Newark Bay Bridge Reconstruction

Total Page:16

File Type:pdf, Size:1020Kb

Newark Bay Bridge Reconstruction NEWARK BAY BRIDGE RECONSTRUCTION New Jersey Turnpike Authority Contract: T100.034 Newark Bay Bridge Deck Reconstruction and Miscellaneous Structural, Roadway, and Lighting Improvements Overview of Project • Officially Named the “Vincent R. Casciano Memorial Bridge” • Opened to Traffic April 4, 1956 • Three Span Thru Arch Truss Main Span • Girder/Floor Beam Approaches • Total Length = 9,560 ft • Main Span = 1,270 ft • Re-decking Limits = 7,357 ft • AADT = 65,000 • Additional Traffic Due to Pulaski Skyway = ORGANIZATION CHART New Jersey Turnpike Authority Ammann & Whitney URS Ferreira/Tutor-Perini Construction Oversight Design Engineer Joint Venture (FTP JV) Fort Miller Co, Inc. Precast Supplier SEQUENCE OF OPERATIONS • Constructability Review – RFI Process • Demolition of Existing Structure • Miscellaneous Steel Repairs Throughout Structure • Painting & Prep of Existing Steel • Installation of Shear Studs and Haunch Angles • Receive and Set Panels/Grout Panels • Installation of New Scuppers • Installation of New Expansion Joints/Joint Closure Pours with HPC • Installation of New HPC Cast in Place Parapet/Precast HPC Median Barrier • Installation of New LED Lighting • Milling/Diamond Grinding of New Deck • Transverse Sawcut Grooving • Installation of the Lane Control System due to the Pulaski Skyway Reconstruction • Return Traffic back to Pre-Construction Conditions SCHEDULE • Original Milestone Dates • Pre-Stage – October 27, 2010 • Stage I – July 15, 2011 • Stage II – June 1, 2012 • Stage III – June 3, 2013 • Stage IV – August 26, 2013 – Final Completion • Revised Milestone Dates as of CPM Update #10 • Pre-Stage – December 8, 2010 (Expanded Scope) • Stage I – December 29, 2011 • Stage II – September 12, 2012 • Stage III – September 30, 2013 • Stage IV – November 1, 2013 • Completion of LCS – January 14, 2014 – Additional Work • Completion of Security Fence – May 2014 – Additional Work STAGED CONSTRUCTION DEMOLITION • The JV Milled the Existing Roadway to Separate Asphalt from the Concrete • Concrete Deck Sawcut into Sections and Removed by Excavator • Slabs Placed Directly into Dumpsters and Properly Disposed • Concrete Median Barrier was Munched by Machine and Debris Removed by Hand • Scuppers and Joints Removed and Disposed of • Protection of Fiber Optic Line CONSTRUCTABILITY REVIEW – RFI PROCESS • Constructability Issues Arose During Shop Drawing Submittal Process for the Precast Panels • The Design Attempted to Minimize Joint Widths & Grout Pocket Size Due to the Excessive Cost of the MMA Grout • During a Meeting with the NJTA Designers and the NJTA Construction Teams, Fort Miller Demonstrated the Difficulty in Working with the Proposed Connections • The Design was More Stringent that Allowable PCI Standards CONSTRUCTABILITY REVIEW • Mock-ups – Very Important to the Process – Included Full Size Panel Assembly – FTP JV was Required to Grout One Transverse Joint and One Longitudinal Joint – Cores Were Taken to Evaluate Consolidation • Design Changes – Pocket Size Increased – Elimination of Pre-Stress Tension Bars – Maximum Extension of Pea Gravel Reduced STEEL REPAIRS • Lateral Bracing was Severely Damaged by Corrosion and Vibration of Bridge – Bolts were Worn Down to Nubs • East Abutment Bearings were Corroded and Extended • Gusset Plates from Floor Beams to Girders were Cracked and Severely Corroded • Tie Chord Plates in the Navigable Water Way are Corroded and Require Replacement STEEL REPAIRS REMOVE AND REPAINT TOP FLANGE • The Joint Venture Removed the Lead Based Paint within Full Containment • The Joint Venture Placed One Coat of Epoxy Primer, a Minimum of 4 mils SHEAR STUDS • Over 200,000 Shear Studs to Layout and Coordinate with the Precast Panel Pockets • There is a Minimum of 1” Penetration Embedment Length and a Maximum of 3” Into the Shear Stud Pocket RECEIVE AND SET PANELS • The Joint Venture is using a Gantry System for Stage I Erection of the Precast Panels • The Precast Panels are Shipped from Saratoga, NY with the Understanding that the Supplier Meets the Necessary Height and Width Restrictions to Travel Without an Escort TYPICAL JOINT POCKETS GROUT PANELS • The Specified Grout is a Two Component System, a