Optimized MV Generator Power Plant Architectures for Large Data Centers

Total Page:16

File Type:pdf, Size:1020Kb

Optimized MV Generator Power Plant Architectures for Large Data Centers Optimized MV Generator Power Plant Architectures for Large Data Centers White Paper 262 Revision 0 by Julien Moreau Malik Megdiche Daniel Radu Executive summary For large (>5 MW) data center applications, it is common to have large generator power plants connected directly to the medium voltage (MV) electrical distribution network. The principal way to cost optimize the system is to reduce the number of generators installed using N+1 redundancy instead of 2N. This paper introduces some optimized electrical distribution architectures for the generator power plant that meets the various Uptime Institute Tier levels. A cost comparison study and reliability calculations were made on a representative case study. The results are presented in this paper. Rec- ommendations for choosing an architecture based on the expected performance of the system are also provided. Schneider Electric – Data Center Science Center White Paper 262 Rev 0 2 Introduction For data centers larger than about 5 MW it begins to make sense to move more of the electrical distribution typically done at low voltage (LV) to the medium voltage (MV) level while also, perhaps, making the connection to the utility grid at the high voltage (HV) transmission level1. Data centers at these large power capacities have an opportunity to significantly reduce both capital and operating expenses by opti- mizing the design of both the electrical distribution network and how the backup power supply is connected to that network. The key optimization for doing this is going from a traditional 2N or N+1 LV generator architecture to a centralized MV generator power plant that is connected to the MV distribution network. This im- proved architecture is discussed in detail in this paper. Traditionally, generators are provided in a 2N configuration to yield a high level of availability for the backup power supply. But, this comes at a high cost, both CAPEX and OPEX-wise. And since these larger data centers are connected either to redundant MV distribution feeds or to the HV transmission grid itself, the question arises as to whether 2N generator plants are required since the reliability of the grid at MV and HV is very high. Additionally, generator power plants are typically run only periodically for testing and are not used as the continuous power supply for the data center. Of course, a highly available grid does not mean that a reliable backup power supply is not required. But a 2N-based generator architecture is un- necessary especially in light of its high cost. As a result, for large data centers, N+1 (or N+2) generator architectures are becoming the reference standard design. Since in a 2N design the generator power plant represents about 30% of the total electrical distribution investment for a data center of this size - from the connection to the grid down to the rack PDU - optimization has a significant and positive im- pact on the total CapEx by reducing the type and number of equipment including electrical switchboards and so on. It can also potentially improve OpEx, reduce the overall footprint, simplify the design, reduce operational risks, improve scalability, and lower carbon footprint. This paper will describe a globally-applicable electrical architecture using an N+1 generator power plant connected on a fully redundant MV electrical distribution (Figure 1). Note that the generator power plant distribution network (shown in the red box in the figure) is the focus of this paper. The overall electrical distribution network supporting the generators will be explained along with analyzing the relia- bility and cost of this proposed architecture. To do this, this paper will cover the fol- lowing topics: • High level description of cost and comparative cost differences of optimized MV generator power plant architectures based on the Uptime Institute’s Tier levels (i.e., Tier II, Tier III and Tier IV classification)2 • A comparison of these architectures in terms of CAPEX and reliability. 1 Most data centers below 1MW connect to the grid at the LV level. However, much larger data centers tend to connect to the grid at the MV and even HV level. Connection to the grid refers to where the customer-owned gear is connected to the utility-owned gear. 2 Turner, W.P., J.H. Seader. V. Renaud, K.G. Brill; “Tier Classifications Define Site Infrastructure Perfor- mance.” 