T9 Characteristics of the UCTE Cross-Frontier Lines As of 31 December 2007
Total Page:16
File Type:pdf, Size:1020Kb
Load more
Recommended publications
-
Cross-Border Electricity Trading in Southeast Europe Towards an Internal European Market †
energies Article Cross-Border Electricity Trading in Southeast Europe Towards an Internal European Market † Despoina I. Makrygiorgou 1,2,*, Nikos Andriopoulos 1,2, Ioannis Georgantas 1, Christos Dikaiakos 1 and George P. Papaioannou 1 1 Research, Technology & Development Department, Independent Power Transmission Operator (IPTO) S.A., 89 Dyrrachiou & Kifisou Str. Gr, 10443 Athens, Greece; [email protected] (N.A.); [email protected] (I.G.); [email protected] (C.D.); [email protected] (G.P.P.) 2 Department of Electrical and Computer Engineering, University of Patras, 26500 Patras, Greece * Correspondence: [email protected] † This paper is an extended version of our paper published in 17th International Conference on the European Energy Market (EEM), IEEE, Stockholm, Sweden, 16–18 September 2020; pp. 1–6. Received: 8 December 2020; Accepted: 14 December 2020; Published: 17 December 2020 Abstract: The European Commission’s Target Model’s main objective is to integrate European electricity markets, leading to a single internal energy market and guaranteeing the instantaneous balance between electricity generation and demand. According to the target model for electricity trading, proposed by the European Network Transmission System Operators for Electricity (ENTSO-E), within each zone, electricity can be traded freely without taking into consideration network limitations. In contrast, for cross-border trading, the exchanges with other market areas are taken into account. Cross-border trade poses a further burden on the interconnection lines, resulting in increasing network congestion, which in turn restricts electricity trading. Thus, calculating the available capacity for trade has a significant ramification on the market. Today, the Available Transfer Capacity (ATC) mechanism dominates cross-border trading, but this methodology may be replaced by the Flow-Based (FB) approach across Europe. -
Reviewing and Improving Our Public Consultation Process Appendix 7B
Reviewing and improving our public consultation process Appendix 7b Working with you for our energy future www.eirgrid.com Appendix 7b European Grid Report: Beyond Public Opposition - Lessons Learned Across Europe Update 2013 Renewables Grid Initiative EUROPEAN G R I D R E P O R T Beyond Public Opposition Lessons Learned Across Europe Update 2013 EirGrid • Reviewing and Improving our Public Consultation Process • Appendix 7b Page 1 EUROPEAN GRID REPORT – UPDATE 2013 Imprint The Renewables-‐Grid-‐Initiative is managed and legally represented by Renewables Grid gUG. Haydnstraße 1 12203 Berlin, Germany Managing Director: Antonella Battaglini Jurisdiction: AG Charlottenburg / HR 141989 B Tax number: 27/602/56382 Authors: Theresa Schneider, Stephanie Bätjer are The Renewables-‐Grid-‐Initiative (RGI) gratefully acknowledges funding support from the European Commission. All content and opinions expressed in this publication solely those of RGI. Co-funded by the Intelligent Energy Europe Programme of the European Union 2 EirGrid • Reviewing and Improving our Public Consultation Process • Appendix 7b Page 2 EUROPEAN GRID REPORT – UPDATE 2013 TABLE OF CONTENTS Table of Contents 1. INTRODUCTION 5 1.1. THE ADDED VALUE OF THIS UPDATE 5 1.2. SCOPE AND METHODOLOGY 6 2. CHALLENGES 7 2.1. PLANNING AND APPROVAL PROCESS AND INTERACTION WITH STAKEHOLDERS 7 2.2. NATURE CONSERVATION AND ENVIRONMENT 11 3. SWITZERLAND 12 3.1. TERMINOLOGY 12 3.2. PLANNING AND APPROVAL PROCESS AND INTERACTION WITH STAKEHOLDERS 12 3.3. NATURE CONSERVATION AND ENVIRONMENT 16 3.4. CHANGE PROCESS AND INTERNAL STRUCTURES 17 3.5. PLANNING AND PERMITTING PROCEDURE: OVERVIEW 18 4. UPDATE FROM BELGIUM 19 4.1. -
Minutes SDAC Joint Steering Committee Meeting 30/01/2020,11:00 – 17:00 CET, Brussels Airport
