Texas City Channel Deepening — a Design-Build First

Total Page:16

File Type:pdf, Size:1020Kb

Texas City Channel Deepening — a Design-Build First Proceedings, WEDA XXXII Technical Conference & TAMU 43 Dredging Seminar TEXAS CITY CHANNEL DEEPENING – A DESIGN-BUILD FIRST Larry A. Wise, P.E.1 and Philip J. Burgmeier2 ABSTRACT Chosen for its efficient delivery process, the Texas City Channel Deepening Project marks the first time that the USACE utilized the design-build method for a major navigational improvement dredging project. Moffatt & Nichol along with HVJ Associates, as engineers and designers of record, and Weeks Marine, Inc., as constructors, formed the design-build team for dredging and placement, modification of existing placement area levees, and onsite construction support. The 11 km (6.75 mile) long Texas City Channel connects the Port of Texas City to the Houston-Galveston Channel and the Gulf of Mexico. The channel serves the 10th largest port (in terms of tonnage) in the country. Weeks Marine, Inc., under contract to the U.S. Army Corps of Engineers (USACE) Galveston District, deepened the channel from 12.2 m (40 feet, ft) to 13.7 m (45 ft). The project consisted of maintenance dredging followed by dredging for the deepening, which produced approximately four million cubic yards of dredge material. Approximately 690,000 m3 (900,000 cubic yards, cy) of maintenance material was used to renourish an existing recreational beach on the Texas City Dike. The new work material was used to construct perimeter levees for 273 hectares (685 acres, ac) of new intertidal wetlands near the Texas City Channel and adjacent to Pelican Island, which will be filled over time with approximately 7.6 million m3 (10 million cy) maintenance dredged material. These new levees were armored with rock to protect them against waves. Design-build is a new methodology for the U.S. Army Corps of Engineers for navigation projects. Some of the highlights and lessons learned from the contractor’s and engineer’s perspectives will be discussed. Keywords: Dredging, beneficial uses, levees, design build. INTRODUCTION The design-build procurement and construction methodology currently accounts for more than 1/3rd of private sector, non-residential construction and is growing in importance for public sector work in the United States. Under the traditional design-bid-build methodology the design work is completed by the owner, or the owner’s engineer, and then a complete set of construction documents (plans and specifications) are bid on by the construction contractor. In the design-build methodology the owner provides a conceptual level (typically 30% complete) design along with functional requirements for the project. The construction contractors then team with an engineer to serve as the designer of record and complete the construction documents. The owner maintains involvement, either directly or using an outside owner’s engineer, to ensure that the construction documents and constructed project meet the needs and intent of the project. The design-build methodology offers several potential advantages to the owner and constructor. These include: Potential to expedite project schedule by completing design tasks, particularly for later portions of the job, during construction. Ability of the contractor to modify design elements, within functional requirements of the owner, to better suit the contractor’s available equipment and preferred methodologies. Potential for alternative design concepts to be used which may result in cost or schedule savings. Increased participation of the engineer throughout the construction process. 1 Sr. Coastal Engineer, Moffatt & Nichol, 11011 Richmond Ave. Suite 200, Houston, Texas 77042, USA, T: 713- 977-7372, Fax: 713-977-7379, Email:[email protected]. 2 Project Manager, Weeks Marine, Inc., 304 Gaille Drive, Covington, Louisiana 70433, USA, 985-875-2500, 985- 875-2570, [email protected]. 