R U Y R C A N L E G EL A CT N RIFICATIO

Rural Electrification Agency Ministry of Energy and Mineral Development

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link H.E President Yoweri Kaguta Museveni commissions the Kayunga-Busana Powerline Rural Electrification Agency Ministry of Energy and Mineral Development

Vision Universal access to electricity by 2035 Mission To facilitate provision of electricity for socio-economic rural transformation in an equitable and sustainable manner

Objectives

1. Promoting equitable rural electrification access and having special regard to those areas of the community that are currently marginalized

2. Establishing and maintaining a comprehensive database on 's Rural Electrification sub-sector to facilitate informed decision making

3. Enhancing the available financial resource base for Rural Electrification through strategic fundraising

4. Promote institutional sustainability of the Rural Electrification Fund

Core Values The REA organizational philosophy is anchored in the following three core values; · Responsiveness to stakeholders needs, reliability and accessibility at all times · Effectiveness and efficiency anchored in professionalism, teamwork, time management, innovation and practicing the concept of a learning organization · Accountability and transparency in the conduct of public affairs

Ps: the acronym REA that rhymes with the Agency's own name enables staff internalize the organisational philosophy

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link i Rural Electrification Agency Ministry of Energy and Mineral Development

MAP HIGHLIGHTING RURAL ELECTRIFICATION STATUS AS OF END OF FINANCIAL YEAR 2011/12

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 ii The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development

CONTENTS

ABBREVIATIONS AND ACRONYMNS...... 5

FOREWORD...... 6

EXECUTIVE SUMMARY...... 7

1.0 INTRODUCTION...... 9

2.0 OPERATIONAL PERFORMANCE OF THE RURAL ELECTRIFICATION PROGRAMME FOR THE FINANCIAL

YEAR JULY 2011 –JUNE 2012...... 14

3.0 SOCIAL INTERMEDIATION, ENVIRONMENTAL AND WAYLEAVES ISSUES...... 21

4.0 CAPACITY BUILDING...... 26

5.0 FINANCIAL PERFORMANCE FOR THE YEAR 2011/2012...... 28

6.0 PROJECT IMPLEMENTTAION PLANS FOR 2012/13...... 29

7.0 IMPLEMENTTAION CONSTRAINSTS AND PRPOSED SOLUTIONS...... 33

8.0 CONCLUSION...... 36

9.0 AUDITED REPORTS...... 37

ANNEX I PROJECTS COMPLETED AND COMMISSIONED DURING 2010/2011 FY...... 38

ANNEX II PROJECTS UNDER IMPLEMENTATION...... 42

ANNEX III PROJECTS UNDER PROCUREMENT...... 51

ANNEX IV PLANNED PROJECTS...... 52

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link iii Rural Electrification Agency Ministry of Energy and Mineral Development ABBREVIATIONS AND ACRONYMNS

BADEA The Arab Bank for Economic Development in Africa

BECS Bundibugyo Electricity Cooperatives Society

EEW Energy Efficiency Week

ERA Electricity Regulatory Authority

ERT Energy for Rural Transformation

HFO Heavy Fuel Oil

IREMP Indicative Rural Electrification Master Plan

JICA Japan International Cooperation Agency

KIL Kilembe Investments Ltd

KW Kilo Watt

MEMD Ministry of Energy and Mineral Development

MW Mega Watt

NORAD Norwegian Agency for Development Cooperation

PACMECS Pader - Abim Cooperatives Multipurpose Electricity Cooperative Society

PPA Power Purchase Agreement

PPP Private Public Partnerships

PVTMA Photovoltaic Targeted Market Approach

REA Rural Electrification Agency

REB Rural Electrification Board

REF Rural Electrification Fund

RESP Rural Electrification Strategy and Plan

SFD The Saudi Fund for Development

SIDA Swedish International Development Agency

UEDCL Uganda Electricity Distribution Company Limited

UETCL Uganda Electricity Transmission Company Limited

WENRECO West Nile Rural Electrification Company

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 iv The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development FOREWORD

I am pleased to introduce the 2011/12 Annual Rural Electrification Report in accordance with the requirements of Section 64(2) of the Electricity Act (1999). The Government, through its rural electrification programme, has a goal of increasing the Rural Electrification coverage from 1% in 2001 to 10% by 2012 as spelt in its Rural Electrification Strategy and Plan (RESP) (2001). This report covers activities undertaken by the Government of Uganda, its development partners and the private sector Hon. Eng. Irene Muloni (MP) in implementing the rural electrification programme. Minister for Energy and The report also highlights the social intermediation, Mineral Development environmental issues, way leaves issues, capacity building activities and the financial performance of the Agency. Through Private Public Partnerships (PPP), the Government has endeavored to promote renewable energy technologies including the development of Mini hydropower plants, cogeneration facilities and solar energy utilization. So far, one of the main constraints to the programme is the current inadequate supply onto the main electricity grid. It is hoped that the construction of the 250MW Bujagali, 700MW at Karuma, 18MW in Mpanga, Kamwenge, 6MW in Isasha and 3.5 in Nyagak will go along way towards Hon. Eng. Simon D’Ujanga reducing the load shedding experienced in the country Minister of State for Energy at the moment and boosting the new rural electrification networks being added on the grid. The programme continues to progress with support from development partners including; the World Bank, the Royal Nowergian Government and the Japanese Government. New players on board include the Arab Bank for Economic Development in Africa (BADEA) and the Saudi Fund for Development (SFD) and I am sincerely grateful to them. I would like to thank His Excellency the President and Hon. Peter Lokeris my Colleagues in Cabinet, Parliament and Local District Minister of State for Mineral Development Authorities for the continued guidance and support they have provided to scale up electricity access. I particularly want to thank my Colleagues; the Ministers of State in the Ministry, the Permanent Secretary / Chairman of the Rural Electrification Board and members of the Rural Electrification Board (REB), the Executive Director and members of staff of the Rural Electrification Agency. Their hard work and dedication is enabling Government draw closer to achieving its goal of providing electricity in an equitable manner for socio- economic rural transformation. For God and My Country

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link v Rural Electrification Agency Ministry of Energy and Mineral Development

EXECUTIVE SUMMARY The Annual Rural Electrification Report 2011/12 provides the status of the progress and milestones of the rural electrification plan as of June 2012. The report underscores the operational and financial performance of the Rural Electrification Programme in line with its Short and Medium term Plans that were set to meet the set goals. The report also highlights the institutional capacity building programme, the implementation constraints, mitigation measures and lessons learnt in the process of implementing the targets set in the Rural Electrification Strategy and Plan (RESP) (2001).

A new RESP was finalized this financial year with consultancy backing from the national Rural Electric Cooperation Association (NRECA) International Ltd and support from the World bank under ERT programme. The main goal of the RESP is to raise the rural electrification rate to 22% from its current rate. The new RESP (2012-2021) will be used as a trajectory of achieving the Universal Electrification Access by 2040, taking into account lessons learnt during the 2001-2012 implemetation period. The focus in this RESP will be Public Financing as opposed to the previous one that focused on Public Private Ptnerships. Additionally, the new RESP introduces thirteen (13) commercially viable servive territories.

In line with the country's electrification vision and goals as spelt out in its strategic documents including the National Development Plan (NDP) (2010) and the Rural Electrification Strategy and Plan (RESP) (2001), the programme has made tremendous progress with electricity coverage and access having a cumulative increase from 1%, when the programme started in 2003 to 7%, while the overall national electricity access is at 12%.

This period witnessed increased consumer connections especially in the districts of Bundibugyo, ntoroko, Pader, Agago and Abim, mostly as a result of the operations electricity cooperatives including Bundibugyo Electricity Cooperative Society (BECS) and Pader- Abim Community Multi-purpose Cooperative Society (PACMECS). The PVTMA solar programme has also enabled the Agency reach out to a wider population, especially those far off from the main grid. To date over 3.000 consumers have ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 vi The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development been connected to a solar energy system. This programme is implemeneted in partnership with four (4) financial institutions, 100 SACCOs and 24 prequalified solar companies.

Several grid extension projects were progressed focusing on connection of district headquarters, supporting major agro-processing industries, other economic activities like trading centres and social services including health centres, educational institutions and water supply. Small schemes in the form of spurs on the Umeme network, and intensification within the Umeme footprint were constructed.

Government is looking at other avenues to finance the programme. During the FY 2011/12, several Development Partners supported the programme including; the Government of the Royal Norwegian, the African Development Bank, the Organisation of Islamic Countries (e.g. Kuwait Fund, the Saudi Fund for Development, and the Arab Bank for Economic Development of Africa). Further support came from the World Bank under ERT II, the Japanese International Cooperation Agency (JICA II) and support from the local financing through the Consolidated Fund and the Transmission Levy.

The Government continues to encourage private sector participation in the energy sector through the development and promotion of renewable energy projects including; Kinyara (bagasse) cogeneration project, Bugoye mini-hydro (13 MW), Mpanga mini-hydro (18 MW), Buseruka mini-hydro (9MW), Ishasha mini-hydro (6.5 MW), Kikagati mini-hydro (10 MW) and the solar Photo-Voltaic.

The key challenges affecting the rural electrification programme include low level private sector investment, way leaves acquisition and compensation for the lines, inadequate power supply on the main grid majorly due to limited installed capacity and high consumer tariffs which affects connection rates.

F. A. Kabagambe-Kaliisa Permanent Secretary, Ministry of Energy and Mineral Development and,

Chairman, Rural Electrification Board

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link vii Rural Electrification Agency Ministry of Energy and Mineral Development

1.0 INTRODUCTION

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 viii The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development 1.0 INTRODUCTION

In the reporting period of Financial Year 2011/12, the programme continued to focus on the following broad objectives:

i) Expanding the level of coverage of the electricity network countrywide while putting into consideration the issue of equitable regional distribution access specifically, targeting of district Headquarters and economically productive activities;

ii) Maximizing the economic and social benefits of the Rural Electrification Fund in extending electricity services while taking care of the attendant environmental issues;

iii) Promoting the use of various technical solutions in the design and implementation of projects, including grid extension and off-grids as well as introducing low cost technologies for infrastructure and service provision; and

iv) Promoting private sector generation of electricity from small renewable energy sources and selling to the grid.

Major project activities were in the following areas:

i) On-grid projects

· Main grid expansion – design, procurements and construction of networks;

· Small schemes, mainly within Umeme's footprint (grid intensification);

· Support to renewable energy power generation projects, including planning for constructing;

· the inter-connectors to the main grid;

· Continued support to the concessions and monitoring their performance;

ii) Off-grid projects

· Continued support to the resumption of implementation of the Nyagak hydro power project;

· Continued provision of support to the mini grid of Kalangala and Ngoma monitoring its performance;

· Implementation of the Photovoltaic Targeted Market Approach (PVTMA) which is based on the provision of credit and subsidies to targeted communities to enable them afford solar PV electrification; and

· Planning for additional energy packages (PV systems) for health centres,

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 1 Rural Electrification Agency Ministry of Energy and Mineral Development educational institutions, ICT and water supply under ERT II.

1.1 Institutional set up

The major institution responsible for the Rural Electrification Programme is the Rural Electrification Agency (REA), which is the Secretariat of the Rural Electrification Board (REB). REA has the overall responsibility of planning and implementing the mainstream Rural Electrification Programme which includes main grid extension, independent (mini) grids, isolated commercial solar PV systems (e.g solar home systems), and promotion of private sector investments in renewable energy generation (below 20 MW installed capacity).

The Rural Electrification Board (REB)

The Rural Electrification Board (REB) is charged with the responsibility to manage the Rural Electrification Fund (REF) on behalf of the Minister of Energy and Mineral Development (MEMD) as prescribed in Statutory Instrument No.75 of 2001 which established the REF.

According to Regulation 5 (2) of the Statutory Instrument, the Board should consist of the following members:-

· The Permanent Secretary of the Ministry responsible for Energy, who is the Chairperson;

· The Permanent Secretary of the Ministry responsible for Finance;

· The Permanent Secretary of the Ministry responsible for Local Government;

· A representative of the private sector involved in Rural Electrification, nominated for appointment by the Private Sector Foundation;

· A representative of the financial sector nominated for appointment by the Uganda Bankers Association; and

· A representative of the Non-Governmental Organizations engaged in rural development projects, apart from the energy sector nominated for appointment by the NGO community).

The Rural Electrification Agency (REA)

The major role of REA is to implement Government's Rural Electrification Programme in line with the Rural Electrification Strategy and Plan, with specific focus on the following functions prescribed in Section 11 of the Statutory Instrument, but modified in accordance with the evolving reality of financing and implementing a rural electrification programme:

· Planning and implementing projects as approved by the Board;

· Procurement of private sector operators to manage public funded rural electricity; ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 2 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development · Building and maintaining a national rural electrification data base;

· Preparing annual status reports on the progress of the rural electrification programme;

· Recommending to the Board the most efficient use of the REF;

· Generating information relating to investment opportunities in rural electrification; and

· Processing application for financial support from the REF.

REA is headed by an Executive Director, who is supported by a team of 5 managers and 50 other

Members of staff, to oversee the Rural Electrification Programme in Uganda. Photos of board and management to be inserted here

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 3 Rural Electrification Agency Ministry of Energy and Mineral Development 1.2 Partnerships and Networks

During the period under review, REA continued to work with a number of institutions in the power sector as well as other sectors. Additionally, several other institutions of Government carried out other activities, especially with regard to the ERT II project.

Government, Energy sector partners and Public-Private Partnerships (PPP)

The Ministry of Energy and Mineral Development (MEMD) provides policy guidance and oversight for the Rural Electrification Programme as well as generating basic data on new resources (e.g. geothermal energy).

Within the energy sector REA worked with Electricity Regulatory Authority (ERA) especially in the area of concession monitoring, Uganda Electricity Distribution Company Limited (UEDCL) in small scheme implementation, Uganda Electricity Transmission Company Limited (UETCL) on rationalising network expansion and the Uganda Energy Credit capitalization Company (UECCC).

