Social Monitoring Report

Semiannual Report

Project no: 44219-014 Loan/Grant: 3139/0397 Period Covered: July-Dec 2018

January 2019

NEP: South Asia Sub-regional Economic Cooperation (SASEC) Power System Expansion Project (On- Grid)- (Annexure 1-9,11,12,13)

Prepared by the Electricity Authority and the Asian Development Bank.

This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Annexure-1 Tower Foundation and Tower Erection Details DKTLP

District: Parbat S.N Angle Point Completed Foundatio Remaining Completed Erection Remarks Location Foundation n Under Erection Under Progress Private Jungle Ailani progress Land (Semi Govt) 1 AP01 1 PVT 1 ku.na.pa-2 2 AP01A 1 PVT 1 ku.na.pa-2 3 AP01B 1 PVT 1 ku.na.pa-2 4 AP01C 1 PVT 1 ku.na.pa-2 5 AP02 1 Guthi 1 ku.na.pa-1 6 AP02/1 1 PVT 1 ku.na.pa-1 7 AP02/2 1 PVT 1 ku.na.pa-1 8 AP02A/0 1 PVT 1 ku.na.pa-1 9 AP03 1 PVT Forest 1 ku.na.pa-1 10 AP04 1 PVT Forest 1 ku.na.pa-1 11 AP05 1 PVT Forest 1 ku.na.pa-1 12 AP06 1 PVT 1 Jaljala-8 13 AP06A 1 PVT Guthi Jaljala-8 14 AP06B 1 PVT 1 Jaljala-8 15 AP07 1 PVT Forest 1 Jaljala-8 16 AP07A 1 PVT Jaljala-8 17 AP08 1 PVT Forest 1 Jaljala-8 18 AP08A 1 Forest Jaljala-8 19 AP09 1 Forest Jaljala-8 20 AP09A 1 Forest Jaljala-8 21 AP09B 1 Forest Jaljala-8 22 AP09C 1 Forest 1 Jaljala-8 23 AP10 1 PVT Forest 1 Jaljala-8 24 AP11 1 PVT Forest Jaljala-7 25 AP11A PVT Jaljala-7 26 AP12 1 PVT Jaljala-7 27 AP13 1 PVT 1 Jaljala-7 28 AP13/1 1 PVT Jaljala-7 29 AP13A 1 PVT 1 Jaljala-7 30 AP13B 1 Forest 1 Jaljala-7 31 AP13C 1 Forest 1 Jaljala-7 32 AP14 1 Forest 1 Jaljala-7 33 AP14/1 1 Forest 1 Jaljala-7 34 AP14A 1 Forest Jaljala-7 35 AP15 1 PVT 1 Jaljala-7 36 AP16 1 Forest 1 Jaljala-4 37 AP16A 1 Forest 1 Jaljala-4 38 AP17 1 PVT 1 Jaljala-4 39 AP17A 1 PVT 1 Jaljala-4 40 AP17B PVT Jaljala-4 41 AP18 1 PVT Jaljala-4 42 AP18A 1 PVT Jaljala-3 43 AP18B 1 Forest 1 Jaljala-3 44 AP18C 1 Forest 1 Jaljala-3 45 AP19 PVT Jaljala-3 46 AP20 1 Forest 1 Jaljala-3 47 AP21 1 PVT 1 Jaljala-3 48 AP21A 1 PVT 1 Jaljala-2 49 AP22 1 PVT Jaljala-2 50 AP23 1 PVT 1 Jaljala-2 51 AP24 1 PVT Jaljala-2 52 AP24A 1 PVT Jaljala-2 53 AP25 1 PVT 1 Jaljala-2 54 AP25A 1 PVT Jaljala-2 55 AP25B 1 PVT 1 Jaljala-2 56 AP26 1 PVT 1 Jaljala-1 Total 45 8 36 1 District: Myagdi SN Angle Point Completed Foundatio Remaining Completed Erection Remarks Location Foundation n Under Erection Under Progress Private Jungle Ailani progress Land (Semi Govt) 57 27/0 1 PVT 1 Rahuganga-3 58 27A/0 1 PVT 1 Rahuganga-3 59 27B/0 1 PVT 1 Rahuganga-3 60 28/0 1 PVT 1 Rahuganga-3 61 28A/0 1 PVT 1 Rahuganga-3 62 29/0 1 PVT Rahuganga-3 63 30/0 1 PVT Rahuganga-2 64 31/0 PVT Rahuganga-2 65 32/0 1 PVT Rahuganga-2 66 32A/0 PVT Rahuganga-2 67 33/0 PVT Rahuganga-2 68 33A/0 PVT Rahuganga-2 69 33B/0 1 PVT 1 Rahuganga-2 70 34/0 1 PVT 1 Rahuganga-2 71 34A/0 1 PVT 1 Rahuganga-2 72 34B/0 1 PVT 1 Rahuganga-2 73 35/0 1 Forest 1 Rahuganga-1 74 35A/0 1 Forest Rahuganga-1 75 35B/0 1 PVT 1 Rahuganga-1 76 35C/0 1 PVT Rahuganga-1 77 36/0 1 PVT 1 Rahuganga-1 78 36A/0 1 PVT 1 Rahuganga-1 79 37/0 1 PVT 1 Annapurna-7 80 38/0 1 PVT 1 Annapurna-7 81 39/0 1 PVT Forest 1 Annapurna-7 82 39A/0 1 PVT Guthi 1 Annapurna-7 83 39B/0 1 PVT Guthi 1 Annapurna-7 84 39C/0 1 PVT Guthi 1 Annapurna-7 85 39D/0 1 PVT 1 Annapurna-1 86 40/0 1 Forest Annapurna-6 87 40A/0 1 PVT 1 Annapurna-1 88 41/0 1 PVT 1 Annapurna-1 89 41A/0 PVT ROW Annapurna-6 90 41B/0 PVT ROW Annapurna-6 91 42/0 PVT ROW Annapurna-6 92 42A/0 PVT ROW Annapurna-6 93 42B/0 PVT ROW Annapurna-6 94 43/0 PVT ROW Annapurna-6 95 44/0 1 PVT 1 Annapurna-2 96 44A/0 1 PVT Forest 1 Annapurna-2 97 45/0 1 Forest Annapurna-2 98 46/0 Govn Annapurna-2 99 46A/0 1 PVT 1 Annapurna-3 100 46B/0 1 Forest Annapurna-3 101 47/0 1 PVT Annapurna-3 102 47A/0 1 forest Annapurna-3 103 47B/0 1 PVT Annapurna-3 104 47C/0 1 PVT 1 Annapurna-3 105 48/0 1 Forest 1 Annapurna-3 106 48A/0 1 PVT 1 Annapurna-3 107 49/0 1 PVT 1 Annapurna-3 108 50/0 1 PVT 1 Annapurna-3 109 51/0 1 PVT 1 Annapurna-3 110 DE 1 PVT 1 Annapurna-3 Total 38 5 29 3 Grand Total 83 13 65 4

MKTLP

SN Angle Point Completed Foundati Remaining Completed Erection Remarks Location Foundation on Under Erection Under Progress Private Jungle Ailani progress Land (Semi-Govt) 1 TP 0 0 0 Bandbhanjyang, Ktm. 2 AP-0/0 DE 1 0 0 Bandbhanjyang 3 AP-1/0 1 0 0 Land Bandbhanjyang Acquisition not done 4 AP-2/0 1 0 0 Land Bandbhanjyang Acquisition not done 5 AP-2/A 1 0 0 Land Bandbhanjyang Acquisition not done Total 0 0 3 1 0 0 4 District: Dhading SN Angle Point Completed Foundati Remaining Completed Erection Remarks Location Foundation on Under Erection Under Progress Private Jungle Ailani progress Land (Semi-Govt) 1 AP-2/B 1 ,Dhunibes i 2 AP-2/C 1 Naubise,Dhunibes i 3 AP-3/0 1 Poultry form Naubise,Dhunibes has i constructed at foundation location. 4 AP-4/0 1 Land has Naubise,Dhunibes excavated i by land owner about 12 m down than original. 5 AP-5/0 1 Naubise,Dhunibes i 6 AP-5/A/0 1 Naubise,Dhunibes i 7 AP-5/B/0 1 Naubise,Dhunibes i 8 AP-6/0 1 Naubise,Dhunibes i 9 AP-6/A/0 1 Naubise,Dhunibes i 10 AP-7/0 1 1 Naubise,Dhunibes i

11 AP-7/A 1 1 Naubise,Dhunibes i 12 AP-7/B 1 1 Naubise,Dhunibes i 13 AP-7/C 1 1 Naubise,Dhunibes i 14 AP-7/D 1 1 Naubise,Dhunibes i 15 AP-7/D/1 1 Not clear Naubise,Dhunibes i 16 AP-7/D/2 1 House at Naubise,Dhunibes foundation i (ROW) 17 AP-7/E 1 1 Naubise,Dhunibes i 18 AP8/0 1 1 Archale

19 AP8/1 1 0 1 Archale

20 AP8/2 1 1 Archale 21 AP-8/A 1 1 Ganishe

22 AP-8/B 1 1 Ganishe Chaur 23 AP-9/0 1 1 Ganishe Chaur

24 AP-10/0 1 1 Tower parts Pandit Pauwa off loaded at site 25 AP-11/0 1 1 Pandit Pauwa

26 AP-11/A 1 1 Pandit Pauwa

27 AP-11/B 1 1 Tower parts Pandit Pauwa off loaded at site 28 AP-11/C 1 1 Pandit Pauwa

29 AP-12/0 1 1 Pandit Pauwa

30 AP-12A 1 1 Kebalpur 31 AP-12/A/1 1 1 Kebalpur 32 AP-12/B 1 Angur Kheti Kebalpur 33 AP-13/0 1 1 Kebalpur 34 AP-13/A 1 1 Kebalpur 35 AP-13/B 1 1 Kebalpur 36 AP-13/C 1 1 Tower parts Kebalpur off loaded at site 37 AP-13/D 1 1 Kebalpur 38 AP-14/0 1 1 leg Kebalpur 39 AP-14/A 1 1 Kebalpur 40 AP-14/B 1 1 Kebalpur 41 AP-14/C 1 1 Kebalpur 42 AP-15/0 1 1 Tower parts Kebalpur off loaded at site 43 AP-16/0 1 1 Goganpani 44 AP-16/A 1 1 2 pit Goganpani 45 AP-16/B 1 1 Tower parts Goganpani off loaded 46 AP-16/C 1 1 Tower parts Goganpani off loaded 47 AP-17/0 1 1 Tower parts Goganpani off loaded 48 AP-17/A 1 Goganpani 49 AP-17/B 1 Goganpani 50 AP-18/0 1 Goganpani 51 AP-18/A 1 Goganpani 52 AP-18/B 1 Goganpani 53 AP-18/B/1 1 2 pit Goganpani

54 AP-18/C 1 Goganpani 55 AP19/0 1 Goganpani 56 AP-19/A 1 Goganpani 57 AP-19/B 1 Goganpani 58 AP-19/C 1 Goganpani 59 AP-20/0 1 Galchhi 60 AP-20/A 1 Galchhi 61 AP-20/B 1 1 Galchhi

62 AP-20/C 1 1 Galchhi

63 AP-20/D 1 1 Galchhi () 64 AP-21/0 1 1 Galchhi

65 AP-21/1 1 ROW Issue Galchhi 66 AP-21/1/1 1 1 Galchhi 67 AP-21/A 1 1 Galchhi

68 AP-21/B 1 ROW Issue Galchhi 69 AP-21/C 1 1 3 pit Galchhi 70 AP-21/D 1 1 Galchhi

71 AP-21/E 1 Galchhi 72 AP-21/F 1 ROW Issue Galchhi 73 AP-21/G 1 1 74 AP-21/H 1 1 Baireni

75 AP-21/I 1 1 Baireni 76 AP-21/J 1 1 Baireni 77 AP-22/0 1 Peda

78 AP-23/0 1 Peda

79 AP-23/A 1 1 Pipaltar, 80 AP-24/0 1 1 Pipaltar,Kumpur AP-24/1 1 3 pit Pipaltar,Kumpur 81 AP-24/A 1 Pipaltar,Kumpur 82 AP-24/B 1 Pipaltar,Kumpur 83 AP-24/C 1 Pipaltar,Kumpur 84 AP-24/D 1 1 2 pit Pipaltar,Kumpur 85 AP-24/D/1 1 1 Pipaltar,Kumpur 86 AP-24/D/2 1 1 Pipaltar,Kumpur 87 AP-24/D/3 1 1 Pipaltar,Kumpur 88 AP-24/E 1 Pipaltar,Kumpur 89 AP-24/F 1 Pipaltar,Kumpur 90 AP-24/G 1 Pipaltar,Kumpur 91 AP-25/0 1 1 Chhapdanda 92 AP-25/A 1 1 Chhapdanda 93 AP-25/B 1 1 Chhapdanda 94 AP-25/B/1 1 1 Tower parts Chhapdanda off loaded 95 AP-25/C 1 1 Tower parts Chhapdanda off loaded 96 AP-26/0 1 1 Tower parts Chhapdanda off loaded 97 AP-26/A 1 1 Kumpur (Siddalek) 98 AP-26/B Kumpur

99 AP-27/0 1 1 Kumpur 100 AP-27/A 1 1 Kumpur 101 AP-27/A/1 1 Kumpur 102 AP-27/B 1 Kumpur 103 AP-27/C 1 Kumpur 104 AP-27/D 1 Kumpur 105 AP-27/E 1 Kumpur 106 AP-28/0 1 1 Kumpur

107 AP-28/A 1 Road 108 AP-29/0 1 Land Malekhu excavated about 17 m down by land owner new tower foundation design to be done. 109 AP-29/A 1 Land rate Malekhu now finalized on19-08- 018 110 AP-29/B 1 do Malekhu 111 AP-30/0 1 do Malekhu 112 AP-30/A 1 do Malekhu 113 AP-31/0 1 1 Salang 114 AP-31/1 1 1 Salang 115 AP-31/2 1 1 Salang 116 AP-31/A 1 1 Salang 117 AP-32/0 1 1 Salang 118 AP-32/1 1 1 Salang 119 AP-33/0 1 1 Salang 120 AP-33/A 1 1 Salang 121 AP-33/B 1 1 Salang 122 AP-33/B/1 1 1 Salang 123 AP-34/0 1 1 Salang 124 AP-34/A 1 Land rate finalized(RO W) 125 AP-34/A/1 1 1 Salang 126 AP-35/0 1 1 Salang 127 AP-37/0 1 1 Bishaltar 128 AP-37/A 1 3 pit Bishaltar 129 AP-43/B 1 ROW Issue 130 AP-44/0 1 1 Jogimara 131 AP-44/A 1 1 Tower parts Jogimara off loaded 132 AP-45/0 1 1 Jogimara 133 AP-46/0 1 1 Jogimara 134 AP-46/1 1 1 Jogimara 135 AP-46/A 1 1 Jogimara 136 AP-46/B 1 1 Jogimara 137 AP-46/C 1 1 pit Jogimara 138 AP-47/0 1 1 Jogimara 139 AP-47/A 1 1 Jogimara 140 AP-47/B 1 1 Jogimara 141 AP-47/C 1 1 Jogimara 142 AP-47/D 1 1 Jogimara 143 AP-48/0 1 1 Jogimara Total 101 14 24 4 76 13 143 District: Chitwan

