Involuntary Resettlement Assessment and Measures

Resettlement Plan for SH-81 (Sakkadi - Nasriganj Subproject) Document Stage: Final Project Number: 41629 July 2010

IND: State Highways II Project

Prepared by Bihar State Road Development Corporation, Government of Bihar.

The resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

ACRONYMS

ADB Asian Development Bank ARO Assistant Resettlement Officer BPL below poverty line BSR basic schedule of rates BSRDC Bihar State Road Development Corporation CPR common property resources CSC Construction Supervision Consultant DC District Collector DGM Deputy General Manager DP displaced person DPR detailed project report EA Executing Agency EE Executive Engineer FGD focus group discussion GoI Government of GRC Grievance Redress Committee IA implementing agency IP indigenous peoples IR Involuntary Resettlement LAA Land Acquisition Act LAP land acquisition plan MD Managing Director NGOs nongovernmental organizations NRRP National Rehabilitation and Resettlement Policy OBC other backward castes PIUs project implementation units PMU project monitoring unit RC resettlement cell R&R resettlement and rehabilitation RF resettlement framework RO Resettlement Officer ROW right of way RP resettlement plan SCs scheduled castes SPS ADB Safeguard Policy Statement STs scheduled tribes TOR terms of reference

TABLE OF CONTENTS

EXECUTIVE SUMMARY i CHAPTER 1: PROJECT DESCRIPTION 1 1.1 General 1 1.2 The Project Road and its Components 1 1.3 Profile of the Project Area 3 1.4 Subproject Impacts and Benefits 3 1.5 Project Components 5 1.6 Minimizing Resettlement 6 1.7 Scope and Objective of Resettlement Plan 7 CHAPTER 2: METHODOLOGY FOR IMPACT ASSESSMENT 9 2.1 Resettlement Screening 9 2.2 Land Acquisition Planning 9 2.3 Census Survey and Inventory of Assets 9 2.4 Public Consultation 10 CHAPTER 3: SOCIOECONOMIC INFORMATION AND PROFILE 11 3.1 Socioeconomic Profile of Project Area 11 3.1 Social Categories of the DPs 12 3.1 Religious Categories of the DPs 12 3.1 Number of DPs 12 3.1 Vulnerable Households being Affected in the Subproject 13 3.1 Annual Income Level of the Affected Households 13 3.1 Educational Status of DPs 14 3.1 Occupational Status of DPs 14 3.1 Impact on Indigenous People 15 3.1 Gender Impact 15 CHAPTER 4: SCOPE OF LAND ACQUISITION AND RESETTLEMENT 17 4.1 Scope of land Acquisition 17 4.1 Loss of Land 17 4.1 Loss of Structure in the Subproject 19

4.1 Loss of Livelihoods 22 4.2 Loss of Community Property Resources 22 4.3 Type of Government Property 23 4.4 Summary Subproject Impacts 23 CHAPTER 5: STAKEHOLDERS CONSULTATION AND PARTICIPATION 25 5.1 Stakeholders in the Project 25 5.2 Public Consultation in the Project 25 5.3 Methods of Public Consultation 25 5.4 Scope of Consultation and Issues 25 5.5 Finding of Focused Group Discussions 26 5.6 Consultations with Officials and other Stakeholders 30 5.7 Plan for further Consultation in the Project 31 5.8 Information Disclosure 33 CHAPTER 6: LEGAL FRAMEWORK 35 6.1 Introduction 35 6.2 Land Acquisition Act 1894 35 6.3 National Rehabilitation and Resettlement Policy, 2007 (NRRP-2007) 36 6.4 Bihar Land Acquisition Resettlement and Rehabilitation Policy-2007 38 6.5 Asian Development Bank’s (ADB) Policy of Involuntary Resettlement 39 6.6 Policy Framework for this Project 40 6.7 Methodology for Determination of Valuation of Assets 42 6.8 Procedure and Steps of Land Acquisition 43 CHAPTER 7: ENTITLEMENTS, ASSISTANCE AND BENEFITS 44 7.1 Definition of DPs and Eligibility 44 7.1 Entitlements 44 7.1 Entitlement Matrix 47 CHAPTER 8: RELOCATION OF HOUSING AND SETTLEMENTS 52 8.1 Basic Provision for Relocation 52 8.2 Need for Relocation 52 8.3 Magnitude of Physical Displacement in the Subproject 52 8.4 Relocation and Compensation Option by DPs 53

8.5 Relocation Strategy 53 CHAPTER 9: INCOME RESTORATION AND REHABILITATION 55 9.1 Loss of Livelihoods in the Subproject 55 9.1 Provisions for Loss of Livelihood 55 9.1 Income Restoration Measures 56 9.1 Additional Support from Ongoing Poverty Reduction Programs 57 CHAPTER 10: RESETTLEMENT BUDGET AND FINANCING PLAN 58 10.1 General 58 10.1 Compensation 58 10.1 Assistance 59 10.1 Compensation for Community and Government Property 59 10.1 RP Implementation and Support Cost 60 10.1 Source of Funding and Fund Flow Management 60 10.1 R&R Budget 60 CHAPTER 11: GRIEVANCE REDRESS MECHANISMS 62 11.1 General 62 11.1 Grievance Redress Mechanism 62 11.1 Constitution and Function of the GRC 62 11.1 Operational Mechanisms of GRC 62 CHAPTER 12: INSTITUTIONAL ARRANGEMENTS 64 12.1 Institutional Requirement 64 12.2 Executing Agency 64 12.3 Project Management Unit (PMU) 64 12.4 Project Implementation Unit (PIU) 64 12.5 Non Government Organization (NGO) 64 12.6 Capacity Building on RP in the EA 66 CHAPTER 13: IMPLEMENTATION SCHEDULE 67 13.1 Introduction 67 13.2 Schedule for Project Implementation 67 13.3 R&R Implementation Schedule 67 CHAPTER 14: MONITORING AND REPORTING 70

14.1 Need for Monitoring and Reporting 70 14.2 Monitoring in the Project 70 14.3 Stages of Monitoring 70 14.4 Monitoring Indicators 71 14.5 Reporting Requirements 72

Appendixes Appendix 1 Census Survey Questionnaire Appendix 2 ToR for NGO Appendix 3 List of Affected Structures Appendix 4 Attendance in FGD Consultation

EXECUTIVE SUMMARY

A. Project Description

1. The Bihar State Road Development Corporation (BSRDC), Government of Bihar is presently implementing Bihar State Highways I Project under Asian Development Bank (ADB) assistance and now intending to take up Bihar State Highways II Project to strengthen and rehabilitate the deteriorated state roads and upgrade some newly declared state roads to provide reliable road transport services in the state. Under Bihar State Highways II Project, four subproject road sections consisting of 351.086 kilometers (km) are selected, for which detailed project reports (DPR) are being prepared by BSRDC. This is a Resettlement Plan1 prepared for the SH-81 subproject, which is considered as “Category A” as far as Involuntary Resettlement (IR) is concerned.

2. The subproject road SH-81 begins at Sakaddi village and terminates at Nasrigunj. It connects NH-30 (Mohania - Bakhtiyarpur) to SH-15 ( -Vikramgunj). The total length of project road is 83.250 km and runs parallel to Sone River. The road runs primarily through agricultural fields and many built-up areas. Some of the heavily- settled areas include Sakaddi, Chandi, Akhgaon, Sandesh, Naunur, Azimabad, Andhari and Kachwa. It also crosses many canals/drains at various locations.

3. The proposed subproject can be viewed as boosting economic growth and poverty reduction which will bring substantial social and economic development in the region. The social benefits due to the subproject will be triggered by the improved accessibility to various services such as easy access to markets, health facilities, schools, workplace, etc, which in turn increases the income of the locals, ultimately elevating their standard of living. However, there will be some negative impacts on the people living in the immediate project area.

4. As the existing right of way (ROW) is very much limited and therefore realignment is proposed for various parts of the project road, the additional requirement of land may be up to 30m in substantial portion of the project length. The 30 meters in rural area and 16 meters in urban area proposed RoW has been decided keeping in mind the future need of expansion and requirement of comparatively more construction width due to high embankments for significant length. Key activities for subproject road improvement involves (i) widening/strengthening of the road up to 2-lane carriageway configuration (ii) improving road geometry (iii) provision of bypasses to avoid heavy built-up area (iv) construction of side drains (vii) construction of ROB (viii) Junctions/intersections improvement and (ix) provision of service roads etc. The brief of all key project activities are described below. Adequate attention has been given during the feasibility and detailed project design phases of the project preparation to minimize the adverse impacts on land acquisition and resettlement impacts. However, technical and engineering constraints were one of the major concerns during exploration of various alternative alignments. With the available options, best engineering solution have been adopted to avoid large scale land acquisition and resettlement impacts.

1 As per ADB’s SPS-2009 and OM Section F-1/OP issued on January 2010, The involuntary resettlement impacts of an ADB-supported project are considered significant if 200 or more persons will experience major impacts, which are defined as (i) being physically displaced from housing, or (ii) losing 10% or more of their productive assets (income generating).

ii

5. The aim of this Resettlement Plan (RP) is to mitigate all such unavoidable negative impacts caused due to the project and resettle the displaced persons and restore their livelihoods. This Full Resettlement Plan has been prepared on the basis of subproject census survey findings and consultation with various stakeholders. The plan complies with ADB Safeguard Policy Statement-2009 designed by ADB to protect the rights of the affected persons and communities.

B. Socioeconomic Information and Profile

6. The project area consists of Bhojpur and , which came into existence in 1992. Earlier this district was part of old Shahabad district. In the year 1972 Shahabad district was bifurcated in two parts namely Bhojpur and Rohtas. Bhojpur being mostly urbanized is way ahead from the Rohtas in all developmental aspects. About 14.18% population of Rohtas are living in urban area whereas about 16% population of Bhojpur are living in the urban areas. Being the capital city, has all major facilities like educational institutes, hospitals, markets, etc whereas it is very much limited in the case of Rohtas. The density of population of Bhojpur district is substantially higher than the state average of 880 persons per sq km, however, the density of population of Rohtas district is lower than state as well as Bhojpur district. While sex ratio, determined by number of females per one thousand males, of Bhojpur district (900) is comparable to the state average of 919, Rohtas district recorded better ratio of 909. Bihar does not have any significant number of tribal population, 0.9% of total population, after division of the state into two, the other half being , the home of many scheduled tribes.

7. The social stratification of the subproject area shows the dominance of Higher Caste population with 1183 (52.16%) households. The second stratum of the social grouping in the area is of other backward caste (OBC) population with 775 (34.17%) households followed by Scheduled Caste 310 (13.67%) households. There is no presence of schedule tribe (ST) population in the subproject area. The subproject area is dominated by Hindu community as they form 98.06 % (2225) of the DPs. There are 13147 DPs, being affected by the subproject, which includes 7226 (56%) males and 5921(44%) females. 31.78% of DPs forms the BPL category. The educational status of head of the households reveals that overall scenario of literacy level is not encouraging in the project area as significant percentage of population, i.e., 11.94 % and 32.39 % are either illiterate or has attained the education up to elementary level respectively. 39.31% DPs are Graduate, while very few (1.14%) have degree of master and above. The census survey revealed that four women headed households will be affected by the subproject.

C Scope of Land Acquisition and Resettlement

8. According to the Land Acquisition Plan (LAP) prepared as a part of Detailed Design Report, 269.62 acres of land will be acquired for the subproject. The area is excluding the area that already lies with Road Construction Department in terms of existing roads falling in the alignment. A project census survey was carried out to identify the persons who would be displaced by the project and to make an inventory of their assets that would be lost to the project, which would be the basis of calculation of compensation.

9. There are 1235 private land units/ plots affected in the subproject. In addition, 672 private structures will be affected in the subproject out of which 517 (76.93%) structures are of residential type, 78 (11.61%) are of commercial type, 77 (11.46%) are of residential-cum- commercial type. In terms of indirect impacts on DPs due to loss of land and structures, many households shall lose their livelihoods or shall get economically displaced. While accounting the

iii number of households losing their livelihoods, owners of agricultural land and associated agricultural laborer and sharecropper are considered. Similarly in case of structures, households associated with commercial activities and employed people thereof are enumerated. However, the residential structures (517) and barren lands (14) do not yield any source of livelihood, these are excluded. A total number of 1377 households shall be losing their livelihoods. This comprises of 913 (66.3%) agricultural land owners, 59 (4.28%) agricultural laborer, 97(7.04%) share croppers in the agriculture and related activities. In case of commercial structures including squatters 59 (4.28%) households will lose their livelihood. In addition, the residential- cum-commercial structures account 43 (3.12%) households. Besides 186 (13.51%) tenant / leaseholder and 20 (1.45%) employees will lose their livelihood. The loss of CPR due to the subproject includes 49 religious places and 3 community structures. The subproject alignment has avoided the heavy built-up area by bypassing it for avoiding large scale destruction and maintaining the safety and sanctity of these places. The summary subproject impacts are presented in the Table E.1.

Table E 1: Summary Subproject Impacts

Sl. No. Impacts Number 1 Total land acquisition requirements (in acre) 269.6 2 Total private land acquisition requirements (in acre) 257.8 3 Total number of land units/plots affected 1,352.0 4 Total number of private land units/plots affected 1,235.0 5 Total Number of private Trees affected 369.0 6 Total number of private structures affected 672.0 7 Total number of households affected (Titleholders-1391, Non- 2,269.0 titleholders-652, Tenants-186, Wage earner/ employee-20 ) 8 Total Number of Vulnerable households affected 513.0 9 Total number of displaced persons (DPs) 13,147.0 10 Total number of CPRs affected (including 49 Religious structures) 52.0 11 Total number of Government properties affected 22.0 Source: Census Survey, Bihar State Highways II Project, 2010

D. Stakeholders Consultation and Participation

10. Consultations with various stakeholders were carried out during various phases of project preparation. The stakeholders in the project are both primary and secondary. The primary stakeholders are project displaced persons (DPs), project affected persons such as host community, Executing Agency especially the officials in BSRDC, PMU, PIU and the field level BSRDC staff. Additionally, the concerned district magistrates and the revenue officials are also considered to be the primary stakeholders. Other stakeholders in the project include village heads, head of Gram Panchayat, village administrative officers, heads of households, women’s groups, farmers, business communities, and other vulnerable DPs like the scheduled caste (SC and BPL people. Project related information were disseminated to the DPs and based on the findings of consultation with DPs alignment was reviewed and suitably modified to minimize the resettlement impacts.

11. To keep more transparency in planning and for further active involvement of DPs and other stakeholders the project information will be disseminated through disclosure of resettlement planning documents. The EA will submit the following documents to ADB for disclosure on ADB’s website:

iv

(i) the final resettlement plan endorsed by the EA after the census of displaced persons has been completed; (ii) a new resettlement plan or an updated resettlement plan, and a corrective action plan prepared during project implementation, if any; and (iii) the resettlement monitoring reports.

12. The EA will provide relevant resettlement information, including information from the above mentioned documents in a timely manner, in an accessible place and in a form and language(s) understandable to affected persons and other stakeholders. A resettlement information leaflet containing information on compensation, entitlement and resettlement management adopted for the subproject will be made available in local language () and distributed to DPs.

E. Legal Framework

13. The legal framework and principles adopted for addressing resettlement issues in the Project have been guided by the existing legislation and policies of the GOI, the Government of Bihar, Asian Development Bank (ADB) and the Resettlement Framework (RF) adopted for the project. Prior to the preparation of the Resettlement Plan, a detailed analysis of the existing national and state policies was undertaken and a RF has been prepared for the entire program. The section below provides details of the various national and state level legislations studied and their applicability within this framework. This RP is prepared based on the review and analysis of all applicable legal and policy frameworks of the country and ADB policy requirements. Based on the analysis of applicable legal and policy frameworks of the country and in consistent with ADB’s policy requirements the broad resettlement principle for this project is finalized.

F. Entitlements, Assistance and Benefits

14. The project will have three types of displaced persons i.e., (i) persons with formal legal rights to land lost in its entirety or in part; (ii) persons who lost the land they occupy in its entirety or in part who have no formal legal rights to such land, but who have claims to such lands that are recognized or recognizable under national laws; and (iii) persons who lost the land they occupy in its entirety or in part who have neither formal legal rights nor recognized or recognizable claims to such land. The involuntary resettlement requirements apply to all three types of displaced persons. DPs entitled for compensation, assistance and rehabilitation provisions under the subproject are:

 All DPs losing land either covered by formal legal title, recognizable title , or without legal status;  Tenants and sharecroppers whether registered or not;  Owners of buildings, plants, or other objects attached to the land; and  DPs losing business, income, and salaries

15. Compensation eligibility is limited by a cut-off date as set for this project on the day of the beginning of the census survey which is 30th December 2009. DPs who settle in the affected areas after the cut-off date will not be eligible for compensation. They, however, will be given sufficient advance notice, requested to vacate premises and dismantle affected structures prior to project implementation. Their dismantled structures materials will not be confiscated and they

v will not pay any fine or suffer any sanction. Compensation for the lost assets to all displaced persons will be paid on the basis of replacement cost. Resettlement assistance for lost income and livelihoods will be provided to both title holders and non-title holders. Special resettlement and rehabilitation measures will be made available to the “Vulnerable Group” comprises of DPs living below poverty line (BPL), SC, women headed households, the elderly and the disabled. An Entitlement Matrix (Table: E-2) has been formulated, which recognizes and lists various types of losses resulting out of the project and specific compensation and resettlement packages.

Table E 2: Entitlement Matrix

S. Type of Unit of N. Loss Entitlement Entitlement Details A. LOSS OF LAND 1 Loss of a) Titleholder a) Compensatio a) Cash compensation at replacement cost as Agricultural b) DPs with n at determined according to BLARRP-2007 or land customary land replacement replacement of land if available. right cost b) If the residual plot(s) is (are) not viable, i.e., b) Special the DP becomes a marginal farmer,2 any of provision for the following three options are to be given to vulnerable the DP, subject to his acceptance: group  The DP remains on the plot, and the compensation and assistance paid to the tune of required amount of land to be acquired.  Compensation and assistance are to be provided for the entire plot including residual part, if the owner of such land wishes that his residual plot should also be acquired by the EA, the EA will acquire the residual plot and pay the compensation for it.  If DP is from vulnerable group, compensation for the entire land by means of land for land will be provided if DP wishes so, provided that land of equal productive value is available. c) All fees, stamp duties, taxes and other charges, as applicable under the relevant laws, incurred in the relocation and rehabilitation process, are to be borne by the EA. 2 Loss of a) Titleholder a) Compensatio a) Cash compensation at replacement cost as homestead b) DPs with n at determined according to BLARRP-2007 or /commercial customary land replacement replacement of land if available. land rights cost b) All fees, stamp duties, taxes and other charges, as applicable under the relevant laws, incurred in the relocation and rehabilitation process, are to be borne by the EA.

2 Marginal farmers are those who own less land than the district minimum land holding.

vi

S. Type of Unit of N. Loss Entitlement Entitlement Details B. LOSS OF STRUCTURE (RESIDENTIAL/COMMERCIAL/OTHER) 3 Loss of a) Titleholder a) a) Compensation of structure will be paid at residential / b) DPs having Compensation the replacement cost to be calculated as per commercial structure with at replacement latest prevailing basic schedules of rates structures customary land cost (BSR) without depreciation. right b) Shifting b) Shifting assistance of Rs. 10000/-3. assistance c) Right to salvage material from demolished structure and frontage etc. d) Rental assistance as per the prevalent rate in the form of grant to cover maximum three month rentals. 4 Loss of Tenants a) Rental a) Rental assistance for both residential & rental Assistance commercial tenants as per the prevalent accommoda b) rate in the form of grant to cover maximum tion Compensation three month rentals. at replacement b) Additional structures erected by tenants will cost also be compensated and deducted from c) Shifting owner’s compensation amount. assistance c) Shifting assistance based on type of house and household assets. d) Any advance deposited by the tenants will be refunded from owners total compensation package to the tenant on submission of documentary evidences. e) Right to salvage material from demolished structure and frontage etc. erected by tenants. C. LOSS OF STRUCTURE BY NON-TITLED HOLDER 5 Loss of Squatters4 having a) No a) Squatters will be notified and given one structure structure compensation month time to remove their assets. (immovable for land b) Compensation for loss of structure at assets b) replacement cost. constructed Compensation c) Shifting assistance of Rs. 100005/-. by squatters for structures. d) Right to salvage material from the and c) Shifting demolished structure. encroacher Assistance s) Encroachers6 a) No a) Encroachers will be notified and given one having structure compensation month time to remove their assets and for land harvest their crops. b) b) Compensation for structures at replacement Compensation cost to the vulnerable households only. for structures c) Right to salvage materials from the to only demolished structure. vulnerable household D. LOSS OF TREES AND CROPS 6 Loss of a) Land holders Compensation a) Advance notice to DPs to harvest fruits and Trees b) Share- at Market value remove trees croppers to be computed b) For fruit bearing trees compensation at c) Lease holders with assistance average fruit production of horticulture for next 15 years to be computed at current department market value c) For timber trees compensation at market cost

3 As required by NRRP 2007. 4 Landless person 5 As required by NRRP 2007. 6 Legitimate land holder but encroaching his movable or immovable assets on Government land

vii

S. Type of Unit of N. Loss Entitlement Entitlement Details based on kind of trees 7 Loss of a) Land holders Compensation a) Advance notice to DPs to harvest crops Crops b) Share- at Market value b) In case of standing crops, cash compensation croppers to be computed at current market cost to be calculated of c) Lease holders with assistance mature crops based on average production. of agriculture department E. LOSS OF MARKET PLACE STRUCTURE BY TITLED HOLDER AND NON-TITLED HOLDER 8 Impact on Titleholder7 Relocation a) Affected enterprises will be provided with the market (Owner) losing Assistance following options: place/ commercial Self managed reconstruction of shops by the area on a enterprise in the shop operators minimum of market area with all benefits as per the entitlement matrix; 25 or shops/ b) Project assisted relocation option will be businesses provided to those whose commercial structure can no longer be used as a commercial enterprise as a result of the Project impact. The allotment of the shops in the market complex will be based on the ownership status of those affected. c) Shifting assistance of Rs. 10000/-8. d) Right to salvage material from demolished structure at no cost. Non-titleholder9 Relocation a) Affected enterprises will be provided with the (tenants, Assistance following options: Self managed leaseholders or reconstruction of shops by the shop operators squatters) losing with all benefits as per the entitlement matrix; commercial or enterprise in the b) Project assisted relocation option will be market area provided to those whose commercial structure can no longer be used as a commercial enterprise as a result of the Project impact. The allotment of the shops in the market complex will be based on the ownership status of those affected. c) Shifting assistance of Rs. 1000010/-. d) Right to salvage material from demolished structure at no cost.

7 In case of affected Title owners who have been carrying out business for 10 or more years – the affected title owners will be allotted a shop in the market in lieu of compensation. No additional compensation will be paid to them. However, they will be entitled to transitional assistance and shifting assistance as applicable and provided for in the Entitlement Matrix. 8 As required by NRRP 2007. 9 In case of affected non-title owners, tenants and leaseholders, squatters and vulnerable encroachers, who have been carrying out business for 10 or more years, will be re-established by creation of market place. The constructed shops in this market will be provided on rent to them. For first 3 months, no rent will be charged from these DPs. However, after three months these DPs need to pay to the authority the agreed rent by demand draft monthly and if he/she wishes to own the same can pay the total amount in agreed installments. The DPs opting for this option will not be paid cash compensation for their structure loss. 10 As required by NRRP 2007

viii

S. Type of Unit of N. Loss Entitlement Entitlement Details F. LOSS OF LIVELIHOOD 9 Titleholders Rehabilitation a) Title holders loosing their business Loss of losing income Assistance establishment due to displacement will be primary through business provided with a lump sum transitional source of allowance of Rs. 900011. income Titleholders Rehabilitation a) Training Assistance will be provided for losing income Assistance income generating vocational training and through skill upgradation options as per DPs choice agriculture at the rate of Rs. 4000 per affected household to those households loosing their primary source of income. b) Employment opportunity for DPs in the road construction work, if available and if so desired by them. Non-titleholders Rehabilitation a) Training would be provided for upgradation namely squatters Assistance of skills @ Rs. 4000/ - per family to the DPs. and vulnerable b) Employment opportunity for DPs in the road encroachers construction work, if available and if s0 losing primary desired by them, Or source of income c) National/State level job card under National Rural Employment Guarantee Program. Wage earning Rehabilitation a) This is valid for persons indirectly affected employees Assistance due to the employer having being displaced, indirectly on case-by-case, based on local wage rates affected due to for three months. displacement of b) Employment opportunity for DPs in the road commercial construction work, if available and if so structure desired by them, Or c) National/State level job card under National Rural Employment Guarantee Program. Agricultural Rehabilitation a) Assistance is to be paid as per the prevailing laborer/share- Assistance local wage rates cropper for 200 days. b) Employment opportunity for DPs in the road construction work, if available and if so desired by them, Or d) National/State level job card under National Rural Employment Guarantee Program. Licensed mobile Rehabilitation a) Mobile venders are not eligible for vendors and Assistance compensation or assistance. kiosk operators b) Those mobile vendors in possession of a permit from local authorities to operate in the affected area will be treated as kiosks operators. c) Kiosk operators and vendors licensed to operate from affected locations will be entitled to a one time lump sum assistance of Rs. 4000/-. G. LOSS OF COMMUNITY INFRASTRUCTURE/COMMON PROPERTY RESOURCES

10 Loss of Community Reconstruction a) Cash compensation at replacement cost or Common / Cash reconstruction of the community structure in Property Compensation consultation with the affected community. Resources at replacement

11 This rate has been fixed based on the estimates of average income for a period of three months.

ix

S. Type of Unit of N. Loss Entitlement Entitlement Details cost

H. ADDITIONAL SUPPORT TO VULNERABLE GROUP

11 Additional Vulnerable Special a) One time lump sum assistance of Rs. 10000/ Assistance households Assistance to vulnerable households. (This will be paid to including BPL, above and over the other assistance(s) as per vulnerable SC, ST, WHH, this framework). groups disabled and elderly I. OTHER UNANTICIPATED IMPACTS

12 Temporary Community / Compensation a) The contractor shall bear the cost of any impact Individual impact on structure or land due to movement during of machinery during construction or construction establishment of construction plant like b) All temporary use of lands outside proposed disruption of RoW to be through written approval of the normal landowner and contractor. traffic, c) Location of Construction camps by damage to contractors in consultation with RCD. adjacent parcel of land / assets due to movement of heavy machinery and plant site 13 Unforeseen Any unanticipated impacts due to the project will be documented and mitigated based impacts if on the spirit of the principle agreed upon in this framework. any

G. Relocation of Housing and Settlements

16. The EA will provide adequate and appropriate replacement land and structures or cash compensation at full replacement cost for lost land and structures, adequate compensation for partially damaged structures, and relocation assistance, according to the Entitlement Matrix. The EA will compensate to the eligible non-title holders for the loss of assets other than land, such as dwellings, and also for other improvements to the land, at full replacement cost. The entitlements to the non-titleholders will be given only if they occupied the land or structures in the project area prior to the cut-off date.

17. Preference will be given to land-based resettlement strategies for displaced persons whose livelihoods are land-based. These strategies may include resettlement on public land, or on private land acquired or purchased for resettlement. Whenever replacement land is offered, displaced persons are provided with land for which a combination of productive potential, locational advantages, and other factors is at least equivalent to the advantages of the land taken. If land is not the preferred option of the displaced persons, or sufficient land is not available at a reasonable price, non-land-based options built around opportunities for employment or self-employment should be provided in addition to cash compensation for land and other assets lost. The non-availability of land will be demonstrated and documented during the implementation of this RP to the satisfaction of ADB. In the case of physically displaced

x persons, the EA will provide (i) relocation assistance, secured tenure to relocation land, better housing at resettlement sites with comparable access to employment and production opportunities, and civic infrastructure and community services as required; (ii) transitional support and development assistance, such as land development, credit facilities, training, or employment opportunities; and (iii) opportunities to derive appropriate development benefits from the project.

18. With the scattered nature of resettlement impacts i.e. 672 structures over 84 kilometers and two districts, it will be difficult and not feasible to provide resettlement colony with all amenities. During the focused group discussion, while discussing about relocation options people were very much in favor of resettlement within the village to avoid disruption of community life and problem with host community. Therefore cash compensation at market rate as more practical solution in this case is suggested for loss of structures.

H. Income Restoration and Rehabilitation

19. The DPs losing their livelihoods includes titleholders land, agricultural laborers, agricultural tenants, and sharecroppers, DPs having commercial structures and employees of the affected structures. In the case of economically displaced persons, regardless of whether or not they are physically displaced, the EA will promptly compensate for the loss of income or livelihood sources at full replacement cost. The EA will also provide assistance such as credit facilities, training, and employment opportunities so that they can improve, or at least restore, their income-earning capacity, production levels, and standards of living to pre-displacement levels.

20. The entitlement proposed for the subproject has adequate provisions for restoration of livelihood of the affected communities. The focus of restoration of livelihoods is to ensure that the DPs are able to at least regain their previous living standards. To restore and enhance the economic conditions of the DPs, certain income generation and income restoration programs are incorporated in the RP. To begin with providing employment to the local people during the construction phase will enable them to benefit from the project, reduce the size of intrusive work forces and keep more of the resources spent on the project in the local economy. It will also give the local communities a greater stake and sense of ownership in the project. The implementing NGO will carry out need assessment and micro plan with training or linking to ongoing income generation training programs and assist in rehabilitation of DPs.

I. Resettlement Budget and Financing Plan

21. The resettlement cost estimate for this subproject includes eligible compensation, resettlement assistance and support cost for RP implementation. The support cost, which includes staffing requirement, monitoring and reporting, involvement of NGO in project implementation and other administrative expenses are part of the overall project cost. The unit cost for land and other assets in this budget has been derived through field survey, consultation with affected families, relevant local authorities and reference from old practices. Contingency provisions have also been made to take into account variations from this estimate. The total R&R budget for the proposed subproject RP works out to Rs. 348.5 million. A summary R&R cost is given in Table: E.3.

xi

Table E.3: R&R Budget

Sl. No. Item Amount (in Rs) 1 Compensation for Land 173,697,626 2 Compensation for Private Structure 119,054,425 3 Compensation for Private Trees 3,993,750 4 Assistance 15,558,000 5 RP Implementation Support Cost 4,600,000 6 Contingency 31,690,380 Grand Total 348,594,181

J. Grievance Redress Mechanisms

22. In the subproject RP implementation there is a need for an efficient grievance redressal mechanism that will assist the DPs in resolving their queries and complaints. Therefore, formation of Grievance Redressal Committee (GRC) will be most important for grievance redressal and it is anticipated that most, if not all grievances, would be settled by the GRC. The GRC will be established at the district level with the primary objective of providing a mechanism to mediate conflict and cut down on lengthy litigation. It will also provide people, who might have objections or concerns about their assistance, a public forum to raise their objections and through conflict resolution, address these issues adequately. The GRCs will continue to function, for the benefit of the DPs, during the entire life of the subproject including the defects liability periods.

23. The GRC will be headed by the District Collector (DC) or his designated representative. The GRC will have representative from the PIU office, representatives of DPs, particularly of vulnerable DPs, local government representatives, representative of local NGOs and other interest groups. It is proposed that GRC will meet regularly (at least twice in a month) on a pre- fixed date. The committee will look into the grievances of the people and will assign the responsibilities to implement the decisions of the committee. The claims will be reviewed and resolved within 15 days from the date of submission to the committee. All Grievances will be routed through the NGO to the GRC. Through public consultations, the DPs will be informed that they have a right to grievance redress. The DPs can call upon the support of the NGO to assist them in presenting their grievances or queries to the GRC .The NGO will act as an in-built grievance redress body. The DPs, who would not be satisfied with the decision of the GRC, will have the right to take the grievance to the PMU Head Office for its redress. Failing the redressal of grievance at PMU, the DPs may take the case to Judiciary. Taking grievances to Judiciary will be avoided as far possible and the NGO will make utmost efforts at reconciliation at the level of GRC.

K. Institutional Arrangements

24. The Executing Agency (EA) for the Project is BSRDC, Government of Bihar. The existing BSRDC has already set up a Project Management Unit (PMU) headed by a Managing Director (MD) with General Managers and Deputy General Managers (DGM) assisted by Managers. This office will be functional for the whole Project duration. The EA, headed by MD will have overall responsibility for implementation of loan and will also be responsible for the overall coordination among ADB, Government of Bihar and PIU.

xii

25. For resettlement activities, PMU will do the overall coordination, planning, implementation, and financing. The PMU will create a Resettlement Cell (RC) within itself with appointment of a Resettlement Officer (RO) at the rank of Executive Engineer (EE) and required support staff for the duration of the Project to ensure timely and effective planning and implementation of resettlement activities. The candidate to be appointed as RO is desired to have similar earlier experience in resettlement and social development planning and implementation. The RO will be assisted by the respective PIU and staff, NGO, for planning and implementation of resettlement activities in the project.

26. Project Implementation Unit (PIU) will be established at subproject level for the implementation of subprojects. The PIU, will appoint/ designate an Assistant Resettlement Officer (ARO) in the rank of Assistant Engineer (AE) who will either be deputed to the PIU or engaged on contractual basis having adequate land acquisition implementation/resettlement experience. The staffs at the PIU level will be provided with the training by the social/ resettlement specialist of the supervision consultant for implementation of the RP. The PIU will maintain all databases, work closely with DPs and other stakeholders and monitor the day today resettlement activities.

27. Involuntary resettlement is a sensitive issue and strong experience in R&R matters along with community related skills will be required by the PIU in order to build a good rapport with the affected community and facilitate satisfactory R&R of the DPs. To overcome this deficiency, experienced and well-qualified NGO in this field will be engaged to assist the PIUs in the implementation of the RP. The NGO would play the role of a facilitator and will work as a link between the PIU and the affected community. NGO will assist AP in income restoration by preparing micro plan and guiding to access into various ongoing government development schemes and agencies providing financial assistance and loan. Taking into account the significant role of the NGO in RP implementation, it is extremely important to select NGO that are capable, genuine and committed to the tasks assigned in order to ensure the success of the Plan.

L. Implementation Schedule

28. Implementation of RP mainly consists of compensation to be paid for affected structures and rehabilitation and resettlement activities. The time for implementation of resettlement plan will be scheduled as per the overall project implementation. All activities related to the land acquisition and resettlement must be planned to ensure that compensation is paid prior to displacement and commencement of civil works. Public consultation, internal monitoring and grievance redress will be undertaken intermittently throughout the project duration. However, the schedule is subject to modification depending on the progress of the project activities. The civil works contract for each subproject will only be awarded after all compensation and relocation has been completed for subproject and rehabilitation measures are in place. The RP preparation and implementation schedule is presented in the Table E-2.

xiii

Table: E-2 R&R Implementation Schedule

Progress (Year/Quarter) Activity 2009 2010 2011 2012 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Project Preparation Stage Screen subproject impact Public Consultation on alignment Prepare Land Acquisition Plan Carry out Census Survey Prepare Resettlement Plan (RP) RP Implementation Stage Hiring of NGOs for RP Implementation Obtaining approval of RP from ADB Disclosure of RP Public consultation  Co-ordination with district authority for LA Submission of LA proposals to DC Declaration of cut-off date (LA Notification) Payment of compensation Taking possession of acquired land Handing over the acquired land to contractor Notify the date of start of construction to

DPs Rehabilitation of DPs Monitoring and Reporting Period Internal monitoring and reporting Hiring Construction Supervision Consultant External monitoring and reporting

M. Monitoring and Reporting

29. Monitoring and reporting are critical activities in involuntary resettlement management in order to ameliorate problems faced by the DPs and develop solutions immediately. Monitoring is a periodic assessment of planned activities providing midway inputs. It facilitates change and gives necessary feedback of activities and the directions on which they are going. Reporting is a summing up activity at the end of the project assessing whether the activities have actually achieved their intended goals and purposes. In other words, monitoring apparatus is crucial mechanism for measuring project performance and fulfillment of the project objectives. RP implementation for the subproject will be closely monitored by the EA through NGO and will be at the helm of all activities related to the RP implementation. The monitoring mechanism will have a two-tier system at the EA level i.e. internal monitoring and external monitoring.

30. PIU responsible for supervision and implementation of the RP will prepare monthly progress reports on resettlement activities and submit to PMU. PMU will submit quarterly reports to ADB. The external R&R monitoring expert under Construction Supervision Consultant (CSC) responsible for external monitoring of the subproject RP implementation will submit a biannual review directly to determine whether resettlement goals have been achieved, more importantly whether livelihoods and living standards have been restored/ enhanced and suggest

xiv suitable recommendations for improvement. All the resettlement monitoring reports will be disclosed to DPs as per procedure followed for disclosure of resettlement plans by the EA.

1

CHAPTER 1 PROJECT DESCRIPTION

1.1 General

1. The Bihar State Road Development Corporation (BSRDC), Government of Bihar is presently implementing Bihar State Highways I Project under Asian Development Bank (ADB) assistance and now intending to take up Bihar State Highways II Project to strengthen and rehabilitate the deteriorated state roads and upgrade some newly declared state roads to provide reliable road transport services in the state. Under Bihar State Highways II Project, four subprojects road sections consisting of 351.086 kilometers are selected for which detailed project reports (DPR) for these road sections are being prepared by BSRDC.

2. This Resettlement Plan1 prepared for the SH-81 subproject is considered as “Category A” as far as involuntary resettlement (IR) is concerned.

1.2 The Project Road and its Location

3. The subproject road section (SH-81) is located in the in Rohtas and Bhojpur district of South Bihar. The Location map of Bihar state Highway Projects-II and subproject is given in Fig. 1.

1 As per ADB’s SPS-2009 and OM Section F-1/OP issued on January 2010, The involuntary resettlement impacts of an ADB-supported project are considered significant if 200 or more persons will experience major impacts, which are defined as (i) being physically displaced from housing, or (ii) losing 10% or more of their productive assets (income generating).

2

Figure 1: Project Location Map

3

4. The subproject road SH-81 begins at Sakaddi village and terminates at Nasrigunj. It connects NH-30 (Mohania - Bakhtiyarpur) to SH-15 (Dehri -Vikramgunj). The total length of project road is 83.250 kms and runs parallel to Sone River. The road runs majorly through agricultural fields and many built-up areas. Some of the heavy settled areas include Sakaddi, Chandi, Akhgaon, Sandesh, Naunur, Azimabad, Andhari and Kachwa. It also crosses many canals/drains at various locations.

1.3 Profile of the Project Area

5. The project area consists of two districts of Bihar i.e. Rohtas and Bhojpur. Brief profiles of both the districts are narrated below.

6. The present Bhojpur came into existence in 1992. Earlier this district was part of old Shahabad district. In the year 1972 Shahabad district was bifurcated in two parts namely Bhojpur and Rohtas. Buxar was a subdivision of old Bhojpur district. In 1992, Buxar became a separate district and rest of Bhojpur district has now three sub-divisions - Arrah Sadar, Jagdishpur and Piro. Arrah town is the headquarters of the district and also its principal town. It is located at a Longitude of 83º45' to 84º45' east and the latitude is 25º10' to 25º40' north. The Bhojpur district is situated at height of 192.989 meters above sea level. Bohjpur district shares it boundary with other districts. In north Bhojpur is bounded by Chapra and Balia district of , Rohtas district in south, Patna, Jahanabadand and Uarwal District in east and Buxar District in west side

7. Rohtas district is one of the thirty-seven districts of Bihar state, India. Headquarter of Rohtas district is . There are three Sub Divisions in Rohtas district named Sasaram, Dehri and . There are nineteen blocks in district named Nauhatta, Chenari, Nasriganj, Rohtas, Shivsagar, , Karakat, Nokha, Vikramganj, Karagahar, Sasaram, Dihri, Dinara, , Akorhigola, Rajpur, Tilauthu, Suryapura and . The Rohtas district is a part of Patna Division, and it has an area of 3850 km² (square kilometres), a population of 2,448,762 (2001 census), and a population density of 636 persons per km². The administrative headquarters of the district, Sasaram is a place of historical importance. Rohtas is located at a Longitude of 83-14” to 83-20” East and the latitude is 24-30” to 25-20” north. The Rohtas district is situated at height of 107.78 meters above sea level. Rohtas district shares it boundary with other districts. In north Rohtas is bounded by Buxar and Bhojpur district, Plamau & district in South, Aurangabad & Part of Gaya district in East and in West side.

1.4 Subproject Impacts and Benefits

8. The proposed subproject can be viewed as boosting economic growth and poverty reduction which will bring substantial social and economic development in the region. The social benefits arising due to the subproject will be triggered off due to improved accessibility to various services such as easy access to markets, health facilities, schools, workplace etc which in turn increases the income of the locals, and ultimately elevating their standard of living. The possible direct and indirect positive impacts of the subproject are listed below.

 The immediate benefits of road construction and improvement will come in the form of direct employment opportunities for the roadside communities and specially those who are engaged as wage laborers, petty contractors and suppliers of raw materials.

4

 Improved road network will provide for improved linkages between the village communities and urban centre, which provides wider marketing facilities.  Road network will not only link the village communities to better markets, but also open up wider work opportunities in distant places. People can shuttle to distant work sites and towns and engage in construction, factories, business as well as domestic works.  Improved road network will encourage urban entrepreneurs to invest in far and remote areas in commercial farming and industrial activities.  Improved road will also help people building strong institutional network with outside agencies. Essential and emergency services like schools, health centre, public distribution system etc can be availed faster.  Increased frequency of interaction with outsiders will increase the awareness level of the people in the village with regard to their health and nutrition, living style, value of education and proper utilization of available resources.  Interaction with the government, non-government and other development agents will help people gain new knowledge on improved farming, land development, development and maintenance of natural resources through the formation of various economic and social development groups.

9. Although various positive subproject impacts and benefits are expected from the proposed subproject as mentioned above, there will be some negative impacts on the people living in the immediate project area. The summary details of project profile including affected villages, households, and land acquisition are presented in the Table: 1.1 below.

