ENEL DISTRIBUZIONE
Progetto Isernia (CP Carpinone) Delibera AEEG ARG/elt 39/10
Giorgio Di Lembo Sistemi di Telecontrollo e Automazione
Milano, 28 Novembre 2013
Questo documento contiene informazioni di proprietà di Enel SpA e deve essere utilizzato esclusivamente dal destinatario in relazione alle finalità per le quali è stato ricevuto. E' vietata qualsiasi forma di riproduzione o di divulgazione senza l'esplicito consenso di Enel SpA. Uso: AZIENDALE Isernia Project
Site information ISERNIA
“Zona” Enel - Isernia
HV/MV substation: “Carpinone” • Bus bar: “Verde”) Primary substation and MV network • TR 25 MVA, Compensated MV neutral point ; • Inversion of power flow: 1,4% of time • 5 MV feeders + “Centro Satellite” Passive Users: • 157 Secondary Subs (7.294 LV users) - 18.540kW • 25 MV users - 12.970 kW Active Users (Producers) • 5 Hydro 8.967 kW • 1 biogas 650 kW • 1 Photovoltaic 82 kW • Connection requests (3.728,3 kW) In acceptance phase (4.686,3 kW) Relevant Operative Center • Campobasso
Uso: AZIENDALE Isernia Project Overview Integration of Smart Grid key elements Project cost ≈ 6,5M€ Time span ≈ 3 years
DG Management Energy Storage System Smart Info Electric Vehicles
31/12/2013 ≈ 5M€
Same functions alredy Integration of developped in POI-P3 First ESS on MV First field test of recharging project (“ Energie network installed in large scale (8000 infrastructure with solar Rinnovabili e Risparmio Italy customers) power plant and Energetico 2007-2013 “: Storage; usage test of Regolazione evoluta EV for Enel field crews della tensione Uso: AZIENDALE Isernia Project DG Management – Main Functions
Anti – Islanding Fast MV fault Isolation Detection of possible Detection on isolation of MV
islanding condition on MV fault sections without the
Network and disconnection tripping of the breaker at the GRIDS SMART
of relevant generators line departure
ALWAYS , ON ALWAYS
\
Voltage Control Measurement collection, Participation of MV DG production forecasting
Distributed Generation to and data transmission
COMMUNICATION Voltage regulation on MV towards TSO systems
feeders
BROADBAND BROADBAND
New regulation rules . New connection criteria; . DG dispatching 4 Uso: AZIENDALE Isernia Project DG Management – Fast MV fault isolation and anti-islanding
Inhibit Inhibit Inhibit PS
Open SS1 SS2 SS3 SS4 Open
Inhibit Inhibit PS
SS1 SS2Open SS3 SS4 Open
5 Uso: AZIENDALE Isernia Project DG Management – Fast MV fault isolation and anti-islanding
Inhibit Inhibit Inhibit PS
RGDM1 RGDM2 RGDM3 RGDM4
Inhibit SS1 SS2 SS3 SS4 MV
Customer Inhibit
Wireless inhibit
Wired inhibit Inhibit
6 Uso: AZIENDALE Isernia Project DG Management – Voltage control
Simulation of regulation
Produced Active Power cos φ
Reactive power
7 Uso: AZIENDALE Isernia Project Measurement collection, DG production forecasting and data transmission towards TSO systems
HV line
HV AT Primary Substation MT Linea MT Linea MT MT MT Weather MV MV Producer Forecast
BT Secondary Autoproduttore MT subsation LV feeder LV LV Producer •Network structure •Generators Autoproduttore BT •Data from meters •Measurements •Load profiles MAGO Intranet ST Web Operative Applications Center
8 Uso: AZIENDALE Isernia project DG Management: Telecommunication and Primary substation
Cabina Primaria Rete di comunicazione WiMax, HSDPA, Wireless fibra ottica, LTE The competition for this service was won by Telecom Italia that will provide LTE (4G) connettivity for about 70 secondary substations CS1 CS2 CS3 CS4 Nuovo Linea MT (Confine) Fibra Fibra Nuovo Sistema di Optical fiber (ADSS) TPT2020 Protezione e Controllo Section 1: Carpinone-Carovilli Section 2: Carpinone- Carpino
PRODUTTORE PRODUTTORE MT MT
Sistema Centrale di controllo
TPT2020 + Centralized Protections (Carpinone + Carovilli): in operation within December 2013;
New transformer Panel (PIT): in operation within December 2013
Uso: AZIENDALE Isernia project DG Management: Secondary substations and producers
MV Enel MV Substation Customer Site Switchboard General Protection Circuit Breaker
Interface Prot. RGDM UP Relais Router and RTU Fault Passage Indicator 61850 Interface (DV7300) Batteries + Charger Inib.+Trip+ΔF WiMax, HDSPA, Broadband IEDs LTE opt Modem
fiber,... Switch MV cables Router Ethernet Inverters AMI ...
