #V2670) for additional unauthorized works which resulted in adverse impacts to the Exhibition Creek corridor, including heavy sediment load entering into the natural system.

In 2012, the landowner at that time appealed to the OMB for non-decision. TRCA requested the Board refrain scheduling a hearing until such time as the violations under the Conservation Authorities Act have been resolved, which was granted.

41 TRCA staff worked with the previous owner to resolve the outstanding violations by providing a restoration plan and re-alignment of Exhibition Creek. The proposed channel realignment is based upon natural channel design principles containing meanders and a new valley wall within 1 hectare of the overall property. The works include increasing the overall width of channel to a corridor ranging from 18-70 metres at the widest section. The plan has been revised since the original permit approval (C-160533) to be entirely contained on this property. The original landowner has since sold the property and the current owner wishes to proceed with the works. As such, the works remain the same, however the permit will be issued to the new owner.

Upon completion, the proposed works will provide significant improvements to the existing corridor, ensuring flood storage and conveyance of floodwaters will be contained within the new channel. The channel will be restored with native, non-invasive plantings, providing an overall ecological benefit for the natural heritage system of this portion of Exhibition Creek. These works will complement the recent completion of another restoration, realignment and enhancement of an upstream section of the same corridor located at 9900 Highway 48 (C- 150828).

The enhanced Exhibition Creek corridor will be required to be conveyed into public ownership as a condition of the future development approvals under the Planning Act.

Control of Flooding: TRCA Water Resource Engineering Staff are satisfied that the proposed channel has been adequately sized to contain and improve flood water conveyance and storage in the area. As such, TRCA staff concur with the consultants' report that the works will not have adverse upstream and downstream impacts.

Pollution: Appropriate sediment and erosion control measures will be put in place and maintained during all phases of construction.

Dynamic Beaches: Not applicable

Erosion: All new valley wall slopes will be constructed at stable slopes and will be vegetated. As such, there are no geotechnical issues anticipated with this application.

Conservation of Land: The existing watercourse is currently in a highly constrained and degraded state. No significant vegetation will be removed through the proposed works. The works will take place within the warm water fisheries timing window (July 1 to March 31).

Plantings A restoration planting plan is included as part of the proposed works. This plan will substantially improve the ecology of the restored and realigned watercourse and will also provide a buffer between the natural feature and the future development lands. The planting plan is composed of native, non-invasive plantings consistent with TRCA Guidelines.

42 Policy Guidelines: This proposal complies with Section 8.8 Interference with a Watercourse of The Living City Policies for Planning and Development in the Watersheds of the Toronto and Region Conservation Authority.

CFN: 58731 - Application #: 1273/17/MARK Report Prepared by: Doris Cheng 5306 [email protected] For information contact: Doris Cheng 5306 [email protected] Date: October 31, 2017

43 TOWN OF CALEDON

10.4 BOLTCOL HOLDINGS NORTH INC. AND BOLTCOL HOLDINGS SOUTH INC. To construct, reconstruct, erect or place a building or structure, site grade and alter a watercourse on Part Lot 2, 3, Concession 5 ALBION Part 1, Part 2 Plan 43R33412, (0 Coleraine Drive and 12300 Coleraine Drive), in the Town of Caledon, Humber River Watershed as located on the property owned by Boltcol Holdings North Inc. and Boltcol Holdings South Inc.. The purpose is to grade, remove and place fill, and construct within a Regulated Area to facilitate the construction of a stormwater management pond associated with a large format employment land site plan application.

The permit will be issued for the period of November 3, 2017 to November 2, 2019 in accordance with the following documents and plans which form part of this permit:

 Letter of Undertaking provided by Derek Boyne, Vice President, Development and Construction, Triovest, dated Oct. 31, 2017, to address all outstanding TRCA requirements prior to issuance of the permit, and received by the TRCA on Oct. 31, 2017.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The subject property is one of two large format employment blocks within the Coleraine West Employment area, located west of Coleraine Drive, north of Mayfield Road, in the Town of Caledon. The Coleraine West employment area is a new employment area in Caledon, located to the west of the existing south Bolton employment lands.

44 The Town of Caledon has recently approved a secondary plan for the Coleraine West area, which provides for Caledon’s employment lands growth targets within the current planning horizon. The Ontari Ltd. lands to the north and the subject lands constitute the majority of the lands within the Coleraine West Secondary Planning area.