SN Angle Point Completed Foundati Remaining Completed Erection Remarks Location Foundation on Under Erection Under Progress Private Jungle Ailani progress Land (Semi Gvt) 1 AP-49/0 0 1 Darechowk 2 AP-49/A 0 1 Darechowk 3 AP-49/B 1 1 Darechowk 4 AP-50/0 1 1 Darechowk 5 AP-50/A 1 1 Darechowk 6 AP-51/0 1 1 Darechowk 7 AP-51/A 1 1 Darechowk 8 AP-51/B 1 Darechowk 9 AP-52/0 1 1 Darechowk 10 AP-52/A 0 1 Darechowk 11 AP-52/B 1 1 Darechowk 12 AP-53/0 1 1 Darechowk 13 AP-54/0 1 1 Darechowk 14 AP-54/A 1 1 Darechowk 15 AP-54/B 1 1 Darechowk 16 AP-54/C 0 1 House Darechowk 17 AP-55/0 1 Darechowk 18 AP-56/0 0 1 Darechowk 19 AP-56/A 0 1 2 pit Darechowk 20 AP-57/0 0 1 3 pit Darechowk 21 AP-57/A 0 0 1 Darechowk 22 AP-57/B 0 0 1 Darechowk 23 AP-57/C 1 1 Darechowk 24 AP-58/0 1 1 Darechowk 25 AP-58/A 1 Darechowk 26 AP-58/B 0 1 2 pit Darechowk 27 AP-58/C 0 1 1 pit Darechowk 28 AP-59/0 0 1 Darechowk 29 AP-60/0 1 Darechowk Total 17 6 2 4 12 1 29 District: Gorkha S. Angle Point Completed Foundati Remaining Completed Erection Remarks Location No. Foundation on Under Erection Under Progress Private Jungle Ailani progress Land (Semi Gvt) 1 AP-35/1 1 1 Siurenitar 2 AP-35/A 1 1 Siurenitar 3 AP-36/0 1 1 Siurenitar 4 AP-37/B 1 1 Ghyalchowk 5 AP-37/C 1 1 Ghyalchowk 6 AP-37/D 1 1 Ghyalchowk 7 AP-38/0 1 1 Ghyalchowk 8 AP-38/1 1 1 Ghyalchowk 9 AP-38/A 1 1 Ghyalchowk 10 AP-38/B 1 1 Ghyalchowk 11 AP-39/0 1 1 Ghyalchowk 12 AP-39/A 1 1 Ghyalchowk 13 AP-40/0 1 1 Ghyalchowk 14 AP-40/A 1 1 Ghyalchowk 15 AP-41/0 1 Ghyalchowk 16 AP-42/0 1 1 Ghyalchowk 17 AP-43/0 1 1 Ghyalchowk 18 AP-43/A 1 1 Ghyalchowk 19 AP-60/A 1 Gyaja 20 AP-61/0 1 Gyaja 21 AP-61/1 1 3 pit Gyaja 22 AP-61/A 1 Gyaja 23 AP-61/B 1 Gyaja 24 AP-62/0 1 Gyaja 25 AP-63/0 1 Gyaja 26 AP-64/0 1 Gyaja 27 AP-65/0 1 Gyaja 28 AP-65/A 1 Gyaja 29 AP-65/B 1 Gyaja 30 AP-66/0 1 Gyaja 31 AP-67/0 1 1 Gyaja 32 AP-67/A 1 Manakamana 33 AP-68/0 1 1 Manakamana 34 AP-69/0 1 1 Manakamana 35 AP-69/1 1 1 Manakamana 36 AP-69/A 1 1 Manakamana 37 AP-70/0 1 1 Deurali 38 AP-70/A 1 Deurali 39 AP-70/B 1 Deurali 40 AP-70/C 1 Deurali 41 AP-70/D 1 1 Deurali 42 AP-71/0 1 1 Deurali 43 AP-72/0 1 1 Deurali 44 AP-72/A 1 Deurali 45 AP-72/B 1 1 Deurali 46 AP-73/0 1 Deurali 47 AP-73/A 1 3 leg Deurali completed 1 leg at house 48 AP-74/0 1 1 Deurali 49 AP-74/1 1 1 Deurali 50 AP-74/2 1 3 leg Deurali complete 1 leg ROW issue 51 AP-75/0 1 1 Deurali Total 43 6 0 2 27 3 51 District: Tanahun S. Angle Point Completed Foundati Remaining Completed Erection Remarks Location No. Foundation on Under Erection Under Progress Private Jungle Ailani progress Land (Semi Gvt) 1 AP-75/A 1 1 2 AP-75/B 1 1 3 AP-75/C 1 1 4 AP-76/0 1 0 0 Markichowk Total 4 0 0 0 3 0 4 Grand Total 165 26 29 11 118 17 231

Annexure-2 Status of Compliance with Loan Covenants

Para Current Sch. Description No. Status 4. 9. The Borrower shall ensure that no Works contract which involves involuntary resettlement impacts is Being awarded, until the Borrower and NEA have prepared and submitted to ADB the final RIPP based on the complied Project’s detailed design, and obtained ADB’s clearance of such RIPP. 4. 10. The Borrower shall ensure that no Works contract which involves impacts on indigenous peoples is Being awarded until the Borrower and NEA have prepared and submitted to ADB the final RIPP, and obtained complied ADB’s clearance of such RIPP. 5. 7. The Borrower shall establish and maintain, or cause NEA and AEPC to establish and maintain, a grievance Being redress mechanism acceptable to ADB for the purpose of addressing any grievances arising out of the complied Project, including those from affected peoples concerning land acquisition, environment and any other social issues in a timely manner. 5. 12. The Borrower shall ensure, or cause NEA and AEPC, as applicable, to ensure, that all land and all rights-of- Being way required for the Project, each Subproject and all Project facilities are made available to the Works complied contractor in accordance with the schedule agreed under the related Works contract and all land acquisition and resettlement activities are implemented in compliance with (a) all applicable laws and regulations of the Borrower relating to land acquisition and involuntary resettlement; (b) the Involuntary Resettlement Safeguards; (c) the RF (for Subprojects); and (d) all measures and requirements set forth in the RIPP, as appropriate, and any corrective or preventative actions set forth in the Safeguards Monitoring Report. 5. 13. Without limiting the application of the Involuntary Resettlement Safeguards or the RIPP, the Borrower shall Being ensure, or cause NEA to ensure, that no physical or economic displacement takes place in connection with complied the Project until: (a) compensation and other entitlements have been provided to affected people in accordance with the RIPP, as appropriate; and (b) a comprehensive income and livelihood restoration program has been established in accordance with the RIPP, as appropriate. 5. 14. The Borrower shall ensure, or cause NEA and AEPC to ensure, as applicable, that the preparation, design, Being construction, implementation and operation of the Project, each Subproject and all project facilities comply complied with (a) all applicable laws and regulations of the Borrower relating to indigenous peoples; (b) the Indigenous Peoples Safeguards; and (c) the IPPF (for Subprojects); and (d) all measures and requirements set forth in the RIPP, as appropriate, and any corrective or preventative actions set forth in a Safeguards Monitoring Report. 5. 15. The Borrower shall ensure that Part 3 of the Project does not have any indigenous peoples or involuntary Being resettlement impacts, all within the meaning of SPS. In the event that Part 3 of the Project does have any complied such impact, the Borrower shall take all steps to ensure that the Project complies with (a) the applicable laws and regulations of the Borrower; (b) the SPS; and (c) the IPPF and the RF, as applicable. 5. 16. The Borrower shall make available, or cause NEA and AEPC to make available, necessary budgetary and Being human resources to fully implement the EMP and the RIPP. complied 5. 17. The Borrower shall ensure, or cause NEA and AEPC to ensure, that all bidding documents and contracts for Being Works contain provisions that require contractors to: complied (a) comply with the measures relevant to the contractor set forth in the IEE, the EMP and the RIPP (to the extent they concern impacts on affected people during construction), and any corrective or preventative actions set forth in a Safeguards Monitoring Report; (b) make available a budget for all such environmental and social measures; (c) provide the Borrower with a written notice of any unanticipated environmental, resettlement or indigenous peoples risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP and the RIPP; (d) adequately record the condition of roads, agricultural land and other infrastructure prior to starting to transport materials and construction; and (e) Reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction. 5. 18. The Borrower shall do the following or cause NEA and AEPC to do the following: Being (a) submit semiannual Safeguards Monitoring Reports to ADB and disclose relevant information from such complied reports to affected persons promptly upon submission; (b) if any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP, and the RIPP, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan; (c) report any actual or potential breach of compliance with the measures and requirements set forth in the EMP and the RIPP promptly after becoming aware of the breach.

Annexure 3

Rate Fixation for compensation

Compensation Rate Fixation in MKTLP-

Land Rate (per Kaththa)

Location Access to earthen Access to track way / No access to motor Way Gully road

Ikchhakamana RM (Former 8 Lakh 7 Lakh 6 Lakh Darechowk VDC, Ward N. 1 and 7)

IkchhakamanaIkchhakamana RM (Former Darechowk VDC, Ward No. 6.50 Lakh 5.50 Lakh 4.75 Lakh 2 and 3)

Compensation Rate Fixation in MKTLP-

Land Rate (per Ropani)

Location Access to earthen Access to track No access to motor Way way / Gully road

24 Lakh 23 Lakh 22 Lakh Berighat Rorang RM ( Surrounding area of Malekhu Bazar of former Benighat VDC ward no-6) 23 Lakh 22 Lakh 21 Lakh

22 Lakh 21 Lakh 20 Lakh Berighat Rorang RM ( Surrounding area of Benighat and Bishaltar of forrmer Benighat VDC 21 Lakh 20 Lakh 19 Lakh ward no-8)

Compensation Rate Fixation Meeting minutes of CDC, Dhading district

Land acquisition notice of district-MKTLP

Annexure 4 Status of Compensation Distribution and Land Acquisition

Details of Compensation Distribution due to land acquired in Myagdi-District (DKTLP)

Tower Received S.N. Land Owner’s Name Address No. Amount

1 Dani Prasad Gauchan Annapurna-3 AP 51 1753906.00 2 Deu Bahadur Garbuja Annapurna-7 AP 38 209375.00 3 Man Bahadur Purja Annapurna-7 AP 37 1196875.00 4 Kum Bahadur Garbuja Annapurna-7 AP 38 175000.00 5 Gam Bahadur Biswakarma Annapurna-3 AP 52 603125.00 6 Mati Maya Thapa Annapurna-3 AP 48 A 218359.00 7 Chandra Prasad Sherchan Annapurna-3 AP 46 A 1828125.00 Gomati Bhanne Gau Devi 8 Raghuganga-1 AP 36 1371094.00 Tilija 9 Krishan Prasad Tulachan Annapurna-3 AP 52 175000.00 10 Purna Bahadur Karki Raghuganga-3 AP 27 B 995313.00 11 Dhan Kumari Bhandari Raghuganga-2 AP 32 925000.00 12 Dil Kumari Pun Raghuganga-1 AP 36 A 462109.00 13 Dalfi Ramjali Magar Annapurna-1 AP 40 A 812500.00 14 Tul Bahadur KC Raghuganga-2 AP 30 415625.00 15 Om Prasad Pun Raghuganga-1 AP 36 A 345313.00 16 Tek BahadurTilija Raghuganga-1 AP 36 A 218359.00 17 Man Bahadur Pun Raghuganga-1 AP 49 96484.00 Nand Bahadur Katuwal 18 Annapurna-3 AP 47 C 776953.00 Chhetri 19 Lil Bahadur Pun Annapurna-3 AP 49 817578.00 AP 27 20 Tug Bahadur Mallla Raghuganga-3 1911328.00 AP 28 21 Toran Kumari Karki Raghuganga-2 AP 33 B 162500.00 22 Karn Bahadur Karki Raghuganga-2 AP 33 B 890625.00 23 Hark Bahadur Ramjali Annapurna-3 AP 50 1002930.00 24 Nar Bahadur Purja Annapurna-3 AP 49 10156.00 25 Tilisara Thapa Magar Annapurna-3 AP 47 B 1015625.00 26 Rammaya Ramjali Annapurna-3 AP 47 A 271680.00 27 Chameli KC Raghuganga-2 AP 30 312500.00 28 Som Bahadur Bhandari Raghuganga-3 AP 27 A 502734.00 29 Indra Bahadur Karki Raghuganga-3 AP 28 18750.00 Bishnu Bahadur Karki,Ram 30 Raghuganga-3 AP 28 9375.00 Bahadur Karki 31 Basant Karki KC, Rajan KC Raghuganga-2 AP 31 765625.00 32 Dirgha Bahadur Thapa Annapurna-3 AP 47 B 10156.00 33 Na Bahadur Purja Annapurna-1 AP 41 1546875.00 34 Rim Bahadur Karki Raghuganga-3 AP 298437.00 Jang Bahadur Rantija Pun, 35 Annapurna-7 AP 39 653125.00 Nandsari 36 Harikala Sherchan Annapurna-3 AP 48 180273.00 37 Jang Bahadur Thapa Annapurna-3 AP 48 A 469727.00

38 Chandra Bahadur Garbuja Annapurna-3 AP 39 C 208203.00

39 Tekku Pun Annapurna-7 AP 39 C 203125.00 40 Ha Bahadur Purja Annapurna-1 AP 39 D 835352.00 41 Rabisha Purja Raghuganga-1 AP 36 A 335157.00 Dhan Bahadur Pun ,Sant 42 Annapurna-3 AP 47 343750.00 Bahadur Garbuja

Thaman Bahadur 43 Annapurna-7 AP 39 121875.00 Purja,Chha Bahadur Purja

44 Fulu Padhyaya Mangala-1 AP 30 456250.00 45 Raju Kumari Shahi Raghuganga-3 AP 27 A 523047.00 46 Takmati Purja Raghuganga-1 AP 35 B 593750.00 47 BalKumari Sunar Annapurna-2 AP 44 671875.00 Hira Bahadur Rantija ,Kum 48 Annapurna-7 AP 38 821875.00 Bahadur Tirth Bahadur and Dhan 49 Raghuganga-1 AP 35 B 898438.00 Bahadur Purja 50 Samita Sherchan Annapurna-2 AP 44 A 212500.00 51 Ram Bahadur Sherchan Annapurna-2 AP 44 A 425000.00 52 Pritam Rantija Annapurna-7 AP 39 C 337695.00 53 Ruk Devi Sherpunja Annapurna-7 AP 39 C 337695.00 54 Min Bahadur Karki Chhetri Annapurna-2 AP 47 C 203125.00 TOTAL 30957226.00

Compensation Distribution of the land acquired for tower construction in -DKTLP

Angel Compensation S.N. Land Owner Address Point Received Amount 1 Khantari Padhyaya 46875/-

2 Chandra Datta Jaisi 31,250/- AP1 Kusma-2 3 Gayatri Devi Padhyani 11,09,375/- 4 Padma Devi Sharma 5,39,062/- 5 Ishwari Prasad Padhya 402343/- 6 Tej Kumari Padhyani 125000/- 7 AP1A Motikala Padhyani Kusma-2 93750/- 8 Gagan Raj Sharma 97656/- 9 Putali Nepali 601562/- Kusma -2 10 AP1B Tara Devi Sharma 332031/- 11 Fanindra Paudel 115625/- 12 Bhumiraj Paudel 271875/-

13 Loknath Paudel 109375/-

14 Pabitra Jaisi 159375/-

15 Rabilal Sharma Paudel 228125/- AP1 C Kusma-1 16 Bal Krishna Upadhyaya 143750/- 17 Pitambar Das Bairagi 15625/- 18 Sabitra Gharti 58593/- 19 Ramakant Paudel 539062/-

20 Ishwari Prasad Rijal 31250/-

21 Gobind Prasad Rijal 171874/-

22 Kul Prasad Paudel 128906/- AP2A Kusma-1 23 Dhaka Ram Paudel 171875/- 24 Netra Lal Rijal 335937/- 25 AP2/1 Madan Prasad Paudel 62,500/- Kusma-1 26 Yadav Prasad Paudel 421875/- 27 Sunil Rijal 287500/- 28 Khyam Raj Rijal 106250/- 29 AP2/2 Jamuna Kadel Kusma-1 193750/- 30 Kopila Rijal 9375/- 31 AP3 Bishnu Prasad Upadhyaya Kusma-1 18750/- 32 Atma Hari KC 262500/- 33 Baburam KC 128906/- Angel Compensation S.N. Land Owner Address Point Received Amount 34 Gajendra Bahadur Khatri 253125/- 35 Parshuram KC 229687/- AP6 Bhim Bahadur Gharti Jaljala-8 36 18750/- Chhetri 37 Bisi Damini 9375/- 38 Hank Bahadur Chhetri 7031/- 39 Durga Bahadur Chhetri 7031/- 40 Khum Bahadur GC 4687/- 378125/- 41 Bhime Damai

42 AP6A Purna Lal Sharma Jaljala -8 134375/- 43 Rishiram Padhya 12500/- 44 Laxmi Prasad Upadhyaya 119531/- 45 Jayashwar Upadhyaya 241406/- AP6 B Narayan Prasad Jaljala-7 46 7031/- Upadhyaya 47 Dandpani Padhya 124609/-

48 Taranath Regmi 124609/- AP7 Jaljala-7 49 Kamal Prasad Regmi 270703/- 50 AP11 Gokul Prasad Jaisi Jaljala-7 96679/- 51 Shiv Prasad Acharya 23437/-

