DISTRICT LOCAL HIGHWAY PANEL Approved Works Programme - 2017/18

At the September 2017 meeting of the Local Highways Panel (LHP) the Panel made some scheme prioritisation recommendations suggestions from both Approved Works Programme – Rolling Programme. It is envisaged that the 2018/19 Capital Budget for the Maldon District LHP will be the same as that in 2017/18, though this will be finalised by ECC at their full Council meeting in February 2018. The Panel are now asked to finalise their scheme funding recommendations for the schemes they wish to see delivered in 2018/19 from their previous Rolling Programme prioritisations and the schemes on the Potential Schemes List.

Members are reminded that the costs supplied are estimates only and there is the possibility that a final scheme cost could change significantly dependant on issues which may arise especially during detailed design and construction. The estimated scheme costs on the Rolling Programme/Potential Scheme List have been reviewed and adjusted as necessary to reflect this. At this stage we have not been notified of the Safer Roads schemes that will need to be progressed within the District in 2018/19. Our Safer Roads team are currently preparing their 2018/19 programme with a view to finalising it by the end of January 2018.

The 2018/19 Maldon District LHP Capital Budget Summary is as follows –

Budget Summary 2018/19

Ref. Item Amount

1 Expected 2018/19 Capital Budget £200,000

3 Rolling Programme Scheme Priorities £69,000

2 Safer Roads Schemes TBC

3 Feasibility Studies & Detailed Designs TBC

4 2018/19 Capital Budget still to allocate £131,000

Page 1 of 6 MALDON DISTRICT LOCAL HIGHWAY PANEL Approved Works Programme - 2017/18

Blank Page

Page 2 of 6 Maldon District Local Highway Panel - Approved Works Programme 2017/18

Schemes Key Completed Cancelled Update

Scheme Ref Cost Code Scheme Parish Finish Works Description Allocated Budget Comments Category

Approved Schemes - Prioritised for delivery in 2017/18

B1010 Maldon Road, Burnham on Crouch - Speed Burnham on Traffic 30mph carriageway speed roundels and speed limit repeater 1 LMAL162078 Mar-17 £7,250 Awaiting programme date for implementation roundels/speed limit repeater signs Crouch Management signs in section without street lighting

Lea Lane, Little Braxted - Traffic Management Traffic 2 LMAL142076 Little Braxted Mar-17 Gateway signage treatment £7,000 Awaiting programme date for implementation Improvements Management

Traffic CMA was submitted in October 2017 and Cabinet Member 3 LMAL142029 King Street/Queens Avenue, Maldon - 20mph Maldon Quarter 4 Implementation of 20 mph speed limit £18,000 Management decision was not to proceed with TRO

Wantz Road (Between j/w Queens Street and j/w Traffic Installation of One-way road to allow Parking Partnership to Objections to TRO received and CMA to be submitted for Cabinet 4 LMAL162069 Maldon Mar-17 £25,000 High Street), Maldon - One-way road Management install Residents Parking Scheme Member decision

London Road (Cemetery to start of 30mph limit), Traffic 5 LMAL162031 Maldon Dec-17 40mph speed limit buffer £8,000 Completed - Oct-17 Maldon - 40mph buffer Management

Traffic Signing review to ensure through traffic navigates through 6 LMAL162120 Maldon Town - Signing Review Maldon Quarter 4 £10,000 Completed - Nov-17 Management Town as efficiently as possible.

Lower Burnham Road j/w Fambridge Road, North 7 LMAL161010 Sep-17 Safer Roads Signing and verge marker posts £16,000 Completed Fambridge - Signs/Verge marker posts

CMA was submitted in September 2017 and Cabinet Member Traffic 8 LMAL152002 Fish Street, Goldhanger - 20mph speed limit Goldhanger Quarter 4 To reduce the speed limit to 20mph £5,000 decision was not to proceed with TRO. September 2017 Panel Management meeting decision to cancel scheme

Scope of scheme changed, with budget adjustment to £3,830. Church Road (To j/w Mope Lane) Wickham Traffic 9 LMAL162083 Wickham Bishops Mar-17 To extend 30mph speed limit to junction £2,500 Consultation finished on 30th November 2017. Awaiting Bishops - Extension of 30mph Management programme date for implementation

Page 3 of 6 Maldon District Local Highway Panel - Approved Works Programme 2017/18

2018/19 Priority Schemes Key Completed Cancelled Update Scheme

CMA Scheme Ref Cost Code Scheme Parish Finish Works Description Allocated Budget Comments Priority Scheme approved Category

Approved Schemes - Prioritised for 2018/19 Rolling Programme

Waterside Road, Bradwell on Sea - HGV Signage Traffic Improvements to HGV signs to prevent goods vehicles being September 2017 Panel decision to prioritise scheme for delivery in 12 LMAL162041 Bradwell on Sea 2018/19 12/04/2016 £5,500 2018/19 Priority Scheme improvements Management unable to turn around at end of road 2018/19

Adjacent White Lyons/Bradwell Church, High Traffic Waiting restrictions - Narrow carriageway and parked September 2017 Panel decision to prioritise scheme for delivery in 13 LMAL162090 Street, Bradwell on Sea - Traffic Management Bradwell on Sea 2018/19 11/04/2017 £5,500 2018/19 Priority Scheme Management vehicles causing congestion issues 2018/19 Improvements