2008, Uptime Institute, NM. Optimized MV Generator Power Plant Architectures for Large Data Centers Schneider Electric – Data Center Science Center White Paper 262 Rev 0 3 HV substation N+1 Generator power plant EG EG EG EG Figure 1 Primary MV distribution Generator MV Primary MV distribution Shows a large data center con- Path A distribution Path B nected on the HV transmission grid. This architecture is also applicable in the case of the Secondary MV Secondary MV connection to a MV distribution distribution distribution grid. The IT load distribution is Path A Path B in 2N but block or dynamic re- dundancy is also applicable. LV distribution LV distribution LV distribution LV distribution & UPS & UPS & UPS & UPS Path A Path B Path A Path B IT Load IT Load The architectures described in this paper are based on the Uptime Institute’s Tier Generator classification system. That classification system is described in Table 1. power plant architectures Tier Level Basic Description Impact to Generator Tier I Basic capacity, no redundancy Redundant capacity compo- One single failure or maintenance opera- Tier II nents tion can lead to unavailability of the gener- (e.g., chiller, UPS, Generator) ator power plant. Redundancy on the emergency generator and its electrical distribution equipment is needed. Table 1 Description of the Uptime Tier II + concurrently maintain- One single failure can lead to unavailability Institute’s Tier levels and able of the generator power plant, but the oper- their implication on Tier III (each capacity component can ator is able to manually reconfigure the generator power plant be maintained and/or removed system no matter the fault type. architecture without impact to IT) The electrical system (protection, monitor- ing, etc.) can be designed to help the op- erator manually reconfigure the system more quickly in the event of a failure Tier III + fault tolerant (no single point of failure; auto- The generator power plant is fault tolerant, matic response to any failure to Tier IV without any Single Point of Failure ensure service continuity to IT (SPOF)*. without any operator action needed) * To be considered a “Tier IV equivalent” generator power plant (fault tolerant), it is necessary to take into account all operating modes when designing the system. For example, a pre-existing failure before the generators start, a failure during the start- ing sequence, or a failure in normal operation must all be taken into consideration and accounted for when designing the system. Optimized MV Generator Power Plant Architectures for Large Data Centers Schneider Electric – Data Center Science Center White Paper 262 Rev 0 4 The Uptime Institute Tier classification system does not take into account the utility’s availability for evaluating designs, solely relying instead on the on-site backup equipment (i.e., emergency back-up generators, water storage, etc.). Tier II generator power plant architecture To meet Tier II requirements, we propose a simple N+1 generator power plant ar- chitecture with one common MV switchboard and a basic electrical protection sys- tem (based on overcurrent and directional protection3) (Figure 2). In this architecture, all generators are connected to a single switchboard. This “backup” switchboard supplies both paths of the data center. In the event of a ma- jor fault (e.g. something that requires switchboard or cubicle replacement) or dur- ing scheduled maintenance of the generator MV switchboard (i.e. busbar cleaning every 5 years), it is not possible to supply the data center through the generators. EG EG EG EG Utility 1 Utility 2 Figure 2 NO NO NO NO Single switchboard Tier II type architecture; Backup NOTE: During normal Loadbank operation with normal conditions, the switch gear is “NO” or “nor- Path A Path B mally open”. ATS NO NO ATS Note: The MV protection system can be designed to have discrimination between the generator incomers (input power feeds) to avoid a blackout, through use of di- rectional overcurrent or generator differential protection. The exception would be a failure on the generator switchboard busbar. Tier III generator power plant type architectures Double-fed architecture To meet Tier III requirements, we propose an architecture with redundant MV switchboards and a simple protection system (Figure 3). This architecture has each generator connected to both MV distribution switchboards (Gen-A and Gen-B) via two feeders. Only one of these two feeders is closed at a time to maintain a “simple” protection system (based on overcurrent and directional protection) and facilitate fault localization in case of a failure. Gen-A and Gen-B switchboards are intercon- nected by a coupling cable (i.e. a tie), as well as to Path-A and Path-B switch- boards to be able to supply both paths even if Gen-A or Gen-B are down. 3 Refer to the “Electrical Network Protection Guide”, http://www.schneider-electric.com/en/down- load/document/CG0021EN/ Optimized MV Generator Power Plant Architectures for Large Data Centers Schneider Electric – Data Center Science Center White Paper 262 Rev 0 5 With a Tier III system, maintenance operation of any part of the installation (i.e., generators and the surrounding electrical equipment) will not affect the availability of the generator power plant. In case of a failure on the power plant MV distribution (i.e. on switchgear G1 to G4, Gen-A and Gen-B, or one of the interconnection cables), the power plant will expe- rience a blackout: however, after the fault location process, it is possible to recon- figure and restart the power plant.