52 Kedarnath Acharya 843750/- AP12 Jaljala-7 53 Lilawati Rijal 73242/- 54 Dil Bahadur Damai 45410/-

55 Bagbir Damai 308007/- AP21 Jaljala-2 56 Durge Damai 185546/- 57 Bagbir Damai 11132/- 58 AP21A Balbir Darji Jaljala-2 55664/- 59 Guma Kumari Baruwal 311717/- AP24 Jaljala-2 60 Chandra Bahadur Baruwal 582617/- Guman Singh Karki 61 AP25 Jaljala-2 968750/- Chhetri 62 AP2/1 Manarupa Rijal Kusma-2 Parbat 421875/- 63 AP12 Shiv Prasad Acharya Jaljala-7 Parbat 98437/- 64 AP13 Man Kumari Upadhyaya Jaljala-7 Parbat 219736/- Angel Compensation S.N. Land Owner Address Point Received Amount 65 AP18A Shyam Bahadur Shrestha Jaljala-3 Parbat 205859/- 66 AP18 Durga Bahadur Karki Jaljala-4 Parbat 260351/- 67 AP1 Durga Bahadur Sharki Jaljala-4 Parbat 248632/- 68 AP18A Ishwari Kumari Shrestha 151366/- 69 AP13A Dandpani Upadhyaya Jaljala-7 Parbat 1084375/- 70 AP2/1 Dilli Raj Upadhyaya Kusma-1 Parbat 25000/- Bam Bahadur Jaljala-3 Parbat 423046/- 71 AP22 Bishwakarma 72 AP17 Arjun Bahadur Malla Jaljala-4 Parbat 404492/- 73 Saraswati Karki Jaljala-4 Parbat 284570/- 74 AP18 Muna Damai Jaljala-4 Parbat 45410/- Total 16,673,246.00/-

Details of Compensation Distribution due to land acquired in Dhading-District (MKTLP)

Deed Total Angle Municipalit Ward Plot Required Land Compensation S.N Land Owner Name Vulnerable Groups transf affected Month Point y/RM No No Area Amount er land sq m Below Women Disabl IP Dalit povert headed ed y line 1 AP8/0 Raj Kumar Tamang 1 1 1 Thakre RM 8 371 0 10 3 0 341.85 839843.75 May 2 AP8/0 Bishnu Kumar Tamang 1 1 Thakre RM 8 373 0 10 3 2 345.83 849609.38 May 3 AP8/1 Ramesh Thapa 1 Thakre RM 8 405 0 11 3 0 373.65 917968.75 May AP46/ Benighat 4 Rudra Devi Mainali 1 10 79 0 7 1 0 230.55 453125.2 May 0 Rorang Sani Maiya 5 AP8/2 Khadka/Hom Bdr 1 Thakre RM 8 235 0 8 3 0 278.25 683593.75 May Khadka AP17/ 6 Bishnu Bhujel 1 1 Thakre RM 11 118 0 13 2 0 429.3 1012500 May 0 AP24F 7 Chandra B.Shrestha 1 1 Siddha Lek 7 182 0 1 3 2 59.63 134765.63 May /0 AP24D 8 Sunita Khatiwada 1 Siddha Lek 7 133 0 14 3 0 469.05 1198437.5 May /1 AP25A 9 Raj Kumar Shrestha 1 1 Siddha Lek 7 223 1 1 3 1 566.38 1280273.44 May /0 AP24G 10 Samsere Sarki 1 1 Siddha Lek 7 272 0 13 0 1 415.39 938867.19 May /0 AP25C 11 Rewati Prasad Pandey 1 Siddha Lek 7 9 0 15 2 2 496.88 1269531.25 May /0 12 8A/0 Kul Bahadur Thapa 1 Thakre RM 8 17 0 8 3 3 284.22 782031.25 May AP33/ 13 Hem Lal Sedai 1 Siddha Lek 3 134 0 10 1 2 329.93 713281.25 May 0 AP33/ 14 Lila Nath Sedai 1 Siddha Lek 3 135 0 11 3 0 373.65 807812.5 May 0 AP33B 15 Khun Prasad Sedai 1 Siddha Lek 3 120 0 10 2 3 339.87 734765.63 May /0 AP33A Deb Kumari Sedai/Than 16 1 Siddha Lek 3 122 0 2 3 3 93.42 201953.13 May /0 Nath Sedai AP34/ 17 Ram Prasad Pandey 1 Siddha Lek 3 181 0 2 3 1 89.44 193359.38 May 0 AP7D/ 18 Duna Raj Koirala 1 Dhunibesi 6 104 0 9 3 0 310.05 731258 May 0 19 AP7/0 Dinesh Thapa Magar 1 1 Dhunibesi 6 529 0 3 1 2 107.33 253125 May Sub Total 6 0 1 1 0 19 5934.67 13996101.98 AP12/ Padam Kumari Pandit 1 Thakre RM 9 402 0 11 3 0 373.65 881258 June 0 20 AP12/ Padam Kumari Pandit 1 Thakre RM 9 400 0 0 1 2 11.93 28125 June 0 AP2C/ 21 Janak K.C 1 Dhunibesi 9 433 0 12 1 2 393.53 1,082,812.50 June 0 AP23A 22 Mandira Khatiwada 1 Siddha Lek 7 123 0 15 2 1 494.89 1264453.13 June /0 AP46/ Benighat 23 Buddhi Lal Shrestha 1 1 10 80 1 1 1 0 548.49 1078125 June 0 Rorang AP13C Rudra Prasad Adhikari 1 Thakre RM 10 105 0 2 3 1 89.44 210937.5 June /0 24 AP13C Rudra Prasad Adhikari 1 Thakre RM 10 156 0 13 2 1 431.29 1017187.5 June /0 AP 25 Durga Ba.Shrestha 1 1 Thakre RM 8 196 0 0 2 1 17.89 49218.75 June 8A/0 AP 26 Saili Shrestha 1 1 Thakre RM 10 157 0 1 3 1 57.64 135937.5 June 13/0 AP25C 27 Yedu Kumar Ghimire 1 Siddha Lek 7 10 0 6 1 2 202.73 458203.13 June /0 AP32/ Keshar Bahadur Thapa 28 1 1 Siddha Lek 4 43 0 15 0 1 478.99 941406.25 June 1 Magar AP24G 29 Yek Maya Mijar 1 1 Siddha Lek 7 271 0 10 2 0 333.9 853125 June /0 AP47A Benighat 30 Om Pd. Shrestha 1 1 10 9 0 3 0 0 95.4 187500 June /0 Rorang Benighat 31 45/0 Dil Bahadur Parja 1 1 10 271 1 4 1 1 645.88 1269531.25 June Rorang 1 Total 6 0 1 0 0 14 0 120 2656 2 93 22 4175.65 9457820.51 3 AP24G 32 Krishne Sarki 1 1 Siddha Lek 7 270 0 1 3 3 61.62 157421 July /0 AP25/ Chandra Bahadur 1 Siddha Lek 7 125 0 8 1 0 262.35 670312.5 July 0 Shrestha 33 AP24F Chandra B Shrestha 1 1 Siddha Lek 7 178 0 4 3 0 151.05 341406.25 July /0 34 AP28/ Kashi Bahadur Magar 1 1 Siddha Lek 6 4 0 9 2 0 302.10 771875 July 0 AP28/ Nanda Kumari Darlami 1 Siddha Lek 6 5 0 10 0 0 318.00 500000 July 0 Magar 35 AP28/ Nanda Kumari Darlami 1 1 Siddha Lek 6 3 0 0 2 3 21.87 49414.06 July 0 Magar AP32/ 36 Indra Kumari Tripathi 1 Siddha Lek 4 138 0 3 1 0 103.35 284375 July 0 AP32/ Yam Kumari Thapa 37 1 1 Siddha Lek 4 42 0 2 2 1 81.49 176171.88 July 1 Magar AP32/ 38 Satal Sing Magar 1 1 Siddha Lek 4 44 0 1 0 2 35.78 77343.75 July 1 Siddha 39 31A/0 Nira Kumari Tripathi 1 1 4 376 1 1 1 0 548.49 1509375 July Lake AP33C 40 Sita Devi Pandey 1 Siddha Lek 3 239 0 2 3 0 87.45 189062.5 July /0 AP34/ Mohan Lal 1 1 Siddha Lek 3 163 0 1 3 0 55.65 120312.5 July 0 Thapa/Magagr 41 AP34/ Mohan Lal Thapa/Magar 1 Siddha Lek 164 0 12 1 2 393.53 850781.25 July 0 AP44/ Benighat Bhim,Udaya, Keshara 1 9 10 0 1 1 0 39.75 218750 July 0 Rorang 42 AP44/ Benighat Bhim,Udaya, Keshara 1 9 13 0 9 1 0 294.15 218750 July 0 Rorang AP44A Benighat 43 Tilak Ba. Malla Thakuri 1 9 3 1 4 3 0 659.79 1296875 July /0 Rorang AP46B Benighat 44 Dhan Kumari Saudi 1 9 172 0 10 1 3 331.92 652343.75 July /0 Rorang AP47A Benighat Om Pd. Shrestha 1 10 11 1 0 2 2 528.62 1039062.5 July /0 Rorang 45 AP47A Benighat Om Pd. Shrestha 1 1 10 113 0 0 0 2 3.98 7812.5 July /0 Rorang AP21I/ Shyam L Shrestha(Anila Galchhi 1 4 283 0 12 1 0 389.55 995312.5 July 0 Rana) RM 46 AP21I/ Shyam L Shrestha(Anila Galchhi 1 1 4 282 0 0 0 1 1.99 5078.13 July 0 Rana) RM AP24/ Krishna Giri 1 Siddha Lek 7 30 0 0 3 1 25.84 66015 July 0 47 AP24/ Krishna Giri 1 Siddha Lek 7 346 0 13 2 2 433.28 1107031.25 July 0 AP24D 48 Aannada Adhikari 1 Siddha Lek 7 502 0 14 3 1 471.04 1203515.63 July /3 AP24F 49 Purna Lal Shrestha 1 1 Siddha Lek 7 179 0 4 2 0 143.10 323437.5 July /0 AP24F 50 Bhawa Nath Bhatta 1 Siddha Lek 7 183 0 13 0 0 413.40 934375 July /0 51 33B/1 Ramesh Prasad Pandey 1 Siddha Lek 4 238 0 10 1 1 327.94 708984.38 July AP2C/ 52 Sarada Baral 1 Dhunibesi 9 434 0 3 3 0 119.25 281250 July 0 AP5A/ 53 Sanu Babu Upreti 1 Dhunibesi 7 110 0 15 2 0 492.90 1162500 July 0 AP6A/ 54 Aambar Ba.Upreti 1 Dhunibesi 7 87 0 4 2 2 147.08 346875 July 0 AP7A/ 55 Danda Prasad Upreti 1 Dhunibesi 6 202 0 11 3 0 373.65 881250 July 0 AP 56 Jagat Ba. Upreti 1 Dhunibesi 6 183 0 8 3 0 278.25 656250 July 7B/0 AP 57 Hari Maya Tiwari 1 Dhunibesi 6 203 0 6 0 0 190.80 450000 July 7B/0 AP7C/ 58 Krishna Ba. Khatri 1 1 Dhunibesi 6 10 0 4 3 2 155.03 365625 July 0 AP7C/ Bishnu Prasad Upreti 1 Dhunibesi 6 15 0 7 1 0 230.55 543750 July 0 59 AP7C/ Bishnu Prasad Upreti 1 Dhunibesi 6 16 0 3 2 0 111.30 262500 July 0 AP 60 Krishna Prasad.Koirala 1 Dhunibesi 6 103 0 3 2 0 111.30 229687.5 July 7D/0 AP7E/ 61 Kaili Lama 1 1 Dhunibesi 6 22 0 2 0 3 69.57 164062.5 July 0 AP 62 Keshab Basnet 1 Dhunibesi 6 23 1 2 3 0 596.19 1406250 July 7E/0 63 AP8/1 Ram Chandra Thapa 1 1 Thakre RM 8 406 0 3 2 1 113.29 278320.31 July Bharat Dangol(Deb 64 AP 9/0 1 1 Thakre RM 8 143 1 0 3 0 532.59 1256250 July Singh Dongol) AP10/ 65 Siddhi Ba.Adhikari 1 Thakre RM 9 357 0 5 2 0 174.90 412500 July 0 AP13A 66 Nani Ram Dongol 1 1 Thakre RM 10 13 0 12 2 1 399.49 942187.5 July /0 AP13B 67 Arjun Tamang 1 1 Thakre RM 10 199 0 7 3 0 246.45 581250 July /0 AP13B 68 Raj Kumar Tamang 1 1 Thakre RM 10 200 0 7 0 1 224.59 529687.5 July /0 69 14A/0 Asta Man Lama 1 1 Thakre RM 45 0 10 2 2 337.88 796875 July AP17A 70 Som Bdr Shrestha 1 1 Thakre RM 11 14 0 0 1 1 9.94 20507.81 July /0 25 3 Sub Total 16 2 1 0 1 47 5 81 11402.08 26042771.95 6 7 71 AP7/0 Bishnu Prasad Upreti 1 Dhunibesi 6 83 0 0 2 3 21.87 51562.5 August 72 AP7/0 Laxmi Thapa Magar 1 1 Dhunibesi 6 84 0 0 1 1 9.94 18750 August 73 AP8/2 Shyam Ba. Khadka 1 Thakre Rm 8 234 0 6 2 0 206.7 487500 August AP10/ Bhakta K Adhikari(Lila 74 1 Thakre Rm 9 73 0 6 1 2 202.73 478125 August 0 Nath Adhikari) AP10/ 75 Ram Kumar Adhikari 1 Thakre Rm 9 356 0 3 2 1 113.29 267187.5 August 0 AP10/ 76 Purnda Ba. Bhandari 1 Thakre Rm 9 75 0 13 0 0 413.4 975000 August 0 AP12A 77 Anad Kumar koirala 1 Thakre Rm 9 52 0 13 2 0 429.3 1012500 August /0 AP Krishna Ba. Lama/Thuli 1 1 Thakre RM 11 29 0 12 3 1 407.44 960937.5 August 16B/0 Lama 78 AP16B Krishna Ba. Lama/Thuli 1 Thakre RM 11 30 0 3 1 3 109.32 225585.94 August /0 Lama AP19C Galchhi 79 Bhim Pd. Khatiwada 1 8 4 1 2 2 0 588.24 1618750 August /0 RM AP31A Dambar Bahadur Siddha 80 1 1 4 16 0 2 2 0 79.5 218750 August /0 Gurung Lake AP33A Siddha 81 Prem Nath Sedai 1 3 123 0 2 3 3 93.42 201953.13 August /0 Lake AP33A Siddha 82 Dhruba Prasad Sedai 1 3 257 0 3 2 3 117.27 253515.63 August /0 Lake AP46/ Benighat 83 Dor Ba. Shrestha 1 1 10 120 0 11 2 0 365.7 695312.5 August 1 Ror- AP21H Galchhi 84 Kana Ba. Shrestha 1 1 4 295 0 2 3 0 87.45 206250 August /0 RM AP23A Siddha 85 Khema Kumari Dhakal 1 7 124 0 5 2 0 174.9 446875 August /0 Lake AP24D Siddha 86 Laxmi Giri 1 7 45 0 4 3 0 151.05 341406.25 August /2 Lake AP24D Siddha Yek Kumar Sedai 1 7 167 0 0 1 2 11.93 30468.75 August /2 Lake 87 AP24D Siddha Yek Kumar Sedai 1 7 171 0 0 2 0 15.9 40625 August /2 Lake AP24D Siddha 88 Bhoj Raj Sedai 1 7 169 0 5 2 0 174.9 446875 August /2 Lake AP24D Siddha 89 Som Natha Sedai 1 7 170 0 6 3 2 218.63 558593.75 August /2 Lake Sub Total 5 21 3992.88 9536523.45 AP10/ Septe 90 Ranga Nath Adhikari 1 Thakre Rm 9 72 0 0 1 0 7.95 18750 0 mber AP25B Ram Maya Bhujel(Jana Siddha Septe 91 1 1 7 118 0 7 1 2 230.19 530078.13 /0 Bahadur Bhujel) Lake mber AP25B Hasta B Bhujel(Bhadra Siddha Septe 92 1 1 7 120 0 7 2 0 234.16 609375 /0 Kumari Ghatri) Lake mber AP32/ Siddha Septe 93 Lila Nath Tripathi 1 4 137 0 10 3 1 337.64 946093.75 0 Lake mber AP44/ Benighat Septe 94 Bhakta Ba. Malla 1 9 12 0 10 0 1 313.79 628906.25 0 Ror- mber AP24/ Siddha Septe 95 Pampha Devi Dhakal 1 7 31 0 1 3 2 59.01 101562.5 0 Lake mber Sub Total 2 0 0 0 0 6 0 35 10 6 1182.74 2834765.63 349/ Octobe 96 AP3/0 Prasant Khadka 1 Dhunibesi 9 0 0 0 3 5.97 230850 512 r 349/ Octobe 97 AP3/0 Ananda Kumar Agrawal 9 0 12 0 2 385.58 230859 512 r 349/ Octobe 98 AP3/0 Rita Agrawal 9 230859 512 r 349/ Octobe 99 AP3/0 Nanda Kishor Gupta 1 230859 512 r Octobe 100 AP5/0 Kaji Babu.Shrestha 1 Dhunibesi 7 32 1 0 0 0 508.74 1170112 r AP5B/ Octobe 101 Krishna prasad Upreti 1 Dhunibesi 7 459 0 6 3 3 220.62 515625 0 r AP5B/ Octobe 102 Gagan Upreti 1 Dhunibesi 7 460 0 8 2 1 272.29 642187.5 0 r AP5B/ Octobe 103 Binod Upreti 1 Dhunibesi 7 461 0 0 2 1 17.89 42187.5 0 r AP11B Octobe 104 Keshav Prasad Subedi 1 Thakre Rm 9 242 1 2 0 0 572.34 1316615 /0 r AP12/ Octobe 105 Thakur Nath Pandit 1 Thakre Rm 9 401 0 2 0 3 69.57 164062.5 0 r AP12/ Octobe 106 Thakur Nath Pandit 1 Thakre Rm 9 403 0 4 2 1 145.09 342187.5 0 r AP17A Octobe 107 Gopi Lal Shrestha 1 Thakre RM 11 40 0 4 1 2 139.13 341796.88 /0 r AP17A Octobe Gopi Lal Shrestha Thakre RM 11 41 0 7 3 0 246.45 605468.75 /0 r AP31/ Siddha Octobe 108 Tika Prasad Silwal 1 4 61 1 0 1 0 516.69 1089410.16 2 Lake r AP31A Siddha Octobe 109 Tek Bahadur Silwal 1 4 239 0 0 1 0 7.95 21885 /0 Lake r AP32/ Siddha Octobe 110 Indra Kumari Tripathi 1 4 207 0 0 3 0 23.85 65625 0 Lake r AP32/ Siddha Octobe 111 Subba Tripathi 1 4 206 0 1 0 0 31.8 87500 0 Lake r Sub Total 0 14 3163.96 7328089.79 AP Novem 112 Guru Pd. Pandey 1 Thakre Rm 9 159 0 0 3 1 25.84 60937.5 11A/0 ber AP19C Galchhi Novem 113 Trilok Ba.Magar 1 1 8 12 0 0 1 0 7.95 21875 /0 RM ber AP26A Siddha Novem 114 Bishnu Koirala/Sarki 1 1 6 27 0 1 1 2 43.11 111718.75 /0 Lake ber AP33B Siddha Novem 115 Khun prasad Sedai 1 3 117 0 0 1 3 13.92 30078.13 /0 Lake ber AP37/ Benighat Novem 116 Bhola Bisural 1 5 36 0 5 0 2 159.88 738281.25 0 Ror- ber Sub Total 1 0 1 0 0 5 250.7 962890.63 AP37/ Benighat Decem 117 Teka Bahadur Bisural 1 5 400 0 6 3 3 216.9 910546.88 0 Ror- ber Siddha Decem 118 33B/1 Dibya Kanta Sedai 1 4 31 0 5 0 3 161.87 356640 Lake ber Sub Total 0 0 0 0 0 2 378.77 1267186.88 Total 36 2 4 1 1 128 30481.45 71426150.82