REA also continued to work with the Solicitor Hon. Byabagambi, Hon D’Ujuanga and General's Office, Chief Government Valuer, Hon Nassasira erecting a pole during the National Roads Authority and National Ibanda – Rushere-Kazo powerline ground Forest Authority on issues of way leaves and breaking ceremony The National Environmental Management Authirty (NEMA), on environement issues. The ministries responsible for Health, Education and Water continued the execution of the solar PV component of ERT II in health centres, educational institutions and for supplying water in rural areas respectively

The Uganda Communications Commission (UCC) continued with the PV communications component of ERT II.

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 4 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development

Private Sector Foundation Uganda (PSFU) also continued with its role under the ERT II project of helping the private sector to develop its capacity for investing in and /or operating rural electrification and renewable energy projects, developing the required business plans for investment and carrying out market development for rural electrification services.

Under the PVTMA programme, a number of financial institutions, notably Post Bank Uganda and FINCA Uganda, Centenary Bank Limited and Opportunity Bank Uganda; continued to provide credit facilities to PV consumers and also act as an avenue for these consumers to access subsidies on PV equipment. A number of approved PV vendors also worked with SACCOs to extend PV systems to rural consumers, carrying out installations and administering the subsidy facility under agreement with REA.

In terms of access to power, REA worked with concessionaires including UMEME in grid intensification, Ferdsult Limited in the West and Mid-Western Concessions, Bundibugyo Electricity Cooperative society (BECS) and Pader-Abim Community Multipurpose Electricty Cooperative Society (PACMECS).

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 5 Rural Electrification Agency Ministry of Energy and Mineral Development Development Partners

Additionally, the Agency worked with several Development Partners to support the programme including;

· the Government of the Royal Kingdom of Norway · the African Development Bank, · the Organisation of Islamic Countries (e.g. Kuwait Fund, the Saudi Fund for Development, and the Arab Bank for Economic Development of Africa)

· the World Bank under ERT II, · the Japanese International Cooperation Agency (JICA II)

Consultants, Contractors and sub-contractors

The contractors and consultants REA worked with in the implementation of its programme in the FY 2011/12 incluyde;

· A2Z · C&G Andijees · Consolidated Power project · CPCC · Energia · Ferdsult Engineering · LTL Consortium · M&T construction Ltd · Megger Technician · Meridian · Multi Consult · Omega · Plan Built · Power Networks · RESCO · Savimaxx · SurvesisSpencon · Tetra Technician · Utility Engineering

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 6 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development

2.0 OPERATIONAL PERFORMANCE OF THE RURAL ELECTRIFICATION PROGRAMME FOR THE FINANCIAL YEAR JULY 2011 –JUNE 2012

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 7 Rural Electrification Agency Ministry of Energy and Mineral Development 2.0 OPERATIONAL PERFORMANCE OF THE RURAL ELECTRIFICATION PROGRAMME FOR THE FINANCIAL YEAR JULY 2011 –JUNE 2012

Section 62 of the Electricity Act 1999 prescribes project types to be supported by the REF as grid extension, independent grids, renewable energy generation projects and photovoltaic systems (for instance solar electrification). The performance of the agency during the period of review is best categorized according to the nature or type of the project and status as further detailed below. 2.1 Main Grid Extension 2.1.1 Electricity supply to District Headquarters Completed projects Electrification of Sironko, Nakapiripirit and Amudat

Construction of the Sironko-Nakapiripirit-Amudat power line to supply Nakapiripirit and Amudat District Headquarters was commissioned in January 2012. The project was financed by the Government of Uganda. Major load centers along the line benefited.

Supply to Kaberamaido, Amolatar and Dokolo District Headquarters

Construction of the Lwala-Kaberamaido-Kobululu-Amolatar and Lwala-Dokolo power line to supply Kaberamaido, Amolatar and Dokolo District Headquarters was financed by Government of Uganda and the project was commissioned in April 2012. Major load centers along the line benefited.

Supply to Alebtong District Headquarter

Construction of the Lira – Apala-Aloi power line to supply Alebtong District Headquarter was financed by Government of Uganda and the project was commissioned in June 2012. Major load centers along the line benefited.

Projects under construction

Supply to Kyankwanzi District Headquarter

Supply of power to Kyankwanzi District Headquarter was financed by the Government of Uganda and the project was in progress by the end of financial year. Commissioning of Bukwiri-Kyankwanzi was envisaged within the first quarter of the 2012/2013 Financial Year.

Supply to Moroto and Napak District Headquarters

Construction of the Katakwi-Moroto with t-offs to Matany and Lorengedwat power line from Katakwi to supply Moroto and Napak District headquarters was completed awaiting completion of Soroti – Katakwi energy feeder. The project is financed by Government of Uganda and commissioning was envisaged within the second quarter of the 2012/2013 Financial Year.

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 8 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development

Hon. Lokeris, Eng Werikhe and the contractors inspecting electricity construction works in the Karamoja region

Electricity Supply to Katakwi and Amuria District Headquaters

The construction of the power line from Soroti to Katakwi District Headquarter with a tee off to Amuria District Headquarter is financed by IDA/World Bank. Construction was underway and completion was envisaged by end of December 2012.

Electricity Supply to Kiruhura District Headquarters

The construction of the Ibanda- Kazo and Kyabirukwa-Nyarukika power line to supply Kiruhura District Headquarters is financed by IDA/World Bank. By close of the reporting period construction was underway and completion is envisaged by end of December 2012.

Eletricity Supply to Kyegegwa District Headquarters

The construction of the power line from Mubende to supply Kyegegwa District headquarter was underway and completion was envisaged by February 2013. This project is financed by the Government of Norway.

Electricity supply to Adjumani and Moyo District headquarters

The contract for the proposed power line from Gulu to Adjumani and Moyo District headquarters with a tee-off to Amuru District Headquarters had been signed and the contractor was mobilising by the end of the financial year. This project is financed by the Government of Norway.

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 9 Rural Electrification Agency Ministry of Energy and Mineral Development Projects under procurement

Electricity Supply to Zombo District Headquarter.

The proposed scope of works shall involve the construction of a 33kv line from Nyagak Power plant through Vurra to Zombo District Headquarters. The project will be financed by the Government of Germany through Kreditanstalt fur Wiederaufbau (KfW) and the Government of Uganda. Procurement of the contractor for construction works was underway by close of the Financial Year and the contract would be in place by end of the first quarter of the 2012/2013 Financial Year.

Electricity Supply to Koboko, Maracha and Yumbe District Headquarters

The proposed works include the extension of a 33kv line from Arua to Yumbe through Maracha and Koboko District Headquarters. The project will be financed by the Government of Germany through Kreditanstalt fur Wiederaufbau (KfW) and the Government of Uganda. Procurement of the contractor for construction works was underway by close of the Financial Year and the contract would be in place by end of the first quarter of the 2012/2013 Financial Year.

Projects under design

Electricity supply to Bukwa district headquarter

SFD and BADEA are jointly financing rural electrification projects in eight areas in Uganda. The procurement for design and supervision consultants was underway by the end of the Financial Year. The district headquarters of Bukwa will be electrified.

2.1.1 Electricity Supply to Economic and Social Growth centres a) Completed

Utilizing funds from Government of Uganda and Development partners, construction of various projects was completed in the reporting period and the details are presented in annex I. These were implemented by REA, Umeme and UEDCL. b) Under Implementation

Various projects that were under construction by close of the reporting period are detailed out in annex II indicating the various financiers. c) Under Procurement

Various projects that were under construction by close of the reporting period are detailed out in annex III indicating the various financiers. d) Planned Projects

Various projects have been planned to commence construction in the FY 2011/12. The list is contained in annex IV

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 10 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development 2.2 Independent Grids

2.2.1 West Nile Rural Electrification Project

The Government resumed construction of Nyagak project as a Public Private Partnership project through a Channeling Agreement for the funds signed between the Ministry of Energy and Mineral Development and WENRECo in July 2010. During the reporting period, works progressed and completion was envisaged within the first quarter 2012/2013. Details on the progress of works are indicated below:

Dam, Spillway & Intake

(i) Construction of all the Blocks (1,2,3,4,5,6,7,8,9,10,11) completed

(i) Construction of gravel sluice channel was complete

(ii) The thrush gate was already installed

Tunnel & Surge Shaft

Excavation of the open cut tunnel was complete and works on the surge shaft were complete

Headrace conduit

Construction of most the sections were complete except at the access points.

Power house and penstock

(i) One turbine was installed; the foundation for the 2nd turbine was being re-inforced to handle the turbine vibrations.

Electromechanical works

Installation of the generator transformers and control panels was complete and wiring was ongoing

2.2.2 Mpanga Hydropower Project

The construction of the 18MW Mpanga Hydropower Plant was completed by April 2011. The Government constructed the 33KV sub- transmission line and a temporary substation. The construction of the 2x20MVA, 33/132KV substation (permanent solution) at Kahunge and works were in progress by close of the reporting period. Commissioning of the substation was envisaged by end of December 2012.

As a way of benefiting the local community, REA procured a contractor for the construction of distribution networks from Mpanga - Kahunge – Nkingo. The works were completed in September 2011. Details on this project are in annex I.

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 11 Rural Electrification Agency Ministry of Energy and Mineral Development 2.2.3 Buseruka Hydropower Project

The construction of the 9MW Buseruka hydropower plant is ongoing and scheduled for completion by end of December 2012. REA procured a contractor for the construction of the 40km, 33KV power evacuation line from Buseruka to Hoima substation. By the end of the reporting period, the works for the High Voltage power line were in final stages and completion was envisaged by second quarter of 2012/2013 Financial Year. Works for the Low Voltage network were in progress.

2.4 Electricity Distribution Concessions

REA supervises concessions which are outside the UMEME network. They include electricity cooperatives and private utility companies. In the reporting period a number of connections were realized under these management models as highlighted in the tables below.

Cooperatives

Item/Name BECS Ltd PACMECS Ltd. KRECS Ltd. NGOMA Ltd. Commencement Registered, Registered, Of business October, 2009 February, 2010 April, 2012 January,2011

Bundibugyo, To serve Kyege- Ntoroko and Pader, Abim, Agago gwa and parts of Ngoma town Area served parts of Kabarole and Lamwo Mubende and council districts Kyenjojo districts

1,663 (Male-1223 Membership 1,580 200 30 Female-415 others 25)

1,573 (single 1,140 phase-1,548&- Connections (single phase-1,140 & - - three phase phase three phase 33) 25)

2.4.2 Other concessions:

Item/Name FESL-Kibaale FESL-Kanungu FESL-Rakai UEDCL-Kalangala Commencement Of business January, 2007 May, 2007 January,2009 Nov., 2010 Kibaale, Kaku- Masaka, Rakai, Isin- Kanungu and Kalangala Area served miro and Kyenjojo giro and Ntungamo Rukungiri districts Town council districts districts

1,387 2,402 2,331 268(single (single (single Connections (single-2,262& three phase-264& three phase-1,337&three phase-2,321&three phase 69) phase-4) phase-50) phase-81)

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 12 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development 2.4.3 New Services Territories

Four new service territories (North Eastern, Lira, Gulu and Mbarara) with ongoing projects are being progressed for operators under management contracts in the interim for a period of three years. UEDCL has been earmarked to provide the management services and we have communicated to PPDA to allow us do a direct procurement for UEDCL.

2.4.4 Key challenges:

Increased bulk supply tariff (59%) for energy to the concession holders without a corresponding increase in the end user tariff.

Increasing infrastructure maintenance costs as assets like poles require replacement earlier than anticipated and the subsidised connection materials are now exhausted.

2.5 Solar Photovoltaic targeted Market Approach (PVTMA)

With support from the World Bank under ERT II, implemenetation of the solar PV Targeted Market Approach (PVTMA) continued with the provision of consumer subsidies and the promotion of consumer credit for both domestic and institutional/commercial solar systems that are located out of denser settlements where loads cannot be economically aggregated for larger grid projects. This programmes is meant to help spread the upfront cost of solar PV which is a main constraint to acquiring solar PV. The subsidy covers USD 5.5/Watt peak on installed solar home systems of up to 50WP including solar lanterns and USD 4.0 / Watt peak up to 500WP for commercial and institutional systems.

The program is implemented through various approved models which include Regulated Financial Institutions (PFI's) Pay plan, Fee for service as well as Savings and Credit Cooperatives (SACCO's).

Upon verification of solar PV installations for compliance to set standards through the end user audit and verification by an independent audit firm, the subsidy is channeled to end-users through the financial institutions . Currently Four regulated financial institutions, over 100 SACCO's and 24 solar companies are participating in the program. The PFI's include Post Bank Uganda, FINCA Uganda, Centenary Bank Limited and Opportunity Bank Uganda. A total of 3,664 solar Home systems and Institutional /commercial systems have been installed in various rural areas.

In addition, REA is facilitating awareness creation and marketing of solar PV loans as well as building the technical capacity of PFIs to handle solar PV technology. REA in collaboration with participating PFI's and MSC, conducted regional workshops targeting PFI, SACCOs staff as well as marketing support through radio campaigns and printing brochures.

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 13 Rural Electrification Agency Ministry of Energy and Mineral Development

3.0 SOCIAL INTERMEDIATION, ENVIRONMENTAL AND WAYLEAVES ISSUES

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 14 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development 3.0 SOCIAL INTERMEDIATION, ENVIRONMENTAL AND WAYLEAVES ISSUES

This section covers issues on environmental management, way leaves and compensation and community sensitization on a range of issues including; productive use of energy, health and safety and energy efficiency issues handled in the FY 2011/12.

Ms. Deborah Nantume, Senior Construction Engineer explains to the Minister of Energy and Mineral Development, Hon. Eng. Irene Muloni, how the ready board works. Looking on is Asst. Commissioner for Energy Efficiency, Mr. James Banaabe

3.1 Community sensitization and Social Intermediation

The unit for Public Information and Outreach is mandated to provide information on all rural electrification projects to the communities that are beneficiaries of the RE programme, investors and the general public. The unit also sensitizes the public on productive use of energy, energy efficiency, health and safety issues as well as way leaves issues including general awareness about the institution and its mandate.