Powder Mixture and a Liquid Polymer. • BASF Allows a Clean, Dry 3/8 inch Pea Gravel as an Extender. The Pea Gravel Does Not Affect the Chemical Reaction Between the Two Components. GROUT OPERATIONS • Grout Installation was Performed Mainly at Night Due to Lane Closing Restrictions and Access • Labor Intensive Operation • Grout Had to be Placed Under Pressure, the Product was not Free-flowing as Specified ADDITIONAL HIGHLIGHTS • Two Spans Used Exclusively Stainless Steel Reinforcing • 202 New Scupper/Fiberglass Downspouts – Openings cast into the precast panels – Lesson Learned, Minor Cracking in the Corner Openings, Better Result in Stage III with Corners Skewed • Installation of New Expansion Joints – Three Types of Joints Installed, Standard, Modular & Relief • Closure Pours at Joint Locations – Cast in Place HPC Between the Expansion Joints and the Precast Panels • Cast In Place HPC Parapets • Precast Median Barrier – Bolted and Grouted into Place for Removal for Next Contract LED LIGHTING • Original Bid Luminaire Was HP Sodium • Issued by NJTA in March 2012 • One of the First Projects to Use LED Lighting • Hapco Light Pole – New Dampener Designed due to Excessive Vibrations on NJTA Structures MICRO-MILLING OF PRECAST DECK • Fort Miller Manufactured the Precast Slabs with an Additional ¼” of HPC Concrete • The Micro-milling Leveled the Longitudinal and Transverse Joints Along with Imperfections with the Precasting TRANSVERSE SAWCUT • Transverse Saw Cutting is Difficult Using Staged Construction • Longitudinal Saw Cutting May Have Been More Appropriate for a Quieter Ride NEW LANE CONTROL SYSTEM • Due to the Reconstruction of the Pulaski Skyway, Additional Roadway Repair Work was Completed • Also, a Lane Control System was Developed for the Eastbound Right Shoulder of the Hudson County Extension Allowing Traffic to Utilize the Area • There will be an Expected Increase of 2000 Vehicles per Peak Hour NEW LANE CONTROL SYSTEM • NEW LCS Included – Eleven New LED Signs that will Display • Down, Green Arrow – Displayed When Patrons can Legally Travel Shoulder • 45 Degree Down, Yellow Arrow – Utilized while Closing the Shoulder to Patrons • A Red “X” when not in use, Except for Emergencies – Two Static Informational Signs – To Be Used During Morning and Afternoon Peak Periods RETURN TRAFFIC TO ORIGINAL CONFIGURATION • Remove LCS System and Return Traffic to Two Lanes in Each Direction for the Entire Length of the Hudson County Extension .
Recommended publications
  • Lower Passaic River Restoration Project and Newark Bay Study
    Lower Passaic River Restoration Project and Newark Bay Study r.'l"r.'' ~ u.s. FISH & WILDLIFE SERVICE ~ LowerLower PassaicPassaic RiverRiver RestorationRestoration ProjectProject andand NewarkNewark BayBay StudyStudy Community Involvement Plan June 2006 PREPARED BY: Malcolm Pirnie, Inc. 104 Corporate Park Drive White Plains, NY 10602 FOR: US Environmental Protection Agency Region 2 US Army Corps of Engineers Kansas City District Contract No. DACW41-02-D-0003 Community Involvement Plan Lower Passaic River Restoration Project / Newark Bay Study Community Involvement Plan (CIP) Preface We are pleased to release this Community Involvement Plan (CIP) for the Lower Passaic River Restoration Project / Newark Bay Study. The partner agencies are committed to active and open public involvement throughout the life of this project. This CIP provides a toolbox of options for keeping the public informed and for soliciting input. Each respective agency has its own set of guidance with regard to public involvement. This CIP does not attempt to capture every possible outreach initiative among all six partner agencies or fit one specific CIP template. This CIP is divided into two parts to enable the reader to go directly to the sections of greatest interest, and also contains charts and graphics to enable the reader to see at a glance project activities and opportunities for public involvement. Part One includes the following: 1.1 Overview: discusses the purpose and scope of the CIP, as well as legal authorities. 1.2 Project Background: outlines the problems being addressed by the project and describes the project areas and the unique federal-state partnership that is supporting the Lower Passaic River Restoration Project.