Southminster Road (old Heath to Mangaps Burnham on Traffic Panel decision required to fund this scheme for delivery in 2018/19 14 LMAL142037 2018/19 11/04/2017 Feasibility Study into walkable verge £4,000 Manor), Burnham on Crouch - Walkable verge Crouch Management financial year

Hackmans Lane, Cock Clarks - Traffic Traffic Bend warning/chevron sign improvements with Max speed Panel decision required to fund this scheme for delivery in 2018/19 15 LMAL152030 Cock Clarks 2018/19 11/04/2017 £6,500 Management Improvements Management 30mph sub-plates as necessary financial year

B1026 Maldon Road, Goldhanger - Speed Traffic 30mph carriageway speed roundels and increased number of September 2017 Panel decision to prioritise scheme for delivery in 16 LMAL162048 Goldhanger 2018/19 12/04/2016 £13,500 2018/19 Priority Scheme roundels/speed limit repeater signs Management speed limit repeater signs 2018/19

Tiptree Road, Great Braxted - Traffic Management Traffic Panel decision required to fund this scheme for delivery in 2018/19 17 LMAL162050 Great Braxted 2018/19 11/04/2017 30mph repeater signage improvements £6,500 Improvements Management financial year

Footpath 4 (Kelvedon Road to Goat Lodge Road), Public Rights of Panel decision required to fund this scheme for delivery in 2018/19 18 LMAL158004 Great Totham 2018/19 11/04/2017 Surface improvements - Planings/timber edging for 200m £5,500 Great Totham - PRoW Way financial year

Traffic Panel decision required to fund this scheme for delivery in 2018/19 19 LMAL152049 Four sites Heybridge - Gateway treatments Heybridge 2018/19 11/04/2017 Post and Rail gateway features £39,000 Management financial year

Lower Burnham Road 600m west of j/w Rectory September 2017 Panel decision to prioritise scheme for delivery in 21 LMAL161011 Latchingdon 2018/19 11/04/2017 Safer Roads Safety measures to prevent vehicles entering pond £13,000 2018/19 Priority Scheme Lane, Latchingdon - vehicle restraint system 2018/19

Witham Road j/w Lea Lane, Little Braxted - HGV Traffic Panel decision required to fund this scheme for delivery in 2018/19 22 LMAL162088 Little Braxted 2018/19 11/04/2017 Feasibility Study/signage review of HGV signage to A12 £4,000 signage Management financial year

Lea Lane (school House to War Memorial), Little Traffic Panel decision required to fund this scheme for delivery in 2018/19 23 LMAL162095 Little Braxted 2018/19 11/04/2017 Install Pedestrian in Road signage £2,500 Braxted - Pedestrian in Road signage Management financial year

Panel decision required to fund this scheme for delivery in 2018/19 Fambridge Road, Maldon (Limebrook Way RAB to Traffic 24 LMAL142006 Maldon 2018/19 15/04/2015 Detailed design of footpath £6,000 financial year. Scheme under negotiation as a result of local Royal Oak PH) - Footpath Management development

Limebrook Way j/w Wantz Road, Maldon - Traffic Traffic Feasibility study into signage improvements A414 to Hythe Panel decision required to fund this scheme for delivery in 2018/19 25 LMAL162071 Maldon 2018/19 11/04/2017 £4,000 Management Improvements Management Quay and Parking at Promenade Park financial year

Outside The Lower Plume School, Mill Road, Passenger Panel decision required to fund this scheme for delivery in 2018/19 26 LMAL165017 Maldon 2018/19 11/04/2017 Replacement bus shelter £8,500 Maldon - Passenger Transport Transport financial year

Imperial Avenue, - Passenger Passenger Panel decision required to fund this scheme for delivery in 2018/19 27 LMAL155008 Maylandsea 2018/19 11/04/2017 Bus cage £3,500 Transport Transport financial year

Page 4 of 6 Maldon District Local Highway Panel - Approved Works Programme 2017/18

2018/19 Priority Schemes Key Completed Cancelled Update Scheme

CMA Scheme Ref Cost Code Scheme Parish Finish Works Description Allocated Budget Comments Priority Scheme approved Category

Approved Schemes - Prioritised for 2018/19 Rolling Programme

Fambridge Road (Lower Burnham Road to Traffic Feasibility Study to consider provision of new Panel decision required to fund this scheme for delivery in 2018/19 28 LMAL152010 Rectory Road), North Fambridge - Study into North Fambridge 2018/19 25/03/2015 £6,000 Management footway/walkable verge financial year provision of footway

Recreation Ground, Fambridge Road, North Traffic Panel decision required to fund this scheme for delivery in 2018/19 29 LMAL142041 North Fambridge 2018/19 11/04/2017 Playground Warning Signs £2,000 Fambridge - Traffic Management Improvements Management financial year

B1010 Fambridge Road (The Wash to Roundbush Traffic Panel decision required to fund this scheme for delivery in 2018/19 30 LMAL142031 P/H), - Traffic Management Purleigh 2018/19 11/04/2017 Feasibility study into speed reduction measures £4,000 Management financial year Improvements

Byway 32 Purleigh (Roundbush Road to How Public Rights of Panel decision required to fund this scheme for delivery in 2018/19 31 LMAL168007 Purleigh 2018/19 11/04/2017 Improve drainage, rebuild surface and install bollards £32,500 Green Road) - PRoW Way financial year

B1010 Chelmsford Road (Spar Lane to Edgeware Feasibility study into walkable verge/footway, pedestrian Panel decision required to fund this scheme for delivery in 2018/19 32 LMAL153001 Purleigh 2018/19 11/04/2017 Walking £8,000 Veterinary Practice), Purleigh -Walking video survey and road safety audit financial year