Recommended publications
  • Emergency Diesel Generator Reliability Study
    Emergency Diesel Generator Reliability Study 1 EDG SYSTEM DESCRIPTION This analysis focused on the ability of the EDG train to start and load its associated safety- related bus for a specified mission time. For the purposes of this study, an EDG train is a diesel engine, electric generator, and the associated support subsystems necessary to power and sequence the electrical loads on the safety-related bus. Typically, two or more EDG trains constitute the onsite emergency ac power system. All but one of the plant designs in this study include the capability for at least two EDG trains to supply power to the plant using independent safety-related buses. The one exception is at Millstone 1 where one EDG train and a gas turbine generator train supply ac power to the emergency ac power system. In some cases, a swing EDG train is used that can supply power to more than one plant (but not simultaneously) such that two plants will have a total of only three EDG trains: one EDG train dedicated to each specific plant and the third, a swing EDG system, capable of powering either plant. Each EDG train uses combinations of one or two diesel engines powering one ac electrical generator. The typical EDG train comprises one diesel engine per generator. In this study, two diesel engines powering one generator were considered as one EDG train. Diesel engines used for fire pumps, specific Appendix R purposes, or non-class 1E backup generators, were not included in the study. Neither was the high-pressure core spray (HPCS) EDGs included in this study.
    [Show full text]
  • Advanced Control of a Compensator Motor Driving a Variable Speed Diesel Generator with Rotating Stator
    energies Article Advanced Control of a Compensator Motor Driving a Variable Speed Diesel Generator with Rotating Stator Mohammadjavad Mobarra 1 , Bruno Tremblay 2, Miloud Rezkallah 3 and Adrian Ilinca 1,* 1 Wind Energy Research Laboratory (WERL), Université du Québec à Rimouski, Rimouski, QC G5L 3A1, Canada; [email protected] 2 Department of Computer Science and Engineering, Université du Québec à Rimouski, Rimouski, QC G5L 3A1, Canada; [email protected] 3 Electrical Engineering Department, Ecole de Technologie Superieure, Montréal, QC H3C 1K3, Canada; [email protected] * Correspondence: [email protected]; Tel.: +1-418-723-1986 (ext. 1460) Received: 4 April 2020; Accepted: 22 April 2020; Published: 2 May 2020 Abstract: Variable speed generators can improve overall genset performance by allowing the diesel engine to reduce its speed at lower loads. In this project, a variable speed diesel generator (VSDG) uses a rotating stator driven by a compensator motor. At lower loads, the stator turns in the opposite direction of the rotor, a process that can be used for purposes like maintaining a fixed relative speed between the two components of a generator. This allows the diesel engine to turn at a lower speed (same as the rotor) and to increase its efficiency. The present research addresses the control of the compensator motor driving the generator’s stator using a variable-frequency drive that adapts the speed to its optimal value according to the load. The performance of the proposed control strategy was tested using a Freescale microcontroller card programmed in C-code to determine the appropriate voltage for the variable-frequency drive.
