<<

Ongoing Projects in - New Lines, Doubling and Gauge Conversion 

Appendix 1 (Ref Para 1.2)

ORGANISATION CHART OF CIVIL ENGINEERING DIRECTORATE

MEMBER ENGINEERING Railway Board Level Additional Member (Civil) Additional Member (Works)

ED (Works) ED (Project Monitoring) ED (Works Planning)

Director (Works I) JD (Works) Director (Works II) Director (Works Planning)

EDCE (General) EDCE (Planning) EDTK (Procurement) EDTK (Monitoring) EDTK (Machine)

DCE (General) DCE (Planning) DTK (Procurement) DTK (Monitoring) DTK (Machine)

Chief Administrative offficer oa ala Level Zonal Railway

Chief Engineer Chief Electrical Engineer FA & CAO CSTE COS

ED - Executive Director, JD –Joint Director, EDCE – Executive Director Civil Engineering, DCE – Director Civil Engineering, EDTK – Executive Director , DTK – Director Track, FA&CAO – Financial Advisor and Chief Accounts Officer, CSTE – Chief Signal and Telecom Engineer, COS – Controller of Stores

Report No. 48 of 2015 Page 96 Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – II (REF. TO PARA – 1.4) High Priority Projects Projects Projects Projects Projects Projects identified for Last mile Projects on cost sharing Project falling in Total Projects with without without without frozen/ detailed review projects basis with the State more than one project maximum milestone revised revised abandon Govt. or other agencies categories selected time s cost commissio ed or (other than PPP repetition overrun estimate ning dropped projects) counted and cost schedule once) overrun Zonal Railways Zonal Railways

CR 1) Wardha 1) Belapur 1) NIL Ahmednaga NIL NIL 1)- 1) Beed- 1. Belapur- Seawood 6 (Sevagram)- –Seawood- Belapur – r-Beed- Pen (DL) Parli-Vaijnath (NL) uran (TOR/COR, -3rd Uran Seawood- Parli- 2) Pen – 2) Wardha-Nanded (NL) WMS & Cost Line 78.3 km Electrified Uran Vaijnath Roha (DL) 3) Belapur –Seawood- Sharing or other than (DL) Double Electrifie (NL) Uran Electrified DL PPP) Line(MTP) d Double (MTP) (NL) 2. Ahmednagr - (NL) Line(MT Beedparli (WRCS & P) (NL) Cost sharing or other than PPP) 1 1 1 0 1 0 0 2 3 2 ER 1. Rampurhat- Nil Nil Nil Nil Nil 1) Nabadwipdham-Patuli Nil 1) -Katwa 1. Bardhman-Katwa 11 Muraroi MM (DL) (GC) (DR,CS or other than (28.48 km) - PPP) 3rd line 2. Tinpahar- Sahibganj (HP, DR) 2. Tinpahar- 2) Tinpahar- Sahibganj 2) Dumka-Rampurhat Sahibganj (DL) (NL)(phase-II of project (DL) (37.82 Rampurhat-Mandarhill via km as Phase I Dumka) of DL of Tinpahar- Bhagalpur) 3. Sahibganj- 3) Bardhaman-Katwa (GC) 3)Deoghar-Dumka (NL) Pirpainti (DL) with New (MM) for Katwa- (10.45 km) Bazarsau (DL), Katwa [Dainhat]-Manteswar Negum-Mangalkot, Manteswar-Memari-(NL)

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͻ͹  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – II (REF. TO PARA – 1.4)

Zonal High Projects Projects Projects Projects Projects Projects identified Last mile Projects on cost sharing Project falling in Total Railw Priority with without without without frozen/ for detailed review projects basis with the State more than one project ays Projects maximum milestones revised cost revised abandoned Govt. or other agencies categories selected time estimate commissi or dropped (other than PPP (repetitio overrun oning projects) n counted and cost schedule once) overrun

4. Pirpainti- 4) Hansdiah-Godda (NL) Bhagalpur (59.06 km) 5. Sainthia- Tarapith 3rd line (DL) 6. Tarapith- Rampurhat (DL) 6 0 0 0 0 0 3 0 4 ECR 1) - Nil Nil Nil 1) Nil 1) Koderma – Ranchi, Nil 1) Koderma- Ranchi (NL) 1. Koderma-Ranchi Ramdaualu Jayanaga (NL) (DR, CS other than Nagar (DL) r – PPP) Darbhang a- Narkatia Gunj (GC) 2) Garhwa 2) Sakri-Nirmali - 2) Koderma- (NL) Road-Ramna Jhanjharpur- (DL) Bazar - Saharsa – Forbesganj,(GC) 3) Rail across River Ganga at Patna (NL) 4) Rail Bridge across River Ganga at (NL) 5) Koderma- Tilaiya (NL)

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͻͺ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – II (REF. TO PARA – 1.4) 2 0 0 0 1 0 2 0 5 1 High Projects Projects Projects Projects Projects frozen/ Projects Last Projects on cost sharing Project falling in Total Priority with without without without abandoned or identified mile basis with the State Govt. more than one project Projects maximum milestones revised cost revised dropped for detailed projects or other agencies (other categories selected time estimate commissioning review than PPP projects) (repetition overrun schedule counted and cost once) overrun Zonal Railways Zonal Railways

ECoR 1) Nil 1) Khurda Nil Nil Nil 1) Talcher- Nil Nil 5 Jharsuguda- Road – Bimlagarh Rengali Bolangir, (NL) (DL) (NL) 2) Khurda- Barang-3rd line (RVNL) 3) Rajatgarh- Barang (DL) (RVNL) 3 0 1 0 0 0 1 0 0 NR 1) Utretia- 1) Nangal 1) Nangal 1) Udham 1) Nangal Dam Nil 1) - Nil 1) Nangal Dam – Talwara 1. Nangal Dam- 10 Zafrabad Dam – Dam – Pur- – Talwara. Jhajjar- (NL) Talwara (DL) Talwara. Talwara. Srinagar- (NL) Rohtak (NL) (TOR/COR,WMS,WR (NL) (NL) CS,Cost sharing/other Rail Link. than PPP) (NL) 2.Udhampur-srinagar- baramula rail link (TOR/COR,WMS,WR CE)

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͻͻ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – II (REF. TO PARA – 1.4) High Projects Projects Projects Projects Projects frozen/ Projects Projects on cost sharing Project falling in Total Priority with without without without abandoned or identified basis with the State Govt. more than one project Projects maximum milestones revised cost revised dropped for detailed or other agencies (other categories selected time estimate commissioning review than PPP projects) (repetition overrun schedule counted and cost once) overrun Zonal Railways Zonal Railways Zonal Railways

2) Udham 2) Udham 2) NDLS- 2) Rewari – Rohtak (NL) Pur- Pur- Tilak Bridge Srinagar- Srinagar- – 5th & Baramull Baramulla 6th line (DL) a Rail Rail Link. 3) Jind – Sonepat (NL) Link. (NL) (NL)

4) – Baddi (NL)

5) Deoband – (NL)

6) Bhanupalli – Bilaspur (NL)

7) Rohtak – Meham - Hansi (NL)

1 2 2 1 1 0 2 0 7 2

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͲͲ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – II (REF. TO PARA – 1.4)

High Projects Projects Projects Projects Projects Projects Projects on cost sharing Project falling in Total Priority with without without without revised frozen/ identified basis with the State Govt. more than one project Projects maximum milestones revised cost commissioning abandoned or for detailed or other agencies (other categories selected time estimate schedule dropped review than PPP projects) (repetition overrun counted and cost once) overrun Zonal Railways Zonal Railways Zonal Railways

NCR Nil Nil Nil Nil Nil Nil 1) - 1) Nil Nil 3 (NL) Bhind- Etawah (Part of Guna- Etawah via Shivpur i) (NL) 2) Dholpur-  Sirmutra(GC ) with extension upto Gangapur City. 0 0 0 0 0 0 2 1 0 0 NER Nil Nil Nil Nil Nil Nil 1) Nil Nil 2 Maharajgang -Masarakh- Rewa Ghat (NL)

2) Aunrihar- Jaunpur (GC) 0 0 0 0 0 0 2 0 0

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͲͳ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – II (REF. TO PARA – 1.4) High Projects Projects Projects Projects Projects frozen/ Projects Last Projects on cost sharing Project falling in Total Priority with without without without abandoned or identified mile basis with the State Govt. more than one project Projects maximum milestones revised cost revised dropped for detailed projects or other agencies (other categories selected time estimate commissioning review than PPP projects) (repetition overrun schedule counted and cost once) overrun Zonal Railways Zonal Railways

NFR 1) 1) Katihar- Nil 1) Bogibeel Nil Nil 1) New 1) Nil 1. Lumding- 5 Lumding- Jogbani Bridge with Mainaguri- Lumding Silchar(HP,LM) Silchar (GC) link Jogighopa - Silchar 2. Rangia- (GC) Lines(NL) (NL) (GC) Murkongselek (DR, 2) Rangia- 2) LM) Murkongsele Rangia- k (GC) Murkon gselek (GC).

1 1 0 1 0 0 2 2 0 2

NWR Nil Nil Nil Nil Nil Nil 1) - Nil 1) -Dungarpur via 4 Ringus- Banswara (NL) Churu & Sikar-Loharu (GC)

2) Suratpura- 2) Thaiyat Hamira-Sanu Hanumangar (NL) h- Sriganganag ar section(GC)

0 0 0 0 0 0 2 0 2

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͲʹ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – II (REF. TO PARA – 1.4) High Projects Projects Projects Projects Projects frozen/ Projects Last Projects on cost sharing Project falling in Total Priority with without without without abandoned or identified mile basis with the State Govt. more than one project Projects maximum milestones revised cost revised dropped for detailed projects or other agencies (other categories selected time estimate commissioning review than PPP projects) (repetition overrun schedule counted and cost once) overrun Zonal Railways Zonal Railways

SR 1) Nil Nil Nil Nil 1) Erode-Palani 1) Nil 1) Cuddalore-Salem via 9 Thanjavur- (NL) Tindivanam- Vridhdhachalam (GC) with Ponmalai Nagari (NL) a (NL) between Chinna (DL)with Salem and Kallakuruchi bypass line before Ponmalai

2) 2) 2) Attipattu-Puttur (NL) Kankanadi- Tindivanam- Panambur Tiruvannama Patch (DL) lai (NL)

3) Angamali- Sabarimala (NL) 4) Quilon- Tirunelveli- Tiruchendur (GC) , Tenkasi- Virudhunaga r (GC)

2 0 0 0 0 1 4 0 2

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͲ͵  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – II (REF. TO PARA – 1.4) High Projects Projects Projects Projects Projects frozen/ Projects Last Projects on cost sharing Project falling in Total Priority with without without without abandoned or identified mile basis with the State Govt. more than one project Projects maximum milestones revised cost revised dropped for detailed projects or other agencies (other categories selected time estimate commissionin review than PPP projects) (repetition overrun g schedule counted and cost once) overrun Zonal Railways Zonal Railways

SCR 1) Nil Nil Nil Nil Nil 1) Bidar - 1) 1) Bidar - Gulbarga 1. Bidar-Gulbarga 7 Gulbarga Peddapal (DR, LM,CS other – li- than PPP) 3rd Line Karimna 2. Nandyal - with gar- Yaregunta (DR, LM) electrificati Nizamba on. d 2) Nandyal – 2) 2) Cuddapah - Yerraguntla Jaggaiah Banglore(NL) peta Town – Mellache ruvu with (MM)for Mellache ruvu - Janpahad 3) Akola - 3) Khandwa Nandyal (GC) – Yerragun tla 4) Bidar - Gulbarg a

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͲͶ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – II (REF. TO PARA – 1.4) High Projects Projects Projects Projects Projects frozen/ Projects Last Projects on cost sharing Project falling in Total Priority with without without without abandoned or identified mile basis with the State Govt. more than one project Projects maximum milestones revised cost revised dropped for detailed projects or other agencies (other categories selected time estimate commissioning review than PPP projects) (repetition overrun schedule counted and cost once) overrun Zonal Railways Zonal Railways

1 0 0 0 0 0 3 4 2 2

SER 1) Goelkera 1) Bankura 1) Nil Nil/silent 1) Bowaichandi Nil Nil 1) Ranchi – Lohardaga 1. Tamluk-Digha 6 – – Damodar – Digha – Arambagh with extension to Tori(GC) (TOR/COR, Manoharpu River (NL) with (NL) WMS,F/A/Dropped) r 3rd line valley four MMs (DL) (GC) with six (MMs) (NL)

2) Sini – 2) Tamluk 2) Tamluk – Adityapur – Digha Digha (NL) 3rd line (NL) with with four MMs (DL) four MMs

2 2 1 0 0 2 0 0 1 1

SECR 1) Khodri- Nil Nil Nil 1) – Nil 1) Nil 1) Dhallirajahara – 1. Gondia - Jabalpur 7 Anuppur Jabalpur,(GC) Chhindwara Jagdalpur (NL) (WRCS,DR,CS other with flyover – Nagpur, 2)Wadsa – Gadchiroli and than PPP) at Bilaspur (GC) two Projects (NL) (DL)

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͲͷ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – II (REF. TO PARA – 1.4) High Projects Projects Projects Projects Projects frozen/ Projects Last Projects on cost sharing Project falling in Total Priority with without without without abandoned or identified for mile basis with the State more than one project Projects maximum milestones revised cost revised dropped detailed projects Govt. or other agencies categories selected time estimate commissionin review (other than PPP (repetition overrun g schedule projects) counted and cost once) overrun Zonal Railways Zonal Railways

2) Salka 2) Gondia – Road- Jabalpur Khongsar- (GC) Patch including doubling Balaghat (DL) Katangi,(GC)

3) Champa- Jharsuguda- 3rd line (DL)

3 0 0 0 1 0 2 0 2 2 SWR 1) Birur- 1) Hubli- Nil Nil 1) Hubli- 1) Hubli-Ankola 1) Munirabad- Nil 1) Kadur-Chikmagalur- 1. Hubli-Ankola 13 Shivani Ankola Ankola (NL) (NL) Raichur (NL) Sakaleshpur (NL) (TOR/COR,WRCS,F/ Patch (DL) (NL) A/Dropped) 2. Banglore- 2) Hosadurga 2) – 2) Rayadurga- 2) Bangalore –Hassan via Sathyamangalam Road- Sathyamangalam Tumkur via Shravanabelagola (NL) (F/A/Dropped, CS Chikjajur (NL) Kalyanadurga other than PPP) Patch (DL) (NL) 3. Munirabad-Raichur (DR,CS other than PPP) 4. Raidurga- 3) Rayadurga-Tumkur Tumkur(DR,CS other via Kalyandurga (NL) than PPP)

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͲ͸  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

High Projects Projects Projects Projects Projects frozen/ Projects Last Projects on cost sharing Project falling in Total Priority with without without without abandoned or identified mile basis with the State Govt. more than one project Projects maximum milestones revised cost APPENDIXrevised – droppedII (REF. TOfor PARAprojects – 1.4) or other agencies (other categories selected time High Projects Projects estimateProjects commissioningProjects Projects frozen/ detailedProjects Last Projectsthan PPP on costprojects) sharing Project falling in (repetitionTotal overrun Priority with without without schedulewithout abandoned or identifiedreview mile basis with the State Govt. more than one countedproject and cost Projects maximum milestones revised cost revised dropped for detailed projects or other agencies (other categories selectedonce) overrun Zonal Railways Zonal Railways time estimate commissionin review than PPP projects) (repetition overrun g schedule counted and cost 5) Bagalkot-Kudachi (NL) once) Zonal Railways Zonal Railways overrun

6) Whitefield-Kolar (NL)

7) Tumkur-Chitradurga- Davanagere (NL)

8) Shimoga-Harihar (NL)

9) Bangalore- Sathyamangalam (NL)

10) Ramanagram-Mysore (DL)

2 1 0 0 1 2 2 0 10 4

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͲ͹  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – II (REF. TO PARA – 1.4) High Projects Projects Projects Projects Projects frozen/ Projects Last mile Projects on cost sharing Project falling in Total Priority with without without without abandoned or identified projects basis with the State Govt. more than one project Projects maximum milestones revised cost revised dropped for or other agencies (other categories selected time estimate commissioning detailed than PPP projects) (repetition overrun schedule review counted and cost once) Zonal Railways Zonal Railways overrun WR 1) Nil Nil Nil Nil Nil 1) Chhoto- Nil Nil 4 Viramgam- Udepur Surendernag Dhar (NL) ar (DL)

2) Udhna- 2) Ratlam- Jalgaon (DL) Mhow- with Khandwa- electrificatio Akola n (GC)

2 0 0 0 0 0 2 0 0

WCR 1) - Nil Nil Nil Nil Nil 1) Lalitpur- Nil Nil 4 Bina -3rd line Singrauli, (RVNL)* (NL)

2) Bina-Kota 2) Ramganj (RVNL)* Mandi – Bhopal, (NL)

2 0 0 0 0 0 2 0 0

28 7 5 2 5 5 31 9 38 16 105

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͲͺ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – III (REF. TO PARA NO. 1.4) STATEMENT SHOWING THE STATUS OF NATIONAL PROJECTS IN NORTH-EASTERN PROJECTS Sl. Name of the project Month and Target date of completion Total anticipated cost ( ` In Physical progress as No Year of crore) of March 2014 sanction Original Revised Original Revised (in per cent)

1 2 3 4 5 5 6 7 1 Kumarghat- (109 km) Jul-96 March 2007 March'16 575 1242.25 100 (MG completed). GC yet to be started. 2 Bogibeel Bridge with linking Lines (73 km) Sept,1997 31.3.06 Dec'16 1000 4996.19 75 3 Jiribam- (Tupul) (110.625 km) 1.4.2003 31.3.09 March'19 2650 5996 34.04 4 Tetelia- Byrnihat (21.5 km) 1.4.06 31.3.09 Mar'17 208.07 430.33 15.1 5 Dimapur- Kohima (88 km) 1.4.06 31.3.12 Mar'20 887.89 2446.57 0 6 Agartala - Sabroom (112 km) 1.4.08 31.3.12 Mar'17 537.66 1741 29.31 7 Bhairabi- Sairang 1.4.08 31.3.14 Mar'20 512.38 2393.48 10.45 8 Sivok- Rangpo 1.4.08 31.3.14 Not fixed 1329.44 3380.58 2 9 Byrnihat- Shillong 1.4.10 31.3.16 Not fixed 3925.79 Not revised 0 10 Lumding- Silchar Gauge Conversion July'1996 31.3.06 Mar'16 648 5185.44 87.97 11 Rangia- Murkongselek along with linked fingers 1.4.03 Mar'09 30.3.14 915.70 3319.17 91.83 line project (510.33 km) 





‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͲͻ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion



APPENDIX IV- (REF. TO PARA – 1.6.2)

STATEMENT SHOWING THE STATUS OF PROJECTS (`150 CRORE AND ABOVE) WHERE PHYSICAL PROGRESS IS 100 PER CENT

` in

` in crore) crore) in

` ) in crore)

` crore Financial progress as of progress Financial March 2014 ( Zonal Railways project of the Name Month and Year of sanction of and year Month of project commencement of completion date Target not section a whole (As wise) ( Cost Total Anticipated in crore) in percent of Return Rate expenditure Cummulative till March 2014 ( Physical progress as of as progress Physical 2014 (in March percentage) Throw forward ( Remarks Remarks Original Original Revised Original Original Revised Original Revised Original New Lines ER Lakhshmikant 1987-88 1993 N.AV N.AV. 100.89 546.78 4.40 Not 139.90 25.59 100 404.28 apur - Revised Namkhana Chandanagar MM for a] 2011-12 Not N.AV. N.AV. 61.85 11.00 Not 0.00 0.00 0.00 0.00 Separate Kakadwip yet Revised expenditure figure Budakhali starte for MM not [5km] and d available

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͳͲ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

b] N.AV N.AV. (-) 9.00 Chandanagar 2011-12 . 165.35 Bakhali [17.2 km] Deoghar- 1998-99 2003 Not Feb'2011 180.73 358.55 5.00 Not 390.01 109.00 100 239.83 Dumka Asses (as per Revised [72.25 km] sed in MOU dt. PET 28.2.2012 Surve ) y ECR Muzaffarpur- 1997-98 June, N.AV N.AV. 210.79 483.62 (-) 3.72 Not 514.88 106.46 100 31.26 Entire section Sitamarhi( 63 2002 revised opened on KM) 26.03.13

