REPORT ON HEARINGS
NAMEW LAKE MINE/MILL
THE CLEAN ENVIRONMENT COMMISSION
SEPTEMBER 12, 1989
THE BACKGROUND
CITIZEN
HUDSON
A.
Manitoba Manitoba
AND
BAY
The
OTHER
Mine The Depressurizing/Dewatering General Wasterock Mill Tailings Depressurizing/Dewatering
Storage Noise sewage Dust Freshwater Solid Ca) Questions Effluent Cc) Cd) Ce) Cb)
Mr. Mr. Ms. Mr. Mr. Mr. Mr. Mr. Mr.
MINING
Pas,
Department
Environment
Geographical
Discharge Underground Other Storage Discharge
Roger
Ed Jan Britton Bruce Frank Al
Clem Larry
HUDSON
Operation Development
Control
PRESENTATIONS
Waste
Control Underground Surface
Johanson Manitoba
Beck
and
Malanewich
AND
and
Monitoring
Moche
Discharge
Wright
Smith Render
Strachan
Supply
BAY
Disposal Handling
SMELTING
Wastewater
NAMEW
to to
Monitoring
of
Department
MINING
Injection
Setting
Namew the
TABLE
Natural
Monitoring
LAKE
Alternatives
Programs
Rocky
of
Ground
CO.
AND
Lake
OF
Gasoline —
MINE
and
Programs
Resources
LIMITED
Effluent
CONTENTS
2.
SMELTING
Lake
Basin —
Resources
Established Program
AND
Basin
and
MILL
PROPOSAL -.
Disposal
CO.
Associated
of
LIMITED
the
Area
Products
PAGE
12 14 13 14 14 18 19 15 18
19
20 21 21 20 22 21 22
28
22 28 28
31 29
30 33 30 31 34 33
33 33
1
3 7
8 9 3 6 r HUDSON BAY MINING AND SMELTING CO. LIMITED NAMEW LAKE MINE AND MILL
TABLE OF CONTENTS
PAGE
B. Cumberland House, Saskatchewan 34
Ms. Delores Laliberty 34 Ms. Rose Dussion 35 Mr. Allen Felix 36 Mayor Leonard Morin 37 Manitoba Environment Department 39 Mr. Larry Strachan 39 Saskatchewan Environment Department 40 Mr. Randy Sentis 40 Mr. Robert Kent 43
SUMMARY, DISCUSSION AND CONCLUSIONS 43
RECOMMENDATIONS 49
FIGURES
Figure 1 4 Figure 2 10
— ii — ri HUDSON BAY MINING AND SMELTING CO. LIMITED
NAMEW LAKE MINE AND MILL
BACKGROUND
On July 8, 1987, the Hudson Bay Mining and Smelting Co. Limited registered a proposal under the Clean Environment Act with respect to a mine and mill operation for the development of a nickel/copper ore body lying under Namew Lake 64 kilometres due south of Fun Flon and 1.6 kilometres east of the Manitoba/saskatchewan border. The construction,of a mine shaft and mill facilities were proposed to be located on the south—east shore of Namew Lake with an adjacent tailing disposal area and ponds for the storage of mine water, mill effluent, and tailings area effluent, prior to discharge to Namew Lake.
Under the terms of the Clean Environment Act, once registered under the Act the Company was enabled to complete its plans for the development of the mine, construct the mine and mill facilities, and commence production prior to the issuance of an environmental licence.
On April 3, 1989, the Company filed a new registration of the proposal under the new Environment Act, including Environmental Impact Assessment documents which detailed a depressurizing/dewatering requirement which had not been anticipated prior to the onset of mine development work and which necessitated the disposal of much more mine water than had originally been anticipated.
During the second week of April, 1989, the Environment Department advertised its consideration of the licencing of the operation under the
Environment Act. A number of concerns and objections were received by the Department from local citizens of both Manitoba and Saskatchewan, including the Northern Village of Cumberland House and the Northern Settlement of Sturgeon Landing, both located in the Province of Saskatchewan, and on
Cumberland
Blanchard,
Commissioners morning
hearing
Saskatchewan,
Commission
Commission
at
organizations,
House,
Department
discussed
that The
Saskatchewan,
the
into
May
Clean
to
BACKGROUND
10:00
Section
Honourable
Pas,
3,
the
the
Environment
Both
After
Saskatchewan,
On
1989
were
of
a.m.,
matter
Commission
the
the
May
June
Mr.
House,
viewed
convened
of
7(3)
(continued)
hearing
the
invited
giving
Honourable
in
terminating
Environment.
mining
and
29,
Ed
as
in Herb
15,
under
of
Environment
attendance
Gramiak,
Commissioner
the
well
the
with
Commission
1989,
the
sessions
a
1989,
notice
hold
Swan.
to
to
development
Royal
mine
hearing
consideration
as
the
Environment
accompany
provide
J.
following
a
the
in
to
Mrs.
and
site
second Glen
concurrence
Because
at
Canadian
Minister,
were
the
receive
to
hearing
in
Len
The
advertising
Joan
and
better
Cummings
hold
The
late
with
chaired
the
hearing
the
Flett
Pas
of
Act.
operations.
by
Vestby
—2—
Legion
Pas,
a
a
was
afternoon
Commission
the
the
Commission’s
the
were
opportunity
submission
Saskatchewan of
public
replaced
advised
by
re—convened
Manitoba,
questions
Saskatchewan
Mr.
in
Hon.
in
and
Mr.
Hall.
Mr.
the
appropriate
Swan,
hearing
J.
Arnie
Dr.
of
Stan on
Citizens
community
the
Mr.
from
Glen
that
On
for
scheduling
Barrie
this commencing
citizens Mr.
raised
Commission
Barr,
Ed
Eagleton.
the
in
on
the
the
Environment
Cummings,
day.
Cummings
Gramiak.
Cumberland
inspection.
the
newspapers,
attending
following
Webster.
Saskatchewan
by
of
receipt
Mr.
and
proposal
Cumberiand
citizens
of
on
Maurice
that
Other
requested
a
requested
June
of
Minister,
hearing
House,
day
the
At
he
On
the
pursuant
input
of
1,
the
had
the
1989
the
in
U
I
U
ID
[
U 1 BACKGROUND
THE
Hudson Director
Manager Mr. Gil Lake construction. Environmental charge delivered The
Saskatchewan,
and situated Cumberland River. the
forest
HUDSON
John
LaBarre,
Geographical
Athapapuskow Sturgeon
project;
The Bay
A
of
Namew
The
cover
of
Most
Ross, of
somewhat
in
water;
at
BAY
Mining presentation
(continued)
the
area Lake
Safety
the
Mill
The
Weir
Lake,
with
of
Mr. Supervisor;
on
MINING
General Fun
Saskatchewan
Namew surrounding located
and
Pas, Setting June
Lakes
and
Superintendent Brian
abbreviated
River
frequent
and
on
Flon
Mr.
AND
Smelting
Manitoba
which 15,
Lake
Manager Environment,
in
of
Salamondra,
into in
mines;
Rob
and
SMELTING
Mr.
1989.
Saskatchewan
the
the
areas
is
the
Narnew
Corden, Resources
River
Namew
Gerald presentation
located
mine
Co.
of
was
Province
Mr.
mine
of
of
the
Lake
CO.
Limited
watershed repeated
Lake,
assisted and
E. SuperintendeTht the
—3—
poorly
Forsyth, Technologist
is
Flin
in
LIMITED
Bron,
of
and
consists
miii
Namew
of located
which
Saskatchewan.
the
was
Flon
of
Manitoba
Saskatchewan
drained
by
development
by
Project
(Figure
Lake
Environmental
the
Area
PROPOSAL made
Mr.
in
Division;
the
and
of
Company
in
turn
mill;
of
Fraser
muskeg.
black
by
following
drain takes
Manager
charge
1).
the
Mr.
discharges
to
proposal
Mr.
and
Mr.
Namew
proposal,
at
Waters
southwards its
Wayne
the
Technologist
of
Steve for
Curnberland
white
Brigg staff
name,
civil
Saskatchewan
Lake
Fraser,
the
from
of
to
West,
spruce
members:
Sigismund,
originally
is
the
Namew Mine;
through
Amisk
House,
in
Mr. p —4- p
Ii
Pcjre I Wildlife
environment THE mine/mill wildlife
being
impact whitefish. fishery commercial staff the concern of Branch
the claims. approximately
forestry the Cumberland at the
located
access
the
HUDSON
mine/mill fishery
project.
development
held
and
Primarily
on
Namew
Discussions
staff
The The Sturgeon
licences
being
within
Branch, will
concerns Claims
smaller
site
the
roads,
BAY
with
market
Heritage
community
Lake
staff
Several from
Lake
to
result
Manitoba
the
SlE,000.00. site
MINING
falls
the
the
determine
for
River. were
into
with because —
damage
a
had
yield fur—bearing
supports
quality
and
were power
to
Province
trapper.
meetings two
damage
Resources
within from
of which
identified.
AND
early
the
reduce
recommendations
Regional
of
in held
resulting
Sturgeon The
of
transmission
SMELTING
conclusion
the
of
the
a Saskatchewan
$25,000
Regular
to
Namew
meetings
initial
Registered
community
of
moderate
have
between
liquid forestry
proposed animals
most
the
Branch
Saskatchewan.
Fisheries
Landing
Lake
been
from
forest
CO.
in meetings
feasible
concerns
effluent
—5—
with
reached
Hudson
was
and
sports
1986, line,
damage
are
of drains.
LIMITED
mining Trapline
held
the
and
have
also
Cumberland
is
because
the
Specialist
implemented
mine/mill
one
between
Bay including will
the
route
located
that respecting
fishery
discharge
as
Regional
development.
