<<

A.

BETWEEN:

NAMES

PARTY:

ENTERPRISE:

INVESTOR:

CLAIMANT!

AND

TIlE

UNDER

ADDRESSES

NORTH

GOVERNMENT

Canada

KIA

Ottawa,

239

Justice

Deputy

Office

GOVERNMENT

Canada

M3B

Don

225

Suite

THE

1532382

Vito

SECTION

Wellington

0H8

Duncan

Mills,

G. AMERICAN

3K9

UNCITRAL

101

STATEMENT

of

Building

Attorney

Ontario OF

Gallo

the

oAc)

Ontario

Ontario

VITO

THE

Mill

B

Street

OF

OF

General

PARTIES

OF

Road

Inc.

G.

ARBITRATION

v

FREE

CANADA

CHAPTER

GALLO

CANADA

OF

of

CLAIM

TRADE

Canada

(“Canada”)

Ii

AGREEMENT

OF

RULES

AND

Investor Party 1. The Investor alleges that the Government of Canada has breached, and continues to breach, its obligations under Chapter 11 of the NAFTA, including, but not limited to:

(i) Article 1105, The Minimum Standard of Treatment (ii) Article 1110, Expropriation and Compensation

2. The relevant portions of the NAFTA are attached as “Appendix ‘A” hereto.

B. FACTS SUPPORTING THE CLAIM

B.I IDENTITY OF THE cLAIMANT, THE INVESTMENT,AND THE ENTERPRISE

3. This claim is brought on behalf of 1532382 Ontario Inc. (“the Enterprise”). The Enterprise was incorporated under the laws of Ontario on June 26, 2002.1

4. The Enterprise owns and controls what had been a licensed waste site whose lands included a former iron ore mine located in , known as the Adams Mine Site (“the Investment”) The Adams Mine Site is approximately 10 kilornetres south-east of the town of2 Kirkland 3Lake. 5. . The Investor, Mr. Vito Gallo, is a national of the United States, resident in 4Pennsylvania. 6. Mr. Brent Swanick is the President and sole director of the Enterprise. Mr. Swanick is also a barrister and solicitor, licensed to practice law in the Province of Ontario.

7. On or about June 26, 2002, Mr. Swanick signed a declaration of trust that he held one common share in the capital of the Enterprise in Trust for Mr. 5Gallo. On or about September 9, 2002, Mr. Swanick transferred the share to Mr. 6Gallo.

8. Mr. Gallo is both the legal and beneficial owner of the Enterprise. He holds title to 100% of the issued common shares in the Enterprise. There are no other class of shares (either common

Corporation Profile Report, incorporation date June 26. 2002 2 To be clear, the character of the Investment is composed not only of its real property, but also of its intangibility roperties represented in its permits and any cause of action arising from their unjust revocation. Land Registry Property Identification for Adams Mine Site Passport of Mr. Vito Gallo Declaration of Trust signed by Mr. Brent Swanick, June 26, 2002 Certificate for Shares in 1532382 Ontario mc, June 26, 2002, Transfer of Shares, September 9, 2002

obligations

Partnership

open-pit

13.

Corporation

the

1532382

Sections

12.

1532382

1532382

Enterprise

the

1532382

10. Enterprise

control

Ontario

9.

person

or

Investment)

preferred)

Limited

The

B.2

Limited Under

115,

to

Limited

iron

Limited

retained

On

or

Mr.

the

the

Profile

Business

Limited

Adams

119

or

company.

ore

on

Enterprise

September

Board

Partnership.

separate

ENVIRONMENTAL

Gallo

WASTE

Partnership OVER

in

Management

Partnership

and

Christopher

June

issued

I

mine,

Report,

the

133

Mine

Partnership

of

Corporations

26,

Investment.

possesses

VIEWAND

under

of

DISPOSAL

occupying

by

agreement,

Directors.

incorporation

Agreement,

the

2002

Loan

Site

10,

Gordon

the

Agreement,

The

the

Ontario

2002,

Agreement, Enterprise.

was

and

1532382

(“Limited

legal

Limited

Associates

HIS

four Brent

Act.

continues

SiTE

an

Business

September the

date

APPRO

Enterprise

ps\

September

TORY

control

ideal

Limited

Enterprise

thousand

June

September

Swanick

Partnership

lie

Mr.

to

CorporationsAct Partnership”).

26,

C-TEt

VALS

location

OF

perform

10,

exercises

to

Management

Gallo

9,

of

2002

2002

hold

THE

entered

2002,

acres,

iSSUED

the

also

became

9,

consulting

2002

does

for those

ONTARIO

does

Enterprise

retained

For

with

control

waste

Agreement.

into

not

a

sole

The

positions. 8

TO

not

specified

superb

services

hold

a

OPERATE

disposal.

Director, on

the

Enterprise

hold

limited

GOVERNMENT

pursuant

the

Limited

these

rail

period

in

any

order

basis

and

as

partnership shares

It

of

ownership

THE

is

is

to

to

Partnership

well

time,

road

of

the

discharge

a

the

his

ADA

decommissioned,

in

the

as

General

access

trust

provisions

right

President,

Limited

MS

interest

known

is

to

for

and

to

MINE

Partner

manage

elect

any

high

as

in

of

of

other

the

and

the

the

the of capacity

iron ore Pit’)

volume

improvements 14.

Dagrams

was

ore

and

The

processed rail-haul

electrical

from

shipped

and

Adams

the

consisted,

photographs

the and

Adams

into

Mine

crushed

natural

steel.’2

that

inter

Site

of

a. b. Mine c.

d.

e.

f. g.

h.

i. k. j.

I.

the

would

gas had paved

paved

a

ore a high heavy a/ia, on-site considerable paved

perimeter water

on-site administrative Adams vehicle

gatchouse

two

Site’s

services.

considerable

on

of:

bay

otherwise roadway

line road

run-off

vehicles, on-site

Mine

daily

fuel

paved

and three,

doors,

rail

fencing;

access

Site

storage with

storage

operated

From

access

detention road

and spur;

deep

site

offices;

complete

cost

on

reinforced

weigh-scale

to

gravel

system;

access;

1965

tanks:

site

to

open-pits

and the

tens

trains

grid

areas

improvements

South

to

maintenance

parking

with of

power 1989,

concrete

millions

to

and infrastructure;

vehicle/crane

(“South Pit;

1-lamilton,

two areas;

catch

(electricity

flooring of

mining

buildings

that

Pit.

basins;

dollars

Ontario,

are

Central

capabilities;

companies

and

capable

required

to

with

natural

develop.

where

Pit,

high

of

for

and

extracted

gas)

servicing

the

ceilings,

a

These

4

Peria

large

iron

obtain

for

considered

19.

for

for

site

Keele

of

the

18.

Adams

next

Together,

York,

17. Valley

searching

material

capacity

waste

of

16.

15.

developing

Toronto

the

purchase

receiving

four

for

generation

several

Valley

In

each

Durham

Adams

Notre

the

The

In

Mine

waste

The

thousand

but

order

of

the

for

1986,

that

GTA.

and

year.

Enterprise’s

South

excluding

of at

began

Site

environmental

at

as

a

GTA

the

Mine

site,

for each

the

and least

the

waste

‘next

least

the

an

reached

The

acre The

Adams

the

Pit

GTA

located

working

Adams

municipalities

ideal

Peel,

Municipality

and

of

21

generation’

disposal

1,341,600

City

Adams

of

South

Adams

final

the

.9

predecessor

also

Regions.

the

candidate

its Mine

collectively:

m.

million

three

of

just

Mine

cover

approvals,

with

maximum

Pit

Adams

obtained

Toronto

readily

leachate

Mine

Mine

site.

Site

alone

north

tonnes

major

Toronto

landfill

of

Site

material.

launched

cubic

to

Site

as Metropolitan

Site

Mine

in

available

had

from

financed

a

of

satisfy

infrastructure

the

which

open

the

capacity

title,

of

time

to

from

meters,

with

the

to

a

Site

“GTA

non-hazardous

serve

‘next

Notre a

total

develop

pits

Notre

limited

had

North

city,

Toronto’s

other

Chevron

is

several

gravel/aggregate

in

as

generation’

ultimately

Government

including

been

approximately

municipalities”)

Toronto

for

the

was

Development

a

municipalities

America-wide

the

right

waste

late

$35

obtained

of

and

approaching

Adams

Request

the

of

municipal,

(“Toronto”)

1990s.

million

disposal

would

waste

Dofasco

landfill

first

engineering

of

by

Mine

200

Ontario

Corp.

for

stockpiles

refusal

and and

serve

near

in

Request

the

site.

site

in

Proposal.

full

metres

industrial

1996. Site

end

determined

the

daily

(“Notre”),

Toronto

1990,

as

for

to licensed

Notre

capacity

and

as

of

Province

waste

for

the

Notre

deep

the for

the

internwdiate

2001:

with

feasibility

Notre

Proposal

was

City

and

(the

GTA,

road

future

disposal

waste

and

identified

and

that

and

the

required

of

commercial

of

Regions

purchased

cover

is

intention

once

Toronto

disposal

Toronto

its

it

Ontario.

disposal

studies

for

capable

began

Keele

sites

cover

this

the

the

and

to of 21. the treatment basin Pit, 20. 23. by and Under three asking 22. Minister referred installed 2001 6

Approval Notice Order Ministry Permit

Golder

design

clay

deep

and

this

the

in a. Notre b. d. c. The The On

1.

to Requiring

Notre’s

at

of

Council

of

plant

Take

conditions

to then

EAB

Notre Approval A612007, Certificate 2000:15 Permit Associates open facility Certificate

Is method containment

of

December the

the

Environment

South

hydraulic

operate

the

submitted

waste

Water

Adams

pumped

prevent

Environment

to Approval,

pits the

proposed

application

acquired

Pit

to

under

a consider

any

Board

for

leachate

management of

of

Take

dated

is

in

containment of

Mine Ltd., of

17,

Provisional

the

leachate its

the

leachate designed

to

and

an

the Approval Southern

August

to

Approval

south

project

a

1997,

“hydraulic

Water

hold April

Adams initial

treatment

the

the

an collection

OWRA, leachate Site.

in

to

pit.

internationally following a

early

13,

from

generated

the Borderlands

Certificate hearing the

23, to

from under

environmental

Adams

systems.

to

1998 Ontario,

method

Mine,

operate

facility

to

Ontario

then

l999;’

December Approval treatment

operate

seeping

containment”

of

the

under

operate

the

Mine,

leachate

four Notre

Ontario of

and

from

for

South

as

Golder EAA,

the Approval

s9.2

Environmental a

storm

into

PTTW

from a

questions:

recognized

the

No.

plant. landfill

landfill

sought

1996. a

the rock

assessment

of

Pit,

that

dated

adjacent

Minister Adams

leachate

water

3250-4NMPDN, Associates

the

design

No.

deposited

No. the

PTTW

walls

will

Unlike

EAA,

Rather

site

approvals

00-P-6040,

using

facility, August

A612007,

Crown,

Mine

consulting

be

an

lands.

under

December

of

treatment

of

approval

Assessment

No.

generated

the

effective the

than

waste

Approval the

Ltd.

the

13,

Site

April

October hydraulic

the mature

only

Certificate

00-P6040,

Environment,

seek

1998;’

South

dated

designed was

16, is

EPA,

engineering

23,

application

facility

with

No.

solution

drained

at

1997

approval

18,

1999

analyzed

Board

the

July

3250-4NMPDN.