128 Proceedings, WEDA XXXII Technical Conference & TAMU 43 Dredging Seminar Decreased risk for the owner due to designer and constructor being joined under one contract, taking the owner out of the middle of disputes. The design-build methodology has recently begun to become used in the U.S. dredging market. Several private marine terminals have used the methodology, including several liquefied natural gas terminals on the Gulf Coast which Weeks Marine, Inc. and Moffatt & Nichol have been involved with either as a team or individually. The Texas City Channel deepening project was funded, largely, under the American Recovery and Reinvestment Act of 2009 (ARRA). Due in part to the desire to expedite construction of the project the U.S. Army Corps of Engineers chose to use the design-build methodology. This is the first time a major navigational improvement dredging project has been procured by the Corps under this methodology. This paper will summarize the project and examine some of the differences between design-build and traditional design-bid-build methodology as pertained to the project as well as discuss some of the lessons learned from the perspective of the design-build team of Weeks Marine and Moffatt & Nichol. PROJECT BACKGROUND AND OVERVIEW Originally created in the 1890s and reaching its present configuration in 1967, the 11 km (6.75 miles) long Texas City Channel (Figure 1) is a federally maintained, deep-draft navigation channel serving the deepwater Port of Texas City. The Port of Texas City is 11 km (7 miles) from Galveston and 18 km (11 miles) from the Gulf of Mexico. The Port of Texas City is currently the 10th largest port in the nation in terms of tonnage, with 48 million tonnes (52.6 million short tons) throughput annually. Key commodities passing through it include crude oil, gasoline, diesel, and jet fuel. The principal purpose of the Texas City Channel project (Figure 2) was to deepen the 121 m (400 ft) wide channel from 12.2 m (40 ft) to 13.7 m (45 ft). This required dredging of approximately 1.9 million m3 (2.5 million cy) of new work material. This newly dredged material was used to construct approximately8.8 km (29,000 linear ft, lf) of new levees to create new dredged material placement areas in open water. Placement area SPPA 2, 59.5 hectares (147 ac), was adjacent to existing placement areas 5 and 6. Placement areas SPPA 3 through 5, totaling 165 hectares (408 ac), are a new island just east of existing placement area 5 and 6. The fifth placement area was constructed on the west side of Pelican Island and totaled 40.9 hectares (101 ac). Placement areas SPPA 2 and Pelican Island were constructed in relatively shallow water ranging from zero to approximately 2 m (6 ft) depth. SPPA 3 through 5 was constructed in slightly deeper water averaging approximately 2.4 m (8 ft) depth. Over time, these placement areas will be filled with dredged material from channel maintenance to create approximately 263 hectares (650 ac) which will eventually be converted to emergent marsh. The project also included levee raising for an existing upland placement areas 5 and 6 in order to accommodate approximately 0.4 million m3 (0.5 million cy) of maintenance dredged material. The contract also included the repair of shore protection, both rock riprap and concrete block mattresses, damaged by Hurricane Ike in 2008. Another approximately 0.8 million m3 (1 million cy) of maintenance dredged material was placed on to the beach on the north side of the Texas City Dike to re-nourish the beaches and help repair damages from Hurricane Ike. 129 Proceedings, WEDA XXXII Technical Conference & TAMU 43 Dredging Seminar Figure 1. Overview of project area including existing placement areas 5 & 6 and new placement areas SPPA 2, and SPPA 3-5 (SPPA 1 & 1A were not included in the contract and Pelican Island placement area is modified from the original RFP configuration) Figure 2. Typical cross-section for channel deepening (previously removed maintenance material shown as cross-hatched). 130 Proceedings, WEDA XXXII Technical Conference & TAMU 43 Dredging Seminar SELECTION The Texas City deepening project was initially studied and authorized (for a 15.2 m (50 ft) depth) by the Corps in 1982 but was never constructed. In 2001 the City of Texas City, the local sponsor, reactivated the project and the Corps completed a limited re-evaluation in 2003. The initial design work was completed by the Galveston District and documented in the Final-Draft Engineering Appendix dated 2007. The conceptual design, 30% complete, was by the Galveston District and released for bidding purposes in June of 2009. The Corps used a two phase “best value” selection process through a Request for Proposals (RFP). The RFP process originally included 30 days for the first phase and 30 days for the second phase. In Phase 1 of the RFP, design-build teams submitted certain