Main Road, St Lawrence - Improvements to traffic Traffic Installation of solar lighting at existing priority working traffic Panel decision required to fund this scheme for delivery in 2018/19 33 LMAL152013 St Lawrence 2018/19 25/03/2015 £14,000 calming Management calming financial year

Works were to be undertaken during 2017/18 Capital Carriageway The Street (The Sun & Anchor PH to The Star Traffic 34 LMAL162062 Steeple 2018/19 12/04/2016 Install edge of carriageway road markings £3,000 Resurfacing Scheme, surfacing scheme currently on hold through PH), Steeple - Edge of carriageway road markings Management this section of the The Street

Hagg Hill - Traffic Management Traffic September 2017 Panel decision to prioritise scheme for delivery in 35 LMAL152029 Stow Maries 2018/19 11/04/2017 Unsuitable for HGV signage £6,500 2018/19 Priority Scheme Improvements Management 2018/19

Woodham Road j/w Martins Lane, Stow Maries - Traffic Drainage improvements - connection of existing drainage Panel decision required to fund this scheme for delivery in 2018/19 36 LMAL162096 Stow Maries 2018/19 11/04/2017 £26,000 Traffic Management Improvements Management systems to maximise flow financial year

Traffic September 2017 Panel decision to prioritise scheme for delivery in 37 LMAL152017 Church Street, Tollesbury - Dropped kerbs Tollesbury 2018/19 25/03/2015 Dropped kerbs to improve access to bus stop £8,500 2018/19 Priority Scheme Management 2018/19

Parish Rooms, Church Street, Tollesbury - Traffic Create pedestrian access to Parish Rooms - kerbing and Panel decision required to fund this scheme for delivery in 2018/19 38 LMAL162093 Tollesbury 2018/19 11/04/2017 £22,500 Pedestrian access improvements Management resurfacing financial year

Factory Hill/Brook Road/D'Arcy Road, Tolleshunt Tolleshunt Traffic Feasibility Study into mini-roundabout improvements - Panel decision required to fund this scheme for delivery in 2018/19 39 LMAL162055 2018/19 12/04/2016 £4,000 Knights - Mini-RAB Knights Management extension of kerb line/domed RAB/directional signage financial year

Brook Road/Tolleshunt D'Arcy Road, Tolleshunt Tolleshunt Traffic Improvements to speed limit repeater signs (size/frequency) September 2017 Panel decision to prioritise scheme for delivery in 40 LMAL162081 2018/19 12/04/2016 £8,500 2018/19 Priority Scheme Knights - Speed limit repeater signs and roundels Knights Management and roundels 2018/19

Beckingham Street/Tolleshunt D'Arcy Road, Traffic Improvements to existing speed limit repeater signs September 2017 Panel decision to prioritise scheme for delivery in 41 LMAL162082 Tolleshunt Major 2018/19 14/04/2016 £6,500 2018/19 Priority Scheme Tolleshunt Major - Speed signage improvements Management (size/frequency) 2018/19

Page 5 of 6 Maldon District Local Highway Panel - Approved Works Programme 2017/18

2018/19 Priority Schemes Key Completed Cancelled Update Scheme

CMA Scheme Ref Cost Code Scheme Parish Finish Works Description Allocated Budget Comments Priority Scheme approved Category

Approved Schemes - Prioritised for 2018/19 Rolling Programme

Mill Lane j/w Beckingham Street, Tolleshunt Major Traffic Signage review of HGV directional signage to ensure correct Panel decision required to fund this scheme for delivery in 2018/19 42 LMAL162091 Tolleshunt Major 2018/19 11/04/2017 £17,000 - Traffic Management Improvements Management route via School Road is used financial year

Maldon Road near Does Corner, Ulting - Traffic Traffic Passed over to Cyclical Maintenance team, scheme does not 43 LMAL162100 Ulting 2018/19 11/04/2017 Drainage system jetting works £2,398 Management Improvements Management require LHP funding

Feasibility Study into priority working/build outs on At March 2017 Panel meeting it was agreed that should funding Witham Road/The Street, Wickham Bishops - Traffic Road/The Street, also to include consideration of closing 44 LMAL162039 Wickham Bishops 01/03/2017 24/06/2016 £13,000 permit this scheme will be brought into 2017/18 programme for Priority Working/Build Outs Management junction of School Road/The Street and making Back Lane delivery one-way from Five Corners junction

Church Road (Holt Drive to Blacksmiths Lane) & Panel decision required to fund this scheme for delivery in 2018/19 45 LMAL153002 Arbour Lane (Blacksmiths Lane to Grange Road ), Wickham Bishops 2018/19 11/04/2017 Walking Feasibility Study into provision of walkable verge/footway £4,000 financial year Wickham Bishops - Walking

Lodge Road, - Traffic Woodham Traffic September 2017 Panel decision to prioritise scheme for delivery in 46 LMAL162075 2018/19 11/04/2017 Unsuitable for HGV signage £1,500 2018/19 Priority Scheme Management Improvements Mortimer Management 2018/19

Footpath 1 (Blue Mills Hill to Mope Lane) Public Rights of Panel decision required to fund this scheme for delivery in 2018/19 47 LMAL158006 Wickham Bishops 2018/19 11/04/2017 Surfacing improvements - Edging boards and planings 950m £15,000 Wickham Bishops - PRoW Way financial year

Page 6 of 6 MALDON DISTRICT LOCAL HIGHWAY PANEL POTENTIAL SCHEMES LIST (Version 26)

This Potential Scheme List identifies all of the scheme requests which have been received for the consideration of the Maldon District Local Highways Panel. The Panel are asked to review the schemes on the attached Potential Scheme List, finalise their scheme funding recommendations for the schemes they wish to see delivered in 2018/19 and remove any schemes the Panel would not wish to consider for future funding.