Pit

containment on

2000

respect

proposed

dated of

the the

and

and 9,

to

for

(the Norm

Approval

for 2001.

to

located a

firm

condition

systems

and

the

storm

the to

containment

October

the

each

“EAB’),’

the

reviewed

expert

site?

16

Sterling,

method.

leachate

Ontario

July

in

of

South

water

6

to

that No.

soil

9.

the

18,

be

in

“on

28.

containment

27.

to

conditions Notre

Notre’s

26.

Environment

EAB

25.

in

20

Site.

Government

24.

following

EAB

the

countering

were

most

application.

Decision:

Adams

and

The

The

The

Ontario’s

The

4.

application

3.

2.

experts

a

included

of

the

Conditions

EAB If

Approval

If

at

effective

If

Ministry

Ministry

design

full

EAB

of

Mine

was

Notre

the the

the

the

the

Ministry

opposition

Ontario.

hearing

in

accepted

Ministry

proposed

answer answer

is

answer

represented

issues

Development

Site.

is

and

a

engineering

solution

an

of

of

requirement

set

an

in

the

the

independent

the

effective

at

of

The

out

Schedule

to

to

raised,

the

to to

of

Kirkland

site?

set

the

Environment

Question

Environment

Question in

EAB

for

the

Question

the

Corporation

Ministry

of

by

Schedule

Environment)

and

the

jointly

Environment

solution

that

the

granting

two

approved

A-i,

L.ake

containment

waste

adjudicative

Notre

1

3

MOE

expert

of

or

is

1

is

A-l

agreed

EA-97-O1.

also

which

for

or

submitted

“No”.

additional

the

“No”,

treatment

of

Notre’s

purchase

appropriate?

2

containment

[Ministry

called

environmental

to

Environment’s

supported

a

upon

is

lasted

is

and

attach waste

in

June

tribunal

“Yes”,

there

application whole

three

to

Conditions,

and

collection

recommended

surrounding

19.

17

the

to disposal

of

an

Notre’s

1998

an

days,

and

expert

are

that

or

any

the

EAB

alternative

in

lawyers.

submissions,

in

collection

the

operates

of

person

by

involved

Certificate

Environmentj

part,

would

technical

application

license.

that

Government

leachate

decision

attached

conditions

what

“the

during

visit

method

you

autonomously

of

40

The

that

witnesses

leachate.”

of

holding

EA-97-Ol

proposed

changes

impose?

to

draft

witnesses,

and

the

Approval.

the

(agreed

of

will

that

provided

Ministry

assisted

Ontario

course

Conditions

Adams

be

in

would

to

to

hydraulic

in

part

generated

between of

from

the

support

1998,18

of

These

of

often

which

Notre

lands

Mine

be

that

draft

7

the

the

the

an of illuminating

following

Technical Ibid..

(b) (a) (j) (g) (d) (c) (1) (i) (1) (e) (u) (r) (o) (n) (k) (h) (t) (q) (p) (m) (v) (s)

at.

26

technical

Appendices,

confirmation

Technical Technical Technical Technical Technical Technical Technical Technical Technical Addendum Technical Technical Addenda Technical Technical Technical Addendum Addendum Technical Technical Technical Addendum

documents2°

Addendums

F5-7

Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix Appendix

Al G1 G2 Cl

of — — — —

the

and

Bird

Public

Surface Surface

inter

viability

A

D C B G F N H G E M J I L K P 0

Response

Hazard —

-Archaeology — — — — — — — — — — —

— a/ia: — — —

Agriculture

and

Geology/Hydrolgeology

Noise

Transportation

Heritage Bird Design

AMSAP Air

Biology Surface Economics Surface Local Social

Water Water

Planned

Agency

Quality

of

to

Hazard and

(1995)

Transportation

Ministry

(1995

Quality Hydrology

and the

Water Water

(1995)

(1995)

Health Public Land

(1995)

proponent’s consultation (1995) Operations (1996)

(1995)

and

of

Use (1995) (1995) Route

(1996)

and

(1996)

Environment

Health

(1996)

(1995)

Agency

Study

Attachments

(1995)

(1995)

(1996) (1995)

design”)9

(1995)

Consultation

Attachments

Notre

(1995)

submitted

8

the 9

(w) Addendum HI — Aquatic Biology (1996)

(x) Attachment Hi E to Addendum Hi — Aquatic biology (1996)

(y) Addendum H2 — Terrestrial Biology (1996)

(z) Response to Ministry of Environment and Energy letter/Sensitivity Analyses — Early Closure and Low Filing Rate Scenarios 29. The Environmental Assessment Board’s 2decision provided, inter alia: As no evidence was provided substantiating an alternative method for the containment and collection of leachate, this decision focused on Question 1, and related conditions. The Board’s response to Question 1, is a conditional “Yes”.

The Board found that, on balance, the evidence indicated that the proposed hydraulic containment design would be effective. A question arises however, concerning the long term maintenance of hydraulic containment (that is, in the gravity drainage phase after the 100-year pumping phase), from the results of tests of groundwater levels in at the single deep angled borehole drilled under the South Pit. Accordingly, Condition of Approval number 10, requests as a condition of proceeding with the proponent’s application for a Certificate of Approval, that two additional deep angled boreholes be drilled under the South Pit, and that “no waste shall be placed in the South Pit until the Director evaluates the results of the tests and determines, without reservation, that the recorded groundwater levels will sustain hydraulic containment in the South Pit such that the environment will be protected, during both pumping and gravity drainage phases.”

The Board’s decision is subject to the Notre Development Corporation meeting, in all, twenty-six conditions, under the following themes:

Monitoring/Operating and Remedial Action and Contingency Plans

Contaminating Lifespan

Financial Assurance

Community Consultation and Participation

Conditions 22 to 26 set out the requirements of a self-managing Community Liaison Committee providing ‘a credible and meaningful opportunity for the people and communities who would be affected by any failure of hydraulic containment to participate in the decision-making process of the landfill project.”

EAB Decision: Notre Development Corporation EA-97-Ol, June 19, 1998, Executive Summary, pp. 1-2. 10

th, 30. On July 8 1998, a group of opponents appealed the EAB decision to the Minister of the

Environment (Minister Sterling) under s. 11(2) of the Ontario Environmental Assessment Act. The Minister denied their request that the Certificate of Approval to be quashed on August 18, 1998. The group attempted to have the Certificate of Approval cancelled by the Ontario Divisional Court immediately thereafter. Its application for an interim injunction was dismissed on April 22, 199922and the application for judicial review was dismissed in its entirety on July

13, 1999: The Ministry of the Environment continued to support Notre throughout the appeal and judicial review process.

31. On April 23, 1999, Notre received the required Certificate of Approval from the Ontario Ministry of the Environment to operate a 24landfill. In Ontario, Certificates of Approval to operate a waste site have conditions which regulate how much waste and what kinds of waste can be disposed both annually and in total over the lifetime of the waste site, as well as the local area which can be serviced by the waste facility. The Certificate of Approval granted to Notre following its environmental hearings, provided, inter alia:

Service Area

12. Wastes may be received at this Site only from within the Province of Ontario.

Ivlaximuin Fill Rate

15. The maximum rate at which the Site can receive waste is 1,341,600 tonnes per year

Waste Placement in the South Pit

34. The total waste disposal volume is 21.9 million cubic metres. This volume includes waste and daily/intermediate cover material and excludes final cover.

32. Certificates of Approval also regulate the geographic boundaries from where the waste site may accept waste, usually from municipalities close to the waste site. Rare among Certificates of Approval, the Adams Mine Site, served by rail-line, was licensed to accept waste

Adams Mine Intervention Coalition v. Ontario (EnvironmentAssessment Board) [1999] O,J. No. 2886 Div. Ct, Adams Mine Inien’ention coalition v. Ontario (Environment Assessment Boardi [1999] O.J. No. 2701 Div. Ct, Ministr of Environment Provisional Certificate of Approval No. A612007. April 23, 1999

expropriation

opposition

Resources

38. the

His

public

opposition

37.

as

Waste

would

36.

Adams

sent Toronto.

35.

complete

together

Ontario),

34.

for

increasingly

Proposals 33.

from

from

RailCycleNorth.

early

opposition

long

for

anywhere

any

protests

Management.

As

also

Following

The

Under

In

Mine

In recycling

term

1990s.

The

to

rail-haul

the

in

2000,

for

Member

location

described

April,

to

adopt

option

offer

October

of

urgent

compacted Canadian

disposal

Disposal

Site;

this

against

the to

the

in

the

making

or

1999,

the

the

to

Ontario.

waste

solution,

Adams

Investment

included in

and

of

being

need

Ontario

Canadian

the

in

2003,

submission

rail

waste

the

Provincial

capacity

followed

National

then

Toronto

more

solution.

waste

use

City

Province

for

option.

deposited

could

Mine

waste

David

being

added

unloaded,

Northland

of

a

that

National

of

detail

would

for

the

replacement

in

Railway

Parliament, issued

be

of

would

Toronto

shipped

Site,

Toronto

Ramsay

This

would

October,

of

capacity,

Adams

sent

into

the

below,

then

Ontario.

sorted

joint

Transportation

Railways,

a

and

RailCycleNorth

to

the

be

soon

and

Request

to

be

had

and

the

Mine

was

compacted

South

1999

the facility

was

in

would

once

venture

loaded

the

and

Adams

follow.

been

Any

the

placed

the

Adams

Site

actively

Enterprise’s

and

and

Pit.

separated,

for

he

waste

expectation

received.

non-hazardous

for

onto

become

as

involving

by

Mine

Ontario

became

Expressions

and

in Commission

Mine

a

the

proposal,

February,

a involved

specially

waste

from

transferred

position

Site.

Keele

with

Site.

predecessor

the

Northland

Ontario’s

Notre,

treatment

that

neighbouring

opponents

key

waste

2000,

in designed

Valley

David

public

of

(owned

to

other

organising

to

Interest

Canadian

act

political

a

six

materials

Railways

Ramsay,

Minister

facility

in

andlor

Site.

on

railway

GTA

railcars;

by

qualified

title,

began

his

municipalities,

in

the

these

A

municipalities

Waste,

actor

private

longstanding had

respect

Notre,

who site

either

was

Province Request

of

organizing

sent

begun

proposals

protests.