Table: 1.1 Summary of Affected Area

No. of Affected No. of Name of Affected Displaced Affected Name of Villages Land Affected District Households Persons1 private (in Acres) CPR Trees Bhojpur Sakaddi Bypass, 1704 9669 220.43 312 41 Kulharia Crossing, Bhadwar, Narhi, Narvirpur, Chandi, Rupchakia, Khangam, Lodipur, Gopalpur, Kosiyan, Bhagwatpur, Vishnupur, Jalpura, Akhgaon Bypass, Narayanpur, Nasratpur, Fatehpur, Chillhos, Raipura, Tilkor, Sandesh, Kajichak, Saraiya, Fulari, Nurpur, Bhimpura, Baga, Milki tola, Azimabad, Varuna, Mehandaura, Brahpur, Nanaur

1 In the context of involuntary resettlement, displaced persons are those who are physically displaced (relocation, loss of residential land, or loss of shelter) and/or economically displaced (loss of land, assets, access to assets, income sources, or means of livelihoods) as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas.

5

No. of Affected No. of Name of Affected Displaced Affected Name of Villages Land Affected District Households Persons1 private (in Acres) CPR Trees Bypass, Baruhi, Bansidihari, Naveentola Sahar, Sahar, Karwashim, Khaira, Dhauri, Chotki Khadao, Andhari Bypass, Imadpur, Dhokraha, Rajpur, Bihta, Englishpul, Amiachak, Khemkarapur, Baga, Baruhi, Banjaria, Beurchak, Abgilla, Peur, Kharau Chaturbhuj, Lodipur, Bhauri, Raipur,

Rohtas Kanchan Bhiga, 565 3478 48.19 57 11 Danwar, Soni tola, Ibrahimpur /Kachwa, Kaithi, Sawarilakh, Maharajganj, Tulsi Tola, Osawon, Gharwas Dih, Paharmalakh, Mednipur, Chanditola, Bardiha, Sakadiya Kaithi, Brahmapur Mehdota

1.5 Project Components

10. As the existing ROW is very much limited and therefore realignment is proposed for various parts of the project road, the additional requirement of land may be up to 30m in substantial portion of the project length. The 30 meters in rural area and 16 meters in urban area proposed RoW has been decided keeping in mind the future need of expansion and requirement of comparatively more construction width due to high embankments for significant length.

11. Key activities for subproject road improvement involves (i) widening/strengthening of the road up to 2-lane divided carriageway configuration (ii) improving road geometry (iii) provision of bypass to avoid heavy built-up area (iv) laying of embankment (v) rehabilitation and construction of new bridges and other cross drainage structures (vi) construction of side drains (vii) construction of ROB (viii) Junctions/intersections improvement (ix) provision of service roads, underpasses and way side amenities etc. The brief of all key project activities are described below.

12. Road Configuration: It is proposed to construct/widen the road to 2 lane standard carriageways of 7.0 m width. The project development will include widening of SH-81 complete Road in a length of 83.24 km (including connectivity to SH-15) Vikramgunj- Nasrigunj- Dehri

6

Road to 2 Lane state highway including construction of four bypasses and realignment at 10 stretches of road and construction of ROB at level Crossing.

13. Realignment/Bypasses: Rrealignments and bypasses are proposed in four congested settlements due to (i) poor road geometry and pavement and embankment conditions, (ii) inadequate ROW, (iii) heavily built-up areas at several locations, (iv) damaged CD structures, (iv) identification of bridges at suitable locations, (v) drainage problems, (vi) cutting of significant number of trees, (vi) minimizing the requirement of railway over bridges (ROB), and (vi) shifting of utilities and many other bottlenecks. Bypasses are proposed at Sakaddi, Nanaur, Akhgaon and Andhari villages.

14. Roadside Drainage: There is no proper drainage along the existing alignment.The provision of catch water drain in cut sections, meter drain or out fall drain will be constructed to avoid outside water coming in and disposal of storm water at frequent intervals to prevent soil erosion.

15. Railway Over Bridges (ROBs): to remove the bottlenecks at one existing level crossings, at Kulharia new ROB at chainage km 1.7 will be constructed.

16. Junctions/intersections Improvement: There is significant number of intersections in this project corridor, such as 4 major intersections and 35 minor intersections. All major intersections will be improved for free and uninterrupted flow of traffic. As per the traffic analysis during feasibility study grade separation is not required at any of the intersection.

17. Service roads and Underpasses: Presently, there is no provision of service road on any location except at chainage 1.7 near ROB, where serviced road has been proposed. The length of the service road is 1.3 km on each side of the road with total length of 2.6 km.

18. Wayside amenities/Toll Plaza/Truck Parkings etc.: No wayside amenities, toll plaza or truck parking is proposed at any locations. However, Bus bays will be provided at 9 locations, while cycle track has been proposed at 14 urban locations.

1.6 Minimizing Resettlement

19. Adequate attention has been given during the feasibility and detailed project design phases of the project preparation to minimize the adverse impacts on land acquisition and resettlement impacts. However, technical and engineering constraints were one of the major concerns during exploration of various alternative alignments. With the available options, best engineering solution have been adopted to avoid large scale land acquisition and resettlement impacts. Following are the general criteria adopted for the selection of the alignment:

 It should serve as uninterrupted traffic for Patna mainly traffic from NH-30;  It should provide linkage to other roads like NH-30 and SH-15 in the region;  It should take in to account the future traffic growth and management;  It should be coordinated with local and national development plans,  It should minimize environment impact along the corridor;  It should take in to consideration the opinions of local people in selection of alignment.

7

20. The specific measures adopted for minimizing the resettlement impacts for the subproject are as follows:

 Exploration of several alternate alignments in consultation with engineering team, concerned government departments and local community;  Following existing local roads as much as possible to minimize the land acquisition in the bypass alignments;  Avoiding major settlements and urban areas to minimize the large scale physical displacement;  Avoiding highly productive agricultural land to minimize the adverse economic displacement;  Diverting the alignment towards the available unused government land to minimize impact on private property.

21. During the impact assessment survey public consultation meetings were organized at various places and based on people’s concerns and suggestions the alignment was adjusted to minimize the resettlement impacts. The resettlement impact minimization efforts and its results are summarized in the Table 1.2.

Table: 1.2 Minimization of Resettlement Impacts

Resettlement Resettlement Sl. Resettlement Impact Impact Before Impact After No. Name of Village Minimization Efforts Action Taken Action Taken 1 Sakaddi Change of Alignment, built-up 60 number of No structures area bypassed permanent affected structures

2 Akhgaon Change of Alignment, built-up 36 structures No structures area bypassed affected affected

3 Nanaur Change of Alignment, built-up 54 structures No structures area bypassed affected affected

4 Andhari Change of Alignment, built-up 53 structures No structures area bypassed affected affected

1.7 Scope and Objective of Resettlement Plan (RP)

22. The aim of this Resettlement Plan (RP) is to mitigate all such unavoidable negative impacts caused due to the project and resettle the displaced persons and restore their livelihoods. This Full Resettlement Plan has been prepared on the basis of subproject census survey findings and consultation with various stakeholders. The plan complies with ADB Safeguard Policy Statement-2009 designed by ADB to protect the rights of the Displaced Persons (DPs) and communities. The issues identified and addressed in this document are as follows:

. Type and extent of loss of land/ non-land assets, loss of livelihood, loss of common property resources and social infrastructure; . Impacts on indigenous people, vulnerable groups like poor, women and other disadvantaged sections of society

8

. Public consultation and peoples participation in the project; . Existing legal and administrative framework and formulation of resettlement policy for the project; . Preparation of entitlement matrix, formulation of relocation strategy and restoration of businesses/income; . Resettlement and rehabilitation (R&R) cost estimate including provision for fund and; . Institutional framework for the implementation of the plan, including grievance redress mechanism and monitoring and reporting.

9

CHAPTER 2 METHODOLOGY FOR IMPACT ASSESSMENT

2.1 Resettlement Screening

23. A social screening exercise was performed through a reconnaissance survey to gather first hand information on impact on land acquisition and resettlement with specific attention on land use, presence of legal and/or illegal housing, traffic patterns, cultural resources, urban settlements and other sensitive areas. The aim of reconnaissance survey was to assess the scope of land acquisition and resettlement study and accordingly the detailed plan of action was prepared for the preparation of land acquisition planning and resettlement plan.

2.2 Land Acquisition Planning

24. The alignment was finalized as per the detailed engineering design. Initially, the numbers of affected villages were identified as per the alignment. All the village maps were collected from the local revenue offices. The village maps were digitized by the detailed design consultant. Following the digitization of village maps, the engineering design of the alignment was superimposed in the digitized cadastral map in order to identify the number of land parcels and their demarcation including the quantification. The superimposition of alignment on the village map provided all the plot numbers. A Land Acquisition Plan (LAP) has been prepared accordingly. Based on the identified land plots, a team of local enumerators were hired and local revenue officials were consulted to collect the names of owners of each plot.

2.3 Census Survey and Inventory of Assets

25. Following finalization of the road alignment and identification of the land parcels, cross- sections design and land acquisition requirements, census of all displaced persons (DPs) was carried in the subproject. The objective of the project census survey was to identify the persons who would be displaced by the project and to make an inventory of their assets that would be lost to the project, which would be the basis of calculation of compensation. A structured census questionnaire (Appendix 1) was used to collect detailed information on affected households/ properties for a full understanding of impacts in order to develop mitigation measures and resettlement plan for the DPs. The survey team was trained by the resettlement specialist and the survey was closely monitored on a regular basis. Additionally, socioeconomic data was also collected as part of the social impact assessment study. The census survey includes the following:

 Inventory of the 100% land and non-land assets  Categorization and measurements of potential loss  Physical measurements of the affected assets/structures  Identification of trees and crops  Household characteristics, including social, economic and demographic profile  Identification of non titleholders  Assessment of potential economic impact

10

2.4 Public Consultation

26. To ensure peoples’ participation in the planning phase and aiming at promotion of public understanding and fruitful solutions of developmental problems such as local needs of road users and problem and prospects of resettlement, various sections of affected persons and other stakeholders were consulted through focus group discussions, individual interviews and formal and informal consultations. The vulnerable sections of DPs and women were also included in this consultation process.

11

CHAPTER 3: SOCIOECONOMIC INFORMATION AND PROFILE

3.1 Socioeconomic Profile of Project Area

27. The subproject road SH-81 begins at Sakaddi village and terminates at Nasrigunj. It connects NH-30 (Mohania - Bakhtiyarpur) to SH-15 (Dehri -Vikramgunj). The total length of project road is 83.250 kms and runs parallel to Sone River. The road runs majorly through agricultural fields and many built-up areas. Some of the heavy settled areas include Sakaddi, Chandi, Akhgaon, Sandesh, Naunur, Azimabad, Andhari and Kachwa. It also crosses many canals/drains at various locations. About 13.93% population of Bhojpur are living in urban area whereas about 13% population of Rohtas are living in the urban areas. Being the headquarter Aara and Sasaram have all major facilities like educational institutes, hospitals, markets, etc.

28. The density of population of Bhojpur districts (903) is substantially higher than the state average of 880 persons per sq km however the density of Population in Rohtas is lower than state. While sex ratio, determined by number of females per one thousand males, of Bhojpur district (900) is comparable to the state average of 919, Rohtas district recorded a better ratio of 909. Bihar does not have any significant number of tribal population, 0.9% of total population, after division of the state into two, the other half being Jharkhand, the home of many scheduled tribes. This trend is also reflected in the two districts. Proportion of scheduled caste population in Bihar is 15.7%. A similar ratio is also shown in Bhojpur with 15.31% while Rohtas has higher proportion with 18.13% of scheduled caste population.

29. Proportion of literates is higher in both the districts as evident from 47.83% in Bhojpur and 49.18% in Rohtas compared to Bihar state, 47.3%. Female literacy is much lower than that of male, which is reflected in 66.55% male literates and about 33.44% female literates in Bhojpur while that of Rohtas are 64.68% male literates against 35.31% females literates. Some of the vital spastics are presented in the Table: 3.1.

Table 3.1: Some Vital Statistics of Project Area

Statistic District Male Female Total Bhojpur 1,179,611 1,063,533 2,243,144 Total Population Rohtas 1,283,485 1,167,263 2,450,748 Bhojpur 3,12,414 169,535 142,879 Urban Population Rohtas 173,402 153,404 326,806 Bhojpur 181,372 162,226 343,598 SC Population Rohtas 233,512 210,821 444,333 Bhojpur 4,457 3,880 8,337 ST Population Rohtas 13,479 12,184 25,663 Bhojpur 714,185 358,825 1,073,010 Literacy Level Rohtas 779,613 425,674 1,205,287 Source: Census of India, 2001

12

30. Some of the socioeconomic information of DPs was collected through the census survey and its findings are presented in the following sections.

3.2 Social Categories of the DPs

31. The social stratification of the subproject area shows the dominance of Higher Caste population with 1183 (52.16%) households. The second stratum of the social grouping in the area is of other backward caste (OBC) population with 775 (34.17%) households followed by Scheduled Caste 310 (13.67%) households. The presence of schedule tribe (ST) population in the subproject area is nil as no household from the ST community is being affected by the project implementation. The detail of social grouping in the subproject area is presented in the Table 3.2.

Table 3.2: Social Categories of DPs along the Project Road

Non- titleholder Titleholder Sl. No. Social Category Household Household Total Percentage 1 SC 120 190 310 13.67 2 OBC 300 475 775 34.17 3 General 486 725 1,183 52.16 Total 878 1,391 2,269 100 Source: Census Survey, Bihar State Highways II Project, 2010

3.3 Religious Categories of the DPs

32. The subproject area is dominated by Hindu community as they form 2225 (98.06%) of the total 2269 DPs. Muslims are 44 in number and they form 1.94 % of the total affected population. The religious categories of DPs are presented in the Table 3.3.

Table 3.3 Religious Categories of the DPs

Religious Non-titleholder Titleholder Sl. No. Group Household Household Total Percentage 1 Hindu 861 1364 2225 98.06 2 Muslim 17 27 44 1.94 Total 878 1391 2269 100 Source: Census Survey, Bihar State Highways II Project, 2010

3.4 Number of DPs

33. There are altogether 13,147 DPs concerning to titled and non-titled categories, that are being affected by the subproject. It includes 7226 (54.96%) males and 5921 (45.04%) females. The number of DPs is substantially significant in the project area mainly because presence of joint family system and a large number of shareholders of landed properties. The details of DPs being affected in the subproject are summarized in the Table 3.4.

13

Table 3.4: Number of DPs

Sl. Non-titleholder Titleholder No. Category DPs DPs Total Percentage 1 Male 2,975 4,251 7,226 54.96 2 Female 2,438 3,483 5,921 45.04 Total 5,413 7,734 13,147 100 Source: Census Survey, Bihar State Highways II Project, 2010

3.5 Vulnerable Households being Affected in the Subproject

34. In the subproject area there are 351 households falling below poverty line (BPL). The State Government of Bihar has identified them and distributed BPL cards to such families. In this subproject among other vulnerable group there are 27 aged person and 11 households are headed by physically handicapped people. The detail arrangements of vulnerable households in different categories are presented in the Table 3.5.

Table 3.5: Vulnerable Households being affected

Vulnerable Non-titleholders Sl. No. category Encroachers Squatters Titleholders Total %age 1 SC 99 2 19 120 5.29 2 BPL 289 3 59 351 15.47 3 WHH 1 0 3 4 0.18 4 PH 11 0 0 11 0.48 5 Aged 50+ 14 1 12 27 1.19 Total Vulnerable 414 6 93 513 22.61 Non-Vulnerable 450 8 1,298 1,756 77.39 Total Affected 864 14 1,391 2,269 100 households Source: Census Survey, Bihar State Highways II Project, 2010

3.6 Annual Income Level of the Affected Households

35. The number of BPL population, is further strengthen from the data analyzed on the basis of monthly income of the households, which reflects that there are 351 (31.78%) households, which are having an average monthly income of less than Rs. 22000/, i.e., BPL level. 47.72 % DPs are having income Rs. 22,000-30,000, while 8 (0.34%) households are annually earning more than Rs. 100,000 only. The average income level of households in the subproject area is summarized in the Table 3.6.

14

Table 3.6: Annual Income Level of the Affected Households

Sl. No. Annual Income (Rs.) Total Percentage 1 Up to 22,000 (BPL Level) 351 31.78 2 22,000 to 30,000 1,083 47.72 3 30,000 to 40,000 538 7.4 4 40,000 to 60,000 147 6.49 5 60,000 to 80,000 44 1.94 6 80,000 to 100,000 49 2.16 7 100,000 to 200,000 49 2.16 8 Above 200,000 8 0.34 Total 2,269 100.00 Source: Census Survey, Bihar State Highways II Project, 2010

3.7 Educational Status of DPs

36. The educational status of head of the households reveals that overall scenario of literacy level is not encouraging in the project area as significant percentage of population, i.e., 11.94 % and 32.39 % are either illiterate or has attained the education up to elementary level respectively. 39.31% DPs are Graduate, while very few (1.14%) have degree of master and above, which are presented in the Table 3.7.

Table 3.7: Educational Status of DPs

Non- Educational titleholder Titleholder Sl. No. Qualification Male Female Male Female Total Percentage 1 Illiterate 57 0 212 2 271 11.94 Primary 331 1 402 1 2 Education 735 32.39 3 10th Pass 84 0 132 0 216 9.52 4 12th Pass 50 0 79 0 129 5.69 5 Graduate 345 0 547 0 892 39.31 6 Above 10 0 16 0 26 1.15 Total 877 1 1,388 3 2269 100.00 Source: Census Survey, Bihar State Highways II Project, 2010

3.8 Occupational Status of DPs

37. The occupational pattern of DPs reveals that 47.47% DPs are having agriculture as their main occupation. Among other categories, 32.13% DPs are working as laborers, followed by 6.17% having service as their main profession, 10.58% are engaged in business and only 0.35% DPs are professionals of different categories. The details of occupational status of DPs are summarized in the Table 3.8.

15

Table 3.8: Occupational Status of DPs

Non-titleholder Titleholder Sl. No. Occupation Male Female Male Female Total Percentage 1 Service 54 0 86 0 140 6.17 2 Business 92 1 147 0 240 10.58 3 Agriculture 418 0 659 0 1,077 47.47 4 Labor 282 0 447 0 729 32.13 5 Professional 3 0 5 0 8 0.35

6 Rural Artisan 1 0 2 0 3 0.13 7 Small Trader 22 0 35 0 57 2.51 8 Self-employed 5 0 8 0 13 0.57 9 Unemployed 0 0 0 3 3 0.13 Total 877 11,388 3 2,269 100 Source: Census Survey, Bihar State Highways II Project, 2010

3.9 Impact on Indigenous People

38. The Scheduled Tribes (STs) in the project area is considered to be IP. The presence of ST population in both the district as displaced person is nil. The census survey finding shows that there is no DP who belongs to the ST community.

3.10 Gender Impact and Mitigation Measures

39. The gender composition of DPs shows that the male accounts for 54.96% and female accounts for 45.04%. The gender disparity is visible in lower sex ratio among DPs i.e. 819 against state level statistic having 929. The census survey revealed that four women headed households will be affected by the subproject.

40. Out of these four households three are losing their land only and another one DP are losing commercial structures only and belong to squatter.

41. The educational level of these female DPs shows that three of them are illiterate, while one female DP is having education up to primary level. The occupational status of these females heading the households reveals that one is engaged in small shop, while three are housewives and not engaged in any economic activities.

42. The participation of women in FGDs during the census survey was not encouraging because of their shy nature and ignorance. Out of eight FGDs conducted along the road sections women members were turned up only at four locations and very few in number. Some of their specific concerns are summarized below.

16

 The working women and girl students face a lot of problems for travel, due to non- availability of good road and transport network. Especially in rainy season, the problem increases manifold which sometimes compels the girl students abstains from classes.  Only primary health centers (PHCs) are located at some villages and the quality of treatment and medical facilities are less than satisfactory. In emergency they have to reach hospitals at district headquarters only.  Health status will improve as they will be able to visit government hospital at Patna if sick and especially during pregnancy and will not have to depend on uneducated rural midwife for safe delivery, which are common in villages. Incidence of child mortality & maternal mortality rate will reduce with easy access to government health care facility centres.  The women feel that their mobility will increase as market & relatives’ places will be easily accessible for them as better road condition will induce more transport vehicles to operate. More shops, markets will open within the village approach area and as a result they will get quality leisure time at their disposal.  Women from poor families will get job opportunity during construction work as casual labor or at office. Besides, women can operate individual / family enterprise by opening small tea stalls, shops/eateries to provide meals to the construction laborers. This will enhance their family income as well as their entrepreneurial skill which may be useful in future.  Women laborers feel that improved road network will provide them with better job opportunity as they will be able to travel further and even can commute from home. Moreover, travel by public transport system, like Govt. bus service, will become cheaper and money saved on transport can be better utilized for household needs.  The girl students will be able to attain higher education at colleges, since journey time and cost will be greatly reduced and the girls can commute from home all by themselves free of hazard.

43. Women will not be affected negatively due to the program. Any negative impacts of the subproject on female-headed households will be taken up on a case-to-case basis and assistance to these households will be treated on a priority basis. During disbursement of compensation and provision of assistance, priority will be given to female-headed households. Additionally, women headed households are considered as vulnerable and provision for additional assistance (lump sum amount at Rs.10, 000 per affected households) has been made in the entitlement of the RP. Provision for equal wage and health safety facilities during the construction will be ensured by the EA. Therefore, the subproject activities will not have any negative impact on women.

17

CHAPTER 4 SCOPE OF LAND ACQUISITION AND RESETTLEMENT

4.1 Scope of Land Acquisition

44. As discussed earlier also the scope of land acquisition is quite significant in the subproject because of availability of limited ROW and construction of four Bypasses. According to the Land Acquisition Plan (LAP) prepared as a part of Detailed Design Report, 269.62 Acres of land will be acquired for the subproject. The area is excluding the area that already lies with Road Construction Department in terms of existing roads falling in the alignment. A project census survey was carried out to identify the persons who would be displaced by the project and to make an inventory of their assets that would be lost to the project, which would be the basis of calculation of compensation. The major findings and magnitude of impacts are discussed in the following sections.

4.2 Loss of land

45. Many DPs will be losing their land to the project and their livelihoods as well as dwellings are affected. The details of subproject impact on land and various types of loss due to the land loss is discussed in this section.

4.2.1 Ownership of Land Being Acquired for the Subproject

46. Out of 269.62 acres of land, which are going to be affected, 257.78 (95.61%) acres land is privately owned, while 11.59 (4.30%) Acres land belongs to government and rest 0.25 acre land is owned by various agencies. There are four land units belong religious and community ownership. The details of land acquisition requirement are summarized in the Table 4.1.

Table 4.1: Details of Land being acquired for the Subproject

Area of land Sl. No. Type of Land No. of Plots (in Acre) % 1 Private Land 1235 257.78 95.61 2. Govt. Land 113 11.59 4.30 2 Religious land/ others 04 0.25 0.09 Total 1,352 269.62 100.00 Land Acquisition Plan, Detailed Design Report, 2010

4.2.2 Type of the Land Being Acquired for the Subproject

47. The land being acquired for the subproject is of various types such as irrigated 206.40 acres (76.55%), non-irrigated 55.44 acres (20.56%), barren 3.59 acres (1.33%) and 4.19 Acres (1.55%) of others categories. Various types of land area with number of plots are presented in the Table 4.2.

18

Table 4.2: Type of the Land being acquired for the Subproject

Sl. No. Type of Land No. of Plots Area (in Acre) % 1 Irrigated 1035 206.40 76.55 2 Non-Irrigated 278 55.44 20.56 3 Barren 18 3.59 1.33 4 Other 21 4.19 1.55 Total 1,352 269.62 100.00 Source: Census Survey, Bihar State Highways II Project, 2010

4.2.3 Use of Land Being Acquired for the Subproject

48. The land use pattern for land to be acquired for the subproject shows that 226.43 Acres (83.98%) of land are being used for cultivation. Among other categories of land use, residential land is 16.31 acres (6.05%), orchard is in 2.16 acres (0.80%) and land used for commercial purpose is 7.60 acres (2.82%) etc. Barren land accounts to 0.24% of total land to be acquired. Details of land use pattern including number of plots are given in the Table 4.3.

Table 4.3: Use of Land Being Acquired for the Subproject

Sl. No. Land Usage No. of No. of Area (in % Plots Households Acre) 1 Cultivation 1,164 1,314 226.43 83.98 2 Orchard 4 10 2.16 0.80 4 Residential 60 60 16.31 6.05 5 Commercial 07 07 7.60 2.82 7 Other/Govt 99 0 16.47 6.11 8 No Use/Barren 18 0 0.65 0.24 Total 1,352 1,391 269.62 100.0 Source: Census Survey, Bihar State Highways II Project, 2010

4.2.4 Ownership Type of Private Land

49. All the private land being acquired for the subproject is owned by titleholders only. Small number of squatters is also found. Out of 1235 private plots, 739 (59.87%) plots are owned by single household whereas 456 (36.92%) plots are owned by two or more households. It was not possible to ascertain the ownership pattern of 40 (4.5%) plots. The ownership pattern of private land is summarized in the Table 4.4.

Table 4.4: Ownership Pattern of Private Land

Sl. No. Ownership Pattern No. of land Unit/ Plot % 1 Single 739 59.87 2 Joint 456 36.92 3 Other/not specified 40 3.21 Total 1,235 100.00 Source: Census Survey, Bihar State Highways II Project, 2010

19

4.2.5 Scale of Impact on Affected Private Land Units/ Plots

50. The analysis of data on scale of impacts on private land reveals that 913 (73.93%) plots are losing more than 10% of their land, followed by 322 (26.07%) plots losing up to 10%. 250 (20.22%) plots are losing between 50% and 75% and 108 (8.74%) plots are losing from 75% to 100% of their respective areas. The details of scale of impacts on private plots are presented in the Table 4.5.

Table 4.5: Scale of Impact on Affected Private Land Units/ Plots

Sl. No. Scale of Impact No. of land Unit/ Plot % 1 Up to 10% 322 26.07 2 Above 10% and Below 25% 242 19.59 3 Above 25% and Below 50% 313 25.38 4 Above 50% and Below 75% 250 20.22 5 Above 75% and up to 100% 108 8.74 Total 1,235 100.00 Source: Census Survey, Bihar State Highways-II Project, 2010

4.3 Loss of Structure in the Subproject

51. During the census survey large number of encroachers was enumerated along the existing road, mostly in the government land. Based on the social survey data, it is estimated that a total of 746 structures would be affected due to the improvement of the project road and all the structures belong to non titleholders. Out of 746 affected structures, 672 are private properties, 49 are religious, 22 are government structures and only three are other community structures as detailed in Table 4.6. Out of 49 religious structures only two are owned by religious body and rest of the 47 are existing within the ROW.

Table 4.6: Loss of Structure

Sl. No. Type of Properties No. of affected structure % 1 Private 672 90.08 2 Religious 49 6.57 3 Government 22 2.95 4 Community 3 0.40 Total 746 100.00 Source: Census Survey, Bihar State Highways II Project, 2010

4.3.1 Type of Construction of Affected Structure

52. The construction type of structures being affected in the subproject area are of various types such as temporary, semi-permanent and permanent. Out of 746 structures, 262 (35.12%) structures are permanent, 467 (2.60%) structures are semi-permanent and 17 (2.28%) structures are of temporary nature. The details of type of constructions of the affected structures are summarized in the Table 4.7. .

20

Table 4.7: Type of Construction of Affected Structure

Type of Sl. No. construction No. of affected structure % 1 Permanent 262 35.12 2 Semi-Permanent 467 62.60 3 Temporary 17 2.28 Total 746 100.00 Source: Census Survey, Bihar State Highways II Project, 2010

4.3.2 Age of Structures Being Affected in the Subproject

53. To know the condition of structures, the age of structures being affected due to the subproject was enumerated during the census survey. Among 746 affected structures, 291 (39%) structures are newly constructed and up to 5 years old only and another 254 (34%) structures are aged between 5 to 10 years followed by 99 (13.30%) structures aged between 10 to 15 years. There are 29 (3.85%) affected structures aged above 35 years. The details of age of affected structures are presented in the Table 4.8.

Table 4.8: Age of Structures Being Affected in the Subproject

Sl. No. Age of Structure No. of Structure % 1 Up to 5 Years 291 39.00 2 Above 5 Years and below 10 Years 254 34.00 3 Above 10 Years and below 15 years 99 13.30 4 Above 15 Years and below 25 years 49 6.56 5 Above 25 Years and below 35 Years 25 3.29 6 Above 35 Years 29 3.85 Total 746 100.00 Source: Census Survey, Bihar State Highways II Project, 2010

4.3.3 Type of Private Structures Affected in the Subproject

54. As per census survey, out of 672 private structures affected in the subproject, 517 (76.93%) structures are of residential type, 78 (11.61%) are of commercial type and 77 (11.46%) are of residential-cum-commercial type .The details of structures are given in the Table 4.9.

Table 4.9: Type of Structures Affected in the Subproject

Type of Private No. of affected structure Sl. No. Total % Property Left Right 1 Residential 209 308 517 76.93 2 Commercial 35 43 78 11.61 3 Res-cum-commercial 39 38 77 11.46 Total 283 389 672 100.00 Source: Census Survey, Bihar State Highways II Project, 2010

21

4.3.4 Scale of Impact on Private Structure

55. The severity of impact on any structure is determined by percentage of impact on the properties and the usable status of residual part of the structure. The impact percentage on the structures is being examined from its distance from the centerline and the total area of the structures. This analysis helps to know that whether the remaining part of the structure would serve any purpose. As per the collected information during the social survey, approximately 17.02% of the affected structures are located completely within 6 meter from the centerline, and 27.08% of the structures are having 50% impact. At the same time, nearly 16.09% of the affected structures are minimally affected i.e. up to 1/4th of the total structure. The exact details for scale of impact on structures are given in Table 4.10.

Table 4.10: Scale of Impact on private structure

Impact Scale of Impact on No. of Sl. No. % Categories structures Structures 1 Up to 10% of the Structure 9 1.21 More than 10% to 25% of 2 108 16.09 Partly Impacted the Structure 25% to 50 % of the 3 182 27.08 Structure 4 50% to 75 % of the Structure 259 38.61 5 Fully impacted 100 % of the Structure 114 17.02 Total 672 100.00 Source: Census Survey, Bihar State Highways II Project, 2010

4.3.5 Indirect Impacts on DPs by Loss of Private Structure

56. As summarized in the Table 4.11 in terms of indirect impacts on DPs due to loss of private structures, 186 tenants and 20 employees will be adversely affected due to implementation of the subproject.

Table 4.11: Indirect Impact on DPs by Loss of Private Structure

Sl. No. Category of Impact No. of Household % 1 Tenant 186 90.29 2 Employee in Residential Structure 20 9.71 Total 206 100.00 Source: Census Survey, Bihar State Highways II Project, 2010

4.3.6 Impacts on Private Trees

57. Due to the subproject proposal various fruit bearing and non-fruit bearing trees are being affected. Among fruit bearing trees, there are five most common species enumerated in the census surveys, i.e. Mango, Jamun, Ber, and Amrud. The details of impacts on trees are summarized in the Table 4.12.

22

Table 4.12: Impacts on Trees

Sl. No. Category of Impact No. of Household % 1 Fruit Bearing Trees 243 65.85 2 Non Fruit Bearing Trees 126 34.15 Total 369 100.00 Source: Census Survey, Bihar State Highways II Project, 2010

4.4 Loss of Livelihoods

58. Due to loss of land and structures many people will be losing their livelihoods and will be economically displaced. As per the census survey, in addition to 913 owners of agricultural land, 59 agricultural laborers and 67 sharecroppers will also be losing their livelihood due to loss of agricultural land. Other DPs losing livelihoods includes 59 owners of commercial structures, 43 owners of residential- cum- commercial structures and 20 employee in commercial structure. The details of impact on livelihoods in the subproject are presented in the Table 4.13.

Table 4.13: Loss of Livelihood

Sl. No. of No. of % of No. Loss Household DPs Households % of DPs Owners of Agricultural Land 1 913 4,839 66.30 36.81 losing more than 10% 2 Agricultural Laborer 59 236 4.28 1.80 3 Sharecropper 97 437 7.04 3.32 Owners of Commercial 4 Structure (47 Vulnerable 59 177 4.28 1.35 Encroachers + 12 Squatters) Owners of Residential cum Commercial Structure (41 5 43 202 3.12 1.54 Vulnerable Encroachers + 2 Squatters ) Commercial tenant 6 +Residential-cum- 186 911 13.51 6.93 commercial tenant Employee in commercial and 7 Residential- cum-commercial 20 80 1.45 0.61 Structure (20) Total 1,377 6,882 100.00 52.35 Total-N 2,269 13,147 100.00 Source: Census Survey, Bihar State Highways II Project, 2010

4.5 Loss of Community Property Resources (CPRs)

59. During census, it was observed that presence of small temples, graveyards, shrines, mosque and other community properties in the Government land is a common feature all along the road. 52 such structures have been identified, within existing ROW at different locations.

23

Most of the identified structures are only partially being affected and during construction period some of these structures can be saved through local adjustment. However, if required the people are agreed to relocate those small shrines which may get affected. The detail of number of religious and community properties, which may face relocation, has been mentioned in Table 4.14.

Table 4.14: Impact on Community Property

Sl. No. Type of Religious Structure Number % 1 Small Temple 15 28.85 2 Graveyards (Kabristans) 2 3.85 3 Shrine 31 59.62 4 Mosque 1 1.92 5 Community hall 3 5.77 Total 52 100.00 Source: Census Survey, Bihar State Highways II Project, 2010

4.6 Type of Government Property

60. Other than the religious and community structures, several government owned structures are also likely to be affected due to the road widening. Out of the 22 likely affected government structures, 11 bus stops and 6 schools are also getting affected. The details are summarized in the Table 4.15.

Table 4.15 Impact on Government Properties

No. of Sl. No. Type of Government Property Structures % Primary Health Centre (Boundary 1 1 4.55 wall) 2 Bus Stop 11 50.00 3 Panchayat Office 1 4.55 4 Govt Office 1 4.55 5 Memorials 2 9.09 6 School (Boundary Wall) 6 27.27 Total 22 100.00 Source: Census Survey, Bihar State Highways II Project, 2010

4.7 Summary Subproject Impacts

61. As per findings of the 100% census of affected land and non-land assets, the subproject impacts can be broadly classified as (i) impacts on private land, (ii) impacts on private structures (Encroachers and Squatters), (iii) impacts on livelihoods due to loss of private properties and (iv) loss of common property resources. From the analysis of impacts, it is noted that altogether 1352 land units/plots including 1235 private land units and 746 structures including 672 private structures will be affected due to the subproject work. As per the survey, total 2269 household comprising of 13147 DPs will be affected in the subproject. The details of subproject impacts are discussed in the following section and the summary subproject impacts are presented in the Table 4.16.

24

Table 4.16: Summary Subproject Impacts

Sl. No. Impacts Number 1 Total land acquisition requirements (in acre) 269.62 2 Total private land acquisition requirements (in acre) 257.78 3 Total number of land units/plots affected 1,352.00 4 Total number of private land units/plots affected 1,235.00 5 Total Number of private Trees affected 369.00 6 Total number of private structures affected 672.00 Total number of households affected (Titleholders-1391, Non- 7 titleholders-652, Tenants-186, Wage earner/ employee-20 ) 2,269.00 8 Total Number of Vulnerable households affected 513.00 9 Total number of displaced persons (DPs) 13,147.00 10 Total number of CPRs affected (including 49 Religious structures) 52.00 11 Total number of Government properties affected 22.00 Source: Census Survey, Bihar State Highways II Project, 2009-10

25

CHAPTER 5: STAKEHOLDERS CONSULTATION AND PARTICIPATION

5.1 Stakeholders in the Project

62. Consultations with various stakeholders were carried out during various phases of project preparation. The stakeholders in the project are both primary and secondary. The primary stakeholders are project displaced persons (DPs), project affected persons (APs) such as host community, the EA especially the officials in BSRDC, PMU, PIU and the field level BSRDC staff. Additionally, the concerned district magistrates and the revenue officials are also considered to be the primary stakeholders. Other stakeholders in the project include village heads, head of Gram Panchayat, village administrative officers, heads of households, women’s groups, farmers, business communities, and other vulnerable DPs like the scheduled caste (SC) and BPL people.

5.2 Public Consultation in the Project

63. Numerous consultations were arranged at the stage of project preparation to ensure peoples’ participation in the planning phase of this project and to treat public consultation and participation as a continuous two way process. Aiming at promotion of public understanding and fruitful solutions of developmental problems such as local needs and problem and prospects of resettlement, various sections of DPs and other stakeholders were consulted through focus group discussions and individual interviews.

5.3 Methods of Public Consultation

64. Consultations and discussions were held along the subprojects with the affected families and other stakeholders. These meetings were organized to get wider public input from both the primary and secondary stakeholders. The consultation methods followed to elicit required information (their views & opinions) are detailed below in Table 5.1.

Table 5.1: Methods of Public Consultations

Stakeholders Consultation Method DPs Census and Socioeconomic Survey Village Pradhan/representative of DPs Focus Group Discussions Local communities Focus Group Discussions Women’s groups Focus Group Discussions Vulnerable groups (SC, BPL) Focus Group Discussions BSRDC/EA Individual interview, discussion, joint field visit Line Departments (Revenue Officials) Individual meeting/interview, discussion

5.4 Scope of Consultation and Issues

65. During the consultation process along with census and socioeconomic survey, efforts were made by the study teams to: . Ascertain the views of the DPs, with reference to land acquisition and road alignment; . Understand views of the community on land acquisition, resettlement issues and rehabilitation options;

26

. Identify and assess the major socioeconomic characteristics of the villages to enable effective planning and implementation; . Obtain opinion of the community on issues related to the impacts on community property and relocation of the same. . Examine DPs’ opinion on problems and prospects of road related issues; . Identify people's expectations from subprojects and their absorbing capacity; . Finally, to establish an understanding for identification of overall developmental goals and benefits of the project.

5.5 Findings of Focused Group Discussions

66. Some of the major issues that were discussed and feedback received from the villagers during the course of the consultations and measures taken are summarized in the Table 5.2:

Table: 5.2 Findings of the Consultations

Sl. Number of Issues Name of Location Gender Age Occupation No. Participants Discussed participants 1 Sakaddi, 9  Adequate Shiveshwar M 45 Cultivation Koilber Compensation Singh 2nd for land Rahul Singh M 47 Cultivation January acquisition. Chandra jota M 41 Cultivation 2010  Employment to Kuwnar affected and Nami Ram M 39 Labor local peple Budhiya F 32 Labor during Sukhiya F 40 Labor implementation Badami F 36 Labor of project. Premdhar Rai M 49 Cultivation  Proper safety Dodha Yadav M 36 Cultivation measures should be adopted during the construction of the road.  Provision of space for an auto Stand near the road side for commercial vehicle running on the project road 2 Gharbas 11  Very few Raj Kishor M 18 Bussiness Dih, structures are Rambabu Singh M 40 Labor Gorhadi present in the Munna Shah M 40 Service th Date- 10 left side of the Bali ram M 41 Agriculture July 2009 road, so people Karchan M 34 Bussiness requested to Lanhi Chaudhri M 44 Service avoid widening Shiv Mani M 54 Service of road on the Chudhri right hand side. Ram Sha Singh M 65 Labor  Adequate M 43 Self Bajnath Singh

27

Sl. Number of Issues Name of Location Gender Age Occupation No. Participants Discussed participants compensation employed at a market Jalaludin M 44 Service rate for the loss M 32 Bussiness of structures.  Absence of hospital or any Bateser Yadav other medical facility in the village 3 Chillaus, 12  People Suresh Kumar M 42 Business Sandesh requested to Manoj Kumar M 20 Labor Date- 9th bypass the Manjeet Kumar M 21 Business July 2009 village as many M 23 Self structures are Anil employed built right next Gorakh Sharma M 50 Business to the existing Banshidhar M 28 Business road. Singh  Availability of Sudhir Kumar M 16 Service govt. land on Haripal Singh M 50 Business the right side of Pandit Singh M 49 Business the road, but it Ramvaran M 50 Agriculture is occupied by Yadav squatters. Lallan Singh M 65 Bussiness  Adequate Mahesh M 55 Agriculture compensation for the loss of structures  Proper drainage system is missing; water collects on the road especially after rains.  Provision of lavatory to be made in the village 4 Sahar 13  Effect on the Haridwar M 40 Bussiness Date- 8th existing Chaudhary July 2009 structures and Manpato Kunwar M 34 Service their Lakshmi M 32 Service replacement Narayan Prasad cost. Rajan Dhari M 55 Service  Comparatively Sharma less number of Anil Kr. M 33 Bussiness structures are Ramjanam Pd. M 45 Bussiness present on the RamPersad M 23 Agriculture left hand side Ram of the existing Audesh M 45 Agriculture road Kalicharan Ram M 32 Agriculture  Existing road Bijay Biru M 34 Bussiness condition is Narayan M 56 Bussiness

28

Sl. Number of Issues Name of Location Gender Age Occupation No. Participants Discussed participants very bad Zakir Husain M 40 Agriculture resulting in M 34 Self Garib Shah poor employed transportation F 37 labor Surti devi facilities. 5 Sandesh 19  A large number Nazir Aalam M 32 Bussiness Date- 7th of commercial Sanjay Kr. M 34 Bussiness July 2009 and residential Gupta structures shall Md. Bulan Miya M 32 Labor be affected as Sunil Kr. Gupta M 55 Labor it is a very Sarjudin Ansari M 34 Labor congested Md. Arsad M 60 Labor area. Md. Lal M 34 Bussiness  People Mohammad requested for Upendra Bari M 28 Bussiness bypassing the Jamal Khan M 30 Bussiness village in order Kanhaiya Lal M 25 Agriculture to save the Ram Kr. Shah M 34 Service structures. Radhika Manto M 56 Service  If demolition Dilip Kumar M 54 Service cannot be Sri Raman Shah M 23 Labor avoided, people Lalan Tato M 33 Agriculture demanded for Doman Lal M 42 Agriculture compensation Kameshwar M 40 Agriculture as per the Shah market rates. Gauri F 34 Agri. Labor  Problems M 32 Agriculture related to drinking water, power supply, medical Bishnu facilities, public toilets, drainage system prevail in the area. 6 Kachwa, 13  Good number Ram ramji M 30 Bussiness Gorhadi of structures is Baburam Lathub M 28 Bussiness Date- 6th present along Jaydev Kumar M 34 Labor July 2009 the road that Kamasher M 42 Agriculture shall be Rprajayam affected due to Malike M 32 Bussiness widening. Dishairy Ram M 34 Labor  People are Krishna M 39 Labor willing to Jayar Shar M 44 Agriculture cooperate, Shavaram M 43 Bussiness provided they Shumer Thakur M 34 Bussiness are paid full Jaychand M 33 Bussiness replacement Chandi cost. Sanjay Shyam M 44 Agriculture  Loss of M 32 Agriculture livelihood due Mohamed to affect on

29

Sl. Number of Issues Name of Location Gender Age Occupation No. Participants Discussed participants commercial structures 7 Andhari, 16  Adequate Seti Sha M 57 Bussiness Tarari Compensation Awdesh Rey M 43 Bussiness Date- 5th for land Dava Singh M 29 Agriculture July 2009 acquisition. Bhuneswar Sha M 32 Bussiness  Employment to Santosh Sonar M 40 Labor affected Manoj Shah M 38 Labor persons during Om Narayan M 39 Self implementation Sha employed of project. Baynath Shah M 41 Labor  Overpass in Sohan Shah M 32 Agriculture market area to Anand Bhusan M 57 Bussiness cross the road. M 43 Self Indu Chaudhry employed Dasrath M 29 Bussiness Chaudhry M 54 Self Sanjay employed Kamdev Singh M 34 Service M Self Basisth Yadav 43 employed Surith Yadav M 32 Service 8 Akhgaon, 15  Provision of Rajeshwer Singh M 45 Cultivation Sandesh Bypass Satnarayan M Cultivation th Date- 4  Adequate Singh 49 July 2009 Compensation Ram Narayan M Cultivation for land Singh 43 acquisition. Lalan Singh M 40 Politician  Proper safety Gauri F 37 Petty shop measures Ram Prabandh M Cultivation should be Singh 55 adopted during Shiv Pujan M Cultivation the Singh 45 construction of Ram Prabandh M Cultivation the road. Singh 38  Employment to F Self Sunaina devi affected 48 employed persons during Ramesh Singh M 34 Cultivation implementation Laxamina Singh M 31 Cultivation of project Sita Ram Singh M 41 Cultivation Bhunshwer M Cultivation Singh 43 Rambachan M Cultivation Singh 42 F Kaushalya Devi 35 Labor

67. Based on the consultation with APs their request, the specific measures taken in project planning and various provisions made in the RP are summarized in the Table 5.3.

