Eskom Presentation

Total Page:16

File Type:pdf, Size:1020Kb

Eskom Presentation Compliance to MES: Progress, postponements and technology options. Portfolio Committee on Environmental Affairs' Workshop on the Minimum Emission Standards. Date: 06 February 2018 Executive overview • Eskom supports the Minimum Emission Standards as they are needed to reduce harmful health effects of air pollution and provide certainty for planning. • Eskom has made progress with its “power plant compliance status” but there are some delays being experienced in project execution • Eskom has made progress with the Air Quality offset programme • Eskom’s ambient air quality monitoring network shows that there is generally compliance with ambient SO2 and NOx standards, but non-compliance with PM10 and PM2.5 standards on the Mpumalanga Highveld. • There continues to be a challenge for existing plants to meet the new plant standards within the required timelines due to high cost, water use and impact on the electricity tariff. • Eskom has initiated the process of applying for new postponements for the next 5 year period. The detail of what postponements will be requested will be available once Eskom has completed a thorough review. Public meetings for Tutuka power station postponement began in January 2018. For four coal fired power stations, no postponements are expected to be applied for. 7 February 2018 2 Overview Emissions and Ambient Air Quality Trends Current Status of Eskom’s Air Quality Compliance Plan Eskom’s Air Quality Offsets Project Alternative Technologies to Reduce Sulphur dioxide Conclusions 7 February 2018 3 Emission and Ambient Air Quality Trends Yearly (financial year) total tonnages from Eskom: 2012/13 – 2016/7 Total Particulate Emissions (PM) (kt) 235000 90 82.34 80.68 78.92 78.37 80 230000 70 65.13 60 225000 50 40 220000 30 20 215000 10 210000 0 2012/13 2013/14 2014/15 2015/16 2016/17 PM (kt) Electricity produced from Eskom power stations (GWh) 7 February 2018 5 The Eskom roadmap travelled to-date to reduce relative yearly particulate emissions (2012/13 to 2017/18) 0.40 0.35 0.30 0.25 0.20 0.15 0.10 0.05 Relative particulate emission(kg/MWhSO) particulate Relative 0.00 FY2013 FY2014 FY2015 FY2016 FY2017 FY2018 - YTD High load factors coupled with plant availability challenges at a number of stations led to the sustained high emissions between FY2013 to FY2016. The reduced system demand from FY2017 provided for maintenance opportunity to undertake essential repairs at a number of units. This coupled with the start of the retrofit of Grootvlei units 2 to 4 to FFPs plus the completion of refurbishment of the ESP on 4 of the 6 units at Matla resulted in an improving trend. 7 February 2018 6 Monthly emission trends (May 2016 to April 2017): Grootvlei fabric filter plant retrofit More than 10-fold reduction in relative particulate Clean stacks after emissions from Grootvlei Power Station due to fabric filter Grootvlei fabric filter 2.5 plant retrofit plant retrofit 2.0 1.5 out) 1.0 0.5 0.0 Relative particulate emissions (kg/MWhemissions sent particulate Relative 2016 2017 7 Yearly total gaseous emissions from Eskom: 2012/13 – 2016/17 Total Sulphur Dioxide (SO2) (kt) 235000 1975 2000 1950 230000 1900 1843 1834 1850 225000 1766 1800 1750 220000 1699 1700 215000 1650 1600 210000 1550 2012/13 2013/14 2014/15 2015/16 2016/17 SO2 (kt) Electricity produced from Eskom power stations (GWh) Total Nitrogen oxide (NOx ) (kt) as NO2 235000 980 965 954 960 230000 937 940 225000 920 893 900 220000 885 880 215000 860 210000 840 2012/13 2013/14 2014/15 2015/16 2016/17 NOx (kt) Electricity produced from Eskom power stations (GWh) 7 February 2018 8 Ambient Air Quality Eskom’s ambient air quality monitoring network • 18 monitoring stations • Operated by Eskom’s ambient air quality monitoring team in RT&D (except for Edgemead and Mossel Bay) • Network is SANAS-accredited Parameter Compliance status SO2 Compliance at all monitoring stations, except non-compliance with daily limit at Komati and KwaZamokuhle NOx Compliance at all monitoring stations Edgemead Mossel Bay Particulate matter Non-compliance at all monitoring (PM1010 & PM2.5) stations except for Camden and Medupi Five year ambient air quality trends of Sulphur dioxide – Kendal Ambient Monitoring Station 25.0 20.0 15.0 10.0 (ppb) 5.0 Annual Annual 0.0 Concentrations Concentrations 2013 2014 2015 2016 2017 Year Annual Concentration Annual Limit = 19ppb 120 100 80 60 40 Number of of Number Exceedances 20 0 2013 2014 2015 2016 2017 • Ambient SO2 levels below permissible number of exceedances at Kendal site – 5km downwind of Kendal except in 2013 (point of 7 Februaryhighest 2018 concentration) 11 Five year ambient air quality trends of Sulphur dioxide – Marapong Ambient Monitoring Station 20.0 Annual Concentration Annual Limit = 19ppb 15.0 10.0 (ppb) Annual Annual 5.0 Concentration Concentration 0.0 2013 2014 2015 2016 2017 Hourly Exceedances of 134ppb 15 10 5 Number of of Number Exceedances 0 2013 2014 2015 2016 2017 • Ambient SO2 levels below permissible (88) number of exceedances at Marapong – township upwind of both Matimba and Medupi 7 February 2018 12 Three year ambient air quality trends of Sulphur dioxide – Medupi Ambient Monitoring Station 20.0 Annual Concentrations Annual Limit = 19ppb 15.0 10.0 Annual Annual 5.0 Concentration (ppb) Concentration 0.0 2015 2016 2017 Hourly Exceedances of 134ppb 46 44 42 40 38 36 Number of of Number Exceedances 34 32 2015 2016 2017 Years • Ambient SO2 levels below permissible (88) number of exceedances at Medupi site – downwind of both Matimba and Medupi 7 February 2018 13 Current Status of Eskom’s Air Quality Compliance Plan Summary of Eskom’s Air Quality Improvement plan - roadmap towards compliance HFT HFT HFT HFT HFT Completed or high frequency transformer (HFT) installations 7 February 2018 15 Eskom’s emission reductions roadmap towards compliance – Particulate Emissions (PM) Particulate emissions: 63% reduction by 2026 0.40 Completed – 0.35 October 2017 Funds allocated and out on tender 0.30 Delayed Grootvlei FFP Funds allocated and 0.25 contracting strategy in progress 0.20 Potential Delay Tutuka FFP 0.15 Kriel FFP 0.10 Matla, Duvha, Lethabo, Kendal, Matimba refurbs & HFTs 0.05 Duvha HFT approved in Dec 2017. Lethabo HFT out on tender. Improved Relative particulate emissions (kg/MWhSO)emissions particulate Relative precip performance at Matla (units 1&4 ESP refurbishments to be 0.00 completed by 2020 and HFT to be tested in 2018 and implemented 2019 to 22) 7 February 2018 16 Eskom’s emission reductions roadmap towards compliance – Nitrogen Oxides (NOx) NOx emissions: 23% reduction by 2026 4.50 4.00 Funds allocated. Detailed designs completed. 