    [Show full text]
  • I. Goals and Objectives Ii. Land Use Plan
    I. GOALS AND OBJECTIVES GOALS ........................................................................................................................................................ I-2 OBJECTIVES .............................................................................................................................................. I-3 Land Use ................................................................................................................................................. I-3 Housing.................................................................................................................................................... I-7 Circulation ................................................................................................................................................ I-8 Economic Development ......................................................................................................................... I-10 Utilities ................................................................................................................................................... I-11 Conservation ......................................................................................................................................... I-12 Community Facilities ............................................................................................................................. I-13 Parks and Recreation ...........................................................................................................................
    [Show full text]
  • New Jersey Statewide FREIGHT PLAN %FDFNCFS
    New Jersey Statewide FREIGHT PLAN %FDFNCFS Table of CONTENTS Any opinions, findings, and conclusions or recommendations expressed in this publication are those of the Author(s) and do not necessarily reflect the view of the Federal Highway Administration. New Jersey Statewide FREIGHT PLAN Page left blank intentionally. Table of CONTENTS Acknowledgements The New Jersey Department of Transportation’s Division of Multimodal Services thanks the many organizations and individuals for their time and contribution in making this document possible. New Jersey Department of Transportation Nicole Minutoli Paul Truban Genevieve Clifton Himanshu Patel Andrew Ludasi New Jersey Freight Advisory Committee Calvin Edghill, FHWA Keith Skilton, FHWA Anne Strauss-Wieder, NJTPA Jakub Rowinski, NJTPA Ted Dahlburg, DVRPC Mike Ruane, DVRPC Bill Schiavi, SJTPO David Heller, SJTPO Steve Brown, PANYNJ Victoria Farr, PANYNJ Stephanie Molden, PANYNJ Alan Kearns, NJ TRANSIT Steve Mazur, SJTA Rodney Oglesby, CSX Rick Crawford, Norfolk Southern Michael Fesen, Norfolk Southern Jocelyn Hill, Conrail Adam Baginski, Conrail Kelvin MacKavanagh, New Jersey Short Line Railroad Association Brian Hare, Pennsylvania Department of Transportation David Rosenberg, New York State Department of Transportation Consultant Team Jennifer Grenier, WSP Stephen Chiaramonte, WSP Alan Meyers, WSP Carlos Bastida, WSP Joseph Bryan, WSP Sebastian Guerrero, WSP Debbie Hartman, WSP Ruchi Shrivastava, WSP Reed Sibley, WSP Scudder Smith, WSP Scott Parker, Jacobs Engineering Jayne Yost, Jacobs Engineering
    [Show full text]
  • Global Terminal, in Bayonne, New Jersey, Has One Clear Advantage
    The New Yorker: PRINTABLES Page 1 of 14 WATCHING THE WATERFRONT by WILLIAM FINNEGAN Mobsters, terrorists, and the docks of New York Harbor. Issue of 2006-06-19 Posted 2006-06-12 Global Terminal, in Bayonne, New Jersey, has one clear advantage over most of its competitors for container-ship business in New York Harbor: it’s a straight shot from the Narrows, the harbor’s entrance. From Global’s wharf to Ambrose Seabuoy, out in the Atlantic, where arriving ships meet the pilots, the distance is only fourteen miles. Maurice Byan, the president of Global, told me that ships ca save four hours by docking at his pier, which looks across at lower Manhattan, rather than turning wes and going through the Kill Van Kull and up into Newark Bay, where the biggest container terminals ar in Port Newark and Elizabeth, or to Howland Hook, on the western shore of Staten Island. Also, ships that dock at Global don’t need to pass under the Bayonne Bridge, which is becoming a problem as container ships grow ever larger. Last year, a freighter had to remove its radio towers to make it. Global, at a hundred acres, is a relatively small terminal, but it’s busy. Byan took me on a tour of the pier in his pickup truck, navigating between walls of containers and dodging big, fast-moving equipment—forklifts, bladed stackers, top loaders, and huge rubber-tired gantries, six stories high. “Empty field!” Byan yelled, pointing at some tall piles of multicolored containers, each one eight feet wide by eight feet high and forty feet long, with “CHINA SHIPPING” and “HANJIN” and “P & O NEDLLOYD painted on the sides.