Natural

north

in

was

known

Miller joined

waste,

to

being

‘I

of

the the

an

in for

of

its

of a activists’ 39. letter

40. reviewed 26

M:ayor

Letter

Letter

dated

In Lastrnan

from from The

claims.

by

response

the conducted Golder Golder The the in being you, assessment, by The received opinion the technical containment Adams flow environmentally groundwater shared Ontario following Landfill examined geoscientists Gartner

Golder Garner design

September

another

others,

Adams

Adams

Toronto

groundwater

and

Adams

on

Adams

reported

to

The

Associates

Lee

by

Associates Associates

by

Mine

Ministry

Lee

September

to

is

your

received

the studies

a

to

the

environmental Limited

the detailed

Golders

letter

Mine

Mine

technical the

based

public

engineering

Limited

evaluate design.

impacts

Mine that 15,

necessary

in

council,

Landfill

technical

Mine

opposition

in

landfill

to

stated

sound

Landfill

have Site 2000,

of

to

detailed

the 1960

Mayor resources

on

hearing

is Ltd.

technical

Associates

approval

Mayor Landfill

14,

the

We

was

an

in

and

our

media

studies

landfill

conclusively

that proven’

in

2000

from

Environment. solution

is

to

the

international Mel

specialists

will

Certificate

are with

design

part:25 site. work. involved Mel engineering

completed

providing

the

to

the in

we

surrounding

Lastman,

stating confident studies

incorporates

regarding

in

1995 Kirkland

Lastman, the

landfill under

be

stand

Limited

prepared

then

is extensive

engineering

to

the and

project.

maintained,

as solid

to

a

and demonstrated

in

City this Mayor

solidly and of

the

the

surrounding environmental

design

consulting

City

the

1999. firm, proper

part:26

Lake. that

of

the

Approval

peer

area.

of landfill

waste

analyses letter

by

independent

Environmental

of

the

a

Toronto,

Golder

expertise

environmental

our

behind

Toronto,

of Gartner

and

and

proven Over

The

reviewers

professional

hydraulic

As

is

disposal. design

Toronto,

landfill

design.

thereby

engineering

operations.

in

a

scientific

landfill

that over

September

for Associates

area.

that

result,

our

response

September

monitoring.

Lee

method

in

inward peer

operation

a

technical

period

that design

containment

who

We

Our

Our

10 Mel

Limited.

has

the

Assessment

preventing

hydrogeological

acceptability

reviewer

engineers principles.

year

15,

want

confidence to

were firm

14,

provides

Adams subsequently

of

groundwater

Ltd.

Lastman, professional

will 2000

our

statements

2000

design.

period

hydraulic

We

from

to

founded

It

chosen,

sent

experts

protect

assure

method

of

wrote Mine

have

and any

Act

All

the

the

the

on

an

of

rebutting

is

a

following

had

letter

12

been

the

to

2000

issued

41,

stated

the

At

this

3.

Permit

concern: comments

opposed

Please

We continued

other

of

communities

environmental

extensive undertaking.

It

were

thoroughness

accepted

The

will

integrity

Gartner

from

in On

credence.

misleading

endorsement

Recently,

deviates

monitoring

immediately

and

private

ground

influence the

beyond

not

part:

With

supporting

is

point

trust

behalf

cause

Adams

landfills.

our

be

the

involved

to

approved

4

have

to

that

require

regarding

in

Take

advised Lee

of

by

review,

well, The

involvement

water

communities

professional environmental

the

the

oftwo

received

below

we

time

information

the

of

this

an

and

the

of

program

and

technical

proposal

Limited

Mine

property

purpose

Water.

have

For

the

which

security

Adams

if

the

monitoring

adverse

in

the public

divide

sets

beyond.

that

the

specific

public

depth

that

the

to

pit

these

proponent

the

Ministry

can

become

levels

the

Landfill

many

is

the

during

Director

of

dewatering.

in the

and

and

Mine

boundaries reporting,

measure

and opinion,

documents

being

of

extensive

liaison

of

record

located

impact

harm,

generally

for

Furthermore,

this

reasons

the

professional

potential

referred

design

one comments

investigation

Kirkland

programs

therefore

independently

of

Landfill.

letter

concerned

the

development

the

reported

to

has

is

straight.

letter Hollinger’s

committees

the

5

on

conduct

water

based

untrue

dewatering

Gartner

many

km

residents

of

of

is

due

indicate

to

In

Environment,

be

been

adverse

ground

was

to

Lake,

the

exceed

in

the

(99

is

west

addition,

Any

based

by

summarized

engineers

set

level

on

false

and

diligence

Special

hydraulically

at

of

a

Adams

in

letters)

Adams

the

Lee publicly

comprehensive

the

and

accompanying

which

evaluated

of assertion

the

the

that

much

Larder

support

has

water

on

and

impact

of

those

statements

media.

of

the

record

Limited

detailed

operation our

amount

special

Conditions

no

the

to

the

were

Mine

through

any

Mine

and

included

site,

and

first

quantity

basis

which

experience,

contact

Lake

scrutinized

of

pit

to

into

that

Under

straight.

three

isolated

the

received:

monitoring the

geoscientists

is

site.

looks

conditions

local

approval

dewatering

hand

Landfill

studies

of

have

in

separated

the

Director

of

and

five

are

letter

ground

proposal.

environmental

representation

fact.

the

3

incorrect

the

The

and

surrounding

the

and

undertaking

wells,

forward

in

been

study

Engeihart.

from

Ministry

the

areas

perceived

has

dated

98

and

place

landfill.

nearest

quality

ensures

4.

water

of

David

2,

scope

well

by

were

given

will

been

The

the who

the

and

and

the

3,

the

of

October

to

a

at

Ilollinger. 13 18 th, Ministry 42.

Leuer

In

from

of

a

4.

5. completed During the studies From As ministry’s A operation examining The proposal. Environment, for design and team hearing August to members in Environmental

the letter

Ministry

public

its

part With to provided Assessment Ministry conducted specific The landfilling consider considered adopts

Landfill

Environment

the

Proponent’s

Board

of

decision

a

to

the

of

technical the

of of

federal

done

government

of

from

the issue

respect

hearing

of

of

the

this

experts. the Environment PTTW

1998.

the

for Environmental

was

Project

Grand

conditions. concerning

the

ample

the

under

by

landfill

conclusions

technical

activities,

dated the

Ministry’s

potential under

concerning

through Department

Assessment

geology,

process

public,

to

asked landfill.

perspective, before

engineers

the also

proposal,

Ministry

Chief

the

opportunity

the as

June

ministries

the

to

Proponent, site,

stated:27

a

concern

to

Algonquin

and

this and

experts, provisions the

for

and

the

The

whole,

Environmental

of

Environmental

hydrogeology,

1998

These reached

look

given

Assessment

the

of

the groundwater

Act EA

and proposal.

of

local

the

predicting

I

Adams

the

Minister,

Fisheries,

am

and

that

Natural

Algonquin

general

Board for specifically

for

and additional approval

as

scientists,

the Nation reviews

proposal

Notre

environmental

in

satisfied

agencies,

the

the

the

of

well

the

presence

that

Mine

was

Secretariat. Ontario

leachate public

lack

landfill

(EA)

Resources,

analyzed

with

Assessment opposition

issues

Development

Assessment

and

as

and

process.

were

for

has iation

public

held

and

of

this that

at

Public

including

process,

the

surface

Cabinet’s hydrology

to

of

been

public

the could the

in

movement

Regulation in

technical groups,

Ministry, July make

both

the

Adams

the

consultation addition

Secretariat

Kirkland

Director

hydraulic

Environment

thoroughly

to

Act

Act, Liaison

fractured 17,

Adams

be water

consultation

peer

the

the

submissions

Corporation,

the

2001

approved,

review

Board

approval, Mine —

and

Ministry

review and Environmental

the

to

reviews

contamination

Lake Adams

285/99,

is

this

Mine

dated

containment

the

Committee,

the

required

rock.

which

Landfill Proponent, design

examined.

concluded

process,

included

work in Canada,

director

landfill

related

subject by

July

issued

of

to

of

ine

1998.

After

were

were

was

and

the

the

the the

of to

in

17,

a

2001,

14

the

May

47.

GTA

barred

in

46.

waste

and

Michigan

Ontario

45.

Michigan

populated

which

and

and

the

44.

contract

industrial, political

October

43.

waste

Regions

Report Earth

the

the

placement

26,

long-term

institutional

waste

to

Tech

Province

Ontario

is

Minister

The

to

to

This

B.

PUBLIC

GTA

Early

waste

2003 In

Michigan.

the

with

interference

Works

also

27,

3

be

legislature

to

Canada

areas

2003-2004,

commercial

management

fear

primary

shortage

close

municipalities

sent

that

Republic

in

2000

to

selected

waste

capacity.

ONTARIO

Committee,

of

of

of

of

October

AND

of

the

Inc. (“ICI”)

the

municipal

Alberta.

the

the

the

border

Ontario

Republic

State

Summary

method

imports

to

intervened

Ministry

PRIVATE

was

Environment

Adams

border

Ontario

the

Services,

and

close

The

system. 29

waste,

City 2000,

SOON

of

closure

Adams

The

also

institutional

began

were

Michigan

of

issues solid

as

of

Report:

the

to

Services

Mine

of

had

the

Toronto, disposal

part

closure

with

to

magnified WASTE however,

REALIZES

Ontario

the

magnified

border. 28

increased

consumer

to

prevent

City

Mine

an

relating

Availability

Chris of

Site.

Environment

consider

demand

immediate

under

June

its

was

of

in of

waste

NEEDS

waste

Site

general

would

Stockwell

Ontario.

Toronto

the

the

20,

Ontario

The

to

by

ITS

on

because

the

waste

contracted

of

for

exceeding

2003

the

to

this

Toronto

border

the

May soon

NEED

Landfill

Region

new

end

the

and

over-reaction

their

closure

work

shortage

Council

(“MSW

political

(through

Carleton

reacted

contract. in

20

of

after

material

caused

FOR

contract

space

waste.

2005.

with

the

of

to

and

daily

of

the

York.

transport

voted

of

waste”)

in

high

AN

the

to

21,

Toronto

pressures

the

an

Farms

Ontario,

Legislation

shortage

commencement

intake

available

However,

to

this

from

border

ONTARIO

immediate

2003,

Ministry

barriers

to

one

as

emergency

approve

and

Landfill

going

well

January

capacity

and

Toronto’s

case

when

as

of

that

airspace

industrial,

the

was

to

on

a

available

of

as

SOLUTION

of

forward.

back-up

threat

2004,

began

entry

the

October

Regions

the

the

in

mad-cow

Durham

introduced

as

of

by

Michigan.

residential

proposal

PP.

United in

Environment)

well

the

to

for

ordering

to

airspace

commercial

the

9-10

within

Instead,

exports

export

of

11.

landfills,

as

grow

and

FOR

disease

densely

York,

States

in

short-

for

15

2000.

Peel

the

The

the

on

and

for

of

of

in

on its Michigan Durham 49. options 48. again, of reusing, 23. compared majority gap capacity Greater and 51. solid approved.33 from and 3.0

3° 50. Senior 52. landfill

City Diversion

ibid Minutes Memorandum

landfill

2003

York) million

ten

in

consumer

of

the

either

Ministry and

As The Following During Ontario’s

disposal

Ontario,

million

Toronto

Toronto

were

in and

was

of

were

provincial airspace

rate

composting to

alone

of

Meeting

the

joint

to

temporarily

Peel

an

generated

of

is

2003-2004, available

Province

Commissioner

2003-2004,

3.4 scheduled

tonnes. the

waste

Understanding of

of

exported annual

Area particularly

annual

provincial-municipal

Minister to

of

amount the

in about

million

of

GTA

have

Ontario. and

and

Environment

the municipalities

in

disposal

After

of in

or

permitted

9.7

of

Waste

waste.

approximately for

the

municipal

contingency

Ontario institutional,

Ontario

pcrmanently.°

the

Chris Ontario

of waste tonnes

regarding

million

renewal.3’

as

Works Southern

diversion,

Coordination

event

environmental that demand

Stockwell’s

of produced and

disposal

to

officials

had

does

tonnes.

a

(Toronto,

governments

Works

of

waste

cooperative

Ontario

plans

to

commercial

group

an

recycling not

1.3

immediate

(after

determine

Meeting.

go overall Committee,

million

n capacity

warned

was

approximately

in

May

to

the

retained

Region,

diversion and

assessments

the

landfill Effort

shipped

July

previous and

began 26,

diversion

tonnes

event and its

options that

border

totalled

to

City

3,

land as

neighbouring

2003

the

Develop

2003 consultants

industrial

there

a

and

of

that

result by

meeting

of

Region

fifteen

filling

Toronto,

and

closure

13.8

for

order,

waste approximately

rate34

truck

recycling)

was

the

Contingency

of

to

new

programs

millions

in

waste American years,

a

that

develop

to

August

regularly

of senior

to

to

substantial

or

Ontario,

Regions

Michigan

capacity

about

Michigan

had

identify

the

that annually,

the

such

20,

Waste

government

torines

the contingency

export

6.4

number

border

2003,

30%

was

the

to

as

of

greatest

landfill

were

Planning,

at

recycling,

million

waste

Durham. evaluate

balance

annually.