In relation to this role, the unit conducted the following activities;

· Community sensitization on way leaves, productive use of energy, energy efficiency, health and safety issues · Radio talk shows in several national and community based stations · Supplements on achievements and plans in media outlets

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 15 Rural Electrification Agency Ministry of Energy and Mineral Development · Television adverts · Ground breaking and commissioning projects · Meetings, Seminars and Workshops · Consumer mobilization for REA concessions · Participation in activities in partnership with stakeholders including participation in the · MEMD annual Energy Efficiency Week · Corporate Social responsibility

o Mobilised financial and material resources for the Bududa Landslide victims

o Mobilized resources for the Bundibugyo cooperative when their offices were destroyed as a result of strong storms

3.2 Environmental issues

REA is involved in and promotes the implementation of mainly, Renewable Energy Projects (Clean Energy), namely Hydropower Dams (Small, Mini, Micro), Power Lines, Solar PV Systems. Rural Electrification projects have environmental and social aspects that are identified through environmental and social impacts assessments and accordingly addressed by implementing the proposed mitigation measures, in line with Environmental and Social Safeguard Policies of the Government of Uganda and/or the Development Partners.

At the beginning of FY 2011/2012, REA recruited an Environmental Specialist to handle Environmental and Social aspects of the Rural Electrification projects. His main duty is to Coordinate environmental and social impact studies of the Rural Electrification Projects and ensure compliance with the GoU/National (NEMA) and donor environmental/social requirements and safeguard policies respectively.

REA's Environmental and Social Management Framework requires Monitoring of the Agency's projects in order to ascertain compliance with Environmental and Social Safeguard Policies of GoU and the funding partners in order to assess the implementation of the Environmental and Social aspects, with a view of recommending appropriate remedial measures to guide project implementation. In order to realize the above-stated obligation, REA has developed Environmental Monitoring Plans and/or Frameworks, aimed at guiding the implementation, monitoring and reporting of Environmental and Social aspects of all RE projects.

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 16 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development

Project Environmental Compliance Status · EIA approvals by NEMA in place. ERT- 3 Old Projects · Environmental Monitoring Frameworks & plans in · Soroti-Katakwi-Amuria 33 kV line place/ under implementation. · Ayer-Kamudini-Minakulu-Bobi 33kV line · Compliance monitoring on-going by REA and · Ibanda (Igorora) -Kazo-Rushere- Supervising Consultant largely Compliant. Rwemikoma-Kyevisa 33kV line · No social issues. ERT- 6 New Projects · Gulu-Acholibur and Opeta Acokara 33 kV · EIAs undertaken, Reports submitted to NEMA for lines review & approval. · Masindi-Buliisa-Waki and Nkonge-Kashozi · Stakeholder consultations undertaken and all Local 33kV lines Authorities and Communities aware of & support · Ruhiira Millennium Village RE 33kV line development of the respective Projects. · Ntenjeru RE 33 kV line NORAD – 5 Projects under Construction · Muhanga-Rwamucucu-Kahambya-Rugeyo/ Kyempene 33 kV lines · EIA approvals by NEMA in place. · Myazi-Kiganda 33kV lines · Environmental Monitoring Frameworks & plans in · Kabale-Kisoro 33 kV line place/ under implementation. · Mubende-Kyenjojo 33 kV line · Compliance monitoring on-going by REA and · Rakai-Isingiro, Lyantonde-Lumbugu, Supervising Consultant largely Compliant Kaliro-Lwebitakuli, Sembabule-Lwemiyaga · No social issues. 33 kV lines · Gulu-Adjumani-Moyo, Apala-Adwari-Kiiru, Rackokoko-Awere-Lalogi 33 kV lines NORAD – Proposed Projects · Kiganda-Mile16 and Ruhumba-Kashwa 33 kV line · Procurement of Consultancy to undertake EIA is · Kibaale-Kikalu, Namalemba-Nakalama, under way. Namutumba-Mazuba & Kaliro-Nawaikoke- Iyingo Landing Site 33kV lines · EIA undertaken and approval from NEMA JICA – Proposed Project obtained. · Mayuge-Lumino 33 kV line · Project implementation to be monitored during construction. BADEA –Projects · EIA undertaken and approval from NEMA · Kapchorwa-Bukwo-Suam, Mayuge- obtained. Bwondha Landing Site, Kasambira- · Project implementation to be monitored during Bugulumbya-Bukuutu 33 kV lines construction. · Mityana-Lusalira, Lake Victoria free trade zone, Apac-Chegere-Alemi, Hoima- · Procurement of Consultancy to undertake EIA is Nalweyo & Kitgum-Namakora/Padibe 33 under way. kV lines · Environmental Scoping undertaken. Bukakata-Kalangala & Environs RE project · Procurement of Consultancy to undertake EIA is under way. · Environmental Scoping undertaken. Diesel based mini-grids for Island Communities · Procurement of Consultancy to undertake EIA is (Buvuma & Kome Islands) under way. · Environmental Scoping undertaken. OPEC Proposed Projects · EIA being planned after Engineering Designs have · West Nile ST, Lira ST, Mid-Western ST, been obtained. North Eastern including East Nile ST

KFW Projects · EIA undertaken and approval from NEMA · Arua-Maracha-Koboko-Yumbe, Nyapea- obtained. Zombo-Zeu-Warr-Vurra, Nebbi-Nyarurur- · Project implementation to be monitored during Pakwach-Panyamur 33 kV lines construction.

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 17 Rural Electrification Agency Ministry of Energy and Mineral Development 3.3 Ways Leaves and Compensation

Figure 1: Way Leaves Officer, James Litta explaining compensation procedures to residents in Serere, to his right are members from the Communication and PR unit

The Way leaves Unit and Communication and Public Relations Unit in liaison with Local Governments has continued to sensitize the general public about provision of way leaves in all areas earmarked to benefit from the rural electrification programmes and schemes. In the reporting period the following areas have been handled;

Wayleaves compensations paid to claimants of the33 kV power lines listed below;

ERT II Completed RAP Studies under implementation;

· Ibanda – Kazo – Rushere 33kV power line (60% paid) · Soroti – Katakwi 33 kV power line - Paid · Ayer – Bobi – Kamudini – Minakulu - Paid

ERT II EIA/RAP Studies complete awaiting NEMA & CGV Approval:

· Ruhiira Millenium Village · Ntenjeru – Bule - Mpenja · Gulu-Acholibur and Paicho-Patiko-Palaro · Opeta-Achokora and Iceme Otwal

GOU Priority Rural Electrification Projects – Wayleaves compensation assessment complete and approved by CGV. Awaiting payment of claimants.

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 18 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development Lot 1

· Sironko – Nakapiriprit – Amudat · Katakwi – Moroto –Matany – Lorengedwat · Kitgum – Palabek and Lira – Apala –Aloi

Lot 2

· Busia /Mbale/Manafwa · Soroti/Pallisa/Bukedea/Tororo · Lwala – Kaberamaido – Kobulubulu – Amolator & Kelle Port, Lwala – Otuboi – Acinip and Lwala – Dokolo

Lot 3

· Kakumiro – Birembo – Nalweyo, Bukwiri – Kyankwanzi and Kayunga – Busana · /Mukono · Kyenjojo/Kibaale/Masindi · Sembabule/Masaka

Lot 4

· Ibanda – Kabujogera and Muhanga – Kamwezi · Mpanga – Kamwenge – Kahunge – Nkingo · Bushenyi/Mitooma/Rukungiri/Ntungamo · Rwebisengo – Kibuuku

NORAD I RAP Studies– Complete awaiting CGV's approval

· Muhanga – Rumucucu – Nyakisenyi – Kisizzi – Kyempane · Myanzi – Kiganda

NORAD II Wayleaves Acquisition – Awaiting Contract Signature

· Mubende – Kyenjojo · Rakai - Lyantonde – Isingiro – Sembabule · Kabale – Kisoro

NORAD III Wayleaves Acquisition – Under procurement

· Gulu-Adjumani-Moyo · Apala-Adwari-Kiiru with a tee-off to Morulem · Rachokoko-Awere-Lalogi

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 19 Rural Electrification Agency Ministry of Energy and Mineral Development

4.0 CAPACITY BUILDING

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 20 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development 4.0 CAPACITY BUILDING

This section covers the capacity building efforts undertaken by the Agency during 2011/12 in a bid to strengthen its service delivery.

Beneficiary Institute Course Period Ms. Barbara Asiimwe Uganda Law Society Arbitration, Mediation 19th July 2011 – Legal Officer/Board and Dispute Resolution Secretary in Oil and Gas Ms .Deborah Nantume Grontmij International Distribution 22nd August – 16th – Senior Construction and AF-Industry Management 2011 September 2011 Engineer Mr. Wilson Grontmij International Distribution 22nd August – 16th Nyabutundu – Rural and AF-Industry Management 2011 September 2011 Electric Cooperative Development Officer Mr. Eric Sakwa – Profounder Procurement , 22nd – 23rd September Internal Auditor Intelligence Tendering, Supply 2011 Management Services Chain & Contract Risk Management Training Ms. Edith Kuteesa – Transafrican Annual Conference 05th – 09th December Personal Assistant to Management Institute for the Executive 2011 ED (TAMI) Secretaries and Administrative / Personal Assistants (ACESA) Standing the Waves of Change, Embracing the Opportunities Ms. Patricia Litho EU Energy Initiative Productive Use of 20th – 22nd September – Communication Partnership Dialogue Electricity 2011 & Public Relations Facility in Cooperation Officer with the African Electrification Initiative Ms. Helena Nyangoma Development Training Effective 28th November 2011 – Receptionist Institute Communication Skills 9th December 2011 Mr. Patrick Kyakulaga Eastern and Southern Finance and Audit 02nd – 21st October – Manager Finance & African Management of Donor Funded 2011 Administration Institute Programs Mr. Wegulo 2KO International MCITP Server 2008 31st October – 21st Byakatonda Administrator training November 2011 – Information Technology Specialist Mr. Eric Sakwa – Eastern and Southern Managing the Audit 14th November to 09th Internal Auditor African Management Function Program December 2011 Institute

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 21 Rural Electrification Agency Ministry of Energy and Mineral Development

Mr. Phillip Ggayi Japan International Sustainable Rural 01st November – 03rd – Senior Planning Cooperation Agency Electrification December 2011 Engineer Promotion Utilizing Renewable Energies

Mr. James Litta – Way The College of Estate Property Valuation 01st December 2011 leaves Officer Management Mr. Daniel Kisira Club ER Secretariat PV – Diesel and 27th November 2011 – – Senior Planning Wind Diesel Hybrid 02nd December 2011 Engineer Solutions Ms. Susan Kavuma Egyptians Fellowship Renewable Energy 05th September 2011 Kisira – Senior Training Hydropower Plants Planning Engineer Rural Electrification and Energy Efficiency Ms. Barbara Nambuya Modern Management Advanced 05th – 09th December – Administrative Institute Management Skills 2011 Assistant Mr. Wilson Maputo Rural Electrification 14th – 19th November Nyabutundu – Rural Forum 2011 2011 Electric Cooperative Development Officer Mr.Godfrey Werikhe Energia International Bridging the Gender 12th – 13th December – Manager Project Network Gap for Development 2011 Development and Effectiveness in the Monitoring Energy Sector

Ms. Patricia Litho Energia International Bridging the Gender 12th – 13th December – Communication Network Gap for Development 2011 & Public Relations Effectiveness in the Executive Energy Sector

Mr. Medard Muganzi Energia International Bridging the Gender 12th – 13th December – Manager Energy for Network Gap for Development 2011 Rural Transformation Effectiveness in the Energy Sector

Mr. Thom Amaku – Egyptians Fellowship Renewable Energy 11th – 22nd December Senior Construction Training Hydropower Plants 2011 Engineer Rural Electrification and Energy Efficiency

Mr. Daniel Kisira Indian Institute of Small Hydro Power 31st January – February – Senior Planning Technology Roorkee Development 2012 Engineer Mr. Charles Lutwama Egyptians Fellowship Renewable Energy 12th – 23rd February – Senior Planning Training Hydropower Plants 2012 Engineer Rural Electrification and Energy Efficiency

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 22 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development

Ms. Barbara Asiimwe Uganda Law Society Land Litigation 15th February 2012 – Legal Officer/Board opportunities and Secretary Challenges

Ms. Barbara Asiimwe Uganda Law Society Principals of 15th March 2012 – Legal Officer/Board International Trade and Secretary East African Regional Integration Law Ms Diana Balihikya - Uganda Management Budgetary 16th – 20th April 2012 Accountant Institute Management and Expenditure Control Mr. Godfrey Spintelligent (PTY) African Utility Week 31st – 24th May 2012 Turyahikayo – LTD 2012 Executive Director Ms. Barbara Asiimwe Uganda Law Society Litigating Labor 08th June 2012 – Legal Officer/Board Disputes Secretary All Staff By Bwanika Richard Records Management 25th – 27th June 2012 Public Servant

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 23 Rural Electrification Agency Ministry of Energy and Mineral Development

5.0 FINANCIAL PERFORMANCE FOR THE YEAR 2011/2012

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 24 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development 5.0 FINANCIAL PERFORMANCE FOR THE YEAR 2011/2012

The Rural Electrification Fund was set up following the enactment of the Electricity Act 1999. Pursuant to Section 65 (1) and (4) of the Act, the Statutory Instrument 2001 No. 75 that provided for establishment of the Rural Electrification Board to oversee management of the fund was issued. Under the same instrument, the Rural Electrification Agency was also established as a Secretariat of the Board among other functions.

