<<

Page 1

ANNEXURE - I LIST OF COMPLETED PROJECTS AGAINST WHICH COMPLETION CERTIFICATES SUBMITTED TO MINISTRY OF DoNER. Sl. SECTOR/NAME OF ESTIMATED Year of Funds Remarks No. PROJECT COST (Rs. Sanction Released. SANCTIONED In crore) ( Rs in crore ) 12 345 6 PH & WS: 1 Water Supply scheme 10.590 1998-99 10.590 Completion Certificate at submitted. 2 Special Restoration of 2.000 1999-2000 2.000 Completion Certificate Water Supply facilities submitted. at .

IFCD: 3 Flood Control work at 7.470 1999-2000 7.470 Completion Certificate Sisiri and Dibang to submitted. protect Bizari

4 Anti Erosion work at 6.876 1999-2000 6.876 Completion Certificate Noa-Dehing to protect submitted. Namsai and Lekang Circle

5 Anti Erosion work of 4.450 1999-2000 4.450 Completion Certificate Tirap river from submitted. Phangtip to Kutchep-I

6 Flood Protection work 7.486 1999-2000 7.486 Completion Certificate on right bank of Siang submitted. river to protect township.

7 Flood Protection work 7.190 1999-2000 7.190 Completion Certificate on Sipu and Siyom submitted. river to protect Along Township.

8 Flood Protection work 5.470 1999-2000 5.470 Completion Certificate at Siyom river to submitted. protect Gaki Cultivation area at Jumlo.

9 Anti Erosion work on 4.147 1999-2000 4.147 Completion Certificate Siyom river to protect submitted. Donyi Polo Govt. College, Kamki. Page 2

Sl. SECTOR/NAME OF ESTIMATED Year of Funds Remarks No. PROJECT COST (Rs. Sanction Released. SANCTIONED In crore) ( Rs in crore ) 12 345 6 10 Flood Protection work 3.234 1999-2000 3.234 Completion Certificate to protect submitted. township. 11 Anti Erosion works on 0.709 1999-2000 0.709 Completion Certificate Kley River (L Subansiri submitted. District) 12 Flood Control work at 2.150 1999-2000 2.150 Completion Certificate Dibru river at Seijosa. submitted.

13 Anti Erosion works to 2.600 1999-2000 2.600 Completion Certificate protect submitted. township

14 Anti Erosion works to 2.100 1999-2000 2.100 Completion Certificate protect submitted. township 15 Anti Erosion works at 2.300 1999-2000 2.300 Completion Certificate Deopani river to submitted. protect Roing township.

16 Flood Control Works 1.437 1999-2000 1.437 Completion Certificate on right bank of submitted. Dikrong river to protect NH-52A near .

17 Treatment of Aba 2.980 1999-2000 2.980 Completion Certificate river basin at Old submitted. Abali village 18 Anti Erosion works on 7.310 2001-02 6.930 Completion Certificate Kley River (L Subansiri submitted. District)

PWD: 19 Maintenance of Foot 1.000 1999-2000 1.000 Completion Certificate Track & Suspension submitted. Bridges. 20 Construction of Porter 2.590 2003-04 2.550 Completion Certificate Track from Nuranang submitted. to Mago. Page 3

Sl. SECTOR/NAME OF ESTIMATED Year of Funds Remarks No. PROJECT COST (Rs. Sanction Released. SANCTIONED In crore) ( Rs in crore ) 12 345 6 21 Improvement and 2.550 2002-03 2.550 Completion Certificate realignment of porter submitted. track from Jang to Sulungthi.

EDUCATION: 22 Furniture for 1557 1.630 2001-02 1.630 Completion Certificate Primary and Middle submitted. Schools and Hostels.