    [Show full text]
  • COMMUNITY INVOLVEMENT PLAN for the LOWER PASSAIC RIVER
    COMMUNITY INVOLVEMENT PLAN for the LOWER PASSAIC RIVER JULY 2017 COMMUNITY INVOLVEMENT PLAN for the LOWER PASSAIC RIVER JULY 2017 Prepared by: LOUIS BERGER 412 MOUNT KEMBLE AVENUE MORRISTOWN, NJ 07962-1946 +1.973.407.1000 TABLE OF CONTENTS TABLE OF CONTENTS ............ IV COMMUNITY FEEDBACK .......... 20 INTRODUCTION ................. 2 3.1 Highlights of Community Involvement to Date .................20 OVERVIEW 4 3.2 Timeline of Major Community 1.1 Purpose of the Community Involvement Activities ................21 Involvement Plan ....................4 3.3 Overview of 2016 Community 1.2 Scope of the Community Interview Process ...................22 Involvement Plan ....................5 3.4 Key Community Concerns . .22 1.3 Agency Partnerships and 3.4.1 Superfund Cleanup Activity Concerns 22 Legal Authorities.....................6 3.4.2 Redevelopment and River Access Concerns 23 PROJECT BACKGROUND.......... 8 3.4.3 Health and Quality of Life Concerns 23 3.4.4 Outreach Concerns and Suggestions 23 2.1 History of Contamination ..............8 2.2 Description of Project Area.............10 2.3 Project Activities.....................12 COMMUNITY PROFILE ............ 24 2.4 The Cleanup Plan for the Lower 8.3 Miles 14 4.1 Land Use Characteristics and 2.5 Next Steps .........................15 Infrastructure .......................24 4.1.1 Redevelopment 25 2.6 Remedial Design (RD) and Remedial Action (RA) .................16 4.1.2 Transportation Infrastructure 25 2.7 Long-term Monitoring and Maintenance ..18 4.1.3 Drinking Water, Sewers and Power 25 4.1.4 Flood Control 26 2.8 Local Workforce Participation During Construction ......19 4.1.5 Recreation 26 4.2 Population and Demographics..........26 4.2.1 Population 27 4.2.2 Age 27 4.2.3 Household Income 27 4.2.4 Race and Ethnicity 28 4.2.5 Immigrant and Minority Population and Linguistic Trends 28 4.2.6 Environmental Justice 29 4.2.7 Education 29 IV COMMUNITY INVOLVEMENT PLAN FOR THE LOWER PASSAIC RIVER COMMUNITY INVOLVEMENT 5.2.14 Public Meetings and ACTION PLAN..................