There are currently potential schemes with an estimated cost of £182,000 as shown in the summary below -

Potential Schemes List (Version 26)

Ref. Scheme Type Total Estimated Costs

1 Traffic Management £120,000

2 Passenger Transport £27,000

3 Public Rights of Way £35,000

4 Total £182,000

On the Potential Schemes List the RAG column acknowledges the status of the scheme request as shown below -

RAG Description of RAG status Status

G The scheme has been validated as being feasible and is available for Panel consideration

A The scheme has been commissioned for a feasibility study which needs completing before any Panel consideration

R A scheme which is against policy or where there is no appropriate engineering solution

V A scheme request has been received and is in the initial validation process

Page 1 of 8 MALDON DISTRICT LOCAL HIGHWAY PANEL POTENTIAL SCHEMES LIST (Version 26)

Blank Page

Page 2 of 8 Traffic Management

Total Value of schemes £128,500

2018/19 Scheme Ref Location Description Problem Requested by Parish Cost Code Estimated cost Comments RAG Priority stage Scheme

Validation - Good compliance with 40mph Fords Corner to speed limit but poor compliance with Riverview Caravan Traffic management and Speed of traffic and Total existing 30mph speed limit. Validation 1 Park, B1010 Lower pedestrian crossing possible relocation of bus Residents Althorne LMAL162104 £20,000 G scheme suggests Village Gateway treatment Burnham Road, improvements stop at Caravan Park £10,000 and 30mph repeater signs/roundels Althorne £10,000

Validation - Posted speed limit 30mph, B1021 Bradwell South bound 36.4mph & North bound Traffic management Speed of traffic in 30mph Total 2 Road, Mill End Councillor Bradwell on Sea LMAL162119 £18,500 37.1mph. Recommendation - Vehicle G improvements limit scheme Bradwell on Sea Activated Sign and speed limit repeater signs

Cedar Grove, Accessibility issues on Burnham on Total 3 Footway improvements Councillor LMAL162116 TBC In validation V Burnham on Crouch footways Crouch scheme

Maldon Road/Hall Road/Walden House Parking improvements at Parking causing problems Total 4 Road/Prince of Parish Council Great Totham LMAL172005 TBC In validation V junctions at junctions scheme Wales Road, Great Totham B1010 Fambridge In validation - Following joint site meeting Road (Limebrook Traffic management Total 5 Speed of traffic Parish Council Hazeleigh LMAL162110 TBC with Councillors, Village Gateways now R Way to Bury Farm), improvements - VAS scheme being considered Hazeleigh

B1010 Fambridge Village Gateway Total Validation - Feasible to install Village 6 Speed of traffic Parish Council Hazeleigh LMAL172002 £14,000 G Road, Hazeleigh Improvements scheme Gateway treatments

The Causeway/The Queuing traffic on RAB Total Validation - Recommends Keep Clear road 7 Square/The Street, RAB improvements Resident Heybridge LMAL172003 £4,000 G blocks road scheme marking at Holloway Road junction Heybridge

Nr Plantpak, In validation - Results of traffic speed survey Traffic management Speed of traffic prior to Total 8 Burnham Road, Councillor Latchingdon LMAL172018 TBC - 60mph speed limit - South bound 43.2mph V improvements 30mph speed limit scheme Lathcingdon & North bound 45.1mph

Fambridge Road (Limebrook Way Lack of footway between Total Liaison on-going regarding nearby potential 9 RAB to Royal Oak Walkable verge/footway small hamlet/public house Councillor Maldon LMAL162099 TBC V scheme development Public House), and Maldon Town Maldon

Page 3 of 8 Traffic Management

Total Value of schemes £128,500

2018/19 Scheme Ref Location Description Problem Requested by Parish Cost Code Estimated cost Comments RAG Priority stage Scheme

Validation - Whilst there is no signage at the top of Market Hill directing traffic to car parks. There is parking in either direction along the High Street which is signed, so Market Hill j/w High Improved signage to Car No signage at top of hill to Total any visitor taking either direction will be able 10 District Council Maldon LMAL152072 NA R Street, Maldon Parks direct traffic to Car Parks scheme to find a car park. Also there are a lot of existing signs at the top of Market Hill and there is a current drive by DfT to reduce sign clutter. Awaiting results of 2017/18 Maldon Town Signing review

Validation - With proposed housing Fambridge Road Traffic management Vehicles routinely leaving Total developments it is likely speed limits could 11 /Limebrook Way Councillor Maldon LMAL162108 NA R improvements carriageway scheme be reviewed on Limebook Way. Suggestion RAB, Maldon to await future developments

Station Road, No through road and lorry Total In validation - Awaiting results of 2017/18 12 Signage improvements Councillor Maldon LMAL162113 TBC V Maldon access scheme Maldon Town Signing review.