specified performance capability and qualifications information, demonstrating their capability and capacity to successfully execute the design-build construction contract. The Corps used the Phase 1 submittals to qualify firms who were requested to submit a follow-on Phase 2 proposal. Selection was based on: business management plan (including organization, quality control, health and safety, and personnel); specialized experience; past performance; key project personnel capabilities and experience; and, financial capability. After notification of qualified firms from the Phase 1 process, approximately three weeks were initially allotted for preparation of the Phase 2 RFP, although through amendments this was extended to approximately seven weeks. In Phase 2, the selected teams submitted a preliminary technical-design, the remainder
Recommended publications
  • Let's Build the Ike Dike
    Let’s Build the Ike Dike William Merrell One hundred years ago in response to the 1900 Great Storm, we built a seawall to protect the East End of Galveston Island from storm surge. The seawall was severely tested by the 1915 Hurricane and again many times after. It stands today as a testimony to the community leaders who funded it and the engineers who designed and built it. The seawall continues to do its job of preventing catastrophic overflows. In the early 1900s, the seawall was a reasonable response to protecting the most precious manmade infrastructure in the region which was then concentrated on Galveston Island. However, over the last century, we have developed many large human settlements and industrial centers throughout the entire Galveston Bay region. In addition to representing considerable wealth, this human footprint now restricts or prevents movements of natural ecosystems in response to storm surge. It is no longer enough to strive to protect Galveston Island alone, we need to protect the entire Galveston Bay region from coastal flooding. Not surprisingly all community leaders are interested in protecting their citizens from the many real and hidden costs of flooding. Recent discussions have focused on building a dike around the east end of Galveston Island - essentially surrounding the area now behind the seawall. This approach argues that, while the seawall did its job in preventing catastrophic overflows like that at Bolivar, a surrounding dike is needed to prevent the backfilling of the Island by heightened bay waters. On the mainland, because the existing Texas City Dike was almost topped, discussions have begun about strengthening it and increasing its height.
    [Show full text]
  • Beach and Bay Access Guide
    Texas Beach & Bay Access Guide Second Edition Texas General Land Office Jerry Patterson, Commissioner The Texas Gulf Coast The Texas Gulf Coast consists of cordgrass marshes, which support a rich array of marine life and provide wintering grounds for birds, and scattered coastal tallgrass and mid-grass prairies. The annual rainfall for the Texas Coast ranges from 25 to 55 inches and supports morning glories, sea ox-eyes, and beach evening primroses. Click on a region of the Texas coast The Texas General Land Office makes no representations or warranties regarding the accuracy or completeness of the information depicted on these maps, or the data from which it was produced. These maps are NOT suitable for navigational purposes and do not purport to depict or establish boundaries between private and public land. Contents I. Introduction 1 II. How to Use This Guide 3 III. Beach and Bay Public Access Sites A. Southeast Texas 7 (Jefferson and Orange Counties) 1. Map 2. Area information 3. Activities/Facilities B. Houston-Galveston (Brazoria, Chambers, Galveston, Harris, and Matagorda Counties) 21 1. Map 2. Area Information 3. Activities/Facilities C. Golden Crescent (Calhoun, Jackson and Victoria Counties) 1. Map 79 2. Area Information 3. Activities/Facilities D. Coastal Bend (Aransas, Kenedy, Kleberg, Nueces, Refugio and San Patricio Counties) 1. Map 96 2. Area Information 3. Activities/Facilities E. Lower Rio Grande Valley (Cameron and Willacy Counties) 1. Map 2. Area Information 128 3. Activities/Facilities IV. National Wildlife Refuges V. Wildlife Management Areas VI. Chambers of Commerce and Visitor Centers 139 143 147 Introduction It’s no wonder that coastal communities are the most densely populated and fastest growing areas in the country.