Ara- 1997-98 May, N.AV N.AV. 189.14 321.87 4,82 Not 319.75 99.34 100 2.12 (98KM) 2002 revised -Hasua 2001-02 Jan- N.AV. N.AV. 180.82 390.00 N.AV. N.AV. 324.68 83.25 100 65.32 -Tilaya(46 02 Km) NR Abohar- 1997-98 2002- N.AV 31.07.12 86.44 229.00 (-)7.44 N.AV. 230.84 100.77 100 2.26 Work completed Fazilka ( 03 % & Commissioned 42.17 Km) in July 2012 Chandigarh- 1997-98 1998- 2005 30.04.13 248.40 1115.21 (-)2.26% N.AV. 985.35 88.36% 100 114.30 Work completed Ludhiana 99 & Commissioned (112 Km) NFR Dudhnoi- 1.4.92 1992- Not March'14 22.33 247.75 Not Not 220.68 89.07 100 27.07 Engine rolling Mendipathar 93 fixed Done Done done on 29.3.14 (BG) (15.5 km) Kumarghat- Jul-96 1996- Mar' March'16 575 1242.25 (-) Not 955.943 76.95 100 286.307 Section was Agartala (109 97 07 11.98% Revised commissioned km) with MG and will be commissioned on BG after GC of LMG-SCL - KUGT project

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͳͳ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

Harmoti- Feb-97 1996- Not Jan'14 156 406.4 (-)6.37% (-) 6.38% 406.33 99.98 100 0.07 Work completed Naharlagun 97 fixed and 1st train (21.75 km) service ran on 7.4.14 SR -Salem 1996-97 N.AV Section already 229.88 1052.68 19.47 3.73 771.81 335.74 100 31.72 Revised estimate . commissioned vetted by finance SER - 1974-75 N.AV Mar-07 Mar-15 31.42 154.3 (-) 0 - 179.37 45.59 100 356.03 Figures shown in Amta (Inclu. col. 13, 14, 15 & Bargachia- 16 are inclusive of Champadanga MM ) (i) 1st MM: 2009-10 N.AV Jan-10 Not 103.2 103.2 19.69 3.00 Amta-Bagnan fixed (ii) 2nd MM: 2009-10 N.AV. April- Not 38.73 38.73 (-)40.49 2.00 Champadang 10 fixed a- Tarakeswar (iii) 3rd MM: 2011-12 N.AV Dec-14 Not 97.23 97.23 (-) 4.40 1.00 Jangipara - fixed F.Sharif Tamluk- 1984-85 N.AV. Completed 43.73 293.97 2.53/ 0.55 456.816 45.08 100 617.64 Figures shown in Digha 3.02 col. 13, 14, 15 & 16 are inclusive of MM (i) 1st MM : 2009-10 N.AV. July-11 June-15 121.44 121.44 - 30.00 Deshpran- Nandigram (ii) 2nd 2011-12 N.AV June-15 June-15 247.28 247.28 (-)4.60 2.00 MM:Kanthi- (iii) 3rd 2012-13 N.AV Not fixed 275.14 275.14 - 1.00 MM:Nandigr am - Kandiamari

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͳʹ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

(iv) 4th MM: 2012-13 N.AV Not fixed 75.91 75.91 - 1.00 Nandakumar - Balaipanda Total 3276.35 7801.31 5896.36 2178.20

CR Latur- 93-94 1993 Not NA 225.00 950.00 4.60% N.AV. 970.24 120.00 100 9.47 osmanabad fixed kurduwadi miraj guage conversion(37 4 Kms) ECR Manasi - 1996-97 May- Target date not 48.39 477.89 11.57 Not 456.14 95.45 Manasi 21.75 Section from Saharsa- 97 fixed revised - mansi to Dauram Saharsa Banmankhi has - - already been Purnia(143 Dauram opened for Km ) Madhep passenger traffic. ura - As on the date of 100% - review. Dauram Madhep ura- Purnia - 80% NER Aunrihar- Jan-04 2004 NA NA 83.37 175.77 6.1 NA 172.75 98.29 100 3.01 Jaunpur NFR Lumding- 1.4.93 1993- Not Complet 442.93 971.22 (-)8.24% Not 833.47 85.82 100 137.75 All 3 phases 94 fixed ed in Revised Completed and including link Dec'09 commissioned branch lines upto Dec'09 of Haibargaon- Mairabari & Senchoa- Silghat (56)

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͳ͵  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

Aluabari 1.4.06 2006- 31.9.08 Complet 190.46 485 (-) (-) 4.58% 417.49 86.08 100 67.51 Work completed Road- Siliguri 07 ed 17.60% and hand over to (76 km) Open Line in Oct'11 NWR Ajmer- 1996-97 Nov- Not Not 566.00 855.16 (+)14.05 not 557.65 65.21 100 297.51 Chittaurgarh- 99 made Applica revised (300 Availab ble km), incl. le material modifications for extension from Udaipur to Umra (11 km) and Mavli Jn.- Bari Sadri (82.01 km) Sri 2003-04 2003 31.03. not 106.09 279.59 (-)13.25 not 241.39 86.34 100 38.2 No Remarks Ganganagar- 11 revised revised Sarupsar Canal Loop (Phase-I) (116 km) Sadulpur- 2007-08 Mar- not Not 643.36 872.22 (-)2.44 not 787.75 90.32 100 84.47 No Remarks & 08 fixed Applica revised Ratangarh- ble Degana (394.35 km) SR Madurai- 1997-98 N.AV N.AV. (Section 246.97 441.69 3.458 NO 369.80 149.73 100 75.35 already commissioned) Thanjavur- 1998-99 N.AV N.AV. (Section 356.88 665.01 14.980 9.226 121.99 34.18 100 541.2495 Villupuram already commissioned) Trichy- 2000-01 N.AV. N.AV. (Section 202.32 410.00 12.790 NO 394.34 194.91 100 40.97 Manamadurai already commissioned)

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͳͶ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

Villupuram- 2000-01 N.AV N.AV. (Section 231.72 780.00 0.441 NO 637.55 275.14 100 297.3197 Katpadi already commissioned) Manamadurai 2006-07 N.AV. N.AV. (Section 138.03 231.58 14.416 8.62 199.80 144.75 100 39.71 - already Virudhunagar commissioned) SCR Guntur- 1992-93 04/20 31-12- 31-03- N.AV. 699.47 N.AV. N.AV. 594.71 85.02 100 104.76 Guntakal- 07 2000 2015, Kalluru 31-03- 2016 Mudkhed – 1995-96 09/20 31-03- 3/31/201 199.06 356.20 No ROR No ROR 321.91 90.37 100 34.29 Adilabad 02 2004 6 made made Dharmavara 1997-98 10/20 N.AV. 31-03- 294.99 704.11 4.49 21.59 658.86 93.57 100 45.25 *ROR on m-Pakala 03 2014, completion is 8.23 31.3.201 6 SER Rupsa- 1995-96 N.AV Completed 50.54 178.76 2.46 0.00 176.86 29.28 100 1.9 Figures shown in Bangiposi col. 13, 14, 15 & 16 are inclusive of MM Bankura - 1998-99 N.AV Completed 111.9 194.5 (-) 0.71 0.00 479.9 46.22 100 943.63 Figures shown in Damodar col. 13, 14, 15 & Valley 16 are inclusive of MM (i) 1st MM: 2002-03 N.AV. Dec-08 Complet 46.255 144.36 (-)238.48 - 100 Rainagar - ed Masagram WR Bharuch- 2006-07 not Aug-10 Sep-11 165.60 332.00 9.20% 9.20% 0 0.00% 100 332.00 Executed by Samni-Dahej availa RVNL. (62.36 KM) ble Total 4349.87 10204.53 8392.60 3116.11

ER Sonarpur- 2000-01 2002 N.AV. N.AV. 30.47 274.47 (-) 10.00 Not 52.87 174.00 100 222.67 Canning Revised

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͳͷ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

[14.96 km]

Kalinarayanp 2000-01 2003 N.AV. N.AV. 43.39 945.29 (-} 21.00 Not 228.87 74.00 100 733.31 kalinaraynpur - ur- Revised Krishnanagar has Krishnanagar been commissioned a] & b] a) & N.AV. N.AV. 651.01 a] (-) Not N.AV. 0.00 100% 0.00 a] Krishnanagar - a]Krishnanag 2001- b) 23.00 b] Revised for [a] Shantipur -GC ar-Shantipur 02, c] 2006 (-) 13.00 commissioned [12 km] -GC , 2008- c) c] (-) b] 09, d] 2010 16.00, d] Krishnanagar- 2010-11 d) (-) 17.00 Chartala [13 Not km] - NL, c] yet Naihati- starte Ranaghat -3rd d line, d] Nabadwipgha t- Nabadwipdha m with extn. To BB Loop [9.58 km] Chandpara- 2003-04 2006 N.AV. N.AV. 22.23 186.88 a] less Not 71.46 38.00 100 127.77 Chandpara- Bongaon than 1.00 Revised Bongaon Section commissioned on 24.07.2012 Pandabeswar 2004-05 2007 N.AV. N.AV. 75.55 292.16 11.00 Not 133.79 46.00 100 % 147.65 Pandabeswar- -Chinpai Revised for a Chinpai has been [21.41 km] only commissioned 01.03.2011 Chinpai- 2005-06 2008 N.AV. N.AV. 86.66 590.91 11.00 Not 121.31 21.00 100 496.22 a] Chinpai- Sainthia Revised Sainthia has been commissioned on 17.5.2010

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͳ͸  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

Ghutiari 2009-10 2011 N.AV. N.AV. 189.97 189.97 (-) 15.00 Not 134.00 71.00 100 % 60.54 a] Ghutiari Sharif- Sharif- revised for a Canning has been Canning with only commissioned extension upto Bangankhali MM for a] 2011-12 Not N.AV. N.AV. 421.06 a] & b] Not 0.00 0.00 0.00 0.00 Bhangankhali yet (-) 15.00 revised - Basanti starte [14.2 km] & d b] Basanti- Jharkhali [23 km] - NL ECR Chapra- 1999- Feb,2 N.AV. N.AV. 72.43 192.22 17.77 N.AV. 169.40 88.13 100 22.82 Section handed Hajipur ( 59 2000 002 over to open line KM) on 30.07.2007 Begusarai- 2005-06 Mar- N.AV. N.AV. 105.57 194.71 14.00 Not 160.85 82.61 100 33.86 Section handed Khagaria 2006 Revised over to open line Doubling on 21.02.12 (40.38 Km) NR Hapur- 2003-04 2003- N.AV. N.AV. 106.64 166.60 19.76 Not 164.69 95.85% 100 3.18 Kankather 04 Revised (42.71 Km) NFR New 1.4.07 2007- Not Complet 99.84 182.9 NA (+) 147.01 80.37 100 35.89 Completed and Guwahati- 08 fixed ed 8.97% commissioned on Digaru- 28.9.11 Patch Doubling (29.81 km) (Phase-I) NWR Jaipur-Dausa 2005-06 Nov- 31.12. 31.03.10 148.38 207.5 (+)18.55 not 209.16 100.8 100 2.89 No Remarks (61.28 km) 06 09 revised SR Calicut- 1995-96 N.AV N.AV. (Section 579.37 621.01 13.430 NO 597.61 103.15 100 20.68 Mangalore . already commissioned)

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͳ͹  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

Madurai- 2003-04 N.AV N.AV. (Section 128.56 261.95 20.718 No 228.59 177.81 100 40.50 Dindugul already commissioned) SCR Gudur - 1997-98 02/20 31-12- 31-03- 133.33 194.18 N.AV. N.AV. 190.76 98.24 100 3.42 Renigunta & 00 2000 2003, Renigunta - 31-03- Tirupati 2013 SEC Bilaspur- 1997-98 1997- 31.07.1 - 270.65 271.34 Not Not 274.76 0.00 100 271.34 R Urkura 98 4 Available Available (110Km) Total 3165.11 4772.091 2885.12 2222.74

G. 10791.33 22777.93 17174.09 7517.05 Total 

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͳͺ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX IV- (REF. TO PARA 1.6.2)

STATEMENT SHOWING THE STATUS OF PROJECTS ( LESS THAN `150 CRORE) WHERE PHYSICAL PROGRESS IS 100 PER CENT n i

` in ` Target date of completion Total anticipated cost ( crore) of Rate Return (in (in ) ) e e g g ercenta ercenta Original Original Revised p p Zonal Railways project of the Name Month and Year of sanction (1- Basis of sanction Socio-economic 2- and consideration socio- other than economic of and year Month of commencement project Original Revised Original Revised Cummulative Cummulative March expenditure till (Rs. in crore) 2014 as of progress Financial March 2014 crore) Remarks Physical progress as of as progress Physical March 2014 Throw forward ( New Lines

CR Puntamba 2000-01 1 2000 N.AV N.AV. 30.22 98.13 5.80% 100.00 100 9.77 shirdi . (16.40)km N.AV. N.AV. 91.5 NWR Ajmer- 2000-01 2 06/2004 28.02. 28.02. 88.40 135.00 -3.40 98.65 100 1.82 Pushkar 09 11 (31.04 Km) not revised not revised 133.18 Bangurgra 2008-09 2 06/2011 not N.A. 144.67 144.67 18.70 95.62 100 5.33 m-Ras fixed (27.8 km) not revised not revised 139.34

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳͳͻ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

SCR Vishnupur 2006-07 2 01/2009 31- 31-03- 52.56 65.24 34.26 102.79 100 1.82 am- 03- 2016 Janpahad 2011 Not revised 67.06 Total 315.85 443.04 18.74 431.08 431.08

Doubling

CR Diva- 1999- 2 2000 N.AV. N.AV. 47.70 231.55 N.AV. 100.00 100.00 151.54 2000 % % Doubling of 5th &

6th line N.AV. 77.11 Panvel- 2000- 2 2002 N.AV. N.AV. 48.00 106.00 N.AV. 100.00 100.00 83.07 Jasai- 01 % % Jawaharlal Nehru Port Trust

(28.5 Km) N.AV. 22.85 ER New 1996- 2 2000 N.AV. N.AV. 18.09 126.17 (-) 25.00 100.00 93.69 commissioned Alipore- 97 17.00% on 13.9.04 d Akra Not Revise 31.15

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳʹͲ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

MM for a] 1 Not yet N.AV. N.AV. 476.49 a] (-) 0.00 0.00 476.49 a)Budge 2009- started 16.00%, Budge- 10, b] (-) Pujali b] b]&c} 17.00%, Pujali- 2011- c] (-) Uluberia[ 12 20.00% Birshivpur ][10.25 km] & c] Pujali-- Bahrahat [9.75 km]-

NL Not Revised 0.00 Habra- 2000- 2 2002 N.AV. N.AV. 40.89 145.12 Less than 50.00 100.00 69.16 Bongaon 01 1.00% Ph-I [Habra- Chandpara

] Not Revised 71.94 MM 2009- 1 Not yet N.AV. N.AV. 104.24 (-) 0.00 0.00 104.24 Machland 10 started 14.00% apur- d Swarupna Not Revise gar 0.00 Barasat- 2000- 2 2002 N.AV. N.AV. 23.65 59.17 Negative 74.00 100.00 1.51 commissioned Sondalia 01 on 04.5.12 [12.12 km] Ph-1 of Barasat Hasnabad

Section Not Revised 43.90 Bandel- 2001- 2 2002 N.AV. N.AV. 51.55 110.24 (-) 8.30% 104.00 100.00 0.60 commissioned Jirat of 02 on 08.2.11 Bandel- d Katwa Not Revise Section 114.87

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳʹͳ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

Baruipur- 2000- 2 2002 N.AV. N.AV. 30.09 52.70 (-) 101.00 100.00 3.26 commissioned Mograhat 01 11.00% on 5.8.11 d [15 km] Not Revise 53.03 Kajra-Kiul 2002- 2 2004 N.AV. N.AV. 23.76 46.68 6.50% 71.00 100.00 14.44 commissioned [15.85 03 d km] Not Revise 32.98 Barharwa- 2003- 2 2005 N.AV. N.AV. 41.13 79.00 1.00% 59.00 100.00 4.50 commissioned Tinpahar 04 d [16.49 km] Not Revise 46.32 Jirat- 2009- 2 2011 N.AV. N.AV. 98.14 139.50 (-) 4.00% 87.00 100.00 16.99 commissioned Ambika 10 Kalna d [20.23 Not Revise km] 121.50 Nalikul - 2009- 2 2011 N.AV. N.AV. 113.33 113.33 (-) 54.00 100.00 25.33 commissioned Tarakeswa 10 10.00% d r [17.18 km] Not Revise 60.98 ECR Tarengna- 2003- 2 June,20 section 46.00 93.44 N.AV. 89.68 100.00 9.64 Ist revised Jehanabad 04 04 commissi estimate (15.20 oned sanctioned by KM) GM/ECR on

N.AV. N.AV. 83.80 06.06.14 Mansi- 2005- 2 N.AV. section 127.07 127.07 N.AV. 14.28 100.00 108.92 Maheskhu 06 commissi nt Patch oned Doubling( 22.12

KM) N.AV. 18.15

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳʹʹ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

Jehanabad 2005- 2 Feb-09 section 127.07 185.77 N.AV. 76.53 100.00 43.60 -Bela 06 commissi (27.47 oned KM) N.AV. N.AV. 142.17 Maheshkh 2005- 2 Feb-06 section 68.75 134.86 14.00 86.99 100.00 17.55 unt- 06 commissi Thanabihp oned d ur (31.75

Km) Not Revise 117.31 Thana- 2005- 2 May,20 section 105.57 68.6 14.00 75.73 100.00 16.65 Bihpur 06 06 commissi Kursela oned Doubling (33.57Km

) Not Revised 51.95 Tilrath - 2005- 2 May,20 section 37.65 37.65 55.00 48.94 100.00 19.22 Begusarai 06 06 commissi d Doubling oned (8.33 Km) Not Revise 18.43 NER Ghagharag Feb-06 2 2007 31.10.12 N.AV. 82.64 130.92 16.17 78.61 100.00 28.01 hat- Chaukagh at N.AV. N.AV. 102.92 NWR Dausa- 2006- 2 04/2008 30.06.20 not 81.00 101.84 26.02 99.97 100.00 0.04 Bandikui 07 10 revised (29.04 Km) not revised not revised 101.81 - 2007- 2 10/2008 31.10.20 not 90.79 91.59 20.87 85.84 100.00 12.98 Harsauli 08 10 revised (34.86 km) not revised not revised 78.62

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳʹ͵  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

Harsauli- 2007- 2 11/2008 31.12.20 not 99.44 133.75 21.66 101.25 100.00 1.67 Rewari 08 10 revised (39.35 km) not revised not revised 135.42 SR Irugur- 1996- 2 N.AV. Section 38.66 120.00 24.85 249.82 100.00 12.09 Coimbator 97 already e commiss ioned No No 96.58 Cheppad- 2003- 2 12/2005 31-05- 04/01/12 26.24 68.74 -2.86 156.67 100.00 22.73 ROR was Kayankula 04 2009 commiss same for m ioned three projects since they are in the same

No No 41.11 stretch. Mavelikar 2003- 2 06/2005 31-05- 22/10/12 48.34 119.49 5.10 242.18 100.00 11.48 a- 04 2009 commiss Chengann ioned ur No No 117.07 Cheppad- 2003- 2 12/2005 30-06- 04/01/12 17.37 40.02 -2.86 185.72 100.00 29.20 Haripad 04 2008 commiss ioned No No 32.26 SECR Bilaspur- 2004- 2 2004-05 N.AV. - 144.19 20.7 71.00 100.00 144.19 Salka 05 140.68 Road- Patch Doubling

(39.4Km) 24.35 106.98 Cph- 2007- 2 2007-08 Dec'10 - 42.93 17.96 157.93 100.00 42.93 Bypass 08 38.86 line N.AV. N.AV. 36.18

