DeliveringStrategies CentralTransportStudy

ReportforSouthRibbleBoroughCouncil&Partners

InAssociationWithGVAGrimley

October2008

DocumentControl

ProjectTitle: SouthRibble,&ChorleyTransportStudy

MVAProjectNumber: C3706100

DocumentType: Report

Directory&FileName: M:\Tet\C37061_SouthRibble_Preston_Chorley\Reports\Final Report\CentralLancashireTransportStudyFinalReport.Doc

DocumentApproval

PrimaryAuthor: LorraineBroadhurst

OtherAuthor(s): JoeCharlesworth

Reviewer(s): DominicMullen

Formattedby: LeticiaRodriguez

Distribution

Issue Date Distribution Comments

1 27/06/2008 DraftReportIssuedtoClient

2 17/10/2008 FinalReportIssuedtoClient

Contents

1 StudyBackground 1.1 1.1 Introduction 1.1 1.2 StudyArea 1.1 1.3 StudyObjectives 1.1 1.4 TasksUndertaken 1.1 1.5 TheReportStructure 1.2

2 PolicyContext 2.1 2.1 Introduction 2.1 2.2 DraftNorthWestRegionalSpatialStrategy(RSS) 2.1 2.3 NorthWestRegionalEconomicStrategy 2.2 2.4 CentralLancashireLocalDevelopmentFramework(LDF)CoreStrategy 2.3 2.5 LancashireSecondLocalTransportPlan(LTP2) 2.4 2.6 TheReplacementJointLancashireStructurePlan2001–2016 2.5 2.7 DraftPrestonandSouthRibble2028TransportStrategy 2.6 2.8 CentralLancashire,GrowthPointBid 2.7 2.9 Summary 2.8

3 BaselineReviews 3.1 3.1 Introduction 3.1 3.2 SocioeconomicReview 3.1 3.3 TraveltoWork 3.2 3.4 PublicTransportServices 3.5 3.5 Cycling&PedestrianReview 3.7 3.6 RoadNetworkReview 3.9 3.7 CarParkingReview 3.12

4 DevelopmentSites 4.1 4.1 Introduction 4.1 4.2 PENELOPE 4.1 4.3 LimitationsofPENELOPE 4.2 4.4 BaselineTrafficConditions–HighwayStressMaps(2007) 4.3 4.5 FutureTrafficGrowthwithnoDevelopmentScenario(2018and2028) 4.4 4.6 DevelopmentScenario2018 4.5 4.7 DevelopmentScenario2028 4.7 4.8 SummaryofOutputs 4.9 4.9 SummaryofIssuesonKeyCorridors 4.10 4.10 ModalShift 4.14 4.11 Modalshiftawayfromcartravel 4.18 4.12 BuckshawVillage 4.20

5 TransportStrategy 5.1 5.1 Introduction 5.1

CentralLancashireTransportStudy 1 Contents

5.2 TransportVision 5.1 5.3 ProblemsandIssues 5.1 5.4 ThePackageofMeasures 5.3 5.5 RailImprovements 5.3 5.6 PotentialNewRailStations 5.7 5.7 LocalBusServices 5.8 5.8 PotentialPark&RideSites 5.13 5.9 PotentialHighwayImprovements 5.13 5.10 WalkingandCycling 5.14 5.11 TravelPlans 5.15 5.12 DemandManagementMeasures 5.16 5.13 Freight 5.17 5.14 Summary 5.17

6 Implementation 6.1 6.1 Introduction 6.1 6.2 Costing 6.1 6.3 DeliveryMechanisms 6.4 6.4 Public&StakeholderConsultation 6.5

7 Funding 7.1 7.1 Introduction 7.1 7.2 MainstreamPublicSectorFundingSources 7.1 7.3 CurrentPrivateSectorFundingMechanisms 7.2 7.4 AlternativeFundingSources 7.5

8 Recommendations&FurtherWork 8.1 8.1 SummaryofFindings 8.1 8.2 DevelopmentofaTransportModel 8.1 8.3 FurtherInvestigations 8.2

Tables

Table3.1JourneytoworkmodalchoiceResidentpopulation(Census2001) 3.2 Table3.2TraveltoworkData(Census2001) 3.4 Table3.3RailStationfacilities 3.7 Table3.4National&RegionalCycleRoutes 3.8 Table3.5:MotorwaysinStudyArea 3.10 Table4.1Highwaycapacity 4.3 Table4.2TEMPROfactors(baseyear2007) 4.5 Table4.3DevelopmentSites–2018Scenario 4.6 Table4.4DevelopmentScenario–2028 4.8 Table4.5Modalshift 4.14 Table4.6Summaryof2018traffic 4.17 Table4.7EstimatedModalSplitsforBuckshawVillage(basedonCensus2001) 4.20

CentralLancashireTransportStudy 2 Contents

Table5.1RailStations–SuggestionsforImprovement 5.5 Table5.2HighQualityPublicTransportRoutes–LikelyTransportIssuesArisingfrom FutureTrafficGrowthandDevelopments 5.8 Table5.3SummaryofSchemeSuggestions 5.18 Table6.1PreliminarySchemeCostings 6.1

Figures

Figure4.1Locationoftrafficsurveys 4.16

Appendices

A BaselineTrafficConditions

B TrafficGrowthwithNoDevelopmentScenario

C DevelopmentScenarios

D FutureTrafficGrowthwithDevelopmentScenarios

E ModalSplitEstimates

F ExistingHighFrequencyBusServices

G ProposedCoreStrategicBusNetwork

H ProposedCentralLancashireCycleNetwork

CentralLancashireTransportStudy 3 Summary

MVA was commissioned by South Ribble Borough Council and its partners to develop a transport strategy capable of delivering an efficient transport network, which would accommodate future travel demands generated by the new development throughout the area.Moderndayactivitiesgeneratesubstantialdemandsforthemovementofbothpeople andgoodsandthusinordertodeliveranefficienttransportnetworkcapableofsupporting theproposeddevelopmentofthe‘cityregion’,itwasrecognisedthatacrossboundarystudy wouldberequired,incorporatingthefollowingdistricts:

 Chorley;

 Preston;and

 SouthRibble.

The objectives of the study as outlined in the brief and agreed at the inception meeting were:

 To outline proposals for future development of a public transport network that will provideforforecastfuturetravelarrangements;

 Toidentifyproposalsforthedevelopmentofacycleandwalkingnetworkandother measurestodeliveranincreaseinactivetravel;

 Toreviewroadcapacitytoidentifyanyforecastpressureson thetransportnetwork that cannot be dealt with through increased use of public transport, cycling and walkingandtorecommendappropriatemeasurestoimprovecapacity;

 ToprovideinputintotheLDFInfrastructurePlanandCommunityInfrastructureLevy; and

 To provide costings for proposed measures and possible funding measures, with deliverydatesandphasing.

Tasksundertakenthroughoutthecourseofthestudyincluded:  Baselinereviewsofthecurrenttransportnetworks;

 Consultationswithrelevantparties;

 Identificationofkeydevelopmentsites;

 Developmentofemergingtransportschemesforfurtherconsideration;

 Preliminarycostingofemergingtransportschemes;and

 Implementationincludingdeliveryandfundingmechanisms.

Problems & Issues

Theworkidentifiedanumberofproblemsandissuesthatthefuturetransportstrategyfor Central Lancashire will need to address, the main ones being outlined in the following paragraphs.

CentralLancashireTransportStudy i Summary

InSouthRibbleandChorley,carownershiplevelsarehigherindicatingahigherdependence on the car for journeys to work and other tips. Whilst car ownership is not necessary a problem in its self, dependency onthe car can be a major contributor to congestion and placesincreasedpressureforresidential,workplaceandtown/citycentreparking.

Thestudyareaiswellservedbyanumberofprincipleroadsmakingdrivingofteneasierand moreattractivethanalternativemodesandthisisalsofurthercompoundedwithoutoftown developmentsthatareofteneasiertoaccessbycar.Someoftheseroadsalsoformbarriers to communities, pedestrians and cyclists giving rise to severance. For instance Bamber BridgefeelsdisconnectedfromtherestoftheBoroughasitisboundedbythemotorwayand theA6.

TheapproachroutesintoPrestonarealreadyexperiencinghighwaycapacityproblemsduring peakperiodsparticularlyatpinchpointssuchasriver crossings and this is forecast to get worse(Table4.6).InChorleyandSouthRibble,congestiontendstobemorelocalisedandis oftenconfinedtospecificjunctionse.g.ChorleyHospital,TardyGate.Congestioncanhavea negativeimpactonthelocaleconomyasitaffectsthereliabilityofemployeesbeingableto gettoworkontime,onretailasshoppersmaydecidetogotoalternativeretailcentresthat areeasiertoaccess,andcongestioncanalsohaveanegativeimpactofthedeliveryofgoods andservices.

Apatternofdevelopmentthattendstofocusondevelopinglandaroundmotorwayjunctions placesincreasedpressureonthestrategictrunkroadnetwork.TheM6betweenBroughton and junction 31 is nearing capacity during peak periods and therefore any future developmentswillneedtoincorporatemitigationmeasuresinordertominimisetheimpact onthestrategicroadnetwork.

Prestonhasawelldevelopednetworkoflocalbusesservicesandsomeofthesehavebeen improvedthroughaprogramofqualitybuspartnerships,andDfTKickstartfundingenabled the introduction of the Orbit services. In general, the existing bus network has been developedtoservethelocalmarketofPreston,thoughtherearesomeinterurbanservices, whicharegenerallyprovidedbyadifferentoperator.

In Chorley, DfT funding has also enabled the introduction of Network Chorley whilst the networkhasseenincreasesinpatronageitisunlikelythatthenetworkwillbecommercially viablebytheendoftheDfTfundingperiod.Therefore,the exitstrategy will involve some continued financial support from Lancashire County Council in conjunction with a network reviewtoensurethatservicesareoperatingwithinfinancialconstraints.

SouthRibbledoesnothaveitsownlocalbusnetworkasalltheserviceswiththeexception of the South Ribble Flexibus pass throughSouth Ribble either on their way to Preston or Chorley.Inaddition,theeastwestconnectionsbypublictransportwithintheboroughtend tobepoor.

There are no network or joint ticketing initiatives currently in operation within the study area,notevenonservicesoperatedbymorethanoneoperator e.g.Service109 operated via Buckshaw. The north south bus routes between the main urban areas are fairly well established but these are often not the most direct of routes and journey times when comparedtocartripsarenotattractive.

CentralLancashireTransportStudy ii Summary

Rail stations suffer from a variety of access issues that range from the lack of parking provision through to poor pedestrian and cycling links between the town/city centres and major employment areas e.g. Bamber Bridge, UCLAN. There are also capacity issues on services to and the timings between Transpennine and Northern Rail services wouldbenefitfromreviewinginordertoprovideamoreattractiveoffer,assometimesthere isonly5minutesbetweensuccessiveservices.

Cyclingandwalkingwilloffermorebenefitsforshorterjourneysbutifwalkingandcyclingis to be encourage, then the supporting infrastructure needs to reflect this. This will involve makingurbancentresandresidentialstreetsmoreattractiveforwalkingandcycling.Cyclists and pedestrians natural desire lines are often constrained by the orientation of the road networkwhichcreatesbarrierstosuchmovements.

Withinthestudyarea,tripsbycarhavecontinuedtohavetheadvantagetosuchanextent thatothermodesoftransporthavebecomerelativelylessattractivebycomparison.Ifthe imbalanceistobereaddressedthenradicalimprovements to infrastructure, improvements to transport services complemented by a mix of incentives and disincentives, need to be implemented to ensure that the existing congestion issues due not increase and that the residents of Central Lancashire are able to access a range of complimentary transport alternativesandmakeinformedchoicesabouthowtheychoosetotravel.

Proposed Package of Measures

Thefuturetraveldemandsoftheareacanonlybesatisfiedbytheintroductionofapackage of measures and it is not intended to introduce measures aimed at disadvantaging the motoristsasthecarisanintegralcomponentofmoderndaysociety.However,theprovision of increased highway capacity tends to only deliver shortterm gains and can actually generate substantial disadvantages for other modes of transport. Therefore the transport strategy for Central Lancashire proposes a comprehensive package of measures, which considers all modes of transport and aims to provide interventions appropriate to the respectiveareasandtheassociateddemandsfortravel.Themeasuresidentifiedinclude:

 Publictransportimprovements;

 Highwayimprovements;

 Cyclingandpedestrianmeasures;

 TravelPlanmeasures;

 Demandmanagementmeasures;and

 Assistanceforthemovementoffreight.

Thestrategyhasbeendesignedtoprovideamixofshort,mediumandlongtermmeasures toensureongoingpublicandpoliticalsupport.Themeasuresalsoneedtoconsiderfuture traveldemandslikelytobegeneratedfromnewdevelopmentsandtheplannedphasingof newinfrastructure.Therefore,thestrategyhasconsideredthefollowingtimeperiods:

 Shortterm–between2008and2013;

 Mediumterm–between2013and2018;and

 Longterm–between2018and2028.

CentralLancashireTransportStudy iii Summary

Themeasuresproposedneedtobecomplimentaryanddeliveredinaholisticmannersoas nottopromotecompetitionbetweendifferentmodese.g.railandbus.

Themeasuresoutlinedbelowareinitialschemesuggestionsforfurtherconsiderationandare notfinaliseddetailedschemedesigns.

Implementation

Wehaveestimatedtheinitialcostsintheshort,mediumandlongtermtobe:

 ShortTerm(20082013)£59.5million;

 MediumTerm(20132018)£86.6million;and

 LongTerm(2018–2028)£110.5million.

Inordertosuccessfullydelivertheproposedinitialtransportschemesasignificantamountof investmentwillberequired.Possiblefundingmechanismsarelikelytoinclude:

 Mainstreampublicsectorfundingsources;

 Currentprivatesectorfundingsources;and

 Alternativefundingsources.

Inordertodelivertheproposedschemesthefollowingwillbenecessary:

 Sufficientstaffresources;

 Politicalsupport;and

 Publicsupport.

Therefore it is recommended that a project manager is appointed to drive forward the finalisedschemesandstrategiesforCentralLancashire

Recommendations & Further Work

Ifnointerventionistakenthentrafficlevelswillcontinuetogrowandtheexistingcongestion problemsaroundPrestonwillcontinuetogetworse.

Given the considerable advantage thatthe caralready has the profiles of public transport servicesandothermodesneedstoberaisedrequiringastepchangeinthelocaltransport networks.

The schemes presented in this reportareemerging schemes forfurther consideration and are not detailed finalised schemes and will need to be investigated further if a robust business case is to be produced. However, in order to undertake the required level of analyseswhich willbe requiredtofully evaluate potential interventions and the impact of future traffic movements, then it will be necessary to develop a multimodal land use transportmodel.Theutilisationofsuchatoolwillalsobeessentialinordertoproducethe requiredevidencetosupportanybidsformajorfundingfromcentralgovernment.

CentralLancashireTransportStudy iv 1 StudyBackground

1.11.11.1 Introduction

1.1.1 MVAwascommissionedbySouthRibbleBoroughCouncilandthefollowingpartnerstoundertake atransportstudy:

 ChorleyBoroughCouncil;

 LancashireCountyCouncil;and

 PrestonCityCouncil.

1.21.21.2 Study Area

1.2.1 Forthepurposesofthisstudytheareaincorporatedthedistrictsof:

 Chorley;

 Preston;and

 SouthRibble.

1.2.2 TheareaiscollectivelyknownasCentralLancashire

1.31.31.3 Study Objectives

1.3.1 Theobjectivesofthestudyasoutlinedinthebriefandagreedatinceptionwere:

 To outline proposals for future development of a public transport network that will provideforforecastfuturetravelarrangements;

 Toidentifyproposalsforthedevelopmentofacycleandwalkingnetworkandother measurestodeliveranincreaseinactivetravel;

 Toreviewroadcapacitytoidentifyanyforecastpressureson thetransportnetwork that cannot be dealt with through increased use of public transport, cycling and walkingandtorecommendappropriatemeasurestoimprovecapacity;

 ToprovideinputintotheLDFInfrastructurePlanandCommunityInfrastructureLevy; and

 To provide costings for proposed measures and possible funding measures, with deliverydatesandphasing.

1.41.41.4 Tasks Undertaken

1.4.1 AdetailedmethodologyhasbeendescribedintheInceptionReport.Belowisasummaryofthe keytasksthathavebeenundertakenduringthecourseofthisstudy:

 Baselinereviewsofthecurrentsituation;

 Consultations;

CentralLancashireTransportStudy 1.1 1 Study Background

 Reviewofkeydevelopmentsites;

 Developmentofemergingtransportschemesforfurtherconsideration;

 Preliminarycostingofemergingtransportschemes;and

 Implementationincludingdeliveryandfundingmechanisms.

1.51.51.5 The Report Structure

1.5.1 Followingonfromtheintroduction,thereportisstructuredasfollows:

 Chapter2PolicyContext;

 Chapter3BaselineReviews;

 Chapter4DevelopmentSites;

 Chapter5TransportStrategy;

 Chapter6Implementation;

 Chapter7Funding;and

 Chapter8Recommendations&FurtherWork.

CentralLancashireTransportStudy 1.2 2 PolicyContext

2.12.12.1 Introduction

2.1.1 This section of the report provides an overview ofthe key regional and local policy documents withtransportimplicationsrelevanttothePreston,SouthRibbleandChorleystudyarea.

2.1.2 Thefollowingpolicydocumentsaresummarised:

 DraftNorthWestRegionalSpatialStrategy(RSS);

 NorthWestRegionalEconomicStrategy;

 CentralLancashireLocalDevelopmentFramework(LDF)CoreStrategy;

 LancashireLocalTransportPlan(LTP);

 JointLancashireStructurePlan;

 DraftPrestonandSouthRibble‘2028’TransportStrategy.

2.1.3 Whereapplicable,policiesandmeasuresspecificallyrelatingtoPreston,SouthRibbleandChorley areoutlined.

2.22.22.2 Draft North West Regional Spatial Strategy (RSS)

2.2.1 The Regional Spatial Strategy (RSS) for the North West of England provides the overarching frameworkfortheplanninganddevelopmentoftheregionforthenext15to20years.TheRSS itself forms part of each local authority’s development plan and feeds directly into the Local Development Framework’s (see subsequent section). Clearly spatial planning is closely interconnected with transport with the location of houses, places of employment, leisure and retailfacilitiesinfluencinghowpeopletravel.

2.2.2 TheRegionalTransportStrategy(RTS)isalsoincorporatedwithintheRSSandaimsto:

 Support economic growth and business competitiveness through the introduction of a rangeofmeasurestotacklecongestion;

 Supportregenerationandreducesocialinclusionthroughthedevelopmentofintegrated transportnetworksandenhancingaccesstokeyemploymentlocations;

 Improvepublicrealmthroughtheintroductionofarangeofmeasurestomanagetravel demand;

 Reduce the wider impacts of road transport through the development of a structured frameworkformanagingandimprovingtheregion’shighwaynetwork;and

 Set a framework for a high quality integrated public transport network and safe and attractiveroutesforcyclingandwalking.

2.2.3 AkeyaspectoftheRSS,andonewhichisreflectedin mostnational, regional and local policy documents, is the policy of encouraging major new developments to be located in the most accessibleurbancentresintheregion.Thispatternofdevelopment,togetherwithmeasuresto improvepublictransportprovisionandtomanagethedemandforcaruse,canhelptoencourage

CentralLancashireTransportStudy 2.1 2 Policy Context

sustainabletravelmodesinpreferencetotheprivatecarandalsotoreducetheneedtotravelin general.

2.2.4 The RSS provides indicative volumes and locations of land to be used for development for employment, housing, retail and other landuses. Development should be located following a sequentialapproachwherebypreviouslyusedlandisprioritisedfordevelopment,followedbythe useofinfillwithinexistingsettlementsandfinallythedevelopmentofotherlandwhereitiswell connectedtorelevantservicesandinfrastructure.

2.2.5 TheRSSsetsoutalocationstrategyfordevelopmentsofmajorsignificance,knownas‘Regional InvestmentSites’(RIS)and‘KnowledgeNucleiSites’(KNS).WithintheCentralLancashirestudy area,NorthWestChorleyandNorthofLeyland/BamberBridgeareidentifiedasbroadlocations fortheRIS’swhileCentralPrestonissetasidetobeaKNS.

2.2.6 Regionalcarparkingstandardsareoutlinedwithinthedocument,althoughthesehavesincebeen furtherdeveloped bytheNorth WestRegional Assembly in a report produced with consultants Mouchel.TheMouchelreport,publishedinearly2008,advancestheparkingstandardsfornew developments and attempts to make standards more flexible in order to account for the accessibilityofagivenlocation.

2.2.7 Part4ofthedocumentoutlinessubregionalpolicyframeworks,includingtheCentralLancashire CityRegion.Withinthisregion,keyeconomicgrowthshouldbefocusedonBlackpool,, andPreston.IndeedthewiderPrestonareaisseenashavingthegreatestpotentialfor growth,dueinparttoitslocationonmajorNorthSouthandEastWestcommunicationroutes. TheproposedplansandstrategiesintheCentralLancashireCityRegionwill:

 Improvetheinternalandexternaltransportlinks;

 Develop the role of Preston as the City Region’s transport ‘gateway’ and key public transportinterchange;

 Improvetheaccessibilityofkeyemploymentlocations;

 Improve road safety, manage traffic growth and maintain a highquality environment throughmitigatingtheimpactsofroadtrafficonairquality,noiseandhealth.

2.32.32.3 North West Regional Economic Strategy

2.3.1 The North West Regional Development Agency (NWDA) led the development of the Regional Economic Strategy (RES) for the region, which has the overall objective of continuing the transformationoftheregionaleconomywhichbeganin2000.Alsoattheheartofthestrategyis theaimofachievingdevelopmentinasustainableway.

2.3.2 Threemajordriversforthegrowthoftheregionareidentifiedasbeing:

 Improvingproductivityandgrowthofthemarket;

 Growingthesizeandcapabilityoftheworkforce;and

 Maintainingconditionsforsustainablegrowth.