    [Show full text]
  • Efficient Operation of Diesel Generator Sets in Remote Environments
    Efficient Operation of Diesel Generator Sets in Remote Environments Kaitlyn R. Wheeler Thesis submitted to the faculty of the Virginia Polytechnic Institute and State University in partial fulfillment of the requirements for the degree of Master of Science In Mechanical Engineering Alfred L. Wicks, Chair Douglas Nelson Steve C. Southward May 9, 2017 Blacksburg, VA Keywords: mobile hybrid power system, fuel consumption, energy storage, diesel engine, generator © 2017, Kaitlyn R. Wheeler i Efficient Operation of Diesel Generator Sets in Remote Environments Kaitlyn R. Wheeler Abstract Diesel engine and generator sets (gensets) have been extensively used for standby and remote power generation over the past hundred years. Due to their use for standby power, these diesel gensets are designed to operate in conjunction with the grid, which relates to a fixed speed operation with a 60 Hz AC output. For operation in remote conditions, such as military and disaster relief applications, this fixed speed operation results in limiting the power output available from the engine, as well as the overall efficiency of the system. The removal of this grid connectivity requirement could result in an increase in system efficiency. At a given load, the engine operates more efficiently at lower speeds, which corresponds to an increase in the system efficiency. This low speed operation also results in lower power output. Knowledge of the load is important in order to determine the most efficient operating point for fixed speed operations. Operating at a higher power output for a given speed also results in higher system efficiency. The addition of a battery pack will allow for a higher apparent load, resulting in higher operating efficiency.
    [Show full text]
  • Technical Specifications of Dg Set
    TECHNICAL SPECIFICATIONS OF DG SET 1.0 INTENT OF SPECIFICATION : 1.1 This specification covers the design, manufacture, assembly, shop testing, packing, despatch, transportation supply, erection, testing, commissioning, performance and guarantee testing of Silent type Diesel Generating Sets, complete in all respects with all equipment, fitting and accessories for efficient and trouble free operation as specified here under including statutory approvals. 1.2 SCOPE OF WORK : General Scope of work shall include design, manufacture, shop testing, packing, despatch, transportation to site, supply, erection, testing and commissioning of the following: a) Diesel engine complete with all accessories, an Alternator directly coupled to the engine through flexible/ rigid coupling complete with all CTs, PTs, etc as required or as per BOQ & specifications, accessories for starting, regulation and control, including base frame, foundation bolts etc, interconnecting piping and accessories, power and control cable glands and lugs. b) AMF/Manual panel including various meters/Annunciation and other control components as per standard practice, BOQ & specifications. Control panel cabling between bidders & local equipments and special cables if any. c) Equipments necessary for fuel storing and distribution, day oil tank, piping, valves, level controller and indicators etc. Load sharing facility with Synchronization Panel. d) Flexible connections and Residential type silencer of exhaust system, including thermal lagging. e) Batteries with teak wood battery stand painted with acid proof black paint and battery charging equipment, including their connections as necessary along with tools & accessories for battery maintenance. f) Anti Vibration Mountings etc. g) Preparing of all related shop drawings for approval from client/consultant and statutory bodies. h) Obtaining approval of the installation of Diesel Generators by the Electrical Inspectorate and Pollution Control bodies and any other statutory bodies.
    [Show full text]
  • NUREG/CR-0660, "Enhancement of On-Site Emergency Diesel
    NUREG/CR-0660 UDR-TR-79-07 ENHANCEMENT OF ONSITE EMERGENCY DIESEL GENERATOR RELIABILITY Final Report Gerald L. Boner Harvey W. Hanners University of Dayton Research Institute Prepared for U. S. Nuclear Regulatory Commission NOTICE This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United. States Government nor any agency thereof, or any of their employees, makes any warranty, expressed or implied, or assumes any legal liability or responsibility for any third party's use, or the results of such use, of any information, apparatus product or process disclosed in this report, or represents that its use by such third party would not infringe privately owned rights. Available from National Technical Information Service Springfield, Virginia 22161 Price: Printed Copy $10.75; Microfiche $3.00 The price of this document for requesters outside of the North American Continent can be obtained from the National Technical Information Service. NUREG/CR-0660 UDR-TR-79-07 ENHANCEMENT OF ON-SITE EMERGENCY DIESEL GENERATOR RELIABILITY Final Report Gerald L. Boner Harvey W. Hanners University of 'Dayton Research Institute Dayton, OH 45469 Manuscript Completed: January 1979 Date Published: February 1979 Prepared for Division of Operating Reactors Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Under Contract No. NRC-03-77-192 TABLE OF CONTENTS SECTION PAGE TASK I REVIEW OF OPERATING EXPERIENCE I-1 1. REVIEW OF LICENSEE EVENT REPORTS (LER's) I-i 2. REVIEW OF REPORTS FROM THE NUCLEAR PLANT RELIABILITY DATA SYSTEM 1-7 3.