    [Show full text]
  • Chapter 3 – State of the Bay, Third Edition
    CHAPTER 3 – STATE OF THE BAY, THIRD EDITION The Human Role: Past Written by Alecya Gallaway At sundown we reached Redfish Bar, composed almost entirely of shells which extend from bank to bank the distance of several miles and appear to be formed by the confluence of the tide and the waters of the San Jacinto and Trinity, which unite a short distance above … This point is undoubtedly the head of navigation for vessels of heavy burden and has occurred to some as a more suitable site for a city than Galveston itself. —Texas in 1837, edited by Andrew Forest Muir (1958) Introduction This chapter examines the history of resource use in Galveston Bay and its adjacent land area. The chapter begins with a look back to the Pleistocene Ice Age and the impact of the earliest humans, continues with the use of resources by Native Americans and changes engendered by the transition to European-American settlement, and then focuses on the alterations that occurred to the bay as the regional focus shifted from agriculture to municipal and industrial development. This chapter describes resource use and human impact from pre-history to 1950. More recent developments and impacts are covered in Chapter 4. Resource Use: Prehistory to 1800 Galveston Bay is a recent feature of the Earth by geological reckoning. Thousands of years before the bay formed, water was held in continental ice sheets causing the sea level to be considerably lower than it is today. The shoreline was located 50–100 miles farther south into the area now covered by the Gulf of Mexico.
    [Show full text]
  • Houston Ship Channel: Texas City and Galveston Bay Collision, Oil Spill and Business Continuity Disruption 22 March 2014
    CASE STUDY – HOUSTON SHIP CHANNEL OIL SPILL, 2014 Emergency Solutions International Inc. “Through Training We Remember” Houston Ship Channel: Texas City and Galveston Bay Collision, Oil Spill and Business Continuity Disruption 22 March 2014 Executive Summary At approximately 1215 hours local time, 22 March 2014, an oil tank barge carrying 1 million gallons of heavy oil, “Kirby 27706” towed by the motor vessel “Miss Susan”, was struck by the 585-foot bulk carrier “Summer Wind”. The collision breached one of the barge’s six fuel tanks causing the release of 170,000 gallons of a marine fuel oil known as RMG 380, a residual and highly persistent marine fuel oil, into the Houston Ship Channel and the waterway between Texas City and Galveston. The collision occurred when the barges being towed by Miss Susan made a left turn to enter the Intracoastal Waterway and were crossing the ship channel. Fog had caused ship traffic to pile up that Saturday at the Figure 1: A key waterway linking refineries and Texas City “Y” and ship pilots were petrochemical plants with the Gulf of Mexico desperate to get where they were going. At remained closed indefinitely to ship traffic, two the spill site, 700 yards offshore from the days after a collision triggered an oil spill in Texas City dike, six crew members of the Texas' Galveston Bay. Miss Susan were injured with non-life threatening injuries. Unified Command was set up in the Galveston Island Conservation Centre comprised of representatives of the Coast Guard, Texas Land Offices, State of Texas and Texas City.
    [Show full text]
  • The Value of Texas Ports 6
    Technical Report Documentation Plllte 1. Report No. 2. Government Accession No. 3. Recipient's Catalog No. TX -96/2994-1 4. Title and Subtitle 5. Report Date Apri11997 THE VALUE OF TEXAS PORTS 6. Performing Organization Code 7. Author(s) 8. Perfonning Organization Report No. Zane A. Goff, William F. McFarland, Billy Edge, John Basilotto, and Sara Graalum Research Report 2994-1 9. Perfonning Organization Name and Address 10. Work Unit No. (fRAIS) Texas Transportation Institute The Texas A&M University System 11. Contract or Grant No. College Station, Texas 77843-3135 Study No. 7-2994 12. Sponsoring Agency Name and Address 13. Type of Report and Period Covered Texas Department of Transportation Final Office of Research and Technology Transfer July 1996 - December 1996 P. O. Box 5080 14. Sponsoring Agency Code Austin, Texas 78763-5080 15. Supplementary Notes Research performed in cooperation with the Texas Department of Transportation and the Texas Port Association. Research Study Title: Identify and Assess the Collective Contribution (Value) of Texas Ports to Texas and the Nation 16. Abstract The foremost objective of this project is to demonstrate the importance of the ports in the State of Texas to the economy of the State and the Nation. Traditionally, the economic value of the state's ports has focused upon the economic impact to the region or a small sector of the state. Seldom has the full interior regions of the state been considered in the economic value of the ports. Moreover, the assessment will provide information including data, analyses and findings that may be used by TxDOT in developing a statewide port planning assistance program.