23 R.K. Mission School, 12.200 2001-02 12.200 Completion Certificate Narrottom Nagar in submitted. .

24 Ramakrishna Sarada 3.000 2001-02 3.000 Completion Certificate Mission Girls School submitted. at , Tirap district.

25 Infrastructure Dev for 0.800 2001-02 0.800 Completion Certificate VK V, Koloriang. submitted.

26 Construction of 0.590 2002-03 0.590 Completion Certificate Academic Block of submitted. Arunachal Pali Vidyapeeth-Phase-I.

27 Infrastructure 40.000 2002-03 24.000 The project has been development of directly monitored by the NERIST. Ministry of HRD.

28 Construction of 0.810 2004-05 0.810 Completion Certificate Academic Block of submitted. Arunachal Pali Vidyapeeth (Phase-II)

29 Financial Assistance 14.480 1999-2000 5.540 Ministry of DONER vide for completion of 532 F.No. DNER/NLP/AP/ incomplete school 20/2002 dated 05.12.2006 Buildings, Teachers has closed the project. Quarter and Hostel.

30 Infrastructure 5.820 2001-02 5.51 Completion certificate development of 275 submitted Community schools running pre-primary classes in villages. Page 4

Sl. SECTOR/NAME OF ESTIMATED Year of Funds Remarks No. PROJECT COST (Rs. Sanction Released. SANCTIONED In crore) ( Rs in crore ) 12 345 6 POWER: 31 2X5 MVA S/S at 1.690 2000-01 1.690 Completion Certificate submitted. Shortfall amount of Rs.0.20 crore met from State Plan fund.

32 2X3.15 MVA S/S at 1.430 2000-01 1.430 Completion Certificate Nirjuli submitted. 33 Rural Electrification 8.960 2000-01 8.960 Completion Certificate of 60 Nos. Tribal submitted. villages. 34 2x5 MVA 33/11 KV 2.640 2002-03 2.640 Completion Certificate S/S at Old . submitted. Shortfall amount of Rs. 0.26 crore met from State Plan fund.

35 Sub-Transmission & 0.680 2002-03 0.300 Physically completed. Distribution -33 KV Financial liabilities to be Express Line from cleared. The Ministry has Tago-Old Ziro.(Lower been requested to release Subansiri District) the balance fund of Rs.38.00 lakh vide letter No. PD(PMC)22/ 2003 dated 04.08.2008. Reminder sent on 13.2.09.

36 33 KV Line from Geku- 16.530 2002-03 15.803 Completion Certificate Along- Pasighat submitted.

37 Sub-Transmission & 0.550 2002-03 0.500 UC and Completion Distribution - 2X5 Certificate submitted to MVA 33/11 KV at Ministry of DoNER vide Sangram (Kurung letter No. Kumey) PD(PMC)21/2003 dated 08.12.2009.

Health. 38 R.K. Mission Hospital, 1.360 2000-01 1.360 Completion Certificate Itanagar. submitted. Page 5

Sl. SECTOR/NAME OF ESTIMATED Year of Funds Remarks No. PROJECT COST (Rs. Sanction Released. SANCTIONED In crore) ( Rs in crore ) 12 345 6 39 One time Grant for 20.000 2007-08 20.000 Amount has been handed Corpus Fund for over to RK Mission R.K.M. Hospital, Hospital, Itanagar. UC Itanagar (PM's submitted to DoNER vide Package). letter dated 11.2.09. As per DoNER's record UC is yet to be received.

40 Upgradation of 4.076 2005-06 3.668 State matching share of Rs.40.76 medical equipments at lakh provided. R.K. Mission Hospital, Itanagar.

