ADMINISTRATION REPORT 2009

PREPARED BY

PLAN IMPLEMENTATION BRANCH IRRIGATION DEPARTMENT

CONTENTS

Page1

Introduction 1 - 2

1. Organization 3

2. Administration 3

3. Overall programme 3 – 5

4.1 Plan Implementation 5

4. Regional Development & Construction Sub Department

5.1 Major Irrigation Schemes 6 – 12

5.2 Medium Irrigation Schemes 13-14

5.3. Procurement Branch 15

5.4 Machinery & Work shop Branch 16

5.5 World Bank Funded Dam Safety & Water Resources Planning Project 17

5.6 Works General 18

6. Specialized Services & Training Sub Departments

6.1 Hydrology Branch 19 – 20

6.2 Engineering Geology Branch 20

6.3 Engineering Materials Branch 21 - 24

6.4 Land Use Division 24- 25

6.5 Hydraulics Branch 25 - 26

6.6 Computer Services Branch 27

6.7 Training Branch (Local & Foreign Training) Annex 3 & 4 27

7 Irrigation and Water Management Sub Department 27 - 33

8 Assets Management Sub Department

8.1 Assets Management Division 34

8.2 Dam Safety Branch 35 – 36

9 Planning and Designs Sub Department

9.1 Water Resources & Project Planning Branch 36 – 39

9.2 Design Branches 40 – 41

9.3 Geo Informatics Branch 41

10. Environment, Drainage & Flood Protection Sub Department

10.1 Environmental Studies Branch 42 – 47

10.2 Drainage Branch 47 – 50

11. Human Resources Branch ( Staff Position ) Annex 1, 2 and 5 50

12. Finance Branch 50 – 53

13. Contract Branch 53

14. Administration Report – Regional Level 55- 108

15. Annexes 1,2,3,4 and 5

IRRIGATION DEPARTMENT

ADMINISTRATION REPORT FOR 2009

1.0 Introduction

The Irrigation Department with over a century of experience as a pioneer organization responsible for most of the development works in the irrigation sector, looks optimistically towards the development envisage in the water sector at the dawn of the new millennium.

1.1 Vision

"Not let a single drop of rain water flow to the sea without first being used for the welfare of mankind"

King Maha Parakramabahu the Great

1153-1186AD

The Vision of the Irrigation Department probably must have emerged from the vision of the great hydraulic civilization which existed from 500 B.C. to 1200 A.D. Despite the fact that this vision might look very optimistic in today’s context, the mission of the Irrigation Department emerged with this broad objective in view. Therefore the Irrigation Department emerged as the principal government organization responsible for the regulation and control of Inland waters.

1.2 Mission

The Mission of the Irrigation Department is to ensure optimum utilization of Water Resource for enhancing the living condition of the farming community of the country and all other uses of Water Resources in sustainable, productive, equitable and environment friendly manner with due attention to conservation of Water shed areas. Hence the Irrigation Department is responsible for planning, design, construction, operation ,management, rehabilitation and efficiency improvement of all major and medium Irrigation schemes and works related to flood control, drainage and salinity extrusion.

1.3 Objectives

The main objectives of the Irrigation Department are as follows; a) Development of land and water resources for Irrigated Agriculture, hydro power, flood control, Domestic Usage, Industrial usage and Aquaculture development, giving priority to the environmental factors.

b) Provision of Irrigation Drainage and salinity exclusion facilities for cultivable lands in Irrigation and Drainage Projects. Provision of salinity exclusion schemes. c) Provision of flood protection and drainage facilities to lands affected by floods. d) Alleviation of poverty of the rural farming community by increasing their farm income and raising their standard of living. e) Management of Water economically for sustainable Agriculture and other uses. f) Productivity enhancement of Land and water in Major/Medium Irrigation Schemes. g) Integrated water resources Management and Participatory Management in Major /Medium Irrigation systems.

1.4 Functions of the Irrigation Department

The functions of the Irrigation Department arising from the objectives are as follows;

a. Preparation of Master plan for development of the different river basins for the optimum utilization of land and water resources giving priority to the environmental factors.

b. Project formulation and detail designs of Irrigation, Hydro-power, Flood control and Reclamation Projects.

c. Construction of Irrigation and Settlement Projects for the conservation, diversion and distribution of water under gravity and lift Irrigation to new and existing land for cultivation by farmers for an enhanced food crop production and to upgrade their living conditions.

d. Construction of Drainage, flood protection and salt water exclusion projects for the protection of cultivable land to enable the cultivation of such lands with rainfall for food crop production with minimized risk.

e. Providing Drainage and flood protection facilities to minimize or mitigate the damages caused by floods.

f. Operation, Maintenance, Improvements, Rehabilitation and Water Management for Medium and Major Irrigation Schemes., Drainage and flood protection scheme and salt water exclusion schemes for optimum productivity enlisting the participation of beneficiaries. Catering of water for Inter Sectoral use, domestic, industrial use and environmental requirements. Construction and maintenance of Conservation .

g. Maintaining and upgrading the water infrastructure including dams for sustainable water supply to agriculture and domestic purposes.

h. Research in Hydraulics, Hydrology, Soil Mechanics, Engineering Geology, Geographic information System (GIS), Engineering Materials and Land Use as applied to water Resources Development Projects.

i. Human Resources Development for optimum utilization of Human Resources.

1 j. Operation and Maintenance of Financial Management system, Accounting, Reporting, Auditing systems of Irrigation Department in accordance with the financial Regulation of the Government of .

k. Providing Consultancy Services to government department, Statutory Boards/Corporation, public and private institutions and individuals; in the fields of Water Resources Development; Foundation Engineering; Quality Control of Earth work and Concrete; Hydraulic Model Testing and Land Use Planning.

2.0 Organization

The Head of the Irrigation Department is the Director General of Irrigation and Eight ( 8 ) other Directors manage the Sub-Departments. These Sub-Departments are ,

1. Regional Development and Construction (RD&C)

2. Specialized Service & Training (SS& Tr.)

3. Irrigation & water Management (I&WM)

4. Assets Management (AM)

5. Plan Implementation (PI)

6. Planning & Designs (P&D)

7. Finance(F)

8. Human Resources (HR)

In addition there was one Senior Deputy Director to cover up the area of Environmental, Drainage & Flood Protection. Further there are separate Project Directors for Weheragala Project, Project and PEACE Project.

Fourteen Regional Office with Regional Directors in charge and forty eight Divisional Irrigation Engineers cover the entire Island in maintaining all major and medium irrigation schemes and rehabilitation activities. Irrigation Training Institute at Galgamuwa is considered as one of the Regional Office for the purpose of document deal, and conduct in service training for the department personnel as well as providing training for other agencies. Director, Irrigation Training Institute is the in charge of the Institute.

Four Mechanical Engineering work shops are functioning at Ratmalana, Rambewa, Halpatota and Ampara headed by Mechanical Engineers and these workshops are being supervised by the Deputy Director, Machinery & Workshops from the head office.

Organization Chart of the Irrigation Department is shown in Annex 01.

3.0 Administration

Eng. H.P.S.Somasiri was the Director General of Irrigation for year 2009 .The key staffs of the Irrigation Department are shown in the Annex 2 and the present strength of the Irrigation Department in all categories is shown in the Annex 3.

4.0 Overall Programme

The Sub Departments and other supporting Branches carried out the programme of the department during the year 2009. These activities can be broadly categorized as follows.

2 1. Feasibility studies of major and medium irrigation schemes.

2. Activities of specialized divisions.

3. Major construction projects under foreign funds..

4. Major construction projects under consolidated funds.

5. Improvements and maintenance of major irrigation schemes and irrigation system management

6. Work done by the department for other organizations.

The total financial allocation for capital expenditure for the year was Rs .2,358.97 Million and Rs. 2,215.08 Million was spent during the year. Detailed account of the progress of individual items is given below with a brief description of the items and present financial and physical position of work.

Summary of Capital Expenditure

Allocation for Cumulative Progress against Name of Project Year 2009 expenditure for Allocation 2009 /Rs.’000 Year 2009/ Rs.’000 ( %) 1. Project 1 (Sub Total) 24.34 22.52 92.52% Administration and Establishment services

2. Project 2 ( Sub Total) 761.55 700.86 92.03% Administration and maintenance of Irrigation schemes

3. Project 3 - Major 1362.08 1,297.26 95.24% Irrigation Schemes

4. Project 4 - Minor 211 194.44 92.15% Irrigation Schemes

Grand Total 2358.97 2215.08 93.90%

A brief explanation of the programme during the year is presented below. The Planning & Design branch concentrated on physical planning of irrigation works and has the responsibility of Planning & Design. (PD)

Under consolidated fund, the following items were approved in the budget for Construction & Rehabilitation as Major and Medium Irrigation Schemes and these schemes were new works, improvements or the rehabilitation of existing irrigation works. These works were implemented under the supervision of the Regional Development and Construction Sub Department. (RD & C).

Major irrigation Schemes

1. Deduru Oya 2. Manik Ganga Reservoir (Weheragala) 3. Rambukkan Oya Reservoir 4. Lower Uva Project 5. Lunugamwehera Scheme ( KOISP tract 1) 6. Ella Pothana Anicut 7. navodaya 8. Essential Rehabilitation in selected Major Irrigation Schemes Medium Irrigation Schemes

3 1. Wahal Kada Tank 2. CIADP 3. Minipe Main Canal 4. Maha Halmillawa wewa 5. Muthukeliyawa Anicut Extension 6. Wemedille Reservoir 7. Kekeiri Obada Reservoir

8. Hekitta Minor Flood Protection Scheme 9. Janaranjana wewa 10. Rehabilitation of Ural Oya 11. Ella Wewa Amuna 12. Hettige Ela 13. Wewlanda Wewa 14. Gurugal Oya project 15. Sugaladevi Wewa The improvements and maintenance of capital assets the work comprised of providing additional safety for dams, irrigation systems management, operation of irrigation schemes, maintenance of all major irrigation schemes, buildings, machinery, vehicles, etc. fall under the purview of Assets Management Sub Department.

The total numbers of Gravity and lift irrigation schemes maintained by the Department were 333, consisted of gravity irrigation schemes, lift irrigation schemes and Gravity irrigation works covering a total extent of 283,773 ha. The extent under lift irrigation works was 2040 ha. And 29,840 ha. were under drainage, flood protection & salt water exclusion schemes.

A detailed account of works carried out by the different Sub departments and branches during the year

4.1 Plan Implementation Branch

Functions of the Plan Implementation Branch

• Preparation of the Capital Budget and the long term financial and physical programmes of the Department for successive years.

• Preparation of Implementation programme according to the guidelines given by the Plan Implementation Ministry at the beginning of each financial year.

• Monitoring of monthly implementation programme during the year according to the master programme prepared at the beginning of the year.

• Submission of progress reports in the required format to the Ministry of Irrigation & Water Management, National Planning Department and to the Ministry of Plan Implementation.

• Preparation of Administration reports, Performance Reports and Annual plans.

The works carried out by Plan Implementation branch during the year 2009 is as follows.

• Preparation of Monthly Financial and Physical Progress reports for 2009.

• Preparation of Annual Budget for 2010.

• Preparation of Performance Report for the year 2008.

4 • Preparation of Project Proposals for 2009.

• Preparation of Administration Report for 2008.

• Preparation of Quarterly progress reports for GOSL funded projects

5. Regional Development & Construction Sub-Department

5.1 Major Irrigation Schemes

5.1.1 Deduru oya Reservoir Project -Kurunegala

5.1.1.1 Introduction

The Deduru Oya is the fourth largest river in the country flowing through Kandy , Matale, Kurunegala and Puttalam Districts. The river originates from the Western slopes of the Kandy Matale Hills. Catchments area of the river is 2620 sq.km. Annual discharge of the river is more than 1000 MCM. About 90% of the Deduru Oya catchment area comes under intermediate zone and rest of the area in mountainous region falls under mid country wet zone.

Deduru Oya and Mee Oya are two adjacent river basins located in the North Western Province. More than 80 percent of the water resource in the water deficit Mee Oya basin is utilized for cultivation. But in the Deduru Oya basin much of the water resource has not yet been utilized. Lands in the Deduru Oya basin are almost developed and lands in the Mee Oya basin yet to be developed. Therefore it is planned to exploit the Deduru Oya water resources in improving the cropping intensity of existing agricultural lands under minor irrigation schemes and to develop new lands in the Mee Oya and the Deduru Oya basins in view of enhancing productivity.

The project envisages construction of a 75 MCM reservoir across Daduru oya, 300 m upstream of existing Redi Bendi Ella Anicut

5.1.1.2 Project Benefits

5.1.1.2.1 Irrigation benefits

LB Main Canal

Augment irrigation water supplies through a network of canal system to 2400 ha. of paddy lands under minor irrigation systems and to develop 300 ha. of new high lands in initials reaches of the proposed LB main canal for OFC cultivation under lift irrigation in Deduru Oya left bank. Cope with under small tanks. Improve the cropping intensity up to 2.0.

Ridi Bendi Ela / Magalla wewa

Augment irrigation water supplies to existing agriculture lands under Ridi Bendi Ella / Magalla Reservoir System and provision of irrigation water to 600 ha. of stage 2 area of the Magalla Reservoir scheme by extending the existing right bank canal system.

R B Trans basin canal

Augment irrigation water supplies to 1000 Ha. of existing agricultural lands under minor irrigation systems and 300 Ha. under lift irrigation along the trans-basin diversion canal of the Deduru Oya Reservoir.

RB Trans basin Canal / Me Oya basin

Augment irrigation water supplies to 3715 ha. of existing agriculture lands under major/medium irrigation scheme in the basin,via a trans-basin diversion to Inginimitiya Reservoir.

Providing irrigation water to 3400 ha. of new and existing lands in the lower reaches of the Mi Oya basin under the Tabbowa scheme and stage 1 and 2 of the Radavi Bendi Ella Anicut scheme.

5 5.1.1.2.2 Power Generation, Drinking Water & Flood Control benefits

Hydropower station with the installed capacity of 1.5 MW (3 units of 0.5 MW capacity) will be located just downstream of the reservoir using irrigation and environmental release from the proposed reservoir.

Supply drinking water to 50,000 families in Kurunegala and Puttalam Districts. Improve drinking water quality. Recharge Ground Water Aquifers - Improve water table. Enhance Micro Climate conditions

Regulate river flow in rainy seasons and minimize flood risk and river bank erosion at the lower reaches of the river.

5.1.1.2.3. Economic, Social & Infrastructure benefits

• Increases Gross Domestic Production.

• Improve livelihood practices/ living standards/ prevent youth unrest.

• Rural development towards reduction of demographic transition.

• New / additional rural road network will be provided for linking villages.

• 15,000 farmer families will directly be benefited by the project while over 50,000 families will indirectly be benefited by getting drinking water and gaining new employment opportunities etc.

5.1.1.2.4. General

At the Spillway and the Bund construction sites, there are more than 150 skilled and unskilled labourers are engaged in different activities. These labourers are from nearby villages and earn 12,000 to 15,000 rupees per month. The project is spending nearly 2.0 Mn rupees per month to pay their wages and thus enhances the personal income level.

Vehicle owners living in the area got opportunity to deploy their small dump trucks and tractors at the work site and thus earn additional income.

More than 15,000 of students from Schools, Technical Colleges and Universities visited to the Project site and gained knowledge about the Irrigation Development Project activities.

Large number of trainees, from Universities and Technical Colleges, in various disciplines gained opportunity to develop their skills by contributing to the project activities.

A few employment opportunities have been provided to qualified personnel for performing task base duties in the work categories of Engineer, Engineering Assistant, Draftsman, Management Assistant and Supervisor.

5.1.1. 3. Project Cost and project Period

This project was commenced in year 2007 and expected to be completion in 2012 at a cost of Rs. 6200 Mn local funds.

5.1.1. 4. Progress of the project

Total Estimated cost - 6200 Mn.

Allocation for year 2009 - 700 Mn.

Expenditure up to end of 2008 - 698.94 Mn

Expenditure during 2009 - 699.95 Mn.

6 Total expenditure upto end of 2009 - 1398.89 Mn.

Overall physical progress - 22.85%

Overall financial progress - 22.56%

Deduru Oya – progress of constructions

Construction of LB canal Construction of Bund

Construction of LB Sluice Construction of Spillway

Construction of Spillway Construction of causeway

7

causeway Tank Bund

5.1.2. Rambukkan oya Reservoir -Ampara

5.1.2.1 Introduction

Proposed Rambukkan oya Reservoir and Irrigable area of the project is located in the Mundeni Aru River basin in Ampara District in the Eastern Province. The scheme is sited at Watawalakandiya across the Rambukkan Oya and is located by the coordinates J (5.9 x 8.5). The tank bund is across the Rambukkan Oya midway between Pollebedda and Kurunduwinna villages in the Bintenne Pattu North in the Ampara district.

The area is presently sparsely settled, and lack of roads, schools, health services and other civic amenities. Presently less than one percent of the land area is utilized and the people practice slash and burn rain fed agriculture. About 2,000 landless families have been proposed to be settled under the scheme.

The construction of earthen dam, tower sluice, spillway and irrigation canals etc. are the main construction activities under this project. Construction of roads and land clearing and land leveling are the some of the social elements to be undertaken under the project.

Resettlement aspects of the project will include training of farmer in irrigated agriculture, development of proper water management, development of communities, provision of health services and schools.

5.1.2.2. Project period

This project was ceremonially commenced on the 12th February ‘2007 and expected to be completed in December 2010 at a cost of Rs.2500 Mn local fund.

5.1.2.3 Progress of the project

Total Estimated cost - 2500 Mn. Allocation for year 2009 - 390 Mn. Expenditure up to end of 2008 - 328.15Mn Expenditure during 2009 - 348.44 Mn. Total expenditure upto end of 2009 - 676.59Mn. Overall financial progress - 27.06% Physical progress of items - 49% Construction of Dam a) 85.7% of core trench was excavated and cement grouting works were completed by the Geo technical Branch. b) 90% of clay filling in core trench was completed, and earth filling in dam was in progress including the construction of toe filter. c) 47% of toe filter construction was completed

8 Construction of Tower sluice a) 67.5% of the construction works were completed for the tower sluice

Construction of Radial gated Spillway a) 90% of soft and hard rock were removed and the cement grouting at upstream transition was already commenced. b) The overall progress was about 14.5%

Reforestation

The maintenance works on 120 Ha of forest area were being carried out in the villages of Galwalyaya, Mahawewa and Tangaltalawa by the Forest Department as per the condition laid down in the EIA report.

Archaeological conservation work

Archaeological conservation works were being carried out by the Archaeological Department. Providing of 160KVA 33KV/LT electricity supply to Rambukkan Oya Project area 99% of 3-Phase supply to the camp and dam site was completed and power supply provided. Investigation on Main channel of 6.7 Km length

The site survey investigation, the work related land acquisitions were completed.

Quality Control on Construction works

The Engineering Materials Division was engaged on overall quality control and quality assurance works.

1. Construction of tower sluice-cut off wall 2. Construction of tower sluice-tower

3. Construction of Dam-Toe filter 4. Construction of Dam-Earth filling

9 5.1.3 Menikganga Reservoir Project (Weheragala)

5.1.3.1 Introduction

Manik Ganga is one of the major rivers of southern quadrant of . This basin is the one of the least developed river basins in Sri Lanka and more than 50 % land is undeveloped. In Manik ganga basin there is no major storage reservoirs across Manik Ganga and only few anicuts are available.

In the adjoining basin , it has a catchment area of an 1178 sq km and most of the water in this river regulated at Lunugamwehera reservoir, which has a capacity of 222 MCM from the total annual average flow of 240 MCM in Kirindi Oya very little water escape to the sea. This reservoir suffers due to shortage of water and there is an annual deficit of about 100 MCM of water to cultivate 10000 Ha of agricultural lands. The project envisages to regulate about 80% of water available in Manik Ganga at Weheragala by constructing an environmental friendly reservoir with a water way conveying about 64 MCM of regulated water to water deficit Kirindi Oya basin while releasing about 30 MCM of regulated water down Manik Ganga.

5.1.3.2 Project details and Benefits

Gross storage - 75 MCM Dam Type - Homogeneous Earth Fill Length of Dam - 2031 m Spill way - Radial gated Sluice - Concrete Tower Length of main canal - 22.35 km

The proposed project period - 2005 to 2008 Extent benefited - 5000 ha. Benefited farmer families - 5000

5.1.3.3. Progress of the projects

Total Estimated cost - 2900 Mn. Allocation for year 2009 - 150 Mn. Expenditure up to end of 2008 - 1710 Mn Expenditure during 2009 - 131 Mn. Total expenditure upto end of 2009 - 1841 Mn. Overall Financial Progress - 63.48%

Overall physical Progress - 100 %

5.1.4. Lower Uva Project

5.1.4.1 Introduction

10 This project is proposed to augment one medium tanks namely Debara Ara Wewa in Wellawaya Divisional Secretary Division and about 22 minor tanks including Gal Wewa, Kolombawatta Wewa, Watagala Ara Wewa and Uruhore Wewa by extending the feeder canal from Ussalla anicut to Balaharuwa Tank and constructing new feeder canal from Balaharuwa Tank to Debara Ara Wewa.

Earth work on bund and LB canal of Gigiri Ella Stage 11 was completed this year. Earth work in LB canal of Danagiriya Sandella and Balaharuwa feeder canal is in progress. Earth work on Bund and main channel work of Hodalkumbura tank also completed. Concrete works in Wepathdeniya tank main channel and Head works of Radaliyadda Aswedduma tank were completed.

5.1.4.2. Progress of the projects

Estimated cost - 550 . Mn. . Expenditure up to 31 Dec 2008 - 9.67 Mn. Allocation for year 2009 - 30.41 Mn Expenditure from Jan. to End of December 2009 - 30.41 Mn Total expenditure upto end of 2009 - 40.09 Mn. Overall Financial Progress - 7.28 % Overall Physical Progress - 12 % 5.1.5. Ellapothana Wewa

5.1.5.1 Introduction

The proposed anicut is to be constructed across about 24 km down stream of existing Illukwewa anicut. It is proposed to augment the existing tanks on both LB and RB sides of the Yan Oya River. In the LB canal it is proposed to augment Wedigawewa, Elapatwewa, Wilewewa, Kudawewa and Thirappankadawalawewa. In the RB canal it is proposed to augment Ellapothana- Siyambalawewa and Wahagahapuwewa and to be constructed along the existing Yoda Ela which is now in completely abandoned state. The total area to be benefited by this proposed scheme is 625 Ha .

5.1.5.2. Progress of the projects Estimated cost - 300 . Mn. Extent benefited - 625 Ha. Benefited farmer families - 1038 Expenditure up to 31 Dec 2008 - 10.55 .Mn Allocation for year 2009 - 31.5 Mn Expenditure up to the end of December 2009 - 31.27 Mn Total expenditure upto end of 2009 - 41.83 Mn. Overall Financial Progress - 13.94 % Overall Physical Progress - 17.%

5.1.6. Other Major Projects

Overall Current Year Progress physical ( Rs. Mn.) Project Name District progress to end of Dec. 2009 Total Exp. To TEC/Mn Allocation 2009 ( %) end of Dec. Galoya Navodaya Ampara 1260 38.3 38.3 8.6 Lunugamwehera Scheme Hambantota 90 7.47 6.54 8 Essential Rehabilitation in selected All District 1000 14.4 11.3 1.13 Major Irrigation schemes

5. 2.Medium Irrigation Projects.

11 Cum. Current Year Progress Progress ( Rs. Overall ( Rs. Mn.) Mn. ) physical Project Name District progress to end of Dec. Allocation Total Exp. To TEC 2009 ( %) 2009 end of Dec.

Improvements to wahalkada Anuradhapura 60 3.30 3.233 100 CentenaryIirrigation Accelerated Development Programme All Districts 500 11.00 8.894 99 ( CIADP) Mahahalmilla Polonnaruwa 61 1.03 0.250 99 Muthukeliyawa Anicut Monaragala 77 4.00 3.157 80 Wemedilla Reservoir Matale 300 17.57 16.938 99.5 KekiriOboda Reservoir Hambantota 445 103.22 103.217 91.5

Hekitha Minor Flood Protection Colombo 53 2.25 0.000 20

Janaranjana Wewa Trincomalee 53 15.50 14.933 100

Gurugaloya Project Kandy 400 11.73 11.485 18

Sugaladevi Wewa Monaragala 119 18.00 15.444 99

Wawelanda Rathnapura 55.25 7.00 4.469 96

Kirampunchennai Anicut Batticaloa 40 0.70 0.000 25

Minipe Main canal Kandy 12.8 5.10 2.719 55

Ural Oya Colombo 34 4.00 3.753 93

Ella Wewa Amuna Anuradhapura 31 3.40 3.378 100

Hettige Ela Colombo 42 2.50 1.962 75

Medagama Gonagama Kurunegala 22.5 0.70 0.599 100

Kekiriobada Reservoir

12 Construction works at Gurugal oya Project

Construction works at Ellapothana Anicut

13 5.3 Procurement Branch

Registration of Suppliers & Services

During the year 2009 in response to advertisements published in the State News Papers, 338 Applications were received and out of them 323 had been registered under 67 categories.

Commodities Processed & Procured by the Head Office Procurement Branch.

No Project & Unit Description of Items Com.E T & T OE DRM LE C&M DRE HE Cost in ( Rs.) 1 Head office 34 Nos 68 Nos 20 Nos 9,597,344.46 2 Hydrology - 04 No.s 2,591,668.80 3 CDOA 13 Lots 1,362,053.00 4 Eng. Geology - 05Lots 2,846,737.60 5 ITI, Galgamuwa 02 Nos 139,299.87 6 Eng. Materials 01 No 262,990.47 7 RDI-Ampara 02 Nos 125,944.80 8 Nilwala ganga Project 02No.s 55,425.01

Grand Total 16,981,484.01

T & T - Tyre & Tube

OE - Office Equipment

SE - Survey Equipment

Com - E - Computer Equipment

DRM - Drawing materials

DRE - Drilling Equipment

LE - Laboratory Equipment

C & M - Construction Machinery

EM - Engineering Materials.