PP.

between

this of

and of

contracts

was

of

2-3

which municipal

not

time.

required shortfall capacity

disposal officials

landfills

plans.2

August

tonnes,

closed

16

of

being

what Peel,

nine

The

the

the

to capacity).

(waste

The

to

56.

from

sites

develop

no

which

Area

Ontario

GTA

55, employment

the

Ontario’s

million

54.

None

vast

intake

53,

Southern in

Gartner

widen

more

Ontario

next

conclusion

that

majority

increasing

(GTA)

Regions

of

disposal

time,

The

capacity

By This

Lee

Those

Region

an

as

rail-hauled

than

25

the

had

Ontario

long emergency

Report

waste 2003

had

consultants

years,

there

was

Ontario

growth

and

been

36

of

confirmed

landfills

term

demand

was

dramatically. fallen

(SOR),

and

landfills

weeks

the

in

the

generation

Region

would

even

GTA closed,

contrast

disposal

permitted

that

for

tonnes

operating

private

Greater

significantly,

plan also

Municipalities

an

of

still

far

Ontario.

allowing

Ontario

that

accepted

be

market.

contingency

as

area

that

exceeds

warned

to

per

operating

continued

no

demand

consultants

well

there

Ottawa

capacity)

the

landfills

that

might

more

year.

was

for

as

only

Adams

was

with includes

Solid

existing that

government

aggressive

would

Region

result

licensed

severely

in

to

disposal

The

a

100,000

had

to the

Waste

the

desperate

retained

rise

Ontario

Mine

handle

annual

be

in

shortfall

majority

Ontario

the

supply

(GOR). and

Disposal

the

capacity

under

fairly

tonnes

capacity

Greater

diversion

landfill,

imposed

the

had

the

by

opening

shortage

intakes

both

consistent

in

government

relevant of

served

The

the Southern

Contingency

insufficient

or

waste

to

the

Windsor

which

at

in

less.

Ministry

and

consultants

price

of

take

of

operating

terms

of

waste

from

the

more

supply

disposal

available

assuming

Ontario

at

was

waste. 5 controls

Plan,

Keele

Area

8.6

of

disposal

projected

a

volume

of

than

permitted

waste

daily

of landfills

January

million

reported

the

(GWA),

capacity

Valley

Region’s

capacity

airspace

700,000

Ontario

average

to

Environment

intake

disposal

capabilities

shortfall prevent

2005

in

tonnes

in

to

landfill

that

Greater

would

2003-2004

the

declined

in

accept

would

population

tonnes,

disposal

and

the

tippage

Ontario

perspective affecting

Province

per

permitted

and

continue

Southern

(ie.

Toronto

over

have

year

and

and

daily.

needs.

other

17

daily

fees

had

that

and

the

for

the

1.3

the

to at development Mine waste. the with 60. waste closed acute Ministry 59. options

58. 2004, expert 57.

Earth

project.

the

shortage

Site

stated

disposal Tech

to

group

B.4 The Amidst In One

for

City

Ontario

of

2002,

into

waste.36 option capacity not and wall hazardous This most A system; associated limit least landfill

Canada Ontario

conclusions

that

The such

the

of

significant retained

of

FUR

currently

of

a

the

waste

in the

of site

significant

Notre scaling.

the Toronto.

18

Environment

fully

RailCycleNorth waste.

waste

January

study

due

Ontario,

I

growing

Adams waste (e.g., cH.4

to of

most

has

million and

waste.

with

transfer

functioning by

to

did 24 approximately

disposal

receiving

was SE

received

2004.

of

volume

etc.);

significant disposal the

groundwater

the

construct

Notre months

the

Mine not

by

OF

the

the

Ontario

tones

This

prepared

time

Province

rail far,

facilities

and

possess

construct

THE

Enterprise

internal

capacity

Site

required

of

facility

consortium waste a

and were haul

and

waste

would required

the

certificate

approved

waste

waste ADAMS

as

the

20

no

known

by

required

the

interceptor

few GTA and

for

a

was

and

disposal

does

that waste

fully million

the

financing

be

Earth

management

disposal associated

moved

necessary

hauling

in

to: the

identified

external

MINE

required

would

to

broke municipalities

engineered

not disposal

number.

of

functioning

type

prepare

for

GTA the

Tech

approval

tones

facility

represent

forward

this system,

by

crisis

SITE Region, capable

restrictions

apart cause

financial

municipalities.

reports

in Canada

before

train.).

Essentially, transportation

capacity

facility with option

the

the

BY

and

and

facilities

after

waste

an

and

to

a

site

of is

and

course

in

1532382

an

short

immediate

therefore

and the

the

the

ready was It

Inc.,

resources seeing

(i.e.,

represents

other the

2003

annual

at

(dewatering

disposal

is

leachate

Adam’s growing

site

information

the

term

facilities Ontario

of estimated required

termination

a

rail

Adams

than

The

the and

ONTARIO

the

private

Adams

could

infrastructure

could

tonnage

car contingency

crisis

to

facility.

project

study.

a

solid report

Mine

collection

2004

demand

was

develop

systems,

disposal

that

and Mine

for receive

not

that

Mine

waste

if

available

non- experiencing

site.

of

The

rate

the

were

INC.

are the dated

through

pit

continue

at

negotiations

Site

for

Site:

border

the

consulting

uniform:

licensed

January

to

Adams

18

to

to

with

take

was

the

the

an

by

the

that

64.

stating

Environment

63.

October

00-PP-6040)

the

62.

complete

facility

assuming 61.

Letter

Notre.

uses

its Adams

from

PTTW

By

in

Notre

Renew

Permits

made by

1532382

30,

part:

the

its

able

which

Providing

within

local

As

Ministry ownership

suggest

definite taking,

October that

for

taking The

April,

Mine

2001.

letter

responded,

had

that

of

would

you site

Permit

the

to

to

PTTW

no

environment

the

PTTW

2004.

Ontario

be

Site

over

applied

Take

six regardless of preparations

had

appear

need

that commencement

of

30,

water local

Environment

reviewed

be

that

January

and

to

as

months

a

originally

we

2001.

application

Water

reviewed,

for

00-P-6040

Take

five

a

again

not

the

environment

for

Inc.

control,

was

waste

retain

the

of

to

year

a

Permits

details

remained

and

Water

15,

(“PTTW”)

of

purchased

taking.

and

by

new the

to

taken

have

disposal your

Notre,

been

2002,

with

the

the

period

Director

the

use,

was

of

requests

turn

PTTW

Mandated

of

an

approval

to

under dewatering

anticipated

application

remained

Enterprise prompt

January

issued

based

and

the

this

unchanged

immediate the

Take

are

and

the

facility

Ministry

David

by

cannot

Adams

taking

a

time

PTTW

on,

indicates Adams

15,

Water

to

approval,

Permit

letter

issued

by unchanged

2002

this Notre

required

EAB

began

limited

activities.

on

Hollinger,

commencement

be

or

and

from Mine

dated

of

are 00-P-6040,

new

file

promptly.

maintained

definite

to

Mine

Approval

the

that

the

on

so

taking

not

cover

in

and

your

Site

PTTW

January

a

Environment

long

November

uses no

the

from

renewal

Further, Site

issued

by

ask

need

into

date

original

Province

the

12

as

letter

ofAdams

being

the

application on

which

in

that

4,

the of

a

months

for

remaining

to

has

the

of

original

September

functioning

we

2002.

dated

water

you

reserve

details

this

1,

made

absence

the

submission, yet

had

of

expired

understand

2000

Mine

notify

Permit,

Ontario.

of

PTTW

The

been

January

promised

will

taking.

submission

of

of

water

water

steps

and

Site

of

Ministry

the

9,

the

waste

be

set

on

us

a

(PTTW

I

2002.

taking

expired

required

To

15,

to

disposal

prepare

2002

Notre

made

of

19

Upon

and

NO.

the

on to preparatory

65. 2003 for 2000, 2003. PTTW

PTTW, 67. 66. enclosed application. surrounding Jhidp. 5SCN9N.4’

Permit Letter Letter

the

to

stating

On remained

from Purchase from On In

Gartner

taking, 3 to

October the

The

Take

July

July

1996, that previously environment, Dewatering prior will 6040, understanding which at Please Certificate still intensive Specifically, on

November

Gordon

Gordon

Ministry

work

in

the the

accompanying

7. file

Lee

Water,

as

7,

in part:

the

be 2003

to

30,

unchanged

Notre oft/ic

same

but

with

Report. 200338, Adams

entailed

McGuinty

McGuinty force,

it could

commencement

accept

the

details

Permit

2004. monitoring

intended

of

did

planned.

of

the

rate 14,

of

Borderlands

same dewatering

had

the

July

and

Approval

be

not that the

the

Number

MOE.

remain Mine

again

2003,

this

temporary to

to

(0.3

of

Environment

from

4.

expert discovered

completed,

Ministry Enterprise

its Ministry

South

proceed

(at

all

to

2003,

this

There

m3/sec)

program

letter

corresponding

to

commence

in Site 4121-5SCN9N that

the

the

of

no

will

Director p.

environmental

taking, unchanged

as Pit

the

of of

4 original dewatering

is

originally

head

pumping

property 3250-4NMPDN at

mandated

Environment

Environment

in

was

be

submitted time as

course

that

anticipating

remains

that

issued

accomplished

previously

support

and

of previously

Hollinger.

operation

to

the

supporting

time.

the

monitoring

of

approved

install

granted a to

the

at

by

from

Government

appropriate.

enclosing

enclosing

an

Permit

report4°

an

the

tailings

the

EAR

This

of

uses

Application

that

approved.

ordinary

the

The end

as

approved

for

the Central

the

within

approval

documentation

to reapplication

by

to

a

application

Gartner being necessary dewatering

the of confirmed

plan

Enterprise

area),

waste

Take

the

application.

various

October.

The

original

of discharge

review

the

Ministry

The

Pit will

under

made Lee

for

Ontario

Water,

ofAdams

contingency and

disposal

12

and

remains

Report

instrumentation

a

discharge

be

mining

that

identified

month

could

PTTW

of demonstrates

PTTW

the fee,

of

followed submission.

is

of

of

Permit

It

an

the

dated

leases

July

the

presently

previous

site

water

the

Mine

period,

begin

is

Application viable.

from

companies

application

00-P-

7,2003

point

plan,

local

July

Environment

as

a

our

number

for Site

as definite

is

soon October

4,

in

with

2003

the

October

20

as

4121

lands

and for for

(“the need

30,

the

in

a

a 21

Borderlands”), were about to expire and began exploring the possibility of purchasing or leasing the Borderlands from the Govermnent of Ontario in order to support the Adams Mine 42Site.