GRAND TOTAL: 223.885 196.650

ANNEXURE-I (A). List of incomplete projects for which full release has been made. (Rs. In crore) Sl. Name of project Approved Year of Total UC Last Release Status No. Cost Sanction Release submitted Amount Date

12 345678 9 Road & Bridges 1 Improvement of 7.440 2005-06 6.695 6.458 2.176 13.02.08 70 % work completed. Palizi to Thrizino Road (17 KM.) West Kameng. Education 2 Hostel Buildings 22.000 2002-03 22.000 22.000 6.000 20.7.04 UC for the entire amount submitted for 110 Primary to DoNER. Deptt is to submit and Middle Completion Certificate. Schools (All Districts) 3 Sarva Shiksha 8.200 2005-06 8.200 8.200 8.200 28.3.06 UC submitted on 23.5.08. Abhiyan (2005- 06) 4 Sarva Shiksa 14.288 2006-07 14.287 8.220 6.068 31.03.08 UC for Rs. 8.219 crore submitted on Abhiyan (2006- 23.5.2008. Deptt is to submit 07) completion certificate. Department is to submit UC for balance amount along with completion certificate. Power 5 Kathalguri- 29.450 1998-99 29.450 28.510 17.420 17.09.03 -NLCPR commitment fully met. - Deptt is to submit UC for balance Transmission Line amount and completion certificate. (Tirap District) - Para-wise replies to the observations made by by the Ministry has been submitted to the Ministry on 24.10.08. 6 Sub-T&D - 2x5 1.720 2002-03 1.720 1.720 0.970 29.7.04 Completion Certificate submitted by KVA Sub-Station Power department has been returned at (West back to the department for obtaining Kameng ) counter sign of Secretary (Power) on 2.7.07. 7 Sub-T& D - 33 2.870 2000-01 2.799 2.300 0.499 26.5.08 Complettion Certifiate submitted to KV DC Line from Ministry of DoNER on 12.05.2009.. Nirjuli to Itanagar Department is to submit the UC for (Papum Pare balance amount of Rs. 0.499 crore District) released during May, 2008. 8 132 KV Ziro- 53.170 1998-99 52.810 52.436 3.200 31.01.07 A revised estimate for Rs. 62.17 -Along crore against the original estimated Transmission Line cost of Rs. 53.17 crore have been (Ziro- Lower submitted to Ministry of DoNER vide Subansiri, Planning Department's letter No. Daporijo- Upper PD(PMC)14/2003 dated 08.03.2006.'- Subansiri, Along- - Para-wise replies to the West Siang observations made by the Ministry District) has been submitted to the Ministry on 24.10.08

Total 139.138 137.961 129.844 44.533

File: Desktop/Xls./Status of NLCPR projects in AP /sheet/full release (08.04.2010) List of ongoing projects ANNEXURE- I (B) (Rs. in Crore) Sl. Name of Project Approved Year of Total UC submitted Last Release Status No. cost Sanction Release Amount Date 12 3456789 PH&WS (Eastern Zone): 1 Water Supply scheme at Along. 3.370 1999-2000 3.021 3.021 0.020 20.02.04 Excess expenditure of (West ) Rs.2.74 crore is made from State Plan fund. A revised estimate at an estimated cost of Rs.8.155 crore against original estimated cost of Rs.5.775 crore with NLCPR support of Rs. 3.37 crore have been submitted to Ministry of DoNER on 25.5.2005. 2 Water Supply scheme at 5.050 1999-2000 4.850 4.850 2.850 20.02.04 Field inspection report Pasighat () submitted to DoNER vide letter No. PD (NLP) 14/2006 dated 20.1.2009. 3 Water Supply scheme at Roing 4.050 1999-2000 3.829 3.829 1.830 20.02.04 A revised estimate at an (Lower ) estimated cost of Rs. 19.17 crore against the original estiamted cost of Rs.4.047 crore have been submitted to Ministry. Ministry of DoNER has been requested to reimburse the contingency expenditure of Rs.11.79 lakhs vide letter No. PD (PMC) 25/2003 dated 16.2.2009. 4 Providing Potable Drinking 17.424 2006-07 10.490 4.592 5.000 27.03.09 Clarification of PHED Water Supply scheme for including revised QPR and villages of Sille, Rani, corrected inspection note Sikabamin, Sika Tode, Oyan at submitted. Physical Sille. (East Siang District) achievement is 28%. Field Inspection Report submitted to DoNER on 09.06.2009. 5 Providing Potable Drinking 20.534 2009-10 7.247 0.000 7.247 23.03.10 Water Supply to Mebo Sub- Divisional HQ and adjoining villages. PH&WS (Western Zone): 6 Water Supply Project for 3.970 2002-03 3.666 3.574 3.299 01.07.04 Work Plan 2008-09 and Daporijo town, (Upper item-wise details of actual Subansiri District). expenditure on contingency components forwarded to Ministry of DoNER on 25.03.2009. FIR forwarded to DoNER on 09.06.2009.