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳʹͶ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APR- 2007- 2 2007-08 15.05.10 - 21.01 22.66 66.00 100.00 21.01 Bypass 08 18.42 line N.AV. N.AV. 21.73 Bhilai- 2005- N.AV 2005-06 N.AV. - 61.53 N.AV. 108.00 100.00 61.53 Durg 3rd 06 . 61.53 line(13.15 Km) N.AV. N.AV. 65.19 WR Akodia- 2003- 2 Feb-05 30-06- Not 34.39 11.17% 156.12 100.00 1648.2641 Mom.Khe 04 2010 revised % % ra- Shujalpur Patch

13.15 Km 11.17% 53.69 Total 2932.8 3296.5282 2389.44 611 2097.9919 G.Total 3315.27

‡’‘”–‘ǤͶͺ‘ˆʹͲͳͷƒ‰‡ͳʹͷ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – V (REF. TO PARA NO.1.6.3)

DELAY IN COMMENCEMENT/NON-COMMENCEMENT

Sr. Name of project Zonal Year of sanction Year of commencement No. Railway

New Line

1. Bariarpur-Mananpur via , Lachmipur-Barhat ER 2007-08 Not yet started

2. Chandigarh- Baddi NR 2007-08 Not yet started

3. Kotipalli-Narsapur SCR 2000-01 Not yet started

4. Macherla-Nalgonda SCR 1997-98 Not yet started

5. Manoharabad-Kothapalli SCR 2006-07 Not yet started

6. Bangalore – Satyamangalam SWR 1997-98 Not yet started

Gauge Conversion

1. Akola – Khandwa SCR 2008-09 Not yet started

2. -Himmatnagar-Udaipur WR 2008-09 Not yet started

3. Bhuj-Naliya WR 2008-09 Not yet started

ReportNo.48of2015ƒ‰‡ͳʹ͸  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

 4. Miyagam-Karjan-Dabhoi-Samlaya WR 2011-12 Not yet started

5. Ahmedabad-Botad WR 2012-13 Not yet started

6. Dhasa-Jetalsar WR 2012-13 Not yet started

Doubling

1. Wardha (Sewagram) – NGP (3rd line) CR 2012-13 Not yet started

2. Kalyan Kasara – 3rd line CR 2011-12 Not yet started

3. Princep Ghat-Majerhat ER 2011-12 Not yet started

4. Bazar Sau-Azimganj Jn. ER 2012-13 Not yet started

5. Monigram-Nimtita ER 2012-13 Not yet started

6. Rani Marwar Jn.-patch doubling NWR 2012-13 Not yet started

7. Bangurgram-Guriya patch doubling NWR 2012-13 Not yet started

8. Ajmer-Bangurgram NWR 2011-12 Not yet started

9. Mudhked-Parbhani SCR 2011-12 Not yet started

10. Torangallu-Ranjithpura SWR 2011-12 Not yet started

Total = 22 (NL-6, GC-6, DL-10)

ReportNo.48of2015ƒ‰‡ͳʹ͹  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – VI (REF. TO PARA -1.6.7.1 AND 1.6.7.2) STATEMENT SHOWING VARIATION ABOVE 100 PER CENT BETWEEN DETAILED ESTIMATE AND REVISED ESTIMATE Sl. Zonal Category of Name of the Projects Cost as per Cost as per Variation between No. Rlys. Work (New detailed estimate revised detailed estimate Line, Guage (` In crore) estimate (Original and Conver-sion and (` In crore) revised estimate) (in per cent) Doubling) 2 3 4 5 6 7 1 CR* NL (1) Ahmednagar-Beed-Parli Vaijnath 514.68 2819.88 447.89 2 (2) Belapur-Seawood-Uran Electrified Double Line. 495.44 1814.1 266.16 3 ER NL Dumka-Rampurhat (Phase II of Rampurhat-Mandarhill via Dumka project) 143.71 450.81 213.69 4 ECR NL (1) Const. of Rly. Bridge over River Ganga at Munger. 815.45 2361.87 289.64 5 (2) Patna Ganga Bridge with linking between Patna & Hajipur. (19 KM) 624.47 2921.46 467.83 6 (3) Giridih- Koderma (Phase-I )150 Km 371.36 768.88 207.04 7 (4) Koderma - Ranchi (189 Km) 1033 2957.11 286.26 8 ECoR NL (1) Khurda Road-Bolangir New Line (289 Kms) 92.78 191.00 106.00 9 NR NL (1) Nangaldam-Talwara 257.81 1036.78 302.15 10 (2) USBRL 3077.230 19564.83 535.79 11 (3) Rewari-Rohtak 194.83 901.55 362.74 12 (4) Bhanupalli-Bilaspur 1046.88 2966.98 183.41 13 (5) Deoband-Roorkee 160.01 336.92 110.56 14 NCR NL (1) Agra-Etawah 108.00 427.21 295.56 15 (2) Bhind-Etawah (Part of Guna-Etawah Project) 92.54 384.04 314.99 16 NER (1) Maharajgang-Masarakh-Rewa Ghat 134.42 504.92 275.63

ReportNo.48of2015ƒ‰‡ͳʹͺ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

17 SR* NL (1) Angamali-Sabarimala 517.17 1566.00 203.00 18 SCR NL (1) Nandyal-Yerraguntla 164.36 883.00 437.24 19 (2) Gulbarga-Bidar 369.70 844.15 128.33 20 (3) Cuddapah-Bangalore 1000.23 2050.00 104.95 21 (4) JPTN-MACU with MM for MACU-Janpahad 65.95 313.24 374.97 22 (5) Peddapalli-Nizamabad 407.79 925.30 126.90 23 SWR (1) Bangalore-Hassan via Shrvanbelagola (166 kms) 412.91 1289.92 212.40 24 (2) Hubli-Ankola (167 kms) 997.58 2315.00 132.06 25 (3) Kadur-Chickmagulur-Sakaleshpur (93Kms) 69.15 244.79 151.79

(i) Kadur-Chickmagulur-Sakaleshpur (93Kms) Part -II Estimate - Phase I 104.96 (Kadur- Chickmagulur) (ii) Kadur-Chickmagulur-Sakaleshpur (93Kms) Part -I Estimate - Phase II 88.71 644.78 626.84 (Chickmagulur-Sakaleshpur) 26 ECR GC (1) Sakri-Laukha bazar-Nirmali-Saharsa-Forbesganj(206.06KM)* 372.14 1250.9 207.04 27 (2) JayNagar - Darbhanga- Narkatiaganj (268 KM ) 324.73 1043.56 321.36 28 NFR GC (1) Lumding- Silchar including alignment between Migrendisa- Ditokchera and 1676.76 5185.44 209.25 extension from Badarpur to Baraigram, M.M Baraigram- Dulabcherra (29.4 km) and Karimganj 29 (2) Katihar- Jogbani (108 km) & - Radhikapur (54.26 km), M.M Raiganj- 489.13 1022.64 109.07 Dalkhola (43.43 km) NL 30 SECR GC Jabalpur-Gondia incl. Balaghat-Katangi(285 km) 511.86 1157.54 126.14 31 ECoR DL Jharsuguda - Rengali Doubling (25.60 Kms ) 91.41 201 120 32 NR DL NDLS-Tilak Bridge 5th & 6th line 33.74 138.46 317.33 32 (NL-25, GC-5, DL-2) Note: * Zonal Railways where no feasibility study and engineering cum traffic survey was conducted.

ReportNo.48of2015ƒ‰‡ͳʹͻ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – VII (REF. TO PARA NO. 1.6.7.1)  STATEMENT SHOWING THE DETAILS OF PROJECTS WHOSE ESTIMATES WERE PREPARED AND SUBMITTED BELATEDLY Sl. Zonal Name of project Year of Date of submission of Detailed Estimate Delay in terms of years No. Railways inclusion in Budget/Sanction 1. CR Ahmednagar-Beed-Parli 1995-96 April – 2004 8 Vaijnath (NL) 2. CR Wardha-Nanded (via 2008-09 June - 2014 6 year 2 month Yavatmal-Pusad) – (NL) 3. ECR Const. of Rly. Bridge over 1997-98 March – 2008 10 year River Ganga at Munger (NL) 4. ECR Giridih- Koderma (Phase-I ) 1996-97 May – 2002 5 year 2 month – NL 5. ECoR Khurda Road-Bolangir (NL) 1994-95 June – 2001 7 year 2 month* 6. SR Angamali-Sabarimala (NL) 1997-98 Sept. – 2004 6 year 6 month 7. SCR Gulbarga-Bidar (NL) 1997-98 January – 2003 5 year 8 month 8. SER Tamluk-Digha (NL) 1984-85 January – 2000 15 year 9. SECR Dallirajhara-Jagdalpur (NL) 1995-96 July – 2014 18 year 1 month # 10. SWR Bangalore- Sathyamangalam 1997-98 Nov. – 2013 16 year 7 month (NL) 11. SWR Munirabad-Raichur (NL) 2007-08 July - 2012 5 year 3 month 12. WCR Ramganj Mandi- Bhopal 2000-01 August – 2007 6 year (NL) 13. ECR Jay Nagar - Darbhanga- 1997-98 April – 2002 5 year 1 month Narkatiaganj (GC) 14. SR Cuddalore-Salem via 1999-2000 March – 2001 5 year 6 month Vriddachalam (GC)

Note: Detailed Estimate not submitted till March 2014. * This is for Part estimate for 36 Km. Detailed estimate for the entire project was not prepared.

ReportNo.48of2015ƒ‰‡ͳ͵Ͳ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – VIII (REF. TO PARA NO. 1.6.7.3) BRIEF RESULTS OF HIGH PRIORITY PROJECTS

1. Wardha-(Sevagram)-Nagpur-3rd line (Doubling) - (Central Railway)

The project was sanctioned during 2012-13, with an original cost of ` 297.85 crore on the ground to connect the Northern, Central and South regions of the country. The estimated ROR of this project was 15.18 per cent. The cumulative expenditure on the project as on March 2014 was ` 3.90 crore. The project is yet to commence. Even the target date for completion of the project has not been fixed.

2. Rampurhat-Muraroi New Line Project (Eastern Railway)

The project with ROR of (-) 11per cent was sanctioned as Material Modification (MM) to the Rampurhat-Manderhill New Line Project in the year 2011-12 at an anticipated cost of ` 224.05 crore on the ground to development and advancement to the people of backward areas of Santhal Parganas region. The sanction of a fresh New Line project as MM to an ongoing project was not in compliance with the Para 1110 of Engineering Code. Moreover, the project involving cost of more than ` 100 crore had no Cabinet Committee of Economic Affiars (CCEA) approval. Although about 3 years already elapsed from the date of sanction, the work has not been commenced yet. The detailed estimate sanctioned on 24.10.2014 targeted for completion in March 2018.

3. Tinpahar-Sahibganj Doubling Project (Eastern Railway)

The project with ROR of 11.20 per cent was sanctioned in 2009-10 at an estimated cost of ` 182.56 crore. The objective of the project was to cater augmentation of traffic by doubling. The detailed estimate was sanctioned in March 2010 and work commenced in 2011. With the incurrence of ` 84.96 crore the physical progress upto March 2014 was 30 per cent. After declaring High Priority the target date for completion of the project has been set as December 2015.

ReportNo.48of2015ƒ‰‡ͳ͵ͳ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

4. Sahibganj- Pirpainti doubling project (Eastern Railway)

The project having ROR of 12 per cent was sanctioned in the year 2010-11 at an anticipated cost of ` 129.45 crore on commercial ground. The detailed estimate was sanctioned in May 2010 and work was commenced in 2012. With the incurrence of ` 60.76 crore the physical progress upto March 2014 was 55 per cent. After declaring High Priority the target date for completion of the project has been set as December 2014.

5. Pirpainti-Bhagalpur Doubling Project (Eastern Railway)

The Pirpainti-Kahalgaon doubling project is a section of Pirpainti-Bhagalpur which was sanctioned in 2011-12 at an estimated cost of ` 332.14 crore. The project with ROR of (-) 8 per cent was considered on socio-economic development basis. The detailed estimate was sanctioned in March, 2012 and the work was commenced in 2013. There was no physical progress of the project after incurring expenditure of ` 13.05 crore upto March 2014. After declaring High Priority the target date for completion of the project has been set as 2015-16. In 2014-15, only ` 5 crore as against the required fund of ` 40 crore has been allotted to the project.

6. Sainthia-Tarapith 3rd line project (DL) (Eastern Railway)

The project having ROR of 16 per cent was sanctioned in the year 2011-12 at an anticipated cost of ` 186.64 crore with the objective to cater for the freight and passenger transport requirements (Commercial ground). After incurring expenditure of ` 15.84 crore upto March,2014 the project could achieve no physical progress and outlay for the project from 2012-13 to 2013-14 was ` 45 crore. It was reported by Zonal Railway that the slow progress of the project was due to shortage of fund.

7. Tarapith-Rampurhat 3rd line project (DL) (Eastern Railway)

The project having ROR of 16 per cent was sanctioned in the year 2012-13 at an anticipated cost of ` 56.30 crore on commercial ground. The detailed estimate was sanctioned on 11.02.2013 and after incurring expenditure of ` 1.31 crore upto March 2014 the project could achieve no physical progress. Although categorized as High Priority only ` 4 crore has been allotted to the project in the year 2014-15 and no commissioning target has been fixed in the years 2014-15 and 2015-16. The commissioning has been targeted in the year 2016-17. However, the preliminary works like Earthwork and Blanketing works have not been started yet.

ReportNo.48of2015ƒ‰‡ͳ͵ʹ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

8. Hajipur-Ramdayalu Nagar Doubling Project (East Central Railway)

The construction of double Line from Hajipur to Ramdayalu Nagar was conceptualized to remove traffic bottlenecks in the section and to ensure the smooth flow of traffic. Ist part detailed estimate of the project was sanctioned at a cost of ` 96.16 crore in August, 2013. Subsequently the detailed estimate of the project was sanctioned at a cost of 367.17 crore. A total of ` 0.05 crore was incurred on the project and the physical & financial progress of the project was 0 & 0.01 per cent respectively as on 31st March, 2014.The project is targeted to complete by 31.12.2018.

9. Garhwa Road - Ramna Road (DL) (East Central Railway)

The project was conceptualized to tap the mineral resources of the area and to ease out the traffic constants of the existing single line. The rate of return (ROR) of the project was assessed at 36 per cent. The detailed estimate at a cost of `363.52 Crore is under approval. The project is targeted to complete by 31.12.2017.

10. Jharsuguda-Rengali (DL) (East Coast Railway)

Jharsuguda- Rengali doubling (25.6 Km) was taken up in 2005-06 in consideration of growth of traffic in Jharsuguda- section (48.656 Km). The line connects HWH- main line with industrial belt developed around Jharsuguda- Sambalpur-Angul section. The RoR of the project was initially 14.28 per cent which was revised to 27.36 per cent for the entire section from Jharsuguda to Sambalpur.

11. Utretia-Zafrabad doubling project including Material Modification - (Northern Railway)

The project was sanctioned in the year 2006-07 with an object to increase the line capacity. The project was proposed for completion by March 2009.The detailed estimate for this work was sanctioned at a cost of ` 369.90 crore in July-2006. The abstract cost of ` 301 crore has escalated to ` 1565 crore as per revised detailed estimate (proposed in August 2014) including MMs.Inclusion of three MMs of ` 734.18 crore in the original work of Doubling increased the cost of project. The project which was sanctioned seven years ago was having a mearge 27.5 km out of 148 km physical progress and no target was set for completion of the project.

ReportNo.48of2015ƒ‰‡ͳ͵͵  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

12. Lumding-Silchar (GC) (North East Frontier Railway)

The National project “Lumding-Silchar (LMG-SCL) Gauge Conversion Project” which was originally sanctioned for ` 648 crore was revised to `5185.44 crore in 2014 with the objective to cater the traffic demand in the states of , , and (On socio-economic ground). The increase in project cost inter-alia included the revision in the scope of works, escalation and inclusion of five branch lines as a Material Modification with sanctioned cost of ` 480.12 crore to the project since 2000. Lumding- Silchar section was, however, flagged off by the Minister for Railways from New on 27 March 2015. The section was not allowed (30 March 2015) to open to passenger traffic by the Commissioner of Railway Safety (CRS) due to non-compliance rules for Railways for Public Carriage of Passenger and BG SOD, 2004 and the same was, however, condoned by the Railway Board. No inspection was done by CRS for 100 Km (out of 215Km). 13. Thanjavur-Ponmalai Doubling project with bye-pass line before Ponmalai (Goldenrock) - (Southern Railway) This project was sanctioned during 2011-12 at an estimated cost of ` 434.62 crore to improve the line capacity of the section and also to meet the future requirements. Locos and brake vans of freight trains going from Thanjavur to Chord line and vice versa, had to be reversed at Ponmalai resulting in detention of minimum 90 minutes per train at Ponmalai due to turnaround of Locos and Brake vans. Locos of coaching trains were also detained due to crossings. The bye-pass line before Ponmalai was proposed to remove this detention. Operational savings to the extent of ` 5.39 crore per annum were expected to materialize due to avoidance of crossings to trains, both coaching and goods, along with elimination of engine reversal to freight trains at Ponmalai.

x The Bye-pass line work was commenced in September 2012 and the civil engineering work was completed (March 2014). Electrical and Signal &Telecommunication work was handed over to RVNL ( Limited). These works were yet (March, 2014) to be completed.

ReportNo.48of2015ƒ‰‡ͳ͵Ͷ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

x The doubling work between Thanjavur and Ponmalai was handed over (January 2014) to RVNL for execution. The work is yet (March, 2014) to be taken up. 

Though, “High Priority” was assigned to this work by RB, no target date was fixed for completion of the work. An expenditure of ` 29.92 crore had been incurred (March 2014) and the physical progress achieved (March 2014) was three per cent since two years of sanction of the project. Land to the extent of two hectares was yet to be acquired for the project. The throw-forward of the project was ` 150.10 crore. The non-completion of Thanjavur-Ponmalai bye pass line delayed the realization of projected operational savings.

14. Kankanadi-Panambur Patch Doubling (Southern Railway) Kankanadi-Panambur is a single line section (19.34 Km) in the Mangalore-Panambur section. The detailed estimate was sanctioned (February 2009) at an estimated cost of ` 149.20 crore with ROR of 29.26 per cent to augment the line capacity of Mangalore – Panambur section. An additional line was proposed from Jokatte yard to Panambur as a material modification which was to eliminate operational constraints in obtaining permission from KRCL for passing Tokkur yard. Thus the work was expected to eliminate detention to . The work commenced (January 2009) after a delay of around two years from sanction and the physical progress (March 2014) was 13 per cent after over five years of its commencement. The throw-forward expenditure of the project was `105.51 crore. The work was progressing slowly due to heavy yard work and tunnel works. No target date was set for completion of the project.



15. Kazipet- Vijayawada (3rd line) (South Central Railway) The project was sanctioned in the year 2012-13 at an anticipated cost of `1054.35 crore with an expected Rate of Return (ROR) at 19.97 per cent . The line was taken up to improve capacity constraints and to facilitate to connect -Delhi, SC 3rd line proposed to increase line capacity. The project was identified as High priority project by Railway Board. The work was taken up in phases as detailed below:

ReportNo.48of2015ƒ‰‡ͳ͵ͷ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

(a) Kondapalli- Vijayawada (17.49km) Part Detailed estimates for `163.50 crore sanctioned by Railway Board in August 2014. Only S&T works are under progress and Civil Engineering works have not been commenced as land acquisition is in progress.

(b) Kazipet- Kondapalli. Final location survey has been completed and Part Detailed estimate submitted to Accounts for vetting.

As against the estimate for `1054.35 crore, only `0.42 crore was incurred till March, 2014 with 0 per cent physical progress and a balance throw forward cost of `1053.93. The project is to be completed by 31-03-2023. Detailed estimate for phase one was only approved so far by Railway Board. Though only a minimum of 3.50 hectares was identified for acquisition, the proposals have not been initiated yet.

