MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

City Accepted Amount AIRDRIE

Rehabilitate the Burt Church Theatre. $2,718,000

Contribute funding to the Acadia Community Association for the $500,000 rehabilitation of the Acadia Recreation Complex arena.

Plan, design, and rehabilitate the Calgary Arts Centre. $2,500,000

Contribute funding to the Crowchild Twin Arena Association for the $628,500 rehabilitation of the Crowchild Arena.

Contribute funding to the Calgary Curling Club for the rehabilitation $500,000 of the curling club.

Construct the Creative Hub for film, television, and digital $10,000,000 production.

Rehabilitate the Ernie Starr Arena. $1,595,000

Rehabilitate the Frank McCool Arena. $1,595,000

Rehabilitate the Henry Viney Arena. $1,595,000

Contribute funding to the Huntington Hills Community Association $643,453 for the rehabilitation of the Huntington Hills Community Centre.

Purchase the King Edward School building and rehabilitate as a $5,000,000 multi-use facility.

Contribute funding to the Millican-Ogden Community Association $287,500 for rehabilitation of the Millican-Ogden Arena.

Contribute funding to the Mount Pleasant Community Association $197,500 to upgrade the arena ice plant.

Contribute funding to the North East Sportsplex Society for the $411,275 rehabilitation of the North East Sportsplex.

Replace irrigation lines at the Optimist Athletic Park. $1,210,000

Contribute funding to the Calgary Soccer Federation for the $2,930,000 construction of a soccer facility.

Contribute funding to the West Hillhurst Community Association $549,000 for the rehabilitation of the West Hillhurst Arena.

Contribute funding to the Mount Pleasant Community Association $55,000 to replace an ice resurfacing machine.

Purchase land and construct affordable housing units in Mount $3,603,350 Pleasant.

Develop the Airport Trail underpass. $162,800,000

Purchase land and construct affordable housing units in Parkdale. $2,755,288

Purchase land and construct affordable housing units in Crescent $3,102,130 Heights.

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 1 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

CALGARY

Purchase land and construct affordable housing units in Kingsland. $5,102,078 COLD LAKE

Upgrade the wastewater and storm water systems along 10 Street, $415,000 and replace a portion of the road.

Replace in-ground hoists at the Davies transit facility. $1,522,412

Replace in-ground hoists at the Paterson transit facility. $2,239,513

Rehabilitate the Millwoods Recreation Centre pool. $2,300,000

Replace portions of the light rail transit signal system. $9,934,000

Extend the light rail transit platforms at the southside stations. $5,000,000

Construct a transit centre in Eaux Claire. $1,964,058

Construct a transit centre park and ride lot in Lewis Farms. $1,008,374

Upgrade Jackie Parker Park. $1,479,723

Construct a park and playground in the Suder Greens $1,186,255 neighbourhood.

Purchase land and construct highway connector links to ring roads $26,338,750 at various locations.

Purchase and install a smart bus system, including hardware, $2,500,000 software, and vehicle location consoles.

Rehabilitate several roads, including associated curbs, $61,012,000 gutters, sidewalks, and street lighting.

Conduct transportation studies and improve roads, signals, and $18,550,000 software for public transit purposes.

Construct and upgrade sidewalks, trails, and other related $7,176,000 infrastructure in various locations.

Rehabilitate portions of roads in Kensington, Sherwood, $2,450,000 Greenfield, Ritchie, and Gold Bar.

Construct a multi-purpose recreation building. $450,000

Design and construct a public works mechanics shop. $3,500,000

Rehabilitate the 100 Avenue bridge. $1,200,000

Upgrade the Dave Barr Community Centre. $1,500,000

Rehabilitate portions of several roads. $3,735,000 LEDUC

Resurface Coady Boulevard in the Caledonia Park Subdivision. $813,500

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 2 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

LEDUC

Purchase a grader. $220,000

Widen and realign the intersection at 50 Avenue and 46 Street. $1,770,000

Rehabilitate several roads in the Corinthia Park Subdivision. $611,850

Construct a municipal facility to house various infrastructure $16,100,000 departments. RED DEER

Rehabilitate portions of several roads. $5,469,424

Construct a sand and salt storage facility. $1,000,000

Design and construct a new public works facility and retrofit the $13,755,000 existing building.

Purchase a fire truck for joint use with and the $433,334 Town of Stony Plain. ST. ALBERT

Rehabilitate portions of several sidewalks. $1,012,000

Upgrade the Havenwood Stormwater Management Facility. $1,000,000

Rehabilitate a portion of Mission Avenue, including wastewater $1,500,000 lines, road base, sidewalk, curb, and gutter.

Specialized Municipality Accepted Amount CROWSNEST PASS, Municipality of

Replace a water main along a portion of 76 Street. $254,419

Migrate several municipal facilities into the supervisory control and $164,482 data acquisition system.

Upgrade underground infrastructure along 17 Avenue, including $569,216 extension and replacement of water, wastewater, and storm water mains.

Install a water main loop on 16 Avenue. $265,334

Complete a preliminary design to upgrade the Frank Wastewater $147,000 Treatment Plant.

Resurface a portion of 127 Street and replace water and $332,000 wastewater mains. JASPER, Municipality of

Rehabilitate and expand the Jasper Municipal Library. $4,200,000 MACKENZIE COUNTY

Rehabilitate a portion of 100 Avenue in the Hamlet of La Crete. $843,344

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 3 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

MACKENZIE COUNTY

Construct a parking lot at the administration and library building in $220,000 the Hamlet of Zama.

Replace a wastewater lift station in the Hamlet of Zama. $600,000

Purchase graders and a tractor. $870,000

Rehabilitate local roads and construct access roads. $500,000 STRATHCONA COUNTY

Rehabilitate the Ardrossan Recreation Complex. $3,648,600 WOOD BUFFALO, Regional Municipality of

Relocate wastewater, water distribution, and fiber optic lines along $13,000,000 Highway 63 and install new water mains and utility casings.

Municipal District Accepted Amount ACADIA NO. 34, M.D. OF

Purchase land for proposed road, water, wastewater, and $200,000 storm water system improvements.

Construct a west hamlet bypass road, a south hamlet bypass $100,000 road, and a service road from Highway 41 to Township Road 254.

