30.11.2018 \

FORM – 1 & 1A

“RUNWAL EDEN” REDEVELOPMENT PROJECT

At P lot bearing C.S number: 233 at Malabar-Cumballa Hill division known as 91 Neapean sea road,

By

M/s. Runwal Township Pvt. Ltd Runwal Township Pvt. Ltd. 5th Floor, Runwal Omkar E-square, Sion (East) Mumbai - 400022

FORM – 1

“RUNWAL EDEN”

REDEVELOPMENT PROJECT

At Plot bearing C.S number: 233 at Malabar-Cumballa Hill division known as 91 Neapean sea road, Mumbai

By

M/s. Runwal Township Pvt. Ltd th Runwal Township Pvt. Ltd. 5 Floor, Runwal Omkar E-square, Sion (East) Mumbai - 400022

APPENDIX - I (See paragraph - 6) FORM 1

(I) Basic Information Sr. Item Details No. 1. Name of the project/s ‘Runwal Eden’ Redevelopment project at Malabar- Cumballa Hill division known as 91 Neapean sea road, Mumbai 2. S. No. in the schedule 8 (a) 3. Proposed capacity/ area/ length/ Total Plot Area: 2,048.96 Sq.mt. tonnage to be handled/ command Built-up Area as per FSI: 10,214.49 Sq. mt. area/ lease area/ number of wells to Total Construction Built -up Area: 31,671.27 Sq. mt. be drilled Project Proposal: Building details Flats 1 Residential Building 2 Basements + Ground floor on MHADA: 12 Nos. stilt, partly for car parking and Redevelopment: 13 partly for entrance lobby + 1st to 8th Nos. Podium levels for car parking + 9th Sale: 27 Nos. service floor + 10th Amenity floor + Total : 52 Nos. 11th to 36th (pt) residential floors.

4. New/Expansion/Modernization Amendment in Environment Clearance 5. Existing Capacity/ Area etc. Received Environmental Clearance File No. SEAC- 2016/C.R.424/TC-1 dated 12.05.2017

Total constructed work on site till date (FSI + Non FSI): 28,561.56 Sq. mt. 6. Category of project i.e.’ A’ or 8(a)B2 ‘B’ 7. Does it attract the general Not Applicable condition? If yes, please specify. 8. Does it attract the specific Not Applicable condition? If yes, please specify. 9. Location 91 Neapean sea road Plot/Survey/Khasra No. C.S. No 233 Village Malabar-Cumballa Hill division Tehsil Mumbai District Mumbai State Maharashtra 10. Nearest railway station Churni road railway station: Within 3.50 Km(Road Distance) Nearest airport Mumbai Chhatrapati Shivaji Airport: Within 21.0 Km (Road Distance) 11. Nearest Town, city, District Mumbai Metropolitan Region headquarters along with distance in kms. 12. Village Panchayats, Zilla Parishad, Municipal Corporation of Greater Mumbai (M.C.G.M.) Municipal Corporation, Local body (complete postal address with telephone nos. to be given) 13. Name of the applicant M/s. Runwal Township Pvt. Ltd. 14. Registered Address Runwal Township Pvt. Ltd. 5th Floor, Runwal Omkar E-square, Sion Chunnabhati signal

