COI Utilization Report May 04, 2011
Total Page:16
File Type:pdf, Size:1020Kb
Load more
Recommended publications
-
Pacific DC Intertie (PDCI) Upgrade Outage / De-Rate Schedule 2014
Version No. Pacific DC Intertie (PDCI) Upgrade 10 POWER SYSTEM Effective Outage / De-rate Schedule 2014-2016 1/12/2016 Date: Introduction The upcoming scheduled outages due to major upgrades on the Pacific DC Intertie (PDCI) will result in reduced available capacity on the line during various periods from 2014 to 2016. Most of the upgrades are convertor station and line work by the Bonneville Power Administration (BPA) to modernize its infrastructure at the Celilo Converter Station, which is the northern terminal of the PDCI. Other work will be performed by the Los Angeles Department of Water and Power (LADWP) in conjunction with the upgrades. Scheduling MW Capacity The schedule below will be updated as outages are scheduled. Start Date End Date Direction Scheduling Capacity (MW) June 28, 2015 October 3, 2015 North – South 1956 HE21 HE3 South – North 975 October 3, 2015 January 20, 2016 North – South 0 HE4 HE24 South – North 0 January 21, 2015 North – South 29901 HE1 South – North 975 From October 3, 2015 to January 21, 2015, the Celilo‐Sylmar Pole 3 1000kV Line and Celilo‐Sylmar Pole 4 1000kV Line will be removed from service and the PDCI will not be available [0MW (N‐S) and 0MW (S‐ N)]. Version Version Revised By Date 1 Document Creation OASIS Group 09/22/2014 2 Corrected outage information OASIS Group 10/14/2014 3 Corrected outage information OASIS Group 10/15/2014 4 Updated outage information OASIS Group 10/16/2014 5 Updated outage information OASIS Group 11/03/2014 6 Updated outage information OASIS Group 12/23/2014 7 Updated outage information OASIS Group 01/09/2015 8 Updated outage information OASIS Group 08/26/2015 Updated PDCI capacity after 12/21/2015 from 3220MW to 9 OASIS Group 09/17/2015 2990MW. -
The History of High Voltage Direct Current Transmission*
47 The history of high voltage direct current transmission* O Peake† Power Systems Electrical Engineer, Collingwood, Victoria SUMMARY: Transmission of electricity by high voltage direct current (HVDC) has provided the electric power industry with a powerful tool to move large quantities of electricity over great distances and also to expand the capacity to transmit electricity by undersea cables. The fi rst commercial HVDC scheme connected the island of Gotland to the Swedish mainland in 1954. During the subsequent 55 years, great advances in HVDC technology and the economic opportunities for HVDC have been achieved. Because of the rapid development of HVDC technology many of the early schemes have already been upgraded, modernised or decommissioned. Very little equipment from the early schemes has survived to illustrate the engineering heritage of HVDC. Conservation of the equipment remaining from the early projects is now an urgent priority, while the conservation of more recent projects, when they are retired, is a future challenge. 1 INTRODUCTION technology for the valves to convert AC to DC and vice versa. At the beginning of the electricity supply industry there was a great battle between the proponents In the late 1920s, the mercury arc rectifi er emerged of alternating current (AC) and direct current as a potential converter technology, however, it was (DC) alternatives for electricity distribution. This not until 1954 that the mercury arc valve technology eventually played out as a win for AC, which has had matured enough for it to be used in a commercial maintained its dominance for almost all domestic, project. This pioneering development led to a industrial and commercial supplies of electricity number of successful projects. -
Advanced Transmission Technologies
Advanced Transmission Technologies December 2020 United States Department of Energy Washington, DC 20585 Executive Summary The high-voltage transmission electric grid is a complex, interconnected, and interdependent system that is responsible for providing safe, reliable, and cost-effective electricity to customers. In the United States, the transmission system is comprised of three distinct power grids, or “interconnections”: the Eastern Interconnection, the Western Interconnection, and a smaller grid containing most of Texas. The three systems have weak ties between them to act as power transfers, but they largely rely on independent systems to remain stable and reliable. Along with aged assets, primarily from the 1960s and 1970s, the electric power system is evolving, from consisting of predominantly reliable, dependable, and variable-output generation sources (e.g., coal, natural gas, and hydroelectric) to increasing percentages of climate- and weather- dependent intermittent power generation sources (e.g., wind and solar). All of these generation sources rely heavily on high-voltage transmission lines, substations, and the distribution grid to bring electric power to the customers. The original vertically-integrated system design was simple, following the path of generation to transmission to distribution to customer. The centralized control paradigm in which generation is dispatched to serve variable customer demands is being challenged with greater deployment of distributed energy resources (at both the transmission and distribution level), which may not follow the traditional path mentioned above. This means an electricity customer today could be a generation source tomorrow if wind or solar assets were on their privately-owned property. The fact that customers can now be power sources means that they do not have to wholly rely on their utility to serve their needs and they could sell power back to the utility. -