3.50 3.00 Tutuka LNB modfication 2.50 Majuba LNB modfication 2.00 Matla burner replacement 1.50 1.00 Funds allocated. Detailed designs in progress. Relative NOx emissions (kg/MWhSO)emissions NOx Relative 0.50 0.00 7 February 2018 17 Eskom’s emission reductions roadmap towards compliance – Sulphur Dioxide (SO2) SO2 emissions: 18% reduction by 2026 9.00 FGD installed at Kusile as part of construction. Unit 1 8.00 in commercial operation. 7.00 Commissioning of Medupi (and Kusile) 6.00 5.00 Medupi FGD retrofit 4.00 Note: Pre-feasibility study in 3.00 progress for Circulating Potential delay in FGD retrofit: Fluidized Bed desulphurisation Project in place to undertake 2.00 for Kendal power station coal blending so as to reduce (2025/26). spikes in SO2 emissions. Relative SO2 emissions (kg/MWhSO)emissions SO2 Relative 1.00 0.00 7 February 2018 18 Eskom’s Air Quality Offset Programme What can be achieved through offsets? Primary • Improve air quality aim • Local job creation and skills development • Improve communities’ health and quality of life Secondary • Improve relationships with communities aims • Reduce energy poverty • Cost effective channelling of resources • Reduce CO2 emissions 7 February 2018 20 What will Eskom be doing for the offsets? Programme of activities: Household Community Education Projects to emission emission and be reduction reduction awareness considered (Nkangala, (Vaal) for Gert household Sibande) application 217 February 2018 21 Eskom’s air quality offsets journey 2011-2013 2014-2016 2017 2018-2020 2019-2025 In contracting phase roll out Insulation and August 2018 Tested insulation, electricity LPG, clean coal Large-scale stoves, electricity roll-out (at subsidy; electricity Lead least one starter pack implementation settlement (KwaZamokuhle, 30-house per power Ezamokuhle station) – 40 electricity Sharpeville) – pilot 000 5000 households Pilot households projects in Completed KwaZamoku in Dec 2017 hle – 120 Pre- households feasibility study Programme Implementation Project design design plans documents document 7 February 2018 22 Key findings from the electricity pilot study • Houses already have Dirty fuels Exclusive use of cleaner fuels electricity but don’t use it due to perceived high cost to cook and heat with and cultural preferences. • It is feasible to switch Coal / RDP Fuel Electricity Electricity LPG household from coal to Wood Switch electricity but there is a high risk of reverting back to coal due to cultural norms, electricity cost, electricity supply cuts, ability to heat houses in winter. • Hybrid of electricity and gas is proposed: Gas/elec plates, electric.. 7 February 2018 23 Changes to AQO plans (interventions) • Intervention for RDP houses (as per initial plan) • Insulation: Full retrofit (ceilings plus walls) Draft proofing • Fuel switching: Switch households to LPG (swop coal stove for LPG stove and heater). • Proposed intervention for RDP houses (current plan) • Insulation: Basic retrofit (ceilings only) • Fuel switching: Switch Draft households to electricity plus LPG proofing backup (swop coal stove for hybrid gas electric ). Rewiring + CoC 7 February 2018 24 Lead implementation rollout starting in October 2018: Number of houses Estimated rollout schedule – 166 houses/month ramping up to 334 houses/month 7 February 2018 25 Large scale roll-out The offset interventions will be rolled out at least one settlement per power station (of which there are 12), commencing with the baseline determination and planning in 2018, and implementation in 2019/20.