7 Naharlagun- Nirjuli Water 11.730 2002-03 11.040 11.040 1.180 27.03.06 Work Physically Supply scheme. (Papum Pare) completed. Ministry of DoNER has been requested to reimburse the contingency expenditure of Rs.34.05 lakhs vide letter No. PD(PMC) 27/2003 dated 16.2.2009. 8 Bomdila Water Supply Scheme. 17.090 2002-03 15.435 15.421 2.830 26.03.07 UC for Rs. 68.69 lakh () submitted to DoNER vide No. PD(PMC)24/ 2004 dated 09.06.2009. 12 3456789 9 Improvement and extension of 4.883 2006-07 4.266 3.138 1.128 16.03.09 F.I.R. submitted to DoNER water supply at Lumla vide No. PD(PMC) 24/ township. ( District) 2004 dated 09.06.2009. 10 Providing/Augmentation of 12.772 2007-08 10.000 7.400 2.000 25.03.10 2nd installment released Water Supply facilities to all the during March, 2009. FIR administrative HQs and it’s forwarded to DoNER vide villages under 14th No. PD(PMC)24/ 2004 Assembly Constituency. dated 09.06.2009. Roads & Bridges, P.W.D. (Western Zone) 11 Improvement of Porter Track 3.106 2003-04 2.714 2.714 1.740 22.12.06 Work completed. from Tungri to Mago (West Department is to submit Kameng District) Completion Certificate. 12 C/O road from Dipu Lamgu 4.172 2005-06 3.646 2.794 1.052 24.03.09 bridge point to Pipu (14 KM). () 13 C/O Road from Bameng to Lada 8.902 2005-06 5.150 2.387 2.763 13.01.10 Target date of completion (70 KM). (East Kameng 2009-10. District) 14 C/O road from Lhou Nallah to 18.030 2005-06 15.754 12.953 4.801 19.12.08 60% work completed. 3rd Mukto CO Hq. via Gomkeling instalment released during and Serjong (15 KM) PH-I 0-5 Dec.'08. KM (Tawang Dist) 15 Road from NH-52A Nirjuli to 20.484 2005-06 17.899 14.356 5.963 16.01.09 60% work completed. 3rd Sagalee (SH: Doimukh to Toru instalment released during (45 KM). () Jan'09. 16 Improvement / Construction of 39.940 2005-06 33.824 30.430 9.562 16.01.09 55% work completed. 3rd road from Sagalee to Sakiang instalment released during (50 KM.) (Papum Pare Jan'09. 17 C/O. Road from Pakke to Wai 13.354 2005-06 11.669 10.006 3.462 25.03.09 U.C. submitted on (18 KM.) (East Kameng 19.08.2009. District) 18 C/o road from Nafra to Nakhu- 7.540 2005-06 6.247 4.231 1.991 27.11.09 3rd instalment released on Nachiban village (11 KM). 27.11.2009. Target date of completion 2010-11. Physical progress as on March, 2009 is 50%. 19 C/o Bailey Bridge (Steel Girder 8.541 2007-08 2.691 0.206 2.691 31.12.07 U.C. submitted on Bridge) between Namara and 19.08.2009. many other villages under Seijosa Circle in . 20 C/o Gacham-Morshing road 19.625 2008-09 13.108 6.043 7.065 08.01.10 Target date of completion (24.50 KM) March 2011. Physical progress as on Nov, 2009 is 31%. 21 Construction of Road from 15.672 2009-10 4.937 0.000 4.937 05.08.09 Released recently. Magopam to Bichom via Namfri (50 KM) via Ditching, Sacheda, Ramu-Sotu and Lichini under Singchung sub-Division in Arunachal Pradesh.