68. Notre’s Certificate of Approval to operate the Adams Mine Site as a waste facility provided, as one of the conditions. that Notre purchase the Borderlands. The purchase condition in the Certificate of Approval read, in part:

Tailings Area

Prior to the receipt of waste for disposal at this Site, the Owner shall acquire legal access to the portions of the existing tailings area not currently controlled by the Owner (described in Schedule “A”, Item 16, Tab 1) and required for the management and discharge of surface water and the treatment and discharge of drainage layer effluent, including constructed wetlands and a constructed channel to direct treated leachate to the tailings pond upgradicnt of Dam #6 and subsequently into the Miserna River via Moosehead Creek.

69. On February 17, 2003, the Ontario Ministry of Natural Resources offered to sell the Borderlands to the Enterprise. Ontario had already completed a supplementary environmental review and obtained an independent property appraisal. The Enterprise accepted the offer, which stated, in part:

As outlined to you, our original offer to you for the lands was $96,000 plus GST and this offer included the trees situated on the lands. As discussed yesterday, due to concerns recently raised as a result of our supplemental environmental review we are prepared to (and you stated your agreement to) finalize the sale to you at this time for the appraised market value of the land only ($48,000.00) plus GST for a total price of $51,360.00. Please note that this offer will be valid for a period of three months from the date of this letter. [Emphasis in the original]

70. On April 10, 2003, the Enterprise delivered a certified cheque to the Ministry of Natural Resources, along with a covering letter 44stating:

Referring to your letter dated February 17, 2003, we enclose herewith the following:

1) Application for Crown Land executed in triplicate

Letter from Notre to Ministry of Natural Resources, October 1. 1996 Letter from Ministry of Natural Resources to Gordon McGuinty, February 17, 2003 Letter from Gordon McGuinty to Ministry of Natural Resources, April 10. 2003 2) The Agreement executed in Triplicate

3) Our certified cheque for S51,360.0O (includes S3,360 GST)

4) A copy of the Company’s Corporate Profile.

Trusting the above is sufficient to complete the transaction if otherwise, please advise. Please return a copy of the finalized documentation for our files, when executed and registered.

71. By tendering full payment on the Ministry of Natural Resources (Crown in Right of Ontario) acceptance of all conditions by the Province of Ontario, at law and/or in equity, the Enterprise was the owner in title of the Borderlands and had met the purchase of the Borderlands condition set out in the Certificate of Approval.

72. Contrary to its obligations under the agreement, the Ministry of Natural Resources failed to transfer title to the Borderlands. As a result, the Enterprise commenced action against the Province of Ontario in the Superior Court of Justice of Ontario of the District of Algoma on October 9, 2003 (Court File Number 4522368/A3). t did so only after having provided the Province of Ontario with the legally required 60 days notice before issuing its statement of claim, as required by the Proceedings Against the crown Act.

73. In its lawsuit against the Province of Ontario, the Enterprise sought the following relief, inter alia:

The [Enterprise] makes the following claims and requests the following orders as against the Defendant:

a. An Interim Declaratory Order that the [Enterprise] is entitled to receive immediate transfer from the [Province of Ontario] of the ownership in fee simple of all the lands set out in Schedule “A”, (the “Lands”), attached hereto;

b. A permanent Declaration that that the [Enterprise] is entitled to receive from the [Province of Ontario] an immediate transfer of the ownership in fee simple of all of the lands;

c. Damages for breach of an Agreement of Purchase and Sale entered into between the [Enterprise] and the [Province of Ontario] wherein the

Notice of Claim. by 1532382 Ontario Inc.. July 28. 2003 and Statement of Claim, Court File No. 22368/A3. October 9. 2003 23

[Province] was to transfer the lands to the [Enterprise]. damages being in the amount of $301,000,000.00:

d. Punitive and exemplary damages in the amount of $1.000,000.00;

e, Pre-judgment and post-judgment interest pursuant to the Courts of Justice Act and Rules of Practice in effect in Ontario

f. Such further and other relief as this Honourable Court deems appropriate in the circumstances.

74. The Attorney General for Ontario filed a Statement of Defence on November 18, 2003.36 stating baldly that there was no agreement between the Enterprise and Ontario and that the Enterprise did not suffer any damages.

75, On March 3, 2004, the Enterprise served a motion for Summary 47Judgment before the Ontario Superior Court of Justice, seeking, inter a/ia:

Partial summary judgment in the form of a Declaratory Order that the [Enterprise] is entitled to receive immediate transfer from the [Province of Ontario] of the ownership in fee simple of all of the [Borderlands].

76. The motion was scheduled to be heard on March 11, 2004 but was adjourned at the request of the Province of Ontario.

77. The Liberal Party of Ontario was elected as a new provincial government in October 2003. During the election, David Ramsay, the incumbent Liberal candidate for the area where the Adams Mine Site is located, pledged to put the project “to bed once and for all” and stated that “we’ve got to kill that 48project.”

78. After Mr. Ramsay was appointed Minister of Natural Resources, on October 23, 2003, he fomented a political crisis and threatened to resign from Cabinet unless the Province of Ontario terminated the Adams Mine 49project. This manufactured crisis reached its climax after the Enterprise’s Permit to Take Water was issued by the Ministry of Environment on November 14, 2003.

Statement of Defence, Court File No. 22368/A3, November 18, 2003 Motion Record of 1532382 Ontario Inc. re: Summary Judgment, returnable March 11, 2004 Northwatch News, “Northeast Goes Tory-Free in Liberal Election Sweep”, URL: http:/!www.web.ca/-.nwatch/nwatchnews/NN Fall 2003 .PDF, accessed June 23, 2008 Benzie, Robert (Nov. 19/03) “Ramsay vows to quit if mine plan proceed”. . 24

79. The exact nature of the process undertaken by the new government in Ontario is unknown to the Investor and Enterprise who will seek full production and discovery during the course of the arbitration.

B. 6 THE ENACTMENT OF THE ADAMS MINE LAKE ACT

80. Unexpectedly and without warning the new government introduced and gave First Reading to Bill 49 on April 5, 2004, “An Act to Prevent the Disposal of Waste at the Adams Mine Site” (“Bill 49”), which is a modern day bill of attainder.

81. The Bill was introduced less than six months after the new government was elected. The bill was introduced without any notice or consultation, even without the required notification required pursuant to the Ontario Environmental Bill of Rights which provides:

Proposals for policies and Acts

15. (1) If a minister considers that a proposal under consideration in his or her ministry for a policy or Act could, if implemented, have a significant effect on the environment, and the minister considers that the public should have an opportunity to comment on the proposal before implementation, the minister shall do everything in his or her power to give notice of the proposal to the public at least thirty days before the proposal is implemented. 1993, c. 28, s. 15 (1).

Exception ) Subsection (I) does not apply to a policy or Act that is predominantly financial or administrative in nature. 1993, c. 28, s. 15 (2).

82. No studies were published and no internal analyses were released regarding Bill 49.

83. In the provincial debates that followed, , who is currently the Minister of Finance of the Government of Canada but was then an opposition member of the Ontario Legislature, commented on Bill 49 on May 3, 2004:

I’m pleased to have an opportunity to speak to [Bill 49j today. It’s an important bill, not particularly because it deals with the Adams mine, but because of the principles that are being violated by this bill relating to the property rights of individuals and corporations in the province of Ontario A huge process was followed: experts on all sides all kinds of evidence, the whole thing according to the rule of law, according to the rules in the 25

province of Ontario. A conclusion was reached. Today, the Liberal government comes before the Legislature and says we should throw all that out the window. ... Then they say, “Oh. OK. compensation. You might want some compensation because we’re changing the rules retroactively, which has substantial financial consequence. You were successful in your application when you followed all the rules back in 1998, six years ago. Now we’re changing the rules. We’re going to limit what you can do. We’re going to say that you lose the fundamental right, which people have in the province of Ontario, to go to court” — Magna Carta, redress, the opportunity, the fundamental principle of the rule of law, that people who have suffered harm at the hands of others may go to court and seek redress. But the Liberals won’t even give them that. They retroactively changed the law vis-à-vis the environment and then they said:” “We won’t let you go to court. We’re going to tell you the kind of compensation you’re entitled to. You’re not going to be allowed to take legal proceedings,” and so °5on. 84. John Baird, the current Minister of the Environment of the Government of Canada and then a member of the Ontario Legislature, stated on May 5, 2004, the following in opposition to Bill 49:

I have some very serious concerns with respect to Bill 49 and they’re twofold. The first concern is with respect to property rights and the second concern is with respect to the political nature of the approval of garbage disposal that this government is engaging in. I’d like to talk first, if I could, about property rights. Section 5 of this bill is outrageous. It says that individuals involved in this dispute can’t even seek the remedy of the courts, that they can’t even seek legal recourse for any dispute. I think property rights are incredibly important. They’re every bit as important as the other rights enumerated in our Charter of Rights and Freedoms. I’m disturbed by this government’s attempt to use legislation to curtail law- abiding citizens’ views and their intervention into the legal process.

Norm Sterling, . . .[isj not just a lawyer, he’s not just an engineer, a former Attorney General and a former Minister of the Environment, but someone who I think most members on all sides of the House would acknowledge has certainly followed environmental issues for many years. ... He spoke of the political meddling involved in this bill. I’m glad to see the member for Timiskaming here. This bill, among some, has been called the “David Ramsay Career Protection Act,” because David Ramsay made commitments and the government is bailing him out from certain electoral defeat on this issue. As Mr. Sterling said, the government wants to throw

°° Hansard Excerpt, May 3, 2004 26

aside proper and due process and inject its political will on the people of Ontario. Section 5 of the bill extinguishes the right of the proponent to legal recourse with regard to what the government has done for this Very political process, and that does cause those of us on this side of the House substantial concern.

85. Bill 49 was enacted on June 17, 2004. It received Royal Assent on the very same day and was immediately proclaimed in force. The effect of Bill 49 was far reaching, cancelling all of the environmental approvals that had been obtained or were pending, Section 3(1) thereof stating:

The following are revoked:

1. The approval dated August 13, 1998 that was issued to Notre Development Corporation under the Environmental Assessment Act, including any amendments made after that date.

2. Certificate of Approval No. A 612007, dated April 23, 1999, issued to Notre Development Corporation under Part V of the Environmental Protection Act, including any amendments made after that date.

3. Approval No. 3250-4NMPDN, dated July 9, 2001, issued to Notre Development Corporation under section 53 of the Ontario Water Resources Act, including any amendments made after that date.

4. Any permit that was issued under section 34 of the Ontario Water Resources Act before this Act comes into force in response to the application submitted by 1532382 Ontario Inc. for New Permit #4121- 5SCN9N (00-P-6040) and described on the environmental registry established under the Environmental Bill of Rights, 1993 as EBR Registry Number XAO3EOO19.2004,

No permit for spec Uled application

(2) No permit shall be issued under section 34 of the Ontario Water Resources Act after this Act comes into force in response to the application referred to in paragraph 4 of subsection (1).