    [Show full text]
  • Classification of Shellfish Harvesting Areas of West Galveston
    6 LOOP 197 N 4 A Houston Ship Channel Marker #33 6 95°20'0"W 95°15'0"W 95°10'0"W 95°5'0"W 95N °0'0"W 94°55'0"W 94°50'0"W 94°45'0"W D N R I A T 4 5 M S M B F H PALMER HWY Y U 8 FM 1764 A S 0 R 1 RD B FM 1764 P N C O S S O R T 2 L D A T E TEXAS AVE T T 5 D S A E T R E - S H n 3 HWY 1765 d H 4 T of 3 0 T W 6 ex 0 as Y 2 C i ty Bolivar Lighthouse 1 D M i 4 ke HSC #25 F 6 A!. S T A T ' E ST FM 519 FM RD 519 MAIN H S W ne 7 an l Y 9 h 1 3 C P ip S O h O S D ST AT L R E n H WY o 6 6 t 4 s 6 e 29°20'0"N M lv F D a V L G Pelican Island B t L s Y L KW A e LF P WO W W SEA A E S A S I UE EN N AV A IC L E I 4 P 5 C Galveston au se wa 7 y WY 8 TE H North Deer Island STA 6 1 S T S Greens Lake South Deer Island T Southwest point of land D SM C LV B at Green's Lake Cut !.
    [Show full text]
  • Regional Environmental Monitoring and Assessment
    United States Region VI EPA/906/R-98/002 Environmental Protection Ecosystems Protection Branch June 1998 Agency 6WQ-E Galveston Bay 1993 Regional Environmental Monitoring and Assessment Program (This page is intentionally blank) EPA/906/R-98/002 Regional Environmental Monitoring And Assessment Program Galveston Bay 1993 June 1998 By Cynthia Gorham-Test U.S. Environmental Protection Agency, Region 6 Ecosystems Protection Branch 6WQ-E 1445 Ross Avenue Dallas, Texas 75202 (This page is intentionally blank) The R-EMAP Galveston Bay Study is a follow-up study of the EMAP-Estuaries: Louisiana Province Studies. Several comparisons are made between data collected and analyzed in this report and that of the following citation: Macauley J.M., J.K. Summers, V.D. Engle, P.T. Heitmuller, and A.M. Adams. 1995. Annual Statistical Summary: EMAP-Estuaries Louisianian Province - 1993. U.S. Environmental Protection Agency, Offices of Research and Development, Environmental Research Laboratory, Gulf Breeze, FL. EPA/620/R-96/003. R-EMAP and EMAP data are available at http://www.epa.gov/emap iv Acknowledgments EPA Region 6, Water Quality Division U.S. EPA, ORD, Gulf Breeze Lab Jeff Catanzarita Virginia Engle Phil Crocker Tom Heitmuller Norm Dyer John Macauley Evan Hornig Kevin Summers Angel Kosfizer James Stiebing U.S. EPA, ORD, EMAP Kenneth Teague Rick Linthurst Gulf Coast Research Group at USM IMS University of Mississippi Richard Heard Carol Cleveland Tom Lytle Gary Gaston Ervin Otvos Chet Rakocinski William Walker Texas A&M University, Geochemical and Environmental Research Group Bob Pressley Terry Wade Texas Research and Analysis Corporation Barbara Albrecht Jerri Brecken-Folse Texas Natural Resource Conservation Commission George Guillen Steve Twidwell v Table of Contents Acknowledgements......................................................................................................................................................