Form 1- Redevelopment project, Malabar-Cumballa Hill 1

Sr. Item Details No. junction, Sion – East, Mumbai - 400022 15. Address for correspondence 5th Floor, Runwal Omkar E-square, Sion Chunnabhati signal junction, Sion – East, Mumbai - 400022 Name Ms. Pallavi Matkari Designation(Owner/Partner/ CEO) Chief Architect Address 5th Floor, Runwal Omkar E-square, Sion Chunnabhati signal junction, Sion – East, Mumbai Pin Code 400022 E-mail [email protected] Telephone No. 61133000 Fax No. 24093799 16. Details of Alternative Sites Not applicable examined, if any. Location of these sites should be shown on a topo- sheet. 17. Interlinked Projects Not applicable 18. Whether separate application of Not applicable interlinked project has been submitted? 19. If yes, date of submission Not applicable 20. If no, reason Not applicable 21. Whether the proposal involves approval/clearance under: if yes, details of the same and their status to be given. (a) The Forest (Conservation) Act, Not Applicable 1980? (b) The Wildlife (Protection) Act, Not Applicable 1972? (c) The C.R.Z Notification, 1991? As per the DP remark, the plot under reference is located in C.R.Z II and landward side of existing Nepean Sea Road. Received clearance from MCZMA. NOC attached as Enclosure 4. 22. Whether there is any Government Received NOC from Mumbai Building Repairs and Order/Policy relevant/ relating to Reconstruction Board (A MHADA Unit) on 02.02.2016, the site? 20.05.2015, 08.04.2013, 01.09.2012. Copy attached as Enclosure 5. 23. Forest land involved (hectares) Not applicable 24. Whether there is any litigation No pending against the project and/or land in which the project is propose to be set up? (a) Name of the Court (b) Case No. (c) Order /directions of the Court, if any and its relevance with the proposed project.

Form 1- Redevelopment project, Malabar-Cumballa Hill 2

(II) Activity 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) Details thereof (with approximate quantities Sr. Information/Checklist Yes /rates, wherever possible) with source of No. confirmation / No information data 1.1 Permanent or temporary change No The site is in Residential zone as per DP in land use, land cover or remarks. topography including increase in DP Remarks is attached as Enclosure 6. intensity of land use (with respect to local land use plan) 1.2 Clearance of existing land, No There was one existing cess structure (G + 2 vegetation and building? upper floors building) on site. This Existing structure has already been demolished. 1.3 Creation of new land uses? No - 1.4 Pre-construction investigation e.g. Yes Geotechnical Investigation has been carried out. bore houses, soil testing? Report is attached as Enclosure 7. 1.5 Construction works? Yes Residential development 1.6 Demolition works? No -- 1.7 Temporary sites used for No -- construction works or housing of construction workers? 1.8 Above ground building, structures Yes  Excavation material has been partly used and or earthworks including linear partly disposed to Authorized landfill as per structures, cut and fill or permission from M.C.G.M. excavations  Construction waste shall be partly used and remaining will be disposed to authorized landfill site as per permission from M.C.G.M. 1.9 Underground works including No Construction of two basements only mining or Tunneling? 1.10 Reclamation works? No -- 1.11 Dredging? No -- 1.12 Offshore structures? No -- 1.13 Production and manufacturing No -- processes? 1.14 Facilities for storage of goods or Yes Temporary storage facilities to store the materials? construction raw material. 1.15 Facilities for treatment or disposal Yes  STP for treatment of sewage of solid waste or liquid effluents?  Segregation of solid waste into non biodegradable and biodegradable garbage  Treatment of biodegradable waste in Organic Waste Converter  Non-biodegradable waste: To authorized recyclers  Dried sludge from STP : As manure 1.16 Facilities for long term housing of No -- operational workers? 1.17 New road, rail, or sea traffic No -- during construction or operation? 1.18 New road, rail, air waterborne or No -- other transport infrastructure including new or altered routes and stations, ports, airports etc?

Form 1- Redevelopment project, Malabar-Cumballa Hill 3

Details thereof (with approximate quantities Sr. Information/Checklist Yes /rates, wherever possible) with source of No. confirmation / No information data 1.19 Closure or diversion of existing No -- transport routes or infrastructure leading to changes in traffic Movements? 1.20 New or diverted transmission No -- lines or pipelines? 1.21 Impoundment, damming, No -- culverting, realignment or other change to the hydrology of watercourses or aquifers? 1.22 Stream crossings? No -- 1.23 Abstraction or transfers of water No -- from ground or surface waters? 1.24 Changes in water bodies or the Yes By considering the runoff prior to development land surface affecting drainage or and runoff after development there is some run-off? increment in runoff of storm water. Incremental Runoff = 0.03 m3/sec 1.25 Transport of personnel or Yes Transport of construction materials. materials for construction, Precautions taken to reduce the impact of the operation or decommissioning? vehicular movement by trying to avoid the vehicular trips during peak hours. 1.26 Long-term dismantling or No -- decommissioning or restoration works? 1.27 Ongoing activity during No -- decommissioning which could have an impact on the environment? 1.28 Influx of people to an area in No Since this is a redevelopment project there will either temporarily or be influx of ~195 persons (only occupancy of permanently? Sale and MHADA tenants) 1.29 Introduction of alien species? No -- 1.30 Loss of native species or genetic No -- diversity? 1.31 Any other actions? No --