30

Table 5.3 Specific Measures Taken after Consultation with APs

Sl. No. Issues Measures 1 Considering the people’s view 4 Bypasses have Provision of Bypass been proposed at Sakaddi, Akhgaon, Nanaur, Andhari to avoid the large number of demolition (the detailed analysis also made under Para 21 and Table 1.2 of Chapter-1 of this RP).

2 Keeping in mind the public view all lands proposed Adequate Compensation to be acquired under this project has been for land acquisition compensated as per replacement cost. Land surveys to determine compensation rates was conducted on the basis of current land use and assessment of market value. DPs for voluntary acquisition were ensured a payment of additional 50% registration cost and 60% solatium . The rate were so fixed that the rates established for the project are sufficient to purchase the same quality and quantity of land in the specific area.

3 Employment to affected Provision has been made in the RP to ensure the and local people during employment to the local people at the time of implementation of project implementation of the project

4 Very few structures are The due consideration was taken by the design present in the left side of engineer to propose the widening in the side the road, so people where there is least impact on the structures (for requested to avoid details Design Plan of the Road) widening of road on the right hand side

5.6 Consultation with Officials and Other Stakeholders

68. Other stakeholders in the subproject such as the EA especially the officials in BSRDC, PMU, PIU and the field level BSRDC staff and the concerned district magistrates and the revenue officials were also consulted on various issues. The details of some of such consultations are summarized in the Table: 5.4.

Table: 5.4 Details of Consultation with Officials and Other Stakeholders

Name and designation of Sl. No. Consulted Person Issue Discussed 1 Mr. Girish Chandra Mishra Project progress, coordination with Design (DGM. Technical, BSRDC) Consultant, BSRDC capacity assessment, Coordination with District collector

2 Mr. Suryamani Singh (DGM. Review of subproject resettlement study progress Environment and Social, and preparation of LAP,

31

Name and designation of Sl. No. Consulted Person Issue Discussed BSRDC)

3 Mr. Brijesh Prasad (GM, SH-81 LAP and resettlement plan preparation, BSRDC) progress review

4 Mr. S N Yadav, (DGM, PIU, SH-81 LAP and resettlement plan preparation, Rajgir) progress review, joint site visit

5 Mr. Sanjeev kumar, (AEE, SH-81 LAP and resettlement plan preparation, PIU, Rajgir) progress review, joint site visit

6 Mr. M Safina, District Landholders data collection for SH-81 in Patna Collector, Arrah district, issue of letters to subordinates and guidance for subproject requirement

7 Dr. J K Jha, Deputy Director, Revenue maps and Landholders details collection State Survey and Land for SH-81 section Records, Gulzarbagh, Patna

8 Dr. Poonam Sinha, Circle Landholders details collection for SH-81 section in Officer, Koilber Block Koilber Block, issue of guidance and follow-up

9 Mr. Dharam kumar, Circle Landholders details collection for SH-81 section in Officer, Agiaon Block Agiaon Block, issue of guidance and follow-up

10 Mr. Raghubir Prasad, Circle Landholders details collection for SH-81 section in Officer, Sandesh Block Sandesh Block, issue of guidance and follow-up

11 Mr. Rajender Pathak, Circle Landholders details collection for SH-81 section in Officer, Nasriganj Block Nasriganj Block, issue of guidance and follow-up

12 Mr. Yogeswar Mathur, Circle Landholders details collection for SH-81 section in Officer, Sahar Block Sahar Block, issue of guidance and follow-up

5.7 Plan for further Consultation in the Project

69. The effectiveness of the R&R program is directly related to the degree of continuing involvement of those affected by the Project. Several additional rounds of consultations with DPs will form part of the further stages of project preparation and implementation. A local NGO will be entrusted with the task of conducting these consultations during RP implementation, which will involve agreements on compensation, assistance options, and entitlement package and income restoration measures suggested for the subproject. The consultation will continue

32 throughout the project implementation. The following set of activities will be undertaken for effective implementation of the Plan:

 In case of any change in engineering alignment planning the DPs and other stakeholders will be consulted in selection of road alignment for minimization of resettlement impacts, development of mitigation measures etc.  Together with the NGO, the Project Implementation Unit (PIU) will conduct information dissemination sessions in the project area and solicit the help of the local community/ leaders and encourage the participation of the AP’s in Plan implementation.  During the implementation of RP, NGO will organize public meetings, and will appraise the communities about the progress in the implementation of project works, including awareness regarding road construction.  Consultation and focus group discussions will be conducted with the vulnerable groups like women, SC, ST, and OBC’s to ensure that the vulnerable groups understand the process and their needs are specifically taken into consideration.  To make reasonable representation of women in the project planning and implementation they will be specifically involved in consultation.

70. A Public Consultation and Disclosure Plan will be prepared by PIU/NGO for each of the subprojects as per the format below in Table: 5.5.

Table: 5.5 Format for Public consultation and Disclosure Plan

Timing (Date/ Activity Task Period) Agencies Remarks Stakeholder Mapping of the PIU/Design identification project area Consultant Project Distribution of PIU/NGO information information leaflets dissemination to displaced persons (DPs)

Consultative Discuss potential PIU/Design meetings with DPs impacts of the Consultant during scoping project Phase

Public Notification Publish list of PIU/NGO affected lands/sites in a local newspaper; establish eligibility cut-off date

Socioeconomic Collect socioeconomic PIU/NGO survey information on AP’s perception on

33

Timing (Date/ Activity Task Period) Agencies Remarks the project

Consultative Discuss PIU/Design meetings on entitlements, Consultant resettlement compensation mitigation rates, grievance measures redress Mechanisms

Publicize the Distribute leaflets PIU/NGO resettlement plan or booklets in local (RP) language

Full disclosure of Distribute RP in PIU/NGO the RP to DPs local language to DPs

Internet disclosure RP posted on ADB PMU of the RP and/or EA website

Consultative Face to face PIU/NGO meetings during meetings with DPs detailed measurement survey(DMS)

Disclosure after Disclose updated PIU/NGO DMS RP to DPs

Internet disclosure Updated RP PMU of the updated RP posted on ADB and/or EA website

5.8 Information Disclosure

71. To keep more transparency in planning and for further active involvement of DPs and other stakeholders the project information will be disseminated through disclosure of resettlement planning documents. The EA will submit the following documents to ADB for disclosure on ADB’s website:

(i) the final resettlement plan endorsed by the EA after the census of displaced persons has been completed; (ii) a new resettlement plan or an updated resettlement plan, and a corrective action plan prepared during project implementation, if any; and (iii) the resettlement monitoring reports.

72. The EA will provide relevant resettlement information, including information from the above mentioned documents in a timely manner, in an accessible place and in a form and

34 language(s) understandable to affected persons and other stakeholders. A resettlement information leaflet containing information on compensation, entitlement and resettlement management adopted for the subproject will be made available in local language (Hindi) and distributed to DPs.

35

CHAPTER 6: LEGAL FRAMEWORK

6.1 Introduction

73. The legal framework and principles adopted for addressing resettlement issues in the Project have been guided by the existing legislation and policies of the GOI, the Government of Bihar, Asian Development Bank and the Resettlement Framework (RF) adopted for the project. Prior to the preparation of the Resettlement Plan, a detailed analysis of the existing national and state policies was undertaken and a RF has been prepared for the entire program. The section below provides details of the various national and state level legislations studied and their applicability within this framework. This RP is prepared based on the review and analysis of all applicable legal and policy frameworks of the country and ADB policy requirements. A summary of applicable acts and policies is presented in the following paragraphs and the detailed policy review and comparison is provided in the RF.

6.2 Land Acquisition Act 1894

74. The Land acquisition Act (LAA) 1894, as amended in 1984 provides the legal framework for land acquisition for a public purpose in India. It enables the State Government to acquire private lands for a public purpose, and seeks to ensure that no person is deprived of land except under the Act. The general process for land acquisition under LAA is:

 Land identified for a project is placed under Section 4 of the LAA. This constitutes notification with Government’s intension to acquire land. Objections must be made within 30 days to the District Collector (DC, highest administrative officer of the concerned District).  The land is then placed under Section 6 of the LAA. This is a declaration made by the Government for acquisition of land for public purpose. The DC is directed to take steps for the acquisition, and the land is placed under Section 9. Interested parties are then invited to state their interest in the land and the price. Under Section 11, the DC shall make an award within one year of the date of publication of the declarations.  In case of disagreement on the price awarded, within 6 weeks of the award the parties (under Section 18) can request the DC to refer the matter to the Courts to make a final ruling on the amount of compensation.  Once the land has been placed under Section 4, no further sales or transfers are allowed.  Compensation for land and improvements (such as houses, wells, trees, etc.) is paid in cash by the project proponent to the State government, which in turn compensates landowners.

75. The price to be paid for the acquisition of agricultural land is based on the circle rate recorded at the District Registrar's office averaged over the three years preceding notification under Section The compensation is paid after the area is acquired. An additional 30% is added to the award as well as an escalation of 12% per year from the date of notification to the final placement under Section 9. For delayed payments, after placement under Section 9, an additional 9% per annum is paid for the first year and 15% for subsequent years.

36

76. Under the Land Acquisition Act 1894, compensation is paid only to the legal titleholders and does not provide any compensation package to the non-titleholders like encroachers, squatters etc.

6.3 National Rehabilitation and Resettlement Policy, 2007 (NRRP-2007)

77. The National Rehabilitation and Resettlement Policy, 2007 (NRRP-2007) was adopted by the Government of India in 31st October, 2007 to address development-induced resettlement issues. The policy provides for the basic minimum requirements, and all projects leading to involuntary displacement of people must address the rehabilitation and resettlement issues comprehensively. The State Governments, Public Sector Undertakings or agencies, and other requiring bodies shall be at liberty to put in place greater benefit levels than those prescribed in the NRRP-2007. The principles of this policy may also apply to the rehabilitation and resettlement of persons involuntarily displaced permanently due to any other reason. The objectives of the National Rehabilitation and Resettlement Policy are as follows:

 to minimize displacement and to promote, as far as possible, non-displacing or least-displacing alternatives;  to ensure adequate rehabilitation package and expeditious implementation of the rehabilitation process with the active participation of the affected families;  to ensure that special care is taken for protecting the rights of the weaker sections of society, especially members of the Scheduled Castes and Scheduled Tribes, and to create obligations on the State for their treatment with concern and sensitivity;  to provide a better standard of living, making concerted efforts for providing sustainable income to the affected families;  to integrate rehabilitation concerns into the development planning and implementation process; and  where displacement is on account of land acquisition, to facilitate harmonious relationship between the requiring body and affected families through mutual cooperation.

78. Some of the salient features of the National Rehabilitation and Resettlement Policy, 2007 are listed below.

 The benefits to be offered to the affected families include; land-for-land, to the extent Government land would be available in the resettlement areas; preference for employment in the project to at least one person from each nuclear family subject to the availability of vacancies and suitability of the displaced person; training and capacity building for taking up suitable jobs and for self-employment; scholarships for education of the eligible persons from the affected families; preference to groups of cooperatives of the affected persons in the allotment of contracts and other economic opportunities in or around the project site; wage employment to the willing affected persons in the construction work in the project; housing benefits including houses to the landless affected families in both rural and urban areas; and other benefits.  Financial support to the affected families for construction of cattle sheds, shops, and working sheds; transportation costs, temporary and transitional accommodation, and comprehensive infrastructural facilities and amenities in the resettlement area including education, health care, drinking water, roads,

37

electricity, sanitation, religious activities, cattle grazing, and other community resources, etc.  A special provision has been made for providing life-time monthly pension to the vulnerable persons, such as the disabled, destitute, orphans, widows, unmarried girls, abandoned women, or persons above 50 years of age (who are not provided or cannot immediately be provided with alternative livelihood).  Special provision for the STs and SCs include preference in land-for-land for STs followed by SCs; a Tribal Development Plan which will also include a program for development for alternate fuel which will also include a program for development for alternate fuel and non-timber forest produce resources, consultations with Gram Sabhas and Tribal Advisory Councils, protection of fishing rights, land free- of-cost for community and religious gatherings, continuation of reservation benefits in resettlement areas, etc.  A strong grievance redressal mechanism has been prescribed, which includes standing R&R Committees at the district level, R&R Committees at the project level, and an Ombudsman duly empowered in this regard. The R&R Committees shall have representatives from the affected families including women, voluntary organizations, Panchayats, local elected representatives, etc. Provision ahs also been made for post-implementation social audits of the rehabilitation and resettlement schemes and plans.  For effective monitoring of the progress of implementation of R&R plans, provisions have been made for a National Monitoring Committee, a National Monitoring Cell, mandatory information sharing by the States and UTs with the National Monitoring Cell, and Oversight Committees in the Ministries/Departments concerned for each major project, etc.  For ensuring transparency, provision has been made for mandatory dissemination of information on displacement, rehabilitation and resettlement, with names of the displaced persons and details of the rehabilitation packages. Such information shall be placed in the public domain on the Internet as well as shared with the concerned Gram Sabhas and Panchayats, etc. by the project authorities.  A National Rehabilitation Commission shall be set up by the Central Government, which will be duly empowered to exercise independent oversight over the rehabilitation and resettlement of the affected families.  Under the new Policy, no project involving displacement of families beyond defined thresholds2 can be undertaken without a detailed Social Impact Assessment, which among other things, shall also take into account the impact that the project will have on public and community properties, assets and infrastructure; and the concerned Government shall have to specify that the ameliorative measures for addressing the said impact, may not be less than what is provided under any scheme or program of the Central or State Government in operation in the area. The SIA report shall be examined by an independent multi- disciplinary expert group, which will also include social science and rehabilitation experts. Following the conditions of the SIA clearance shall be mandatory for all projects displacing people beyond the defined thresholds.  The affected communities shall be duly informed and consulted at each stage, including public hearings in the affected areas for social impact assessment,

2 A new project or expansion of an existing project, which involves involuntary displacement of four hundred or more families en masse in plain areas, or two hundred or more families en masse in tribal or hilly areas, DDP blocks or areas mentioned in the Schedule V or Schedule VI to the Constitution.

38

wide dissemination of the details of the survey to be conducted for R&R plan or scheme, consultations with the Gram Sabhas and public hearings in areas not having Gram Sabhas, consultations with the affected families including women, NGOs, Panchayats, and local elected representatives, among others.  The Policy also provides that land acquired for a public purpose cannot be transferred to any other purpose but a public purpose, and that too, only with prior approval of the Government. If land acquired for a public purpose remains un-utilized for the purpose for five years from the date of taking over the possession, the same shall revert to the Government concerned. When land acquired is transferred for a consideration, eighty per cent of any net unearned income so accruing to the transferor, shall be shared with the persons from whom the lands were acquired, or their heirs, in proportion to the value of the lands acquired.  The entitled persons shall have the option to take up to twenty per cent of their rehabilitation grant and compensation amount in the form of shares, if the Requiring Body is a company authorized to issue shares and debentures; with prior approval of the Government, this proportion can be as high as fifty per cent of the rehabilitation grant and compensation amount.

6.4 Bihar Land Acquisition Resettlement and Rehabilitation Policy-2007 (BLARRP- 2007).

79. In February 2007, Government of Bihar has formulated and adopted a policy called Bihar Land Acquisition Resettlement and Rehabilitation Policy-2007 (BLARRP-2007). The policy comprises provision for compensation according to revised rate of land and additional facilities to be provided to the affected families. The main features of policy are as follows:

 To meet the replacement cost of land payment of compensation in revised rate i.e. 50% additional as registration cost plus 30% solatium in compulsory acquisition and 60% solatium, if owners agree to give land voluntarily.  Where homestead land is being acquired the land owner shall be entitled for same area of land being acquired (Maximum 5 Decimal) which shall be acquired for the purpose and shall be handed over to the entitled person.  Every land owner, whose homestead land has been acquired, shall be paid an amount equal to Rs. 10,000 (Rupees Ten thousand) as one time assistance for temporary recommendation.  Every Land Owner whose homestead land is being acquired shall be entitled for a onetime payment of Rs. 5,000.00 (Rupees five thousand only) as assistance for transportation of his household goods.  Displaced agricultural laborer who has been working for a period of minimum three years and who used to earn his livelihood by working on the land which is now under acquisition and who has become jobless because of the acquisition, shall be entitled for onetime payment of two hundred days wages as fixed by the govt. under minimum wages act and shall also be entitled for National/State level job card under National Rural Employment Guarantee Program.

80. The policy specifies that the entire cost for Resettlement and Rehabilitation, in addition to the cost of acquisition of land shall be borne by the respective requisitioning authorities. The Requisitioning Authority shall deposit an amount equivalent to 0.5 percent of the estimated cost of land under acquisition for the project to the Collector-cum-Administrator, Resettlement and

39

Rehabilitation through a bank draft subject to maximum of Rs. 2.0 (Two lacs) only. This amount shall be over and above the amount paid for establishment expenditure under LAA. This additional amount shall be paid for outsourcing the work of survey for Resettlement, Monitoring, Stationeries, POL and other incidentals like vehicle, Computer, Computer Operator, Amins, Drafts man, Chainman etc.

81. The better part of the BLARRP-2007 is that the rate of land offered under it is near to replacement value. The rate of land according to this policy is 85% more then the rate of land being provided by LAA-1894. Additionally the policy also ensure transitional assistance, transportation assistance and assistance for income loss by the DPs

6.5 Asian Development Bank’s (ADB) Policy of Involuntary Resettlement

82. The ADB has adopted Safeguard Policy Statement (SPS) in 2009 including safeguard requirements for environment, involuntary resettlement and indigenous people. The objectives of the Involuntary Resettlement Safeguard policy is to avoid involuntary resettlement wherever possible; to minimize involuntary resettlement by exploring project and design alternatives; to enhance, or at least restore, the livelihoods of all displaced persons in real terms relative to pre- project levels; and to improve the standards of living of the displaced poor and other vulnerable groups.

83. The involuntary resettlement safeguards covers physical displacement (relocation, loss of residential land, or loss of shelter) and economic displacement (loss of land, assets, access to assets, income sources, or means of livelihoods) as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas. It covers them whether such losses and involuntary restrictions are full or partial, permanent or temporary.

84. The main policy principles of the Involuntary Resettlement Safeguard are:

 Screen the project early on to identify past, present, and future involuntary resettlement impacts and risks. Determine the scope of resettlement planning through a survey and/or census of displaced persons, including a gender analysis, specifically related to resettlement impacts and risks.  Carry out meaningful consultations with affected persons, host communities, and concerned non-government organizations. Inform all displaced persons of their entitlements and resettlement options. Ensure their participation in planning, implementation, and monitoring and reporting of resettlement programs. Pay particular attention to the needs of vulnerable groups, especially those below the poverty line, the landless, the elderly, women and children, and Indigenous Peoples, and those without legal title to land, and ensure their participation in consultations. Establish a grievance redress mechanism to receive and facilitate resolution of the affected persons’ concerns. Support the social and cultural institutions of displaced persons and their host population. Where involuntary resettlement impacts and risks are highly complex and sensitive, compensation and resettlement decisions should be preceded by a social preparation phase.  Improve, or at least restore, the livelihoods of all displaced persons through (i) land-based resettlement strategies when affected livelihoods are land based where possible or cash compensation at replacement value for land when the loss of land does not undermine livelihoods, (ii) prompt replacement of assets with access to assets of equal or higher value, (iii) prompt compensation at full

40

replacement cost for assets that cannot be restored, and (iv) additional revenues and services through benefit sharing schemes where possible.  Provide physically and economically displaced persons with needed assistance, including the following: (i) if there is relocation, secured tenure to relocation land, better housing at resettlement sites with comparable access to employment and production opportunities, integration of resettled persons economically and socially into their host communities, and extension of project benefits to host communities; (ii) transitional support and development assistance, such as land development, credit facilities, training, or employment opportunities; and (iii) civic infrastructure and community services, as required.  Improve the standards of living of the displaced poor and other vulnerable groups, including women, to at least national minimum standards. In rural areas provide them with legal and affordable access to land and resources, and in urban areas provide them with appropriate income sources and legal and affordable access to adequate housing.  Develop procedures in a transparent, consistent, and equitable manner if land acquisition is through negotiated settlement to ensure that those people who enter into negotiated settlements will maintain the same or better income and livelihood status.  Ensure that displaced persons without titles to land or any recognizable legal rights to land are eligible for resettlement assistance and compensation for loss of non-land assets.  Prepare a resettlement plan elaborating on displaced persons’ entitlements, the income and livelihood restoration strategy, institutional arrangements, monitoring and reporting framework, budget, and time-bound implementation schedule.  Disclose a draft resettlement plan, including documentation of the consultation process in a timely manner, before project appraisal, in an accessible place and a form and language(s) understandable to affected persons and other stakeholders. Disclose the final resettlement plan and its updates to affected persons and other stakeholders.  Conceive and execute involuntary resettlement as part of a development project or program. Include the full costs of resettlement in the presentation of project’s costs and benefits. For a project with significant involuntary resettlement impacts, consider implementing the involuntary resettlement component of the project as a stand-alone operation.  Pay compensation and provide other resettlement entitlements before physical or economic displacement. Implement the resettlement plan under close supervision throughout project implementation.  Monitor and assess resettlement outcomes, their impacts on the standards of living of displaced persons, and whether the objectives of the resettlement plan have been achieved by taking into account the baseline conditions and the results of resettlement monitoring. Disclose monitoring reports.

6.6 Policy Framework for this Project

85. Based on the above analysis of applicable legal and policy frameworks of the country and in consistent with ADB’s policy requirements the broad resettlement principle for this project shall be the following:  The involuntary resettlement would be avoided wherever possible or minimized as much as possible by exploring project and design alternatives.

41

 The Project or all subprojects under the program will be screened to identify past, present, and future involuntary resettlement impacts and risks. The scope of resettlement planning will be determined through a survey and/or census of displaced persons, including a gender analysis, specifically related to resettlement impacts and risks.  Meaningful consultations with affected persons, host communities, and concerned non-government organizations will be carried out and all displaced persons will be informed of their entitlements and resettlement options. AP’s participation in planning, implementation, and monitoring and reporting of resettlement programs will be ensured.  Particular attention will be paid to the needs of vulnerable groups, especially those below the poverty line, the landless, the elderly, women and children, and Indigenous Peoples, and those without legal title to land, and ensure their participation in consultations.  An effective grievance redress mechanism will be established to receive and facilitate resolution of the displaced persons’ concerns. The social and cultural institutions of displaced persons and their host population will be supported through proper planning. Where involuntary resettlement impacts and risks are highly complex and sensitive, compensation and resettlement decisions should be preceded by a social preparation phase.  The livelihoods of all displaced persons will be improved or at least restored through (i) land-based resettlement strategies when affected livelihoods are land based where possible or cash compensation at replacement value for land when the loss of land does not undermine livelihoods, (ii) prompt replacement of assets with access to assets of equal or higher value, (iii) prompt compensation at full replacement cost for assets that cannot be restored, and (iv) additional revenues and services through benefit sharing schemes where possible.  Physically and economically displaced persons will be provided with needed assistance, including (i) if there is relocation, secured tenure to relocation land, better housing at resettlement sites with comparable access to employment and production opportunities, integration of resettled persons economically and socially into their host communities, and extension of project benefits to host communities; (ii) transitional support and development assistance, such as land development, credit facilities, training, or employment opportunities; and (iii) civic infrastructure and community services, as required.  The standards of living of the displaced poor and other vulnerable groups, including women, will be improved to at least national minimum standards. In rural areas legal and affordable access to land and resources will be provided, and in urban areas appropriate income sources and legal and affordable access to adequate housing will be provided to the displaced poor.  If land acquisition is through negotiated settlement, procedures will be developed in a transparent, consistent, and equitable manner to ensure that those people who enter into negotiated settlements will maintain the same or better income and livelihood status. If, however, the negotiated settlement fails, the normal procedure of land acquisition will be followed.  Displaced persons without titles to land or any recognizable legal rights to land will be ensured that they are eligible for resettlement assistance and compensation for loss of non-land assets.  A resettlement plan will be prepared elaborating on displaced persons’ entitlements, the income and livelihood restoration strategy, institutional

42

arrangements, monitoring and reporting framework, budget, and time-bound implementation schedule.  The draft resettlement plan, including documentation of the consultation process will be disclosed in a timely manner, before project appraisal, in an accessible place and in a form and language(s) understandable to affected persons and other stakeholders. The final resettlement plan and its updates will also be disclosed to displaced persons and other stakeholders.  Involuntary resettlement will be conceived and executed as part of a development project or program. Full costs of resettlement will be included in the presentation of project’s costs and benefits. For a project with significant involuntary resettlement impacts, consider implementing the involuntary resettlement component of the project as a stand-alone operation.  All compensation will be paid and other resettlement entitlements will be provided before physical or economic displacement. The resettlement plan will be implemented under close supervision throughout project implementation.  Resettlement outcomes, their impacts on the standards of living of displaced persons will be monitored; it will be accessed whether the objectives of the resettlement plan have been achieved by taking into account the baseline conditions and the results of resettlement monitoring. Monitoring reports will be disclosed to DPs.  Land acquisition for the project would be done as per both LAA and the BLARRP 2007. To meet the replacement cost of land payment of compensation in revised rate i.e. 50% additional as registration cost plus 60% solatium will be provided to each land holders.  The uneconomic residual land remaining after land acquisition will be acquired as per the provisions of Land Acquisition Act. The owner of such land/property will have the right to seek acquisition of his entire contiguous holding/ property provided the residual land is less than the average land holding of the district.  People moving in the project area after the cut-off date will not be entitled to any assistance. In case of land acquisition, the date of publication of preliminary notification for acquisition under section 4.1 of the Land Acquisition Act, 1894 will be treated as the cut-off date. For non-titleholders the date of project census survey or a similar designated date declared by the executing agency will be considered as cut-off date.  All common property resources (CPR) lost due to the project will be replaced or compensated by the project.

86. The project will recognize three types of displaced persons like (i) persons with formal legal rights to land lost in its entirety or in part; (ii) persons who lost the land they occupy in its entirety or in part who have no formal legal rights to such land, but who have claims to such lands that are recognized or recognizable under national laws; and (iii) persons who lost the land they occupy in its entirety or in part who have neither formal legal rights nor recognized or recognizable claims to such land. The involuntary resettlement requirements apply to all three types of displaced persons.

6.7 Methodology for Determination of Valuation of Assets

87. All lands proposed to be acquired under this project will be compensated as per replacement cost. Land surveys to determine compensation rates will be conducted on the basis current land use and assessment of market value. Records as they are on the cut-off date

43 will be taken into consideration while determining the current use of land. The EA will determine the replacement cost as per BLARRP-2007 based on market survey and in consultation with DPs. After notification for acquisition as per LAA-1894, the EA will negotiate with DPs for voluntary acquisition and ensure payment of additional 50% registration cost and 60% solatium to all DPs. The EA will ensure that the rates established for the project are sufficient to purchase the same quality and quantity of land in the specific area.

88. The compensation for houses, buildings and other immovable properties will be determined on the basis of replacement cost as on date without depreciation. The EA will determine the replacement cost of structures in consultation with the owners by assessing (i) sources and cost of materials, whether the materials are locally available; (ii) type of shops (private or state-owned); (iii) distance to be traveled to procure materials; (iv) obtaining cost estimates through consultation with three contractors/suppliers in order to identify cost of materials and labor; (v) identifying the cost of different types of houses of different categories and compare the same with district level prices.

89. Cash compensation for properties belonging to the community if opted by the community, will be provided to enable construction of the same at new places through the community/ local self-governing bodies / appropriate authority in accordance with the modalities determined by such bodies / authority to ensure correct use of the amount of compensation.

90. Compensation for trees will be based on their market value. Loss of timber trees will be compensated at their replacement cost while the compensation for the loss of fruit bearing trees will be calculated as annual produce value for at next 15 years depending on the nature of crops/trees.

6.8 Procedure and Steps of Land Acquisition

91. The land acquisition in this subproject context will be accordingly the Land acquisition Act (LAA) 1894, as amended in 1984 along with additional provision made under Bihar Land Acquisition Resettlement and Rehabilitation Policy-2007 (BLARRP-2007). The process for land acquisition in the subproject will be as follows:

1. All the land identified for the subproject will be placed under Section 4 of the LAA-1984 and a notification with Government’s intension to acquire land will be issued by the District Collector (DC). 2. Objections if any must be made within 30 days to the District Collector by the landowners. 3. The land will be then placed under Section 6 of the LAA where a declaration will be made by the Government for acquisition of land for public purpose. 4. The DC will take steps for the acquisition, and the land is placed under Section 9 and notice will be issued by the DC in the name of persons interested. 5. Once the land is placed under Section-9, the EA with the help of NGO will negotiate with DPs for voluntary acquisition to ensure payment of additional 50% registration cost and 60% solatium to all DPs. 6. Under Section 11, the DC will make declaration of award and disburse the compensation to the DPs.

44

CHAPTER 7 ENTITLEMENTS, ASSISTANCE AND BENEFITS

7.1 Definition of DPs and Eligibility

92. The project will have three types of displaced persons i.e., (i) persons with formal legal rights to land lost in its entirety or in part; (ii) persons who lost the land they occupy in its entirety or in part who have no formal legal rights to such land, but who have claims to such lands that are recognized or recognizable under national laws; and (iii) persons who lost the land they occupy in its entirety or in part who have neither formal legal rights nor recognized or recognizable claims to such land. The involuntary resettlement requirements apply to all three types of displaced persons. DPs entitled for compensation, assistance and rehabilitation provisions under the subproject are:

 All DPs losing land either covered by formal legal title, recognizable title , or without legal status;  Tenants and sharecroppers whether registered or not;  Owners of buildings, crops, plants, or other objects attached to the land; and  DPs losing business, income, and salaries

93. Compensation eligibility is limited by a cut-off date as set for this project on the day of the beginning of the census survey which is 10th June 2009. DPs who settle in the affected areas after the cut-off date will not be eligible for compensation. They, however, will be given sufficient advance notice, requested to vacate premises and dismantle affected structures prior to project implementation. Their dismantled structures materials will not be confiscated and they will not pay any fine or suffer any sanction.

7.2 Entitlements

94. The entitlement provisions various categories of DPs in terms loss of land house and income as per census survey are detailed below:

95. Agricultural land impacts will be compensated at replacement cost. Cash compensation at replacement cost will be determined according to BLARRP-2007 or replacement of land if available. If the residual plot(s) is (are) not viable, i.e., the AP becomes a marginal farmer, three options are to be given to the AP, subject to his acceptance which are (i) The AP remains on the plot, and the compensation and assistance paid to the tune of required amount of land to be acquired, (ii) Compensation and assistance are to be provided for the entire plot including residual part, if the owner of such land wishes that his residual plot should also be acquired by the EA, the EA will acquire the residual plot and pay the compensation for it and (iii) If the AP is from vulnerable group, compensation for the entire land by means of land for land will be provided if AP wishes so, provided that land of equal productive value is available. All fees, stamp duties, taxes and other charges, as applicable under the relevant laws, incurred in the relocation and rehabilitation process, are to be borne by the EA.

96. Loss of homestead /Commercial land will be compensated at replacement cost. Cash compensation at replacement cost will be determined according to BLARRP-2007 or replacement of land if available. All fees, stamp duties, taxes and other charges, as applicable under the relevant laws, incurred in the relocation and rehabilitation process, are to be borne by the EA.

45

97. Loss of Structures Residential/Commercial/Other will be compensated at replacement value with other assistance. The details on the determination of compensation will be as (i) Compensation of structure will be paid at the replacement cost to be calculated as per latest prevailing basic schedules of rates (BSR) without depreciation, (ii) Shifting assistance of Rs. 10,000/-, (iii) Right to salvage material from demolished structure and frontage etc, and (iv) Rental assistance as per the prevalent rate in the form of grant to cover maximum three month rentals.

98. Loss of rental accommodation by the tenants will be compensated as rental assistance and shifting assistance. The details assistance will be as per (i) Rental assistance for both residential & commercial tenants as per the prevalent rate in the form of grant to cover maximum three month rentals, (ii) Additional structures erected by tenants will also be compensated and deducted from owner’s compensation amount, (iii) Shifting assistance based on type of house and household assets, (iv) Any advance deposited by the tenants will be refunded from owners total compensation package to the tenant on submission of documentary evidences and (v) Right to salvage material from demolished structure and frontage etc. erected by tenants

99. Loss of structure by non-title holder will be also compensated as per applicable guidelines. The squatters will be compensated for structure and also get shifting assistance, whereas, the vulnerable encroachers only, who are having structure within the proposed ROW will get compensation for affected properties. The detail assistance will be as per (i) compensation for both residential & commercial squatter as per the prevalent rate in the form of grant to cover maximum three month rentals, (ii) Shifting assistance will be Rs. 10000/-, (iii) Right to salvage material from demolished structure and frontage etc. erected by squatters

100. Loss of Trees will be compensated to Land holders, Share- croppers and Lease holders based on the market value to be computed with assistance of horticulture department. This can further be detailed in specific ways such as (i) Advance notice to DPs to harvest fruits and remove trees, (ii) b) For fruit bearing trees compensation at average fruit production for next 15 years to be computed at current market value and (iii) For timber trees compensation at market cost based on kind of trees

101. Loss of Crops will be compensated to Land holders, Share- croppers and Lease holders based on the market value to be computed with assistance of agricultural department. The detailed compensation methods are (i) Advance notice to DPs to harvest crops and (ii) In case of standing crops, cash compensation at current market cost to be calculated of mature crops based on average production.

102. Loss of Livelihood due to Loss of primary source of income will be compensated through rehabilitation assistances. There are various categories of entitled persons under this category which are (i) Titleholders losing income through business, (ii) Titleholders losing income through agriculture, (iii) Non-titleholders namely squatters and vulnerable encroachers losing primary source of income, (iv) Wage earning employees indirectly affected due to displacement of commercial structure, (v) Agricultural laborer/share-cropper and (vi) Licensed mobile vendors and kiosk operators. Details of entitlements for the above categories are described below:

 Title holders losing their business establishment due to displacement will be provided rehabilitation assistance through a lump sum transitional allowance of Rs. 9,000/-

46

 Titleholders losing income through agriculture will be provided with the rehabilitation assistance which are (i) Training Assistance will be provided for income generating vocational training and skill up gradation options as per DPs choice at the rate of Rs. 4,000 per affected household to those households losing their primary source of income and (ii) Employment opportunity for DPs in the road construction work, if available and if so desired by them.

 Non-titleholders namely squatters and vulnerable encroachers losing primary source of income will be provided with rehabilitation assistances through (i) Training would be provided for up-gradation of skills @ Rs. 4,000/ - per family to the DPs, (ii) Employment opportunity for DPs in the road construction work, if available and ,if so desired by them, Or (iii) National/State level job card under National Rural Employment Guarantee Program.

 Wage earning employees indirectly affected due to displacement of commercial structure will be assisted through rehabilitation assistance which are; (i) persons indirectly affected due to the employer having being displaced, on case-by-case, based on local wage rates for three months, (ii) Employment opportunity for DPs in the road construction work, if available and if so desired by them, Or (iii) National/State level job card under National Rural Employment Guarantee Program.

 Rehabilitation assistance for Agricultural laborer/share-cropper will be paid as per the details such as (i) Assistance is to be paid as per the prevailing local wage rates for 200 days., (ii) b) Employment opportunity for DPs in the road construction work, if available and if so desired by them, Or (iii) National/State level job card under National Rural Employment Guarantee Program.

 Licensed mobile vendors and kiosk operators will be provided with the rehabilitation assistance which are (i) Mobile venders are not eligible for compensation or assistance (ii) Those mobile vendors in possession of a permit from local authorities to operate in the affected area will be treated as kiosks operators, (iii) Kiosk operators and vendors licensed to operate from affected locations will be entitled to a one time lump sum assistance of Rs. 4,000/-.

103. Loss of community infrastructure/common property resources will be compensated either by cash compensation at replacement cost or reconstruction of the community structure in consultation with the affected community

104. Additional Assistance to vulnerable groups (Vulnerable households including BPL, SC, ST, WHH, disabled and elderly) will be paid with Special Assistance which will be one time lump sum assistance of Rs. 10,000/ to vulnerable households. This will be paid above and over the other assistance(s) as per this framework.

105. Other Unanticipated Impacts (Temporary impact during construction like disruption of normal traffic, damage to adjacent parcel of land / assets due to movement of heavy machinery and plant site) will be compensated to either individual or community in the form of (i) The contractor shall bear the cost of any impact on structure or land due to movement of machinery during construction or establishment of construction plant and (ii) All temporary use of lands

47 outside proposed RoW to be through written approval of the landowner and contractor. Location of Construction camps by contractors in consultation with RCD.

106. Any unanticipated impacts (if any) due to the project will be documented and mitigated based on the spirit of the principle agreed upon in this framework.

7.3 Entitlement Matrix

107. Compensation for the lost assets to all displaced persons will be paid on the basis of replacement cost. Resettlement assistance for lost income and livelihoods will be provided to both title holders and non-title holders. Special resettlement and rehabilitation measures will be made available to the “Vulnerable Group” comprises of DPs living below poverty line (BPL), SC, ST, women headed households, the elderly and the disabled. An Entitlement Matrix (Table 7.1) has been formulated, which recognizes and lists various types of losses resulting out of the project and specific compensation and resettlement packages.