CentralLancashireTransportStudy 2.2 2 Policy Context

2.3.3 PartofthevisionfortheRESidentifiesPreston,togetherwithManchesterand,asbeing akeydriverofcityregionalgrowth.

2.3.4 Transport is also identified as having a key role in maintaining and developing conditions for sustainable growth. The growth objectives are likely to be inhibited by worsening traffic and congestionontheregion’shighwaynetwork.

2.3.5 TheLancashire subregion,of whichPreston,SouthRibble and Chorleyforms a part, is said to havebeencharacterisedbysteadygrowthinemploymentinrecentyears.Itisalsonotedthat therehavebeensignificantdifferencesingrowthratesbetweenpartsofEastLancashireandthe more dynamic area around Preston. Again, Preston is noted as being a key location for knowledgebasedemployment,withfastgrowthinhightech,ICTandnewmediaoccupations.

2.42.42.4 Central Lancashire Local Development Framework (LDF) Core Strategy

2.4.1 ThethreeCouncilsofPreston,SouthRibbleandChorley,underthetitle‘CentralLancashire’are working together on the Core Strategy of the Local Development Framework (LDF). An LDF consists ofa ‘folder’ of DevelopmentPlanDocuments (DPD) that outlines the spatial planning strategyforthelocalarea.TheCoreStrategydocumentisoneoftherequireddocumentsinthe LDF.

2.4.2 TheCoreStrategyshouldplayakeypartinsettingoutanarea’sspatialaspectsandprovidinga longterm spatial vision for the area. Core Strategies should outline a Council’s strategy for deliveringstrategicdevelopmentneeds,includingforhousing,leisureandretail.ACoreStrategy shouldonlyindicatebroadlocationsforlanduse,which will be taken forwardin more detail in otherdevelopmentplandocuments.

2.4.3 The First Issues and Options Paper fortheCentralLancashireCoreStrategywaspublishedfor consultationinNovember2006,withtheconsultation period running until the following March. ThisdocumentmarkedthebeginningoftheconsultationontheCoreStrategyandfocussedona range of key ‘themes’, including ‘Locating New Development’, ‘Meeting Housing Needs’ and ‘Improving Accessibility’. The responses from this consultation showed that further work was requiredinordertodeveloppossibleoptionsforthedevelopmentofthearea.

2.4.4 The Second Issues and Options Paper progressestheCoreStrategyanddiscussesthespatial issuesthataffectthedifferent‘communities’withintheregion.Thereportalsoincludesanoutline of existing travel patterns between the communities of Central Lancashire. The importance of Preston City in terms of employment for residents of South Ribble and, to a lesser extent, Chorleyisshownwithinthe2001CensusTraveltoWorkpatterns.

2.4.5 The document culminates in the presentation of three potential ‘spatial options’ for the area, whichareoutlinedbelowtogetherwithabriefsummaryoftheprinciplesbehindthem:

 Focus growth in Preston City and the other main urban areas – development locatedinmainurbanareasthatarebetterservedbypublictransportlinksandthisoption also reduces the requirement for Greenfield land. This option, in general, appears to be morecloselyrelatedtonationalandotherregionalpolicies;

 Target growth to a few priority urban locations but protect suburban areas – investment in largest urban areas and in locations with the best growth potential.

CentralLancashireTransportStudy 2.3 2 Policy Context

DevelopmentwillalsoberequiredonsignificantareasofGreenfieldlandasitisproposed suburbanareaswillbe‘protected’fromdevelopment;and

 Spread growth between all the main urban areas and identified rural service centres –growthandprovisionofservicesalsotargetedin certain‘ruralcentres’which maybetterservelocalcommunities.

2.4.6 Thedocumentsummarisesthepotentialoutcomesofeachoftheoptionsforthedifferentareas ofCentralLancashireandalsodiscussesthepossiblesocial,environmentalandeconomicimpacts oftheoptions.

2.4.7 Thedocumentpresentsabalancedargumentforandagainsteachoptionanddoesnotattempt toexpressafavouriteoption.Itconcludesbyopeningafurtherconsultationexerciseonthethree options.

2.52.52.5 Lancashire Second Local Transport Plan (LTP2)

2.5.1 Lancashire County Council submitted its second Local Transport Plan (LTP2) covering their transport plans for theperiod between2006 and 2011. The Plan has the following seven key objectives:

 Reduceroadcasualties;

 Improveaccesstojobsandservices;

 Improveairquality;

 Improvetheconditionoftransportinfrastructure;

 Reducedelaysonjourneys;

 Increasejourneysbybusandrail;and

 Increaseactivetravel.

2.5.2 AkeytenantoftheLTPrelatestotheongoingdevelopmentofanaccessibilitystrategyforthe region. The LTP recognises the importance accessibility can play in modern society and in reducing social exclusion by facilitating access to work, education, healthcare and affordable, healthyfood.

2.5.3 The first LTP outlined Lancashire’s longterm vision for a Total Transport Network (ttn) for Preston and South Ribble. The ttn is a sustainable integrated transport network that brings together new technology and traditional transport solutions to provide an integrated network. DuringthefirstLTPperiodprogresswasmadetowardattnwiththeopeningofPark&Ridesites forPrestonaswellastheintroductionofQualityBusservicesonthreecorridors.TheLTP2will takeonthedevelopmenttowardthettnwith£4.2millionassignedforinvestmentovertheLTP2 period. This will include the promotion of sustainable transport modes with new vehicle technologiesforbuses(includinghybridvehicles),congestionreducingmeasuresandinnovative informationsystems.

2.5.4 There are several other schemes, strategiesand policies specifically identified for the areas of Preston,SouthRibbleandChorley.Thesearesummarisedforeachdistrictbelow:

CentralLancashireTransportStudy 2.4 2 Policy Context

Preston

2.5.5 ConsultationbetweenLancashireCountyCouncil,theLocalStrategicPartnershipandPrestonCity CouncilhasresultedinthefollowingkeyschemesforPreston:

 PrestonNorthPark&RideschemesincludinghighwayimprovementsatM55Junction1;

 CiVITASSustainableTransportProject(CiVITASisaEuropeanUnionprogrammeaimedat promotingsustainabletransportoptions);

 PrestonGuildWheelCycleRouteandCityCentreCycleHub;

 PrestonAirQualityJunctionimprovements;and

 PrestonBusStation.

South Ribble

2.5.6 ThekeyschemesforSouthRibblehavebeendeveloped during consultation with South Ribble BoroughCouncilandareshownbelow:

 LeylandTownCentreRegeneration;

 TardyGateAQMAActionPlan;

 BamberBridgePublicTransportInitiatives;

 AccessibilityImprovementstoEmploymentAreastoHospitals;and

 SchoolTravelPlanPackage.

Chorley

2.5.7 ThekeyschemesforChorley,developedtogetherwithChorleyBoroughCouncil,include:

 EavesGreenLinkRoad;

 ChorleyConnectDepartmentforTransport(DfT)KickstartBusProject;

 BuckshawParkwayPark&Ride;

 ChorleyPedestrianPriority,AccessandParking;and

 AccessibilityStudyofChorleyBorough.

2.5.8 AtthetimetheLTP2wassubmitted,potentialMajorSchemebidstobeconsideredinthefuture includedtheA59Bypass.

2.62.62.6 The Replacement Joint Lancashire Structure Plan 2001 – 2016

2.6.1 TheReplacementJointLancashireStructurePlan(JLSP)outlinesstrategicpoliciesandproposals forthedevelopment,useandconservationoflandinLancashire.Italsosetsouttheanticipated amount,andgenerallocation,ofdevelopmentrequiredtomeetthefutureneedsofLancashire’s population. When the Regional Spatial Strategy (RSS) is fully adopted the JLSP will be superseded.

CentralLancashireTransportStudy 2.5 2 Policy Context

2.6.2 Asettlementhierarchyispresentedwithinthedocumentwiththemajorityofdevelopmenttobe directed to the ‘Principal Urban Areas’ of Blackburn, Blackpool and the Fylde Coast, Burnley, Lancaster/and Greater Preston .

2.6.3 Levelsofhousingandbusinesslandprovisionareidentifiedforeachdistrictupuntil2016.The Royal Ordnance site at Euxton near Chorley is also identified as a Strategic Location for Development.

2.6.4 Fivebroadpoliciesarealsodiscussedwithinthe‘AccessibilityandTransport’sectionoftheJLSP. Thesepoliciesare:

 Parking – aim to restrict and gradually reduce longstay provision in major centres, prioritytoshortstayprovisionandbusbasedPark&Rideschemedevelopment;

 Strategic Road Network Proposed Improvements – including pursuing possibility of BroughtonBypassandPenworthamBypass;

 Rapid Transport Systems in Regeneration Priority Areas – not directly relevant to CentralLancashirestudyarea;

 Rail and Bus Improvements –provisiontobemadefornewrailstationsCottam,Midge Hall, Royal Ordnance (Euxton) and Coppull and a new public transport interchange at Preston;and

 Freight distribution –developmentinvolvingrequirementsforsignificantdistributionto be located in places with good access to the strategic road network and, wherever possible,portsandtherailnetwork.

2.72.72.7 Draft Preston and South Ribble 2028 Transport Strategy

2.7.1 ThePrestonandSouthRibble2028TransportStrategy documentdescribesa range of policies andproposedmeasuresaimedatimprovingtransportforpeopleinthetwoareas.TheStrategy recognisestheneedtomovejourneysawayfromtheprivatecarand toward more sustainable modesoftransport.Thisinvolvesthecreationofthe Total TransportNetwork(ttn).Thelong termStrategyisbasedontheexampleoftheintegratedtransportsysteminthecityofCuritiba, Brazil.

2.7.2 TheStrategyhasthefollowingoverarchingobjectives:

 Reducethenegativeimpactwehaveonourplanet;

 Promoteeconomicactivityandvitalityandimprovesocialinclusion;

 Playitspartinimprovinglocalenvironmentalqualityandqualityoflife;

 Improve accessibility for all forms of transport and to provide a wider choice of quality transportmodes;

 Maintaingoodaccessibilityforall,bothtoandwithinthecity;

 Provideastronglinkbetweenlanduseplanningandtransportprovision;

 Improvepersonalsafetyandsecurity;

 Improveaccessibilityforvulnerableusers;and

CentralLancashireTransportStudy 2.6 2 Policy Context

 Promotetheefficientuseofscarceresources.

2.7.3 The document setsoutthe transport strategy intwo broad sections with the first focusing on effortstochangeattitudesandbehaviour.Thesecondsectionoutlinespoliciesandinfrastructure improvementsfor:

 Publictransport;

 ‘Streetsforpeople’;

 Cars;

 Cycling;and

 Freight.

2.7.4 Key developments outlined within the public transport section of the Strategy include the redevelopment of Preston rail and bus stations and improved interchanges between the two, improved crosscity routing patterns, new bus priority measures and the development of new ParkandRidesitestothesouthofPrestonandinSouthRibble.

2.7.5 The ‘Streets for People’ section of the Strategy outlines plans to create safer signed walking routes,toimprovecrossingfacilitiesforpedestrians,tocalmtrafficinappropriateplacesandto generallyputpedestriansandcyclistsatthetopofthe street hierarchy, rather than motorised vehicles.

2.7.6 Withregardstothehighwaynetwork,itisviewedintheStrategythatmajorroadbuildingisnot a realistic response to the problems facing urban transport, unless this building includes significantimprovementsforpublictransportefficiency.However,theStrategyincludesarange of policy commitments to better maintain and manage the existing network with focus on improving the efficiency of the Ring Road (Ringway) and in improving signage. The Strategy states that longstay parking will be restricted in order to limit increase in commuting by car, althoughshortstayparkingwillbeaccommodatedtoencouragevisitors.

2.7.7 Itisanticipatedthatin2009thisstrategywillbeadaptedtoincludeChorley,whichiscurrently notincludedwithinthe2028TransportStrategydocument.

2.82.82.8 Central Lancashire, Blackpool Growth Point Bid

2.8.1 TheNewGrowthPointsinitiativeisdesignedtoprovidesupporttolocalcommunitieswhowishto pursue large scale and sustainable growth, including new housing, through a partnership with Government.

2.8.2 In October 2007 a submission was made on behalf of the councils of Preston, South Ribble, Chorley, Blackpool and Lancashire to the Department for Communities and Local Government outlining an accelerated housing growth programme, which would stimulate further economic growthandregeneration.

2.8.3 The submission proposed to deliver almost 20,000 homes by 2016 offering a mix of types in sustainablelocations.Thebidwascentredonanenhancedpublictransportprovisionandamore efficienturbantransitsystemalthoughnewhighwayinfrastructurewasidentifiedaspartofthe bidtounlockcertainsites,whicharecurrentlyconstrained.Thebidalsohighlightedtheneedto developamultimodaltransportmodelforthearea.

CentralLancashireTransportStudy 2.7 2 Policy Context

2.8.4 Thetransportprioritiesrecommendedaspartofthebidwere:

 EnhancingpublictransportconnectionsbetweenPrestonandBlackpool;

 ImprovementstoPrestonRailStation;

 UrbantransitsystemalongmorecongestedroutesintoPreston;

 NewbusstationinPrestonCityCentre;

 NewRailwayStations(includingBuckshawParkway);

 InterlinkedPark&Ridesites;

 Partnershipworkingtopromotemoresustainableformsoftransport;and

 Longer term (beyond 2016) – provision of new highway infrastructure to support developmentstothesouthandwestofPreston

2.8.5 The partners are currently working on developing a Programme of Development for the next phase of the Growth Point process following the announcement that the initial expression of interestsubmittedin2007wassuccessful.

2.8.6 The designation of Central Lancashire and Blackpool as a growth point area has also enabled transportinfrastructureprojectstobeputforwardasexpressionsofinterestfortheCommunity Infrastructure Fund Round 2. These are outlined in more detail in the chapter on funding (Chapter7).

2.92.92.9 Summary

2.9.1 Thissectionhassummarisedthemostrelevantregionalandlocalplanningandtransportpolicies relatingtothePreston,SouthRibbleandChorleyTransportStudy.

2.9.2 Ingeneralregionalpolicieswishtoseemajordevelopmentfocusedonthemainurbancentresin theregion,particularlyinthecityofPreston.Thiscloselyfollowskeynationalpolicies.

2.9.3 Current policy documents recognise the need for transport improvements within the region in order for the forecast economic growth to be successfully managed and maintained. Of key importance,particularlyrelatingtothe national sustainabilityagenda,are improvements to the public transport network in the area. Major improvements to this include the ongoing development of the Total Transport Network (ttn) and improvements to local bus and rail interchangefacilities.

2.9.4 Some improvements to the local highway network are proposed within local policies although greater attention is paid to managing demand rather than wholesale capacity improvements. Parking management strategies are one such demand management technique with proposed restrictionsonthegrowthoflongstayparkingprovisioninfavourofshortstay,whichwillfavour shortbasedshoppingtripstothetownandcitycentres.

CentralLancashireTransportStudy 2.8 3 BaselineReviews

3.13.13.1 Introduction

3.1.1 This section of the report summarises the following current baseline reviews that were undertakenaspartofthisstudy:

 SocioeconomicReview;

 ReviewofTraveltoWork;

 PublicTransportServices;

 Cycling&PedestrianReview;

 RoadNetworkReview;and

 CarParkingReview.

3.23.23.2 Socioeconomic Review

3.2.1 There areapproximately 334,000 people living in the three districts that make up the Central Lancashirestudyarea.Justoverhalfthepopulationareagedbetween24and64yearsoldand 35%areeitherunder15yrsorover65yrsthisgrouparetraditionallymoredependentupon public transport services.The 1624 age group makeup1014% ofthe population across the three districts. This population is slightly higher in Preston due to the University of Central Lancashire(UCLAN).

3.2.2 ThenumberofstudentsattendingUCLANisabout35,000withapproximately 3,000 staff.The wards surrounding the university have the highest number of student residents indicating a preferencetolivewithinwalkingdistanceofthecampus.Traditionallystudent’sprimarymodeof transporttendstobewalkingorcycling.

3.2.3 InChorleyandSouthRibbletherearealowerpercentageof people livingontheir own buta greaterproportionofhouseholdswith24people.InPreston63%ofhouseholdsconsistof12 people. Household composition has important consequences for car ownership and residential parking.

3.2.4 Householdforecastsbetween2003and2006predictthatmostofthegrowthwillbeinChorley andSouthRibblewithaslowerrateofgrowthinPreston.

3.2.5 Areaswiththehighestlevelsofcarownershiptendtobetothenorthandtheeastofthestudy area.Howeverinruralcommunitiesevenhouseholdswithaccesstoonecarcanexperiencesocial exclusionparticularlywhentheprimarywageearnerneedsthecarforcommutingtowork.

3.2.6 PocketsofeducationandskillsdeprivationexistinalltheboroughsofCentralLancashire,thisis particularly evident east of Preston city centre with several wards falling into the 10% of the mostdeprivedinthecountry.

3.2.7 Areas where there is significant exportation of labour are characterised by high levels of car ownershipandtraveltoworkbycar.Someoftheseareruralareaswherethepublictransport alternativemaynotbeaviableoption.

CentralLancashireTransportStudy 3.1 3 Baseline Reviews

3.2.8 Prestoncitycentreexhibitsdifferentcharacteristicstotherestofthestudyarea.Thepresenceof the university means a much larger proportion of the population are students, there are also considerably lower car ownershiplevelsand the centreis a large importer of labour.However thesewardsalsohavesomeofthelowestaveragehouseholdincomesinthestudyarea.

3.2.9 Thewardsontheperipheryofthethreedistricts,particularlytotheeastandnorthofthestudy areae.g.PennineandChisnallhavemuchsparserpopulationsthantheurbanareas,buthigher averagehouseholdincomesandcarownership.Theseareasarecharacterisedbyhavingfewjobs availablelocallysoarehighexportersoflabour.

3.2.10 Outsideofthesetwogroupsthereareanumberofotherwards,mainlyinthesuburbsofPreston andtheurbancentresofChorley,BamberBridgeandLeyland.Theytypicallyshowsomeofthe economic and social characteristics of Preston city centre, although unemployment rates are lowerandhouseholdincomelevelsaremoderatelyhigher.

3.33.33.3 Travel to Work

3.3.1 Thejourneytoworkdatabymodeanddistrictarepresentedintable3.1focusesonthedistrict’s residentpopulation–thepopulationthatliveintheparticulardistrict.

Table 3.1 Journey to work modal choice - Resident population (Census 2001)

Method of England and Chorley Preston South Ribble travel Wales

Workmainlyfrom 9.2 9.3 7.4 8.1 home

Drivecar 55.2 65.5 55.9 64.6

Carpassenger 6.3 7.3 7.5 7.4

Bus 7.4 3.3 11.2 5.8

Train 4.1 1.8 0.7 1.0

Motorcycle 1.1 1.0 0.9 1.3

Bicycle 2.8 1.8 2.6 3.9

Walk 10.0 9.2 12.9 7.2

Other 4.0 0.8 0.9 0.7

3.3.2 Modal choice in Chorley and South Ribble are very similar with around 7273 percent of the resident population travelling to work by car. In Preston this figure is lower because a smaller percentage of people drive a car to work. This is reflected in higher levels of bus travel and walkingtowork.

CentralLancashireTransportStudy 3.2 3 Baseline Reviews

3.3.3 Preston has the highest levels of bus travel at 11.2 percent, more than 3 times the level in Chorley.Ithasalsothehighestpercentageofpeoplewalkingtowork,butthelowestlevelsusing thetrain.

3.3.4 Table 3.2 summarises the travel to work data for key origins and destinations. From this it is possible to identify thejourneysthatarecontainedwithinthelocalareaandthelevelofout commuting.

3.3.5 AnumberofkeypointsemergefromthedatapresentedinTable3.2:

 ThemajorityofjourneystoworkstartandendinPreston,suggestingsignificantretention oflabourinPrestondistrict;

 InChorleyapproximatelyhalfofthepopulationworkwithinChorleyDistrictandtheother halfcommutetothesurroundingareasparticularlyManchesterCityRegion(16%),Preston (11%)andSouthRibble(13%);

 AsthemajorpopulationandeconomiccentreinCentralLancashire,Prestondrawsinlarge numbersofworkersfromthesurroundingauthorities.Thisismostnotablythecasewith neighbouringSouthRibblewithover14000journeysadaymadetoPreston.Incontrast only4149peopletravelintheoppositedirection;

 AlthoughsignificantnumberstravelfromChorleytoPrestonandSouthRibbletowork,the largestdestinationforworkersfromChorleyistheManchesterCityRegion.Thisispossibly explained by Chorley’s closer proximity to Manchester and well developed road and rail linksfromthetown;and

 The three main origins of journeys to Chorley are South Ribble (3,728), Manchester (3,694)andPreston(1,100).

3.3.6 Anumberoffindingscanbedrawnfromthejourneytoworkdata:

 The majority of journeys to work in Central Lancashire are made by car (over 70% in ChorleyandSouthRibble);

 Over10%ofjourneystoworkarebybusinPrestonbutfigures for Chorleyand South Ribble are much lower.This couldbeaccounted forbyarangeoffactorsincludingless comprehensive services, longer more complicated journeys and the availability of free workplaceparking;

 Figuresforwalkingandcyclingcombinedarearound10percentinallthreedistricts;

 Preston,asthelargesturbancentreinCentralLancashiredrawsinlabourfromacrossthe area;

 otheremploymentcentreswereidentifiedinLeyland,ChorleytowncentreandatWalton Summit;and

 SouthRibbleinparticularhashighlevelsofoutcommuting comparedtothe other two districtsinthestudyarea.Prestonismoreselfsufficientandalargenumberofresidents, particularlyinChorley,commutetoGreaterManchester.

CentralLancashireTransportStudy 3.3 3 Baseline Reviews

Table 3.2 Travel to work Data (Census 2001)

Destination Total Chorley Preston South Fylde Ribble Blackburn Manchester Liverpool > Ribble Valley City Region City Region

Origin \/

Chorley 47312 24589 5021 6300 660 466 1458 7702 1116

Preston 53279 1100 39067 4149 3592 1630 821 2080 840

SouthRibble 49371 3728 14752 23317 1995 1044 1085 2610 840

Fylde 3659 219 2825 615

RibbleValley 2990 517 2272 201

Blackburn 3183 525 1669 989

Manchester 3694 3339 2586 Cityregion 9619

LiverpoolCity 690 1342 823 region 2855

CentralLancashireTransportStudy 3.4 3 Baseline Reviews

3.43.43.4 Public Transport Services

Local Bus Services

3.4.1 Preston is well served by a number of frequent local bus services mostly operated within the urban area by Preston Bus. Most of the roads within Preston suffer from congestion to some degreewhichseemstobeattributabletothehistoriclayoutofsomeofthestreetsbutalsothere aresomeissueswithsignalisationandlackofpriorityforbuses.