86. Bill 49 went on also to extinguish the agreement of purchase and sale to purchase the Borderlands in Article 4 thereof

4. (1) An agreement entered into by Notre Development Corporation or 1532382 Ontario Inc. after December 31, 1988 and before this Act comes

Hansard Excerpt, May 5, 2004 27

into force is of no force or effect if the agreement is with the Crown in right of Ontario and is in respect of,

(a) the purchase or sale of the lands described in Schedule I or any part of those lands;

(b) the granting of letters patent for the lands described in Schedule 1 or any part of those lands; or

(c) any interest in, or any occupation or use of, the lands described in

Schedule 1 or any part of those lands.

SCHEDULE 1

The lands described as:

Location CL 411-A, Boston Township, District of Timiskarning, containing 387.48 hectares;

Location CLM 104, McElroy Township, District of Timiskaming, containing 238.72 hectares;

Parts 1, 2, 3, 4, 5, 6, Plan 54R-2947, Boston Township, District of Tirniskaming, containing 14.58 hectares;

Parts 1, 2, 3, Plan 54R-1694, Boston Township, District of Tirniskaming, containing 18.76 hectares;

Location CL 936, Plan TER-670, Boston Township, District of Timiskaming, containing 33.46 hectares;

Parts 1, 2, Plan 54R-1807, Boston Township, District of Timiskaming, containing 37.10 hectares;

Parts 1, 2, 3, Plan 54R-1693, Boston Township, District of Timiskaming, containing 12.12 hectares;

Parts 1, 2, Plan 54R-2322, Boston Township, District of Tirniskaming. containing 18.69 hectares;

Part 1, Plan 54R-l540. Boston Township, District of Timiskarning. containing 14.48 hectares;

Location CL 1584, Part 1, Plan 54R-151 1, Boston Township, District of Timiskaming, containing 16.06 hectares;

Location CL 1221, CL 1222, Parts 1, 2, Plan 54R-1291, McElroy Township, District of Timiskaming, containing 34.02 hectares; in above:

87.

the

Statement

Bill

Application Township, containing Location Enactment person against Parts Mine whole the of Executive Extinguishment provision before (2) respect (3) Same (5) from lands 5. Same subsections to (4) section to

49

in the in

(1)

also

lands

Without

Subject Subsections

No

subsection

subsection

1.

described

site

any

of

Crown

or

this

Any

referred

the 35 of

2,

terminated

cause

in Claim

CL

or

of

described

3, any

Council, of aboriginal

43.28

District

Act

of

Crown

part,

cause

to

apply

the

this

Plan

limiting

the

this

in

1220,

representation

section

comes

of

in of

to

lands

that

(1),

right

(1), (1) Act.

Constitution from hectares.

Act

54R-l619,

of

action Schedule causes

to

in

in

of

the

or

and in

Parts and action

was

as

a

right

subsection

Timiskaming,

the or

described

of

into

anything 6,

an

cause cause

Schedule

a

no

treaty Ontario

(2) no

arises

of

generality employee issued

direct

force.

of

1,

that

cause

action

1

compensation

do

McElroy

or

of of Ontario,

Act,

2, is

that

right

exists other

after

in hereby

not

or action

action

(1)

on

3,

in

1

of

Schedule

1982.

indirect

if

4, respect

occurred containing

or

October apply

in of

action

this that

conduct,

on

the

Township.

a

5, agent

including,

respect

in extinguished. subsections

member

the

6,

Act

cause respect

is

to

is

arises

result

of

1.

day

7,

or recognized

payable after 9,

a

the

that comes

of

102.62

cause

Plan

2003 former

of

this

or

District

against

without

of the

of

Adams

December

is

action

(1),

former

the

any

Act

related

54R-1292,

by

Adams

of in

into

hectares;

employee

(2)

enactment

the

action

a

and

a

agreement,

of comes

limitation, Mine

would

person

force

person

member

and

Timiskaming,

circumstances

to

31,

Mine

affirmed

the

that

site

(4), into

against

McElroy

1988

or

arise,

referred referred

Adams

of

site

of or

arises

agent

those the

force

or

any and

the the

by

or

in

in

relief

a

described

sought

28 29

(6) Without limiting the generality of subsections (1), (2) and (4), those subsections apply to a cause of action arising in contract, tort, restitution. trust, fiduciary obligations or otherwise.

Legal proceedings

(7) No action or other proceeding shall be commenced or continued by any person against a person referred to in subsection (I) in respect of a cause of action that is extinguished by subsection (1) or a cause of action that, pursuant to subsection (2) or (4), does not arise.

Same

(8) Without limiting the generality of subsection (7), that subsection applies to an action or other proceeding claiming any remedy or relief, including specific performance, injunction, declaratory reliet any form of compensation or damages, or any other remedy or relief.

Same

(9) Subsection (7) applies to actions and other proceedings commenced before or after this Act comes into force.

88. Bill 49 also included a provision declaring that the statute itself does not constitute an expropriation, even though it constitutes an expropriation or conduct tantamount to expropriation at international law:

5(10) Nothing in this Act and nothing done or not done in accordance with this Act constitutes an expropriation or injurious affection for the purposes of the Expropriations Act or otherwise at law.

89. The amount of compensation under the Statute was unduly limited and in no manner compensated the Enterprise, stating, inter alia:

Compensation

6. (1) The Crown in right of Ontario shall pay compensation to 1532382 Ontario Inc. and Notre Development Corporation in accordance with this section.

Amount

(2) Subject to subsection (3), the amount of the compensation payable to a corporation under subsection (1) shall be determined in accordance with the following formula: 30

A+B+C

where,

A = the reasonable expenses incurred and paid by the corporation after December 31, 1988 and before April 5, 2004 for the purpose of using the Adams Mine site to dispose of waste,

B = the lesser of.

i. the reasonable expenses incurred by the corporation after December 31, 1988 and before April 5, 2004, but not paid before April 5, 2004, for the purpose of using the Adams Mine site to dispose of waste, and

ii. $1,500,000, in the case of Notre Development Corporation, or $500,000, in the case of 1532382 Ontario Inc.,

C = the reasonable expenses incurred by the corporation on or after April 5. 2004 for the purpose of using the Adams Mine site to dispose of waste, if the expenses arc for legal fees and disbursements in respect of legal services provided on or after April 5, 2004 and before this Act comes into force.

Same

(3) The amount of the compensation payable to 1532382 Ontario Inc. under subsection (1) shall be the amount determined for that corporation under subsection (2), less the fair market value, on the day this Act comes into force, of the Adams Mine site.

90. Bill 49 also specifically states that no payment will be made for any loss of goodwill or possible loss of profits:

Loss of goodwill or possible pro!Its

(8) For greater certainty, no compensation is payable under subsection (1) for any loss of goodwill or possible profits.

91. The intent of Bill 49 was clear and beyond dispute: to eliminate the Investment as a solid waste landfill site and to destroy its value for the Enterprise, while preserving its title in order to ensure that any ongoing liabilities in respect of the land would be borne by the Enterprise rather than the Province of Ontario. The statute specifically:

a. Revoked each of the certificates of approval and licenses that the Enterprise held to operate the Adams Mine Site as a waste disposal site:

context

conclusive

authentic

and

in

95.

restated

international

94.

Article

provides

applicable

with

93.

C.

since

92.

good

in

the

THE

passage

the

The

in

Construed

NAFTA

Interpretation

102(1).

f e.

d.

c.

in b.

faith

The

NAFTA

expression

which

that

Articles

of

light

rules

any

and

the

Restricted Extinguished

was

Court

NAFTA

Extinguished

applicable Cancelled

cancelled

Terminated

Government

the

law’

in

of

NAFTA

future,

recovery

specifically

before

of

accordance Article

the

Bill

of

obligations

of

within

and

31

includes

its

subject

international

Justice

AND

of

49.

the

of

and

the

including

damages

stated

rules

the

the

the

the

1131(1)

provisions

the

the on

all

Permit

the

binding

of

32

applicable

Court

APPLICABLE

application

text

limited

the

parties’

NAFTA proceeding

with

of

other

the

Ontario

context

owed

object

of

Enterprise’s

treaty

basis

andior

appears

the

recourse

provides

to

customary

on

the

law

agreement

causes

by

Take

recovery

Vienna

a

and

shall

intentions.

of

has

of

ordinary

interpretation

rules

Motion

a

and

compensation,

Articles

process

party that

goodwill

and

purpose.

Water

failed

under

of

that

be

causes

in

of

convention INTERNATIONAL

action

had

the international

for

to

For

to

a

light

interpreted

international

meaning

to

that

for

the

sell

tribunal

102(2)

object

a

future

been

The

or

pay

Summary

treaty.

of

that

The

the

Province’s

the

of

require

had

loss

action

ordinary

commenced

any

limiting

and

the

issuance

and expenses

the

Borderlands

on

text

been

to

shall

of

Such

law

and

compensation

the

be

purpose

objectives Enterprise

profits.

that

1131(1),

law.

Judgement;

of

that

issued

decide

given

Law

Expropriation

rules

meaning

applied

the

the

meaning

of

the

and

LAW

had

NAFTA

on

the

of

costs

treaty

of

NAFTA

to

in

to the

issues

of

liabilities

Treaties. either

October

of

been

the

November Permit

the

its

in

term

treaty

of

to

is

that

the

treaty

is

Enterprise:

terms

Article

in

accordance

also

the 1532382

made

had

presumed

Act;

shall

NAFTA

‘applicable

could

dispute

To

9,

on

interpretation,

text

informed

in

or

in

2003

Take

2003;

and

the

in

be

question. ¬

102(2)

would

their

be

is

Ontario

its

accordance

interpreted

site

set

and

Water

to

normally

recovered

with

Superior

rules

context

by be

and have

further

out

which

31

the

the

Inc.

the

and

for

as

of

in in 96. NAFTA. Articles manner territories 97. enterprise also competition of 98. predictable claims claim bring consistent 99. and

NAFTA

investment

provides

a

to

brought

NAFTA Jurisdiction

Because The As

claim

consistent

1101,

arbitration

of

with

has

Article

through such, (a) disputes; (d) of, (f) (e) (c) (b) cooperation this Parties; intellectual favoured-nation

1.

Chapter Tribunal’s

commercial

in

the

to

the

The

goods

promote eliminate

establish

suffered create increase

1116

by

environmental

in the

provide

Agreement,

Article

arbitration

the

the

Parties,

context

the

investors

with

1122

objectives

free

over

its and/or

and NAFTA

11

and on

terms

effective

territories

jurisdiction

property

to conditions

arising

by substantially

the

102

principles

a

behalf barriers provides trade

Claims

services

adequate the

within

framework expand

framework

a

for

of

treatment NAFTA’s

1117

of explicitly

Party.

for

‘object

contains

NAFTA

protection area

another

loss

of

procedures

out

of rights

of

under

which

to

and its

between

and

that

this of

to the an

of

or

trade

and and

and

Article

joint

and

investment

fair

hear

and

1122.

enhance damage in delineates

a

enterprise

object

Parties. for for

the

Party

Chapter explicit

Agreement,

its

Chapter

breach substantially

each

rules,

and

competition in,

purpose’

effective

transparency,

a

further provisions

the

NAFTA

administration

for business

claim

1117

and

under Article

and

conservation.”