Recommended publications
  • (Special Trip) XXXX WER Yes AANDRUS, Bloemfontein 9300
    Place Name Code Hub Surch Regional A KRIEK (special trip) XXXX WER Yes AANDRUS, Bloemfontein 9300 BFN No AANHOU WEN, Stellenbosch 7600 SSS No ABBOTSDALE 7600 SSS No ABBOTSFORD, East London 5241 ELS No ABBOTSFORD, Johannesburg 2192 JNB No ABBOTSPOORT 0608 PTR Yes ABERDEEN (48 hrs) 6270 PLR Yes ABORETUM 3900 RCB Town Ships No ACACIA PARK 7405 CPT No ACACIAVILLE 3370 LDY Town Ships No ACKERVILLE, Witbank 1035 WIR Town Ships Yes ACORNHOEK 1 3 5 1360 NLR Town Ships Yes ACTIVIA PARK, Elandsfontein 1406 JNB No ACTONVILLE & Ext 2 - Benoni 1501 JNB No ADAMAYVIEW, Klerksdorp 2571 RAN No ADAMS MISSION 4100 DUR No ADCOCK VALE Ext/Uit, Port Elizabeth 6045 PLZ No ADCOCK VALE, Port Elizabeth 6001 PLZ No ADDINGTON, Durban 4001 DUR No ADDNEY 0712 PTR Yes ADDO 2 5 6105 PLR Yes ADELAIDE ( Daily 48 Hrs ) 5760 PLR Yes ADENDORP 6282 PLR Yes AERORAND, Middelburg (Tvl) 1050 WIR Yes AEROTON, Johannesburg 2013 JNB No AFGHANI 2 4 XXXX BTL Town Ships Yes AFGUNS ( Special Trip ) 0534 NYL Town Ships Yes AFRIKASKOP 3 9860 HAR Yes AGAVIA, Krugersdorp 1739 JNB No AGGENEYS (Special trip) 8893 UPI Town Ships Yes AGINCOURT, Nelspruit (Special Trip) 1368 NLR Yes AGISANANG 3 2760 VRR Town Ships Yes AGULHAS (2 4) 7287 OVB Town Ships Yes AHRENS 3507 DBR No AIRDLIN, Sunninghill 2157 JNB No AIRFIELD, Benoni 1501 JNB No AIRFORCE BASE MAKHADO (special trip) 0955 PTR Yes AIRLIE, Constantia Cape Town 7945 CPT No AIRPORT INDUSTRIA, Cape Town 7525 CPT No AKASIA, Potgietersrus 0600 PTR Yes AKASIA, Pretoria 0182 JNB No AKASIAPARK Boxes 7415 CPT No AKASIAPARK, Goodwood 7460 CPT No AKASIAPARKKAMP,
    [Show full text]
  • Overview of the South African Coal Value Chain
    SOUTH AFRICAN COAL ROADMAP OVERVIEW OF THE SOUTH AFRICAN COAL VALUE CHAIN PREPARED AS A BASIS FOR THE DEVELOPMENT OF THE SOUTH AFRICAN COAL ROADMAP OCTOBER 2011 Overview of the South African Coal Value Chain | I Disclaimer: The statements and views of the South African Coal Roadmap are a consensus view of the participants in the development of the roadmap and do not necessarily represent the views of the participating members in their individual capacity. An extensive as reasonably possible range of information was used in compiling the roadmap; all judgments and views expressed in the roadmap are based upon the information available at the time and remain subject to further review. The South African Coal Roadmap does not guarantee the correctness, reliability or completeness of any information, judgments or views included in the roadmap. All forecasts made in this document have been referenced where possible and the use and interpretation of these forecasts and any information, judgments or views contained in the roadmap is entirely the risk of the user. The participants in the compiling of this roadmap will not accept any liability whatsoever in respect of any information contained in the roadmap or any statements, judgments or views expressed as part of the South African Coal Roadmap. SYNTHESIS enables a wide range of stakeholders to discuss the future of the industry. The fact that at this stage in the process Phase The South African Coal Roadmap (SACRM) process I does not provide any clarity on the outlook for the South African coal industry is o"set by the constructive process The need for a Coal Roadmap for South Africa was identi!ed which has been initiated, which augurs well for the successful in 2007 by key role players in the industry, under the auspices development of a South African Coal Roadmap in Phase II.
