MAJOR PROJECTS 2017-2019
MINISTRY OF PUBLIC WORKS JUNE 2017
CONCESSIONS
- The Loa Route - Route 5: Section Caldera - Antofagasta - Re-tender of Route N° 5 Los Vilos – La Serena and Conurbation - Interconnection Santiago-Valparaíso-Viña del Mar (Route 68) + Alternatives - Costanera Central Highway - Section Av. La Florida – Camilo Henríquez - Eastern Américo Vespucio Urban Highway - Príncipe de Gales – Grecia - Interconnection Highway 68 with Highway 78 - Fruit Highway, G-66 - Re-tender Route 5 - Talca – Chillán - Re-tender Route 5 - Chillán – Collipulli - Nahuelbuta Route 180 - Route Freire – Villarrica – Pucón - Re-tender Route 5: Temuco – Rio Bueno + Access to Valdivia - Metropolitan Highway of Puerto Montt - North-South Route of Chiloé - Las Palmas Reservoir - Los Angeles Reservoir - Catemu Reservoir - La Tranca and Murallas Viejas Reservoirs
PROJECT DATA SHEET PUBLIC WORKS PPP - THE LOA ROUTE Updated: JUNE 2017
Location Map Project Information Communes of Sierra Gorda and Calama in Antofagasta Location Region
Increase service levels and improving connectivity and Objective territorial integration of the Region Rutas del Loa
Revamping and expansion up to 2 lanes each side Description of the Route 25 of Works Construction of the Eastern bypass to Calama connecting Routes 21, 23, 24 and 25
Economic It considers MGI and ITC Conditions R Estimated US$ 293 million ut Investment as Type of PPP – BOT Investment de l Improvement of service and standard levels of Lo Route 25. Benefits Improvement of safety conditions and shorter travel a times (1 36
K Current Situation m. Timetable
Call for Bids ) 2nd Quarter 2017
• Bidding conditions ready Receipt of Tenders 4th Quarter 2017
Contract award 1st Semester 2018
Source: CCOP
PROJECT DATA SHEET PUBLIC WORKS PPP - ROUTE 5: SECTION CALDERA - Updated: JUNE 2017 ANTOFAGASTA
Project Information: Location Map
Route 5 between the cities of Caldera and Location Antofagasta
Improvement of the standard in this section of the Objective Route 5
Description of Two lanes in each side. Works Max speed 120km/h
Road tolls Economic Conditions State subsidy 30 %
Estimated US$ 640 million Investment Type of PPP – BOT - Investment
Expansion of the 4 lanes highway from Antofagasta to the south Benefits Improvement of safety conditions and shorter travel times More secondary access roads
Current Situation Timetable
Call for Bids 3rd Quarter 2018
Studies of this private proposal under progress Receipt of Tenders 1st Quarter 2019
Contract award 2nd Semester 2019
Source: CCOP
PROJECT DATA SHEET PUBLIC WORKS PPP
- RE-TENDER OF ROUTE N° 5 LOS VILOS – LA Updated: JUNE 2017 SERENA AND CONURBATION
Project Information Location Map Location North of Santiago from km 229 to km 474 Re- tender of the contract for Route N° 5 from Los Objective Vilos to Coquimbo, including urban sector between Coquimbo and La Serena
Description of 229 km 4-lanes intercity road Works 17 km of urban highway with three lanes in each direction
Economic Road tolls Conditions
Estimated US$ 328 million Investment Type of PPP – BOT Investment
Improve urban connectivity Increase transport capacity on the urban sector Benefits Reduce accidents With this section the concessioned highway from Caldera to Pargua goes up to 1.955 km
Current Situation Timetable
Private Initiative Call for bids 3rd Quarter 2017 Developing studies for: design, expropriations, environmental
assessment Reception of bids End of 2017 Finishing project proposal Preparation of bidding conditions Contract award 1st Semester 2018
Source: CCOP
PROJECT DATA SHEET PUBLIC WORKS PPP - INTERCONNECTION SANTIAGO-VALPARAÍSO- Updated: JUNE 2017 VIÑA DEL MAR (ROUTE 68) + ALTERNATIVES
Project Information: Location Map
Location Provinces of Valparaíso and Santiago
Increase service levels and improving the standard Objective of the highway
Route 68, has 110 km. It needs a better standard Description of with different secondary roads, junctions and Works additional lanes.