    [Show full text]
  • Impacts of Hurricane Ike on the Galveston Bay Fishing Community Prepared by Rhonda Cummins Texas Sea Grant Extension Program July 2009
    Impacts of Hurricane Ike on the Galveston Bay Fishing Community Prepared by Rhonda Cummins Texas Sea Grant Extension Program July 2009 Introduction The western Gulf of Mexico was hit with four named storms in 2008. Hurricane Gustav, Tropical Storm Edouard, and Hurricane Ike all impacted the fishing communities in Brazoria, Galveston, Harris, Liberty, and Chambers Counties. While spared damage in the first two events, the sheer size and magnitude of Hurricane Ike affected the entire Gulf of Mexico, but particularly the Galveston Bay Complex and the Sabine Lake area. Fishing communities, recreational marinas, and coastal wetlands were devastated by the large storm surge that scoured the low lying areas. Already in decline for a number of economic reasons not to be discussed in this paper, the Texas commercial seafood industry was further crippled as a result of damage to vessels, docks, processors, and dealers. Boat owners able to fish immediately after the storm experienced problems with debris, lack of fuel and ice, and selling their products due to the destruction of the shore-side infrastructure. Recreational and charter anglers were also affected by damage to bait shops, marinas, and boat ramps. While the resiliency of fishermen in the Gulf of Mexico is well- documented, the devastation to the fishing communities is unprecedented and aid is needed to rebuild and sustain the infrastructure of this viable community. Background study A comprehensive report on the NOAA Fisheries study titled “Identifying Communities Associated with the Fishing Industry in Texas” was published just months after Hurricane Rita made landfall on the Texas/Louisiana border.
    [Show full text]
  • Proposed Ike Dike Project in Galveston, Texas
    Coastal and Ocean Engineering Undergraduate Student Forum, COASTAL-2013 Faculty of Engineering and Applied Science, Memorial University, St. john’s, NL, Canada March, 2013 Paper Code. No. Adey, 2013 Proposed Ike Dike Project In Galveston, Texas Maria Adey Memorial University of Newfoundland St. John’s, NL, Canada [email protected] ABSTRACT On September 13th, 2008, Hurricane Ike made landfall along the southeast coast of Texas, devastating Galveston Island, the city of Galveston and the Bolivar peninsula. Ike was a category 2 hurricane when it made landfall in Galveston and consisted of 200 km/h hour winds at the hurricane eye and storm surges of up to six metres in height. The hurricane resulted in $25 billion in damages and left 1,500 people homeless. [1] A 17-foot high seawall currently protects the city of Galveston, while a 27-kilometre network of levees protects Texas City. The levees were designed to withstand a 100-year storm event, but were damaged as a result of Hurricane Ike. North of Texas City is the Port of Houston, which is the second largest port in the country and an important economic centre. The Texas City Dike was nearly topped during Hurricane Ike and future storm surges present a threat to the Port of Houston. [2] To address the threat of future hurricanes, Dr. William J. Merrell and the Texas A&M University in Galveston have proposed the construction of the “Ike Dike”. This project would consist of strengthening the existing Galveston seawall, protecting the rest of Galveston and Bolivar by adding revetments and raising coastal highways, and constructing sea gates at the San Luis Pass and Bolivar Roads.
    [Show full text]
  • Chapter 4 – State of the Bay, Third Edition
    CHAPTER 4 – STATE OF THE BAY, THIRD EDITION The Human Role, Present Written & Revised by Lisa A. Gonzalez The segment of the planet Earth called the coastal zone is especially important in the context of diversity and human interactions. This is by far the most populated and urbanized portion of our planet, as well as the richest and among the most perturbed. It is a bit surprising that it is also not the most familiar in concept and dimension, in view of the fact that so many people live within it or near it. —G. Carlton Ray, Sustainable Use of the Global Ocean, (1989) Introduction Human activities in and around Galveston Bay have shaped the watershed for thousands of years. The categories of resource use are wide ranging. From humans’ creation of the first shell middens to the present dredging of numerous navigation channels, human inhabitants have an impact on the bay and its surrounding landscape. As the human population grows, society’s influence on the physical and ecological components of the estuarine system becomes more pronounced. Anthropogenic stresses are placed upon the bay’s natural resources and the ecosystem services that they provide (such as clean air and water, flood attenuation, and wildlife habitat). The stressors diminish the health of the estuary and its watershed, as well as the quality of life of residents. The physical and ecological condition of Galveston Bay is a general indicator of the well-being of the regional environment. Most people realize that the bay is an important regional ecosystem, and they have a keen State of the Bay interest in protecting and maintaining its – Figure 4.1.