Traffic management Old Heath Road, Speed of traffic on narrow Total In validation - Initial findings are a Feasibility 13 improvements and request Councillor Southminster LMAL162118 TBC V Southminster rural road scheme Study could be warranted for Quiet Lane status

Validation - Review size/frequency of 20mph High Street, 20mph repeater signs Identifying 20mph speed Total 14 Parish Council Southminster LMAL172009 £4,000 repeater signs and terminal signs. G Southminster size/frequency limit scheme Implement changes

East Street/High Validation - parking restrictions here would Total 15 Street jw Station Parking improvements Parking issues at junction Parish Council Tollesbury LMAL172001 NA need to be considered by Parking R scheme Road Tollesbury Partnership

Kelvedon Road nr Vehicle Activated Tolleshunt Total In validation - Awaiting LHP scheme request 16 j/w Maypole Road, Sign/Speed Indicator Speed/volume of traffic Parish Council LMAL162074 TBC V Knights scheme form Tolleshunt Knights Device

Page 4 of 8 Traffic Management

Total Value of schemes £128,500

2018/19 Scheme Ref Location Description Problem Requested by Parish Cost Code Estimated cost Comments RAG Priority stage Scheme

From Feasibility Study Parish Council preferred Option 2, Standard T-junction with pedestrian island at estimated cost Beckingham £125,000. Scheme would require acquisition Street/Tolleshunt Existing bennett junction Total 17 Junction improvements Parish Council Tolleshunt Major LMAL162077 £45,000 of land. Following site meeting with Parish G D'Arcy Road, causing issues scheme Council representatives in October 2017 Tolleshunt Major Parish indicate Option 1 Standard T-junction estimated cost £45,000 could meet their needs subject to final design.

Validation - There is evidence of some Witham Road, speeding vehicles, there is an agreed Maypole Road, The Wickham Bishops - "Road Total scheme for SID's through the village. 18 Street, Kelvedon Narrowing" at entry points to Speed of Traffic Parish Council Wickham Bishops LMAL142059 TBC V scheme Recommendation is for speed surveys 6 Road, Wickham Village months after the installation of the SID sites Bishops - TMI and then review this request

Validation - "B" road and PR2, width restriction contrary to policy as its main B1018 Langford Width of road when two function is movement of traffic. Suggestion 19 Road, Wickham Carriageway improvements Resident Wickham Bishops Studies LMAL172008 £5,000 G vehicles try to pass is to review Warning Signs and Road Bishops Markings indicating hazards and narrow sections of road

Speed of traffic and A414 Maldon Road, Traffic management Woodham Total In validation - awaiting results of traffic 20 pedestrian access across Parish Council LMAL172016 TBC V Woodham Mortimer improvements Mortimer scheme speed/volume surveys A414 to bus stops

Validation - ATC Rectory Road (nr Bowers Way) - South 33.0mph & North 33.4mph, Herbage Park Road - South 33.7mph & Herbage Park North 34.5mph. Speeds do not meet criteria Road/Church Speed Indicator Device and Total 21 Speed of traffic Parish Council LMAL152057a NA for a VAS/SID, 5mph over posted speed R Hill/Rectory Road, three poles for rotation scheme limit. Some vehicles travelling over 35mph Woodham Walter mainly during hours of darkness. UPDATE - Cabinet Member Briefing Note being considered to allow progression of scheme

Page 5 of 8 Traffic Management

Total Value of schemes £128,500

2018/19 Scheme Ref Location Description Problem Requested by Parish Cost Code Estimated cost Comments RAG Priority stage Scheme

Validation - Maintenance issues need to be B1010 Burnham addressed, missing sign and cutting back of Road near its Traffic management Difficulty turning into Total vegetation. Then junction could be reviewed 22 junction with Marlpits Parish Council Woodham Walter LMAL152060 TBC V improvements Marlpits Road from B1010 scheme to assess the impact. Any engineering Road, Woodham solution would involve major junction Walter realignment.

Validation - ATC Rectory Road (nr Bowers Way) - South 33.0mph & North 33.4mph, Herbage Park Traffic management Herbage Park Road - South 33.7mph & Road/Church improvements - Feasible to Total North 34.5mph. Speeds do not meet criteria 23 Speed of traffic Parish Council Woodham Walter LMAL152057b £6,000 G Hill/Rectory Road, review speed repeater scheme for a VAS/SID. Some vehicles travelling Woodham Walter signage over 35mph mainly during hours of darkness. Validation suggestion is to review speed repeater sign size/visibility/locations.

Validation - ATC Rectory Road (nr Bowers Way) - South 33.0mph & North 33.4mph, Herbage Park Road - South 33.7mph & Herbage Park North 34.5mph. Speeds do not meet criteria Road/Church Speed Indicator Device and Total 24 Speed of traffic Parish Council Woodham Walter LMAL152057a NA for a VAS/SID, 5mph over posted speed R Hill/Rectory Road, three poles for rotation scheme limit. Some vehicles travelling over 35mph Woodham Walter mainly during hours of darkness. UPDATE - Cabinet Member Briefing Note being considered to allow progression of scheme

West Bowers Road Lack of sign for National Total Validation - recommends signage for NCN1 25 j/w Stivvy Road, Cycle route signage Parish Council Woodham Walter LMAL172015 £3,500 G Cycle Network Route1 scheme at either end of Stivvy Road Woodham Walter

Top Lane j/w Parked cars causing Validation - Current KEEP CLEAR road Rectory Road/The problems around junction, Total markings cover maximum distance under 26 Parking improvements Parish Council Woodham Walter LMAL172010 NA R Street, Woodham especially for pedestrians scheme TSRGD. Double yellow lines could be Walter crossing road considered by Parking Partnership.