3.4.2 However as Preston develops there will be a requirement to give greater priority to local bus servicesalongkeycorridors.Weanticipatethatserviceenhancementswillinvolveextracapacity duringpeakperiods,someservicediversionsornewroutestolinkemploymentwithresidential areas.

3.4.3 UnlikeChorleyandPrestonSouthRibbledoesnothaveitsownnetworkofservices.Busservices tendtopassthroughtheboroughonroutetoChorleyorPreston.Theservicestendtofocuson Chorley–BamberBridge–PrestonorLeyland–Penwortham–Prestoncorridorsleadingtopoor connectivityandpenetrationbetweenurbancentreswithintheBorough.

3.4.4 NetworkChorleyiscurrentlyfundedthroughKickstartfundingandsomedevelopercontributions and Kickstart funding is due to end in 2011. Whilst there has been in growth in passenger numbers it is unlikely that the network will be commercially viable by the end of the funding period. Therefore the exit strategy will be to preserve the existing passengers and reduce the service levels to a more economically sustainable network with some ongoing support from LancashireCountyCouncil.

3.4.5 The network consists of core town services of 23 buses per hour and hourly services to the nearbyruralsettlements.Whilstthislevelofservicemaybeadequateatpresentitwillneedto bekeptunderreviewasChorleyexpands.TherearegoodbuslinksbetweenPrestonandBolton provided by the 125/126 but at present there is only an hourly service between Chorley and Blackburn.AccessibilityinthemoreruralpartsoftheBoroughisaparticularconcernraisedby officersatChorleyBoroughCouncilandhighlightedinarecentaccessibilityaudit.

3.4.6 Local bus operators have reported localised congestion problems at the following locations throughoutthearea:

 TardyGate;

 A6Sainsbury’s,BamberBridge;

 A6PrestonRoadbytheCapitolCentre;

 ChorleyHospital–thejunctionandaccesstothehospitalgrounds;and

 Prisonjunction,Preston

3.4.7 Atpresenttherearenojointornetworkticketinginitiativeswithintheareaevenonservicesthat are jointly operated such at the 109 which currently serves Buckshaw. A stored rights pilot is proposed for the Central Lancashire area using smartcard technology. The pilot will start in November2008andwillbeaimedat1623yearolds.

CentralLancashireTransportStudy 3.5 3 Baseline Reviews

3.4.8 AnewbusinterchangewillbebuiltonChurchStreetinPrestonaspartoftheTitheBarnproject and is due to open in 2011. There are also developer contributions to develop a busrail interchangeatPrestonRailStation.Abus–railinterchangeisalsoproposedforBuckshawVillage and it is anticipated that this will open in March 2009 although at present there is a funding shortfall.

3.4.9 AnewPark&Ridesiteisalsoprogrammedforjunction31aandisduetobeoperationalin2009. Thesitewillprovideapproximately500parkingspacesandwillbeservedbythePrestonOrbit services,whichwillconnecttoPrestonRoyalHospitalaswellastheCityCentre.

Rail Services

3.4.10 Thereareeightstationsinthestudyarea:

 Preston–westcoastmainlineservices,Blackpool,Manchester,Liverpool,Blackburn

 LostockHall–Preston,Blackburn,Blackpool

 BamberBridge–Preston,Blackburn,Blackpool

 Leyland–Manchester,Preston,Liverpool,Blackpool

 –Ormskirk,Preston

 Euxton–Preston,Liverpool

 Chorley–Preston,Blackpool,Manchester,Cumbria,Scotland

 Adlington–Preston,Manchester,Blackpool

3.4.11 Preston is the busiest station and has strategic importance as it provides links to the national network as well as the local network. There are also significant numbers of passengers using ChorleyrailstationwhichprovideslinkstobothPrestonandManchester.

CentralLancashireTransportStudy 3.6 3 Baseline Reviews

Table 3.3 Rail Station facilities

Station Staffed CCTV Waiting Bus/taxi Car Park Cycle room storage

Preston Yes Yes Yes Both 475 30spaces, spaces,£6 sheltered, perday CCTV

Chorley Yes Yes Yes Bus 50free 12spaces spaces

Bamber No No Shelters Bus Yes No Bridge

Leyland Yes No Shelters Bus 72free 12spaces spaces

Lostock No No Shelters Bus 20free No Hall spaces

Euxton No No Shelters Bus 42free 5spaces Balshaw spaces Lane

Adlington DuringAM No Yes Bus 25free No Peak spaces

Croston No No Shelter Bus 30free No spaces

3.4.12 Facilities at stations vary from station to station (Table 3.3). At Preston there are issues with congestionandaccessibilityontheButlerStreetfootbridgeandthestructuresonplatforms1and 2maketheseplatformsfeelverycluttered.AtChorleythestationcarparkisoftenfullby8am andinLeylandthegeneralstandardofpassengerfacilitiesarepoor.

3.53.53.5 Cycling & Pedestrian Review

3.5.1 Manymeasuresforcyclistswillalsobenefitpedestriansaswellascyclists.

3.5.2 CyclinghasbeenidentifiedasapotentialareaforgrowthbythePrestonandSouthRibbleTravel Behaviour Research and the Preston Cycling Strategy. Although it is acknowledged in these reports that the cycling infrastructure could and will improve, it was also felt there were “subjective reasons preventing a switch to cycling” based on people’s perceptions and lack of experience. If publicity and facilities are improved it may be possible to change these perceptions.

3.5.3 Another way in which cycling could grow is in providing a connecting link to other forms of transport,suchasfromthehometorailwaystationsorparkandridesites.Inorderforthese

CentralLancashireTransportStudy 3.7 3 Baseline Reviews

types of schemes to be successful it is important access is good to these sites and storage facilitiesareprovided.

3.5.4 Since 1995 a National Cycle Network (NCN) with routes across the UK has been created. This networkisoverseenbySUSTRANSandissupplementedbypathsdesignatedasregionalroutes, which are usually promoted by local authorities. Table 3.4 lists the national and regional cycle routeswhichpassthroughtheboroughsofCentralLancashire.

Table 3.4 National & Regional Cycle Routes

Route number Proposed Route details

NationalRoute6 PrestonLancasterKendal

NationalRoute55 IronbridgeStaffordMacclesfieldStockportor BoltonPreston(proposed)

NationalRoute62 SelbyPrestonBlackpool

RegionalRoute90 LancashireNorthernLoop(BowlandForest)

RegionalRoute91 LancashireSouthernLoop

3.5.5 At the moment many National Routes are still to be completed, although sections in Central Lancashireareopen.

3.5.6 ACyclingStrategyiscurrentlybeingpreparedbyMayerBrownforPreston.Thestudyfocuseson thedistrictofPreston,butalsoinvestigatescycletrippatternstoandfromneighbouringSouth Ribble.

3.5.7 Theprincipalexistingcycleroutesare:

 NCNroute6crossingnorth/souththroughthecity;

 CanalcycleroutelocatedtothenorthwestofthecitycentretoandbeyondtheCottam districtinthenorthwestofthestudyarea;

 Longridgerailwaylink;

 PrestontoBlackpool(route62)fromthecitycentre;

 PrestontoBamberBridgecycleway;and

 Inadditionitisnotedthereareoffandoncarriagewaysectionsofcycleroutethroughout thedistrict.

3.5.8 Anumberof‘strategicproblems’currentlyaffectcyclists.Theseproblemsinclude:

 Isolatedfacilitieswithpoorroutedefinition;

 Limitedroutedevelopmentandcyclerestrictionsthroughthecitycentre;

 Limitedcycleexemptionfromonewaystreetorders;

 Poorcycleaccesstobus/railstations;

CentralLancashireTransportStudy 3.8 3 Baseline Reviews

 Limiteddefinedcycleroutes;

 Poorconnectionbetweenthesubstantialnetworkofoffcarriagewaycycleroutesandthe neighbouringurbanareasandwiderhighwaynetwork;

 Ringwayformingabarriertocyclemovementsnorthofthecitycentre;

 Poorconnectivityofresidentialareastokeyemploymentsites;

 Lackoflongtermcycleparking;

 Limitedcyclecountdataforcycletrendanalysis;

 Poorknowledgeofroutelocationsandsignage;

 Perceiveddangerofcycling;and

 Limited‘recycling’orsecondhandcyclebusinesses.

3.5.9 ThecyclingstrategyforSouthRibbleiscurrentlybeingdevelopedbyLancashireCountyCouncil. TheemphasisofthecyclingstrategyisreinforcingandimprovinglinksbetweenLeyland,Preston, Croston(particularlytheprison)andChorleyviaBuckshaw.Thereisalsoopportunitytoconvert someofthewidepavementsaroundMorrisonsinLeylandtoshareduse.

3.5.10 Historicallycyclinghasbeenpopularwiththetraditionalindustriessuchasthemotorcarindustry and this is evident in the higher proportions of cycling to work in Leyland. However these traditionalindustriesarenowindecline.

3.5.11 There are a number of opportunities to integrate cycling more effectively with wider transport networkssuchasrailstations,businterchangesandpark&ridesites.

3.5.12 Therealsoneedstobeanoverarchingcyclingandpedestrianstrategytopromoteconnectivity acrossthestudyarea.

3.63.63.6 Road Network Review

Motorway Network

3.6.1 Thestudyareahasastrategiclocationonkeynorthsouthandeastwesttransportcorridors;the country’sfirststretchofmotorwaywastheM6closetoPreston.Themajorurbanareasofthe studyareaallhaveexcellentconnectionstothestrategicroadnetwork,withtheM6,M55,M61 andM65alleitherstartinginthestudyareaorpassingthroughit.

3.6.2 The M6 and M61 provide strong northsouth connectivity throughout the extent of the study area.TheM6inparticularisofnationalsignificanceandconnectsthestudyareatoCheshireand theMidlandsinthesouthandtoScotland,viaLancasterand,inthenorth.

3.6.3 TheM55runstothenorthofPrestonandconnectsM6toBlackpoolinthewest.Meanwhile,the M65connectsthestudyareatothetownsofAccrington,BlackburnandBurnley.

3.6.4 Table3.5showstheapproximatelengthofeachmotorwaywithinthePreston,SouthRibbleand Chorleystudyarea.

CentralLancashireTransportStudy 3.9 3 Baseline Reviews

Table 3.5: Motorways in Study Area

Motorway Approximate Length

M6 34km

M61 18km

M65 12km

M55 8km

3.6.5 Thereareatotaloftenmotorwayjunctionswithinthestudyarea,withsixoftheseontheM6.All butonejunctionenablesallvehicularmovements(i.e.onandoffinalldirections);theexception isJunction31aontheM6,whichprovideslimitedinterchangewiththeB6242tothenortheastof Preston. Only northbound traffic can exit the M6 while B6242 traffic is limited to joining the motorwayinasouthbounddirection.

3.6.6 Ingeneralthemotorwaynetworkinthestudyareaisthreelaneineachdirection,althoughthe M6betweentheM61(Junction30)andtheM55(Junction32)hasbeenwidenedtofourlanesin eachdirection.

Principle Routes

3.6.7 The study area also has an extensive nonmotorway highway network that connects the communitieswithinthestudyareaandalsolinksthestudyareatoneighbouringareas.Routesof notablesignificanceinclude:

 A581–Chorley–Southport;

 A6–Preston–Chorley–GreaterManchester;

 A59–Preston–Liverpool;

 A49–Wigan–Euxton–Preston;

 A583–Preston–Blackpool;

 A582–Preston–Penwortham–LostockHall;

 A677–Preston–Blackburn;and

 A674–Blackburn–Chorley.

3.6.8 There are a range of roads radiating from Preston city centre, which is also bypassed by the Ringway (A6, A59). Blackpool Road (A5085) also provides an orbital route to the north of Preston.

3.6.9 Together with the M6 and M61 motorways, the highway network is dominated by northsouth routessuchastheA6,A49andtheA59.

3.6.10 TrafficflowsonthemotorwaynetworkaregreatestonthefourlanestretchoftheM6between the M55 and M61 junctions. Hourly flows between these junctions reach 6,500 in a single directioninthepeakhourswith12hourflowsexceeding60,000.

CentralLancashireTransportStudy 3.10 3 Baseline Reviews

3.6.11 Twelvehour flows on the motorways in the south of the study area connecting to Greater Manchester (M6andM61) arealsohighwiththe M6 in thisarea exceeding40,000vehicles in eachdirectionandtheM61exceeding31,000vehiclesineachdirection.

3.6.12 FlowsontheM55towardBlackpoolandontheM65towardEastLancashirearesomewhatlower than onthe major northsouth routes.Peakhourflowson theseeastwest routesare typically between2,500–3,000ineachdirectionwithtwelvehourflowsbetween25,000and30,000.The M6 north of the study area, which connects to north Lancashire, Cumbria and Scotland, have flowscomparableinvolumeastheM55andM65.

Preston City Centre Cordon Counts

3.6.13 Data in theLTP2 showed that, in 2005, upto approximately 7,400 vehicles cross the inbound PrestoncitycentremonitoringcordonintheAMpeakhour(08:00to09:00).Over8,000vehicles crossintheoutbounddirectioninthePMpeakhour(17:00to18:00).Between2003and2005 therewasapproximatelya3%increaseintrafficcrossingthecitycentrecordonsineachpeak period(07:00to10:00and16:00to19:00)although,ingeneral,therewasaspreadingofthe peakperiodwiththeincreasesmostnotableintheearlyandlatepartofthepeakperiod.

Penwortham Bypass

3.6.14 Proposals to complete a bypass of Penwortham have been the subject of discussion for a significantlengthoftime.TheschemewouldseetheA59connectedtotheexistingBroadOak Roundabout on the A582 via a new dualcarriageway with sections of the A582 also to be upgradedtoadualcarriageway.

3.6.15 Following a review of the regional transport priorities by the Government Office for the North West (GONW) and theNorth West Regional Assembly (NWRA)anumber of schemes were put forwardtotheDepartmentforTransport(DfT)asprioritiesfortheregion.Followingthereviewof schemesbyGONWandNWRA,thelistofschemesweresplitintofourprioritycategories,(known as Priority Quartiles). The three schemes in the top priority quartile were included as major schemebidswithintheSecondLancashireLocalTransportPlan(LTP2).ThePenworthamBypass scheme wasallocatedin thethird priority quartile and has been included asapotentialfuture major scheme bid in theLTP2.Theprecise position ofthePenworthamBypass scheme will be subjecttofurtherreviewinthelightoftheGONWandNWRAprioritisationprocess.

Broughton Bypass

3.6.16 Provision of the bypass and reduction of traffic within Broughton will enable a package of measurestoimprovetheenvironmentoftheA6withinthevillageandprovidebetterconditions forpedestrians,cyclistsandpublictransport.

3.6.17 Although the need for the bypass is justified by the level of existing and forecast traffic flows through Broughton, the bypass is also required before the potential strategic growth at Goosnargh/Whittingham,canbefullydeveloped.

3.6.18 Lancashire County Council approved a planning application for the bypass in July 2001. The Whittingham Hospital development will contribute to the cost of constructing the bypass. The planning permission for the redevelopment of the hospital site is subject to a condition which limits the amount of development that can take place before construction of the bypass commences.

CentralLancashireTransportStudy 3.11 3 Baseline Reviews

South Ribble Cross Borough Link

3.6.19 Policy T3 in the South Ribble Local Plan states that a road will be constructed from the roundaboutonCarrwoodRoadtoLeylandRoadinthevicinityofBeeLaneinordertoopenup landfordevelopmentandtoserveasalocalthroughroute.Trafficmanagementmeasureswillbe undertakenonLeylandRoadinordertolimitanyincreaseinroadspaceforcars.

3.6.20 TheproposedlengthofroadwillconnectCarrwoodRoundabouttoLeylandRoad.Thisroadwill servea dual function byopening up landfordevelopmentandproviding a local through route fromPenworthamtoWaltonleDale/BamberBridge;initslatterroletheproposalwillsupersede LeylandRoadforthroughtraffic.

3.6.21 TheconstructionoftheroadisidentifiedasnecessarybytheLocalPlantoenabletheresidential andmixedusedevelopmentsonlandtotheeastofLeylandRoadandontheformerGasworks sitetogoahead.ThelandaroundtheGasworksandtheGasworkssiteitselfcannotbedeveloped withoutanewaccessontoLeylandRoadandaconnectiontotheA6BamberBridgeBypass.

3.73.73.7 Car Parking Review

3.7.1 TheinformationforthissectionisbasedonareportproducedbyFaberMaunsellwhichdidnot include Chorley and summarises the key conclusions and recommendations from the Faber MaunsellparkingstudyofPrestonandLeyland.

Impact of Future Developments

3.7.2 The Faber Maunsell report states that the Leyland Masterplan will drive regeneration and developmentofthetowncentreandthatthisdoesnotproposesignificantincreasesinparking stock levels. Instead the Masterplan is to focus on rationalisation of parking areas and also improvedqualityofparkingprovision.

3.7.3 ItisnotedthattheconsiderableamountofredevelopmentandregenerationplannedforPreston willincludesubstantialincreasesincarparkingsupply.TheFaberMaunsellreportstatesthata netincreaseinexcessof4,500carparkingspaceswillresultifallplanningapplicationandfuture regeneration schemes in Preston proceed as planned. This represents an increase of approximately35%oftotalparkingstock.

3.7.4 LeylandConclusionsandRecommendations

3.7.5 TheFaberMaunsellreportconcludeswiththefollowingrecommendationsforLeyland:

 In line with the Leyland Masterplan, consider improvements to public car parks and improvelinksbetweenpubliccarparksandHoughLane;

 Consider the removal of chargesat the Station Approach car park to encourage greater useofrailcommuting;and

 ConsidertheintroductionofhalfhourlimitedparkingonHoughLane.

CentralLancashireTransportStudy 3.12 3 Baseline Reviews

Preston Conclusions and Recommendations

3.7.6 TheFaberMaunsellreportconcludeswiththefollowingrecommendationsforPreston:

 Consider introduction of a signage strategy to include intelligent and responsive car parkingsignage;

 Ensuredisabledparkingprovisionfornewdevelopmentsismeetingrecommendedlevels;

 Monitor occupancy levels at existing Park & Ride sites and continue to develop existing capacitiesinlinewithdemandwherepossible;

 Monitor the development of Workplace Parking Levy policies from the Department for Transportandkeepthispolicyoptionunderreview;and

 Ensureimplementationofthecaponlongstayparkingprovisionandreviewonanannual basisforreportingintheLocalTransportPlan.

CentralLancashireTransportStudy 3.13 4 DevelopmentSites

4.14.14.1 Introduction

4.1.1 Thederivationofatransportstrategyforthestudyareawasbasedontwopotentialdevelopment scenarios:

 2018–whichrepresentedarapidgrowthindevelopmentandassumedasuccessful growthpointbid;and

 2028–providesalongertermviewandconsistofthelargerpotentialsites,emerging fromthesitesuggestionprocess

4.1.2 Thesitesthathavebeenidentifiedforthe2018assessmentarethosecurrentlyconsideredthe most likely to be developed within the initial time frame. However, the sites identified for the 2028 assessment are less certain and subsequently the potential development proposals for theseareasshouldbetreatedwithcaution.

4.1.3 Itislikelythatsomeofthesitesincludedinthe2028scenariomaynotbeincludedwithinthe LocalDevelopmentFrameworkastheymaynotconformtocurrentplanningpolicyortheoverall spatialstrategy.Inaddition,somesitesmaybebroughtforwardanddeliveredsoonerthan2028 butitisnotpossibleatthisstagetodetermineanaccuratedeliveryschedulegivenuncertainties regardingfutureeconomic policies, demandsetc.Therefore the scenariofor2028 representsa ‘best guess’ based on current available information but it should be notedthat the scenario is verylikelytochange.

4.1.4 Traffic generation assessments for developments included in the 2018 scenario have been undertakenusingPENELOPE,whichisatoolthathasbeendevelopedfortheHighwaysAgencyto helpintheirassessmentofthepotentialimpactthedevelopmentscouldhaveinrelationtothe trunkroadnetwork.

4.1.5 Giventheuncertainties,timescalesandlackofdetailedlandusedata,PENELOPEwasnotused forthe2028scenario,buttripestimateswereobtainedusingtheTRICSdatabase,basedonland usepredictionsasagreedwiththeclient.

4.1.6 Therearelimitationstotheactuallevelofanalysisthatcanbeundertakenaspartofthisstudy, giventhelackofavailabledataandacomprehensivetransportmodelofthearea.Belowwehave included analysesof thedevelopment sitesandtheirlikelyimpactonthenetworkasawhole. However these analyses are only indicative and need to be supported by more detailed assessmentwork.

4.24.24.2 PENELOPE

4.2.1 “PENELOPEembodiestheprincipleof‘gravitymodeling”.Thisisamethodologyforproportioning the total trips associated with a site among the surrounding wards according to their relative attractions, hence the name ‘gravitymodeling”. For example, if a new housing estate were proposed, the total number of trips would be predicted based on the number of houses to be built,andintheAMpeakthebulkofthosetripswillbepeopletravelingtowork.

CentralLancashireTransportStudy 4.1 4 Development Sites

4.2.2 In the absence ofany more detailed information (which by definition is unavailable before the estatehasbeenconstructed);theassumptionisthatthesepeoplewillgotoworkprimarilywithin the existing centres of employment surrounding the site. Some major concentrations of employment(suchascitycentres)maybefurtherawaythansmallerconcentrationsnearby,but the extra distance or time required to travel there is outweighed by the extent of commercial activity.The‘gravityfunction”isusedtocalculatearelativeweightingforeachward,basedon theappropriatedemographicvalueassociatedwitheachwardandthegeneral‘cost”oftraveling betweenthesiteandthatward.” 1

4.2.3 Tripratesfromthenewdevelopmentsarebasedontheinputsdetailedintable4.1.Thetraffic generationfromeachofthesitesiscalculatedusing‘appropriatestandardtriprates’.