V - Vehicles

SP - Sheet piles

H.E - Hydrological Equipment

5.4 Machinery and Work Shop

Machinery and Workshop Branch is functioning under Director of Irrigation (Regional Development & Construction), Deputy Director (Machinery & Workshop)

Main responsibilities of the Branch are as follows,

• Repairs, maintenance and up keep of vehicles, machinery and equipments attached to the department . • Repairs, maintenance and up keep of mechanical structures such as radial gates, sluice gates etc. • Repairs, maintenance and up keep of pumps attached to the lift irrigation systems. • Preparation of specification for the procurement of plant machinery and equipment for the Department.

14 • Administration of the Mechanical staff at the Department • Financial control over the workshop and repairs to vehicles, machinery and equipment in the Department.

Revised Allocation and Progress of the Repairs for the Year 2009 are as follows.

Vote particular/ Allocation Expenditure Remarks Description Received

282-02-2-2-2003 21,250,000.00 19,452,631.96 100 Nos Vehicles Repairs to vehicles

282-02-2-2-2002 15,300,000.00 13,390,066.84 60 Nos Machinery Repairs to machinery & equipment

282-01-01-01-2003 (ii) 0.00 1,290,614.56 H.O.Vehicles Repairs to vehicles

282-01-01-01-2002 (ii) 197,000.00 86,594.70 Machinery Repairs to machinery & equipment

282-02-2-2-2103 (ii) 40,000,000 40,346,307.16 04 No.s Machinery Purchase of machinery

282-01-01-01-2001(ii) 04 No.s Mechanical 2,000,000.00 1,250,553,32. Improvements to Work Shops. mechanical Workshops

5.5 World Bank Funded Dam Safety & Water Resources Planning Project (DSWRPP)

Separate Dam Safety Construction unit formed to implement the Rehabilitation works of Major tank on 01st August 2009, under Director of Regional Development and Construction.

Under the component of the Dam Safety and Operational efficiency of DSWRPP the expected outcome would be to enhance safety of selected major dams, and sustainable institutional arrangement for effective dam safety management and efficient O &M. This would be achieved through

• Dam Rehabilitation and Remedial works to 16 selected Dams. • Providing Basic Safety Facilities for 49 Dams

15 • Improvement of O & M practices for 16 Rehabilitated Dams • Special Studies on Safety of Senanayake Samudraya Dam • Institutional Strengthening of Dam O & M Staff

POYRY Consultant visited to finalize project proposals, preparing estimate and tender document

Finalized estimated for following schemes were submitted by respective IE division to Dam Safety Branch and from their checked & forwarded to POYRY Consultant, • Kantale Dam • Inginimitiya Dam • Parakkrama Samudraya Dam

The consultant (POYRY) had inspects schemes & proposals they are preparing the estimates for following 13 schemes.

• Nuwarawewa Dam • Tissa wewa Dam • Huruluwewa Dam • Nachchaduwa Dam • Rajangana Dam • Ridiyagama Dam • Nalanda Dam • Usgala Siyabalangamuwa Dam • Kaudulla Dam • Minneriya Dam • Girithale Dam • Tabbowa Dam • Vendrason Dam

5.6 Works General Branch

Duties assigned to the section can be classified as follows.

• Reservation of accommodation in field circuit bungalows in Range offices which are managed by the head office • Upkeep and maintenance of PABX inter communication services including departmental telephone directory. • Provision of garage facilities for departmental vehicles attached to head office staff and private vehicles of head office staff. • Provision of approval for social activities within the head office premises organized by the welfare society and for Auditorium facilities for different departmental activities. • Checking of holiday payment vouchers of all staff and field officers in the department for DGI’s approval, • Organizing yearly special forums such as RDI’s conferences. World water day etc. • Miscellaneous matters cannot be assigned under the functions of other branches such as Parliamentary consultancy committee matters, Public petitions committee matters etc.

The following works were carried out during the year 2009

• Replacing of old Panasonic 333 internal telephone system of all buildings in Head office premises by a new telephone system with a cost of Rs. 1,785,620.00 for 198 ports. • Fixing of new Air condition machine to the PABX room. Cost was Rs. 76,680.00 • Responses to the petitions received can be classified as follows.

16 Ministry / Department / Numbers Replied with Institution received solutions. Parliamentary consultancy 28 24 committee 02 01 Public petitions committee 60 50 Presidential office 155 80 Ministry of Irrigation & Water management 44 10 Other organizations/ farmers / etc.

Extension to Kaudulla Scheme under Moragahakanda Development Project

This is done under Moragahakanda Development project to resettle the displaced people under Moragahakanda project. Following items are handled by the Irrigation Department under the Irrigation infrastructure Development to extend irrigation facilities of 4000 acs. Of additional land.

• Preparation of Blocking out plans & soil classification maps for newly identified areas. • Widening of existing left bank main canal ( 6km) • Investigation and construction of 23 km of new branch canal • Improvements to 30 nos minor tanks and 30 km of distributory & field canals including all necessary structures

All construction work to be completed by the end of year 2014 and it has been proposed to start settling from end of 2012. As estimate was approved for Rs. 204 Mn. for the year 2009 and the total cost estimate is not finalized.

Progress of Work under Irrigation Department in 2009

• Blocking out of the irrigable area and Soil Classification maps were completed. • Construction of 2 minor tank were started and 60% of the bund earth work was completed • 50% of the earth work in Widening of 1st km of L/B main canal was completed

6.0 Specialized Service and Training Sub-Department

6.1 Hydrology Branch

This Division deals mainly with collection storage, analysis and dissemination of Hydrological data, Hydrology, which treats all phase of surface water is a subject of great importance for people and their environment. The following Hydrological data is collected from the field.

1. River water level 2. Rain fall 3. River flow discharge 4. Evaporation 5. Sun shine records 6. Wind Velocity 7. Wet & dry bulb temperature 8. Sediment sampling and bed- load sampling.

Above data are processed, analyzed and published for the use of planning of Water Resources Development of the country. Another main aspect of the division is flood forecasting in the areas vulnerable to floods Kelani ganga, , Gin ganaga,

17 Nilwalaganga, Deduru oya and Attanagalu oya are highly vulnerable to flood. Preparation of flood hazard maps for these areas the new responsibilities entrusted to this division.

6.1.1 Hydro – meteorological Net work

In 2009 Hydrological Stations maintained by this division can be categorized as follows depending on the equipments installed.

1 . No of River Gauging Stations - 88 Nos.

1.1 Gauging stations equipped with cable ways and winches for current metering - 11 Nos.

1.2 Gauging stations equipped with Automatic water level recorders(14 No are out of order) - 22 Nos

2. Rain gauging stations .

2.1 Automatic rainfall recorders ( Mechanical type) 03 Nos are out of order) - 08 Nos.

2.2 Automatic rainfall recorders (Electrical type) - 09 Nos.

2.3 Ordinary rain fall recorders - 42 Nos.

3. Evaporation pans ( 3 Nos are out of order) - 10 Nos.

4. Weather stations - 02 Nos

In most of the Main River Gauging Stations. Rain gauges are also maintained.

6.1.2 The following Gauging Stations are newly established during the year 2009

i. near Yatiella 6th mile post and Mandappan oya near Mallgama gauging station were established for Hydrological investigation for proposed Nakkala Reservoir Project.

ii. Punchivilaththuwa gauging station at Deduru oya was established for requirement of ADB assisted small towns and rural arid – areas Water Supply and Sanitation Project.

iii. Neelabemma gauging station at Kla oya was established for requirement of ADB assisted small towns and rural arid – areas Water Supply and Sanitation Project. New ordinary Rainfall records were installed at Noewood and Calidoniya in Basin.

6.1.3 Special Works during the Period of 2009

Civil construction works of cable way completed at Giriulla Gauging Station.

Taken over the telemetry system installed at Kithulgala which enable to read River water level from Head office at any time.

6.2 Engineering Geology Branch

The following works were carried out by the Engineering Geology Branch during the Year 2009.

6.2.1 Work done for the department

1) Drilling and grouting work at Deduru oya Project - Kurunegala Range 2) Drilling investigation at Attikkawa Anicut - Southern Range 3) Drilling investigation for proposed Kumbukkan oya reservoir - Moneragala Range 4) Foundation treatment at Gurugal oya dam axis - Kandy Range 5) Foundation treatment at RB axis and spill foundation at Rambukkan oya Project - Ampara Range 1. Drilling and grouting work at Deduru oya Project

This work was commenced on 2009-02-19 and completed on 2010-10-07. At this site307 No of bore holes were drilled and 252 boreholes were grouted. Total length of drilled was 3207.29m through the 1739.41m in overburden and 1467.88m in rock.384 bags of cement were used for cement grouting work.

18 2. Drilling investigation at Attikkawa Anicut

Drilling investigation at Attikkawa Anicut was commenced on 2009-02-26 and completed on 2009-03-28. At this site04 Nos of NX size drill hole were completed. The total depth of drilling was 54.80 m through the 15.72m in overburden and 39.08 m in rock.

3. Drilling Investigation for proposed Kumbukkan oya Reservoir

This work was commenced on 2009-7-27 and completed on 2009-10-01. At this site 05 Nos of N size drill hole were completed. The total depth of drilling was 138.66 m through the 4.53 m in overburden and 134.13 m in rock.

4. Foundation treatment at Gurugal oya dam axis

This work was commenced on 2009-08-12 and completed on 2009-10- 12 according to the DD (EG) instruction in the RB of the Dam Axis. At this site 32 Nos of bore holes with B & R sizes were drilled and grouted. The total depth of drilling was 159.0 m in rock. 30 bags of cement were used for grouting.

5. Foundation treatment at RB axis and spill foundation at Rambukkan oya Project

This works were commenced on 2009-10-07 and completed on 2009-10-22. At this site 81 Nos of drill holes done with A & R sizes in spill site, river level and bund axis 19 Nos. of bore holes were grouted. The Total depth of drilling was 390.93 m through the 98.26m in over burden and 292.67 m in rock. 43 Nos bags of cement were used for the grouting.

6.2.2 Work done for other organizations

1. Drilling Investigation for proposed Etambagolla bridge site. – Kulugaga project.

The works were commenced on 14-03-2009 and completed on 29-05-2009. At this site 4 Nos of drill holes done with B sizes on the RB of the bridge abutment. The total depth of drilling was 14.95 m through he 4.35m in overburden and 10.60 m in rock.

2. Drilling Investigations at level crossing I,II and the bridge across Nikkawathurawa Stream- Kaluganga Project

3. Geological Investigations at RB spill of Ethinikada wewa – Ampara Range.

The works were commenced on 15-05-2009 and completed on 01-07--2009. At this site 6 Nos of drill holes done with N size. The total depth of drilling was 43.85 m through the 18.51 m in overburden and 25.34 m in rock.

6.3 Engineering Materials Branch

6.3.1 Aims and Objectives

This branch provides a supportive service to the Irrigation Department as well as to other organizations such as Provincial Councils, Statutory Boards and Authorities, to assure the quality of works in following stages.

• Planning • Designing • Construction • Maintenance

6.3.2 The main activities performed under the above stages are:

• Foundation investigation for earthen dams (new and breached),channels, anicuts other irrigation related structures and Buildings. • Locating borrow areas for earthwork and selecting sources of materials for concrete structures ,filters and road works. • Designs of earthen dams, earth structures and foundations. • Performing quality assurance tests for concrete and earth works.

19 • Providing consultancy services to private sector and semi government organizations for site investigations and quality assessment in earth works and concrete construction.

6.3.3 The above four stages are can be as follows:

Planning

• Borrow Area Investigation to identify suitable fill material and the estimation of the quantity available. Performing laboratory tests on samples • Properties and parameters of available material at the proposed site and its locality Designing

Carrying out a design for a suitable embankment section and earth structures based on following aspects.

. Properties & parameters of available material . Data provided by the Designs, Planning Branch and Regional Offices. . Recommendation for foundation by the Engineering Geology Branch Construction:

Earth work

. Conditioning the borrow area to get the optimum moisture content. . Placing & compacting the fill material to the required degree of compaction

Cement /Concrete work

• Testing the quality of cement • Suitability test for coarse and fine aggregate • In- situ tests • Compressive strength test

Maintenance

Providing remedial measures after inspection for any reported / observed defects in Earthen and Concrete structures.

6.3.4 Investigations carried out during the year 2009

Soil investigations were commenced and carried out partially for the Batuwita ara tank in Galle RDI range.

Further, borrow are investigation for Deduru oya reservoir were carried out due to shortage of available material.

6.3.5 Designs undertaken/ completed during the year 2009

Elle wewa - Carried out stability analysis proposals were submitted

Parakrama Samudra Tank - Carried out filter design for remedial measures.

Yoda wewa - Carried out filter design for remedial measures.

Gurugal oya - Studies are undertaken.

Batuvita tank - Carried out stability analysis proposals were submitted

20 6.3.6. Quality Control of Major Construction Works

Quality control of following major construction projects , implemented by the Irrigation Department were carried out in addition to the normal quality control works.

• Weheragala Reservoir Project

• Deduruoya Reservoir Project

• Rambukkanoya Reservoir project

• Kekiriobada Reservoir project

Further quality assurance work of Moragahakanda Reservoir Project ,which is implemented by Mahaweli authority was also carried out by the Engineering Materials Division of the Irrigation Department .

6.3.7 Quality control works of other project

Quality control works of the following projects were also undertaken by the Engineering Materials Division.

• PEACE Project - Kurunegala & Anuradhapura districts and North and East provinces • NEIAP Project - North and East provinces • Uthuru Wasnathaya - Quality control works of Giants tank in Vavuniya • DS & WRP Project - Tri axial and material classification tests were carried out at the Central Laboratory under this project for the following tanks. 1. Kandalama Tank 2. Kalawewa 3. Chandrika wewa

Field and Central Laboratory Tests carried out during the year 2009

Central Laboratory

SOILS Particle size Distribution test 191 Index Properties test 147 Dry Density /Moisture Relation ship test 54 Specific gravity test 25 Tri- axial Shear Test 16 Coarse Aggregates Gradation Test 01 Soundness Test Aggregate Abrasion Test 02 Fine Aggregate Gradation Test 02 Concrete Comparatives strength of tests cubes 42 Total 480 Field Laboratory Tests:

21 FIELD Laboratory Soil Test pits 472 Practical size Distribution test 08 Soil Index Properties test 17 Proctor compaction Test 326 In-situ Density Test 1964 Permeability Test 18 Maximum & minimum density of sand 05 Relative density Test 09 Moisture content test 129 Concrete Gradation test ( fine Aggregate) 200 Gradation test ( coarse Aggregate) 196 Slump test 637 No of cubes casted 2644 No of cubes tested 2573 Total 9198

Expenditure during the year 2009

ITEM /Vote Particulars Allocation(Rs. Expenditure(Rs. Mn) Mn_) Engineering materials studies 1.950 1.949 282-2-2-2502-11-3-5 Testing materials & Equipments 5.0 0.673 282-2-2-2103-11-2 Exhibition & Publicity 2.0 0.898 282-2-2-2502-11-4-7

6.3.8. Exhibition and Publicity

Irrigation Department participated in exhibition and other publicity programs in several areas in Sri Lanka. The main objective is to make the public aware of the functions of Irrigation Department, achievements, benefits to the public of on going and proposed irrigation projects. Further, Specialized Branches of the Irrigation Department made special attempts to educate the school and university students and the public, of the irrigation related models, structures, materials and some data. “Deyata Kirula”National Development Exhibition is a typical example.

6.3.9. Expenditure during the year 2009

Item Vote Particulars Allocation (Rs. Mn.) Expenditure (Rs. Mn.)

Engineering Materials Studies 282-02-2-2502-11-3-5 1.950 1.949

Testing Materials & Equipments 282-02-2-2103-11-2 5.000 0.673

Exhibition & Publicity 282-02-2-2502-11-4-7 2.000 0.898

6.4 Land Use Division

This Division provides a supportive service to the Irrigation Department and other Government and private organizations by preparing maps and other reports of land suitability for irrigated and rain fed agricultural practices and other purposes as well.

During the year 2009 the following works were carried out.

22 6.4.1. National Soils and Land Use Surveys

Under this survey programme low intensity soil survey were conducted in the following District.

District Total cost Completed Area Gampaha 10,000 ha 1.03 Mn. Hambantota 10,000 ha.

Provincial Soil legends and draft soil maps of the surveyed area were prepared. The result of soils and lands used studies may be used in projects identification, feasibility studies and detailed planning of projects and in regional land use planning.

6.4.2. Moragahakanda Development Project Kaudulla Area - Tracts 1,2,3,4 and 7

On a request made by Mahaweli Authority (MASL) soils and land use studies were conducted in track 1,2 3,4 and 7 covering on extent of approximately 3300 ha. at medium intensity level for land use planning for making crop recommendations and for detailed designing of the canal system.

The land evaluation map indicating the land use recommendations for tract 2,3,4 and 7 were submit to the Irrigation Department for canal designing and blocking out. The land evaluation maps for track 1,2,3,4, and 7 were submitted to Mahaweli Authority of Sri Lanka.

6.4.3. Soil and Land Use Survey in Giant’s Tank – Mannar

Under the project of Uthuru Wasanthaya the Regional Director of Irrigation Vavuniya had requested to conduct Soil Investigation for making crop recommendation in Manner and . The detail soil survey ( Medium intensity) was started in October from Giant”s Tank area in Manner District. 2800 ha. Of project area were surveyed during the year 2009 and this continues up to 2010.

6.4.4. Water Quality Assessment.

Water samples collected from proposed Urugamuwa, Samaradeniya and Kadukkana irrigation projects were tested for nutrients, alkalinity and turbidity. 18 No.s samples were analysed and reports were submitted to Environmental Division.

6.4.5. Laboratory Analytical Work

The following Laboratory analysis were made for soil samples collected from Kaudulla and Giant’s Tank area in Manner. Determination of PH .( sat.paste, sat.ext, 1:5 soil :water) EC ( sat.paste, sat ext, 1:5 soil :water) of 160 Nos of soil sample.

6.4.6. Map Production

Soil Cartography and Map Production Preparation of draft of medium intensity soil maps of track 2,3,4 and 7 Moragahakanda Kaudulla extension

6.4.7. Digital Map Production

Preparation of medium intensity soil maps of Moragahakanda Tract 2,3,4, and 7. Preparation of land evaluation map of Moragahakanda track 2,3,4, and 7

6.5 Hydraulics Research Branch

6.5.1 Physical model studies

Hydraulic Research Laboratory of the Irrigation Department carried out Hydraulic model investigations and field investigation for the Department and also provided consultancy services to the other organizations.

1. Hydraulic Scale Model Studies The design of a hydraulic structure is based on theoretical consideration with some assumptions. The results of model studies are essential for solving various problems of Hydraulic Engineering. Therefore proposed Rambukkan oya spillway and proposed Deduru oya spillway, scale model studies were referred to Hydraulic Research Laboratory. The aim of these studies is to determine the flow characteristics, operations etc. of the proposed spillway structures. The details of the studies are as follows.

23 a. Rambukkan oya Spillway

The required field data were collected. The construction of the scalar model to scale 1:35 was completed. The original design was tested and observations were made. Modification to approach channel is finalized.

b. Deduru oya Spillway

The required field data were collected. The construction of the model to scale 1:60 was completed. The preliminary tests for original design were completed.

Kalu Ganga Bank Erosion Protection Model Studies at Saman Devalaya

The study was undertaken the request of Basnayaka Nilame at Saman Devalaya through RDI ( Colombo). The aim of this study is to protect at Kaluganga River banks at Saman Devalaya. The required data for the model study was collected. The construction of the model to scale 1:30 was completed.

6.5. 2. Training Progammes Hydraulic practicals and training were conducted for student of Open University of Sri Lanka

6.5.3. Exhibitions

Hydraulic Research Laboratory section was responsible for preparation and display of the Department hydraulic stall for following exhibitions. All are successfully completed. • “Deyata Kirula 2009” • “50th Anniversary Exhibition” at University of Sri Jayawardhanapura. • “Soba Jathika Pradarsanaya” exhibition held at Viharamahadevi Park at Colombo. • “Sanyukta 2009” Exhibition held at Keppetipola Maha Vidyalaya at Gampaha. • :Efi 2009” Exhibition held at University of Peradeniya. • “Galu Samaya” exibition held at Galle Fort.

6.5. 4. Instrument Section

1. Repairing and Servicing of Survey equipment are as follow.

Range/ Division Nos. of Nos. of Theodolites levels I.E Murunkan 2 - I.E Vavunia 1 - ITI Galgamuwa 18 8 Total 21 08

2. Final adjustments and fixing of bubbles in 41 Nos. of Evaporimeters for Water Management Sub Department were completed. 3. Fabrication and final adjustments of 1 No Electronic evaporimeter is completed. 4. Repairing and servicing of 1 No. Automatic water level recorder at Thanamalwila ( Hydrology Division) 5. Servicing of 1 No Automatic rainfall recorder clock at Thanamalwila ( Hydrology Division)

6.5.5. Photography Section

• Construction works at Weheragala Project on 1st January 2009 and inauguration ceremony of Weheragala Project.

• Uma oya scheme for Deyata Kirula exhibition. • Technical photographer participated for 3 days in media purpose of honorable Minister of Chamal Rajapaksha. • Inauguration ceremony of the new canteen Irrigation Department head office • Maps of dam safety unit. • Stat file maps of wewa, Kaluganga, Hurulu wewa Project , Galoya project to Dam safety unit. • Photos of weheragala, Mau ara, Rambukkan oya, Deduru oya, Rajanganaya, Mahavilachchiya to Media Secretary of Mahaweli Ministry.

24 • Photos of Tissa wewa, Yoda wewa, Parakkrama Samudraya etc. to RD & C branch to prepare a CD • Photos of Weheraga project to DD ( Dam safety) to published in a magazine. • Photos of Mau ara, Gal amuna, Weli oya’ Weheragala’ Rajanganaya, Rambukkam oya to Director of in the Ministry of Irrigation to present for “ Haritha Pradarshanaya” exhibition.

6.5.6 Some Works done for other Division Hydrology Division • Planning and marking 70 Nos gauge posts. • Prepared material list for 30 Nos telephone boxes for Hydrology division and submitted the same.

Engineering Materials and Quality Control Division. • Six (6) Nos of samplings tubes were sharped. • Repairing the core- cutter extruder

Engineering Geology Division • 65 pieces of pipes were cut with thread by using IDMP for grout machine pump. • Cut threads and welded the pipe for D 1265 drilling machine • Filled and lathe the oil bush of the gear box of D 1254 drilling machine

• Lathe and sharpening the clutch collar of the drilling machine.

Colombo IE Division • Brackets were fabricated for wash basins in new canteen in the head office. • Two volley ball posts were fabricated for Head office.

• Fabricating a ladder for temporary shed at roof top in Hydrology Division. 6.6 Computer Services Branch The Computer Branch is staffed by a Senior Irrigation Engineer, Development Assistant for providing support service. The activities of the branch was supervised by Director (SS & Tr ).

The Branch is equipped with Desktop Computers, Note book computer, Printers, Scanners, and Multimedia projectors. In addition, it is also technically equipped for provision of all support services required for presentations, discussions, conferences and seminars held in Head Office. The Branch is also responsible for uploading information and maintaining department website www.irrigation.gov.lk .Local area Net work and Local Government Net work and E – Sri Lanka activities.

Services Upgrading during 2009

• Installed Desktop Computers, Laser Printers and Plotter • Expansion of ADSL and Local area network for web browsing and data sharing Activities During -2009

1. Upgrade and maintain Department Website. 2. Maintain an inventory on Computer Equipment in the Department. 3. Provide Conformity Certificates for Computer equipments and office equipments. 4. Provide un-serviceable certificates for unusable computer equipment for disposal. 5. Preparation of department specifications for procurement of computers and office equipments. 6. Troubleshooting and attending to minor repairs to computers installed in Head Office. 7. Functioning & maintaining of Time machines

25 6.7 Training Branch ( Local & Foreign Training )

Please see annex 3 & 4 for Local Training , Foreign Training and Examinations details

7.0 Irrigation & Water Management Sub Department

7.1 Functions:

Main functional areas of the Irrigation & Water Management Sub Department include: 1 Water Management in Major & Medium Irrigation Schemes 2 Participatory irrigation Management 3 Promote Farm Productivity Improvement 4 Rehabilitation, improvements and additions to Irrigation System

7.2 Water Management

7.2.1 Activities

Work includes seasonal planning interventions, co – ordination of water allocations in Mahaweli fed systems. Monitoring of storages of major reservoirs & water issues & overall performance assessments.

7.2.2 Extents cultivated during Maha 2008/09 and Yala 2009

Maha 2008/2009

At the beginning of the Maha season 2008/09 almost all the irrigation reservoirs were at their lowest levels and some reservoir water levels were given below the minimum operation levels. However the monsoon heavy rainfalls started in early December caused a sudden rise of reservoir water levels and most of them were spilling. In most areas cultivations had started with inter monsoonal rains in November and a extent of 233097 ha. (94%) in major irrigation schemes 27305 ha. (81%) in medium schemes had been able to cultivate.

Yala 2009

At the start of Yala 2009 though irrigation reservoirs had reasonable carry over storage rain fall during the season was low. Extent cultivated during the season area 168406 ha. o %) in major schemes and 17575 ha. (52 %) in medium schemes.