Page 6 of 8 Passenger Transport

Total Value of schemes £27,000

2018/19 Scheme Estimated Ref Location Description Problem Requested by Parish Cost Code Comments RAG Priority stage cost Scheme

Stop ID 1500LATCHG2 - metal Burnham Road, Parish Council/Passenger Total Validated by Passenger 1 Wooden bus shelter shelter needs replacing (Parish Latchingdon LMAL155016 £9,000 G Latchingdon Transport Team scheme Transport team Council owned Shelter)

Stop ID 1500IM2085 - North Fambridge Road, North North Total Validated by Passenger 2 Wooden bus shelter Fambridge Shelter - replacement Passenger Transport Team LMAL155013 £9,000 G Fambridge Fambridge scheme Transport team needed

Stop ID 1500IM2536 - Ferry The Avenue, North North Total Validated by Passenger 3 Wooden bus shelter Corner Shelter - replacement Passenger Transport Team LMAL155014 £9,000 G Fambridge Fambridge scheme Transport team needed

Page 7 of 8 Public Rights of Way

Total Value of schemes £35,000

2018/19 Ref Location Description Problem Parish Scheme stage Cost Code Estimated cost Comments RAG Priority Scheme

Handley's Lane, Validation - Surfacing to between Kelvedon north-east section (not to Surface improvements to Byway often inaccessible Road and adoptable standards) and 1 byway to allow all year due to flooding /surface Wickham Bishops Total scheme LMAL158003 £35,000 G Handley's Lane middle section round usage condition roadway, Wickham levelled/finished with Bishops planings

Page 8 of 8 Maldon District Local Highway Panel - Section 106 Programme 2017/18

Schemes Key Completed Cancelled Update

Ref Cost Code Scheme Parish Finish Scheme Category Works Description Allocated Budget Comments

Traffic Management 1 10001424 Fullbridge, Maldon - Upgrade crossing Maldon Mar-17 Design of pedestrian crossing upgrade £5,000.00 Design only 2017/18 Improvement Maldon District Highway Rangers - August to September 2017 Works Summary

REF Parish/Ward Road Name Location Type of Work Required Comments Date Completed

1 MDC Little Braxted Old School Lane Old School Lane Other (explain in notes) Dug holes & concreted in 2 road signs 07/08/2017

2 MDC Little Braxted Various roads Various locations Vegetation trimming Clean & cut around Parish Sign 08/08/2017

3 MDC Great Braxted Various roads Various locations Other (explain in notes) Cleaned & cut around signs 08/08/2017

4 MDC Bradwell Various roads Various locations Sign cleaning Started to clean Parish Signs 08/08/2017

5 MDC Great Totham Wood Road/ Broad Street Green Various locations Vegetation trimming Hedgeccut & strim footpath 10/08/2017

6 ECC Great Totham Colchester Road Bus shelter Opp side of road to Compasses P/H Sign cleaning Bus shelter and flag including visibility splay overgrown 11/08/2017

7 MDC Great Totham Colchester Road Bus stop opp Compasses pub Vegetation trimming Cut back & strimmed around bus stop 11/08/2017

8 MDC Bradwell Various roads Various locations Vegetation trimming Cut & strim footpath 11/08/2017

9 MDC Bradwell Various roads Various locations Sign cleaning Finish cleaning signs in Bradwell 11/08/2017

10 ECC Maldon Midguard Way Whole length Vegetation trimming 40x0.5m weeds over footway 14/08/2017 Independent path end of Longship Way to Washington 11 ECC Maldon Longship Way Vegetation trimming Approx. 40m nettles / bushes over footway 14/08/2017 Road 12 MDC Maldon Various roads Various locations Vegetation trimming Cut & strim footpath Midguard Way to Comm Centre 14/08/2017

14 MDC Mayland Nipsells Chase On road Other (explain in notes) Fix dog bin to post 15/08/2017 Between Washingotn Road, Norfolk Close, Norfolk 15 MDC Maldon High Street Vegetation trimming Cut & strim footpaths 16/08/2017 Road Cut out old sign, dig new holes, concrete, tarmac & fit 16 MDC Heybridge Coopers Avenue On road Other (explain in notes) 17/08/2017 new sign 17 MDC Burnham Sea Wall Trails Various locations Vegetation trimming Riverside Park strimming sea wall trail runs 21/08/2017

18 ECC North Fambridge Fambridge Road Between Rectory Road and Buller Road Vegetation trimming Nettles and brambles encroaching f/way, 50.0m x 0.5m 22/08/2017 Cut & strim footpath Rectory Rd, also up & over bridge 19 MDC North Fambridge Rectory Rd Various locations Vegetation trimming 22/08/2017 & the avenue Cut & strim footpath. Playsite heybridge approach to 20 MDC North Fambridge Emporer Place to Elizabeth Way Various locations Vegetation trimming 24/08/2017 Samian Close 21 MDC Tollesbury Various roads Various locations Other (explain in notes) Digging out & install concrete base for recycling bin 25/08/2017

22 MDC Tollesbury Woodrolfe Road Park area Vegetation trimming Cut & strim hedge toilet to gate 25/08/2017

23 MDC Heybridge Elizabeth Way/ Emporer Close Footpath to Heybridge Approach Vegetation trimming Strim footway 28/08/2017 Elizabeth Way to Heybridge 24 MDC Heybrige Footpath to Heybridge Approach Vegetation trimming Finish off strimming 29/08/2017 Approach 25 MDC Tollesbury St Johns Court Footpath Vegetation trimming Cut & strim footpath 29/08/2017