Party’s

territories

it

the the

objectives,

of

1

including

has

11

its opportunities

facilitate

J of

purpose,

permits

trilateral, under

benefits

Section

implementation

Article of

object

are

protection

Parties

another

1116 as suffered

territory; planning

are increasing in

the

to

are

elaborated

the

NAFTA

of

to

treaty

permits an

the

and

be

and 1116 or

national A

of

such the

to:

proactively

free be

regional

Party

investor

arising

promoting of

this

construed

cross-border

purpose.

in

Parties;

interpreted,

and

for

and

and/or

is

NAFTA trade

as

investment

the

Chapter

Agreement.

an

clear.

and

for

more

promoting

the

treatment,

out investment..,

territories investor enforcement

and

of

area;

Article

loss

application

consent

resolution It

in

of

and

another

Chapter

The

multilateral specifically

Il

provides:

a movement

a

including

or

opportunities protecting

breach

broad

is

of

NAFTA

1117.

conditions

damages

established

of

most-

to

another

Party

11 the

in

arbitration

of of of

and

of

ensuring

by

a

to Section

preamble

fair

remedial

a that Party

manner

bring

of

32

Party.

in

under

trade

fair

the

the

“a

of

to

A

a

investments

treatment

which

corporation

are

104.

an

association

Article

same

another

the

103.

investor

whenever

102. investors

purpose

101.

fair

indicated

100.

enterprise

issues

scope

competition

provision,

constitutes

Article

NAFTA

NAFTA

201

NAFTA

NAFTA

NAFTA

NAFTA

of

of

and

of

above,

and

of

a

another

of (c)

constituted and (b)

relating

(a)

provides

1

is

the

in

the

measure

of

fact

the

1105:

demonstrated

This

full

with investors

to

investments

NAFTA.

Article

its

another

Chapter

Article

Article Article

in

Article

an

like

‘investment’ Party

Party.

their

to

protection

Party

the

to:

territory.

respect

Chapter

enterprise

Treatment

that

be

all

directly

or

territories

who

1117

investments

of

Party

1101

1139

determined

NAFTA

11

1105 1101

owns

‘enterprise’

organized

which

another

of

to

by

has

applies

provides

provides

provides

Articles

that

and

as

investors

establishes

is

or

reaffirms

affects

in

Whether

possession

is

made,

defined

of

Accordance

defined

provisions

controls

the

Party;

intended

security

under

the

based

to

in

includes

that

investor

an

that

1106

NAFTA

that

is

measures

the

of

above.

enforced

Canada’s

the

as

in

the

investor

making

an

another

of

upon

the

to

an

territory

to

and

its

the

including

laws

investor

a

with

scope

a

American

promote

Chapter

either

terms

investor

corporation

territory Parties.

majority

1114,

the

adopted

of

or

International

Party

of

by

obligation

of

evidence

a

must

of

owns

seeks

of

another

all

Party.

application

way

both broadly

opportunities

of

Article

another

of

a

in

of

and

investments

Party

be

or

another

another

or

or

the

to

the

real

of

construed

maintained

partnership,

controls.

Mexican

make

on

Party,

territory

to

applies

Law

issued

1101

may

treaty

NAFTA

property

the

provide

for

NAFTA

Party

an

bring

provides,

or for

record.

in

NAFTA

shares

to

or

in

investment.

nationals

Ownership

of

the

an

includes

investment

by

measures

joint

light

Party.

the

a

through and

fair

Party,

investment

territory

claim

a

of

Party;

Ownership

in

venture of

Party

Chapter

an

and

a

relevant

the

and

a it

Accordingly,

corporation. on

enterprise.’

and

re1ating

customary

falls

national

and

Under

equitable

object

behalf

to

or

control

that

11.

within

ensure

their

part:

other

of

the

and

to’

of

an

As

of a 34 international law, the fair and equitable treatment standard establishes a floor below which no State conduct shall fall. Application of the standard is normally dependent upon a detailed appraisal of the factual context, but in no case can a State satisfy its obligation to accord fair and equitable treatment by providing only a ‘minimal’ level of treatment, rather than the ‘minimum’ that is required under customary international law and NAFTA Article 1105.

105. The State’s obligation to accord fair and equitable treatment is not fixed in time. The content of the standard continues to evolve, as expectations reasonably held by the international investment community increase over time. Under Article 1105, Canada is required to act in accordance with the customary international law principle of good faith; to provide a stable, transparent and predictable regulatory and business environment for foreign investment; and to accord both substantive and procedural due process in exercising its legislative, judicial and administrative functions.

Article 1/JO: Expropriation

106. As Article 1110 of the NAFTA explicitly provides, “no Party may directly or indirectly expropriate an investment of an investor of another Party in its territory or take a measure tantamount to the expropriation of such investment except for: a public purpose; on a non discriminatory basis; in accordance with due process of law; on payment of compensation.”

A measure constitutes an indirect taking or act tantamount to expropriation when it substantially interferes with the investor’s ability to derive the full economic benefit of its investment in the host State.

107, Canada breaches its obligation under Article 1110 when it enacts a measure that constitutes an indirect expropriation or an act tantamount to expropriation but for which it has either failed to pay compensation to the investor or has failed to pay compensation that is “equivalent to the fair market value of the expropriated investment immediately before the expropriation took place” or where has failed to pay compensation that does not “reflect any change in value occurring because of the intended expropriation and valuation criteria must include going concern value, asset value and such other criteria as appropriate to determine fair market value.” Canada must also ensure that expropriatory measures are executed in accordance with due process of law; arc not otherwise discriminatory or not for a public purpose. 35

108. A measure constitutes an indirect taking or act tantamount to expropriation when it substantially interferes with the investor’s ability to derive the full economic benefit of its investment in the host State.

Damages

109. Under customary international law, which constitutes applicable international law under

Article 1131(1), Canada is required to make full reparation for the harm caused to the Enterprise, placing it in the position it would have been in but for Canada’s breach of NAFTA Article 1105

and/or Article 1110. Under customary international law, the standard of compensation for a breach of Article 1105 may be the same as the compensation stipulated under Article 1110(2). In circumstances such as the instant case, the only appropriate compensation for total deprivation of one’s enjoyment of the intended use of an investment is payment of fair market value of that investment as of the date immediately before the measure was enacted and harm caused thereby.

D. APLICATION OF THE NAFTA AND INTERNATIONAL LAW TO THE FACTS OF THIS CASE

Jurisdiction

110. Mr. Vito Gallo is a national of the United States of America. He therefore qualifies as an investor of another Party with respect to Canada. Mr. Gallo owns 100% of the issued common

shares of the Enterprise, 1532382 Ontario Limited. The Enterprise was constituted and is organized under the laws of Ontario. The Enterprise therefore qualifies as an investment in the territory of Canada. At all relevant times, the Enterprise has owned and controlled the lands that form the subject of this claim, i.e. the Adams Mine Site, as well as all of the Certificates necessary to permit the establishment and operation of the Landfill Site.

111. This claim has been brought by Mr. Gallo on behalf of the Enterprise. under NAFTA Article 1117, for loss and damage suffered by the Enterprise arising from imposition of Bill 49. and the steps taken by the to frustrate and delay the Enterprise’s ability to operate or obtain returns from its investment, including the Government’s failure to honour its good faith obligation to transfer the Borderlands to the Enterprise pursuant to the contract between them. Accordingly, the Tribunal has jurisdiction to hear the claim. 36

Article 1105

112. The measure purports to deny all access to the Courts of Ontario for vindication of a claim for damages concerning the Adams Mine Site. The measure thus constitutes a prima fade denial of justice, contrary to customary international law generally and the standard of fair and equitable treatment in particular, contrary to NAFTA Article 1105. In no uncertain terms, Bill 49 was contrived to deny the Enterprise from having sits day in court’ in respect of the destruction of the investment.

113. At the time the investment was acquired, there was no reason to expect that the Government of Ontario would not abide by the terms of the Certificates its own officials had lawfully and properly issued for its operation as a waste landfill, or to perform the undertakings provided under contract to the Enterprise for transfer of the Borderlands. No foreign investor could have reasonably anticipated that the Government of Ontario would abrogate each of those Certificates by legislative fiat, well aware that investments had been made in reliance upon the existence of those Certificates and undertakings.

114. Such conduct constitutes an obvious failure by Canada to accord fair and equitable treatment to the Enterprise, because the Enterprise was entitled to reasonably expect that it could rely upon the good faith of the Government of Ontario in respect of the permits that had been issued for operation of the investment.

115. Moreover, no foreign investor should have expected that the Government of Ontario would engage in tactics of obfuscation and delay, impairing the Enterprise’s ability to obtain redress before its courts, while drafting legislation that would purport to annul any right to redress in its entirety. Such conduct constitutes a breach of the customary international law standard of fair and equitable treatment because it demonstrates a lack of good faith.

116. It was also not unreasonable to expect that the Government of Ontario would negotiate and honour its obligations, in good faith, transferring the Borderlands it had promised in sale to the Enterprise, for expansion of the Adams Mine Site. The Government’s conduct in this regard further demonstrates a lack of good faith contrary to the general international law principle of good faith and the principle of transparency referenced in NAFTA Article 102(1), both of which inform the standard of fair and equitable treatment set out in Article 1105. Such conduct 37 accordingly further breached Canada’s obligation to accord fair and equitable treatment under Article 1105 and under customary international law.

117. It is not necessary to establish that substantial interference or total deprivation has occurred to establish liability under Article 1105. Any level of unlawful interference is prohibited under international law. Nonetheless, in this case the measure does totally deprive the Enterprise of the highest and best use of the Adams Mine Site, which was also the basis upon which the investment was established: as a fully-permitted mega landfill waste treatment site.

Article 1110

118. The purpose and effect of the measure was to totally deprive any owner of the Adams Mine Site of the right to operate it as a waste landfill facility. Bill 49 also reduced the asset value of the investment to a negative amount, and in no case more than nil, because of taxes and the ongoing costs associated with maintaining the site.

119. While the Government of Ontario could have directly expropriated the investment with its measure, it did so indirectly for one simple reason. By leaving title to the Adams Mine Site with the Enterprise, the Government was able to encumber the Enterprise with the on-going costs of maintaining the site. The intent behind the measure was to definitively limit any compensation payable under domestic law, while nonetheless ‘killing the project.’ The measure is accordingly an indirect expropriation and a measure tantamount to expropriation under NAFTA Article 1110 and customary international law.

120. Article 1110(l)(a) provides that a measure must be imposed for a public purpose. Bill 49 was not implemented for a public purpose because it was not a measure of general application and was issued contrary to the principles of economic efficiency and sustainable development. Article lllO(l)(a) provides that a measure must not be discriminatory. Bill 49 is discriminatory because it was targeted specifically at the Enterprise and the investment, rather than at the industry generally.

121. NAFTA Article 11lO(l)(c) provides that a measure must be imposed in accordance with due process of law. Bill 49 purports to eliminate all claims for damages that might lie for the Enterprise under domestic law and purports to relieve the Government of Ontario from its 38 obligations to produce witnesses in any domestic legal proceeding arising in respect of imposition of the measure or its application to the Adams Mine Site. As such, the measure is designed to completely deprive the Enterprise of any kind of due process rights under domestic law.

122. Finally, NAFTA Article 1110(l)(d) provides that an expropriatory measure must not be imposed without payment of compensation in accordance with Article 1110(2). To be clear, Article 1110 provides that compensation must be paid regardless of whether the measure was for a public purpose, was not discriminatory and was in accordance with due process of law. The provision clearly states that compensation must be paid in the event of a finding of expropriation, whether direct or indirect. Article 1110(2) also establishes that valuation criteria shall include “fair market value,” which obviously contemplates recognition of lost future cash flows as part of the valuation ana1ysi. Bill 49 directly contradicts Article 1110(2) by specifically provides that “no compensation is payable ... for any loss of goodwill or possible profits.”