Economic Road tolls Conditions
Estimated US$ 600 million Investment
Type of PPP – BOT Investment
Promotes regional economic growth and Benefits territorial integration of 2 of the most important metropolitan areas of the country and Valparaíso seaport
Current Situation Timetable
Call for Bids 1st Semester 2019 Studies of demand and Social Evaluation under progress Receipt of Tenders End of 2019 Re-tender Route 68 Santiago – Valparaíso – Viña del Mar.
Contract award 2nd Quarter 2020
Source: CCOP
PROJECT DATA SHEET PUBLIC WORKS PPP - COSTANERA CENTRAL HIGHWAY - SECTION AV. LA FLORIDA – CAMILO HENRÍQUEZ Updated: JUNE 2017
Project Information: Location Map South-east side of Santiago Location Metropolitan Area. Communes of La Florida and Puente Alto.
Improvement of transport system, connectivity and Objective infrastructure standard of the city Building a high standard underground highway of 12 km.. 9 km is an underground route with 3 lanes in each side and the Description of other 3 km will have 2 lanes in each side. Works The project includes connections to local roads and Américo Vespucio Sur Highway.
Road tolls Economic State subsidies 36 % Conditions Free flow tolls
Estimated US$ 1.1 Billion Investment Type of Private Initiative - PPP – BOT Investment
Improvement of connectivity between south-east districts and downtown Reduction of traffic congestion Benefits New public transport corridor Reduction of operational costs. Improvement of safety conditions and shorter travel times.
Current Situation Timetable Call for bids 2nd Quarter 2018 Developing of technical studies and bidding conditions Citizen participation in local communities Receipt of tenders 1st Quarter 2019
Contract award 4th Quarter 2019
Source: CCOP
PROJECT DATA SHEET PUBLIC WORKS PPP - Eastern Américo Vespucio Urban Updated: JUNE 2017 Highway - Príncipe de Gales – Grecia
Project Information Location Map
Location Eastern side of Santiago
Complete the Americo Vespucio ring road with high Objective quality and service standard Construction of two underground double tracks with 3 lanes each side Description of Works Urban redeveloping in surface considering larger green areas and more facilities for public urban transportation. Road tolls Economic Estimated 15% of state subsidy Conditions Free flow tolls Estimated US$ 786 million Investment Type of PPP – BOT Investment Complete the Américo Vespucio ring road in Santiago with a high service standard Reduce accidents and traffic jams, mainly during rush hours. Benefits Reduce commuting time and pollution emissions. Improve public transportation and connectivity in the city.
Current Situation Timetable
Call for Bids August 2016 Finishing technical studies and bidding bases
Prequalification process re-open Receipt of Tenders 2nd Quarter 2017 Closing agreements and approval with authorities Contract award 4th Quarter 2017
Source: CCOP
PROJECT DATA SHEET PUBLIC WORKS PPP INTERCONNECTION HIGHWAY 68 WITH HIGHWAY 78 Updated: JUNE 2017
Project Information: Location Map Western side of Santiago Location Metropolitan Area. Communes of Pudahuel and Maipú. Improvement of transport system, Objective connectivity and infrastructure standard of Western Santiago Construction of a 9.4 km 4- lanes road, to reduce traffic impact in urban zones Internal roads, lighting and drainage Description of Works Construction of different flyovers and structures in the junctions with Route 68 and Route 78 Internal roads and road safety measures Road tolls Economic Conditions Free flow tolls Not subsidies
Estimated Investment US$ 250 million
Type of Investment Private Initiative - PPP – BOT Improve connectivity between central and western areas of Santiago Improve connection to the main Benefits national seaports avoiding to cross through Santiago. Better local urban development Reduction of accidents, travel times and pollution emissions Current Situation Timetable Call for bids 3rd Quarter 2017 Finishing technical studies and developing of bidding contracts Reception of bids End of 2017
Contract award 1st Semester 2018
Source: CCOP
PROJECT DATA SHEET PUBLIC WORKS PPP - FRUIT HIGHWAY, G-66 Updated: JUNE 2017