been
consulted
PROPOSAL
Both
#35,
in staff
well tailings
continue
very
the
to
Manitoba,
paid
Hudson
on House of
ongoing
and
operation,
regarding
as
follow
access
pickerel,
and
during
representative
little
into
these the
wildlife,
(continued)
to
and in
three
disposal
Regional
to
is
Bay
assess
the
shore
There
Namew
in
no
discussions with road
ensure
the
communities
located
impact
commercial protection
environment
amount
the
concerns
pike,
the
operation
of
may Hudson and
a
Lake. area,
final
Forestry development
major
that
Nariew
to
on
of
be
and
of
local
and
damage
about
Bay
the are some
are
of
Lake
of minesite. mine. The development of General Cross THE south a Saskatchewan cottagers. Lake. Township milling body. approximately Finland north approximately Limited Employment the joint the east HUDSON Manitoba/Saskatchewan Bay basin east Other Frewan area These The The The The Continued venture facilities (40%). (HBM&s) shore 60, of This BAY presence Namew mine/mill of Namew at Rocky of of in are River. Namew features Range Lake the $85 the Rocky MINING of the 1980, $50 by lake Hudson employees shown drilling Lake Lake minesite. million Lake the mine/mill mine Lake. Hudson is million 20, located of Lake. is complex leading of AND main nickel/copper located nine/mill drains on W.P.14. the Bay are in the The SMELTING figure Bay with in border and ore the basin operates within for Rocky 3 will area This to 1985 is unamed small 10 Mining through 15 Rocky wages, body an drilling complex located of km 1. with contractor be substantiated Lake that lake annual Manitoba CO. Rocky south mine lakes was the 140 lake Lake and Chocolate Root both services, were discharges LIMITED is on indicated Hudson joint represents and Smelting in operational of drainage part — Lake (Lake and on the the Chocolate, considered 1984 employees. the mill venture. Provincial PROPOSAL Reeder of Lake is ore shore Bay B) material the mine which a used to by development (60%) basin is a body Mining separate is importance Namew an of capital expenditure site 5 Lakes approximately Frewan extensively in discovered km and electromagnetic (continued) Namew and Most and Crown and planning and with south Lake Outokumpu to the drains drainage supplies. investment if and and Lake Smelting the of Land a near mining not of of an discharge operation the the the by adjacent the to in all unnamed the 5 basin. deposit. of ore km the and Co. survey of of the to to is
U [] U r workers and palladium. THE work grading their pillar Mine 1,300 life and depth hole and first level. and development backfill. underground replace a HUDSON blast maintenance so of and/or Development drift work homes tonnes ore of Ore The of Mine Approximately limestone remain the 2.44% The the 411.Srn dolomite was from week BAY ore reserves and which mine At new development ore via extracted is per nickel produced MINItG in body the drill fill. being exploratory is with deposit a of and day, will are an fill planned four and the at is adjacent and the lateral utilized raises 225,000 AND located the Electric be ore. the sandstone located late mine raise. days. will commenced mill 0.9% quarried SMELTING mine production Namew work in The 3m access development be tonnes camp principally copper beyond for At life in 1988 long Some in mined mill mine varying in the the diameter. mine in and Co. since road. will the by of hole of —7— with this 1985 tailings end are rate Elm by crushed LIMITED drifting fill the site area, the be in at drill the of in estimated significant time with The of Elon waste depth 5.5 the will development shifts the Flin long 475,000 if on are remainder PROPOSAL period. the rigs years, greenstone l2Om through shift, successful, be the rock non. from hole unsuitable sinking are at will required and surface amounts tonnes produced although 2.58 2m raising workers of (continued) the will and 32Cm be to 12 belt of million ore utilized for per could 30m. and annually be for hours of a levels. method during return development beneath above shaft the used year, platinum mine delivered extend duration tonnes upgrading to for and the backfill to mine to to or The a drill a mine and the l2Om long will discharge. Mine minerals dewatering THE be collection Mill wastewater seepage/process be the collected suspended % into % copper the smelting thickener 1.0 railhead cellulose, material copper solids directed high. HUDSON % nickel flotation wascewater, Operation settle the copper. Dewatering The and A Essentially, mine and and number and for in in Water within overflow solids. pond. and SAY mill concentrate storage nickel a out to the the then shipment refining. water 1.3 workings and depressurizing MINING a Concentrates discharges was water. and ore, of bulk designated consisting the % and The separation filtered. from pond. streams The nickel. reagents soluble where completed all mine will rougher depressurizing AND final to and overflow is the The the Copper Fort SMELTING and be further trucked as this and ore. polymer wastewater mine of The are sulphide copper are processes rejected Processed flotation; operations pumped high in Saskatchewan. seepage passed concentrate water nickel treated from used wastewater, 1988 These treatment to as CO. concentrate which minerals to requirements Thompson the in will with 400 in through and LIMITED storage of concentrate concentrates include with the the potassium will the clarifier is L/s the mine not a is surface can used mill when mill design flocculent, Filtrate will collect mill. a and trucked in PROPOSAL pond be from sodium process be clarifier the to operation mixed pumped in process part amyl probably done, assays is where capacity at depress are the the The ore water water discharged to carboxy a shipped canthate, water, with mill (continued) shipped mine to gangue, will rate if thickened Flin suspended to for 17.5 to prior be the required, the is assays the of the are of be Flon. methyl separate removal will necessary. % combined to surface, 1900 gangue elsewhere mine 16 nickel tailings or recovered to a expected to the to collector be L/s. solids waste about the its t/d. Part prior about of nearest the and with will entry Mine of for 28.5 to by to 60
r [I
U
[ -l 1 which enhance that carbinol, THE
fiocculent thickeners; destroyed higher probably wastewater into reagents assurance down of environmental storage has tailings Tailings
toxicity. water a
(figure be
tailings
the
utilized
HUDSON
exceeded
is
the
to
is
encountered
concentrations.
In
Federal
It Tailings
commonly
the
pond.
acceptable
2).
used concentrates
or ranges based
and
an
by the
that is
BAY
which
storage
pond,
sodium separation
the
to
alcohol
aeration
not Wastewater
the
In
event in
effects
MINING
on
Metal
In the
receive
from process
and
addition,
used
the
is
expected
requirements
a
oxidation
the
during
cyanide
wastewater levels,
pond
reclaim
used
that
wastewater
separation frother
19
Mining
AND for
or
event and
in
of
mine
wastes
to
In
effluent
to
sodium
residual
the
mine
SMELTING
the
copper
some
that
as
which
all 500
a
water
treat
using that
Effluent
depressurizing/dewatering
used
cyanide
final
a
bulk
of
storage
development,
kg/day cases,
by from
any
management
result
circuit
cyanide
may
from
natural
has
the
reservoir,
both
concentrations in
natural hydrogen
flotation CO.
effluent.
of
the
—9—
bulk be
destruction
Regulations
been
Federal
nickel. exclusive
these
pond the
of
LIMITED
concentrates
used
mill to
is
degradation
the
roughing
degradation
chemicals
will tested
depress
used, peroxide.
effluent
it
reagents
and
of
in
ooeration.
Metal
unanticipated
The
is
PROPOSAL
The
utilize
sulphides;
of the
a
can
some
plant which
for
proposed
Company
wastewater
and
nickel; addition
lime
Mining
prior
separation
will
will
be are
fails
toxicity
cyanide
in
effluent.
cleaning
will
include
three
which
(continued)
found
either
meet the
lead
to
has
Regulation
that
methyl
polyacrylamide
to
volume
rate
be
entering
wastewater
storage
storage
will is
in
also reduce
and to
the
circuit
employed
bioassays.
Chocolate
stages;
incorporated
of used
the
adverse
isobutyl
requirements
the
of
be
given
these
mill
cyanide
for
pond mine ponds
the
in
quality
to
lime
much
Lake —
The — 10 —
a s t ew at e r St or age Pon d
Wastewater Disehar
Pipe I ine SI Freshwater to / V Pumphouse Chocolate 1 Lake / At — Tai lings Discharge — Mine / NIii Site Tailings Pond
Emergency Pu — — - Discharge Spil Iway
Reclaim Water Reservoir
Namew Lake
FIGURE2 — 11 —
THE HUDSON BAY MINING AND SMELTING CO. LIMITED PROPOSAL (continued)
The tailings material separated from the mineral in the ore following the bulk crashing and cleaning process will be deposited in the tailings pond at an estimated volume of 1600 tonnes/day. Over the 5.5 year life of the operation, an estimated 2.2 million tonnes of tailings will be deposited. The tailings will he of low sulphur content ranging from 0.4 to 0.7%. Acid generated, will be neutralized by alkaline material in the tailings. Acid not neutralized will remain in the tailings and will have to be addressed by the tailings rehabilitation plan. The major impact of tailings will be the inundation of the tailings pond with 2m of tailings. Amelioration of this area will be included in the rehabilitation plans.
Discharge of the clarified effluent from the tailings pond will be collected in the reclaim water reservoir for reuse in the mill with no discharge to the environment. The reclaim water reservoir has a capacity of approximately 884,000 3m and will accommodate the overflow from the tailings pond. The anticipated rate of overflow is 32 L/s which will be augmented by surface run—off. The mill pumphouse will withdraw water from the reclaim pond at a rate of 35 L/s. Provisions have been made to remove excess water from the reclaim pond to the wastewater storage pond during periods of higher than normal runoff and to add mine wastewater to the reclaim system during periods of lower than normal runoff in order to balance the mill water requirement. Therefore, under normal conditions there will not be any discharge from the reclaim water reservoir. There is a spillway with stop logs that will permit discharge to Namew Lake in the event of an extraordinary precipitation event. The reclaim pond system will be operated to protect the dykes and prevent any but an usual overflow. It is estimated that approximately 80% of the mill water requirements will be met with reclaimed water.
a capacity of 87,000 in The wastewater storage pond has storage ,3 which will provide 10 days of detention. Inflow to the pond consists of mine The water at a rate of 16 1/s and mill process water at a rate of 13 1/s. mill wastewater has a pfl of 12 and its re—use in the mill may cause problems with the metallurgy. The chemistry of the mill process wastewater will contribute THE HUDSON BAY MIN:NG AND SMELTING CO. LIMITED PROPOSAL (continued) fl to the precipitation of heavy metals and is therefore beneficial to the r treatment of the water in the wastewater storage pond in meeting effluent requirements. In the event that the desired effluent limits are not achieved from the wastewater storage pond, additional treatment would have to be provided prior to discharge. At the outset, it was proposed to discharge effluent directly to Namew Lake. The proposal is now to discharge effluent I I from the wastewater storage pond to the depressurizing/dewatering pipeline. ri As noted, this pipeline is proposed to be discharged into Chocolate Lake. This will provide only one effluent discharge point — from Chocolate Lake to Namew Lake. U
Depressurizing/Dewatering
In order to allow safe mining to proceed, it was determined that extensive dewatering and depressurizing of the host rock surrounding the ore body would be required. The volume, combined with its salinity, constituted a massive water problem. The Company retained a hydrogeological consultant to advise on remedial measures. The consultant reported in early December, 1988, that depressurizing of the water—bearing zone surrounding the ore body would be required to reduce water risks to a minimum. The consultant estimated that withdrawal of 500 L/s for 70 days would totally depressurize the surrounding rock. Ongoing dewatering at an estimated rate of 250 L/s would be required to maintain the depressurized state. Without this process in place the mine might become totally flooded as mine development progressed.
At the time of the hearing the mining of ore had been much reduced from the scheduled 1300 tonnes per day because of this water with hazard mining LI operations being confined to the upper mining level where the risk of flooding was acceptably low. LI
:n order to reduce the waterflows, exploration drill holes into the ore body through Namew Lake had been located and resealed. I — 13 —
THE HUDSON BAY MINING AND SMELTING CO. LIMITED PROPOSAL (continued)
Initial depressurizing commenced May 22, 1989, with the resultant discharge directed to the tailings area. The ponds were re—engineered and earthworks constructed to allow for storage of all depressurizing water for a minimum 90—120 days. Additional construction for further storage would also be a possibility but the costs would be very high.
It is now estimated that depressurizing/dewatering effluent discharged from the mine will contain 1500 to 2000 ppm total dissolved solids, principally chloride salts of sodium and calcium.
In order to provide for other disposal of this water, a pipeline had been constructed to direct the depressurizing water to Chocolate Lake. This line had not yet been placed in service at the time of the Commission’s hearings.
At a later date, it is intended that depressurizing water be recovered from the tailings pond and disposed of by other environmentally acceptable means.
Depressurizing/Dewatering Effluent Disposal
The principal environmental effects of disposal of the dewatering/depressurizing effluent will be on the aquatic ecosystem.
Several options for the storage or disposal of this water were considered by the company. Evaluation of the various options were done in relation to the following assumptions that:
(1) The depressurizing effluent is not toxic to fish.
(2) The optimum total dissolved solids (T.D.S.) for fish is 200 mg/l. THE
examined,
other (a)
mine. rock volume
surrounding (b)
inundated
Root
located Cc) Pas.
HUDSON
(3)
formations
and
rock
A
Underground
Underground
of
Storage
This
Discharge
The
number
east
as
Reeder
water
BAY
over
formation
Rocky
The
other the
flat is
follows.
of
MINING
not
of
the
surrounding or
depressurizing
pumping
Lakes the
terrain.
to
Lake
effects
options
Injection
injection
the
a
life
the
Namew was
AND
practical
drainage
before
injected
operation.
of
Rocky
considered.