    [Show full text]
  • Mercury Emissions from South Africa's Coal-Fired Power Stations
    Mercury emissions from South Africa’s coal-fired power stations Belinda L. Garnham*1 and Kristy E. Langerman1 1Eskom Holdings SOC Limited, Megawatt Park, 1Maxwell Drive, Sunninghill, Sandton, [email protected], [email protected] Received: 8 August 2016 - Reviewed: 3 October 2016 - Accepted: 2 November 2016 http://dx.doi.org/10.17159/2410-972X/2016/v26n2a8 Abstract Mercury is a persistent and toxic substance that can be bio-accumulated in the food chain. Natural and anthropogenic sources con- tribute to the mercury emitted in the atmosphere. Eskom’s coal-fired power stations in South Africa contributed just under 93% of the total electricity produced in 2015 (Eskom 2016). Trace amounts of mercury can be found in coal, mostly combined with sulphur, and can be released into the atmosphere upon combustion. Coal-fired electricity generation plants are the highest contributors to mer- cury emissions in South Africa. A major factor affecting the amount of mercury emitted into the atmosphere is the type and efficiency of emission abatement equipment at a power station. Eskom employs particulate emission control technology at all its coal-fired power stations, and new power stations will also have sulphur dioxide abatement technology. A co-beneficial reduction of mercury emissions exists as a result of emission control technology. The amount of mercury emitted from each of Eskom’s coal-fired power stations is calculated, based on the amount of coal burnt and the mercury content in the coal. Emission Reduction Factors (ERF’s) from two sources are taken into consideration to reflect the co-benefit received from the emission control technologies at the stations.
    [Show full text]
  • Cenyu Scoping Report
    EASTERN CAPE DEPARTMENT OF HOUSING Cenyu/ Cenyulands Housing Dev elopment Scoping Report December 2011 J29034A Arcus GIBB (Pty) Ltd Reg. 1992/007139/07 East London Office: 9 Pearce St reet , Berea , East London PROPOSED CENYU/ CENYULANDS HOUSING DEVELOPMENT DRAFT SCOPING REPORT CONTENTS Chapter Description Page 1 INTRODUCTION 1 1.1 Purpose of Report 1 1.2 EIA Process 1 2 PROPOSED ACTIVITY 5 2.1 Location of the proposed activity 5 2.2 Description of Proposed Activity 7 2.3 Roads 9 2.4 Stormwater Drainage 9 2.5 Bulk Water Supply and Reticulation 12 2.6 Sanitation 13 2.7 Motivation for Proposed Activity 13 2.8 Alternatives 13 3 LEGISLATION AND POLICY GUIDELINES CONSIDERED 15 3.1 The Constitution of South Africa (Act No. 108 of 1996) 15 3.2 The National Environmental Management Act (Act 107 of 1998) 15 3.3 Legislation for the Conservation of Natural Resources 17 3.4 Summary of Relevant Legislation 22 4 DESCRIPTION OF THE RECEIVING ENVIRONMENT 24 4.1 Introduction 24 4.2 Physical Environment 24 4.3 Biological Environment 27 4.4 Socio-Economic Environment 31 4.5 Cultural/ Historical sites 32 i 5 DESCRIPTION OF ENVIRONMENTAL ISSUES AND IMPACTS IDENTIFIED 33 5.1 Project activities affecting the environment 33 5.2 Need and Desirability of Project 34 5.3 Biophysical Impacts 35 5.4 Ecological Impacts 36 5.5 Socio-economic Impacts 37 5.6 Cumulative Impacts 37 5.7 Key Issues to be addressed in the EIA Phase 38 6 METHODOLOGY IN ASSESSING IMPACTS 39 6.1 Introduction 39 7 PLAN OF STUDY FOR EIA 42 7.1 Introduction 42 7.2 Key Issues to be addressed in the
    [Show full text]
  • Power Projects in Africa, April 2008 Annual Conference
    Power Projects in Africa EXPORT-IMPORT BANK of the UNITED STATES 2008 Annual Conference April 17 & 18 Each year during the annual conference, the Export-Import Bank of the United States highlights emerging trends and opportunities within Africa. This year, our focus features the energy needs throughout the continent and the opportunities for U.S. exporters and financial institutions in the growing power sector. In order to effectively present these initiatives, the following document has been compiled which provides an overview of several key African markets and their energy requirements. Additionally, a selection of current or proposed power projects in the various countries have been detailed and key contact information listed. The Ex-Im Bank wishes to acknowledge with special appreciation the respective U.S. Missions in Botswana, Egypt, Ghana, Kenya, Morocco, Mozambique, Malawi, Nigeria, Senegal, South Africa, Tanzania, and Uganda as well as the Federal Ministry of Energy of the Government of Nigeria for their contributions in preparing the reports. TABLE OF CONTENTS Botswana............................................................................................................................ 2 Egypt .................................................................................................................................. 6 Gabon............................................................................................................................... 10 Ghana..............................................................................................................................