4.2.4 One of the advantages of PENELOPE is that it allows sites to ‘interact’ with each other and recognizesthattherewillbearelationshipbetweennewhousingandemploymentsitesandthe existingworkplaceandresidentpopulations.Thisisachievedbyatemporarymanipulationofthe census data when multiple sites in PENELOPE are being assessed. As a consequence of this feature, the sites in each PENELOPE run in the Central Lancashire will display a level of interaction.

4.2.5 When the model hasbeen run PENLOPE generates twodigital map data layers.The first layer details trips at a ward level and is therefore useful in assessing which wards will generate additionaltrafficwhenthedevelopmentsarecomplete.Thesecondlayerassignsthesetripsto specific links within the highway network, which can be used for identifying hotspots and developmentconstraintsinthenetwork.

4.34.34.3 Limitations of PENELOPE

4.3.1 PENELOPE does not take into account modal changes to public transport that could arise asa resultofaplanningconditionplacedonasite.Asaconsequence,theforecastnumbersoftrips ontheStrategicHighwayNetworkasidentifiedfromthePENELOPEoutputarelikelytobelower inpractice,duetotheuseofpublictransportaswellasothersustainablemodes.

4.3.2 PENELOPEanalysisis limited to the classified roadnetworkandcertain essential nonclassified links.Atthesametimeeachwardandeachsiteonlyhasasingleconnectorlinktothenetwork. In reality, a large development might have several access/egress points. This means that site access links can have very high levels of additional traffic in PENELOPE because traffic is effectively channeled onto these links, though in reality this traffic would be dispersed over severalaccesspointse.g.Buckshaw.

4.3.3 ItisonlypossibletomodeleightsitesinonerunofPENELOPE.Thismeantinordertoassessall ofthesites,tworunswererequired–oneforthesitesinPrestonandasecondforthesitein Chorley and South Ribble. This means that only sites in the same run will interact with each other.RunswerealsoonlycarriedoutfortheAMpeak.Despitetheselimitations,PENELOPEis still useful as a broad indicator of future highway constraints and to identify potential pinch points/hotspotsontheexistingroadnetwork.

1Taken from PENELOPE Summary Specifications, User Guide, and Performance Report 2008

CentralLancashireTransportStudy 4.2 4 Development Sites

4.44.44.4 Baseline Traffic Conditions – Highway Stress Maps (2007)

4.4.1 Highwaynetworkstressmapsaredesignedtoshowcapacityissuesor‘stresses’onselectlinksof thehighwaynetwork,whichisimportantparticularlyasPENELOPEdoesnotincludebaselineflow data.

4.4.2 Aspartofthisstudyhighwaystressmapshavebeencompiledbasedoninformationtakenfrom 58sitesaroundCentralLancashire.

4.4.3 Thehighwaystressiscalculatedusingthefollowingmethod:

flow capacity 4.4.4 Whereflowisthetrafficflowalongtheselectedlinkandcapacityisthehighwaycapacityforthat link.

4.4.5 Thetrafficflowinputsforthecalculationcamefromtrafficcountdatacarriedoutmainlyin2007 and provided by Lancashire County Council and the Highways Agency (for the motorway network). The Highway capacity for each of the sites was based on guidelines taken from TD20/85(DoT,1985).

Table 4.1 Highway capacity

Road Type Lanes Capacity (per hour)

Motorway 8 16000

Motorway 6 12000

Motorway 4 8000

DualCarriageway 4 6400

SingleCarriageway 4 5600

WideSingleCarriageway 2 2500

StandardSingleCarriageway 2 2000

4.4.6 Traffic flows inpeaksperiods, particularlyaroundurban centres, tendto be tidal in nature i.e. higherinonedirectionthantheother,andhenceinboundlanescanbesubjecttocapacityissues whilsttheoutboundlanesshownocapacityissues.PENELOPEdoesnotmakethisdistinctionand thereforeforconsistency,wehavepresentedtrafficflowsinbothdirections.

CentralLancashireTransportStudy 4.3 4 Development Sites

4.4.7 Thestressmapsareusefulingivingbroadindicationsofhighwaycapacityissues.However,as road capacity is determined by junction and link capacity, much more detailed analysis incorporatingjunctionassessmentswouldberequiredtosaywithcertaintywhereroadcapacity isbeingreachedorexceeded.

4.4.8 ThemapsarepresentedinAppendixAFigureA.1.

4.54.54.5 Future Traffic Growth with no Development Scenario - (2018 and 2028)

4.5.1 The maps were created using a similar method to the one outlined above, the only difference beingtrafficflowswerefactoredupfromthebaseyearof2007toreflecttrafficgrowthby2018 and2028.ThisgrowthwascalculatedusingTEMPROforecasting.

4.5.2 TEMPROfactorspresentsbenefitsoverothertrafficforecastingmethodssuchasNationalRoad TrafficForecasts(NRTF)andthenewNationalTrafficModel(NTM)becauseitprovidesfactorsfor differenttimesofthedayandfordifferentlocalauthorities.

4.5.3 The locationofthetrafficsurvey site determined theTEMPROfactor used.For A, B roadsand unclassified roads the local authority TEMPRO factor was used, traffic counts on the motorway networkwerefactoredbytheNorthWestregionfigure,astheseroutesaremuchlessaffectedby localdifferences.

4.5.4 TheTEMPROfactorsusedaredetailedinthetable4.2.

CentralLancashireTransportStudy 4.4 4 Development Sites

Table 4.2 TEMPRO factors (base year 2007)

Area Year Growth factor (time period)

Chorley 2018 1.053(AM)

1.065(PM)

2028 1.094(AM)

1.113(PM)

Preston 2018 1.052(AM)

1.063(PM)

2028 1.093(AM)

1.111(PM)

South Ribble 2018 1.057(AM)

1.073(PM)

2028 1.103(AM)

1.130(PM)

North West Region 2018 1.070(AM)

1.074(PM)

2028 1.114(AM)

1.120(PM)

4.5.5 Themapsshowinglinkcapacityissuesforfuturetrafficintheabsenceofanydevelopmentare presentedinAppendixBFiguresB.1–B.2

4.64.64.6 Development Scenario - 2018

4.6.1 Thedevelopmentsitesprovidedforinclusioninthemodelrunswerethoseagreedwiththeclient anditwasassumedthatthesiteswillallbefullydevelopedby2018(AppendixCFiguresC.1– C.4).Thesitetype,location,areaanddwellingswerethebasedatainputtedintothePENELOPE runs.Detailsofthesitesandassociatedlandusesareshownintable4.3.

CentralLancashireTransportStudy 4.5 4 Development Sites

Table 4.3 Development Sites – 2018 Scenario

Site Name Site Type (land Location Area Dwellings (Model Run) use class) (hectares)

BuckshawVillage Mixed(mixedres. Edgeoftown 29* 2785 (Ch/SR) andB2)

SouthofWade Housing(mixed Edgeoftown 900 Hall(Ch/SR) residential)

MossSide Housing(mixed Edgeoftown 639 (Ch/SR) residential)

Farington Housing(mixed Edgeoftown 2101 (Ch/SR) residential)

CuerdenRegional Employment(B2) Edgeoftown 65* BusinessPark (Ch/SR)

AdjScepture Employment(B1) Edgeoftown 4.8* Point(Ch/SR)

PickeringsFarm Housing(mixed Suburban 1000 (Ch/SR) housing)

LostockHall Housing(mixed Suburban 940 Gasworks housing) (Ch/SR)

SamlesburyBAE Employment(B1 Edgeoftown Grossfloorarea development(Pr) andB2) 39048sqm(B1)

57884sqm(B2)

PrestonEast(Pr) Employment(B2) Edgeoftown 35*

Whittingham(Pr) Housing(mixed Edgeoftown 650 housing)

Broughton Mixed(mixed Suburban Grossfloorarea 70 BusinessPark housing,B1andB2) 25500sqm(B1) (Pr) 6600sqm(B2)

CottamHall(Pr) Housing(mixed Suburban 1464 housing)

PrestonCBD(Pr) Employment(B1) Towncentre Grossfloorarea

135700sqm

CentralLancashireTransportStudy 4.6 4 Development Sites

Tithebarn(Pr) Mixed(mixed Towncentre GrossFloorArea 1380 residential,B1,non 9300sqm(B1) foodretail,sports 60000sqm centre) (nonfoodretail)

14000sqm (sportscentre)

*indicatesthisisoverallsitearea,notfloorspace

4.6.2 Forsomeemploymentsitesanestimateoftotalfloorspacewasnotavailable,forthesesitesa figure forthe total sitearea inhectareswasprovided.For these sitesPENELOPEautomatically performsa calculation togiveanestimateofthe gross floor area. Thesesites areindicated in table4.3withanasterisk(*).

4.6.3 When inputting development site information, the following assumptions were made about the characteristicsofeachsite:

 Forhousingsites,the‘mixedresidential’optionwasused.Duetothescaleofthehousing schemesbeingpromoted,andpayingattentiontogovernmentpolicyregardinglargescale housing schemes, it was prudent toassume thata mix ofunits and residents would be prevalentinanyhousingsitesbeingdeveloped;

 WhereB1,B2orB8useclasseswereidentified,thesewerereplicatedwithinPENELOPE;

 Wherenofixedquantumofdevelopmentwasstated,thehighergeneratinguseclasswas used(i.e.ifacombinationofB2/B8foracertainnumbersofhectareswasstatedbutno percentagespiltofthetwouseclasses,100%B2wouldbeassumedasthisisthehigher generatoroftrafficinthepeakperiods);

 Where a retail allocation was identified, the nonfood retail category in PENELOPE was selected;

 OnlytheAMPeakwasassessedintermsoftripgeneration;

 The Lancashire Waste Technology Park was not assessed in PENELOPE as the characteristics of this type of development could not be replicatedaccurately within the parametersofPENELOPE.However,duetotherelativeamountoffloorspace/jobstobe providedatthissitecomparedtotheotheremploymentsitescomingforward,itwasfelt acceptable to omit it from the analysis as it would be unlikely to generate substantial volumesoftrafficduringmorningandeveningpeakhours;and

 A30minutetraveltimewasusedforeachsite.Itwasdecidedtousesuchatraveltimeto allow the sites to be accessible by car from the entire CLCR. This drive time zone also allowedpeoplelivinginneighbouringauthoritiestobeincludedinthecatchmentarea,as well as allowing the flow of people to key regional centres such as Liverpool and Manchester. It is accepted that people will not just be confined to their local authority boundarieswhenlookingforemploymentopportunitiesorhousing.

4.74.74.7 Development Scenario -2028

4.7.1 The development sites agreed for inclusionin the2028 scenarioare presented in table4.4. It shouldbenotedthatthesesitesarebasedoninformationthatwascurrentlyavailableatthetime

CentralLancashireTransportStudy 4.7 4 Development Sites

ofthisstudyanditishighlylikelythatgiventhetimeperiodthatsomethesesitesmaynotbe developedbecausetheyarenotcompliantwiththeemergingspatialstrategyorotherplanning policy.

Table 4.4 Development Scenario – 2028

Area Name (HA) Dwellings Landuse TripsArr TripsDep TripsTotal

NorthofLancasterLane 44.6 676 Housing 59 166 226

WhittleleWoods 30.6 504 Housing 44 124 168

Euxton 37 345 Housing 30 85 115

NorthofChorley 16.15 294 Housing 26 72 98

Camelot 1030 Housing 91 253 344

10.2 D2 158 161 319

Camelot 10.2 1030 Mixed 248 415 663

Junction8M61 19.87 N/A B2 297 214 511

GreatKnowley/BotanyBay 17.92 N/A B2 268 193 461

M61/M65 54.99 N/A B2 823 591 1414

EastofM61 13.89 N/A B2 208 149 357

LeylandSouth 23.6 N/A B2 353 254 607

SouthRings 8.4 N/A B1 285 62 347

Dunbia 3.4 N/A B2 51 37 87

LimeKilnFarm N/A 204 Housing 18 50 68

R/oChurchLane N/A 317 Housing 28 78 106

ArlaFoods N/A 165 Housing 15 41 55

BrindleRoad N/A 650 Housing 57 160 217

Lightfoot 194.5 2917 Housing 257 718 974

Broughton 52.2 825 Housing 73 203 276

Goonsnargh 43.5 725 Housing 64 178 242

CentralLancashireTransportStudy 4.8 4 Development Sites

Area Name (HA) Dwellings Landuse TripsArr TripsDep TripsTotal

Longridge 18.9 284 Housing 25 70 95

Grimsargh 13.9 208 Housing 18 51 69

Lea 12 181 Housing 16 45 60

4.84.84.8 Summary of Outputs

4.8.1 The final stress maps have been created in an attempt to give a best estimate of traffic levels in 2018 and 2028 if the current proposals for development are implemented (see AppendixDFiguresD.1D.4).

4.8.2 For 2018, flows from the PENELOPE runs were combined with the TEMPRO factored base flows to create an overall flow. Unfortunately only a maximum of eight development sites canbeincludedinanyonePENELOPErunpreventinganyinteractionbetweendevelopment sites in Preston and those in Chorley/South Ribble. This also means separate maps have beenproducedfortheChorley/SouthRibblePENELOPErunandthePrestonrun.

4.8.3 ThetwoPENELOPErunscarriedoutfor2018,showlargeincreasesintrafficonthefollowing links:

 A59andotherroutesaroundSamlesburydevelopment;

 Prestonringroad(B6241),northofPreston;

 M6betweenJ29andJ32;

 A6fromcentralPrestonsouthwardstoBamberBridgeandChorley;

 A582/B5253FlensburgWay/PenworthamWayshowlargetrafficincreasesactingasa northsouthlinkinthewestofCentralLancashireandaneastwestlinkacrossSouth Ribble;and

 BuckshawVillageisalargegeneratorofextratrafficonboththelocalnetworkandthe strategic network although this may represent a worst case scenario due to the uncertainties of the extent (in terms of gross floor space) of the employment development.

4.8.4 By2018thefollowingpinchpointshavebeenidentifiedonthehighwaynetwork

 Prestonringroad(B6241);

 M6J30J32;

 Prestonradialroutes,particularlythoseclosetomotorwayjunctions;

 PenworthamWay/FlensburgWay(A582/B5253);and

 A6betweenChorleyandBamberBridge.

CentralLancashireTransportStudy 4.9 4 Development Sites

4.8.5 Due tothe turnaroundtime neededto completea run of PENELOPE it wasnotpossible to complete PENELOPE runs for the 2028 development scenarios. However it was still felt importanttoexaminethe2028developmentscenariosandfromthisderiveabestestimate ofhighwaystressesin2028.

4.8.6 Themethodforcreatingthebestestimateutilisesthe2007trafficdata,datafromthe2018 PENELOPErunandtrafficgenerationfiguresforthe2028developmentscalculatedusingthe TRICSdatabase.

4.8.7 TEMPRO factored base flows were added to the 2018 PENELOPE flows to give a total backgroundflowfor2028.

4.8.8 Trafficgenerationforeachofthe2028siteshasbeencalculatedusingtheTRICSdatabase. Unfortunatelyitwasnotpossibletodistributetraffictothehighwaynetworkfromthe2028 developments in any sort of meaningful way, so instead each site has been labelled with arrival,departureandtotaltrafficgenerationfigures.

4.8.9 Thenatureofthismethodandthetimescalebeingconsideredmeanforecastscanonlybe takenasabroadindicatoroffuturetrafficlevels.

4.8.10 Backgroundtrafficflowsfor2028showthesamehotspots as 2018,although traffic levels willbehigherin2028.Takingintoaccountthelocationofthe2028developmentsandtheir trafficgeneration,thefollowinglinksarelikelytofacecapacityissues:

 A6 and B6241 (Lightfoot Lane) will act as the main access roads for the Lightfoot and Broughtondevelopmentsiteswhichbetweenthemwillgeneratemorethan1,000vehicle tripsintheAMpeak,evenwithoutthesedevelopmentstheseroadswouldbeatorclose tocapacity;

 B5253–capacityissueshavealreadybeenidentifiedtothenorthofLeylandonFlensburg Way,withtheSouthLeylanddevelopmentgeneratingintheregionof600700additional tripsintheAMpeakthesouthernsectionoftheroutemayalsobecomemorecongested; and

 MostoftheChorleyandSouthRibble2028developmentsarelocatednexttomotorway junctions.Thispresentsobviousadvantagestodeveloperswhohaveconvenientaccessto thenationaltrunkroadnetwork,butitcanmakepredictingtrafficgrowthmoredifficultas nationaltrendshaveagreaterbearing.Despitethisuncertaintyitisimportanttoensure locally that spare capacity exits in the network to allow easy and fast access to the motorways.

4.94.94.9 Summary of Issues on Key Corridors

4.9.1 An overview of each of the key corridors in the study area is presented below with some commentarytoidentifycongestionissueswhicharelikelytoemergeoverthenextdecadedueto increasedvolumesoftraffic,generatedfromproposednewdevelopmentandgrowthinexisting backgroundtrafficflows.

4.9.2 TrafficcountsandaveragetrafficspeedscomefromsurveydatacollectedbyLancashireCounty Council in 2007. Traffic forecasts were calculated using TEMPRO factors and the data output fromthePENELOPEgravitymodellingsoftware.

CentralLancashireTransportStudy 4.10 4 Development Sites

A59 Eastern corridor

 Congestion problems arise when the A59 reduces in width from a 2lane dual carriagewaytoa3lane(2lanestowardsPrestonontheinclinefromtheRibble)single carriagewayattheRiverRibbleBridge;

 AlthoughaconsiderableamountoftrafficapproachingfromtheeastleavestheA59at theM6junction,alargevolume(1175vehiclesinAMpeakhour)oftrafficcontinues towardsPrestonCityCentre.ThissectionoftheA59isthemaingatewayintoPreston fortrafficfromtheM6;

 Averagespeeddecreasesto08mphintheAMpeakbetweenjunction31oftheM6 andtheA5085(BlackpoolRoad)junction;and

 AstheA59approachesPreston,thecarriagewaybecomesnarrowerandtherearean increasing number of side roads, frontage activity and pedestrian conflicts. These factorscontributetofurtherreduceroadcapacityandsubsequentlycontributetothe levelsofcongestionwhichoccurinpeakhours.

B6243

 TheroutelinksthecommunitiesofLongridgeandGrimsarghwithPreston;

 AtatrafficcountlocationjustinsidetheM6,692vehicleswererecordedheadingina southwesterlydirectionintheAMpeak.Averagespeedsforthissectionarecurrently 1520 mph in the AM peak. Forecasts which include PENELOPEflows suggest traffic couldincreasetoover1,200vehiclesby2018.Suchanincreasewouldtaketheroad above its design capacity, significantly impacting on average speeds and creating considerabledelaysandcongestion;and

 BythetimetheB6243hasreachedtheA6atPrestonPrisonaverage trafficspeeds have decreased to between 8 and 15 mph, effecting traffic in both directions. This junctionwasidentifiedbybusoperatorsasacongestion‘hotspot’.

B6242/A6063

 Servesas the main link between M6 J31a andPrestonCityCentre.Also gives good accessfromtheM6tothenortheastofPreston;

 DuringtheAMpeak,averagespeedsarealreadylessthan20mph;and

 TheA6063joinstheB6243atPrestonPrisonwhichmeansvehiclesareaffectedbythe congestionhotspot.

A6 North (Garstang Road)

 ServesasthearterialcorridorlinkingPrestoncitycentretothevariousdistrictstothe northofthecity,aswellasJunction1oftheM55;

 AveragetrafficspeedsonlargesectionsoftheroutebetweenBroughtonandPreston City Centre are between 8 and 15 mph in the AM and PM Peaks. This suggests congestion is already an issue on the road during peak periods. These low average speedseffecttrafficinbothdirections;

 The road is expected to see an increase in traffic, particularly when taking into considerationnewdevelopmentsinPrestonCityCentre,BroughtonandLightfoot.This

CentralLancashireTransportStudy 4.11 4 Development Sites

islikelyto havethegreatestimpactattheM55roundaboutandthejunctionofthe B6241(Eastway);and

 The impacts of congestion are exacerbated by the fact there are a large number of featuresonthesouthernsectionofthecorridorwhichslowtrafficsuchassideroads, residentialfrontagesandpedestriancrossings.

A583

 Unlike most of the other major corridors into Preston city centre, the A583 is dual carriageway until it reaches the edge of the city centre, lessening the impact of congestion on the highway. As a result, average speeds are generally higher than otherradialroutes;and

 Congestionworsensattheedgeofthecitycentreinthesamewayitdoesforallradial routesfromthecitycentre.

A59 West

 Therouteisa2lanedualcarriagewayexceptthesectionthroughHigherPenwortham, where it narrows to single carriageway. On this section there are also side roads, significantfrontageactivityandpedestriancrossings,allcombiningtoreducecapacity significantlyandcreateapinchpointonthenetwork.Thisisreflectedbyanaverage speedof815mphthroughPenworthamtowardsPrestonintheAMpeak;

 By2018anadditional133vehiclesareforecasttotravelthroughHigherPenwortham towardsPrestonintheAMpeak,withoutsomeformofmitigatingmeasuresaverage journeytimeswillincreaseasaveragespeedsdecrease;

 The second potential pinch point on the route is at the River Ribble crossings. Additional traffic from the A582 (Penwortham Way) and the B5254 (Leyland Road) alsousethesebridgestoaccessPreston;

 In the next decade an additional 900 vehicles are forecast to use the Penwortham BridgestocrosstheRiverRibbletoPrestonintheAMpeak.Suchanincreasecould leadto major delaysto trafficand queuing is likely to extend back on to roads the roadnetwork,southoftheriver;and

 The building of a bypass at Penwortham is likely to have a huge bearing on future trafficflowsinthisarea.