SMELTING
not
for
Lake
An the
Nanew
of
entering
naturally
disposal
estimated
Lake
effluent
option
project.
basin minesite. the water
Lake CO.
Basin water
comprises This
would LIMITED
due
would
the
of
will
reversible
28
back
to the
was Rocky
Saskatchewan
square
short—circuit
either
not
the
PROPOSAL
depressurizing
into
rejected
some
Lake
lead
volume
kilometers
following
the
be
500
drains
to
nable
(continued)
originating
as
River
of
square
solids
directly
an
water
south,
completion
water of
option to
upstream
miles
deposition
land
accept
and
back
were
or
through
since
would the
and
some
of
the to
of
is
The
the
the
or
be
r fl
11
the
Lake
records
Lake
the
optimum,
T.D.S. flow
(a)
Namew
in bait
total primary
depressurizing
marshlands
Rocky
Lake,
the
anticipated
basin
lake
lake
combinations
THE
excess
minimum.
Namew
and
via
lake
of
HUDSON
fish
would
located
Mine
dissolved
Ducks and
The
Discharge
feeding
to
The
show
Rocky
Discharge
7000
spawning
Cumberland
the
and
and
Lake
the
of
operation
Namew
Namew
depressurizing
south between
provide
BAY
that
Sturgeon
Unlimited
effluent
negative
g.p.m.
the
The
has
Lake
at
lake
of
minesite.
Rocky
and
MINING
solids
Lakes
Lake
to
about
free
fisheries
and
end
maximum
minimum
numerous
of
supports
water.
from
Root
Lake
Namew
would,
some
conduct
Lake
depressurizing
rearing
of
Weir
drainage
volume
effects
discharge,
operate
is
the
AND
(T.D.S.)
which
Rocky
Lake
to
dilution
flow
flow
a
Both
would
Lake
effluent
River;
cottages
midpoint
This
at
optimum
SMELTING
wildlife
the
an
activities
from
area
and
on
the
water
Lake,
is through
basin a
active
Amisk
Basin
Saskatchewan
provide
would
in
water
ditching
the
the
Namew
in
the
at
21:1
for
Rocky
at
level
along
between
water
CO.
discharges
which
management
a
and
conprises
the fishery
—
Saskatchewan
mine.
sports
move
an
the
50:1 the
control
dilution,
on
15
Lake
a
LIMITED
Athapapuskow
outset
of
estimated
Lake
the
dilution
or
to Rocky
—
would
this
lake
the
ratio
the
200
River.
in
fishery
would
piping,
Rocky
east
is
structure
sone
water
portion
from
is
aTea.
turn
minesite
of
rng/1.
PROPOSAL
Lake
receive
add
300—350
to
River.
approximately
shore.
factor
probably
the
Lake
level
5600
Rocky
discharges the
Long—tern
on
and
quality
a
fishery.
Lakes
Downstream
discharge.
further
of
the
the
could
effluent
anticipated
for
square
and
the
of
mg/l
(continued)
of
the
Lake,
The
discharge
northern
drain
result.
1500
management
Rocky
21:1
use
further
involve
which
lake.
hydrological
region
70
Two
through
miles
serves
five
of
T.D.S.
from
from
to
to
mg/i
The
Lake.
commercial
an
is
maximum
portion
Namew
the
from
of
Current
times
between
north
various
Rocky
drainage
unnamed
of
already
as
Cross of
and
the
This
the
the
of
a of THE Namew
about
yield fishing on being
fishermen The addition, primarily
underlying
is
Lake the will other for
will
water course rock depressurizing
Lake.
ability reservoirs
water
the
HUDSON
the
discharge
depressurizing
the
Lake
twice
is
the in
reduce reverse from
Namew
hand,
Water north
is
same
Mr.
licences
from
of
Two
much
fishery 1987
to
fish and
added
which
BAY
in Mine
the several
sedimentary
the
Fraser’s
water
small
prior
hold Lake
the the the shore
entering
the
less
had
the sports
from MINING
of
Lake.
depressurizing
annual
water
to
represents
which, —
mine natural Company
lake
supports
the a value.
hydraulic
which
Lakes
to
than two
of
years, the Namew
water
market
analysis
fishing
AND
discharge
water
will the
The
Namew
to bottom
flow—through.
in
Lake,
rocks
the
in
in is
expects
entry
Lake
Namew SMELTING
would
Saskatchewan The
lake
net
approach
a
the value
contain
about
proximity causing
optimum
prior
force
Lake
moderate
outfitters
the
where provide
noted
small
result contains
water
Company’s
of at
Lake
of
bring
of
that
T.D.S. contains
50
to
saline
such the
CO.
depressurizing
an
that
-16- upward
problems
that
200 $25,000
community
would, tons
volume.
discharge
would
an
to
sports
the
the Sturgeon
initial
LIMITED
and
that
a
mg/L.
work
of at
artesian
the
the
view,
water
per T.D.S.
T.D.s.
underground
a
hydraulic
one
be
the
however, the
with
water
T.D.S.
mine
in
T.D.S.
fishery
out
day
Water
of
T.D.S.
that,
PROPOSAL
He
provides
could Weir in
through
Lake incoming
the
of
closer pickerel,
Sturgeon
of
of
flow
could
effluent
believed
Manitoba.
will
of
115
volume
Namew
naturally
River;
this
outlet if
add combined
pressure
and
be
of
depressurizing
approximately
of
the
no enter
mg/l.
(continued) serve
beneficial. to
a
some
water.
back
three
community.
saline
Lake
benefit Landing
additional
in
to that
the pike
commercial
Lake
will,
The
the 4000
minerals salts,
from
as Namew
Namew present
This
mine.
commercial
optimum
the
and
bottom,
The
water.
holding
commercial
underlying
over
mg/L, is
in
the
T.D.S.
Lake
Lake. addition whitefish
addition 90
is
On program
located that
saline
in
the
to
T.D.S.
mg/i...
sourced
the and
This
is Namew
the
the
The
of
of
r U — 17 —
THE HUDSON BAY MINING AND SMELTING CO. LIMITED PROPOSAL (continued) decreasing to a projected 1500 mg/L after depressurizing has been achieved. Retention of the initial discharge would allow dilution to be gained prior to discharge of the higher T.D.S. water to Namew Lake. The temperature of the depressurized water would also approach that of Namew Lake as a result of retention in an intermediate lake. A uniform temperature would assist in preventing stratification of the Chocolate Lake discharge in Namew Lake.
One of these intermediate lakes, Chocolate Lake, is located 5 km north and east of the minesite. The lake appears to contain a limited fish population consisting of minnows and northern pite. The lake discharges via a creek to Namew Lake, which it enters close to the minesite. The lake, averaging 4 — 4.Sm in depth and about 300 hectares in surface area, is located in a flat swampy area. Attempts to increase the holding capacity of this lake with dykes or dams would be difficult.
Chocolate Lake currently holds a volume of water equal to three or four times a 70 day discharge of 530 L/s. Addition of dewatering effluent to this lake could be done at one of several locations, with a point towards the east end being the most desirable to prevent flow short—circuiting to the lake outlet. Both the lake and the creek are located in the Province of Manitoba.
Frewan Lake, the second of these lakes, has a large holding capacity. Discharge from Frewan Lake takes place into Cross Bay of Namew Lake. This portion of Namew Lake has little fishery. However, both Frewan Lake and Cross Bay are located in the Province of Saskatchewan and would require approval from that jurisdiction. This option was rejected as a consequence.
A Direct discharge to Namew Lake was also considered. Mixing to equalize the mineral concentration of the depressurizing water and to bring the temperature to that of Namew Lake would not occur with a direct discharge. Significant mixing of the discharge to the lake might therefore not occur in all seasons and the discharge could be disruptive to shoreline habitat. THE Weir
Namew Company subject be (e) Saskatchewan.
selected the under future. Chocolate rainbow trout wasterock
auxiliary underground. wasterock site
ingredients
minimal.
HUDSON
best
River
development,
Lake
review
stocking ______
Two Other
After
Additional Wasterock
Wasterock
noted to
trout
alternative. storage This
Lake,
service
is
BAY
other and
at
freezing.
Discharge
(ie. consideration
In
with
not
Sturgeon that
examination
fishery.
A
MINING
one
program
the
with
limestone
discharge
in
generated
generated
available.
sulfur)
fisheries
toxicity
upgrading
roads
both to
Case
Chocolate
the
AND
the
In
Weir Alternatives
In
if
pipelines
Hudson
around
of the
increased
at SMELTING
Goose
would
support
it
quarry
formats
of
tests
at
by
Sturgeon
in
experts
and
levels
case
is
The
the Lake
the
the
both
Bay
the
River.
be
reasonable maintenance
on
wasterock
is
would
of
of foregoing
mining site
were CO.
and
will
used
level
mine/mill
which
cases.
and
the
being
Weir,
the
this
LIZIITED
subsequent
during
examined The
be
will
support in effluent
Goose
of
operations
will
alternative,
developed
long
the
the and
will
outcome
In discharge
T.D.S.
of
be
complex.
mine
cause PROPOSAL
River discharge
rejecting
determination
desirable.
the
and
scheduled or
not —
were
discharge
a
would
undertake
mine development
would
thus
will
contain for
concerns
pipeline
discharge,
options
being
additional
(continued)
access
use
would expensive these
be
be
be
for
into acceptable
conducted.
used
as
chemically—active
a
as
this
or
to
the
the
discharge proposals,
occur
was
backfill road
dilution
to
impacts.
the
Namew
for
Company
studies
near rainbow
and
whether
used
and
Sturgeon
in
backfill
also
as Lake
for
when
would
to
the
were
a
as
r [1
U
U LI fl — 19 —
TE HUDSON BAY M:NING AND SMELTING CO. LIMITED PROPOSAL (continued)
Storage and Handling of Gasoline and Associated Products
All petroleum products are being stored and handled in accordance with Manitoba Regulation 97/88R under the Environment Act.
Dust Control
Dust emissions from the Namew Lake mine/mill complex are expected to be well below the standard imposed on the Snow Lake concentrator in Clean Environment Commission Order No. 765. This is a result of the complete enclosure of the ore handling system. The crusher and conveyor systems produce dust due to the nature of the operation. These have been enclosed and have been equipped with an air ventilation system which utilizes a water scrubber to clean all exhaust air, which in turn is replaced by heated, fresh make up air. The milling and concentrating operations all occur on slurry material and do not produce dust.
Fugitive dust emissions from vehicle traffic on the mine access road and on site will be handled through routine maintenance and good housekeeping practices. During extended periods of hot, dry weather an environmentally acceptable dust stabilization compound will be used as required to control this dust. It is estimated that heavy vehicle traffic will be limited to 8—10 transport trucks per 24 hour day. while moderate levels of light vehicle traffic will occur. If airborne dust from drilling and blasting at the limestone quarry occurs, the operation will be temporarily shut down. ______
THE
double Noise mine
equipped
insulated operation preserving most the dampening minimum
operation levels
Solid
solid Environmental non—burnable has clayfill
Natural
only
HUDSON
shoreline
been
ventilation
significant
Control be
Waste
wastes
Ore
skin
In
generated It
A
The
impact
Resources.
undertaken with
solid
material erected
and
on an
and
will
is
BAY
handling
the
disposal
exterior
Disposal
Namew effort
anticipated
will and
equipped
efficient
of
eliminating
Control
MINING
natural
on be
waste
system
the
by source
for to
seasonal
the
be and
Lake,
facilities once
to
the
site
aid
wall.
lake
Ground
disposal
periodically
storage
AND
environment
Branch
allowed
with
minimize
appearance
mufflers.
is
drilling, of
in
authorization
a
that
is
SMELTING
and
most
fitted
buffer
noise and
the
efficient, Pumphouses
segmented
for
of
mine/mill
the
ground
to
are
of can
proper
the
used
generated
the
naturally
with
line of the
blasting,
limestone
(spring
capped
CO.
completely
be
-20-
impact
the
approval solid
barrels
noise
operated
into
operation LIMITED
and
a is
relatively of
site.
silencer
site
with
received
trees
and
ether
of
by
waste
three
reveqetate.
generated
backfill and
and
enclosed
no’ise
when
the fall).
has
a
PROPOSAL
This
when
has
limited
of layer
satellite
disposal
salvageable separate
and noiseless
entire
been
from
viewed
the
buffer levels been
the
quarry
has
on
of
with
received
site.