Project Information Location Map 120 km south from Santiago to the port of San Location Antonio Improve connectivity for small and medium scale producers (fruits, vegetables and wine) from Objective O’Higgins and Maule Regions to the port of San Antonio Restore and improve 138 km of the existing road and construction of a bidirectional road to reduce traffic impact in urban zones Description of Construction of a 21 km 4-lanes road Works Construction of different flyovers and structures to reduce negative impact on population Road tolls Economic State subsidies 50-60 % Conditions Free flow tolls Estimated US$ 600 million Investment Type of PPP – BOT Investment Improvement of connectivity Reduction of transport costs for local Benefits producers Reduction of accidents
Current Situation Timetable
Call for Bids 3rd Quarter 2017 Technical studies ready
Agreements with local authorities and citizen participation Receipt of Tenders 1st Quarter 2018 Preparation of bidding contracts
Contract award 1st semester 2018
Source: CCOP
PROJECT DATA SHEET PUBLIC WORKS PPP RE-TENDER ROUTE 5 - TALCA – CHILLÁN Updated: JUNE 2017
Project Information: Location Map Communes of Río Claro, San Rafael, Talca, Maule, San Javier, Villa Alegre, Linares, Longaví, Location Retiro, Parral y Ñiquén, San Carlos, San Nicolás, Chillán and Chillán Viejo. Increase service levels and improving the standard Objective of the highway with additional works
4-lanes road and 193.3 km, It will have: Description of New local roads Works Junctions – bridges Bypass sectors Free flow toll system
Economic Road tolls Conditions Not subsidies
Estimated US$ 225 million Investment Type of PPP – BOT Investment
Improve connectivity between central and southern Chile Better local and regional economic Benefits development and integration Reduction of accidents, travel times and pollution emissions
Current Situation Timetable
Call for Bids 1st Quarter 2019 Studies of demand and social evaluation under progress Receipt of Tenders 3rd Quarter 2019 TOR of basic engineering studies in preparation.
Contract award 1st Quarter 2020
Source: CCOP
PROJECT DATA SHEET PUBLIC WORKS PPP - RE-TENDER ROUTE 5 - CHILLÁN – Updated: JUNE 2017 COLLIPULLI
Project Information: Location Map
Communes of Chillán, Bulnes, Cabrero, Los Location Ángeles, Mulchén and Collipulli in Biobío Region Improvement of actual highway standard, including Objective additional works and the increase of service levels while improving user safety Section of 160 km. in Route 5 with 2-lanes in each side.
To include: Description of Works New local roads Junctions – bridges Bypass sectors Free flow toll system
Economic Road tolls Conditions Not subsidies
Estimated US$ 225 million Investment Type of PPP – BOT Investment Improvement of connectivity Reduction of transport costs for local producers Reduction of accidents Improve connectivity between central and Benefits southern Chile Better local and regional economic development and integration
Current Situation Timetable Call for Bids 1st Semester 2019 Studies under progress Receipt of Tenders 3rd Quarter 2019 Contract award 2nd Quarter 2020 Source: CCOP
PROJECT DATA SHEET PUBLIC WORKS PPP - NAHUELBUTA ROUTE 180 Updated: JUNE 2017
Project Information Location Map
Location Km 520 south of Santiago
Improve connectivity and maximize economic and Objective social benefits in an area mainly focused on forests and forestry 55 km road Description of 4-lanes highway Works Uneven junctions Road tolls Economic Estimated 41% of state subsidy Conditions Manual tolls Estimated US$ 245 million Investment Type of PPP – B5OT Investment
Connectivity improvement Benefits Reduction of transport costs for local producers Reduction of accidents
Current Situation Timetable
Call for Bids November 2016
Bidding bases and procedures in progress Receipt of Tenders 2nd Quarter 2017 Agreements with local authorities and indigenous communities Contract award End of 2017
Source: CCOP
PROJECT DATA SHEET PUBLIC WORKS PPP - RE-TENDER ROUTE 5: TEMUCO – RIO BUENO + Updated: JUNE 2017 ACCESS TO VALDIVIA
Location Map
Project Information: Communes of Gorbea, Loncoche, Lanco, San José Location de la Mariquina, Máfil, Los Lagos, Paillaco, La Unión, Río Bueno and Valdivia
Improvement of actual highway standard, including Objective additional works and the increase of service levels while improving user safety and better access to Valdivia city Improvement of 172 km. of the 4 - lanes road Upgrade to 2-lanes in each side to Valdivia (88 Description of km.) Works New local roads Junctions – bridges Bypass sectors.