The monies of the fund consist of money appropriated by Parliament, any surplus moneys made from operations of the Electricity Regulatory Authority, a levy of 5% on transmission bulk purchase of electricity from generation stations and donations, gifts, grants and loans acceptable to the Minister responsible for finance.

During the financial year under review, the fund received monies from World Bank (GEF and IDA), Government of Uganda through treasury releases and the levy on transmission bulk purchases. A summary of the Agency's financial performance is reflected in the tables below showing receipts and application of the funds.

5.1 Highlights of financial performance

5.2 Rural Electrification projects

5.3 RE support Programmes-Ministries

5.4 Operations (REB & REA)

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 25 Rural Electrification Agency Ministry of Energy and Mineral Development

6.0 PROJECT IMPLEMENTATION PLANS FOR 2012/13

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 26 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development 6.0 PROJECT IMPLEMENTTAION PLANS FOR 2012/13

In the Financial Year 2011/2012, the following projects were planned for:

6.1 Community Schemes (Government of Uganda Financing)

During the period of July 2011 to June 2012, the Agency successfully packaged twenty eight (28) community-initiated schemes (worth Uganda Shillings 3,493,565,590/- only) within the UMEME footprint (shown in Annex V) where the respective beneficiary communities contributed at-least 30% of the associated Low Voltage network costs.

The overall project scopes comprised construction of over 29 km of High Voltage lines and 38 km of LV network in various districts of the Country.

Annex VI shows UMEME schemes (worth UGX19,461,635,559/- only) awaiting cost- sharing financing.

In addition to the above, Annex VII shows schemes outside the UMEME footprint (worth UGX81,238,962,754/- only) for which the Agency carried out preliminary power line surveys covering over 794 km of High Voltage lines and 317 km of associated LV reticulations. The schemes are ready for implementation as soon as funding is available.

6.2 JICA III Grid-extension projects

Following the successful implementation of JICA II grant-financed grid-extensions (i.e. Kagadi-Munteme, Masaka-Bukakata, Nabitende-Itanda and Iwemba-Bugeso), JICA engaged Yachiyo Engineering Co. Ltd to appraise the following Phase III proposals:

· Mayuge – Lumino · Kitagata – Kasana & Kitagata-Kabwohe · Bikira – Masaka & Masaka - Nyabyajjwe · Baale - Galiraya · Kiganda - Mubende · Hoima – Mbaraara - Kinyara

Working closely with REA, the JICA consultant ranked Mayuge – Lumino as the most feasible project in accordance to the Appraisal Report dated March 2012 where JICA expressed interest in funding the 33 kV grid-extension line and the Government of Uganda will be required to finance LV reticulation network costs including payment of way-leaves compensation and all associated URA tax obligations.

In view of the above, the Agency finalised the LV network designs and obtained the Certificate of Approval of Environmental Impact Assessment from NEMA for the whole project scope comprising of approximately 134.4 km of 33 kV network, 64 km of LV and installation of 50 distribution substations.

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 27 Rural Electrification Agency Ministry of Energy and Mineral Development The project will be ready for implementation as soon as a financing agreement between the Governments of Uganda and Japan is signed.

6.3 BADEA Grand Financing

The Government of Uganda received a Grant (worth US$400,000.00) from the Arab Bank for Economic Development in Africa (BADEA) towards the cost of technical assistance to finance feasibility studies for grid-extensions in the following five areas:

Baale - Galiraya with tee-offs Kayonza – Kawololokato – Namizo, Kitwe – Kafumba, Kasokwe – Gwero, Kyna – Buyobe-Kawuku, Kitimbwa – Nkonkonjeru-Nakivubo, Kyerima-Namabuga, Nakyesa-Kakiri-Namanoga, Kyanya – Busale-Nongo, Nabuganyi- Mutukula-Namusala-Lusenke, Nabuganyi-Bukolwa, Busaana, Busaana-Namirembe, Kanjuki-Buwumbiro and Sente Anyize-Bukasa. (150 km of HV network)

Nabirumba - Bugaya - Kitukiro - Buyende and Environs (160 km of HV network)

Bikira – Namirembe & Masaka – Nyabyajjwe (95 km of HV)

Katobo - Rwenshama via Bwambara and tee-offs to Kishenyi, Bubangizi-Kanyabwanaga, Kigongi, Rwenpungu, Kisiizi, Kashasha, Ndere, Rwenshaka and Kashenyi including Kitagata-Kasaana & Kitagata – Kabwohe (180 km)

Gulu - Olwiyo – Pachwach with tee-off Gulu – KochGoma, Spur Agong, Spur Wii-Anoka and Spur Alelele Lira (110 km)

In accordance with the Letter of Understanding signed between GOU and BADEA on 23 October, 2011, REA was obliged to procure consultancy services to undertake the engineering designs and environmental assessment in line with BADEA procurement guidelines. Consequently, by the end of Financial Year 2011/12, REA had submitted a short-list of consultants for BADEA no-objection.

6.4 Uganda Accelerated Rural Electrification Project (World Bank Financing)

The Agency worked closely with National Rural Electric Cooperative Association (NRECA) International Ltd, a consultancy firm that was contracted by the World Bank under the Energy for Rural Transformation, to prepare the new Rural Electrification Strategy and Plan (RESP) for the period 2012 – 2021.

Once approved, the RESP will be the new Government Policy whose specific goal is to raise the rural electricity penetration rate from under 3% in 2011 to 22% by the end of the ten-year period in 2021. Also, the RESP will be used as a trajectory of achieving universal electrification access by 2040 taking into account a number of important lesson learnt during the period 2001 – 2010.

The principal difference between the old RESP (2001 – 2010) and the new RESP (2012 – 2021) is that the new policy document will focus mainly on implementing rural electrification projects using Public Financing as opposed to Public Private Partnerships used earlier. ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 28 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development Furthermore, the new RESP (2012 – 2021) has introduced the Service Territory Concept whereby the rural electrification sector is to be divided into thirteen (13) commercially viable electricity distribution service areas. Each area will have a ten-year business plan with given financial resources and connection targets towards achieving an overall 22% electrification rate by 2021. A map of the proposed rural service territories is given in Annex IV.

Following a number of stakeholder consultative meetings, the draft final RESP (2012 – 2021) was finalised in May 2012 and consequently submitted for cabinet approval in June 2012.

6.5 Procurement of Bukakata-Kalangala Interconnection (Government of Uganda Financing)

During the Financial Year 2011/12, the Agency initiated the procurement of consultancy services to undertake Engineering Design and Environmental Assessment for the construction of a 33 kV sub-sea cable to inter-connect Kalangala Island mini-grid to the National Grid. It is expected that the design will be completed by April 2013.

6.6 Procurement of Feasibility Studies of New Service Territories (Government of Uganda Financing)

In line with the emerging RESP (2012 – 2021), the Agency initiated the procurement of consultancy services to undertake feasibility studies in the proposed Service Territory areas. The studies will be ready by June 2013 and accordingly packaged for implementation during the Financial Year 2013/14.

6.7 Engineering Designs for the Proposed Government of Norway Phase III Financing

In line with the existing five-year framework financing agreement between the Governments of Uganda and Norway, the Agency packaged a proposal worth USD21.2 million seeking construction funds to implement the following grid-extension projects:

· Ruhumba – Kashwa with tee-off Rwebishuri (113 km of 33 kV lines) · Kibaale – Kikalu, Namalemba – Nakalama and Namutumba – Mazuba (81 km of 33 kV lines)

· Kaliro – Nawaikoke – Iyingo Landing site with tee-off Saka Bridge (132 km of 33 kV lines)

· Kiganda – Mile 16 with tee-offs Katabalanga and Kibyamirizi (117 km of 33 kV lines)

The proposal was submitted to the Norwegian Embassy ( Office) for review and approval in June 2012.

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 29 Rural Electrification Agency Ministry of Energy and Mineral Development

7.0 IMPLEMENTTAION CONSTRAINSTS AND PRPOSED SOLUTIONS

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 30 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development 7.0 IMPLEMENTTAION CONSTRAINSTS AND PRPOSED SOLUTIONS

Rural electrification is impacted on by social and political issues. One aspect is the local community-level problems associated with the right of way for electricity lines as they traverse the countryside. The other aspect is the politics surrounding electricity, whereby political leaders want their constituencies prioritized for service, thus exerting undue pressure on the responsible institutions in spite of the limited resources. These issues form the basis of the issues which have been encountered during the period of reporting as highlighted below;

7.1 Constraints

7.1.1 Limited Government Budget

Appropriations from the Consolidated Fund have been inadequate and inconsistent. It is instructive that adequate funds be committed from the Consolidated Fund to support the Rural Electrification Programme so as to give confidence to development partners about Government's seriousness about rural electrification and also take care of ongoing pressures for electricity services all over the country. Otherwise, the ambitious targets we have set will never be met.

7.1.2 Issues of way leaves and compensation

While it is expected that private rights should give way on occasion to the wider public interest, it is not always the case. REA continues to experience resistance from some communities on the issue to the extent of blocking construction works. Some sections of the public tend to view rural electrification schemes as a way to make quick gains especially when asked to consent to routing power lines through their land. They often make exorbitant claims for compensation in total disregard of approved district compensation, as a result some projects have been held up while the Agency and Local

7.1.3 Authorities try to negotiate for way leaves.

The biggest source of conflict is the fact that most people affected expect and demand for upfront payment before commencement of the project. However, the compensation process is rather lengthy due to the fact that REA has to adhere to acceptable Government procedures which involve claim verification and clearances by institutions outside the Agency including the Government Valuer and Auditor General. It is important to note that as a rule, Government has to compensate those individuals whose property (crops, plantations, buildings, etc) has been affected. However an increased compensation bill directly affects the Agency's role out programme since money is used for compensation of way leaves damages instead of being utilized for construction of more power lines.

7.1.4 Cost of investment and Connection rates

Connection rates often remain low long after a project is completed even up to a period of two years. Experience shows that in areas where schemes have been constructed, only about 10% of the originally projected consumers get connected. In order to cure this problem, REA introduced the concept of community contributions for the low voltage ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 31 Rural Electrification Agency Ministry of Energy and Mineral Development network (detailed under 6.2). However, the community leadership in most cases has not been able to mobilize the communities to make the necessary contributions once REA has communicated the costs of these schemes to them.

7.1.5 Increasing demand for electricity

There is a lot of pressure from leaders and communities to have electricity extended to their areas. Focus is particularly on grid-extension, whether it makes financial/economic sense or not. Yet, much of the demands could be met by other means, like solar electrification (Solar PV Systems). With the publication of the recently finished Rural Electrification Master Plan, we have rationalized our planning perspective. However, the bottom line is that these pressures can only be addressed if there are reasonable financial resources to extend either grid or off-grid power.

7.1.6 Inadequate local private sector capacity in the power industry

One of the challenges the programme has experienced is that of inadequate local capacity to invest (especially in renewable energy projects) and undertake construction of infrastructure. This has resulted into the bulk of renewable energy projects supported by the programme being undertaken by foreign developers, limited credible bids for construction works and limited bids for operating built networks and delayed project development processes.

7.1.7 Inadequate productive uses of electricity.

Low productive uses of electricity reduce the financial viability of rural electrification initiatives. Because end users are not using the electricity productively, there appears a low demand factor and revenue accruing to the end users remains low. Ultimately, this reduces the economic benefits of the rural electrification.

7.2 Intervention Measures and Strategies

7.2.1 Community Schemes

To be able to reach a wider group REA accepts community initiated schemes. This however only benefits those within a radius of 1 to 2 km. the procedure includes;

· Community mobilises itself and sends an expression of interest to REA · Community expresses a willingness to cost share with REA (30/70) and endorses consent in writing · Community must be willing to contribute right of way towards rural electrification project and endorses right of way in writing. · REA appraises schemes for economic viability · REA mobilises for surveys and costing of works · Community makes its contribution to REA's Account. · REA mobilises for construction of schemes.

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 32 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development 7.2.2 Low cost technology (ready boards)

REA promotes alternative technologies in addition to the grid including solar energy and low cost wiring using the Ready Board. REA also promotes the use pre-paid metering systems so that consumers can better manage their consumption.

7.2.3 OBA (subsidy)

Under ERT II, initial consumer subsidies for “immediate connections have been instituted while an output based aid (OBA) Scheme to provide an output-based type of subsidy has also been worked out for consumers who cannot pay for connection within the first 18 months of the commissioning of a project.

The OBA Scheme is a 4-year project funded by the World Bank (IDA), the Global Partnership on Output-Based Aid (GPOBA), the Government of Uganda and the German Financial Cooperation (KfW). The project aims at connecting about 132,500 low-income Ugandan households (or approximately, 655,000 beneficiaries) to electricity grids throughout Uganda, in rural, peri-urban and urban areas.

7.2.4 Corporate social responsibility, Community consultations and awareness creation processes

Continuous community sensitization and negotiations on the various conflicts related to way leaves and compensation does make a difference. Many times some of the conflict is politically motivated and REA has to continually visit projects areas to re-assure the communities until the compensations are made.

In addition REA endeavours to extend Corporate Social Responsibility (CPR) to the communities they work, in order to gain community confidence in the projects and also solicit the necessary support. The Agency supports causes, seminars and gives tips o productive use of energy through seminars and radio talk shows and advertisements.

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 33 Rural Electrification Agency Ministry of Energy and Mineral Development

8.0 CONCLUSION

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 34 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development 8.0 CONCLUSION

The 2011/2012 Financial Year marked several milestones. REA managed to clear a backlog of way leaves compensations. This helped reduce the conflicts that were arising as a result of delayed payments.

A new Rural Electrification Strategy and Plan (RESP) for the period 2012 – 2021 was preparted and it introduced service territotries with empahsisi on public financing.

New initiatives were started to try and increase the number of connections within the REA projects area. An output based aid (OBA) scheme subsidy has been initiated to enhance connections for those who have not made connections to the grid 18 months after the commissioning of a project. The Royal Norwegian Government also came on board to offer connection subsidies for over 9,000 consumers.