(continued) the
effect
crushing
All
left
operation. site
waste
been
from
areas
site.
structures
has emitting
equipment. an Department
site
required
wastes.
standing
as
Burning
insulated enclosed
the
the
of
rock
from for
well
will
will
the
effect
lake.
from
burnables,
and
This
the
signing
are
as
be
have noise
The will
of
between
The and
the
the
well
of
a
(--I U U
U
U L — 21 —
THE HUDSON BAY MINING AND SMELTING CO. LIMITED PROPOSAL (continued)
Sewage
An estimated 30 cubic meters per day of sewage and domestic wastewater will be generated at the mine/mill complex. This water will be collected through a series of gravity flow sewer lines in the sewage lift station located on the northern side of the site. From there, it will be pumped to a two—stage above—ground sewage holding tank. Effluent is decanted from the holding tank and discharged to the tailing pond. The solids will be removed by contract to an approved waste disposal groun&.
Freshwater Supply
A Water Rights Licence was issued to Hudson Bay Mining and Smelting Company from the Water Resources Branch of the Department at Natural Resources to withdraw fresh water for the various minesite uses from Namew Lake. Domestic water will be disinfected. Approval has been received for the water supply and distribution system and wastewater collection system tram the Environment Department.
Effluent Monitoring Programs Established
Effluent monitoring programs have been established at the Namew mine/mill site to gather effluent quality data to allow determination of the type of treatment required. Regular monitoring programs will also indicate changes in effluent quality which could result in changes being required to treatment techniques. drainage discharge been three Questions because should THE HUDSON discussed or With collected minewater analysis. personnel analysis. In discharge complex. benefit Analytical directed Surface to and samples monitor sampling Effluent final Underground of channel four from response entering drought delivered BAY regard underground years. with Chocolate Monitoring MINING are the the discharges to locations Weekly by but discharge and and Bi-weekly Department to conditions the effluent collected quality to Monitoring trappers Mine the delivered that, to final questions Registered Chocolate AND reclaim samples trapper the Department Lake sump were Programs SMELTING at discharge from of from samples Sudson containment for activities. by present, to there various Program for to reservoir, chosen at of underground Lake the Mine and Trapline Namew analysis. the discharge The Mill Bay CO. personnel of had stabilization final -22- is Department from Hudson underground flows the Namew Lake Pas Analytical LIMITED probably process areas in underground are the #35, hearing, the lake would and which to Bay Lake and collected tailings adjacent order the surface. PROPOSAL was water surface personnel not Analytical delivered be at raw Department ultimately of Chocolate Mr. 1 been of through different the — water sump discharge, containment to l.25m Fraser by Mill lBm (continued) The lake any on the Mine to above to supply Department a Lake a underground operations in report below mine/mill discharge surface water natural the hi—weekly stated levels Department Flin tailings Namew proposal and Hudson area normal to level non are that to for the Lake. are prior for basis Bay for and
had
U
U
II
H r — 23 —
HBM&S CO. LIMITED PROPOSAL — QUESTIONS (continued)
Mr. Fraser stated that the need for unusual measures to depressurize the mine became apparent only in November, 1988 as mine development progressed. Until this problem is overcome mining has been restricted to the upper level of mine development, so that mining was being done at only 30% of the production budget and less than 10% of capacity. Mining at this level of production would not normally be economic.
In answer to a question from Mr. Phil Leonard of the Rocky Lake Cottage Association, Mr. Fraser stated that the estimated depressurizing/dewatering pumping rate was down from the original estimate, when the report was compiled, to a current estimate of 300 L/s. A ridge surrounding Chocolate Lake would prevent outflow into Rocky Lake. Toxicity tests had been conducted on the depressurized water at about the 4,000 p.p.m. T.D.S. level without toxic effect on rainbow trout and other aquatic life. At this concentration, jackfish would probably be adversely affected. The depressurizing operation should not have any direct affect on the water or water levels in Rocky Lake.
In answer to other questions, Mr. Fraser confirmed that the current consideration by the Company was not to discharge water from the wastewater pond directly to Namew Lake but to inject it into the depressurizing water pipeline and by this means discharge it to Chocolate Lake along with effluent from the mine wastewater storage pond. He stated that the pH of the wastewater pond discharge was too high to re—use in the mill process — that metal recovery in the mill process could be affected by the high pH. He also stated that in the event of an emergency discharge to Namew Lake during an extreme rainstorm event, attempts would be made to pump down the water level of the reclaim pond and return the effluent to the tailings pond area.
In response to another question, Mr. Fraser said that the net acid generating potential of tailings from the Namew Lake mine and mill operation the is of the order of only 0.4 to 0.5% sulphur as compared to tailings from Flin Flon operation in the range of 20 — 25% sulphur. The Fun Flon tailings of has a net acid generating potential of almost 500 kg of acid per tonne -
17
— 24 —
----I
HBM&S CO. LIMITED PROPOSAL — QUESTIONS (continued) tailings. Such acid conditions can result in the release of heavy metals from [] the tailings residue. Such metals can then reach the nearby receiving streams. It is fortunate that the sulphur content of the ore is so low at the Namew Lake mine.
In response to a question from Mr. Ed. Johanson, representing the Manitoba Environmental Council, Mr. Fraser was of the opinion that the stocking of Chocolate Lake with rainbow trout would be good proof of a (i discharge of mine water to Namew Lake from Chocolate Lake that would be acceptable to the water of Namew Lake. .. [_1
Answering another questioner, Mr. Fraser explained that due to the mining method employed in the Namew Lake mine with a resultant fine grind of the tailings that backfilling this material into the mine was not a practical consideration.
In answer to another question, Mr. Fraser stated that if the depressurizing water stays at a T.D.S. level of 4,000 or becomes higher, dilution would likely be the only practical method of reducing the Li concentration to an acceptable level for discharge.
In response to a question from Mr. Larry Strachan, Chief of Environmental Control Programs of the Environment Department, Mr. Eraser agreed that a single point discharge from Chocolate Lake would be a logical licencing requirement. He also favoured the formation of a committee to develop a rehabilitation plan for the mine for implementation following mine closing and abandonment. In the event that cyanide is used in the mill operation, the Company would expect to meet standard discharge limits.
Questioning of Mr. Fraser continued at Cumberland House on June 15th following his condensed presentation of the Company proposal on that occasion.
11
II — 25 —
HBM&S CO. LIMITED PROPOSAL — QUESTIONS (continued)
In response to questions by Mayor Morin of Cumberland House, with regard to impurities in mine/mill effluent, Mr. Fraser said that the Company’s proposal was that effluent from the wastewater pond entering the pipeline to Chocolate Lake would meet Federal Mine/Mill Regulation Limits, which he felt were achieveable and had been demonstrated to be reasonable for substances such as nickel and copper. A further part of the proposal is that there be a limit of 2,000 p.p.m. T.D.S. for effluent discharged into Chocolate Lake.
Mayor Morin had further questions about the quality and constituents of the proposed discharge from Chocolate Lake to Namew Lake. In response, Mr. Fraser referred to tests conducted on samples of the brackish water from the mine depressurizing process. Bioassay tests had been conducted by an independent laboratory on samples up to 4,000 mg/L T.D.S. without any lethality. Tests on mill process wastewater was also proven to be non—toxic.
Mr. Fraser said that flow into Namew Lake from the Sturgeon Weir River would, at minimum flow, provide an 80:1 dilution ratio for the wastewater and depressurizing water discharge from the mine. At average flow the dilution ratio would be 160:1. He also said that the proposed establishment of a trout fishery in Chocolate Lake would provide the ultimate test as rainbow trout are the species used in Federal Metal Mining Liquid Effluent Regulations for bioassay purposes.
Brian Christianson, Fisheries Habitat Co—ordinator for Saskatchewan Parks, Recreation and Culture stated that the two species of fish used for the tests referred to by Mr. Fraser, are extremely tolerant of salt. He would be more impressed if the tests had been done on pike or walleye. He agreed with Mr. Fraser that the tests chosen were standard protocols which Mr. Fraser said had been recommended to him by the Manitoba Fisheries Branch; however, he said that in Saskatchewan rainbow trout had been grown in water with a strength of 20,000 p.p.m. T.D.S. because rabbow trout can live naturally in seawater. It was Mr. Christianson’s opinion that 2,000 p.p.m. would be very tough on pike or walleye. discharge of discussion drew with Chocolate alternatives, House entering the insufficient Lake underground surface analysis. 20 1988. into since of to that HBM&S is the cm the a the water would possible support much Rocky the Mr. above insufficient CO. Mr. Chocolate Mr. Biological In dewatering/depressurizing Saskatchewan In In of Winnipeg the go Lake. Fraser response in smaller response response lIMITED was Fraser Namew have Fraser Lake water that from bottom to information the problems as joined Rocky been was previously Lake observation said of Lake. Mr. again pressure groundwater drainage data showed PROPOSAL to time to to of River. the in considerably disposal Lake by McAuley. that questions another further — collection the a went This lake. had Mr. available it a neighboring because discharge graph Lake basin had — would presented been over well Christianson, QUESTIONS indicated questions question, formation option; dropped Since due from problem of and available remain the less had work then for to the of Mr. ______the discharges drainage Chocolate been at however, him pressure expensive was that from (continued) Saskatchewan observation the near Mr. from Manitoba’s The start Leon had who to reduced still to mine/depressurizing salt 450 Fraser Pas, Namew only Mr. assess McAuley, complete basin also of he Lake p.s.i. below through water than underway Christianson, become in the would Lake to re—iterated problem. said well to and would the some a depressurizing the the may a to Namew the Root with level Rocky prefer affect that citizen known that cost detail. about at Lake. not no data Chocolate a and Lake. This there had longer 2.5m have water Lake of Mr. in that to on water 80 collection of Reeder pumping November, been position have Namew This below p.s.i. Fraser disposal was to Rocky Cumberland the program be level to deal drilled Lake the extent Lakes Rocky Lake the and to Lake said
and
I f
(-)
U
U
L {] r
I r — 27 —
HBM&S CO. LIMITED PROPOSAL — QUESTIONS (continued)
In response to the foregoing, Mr. Fraser said that he was only seeking the best environmental solution regardless of political boundaries and that his information, and the opinion of the Manitoba Fisheries Branch officer, was that Namew Lake would be adequately protected through the use of Chocolate Lake as an initial receiving body for the discharge of effluent from the mining operation. In response to a question, Mr. Fraser said that differences in land elevation were such that Chocolate Lake could not be drained by gravity into Rocky Lake.