District – wise extent cultivated during Maha 2008/2009 and Yala 2009 are given in Table below: Table 7.2.1 : Major Irrigation Schemes

26 District Extent Maha 2008/09 Yala 2009 Acs Ha Acs. Ha. Acs. Ha. Ampara 142,880 57,846 142,848 57,833 108,136 43,780 Anuradhapura 66,664 26,990 66,663 26,989 39,766 16,100 Badulla 19,533 7,908 19,535 7,909 15,309 6,198 Batticaloa 49,889 20,198 44,144 17,872 20,581 8,332 Ratnapura 4,387 1,776 4,387 1,776 4,388 1,776 Gampaha 6,813 2,758 6,192 2,507 4,296 1,739 Matara 15,587 6,311 10,532 4,264 11,737 4,752 Galle 5,345 2,164 3,073 1,244 2,616 1,059 Hambantota 57,662 23,345 57,662 23,345 53,559 21,684 Nuwara Eliya 1,616 654 1,615 654 1,616 654 Matale 4,142 1,677 4,142 1,677 4,142 1,677 Kandy 19,879 8,048 19,299 7,813 12,896 5,221 Kurunegala 29,429 11,914 29,008 11,744 17,057 6,906 Moneragala 8,703 3,523 8,704 3,524 4,719 1,911 Puttalam 12,499 5,060 12,498 5,060 11,156 4,517 Polonnaruwa 84,069 34,036 81,031 32,806 60,353 24,434 Trincomalee 49,458 20,023 45,704 18,504 43,634 17,666 Vavuniya 4,135 1,674 3,300 1,336 - - Mannar 31,892 12,912 15,412 6,240 - - Total 614,580 248,818 575,749 233,097 415,963 168,406 Cultivated % 94% 68%

Table 7.2.2 : Medium Irrigation Schemes

District Extent Maha 2008/09 Yala 2009 Acs Ha Acs. Ha. Acs. Ha. Ampara 3,280 1,328 2,879 1,166 815 330 Anuradhapura 27,348 11,072 22,233 9,001 9,769 3,955 Badulla 3,212 1,300 3,212 1,300 2,265 917 Batticaloa 3,664 1,483 880 356 1,452 588 Colombo 438 177 276 112 231 94 Ratnapura 1,651 668 1,651 668 1,700 688 Kalutara 350 142 275 111 300 121 Gampaha 5,163 2,090 3,523 1,426 1,734 702 Galle 440 178 440 178 440 178 Matara 4,170 1,688 3,796 1,537 4,170 1,688 Hambantota 3,136 1,270 2,196 889 2,916 1,181 Nuwara Eliya 1,681 681 1,441 583 1,427 578 Matale 2,524 1,022 1,709 692 1,085 439 Kandy 1,811 733 1,423 576 1,733 702 Kurunegala 7,395 2,994 6,717 2,719 6,082 2,462 Moneragala 8,459 3,425 7,459 3,020 4,562 1,847 Puttalam 3,876 1,569 3,876 1,569 1,398 566 Polonnaruwa 1,436 581 1,434 581 756 306 Trincomalee 600 243 450 182 500 202 Vavuniya 2,609 1,056 1,574 637 75 30 Total 83,243 33,702 67,443 27,305 43,410 17,575 Cultivated % 81% 52%

7.2.3 Performance

While a comparison of cultivated extent in major schemes during Maha & Yala seasons in given fig 2.3.1 All Island Annual Cropping Intensity of major schemes in given in Fig 2.3.2 . Cultivation of 3 – 3 1/2 month varieties for both season and shortening of land preparation period to 3 – 4 to weeks were adopted as strategies to improve water use efficiency.

27 Fig 7.2.3 : Comparison of Cultivated Extent Maha & Yala

Comparison of Cultivated extent of Major schemes during past Maha & Yala

300000

250000

. 200000 a h

t

n 150000 e t x

E 100000

50000

0

4 5 6 7 8 9 0 0 0 0 0 0 0 0 0 0 0 0 2 2 2 2 2 2 Gross Extent Ha Maha Cultivated Extent Ha. Yala Cultivated Extent Ha. Year

Fig 7.2.4 All Island Cropping Intensity Major Schemes

IRRGATION DEPARTMENT ALL ISLAND CROPPING INTENSITY & CULTIVATED EXTENT 1993/94 TO 2008/2009

2 .0 0 12 0 0 0 0 0 1.72 1.73 1.73 1. 8 0 1.61 1.66 1.63 1.61 1.51 1.57 1.56 1.57 1.58 10 0 0 0 0 0 1. 6 0 1.50 t y 1.44 t n

i 1.37 e s

1. 4 0 1.28 t

n 8 0 0 0 0 0 x e t 1. 2 0 E

n n I

1. 0 0 6 0 0 0 0 0 o i g t n

0 .8 0 a i v p

4 0 0 0 0 0 i

0 .6 0 t p l o u

r 0 .4 0 2 0 0 0 0 0 C C 0 .2 0 0 .0 0 0

Cultivation Year

C ro pping Intecsity To tal C ultivated Extent M aha & Yala

7.3 Participatory Irrigation Management Programme

Waphaula Programme.

Irrigation Department implements the government policy of participatory Irrigation Management Programme through the “WAPHAULA” programme.

28 Two hundred and thirty five major and medium schemes covering about 100,000 ha have so far been taken up under the WAPHAULA Programme and 1001 FOO have been formed. Action has been instituted to Re- Register the FOO under the Agrarian Development Act. No 46 of 2000.

Specific Activities

The specific activities performed from the allocation of Rs. 1.7 million under Farm Productivity & Profitability Improvements and Farmer Organization Development Vote are as follows.

Training Programmes

With the allocations of Farm Productivity & Profitability Improvements and Farmer Organization Development vote number of Training Programmes were conducted in the following subject areas .

1. Review and planning workshops at the Regional level - 11 Nos

2. Substantial number of Training programmes for officers/FO Leaders/Farmers to strengthen farmer organization to undertake efficient and effective operations, Maintenance, system protection and productivity increase. – 172 Nos

Demonstrations

200 paddy productivities improvements demonstrations with assistance of Agriculture Department were done. They were done using Farmer Organization revolving funds with technical advise and extension support being provided by agencies. Demonstration showed potential for yield increase in most area.

Some of the results achieved in demonstration plots are given below.

District Scheme Yield Bush/Acs

AmparaWeerayadi 165

Colombo Kaltota 140

Galle Urapola 158

Kandy Ratne Ella 80

Radagalpotha 135

Himbiliyakada 135

Kurunegala Nikapitiya 160

Monaragala Karawila 140 Detagamuwa

Trincomalee Peramaduwa 120

7.4 Rehabilitation of Irrigation Schemes

The work carried out for the year 2009 consists of 89 items of Head Works, Main and Distributory Canals in twenty seven irrigation schemes in twelve (12) Regions. List of schemes is given below. Seventy eight items were completed and financial Progress 46.97 Rs Mn. out of 51.0 Rs Mn..

Ampara Badulla Hambantota Moneragala

29 1.Will Oya 1.Badulu Oya 1.Weerawila 1.Pelwatta

2.Nawal aru 2.Bathmedilla 2.Debarawewa 2.Badulu Oya

3.Ekgal Oya Batticaloa 3.Tissa wewa 3.Monarawana

4.Ambalan Oya 1.Vakaneri 4.Gamunupura Puttalam

Anuradhapura Galle Kandy 1.Pawattamaduwa

1.Kawarakkulama 1.Dedduwa 1.Ratnaela Trincomalee

2.Thanneyankulam 2.Ranthotuwila Kurunegala 1.Peramaduwa a

3.Ittikulama Matara 1.wellangiriya Mannar

4.Illukwewa 1.Urapola 1.Giants tank

2.Denagama

Repairing Thannayankulam Sluice Raising of Hettu Wewa Bund under Illukwewa Anicut, Anuradhapura Division Hurulu Wewa Division

Gaints tank – Murukan Division - Rip Rap Protection; Tissa Wewa Bund Vavuniya Region Hambantota Region

7.5 Pro-Poor Economic Advancement and Community Enhancement (PEACE) Project

Location

30 The project covers 8 major irrigation schemes and 12 medium irrigation schemes which are scattered in the Anuradhapura and Kurunegala districts. Total irrigation area is around 18,200 ha.

Implementing Agency

ID will be the principle implementation agency for the rehabilitation and upgrading of irrigation facilities and related facilities including farm roads, improvement of water management of all inter-provincial major and medium schemes and for participatory irrigation management in inter-provincial medium schemes. The Kurunegala and Anuradhapura Development Plan of the Project comprise the following components.

• Awareness programmes / training of Medium Schemes • Strengthening FOs of Medium Schemes • Stable crop production/ crop diversification • Income generation programme of Medium Schemes • Rehabilitation and upgrading of Main system irrigation facilities of Major / Medium schemes • Engineer of the sub system rehabilitation programme • Farm road improvement • Improvements to feeder canals • Improvement of water management and O & M of facilities • Strengthening of agricultural support services of Medium Schemes • Construction Management, Water Management training • Monitoring and evaluations

Engineering works Rehabilitation and Implementation of main system.

Surveys and Investigation

Irrigation Department has completed the surveys and investigation of the main systems in major and medium schemes.

Construction works – Main System 1. Anuradhapura

Total allocation for main system rehabilitation in Anuradhapura component for the year 2009 is Rs 988 million. Total expenditure up to end of December 2009 is Rs 316 million. It is observed that Rs.544 million worth of contracts awarded and estimating are in progress for Rs 163 million worth of contract packages.

Nachchaduwa Feeder Canal Improvements to Rajangana main canal.

31

Construction of Nachchaduwa Feeder Canal: Improvements to Tissa wewa access road: Anuradhapura Region. Anuradhapura Region

Rehabilitation of Angamuwa Wewa Bund Improvements to Periyakulam Bund Rajangana Scheme Anuradhapura Region

2. Kurnegala

Total allocation for main system rehabilitation in Kurunegala component for the year 2009 is Rs 246.5 million. Total expenditure up to end of December 2009 is Rs 92.0 million. It is observered that Rs 24 million worth of contracts are completed and Rs 130 million contract packages are in progress. Rs 45 million worth of contract packages tendered. Estimating are in progress for Rs 9 million worth of contract packages.

Improvements to Attaragalla Wewa Bund Improvements to Hulugalla Wewa Bund Kurunegala Region Kurunegala Region

32 8.0 Assets Management Sub Department

8.1 Assets Management Branch

The operation & maintenance of the following schemes which services required by the farmers and other recipients in the country at large were under taken by the department during the year 2009. Following schemes were under purview of AM branch in this period.

1. Gravity irrigation works (Reservoirs & Anicuts) - 304 schemes (264663 ha.) 2. Lift irrigation - 06 schemes (382 ha.)

Following allocations received from budgetary provisions for the above two items.

1. Gravity irrigation works. Rs. 40,000,000.00 2. Lift irrigation Rs. 391,203.00

The allocation under item 1 was utilized for the payment of wages of regular casual and adhoc labours engaged in operation and maintenance of gravity irrigation schemes. The funds provided through the irrigation management division (IMD) of the ministry separately for the maintenance and improvement of gravity schemes are as follows.

3. O & M gravity Rs. 206,376,295.00 4. Improvements to Major work. Rs. 24,456,554.00

Funds have also been allocated for management of Assets, under other departmental votes as well.

5. Maintenance of Departmental Roads Rs. 26,750,000.00 6. Flood Damage Repairs Rs. 43,359,204.00 7. Improvements to Building Rs. 34,690,006.00 8. Maintenance of Mahanuwara Wewa Rs. 4,250,000.00 9. Electrical installation Rs. 147,956.00 10. Minipe Main channel Rs. 5,100,000.00 11. Preventive Maintenance Rs. 44,373,705.00 12. Purchasing of Communication Equipment Rs. 740,212.00 13. Rehabilitation of Ratmalana Housing scheme Rs. 2,000.000.00 14. Irrigation Secretariat Rs. 10,850,000.00 15. Management supporting facilities Rs 8,803,373.00 16. Construction of New Quarters & Buildings. Rs 11,766,371.00

Steps have been taken to recovery & safe guarding Land and Reservations of the department. Allocation also released under department vote as well.

17. Recovery of Possession & safe guarding of Dept. Lands & Reservations. Rs. 4,240,142.00

Scheme data base is been prepared by the AM branch. This comprised all technical data of head works and IFF, of schemes maintained by the department.

Data base for lands and buildings vested with ID is also been prepared. Steps were taken to Survey and transfer the ownership of the lands to the department.

New project was implemented and funds also been allocated to improve the cropping intensity, capacity and the conditions of the channel systems of major irrigation scheme under Essential Rehabilitation of Major Irrigation schemes.

18. Essential rehabilitation of selected major irrigation schemes. Rs. 14,400,000.00

33 8.2 Dam Safety Branch

8.2.1. The Dam Safety Division established in 1997 is entrusted with

• Monitoring, evaluation and feed back of periodical inspection of dams • Evolving guidelines to streamline dam safety practices • Compilation of technical data and historical events of dams • Developing and updating of standing orders • Coordination with specialized divisions, outside service organizations and Professional bodies to carry out inspections, investigations and implementation of remedial measures • Monitoring the annual works programs for Strengthening the Safety of Head works • Maintain the Secretariat of National Committee on Large Dams of International Commission on Large Dams • Coordination with Project Management Unit of Dam Safety and Water Resources Planning Project (DSWRPP) to Rehabilitate 16 Major Dams, provision of Basic Safety Facilities for 49 schemes and special studies on Senanayaka Samudraya scheme.

8.2.2. Physical work done under Improvements to Head works of Tanks for Additional Safety.

Regional Directors have prioritized Rs: 70 million worth of urgent improvements to strengthen the safety of head works, to be attended in year 2009. Only Rs: 29.75 million was available under block vote and hence had to select very urgent repairs. Only Seventy Six (76) work items were selected out of 106 new items and there are 31 continuation works. Some of the significant items are listed below.

a) New Items

• Repairs to Ilukchenai anicut in Kurunda oya in Pothuvil Division • Improvement to LB Tower type sluice in Thithgonawa in Anuradhapura Division. • Construction of supporting piers for morning glory spill in Dambe wewa Scheme in Wellawaya Division • Protection to RB of D/S of weerayadi Anicut in Sammanthuri Division • Repairs of scour section and providing Rip-Rap protection of Muhanthankulama bund in Vavuniya Division. • Construction of Wave protection wall of Bathalagoda Main Bund from 0+440 to 0+480 in Hiriyala Division

b) Continuation Items

• Removing existing collapsed rip-rap & providing rip-rap from 1590m-2055m in Mahawilachchiya Tank Bund. • Tank Bund Improvement Udamaluwa Wewa in Kandy Division. • Improvements to R.B. Spill in Balaharuwa Scheme in Wellawaya Division

8.2.3. Physical work done under Electro & Electro Mechanical Installation

Rs 0.85 million were available under this block vote and selected only 4 Nos urgent repairs of gates. Some of the items are listed below.

a) New Items

• Repairs to Wahalkada main sluice gates and emergency gates at Wahalkada Scheme in Padaviya Division • Improvement to mobile pump plant Panadugama in Mathara Division

b) Continuation Item

• Repairs of sluice gates replacing steel regulator gates and painting of radial gates of Pavatkulam scheme in Vavuniya Division

8.2.4. Sri Lanka National Committee of Large Dams for International Commission on Large Dams (SLNCOLD)

The secretariat of SLNCOLD is hosted by Irrigation Department from1958. Financial provision has been made by the government in the recurrent vote of annual budget of Irrigation Department for the subscription payments for ICOLD. Membership of SLNCOLD is comprised with professionals in ID, MASL, CEB, CECB, Universities and freelance dam consultants and there are 5 Organizations having cooperate membership.

34 Following Seminars were organized in this year and other activities were carried out by the SLNCOLD as in early years.

1. Why Irrigation Development of Sri Lanka Differs form rest of the world on 18th February 2009 2. Climate change & Possible impacts on agriculture in Sri Lanka on 27th October 2009 3. Leakage in Samanalawewa Reservoir 16th December 2009 4. Recent Advance in Geotechnical Engineering Research on 22nd December 2009.

The agreement for construction works for Pavatkulam scheme under Basic Safety Facilities signed on 30th October 2009 and construction works proceeding. The estimates were finalized for another 12 dams and forwarded to Project Monitoring Unit (PMU) and reaming 20 estimated to be finalized out of 33 Dams. (Apart from selected 16 dams for rehabilitation)

9.0 Planning & Designs Sub Department

9.1 Water Resources & Project Planning Branch

The following items of works had been carried out by the water resources & project planning (WR & PP) branch during the year 2009.

9.1.1. Pre-feasibility Study of Ellewewa Reservoir Project

Panamure anicut scheme is located across Kadigan Ara which is a tributary of Hulanda Oya in Walawe basin in the city of Embilipitiya. This scheme is depended on in-basin water resources from Kadigan Ara & the diverted water received from Kithalabokka anicut which is located across Eraporu Ganga, through a transbasin canal. Irrigable areas of Panamure scheme is scattered over the Kadigan Ara sub basin & irrigation water is provided from a cascade of 07 anicuts across Kadigan Ara.

During the drought periods, at the tail end of Yala season, Kadigan Ara flow goes dry & irrigation water supply get affected especially during the months of February & March. Reason for this water deficit is mainly due to increase in irrigable area owing to the encroachment by new settlers. At the beginning of Panamure scheme, about 215 Acs. of paddy lands were fed & presently it have been increased up to 1250 Acs. In addition to provide the irrigation water deficit, drinking water supply from a reliable water source is demanded by the people in Panamure area through irrigation engineer Ratnapura & local political authority.

Under the pre-feasibility study it is proposed to construct Ellewewa reservoir (2.4 MCM) across Kadigan Ara and to store water during rainy reason. During drought spell of the year water will be released to Kadigan Ara through the sluice and existing irrigation infrastructure will be used to provide irrigation water to the irrigable area. During the study it was revealed that the generation of hydropower also possible and a 0.7 MW hydropower plant will be established in right bank with 2.0 Gwh annual energy as an extra benefit by this project. A morning-glory spillway will be constructed at left bank in addition to a natural spillway (breach section at HFL) provided at right bank in case of higher flood larger than the design flood. Under this pre-feasibility study, hydrological analysis, flood study, operation study, design of morning-glory spillway, design of hydropower plant & related structures, economic analysis, preparation of cost estimate & relevant drawings were completed.

9.1.2. Kaluganga Multi-purpose Development Project

A special cabinet committee chaired by Hon. Prime minister requested the Irrigation Department to study on Kaluganga basin and submit a project proposal/concept paper to harness the Kaluganga water resources while reducing the flood menace, which has become a nuisance to the people living in the low lying areas of the basin. Under this concept paper preparation, previous study reports prepared by local & foreign consultants were studied and their recommendations were considered in order to propose the best option available for Kaluganga basin. In order to minimize flooding situation in down stream, it is compulsory to construct

35 reservoirs in up stream to arrest flood volume. Therefore as recommended in previous studies too, it is required to construct Malwala and upper Kukule reservoirs. However with these two reservoirs alone it will not be possible to minimize flooding in down stream. Hence flood bunds and gravity outlets too required in downstream for flood protection.

During this project proposal study, operation studies were carried out with updated hydrological data and other related parameters. From the operation study, to minimize flooding in Ratnapura, it is required to construct a reservoir with 250 MCM capacity for safeguarding a 20 yr return period flood. Evaluation of hydropower potential was based on the runoff records available for a period of 42 yrs and the optimum installed capacity was 13 MW with 61 Gwh of annual energy.

Upper Kukule reservoir was proposed across Kuda Oya, upstream of existing Kukule run-of the river diversion weir. Existing power house will not be affected due to proposed reservoir & power house as the down stream flow will be guaranteed. Evaluation of hydropower potential was based on the run-off records available for a period of 12 years at Kukule gauging station. Optimum installed capacity was 6 MW and 25 GWh of energy could be generated annually.

Preliminary designs of concrete faced rock fill dams, spillways, economic analysis and report was prepared during the year 2009.

9.1.3. Batuwita Ara Reservoir Project

This proposal had drawn the attention under the Nilwala Ganga Action Plan in 1990s. Initially this project was proposed under ‘Rectification of Nilwala Ganga Scheme’. Terms considered under the new action plan were broader thus incorporating flood control and supply of potable water in addition to the supply of water for irrigation. Initially the task was attributed with Nilwala Basin Project office and they had come up with three alternative solutions basically to address flood control for probabilistic floods of 2 years, 10 years and only for irrigation requirement to cater an irrigable area of 310 acres of paddy lands in both seasons. Later the task was under taken by this branch and hydrological analysis was carried out based on actual rainfall data and stream flow data for last twenty years. This study included a more detailed flood control analysis for last 20 years based on different reservoir scenarios.

In order to obtain the reservoir parameters and to analyze the behavior of the proposed reservoir against the objectives, the operation study was carried out based on the inflow time series. From the results of the operation study an optimum of 1030 ac.ft. of active storage capacity was selected. The maximum height of the earth bund was 57 feet at the river section.

Based on the geological conditions, location, economy and the scale of the project it was decided to provide a morning-glory spillway for this reservoir. In order to minimize the cost, the sluice is incorporated with the spillway structure.

9.1.4. Proposed Aparekka Ara Reservoir Project

Proposed Aparakka Ara reservoir is located in across Aparekka Ara Nilwala basin. This reservoir is aimed to irrigate about 600 Acres of paddy lands in both Yala / Maha seasons. It is further expected to mitigate down stream flood potential and to be used as a source for potable water supply.

An inflow series was generated for Aparekka Ara proposed location in order to carry out the operation study for a period of 20 years based on actual rainfall data obtained from the Meteorological Department (from 1989 to 2008). Based on that data a number of possible alternative reservoir scenarios were analyzed to obtain the optimum reservoir parameters. Flood analysis was carried out for 100 yr probable flood. Finalized a suitable bund section and fixing reservoir parameters are in progress.

36 9.1.5. Downstream Development under Uma Oya Project

Uma Oya is one of the major tributaries of Mahaweli Ganga which is the largest river in Sri Lanka. Uma Oya flows northeastward across the central highlands at about elevation of 1000 m msl & discharges in to Rantambe reservoir at Bembiya. Uma Oya multipurpose project envisaged to divert water from Uma Oya to Kirindi Oya after harnessing hydropower potential and to irrigate dry & less developed southeastern region of Sri Lanka. After generating hydropower, water conveys to Alikota Ara which is a tributary of Kirindi Oya. About 150 MCM of water will be diverted annually from Uma Oya to Kirindi Oya under the proposed development.

The proposed capacity of Alikota Ara reservoir is around 2 MCM. Since the low capacity of proposed Alikota Ara reservoir, it is required to transfer water to proposed Kuda Oya reservoir through Alikota Ara right bank main canal while releasing water to Kirindi Oya. The part of water picked up at Handapanagala anicut will be diverted to Handapanagala reservoir while the balance will be utilized for irrigated agriculture in minor tanks through proposed Handapanagala Anicut right bank canal. If excess water is available after storing in above major and minor tanks, it can be allowed to flow to Kirindi Oya reservoir to meet the enhanced drinking and industrial demands of the region.

Water released from the sluice of Alikota Ara reservoir to Kirindi Oya, will be picked up at existing Handapanagala Anicut. Handapanagala anicut consists of existing left bank & proposed right bank feeder canals. Handapanagala existing left bank feeder canal conveys water to Handapanagala reservoir. Proposed Handapanagala right bank feeder canal conveys water to ancient abandoned Yoda Ela & will feed existing & proposed new tanks & irrigable areas in Ethili wewa area. It is expected to increase the capacity of existing Handapanagala right bank main canal and to construct a new left bank main canal in order to irrigate more lands under Handapanagala reservoir. Also, it is expected to raise the bund in-order to increase the capacity of Handapanagala reservoir.

Proposed Kuda Oya reservoir is to be constructed across Kuda Oya which is also a tributary of Kirindi Oya in order to feed identified irrigable areas in Kuda Oya right bank side & identified irrigable areas in adjacent basins. Kuda Oya reservoir right bank canal is planned at a higher contour closer to the ridge of the Kuda Oya in order to feed identified irrigable areas in right bank side of Kuda Oya and Kahakurullanpellessa and Sinhalayagama tanks which are located in dry areas in the adjacent Mau Ara and Malala Oya basins respectively. In addition to Kuda Oya right bank area, it is expected to release water to Kuda Oya from the sluice of the proposed Kuda Oya reservoir in order to irrigate from Ussella anicut. Right bank canal of the Ussella anicut is much lower in elevation to Kuda Oya right bank main canal and planned to feed several minor tanks & irrigable areas in right bank of Kuda Oya and in Thanamalwila area.

Diverted Uma Oya water is planned to be utilized for irrigation demands of new irrigation areas in both Yala & Maha and irrigation demands of existing areas during Yala. Altogether, it is expected to develop about 5000 ha of lands in southern part of Sri Lanka.

9.1.6. Kumbukkan Oya Basin Development Project – (Nakkala Reservoir & Mandappan Oya Reservoir)

Presently within the Kumbukkan Oya basin there are no major storage tanks across the main Kumbukkan Oya and there are few anicut schemes. Kumbukkana anicut has about 2100 Acs. of paddy lands and the present cropping intensity is about 1.5. Proposed project envisaged to increase the cropping intensity of the scheme up to 2 and planned to irrigate new lands of 2,000 acs in Kumbukkan Oya basin. (500 Acs. under Yakurawa anicut, 750 Acs. under Therappahuwa anicut and 750 Acs. under Nugamandiya anicut). In addition to irrigated agriculture it is proposed to provide drinking water to Moneragala district.

Proposed project envisaged to construct two reservoirs. One is across Kumbukkan Oya at Horagolla, upstream of the Nakkala & the other is across the Mandappan Oya which is a tributary of Gal Oya at Karametiya.

Kumbukkan Oya is the major river in the Moneragala district. Average annual inflow to the proposed reservoir at Nakkala is about 201 MCM. There is no possibility of utilizing this water within the Kumbukkan Oya basin alone due to topography of the area.

37 Therefore part of this water has to be diverted to the adjacent Gal Oya basin through a tunnel to develop the lands in Moneragala district. It is proposed to irrigate about 5000 Acs. under the proposed Mandappan Oya reservoir.

Collecting of rainfall data, hydrological studies for proposed reservoirs were done during the year 2009 & reservoir sizing is in progress.