    [Show full text]
  • Communication of Progress
    United Nations Global Compact Advanced Communication on Progress September 2015 UN Global Compact – Communication of Progress Letter from the chairperson Our overall strategic direction is aligned with the Strategic Intent Statement determined by the shareholder. This includes the strategic objectives of security and reliability of supply of electricity, business and financial sustainability, reduction of our carbon footprint and environmental impact, alignment with Government’s strategic initiatives and driving industrialisation, transformation of the economy and the procurement landscape. The practice of keeping the lights on at all costs by delaying critical maintenance, other essential refurbishment and replacement of generating equipment has caused an escalation in breakdowns of our Generation plant. A short-term Generation recovery strategy has been developed to reduce unplanned maintenance to below 7 000MW (or approximately 16%) by 2015/16 and to less than 4 000MW (approximately 8.8%) by 2021/22. This drive towards predictability and sustainability aims to achieve plant availability of 80% by 2021/22. The delay in delivering on the new build programme has placed additional pressure on the ageing generating plant at a time when there is little spare capacity to do maintenance. Medupi is only expected to be fully operational by 2019, with six units providing total additional capacity of 4 764MW. The six units at Kusile will provide an extra 4 800MW but they are expected to be fully operational only by 2021. The four units of 1 332MW at Ingula Pumped Storage Scheme are anticipated to be fully operational only by 2017. NERSA’s third multi-year price determination of an 8% annual tariff increase has resulted in significant pressure on our liquidity and going concern status.
    [Show full text]
  • Our Preparations for Expansion
    Our Specialist Services After decades of expansion to meet the challenges in infrastructural development and population growth, we are ensuring that we are ready for the demands of 2020 and beyond by focusing on infrastructure refurbishment and development. Our Specialist Services Division focuses on expanding the business of Rand Water outside of our core business of bulk water supply. During the year under review, Specialist Services undertook the following projects: • Ghana Urban Water Management Contract Client: Ghana Water Company Limited (GWCL) Budget: US$103million for 5 years Funder: World Bank Project Duration: June 2006 - June 2011 In December 2004, the Government of the Republic of Ghana issued an invitation for a Bids-Management Contract for the provision of services to the urban water sector in that country. This invitation followed a general notice that Ghana had secured USD 103 million from the International Development Association to fi nance the Project. The intent was to apply part of the grant to a Multi-year Management Contract for the provision of services in the urban water sector. For this project which commenced on the 5 June 2006, Rand Water through our then subsidiary Rand Water Services (Pty) Ltd entered into a joint venture agreement with Vitens (Dutch-based company). 47 • Technical Assistance to the Democratic Republic of the Congo Client: Department of Water Affairs Budget: R22 million Funder: African Renaissance Fund Project Duration: 18 Months (from June 2011) Benefi ciary: REGIDESO The Government of South Africa has continued to strengthen its relationship with the Democratic Republic of the Congo. President Jacob Zuma and a business delegation from South Africa visited the Democratic Republic of the Congo (DRC) in June 2011 for the signing of the Binational Co-orperative agreement between the two countries.