Replace the existing sports arena. $500,000

Install water and wastewater distribution lines in the Hamlet of $324,530 Acadia Valley. ATHABASCA COUNTY

Rehabilitate the Pine Grove Estates and White Gull Access Roads. $508,300

Construct a regional waterline from the Village of Boyle to the $1,023,294 Hamlet of Wandering River, including a reservoir and pumphouse.

Upgrade Aspen Ridge Road from Highway 2 to Landing Trail Road. $912,400

Upgrade Skeleton Narrows Road from Range Road 191 to $928,800 Paradise Valley Road. BEAVER COUNTY

Purchase a grader shed in the Town of Viking. $350,000

Contribute funding to the Tofield Agriculture Society for the $200,000 purchase of an ice plant.

Purchase graders. $600,000 BIG LAKES, M.D. OF

Replace the South Heart River Bridge. $529,639

Replace a bridge and pedestrian walkway at Mission Creek. $673,579

Expand the public works shop. $152,303

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 4 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

BIG LAKES, M.D. OF

Construct a fire hall in the Hamlet of Kinuso. $1,066,168 BIRCH HILLS COUNTY

Purchase a supply of gravel. $756,901 BONNYVILLE NO. 87, M.D. OF

Expand and upgrade the municipal administration building. $6,394,300

Pave a portion of Dupre Road. $2,543,348 CAMROSE COUNTY

Install water distribution lines in the Hamlet of Duhamel. $2,179,580 CARDSTON COUNTY

Purchase land for a public works facility. $320,000

Purchase a gravel truck. $134,944

Purchase a tractor with a belly dump trailer. $164,039

Purchase a grader. $221,702 CLEARWATER COUNTY

Rehabilitate several roads. $2,454,311

Develop the Nordegg subdivision. $2,469,327 CYPRESS COUNTY

Construct and rehabilitate several roads. $1,000,000

Purchase a sanding truck. $300,000

Purchase a grader. $400,000

Jointly purchase a fire truck with the Special Areas Board. $216,900

Complete phase 2 of the Eagle Butte Road rehabilitation. $1,861,277 FAIRVIEW NO. 136, M.D. OF

Contribute funding to the Fairview Rural Water Coop for the $15,000 purchase of electronic water meter heads.

Purchase a community bus for use by various associations, sport $200,000 clubs, and other groups.

Purchase a supply of gravel. $500,000

Purchase and install automated vehicle location units as part of $250,000 the infrastructure management system. FOOTHILLS NO. 31, M.D. OF

Jointly construct an overpass at the junction of Highway 2 and 498 $1,900,000 Avenue with the Province of Alberta and the Town of High River.

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 5 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

FOOTHILLS NO. 31, M.D. OF

Purchase a pumper truck and tanker truck. $700,000

Conduct a water resource study. $352,000

Rehabilitate portions of several roads. $600,000 GRANDE PRAIRIE NO. 1, COUNTY OF

Pave a portion of Township Road 730. $1,500,000

Design and construct a sportsplex facility. $19,500,000

Construct a turning lane at Evergreen Park intersection. $1,500,000

Rehabilitate and widen Bauman Road. $720,000 GREENVIEW NO. 16, M.D. OF

Pave portions of Harper Creek Road and Township Road 704. $6,679,160 KNEEHILL COUNTY

Design and construct a county administration building. $5,500,000 LAC STE. ANNE COUNTY

Upgrade a portion of Range Road 84. $195,000

Upgrade a portion of Rail Grade Road. $150,000

Upgrade a portion of Township Road 540. $250,000

Upgrade a portion of Range Road 30. $525,000

Purchase a tanker truck. $279,983

Purchase graders. $1,097,444 LACOMBE COUNTY

Complete phase 2 of Haynes Road rehabilitation. $3,500,000

Rehabilitate a portion of Prentiss Road. $720,000

Rehabilitate and widen a portion of a road. $1,219,914 LAMONT COUNTY

Purchase a bulldozer. $185,000

Purchase a semi-tractor trailer. $125,371

Purchase a gravel pit. $265,000

Purchase a road mulcher. $447,954

Purchase two graders. $454,000 LEDUC COUNTY

Purchase two graders. $535,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 6 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

LEDUC COUNTY

Contribute funding to the Town of Beaumont for the installation of $203,000 traffic signals at the intersection of 50 Street and Township Road 510.

Contribute funding to the construction of the Beaumont S&D Aqua- $864,000 Fit Complex.

Upgrade the pumphouse in the Hamlet of New Sarepta. $24,000

Pave a portion of 5 Street. $450,000

Upgrade the wastewater lift station in the Hamlet of New Sarepta. $31,000

Rehabilitate a portion of Range Road 263 including an intersection $2,095,557 analysis and widening the road.

Replace graders. $636,000

Rehabilitate portions of roads in the Nisku Industrial Park. $1,691,395

Reinforce the sand and salt shed located near the Village of $260,000 Thorsby.

Replace the sand and salt shed located in the Hamlet of Nisku. $300,000 , COUNTY OF

Purchase a grader. $450,000

Reconstruct a portion of North Park Lake Road. $2,997,300 MINBURN NO. 27, COUNTY OF

Conduct a feasibility study for Range Road 91 and rehabilitate $341,532 several roads.

Jointly upgrade a waste transfer station with the villages $382,500 of Innisfree, Mannville, and Minburn.

Construct a water truck fill station in the Hamlet of Lavoy and $531,000 upgrade the associated pump station and reservoir.

Convert the existing landfill in the Hamlet of Ranfurly into a solid $721,500 waste transfer station.

Rehabilitate portions of Range Road 141, including the road $358,800 embankment. MOUNTAIN VIEW COUNTY

Rehabilitate portions of several roads. $1,850,000

Rehabilitate and pave several roads. $205,000

Construct a guard rail on Wimborne Road. $205,000 NEWELL, COUNTY OF

Construct water distribution lines for a regional water system. $27,000,000 NORTHERN LIGHTS, COUNTY OF

Purchase a grader. $400,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 7 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

NORTHERN LIGHTS, COUNTY OF

Contribute funding to the Town of Manning for the construction of $1,200,000 a fire hall. NORTHERN SUNRISE COUNTY

Develop the basement in the county administration building. $250,000 PARKLAND COUNTY

Rehabilitate Township Road 510 from Highway 759 to Range $1,100,000 Road 55.

Purchase right-of-way and rehabilitate Campsite Road from $5,500,000 Secondary Highway 627 to 628.