Table 7.1: Entitlement Matrix

S. Unit of Type of Loss Entitlement Details N. Entitlement A. LOSS OF LAND 1 Loss of a) Titleholder c) Compensatio a) Cash compensation at replacement cost as Agricultural b) DPs with n at determined according to BLARRP-2007 or land customary land replacement replacement of land if available. right cost b) If the residual plot(s) is (are) not viable, i.e., the d) Special DP becomes a marginal farmer,3 any of the provision for following three options are to be given to the vulnerable DP, subject to his acceptance: group  The DP remains on the plot, and the compensation and assistance paid to the tune of required amount of land to be acquired.  Compensation and assistance are to be provided for the entire plot including residual part, if the owner of such land wishes that his residual plot should also be acquired by the EA, the EA will acquire the residual plot and pay the compensation for it.  If DP is from vulnerable group, compensation for the entire land by means of land for land will be provided if DP wishes so, provided that land of equal productive value is available. c) All fees, stamp duties, taxes and other charges, as applicable under the relevant laws, incurred in the relocation and rehabilitation process, are to be borne by the EA. 2 Loss of a) Titleholder a) Compensatio a) Cash compensation at replacement cost as homestead b) DPs with n at determined according to BLARRP-2007 or /commercial customary land replacement replacement of land if available. land rights cost b) All fees, stamp duties, taxes and other charges, as applicable under the relevant laws, incurred in the relocation and rehabilitation process, are to be borne by the EA. B. LOSS OF STRUCTURE (RESIDENTIAL/COMMERCIAL/OTHER)

3 Marginal farmers are those who own less land than the district minimum land holding.

48

S. Unit of Type of Loss Entitlement Details N. Entitlement 3 Loss of a) Titleholder a) a) Compensation of structure will be paid at the residential / b) DPs having Compensation replacement cost to be calculated as per latest commercial structure with at replacement prevailing basic schedules of rates (BSR) structures customary land cost without depreciation. right b) Shifting b) Shifting assistance of Rs. 10000/-4. assistance c) Right to salvage material from demolished structure and frontage etc. d) Rental assistance as per the prevalent rate in the form of grant to cover maximum three month rentals. 4 Loss of rental Tenants a) Rental a) Rental assistance for both residential & accommodati Assistance commercial tenants as per the prevalent rate on b) in the form of grant to cover maximum three Compensation month rentals. at replacement b) Additional structures erected by tenants will cost also be compensated and deducted from c) Shifting owner’s compensation amount. assistance c) Shifting assistance based on type of house and household assets. d) Any advance deposited by the tenants will be refunded from owners total compensation package to the tenant on submission of documentary evidences. e) Right to salvage material from demolished structure and frontage etc. erected by tenants. C. LOSS OF STRUCTURE BY NON-TITLED HOLDER 5 Loss of Squatters5 having a) No a) Squatters will be notified and given one month structure structure compensation time to remove their assets. (immovable for land b) Compensation for loss of structure at assets b) replacement cost. constructed Compensation c) Shifting assistance of Rs. 100006/-. by squatters for structures. d) Right to salvage material from the demolished and c) Shifting structure. encroachers) Assistance Encroachers7 a) No a) Encroachers will be notified and given one having structure compensation month time to remove their assets and harvest for land their crops. b) b) Compensation for structures at replacement Compensation cost to the vulnerable households only. for structures c) Right to salvage materials from the demolished to only structure. vulnerable household D. LOSS OF TREES AND CROPS 6 Loss of Trees a) Land holders Compensation a) Advance notice to DPs to harvest fruits and b) Share- at Market value remove trees croppers to be computed b) For fruit bearing trees compensation at average c) Lease holders with assistance fruit production of horticulture for next 15 years to be computed at current department market value c) For timber trees compensation at market cost based on kind of trees

4 As required by NRRP 2007. 5 Landless person 6 As required by NRRP 2007. 7 Legitimate land holder but encroaching his movable or immovable assets on Government land

49

S. Unit of Type of Loss Entitlement Details N. Entitlement 7 Loss of Crops a) Land holders Compensation a) Advance notice to DPs to harvest crops b) Share- at Market value b) In case of standing crops, cash compensation croppers to be computed at current market cost to be calculated of c) Lease holders with assistance mature crops based on average production. of agriculture department E. LOSS OF MARKET PLACE STRUCTURE BY TITLED HOLDER AND NON-TITLED HOLDER 8 Impact on Titleholder8 Relocation a) Affected enterprises will be provided with the market place/ (Owner) losing Assistance following options: area on a commercial Self managed reconstruction of shops by the minimum of enterprise in the shop operators 25 market area with all benefits as per the entitlement matrix; or shops/ b) Project assisted relocation option will be businesses provided to those whose commercial structure can no longer be used as a commercial enterprise as a result of the Project impact. The allotment of the shops in the market complex will be based on the ownership status of those affected. c) Shifting assistance of Rs. 10000/-9. d) Right to salvage material from demolished structure at no cost. Non-titleholder10 Relocation a) Affected enterprises will be provided with the (tenants, Assistance following options: Self managed reconstruction leaseholders or of shops by the shop operators with all benefits squatters) losing as per the entitlement matrix; or commercial b) Project assisted relocation option will be enterprise in the provided to those whose commercial structure market area can no longer be used as a commercial enterprise as a result of the Project impact. The allotment of the shops in the market complex will be based on the ownership status of those affected. c) Shifting assistance of Rs. 1000011/-. d) Right to salvage material from demolished structure at no cost. F. LOSS OF LIVELIHOOD 9 Titleholders Rehabilitation b) Title holders loosing their business Loss of losing income Assistance establishment due to displacement will be primary through business provided with a lump sum transitional source of allowance of Rs. 900012.

8 In case of affected Title owners who have been carrying out business for 10 or more years – the affected title owners will be allotted a shop in the market in lieu of compensation. No additional compensation will be paid to them. However, they will be entitled to transitional assistance and shifting assistance as applicable and provided for in the Entitlement Matrix. 9 As required by NRRP 2007. 10 In case of affected non-title owners, tenants and leaseholders, squatters and vulnerable encroachers, who have been carrying out business for 10 or more years, will be re-established by creation of market place. The constructed shops in this market will be provided on rent to them. For first 3 months, no rent will be charged from these DPs. However, after three months these DPs need to pay to the authority the agreed rent by demand draft monthly and if he/she wishes to own the same can pay the total amount in agreed installments. The DPs opting for this option will not be paid cash compensation for their structure loss. 11 As required by NRRP 2007 12 This rate has been fixed based on the estimates of average income for a period of three months.

50

S. Unit of Type of Loss Entitlement Details N. Entitlement income Titleholders Rehabilitation c) Training Assistance will be provided for income losing income Assistance generating vocational training and skill through upgradation options as per DPs choice at the agriculture rate of Rs. 4000 per affected household to those households loosing their primary source of income. d) Employment opportunity for DPs in the road construction work, if available and if so desired by them. Non-titleholders Rehabilitation d) Training would be provided for upgradation of namely squatters Assistance skills @ Rs. 4000/ - per family to the DPs. and vulnerable e) Employment opportunity for DPs in the road encroachers construction work, if available and if s0 desired losing primary by them, Or source of income f) National/State level job card under National Rural Employment Guarantee Program. Wage earning Rehabilitation d) This is valid for persons indirectly affected due employees Assistance to the employer having being displaced, on indirectly case-by-case, based on local wage rates for affected due to three months. displacement of e) Employment opportunity for DPs in the road commercial construction work, if available and if so desired structure by them, Or f) National/State level job card under National Rural Employment Guarantee Program. Agricultural Rehabilitation a) Assistance is to be paid as per the prevailing laborer/share- Assistance local wage rates cropper for 200 days. b) Employment opportunity for DPs in the road construction work, if available and if so desired by them, Or d) National/State level job card under National Rural Employment Guarantee Program. Licensed mobile Rehabilitation d) Mobile venders are not eligible for vendors and Assistance compensation or assistance. kiosk operators e) Those mobile vendors in possession of a permit from local authorities to operate in the affected area will be treated as kiosks operators. f) Kiosk operators and vendors licensed to operate from affected locations will be entitled to a one time lump sum assistance of Rs. 4000/-. G. LOSS OF COMMUNITY INFRASTRUCTURE/COMMON PROPERTY RESOURCES

10 Loss of Community Reconstruction a) Cash compensation at replacement cost or Common / Cash reconstruction of the community structure in Property Compensation consultation with the affected community. Resources at replacement cost

51

S. Unit of Type of Loss Entitlement Details N. Entitlement H. ADDITIONAL SUPPORT TO VULNERABLE GROUP

11 Additional Vulnerable Special a) One time lump sum assistance of Rs. 10000/ to Assistance to households Assistance vulnerable households. (This will be paid above vulnerable including BPL, and over the other assistance(s) as per this groups SC, ST, WHH, framework). disabled and elderly I. OTHER UNANTICIPATED IMPACTS

12 Temporary Community / Compensation d) The contractor shall bear the cost of any impact impact during Individual on structure or land due to movement of construction machinery during construction or establishment like disruption of construction plant of normal e) All temporary use of lands outside proposed traffic, RoW to be through written approval of the damage to landowner and contractor. adjacent f) Location of Construction camps by contractors parcel of land in consultation with RCD. / assets due to movement of heavy machinery and plant site 13 Unforeseen Any unanticipated impacts due to the project will be documented and mitigated based on impacts if any the spirit of the principle agreed upon in this framework.

52

CHAPTER 8 RELOCATION OF HOUSING AND SETTLEMENTS

8.1 Basic Provision for Relocation

108. The EA will provide adequate and appropriate replacement land and structures or cash compensation at full replacement cost for lost land and structures, adequate compensation for partially damaged structures, and relocation assistance, according to the Entitlement Matrix. The EA will compensate to the non-title holders for the loss of assets other than land, such as dwellings, and also for other improvements to the land, at full replacement cost. The entitlements to the non-titleholders will be given only if they occupied the land or structures in the project area prior to the cut-off date.

109. Preference will be given to land-based resettlement strategies for displaced persons whose livelihoods are land-based. These strategies may include resettlement on public land, or on private land acquired or purchased for resettlement. Whenever replacement land is offered, displaced persons are provided with land for which a combination of productive potential, locational advantages, and other factors is at least equivalent to the advantages of the land taken. If land is not the preferred option of the displaced persons, or sufficient land is not available at a reasonable price, non-land-based options built around opportunities for employment or self-employment should be provided in addition to cash compensation for land and other assets lost. The non-availability of land will be demonstrated and documented during the implementation of this RP to the satisfaction of ADB.

110. In the case of physically displaced persons, the EA will provide (i) relocation assistance, secured tenure to relocation land, better housing at resettlement sites with comparable access to employment and production opportunities, and civic infrastructure and community services as required; (ii) transitional support and development assistance, such as land development, credit facilities, training, or employment opportunities; and (iii) opportunities to derive appropriate development benefits from the project.

8.2 Need for Relocation

111. Despite being a linear project, the quantum of land acquisition is high in the subproject because of construction of four bypasses and widening proposal. The efforts were made to minimize the resettlement; however, despite the mitigation measures 672 families all from encroachers or squatters categories, are losing their structures of different use. In addition to this, 1235 households are losing their land in the subproject. However, all efforts were made through various provisions in this RP to mitigate negative social impacts and compensate for loss of displaced persons and communities by supporting relocation of affected households as per entitlement framework so that they could restore their pre-project levels of income.

8.3 Magnitude of Physical Displacement in the Subproject

112. Among affected villages in the subproject, 672 households of encroachers and squatters categories are losing various types of structures, i.e., 517 residential, 78 commercial and 77 residential cum commercial type etc. Out of 672 households, 414 encroachers are entitled due to their vulnerability status and 14 squatters are entitled for various rehabilitation assistances as per relocation measures. The eligible encroachers and squatters will be entitled for loss of their structures only and will not get any compensation for land. During the census survey encroachers and squatters were asked whether they have additional land to shift and in most of

53 the cases their response was affirmative and they only want the compensation and assistance as per entitlement. The survey data reveals that 659 (98.07%) out of 672 households have additional land to shift (refer Table 8.1).

Table 8.1: Availability of Additional Land

Sl. No. Additional Land No. of Households % 1 Available 659 98.07 2 Not Available 13 1.93 Total 672 100.00 Source: Census Survey, Bihar State Highways II Project, 2010

8.4 Relocation and Compensation Option by DPs

113. To understand and know the relocation options, DPs were consulted during the census survey and out of 672 households losing structures, 659 (98.07%) households have opted for self relocation as they have additional land to shift. Details of relocation and compensation option are given in Table 8.2.

Table 8.2: Relocation Option by DPs

Sl. No. Relocation Options No. of Households Self Relocation and cash 1 Compensation 659 2 Relocation by the Project 13 Total 672 Source: Census Survey, Bihar State Highways II Project, 2010

8.5 Relocation Strategy

114. With the scattered nature of resettlement impacts i.e. 672 over 84 kilometers and two districts and all are non-titleholders, it will be difficult and not feasible to provide resettlement colony with all amenities. During the focused group discussion, while discussing about relocation options people were very much in favor of resettlement within the village to avoid disruption of community life and problem with host community. Therefore cash compensation at market rate as more practical solution in this case is suggested for loss of structures.

115. All the structures affected in the subproject as per provisions made in the entitlement matrix will be entitled for the following:

(i) Compensation of structure will be paid at the replacement cost to be calculated as per latest prevailing basic schedules of rates (BSR) without depreciation, (ii) Shifting assistance to all structures at of Rs. 10,000 per structure, (iii) Right to salvage material from demolished structure and frontage etc, (iv) Rental assistance as per the prevalent rate in the form of grant to cover maximum three month rentals.

116. To help the DPs losing structures in getting all above entitlements and relocating themselves, following relocation strategy will be adopted in the subproject: a) All compensation will be paid and other resettlement entitlements will be provided before physical displacement.

54

b) At least one month advance notice before demolition of structure. c) Their dismantled structures materials will not be confiscated and they will not pay any fine or suffer any sanction. d) The NGO engaged for RP implementation will assist DPs during verification of assets and will provide necessary counseling on payment of compensation and assistance. e) The NGO will assist the project authorities in ensuring a smooth transition (during the part or full relocation of the DPs), helping the DPs to take salvaged materials and shift. f) In close consultation with the DPs, the NGO will fix the shifting dates agreed with the DPs in writing and the arrangements desired by the DPs with respect to their entitlements. g) In case of self relocation also, the NGO will assist the DPs in finding alternative land within the village if so desired by the DPs.

55

CHAPTER 9 INCOME RESTORATION AND REHABILITATION

9.1 Loss of Livelihoods in the Subproject

117. Due to loss of land and structures, many households shall lose their livelihoods or shall get economically displaced. While accounting the number of households losing their livelihoods, owners of agricultural land and associated agricultural laborer and share cropper are considered. Similarly in case of structures, households associated with commercial activities and employed people thereof are enumerated. However, the residential structures (517) and barren lands (14) do not yield any source of livelihood, these are excluded. A total number of 1377 households shall be losing their livelihoods. This comprises of 913 (66.3%) agricultural land owners, 59 (4.28%) agricultural laborer, 97 (7.04%) share croppers in the agriculture and related activities. In case of commercial structures including squatters 59 (4.28%) households will lose their livelihood. In addition, the residential-cum-commercial structures account 43 (3.12%) households. Besides 186 (13.51%) tenant/leaseholder and 20 (1.45%) employees will lose their livelihood. The details of impact on livelihoods in the subproject are presented in the Table 9.1.

Table 9.1: Loss of Livelihood

Sl. No. of No. of %age of % of Loss No. Household DPs Households DPs Owners of agricultural land losing more 1 than 10% 913 4,839 66.30 36.81

Agricultural Laborer 2 59 236 4.28 1.80

Sharecropper 3 97 437 7.04 3.32

Owners of Commercial Structure (47 4 59 177 4.28 1.35 vulnerable encroachers+12 Squatters) Owners of Residential cum Commercial 5 Structure (41 Vulnerable Encroachers + 43 202 3.12 1.54 2 Squatters ) Commercial tenant +Residential-cum- 6 186 911 13.51 6.93 commercial tenant Employee in commercial and residential- 7 20 80 1.45 0.61 cum-commercial structure (20) Total 1,377 6,882 100 52.35 Total-N 2,269 13,147 100.00 Source: Census Survey, Bihar State Highways II Project, 2010

9.2 Provisions for Loss of Livelihood

118. The DPs losing their livelihoods includes titleholders land, agricultural laborers, agricultural tenants, and sharecroppers, DPs having commercial structures and employees of the affected structures. In the case of economically displaced persons, regardless of whether or not they are physically displaced, the EA will promptly compensate for the loss of income or livelihood sources at full replacement cost. The EA will also provide assistance such as credit facilities, training, and employment opportunities so that they can improve, or at least restore,

56 their income-earning capacity, production levels, and standards of living to pre-displacement levels.

119. In cases where land acquisition affects commercial structures, affected business owners are entitled to (i) the costs of re-establishing commercial activities elsewhere; (ii) the net income lost during the transition period; and (iii) the costs of transferring and reinstalling plant, machinery, or other equipment. Business owners with legal rights or recognized or recognizable claims to land where they carry out commercial activities are entitled to replacement property of equal or greater value or cash compensation at full replacement cost. The EA will ensure that no physical displacement or economic displacement will occur until (i) compensation at full replacement cost has been paid to each displaced person for project components or sections that are ready to be constructed; (ii) other entitlements listed in the resettlement plan have been provided to displaced persons; and (iii) a comprehensive income and livelihood rehabilitation program, supported by an adequate budget, is in place to help displaced persons improve, or at least restore, their incomes and livelihoods.

9.3 Income Restoration Measures

120. The entitlement proposed for the subproject has adequate provisions for restoration of livelihood of the affected communities. The focus of restoration of livelihoods is to ensure that the DPs are able to at least regain their previous living standards. To restore and enhance the economic conditions of the DPs, certain income generation and income restoration programs are incorporated in the RP. To begin with providing employment to the local people during the construction phase will enable them to benefit from the project, reduce the size of intrusive work forces and keep more of the resources spent on the project in the local economy. It will also give the local communities a greater stake and sense of ownership in the project.

121. Among specific rehabilitation measures, capacity building of all the economically displaced persons will be carried out by the project authority. The NGO to be engaged for implementation of RP will carry out assessment and prepare micro plan for rehabilitation of DPs. The NGO will make the training need assessment and will impart training to the eligible DPs for income restoration and skill up-gradation as necessary. The EA will also provide opportunities to displaced persons to derive appropriate development benefits from the project. The vulnerable DPs will be given preference in availing employment opportunities in subproject construction work. The women headed households also will be taken care of in a case to case basis and the NGO will help them in forming Self help Groups (SHGs), establish linkages to available credit facilities, special trainings, and linking them with ongoing govt. schemes. Budget for training in terms of assistance is provided to DPs losing livelihoods and the NGO will either organize training programs or link the DPs to various ongoing training schemes. Fund for training is provided in the R&R budget keeping in view the average expenditure for ongoing training programs in the project area. Following training programs will be considered based on further training need assessment to be carried out by the NGO.

57

 Food processing such as making pickle, making sweets, making tomato sauce, etc.  Manufacturing of detergent items like soap, and shampoo  Manufacturing cosmetic items like talk and perfumes  Manufacturing candle  Manufacturing incense sticks  Cycle repairing  Auto workshop  Electric fitting and repairing  Mushroom plantation  Animal husbandry, poultry, and piggery  Clothes sewing and weaving

9.4 Additional Support from Ongoing Poverty Reduction Programs

122. In addition to project-sponsored programs, the implementing NGO will play a proactive role to mobilize DPs to get benefits from various government schemes and ensure their accessibility particularly of vulnerable groups. In India, panchayat government systems at the village, block and district/zilla levels are now responsible for planning and implementation of all anti-poverty programs funded by the central and state governments. The implementing NGO will work with the panchayat governments to make available to the DPs benefits of some of the ongoing pro-poor programs for poverty reduction.

58

CHAPTER 10: RESETTLEMENT BUDGET AND FINANCING PLAN

10.1 General

123. The resettlement cost estimate for this subproject includes eligible compensation, resettlement assistance and support cost for RP implementation. The support cost, which includes staffing requirement, monitoring and reporting, involvement of NGO in project implementation and other administrative expenses are part of the overall project cost. The unit cost for land and other assets in this budget has been derived through field survey, consultation with affected families, relevant local authorities and reference from old practices. Contingency provisions have also been made to take into account variations from this estimate. Some of the major items of this R&R cost estimate are outlined below:

 Compensation for agricultural, residential and commercial land at their replacement value  compensation for structures (residential/ commercial) and other immovable assets at their replacement cost  Compensation for crops and trees  Assistance in lieu of the loss of business/ wage income/ employment and livelihood  Assistance for shifting of the structures  Resettlement and Rehabilitation Assistance in the form of Training allowance  Special assistance to vulnerable groups for their livelihood restoration  Cost for implementation of RP.

10.2 Compensation

124. Private Agricultural Land: The unit rate for agricultural land has been estimated as per Bihar Land Acquisition and Resettlement Policy-2007. To meet the replacement cost of land compensation will be calculated over updated land rate with 50% additional as registration cost plus 60% solatium.

125. Residential/ Commercial and other structures: The compensation cost of structures are arrived at by assessment of market value, consultation with DPs and data collected from building contractors and property agents this meets the replacement cost of the structures. The average rate for permanent structures without land has been calculated at Rs. 3,500/m2, semi- permanent structures have been calculated at Rs. 2,500/m2, and temporary structures have been calculated at the rate of Rs. 1,500/m2.

126. Trees: As per provision made in the entitlement matrix trees will be compensated at market value. Among fruit bearing trees, there are five most common species enumerated in the census surveys, i.e. Mango, Jamun, Ber, and Amrud. For fruit bearing trees, compensation is calculated on the basis of annual produce value for the next 15 years and according to the local assessment, the maximum average annual produce value of these trees are Rs. 750. Therefore, the cost of fruit bearing trees for next 15 years is estimated at Rs. 11,250/-. Among non-fruit bearing/timber trees, some common species enumerated in the survey includes Sisam, bamboo, Mahua and pippal. For timber trees, compensation is calculated on the basis of market

59 rate ofRs. 10,000/- for a fully grownup tree.

10.3 Assistance

127. Shifting allowance: Shifting allowance will be provided to all the affected households losing structures and tenants. The unit cost has been derived on a lump sum basis of Rs. 10000/- as required by NPRR 2007.

128. Rental Assistance: Rental assistance to titleholder (structures) and tenants in structures will be provided in the form of grants to cover maximum three months rentals @ Rs. 1000/- per month.

129. Rehabilitation Assistance to DPs Losing Business Establishment: Title holders losing their business establishment due to displacement will be provided with a lump sum transitional allowance of Rs. 9,000. This rate has been fixed based on the estimates of average income for a period of three months.

130. Training Assistance to Agricultural Titleholders: Training Assistance will be provided for income generating vocational training and skill up-gradation options as per DPs choice at the rate of Rs. 4000/- per affected household to those households losing their primary source of income.

131. Rehabilitation Assistance to Employees in Structure: Wage earning employees indirectly affected due to displacement of commercial structure will be provided assistance as per the prevailing local wage rate for 3 months i.e. @ Rs. 100/- for 90 days.

132. Rehabilitation Assistance to Agricultural Laborers/Sharecroppers: Agricultural Laborers/ Sharecroppers will be provided with assistance as per the prevailing local wage rate for 200 days at Rs. 100 per day.

133. Assistance to Vulnerable Households: One time lump sum assistance of Rs. 10,000 will be paid to each vulnerable households. (This will be paid above and over the other assistance(s) as per the entitlement matrix).

10.4 Compensation for Community and Government Property

134. Government Land: The cost estimate for government land to be acquired for the subproject are made @ Rs 1,000,000.00/acre, however, it is expected that these land will to transferred from other departments to the EA.

135. Religious and community land: The unit cost for religious and community structures is calculated on a lump sum basis at Rs. 1,000,000 per acre which is derived from the feedbacks from the local people during the resettlement survey.

136. Religious and community Structures: The religious and community structures are being partially affected and do not require full replacement. However a lump sum provision of Rs. 100000/- per structure is made in the budget to rebuild are enhance the ambience of these structures.

60

10.5 RP Implementation and Support Cost

137. The unit cost for hiring of the implementing NGO has been calculated on a lump sum basis for Rs. 3,000,000. This is based on the similar earlier project experiences and informal consultation and feedback received from the local staff and keeping in consideration one year duration of NGO’s involvement. Costs will be updated during implementation. A 10% contingency has been added in order to adjust any escalation. For grievance redress process a lump sum of Rs. 200000/- is provided and cost of other RP implementation and administrative activities will be a part of existing departmental expenditure. The separate fund for grievance redressal for this project is made based on intensity of impacts. In addition the process will involve interdepartmental arrangement and include participation by representatives of APs, particularly of vulnerable DPs, local government representatives, representative of local NGOs and other interest groups besides PIU and implementing NGO.

10.6 Source of Funding and Fund Flow Management

138. The cost related to land acquisition and resettlement cost will be borne by the EA. The EA will ensure allocation of funds and availability of resources for smooth implementation of the subproject R&R activities. The EA will, in advance, initiate the process and will try to keep the approval for the R&R budget in the fiscal budget through the ministry of finance. In the case of assistance and other rehabilitation measures, the EA will directly pay the money or any other assistance as stated in the RP to DPs. The implementing NGO will be involved in facilitating the disbursement process and rehabilitation program.

10.7 R&R Budget

139. The total R&R budget for the proposed subproject RP works out to Rs. 348.5 million. A detailed indicative R&R cost is given in Table 10.1.

Table 10.1: R&R Budget

Sl. No. Item Unit Rate Amount A Compensation for Land in Acre in Rupees 1 Compensation for Private Land 257.78 As per BLLARP 161,857,626.3 Rs. 1,000,000 Compensation for Government Land 11.59 per acre 11,590,000 Rs. 1,000,000 2 Compensation for Religious Land 0.25 per acre 250,000 Subtotal A 173,697,626 B Compensation for Private Structure in Sq. mtr. Rupees 1 Compensation for Permanent Structure 15398.3 3,500 53,894,050 Compensation for Semi-Permanent 2 Structure 23536.85 2,500 58,842,125 3 Compensation for Temporary Structure 745.5 1,500 1,118,250 4 Compensation/ Relcoation of CPRs 52 in number 100,000 5,200,000 Subtotal B 119,054,425 C Compensation for Private Trees Number Rupees 1 Compensation for Fruit Bearing Trees 243 11,250 2,733,750

61

Sl. No. Item Unit Rate Amount Compensation for Non-Fruit Bearing 2 Trees 126 10,000 1,260,000 Subtotal C 3,993,750 D Assistance Number 1 Shifting Assistance to Squatter 14 Rs. 10,000 140,000 Rental Assistance to Tenants in 3 months X Rs. 2 Structures 186 1000 558,000 Shifting Assistance to Tenants in 3 Structures 186 Rs. 10,000 1,860,000 Rehabilitation Assistance to DPs Losing Lump sum Rs. 4 Business Establishment 102 9,000 918,000 Training Assistance to Agricultural 5 Titleholders 913 Rs. 4,000 3,652,000 Rehabilitation Assistance to Employees 90 days X Rs. 6 in Structure 20 100 180,000 Rehabilitation Assistance to Agricultural 200 days X Rs. 7 Laborers/Sharecroppers 156 100 3,120,000 Lump sum Rs. 8 Assistance to Vulnerable Households 513 10,000 5,130,000 Subtotal D 15,558,000 E RP Implementation Support Cost Number Lump sum Rs. 1 Hiring of NGO for RP Implementation 1 3,000,000 3,000,000 2 Grievance Redressal Cost lump sum Rs. 2,00,000 200,000 rs 200,000 per 3 Training for DPs by NGO 7 Blocks Block 1,400,000 Subtotal E 4,600,000 Total (A+B+C+D+E) 316,903,801 Contingency (10%) 31,690,380 GRAND TOTAL 348,594,181

62

CHAPTER 11 GRIEVANCE REDRESS MECHANISMS

11.1 General

140. In the subproject RP implementation there is a need for an efficient grievance redressal mechanism that will assist the DPs in resolving their queries and complaints. Therefore, formation of Grievance Redressal Committee (GRC) will be most important for grievance redressal and it is anticipated that most, if not all grievances, would be settled by the GRC.

11.2 Grievance Redress Mechanism

141. The EA will establish a mechanism to receive and facilitate the resolution of displaced persons’ concerns and grievances about physical and economic displacement and other project impacts, paying particular attention to the impacts on vulnerable groups. The grievance redress mechanism will address affected persons’ concerns and complaints promptly, using an understandable and transparent process that is gender responsive, culturally appropriate, and readily accessible to the displaced persons at no costs and without retribution.

11.3 Constitution and Function of the GRC

142. The GRC will be established at the district level with the primary objective of providing a mechanism to mediate conflict and cut down on lengthy litigation. It will also provide people, who might have objections or concerns about their assistance, a public forum to raise their objections and through conflict resolution, address these issues adequately. The GRCs will continue to function, for the benefit of the DPs, during the entire life of the subproject including the defects liability periods.

143. The GRC will be headed by the District Collector (DC) or his designated representative. The GRC will have representative from the PIU office, representatives of DPs, particularly of vulnerable DPs, local government representatives, representative of local NGOs and other interest groups. The GRC will meet at least once in each 15 days. Other than disputes relating to ownership rights under the court of law, GRC will review grievances involving all resettlement benefits, compensation, relocation, and other assistance. At least one member from each Panchayat will be a woman. The Committee will co-opt a member from each of the affected Panchayat institution when dealing with matters coming from a particular panchayats. Some of the specific functions of the GRC will be as following:

. To provide support for the DPs on problems arising out of land/property acquisition like award of compensation and value of assets; . To record the grievances of the DPs, categorize and prioritize the grievances that needs to be resolved by the Committee and solve them within a month; . To inform PIU/PMU of serious cases within an appropriate time frame; and . To report to the aggrieved parties about the development regarding their grievance and decision of PIU/PMU.

11.4 Operational Mechanisms of GRC

144. It is proposed that GRC will meet regularly (at least twice in a month) on a pre-fixed date. The committee will look into the grievances of the people and will assign the responsibilities to implement the decisions of the committee. The claims will be reviewed and

63 resolved within 15 days from the date of submission to the committee. All Grievance will be routed through the NGO to the GRC. Through public consultations, the DPs will be informed that they have a right to grievance redress. The DPs can call upon the support of the NGO to assist them in presenting their grievances or queries to the GRC .The NGO will act as an in-built grievance redress body. The DPs, who would not be satisfied with the decision of the GRC, will have the right to take the grievance to the PMU Head Office for its redress. Failing the redressal of grievance at PMU, the DPs may take the case to Judiciary. Taking grievances to Judiciary will be avoided as far possible and the NGO will make utmost efforts at reconciliation at the level of GRC.

64

CHAPTER 12: INSTITUTIONAL ARRANGEMENTS

12.1 Institutional Requirement

145. For implementation of RP there will be a set of institutions involved at various levels and stages of the project. For successful implementation of the RP the proposed institutional arrangement with their role and responsibility has been outlined in this section. The primary institutions, which will be involved in this implementation process, are the following:

. Bihar State Road Development Corporation (BSRDC), Government of Bihar . Project Management Unit (PMU) . Project Implementation Unit (PIU) . Non Government Organization (NGO)

12.2 Executing Agency

146. The Executing Agency (EA) for the Project is BSRDC, Government of Bihar. The existing BSRDC has already set up a Project Management Unit (PMU) headed by a Managing Director (MD) with General managers and Deputy General Managers (DGM) assisted by Managers. This office will be functional for the whole Project duration. The EA, headed by MD will have overall responsibility for implementation of loan and will also be responsible for the overall coordination among ADB, Government of Bihar and PIU.

12.3 Project Management Unit (PMU)

147. For resettlement activities, PMU will do the overall coordination, planning, implementation, and financing. The PMU will create a Resettlement Cell (RC) within itself with appointment of a Resettlement Officer (RO) at the rank of Executive Engineer (EE) and required support staff for the duration of the Project to ensure timely and effective planning and implementation of resettlement activities. The candidate to be appointed as RO is desired to have similar earlier experience in resettlement and social development planning and implementation. The RO will be assisted by the respective PIU and staff, NGO, for planning and implementation of resettlement activities in the project. Some of the specific functions of the PMU in regards to resettlement management will include:

. Overall responsibility of implementation and monitoring of R&R activities in the Project; . Ensure availability of budget for R&R activities; . Liaison lined agencies support for land acquisition and implementation of R&R; . Selection and appointment of the NGOs. . Coordinating with line Departments, PIU, implementing NGO and Construction Supervision Consultant (CSC)

12.4 Project Implementation Unit (PIU)

148. Project Implementation Unit (PIU) will be established at subproject level for the implementation of subprojects. The PIU, will appoint/ designate an Assistant Resettlement Officer (ARO) in the rank of Assistant Engineer (AE) who will either be deputed to the PIU or engaged on contractual basis having adequate land acquisition implementation/resettlement

65 experience. The staffs at the PIU level will be provided with the training by the social/ resettlement specialist of the supervision consultant for implementation of the RP. The PIU will maintain all databases, work closely with DPs and other stakeholders and monitor the day today resettlement activities. Some of the specific tasks to be performed by PIU include:

. To coordinate with district administration for land acquisition; . Translation of RP in local language; . Liaison with district administration for dovetailing government’s income generating and developmental programs for the DPs; . Ensure the inclusion of those DPs who may have not been covered during the census survey; . facilitate the opening of accounts in local banks to transfer assistance to DPs, and organize the disbursement of cheque for assistance in the affected area in public; . Monitor physical and financial progress on land acquisition and R&R activities; . Participate in regular meetings in GRC; and . Organize monthly meetings with the NGO to review the progress on R&R.

12.5 Non Government Organization (NGO)

149. Involuntary resettlement is a sensitive issue and strong experience in R&R matters along with community related skills will be required by the PIU in order to build a good rapport with the affected community and facilitate satisfactory R&R of the DPs. To overcome this deficiency, experienced and well-qualified NGO in this field will be engaged to assist the PIUs in the implementation of the RP. The NGO would play the role of a facilitator and will work as a link between the PIU and the affected community. NGO will assist AP in income restoration by preparing micro plan and guiding to access into various ongoing government development schemes and agencies providing financial assistance and loan. Taking into account the significant role of the NGO in RP implementation, it is extremely important to select NGO that are capable, genuine and committed to the tasks assigned in order to ensure the success of the Plan. An outline TOR for NGO is attached as Appendix 2.

150. The roles and responsibilities of various agencies to be involved in resettlement planning process and implementation of resettlement activities are summarized in Table: 12.1.

Table 12.1: Agencies Responsible for Resettlement Implementation

Activity Agency Responsible Establishment of Resettlement Units in PMU and appointment of Resettlement officer (RO) PMU

Organizing resettlement training workshop PMU

Social Assessment and Preparation of land acquisition plan, Resettlement Plan (RP) PMU through Design Consultant

Hiring of (Non Government Organization) NGOs PMU

Public consultation and disclosure of RP PIU/ Design Consultant/NGO

Co-ordination with district administration for land acquisition PIU/ Design Consultant

66

Activity Agency Responsible

Declaration of cut-off date PMU/PIU

Review and obtaining of approval of resettlement plan form ADB PMU

Submission of land acquisition proposals to District Commissioner PIU

Compensation award and payment of compensation District Collector (DC)

Payment of replacement cost and allowance PIU

Taking possession of acquired land and structures PIU from DC

Handing over the acquired land to contractors for construction PIU

Notify the date of commencement of construction to DPs PIU/NGO

Assistance in relocation, particularly for vulnerable groups PIU/ NGO

Internal monitoring of overall RP Implementation PIU/NGO

External Monitoring and Reporting (Supervision Consultant)

151. An organogram for the institutional arrangement is presented below in Figure: 12.1.

Figure: 12.1 Organogram for the Institutional Arrangement

EA/BSRDC

PMU Resettlement Officer

Supervision Consultant PIU Resettlement Specialist Assistant Resettlement Officer

Design Consultant Resettlement NGO

67

12.6 Capacity Building on RP in the EA

152. Close consultations were held with all the concerned departments to have an initial level of capacity assessment and capacity building exercise in the relevant agencies during the preparation of this RP. The BSRDC has already established a PMU with designated officials dealing with the land acquisition and resettlement for other projects. These officers have been working closely with the consultant team for the preparation of RP. The designated officials from BSRDC were also actively participated during the preparation of LA Plan and census survey. Capacity building training was also initiated through a series of consultations and informal orientation sessions in the local administration level especially in the local revenue offices. The concerned district collectors were also informed about the project and the local revenue officials were consulted for collection of relevant land data and land holders’ details. During, the preparation of RP and especially, during the land acquisition and resettlement survey, concerned officials were informed about their role during the implementation of RP particularly during the disbursement of compensation, assistance and relocation etc.

153. To allow an effective execution of all RP related tasks some expansion of the capacity on RP currently available at EA/PMU/PIU may be needed. As soon as the project will become effective BSRDC will carry out a capacity need assessment and will define the capacity building activities and if needed the additional experts required. All concerned staff both at PMU, PIU level involved in land acquisition and resettlement activities will undergo an orientation and training in ADB resettlement policy and management. The ADB’s PPTA consultant’s resettlement specialist will organize a training workshop and provide training to the PMU/PIU staff. Broadly, the training will cover various topics such as (i) Principles and procedures of land acquisition; (ii) Public consultation and participation; (iii) Entitlements and compensation & assistance disbursement mechanisms; Grievance redress; and (iv) Monitoring of resettlement operations. These will be covered through a formal workshop by the consultant under the ongoing technical assistance program. In addition the R&R expert under Construction Supervision Consultant can also impart training to the PMU/PIU staff during the project implementation if required. The specific components under the training will cover the following:

. Understanding of the ADB Policy Guidelines and requirements and differences between country policy and laws . Understanding of the policy and procedure adopted for the Project . Understanding of the Implementation Schedule activities step-by-step . Understanding of the Monitoring and reporting mechanism . Understanding of the economic rehabilitation schemes

68

CHAPTER 13: IMPLEMENTATION SCHEDULE

13.1 Introduction

154. Implementation of RP mainly consists of compensation to be paid for affected structures and rehabilitation and resettlement activities. The time for implementation of resettlement plan will be scheduled as per the overall project implementation. All activities related to the land acquisition and resettlement must be planned to ensure that compensation is paid prior to displacement and commencement of civil works. Public consultation, internal monitoring and grievance redress will be undertaken intermittently throughout the project duration. However, the schedule is subject to modification depending on the progress of the project activities. The civil works contract for each subproject will only be awarded after all compensation and relocation has been completed for subproject and rehabilitation measures are in place.

13.2 Schedule for Project Implementation

155. The proposed subproject R&R activities are divided in to three broad categories based on the stages of work and process of implementation. The details of activities involved in these three phases i.e. Project Preparation phase, RP Implementation phase, Monitoring and Reporting period are discussed in the following paragraphs.

13.2.1 Project Preparation Phase

156. The major activities to be performed in this period include establishment of PMU and PIU at project and subproject level respectively; submission of RP for ADB approval; appointment of NGO and establishment of GRC etc. The information campaign & community consultation will be a process initiated from this stage and will go on till the end of the project.

13.2.2 RP Implementation Phase

157. After the project preparation phase the next stage is implementation of RP which includes issues like compensation of award by EA; payment of all eligible assistance; relocation of DPs; initiation of economic rehabilitation measures; site preparation for delivering the site to contractors for construction and finally starting civil work.

13.2.3 Monitoring and Reporting Period

158. As mentioned earlier the internal monitoring will be the responsibility of PMU, PIU and implementing NGO and will start early during the project when implementation of RP starts and will continue till the complementation of the subproject. The independent monitoring and reporting will be the responsibility of Construction Supervision Consultant (CSC) to be hired for the subproject.

13.3 R&R Implementation Schedule

159. A composite implementation schedule for R&R activities in the subproject including various sub tasks and time line matching with civil work schedule is prepared and presented in the form of Table: 13.1. As per the project progress the detailed design is ready with Land Acquisition Plan (LAP) and the EA will be initiating the land acquisition process by July 2010.

69

The cut-off date will be notified formally for titleholder as the date of LA notification and for non- titleholders as the date of census survey. However, the sequence may change or delays may occur due to circumstances beyond the control of the Project and accordingly the time can be adjusted for the implementation of the plan. The implementation schedule can also be structured through package wise. The entire stretch can be divided in to various contract packages and the completion of resettlement implementation for each contract package shall be the pre condition to start of the civil work at that particular contract package.

Table: 13.1 R&R Implementation Schedule

Progress (Year/Quarter) Activity 2009 2010 2011 2012 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Project Preparation Stage Screen subproject impact  Public Consultation on alignment  Prepare Land Acquisition Plan  Carry out Census Survey   Prepare Resettlement Plan (RP)  RP Implementation Stage Hiring of NGOs for RP Implementation  Obtaining approval of RP from ADB  Disclosure of RP  Public consultation       Co-ordination with district authority for LA  Submission of LA proposals to DC  Declaration of cut-off date (LA Notification)  Payment of compensation   Taking possession of acquired land  Handing over the acquired land to  contractor Notify the date of start of construction to  DPs Rehabilitation of DPs      Monitoring and Reporting Period Internal monitoring and reporting       Hiring Construction Supervision Consultant   External monitoring and reporting     

70

CHAPTER 14: MONITORING AND REPORTING

14.1 Need for Monitoring and Reporting

160. Monitoring and reporting are critical activities in involuntary resettlement management in order to ameliorate problems faced by the DPs and develop solutions immediately. Monitoring is a periodic assessment of planned activities providing midway inputs. It facilitates change and gives necessary feedback of activities and the directions on which they are going. In other words, monitoring apparatus is crucial mechanism for measuring project performance and fulfillment of the project objectives.

14.2 Monitoring in the Project

161. RP implementation for the subproject will be closely monitored by the EA through NGO and will be at the helm of all activities related to the RP implementation. The monitoring mechanism will have a two-tier system at the EA level i.e. internal monitoring and external monitoring.

14.2.1 Internal Monitoring

162. One of the main roles of PIU will be to see proper and timely implementation of all activities in RP. Internal Monitoring will be a regular activity for PIU and Resettlement Officer at this level will see the timely implementation of R&R activities. Internal Monitoring will be carried out by the PIU and its agents, such as NGOs and will prepare monthly reports on the progress of RP Implementation. PIU will collect information from the project site and assimilate in the form of monthly report to assess the progress and results of RP implementation and adjust work program where necessary, in case of delays or any implementation problems as identified. Monitoring reports will be submitted at regular intervals as specified. This monitoring will form parts of regular activity and reporting on this will be extremely important in order to undertake mid-way corrective steps. The internal monitoring by PMU/PIU will include:

(i) administrative monitoring: daily planning, implementation, feedback and trouble shooting, individual AP database maintenance, and progress reports; (ii) socioeconomic monitoring: case studies, using baseline information for comparing AP socioeconomic conditions, evacuation, demolition, salvaging materials, morbidity and mortality, community relationships, dates for consultations, and number of appeals placed; and (iii) Impact monitoring: Income standards restored/improved, and socioeconomic conditions of the displaced persons. Monitoring reports documenting progress on resettlement implementation and RP completion reports will be provided by the PIU to PMU for review and approval from ADB.

14.2.2 External Monitoring

163. The external monitoring of RP will be undertaken by the R&R expert to be hired under construction supervision consultant (CSC) by EA in agreement with ADB. The main objective of this external monitoring is to supervise overall monitoring of the subproject and submit a biannual report to determine whether resettlement goals have been achieved, more importantly whether livelihoods and living standards have been restored/ enhanced and suggest suitable recommendations for improvement.

71

164. The external monitoring consultant under CSC will be selected within three months of loan approval and the monitoring will be carried out intermittently during the RP implementation. The key tasks during external monitoring will include:

. Review and verify the internal monitoring reports prepared by PIU; . Review of socioeconomic baseline census information of pre-displaced persons; . Identification and selection of impact indicators; . Impact assessment through formal and informal surveys with the displaced persons; . Consultation with DPs, officials, community leaders for preparing review report; . Assess the resettlement efficiency, effectiveness, impact and sustainability, drawing lessons for future resettlement policy formulation and planning.

165. The following should be considered as the basis for indicators in monitoring and reporting of the project:

a) socioeconomic conditions of the DPs in the post-resettlement period; b) communication and reactions from DPs on entitlements, compensation, options, alternative developments and relocation timetables etc.; c) changes in housing and income levels; d) rehabilitation of informal settlers; e) valuation of property; f) grievance procedures; g) disbursement of compensation; and h) level of satisfaction of DPs in the post resettlement period.