Mr. Cliff Potter of the Saskatchewan Envi’ronment Mines Pollution Control Branch agreed that there was some salt water entering Namew Lake (he calculated 11 tonnes per day) but he stated that studies undertaken on behalf of the Company by A.E.C.L. to determine where the salt water was entering the bottom of Namew Lake were inconclusive. Major discharges into the bottom of the lake were not discovered. He believed that at times there was an upward pressure on the lake bottom and at times a downward pressure. The known information was not conclusive. Based on the limited information available, he did not believe that there was presently a significant mineral loading on
Namew Lake from underground water in comparsion with the discharge proposed by the Company.
in response, Mr. Fraser said that his calculations of natural loading on Namew Lake amounted to 50 tonnes per day. Mr. Potter agreed that he had used the same data; however, his calculations had used the average concentration values whereas the Company had used the extreme values.
Mr. Potter also had questions about post abandonment rehabilitation, tailing pond seepage, acid generation potential, and leachability. In this regard, Mr. Fraser agreed with a suggestion that, under the prevailing circumstances, a representative of Saskatchewan Environment could be asked to sit on a rehabilitation committee along with members of the public. H
-I
— 28 —
CITIZEN AND OTHER PRESENTATIONS II
A. The Pas, Manitoba
Mr. Ed Johanson representing the Manitoba Environmental Council presented a brief on behalf of the Council.
The brief drew attention to the relatively short notice given for the hearing which did not provide sufficient time for the volunteer Council members to assess the project proposal as thoroughly as they would have wished.
Council believes that a good environmental impact assessment (E.I.A.) must contain at least three things. 1) A description of the environment to be affected, especially its ecosystems and vulnerable components, 2) a description of the potential impacts of the operation on the organisms and ecosystem involved, and 3) an analysis of how these impacts would affect the organisms and ecosystems involved. As well, an Environmental Protection Plan should identify ways of eliminating negative environmental impacts or reducing them to an ‘acceptable level.
Although some of these elements are inadequately covered, the total documents submitted contain all of these components. However, the description and identification of ecosystems and vulnerable species in the Company proposal is weak. More onus should have been put on the developer to get basic biological data as well as the hydrologic and chemical data which was compiled.
A further deficiency was that little resource data was provided for Chocolate Lake or for Namew Lake in the vicinity of the proposed discharge points. U
U
U — 29 —
CITIZEN AND OTHER PRESENTATIONS — THE PAS (continued)
Mr. Roger Smith, who operates a fishing and hunting lodge at Sturgeon Landing on Namew Lake spoke on his own behalf as well as representing the interests of the Native people who live at Sturgeon Landing.
He stated that the lakes and forests in he vicinity provide hunting, trapping, and some commercial fishing for the local population. As well, the river and lake are the primary source of drinking water, as the water from drilled wells is not used by the Native people.
Mr. Smith referred to the disastrous conditions imposed on the environment by other abandoned mining operations in the north and wanted assurance that this project would not have a similar result.
Mr. Smith and the other Sturgeon Landing people are opposed to the use of Namew Lake for disposal of saline waters from the mining operation — or Too other mine effluent — either directly or indirectly via Chocolate Lake. many uncertainties exist.
As regards employment benefits, only one person from Sturgeon Landing is working at the mine and he did not believe that any person from Cumberland House was so employed.
He stated that the roads had not been sufficiently improved or maintained for the volume of truck and passenger vehicle traffic generated by the mine and that present traffic and road conditions were both a hazard and a discouragement to the use of the road by himself and his lodge guests. Shift changes at the mine were an exceptionally bad time for traffic.
He stated that the original information about the Mining development was that nothing was going to be dumped into Namew Lake but now things are changing and he is very concerned.
absolutely
tailings Further
caused
liquid
to Pollution.
operation.
depressurizing
unknown
habitat
Owner’s
inadequate
Lake,
had
discussions
upgrading
CITIZEN
is
the
in
prepared
Wanless,
charge
He
effluent.
by
He
surrounding
Mr.
These
The
Ms.
In
treatment
quantities
has Association.
AND
area,
warned
H.B.M.
related
the
response
binding
Britton,
to
proposed
Jan
greatly
were
OTHER
unknown
information
of
cope
road,
is
and
Cumberland
Malanewich
Namew
that &
being
necessary.
An
to
problems
PRESENTATIONS
S.
rehabilitation
environment
with
and
dewatering
to
of
development
affected
particularly
alternative
that
factors
mining
the
Mr.
Lake
quality
Flin
held
these
on
proposed
proposed
House,
made
Smith’s
with
operations
Flon,
behalf
with
and
are
other
Perhaps
unknown
requirement
had
of
a
air is
—
filtration
smelting
unacceptable
and
with
presentation
the
agreement,
represented water.
concern
THE
by
operation
resulted.
areas
of
of
and
-30-
Sturgeon
Manitoba
a
H.B.M.
values.
great
the
regard
for PAS
performance
water
of
activities.
Traditional
deals
Rocky
over
H.B.M.
(continued)
method
mining
condern
will
&
including
to
quality
to
the
Landing.
on
Department
S.
road
with
Lake dust
the
behalf
&
should
have
Concerned
should
development.
S.
bond
to
conditions
licencing
only
East control.
in
approaches
said
A
restoration to
the
The
of
be
should
great
the
of
be
be
assumptions
Shore
people
Mr.
that
carried
Citizens
pollution
Highways
watched
considered.
Flin
deal
of
John
Mr.
be
Cottage
ongoing
may
The
Flon
this
of
of
required.
Baron,
out
of
Bodnar
closely.
Against
be
Rocky
for
the
of
about
damage
area
on
fish
An
who
the
who
U
I U
D
{]
r f1 — 31 —
AND CITIZEN OTHER PRESENTATIONS — THE PAS (continued)
i4anitoba Department of Natural Resources
Mr. Bruce Wright, Regional Fisheries Branch Representative of the Manitoba Department of Natural Resources, did not have a prepared presentation but agreed to discuss the proposal and its possible affect on the fisheries of Nanew Lake and Chocolate Lakes and to answer questions.
He stated that the Fisheries Branch mandate was to manage the fisheries resource but that the matter of the possible impact of the mining activities on the fisheries resource was the responsibility of the Environment Department. However, based on only limited experience by himself and his colleagues with saline discharges and saline water, he was of the opinion that the alteration to Namew lake from mine discharges would not be significant or long term in nature. He felt that the impacts would be acceptable, provided appropriate monitoring was done.
With regard to Chocolate Lake, Mr. Wright stated that he would like to see the enhancement of that lake by replacement of the fish population with rainbow trout, based on feasibility studies being done. He believed that such a program would be the first of its kind in the north, i.e. the use of a lake as a mixing zone or settling basin for mine effluent discharge and still stocked and utilized as a sport fishery. Such a program would demonstrate to the public that the Company was not destroying the fishery but rather enhancing it for useful value to fishermen.
In addition, the presence of rainbow trout would act as a monitor not only for the water quality of Chocolate Lake but also for the quality of water discharged from Chocolate Lake to Namew Lake.
In response to a question, Mr. Wright said that a T.D.S. level of 200 supports a very productive fishery in some lakes; however, he deferred the question of the optimum level of T.D.S. for fish to the Environment Department.
CITIZEN
T.D.S. said 200
winter has
feasibility present unable summer
on
Lake Lake
change from
trout discharge conditions.
aware damage
engineer setting
by and
and
mine
mg/L
the
sufficient
that maintaining
obligations
Chocolate than
is
of in
of
and In months.
to
Mr.
Mr.
the
due
AND
Mr.
Fisheries
water
discharges not
of
support
Chocolate
fish
with
about
in
response
say
Chocolate
from
if Wright
Roger
ecology
OTHER adequate Wright
to
studies
adversely
He
the
Mr.
the
quality.
if
spawning an
the
oxygen
to
Chocolate
was
2300
The
provincial a
would the
this
Wright’s Smith
environmental PRESENTATIONS
Branch
lake
placed
Namew
agreed Environment very
to
sufficient
of
take
also
on
present
Lake
quality
p.p.m.
fishery
another
was in
impacted.
the
Chocolate
depth be
observed
areas
productive
Lake
should
aware
and
its
a
and
Lake.
with
understood
from
lake response
far
and Swan
pike
levels
on the
natural
is
advocated
was
on
question,
to
a that Department,
overpopulation
greater
and
verify
change —
Chocolate the
sufficient
that
However, the
suggestion Creek Company,
Lake
population
ensure
not
THE
recreational
adversely
to
-32-
some on
fish
portion
by
state
even
toxic
PAS
are
a this
effluent
in
fish
priority
the
Mr.
both
that
good
lakes
are
there
Namew
with
Lake necessary (continued)
if
that
to
for
placement
was
to
by hatchery
Wright
of
of
very parties. ______
the
saline
affect water
carry
and
the
with
Mr.
would
regard
fish
the
was that Namew
would
Lake
or
a
on
fishery
contract
healthy.
lack
Namew
Clem
a
said
lake
the
quality
the
a
a to
to
effluent
the fish
and
commercial
the be
of
be Lake
T.D.S.
to
fish
determine
survive
of
protection
possibility
Moche,
that useful
are
water
presence Lake
well that
important. a
resource
spawning
food
that
or program
population
and
stunted
level
current
which
fishery,
water
is agreement,
quality
an
so
or
in
would
he
fishery.
why
if
of
environmental
that
because
the
of
of
areas was
well
of
would
of
used
the
but
thriving
the
Namew
Narnew
receive
over stocking warmer
limits
it
not
fish
rights
above
lake
he
and
signed has
could flow
He
of
was
a
[‘1 [1
I
-j
U
I — 33 —
CITIZEN AND OTHER PRESENTATIONS — THE PAS (continued)
Mr. Frank Render, a hydrogeologist with the Water Resources Branch of the Department of Natural Resources, in response to a question, gave a brief summary of his view of the origin of the saline water surrounding the mine and the possible scenarios that might be encountered in the depressurizing/dewatering program with regard to continued water volume and salinity. There was a wide range of possibilities. Mr. Render stated that in his opinion there was a possibility that the mine depressurizing program would restrict some of the saline water normally surging upwards into the lake — as had been suggested by Mr. Fraser — so that, by good luck, a balance would be achieved; however, in Mr. Pender’s opinion, this was pure speculation.
Mr. Al Beck, a water quality specialist with The Manitoba Environment Department, in response to a question said that the level of 200 mg/l T.D.S. was a very quick and simple measure of an acceptable level for fish. An analysis of what constituents made up the 200 T.D.S. eg. chlorides, sulphates, carbonates etc. was the ultimate determination of the benefit or disbenefit to fish.
In response to another question, Mr. Beck said that he did not believe that the current proposal by the Company to discharge mine effluent to Chocolate Lake and thence to Namew Lake would adversely affect Namew Lake as a domestic water supply to a significant degree; however, protection of the Namew Narnew Lake fishery should, in general terms, assure the suitability of than humans to Lake as a domestic water source — fish being more sensitive water quality, generally speaking. Mr. Beck believed that the use of Chocolate Lake, as proposed, would help to protect Narnew Lake.
Manitoba Environment Department
Mr. Larry Strachan, Chief of Environmental Control Programs of the Manitoba Environment Department, agreed that the Chocolate Lake option was the most environmentally suitable one.
House B.
when
negotiate
exits
provide
road occasions
respond
its
conveying
lake,
quality
effluent
about
adequate one
classification
CITIZEN
recommended
impact
to
fast
to
Band.
or
for
10%
Ms.
Cumberland
Mr.
Mr.