    [Show full text]
  • Rope Access Brochure
    Maintenance Repairs Installations Inspections Committed to Performance Excellence www.sgbcaperopeaccess.co.za www.sgbcaperopeaccess.co.za We are Who We Are Expertise and Experience Count SGB-Cape Rope Access is an operating division of SGB-Cape, one of South Africa’s leading service providers of access scaffolding and industrial access based maintenance such as thermal insulation and corrosion protection. Operating under Waco Africa, SGB-Cape is part of Waco International, a leading equipment rental and industrial services business with operations in Africa, Australasia and the United Kingdom. An Affordable Alternative Our specialist rope access services complement the Group’s traditional scaffolding, mobile elevated work platforms and suspended platforms, offering an affordable alternative to access hard-to-reach locations quickly, efficiently and with minimal disruption. We are experienced in many industry sectors including construction, power, oil and gas, banner signage, industrial maintenance and telecommunications. Regardless of the size or complexity of the job, SGB-Cape Rope Access can provide an affordable solution. Waco Africa is a proud Level 3 BBBEE supplier with 52.14% black ownership. Our Growing Footprint With our operational facilities strategically established throughout South Africa, Zambia, Mozambique, Angola, DRC, Ghana and Namibia, we have developed an infrastructure to cost effectively maintain and support operations in these locales. Our South African neighbouring countries are being serviced on a project base. Front cover: Rope access offshore maintenance A1Thermal Grand Prix insulation seating, installation Durban via rope access What We Do Core Services SGB-Cape Rope Access provides customers with the ability to access hard-to-reach locations quickly, efficiently • Maintenance and with minimal disruption.
    [Show full text]
  • Application for Alternative Limits and Suspension of the Minimum Emissions Standards Compliance Timeframes for the Grootvlei Power Station
    ESKOM APPLICATION FOR ALTERNATIVE LIMITS AND SUSPENSION OF THE MINIMUM EMISSIONS STANDARDS COMPLIANCE TIMEFRAMES FOR THE GROOTVLEI POWER STATION DATE: JUNE 2020 Report reference ESKOM ENV19-R236 rev 2 Grootvlei TABLE OF CONTENTS 1 INTRODUCTION .............................................................................................................................. 4 2 ESKOM’S EMISSION REDUCTION PLAN ...................................................................................... 5 3 ESKOM’S APPROACH TO A JUST ENERGY TRANSITION .......................................................... 7 4 REQUESTED POSTPONEMENT EMISSION LIMITS ..................................................................... 8 5 LEGAL BASIS FOR DECISION-MAKING ...................................................................................... 10 5.1 Regulatory Requirements ....................................................................................................................... 10 5.2 Changes in Regulatory Framework ........................................................................................................ 11 5.3 The Need to Amend Variation Requests ................................................................................................ 11 6 REASONS FOR APPLYING FOR SUSPENSION ......................................................................... 11 6.1 Remaining Power Station Life ................................................................................................................ 12 6.2 Water Availability
    [Show full text]
  • Objection on Behalf of the Life After
    Ms Marissa Botha Environmental Assessment Practitioner Naledzi Environmental Consultants CC By email: [email protected] Copied to: Mr Moegamat Ishaam Abader Dr Thulie Khumalo Acting Director General National Air Quality Officer Department of Environment, Forestry and Fisheries Department of Environment, Forestry and Fisheries By email: [email protected] By email: [email protected] Mr Olebogeng Matshediso Mr Dan Hlanyane Deputy-Director: Atmospheric Policy, Norms and Standards Gert Sibande District Municipality Department of Environment, Forestry and Fisheries By email: [email protected] By email: [email protected] Ms Mpho Nembilwi Pollution Control and Environmental Division Nkangala District Municipality By email: [email protected] 30 July 2020 Dear Ms Botha WRITTEN OBJECTIONS TO ESKOM’S APPLICATION FOR A ONCE-OFF SUSPENSION OF COMPLIANCE WITH THE NEW PLANT MINIMUM EMISSION STANDARDS AND VARIATION REQUEST FOR THE GROOTVLEI POWER STATION 1. We address you, again, as the Life After Coal campaign, a joint campaign by the Centre for Environmental Rights (CER), groundWork (gW), and Earthlife Africa Johannesburg (ELA). We also address you on behalf of the Highveld Environmental Justice Network (HEJN), Vukani Environmental Justice Movement in Action (VEJMA), and the Vaal Environmental Justice Alliance (VEJA). CER, groundWork, Earthlife Africa, HEJN, VEJMA, and VEJA are all interested and affected parties (I&APs) in relation to Eskom’s multiple rolling applications for suspension, alternative limits and/or postponement of compliance with the minimum emission standards (MES), across its fleet of coal-fired and gas-fired power stations. 2. Upfront, we point out that this is Eskom’s 6th round of applications for MES leniency in relation to its coal-fired power stations.