26 MDC St Stephens Raod Footpath Other (explain in notes) Re-concrete post in with dog bin on it 30/08/2017

27 MDC Tollesbury Woodrolfe Road Footpath Other (explain in notes) Drill in litter bin into concrete base 30/08/2017

28 MDC Tollesbury Various roads Various locations Sign cleaning Cut back & wash signs 30/08/2017

29 MDC Heybridge Goldhanger Road Salcote Maltings to turning Vegetation trimming Cut back vegetation of on footpath 30/08/2017

Page 1 of 4 Maldon District Highway Rangers - August to September 2017 Works Summary

REF Parish/Ward Road Name Location Type of Work Required Comments Date Completed

30 MDC Heybridge Goldhanger Road Salcote Maltings to caravan park Vegetation trimming Cut back footpath 31/08/2017

31 MDC Maldon Dump Road Dump Road next to Prom Park Other (explain in notes) Saw & remove fallen tree 01/09/2017 Remove 2 trees, cut back footpath ready for installation 32 MDC Burnham-On-Crouch Town Riverside Footpath Other (explain in notes) 05/09/2017 of new surface for picnic benches 33 MDC Stow Maries Haggs Hill Haggs Hill Other (explain in notes) reconcrete Haggs Hill sign in place 06/09/2017

34 MDC Heybridge Nr A414 Oak Tree Meadow Vegetation trimming Cut & strim oaktree meadow to Tesco blue bridge 06/09/2017

65 MDC Heybridge Heybridge Approach Heybridge Approach roundabout to Double Day Drive Vegetation trimming Strim vegetation 7 to 8/09/17 Footpath from Bus stop on Hatfield Rodd to Ulting 35 ECC Langford Hatfield Road Vegetation trimming Footway obstructed by vegetation 11/09/2017 Lane 36 ECC Maldon Mill Road Outside 47 the museum Sign cleaning Bend warning sign obscured by vegetation 11/09/2017

37 MDC Ulting Ulting Lane to Hatfield Road Between 2 locations & bus stop Vegetation trimming Strimmed footpath 11/09/2017

38 ECC St Lawrence Main Road Opposite Moorhen Avenue Sign cleaning Road sign needs cleaning 12/09/2017

39 MDC St Lawrence Moorhen Avenue Various locations Vegetation trimming Cut back hedge, strim & clean road signs 12/09/2017

40 MDC Heybridge Heybridge Approach Elms Farm roundabout to Heybridge Approach Vegetation trimming Cut & strim 13/09/2017 Between Jacobs farm and Lawling Avenue rear of 41 ECC Heybridge Goldhanger Road Vegetation trimming 40m veg weeds / bushes encroaching on footway 14/09/2017 16/18 Southey close Cut & strim footpath. 4 trees blown over, chain sawed 42 MDC Heybridge Goldhanger Raod Footpath Jacobs Farm to Lawling Avenue Vegetation trimming 14/09/2017 & made safe Nettles & vegetation encroaching onto footway, 50.0m 43 ECC Mayland Wembely Avenue Between j/w Nipsells chase and Hillcrest Vegetation trimming 15/09/2017 x 0.4m 44 ECC Mayland MAYLAND GREEN Adj Whitfield court Vegetation trimming Brambles encroaching f/way, 10.0m x 0.4m 15/09/2017

45 ECC Mayland MAYLAND GREEN Between opp The Copse and Whitefield court Vegetation trimming Branches encroaching footway, 20.0m x 1.0m 15/09/2017 Nipsells Chase, Wembley 46 MDC Mayland Vegetation trimming Cut & strimmed between locations 15/09/2017 Avenue, Hillcrest Low overhanging branches across carriageway, 16.0m 47 ECC Cold Norton VICTORIA ROAD Side of 4 Brennan Close Vegetation trimming 18/09/2017 x 2.5m 48 ECC Cold Norton CLARKE RISE Between lamp column 1 & j/w Latchingdon Road Vegetation trimming Low overhanging branches, 10.0m x 1.0m 18/09/2017

49 MDC Cold Norton Victoria Road Vegetation trimming Cut & strim hedge and low branches over hanging 18/09/2017 100m vegetation over footway grass / siding / low 50 ECC Heybridge HOLLOWAY ROAD From Holloway Road to Glynwood Vegetation trimming 19/09/2017 branches 51 ECC Great Totham MALDON ROAD Os 56 Vegetation trimming Weed growth through footway 19/09/2017 100m vegetation over footway grass / siding / low 52 MDC Heybridge Holloway Road From Holloway Road to Glynwood Vegetation trimming 19/09/2017 branches 53 MDC Great Totham Maldon Road Vegetation trimming Weed growth through footway 19/09/2017 Over raised walkway Langford bridge outside Museum Approx. 120m veg encroaching on footway on raised 54 ECC Langford HATFIELD ROAD Vegetation trimming 20/09/2017 of Power walkway Belisha beacon obscured by hedge, others sides 55 ECC Latchingdon THE STREET Opp 93 Vegetation trimming 20/09/2017 visible, 10.0m x 0.4m Cut & strim raised footway Hatfield Road, Langford 56 MDC Langford HATFIELD ROAD Hatfield Road Vegetation trimming 20/09/2017 between bridge and museum