16. Goelkera-Monaharpur 3rd line (DL) - (South Eastern Railway)

The project was included in the Pink Book 1997-98 at an approximate cost of ` 95.29 crore with the objective to cater anticipated growth of traffic on account of expansion of Steel plant, Cement Plant and additional coaching traffic. The work was frozen in July 2001 and further de-frozen in February 2006. The project was transferred to RVNL in March 2008. The latest anticipated cost of the project has gone up to ` 360 crore. The project was initially declared as 'High Priority' project in July 2013. Though the first phase of the project, i.e., Monaharpur-Posotia was completed in March 2013, it could not be opened for traffic till March 2014. The total cost incurred on this project was ` 144.97 crore up to March 2014. Due to inconsistent decisions taken by railway over a period of time i.e. freezing the project for five years after taking it up and then after another seven years categorizing as a 'High priority' project, the project suffered severe delays and cost overrun. After 16 years from taking up of the project, the work is still going on (Physical Progress 80 per cent) and the cost of the project has increased almost three times.

17. Sini – Adityapur 3rd line (DL) (South Eastern Railway) The project was sanctioned by Railway Board in 2010-11 at an estimated cost of

ReportNo.48of2015ƒ‰‡ͳ͵͸  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

` 143.16 crore with the target to complete the work in three years. The work is still to be completed (November 2014) even after a lapse of more than four years. The main objective of taking up the project was to enhance the throughput of the sections covered under the project (Commercial purpose). The stated objectives of taking up the project were defeated due to delay in completion of the project as the utilisation of line capacity of the existing lines which was 91.8 per cent at the time of the proposal in PWP (2008-09) had increased to 114 per cent in September 2014, thereby increasing the line congestion rather than augmenting it.

18. Birur–Shivani DL (RRB–SHV) and Hosadurga Road–Chickjajur DL (HSD–JRU) (South Western Railway)

Birur–Hosadurga–Chickjajur section is a sub-section of Tumkur-Hubli (TK-UBL) section of Mysore Division. This is a single line non-electrified section. The length of the section is 67.54 km with a ruling gradient of 1 in 100 (compensated) and maximum speed is 100 kmph. Maximum permissible speed of the goods train is 75 kmph. This section was handling, each way, daily 13 Express trains, 4 Passenger trains and 7 goods trains. Due to single line virtually there was no path available between 22:00 hrs to 04:00 hrs. Goods trains were regulated/ stabled at Birur, Ajjampura and Shivani duly shutting down the . Hence the urgent need to increase the charted capacity to accommodate freight trains. Commissioning of Hassan-Mangalore (HAS–MAQ) BG conversion has also resulted in increase in carriage of freight by 4 million tons (Iron Ore) over this section towards MAQ port. The bottleneck was this section as DL upto Birur was almost complete. DL of the section between RRB–JRU will result in avoiding the crossing of trains thereby resulting in reduction of the overall running time. The section between RRB–JRU was taken up as 3 patch doubling projects as follows:

Sl. No. Name of the Section Distance (km) Ref. to PB Abstract cost (` in crore)

1 RRB–SHV 28.68 24 of 2010-11 121.98 2 HSD–JRU 28.89 25 of 2010-11 116.00 3 SHV–HSD 9.98 28 of 2011-12 33.36 Total 67.54 271.34

ReportNo.48of2015ƒ‰‡ͳ͵͹  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

19. RRB–SHV patch doubling This patch doubling was originally approved in Railway Budget in the year 2010-11 at an anticipated cost of ``121.98 crore. Detailed Estimate was sanctioned for `142.64 crore vide No. 2010/W-4/DL/SWR/BS dated 31/05/2011. This project was afforded the status of “High Priority” during the year 2013-14.

20. HSD–JRU Patch doubling

This project was originally approved in Railway Budget 2010-11, at an abstract cost of `116.00 crore. Detailed Estimate was sanctioned for `203.40 crore vide Railway Board letter No. 2012/W1/DL/SWR/HRC dated 04/07/2013. This project was included as “High Priority” project during 2013- 14.The projects were sanctioned for a total stretch of 67.54 km (Birur-Chikjajur Section) at an overall cost of `475.85 crore with a view to iIncrease the chartered line capacity, reduce the running time of trains, provide additional paths for Goods trains and increase average speed of Goods trains.

These projects were justified on the ground that the total utilisation of the charted capacity of the section was to the extent of 137 per cent (2008-09 and 2009-10).

Further, Railway Board, vide Pink Book item No.17 of 2007-08 had sanctioned Traffic Facility works of strengthening of nine stations on iron ore moving routes. Out of these nine stations, works of provision of crossing stations at Ajjampur, Hosadurga Road, Ramagiri and Holalkere fell in the same Birur–Chikjajur section. This work was sanctioned as urgent measures were required to increase the line capacity of the section. A third line with CSL of 715 meters was to be provided at these stations which would serve to ease out the congestion in this section. The work was taken up for execution only in 2013 in four stations. Even those four stations fell in other than the Birur-Chikjajur Section. However, works in the four stations Ajjampur, Hosadurga Road, Ramagiri and Holalkere falling in Birur-Chikjajur Section were handed over to the Construction organization even as doubling work in the section was in progress.

Incidentally, Tumkur-Davanagere NL Project was sanctioned during 2011-12 (during the same period the patch doubling projects were sanctioned) as a cost sharing project with GoK in the ratio of 50:50 with land to be provided free of cost by the State Government. This project was sanctioned with a view to divert passenger traffic on Bangalore-Hubli section and beyond from the existing line via Birur-Chikjajur. Out of 17 passenger services on

ReportNo.48of2015ƒ‰‡ͳ͵ͺ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

the Birur-Chikjajur route, more than 50 per cent were towards Hubli from Bangalore. This NL was also shorter by more than 55 kms to the existing route via Birur-Chikjajur.

The proposal and sanction of the three patch doubling projects were not justified for the following reasons:

Out of the total utilization of 137 per cent of the charted capacity of the section, 75 per cent of the capacity accounted for running of passenger trains. Goods trains occupied to the extent of 20 per cent and the balance five per cent by other trains. Even the NL would serve to ease the capacity utilization of Birur-Chikjajur by more than 50 per cent in addition to the adding up of new lines for a length of 199.70 km with scope for development of the backward areas along the new line.

Thus, failure of Railway Administration in completing the traffic facility works sanctioned in 2007-08 had resulted in increased capacity utilization of the line to 137 per cent during 2008-09and 2009-10. It is pertinent to note that due to imposition of ban on Iron-Ore by Honorable Supreme Court during June 2010, the capacity utilization eased out and came down drastically to 78 per cent in 2013-14. Railway Administration being aware of reduction in Iron-Ore traffic could have continued operation in the section with single line duly increasing line capacity by completing the traffic facility work in all the nine stations.

Thus the objective of easing/ increasing the line capacity of Birur-Chikjajur section could have been achieved by completing the sanctioned traffic facility works and execution of the Tumkur-Davanagere NL project. Proposing and sanctioning of the patch doubling works in Birur-Chikjajur at a huge cost of `395.80 crore, on the eve of Tumkur-Davanagere NL was totally unjustified. The expenditure of `177 crore already incurred on the doubling project upto 31/03/2014 would remain unproductive.

21. Viramgam-Surendranagar (DL) (Western Railway)

The work was scheduled to be completed by March 2014. Out of total length of 65.26 km as on 05/08/2015, 53.01 km is pending.

ReportNo.48of2015ƒ‰‡ͳ͵ͻ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

22. Udhna-Jalgaon with electrification (DL) (Western Railway)

The work was scheduled to be completed by March 2014 as per original DOC. Till March 2015, 229 Kms was completed, out of which 85 Kms was commissioned. The revised target date for completion of balance 65 kms was scheduled for completion by March 2016 and balance 13 kms scheduled for completion by March 2017. Increase in time lag for completion resulted in increase in project cost per km from the original ` 2.32 crore to `7.06 crore.

23. Bhopal-Bina project 3rd line– RVNL-(DL) (West Central Railway) The construction of Bhopal- Bina 3rd line (143 Kms) was taken up primarily for enhancing the throughput of the sections. The project was sanctioned in the year 2008-09 and taken up in October 2009 with the original target of completion in August 2011. The target date of completion was revised to December 2015. 86 per cent of the work was completed as of March 2014. Out of a total length of 143 kms., only 19 kms. of section length was commissioned. Thus, due to delay in completion of the whole project, the objective of increasing the throughput was delayed to that extent. 24. Bina-Kota – RVNL (DL) (West Central Railway) The objective of the project was to increase rake capacity due to upcoming Thermal Power stations i.e. Motipura chowki and Salpura. The Detailed Estimate was sanctioned in September 2012 and work was commenced in October 2012 with target date May 2017. It was seen that only 3.35 per cent of work has been completed as of March 2014. 

ReportNo.48of2015ƒ‰‡ͳͶͲ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – IX (REF. TO PARA -1.6.9) STATEMENT SHOWING ALLOTMENT OF FUNDS VIS-À-VIS PHYSICAL PROGRESS (LESS THAN 50 PER CENT) ( ` IN CRORE) S. No. Name of project Railway BG / Year AE during the Percentage of AE to Physical progress in same year BG per cent New . Belapur-Seawood-Uran Electrified Double CR 92.5 (2010-11) 5.13 13.12 12 line 55 (2011-12) 11.07 20.12 12 2. Khurda Road-Bolangir New Line (289 ECoR 28.1 (2009-10) 13.92 49.54 10 Kms) 120 (2010-11) 54.49 45.41 11 3. Talcher - Bimlagarh 50 (2010-11) 20.17 40.34 5 30 (2012-13) 14.63 48.77 6 4. Giridih- Koderma (Phase-I ) 150 Km ECR 60 (2010-11) 16.67 27.78 Not made available 5. Koderma - Tilaiya( 68 Km) 20 (2010-11) 5.80 29.00 30 (2011-12) 9.92 33.07 6. Agra-Etawah NCR 50 (2011-12) 0.94 1.88 84 7. Jind- Sonepat (88.90 Km) NR 33.30 (2011-12) 2.56 7.69 27 8. Chandigarh- Baddi (33.23 Km) 1.91 (2009-10) 0.00 0 0 9. Deoband- Roorkee (27.45 Km) 20 (2012-13) 4.69 23.45 5 10. Cuddapah-Bangalore SCR 29 (2009-10) 0.78 2.69 3 40 (2010-11) 7.59 18.98 3.93 50 (2011-12) 0 0 5 11. Dallirajahara-Jagdalpur (235 km) SECR 115 (2010-11) 0 0 0 12. Wadsa-Gadchiroli (49.5 km) 2.00 (2013-14) 0.23 11.5 Not available 13. Bowaichandi-Arambagh (31 km) SER 20 (2010-11) 0.55 2.75 1 122 (2011-12) 16.13 13.22 5 14. Bagalkot-kudachi (142Kms) SWR 30 (2012-13) 1.94 6.47 0 15. Bangalore- Sathyamangalam (260 Kms) 2 (2012-13) 0.06 3 0

ReportNo.48of2015ƒ‰‡ͳͶͳ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

16. Hubli-Ankola (167 kms) 5 (2009-10) 0.47 9.4 15 17. Munirabad-Raichur (165 kms) 20 (2009-10) 2.65 13.25 5 GC 1. Bardhaman-Katwa [51.52 km] with New ER 40 (2009-10) 0.01 0.025 0 Material Modification for Katwa-Bazarsau [30.59 km]- Doubling. Katwa[Dainhat]- Mateswar [34.4 km] 2. Ratlam-Mhow-Khandwa-Akola (472.64 WR 25 (2009-10) 1.07 4.28 0 kms) DL 1. Pirpainti-Bhagalpur (59.06 km) ER 20 (2011-12) 0 0 0 2. Tinpahar-Sahibganj [37.81 km] as Ph-1 of 13 (2009-10) 0 0 0 doubling of Tinpahar-Bhagalpur 3. Sahibganj-Pirpaniti (10.45 km) 4 (2010-11) 0.54 13.5 0 4. Nabadwipdham-Patuli 20 (2011-12) 1.43 7.15 0 5. Salka Road-KGS-Patch Doubling (26 SECR 60 (2011-12) 3 0.05 39.3 Km) 6. Khodri-Anuppur with flyover at BSP (61.6 60 (2011-12) 5.55 9.25 46.98 Km) 7. CPH-JSG 3rd line 10 (2009-10) 2.33 23.3 0 25 (2010-11) 3.01 12.04 10 50 (2011-12) 9.4 18.8 10 8. Goelkera - Monoharpur 3rd Line SER 39.45 (2009-10) 0.01 0.03 0 9. Sini - Adityapur - 3rd line 4 (2010-11) 0.04 1 1 10. Viramgam-Surendranagar (65.26 kms) WR 5 (2010-11) 0.04 0.8 0 59 (2011-12) 5.35 9.07 0 Total = 29 (NL-17, GC-2, DL-10) 11 ZRs 

ReportNo.48of2015ƒ‰‡ͳͶʹ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – X (REF. TO PARA-1.6.9) STATEMENT SHOWING EXCESS EXPENDITURE AGAINST BUDGET ALLOTMENT) (` IN CRORE) S. Name of project Railway BG (year) AE during same year Percentage of excess expenditure No. NL 1. Ahmednagar-Parli Vaijnath CR 55 (2011-12) 77.10 40.18 25 (2012-13) 78.83 215.32 2. Belapur-Seawood-Uran Electrified Double line 10 (2013-14) 52.99 429.9 3. Talcher - Bimlagarh ECoR 10 (2009-10) 21.42 114.20 5 (2013-14) 12.3 146 4. Const. of Rly. Bridge over River Ganga at Munger ECR 40 (2009-10) 61.58 53.95 57 (2011-12) 114.29 100.51 5. Patna Ganga Bridge with linking between Patna & Hajipur. (19 KM) 40 (2009-10) 91.42 128.55 50 (2011-12) 157.38 214.76 14 (2012-13) 145.16 936.86 6. Giridih- Koderma (Phase-I ) 150 Km 10 (2009-10) 40.10 301 7. Koderma - Ranchi (189 Km) 68 (2009-10) 184.53 171.37 8. Deoghar-Dumka [72.25 km] ER 16.50 (2009-10) 29.63 79.58 2.88 (2011-12) 32.11 1014.93 9. Rampurhat-Mandarhill via Dumka (130 km) 30 (2010-11) 105.64 252.13 10. Agra-Etawah NCR 25 (2009-10) 62.18 148.72 20 (2012-13) 58.77 193.85 11. Nangaldam-Talwara (83.74 Km) NR 25 (2009-10) 87.75 251 12. Rewari-Rohtak (81.26 Km) 35 (2009-10) 59.83 70.94 13. Jind- Sonepat (88.90 Km) 15 (2009-10) 87.47 483.83 14. Nandyal-Yerraguntla SCR 40 (2011-12) 150.25 275.63 15. Gulbarga-Bidar 15 (2013-14) 112.68 651.2 16. PDPL-KRMR-NZB 15 (2009-10) 43.25 188.33 17. Bangalore-Hassan via Shrvanbelagola (166 kms) SWR 70 (2012-13) 134.22 91.74 18. Kadur-Chickmagulur-Sakaleshpur (93Kms) 5 (2009-10) 30.50 510 19. Rayadurga-Tumkur via Kalyandurga (206 kms) 5 (2010-11) 20.79 318 GC 1. JayNagar - Darbhanga- Narkatiaganj (268 KM ) ECR 30 (2010-11) 75.50 151.67

ReportNo.48of2015ƒ‰‡ͳͶ͵  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

2. Quilon-Tirunelveli-Tiruchendur; Tenkasi – Virudunagar SR 0 (2011-12) 79.99 100 DL 1. Utratia-Zafrabad doubling of balance 148 km section with MMs for NR 8.92 (2009-10) 69.60 680.27 Raibareli-akbarganj (46.9 km) and Sultanpur- (19.22 km) with new MM of Sultanpur-Kadipur(38.7 km)- new lines 2. Goelkera - Monoharpur 3rd Line SER 10 (2011-12) 37.63 276.3 3. BPL-BINA-3rd LINE WCR 35 (2009-10) 130.87 273.91 50 (2010-11) 200.37 300.74 Total = 24 (NL-19, GC-2, DL-3)

ReportNo.48of2015ƒ‰‡ͳͶͶ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX- XI (REF. TO PARA 1.6.9.3)

BRIEF RESULTS ON COST SHARING PROJECTS

In 10 ZRs ((CR, ER, ECR, NR, NWR, SR, SCR, SER, SECR and SWR), 38 projects covering a length of 3551.67 Km were taken up on cost sharing basis with the State Governments. The original target date of completion was not fixed for 23 projects (NL-22, GC-1). Further, dispute noticed in four cost sharing projects as the State Government refused to bear this additional financial liability due to increase in land cost. 12 cases were delayed from original date of completion. In 24 cases, the target date was not fixed or not available. The brief results of these 38 ongoing cost sharing projects are given below:

1. Ahmednagar-Beed-Parli Vaijnath New Line project - (Central Railway):-

The project Ahmednagar-Beed-Parli-Vaijnath was sanctioned during the year 1995-96 on socio economic basis with the aim to provide infrastructure for the speedy economic development of the backward area of . The project commenced during the year 1996 with estimated Rate of Return (ROR) being (-) 0.208per cent. The project is still going on for the last 18 years and the physical progress was only five per cent as on 31.03.2014. The original target date was 24 months from the date of sanction of the work; however there was no revision of target date for the completion of the project thereafter. This project was undertaken on 50:50 cost sharing basis with the Government of Maharashtra. Original cost of the project was ` 353 crore which was revised to ` 2820 crore in March 2014. The Railways share at the initial stage was ` 176.54 crore which was increased to `1410 crore as per the latest anticipated cost of the project. The cumulative expenditure on the project as on March 2014 was ` 299.28 crore. The balance amount required for completion of the project as per PB of 2014-15 was ` 2486.08 crore, of which Railway’s share was ` 1249.95 crore and Government of Maharashtra’s share was `1236.13 crore. The work was to be carried out in five phases. Sanction for 15 kms from ANG-Narayandoh was received in January 1999. Sanction for the balance kms was received in May 2008. Land acquisition for first 15 kms was completed and formation along with the bridge work was completed in March 2006. The work could not be put to use as the P. way and other works were not completed. The unfruitful expenditure of ` 15.15 crore, incurred on the first phase was taken up in audit in Draft Paragraph No.11 of 2005-06

ReportNo.48of2015ƒ‰‡ͳͶͷ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

Achieving the desired objective seems very remote and the completion of the project also looks equally remote considering the pace of progress and the time over run of the project. 2. Wardha-Nanded (via Yavatmal-Pusad) New Line – (Central Railways):- The project of Wardha-Nanded (via Yavatmal-Pusad) New Line was sanctioned during the year 2008-09, on socio economic consideration with the aim to provide the infrastructure for the speedy economic development of the backward area of Maharashtra. The project commenced during the year 2010 with estimated Rate of Return (ROR) being -2.684per cent. The project is going on for the last 4 years and the physical progress is only 10per cent as on 31.03.2014. The original cost of the project was ` 697 crore which was revised to ` 2500 crore in March 2014. The target date for completion of this project has not been fixed. This project was undertaken on 60:40 cost sharing basis with the Government of Maharashtra (40per cent). Railway’s share at the initial stage was Rs 418.20 crore which increased to `1500 crore as per the latest anticipated cost of the project. The cumulative expenditure on the project as on March 2014 was ` 68.25 crore. The balance amount required for completion of the project as per PB of 2014-15 was ` 2432.68 crore, of which Railway’s share was ` 1473.64 crore and the Government of Maharashtra’s share was `959.04 crore. As the target date for completion of the project was not been set, achieving of the objective has become remote and the completion of the project also looks equally remote considering the pace of progress and the time over run of the project. Feasibility study and Engineering cum traffic survey was also not conducted for this project.