Compensation Distribution for land acquired in Chitwan-MKTLP

S Tower Targeted Received N Address Name of Aps Number Amount (NRs.) Status

1 AP 50 Ikchhchhakamana-3 Prithivi Gurung 820000.00 Received

2 AP51/0 Ikchhchhakamana-3 Dhanikala Gurung 340000.00 Received 3 AP51/0 Ikchhchhakamana-3 Harimaya Gurung 1470000.00 Received 4 AP51/0 Ikchhchhakamana-3 Sanbahadur Gurung 60000.00 Received 5 AP52B Ikchhchhakamana-3 Dipakraj Poudel 750000.00 Received 6 AP52B Ikchhchhakamana-3 Ramchandra Lamichane 830000.00 Received 7 AP54A Ikchhchhakamana-3 Uttam Gurung 1420000.00 Received

8 AP54A Ikchhchhakamana-3 Om Gurung 100000.00 Received

9 AP59/0 Ikchhchhakamana-4 Lekhbahadur Thapa 406250.00 Received 10 AP59/0 Ikchhchhakamana-4 SombahadurThapa 446875.00 Received 11 AP59/0 Ikchhchhakamana-4 Khilbahadur Thapa 146250.00 Received 12 AP 52 Ikchhchhakamana-3 Sukmaya Gurung 1023750.00 Received 13 AP 50A Ikchhchhakamana-3 Suryabahadur Gurung 460000.00 Received 14 AP 50A Ikchhchhakamana-3 Dhan Bahadur Gurung 270000.00 Received 15 AP51A Ikchhchhakamana-3 Narbahadur Gurung 1447800.00 Received 16 AP57 Ikchhchhakamana-4 Serbahadur Parja 804375.00 Received 17 APAP50A Ikchhchhakamana-3 Chepti Gurung 920000.00 Received Total Amount 11715300.00

Compensation Distribution for land acquired in Gorkha-MKTLP

Compensation Distribution Status in Shahidlakhan RM, Gorkha District, MKTLP

S.N Address Compensation Tower Number AP Name Status Present Former Sahid Manakamana- 1 69/ADDO Lakhan RM Tam Bahadur Thapa Distributed 6 -3 Sahid Manakamana- 2 69/ADDO Lakhan RM Buddhi bal Thapa Distributed 6 -3 Sahid Manakamana- 3 GMT Lakhan RM Rikta Bahadur Thapa In process 6 -3 Sahid Manakamana- 4 69/1DDO Lakhan RM Thakur Thapa Distributed 6 -3 Sahid Manakamana- 5 69DD9 Lakhan RM Mangal sing Thapa Distributed 6 -3 Sahid Manakamana- 6 69DD10 Lakhan RM Nar bahadur Gyami Distributed 6 -3 Sahid Manakamana- 7 68DD9 Lakhan RM Yugananda Koirela Distributed 6 -3 Sahid Manakamana- 8 68DD9 Lakhan RM Rameshwor Pokheral Distributed 6 -3 Sahid Manakamana- Narayan Prasad 9 68DD9 Lakhan RM Distributed 6 Pokheral -3 Sahid Manakamana- 10 67ADBO Lakhan RM Kali Aamaghai Distributed 6 -3 Sahid Manakamana- 11 67ADBO Lakhan RM Kabidatta Aryal Distributed 6 -3 Sahid Manakamana- 12 66DDO Lakhan RM Setimaya Gurung Distributed 7 -3 Sahid Manakamana- 13 65/BDC3 Lakhan RM Mahabir Gurung Distributed 7 -3 Sahid Manakamana- 14 65/BDC3 Lakhan RM Chandra Bhadur Magar Distributed 7 -3 Sahid Manakamana- Man Bahadur Thapa 15 65/BDC3 Lakhan RM Distributed 7 Magar -3 Sahid Manakamana- 16 64DD9 Lakhan RM Khadka Bahadur Thapa Distributed 8 -3 Sahid Manakamana- 17 64DD9 Lakhan RM Tek Bahadur Thapa Distributed 8 -3 S.N Address Compensation Tower Number AP Name Status Present Former Sahid Manakamana- 18 64DD9 Lakhan RM Thaman Bahadur Thapa Distributed 8 -3 Sahid Manakamana- 19 64DD9 Lakhan RM Tek Bahadur Thapa Distributed 8 -3 Sahid Manakamana- 20 63DC0 Lakhan RM Chandra bahadur Thapa Distributed 8 -3 Sahid Manakamana- 21 63DC0 Lakhan RM Lil Bahadur Thapa Distributed 8 -3 Sahid Manakamana- 22 63DC0 Lakhan RM Ran Bahadur Thapa Distributed 8 -3 Sahid Manakamana- 23 63DC0 Lakhan RM Ram Bahadur Thapa In process 8 -3 Sahid Manakamana- 24 63DC0 Lakhan RM Gyan Bahadur Thapa Distributed 8 -3 Sahid Manakamana- 25 63DC0 Lakhan RM Kaman shing Thapa Distributed 8 -3 Sahid Manakamana- 26 63DC0 Lakhan RM Kul Bahadur Thapa Distributed 8 -3 Sahid Manakamana- 27 63DC0 Lakhan RM Hasta Bir Thapa Distributed 8 -3 Sahid Manakamana- 28 62DB9 Lakhan RM Nar bahadur Thapa Distributed 8 -3 Sahid Manakamana- 29 62DB9 Lakhan RM Indra bahadur Thapa Distributed 8 -3 Sahid Manakamana- 30 62DB9 Lakhan RM Ekman Thapa Magar Distributed 8 -3 Sahid Manakamana- 31 62DB9 Lakhan RM Suk bahadur Thapa Distributed 8 -3 Sahid Manakamana- 32 61/BDB6 Lakhan RM Hasta Bahadur Gurung Distributed 8 -3 Sahid Manakamana- 33 61/BDB6 Lakhan RM Gaj Bahadur Gurung Distributed 8 -3 Sahid Manakamana- 34 61/BDB6 Lakhan RM Non-Title Holder 678 8 -3 Sahid Manakamana- 35 61/ADB3 Lakhan RM Non-Title Holder 705 8 -3 36 61/ADB3 Sahid Manakamana- Buddhiman Gurung Distributed S.N Address Compensation Tower Number AP Name Status Present Former Lakhan RM 8 -3 Sahid Manakamana- 37 61/ADB3 Lakhan RM Chitra Bahadur Gurung Distributed 8 -3 Sahid Manakamana- 38 61/1DB6 Lakhan RM Dal Bahadur Gurung Distributed 8 -3 Sahid Manakamana- 39 61/1DB6 Lakhan RM Keshar sing Gurung Distributed 8 -3 Sahid Manakamana- 40 61BDO Lakhan RM Ishor Shrestha Distributed 8 -3 Sahid Manakamana- 41 61BDO Lakhan RM Non-Title Holder 756 8 -3 Sahid Manakamana- 42 61BDO Lakhan RM Khilman Shrestha Distributed 8 -3 Sahid Manakamana- 43 61BDO Lakhan RM Chet Bahadur Thapa Distributed 8 -3 Sahid Manakamana- 44 60/ADDO Lakhan RM Purnalal shrestha Distributed 8 -3 Sahid Manakamana- 45 60/ADDO Lakhan RM Bhim bahadur Thapa Distributed 8 -3 Sahid Manakamana- 46 60/ADDO Lakhan RM Krishna Babu Shrestha Distributed 8 -3

Compensation Distribution Status in Gandaki RM, Gorkha District, MKTLP

Address Compensation SN Tower Name AP Name Status Present Former 1 35/ADD0 Gandaki RM-7 Ghyalchowk 9 Shiva Bahadur Majhi Distributed 2 35/ADD0 Gandaki RM-7 Ghyalchowk 9 Non Tital Holder 3 37/BDB12 Gandaki RM-7 Ghyalchowk 9 Santa bahadur Dabadi Distributed 4 37/BDB12 Gandaki RM-7 Ghyalchowk 9 Dhakalman Shrestha Distributed 5 37/BDB12 Gandaki RM-7 Ghyalchowk 9 Ambar Bahadur Khadka Distributed 6 37/CDB12 Gandaki RM-7 Ghyalchowk 9 Dipendra Khadka Distributed 7 37/CDB12 Gandaki RM-7 Ghyalchowk 9 Dilnath Adhikari Distributed 8 37/CDB12 Gandaki RM-7 Ghyalchowk 9 Dilnath Adhikari Distributed 9 37/CDB12 Gandaki RM-7 Ghyalchowk 9 Dilnath Adhikari Distributed 10 37/DDB0 Gandaki RM-7 Ghyalchowk 9 In Kumari Regmi Distributed 11 37/DDB0 Gandaki RM-7 Ghyalchowk 9 Non Tital Holder 12 38DB0 Gandaki RM-7 Ghyalchowk 9 Ganga Bahadur Bhujel Distributed 13 38DB0 Gandaki RM-7 Ghyalchowk 9 Kulman Shrestha Distributed 14 38/1DB3 Gandaki RM-7 Ghyalchowk 9 Chanamati Sarkeni Distributed 15 38/1DB3 Gandaki RM-7 Ghyalchowk 9 Dal Narayan Shrestha Distributed 16 38/ADB9 Gandaki RM-7 Ghyalchowk 9 Lok Bahadur Ranamagar Distributed 17 38/ADB9 Gandaki RM-7 Ghyalchowk 9 Chanamaya Sharki Distributed 18 38/BDB0 Gandaki RM-8 Ghyalchowk 5 Purna Prasad Poudel Distributed 19 38/BDB0 Gandaki RM-8 Ghyalchowk 5 Purna Prasad Poudel Distributed 20 39DB0 Gandaki RM-8 Ghyalchowk 5 Yog Kumari Regmi Distributed 21 39DB0 Gandaki RM-8 Ghyalchowk 5 Pusparaj Rej Regmi Distributed 22 39DB0 Gandaki RM-8 Ghyalchowk 5 Mishra Regmi In Process 23 39DB0 Gandaki RM-8 Ghyalchowk 5 Non Tital Holder 24 39/ADBO Gandaki RM-8 Ghyalchowk 5 Bimaya Ranamagar Distributed 25 39/ADBO Gandaki RM-8 Ghyalchowk 5 Hit Bahadur Ranamagar Distributed 26 4QDB3 Gandaki RM-8 Ghyalchowk 5 Lalimaya BK Kami Distributed 27 4QDB3 Gandaki RM-8 Ghyalchowk 5 Non Tital Holder 28 40/ADB9 Gandaki RM-8 Ghyalchowk 5 Bhup Bahadur Bhattarai Distributed 29 40/ADB9 Gandaki RM-8 Ghyalchowk 5 Resam Bahadur Bhattarai Distributed 30 40/ADB9 Gandaki RM-8 Ghyalchowk 5 Rohini Kumari Chaapagai Distributed 31 42DD0 Gandaki RM-8 Ghyalchowk 5 Gagendar Prasad Regmi Distributed 32 43DB0 Gandaki RM-8 Ghyalchowk 5 Ishwor Prasad Regmi Distributed 33 43DB0 Gandaki RM-8 Ghyalchowk 5 Praksah Babu Regmi Distributed 34 43BDD0 Gandaki RM-8 Ghyalchowk 5 Govinda Prasad Regmi Distributed 35 43BDD0 Gandaki RM-8 Ghyalchowk 5 Sushila Regmi Distributed 36 43BDD0 Gandaki RM-8 Ghyalchowk 5 Bhubaneshwor Regmi In Process

Compensation Distribution Status in Gorkha , Gorkha District, MKTLP

Tower Number Address AP Name Compensation S.N status Present Former Gorkha 1 74/2DBO Deurali -4 Krishna Bahadur Sunar Distributed Municipality -14 Gorkha 2 74/2DBO Deurali -4 Padm bahadur Sunar In Process Municipality -14 Gorkha 3 74/2DBO Deurali -4 Kheme Kami Distributed Municipality -14 Gorkha 4 74/2DBO Deurali -4 Non-Title Holder 474 Municipality -14 Gorkha 5 74/2DBO Deurali -4 Non-Title Holder 476 Municipality -14 Gorkha 6 74/1DB1.5 Deurali -4 Dhak Bahadur Bk Distributed Municipality -14 Gorkha 7 74/1DB1.5 Deurali -4 Maite BK Distributed Municipality -14 Gorkha 8 74/1DB1.5 Deurali -4 Mangal Bahadur BK Distributed Municipality -14 Gorkha 9 74DB9 Deurali -4 Lila Bahadur Karki Distributed Municipality -14 Gorkha 10 73/ADBO Deurali -4 Maiya Karakheti Distributed Municipality -14 Gorkha 11 73/ADBO Deurali -4 Non-Title Holder 239 Municipality -14 Gorkha 12 72/ADBO Deurali -7 Bhim Kumari Mahat Distributed Municipality -13 Gorkha 13 72/ADBO Deurali -7 Man Kumari Pulami Distributed Municipality -13 Gorkha 14 72/ADBO Deurali -7 Rishiram Khanal Distributed Municipality -13 Gorkha 15 72DD3 Deurali -7 Sudama Pandey Distributed Municipality -13

Details of Compensation Distribution in Chitwan District -MKTLP

Details of Compensation Distribution at MKTLP,-in Gorkha district

Land acquisition notice of Kathmandu district-MKTLP

Annexure 5

Details of Compensation Distribution for Structure Loss

DKTLP

Finalized Compensation by CDC for structure in Myagdi District

S.N. Land Owner’s Name Address Tower No. Received Amount

1 Dalfi Ramjali Annapurna 1 40 A 501608 2 Tek Bahadur Karki Raghuganga 3 29 2000211 3 Dudh Bahadur Purja Raghuganga 2 35 C 937500 4 Dhan Kumari Bhandari Raghuganga-2 32 1167211 Total 4606530