9.1.7. NCP canal Project

Under the original Mahaweli master plan of 1968, five major reservoirs were proposed. Out of five Kothmale, Victoria, Randenigala and Rantambe reservoirs have been completed. The fifth major reservoir Moragahakanda is now under construction and it is across Amban Ganga, a major tributary of Mahaweli Ganga.

The original master plan envisaged to convey Moragahakanda water to the North-central province through a ridge canal (NCP canal) and continues beyond Vavuniya district and enters into Kanagarayan Aru in district to feed .

To justify the viability of the project it is necessary to assess the water availability in the Mahaweli system in order to transfer excess water to NCP canal. For this task water availability at Minipe Anicut and Polgolla-Amban Ganga complex was assessed based on the water issues data issued by MASL during the year 2009.

9.1.8. Kadukanna Reservoir Project This proposal was forwarded to action plan of Nilwala rehabilitation programme by the farmers of the area. The proposed Kadukanna reservoir is located in basin in Matara district. There is no reliable water source for the surrounding paddy lands. Although there are few anicuts across Kadukanna ara to irrigate the paddy lands, water in the stream is not sufficient to meet the demand during the dry spells of the year. On the other hand, these lands are inundated damaging crops during rainy seasons and this water drains to downstream lands resulting minor floods. Hence, some sort of regulation of the flow of the Kadukanna ara is quite necessary and hydrological studies, operation studies & preliminary designs of structures were completed during 2009. 9. 2 Designs Branch

9.2.1 Designs Branch - 1

The Design works carried out in the Design Branch 01 are as follows:

9.2.1.1. Deduru Oya Radial Gated Spillway The proposed Deduru Oya Reservoir will impound 75 MCM water at the Full Supply Level of 70.99 m MSL. The proposed spill way consists of 8 No 8.50 m(W) X 8.00 m(H) Radial Gates.

Originally the Energy Dissipation was proposed by providing a stilling Basin. But considering the amount of hard rock to be excavated and removed, later it was decided to do away with the stilling basin.

Accordingly the entire Design was redone and completed during the year 2009.

9.2.1.2. Rambukkkan Oya Blocking Out Plan

Rambukkan Oya Reservoir Project was proposed to irrigate 3500 Ac. of land. The Blocking Out was done on a 2.5 Ac lot basis. Due to the scarcity of irrigable land the Blocking Out Was redone keeping the individual lot size as 1.5 Ac.

The canal net work consists of 6.7 km long Main Canal, 8 No Distributory Canals and 56 No field Canals. The canal net work was laid so as to feed the existing tanks in the vicinity and creating possible new tanks en route the canal network. Accordingly one medium tank, six village tanks and three new village tanks will be fed by the Rambukkan Oya reservoir.

The Irrigable area consists a total of 2305 lots under 5 Tracts. The total area blocked out is 3457.5 Ac.

38 9.2.1.3. Proposed Branch Canal No2 in Kaudulla Reservoir Scheme.

The development of Branch Canal No2 was proposed to resettle farm families who are displaced by Moragahakanda Reservoir impounding.

In the development of irrigable area the concept of ”DUAL CANAL SYSTEM” is introduced. Under this system, separate canals are formed for paddy and Other Food Crops. Normal field canals feed the paddy area 24 hours a day as practiced at present. The canals feeding other Food Crops are named Upper Canals and operate during the day time only. At night these upper canals are closed. Upper canals are fed by newly formed “High” tanks or existing minor tanks. These tanks store water during night and feed the canal during day time. The Tracts 1,2,3 and 4 under Branch Canal No. 2 are initially selected for Blocking Out. Each block is 1.5 Ac in extent .The Land use survey Maps were used to identify suitable Lands for Paddy and Other Food Crops. While existing village tanks are proposed to be fed by the cannel net work new Low and High Tanks are proposed wherever possible.

Accordingly 1051 paddy lots and 685 Other Food Crop lots are blocked out totaling an extent of 2604 Ac.

9.2.1.4. Seinor Staff Quarters at Cotta Road, Borella

This building is four storied and consists eight units for the occupation of Snr. Staff of the Irrigation Department. The foundation material is weak and hence it is proposed to remove 2.5 m. deep soil and to refill selected SC material. A value of 84 kN/m2 was used as the bearing capacity of the soil for the design of foundation. The columns are interconnected with inverted beams at the foundation level to minimize differential settlement.

9.2.1.5. Improvements to Land use Building

The design of roof for the existing Land Use Building in Head Office was done in Design Branch.

The roof is made of Zinc Alum roof sheets fixed to Galvanized Iron “C” purlins. The purlins fitted to “I” sectioned steel rafters.

9.2.2. Designs Branch - 2

The Following Design works were carried out in the Design Branch (2) during the year 2009

9.2.2.1. Rambukkan Oya Reservoir Project - Spill Way and Sluice

The design of abutments were completed and the drawings were prepared for the spill way and abutments.

The drawings of the sluice tower and barrels were completed. All the approved drawings with bar schedules were submitted to the relevant authorities.

9.2.2.2. Yakamuna Anicut

All the design calculations were completed.

9.2.2.3. Heda Oya-Sluice

Design of Heda Oya sluice tower was carried out for the design discharge of 325 cusec. It is proposed two nos of barrels (4.50’ x 6.00’ each) for to release water for irrigation facilities.

9.2.2.4. Uragamuwa – Mawala tank- Spill Way

This tank is proposed to construct in Dickewella District secretaries Division in Matara District. Design of morning glory spill way for this tank was started.

9.3. Geoinformatics Branch

The following items have been carried out by the Geoinformatics Unit during the year 2009

9.3.1. An irrigable area survey at Hettige oya in Colombo Division

• The survey was carried out with GPS instrument in order to verify the actual extent of the scheme

39 • The scheme map was prepared with Arc GIS software showing details such as irrigable area existing anicuts, existing canals and minor roads etc.

9.3.2. Assisted in preparation of Uma oys Multi Purpose Project Map with following activities.

• Topographical maps of 1:10:000 sheets were digitized and the features were separated into different categories such as contours, roads, streams, paddy areas, proposed canal trace and existing reservoirs etc.

• The project map was prepared with Arc GIS showing the proposed reservoirs, canals, irrigable areas and the locations where the Engineering surveys are required.

• Prepared a River Basin Map containing all streams, roads, administration boundaries, river basin boundaries and tanks after digitizing 1:250,000 scale Map.

10.0 Environmental Drainage and Flood protection Sub Department

10.1 Environmental Studies Branch

This branch handles all the environmental matters pertaining to the Irrigation Department. The functions of the branch are as follows.

1. Obtain the environmental clearance (EIA/IEE) from Central Environmental Authority or project approving agency for all the projects under the purview of the Irrigation Department. 2. Issuing Irrigation Department clearance, when ever necessary for the projects handled by the other Government Institutes and private sector such as High ways, Mini Hydropower, Industries land fillings, hotel resort and drinking water projects etc. 3. Attend to CEA meetings and submit a recommendations suggestions as a TEC member. 4. Attend to environmental matters in the Irrigation projects & related works.

The main items handled by the branch are as follows. (1) Irrigation Department Projects.

Name of Project Status Rambukkan Oya Reservoir work commenced under D(RD&C). Monitoring programme is on progress. Project Daduru oya project work commenced under D(RD&C) . ). Monitoring programme is on progress.

Ellapothana irrigation Project Environmental clearance was granted. D(RD&C) was informed to commence work. Archaeological clearance was granted. Lower Uva irrigation Project Environmental clearance was granted. D(RD&C) was informed to commence work Archaeological clearance is not received yet. Batuwita Ara irrigation Preliminary meeting at CEA was completed. F.D has not given approval for land Project clearance. Informed to ministry for further action Re appeal was send to F.D. & field inspection is carried out. Re appeal was rejected by F. D. & informed to I.& WM ministry. Archaeological clearance is not received yet. Kadukanna irrigation Project Environmental clearance was granted. Archaeological clearance was granted.

Samaradeniya irrigation Environmental clearance was granted. Archaeological clearance was granted. Project Urugammuwa Mawala Environmental clearance was granted. Archaeological clearance was granted . reservoir project. Gurugal oya irrigation Project Environmental clearance was granted. D(RD&C) was informed to commence work. Archaeological clearance was granted. Pavitra Ganga Programme Baseline survey started. Checked water samples for pesticides. Work shop was held. 50 Batugedara Scheme Acs. is selected for organic/traditional farming. Field demonstration is completed. (Continuation) Rathnapura. Traditional seed paddy was distributed among the farmers, Mitigation work was started. More details Pl. see item ( 9) Heda oya Project Feasibility study report is not ready yet. Yan Oya Reservoir Project Preliminary meeting was held. Field inspection was completed. TOR was submitted to CECB for preparation of EIAR. Uma Oya Reservoir Project Attending to EIA, TEC meeting at CEA.

Mini hydro power project . Submitted the concept paper. Preliminary study was started. LOI & Sustainable Bathmedilla project Energy Authority clearance was received.. Scoping meeting /Field visit completed for Environmental clearance. TOR was received Archaeological clearance was received. IEE report is under preparation.

40 Kohombaketiya irrigation IEE report is 80% completed. Archaeological clearance was granted. Allocation for Project further study was released to Archaeological Department. Giant Tank irrigation Project Environmental clearance was granted by CEA.. Director (NEIAP) was informed to commence work.

Mahagona wewa irrigation F.D. has not given approval for land clearance. Appeal was submitted. Scoping meeting Project was held. F.D. has informed to prepare EIA. for the clearance. TOR is received. Archaeological clearance is not received yet Relevant some documents submitted to CECB for EIA preparation.

Kospothu oya irrigation Feasibility study report is not received.( from RDI Kandy) Project Ippologama Manewa project Request for rehabilitation was received ( from RDI Anuradhapura).Feasibility study report is not received yet.

(2) Mini Hydro Power Projects

Range angeName of project Status Kandy Ebbawala Clearance was granted.

Falcon Valley Clearance was granted. Kirikoswald Clearance was granted. Gampola Clearance was granted. Waltrim Clearance was granted. Watawala Estate Clearance was granted.

Iddigolla Clearance was granted. Mossville Clearance was granted. Gammaduwa Clearance was granted. Thawalanthenna Requested some details from project proponent to consider clearance.

Kosgama Requested some details from project proponent to consider clearance.

KEW-Abagamuwa Basic information reports requested from project proponent.

Huluganga Basic information reports requested from project proponent.

Kurudu Oya Ella Preliminary meeting was held. Galatha Atabage oya Requested some details from project proponent to consider clearance. Koladeniya RDI &IE recommendation was received. Dunseine Basic information reports requested from project proponent. Illukpelessa RDI &IE recommendation was received Upper Sheen Basic information reports requested from project proponent Upper Duncinane Basic information reports requested from project proponent Ramboda Basic information reports requested from project proponent Rattota Oya RDI &IE recommendation was received Karapalagama RDI &IE recommendation was received Lower Atambage 11 RDI &IE recommendation was received St Heliers RDI &IE recommendation was received Theberton Estate RDI &IE recommendation was received Theligama RDI &IE recommendation was not received yet.

41 Horatota RDI &IE recommendation was not received yet. Pupuressa RDI &IE recommendation was not received yet. Galaha Oya RDI &IE recommendation was not received yet. Babarapana RDI &IE recommendation was not received yet. Galabada watta RDI &IE recommendation was received Halgran Oya 1 RDI &IE recommendation was not received yet. Halgran Oya 11 RDI &IE recommendation was not received yet. Biraha RDI &IE recommendation was not received yet. Ellahena 1 ,11 ,111. RDI &IE recommendation was not received yet. Stelenberg RDI &IE recommendation was not received yet. Kalugala Pitawala RDI &IE recommendation was not received yet. Glso & Edinboro RDI &IE recommendation was not received yet.

Colombo Koskulana Clearance was granted. Indurana Clearance was granted. Udagalakanda Clearance was granted. Polgas watta Clearance was granted. Kosgulana Clearance was granted. Guruluwana Clearance was granted. Ritigaha Oya Clearance was granted. Kitulgala Clearance was granted. Katurugaldola Clearance was granted. Maliboda Clearance was granted. Punugala Clearance was granted. Kankiriya Thabiliya Clearance was granted. Thebuwana Clearance was granted. Monaraela Clearance was granted. Gawaragiriya Clearance was granted. Wee oya Clearance was granted. Alupolagama Clearance was granted. Berannawa Clearance was granted. Adawikanda 11 Requested some details from project proponent to consider clearance. Ingiriya Requested some details from project proponent to consider clearance. Alupotha Basic information reports requested from project proponent Erathna 11 RDI &IE recommendation was received Napeldola Requested some details from project proponent to consider clearance. Ilukpelessa (Walana) RDI &IE recommendation was not received yet.

Kitulgala(Main river) Requested some details from project proponent to consider clearance. Marukanda Requested detail study from CEA Morathenna Ibulpe Preliminary meeting was held Doloswala Requested some details from project proponent to consider clearance.

Dolekanda Requested some details from project proponent to consider clearance.

Illmbekanda Basic information reports requested from project proponent Wembiyagoda Requested some details from project proponent to consider clearance.

MawananaGalle Clearance was granted.

Kapila watta Clearance was granted. Kiriweldola Requested some details from project proponent to consider clearance BandarawelaMille oya Requested some details from project proponent to consider clearance. Upper Hal Oya On progress

42 Babaragaha Oya On progress MonaragalaWellawaya Clearance was granted

Mini Hydro Power Projects Summary Granted - 30 projects In Progress - 47 projects

(3) Holiday resort and Hotel project

Name of Project Status Baddagewatta , Bentota Comments for TOR was sent. Hotel at Awissawella Clearance was granted Lake nest resort (Bolgoda) Conditional approval was granted.. Holiday resort Madapatha, Piliyandala Field visit results informed to CEA Luxury hotel at Kalutara Scooping committee meeting was held. Holiday home at Attidiya Preliminary meeting was held Hotel at Wemidilla Wewa Nauala Requested some details from project proponent to consider clearance Dedduwa lake resort tourism development Conditional approval was granted area Periyakarypone Bangadeniya Chilaw Preliminary meeting was held Panorama Hotel Kalutara Preliminary meeting was held (4) Water supply project

Name of Project Status Proposed Maha Thotilla Oya water supply D (P&D) was requested to submit recommendation project Multipurpose dam across , Conditional approval was granted . Yatimahana Mawanella. Proposed ThibbotuOya water supply D (P&D) was requested to submit recommendation project Low flow Weir across Kelani Ganga for Hydraulics study report was sent to BOI. Sitawaka Industrial park Proposed Galigamuwa water supply project D (P&D) was requested to submit recommendation Proposed Katuwana –Kirama water supply D (I&WM) was requested to submit recommendation project (5) Roads /Rail Roads

Name of Project Status Southern express way (ADB section) Attending to the monitoring process. Southern express way (JBIC section) Attending to the monitoring process. Colombo Kandy alternative highway Commence the Environmental clearance process Colombo Katunayaka express way. Extension of clearance was granted. Drainage study report was submitted for approval.

Matara Kataragama Rail Road Project. Commenced the EIA clearance process. EIA report is completed.

Habarana –Kurunegala Rail Road Project Preliminary meeting & field visit completed. Proposed rail way track from Panadura to Preliminary meeting & field visit completed. Horana. (6) Miscellaneous

Name of Project Status Proposed to cultivate Maize at Kantale TEC meeting was held. Proposed banana cultivation project in Requested to comments from RDI (Trincomalee) Kantale Ederamulla Town Development Project Scoping meeting was completed & submitted department recommendations.

43 Strategic Environmental Assessment for the TOR was received. Preliminary meeting was held. Northern province Proposed Waste Management project at Preliminary meeting was held. Site inspection was done. Land filling with Kolonnawa, waste is not recommended &informed to CEA.

2x250 M.W Coal power plant in Preliminary meeting was held. TOR was received. . Trincomalee. Trincomalee development plan. Preliminary meeting was held Proposed sapugaskenda oil refinery Preliminary meeting was held. expansion & modernization project.

(7) Industrial Estates

Proposed export processing zone at . Preliminary meeting was held. Perth Estate Horana Proposed export processing zone at Preliminary meeting was held. Mirigama

(8) Transmission Line

Habarana/Valachchani transmission Field visit has been completed & requested to RDI line (132 kv) recommendation. Habarana to Veyangoda 220 kv Clearance was granted. transmission line Rantambe to Mahiyangana (132kv) Clearance was granted. Galle to Matara (132kv) Clearance was granted.

Kilinochi –Chunnakam 132 kv Scoping meeting was held.field visit has been completed. transmission line. Habarana to Muttur 220 kv Field inspection is completed. Draft TOR is received. transmission line

Pavitra Ganga Programme Batugedara Scheme, Rathnapura.

This is a pilot project conducted by Irrigation Department, under the Pavithra Jala Kendraya

Main objectives

The main objective is to strengthen the livelihood security of the urban poor paddy farmers in Batugedara Irrigation scheme and to reduce the water pollution due to present cultivation practices. (Excessive use of agro chemicals and fertilizer.) It has been decided to do a base line survey to access pollution levels with in and around the system as follows. 1 Identification of point sources of pollutants. 2. Access pollution levels in the water entering, distribution, and leaving in the drainage canals. 3 Use of agro chemicals. Promote organic paddy farming with traditional varieties and to practice traditional methods for pest control and promote organic fertilizer. Present condition

Field demonstration & awareness programme was held under agrarian service, agriculture department & cea.. department of

agriculture was helped for manufacturing organic fertilizer. 50 acs .were selected for organic/traditional farming. traditional seed paddy was distributed among the farmers and now good demand for traditional rice in market.

44 Water Quality testing -Batugedara scheme

Good demand for Traditional rice in the market – Batugedara scheme

10.2 Drainage Branch

10.2.1 Introduction

The Drainage Branch is an established under the sub department of Environment, Drainage and Flood Protection. The main objective of the Drainage and Flood Protection branch is to minimize the damages to the public and private properties (including crops) due to flood damages problems and salt water intrusion.

The main function of the drainage branch is maintenance of the drainage & flood protection and salt water execution schemes under the preview of the Irrigation Department.

At present the drainage branch is assisting the planning branch in formatting proposals on new flood protection, drainage and SWE projects. Since the coastal drainage & flood protection and SWE subjects are complex in nature, the experience gathered during the operation of existing schemes is essential in designing new projects. Therefore the drainage branch has to be fully developed to undertake planning of drainage, flood protection and SWE projects in future.

Most of the drainage & flood protection SWE scheme implemented in the past have been deteriorated due to

1. Increases in O & M cost and decreases amount of annual allocation. 2. Lack of interest in paddy farming due to less profit. 3. Invasive aquatic plants in the drainage canals. 4. Sea level rise and climate change and sand mining in rivers and coral mining in coastal regions. 5. Reduction of wet lands due to garbage filling and housing scheme and encroachments. 6. Water pollution due to urbanization.

45 Most of the pumps installed in old drainage & flood protection scheme have been removed due to energy crises. (high fuel and electricity priced)

New engin installed at Magalagoda pump house Nilwalaganga drainage and flood protection scheme

10.2.2 Work done under the Drainage & Flood Protection in 2009

(a) O & M of Drainage and Flood Protection works:- Rs. 34.0 Million was provided in 2009 under block votes for Major Drainage & Flood Protection Schemes in Ampara, Batticaloa, Colombo, Galle and Southern range.

(b) Funds were allocated to above schemes to protect of paddy cultivation land by maintenance over 186 km length of flood bunds.

(c) Provided Drainage facilities to cultivation lands by maintaining over 825 km length of drainage canals under the Drainage and Flood Protection.

(d) Funds were also allocated to operate & maintain over 70 no. of pumps of the drainage and flood protection schemes in Nilwala ganga, and Kelani ganga flood protection schemes to facilitate protection of more than 13,000 Ha of paddy lands.

(e) Replaced 04 Nos. of trash tracks at Ginganga Scheme

.(f) Repaired one of lighting protection tower and panel board at Ginganga Scheme.

(g) Priority is given to Nilwala Ganga flood protection scheme where owing to aging of existing diesel pumps in 3 pump houses; paddy cultivation were faced numerous flood threats. Therefore Repaired 04 Nos. of Diesel pumps at Tudawa pump house and replaced 2 diesel engines with new ones. Replaced one diesel engine at Magalagoda pump house; in 2009.

(h) Irrigation department was able to arrange to Purchase 02 Nos. of new diesel engines for Nilwala ganga scheme in 2009 for the worth of 21.4 Million rupees and arrangements have been made to purchase another five diesel engines for the value of 60 Million rupees in 2010. New Excavator was purchased in 2009 for the value of 7 Million rupees and handed over to Irrigation Engineer (Gin Ganga) to facilitate dredging of drainage canals.

The Gin Ganga and Nilwala Ganga flood protection schemes are the largest flood protection scheme in Sri Lanka. The total protected extent of land under scheme is around 25000 Acs. (each scheme protects 12500 Acs.) Although those 2 are called flood protection schemes, those schemes include flood protection drainage and salt water execution also.

There are similarities in these schemes. Component table is given below.

Gin Ganga Nilwala Ganga

Flood bunds 24.18 km 10.16 km

46 Protected area 12500 Acs. 12500 Acs.

Un Protected area 2000 Acs 7000 Acs.

Pumping Stations 103

Engine of the pumps are run by Electric motors Diesel engines

Annual average energy cost Rs. 12.6 Mn .Rs.13.36 Mn.

Annual average maintenance cost Rs.5.06 Mn Rs. 6.6 Mn.

Average length of drainage canals 31.60 Km. 70.5 Km.

Summary of Total Fuel Cost at Nilwala Ganga Scheme

30.00 s

n 25.00 o i l ) l . i 20.00 s M R (

15.00 t s

o 10.00 Fuel C Expenditure 5.00 (Rs.) - 1 2 3 4 5 6 7 8 9 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 2 Year

47 Variation of Electricity Cost at Gin Ganga Scheme

18.00 s

n 16.00 o i l l

i 14.00

M 12.00 t

s 10.00 o

C 8.00 Electricity 6.00 Expenditure 4.00 (Rs.) 2.00 - 1 3 6 8 2 4 5 7 9 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Variation2 of Electricity2 2 unit2 Year prices2 at Gin2 Ganga2 Scheme2 2 K.V.A unit Cost (Rs.) ) .

s 700 R (

600 t

s 500 o K.V.A.unit

C 400

t Cost (Rs.) i 300 n u

200 A

. 100 V

. 0 K 6 7 9 1 3 7 8 5 9 9 0 0 9 0 0 0 9 0 0 9 9 0 0 0 1 1 1 2 2 2 2 2 It is obvious that the Year

48 (3) 03 in Project Office

Function of the Finance Division • Preparation of Annual Expenditure, Revenue and Advance Account Estimates • Annual imprest control

• Effecting all payments under • Domestic Fund • Reimbursable foreign Aid

• Effecting all payments under • Capital Expenditure • Recurrent Expenditure

Release of allocations and maintaining control ledgers • Submission of monthly Summary of Accounts • Submission of claims to Reimburse funds from donor agencies • Submission of monthly financial progress reports • Attending to contract management activities • Maintaining a close liaison with General Treasury, finance Ministry, Line Ministry and other institution on finance matters. • Submission of Annual Appropriation account, Public Officers Advance Accounts, Deposits Accounts to the Auditor General • Asset management, conduct of Annual Board of Surveys and dealing with Disposals, write-off applications etc.

• Submission of replies to Auditor Queries, Refund from Revenue etc.

• All other accounting related activities

Financial Performance for the Year 2009

(1) Financial Performance for the Year 2009

Head Prog Proj Project Recurrent Capital Provision Mn Expen. Mn Provision Mn Expen. Mn General administration & 282 1 1 establishment Services 293.1 277.31 24.34 22.52 Administration & maintenance of 282 2 2 Irrigation schemes 856.6 846.14 761.55 700.86

282 2 3 Major Irrigation Scheme 1362.08 1297.26

282 2 4 Medium Irrigation Scheme 210.99 194.44 Total 1149.7 1123.45 2358.96 2215.08

Total Expenditure

49 Exp. Provision Expenditure Percentage Savings Sav. Percentage

M M M Recurre nt1149. 7 1123.45 98% 26.25 2.00%

Capital235 8.96 2215.08 94% 143.88 6%

Capital expenditure (categary Wise)

Total Expend. Percentage Purchases 299.71 14% Salaries 42.14 2% Deduru Oya Project 565.91 26% Project 131.03 6% Rambukkan Oya Project 233 10% Lower Uwa Project 30.41 1% Ellapothana Anicut 31.27 1% Galoya Nawodaya Project 38.3 2% Kekiri Obada Project 103.22 5% Other Capital expenditure 740.08 33% Total 2215.07 100%

Expenditure incurred under other Department votes - 2009 Provision Expenditure during Department/Ministry Vote particulars granted in 2009 2009

M/of Irrigation & Water Management 152-2-3-0-2001 2,595,246.50 2,368,416.95 M/of Irrigation & Water Management 152-2-3-0-2104 4,000,000.00 3,941,984.97 M/of Irrigation & Water Management 152-1-2-0-2401-01 600,000.00 494,578.60 M/of Irrigation & Water Management 152-2-3-4-2105(17) 10,000,000.00 846,516.98 M/of Irrigation & Water Management 152-2-3-1-2502(17) 2,000,000.00 0.00

50 Department of Archaeology 207-2-2-0-1303(11) 270,311.00 241,054.41 M/ of Tourism 107-2-3-8-2502 2,810,000.00 2,763,800.03 M/ of Justice & Law Reforms 228-1-1-0-2001 2,075,000.00 1,625,605.31 Department of Agriculture 285-2-4-1-2502 275,000.00 0.00 M/ of Nation Building 105-2-1-10-2502 41,555,000.00 12,598,160.22 M/ of Nation Building 105-2-1-11-2502 8,000,000.00 7,999,495.91 Total 74,180,557.50 32,879,613.38

(2) Write offs during the year 2009

Losses not written off are accumulated over the past years and action expedited to write off the losses and amounts written off during 2009 are as follows.