Purchase right-of-way and rehabilitate Township Road 530 from $5,260,000 Secondary Highway 770 to Range Road 21.

Purchase right-of-way and rehabilitate Township Road 510 $3,330,000 from Range Road 44 to 51.

Purchase right-of-way and rehabilitate Campsite Road from $3,000,000 Township Road 540 to Secondary Highway 633.

Purchase right-of-way and rehabilitate Graminia Road from Range $3,320,000 Road 271 to 273.

Purchase right-of-way and rehabilitate Range Road 51 from $700,000 Township 503A to 505.

Replace a portion of wastewater line and roadway along 51 Street $900,000 and 53 Avenue in the Hamlet of Entwistle.

Purchase three aerial fire trucks for joint use with the City of $1,421,833 Spruce Grove and the Town of Stony Plain. PEACE NO. 135, M.D. OF

Purchase a grader. $250,000

Purchase a backhoe loader. $65,000

Replace the culvert structure on Range Road 231. $30,000

Purchase a fire pumper truck. $150,000

Replace the fuel storage system, including installation of new $100,000 tanks and pipes. PINCHER CREEK NO. 9, M.D. OF

Repave a portion of Landfill Road. $1,980,125 PONOKA COUNTY

Rehabilitate a portion of Mecca Glen Road. $1,369,307 PROVOST NO. 52, M.D. OF

Rehabilitate a portion of Township Road 422. $1,372,731

Rehabilitate a portion of Range Road 82. $400,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 8 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

RANCHLAND NO. 66, M.D. OF

Contribute funding to the Town of Nanton for the rehabilitation of $16,000 the Tom Hornecker Recreation Centre roof. ROCKY VIEW COUNTY

Construct a fire hall and purchase firefighting equipment. $6,060,000 SADDLE HILLS COUNTY

Rehabilitate a portion of Township Road 801. $1,671,920 SMOKY LAKE COUNTY

Rehabilitate a portion of Range Road 180 between Township $125,250 Roads 595 and 600.

Purchase a trailer to transport road maintenance equipment. $110,000

Rehabilitate portions of Range Road 141. $145,000

Rehabilitate a portion of Township Road 620 between Range $200,000 Roads 140A and 142.

Rehabilitate a portion of Range Road 170 between Highway 28 $194,705 and Township Road 600.

Rehabilitate a portion of Range Road 170 between Highway 28 $107,800 and Township Road 592.

Rehabilitate a portion of Township Road 600 between Range $151,142 Roads 180 and 181A.

Pave roads in the resort communities of Mons Lake and Sandy $141,830 Lane. SMOKY RIVER NO. 130, M.D. OF

Rehabilitate several roads. $275,000

Upgrade several roads from dirt to gravel. $186,581

Purchase right-of-way for construction of the Peavine Road. $80,000 SPIRIT RIVER NO. 133, M.D. OF

Reconstruct a bridge along Township Road 773 between Range $87,500 Road 55 and 60.

Purchase a skid steer with attachments. $120,000

Upgrade portions of Township Road 782, including the purchase $50,000 of a right-of-way, installation of culverts, and widening of ditches. ST. PAUL NO. 19, COUNTY OF

Purchase graders. $1,714,091 STARLAND COUNTY

Purchase hardware and vehicle components for a vehicle-based $110,000 asset tracking system.

Design, purchase, and install rural addressing signs. $150,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 9 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

STARLAND COUNTY

Contribute funding to the Town of Drumheller for the construction $100,000 of the Badlands Community Facility.

Upgrade administrative building parking lot and install a buried $65,000 power line.

Purchase a modular office to temporarily house public works staff. $70,000

Design and construct a public works shop. $3,653,754 STURGEON COUNTY

Pave Excelsior Road from Highway 28 to Hewitt Estates. $1,680,000

Pave Sunnyside Road from Sturgeon River Bridge to Highway 28. $4,480,000 TABER, M.D. OF

Rehabilitate several roads. $1,044,214 VERMILION RIVER, COUNTY OF

Construct salt storage sheds. $550,000

Rehabilitate a portion of Township Road 511. $1,300,000

Rehabilitate a portion of Township Road 514. $2,700,000

Replace water and sewer lines on 51 Street. $217,000 VULCAN COUNTY

Purchase a water tanker truck. $129,436

Purchase several road maintenance vehicles. $1,128,201

Purchase a maintenance equipment service truck. $106,244

Purchase a tandem truck. $151,730

Purchase a generator. $89,000

Purchase a fire truck. $250,000

Purchase self-contained breathing apparatus equipment. $180,000

Purchase an emergency operations centre vehicle. $92,000

Construct a fire training facility. $525,000

Rehabilitate portions of several gravel roads. $659,494 WAINWRIGHT NO. 61, M.D. OF

Pave a portion of Township Road 452 and 454. $2,387,632 WARNER NO. 5, COUNTY OF

Purchase a grader. $221,150

Rehabilitate portions of Rod Nelson Road north. $404,880

Rehabilitate Roy Swanson Road. $268,079

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 10 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

WARNER NO. 5, COUNTY OF

Construct an access road to Goldsprings Colony. $425,051

Extend a waterline from the Raymond Regional Water Treatment $186,000 Plant to the Hamlet of New Dayton and county residents.

Contribute funding to the Town of Milk River for the construction of $136,000 the Milk River-Coutts Regional waterline.

Replace a portion of County Road. $218,000

Purchase a pumper truck. $314,000

Rehabilitate a portion of Township Road 612. $409,920

Purchase a gravel supply and rehabilitate portions of several $1,020,734 roads.

Purchase land and expand and rehabilitate the Pickardville $291,800 Lagoon. NO. 10, COUNTY OF

Contribute funding to the Fletcher Community Association to $2,400 replace gutters and eaves at the Fletcher Community Hall.

Contribute funding to the Lakedell Agricultural Society for boiler $29,402 replacement at the Lakedell Community Hall.

Implement rural addressing signage system $238,769

Purchase and install automatic vehicle location hardware in $361,231 county-owned vehicles.

Replace a culvert on Range Road 234. $336,000

Resurface a portion of Township Road 464 with chipseal. $481,191

Construct a public works storage building. $288,170

Contribute funding to the Alder Flats Agricultural Society to replace $30,000 the roof of the Alder Flats Community Hall.