Compensation Distribution for structure loss at Parbat -DKTLP

S.N. Land Owner’s Name Address Tower No. Received Amount

1 Tike Damai Budhi Nepali Jaljala-8 10 61425 2 Sarala Padhyaya Jaljala-8 7A 838148 3 Gorkha Bahadur Karki Jaljala-2 24 A 1505117 Total 2404690

MKTLP

Finalized Compensation by CDC for structure in Dhading District

Name of Total Angle S.N official land Address Property Compensation point owner Target Amount

Aaru Bote, Tin Shade 241635.31 Dhunibesi-7 Guna Raj 1 6A/0 Cow Tin Shade 103382.35 Upreti Cow Tin Shade 35411.11 Sub Total 380428.77 Aaru Bote, Tin Shade 35651.81 Ambar Dhunibesi-7 2 6A/0 Bahadur Stone Masonry Toilet 46685.45 Uprety Sub Total 82337.26 Waibatol- Tin Shade 189907.82 Shankar Dhunibesi-6 3 7D/2 Tamang Cow Tin Shade 45566.37 Sub Total 235474.19 Waibatol- Saraswoti Tin Shade 154011.48 4 7D/2 Dhunibesi-6 Tamang Sub Total 154011.48 Waibatol- Tin Shade 204540.81 Ram Dhunibesi-6 5 7D/2 Bahadur Tamang Stone Masonry Toilet 54030.77 Sub Total 258571.58 Waibatol- Tin Shade 157573.22 Subba Dhunibesi-6 6 7D/2 Tamang Cow Tin Shade 37319.36 Sub Total 194892.58 Roshan Waibatol- Tin Shade 221477.2 7 7D/2 Tamang Dhunibesi-6 Sub Total 221477.2 Arjun Tamang / Thakre-10 Tin Shade 109965.59 8 13B/0 Raj Kumar

Tamang Sub Total 109965.59 Siddhalek- Ram Sharan Tin cow Shade 100630.77 9 24/0 7,Adamtar Giri Sub Total 100630.77

Sunrise Dhunibesi-9 Poultry Truss Works 3111559.17 10 3/0 Breeding Egg Collection Centre 114605.2 Center Sub Total 3226164.37 Benighat Khar Shed 17974.78 Rorang-10 Rajesh 11 47C/0 CGI Sheet Shed 42505.43 Chepang Khar Shed 1 29438.44 Sub Total 89918.65 Total 5053872.44

Details of Compensation Distribution for Structure Loss in Dhading District

Total Total Angle Name of official land Compensation SN Address Property Compensated Remarks point owner Target Amount Amount

Dhunibesi- Poultry Truss Works 3111559.17 Sunrise Breeding 9 1 3/0 Center 1613000 Egg Collection Centre 114605.2 Arjun Tamang / 2 13B/0 Thakre-10 Tin Shade 109965.59 109965.59 Raj Kumar Tamang Siddhalek- 3 24/0 Ram Sharan Giri Tin cow Shade 100630.77 100630.77 7,Adamtar Benighat Khar Shed 17974.78 Rorang-10 4 47C/0 Rajesh Chepang 89918.64 CGI Sheet Shed 42505.43 Khar Shed 1 29438.44

Aaru Bote, Tin Shade 35651.81 5 6A/0 Ambar Bahadur Upreti Dhunibesi- 82337.26 7 Stone Masonry Toilet 46685.45

1,995,852.26 Total

Details of APs for Structure Loss in Chitwan District

SN. House Owner Section House Details Address 1 Prem Bahadur Magar AP 59 to AP 58C Hut 1 Ichchhakaman -4 2 Fullmaya Chepang AP 55 to AP 54C House 1 Ichchhakaman -4 3 Kumar Chepang AP 55 to AP 54C House 2, Hut 1 Ichchhakaman -4 4 Santa Bahadur Chepang AP 55 to AP 54C House 1 Ichchhakaman -4 5 Fullmaya Chepang AP 54C House 2, Toilet 1 Ichchhakaman -4 6 Om Gurung AP 54A to AP 54 House 1, Hut 1 Ichchhakaman -4 7 Ramchandra Lamichane AP 53 to AP 52B Hut 1, Ichchhakaman -4

House 1, Hut 2, 8 Kamal Bdr. Gurung AP 51A to AP 51 Ichchhakaman -3 Toilet 1,

House 1, Hut 3, 9 Harimaya Gurung AP 51 to AP 50A Ichchhakaman -3 Toilet 1,

10 Surya Bahadur Gurung AP 50A to AP 50 Hut 1 Ichchhakaman -3 11 Min Bahadur Gurung AP 59 to AP 49B Hut 3 Ichchhakaman -3

Details of Compensation Distribution for Structure loss in Gorkha District

Name of official land Total Compensated SN Angle Point Address owner Amount Gyalchowk-5, Gandaki 1 AP 40/0 Lalimaya BK 458,077.11 Rural Municipality, Gorkha Sahidlakhan Rural 2 AP 61 Gaj Bahadur Gurung 235,175.51 Municipality, Gorkha Total 693,252.62

Annexure 6

Details of Compensation Distribution for Crop Loss

DKTLP

Myagdi District

Received S.N. Name Address Remarks Amount 1 Diwakar Subedi Kusma-1 2474.28 2 Kashi Ram Subedi Kusma-1 1592.64 3 Tika Kumari Malla Jaljala-4 5771.82 4 Purna Kumari Malla Jaljala-4 19283.13 5 Hira Kumari Malla Jaljala-4 6733.79 6 Hari Bahadur GC Jaljala-4 5063 Nand Kumari /Tirth Kumari 7 Jaljala-4 3724.04 Malla Resham Bahadur 8 Jaljala-4 15373.62 Hamal(Putali Hamal) Nar Bahadur Hamal (Putali 9 Jaljala-4 3088.43 Hamal) 10 Dhan Kumari Bhandari Raghuganga-2 30580.08 11 Purna Kumari Malla Jaljala-4 10568.3 12 Ashok Malla Jaljala-4 15867.82 13 Chandra Bahadur Malla Jaljala-4 32417.74 Nar Bahadur Hamal(Lok 14 Jaljala-4 13416.95 Bahadur Hamal) Nar Bahadur Hamal(Indra 15 Jaljala-4 12505.61 Bahadur Malla) 16 Chandra Bahadur Malla Jaljala-4 16594.86 17 Arjun Bahadur Malla Jaljala-4 22175.94 18 Tirth Bahadur Malla Jaljala-4 32621.43 19 Karn Bahadur KC Jaljala-3 7330.82 20 Lal Bahadur Thapa Jaljala-3 7120.87 21 Durga Bahadur Sharki Jaljala-3 8731.72 22 Baghbir Damai Jaljala-3 9481.71 23 Durge Damai Jaljala-3 6542.39 24 Seti Baruwal Jaljala-2 12850.62 25 Baghbir Damai Jaljala-2 405.32 26 Balbir Darji Jaljala-2 1727.24 27 Bam Bahadur Biswakarma Jaljala-2 2715.15 28 Bam Bahadur Biswakarma Jaljala-2 1652.07 29 Chakra Bahadur Kami Jaljala-2 6338.01 30 Tug Bahadur Malla Raghuganga-3 25640.72 Plot no.72 31 Tug Bahadur Malla Raghuganga-3 45787.29 Plot no.134 32 Dil KUmari KC Raghuganga-2 8462.40 33 Tika Bahadur KC Raghuganga-2 1556.84 34 Taranath Padhya Jaljala-8 11561.85 AP 7 A 35 Atma Hari KC Jaljala-8 6566.00 AP 6 36 Gajendra Bahadur Khatri Jaljala-8 7182.00 AP 6 37 Baburam KC Jaljala-8 7064.00 AP 6 38 Parshuram KC Jaljala-8 14636.00 AP 6 39 Hark Bahadur Chhetri Jaljala-8 426.8 AP 6 40 Kamal Prasad Regmi Jaljala-8 118000.00 AP 7 41 Tek Bahadur Karki Raghuganga -3 12104.02 AP 29 42 Guma Kumari Baruwal Jaljala-2 3233.00 Plot no.705/708 43 Bam Bahadur BK Jaljala-2 11222.58 Plot no.706/707 44 Chandra Bahadur Baruwal Jaljala-2 8405.46 Plot no.709 45 Man Kumari Upadhyaya Jaljala-7 13937.52 Plot no.81 46 Durga Dutta Upadhyaya Jaljala-7 2587.74 Plot no.377 47 Jamuna Acharya Jaljala-7 2587.74 Plot no.343 TOTAL 615711.35

Parbat District (in October, 2018)

Total Angle Foundation/ Name of official land S.N Address Compensation point Erection owner Amount 1 24 Erection Guma Kumari Baruwal Jaljala-2 3,233/46 2 22 Foundation Bam Bahadur BK Jaljala-2 11,222/58 3 24 Erection Chandra Bahadur Baruwal Jaljala-2 8,405/46 4 13 Erection Man Kumari Upadhyaya Jaljala-7 13,937/52 5 15 Erection Durga Datta Upadhyaya Jaljala-7 2,587/74 6 15 Erection Jamuna Acharya Jaljala-7 2,587/74 Total 41,974.50

Details of the compensation distribution for tree loss in DKTLP

Myagdi (In August, 2018)

Received S.N. Name Address Remarks Amount 1 Durga Dutta Upadhyaya Jaljala-7 20706.84 AP 15

Details of Compensation Distribution for Crop Loss

MKTLP:

Dhading District

Foundation Total S. Angle Name of official land / Address Compensate N point owner Erection d Amount 33/0 Erection Ram Pd Sedhai Siddhalek-3 43500 1 33/0 Erection Ram Pd Sedhai Siddhalek-3 17400 33/0 Erection Ram Pd Sedhai Siddhalek-3 22250 48/0 Foundation Maniraj Ghale Jogimara -3 297000 2 48/0 Foundation Maniraj Ghale Jogimara -3 48060 3 48/0 Foundation Sari Ghale Benighat - 3 13050 4 34A/1 Foundation Yeka Ba. Magar Salang -5 10930 5 34A/0 Foundation Yeka Ba. magar Jogimara-6 11712 6 35/0 Foundation Dip Ba.Magar Salang -6 16800 7 44/0 Foundation Hita Ba. Malla Jogimara -9 6336 8 34/0 Erection Mohan Lal Thapamar Siddhalek-4 22500 9 33A Erection Umakanta Sedhai Siddhalek-3 23887.5 33/0 Erection Khun Pd. Sedhai Siddhalek-3 27300 10 33/0 Erection Khun Pd. Sedhai Siddhalek-3 13750

33B/0 Foundation Khun Pd. Sedhai Salang -5 22932 11 33/0 Erection Ramsaran Sedhai Siddhalek-3 16312.5 33/0 Erection Ramsaran Sedhai Siddhalek-3 11375 33/0 Erection Ramsaran Sedhai Siddhalek-3 26700 12 33A Foundation Umakanta Sedhai Siddhalek-3 22500 31A/0 Foundation Subbha Pd. Trpathi Siddhalek-4 6125 13 31A/0 Foundation Subbha Pd. Trpathi Siddhalek-4 11250

31A/0 Foundation Subba Pd. Trpathi Siddhalek-4 11250 14 31A/0 Foundation Man Ba. Majhi Kalleri -2 32760 15 33/0 Erection Rebati Pd. Sedhai Siddhalek-3 26100 16 44A/0 Foundation Bhakta Ba. Malla Jogimara -9 6600 44A/0 Foundation Bhakta Ba. Malla Jogimara -9 4824 17 21/1/1 Erection Bhim Ba.Dhungana Galchhi- 1 9520 21/1/1 Erection Bhim Ba.Dhungana Galchhi- 1 20100 8/0 Erection Bishnu Tamang Thakre -9 4422.6 18 8/0 Erection Bishnu Tamang Thakre -9 1449 46/0 Foundation Buddhi Lal Shrestha Jogimara -10 3120 19 46/0 Foundation Buddhi Lal Shrestha Jogimara -10 20025 20 30A/0 Foundation Damber Ba. Gurung Siddhalek -6 997.5 7/0 Foundation Ganga Pd. Rijal Naubise- 9 2000 21 7/0 Foundation Ganga Pd. Rijal Naubise- 9 2250 7/0 Foundation Ganga Pd. Rijal Naubise- 9 5500 7/0 Foundation Ganga Pd. Rijal Naubise- 9 50000

7/0 Foundation Ganga Pd. Rijal Naubise- 9 16000 Foundation Total S. Angle Name of official land / Address Compensate N point owner Erection d Amount 25B/0 Foundation Hasta Ba. Bhujel Kumpur-7 14418 22 25B/0 Foundation Hasta Ba. Bhujel Kumpur-7 10647 7E/0 Foundation Kaili Lama Naubise -1 605.15 23 7E/0 Foundation Kaili Lama Naubise -1 1245 8/0 Foundation Kalpana Lama Thakre -9 840 8/0 Foundation Kalpana Lama Thakre -9 1037.5 24 8/0 Erection Kalpana Tamang Thakre -9 4422.6 8/0 Erection Kalpana Tamang Thakre -9 3061.8 8A/0 Foundation Kul Ba. Thapa Thakre -9 4704 8A/0 Foundation Kul Ba. Thapa Thakre -9 1078.7 25 8A/0 Erection Kul Ba.Thapa Thakre -8 166.25 8A/0 Erection Kul Ba.Thapa Thakre -8 179.55 8A/0 Erection Kul Ba.Thapa Thakre -8 159.6 20C/0 Foundation Manoj Gautam Goganpani- 1 5607 26 20C/0 Foundation Manoj Gautam Goganpani- 1 550 27 34/0 Erection Ram Pd Pande Siddhalek -3 3412.5 33/0 Erection Ramesh Pd Pande Siddhalek -6 3150 33/0 Erection Ramesh Pd Pande Siddhalek-3 1181.6

33/0 Erection Ramesh Pd Pande Siddhalek-3 1181.6 33B/1 Erection Ramesh Pd. Pande Siddhalek - 3 2310 28 8/1 Erection Ramesh Thapa Naubise - 1 3325 29 25B/0 Foundation Ram maya Bhujel Kumpur-7 6942 25B/0 Foundation Rammaya Bhujel Kumpur-7 4368 10/0 Foundation Siddhi Pd. Adhikari Kewalpur- 9 581.7 30 10/0 Foundation Siddhi Pd. Adhikari Kewalpur- 9 17622 34/0 Erection Sudip Sedhai Siddhalek -3 2992.5 31 34/0 Erection Sudip Sedhai Siddhalek -3 3412.5 33B/0 Foundation Sun Pd. Sedhai Salang -5 3660 32 33B/0 Foundation Sun Pd. Sedhai Salang -5 22932 33 32D/0 Foundation Tulimaya Magar Salang-6 3294 11/0 Foundation Tulsi Pd.Regmi Kewalpur -9 2573.55 11/0 Foundation Tulsi Pd.Regmi Kewalpur -9 3211.95 34 11/0 Foundation Tulsi Pd.Regmi Kewalpur -9 791.35 11/0 Foundation Tulsi Pd.Regmi Kewalpur -9 359.1 35 10/0 Foundation Bikash Acharya Kewalpur- 9 2154.6

17/0 Foundation Bishnu Bhujel Goganpani -8 2880 36 17/0 Foundation Bishnu Bhujel Goganpani -8 2523.6

31/2 Foundation Maya Nath Silwal Salang-7 1602 37 31/2 Foundation Maya Nath Silwal Salang-7 4352.4

38 17B/0 Foundation Ram Chandra Lama Goganpani- 6 1874.8 Foundation Total S. Angle Name of official land / Address Compensate N point owner Erection d Amount 17B/0 Foundation Ram Chandra Lama Goganpani -6 24000