Minutes SDAC Joint Steering Committee Meeting 30/01/2020,11:00 – 17:00 CET, Brussels Airport Present parties 50Hertz Cropex EPEX Spot Litgrid PSE Terna Admie EirGrid (TSO) ESO MAVIR REE TGE Amprion Eirgrid (SEMO PX) EXAA Nasdaq REN Transelectrica APG ElecLink Fingrid Nemo Link RTE Transnet BW AST Elering GME NGIC SEPS TTG BritNed ELES HEnEx OKTE SONI (SEMO PX) TTN BSP Elia HOPS OMIE SONI (TSO) ČEPS EMCO Nord Pool HUPX OPCOM Statnett Creos Energinet IBEX OTE Svk Attending in person Attending by phone Proxy arranged Not present Present chairs, TF leaders, PMOs, observers BMTF leader JSC Secretary MRC OPSCOM PMO MSD PMO PCR chair & PMO TSO co-chair EC MEPSO MSD NEMO co-leader NEMO co-chair Procedures TF leader Entso-e MRC OPSCOM leader MSD TSO co-leader OST Swissgrid Attending in person Attending by phone Not present Meeting agenda # Topic For 1 Welcome, practicalities 1.1 Confirm quorum Inf 1.2 Adoption of the agenda Dec 1.3 Approval of minutes of past meetings/calls (incl. part for publication) Dec 1.4 Review open action points Inf 1.5 Participation in SDAC JSCs – overview 2019 meetings Dis 2 Decisions required 2.1 Way forward Central Settlement Entity (without JAO present) Dec 2.2 NRA access to Simulation Facility & cost sharing Dec 2.3 Mandate for co-chairs to take actions after a decoupling event Dec LUNCH 3 TF status reports and decisions requested 3.1 BMTF Dec 3.2 MRC OPSCOM Dec 3.3 Procedures TF 3.4 MSD Dec 3.5 MNA Implementation Coordination Group Inf 3.6 Legal TF Inf 3.7 Communication TF Inf 3.8 Feedback from 29/01 Internal Coordination Team (ICT) strategy meeting Inf 4 Important points for SDAC from ENTSO-E/ NC/ NRAs/ ACER/ EC 4.1 NEMOs status report Inf 4.2 Feedback from 10/12 TCG and 18/12 MESC meetings Inf 4.3 Update on Algorithm Methodology 5 Any other business 5.1 Baltic Cable – status update on TSO certification Inf 5.2 CCP default Dis 5.3 Next meetings Inf 1 List of decisions # Topic Decision 1.2 Adoption of the The meeting agenda is approved. -
Flexible Resources for Flexible Transmission System Operation
Flexible resources for flexible transmission system operation IEA-PVPS Task 14: “High Penetration of PV Systems in Electricity Grids” Subtask 3: High penetration solutions for central PV generation scenarios i Report IEA-PVPS T14-09:2017 ISBN 978-3-906042-66-4 ii INTERNATIONAL ENERGY AGENCY PHOTOVOLTAIC POWER SYSTEMS PROGRAMME Flexible resources for flexible transmission system operation IEA-PVPS Task 14: “High Penetration of PV Systems in Electricity Grids” Subtask 3: High penetration solutions for central PV generation scenarios IEA-PVPS T14-09:2017 October 2017 Corresponding Author: Eng. Adriano Iaria Development of Energy Systems Dept. RSE S.p.A Ricerca sul Sistema Energetico. Via Rubattino, 54, 20134 Milano (MI) - Italy Ph. +39-02-3992-5241 Fax +39-02-3992-5597 e-mail: [email protected] iii Report contributors BELGIUM Koen Verpoorten1,2, Kristof De Vos1,2 1Department of Electrical Engineering, University of Leuven, Leuven, Belgium 2EnergyVille, Genk, Belgium GERMANY Markus Kraiczy1, Rafael Fritz1, Bernhard Ernst1, Dominik Jost1, 1 Fraunhofer Institute for Wind Energy and Energy System Technology, Kassel Germany GREECE Stathis Tselepis, CRES, Centre for Renewable energy Sources and Saving, Greece. ITALY Adriano Iaria2, Claudio Brasca2, Diego Cirio2, Antonio Gatti2, Marco Rapizza2 2Ricerca sul Sistema Energetico – RSE S.p.A., Energy Systems Development Dept., Milano, Italy JAPAN Kazuhiko Ogimoto3, Ken Obayashi4, Koichi Asano4 3University of Tokyo, Institute of Industrial Science, Tokyo, Japan 4New Energy and Industrial Technology Development Organization, (NEDO), Smart Community Department, Kawasaki City, Japan SWITZERLAND Christof Bucher, Basler & Hofmann AG, Zürich, Switzerland UNITED STATES OF AMERICA Barry Mather5, Vahan Gevorgian5 5National Renewable Energy Laboratory (NREL), Golden, Colorado, USA Foto credit cover page RSE S.p.A. -
Minutes SDAC Joint Steering Committee Meeting 04/06/2020,13:30 – 17:00 CET, Conference Call