14.3 Stages of Monitoring

166. Considering the importance of the various stage of project cycle, the EA will handle the monitoring at each stage as stated below:

14.3.1 Preparatory Stage

167. During the pre-relocation phase of resettlement operation, monitoring is concerned with administrative issues such as, establishment of resettlement unit, budget, land acquisition, consultation with DPs in the preparation of resettlement plan, payments of entitlement due, grievance redressal, and so on. The key issue for monitoring will be:

. Conduct of baseline survey . Consultations . Identification of AP and the numbers . Identification of different categories of DPs and their entitlements . Collection of gender disaggregated data . Inventory & losses survey . Asset inventory . Entitlements . Valuation of different assets . Budgeting

72

. Information dissemination . Institutional arrangements . Implementation schedule review, budgets and line items expenditure

14.3.2 Relocation Stage

168. Monitoring during the relocation phase covers such issues as site selection in consultation with DPs, development of relocation sites, assistance to DPs (especially to vulnerable groups) in physically moving to the new site. Likewise aspects such as adjustment of DPs in the new surroundings, attitude of the host population towards the new comers and development of community life are also considered at this stage. The key issue for monitoring will be:

. Payment of compensation . Delivery of entitlement . Grievance handling . Preparation of resettlement site, including civic amenities (water, sanitation, drainage, paved streets, electricity) . Consultations . Relocation . Payment of compensation . Livelihood restoration assistance and measures

14.3.3 Rehabilitation Stage

169. Once DPs have settled down at the new sites, the focus of monitoring will shift to issues of economic recovery programs including income restoration measures, acceptance of these schemes by DPs, impact of income restoration measures on living standards, and the sustainability of the new livelihood patterns. The key issue for monitoring will be:

. Initiation of income generation activities . Provision of basic civic amenities and essential facilities in the relocated area . Consultations . Assistance to enhance livelihood and quality of life

14.4 Monitoring Indicators

170. The most crucial components/indicators to be monitored are specific contents of the activities and entitlement matrix. The RP contains indicators and benchmarks for achievement of the objectives under the resettlement program. These indicators and benchmarks are of three kinds:

. Process indicators including project inputs, expenditures, staff deployment, etc. . Output indicators indicating results in terms of numbers of affected people compensated and resettled, training held, credit disbursed, etc and . Impact indicators related to the longer-term effect of the project on people's lives.

73

171. Input and output indicators related to physical progress of the work will include items as following:

. training of PIU staff completed . Public meetings held . Census, assets inventories, assessments and socioeconomic studies completed . NGO recruited and trained . Meetings of GRC . Grievance redress procedures in-place and functioning . Compensation payments disbursed . Relocation of DPs completed . Employment provided to DPs . Training of DPs initiated . Income restoration activities initiated . Number of families physically displaced and resettled . Monitoring reports submitted

14.5 Reporting Requirements

172. PIU responsible for supervision and implementation of the RP will prepare monthly progress reports on resettlement activities and submit to PMU. PMU will submit quarterly reports to ADB.

173. The external monitoring expert under CSC responsible for external monitoring of the RP implementation will submit a biannual review report to determine whether resettlement goals have been achieved, more importantly whether livelihoods and living standards have been restored/ enhanced and suggest suitable recommendations for improvement.

174. All the resettlement monitoring reports will be disclosed to DPs as per procedure followed for disclosure of resettlement documents by the EA.

Appendix 1 74

Census Survey Questionnaire

A. Subproject Road Name: ...... B. Questionnaire No: …….…………. C. Name of the Village: ……..…………………… D. Name of Block: …………….…………. E. District: ………………………. F. Thana No: ……………..G. Plot No...... H. Km/Chainage. ………………..…. 1. Ownership of the Land

1. Private 2. Government 3. Religious 4. Community 5. Others 2. Type of Land

1. Irrigated 2. Non-Irrigated 3. Barren 4. Forest 5. Other………….. 3. Use of Land 1.Cultivation 2. Orchard 3. Residential 4. Commercial 5. Forestation 6. No Use/ Barren 7. Other (specify) …………………..…..

4. Affected area of the Land/Plot (in Acre): ……………...... 5. Total Area of the affected Land/Plot (in Acre): ……………...... 6. Total Land Holding of the Affected Person (in Acre) 1. Irrigated: …………………...... 2. Non-irrigated: …………………...... 3. Other: ………………………...…….. 4. Total: ...... 7. Status of Ownership

1. Titleholder 2. Customary Right 3. License from Local Authority 4. Encroacher 5. Squatter 6. Other (specify): …………………………………

8. Type of Private Ownership 1. Individual/Single 2. Joint/Shareholders 3. Other (specify): ………… 9. Name of the Owner/Occupier (s): ………………………...... 10. Father’s Name: ...... 11. Rate of the Land (Per Acre) 1. Market Rate: ...... 2. Revenue Rate: ...... 12. Any of the following people associated with the Land A. Agricultural Laborer 1. Yes 2. No

Name (i)………………………………………… (ii) …………..…………………………….. B. Tenant/Lessee 1. Yes 2. No

Name (i)………………………………………… (ii) …………..…………………………….. C. Sharecropper 1. Yes 2. No Name (i)………………………………………… (ii) …………..……………………………..

13. Any structure in the Affected Land 1. Yes...... 2. No...... 14. Distance of the main structure from center line of the road (in mtr.)……………..……… 15. Distance of boundary wall (if any) from center line of the road (in mtr.)……………….… 16. Area of the affected structure excluding boundary wall (in Square Meter) a) Length ...... …... b) Width ...... …...... c) Height …….……………

Appendix 1 75

17. Area of the boundary wall only (in Meter): a) Length ...... b) Height …….……… 18. Area of the total structure excluding boundary wall (in Square Meter) a) Length ...... …... b) Width ...... …...... c) Height ………………… 19. Scale of Impact on structure a) 25% b) 50% c) 75% d) 100% 20. Type of Construction of the Structure 1. Temporary (buildings with mud/brick/wood made walls, thatched/tin roof) 2. Semi-Permanent (buildings, with tiled roof and normal cement floor) 3. Permanent (with RCC, Single/ Double storey building)

21. Type of Construction of the Boundary Wall (use code from Question: 20) 22. Age of the Structure (in years): …………………………. 23. Market Value of the Structure (in Rs.): …………………...... 24. Use of the Structure (select appropriate code from below) A. Residential Category 1. House 2. Hut 3. Other (specify)…………………………….……….. B. Commercial Category 4. Shops 5. Hotel 6. Small Eatery 7. Kiosk 8. Farm House 9. Petrol Pump 10. Clinic 11. STD Booth 12. Workshop 13. Vendors 14. Com. Complex 15. Industry 16. Other (specify)…………………………….…….. C. Mixed Category 18. Residential-cum-Commercial Structure D. Community Type 19. Comm. Center 20. Club 21. Trust 22. Memorials 23 Other (specify)…………………………….…….. E. Religious Structure 24. Temple 25. Church 26. Mosque 27. Gurudwara 28. Shrines 29. Sacred Grove 30. Other (specify)…………………………….……. F. Government Structure 31. Government Office 32. Hospital 33. School 34. College 35. Bus Stop 36. Other (specify)…………………………….……. G. Other Structure 37. Boundary Wall 38. Foundation 39. Cattle Shed 40. Other (specify)…………………………….……. 25. Type of Business/Profession by Head of Household: ………………………………… 26. Status of the Structure 1. Legal Titleholder 2. Customary Right 3. License from Local Authority 4. Encroacher 5. Squatter 27. Any of the following people associated with the Structure? A. Tenant in the structure 1. Yes 2. No

Name (i) ……………………………………. (ii) …………………..………………….….. (iii) …………………………………… (iv) …………….…………………….……..

B. Employee/ wage earner in commercial structure 1. Yes 2. No Name (i) ……………………………………. (ii) …………………..…………….……….. (iii) …………………………………… (iv) …………….………………….………..

76 Appendix 1

C. Employee/ wage earner in residential structure 1. Yes 2. No Name (i) ……………………………………. (ii) …………………..…………….……….. (iii) …………………………………… (iv) …………….………………………….. 28. Number of trees within the affected area 1. Fruit Bearing………….…2. Non-fruit Bearing…….………3. Total……..………… 29. Social Category of AP

1. SC 2. ST 3. OBC 4. General 5. Others (specify)…………………

30. Religious Category 1. Hindu 2. Muslim 3. Christian 4. Buddhist 5. Jain 6. Other (specify)………

31. Number of family members Male……… Female………. Total…………. 32. Number of family members with following criteria 1. Unmarried Son > 30 years…………2. Unmarried Daughter/Sister > 30 years……….. 3. Divorcee/Widow………….4. Physically/Mentally Challenged Person ………… 5. Minor Orphan……………. 33. Vulnerability Status of the Household: A. Is it a woman headed household? 1. Yes 2. No B. Is it headed by physically/mentally challenged person? 1. Yes 2. No C. Is it a household Below Poverty Line (BPL) 1. Yes 2. No 34. Annual income of the family Rs…………………. 35. If displaced, do you have additional land to shift? 1. Yes 2. No

36. Resettlement/ Relocation Option 1. Self Relocation 2. Project Assisted Relocation 37. Compensation Option for Land loser 1. Land for land loss 2. Cash for Land loss 38. Compensation Options for Structure loser 1. Structure for structure loss 2. Cash for Structure loss 39. Income Restoration Assistance (fill codes in preferred order) 1. Employment Opportunities in Construction work

2. Assistance/ Loan from other ongoing development scheme 3. Vocational Training 4. Others (specify ...... )

Appendix 1 77

40. Details of Family Members: (fill appropriate code) Marital Sl. No Name of the Family Member Age Sex Education Occupation Status (in 1. Male 1. Married 1.Illiterate 1. Service years) 2. Female 2. Unmarried 2.Literate 2. Business

3. Widow 3. Up to middle 3. Agriculture 4.Widower 4. Below metric 4. Study 5. Others 5. Metric 5. Housewife 6. Graduate 6. Labour 7. Above 7. Unemployed 8. Professional 1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

(Signature of the Supervisor) Date: ...... (Signature of the investigator)

Appendix 2 78

Terms of References (TOR) for the NGO to Implement the Resettlement Plan (RP) for SH-81 (Sakaddi - Nasriganj) Subproject under Bihar State Highways-II Project

1. Project Background

1. The Asian Development Bank (ADB) has agreed with national and state government of Bihar to fund the Bihar State Highways Project (BSHP) which will include upgradation and strengthening of various state highways in Bihar. SH-81 (Sakaddi-Nasriganj) subproject is one among several other subprojects under the BSHP.

2. The subproject road SH-81 begins at Sakaddi village and terminates at Nasrigunj. It connects NH-30 (Mohania - Bakhtiyarpur) to SH-15 (Dehri -Vikramgunj). The total length of project road is 83.250 kms and runs parallel to Sone River. The road runs majorly through agricultural fields and many built-up areas. Some of the heavy settled areas include Sakaddi, Chandi, Akhgaon, Sandesh, Naunur, Azimabad, Andhari and Kachwa. It also crosses many canals/drains at various locations.

3. The condition of the existing road is very poor. There are villages in regular interval with many squatters and encroachers living or doing business along the road. All possible steps have been taken to minimize land acquisition and demolition of structures so as to reduce adverse impacts on people settled along the road. Based on the State Resettlement and Rehabilitation (R&R) Policy, GOI norms and ADB R&R policies, Bihar State Road Development Corporation (BSRDC), Government of Bihar has prepared Resettlement Plans (RPs) to deal with involuntary resettlement involve in the entire Project. All RPs have been prepared based on census and baseline socioeconomic surveys conducted in the fields.

4. To assist in the implementation of the RP for SH-81 (Sakaddi-Nasriganj), BSRDC now invites the services of eligible NGO.

2. Objectives of the Assignment

5. The NGO shall be responsible for the following, according to the Resettlement Plan:

 Educating the DPs on their rights to entitlements and obligations.  To ensure that the DPs are given the full entitlements due to them, according to the entitlements in the RP.  To provide support and information to DPs for income restoration.  Assist the DPs in relocation and rehabilitation, including counseling, and coordination with local authorities.  Assist the DPs in redressing their grievances (through the grievance redress committee set up by the subproject)  Impart information to all the DPs about the functional aspects of the various set up by the project, and assist them in benefiting from such institutional mechanisms.  To assist the Project Management Unit (PMU) and Project Implementation Unit (PIU) with social responsibilities of the subproject, such as compliance with labor laws, prohibition of child labor, and gender issues.

Appendix 2 79

 To conduct awareness program for HIV/AIDs, Human Trafficking.  To collect data and submit progress reports on a monthly and quarterly basis for BSRDC to monitor the progress of RP implementation.

3. Scope of Work

6. The NGO shall play the role of a secondary stakeholder in implementation of the RP and in mitigating adverse effects of the project. The NGO shall be responsible for the development of a comprehensive livelihood restoration system to facilitate the DPs to take advantage of the options available (as per the RP).

3.1 Administrative Responsibilities of the NGO

7. The administrative responsibilities of the NGO will include:  Working in co-ordination with the Project Resettlement Officer (RO) in the PMU and Resettlement Officer in the PIU;  Assist the RO in carrying out the implementation of the RP;  To coordinate with the GRCs in implementing the RP;  Assist the RO in conducting all public meetings, information campaigns at the commencement of the project and give full information to the affected community;  Translate the summary RP in local language to implement actions for mitigating adverse impacts on the DPs;  To assist the PIU/Engineers (Construction Supervision Consultants) to ensure that the Contracts comply with the applicable labor laws (including prohibition of child labor) and gender issues;  To assist the PIU and /or the Engineers in ensuring compliance with the safety, health and hygiene norms, and the conduct HIV/AIDS and Human Trafficking awareness/prevention campaigns.  Report to the RO on a monthly and quarterly basis. The report should include physical and financial progress, both in quantitative and qualitative terms. The report should prominently feature the problems and issues addressed and tackled with the DPs and the solutions found. The report should have a separate chapter on women's issues, their problems and what has been done (within the framework of the RP) to ensure their participation in decision-making as well as the options made available to them to access economic opportunities, marketing and credit. The report should clearly indicate the number of field visits made by the NGO staff and the outcome of consultations with people.  Data base management of the DPs.  The displaced persons will be assisted in the Income Generation Scheme training through the NGO i.e. the provision made for training will be best utilised through the active support and involvement of the NGO.

3.2 Responsibilities for Implementation of the RP

3.2.1 Identification DPs and Verification of Database from RP

 NGO shall verify the information already contained in the RP and the individual losses of the DPs. They should validate the data provided in the RP and make suitable changes if required. The NGO shall establish rapport with DPs, consult

80 Appendix 2

and provide information to them about the respective entitlements as proposed under the RP, and distribute entitlement cum Identity Cards to the eligible DPs. The identity card should include a photograph of the DP, the extent of loss suffered due to the project, and the choice of the DP with regard to the mode of compensation and assistance.  The NGO shall develop rapport between the DPs and the Project Authority, particularly the RO. This will be achieved through regular meetings with both the RO and the DPs. Meetings with the RO will be held at least fortnightly, and meetings with the DPs will be held monthly, during the entire duration of the assignment. All meetings and decisions taken shall be documented by the NGO.  Prepare monthly action plans with targets in consultation with the RO.  The NGO shall prepare a list of the project-displaced persons/families for relocation, enlisting the losses and the entitlements, after verification. It shall also prepare a list of the displaced persons (DPs) enlisting the losses and the entitlement as per the RP, after verification. Verification shall include actual measurement of the extent of total property loss/damage, and valuation of the loss/damage/affect along with the RO. The NGO shall display the list of eligible DPs in prominent public places like villages, Panchayat Offices, Block/Tehsil headquarters, and the District Headquarters.  During the identification and verification of the eligible DPs, the NGO shall ensure that each of the DPs are contacted and consulted either in groups or individually. The NGO shall specially ensure consultation with women from the DP families especially women headed households.  Participatory methods should be adopted in assessing the needs of the DPs, especially with regard to the vulnerable groups of DPs. The methods of contact may include village level meetings, gender participation through group’s interactions, and Individual meetings and interactions.  While finalizing the entitled persons (EPs) for compensation/assistance the NGO shall make a list of entitled DPs, and distribute Identity Cards to each and every verified eligible DP.

3.2.2 Counseling the Entitled Persons

8. The counseling shall include the following activities:  The NGO shall explain to the DPs the provisions of the policy and the entitlements under the RP. This shall include communication to the roadside squatters and encroachers about the need for their eviction, the timeframe for their removal and their entitlements.  The NGO shall disseminate information to the DPs on the possible consequences of the project on the communities' livelihood systems and the options available, so that they do not remain ignorant.  The NGO shall prepare micro-level plans for income restoration, in consultation with the DPs. Women's perceptions are important to be incorporated in the development of these plans.  NGO will monitor the involvement of child labor in the civil construction work in each package.

Appendix 2 81

9. In all of these, the NGO shall consider women as a special focus group, and deal with them with care and sympathy.

3.2.3 Disbursing the Assistance

 Prepare micro plans indicating category of entitlement.  Prepare micro plans for livelihood indicating alternative livelihood options, land identification, skills up grading and institutions responsible for training for eligible DPs.  The NGO shall assist the project authorities in ensuring a smooth transition (during the part or full relocation of the DPs), helping the DPs to take salvaged materials and shift. In close consultation with the DPs, the NGO shall inform the RO about the shifting dates agreed with the DPs in writing and the arrangements desired by the DPs with respect to their entitlements.  The NGO shall assist the DPs in opening bank accounts explaining the implications, the rules and the obligations of a joint account and how s/he can access the resources s/he is entitled to.  The NGO shall ensure proper utilisation of the R&R budget available for each of the packages. The NGO shall ensure that the DPs have found economic investment options and are able to restore the losses of land and other productive assets. The NGO shall identify means and advise the RO to disburse the entitlements to the eligible persons/families in a manner that is transparent, and shall report to the BSRDC on the level of transparency achieved in the project.

3.2.4 Accompanying and Representing the EPs at the Grievance Committee Meetings

 The NGO shall nominate a suitable person (from the staff of the NGO) to be a member of the GRCs for the respective contract packages.  The NGO shall make the DPs aware of the grievance redress committees (GRCs)  The NGO shall train the DPs on the procedure to file a grievance application and to confirm that a statement of claim from the concerned DP accompanies each grievance application. The NGO shall help the DPs in filling the grievance application and also in clearing their doubts about the procedure as well as the context of the GRC award.  The NGO shall record the grievance and bring it to the notice of the GRCs within seven days of receipt of the grievance from the DPs. It shall submit a draft resolution with respect to the particular grievance of the AP, suggesting multiple solutions, if possible, and deliberate on the same in the GRC meeting through the NGO representative in the GRC.  To accompany the DPs to the GRC meeting on the decided date, help the DP to express his/her grievance in a formal manner if requested by the GRC and again inform the DPs of the decisions taken by the GRC within 3 days of receiving a decision from the GRC. (The time frame for the GRC to take a decision is 15 days).

82 Appendix 2

3.2.5 Assisting the EPs and the RO to Identity and Negotiate for New Land for Resettlement

10. As part of the RP, it is proposed that a sizable number among the eligible DPs will receive alternative land (commercial) building structures. Some of the more vulnerable among the DPs will be eligible to receive these free of cost. Regarding these the NGO shall,

 Obtain the DPs choice in terms of Land identification, Site for relocation, Shifting plan and arrangements, Grant utilization plan and Community asset building plan and institutional arrangements in maintaining the assets.  Assist squatters whose structures needs to be shifted to the remaining government land for continuation of earning their livelihood before construction of road starts.  Assist the DPs/ RO in identifying suitable land for relocation and for agriculture, ensuring the replacement of the land lost in terms of quality and quantity.  Identify suitable government land in consultation with the Revenue Department officials and assist in negotiating its transfer to the DPs/ RO at reasonable prices and motivate them to appreciate and welcome the new neighbours.

3.2.6 Assisting Eligible DPs to take advantage of the existing Government Housing and Employment Schemes

11. With regard to the above, the NGO shall  Coordinate (and impart wherever required) the training and capacity building of the DPs, for upgrading their skills for income restoration. This will include the training to be given by the NGO to women self-help-group members in accounting, record maintenance, skill acquisition in the chosen enterprise, and marketing, etc.  Help the DPs in realizing and optimising the indigenous technology knowledge (ITK) through use of local resources.  Define, evolve, and explore alternative methods of livelihood using the local skill and resources.  Contact financial institutions like NABARD, DIC, and the Lead Bank of the area in accessing the credit required by the individual as well as groups of DPs and the women's groups from the DPs. The NGO shall maintain a detailed record of such facilitation, and plan for each DP to repay the loan.  Establish linkages with the district administration to ensure that the DPs are benefited from the schemes available and those they are entitled to. The focus for this component of the NGO work shall be the vulnerable DPs for their income restoration. The NGO shall maintain a detailed record of such facilitation.

3.2.7 Inter-Agency Linkages for Income Restoration and other R&R Services

12. The NGO shall be responsible for establishing linkages with,  Financial institutions to assist the DPs to access credit.  Government departments, district administration, etc., to ensure that the DPs are included in the development schemes, as applicable;  Training institutes to impart skills and management training for enterprise creation and development.  NGO shall conduct training programmes for income restoration for DPs.

Appendix 2 83

 NGO should prepare an income restoration plan.

3.2.8 Assisting the Supervision Consultant with the Project’s Social Responsibilities

13. The NGO shall assist the Engineers (Supervision Consultants) to ensure that the Contractors are abiding by the various provisions of the applicable laws, concerning the worker's safety, health and hygiene; women's issues and the child labor issues. The applicable laws include (A) the maternity benefit Act, 1951; (B) the contract labor (Regulation and Abolition) Act, 1948; (C) the Minimum Wagers act, 1948. (D) The Equal Remuneration Act, 1979. (E) the industrial Employment (Standing Order) Act, 1946; (F) the Child Labor (Prohibition and Regulation ) Act, 1986; (G) the Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act 1996; (H) the cess Act of 1996 and (I) the Factories Act, 1948. any divergence from the (workers welfare and remuneration, safety, health, hygiene, women's issues, and child labor issues) provisions of these laws should be brought to the notice of the supervision consultant and the RO.

14. According to these laws, there are specifications regarding the facilities/requirements at the construction camp/site, including basic health care facilities, Mother and Child Welfare units and facilities for vaccinations, day crèche facilities, etc. The NGO shall work in co-ordination of the Lady Inspector of Works or the Resident engineers of the Contractor, or any other representative of the Contractors, to ensure these facilities are provided in a satisfactory manner, and all social responsibilities of the Contract is implemented satisfactorily.

15. Coordinate with the Environmental Officer to facilitate consultation on rehabilitation of borrow areas.

3.2.9 Assisting the PMU/Supervision Consultant in HIV/AIDS Awareness/Prevention Campaigns

16. Information campaigns/advertisements in collaboration with line agencies (such as NACO, DFID, etc), including provision of signage/hoardings at suitable locations, distribution of vehicle stickers, and provision of condom vending machines at suitable locations (rest areas, truck parking lay-byes, etc.). The NGO shall assist the PMU to implement these measures, including collaboration with the line agencies.

17. The contractors are required to provide condom vending machines at the construction camps, provide for medical facilities and regular medical checkups especially for detecting/curing STD/AIDS. The NGO shall ensure, in collaboration with the Engineer that such facilities and medical checkups are provided to the workers at the construction camps.

3.2.10 Monitoring and Reporting

18. The RP includes provision for monthly internal monitoring by NGO/ RO and quarterly, mid-term, and post-project monitoring and Reporting by external agency. The NGO involved in the implementation of the RP will be required to supply all information, documents to the external monitoring and Reporting consultants. To this end, the NGO shall keep proper documentation of their work and the R&R process involved in the project, and shall be responsible for the upkeep and updating of such documents periodically and regularly. The documentation shall include photographs and videotapes of the pre-intervention and post- intervention scenario of all the properties, structures, and assets affected by the project.

84 Appendix 2

3.2.11 Recommending Improvement of R&R Services

 Extend all services recommended by any additional studies to be undertaken by the project, in respect to the R&R services to be provided as part of the project.  Recommend and suggest techniques and methods for improvement of services extended by the concerned government departments and other agencies and committees in disbursement/extension of R&R services in the project.  Document implementation of the R&R process and services, including difficulties faced and corresponding solutions.  Discuss, with the PMU/PIU on contingency management and other improvement of R&R services, within the project period.  Documenting of tasks carried out by the NGO and Reporting of the achievements of RP.

3.3 Documentation and Reporting by NGO

19. The NGO selected for the assignments shall be responsible to:  Submit an inception report within three weeks; on signing up of the contract including a work plan for the whole contract period, staffing and personnel deployment plan, and a withdrawal plan at the end of the period of contract. The withdrawal plan shall be detailed and reflect how the DPs will maintain the assets created and transferred to the DPs.  Prepare monthly progress reports to be submitted to the RO, with weekly progress and work charts as against the scheduled timeframe of RP implementation.  Prepare and submit quarterly reports on a regular basis, to be submitted to the RO.  Submit a completion report at the end of the contract period summarizing the actions taken during the project, the methods and personnel used to carry out the assignment, and a summary of support/assistance given to the DPs.  All other reports/documentation as described in these terms of reference.  Record minutes of all meetings.

20. All progress reports shall include data on input and output indicators as required by the RO. Reporting in writing as well as photographs, videotapes etc., taken during the assignment shall be submitted in support of the reports, along with an electronic copy of the documents in a floppy or a CD. All reports should be in English only. Accounts reports both on expenditure on administration as well as training and other heads shall be submitted with the quarterly and the completion reports.

21. In addition to these above, the NGO shall prepare and submit separate descriptive reports on participatory micro-plans with full details of the Participatory Rapid Appraisal exercises conducted.

22. The NGO shall document in full detail, the consultation/counseling processes, the process of identification of the resettlement sites, and a full description of the training imparted (on facilitated) as part of the assignment. This documentation shall be submitted to the BSRDC as annual reports.

Appendix 2 85

3.4 Condition of Services

23. The NGO shall ensure that the RP is implemented in an effective and proper manner. The prime responsibility of the NGO shall be to ensure that each and every eligible DP receives appropriate and due entitlement (within the Entitlement Framework) and that, at the end of the project R&R services, the eligible DPs have improved (or at least restored) their previous standard of living. Additionally the NGO shall help the PMU/PIU in all other matters deemed to be required to implement the RP in its spirit and entirely including activities involving some financial implications.

24. All documents created, generated or collected during the period of contract, in carrying out the services under this assignment will be the property of the PMU/PIU. No information gathered or generated during and in carrying out this assignment shall be disclosed by the NGO without explicit permission of the PMU/PIU.

3.5 Timeframe for Services

25. The NGO will be contracted for a period of 12 months from the date of commencement, with a withdrawal methodology built in to the proposals from the NGO.

3.6 Data, Services and Facilities to be provided by the Client

26. The PMU/PIU will provide to the NGO the copies of the SIA report/ DPs' Census, the RP, the strip plan final design report and any other relevant reports/data prepared by the project preparation consultants. The PMU/PIU will assist the NGO in collaborating with the Supervision Consultants. All facilities required in the performance of the assignment, including office space, office stationery, transportation and accommodation for staff of the NGO, etc., shall be arranged by the NGO.

3.7 Payment Schedule:

27. The following payment milestone is proposed for making the payment to the NGO. The payment will be made subject to the submission of a certificate from the PMU/PIU/RO that the targets have been achieved in a satisfactory manner.

Sl. Payment Milestone Payment (% of No. contract Value) 1. On submission of the inception Report complete in all respects 20

2. On completion of the identification, verification of DPs and 20 initial consultation sessions, and submission of updated data on DPs (Identification and Verification report) and review of the same by the PMU/PIU.

3. On submission and approval of the Micro Plan of DPs 20

4. On completion of the rehabilitation process and 20 implementation of I.R. Plan

5. On submission of the Final Completion Report 20 Total 100

86 Appendix 2

28. The above remuneration includes all costs related to carrying out the services, including overhead. The service tax or any other tax component shall be reimbursed/ paid to NGO on production of documents. The insurance cost will be separate of the total project cost; the client shall be billed for this.

3.8 Team for the Assignment

29. The NGO shall assign a team of professionals to the site. The constitution of the team and the qualification for the team members is given below:

Sl. No. Of No. Position Positions Qualifications 1. Team Leader 1 The Team Leader should be a post-graduate in sociology/social work/r, and should have experience of working in civil engineering projects. S/he should have more than 10 years experience in implementation of R&R and rural development works. S/he should have held responsible positions in previous assignments possess participatory management skills and should have good knowledge of the region and the local languages.

2. Key 1 Should be at least a graduate in social science. S/he Professionals should have at least 5 years experience in fieldwork. (A) S/he should have participated in at least one project involving R&R activities, should have participatory knowledge of land measurement, and should be conversant with land valuation methods. Knowledge of local language is a necessary qualification. S/he should have experience in livelihood analysis, developing and implementing vocational training, experience in participatory management.

3. Key 2 Should be at least a graduate in social sciences. S/he Professionals should have about 5 years of working experience of (B) which about 2 years in R&R or rural development projects. Should have sound understanding of the land acquisition process and experience in participatory management. S/he should have experience in livelihood analysis, developing and implementing vocational training, experience in participatory management. Knowledge of local language is a necessary qualification.

4. Technical Adequate Should be graduate or equivalent in social sciences support as per the with field work experiences. Knowledge of local professionals NGO language and experience of working in the region desired.

5. Other support Adequate No minimum qualification

Appendix 2 87

Sl. No. Of No. Position Positions Qualifications Personnel as per the NGO

30. Additionally the following conditions shall apply to the team proposed by the NGO.

 The proposal should accompany a personnel deployment schedule, clearly indicating whether the deployment is home-office based or in the field.  The NGO must propose at least one woman as part of the key personnel. The person-month deployment of the woman key personnel shall constitute at least 33 % of the person-month deployment of all key professionals (including the team leader) in the assignment. At least two proposed woman key person shall be available to work at site for at least 50% of the duration.  The women key persons, if selected for the contract, may be replaced during the period of contract, only with women key persons of equivalent qualifications and experience.  The NGO will assign a 'technical support' team to work at the site, which will consist of at least 33 % of women members. Junior support personnel and/or administrative staff will not be considered as 'technical support' professionals, as far as this condition is concerned.

Appendix 3 to Resettlement Plan (SH-81) LIST OF AFFECTED PROPERTIES - CPR Land Name of Affected Area Sl. No. Name of the Village Name of Block Plot No. Use of Land Name of the Owner Father’s Name District (in Acre) 1 Kharao chaturbhuj Sahar Bhojpur 1814 Others 0.051 Temple Land Temple Land 2 Kharao chaturbhuj Sahar Bhojpur 1887 Others Temple Land Temple Land 3 Nonaur Agiaon Bhojpur 242 _ 0.103 Kabristan Kabristan 4 Imadpur Tarari Bhojpur 1187 Others Takur jee Sewayat Takur jee Sewayat

1 Appendix 3 to Resettlement Plan (SH-81) LIST OF AFFECTED PROPERTIES - CPR-Structures Existing Type of Distance from Sl. No. Road Side Ownership Type of Construction (Km.) Properties C/L (in mts.) 1 Right 0.200 Shrine Religious 3.00 Permanent 2 Left 0.800 Shrine Religious 4.00 Permanent 3 Left 1.800 Shrine Religious 3.00 Permanent 4 Right 2.700 Shrine Religious 7.00 Semi-Permanent 5 Left 3.200 Shrine Religious 4.00 Permanent 6 Right 3.600 Shrine Religious 2.00 Permanent 7 Left 5.400 Shrine Religious 2.00 Semi-Permanent 8 Right 6.900 Shrine Religious 4.00 Permanent 9 Right 7.800 Shrine Religious 3.00 Permanent 10 Right 8.100 Shrine Religious 4.00 Permanent 11 Left 8.200 Shrine Religious 4.50 Semi-Permanent 12 Left 10.000 Shrine Religious 2.50 Semi-Permanent 13 Right 10.900 Shrine Religious 4.50 Semi-Permanent 14 Left 10.900 Shrine Religious 3.00 Semi-Permanent 15 Left 12.500 Shrine Religious 3.00 Permanent 16 Right 13.300 Shrine Religious 3.50 Permanent 17 Left 15.000 Shrine Religious 5.50 Semi-Permanent 18 Right 17.200 Shrine Religious 3.00 Semi-Permanent 19 Right 18.500 Shrine Religious 2.50 Semi-Permanent 20 Left 18.600 Shrine Religious 5.50 Permanent 21 Right 18.500 Shrine Religious 4.00 Permanent 22 Left 12.500 Small Temple Religious 4.00 Permanent 23 Right 18.600 Kabristan Religious 4.00 Permanent 24 Left 21.000 Small Temple Religious 4.00 Permanent 25 Right 21.300 Small Temple Religious 5.00 Permanent 26 Left 21.900 Community Hall Community 12.70 Permanent 27 Right 24.100 Mosque Religious 9.50 Permanent 28 Right 24.000 Small Temple Religious 14.20 Permanent 29 Right 25.000 Shrine Religious 5.00 Permanent 30 Right 23.400 Small Temple Religious 7.50 Permanent 31 Right 27.300 Small Temple Religious 3.30 Permanent 32 Right 29.400 Shrine Religious 4.50 Semi-Permanent 33 Right 29.600 Shrine Religious 8.00 Semi-Permanent 34 Right 40.300 Small Temple Religious 5.80 Permanent 35 Right 42.300 Community Hall Community 7.50 Permanent 36 Right 45.600 Shrine Religious 6.20 Permanent 37 Right 45.800 Shrine Religious 6.00 Permanent 38 Left 46.000 Aaganbadi Community 14.80 Permanent 39 Right 20.400 Kabristan Religious 5.00 Permanent 40 Right 24.200 Shrine Religious 14.80 Permanent 41 Right 24.900 Shrine Religious 12.70 Temporary 42 Right 51.000 Small Temple Religious 12.50 Permanent 43 Left 58.000 Shrine Religious 6.00 Temporary 44 Right 67.000 Small Temple Religious 3.00 Temporary 45 Right 71.700 Shrine Religious 3.00 Permanent 46 Right 73.100 Small Temple Religious 3.50 Permanent 47 Right 73.400 Temple Religious 5.50 Permanent 48 Right 32.000 Small Temple Religious 6.10 Permanent 49 Right 47.600 Small Temple Religious 4.50 Permanent 50 Right 51.900 Small Temple Religious 3.00 Permanent 51 Right 54.500 Shrine Religious 9.60 Permanent 52 Right 65.400 Small Temple Religious 5.50 Permanent

1 Appendix 3 to Resettlement Plan (SH-81) LIST OF AFFECTED PROPERTIES - Government Land Name of Affected Area Sl. No. Name of the Village Name of Block Plot No. Use of Land Name of the Owner District (in Acre) 1 Sakaddi Koilwar Bhojpur 2690 _ Jila Parishad 2 Sakaddi Koilwar Bhojpur 2691 _ Jila Parishad 3 Sakaddi Koilwar Bhojpur 2727 _ Government of Bihar 4 Sakaddi Koilwar Bhojpur 3207 _ Bihar Government 5 Sakaddi Koilwar Bhojpur 3208 _ Bihar Government 6 Sakaddi Koilwar Bhojpur 3209 _ 0.013 Bihar Government 7 Sakaddi Koilwar Bhojpur 3324 Bihar Government 8 Ahiman Chak Sandesh Bhojpur 277 _ Government of Bihar 9 Baga Sandesh Bhojpur 1366 _ Bihar Government 10 Andhari Sahar Bhojpur 1501 _ Canal department 11 Andhari Sahar Bhojpur 794 _ Canal department 12 Andhari Sahar Bhojpur 2056 _ District Board 13 Andhari Sahar Bhojpur 2057 _ 0.153 District Board 14 Andhari Sahar Bhojpur 1522 _ Canal department 15 Andhari Sahar Bhojpur 1707 _ Government of India 16 Andhari Sahar Bhojpur 1737 _ Government of India 17 Andhari Sahar Bhojpur 1783 _ Government of India 18 Andhari Sahar Bhojpur 1788 _ Government of India 19 Andhari Sahar Bhojpur 2056 _ District Board 20 Baruhi Sahar Bhojpur 3655 Others Govt of Bihar 21 Baruhi Sahar Bhojpur 3585 Others Government of India 22 Banjaria Sahar Bhojpur 1554 _ Jila parishad 23 Banjaria Sahar Bhojpur 2104 Others Jila parishad 24 Peur Chak Sahar Bhojpur 240 _ Canal Department Government of Bihar 25 Sahar Sahar Bhojpur 564 Others Government of Bihar 26 Abgilla Sahar Bhojpur 510 _ Government of Bihar 27 Abgilla Sahar Bhojpur 638 _ Samudayic Vikash Vibhag 28 Abgilla Sahar Bhojpur 510 _ Government of Bihar 29 Abgilla Sahar Bhojpur 510 _ Government of Bihar 30 Peur Sahar Bhojpur 306 _ Government of Bihar 31 Peur Sahar Bhojpur 341 _ Government of Bihar 32 Kharao chaturbhuj Sahar Bhojpur 1348 _ 0.012 Government of Bihar 33 Dhauri Sahar Bhojpur 381 _ Government of Bihar 34 Dhauri Sahar Bhojpur 380 Cultivation Government of Bihar 35 Banshi Dihri Sahar Bhojpur 804 _ 0.005 Government of Bihar 36 Banshi Dihri Sahar Bhojpur 805 _ 0.007 Government of Bihar 37 Banshi Dihri Sahar Bhojpur 803 _ Government of Bihar 38 Banshi Dihri Sahar Bhojpur 807 _ Government of Bihar 39 Banshi Dihri Sahar Bhojpur 808 _ Government of Bihar 40 Banshi Dihri Sahar Bhojpur 626 _ Government of Bihar 41 Banshi Dihri Sahar Bhojpur 627 _ Government of Bihar 42 Banshi Dihri Sahar Bhojpur 628 _ Government of Bihar 43 Nonaur Agiaon Bhojpur 341 _ Canal Department, Govt. of Bihar 44 Nonaur Agiaon Bhojpur 415 _ 0.016 Government of Bihar 45 Nonaur Agiaon Bhojpur 417 _ Canal Department, Govt. of Bihar 46 Bramapur-Mehdora Agiaon Bhojpur 2956 _ District Board 47 Bramapur-Mehdora Agiaon Bhojpur 2957 _ Canal Department, Govt. of Bihar 48 Bramapur-Mehdora Agiaon Bhojpur 2955 _ Canal Department, Govt. of Bihar 49 Bramapur-Mehdora Agiaon Bhojpur 2954 _ Canal Department, Govt. of Bihar 50 Bramapur-Mehdora Agiaon Bhojpur 2953 _ Canal Department, Govt. of Bihar 51 Bramapur-Mehdora Agiaon Bhojpur 2956 _ District Board 52 Bramapur-Mehdora Agiaon Bhojpur 2956 _ Canal Department, Govt. of Bihar 53 Bramapur-Mehdora Agiaon Bhojpur 1405 _ Canal Department, Govt. of Bihar 54 Imadpur Tarari Bhojpur 1215 _ Government of Bihar 55 Imadpur Tarari Bhojpur 1188 _ 0.222 Government of Bihar 56 Imadpur Tarari Bhojpur 1148 _ 0.438 Government of Bihar 57 Imadpur Tarari Bhojpur 1066 _ 0.014 Government of Bihar 58 Rajpur Tarari Bhojpur 1263 _ 0.003 Government of India 59 Rajpur Tarari Bhojpur 1418 _ |Jila Parishad 60 Rajpur Tarari Bhojpur 1419 _ |Jila Parishad 61 Rajpur Tarari Bhojpur 1134 _ Bihar Government 62 Bihta Tarari Bhojpur 2920 _ 0.058 Govt of Bihar 63 Bihta Tarari Bhojpur 2905 _ Government of Bihar 64 Bihta Tarari Bhojpur 2919 _ 0.017 Government of Bihar 65 Bihta Tarari Bhojpur 2871 _ Government of Bihar 66 Bihta Tarari Bhojpur 2031 0.007 Jila Parishad 67 Bihta Tarari Bhojpur 3035 0.016 Jila Parishad 68 Bihta Tarari Bhojpur 3036 0.019 Jila Parishad 69 Bihta Tarari Bhojpur 3046 _ Jila Parishad 70 Bihta Tarari Bhojpur 3604 _ Government of Bihar 71 Bihta Tarari Bhojpur 4210 _ Government of Bihar 72 Bihta Tarari Bhojpur 4223 _ Government of Bihar 73 Bihta Tarari Bhojpur 4228 _ Government of Bihar 74 Bihta Tarari Bhojpur 4229 _ Government of Bihar 75 Bihta Tarari Bhojpur 4248 _ Government of Bihar 76 Bihta Tarari Bhojpur 6542 _ Jila Parishad, Govt. of Bihar 77 Bihta Tarari Bhojpur 6390 _ Government of Bihar 78 Bihta Tarari Bhojpur 5701 _ Government of Bihar 79 Bihta Tarari Bhojpur 6542 _ Jila Parishad, Govt. of Bihar 80 Bihta Tarari Bhojpur 5672 _ Government of Bihar 81 Bihta Tarari Bhojpur 4228 _ Government of Bihar 82 Bihta Tarari Bhojpur 5007 _ Canal Department, Govt. of Bihar 83 Bihta Tarari Bhojpur 5009 _ Canal Department, Govt. of Bihar 84 Bihta Tarari Bhojpur 5640 _ Canal Department, Govt. of Bihar 85 Bihta Tarari Bhojpur 5641 _ Jila Parishad, Govt. of Bihar 86 Bihta Tarari Bhojpur 6542 _ Jila Parishad, Govt. of Bihar 87 Sawari Lakh Nasrigung Rohtas 56 _ Government of Bihar 88 Sawari Lakh Nasrigung Rohtas 200 _ Government of Bihar 89 Sawari Lakh Nasrigung Rohtas 149 _ 0.011 Government of Bihar 90 Sawari Lakh Nasrigung Rohtas 139 _ Government of Bihar 91 Sawari Lakh Nasrigung Rohtas 150 _ 0.003 Government of Bihar 92 Sawari Lakh Nasrigung Rohtas 154 _ 0.002 Government of Bihar 93 Sawari Lakh Nasrigung Rohtas 146 _ Government of Bihar 94 Sawari Lakh Nasrigung Rohtas 147 _ Jila Parishad 95 Sawari Lakh Nasrigung Rohtas 259 _ 0.075 Jila Parishad 96 Sawari Lakh Nasrigung Rohtas 260 _ 0.026 Jila Parishad 97 Sawari Lakh Nasrigung Rohtas 232 _ GOIApendix 3