22 Construction of Arunachal 91.868 2009-10 33.072 0.000 33.072 31.08.09 Pradesh Civil Secretariat Building at Itanagar. 23 Improvement of Tawang 4.896 2009-10 1.728 0.000 1.728 16.02.10 Township road network Roads & Bridges, P.W.D. (Central Zone) 24 C/O. Road from Jop to Silsango 34.500 2005-06 30.110 22.364 7.774 17.03.10 (30 KM) in . 25 C/o Tamen Tali Road via 8.981 2008-09 6.062 6.062 3.233 04.01.10 Target date of completion Yarkum (60 KM) (Ph-I) 0.00- 2011-12. Physical progress 49.00 KM. as on March, 2009 is 25%. 12 3456789 26 Constrcution of road from 8.817 2008-09 5.465 1.326 2.688 17.03.10 Sangram to Phassang-Pallang via Nyapin (SDO HQ) Ph-I. 27 Restoration and Upgradation of 13.999 2008-09 9.360 4.400 4.950 12.03.10 32 KM internal road at Ziro township. 28 Construction of Road from 7.691 2009-10 2.769 2.700 2.769 13.01.10 Ziro BRTF road to Krishi Vigyan Kendra at Yachuli.

29 Construction of Steel 8.616 2005-06 7.755 5.714 2.041 18.03.10 Suspension Bridge over Subansiri river near Siyum (Span 174 Mtr.) () 30 Improvement / upgradation of 3.570 2005-06 2.408 1.124 1.284 16.03.10 UC for Rs. 17.07 lakh Menga - Giba Road ( 8 KM ) forwarded to DoNER on (Upper Subansiri District) 27.08.2009. 31 C/o Permanent Suspension 7.640 2005-06 6.678 5.406 1.268 11.03.10 UC for Rs.94.63 lakh bridge over river Siyom at forwarded to DoNER on Paksing (122 mtr) (West Siang 27.08.2009. District) 32 C/O. Road from Nyorak to 9.900 2005-06 6.395 2.845 3.550 18.03.10 Rime Moku village in (20 KM, Ph-I - 9.20 KM) 33 C/o Dupmorijo Hali road (45 31.764 2007-08 21.020 9.809 11.211 16.03.10 KM) 34 C/o Wak Liromoba Road (78 6.600 2008-09 4.360 2.030 2.330 12.03.10 KM) Phase-I (15 KM)