    [Show full text]
  • Galveston Bay: a Brief History of One of America's Great Waters
    Galveston Bay: A Brief History of One of America’s Great Waters By Courtney Smith Roseate spoonbills and laughing gulls wade near stands of California bulrush on Galveston Bay Foundation’s Sweetwater Nature Preserve on Galveston Island. Photo by Andrew Hancock, courtesy of Galveston Bay Foundation. 8 HOUSTON HISTORY Vol. 10 • No.2 alveston Bay is the most prominent geologic feature the Gulf of Mexico are dependent upon estuaries like Galveston Gon the upper Texas coast. It is the state’s largest bay, Bay during some part of their life cycle. Galveston Bay is the covering about 600 square miles, situated in one of its most most productive bay in Texas and one of the most productive urbanized and industrialized areas. The positioning and vi- bays in the country, trailing only Chesapeake Bay, which is ability of Houston can be traced to its proximity to Galves- eight times its size. ton Bay. Beyond this, the Galveston Bay watershed—or the Chances are if you live, work, study, or recreate in or around area of land that drains into a given waterbody—is about Houston, you depend on Galveston Bay in some way. The 24,000 square miles, stretching from the Houston metro- bay supports a wide array of human uses, including marine politan area north along the Trinity River basin past the transportation, industrial, agricultural, fisheries, residential, Dallas-Fort Worth Metroplex. Half the population of Texas recreational, and tourism. The Houston-Galveston region owes currently lives in the Galveston Bay watershed. Yet few much of its economic viability to ports and shipping, and its know of its worth and even fewer of its rich history.
    [Show full text]
  • Profile 2019.Pub
    Aerial View of Texas City-La Marque (looking south toward Galveston Island) Page 2 Texas City—La Marque Chamber of Commerce 2 Texas City — La Marque Chamber of Commerce 9702 Emmett F. Lowry Expressway P. O. Box 1717 Texas City, Texas 77592 Telephone: 409-935-1408 Fax: 409-316-0901 Hours: Monday—Friday 8:30 am to 5:00 pm www.tclmchamber.com Chamber Administration President ............................................................................ Jenny Senter Ofϐice Manager/Administrative Assistant……….Leanne Post Communications Director ...................................... ..Lorrie Koster Member Relations Manager……………….....…..…..Lauren Perez Special Projects Coordinator……………….…...…Jessica Spangle 2020 Executive Board (Meets 10 am 4th Wednesday of each month) Chairman ……..………………………….………Rusty Plackemeier Chairman Elect…………………………………....…Georgia Meyer Vice Chairman/Treasurer…...………………....Jim MacPherson Vice Chairman ……………..……………..…Genevieve McGarvey Vice Chairman…………………………………….………...Ron Assad Vice Chairman…………………………………………..Gail Figueroa Texas City-La Marque Chamber of Commerce Vice Chairman………………………………………….Phillip Orange Jimmy Hayley Building Past Chairman………………………………………..…Sergio Matute 9702 E.F. Lowry Expressway Texas City, Texas 77591 President……………………………………………….......Jenny Senter 409.935.1408 2020 Board of Directors (meets 11:30 a.m. on the 4th Wednesday of each month) Ron Assad…………………………………………….………...……...Gallant Builders April Jones………………………………………….….Queens Attic Boutique Ramiro Barba……………………………………….……………...Port of Texas City Caitlin
    [Show full text]