1 Name of Affected Area Sl. No. Name of the Village Name of Block Plot No. Use of Land Name of the Owner District (in Acre) 98 Sawari Lakh Nasrigung Rohtas 166 _ 0.015 Government of Bihar 99 Medinipur Nasrigung Rohtas 179 _ Jila Parishad 100 Medinipur Nasrigung Rohtas 180 _ 0.108 Jila Parishad 101 Medinipur Nasrigung Rohtas 143 _ Jila Parishad 102 Medinipur Nasrigung Rohtas 144 _ Jila Parishad 103 Medinipur Nasrigung Rohtas 316 _ Jila Parishad 104 Medinipur Nasrigung Rohtas 318 _ 0.146 Jila Parishad 105 Medinipur Nasrigung Rohtas 134 _ Government of India 106 Medinipur Nasrigung Rohtas 323 _ Jila Parishad 107 Sikariya Karakat Rohtas 1570 _ Sarva Sadharan 108 Sikariya Karakat Rohtas 1577 _ 0.007 Sarva Sadharan 109 Gharwasdih Karakat Rohtas 812 _ 0.021 Government of Bihar 110 Gharwasdih Karakat Rohtas 766 _ 0.005 Government of Bihar 111 Gharwasdih Karakat Rohtas 877 _ 0.307 Government of Bihar 112 Gharwasdih Karakat Rohtas 824 _ 0.027 Government of Bihar 113 Gharwasdih Karakat Rohtas 878 _ Government of Bihar

2 SAppendix 3 to Resettlement Plan (SH-81) LIST OF AFFECTED PROPERTIES - Private Land Name of Affected Area Sl. No. Name of the Village Name of Block Plot No. Use of Land Name of the Owner Father’s Name District (in Acre) 1 Sakaddi Koilwar Bhojpur 2326 Cultivation 0.006 Devkeshwar Singh Ramswaraj Singh 2 Sakaddi Koilwar Bhojpur 2327 Cultivation 0.006 Badri Nath Singh Keli Singh 3 Sakaddi Koilwar Bhojpur 2328 Cultivation 0.064 Badli Singh Shivgovind Singh 4 Sakaddi Koilwar Bhojpur 3350 Cultivation 0.113 Sabhan Miya Subedar Miya 5 Sakaddi Koilwar Bhojpur 2342 Cultivation 0.059 Badli Singh Shivgovind Singh 6 Sakaddi Koilwar Bhojpur 2343 Cultivation 0.008 Nathuni Singh Brikshwar Singh 7 Sakaddi Koilwar Bhojpur 2344 Cultivation 0.01 Nathuni Singh Brikshwar Singh 8 Sakaddi Koilwar Bhojpur 2328 Cultivation 0.064 Badli Singh Shivgovind Singh 9 Sakaddi Koilwar Bhojpur 2347 Cultivation 0.016 Nathuni Singh Brikshwar Singh 10 Sakaddi Koilwar Bhojpur 2348 Cultivation 0.012 Kameshwar Singh Dhanpat Singh 11 Sakaddi Koilwar Bhojpur 2349 Cultivation Ramanand Singh Anirudh Singh 12 Sakaddi Koilwar Bhojpur 2350 Cultivation Anirudh Singh Mandeep Singh 13 Sakaddi Koilwar Bhojpur 2352 Cultivation Ramakant Singh Ganesh Singh 14 Sakaddi Koilwar Bhojpur 2692 Cultivation 0.016 Nag Narayan Singh Ramyash Singh 15 Sakaddi Koilwar Bhojpur 2693 Cultivation 0.014 Bhuneshwar Singh Ram Bahadur Singh 16 Sakaddi Koilwar Bhojpur 2694 Cultivation Md Jaya -ul-Haq Md. Islam 17 Sakaddi Koilwar Bhojpur 2695 Cultivation 0.076 Shiveshwar Singh Ram Lagan Singh 18 Sakaddi Koilwar Bhojpur 2696 Cultivation 0.007 Bhaneshwer Singh Ram Bahadur Singh 19 Sakaddi Koilwar Bhojpur 2701 Cultivation 0.044 Ramye Singh Bikrma Singh 20 Sakaddi Koilwar Bhojpur 2702 Cultivation 0.052 Kalpu Lal Bishun Lal 21 Sakaddi Koilwar Bhojpur 2703 Cultivation 0.083 Barmeshwer Singh Ram Kumar Singh 22 Sakaddi Koilwar Bhojpur 2707 Cultivation Nathuni Singh Virkeshwar Singh 23 Sakaddi Koilwar Bhojpur 2726 Cultivation Nathuni Singh Virkeshwar Singh 24 Sakaddi Koilwar Bhojpur 2745 Cultivation 0.049 Rahul Singh Baccha Bahudur Singh 25 Sakaddi Koilwar Bhojpur 2748 Cultivation 0.018 Rahul Singh Baccha Bahudur Singh 26 Sakaddi Koilwar Bhojpur 2751 0.035 Raghunandan Singh Ramnarayan Singh 27 Sakaddi Koilwar Bhojpur 2753 Cultivation 0.017 Jagarnath Mishra Kedar Mishra 28 Sakaddi Koilwar Bhojpur 2756 Cultivation 0.015 Jagarnath Mishra Kedar Mishra 29 Sakaddi Koilwar Bhojpur 2757 Cultivation 0.08 Ramanand Singh Chandrama Singh 30 Sakaddi Koilwar Bhojpur 2759 Cultivation Ramanand Singh Chandrama Singh 31 Sakaddi Koilwar Bhojpur 2760 Cultivation 0.027 Ramanand Singh Chandrama Singh 32 Sakaddi Koilwar Bhojpur 2761 Cultivation Ramanand Singh Chandrama Singh 33 Sakaddi Koilwar Bhojpur 2762 Cultivation Ramanand Singh Chandrama Singh 34 Sakaddi Koilwar Bhojpur 2769 Cultivation 0.014 Ramanand Singh Chandrama Singh 35 Sakaddi Koilwar Bhojpur 2790 0.13 Ramanand Singh Chandrama Singh 36 Sakaddi Koilwar Bhojpur 2791 Cultivation 0.038 Chandra jota Kuwnar Sahab Singh 37 Sakaddi Koilwar Bhojpur 2805 Cultivation 0.001 Chandra jota Kuwnar Sahab Singh 38 Sakaddi Koilwar Bhojpur 2807 0.072 Strudhan Prasad Ramkit Matho 39 Sakaddi Koilwar Bhojpur 2808 Cultivation 0.056 Satyanaryan Singh Budhu Singh 40 Sakaddi Koilwar Bhojpur 2809 Cultivation 0.054 Bhola Rai Bandhu Rai 41 Sakaddi Koilwar Bhojpur 2810 0.019 Ramanand Singh Chandra daman Singh 42 Sakaddi Koilwar Bhojpur 2811 Cultivation 0.038 Ramanand Singh Chandrama Singh 43 Sakaddi Koilwar Bhojpur 2812 Cultivation 0.045 Ramanand Singh Chandrama Singh 44 Sakaddi Koilwar Bhojpur 2813 Cultivation 0.027 Ramanand Singh Chandrama Singh 45 Sakaddi Koilwar Bhojpur 2814 Cultivation 0.016 Ramanand Singh Chandrama Singh 46 Sakaddi Koilwar Bhojpur 2835 Cultivation Dukhharn Sah Ramdevi Sah 47 Sakaddi Koilwar Bhojpur 2836 Cultivation Statradhan Prasad Ramkit Matho 48 Sakaddi Koilwar Bhojpur 2837 Cultivation 0.204 Statradhan Prasad Ramkit Matho 49 Sakaddi Koilwar Bhojpur 3180 Cultivation 0.012 Mahipad Dusadh Deepan Dusadh 50 Sakaddi Koilwar Bhojpur 3181 Cultivation 0.048 Ramdhar Yadav Balgovind Badgha 51 Sakaddi Koilwar Bhojpur 3182 Cultivation 0.105 Sita Ram Mali Satyadev Sharma 52 Sakaddi Koilwar Bhojpur 3192 Cultivation 0.046 Md.Aziz Miya Bahadur Miya 53 Sakaddi Koilwar Bhojpur 3199 Cultivation 0.098 Ramgobin Mahto Shivratan Mahto 54 Sakaddi Koilwar Bhojpur 3200 Cultivation 0.021 Abdul Miya Sabir Miya 55 Sakaddi Koilwar Bhojpur 3202 Cultivation 0.092 Gurucharan Yadav Naryan Dutt Yadav 56 Sakaddi Koilwar Bhojpur 3203 Cultivation 0.102 Gulab Yadav Ramchandra Yadav 57 Sakaddi Koilwar Bhojpur 3204 Cultivation 0.065 Nayam Miya Mugeri Miya 58 Sakaddi Koilwar Bhojpur 3205 Cultivation 0.017 Dodha Yadav Shiv Yadav 59 Sakaddi Koilwar Bhojpur 3210 Cultivation 0.008 Premdhar Rai Guruchrn Rai 60 Sakaddi Koilwar Bhojpur 3211 Cultivation 0.017 Shivdahin Yadav Raval Yadav 61 Sakaddi Koilwar Bhojpur 3230 0.039 Yogindra Pd Singh Parma Singh Yadav 62 Sakaddi Koilwar Bhojpur 3231 Cultivation 0.057 Ramchand Yadav Naryandatt Yadav 63 Sakaddi Koilwar Bhojpur 3235 Cultivation 0.078 Abdul Gaffur Nathuni Mia 64 Sakaddi Koilwar Bhojpur 3236 Cultivation 0.025 Dodha Yadav Shiv Yadav 65 Sakaddi Koilwar Bhojpur 3237 Cultivation 0.049 Rufa Mia Abdul Rahim Ansari 66 Sakaddi Koilwar Bhojpur 3238 Cultivation 0.014 Dodha Yadav Shiv Yadav 67 Sakaddi Koilwar Bhojpur 3240 Cultivation 0.029 Yogindra Pd Singh Parma Singh Yadav 68 Sakaddi Koilwar Bhojpur 3274 Cultivation Gurucharan Yadav Narayandutt Yadav 69 Sakaddi Koilwar Bhojpur 3275 Cultivation 0.04 Gurucharan Yadav Narayandutt Yadav 70 Sakaddi Koilwar Bhojpur 3276 Cultivation Dodha Yadav Shiv Yadav 71 Sakaddi Koilwar Bhojpur 3277 Cultivation 0.031 Dodha Yadav Shiv Yadav 72 Sakaddi Koilwar Bhojpur 3278 Cultivation 0.041 Dodha Yadav Shiv Yadav 73 Sakaddi Koilwar Bhojpur 3279 Cultivation Chandeo 74 Sakaddi Koilwar Bhojpur 3280 Cultivation Dodha Yadav Shiv Yadav 75 Sakaddi Koilwar Bhojpur 3283 Cultivation 0.005 Lotan Yadav Shyama Yadav 76 Sakaddi Koilwar Bhojpur 3284 Cultivation Dodha Yadav Shiv Yadav 77 Sakaddi Koilwar Bhojpur 3310 Cultivation Mahabir Rai Khuba Rai 78 Sakaddi Koilwar Bhojpur 3313 Cultivation 0.031 Hari Yadav Shyama Yadav 79 Sakaddi Koilwar Bhojpur 3314 Cultivation 0.028 Hari Yadav Shyama Yadav 80 Sakaddi Koilwar Bhojpur 3315 Cultivation 0.008 Subhan Mistri Subedan Mistri 81 Sakaddi Koilwar Bhojpur 3316 Cultivation 0.007 Hrendra Rai Binoda Rai 82 Sakaddi Koilwar Bhojpur 3317 Cultivation 0.049 Chandan Mishra Pramanand Mishra 83 Sakaddi Koilwar Bhojpur 3321 Cultivation 0.006 Parpati Mistri Jawahir Mistri 84 Sakaddi Koilwar Bhojpur 3325 Cultivation Balgovind Bandhudaga 85 Sakaddi Koilwar Bhojpur 3349 Cultivation 0.051 Durabin Mahto Bakhand Mahato 86 Sakaddi Koilwar Bhojpur 3350 Cultivation 0.113 Sabhan Miya Subedar Miya 87 Sakaddi Koilwar Bhojpur 3351 Cultivation 0.058 Sabhan Miya Subedar Miya 88 Sakaddi Koilwar Bhojpur 3352 Cultivation Daran Shrama Dev Kumar Sharma 89 Sakaddi Koilwar Bhojpur 3356 Cultivation 0.032 Parmeshwar Kailash 90 Sakaddi Koilwar Bhojpur 3357 Cultivation Panpatti Barhai Jawahir Mistri 91 Sakaddi Koilwar Bhojpur 3378 Cultivation 0.016 Brijnandan Yadav Ram Chandara Yadav 92 Sakaddi Koilwar Bhojpur 3385 Cultivation 0.066 Nathuni Singh Virkeshwar Singh 93 Sakaddi Koilwar Bhojpur 3386 Cultivation 0.0316 Nathuni Singh Virkeshwar Singh 94 Sakaddi Koilwar Bhojpur 3612 Ram Raj Yadav Nathuni Yadav 95 Sakaddi Koilwar Bhojpur 3618 Cultivation 0.016 Ram Janam Singh Shiv Nandan Singh 96 Sakaddi Koilwar Bhojpur 3919 Cultivation Ram Janam Singh Shiv Nandan Singh 97 Sakaddi Koilwar Bhojpur 3620 Cultivation 0.042 Ram Janam Singh Shiv Nandan Singh

1 Name of Affected Area Sl. No. Name of the Village Name of Block Plot No. Use of Land Name of the Owner Father’s Name District (in Acre) 98 Sakaddi Koilwar Bhojpur 3621 0.002 Shiveshwar Singh Ram Lagan Singh 99 Akhgaon Sandesh Bhojpur 1051 Cultivation 0.019 Lagandeep Singh Devi Singh 100 Akhgaon Sandesh Bhojpur 1052 Cultivation 0.082 Panchanand Singh Ram Pd Singh 101 Akhgaon Sandesh Bhojpur 1059 Cultivation 0.097 Moti Singh Dev Nandan Singh 102 Akhgaon Sandesh Bhojpur 1060 Cultivation 0.072 Gopal Dutt Shastri Niwash Singh 103 Akhgaon Sandesh Bhojpur 1061 Cultivation 0.029 Narshit Tiwari Kapil dev Tiwari 104 Akhgaon Sandesh Bhojpur 1064 Cultivation 0.102 Sardar Dina Singh Bidyanandan Singh 105 Akhgaon Sandesh Bhojpur 1065 Cultivation Shaanjada Singh Tuna Singh 106 Akhgaon Sandesh Bhojpur 1067 Cultivation 0.048 Sukhai Yadav Ram Bireoch Yadav 107 Akhgaon Sandesh Bhojpur 1072 Cultivation 0.034 Jagranath Sah Gulaba Chand Sah 108 Akhgaon Sandesh Bhojpur 1073 Cultivation 0.114 Raghunath Prasad Choursiya Ramdahin Sah 109 Akhgaon Sandesh Bhojpur 1075 Cultivation 0.064 Bhagendra Bhagat Ruplal Bhagat 110 Akhgaon Sandesh Bhojpur 1076 Cultivation 0.032 Hidal Yadav Yadu Yadav 111 Akhgaon Sandesh Bhojpur 1128 Radha Singh Rang Lal Singh 112 Akhgaon Sandesh Bhojpur 1140 Cultivation 0.025 Jagranath Sah Ram Jatan Singh 113 Akhgaon Sandesh Bhojpur 1141 Cultivation 0.087 Gharbharan Dushad Jadik Dushad 114 Akhgaon Sandesh Bhojpur 1142 Cultivation Moti Singh Ramlayak Singh 115 Akhgaon Sandesh Bhojpur 1143 Cultivation 0.026 Shviman naryan Singh Hardev Singh 116 Akhgaon Sandesh Bhojpur 1148 Cultivation 0.033 Lalita Kumari Aashdev Singh 117 Akhgaon Sandesh Bhojpur 1150 Saryu Pd Singh Dhanurdhari Singh 118 Akhgaon Sandesh Bhojpur 1153 Cultivation Chandordev Singh Jagesh Singh 119 Akhgaon Sandesh Bhojpur 1154 Cultivation 0.033 Laxmi Singh Ramjatan Singh 120 Akhgaon Sandesh Bhojpur 1155 Cultivation Rajeshwer Singh Ramnath Singh 121 Akhgaon Sandesh Bhojpur 1156 Cultivation Satnarayan Singh RamPrabandh Singh 122 Akhgaon Sandesh Bhojpur 1157 Cultivation 0.101 Ram Narayan Singh Ram Autar Singh 123 Akhgaon Sandesh Bhojpur 1158 Cultivation 0.087 Shahbjad Singh Nath Narayan Singh 124 Akhgaon Sandesh Bhojpur 1160 Cultivation 0.018 Let-Sudama Singh Dhupan Singh 125 Akhgaon Sandesh Bhojpur 1161 Cultivation 0.105 Ram Prabandh Singh Devnandan Singh 126 Akhgaon Sandesh Bhojpur 1162 Cultivation 0.041 Shiv Pujan Singh Tapsaya Singh 127 Akhgaon Sandesh Bhojpur 1163 Cultivation 0.012 Ram Prabandh Singh Devnandan Singh 128 Akhgaon Sandesh Bhojpur 1320 Cultivation Rambachan Singh Janardan Singh 129 Akhgaon Sandesh Bhojpur 1330 Residential Ramesh Singh Aryun Singh 130 Akhgaon Sandesh Bhojpur 1337 0.043 Laxamina Singh Kuldeep Singh 131 Akhgaon Sandesh Bhojpur 1343 0.062 Lagandeep Singh Devi Singh 132 Akhgaon Sandesh Bhojpur 1347 Bhunshwer Singh Ram Chotaka 133 Akhgaon Sandesh Bhojpur 1352 Cultivation 0.142 Rambachan Singh Janardan Singh 134 Akhgaon Sandesh Bhojpur 1361 Cultivation Ramjesh Singh Shiv narayan Singh 135 Akhgaon Sandesh Bhojpur 1362 Prabhu Dayal Singh Lal Barander Singh 136 Akhgaon Sandesh Bhojpur 1363 Cultivation 0.065 Janardan Singh Ram Dattath Singh 137 Akhgaon Sandesh Bhojpur 1364 Cultivation Kapil Muni Pandey Barbar Pandey 138 Akhgaon Sandesh Bhojpur 1365 Cultivation Ram Ashra Pandey Puran Pandey 139 Akhgaon Sandesh Bhojpur 1367 Cultivation 0.147 Bhim Shah Kuldip Shah 140 Akhgaon Sandesh Bhojpur 1381 Jira Devi Khomaran Ram 141 Akhgaon Sandesh Bhojpur 1382 Cultivation 0.03 Chandrhckher Singh Ram Shrakh Singh 142 Akhgaon Sandesh Bhojpur 1385 Shvi Niwash Pandey Bal Kishun Pandey 143 Akhgaon Sandesh Bhojpur 1386 Cultivation 0.083 Sriram Pandey Ram Kishun Pandey 144 Akhgaon Sandesh Bhojpur 1387 Cultivation 0.108 Radha Singh Rang Lal Singh 145 Akhgaon Sandesh Bhojpur 1393 Cultivation Janardah Singh Ram Padrash Singh 146 Akhgaon Sandesh Bhojpur 1395 Cultivation 0.026 Moti Singh Ram Lakai Singh 147 Akhgaon Sandesh Bhojpur 1396 0.036 Jagut Narayan Lal Shri Sanker Bhagawon 148 Akhgaon Sandesh Bhojpur 1397 Cultivation Jadu Singh Ujageev Singh 149 Akhgaon Sandesh Bhojpur 1398 Cultivation Moti Singh Suraj Singh 150 Akhgaon Sandesh Bhojpur 1399 Cultivation Lakshmi Singh Kuldip Singh 151 Akhgaon Sandesh Bhojpur 1966 Cultivation 0.024 Math Dass Ram Lagan Dass 152 Akhgaon Sandesh Bhojpur 1967 Cultivation 0.048 Danpal Dass Ram Lochan Dass 153 Akhgaon Sandesh Bhojpur 1972 Cultivation 0.066 Ramesh Singh Radmohan Singh 154 Akhgaon Sandesh Bhojpur 1973 0.099 Ramjeet Singh Udhawal Singh 155 Akhgaon Sandesh Bhojpur 1975 Cultivation 0.099 Sadheshwer Singh Ram Raj Singh 156 Akhgaon Sandesh Bhojpur 1976 Cultivation 0.093 Sakun Yadav Rgubar yadav 157 Akhgaon Sandesh Bhojpur 2011 Cultivation Bijali Yadav Gharahu Yadav 158 Akhgaon Sandesh Bhojpur 2012 Cultivation 0.06 Smt Malida Devi Sukhdev Singh 159 Akhgaon Sandesh Bhojpur 2013 Cultivation 0.012 Banke Yadav Gaya Yadav 160 Akhgaon Sandesh Bhojpur 1435 Cultivation Gaya Singh Awadh Behari Singh 161 Akhgaon Sandesh Bhojpur 1434 Cultivation Ram Shekhar Singh Sablayak Singh 162 Akhgaon Sandesh Bhojpur 1433 Cultivation Dhan Laxmi Shankar Nath Lal 163 Akhgaon Sandesh Bhojpur 1410 Cultivation Behari Singh Birai Singh 164 Akhgaon Sandesh Bhojpur 1400 Cultivation Brijnandan Singh Mathura Singh 165 Akhgaon Sandesh Bhojpur 1441 Cultivation Dharbharan Dusadh Jadik Dusadh 166 Akhgaon Sandesh Bhojpur 1442 Cultivation Mudrika Dusadh Dharbharan Dusadh 167 Akhgaon Sandesh Bhojpur 1443 Cultivation Jagmohan Pandey Fagu Pandey 168 Akhgaon Sandesh Bhojpur 1444 Nagina Thakur Bulaki Thakur 169 Akhgaon Sandesh Bhojpur 1445 Cultivation Kapil Muni Pandey Babar Muni Pandey 170 Akhgaon Sandesh Bhojpur 1446 Cultivation Rang Nath Pandey Mahanand Pandey 171 Akhgaon Sandesh Bhojpur 1434 Cultivation Ram Shekhar Singh Sablayak Singh 172 Ahiman Chak Sandesh Bhojpur 1114 Cultivation Kadhar Singh Shiv Lal Singh 173 Ahiman Chak Sandesh Bhojpur 1113 Cultivation Kadhar Singh Shiv Lal Singh 174 Ahiman Chak Sandesh Bhojpur 1112 Cultivation Kadhar Singh Shiv Lal Singh 175 Ahiman Chak Sandesh Bhojpur 1111 Cultivation Khudaran Choudhary Baghwan Choudhary 176 Ahiman Chak Sandesh Bhojpur 1111 Cultivation Khudaran Choudhary Baghwan Choudhary 177 Ahiman Chak Sandesh Bhojpur 1110 Cultivation Khudaran Choudhary Baghwan Choudhary 178 Ahiman Chak Sandesh Bhojpur 1109 Cultivation Raman Choudhary Rakhi Choudhary 179 Ahiman Chak Sandesh Bhojpur 1108 Cultivation Raman Choudhary Rakhi Choudhary 180 Ahiman Chak Sandesh Bhojpur 378 Cultivation Basharophan Mallah Bulaki Mallah 181 Ahiman Chak Sandesh Bhojpur 386 Cultivation Ram Aashish Singh Harifa Singh 182 Ahiman Chak Sandesh Bhojpur 383 Cultivation Jagnath Ramrekha Singh 183 Ahiman Chak Sandesh Bhojpur 376 Cultivation Khadan Singh Juthan Singh 184 Ahiman Chak Sandesh Bhojpur 375 Cultivation Khadan Singh Juthan Singh 185 Ahiman Chak Sandesh Bhojpur 372 Cultivation Chandra Han Singh Alakha Singh 186 Ahiman Chak Sandesh Bhojpur 337 Cultivation Amika Nandan Ram Nandan Singh 187 Ahiman Chak Sandesh Bhojpur 335 Cultivation 0.01 Prashid Naryan Bhimanandan Ojha 188 Ahiman Chak Sandesh Bhojpur 327 Cultivation 0.02 Shudave Singh Jay Dev Singh 189 Ahiman Chak Sandesh Bhojpur 324 Cultivation Narahari Singh Aajibad Singh 190 Ahiman Chak Sandesh Bhojpur 321 Cultivation Narahari Singh Aajibad Singh 191 Ahiman Chak Sandesh Bhojpur 385 Cultivation Ram Aashish Singh Dawarika Singh 192 Ahiman Chak Sandesh Bhojpur 298 Cultivation 0.008 Dharamesha Kuwnar ShivBhare Singh 193 Ahiman Chak Sandesh Bhojpur 284 Cultivation Ram Aashish Singh Dawarika Singh 194 Ahiman Chak Sandesh Bhojpur 283 Cultivation Ram Dhine Singh Saghar Singh 195 Ahiman Chak Sandesh Bhojpur 281 Cultivation 0.015 M.Byano Kapil Dev Singh 196 Ahiman Chak Sandesh Bhojpur 276 Cultivation 0.02 M.Byano Kapil Dev Singh

2 Name of Affected Area Sl. No. Name of the Village Name of Block Plot No. Use of Land Name of the Owner Father’s Name District (in Acre) 197 Ahiman Chak Sandesh Bhojpur 276 Cultivation 0.02 Amika Nand Rama Nand Singh 198 Ahiman Chak Sandesh Bhojpur 268 Cultivation Khalifa Singh Chatur Singh 199 Ahiman Chak Sandesh Bhojpur 257 Cultivation Kedar Singh Shiv Lal Singh 200 Ahiman Chak Sandesh Bhojpur 251 Cultivation 0.031 Brij Bihari Singh Ram Shomo Singh 201 Ahiman Chak Sandesh Bhojpur 252 Cultivation NaRaian Singh Sita Ram Singh 202 Ahiman Chak Sandesh Bhojpur 237 Cultivation Ishawer Ram Dhayan Singh 203 Ahiman Chak Sandesh Bhojpur 389 Cultivation 0.027 Musmat Ramdai Kuwar Sahdev Singh 204 Ahiman Chak Sandesh Bhojpur 398 Cultivation Klapanath Singh Danuk Singh 205 Ahiman Chak Sandesh Bhojpur 394 Cultivation 0.012 Timal Singh Hari Seakh Singh 206 Ahiman Chak Sandesh Bhojpur 395 Cultivation 0.012 Timal Singh Hari Seakh Singh 207 Ahiman Chak Sandesh Bhojpur 400 Cultivation Ram Daya Kuwar Hadave 208 Ahiman Chak Sandesh Bhojpur 401 Cultivation Ranganath Singh Shavi Naryan Singh 209 Ahiman Chak Sandesh Bhojpur 402 Cultivation 0.021 M.Shama Kuwar Vayash Singh 210 Ahiman Chak Sandesh Bhojpur 404 Cultivation M.Shama Kuwar Vayash Singh 211 Ahiman Chak Sandesh Bhojpur 408 Cultivation 0.057 Devi Lal Singh Awatar Singh 212 Ahiman Chak Sandesh Bhojpur 409 Cultivation 0.018 Ram Layka Singh ram pota Singh 213 Ahiman Chak Sandesh Bhojpur 410 Cultivation 0.021 Tulashi Singh Ram Keval Singh 214 Ahiman Chak Sandesh Bhojpur 411 Cultivation 0.024 Amika Nand Singh 215 Ahiman Chak Sandesh Bhojpur 414 Cultivation 0.009 Jagadeep Singh Nandan Singh 216 Ahiman Chak Sandesh Bhojpur 416 Cultivation 0.026 Brij Bihari Singh Ram Soni Singh 217 Ahiman Chak Sandesh Bhojpur 417 Cultivation 0.026 Brij Bihari Singh Ram Soni Singh 218 Ahiman Chak Sandesh Bhojpur 415 Cultivation 0.009 Devi Lal Singh Ram Awater Singh 219 Ahiman Chak Sandesh Bhojpur 418 Cultivation 0.018 Rajeswer Singh Pachndra Singh 220 Ahiman Chak Sandesh Bhojpur 1675 Cultivation 0.015 Baleshama Singh Malakha Singh 221 Ahiman Chak Sandesh Bhojpur 928 Cultivation 0.043 Baleshama Singh Malakha Singh 222 Ahiman Chak Sandesh Bhojpur 931 Cultivation 0.031 Devnandan Singh Naydev Singh 223 Ahiman Chak Sandesh Bhojpur 932 Cultivation 0.016 Chandra Dev Singh Sandeep Singh 224 Ahiman Chak Sandesh Bhojpur 934 Cultivation 0.016 Jagadeep Singh Yadhunandan Singh 225 Ahiman Chak Sandesh Bhojpur 935 Cultivation 0.033 Amika Rama Nand Singh 226 Ahiman Chak Sandesh Bhojpur 970 Cultivation 0.017 Ram Shubhag Singh Khan Singh 227 Khem Karanpur Sandesh Bhojpur 474 Cultivation Raman Ojha Ram raj Ojha 228 Khem Karanpur Sandesh Bhojpur 476 Cultivation Raman Ojha Ram raj Ojha 229 Khem Karanpur Sandesh Bhojpur 473 Cultivation Bhavishan Singh Sravan Singh 230 Khem Karanpur Sandesh Bhojpur 472 Cultivation Bhavishan Singh Sravan Singh 231 Khem Karanpur Sandesh Bhojpur 470 Cultivation Sachidananda Singh Kalpnath Singh 232 Khem Karanpur Sandesh Bhojpur 471 Cultivation Ram Kishun Ojha Panpat Ojha 233 Khem Karanpur Sandesh Bhojpur 459 Cultivation Jange Badhur Ojha Chaturabhu Ojha 234 Khem Karanpur Sandesh Bhojpur 466 Cultivation Jange Badhur Ojha Chaturabhu Ojha 235 Khem Karanpur Sandesh Bhojpur 465 Cultivation Ram Kishun Ojha Rama Nand Ojha 236 Khem Karanpur Sandesh Bhojpur 464 Cultivation Jang Badhur Ojha Chaturabhuj Ojha 237 Khem Karanpur Sandesh Bhojpur 468 Cultivation Indrashan Ojha Ramanta Nand Ojha 238 Khem Karanpur Sandesh Bhojpur 489 Cultivation Kaiser Hind 239 Khem Karanpur Sandesh Bhojpur 475 Cultivation Sidhanath Ojha Rambhujha Ojha 240 Khem Karanpur Sandesh Bhojpur 477 Cultivation Sanker Dayal Ojha Ramadhar Ojha 241 Khem Karanpur Sandesh Bhojpur 458 Cultivation Not Available 242 Khem Karanpur Sandesh Bhojpur 459 Cultivation Not Available 243 Khem Karanpur Sandesh Bhojpur 460 Cultivation Not Available 244 Khem Karanpur Sandesh Bhojpur 437 Cultivation Not Available 245 Khem Karanpur Sandesh Bhojpur 434 Cultivation Not Available 246 Khem Karanpur Sandesh Bhojpur 435 Cultivation Not Available 247 Khem Karanpur Sandesh Bhojpur 432 Cultivation Not Available 248 Khem Karanpur Sandesh Bhojpur 431 Cultivation Not Available 249 Khem Karanpur Sandesh Bhojpur 430 Cultivation Not Available 250 Khem Karanpur Sandesh Bhojpur 429 Cultivation Not Available 251 Khem Karanpur Sandesh Bhojpur 427 Cultivation Not Available 252 Khem Karanpur Sandesh Bhojpur 420 Cultivation Not Available 253 Khem Karanpur Sandesh Bhojpur 419 Cultivation Not Available 254 Khem Karanpur Sandesh Bhojpur 478 Cultivation Ram Keshun Ojha Rama Nand Ojha 255 Baga Sandesh Bhojpur 829 Cultivation Sita Ram Singh Gudari Singh 256 Baga Sandesh Bhojpur 830 Cultivation Siri Singh Ramkhelavan Singh 257 Baga Sandesh Bhojpur 832 Cultivation Dukchal Singh Eishvari Singh 258 Baga Sandesh Bhojpur 838 Cultivation Sivbinay Singh Bhanda Singh 259 Baga Sandesh Bhojpur 839 Cultivation Sita Ram Singh Gudari Singh 260 Baga Sandesh Bhojpur 825 Cultivation Ram bachan Singh Sarju Singh 261 Baga Sandesh Bhojpur 826 Cultivation Ram mandil Singh Samuander Singh 262 Baga Sandesh Bhojpur 840 Cultivation Virodha Singh Dudeshvar Singh 263 Baga Sandesh Bhojpur 841 Cultivation Sivbinay Singh Bhanda Singh 264 Baga Sandesh Bhojpur 842 Cultivation Sivbinay Singh Bhanda Singh 265 Baga Sandesh Bhojpur 820 Cultivation Bhagwan Dayal Singh Jhagaru Singh 266 Baga Sandesh Bhojpur 823 Cultivation Kalpu Singh Sadanand Singh 267 Baga Sandesh Bhojpur 824 Cultivation Prasidh NaRaian Ojha Sadanand Ojha 268 Baga Sandesh Bhojpur 815 Cultivation Sivbinay Singh Bhanda Singh 269 Baga Sandesh Bhojpur 816 Cultivation Sivbinay Singh Bhanda Singh 270 Baga Sandesh Bhojpur 817 Cultivation Sivbinay Singh Bhanda Singh 271 Baga Sandesh Bhojpur 818 Cultivation Sivbalak Singh Sakal Singh 272 Baga Sandesh Bhojpur 811 Cultivation Navlakh Singh Babhu Singh 273 Baga Sandesh Bhojpur 812 Cultivation RupnaRaian Singh Shrinath Singh 274 Baga Sandesh Bhojpur 784 Cultivation Paras Singh Srinath Singh 275 Baga Sandesh Bhojpur 785 _ Upadhya Singh Rahdev Singh 276 Baga Sandesh Bhojpur 1258 Cultivation Bihar Government Bihar Government 277 Baga Sandesh Bhojpur 1263 Cultivation RupnaRaian Singh Babhu Singh 278 Baga Sandesh Bhojpur 1265 Cultivation Narwadeshwar Mahadevji 279 Baga Sandesh Bhojpur 1267 Cultivation Paras Singh Shrinath Singh 280 Baga Sandesh Bhojpur 1268 Cultivation Paras Singh Shrinath Singh 281 Baga Sandesh Bhojpur 1270 Cultivation Sadhusaran Singh Bashavana Singh 282 Baga Sandesh Bhojpur 1271 Cultivation Sadhusaran Singh Bashavana Singh 283 Baga Sandesh Bhojpur 609 Cultivation Dukbal Singh Eishvari Singh 284 Baga Sandesh Bhojpur 610 Cultivation Dukhchal Singh Ishwari Singh 285 Baga Sandesh Bhojpur 568 Cultivation Brajkishore Das Narayan Das 286 Baga Sandesh Bhojpur 569 Cultivation Awadhes Yana Rai 287 Baga Sandesh Bhojpur 567 Cultivation Sadhusaran Singh Basavan Singh 288 Baga Sandesh Bhojpur 564 Cultivation Gayan Mahto Ramjanam Singh 289 Baga Sandesh Bhojpur 563 Cultivation Gayan Mahto Ramjanam Singh 290 Baga Sandesh Bhojpur 559 Cultivation Mahant Lalit Kishore Duarika Dash 291 Baga Sandesh Bhojpur 418 Cultivation 0.009 Not Available 292 Baga Sandesh Bhojpur 417 Cultivation 0.001 Not Available 293 Baga Sandesh Bhojpur 781 Cultivation 0.012 Not Available 294 Baga Sandesh Bhojpur 782 Cultivation 0.003 Not Available 295 Baga Sandesh Bhojpur 779 Cultivation 0.035 Not Available

3 Name of Affected Area Sl. No. Name of the Village Name of Block Plot No. Use of Land Name of the Owner Father’s Name District (in Acre) 296 Baga Sandesh Bhojpur 778 Cultivation 0.027 Not Available 297 Baga Sandesh Bhojpur 777 Cultivation 0.021 Not Available 298 Baga Sandesh Bhojpur 765 Cultivation 0.031 Not Available 299 Baga Sandesh Bhojpur 763 Cultivation 0.035 Not Available 300 Baga Sandesh Bhojpur 760 Cultivation 0.038 Not Available 301 Baga Sandesh Bhojpur 751 Cultivation 0.006 Not Available 302 Baga Sandesh Bhojpur 757 Cultivation 0.023 Not Available 303 Baga Sandesh Bhojpur 756 Cultivation 0.012 Not Available 304 Baga Sandesh Bhojpur 755 Cultivation 0.010 Not Available 305 Baga Sandesh Bhojpur 668 Cultivation 0.006 Not Available 306 Baga Sandesh Bhojpur 670 Cultivation 0.009 Not Available 307 Baga Sandesh Bhojpur 671 Cultivation 0.009 Not Available 308 Baga Sandesh Bhojpur 662 Cultivation 0.022 Not Available 309 Baga Sandesh Bhojpur 660 Cultivation 0.008 Not Available 310 Baga Sandesh Bhojpur 660 Cultivation 0.008 Not Available 311 Baga Sandesh Bhojpur 656 Cultivation 0.005 Not Available 312 Baga Sandesh Bhojpur 657 Cultivation 0.039 Not Available 313 Baga Sandesh Bhojpur 658 Cultivation 0.005 Not Available 314 Baga Sandesh Bhojpur 655 Cultivation 0.025 Not Available 315 Baga Sandesh Bhojpur A Cultivation 0.008 Not Available 316 Baga Sandesh Bhojpur 617 Cultivation 0.053 Not Available 317 Baga Sandesh Bhojpur 619 Cultivation 0.002 Not Available 318 Baga Sandesh Bhojpur B Cultivation 0.028 Not Available 319 Baga Sandesh Bhojpur 613 Cultivation 0.031 Not Available 320 Baga Sandesh Bhojpur 612 Cultivation 0.031 Not Available 321 Baga Sandesh Bhojpur 560 Cultivation Sadhu Saran Singh Basavan Singh 322 Andhari Sahar Bhojpur 2083 Cultivation 0.007 Janha Kunwar Muvari Rai 323 Andhari Sahar Bhojpur 2077 Cultivation 0.015 Raghnand Rai Dashhar Rai 324 Andhari Sahar Bhojpur 2083 Cultivation 0.007 Parmeshwar Rai Savab Rai 325 Andhari Sahar Bhojpur 2085 Cultivation 0.003 Shri Bhagwan Rai Nawal Rai 326 Andhari Sahar Bhojpur 2084 Cultivation 0.003 Sital Rai Nabab Rai 327 Andhari Sahar Bhojpur 1943 Cultivation Bag Rangi Rai Ram Nath Rai 328 Andhari Sahar Bhojpur 1467 Cultivation Bag Rangi Rai Ram Nath Rai 329 Andhari Sahar Bhojpur 1303 Cultivation Bag Rangi Rai Ram Nath Rai 330 Andhari Sahar Bhojpur 1458 Cultivation chandar Deep Rai Nahak Rai 331 Andhari Sahar Bhojpur 1459 Cultivation Baleshwar Rai Beni Rai 332 Andhari Sahar Bhojpur 1347 Cultivation Chandar Dep Rai Nanhak Rai 333 Andhari Sahar Bhojpur 1465 Cultivation Baleshwar Rai Beni Rai 334 Andhari Sahar Bhojpur 1454 Cultivation Randhari Rai Ram Aiatar Rai 335 Andhari Sahar Bhojpur 1436 Cultivation 0.044 Alakh Narayan Rai Bhagi Rai 336 Andhari Sahar Bhojpur 1437 Cultivation 0.043 Alakh Narayan Rai Bhagi Rai 337 Andhari Sahar Bhojpur 1435 Cultivation 0.079 Alakh Narayan Rai Bhagi Rai 338 Andhari Sahar Bhojpur 2064 Cultivation 0.04 Kedar Rai Rameswer Rai 339 Andhari Sahar Bhojpur 2065 Cultivation 0.018 Kedar Rai Rameswer Rai 340 Andhari Sahar Bhojpur 2066 Cultivation 0.014 Kedar Rai Rameswer Rai 341 Andhari Sahar Bhojpur 1403 Cultivation Kedar Rai Rameswer Rai 342 Andhari Sahar Bhojpur 761 Cultivation 0.04 Sukhdev Rai Makhan Rai 343 Andhari Sahar Bhojpur 1500 Cultivation Ashlok Rai Laljee Rai 344 Andhari Sahar Bhojpur 756 Cultivation 0.064 Ramyanm Rai Aaskrn Rai 345 Andhari Sahar Bhojpur 758 Cultivation 0.041 Triveni Rai Khomari Rai 346 Andhari Sahar Bhojpur 9749 Cultivation Raja Rai Khrlawer Rai 347 Andhari Sahar Bhojpur 741 Cultivation Dhenuk Rai Lalbhukhan Rai 348 Andhari Sahar Bhojpur 710 Cultivation 0.053 Dhenuk Rai Lalbhukhan Rai 349 Andhari Sahar Bhojpur 769 Cultivation Parama Rai Mohan Rai 350 Andhari Sahar Bhojpur 704 Cultivation 0.066 Parama Rai Mohan Rai 351 Andhari Sahar Bhojpur 764 Cultivation 0.083 Parama Rai Mohan Rai 352 Andhari Sahar Bhojpur 750 Cultivation 0.062 Parama Rai Mohan Rai 353 Andhari Sahar Bhojpur 748 Cultivation 0.027 Bhaguat Parwat Rai 354 Andhari Sahar Bhojpur 708 Cultivation 0.008 Raja Pathak Sukdev Pathak 355 Andhari Sahar Bhojpur 707 Cultivation Raja Pathak Sukdev Pathak 356 Andhari Sahar Bhojpur 706 Cultivation Yamuna Pathak Vidhya Pathak 357 Andhari Sahar Bhojpur 702 Cultivation 0.093 Yamuna Pathak Vidhya Pathak 358 Andhari Sahar Bhojpur 705 Cultivation Meghnath Rai Nithuni Rai 359 Andhari Sahar Bhojpur 712 Cultivation 0.056 Surydev Rai Ram Khelawan Rai 360 Andhari Sahar Bhojpur 203 Cultivation Judagi Pathak Vasudev Pathak 361 Andhari Sahar Bhojpur 1365 Cultivation Ram Dhyan Rai Man Rai 362 Andhari Sahar Bhojpur 1502 Cultivation Ram Dhyan Rai Man Rai 363 Andhari Sahar Bhojpur 763 Cultivation Ram Dhyan Rai Man Rai 364 Andhari Sahar Bhojpur 760 Cultivation Ram Dhyan Rai Man Rai 365 Andhari Sahar Bhojpur 759 Cultivation Ram Dhyan Rai Man Rai 366 Andhari Sahar Bhojpur 1357 Cultivation Ram Adhar Rai Ripa Rai 367 Andhari Sahar Bhojpur 2076 Cultivation 0.016 Ram Adhar Rai Ripa Rai 368 Andhari Sahar Bhojpur 2070 Cultivation 0.018 Ram Adhar Rai Ripa Rai 369 Andhari Sahar Bhojpur 1304 Cultivation Hargovind Rai Faudar Rai 370 Andhari Sahar Bhojpur 1358 Cultivation Manlayak Rai Jivdhar Rai 371 Andhari Sahar Bhojpur 1354 Cultivation Manlayak Rai Jivdhar Rai 372 Andhari Sahar Bhojpur 2069 Cultivation 0.013 Munka Kuwar Salik Rai 373 Andhari Sahar Bhojpur 2067 Cultivation Pulish Mahto Raja Mahto 374 Andhari Sahar Bhojpur 1942 Cultivation M. Ram Vyasi Dei Jagdish Naryan Sinha 375 Andhari Sahar Bhojpur 1348 Cultivation Dharmnath Rai Sudama Rai 376 Andhari Sahar Bhojpur 1925 Cultivation 0.007 Not Available 377 Andhari Sahar Bhojpur 1926 Cultivation 0.114 Not Available 378 Andhari Sahar Bhojpur 1927 Cultivation 0.026 Not Available 379 Andhari Sahar Bhojpur 1928 Cultivation 0.003 Not Available 380 Andhari Sahar Bhojpur 1929 Cultivation 0.074 Not Available 381 Andhari Sahar Bhojpur 1930 Cultivation 0.027 Not Available 382 Andhari Sahar Bhojpur 1932 Cultivation 0.141 Not Available 383 Andhari Sahar Bhojpur 1933 Cultivation 0.018 Not Available 384 Andhari Sahar Bhojpur 1934 Cultivation 0.104 Not Available 385 Andhari Sahar Bhojpur 1935 Cultivation 0.017 Not Available 386 Andhari Sahar Bhojpur 1936 Cultivation 0.037 Not Available 387 Andhari Sahar Bhojpur 1937 Cultivation 0.041 Not Available 388 Andhari Sahar Bhojpur 1938 Cultivation 0.049 Not Available 389 Andhari Sahar Bhojpur 2056 Cultivation 0.417 Not Available 390 Andhari Sahar Bhojpur 2057 Cultivation 0.153 Not Available 391 Andhari Sahar Bhojpur 2090 Cultivation 0.000 Not Available 392 Andhari Sahar Bhojpur 2089 Cultivation 0.003 Not Available 393 Andhari Sahar Bhojpur 2088 Cultivation 0.017 Not Available 394 Andhari Sahar Bhojpur 2085 Cultivation 0.003 Not Available