Contribute funding to the Usona Agricultural Society to rehabilitate $10,741 the kitchen at the Usona Community Hall.

Contribute funding to the Buck Lake Seniors to replace the $10,000 furnace, water tanks, and boiler at the Buck Lake Seniors Drop-in Centre.

Contribute funding to the Fellowship of Alder Flats School $30,000 Committee for the construction of a playground in the Hamlet of Alder Flats.

Contribute funding to the Buck Lake Agricultural Society to $10,123 upgrade the washrooms in the Buck Lake Community Hall. WHEATLAND COUNTY

Repave portions of Rockyford Road. $3,810,000

Extend and replace waterlines in the Hamlet of Gleichen. $305,287

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 11 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

WOODLANDS COUNTY

Widen and rehabilitate a portion of Old Blue Ridge Highway. $2,500,000 YELLOWHEAD COUNTY

Pave Pindale Road. $1,735,146

Upgrade Long Lake Road. $4,150,000

Town Accepted Amount ATHABASCA

Purchase a mower. $70,000

Purchase a front-end loader. $150,000

Purchase a geographic information system. $90,000

Upgrade the supervisory control and data acquisition system for $50,000 the local water and wastewater systems. BASHAW

Install a storm water drainage swale and pipe at 51 Street. $37,350

Contribute funding to the Bashaw Playground Committee for the $11,430 rehabilitation of the local playground and sports field.

Install water valves. $79,416

Extend the road and underground utilities to 55A Avenue. $156,734

Rehabilitate a wastewater lagoon. $209,000 BEAVERLODGE

Jointly construct phase 2 of an indoor swimming pool with the $3,700,000 County of Grande Prairie. BLACK DIAMOND

Rehabilitate a portion of 1 Street. $76,250 BON ACCORD

Rehabilitate the administration building, including the construction $20,800 of additional offices.

Purchase a loader. $85,000

Purchase a mower. $40,000

Upgrade the arena, including the construction of meeting rooms $150,000 and barrier free washrooms.

Upgrade the public works shop. $57,000 BONNYVILLE

Construct a wastewater lift station in the Gateway Industrial Park $521,374 subdivision.

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 12 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

BONNYVILLE

Upgrade a portion of 54 Avenue, including road widening and $1,250,000 installation of a water line. BOW ISLAND

Repave School Crescent and replace the sidewalks, wastewater $545,000 lines, and waterlines. BRUDERHEIM

Replace a portion of sidewalk on 46 Street. $29,000

Rehabilitate a portion of 53 Avenue. $400,000

Construct a fire hall. $99,597 CALMAR

Repave a portion of 47 Street and 54 Avenue and replace curbs, $427,858 gutters, and sidewalks. CANMORE

Construct community daycare facility. $1,300,000 CARDSTON

Expand an irrigation line to several parks and the campground. $275,236

Install sidewalk, curb, and gutter along portions of 1 Street East $63,709 and 4 Avenue West.

Construct a wastewater line along 1 Street East and Lees Creek. $900,000

Replace waterlines along portions of 4 Avenue West and Main $240,500 Street.

Repave and rehabilitate portions of 2 Street East and 3 Avenue $83,800 East and West.

Install solar-powered circulators at the raw water reservoir. $54,425

Replace water pumps at the 9 Avenue booster station. $31,000

Install chlorine monitoring and disinfection equipment at the water $32,056 treatment plant.

Purchase a sewer camera. $80,000 CARSTAIRS

Construct the Tiny Lafleur Sports Park. $80,265

Construct a walking path. $43,750

Complete phase 2 of the Tiny Lafleur Sports Park construction. $60,000

Rehabilitate and pave a parking lot. $42,650 CASTOR

Replace portions of waterlines. $231,082

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 13 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

CASTOR

Install an emergency back up generator at the water plant. $106,700

Purchase a skid steer and a hydrovac. $123,400

Purchase a garbage truck. $19,700

Purchase an excavator. $260,000

Purchase a water tanker. $350,000

Construct a fire hall. $300,000

Construct an addition to the public works facility. $500,000

Renovate the multi-use administration building and emergency $205,000 operation centre.

Purchase a grader. $180,000

Purchase a highway tractor. $180,000 CLARESHOLM

Rehabilitate several roads in the North Industrial Subdivision. $131,028

Rehabilitate several roads and a parking lot, including $117,000 modifications required to control storm drainage. COALDALE

Construct a storm water detention pond. $1,052,400

Construct a multi-use facility for recreation and emergency $633,000 operations.

Construct sportsfields, including change rooms and storage $120,000 facilities.

Rehabilitate the Coaldale Sportsplex. $712,500 COALHURST

Upgrade the Coalhurst and District Community Centre parking lot. $30,000

Purchase and install playground equipment at Imperial Meadows $40,000 Park.

Purchase a fire rescue vehicle for joint use with the County of $75,000 Lethbridge.

Upgrade Miners Memorial Park. $38,000

Construct an access road to Highway 25. $322,785 COCHRANE

Replace street lights. $330,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 14 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

CORONATION

Replace a wastewater main along Victoria Avenue and Royal $245,217 Street. DAYSLAND

Replace gas meters. $25,000

Rehabilitate a portion of a waterwater line. $100,000

Rehabilitate the west end railway crossing. $40,000

Purchase and install fencing around recreational areas. $30,000

Rehabilitate a wastewater lift station. $200,000

Construct a storm water retention pond. $70,000 DIDSBURY

Rehabilitate and expand the wastewater lagoon system. $5,904,809 DRAYTON VALLEY

Rehabilitate a portion of 50 Avenue, including paving overlay and $321,528 installation of sidewalks. DRUMHELLER

Purchase a backhoe loader. $225,000

Reconfigure the existing civic centre into a new administrative $1,330,000 building.

Replace a ventilation unit in the Drumheller Aquaplex. $165,000

Replace mechanical equipment in the Drumheller Memorial Arena. $125,000

Purchase a fire pumper truck. $360,000

Replace the water slide in the Drumheller Aquaplex. $500,000 EDSON

Purchase an existing building in which physician office spaces are $350,000 located.