Mr.
apply
Mr.
and
the
that
criteria
AND
temporary
protection.
from
with
moving
depressurizing
to
the
of
Delores
Moche
on
Moche
Moche
Moche
mine
under
OTHER
the
quantify
kind
the
to
end
the
receiving
the
plus
use
the
also
vehicles
so
also
stated
Lake. an
for
House,
of wastewater
the of
PRESENTATIONS
Laliberty
Department pull—off
that
classification
of
the Environmental
information
the
the
suggested
new
environmental
recommended
Manitoba
waters.
that
stocking
In
Saskatchewan
vehicles
pipe
water
effluent
are
Environment
Mr.
areas
made
his
storage
of
seen
discharging
and
Moche’s
that, Water
—
Highways department
that
He
of
a
could
could
discharging
that
THE
Engineer
to
mine
of
presentation
stated
impact
the
-34-
pond
was
be to
Act
Quality
Chocolate
PAS
opinion,
it
pull
be
water
lake
approaching
relieve
about
lacking
before would
the
into
(continued)
constructed
that
in with
had
off
with
onus
terms
to
from Objective
Chocolate
the
requested
the
be
the
Lake;
the
on
road
to
Chocolate
injection
in
trout
was
Chocolate
reasonable
behalf
construction
Company
the of
application
Environment
ahead.
the
traffic
with
at on
effluent
side
should
2A
present
Lake,
intervals the
the
of
Lake.
as
into
a
had
The
out
mixing
Lake
the
proponent
hazards,
Company
to
being
and
provide
quality
failed
the of
Department,
of
Company
of
consideration.
specify
Cumberland
to
for
this
along
harms
these.
pipeline
a
zone
Name.i
on
proper
safety
to
to
and
could
water
two
of
way
the
U
0
El F_i [1 — 35 —
CITIZEN AND OTHER PRESENTATIONS - CUMBERLAND HOUSE (continued)
The Cumberland House Band is very concerned about the potential environmental impact of discharge effluent from the Namew Lake mine and mill operation on the water quality of Namew Lake and then downstream on Cumberland Lake. The Band draws its domestic water supply from Cumberland Lake.
She stated that there had not been any consultation about the mining project with the Band and the following major concerns will have to be addressed:
1. Federal Environmental Assessment rviewed by the Federal Minister of Environment.
2. Public hearings in Saskatchewan, preferrably Curnberland House.
3. Water Quality standards established, since there doesn’t seem to be any evidence of standards set.
4. Identification of impact to drawdown area.
5. Baseline information required on effluent discharge.
6. Information on seepage of water discharge.
7. Tailings reclamation programs required.
In response to a question following the presentation, Ms Rose Thission, Environmental Worker for the Band indicated that the Lake water surrounding Cumberland House had already been badly impacted by the Saskatchewan Hydro—electric power plant development upstream on the Saskatchewan River. The already serious adverse impact of this development was a cause of concern that the water quality might be even further impacted by the Namew Lake mine. Bands’ treaty fishing. the only unable Environment District Chief Council CITIZEN Environmental the 4. 1. 3. of 2. Treaty The rights. Mr. The to Mr. AND stated Cumberland Chiefs Staff attend proposed Prince Felix Allen Offices. OTHER Cumberland The Bands discharge There fisheries consumption. on The A impacts and Federal Executive that The the Council. Peter Namew had the Felix, riparian Albert Impact PRESENTATIONS and is discharge project mine House he on four hearing. insufficient Mr. the Ballantyne on and Lake Environmental is House the District and Assessment District Officer With main individuals Band Felix’s a wildlife Federal Also, rights contemplates mine/mill Namew politically mill of Band points but Mr. — effluent the Representative, in to Band operations presentation Lake Chief’s CUMBERLAND Crown. also is information Felix resources process the — water effect Assessment using a operation to 36 and is signatory operations the elected a make; was — from a Council and substantial Cumberland signatory of the Peter in at Tamrny HOUSE have to the on the §askatchewan. was will Namew and lake official Prince hunting, to the has Ballantyne mine/mill mine not also Oleksyn, of (continued) Review Treaty water have to effects Lake. House played the violation been effluent made Albert Treaty as severe Prince trapping for should waterways. determined. #5 well the would an on Band, of between human District #6 active behalf Council’s of on environmental the Albert as be and violate who and those the being effluent conducted these the were of role Chiefs not the the
in
U
U [
F.
H
14 12
Li 1’ [Jj - 1 I — 37 —
CITIZEN AND OTHER PRESENTATIONS — CUMBERLAND HOUSE (continued)
The Bands have rights to an unpolluted source of water and damage to the fishery will violate the Bands’ rights to fish and to economic development.
Mr. Felix stated that he was not against development but was concerned about health hazards posed by the mining development.
Mayor Leonard Morin of Curnberland House stated that the livelihood of the Cumberland House Band was basically derived from trapping and fishing and that these activities were the backbone of the Cumberland House Community prior to construction of the Squaw Rapids Dam, u’pstream on the Saskatchewan River. These Band activities did not pollute the environment. Cumberland House is an island surrounded by Cumberland Lake, the Saskatchewan River and the Tearing River. Namew Lake discharges to Cumberland Lake.
Cumberland House is a mixed community of Treaty people and t4etis people. The Band has Treaty rights but the Metis people do not have special rights.
Of all the 44 northern communities, Cumberland House is the most southerly and is in a special area, unique because of big game — moose, elk, deer, and bear; wild birds — ducks and geese; and fish — sturgeon, pike, walleye, whitefish, goldeye, etc. These resources provide a living for the local inhabitants. The living was good until the Squaw Rapids Dam destroyed this livelihood and, since then, the traditional lifestyle has changed considerably. Tourism is a part of the community’s industry.
Because of the adverse effects of the Squaw Rapids Dam and the resultant destruction of trapping, fishing, and hunting, the Band filed a Statement of Claim for $200 million but has since reached a settlement for less than this amount. During this process the Band also filed a court injunction against the Francis Finiay Dam in Nipawin and again reached a settlement agreement. discharge done matter wildlife. had also destroy improved Cumberland the water. Because to from a from new, the discharge treatment CITIZEN well the been dam, river by the the good the Mr. Mayor In Namew The The Saskatchewan but Part the sone of AND no possibility road from mine. Namew of summary, water by plant, from Morin Offensive Cornniunity Cumberland Lake. a the previous Province OTHER of effluent Morin of Lake dam pail. services the water Lake Cumberland the the supply The asked on with mine Concerns Sturgeon PRESENTATIONS the was foregoing best River mine. The the treatment consultation odours of also of was from House a Cumberland and if development. interested is Saskatchewan. seepage Terring Cumberland reservoir fishing not there and is in Lake. employment Weir the This include or Community concerned of jeopardy settlement clear plant Namew air had water River, from flows good - and Before with House in beside CUMBERLAND possible emissions House been drinking will — Mr. Lake the spawning quality opportunities. system. from is from 38 the that the community this involved an mine. Fraser’s strongty not Community the — Mine Cumberland water Namew toxic Environmental pollutants health were water and was remove Big HOUSE areas into Mayor contaminants water Lake constructed is $1 Stone statements another is opposed effects is is (continued) Namew diverted in million toxic strongly House Morin obtained, now to Cross in River had Cumberland Lake. concern. Impact the to chemicals concerned for to Community stated for about Bay the around the at opposed discharge be in both by a the Assessment and discharge conveyed Community the new possible means that There humans the point that from Lake. discharge on to water there will island the the of the the was of from and
had
U
U El
F p Manitoba CITIZEN
Mr. optimum This general
but component
rule—of—thumb
important Lake, the Surface
to
Lake.
would life, it fishery trout course, continued indigenous water, standard
saline concentration
was follow
Al
in discharge
letter
as
and
provide are
Mr.
Beck
reality
Mr.
Mr. Assuming
water Mr. AND as
T.D.S.
and
Water
of
that
Environment
proposed,
recommended
factor. that
a
that
more
use
they Larry
Beck’s
Beck’s Namew
to OTHER
Christianson
addressed of
non—specific
discharge
disinfection
conditions,
to
Quality effluent
an
Namew of
of
the values
best
the
saline
sensitive
may
wastewater
Strachan
assess
added
Lake. Namew
PRESENTATIONS
other
letter
assessment
Manitoba
make—up
It would
be
promotes
Lake.
Department
practice.
a
for
is plume
Objectives
discharge
more
and
measure
Lake
chemicals
discussion,
conditions
The
agreed
way,
also the
be
to
it
representing
fisheries.
of
of
that, discharge
There
Environment susceptible
beneficial
from
most
establishment
as
is
carbonate
fisheries
that
all
a
the
contained
of
a -
appropriate that,
level
will
under Chocolate
set
would contaminants
domestic surface
CUMBERLAND
or
constituents
protection
there
for —
held
elements
for to
not
while
39
This of
Manitoba
optimum
production. fraction
such
to
likewise
Water
to
his
Chocolate
would —
at
200
the exceed
waters,
thermal
of water
such
letter
Lake
to rainbow
the
opinion
conditions,
HOUSE
mg/l
protection
a
to
that
Standards
be
than
use
of fisheries
trout
things Environment hearing
bf
for
a
Namew
not
supply,
no
before
confirmed
T.D.S.
the
acclimation
Lake
T.D.S.
may trout
(continued)
T.D.S.
other
trout
that
any
detrimental
be
fishery
T.D.S.
Lake,
as be
will
a
and
at
distance of it
recognizing,
domestic
for
might production
the
value
fish hazard
are present heavy
that
The
would
cold
read
Studies that
meet
since
tests
would
use
in
more
and
species
Pas,
be
is
of
metals.
water
effect
Chocolate
to
a
in
of
be
Manitoba’s
into
use,
in
a
mixing the
2000
rainbow
of
tolerant
letter
be
the
about
a Section. potential
Chocolate difficult
mine
of
the
very
the
aquatic Namew
is
mg/l,
on
of
a
from
the
Lake
of ______r
CITIZEN AND OTHER PRESENTATIONS — CUMBERLAND HOUSE (continued) [1
In response to a question, Mr. Strachan outlined the protection of water quality that would be given by the suggested application of Manitoba’s 2A Water Quality Objectives to Chocolate or Namew Lakes. Mr. Beck had suggested in other correspondence with the Commission that a mixing zone in the order of a lOOm radius should be considered for application to the p discharge of effluent from Chocolate Lake to Namew Lake in order to allow for Ii mixing in such a zone.
U In response to another question, Mr. Strachan confirmed that Manitoba’s Surface Water Quality Objectives contain specifit maximum level limits for a wide variety of contaminants, including heavy metals. -
F, Saskatchewan Environment Department
Mr. Randy Sentis, Assistant Deputy Minister of Saskatchewan Environment and Public Safety made the final presentation at the Cumberland House hearing.
He stated that information provided by the proponent had been forwarded [1 to Saskatchewan Environment for review. In commenting to Manitoba, - Saskatchewan raised a number of concerns related to the project and, since the original submission was received, some additional information had been provided; however, on the basis of information provided it is still not possible to adequately assess the project, and its environmental impacts.
People residing in the area, including Cumberland House and Sturgeon U Landing, are very concerned about the quality of their environment, and possible effects on resources resulting from the project. U
Despite the fact that the development has been ongoing for more than two years, the proponent has not been in direct contact with area residents. Public consultation is of critical importance in the planning and assessment of major development projects for the identification of local concerns. — 41 —
CITIZEN AND OTHER PRESENTATIONS — CUMBERLAND HOUSE (continued)
Baseline environmental data are lacking to assess effects on wildlife, vegetation, and the social community. Data are also lacking on aquatic resources and water quality. Impacts on aquatic ecosystems are of primary interest. Basic limnological/hydrological data are required.