    [Show full text]
  • INFORMATION Sandy Hook Pilots
    INFORMATION Sandy Hook Pilots 2015 Tide Tables NOTICE THIS PUBLICATION CONTAINS TIDE AND/OR TIDAL CURRENT PREDICTIONS AND ASSOCIATED INFORMATION PRODUCED BY ANDOBTAINED FROM THE DEPARTMENT OFCOMMERCE, NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION (NOAA), NATIONAL OCEAN SERVICE. THESE PREDICTIONS ARE RECEIVED PRIOR TO OCTOBER OF THE PREVIOUS YEAR AND ARE SUBJECT TO REVISION BY NOAA WITHOUT NOTICE. TIDES MAY VARY WITH WEATHER CONDITIONS. ALL OTHER INFORMATION CONTAINED IN THIS PUBLICATION IS OBTAINED FROM SOURCES BELIEVED TO BE RELIABLE. WE DISCLAIM LIABILITY FOR ANY MISTAKES OR OMISSIONS IN ANY OF THE INFORMATION CONTAINED HEREIN. THE TIME OF TIDES SET FORTH IN THESE TABLES IS GIVEN AT EASTERN STANDARD TIME. PLEASE NOTE: SLACK WATER TIMES ARE AN ESTIMATE BASED ON PILOT OBSERVATIONS AND THEIR ACCURACY CANNOT BE GUARANTEED. Compliments of THE UNITED NEW YORK SANDY HOOK PILOTS BENEVOLENT ASSOCIATION and THE UNITED NEW JERSEY SANDY HOOK PILOTS BENEVOLENT ASSOCIATION 201 Edgewater Street Staten Island, N.Y. 10305 www.sandyhookpilots.com Masters or Agents are requested to advise Pilots of any change in arrival time 12 hours in advance. New York Pilots ........................................... 718.448.3900 New Jersey Pilots .......................................... 718.448.3900 Hell Gate Pilots ............................................. 718.448.3900 Long Island Sound Pilots .............................718.448.3900 Hudson River Pilots ......................................718.815.4316 Dispatch Email ........... [email protected]
    [Show full text]
  • Newark Bay Complex
    Newark Bay Complex WATERBODY SPECIFIC Including Newark Bay, tidal Hackensack River, Arthur Kill, Kill Van Kull and all tidal tributaries WATER BODY SPECIFIC ADVISORIES Fish Identification Species General Population High Risk Population EAT NO MORE THAN: EAT NO MORE THAN: Blue Crab* Do not Harvest or Eat 5 Do not Harvest or Eat 5 Striped Bass* Four meals per year Do Not Eat White Perch Do Not Eat Four meals per year White Catfish One meal per year Do Not Eat American Eel Four meals per year Do Not Eat Bluefish One meal per month Do Not Eat Summer Flounder One meal per month Do Not Eat Atlantic Needlefish One meal per month Do Not Eat Rainbow Smelt One meal per month Do Not Eat Gizzard Shad Do Not Eat Do Not Eat STATEWIDE FRESHWATER ADVISORIES General Population High-Risk Individuals Species Eat No More Than Eat No More Than Trout - (Brown, Brook Rainbow and Hybrid) One meal per week One meal per week Smallmouth Bass One meal per week One meal per month Chain Pickerel One meal per week One meal per month Sunfish (pumpkinseed and redbreast) No restrictions One meal per week Brown Bullhead No restrictions One meal per month Yellow Bullhead No restrictions One meal per month Common Carp One meal per month Do Not Eat ** Important Consumption Reminders ** (1) High-Risk Individuals include infants, children, pregnant women, nursing mothers and women of childbearing age. (2) One meal is defined as an eight-ounce serving (3) Eat only the fillet portions of the fish. Use proper trimming techniques to remove fat, and cooking methods that allow juices to drain from the fish (e.g., baking broiling, frying or grilling, and steaming).
    [Show full text]
  • New Jersey Turnpike Authority ADMINISTRATION BUILDING P.O
    1998 Annual New Jersey Report Turnpike Authority Frank X. McDermott Nancy H. Becker Raymond M. Pocino Chairman Vice Chair Treasurer Joseph P. (J.P.) Miele Jerome P. Amedeo James Weinstein Commissioner Commissioner Commissioner NJDOT Lawrence F. Pat Kramer Edward Gross Diane Scaccetti Commissioner Executive Director Deputy Executive Director From Sept. 1994 to Nov. 1998 Staff Consultants Ralph J. Bruzzichesi, Director of Technology & Admin. Services Riker Danzig Scherer Hyland & Perretti William J. Burke, Director of Toll Collection General Counsel Randy Corman, Director of Law HNTB Corporation Robert F. Dale, Director of Operations Gene ral Consulting Engineer Lynn M. Fleeger, Acting Director of Communications/ Paulus, Sokolowski & Sartor Chief Information Officer Gene ral Environmental Consultant Mary-Elizabeth Garrity, Director of Human Resources KPMGLLP John G. Kunna, Chief Engineer Auditor Catherine A. Schladebeck, Director of Finance & Budgets Wilbur Smith Associates David L. Wingerter, Director of Maintenance Traffic & Revenue Consultant New Jersey Turnpike Authority ADMINISTRATION BUILDING P.O. BOX 1121 NEW BRUNSWICK, NEW JERSEY 08903 (732) 247-0900 COMMISSIONERS FRANK X. McDERMOTT, Chairman NANCY H. BECKER, Vice Chair RAYMOND M. POCINO, Treasurer JOSEPH (J.P.) MIELE JEROME P. AMEDEO JAMES WEINSTEIN EXECUTIVE DIRECTOR EDWARD GROSS To the Honorable Christine Todd Whitman, Governor and the Members of the New Jersey Legislature: It is my privilege to submit to you the 1998 Annual Report of the New Jersey Turnpike Authority. In 1998, the New Jersey Turnpike moved a record 209,408,270 vehicles almost 5,000,000,000 miles. Patrons including business and industry, commuters, residents and tourists, traveled safely and efficiently over 148 miles of roadway.