    [Show full text]
  • Solar Photovoltaic, Diesel Generator and Battery Storage System) for Electrification for Gwakwani Village, South Africa
    environments Article Comparison between Three Off-Grid Hybrid Systems (Solar Photovoltaic, Diesel Generator and Battery Storage System) for Electrification for Gwakwani Village, South Africa Miriam Madziga 1 ID , Abdulla Rahil 2,* ID and Riyadh Mansoor 3 1 Faculty of Technology, De Montfort University, Leicester LE1 9BH, UK; [email protected] or [email protected] 2 Institute of Energy and Sustainable Development (IESD), De Montfort University, Leicester LE1 9BH, UK 3 Engineering College, Al-Muthanna University, Samawa, NA, Iraq; [email protected] * Correspondence: [email protected]; Tel.: +44-116-250-6848 Received: 12 March 2018; Accepted: 2 May 2018; Published: 8 May 2018 Abstract: A single energy-based technology has been the traditional approach to supplying basic energy needs, but its limitations give rise to other viable options. Renewable off-grid electricity supply is one alternative that has gained attention, especially with areas lacking a grid system. The aim of this paper is to present an optimal hybrid energy system to meet the electrical demand in a reliable and sustainable manner for an off-grid remote village, Gwakwani, in South Africa. Three off-grid systems have been proposed: (i) Photovoltaic (PV) systems with a diesel generator; (ii) Photovoltaic systems and battery storage; and (iii) Photovoltaic systems with diesel generator and battery storage. For this analysis, different size of photovoltaic panels were tested and the optimal size in each scenario was chosen. These PV sizes were 1, 0.8, 0.6 and 0.4 kW. The optimization between these sizes was built based on three main objectives.
    [Show full text]
  • Abstract—Rural Electrification Rate (RER) in Africa Is Still Low to Date. Several Countries in Sub-Saharan Africa Have Tried T
    Preprints (www.preprints.org) | NOT PEER-REVIEWED | Posted: 25 August 2021 doi:10.20944/preprints202108.0485.v1 Potential for Increased Rural Electrification Rate in Sub-Saharan Africa using SWER Power Distribution Networks M. E. Irechukwu and A. T. Mushi Department of Electrical Engineering, University of Dar es Salaam, P.O. Box 35131, Dar es Salaam – TANZANIA Abstract—Rural electrification rate (RER) in Africa is still low to date. Several countries in Sub-Saharan Africa have tried to address this problem using conventional single-phase two-wire or three-phase three-wire systems, however at large costs due to the nature of dispersed rural load centers, low load demand, and low population density. Another solution of off-grid generation creates associated health problems. Therefore, this paper undertakes a review of a single wire earth return (SWER) network as a RER improvement solution. The paper undertakes intensive literature review to elucidate challenges and solutions to the implementation of SWER technology. Advantages of SWER technology discussed make it the choice for RER improvement in Sub-Saharan African countries. After that, a case study is selected in rural Tanzania, and a preliminary SWER network design is undertaken. Index Terms—Single wire earth return (SWER), power distribution networks, rural electrification rate (RER). I. INTRODUCTION Majority of grid-connected rural electrification (RE) technology in Africa are the single-phase two-wire (SPTW) distribution system and the three-phase three wire (TPTW) distribution system, called conventional technologies. Mahanthege (2015) cited a study that presented data of rural electrification rate (RER) in Sub-Saharan Africa at about 14.2%.