Install and connect water wells to the existing water system. $460,265

Expand and pave the Galloway Museum parking lot. $95,000

Construct a performance pavilion at Centennial Park. $310,185

Rehabilitate and pave portions of several roads. $161,050

Purchase a sewer camera and a waterline leak detector. $160,000

Purchase a fire engine. $292,500 FAIRVIEW

Construct a fire hall. $957,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 15 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

FALHER

Purchase and install water meters. $125,000

Purchase land to support the existing library. $52,151 FORT MACLEOD

Construct a wastewater trunk line and a water transmission main $584,978 to new subdivisions and the Alberta Public Safety and Law Enforcement Training Center. FOX CREEK

Purchase and install residential water meters. $404,500 GIBBONS

Purchase a loader. $175,000

Replace a water main along a portion of 51 Street. $33,913

Install a water main and fire hydrants along 51 Avenue. $341,250 GRANUM

Purchase a mower. $13,866 GRIMSHAW

Reconstruct the Grimshaw Multiplex. $1,230,086 HARDISTY

Replace the waterlines along 50 Street from 48 Avenue to 49 $187,966 Avenue, and affected roadway, curb, and sidewalk.

Purchase a sanding truck. $29,675 HIGH LEVEL

Construct a town hall park, including a paved walkway. $275,000

Construct an animal control facility. $238,544

Purchase a backhoe. $150,000

Replace a fire department rescue vehicle. $240,000 HIGH PRAIRIE

Jointly expand the fire hall with the Municipal District of Big Lakes. $521,000 HIGH RIVER

Construct a dyke to protect the Beachwood Subdivision. $1,415,350

Replace the communication system in the administration building $162,250 and fire hall, including telephones and controllers.

Replace a fire pumper truck. $383,612

Upgrade the Operations Centre. $350,000

Develop plans for a leisure centre. $150,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 16 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

HIGH RIVER

Rehabilitate and widen a portion of 12 Avenue. $3,225,000

Develop an Infrastructure Master Plan. $350,000

Develop a Flood Management Master Plan. $425,000

Construct a parking lot and restore landscaping at the Charles $500,000 Clark Medical Centre. HINTON

Construct a park along Happy Creek with picnic and play areas, $1,170,000 trails, and a bike park. INNISFAIL

Renovate the former library to become the firehall and construct $1,466,616 an addition on the building for the Emergency Operations Centre. IRRICANA

Purchase a riding mower. $16,000

Purchase a truck equipped with a plow and dump box. $76,000

Replace the community hall roof. $35,000

Replace furnaces in the community hall. $16,000

Construct an addition to the recreation complex. $20,000

Conduct a system-wide review of municipal buildings. $50,000 KILLAM

Rehabilitate an administration building. $17,390

Rehabilitate the Agriplex parking lot. $30,000

Purchase a fire truck. $180,000 LAMONT

Construct a new administration building. $1,200,000 LEGAL

Rehabilitate a baseball park, including replacement of bleachers $15,000 and reconstruction of washroom facilities.

Upgrade the arena, including rehabilitation of washroom facilities, $58,000 relocation of penalty boxes, and replacement of players benches.

Upgrade the trail system, including extension and pavement of $47,000 walkways, and rehabilitation of a wooden bridge.

Rehabilitate a portion of 50 Avenue and replace curbs and $166,793 sidewalk. MAGRATH

Upgrade the water treatment plant. $900,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 17 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

MANNING

Replace storm water conduits. $41,804

Pave a portion of 2 Avenue. $289,533 MCLENNAN

Upgrade the water treatment plant. $168,000

Contribute funding to the Municipal District of Smoky River for the $136,000 construction of a road from the Town of McLennan to the Peavine Métis Settlement.

Purchase a grader. $200,000 MILLET

Purchase a backhoe. $121,490 NANTON

Develop an infrastructure implementation plan. $30,000

Replace the Tom Hornecker Recreation Centre roof. $121,000 OKOTOKS

Purchase waste collection trucks and bins. $1,238,125 OLDS

Purchase a multi-purpose machine with attachments. $165,000

Purchase a loader mounted snow blower. $73,655

Install an acoustic leak monitoring system in the new subdivision $75,000 water distribution systems.

Rehabilitate several roads, including resurfacing and replacement $1,050,000 of waterlines, wastewater lines, and storm waterlines.

Prepare an Open Space and Trails Master Plan and upgrade the $200,000 trail system. ONOWAY

Upgrade a lift station including construction of a well and $367,163 installation of new mechanical, electrical, and control systems.

Rehabilitate Elks Park, including installation of new playground $28,725 equipment and parking lot upgrades.

Replace wastewater lines adjacent to Lac Ste. Anne Trail. $271,200 OYEN

Contribute funding to Alberta Health Services for the construction $100,000 of a medical clinic.

Replace the swimming pool boiler. $20,000

Purchase a first response vehicle and breathing apparatus. $63,000

Purchase a compressor and condenser for the arena. $73,565

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 18 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

PEACE RIVER

Replace water and wastewater mains in the Lower West Peace $163,903 area.

Replace water and wastewater mains in the West Hill area. $400,000

Purchase a water vacuum truck, a dump truck, and an ice $325,000 resurfacing machine.

Install a wheelchair accessible elevator in the town office. $184,750

Rehabilitate the water system, including replacement of a water $120,000 pump and water meter upgrades. PICTURE BUTTE

Construct a waterline. $65,000

Replace a water treatment facility pump. $17,500

Pave Factory Drive. $140,343

Purchase a skid steer. $60,000 PINCHER CREEK

Replace the roof of the Fred Huddlestun Senior Citizen Centre. $100,000

Replace the waterline along Church Avenue and Dupuy Street. $200,000

Expand the town hall and upgrade the meeting room. $265,000

Upgrade Castleview Heights Park, including relocation of $175,000 playground equipment and drainage improvements.

Upgrade the supervisory control and data acquisition system at $40,000 the water treatment plant.

Construct an asphalt trail from Elizabeth Street to Frederick Street. $200,000 PONOKA

Upgrade the Ponoka Culture and Recreation Complex, including $130,000 the front foyer and washrooms.

Reconfigure the existing water treatment facility into a new $93,000 community activity centre.

Upgrade the wastewater force main and lift station. $978,500 RAINBOW LAKE

Rehabilitate a municipally-owned staff housing unit. $40,000 RAYMOND

Upgrade the waste transfer station. $164,496

Upgrade the recreation facility. $311,576

Replace portions of several sidewalks. $35,504

Construct a covered picnic shelter. $80,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 19 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

REDCLIFF

Complete the design and engineering for the North Side Industrial $500,000 Subdivision expansion.