    [Show full text]
  • Newark Bay Study Underway Project Update
    NEWARK BAY STUDY UNDERWAY PROJECT UPDATE Newark Bay Study - Diamond Alkali Superfund Site Summer 2005 Field Work Scheduled to Begin Fall 2005 Tackling the Problems In 2004, the U.S. Environmental Protection Agency (EPA) signed an In the early 1980’s, EPA found soil agreement with Occidental Chemical Corporation to study Newark Bay under contaminated with dioxin at Diamond the authorities of the federal Superfund program. A multi-year remedial investigation/feasibility study is being conducted by Tierra Solutions, Alkali Company – a former pesticides Inc. with EPA oversight. Tierra Solutions, Inc. is performing the work for manufacturing site located on the Lower Occidental Chemical Corporation. This study will assess the nature and Passaic River in Newark. EPA added extent of contamination in the Newark Bay area and develop cleanup plans to the Diamond Alkali site to its Superfund address those problems, as necessary. The Newark Bay study area includes Newark Bay and portions of the Hackensack River, the Arthur Kill and the Kill National Priorities List in 1984, Van Kull. making it eligible for federal cleanup funds under the Superfund program. Tierra Solutions, Inc. has submitted a work plan for the investigation to EPA for review. EPA is currently working with Tierra Solutions, Inc. and various Dioxin, pesticides and other hazardous other government agencies and interested parties to refi ne this work plan substances were found in sediment with the expectation of starting sediment sampling and other fi eld work samples taken from the Passaic in fall 2005. Once fi nalized, this work plan will be made available at local information repositories.
    [Show full text]
  • New York & New Jersey Harbor Navigation Channel
    NEW YORK & NEW JERSEY HARBOR NAVIGATION CHANNEL DEEPENING A Project Manager’s Perspective Bryce Wisemiller Project Manager U.S. Army Corps of Engineers New York District US Army Corps of Engineers New York District BUILDING STRONG® BUILDING STRONG® Channel Deepening in the Port of NY & NJ Newark Bay Port Jersey Arthur Kill Kill Van Kull 2 BUILDING STRONG® Deepening Project’s Costs $1,800,000,000 $1,600,000,000 $1,400,000,000 $1,200,000,000 $1,000,000,000 $800,000,000 $600,000,000 $400,000,000 $200,000,000 $- Kill Van Kull & Kill Van Kull & Port Jersey Arthur Kill NY/NJ Harbor Newark Bay Newark Bay Channel (41 ft.) Channel (41/40 Deepening Channel Project Project Phase 2 ft.) Project (50 ft.) - Phase 1 (40 ft.) (45 ft.) Original Estimated Total Cost Actual Total Cost 3 BUILDING STRONG® NY/NJ Harbor 50 ft. Deepening Contracts Anchorage Newark Bay Port Jersey Arthur Kill Ambrose Kill Van Kull 4 BUILDING STRONG® Notable Project Features . Geologically Varied & Challenging . Bedrock Drilling & Blasting Operations . Wetland & Air Mitigation . Beneficial Use of Dredged Material . Environmental Monitoring – benthic, suspended sediment from dredging & other sources . Utility Protection Features in Port Jersey Channel 5 BUILDING STRONG® Surficially Geologically Varied & Challenging . Surficial Holocene Sediments vary greatly physically, chemically and biologically . Predominantly sandy material from the Lower Bay was directly suitable for remediation material at the HARS or for beneficial use (e.g., marsh restoration) . Siltier material from inner harbor areas oftentimes not suitable for placement at HARS due to exposure to historic contamination . Non-HARS suitable material was either beneficially used in remediating upland impacted sites in the region or, when necessary, disposed in the Newark Bay Confined Disposal Facility (NBCDF) owned & operated by the Port Authority of NY & NJ 6 BUILDING STRONG® What is the HARS? .