The Financial Year also saw the several development partners coming on board to fund the Rural Electrification Programme including the Norwegian Government, KfW, the Saudi Fund for Development (SFD) and the Arab Bank for Economic development in Africa (BADEA). This is in addition to other funders the Agency has always had on board including the Government of Uganda, the World Bank, JICA and Sida.

It is the Agency's sincere hope that the lessons learnt and the experience gained during this financial year will be used to put in place the right mechanisms for a successful Rural Electrification Programme in future.

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 35 Rural Electrification Agency Ministry of Energy and Mineral Development

9.0 AUDITED REPORTS FY 2011/12...

ANNEXES

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 36 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development ANNEX I PROJECTS COMPLETED AND COMMISSIONED DURING 2010/2011 FY

A. Government of Uganda Funded Projects A.1 Medium Size Turnkey Projects

Project Name District Load Centers Status

Electricity Power Networks Matinza T/C and Environs in Kisoro District Karuhuri T/C, Gatete T/C Kisoro Commissioned in February · Mutolere – Matinza-Nya- and environs, Chibumba 2011 1 kabaya TC, Sereri TC, Chahafi TC, · Kyanika – Mulora Murora S/County

Electricity Power networks Budabangula, Bukanga, in Tembo, Bulonge Busalamu, Namadope, Iganga /Luuka complete awaiting commis- and Kiyunga Kinawanswa, Bulamagi, 2 sioning · Tembo – Bulonge – Bubowoza Kiyunga

Electricity power networks in Mutala, Mutaka Kaoline Mutala Tc and Mutaka Kao- mines and Nyakahika Bushenyi / complete awaiting commis- iline Mines, Nyakahita TC, 3 · Mutala – Mutaka Kaoline Kabarole sioning Kiburara and environs mines – Nyakahika · Kiburara & environs Itojo TC, Karagwe TC, Rwen- Electricity power networks yonzi Village, Kichwambi- 4 in Ntungamo District Ntungamo roTC · Mpaama – Nyakyera Kyabajwe Village complete awaiting commis- · Kabuhome Kabuhoma TC,Nyaburizi TC, sioning · Itojo Subcounty and Omukakoni TC environs Nyakyera TC, Rwenyontonzi TC, Kishami TC

Electricity power networks Paidha Japdong Village Commissioned in September in Paidha and Nebbi 5 Nebbi 2010 · Japdong village

Electricity power networks Pallisa Agule TC, Kamaka TC, 6 in Pallisa, Tororo, and Kaboli TC Mbale Kwapa Community, Asinge Commissioned in June 2011 · Kaboli – Agule – Kamake TC, Khamoto · Kwapa and Asinge Mooni TC · Khamoto and Mooni Electricity power networks Namwalo, Shikoye, Wapon- in Mbale and Budaka Mbale do, Buyaka Villages Commissioned in June 2011 7 · Lyama & Kakoli Budaka Kakoli TC, Naboa TC, Lupa- · Namwaalo village da TC Padibe West TC, St Paul and Electricity power networks Peter HC II Padibe, Padibe in Kitgum, Padibe and Lamwo Vocational, Commissioned in February Lokung 8 Padibe s/county, Lukona 2011. · Kitgum – Padibe – TC, Abakyadek TC, Lai TC, Lokung Lokung Electricity power networks Ochola TC, Mugaba TC, Commissioned in October in Budusu and Bunawale Butaleja Habiga TC, Budusu TC, 9 2010. · Budusu – Bunawale Kamwokya

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 37 Rural Electrification Agency Ministry of Energy and Mineral Development

Namungalwe TC, Nabitende Electricity power networks TC, Bugono TC, Kiwanyi TC in Nabitende and Itanda Iganga Nawangaiza TC, Naluko · Nabitende – Kawete - Commissioned in March 2011. 10 TC, Ituba TC, Itanda TC, Itanda Nawankwale TC, Naguwa

TC Bugeso TC, Iwemba TC, Electricity power networks Bugiri Nabirere TC, Buyala TC, in Bugeso and Iwemba Commissioned in March 2011. 11 Nambo TC · Bugeso - Iwemba Busimba TC, Kigulu TC

Kyabajanja TC, Katoo- Construction of rural elec- go,KasanaTC, St mary’s trification schemes Mitete PS, Ndaiga, complete awaiting commis- Kalubulu-Mitete-Lwebi- 12 Lwebitakuli TC, Katimba sioning takuli Mitete TC, Kalugungu TC, Kalubulu

Kaswa TC, Lusakalwamese, Magiri, Kamulegu PS, HCII Kyanamuka-Kyesiga-Dimo and TC, Lwemode, Kyesiga complete awaiting commis- landing site 13 village,Gayaza kanala TC, sioning Bbuliro TC, Ddimo landing site

14 Mpanga-Kamwenge evacu- Commissioned in October Kamwenge ation line 2010.

A.2 Projects Implemented and completed through UMEME Scheme Name District 1 Electricity supply to Sonde village Mukono 2 Electricity supply to Ddundu, Kyampisi Wakiso 3 Electricity Supply to Amakol Trading centre Kapchorwa 4 Electricity supply to Burkoyen trading center Kapchorwa 5 Electricity supply to Nalugugu Trading center Mbale 6 Electricity supply to Buwagogo Commu- nity Mbale 7 Electricity supply to Kaucho C Community Palisa 8 Electricity supply to Buwanyanga Trading Sironko center 9 Electricity supply to Rwabutura, Itendero Bushenyi additional works 10 Electricity supply to Kicucu Trading center Kabarole 11 Electricity supply to Rutooma Modern Mbarara Community

A.3 Projects Implemented and completed through UEDCL Scheme Name Status 1 Kitakamwe- Nyamabale- Rubingo line in commissioned Kyabugimbi and Kyeizoba Subcounties

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 38 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development

2 Bubulo -Matsatsa Completed awaiting commissioning 3 Timuna-Nakaseke-Bwanga-Kasangombe Subcounty& Hanhe farm commissioned 4 Rwoburundo - Kinoni Completed awaiting commissioning 5 Lukumbi-Kalege and environs Completed awaiting commissioning 6 International Agriculture Lutembe commissioned 7 Mundazabazadde - Namaina commissioned 8 Tuba Village And Environs Completed awaiting commissioning 9 Kikamulo-Bujubya commissioned 10 Kabubbu-Bugerere,Magoma-Kyabarere,K- abbu town,-Wabitunda Kasimba- zi,Kiwoko Hospital and environs southern part) Completed awaiting commissioning 11 Nakaseke Suncounty & Kitto subcounty(- commissioned Mufunya-Kembogo, Kitto town & Naluvule TC LV) 12 Buyengo and Environs commissioned 13 Buwabwala S/County, 54 HV poles, 80 LV Completed awaiting commissioning poles 14 Kaptoyoy TC & Chepyakawet TC Completed awaiting commissioning 15 Ambassadors of hope-Kasiso TC-Abud- commissioned ul-Kadiri 16 Namisuni H/C and environs Completed awaiting commissioning 17 Power supply to Buyobo S/C (Sonoli TC, commissioned Buweri TC & Bunabonyo TC) 18 Bisheshe - Rwenkobwa Trading Centre Completed awaiting commissioning 19 Mutyoru,Kabukoch ,Kyelel village, kalasa Completed awaiting commissioning 20 Ntandikwa Villages, Kyesengok & Mailo Completed awaiting commissioning Tano 21 Kitumba Parish commissioned 22 Sisiyi Subcounty & Environs commissioned

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 39 Rural Electrification Agency Ministry of Energy and Mineral Development ANNEX II PROJECTS UNDER IMPLEMENTATION

A. A. Government of Uganda Funded A.1 Medium Turnkey Projects Implemented by REA Project Name District Load Centers Status 1 Electricity power networks in Kamuli / Nakulyaku Tc, Namwigulu Construction experienced de- Kamuli and Namutumba Namutum- Tc, lays however contractor asked · Namutumba - Bugobi ba Bulange TC, Nawampandu to resume works Trading Centre TC, Buwampa TC, Bugobi · Nakulyaku – Nabwigulu TC 2 Electricity power networks in Bushenyi Katoke TC, Karuyenje Works in progress and comple- Bushenyi and Rukungiri and TC,Buhunga TC,Rusheshe tion expected in August 2011 · Bugongi – Kyabuyonga Rukungiri TC, · PBID and environs Rwamugoma TC, Burombe · Buyanja – Nyabitete – TC, Kichwamba TC Nyakiju Omukokoni TC, Nyaburiza · Buhanga - Ruhinda TC, Kabuhoma TC PBID and environs Bugongi TC, Kabuyonga TC

3 Electricity power networks in Hoima, Kyamukonda, Kafu and Construction experienced de- Hoima and Nakasongola Nakason- Nakitoma TC lays however contractor asked · Bujwahya – Bulyango gola Bujwahya TC, Bulyango to resume works · Migyera – Nyakitoma TC and water scheme

4 Mpanga-Kamwenge-Ka- Kamwenge Mukekubo,Kasakye,Ngo- Works in progress and comple- hunge-Nkingo ma,Hima Cement Dura tion expected in September Offices 2011 Buhumuriro, Nkongoro, Kanyegarukire, Railway Staff Qtrs , Kamwenge, Afreka Hotel - Kamwenge, Businge, Kahunge 3, Ka- naara, Ganyenda, Prisons - Kamwenge, Rukunyu TC, St George PTC, Kyakanye- mera, Kahunge 1, Kahunge 2, Greenadine, Bigodi, Nkingo, Rukunyu HC, Dura Quarry

5 Construction of Sub stations Kamwenge 2x20MVA, 33kV/132kV Works in progress and comple- at Mpanga and Kahunge and substation and 33kV/33kV tion expected in ---=-=-- switching station switching station

A.2 Large Turnkey Projects implemented by REA Project Name District Load Centers Sironko-Naka- Sironko, Bunangaka, Bukaya P/S, Cheptui, Bunambutye T/C and environs, 1 piripirit-Amudat Nakapiripirit and Tabakonyi T/C, Kata Military Police Training School, Chepsukunya T/C, Amudat Pian Game reserve H/Qs, Takola HC, Ug. Namalu T/C and environs, Okwapwoa P/S, Takola T/C , Nakapiripirit T/C

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 40 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development

Katakwi-Moro- Katakwi, Ochormongin, Angariam T/C, Aakum, Iriiri T/C, Lorengecora T/C, 2 to with t-offs Moroto Matany T/C, Matany Parish hospital, State lodge, Kangole T/C, Kango- Matany le Mission, Moroto S/S area, St. Mary’s Seminary Nadiket and Lorenged- Kidiki village, Koire village, Atoot village, Kobwin TC, Tiling TC, Kobwin wat; Sub county and Health Centre, Opot and Adok

and Kobwin in Ngora

Lwala-Kabera- Kaberamaido/ Lwala T/C, Lwala Catholic Mission, Dokolo T/C, Abalang (Lira), Otuboi 3 maido-Kobulu- Dokolo T/C, Apaneti vllage, Anyar, Otuboi H/Q, Acinip, Kaberamaido Town- lu-Amolatar and ship, Kaberamaido S S., Alem TC , Kaberamaido District H/Q, Kabera- Kelle Port maido Junction, St. Charles Lwanga, Alem boarding Pri. School, Lwala-Otuboi- Kaberamaido Tech. Institute, Kobulubulu T/C, Kobulubulu Ginnery, Acinip and Kanyalam, Ochero T/C and Health centre, Kelle port,Ayala T/C and Lwala-Dokolo sub-county H/Qs, Abalanga, Dokolo TC, Otuboi TC, Apeneti Village,

Kitgum-Palabek Kitgum/Lira Kitgum Town centre, Pajumo sub-county H/Qs, Pajumo Pri. Sch., 4 and Lira – Apa- Community college Akwero, Opoki Army barracks & Pri. Sch, Palabek la-Aloi T/C, Palabek S S S, Palabek-Kal T/C, Palabek-Kal Pri. Sch, Obim rock T/C,Apara T/C , Abongdyang Pri. Sch, Abongdyang T/C, Aloi Sec Sch, Aloi High Pri Sch, Aloi Corner T/C, Rhino Academy, Aloi sub-county hqrs, Alebong Pri. Sch, Alebtong COmbatari T/C

5 Ibanda-Kabujo- Ibanda/Kam- Omurwera, Kichenche sub-county hqrs, Kitagwenda high school, gera-Kamwenge wenge Omukarere, Buryasungwe T/C, Sec Sch & Pri Sch, Fr. Kibira, Kinyungu and T/C, Omuruhiga, Bunena, Kabujogera T/C, Iryangabi T/C, Mahyoro T/C, Muhanga –Kam- landing site, Mildmay HC, Kichwamba TC, Ntara TC, Ntara Christian wezi sch, Rida Voc Training Centre, Rwentuha, Hon. Byamukama, Nyabani TC, Nyabani Health Centre, Rutoma T/C, Rwenyonza PS, Rwenyange TC, Omunkole, Mbarara TC, Kacucu, Kamwezi Catholic Parish, St. Mark SS, Kacucu PS, Kigara TC, Kamwezi HC, Kamwezi Voc/High Sch, Kam- wezi PS, Staff qtrs, Rwamatunguru TC, Kanyeganyegye PS, Kamwezi Border Post area- URA office

6 Kakumiro-Birem- Kibale/Hoima/ Kakumiro, Kikwaya, kikondo, Kasambya, Kiweza TC, Birembo TC, bo-Nalweyo, Kyankwanzi/ Kiboijana TC, Kikwaya TC, Kakindo TC, Kisaiji TC, , Kasenyi TC, Naseko Bukwiri-Kyank- Kayunga seeds, Nalweyo TC, Busaana TC, Composite school, Wampologoma TC, wanzi and Nabugany PS, Nabugany landing site, usaana Parents, Kyankwanzi, Kayunga-Busana Butemba