Import/Export Paths: Summary of Transmission Issues and Implications
DOCKETED Docket Number: 15-RETI-02 Project Title: Renewable Energy Transmission Initiative 2.0 TN #: 214834 Document Title: Appendix A. Transmission Assessment Focus Area Information Description: N/A Filer: Misa Milliron Organization: California Energy Commission Submitter Role: Commission Staff Submission Date: 12/16/2016 10:49:38 AM Docketed Date: 12/16/2016 Public Review Draft 12/16/2016 Appendix A. Transmission Assessment Focus Area Information Renewable Energy Transmission Initiative 2.0 PUBLIC REVIEW DRAFT December 16, 2016 Public Review Draft 12/16/2016 Contents of Appendix A Introduction .......................................................................................................................... 1 In-State TAFAs: Transmission and Environmental/Land-Use Implications ............................... 3 In-State TAFA Data Maps........................................................................................................................ 3 Imperial Valley TAFA ............................................................................................................................... 9 Riverside East TAFA .............................................................................................................................. 16 Victorville/Barstow TAFA ...................................................................................................................... 20 Tehachapi TAFA ................................................................................................................................... -
2002 ABB ELECTRIC UTILITY CONFERENCE HVDC Technologies
2002 ABB ELECTRIC UTILITY CONFERENCE PAPER IV – 3 POWER SYSTEMS HVDC Technologies – The Right Fit for the Application Michael P. Bahrman ABB Inc. 1021 Main Campus Dr. Raleigh, NC 27606 Abstract: Traditional HVDC transmission has often provided economic solutions for special transmission applications. These include long-distance, bulk-power transmission, long submarine cable crossings and asynchronous interconnections. Deregulated generation markets, open access to transmission, formation of RTO’s, regional differences in generation costs and increased difficulty in siting new transmission lines, however, have led to a renewed interest in HVDC transmission often in non-traditional applications. HVDC transmission technologies available today offer the planner increased flexibility in meeting transmission challenges. This paper describes the latest developments in conventional HVDC technology as well as in alternative HVDC transmission technologies offering supplemental system benefits. Keywords: HVDC, DC, CCC, VSC, PWM, RTO, Asynchronous, HVDC Light I. INTRODUCTION Economic signals arising from deregulation of the generation market have led developers and transmission providers alike to follow the path of least resistance much like the power flow over the network on which their mutual business interests rely. On the generation side, the developer has invoked a quick-strike strategy siting units where there is convergence of low-cost fuel supplies, relative ease of permitting, water supply, ready access to transmission and proximity to load. On the transmission side, the transmission provider has been preoccupied with cost reduction, compensation for stranded assets, potential under-utilization of assets and reacting to evolving regulatory mandates. Although such development may result in a short-term gain in new, economic power resources, the long term benefit is not all that clear. -
Renewable Energy Transmission Initiative V2.0
Renewable Energy Transmission Initiative v2.0 Brian Turner RETI 2.0 Project Director California Natural Resources Agency Western Regional Partnership June 9, 2016 California Public California Energy Utilities Commission Commission 1 Agenda 1. RETI 2.0 Background 2. Planning Goals summary 3. Resource Values summary 4. Focus Areas summary 5. Current Activities California Public California Energy Utilities Commission Commission 2 RETI 2.0 Background California Public California Energy Utilities Commission Commission 3 Renewable Energy Transmission Initiative v2.0 • Cooperative project of four state and one federal agency • Statewide, non-regulatory planning effort to help meet statewide GHG and renewable energy goals. • Explore combinations of renewable generation resources in California and throughout the West that can best meet goals • Build understanding of transmission implications of renewable scenarios, and identify common transmission elements • Identify land use and environmental opportunities and constraints to accessing these resources • Accelerated, agency-driven, high-level assessment to inform future planning and regulatory proceedings California Public California Energy Utilities Commission Commission 4 RETI 2.0 Policy Context Executive Order B-30-15 • Established 40% GHG reduction goal by 2030 • Mandates state agencies to pursue with all statutory authority • New California Air Resources Board Scoping Plan SB 350 • CPUC and CEC increase Renewable Requirements from 33% by 2020 to 50% by 2030 • Require resource optimization -