Economic - Road tolls Conditions - Not subsidies
Estimated US$ 250 million. Investment Type of PPP – BOT Investment Increase of safety standard to decrease accident rate in acess to Valdivia
Connectivity improvement
Reduction of transport costs for local producers Benefits
Reduction of accidents and congestion
Better local and regional economic development
Current Situation Timetable
Call for Bids End of 2017 Private initiative. Proponent R y Q Ingeniería. Time limit for Receipt of Tenders 4th Quarter 2018 presentation of first studies: April 2017
Contract award 2nd Quarter 2019
Source: CCOP
PROJECT DATA SHEET PUBLIC WORKS PPP - METROPOLITAN HIGHWAY OF PUERTO Updated: JUNE 2017 MONTT
Project Information Location Map
Location Puerto Montt - 1.000 km. south of Santiago
• Improvement of transport system, connectivity Objective and infrastructure standard of Puerto Montt • Improvement of connection between Puerto Varas and El Tepual Airport Description of 4-lanes highway in 32 km. Works Urban highway standard Road tolls Economic Estimated State subsidy; 30 % Conditions Free flow tolls Estimated US$ 321 million Investment Type of Investment PPP – BOT
Improvement of connectivity between Puerto Montt and Puerto Varas Benefits Reduction of traffic congestion. Reduction of operational costs. Improvement of safety conditions.
Current Situation Timetable
Private initiative Call for Bids End of 2017 Developing of technical studies (demand, environmental
assessement, business model, etc..) Receipt of Tenders 2nd Quarter 2018 Defining economic conditions Citizen participation from 2nd Semester 2016 Contract award End of 2018
Source: CCOP
PROJECT DATA SHEET PUBLIC WORKS PPP - NORTH-SOUTH ROUTE OF CHILOÉ Updated: JUNE 2017
Project Information Location Map
Location 1,100 km south of Santiago
Improve and extend the transportation system in the Objective island of Chiloé Improvement of 101 km road with 2-lanes each side Description of Construction of auxiliary tracks, road safety Works measures, path rectification, construction of new bridges and maintenance of existing ones and environmental measures.
Economic Road tolls Conditions Not subsidies
Estimated US$ 250 million Investment Type of Private initiative – PPP BOT Investment
Improve connectivity Increase transport capacity on the trunk road of the island Benefits Reduce accidents Contribute to the economic development of the island
Current Situation Timetable
Call for Bids 3rd Quarter 2017 Private initiative (Constructora Internacional). Developing of
studies until June 2017 Receipt of Tenders 2nd Quarter 2018 Developing of bidding conditions Contract award End of 2018
Source: CCOP
NATIONAL DEP. FOR HYDRAULIC PROJECT DATA SHEET WORKS - PUBLIC WORKS PPP - LAS PALMAS RESERVOIR Updated: JUNE 2017
Project Information: Location Map
Petorca Province, Petorca Commune Location
Volume of the reservoir: 55 Hm3. Description of Feeder channel: 58 km Works .
Irrigation área 2.932 Ha and 1,285 rural properties
River sections In communes of Petorca and Cabildo
Estimated VAN MM$ 35,000. investment and TIR = 8,9 % economic conditions US$ 161 million – State subsidy near 100 %
Hydroelectric Not generation The National Department has water rights for 10 Water rights Hm3/year, in rivulet Las Palmas.
Current Situation Timetable Activity Date End of design December 2016 Environment December 2016 1. Design studies under process Assessment Call for bids 3rd Quarter 2017 2. Project in the National System for Environment Assessment
Receipt of Tenders End of 2017 End of construction 2022
Source: Department of Irrigation Projects
NATIONAL DEP. FOR HYDRAULIC PROJECT DATA SHEET WORKS - PUBLIC WORKS PPP - LOS ÁNGELES RESERVOIR Updated: JUNE 2017
Project Information Location Map
Location Petorca Province, Commune of La Ligua.
Multipurpose reservoir with capacity of 30 Description of Hm3 and a feeder channel of 24 km (from Works Alicahue River).
Irrigation Area 2,160 Ha. and 676 rural properties
Socio-economic indicators VAN: MM$ 280
Estimated US$ 161 million – State subsidy near 100 % Investment
Hydroelectric No Generation Water rights under study. The reservoir has Water rights water rights from users.
