Procurement Plan for Punjab RWSS (P150520)

I. General

1. Bank’s approval Date of the procurement Plan 2012 Public Disclosure Authorized 2. Date of General Procurement Notice: [October 01, 2014 ] 3. Period covered by this procurement plan: January 2017 onwards

II. Goods and Works and non-consulting services.

1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: 2. Procurement Method Prior Review Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 2. NCB (Goods) Above US$ 100,000 3. ICB (Works) Above US$ 40 million Public Disclosure Authorized 4. NCB (Works) Above US$ 10 million 5. (Non-Consultant Services) Below US$ 100,000

2. Prequalification for Bidders _Not applicable_

3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA

4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P150520

Public Disclosure Authorized 5. Any Other Special Procurement Arrangements:

In addition, the justification for all contracts to be issued on the basis of LIB, single-source or direct contracting (except for contracts less than US$50,000 in value) will be subject to prior review. Justification for all contracts to be issued on the basis of LIB, single-source or direct contracting (except for contracts less than US$50,000 in value) will be subject to prior review.

III. Selection of Consultants

1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants:

Public Disclosure Authorized Selection Method Prior Review Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) Above US$ 50,000 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. PROCUREMENT : IN Punjab Rural Water and Sanitation Sector Improvement Project PLAN General Information

Country: India Bank’s Approval Date of the Original Procurement Plan: 2018-08-29 Revised Plan Date(s): (comma delineated, leave blank if none)2019-03-07 Project ID: P150520 GPN Date: Project Name: IN Punjab Rural Water and Sanitation Sector Improvement Project Loan / Credit No: IBRD / 84870 Executing Agency(ies):Division (EE-2nd)

WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

PRWSS-S-DIV82-5442-1 / Renovation of rooms for new Je sections (S110 to S116) under jurisdiction of Division Under Request for Single Stage - One Batala EE-2nd including IBRD / 84870 Post Open - National 0.00 Implementati 2018-09-08 2018-11-03 2019-05-02 Quotations Envelope white washing repair of on room fixing electric fans and lights e.t.c under component 4A of PRWSSIP

DWSS-W-DIV82-5384-1 / Design and build W/S Sys. incl. WTP, Clear & Raw Water PS, CW Transmission mains upto OHSRs of Under existing Villages. Inst. of Single Stage - Two IBRD / 84870 Post Request for Bids Open - National 0.00 Implementati 2018-11-01 2018-11-06 2018-12-18 2019-03-02 2019-04-06 2021-03-31 Blk Water Meters, Silent Envelope on Generator, Transformer, SCADA/PLC for prov. W/S to 40 villages of various blocks of & 10 yrs O&M

DWSS-W-DIV82-5669-1 / WSS village Fazlabad BLOCK DISTT. GURDASPUR. :Prov & Inst tubewell, Pumping Under Request for Single Stage - One Machinery, Disinfection IBRD / 84870 Post Open - National 0.00 Implementati 2019-01-26 2019-03-23 2019-09-19 Quotations Envelope Unit,PVC pipes. Const. of on Pump Chamber & OHSR. O&M for 3 months under component 1A(ii) of PRWSSIP.

PRWSS-W-DIV82-5778-1 / WSS village Raje ke & Chack Mehma Block Dera Baba Nanak Distt. Gurdaspur. Prov & Inst Under tubewell , Pumping Request for Single Stage - One IBRD / 84870 Post Open - National 0.00 Implementati 2019-02-17 2019-04-14 2019-10-11 Machinery, Disinfections Quotations Envelope on Unit . Const. of Pump Chamber ,OHSR . O & M for 3 Months under component 1A(iii) of PRWSSIP.

Page 1 DWSS-W-DIV82- 5777-1 / WSS Kot Mulvi Block Fatehgarh Churrian Distt. Gurdaspur. Prov & Inst tubewell , Pumping Under Request for Single Stage - One Machinery, Disinfections IBRD / 84870 Post Open - National 0.00 Implementati 2019-02-17 2019-04-14 2019-10-11 Quotations Envelope Unit . Const. of Pump on Chamber ,OHSR . O & M for 3 Months under component 1a(iii) of PRWSSIP

PRWSS-W-DIV82-5776-1 / WSS village Khushalpur BLOCK Dera Baba Nanak DISTT. GURDASPUR. Prov & Inst tubewell , Under Request for Single Stage - One Pumping Machinery, IBRD / 84870 Post Open - National 0.00 Implementati 2019-02-17 2019-04-14 2019-10-11 Quotations Envelope Disinfections Unit . Const. on of Pump Chamber ,OHSR . O & M for 3 Months under component 1a(iii) of PRWSSIP

DWSS-W-DIV82-6018-1 / WSS village Bishniwal BLOCK Fatehgarh Churrian DISTT. GURDASPUR. Providing and Installing tubewell, Pumping Under Request for Single Stage - One Disinfections Unit, Supplying IBRD / 84870 Post Open - National 0.00 Implementati 2019-03-17 2019-05-12 2020-02-06 Quotations Envelope and laying of PVC pipes, on valves. Const. Pump Chamber, OHSR . O & M for 3 Months under component 1A(iii) of PRWSSIP

PRWSS-W-DIV82-6067-1 / WSS Village Akarpura and Akarpura Khurd Block Dera baba Nanak, District Gurdaspur: Installing Under Request for Single Stage - One tubewell , const. of pump IBRD / 84870 Post Open - National 0.00 Implementati 2019-02-19 2019-04-16 2019-10-13 Quotations Envelope chamber with disinfection on unit . const. of HSR . o & M fr 3 months under component 1A(iii) of PRWSSIP

DWSS-W-DIV82-6266-1 / WSS Village Chatha Block Fatehgarh Churrian District Gurdaspur: Providing and Pending Request for Single Stage - One Installing Tubewell, OHSR, IBRD / 84870 Post Open - National 0.00 Implementati 2019-03-23 2019-05-18 2019-11-14 Quotations Envelope Civil Work,Pump on Chamber,Pumping Machinery etc.under component 1A(iii) of PRWSSIP.

GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

Page 2 PRWSS-G-DIV82-5440-1 / Procurement of Office furniture, Electric fans tools and plants and other Under Request for Single Stage - One facilities for New JE IBRD / 84870 Post Open - National 0.00 Implementati 2018-09-08 2018-11-03 2019-05-02 Quotations Envelope sections (S110 to S116) on under jurisdiction of Division Batala EE-2nd under Component 4 A of PRWSSIP

NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual