PANAMA CANAL EXPANSION PROGRAM 2010 Expansion Program Components 1 Post-Panamax Locks Construction of New Post-Panamax Locks on the Pacific and Atlantic Sides

Total Page:16

File Type:pdf, Size:1020Kb

PANAMA CANAL EXPANSION PROGRAM 2010 Expansion Program Components 1 Post-Panamax Locks Construction of New Post-Panamax Locks on the Pacific and Atlantic Sides PANAMA CANAL EXPANSION PROGRAM 2010 Expansion Program Components 1 Post-Panamax Locks Construction of new Post-Panamax locks on the Pacific and Atlantic sides. The new locks complexes will have three chambers each with water-saving basins, a lateral filling and emptying system and rolling gates. 2 3 Pacific Access Channel 4 Excavation of the new Pacific Post-Panamax locks north access 5 channel. The project requires the dry excavation of approximately 49 million cubic meters of material along 6.1 kilometers. Executed in four different phases (PACs 1 – 4). Improvements to Navigational Channels Involve dredging of the existing navigation channels to enable the 6 safe navigation of Post-Panamax vessels through the expanded Canal. Improvements to Water Supply 8 Call for an increase of Gatun Lake’s maximum operating level by 45 7 centimeters to improve Canal water supply and draft dependability. 9 B A 10 E C G F 11 D A. Atlantic entrance deepening and widening B. Atlantic Post-Panamax locks C. Rising Gatun Lake's maximum 1. Culebra Cut 10. Pacific Post-Panamax operation level 2. PAC-1 locks D. Deepening and widening of Gatun 3. MEC-1 11. Pacific Entrance Lake and Culebra Cut navigational 4. PAC-3 Dredging channels 5. MEC-2 - Page 3 - E. Post-Panamax locks Pacific access 6. PAC-4 12. Atlantic Entrance channel 7. MEC-3 Dredging F. Pacific Post-Panamax locks 8. Miraflores Lake 13. Atlantic Post-Panamax G. Pacific entrance deepening and 9. PAC-2 locks widening 14. Gatun Lake 2 Projects By August 31, 2010, contracts for the amount of $4,190 million had already been awarded Excavation of the Pacific Access Channel Phase 1 This contract was awarded on July 17, 2007 to Panama – based Constructora Urbana S.A. (CUSA) for a total of B /. 41.1 million. It was completed during the first quarter of 2010 and its activities included the leveling of Paraiso Hill from its original 136 meters to 46 meters 12 above sea level. In achieving this, CUSA removed a total of 7.3 million cubic meters of material. The contract also included the cleaning of a total 146 hectares of firing ranges, known as MEC (munitions and explosives of concern) areas, and the relocation of 3.6 kilometers of the Borinquen road. September 2007 July 2009 Excavation of the Pacific Access Channel Phase 2 This contract was awarded on November 27, 2007 to Cilsa Panama - Minera Maria, for a total of B /. 25.5 million. It was completed during the first quarter of 2010. Activities under the contract involved the removal of 7.4 million cubic meters of material, the 3.5 – kilometer diversion of the Cocolí River and the relocation of 1.3 kilometers of the Borinquen road. Construction of this road began in May 2008. 13 14 The new Borinquen road. 3 View of the work under the third phase of the dry-excavation from the Centennial Bridge. Excavation of the Pacific Access Channel Dredging of the Pacific Entrance Phase 3 Navigational Channel The ACP awarded this contract on December 16, 2008, This contract was awarded on April 1, 2008 to Belgian to Constructora Meco S.A., for a total of $35.5 million. company Dredging International for a total of $177.5 This contract includes the excavation, removal and million. disposal of 8 million cubic meters of material, leveling of Paraiso Hill from 46 to 27.5 meters above sea level and The project consists of the widening of the Panama clearing of 190 hectares of MEC areas. Canal Pacific entrance navigational channel to a minimum 225 meters and deepening to 15.5 meters Excavation of the Pacific Access Channel below mean low water level, as well as partial construction of the Pacific Post-Panamax locks south Phase 4 access. A total of 8.7 million cubic meters of material will be removed under this project. The ACP awarded this contract on January 7, 2010 to consortium ICA-FCC-MECO, for a total of $267.8 million. PAC-4 includes the excavation of nearly 26 million cubic Dredging for the Deepening and meters of unclassified material; construction of the Widening of Gatun Lake and Deepening 2.3-kilometer long Borinquen dam that will separate the of Culebra Cut waters of Miraflores Lake from the new channel; and clearing of 80 hectares of MEC-contaminated areas. ACP personnel is responsible for dredging work for the deepening and widening of Gatun Lake, as well as the deepening of Culebra Cut, from which 20 million cubic meters of material will be removed. To complete this project, the ACP is using in-house and leased equipment. Dredging of the new Pacific Access Channel North Approach ACP awarded this contract to dredging company Jan De Nul n.v. on August 16, 2010, for a total of $54.5 million. The project entails dredging of the Pacific access channel north approach, which will link the new locks on Ongoing work on the Borinquen cofferdam. the Pacific to Culebra Cut. 4 Its activities include the excavation and dredging of nearly 4 million cubic meters of material, widening to 218 meters and deepening to 16.76 meters below mean lake water level along 1.6 kilometers on the area of the north access channel that will join the Third Set of Locks on the Pacific with Culebra Cut. Proposals for this contract's public bid were submitted on August 6, 2010. This is the last excavation and dredging contract to be awarded under the Canal Expansion Program. Dredging of the Gatun Lake North Access Channel Equipment deployed for dredging activities on the Atlantic side. On June 4, 2010, the ACP awarded Dredging International a $40 million contract to dredge a section which will require dredging of some 14.8 million cubic of the Gatun Lake north access channel. A total of 4.6 meters of material, and dry excavation of an additional million cubic meters of material will be removed from 812 thousand cubic meters of material. the area. An area of approximately 13.8 kilometers is being dredged and the existing Atlantic entrance navigation channel is being widened from its 198 meters to a minimum 225 meters, and the north access channel to the new locks on the Atlantic side to a minimum 218 meters. This contract includes the execution of an option for additional deepening up to 16.1 meters, which represents a volume of 2.3 million cubic meters of material, at a cost of $16,411,600. Both volumes include the 60-centimeter dredging tolerance. Raising Gatun Lake’s Maximum Operating Level April 2009 The project entails rising Gatun Lake’s maximum May 2010 operating level from 26.67 meters to 27.13 meters to increase water supply for the operation of the expanded Canal. Due to the increase in water level, it will be necessary to modify certain infrastructure, including hydraulic cylinders for the operation of the gates in Pedro Miguel and Gatun locks, Gatun Spillway gates and other ACP and third party facilities. The project is scheduled for completion by September 2013. Excavation work on De Lesseps Island. Dredging of the Canal Atlantic Entrance This contract was awarded to Belgian company Jan de Nul n.v. on September 25, 2009, for a total of $89.6 million. The work includes the deepening of the approach channel to 15.5 meters below mean low water level, Extension of Gatun Spillway gates 5 Third Set of Locks ACCESS CHANNEL LOCKS CONTROL HOUSE POST-PANAMAX VESSEL 427 m CHAMBERS WSB 1 WSB 2 WSB 3 55 m APPROACH STRUCTURE POST-PANAMAX LOCKS The new locks complexes will have three chambers each, water-saving basins on each level, a lateral filling and emptying system and rolling gates. WATER-SAVING SYSTEM Water-saving basin (WSB) technology is the most With three water-saving basins per efficient system to reduce the volume of water to be chamber, the new locks will save 60% of used by the new locks. The WSBs work as the water used in a lockage. Even water-damming structures located adjacent to the though the new locks have larger lock chambers and connected to them through chambers, they will use 7% less water culverts regulated by flow valves. per transit than the existing locks. 1 1 2 2 3 3 4 5 1 , 2 & 3 : Water is transferred by gravity to WSBs to be used on the following lockage. 4 & 5 : Once equalized, it moves to the next level and eventually to sea. 6 General Information on the New Locks EXISTING LOCKS NEW LOCKS The use of rolling gates will ease their maintenance. Post-panamax Panamax 12.4m 15.2m (39.5’) (50’) GATE OPERATIONS BUILDING GATE RECESSES ROLLING GATE 2 ROLLING GATE 1 GATES AND RECESSES The new locks will require 16 rolling-type gates that will This results in increased lockage capacity and flexibility operate from adjacent recesses located perpendicular to and provides for shorter and more cost-effective mainte- the lock chambers. Such gate configuration allows each nance times. recess to perform as a dry dock, which in turn enables servicing the gates on site without the need to remove In contrast, the miter gates that are currently in operation, them and therefore interrupt lock operations. do not have a recess, they need to be removed and trans- ported to a dry dock whenever overhaul work is required. This process requires the temporary interruption of lock operations. 7 Design and Construction of the Third Set of Locks After little over a year of intensive administrative and field work, efforts for the design and construction of the Third Set of Locks by Grupo Unidos por el Canal, S.A.
Recommended publications
  • International Seaways Inc
    International Seaways, Inc. Third Quarter 2020 Earnings Presentation November 6, 2020 Disclaimer Forward-Looking Statements During the course of this presentation, the Company (International Seaways, Inc. (INSW)) may make forward-looking statements or provide forward-looking information. All statements other than statements of historical facts should be considered forward-looking statements. Some of these statements include words such as ‘‘outlook,’’ ‘‘believe,’’ ‘‘expect,’’ ‘‘potential,’’ ‘‘continue,’’ ‘‘may,’’ ‘‘will,’’ ‘‘should,’’ ‘‘could,’’ ‘‘seek,’’ ‘‘predict,’’ ‘‘intend,’’ ‘‘plan,’’ ‘‘estimate,’’ ‘‘anticipate,’’ ‘‘target,’’ ‘‘project,’’ ‘‘forecast,’’ ‘‘shall,’’ ‘‘contemplate’’ or the negative version of those words or other comparable words. Although they reflect INSW’s current expectations, these statements are not guarantees of future performance, but involve a number of risks, uncertainties, and assumptions which are difficult to predict. Some of the factors that may cause actual outcomes and results to differ materially from those expressed in, or implied by, the forward-looking statements include, but are not necessarily limited to, vessel acquisitions, general economic conditions, competitive pressures, the nature of the Company’s services and their price movements, and the ability to retain key employees. The Company does not undertake to update any forward-looking statements as a result of future developments, new information or otherwise. Non-GAAP Financial Measures Included in this presentation are certain non-GAAP financial measures, including Time Charter Equivalent (“TCE”) revenue, EBITDA, Adjusted EBITDA, and total leverage ratios, designed to complement the financial information presented in accordance with generally accepted accounting principles in the United States of America because management believes such measures are useful to investors. TCE revenues, which represents shipping revenues less voyage expenses, is a measure to compare revenue generated from a voyage charter to revenue generated from a time charter.
    [Show full text]
  • ANNUAL REPORT 2016 Corporate Profile
    ANNUAL REPORT 2016 Corporate Profile Diana Shipping Inc. (NYSE: DSX) is a global provider of shipping transportation services. We specialize in the ownership of dry bulk vessels. As of April 28, 2017 our fleet consists of 48 dry bulk vessels (4 Newcastlemax, 14 Capesize, 3 Post-Panamax, 4 Kamsarmax and 23 Panamax). The Company also expects to take delivery of one Post-Panamax dry bulk vessel by the middle of May 2017, one Post-Panamax dry bulk vessel by the middle of June 2017 as well as one Kamsarmax dry bulk vessel by the middle of June 2017. As of the same date, the combined carrying capacity of our fleet, excluding the three vessels not yet delivered, is approximately 5.7 million dwt with a weighted average age of 7.91 years. Our fleet is managed by our wholly-owned subsidiary Diana Shipping Services S.A. and our established 50/50 joint venture with Wilhelmsen Ship Management named Diana Wilhelmsen Management Limited in Cyprus. Diana Shipping Inc. also owns approximately 25.7% of the issued and outstanding shares of Diana Containerships Inc. (NASDAQ: DCIX), a global provider of shipping transportation services through its ownership of containerships, that currently owns and operates twelve container vessels (6 Post-Panamax and 6 Panamax). Among the distinguishing strengths that we believe provide us with a competitive advantage in the dry bulk shipping industry are the following: > We own a modern, high quality fleet of dry bulk carriers. > Our fleet includes groups of sister ships, providing operational and scheduling flexibility, as well as cost efficiencies.
    [Show full text]
  • The Impact of the New Panama Canal on Cost-Savings in the Shipping Industry
    the International Journal Volume 13 on Marine Navigation Number 3 http://www.transnav.eu and Safety of Sea Transportation September 2019 DOI: 10.12716/1001.13.03.07 The Impact of the New Panama Canal on Cost-savings in the Shipping Industry D. Zupanovic, L. Grbic & M. Baric University of Zadar, Zadar, Croatia ABSTRACT: The passage through the Panama Canal has become the usual waterway for all the ships that can navigate through the Canal. The traffic through the canal is limited by the size of a ship. The need for the expansion of the Canal has emerged due to the development of the global trade and the shipping industry. The new dimensions of the lock‐chambers determine the size of the ships as well. The new generation of ships built to the largest specifications possible to transit the current locks of the canal are called the Post‐Panamax vessels. The maximum dimensions of these ships are 366 meters in length, 49 meters in beam and 15.2 metres in draught. The paper analyses savings in the operational costs on three types of the Post‐Panamax vessels after the Canal expansion. 1 INTRODUCTION The construction of the new and expanded canal enabled the passage of the Post‐Panamax ships. The The construction of the Canal, which lasted for 34 navigation of this category became a standard in the years, introduced the shorter and more efficient route maritime industry and proved the Canal to be of great between the east and west coasts of the United States importance to the world shipping.
    [Show full text]
  • Table of Contents 4.0 Description of the Physical
    TABLE OF CONTENTS 4.0 DESCRIPTION OF THE PHYSICAL ENVIRONMENT............................................ 4­1 4.1 Geology ................................................................................................. 4­1 4.1.1 Methodology ........................................................................................ 4­1 4.1.2 Regional Geological Formations........................................................... 4­2 4.1.3 Local Geological Units ......................................................................... 4­7 4.1.3.1 Atlantic Coast .......................................................................... 4­7 4.1.3.2 Gatun Locks.............................................................................. 4­8 4.1.3.3 Gatun Lake ............................................................................... 4­9 4.1.3.4 Culebra Cut ......................................................................... ...4­10 4.1.3.5 Pacific Locks ...........................................................................4­11 4.1.3.6 Pacific Coast............................................................................4­12 4.1.4 Paleontological Resources ...................................................................4­13 4.1.5 Geotechnical Characterization .............................................................4­17 4.1.6 Tectonics.............................................................................................4­21 4.2 Geomorphology ..............................................................................................4­22
    [Show full text]
  • Project JYP-1104 SALT INTRUSION in GATUN LAKE a Major Qualifying
    Project JYP-1104 SALT INTRUSION IN GATUN LAKE A Major Qualifying Project submitted to the Faculty of WORCESTER POLYTECHNIC INSTITUTE in partial fulfillment of the requirements for the Degree of Bachelor of Science By Assel Akhmetova Cristina Crespo Edwin Muñiz March 11, 2012 Jeanine D. Plummer, Major Advisor Associate Professor, Civil and Environmental Engineering 1. Gatun Lake 2. Salt Intrusion 3. Panama Canal Abstract The expansion of the Panama Canal is adding another lock lane to the canal, allowing passage of larger ships. Increases in the number of transits and the size of the locks may displace more salt from the oceans into the freshwater lake, Gatun Lake, which is a drinking water source for Panama City. This project evaluated future salinity levels in Gatun Lake. Water quality and hydrometeorological data were input into a predictive hydrodynamic software package to project salinity levels in the lake after the new lock system is completed. Modeling results showed that salinity levels are expected to remain in the freshwater range. In the event that the lake becomes brackish, the team designed a water treatment plant using electrodialysis reversal for salt removal and UV light disinfection. ii Executive Summary The Panama Canal runs from the Pacific Ocean in the southeast to the Atlantic Ocean in the northwest over a watershed area containing the freshwater lake, Gatun Lake. The canal facilitates the transit of 36 ships daily using three sets of locks, which displace large volumes of water into and out of Gatun Lake. The displacement of water has the potential to cause salt intrusion into the freshwater Gatun Lake.
    [Show full text]
  • The Panama Canal: It's All About Connectivity
    The Panama Canal: It’s all about connectivity Panama at a glance GDP growth rate – last 10 years 7.5% GDP estimated- 2013 (dollars) 38,6b GDP per capita - 2013 estimated (in dollars) 13,032 Population (million) 3.5 Unemployment rate (in %) 4.0 Inflation rate - 2013 (in %) 4.08 It’s all about Connectivity • 144 trade routes • 1,700 ports • 160 countries The Panama Canal’s value added service The Panama Canal Service Package Economies of Scale Connectivity Sustainability Reliability Reliability • Opens 24 hours a day, 7 days a week, 365 days a year • Safe and secure • 98% customer satisfaction • Strikes not allowed by law; only two closures in its history • Predictability: Published tariffs and fixed transit date with reservation TIME AND DISTANCE SAVINGS ALTERNATE ROUTES PANAMA CANAL SUEZ CAPE HORN CAPE OF GOOD HOPE DAYS DISTANCE DAYS DISTANCE DAYS DISTANCE DAYS DISTANCE East and Gulf Coast US - Asia 20.0 9,640 29.5 14,178 35.6 17,112 31.6 15,417 West Coast South America – 7.3 3,351 43.3 19,776 21.3 9,753 43.1 19,693 East Coast US West Coast South America - 14.1 6,433 39.8 18,184 22 10,506 42.3 19,321 Europe West Coast US - Europe 17.5 8,005 35.5 16,210 30 13,702 42.4 19,385 West Coast Central America – 6.3 2,900 43.2 19,756 24.9 11,379 44.4 20,299 East Coast US Source: Fairplay Distance Table Speed: 20 knots Distance from point to point, travel days without considering port calls Sustainability PanamaCapacity: Canal - 2015 Existing Canal: 330m PC/UMS tons Expanded Canal: 600m PC/UMS tons Expansion Program Components Atlantic Site Post-
    [Show full text]
  • THE PANAMA CANAL REVIEW Number 215 Are in Competitive Jobs With- Mileage Allowance
    ^) T«f - l-P-03 -G Gift ofthe Panama Canal Museum^ Vol. 5, No. 3 BALBOA HEIGHTS, CANAL ZONE, OCTOBER 1, 1954 5 cents Fearless Foursome TEMPORARY PLAN USED TO COVER VACATION TRAVEL Judging by the avalanche of real and hypothetical questions thrown at the three employees in the Transportation Section of the Administrative Branch, it was fortunate that enactment of the free home leave travel legislation came at the end of the summer vacation season. No subject in many years has stimu- lated more interest or evoked more ques- tions than this. So many inquiries were received by the Transportation Section that a special request was made for em- ployees not planning immediate vacations to delay their questions. The Canal administration moved quick- ly when news was received that President Eisenhower had signed the bill into law. The plan was made effective immediately and employees leaving the next day on the Panama Line were given an oppor- tunity to accept free transportation. The plan is still SLIDING'S FUN and stirs up a breeze on a hot day. These Los Rios youngsters enjoy some of the being operated under equipment at their new play area: Ricky Riesch, Martha Jane Spinney (asked to spell it, she said: "You temporary rules until permanent regula- don't. You say it!"), Madeline Hopson, and Janet Stuart. For more on Canal Zone playgrounds, see tions are formulated. It is expected that page 5. these will be ready for announcement at an early date. First Free Tickets CANAL EMPLOYEES BEGIN TO SEE EFFECTS Travel orders are now being issued for all forms of transportation, and employ- BILL ees leaving today on the S.
    [Show full text]
  • Panamax - Wikipedia 4/20/20, 1018 AM
    Panamax - Wikipedia 4/20/20, 1018 AM Panamax Panamax and New Panamax (or Neopanamax) are terms for the size limits for ships travelling through the Panama Canal. General characteristics The limits and requirements are published by the Panama Canal Panamax Authority (ACP) in a publication titled "Vessel Requirements".[1] Tonnage: 52,500 DWT These requirements also describe topics like exceptional dry Length: 289.56 m (950 ft) seasonal limits, propulsion, communications, and detailed ship design. Beam: 32.31 m (106 ft) Height: 57.91 m (190 ft) The allowable size is limited by the width and length of the available lock chambers, by the depth of water in the canal, and Draft: 12.04 m (39.5 ft) by the height of the Bridge of the Americas since that bridge's Capacity: 5,000 TEU construction. These dimensions give clear parameters for ships Notes: Opened 1914 destined to traverse the Panama Canal and have influenced the design of cargo ships, naval vessels, and passenger ships. General characteristics New Panamax specifications have been in effect since the opening of Panamax the canal in 1914. In 2009 the ACP published the New Panamax Tonnage: 120,000 DWT specification[2] which came into effect when the canal's third set of locks, larger than the original two, opened on 26 June 2016. Length: 366 m (1,201 ft) Ships that do not fall within the Panamax-sizes are called post- Beam: 51.25 m (168 ft) Panamax or super-Panamax. Height: 57.91 m (190 ft) The increasing prevalence of vessels of the maximum size is a Draft: 15.2 m (50 ft) problem for the canal, as a Panamax ship is a tight fit that Capacity: 13,000 TEU requires precise control of the vessel in the locks, possibly resulting in longer lock time, and requiring that these ships Notes: Opened 2016 transit in daylight.
    [Show full text]
  • Weekly Market Report
    GLENPOINTE CENTRE WEST, FIRST FLOOR, 500 FRANK W. BURR BOULEVARD TEANECK, NJ 07666 (201) 907-0009 September 24th 2021 / Week 38 THE VIEW FROM THE BRIDGE The Capesize chartering market is still moving up and leading the way for increased dry cargo rates across all segments. The Baltic Exchange Capesize 5TC opened the week at $53,240/day and closed out the week up $8,069 settling today at $61,309/day. The Fronthaul C9 to the Far East reached $81,775/day! Kamsarmaxes are also obtaining excellent numbers, reports of an 81,000 DWT unit obtaining $36,500/day for a trip via east coast South America with delivery in Singapore. Coal voyages from Indonesia and Australia to India are seeing $38,250/day levels and an 81,000 DWT vessel achieved $34,000/day for 4-6 months T/C. A 63,000 DWT Ultramax open Southeast Asia fixed 5-7 months in the low $40,000/day levels while a 56,000 DWT supramax fixed a trip from Turkey to West Africa at $52,000/day. An Ultramax fixed from the US Gulf to the far east in the low $50,000/day. The Handysize index BHSI rose all week and finished at a new yearly high of 1925 points. A 37,000 DWT handy fixed a trip from East coast South America with alumina to Norway for $37,000/day plus a 28,000 DWT handy fixed from Santos to Morocco with sugar at $34,000/day. A 35,000 DWT handy was fixed from Morocco to Bangladesh at $45,250/day and in the Mediterranean a 37,000 DWT handy booked a trip from Turkey to the US Gulf with an intended cargo of steels at $41,000/day.
    [Show full text]
  • Panama Canal Railway Coordinates: 8.97702°N 79.56773°W from Wikipedia, the Free Encyclopedia
    Panama Canal Railway Coordinates: 8.97702°N 79.56773°W From Wikipedia, the free encyclopedia The Panama Canal Railway is a railway line that runs parallel to the Panama Canal, linking the Atlantic Ocean to the Pacific Ocean in Central America. The Panama Canal Railway Company route stretches 47.6 miles (76.6 km) across the Isthmus of Panama from Colón (Atlantic) to Balboa (Pacific, near Panama City). It is operated by Panama Canal Railway Company (reporting mark: PCRC), which is jointly owned by Kansas City Southern and Mi-Jack Products. [2] The Panama Canal Railway currently provides both freight and passenger service. The infrastructure of this railroad (formerly named the Panama Railway or Panama Rail Road ) was of vital importance for the construction of the Panama Canal over a parallel route half a century later. The principal incentive for the building of the rail line was the vast increase in traffic to California owing to the 1849 California Gold Rush. Construction on the Panama Railroad began in 1850 and the first revenue train ran over the full length on January 28, 1855. [3] Referred to as an inter-oceanic railroad when it opened, [4] it was later also described by some as representing a "transcontinental" railroad, despite only transversing the narrow isthmus connecting the North and South American continents.