A.3 Medium Size Turnkey Projects being implemented by REA Project Name Targeted Load Centers 1 Busia/Manafa/Mbale Districts Masafu-Bushiko-Buhasaha-Na- Masafu, Bushiki, Buhasaha, Nahayeka, Buhehe hayeka-Buhehe Namawanga-Musese-Nabweyo Namawanga, Musese, Kimaluli Nabweyo Butiru-Bumbo-Lwakhakha Butiru, Munamba, Lwakhakha,Bumbo Nalondo-Namaloko Nalondo, Bugobera, Namaloko Sibanga-Bugobera Sibanga, Bugobera Busaamaga-Bukonde-Bufumbo Busaamaga, Bukonde, Bufumbo 2 Soroti/Pallisa/Bukedea/Tororo Districts Serere-Apapai-Bugondo Kidetok TC and PS, Pingire TC, Kasiro, Apapai TC and PS, Bugondo S/c HQs, Bugondo Ginnery and TC

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 41 Rural Electrification Agency Ministry of Energy and Mineral Development

Kanginima-Namiyembe-Kabelai Namiyembe TC, Kabelai TC, Okona-Bukedea-Malera-Atutur Kachabala TC, Ambasador stage,Apaade TC, Okona TC, Bukedea mis- Hospital sion, Kaloko TC,Kakere, Ochodong, Kanyanga TC, Kabilaep, Kotiokot, Osumujai, Malera S/county, Aligoi TC,Kasechi TC, Atutur village, Atutur hospital

Mailo 8-Lyolwa-Fungwe Funge PS and HC, Patumbo, Pobot, Bumanda, Pasindi, St, Mary PS Gule Lyolwa technical, church mision,S/county and TC, Nambogo, Serere, Jin- ja TC, Helping hands, Magoola, Mailo 11, Mailo 10 and Papoli PS, Mailo 8 and Odur PS, P’Otaala TC

3 Nakaseke/Mukono District Mayanja-Kelege-Nyanja Kelege, Nyanja village Kapeka-Wakinoni Wakinoni, village, Kapeka, Kabere, Bukeeka PS, Wakisi-Dekabusa Dekabusa TC, Wabiyinja Kikubamutwe-Nakwanga Kikubamutwe TC, Nakwanga TC Kisoga-Kiyola-Katete Kiyora TC, Buzzu, Katente TC, Bumbaja, Kisoko, Buyira village Katete TC and vocational institute 4 Bushenyi/Rukungiri District Rwabutura-Rwengando-Kiziba Rwengando, Kisiba, Nyakariro TC,Kazindiro, Kangarame,Bugangari TC and coffee factory, Katabushera, katonya TC and COU,Kashekuro TC.

Nyakagemye-Rugando-Nyabitete Rugando, Nyabitete, Rwerere-Bugangari-Kabugashe Rwerere, Omukagashe,Bugangari, Kyabugashe, Ryakasiga Kashekuru-Kyeibanga Kashekuru, Kyeibanga TC, Yesu Natamba Vocational Kabira-Rubanga Rubanga Rwakasiga-Kyempitsi-Nyamabare Kyempitsi, Nyamabare, Rugonza riverside academy, nyakihanga Kayeigoro-Kashozi-Kanekye Kashozi, Kanekye, rwanyamukinya 5 Kyenjojo/ Kibale/Masindi Districts Nyarukungo-Kidudu-Nyarukoma Nyarukungo, Kidudu, Nyarukoma S/county HQ, PS, SS, HC Murro Murro Catholic church, PS and TC Isagara Isagara Village Nyabeya Nyabeya Community, HC and PS. Katooke-Muhororo Bwalo TC, Katooke, Muhororo, Mukoole TC and Village, Kitaara, Nyank- wazi, Hansanju, Kyamutuzi TC, NyansekeTC, Muhororo TC

6 Bundibugyo District Kibuuku-Rwebisengo Bugando Village, Makondo TC,Rwebisengo S/county HQs, HCIII and TC

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 42 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development

A.4 Small schemes implemented as labor contracts through UMEME

Scheme Name District 1 Kasega TC Kiboga 2 Namayamba, Nsanve & Makulubita S/C Luweero 3 Kasanje TC Masaka 4 Kyanakase TC Masaka 5 Kakunyu TC Masaka 6 Kinoni Cell, Magamaga TC Mayuge 7 Maziba Village Mpigi 8 Namuyenje TC and Environs Mukono 9 Ddambwe TC and Environs Wakiso 10 Bunyiro Bubogo Iganga 11 St Stephens PS, Nawanyango Kamuli

12 Pulkewet TC Kapchorwa 13 Bamuketsi-Bamatanda Communities Mbale 14 Bukibokolo Health Centre Mbale 15 St James SS Tororo 16 Buhanika Seed Company Hoima 17 Agweng Township Lira 18 Amuca TC Lira 19 Nyamufura, Mukinga Bushenyi Yesu Natamba Day & Boarding PS, Nyakosho- 20 jwa Bushenyi Nyabuhama, Migina, Nyakabira, Omukapera 21 and Mushojwa Bushenyi 22 Ruhumba TC Ibanda 23 Bushuro-Kitumba Kabale 24 Nkumbura, Nyakibugwe Kabale 25 Kataraga Parish & Hamuhambo TC Kabale 26 Nyamabuga Kyenjojo 27 Kanyeganyege TC Mbarara 28 Rwentojo TC Mbarara 29 Nyakaguruka, Karora & Buhihi TC Mbarara 30 Bukuuna Parish Mbarara 31 Bwongyera HC, Omukataba TC Ntungamo 32 Kyabirara Market and Environs Ntungamo 33 Kyamakanda TC and Environs Rukungiri 34 Nyamayenje Rukungiri 35 Kigoma Trading Centre Bushenyi

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 43 Rural Electrification Agency Ministry of Energy and Mineral Development

A.5 Small Schemes implemented as labor contracts through UEDCL 1 Completion of Kikandwa- Mabindi Scheme to Cover HCII Luwero Iddi Corner - Butobe S.S.S- Kamenyamigo-Matakokore Catholic Mission - Nasule- 2 ta T/C scheme Pallisa 3 Nyakibyerere Village in Igara East Bushenyi 4 Nawanjovu Sub-County Headquarters, Bingo, Bubalya, Budembe,Kaiti, Nasingi Butaleja 5 Electricity to Kituntu Golo Mpigi 6 Nakigo, Bulubandi, Bugabwe,Kabira, Nawanzu, Buseyi & Wairama Iganga 7 Kalasa - (Makulubita) Luwero 8 Kadami Hospital Bukedea 9 Butega - Village And M/S 4 J Farm Mityana 10 Kolir & Algoi Tc & Environs Mbale 11 Muduuma Village Mityana 12 Bufumba Trading Centre Kamuli 13 Buyomba Trading Centre Kamuli 14 Nabirumba Trading Centre, Health Centre And Environs Kamuli 15 Bungokho Sub-County & Environs Mbale

16 Kadama - Kawami Trading Centre Palisa 17 Nyakisharara And Nyarubanga Village Mbarara 18 Namashere Mbale 19 Kikamulo S/County( Kikamulo-Nango) Nakaseke 20 -Kireeta Nakaseke 21 Lukolo TC Jinja 22 Nakabugu - Lambala Iganga 23 Apokor P/S, Kumi 24 Kidoko & Amurwo LV networks Tororo& Butalejja 25 Bulangira ( Radio Uganda) Palisa 26 Kumi Industrial TC Kumi 27 Kidetok Catholic Mission & TC Palisa 28 Magambo S/C HQs- Butoha HealthCenter ii- Bugaya Parish Bushenyi- Bunyaruguru 29 Izaniron Community farm and Extension of Magogo - Kakira Kamuli 30 Nawanyago Village Near Kamuli Girls School Kamuli 31 Kirindi/Bukamba/Budoda Kayunga 32 Kaliro-Katono Luwero 33 Bukolwa HC II and Environs Luwero 34 Kijebejo - Kasiso -Kibaale Nakaseke 35 kijebejo - Bugamba -Kimu Nakaseke 36 Guluddene Parish Wakiso 37 Tasanga Orphanage and Children Center in Busikuma Subcounty Wakiso 38 Electricity supply to Nombe S.S.S Mbarara 39 Budhatemwa Pri Sch and Kitayunjwa subcounty Kamuli

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 44 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development

B. Turnkey projects funded by the Government of Norway Name District Load Center 1 Myanzi- Kiganda Mityana Lubumba, Kakungube, Nalutuntu, Mulura, Namuganda, Kyakatebe, Kigoloba, Kalamba Kiganda, Nakiganda Sozinga Tc; Kiganda

2 Muhanga-Rwamucu- Kabale/ Rukun- Kyerero, Kandago, Nyakarambi, Mborozo, Hakakungu, Skoho, cu-Kisiizi-Kyempene with giri/ Kanungu/ Sindi, Ihanga, Mparo, Mparo Nozi, Rwamucucu, Kabirizi, Kitan- tee offs to Omukiyenge Ntungamo ga, Ntaraga, Kamusiza, Kantare, Kashambya, Kanyabugunga, and Rugyeyo via Nyak- Bikongozo, Kebishuha, Ntaara, Kirimbe, Omukarere, Omukiny- ishenyi inya, Nyarurambi, Nyakishenyi, Nyakisoroza, Murama, Karuka- ta, Ihambiro, Karama,Ndago,Katunga, Musyana, Nyabushenyi, Ikona, Omuruhanga, Nyakatunga, Kagina, Nyamakobora, Bwanga, Omukiyenje, Kyihungwe.

C. Turnkey Projects funded by World Bank under ERT II

Name District Load Center

1 Ibanda- Kazo and Kyab- Kiruhura/ Akatongole, Rwomuhoro, kinoni, Nyanza cell, Nyambanga, Kantan- irukwa-Nyarukika Ibanda ganya, Kitongole, Mbaba, Rwemirondo, Kazo Tc, Nyamambo TC and Village, Mitoma Kayanga, kashwa, Kiruhura Town, Nyakasharara,kachumbiro, Rwabon- yo water, Bugarihe, Mukula Village, Rwemikoma, Keihangara, Kyaba- ganda, St ann SS,Kihani, Rwenkuba, Rwenengo, rwengwe, Nyakiganda, Kayansheko, Mpasha TC Omukakona, Kyanika, Mabonwa, Mwamba, bwenda, Kigunga, Rukiri HC, Nyarukika

2 Soroti-Katakwi-Amuria Amuria/ Aten-oliana, Wera S/county, Adeki, Okwalo, Asumuk S/county and TC,

Katakwi Amuria TC, Amuria HC, Amuria District Hq, Wera TC, Amolo, Getom, Katakwi tech Institute, Katakwi Town, Katakwi HC and water pump

3 Ayer-Kamdini-Bobi Lira/Gulu Ayer TC, Agulurude, Aridi, Aye, Iyanyi, Loro TC, Loro PTC, Aboroneno, Odike Ayamapwono, Wirao, Atapara mission, Corner Atapara, Aber, Aber Ginery, Corner kamdini, Bobi, Bobi Minakulu, Minakulu TC, Ngutchati, Awe-Betty, Apwore-cero, Amiromir, Amwa, Aban, Aleny

ANNEX III PROJECTS UNDER PROCUREMENT

Project Name District 1 Kaddugala – Lyamanyonyi; Rutunguru - Rweibango, Kabumba, Nyabihoko Masaka and Ntungamo 2 Katuugo – - Ngoma Nakaseke

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 45 Rural Electrification Agency Ministry of Energy and Mineral Development ANNEX IV PLANNED PROJECTS

A. Packaged for implementation through the Norwegian Government Name District Status Lira - Adwari- Abim- Abim -Kotido Lira/kotido Norwegian Embassy still 1 and environs working on the framework agreement for financing 2 Parak Mission-Awere and environs Gulu over the next 5 years. 3 Gulu-Adjumani-Moyo and environs Gulu/Moyo/ Adjumani/ Amuru Financing agreement ex- pected to be signed in July 4 Mubende-Kyenjojo and Environs Mubende/ Kyenjojo 2011. Tender documents 5 Kabale-Kisoro Kisoro/ Kabale submitted to the Embassy for a No objection Rakai-Ssembabule Rakai/ Ssembabule/Isingiro 6

B. Packaged for implementation through KfW / Government of Germany

Name District Status Nebbi- Nyaruvur – Packwach with Nebbi Consultancy Contract 1 tee-off to Panyimur and Parombo signed on 07/03/2011 Line route & Engineering 2 Nyagak-Zombo-Zeu-Warr-Vurra Zombo Design in progress to be Arua-Maracha -Koboko-Yumbe Arua/Maracha/ Koboko/Yumbe completed by August 2011 3

C. Packaged for implementation through the Arab Bank for Economic Development in Africa (BADEA) and Saudi Fund for Development (SFD)

Name District Status

1 Kapchorwa-Bukwo-Suam Kapchorwa EOI for consultants under preparation to be adver- 2 Mayuge-Bwondha Landing Site Mayuge tised in July 2011. 3 Kasambira-Bugulumbya-Bukuutu Kamuli 4 Mityana-Lusalira Mityana 5 Lake Victoria free Trade Zone Rakai, Masaka 6 Apac – Chegere - Alemi Apac 7 Hoima - Nalweyo Hoima 8 Kitgum – Namokora / Padipe Kitgum

D. Packaged for implementation through the Government of Japan under JICA III

Name District Status Mayuge-Namayingo, Lumino-Na- Mayuge, Bugiri, JICA consultant on ground carrying out engineering maingo, Namaingo- Bumeru Busia, Namaingo, surveys, Socio Economic and Environmental assess- Landing site, with tee-offs to Iganga ments. These will be completed in July 2011. No finan- 1 Makuutu S/C, Lugala Landing site, cial commitment yet. Mwembe-Tayari TC and Mundidi TC

E. Packaged for implementation under World Bank/IDA Through ERT II

Name District Status

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 46 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development

Opeta-Achokora and Iceme Otwal Lira/ Apac Procurement of Consultancy services is awaiting guid- ance from WB on the Terms of Reference in the RfP 1 The WB issued a “No-objection” for Terms of Reference for EA/RAP consultancy services Masindi/Hoima-Waki small hydro Masindi/Bullisa Engineering & Design and Construction Supervi- including Buliisa sion Contract was sent to the Solicitor General for 2 clearance. The WB issued a “No-objection” for Terms of Reference for EA/RAP consultancy services Gulu-Acholibur and Paicho-Pa- Gulu/ Pader Engineering & Design and Construction Supervision tiko-Palaro Contract was signed on 07 June 2011. 3 The WB issued a “No-objection” for Terms of Reference for EA/RAP consultancy services Kazo-Rwemikoma-Bulem- Kiruhura/Semba- Engineering & Design and Construction Supervi- be-Rukunyu including bule sion Contract was sent to the Solicitor General for 4 Rushere-Mugole-Kijuma clearance. The WB issued a “No-objection” for Terms of Reference for EA/RAP consultancy services Ruhiira Millenium Village Isingiro/Mbarara Engineering & Design and Construction Supervision Contract was signed on 07 June 2011. 5 The WB issued a “No-objection” for Terms of Reference for EA/RAP consultancy services Ntenjeru-Bule-Mpenja Mukono The draft Engineering & Design Document has been reviewed; and the consultant has been given a go- 6 ahead to produce the final report. The WB issued a “No-objection” for Terms of Reference for EA/RAP consultancy services. F. Projects to be funded by Government of Uganda F.1 Proposed for financing through the Consolidated Fund

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 47 Rural Electrification Agency Ministry of Energy and Mineral Development

Name District Status

1 Survey and preparation of BoQs in progress awaiting Kisindi Masindi Farm Inouts (FICA) Masindi confirmation of finances.