Planning for the Coleraine West Employment area has been a comprehensive, multi-year process, which has involved a Regional Official Plan amendment for the urban boundary expansion, as well as a local Official Plan amendment for the Coleraine West Secondary Plan, and a comprehensive Zoning by-law amendment. In the initial stages of this process, the Town retained consultants to complete a Comprehensive Environmental Impact Study and Management Plan (CEISMP). The CEISMP identified the need for additional analysis to be completed in support of individual development applications. This work has been completed collaboratively by Ontari and Boltcol, as an integrated assessment in support of the Zoning by- law amendment (ZBA) for Coleraine West. TRCA staff was involved in the CEISMP process as well as in the review of the Ontari and Boltcol ZBA submission. More detailed analysis will be required in support of the future site-specific site plan applications for these properties.

The subject property is traversed by the Clarkway Drive Tributary – a tributary of the West Humber River, which contains a Provincially Significant Wetland. The main corridor and appropriate buffers have been protected and excluded from the lands for development, and an appropriate strategy has been devised with respect to the treatment of lower order headwater drainage features, and the enhancement of the system. A headwater drainage feature that conveys flow from the existing industrial lands to the north-east, to the main branch of the Clarkway Drive Tributary will be realigned within a new natural channel. A previous permit issued by the TRCA (i.e. Permit C-170019) permitted the construction of the new natural channel; however, the existing drainage feature cannot be taken off-line until a storm sewer pipe is installed along Coleraine Drive that will divert the flows to the new channel. The earth works required to facilitate the modifications to the watercourses on the subject lands have been approved under separate permits.

The purpose of this subject permit is to construct the stormwater management pond on the site. A pre-grading and servicing agreement between the applicant and the Town of Caledon will also be required to facilitate these works. Additional permits will be required for the construction of the buildings and final servicing on the site.

A separate permit report to facilitate the site grading, modifications to the existing headwater drainage features, a cut and fill balance and construction of a 1350 mm storm sewer diversion pipe on the subject lands is also on the November 17, 2017 TRCA Executive Committee agenda for approval.

Control of Flooding: No impacts on the storage or conveyance of floodwaters are anticipated.

Pollution: Sediment and erosion control measures will be installed and maintained throughout construction to prevent sediment from migrating from the portion of the site on which the development is being completed.

Dynamic Beaches: Not applicable

45 Erosion: There are no existing geotechnical/slope stability issues associated with this site. In addition, the implementation of the aforementioned sediment and erosion control measures will minimize erosion on the site.

Conservation of Land: A landscaping plan has been submitted for the stormwater management pond.

Plantings All plantings will be native, non-invasive species as per TRCA's guidelines. Furthermore, disturbed areas will be seeded with native seed mix as a means of erosion control.

Policy Guidelines: This proposal is consistent with Section 8.4, General Regulation Policies; 8.8, Interference with a Watercourse; and 8.12, Fill Placement, Excavation and/or Grade Modification Policies of The Living City Policies for Planning and Development in the Watersheds of the Toronto and Region Conservation Authority.

CFN: 56927 - Application #: 0032/17/CAL Report Prepared by: Leilani Lee-Yates 5370 [email protected] For information contact: Leilani Lee-Yates 5370 [email protected] Date: November 1, 2017

46 TOWN OF CALEDON

10.5 BOLTCOL HOLDINGS NORTH INC. AND BOLTCOL HOLDINGS SOUTH INC. To site grade, temporarily or permanently place, dump or remove any material, originating on the site or elsewhere and alter a watercourse on Part Lot 2, 3, Concession 5 ALBION Part 1, Part 2 Plan 43R33412, (0 Coleraine Drive and 12300 Coleraine Drive), in the Town of Caledon, Humber River Watershed as located on the property owned by Boltcol Holdings North Inc. and Boltcol Holdings South Inc.. The purpose is to grade, remove and place fill, and construct within a Regulated Area to facilitate site grading, watercourse realignment works and installation of a storm sewer pipe associated with a large format employment land site plan application.

The permit will be issued for the period of November 3, 2017 to November 2, 2019 in accordance with the following documents and plans which form part of this permit:

 Letter of Undertaking provided by Derek Boyne, Vice President, Development and Construction, Triovest, dated Oct. 31, 2017, to address all outstanding TRCA requirements prior to issuance of the permit, and received by the TRCA on Oct. 31, 2017.