Roads & Bridges, P.W.D. (Eastern Zone) 35 C/O Motorable Suspension 13.100 2005-06 8.252 8.126 4.126 16.03.09 UC for Rs. 215.00 lakh Bridge over Lohit river to forwarded to DoNER on connect Manchal Circle 27.08.2009. Headquarters. (Lohit/) 36 C/O Steel suspension Bridge 13.960 2005-06 9.736 4.397 5.339 28.03.09 Physical achievement is over Siang river at Kodak near 30%. . () 37 C/O. Motorable Suspension 25.220 2005-06 13.777 5.177 10.000 27.03.09 UC for Rs. 140.00 lakh bridge over river Siang at the forwarded to DoNER on site of Gandhi Bridge. (Upper 27.08.2009. Siang District) 38 C/o road from Jengging to 5.370 2005-06 3.690 3.690 2.000 19.02.08 UC, QPR for March, 2009, Ramsing in Upper Siang District photographs and inspection (30.20 KM) (Upper Siang report forwarded to District) DoNER vide letter No. PD(PMC)39/2004 dated 07.05.2009. 39 C/O. Motorable Suspension 18.344 2005-06 5.778 1.709 5.778 26.09.07 UC for Rs. 12.84 lakh Bridge over river Siang between forwarded to DoNER on BRTF road and Komsing (Span 27.08.2009. 225 m) at Sangam in East Siang District. 40 C/o Satnaguri to Longding road 5.660 2007-08 4.992 3.747 1.245 09.02.09 3rd installment received via Kanubari, Banfera, Wanu during December, 2009. and Zedua (Phase-I) (15.50 Target date of completion KM). 2010-11. 41 C/o road from to 8.587 2008-09 5.572 0.000 3.031 22.03.10 Khimiyang (36.10 KM) 12 3456789 42 C/o road from New Mohong to 3.554 2008-09 1.120 0.930 1.120 18.11.08 Detailed justification in Mahadevpur township via response to DoNER's letter Nongkhon (12 KM). dated 27.04.2009 for a separate carriage cost for constrution materials have been forwarded to DoNER vide letter No. PD(NLP)11/2007 dated 20.05.2009. UC for Rs.30.00 lakh forwarded 43 C/o road from Hawai to 32.530 2008-09 10.247 1.292 10.247 18.11.08 UC for Rs.129.20 lakh Manchal Bridge Point (55.77 forwarded to DoNER on KM) 27.08.2009. 44 Construction of road from BRO 22.140 2008-09 6.974 0.000 6.974 30.03.09 road (4 KM Point) on Dambuine road to Etabe in Dibang Valley dist. 45 Improvement and Extension of 18.621 2008-09 5.752 0.000 5.752 31.03.09 Dosing Pareng Sine Yibuk road (Ph-I) 46 Construction of Single Lane 3.404 2008-09 1.072 0.500 1.072 30.03.09 UC for Rs.50.00 lakh Bailey bridge (Span 40 Mtr.) forwarded to DoNER on over Tatsing river between 27.08.2009. Borguli and Seram village on Mebo-Dhola Road. 47 Construction of Namsang - 4.947 2009-10 1.781 0.000 1.781 04.01.10 Khela road (45.30 KM) 48 C/o Motorable Steel Arch 6.344 2009-10 2.284 0.000 2.284 09.02.10 Released recently. Bridge over river Yamne at Reglat under Mariyang Division Span 90 Mtr. 49 C/o road from PWD road from 13.532 2009-10 4.776 0.000 4.776 15.02.10 Kamhua Noknu village (Pongchau Circle) to Nginue- BRTF road point (Wakka Circle). 50 C/o road from Jia Tinali to 15.446 2009-10 5.452 0.000 5.452 08.02.10 Roing-Shantipur road (Ch:9.20 KM) to Bizari via Idilli (19.80 KM). 51 C/o Road from Pugging to 15.301 2009-10 5.401 0.000 5.401 16.02.10 Palling in Arunahal Pradesh R.W.D 52 C/O. Road from NH-52 'A' to 3.990 2005-06 1.257 0.000 1.257 27.09.07 A fax message requesting Pappu Hill settlement (2 KM) in CE, RWD to submit UC, AP latest QPR, inspection report, photographs and action plan for 2008-09 have been sent vide No. PD(NLP)MISC/08-09 dated 20.03.2009. 53 C/O. road from Sille to Yagrung 5.010 2007-08 1.578 1.578 1.578 27.03.08 Department is to expedite village in East Siang District ( utilization of fund. 10 KM). 