Minutes SDAC Joint Steering Committee Meeting 04/06/2020,13:30 – 17:00 CET, conference call Present parties 50Hertz Cropex EPEX Spot Litgrid PSE Terna Admie EirGrid (TSO) ESO MAVIR REE TGE Amprion Eirgrid (SEMO PX) EXAA Nasdaq REN Transelectrica APG ElecLink Fingrid Nemo Link RTE Transnet BW AST Elering GME NGIC SEPS TTG BritNed ELES HEnEx OKTE SONI (SEMO PX) TTN BSP Elia HOPS OMIE SONI (TSO) ČEPS EMCO Nord Pool HUPX OPCOM Statnett Creos Energinet IBEX OTE Svk Attending by phone Not present Present chairs, TF leaders, PMOs, observers BMTF leader/PMO Entso-e MRC OPSCOM leader MSD TSO co-leader OST Swissgrid EC JSC Secretary MRC OPSCOM PMO MSD PMO PCR chair & PMO TSO co-chair EMS MEPSO MSD NEMO co-leader NEMO co-chair Procedures TF leader Attending by phone Not present Meeting agenda # Topic For 1 Welcome, practicalities 1.1 Confirm quorum Inf 1.2 Adoption of the agenda Dec 1.3 Approval of minutes of past meetings/calls (incl. part for publication) Dec 1.4 Review open action points Inf 2 Strategy/governance – decisions required 2.1 Way forward Central Settlement Entity Inf 3 Important points to highlight and decisions requested by TFs 3.1 Status extension projects and communication towards EC Dec 3.2 MRC OPSCOM Dec 3.3 MSD Dec 3.4 Procedures TF Inf 3.5 BMTF Dec 3.6 JSC members questions to reports in back-up section Dis 4 Important points for SDAC from ENTSO-E/ NC/ NRAs/ ACER/ EC 4.1 Preparations for next TCG and MESC Inf 4.2 EC consultation on first light amendment of some relevant regulations incl. -
GARPUR Template Deliverable
Project no.: 608540 Project acronym: GARPUR Project full title: Generally Accepted Reliability Principle with Uncertainty modelling and through probabilistic Risk assessment Collaborative project FP7-ENERGY-2013-1 Start date of project: 2013-09-01 Duration: 4 years D10.3d Workshops proceedings and satisfaction questionnaires (all reporting periods) Due delivery date: 2016-08-31 Actual delivery date: 2017-10-31 Organisation name of lead beneficiary for this deliverable: TECHNOFI Project co-funded by the European Commission within the Seventh Framework Programme (2007-2013) Dissemination Level PU Public x PP Restricted to other programme participants (including the Commission Services) RE Restricted to a group specified by the consortium (including the Commission Services) CO Confidential, only for members of the consortium (including the Commission Services) This document reflects only the author's views and the Union is not liable for any use that may be made of the information contained herein. Page 3 of 65 Deliverable number: D10.3d Deliverable short title: Workshops proceedings and satisfaction questionnaires (all reporting periods) Deliverable title: Workshops proceedings and satisfaction questionnaire exploitation for all the yearly interactive workshops occurring in WP10 (T10.3, T10.4 and T10.10) Work package: WP10 Dissemination and exploitation Lead participant: TECHNOFI Revision Control Date Revision Author(s) Comments 2014-08-29 a Sophie Dourlens- Initial version: proceedings of workshops Quaranta held during the first year of -
UCTE Transmission Development Plan
UCTE Transmission Development Plan Edition 2008 union for the co-ordination of transmission of electricity Table of contents Executive Summary 3 1 Introduction 5 2 Evolution of the UCTE Generation-Load Balance 12 3 Development of Interconnections 19 4 Transmission Network Development 37 Appendix 1 39 Detailed Information on Interconnection Projects Appendix 2 66 UCTE Members Internal Grid Development EXecutiVE summaRY Executive Summary In order to meet the objectives of the European energy policy, the transmission grid must be devel- oped while maximizing security and minimizing the total cost ( from generation to retail ). Grid devel- opment is influenced by two interrelated parameters: consumption and generation. If consumption is expected to follow a rather low growth rate as a result of improved energy efficiency, generation is affected by major changes resulting from the development of renewable energy sources and the renewal of the oldest thermal plants. The UCTE Transmission System Operators ( TSOs ) therefore have two objectives: maximising the security of supply and integrating the market in order to allow an efficient use of the generation and by this way minimise total costs. Over the next 10 years, net installed generation capacity in UCTE attributable to both new projects already submitted to the TSOs and expected decommissioning of existing plants or attributable to energy policy objectives amounts be approximately 220 GW ( including 80 GW of wind power ). At the same time, consumption over the same period is forecasted to increase by approximately 90 GW. Since rising generation capacity is strongly linked to market conditions, there is almost certain that all generation projects submitted to the TSOs will not be confirmed. -
Establishing the Institutional Set- up for Organized Day-Ahead Market in Bosnia and Herzegovina