4 Name of Affected Area Sl. No. Name of the Village Name of Block Plot No. Use of Land Name of the Owner Father’s Name District (in Acre) 395 Andhari Sahar Bhojpur 2066 Cultivation 0.014 Kedar Rai Rameswer Rai 396 Andhari Sahar Bhojpur 2069 Cultivation 0.013 Not Available 397 Andhari Sahar Bhojpur 2066 Cultivation 0.014 Not Available 398 Andhari Sahar Bhojpur 2065 Cultivation 0.018 Not Available 399 Andhari Sahar Bhojpur 2064 Cultivation 0.040 Not Available 400 Andhari Sahar Bhojpur 2063 Cultivation 0.051 Not Available 401 Andhari Sahar Bhojpur 2042 Cultivation 0.011 Not Available 402 Andhari Sahar Bhojpur 2062 Cultivation 0.033 Not Available 403 Andhari Sahar Bhojpur 2061 Cultivation 0.033 Not Available 404 Andhari Sahar Bhojpur 2060 Cultivation 0.032 Not Available

405 Andhari Sahar Bhojpur 2059 Cultivation 0.030 Not Available 406 Baruhi Sahar Bhojpur 3505 Cultivation Tarkeshwer Rai Kachuya Rai 407 Baruhi Sahar Bhojpur 3506 Cultivation Dapan Yadav Hira Yadav 408 Baruhi Sahar Bhojpur 3507 Cultivation Anjor Singh Kashol Singh 409 Baruhi Sahar Bhojpur 3510 Cultivation Rajender Pd Nathuni Pd 410 Baruhi Sahar Bhojpur 4069 Cultivation Bavanatha Rai Palatan Rai 411 Baruhi Sahar Bhojpur 4068 Cultivation Bavanatha Rai Palatan Rai 412 Baruhi Sahar Bhojpur 4028 Cultivation Rambali Ramlachan 413 Baruhi Sahar Bhojpur 2967 Cultivation Kedarnath Pandey Shivparshan pandey 414 Baruhi Sahar Bhojpur 3876 Cultivation Badrinath Mishra Gopinatha Mishra 415 Baruhi Sahar Bhojpur 3804 Cultivation Mangnu Singh Ram Kishun Singh 416 Baruhi Sahar Bhojpur 3870 Cultivation Kedarnath Pandey Shivparshan pandey 417 Baruhi Sahar Bhojpur 3869 Cultivation Badrinath Mishra Gopinatha Mishra 418 Baruhi Sahar Bhojpur 3770 Cultivation Radhika Kuwnar Nagandra Pathak 419 Baruhi Sahar Bhojpur 3661 Cultivation Hira Lal Pathak Paltu Pathak 420 Baruhi Sahar Bhojpur 3768 Cultivation Jatan Singh Vigha Singh 421 Baruhi Sahar Bhojpur 3748 Cultivation Dodha Rai Kenadar Rai 422 Baruhi Sahar Bhojpur 3510 Cultivation Rajender Pd Nathuni Pd 423 Baruhi Sahar Bhojpur 3663 Cultivation Hira Lal Pathak Paltu Pathak 424 Baruhi Sahar Bhojpur 3664 Cultivation Hira Lal Pathak Paltu Pathak 425 Baruhi Sahar Bhojpur 3662 Cultivation Hira Lal Pathak Paltu Pathak 426 Baruhi Sahar Bhojpur 3661 Cultivation Hira Lal Pathak Paltu Pathak 427 Baruhi Sahar Bhojpur 3666 Cultivation Yadunandan Rai Bashudav Rai 428 Baruhi Sahar Bhojpur 3658 Cultivation Yadunandan Rai Bashudav Rai 429 Baruhi Sahar Bhojpur 3653 Cultivation Meshwer Pd Mishra Raj Kishor Mishra 430 Baruhi Sahar Bhojpur 3666 Cultivation Ram Bishun Hari Kushin Rai 431 Baruhi Sahar Bhojpur 3669 Cultivation Giwath Rai Aklu Rai 432 Baruhi Sahar Bhojpur 3670 Cultivation Ragunath Rai Balvadra Rai 433 Baruhi Sahar Bhojpur 3671 Cultivation Payar Dusadh Bizamohan 434 Baruhi Sahar Bhojpur 3672 Cultivation Ramaashara Ahir Ram Lagan Ahir 435 Baruhi Sahar Bhojpur 3673 Cultivation Ram Biharo Rai Mahadava Rai 436 Baruhi Sahar Bhojpur 3676 Cultivation Ram Bishun Hari Kushin Rai 437 Baruhi Sahar Bhojpur 3584 Cultivation Bavanatha Rai Palatan Rai 438 Baruhi Sahar Bhojpur 3583 Cultivation Bavanatha Rai Palatan Rai 439 Baruhi Sahar Bhojpur 3582 Cultivation Kunga Bihari Rai Surya Natha Rai 440 Baruhi Sahar Bhojpur 3581 Cultivation Bavanatha Rai Palatan Rai 441 Baruhi Sahar Bhojpur 4164 Cultivation Kashala Ku Singh Jang Bahadura Singh 442 Baruhi Sahar Bhojpur 4138 Cultivation Kashala Ku Singh Jang Bahadura Singh 443 Baruhi Sahar Bhojpur 4137 Cultivation Bavanatha Rai Palatan Rai 444 Baruhi Sahar Bhojpur 4047 Cultivation Bavanatha Rai Palatan Rai 445 Baruhi Sahar Bhojpur 4068 Cultivation Kashala Ku Singh Jang Bahadura Singh 446 Baruhi Sahar Bhojpur 4029 Cultivation Madan Rai Dukha Davan Rai 447 Baruhi Sahar Bhojpur 3806 Cultivation Aanaki Rai Shyam Sundar Rai 448 Banjaria Sahar Bhojpur 1557 Cultivation Sri lilavati devi Murli dhar Singh 449 Banjaria Sahar Bhojpur 2127 Cultivation Murli dhar Singh Jung badhur Singh 450 Banjaria Sahar Bhojpur 1523 Cultivation 0.011 kashi yadav Devi dayal yadav 451 Banjaria Sahar Bhojpur 2124 Cultivation Doma yadav Parikha yadav 452 Banjaria Sahar Bhojpur 1555 Cultivation Sri lilavati devi Murli dhar Singh 453 Banjaria Sahar Bhojpur 1559 Cultivation Subadar Singh Mahavir Singh 454 Banjaria Sahar Bhojpur 1589 Cultivation Shivparasan Singh Ram Dyala Panday 455 Banjaria Sahar Bhojpur 1585 Cultivation Ramivashor panday Madshavar panday 456 Banjaria Sahar Bhojpur 1588 Cultivation Ram Ikbal Singh Rupan Singh 457 Banjaria Sahar Bhojpur 1562 Cultivation Natunhi dushad Dhan Dushadh 458 Banjaria Sahar Bhojpur 1563 Cultivation Natunhi dushad Dhan Dushadh 459 Banjaria Sahar Bhojpur 1567 Cultivation Dudnath Singh Ram janam Singh 460 Banjaria Sahar Bhojpur 1611 Cultivation 0.006 vish nath ram Thakur Ram 461 Banjaria Sahar Bhojpur 1628 Cultivation 0.014 Govrdhan Singh Rup Naraian Singh 462 Banjaria Sahar Bhojpur 1636 Cultivation Nagishar Singh Chaturi Singh 463 Banjaria Sahar Bhojpur 1637 Cultivation Nagishar Singh Chaturi Singh 464 Banjaria Sahar Bhojpur 1638 Cultivation 0.024 Ramushar panday Ram jatan panday 465 Banjaria Sahar Bhojpur 1630 Cultivation Prabha nand Singh Briksha Singh 466 Peur Chak Sahar Bhojpur 5 Cultivation 0.005 Shaikh Nihal Aarif Hussain 467 Peur Chak Sahar Bhojpur 6 Cultivation 0.003 Virudhin Kakhu 468 Peur Chak Sahar Bhojpur 14 Cultivation 0.002 Shaikh Sikandar Shaikh Fajul Ajjush 469 Peur Chak Sahar Bhojpur 13 Cultivation Shaikh Mohhamad Dhakar Chadi ali 470 Peur Chak Sahar Bhojpur 23 Cultivation 0.004 Raian ali Veer ali 471 Peur Chak Sahar Bhojpur 24 Cultivation 0.011 Shaikh Musthn Shaikh abdul satar 472 Peur Chak Sahar Bhojpur 33 Cultivation 0.009 Sabhia Khatun Luckman haddar 473 Peur Chak Sahar Bhojpur 35 Cultivation 0.013 Bibi Sajidha khatun Syed Ahamad 474 Peur Chak Sahar Bhojpur 43 Cultivation 0.015 Md Numan Shaikh Praful Ahamad 475 Peur Chak Sahar Bhojpur 44 Cultivation 0.019 Md Numan Seakh praful ahamad 476 Peur Chak Sahar Bhojpur 50 Cultivation 0.01 Bibhi sadira khatun Hakim faijjul khan 477 Peur Chak Sahar Bhojpur 54 Cultivation 0.011 Shaikh Abrar Said Ehsaan 478 Peur Chak Sahar Bhojpur 56 Cultivation 0.024 Said Ishrar Said Ehsaan 479 Peur Chak Sahar Bhojpur 57 Cultivation 0.021 Saidh Anwer Amadh Asshah 480 Peur Chak Sahar Bhojpur 58 Cultivation Bibi Shair Khatun Ahamad Kasshi 481 Peur Chak Sahar Bhojpur 59 Cultivation 0.007 Md.Aaubh Kahh Parful Kahh 482 Peur Chak Sahar Bhojpur 60 Cultivation 0.008 SuRai Dev Rai Rajunadan Rai 483 Peur Chak Sahar Bhojpur 64 Cultivation 0.007 Seakh Valhi Alli Amadh Abdul Hakim 484 Peur Chak Sahar Bhojpur 65 Cultivation 0.008 Bibi Uadhav Abdul Karim 485 Peur Chak Sahar Bhojpur 76 Cultivation 0.018 Shaikh Russi Ahmed Ahamad Rash id 486 Peur Chak Sahar Bhojpur 77 Cultivation 0.015 Shaikh Sikandar Shaikh Abdu aajida 487 Peur Chak Sahar Bhojpur 84 Cultivation Shaikh Sikandar Shaikh Abdu aajida 488 Peur Chak Sahar Bhojpur 83 Cultivation Shaikh Hashim Seakh 489 Peur Chak Sahar Bhojpur 87 Cultivation Shaikh Abdul Satar Shaikh Ali Eabbar 490 Peur Chak Sahar Bhojpur 54 Cultivation 0.011 Shaikh Abrar Said Ehsaan 491 Peur Chak Sahar Bhojpur 277 Cultivation 0.019 Seakh Md. Hanana Shaikh Abdul Jani 492 Peur Chak Sahar Bhojpur 275 Cultivation Nishar Amadh

5 Name of Affected Area Sl. No. Name of the Village Name of Block Plot No. Use of Land Name of the Owner Father’s Name District (in Acre) 493 Peur Chak Sahar Bhojpur 276 Cultivation Shaikh Hashim Shaikh Abdul 494 Peur Chak Sahar Bhojpur 266 Cultivation 0.008 Bibi Uadhav Abdul Karim 495 Peur Chak Sahar Bhojpur 265 Cultivation 0.008 Banshi Lala Yaha Shada 496 Peur Chak Sahar Bhojpur 251 Cultivation Bibi Uadhav Abdul karim 497 Peur Chak Sahar Bhojpur 250 Cultivation Seakh amadha Seakh Md.Aarin 498 Peur Chak Sahar Bhojpur 249 Cultivation Shaikh Mohhamad Suleman Shaikh Hidayat Alli 499 Peur Chak Sahar Bhojpur 248 Cultivation 0.011 Munni Lal Ramdas 500 Peur Chak Sahar Bhojpur 247 Cultivation Shaikh Suleman Shaikh Hidayat Alli 501 Peur Chak Sahar Bhojpur 246 Cultivation Mohammad Ibisya Hekharu 502 Peur Chak Sahar Bhojpur 242 Cultivation 0.01 Jairupi UdavPassi 503 Peur Chak Sahar Bhojpur 241 Cultivation Mohammad Bibi Sajida Said Ahmad 504 Peur Chak Sahar Bhojpur 263 Cultivation Shaikh Halim Shaikh Kashi Alli 505 Peur Chak Sahar Bhojpur 164 Cultivation 0.026 Said Abrar Said Ahasan 506 Peur Chak Sahar Bhojpur 165 Cultivation 0.025 Said Anwar Ahsan Ahmed 507 Peur Chak Sahar Bhojpur 318 Cultivation Mohammad Ishak Md. Israel 508 Peur Chak Sahar Bhojpur 319 Cultivation Shaikh Numan Shaikh Rahman 509 Peur Chak Sahar Bhojpur 178 Cultivation 0.007 Shaikh Tahir Shaikh Ahamad Asin 510 Peur Chak Sahar Bhojpur 181 Cultivation 0.009 Vashi Lal Mah Sah 511 Peur Chak Sahar Bhojpur 249 Cultivation Shaikh Mohhamad Suleman Shaikh Hidayat Alli 512 Peur Chak Sahar Bhojpur 183 Cultivation Bibi Adal Abdul Karim 513 Peur Chak Sahar Bhojpur 184 Cultivation Sukh Dev Mahuar Satal Mahuar 514 Peur Chak Sahar Bhojpur 185 Cultivation Shaikh Md. Muslim Alam Alli 515 Peur Chak Sahar Bhojpur 227 Cultivation 0.016 Shaikh Md Suleman Hidayat Alli 516 Peur Chak Sahar Bhojpur 209 Cultivation Triloki Sah Bharat Sah 517 Peur Chak Sahar Bhojpur 211 Cultivation 0.01 Bibi Shayara Khatun Md. Kasim 518 Peur Chak Sahar Bhojpur 213 Cultivation 0.008 Md. Numan Shaikh Abdul Rahaman 519 Peur Chak Sahar Bhojpur 215 Cultivation 0.011 Md. Ajmer Wali Ahmad 520 Peur Chak Sahar Bhojpur 214 Cultivation 0.007 Shaikh Md Suleman Hidayat Alli 521 Peur Chak Sahar Bhojpur 227 Cultivation 0.016 Shaikh Md Suleman Hidayat Alli 522 Peur Chak Sahar Bhojpur 238 Cultivation Nir Ahmad Hasan Mir Jahur 523 Peur Chak Sahar Bhojpur 237 Cultivation 0.014 Shaikh Md. Wali Ilta Hussain 524 Sahar Sahar Bhojpur 558 Cultivation 0.035 Ganga Prasad Moijee Lal 525 Sahar Sahar Bhojpur 557 Cultivation 0.017 Ganga Prasad Moijee Lal 526 Sahar Sahar Bhojpur 556 Cultivation 0.017 Shivpujan Brahamdutt Pathak 527 Sahar Sahar Bhojpur 554 Cultivation 0.01 Hori Lal Pathak Nakul Pathak 528 Sahar Sahar Bhojpur 553 Cultivation 0.008 Naresh Pathak Naryan Pathak 529 Sahar Sahar Bhojpur 552 Cultivation 0.018 Ganga Prasad Moijee Lal 530 Sahar Sahar Bhojpur 1346 Ganga Prasad Moijee Lal 531 Sahar Sahar Bhojpur 544 Cultivation 0.019 Ganga Prasad Mojee Lal 532 Sahar Sahar Bhojpur 543 Cultivation 0.01 Ganga Prasad Mojee Lal 533 Sahar Sahar Bhojpur 530 Cultivation 0.008 Bibi Rajdial Abdul Rahman 534 Sahar Sahar Bhojpur 523 Cultivation Bibi Rajdial Abdul Rahman 535 Sahar Sahar Bhojpur 528 Cultivation 0.024 Bibi Rajdial Abdul Rahman 536 Sahar Sahar Bhojpur 527 Cultivation 0.01 Shodari Brikha Choudary 537 Sahar Sahar Bhojpur 500 Cultivation Manik Chandra Sha Dular Chand Sha 538 Sahar Sahar Bhojpur 501 Cultivation 0.012 Brikha Choudhary Bhagirath Choudhary 539 Sahar Sahar Bhojpur 502 Cultivation 0.011 Vyash Choudhary Babu Lal Choudary 540 Sahar Sahar Bhojpur 474 Cultivation Mabihar Sah Dalai Sah 541 Sahar Sahar Bhojpur 472 Cultivation Lalu Kanu Ram Sharan Kanu 542 Sahar Sahar Bhojpur 471 Cultivation Sathoki Malaha Bhagan Malaha 543 Sahar Sahar Bhojpur 470 Cultivation Ram Pd. Kumhar Gayaba 544 Sahar Sahar Bhojpur 466 Cultivation Moti Lal Dushad Janki Dushad 545 Sahar Sahar Bhojpur 467 Cultivation 0.014 Moti Lal Dushad Janki Dushad 546 Sahar Sahar Bhojpur 303 Cultivation Abdul Azij Md.Sarif 547 Sahar Sahar Bhojpur 302 Cultivation Bibi mana Seakh Kudrat Kariam 548 Sahar Sahar Bhojpur 242 Cultivation 0.055 Bibi Nautan Shaikh Abdul 549 Sahar Sahar Bhojpur 241 Cultivation Dival khoya Dhesh Lal 550 Sahar Sahar Bhojpur 121 Cultivation 0.017 Madan Pd Vishwanath Pd 551 Sahar Sahar Bhojpur 122 Cultivation 0.025 Madan Pd Vishwanath Pd 552 Sahar Sahar Bhojpur 123 Cultivation Mora Md. Shuyor Mora Md. Ishamial 553 Sahar Sahar Bhojpur 125 Cultivation Mora Md. Shuyor Mora Md. Ishamial 554 Sahar Sahar Bhojpur 134 Cultivation Shaikh Kudarat Seakh Samashur Din 555 Sahar Sahar Bhojpur 135 Cultivation Shaikh Kudarat Seakh Samashur Din 556 Abgilla Sahar Bhojpur 377 Cultivation Kokel Sha Sanker Sha 557 Abgilla Sahar Bhojpur 378 Cultivation Paramjota Dev Sita Ram Rai 558 Abgilla Sahar Bhojpur 843 Cultivation Naresh Pathak NaRaian Pathak 559 Abgilla Sahar Bhojpur 842 Cultivation Shaikh Hayat Hushan Kudarat Alali 560 Abgilla Sahar Bhojpur 830 Cultivation Ram Mashawer Singh Kamala Singh 561 Abgilla Sahar Bhojpur 832 Cultivation Md.Halim Sayada napurual Hak 562 Abgilla Sahar Bhojpur 840 Cultivation Kudarat Miya Aojir Miya 563 Abgilla Sahar Bhojpur 833 Cultivation Sadaya Jadurul Hashan Sadaya Shahu Hashan 564 Abgilla Sahar Bhojpur 829 Cultivation Iadrash Mahama Deep 565 Abgilla Sahar Bhojpur 826 Cultivation Mangar Ahir Ram Dahen 566 Abgilla Sahar Bhojpur 824 Cultivation Ram Mashawer Singh Kamala Singh 567 Abgilla Sahar Bhojpur 439 Cultivation Bashatan Gafur 568 Abgilla Sahar Bhojpur 779 Cultivation Mashjid Miya Mahayar Ali 569 Abgilla Sahar Bhojpur 770 Cultivation Man Kashara Kuwanr Subadar Rai 570 Abgilla Sahar Bhojpur 769 Cultivation Kapil Dev Singh Nand Gopal Singh 571 Abgilla Sahar Bhojpur 768 Cultivation Kapil Dev Singh Nand Gopal Singh 572 Abgilla Sahar Bhojpur 705 Cultivation Mankeshwar Kuwnar Subadar Rai 573 Abgilla Sahar Bhojpur 704 Cultivation Chapo Devi Fathabadhur Singh 574 Abgilla Sahar Bhojpur 703 Cultivation Rajendra Rai Ram Sawaruap Rai 575 Abgilla Sahar Bhojpur 702 Cultivation M.Jutani Aatar Pashi 576 Abgilla Sahar Bhojpur 640 Cultivation Moti Rajeya Halak Khari Passhi 577 Abgilla Sahar Bhojpur 636 Cultivation Moti Rajeya Halak Khari Passhi 578 Abgilla Sahar Bhojpur 635 Cultivation Kapil Dev Singh Nand Gopal 579 Abgilla Sahar Bhojpur 637 Cultivation Yamuna Rai Kripa Rai 580 Abgilla Sahar Bhojpur 518 Cultivation Rajak Abdulla 581 Peur Sahar Bhojpur 47 Cultivation Visawanath Rai Vishanandan Rai 582 Peur Sahar Bhojpur 55 Cultivation Jashi Amadha Seakh Mohandam 583 Peur Sahar Bhojpur 56 Cultivation Visawanath Rai Vishanandan Rai 584 Peur Sahar Bhojpur 66 Cultivation Sakhaldeep Singh Nithun Singh 585 Peur Sahar Bhojpur 67 Cultivation Abdal Mashijad Abdul Karim 586 Peur Sahar Bhojpur 68 Cultivation Bibi Shajada Sayada Yashan 587 Peur Sahar Bhojpur 84 Cultivation Indardav Rai Ram Sabak Rai 588 Peur Sahar Bhojpur 85 Cultivation Md.Takke Chaddi Ali 589 Peur Sahar Bhojpur 86 Cultivation Seakh Mashijad Abdul Karim 590 Peur Sahar Bhojpur 87 Cultivation Md. Ajem Md.Eakaram 591 Peur Sahar Bhojpur 93 Cultivation Md.Ajej Fherashan Hushan

6 Name of Affected Area Sl. No. Name of the Village Name of Block Plot No. Use of Land Name of the Owner Father’s Name District (in Acre) 592 Peur Sahar Bhojpur 88 Cultivation Abdal Hanana Abdul Gane 593 Peur Sahar Bhojpur 85 Cultivation Md.Takke Chaddi Ali 594 Peur Sahar Bhojpur 100 Cultivation Chandarika Rai Gaga Rai 595 Peur Sahar Bhojpur 116 Cultivation Md.Aarefa Jamera Udhan 596 Peur Sahar Bhojpur 994 Cultivation Seakh Sulaman Hidhayat Ali 597 Peur Sahar Bhojpur 118 Cultivation Md. Numan Abdul Rahman 598 Peur Sahar Bhojpur 119 Cultivation Md. Ajej Md.Eakaram 599 Peur Sahar Bhojpur 120 Cultivation Md.Ajej Md.Eakaram 600 Peur Sahar Bhojpur 130 Cultivation Shaikh Sulaman Hidhayat Ali 601 Peur Sahar Bhojpur 126 Cultivation Ram Kishun Pandit Charetar Pandit 602 Peur Sahar Bhojpur 122 Cultivation Shaikh kashi Amadh Shaikh Rashid Ali 603 Peur Sahar Bhojpur 124 Cultivation Md.Kashem Ahamad Aaful 604 Peur Sahar Bhojpur 264 Cultivation Abdul Hanan Abdul Gane 605 Peur Sahar Bhojpur 319 Cultivation Shaikh Sulaman Hidhayat Ali 606 Peur Sahar Bhojpur 318 Cultivation Sayyad Anawar Md.Ehsaan Ahmad 607 Peur Sahar Bhojpur 316 Cultivation Abdul Hanan Abdual Karim 608 Peur Sahar Bhojpur 315 Cultivation Abdual Hanan Abdual Karim 609 Peur Sahar Bhojpur 305 Cultivation Bibi Rukeya Aashik Md. 610 Peur Sahar Bhojpur 302 Cultivation Sayyad Anawar Md.Ehsaan Ahmad 611 Peur Sahar Bhojpur 301 Cultivation Sayyad Anawar Md.Ehsaan Ahmad 612 Peur Sahar Bhojpur 304 Cultivation Md.Wali Lathaf Hushan 613 Peur Sahar Bhojpur 346 Cultivation Bibi Jashan Kali Maudeen 614 Peur Sahar Bhojpur 554 Cultivation 0.01 Md.Aarifa Amir Udhin 615 Peur Sahar Bhojpur 355 Cultivation Abdual Hashan Abdual Hayat 616 Peur Sahar Bhojpur 356 Cultivation Md.Mustaka Abdul Sattar 617 Peur Sahar Bhojpur 357 Cultivation Shaikh M.Ajiba Shaikh Ali 618 Kharao chaturbhuj Sahar Bhojpur 1583 Cultivation Baaldev Maour Ramdash Maour 619 Kharao chaturbhuj Sahar Bhojpur 2799 Cultivation 0.003 Hari Bansh Singh Babulal 620 Kharao chaturbhuj Sahar Bhojpur 2700 Cultivation Baleshvar Maour Jagdeep Maour 621 Kharao chaturbhuj Sahar Bhojpur 1344 Cultivation 0.044 Sukhadave Sarju 622 Kharao chaturbhuj Sahar Bhojpur 1345 Cultivation 0.03 Mathura Mauhar Mohan Mauhar 623 Kharao chaturbhuj Sahar Bhojpur 1346 Cultivation 0.03 Bassmuni Mauhar Mukhalal Mauhar 624 Kharao chaturbhuj Sahar Bhojpur 1347 Cultivation Kariman Mauhar Bridha Mauhar 625 Kharao chaturbhuj Sahar Bhojpur 1360 Cultivation 0.05 Mukhan Mauhar Ram Sahaek 626 Kharao chaturbhuj Sahar Bhojpur 1361 Cultivation 0.042 Janki Mauhar Yadunandn Mauhar 627 Kharao chaturbhuj Sahar Bhojpur 1362 Cultivation 0.101 Mathura Mauhar Mohan Mauhar 628 Kharao chaturbhuj Sahar Bhojpur 1363 Cultivation Kariman Mauhar Bridha Mauhar 629 Kharao chaturbhuj Sahar Bhojpur 1391 Cultivation 0.139 Dukhan Mauhar Ram Sahaek 630 Kharao chaturbhuj Sahar Bhojpur 1392 Cultivation 0.103 Janki Mauhar Yadunandn Mauhar 631 Kharao chaturbhuj Sahar Bhojpur 1418 Cultivation Ramlakhan Dubha Amar deep Dubha 632 Kharao chaturbhuj Sahar Bhojpur 1419 Cultivation 0.07 Raghubihar Matho Sadhi Matho 633 Kharao chaturbhuj Sahar Bhojpur 1420 Cultivation 0.063 Basgit Sha Jageshwer Sha 634 Kharao chaturbhuj Sahar Bhojpur 1483 Cultivation Shivnandan Rashdhari 635 Kharao chaturbhuj Sahar Bhojpur 1484 Cultivation Dukhan Mauhar Ram Sahaek 636 Kharao chaturbhuj Sahar Bhojpur 1485 Cultivation Bassdave Mauhar Ramharan Mauhar 637 Kharao chaturbhuj Sahar Bhojpur 1812 Cultivation 0.067 Hari Bansh Chatu 638 Kharao chaturbhuj Sahar Bhojpur 1815 Cultivation Ram Kishuna Singh Batish Singh 639 Kharao chaturbhuj Sahar Bhojpur 1813 Cultivation 0.032 Ram Kishuna Singh Batish Singh 640 Kharao chaturbhuj Sahar Bhojpur 1819 Cultivation 0.038 Janki Mauhar Yadunandn Mauhar 641 Kharao chaturbhuj Sahar Bhojpur 1820 Cultivation Hari Bansh Chatu 642 Kharao chaturbhuj Sahar Bhojpur 1805 Cultivation Amar Deep Mauhar Suraj Mauhar 643 Kharao chaturbhuj Sahar Bhojpur 1901 Cultivation Ram Deep Devnandan 644 Kharao chaturbhuj Sahar Bhojpur 1902 Cultivation Ramjanam Bashudav Rai 645 Kharao chaturbhuj Sahar Bhojpur 1904 Cultivation Kaliesh Mauhar Parash Mauhar 646 Kharao chaturbhuj Sahar Bhojpur 1903 Cultivation 0.021 Ramjanam Bashudav Rai 647 Kharao chaturbhuj Sahar Bhojpur 1944 Cultivation Yamuna Mauhar Baghwan Sahay Mauhar 648 Kharao chaturbhuj Sahar Bhojpur 1945 Cultivation Ram Deep Devnandan 649 Kharao chaturbhuj Sahar Bhojpur 1946 Cultivation Ramlakhan Dubha Haribansh 650 Kharao chaturbhuj Sahar Bhojpur 1947 Cultivation Mathura Mauhar Mohan Mauhar 651 Kharao chaturbhuj Sahar Bhojpur 1948 Cultivation Ramgadan Matho Khalawan Matho 652 Kharao chaturbhuj Sahar Bhojpur 1949 Cultivation Shivgadan Singhj Ramdahine Singh 653 Kharao chaturbhuj Sahar Bhojpur 1950 Cultivation Shivshay Matho Ram Naryan Matho 654 Kharao chaturbhuj Sahar Bhojpur 1953 Cultivation Nahgina Mauihar Nihora Mauhar 655 Kharao chaturbhuj Sahar Bhojpur 2005 Cultivation Ram ikbal Singh Raghunandan Mauhar 656 Kharao chaturbhuj Sahar Bhojpur 2556 Cultivation ShivDutt Basgit 657 Kharao chaturbhuj Sahar Bhojpur 2557 Cultivation Yugati Matho Madho Tiwari 658 Kharao chaturbhuj Sahar Bhojpur 2561 Cultivation Ramlakhan Dubha Chandeep Dubha 659 Kharao chaturbhuj Sahar Bhojpur 2589 Cultivation Jagdeep Maour Ramjanam Maour 660 Kharao chaturbhuj Sahar Bhojpur 2581 Cultivation Rameshvar Doman 661 Kharao chaturbhuj Sahar Bhojpur 1583 Cultivation Baaldev Maour Ramdash Maour 662 Kharao chaturbhuj Sahar Bhojpur 2799 Cultivation 0.003 Hari Bansh Singh Babulal 663 Kharao chaturbhuj Sahar Bhojpur 2700 Cultivation Baleshvar Maour Jagdeep Maour 664 Lodipur Sahar Bhojpur 142 Cultivation Jhagaru Mahto Phuran Mahto 665 Lodipur Sahar Bhojpur 231 Cultivation Jhagaru Mahto Phuran Mahto 666 Lodipur Sahar Bhojpur 229 Cultivation Baijnath Giri JagnaRaian Giri 667 Lodipur Sahar Bhojpur 227 Cultivation Jagdish Chandra Giri Rambricha Giri 668 Lodipur Sahar Bhojpur 121 Cultivation Ramjee Lakshmi Chand 669 Lodipur Sahar Bhojpur 122 Cultivation Ramjee Lakshmi Chand 670 Lodipur Sahar Bhojpur 124 Cultivation Ramjee Lakshmi Chand 671 Lodipur Sahar Bhojpur 129 Cultivation Ramjee Lakshmi Chand 672 Lodipur Sahar Bhojpur 118 Cultivation Ramjee Lakshmi Chand 673 Lodipur Sahar Bhojpur 121 Cultivation Ramjee Lakshmi Chand 674 Lodipur Sahar Bhojpur 116 Cultivation Damodar Rai Madho Rai 675 Lodipur Sahar Bhojpur 384 Cultivation Chandadeep Rai Visheshr Rai 676 Lodipur Sahar Bhojpur 386 Cultivation Ram naresh Singh Dudheswar Singh 677 Lodipur Sahar Bhojpur 388 Cultivation Ramgati Mallah Khaderan Mallah 678 Lodipur Sahar Bhojpur 104 Cultivation Nifikir Singh Dhuri Singh 679 Lodipur Sahar Bhojpur 385 Cultivation Chandeep Rai Visheshr Rai 680 Lodipur Sahar Bhojpur 101 Cultivation Guru Saran Mallah Krisna Singh 681 Lodipur Sahar Bhojpur 103 Cultivation Nifikir Singh Dhuri Singh 682 Lodipur Sahar Bhojpur 115 Cultivation Nitikir Singh Dhuri Singh 683 Lodipur Sahar Bhojpur 387 Cultivation Ram Asish malah Sayar Malah 684 Lodipur Sahar Bhojpur 230 Cultivation Ramdash Rai Belash Rai 685 Lodipur Sahar Bhojpur 102 Cultivation Shiv Sharn Malah Dhamn Malah 686 Lodipur Sahar Bhojpur 228 Cultivation Daroga Rai Guru Sahy Rai 687 Dhauri Sahar Bhojpur 205 Cultivation Mahabhir Chodary Shakhe Malalaha 688 Dhauri Sahar Bhojpur 206 Cultivation 0.047 Gana Malalaha Shivasaran Malalaha 689 Dhauri Sahar Bhojpur 203 Cultivation Nasheba Singh Ram Rakha Singh 690 Dhauri Sahar Bhojpur 208 Cultivation 0.037 Nasheba Singh Ram Rakha Singh

7 Name of Affected Area Sl. No. Name of the Village Name of Block Plot No. Use of Land Name of the Owner Father’s Name District (in Acre) 691 Dhauri Sahar Bhojpur 209 Cultivation Nasheba Singh Ram Rakha Singh 692 Dhauri Sahar Bhojpur 210 Cultivation 0.069 Pramesawer Singh Nathuni Singh 693 Dhauri Sahar Bhojpur 214 Cultivation Shuba Rai Anak Rai 694 Dhauri Sahar Bhojpur 233 Cultivation Daroga Singh Ramrit Singh 695 Dhauri Sahar Bhojpur 235 Cultivation Ram Aashis Singh Suary Ku Singh 696 Dhauri Sahar Bhojpur 234 Cultivation Shav Singh Sampate Singh 697 Dhauri Sahar Bhojpur 235 Cultivation Ram Aashis Singh Suary Ku Singh 698 Dhauri Sahar Bhojpur 236 Cultivation Shipahi Singh Kapil Dev Singh 699 Dhauri Sahar Bhojpur 237 Cultivation Chabela Singh Ram Dutt Singh 700 Dhauri Sahar Bhojpur 238 Cultivation Kapil Dev Singh Ram Dutt Singh 701 Dhauri Sahar Bhojpur 239 Cultivation Anurag Singh Rajdave Singh 702 Dhauri Sahar Bhojpur 240 Cultivation Kapil Dev Singh Balachad Singh 703 Dhauri Sahar Bhojpur 241 Cultivation Daroga Singh Ramkrit Singh 704 Dhauri Sahar Bhojpur 242 Cultivation Anurag Singh Raj Dev Singh 705 Banshi Dihri Sahar Bhojpur 608 Cultivation Chandrika Rai Jaga Rai 706 Banshi Dihri Sahar Bhojpur 609 Cultivation Devi Rai Ram Devi Rai 707 Banshi Dihri Sahar Bhojpur 610 Cultivation Shumant Rai Haricharan Rai 708 Banshi Dihri Sahar Bhojpur 1140 Cultivation Shumant Ram Haricharan Rai 709 Banshi Dihri Sahar Bhojpur 624 Cultivation Alakha Naraian Rai Shrinath Rai 710 Banshi Dihri Sahar Bhojpur 625 Cultivation Alakha Naraian Rai Shrinath Rai 711 Banshi Dihri Sahar Bhojpur 799 Cultivation Shumant Rai Haricharan Rai 712 Banshi Dihri Sahar Bhojpur 800 Cultivation Gambhir Rai Raghunandan Rai 713 Banshi Dihri Sahar Bhojpur 801 Cultivation Gambhir Rai Raghunandan Rai 714 Banshi Dihri Sahar Bhojpur 785 Cultivation Keshwer Ahir Ramlakhan Ahir 715 Banshi Dihri Sahar Bhojpur 784 Cultivation Vira Ahir Manger Ahir 716 Banshi Dihri Sahar Bhojpur 783 Cultivation Mangalwasho Devi Jatu Ram 717 Banshi Dihri Sahar Bhojpur 782 Cultivation Mahabir Pashi NaRaian Pashi 718 Banshi Dihri Sahar Bhojpur 781 Cultivation Dinanath Ram Arjun Rai 719 Banshi Dihri Sahar Bhojpur 780 Cultivation Alakhanaraian Shrinath Rai 720 Banshi Dihri Sahar Bhojpur 779 Cultivation Rajender Ram Shadave Ram 721 Banshi Dihri Sahar Bhojpur 765 Cultivation 0.008 Janakdahari Rai Chandrika Rai 722 Banshi Dihri Sahar Bhojpur 763 Cultivation 0.03 Devi Rai Ram dani Rai 723 Banshi Dihri Sahar Bhojpur 784 Cultivation Vira Ahir Manger Ahir 724 Banshi Dihri Sahar Bhojpur 747 Cultivation 0.036 Janakdahari Rai Chandrika Rai 725 Banshi Dihri Sahar Bhojpur 746 Cultivation 0.042 Rajdave Rai Baghanath Rai 726 Banshi Dihri Sahar Bhojpur 744 Cultivation 0.05 Rajdave Rai Baghanath Rai 727 Banshi Dihri Sahar Bhojpur 729 Cultivation 0.033 Dinanath Ram Arjun Ram 728 Banshi Dihri Sahar Bhojpur 728 Cultivation Alakhanaraian Shrinath Ram 729 Banshi Dihri Sahar Bhojpur 727 Ramchandra Rai Sahdev Rai 730 Banshi Dihri Sahar Bhojpur 726 Cultivation 0.025 Chandrika Ram Jaga Ram 731 Banshi Dihri Sahar Bhojpur 723 Cultivation 0.028 Shumant Rai Haricharan Rai 732 Nonaur Agiaon Bhojpur 205 Cultivation 0.009 Jai Govind Singh Pradeep Singh 733 Nonaur Agiaon Bhojpur 207 Cultivation Pradeep Singh Jai Gopal Ray 734 Nonaur Agiaon Bhojpur 213 Cultivation 0.046 Adya Prasad Ray 735 Nonaur Agiaon Bhojpur 238 Cultivation Narayan Singh Jagdish Singh 736 Nonaur Agiaon Bhojpur 241 Cultivation 0.001 RamDhari Singh Parikha Singh 737 Nonaur Agiaon Bhojpur 245 Cultivation 0.001 Ramesh Singh Devi Singh 738 Nonaur Agiaon Bhojpur 246 Cultivation 0.041 Ramesh Singh Devi Singh 739 Nonaur Agiaon Bhojpur 247 Cultivation 0.042 Ramprasad Singh 740 Nonaur Agiaon Bhojpur 337 Cultivation 0.1 Narayan Singh Jagdish Singh 741 Nonaur Agiaon Bhojpur 338 Cultivation 0.033 Anjani Kr. Singh Harivansh Singh 742 Nonaur Agiaon Bhojpur 340 Cultivation 0.107 ChandraDev Singh Umeshwar Narayan Singh 743 Nonaur Agiaon Bhojpur 343 Cultivation 0.064 Shyam Sunder Hari Kishun Singh 744 Nonaur Agiaon Bhojpur 344 Cultivation 0.002 Shyam Sunder Hari Kishun Singh 745 Nonaur Agiaon Bhojpur 345 Cultivation Shyam Sunder Hari Kishun Singh 746 Nonaur Agiaon Bhojpur 346 Cultivation 0.048 Ram Singhasan Singh Deep Singh 747 Nonaur Agiaon Bhojpur 347 Cultivation 0.056 Ram Singhasan Singh Deep Singh 748 Nonaur Agiaon Bhojpur 406 Cultivation DukhHaran Singh Charitra Singh 749 Nonaur Agiaon Bhojpur 407 Cultivation 0.022 Shyam Sundar HariKishun Singh 750 Nonaur Agiaon Bhojpur 408 Cultivation Dudheshwar Singh Ramdin Singh 751 Nonaur Agiaon Bhojpur 409 Cultivation Bam Singh Chandrika Singh 752 Nonaur Agiaon Bhojpur 410 Cultivation 0.017 Ram Prasad Singh Inar Singh 753 Nonaur Agiaon Bhojpur 411 Cultivation 0.037 Ram Prasad Singh Inar Singh 754 Nonaur Agiaon Bhojpur 412 Cultivation 0.029 Prasad Singh Tenjri Singh 755 Nonaur Agiaon Bhojpur 413 Cultivation 0.004 Ram Prasar Singh L Ram Lochan Singh 756 Nonaur Agiaon Bhojpur 414 Cultivation 0.071 L Ram Dhari Singh L Parikha Singh 757 Nonaur Agiaon Bhojpur 416 Cultivation 0.023 Rajender Singh Surender Singh 758 Nonaur Agiaon Bhojpur 418 Cultivation Megha Singh Guman Singh 759 Nonaur Agiaon Bhojpur 420 Cultivation 0.037 Ram Prasad Singh Inar Singh 760 Nonaur Agiaon Bhojpur 440 Cultivation 0.045 Ram Dhari Singh Pavikha Singh 761 Nonaur Agiaon Bhojpur 342 Cultivation 0.045 Dudheshwar Singh 762 Nonaur Agiaon Bhojpur 421 Cultivation 0.059 Ram Prasad Singh Inar Singh 763 Nonaur Agiaon Bhojpur 443 Cultivation 0.035 Paras Singh Ram Lochan Singh 764 Nonaur Agiaon Bhojpur 444 Cultivation 0.04 Nagina Singh Niranjan Singh 765 Nonaur Agiaon Bhojpur 445 Cultivation 0.048 Prasid Singh Tengri Singh 766 Nonaur Agiaon Bhojpur 446 Cultivation 0.037 Prasid Singh Tengri Singh 767 Nonaur Agiaon Bhojpur 447 Cultivation 0.05 Raja Ram Singh Satrudhan Singh 768 Nonaur Agiaon Bhojpur 448 Cultivation 0.053 Dukh Haran Singh Lcharitra Singh 769 Nonaur Agiaon Bhojpur 449 Cultivation 0.034 Ram Sigashan Singh Deepa Singh 770 Nonaur Agiaon Bhojpur 450 Cultivation Ram Sigashan Singh Deepa Singh 771 Nonaur Agiaon Bhojpur 965 Cultivation Prdeep Singh Kaushal Kr.Singh 772 Nonaur Agiaon Bhojpur 968 Cultivation Sachitanand Singh Triyogi Rai 773 Nonaur Agiaon Bhojpur 968 Cultivation Rouf Miya Ishbal Miya 774 Nonaur Agiaon Bhojpur 969 Cultivation 0.067 Samsudin Miya Sckhe Miya 775 Nonaur Agiaon Bhojpur 967 Cultivation Raj Kumar Singh Ram Janam Singh 776 Nonaur Agiaon Bhojpur 975 0.039 Musmat Balkeshwari 777 Nonaur Agiaon Bhojpur 976 Cultivation Trivhun Singh Baoul Singh 778 Nonaur Agiaon Bhojpur 977 Rajdev Singh 779 Nonaur Agiaon Bhojpur 1018 Cultivation Mashwer Singh Satyanaryan Singh 780 Nonaur Agiaon Bhojpur 1019 Cultivation 0.003 BamBhola Yadav Ram Pravash Yadav 781 Nonaur Agiaon Bhojpur 1020 Cultivation 0.002 Yamuna Sah Hajevi Sah 782 Nonaur Agiaon Bhojpur 1021 Cultivation 0.005 Nathui Sah Ramkishun Sah 783 Nonaur Agiaon Bhojpur 1121 Cultivation Rajendar Pd Rai Dinesh Singh 784 Nonaur Agiaon Bhojpur 1248 Cultivation Rajendar Singh Surat Singh 785 Nonaur Agiaon Bhojpur 1541 Cultivation Dakhuran Singh Charitra Singh 786 Nonaur Agiaon Bhojpur 1126 Cultivation 0.024 Shiv Dave Rai Jaganaryan Rai 787 Nonaur Agiaon Bhojpur 444 Cultivation 0.04 Jadhu Singh Nagina Singh 788 Nonaur Agiaon Bhojpur 1238 Cultivation Rajandhra Singh Chandan Singh 789 Nonaur Agiaon Bhojpur 1130 Cultivation 0.031 Triyogi Singh Sachitanand Singh