    [Show full text]
  • The Port of New York & New Jersey a Leading Indicator of Globalization
    The Port of New York & New Jersey A Leading Indicator of Globalization Transportation Research Forum Plenary Session March 23, 2006 R.M. Larrabee Director – Port Commerce Department Port Authority of New York & New Jersey The Port Authority of New York & New Jersey Responsible for Airports Tunnels & Bridges PATH Port of NY & NJ World Trade Center Site Established in 1921 by an act of US Congress Financially self-supporting through user fees and bond issues. Board of Commissioners chosen by Governors of NY(6) and NJ(6) International Trade Increases World Trade’s Contribution to 30% U.S. Gross Domestic Product 25% 20% 15% 10% 5% 0% Source:1 U.S.9 8Bureau2 1996 Dollars of Labor19 9Statistics2 2002 2012 Imports Ex por ts Historic Pattern of Growth 25% 20% Gross Domestic Product vs. Import Growth 15% 10% 5% 0% 1995 1996 1997 1998 1999 2000 GDP Grow2001 th 2002 2003 2004 Import Grow th Growth in Trade with Asia 25 20 15 10 Million TEU 5 0 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 Total Asia Europe Northeast USA is the Largest Consumer Market Impact on the Port of New York and New Jersey Landbridge 10-State Market Area Algeciras New York/New Jersey GioaTauro Los ANgeles Kobe Jiddah Hong Kong Kaohsiung Colombo Singapore Port of NY/NJ Containers and Total TEUs, 1991 - 2004 4,500,000 4,000,000 4,478,480 3,500,000 4,067,811 Containers TEUs 3,000,000 3,749,014 3,316,276 2,500,000 3,050,746 2,828,878 2,000,000 2,620,113 2,465,993 2,456,886 2,382,639 2,262,792 2,269,145 1,500,000 2,200,922 1,972,692 2,014,052 1,953,006 2,033,879 1,865,471 1,828,636
    [Show full text]
  • Sediment, Sedimentation, and Environments of the Lower Hackensack River and Newark Bay Estuary Complex
    Proceedings, WEDA XXXI Technical Conference & TAMU 42 Dredging Seminar SEDIMENT, SEDIMENTATION, AND ENVIRONMENTS OF THE LOWER HACKENSACK RIVER AND NEWARK BAY ESTUARY COMPLEX W. Murphy III1, W.B. Ward1, B. Boyd1, W. Murphy IV1, R. Nolen-Hoeksema1, M. Art1, D.A. Rosales-R1 ABSTRACT The Meadowlands, the lower Hackensack River, and Newark Bay in New Jersey form a connected estuarine system that is an important asset for the greater New York City metropolitan region because of its economic, environmental, and recreational value. The Corps of Engineers is deepening Newark Bay and at the same time initiating enhancements under the Hudson-Raritan Estuary Ecosystem Restoration Study. e4sciences|Earthworks LLC has produced sediment and ecological maps of Newark Bay and the lower 22 kilometers (14 miles) of the Hackensack River, which includes the Meadowlands. The accuracy is ±0.3m (±1ft). The fundamental concept is that different sediment deposits have distinctive measurable properties and behavior. On this basis, we can map, quantify, and characterize the deposits. The maps form the basis of targeted coring and testing as opposed to more expensive random testing. The mapping program included sub-bottom seismic profiling, orthosonography, multibeam bathymetry, magnetometry, digital photography, aerial photography, cores, sediment profile imagery, morphology, stratigraphy, sedimentation, biological data, and benthos. The geophysical methods imaged the water-bottom morphology and subsurface stratigraphy to 30.5 meters (100 feet) depth with 0.6-meter (2-foot) spatial resolution. Keywords: Dredging, beneficial uses, slurry transport, dredged material disposal, partially oil-saturated sediment. INTRODUCTION The Hudson-Raritan Estuary of New York and New Jersey is one of the largest estuaries on the East Coast of the United States.
    [Show full text]