RATIONALE The application was reviewed by staff on the basis of the following information:

Proposal: The subject property is one of two large format employment blocks within the Coleraine West Employment area, located west of Coleraine Drive, north of Mayfield Road, in the Town of Caledon. The Coleraine West employment area is a new employment area in Caledon, located to the west of the existing south Bolton employment lands.

47 The Town of Caledon has recently approved a secondary plan for the Coleraine West area, which provides for Caledon’s employment lands growth targets within the current planning horizon. The Ontari Ltd. lands to the north and the subject lands constitute the majority of the lands within the Coleraine West Secondary Planning area.

Planning for the Coleraine West Employment area has been a comprehensive, multi-year process, which has involved a Regional Official Plan amendment for the urban boundary expansion, as well as a local Official Plan amendment for the Coleraine West Secondary Plan, and a comprehensive Zoning by-law amendment. In the initial stages of this process, the Town retained consultants to complete a Comprehensive Environmental Impact Study and Management Plan (CEISMP). The CEISMP identified the need for additional analysis to be completed in support of individual development applications. This work has been completed collaboratively by Ontari and Boltcol, as an integrated assessment in support of the Zoning by- law amendment (ZBA) for Coleraine West. TRCA staff was involved in the CEISMP process as well as in the review of the Ontari and Boltcol ZBA submission. More detailed analysis will be required in support of the future site-specific site plan applications for these properties.

The subject property is traversed by the Clarkway Drive Tributary – a tributary of the West Humber River, which contains a Provincially Significant Wetland. The main corridor and appropriate buffers have been protected and excluded from the lands for development, and an appropriate strategy has been devised with respect to the treatment of lower order headwater drainage features, and the enhancement of the system. A headwater drainage feature that conveys flow from the existing industrial lands to the north-east, to the main branch of the Clarkway Drive Tributary will be realigned within a new natural channel. A previous permit issued by the TRCA (i.e. Permit C-170019) permitted the construction of the new natural channel; however, the existing drainage feature cannot be taken off-line until a storm sewer pipe is installed along Coleraine Drive that will divert the flows to the new channel. There is a second headwater drainage feature to the south of the realigned channel, that the CEISMP concluded could be removed provided that the existing flows are maintained through the stormwater management strategy.

The purpose of this subject permit is to site grade, install a 1350 mm storm sewer pipe to divert flows to the new natural channel, and a cut and bill balance to facilitate the removal of the southern headwater drainage feature. A pre-grading and servicing agreement between the applicant and the Town of Caledon will also be required to facilitate these works. Additional permits will be required for the construction of the buildings and final servicing on the site.

A separate permit report to facilitate the construction of the stormwater management pond on the subject lands is also on the November 17, 2017 TRCA Executive Committee agenda for approval

Control of Flooding: A cut and fill balance analysis for the modifications to the Clarkway Drive Tributary and associated headwater drainage feature has been completed to the satisfaction of the TRCA. As such, no impacts on the storage or conveyance of floodwaters are anticipated.

Pollution: Sediment and erosion control measures will be installed and maintained throughout construction to prevent sediment from migrating from the portion of the site on which the development is being completed.

48 Dynamic Beaches: Not applicable

Erosion: There are no existing geotechnical/slope stability issues associated with this site. In addition, the implementation of the aforementioned sediment and erosion control measures will minimize erosion on the site.

Conservation of Land: All significant natural areas have been previously set aside for long-term protection, and will be dedicated into public ownership. The proposed works are only within the lands that have been designated for development in the Town's Official Plan and amended Zoning By-law.

Plantings All disturbed areas will be seeded with native seed mix as a means of erosion control.

Policy Guidelines: This proposal is consistent with Section 8.4, General Regulation Policies; 8.8, Interference with a Watercourse; and 8.12, Fill Placement, Excavation and/or Grade Modification Policies of The Living City Policies for Planning and Development in the Watersheds of the Toronto and Region Conservation Authority.

CFN: 56928 - Application #: 0033/17/CAL Report Prepared by: Leilani Lee-Yates 5370 [email protected] For information contact: Leilani Lee-Yates 5370 [email protected] Date: November 1, 2017

49 TOWN OF RICHMOND HILL

10.6 MATTAMY HOMES (ELGIN MILLS) LIMITED To site grade, temporarily or permanently place, dump or remove any material, originating on the site or elsewhere and interfere with a wetland on Part Lot 27, 28, Concession 2, (Leslie Street and Elgin Mills Road East), in the Town of Richmond Hill, Rouge River Watershed as located on the property owned by Mattamy Homes (Elgin Mills) Limited. The purpose is to undertake works within a TRCA Regulated Area of the Rouge River Watershed in order to facilitate Phase 2 topsoil stripping, stockpiling, site alteration and grading, import large volumes of fill and implement sediment and erosion control measures in support of an approved draft plan of subdivision, associated with a municipal building permit..