17B/0 Foundation Ram Chandra Lama Goganpani -6 19000

39 10/0 Foundation Ram Kumar Adhikari Kewalpur- 9 1901.9

40 10/0 Foundation Sita Acharya Kewalpur- 9 791.35

41 10/0 Foundation Sita Acharya Kewalpur- 9 7610

42 8/2 Erection Mina Khadka Thakre-9 8675.7 43 8A/0 Foundation Kul Bahadur Thapa Thakre-9 5782 44 46/0 Foundation Buddhilal Shrestha Rorang-10 31660 45 44/0 Foundation Hit Bahadur Malla Rorang-9 9361 46 21/0 Erection Gitadatta Khatiwada Galchhi-1 3745 47 46/1 Erection Rupa Basnet Rorang-10 1820 48 46/0 Erection Kumar Rijal Roranh-10 2100 49 31B/1 Erection Bale Sarki Siddhalek-3 3500 50 31B/1 Erection Bimal Sarki Siddhalek-3 3500 51 7D/0 Foundation Laxmi Koirala Dhunibesi-6 1750 52 31B/1 Erection Purne sarki Siddhalek-3 1750 53 7A/0 Foundation Shyam Raja Thapa Dhunibesi-6 2765 54 46B Erection Kop Bahadur Saudi Rorang-10 15750 Dev Kumari Malla 55 44/0 Erection Rorang-10 7000 Thakuri 56 44A/0 Erection Sita Malla Rorang-10 15570 57 44A/0 Erection Suntali Malla Rorang-10 28625 58 31B/0 Erection Sita RamThapa Magar Siddhalek-3 7115 59 31B/1 Erection Shanker Prasad sedai Siddhalek-3 31500 60 34/1 Erection Khelu Nepali Siddhalek-3 6300 61 23A/0 Erection Sita Majhi Siddhalek-7 26260.5 62 23A/0 Foundation Khem Khumari Dhakal Siddhalek-7 12232.5 63 24/0 Foundation Krishna Giri Siddhalek-7 33060 64 24/0 Foundation Ramsharan Giri Siddhalek-7 49310 65 9/0 Erection Kalpana Dangol Thakre-8 5250 66 8/0 Erection Raj Kumar Tamang Thakre-8 6329.5 67 33B/0 Erection Krishna Prasad Sedai Siddhalek-3 36000 68 33B/1 Erection Rewati Prasad Sedai Siddhalek-3 11250 69 33B/1 Erection Ram Hari Sedai Siddhalek-3 25850 70 32A/0 Erection Chiranjivi Sedai Siddhalek-3 7200 71 9/0 Erection Ram Bahadur Dangol Thakre-8 1575 72 9/0 Erection Samjhana Dangol Thakre-8 953.75 73 9/0 Erection Bharat Dangol Thakre-8 3780 74 9/0 Erection Mukunda Dangol Thakre-8 673.75 75 37/0 Foundation Nawa Raj Pandey Benighat Rorang-5 18750 76 37/0 Foundation Gopal Bahadur Bisural Benighat Rorang-5 18800 Foundation Total S. Angle Name of official land / Address Compensate N point owner Erection d Amount 77 37/0 Foundation Hari Bahadur Bisural Benighat Rorang-5 20250 78 37/0 Foundation Tep Bahadur Bisural Benighat Rorang-5 47000 Benighat Rorang- 79 46B/0 Erection Dor Bahadur Shrestha 36360 10 80 44A/0 Foundation Parwati Singh Thakuri Benighat Rorang-9 21000 81 31A/0 Foundation Tek Bahadur Silwal Siddhalek-3 23240 82 7C/0 Erection Bishnu Prasad Upreti Dhunibesi-6 45775 83 44A/0 Erection Bhakta Bahadur Malla Benighat Rorang-9 7875 84 33A/0 Erection Dhruba Prasad Sedai Siddhalek-3 63900 85 33B/1 Foundation Ram Hari Sedai Siddhalek-3 29600 86 8/1 Foundation Binda KC Thakre-8 18305 87 34/0 Foundation Sita Sedai Siddhalek-3 10912 Total 1831867.95

Gorkha District

Annexure 7 Letter related to Livelihood Restoration Program (Skill Training implementation) -DKTLP Annexure 8 Details related to trainings Detail participant’s list of Driving Training in - DKTLP

S. Relation on Participants Name Address Land Owner’s Name Gender Tower/SS/ROW/Structure Training N. Land Owner 1 Binita Sharma Kusma MC 2 Birendra Paudel Daughter F Khurkot SS Driving 2 Lopchan Sherpunja Annapurna 7 Rupdevi Sherpunja Brother M Structure AP 39C Driving 3 Bibek Shepunja Annapurna 7 Gauseri Shrpunja Son M ROW Driving 4 Dinesh Karki Raghuganga 3 Tek Bahadur Karki Son M Structure AP 29 Driving Khurkot SS 5 Pushpa Sharma Kusma MC 2 Taranath Paudel Daughter F Driving

BamBahadur 6 Swikriti Ghamal BK Jaljala 2 Daugher in Law F AP 22 Driving Biswakarma 7 Nabin Malla Jaljala 4 Chandra Bahadur Malla Son M AP 17A Driving 8 Mukund Prasad Acharya Jaljala 7 Bal Krishna Upadhyaya Son M AP 11 Driving 9 Sanjaya Bahadur Shahi Raghugaga 3 Dirgha Kumari Shahi Grand Son M AP 27A Driving 10 Arbinda Karki Jaljala 2 Nir Bahadur Karki Son M AP 24A Driving 11 Jivnath Subedi Kusma RM 2 Jivnath Subedi Self M Khurkot SS Driving 12 Yogendra Malla Jaljala 4 Hira Kumari Malla Son M AP 17 Driving 13 Sharmila Hamal Malla Jaljala 4 Tika Kumari Malla Daughter in law F AP 24 Driving 14 Tilak Prasad Rijal Jaljala 7 Him Lal Padhyaya Son M AP 13 Driving 15 Sagar Rijal Jaljala 7 Muktiram Upadhyaya Son M AP 13/1 Driving 16 Ranjita Malla Jaljala 4 Purna Kumari Malla Daughter in law F AP 17 Driving 17 Prasiddha Acharya Jaljala 7 Dand Pani Padhyaya Nephew M AP 13A Driving 18 Ganesh Acharya Jaljala 7 Jamuna Acharya Brother M AP 15 Driving 19 Sagar Acharya Jaljala 7 Yamnath Sharma Son M AP 11 Driving 20 Rajesh Rijal Jaljala 7 Man Kumari Upadhyaya Son M AP 13 Driving Indra Bahadur 21 Bishal Biswakarma Jaljala 2 Son M ROW/Structure Driving Biswakarma AP 12 22 Bhojraj Acharya Jaljala 7 Kedarnath Acharya Brother M Driving

23 Gokarna Bhandari Raghuganga 2 Dhan Kumari Bhandari Son M AP 32 /Structure Driving 24 Krishna Bahadur Thapa Jaljala 3 Lal Bahadur Thapa Son M AP 21 Driving 25 Tirth Nath Sharma Jaljala 7 Tirthnath Sharma Self M AP 15 Driving Letter of Implementation of Driving Training in Parbat District- DKTLP

List of Participants of Driving Training in Parbat District- DKTLP

List of Participants of Beautician Training in Dhading District-MKTLP

Detail of participants’ list of Beautician Training in MKTLP

Name of Training event: Beautician (Basic Level)Training Training Place: Dhunibesi Municipality-6,Dharke Training Participants Date: 03 Mansir to 03 Magha 2075 Sex Ethnicity SN Trainee Name Address Male Female Total IP Dalit Other 1 Bimala Upreti 1 1 1 Dhunibesi-6 2 Sapana Adhikari 1 1 1 Thakre-9 3 Santoshi Upreti 1 1 1 Dhunibesi-7 4 Anjana Acharya 1 1 1 Thakre-9 5 Dipa Dangol 1 1 1 Thakre-9 6 Shrijana Danjol 1 1 1 Thakre-9 7 Ambika Thapa 1 1 1 Thakre-8 8 Britney Bhandari 1 1 1 -7 9 Sunita Tamang 1 1 1 Thakre-11 10 Radhika Dhungana 1 1 1 Galchhi-1 11 Ganga Dhungana 1 1 1 Galchhi-1 12 Rabina Thapa 1 1 1 Gorkha 13 Rejina Thapa 1 1 1 Dhunibesi-6 14 Sabita Thapa 1 1 1 Dhunibesi-6 15 Mina Khatri 1 1 1 Dhunibesi -6 16 Mina Pandit 1 1 1 Dhunibesi-8 17 Samita Tamang 1 1 1 Thakre-11 18 Sabina Acharya 1 1 1 Thakre-11 19 Anu Lama 1 1 1 Dhunibesi-6 20 Usha Aryal 1 1 1 Thakre-8 21 Renuka Tamang 1 1 1 Dhunibeshi-6 22 Tulasha Pandit 1 1 1 Thakre-8 23 Bimala Khatiwada 1 1 1 Galchhi-8 24 Pramila Tamang 1 1 1 Dhunibeshi-6 25 Rita Tamang 1 1 1 Dhunibesi-6 26 Sarita BK 1 1 1 Gorkha 27 Asmita Tamang 1 1 1 Dhunibesi-6 Total 0 27 27 9 1 17

Detail of participants’ list of Seasonal and Off -seasonal Vegetable Production Training in MKTLP

Name of Training event: Seasonal and Off-seasonal Vegetable Production Technology Training Place: Siddhalek RM-4,Nibuwatar,Community building Training Participants Date: 17-23 Mansir 2075 Sex Ethnicity SN Trainee Name Address Male Female Total IP Dalit Others 1 Maya Nath Silwal 1 1 1 Siddhalek-4 2 Dambar Bahadur Gurung 1 1 1 Siddhalek-4 3 Ramsharan Tripathi 1 1 1 Siddhalek-4 4 Ram Prasad Pandey 1 1 1 Siddhalek-4 Yak Bahadur Thapa 5 1 1 1 Siddhalek-4 Magar 6 Nawa Raj Tripathi 1 1 1 Siddhalek-4 7 Raju Tripathi 1 1 1 Siddhalek-4 8 Dhruba Prasad Sedai 1 1 1 Siddhalek-4 9 Ram Prasad Sedai (Ka) 1 1 1 Siddhalek-4 10 Bimala Sedai (Ka) 1 1 1 Siddhalek-3 11 Tulasi Thapa Magar 1 1 1 Siddhalek-4 12 Kabita Rana Magar 1 1 1 Siddhalek-4 13 Ambika Sedai 1 1 1 Siddhalek-3 14 Manju Sedai 1 1 1 Siddhalek-3 15 Devaki Sedai 1 1 1 Siddhalek-4 16 Bimala Sedai (Kha) 1 1 1 Siddhalek-4 17 Dhan Maya Sedai 1 1 1 Siddhalek-3 18 Amrita Sedai 1 1 1 Siddhalek-3 19 Bhagawati Sedai 1 1 1 Siddhalek-4 20 Mina sedai 1 1 1 Siddhalek-3 21 Nirmala sedai 1 1 1 Siddhalek-3 22 Aam Maya Thapa Magar 1 1 1 Siddhalek-3 23 Ram Hari Pandey 1 1 1 Siddhalek-3 24 Ram Prasad Sedai (Kha) 1 1 1 Siddhalek-3 Total 12 12 24 6 0 18

Name of Training event: Seasonal and Off-seasonal Vegetable Production Technology Training Place: Siddhalek RM-7,Pipaltar,Ward Office building Training Participants Date:25 Mansir-02 Poush 2075 Sex Ethnicity SN Trainee Name Address Male Female Total IP Dalit Other 1 Parbati Pokharel 1 1 1 Siddhalek-7 2 Yak kumari Giri 1 1 1 Siddhalek-7 3 Shova Sedai 1 1 1 Siddhalek-7 4 Samita Kandel 1 1 1 Siddhalek-7 5 Ram Maya Basel 1 1 1 Siddhalek-7 6 Bishnu Giri 1 1 1 Siddhalek-7 7 Mato Giri 1 1 1 Siddhalek-7 8 Rewati Pandey 1 1 1 Siddhalek-7 9 Mitra Lal Shrestha 1 1 1 Siddhalek-7 10 Raj Kumar Shrestha 1 1 1 Siddhalek-7 11 Ram Shran Bhujel 1 1 1 Siddhalek-7 12 Purna Lal Shrestha 1 1 1 Siddhalek-7 13 Indra Bahadur Bhujel 1 1 1 Siddhalek-7 14 Bhim Kumari Sedai 1 1 1 Siddhalek-7 15 Ram Bahadur Bhujel 1 1 1 Siddhalek-7 16 Tuk Bahadur Bhujel 1 1 1 Siddhalek-7 17 Lal Bahadur Bhujel 1 1 1 Siddhalek-7 18 Samsher Sarki 1 1 1 Siddhalek-7 19 Bed Nidhi Kandel 1 1 1 Siddhalek-7 20 Khem kumari Dhakal 1 1 1 Siddhalek-7 21 Samjhana Bhatta 1 1 1 Siddhalek-7 22 Nawa Raj Adhikari 1 1 1 Siddhalek-7 23 Rohini Prasad Khatiwada 1 1 1 Siddhalek-7 Total 15 8 23 8 2 13

Annexure 9

Grievance Redress Committee Meeting Matrix

No. of Topics/ Issues SN Date Type of Participants Location Information Disseminated Participants discussed

DKTLP Purpose to use the Male-9 GRC committee members and budget that has 2075/3/27 Jaljala, Gandaki VDC 1 Female-1 coordinator of GRC Mr. Tungnath given to Jaljala 11 July 2018 ward no. 7 Total-10 Sharma and locals Gandaki VDC wardno.7 by ESSD Male-9 GRC committee members and Road construction 2075/3/28 2 Female-1 coordinator of GRC Mr. Tungnath at Majhigaun Kushma RM ward no.2 12 July 2018 Total-10 Sharma and locals Purpose to use the Male-6 GRC committee members and budget given from 2075/3/28 3 Female-1 coordinator of GRC Mr. Devendra the project to Kushma RM ward no.1 12 July 2018 Total-7 Prasad Subedi and locals Affected households Male-7 GRC committee members and Purpose to use the 2075/3/28 4 Female-1 coordinator of GRC Mr. Hari Bikash budget given from Jaljala Ward no.8 12 July 2018 Total-8 J.C the project Purpose to use the Male-6 GRC committee members and budget given from 2075/3/31 Annapurna VCD ward no. 5 Female-1 coordinator of GRC Mr. Gam Bdr the project to 15 July 2018 7 Total-7 Fagami and locals Affected households 2075/6/16 Total-16 The ward chairman Mr. Yadu Nath Khurkot ,Kusma- CSR budget,social issues,skill 6 2 October Male-14 GRC meeting Bastola, GRC members and others 2,Bagaicha development training, 2018 Female -2 Annapurna RM vice chairman, Ward 2075/7/9 Total -22 Shifting the affected people Deputy chairman, Annapurna RM Tatopani Bazar Police 7 26 October Male-11 GRC meeting and compensate the crop and Officer,contractor ,ESSD,Project chauki 2018 Female -11 other losses Officer and others.

2075/8/3 Total-24 Crop compensation, social The ward chairman GRC Mr. Gam Bdr 8 19 November Male-12 GRC meeting Annapurna-7,Mahavir issues, skill development Fagami, GRC members and others 2018 Female -12 training

2075/8/3 Total -15 The ward chairman GRC Mr. Bil Bdr Tiplyang Bazar About crop compensation and 9 19 November Male-13 Fagami member ,Contractor, Project, GRC Meeting Raghuganga-1 skill training. 2018 Female -2 ESSD Beni unit and others

2075/8/24 Total-8 Demand on road construction Raghuganga 2,GRC Chairman and Demand of 10 10 December, Male-7 ESSD Beni Unit Office equipment (JCV) for Members equipment 2018 Female-1 excavation. To construct the road which is CSR 2075/9/1 Total-25 GRC Chairman, GRC members, affected by the AP 44A tower Implementation,AP 11 16 December, Male-18 PAFs, Contractor and other local Annapurna RM 2 Tatopni , foundation,Shifting AP 45 45 issues,AP 44A 2018 Female-7 person affected families and CSR issues Budget implantation. 2075/9/3 Total-15 GRC Chairman,GRC members, Demand on different 16 Topics Annapurna 7,Histan,Ward 12 18 December, Male-13 Project Manager, PAFs, other local Various Demands for solving by the Project and Office 2018 Female-2 person ESSD.