1. Loss of stores No Amount

Losses below 25000/= 241 839,639.55

Over 25000/= 44 9,058,840.93

Total 9,898,480.48

2. Vehicle accidents No Amount

Losses below 25000/= 13 101,973.47

Over 25000/= 22 2,414,428.97

Total RS. 2,516,402.44

(3) Advance Account Activities

Total Amount of loans No Amount

Distress Loan 1251 139,096,510.10

Festival Advances 3577 17,883,000.00

Special Advances 2042 5,105,000.00

Cycle Loans 70 420,000.00

Total 6940 162,504,510.10

Total Advances paid is within the Advance Account limit, provided for the year 2009.

Bank Loans Recommended (Property) 10 10,933,900.00

13. 0 Contract Branch

Major Contracts

No Major contract was awarded to a Contractor during this year.

51

ADMINISTRATION REPORTS REGIONAL LEVELS

52 ALLOCATION AND EXPENDITURE OF RANGES IN YEAR - 2009

Range Allocation 2009 Expenditure 2009 Extent (Ha)

Capital Recurrent Capital Recurrent

Ampara 141,652,243 83,671,320 37,676,076.26 96,962,928.77 57,134

Anuradhapura 127,137,334 86,374,579 114,372,489 90,837,708.78 35,823

Batticaloa 29,502,538 35,518,318 24,165,874 35,028,767 21,502

Bandarawela 35,593,185 39,484,284 34,219,356 41,489,768 8,494

Colombo 95,089,144 69,571,282 75,799,976 70,795,290 7,193

Galle 43,216,353 117,954,241 39,852,181 139,554,531 3,849

Hambantota 281,699,942 80,787,976 288,377,360 86,727,098 22,723

Kandy 87,186,344 59,599,569 78,266,826.35 62,952,952 11,128

Kurunegala 652,534,659 75,303,966 426,462,073 74,623,435 11,975

Moneragala 97,570,481 37,597,383 85,504,304 39,663,041 7,308

Polonnaruwa 13,342,208 53,361,928 13,056,494 58,395,035 39,679

Puttalam 25,760,811 26,592,186 19,619,443 26,149,202 7,204

Trincomalee 49,915,606 27,788,188 45,158,972 33,764,527 16,865

Vavuniya 44,293,745 19,768,380 35,295,373 20,307,063 15,701

53 Ampara Range- 2009

RDI”s office coordinates the functions of 5 Divisional I.E’s offices and one workshop.

• Ampara Division

• Akkaraipattu Division

• Pothuvil Division

• Sammanthurai Division

• Kalmunai Division

DIVISION SCHEMES Extent in (Ha)

RDI's Office Ampara Aligalge, Himmudurawa, Walagama, Padagoda, Alahena and Malayadai Minor Tanks Ambalan Oya 1,457 Eggal Oya 891 Gal Oya 18,677 Namal Oya 1,700 Pallang Oya 1,551 Pannalagama 1,094 Tempitiya 174 Senanayake Samudraya

DIVISIONAL TOTAL 25,544 Kalmune Gal Oya 5,180 DIVISIONAL TOTAL 5,180 Samanthure Gal Oya 9,358 DIVISIONAL TOTAL 9,358 Akkarapaththu Gal Oya 11,500 DIVISIONAL TOTAL 11,500

Pothuvil Karanda Oya 1,710 Lahugala 463 Naval Aru 1,789 Panama 182 Radella 558 Rottai Kulam 607 Will Oya 243 DIVISIONAL TOTAL 5552

Operation and Maintenance

An irrigable extent of 145,000 acrs was under operation cultivating both Maha and Yala season successfully. The cumulative expenditure are as follows.

54 Description Allocation Expenditure

A. For wages of MLL 5,100,000.00 5,326,613.86 ( Casual)

B. O & M Gravity works 36,625,044.00 37,365,086.70

C. O & M of Drainage 3,548,750,00 3,443,700,60 scheme

Block Vote

No Description of works Allocation No of Items Extend Benefit Expenditure 2009 Continue Commence Completed New/ Exist/ Tota d from d in 2009 in 2009 Acs Acs l/acs 2008 Maintenance of Dept 1 3,172,204.00 03 13 14 3,058,520.00 roads Flood damage repairs 13,098,250.0 2 30 10 37 12,762,838.00 0 3 Building & Structures 572,500.00 04 02 572,231.90 4 Dept. Building 2,790,900.00 09 12 21 2,797,784.50 5 Impts. To Major works 4,051,593.00 01 05 05 4,088,623.00 Impts to water 6 2,610,535.00 04 09 11 2,720,233.00 management 7 Impts to head works 3,044,100.00 04 03 07 2,825,565.30 8 Feasibility studies 637,209.00 07 0 309,445.00 Drainage & flood 9 3,548,750.00 01 10 11 3,443,700.60 protection 10 Preventive maintenance 4,925,446.00 05 10 12 6,099,236.00

CIADP

N Description of works Allocation No of Items Extend Benefit Expenditure o 2009 Continue Commence Completed New/Ac Exist/Ac Total/ d from d in 2009 in 2009 s s acs 2008 1 Repairs to Panama tank 459,900.00 01 0 01 bund 649,907.02 190,000.00 2 R/H of TM 5.1 channel 0 01 01

ISRP

N Description of works Allocation No of Items Extend Benefit Expenditure o 2008 Continu Commence Completed New/Ac Exist/Ac Total/a ed from d in 2008 in 2008 s s cs 2007 1 Naval aru Scheme 03 03 4400 4400

2 Weli oya scheme 05 05 600 600 15,147,390.00 3 Ekgal oya scheme 07 05 2800 2800 14,424,101.02 Ambalan oya scheme 03 03 4520 4520 4

55 Major Irrigation Scheme

Rambukkan oya Project

This is one of the Major Irrigation Scheme which was commenced during 2007, being implemented at Ampara Range under the supervision of CRE, RE of Rambukkan oya Project. The target year of completion will be 2010.

Gal oya Navodaya Programme

The Gal oya Navodaya Programme was initiated during the year 2008 and the following items were taken up for implementation.

No Description of works Allocation No of Items Extend Benefit Expenditure 2009 Continue Commence Completed Ne Exis Total/ac d from d in 2009 in 2009 w/A t/Ac s 2008 cs s 1 Pannalagama scheme 16,096,000.0 0 08 04 200 14,686,720.00 0 2 Con. Of Kandanveli anicut 3,846,620.00 0 01 0 510 3,342,758.16 Reh of 7th Km Gonagolla 1,520,000.00 0 01 1,662,259.00 3 01 Branch chal. Reh of 8th Km Gonagolla 1,267,000.00 0 01 1,095,876.00 4 01 Branch chal. Reh of G 23 Km 910,000.00 0 01 846,330.00 5 0 Gonagolla distribution Reh of “C” canal stage 1 in 2,424,490.00 0 01 2,555,077.91 6 0 block unit Repairs & modification to 1,095,000.00 0 01 1,194,708.00 7 01 D/S of Sooriyadi RB unit Reh of M 18.16 D canal at 700,000.00 0 01 0 1,278,089.00 8 Stn. 1+000 km to 2+ 290 km in Annamali Anicut Impts to KL 21- KL 26 in 700,000.00 0 01 01 745,183.14 9 Deegawapi unit Reh of M 5.4 canal at stn 500,000.00 0 01 0 1,439,739.00 10 4+187 km to 4+547 km at Weeagoda unit Cons of retaining wall and 400,000.00 0 01 01 1,101,930.00 bathing step at D/S of 11 Kallarichchai anicut inupper Kurunal Kanji unit Reh of kalladipattu road & 480,000.00 0 01 0 1,063,745.13 12 Kiddikadu drainage in Veeryadi Unit Reh of 10th Km in 1,288,000.00 0 01 0 1,169,091.00 13 Gonagolla branch channel Reh of M 18.15.2 D canal 2,1000,000.0 0 01 0 879,415.00 14 at Stn. 0+000 km in 0 Annamali Anicut Reh of M 18.16 D canal at 1,054,000.00 0 01 0 760,055.00 15 Stn. 0+000 to 1+000 km in Annamali Anicut Cons of regulator in 1,600,000.00 0 01 0 - Chettiyawattai branch 16 channel at stn 5+910 km in Senagappadai LB unit Reh of M 5.4.10 D canal 1,604,000.00 0 01 0 815,535.00 17 in Weeagoda unit

Impts to KL 26- KL30 in 1,238,000.00 0 01 0 908,347.57 18 Deegawapi unit

56 Gamaneguma Programme

N Description of works Allocation No of Items Extend Benefit Expenditure o 2009 Continue Commence Completed New Exist/ Total/ d from d in 2009 in 2009 /Acs Acs acs 2008 Raising of spill in Padagoda 204,000.00 tank in RB main channel at 225,00.00 1 0 01 01 stn. 8+700 km at Damana unit Raising of Maklayadi tank 262,000.00 150,000.00 2 spill way by 0.45m at 0 01 01 Damana unit Raising of Alahena tank 195,000.00 137,472.00 3 spill in RB main canal at 0 01 01 Damana unit Removal of waterweeds 3,607,000.00 1,200,000.00 (Diya kubuk) to open the 4 0 01 0 water body & desilting in Alahena tank Raising of crest level by 2 4,350,000.00 3,250,000.00 ft of the 3 Nos spill in 5 0 01 01 Walgama tank at Uhana unit Replacing damaged and 1,356,000.00 1,220,770.00 corroded gates with 6 spindles in Alayadi odai 0 01 01 anicut in Sengapadai RB unit Repairs to regulator at UB 7 0 01 01 12 canal in Uhana unit Slope protection in right 2,050,000.00 8 0 01 01 bank of LBMC at Uhana Repairs to LB 16-2 canal in 970,201.00 9 0 01 01 Uhana unit Improvements to LB slope 747,770.68 1 of the spill No2 of 0 01 01 0 Walgampura tank, Uhana unit Improvements to LB slope 1 of the spill No3 of 0 01 01 1 Walgampura tank, Uhana unit Construction of bathing 69,786.19 1 place at stn 0+605km in 0 01 01 2 Uhana branch canal , Uhana unit

Anuradhapura Range- 2009

Anuradhapura Regional Directors office coordinates the functions of 6 Divisional Irrigation Engineer’s offices who are responsible for operation and maintenance as well as improvements in Irrigation, Drainage and flood protection schemes.

• Anuradhapura Division • Huruluwewai Division • Padaviya Division • Rajangana Division • RE’s office – Nachchaduwa • Rambawa ME”s office Major Irrigation Scheme

1. Rajanganaya 2. Padaviya 3. Wahalkada 4. Huruluwewa 5. Manankattiya 6. Mahakandarawa 7. Mahawilachchiya 8. Nuwarawewa 9. Tissawewa/Abayawewa 10. Nachchaduwa Feeder canal scheme

57 DIVISION SCHEMES Extent in (Ha)

RDI's Office Anuradhapura Basawakkulama 156 Eru wewa & Feeder Canal 61 Galkadawala Wewa 141 Halpan Ela Anicut 240 Kadurugasdamana Wewa 107 Kallanchiya 243 Kandewa Wewa 94 Kapirigama Wewa 113 Karambewa Yoda Ela 237 Kawarakkulama 85 Keerakkulama (NEW) 174 Kokatiyagollewa Wewa 95 Mahabulankulama 89 Mahabulankulama Anicut 103 Mahakandarawa 2,470 Mahawillachchiya 1,079 Maminiyawa 177 Nuwarawewa 1,012 Nuwarawewa Complex Nuwarawewa Feeder chl. 325 Periya kulama 81 Pihimbiyagollewa 129 Tannayan Kulama 81 Thalagahawewa 142 Thambalagollewa Wewa 85 Tisawewa 365 Uttimaduwa Wewa 85 Weruppankulama 130 Huruluwewa Aluth Divul Wewa 115 Bellankadawela Wewa 81 Dekathipothana Wewa 146 Demata Wewa 45 Elle Wewa 103 Horiwila Wewa 287 Horowpothanawewa 173 Huruluwewa 4,049 Illukwewa Anicut 486 Iratiyawa Wewa 60 Kalpe Wewa 91 Kanadara Ratmale Wewa 153 Kanhinda Wewa 194 Kapugollewa Wewa 121 Kudapattiya Divulwewa 187 Maha Halmillewa Wewa 154 Mahakivulekada wewa 81 Mahawewelkada Wewa 101 Manakattiya 427 Maradanmaduwa Wewa 89 Moragahadigiliya Wewa 85 Muslim Walahawidda Wewa 89 Pandarallawwa Wewa 104 Panwela Wewa 52 Parangiyawadiya Wewa 293 Pethiyannekadawewa 88 Ranpathwila Wewa 108 Rasnaka Wewa 182 Serunewewa Mahawewa 81 Sinhala Walahavidda Wewa 168 Thawalanhalmillewa Wewa 101 Thirappankadawela Wewa 89

58

DIVISION SCHEMES Extent in (Ha) Wadiga Wewa 142 Wagollekadawewa 146 Wahagahapu wewa 81 Welimuwapothana Wewa 114 Padaviya Aiyatige Wewa 130 Bandara Ulpotha Wewa 162 Ellewewa Anicut 162 Ethakada Mahawewa 105 Gonuhathdena Wewa 95 Hendagama Wewa 108 Kebithigollewa Wewa 95 Kidawarankulama Wewa 151 Kirigollewa Wewa 108 Mahadivulwewa 113 Marakkala Etaweera Wewa 162 Medawachchiya Wewa 81 Muwaetagama Wewa 104 Padaviya 5,587 Sangilikanadarawa Wewa 340 Tittagonewa Wewa 96 Wahalkada 810 Watte Wewa 84 Rajangana Ambagaha Wewa 121 Itticulama Wewa (NEW ) 121 Kirindiwatta Wewa 188 Mahahoruwila Wewa 81 Manewa Wewa 81 Rajangana 5,523 Ralapanawa Wewa 101 Nachchaduwa Kalawewa-Tisawewa YodaEla Nachchaduwa 2,540 Nachchaduwa Feeder chl. 127 Thuruwila 187 Kadahathawewa 170 Labunoruwa 258 Mahalindawewa 172 Mahamankadawela 170 Mahamankadawela Wewa 140 Maningamuwa Wewa 85 Mankadawela Wewa 100

Medium Irrigation Scheme – 80 Nos

Recurrent Expenditure - 90,837,708.78

Capital Expenditure - 114,372,489.92

Other Votes

Repairs to IMDBuildings - 526,048.76

O & M Gravity works - 28,378,540.03

Preventive Maintenance - 2,394,804.98

Impts to Water Management - 934,934.64

Plant, Machinery & office - 5,562,935.95

59 Gravity Irrigation Works ( WAGES) - 4,082,887.84

DSWRP Project - -

Gamaneguma - 2,613,984.18

WAPHAULA Programme and IMAC Activities

In 2009 three new medium irrigation schemes were taken up under WAPHAULA PROGRAMME. At present there are 66 scheme functioning under above programme

ITEMISED works

Ellepothana Anicut

Project Features

Total Project cost Rs. 300 million

District - Anuradhapura

DS Division - Kahatagasdigiliya

IE’s Division - Huruluwewa

Source - Yan oya

Description of the Project

Construction of a diversion structure across Yan –Oya and diverting water to RB and LB through RB and LB canals respectively. Improve irrigation facilities to 1545 acres of land in LB & RB of the Yan oya by improving 8 Nos. village tanks.

Name of Tanks Irrigable area to be developed(Acs)

Wadigawewa 338 Elapathwewa 82 Wilewewa 75.25 Kudawewa 15 Thirappankadawala tank 294 Ellapothana – Siyabalawewa 40.5 Walahagahapuwewa 285 Expenditure - 31,241,959.27

Wahalkada Tank

DS Division – Kebithigollewa & Horowpothana

Year of commencing of the Project - 1998

Expenditure in2009 - Rs. .2..39 Mn

60 Batticaloa Range -2009

Batticaloa Regional Director’s office coordinates the functions of 2 Divisional Irrigation Engineer’s offices who are responsible for operation and maintenance as well as improvements in Irrigation, Drainage and flood protection schemes.

• Rugam Division • Navakiri Division

DIVISION SCHEMES Specified Extent (Ha)

RDI's Office Rugam Kaddumurivu 344 Kitulwewa 328 Punani 628 Rugam 3,948 Unnichchai 5,165 Vahaneri 3,441 Wadamunai 153 Weligahandiya 137

DIVISIONAL TOTAL 14,144.00 Navakiri Navakiri 7,087 Thumpankerny 271 DIVISIONAL TOTAL 7,358

(I) Assest Management Sub Department

1. Maintenance & Improvements to Buildings

Following works are performed in 2009 1.Impts to IE’s office Building, Rugam & RDI’s Bungalow 2.Const. of toilet to Thumpankerny unit office in Navakiri Division Completed 3. Const. of well to Thumpankerny unit office in Navakiri Division

2. Maintenance to Departmental Roads in Irrigation Scheme

• Rehabilitation of Varithamby anicut acess road in Unnichchai scheme - Completed

3.Flood Damage Repairs

1. FDR to Supply Channel of Kakachchivettai anicut in Navakiri division 2. FDR to River & Channels in odduveli & Makkilanakandam in Vahanery scheme Completed • FDR to U/S LB flood bund of Panaiyaruppan anicut in Navakiri division 4.Preventive Maintenance

1.Construction of temporary dam at Mavadiodai in Rugam scheme 2.Structure repairs to LB-43 Channel n Navakiri division 3.Repairs to Udayandachchenai anicut in Unnichchai scheme Completed 4.Reconstruction of damaged portion of rough in LB chl of Wadamunai tank 5.Improvements to Kanthankudamadu Regulator in Navakiri division 6.Construction of road crossing across the access road of Nadupanku anicut in Navakiri division 7.Repairs to Kochcharchenai anicut in Unnichchai scheme

61 5.Improvements to Major Works

1.Replacing the damaged steel gates & accessories to Ragunathan anicut in Navakiri division 2.Repairs to drop structure in RB 2 off WB channel in Unnichchai scheme Completed 3.Repairs to Mudakkumadu anicut in Unnichchai scheme 4.Repairs to Thaharavadi anicut in Unnichchai scheme (Continues work of 2008) 5.Const.of channel spill in Kaddumurivu LB main channel (Continues work of 2008)

Irrigation & Water Management Sub Department

ISRP

1.Rehabilitation of D2 chl & bund road in Vahanery scheme Rugam Division (Continues work of 2008)

Improvements to Water Management

1.Repairs to Muthiyarvadi Anicut in Unnichchai scheme 2.Improvements to 3 way regulator at stn 47+018 along LB main chl in Navakiri division Completed

Regional Development & Construction Sub Department

CIADP

1.Construction of Munaiwaram anicut in Navakiri division (Continues work of 2008 2.Additional work of Thavanamadu anicut in Unnichchai scheme Completed

Environmental Drainage & Flood Protection Sub department

Following works are performed in 2009

Drainage and Flood Protection

1.Construction of Morning glory spill along K2 D channel in Navakiri division Completed 2.Desilting of Muruukanthivu distributory & drainage channel in Vahanery scheme

PERFORMANCE OF THE FOREIGN FUNDED PROJECT

Batticaloa Town,Kattankudy,Araiyampathy, Eravur Pattu, Eravur Town. Irrigation Department s responsible for the augmentation activities of the Tank. Water Supply Scheme-National Water supply and Drainage Board. Contractor- Access Engineering Ltd

Total Source of Expenditur S.No Main Activities Accocation Status Fund e (Mn) ( Mn)

Raising of Unnichchai Tank Bund and Construction & Completion of its Appurtenant Structure 1 Embakment Construction Asian Work Developm 443.0 810.0 2 Instrumentation Completed ent Bank 3 Concrete Production & Construction 4 Concrete in Structures 5 Precast Concrete Total allocation 443.0 810.0

62 Rehabilitation of Rugam Major Scheme under Re-awakening Project

Brief Description and scope of the project.

It is a major irrigation scheme under the custody of Irrigation department

The entire irrigation system is in a dilapidated condition currently and needs extensive rehabilitation to restore its originally designed potential of the scheme.

Under the Re-awakening Project which is funded by the World Bank it is proposed to undertake the identified essential rehabilitation works to restore its original status.

It is aimed to rehabilitate the head works, roads selected canals , drainage channels and anicuts ensuring the issue of irrigation for cultivation of proposed paddy lands during both Maha and Yala seasons.

Total S.N Source Expenditure Main activities Allocation Status o of Fund (Mn) (Mn)

Rehabilitation of Rugam Major Scheme under Re-Awakening Project( NEIAP II) 1 Improvements to Head works 2 Improvement to Roads World 86.0 Mn work 340.0 86.0 3 Rehabilitation of Anicut Bank completed Structure 4 Replacing Sand dams by Anicut structure 5 Rehabilitation of Irrigation Main Channels 340.0 86.0

Total

Achievement:

• Improvements to Head works 70% work completed • Improvement to Roads 70% work completed • Rehabilitation of Anicut Structure 60% work completed • Replacing Sand dams by Anicut structure 20% work completed • Rehabilitation of Irrigation Main Channels 45% work completed

Bandarawela Range

Bandarawela Regional Directors office coordinates the functions of 3 Divisional Irrigation Engineer’s offices who are responsible for operation and maintenance as well as improvements in Irrigation, Drainage and flood protection schemes in two administration districts.

• Badulla Division

• Mapakada Division

• Kandeketiya Division

63 DIVISION SCHEMES Specified Extent (Ha)

RDI's Office Badulla Ambewela 405 Dambawinna 101 Diyabana Oya 315 Kande Ela 971 Maha Eliya 202 Mahatotilla 202 Taldena 141 Uma Ela 708

DIVISIONAL TOTAL 3,045 Mapakada Dambarawa 426 Dehigama 96 Demodara 202 Mapakada 542 Nagadeepa 1,680 Soraborawewa 800

DIVISIONAL TOTAL 3,746

Kandeketiya Badulu Oya 567 Bathmedilla 570 Komarika Ela 566

DIVISIONAL TOTAL 1,703

Nildiyawara Auditorium - 100% completed

Upgrading local cattle in Komarika Ela Scheme under IMAC Activities

Prevention of Soil erosion in canal banks of Komarika ela , Uma oya, Dehigama/ Demodara Schemes.

Colombo Range -2009

Colombo Regional Directors office coordinates the functions of four Divisional Irrigation Engineer’s offices who are responsible for operation and maintenance as well as improvements in Irrigation, Drainage and flood protection schemes in two administration districts in western and Sabaragamuwa provinces

7. Colombo Division

8. Gampaha Division

9. Kalutara Division

64 10. Ratnapura Division..

DIVISION SCHEMES Specified Extent (Ha)

RDI's Office RDI's Office Colombo Boralesgamuwa 94 Talangama tank 83 DIVISIONAL TOTAL 177 Ratnapura Ratnapura Batugedara 87 Damme Ela 143 Hulanda Oya 95 Kaltota 923 Katupath Oya ( New ) 400 Panamura 456 Walalgoda 202 Wellawa 142 DIVISIONAL TOTAL 2448 Kalutara Kalutara Uyanwatta 142

DIVISIONAL TOTAL 142 Gampaha Attanagalu Oya 4,426

DIVISIONAL TOTAL 4,426

Kalutara Division

Most of the canals have been cleared under the funds of the Ministry of Disaster Management and Southern Transport Development Project in 2009 and also provided lifting wooden gates to Toragala MFP structure in Kaluganga Scheme.

Project completed within- 2009

Departmental Funds

• Provided of lifting wooden gates to Toragala MFP structure in Kaluganga Scheme. No of gates 2 size 5”-6” - 7”-0” physical progress – 100%

• Rehabilitation of Rathable ela anicut scheme in Dambara. Physical Progress – 80%

Disaster Management Ministry

• Impts to Ilukgolla ela in Bolgoda scheme. Improved length – 1250m - physical progress – 100% • Impts to Digapatha ela (Dr. channel No 1) improved length – 853 m- physical progress – 90% • Impts to Moda ela (Dr. channel No 2) improved length – 427 m- physical progress – 100% • Impts to Radan ela, Uyanawatta wewa scheme. Improved length , - physical progress – 100% • Impts to Digapatha ela (Dr. channel No 1) improved length – 378 m-- physical progress – 100% Southern Transport Development Project

• Impts to Dowa ela in Bentara RB scheme. Improved length – 1250m - physical progress – 100% • Impts to Lenthiri ela in Bentara RB scheme. Improved length – 950m - physical progress – 100%

65 • Impts to Lewwanduwa ela in Bentara RB scheme. Improved length – 1650m - physical progress – 100% • Impts to Paraigama ela in Bentara RB scheme. Improved length – 1.2 km - physical progress – 100%

These canals were covered completely with weeds such as jabara and also those were not cleared for last 4-5 years. Therefore following of flood water very slow and lands were inundated for about 2 weeks in s heavy rain. People requested to clear these canals from a long time and about people were benefited after the successful completion of those projects.

Hettige oya Scheme

This scheme is situvated in Kaduwela and Homagama Divisional secretariat divisions in Colombo District. Project was launched in 2005 and it will be continued until end of this year. The estimated project cost was Rs. 42 Mn and cumulative expenditure upto end of 2009 was Rs. 19.9 million. The aim of the project is to provide proper drainage facilities and structural improvements for 400 Acs of paddy lands.

Improvements to 9.48 km length of main drainage canal and 20.50 km length of branch channels, number of channel structures, drops regulators and crossing structures have been constructed. In year 2010 it is planned to improve 3.0 km of Godagama ela , Kotigahala Wanduramulla road and provide RCC Hume pipes for improved canals.

There are 16 Nos of farmer organizations in this scheme. In addition to that they have made and organization named as “Hettige oya Surakeeme Sanvidanaya” to carry out a better service through the scheme.

Total paddy cultivation under the project has increased from 400 Acs to 1700 Acs up to now and this scheme has become the major paddy cultivation area in Colombo District. The highest yield (III.2 Bushels/ Acs) was observed in the Meegasmulla area in this scheme. Achived benefits under the project were highly appreciated by the farmer organization and the environmental and health benefits were clearly observed.