RGDAT/1 UP/1 RGDAT/2 UP/2 Ingressi misura Presenza Vcc WAN1 Display Anomalia Ethernet1 2 3 4 5 6 7 8 24 Vcc WAN2 (+) - + CONSOLE (-) O.F. towards Active Customer …. IRE
RGDMs + MV Switchboard (DY800) DV7300 + Ethernet Switch: within Sept. 2014 Installation = done; IRE: within September 2014 10 UP + Routers + Modem: within March 2014 Uso: AZIENDALE Isernia Project Energy Storage System Battery Technology: Li-ion Maximum Power: 1 MVA Energy Capacity: 500 kWh Number of Cycles: 2000 Efficiency: 85% Installation Area: 90 m2
Basic functions (P,Q,cosφ): in operation;
Advanced functions: September 2014; (Peak shaving, voltage regulation, optimization functions and integration with recharging station) 11 . Uso: AZIENDALE Isernia Project Electric Vehicles 1/2
5 Renault Cangoo to be used by Enel Crews (average trip: 90km per day) Uso: AZIENDALE Isernia Project Electric Vehicles 2/2
PV roof for electric vans Intelligent controller
MV Network MV/LV transformers Recharging pole (outdoor )
MV storage system 13 Uso: AZIENDALE Isernia Project Smart Info: Overview
The project includes the installation of approximately 8,000 devices in order to increase the participation of the end user to the electrical system and promote an efficient use of energy; it gives the customer readable information on energy consumption and provides home controllers with data for load management (home automation)
Smart Info is based on Enel remote metering system activated more then 10 years ago, on the whole national territory: • plugged into one of the house electricity sockets; • univocally associated to customer’s own meter; • makes consumption or generation data available.
14 Uso: AZIENDALE Isernia Project Smart Info: Main functions of Enel Info+
ANALYSE: Smart Info Manager SEE: Smart Info Display “SEE” plus: • Current, historical, tendency • Detailed analysis of load profile consumption • Comparisons in time • Tariff time bands notification • Comparison generation vs consumption • Power/Consumption limits • Energy efficiency suggestions monitoring • Contractual data visualisation • Messages from SO • Extra information (date, hour…)
EXPLORE: Smart Info Mobile “SEE” + “ANALYSE” accessible from a smartphone
Data Analytics Uso: AZIENDALE Isernia Project Enel Info+: 2013 activities • Progress: 3300 households recruited (~30% of the invited households) • Forecast 2013: 4500 households • Project launched in 19 towns with Vastogirardi dedicated events
Carovilli
Roccasicura
Pescolanciano Chiauci
Miranda Sessano del M. Civitanova Del Sannio Enel Info+ Kit Fornelli Pesche ISERNIA Carpinone
Macchia di I. Pettoranello S.Maria del M.
S.Agapito Castelpetroso
Monteroduni Longano
Castelpizzuto
Project already launched Uso: AZIENDALE Isernia Project Lesson learned
Unexpected component costs:
• Telecommunication (LTE, Optical fibre, Routers, and switches); • IRE interface.
Difficulties and time consuming activities: Enel Info+ Kit
• To involve producer and to equip their plants; • To involve people in Enel smart info trial; • To involve the main European producers of inverters; • To obtain permission for PV power plant.
19