    [Show full text]
  • WL International Commercial & Industrial Generator Sets
    WL International Commercial & Industrial Generator Sets High Performance Diesel Engine & Genset Solutions WL International Built To Perform. Built To Last. For over 125 years, we have been developing innovative power generation technologies and solutions that enable our customers – and entire industries – to increase performance, productivity and uptime in the world’s most demanding environments. Today, our extensive line of WLI2K, WLI3K, WLI4K and WLI6K Series diesel engines for gensets, and WLI PG 2000-6000 Series diesel generator sets, are the powerful, reliable and cost effective solutions for a diverse range of light and heavy duty applications in non-USA international markets. Key Applications Medical Commercial Military Industrial Residential Special Projects Critical Features Diesel Engines Diesel Generators 5-420 kW (1500 rpm) / 6-467 kW (1800 rpm) 6-525 kVA (1500 rpm) / 7-583 kVA (1800 rpm) 2, 3, 4 and 6 cylinder 2, 3, 4 and 6 cylinder Compact, quiet & fuel efficient Open Type and Silent Type models Switchable 1500 (50Hz) /1800 (60Hz) Mechanical governor: 6-94 kVA (1500 rpm) Direct injection in-line pump Electronic governor: 106-583 kVA (1800 rpm) 12/24 VDC electric system Equipped with high efficiency combustion system Reliable Power Heavy duty air filter High power output, fuel efficient, quiet for a Wide Range Mechanical governor: 5-68 kW (1500 rpm) Utilizes DeepSea DSE 6020 MKII Auto Main Electronic governor: 85-467 kW (1800 rpm) (Utility) Failure Control Modules of Industries and Radiator rated at 55˚C as standard Equipped
    [Show full text]
  • Earth Grid Down 1St Edition Pdf, Epub, Ebook
    EARTH GRID DOWN 1ST EDITION PDF, EPUB, EBOOK Stuart P Coates | 9781532015779 | | | | | Earth Grid Down 1st edition PDF Book Yang; doi : I believe a cellphone may be damaged mainly because some use RF near-field charging which is designed to receive an RF charge and in a solar flare the ambient charge would be thousands if not 10s of thousands of times higher. Would using cash make us vulnerable to robbery or home invasion? He said federal policy and practice are missing programs for the following:. Have some wet wipes available for clean up. Utilities may impose load shedding on service areas via targeted blackouts, rolling blackouts or by agreements with specific high-use industrial consumers to turn off equipment at times of system-wide peak demand. Propane stores well and safely if outside. To avoid electrochemical corrosion, the ground electrodes of such systems are situated apart from the converter stations and not near the transmission cable. Orpha, I just emailed you a copy of the list so you can print it out more easily. Synchronous grids with ample capacity facilitate electricity market trading across wide areas. The Indian Express. Also hand sanitizer makes a great fire starter in an emergency. Legislatively, in the first quarter of the year 82 relevant bills were introduced in different parts of the United States. Others however express concern [ 55 ]. Another option is a commode , using a bucket and garbage bags. In , it completed the power supply project of China's important electrified railways in its operating areas, such as Jingtong Railway , Haoji Railway , Zhengzhou—Wanzhou high-speed railway , et cetera, providing power supply guarantee for traction stations, and its cumulative power line construction length reached 6, kilometers.
    [Show full text]
  • Solar/Diesel Mini Grid Handbook
    POWER AND WATER CORPORATION SOLAR/DIESEL MINI-GRID HANDBOOK This project is supported by the Australian Government through the Australian Renewable Energy Agency (ARENA). ARENA is an independent agency established to make renewable energy technologies more affordable and increase the amount used in Australia. ARENA is supportive of all renewable energy technologies and invests along the innovation chain – from research in the laboratory to large scale technology projects, as well as activities to capture and share knowledge. More information is available at www.arena.gov.au. Power and Water Corporation (PWC), through its not-for-profit subsidiary Indigenous Essential Services Pty Ltd (IES), is responsible for the provision of energy, water and wastewater services to 72 nominated remote Indigenous communities and 66 outstations across the Northern Territory (NT). To service these communities, PWC operates over 50 isolated mini-grid power systems, most of which rely on diesel fuel for power generation. Electricity demand in remote NT communities is continuing to increase, as a result of Government infrastructure development, service improvement and housing programs and population growth. At the same time the price of diesel fuel is highly volatile, being affected by global supply constraints and exchange rate movements. An ongoing reliance on diesel fuel for remote power generation represents considerable and increasing financial risk. 3 PWC is committed to delivering least-cost, reliable and safe electricity services to remote Indigenous communities and has long pursued alternative energy source options. PWC recognises the opportunity solar technologies present to reduce the reliance on diesel fuel and drive down operational expenditure. PWC has an over 20 year track record of owning and operating solar/diesel hybrid systems Solar/Diesel Mini-Grid Handbook in remote Indigenous communities.