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): Sr. Information/checklist Yes Details thereof (with approximate quantities /rates, No. confirmation / wherever possible) with source of information data No 2.1 Land especially No The land is in developed infrastructure area. undeveloped or agricultural land (ha) 2.2 Water (expected Yes During Operational Phase – source & competing For Workers : From M.C.G.M.: 12 KLD users) unit : KLD For Construction: From Water tankers: 10 - 20 KLD (Depending upon the activity) During Operational Phase – Fresh water from M.C.G.M.: 23 KLD (Domestic)

Form 1- Redevelopment project, Malabar-Cumballa Hill 4

Sr. Information/checklist Yes Details thereof (with approximate quantities /rates, No. confirmation / wherever possible) with source of information data No 2.3 Minerals (MT) No --- 2.4 Construction material Yes Quantity: As per requirement – stone, aggregates, Stone aggregates demand will be met from the clay/soil and / soil (expected generated after excavation and from open market source – MT) Sources: The material required for construction activities shall be procured from company’s authorized/ approved vendors only. The vendor’s performance will be monitored periodically. In case of urgency or non-availability of materials from authorized/ approved vendors, it will be procured from the open market. 2.5 Forests and timber Yes Timber required for doors sourced from local suppliers. (source – MT) 2.6 Energy including Yes During Construction Phase - electricity and fuels Source : BEST (source, competing D.G. Sets: As per requirement users) Unit: fuel (MT), energy (MW) During Operational Phase – Source: BEST Connected load 1537 kW Maximum demand 593 KW D.G sets (For emergency Sale : 1 of 650 kVA each backup in case of power MCGM parking: 1 of 200 kVA failure)

2.7 Any other natural No -- resources (use appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health. Sr. Information/Checklist confirmation Yes / Details thereof (with approximate No. No quantities/rates, wherever possible) with source of information data 3.1 Use of substances or materials, which No --- are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies) 3.2 Changes in occurrence of disease or No --- affect disease vectors (e.g. insect or water borne diseases) 3.3 Affect the welfare of people e.g. by No changing living conditions 3.4 Vulnerable groups of people who could No --- be affected by the project e.g. hospital patients, children, the elderly etc., 3.5 Any other causes No ---

Form 1- Redevelopment project, Malabar-Cumballa Hill 5

4. Production of solid wastes during construction or operation or decommissioning (MT/month): Details thereof (with approximate quantities Sr. Information/Checklist Yes / / rates, wherever possible) with source of No. confirmation No information data 4.1 Spoil, overburden or mine wastes No --- 4.2 Municipal waste (domestic and or Yes The total quantity of solid waste: 117 Kg /day. commercial wastes) (Biodegradable and Non biodegradable) 4.3 Hazardous wastes (as per Yes Waste oil generated from D.G. shall be stored at Hazardous waste Management separate location duly marked and will be sold Rules) to the authorized recyclers. 4.4 Other industrial process wastes No -- 4.5 Surplus product No -- 4.6 Sewage sludge or other sludge from Yes Dried sludge from STP will be used as manure effluent treatment. for plants within the premises. 4.7 Construction or demolition wastes. Yes Construction waste shall be partly used and remaining will be disposed to authorized landfill site as per permission from M.C.G.M. 4.8 Redundant machinery or No -- equipment. 4.9 Contaminated soils or other No -- materials. 4.10 Agriculture wastes. No -- 4.11 Other solid wastes. No --