Current Situation Timetable Activity Date Design Studies 1st Semester 2017 1. Environment assessment studies under progress. Environment Assessment 2nd Semester 2017 2. Complementary design studies are developing Call for bidding 4th Quarter 2017 3. The MOPW is analyzing PPP conditions Receipt of Tenders 1st Quarter 2018
Source: Department of Irrigation Projects
NATIONAL DEP. FOR HYDRAULIC PROJECT DATA SHEET WORKS - PUBLIC WORKS PPP - CATEMU RESERVOIR Updated: JUNE 2017
Project Information Location Map
San Felipe Province, Commune of Catemu in Location Valparaiso Region
Volume of the reservoir: 180 Hm3 Description Dam wall height: 65 m of Works Feeder Channel: 25 km (from Aconcagua River) and a capacity of 20 m3/s
Irrigation 33,100 Ha and 4,160 rural properties área
River Lower areas of 2nd, 3rd and 4th sections of Aconcagua sections River
Estimated US$ 423 million – State subsidy near 100 % investment
Hydroelectric 5 to 10 MW generation
The National Department has water rights for 630 Water rights Hm3/year in the 2nd section of Aconcagua River. Water rights of users equivalent to 70 % during winter.
Current Situation Timetable Activity Date
Environment
Assessment and 2nd Sem. 2017 Technical studies to review and complement the feasibility of the dam studies performed
Expropiations 2nd Sem. 2017 Study of environmental assessment under finishing process.
Bidding process 2nd Sem. 2017 Tender conditions ready
Receipt of Tenders 1st Sem. 2018
Source: Department of Irrigation Projects
NATIONAL DEP FPR HYDAULIC WORKS – PROJECT DATA SHEET PUBLIC WORKS PPP LA TRANCA RESERVOIR Updated: JUNE 2017
Project Information
Location Limari Province, commune of Combarbalá,
Cogotí River Multipurpose reservoir type CFRD Description of Capacity: 50 Hm3. Works Dam wall height: 120 m It includes some complementary works.
Benefits Commune of Combarbalá inhabitants 4,940 Ha of irrigation area and 432 rural properties. Estimated Investment US$ 177 million and 100 % subsidy
Hydroelectric Generation 2.4 MW
Water rights Mainly from rural users
Current situation Timetable End of basic design 2nd Semester 2017 Complementary design studies under progress studies
nd Environment assessment studies developing End of EAS 2 Semester 2017 Call for bidding End of 2017
Receipt of Tenders 3rd Quarter 2018
Source: Department of Irrigation Projects
NATIONAL DEP. FOR HYDRAULIC
PROJECT DATA SHEET WORKS – PUBLIC WORKS PPP MURALLAS VIEJAS RESERVOIR Updated: JUNE 2017
Project Information
Location Limarí Province, commune of Combarbalá, Combarbalá River
Description of Works Multipurpose reservoir type CFRD Capacity: 50 Hm3 Dam wall height: 107 m It includes some complementary works
Inhabitants and agriculture producers
of Combarbalá commune Benefits 2,370 Ha irrigation area and 500 rural properties Rural drinking water programme Estimated US$ 125 million with 100 % subsidies Investment
Hydroelectric 1 MW Generation . Water rights Mainly from rural users
Current Situation Timetable End of basic design 2nd Semester 2017 Complementary design studies under progress studies
Environment assessment studies developing End of EAS 2nd Semester 2017
Call for bidding 2nd Semester 2017
Receipt of Tenders 1st Semester 2018 Source: Department of Irrigation Projects
La Tranca and Murallas Viejas reservoirs will be tendered jointly
BINATIONAL PROJECTS
- Agua Negra Binational Tunnel
PROJECT DATA SHEET CHILE-ARGENTINA - AGUA NEGRA BINATIONAL TUNNEL Updated: JUNE 2017
Project Information Location Map Coquimbo region in Chile and San Juan Province Location in Argentina Improve integration between Chile and Argentina Objective and extend the transportation system with Mercosur countries
Description of Construction of a tunnel of 13.9 km in the Works Andes Mountains at 3,600 mt of altitude
Economic Total costs according to the territorial part: 72 % Conditions Argentina and 28 % Chile
Estimated US$ 1.4 billion Investment Type of Direct public investment financed by IABD Investment
Improve connectivity of Chile and Mercosur countries Benefits Contribute to the economic development mainly of Coquimbo region and San Juan Province
Current Situation Timetable Call for October 19th, 2016 prequalification Institutional organization of a binational entity: EBITAN Call for Bids 4th Quarter 2017 Prequalification in progress
Contract award 1st Semester 2018
Source: MOP
CONTACTS
CONCESSIONS
Concessions Coordinator: Eduardo Abedrapo, Merced 753, Santiago, Chile, email: [email protected]
INTERNATIONAL COORDINATION
International Coordinator MOP: Rigoberto García G., Morandé 59, 6º piso, Santiago, Chile, email: [email protected]