2075/9/10 Total-10 GRC Chairman, GRC members, CSR 13 25 December, Male-9 Project Manager, PAFs, other local Jaljala 2 CSR Implementation Implementation 2018 Female-1 person

S. No. of Type of Topics/ issue Date Location Information disseminated N. Participant Participants discussed MKTLP Discussion was made on the issues of land for construction of tower 2075/3/21 Male – 6 Land and GRC committee no 31A/0.AP agreed to provide land and the meeting decided to start 1 5’th July Female – 0 compensation Siddhalek members the tower foundation work at site. Also decided to provide land 2018 Total - 6 issue -7,Salang compensation amount to AP as soon as possible. Discussed on the land and crop loss issue from the construction 2075/4/2 Male – 6 Land and Siddhalek work of AP 23A/0 and 24/0.The meeting decided to measure the GRM committee 2 18’th July Female – 0 compensation - crop loss area of APs and request to Project Management Office to members 2018 Total – 6 issue 7,Adamta make necessary arrangement for providing crop and land r compensation amount to APs immediately. Project staffs, 2075/4/16 Wards Siddhalek The meeting decided to carryout survey and design work for the Male – 7 representative, Discussion on - protection and maintenance of rural road as suggested by 3 Female – 1 01 August Staffs of TATA road issue 7,Adamta community. Also decided to start the maintenance work immediately Total – 8 2018 project and r,Dhading after the monsoon. Community Full affected Aps name list was not published Land area which was used in tower construction work will be Ikchhaka 2075/4/7 Male – 6 During the measured and compensated as per project for the loss of crops and Project Staffs and mana RM 4 23rd July, Female – 0 construction road from the project as well. APs name and compensatory for all community 4, 2018 Total- 6 work road was those affected Aps whose name hasn’t been published in land Chitwan damaged as acquisition notice well crop loss of others agricultural land. Landslide by the leg of AP50A from Ikchhaka Right compensation for the loss of crops during the construction as 2075/4/14 Male- 8 Project Staffs and uses of JVC mana RM well clearance of stone, muds and bricks. Construction of road with 5 30th July, Female-0 community crop loss was 3, broad turnings point which was damaged by JVC during the 2018 Total- 8 occur of Prithivi Chitwan construction Gurung’s land.

Benighat 2075/5/8 Male – 10 Rorang It was informed that survey and design work for the protection of GRM committee Land slide 6 24 August Female – 0 RM- rural road and tower itself has been completed. The meeting decided members issue 2018 Total – 10 10,Dhadi to start the protection work immediately. ng district 2075/5/5 Male-7 NEA staffs, Ichhakama Meeting was about the issues solved of the GRC meeting formed GRC Issues 7 21/August / Female-0 Contractor staffs, na, RM-4 on 2075-4-7 solved 2018 Total-7 ESMU Officers Chiwan district

Land owner Mr. Bhakta Bahadur Malla has stopped the tower erection work of AP 44/0 due to delay in providing land 2075/5/20 Male – 7 Benighat compensation to his land. Discussion was held with him and GRC 05th GRC committee Land 8 Female – 0 Rorang, meeting was also organized to discuss the issues. It was decided to September, members compensation Total - 7 Dhading provide land compensation immediately to him and Mr. Malla agreed 2018 to resume the tower erection work at his land. Now compensation was provided to him. Community and user committee of Parewatar-Khanibhayang rural road had complained that one leg of tower 28/0 lies on the road 2075/5/21 Siddhalek which obstacle in vehicle movement. It was discussed in GRC Male – 7 06 GRC committee RM- meeting and decided to open the diversion track for vehicle 9 Female – 0 Rural Road September, members 6,Dhadin movement during the foundation work. It was also decided to Total - 7 2018 g rehabilitate the rural road as in previous condition with appropriate engineering design and structure after the foundation work is completed. Crop loss area during the tower construction work which was left out as complained by community was carried out with participation of 2075/6/04 Male – 5 GRC members and local community. Regarding the payment due GRC committee Siddhalek- 10 20 Female – 0 Crop loss issue of labor gang during their stay at community which they used members 3,Dhading September Total - 5 fire wood and vegetables from community It was decided to communicate with TATA project office to settle the issue if any as complained by community. Implementation Siddhalek Male – 6 Discussed on implementation of seasonal and off seasonal 2075/6/15 GRC committee of livelihood RM- 11 Female – 0 vegetable production training to 20 PAFs of ward no 7 of Siddhalek 01 October members restoration 7,Dhadin Total - 6 RM. activity g Implementation Siddhalek Male – 7 Discussed on implementation of seasonal and off seasonal 2075/6/19 GRC committee of livelihood RM- 12 Female – 0 vegetable production training to 20 PAFs of ward no 3 and 4 of 05 October members restoration 3,Dhadin Total - 7 Siddhalek RM. activity g 2075/7/20 Submission of Thakre Decided to inform the APs to summit application to project office for Male – 6 06 GRC committee application for RM- land compensation. Also discussed on grievance received from Sanu 13 Female – 0 November members land 11,Dhadi Kanchha Tamang and decided to inform the project office for further Total - 6 2018 compensation ng process. 2075/08/17 Male – 6 Commenceme Decided for the commencement of 7 days long vegetable farming 03 GRC committee Siddhalek 14 Female – 0 nt of vegetable training to PAFs from 03 December 2018 at Siddhalek RM-3 under December members RM-3 Total - 6 farming training project mitigation activity. 2018 2075/08/25 Male – 5 Commenceme Decided for the commencement of 7 days long vegetable farming 11 GRC committee Siddhalek 15 Female – 0 nt of vegetable training to PAFs from 11 December 2018 at Siddhalek RM-3 under December members RM-7 Total - 5 farming training project mitigation activity. 2018 2075/08/27 Site clearance Decided to communicate with TATA project office for the immediate Male – 5 13 GRC committee and Siddhalek action to solve the issues raised by community. Also decided to 16 Female – 0 December members implementation RM-3 & 4 inform the PMO Office and ESSD to address the community demand Total - 5 2018 of CSR activity under CSR activity. 2075/08/29 Male – 5 Land plot differ 15 GRC committee Siddhalek Decided to inform the issues to PMO office and will request for site 17 Female – 0 and additional December members RM-7 visit with land measurement staff to solve the APs complaint. Total - 5 land used 2018 GRC committee members visited the site and discussed with the 2075/09/10 Dhunibes APs of tower no.6/0 and 6A/0. GRC committee members requested Male – 10 25 GRC committee i the APs to provide land for the construction of towers as other 18 Female – 0 Land issue December members Municipal people who are supporting to project activity. Also informed to the Total - 10 2018 ity-7 APs not to construct any structure in the land to be acquired for project activity. About selection 2075/8/12 Gorkha Male – 6 of trainees for The PAF from Gorkha municipality of ward number 13 and 14 will be 28th GRC committee municipal 19 Female – 1 tailoring and selected for the Skill development training -Tailoring and Seasonal November, members ity, ward Total -7 agriculture and offseanosal vegetable growing training as identified by RIPP. 2018 no 14 training About selection 2075/9/3 of trainees for Gandaki Male – 7 18th GRC committee seasonal and RM, ward Total 25 trainees were selected of trainees for tailoring and 20 Female – 1 December, members non-seasonal no. 8, agriculture training. Total -8 2018 vegetable Gorkha farming training About training starting of non- Ichhakam 2075/9/4 Male – 7 seasonal anaRM, Training was concluded to start from 4th January of 2019 in ward no 19th GRC committee 21 Female – 0 vegetable ward no. 3 and 4 of Ichhakamana RM. Similarly the trainer for the training was December, members Total -7 farming training 4 , also selected. 2018 and trainer Chitwan selection Chautaro was Impacted while constructing AP GRC team has decide to take application from community people 2075/9/6 71/0 at Gorkha Male – 8 with proposed location for the restoration of Chautaro. After taking 21st GRC committee Yangkot and Municipal 22 Female – 3 application GRC decided to process ahead for the application. December, members local track road ity, ward Total -11 Contractor is agreed to maintain impacted local track road after 2018 was also no. 13 finishing tower erection work. impacted by Tower Pad of AP 71/0

S.N. No. of Type of Topics/ issue Date Location Information disseminated Participant Participants discussed

KNBTLP

1 2075/08/11 Male-10 Executive ward GRC meeting: Baglung With field observation of alignment; affected families Female-1 chairperson, Local Final Confirmation municipality- informed about projects procedure, government policy, and th 27 Dalit-3 people, PAFs, of Alignment & 13, Baglung land acquisition act 2034, compensation of land. November, Janjati-0 Project staffs, Check Survey and 2018 Others-8 Contractor and Cadastral Survey ESMU Total -11

Annexure 11

Grievance Received Matrix

Recorded Grievances

S.N Location Recorded by Issue Type Issue Description Status

DKTLP 1 Annapurna 3, Myagdi Chandra Land Need of compensation after land Solved Prasad compensation used for tower construction Serchan 2 Mallaz Jaljala- 3 Krishna Crop Need of Compensation for his Solved Parbat Bahadur compensation crop destruction due to Baruwal construction 3 Jaljalla -2, Parbat Bam Bahadur Re- mapping Re- mapping and surveying of his Solved Bishwokarma and surveying land for the construction of tower of Land

4 Jaljalla -8, Parbat Bal Bahadur Land and crop Need of compensation after land Under Chhetri compensation used and crop destruction for process of tower construction solving

5 Jaljala-7, Parbat Dandapani Land and crop Need of compensation after land Solved Upadhyaya compensation used and crop destruction for tower construction

6 Jaljala, Parbat Shiva Prasad Land and crop Need of compensation after land Solved Acharya Compensation used and crop destruction for tower construction

7 Raghu RM-3, Myagdi Tunga Damage of Need to make new canal and also Solved Bahadur Canal fill up the land which has been Malla damaged.

8 Myagdi Dinesh Karki Temple and Need of compensation for temple Solved road and Road re-construction due to compensation AP 29.

9 Jaljala- 7 Parbat Kedar Nath Land Need of Compensation for his Under Acharya compensation land destruction due to process of & disable construction and compensation solving compensation for his disabled son 10 Jaljala- 7 Parbat Kedar Nath crop Need of Compensation for his Under Acharya compensation crop destruction (maize and rice) process of solving

11 Jaljala- 7 Parbat Kedar Nath Private tree Need of his tree compensation on Under Acharya compensation his private land process of solving MKTLP

1 Dhunibesi Krishna Land area Land area used in tower Solved Municipality-6 Bahadur construction work but name was Khatri not published in land acquisition notice. 2 Siddhalek RM-3 Ram Prasad Rural road Rural road lies under tower pad of Under Sedai under tower AP 34A/1 tower. Communities are process of pad demanding to support them in solving road diversion work.

3 Siddhalek RM-3 Maya Nath Clearance of Excavated materials produced Under Silwal excavated during the tower construction to process of materials be cleared at site. solving

4 Siddhalek RM-3 Kinara Rajya Protection and A religious house (Pouwa) lies Under Laxmi Devi restoration of under RoW of tower no AP 35/0. process of Malla religious house Community is demanding support solving (Pouwa) for restoration of Pouwa.

5. Thakre RM-8 Arjun Protection of IP IPs (Gurung & Tamang) Solved Gurung/Raju cremation cremation place at AP 9/0 lies Gurung place under RoW.

6 Siddhalek RM- Ward Office Rural road Ward Office of Siddhalek RM-7 Solved 7,Adamtar,Dhading of Siddhalek and community people had RM-7 complaint that some part of the rural road was used in construction of AP 23A/0 as a result existing road is narrowed for vehicle movement. Necessary work to be carried out by the project for the maintenance of existing road. 7 Dhunibesi Krishna Soil erosion Mr Khatri complained that Solved Municipality-6,Dhading Bahadur protection work to be Khatri implemented immediately to control the soil erosion at AP 7D/0. He was worried that land erosion could affect to his house and shed if protection work is not carried out immediately. 8 Siddhalek RM- Community Crop loss Community of Siddhalek RM-3 Solved 3,Dhading and 4 complained that some AP’s crop loss area measurement has been left. Community has requested to measure the crop loss area whose crop area was left out to measure during the tower foundation and erection work. 9 Sahidlakhan RM-3, Narayan Impact on Land Impact on land during tower Solved Banauti, Gorkha Prasad foundation work and erection Pokhrel work by the movement of the contractor vehicle 10 Sahidlakhan RM-3, Bhim Prasad Impact on Land Impact on land during tower Solved Banauti, Gorkha Pokhrel foundation work and erection work by the movement of the contractor vehicle and land also use for labor camp 11 Sahidlakhan RM-3, Madan Dutta Impact on Land Impact on land during tower Solved Banauti, Gorkha Koirala foundation work and erection work by the movement of the contractor vehicle

12 Benighat Rorang Bhakta Land Delay in providing land Solved RM-9 Bahadur compensation compensation which the land is Malla used for the construction of tower no 44/0. 13 Siddhalek RM-6 Ram Kumar Disturbances Construction of tower no 28/0 Solved Shrestha to rural road obstacles the vehicle movement in rural road. 14 Siddhalek RM-7 Lal Bahadur Damaged of One table and one fan damaged Solved Bhujel house hold by hit of boulder during the appliance and construction work of tower no furniture 25B/0.No any compensation received against the damaged goods. 15 Galchhi Bharat Disturbances Construction of tower no 18C/0 is Solved RM-8 Bahadur to rural road likely to affect the expansion of Wagle Galchhi-Mahadevbesi rural road.

16 Thakre RM-11, Sanu Risk of Affected to private house and Under Dhading Kanchha landslide to shed due to construction of tower process of Tamang house and no 16A/0.Also generates risk of solving shed land slide to house and land. 17 Benighat Rorang RM, Santosh Disturbances Damaged of community irrigation Under Dhading Dallakoti to Community canal due to tower construction process of Irrigation canal work. No maintenance support solving receives from project. 18 Thakre RM-11, Chyante Land owner Private land belonging to Chyante Under Dhading Praja name not Praja was used in tower process of published in construction work of 14C/0 but his solving land acquisition name was not published in land notice acquisition notice. 19 Ichchayakaman RM-3 Dil Bahadur Land GRC meeting is in process Under Gurung Compensation, process of ROW issue solving and Resettlement. 20 Gorkha Municipality-13 Basudev Impact on Chautaro was Impacted while Under Shrestha and Chautaro and constructing AP 71/0 at Yangkot process of others local track road and local track road was also solving by Tower Pad impacted by Tower Pad of AP of AP 71/0 71/0 21 Siddhalek RM-4 Dambar Site clearance At AP 31/0, excavated soil Under Bahadur and crop during the tower foundation work process of Gurung damage has not been removed from his solving field. 22 Siddhalek RM-7 Ram Bahadur More land used At AP 24D/3, tower has been Under Sarki and Land plot constructed in new land plot no process of no differ rather than the land plots no 502 solving which was published in land acquisition notice. Also more land has been used for the tower construction work. 23 Siddhalek RM-3 Yak Bahadur Bank denied to Bank denied to provide cheque Solved Tumasi provide cheque amount due to difference in title amount name written in cheque (cheque was provided him for crop compensation by PMO office) and account name maintained at bank. This has been solved now. 24 Galchhi RM-8 Sher Bahadur Simpani Kalika Simpani Kalika CF building lies Solved Nepal CF areas and under the RoW of MKTLP CF Office transmission line. CF members building to be explained that compensation to affected be provided soon to construct new building in safe site KNBTLP 1 Bihadi-3 Janak Prasad Shifting the Transmission line directly affect Solved Ranipani, Parbat Bhattrai alignment way his residential plot (Ghaderi) so need of shifting.