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) : Sr. Information/Checklist confirmation Yes / Details thereof (with approximate No. No quantities/ rates, wherever possible) with source of information data 5.1 Emissions from combustion of fossil Yes CPCB approved D.G. Sets will be used fuels from stationary or mobile during power failure. sources 5.2 Emissions from production processes No -- 5.3 Emissions from materials handling Yes Fugitive dust emission due to handling and including storage or transport loading-unloading activities is envisaged during construction. Frequent water sprinkling will be done to minimise the fugitive emissions. 5.4 Emissions from construction activities Yes / The project may cause rise in dust levels including plant and equipment Marginal during construction phase. Precautions would be taken to reduce dust generation by water sprinkling at regular intervals. 5.5 Dust or odours from handling of Yes Dust generation controlled as described materials including construction above. materials, sewage and waste For odour control: Proper ventilation shall be provided around STP and solid waste management facilities 5.6 Emissions from incineration of waste No -- 5.7 Emissions from burning of waste in No -- open air (e.g. slash materials, construction debris) 5.8 Emissions from any other sources No --

Form 1- Redevelopment project, Malabar-Cumballa Hill 6

6. Generation of Noise and Vibration, and Emissions of Light and Heat: Sr. Information/Checklist Yes / Details thereof (with approximate No. confirmation No quantities/rates, wherever possible) with source of information data 6.1 From operation of Yes For control of noise following measures shall be equipment e.g. engines, but adopted: ventilation plant, crushers. negligible  Regular noise monitoring to be scheduled to maintain the noise level within the levels prescribed by CPCB during day and night time  Provision of ear plugs to workers  Use of high efficiency mufflers  No noise polluting work in night shifts  Provision of barricades along the periphery of the site. 6.2 From industrial or similar No -- processes. 6.3 From construction or Yes Noise levels may increase due to operation of demolition. machinery as well as transportation vehicles. This may cause nuisance to the nearby area. Following precautions shall be taken to control noise pollution:  Regular noise monitoring to maintain the noise level within the levels prescribed by CPCB during day and night time  Provision of ear plugs to workers  Use of high efficiency mufflers  No noise polluting work in night shifts  Provision of barricades along the periphery of the site  Plantation of Trees 6.4 From blasting or piling. No -- 6.5 From construction or Yes During Construction phase: operational traffic. Transport of materials for construction work. Precautions will be taken to reduce the impact of the vehicular movement such as vehicular trips will not be at peak traffic hours.

Operation Phase : The vehicular parking will be restricted only in the adequate parking area provided, which would help in reducing noise pollution due to traffic congestion Tree plantation will also help to reduce the noise level and also will enhance air quality. 6.6 From lighting or cooling No -- systems. 6.7 From any other sources. No --

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: Sr. Information/Checklist confirmation Yes / Details thereof (with approximate No. No quantities/rates, wherever possible) with source of information data 7.1 From handling, storage, use or No -- spillage of hazardous materials.

Form 1- Redevelopment project, Malabar-Cumballa Hill 7

Sr. Information/Checklist confirmation Yes / Details thereof (with approximate No. No quantities/rates, wherever possible) with source of information data 7.2 From discharge of sewage or other No The treated sewage will be reused for effluents to water or the land flushing and gardening within the premises. (expected mode and place of Excess treated sewage (during monsoon and discharge). non monsoon season) will be disposed to sewer line 7.3 By deposition of pollutants emitted to No Dust will be generated during construction air into the land or into water. phase from earthworks and movement of vehicles. Appropriate fugitive dust control measures, including watering, water sprinkling of exposed areas and dust covers for trucks, will be provided to minimize any impacts. DG exhaust will be discharged at stipulated height by providing adequate stack height to the DG sets. 7.4 From any other sources. No --