Finland Energy Community Norway Members Sweden European Union Estonia Observers Contracting parties Latvia Denmark Candidate Lithuania Ireland Great Britain Netherlands Poland Germany Belgium Luxembourg Czech Republic Slovakia Ukraine Austria Moldova Hungary France Slovenia Romania Croatia Bosnia & Herzegovina Serbia Italy Montenegro Kosovo* Bulgaria Georgia FYR of Portugal Macedonia Albania Spain Armenia Greece Turkey Malta Cyprus Establishing the institutional set- up for organized day-ahead market in Bosnia and Herzegovina SEEC Ltd. and MRC Consultants and Transaction Advisers March 2018 This report is a deliverable under the Technical Assistance to Connectivity in the Western Balkans, Component 2: Regional Energy Market. www.energy-community.com Establishing the Institutional Set-up for Organized Day-ahead market in Bosnia and Herzegovina TECHNICAL REPORT Prepared for March 2018 MRC Consultants and Transaction Advisers General Moscardo 32, 1-A, 28020 Madrid (Spain) www.mrc-consultants.com SEEC Ltd. and MRC Consultants and Transaction Advisers and their directors and staff neither owe nor accept any duty of care to any third party whether in contract or in tort (including without limitation negligence or statutory duty or howsoever otherwise arising) and shall not be liable in respect of any loss, damage or expense of whatsoever nature which is caused by any third party’s reliance upon information derived from the report. If any third party wishes to rely upon the report or information derived there from, they do so entirely at their own risk. The information used in preparing this Report has been obtained from a variety of sources as indicated within the Report. Our work has not included an audit in accordance with generally accepted auditing standards. -
Repower – Kosovo Demand Side Response in Kosovo Power System
REPOWER – KOSOVO DEMAND SIDE RESPONSE IN KOSOVO POWER SYSTEM DATE: July 2019 This publication was produced for review by the United States Agency for International Development. It was prepared by AECOM. ___________________________________________________________________________________________ REPOWER – KOSOVO i/77 REPOWER-KOSOVO DEMAND SIDE RESPONSE IN KOSOVO POWER SYSTEM Contract Number: AID-OAA-I-13-00012 Task Order: AID-167-TO-14-00007 Submitted to: USAID/Kosovo Prepared by: AECOM International Development DISCLAIMER: The authors’ views expressed in this document do not necessarily reflect the views of the United States Agency for International Development or the United States Government. ___________________________________________________________________________________________ REPOWER – KOSOVO 2/77 Contents 1. GENERAL CONCEPT OF DEMAND SIDE RESPONSE ................................................. 4 2. OTHER COUNTRIES EXPERIENCE ............................................................................... 10 2.1. Austria ............................................................................................................................................................. 13 2.2. Belgium ............................................................................................................................................................ 16 2.3. Bosnia and herzegovina ............................................................................................................................... 19 2.4. Croatia ........................................................................................................................................................... -
View Annual Report
ANNUAL REPORT 2014 Our energy in motion ELIA - ANNUAL REPORT 2014 ANNUAL REPORT ELIA - Summary 01 Executive report 01 — The system operator, a key player in the electrical system 02 — Challenges for a sustainable energy transition 04 — Letter from the Chairman1 06 — Letter from the CEO 08 — Key events in 20141 12 The Elia Group 12 — Playing a key role in a complex environment 14 — Two system operators, one European Group 16 — Dialogue with stakeholders 20 — Elia Group’s new strategy for creating added value 24 Challenges and prospects 24 — Prospects and challenges for 20151 26 — Guaranteeing reliable electricity transmission, both now and in the future 28 — Operating grid infrastructure 40 — Managing the electricity systems 46 — Facilitating the market 52 — An inside look at Elia 58 Corporate governance statement1 59 — Composition of the management bodies as at 31 December 2014 68 — Remuneration report 72 — Features of the internal control systems 76 — Risks and uncertainties facing the company 80 The Elia share in 2014 82 Consolidated financial statements 82 — Consolidated statement of financial position1 83 — Consolidated statement of changes in equity 84 — Consolidated statement of cash flows1 85 — Consolidated statement of comprehensive income 86 — Consolidated income statement1 87 Reporting parameters Discover our online report @ http://annualreport.elia.be/2014 1. These chapters form the annual report cf. article 119 of the Belgian Companies Code. The Elia Group in 2014 In fi gures DE/BE contribution to IFRS results Investments -
Winter Review and Summer Outlook 2009
European Network of Transmission System Operators for Electricity An Overview of System Adequacy: Winter Review and Summer Outlook Report 2009 ENTSO-E • Boulevard Saint-Michel, 15 • 1040 Brussels • Belgium • Tel +32 2 737 15 80 • Fax +32 2 741 69 49 • [email protected] • www.entsoe.eu European Network of Transmission System Operators for Electricity Contents 1 Executive Summary .......................................................................................................3 1.1 Winter Review 2008/09....................................................................................................3 1.2 Summer Outlook 2009 .....................................................................................................8 2 Introduction and Methodology ...................................................................................11 2.1 Scope & Objectives of the Report ..................................................................................11 2.1.1 Winter Review Report ..................................................................................................11 2.1.2 Summer Outlook Report..............................................................................................11 2.2 Sources of Information & Methodology ..........................................................................11 2.2.1 Winter Review Report ..................................................................................................11 2.2.2 Summer Outlook Report..............................................................................................12 -
79Th ENTSO-E MC Meeting
79th ENTSO-E MC meeting Date: Tuesday, 30 June 2020 Minutes This document includes the MC decisions individually as part of implementation projects in accordance with Network codes (NCs)/Guidelines (GLs). Participants Country Involved TSOs Albania OST - Operatori i Sistemit të Transmetimit (non-EU) Austria APG - Austrian Power Grid AG VÜEN-Vorarlberger Übertragungsnetz GmbH Belgium Elia - Elia System Operator S.A. Bosnia Herzegovina NOS BiH - Nezavisni operator sustava u Bosni I Hercegovini (non-EU) Bulgaria ESO – Electroenergien Sistemen Operator EAD Croatia HOPS - Croatian Transmission System Operator Ltd Cyprus TSO Cyprus - Cyprus Transmission System Operator Czech Republic ČEPS - ČEPS, a.s. Denmark Energinet Estonia Elering - Elering AS Finland Fingrid - Fingrid OyJ Kraftnat Aland Ab France RTE - Réseau de Transport d'Electricité, SA Amprion - Amprion GmbH TransnetBW -TransnetBW GmbH Germany TenneT GER - TenneT TSO GmbH 50Hertz - 50Hertz Transmission GmbH Greece IPTO - Independent Power Transmission Operator S.A. Hungary MAVIR ZRt. - MAVIR Magyar Villamosenergia-ipari Átviteli Rendszerirányító Zártkörűen Működő Részvénytársaság ZRt. ENTSO-E | Rue de Spa, 8 | 1000 Brussels | [email protected] | www.entsoe.eu | @entso_e 1 Iceland Landsnet - Landsnet hf (non-EU) Ireland EirGrid - EirGrid plc Italy Terna - Terna SpA Latvia Augstsprieguma tïkls - AS Augstsprieguma tïkls Lithuania LITGRID AB Luxembourg CREOS Luxembourg - CREOS Luxembourg S.A. Montenegro CGES - Crnogorski elektroprenosni sistem AD (non-EU) Netherlands TenneT TSO - TenneT TSO B.V. BritNed (as a certified TSO in the Netherlands) Norway Statnett - Statnett SF (non-EU) Poland PSE - PSE S.A. Portugal REN - Rede Eléctrica Nacional, S.A. Romania Transelectrica S.A. Serbia EMS AD Beograd (non-EU) Slovak Republic SEPS - Slovenská elektrizačná prenosovú sústava, a.s.