Annexure 12

Grievance Received Letters

DKTLP

MKTLP

KNBTLP

Annexure 13 Public Consultation Matrix

SN Date No. of Type of Participants Topics/ Issues Location Information Disseminated Participants discussed DKTLP 1 2075/3/28 Male-6 Ward chief, TATA, GRC Kushma RM ward no.1 12th July, Female-0 ward Staffs Formation 2018 Total-6 2 2075/3/31 Male-5 Ward chief Mr. Gam GRC Annapurna VCD ward no. 15 July 2018 Female-0 Bdr. Fagami , ESSD Formation 7 Total-5 and local

3 2075/4/10 Male-13 Kusma MC Mayor Landslide Kusma MC Office Kusma Clean the drainage and field visit 26 July 2018 Total-13 ,Project Manager issues for Parbat on landslide site. ,ESSD Unit and others NayaPulKusma MC -2 4 2075/4/15 Male -11 Kusma MC Mayor Landslide Kusma MC Office Kusma Cost Esrimate and Construction 31 July 2018 Total-11 ,Project Manager issues for Parbat by the Project ,ESSD Unit and others NayaPulKusma MC -2 5 2075/5/22 Total-13 CFUG, Forest officer, About Tree Raghuganga -3 ,ward About all the issues solved and 7 September Male-12 ESSD, Project cutting for AP office not any issues remaining for AP 2018 Female-1 27 A 27 A

6 2075/5/24 Total-18 Ward chairman About GRC Annapurna- Meeting about the GRC formation 9 September Male-18 Annapurna-6, ESSD, formation 6,Pokharebagar 2018 Project, and other stakeholders. 7 2075/6/11 Total-6 Bidhyajyoti SS About Beni unit office,Beni Meeting was held about the 27 September Male-6 principal ,social Grievances Playground, Children park and 2018 persons ESSD, Project and social Helipad construction. issues. 8 2075/6/2 Total-24 Ward chairman, ESSD, About Annapurna -3 ward office About the issue on CSR budget. 28 September Male-19 Contractor Grievances ,Dana As APs are demanding more 2018 Female-5 Representative ,Project and CSR. budget. Not any decision was and others made as their demands were very high which cannot solved by ESSD

9 2075/6/14 Total -26 Chief district officer, About social At CDO office Beni, Reporting for shifting alignment, 30 September Male-23 DSP, District issues Myagdi. compensation and other issues 2018 Female-3 coordination committee Annapurna-6, within a week by the project. chief, Annapurna Rural Pokhrebagar. Municipality Chairman, Project manager, Ward Chairman, ESSD Beni unit, Affected persons, press reporter and others

10 2075/6/23 Total -35 Annapurna Public Annapurn - About Compensation 9 October Male-33 Chairman,CDO Consultation 6,Pokharebagar,RM Hall Alignment shifting,and other 2018 Female-2 Myagdi, Ward Meeting issues. Chairman, Project Manager, ESSD Beni unit, Contractor, PAFs and Social Person. 11 2075/6/24 Total -17 Annapurna Chairman, Public Tatopani Bazar About the AP 45 Affected shifting 10 October Male -12 Ward chairman, Consultation and protection. 2018 Female-5 Project Officer, Meeting Contractor affected people, and others

12 2075/7/9 Total -22 Annapurna RM vice GRC Tatopani Bazar Police GRC formation. 26 October Male-11 chairman, Ward Formation chauki 2018 Female -11 chairman, Annapurna RM Officer,contractor ,ESSD,Project Officer and others. 13 2075/8/13 Total -21 Community forest user Public Jaljala 7 ,Parbat About social issues 29 November Male-3 group ,temple Consultation 2018 Female-18 chairman ,Contractor Meeting and ESSD Beni unit 14 2075/9/1 Total-24 ADB Consultant ,ESSD Shifting Annapurna 6,Pokhrebagar About shifting alignment. 16th Dec, Male-18 Beni, PAFs, Other Alignment 2018 Female-6 Local people 15 2075/9/6 Total-11 Project Manager, PSC, CSR Project Office Beni Technical Estimate for CSR 21 Dec, 2018 Male-11 ESSD, ESSD Beni Implementation Demands. Female-0 and data collection 16 2075/9/6 Total-13 ESSD, Project ,Civil CSR Estimate Annapurna 1 ,Bega CSR Estimate 21 Dec, 2018 Male-11 technical person, Female-2 ESSD Beni 17 2075/9/6 Total-13 ESSD, Project ,Civil CSR Estimate Annapurna 7 CSR Estimate 21 Dec, 2018 Male-12 technical person, Female-1 ESSD Beni 18 2075/9/7 Total-6 ESSD, Project ,Civil CSR Estimate Annapurna 2 CSR Estimate 22 Dec, 2018 Male-6 technical person, Female-0 ESSD Beni 19 2075/9/8 Total-10 ESSD, Project ,Civil CSR Estimate Jaljala 4 CSR Estimate 23 Dec, 2018 Male-5 technical person, Female-5 ESSD Beni 20 2075/9/9 Total-15 ESSD, Project ,Civil Social and Jaljala 8 About Social and Environment 24 Dec Male-15 technical person, Environment issues Female-0 ESSD Beni issues 21 2075/8/21 Total-19 Ward Chief, PSC, Rate fixation of Beni Rate fixation of land 7th Dec 2018 Male-18 ESSD, ESSD Beni land Female-1 MKTLP 1 2075/3/28 Male – 8 Project staffs and Discussion on Dhunibesi-6,Dhading Land area which was used in Female – 1 Community land issue tower construction work will be 12 July, 2018 Total – 9 measured and compensated as per project rules.APs name was not published in land acquisition notice. 2 2075/4/8 Male – 4 Project staffs and Support for Ganise Chour, Thakre APs were informed that 24’th July Female – 0 community construction of RM-8,Dhading application received from them 2018 Total – 4 cremation has already been submitted to place project Management Office and ESSD for necessary action. IPs (Gurung & Tamang) cremation place at AP 9/0 lies under RoW and requested for support construct cremation place at safe site. 3 2075/4/10 Male – 15 Project Staffs and Tower Siddhalek RM-3,Dhading Communities were informed that Female – 1 community foundation site the issues will be discussed with 26 July, 2018 Total – 16 clearance, rural TATA project staffs and Project road under Management Office for proper tower solution. 4 2075//18 Male – 6 Project staffs and Discussion on Dhunibesi-6,Dhading Land area which was used in Female – 2 Community land issue tower construction work will be 3rd Sep, 2018 Total – 8 measured and compensated as per project rules.APs name was not published in land acquisition notice. 5 2075/4/16 Male – 25 Project staffs, Wards Discussion on Siddhalek-7,Adamtar, The meeting decided to carryout Female – 3 representative, Staffs road issue Dhading survey and design work for the 01 August Total – 28 of TATA project and protection and maintenance of 2018 Community rural road as suggested by community. Also decided to start the maintenance work immediately after the monsoon. 6 2075/4/22 Male= 8 Contractor staffs, Improvement Dahaki, Ichchhakamana Suggestion for local road 7 August Female=2 ESMU Officer, Project of local road RM-3, Chitwan district maintenance and improvement of 2018 Total=10 affected villagers section drinking water source has been (Chumling- forwarded to concerned Dahaki); stakeholder (TATA, ESSD, and Improvement Project Office) for further actions. of water source by providing required cement 7 2075/6/11 Male – 22 Project staffs, Wards Discussion on Galchhi-8,Dhading The meeting with community was Female – 2 representative, Staffs rural road issue decided to request PMO office to 27 September Total –24 of TATA project and at AP 18C/0 carryout site inspection at AP 2018 Community 18C/0 by the concerned specialist from PMO office for the protection and maintenance of rural road as suggested by community. 8 2075/5/25 Male-12 Project staffs, Wards Discussion Sahidlakhan-3, Gorkha The issues of land has been Female-0 representative, Staffs Land issue observed with meeting attendants. 10 Total-12 of TATA project and September, Community 2018

9 2075/8/3 Male – 0 Trainee of skill Discussion on Dhunibesi Municipality- Female – 30 development training implementation 7,Dhading 19 November Total – 30 (Beautician training) of training 2018

10 2075/8/11 Male=14 Local Representative, Consultation Gorkha Municipality 27 November, Female=1 NEA Representative, meeting was Ward 14 Yankot, 2018 Total=15 SSO, ESO, TATA done for issue Gorkha Project Representative, regarding land NEA, Project Affected acquisition and people. obstacle for construction on AP 74/2 11 2075/8/1 Male -5 Local Representative, Consultation 17 November, Female-1 NEA Representative, meeting was Gorkha Municipality 2018 Total-6 SSO, ESO, TATA done regarding Ward 14 Yankot, Project Representative, compensation Gorkha NEA, Project Affected of structure people. and assistance for resettlement in AP73/A 12 2075/8/18 Male – 25 Beni Pakha Discussion on Siddhalek RM-3 Discussion was made with the Female – 11 Community forest user implementation members of Beni Pakha CF user 04 December Total – 36 group of training group to start the stringing work at 2018 forest area and agreed to support some aid to CF on behalf of TATA project Ltd. 13 2075/8/25 Male – 18 Trainee of Vegetable Agriculture Siddhalek RM-7 Regarding the query of trainee to Female – 10 farming tools support support them agriculture tools 11 December Total – 28 ie.Plastic tunnel, hand tractor, 2018 pesticide spray pump etc, It was informed them that their demand will be communicated and submitted to PMO Office. 14 2075/8/14 Male -7 SSO, ESO, and Consultation Markichowk Substation Contractor was advised to provide 30 November Female -0 Workers was done Aabukhaireni RM - regular health checkup facilities 2018 Total 0-7 regarding Tanahu for labour inside Substation and issues of also adviced to pay wages in time wages and health facilities

15 2075/8/24 Male -7 Local Representative, Water supply Sahid Lakhan RM -3 Contractor was agreed to make 10 Decemebr Female-0 NEA Representative, for construction Banauti Gorkha water supply route and maintain 2018 Total -7 SSO, ESO, TATA of tower properly by using 1000 m pipe Project Representative, provided to community under CSR 5NEA, Project Affected program. people

16 2075/9/6 Male -7 Local Representative, Compensation Sahid Lakhan RM -3 Contractor was agreed to provide 21 Decemebr Female -1 NEA Representative, for land which Banauti Gorkha 6 hour JCB support for restore of 2018 Total-8 SSO, ESO, TATA was used by land which was impacted while Project Representative, contractor for vehicle movement. NEA, Project Affected vehicle people movement and issues of crops 17 2075/9/8 Male -9 Local Representative, Compliance of TATA office at Contractor was advised to comply 23 December Female -0 NEA Representative, EHS Aabukhaireni’ Tanahu the issues regarding Environment 2018 Total-9 SSO, ESO, TATA Health and safety. Project Representative, NEA, Project Affected people

KNBTLP 1 2075/04/16 Male-13 Ward Chairperson, GRC Tansen Municipality-9, A committee was formed in the Female-4 Local people, Project Formation . Chairmanship of Ward 1/August/ Janjati-1 staffs, Contractor and Chairperson Tika ram Gaudel 2018 Others-16 ESSD Unit & APs Total-17

2 2075/04/23 Male-13 Ward Chairperson, GRC Palpa -1, Palpa District. A committee was formed in the Female-0 Local people, Project Formation Chairmanship of Ward 8/August / Total-13 staffs, Contractor and Chairperson Som Bdr.Jhedi 2018 ESSD Unit & APs

3 2075/04/30 Male-17 Ward Chairperson, GRC Galyang Municipality -5, A committee was formed in the Female-4 Local people, Project Formation Syanja District Chairmanship of Ward 15/August / Tota-21 staffs, Contractor and Chairperson Bishnu Basyal 2018 ESSD Unit & APs Cheetri

4 2075/06/5 Male-7 Ward Chairperson, GRC Tinahu Rural municipality A committee was formed in the Female-0 Local people, Project Formation (RM) -5, Palpa District. Chairmanship of Ward 21/September Janjati-1 staffs, NEA Chairperson chairperson Mr. Dal / 2018 Dalit-0 representatives, Bahadur Darlami. Others-6 Contractor and ESSD Unit & APs

5 2075/6/18 Male-14 Ward Chairperson, GRC Bihadi rural municipality- Discussed on objectives of GRC Female-3 Local people, Project Formation 6, Parbat District formation, its role and 4th October, Dalit-3 staffs, Contractor and responsibilities and then GRC 2018 Janjati-3 ESSD Unit & APs formed with the leadership of Others-11 Ward Chairperson Mr. Tek Total -17 Bahadur Thapa. 6 2075/6/19 Male-14 Ward Chairperson, GRC Bihadi rural municipality- Discussed on objectives of GRC Female-3 Local people, Project Formation 3, Parbat District formation, its role and 5th October, Dalit-0 staffs, Contractor and responsibilities and then GRC 2018 Janjati-4 ESSD Unit & APs formed with the leadership of Others-13 Ward Chairperson Mr. Rana Total -17 Bahadur Aale

7 2075/6/19 Male-18 Ward Chairperson, GRC Bihadi rural municipality- Discussed on objectives of GRC Female-1 Local people, Project Formation 2, Parbat District formation, its role and 5th October, Dalit-2 staffs, Contractor and responsibilities and then GRC 2018 Janjati-0 ESSD Unit & APs formed with the leadership of Others-17 Ward Chairperson Mr. Total -19 Om Prakash Kunwar

8 2075/7/6 Male-20 Ward Chairperson, GRC Tinahu Rural Discussed on objectives of GRC Female-6 Local people, Project Formation Municipality-4, Palpa formation, its role and 23rd October, Dalit-0 staffs, Contractor, District responsibilities and then GRC 2018 Janjati-23 ESSD Unit & APs formed with the leadership of Others-3 Ward Chairperson Mr. Dan Total -26 Bahadur Gaha

9 2075/7/8 Male-11 Ward Chairperson, GRC Bagnaskali Rural Discussed on objectives of GRC Female-3 Local people, Project Formation Municipality-9, Palpa formation, its role and 25th October, Dalit-2 staffs, Contractor and District responsibilities and then GRC 2018 Janjati-6 ESSD Unit & APs formed with the leadership of Others-6 Ward Chairperson Mr. Total -14 Thaneshwar Timilsena

10 2075/7/9 Male -14 Ward Chairperson, GRC Bagnasakali Rural Discussed on objectives of GRC Female-8 Local people, Project Formation Municipality, Ward no-5 formation, its role and 26th October, Total-22 staffs, Contractor, responsibilities and then GRC 2018 ESSD Unit & APs formed with the leadership of Ward Chairperson Mr. Ishwor Kumar Rana 11 2075/7/9 Male -14 Ward Chairperson, GRC Discussed on objectives of GRC Female-7 Local people, Project Formation Bagnasakali Rural formation, its role and 26th October, Total-21 staffs, Contractor, Municipality, Ward no-6 responsibilities and then GRC 2018 ESSD Unit & APs formed with the leadership of Ward Chairperson Mr. Laxmi Prasad Adhikari

12 2075/7/12 Male -31 Ward Chairperson, GRC Mathagadi Rural Discussed on objectives of GRC Female-6 Local people, Project Formation Municipality, Ward no-5 formation, its role and 29th October, Total-37 staffs, Contractor, responsibilities and then GRC 2018 ESSD Unit & APs formed with the leadership of Ward Chairperson Mr. Bel Bahadur Denga

13 2075/7/30 Male -21 Ward Chairperson, GRC Sunwal Rural Municipality, Discussed on objectives of GRC Female-1 Local people, Project Formation Ward No 11, Nawalparasi formation, its role and 15th Total-22 staffs, Contractor, District responsibilities and then GRC November, ESSD Unit & APs formed with the leadership of 2018 Ward Chairperson Mr. Devi Lal Dungre

14 2075/8/4 Male -16 Ward Chairperson, GRC Devraha Municipality, Ward Discussed on objectives of GRC Female-4 Local people, Project Formation no 6 andd 5, Rupandehi formation, its role and 20th Total-20 staffs, Contractor, District responsibilities and then GRC November, ESSD Unit & APs formed with the leadership of 2018 Ward Chairperson Mr. Damodar Chhettri

15 2075/7/16 Male -5 Ward Chairperson, GRC Sunwal Rural Municipality, Discussed on objectives of GRC Female-2 Local people, Project Formation Ward No 13, Nawalparasi formation, its role and 2nd Total-7 staffs, Contractor, District responsibilities and then GRC November, ESSD Unit & APs formed with the leadership of 2018 Ward Chairperson Mr. Upendra Raj Poudel 16 2075/8/3 Male -9 Ward Chairperson, GRC Sunwal Rural Municipality, Discussed on objectives of GRC Female-2 Local people, Project Formation Ward No 13, Nawalparasi formation, its role and 19th Total-11 staffs, Contractor, District responsibilities and then GRC November, ESSD Unit & APs formed with the leadership of 2018 Ward Chairperson Mr. Krishna Prasad Devkota

17 2075/08/11 Male-12 Ward Chairperson, GRC Parbat, Bihadi-14 Informed about KNBTLP and 27th Nov, Female-2 Local people, PAFs, Formation discussed on objectives of GRC 2018 Total -14 Project staffs, Alignment and formation, Contractor and ESMU site clearance Its role and responsibilities and project implementation modality and procedure, site clearance  18 2075/08/10 Male-23 Ward Chairperson, Coordination Parbat, Bihadi-1  The alignment proposed by 26th Nov, Female-2 Local people, PAFs, committee local does not seem feasible 2018 Total -25 Project staffs, meeting for technically and economically, Contractor and ESMU GRC formation then to address the issues : Alignment meeting have concluded for Shift and land discussion on compensation compensation amount of land in next under TL meeting. 19 2075/8/21 Total -13 Project representative, Demanding the AP 41d and AP 42  Conducted community 7th Dec 2018 Male-13 ESMU unit Butwal, grievances AP Galyang-5, Syangja consultation meeting, Female-0 Contractor, PAFs and Tower &  Giving information about Social intellectual Alignment project and trying to maximum persons. shifting from compensation of cultivation cultivation land. land by project.

20 2075/8/23 Total -12 Ward chairperson, Demanding the AP34-AP35 Bihadi-3  Conducted community 9th Dec 2018 Male-11 ESMU unit Butwal, AP Tower & Ranipani consultation meeting, Female-1 Contractor, PAFs and Alignment  Giving information about Social intellectual shifting from project. persons. purposes  Retry to shifting the alignment residential plot way if technically possible, which has  Trying to maximum joined the compensation of purpose lokmarg residential plot according to land acquisition act.