Page 2 of 4 Maldon District Highway Rangers - August to September 2017 Works Summary

REF Parish/Ward Road Name Location Type of Work Required Comments Date Completed

Cut & strim hedge, The Street up to Zebra crossing & 57 MDC Latchingdon THE STREET The Street Vegetation trimming 20/09/2017 flashing beacon 58 ECC Mayland Mayland Green Between Opp The Jays & Avocet House Vegetation trimming Hedge encroaching c/way, 35.0m x 1.0m 21/09/2017 Cut & strim semi circle Hedge Mayland Close and saw 59 MDC Mayland Mayland Green Mayland Close, Maldon Road Vegetation trimming 21/09/2017 low branches. Cut & strim & litterpick footpath Cutting hedges towards main doors of Wickham 60 MDC Wickham Bishops The Street Wickham Bishops Community Centre Vegetation trimming 22/09/2017 Bishops Community Centre to bus stop Cut & strim: footpath from Station Road, The Street to 61 MDC Southminster Station Road Station Road, The Street to Seasons Wood Vegetation trimming 27/09/2017 Seasons Wood 62 MDC Burnham-On-Crouch Town Southminster Road St Mary's Church Vegetation trimming Cut & strim footpath back at St. Mary's Church 28/09/2017 Strim & mow 4 x verges in Down Road, Strim verge 63 MDC Heybridge Wood Road, Downs Road Various locations Grass 28/09/2017 opposite Wood Road, Heybridge Cut & strim & litter pick footpath next to Little Steps 64 MDC Maldon Blind Lane Little Steps Nursery Vegetation trimming 29/09/2017 Nursery

Page 3 of 4

Blank Page

Page 4 of 4 Maldon District Local Highway Panel - Revenue Budget 2017/18

Item Amount Revenue Budget £97,247 Monies allocated £79,624 Monies remaining £17,623

Ref. Allocated Cost code Description Problem Requested by Parish Comments No. Budget

2017/18 Highway Rangers Service Provision of Highway 1 Minor highway works Panel Various £72,000 provided by Maldon District Council Rangers service

ATC's completed - East - 30 mph E bound 28.8 mph & W bound 32.2 VAS not working, ATC mph, Mid - 30 mph E 2 LMAL172007 The Street Steeple checks to ensure three sites HLO Steeple £750 Bound 31.3 mph & 32.0 still meet criteria mph. West - 30mph E bound 32.6 mph & W bound 30.8 mph

ATC completed - VAS not working, ATC check 30mph speed limit - SE 3 LMAL172006 D'Arcy Road, Tolleshunt Knights to ensure site still meets VAS HLO Tolleshunt Knights £250 bound 37.9 mph & NW criteria bound 36.5 mph

Black House Farm Cottages, 4 LMAL172011 Road safety assessment Panel St Lawrence £500 RSA completed Steeple Road, St Lawrence

ATC data - Speed limit 30mph - South of Cromwell Hill - Uphill Two ATC checks to feed into 22.9 mph & Downhill 5 LMAL172012 Market Hill, Maldon HLO Maldon £500 validation of TMI request 25.1 mph And South of Fullbridge - Uphill 29.2 mph & Downhill 27.9 mph

Page 1 of 4 Maldon District Local Highway Panel - Revenue Budget 2017/18

Item Amount Revenue Budget £97,247 Monies allocated £79,624 Monies remaining £17,623

Ref. Allocated Cost code Description Problem Requested by Parish Comments No. Budget

ATC data - Speed limit ATC check to feed into 30mph South bound 6 LMAL172013 Main Road, Mundon Parish Mundon £250 validation of TMI request 35.3mph & North bound 33.3mph

7 LMAL172006 D'Arcy Road, Tolleshunt Knights VAS repair Parish Council Tolleshunt Knights £344 Completed

Completed - 60mph Nr Brants Lane - East 46.8mph & West A414 Maldon Road, Woodham Three ATC checks to feed 47.6mph, Nr Rectory 8 LMAL172016 Parish Council Woodham Walter £750 Walter into validation of TMI request Lane - East 50.9mph & West 52.8mph, Nr Lodge Road - East 48.9mph & 49.4mph

1. Maldon Road, Burnham on 9 LMAL172017 Crouch, 2. Hackmans Lane, Cock VAS repairs Parish Council Various £880 Completed Clarks, 3. Main Road, Mundon

Riverview Caravan Park, B1010 Completed - PV² value 10 LMAL162104 PV² Survey Councillor Althorne £900 Lower Burnham Road, Althorne 0.003x10^8

Completed - 60mph Nr PlantPak, Burnham Road, ATC check to feed into 11 LMAL172018 Councillor Latchingdon £250 South 43.2mph & North Latchingdon validation of TMI request 45.1mph

Page 2 of 4 Maldon District Local Highway Panel - Revenue Budget 2017/18

Item Amount Revenue Budget £97,247 Monies allocated £79,624 Monies remaining £17,623

Ref. Allocated Cost code Description Problem Requested by Parish Comments No. Budget

Completed - 30mph - ATC check to feed into 12 LMAL172019 Princes Road, Maldon Councillor Maldon £250 South 23.9mph & North validation of TMI request 24.2mph

Rotation of two SID units Being arranged with 13 LMAL142061 Rotation of SID in Wickham Bishops Panel Wickham Bishops £2,000 between five poles supplier

Page 3 of 4 Maldon District Local Highway Panel - Revenue Budget 2017/18