With regard to the project description, uncertainties remain with respect to the quality and quantity of depressurizing water. There are large variations in both estimated discharge quantities and T.D.S. content. The proponent’s conclusion that an increase in T.D.S. will benefit Namew Lake cannot be supported. In addition, the proponent’ has not described the effects of depressurizing on regional systems.
More information is required on the characteristics of all waste streams, the efficiency and effectiveness of treatment systems, and final discharge quality.
Possible seepage from the tailings management area and wastewater ponds has not been adequantly addressed. It is inappropriate to use clean runoff to meet contaminant discharge standards.
Saskatchewan Environment supports a single point of discharge for all project effluents; preferably in a Manitoba drainage area or alternatively Chocolate Lake.
In the absence of adequate data, it is impossible to form an adequate assessment of possible impacts of the project on the environment. Impacts on the terrestrial environment seem to have been disregarded. The proponent seems to believe that if effluent discharge standards are met, impacts on aquatic systems will be minimal. Standards have not been established for some water quality parameters, including metals. If Chocolate Lake is utilized, surface water quality objectives should be established, including a limited mixing zone and the objectives should be used to establish effluent loading limits for both the mine/mill and the depressurizing system. — 42 —
CITIZEN AND OTHER PRESENTATIONS — CUMBERLAND HOUSE (continued)
For the purpose of monitoring the biological impacts, Saskatchewan Environment commends H.B.M.& S. for their commitment to establish a rainbow trout fishery in Chocolate Lake in 1989.
Project documentation suggests that the proponent wishes to monitor the operation and react to problems as they are identified. While monitoring is important, it does not substitute for a comprehensive pre—operation evaluation of potential impacts, which is necessary to determine environmental acceptability.
Saskatchewan is concerned that if the project is approved, they would have no input to the establishment of release standards, or access to monitoring data. Projects which directly overlap provincial boundaries demand £ a co—operative approach to ensuring environmental protection.
No contingency plans have been provided outlining planned actions in the event of a dam spill, containment pond seepage, etc. This is especially important in view of the proximity of the project to Namew Lake.
Saskatchewan believes that decommissioning and abandonment procedures should be considered and addressed in the design of a mining and milling LI project — not at the end — particularly where long—term effects may be felt in Saskatchewan. The tailings, wastewater handling and waste rock sites are areas requiring attention now.
In conclusion, Mr. Sentis stated that the Province of Saskatchewan seeks assurance that, if approved, the Namew Lake project proceed in an environmentally acceptable manner. Information available does not allow U adequate assessment of effects. Saskatchewan asks that a joint environmental control system be established between Saskatchewan and Manitoba regulatory U agencies, including joint inspections and a co—operative approach to determining requirements for licencing, monitoring and reporting.
ci — 43 —
CITIZEN AND OTHER PRESENTATIONS — CUMBERLAND HOUSE (continued)
Commenting on the Saskatchewan presentation Mr. McAuley supported the conclusions and, in addition, felt that the Federal Government should be involved in the case of a Federal/Provincial waterway.
Ms. Laliberty commented that the review period for participants had not been sufficient to allow adequate preparation for and participation in the review and consideration of the impacts on the area residents.
Mayor Morin supported the Saskatchewan Environment presentation. He also re—iterated that the Cumberland House water treatment system would not protect against toxic chemicals in the water.
Mr. Robert Kent, from Edmonton, representing Environment Canada, stated that Environment Canada will provide comments to the Province of Manitoba on the adequacy of the Environmental Impact Assessment. Minewater effluent from the Namew Lake mine will be subject to the Metal Mining Liquid Effluent Regulation under the Federal Fisheries Act. In addition, the Federal Environmental Assessment and Review Office officials are reviewing the Company’s development in consultation with the Department of Fisheries and Oceans and the Department of Indian and Northern Affairs to determine if the Federal process should apply.
SUMMARY, DISCUSSION AND CONCLUSIONS
Namew Lake Mine is a joint venture of H.B.M.&S., Flin Flon and Outokumpu of Europe. It is a nickel—copper mine located 64 km south of Flin was Flon within 1 1/2 km of the Manitoba—Saskatchewan boundary. The project registered under the Clean Environment Act of Manitoba in July, 1987. Under this Act, applications only had to be filed prior to construction and operation of a facility.
water.
Approximately
reclaim
process
since
concentrate
constitutes
the
subsequent
Mill located
estimated ore
is A
located
Department
The
distance
drains
principally
through of
Lake
Lake
is
SUMMARY,
6
located
part
HBM&S
sulfide
body
or
Pas.
construction
Athapapuskow
is
the
The
Mine
7
The
into
The
The pond.
is
beneath
at
Whitey
of
the
took
km
of
is
DISCUSSION
high
to
This
tailings discharged
stages
on
the mine
of
mine
the
Company
minerals
the
is
development
extension
Cumberland
the
contributory
Sturgeon
in
last
80%
place
the
Highways
Water
alkalinity
separated
south
road
Narrows
the
Saskatchewan
mill
Namew
is
Saskatchewan
site
of
was
to
5.5
shore
with
accessed
Province
pond
reported
at
services
AND
from
the
which
a
tailings
east
Weir
is
to
years
completed
Lake
to
fine
the
which
House
and
its
of
began
located
CONCLUSIONS
mill
a
is
into
the
to
would
the
corner
River
wastewater
contain
Narnew
120
in
hence
tributaries
decanted
product.
at
by
of
River
this
that
toad has River.
the
enters
water
copper
reclaim
and
the
in
a
and
a
Saskatchewan
be
in
which within
planned
Lake.
1985
of
community
its
gravel
to drainage
mill
is
Cambrian
was
Watershed
detrimental
the
the
320
requirements
Namew
Manitoba.
Cumberland
-44-
and
and
(continued)
discharged
junction The
pond
storage
A
with
required
drains
process
metal.
fall
in
in
the
flotation
Lateral
road
nickel.
the
production
level.
Saskatchewan
Lake.
basin.
Manitoba.
is
rock
the
of
drainage
of
and
Division.
effluent
serviced
Amisk
re—used
pond.
with
Sturgeon
wastewater
to
The
1988.
sinking
to
Lake.
to
development
formation.
discharges
will
Most
The
the process
service
Namew
a
underfiow
?TH
Lake
rate
basin
tailings
The
be
in
nickel
waste
is
The
of
by
River
Cumberland
of
Landing,
410
The
Lake
in
met
discharged
the
of
the
the
main
cannot
ore
is a
the
of
near
to
main
Saskatchewan
product
Ore
1300
shaft.
to
within
mill.
with
flotation
from
used ore
Manitoba
is
Namew
pond.
is
mine/mill
Cross
mining
intersect
reserves
Saskatchewan.
Atik,
located
inlet
be
ground
tonnes/day.
body
Lake
reclaimed
this
to
a
Lake
re—used
to
from
This
Lake
The
recover
short
complex
is
North
in
to
a
process
in
site
and which
this
are
the
shaft
turn
Namew
of
U
U
U
r fl SUMMARY, process.
discharged
and
wastewater storage
in
development throughout
reaching the mine
the
fractures
full required removed
the 115 the
flow (T.D.S.).
Company
discharge
Lake considered of and
the
mine
development
the Company
mg/i depressurizing
Company
Frewan
very
development
to
via
Federal
Unlike
A
pond. Aside
Environment
is
a DISCUSSION
but water,
Lull
in
and
As number
Frewan
which
quickly.
T.D.S.
to
pond
route
the
brackish This
as
Lake
had
established
order
at
well
all
Rocky
the
from all
production
The
Metal
alternatives. years,
300
approximately
effluent.
of to
under
compares
of
but
would to Lake
of
of
as
wastewater
of
to
Company
the
be
lateral
water
Lake L/s
AND
alternate
the
because
Depressurizing the containing
2000 mill
one
Mining
the
drop
and
Namew
stopped
full
Namew
both
CONCLUSIONS
(4000
Goose
mining that
from
mining
(Rocky
because
projected to
mg/I.
process
the
the
reported
drifts. water
Liquid
Lake
require
of
a
pond.
Lake
the
300
i.g.p.m.) wastewater
River,
10
south Two
in pressure
T.D.S.
their
an operation.
Lake)
operations
days
of has
late pressure
rock
to
wastewater,
wastewater
of
average
Effluent
of
over —
At
that (continued) Bay
the a A
350
Sturgeon
been the
Saskatchewan
range
45
detention
involved
massive
hydrogeological
1988 surrounding the
the
in
which
of
approval
mg/l. — the
discharge
the
candidate
the
water could
of the
proposed
Rocky
that
due
Unfortunately,
in
Regulations
life
discharge
objectives
4000
includes
seepage
Weir
water only
mine,
Namew
Namew
to
The
is
the
bearing flood
Lake of
of
major
the
mg/l
location.
routes available
River,
routes mine
average
flow
Commission problem. the
prevent
Lake the
Lake.
wastes
via
consultant ore
the
freshwater
via
total
would
ear
Saskatchewan prevented
water
zone
mine
rate
ranging
were
Cross — Lake
body
lower
the
Chocolate
rate
substances
Sturgeon
flooding
from
in
was The
dissolved
is
of
be
Underground
inflows
water
examined
3
have
contained
Bay the
part
of
estimated
mill
met were
retained
dilution shown
to from
the
from
pumping
wastewater
on
dealt
to
dilute
Lake, Weir
on
Department
of
and
mine
process
during
90
Namew
listed
to be
solids
by
the
the
major
allow
to
River with
by
be
by
are
the a
of
the mine storage ads hearing which water. discharge is and discredit sensitive seemed by depressurizing It basin operation discharge had had in representatives since was this available increase 300—350 SUMMMVI, reach to did the large only saline concerns been discredited site increase discharge borders of it this The note to Company The pond Rocky from mg/l mentioned discredited Rocky number serves in DISCUSSION be known is the to reaching of at water Company Namew location that T.D.S. into the dealing at changes about wastewater and the on discharge Lake of relating of Lake to as a at as from by several eggs Indian at T.D.S. Lake Goose the a concentration the the a has Chocolate Rocky is The the a of the pipeline 1%). was would AND Namew with by in primary the flow also and rock proposal 65 east proposed possibility Pas River Company Reserves mineral of to the not from could CONCLUSIONS Indian Lake. mg/i. East saline In larvae be through part Lake the T.D.S. hearing. formation end Company considered containing the Lake. the spawning extremely location short have wastewater as since of discharge Reserves. of to of concentration Direct In of located case mining rather and advertised the discharge a the 0.2% of some the The fisheries cottagers in — (continued) small They and the of spawning seepage and would system 46 Root discharge by its view long. the before than outlet operation impact near the its T.0.S. — proposal. to had them rearing lake There proposal. depressurizing and be of effluent Namew brackish the would impacts included Reeder although fish concerns group from The dilution areas to from on minimal the some Reeder in were south of be area to this Rocky are Lake any company the result Chocolate effluent of 6 Lake did a on Namew from water no The only km Lake usually basin part the possibility about Rocky area for and Lake mine in Rocky Lake representives not north since reference in water. the documentation the a Lake; the the representative, drainage of of (sea ranges wastewater, of necessarily the to Lake discharge reference a Lake Lake. wastewater the receiving the Lake Rocky pipeline further east Rocky the the water however, The were most mining since is from newspaper presented south fishery. of system They Lake pipeline Lake. located at at present to route the to the it the 3.5%
also
U
Li
I
fl
fl LI — 47 —
SUMMARY, DISCUSSION AND CONCLUSIONS (continued) at the west end of the Lake. Chocolate Lake is a tributary to Namew Lake in the vicinity of the mine site. The Company has proposed that the discharge be restricted to a T.D.S. level of 2000 mg/l with the expected discharge being 300 L/s (4000 i.g.p.m.). In the event that this T.D.S. concentration is exceeded, make—up from Namew Lake will be used to dilute the effluent. The purpose of utilizing Chocolate Lake is to act as a reservoir in adjusting the temperature of the effluent and equalizing the chemistry of the discharge. If the depressurizing water was to be discharged directly to Namew Lake, there was a concern that thermal stratification would occur with a concentration of the brackish water in one area of Namew Lake. This concentration of wastewater could significantly impact the area of the lake containing the higher level of mineralization. The Environment Department representatives felt that the Chocolate Lake discharge would mix with Namew Lake and would not be prejudicial to the Lake fishery. The view was also expressed that the impact to the water supply at Cumberland House would be insignificant. The Company reported that both lethal and chronic toxicity tests had been conducted on the depressurizing water as well as the effluent from the wastewater pond and the results had exceeded the toxicity requirement under the Federal Metal Mining Regulations. The Company had also agreed to work together with the Fisheries Branch in stocking Chocolate Lake with trout. It was the expectation that Chocolate Lake would become a valuable sport fishery with the introduction of trout. A Manitoba Fisheries Branch representative felt that not only would the trout fishery be attractive but would also act as Narnew a large scale bioassay to monitor the wastewater before discharge to Lake.