3. Belapur-Seawood-Uran Electrified double line – (Central Railway) The project of Belapur-Seawood-Uran Electrified double line was sanctioned during 1996-97 with an abstract cost of ` 401.80 crore for development of Navi Mumbai & facilitate operation of train services connecting Greater Mumbai. This project was undertaken on 33:67 cost sharing basis with CIDCO. The Railway’s share of ` 132.59 crore at the initial stage increased to ` 604.83 crore as per the latest anticipated cost of the project. The cumulative expenditure on the project as on March 2014 was ` 372.89 crore. The project cost was revised to ` 1814.48 crore in March 2014. The balance amount required for completion of the project as per PB of 2014-15 was ` 1543.84 crore, of which Railway’s share was ` 452.70 crore and CIDCO’s share was `1091.14 crore. The route length of the Railway line was 23 Km. The main purpose of this project was to improve the accessibility of the central part of Navi Mumbai from other peripheral area of the region where development was planned/taken place. The project commenced during the year 1996 and

ReportNo.48of2015ƒ‰‡ͳͶ͸  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

has been going on for the last 18 years and the physical progress is only 15per cent as on 31.03.2014. The original target date was 4 years from the date of sanction of the work. The work was now to be completed by June 2014, subject to availability of funds and clear site. Achieving the desired objective seems very remote and the completion of the project also looks equally remote considering the pace of progress and the time over run of the project. 4. Construction of Rail cum Road Bridge across River Ganga at Munger – New Line – (East Central Railways) The Project “Construction of Bridge over River Ganga at Munger was sanctioned in 1997-98 at an anticipated cost of ` 920.77 crore. The Detailed Project Report (DPR) of the work was submitted by RITES in Feb, 2002 & the work was taken up keeping in the mind the socio- economic upliftment of the region since the Rate of Return (ROR) of the project was on lower side (1.545per cent). The Cabinet committee on Economic Affairs (CCEA) gave the clearance for the Rail Bridge in September, 2002 and Railway decided to execute the work on cost sharing basis with Ministry of Surface and Road Transport (MOSRTH). It was agreed by the parties concerned that the cost of Main Bridge will be shared in 56.64 & 43.36 per cent by the Railway and Sharing Agency & the cost of Guide Bund will be borne equally by the both parties. It was also decided that the cost of Rail link and Road line will be borne by the Railway and the sharing agency respectively Accordingly, the Project Rail cum Road Bridge across River Ganga was sanctioned by Railway Board on 07.10.02 at a total cost of ` 921 crore with Railways share as ` 539 crore and Ministry of Surface and Road Transport (MOSRTH) share of Rs 392 crore. The said estimate of the project was sanctioned in four part estimates excluding the road portion at a total cost of ` 815.45 crore. The detailed cost of the project was later revised and the Railway Board sanctioned the revised estimate of the project including the cost of road approaches at a total cost of ` 2361.87 crore with Railways’ share as ` 1246.55 crore and MOSRTH’s share as ` 1115.32 crore. A total of ` 1341.09 crore was incurred on the project and the physical & financial progress of the work was 72 & 57 per cent respectively as on 31st March, 2014. The work was originally targeted to be completed by 31.12.2007 but the work is still incomplete in spite of lapse of approximately seven years since the original target date of completion. Moreover, the target date of the completion of the project has now been fixed as 30.06.2015. 5. Construction of Rail cum Road Bridge across River Ganga at Patna New Line – (East Central Railways)

The Project “Construction of Bridge over River Ganga at Patna was sanctioned in 1997-98 at an anticipated cost of ` 600 crore. The Detailed Project Report (DPR) of the work was submitted by the RITES in June, 2001 the work to be taken up keeping in the mind the socio-economic upliftment of the region since the Rate of Return (ROR) of the project was on lower side (5.6 per cent). The detailed estimate of the project was sanctioned by the Railway Board at a cost of ` 624.47 crore in January 2002. Meanwhile Railway Board enhanced the scope of work and

ReportNo.48of2015ƒ‰‡ͳͶ͹  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

agreed for the construction of Rail cum Road Bridge on cost sharing basis with the Government of State of at an abstract cost of ` 1389 crore. The sharing cost of the project on behalf of the state of Bihar was to be funded out from the Backward Region Development Fund (BRGF).It was decided that the cost of Main bridge will be shared in 57 & 43 per cent by the Railway and Sharing Agency & the cost of Guide Bund will be borne equally by the both parties. It was also decided that the cost of Rail link and Road line will be borne by the Railway and the sharing agency respectively. Accordingly revised estimate excluding the cost of construction of road approaches amounting to ` 1366.75 crore was sanctioned by Railway Board in December 2007. The proper Rail cum Road Bridge was to be executed by the Railways while the road approaches were to be constructed by the concerned Road Authorities. The revised detailed estimate of the project was later again revised and the Railway Board sanctioned the 2nd revised estimate of the project including the cost of road approaches at a total cost of ` 2921.46 crore with Railways’ share as ` 1681.36 crore and NHAI share as ` 1240.09 crore. A total of ` 2071.80 crore was incurred on the project and the physical & financial progress of the work was 67.11 & 70.92 per cent respectively as on 31st March, 2014. The work was originally targeted to be completed by 31.12.2007 but the work is still incomplete in spite of lapse of approximately 7 years since the original target date of completion. Moreover, the target date of the completion of the project has now been fixed as 30.06.2015. 6. Koderma-Girdih New Line Project– (East Central Railways) The Project of Construction of New line from Koderma to Girdih was sanctioned in 1996-97 at an anticipated cost of ` 145 crore to provide a better Rail link to deprived area and to ease infrastructural constraints to boost trade. It was agreed by the MOR and Govt. of (GOJ) that the cost of the construction of this project will be bear in the ratio of 2:1 by the GOJ and MOR respectively. The part detailed estimate for the project was sanctioned at a cost of ` 51.82 Crore on 10.10.2000. Subsequently, the detailed estimate of the project was sanctioned at a cost of ` 371.86 crore. Later the funding pattern of this project was changed and it was decided that the cost over and above the original estimated cost will be borne equally by the both parties. Total anticipated cost of the project has reached to ` 768.87 crore out of which ` 442.20 crore would be from the deposits made by GOJ. A total of ` 540.94 crore was incurred on the project and the physical & financial progress of the project was 73 & 70 per cent for the project respectively as on 31st March, 2014. 7. Koderma-Ranchi New Line Project– (East Central Railways) The Project of New line from Koderma to Ranchi was sanctioned in 1998-99 to provide a better Rail link to deprived area and to ease infrastructural constraints to boost trade. Railway Board decided to build the Railway line in three phases- Koderma to Hazaribagh, Hazaribagh to Barkakana & Barkakana to Ranchi. Meanwhile the Memorandum of Understanding was signed in February 2002 between the Ministry of Railways (MOR) and Government of Jharkhand (GOJ) to share the cost of construction of this project. It was agreed that the cost of the

ReportNo.48of2015ƒ‰‡ͳͶͺ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

construction will be bear in the ratio of 2:1 by the GOJ and MOR respectively. The detailed estimate for the first phase i.e. Koderma to Hazaribagh and for the second phase i.e. Hazaribagh to Barkakana was sanctioned at a cost of `332.06 crore and `307.73 crore respectively on 08.02.2002. Railway Board sanctioned the detailed estimate for third phase i.e. Barkakana to Ranchi at a cost of `393.25 crore on 14.10.2003.The combined revised estimate of the project at a cost of `2957.21 crore was under approval as on 31st March, 2014. Later the funding pattern of this project was changed and it was decided that the cost over and above the original estimated cost will be borne equally by the both parties. A total of `1775.34 crore was incurred on the project and the physical & financial progress of the work as a whole was 64 & 60 per cent for the project respectively as on 31st March, 2014. 8. Koderma-Tilaiya New Line Project– (East Central Railways) The construction of New Line from Koderma to Tilaiya was conceptualized to provide a Rail link from Shivpur coalfields to super thermal Power plant of NTPC at Barh and to open a short route between the capitals of Bihar & Jharkhand. The consolidated detailed estimate of the project was sanctioned at a cost of ` 418.17 crore in November 2004. Meanwhile, the Memorandum of Understanding was signed between the Ministry of Railways (MOR) and Government of Jharkhand (GOJ) to share the cost of construction of this project but limited to portion falling in the state of Jharkhand since the project is spread in Bihar and Jharkahnd lines projects on 19th February 2002. Out of these six projects, three new line projects is being constructed by East Central Railway. It was agreed by the both parties that the cost of the construction of all these six projects will be bear in the ratio of 2:1 by the GOJ and MOR respectively. Later the funding pattern of the project was changed and it was decided that the cost over and above the original estimated cost will be borne equally by the both parties. A total of `219.54 crore was incurred on the project and the physical & financial progress of the project was 46 & 52 per cent for the project respectively as on 31st March 2014. 9. Bardhaman-Katwa [51.52 km] Gauge Conversion with New Material Modification for Katwa-Bazarsau [30.59 km]- Doubling, Katwa [Dainhat]-Manteswar [34.4 km], Negum-Mangalkot [8.60 km] and Manteswar-Memari[35.6km]-New Line project - (Eastern Railway) The Bardhaman-Katwa Gauge Conversion project was sanctioned in 2007-08 with the anticipated cost of ` 245.16 Crore and schedule period of opening in 2011-12 to improvement of passenger services and inclusion of goods traffic. Although being cost sharing project with State Government on 50:50 share basis no MOU has been executed so far. The project was taken up as cost sharing on the basis of a letter from the State Government. However, the liability of State Government subsequently have been handed over to NTPC who deposited an amount of ` 112.58 crores in March 2014 after the deposit of ` 10 Crores by State Government. The project with incurrence of an expenditure of ` 225.81 Crores (92per cent financial progress) upto March 2014 could achieve only 50per cent physical progress. The ROR of the project was assessed

ReportNo.48of2015ƒ‰‡ͳͶͻ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

at 10per cent by taking into account the element of cost sharing deposit of state government as well as by anticipating goods earnings with the setting up of a coal based thermal plant of NTPC near Katwa in March 2010.

In taking up the project the annual savings due to conversion from NG to BG was anticipated at ` 2.58 Crore and net goods earnings was assessed at ` 15.42 Crore per year from the opening year 2011-12. But with completion of 50per cent of the project after lapse of 3 years from schedule date of opening , the projected savings lagged behind ` 3.87 Cr. (50per cent of ` 2.58 x 3 years) and the projected net earning @ ` 14.00 Crore per year from 2011-12 could not be achieved which amounted to ` 46.26 Crore (` 15.42 x 3 years). Thus financial impact of delay in completion of the project was assessed as ` 50.13 crore during the period from 2011-12 to 2013-14. The project was categorized as High Priority during 2012-13 and again in 2013-14 but with incurrence of ` 33 Crore in 2012-13 no further physical progress beyond 50per cent (achieved in 2011) could be achieved, thereby defeating very purpose of categorization as High Priority. 10. Dumka-Rampurhat New Line Project – (Eastern Railway) This is the Phase-II project of Manderhill-Rampurhat via Dumka Project taken up for Socio-economic development of Santhal Parganas. The project was sanctioned in 2001 with the anticipated cost of ` 143.71 Crore. But with only 60per cent of physical progress the project cost has reached to ` 418.88 crores upto February 2014. This is a cost sharing project with Jharkand Government. Initially, in the MOU executed in February 2002 the share of Railways and the State Government was fixed on 1/3rd and 2/3rd ratio but when the MOU was renewed in February 2012 a modification in the share has been brought into. The additional expenditure over and above the initial project cost of ` 154 Crore (MOU) was decided to be shared on 50:50 basis. The latest anticipated cost of the project is ` 512.46 Crore and with the increase of share of 16.67per cent the liability of the Railways increased to ` 59.75 Crores. The substantial excess expenditure of ` 271.17 Crores upto February 2014 however included an amount of ` 118.77 crores on account of price escalation due to delay in completion of the project. The project cost has also increased due to addition in quantity amounting to ` 71.38 Crores. The Revised Estimate was not sent to Railway Board in time and it was sent in July 2012 but not yet sanctioned by Railway Board, who observed that a blatant violation of Engineering Code was done by the Zonal Railways by not sending the revised estimate in time. Government of , Ministry of Finance, Department of Expenditure O.M. dated 07.05.2003read with Planning Commission,’s D.O. No. O- 14015/2/98-PAMD dated August 19, 1998 prescribed to formulate an accountability mechanism in case of Time and Cost Overrun of the projects funded by Government. The O.M.s prescribed to devise an appropriate mechanism for fixing the responsibility for delay in submission of Revised Cost Estimate. No such mechanism was found to be set up in Eastern Railway.

ReportNo.48of2015ƒ‰‡ͳͷͲ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

11. Deoghar-Dumka project New Line Project – (Eastern Railway) The project was sanctioned in 1998-99 with anticipated cost of `180.73 crore. The completion date was not assessed in PET survey. In case of Deoghar-Dumka project it was noticed that expenditure amounting to `400 crore had already been incurred as against the agreed cost of `200 crore as appeared in MOU thereby enhancing the original cost by `200 crore. The ratio of the liability between Railways and State was similar to as discussed in case of Dumka-Rampurhat project i.e. initially 33.33per cent (Railways) and 66.66per cent (State) and finally 50:50. Therefore, Eastern Railway had to incur an amount of `100 crore out of the additional cost of `200 crore. The additional expenditure, however, was inclusive of price escalation of `77.26 crores for which extra liability of the Railway amounted to `38.63 crores (50per cent of `77.26 crores). The above additional financial liability was due to time and cost overrun. 12. Hansdiha- Godda New Line Project– (Eastern Railway) This is a cost sharing project with Jharkhand Government on 50:50 share basis sanctioned by Railway Board on 18.05.2011 at an anticipated cost of `267.09 Crore. The Project with ROR of (-) 38per cent was considered on socio-economic development basis. Till date the State Government deposited an amount of `20 Crore. The work has not been commenced with incurrence of expenditure only `87 Crore till March 2014. The cost of the land however, was assessed at `40 lakh per hectare in the Abstract Estimate (in May 2011) on approximation basis. But while preparing part detailed estimate (Feb 2014) the rate of land (`3.05 crore per hectre) was collected from Jharkhand Government in February 2013 leading to 7.62 times increase of the initial cost amounting to `55.90 Crore. This led to extra financial burden of Railway amounting `27.95 Crore (50per cent of `55.90 Crore, being Cost sharing project with 50:50 share).

13. Nangal Dam – Talwara BG rail link New Line – (Northern Railway) First phase of the project from Nangal Dam to Amb Andaura (43.914 km) was sanctioned in the year 1982-83 for socio-economic development and work started in 1982 on issue of urgency certificate after an assurance from the Govt. of to share the financial burden for the construction of the Railway line to the following extent ; i. Bearing cost of land ii. Bearing cost of labour component of earthwork and iii. Providing wooden sleepers at cost price.

ReportNo.48of2015ƒ‰‡ͳͷͳ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

Detailed estimate for phase-I of the project was sanctioned in 1985 at a cost of `37.68 crore (Nangal Dam – Amb Andaura). The construction from Nangaldam to Una-Himachal section was started in 1982 and completed in October 1989 at a total cost of `24.13 crore and formally opened to traffic in January 1991 i.e. after nine years of commencement of the work. The project remained frozen from the year 1991-92 to 1995-96 due to HP Govt.’s refusal to bear cost of land and it was de-frozen in September 1996 when HP Govt. agreed to give land to the Railway free of cost. The construction of 2nd block (Una Himachal to Charuru Takrala) was started in 1998 and completed in June 2004 at a cost of `66.97 crores and the section was formally opened for traffic in March 2005. Construction of 3rd block (Churaru Takrala to Amb Andaura) was completed in January 2011with a total expenditure of `136.17 crore and opened for traffic in July 2011. Detailed estimate for 4th and 5th block (Amb-Andaura to Daulatpur Chowk) and (Daulatpur Chowk to Kartoli ) respectively amounting to ` 220.13 crore has been sanctioned by Railway Board in December 2008. The work was held up due to shortage of funds. Later on Revised Estimate for `343.43 crore was submitted to Railway Board in April 2010 for sanction. After lapse of four years, Railway Board, in June 2014, returned the same stating that RE being four years old, revision of the estimate (RE) is necessary and directed to send modified Revised Estimate. No modified estimate (RE) was, however, sent by Northern Railway to Railway Board till date (March 2014). An expenditure of `178.24 crore has been incurred till March 2014. The DE of 6th block (TLR new BG rail link amounting to `354.14 crore) submitted by Zonal Railway in March 2009 was not sanctioned till March 2014 even after lapse of 5 years. Total expenditure on the project as of March 2014 was `383.89 crore with a physical progress of about 55 percent. The main reason for delay in completion of this project was HP Government’s backing out of its commitment. 14. Rewari-Rohtak - New line - (Northern Railway) With the pursuance of State Government and with assurance of sharing 50per cent of the cost, the work of new line Rewari-Rohtak (75 Km) was sanctioned by Railway Board in 2003-04 considering socio-economic development. The detailed estimate for `194.83 crore was sanctioned by Railway Board in May 2006. However, no provision of major having construction cost (`144.94 crore) almost equivalent to abstract estimate, was made and within a year of starting of work a material modification amounting to `145.04 crore for making provision of ROB/RUBs was sent to Railway Board for sanction. Railway Board sanctioned in March 2009 the proposal at a cost of `144.94 crore. Later on, revised estimate of `330.23 crore was sanctioned in March 2009 by Railway Board. Second revised estimate for ` 901.55 crore has been sanctioned by Railway Board in July 2013 which also includes a material modification for shifting of Rohtak - Panipat old line at a cost of ` 181 crore.

ReportNo.48of2015ƒ‰‡ͳͷʹ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

The project has been completed at a cost of ` 543.33 crore and was opened in January 2013 (except MM of shifting of ROK-Gohana existing line). The project was sanctioned with updation of data of 1997 ignoring the changes in ground realities which included necessity of 4 major bridges having cost equivalent to abstract estimates. There was a steep increase in the cost of land which increased from ` 19 crore to ` 156 crore by the time the project was commissioned. Railways should have insisted upon the State Government to bear the extra cost of land as the increase was within a year and after preparation of detailed estimate.Further Material modification for shifting of existing Rohtak - Gohana line is not prudent in view of the huge cost ( ` 181 crore) involved and having no financial benefit to Railway. From the above it is clear that a project started at cost of ` 194.83 crore has not been completed even at a cost of `901.55 crore. 15. Chandigarh-Baddi New Line project- (Northern Railway) This project having Rate of Return of (-) 6.6per cent was included in the pink book of 2007-08 at an anticipated cost of ` 328 crore considering socio-economic development. The detailed estimate for ` 699.06 crore was sent to Railway Board in November 2008 for sanction. The proposal for this project could not materialise due to land acquisition problems. A revised proposal for Baddi- Ghanauli is under examination. The Physical progress on the project as on 31 March 2014 is Nil after a lapse of a period of more than six years.