    [Show full text]
  • Hydropower Plants As Black Start Resources
    Hydropower Plants as Black Start Resources May 2019 Jose R. Gracia Patrick W. O’Connor Lawrence C. Markel Rui Shan D. Thomas Rizy Alfonso Tarditi ORNL/SPR-2018/1077 Approved for public release. Distribution is unlimited. Acknowledgments This work was authored by Oak Ridge National Laboratory, managed by UT-Battelle for the US Department of Energy, under contract DE-AC05-00OR22725 and supported by the HydroWIRES Initiative of the Energy Department’s Water Power Technologies Office (WPTO), under contract number DE-AC05-00OR22725. The authors would like to thank Stephen Signore of Oak Ridge National Laboratory for his help in determining the makeup of current black start units in the United States. Additional thanks go to Alejandro Moreno, Samuel Bockenhauer, and Rebecca O’Neil for their thoughtful comments on drafts of the white paper. HydroWIRES The US electricity system is changing rapidly with the large-scale addition of variable renewables, and the flexible capabilities of hydropower (including pumped storage hydropower) make it well-positioned to aid in integrating these variable resources while supporting grid reliability and resilience. Recognizing these challenges and opportunities, WPTO has launched a new initiative known as HydroWIRES: Water Innovation for a Resilient Electricity System. HydroWIRES is principally focused on understanding and supporting the changing role of hydropower in the evolving US electricity system. Through the HydroWIRES initiative, WPTO seeks to understand and drive utilization of the full potential of hydropower resources to contribute to electricity system reliability and resilience, now and into the future. HydroWIRES is distinguished in its close engagement with the US Department of Energy (DOE) national laboratories.
    [Show full text]
  • Diesel Generator Operation
    Working Copy WP 04-ED1301 Revision 10 Diesel Generator Operation Technical Procedure EFFECTIVE DATE: 10/13/06 Leroy Bostick APPROVED FOR USE CONTINUOUS USE PROCEDURE Working Copy WP 04-ED1301 Rev. 10 Page 2 of 36 TABLE OF CONTENTS INTRODUCTION. ..................................................... 3 REFERENCES........................................................ 3 PRECAUTIONS AND LIMITATIONS....................................... 4 INITIAL CONDITIONS.................................................. 5 PERFORMANCE...................................................... 6 1.0 DIESEL GENERATOR 1 OPERABILITY CHECK USING LOAD BANK 25P-LB04/1...................................................... 6 2.0 DIESEL GENERATOR 2 OPERABILITY CHECK USING LOAD BANK 25P-LB04/1..................................................... 1 3 3.0 REMOTE START................................................. 2 1 4.0 LOCAL START. ................................................. 2 4 5.0 DIESEL GENERATOR LOADING.................................... 2 7 6.0 DIESEL GENERATOR OPERABILITY CHECK USING SUBSTATION THREE......................................................... 2 8 7.0 RESTORATION FOLLOWING OPERABILITY CHECK USING SUBSTATION THREE......................................................... 2 9 8.0 LOCAL START, DIESEL GENERATOR OPERABILITY CHECK USING LOAD BANK 25P-LB04/1................................................ 3 0 9.0 LOCAL SHUTDOWN, RESTORATION FOLLOWING OPERABILITY CHECK USING LOAD BANK 25P-LB04/1. ................................... 3 3 10.0 REMOTE SHUTDOWN...........................................
    [Show full text]