2019 ENDTF Reliability Assessment Report
System Resilience Under Extreme Natural Disaster January 8, 2020 System Resilience Under Extreme Natural Disaster Executive Summary The purpose of this assessment is to evaluate the impact of an extreme natural disaster on the reliability of the Bulk Electric System (BES) in the Western Interconnection (WI). Given that the WI experiences extreme disasters somewhat regularly, such as yearly wild fires and occasional extreme earthquakes, this assessment is designed to identify challenges to the resilience of the WI and to help transmission providers plan accordingly. The scope of this assessment includes studying the impact on WI system adequacy and system stability within a Year 10 future in an Extreme Event caused by California wild fires. This case study was inspired by California’s Tucker Wild Fire in July 2019. The assessment used WECC’s 2028 Anchor Data Set (ADS) planning cases to model a Production Cost Model (PCM) analysis using ABB’s GridView software and a Power Flow (PF) Model analysis using GE’s PSLF software. To identify a highly stressed system condition, the assessment started with the ADS 2028 PCM Phase 1 V2.2, and identified August 7, 2028, Hour 20 (08/07/2018 Hr. 20) as the hour when Path 66 (COI) and Path 65 (PDCI) were most heavily loaded, and the danger of fire was highest. The generation dispatch and load for the 08/07/2028 Hr. 20 were extracted from the 2028 ADS PCM Phase 1 V2.2 and used as input for the 2028 Heavy Summer 1 base case to create a PF case for the assessment. -
Wind Power Transmission from Energy Rich North Dakota to California Through HVDC Lines
Session 2433 A Novel Solution for California’s Energy Crisis: Wind Power Transmission from Energy Rich North Dakota to California through HVDC Lines Recayi Pecen William Leighty Electrical & Information The Leighty Foundation-Alaska Engineering Technology Program University of Northern Iowa Abstract This paper first investigates feasibility of establishing a 7,000 MW power capacity wind farm, and the conversion of the total AC electrical power of 4,000 MW to the DC in a large converter station in Olga, North Dakota. Then it includes transmission of this bulk power to Northern California through a 1,700 miles, two bipolar +500 kV, 2,000A high voltage DC (HVDC) lines. The study assumes that there exists an average AC electrical power of 4,000 MW generated through two wind farms located in Olga, ND with 10,000 MW capacity. An existing wind capacity factor (CF) of 40%, which shows actual or predicted output as a % of installed capacity, is considered for this study. Two wind farms are considered to be established at Olga 3 and Olga 5 locations with average wind data available by North Dakota Department of Commerce - Division of Community Services. The commercially available North Dakota wind resource alone is estimated at over 1,000 TWh (billion kWh) per year. Dakotas wind energy potential is very stranded allover the land. Manitoba HVDC Research Center’s PSCAD /EMTDC power system software is used for the system modeling and simulation studies of the proposed HVDC scheme. Overall, the researchers determined that it is feasible and economical to establish a total power capacity of 10,000 MW from two new wind farms including 5,000MW at Olga 3, and other 5,000MW at Olga 5 wind sites, both are located in the north east corner of North Dakota, and one large 4,000 MW AC to DC converter station in Olga 5, and to transfer this DC power to the Northern California by HVDC lines. -
Upgrading the Intermountain HVDC Project to Handle 480 MW Additional Wind Power
21, rue d’Artois, F-75008 PARIS B4-108 CIGRE 2012 http : //www.cigre.org Upgrading the Intermountain HVDC Project to handle 480 MW additional Wind Power Mohammed J. Beshir Hans Bjorklund Los Angeles Department of Water and Power ABB USA Sweden SUMMARY The Intermountain Power Project, Southern Transmission System (IPP STS) was built in the early 80’s and commissioned in 1986 to bring power from a 1600 MW coal-fired generating plant in Utah to Southern California. The original project comprised of one bipole with 1600 MW ±500 kV continuous rating, meeting (N-1) reliability criteria. IPP STS had a very unique short-time overload rating allowing one pole to run at 2.3 p.u. current for few seconds before ramping down to operate continuously at 1.5 p.u. current (1200 MW power) should one pole trip [1]. To achieve this large overload on one pole all redundant cooling equipment for the transformers and the valves were used. The reactive consumption increased for the overloaded pole, but the full reactive power compensation for the bipole was available for that single pole. Some of this overload capability was used in 1989 when the bipole was up-rated to 1920 MW. To advance California’s environmental policies, in 2005 Los Angeles initiated an aggressive renewable resource development program to reach a 20% renewable portfolio standard (RPS) by 2010 (which was later supplemented with 35% RPS by 2020 and 30% CO2 reduction by 2030). One possible source for additional renewable resources was the wind power potential of southern Utah. -
2019 Transmission Plan