16. Deoband-Roorkee New Line project - (Northern Railway) Deoband-Roorkee (NL) project was sanctioned in the Pink Book of 2007-08 at a cost of `105.52 crore considering socio-economic development. The main beneficiary of this project was Government. Hence, State Government agreed (September 2006) to bear 50per cent cost of the project. The Detailed Estimate (DE) proposed was of ` 164.80 crore (June 2008), however, Railway Board sanctioned `160.01 crore (November 2008). NRCO submitted the revised estimate in November 2010 at a cost of `336.91 crore. The huge excess was due to increase in cost of land, ` 18.86 crore was sanctioned in DE now the cost of land was ` 153.01 crore. five contracts were awarded in the project and none of them, was completed due to non-availabilty of land. Only 4.82 kms out of the total 28.48 kms of project was available with NRCO. The work on project was stopped in the year 2010 and physical progress at that time was 30 per cent. State Government of Uttrakhand backed out of its commitment of sharing the 50per cent cost and the project of Deoband-Roorkee new line is lying as it is for the last 2 years though an expenditure of ` 159.86 crore has been incurred by both the parties. 17. Bhanupalli –Bilaspur- New Line project - (Northern Railway) This new line work appeared in Pink Book vide item no. 10-A of 2008-09 with a cost of ` 1047 crore considering socio-economic development. ROR of this project was (-) 11.48per cent. In response to Railway Board’s instruction of November 2008, part estimate of `350.32 crore,

ReportNo.48of2015ƒ‰‡ͳͷ͵  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

covering about 20 km length appeared in February 2009 and was sanctioned by the Board in February 2009 with the instructions that HP Government may be suitably advised to provide fund for land acquisition or else the project will not take off. Further Railway Board has advised not to take up the work beyond Dharat till the decision on funding is finalized. 18. Jind-Sonepat New Line project - (Northern Railway)

Jind-Sonepat new line work was sanctioned in supplementary demand of 2003-04 at cost amounting to `190.81 crore on socio-economic basis. Detailed estimate amounting to ` 236.08 crore was sanctioned by the Railway Board in June 2009. ROR of the project is negative i.e. (-) 15.64per cent. Revised Estimate amount to ` 740.80 crore duly vetted by associate finance was sent to Railway Board for sanction in February 2014 but the same is yet to be sanctioned. This work is being executed with 50:50 cost sharing with Government. Upto March 2014 expenditure amounting to ` 541.83 has been incurred. Haryana Government had deposited ` 310 crore towards its share of cost. Upto March 2014, physical progress of the project is 85per cent. 19. Rohtak-Meham-Hansi New Line project - (Northern Railway)

The Reconnaissance Engineering cum Traffic Survey for the project was carried out in October 2009 but at that time it was not considered by the Railway Board. On persistent demands from the people of the region survey was against carried out in the year 2012. As per survey report the cost of the construction was ` 406.87 crore with ROR of (-) 6.5per cent. On the assurance of Haryana Govt. that they will provide land free of cost besides 50per cent share of cost in the project, the Railway Administration had agreed to. Consequently, this project appeared in Pink Book of 2012-13 under item no. 14 at an anticipated cost of Rs 287 crore on socio-economic basis. The work has been started and simultaneously a detailed estimate for ` 754.88 crore was submitted to Railway Board in September 2013. Railway Board has been raising the various queries on the detailed estimate since then. As per latest information, the Railway has reduced the cost of detailed estimate from 754.88 crore to 576.18 crore and resubmitted the same in November 2014. The detailed estimate has not yet been sanctioned. However the expenditure of ` 8.5 crore has since been incurred. The financial progress is 1.2per cent and the physical progress is zero as on 31.3.2014. 20. Ratlam-Dungurpur via Banswara New Line project – (North Western Railway)

The project was sanctioned in 2011-12 on cost sharing basis in the ratio of 50:50 between MOR and GOR (excluding land) for which, the MoU entered into between the Ministry of Railway(MOR) and Government of (GOR) on 31.05.2011 

ReportNo.48of2015ƒ‰‡ͳͷͶ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

envisaged a completion period of five years from the date of MoU i.e. upto May 2016. However, the physical and financial progress was only 1per cent as on March 2014 i.e. after passing of nearly three years and as such, target date of completion of May 2016 is unlikely to be achieved. This would result in postponing the anticipated earnings of the project. As against the Abstract estimated cost of `2082.75 crore, the revised cost as per Detailed Estimate Part-II submitted by Railway Administration in December 2013 worked out to ` 2920.65 crore. This increased the shared cost of the Railways from ` 1025.90 crore to ` 1460.33 crore resulting in increased liability of ` 434.43 crore for the Railways. Final Location Survey (FLS) was started in Nov 2011. No flow chart for

RATLAM-DUNGARPUR VIA BANSWARA NEW LINE

scheduling of the project was prepared. RoR of the project was estimated at (+) 3.88 percent which does not qualify the stipulated 14 percent for sanctioning the project. The objective of the project was to serve as an impetus for the development of socially and economically backward areas covering the alignment. It was also observed that revision of RoR has not been done in view of the reduced period of completion of 5 years as given in the MoU in comparison to a period of 10 years adopted in the project report and considering State Govt. share of cost of the project. Land acquisition for the project being done by GOR was planned to be completed in an unrealistic period of one year i.e. by 2011-12 as per MoU. However, till March 2014, only 118.08 hectares (6.95per cent) of the 1699.93 hectares is acquired. Due to meagre allotment of funds mainly owing to delayed land acquisition, the final allotment had to be reduced drastically due to which contracts for works could not be awarded. Major deviations from the planned activity indicate that the project would suffer cost and time overrun which will also have to be shared by the Railways.

ReportNo.48of2015ƒ‰‡ͳͷͷ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

The construction of the permanent structures at a cost of `1.79 crore was not in accordance with the codal provisions. It was observed that the Measurement Book maintained for the work did not contain measurement of each building separately instead it captures SOR items operated for all such works in a contract in a single measurement book. Thus, transparency of execution of items for each sub-work is not maintained.

21. Thaiyat Hamira-Sanu, new line projects – (North Western Railway)

The objectives were to provide, shorter & quick transport infrastructure for the people of North Western part of Rajasthan & also to provide loading facilities of lime stone from Sanu. THM-Sanu project was sanctioned in year 2013-14. The project was to be taken up by North Western Railway on cost sharing basis (50:50) with the Rajasthan State Mines & Mineral Limited (RSMML). The cost of the project as per abstract estimate was ` 236.93 crore. As per provision of the Railway Board’s Circular No. 2008/PL/9/16 dated 20-07-2010 every project that shall qualify under the policy of the Railway initiative scheme, shall have undergone a Preliminary Engineering cum Traffic Survey (PETS) which should be not more than six months old. An MOU shall be signed between the Railway & the applicant laying down the broad terms of agreement. Only after which necessary sanction will be processed by Railways. This will be followed by the FLS which will be under taken by the Railways & the cost of FLS would be shared by the Railway & the party in the proportion of the agreed cost sharing. In contravention to above provisions of the Railway Board’s Circular dated 20-07-2010, the MOU has not been signed between the Railway & RSMML till date (Oct. 2014). Whereas FLS was completed in July 2014. The ROR was assessed by the Railway Administration at (+) 15.58 percent in January 2012. This was revised to (+) 21.71 percent in March 2012 on the basis of exclusion of the contribution by RSMML from the projected cash flow for the purpose of determining the ROR. The methodology adopted by the Railway Administration is not consistent with the R3i policy. Permanent way material worth `2.63 crore was issued by Sr. Section Engineer/C/P.way/HMH to Sr. Section Engineer/C/P.way/ during the period between November 2012 and January 2013. Out of the above material valuing ` 2.63 crore, P.way material worth ` 2.19 crore was utilized in yard remodeling work at Jodhpur & the remaining material is lying in the store of SSE/C/P.way/Jodhpur in February 2014. This amount of ` 2.63 crore was debited to the year Re-modeling work & debited it to this New Line project of THM-Sanu in which even the Detailed estimate has not been sanctioned so far (October 2014) and there was no allotment of funds (Final Grant) for the project during the year 2013-14. This amount of

ReportNo.48of2015ƒ‰‡ͳͷ͸  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

` 2.63 crore was debited against Deposit of RSMML worth `118.46 crore lying with Railway. Thus, the deposits with Railway of THM-Sanu New lines Project were utilized to complete the other works in which funds were not avoidable. The objectives/significance of the project were defined in the DPR. This was to provide rail connectivity to the backward/tribal areas of Rajasthan and MP in Banswara and Dungarpur districts besides facilitating the development of the area and transportation of inputs such as coal to the proposed thermal power plants and industries coming up in this area. The MoU entered into between the Ministry of Railway (MOR) and Government of Rajasthan(GOR) on 31.05.2011 envisaged a completion period of five years from the date of MoU i.e. upto May 2016. However, the physical and financial progress was only 1per cent as on March 2014 i.e. after passing of nearly three years and as such, target date of completion of May 2016 is unlikely to be achieved.

22. Bidar – Gulbarga New line project – (South Central Railway) The new line project between Bidar – Gulbarga was taken up on socio economic considerations. The project which was sanctioned in the year 1997-98 could commence only in the year 2003 i.e. after a gap of five years. As of March 2014, a total amount of ` 521 crore was spent on the project and the project still has an anticipated balance cost of more than ` 324 crore. The project could be completed only upto 65per cent even after 11 years of its commencement.

23. Cuddapah- Bangalore New line project - (South Central Railway)

The project was sanctioned in the year 2008-09 at an anticipated cost of ` 1000.23 Crore with an expected Rate of Return (ROR) at 18.78 per cent (revised to 10.68per cent)..The objective of the line is to develop the backward districts of Cuddapah and Kurnool apart from ensuring shortest route to Bangalore and was taken up on 50 per cent cost sharing with the Government of Andhra Pradesh. The work was taken up in three phases as detailed below: (a) Cuddapah to Pendlimarri (21 km) Engine rolling done for 18.5 kms and balance 2.5 kms held up due to dispute on land. (b) Pendlimarri- Rayachoti(79.2 km)- Part Detailed estimate to be approved by Railway Board (c) Rayachoti- Vayalpadu(53.93km)- Part Detailed estimate to be approved by Railway Board

ReportNo.48of2015ƒ‰‡ͳͷ͹  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

(d ) Madanapalle-Mulbagal(61.6 km)- Part Detailed estimate to be approved by Railway Board As against the revised estimate for ` 2050 Crore , ` 162.24 Crore was incurred till March, 2014 with a physical progress of only 7per cent and a balance throw forward cost of ` 1887.76 crore. The delay in completion of the project is due to tardy acquisition of land and provision of meager funds and non-finalization of detailed estimate. Though the project is to be completed by March, 2014, only seven per cent progress has been achieved till March, 2014. The following audit issues were noticed in the implementation of the project.Detailed estimate for phase one was only approved so far by Railway Board. Avoidable delay of eight months in arranging payments resulting in delay in land acquisition. The estimated cost and ROR were changed several times between September 1998 and December 2007 due to incorrect adoption of procedures while working out the ROR. 24. Dhallirajahara – Jagdalpur New Line project – (South East Central Railway) The New Line Project of Dhallirajahara – Jagdalpur (235 Km) was sanctioned long back in 1995-96 being non-target work in the beginning and later the revised target date of completion was 31-10-2016 but the physical progress of the work was very slow (18.06 per cent) as of March 2014. 25. Wadsa – Gadchiroli New Line project - (South East Central Railway) The physical progress of Project of Wadsa – Gadchiroli (49.5 Km) sanctioned in 2011-12 being the non-target work for which target date of completion was given as 31-12-2020 was zero per cent as of March 2014. 26. Ranchi (RNC) – Lohardaga (LAD) NG to BG conversion (South Eastern Railway) The project and extension to Tori (44.31 Km) was taken up on cost-sharing basis with the State Government of Jharkhand1 in 1997-98. The main objective of taking up the project was to provide a basic developmental infrastructure in the area in the backward region of Lohardaga and major expansion of Aluminium plant both at Muri as well as Renukoot apart from promoting trade, industries and mining as well, in line with the planning of Bihar Government. This railway line was expected to boost mining of bauxite ore, kaoline and limestone in the Lohardaga and Ranchi districts and related industries like INDALCO, HINDALCO and Bokaro as well as

 1 Pink Book item no. 14 of 1997-98

ReportNo.48of2015ƒ‰‡ͳͷͺ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

Steel Plants besides providing a shorter gateway to Northern India via Tori. The ROR for the project was worked out as (-) 1.24 per cent with Overhead Electrification (OHE) and 0.16 per cent without OHE. Though initially no target date was fixed for completion of the project, the same was fixed as five years from the date of executing the Memorandum of Understanding (MOU) with the State Government of Jharkhand on 19 Feb 2002. The MOU was further extended for six years i.e. up to February 2013, on 14 Feb 2012. Further extension of MOU has not been done till date (March 2014). The MOU dated 19 February 2002, laid down the estimated cost of the project as ` 216 crore of which 33 per cent cost was to be borne by Railways and 67 per cent by State Government. Later, after extension up to February 2013, with anticipated cost of ` 456 crore, over and above ` 216 crore, it was stipulated that Railways and State Government would contribute 50 per cent each. The total cost of the project increased to ` 699.01 crore after inclusion of electrification work as MM. The work of Gauge Conversion of Ranchi (RNC) – Lohardaga (LAD) has been completed and commissioned in March 2008. The work of LAD – Barkichanpi (14.5 kms) towards Tori has also been commissioned and passenger train started running on November 2011. Physical progress of the remaining portion of the project i.e. Barkichanpi – Tori (29.5 kms) was 71 per cent till December 2013 after lapse of almost 6 year from the scheduled time of completion and latest target set for completion is December 2015. The anticipated cost of the project has increased from ` 147 crore to ` 699 crore in the last 17 years. Further revision of the estimate was sent to Railway Board in 2013, which is still to be sanctioned due to its non-acceptance by the State Government till date. The initial cost to be shared by railways was ` 71.28 crore, which now stands at ` 312.79 crore. As such, the financial liability of the railways has increased by more than three times. There was no provision of OHE in the original estimate. With both ends Ranchi as well as Lohardaga having electrified sections, Ranchi- Lohardaga section would be an isolated diesel section, there would be operational problems and the route cannot be used as a seamless alternative route. The MOU is yet to be extended beyond Feb 2013. The revised estimate as well as the cost of electrification, which is included as material modification to the sanctioned estimate, is also not yet accepted by the State Government. 27. Attipattu-Puttur New Line project – (Southern Railway) This new line project was proposed to be on cost sharing basis with M/s. Ennore Port Limited (EPL) which agreed to share 50 per cent of the cost of the project. A preliminary engineering cum traffic survey for a

ReportNo.48of2015ƒ‰‡ͳͷͻ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

new line between Attipattu and Puttur was sanctioned in September 2002 and the survey report was submitted (March 2004) to RB and the same was updated (November2006).

The project was proposed to be on cost sharing basis with M/s. Ennore Port Limited (EPL) considering the increase in port activities and the proposed shifting of entire iron ore and coal traffic to the new port at Ennore. It was also expected to ease the line capacity constraints in the Arakkonam-Puttur section. As M/s.EPL had agreed to share 50 per cent of the cost of the project, the share of M/s.EPL was proposed to be reimbursed interest free through freight rebate at 10 per cent for 10 years or till the amount was recovered whichever was earlier. This project was included in the railway budget for 2008-09 and RB advised (April 2008) SR administration to initiate action for early finalization of Memorandum of Understanding (MoU) with M/s.EPL and to undertake final location survey, preparation of plans and estimate for the project. M/s.EPL expressed their inability (September 2009) to fund the project due tothe ban imposed by state government of based on the directions of Supreme Court of India on export of iron ore and movement of iron ore traffic from Bellary-Hosepet areas, the traffic from these areas to Ennore Port had dwindled changing the iron ore traffic scenario and

SR administration’s decision to extend freight discount only for outward traffic (from Port to Indian Railways section) The detailed estimate for the project for ` 527.37 crore was submitted (February 2011) to RB and the same was approved (September 2011) by RB after a delay of seven months. SR administration failed to persuade RB to explore the possibility of revising the policy on freight discount. Further instructions were not obtained from RB for pursuing the project. No action was taken by SR to finalize the MOU. Meanwhile, fund (`12 crore) was allotted in the budget for 2012-13 and M/s.EPL were requested (May 2012) to formally communicate their acceptance for equal sharing of the cost of the project and to deposit a sum of `12 crore towards their share for the year 2012-13. M/s. EPL reiterated their inability to participate in the project. RB made budget allotment of `75.66 crore during 2009-14 and expenditure of `2.96 crore (survey, permanent way materials, establishment and general charges) was incurred (March 2014) towards the project. The physical progress was one per cent. Though the detailed estimate was sanctioned, no further progress was made pending decision from RB. SR administration pursued the project inspite of M/s.EPL expressing their inability to fund the project. The project was taken up without assessing the changed scenario of iron ore traffic and signing of MoU with M/s.EPL. This resulted in blocking up of expenditure of `2.96 crore.

ReportNo.48of2015ƒ‰‡ͳ͸Ͳ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

28. Cuddalore-Salem Gauge Conversion with new line between Chinna Salem and Kallakuruchi – (Southern Railway) This project was sanctioned under unigauge policy and for development of Cuddalore port and industries. This project was taken up on the request of the State Government of . The project was sanctioned in 1999-2000 at an estimated cost of ` 300.01crore (including new line between Chinna Salem and Kallakurichi) on cost sharing by the State Government of Tamil Nadu to the extent of 50 per cent. The State Government deposited ` 112 crore during the period from 2003-04 to 2006-07. As the anticipated cost of the project increased to ` 372.09 crore, the State Government was advised to deposit an additional amount of `74.05 crore. The anticipated cost of the project was further increased to `556.64 crore. The State Government had since deposited `123.79 crore being its share on the project. An Expenditure of ` 408.05 crore was incurred (March2014) and the share of the State Government worked out to ` 204.03 crore. The Cuddalore-Salem via Vridachalam gauge conversion was completed and opened for traffic during the period from January 2003 to November 2007. Due to delay in sharing of cost by the State Government and change in alignment issues, work relating to new line Chinna Salem and Kallakuruchi did not commence (March 2014). South Western Railway SWR had ten ongoing projects on cost sharing terms with Government of Karnataka (GoK) and Andhra Pradesh. For five projects, out of nine executed on cost sharing terms with GoK, land was provided free besides sharing the cost. The cost sharing ratio is 50:50 for all the projects except one in which GoK had agreed to bear 2/3 of the cost. It was observed that no Memorandum of Understanding (MoU) was executed between State Governments and MoR for these projects. Review of these costs sharing projects revealed that: There was inordinate delay in handing over the land agreed to be provided free by Government of Karnataka which resulted in time and cost overrun.Due to huge cost overrun of cost sharing projects, attributable to delay in completion, Government of Karnataka, vide letter No.CM/246/GOI/14 dated 05/07/2014 had urged MoR to either fully bear the cost of the projects or reduce the share to be borne by Government of Karnataka to 1/3 instead of the agreed 50 per cent.

ReportNo.48of2015ƒ‰‡ͳ͸ͳ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

In the absence of a MoU with Government of Karnataka for timely execution of the project, financial interests of the Railways were not adequately safeguarded. The cost sharing authority’s interests were also affected as there was no schedule for execution/ completion of the projects resulting in increased financial liability and non-achieving of intended objectives. 29. Kadur – Chickamagalur - Sakleshpur DL project – (South Western Railway)

This work was included in Supplementary Budget Grant of 1996-97 at a cost of `157 crore. The Malnad region of Karnataka State a tourist spot was without rail connectivity. This line in addition to connecting the Malnad region would also provide an alternate shorter route linkage between MAQ port in the West coast and Kakinada, and Pradeep on the East Coast. Even though the project was not financially viable, the construction was justified as it is shorter BG Route connecting East and West ports. As per Board’s instruction the section was divided into two phases. Phase I : DRU – CMGR, Phase II: CMGR – SKLR

Revised Estimate for Phase I at a cost of `139.83 crore was approved by Railway board vide letter No. 93/W-1/Survey/SWR/2 dated 27/06/2012 and Phase II Detailed Estimate has been sanctioned at a cost of ` 644.73 crore vide letter No. 93/W1/Survey/SWR/3 dated 27/03/2010 bringing the total cost of the project to `889.52 crore. Railway Board has frozen the execution of Phase II of the project vide letter dated 19/09/2007. Principal Secretary of GOK vide letter dated 02/02/2013 had requested to defreeze the project and agreed to share 50 per cent of the cost of Phase II.

Revised Estimate of Kadur-Chikmagalur NL project provided for eight manned LCs at a cost of `0.74 crore. The work was completed. Based on the policy guidelines of Railway Board (January 2012), the Executing Authority had examined the feasibility of eliminating of the LCs and proposed to open the section duly retaining the LCs. However, GM gave instructions in April 2012 for taking up the work of construction of two RUBs under List of Approved Works (LAW) under the Plan Head 3000, construction of ROBs at four locations and diversions at the remaining two locations charging the expenditure to the project. Construction Organization had obtained Finance concurrence for including the RUBs under LAW during May 2012. However, all the bridge works were awarded by Construction chargeable to the project as under: Sl. Contract No. ROB/ RUB Awarded Value Executed Value (`` in crore) (`` in crore) 1 73600 dated 19/10/2012 2 RUBs 3.17 3.79 2 73628 dated 18/12/2012 2 ROBs 10.83 12.22 3 73622 dated 18/11/2012 2 ROBs 5.25 7.38 Total 19.25 23.39

ReportNo.48of2015ƒ‰‡ͳ͸ʹ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

Execution of these bridges was totally unjustified due to the following: (i) The original estimate did not even provide for LCs at these eight locations which indicated that the provision was not supported by the requisite Train Vehicle Unit (TVU) factor. (ii) The eight locations were neither on State Highways nor on National Highways justifying the requirement of these bridges. Thus erroneous and unjustified decision of provision of ROBs and RUBs had resulted in incurring an avoidable expenditure of `23.39 crore in addition to infructuous expenditure of ` 0.74 crore on construction of these LCs.  30. Rayadurga- Tumkur New Line project - (South Western Railway)

The project was sanctioned on socio-economic considerations. This will also serve in reduction of Rail distance between Bangalore–Rayadurga- Bellary stations by 137 km. This project was initially included in the pink book 2007-08 at an abstract cost of ` 887.315 crore. Detailed estimate cost sanctioned during 2009 was ` 970.34 crore. Latest anticipated cost of the project is estimated at `1743.09 crore. This is cost sharing project with GOK and GOAP in the ratio of 50:50. 31. Bangalore–Hassan via Sharavanabelagola New Line - (South Western Railway)

The Project was initially approved by Railway Board in 1996-97 for an abstract cost of ` 295.75 crore. The NL project was taken upon Socio- Economic consideration. The stretch of 44 km between HAS–SBC was completed and commissioned in 2006 in view of tourist potential for the Mahamastakabhisheka at SGBL. The entire project cost was to be borne by Railways. In 2011 after Railways had incurred an expenditure of ` 355.50 crore GOK agreed to share the balance cost of the project in the ratio of 50:50 from April 2010 onwards. Total cost of the project as per Revised Estimate vide letter No. 96/W-1/NL/S/27 dated 24/09/2013 is `1289.92 crore. Balance cost to be shared 50:50 between GOK & MOR.