123. That the measure constitutes an illegal expropriation, contrary to Article 1110 and customary international law, is not seriously in question. The Government of Ontario’s has admitted as much by publicly proclaiming, with imposition of the measure, that it the measure could not be considered an expropriation under its own law.

Damages

124. The fair market value of the Investment, as it existed on June 3, 2004, must be determined on the basis of the Investment’s highest and best use. Its best use was as a high volume, waste-by-rail, landfill disposal facility. The value of the site resided in its right to accept waste and the extent and density of its “air space” as defined by its certificate of approval. The volume established by the Adams Mine Site certificate of approval was 1,341,600 tonnes per year. This amount constituted a “mega landfill” disposal facility, as understood in the waste management industry.

125. In Ontario, both today and at all relevant times, demand for waste disposal has far exceeded the supply. Permitted mega landfill disposal facilities are readily saleable and a market exists for them both within the vicinity of Toronto and throughout North America. Because high 39 barriers to entry characterize the market for waste landfill facilities in North America. permitted air space is considered within the industry to be a scarce commodity with very high demand.

126. The introduction and subsequent passage of the Adams Mine Lake Act destroyed the fair market value of the permitted air space for the Adams Mine Site by canceling the Certificates of

Approval and all other permits that had been granted for its operation as a waste landtill facility.

The measure did not provide for compensation to the Enterprise or the Investor. Instead, it statutorily barred the payment of just compensation on a timely basis and purported to remove all causes of action for such compensation under applicable domestic law.

127. The estimated fair market value of the investment, as of the moment immediately before the measure was announced, is US$355,100,000.00.

E. THE ISSUES

128. There are three issues in this claim:

(i) Does the measure breach Article 1105 by arbitrarily depriving the Enterprise from recourse to a civil court for the loss and damage it causes?

(ii) Does the measure breach Article 1105 because Canada failed to provide the lnvcstor and Enterprise with a transparent and predictable regulatory environment upon which to establish and maintain the investment?

(iii)Does the measure indirectly expropriate the investment by depriving the Enterprise of its use without payment of prompt, adequate and effective compensation contrary to Article 1110(2)?

F. RELIEF SOUGHT AND DAMAGES CLAIMED

129. The Investor claims damages on behalf of the Enterprise for the following:

a. Payment of not less than US$355,100,000.00 as compensation for the damages caused by, or arising out of, Canad&s measures that are inconsistent with its obligations contained in Part A of Chapter 11 of the North American Free Trade Agreement;

b, Out-of-pocket costs incurred by the Enterprise in opposing imposition of the measure:

c. Compensation for any on-going or future liabilities arising from the Adams Mine site including, without limitation, for its environmental remediation;

Date

of

g.

f.

e.

d.

Service:

appropriate.

Such

Tax

Pre-award Costs

les

consequences

and

associated

June further

disbursements.

and

73

relief

post-award

2008

with

to

maintain

as

the

counsel

expropriation,

compound

the

integrity

may

interest

advise

these

of

at

the

Counsel

(202)

(202)

London.

proceedings,

Barrister

Ti.

12-20

(416)

(416)

Toronto.

94-3

Barrister

Murdoch

(416)361-1530

(416)

Charles

Toronto,

36

Barristers

a

BENNETT

and

award.

rate

,1

Toronto

Lerson

3

403-3597

517-1597

14

964-2

433-2890

361-3319

Hazelton

that

to

to

Valley

Ontario

M.

&

Ontario

&

be

R. Ontari-MC

the

and

Solicitor

the

Solicitor

Gastle

Street.

fixed

GASTLE

Martyn

28

including

Weiler

Investor

Solicitors

Run

(Fax) (Fax) Avenue

Ext

Tribunal

(Fax)

N6G

by

M5R

Suite

Blvd.

222

the

5N8

RC.

all

2E3

2C5

Tribunal.

250

professional

may

40 deem 41

COPY TO:

Office of the Deputy Attorney General of Canada Justice Building 284 Wellington Street, Ottawa, Ontario KIA 0H8 41

COPY TO:

Office of the Deputy Attorney General of Canada Justice Building 284 Wellington Street, Ottawa, Ontario K1A 0H8

Article

currency

compensation

exchange

paid

5.

until

at

4.

3.

and

going

of

intended

expropriated

2.

(d)

(c)

(b)

(a) tantamount

(“expropriation”),

investment

owing

it

2.

investors each

1.

treatment

treatment

Article

1.

a

adopts

expropriation”),

commercially

other

on

the

Party

concern

1110:

If

If

Compensation

to

Compensation

the on

in

on

for

No

Without

Each

date

at

1105:

expropriation

a

payment

prevailing

or

criteria,

armed

accordance of

payment

and

in

a

the Party

date

a

Party

shall

of

to

maintains

nondiscriminatory

another

public Expropriation

investment

of

accordance

Party

owed

an

value,

nationalization

market

full

Minimum

of actual

conflict

prejudice

elects

accord

may

investor

reasonable

as

payment,

is

except:

protection

and

shall

purpose;

of

on

on

appropriate,

made

Party,

asset

with

shall

rate directly

payment.

shall

compensation

relating

the

had

to

that

shall

to

immediately

or

accord

with

pay

of

Standard

date

of

value

to

investors

in

due

become

nondiscriminatory

be

date,

civil

be

if

not

and

another

paragraph

APPENDIX

rate

exchange

a

and

in

or

international

paid

converted or

equivalent

to

G7

process

basis;

of

to

reflect

a

strife.

including

expropriation

shall

indirectly

to

Compensation

losses

for

security.

expropriation

currency

currency,

investments

without

known

determine

of

Party of

in

that

before

be

another

prevailing

of

any

accordance

Treatment

suffered

1

into

no

currency

to

and

law

declared

“A”

in

earlier.

nationalize

law,

other

delay

change

the

less

the

compensation

a

its

notwithstanding

and

treatment

fair

of

G7 Party,

of

fair

including

territory

expropriation

had

than

by

than

and such

on

investors

Article

market

Valuation

currency

from

with

in

tax

investments

market

been

that

and

if

be

value

a

an

or

value

the

G7

with

the

paragraphs

fully

or

date,

expropriate

investment

to

value.

1105(1):

fair

converted

shall

amount

currency,

value

of

take

date occurring

at

investments

criteria

respect

of

realizable.

and

another

took

Article

the

and

tangible

in

include

a

of

of

market

measure

equitable

its

interest

and

place

expropriation

of

2

the

into

shall

to

the

an

through

territory

because

1

Party

measures

108(7)(b),

interest

property,

of

amount

that

(“date

rate

include

ad

G7

of

6. the accrued expropriation Article creation 6. the revocation, grounds (intellectual in measure 7. expropriation 8.

relation

debt.

On This

For

1109.

at

of that

of

a to

payment,

intellectual

purposes

general

limitation

commercially Article

Property).

the

intellectual

until

of

measure

debt

the

application

does

compensation

of

security

or

date

property

this

creation

property

not

imposes

reasonable

of

Article

apply

payment. or

shall

rights,

loan

is

rights,

costs

to

shall

and

consistent

not

the

covered

rate

to

for

on

be

be

or

issuance

the

for

the

greater

considered

freely to

that extent

the

with by

debtor

this

revocation,

transferable

G7

of

certainty,

Chapter

that

compulsory

Chapter

that

currency

a

measure

such

cause

Seventeen

a

limitation

issuance,

solely

non-discriminator as

from

it

provided

tantamount

licenses

to

on the

default

the

or

date

granted

in

43

on

of

to

an SCHEDULE “1”

1 Corporation Profile Report, incorporation date June 26, 2002

2. Land Registry Property Identification for Adams Mine Site

3. Passport of Mr. Vito Gallo

4. Declaration of Trust signed by Mr. Brent Swanick, June 26, 2002

5. Certificate for Shares in 1532382 Ontario Inc. June 26, 2002

6. Sections 115, 119 and 133 of the Ontario Business Corporations Act

7. 1532382 Limited Partnership Agreement, September 10, 2002

8. 1532382 Limited Partnership Loan Agreement, September 9, 2002

9. 1532382 Limited Management Agreement, September 9, 2002

10. Diagrams and photographs of the Adams Mine Site

11. Order in Council Approval, August 13, 1998

12. Ministry of Environment Provisional Certificate of Approval No. A612007, April 23, 1999

13. Permit to Take Water for the south pit, Adams Mine, PTTW No. 00-P-6040, October 18, 2000

14. Approval to operate a leachate treatment facility and storm water facility, Approval No. 3250-4NMPDN, July 9, 2001

15. Notice Requiring the Board to hold a hearing under s.9.2 of the EAA, December 16, 1997

16. EAB Decision: Notre Development Corporation EA-97-0l, June 19, 1998

17. Technical Appendices, Addendums and Response to Ministry of Environment

18. Adams ji,’fineIntervention Coalition v. Ontario (Environment Assessment Board) [1999] O.J. No. 2886 Div. Ct.

19. Adams Mine Intervention coalition v. Ontario (Environment Assessment Board) [1999] O.J. No. 2701 Div. Ct.

20. Letter from Golder Associates to Mayor , City of Toronto, September 15, 2000 45

21, Letter from Garner Lee Limited to Mayor Mel Lastman, City of Toronto, September 14, 2000

22. Letter from Ministry of Environment to Algonquin Nation Secretariat, July 17, 2001

23. Earth Tech Canada Inc. Summary Report: Availability of Landfill space in Ontario, January 2004

24. Report to Works Committee, City of Toronto, June 20, 2003

25. City of Toronto Commissioner of Works to Works Committee, City of Toronto, August 20, 2003

26. Minutes of Meeting of GTA Waste Coordination Meeting, July 3, 2003

27. Memorandum of Understanding regarding a cooperative Effort to Develop Contingency Waste Planning, August 23, 2003

28. Gartner Lee Report — GTA Municipalities Solid Waste Disposal Contingency Plan, January 2005

29. Letter from Ministry of Environment to Notre, January 15, 2002

30. Letter from Gordon McGuinty to Ministry of Environment enclosing Gartner Lee Report dated July 4, 2003 and application, July 7, 2003

31. Permit to Take Water, Permit Number 4121-5SCN9N

32. Letter from Notre to Ministry of Natural Resources, October 1, 1996

33. Letter from Ministry of Natural Resources to Gordon McGuinty, February 17, 2003

34. Letter from Gordon McGuinty to Ministry of Natural Resources, April 10, 2003

35. Notice of Claim, by 1532382 Ontario Inc., July 28, 2003

36. Statement of Claim, Court File No. 22368/A3, October 9, 2003

37. Statement of Defence, Court File No. 22368/A3, November 18, 2003

38. Motion Record of 1532382 Ontario Inc. re: Summary Judgment, returnable March 11, 2004

39. Northwatch News, “Northeast Goes Tory-Free in Liberal Election Sweep”, URL: http://www.web.cak-nwatch/nwatchnews/NN Fall 2003 .PDF, accessed June 23, 2008 46

40. Benzie, Robert (Nov. 19/03) “Ramsay vows to quit if mine plan proceed’. Toronto Star.

41. Hansard Excerpt, May 3, 2004

42. Hansard Excerpt, May 5, 2004