A6 South

 The A6 to the south of Preston acts as an important northsouth corridor linking Chorley,BamberBridgeandPreston;

 Severalpointsonthecorridorwereidentifiedbybusoperatorsascongestionhotspots –attheChorleyandSouthRibbleGeneralHospitalroundabout,thejunctionoftheA6 withtheA582andatWaltonBridge;

 Traffic on this corridor is forecast to increase significantly in the next decade, particularlybetweenJunction1AoftheM65andPreston.Thisisalsothelocationof the proposed Cuerden Regional Business Park, creating nearly 7,000 jobs and associatedvehicletraffic;and

CentralLancashireTransportStudy 4.12 4 Development Sites

 Walton Bridge which crosses the River Ribble is expected to be carrying over 200 vehicles above its capacity towards Preston in the AM peak by 2018, leading to increasinglyworsecongestionandincreasedjourneytimes.

B6241 (Tom Benson Way)

 CottamtothenorthwestofPrestonCityCentrehasbeenearmarkedasthelocation ofseveralnewhousingdevelopmentsites;

 TheB6241ringroadalsoactsasalinkinthisareaofPrestontothecitycentreand themotorwaynetwork.Atthepresenttimetherearenomajorconcernsoverhighway capacity;and

 Significant amounts of additional traffic are expected to be using the road by 2018 whennewhousingdevelopmentsatCottamHallandBroughtonarecompleted.This increase is forecast to push the existing road to the limit of its capacity. Further developments are planned for 2028 including the Lightfoot site which could provide around1,000dwellings.Suchadevelopmentwouldbeexpectedtogeneratearound 1,000vehicletripsinthepeakhours.Itisthereforeimperativethatactionistakento encourage the use of more sustainable modes of transport to reduce the impact of these new developments on the local highway network. Even with these mitigating measures it is likely that highway improvements will be needed, particularly to junctionsandtheremaybeaneedtoincreasecapacity.

(A582/B5253)

 AtthepresenttimethislinkactsasanorthsouthcorridortothewestofSouthRibble. Over the nextdecade itsimportance to thearea will increase with at least 4 major developmentsitesincloseproximitytothelink;

 The sites at Farington, Pickering’s Farm, Moss Side and South of Wade Hall could include over 4,500 additional dwellings, which subsequently will generate a large amount of additional traffic. Data taken from the PENELOPE runs forecasts an additional1,000vehicletripsbetween0800and0900ontheB5253andA582outside theFaringtonandPickering’sFarmsites;

 Consideringthecapacityoftheexistinghighwayinfrastructure,thisincreaseintraffic volumesisunsustainable.Therefore,eithermajorhighwayworksareneededincluding road widening, and/or a range of mitigating measures are needed to minimise the impacts;

 Atthemomentpublictransportlinksarerelativelypoorinthispartofthestudyarea. To meet the expected needs of the corridor regular northsouth and eastwest bus services are required. Options for walking and cycling routes should also be consideredinallthenewdevelopments;and

 Highwayimprovementssuchasincreasingjunctioncapacityarealsorequiredtoavoid gridlockonthecorridor.

A6/B5248 (Dawson Lane)/A49/A582/B5254 (Leyland Road)

 Thiscorridorservessomeofthemainpopulationcentresinthestudyarea,aswellas severaloftheproposeddevelopmentsites,andthusisanimportantlocallink;

 At the moment the corridor is relatively free flowing even at peak times, although averagetrafficspeedsdodroponLeylandRoad;

CentralLancashireTransportStudy 4.13 4 Development Sites

 Twoofthebiggest2018developmentsitesareclosetothecorridor.BuckshawVillage which will be a mixed development incorporating nearly 3,000 houses and employment for 7,000 people and the Cuerden Regional Business Park which will createanother6,800jobs;

 Developments of this scale will have major impacts on the highway network. The PENELOPErunsindicatetrafficgenerationofover4,000 2vehiclesintheAMpeakfrom BuckshawVillageand3,000vehiclesatCuerden.Althoughtheproximityofthesesites to the motorway network will limit the impact on the wider network, it is very important that the local network and particularly junctions can cope with this additional traffic, thus ensuring a quick passage from the development sites to the motorwaysandtrunkroadnetwork;and

 Althoughalotoftrafficwillgettoandfromthesitesonthemotorways,asignificant amountofadditional traffic will use localroutes. RoutestoPrestonincludingtheA6 andB5254mayfacecapacityissues,theA6tothenorthofChorleyisalsoforecastto carryanadditional650vehiclesintheAM.

4.10 Modal Shift

4.10.1 In thenext20years if CentralLancashire isto deliver its planned increases in populationand economic growth it will be necessary to ensure that the required transport infrastructure is providedinordertomeettheresultingdemandsfortravel.Satisfyingthisincreaseddemandwill presentamajorchallengetocreateasustainabletransportpolicy,whichcomplieswithcurrent DfTguidelines.Itisnolongeracceptabletoseektosimplyincreasehighwaycapacityinorderto accommodate the forecast growth in car use, as it is necessary to introduce measures which providereal,efficientalternativestotheprivatecarandwhichwillencourageasubstantiallevel of modal shift away from the car. The following paragraphs present a summary of the traffic increaseswhichareforecastforCentralLancashireandthemodalshiftwhichneedstotakeplace inordertoavoidfuturecongestionandhighwaycapacityproblems.

Evidence of modal shift

4.10.2 InDecember2004theDepartmentforTransportproducedadocumententitled Bus Priority: The Way Ahead whichlookedattheevidenceproducedfromarangeofmeasuresaimedatreducing trafficflowsandjourneytimesandidentifieddetailsoftherecordedmodalshiftawayfromthe car. A similar exercise was also conducted by South Yorkshire Passenger Transport Authority (SYPTA).Table4.5givesasummaryofthekeyfindingsfromthesereports.

Table 4.5 Modal shift

Scheme (location) % reduction in Modal Shift from Reduction in vehicle flow car journey time

Bus lanes (A47 17%(AMpeak) N/A 2223% HinckleyRoad, 15%(PMPeak) Leicester)

2AtthetimeoftheassessmenttheextentoftheemploymentdevelopmentswereuncertainforBuckshawandCuerdenthereforethe tripestimateswerebasedonsiteareasandnotgrossfloorspace.Therefore,thetripestimatesrepresentaworstcasescenario.

CentralLancashireTransportStudy 4.14 4 Development Sites

Showcase routes N/A 613% N/A (variousWest Midlands)

Greenway bus lanes Upto10% 4%(increasein N/A inc. bus priority buspatronage) (Edinburgh)

Guided Busway 1314% N/A 710%inpeaktimes (Bradford)

Town Centre Traffic 1216% N/A 5% Management (West Bromwich)

High Occupancy Initialreductionsin Averagecar Lanes (A647,Leeds) flows,althoughthis occupancyrose wasputdownto from1.35people peopleavoidingthe to1.51people road,trafficlevels havereturnedto oldlevels.

Park and Ride Over20% N/A Sameforcars (Leicester) Busjourneytimes reduced

4.10.3 AstudycommissionedbySouthYorkshirePassengerTransportExecutive(SYPTE)foundthat based on existing Quality Bus Corridors (QBCs) a combination of bus lane provision, new vehiclesandintegratedsmartcardticketingcouldseea24%increaseinbuspatronage.A further 3% growth could be achieved with dedicated high quality routes through the city centre.

4.10.4 Itbecomesevidentfromthetableabovethatdifferenttypesofschemesandlocalconditions leadtovariationsinthesuccessofbusprioritymeasures.Howeverthecommonfeatureis that schemes in the vast majority of cases lead to some reduction in traffic flows and a modalshiftfromcars.

4.10.5 Furthertotheevidenceofmodalshiftinthecasestudiesabove,LancashireCountyCouncil havedrawnupanumberoftargetswhichappearintheJointLancashireStructurePlanand theDraftLancashireWalkingStrategy,namely;

 Constructionof8newparkandridesinLancashireby2016;

 90%ofnewdevelopmenttobewithin400metresofanexistingorproposedbusstop orwithin800mofanexistingorproposedrailwaystation,20012016;

 Rail patronage from stations in Lancashire to increase by 75% from 2001 levels by 2016;

CentralLancashireTransportStudy 4.15 4 Development Sites

 BusjourneyswithinLancashiretoincreaseby20%from2001levelsby2016;

 Maintainorincreasethepercentageoftheworkingpopulationwalkingtoworkandto decreasethemodalshareofschoolchildrenbeingtakentoschoolbycar;and

 A25%increaseincycleflowsfrom2002levelsby2011.

Central Lancashire

4.10.6 Thissectionlooksatdatafromthehighwaystressmapswhichincludebackgroundtrafficflows factoredupto2018levelsandtrafficfromthePENELOPEruns.Theaimistoassesswhichparts ofthenetworkwillcomeunderparticularstressinthefutureandwhethercapacityissuesmay develop. The locations of the survey sites can be seen in figure 4.1 which are sites that are continuouslymonitoredbyLancashireCountyCouncil,trafficflowsforeachsitearesummarised intable4.6.Allofthesitesinfigure4.1areontheoutskirtsofPrestonbasedontheassumption thatPrestonwillbethemaindestinationforemploymentwithinthesubregion.

Figure 4.1 Location of traffic surveys

4.10.7 Whenexaminingthisdataitisimportanttorememberroadcapacitiesareindicativeonlyand based on estimated link capacity. PENELOPE forecasts are based on the planned 2018 developmentsites.

CentralLancashireTransportStudy 4.16 4 Development Sites

Table 4.6 Summary of 2018 traffic

Road (traffic Difference in traffic Percentage link is Under (-)/over (+) survey reference between 2007 and under (-)/over capacity with 10% number) 2018 (peak (+) capacity modal shift from direction flow) car

A59(1) +98 +6% 11%

A675(2) +31 66% 71%

A6(3) +880 24% 37%

B5254(4) +196 19% 44%

A582(5) +694 +48% +24%

A59(6) +133 27% 39%

A583(7) +168 39% 49%

B6241(8) +355 14% 28%

B6241(9) +359 30% 41%

A6(10) +412 1% 17%

B6241(11) +520 +44% +21%

B6242(12) +662 +35% +13%

B6243(13) +572 +5% 12%

4.10.8 Inadditiontothesitesintable4.6,anumberofotherlinkshavebeenidentifiedduringthe course of the study which could present capacity issues in the future. These tend to be aroundnewdevelopmentsitessuchasBuckshawVillageandontheB5253.

4.10.9 It is therefore important that these developments are taken forward with this in mind. Provisionforwalkingandcyclingshouldbeincorporatedintheplanningofthesiteandpublic transportprovisionshouldbeconsidered.

4.10.10 Whenthesiteopensitisimportanttotryandgetresidentsoremployeestousesustainable modesfrom day one,which should beeasierthantryingtoaffectamodalshiftatalater date. At the development stage this means undertaking travel planning and publicising modesoftransportotherthancar.

CentralLancashireTransportStudy 4.17 4 Development Sites

4.11 Modal shift away from car travel

4.11.1 Basedon2001journeytoworkCensusdata,thecurrentmodalshareforcardriversis61%. Forthisstudywehaveassumedthismodalsplitappliestoalljourneystypes.

4.11.2 Amodalshiftawayfromthecarof20%wouldbringalltheroadsinthissurveybackdown undercapacity.Howevertoachievesuchashiftin10yearsisunrealistic.Insteadashiftof 10percentshouldbetargeted.

4.11.3 Ashiftof10percentwouldrequirea20percentincreasefromeachoftheothermodesa figurewhichisbroadlyinlinewithLancashireCountyCouncil’stargetsforincreasingbusand cycletravelforthetotaltransportnetwork.

4.11.4 Inordertoachievethismodalshift,anincreaseinbususe,carsharingandwalkingwillbe ofgreatimportance,asthesethreemodesmakeupalargeproportionofjourneystowork thatarenotbycar.

4.11.5 For shorter journeysof under 2km, walking and cycling needto be made as attractive as possible.Pathsneedtobewellmaintained,safe,directandwherepossibleseparatedfrom vehicletraffic.Walkingtoschoolalsoneedstobeencouraged,whichwilltakevehiclesofthe roadinthepeakhours,particularlyinthemorningandhastheaddedbenefitofimproving children’shealth.

4.11.6 Car sharing, particularly on the journey to work can be encouraged in a number of ways including guaranteed lifts, priority parking, incentives and high occupancy vehicle (HOV) lanes.HoweverwiththeexceptionofHOVlanes,carsharinginitiativesrequirecooperation withlocalbusinessestoensuretheyencouragetheirstafftocarshare.

4.11.7 If a 10 percent modal shift is achieved it would go some way to alleviating congestion hotspotsandspeedingupjourneytimesonthehighwaynetwork.

4.11.8 Onsomeroutestrafficwillincreaseinthenext10yearsduetolargenewdevelopmentsand population increases, meaning congestion problems may still exist in the peak hours, althoughitislikelythesewouldbeforshorterperiodsandlesssevere.

4.11.9 The routes that are likely to see the greatest increase in traffic and potentially highway capacityproblemsare:

 The A582 Penwortham Way and B5253 Flensburg Way as a result of developments aroundMossSide,PickeringsFarmandFarrington;

 B5248DawsonLaneandA49WiganRoadresultingfromBuckshawVillage;

 A6 Garstang Road and B6241 to the north and west of Preston as a results of developments a Whittingham, Cottam and some longer term potential development sitesemergingfromtheLDFsitesuggestionprocess;

 A6LondonWaytothesouthofPrestonresultingfromcitycentredevelopments;and

 LinkstotheeastofPrestonincludingtheB6242BluebellWay,B6243LongridgeRoad andtheA59BrockholesBrowasaresultofdevelopmenttotheeastofPreston.

CentralLancashireTransportStudy 4.18 4 Development Sites

4.11.10 Itisthesecorridorswherethemostemphasisneedstobeplaced.Itmightbenecessaryto undertake highway modifications and improvements to increase capacity but is also importantthatalternativestothecarareavailableandtheiruseencouraged.

4.11.11 Asalreadyexplaineditisimportantthatnewdevelopmentsareaccessiblebymodesother thanthecarfromdayoneandthatusersofthesites are aware of these alternatives.To achievethiscooperationwithdevelopers,localtransportoperatorsandtheactualusersofa site,whethertheyareresidentsorbusinesses,isofparamountimportance.

Additional Buses Required

4.11.12 Bususeneedstobeseenasaviablealternativetothecar.Thismeansservicesneedtobe reliable, frequent, direct and serve areas that people need to travel to. Measures such as high quality corridors and park and ride schemes would help in the delivery of bus user targets.

4.11.13 Table E.1 in Appendix E shows the estimated modal splits based on the additional traffic generatedbybothdevelopmentsitesandalsofactoredtoallowfornaturaltrafficgrowthin the am peak. The difference between the 2018 and 2007 flows has then been distributed acrossthemodesaccordingtocensusdatasplits.

4.11.14 Theadditionalnumberofbuspassengersthatarelikelytotravelhasthenbeendividedby 80(thecapacityofadoubledeckerbus)togiveabroadindicationoftheextranumbersof busesrequiredduringtheampeak:

3 Additional Buses

 A6LondonWay

2 Additional Buses

 A582PenworthamWay;

 B6241Eastway;

 B6242AndertonsWay/LongsandsLane;and

 B6243LongridgeRoad.

1 Additional Bus

 B5254WatkinLane;

 A583BlackpoolRoad;

 B6241TomBensonWay;

 B6241LightfootLane;and

 A6GarstangRoad.

CentralLancashireTransportStudy 4.19 4 Development Sites

4.12 Buckshaw Village

4.12.1 DataprovidedbyEnglishPartnershipssuggestthatBuckshawcouldpotentiallyseethecreation of 7000 jobsin addition to the3000 dwelling proposed forthis site,whichwouldresultin the generationofasignificantamountofnewtrips.BasedontripforecastsasprovidedbyPenelope thiscouldbeintheregionofanadditional4000trips.Forthesetripstobeaccommodatedby publictransportanadditional18buseswouldberequiredbasedonthemodalsplitsasshownin Table4.7

Table 4.7 Estimated Modal Splits for Buckshaw Village (based on Census 2001)

Generated Work Bus Train M/C Cycle Walk Other Additional Trips from Buses home

4370 755 1457 270 162 324 1295 108 18

4.12.2 Buckshawiscurrentlybeingservedby2busesperhourwiththepotentialofthisbeingincreased to4busesperhour.

CentralLancashireTransportStudy 4.20 5 TransportStrategy

5.15.15.1 Introduction

5.1.1 This chapter of the report describes the policies, strategies and measures that we are recommendingshouldbeimplementedtosupportthefuturedevelopmentandplannedeconomic growthacrossthestudyarea.

5.1.2 Thestrategyisbaseduponthefollowinghierarchyofusers:

 Vulnerableuserse.g.Pedestrians,cyclists,peoplewithdisabilities;

 PublicTransport;

 Freight;

 Motorcycles;and

 Cars.

5.1.3 The strategy presented below represents an overarching high level strategy for Central Lancashireasasingleentity.

5.25.25.2 Transport Vision

5.2.1 IfCentralLancashireistofulfilitsaspirationsforeconomicgrowthanddevelopment,accessibility needstobeimprovedacrossallmodes.Thiswillinvolvebothoptimisingtheuseofthecarand providingalternativestosingleoccupancycartravel.

5.2.2 Specificallythetransportvisionseeksto:

 Provide high quality and flexible transport networks that can respond to changes in developmentandthelocaleconomy;

 Integrate land use and transport policy through a partnership that involves local planningauthoritiesandthetransportauthority;

 MaketravelwithinCentralLancashiresaferforall;

 Promote choice to local residents by providing alternatives, particularly for those withoutaccesstoacar;and

 Reducetheimpactthattransporthasontheenvironmentbymaximisingtechnological advancesandmakingbetteruseofresources.

5.35.35.3 Problems and Issues

5.3.1 ThereareanumberofproblemandissuesthatthetransportstrategyforCentralLancashirewill needtoaddress.

5.3.2 InSouthRibbleandChorleycarownershiplevelsarehigherindicatingahigherdependenceon thecarforjourneystoworkandothertrips.Whilstcarownershipisnotnecessarilyaproblemin itsself,dependencyonthecarcanbeamajorcontributortocongestionandsubsequentlyplaces increasedpressureonresidential,workplaceandtown/citycentreparking.

CentralLancashireTransportStudy 5.1 5 Transport Strategy

5.3.3 Thestudyareaisalsowellservedbyanumberofprincipleroadsmakingdrivingeasierandmore attractive than alternative modes and this is also further compounded with out of town developments that are easier to access by car. Some of these roads also form barriers to communities,pedestriansandcyclists,givingrisetoseverance.ForinstanceBamberBridgefeels disconnectedfromtherestoftheBoroughasitisboundedbythemotorwayandtheA6.

5.3.4 The approach routes into Preston are already experiencing capacity problems during peak periods,particularlyatpinchpointssuchasrivercrossingsandthisisforecasttogetworse(See Table 4.6). In Chorley and South Ribble congestion tends to be more localised and often associated at specific junctions e.g. Chorley Hospital, Tardy Gate. Congestion can have a negativeimpactonthelocaleconomyasitaffectsthereliabilityofemployeesbeingabletoget to work on time, it can have a negative impact on retail as visitors may decide to go to alternative retail centres that are easier to access and congestion can also have a negative impactofthedeliveryofgoodsandservices.

5.3.5 A pattern of development that tends to focus on developing land around motorway junctions placesincreasedpressureonthelocalmotorways.TheM6betweenBroughtonandjunction31is nearing capacity and therefore any future developments will need to consider mitigation measurestominimisetheimpactonthestrategicroadnetwork.

5.3.6 Preston has a well developed network of local bus services and some of these have been improvedthroughaprogramofqualitybuspartnerships,andDfTKickstartfundingenabledthe introductionoftheOrbitservices.Primarily,thenetworkhasbeendevelopedtoservethelocal marketofPrestonthoughtherearesomeinterurbanservices,whicharegenerallyoperatedbya differentoperator.

5.3.7 InChorleyDfTfundinghasalsoenabledtheintroductionofNetworkChorley.Whilstthenetwork hasseenincreasesinpatronageitisunlikelythatitwillbecommerciallyviablebytheendofthe DfTfundingperiod,sotheexitstrategywillinvolvecontinuedfinancialsupportfromLancashire CountyCouncilinconjunctionwithanetworkreviewtoensurethatservicesareoperatingwithin financialconstraints.

5.3.8 SouthRibbledoesnothaveitsownlocalbusnetworkasalltheserviceswiththeexceptionofthe SouthRibbleFlexibus,passthroughSouthRibbleeitherontheirwaytoPrestonorChorley.The eastwestconnectionsbypublictransportwithintheboroughtendtobepoor.

5.3.9 Thereisnonetworkorjointticketinginitiativescurrentlyinoperationwithinthestudyarea(not evenonservicesoperatedbymorethanoneoperatore.g.Service109operatedviaBuckshaw). Thenorthsouthbusroutesbetweenthemainurbanareasarefairlywellestablishedbutthese are often not the most direct routes and journey times when compared to car trips are not attractive.

5.3.10 The key bus issues and the existing high frequency routes are summarised on Figure F.1 in AppendixF.

5.3.11 Railstationssufferfromvaryingdegreesofaccessissuesthatrangefromlackofassociatedcar parkingtopoorpedestrianandcyclinglinksbetweenthetown/citycentresandemploymentarea e.g.BamberBridge,UCLAN.TherearealsocapacityissuesonrailservicestoManchesterandthe timingsbetweenTranspennineandNorthernRailserviceswouldbenefitfromreviewinginorder to provide a more attractive offer for users as sometimes there are only 5 minutes between services.

CentralLancashireTransportStudy 5.2 5 Transport Strategy

5.3.12 Cycling and walking will offer more benefits for shorter journeys, but if such modes are to be encouragedthentherespectiveinfrastructureneedstoreflectthis.Thiswillinvolvemakingurban centres and residential streets moreattractive for walking and cycling. Cyclists and pedestrian naturaldesirelinesareoftenconstrainedbytheorientationoftheroadnetworkcreatingbarriers anditwillbeimportanttointroducemeasurestoovercomesuchobstacles.

5.45.45.4 The Package of Measures

5.4.1 Withinthestudyareatripsbycarhavecontinuedtohavetheadvantagetosuchanextentthat othermodesoftransporthavebecomerelativelylessattractivebycomparison.Iftheimbalance is to be readdressed then radical improvements to infrastructure, improvements to transport services complemented by a mix of incentives and disincentives need to be implemented to ensure that the existing congestion issues do not get worse and that the residents of Central Lancashire are able to access a range of complimentary transport alternatives and make informedchoicesabouthowtheychoosetotravel.