Bangalore-Hassan via Shravanabelagola NL project was sanctioned in 1996-97 at an Abstract cost of `295.75 crore. Subsequently, Detailed Estimate at `412.91 crore and Revised Modified Estimate at `1289.92 crore were sanctioned. Initially, the cost of the entire project was to be borne by Railways. With effect from April 2010, GoK had agreed to share the cost in the ratio of 50:50. Hassan-Shravanabelagola section (41.17 km) had been completed at a cost of `140 crore (January 2006) and opened for passenger traffic on 07/02/2006. CRS accorded conditional authorization as under: Balance works, signaling and inter locking works being completed and commissioned as per sanctions under Joint safety certificate. Specified number of staff/ gangs, including gateman as per the approved yardstick should be in position within one month from the date of opening.

ReportNo.48of2015ƒ‰‡ͳ͸͵  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

Due to non-compliance of the above conditions, CRS withdrew sanction and the section remained closed for traffic since September 2006 till 2011-12. The review of records revealed the following: 9 Together with the Opening Documents, no geo technical report was submitted to CRS. This had also been brought out in the note regarding delay in commissioning submitted by CE to CAO. It was observed that no soil investigation was carried out before commencing earthwork which was a primary requirement. 9 However, during December 2005 itself, as problems of water oozing from formation and slips (from Chainage 122/00 to Chainage 162/000) due to unstable and deep cuttings were noticed, a reference was made to RDSO. Without attending to the problems, the section was offered for CRS inspection and authorization was given by CRS for opening of the section for passenger traffic. This was highly irregular as passenger safety was compromised as the problem was persisting in all the cuttings. Also it was not apparent as to how opening of the section was authorized by CRS. 9 RDSO had inspected the line during February and May 2006 and had suggested blanketing of 45 cum thickness in cutting, provision of pucca drains, line catch water drains, easing of the side slopes to 2.5:1 with berms of 4 meters in all the cuttings. Hence, to attend to earthwork, as advised by RDSO, two contracts were awarded during 2009-10 and completed in 2011-12 at a cost of `8.68 crore.

Thus the practice of commencing Earthwork without detailed geo-technical survey had resulted in idling of investment of `140 crore for five years (2006-11), extra expenditure and recurring expenditure on maintenance of the idling asset. 32. Munirabad–Raichur New Line project - (South Western Railway)

This NL project was originally sanctioned from Mehaboobnagar to Munirabad and was included in the PB of SCR, later as per Railway Board directions the section between Raichur and Munirabad was handed over to SWR on 25/01/2008. The project was taken on Socio-Economic considerations. Detailed Estimate for the line between Ginigera–Raichur was sanctioned vide Board’s letter No. 2008/W1/NL/SWR/MR/2 dated 30/11/2013 for `1350.91 crore. As on 31/03/2014, 15 per cent of the work was completed. This work also is a cost sharing work with GOK in the ratio of 50:50 with land provided free by GOK. 33. Bagalkot-Kudachi New BG Line project - (South Western Railway)

Originally this work was sanctioned vide PB item 7 of 2010-11 at an anticipated cost of `816.14 crore. This is also a cost sharing project with GOK in the ratio of 50:50 with land provided free of cost by GOK. This new line would link the agricultural and backward areas of Dharwad

ReportNo.48of2015ƒ‰‡ͳ͸Ͷ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

and district covering and Krishna river valleys. This line also connects two existing main lines Gadag-Hotgi & Londa– . Detailed Estimate of `986.30 crore sanctioned vide Railway Board letter dated 04/10/2013.  34. Whitefield-Kolar New Line project - (South Western Railway)

The BG NL work was initially included vide item No. 7a of 2011-12 PB at a cost of `341.05 crore. This line would serve as a direct link between WFD to KQZ with a length of about s saving a distance of 32 km (through the existing route via Bangarpet). This line would also help in improvement of Bangalore Rural and Kolar Districts of Karnataka apart from providing a shorter lead for passenger and goods traffic from Chittor and Cuddapah side. Detailed Estimate was sanctioned vide letter No. 2009/W1/SWR/WK dated 08/10/2012. This work is a cost sharing of 50:50 with GOK and land provided being provided free of cost.

SWR had ten ongoing projects on cost sharing terms with GoK and GoAP. For five projects, out of nine executed on cost sharing terms with GoK, land is provided free besides sharing the cost. The cost sharing ratio is 50:50 for all the projects except one in which GoK had agreed to bear 2/3 of the cost. It was observed that no Memorandum of Understanding (MoU) was executed between State Governments and Ministry of Railways for these projects. Review of these costs sharing projects revealed that:

1. There was inordinate delay in handing over the land agreed to be provided free by GoK which resulted in time and cost overrun.

2. Due to huge cost overrun of cost sharing projects, attributable to delay in completion, GoK, vide letter No.CM/246/GOI/14 dated 05/07/2014 had urged Ministry of Railways to either fully bear the cost of the projects or reduce the share to be borne by GoK to 1/3 instead of the agreed 50 per cent.

In the absence of a MoU with GoK for timely execution of the project, financial interests of the Railways were not adequately safeguarded. The cost sharing authority’s interests were also affected as there was no schedule for execution/ completion of the projects resulting in increased financial liability and non-achieving of intended objectives.

ReportNo.48of2015ƒ‰‡ͳ͸ͷ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

35. Tumkur-Davangere via Chitradurga New BG line project - (South Western Railway)

This project was sanctioned in the year 2011-12 with anticipated cost of `913 crore. This is a cost sharing project with GOK in the ratio of 50:50 with land being made available free of cost by GOK. This project is identified as part of Chennai-Bangalore Industrial corridor which needs to be completed to harness the full potential of the proposed corridor. The existing BG line connecting TK to DVG was via ASK, RRB, JRU with a distance of 255.18 km. The proposed line would serve the TK, CTA & DVG districts and would reduce the distance by 55.48 km between UBL and SBC. Detailed estimate was sanctioned by Railway Board vide letter No. 2009/W-I/NL/SWR/TD dated 29/10/2013 for `1801.01 crore. The increase in the cost of the project is mainly attributable to change in the scope of work (68.33 per cent) like increase in the height of formation in embankment to accommodate ROB/ RUBs in lieu of LCs and adoption of new track structure as per Railway Board Guidelines. 36. Shimoga –Harihara New BG Line project - (South Western Railway)

Originally included in 2001-12 at a cost of `562.74 crore. Detailed estimate at `832.47 crore has been sanctioned vide Railway Boards letter No.2010/W-1/NL/SWR/84 dated 29/11/2013. As on 31/03/2014, the work was yet to commence. This work is a cost sharing work with GOK in the ratio of 50:50 with land being made available by GOK free of cost.

37. Bangalore-Sathyamangalam New BG Line project - (South Western Railway)

Bangalore-Sathyamangalam New BG line was sanctioned by Railway Board in the year 1997-98 at an abstract cost of ` 225 crore. The Final Location Survey (FLS) was sanctioned by the GM, vide W.193/CN/BNC/SBC/STMLM/1 dated 16/08/1999, at a cost of `0.60 crore. Cabinet Committee on Economic Affairs (CCEA) had cleared the project on 04/12/1999 at a cost of `640 crore. The FLS could not be completed as permission for a stretch of 58 km, falling under the Tamil Nadu Forest department, was not granted. FLS was not permitted by the CEC in the forest area. Hence, Railway Board vide letter No.96/W.1/NL/SWR/34 dated 14/06/2011 directed to drop the work in reserve forest area and this will give direct Railway facilities providing link from Bangalore to Chamarajanagar via Kanakapura, T-Narasipura and also connects Melkote, Halaguru & Malavalli. GoK agreed to share 50 per cent of cost of the project in addition to providing land free of cost. Accordingly, the detailed estimate for `1382.78 crore for Hejjala-Chamrajanagar (152 km) was sanctioned (December 2013). This project was taken on Socio – Economic considerations. The work was yet to commence. An amount of `0.68 crore, towards preliminary survey expenses had been booked as at the end of March 2014.

ReportNo.48of2015ƒ‰‡ͳ͸͸  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

38. Ramanagara–Mysore Doubling –(South Western Railway)

SBC–MYS section (138.25 km) is single line from RMGM. Patch DL of SBC–KGI and KGI–RMGM is already sanctioned and work between SBC–KGI is completed and between KGI–RMGM is in progress. This section has 24 scheduled Express/ Passenger trains running in addition to freight trains. Line capacity utilization is 107.9 per cent with MTCE block. There is a public demand for two more trains during day time as MYS is a tourist place with huge passenger potential. To ease out the congestion, doubling between RMGM–MYS was sanctioned by Railway Board during 2007-08 at a cost of `343.20 crore. Revised Estimate at `874.54 crore sanctioned by Railway Board includes Electrification.

This project is cost sharing project with GOK in the ratio of 66:33 for the DL cost and 50:50 Electrification cost.

ReportNo.48of2015ƒ‰‡ͳ͸͹  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – XII (REF. TO PARA 1.6.10)

STATEMENT SHOWING TOTAL EXPENDITURE INCURRED IN RESPECT OF SPUR-I & II Sl. No. CA No. & date Spur No. Amount (in`)

1. Con/BB/125 dt.15.03.2007 I 57771211

2. Con/BB/DBRT dt.20.03.2008 I 47666833

3. Con/BB/113 dt. 29.01.2007 II 50878594

156316638

Statement showing details of expenditure incurred in respect of Spur-I Item No. Description of works Quantity Rate (in `) 200 per cent above Amount (in `) 13 Making, supplying, weaving, shaping, wire sausage, …etc. 1010.2 RM 2950 -- 2980090 15/9(II) Circular Sausage Crate (1606/a/iv) 3620.45 RM 377 -- 4094728 15/1(b) Providing, making & bundeling etc. up to 2m to 3m height in 1909.44 Sqm 122.5 367.50 701719 water (1602/b) 15/2 Supplying etc. Empty cement bags (1617/b) 13026 nos 5.35 16.05 209067 15/3 Construction of permeable screen (1618) 15 nos 1040 3120 46800 10 Supplying, filling loose boulder… etc 2397.516 cum 1500 -- 3596274 11 Supplying & spreading filter media ….complete 1289.122 cum 990 -- 1276230 15/1(a) Providing, making & bundeling etc up to 2m height in water 1073.3 Sqm 92.50 277.50 297840 (1602/a) 15/9(I) Circular sausage crate (1602/a/iii) 1250.7 RM 765.7 2297.10 2872982 9 Supplying & pitching of shingle boulder hand packed …etc 3355.99 cum 1860 -- 6242141 1 Earthwork in filling…shrinkage 78267.50 cum 129 -- 10096507

ReportNo.48of2015ƒ‰‡ͳ͸ͺ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

9(i) Circular sausage crate (1606/a/iii) 596.2 RM 765.7 2297.10 1369531 9(ii) Circular sausage crate by boulder (1606/a/iv) 5508.85 RM 377 1131 6230509 Total: 40014418 * Add Cost of Rly. Boulder 9729.75 cum@ Rs 1825/- (+)17756793 Grand Total: 57771211 Note: Rates of Railway Boulder has been taken from RITES Project Report, April/2006

Statement showing details of expenditure incurred in respect of Spur-II Item No. Description of works Quantity Rate (in `) 160 per cent above Amount (in `) 1 Earthwork in filling layers to form embankment…etc 137957.906 88 -- 12140295 cum 1602 Providing, making & bundelling etc. up to 2m height in water 4434.91 sqm 122.5 318.5 1412518 NFSR 1618 Construction of permeable screen as per drawing …etc 327.8 nos 1040.25 2704.65 886584 NFSR 11 Making, supplying, weaving, shaping, wire sausage …etc. 6940.399 RM 3000 -- 20821197 10 Supplying & spreading filter media of approved quality….etc. 657.277 cum 850 -- 558685 9 Supplying & pitching of shingle boulder hand packed …etc 9412.072 cum 1600 -- 15059315 Total= 50878594 Statement showing the expenditure incurred in connection with the protection work of Spur-I

Sl. No. Particulars Amount (in `)

1 Total cost of execution of the CA 13057489.81

2 * Cost of the boulder for 18964.024 cum @ `1825 per cum 34609343.80

Total 47666833.61

* Note: Rates of Railway Boulder has been taken from RITES Project Report, April/2006

ReportNo.48of2015ƒ‰‡ͳ͸ͻ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – XIII (REF. TO PARA 1.6.10) STATEMENT SHOWING LOSS FOR INJUDICIOUS CONSTRUCTION OF NORTH GUIDE BUND AND RIVER TRAINING PROTECTION WORKS Sl. Description of Work Quantity Rate per per cent below Rate, after consideration of Amount (in `) No. executed as per cum original rate 14 per cent below CC-III (in cum) (in `) (in `) 1 Earthwork in filling in layers to form 1418000 156 14 134.16 19023888 embankment/sub-bank etc. per cent 2 Earthwork in filling with contractor’s own 625000 148 14 127.28 79550000 earth … per cent 9(f) Carrying and filling loose boulders etc. 41000 467 14 401.62 16466420 per cent 9(g) Making, supplying, weaving, shaping, wire 7000 RM 1561 per 14 1342.46 9397220 sausage crates, etc. RM per cent Total 124437528 Add: Cost of boulder for 41000 cum @ ` 1529.24 per cum 62698840 Sub-Total 187136368 Less: Cost of railways earth reused from old location to new location for 200000 cum @ ` 134.16 (after consideration of 14per cent 26832000 below) as per CC bill no. XIX dt. 26.11.10 Total 160304368 * Add: Carrying cost of 200000 cum of Railway earth reused at new location through NFSR item by execution of item no. NFSR/201/e 4730000 & NFSR/202/e @ `15.35/- per cum & ` 8.30/- per cum respectively i.e. Total rate for per cum is ` 23.65/- Grand Total: 165034368 * Note:- Though it was proposed in the variation statement that 250000 cum of earth was to be reused under the NFSR as Railway earth at the shifted location yet 200000 cum was reused as per CC Bill no.XIX .

ReportNo.48of2015ƒ‰‡ͳ͹Ͳ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX - XIV (REF. TO PARA 1.6.10) CALCULATION SHOWING EXTRA EXPENDITURE DUE TO INCREASE IN THE BRIDGE LENGTH

A) CA value of sub-structure for 34 numbers of span = ` 343.90 crore

Therefore, Cost of 5 numbers of span = 5 x 343.90/34 = `50.55 crore

B) CA value of super-structure for 34 numbers of span = ` 987.19 crore

Therefore, Cost of 5 numbers of span = 5x 987.19/34 = ` 145.15 crore

C) Total financial implication for sub-structure and super-structure for additional 5 numbers of span = Rs (50.55 +145.15) crore = `195.70 crore APPENDIX – XV (REF. TO PARA 1.6.11) STATEMENT SHOWING CASES OF PREMATURE TERMINATION OF CONTRACTS AND IN FRUCTUOUS EXPENDITURE

Chota-Udepur-Dhar (WR) project has been stuck up due to non-acquisition of land passing through a tribal stretch. As such, there has been no physical progress in this work and four contracts were fore closed as work could not progress. This has resulted in `12.03 crore expenditure incurred on incomplete works. Tender No. Value of Contract Payment made upto 31/03/2014 ( ` in lakh) (` in lakh) DY.CE/BRC/CTD-DHAR/ 1 177.77 147.49 CANO.DYCE/BRC/CA/261 Date: 26/12/2008 DY.CE/BRC/CTD-DHAR/3 CA. NO.DYCE/BRC/CA/293 Date: 04/12/08 950.87 666.04 DY.CE/BRC/CTD-DHAR/4 CA. NO.DYCE/BRC/CA/294 897.89 371.51 Date: 04/12/2009 DY.CE/BRC/CTD-DHAR/9 CA. NO.DYCE/BRC/CA/317 93.66 17.56 Date: 18/03/2011 Total 1202.26

ReportNo.48of2015ƒ‰‡ͳ͹ͳ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – XVI (REF. TO PARA 1.6.12.2) DETAILS OF SANCTION OF LUMDING -SILCHAR GAUGE CONVERSION PROJECT (367.247KM.) Sl. Details of Sanctions Sanctioned Cost Reference to sanction No. (` in crore) 1. Lumding – Silchar (i) Lumding – Hatikhali (19.994 Km) 72.94 95/W1/LCT/NF/I/Pt.I dt.2.11.99 & 13.11.2000 (ii) Hatikhali – Langting (19.130 Km) 63.37 95/W1/LCT/NF/I/Pt.III dt.28.3.2000 & 20.11.2000. (iii) Langting – Ditokcherra (89.90 Km) 872.54 2001/W1/GC/NF/4 dt. 17.06.2002 (iv) Ditokcherra – Chandranathpur (20.020 Km) 152.09 2000/W1/LCT/NF/DTC-CNE dt.14.11.2000 (v) Chandranathpur – Badarpur (20.158 Km) 54.72 95/W1/LCT/NF/I/Pt.II dated 22.10.99 & 20.11.2000 (vi) Badarpur – Silchar (29.84 Km) 32.83 95/W1/LCT/NF/I/Pt.I dt.8.9.97 2. Silchar – Jiribam (50.385 Km) 49.41 95/W1/LCT/NF/I/Pt. dt.20.11.2000

3. Badarpur – Baraigram (42.74 Km) 56.19 2002/W-1/GC/NF/9 (MME) dt.25.9.03

4. Baraigram – Kumarghat (75.08 Km) 192.68 95/W-1/NF/GC/II (Pt) dt.20.7.2007 Civil Engg. - Total 1546.77 Other Engg. Estimates 129.99 Grand. Total 1676.76

ReportNo.48of2015ƒ‰‡ͳ͹ʹ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX- XVII (REF. TO PARA 1.6.12.2 A)

STATEMENT SHOWING THE ADDITIONAL PROTECTIVE WORKS TAKEN UP CONCURRENTLY DURING EXECUTION OF EARTHWORK CONTRACTS CAs executed through CE/CON/MLG CAs executed through Dy. CE/CON-IV/LMG

Sl. CA No Description of works CA value Sl.No CA No. and date Description of works CA value Amt. passed No. and date (in `) . (in `) ( ` in crore)

1 CON/S- Earth work in formation 1,81,13,750 1 CON/S-L/IV/ 26 Construction of modified side drain and 98,56,52 1.52 L/985 for making new bank dt.27.3.2008 other protection works in between km. SCA =Rs. 2 dt.7.8.20 and e/work in cutting to (M/s.D.N. 114/512 to km. 114/715 of proposed crore 06 make profile on Singh) BG alignment (M/s.Shi diverted alignment as vam) per BG standard, side 2 CON/S-L/IV/20 Construction of modified side drains 0.67 crore 0.60 drains, toe wall and dt. 28.2.2008 and other protection works in between other ancillary works Shri A.K.Thakur 114/715 km. to 114/ 925 km from km. 114/030 to km. 114/920 (new ch.) excluding km. 114/150- 510 (for Major Br. No.III/96 and III/97) 3 CON/S-L/IV/21 Earth work in cutting to make profile 36,54,000/- 0.40 dt. 14.3.2008 on diverted alignment as per BG [M/s.Shivam] standard and other ancillary works from km. 114/745 to km. 114/850 2 CON/S- Earth work in filling 1 CON/S-L/IV/14 Construction of 1 no. minor bridge, 0.94 L/1023 and in cutting for 4,03,38,245/ dt.10.1.2008 e/work in filling, modified side drains 95,47,310/- dt.20.9.2 making BG formation, - and other protection works in between 006 construction of 6 nos. [M/s.R.L.Constr 119/800 km. to 119/ 950 and in (M/s.R minor Br., side drains SCA-2 value uction] between 122/585 km. to 123/740 km &L and other protection = Construc works in between new `7,90,07,59 tion) ch. 119/800 km to 0.23 119/950 km and in 2 W/362/CON/L- e/work in km 119/800 to km 119/950 0.95 - between new ch. S/LMG/MB/16 and in between 122/585 to km 123/740 dt. 11.16.2007