Rehabilitate a portion of 4 Avenue. $358,000

Rehabilitate a portion of 1 Avenue. $340,000

Rehabilitate a portion of 2 Avenue. $293,800

Rehabilitate portions of the road along 6 Avenue South East. $97,106

Evaluate the storm water system. $60,000 REDWATER

Purchase a rescue vehicle outfitted with extrication equipment. $35,530

Purchase a skid steer with attachments. $44,800

Purchase a lift truck. $24,500

Rehabilitate portions of 49 Avenue from 51 Street to 47 Street, $900,000 including sidewalk and drainage.

Purchase an ice resurfacing machine. $98,950 RIMBEY

Purchase a fire pumper truck for joint use with Ponoka County. $100,000

Evaluate existing infrastructure and develop an Infrastructure $60,000 Management Plan.

Replace sidewalks. $100,000

Upgrade the intersection at Highway 20 and 57 Avenue. $100,000

Install waterlines, valves, and pumps to connect the reservoir to $96,587 the water distribution system.

Install a sports floor in the Rimbey Community Centre Complex. $100,000

Replace playground equipment. $50,000 ROCKY MOUNTAIN HOUSE

Replace sections of water mains along 52, 53, 54 Avenue $1,178,099 and install a storm water main.

Replace sections of water mains along 47 and 48 Street. $630,000 SEDGEWICK

Replace the roof on the Sedgewick Recreation Center. $183,660

Repurpose a building into an eco-centre. $270,000

Replace portions of wastewater lines. $1,400,000

Rebuild Main Street Park, including replacement of the water $244,500 system and seating areas.

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 20 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

SEXSMITH

Construct an addition to the Community Center. $45,000

Construct a water spray park. $343,188 SMOKY LAKE

Develop a storm water retention plan. $50,000

Purchase a mower. $13,900

Purchase a gravel truck. $50,000 ST. PAUL

Jointly construct a medical clinic with the County of St. Paul. $2,100,000

Install water and wastewater lines along 57 Street. $375,000 STETTLER

Replace a culvert at Red Willow Creek. $280,000

Rehabilitate a portion of Main Street, including replacement of $408,000 sidewalks and installation of curb extensions.

Replace a wastewater main along a portion of 51 Avenue. $75,000

Replace a wastewater main located between 54 Street and 55 $300,000 Street.

Construct flood protection levees along Red Willow Creek. $160,000 STRATHMORE

Replace a pump at the Brentwood Reservoir and rehabilitate the $362,000 reservoir columns. SUNDRE

Install wheelchair access ramps in the downtown area. $55,200

Replace the roof of an office building that houses municipal $115,000 services, including a fire station.

Install manholes and purchase flow meters to monitor water leaks. $121,500 SWAN HILLS

Design and construct a solid waste transfer and recycle station. $149,480

Purchase a multi-purpose vehicle. $215,000

Purchase a skid steer loader with attachments. $75,000

Purchase a shoring cage and safety equipment for waterline $55,000 trenching. SYLVAN LAKE

Carry out phase 3 of Lakeshore Drive redevelopment, including $4,800,000 roadway, promenade, and Centennial Park improvements.

Construct an administration building. $610,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 21 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

SYLVAN LAKE

Upgrade a portion of 47A Avenue, including road reconstruction, $300,000 widening, and installation of a sidewalk. TABER

Rehabilitate the administration building. $1,114,373 THREE HILLS

Improve drainage around the water park and install a concrete $50,000 deck, walkway, and fence.

Develop a walking path and bike trail system. $125,000

Replace the aquatic centre roof. $60,000 TOFIELD

Contribute funding to the Tofield Agricultural Society for the $165,250 replacement of the ice plant in the Tofield Arena.

Purchase a flush truck. $250,000 TROCHU

Extend water and wastewater lines to a new mobile-home $523,668 subdivision and pave the roadway. TURNER VALLEY

Purchase a gravel truck. $43,550

Upgrade a section of road and replace manholes, wastewater $322,145 lines, and water mains. TWO HILLS

Pave a portion of 53 Avenue including the addition of curbs, $114,785 gutters, and sidewalk. VALLEYVIEW

Renovate the community hall. $206,383

Rehabilitate portions of several roads. $44,375

Rehabilitate the recreation facility and install free standing $30,000 exercise equipment along a trail.

Purchase a front-end loader. $112,000

Purchase an emergency response vehicle. $25,000 VAUXHALL

Purchase a grader and loader. $250,000 VEGREVILLE

Construct an equipment storage facility. $437,000

Purchase a garbage and recycling truck. $260,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 22 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

VEGREVILLE

Purchase a gravel truck. $106,000

Purchase a street sweeper. $200,500

Purchase an ice resurfacing machine. $100,000

Rehabilitate the Vegreville Materials Recovery Facility. $106,000 VERMILION

Construct a sand and salt storage building. $59,500

Rehabilitate local roads, including paving and installation of $336,647 sidewalks.

Rehabilitate the Vermilion Recreation Centre. $217,500 VIKING

Replace a snow blower attachment. $17,000

Replace a tandem truck. $55,000 WAINWRIGHT

Extend water and wastewater lines. $865,535

Rehabilitate a portion of Main Street including underground $3,687,737 infrastructure, sidewalks, curbs, and gutters. WHITECOURT

Replace the fire standpipe system in the Whitecourt Twin Arenas. $175,500

Replace the heating, ventilation, and air conditioning system in the $156,000 Allan and Jean Millar Centre.

Village Accepted Amount ACME

Rehabilitate the existing wastewater line by installing a liner. $400,000 ALBERTA BEACH

Construct a public works building. $276,659 ALIX

Upgrade lagoon pond banks. $50,000

Rehabilitate the railway crossings at Main Street and 47 Street. $12,000

Replace a storm water conduit. $20,000

Rehabilitate a portion of Railway Avenue. $50,000

Rehabilitate portions of several roads. $50,000 ALLIANCE

Purchase a loader including snow blade attachment. $45,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 23 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

AMISK

Assess municipal infrastructure and develop a long-term capital $125,000 plan. BARONS

Replace a tractor mower. $38,000

Replace the breathing apparatus in the fire hall. $20,000

Upgrade the wastewater system, including replacement of several $33,000 manholes and an outtake pipe.