5.4.2 Therefore, the proposed transport strategy for Central Lancashire comprises of a package of measures aimed at addressing the problems and issues that have been identified during the courseofthisstudy.Themeasureswillinclude:

 Publictransportimprovements;

 Highwayimprovements;

 Cyclingandpedestrianmeasures;

 TravelPlanmeasures;

 Demandmanagementmeasures;and

 Improvementsforfreight.

5.4.3 Thestrategywillneedtopresentamixofshort,mediumandlongtermmeasurestoensureon going public and political support. In order to give some sense of priority schemes have been identifiedthatcouldbedeliveredinthe:

 Shortterm–between2008and2013;

 Mediumterm–between2013and2018;and

 Longterm–between2018and2028.

5.4.4 Themeasuresproposedneedtobecomplimentaryanddeliveredinaholisticmannersoasnotto promotecompetitionbetweendifferentmodese.g.railandbus.

5.4.5 Themeasuresoutlinedbelowareinitialschemesuggestionsforfurtherconsiderationandarenot finaliseddetailedschemedesigns.

5.55.55.5 Rail Improvements

5.5.1 There are a number of common access issues occurring at most rail stations within the study areaandmeasurestobeintroducedinclude:

 Increasedparkingsupplyatstations;

CentralLancashireTransportStudy 5.3 5 Transport Strategy

 Greaterpriority/provisionforpedestriansandcyclists;and

 Betterintegrationwithbusservices.

5.5.2 The issues and suggested improvements for individual rail stations within the study area are presentedinTable5.1.

CentralLancashireTransportStudy 5.4 5 Transport Strategy

Table 5.1 Rail Stations – Suggestions for Improvement

Station Problems/Issues Potential Comment Solution

Preston Parkingcapacity Virginare GettingtoPrestonStationbycar progressinga canbedifficultduetocongestion schemeto onthewidernetwork provideanew multistoreycar park

Poorimage ImageofPreston PrestonRailStationisamajor Stationneedsto gatewaytothesubregion reflectHighTech aspirationsofthe CBD

AccessibilityHeavy Prestonstation Networkrailaredeveloping pedestriantraffic needstobe proposalstoupgradepassenger andthestairsonthe accessibleby operatedliftsandsubways ButlerStreet cyclistsand Footbridgeisa pedestrians particularproblem particularlythe mobilityimpaired.

Platforms1&2 Relocate Thishasbeenidentifiedinthe whichconnect temporary Lancashire&CumbriaRUS Blackpoolandthe structuresto Airportarecluttered createmore withcafesand spaceonthe portacabins platform

Leyland Largegapsbetween Reducegap Thisiscurrentlybeing thetrainand betweenplatform investigated platforms andtrain

Generallow Improvethe standardoffacilities, standardof lackofrealtime facilitiestogive information,poor thestationahigh qualitysheltersetc quality appearance

Poorconnectivity Improved betweenthestation pedestrian andthetown signage

Nodisabledaccess. Provideaccessfor Onlyaccessbetween thedisabled

CentralLancashireTransportStudy 5.5 5 Transport Strategy

Station Problems/Issues Potential Comment Solution

platformsisviaa footbridgewith steps

Lackofsecure Providecycle parkingforcyclists lockers

Lackofparking Increaseparking SRBCareindiscussionswith provision capacity NorthernRailregardingusingthe councilownedcarparkonGolden Hillforrailusers

Poorfrequencyof Improve services frequencyto3or 4trainsperhour

Chorley Limitedparking– Increaseparking Itisanticipatedthatthenewrail carparkisfullby capacityby stationatBuckshawVillagewill 08:00 deckingcarpark alleviatesomeoftheparking pressuresatChorley

Railservicesare Improvecapacity ThenewrailstationatBuckshaw overcrowdedduring duringpeak mayexacerbateovercrowdingon peakperiodsgoing periods thetrainwhenitreachesChorley. toManchester Althoughthereareproposalsto mitigatepotentialovercrowding

TimingofServices– Reviewofservice sometimesthereare timings twoserviceswithin particularly 5minsofeachother Buxtonservice

ShepherdsWayisa Thephasingof barrierto thepelican pedestriansand crossingneeds cyclists reviewingasit nowtakeslonger forpedestriansto crosstheroad. Shouldalso considersome cyclecrossingin thislocation

Lackofsecure Providecycle parkingforcyclists lockers

CentralLancashireTransportStudy 5.6 5 Transport Strategy

Station Problems/Issues Potential Comment Solution

Noprovisionfor Taxirankor taxis freephonetolocal taxicompany

Poordisabledaccess Toaccess Thereisasecondentranceonthe platform2from othersideofthestationbutneed themainentrance togooutofthestationandlong needtowalk wayroundonfootway downstepsto subway

Adlington Lackofparking Increaseparking Thereissomelandallocatedin provision capacity theLocalPlanforparkingtoserve thestation

Bamber Poorconnectivityfor Improve Thereisanexistingsubway Bridge cyclistsand pedestrianand underthemotorway pedestrianswith cyclinglinks employmentareaat betweenBamber WaltonSummit Bridgeand WaltonSummit

LostockHall Pooraccessand Improveaccess currentlyunderused andpromoteas localtransport link

5.5.3 Alloftheaboveissuesneedaddressingnowandshouldbeprioritisedfortheshorttomedium term.Wesuggestthatstationsshouldbedealtwithinthefollowingorderofpriority:

 Prestonasthisisamajorgatewaytothesubregion;

 Leylandasthefacilitiesforpassengersareverypoor;

 ChorleyasthisprovidesasimportantlinktoManchester;

 AdlingtonalsoprovidesanimportantlinktoManchester;

 BamberBridgepotentiallinkswithWaltonSummit;and

 LostockHallservesasalocalstation.

5.65.65.6 Potential New Rail Stations

5.6.1 The following locations have been identified as having potential for new rail stations. The rail networkisperceivedasbeingimportantforbothlocalandstrategicrailnetworksanditislikely that these stations will be delivered in the longer term and in response to the introduction of majordevelopmentswithintherespectiveareas:

CentralLancashireTransportStudy 5.7 5 Transport Strategy

 Cottam – this is a long standingaspiration within thePreston LocalPlan and would also complement the proposed increase in residential development in the area. An alternativeoptionistohavearailstationfurtheroutthatcouldprovidepark&ride opportunities for both Blackpool and Preston, though likely patronage volumes may notjustifysuchafacility;

 Broughton – Might be required to serve future (2028) development planned in the area. However, it is only a 2 line track and thus it may not prove feasible to have crosscountryservicesstoppingatthisstation.

 Coppull–thereisasitethatiscurrentlysafeguardedintheChorleyLocalPlan.The proposed line upgrades along the west coast mainline in this vicinity make the probability of a new station in this location more feasible than other suggested locations.

 MidgeHall–wouldeffectivelybea‘local’stationandcouldonlybejustifiedbyfuture developmentinthearea.

5.75.75.7 Local Bus Services

Core Strategic Network

5.7.1 The initial suggestionsproposethe implementationofa strategic core busnetworkto promote connectivity across Central Lancashire which should be linked to the future pattern of developmentandcouldbedeliveredinphases.Thenetworkconsistsof(AppendixG:FigureG.1 CoreStrategicRoutes

 Primary routes providing a minimum 10 minute frequency (these would be high qualitypublictransportroutes)

 Secondaryroutesprovidingaminimum15minutefrequency

 Tertiaryroutesprovidingaminimum30minutefrequency

5.7.2 TheprimaryroutesorhighqualitypublictransportroutesaredescribedinTable5.2.

Table 5.2 High Quality Public Transport Routes – Likely Transport Issues Arising from Future Traffic Growth and Developments

Corridor Issues Dependant Delivery Description Developments

Longridge–Preston AveragespeedsfortheB6243are Longridge Mediumterm (guidedbusway currently1520mphintheAMpeak. Grimsargh alongLongridgeline) Trafficforecastswhichsuggesttraffic couldincreasetoover1,200vehicles PrestonEast by2018takingtheroadaboveits capacity.

AlongtheB6242/A6063duringtheAM peakaveragespeedsarealreadyless than20mph.Thisisfurther

CentralLancashireTransportStudy 5.8 5 Transport Strategy

Corridor Issues Dependant Delivery Description Developments

compoundedcongestionatthePrison junction

BroughtonPreston Averagetrafficspeedsonlargesections Whittingham Shortterm oftheroutebetweenBroughtonand Broughton PrestonCityCentrearebetween8and 15mphintheAMandPMPeaks. Lightfoot

Theroadisexpectedtoseeanincrease Cottam intraffic,particularlywhentakinginto considerationnewdevelopmentsin PrestonCityCentre,Broughtonand Lightfoot

CottamPreston Significantamountsofadditionaltraffic Cottam Longterm areexpectedtobeusingtheroadby Lightfoot 2018whennewhousingdevelopments atCottamHallandBroughtonare completed.Thisincreaseisforecastto taketheexistingroadtocapacityand thisisforecasttogetworseby2028if thedevelopmentsatLightfootproceed

Lea–Preston(with Unlikemostoftheothermajor Lea Longterm potentialscopeto corridorsintoPrestoncitycentre,the extendtoBlackpool) A583isdualcarriagewayuntilit reachestheedgeofthecitycentre, lesseningtheimpactofcongestionon thehighway.Asaresult,average speedsaregenerallyhigherthanother radialroutes.

Preston– Although a considerable amount of Samlesbury Mediumterm Samlesbury(with trafficapproachingfromtheeastleaves potentialscopeto the A59 at the M6 junction, a large extendtoBlackburn) volume (1175 vehicles in AM peak hour) of traffic continues towards PrestonCityCentre.

Averagespeeddecreasesto08mphin theAMpeakbetweenjunction31ofthe M6 and the A5085 (Blackpool Road) junction.

AstheroadapproachesPrestonthe carriagewaybecomesnarrowerand thereanincreasingnumberofside roads.Thesefactorscontributetoa

CentralLancashireTransportStudy 5.9 5 Transport Strategy

Corridor Issues Dependant Delivery Description Developments

decreaseinroadcapacityandthe congestionwhichcanforminpeak hours.

ChorleyBuckshaw Trafficgenerationofover4,000 Buckshaw Mediumterm LeylandPreston vehiclesintheAMpeakfromBuckshaw Northof Villageand3,000vehiclesatCuerden Chorley willhaveasignificantimpactonthis corridor 3 Euxton

WadeHallBroad Trafficforecastsindicateadditional LeylandSouth Longterm OakPreston 1,000vehicletripsintheAMpeakon SouthofWade theB5253andA582outsidethe Hall FaringtonandPickering’sFarmsites Farrington

PickeringsFarm

MossSide–Tardy TheB5254WatkinLane/LeylandRoad MossSide Shortterm GatePreston isanimportantexistingbusroute Farrington linkingLeylandtoPreston.Additional trafficgeneratedalongB5253andA582 Cuerden

islikelytobedisplacedalongthisroute PickeringsFarm exacerbatingexistingproblemsat TardyGate LostockHall Gasworks

LimeKiln

ChorleyBamber Traffic on this corridor is forecast to Whittlele Bridgestartof increase significantly in the next Woods guidedbuswayalong decade, particularly between Junction Dunbia oldrailwaycorridor 1AoftheM65andPreston,thisisalso the location of the Cuerden Regional SouthRings

Business Park, creating nearly 7,000 LostockHall jobsandassociatedvehicletraffic. Gasworks Mediumterm WaltonBridgewhichcrossestheRiver LimeKiln Ribble,isexpectedtobecarryingover ChorleyBamber 200vehiclesaboveitscapacitytowards Whittlele BridgePrestonvia PrestonintheAMpeakby2018, Woods B6258(thiswouldbe leadingtoincreasinglyworse ArlaFoods thealternative congestionandincreasedjourney route) times .

3AtthetimeoftheassessmenttheextentoftheemploymentdevelopmentswereuncertainforBuckshawandCuerdenandtherefore theassessmentwerebasedonsiteareasandnotgrossfloorspace.Thetripestimatesrepresentaworstcasescenarioanditis anticipatedthattheactualimpactwillbemuchlower

CentralLancashireTransportStudy 5.10 5 Transport Strategy

Corridor Issues Dependant Delivery Description Developments

MuchHoole– Averagespeedof815mphthrough N/A Longterm Preston(with PenworthamtowardsPrestonintheAM potentialscopeto peak.By2018anadditional133 extendtoSouthport) vehiclesareforecasttotravelthrough HigherPenworthamtowardsPrestonin theAMpeak,withoutsomeformof mitigatingmeasuresaveragejourney timeswillincreaseasaveragespeeds decrease.

Anadditional900vehiclesareforecast tousethePenworthamBridgestocross theRiverRibbletoPrestonintheAM peak.Suchanincreasecouldleadto majordelaystotrafficandqueuing throughHigherPenwortham.

5.7.3 Thehighqualitypublictransportroutescouldbedevelopedasbusrapidtransitstyleservicesand wouldbecomplimentedbyshowcasemeasuressuchasbuspriority,highqualitybussheltersand realtimeinformation.Networkticketingisstronglyrecommendedtomaketravelandinterchange easierforpassengers.Interchangepointsalsoneedtobeclearlydistinguishablefromotherstops andsheltersandcouldincorporatesomejourneytimeinformation.

5.7.4 It is anticipated that the network would be franchised under new powers emerging from the Transport Bill. The current Quality Partnership Scheme model introduced by the Transport Act 2000 is a means by which a local authority agrees to invest in improved facilities at specific locations along bus routes (e.g. bus stops or bus lanes) and operators whowish to use those facilities agree to provide services of a particular standard (e.g. new buses, or driver training standards).

5.7.5 Underproposals in the Local Transport Bill quality partnership schemes would be able,for the firsttime,tospecifyfrequencies,timingsandmaximumfaresasstandardsofservice.Thiscould onlybedonewheretherewereno“admissibleobjections”from“relevantoperators”.

5.7.6 The Strategic Core Network focuses on the emerging development sites and the commuter market. Commuters prefer fast and direct services as well as high quality vehicles and if aspirations to achieve modal switch from single occupancy car travel and mitigation against increasedcongestionaretoberealisedthismarketwillneedtobecateredfor.

5.7.7 Howeverthereareanumberoftraditionalmarketse.g.seniorcitizenswhoaretraditionallymore dependantuponlocalbusservicesandtowhomjourneytimeisnotsoimportantbutmaynotbe abletowalktoofartotheirneareststop.Itisanticipatedthatthecorestrategicnetworkwillbe complementedbymorelocalservicesfulfillingmoreofasocialneedandthesemaybeamixof commercialandsubsidisedservices.

CentralLancashireTransportStudy 5.11 5 Transport Strategy

5.7.8 Thestrategyalsopresentsopportunitiesforpotentiallocalisedschemesandthesecouldinclude:

South Ribble

 Leylandtransporthub–HoughLaneand/orTesco(ShortTerm);

 South Ribble Rider – local bus services improving connectivity within South Ribble betweenurbancentresandraillinks(MediumTerm);

 SouthRibbleFlexibus–expansionoftheexistingservicetofocusonmoreremoteand ruralpartsoftheBorough(MediumTerm);and

 Miniinterchanges:TardyGate,BamberBridge,LostockHall(MediumTerm).

Preston

 BusInterchange–PrestonRailwayStation(MediumTerm);

 NewbusstationaspartofTithebarndevelopment(Shortterm);

 Free Shuttle Service – between rail station, CBD, UCLAN, city car parks and bus station(MediumTerm);and

 Miniinterchange:RoyalPrestonHospital(ShortTerm).

Chorley

 NetworkChorley–stepchangetoincreasecoretownservicesto4busesperhourand extensions/newservicese.g.BotanyBayparticularlyasChorleygrowsanddevelops toensurenewdevelopmentsitesareservedbypublictransport.Increasesservicesto surroundingruralvillagesto2buses(LongTerm);

 Croston–ruraltransporthubwithsomeDRTwiththeproposedimprovementstothe Preston–OrmskirkserviceandproposedimprovementstothebusservicetoChorley thiscouldbeapotentialoption(LongTerm);

 IncreasethefrequencyoftheservicebetweenBlackburnandChorleyto2busesper hourpotentialtolinkwithDRT/FlexibletransporttoserverruralareastoNorthEastof Chorley.(MediumTerm);

 The current links between Chorley and Bolton and Chorley and Wigan should be retainedanddevelopedasrequired(ShorttoLongerTerm);and

 Miniinterchanges:ChorleyHospital,ASDA/ClaytonGreen(ShortTerm).

5.7.9 Tosupporttheproposedimprovementstolocalbusservicesthefollowingbusprioritymeasures arebeingsuggestedforfurtherconsideration:

 High Occupancy Vehicles (HOV)/Bus Lanes on approaches to Preston e.g. A6, A59, A582,A583(Shortterm);

 Some junction remodelling to incorporate greater bus priority e.g. Tardy Gate, Seaview(A6),ChorleyHospital,PrisonJunctioninPreston(ShortTerm);and

 Primaryroutesformshowcasecorridorsandwouldincorporatebusprioritymeasures (seetable5.1).

CentralLancashireTransportStudy 5.12 5 Transport Strategy

5.85.85.8 Potential Park & Ride Sites

5.8.1 ThefollowingsitesareinitiallybeingrecommendedforfurtherconsiderationasbusbasedPark& Ride:

 TickledTrout–PrestonwithpotentialtoserveSamlesbury(MediumTerm);

 Broughton–nextsitetobedevelopedafterjunction31a(ShortTerm);

 Junction31a–alreadyacommittedschemeandduetogoin2008/2009(ShortTerm);

 CuerdenGreen(MediumTerm);and

 PenworthamWay(LongTerm).

5.8.2 ThePark&Ridesitesarelocatedontheprimary/highqualitypublictransportroutesandwillbe served by the buses operating along these routes (i.e. not a dedicated Park & Ride service). Thereisariskthatifadedicatedserviceisnotprovidedthatthebusservicecouldbedelayed elsewhereonthenetworkorthatitcouldbefullbythetimeitreachesthesitesothiswillneed to be compensated for by provision of a high frequency service. Routes should also be complimentedwithbusprioritymeasures.

5.8.3 ThefollowingsitesareinitiallybeingrecommendedasrailbasedPark&Ridesites(seesection 5.6).WiththeexceptionofBuckshawthesewouldallbedeliveredoverthelongerterm:

 Cottam–thiscouldbeequallyservedasabusbasedPark&Ride;

 Broughton;

 –possiblytoincorporatePreston’sCityVisionofsomeformoflightrail;

 MidgeHall,

 Coppull;and

 Buckshawduetoopen2010.

5.8.4 Park & Ride sites also have potential to be developed as transport hubs linking in with local servicesandalsohavepotentialforpark&cycleaswellpark&share(carsharing)schemes.As the sites will be gateways to Preston and should reflect the aspirations for Preston city centre thereforethesewillneedtobehighqualitysitesreflectingcurrentbestpracticeinPark&Ride design.

5.95.95.9 Potential Highway Improvements

5.9.1 Initialrecommendationsforfurtherconsiderationinclude:

 Improvingeasttowesthighwayconnections.Thiswouldbedoneonanincremental basis, and would be driven by the delivery of development in areas which the proposedhighwaywouldserve.Theproposalswouldincorporatesomeduallingofthe A582,provisionofthePenworthamBypass,anewcrossingoftheRiverRibbleanda northernextensiontotheM55(thoughDfTapprovalwillberequiredfortheprovision ofanewjunctionontheM55).Provisionofsucharoute will provideanalternative rivercrossingandcouldalsoprovidesomerelieffortheM6/M55corridor(LongTerm);

CentralLancashireTransportStudy 5.13 5 Transport Strategy

 Broughton Bypass including link to Eastway – this is a combined LCC/developer funded scheme and would provide relief to Eastway which is showing increased pressure as a result of the developments at Broughton and Whittingham (Short Term);

 ImprovementstothejunctionbetweentheA6andtheM55Junction1thisjunctionis operating at capacity and further development to the north of Preston cannot be delivered without increased delays and queues forming on the M55 motorway and extendingintotheadjacentM6Junction32;

 SouthRibbleCrossBoroughLinkRoad–thiscouldhelptoopenupsitesatPickerings Farm and Lostock Hall Gasworks and could provide relief to the A582 Flensburg Way/FarringtonRoadwhichisshowingincreasedpressureasaresultofdevelopments at Pickerings Farm and Farington. The completion of the Cross Borough link road wouldrequiresomecostlyinfrastructureacrosstheWestCoastMainLineinvolvinga lengthyplanningprocess(LongTerm);and

 BusprioritymeasuresalongthemainapproachesintoPreston(ShortTerm).

5.10 Walking and Cycling

5.10.1 Approx10%ofpeoplewalktowork 4inCentralLancashireandapprox80%ofalltripsundera mile 5areundertakenonfoot.Thereforeitisnotunreasonabletoexpectpeopletowalktoworkif theylivewithinamileoftheirworkplace–assumingnomajorbarrierstheanticipatedjourney timewouldbe1520mins.

5.10.2 Measurestoencouragewalkinginclude:

 Improvedstreetlightingtopromotepersonalsecurity;

 Goodstreetscapedesign(ManualforStreets)tomakethewalkingenvironmentmore attractivee.g.service/towncentres,residentialareas;

 Pedestriancrossingsatpointswherepedestrianswanttocross;

 Travelplanning–school,work,travelsmart;

 Improved connectivity between residential areas, transport hubs, town/service centres,employmentarea;and

 Developmentsitesalsoneedtoconsidermovementwithinthesiteaswellasto/from sites.

5.10.3 It is recommended that consideration is given to developing a design guide in the form of a supplementaryplanningdocumenttocoverstreetscapedesignforresidential,town/citycentres, retailcentresandplaceswheretherearelikelytobeareasofhighpedestrianactivity.Thiscould bedeliveredintheshorterterm.

5.10.4 Walkingisalsoanimportantpartoflongerjourneysaspeopleoftenhavetowalktotransport interchanges/stations, bus stops, car parks. Normally these trips should be within 510 mins otherwisetheoveralljourneytakestoolong.