[5][6][7][8] Contents 1 History of earlier isthmus crossings and plans 2 1855 Panama Railroad 2.1 Construction Current Panama Canal Railway line 2.2 Financing (interactive version)[1] 2.3 Death toll Legend 2.4 Cadaver
    [Show full text]
  • Panama Canal Expansion Impacts on Fleet Patterns and Challenges in Terminal Design Presented by Michael Horton, C
    Panama Canal Expansion Impacts on Fleet Patterns and Challenges in Terminal Design Presented by Michael Horton, C. Eng, P.E. Agenda • Panama Canal Expansion, the Coming Fleet – Fleet Vessel size – Container Vessel Size • Design Criteria , Present & Future – Terminal Requirements for the Future – Options for Berth Construction • Challenges, Moving Forward – Time – Money • Conclusions The New Generation Source: ACP Ready or Not? In 1995 the Regina Maersk was big at 6,500 TEU – 5,800 trucks – 25 barges – 550 cargo planes Regina Maersk (1995) Now We Have the Emma Maersk at 11,000 or 13,000TEUs Emma Maersk (2006) But Still Not The Biggest Vessel On The Water Typical Maritime Transport Costs Source: Delft University, “Containerization International Charter Market Report”, Drewry Container Market Review 2006-2007. Container Ship Dimensions by Capacity (averages) Capacity Draft LOA Beam (TEUs) (m) (m) (m) 2,000-2,999 11.6 239 31.5 3,000-3,999 12.1 259 32.4 4,000-4,999 13.0 284 33.2 5,000-5,999 13.7 281 39.0 6,000-6,999 13.9 302 40.6 7,000-7,999 14.6 343 42.6 8,000-8,999 14.3 329 42.8 9,000-9,999 14.7 344 44.0 >10,000 15.5 398 56.4 Immediate Demand (ECSA carrier) • (2010) - 6,300 TEUS: – Length: 300 Meters – Beam: 40 Meters – Draft: 14.5 Meters – DWT: 76,000 • (2014) - 8,800 TEUS: – Length: 338 Meters – Beam: 46 Meters – Draft: 15.5 Meters – DWT: 116,000 Vessel Size: Conclusion • Panama Canal sets the new top end? • Vessel size will be a factor of route, market potential and facilities availability • With or without the Canal expansion, terminal
    [Show full text]
  • PANAMA CANAL PANAMA Connecting Hemispheres in Panama 8 DAYS | Choose Your Dates
    MIRAFLORES LOCKS, PANAMA CANAL PANAMA Connecting Hemispheres in Panama 8 DAYS | Choose your dates About this trip Your students will... Connecting the ecosystems and civilizations of two continents, • Visit a coffee farm and discuss the importance of Panama is an ideal classroom for examining topics of biology, pollination and sustainable culture, engineering, and more. Compare rainforest and cloud forest farming. habitats while observing neotropical wildlife. Spend the day with an • Learn about medicinal plants in the rainforest with indigenous tribe to learn about their way of life. Analyze the lasting an Emberá village elder. effects of the country’s early colonial roots, its role in World War II, • Delve into the country’s history on a stroll through and the construction of the famed Panama Canal. Finally, discuss the parks and colorful streets how modern Panamanians are looking ahead to a sustainable future. of Casco Viejo, Panama City’s historical center. • Gain a deeper Educational Connections What’s included? understanding of the engineering marvel that is • Bilingual local guide the Panama Canal during a • Driver visit to the Miraflores Locks • Accommodations Visitor Center. Interdisciplinary Natural Studies History • Activities • Enjoy fun adventure • Private transportation activities, including • Meals whitewater rafting, kayaking, and guided rainforest and • Beverages with meals cloud forest hikes. • Carbon offsetting Cultural Adventure Studies Learning holbrooktravel.com | 800-451-7111 Itinerary BLD = BREAKFAST, LUNCH, DINNER relocation during canal expansion, and meet their animal ambassadors. This afternoon, go kayaking on the Chagres River. After dinner meet with Yaguara Conservation to learn about the plight of the jaguar DAY 1 - PANAMA CITY and measures taken to replenish the wild cat population.
    [Show full text]