54 Construction of road from Kheti 10.871 2008-09 3.424 3.424 3.424 31.03.09 to Dadam (21 KM) in Arunachal Pradesh. EDUCATION: 55 Ramakrishna Mission School at 2.560 1998-99 2.182 2.182 0.900 19.03.04 Report of DC, on the Along (West Siang District) alleged misappropriation of fund have been forwarded to Ministry of DoNER vide No. PD(PMC)53/2005 (Part) dated 23.03.2009. 12 3456789 56 C/O 200 seats Girls Hostel, 5.151 2005-06 4.501 4.501 1.303 20.03.09 auditorium, Laboratory, security fencing etc. in JN College, Pasighat. 57 Construction of 150 boarders 0.950 2005-06 0.830 0.830 0.531 27.09.07 UC submitted to DoNER hostel at Koloriang HS school. on 24.09.2008 () 58 Reconstruction of Higher 3.023 2005-06 2.642 2.635 0.690 03.02.09 UC for Rs. 68.32 lakh Secondary School, Anini. forwarded to DoNER on (Lower Dibang Valley District) 27.08.2009. 59 Vivekananda Kendra Vidyalaya, 5.210 2005-06 4.552 3.641 0.911 09.02.09 UC, QPR for July,2009, Kitpi in . work plan FIR and photograph submitted to DoNER on 13.08.2009. Querries of DoNER vide letter dated 09.12.2009 forwarded to Dir(School Edn) on 23.12.2009.Target date of completion 2009-10 60 Infrastructure Development of 3.100 2007-08 0.977 0.977 0.977 Application under RTI School run by Arunachal forwarded to nodal Welfare and Education Society, department on 12.1.09. Itanagar, Arunachal Pradesh- Target date of completion Construction of JNK School 2010-11. UC, QPR March, Building 2009, photographs and work plan forwarded to DoNER on 03.12.2009. 61 Construction of JNK Hostel 1.570 2007-08 0.496 0.496 0.496 -do- Building. 62 Opening of Ramakrishna Sarada 5.881 2007-08 3.852 3.852 1.336 20.03.09 Mission School for Girls at Khaso (Dirang) 63 Development of Shanti Deva 2.975 2007-08 0.937 0.000 0.937 28.12.07 School Education Vidyalaya at Bomdila Monastry department is being asked in Arunachal Pradesh. to expedite submission of required documents at the earliest. 64 Sanction of Residential 2.156 2009-10 0.000 0.000 0.000 0.000 Sanctioned during October, Quarters, Procurement of Diesel 2009. Generator Set for Shanti Deva Vidyalaya at Bomdila Monastery. POWER(Eastern Elect. Zone): 65 C/O. 11 KV Transmission Line 2.340 2002-03 2.150 2.150 1.340 01.12.06 Power Deptt. is to submit from Hawai to via; Mati the Completion Certificate. Nallah MH project. 66 132 KV S/C Transmission Line 29.020 2002-03 19.646 9.180 8.846 31.03.09 QPR for June 2009 from Along to Pasighat.(East- forwarded to DoNER. Phy. West Siang District) Progress is 57%. POWER(Western Elect. Zone): 67 C/o 33 KV Express Line from 6.220 2002-03 5.596 3.959 1.637 28.03.09 Revised UC for Rs.395.85 Tawang to Lumla with 33/11 lakh submitted. KV, 2x1.6 MVA Sub-Station at Lumla. HEALTH: 68 C/O. New OPD Block at R.K. 3.880 2005-06 3.388 3.388 2.218 28.9.06 Required documents for Mission Hospital, Itanagar. release of balance fund submitted to DoNER on 05.03.09. UC for Rs.4.76 lakh submitted to DoNER on 02.03.10.Target date of completion 2009-10. Completion certificate submitted to DoNER on 18.03.2010. 12 3456789 69 Infrastructure Strengthening of 4.720 2005-06 4.120 3.484 0.636 24.03.09 Completed upto Plinth Secondary Health Care Facilities level. Around 30% work at General Hospital, completed. Naharlagun. TOURISM. 70 C/O. Ropeway from Tawang 3.310 2006-07 2.892 2.042 0.850 16.03.10 Monastery to Ani Gompa (Tawang District) 71 Tourism Infrstructure 4.000 2007-08 1.260 1.210 1.260 13.02.08 Development at Hotspring (at Dong) which includes construction of Yatri Niwas at Wallong, Hawai and .

ASSMBLY 72 C/O. Legislative Assembly 38.922 2006-07 18.626 4.100 13.626 17.03.10 Building at Itanagar ( Papum Pare District) TOTAL 870.000 510.227 289.962 272.440