Gampaha Division

Departmental Funds

• Kelani ganga minor flood protection project – fixing gates – 100% completed • Kelani ganga minor flood protection project – improvements to Malwana, Pattiwila, Thalawatta – 100% completed • Construction of Nammawila culvert – Tammita Anicut • Supplying & Fixing 5 Nos of gates for Thammita Anicut • Supplying & Fixing lifting gates for Pathakada Anicut • Fixing of 4 Nos gates for Batapath jail ela • Fixing flood protection gates for Ja-ela flood bund

Flood Damage Repairs

• Construction of tractor crossing in Kinigama • Supplying & fixing gates for Galwetiya Anicut • Construction of Polonmulla drainage canal structure for Doranegoda Anicut • Fixing 4 Nos of gates for Ketawala Galwala Anicut • Reha of RB 4 canal in Ketawala scheme was done under CIADP programme Gama Neguma - 2009

• Clearing no.of drainage canals was done under the project • TCE was 18.82 Mn and 30531 farmer families were benefitted from these project

SIRUP Project – 2009

2. Rehabilitation of Galwala Anicut in Kinigama scheme 3. Construction of Tractor crossing in main canal of Kinigama RB 4. Rehabilitation of Right & Left canals of Nahitiya

Ratnapura Division

Construction of Kaltota Causeway

66 This located at Balangoda Divisional Secretariat area of Ratnapura District in Kaltota Scheme (LB Demodara) . This causeway was constructed across Walawe ganga by linking demodara and WaLIPOTHA. Estimated cost was Rs. 1,963,000.00 . This was started to do with direct labour system on 07-02-2009 and completed by the end of year 2009.People requested to construct this caseway from a long time and now about 200 families were benefitted from this project

Also following benefits were observed with the completion of the Project

• Easy to do O & M works in Irrigation Department

• Saving of time and abour of school student and farmers

• Easy to access to Irrigation Department, Hospital, Agricultural Department, Agrarian Sevicer Department, Bank, Filling station and Bus road in a short time

• Increase the association and coordination of the people in that area.

Galle Range- 2009

Galle region of the Irrigation Department is responsible for managing all major and medium irrigation drainage and flood protection schemes in two administrative districts Galle,Matara. Galle region comprised of three I.E.’s division to manage above schemes and one mechanical workshop at Halpatota to take care of electro mechanical installation in pumping stations at flood protection schemes and vehicles and machinery attached to the region.

3. Matara,

4. Ambalangoda

5. Ginganga

DIVISION SCHEMES Specified Extent (Ha)

RDI's Office Ambalangoda Aluthpahala Kepu Ela 97

DIVISIONAL TOTAL 97 Gin Ganga Holuwagoda 464

DIVISIONAL TOTAL 464 Matara Alawatugoda Anicut 136 Dediyagala Anicut 141 Denagama Tank 343 Diyalape Anicut 283 Ellewela 528 Hali Ela Tank 100 Hamaragoda Anicut 144 Kekanadura 445 Pettara Anicut 318 Sapugoda Anicut 125 Urapola Anicut 627 Uyanwewa 98 DIVISIONAL TOTAL 3288

67 Operation & maintenance works of following irrigation and drainage schemes are managed by Ambalangoda divisional Office.

Scheme Type Gross Extent (Acs.)

(1) Dedduwa Drainage Scheme 2100 (11) Rantotuwila -do- 2000 (111) Uthurupitigala -do- 200 (1V) Aluthpahala Kepuela Gravity Irrigation Scheme 240

O & M works of following Irrigation & Drainage Schemes are managed by the Ginganga divisional office. Scheme Type Gross Extent (Acs.)

(1) Ginganga Drainage & F.P.scheme. 12360 (11) Holuwagoda Gravity Irrigation Scheme 1140

O & M works of following Irrigation & Drainage Schemes are managed by the Matara divisional office.

Scheme Type Gross Extent (Acs.)

Nilwala Drainage & F.P. scheme. 13410 Denagama,Uyanwewa Ellewala, Haliela,Kakanadura, Sapugoda, Peththra, Gravity Irrigation Schemes. 8832 Urapola, Alawathugoda Dediyagala ,Diyalape Hamaragoda

Construction of Mechanical Engineer’s quarters Construction of Drivers room at Halpathota at Beligaha RDI Office

The following constructions of the departmental roads in irrigation scheme were done.

1. Construction of Uthurupitigala causeway. 2. Construction of box culvert in Sapugoda main canal.

68 The following works of canals were done in several schemes.

1. Construction of under crossing at Haliela main canal. 90% of work was completed. 2. Channel lining of main canal in Haliela. 80% of work was completed. 3. Concrete lining at dediyagala main canal. 4. Concrete lining at in main channel in Sapugoda scheme. The following improvements were done in existing irrigation works.

• Making and fixing wooden lifting gates 3 numbers in Diyalape. • Making and fixing anicut gates for Kadaedduwa sector.90% works were completed. • Making and fixing lifting gates in Kiralakele sector.

The following improvements of head works were done in the region.

Improvements to down stream of Uyanwewa spillway with Renomettress. 90% works were completed. Filling pot holes and gravelling Kumburuhena bund.90% works were completed. Down stream protection of spill cum cause way of Kumburuhena tank bund. Performance of the region specially project funded by the other organizations

5 Irrigation Scheme Rehabilitation Project. (ISRP)

Under the above scheme the following works were completed.

5. Construction of concrete lining in LBMC of Denagama scheme. 6. Providing lifting gates & construction of drop structure 30m of LBMC Denagama. 7. Construction of concrete trough at Urapola scheme. 8. Supplying & fixing of anicut gates for Pitamulana anicut in Urapola scheme. 9. Supplying & fixing of anicut gates for Komanovita anicut in Urapola scheme. 10. Supplying & fixing of anicut gates for Dodangasmodara anicut in Urapola scheme 11. Construction of toe wall in main canal at Urapola scheme. 12. Construction of SWE structure in Dedduwa scheme. 13. Improvements to Maddu Ela in Dedduwa scheme. 14. Improvements to Meegaspitiya d ela. 15. Improvements to Puwakgaha channel in Ranthotuwila scheme.

(B) Construction of wedakade anicut in Matara division was done by fund of RDA.

Construction of wedakade anicut in Matara division Channel lining of main canal in Haliela.

69 Hambantota Range

Hambantota Range activities were administrated under the supervision of RDI with the assistance of Divisional I.EE. There are five I.EE divisions.

• Hambantota Division • Weeraketiya Division • Kekiri obada Project • Weheragala Project • Tissamaharama Division

SCHEMES DIVISION Specified Extent (Ha)

RDI's Office Tissamaharama Badagiriya 668 Debarawewa 383 Gemunupura 97 Lunugamwehera 5,364 Pannegamuwa 227 Tissawewa 1,113 Weerawila Wewa 931 Yodawewa 1,323

DIVISIONAL TOTAL 10,106

Hambantota Mahaaluthgam Ara 142 Minor Tanks : Maha Indi Wewa Bogaha Indi Wewa Kuda Indi Wewa Malasnagala Hodi Pirunu Wewa Wehera Pelessa Wewa Pahala Kumbuk WewaMahagal Wewa 162 Mau Ara Pahala Andara Wewa 85 Pallematttala Wewa 134 Ranmuduwewa 81 Walawe LB ( Ridiyagama ) 2,742 Walawe RB 2,546 Minor Tanks 135

DIVISIONAL TOTAL 6027

Weeraketiya Kirama Oya 2,140 Muruthawela 1,792 Pattiyapola Mahawewa 263 Urubokka Sch 2,263

DIVISIONAL TOTAL 6,458

70 O & M Schemes in the Range

Division Scheme Specified extent (Ha) Allocation (Rs)

R.D.I’s Office Overheads 364000.00

Tissa Bandagiriya 668 482000.00

Deberawewa 383 281000.00

Gemunupura 97 134000.00

Lunugamwehera 5364 3807000.00

Pannegamuwa 227 155000.00

Tissawewa 1113 792000.00

Weerawila 931 663000.00

Yodawewa 1323 936,000.00

Overheads 363,000.00

Hambantota Maha 142 162,000.00 Aluthgamara

. Mahagalwewa 162 120,000.00

Mau Ara 1,575,000.00

Pahala 85 72,000.00 Andarawewa

Pallemattala 134 66,000.00

Ranmuduwewa 81 63,000.00

Walawa LB 2742 1,807,000.00 (Ridiyagama)

Walawa RB 2546 1,797,000.00

Minor Tanks 135 135,000.00

Overheads 290,000.00

Weeraketiya Kirama oya 2140 1,320,000.00

Kongal ara 132 66,000.00

Muruthawela 1792 939,000.00

Pattiyapola Maha 263 144,000.00 wewa

Urubokuoya 2263 1,470,000.00

Overheads 194,000.00

Total 18,197,000.00

71 Project funded by other organizations.

Wild Life Department

Allocation Expenditure Physical Progress

6) Construction of Butawa wewa. - 2,906,514.00 2,872,174.43 100% 7) Construction of Korawak wewa. - 832,000.00 562,157.50 100% 8) Construction of Gonagalara wewa. - 725,485.33 711,925.00 100% Kandy Range

Kandy Regional Director’s office is responsible for maintaining and rehabilitation of all major and medium schemes in entire Central province, which includes administrative districts of Kandy, Matale and NuweraEliya. This region comprised of five Irrigation Engineer’s divisions.

Kandy Division Matale Division Dambulla division Minipe Division NuweraEliya Division

I.E. DIVISION SCHEME IRRIGABLE AREA (Ha.)

Gampolawela Rajaela 164

Kithulpe ela 137

Udugoda Bandara Ela 163

Ma Ela 654

Kandy Lamasooriya 161

Bodhi Ela 154

Kehelpath Amuna 100

Murapola Ela 555

Bandara Amuna 97

Divisional total 2185

Waduwawala 194

Bolagandawela 148

NuwaraEliya Keenawela Ela 102

Paragahaarawa 97

Mulhal Ela 152

Divisional total 693

Bellan Oya 82

Dewahuwa 947

Pahala Araula Wewa 138

Dambulla Wewala Wewa 97

Wemadilla Wewa 906

Nalanda & Ebbawala 79

Mahanikatuwa wewa 81

72 Dambulu oya 161

Divisional total 2491

I.E. DIVISION SCHEME IRRIGABLE AREA (Ha.)

Minipe Rathna Ella 107

Himbiliyakada Wewa 155

Radagalpotha 86

Minipe Main chl. 7400

Divisional total 7748

Matale Hattota Amuna 296

Meewelpitiya Wewa 82

Bowatenna 126

Kandepitawela 242

Divisional total 746

Range Total 13863

Block Vote Items

No. of Items No. of Items Allocation Description and Vote Particulars commenced completed in Expenditure (Rs.) (Rs.) in 2009 2009

O & M Gravity Works- ID(Wages ) 4,814.54 5 5 4,814.540

Repairs to Vehicles 1,273.692 10 5 1,102.530

Maintenance of Dept.Roads 2,756.45 8 5 2756.45

Maintenance of 4,250.00 6 2 4,204.410

Flood Damage Repairs 6,844.546 27 15 6,162.16

Improvements to Building & Electrical 3,565.64 33 11 3,565.637 Installation to Departmental Buildings

Improvements to H /W for Addl. Safety 2,690.00 4 3 2,782.220

Preventive maintenance 2,647.65 11 3 2,128.215

O & M Gravity Works & Over heads -IMD 11,932.17 45 13 11,181.011

Impts.to Major Works 2405.084 10 5 1,589.918

Impts.to Water Management 2,153.370 11 3 1,533.685

Rehab. Of Office Equipment 162.616 7 3 173.325

73 SIRUP

Construction of Wemadilla Reservoir - Kandy Range

TEC Rs. 250.0 Mn.

Allocation for the year 2009 Rs. 12.0 Mn.

Expenditure up to Dec. 2009 Rs. 10.74 Mn.

Cumulative Expenditure up to Dec. 2009 Rs. 235.57 Mn.

Overall Physical Progress 99.5%

Overall Financial Progress 94%

Itemized work

Construction of Gurugal oya - Kandy Range

TEC Rs. 180.0 Mn.

Allocation for the year 2009 Rs. 10.891 Mn.

Expenditure up to Dec. 2009 Rs. 10.405 Mn.

Cumulative Expenditure up to Dec. 2009 Rs. 10.605 Mn.

Overall Physical Progress 18%

Overall Financial Progress 6%

Deposit Account

“ Dayata Kirula ” Programme

Improvements to existing Tank at Sri Lanka International Buddhist Academy , Pallekele under in Kandy Division.

TEC Rs. 4.90 Mn.

Allocation for the year 2009 Rs. 4.00 Mn.

Expenditure up to Dec. 2009 Rs. 1.50Mn.

Overall Physical Progress 35%

Overall Financial Progress 30%

Dankanda Katarantenna Upper Tank

TEC Rs. 5.455 Mn.

Allocation for the year 2009 Rs. 5.455 Mn.

Expenditure up to Dec. 2009 Rs. 5.005 Mn.

Overall Physical Progress 100%

Overall Financial Progress 92%

74 Surveying of Minipe main canal from 0.0 km to 12.0 km

Desilting / removing water weeds in minor feeder tanks in the scheme

Desilting in Minipe Main Canal

Construction of Deyata Kirula Wewa Construction of Dankande Katarantenne Sluice

75 Kurunegala Range

Kurunegala RDI’s office coordinates the functions of 04 Divisional I.EE. offices .

1. Hiriyala Division

2. Nikaweratiya Division

3. Galgamuwa Division

4. Katugampola Division

Specified Extent (Ha) DIVISION SCHEMES Batalagoda & RDI's Office Dolukanda 2,046 Hiriyala Diyatura 192 Hakwatuna Oya 1,656 Kimbulwana Oya 666 Kospothu Oya 53 Meddeketiya 93 Moragoda 228 Morathi Oya 101 Welikumbura 116 Wennoru Wewa 192

DIVISIONAL TOTAL 5343

Galgamuwa Abakolawewa 340 Attaragalla 419 Mahagalgamuwa 164 Mahananneriya 158 Mahasiyambalangamuw a 165 Palukadawala 820 Usgala Siyambalangamuwa 667 Usgala Siyambalangamuwa Feeder canal 2.23 Km

DIVISIONAL TOTAL 2733 Nikaweratiya Hulugalla 84 Kadiragala 89 Kekirihena 142 Magalla Wewa Mediyawa 394 Ridi Bendi Ela 2289 (Head Works & Feeder Chl.) DIVISIONAL TOTAL 2998 Katugampola Kiniyama Scheme 356 Madulla 140 Makandura 304 Nikapitiya 101 DIVISIONAL TOTAL 901

76 Itemized work and Block Vote Items -2009

No Description of Work Allocation No.of items No of items Expenditure Rs. commenced in completed in Rs. 2009 2009 01 O & M Lift irrigation 364,161.00 4 4 243,980.00 02 Main. Of Dept Road 944,912.00 10 7 859,280.00

03 Flood damage repairs 1,044,259.00 8 7 653,120.00

04 Main. & Impts to building 13 8 631,770.00 866,849.00 05 Impts to H/W of tanks for additional safety 11 6 1,985,320.00 1,186,400.00 06 Repairs to IMD Buildings 3 3 787,500.00 832,752.00 07 Impts. To Major works 12 10 443,190.00 738,385.00 08 Impts. To water management 11 6 594,090.00 606,780.00 09 Preventives maintenance works 23 3,618,980.00 15 10 Impts. Upgrading the Hydrological monitoring & 4,648,114.00 4 230,710.00 flood warning ) 1 196,278.00

11 Management supporting facilities for O & M 4 409,740.00 4 12 Safe guarding of deptl. Land & reservation 427,000.00 3 521,400.00 2 13 Investigation surveys 5 76,400.00 762,185.00 14 Repairs to Vehicles 2 2 218,020.00 472,100.00 2 209,615.00

Operation and Maintenance

O & M work attended during the year the as follows

Major systems 08 Nos 24446 Acs.

Medium Systems 17 Nos 7109 Acs.

Operation and Maintenance

Allocation - Rs. 9,060,000.00

Expenditure - Rs. 6,709,000.19

Progress - 100%

Cultivation Performances ( Gravity Systems)

Total command area - 36047

Maha Season 2008/2009

Paddy - 353339 Acs

OFC - -

77 Reported Crop failures - 456 Acs.

Yala Seasons 2009

Extended cultivated - 22886

Paddy - 20656 Acs

OFC - 2230 Acs.

Reported crop failures - 25 Acs.

Special Project Works

ISRP

Improvements to channel system of Wellangiriya lift irrigation schemes- Bathalagoda Scheme

Allocation - Rs. 489,900.00

Expenditure - Rs. 101,671.00

Patharagala wewa

Construction of Patharagala tank started & happened to stop due to lack of funds.

Estimated funds - Rs. 32,400,000,00

2009 year Allocation - Rs. 24,000.000.00

2009 year Expenditure - Rs. 11,126,000.00

Total Expenditure - Rs. 18,900,000.00

PEACE Project, JICA Project & Deduruoya Project are in the region

Investigation

Hiriyala Division - Ginikarawa tank, Pandeniya tank & Adagala tankt

Galgamuwa Division - Siyambalangamuwa oya to Maha Galgamuwa tank

Katugampola Division - Yakamunna Anicut

Moneragala Range -2009

Monaragala Range activities during the year 2008 were administrated under the supervision of l RDI with the assistance of Divisional I.EE. There are 3 I.EE divisions and Construction office at Welioya is headed by a Resident Engineer.

1. Moneragala Division

2. Wellawaya Division

3. Bibile Division

78 Specified DIVISION SCHEMES Extent (Ha)

79 RDI's Office Monaragala Buttala 640 Ethimale 406 Hulandawa LB 90 Kotiyagala 182 Kubukkan Oya 754 Muthukandiya 827 Saddatissa 170 Yudaganawa 180

DIVISIONAL TOTAL 3249 Wellawaya Alugalge 100 Balaharuwa 84 Dambe Wewa 92 Debara Ara 96 Gal Amuna 200 Halmillapillewa 106 Hambegamuwa 270 Handapanagala 400 Horabokka 100 Kahakurullanpelessa 100 Kandiyapita 144 Karawila, Milagama, Detagaha 160 Kukurampola 146 Mahawewa 100 Pelawatta 120 Radapola 120 Sudupanwela 240 Weli Oya ( New ) Irri. Area ? 800 DIVISIONAL TOTAL 3378

Bibile Badulu Oya 212 Dehiattawela 296 Magandana Oya 80 Monarawana 93 DIVISIONAL TOTAL 681

Major Project

Restoration of Sugaladevi Tank

This is an ancient abandoned Tank located across Govinda oya which is a tributary of Karanda oya and supposed to irrigate 750 Acs. of new land in Siyabalanduwa divisional secretary division , Moneragala District. The total estimated cost of the work was Rs. 75 m. The work was awarded to Devecoshowa (Pvt) Ltd on negotiated terms in 1998. Due to poor financial management, this agency could not proceed with the work and work was abandoned in the letter part of the year 2001. Then irrigation department decided to terminate the contract at that time contractor had completed approximately 50% of the work . Subsequently department under took the balance construction work in the year 2002 and completed the same and impended water. Construction of head works, main canal and relevant structures in the main canal were completed. The construction of down stream development work was executed by the Irrigation Department and it was planned to be completed by the end of 2005. Due to delaying construction, price escalation some earth work and delaying obtaining land released from Forest Department estimate has been

80 revised and cabinet approval was granted for Rs. 119 m in 2007. Cumulative expenditure up to end of 2007 is Rs. 98,147 m. Although the attempt made to release the lands from Forest Department for construction distribution canals was successful. The Timber Corporation failed to complete the clearing of timber from the irrigable area. Hence there is no expenditure incurred during year 2007. The allocation revised for year 2008 was Rs. 15.0 m and expenditure incurred during year 2009 was Rs. 2.278 m.

The allocation received for year 2009 was Rs. 19.0 mn and expenditure incurred during year 2009 was Rs. 15.453 mn . Culalative expenditure upto end of year 2009 is Rs. 115.879 mn. And cumulative progress up to end of year 2009 is 99%

The following works were carried out during year 2009

Impts. To main canal

Construction of DC 1 including FC1,FC2,SFC2,FC4

Construction of DC2 including FC 6

Construction of DC3

Construction of DC 4

Providing toe drain and loading berm

Construction of steps to reach bund from sluice down stream

Impts to access road to tank bund

Impts to main canal bund road

Centenary Irrigation Accelerated Development Project (CIADP)

Dambewewa Scheme

Construction of 2 Nos box culverts were proposed under CIADP and allocation received for year 2009 is Rs. 1.605 Mn and expenditure at the end of 2009 was Rs. 1.165 Mn.

Small Scale Infrastructure Rehabilitation and upgrading Project (SIRUP)

Muthukeliyawa Project

Muthukeliyawa Project to augment several tank in RB of Menikganga in Buttala area is to facilitate IFF for 750 Acs. The total cost of the project is 77 mn. and the work was commenced in 2004 during the year 2007. Department machineries were deployed for rock excavation to construct feeder canal from Kongaha wewa to Serugas Ara wewa. The allocation for 2009 is Rs. 4.0 mn. and the expenditure of Rs. 3.157 mn was incurred at the end of Dec 2009. Cumulative expenditure was year 2009 Rs. 64,736 mn. and cumulative progress up to end of year is 77%

The following works were carried out.

Structures from Serugas ara to Drainage canal Construction of through at 5+ 492 km Kongahawewa to drainage canal. Structure from Karawila kanatta to Tammenna ara wewa.

Irrigation Scheme Rehabilitation Project (ISRP)

4 medium irrigation schemes were taken up under above project and the expenditure for 2009 is Rs. 2.109 m

Name of Scheme Expenditure

Pelwatta Rs. 293,000.00

Kandiyapita Rs. 316,000.00

81 Monarawana Rs. 879,000.00

Badulu oya Rs. 621,000.00

Lower Uva Minor Irrigation Rehabilitation Project (LU MP)

Development of water resources in the upper zone of Kirindioya was discouraged during last few decades owing to the water shortage experienced in the Lunugamwehera reservoir. When the augmentation of the Lunugamwehera was proposed by diverting water from Menikganga farmer community in the Moneragala district made a storage request that long outstanding Water Resources Development issues in the Lower Uva Area also to be considered in parallel to the Menikganga diversion works.

A memorandum of understanding was signed in this regard between Irrigation Department and District Secretary( Moneragala) In this MOU certain development areas were identified and it is agreed that ID shall properly investigate those proposals and implement if found technically feasible and economically viable.

The allocation for year 2009 for Lower Uva , minor irrigation rehabilitation project was Rs. 35 mn and the following minor schemes were rehabilitated

Expenditure during the year 2009 Rs. 30.414 Mn

Operation, Maintenance , Improvements & Institutional Activities

Operation and Maintenance

Allocation was Rs. 7,687 mn an expenditure of Rs. 7.676 m increasing the allocation to suit the ever rising cost of material, transport etc is vital for proper maintenance and up keep of scheme.

Improvements to Major works

An allocation of Rs.2,807,400.00 was received for above work carried out and completed within the year.

Puttallam Range

Puttalam Range RDI’s office coordinates the functions of 2 divisional I.EE offices. 4. Puttalam Division 5. Inginimitiya Division

DIVISION SCHEMES Specified Extent

(Ha)

RDI's Office Inginimitiya Inginimitiya 2,160 Mahandarawewa 151 Mahauswewa 364 Puliyankulama Feeder Chl. ( New ) Radavi Bandi Ela 240 Radavi Bandi Ela RB & LB Uriyawa 119

DIVISIONAL TOTAL 3,034 Puttalam Eluwankulama 219 Karawita & Mahawilawaththa 383 Kottukachchiya 347 Neelabemma 146 Neelabemma Feeder chl 527 Pahariya 146

82 Pawattamadu 121 Rathambala Oya 616 Sengal Oya Complex 455 Sengal Oya Feeder chl 161 Tabbowa 847 Wattakandal 202 DIVISIONAL TOTAL 4,170

Implemented works and achievements in 2009

No/Works Description No of works item Expe. (Rs) implemented

1.11.1O & M Gravity works 22 6588 1.21.2Maintenance of Deptl. road 05 971 1.31.3Maintenance & Impts to buildings 06 992 1.41.4Flood Damage Repairs 03 560 1.51.5Repairs to vehicle 06 818 1.61.6Repairs to IMD Building 03 988 1.71.7Impts to Head works for Additional sefty 04 1067 1.8t1.8Purchase of furniture of office equipment 01 171 1.91.9Preventive maintenance 04 633 1.11.10Impts to Major works 02 124 1.111.11Improvements to water management 03 477 1.121.12Repairs to office equipments 02 48 1.13I1.13Irrigation system Technology Improvement 01 168 1.141.14Repairs to machinery 02 21 1.151.15Const. of New quarters & office building the ID 02 893 ISRP

Pawattamaduwa New RB Area Scheme

The allocation for 2009 was Rs. 861,269/- and expenditure was Rs. 817,132.65/- Physical progress achieved during the year 2009 was 100% of earth work on bund and retaining wall.

Re-settlement of Families Displaced from Deduru oya Reservoir Project under Deduru iya Project

Parts of the above work done by Inginimitiya division, under main supervision of Deduru oya Project Director, and Physical progress achieved was as follows.

No. Works Description Progress beginning Progress end of 2009 2009

1Land survey at Heenatikulama part 1 50% 100% 2 Land survey at Heenatikulama part 11 0% Suspended 3Impts. To pipe culvert at 20.8 chs. In D3 tract 0% 100% 3 in Radavi Bendi Ela canal 4Ihala Nelumwewa survey 0% 100% 5Proposed community centre 0% 100% 6Providing drinking water 0% 100% 7For canal trace surveying for Heenetikulama 0% 100%

Investigation of RB Main Canal under Deduru oya Reservoir Project

No.NoWorks Description Progress beginning Progress end of 2009 2009

Survey Works in RB main canal from 0% 80.00%

83 Hidogama Tank bed to Inginimitiya tank bed1

The total allocation for item 3 and 4 during year 2009 was Rs. 54.6 million . The expenditure was Rs. 3.0 Mn.