    [Show full text]
  • Economic Impact Assessment of Grootvlei Power Station
    as Economic Impact Assessment of Grootvlei Power Station Eskom Holdings SOC Ltd. 07 July 2017 1 Disclaimer This report has been prepared by KPMG Services (Pty) Ltd (“KPMG”) exclusively for the benefit, information use of ESKOM for the exclusive purposes of/in order to assist ESKOM to estimate the socio-economic impact of the coal power station’s capital and operational expenditure between 2014/15 to 2016/17. KPMG has been informed and requested by ESKOM that this report may be published, as well as shared individually with third parties. Notwithstanding the provisions of the Engagement Letter and Terms and Conditions, KPMG is willing to give its consent for ESKOM to do so on the following basis: . KPMG accepts no liability to any third party in connection with the Services; and . KPMG does not have a duty of care or any legal obligation to any third party in connection with the Services. 2 Glossary CPI Consumer Price Index CSR Corporate Social Responsibility DoE Department of Energy EIA Economic Impact Assessment EIUG Energy Intensive Users Group EUF Energy Utilisation Factor FBE Free Basic Electricity GHG Greenhouse Gases GDP Gross Domestic Product GOS Gross Operating Surplus GWh Gigawatt hours GVA Gross Value Added IEP Integrated Energy Plan I-O Input-Output IRP Integrated Resource Plan ISO International Organisation Standards LTIR Loss Time Injury Rate MW Megawatts NDP National Development Plan NOSA National Occupational Safety Association OECD Organisation for Economic Co-operation and Development OHSAS Occupational Health and Safety
    [Show full text]
  • Annual Report 2009 Sunninghill 2000 Annual Report 2009 Annual Report Sandton 2157
    Contact information Telephone Websites and email Eskom head offi ce: +27 11 800 8111 Eskom website: www.eskom.co.za Eskom Group Communications: +27 11 800 2323 Eskom environmental: [email protected] Eskom Development Foundation: +27 11 800 2758 Eskom annual report: www.eskom.co.za/annreport09/ Eskom Development Foundation: www.eskom.co.za/csi Ethics offi ce advisory service: +27 11 800 2791/3187 or [email protected] Confi dential fax line: +27 11 507 6358 Physical address Postal address Eskom Eskom Megawatt Park PO Box 1091 Maxwell Drive Johannesburg Annual Report 2009 Sunninghill 2000 Annual ReportAnnual 2009 Sandton 2157 Eskom Holdings Secretariat N Msomi (Company Secretary) Megawatt Park PO Box 1091 Johannesburg 2000 www.eskom.co.za Empowering the South African dream BASTION GRAPHICS Artist’s impression of the new Moses Mabhida Stadium courtesy of Mediaclubsouthafrica.com Contact information Telephone Websites and email Eskom head offi ce: +27 11 800 8111 Eskom website: www.eskom.co.za Eskom Group Communications: +27 11 800 2323 Eskom environmental: [email protected] Eskom Development Foundation: +27 11 800 2758 Eskom annual report: www.eskom.co.za/annreport09/ Eskom Development Foundation: www.eskom.co.za/csi Ethics offi ce advisory service: +27 11 800 2791/3187 or [email protected] Confi dential fax line: +27 11 507 6358 Physical address Postal address Eskom Eskom Megawatt Park PO Box 1091 Maxwell Drive Johannesburg Annual Report 2009 Sunninghill 2000 Annual ReportAnnual 2009 Sandton 2157 Eskom Holdings Secretariat N Msomi (Company
    [Show full text]