4Census2001 5www.dft.gov.uk

CentralLancashireTransportStudy 5.14 5 Transport Strategy

5.10.5 Transportinterchanges/stationsneedtobefullyaccessibleforallpedestriansparticularlypeople withspecial needs(this canalso includeparents) andthis alsoneeds toinclude linksbetween transport hubs and other areas of pedestrian activity. Provision also needs to be made for adequateandsecurecyclestorage.

5.10.6 Many measures proposed for pedestrians will also be applicable to cyclists and vice versa. Cyclistswilloftenwanttotakethemostdirectroutethroughtowncentresanddonotoftenfeel safecyclingonringroads.Sometimesasanalternativetobuildingexpensivesegregatedcycle ways, quieter side/back roads canoftenbepromotedassafe routesfor cyclists;also reducing thespeedwithinurbanisedareasto20mphcanbeaneffectivemeansofpromotingcycling.

5.10.7 Measurestopromotecyclingcouldinclude:

 Dedicatedcycleways;

 Securecycleparkingwithinapartmentblocksandatemploymentsites;

 Shower/washfacilitiesatworkplaces;

 Promotionofquieterside/backroads;

 Reducedspeedlimitse.g.20mph;

 Cyclecrossingparticularlyonbusyroads;and

 Ensuringtransportinterchangesareaccessibleforcyclists.

5.10.8 Apotentialshorttermschemethatwarrantsfurtherinvestigationisthecreationofapedestrian andcyclelinkbetweenBamberBridgeandWaltonSummitIndustrialPark.Thereisanexisting footpaththatrunsalongtherailtrackandpassesunderthemotorway.Atpresentitisdifficultto findifyouareunfamiliarwiththeareaandwouldneedsomewideningandlandscapingtomake itsafeandattractiveenoughtobepromotedasacyclingandpedestrianlink.Ifadirectroute couldbecreatedalongtherailwaylinefromthestationthenthiswouldbearealopportunity.

5.10.9 Throughadesktopstudyofexistingcyclemaps,previousstudiesandstrategiesandinformation available on the Lancashire and Sustrans website, we have identified national and local cycle routes. General improvements and additions to the network are recommended for further considerationinthelongtermanditisalsorecommendedthatdevelopmentsitesarelinkedto thewidercyclingnetwork(AnnexHFigureH.1).

5.11 Travel Plans

5.11.1 Travel plans are a package of measures aimed at reducing single occupancy car travel. In a development context they are used to reduce the forecast traffic volume generated by the developmentsiteandcanbeimposedbyaconditionattheplanningapprovalstage.Themain objectivesofatravelplanareto:

 Reducetheneedtotravel;

 Reducethenumberofvehiclesonsite;

 Providea‘safe’minimumnumberofparkingspaces;

 Reducetheimpactofthetrafficonthesiteandthesurroundingareas;

 Improvethesafetyandsecurityofpeoplewhotraveltothesite;

CentralLancashireTransportStudy 5.15 5 Transport Strategy

 Promotesustainabletransportmodesandhealthierliving;and

 Inform employees of the social, environmental and economic costs of their travel choices.

5.11.2 TravelPlanrecommendationsforfurtherconsiderationincludes:

 Specifications for minimum standard for secure cycle parking e.g. basement cycle parkingforapartmentblocks(ShortTerm);

 Modalsplittargets–needtobechallengingbutdeliverable(ShortTerm);

 CentralLancashirecarparkingstandards(ShortTerm);

 SupplementaryPlanningDocumentonTravelPlans(ShortTerm);

 Umbrellaorareawidetravelplansforlargerdevelopmentsitesincludingapickand mixofmeasuresthatcanbetailoredtosuitindividualsites(ShortTerm);

 Residential Travel Plans including new residential developments and personalised travelplanning(ShortTerm);

 Effective travel plan monitoring resources to cover each of the Districts – there is currentlyinsufficientresourcetoundertakethisandthereforedevelopertravelplans arenotbeingenforced(ShortTerm);

 Travel Plan Champions based at development sites – travel plans are always more effective when there are local ‘champions’ or coordinators to drive the measures (ShortTerm);and

 TravelPlanForumforsharingresourcesandbestpractice(ShortTerm).

5.12 Demand Management Measures

5.12.1 Toencouragemodalswitchfromthesingleoccupancycartraveltomoresustainablemodeswill require a mix of incentives and disincentives as the car currently has a huge advantage and therefore radical measures are required readdress the imbalance. Disincentives for further considerationwouldinclude:

 Decrease long stay parking in Preston City Centre and increase short stay parking (ShortTerm);

 Increaselongstay parking charges to encouragemorePark & Ride/Public Transport (ShortTerm);and

 Privatenonresidentialparking(PrestonCityCentre)–workplaceparkinglevywhich couldbeusedtocrosssubsidepublictransportimprovements(LongTerm).

5.12.2 Measuresaimedspecificallyatdemandmanagementandsuitableforfurtherconsiderationwould include:

 MoreeffectiveuseofUrbanTrafficControl(UTC)andpossibleexpansione.g.queue management(ShortTerm);

 Routemanagementstrategieslinkedwithimplementationofprimarybusroutesand incorporatingimprovementsforpedestriansandcycliststoprovideaholisticapproach (MediumtoLongTerm);

CentralLancashireTransportStudy 5.16 5 Transport Strategy

 VariableMessageSigning(VMS)onapproachestoPreston,whichcouldbelinkedto realtimejourneyplanning(ShortTerm);

 Activetrafficmanagementonthemotorway(LongTerm);and

 Ramp metering on slips roads i.e. controls flows off slip roads onto motorways via trafficsignals(LongTerm).

5.13 Freight

5.13.1 Thefollowingmeasuresarebeingsuggestedforfurtherconsideration:

 QualityFreightPartnership–partnershipselfregulatingapproachtothemanagement ofthefreightindustry(ShortTerm);

 FreightMap–identifiessuitableroutesforHGVsandisparticularlyusefulfordrivers thatareunfamiliarwiththearea(ShortTerm);

 Signage–complimentsthefreightmap(ShortTerm);and

 LocalisedServicing–restrictedaccesstimes,weightrestrictionsparticularlyinurban centres(ShorttoMediumTerm).

5.14 Summary

5.14.1 The table blow summarises the initial scheme suggestions for further consideration and their priorityintermsofdeliveryintheshort,mediumorlongerterm.

CentralLancashireTransportStudy 5.17 5 Transport Strategy

Table 5.3 Summary of Scheme Suggestions

Scheme Suggestion Dependant Short Term Medium Term Long Term Developments 2008-2013 2013-2018 2018-2028

Rail Schemes

Existingstationimprovements(see Prestoncitycentre √ table5.1) developments

Developments aroundLeyland

Potentialnewrailstations(except Cottam √ Buckshaw) Broughton

Lightfoot

MossSide

SouthofWadeHall

SouthLeyland

BuckshawParkway Buckshaw √

Euxton

NorthofChorley

NorthofLancaster Lane

WhittleleWoods

High Quality Public Transport Routes

Longridge–Preston(guided Longridge √ buswayalongLongridgeline) Grimsargh

PrestonEast

BroughtonPreston Whittingham √

Broughton

Lightfoot

Cottam

CottamPreston Cottam √

Lightfoot

CentralLancashireTransportStudy 5.18 5 Transport Strategy

Scheme Suggestion Dependant Short Term Medium Term Long Term Developments 2008-2013 2013-2018 2018-2028

LeaPreston Lea √

PrestonSamlesbury Samlesbury √

ChorleyBuckshawLeyland Buckshaw √ Preston NorthofChorley

Euxton

WadeHallBroadOakPreston LeylandSouth √

SouthofWadeHall

Farrington

PickeringsFarm

MossSide–TardyGatePreston MossSide

Farrington

Cuerden

PickeringsFarm √

LostockHall Gasworks

LimeKiln

ChorleyBamberBridgestartof WhittleleWoods guidedbuswayalongoldrailway Dunbia corridor SouthRings √ LostockHall Gasworks

LimeKiln

ChorleyBamberBridgePreston WhittleleWoods √ viaB6258(asanalternativeoption ArlaFoods toguidedbusway)

MuchHoolePreston N/A √

Local Bus Schemes

Leylandtransporthub MossSide √

LeylandSouth

CentralLancashireTransportStudy 5.19 5 Transport Strategy

Scheme Suggestion Dependant Short Term Medium Term Long Term Developments 2008-2013 2013-2018 2018-2028

WadeHall

Farrington

SouthRibbleRider Providingalink √ between developmentsin thewestto developmentsin theeastofthe Borough

SouthRibbleFlexibusexpansion Couldbelinkedto √ newdevelopment sites

Miniinterchanges:TardyGate, MossSide √ √ BamberBridge,LostockHall PickeringsFarm

LostockHall Gasworks

LimeKiln

Farrington

BusInterchange–PrestonRailway CentralBusiness √ Station District

TitheBarn

QueenStreet

NewbusstationaspartofTithe TitheBarn √ barndevelopment QueenStreet

FreeShuttleService–betweenrail CentralBusiness √ station,CBD,UCLAN,citycar District parksandbusstation TitheBarn

Miniinterchange:RoyalPreston Broughton √ Hospital Whittingham

Cottam

Lightfoot

NetworkChorleystepchange Alldevelopments √ withinChorley

CentralLancashireTransportStudy 5.20 5 Transport Strategy

Scheme Suggestion Dependant Short Term Medium Term Long Term Developments 2008-2013 2013-2018 2018-2028

Crostonruraltransporthub N/A √

Increasethefrequencyofthe Great √ servicebetweenBlackburnand Knowley/Botany Chorley Bay

M61Junction8

Retainthecurrentlinksbetween N/A √ √ √ BoltonandWigan

Miniinterchanges:Chorley NorthofLancaster √ Hospital,ASDA/ClaytonGreen Lane (ShortTerm)

Bus Priority/HOV Lanes

High Occupancy Vehicles Allcitycentre √ (HOV)/BusLanesonapproachesto developments Prestone.g.A6,A59,A582,A583

Somejunctionremodellingto MossSide √ incorporategreaterbuspriority Farrington e.g.TardyGate,Seaview(A6), ChorleyHospital,PrisonJunctionin PickeringsFarm Preston LostockHall Gasworks

LimeKiln

Buckshaw

TitheBarn

CBD

Park & Ride Sites

TickledTrout Samlesbury √

CityCentre Developments

Broughton Broughton √

Whittingham

Cottam

Lightfoot

CentralLancashireTransportStudy 5.21 5 Transport Strategy

Scheme Suggestion Dependant Short Term Medium Term Long Term Developments 2008-2013 2013-2018 2018-2028

CityCentre Developments

Junction31a CityCentre √ Developments

CuerdenGreen Buckshaw √

NorthofLancaster Lane

Farrington

Euxton

NorthofChorley

WhittleleWoods

CityCentre Developments

Penwortham MossSide √

LeylandSouth

WadeHall

Farrington

PickeringsFarm

Cottam Cottam √

Lightfoot

Lea

Highway Improvements

Duallingandpossibleextensionof PickeringFarm √ √ A582 Farrington

MossSide

WadeHall

LeylandSouth

BroughtonBypassincludinglinkto Whittingham √ √ Eastway Landat Eastway/Broughton BusinessPark

Cottam

CentralLancashireTransportStudy 5.22 5 Transport Strategy

Scheme Suggestion Dependant Short Term Medium Term Long Term Developments 2008-2013 2013-2018 2018-2028

Broughton

Lightfoot

ImprovementstoA6andjunction Whittingham √ withM55 Landat Eastway/Broughton BusinessPark

Cottam

Broughton

Lightfoot

SouthRibbleCrossBoroughLink PickeringsFarm √ Road LostockHall Gasworks

LimeKiln

Pedestrians & Cyclists

DesignGuide(SPD)for Alldevelopment √ streetscapedesign sites

Improvedpedestrian&cyclinglink N/A √ betweenBamberBridgeand WaltonSummit

CentralLancashirecyclingnetwork Alldevelopment √ sites

Travel Plans

Specificationsforminimum Alldevelopment √ standardforsecurecycleparking sites

Modalsplittargets Alldevelopment √ sites

CentralLancashirecarparking Alldevelopment √ standards sites

SupplementaryPlanningDocument Alldevelopment √ onTravelPlans sites

Umbrellaorareawidetravelplans Alllarge √ forlargerdevelopmentsites developmentsites

CentralLancashireTransportStudy 5.23 5 Transport Strategy

Scheme Suggestion Dependant Short Term Medium Term Long Term Developments 2008-2013 2013-2018 2018-2028

ResidentialTravelPlansincluding Allresidential √ newresidentialdevelopmentsand developments personalisedtravelplans

Effectivetravelplanmonitoring Alldevelopment √ resourcestocovereachofthe sites Districts

TravelPlanChampionsbasedat Alldevelopment √ developmentsites sites

TravelPlanForumforsharing N/A √ resourcesandbestpractice

Demand Management

Decreaselongstayparkingin Citycentre √ PrestonCityCentreandincrease developments shortstayparking

Increaselongstayparkingcharges Citycentre √ toencouragemorePark& developments Ride/PublicTransport

Privatenonresidentialparking Citycentre √ (PrestonCityCentre)–workplace developments parkinglevy

MoreeffectiveuseofUrbanTraffic Citycentre √ Control(UTC) developments

Routemanagementstrategies N/A √ √

VariableMessageSigning(VMS) Citycentre √ developments

Activetrafficmanagementonthe N/A √ motorway

Rampmeteringonslipsroads N/A √

Freight

QualityFreightPartnership Citycentre √ developments

FreightMap N/A √

CentralLancashireTransportStudy 5.24 5 Transport Strategy

Scheme Suggestion Dependant Short Term Medium Term Long Term Developments 2008-2013 2013-2018 2018-2028

Signage Citycentre √ developments

LocalisedServicing Citycentre √ √ developments/Or largemixeduse sites

CentralLancashireTransportStudy 5.25 6 Implementation

6.16.16.1 Introduction

6.1.1 This section of the report provides preliminary costings for the initial scheme suggestions and discussesdeliveryofschemes.

6.26.26.2 Costing

6.2.1 The costingsare basedoncurrent pricesand do notincludeanyallowancefor inflationorany optimism bias. Costings have been drawn from a variety of sources such as Local Transport TodayandSPONS.Thefiguresarepresentedintable6.1andhavebeenbrokendownbyscheme typeandtotalinvestmentforeachdeliveryperiod:

 ShortTerm–between2008and2013;

 MediumTerm–between2013and2018;and

 LongTerm–between2018and2028.

Table 6.1 Preliminary Scheme Costings

2008-2013 2013-2018 2018-2028

Rail Schemes

Existingstationimprovements £1,500,000

Potentialnewrailstations(except £16,000,000 Buckshaw)x4

BuckshawRailStation £7,000,000

Total for Rail Schemes £24,500,000

High Quality Public Transport Routes

Longridge–Preston(guided £22,500,000 buswayalongLongridgeline)

BroughtonPreston £9,000,000

CottamPreston £9,000,000

LeaPreston £9,000,000

PrestonSamlesbury £15,000,000

ChorleyBuckshawLeylandPreston £27,000,000

CentralLancashireTransportStudy 6.1 6 Implementation

2008-2013 2013-2018 2018-2028

WadeHallBroadOakPreston £12,000,000

MossSideTardyGatePreston £9,000,000

ChorleyBamberBridgestartof £13,500,000 guidedbuswayalongoldrailway corridor

ChorleyBamberBridgePrestonvia £9,000,000 B6258

MuchHoolePreston £9,000,000

Total for High Quality Public £144,000,000 transport Routes

Local Bus Schemes

Leylandtransporthub £500,000

Miniinterchanges:TardyGate, £300,000 BamberBridge,LostockHall

BusInterchange–PrestonRailway £2,000,000 Station

NewbusstationaspartofTithe £5,000,000 barndevelopment

FreeShuttleService–basedontwo £1,000,000 £800,000 £1,800,000 vehicles*

Miniinterchange:RoyalPreston £100,000 Hospital

Crostonruraltransporthub £500,000

Miniinterchanges:ChorleyHospital, £200,000 ASDA/ClaytonGreen(ShortTerm)

Total for Local Bus Schemes £12,200,000

Bus Priority/HOV Lanes

HighOccupancyVehicles(HOV)/Bus £2,000,000 LanesonapproachestoPreston e.g.A6,A59,A582,A583

Somejunctionremodelingto £1,000,000 incorporategreaterbusprioritye.g.

CentralLancashireTransportStudy 6.2 6 Implementation

2008-2013 2013-2018 2018-2028

TardyGate,Seaview(A6),Chorley Hospital,PrisonJunctioninPreston

Total for Bus Priority/HOV £3,000,000 Lanes

Park & Ride Sites

TickledTrout £4,500,000

Broughton £4,500,000

Junction31a £4,500,000

CuerdenGreen £4,500,000

Penwortham(BroadOak) £4,500,000

Cottam £4,500,000

Total for Park & Ride Sites £27,000,000

Highway Improvements

Duallingandpossibleextensionof £10,000,000 £17,000,000 A582

ImprovementstoA6andjunction £3,500,000 withM55

Total for Highway £30,500,000 Improvements

Pedestrians & Cyclists

Improvedpedestrian&cyclinglink £200,000 betweenBamberBridgeandWalton Summit

Generalimprovementsand £2,750,000 extensionstocyclenetwork

Total for Pedestrian & Cyclists £2,950,000

Demand Management

MoreeffectiveuseofUrbanTraffic £1,000,000 Control(UTC)

VariableMessageSigning(VMS) £500,000

CentralLancashireTransportStudy 6.3 6 Implementation

2008-2013 2013-2018 2018-2028

Activetrafficmanagementonthe £10,000,000 motorway

Rampmeteringonslipsroads £500,000

Total for demand Management £12,000,000

Total Investment £59,500,000 £86,600,000 £110,050,000

*basedonaninitialvehiclecostof£100,000pervehicleandarunningcostof£80,000pervehicleper annum

6.36.36.3 Delivery Mechanisms

6.3.1 In order to successfully deliver the proposed initial transport schemes a significant amount of investmentwillberequired.Potentialfundingmechanismsaredealtwithinthenextchapter.

6.3.2 Inordertodelivertheproposedschemesthefollowingwillbenecessary:

 Sufficientstaffresources;

 Politicalsupport;and

 Publicsupport.

6.3.3 Itisrecommendedthatadedicatedprojectmanagershouldbeappointedtodriveforwardthe deliveryoftheproposedschemes.Theprojectmanagerwillneedtobesupportedbystafffrom boththedistrictsandcountycouncilandthereforewesuggestthatthesteeringgroupcontinues tomeetaregularintervalsandthatthesteeringgroupshouldbesupportedbyaworkingofficer group.

6.3.4 The schemes need to be delivered in a coordinated manner and therefore it would seem appropriatetorecommendaroutemanagementapproachtoachievetherequireddeliveryof:

 Publictransportcorridors;

 Demandmanagementmeasures;

 Highwayimprovements;and

 Facilitiesforpedestriansandcyclists.

6.3.5 Measures should also be complimentary to each other and should not encourage competition betweensustainablemodesastheoverallaimwillbetoreducecartraffic.

CentralLancashireTransportStudy 6.4 6 Implementation

6.46.46.4 Public & Stakeholder Consultation

6.4.1 Itwillbenecessaryearlyonintheprocesstoidentifykeystakeholdersandtotrytoinvolvethem intheconsultationprocessearlysoastoidentifyandanticipateandkeyissuesandobjections. Stakeholdersarelikelytoinvolveavarietyoforganisationsandthelistbelowisnotmeanttobe exhaustiveandcanbeaddedordeletedasappropriate:

 HighwaysAgency;

 NetworkRail;

 Localrailandbusoperators;

 Statutoryenvironmentalbodies;

 Landownersanddevelopers;and

 CommunityRepresentatives.

6.4.2 Public consultation will be a key issue to the delivery ofany transport schemes within Central Lancashire.TheLocalGovernmentandPublicInvolvementinHealthAct2007introducesanew dutyonbestvalueauthoritiestoinvolvelocalpeople,strengtheningaccountabilityandensuring that assessment and inspection are more reflective of and responsive to, local citizens’ and services users’ views. This duty is expected to be implemented from April 2009. Work is underwaywithkeystakeholderstoscopeoutlighttouchstatutoryguidanceonthisnewduty,in linewiththenewguidanceprotocolagreedwithlocalgovernment.

CentralLancashireTransportStudy 6.5 7 Funding

7.17.17.1 Introduction

7.1.1 The section sets outanumber offunding sourcesor mechanisms through whichinfrastructure couldbedelivered,brokendownintoprivateandpublicsectorsources.

7.27.27.2 Mainstream Public Sector Funding Sources

7.2.1 Therehavebeenincreasingpressurestodevelopinfrastructurethroughcreativemechanismsto tieprivatesectorfundinglinkedtodevelopmentoutputs.However,itisimportanttorecognise thatthescaleandtimingofanumberofthemajorinfrastructurerequirementsidentifiedwithin the proposed Transport Strategy mean that there will be a continued requirement for public sectorfundingtosupportdevelopmentandgrowthaspirations.Inordertofrontloadanumberof thelargeinfrastructureprojects,mainstreampublicsectorfundingwillberequiredandthiscan onlybeprovidedbytheUKCentralGovernmentdepartments.

Local Transport Plan / Regional Funding Allocations

7.2.2 ThecurrentLancashireLocalTransportPlan(LTP)identifiesmajorinfrastructureprojectswhich are programmed to receive regional funding allocations. Whilst these are spread across LancashiretherearenodirectinfrastructureschemeswithinCentralLancashirewiththeprojects identifiedthroughthisStrategysittingoutsideofthecurrentshortlistofprojects.

7.2.3 TheLocaltransportPlanprocessischangingwithproposalsundertheTransportBilltoremove the requirementsfor localtransportauthorities toproduce LTPsevery 5years.Localtransport authoritieswillnowhavemuchmorediscretionoverwhentheyneedtoupdatetheirplans.

7.2.4 Funding allocations have also changed withboth thehighways and integrated transport blocks beingformulaic.Thiswillplacelimitationsonwhatcanbedeliveredthroughfuturelocaltransport allocationsrequiringtheneedforgreaterpriority.