The permit will be issued for the period of November 3, 2017 to November 2, 2019 in accordance with the following documents and plans which form part of this permit:

 Letter of Undertaking, prepared by Fran Bon, ASO of Mattamy Homes, dated October 30, 2017, committing to satisfy TRCA's outstanding comments for all applicable reports and permit drawing prior to final issuance of the permit.

RATIONALE The application was reviewed by staff on the basis of the following information:

50 Proposal: The purpose is to undertake works within a TRCA Regulated Area of the Rouge River Watershed in order to facilitate Phase 2 topsoil stripping and stockpiling, site alteration and grading, import large volumes of fill, and to implement revised sediment and erosion control measures in support of the approved draft plan of subdivision, associated with a municipal building permit. The subject property is located north of Elgin Mills Road East, west of Leslie Street and south of 19th Avenue, in the Town of Richmond Hill. Located in the North Leslie Secondary Plan Area, the Master Environmental Servicing Plan (MESP) for North Leslie (west of Leslie Street) was reviewed and approved in principle by TRCA staff on October 9, 2015.

The proposed works includes establishing the rough grades for Phase 2 works of the draft plan of subdivision, which involves the importing of fill to the site and amending the sediment and erosion controls as necessary. The Phase 2 grading works include the lands that were excluded from the Phase 1 grading works (TRCA Permit C-170680) including the area of grade transition from the tableland to the natural heritage system and stormwater management blocks. The grade transition includes some minor grading into the future buffer to the natural heritage system for the purposes of stormwater management infrastructure in accordance with Town approvals. Due to the extent of the grade transition, additional grading into the buffer is required to match the proposed grade to existing. As such, the applicant is proposing an overall net benefit by providing a net gain of land conveyance (to be added to the natural heritage system) which will be conveyed to the Town, in combination with limited height retaining walls (maximum of 2 metres high). The additional lands will be planted and restored with native, self sustaining vegetation. Once the works are completed, the sediment and erosion control measures will continue to remain in place and be maintained until the construction of the subdivision is complete. As the review of the grading plans remain ongoing, the owner has agreed through a letter of undertaking to satisfy all requirements in accordance to the conditions of draft approval, and to complete all reports and drawings to the satisfaction of staff prior to issuing the permit.

Control of Flooding: The proposed works are located on tableland, but are regulated due to its proximity to the area of interference of a Provincially Significant Wetland. As such, there are no anticipated impacts related to flood control or flood conveyance as a result of the proposed works.

Pollution: Appropriate sediment and erosion control measures are to be installed prior to, and maintained during all phases of construction. In addition, a comprehensive monitoring plan has been included in the Environmental Management Plan to undertake ongoing monitoring of the wetland and watercourses.

Dynamic Beaches: Not applicable

Erosion: Due to the dynamic hydrogeological conditions within North Leslie, this site (as with all sites in North Leslie) is subject to large volumes of fill to bring the overall grading above the elevation of the groundwater. This results in the need to undertake grade transitions from the proposed to the existing grades. As such, the proposed works includes the construction of an engineered slope that transitions from the residential lots to the limit of the natural heritage system and/or stormwater management ponds. This grade transition has been accommodated through a combination of engineered slopes ranging from 3:1 to 2:1 and retaining walls, to the satisfaction of the TRCA and the Town.

51 Conservation of Land: The site has been historically used as active farmland. As such, there is no significant vegetation to be removed as a result of Phase 2 works. Furthermore, this phase does not contain any in-water works, and as such, there are no fisheries related impacts anticipated with the proposed works associated with these works.

Plantings Due to the nature of the construction phasing, this permit will include the planting and restoration of all environmental buffers. All planting and restoration works will be required for the plan of subdivision, with the exception of the stormwater management ponds. All restoration and planting plans for the ponds will be included with the respective permits.

Policy Guidelines: This proposal is consistent with Section 8.4 - General Regulation Policies of the Living City Policies for Planning and Development in the Watersheds of the TRCA.

CFN: 58743 - Application #: 1267/17/RH Report Prepared by: Doris Cheng 5306 [email protected] For information contact: Doris Cheng 5306 [email protected] Date: November 1, 2017

52