Final Days at Transalta's First Coal-Fired Generating Plant
Total Page:16
File Type:pdf, Size:1020Kb
Building community connections April 2010 Kilowatt Connection. Final days at TransAlta’s first coal-fired generating plant. On March 31, TransAlta’s Wabamun plant ceased The Wabamun site was “Many lived in the community of Wabamun and I’d like chosen for TransAlta’s to express my sincerest appreciation to the community operations after more than 50 years of supplying Albertans first coal-fired facility for its ongoing support and commitment to TransAlta with low-cost, reliable power. because of its proximity and our families.” to the large load centre in Edmonton, an adequate TransAlta is especially proud of the relationship Following the shut-down of the fourth and final unit, supply of cooling water and a significant deposit of developed between our company and the Village of TransAlta is now the first company in Alberta to some 50 to 60 million tonnes of coal located at the Wabamun over the years. With important plans for undertake complete decommissioning of a coal-fired nearby Whitewood Mine. tourism and development in the Wabamun area, we plant. Production from the Whitewood Mine ceased Wabamun’s team of hardworking and knowledgeable were pleased to discuss the options for some of the coinciding with the closure of the plant and maintenance and operations employees have been land zoned to TransAlta, west of the village, to be reclamation activities will begin shortly. reassigned and will be integrated reclaimed for future development. In November 2002, TransAlta announced plans to into other areas. “For more than 50 years some of “We saw reclaiming this land for future use as an easy implement a phased shut-down of the Wabamun our most talented employees kept the way to demonstrate our commitment to listening to plant. Unit 3 was shut-down in 2002 and Units 1 and 2 lights on in Alberta at the Wabamun our neighbours, “said Ralph Leriger, manager of were shut-down in December 2004. The decision to Plant,” said Steve Snyder, President Stakeholder Relations at TransAlta. ”And, we’re very decommission the Wabamun plant was made after a and CEO of pleased to do what we can to be a part of their plans to careful and thorough analysis which identified the TransAlta. ensure economic sustainability for their community.” costs to upgrade the 50 year-old facility to emerging environmental standards outweighed the benefits of continuing operation. Commissioning Keephills 3 At the Keephills 3 plant, the commissioning Anticipated Key phase is now underway. Commissioning is the Milestones in 2010 process during which the hand over from January construction to operation takes place. • Start instrumentation, air compressor system As various parts of the facility are completed, control commissioning activities can begin. Until the completion of construction, both commissioning and February/March construction can be happening at once. When the • Boiler hydro entire facility has been given the final stamp of • Water treatment plant approval, we are able to declare commercial operation. commissioning begins Contractually, Capital Power is responsible for the April / May construction phase, and TransAlta the operational • Turbine lube oil flushing phase. However, given that these two phases overlap, Capital Power representatives will continue to work July/August Traffic and Road Safety onsite, reducing their involvement over several • Air balance tests Keephills 3 - Construction Traffic Schedule months after commercial operation is achieved. • First boiler fire The majority of the K3 construction traffic accesses the site from the east in the There are a number of critical activities that take place morning and travels east from the site in the afternoon. Maximum traffic flows are during commissioning, including: August / September 15 – 20 minutes in duration. The following outlines the peak flow traffic times. This • Steam blows information is provided so that residents may avoid use of the noted highways at • Complete system walk downs (inspections) September / peak times (if possible) to reduce travel time delays due to traffic volume. We • First energization of equipment October anticipate traffic volume to steadily decrease over the coming months as fewer • Running equipment for the first time and making • Synchronization to the grid workers are required onsite. and combustion testing adjustments Monday – Friday (a.m.) TransAlta and Capital Power monitor • Running equipment as part of the bigger systems October / December 6:30 a.m. - 7 a.m. employee and contractor driving behaviours • Unit controls tuning on roads and highways that access the • Performance test run of entire system to validate Westbound on Hwy 627 Keephills 3 site. To help ensure a high guarantees – enter site via RR40 standard of safety, residents are encouraged • Final acceptance of equipment (the power plant) Monday – Thursday (p.m.) to phone the K3 Stakeholder Hotline at 