Transport Innovation Fund

7.2.5 TheTransportInnovationFund(TIF)wasoriginallyproposedinthe2004WhitePaper‘TheFuture of Transport’ and represents additional public sector funding outside of the Regional Funding AllocationandLTPblockgrants.TheFundisdirectlytargetedattwopriorityobjectives;tackling congestion and improving productivity with £290m available nationally in 2008/09 rising to £1.3bn in 2011/12and £2.55bn in2014/15.The GreaterManchesterauthorities have recently successfully obtained TIF funding linked to the introduction ofa congestion charge around the regionalcentre,withTIFfundingprovidingasubstantialupfrontinvestmentinanumberofmajor publictransportproposals,includingtheextensionoftheexistingMetrolinktramnetwork.Whilst theCentralLancashireauthoritieshavesignificantambitionsforeconomicandhousinggrowthit is unlikely that TIF funding represents a realistic opportunity in the short term, as eligible projectsareintendedtohaveanationalorregionalsignificanceforproductivity,withthescaleof theGreaterManchesterproposalrepresentingaclearbenchmark.

CentralLancashireTransportStudy 7.1 7 Funding

Community Infrastructure Fund

7.2.6 TheCentralLancashireauthoritiesareawaitingadecisionrelatingtotheirExpressionofInterest jointlypreparedwiththeBlackpool,FyldeandWyreCouncils,respondingtotheinvitationsetout withintheHousingGreenPaper,‘Homesforthefuture:moreaffordable,moresustainable’,fora secondphaseofGrowthPointallocations.AdecisionisanticipatedbytheendofJulyfromcentral governmentwithasuccessfulbidensuringthattheauthoritieswouldhaveaccesstothesecond round ofthe CommunityInfrastructure Fund (CIF2). TheGreenPaper identified thatatotal of £300m would be made available nationally through CIF2 with further rounds of funding anticipated.

7.2.7 TheCIFfundisdesignedtocomplementmainstreamtransportfundingwithexistingLTP/RFA schemesgenerallynoteligible.However,thefundisspecificallytargetedatlinkingtheprovision of funding for transport infrastructure to the delivery of housing, with CIF bids expected to illustrate their role in unlocking large housing development sites, enabling the acceleration of housing development and improving the sustainability of major locations for housing growth. These criteria fit closely with a number of the projects identified within the strategy with the originalEOIincludingashortlistofkeyschemes/projectsassociatedwithunlockinganumberof largehousingsitesinSouthRibbleandPrestontoacceleratethedeliveryofhousingacrossthe area.

7.2.8 It is important to note that the CIF is a capital grant allocation, with no revenue funding available,thereforelimitingtheprojectseligibleforapplication.However,fundingisnotlimitedto large or major infrastructure proposals with packages of smallerscale infrastructure schemes alsoeligible.ItisimportanttonotethatfundingobtainedfromCIFwillberingfencedtospecific projectsandnontransferable,withschemesneedingtobecompletebythe31 st March2011.

7.2.9 ThreeExpressionsofInterest(EOI)fortheCommunityInfrastructureFund(CIF)weresubmitted totheDepartmentofCommunitiesandLocalGovernment(DCLG)inSeptember2008tosupport earlyhousingdevelopmentwithinCentralLancashire.TheseEOIsincluded:

 Broughton Park & Ride including junction improvements at M55 Junction 1 and bus priority measures along the A6 Garstang Road. The proposals will support developmenttothenorthofPreston;

 SustainableTravelinSouthRibble,whichincludedhighwayimprovementsalongthe A582 and the creation of a high quality bus corridor along the B5254 Leyland Road/WatkinLane,whichsupporteddevelopmentsatPickeringsfarm,MossSide,Gas WorksandLimeKiln;and

 Buckshaw Parkway Park & Ride which, supported the development at Buckshaw Village.

7.2.10 TheoutcomesoftheexpressionofinterestareexpectedtobeannouncedinJanuary2009anda fullbusinesscasetobesubmittedbyApril2009.Theannouncementforsuccessfulschemesis expectedinJuly2009.

7.37.37.3 Current Private Sector Funding Mechanisms

7.3.1 Inconsideringprivatesectorfundingmechanismsitisimportanttorecogniseandunderstandthe implicationsofcurrentmarketsensitivities.Thewelldocumentedcurrentdownturninthemarket

CentralLancashireTransportStudy 7.2 7 Funding

willhaveimplicationsregardingtheviabilityofschemesandthelevelofcontributionsattainable through development at least within the initial phases of the Strategy. Current projections are indicatingthatitisunlikelythatthemarketwillfullyrecoverinthenextfourtofiveyearsand thiswillhavesignificantimplicationsregardingboththelevelofdevelopmentandtheviabilityof schemesandthereforethequantumoffundingavailabletobenegotiated.

The Existing S106 Regime

7.3.2 The three Central Lancashire authorities have, over recent years, successfully secured S106 agreements associated with a number of major schemes including the large Buckshaw Village developmentlocatedontheborderofSouthRibbleandChorley.Theseagreementshavefunded arangeofinfrastructuralelementsincludingpublictransportimprovements.

7.3.3 Despite these successes the current regime has not maximised the potential from significant levels of private sector housing development across Central Lancashire. Smaller housing developments and windfall developments have not been required to provide contributions to transport infrastructure, with these developments representing a significant proportion of the overall supply of housing across the three authorities. Other pressures to deliver affordable housingunitsand regeneration initiativeshavealsolimited theoverall funding contributionsto infrastructureimprovements.

7.3.4 ContinuingtousetraditionalS106agreementstonegotiatefundingforinfrastructurealsofailsto addressthefactthattheimpactofdevelopmentiscumulativewithalargenumberofsmallsites collectivelycreatingpressureonexistinginfrastructureaswellasthedeliveryofthelargersites. ThisisclearlyillustratedthroughtheoverallStrategyandtheidentifiedinfrastructuralprojects.It isdifficulttodirectlyassociateanumberofthelargepublictransportandhighwayimprovements requiredtospecificdevelopmentsites.Theoverallquantumofdevelopment,particularlyunder an accelerated growth scenario would place pressure upon infrastructure beyond that directly associatedwithspecificsitesandrequireanapproachtodevelopingnewinfrastructurewhichwas notpiecemealinnature.

7.3.5 Agreeingspecificinfrastructurerequirementsandagreedcontributionswhenplanningpermission is granted, as prescribed through the traditional S106 route, prevents sufficient flexibility to recognise that external circumstances may change throughout the development programme leading to transport requirements or opportunities which are new and/or different to those agreed.

7.3.6 Inordertoachievethelevelsofinfrastructureimprovementsproposedalongsidetheambitions foreconomicandhousinggrowthitisclearthatanalternativeregimeforobtainingprivatesector contributionstoinfrastructureimprovementswillberequired.

Community Infrastructure Levy / Tariff Model

7.3.7 ThepublicationofdocumentationontheCommunityInfrastructureLevy(CIL)byDCLG(January 008) and provisions within the Planning Bill clearly signals the Governments intent to bring forwardasystemoflocallybaseddevelopercontributionswithinatariffsystem.Thisstatutory planningchargewouldoperateunderasimilarapproachasaSection106Tariffapproach,with the primary difference being the fact that there would be a set of national policy guidelines defininghowthechargewouldbecalculatedineachofthehousingmarketsorlocalities.

CentralLancashireTransportStudy 7.3 7 Funding

7.3.8 IfapprovedtheCILwouldbeastandardchargedecidedbydesignatedchargingauthoritiesand levied by them on new development e.g. a prescribed amount per dwelling or m 2 of development.Thescaleofthechargewillneedtotakeintoaccountthefullrangeofdevelopment costsplacedonthedevelop,includingaffordablehousingcontributionsandbespokesiteissues includinglandremediationcosts.

7.3.9 Unlike previous legislation the CIL would remove restrictions regarding the linking of contributionstotheimpactof,orbenefitto,developmentataspecificsiteorsites.Thisabilityto pool resources would enable the cumulative effect of development on infrastructure to be recognisedandaddressedthroughthedeliveryofjointlyfundedstrategicinfrastructureprojects. Itis important tonotethat contributions generated through CILcould not be usedforgeneral localauthorityexpenditure,andwouldnotbeavailabletoremedypreexistingdeficienciesunless thesehavebeenaggravatedbynewdevelopment.However,thisdoesnotprecludecontributions frombeingspentonupgradingorimprovingexistinginfrastructureifadditionalpressureresults fromnewdevelopment.

7.3.10 As noted above, it is unlikely that the money generated through the implementing of the CIL would be sufficient to meet the entire costs of the projects identified within the Strategy, especiallyasanumberoftheserequireinitial‘pumppriming’.Thereforemoniesobtainedthrough thepublicsectorfundingsourcesidentifiedabovewillcontinuetobeimportant,however,theCIL representsapotentialmeanstorepaysomeofthepublicsectorinvestmentandalsoensurethe continued delivery of infrastructure projects to assist in facilitating other development sites phasedlaterwithintheStrategy.

7.3.11 If approved the CIL would clearly represent a critical factor in facilitating the delivery of infrastructureforprojectsinthefuture,ensuringthatagreaterproportionofdevelopmentwould contributetoinfrastructureimprovementsandagreaterflexibilitytoprovidelargescalestrategic infrastructureprojects.TheStrategyclearlyestablishesasetofinfrastructureprojectstowhich moniesgeneratedthroughtheCILcouldcontribute.ContinuingtoupdatethisStrategywillmean thattheCentralLancashireauthoritieshavetherequiredframeworkinplacetointroducetheCIL assumingitisapprovedbyGovernment.

An Emerging Tariff Model

7.3.12 InadvanceoftheCILSouthRibblehasalreadydraftedapolicytointroduceadevelopmenttariff on new house building. This adopts a similar approach as would be prescribed more formally nationally through the CIL. The Tariff, which is currently being consulted upon, prescribes a £4,000taxoneachhousingunitdevelopedwithmoniespooledcollectivelytocontributetothe developmentofkeyinfrastructureprojects.

7.3.13 The opportunity exists to expand the proposed South Ribble Tariff system and adopt a ‘public sectorringmaster’modelcoveringthethreeauthoritiesinadvanceoftheCIL.Thisapproachhas beenusedinMiltonKeynestoprovidekeyinfrastructureprojectsrequiredtofacilitatecontinued newdevelopment.Thismodelenablesapublicsectororganisationtoprovideupfrontfundingfor infrastructure that is then repaid by multiple benefiting private investments as development is delivered.Agreementsarereachedwithkeylandownerswhosedevelopmentisdependentupon thedeliveryofamajorscaleinfrastructureproject,withapublicsectororganisationactingasthe accountablebody.

CentralLancashireTransportStudy 7.4 7 Funding

7.3.14 This approach works best where there are a number of larger development sites that have a complexinfrastructureburdenorasharedinterestinalargescaleinfrastructurecomponent.Itis clear that across Central Lancashire these conditions exists with the Strategy identifying a number of large potential early phased developable sites which under an accelerated growth scenarioinparticular,wouldrequiresignificantinfrastructureprojectstoprogressinparallel.

7.3.15 TheGrowthPointEOIsubmittedbytheCentralLancashireauthoritiesandBlackpoolincorporated a Tariff model, with a higher tax of £10,000 suggested. Consideration was also given to the opportunity presented through the large quantum of publicly owned developable land within Central Lancashire. A number of the large potential housing development sites within Central Lancashirearewithinpublicsectorownership(mainlyEnglishPartnershipownership).Thisoffers thepotentialtodevelopamodelbasedonpublicsectorlandpoolinginassociationwithprivate sector development partners, which sees the public sector gain from; increases in land value achieved through the granting of planning permission, investment in enabling infrastructureor markettrends.Existingmodelswhichincorporatethisapproacharecurrentlybeingexploredby the Government and include the current round of pilot Local Housing Companies. Alongside a Tariff model, as described above, the opportunity exists under this approach to maximise the contribution of private sector development to the infrastructure projects outlined within the Strategy.

7.47.47.4 Alternative Funding Sources

7.4.1 Inadditiontothepublicandprivatesectorfundingsourcesandmechanismsidentifiedabovea numberofotherspecificfundingopportunitiesexistwhichshouldbegivenconsiderationinthe future delivery of transport infrastructure across Central Lancashire over the lifetime of the Strategy.Theseotherfundingsourcesandmechanismsaresummarisedbelow.

European Funding - CIVITAS

7.4.2 TheauthoritieswithinCentralLancashirearenotclassifiedasbeingeligibleforEuropeanfunding directly under spatial designations for assistance.This limits the opportunityto seek European fundingdirectlyforinfrastructureprojects.

7.4.3 However, Preston is one of four cities within England which are included within the CIVITAS initiative.TheCIVITASinitiative(CItyVITAlitySustainability)isanECprojectsetuptosupport andevaluatetheimplementationofambitiousintegratedsustainableurbantransportstrategies withinkeyselectedcities,theintentionbeingtolearnlessonswhichcanbereplicatedandapplied acrossEurope.

7.4.4 Preston,alongwiththecitiesofLaRochelleandPloiesti,aspartofCIVITASIIaredevelopinga project titled SUCCESS (Smaller Urban Communities in Civitas for Environmentally Sustainable Solutions),focussedondeliveringsustainabletransportsolutionsandprovidingbestpracticecase studies. The involvement in these European funded initiatives clearly raises the profile of infrastructure improvements within Central Lancashire and could potentially secure additional fundingopportunities.

7.4.5 For example, as part of the redevelopment of the city centre of Preston, which will include a significant quantum of new office and retail floorspace, the opportunity exists for the Preston VisionBoardtoaccessEuropeanfundingviatheNWDAandEnglishPartnershipsinadditionto theotherlargepublicsectorfundingsourcesidentifiedabove.

CentralLancashireTransportStudy 7.5 7 Funding

Local Authority Business Growth Initiative

7.4.6 TheStrategyidentifiesnewlargeemploymentsiteswhichareplannedtocomeforwardoverthe plan period and contribute to economic growth across Central Lancashire. Whilst most of the private funding models focus on housing development, it is important to recognise that the potentialalsoexiststoobtaininfrastructurefundingassistancefromeconomicdevelopmentand thelocalbusinessbase.

7.4.7 TheLocalAuthorityBusinessGrowthInitiative(LABGI)allowslocalauthoritiestospendaportion ofbusinessraterevenueonlocallyidentifiedinitiatives.Thisthereforeofferstheopportunityto capture fundingfrom existingaswell asnew businesses whichbenefitfromnewinfrastructure projectswhichclearlyhaveaneconomicdevelopmentbenefit.Thiscouldincludeforexample,the improvement or introduction of new public transport projects linking employment sites with residentialareas.Itisimportanttorecognisethatthefundsgeneratedthroughthisapproachare likely to be limited in scale and should therefore complement or supplement other funding sources.Considerationwillalsoneedtobegiventotheimpactonthe‘health’oflocalbusinesses andtheirabilitytocompetewithincreasedcostsassociatedwithraisedbusinessrates.

CentralLancashireTransportStudy 7.6 8 Recommendations&FurtherWork

8.18.18.1 Summary of Findings

8.1.1 Fromtheevidencepresentedinthisreportitisclearthatifnosignificantlevelofinterventionis taken, then traffic levels will continue to grow and the existing congestion problems around Preston will continue to get worse. The existing transport infrastructure will not facilitate the developmentaspirationsthattheareaiscurrentlypromoting.

8.1.2 ThecaralreadyhasaconsiderableadvantageintheareaparticularlyinSouthRibbleandChorley wherethebusservicesmaynotbeasfrequentastheyareinPreston.Prestonalsohasastudent populationwhich affects car ownership levels and it its relatively compact makingwalking and cyclingeasierforlocaltrips.

8.1.3 Iftheimbalancebetweenthecarandothermoresustainablemodesaretobeaddressedthena step change will be required in the public transport networks. The step change will need to incorporateserviceimprovementsandinfrastructureimprovementstoraisetheprofileofpublic transportnetworksthereforewehavemadesuggestionsforfurtherconsiderationthatinclude:

 Localrailstationimprovements;

 Potentialnewrailstations;

 StrategiccorebusnetworkforCentralLancashire;

 Localbusschemes;

 Busprioritymeasures;

 Potentialnewpark&ridesites;

 Highwayimprovements;

 Cyclistandpedestrianmeasures;

 Travelplanmeasures;

 Demandmanagementmeasures;and

 Freightmeasures.

8.1.4 Wehaveestimatedtheinitialcostsintheshort,mediumandlongtermtobe:

 ShortTerm(20082013)£59.5million;

 MediumTerm(20132018)£86.6million;and

 LongTerm(2018–2028)£110.5million.

8.28.28.2 Development of a Transport Model

8.2.1 Many of the interventions identified as part of the proposed Transport Strategy will have a significantimpactontrafficmovementsinthearea,aswillthedeliveryofsignificantamountsof new development. Unfortunately, the necessary data and the required mechanisms are not currently available to enable the accurate evaluation of the impact the proposals would have, both in relation to mode transfers, congestion and economic evaluation. This analyses and

CentralLancashireTransportStudy 8.1 8 Recommendations & Further Work

evaluation is fundamental to any future bid for substantial funding from Central Government sources.Therefore,inordertoactivelyprogresstheproposalsandtoassesstheimpactofnew developmentoveranareawidebasis,thenitisstronglyrecommendedthatconsiderationshould begiventothedevelopmentofamultimodallandusetransportmodelfortheCentralLancashire area.

8.2.2 Atransportmodelisusuallyrequiredindevelopingthebusinesscaseforamajorschemebidand it can also be used to test different development scenarios and would be a useful tool when assessing the impact of planning applications, particularly those that will have a significant impactuponthetransportnetworks.

8.2.3 The estimated cost of developing a transport model would be approximately £650,000 £750,000andthiswillcoveradditionaldatacollectioncostsaswellastimeneededtodevelop andvalidatethemodel.

8.38.38.3 Further Investigations

8.3.1 Additional feasibility studies will need to be undertaken for the highway and public transport proposals and it is recommended that these are undertaken on a corridor basis. These may incorporate:

 Additional data collection e.g. origindestination surveys, traffic counts, junction counts,journeytimesurveys;

 Detailedjunctionassessments;

 Detailedsiteauditsandengineeringsurveys;

 AccessibilityassessmentsusingAccession;

 Demandforecasts–basedonservicefrequencies,fares,journeytimes;

 Developmentalimpact–additionaltrafficgeneratedbynewdevelopmentsalongthe corridor;

 Environmentalimpactse.g.airquality,climatechange,biodiversity;and

 Behaviouralchanges–modalswitches,targetedmarketing.

8.3.2 Given time and financial constraints it is recognised that there will be a need to prioritise the corridorsinorderofthosethatwillneedmostattention.Throughanalysisundertakenaspartof thisstudywehavebeenabletoidentifylinksalongthekeycorridorsthatarelikelytoexceed capacityasaresultof trafficgrowthandnew developments proposedfor2018and2028.The corridorsbelowarelistedinorderofprioritywiththoserequiringearlyattentionbeinglistedfirst:

 A6 North –althoughtheselectlink analysis didnot indicate any capacity issues at presenttheLancashirespeedsurveyresultsdidhighlightcongestionissuesalongthis corridor and as Broughton is the next Park & Ride site to be implemented after Junction31aitisrecommendedthatthiscorridorshouldbegivenpriority.Thiswould alsoassist the situationon the Eastway,whichwould be relieved by the Broughton Bypass;

 A582by2018thiscorridorisforecastedtobeovercapacityby48%;

CentralLancashireTransportStudy 8.2 8 Recommendations & Further Work

 A49WiganRoadandB5248DawsonLaneassignificantemploymentsandresidential developmentatBuckshawislikelytoseesubstantialincreasesintrafficinthisarea;

 A59EastcomingtoPrestonthissectionofroadisforecasttobe47%overcapacityby 2018 (based on Preston inner cordon) and Stagecoach have reported issues on the routebythepoliceheadquarters;

 A6South–thereareparticularcapacityissuesatthejunctionbetweenLondonWay and Higher Walton Road which will require further investigation and is currently forecasttobe13%overlinkcapacity;

 A59East–thelinkcapacityisforecasttobeover6%capacityby2018;

 B6243–thelinkisforecasttobeover5%capacityby2018;and

 B6241TomBensonWay.

CentralLancashireTransportStudy 8.3 MVA Consultancy provides advice on transport and other policy areas, to central, regional and local government, agencies, developers, operators and financiers.

A diverse group of results-oriented people, we are part of a 350-strong team worldwide. Through client business planning, customer research and strategy development we create solutions that work for real people in the real world.

For more information visit www.mvaconsultancy.com

Birmingham Lyon SecondFloor,37aWaterlooStreet 11,ruedelaRépublique,69001Lyon,France B25TJUnitedKingdom T:+33(0)472102929F:+33(0)472102928 T:+44(0)1212337680F:+44(0)1212337681 Manchester Dubai 25thFloor,CityTower,PiccadillyPlaza POBox123166Dubai,803805ArbiftTower ManchesterM14BTUnitedKingdom BaniyasRoad,Deira,DubaiUAE T:+44(0)1612360282F:+44(0)1612360095 T:+971(0)42230144F:+971(0)42231088 Marseille Dublin 76,ruedelaRépublique,13002Marseille,France FirstFloor,12/13ExchangePlace T:+33(0)491373515F:+33(0)491919014 CustomHouseDocks,IFSC,Dublin1,Ireland T:+353(0)15426000F:+353(0)15426001 Paris 1214,rueJulesCésar,75012Paris,France Edinburgh T:+33(0)153173600F:+33(0)153173601 StewartHouse,ThistleStreet,NorthWestLane EdinburghEH21BYUnitedKingdom Woking T:+44(0)1312206966F:+44(0)1312206087 FirstFloor,DukesCourt,DukeStreet Woking,SurreyGU215BHUnitedKingdom T:+44(0)1483728051F:+44(0)1483755207 SeventhFloor,78StVincentStreet GlasgowG25UBUnitedKingdom T:+44(0)1412254400F:+44(0)1412254401 London SecondFloor,17HanoverSquare LondonW1S1HUUnitedKingdom T:+44(0)2075296500F:+44(0)2075296556

Email: [email protected]

Offices also in Bangkok,Beijing,HongKong,ShenzhenandSingapore