At the request of the Minister of Environment of Saskatchewan, the Commission were asked to reconvene a hearing at Cumberland House, Saskatchewan in order to communicate directly with residents in that area located on Cumberland Lake. This includes the community of Cumberland House and 2 Indian Reserves. There is also a settlement and an Indian Reserve located at the Sturgeon inlet to Namew Lake at Sturgeon Weir Landing. The residents of Landing were represented by a resort operator and outfitter from this location would dilution concerning discharge before well to were be benefits purposes. sufficient outlet treatment. waters information portion commercial and Lake Manitoba, well was Landing, in Environment Cuinberland the at SUMMARY, the discharged Saskatchewan the question to Prince as not system represented also merits The being of The of the hearing aesthetics. of of accrue impacts Cumberland DISCUSSION limit. Cumberland Namew, the Commission be detail majority the Namew and effect Albert Lake. the contained Residents as and released the and significantly to principal a impacts for at wastewater to Natural and Namew water that Cross proponent. Lake. by validity It for Representatives District that The Saskatchewan sustenance of therefore House both AND was Perhaps Lake concludes would to the located in Pas. Lake. on the and supply. although Resources The portion CONCLUSIONS Chocolate also the local Namew and residents for with of presentations Cumberland Chiefs diluted affect Commission Cumberland proposal the The a noted Saskatchewan along municipal purposes. the the officials and trout that fresh Lake Cumberland of the main concern were with which impacts 2 Lake. the the by that and its the Namew Indian -48- (continued) there from water fishery theme by Lake the was residents’ wastewater in the House water the residents, Lake includes wastewater the to The expressed and would the attendance Lake are addition representatives House Reserves for told Saskatchewan agencies was from the withdrew Company residents and a in outflow supply still Mine district its Commission the occur that Chocolate Namew withdraws the the health receiving the by fishery of view from project were uncertainties was to purposes residents to 2 2 water of all in depressurizing wastewater Lake also reserves Indian be make Departments representative the and that incomplete Chocolate dependent the of were assured Lake water indicated both to for depend water is wastewater livelihood Saskatchewan a the since following Reserves meet of presentation located and opposed domestic sport, located presentations from should Sturgeon is with that Lake, upon upon also a and no of that located water the in were from pond regard to as there lacked the on the not the
the
U
U
U
U El — 49 —
SUMMARY, DISCUSSION AND CONCLUSIONS (continued) particularly near the discharge location. The major uncertainty is connected with a lack of knowledge of the volume and character of the underground depressurizing water. Based upon figures provided by the Company on the volume of Chocolate Lake, the volume of wastewater, and the spring run—off contributions to Chocolate Lake, the T.D.S. of the outflow from Chocolate Lake will he significantly less than the T.D.S. of the depressurizing water discharge to Chocolate Lake (2,000 mg/l) for a period of at least 1 year. Chocolate Lake, without any other source of inflow and based on laminar flow, would provide a residence time of close to 1 year. Whatever impacts occur in Namew Lake will be much less than those which would occur in Chocolate Lake. The Commission believes that this period of time would provide an opportunity for investigations to be undertaken by the Company with guidance from representatives of all parties who have an interest in Chocolate and Namew Lakes.
RECOMMENDATIONS
The Commission recommends:
1. That a temporary licence be issued to the applicant for the Narnew Lake Mine project, expiring on July 31, 1990, that will permit the Company to discharge water from the depressurizing of underground rock and effluent from the wastewater storage pond into the east end of Chocolate Lake.
2. That the combined flow of water and wastewater from depressurizing and from the wastewater storage pond of the said project be stored effectively in Chocolate Lake so that the temperature of the discharge from the lake will correspond as nearly as possible with water in the near shore area of Namew Lake at the location of the outflow of Chocolate Lake and so that Chocolate Lake will also act as of the an averaging basin for the chemical characteristics inflow. U
-50-
RECOMMENDATIONS (continued)
3. That the Manitoba Department of Environment establish limits on the wastewater storage pond effluent of the said project to meet cold water aquatic life water quality objectives in Chocolate Lake exclusive of the discharge [1 from the depressurizing effluent but taking into account a mixing zone in Chocolate Lake. (Manitoba Surface Water Quality Objectives, 1988; sections 1.9 and 2.2.1).
4. That the discharge from the underground mine depressurizing program from the said projecb be pumped to Chocolate Lake [} at a rate and concentration not exceeding 300 L/s (4000 i.g.p.m.) and 2000 mg/l total dissolved solids.
5. That the mill tailings effluent from the said project be recycled to the mill for use as process water at a rate of at least 80% of the mill water requirements. Investigations should continue into the reclamation of additional mill tailings or mill process wastewater.
6. That a Committee consisting of a representative of the Manitoba Department of the Environment, Manitoba Department
of Natural Resources — Fisheries Branch, Manitoba
Department of Natural Resources — Water Resources Branch, Saskatchewan Department of the Environment, Saskatchewan Department of Natural Resources, a resident of Cumberland House and a resident of Sturgeon Landing be formed to U collaborate with the applicant for the following purposes:
Li
Li
a! I — 51 —
RECOtIIIENDATIOt4S (continued)
6. Ca) to identify an effective monitoring program on all aspects of the liquid wastewater handling system of the project to be undertaken by the applicant. In the interim, until the committee is functional, the applicant shall undertake a monitoring program (Notes 1 and 2) as identified on pages
37 & 38 of the applicant’s presentation to the Commission and overhead 15 presented at the hearings in June, 1989 by the applicant;
Cb) to identify limnological surveys that the Company will undertake on Chocolate and Namew Lakes that will enable the evaluation of the impacts of the wastewater discharges from the project on Namew Lake and also the ability of Chocolate Lake to support a population of sport fish;
(i) surveys to be undertaken shall include samples and analysis of the domestic water supply of the communities of Cumberland House and Sturgeon Landing.
Cc) to identify a program that the applicant will undertake on
Lake B south of the minesite and also the south basin of Rocky Lake to determine the impacts on walleye rearing in the south basin in the event that a decision must be made to utilize this drainage route for wastewater from the project; Cd) to collaborate with the Company in identifying the best method of operating the reclaim, tailings and wastewater storage ponds to prevent emergency spills through the overflow structures directly to Namew Lake under all but extreme conditions of precipitation; r
-52-
RECOMMENDATIONS (continued) I
(e) to identify a tailings pond rehabilitation program. H
This Committee shall be chaired by a representative of the H Manitoba Department of the Environment who will, in collaboration with the Saskatchewan Department of the p Environment select a representative from the Saskatchewan Li Department of the Environment, the Saskatchewan Department of a Natural Resources, and representative from each of the H Saskatchewan communities of Cumberland House and Sturgeon Landing. This selection process shall begin immediately and the Committee shall begin meetings before August 31, 1989. The applicant shall be responsible for payment of the expenses of the Saskatchewan members of the Committee to attend the meetings.
(i) This Committee shall make a report at the end of each month to the “Director of the Manitoba Department of Environment.
El
7. The Company shall make a full report, including up to date information from its hydrogeological consultant, on the status 1 and results of the Company’s depressurizing/dewatering program including an assessment of the hydrogeological effects on the surrounding area affected and the quantity and quality of the water being withdrawn. This information shall be made available to the Committee prior to its first meeting (August 31).
ci
‘I
Li — 53 —
RECOMMENDATIONS (continued)
B. That the Clean Environment Commission shall convene a hearing or hearings to hear representations based on the studies undertaken by the Company on behalf of the Committee named in Clause 6, and any other recommendations of the Committee, the main purpose of which hearings would be to determine possible further mitigative measures that might be undertaken on the wastewater discharge or to prescribe an alternative discharge method. This hearing shall be held on or about July 1, 1990.
In this regard, should the Committee detrmine before this date that Namew Lake is being or will likely be adversely affected to an unacceptable degree, the Committee shall request the Clean Environment Commission to hold a hearing to review the situation before this date.
NOTE 1 [Reconunendation 6(a)] — Copy of Overhead 15
MONITORING:
— Quality
— Flows
(A) Underground Flows — bi—weekly (B) Mill Process Tailings Discharge
Tailings Weir — weekly Reclaim Reservoir Depressurizing Mine Final Stamp
(C) Namew Lake Supply — hi—weekly
Intended Quality — Federal Limits
— Aquatic Toxicity Tests
Receiving Body — Quality Monitoring
— Limnology, etc. [1
— 54 —
NOTE 2 [Recommendation 6(a)] — pages 37 and 38 of Applicant’s Presentation to the Commission U Monitoring programs have been established at the Narnew mine/mill site to gather effluent quality and flow data on the various streams, discharges U and receiving bodies. These programs will also indicate changes in effluent quality which could require incorporation of or changes to treatment techniques.
Sampling locations have been chosen underground at different levels to monitor the quality of various flows which ultimately report to the final underground sump for discharge to surface. Theunderground samples are 1] collected by Mine Department personnel on a bi—weekly basis and delivered, to the Hudson Bay Analytical Department in Flin Flon for analysis. fl Effluent discharges from underground and surface mill operations are directed to effluent containment areas adjacent to the mine/mill complex. Weekly samples of mill process water discharge, tailings discharge and final discharge from the tailings containment area prior to entering the reclaim reservoir, are collected by Mine Department personnel and delivered to the Hudson Bay Analytical Department for analysis. Bi—weekly samples of Namew Lake raw water supply and minewater discharge from the final underground sump to surface are collected by Mine Department personnel and delivered to the Hudson Bay analytical Department for analysis.
Monitoring program results will be considered with respect to standards established for quality. It is intended that the effluent quality of the wastewater storage pond discharge and tailings/reclaim pond system discharge, if there is any, will meet the Federal Mine/Mill effluent regulation limits and pass aquatic toxicity tests as outlined in the Canadian Fisheries Act. (Metal Mining Liquid Effluent Guidelines). Final discharges to Namew Lake will produce, outside of an immediate mixing zone, only trivial or non—significant elevations of constituents. Appropriate lake quality sampling and monitoring surveys will none—the—less be conducted.
I
U
Li
Li
I
LI
‘LI
Li
n
U
U
U
H