Dam Safety and Water Resource Planning Project (DSWRPP)

Tabbowa and Inginimitiya major schemes have been selected for this Project from Puttalam Range. The estimates for Inginimitiya head works already been prepared and submitted to Head office. The estimations of hard works of Tabbowa Tank is in progress

Polonnaruwa Range

Polonnaruwa RDI’s office coordinates the functions of 4 Divisional I.EE offices.

• Polonnaruwa Division

• Minneriya Division

• Kaudulla Division

• Elahera Division

DIVISION SCHEMES Specified Extent (Ha)

RDI's Office Kaudulla Bebiyawewa 89 Kaudulla 5,060

DIVISIONAL TOTAL 5,149 Polonnaruwa Boo Wewa 83 PSS 10,212

DIVISIONAL TOTAL 10,295 Elahera Attaragallewa 210 EMYE (From Elahara to Diya- 6,073 beduma and Girithale) Heerati Oya 81 Mahaweli System G 5470

DIVISIONAL TOTAL 11834 Minneriya Erige Oya 104 Giritale 3,076 Minneriya 9,054 MKYE 167 (From Minneriya to Gal Oya)

DIVISIONAL TOTAL 12401 Trincomalee Range -2009

Trincomalee Range RDI’s office coordinates the functions of Three divisional I.EE’s offices.

84 1. Kantale Division

2. Muthur Division

3. Gomarankadawala Division

DIVISION SCHEMES Specified Extent (Ha)

RDI's Office Kantale Kantale 5,497 MKYE (24.5 Km) (From Gal Oya to Kantale) Peramadu 243 Vendrasan 650 Wan-Ela 638

DIVISIONAL TOTAL 7,028

Muthur Allai 7,050

DIVISIONAL TOTAL 7,050

Gomarankadawala Mahadivul Wewa 563 Morawewa 1,635 Yan Oya 589

DIVISIONAL TOTAL 2,787

RANGE TOTAL

S.I Description of Vote Allocation in (Rs.) Expenditure in (Rs.) Physical Progress 1 O & M Gravity Works - Wages 2,200,000.00 2,175,127.04 100.00%

2 O & M Gravity Works - IMD 13,233,236.00 12,119,030.40 100%

3 Management Supporting Facilities 450,000.00 449,751.74 100%

4 Maintenance of Dept. Road 1,666,731.00 1,052,912.22 70.30%

5 Improvements to Building 2,000,000.00 1,588,808.08 100%

6 Preventive Maintenance 2,395,098.00 2,189,489.00 100%

7 Impts. to Major works 1,069,238.00 447015.74 100%

8 Impts. to Water Management 663,820.00 435,477.34 100%

9 Flood Damage Repairs 1,459,364.00 816,221.47 100%

10 Repairs to Machinery 232,000.00 190,804.86 100%

11 Repairs to Vehicles 836,935.00 832,191.67 100%

85 Desilting d/s of mahadivulwewa sluice

MUSEUM

Total Estimated Cost - Rs. 21,000,000.00

Expenditure - Rs. 15,958,492.34

Allocation Required - Rs. 342,238.81

RUP

Scheme - Janaranjanawewa Total Allocation for 2009 - Rs. 15,500,000.00 Expenditure - Rs. 14,933,634.49

No Name of work Sanction Amount Agreed Amount Expenditure Progress 1 Improvements to LB Bund 0m to 9,000,000.00 6,582,620.00 4,235,592.16 60% Terminated 2930m. 2 Improvements to Mavil Aru RB Bund 0m to 14,000,000.00 9,675,282.56 7,058,002.10 100% 870m. 3 Improvements to Mavil Aru RB Bund 870m to 22,900,000.00 15,778,229.50 12,882,059.94 100% 1780m. 4 D1 Channel off RB Main Channel 2,500,000.00 1,999,786.90 2,017,292.96 100% 5 D1 Channel off LB Main Channel 3,760,000.00 2,622,493.00 2,712,509.41 100% 6 D2 Channel off LB main channel 700,000.00 561,832.29 377,448.71 100%

86 7 D3 Channel off LB main channel 565,000.00 448,923.32 301,546.19 100% 8 LB1 Channel off LB Main Channel (0m – 1,800,000.00 1,541,383.00 930,043.55 95% 1000m) 9 LB1 Channel off LB Main Channel (1000m – 2,100,000.00 1,811,376.72 1,454,752.90 95% 3000m) 10 LB1 Channel off LB Main Channel (3000m – 2,200,000.00 1,887,309.20 1,321,033.72 95% 4800m) 11 LB2 Channel off LB Main Channel 11,750,000.00 10,830,117.00 5,921,399.54 100% 12 FC61Channel off LB Main Channel 1,248,000.00 891,010.23 277,860.96 50% Terminated 13 Br. Chl No. 3 off RB Main Channel 1,238,000.00 1,006,984.20 1,606,080.40 100% 14 D2 Channel off Br. Chl. No.3 (0m – 1300m) 1,777,000.00 1,421,622.00 1,152,667.45 100%

15 D2 Channel off Br. Chl. No.3 (1300m – 1900m) 1,715,000.00 1,371,987.35 781,264.25 100%

16 D2 Channel off Br. Chl. No.3 (1900m – 2300m) 1,890,000.00 1,476,776.96 - 60%

17 D2 Channel off Br. Chl. No.3 (2300m – 3300m) 1,825,000.00 1,427,081.10 - 0%

18 Raja Ela Stage 1 & 2 13,500,000.00 13,500,000.00 13,544,653.53 100% 19 Improvements to Access road to Mavil Aru 5,000,000.00 4,740,000.00 3,175,344.65 100% 20 Rehabilitation of Mahaweli Flood Bund 10,500,000.00 7,525,520.00 5,295,685.94 95% 21 Improvements to Branch chl.No.1 off RBMC 12,550,000.00 9,474,760.00 8,303,452.92 100%

22 Improvements to Branch chl.No.2 off RBMC 7,200,000.00 5,570,052.00 3,674,162.36 100%

23 Improvements to Branch chl.No.4 off RBMC 11,500,000.00 9,398,965.00 6,674,668.80 100%

24 Improvements to LB5 Off LBMC 16,200,000.00 12,997,605.50 9,018,741.93 100% 25 Improvements to D6 Channel off LBMC 17,500,000.00 13,051,973.50 6,406,982.49 100% 26 Improvements to Muthur Channel 19,000,000.00 17,962,719.35 17,567,982.56 100% 27 Improvements to D13 Channel off LBMC 11,800,000.00 8,369,809.25 5,580,312.99 100% 28 Improvements to RB Main Chl 8km to 15.3km 13,500,000.00 10,483,147.50 3,122,730.39 60% Terminated

29 Impts. to Dr. Chl. between D9 & D11 800,000.00 664,711.50 571,911.50 100%

No Name of work Sanction Amount Agreed Amount Expenditure Progress

30 Improvements to D5 Channel off LBMC 1,315,000.00 1,296,344.58 696,932.96 100%

31 Improvements to RB Main Chl 0km to 3.12km 26,970,000.00 22,305,240.00 9,070,057.56 75%

32 Improvements to RB Main Chl 3.12km to 8.0km 16,322,000.00 15,485,917.00 5,752,351.97 75.00%

33 Improvements to LB Main Chl 0km to 7.6km 23,700,000.00 20,105,930.00 7,210,778.27 75%

34 Improvements to LB Main Chl 7.6km to 11.84km 16,301,000.00 11,949,862.00 - 50%

35 Improvements to LB Main Chl 11.84km to 15.3km 17,649,000.00 12,643,967.74 3,257,415.42 50%

36 Cannel Lining in D 1 off Br.No. 3 off RBMC (0m – 18,257,000.00 12,785,565.00 3,058,698.12 40% 770m) 37 Cannel Lining in Muthur Channel (2880m – 16,065,000.00 11,262,000.00 8,879,514.25 75% 4864m) 38 Construction of Pirambuweli Anicut (Balance 12,700,000.00 10,051,175.43 - 50% Work) 39 Improvements to Spill No. 02 1,137,006.36 931,972.43 670,059.06 100%

40 Improvements to D7 Channel off LBMC 1,620,000.00 1,317,127.00 263,425.40 60%

87 41 Rehabilitation of Peruweli Dr.Chl. (0m to 1500m) 700,381.03 70%

42 Rehabilitation of Peruweli Dr.Chl. (1500m to 2,080,000.00 1,264,986.72 70% 4300m) 43 Improvements to D6/LBMC from 2100 to 5000 3,234,084.00 2,686,518.75 10%

44 Improvements to D6/LBMC from 5000 to 7035 4,740,000.00 3,934,540.00 10%

45 Improvements to RBMC from8000to 5,000,000.00 4,296,769.84 10% 15300(Balance) 46 Rehabilitation of LB 1 / D6/LBMC 7,567,000.00 7,567,000.00 1,606,080.40 Terminated

47 Repairs to Office and Quarters at Kallar 2,460,130.00 2,460,130.00 1,216,411.02 100%

48 Const. of Soil Laboratory 1,493,040.00 1,493,040.00 1,477,560.68 100%

49 Cons. Of Staff Quarters at Kallar. 1,550,620.00 1,550,620.00 1,411,018.05 100%

50 Investigation of LBMC upto Ranathunga Gate. 80,950.00 80,950.00 42,000.00 100%

51 Investigation of Muthur Channel. 0m to 8000m 50,000.00 50,000.00 48,000.00 100%

52 Survey Investigation of RBMC 0km – 8 km 158,000.00 158,000.00 83,900.00 100%

53 Survey Investigation of LBMC 0km – 15.83 km 160,000.00 160,000.00 108,000.00 100%

54 Survey Investigation of RBMC 8km – 14.9 km 50,000.00 50,000.00 41,000.00 100%

Sub total 388,404,127.39 310,744,287.86 170,717,358.40

Description of work Civil cost+ Contract signed Expenditure in Status contigencles (Rs) (value in Rs) curred to date excluding retention &VAT(Rs)

Estimate sent to Improvements to Tank Head Work 7,562,954.31 - PUM

Work is in Progress. Rehabilitation of Nelu Oya Link Canal 23,602,500.00 24,406,508.56 21,085,663.50 -93%

Installation of 3Nos Collapsible vertical gates for Work offered to 8,400,000.00 - Neluoya Anicut Govt. Factory.

Jungle clearing of Neluoya Access road to Morawewa Work is in progress 4,883,200.00 4,750,000.00 4,228,097.00 Scheme Trincomalee -100%

88 Rehabilitation of Main Canal bund road Metalling 10,703,450.41 10,703,450.41 10,785,747.30 Work completed and Tarring -3.394km

Terminated Rehabilitation of Main Canal & bund Road 5.05km 23,105,750.13 17,994,581.00 16,154,666.39 Work is in progress (0km to 5.05km) -45%

Rehabilitation of Main Canal-1.232km (5.21km to 2,776,768.34 2,467,091.35 2,261,568.15 Work completed 6.450km)

Rehabilitation of Main Canal- 1.973km (6.450km 2,952,232.72 2,595,561.00 2,546,427.30 Work completed to8.423 km)

Improvements to Main canal bund Road (from 5.218km 7,610,900.00 7,800,000.00 7,788,676.15 Work completed to 8.613km)

Concrete canal lining For main Canal from 5.268km to Work is in progress 20,591,754.02 15,625,902.17 11,024,696.30 5.921km -65%

Rehabilitation of Branch Canal No:1&Bund road Work is in progress 19,198,759.60 14,581,541.30 14,764,389.82 -1.500km(-0.175km to 1.325km) -96%

Rehabilitation of Branch Canal No:1&Bund road 18,128,994.59 15,283,604.75 15,121,914.10 Work completed -1.000km(1.325km to 2.325km)

Rehabilitation of Branch Canal No:1&Bund road 21,207,740.82 21,207,740.82 21,087,766.55 Work completed -2.846km(2.325km to 5.171km)

Rehabilitation of Branch Canal No:1 From 2.825km to 5,864,191.71 5,150,660.00 5,155,947.62 Work completed 3.375km-0.550km (2.875km to 3.425km)

Rehabilitation of Branch Canal No:1For Concrete Work is in progress 11,351,748.10 8,552,056.80 8,976,743.82 canal lining form 0km to 0.605km -100%

Description of work Civil cost+ Contract signed Expenditure in Status

e contigencles (value in Rs) curred to date g a

k (Rs) excluding a

P retention &VAT(Rs) Rehabilitation of D7&LB A1 off Main canals- P1 2.250km Work is in 8505996.21 6572502.9 1,117,477.16 Rehabilitation of field Channels off Progress-30% P2 D7(LBA1,LB1,LB2,LB3,RBA1,RB2,&RB3)- 2.350km Work is in Rehabilitation of Progress- P1 D8 10,510,168.36 48% Cannnel2.31km P2 8,020,111. Rehabilitation of field Channels off Tender Procedure 40 (LB1,LB2,RB1,RB2,RB4&FC1,FC2,FC2A,F - - - Adopted 3,562,230. C3,OFF RB4)-3.337km 45 Rehabilitation of field Channels P3 - - - Estimate Ready off( RB3,LB3& FC1B off RB3)

Rehabilitation of field Channels P4 - - - Estimate Ready FC1A,FC1,FC2,FC3,&FC3Aoff RB3)-3.33km

89 Rehabilitation of RB5 & RB6 off D8 Channel P5 and it's field Channels FC1A,FC1, off RB5 of - - - Estimate Ready D8-4.310km Rehabilitation of LB1,LBA1& LB1 off BC 1 Work is in P1 Canal &field Channels of FC1 Off RB1 of 5,881,220.71 5,878,624.76 3,924,273.33 progress -100% BC1-2.578km

Rehabilitation of LB2,LB3 & RB2 off BC1 Canal, FC1&FC2 off RB5 & LB1 off BC1 Work is in P2 3,663,217.30 2,795,042.02 1,329,838.84 field Channels of FC1 off LB3 of Bc1 progress -80% 2.655km Off RB1 of BC1-2.578km

Rehabilitation of LB4 & RB 2B off BC1 Work is in P3 Canal & Field Channels of LB4 4,182,792.51 3,207,192.08 975,166.58 progress -80% (FC1,FC2,FC3 & FC4)-2.376 km

Rehabilitation of LB5 & RB 3&RB4 off BC1 Work is in P4 canal & field channels of FC1 off LB5 of BC1- 4,451,924.38 3,344,321.88 430,736.12 Progress-20% 3.730km

Rehabilitation of RB6 & LB7 off BC1 Work is in P5 2,059,625.10 1,909,883.27 359,281.04 Channel & field channels of RB6-1.290km progress -60%

Rehabilitation of RB7 off BC1 Channel& Work is in P6 2,131,888.77 1,977,419.41 1,172,154.12 Field Channels (FC1,FC2,FC3&FC4)-2.890 progress -54%

Rehabilitation of D9 Channels 1.1562km Work is in P1 Rehabilitation of D9 field 3,691,350.46 3,449,860.25 1,904,442.06 progress -65% Channels(RA1,RB1,RB2,RB3offD9,FC1 off

Rehabilitation of Field Channels of Work is in P1 D10(LB1,LB2,LB3,LB4 off D10,FC1,FC2,off 3,856,013.14 3,084,600.31 602,392.28 Progress-29% LB3)-3.440km

Work is in P2 Rehabilitation of D10 Main Channel km 1,870,329.38 1,570,788.44 626,396.74 Progress-50%

Expenditure in

e curred to date g Civil cost+ Contract signed a

k Description of work excluding Status

a contigencles (Rs) (value in Rs)

P retention &VAT(Rs)

Rehabilitation of Field Channels of Leveling P1 BC2(LB5,LB6,LB7,LB8&LB9)2.930 - - - completed (FC1,FC2,FC3&FC4)-2.890km Rehabilitation of Field Channels of Leveling P2 BC2(LB10,LB11,FC2 off LB9 - - - completed FC1,FC2,FC3,off LB11)-3.110km

Rehabilitation of Field Channels of Work is in P3 8,926,474.08 6,876,612.00 4,943,683.00 BC2(LB1,LB2,LB3,&LB4)=2.730km Progress-90%

90 Rehabilitation of FCC/BC2 (FC1,FC2,FC4,FC5 off LB3)-Reh. of Agreement P4 6,831,678.66 5,863,275.87 600,000.00 FC2/LB3/BC2 Reh of FC6/FC7 /FC8 Signed LB3 .BC2 Total 321,207,727.10 250,526,407.37 207,747,843.21

UNDP

Scheme - Mahadivulwewa

Total Allocation for 2009 - Rs. 5,000,000.00

Physical Progress - 100%

Vavuniya Range

Vavuniya Range consists of two divisions viz Vavuniya and Murunkan and also covers Vavuniya and . 05 tanks and anicut scheme are under the Vavuniya Division which schemes are irrigated 6,743Acs of paddy land in Vavuniya District and 03 tanks are under the Murunkan Division which schemes are irrigated 31,892Acs of paddy land in Mannar District.

• Vavuniya Division

• Murunkan Division.

DIVISION SCHEMES Specified Extent

(Ha)

RDI's Office Murunkan Akathimurippu 2,564 Giants Tank 9,897 Viyadi Kulam 495

DIVISIONAL TOTAL 12,956 Vavuniya

91 Irataperiya Kulam 204 Kalaru Anicut 243 Maruthamadu Tank 178 Muhathan Kulam 326 Pavatkulam 1,674 Rajendran Kulam 120 DIVISIONAL TOTAL 2745

General Climatic

According to the records available; Vavuniya Region receives most of the rainfall by North East moon soon during October to December. But comparing to previous year, this year only around 50% of rain fall observed in many stations In year 2009 rainfall received during October to December at Pavatkulam station (Vavuniya District) is 542 mm and Giants Tank (Mannar District) station is 629 mm. But average rainfall of the Vavuniya and Mannar Districts are 1074 mm 804mm and respectively.

Scheme Details

Irrigable Extend / Catchment area / Name of Scheme Division FSD / (Ft) (Acs) Sq.mile

Pavatkulam Vavuniya 19’ – 4” 4134 115.00

Irratperiyakulam Vavuniya 15’ – 4” 502 12.24

Muhathankulam Vavuniya 11’ – 0” 774 34.00

Maruthamadu Vavuniya 12’ – 0” 438 14.60

Rajendrakulam Vavuniya 12’ – 6” 295 2.40

KalAru Anicut Vavuniya 3’ – 3” 600 170.00

38.0 & Aruvi aru Giants tank (including 162 feeder tanks) Murunkan 11.56’ 24438 diversion

Akathimuripputank (including 40 feeder Murunkan 10’ – 0” 6231 1.5 & Aruvi aru diversion tanks)

3.5 & Modaragama aru Viyadikulam (including 06 feeder tanks) Murunkan 8’ – 0” 1223 diversion

PROGRAMME

Cultivation Program

Yala Irrigable Maha 2008 / Name of Tank Division 2009 / Extend / (Acs) 2009 (Acs) (Acs)

Pavatkulam Vavuniya 4134 4134 Nil

Irratperiyakula Vavuniya 502 502 152 m

Muhathankula Vavuniya 774 774 Nil m

Maruthamadu Vavuniya 438 438 70

Rajendrakulam Vavuniya 295 295 Nil

92 Giants tank Murunkan 24438 13900 Nil

Akathimurippu Murunkan 6231 - Nil tank

Viyadikulam Murunkan 1223 - Nil

General works

The functions of this Irrigation Division can be broadly categorized as follows.

Operation & Maintenance of Irrigation scheme Providing Irrigation water to crops during Maha and Yala. Improvements and rehabilitation of Irrigation schemes in Vavuniya & Mannar Districts. Implementing the project works such as CAARP, RAP, PEACE & Wadakkin Vasantham.

Progress & Achievements - Cultivation Performance

Irrigable Extend / Maha 2008 / 2009 Yala 2009 / Name of Tank Division (Acs) (Acs) (Acs)

Pavatkulam Vavuniya 4134 3300 Nil

Irratperiyakulam Vavuniya 502 502 Nil

Muhathankulam Vavuniya 774 547 Nil

Maruthamadu Vavuniya 438 230 75

Rajendrakulam Vavuniya 295 295 Nil

Giants tank Murunkan 24438 15412 Nil

Akathimurippu Murunkan 6231 Nil Nil tank

Viyadikulam Murunkan 1223 Nil Nil

Departmental & Project Works

Departmental Work

9. Operation & Maintenance Total allocation Received in year 2009 - Rs. 11.83 mn

Expenditure upto end of 2009 - Rs. 9.26 mn

Achievement - Physical - 100%

- Financial - 78%

10. Improvements to Departmental Roads Total allocation Received in year 2009 - Rs. 1.37 mn

Expenditure upto end of 2009 - Rs. 1.33 mn

93 Achievement - Physical - 100%

- Financial - 96%

11. Electrical Installation to Departmental Building Total allocation Received in year 2009 - Rs. 0.15 mn

Expenditure up to end of 2009 - Rs. 0.14 mn

Achievement - Physical - 100%

- Financial - 98%

12. Improvement to Departmental Buildings Total allocation Received in year 2009 - Rs. 1.00 mn

Expenditure upto end of 2009 - Rs. 0.97 mn

Achievement - Physical - 100%

- Financial - 97%

13. Improvements to Major work Total allocation Received in year 2009 - Rs. 2.47 mn

Expenditure upto end of 2009 - Rs. 2.12 mn

Achievement - Physical - 100%

- Financial - 86%

14. Improvements to water Management

Total allocation Received in year 2009 - Rs. 0.58mn

Expenditure upto end of 2009 - Rs. 0.45mn

Achievement - Physical - 100%

- Financial - 79%

15. Improvement to Head works for Additional Safety

Total allocation Received in year 2009 - Rs. 1.00 mn

Expenditure upto end of 2009 - Rs. 0.82mn

Achievement - Physical - 100%

- Financial - 82%

16. Preventive Maintenance Total allocation Received in year 2009 - Rs. 1.83 mn

Expenditure upto end of 2009 - Rs. 1.05 mn

Achievement - Physical - 100%

94 - Financial - 57%

17. Food Damage Repairs Total allocation Received in year 2009 - Rs. 6.05 mn

Expenditure upto end of 2009 - Rs. 5.07 mn

Achievement - Physical - 100%

- Financial - 84%

10. Management supporting facilities

Total allocation Received in year 2009 - Rs. 0.30 mn

Expenditure upto end of 2009 - Rs. 0.25 mn

Achievement - Physical - 100%

- Financial - 85%

11. Construction of new Building

Total allocation Received in year 2009 - Rs. 2.8 mn

Expenditure upto end of 2009 - Rs. 1.83mn

Achievement - Physical - 100%

- Financial - 65%

Projects Works

CAARP (Conflicted Affected Area Rehabilitation Project – ADB Fund) Name of Work: Contraction of 2 Nos. Junior staff quarters at Murunkan Division (Continuation)

Achievement - 100% Total Allocation - Rs.6.70Mn

RAP Details of Work annexed for your reference

Name of Scheme Giants Tank: Works started in 2008 and will be completed in

2010. Total allocation received is Rs. 385.0mm.

Total cumulative expenditure up to

December 2009 is Rs. 170.0 million

Name of Scheme :- Pavatkulam: Works started in July 2009 and will be completed

95 in 2010. Total allocation received is Rs.50.0million

Total cumulative expenditure up to

December 2009 in Rs. 17.97 million

PEACE Details of Work annexed for your reference

Name of Scheme :- Akathimurippu works started in July2009 and will be

Completed in 2011. The original allocation Rs.225 million and later increase to 400mn

Wadakkin Vasantha Details of Work annexed for your reference

Name of Scheme :- The total allocation received for both district is Rs. 32.0million and all

work completes in year 2009

Gamanegume

Name of Scheme - Kal Aru Aincut - 1.5Mn

Name of Work :- Clearing of Main canal

CONSTRAINTS ENCOUNTERED

The main constraints in this Region are shortage of staff and lack of good motorable vehicles for plying on rough track roads in outskirts. The available staff is inadequate for the heavy workload including project works that is being carried out in this Region in Vavuniya and Mannar Districts. The works are being done with dedication and commitment even on weekends to fulfill the expected Programs and targets, with a shortage of staff and frequently break down vehicles.