5:25 p.m. – 5:45 p.m. 1-877-636-7823 if they witness unsafe or Craig Beattie, Keephills 3 project manager for aggressive driving practices. TransAlta, confirms we are on track to achieve Eastbound on Hwy 627 commercial operation in the first quarter of – exit site via RR40 Bus use by workers continues to increase 2011.”Given our past successful experience in Friday (p.m.) and currently 17 busses transport almost 50 commissioning coal plants, as well as our strong per cent of the 1,600 workers to and from 3:25 p.m. – 3:45 p.m. working relationship with Capital Power, we are site each day. confident that commissioning activities will be Eastbound on Hwy 627 completed according to plan and within our projected – exit site via RR40 timelines,” he says. www.transalta.com Building community connections Highvale Mine Stakeholder TransAlta’s 2010 Safety Goals Meetings The health and safety of our employees and communities is of paramount importance at TransAlta. We believe that achieving zero safety incidents is possible. Our rigorous management system, based on the OHSAS 18001 framework, guides our way. Our signature workforce safety program, Target Zero, is a way of working that is integrated into all that we do. This belief extends to: • A work environment where all known hazards are eliminated or safeguarded • People who understand their jobs, are properly trained, are mentally and physically fit, and follow proper work practices so that safety is integrated into all tasks performed • An empowered workforce where individuals take responsibility for their own safety, the safety of those they work with, and the safety of the communities surrounding our operations In 2010, TransAlta’s coal & mining, renewables, gas and construction teams all have their sights set on achieving aggressive but achievable safety targets across the fleet. Overall, this year we are striving to achieve an almost 13 per cent improvement compared to our year end in 2009. The teams are aiming to reduce the total number of recordable incidents to 52 compared to 56 in 2009. “We are getting back to the basics to improve our safety performance in 2010 TransAlta currently has to ensure that everyone goes home safely Over the past year there has been a steady increase in at the end of each day,” said Rod Kause, 412 MW of projects in activities at Pit 4 of the Highvale Mine. We are aware that director, Corporate Environment Health & development: 46 MW for with this ramp up in activity, there have been questions Safety. “Each team is committed to driving a true safety culture in order to Keephills 1 and 2 uprates; and concerns voiced by our neighbours. achieve outstanding results this year.” 225 MW for Keephills 3; 18 We are planning to hold a stakeholder information meeting to share our mine plans, as In order to decrease the number of MW for Bone Creek hydro well as to take the opportunity to discuss any concerns you may have.We intend to hold injuries by our contractors during outages the meeting at the Jack Pine Community Hall this spring. We will provide public notice in 2009 extra efforts are in place for project and 123 MW for when the date and time are confirmed. aggressive pre-outage safety orientation Ardenville and Kent Hills and training. Significant work is also TransAlta is committed to open dialogue with our stakeholders and are looking forward Expansion wind projects. to meeting with you. To receive more information about the stakeholder meeting, or for underway to educate and train all new any further information about our activity at the Highvale Mine, please call employees as part of their integration 1-877-636-7822. into TransAlta’s safety culture, tools and polices and procedures. As of March 3, 2010, there have been only six recordable incidents. “By working together and remaining focused we can maintain this positive trend and celebrate our best first quarter performance ever,” added Kause. Project Pioneer: How Will it Work? Project Pioneer is among the world’s largest fully-integrated carbon capture and storage (CCS) initiatives within the power sector. It will be a near-commercial scale demonstration of all elements of the CCS chain through a unique combination of partners, technology and integration. How will Project Pioneer Work Project Pioneer will be among the world’s first projects to test the full life cycle of CCS. Operating by 2015, Project Pioneer will be integrated with Keephills 3 (K3) – a 450 MW supercritical coal-fired plant jointly owned by TransAlta and Capital Power. On Oct. 20, TransAlta celebrated Located 70 kilometres west of Edmonton, Alberta, K3 is ideally situated overtop potential saline aquifer storage sites and near large, oil fields suitable for enhanced oil recovery (EOR). For 2010, the key focus for Project 100 years of incorporation. Pioneer is the completion of the front-end engineering and design (FEED) work. Today we are positioning our We look forward to meeting with you early this summer at our project open houses.