2 National High Altitude Centre Kapchorwa

3 Kibugga Village & Trading Centre Mpigi

4 Nyakibobo, Itojo Sub-county Ntungamo

5 Katovu - Mudula Lwengo

6 Kalengero TC Lwengo

7 Nyabushabi - Muyumbu Kabale

8 Nsiika Area, Buhweju District Buhweju

9 Busiu TC Mbale Rukungiri Primary Teacher Train- 10 ing College Rukungiri

11 Buwuda TC Kamuli

12 Kafu TC & Kafu Farm Nakasongola

13 Maizimasa S/C and Doho Butaleja

14 Rokondwa Village Masindi

15 Muwafu TC Tororo

16 Nawangaiza TC Kamuli

17 Butansi TC Kamuli

18 Opanyi PS, Mierikiti TC Tororo

F.2 Proposed for financing through the Transmission Levy Name District Status

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 48 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development

1 Ogur TC Lira

2 Pongdwong TC Kitgum

3 Bunjojo TC Kabarole

4 Leo Atubo College, Ngeta Lira

5 Kikera Village Mpigi

6 Kalyowa P/S and Environs Luuka Kyampisi and Namengo - Oikos 7 Investments Ltd Mukono

8 Nyakatooke Village Kyenjojo

9 Maddox Secondary School Kyenjojo

10 Kabingo Parish Rukungiri

11 Kabakonyo TC & Environs Mityana

12 Bwizibwera - Biharwe Mbarara Garubanga - Mbaga, Mukiragiro 13 - Ibumba Rukungiri Rukararwe Appropriate Technol- 14 ogy Centre Bushenyi Katenga - Rubaare - Katooma - 15 Rwagashane (Kashenyi) Bushenyi

16 Nsotoka Village Kayunga

17 Buramizi Baracks Kanungu

18 Mpangango Kanungu Rubaya - Butanda & Kikubi TC, 19 Kabale Kabale Nakabango & Wanyange Landing 20 Site Jinja

21 Ziba Lubongo Namaseke, Buikwe Buikwe

22 Nyabuhikya, Ibanda Ibanda

23 Kitwe Farm, Ntungamo Ntungamo

24 Namakhale - Butiru Mbale Byakatimba Trading Centre - Mile 25 17 Isingiro Kedof Farm, Nangabo Makenke Survey and preparation of BoQs in progress awaiting 26 Hill, Gayaza Road Wakiso confirmation of finances.

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 49 Rural Electrification Agency Ministry of Energy and Mineral Development ANNEX V

UMEME Schemes implemented on cost-sharing Basis

VOLTAGE HV TX SIZE NO. SCHEME NAME LOCATION COST (UGX) LV (km) (kV) (km) (kVA) 1 AKALO SECONDARY SCHOOL APAC 70,168,529.00 33.00 0.20 1.00 100 2 KUBAMITWE VILLAGE LUWERO 80,128,299.00 11.00 1.30 2.10 200 3 BULOBA RESETTLEMENT SITE JINJA 89,988,703.00 33.00 0.14 2.00 50

4 MALINDI RESETTLEMENT SITE JINJA 71,177,175.00 33.00 0.14 1.00 50

KIKUBAMITWE RESETTLEMENT 5 JINJA 118,500,030.00 33.00 0.05 2.50 100 SITE 6 KYABIRWA RESETTLEMENT SITE JINJA 327,447,023.00 33.00 1.70 4.10 50x2 & 100 7 IVUNAMBA RESETTLEMENT SITE JINJA 203,897,108.00 33.00 0.52 2.15 50x3 8 NAMIZI RESETTLEMENT SITE JINJA 400,387,049.00 33.00 4.50 3.90 50x4 9 KIRA RESETTLEMENT SITE JINJA 123,199,663.00 33.00 0.14 1.88 50 NANKWANGA RESETTLEMENT 10 JINJA 210,119,860.00 33.00 0.03 1.50 50 SITE 11 BUJAGALI RESETTLEMENT SITE JINJA 69,707,252.00 33.00 0.04 1.50 50 PAYERO MILLERS COMPANY 12 GULU 51,360,057.00 11.00 0.08 0.04 315 LIMITED NAKASONGOLA DISTRICT FARM- NAKASON- 13 42,395,449.00 33.00 0.45 0.04 50 ERS ASSOCIATION GOLA NOMBE BUGARAMA KATINDA - 14 MBARARA 24,909,682.00 33.00 0.62 0.19 50 Additional Works

15 MBUZZI VILLAGE BUTEBE KABAROLE 232,397,092.00 11.00 1.50 3.45 50x2

16 KISOMORO TC AND HC KABAROLE 76,924,703.00 33.00 0.45 1.00 100

17 UCHUMI (U) LTD WAKISO 89,309,308.00 11.00 0.07 0.18 500

18 IGAMBIRO TC MITOOMA 82,371,199.00 33.00 0.40 3.00 50x2

19 CHAKIG INVESTMENTS LTD MUKONO 44,058,979.00 11.00 0.80 0.29 50

20 MBALE RESORT LTD MBALE 56,926,769.00 11.00 0.50 0.03 500

21 KAROKORA FARM BUSHENYI 208,889,851.00 33.00 4.00 0.94 50

22 TOMASI’S FARM IN BWESHARIRE KIRUHURA 225,686,587.00 33.00 4.10 0.60 50 & 100

23 KIYAGI / KITULA VILLAGE BUIKWE 125,836,016.00 11.00 1.80 1.66 50

24 KADEGELE VILLAGE IN PALLISA PALLISA 259,576,100.00 11.00 3.40 2.70 100

LYAN- 25 SALAAMA SHIELD COLLEGE 125,554,281.00 33.00 1.60 0.26 200 TONDE

26 HANHE (U) LTD NAKASEKE 82,648,826.00 33.00 0.23 0.02 500

Overall Total 3,493,565,590.00 29 38

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 50 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development ANNEX VI

UMEME Schemes Awaiting Funding on cost-sharing Basis

VOLTAGE HV LV TX SIZE NO. SCHEME NAME LOCATION COST (UGX) (kV) (km) (km) (kVA) KIYAGI / KITULA - Addi- 1 tional works BUIKWE 70,023,254.00 11.00 1.75 1.66 50 KALAMBI VILLAGE IN 2 BULOBA WAKISO 346,769,643.00 33.00 1.80 7.70 100x2

3 MATTE TRADING CENTER MITYANA 84,924,255.00 11.00 - 2.40 100 NAMIGANVU TRADING 4 CENTER MITYANA 69,204,986.00 11.00 - 2.50 50

5 NICE LIFE COMPANY LTD WAKISO 176,016,798.00 33.00 3.20 0.04 50 BUYAMBI PARISH - Addi- 6 tional MITYANA 65,763,508.00 11.00 - 1.80 50 KAVULE AND NAKABISO VILLAGES IN 100x2 & 7 KIRINGENTE MPIGI 368,596,394.00 33.00 4.20 6.70 50 HABITAT FOR HUMANITY 8 NANGABO WAKISO 31,159,824.00 11.00 0.13 0.30 50 KATEREZA VILLAGE IN 9 RUGANDO RWAMPARA MBARARA 557,624,104.00 33.00 5.00 6.10 50x2 KIKULULA LC I COMMU- 10 NITY BULAYI PARISH MASAKA 352,714,461.00 11.00 0.65 8.00 50100

11 VERDE - UGANDA TORORO 155,276,445.00 33.00 3.20 0.85 100 MUYENJE LC I - BUSIRO 12 COUNTY WAKISO 300,696,603.00 33.00 9.24 2.70 50x2

13 BALA TRADING CENTER KOLE 480,715,268.00 33.00 12.60 3.60 50 & 100 COLOMA PRIMARY 14 SCHOOL MBARARA 110,464,045.00 33.00 1.70 0.81 50 KANYOGOGA CATHOLIC 15 PARISH MITYANA 203,897,108.00

RUSHAKI SOUTHERN DIVISION OF KABALE - 16 NYAKAIKA VILLAGE KABALE 417,638,131.00 11.00 4.70 7.70 50x4 MZEE NYABONGO’S 17 RESIDENCE KABAROLE 6,382,649.12 0.42 - 0.33 0 KABEREBERE TO 50x6 & 18 NYAMUYANJA ISINGIRO 1,262,738,593.00 33.00 14.00 100x2 FAITH CHRISTIAN ACADE- 19 MY WOBULENZI LUWERO 40,757,949.00 11.00 0.17 1.05 50 ST. PAUL BIHARWE HIGH 20 SCHOOL MBARARA 55,359,249.00 11.00 0.07 1.10 50 KYANAMUKAKA PAR- 21 ENTS P/SCHOOL MASAKA 21,822,472.00 11.00 0.01 0.02 50 FAITH DAY AND BOARD- 22 ING P/SCHOOL SHEEMA 97,015,981.00 11.00 0.80 1.76 50

23 KIBINGO VILLAGE SHEEMA 320,560,328.00 11.00 1.40 6.80 50x2

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 51 Rural Electrification Agency Ministry of Energy and Mineral Development

MASHERUKA - RWEICU- 24 MU SHEEMA 565,472,490.00 11.00 4.60 8.00 50x5

25 PULAKA FAMILY HELPER MBALE 178,224,625.00 11.00 0.80 0.90 100 BUJJUKO VILLAGE IN 26 KYEBANDO WAKISO 123,174,710.00 11.00 0.65 3.80 100 BUSAALAMU TO WAIBUGA 27 LUUKA 325,395,350.00 33.00 5.00 2.30 200

28 NAMIREMBE - KIREMA NAKASEKE 55,359,249.00 11.00 0.07 1.00 50 KISIMBIRI LC I - KI- 29 KOOKIRO ZONE WAKISO 281,191,289.00 11.00 1.10 4.10 50x5 IHONDERO LC I - KAMWI- 30 RI PARISH IBANDA 290,577,513.00 33.00 3.50 3.50 50x6

31 LP INVESTMENTS LTD MUKONO 40,034,785.00 11.00 0.05 0.02 200 WORLD BRAIN RAYS 32 TRAINING CENTER WAKISO 315,054,214.08 11.00 3.50 2.90 100x2 WABINYONYI AND KIBEN- NAKASON- 33 GOS VILLAGE GOLA 503,887,261.00 33.00 5.82 3.70 50x2 50x2 & 34 BATUWA - BUKIMANAI MANAFA 427,659,387.00 11.00 4.50 5.40 100 BARAKA POULTRY 35 BREEDERS MBARARA 59,969,741.00 33.00 0.80 0.02 50 MR. BAGUMA ANGEL’S 36 FARM AT MBALALA MUKONO 23,799,735.00 11.00 0.08 0.03 50 NSAMBYA KYAKANYO- 37 MOZI IN KALISIZO RAKAI 291,063,896.00 11.00 2.70 4.60 50 & 100 SUNGIRA AND KABIRA 38 VILLAGES BOMBO 341,121,698.00 33.00 4.10 2.00 50x3 ST. JOHN NEPOMUK 39 PRIMARY SCHOOL BUIKWE 100,080,656.00 11.00 1.80 0.05 50

40 BUKANAGA VILLAGE MITYANA 253,727,950.66 11.00 4.50 4.90 50x3

41 BANAKIJJA VILLAGE MUKONO 717,057,232.00 11.00 7.50 8.50 50x6 BUSASA KYABARANGA 50x2 & 42 PARISH FORT PORTAL 366,755,152.00 33.00 5.20 2.50 100 GLOBAL INITIATIVE FOR 43 CAPACITY BUILDING MBARARA 98,331,360.00 33.00 0.15 2.00 50 KAKUNYU, NYAKABW- ERA, RYAMUHUNGA & 50x3 & 44 KIGIMBI MBARARA 822,664,412.00 11.00 3.00 16.00 100x2

45 KIBIRA ZONE, BUSABALA WAKISO 116,021,174.00 11.00 1.10 2.55 100 NYANGA AND KYAMA- 46 TONGO CELLS MBARARA 237,978,737.00 11.00 1.70 3.80 50x2 NAKIREBE LC - NANT- 47 WALA MPIGI 241,281,880.00 33.00 0.95 3.70 50x2 KIREMBE, RUBAARE, 48 KAKYELA 11 BUSHENYI 1,680,775,129.00 33.00 16.00 13.70 50x16 50x2, 100 49 LWANYONYI CELL MUKONO 396,590,784.00 33.00 2.10 5.10 & 200 MABALE, MUGUSU 50x3 & 50 VILLAGE FORT PORTAL 387,169,572.00 11.00 3.00 5.20 100x3