Complete an assessment study of the storm water system. $25,000

Install water valves and fire hydrants. $30,000 BIG VALLEY

Rehabilitate 2 Avenue, including storm water drainage and $309,475 pavement.

Replace water valves. $75,000 BRETON

Construct a road and storm water ditches adjacent to Fraser Drive $246,725 and install water and wastewater infrastructure.

Install several fire hydrants. $52,400 CARBON

Complete the final phase of renovations in the administration $20,000 building.

Design and construct a fire station. $705,000

Inspect wastewater lines and prepare an assessment report. $10,200

Upgrade the electrical system in the campground. $40,250

Replace portions of wastewater lines. $70,000 CARMANGAY

Complete a major clean-up of a lagoon. $30,000

Purchase a backhoe. $55,000

Replace the roof on the administration building. $7,000

Install fire hydrants. $28,000 CHAUVIN

Purchase and install automated gas meter readers. $25,000

Pave 3 Avenue from Main Street to Dominion Street. $123,584 CLYDE

Purchase and install water meters. $54,803

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 24 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

CLYDE

Install a water main along a portion of Highway 18 to connect to $100,814 the existing water distribution system.

Pave a portion of 49 Street and rehabilitate a portion of 52 $47,033 Avenue. COUTTS

Jointly construct a regional water line with the Town of Milk River. $367,000 CREMONA

Replace the sidewalk on Railway Avenue. $25,000 CZAR

Rehabilitate several streets, including pavement and installation of $178,407 sidewalks. DELIA

Replace wastewater lines. $244,451 DONALDA

Replace the heating, ventilation, and air conditioning units in $18,042 the Village Complex.

Replace a wastewater line. $40,308

Purchase a tractor and a mower with attachments. $81,103

Purchase a public works vehicle. $52,875

Contribute funding to the County of Stettler for the joint purchase $25,000 of a pumper truck.

Purchase a snow plow attachment. $6,999 DONNELLY

Install a main distribution waterline. $149,000

Purchase and install upgraded water meters. $62,000 DUCHESS

Pave a portion of Prairie Winds subdivision and 1 Street. $250,000

Install a wastewater bypass line parallel to Highway 550. $90,500

Install a lift station for a storm water retention pond. $30,000 ELNORA

Replace a section of wastewater line. $15,000

Purchase a skid steer. $10,000

Develop a Storm Water Management Plan. $25,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 25 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

EMPRESS

Purchase a modified truck for use as a gravel truck for garbage $135,000 and snow removal. FOREMOST

Rehabilitate the Foremost and District Civic Centre and $80,000 Recreational Facility, including replacement of siding and the swimming pool filtration system.

Purchase a front-mount mower. $17,000

Upgrade the wastewater lift station. $73,435

Upgrade the raw water pump and system controls. $68,110 FORESTBURG

Replace wastewater lines. $302,825

Repave portions of several roads. $225,957 GALAHAD

Replace the electrical panel and the structure housing the water $7,000 wells.

Inspect water and wastewater lines, and prepare an underground $25,000 infrastructure capital plan.

Develop a community park, including washroom facilities. $32,000 GIROUXVILLE

Pave a portion of 50 Avenue, replace sidewalks, and install a $177,913 storm water line. GLENWOOD

Construct the Glenwood Community Centre including rehabilitation $765,048 of associated library space and relocation of the village office. HALKIRK

Pave a portion of Howard Street. $80,000 HAY LAKES

Conduct a drainage assessment and geotechnical study and pave $60,930 several local roadways.

Purchase an emergency generator and install transfer switches. $52,621

Replace the bobcat and purchase attachments. $25,776 HEISLER

Develop a new municipal park. $22,000 HILL SPRING

Rehabilitate a skating rink. $7,000

Install a storm water line. $17,760

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 26 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

HILL SPRING

Extend portions of the village's drainage ditch network. $149,423 HUGHENDEN

Purchase snow removal equipment. $79,000

Rehabilitate the wastewater lagoon. $190,000 HUSSAR

Construct a wastewater lift station. $285,841 INNISFREE

Contribute funding to the County of Two Hills for construction of a $55,944 regional waste transfer site.

Contribute funding to the Alberta East Central Water Corporation $73,920 for a regional water system. IRMA

Upgrade 50 Street and replace the water and wastewater lines. $241,960

Purchase tractor mowers. $29,101 LOMOND

Replace several residential and business water meters. $40,000

Purchase a new tractor bucket. $6,700

Replace the roof on the village office. $10,160

Replace the roof on the water treatment plant. $6,500

Replace residential cast iron water lines. $71,942

Upgrade the water treatment plant. $59,421

Replace the tractor-mounted mower. $6,300 LONGVIEW

Construct a wastewater lagoon. $388,277 LOUGHEED

Rehabilitate the roof of the administration building and public $14,298 library.

Construct an access road for a commercial district. $32,000 MARWAYNE

Replace portions of water and wastewater lines. $251,197 MILO

Replace several curb stops. $200,000

Purchase a skid steer. $35,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 27 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

MILO

Purchase land and a facility for the Public Works Department. $50,000

Inspect the wastewater lines using camera technology. $16,726

Rehabilitate the Snake Valley Drop-in Centre. $15,500

Rehabiliate the administration office. $9,600 MINBURN

Rehabilitate a baseball field, including installation of fencing and $10,000 bleachers.

Rehabilitate a portion of Main Street. $50,000

Purchase a maintenance truck. $8,500

Purchase a video security system to monitor village roads. $25,000

Upgrade infrastructure for a wireless internet network expansion. $30,000

Install infrastructure for a new subdivision including roads, $40,000 sidewalks, and a sewer line. MORRIN

Replace a portion of the wastewater lines along 2 Avenue. $300,000 MUNSON

Purchase a computer for use with infrastructure management $7,200 system software.