BONNEVILLE POWER ADMINISTRATION OPEN ACCESS TRANSMISSION TARIFF – ATTACHMENT K TRANSMISSION PLAN Prepared by Transmission Planning December 2019 2019 Table of Contents 1. Executive Summary .............................................................................................................................................................................. 6 2. Transmission Services ........................................................................................................................................................................... 8 2.1 Transmission Business Model .................................................................................................................................................. 8 2.2 Planning & Asset Management Organization ................................................................................................................... 8 2.3 Attachment K Planning Process ........................................................................................................................................... 9 2.4 FERC Order 845 ....................................................................................................................................................................... 9 3. Transmission Planning Activities ........................................................................................................................................................ 10 3.1 Area Planning and System Assessment ............................................................................................................................ -
OO-\EP-\B DATE AUG 0 1 2008 the STATE of CALIFORNIA Reed
DOCKET OO-\EP-\B DATE AUG 0 1 2008 THE STATE OF CALIFORNIA REeD. AUG 0 4 2008 BEFORE THE : ••t CALIFORNIA ENERGY COMMISSION In the Matter qf: ) ) . Preparation of the ) Docket No. 08-IEP-IB 2008 Integrated Energy Policy Report ) Update and the 2009 Integrated ) Energy Policy Report ) POST WORKSHOP COMMENTS OF THE CALIFORNIA MUNICIPAL UTILITIES ASSOCIATION, IMPERIAL IRRIGATION DISTRICT, LOS ANGELES DEPARTMENT OF WATER AND POWER, AND THE SACRAMENTO MUNICIPAL UTILITY DISTRICT . Pursuant to the Notice of Staff Workshop on Transmission Issues for 33% Renewables by 2020, the California Municipal Utilities Association and certain of its member utilities, the Imperial Irrigation District ("IID"), Los Angeles Department of Water and Power ("LAPWP"), and the Sacramento Municipal Utility District ("SMUD") (collectively "Joint Commentors"), respectfully submit these Post-Workshop Comments on issues regarding transmission infrastructure development to meet renewable energy goals. CMUA is a statewide organization of local public agencies in California that provide water, gas, and electricity service to California consumers. CMUA membership includes 43 electric distribution systems and other public agencies directly involved in the electricity industry. 1 CMUA members, including those listed above, own and operate CMUA electric utility members iilclude the Cities of Alameda, Anaheim, Azusa, Banning, Burbank, Cerritos, Colton, Corona, Glendale, Healdsburg, Lodi, Lompoc, Los Angeles, Needles, Palo Alto, Pasadena, Rancho Cucamonga, Redding, Riverside, Roseville, Santa Clara, and Vernon, as well as the Imperial, Merced, Modesto, Turlock Irrigation Districts, the Northern California Power Agency, Southern California Public Power Authority, Transmission Agency of Northern California, Lassen Municipal Utility District, Power and Water Resources Pooling Authority, Sacramento Municipal Utility District, the Trinity and Truckee Donner Public Utility Districts, the Metropolitan Water District of Southern California, and the City and COlmty of San Francisco, Hetch-Hetchy. -
FOIA #BPA-2019-00411-F Nathan Sandvig 205 SE Spokane Street
Department of Energy Bonneville Power Administration P.O. Box 3621 Portland, Oregon 97208-3621 FREEDOM OF INFORMATION ACT PROGRAM October 21, 2019 In reply refer to: FOIA #BPA-2019-00411-F Nathan Sandvig 205 SE Spokane Street, Suite 300 Portland, OR 97202 Email: [email protected] Dear Mr. Sandvig, This communication is the Bonneville Power Administration’s (BPA) final response to your request for agency records made under the Freedom of Information Act, 5 U.S.C. § 552 (FOIA). Your request was received on January 31, 2019, with a formal acknowledgement letter sent to you on February 12, 2019. Request “1. Contracts between the Bonneville Power Administration and PacifiCorp regarding construction and commercial use of PacifiCorp's Midpoint to Meridian transmission line. 2. Contracts between the Bonneville Power Administration and PacifiCorp and any other entity regarding operation and use of the Malin Substation.” Response BPA conducted a search of the electronic records in the Transmission Account Services office. That office located 95 pages of records responsive to your request. BPA is herein releasing all pages, with no redactions. Fees There are no fees associated with the response to your FOIA request. Certification Pursuant to 10 C.F.R. § 1004.7(b)(2), I am the individual responsible for the search, determination, and records release described above. Your FOIA request BPA-2019-00411-F is now closed with all available agency records provided. Appeal The adequacy of the search may be appealed within 90 calendar days from your receipt of this letter pursuant to 10 C.F.R. § 1004.8.