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 52 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development

MADUDU CATHOLIC 50 & 51 PARISH MUBENDE 592,035,274.00 33.00 7.90 5.90 100x2 MITOOMA, RWA- GASHANI, KATUNDA, 52 MUSHUNGU BUSHENYI 690,201,673.00 33.00 6.20 8.30 50x6 MAZIBA HEALTH CENTER 53 IV KABALE 36,652,315.00 33.00 1.80 0.03 50 MATALE, KALISIZO AND 54 KALANGALA VILLAGES MASAKA 174,192,797.00 11.00 1.00 2.30 100 NYAKATETE PARISH ON 55 ISHAKA - KITAGATA RD BUSHENYI 684,086,465.07 33.00 4.62 15.60 50

56 CALIFORNIA STAGE IGANGA 63,397,596.00 33.00 0.12 1.60 100

57 NAIBIRI TC IGANGA 67,530,413.00 33.00 0.04 1.30 100 NYAKAGONGO MITOOMA 58 KASHENSHERO MITOOMA 100,463,142.00 33.00 0.40 0.90 50 SCRIPTURE UNION OF 59 UGANDA AT WAKISO WAKISO 37,453,351.00 11.00 0.16 0.02 100 MASHERUKA - KA- 60 BUSIKYE, KABWOHE SHEEMA 178,657,630.00 11.00 1.20 2.50 50 MUKINGA NYAMUFUMU- RA KABWOHE - 61 ADDITIONS SHEEMA 531,473,755.00 11.00 2.80 10.00 50x2 KIBAZO P/SCHOOL AND 62 ENVIRONS MUKONO 59,688,252.00 11.00 0.03 0.99 50 GOLI GOLI IN KAGUMU 63 SUB-COUNTY KIBUKU 68,435,748.00 11.00 0.17 1.00 50 NYAKAHITA TC IN NYAK- 64 ISHARARA KIRUHURA 53,839,754.00 33.00 0.02 0.44 50 MANYAKABI AREA COP- 65 ERATIVE ENTERPRISE MBARARA 53,121,500.00 33.00 0.03 0.02 200

66 SERERE TOWN COUNCIL SERERE 107,300,992.00 11.00 - 1.40 100 KIGUMBA CENTRAL 67 PRIMARY SCHOOL MASINDI 72,688,194.00 33.00 0.06 0.85 100 MR. OPOLOT OSIBA’S 68 FARM IN KOBOLOI PALLISA 78,164,035.00 11.00 0.85 0.48 50

69 AWIO TC LIRA 64,429,149.00 33.00 0.06 0.95 100 IBANDA TC I AND II 70 VILLAGES KASESE 783,625,395.00 33.00 0.31 15.00 25 & 315 MAZIBA BALOOLE 71 VILLAGE MPIGI 127,656,099.00 33.00 0.60 1.44 50

Overall Total 19,461,635,559 177 245

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 53 Rural Electrification Agency Ministry of Energy and Mineral Development ANNEX VII

Surveyed Schemes

MEDIUM TOTAL LOW VOLTAGE TOTAL PROJECT NO. SCHEME NAME DISTRICT VOLTAGE VOLTAGE (kV) COST (UGX) (km) (km)

1 Busalamu TC to Kiroba Village Luuka 33 3.10 0.50 512,982,485.60

2 Bukendi Parish Luuka 11 3.25 2.00 635,162,364.20 Namukubenbe TC to Buwologo- ma 3 TC and Environs Luuka 33 5.10 1.40 772,812,326.00

4 Waibuga sub-county Luuka 33 5.00 0.60 595,820,019.60

5 Bukoova to Ikumbya Luuka 33 12.00 6.00 1,438,398,052.00 Luuka Town Council and 6 Environs Luuka 33 0.50 1.50 158,083,302.00

Kapchorwa Town, Porkland and Kapchor- 7 Boma ground wa 33 0.30 0.80 167,840,309.00 Kapchor- 8 Kapkwirok TC and Environs wa 33 0.95 0.30 215,371,759.20 Kapchor- 9 Chema TC to Taryet Stadium wa 33 15.70 4.85 2,207,742,464.20

Feel Free TC, Kobilu, Kapsukun- Kapchor- 10 yo to Chepkwatit to Nakawa TC wa 33 8.90 2.00 1,355,087,739.20

Ngaimbirir and Kamuke’s vil- Kapchor- 11 lage in Kaptanya sub-county wa 33 2.95 1.00 434,417,141.60

12 Ndalike TC Kamuli 11 3.70 0.58 436,911,885.80

13 Nakalanga and Lugoloire Kamuli 11 5.00 1.00 596,273,470.00

14 Nalinaiwe TC Jinja 11 4.30 0.50 530,513,344.40 Mulanda - Nawansega - 15 Bumpingu - Wairama Mbale 33 8.80 5.80 1,256,721,216.40 Namawanga - Wokukiri - Nan- girima 16 Water pump - Makunda Mbale 11 7.40 2.00 975,631,363.20 Butemu Village (Fruit Process- 17 ing Plant) Bugiri 33 0.50 0.20 204,916,628.80

Kanyumu - Buteba - Kasieba - 18 Akasim - Nyondo - Buwongwe Pallisa 11 30.00 10.00 2,577,120,000.00

Bumwangu - Bwirusa - Bub- 19 waya - Bumkoya Manafa 11 5.70 2.00 933,122,382.40

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 54 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development

Munarya TC - Kasukunyo Prima- ry School - Marine and Gamogo TCs - Gamatui to Tangwen and Kapchor- 20 Kitobo TCs wa 33 14.20 18.50 2,169,336,258.44

21 Arapai - Katine - Tuburu Soroti 11 57.50 15.00 4,975,967,724.00

Magola - Busegera - Bwayuya - Namutum- 22 Nakyele TCs ba 33 3.90 1.50 371,513,324.00

23 Jenima High School Kamuli 11 0.40 0.10 93,273,029.20

24 Kalebi’s Farm Balawoli Kamuli 33 2.80 0.10 282,261,829.20

25 Kanyale in Mutai Jinja 33 0.07 0.80 226,973,708.00

1 Bala TC and Environs Kole 33 12.60 1.00 1,346,555,631

2 Obok Olot Gulu 33 41.20 8.00 3,539,244,800

Lango Cultural Community at 3 Teboke Gulu 33 27.10 3.50 2,474,068,948

4 Ober TC Lira 33 0.05 0.55 108,321,876

5 Ober Parish Lira 33 0.50 0.60 147,563,130 Abdalla Anyuru Memorial College 6 and Environs Lira 33 1.10 0.15 177,549,455

7 Minakulu TC Oyam 33 0.50 1.10 206,369,634

8 Opong Village Gulu 33 2.30 0.80 312,676,140

1 Ntawo-Nyenje and Budugala Mukono 11 7.40 2.40 994,615,533.60 Kyenda - Kikoma - Katovu - Kyank- 2 Byerima wanzi 33 18.00 4.00 1,582,759,724.00 Kyank- 3 Katanabira - Kigando - Ntunda wanzi 33 20.00 5.00 1,754,567,724.00

4 Kidusu TC - Buwampa TC Buikwe 11 4.00 4.50 337,151,724.00

Ssesse TC - Buwagajjo landing 5 site to Namabu Health center Buikwe 11 4.00 1.30 380,103,724.00

6 Lugasa to Wasigalira Buikwe 11 0.90 1.65 551,911,724.00

Senyi & Nansagazi Fish Landing Sites 7 in Ssi Sub-county Buikwe South Buikwe 11 37.50 8.00 294,199,724.00

Buwoya TC - Najja - Makindu - 8 Bulega Buikwe 11 10.70 4.50 955,660,524.00

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 55 Rural Electrification Agency Ministry of Energy and Mineral Development

Kauku - Kiteza - Kasubi - Busa- 9 baga - Malalamasi Buikwe 11 18.70 6.00 1,642,892,524.00

Koba village - Kasokosoko - luwaya village - kabula - kikati 10 - Kizgo - Magwa Farm Buikwe 11 9.90 3.40 886,937,324.00

Najja TC - Gulama TC - Bujaaya 11 TC and Wankale TC Buikwe 11 5.50 4.80 731,980,927.60

12 Lutente - Birongo and Nabwato Kalungu 33 25.00 10.00 2,626,554,684.00

Nakason- 13 Migyera - Moone - Lwampanga gola 33 67.00 7.00 6,100,613,688.00

Nakason- 14 Wabinyonyi - Kalungi - Kalongo gola 33 39.00 5.80 3,640,569,181.60

Mr. Donar Masolo’s Farm - Nakason- 15 Kyampisi gola 33 2.20 1.40 290,110,386.80

16 Kyampisi - Namere Mukono 33 2.00 1.50 225,022,460.00

Bulera - Mtetema - Kiryokya - 17 Kyamusisi to Nalungi Parish Mityana 33 35.00 10.00 3,581,380,712.00 Rutunku Polytechnic and 18 Environs Masaka 33 17.60 9.30 1,712,505,444.00 Kateera - Mukati - Jokero - Mu- Kyank- 19 wanga TCs wanzi 33 9.50 9.00 1,211,264,994.18

Buyege - Bugogo - Buyiga - Bu- 20 lumbi in Kasanje sub-county Wakiso 33 14.50 17.25 1,482,384,888.00

1 Ibaare Kashekure Mitooma 33 0.03 0.40 166,764,514.80

2 Kaberebere to Nyamuyanja TCs Isingiro 33 15.00 5.00 1,288,560,000.00 Nyamunuka / Kyaruhunga to 3 Kahunga Ntungamo 33 12.00 2.20 1,030,848,000.00

4 Katinda - Nyakisa to Ihunga Ntungamo 33 3.00 1.00 257,712,000.00 Ruburankono Village, Gasiza 5 Parish Kisoro 33 2.00 1.50 291,976,958.00 Kyamate - Nyakashozi - Kabin- 6 go Ntungamo 33 2.00 2.20 401,732,663.80

7 Kanyamugamba - Ngoma Ntungamo 33 3.20 2.40 435,831,029.40

Masaka - Kagando - Kyambula 8 Villages Kasese 33 0.50 2.90 195,176,802.60

9 Bushenyi - Nyamiko - Mazinga Bushenyi 33 3.00 4.00 444,050,048.00 Bundib- 10 Nyahuka to Busunga ugyo 33 10.00 5.00 1,607,056,750.00 Kamwenge Secondary and Vocational 11 School and Environs Kamwenge 33 1.50 0.60 213,430,773.66

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 56 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development

Buseruka dam - Tonya and Kasi- 12 so Oil well areas and Environs Hoima 33 26.00 0.10 2,238,746,905.20 Buseruka TC - Kolin Construc- tion camp - Kabaale TC and 13 Environs Hoima 33 22.00 3.10 2,033,715,533.20

14 Rwengogo Village Kabale 33 0.80 0.70 105,210,924.00

15 Kisiizi Hospital and Environs Kabale 33 0.50 1.10 36,487,724.00

16 Kabale Polytechnic School Kabale 33 1.00 3.00 256,300,720.00

Ndego UWA site and Ruhiija 17 Trading center Kabale 33 25.00 8.00 2,184,087,724.00

18 Kamasasa Village Kasese 33 1.50 2.04 231,238,287.00

Mukunyu - Kanyampara - Mailo Kumi 19 Kasese 33 2.43 8.10 631,263,685.50

20 Maliba - Kyanya Kasese 33 2.40 6.10 498,688,331.40

21 Kisinga - Kajwenge TCs Kasese 33 2.95 13.80 756,592,004.70

22 Kitswamba Kasese 33 4.00 8.60 543,787,372.50

23 Kyabarungira Kasese 33 10.00 14.00 1,161,624,202.00

24 Nyakiyumbu Kasese 33 7.00 10.00 808,288,443.76

Overall Total 794 317 81,238,962,754

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 57 Rural Electrification Agency Ministry of Energy and Mineral Development ANNEX IV

Map of Uganda showing the proposed Service Territories

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 58 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development

Hon. Maria Kiwanuka, Minister of Finance , planning and economic development , H.E Yousef Ibrahim, Vice chairman and managing director of the saudi Fund for dvelopment and Hon. Irene Muloni, Minister for Energy and Mineral Development signing a loan a

REA in FY 2011/12 in Pictures

Hon Peter Lokeris, RDCs of Soroti and Katakwi and REA staff on a radio talk show at Etop radio

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 5959 Rural Electrification Agency Ministry of Energy and Mineral Development

Eng. Werikhe speaking at the Energia meeting at Imperial Royale Hotel Kampala.

REA in FY 2011/12 in Pictures

Katrin Lervik and Ms Patricia Litho in Myanzi at one of the Norad Funded projects and looking on are the Ferdsult Engineering contractors

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 6060 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development

CP&RE, Patricia Litho speaking to one of the participants at the Joint sector review exhibition

REA in FY 2011/12 in Pictures

A sensitisation meeting in Rakai

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link 6161 Rural Electrification Agency Ministry of Energy and Mineral Development NOTES

REF:......

DATE:......

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 62 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 The peoples electricity link Rural Electrification Agency Ministry of Energy and Mineral Development

RURAL ELECTRIFICATION AGENCY

MINISTRY OF ENERGY AND MINERAL DEVELOPMENT

R U Y R C Plot 10, Winsor Loop-Kololo 2nd Floor, House of Hope A N L E G EL A CT N P.O. Box 7317 Kampala Uganda : +256 312 264 095 RIFICATIO Tel Fax: +256 414 346 013 Email: [email protected] www.rea.or.ug

ANNUAL RURAL ELECTRIFICATION REPORT 2011/12 64 The peoples electricity link