Rehabilitate portions of several streets. $24,000

Purchase a sanding truck. $50,000

Purchase a tractor. $32,000 MYRNAM

Purchase a water truck. $35,000

Purchase a bobcat and attachments. $27,000 NAMPA

Rehabilitate a portion of Railway Avenue. $241,000 NEW NORWAY

Construct a pumphouse. $150,544 PARADISE VALLEY

Replace fire hydrants. $8,300

Purchase a loader. $100,865 ROSALIND

Construct water and wasterwater lines. $42,390

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 28 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

ROSALIND

Drill a water well. $18,000

Purchase a tractor with additional components. $15,330 ROSEMARY

Install water mains on Lupin Avenue and Aster Street. $115,000

Rehabilitate the wastewater line along Centre Street and Aster $44,100 Street. RYLEY

Replace a dump truck. $25,000

Replace a lawnmower. $20,000

Rehabilitate existing wastewater lines by installing a liner. $150,000 SPRING LAKE

Construct a recreational trail system. $15,200 STANDARD

Install an aeration system at the raw water reservoir. $75,000

Replace water and wastewater lines. $900,000

Purchase a tractor. $35,000 STIRLING

Construct a storage facility and install fencing at the local sports $60,000 complex.

Upgrade the swimming pool. $50,000

Pave and upgrade portions of 2 and 3 Street between 4 and 5 $193,658 Avenue. STROME

Complete engineering work to extend 48 Street and 49 Street to a $10,500 new subdivision.

Purchase a public works vehicle. $10,000

Replace water main valves and upgrade manholes. $180,000

Purchase a grader. $15,000 VETERAN

Replace the garbage truck. $20,000 VILNA

Rehabilitate and replace fire hydrants. $87,750

Upgrade the Vilna Water Treatment and Distribution Facility. $105,720

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 29 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

WABAMUN

Construct a playground in Waterfront Park. $133,046

Upgrade the parking lot in Waterfront Park. $133,046 WARBURG

Pave a section of and construct sidewalks along 52 Avenue and $142,205 45 Street.

Jointly construct an addition to the fire hall with Leduc County. $23,700

Replace portions of several sidewalks. $25,000

Purchase a mower. $10,000 WASKATENAU

Construct a shelter for an emergency response vehicle. $15,000

Replace the roof on a water facility. $10,000 WILLINGDON

Construct an addition to the firehall. $50,000 YOUNGSTOWN

Rehabilitate several roads. $150,000

Summer Village Accepted Amount

Construct a wastewater collection system. $1,186,128

Rehabilitate several roads, including paving, installation of guard $734,000 rails, and culverts.

Construct a storm water ditch in Perch Close. $15,868

Construct a solid waste collection depot. $99,000 CASTLE ISLAND

Construct a storage shed. $6,000 HALF MOON BAY

Design a wastewater collection system. $110,000 HORSESHOE BAY

Construct a parking lot. $10,000

Rehabilitate Shank Drive, Kirby Place, and Neilson Drive. $544,165

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 30 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

JARVIS BAY

Design a waterline. $120,000 LARKSPUR

Resurface several roads. $166,407 MA-ME-O BEACH

Repave several roads. $51,176

Rehabilitate the community hall, including plumbing, heating, and $50,000 ventilation system upgrades and replacement of windows and doors.

Rehabilitate Mewatha Drive. $88,101

Upgrade the electrical system in the public works building. $12,000

Purchase a truck equipped with a hydraulic lift. $20,000

Construct a storage shed. $20,000

Design a waterline. $120,000

Install a wastewater collection system to connect to the Pigeon $89,909 Lake Regional Wastewater system.

Convert an existing natural area into a park and install playground $100,000 equipment. PARKLAND BEACH

Expand and renovate the community hall/administration facility, $188,000 including the installation of a new water well and septic tank.

Complete the construction of the public works shop. $15,000

Purchase and install playground equipment. $20,000 PELICAN NARROWS

Rehabilitate portions of several roads. $178,972

Purchase a walkway sweeper and blower. $9,345

Rehabilitate Prospect Drive. $14,000

Rehabilitate a portion of Poplar Bay Drive. $105,500

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 31 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

ROSS HAVEN

Construct a new recreational trail system. $115,900 SILVER SANDS

Rehabilitate several roads. $23,563

SUNBREAKER COVE

Design a wastewater collection system. $120,000 SUNRISE BEACH

Purchase a mower. $10,270

Pave portions of Victory Road and Shedden Drive. $461,987 SUNSET BEACH

Rehabilitate a portion of Willow Drive. $400,000 SUNSET POINT

Construct designated parking areas. $50,000

Rehabilitate the storm water drainage system. $350,000

Rehabilitate the wastewater lagoon. $200,000 YELLOWSTONE

Contribute funding to the North 43 Lagoon Commission for the $117,325 construction of a lagoon force main.

Construct an addition to the public works building. $90,000

Purchase a video security system to monitor the main road. $6,000

Improvement District Accepted Amount I.D. NO. 04 (WATERTON)

Upgrade equipment at the water spray park and extend adjacent $60,000 sidewalks. I.D. NO. 12 (JASPER NATIONAL PARK)

Rehabilitate a railway crossing and adjacent road. $120,000

Special Area Accepted Amount SPECIAL AREAS BOARD

Jointly purchase a fire truck with Cypress County. $250,000

Purchase graders. $669,500

Purchase a maintenance reclaimer. $614,000

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 32 Project descriptions and amounts include accepted amendments as of June 8, 2012. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2011 Accepted Projects Report

SPECIAL AREAS BOARD

Design and construct new disposal sites at the Big Country Waste $500,000 Management landfill.

Metis Settlement Accepted Amount BUFFALO LAKE METIS SETTLEMENT

Purchase a vacuum truck. $157,528 EAST PRAIRIE METIS SETTLEMENT

Purchase a water distribution truck. $196,208

Purchase emergency generators. $10,000

Purchase a garbage truck. $70,000 ELIZABETH METIS SETTLEMENT

Purchase a mulcher and track loader. $79,850

Purchase and install infrastructure for a broadband internet $186,598 network.

Purchase a garbage truck. $97,000

Rehabilitate the public works building. $28,000

Rehabilitate the community recreation centre. $20,000

Rehabilitate a portion of South Road. $40,000

Rehabilitate portions of gravel roads. $100,000 KIKINO METIS SETTLEMENT

Design of and engineering for the Kikino Communi-plex. $217,019

Other Accepted Amount TOWNSITE OF REDWOOD MEADOWS ADMIN SOC

Develop an Infrastructure and Drainage Plan. $30,000

Purchase a multi-use utility vehicle. $28,000

Purchase a water tanker truck for the fire department. $280,000

Rehabilitate the administrative and community centre building. $32,803

This report reflects the name and status in effect for each municipality at the time the report was produced. Page 33 Project descriptions and amounts include accepted amendments as of June 8, 2012.