Re- Awakening Project - Vavuniya Division

Agreement Physical S.N Description of Work Payment Amount Amount Progress

Survey and Investigation of Pavatkulam 1 506,000.00 - 75% Scheme

2 Improvements to Pavatkulam RB Main canal 9,437,445.25 8,004,242.87 85%

2 Improvements to Branch canal of Pavatkulam 4,595,251.00 2,201,647.10 85% RB Scheme

96 3 Improvements to D2, D3 Canal of RB Main 4,341,905.00 3,398,408.68 80% Canal of Pavatkulam Scheme

4 Improvements to Branch Canal off Purana 3,035,750.99 537,163.20 40% main Canal in Pavatkulam LB Scheme

5 Improvements to Purana Canal of Pavatkulam 4,397,160.50 3,374,385.71 50% LB Scheme

6 Improvements to D8, D9 Canal & D9 Branch 5,751,445.00 - 25% Canal in Pavatkulam RB Scheme

7 1,697,854.88 - 75% Rehabilitation of Pavatkulam LB Main Canal

8 Improvements to D10 Canal & D12 Canal of 2,535,319.21 - 0% Pavatkulam RB Scheme

Improvements to D2 Canal, D2 Branch Canal 9 5,372,538.00 1,074,507.60 5% D3 canal & D3 Branch canal off LB Main Canal in Pavatkulam Scheme

Improvements to D13 canal, D14 Canal of 10 - TP Pavatkulam Scheme

Re- Awakening Project - Murunkan Division

Description of Work Agreement Amount Payment Amount Physical Progress

1.Construction of 4.35 M Span Bridge Cum Regulator Across 12th 2,574,611.46 2,559,609.69 100 Mile Main Canal Under GT Scheme 2.Rehabilitation of Pandithankaddu Tank in Isaimalaithalvu Main 1,600,000.00 1,056,846.11 90 Channel of GT Scheme 3.Improvements to Perumparappu Canal Under 14th Mile Sluice in 4,480,591.63 2,787,892.15 100 GT Scheme 4.Improvements to 12th Mile Main Canal (From 0+500 M to 2+ 6,296,691.00 6,174,685.13 100 250M) Under 12th Mile Sluice in GT Scheme' 5.Rehabilitation of Giants Tank Head Works in Murunkan 59,000,000.00 39,939,130.93 72 Division 6.Improvements to 14th Mile Main Canal from 0+200 to 1+600 in 3,715,181.50 1,071,683.24 65 GT Scheme 7.Rehabilitation of Sornavayel Feeder Canal of 11th Mile Channel 573,220.00 467,641.75 100 of GT Scheme

97 8.Improvements to Manankavely Tank under 14th Mile Sluice in 2,716,688.07 1,534,194.16 100 GT Scheme 9.Rehabilitation of Kusavankuli Under 13th Mile Sluice in GT 1,538,468.45 1,107,654.03 100 Scheme 10.Rehabilitation of Vannamoddai Tank Under Isaimalaithalvu 1,518,800.60 1,055,422.08 90 Main Canal in GT Scheme 11.Rehabilitation of Kochchikulam Tank Under Isaimalaithalvu 1,263,667.20 786,048.82 80 Main Canal in GT Scheme 12.Rehabilitation of Sampanpuliyankulam Under Irattaikuloam 1,709,826.44 1,396,530.85 100 Main Canal of GT Scheme

13.Improvements to Pallankoddai Branch Canal Under 13th Mile 5,799,100.35 3,696,079.30 95 Main Canal in GT Scheme 14.Improvements to Vanchiyankulam Spill Tail Canal Under 11th 1,770,493.10 1,323,597.76 100 Mile Sluice in GT Scheme 15.Rehabilitation of Achchankulam Tank Under 12th Mile Main 4,781,645.27 3,097,647.17 80 Canal in GT Scheme 16.Improvements to Vellakaddu Tank Under 13th Mile Sluice 1,995,199.20 749,138.85 100 Under GT Scheme 17.Construction of Isaimalaithalvu 9 Bay regulator & 92 M Long 4,447,346.50 3,841,235.75 100 Retaining Walll in Inlet Channe Under GT Scheme 18.Re-construction of 14th Mile 07 Bay regulator & retaining wall 3,738,433.00 2,885,953.13 100 in GT Scheme (Murunkan Regulator) 19.Rehabilitation of Karukkamurippu Tank Under 12th Mile Main 2,664,563.62 1,346,625.68 95 Canal in GT Scheme 20.Improvements to Giants Tank Inlet Channel Bund 25+200 to 3,746,033.42 552,939.19 95 26+025 in GT Scheme Rehabilitation of 11th Mile Main Canal From 0+000 to 7+300 Under GT Scheme

43144546.00 42,223,126.49 100

21. Construction of Perumparappu Link Canal in between 14th Mile Main Canal & Perumparappu branch Canal under 14th Mile Sluice in GT Scheme 22.Improvements to 13th Mile Main Canal in GT Scheme 9,535,747.70 6,180,946.23 65 23.Improvements to Parikarikandal Branch Canal from 0+000 to 8,339,348.45 6,262,502.77 98 2+650 under Irattaikulam Sluice in GT Scheme 24.Rehabilitation of Kalmoddai Tank Under Adaikkalamoddai 1,508,264.79 1,080,125.37 100 Main Canal in GT Scheme 25.Rehabilitation of Uyilankulam Branch Canal Under 4,151,229.25 2,176,906.70 70 Adaikkalamoddai Main Canal in GT Scheme 26.Improvements to Malihainaddy Tank Bund Mallihainaddi Spill 3,375,323.99 70 Tail Canal & Vanchiyankulam Breaching Section Under 11th Mile Sluice in GT Scheme

S.NoDescription of Work Agreement Amount Payment Amount Physical Progress

27.Rehabilitation of Kallikaddaikadu Feeder Canal Under 2,613,832.40 65 Adaikkalamoddai Main Canal in GT Scheme

28.Re-Construction of 12 Bay Irattaikulam regulator across Inlet 4,700,000.00 4,528,392.48 100 Channel Under GT Scheme 29.Rehabilitation of Mandukumundan Tank Under 2,968,084.33 694,668.33 70 Adaikkalamoddai Main Canal in GT Scheme

30.Improvements to Isaimalaithalvu Main Canal & Pichchaikulam 5,757,080.52 1,268,037.07 40 Feeder Canal Under Isaimalaithalvu Sluice in GT Scheme

31.Rehabilitation of Kunchukulam Tank Under Adaikkalamoddai 2,034,526.30 672,020.56 75 Main Canal in GT Scheme 32.Rehabilitation of Pappankulam Tank under Adaikalamoddai 3,204,115.86 1,701,773.83 70 Main Canal in GT Scheme 33.Improvements to Pasikulam tank bund & Pichchaikulam feeder 7.931,330.20 634,274.25 20 canal under 12th Mile Main Sluice in GT Scheme

98 34.Improvements to Vankalai -Thuvarankeni Bund Cum Road Under Adaikkalamoddai Sluice in GT Scheme 8,427,918.00 1,009,324.98 25 Improvements to Vankalai Branch Canal from 9+000 to 4+025 under Adaikkalamoddai Sluice in GT Scheme 35.Improvements to 12th Mille Main Canal (From 2+250 m to 6+425m) Under 12th Mile Sluice in GT Scheme 16,568,368.02 7,232,628.90 35 Rehabilitation of Alvakkai Bruanch Canal under 13th Mile Sluice in GT Scheme 36.Rehabilitation of Inlet Canal from Head Sluice to 13th Mile Sluice in GT Scheme 26,270,700.00 16,669,453.00 80 Improvements to Inlet Canal LB Bund from 0+000 to 23+450 M in GT Scheme 37.Improvements to Irattaikulam Main Canal from 0+000 to 1+ 954 under GT Scheme 11,115,863.11 4,990,788.65 60 Rehabilitation of Parikarikandal Tank under Irattaikulam Main Canal in GT Scheme 38.Improvements to Nochchikulam Tank under 13th Mile Sluice TP in GT Scheme 39.Improvement to Chalampan Tank under 13th Mile Sluice in GT TP Scheme 40Improvements to Anddarcheddivelli Tank under 13th Mile Sluice GT Scheme TP Improvementsto Kanakanvelli tank under 13th mile Sluice GT Scheme 41.Improvements to Kumulamoddai tank from 0+000 to 1+860m under 12th mile in GT Scheme Improvements to Poovarasankandal tank from 0+000 to 1+990 m TP unde 12th mile sluice in GT Scheme Improvements to Vannakulam road from 0+000 to 1+775 under 12th mile Sluice in GT Scheme

TP 42.Rehabilitation of Illuppaikulam tank under 11th mile main canal 43.Improvements to Periyalankulam tank under Adaikkalamoddai TP main canal in GT Scheme 45.Improvements to Peruvelli spill tail canal & Road under 12th TP mile sluice 46.Improvements to Thuppasiyalankulam tank under TP Adaikkalamoddai main canal in GT Scheme

Details of Work - Vadakkil Vasantham Vavuniya Division

01.Rehabilitation of DI canal off LB main canal at Pavatkulam Scheme

Total allocation Received in year 2009 - Rs. 7.00mn

Expenditure up to end of 2009 - Rs. 4.72mn

Achievement - Physical - 100%

- Financial - 67%

02. Urgent Clearing of canal systems at Pavatkulam Scheme

To issue water for Maha cultivation in resettle area

Total allocation Received in year 2009 - Rs. 2.10mn

99 Expenditure up to end of 2009 - Rs.1.86mn

Achievement - Physical - 100%

- Financial - 89%

03. Strengthening of Scoured section on U/S of bund

and providing Rip Rap Protection in Muhathankulam

Tank Bund from 0+400 to 0+850 and 1+025 to 1+200

Total allocation Received in year 2009 - Rs. 6.70mn

Expenditure up to end of 2009 - Rs. 5.94mn

Achievement - Physical - 100%

- Financial - 89%

04. Rehabilitation of LB main canal at Irratperiyakulam

Total allocation Received in year 2009 - Rs. 3.27mn

Expenditure up to end of 2009 - Rs. 2.18mn

Achievement - Physical - 100%

- Financial - 67%

05.Rehabilitation of RB main canal at Irratperiyakulam

Total allocation Received in year 2009 - Rs. 2.93mn

Expenditure up to end of 2009 - Rs.1.69mn

Achievement - Physical - 100%

- Financial - 58%

Details of Work - Vadakkil Vasantham Murunkan Division

• Enhanced maintenance of Adaikkalamoddaimain canal system in Giants Tank Scheme Total allocation Received in year 2009 - Rs. 5.18mn

Expenditure upto end of 2009 - Rs.3.08mn

Achievement - Physical - 100%

- Financial - 59%

02. Desiliting of 11th mile 12th mile main canals system

in Giants tank scheme

100 Total allocation Received in year 2009 - Rs. 0.672mn

Expenditure upto end of 2009 - Rs.0.67mn

Achievement - Physical - 100%

- Financial - 99%

03. Enhanced maintenance of Akathimurippu Scheme

Total allocation Received in year 2009 - Rs. 4.248mn

Expenditure upto end of 2009 - Rs.4.25mn

Achievement - Physical - 100%

- Financial - 100%

Retaining wall Construction at RB main canal of Pavatkulam Earth work on Purana canal off LB main canal

Scheme under Re- awakening Project of Pavatkulam Scheme

101 Lining work at D8 canal off RB main canal of Rehabilitation of Giants Tank Bund

Pavatkulam Scheme under Re- awakening Project under Reawakening Project

Construction of Perumparappu Link channel (01 km) Construction of Irraddaikulam Regulator

Akkathimurippu tank bund under PEACE Project Resettled farmers engaging for field canal work at rice bowel

Irrigation Training Institute (ITI) - Galgamuwa - 2009

Diploma Course in Irrigation Engineering (2007/2009)

Academic works of the batch of irrigation learners (2007/2009) consisting 32 have being continued from January to August and completed by August 2009.

In-service Training Courses

10 No of training courses were held during the year 2009, out of 7 Nos. training were conducted for Irrigation Department staff, covering subject areas of Irrigation works, Computer skills development, Drawing office management, Quality Control Works & Water Management for different categories, such as Engineering Assistants, Drilling Assistants, Draughtsmen, Management assistants, Soil Testers and Hydrological Assistants. Other 3 Nos training courses were conducted for Engineers and technical officers of outside organizations, covering the subject areas of irrigation works and water management.

One seminar for ID Accountants & 5 Nos of JICA & ICIM workshops were also held during the year.

102 Examinations

1 No of Junior Technical Examination & 2 No. of Senior Technical Examinations (practical- 2009) for Engineering Assistants were conducted in July, November and December 2009 respectively.

Preparing estimates for rehabilitation work under PEACE Project.

Conducting surveying, designing of structures and canal systems and preparing estimates have being conducted for rehabilitation work under Rajangana and Galgamuwa IE divisions under PEACE Project. 24 Nos new IEs (contract basis) and 23 Nos of new EAs worked under ITI for above work.

Expansion Facilities

Under this vote Rs.1,700,000.00 was allocated for the construction of new bathroom for SQ3 and repairs of quarters and hostels and improving facilities of ITI. All the works were completed during the year and the total expenditure was Rs.1,700,000.00

Supplying of Equipments and Vehicle.

17 Nos of desk top computers, 19 Nos of UPSs, 2Nos of Photocopy machines, one laser printer and computer network system, 13 Nos of leveling instruments with tripods and 24 Nos of leveling staves were received under PEACE project. One Dish washer and Refrigerator were received from Head office. New two wheel drive double cab was received under PEACE project.

Irrigation Training Institute – Galgamuwa

Residential In- service Training Conducted during year 2009

No. of Duration No. Description of Programme Participants ( Days)

1 AUTO CAD Training for Draughtsman 25 5

2 AUTO CAD Training for Draughtsman 23 5

3 Workshop for expediting main & sub system 29 1 rehabilitations under PEACE Project

4 Surveying, leveling and workshop practice for Drilling 13 5 Assistants

5 Project Review of sub system main systems under PEACE 27 1 Project

6 Junior Technical Examination 2009 08 6

7 Training course on Irrigation works to Technical Officers 29 12

8 Refresher Training Course of Engineering Assistants of 09 1 Irrigation Department ( from 27th to 31st July 2009)

9 Training course for the Management Assistants of 31 5 Irrigation Department (from 24th to 28th August 2009)

10 Training course on Water Management for Engineers of 18 8 Mahaweli Authority

11 Senior Technical Examination 2009 17 6

103 12 Seminar for Accountants 21 2

13 Introduction to Water Management Manual under PEACE 20 2 Project

14 Training Course on Water Management for Technical 25 3 Officers of Mahaweli Authority

15 Training course on Water Management for Engineers of 18 2 Mahaweli Authority

16 Senior Technical Examination 2009 11 7

Annexures

Annexures 1 - Irrigation Department Organigram

Annexures 2 - Irrigation Department Key Position - 2009

Annexures 3 - Foreign & Local Training - 2009

Annexures 4 - Examination - 2009

Annexures 5 - Irrigation Department Staff Position - 2009

104 105 IRRIGATION DEPARTMENT- ORGANIGRAM 2009 ANNEX 01

Director General of Irrigation

)

) ) )

E

D )

R C ) ) M

, ) C ) T D

I &

E R T N M

W & ( P & )

A A A H ( C D

I F

( ( D & ( P N S

( I R I & C

D R

S (

( I R F R ( D

.

I ( I

R

D

I D R R R

D D R I R I I D I N

D D D D S

DD (WR DD (M&WS) DIR (ITI) DD (SR) DD (AM) DD (PI) CDOA LIBRARIAN DD (FIN) DD (HR) DD (DR) & PP) DD DD(PT) DD (HYG) DD (WM) DD (DS) DD (SD) (EST & DD (ENV) ACC) DD(RW) DD (HYD) DD (IM) DD (PD)

DD (WG) HEAD (LUD) DD (GIS) RDI

DD(MC) DD (TR) AMPARA

DD(EST) DD (COM) ANURADAPURA

PDD (PROJECTS) DD (EM) BANDARAWELA

CREE (PROJECTS) BATT ICALOA

COLOMBO

GALLE

HAMBANTOT A

KANDY

KURUNAGALA

MONARAGALA

POLONNARUWA

PUTTALAM

TRINCOMALEE

VAVUNIYA

DGI Director General of Irrigation PT Procurement WR & PP Water Resources & Project Planning SNR. DD Senior Deputy Director RW Regional Works SD System Design DIR Director WG Works General PS Project Design DD Deputy Director MC Major Constructions GIS Geo-informatics RDI Regional Irrigation Director EST Engineering Scientif ic & TechnologicalDR Serv ices Drainage and Flood Protection CIA Chief Internal Auditor EM Engineering Materials ENV Environment CDOA Chief Draw ing Office Assistant HYG Hydrology AM Assets Management RD &C Regional Development and Construction DS Dam Safety SS & TR Specialized Services & TrainingTraining HYD Hydraulics I & WM Irrigation & Water Management LUD Land Use Division AM Assets Management TR Training PI Plan Implementation COMComputer P & D Planning & Designs ITI Irrigation Training Institute HR Human Resources SR System Rehabilitation E,D & F Environment, Drainage & Flood Protection CT Contracts WM Water Management M & WS Machinery & Work Shops IM Irrigation Management

106 Annexure - 2

IRRIGATION DEPARTMENT KEY POSITION FOR 2009

Designation Name

Director General of Irrigation Eng. H.P.S.Somasiri

Director (RD & C) Eng. Dr. G.G.A.Godaliyadda

Director (SS & Tr) Eng P.C.Senaratne

Director( I & WM) Eng. H.M.Jayatilaka

Director (AM) Eng N.Indrasenan

Director (PI) Eng. Mrs. W.L.D.P.de Silva

Director ( P & D) Eng. G.V.Ratnasara

Director ( HR) Eng. Ms. Y.G.M.C.Godaliyadda

Director (Finance) Mr. W.P.Fernando

Snr Deputy Director (ED & FP) Eng B.K.. Jayasundera

Deputy Director (AM) Eng. Mrs. B.U.Kamaladasa

Deputy Director ( Com. Service) Eng. M.Thuraisingham

Deputy Director ( Eng. Materials) Eng. Eng. Jayabalamoorthi

Deputy Director (Eng. Geo ) Eng. S.P.P..Gamage

Deputy Director (Hydrology) Eng. Miss. P.P.G. Dias

Deputy Director (Designs - 1) Eng. Jegatheswaran

Deputy Director ( RW) Eng. Deheragoda

Deputy Director (Designs - 2) Eng. Miss. R.A.D.Jayanthi

Deputy Director (Drainage) Eng. G.P.Gunawardena

Deputy Director (Planning) Eng. Miss. C.H.Devendra

Deputy Director (Dam Safety) Eng. C.Vithana

Deputy Director (Training) Eng. Ms. D.R.Weerasingha

Deputy Director (Hydraulics) Eng. Mrs. H.V.P.D. Wijewickrama

Project Director ( Com. Service - 2) Eng. H.S.S.Perera

Project Director (Major Construction) Eng. K.D.N.Siriwardena

Project Director (Eng. Met - 2) Eng. Ms. I.D.S.Samarasooriya

107 Project Director (Est) Eng. W,S,T,Perera

Deputy Director (Works General) Eng.

Deputy Director (M & WS) Eng. W.G.S.D.Weerasekara

Deputy Director (Finance) Mrs. G.C.W.K.Wijesekara

Head (Land Use Division) Dr. T.S.B.Weerasekara

Local Training 2009 Annexure - 3

Name Desig. Course Name Inst.

Group of Engineers Engs Effective Communication Institute of IESL Engineers

Eng.L.L.Silva DD Seminar on Nanotechnology Application ICTAD

Group of D’man D’man Quantity Surveying (Preparation of BOQ & CHPB Estimate – 15)

Ms.W.A.P.M.Weerasinghe D’man Design Application Detailing & Draughting CHPB

Ms.O.D.Wasantha

Eng.H.M.Junaid DD Adjudication in Construction Contract ICTAD

Eng.G.Sarvananavan CIE

Eng.G.K.Pathmakeerthi IE

Mr.H.V.Kodithuwakku IE

Mr.M.A.R.Jayalal DA Computer Network Administration NIBM

Eng.T.A.Ratnasiri IE Maintenance of Electrical Installation CETRAC

MAA MAA Govt. Payroll Management INGAF

MAA MAA CIGAS INGAF

MAA MAA Annual Verification & Disposal Procedure INGAF

Mr.H.V.Kodithuwakku IE Contract & Procurement Procedure ICTAD

MAA MAA Maintenance of Personal Files INGAF

MAA MAA MS Excel INGAF

MAA MAA Introduction to Government Procurement INGAF Procedure

MAA MAA Public Finance & Accounting Skills Development INGAF

Mr.B.K.Nishantha Acct. Master Degree in Business Administration University of Ruhuna

Mr.J.Rajawickrama Research Diploma in Communication University of Sri Assistant Jayawardhanpura

Eng.B.A.S.S.Perera Co-P.D. MBA Programme – Intake III University of

108 Wayaba

Ms.P.C.W.K.Wijesekara DD (Fi.) Economic Degree Programme University of Kelaniya Ms.M.H.Sriyamani Acct.

Eng.G.Mugunthan IE Master of Information Technology University of Colombo

Mr.E.M.U.S.Ekanayake Acct. M.Com. Degree University of Kelaniya

Mr.G.M.L.Chandima Acct. Masters of Business Studies Degree University of Colombo

Eng.J.D.Amarasekara IE 18th Short Course - GIS & Applications University of Peradeniya

Eng.L.R.H.Perera IE 20th Short Course - GIS & Applications University of Peradeniya Eng.W.K.R.D.Wickramasinghe IE

Eng.M.A.S.S.Gunasena IE 3 D Modelling with the use of Auto CAD University of 2007/2008 Moratuwa Eng.A.L.T.C.Samarasinghe IE

Eng.N.C.Samarakkody IE

Group of IE, EA, D’man, DA IE, EA, Computer Aided Draughting using Auto CAD University of D’man, DA 2007/2008 Moratuwa

Mr.V.A.P.K.Udawela DA Geology – 2009/2010 University of Moratuwa Mr.H.M.W.J.Senanayaka DA

Mr.M.A.V.Wijayasiri DA

Mr.N.T.A.D.Dias AO Diploma in Office Management -S/E(2009/2010) SLIDA

Mr.G.Mugunthan IE DEP – Level 01, 02 SLIDA

Mr.D.S.Samarawickrama Acct. Master of Public Management SLIDA

Groups of Engineers Engs Quantity Surveying (Preparation of BOQ & CHPB Estimate) – 15

Mr.H.T.J.Peris D’man Quantity Surveying (Pre Contract Phase) – 23 CHPB

Mr.V.G.U.R.Weerawansa D’man

Ms.M.T.P.Priyangani D. Person

Group of Eng, DA, EA, D’person Engs, EA, Price Fluctuation Formula ICTAD DA, D’person

Mr.H.V.Kodithuwakku IE Contract & Procurement Management CHPB

109 Annexure - 4

Examinations Conducted during the year 2009

No.Name of Examination Date

01. First Efficiency Bar Examination of Engineers in SLES Class 28.03.2009 II Grade II - 2009

02. The examination at the end of two years training of HAA 06.06.2009 & HFAA

03. The examination at the end of two years training of 23.06.2009 Drilling Assistants

04. The examination at the end of two years training of Soil 21.08.2009 Testers

05. Efficiency Bar Examination of Engineering Assistants in 26.09.2009 Class II Grade I - 2009

06. Promotion Examination of D’man in SLTS from Class II B 24.10.2009 to Class II A - 2009

110 111 112 ANNEX – 5 (2-1) STAFF POSITION - 2009 Retur Category of Staff Cadre The No Resigened Vacated Dismissed Retired Dead n New Transfer Promoted Avalable beginning pay on Appoint In out to other at the of the year Designation end of the 2009 Year 2009 Director General of Irrigation 1 1 1 Director (SLES) 7 7 Director (SLAS -01) Directir (Acct - Class 1) 1 1 Civil Engineer (Grade 1) 42 3 1 3 37 Civil Engineer (Grade 11) 49 1 1 3 7 2 49 Civil Engineer (Grade 111) 78 1 2 7 69 Civil Engineer (NPQ) 281 30 1 1 28 Civil Engineer (Casual) 12 4 8 Civil Engineer (Contract) 52 25 27 Mech. Engineer (Grade 1) 1 1 Mech. Engineer (Grade 11) 4 4 Mech. Engineer (Grade 111) 7 2 2 Mech. Engineer (Contract) 3 3 Accountant (Grade 1) 5 1 4 Accountant (Grade 11) 24 3 1 2 Accountant (Grade 111) 13 1 14 Senior Specialist Officer (Soil) 1 1 1 Specialist Officer (Land Use) 2 Assis Soil Chemist 5 4 4 Research Officers 2 2 2 Suprintendent Of Instrument 1 1 1 Assist. Suprintendent Of Instrument 1 Suprintendent Of Drilling 1 Gec Technical Officers 1 1 1 Development Assistant 52 24 24 Institutional Development Officers 11 8 8 Budget Assistant 2 1 1 Engineering Assistant 649 321 10 2 21 288 Drawing Office Assistant 21 21 5 1 15 Draugstsman 301 247 4 1 2 243 Research Assistant (SLTS) 28 20 2 18 Research Assistant (GEN) 7 3 3 Hydrolical Field Assistant 38 16 16 Hydrolical Assistant 23 19 1 18 Land Use Officers 3 3 3 Soil Testers (SLTS) 34 20 1 19 Soil Surveyors 30 23 2 21 Drilling Assistant 31 27 2 25 Experimental Officer 1 Mapping officer 1 Translator 3 1 1 Soil Cartographer 6 6 6 Mechanical Formen 7 7 7 Radio (Photographer) 1 1 1 Plan Keepers 12 3 1 2 Plan Printer 2 2 2 Management Assistant (Supra) 19 14 14 Management Assistant Service 840 636 9 20 2 11 38 28 626 Stores Liasen Officer 1 Planning Assistant ANNEX – 5 (2-2)

113 STAFF POSITION - 2009 Retur Category of Staff Cadre The No Resigened Vacated Dismissed Retired Dead n New Transfer Promoted Avalable beginning pay on Appoint In out to other at the of the year Designation end of the 2009 Year 2009 Librarion 2 1 1 Assistant Librarian 1 1 1 Welders 19 5 1 4 Operators 90 55 12 1 42 Painter 5 3 3 Telephone Operators Record Keepers Binder Duplicating Machine Operator KKs (Head) KKs 295 159 9 27 123 Cycle Orderly Lift Operator Offoce Watcher Office labours Sanitory Labours Stores Labours 32 37 6 2 29 Instrument talist 1 1 1 Drivers 225 167 15 12 164 Transport Overseers 2 1 1 Circuit Keepers 23 12 12 Work Supervisors ( SLTS) 478 159 25 134 Work Supervisors (NON SLTS) Hydrolical survey Labours 110 85 14 1 70 Masons 3 4 1 3 Carpenters 12 10 5 5 Blacksmith 1 Machanics 50 38 1 2 35 Cleaners 5 3 3 Storemen 10 6 6 Water Issuers Machinics 2 1 1 Electrician 7 7 7 Field Watcher 96 49 13 3 33 Lathmen 1 Tinker 4 2 2 Pump Operator 26 19 2 1 16 Fitter 1 1 1 Maintanance Labours 870 678 36 6 636 Greeser 30 19 5 14 Minor Supervisor 4 4 4 watch Repairer 1 1 Laboratory Labour 40 38 1 37 Total 4897 3299 2 38 3 1 203 33 0 22 56 3017

114