7.5 Is there a risk of long term build up No -- of pollutants in the environment from these sources?

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment : Sr. Information/Checklist confirmation Yes / Details thereof (with approximate No. No quantities /rates, wherever possible) with source of information data 8.1 From explosions, spillages, fires etc No -- from storage, handling, use or production of hazardous substances 8.2 From any other causes. No -- 8.3 Could the project be affected by -- Landslides are not expected in the area. natural disasters causing Management plan for flood and earthquake is environmental damage (e.g. floods, as follows : earthquakes, landslides, and Flood : cloudburst)?  Minimizing the incremental runoff from the site with the help of rain water harvesting tank of capacity 20 KL  Proper management of channelization of storm water from site by using proper internal SWD system and discharge points of having adequate capacity  Use of screens and silt traps to SWD  Proper maintenance of storm water drainage to avoid choking of drains and flooding on site  Ensure discharge of storm water from the site is clear of sediment and pollution  Provision of sump pumps  Existing external drain of adequate capacity Earthquake :

Form 1- Redevelopment project, Malabar-Cumballa Hill 8

Sr. Information/Checklist confirmation Yes / Details thereof (with approximate No. No quantities /rates, wherever possible) with source of information data The structure of the building is designed as per IS codes for zone III. Disaster Management Plan is attached as Enclosure 8.

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality: Sr. Information/Checklist confirmation Yes / Details thereof (with approximate No. No quantities/rates, wherever possible) with source of information data 9.1 Lead to development of supporting facilities, ancillary development or development stimulated by the project which could have impact on the environment e.g.: •Supporting infrastructure (roads, No Supporting infrastructure is already in power supply, waste or waste water existence. treatment, etc.) • housing development Yes R edevelopment project • extractive industries • supply industries • other 9.2 Lead to after-use of the site, which No --- could have an impact on the environment 9.3 Set a precedent for later Yes Will create job opportunity in construction developments and operation phase with support staff like security, maintenance, household workers, shop keepers etc. 9.4 Have cumulative effects due to Yes Impacts on water availability, storm water proximity to other existing or drainage, availability of electricity, traffic planned projects with similar effects congestion etc.

(III) Environmental Sensitivity Sr. Areas Name/ Aerial distance No. Identity (within 15 km.) from Proposed project location boundary 1 Areas protected under international Nil -- conventions, national or local legislation for their ecological, landscape, cultural or other related value 2 Areas which are important or sensitive for Bay Approx. 8.0 Km ecological reasons - Wetlands, Mahul Sewri Creek Approx. 10.0 Km watercourses or other water bodies, Arabian Sea Approx. 0.4 Km coastal zone, biospheres, mountains, forests

Form 1- Redevelopment project, Malabar-Cumballa Hill 9

Sr. Areas Name/ Aerial distance No. Identity (within 15 km.) from Proposed project location boundary 3 Areas used by protected, important or Maharashtra Nature Park Approx. 13.0 Km sensitive species of flora or fauna for Jijamata Udyan Approx. 5.0 Km breeding, nesting, foraging, resting, over Approx.1.0 Km wintering, migration 4 Inland, coastal, marine or underground Mahim Bay Approx. 8.0 Km waters Mahul Sewri Creek Approx. 10.0 Km Arabian Sea Approx. 0.4 Km Banganaga Talao Approx. 1.0 Km 5 State, National boundaries No -- 6 Routes or facilities used by the public for Eastern Fly Way. Approx. 5.0 Km access to recreation or other tourist, National Highway 3 (JJ Approx. 4.0 Km pilgrim areas Road) sea link Approx. 7.0 Km 7 Defence installations No -- 8 Densely populated or built-up area Mumbai Metropolitan -- Region 9 Areas occupied by sensitive man-made Mumbai Metropolitan -- land uses (hospitals, schools, places of Region worship, community facilities) 10 Areas containing important, high quality No -- or scarce resources (Ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11 Areas already subjected to pollution or No -- environmental damage. (those where existing legal environmental standards are exceeded) 12 Areas susceptible to natural hazard which No -- could cause the project to present environmental problems (Earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)

(IV) Proposed Terms of Reference for EIA studies: Not Applicable

Form 1- Redevelopment project, Malabar-Cumballa Hill 10