ReportNo.48of2015ƒ‰‡ͳ͹͵  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

122/585 km. to 123/740 3 CON/S-L/IV/15 Construction of modified side drains - km. between Jatinga dt.10.1.2008 and other protection works in between 97,05,950/- Lumpur-new [M/s. 122/800 km. to 123/ 740 km between Harangajao – R.L.Construction New HJO- DTC Station Ditokcherra station as per BG standards on diverted alignment 3 CON/S- Earth work in formation 11,25,92,89 1 CON/S-L/IV/11 Construction of modified side drains 76,57,400/- 0.45 L/773 for making new bank 1.25 dt.28.12.2007 and other protection works in between dt.5.11.2 and e/work in cutting to SAC-1 vaue 111/025 km. to 111/ 300 km 003 make profile on = [M/s.C.C.Constr (M/s.C diverted alignment as `12,57,05,2 uction] .C per BG standard 64.5 Construc including construction tion) of 6 nos. of minor Br., side drains, toe wall and 2 CON/SL/IV / 32 Additional earthworks and protection 1..99 1.46 other ancillary works dt.16.3.2010 for the chain-age 111/300 to 112/650 from km. 111/020 to km. 112/680 (new ch) Between Jatinga Lumpur to New Harangajao station 4 CON/S- Earth work in formation 5,90,76,917/ 1 CON/SL/IV/ 31 Protection work at Br. No.111/126 to 0.62 0.61 L/554 for making new bank - dt. 9.2.2010 111/127 and provision of catch water dt.20.12. and e/work in cutting to drain from 122/600 to 124/400 2001 make profile on (M/s.A diverted alignment as .C per BG standard Nayak) including construction of 7 nos. of minor Br., side drains, toe wall and other ancillary works from km. 125/820 to km. 127/880 (new ch) Between New Harangajao to Ditokcherra station

ReportNo.48of2015ƒ‰‡ͳ͹Ͷ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

5 CON/S- Earth work in formation 4,35,21,826/ 1 CON/L-S/IV/24 Earth work in formation including 0.97 0.85 L/553 for making new bank - dt. 20.3.2008 extension of the minor br. (Br. No. dt.20.12. and e/work in cutting to III/102)from ch. 115/850 to ch. 2001 make profile on [M/s..Nayak 116/602 ,side drains and other (M/s.A diverted alignment as Infrastructure] protection works .C per BG standard 2 CON/S-L/IV/19 Construction of 2 nos. of minor bridge 1.32 1.32 Nayak) including construction dt.28.2.2008 (Br. No.III/105 and III/111) at ch. of 6 nos. of minor Br., [Shri 117/598 and 120/575 and e/work in side drains, toe wall and A.K.Thakur] filling, side drain and other protection other ancillary works works from km. 115/420 to km. 117/000 & km. 117/516 to km.119/420 (new ch) Between 3 CON/SL/IV/ 37 Modified side drain at km 118/790 to 1.48 0.99 Jatinga Lumpur to New dt.28.3.2011 118/860 Harangajao station 6 CON/S- Earth work in formation 1,52,37,864/ 1 CON/S-L/IV/36 Construction of modified side drains 0.86 0.51 L/566 for making new bank - Dt. 20-12-2010 and other protection works in between dt.11.02. and e/work in cutting to [M/s. A.C. 121/300 km. to 121/ 600 km 2002 make profile on SCA-2 Nayak] (M/s. diverted alignment as dt.3.1.2006= Nayak per BG standard 3,07,82,997. Engineer including construction 04 ing of 1 no. minor Br., side works) drains, toe wall and other ancillary works from km. 121/300 to km. 121/800 (new ch) 7 CON/S- Earth work in formation 3,62,08,108. 1 CON/S-L/IV/22 Construction of modified side drains 87,47,920/- 0.87 L/558 for making new bank 50/- dt.20.3.2008 and other protection works in between dt.3.01.2 and e/work in cutting to SCA-2 [M/s. Nayak 123/960 km. to 124/ 150 km 002 make profile on dt.30.12.200 Infrastructure] (M/s. diverted alignment as 5 = Nayak per BG standard 4,50,19,019.

ReportNo.48of2015ƒ‰‡ͳ͹ͷ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

Engineer including construction 30 2 CON/SL/IV/ 35 Construction of modified side drains 0.48 ing of 3 nos. minor Br., dt.20.12.2010 and other protection works in between 36,88,500/- works) side drains, toe wall and [M/s.. Nayak 124/620 km. to 124/ 700 km other ancillary works Infrastructure] from km. 123/940 to km. 125/760 (new ch)

4 CON/S-L/IV/23 Construction of modified side drains 0.71 dt.20.3.2008 and other protection works in between 82,10,600/- [M/s.. Nayak] 124/150 km. to 124/ 325km Infrastructure 8 CON/S- Earth work in formation 42775505 1 CON/S-L/IV/25 Construction of modified side drains 9451425/- 0.25 L/752 for making new bank dt.20.3.2008 and other protection works in between dt.1.08.2 and e/work in cutting to [M/s. A.C. 120/270 km. to 121/ 300 km 003 make profile on Nayak] (M/s. diverted alignment as Hari per BG standard Construc including construction 2 CON/S-L/IV/13 Construction of 1 no. of minor bridge 7874750/- 0.98 tion) of 4 nos. minor Br., dt.10.1.2008 (Br. No.III/110) at ch. 120/193 and side drains, toe wall and [M/s. e/work in filling, side drain and other other ancillary works R.L.Construction protection works from km. 120/040 to ] km. 121/300 (new ch) 3 CON/S-L/IV/27 Additional e/work for flattering of 19772200/- 1.82 dt.19.7.2008 slope to make BG profile extension of [M/s. 1 no. minor Bridge and other protection R.L.Construction work etc. from km. 120/100 to km. ] 121/300 .. 19.22

ReportNo.48of2015ƒ‰‡ͳ͹͸  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX-XVIII (REF. TO PARA 1.6.12.2) LOSS OF ` 5.90 CRORE (` 21.71 LAKHS FROM A AND ` 5.69 CRORE FROM B BELOW) ON ACCOUNT OF DISMANTLING OF DEFORMED TUNNEL OF 28 M OF TUNNEL NO. 8 AND SUBSEQUENT RECONSTRUCTION

A.Operation of NS item in the CA schedule for dismantling of deformed 28 m Tunnel in Tunnel No. 8 (Statement-I)

Item No. Description of item Quantity Rate(in`) Totalamount(in`) NS-01 Breaking and removing of concrete lining 210 cum 7853 per cum 1649130 NS-02 Cutting, dismantling and removing of permanent steel supports 40 MT 13053 per MT 522120  Total ` 2 1.71 lakh B. Reconstruction of deformed 28 m Tunnel in tunnel No. 8 (STATEMENT-I) Schedule Description of item Quantity Rate Total amount of Item (in`) (in`) No. 6 Concrete lining including backfill concrete 5500 cum 5760 per cum 31680000 5(a) Supply of permanent steel supports 530 MT 38700 per MT 20511000 5 (b) Manufacturing ,leading and erecting permanent steel supports 530 MT 9000 per MT 4770000 Total ` 5.69 crore

ReportNo.48of2015ƒ‰‡ͳ͹͹  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

APPENDIX – XIX (REF. TO PARA 1.6.12.2) LOSE DUE TO FAILURE OF TUNNEL NO. 12 (STATEMENT –II)

After construction of 28m tunnel in Face-2 side , the entire portion of tunnel was collapsed due to excessive pressure of earth resulting in deformation of tunnel on account of squeezing, distortion and twisting of supports and during which an amount of`13.10 crore was already paid to the agency. The contract was, thereafter, terminated at the Risk and Cost of the agency. Thus, the entire expenditure paid to contractor was an in fructuous expenditure and had been taken into account as loss to the railway.

The new agency took two years to complete the rectification works of collapsed tunnel by dismantling the old concrete steel supports and reconstruct of the same which included an expenditure of`0.12 crore towards dismantlement of damaged structures as detailed below:

Item No. Description of item Quantity Rate (in `) Total amount (in `) NS-01 Breaking and removing of concrete lining 110 cum 7800 per cum 858000 NS-02 Cutting, dismantling and removing of permanent steel supports 27MT 13050 per MT 352350  Total 12.10 lakh 











ReportNo.48of2015ƒ‰‡ͳ͹ͺ  Status of Ongoing Projects in Indian Railways – New Line, Doubling and Gauge Conversion

`

APPENDIX – XX (REF. TO PARA 1.6.12.2)

STATEMENT SHOWING THE EXTRA EXPENDITURE DUE TO COLLAPSE OF WELL FOUNDATION

1. Expenditure incurred as per original CA No. CON/S-L/620 dated 31.5.02 for substructure of `11.17 crore Bridge No.572 2. The contract value of the subsequent contract for `19.03 crore construction of sub structure of bridge was

3. Expenditure incurred for construction of Bridge against the contract at Sl. No. 2 `16.99 crore.

4. Total expenditure (Sl. No. 1 and 3 ) `28.16 crore

5. Original Contract value `13.56 crore

6. Additional Expenditure (Sl.No. 4 - Sl.No. 5) `14.60 crore



ReportNo.48of2015ƒ‰‡ͳ͹ͻ  Management of Works Contract in Indian Railways



APPENDIX I (PARA REFERENCE 2.1) BASIS OF SAMPLE SELECTION Sl. Area Monetary Limits Criteria for selection Period No. Covered 1 Contracts finalised Upto `1 crore 6 contracts on two divisions for 2011-12 to during the year each year 2013-14 `1 crore to `5 crore 8 contracts on two divisions and 2 contracts on construction for each year Above `5 crore for 2 contracts on two divisions and 4 division and `5 crore to contracts on construction for each `10 crore year

Above `10 crore 4 contracts on construction for each year 2 Contracts in 15 percent each for Open Line and Construction As on progress 31-3-2014

3 Completed 25 percent each for Open Line and Construction 2013-14 contracts 4 Discharged tenders 100 percent for tenders valuing above ` 1 crore 2011-12 to 2013-14 5 Tenders valuing 2011-12 to above `8 crore/ 100 per cent 2013-14 `10 crore

6 Contracts short- 100 per cent for tenders valuing above `1 crore 2011-12 to closed/foreclosed 2013-14

7 Contracts 100 per cent for tenders valuing above `1 crore 2011-12 to terminated 2013-14 8 Arbitration awards 10 cases in Construction and in Open Line separately 2011-12 to settled 2013-14

Report No. 48 of 2015 ƒ‰‡ͳͺͲ  Management of Works Contract in Indian Railways



APPENDIX II (PARA REFERENCE 2.1) SAMPLE CHECKED IN AUDIT Sl. No. Description Sample checked 1. Tenders executed 1215

2. Contracts in Progress as on 31.03.14 927

3. Contracts completed during 2013-14 313

4. Discharged tenders 647 5. Tenders valuing above `8 crore/ `10 crore 321

6. Contracts short-closed/fore-closed 173

7. Contracts terminated on account of Contractor failure 265

8. Arbitration awards settled 214

Report No. 48 of 2015 ƒ‰‡ͳͺͳ  Modernisation of Signalling and Telecommunications System by Indian Railway Project Management Unit 

APPENDIX I (PARA REFERENCE- 4.1)

STATEMENT SHOWING THE WORKS TAKEN UP FOR MODERNIZATION OF SIGNALING AND TELECOMMUNICATION WHICH WERE FUNDED BY FOREIGN LOAN

I. Replacement of signaling gears by solid state ( 5 stations) on - II. Replacement of Signal equipment by electronic interlocking (7 stations) on Ghaziabad-Tundla section III. Replacement of signaling gears by route relay interlocking at Tundla IV. Automatic block signaling on Aligarh – Ghaziabad section V. Modernization of signals on Ghaziabad-Kanpur route VI. Replacement of Cable by optic fibre cable Delhi – Ghaziabad-Panki section VII. Replacement of gears by electronic interlocking (19 stations) on Ghaziabad-Kanpur section VIII. Replacement of signaling gears by electronic interlocking (15 stations) in Ghaziabad-Kanpur section IX. Track circuiting with automatic block signaling in golden quadrilateral/Rajdhani and Shatabdi route- Aligarh-Kanpur route X. Indoor equipment, recording systems & control equipment in connection with control centre at Aligarh. XI. Indoor equipment recording system & control equipment in connection with control equipment in connection with control centre at ETW

Report No. 48 of 2015 ƒ‰‡ͳͺʹ  Modernisation of Signalling and Telecommunications System by Indian Railway Project Management Unit  APPENDIX II (PARA REFERENCE - 4.2)

DESIGNATIONS OF OFFICERS ASSOCIATED WITH THE FUNCTIONING OF DEDICATED INDIAN RAILWAY PROJECT MANAGEMENT UNIT (IRPMU)

MoR is responsible for functional planning, tendering, contracting and overall supervision of the execution of the S&T contracts on turn-key basis. The matters related to IRPMU are dealt at MoR by S&T Directorate headed by Member (Electrical). He is assisted by Advisors (Signal) and Executive Directors (Signal Project). Member Electrical works as the project co- ordinator and is responsible for taking major policy decisions, authorisation of major project revisions, monitoring the overall project progress, approval for tender evaluation, decision on procurement, co-ordination with other projects in IR.

General Manager (NCR) is responsible to support the Member Electrical on project related issues, approval of project expenses in co-ordination with the consultant up to an amount fixed by IR, revision and approval of the project schedule, the disbursement of money, all procurement, documentation for the project works and quarterly progress reports to Member Electrical and KfW.

The head of IRPMU is Chief Administrative Officer (CAO) The CAO/IRPMU is assisted by several officers while performing various duties assigned to IRPMU. These officers are Chief Signal &Telecommunication Engineer (CSTE), CSTE/Planning, Chief Project Manager (CPM), CPM/ Train Protection and Warning System (TPWS), Chief Personnel Officer (CPO), Chief Traffic Manager (CTM) and Financial Advisor & Chief Accounts Officer (FA&CAO) besides Engineers of various levels posted at Aligarh, Allahabad and Kanpur.

Report No. 48 of 2015 ƒ‰‡ͳͺ͵  Modernisation of Signalling and Telecommunications System by Indian Railway Project Management Unit  APPENDIX III (PARA REFERENCE - 4.4.1)

THE REASONS FOR CONSIDERING THE OFFER OF M/S. ASC AS "UNSUITABLE"

The Financial bids of only the technically acceptable offers were to be opened for further evaluation. and ranking. The consultant was to evaluate the offers of tenderers considering maximum weightage of 70 points for technical bid and 30 points for financial bid. The Consultant found that offers of only two bidders (M/s Alcatel Consortium –L1 and M/s Siemens-L2) were technically suitable. Out of these, the L 2 tenderer turned out to be the preferred bidder due to highest scoring. The Consultant found technically unsuitable the offers of remaining two tenderers [M/s IGE Consortium (M/s IGEC) and M/s Ansaldo consortium (M/s ASC)] and recommended their exclusion in further evaluation process. However, Consultant was instructed by the Tender Committee to consider the financial offer of M/s ASC also. Since the objective of first packet was to scrutinize the capability of the bidder, the opening of the second packet of unsuitable bidder was against the principle of pre- qualification criteria. The Consultant did not accept the financial bid of M/s ASC also on the plea that the bidder did not provide the relevant schedules, left out supplies and services outlined in the technical offer besides non-supply of the “grand total” of all the schedules. Tender Committee (TC) observed that although the Consultant had taken the bid price of M/s ASC as basis for awarding scores to other bidders in their financial bids, they had not considered the financial bid of M/s ASC.

Report No. 48 of 2015 ƒ‰‡ͳͺͶ  Modernisation of Signalling and Telecommunications System by Indian Railway Project Management Unit  APPENDIX IV (PARA REFERENCE - 4.4.1) DEFICIENCIES IN FINALISATION OF GLOBAL TENDER AND AWARD OF CONTRACT TO M/S ASC FOR EXECUTION OF KFW FUNDED WORKS

Name of the Scores on Scores on Scores on Total Scores Contractor Credential bid Credential Financial (Col. 3 & 4) (Out of 100) bid bid (Out of 70) (Out of 30) 1 2 3 4 5 M/s Siemens 81.45 57.01 21.38 78.39 AG M/s Alcatel 75.00 52.50 18.26 70.76 SEL AG M/s ASC 67.50 47.25 Nil (being Nil (technically technically unsuitable) unsuitable) The TC made M/s ASC offer comparable through adjustment in the financial offer by increasing the offered amount by Euro 24,337,604. The score awarded by TC were as under: Name of the Scores on Scores on Scores on Total Scores firm Credential bid Credential Financial (Col. 3 & 4) (Out of 100) bid bid (Out of 70) (Out of 30) 1 2 3 4 5 M/s Siemens 84.57 59.41 16.26 75.67 AG M/s Alcatel 83.56 58.49 12.98 71.47 SEL AG M/s Ansaldo 83.53 58.47 30.00 88.47 Signal Consortium Railway Board recommended that the contract may be awarded to M/s ASC after taking an undertaking that In the event of Microlok II system was not found as per CENELEC Safety Integrity Level 4 (SIL4) requirements for heavy mixed traffic, the contractor was to supply another approved SSI system acceptable to IR at no extra cost. As a result, Letter of Acceptance (LOA) to the contractor was issued with proviso. The contract agreement was to be signed only after successful review of assessment of Microlok II interlocking system as per CENELEC standards by TUV inter traffic. Further, although KfW had informed IR (September 2005) that Microlok II interlocking system would not be a real reference for comparing the routes on IR with routes on Bangladesh/ Malaysia. Even, IR decided to undertake as a first step to assess the Microlok II interlocking system as per CENELAC, European Committee for Electro-technical Standardization. They entered into the contract (February 2006) while the final assessment report was received in August 2006. This was in contradiction of proviso in the LOA and against the spirit of decision taken by Railway at a later stage to undertake as a first step the assessment of specific interlocking work.

Report No. 48 of 2015 ƒ‰‡ͳͺͷ  Modernisation of Signalling and Telecommunications System by Indian Railway Project Management Unit 

APPENDIX V (PARA REFERENCE 4.4.2.2)

REASONS FOR DELAY IN EXECUTION OF S&T WORKS AND THE NECESSITY FOR EXTENSION IN COMPLETION PERIOD

Railway Board had decided in November 2006 to use dual detection i.e. using AFTC and Axle counters working in parallel at 12 stations and associated block sections and only DC track circuits at stations. This had negative impact on SIP, Selection Table, interface circuits, application logic preparation etc, and necessitated the preparation of cable core allocation charts and field designs. The power supply was required at LSC and stations besides procurement of material and assessment of hazards of such system. By that time, three sections had been commissioned without using dual detection. Railway experienced a lot of problem on account of failures of AFTC, mainly due to theft and vandalism, resulting in failures of Auto signals and detention of trains. As a result, dual detection was considered a necessity of the route (January 2007). However, decision in this regard could be communicated by MoR in April 2009 only. As such, the design and field work for providing dual detection at all stations and block sections was started after this decision. Besides dual detection, there had been changes in the facility at almost all stations like additional shunt signals and provision of Stand Humps/dead ends etc. At stations where auto signalling work had not been taken by that time, yard remodelling had already been planned (HRS, TDL, ETW and FZD stations) impacting on the completion time of the contract. Further, Railways had been considering the execution of work of 3rd line in Aligarh Jn-Ghaziabad section and KfW project works in integrated manner and a decision on that was awaited. The decision to provide and install 13 Child Exchanges at various locations was communicated to contractor in February 2008. The contractor requested to take a decision for remaining Exchanges also. The desired decision was communicated in June 2009 only.

Report No. 48 of 2015 ƒ‰‡ͳͺ͸