8 Name of Affected Area Sl. No. Name of the Village Name of Block Plot No. Use of Land Name of the Owner Father’s Name District (in Acre) 790 Nonaur Agiaon Bhojpur 1247 Ramdev Singh 791 Nonaur Agiaon Bhojpur 960 Cultivation 0.029 Ranjeet Singh RamDayal Rai 792 Nonaur Agiaon Bhojpur 1176 Cultivation Raj Kishor Singh Phaujdov Singh 793 Nonaur Agiaon Bhojpur 1054 Cultivation 0.006 Chhahal Pasawar Beni Pasawar 794 Nonaur Agiaon Bhojpur 1160 Cultivation Liswar Dutt Singh Jit Narayan Singh 795 Nonaur Agiaon Bhojpur 1044 Cultivation 0.003 Gariba Sha Ramrekha Sah 796 Nonaur Agiaon Bhojpur 1240 Cultivation Ram Balak Singh Shvi Nath Singh 797 Nonaur Agiaon Bhojpur 970 Cultivation 0.06 Chamsuedin Miya Kudartali Miya 798 Nonaur Agiaon Bhojpur 971 Cultivation 0.04 Chedi Miya Jangli Miya 799 Nonaur Agiaon Bhojpur 998 Cultivation 0.04 Neyernat Miya Golayayt Miya 800 Nonaur Agiaon Bhojpur 1055 Cultivation 0.004 Goclhan Pasawan Beni Pasawan 801 Nonaur Agiaon Bhojpur 1057 Cultivation 0.008 Goclhan Pasawan Beni Paswan 802 Bramapur-Mehdora Agiaon Bhojpur 2964 Cultivation Sh. Ram Kaval Rai Sh. Moti Rai 803 Bramapur-Mehdora Agiaon Bhojpur 2967 Cultivation Sh. Shivbaran Rai Sh. Algu Rai 804 Bramapur-Mehdora Agiaon Bhojpur 2952 Cultivation Sh. Kuldip Rai Sh. Maha Dev Rai 805 Bramapur-Mehdora Agiaon Bhojpur 2951 Cultivation 0.03 Sh. Surya Nath Rai Sh. Bokhari Rai 806 Bramapur-Mehdora Agiaon Bhojpur 2950 Cultivation 0.001 Surya Nath Rai Bokhari Rai 807 Bramapur-Mehdora Agiaon Bhojpur 2944 Cultivation Sh. Ram Hayan Rai Devki Rai 808 Bramapur-Mehdora Agiaon Bhojpur 2943 Cultivation 0.034 Sh. Lutai Rai Sh. Deep NaRaian Rai 809 Bramapur-Mehdora Agiaon Bhojpur 2941 Cultivation 0.121 Sh. Raja Rai Sh. Shiv Gulam Rai 810 Bramapur-Mehdora Agiaon Bhojpur 2940 Cultivation 0.086 Sh. Bhuneshwar Rai Sh. Kameshwar Rai 811 Bramapur-Mehdora Agiaon Bhojpur 2939 Cultivation Sh. Raja Rai Sh. Shiv Gulam Rai 812 Bramapur-Mehdora Agiaon Bhojpur 2938 Cultivation Sh. Raja Rai Sh. Shiv Gulam Rai 813 Bramapur-Mehdora Agiaon Bhojpur 2937 Cultivation Sh. Rambriksh Rai Sh. Brahm Rai 814 Bramapur-Mehdora Agiaon Bhojpur 2936 Cultivation 0.018 Sh. Bhuneshwar Rai Sh. Kameshwar Rai 815 Bramapur-Mehdora Agiaon Bhojpur 2935 Cultivation 0.016 Sh. Basawan Rai Sh. Tribhuvan Rai 816 Bramapur-Mehdora Agiaon Bhojpur 2934 Cultivation 0.012 Sh. Rambriksh Rai Sh. Brahm Rai 817 Bramapur-Mehdora Agiaon Bhojpur 2933 Cultivation Sh. Krit Rai Sh. Radhey Rai 818 Bramapur-Mehdora Agiaon Bhojpur 2929 Cultivation 0.039 Sh. Lutai Rai Sh. Deep NaRaian Rai 819 Bramapur-Mehdora Agiaon Bhojpur 2930 Cultivation 0.068 Sh. Ram Pujan Mistry Sh. Bhanu Mistry 820 Bramapur-Mehdora Agiaon Bhojpur 2925 Cultivation Sh. Bhuneshwar Rai Sh. Kameshwar Rai 821 Bramapur-Mehdora Agiaon Bhojpur 2924 Cultivation Sh. Prahlad Rai Sh. Shivgurucharan Rai 822 Bramapur-Mehdora Agiaon Bhojpur 2923 Cultivation Sh. Basawan Rai Sh. Tribhuvan Rai 823 Bramapur-Mehdora Agiaon Bhojpur 2922 Cultivation Sh. Prahlad Rai Sh. Shivgurucharan Rai 824 Bramapur-Mehdora Agiaon Bhojpur 2921 Cultivation Sh. Rambriksh Rai Sh. Brahm Rai 825 Bramapur-Mehdora Agiaon Bhojpur 2816 Cultivation Sh. Yogi Shah Sh. Dasai Saha 826 Bramapur-Mehdora Agiaon Bhojpur 2819 Cultivation Sh. Ram Pujan Mistry Sh. Bhanu Mistry 827 Bramapur-Mehdora Agiaon Bhojpur 2818 Cultivation Sh. Ram Pujan Mistry Sh. Bhanu Mistry 828 Bramapur-Mehdora Agiaon Bhojpur 2810 Cultivation 0.018 Sh. Janak Mistry Sh. Puni Mistry 829 Bramapur-Mehdora Agiaon Bhojpur 2811 Cultivation Sh. Ram Pujan Mistry Sh. Bhanu Mistry 830 Bramapur-Mehdora Agiaon Bhojpur 2809 Cultivation Sh. Chavi Nath Rai Sh. Bihari Rai 831 Bramapur-Mehdora Agiaon Bhojpur 2808 Cultivation 0.038 Sh. Ram Pujan Mistry Sh. Bhanu Mistry 832 Bramapur-Mehdora Agiaon Bhojpur 2807 Cultivation Sh. Gaya Mistry Sh. Naknam Mistry 833 Bramapur-Mehdora Agiaon Bhojpur 2787 Cultivation 0.019 Sh. Kuldip Rai Sh. Maha Dev Rai 834 Bramapur-Mehdora Agiaon Bhojpur 2786 Cultivation 0.027 Sh. Vimal Rai Sh. Mahavir Rai 835 Bramapur-Mehdora Agiaon Bhojpur 2785 Cultivation Sh. Ram Kaval Rai Sh. Moti Rai 836 Bramapur-Mehdora Agiaon Bhojpur 2784 Cultivation Sh. Kuldip Rai Sh. Maha Dev Rai 837 Bramapur-Mehdora Agiaon Bhojpur 2783 Cultivation Sh. Chavi Nath Rai Sh. Bihari Rai 838 Bramapur-Mehdora Agiaon Bhojpur 2819 Cultivation Sh. Ram Pujan Mistry Sh. Bhanu Mistry 839 Bramapur-Mehdora Agiaon Bhojpur 2818 Cultivation Sh. Ram Pujan Mistry Sh. Bhanu Mistry 840 Bramapur-Mehdora Agiaon Bhojpur 2791 Cultivation 0.011 Sh. Chenuk Dhari Rai Sh. Harihar Rai 841 Bramapur-Mehdora Agiaon Bhojpur 2792 Cultivation Sh. Kuldip Rai Sh. Maha Dev Rai 842 Bramapur-Mehdora Agiaon Bhojpur 2793 Cultivation Sh. Kuldip Rai Sh. Maha Dev Rai 843 Bramapur-Mehdora Agiaon Bhojpur 2777 Cultivation 0.075 Sh. Muneshwar Rai Sh. Lalan Rai 844 Bramapur-Mehdora Agiaon Bhojpur 2776 Cultivation Sh. Butai Rai Sh. Chandrik Rai 845 Bramapur-Mehdora Agiaon Bhojpur 2775 Cultivation Sh. Butai Rai Sh. Chandrik Rai 846 Bramapur-Mehdora Agiaon Bhojpur 2778 Cultivation 0.036 Sh. Muneshwar Rai Sh. Lalan Rai 847 Bramapur-Mehdora Agiaon Bhojpur 2779 Cultivation Sh. Basropan Rai Sh. Chanhu Rai 848 Bramapur-Mehdora Agiaon Bhojpur 2765 Cultivation Sh. Sant Belas Rai Sh. Kunj Bihari Rai 849 Bramapur-Mehdora Agiaon Bhojpur 2758 Cultivation 0.109 Sh. Sant Belas Rai Sh. Kunj Bihari Rai 850 Bramapur-Mehdora Agiaon Bhojpur 2757 Cultivation Sh. Sant Belas Rai Sh. Kunj Bihari Rai 851 Bramapur-Mehdora Agiaon Bhojpur 2754 Cultivation Sh. Baschand Saha Sh. Mahngu Saha 852 Bramapur-Mehdora Agiaon Bhojpur 2738 Cultivation Sh. Suti Nath Rai Sh. Khobhari Rai 853 Bramapur-Mehdora Agiaon Bhojpur 2739 Cultivation Sh. Surya Nath Rai Sh. Khobhari Rai 854 Bramapur-Mehdora Agiaon Bhojpur 2446 Cultivation Sh. Jay Govind Rai Sh. Ram Prit Rai 855 Bramapur-Mehdora Agiaon Bhojpur 2445 Cultivation Sh. Ram Govind Tiwary Sh. Chadhu Tiwary 856 Bramapur-Mehdora Agiaon Bhojpur 2444 Cultivation Sh. Krit Rai Sh. Radhey Rai 857 Bramapur-Mehdora Agiaon Bhojpur 2443 Cultivation Sh. Sakhi Rai Mallah Sh. Sukun Mallah 858 Bramapur-Mehdora Agiaon Bhojpur 2442 Cultivation Sh. Ram Govind Tiwary Sh. Khobhari Tiwary 859 Bramapur-Mehdora Agiaon Bhojpur 2441 Cultivation Sh. Ram Govind Tiwary Sh. Khobhari Tiwary 860 Bramapur-Mehdora Agiaon Bhojpur 2440 Cultivation Sh. Ram Lalan Tiwary Sh. Ram Avtar Tiwary 861 Bramapur-Mehdora Agiaon Bhojpur 2429 Cultivation Sh. Dhenuk Dhari Rai Sh. Harihar Rai 862 Bramapur-Mehdora Agiaon Bhojpur 2477 Cultivation Sh. Dhenuk Dhari Rai Sh. Harihar Rai 863 Bramapur-Mehdora Agiaon Bhojpur 2478 Cultivation 0.158 Sh Shivbaran Rai Sh. Aklu Rai 864 Bramapur-Mehdora Agiaon Bhojpur 2479 Cultivation Sh. Laldev Rai Sh. RamDhari Rai 865 Bramapur-Mehdora Agiaon Bhojpur 2480 Cultivation Sh. Shivbaran Rai Sh. Aklu Rai 866 Bramapur-Mehdora Agiaon Bhojpur 2474 Cultivation Sh. Dhenuk Dhari Rai Sh. Harihar Rai 867 Bramapur-Mehdora Agiaon Bhojpur 2473 Cultivation Sh. Kuldip Rai Sh. Mahadev Rai 868 Bramapur-Mehdora Agiaon Bhojpur 2472 Cultivation Sh. Butai Rai Sh. DipnaRaian Rai 869 Bramapur-Mehdora Agiaon Bhojpur 2471 Cultivation Sh. Ramkrit Rai Sh. Jay Dayal Rai 870 Bramapur-Mehdora Agiaon Bhojpur 2470 Cultivation 0.015 Sh. Shivbaran Rai Sh. Aklu Rai 871 Bramapur-Mehdora Agiaon Bhojpur 1874 Cultivation 0.053 Sh. Bhuneshwar Rai Sh. Ram Ayoudhya Rai 872 Bramapur-Mehdora Agiaon Bhojpur 1873 Cultivation Musmat Asturna Kunwar Sh. Keso Rai 873 Bramapur-Mehdora Agiaon Bhojpur 1875 Cultivation Sh. Ram Tapasya Rai Sh. Brijnandan Rai 874 Bramapur-Mehdora Agiaon Bhojpur 1853 Cultivation Sh. Khanap Rai Sh. Girwar Rai 875 Bramapur-Mehdora Agiaon Bhojpur 1852 Cultivation Sh. Raj Dayal Rai Sh. Bani Rai 876 Bramapur-Mehdora Agiaon Bhojpur 2738 Cultivation Sh. Suti Nath Rai Sh. Khobhari Rai 877 Bramapur-Mehdora Agiaon Bhojpur 2739 Cultivation Sh. Surya Nath Rai Sh. Khobhari Rai 878 Bramapur-Mehdora Agiaon Bhojpur 1849 Cultivation Sh. Kariman Ahir Sh. Deni Ahir 879 Bramapur-Mehdora Agiaon Bhojpur 1850 Cultivation Sh. Janak Rai Sh. Hargovind Rai 880 Bramapur-Mehdora Agiaon Bhojpur 1857 Cultivation 0.035 Sh. Janak Rai Sh. Hargovind Rai 881 Bramapur-Mehdora Agiaon Bhojpur 1858 Cultivation Sh. Janak Rai Sh. Hargovind Rai 882 Bramapur-Mehdora Agiaon Bhojpur 1847 Cultivation Sh. Kariman Ahir Sh. Deni Ahir 883 Bramapur-Mehdora Agiaon Bhojpur 1859 Cultivation 0.018 Sh. Hardwar Rai Sh. Dwarika Rai 884 Bramapur-Mehdora Agiaon Bhojpur 1860 Cultivation 0.02 Sh. Jay Govind Rai Sh. Ram Rai 885 Bramapur-Mehdora Agiaon Bhojpur 1845 Cultivation 0.027 Sh. Janak Rai Sh. Hargovind Rai 886 Bramapur-Mehdora Agiaon Bhojpur 1846 Cultivation Sh. Yadu Saha Sh. Kanhai Saha 887 Bramapur-Mehdora Agiaon Bhojpur 1866 Cultivation Sh. Narshima Rai Sh. Musafir Rai 888 Bramapur-Mehdora Agiaon Bhojpur 1826 Cultivation 0.022 Sh. Kariman Ahir Sh. Deni Ahir

9 Name of Affected Area Sl. No. Name of the Village Name of Block Plot No. Use of Land Name of the Owner Father’s Name District (in Acre) 889 Bramapur-Mehdora Agiaon Bhojpur 1827 Cultivation 0.013 Sh. Kuldip Ahir Sh. Ganpati Ahir 890 Bramapur-Mehdora Agiaon Bhojpur 1867 Cultivation Sh. Samla Rai Sh. Ramasro Rai 891 Bramapur-Mehdora Agiaon Bhojpur 1480 Cultivation Sh. Musadev Rai Sh. Ram Rekha Rai 892 Bramapur-Mehdora Agiaon Bhojpur 1479 Cultivation Sh. Ramla Rai Sh. Ramasro Rai 893 Bramapur-Mehdora Agiaon Bhojpur 1475 Cultivation Sh. Yamuna Rai Sh. Shiv Bahadur Rai 894 Bramapur-Mehdora Agiaon Bhojpur 176 Cultivation Sh. Balrup Rai Sh. Ganga Govind Rai 895 Bramapur-Mehdora Agiaon Bhojpur 1495 Cultivation Sh. Yamuna Rai Sh. Shiv Bahadur Rai 896 Bramapur-Mehdora Agiaon Bhojpur 1473 Cultivation Sh. Sarju Rai Sh. Beni Rai 897 Bramapur-Mehdora Agiaon Bhojpur 1472 Cultivation Sh. Sudeshwar Rai Sh. Khelawan Rai 898 Bramapur-Mehdora Agiaon Bhojpur 1471 Cultivation 0.001 Sh. Ram Kamlesh Rai Sh. Shiv Dayal Rai 899 Bramapur-Mehdora Agiaon Bhojpur 1470 Cultivation 0.014 Sh. Yamuna Rai Sh. Shiv Bahadur Rai 900 Bramapur-Mehdora Agiaon Bhojpur 1469 Cultivation Sh. Sarju Rai Sh. Beni Rai 901 Bramapur-Mehdora Agiaon Bhojpur 1468 Cultivation 0.028 Sh. Ram Pujan Mia Sh. Shami Mian 902 Bramapur-Mehdora Agiaon Bhojpur 1467 Cultivation 0.029 Sh. Awadesh Rai Sh. Ram Dhi Rai 903 Bramapur-Mehdora Agiaon Bhojpur 1449 Cultivation Sh. Narshima Rai Sh. Musafir Rai 904 Bramapur-Mehdora Agiaon Bhojpur 1450 Cultivation Sh. Ram Dhayan Rai Sh. Sukhdev Rai 905 Bramapur-Mehdora Agiaon Bhojpur 1451 Cultivation 0.028 Sh. Jagmohan Rai Sh. Yadhu Rai 906 Bramapur-Mehdora Agiaon Bhojpur 1452 Cultivation 0.017 Sh. Ram Dhayan Rai Sh. Sukhdev Rai 907 Bramapur-Mehdora Agiaon Bhojpur 1453 Cultivation Sh. Sahdev Rai Sh. Takur Rai 908 Bramapur-Mehdora Agiaon Bhojpur 1454 Cultivation Sh. Prashad Rai Sh. Ram Ratan Rai 909 Bramapur-Mehdora Agiaon Bhojpur 1456 Cultivation Sh. Satram Rai Sh. Dhamal Rai 910 Bramapur-Mehdora Agiaon Bhojpur 1455 Cultivation 0.003 Sh. Janak Rai Sh. Hargovind Rai 911 Bramapur-Mehdora Agiaon Bhojpur 1447 Cultivation Sh. Hardwar Rai Sh. Dwarika Rai 912 Bramapur-Mehdora Agiaon Bhojpur 1445 Cultivation Sh. Narshima Rai Sh. Musafir Rai 913 Bramapur-Mehdora Agiaon Bhojpur 1409 Cultivation 0.055 Sh. Sant Belas Rai Sh. Kunj Bihari Rai 914 Bramapur-Mehdora Agiaon Bhojpur 1410 Cultivation 0.011 Sh. Janak Rai Sh. Hargovind Rai 915 Bramapur-Mehdora Agiaon Bhojpur 1451 Cultivation 0.028 Sh. Jagmohan Rai Sh. Yadhu Rai 916 Bramapur-Mehdora Agiaon Bhojpur 1452 Cultivation 0.017 Sh. Ram Dhayan Rai Sh. Sukhdev Rai 917 Bramapur-Mehdora Agiaon Bhojpur 1404 Cultivation Sh. Dukhan Rai Sh. Sewak Rai 918 Bramapur-Mehdora Agiaon Bhojpur 1403 Cultivation Sh. Basropan Rai Sh. Nanhu Rai 919 Bramapur-Mehdora Agiaon Bhojpur 1402 Cultivation Sh. Aayit Rai Sh. Miman Rai 920 Bramapur-Mehdora Agiaon Bhojpur 1401 Cultivation Sh. Aayit Rai Sh. Miman Rai 921 Bramapur-Mehdora Agiaon Bhojpur 1400 Cultivation 0.002 Sh. Ram Dhayan Rai Sh. Devki Rai 922 Bramapur-Mehdora Agiaon Bhojpur 1378 Cultivation Sh. Surud Rai Sh. Jaddu Rai 923 Bramapur-Mehdora Agiaon Bhojpur 1377 Cultivation 0.041 Sh. Surud Rai Sh. Jaddu Rai 924 Bramapur-Mehdora Agiaon Bhojpur 1376 Cultivation 0.049 Sh. Ram Kavlesh Rai Sh. Shiv Dayal Rai 925 Bramapur-Mehdora Agiaon Bhojpur 1375 Cultivation 0.049 Sh. Sarju Rai Sh. Beni Rai 926 Bramapur-Mehdora Agiaon Bhojpur 1372 Cultivation 0.04 Sh. Yamuna Rai Sh. Siv Bahadur Rai 927 Bramapur-Mehdora Agiaon Bhojpur 1371 Cultivation Sh. Tapashya Rai Sh. Brijnandan Rai 928 Bramapur-Mehdora Agiaon Bhojpur 1327 Cultivation 0.037 Sh. Hasiha Rai Sh. Khelawan Rai 929 Bramapur-Mehdora Agiaon Bhojpur 1326 Cultivation Sh. Hasiha Rai Sh. Khelawan Rai 930 Bramapur-Mehdora Agiaon Bhojpur 1325 Cultivation 0.03 Sh. Hasiha Rai Sh. Khelawan Rai 931 Bramapur-Mehdora Agiaon Bhojpur 1320 Cultivation 0.002 Sh. Janak Rai Sh. Hargovind Rai 932 Bramapur-Mehdora Agiaon Bhojpur 1324 Cultivation 0.036 Sh. Shivnath Rai Sh. Dev Nath Rai 933 Bramapur-Mehdora Agiaon Bhojpur 1323 Cultivation 0.027 Sh. Shivnath Rai Sh. Dev Nath Rai 934 Bramapur-Mehdora Agiaon Bhojpur 1264 Cultivation Sh. Vishnath Saha Sh. Raghubir Saha 935 Bramapur-Mehdora Agiaon Bhojpur 2973 Cultivation 0.132 Not Available 936 Bramapur-Mehdora Agiaon Bhojpur 2972 Cultivation 0.048 Not Available 937 Bramapur-Mehdora Agiaon Bhojpur 2971 Cultivation 0.112 Not Available 938 Bramapur-Mehdora Agiaon Bhojpur 2970 Cultivation 0.059 Not Available 939 Bramapur-Mehdora Agiaon Bhojpur 2969 Cultivation 0.055 Not Available 940 Bramapur-Mehdora Agiaon Bhojpur 2968 Cultivation 0.043 Not Available 941 Bramapur-Mehdora Agiaon Bhojpur A Cultivation 0.025 Not Available 942 Bramapur-Mehdora Agiaon Bhojpur B Cultivation 0.007 Not Available 943 Bramapur-Mehdora Agiaon Bhojpur C Cultivation 0.007 Not Available 944 Bramapur-Mehdora Agiaon Bhojpur D Cultivation 0.007 Not Available 945 Bramapur-Mehdora Agiaon Bhojpur E Cultivation 0.009 Not Available 946 Bramapur-Mehdora Agiaon Bhojpur 2951 Cultivation 0.030 Not Available 947 Bramapur-Mehdora Agiaon Bhojpur 2950 Cultivation 0.001 Not Available 948 Bramapur-Mehdora Agiaon Bhojpur 1265 Cultivation Sh. Basudev Rai Sh. Supan Malah 949 Imadpur Tarari Bhojpur 1243 Cultivation RamNagani Pandey Tapleshwer Pandey 950 Imadpur Tarari Bhojpur 1242 Cultivation Ram Niwesh Pandey Ram Kishun Pandey 951 Imadpur Tarari Bhojpur 1241 Cultivation Ramjee Pandey Ramadhar Pandey 952 Imadpur Tarari Bhojpur 1233 Cultivation M.Indrash Kuwnar Shukhadav Pandey 953 Imadpur Tarari Bhojpur 1232 Cultivation Ram Niwesh Pandey Ram Kishun Pandey 954 Imadpur Tarari Bhojpur 1231 Cultivation Ram Niwesh Pandey Ram Kishun Pandey 955 Imadpur Tarari Bhojpur 1214 Cultivation Bhuneshwar Pandey Shaligram Pandey 956 Imadpur Tarari Bhojpur 1213 Cultivation Ram Aashis Pandey Ram Kesho Pandey 957 Imadpur Tarari Bhojpur 1205 Cultivation Tetra Kuwar Sataraj Raj Pandey 958 Imadpur Tarari Bhojpur 1198 Cultivation Radha Raman Pandey Nathuni Pandey 959 Imadpur Tarari Bhojpur 1195 Cultivation Jagdev Pandey Sadager Pandey 960 Imadpur Tarari Bhojpur 1180 Cultivation Bashropan Pandey Bhola Pandey 961 Imadpur Tarari Bhojpur 1172 Cultivation 0.021 Awadh Behari Shrikant 962 Imadpur Tarari Bhojpur 1173 Cultivation 0.014 Radha Raman Pandey Nathuni Pandey 963 Imadpur Tarari Bhojpur 1304 Cultivation Adhar Dyal Pandey subha Pandey 964 Imadpur Tarari Bhojpur 1303 Cultivation Bila Pandey Palak Pandey 965 Imadpur Tarari Bhojpur 1302 Cultivation Adhar Dyal Pandey subha Pandey 966 Imadpur Tarari Bhojpur 1301 Cultivation Dihal Pandey Palak Pandey 967 Imadpur Tarari Bhojpur 1258 Cultivation Rajendar Pandey Shri Niwash Pandey 968 Rajpur Tarari Bhojpur 1415 Cultivation Amawash Ahir Jadhik Ahir 969 Rajpur Tarari Bhojpur 1414 Cultivation Shahadave Ahir Nabat Ahir 970 Rajpur Tarari Bhojpur 1413 Cultivation Dangu Ahir Karateshwer Ahir 971 Rajpur Tarari Bhojpur 1409 Cultivation RamChanar Pashi Shakhari Pashi 972 Rajpur Tarari Bhojpur 1408 Cultivation Ram Chanar Pashi Shakhari Pashi 973 Rajpur Tarari Bhojpur 1407 Cultivation Ram Chanar Pashi Shakhari Pashi 974 Rajpur Tarari Bhojpur 1380 Cultivation Tarakeshwer Tiwari Jaganath Tiwari 975 Rajpur Tarari Bhojpur 1379 Cultivation Nand Keshwer Tiwari Jaganath Tiwari 976 Rajpur Tarari Bhojpur 1378 Cultivation Laxamni Tiwari Jaganath Tiwari 977 Rajpur Tarari Bhojpur 1345 Cultivation Shivedahen Ahir Janaki Ahir 978 Rajpur Tarari Bhojpur 1362 Cultivation Curamati Budhu 979 Rajpur Tarari Bhojpur 1355 Cultivation Shadave Ahir Nabat Ahir 980 Rajpur Tarari Bhojpur 1354 Cultivation Amawash Ahir Jadhik Ahir 981 Rajpur Tarari Bhojpur 1353 Cultivation Dangu Ahir Gupteshwer Ahir 982 Rajpur Tarari Bhojpur 1348 Cultivation NaRaian Ahir Janaki Ahir 983 Rajpur Tarari Bhojpur 1347 Cultivation 0.001 Shivedahen Ahir Janaki Ahir 984 Rajpur Tarari Bhojpur 1346 Cultivation 0.003 Pram Kumar 985 Rajpur Tarari Bhojpur 1345 Cultivation Shivedahen Ahir Janaki Ahir 986 Rajpur Tarari Bhojpur 1344 Cultivation 0.007 Prashad Ahir Janaki Ahir 987 Rajpur Tarari Bhojpur 1305 Cultivation 0.014 Nagina Jay Kishun

10 Name of Affected Area Sl. No. Name of the Village Name of Block Plot No. Use of Land Name of the Owner Father’s Name District (in Acre) 988 Rajpur Tarari Bhojpur 1304 Cultivation Bayuthi Ahir Shivadhan 989 Rajpur Tarari Bhojpur 1302 Cultivation Shivedahen Ahir Janaki Ahir 990 Rajpur Tarari Bhojpur 2420 Cultivation 0.018 Not Available 991 Rajpur Tarari Bhojpur 1249 Cultivation Shahdave Ahir Nabat Ahir 992 Rajpur Tarari Bhojpur 1301 Cultivation Mashodhi Pashi Kirangi Pashi 993 Rajpur Tarari Bhojpur 1262 Cultivation Banarashi Tiwari Balak Tiwari 994 Rajpur Tarari Bhojpur 1261 Cultivation Dangu Ahir Gupteshwer Ahir 995 Rajpur Tarari Bhojpur 1147 Cultivation Shigashan Nand Kumar 996 Rajpur Tarari Bhojpur 1260 Cultivation Ramadhar Tiwari Bani Tiwari 997 Rajpur Tarari Bhojpur 1259 Cultivation Laximi Tiwari Nandkeshwer Tiwari 998 Rajpur Tarari Bhojpur 1249 Cultivation Shahdave Ahir Nabat Ahir 999 Rajpur Tarari Bhojpur 1141 Cultivation Ram Eakabal Tiwari Raj Nandan Tiwai 1000 Rajpur Tarari Bhojpur 1165 Cultivation Budha Pashi Moti Pashi 1001 Rajpur Tarari Bhojpur 1163 Cultivation Gyan Chand Dusadh Bilar Dusadh 1002 Rajpur Tarari Bhojpur 1161 Cultivation Dangu Ahir Gupteshwer Ahir 1003 Rajpur Tarari Bhojpur 1160 Cultivation Dangu Ahir Gupteshwer Ahir 1004 Rajpur Tarari Bhojpur 1149 Cultivation Dangu Ahir Gupteshwer Ahir 1005 Rajpur Tarari Bhojpur 1148 Cultivation Dangu Ahir Gupteshwer Ahir 1006 Rajpur Tarari Bhojpur 1147 Cultivation Shigashan Nand Kumar 1007 Rajpur Tarari Bhojpur 1140 Cultivation Rupa Matho Rakha 1008 Rajpur Tarari Bhojpur 1139 Cultivation Bala dave Matho Bikram Matho 1009 Rajpur Tarari Bhojpur 1138 Cultivation Shadave Matho Bikram Matho 1010 Rajpur Tarari Bhojpur 1132 Cultivation Mushmat Subhago Darshat Tiwari 1011 Rajpur Tarari Bhojpur 1137 Cultivation 0.005 Shigashan Nand Kumar 1012 Rajpur Tarari Bhojpur 1135 Cultivation Radha Tiwari Pritam Tiwari 1013 Rajpur Tarari Bhojpur 1133 Cultivation Baghat Tiwari Bohari Tiwari 1014 Rajpur Tarari Bhojpur 1132 Cultivation Mushmat Subhago Darshat Tiwari 1015 Rajpur Tarari Bhojpur 1131 Cultivation Jatan Tiwari Ganesh Tiwari 1016 Rajpur Tarari Bhojpur 1130 Cultivation Prashad Singh Kripa Singh 1017 Rajpur Tarari Bhojpur 1434 Cultivation Dangu Ahir Gupteshwer Ahir 1018 Bihta Tarari Bhojpur 3154 Cultivation Sh. Dev Sharn Pandey Sh. Dhank Pandey 1019 Bihta Tarari Bhojpur 3155 Cultivation Sh. SatyanaRaian Singh Sh. Janki Singh 1020 Bihta Tarari Bhojpur 3157 Cultivation Sh. Dev NaRaian Mishra Sh. Man Vrit Mishra 1021 Bihta Tarari Bhojpur 3158 Cultivation Sh. Ram Singh Sh. Shankar Dayal Singh 1022 Bihta Tarari Bhojpur 2918 Cultivation 0.036 Sh. Bhikhari Singh Sh. Badhai Singh 1023 Bihta Tarari Bhojpur 2921 Cultivation 0.058 Sh. Jagna Raian Singh Sh. Kunwar Singh 1024 Bihta Tarari Bhojpur 2918 Cultivation 0.036 Sh. Bhikhari Singh Sh. Badhai Singh 1025 Bihta Tarari Bhojpur 2915 Cultivation Sh. Basdev Tiwari Sh. Praku Tiwari 1026 Bihta Tarari Bhojpur 2912 Cultivation Sh. Baleswar Mishra Sh. Veer Mishra 1027 Bihta Tarari Bhojpur 2914 Cultivation 0.006 Sh. Baleswar Mishra Sh. Veer Mishra 1028 Bihta Tarari Bhojpur 2926 Cultivation Sh. Yadu Nand Tiwari Sh. Sharan Tiwari 1029 Bihta Tarari Bhojpur 2904 Cultivation 0.016 Sh. Yadu Nand Tiwari Sh. Sharan Tiwari 1030 Bihta Tarari Bhojpur 2903 Cultivation 0.022 Sh. Devnaryan Mishra Sh. Man Vrit Mishra 1031 Bihta Tarari Bhojpur 2910 Cultivation 0.031 Sh. Uma shankar Singh Sh. Ramavtar Singh 1032 Bihta Tarari Bhojpur 2918 Cultivation 0.036 Sh. Bhikhari Singh Sh. Badhai Singh 1033 Bihta Tarari Bhojpur 905 Cultivation Sh. Basudev Pandey Sh. Ram Kumar Pandey 1034 Bihta Tarari Bhojpur 904 Cultivation Sh. Basudev Pandey Sh. Ram Kumar Pandey 1035 Bihta Tarari Bhojpur 903 Cultivation Sh. Basudev Pandey Sh. Ram Kumar Pandey 1036 Bihta Tarari Bhojpur 2884 Cultivation 0.187 Sh. Yadu Nand Tiwari Sh. Sharan Tiwari 1037 Bihta Tarari Bhojpur 2882 Cultivation 0.018 Sh. Dasai Tiwari Sh. Bahoi Tiwari 1038 Bihta Tarari Bhojpur 2881 Cultivation 0.019 Sh. Hari Nath Tiwari Sh. Pragas Tiwari 1039 Bihta Tarari Bhojpur 2880 Cultivation 0.013 Sh. Ram Lall Singh Sh. Ram Sharikh Singh 1040 Bihta Tarari Bhojpur 3549 Cultivation 0.01 Sh. Rajeshwar Singh Sh. Ramcharitar Singh 1041 Bihta Tarari Bhojpur 2878 Cultivation Sh. Tej Naraian Sh. Ramadhar Singh 1042 Bihta Tarari Bhojpur 2877 Cultivation Sh. Tej Naraian Sh. Ramadhar Singh 1043 Bihta Tarari Bhojpur 2870 Cultivation Sh. Takur Singh Sh. Siv Ratan Singh 1044 Bihta Tarari Bhojpur 2869 Cultivation Sh. Takur Singh Sh. Siv Ratan Singh 1045 Bihta Tarari Bhojpur 2866 Cultivation Sh. Radha Singh Sh. Mahesh Singh 1046 Bihta Tarari Bhojpur 2942 Cultivation Sh. Sadhu Sharan Singh Sh. Bihari Singh 1047 Bihta Tarari Bhojpur 2029 Cultivation Sh. Sarikhan Hajam Sh. Mahangu Hajan 1048 Bihta Tarari Bhojpur 2043 Cultivation Sh. Chandradeep Sh. Nand Kishore 1049 Bihta Tarari Bhojpur 3032 Cultivation Sh. Ram NaRaian Mishra Sh. Bhekha Mishra 1050 Bihta Tarari Bhojpur 3033 Cultivation Sh. Ram NaRaian Pathak Sh. Thakur Pathak 1051 Bihta Tarari Bhojpur 2992 Cultivation Sh. Thakur Singh Sh. Shiv Ratan Singh 1052 Bihta Tarari Bhojpur 3601 Cultivation Sh. Ram Singh Sh. Shankar Dayal Singh 1053 Bihta Tarari Bhojpur 2597 Cultivation Sh. Daura Mahto Sh. Shiv Charan Mahto 1054 Bihta Tarari Bhojpur 2564 Cultivation Sh. Ram Lakhan Choubey Sh. Ram Bharitar Choubey 1055 Bihta Tarari Bhojpur 2560 Cultivation Sh. Kalika Prashad Singh Sh. Thakur Singh 1056 Bihta Tarari Bhojpur 3665 Cultivation Sh. Jagdev Dev Singh Sh. Devi Singh 1057 Bihta Tarari Bhojpur 4214 Cultivation Sh. Nath Chamar Sh. Dhurphekan Chamar 1058 Bihta Tarari Bhojpur 4207 Cultivation Sh. Kalika Prashad Singh Sh. Thakur Singh 1059 Bihta Tarari Bhojpur 4220 Cultivation Sh. Kalika Prashad Singh Sh. Thakur Singh 1060 Bihta Tarari Bhojpur 4230 Cultivation Sh. Vashisth Singh Sh. Vasawan Singh 1061 Bihta Tarari Bhojpur 4241 Cultivation Sh. Viswanath Singh Sh. Ram Bhandra Singh 1062 Bihta Tarari Bhojpur 4242 Cultivation Sh. Viswanath Singh Sh. Ram Bhandra Singh 1063 Bihta Tarari Bhojpur 4243 Cultivation Sh. Thakur Singh Sh. Shiv Ratan Singh 1064 Bihta Tarari Bhojpur 4245 Cultivation Sh. Badri Singh Sh. Jugeshwar Singh 1065 Bihta Tarari Bhojpur 4246 Cultivation Sh. Tej NaRaian Singh Sh. Ramadhar Singh 1066 Bihta Tarari Bhojpur 4247 Cultivation Sh. Tej NaRaian Singh Sh. Ramadhar Singh 1067 Bihta Tarari Bhojpur 2585 Cultivation Sh. Yudh Nandan Tiwari Sh. Saran Tiwari 1068 Bihta Tarari Bhojpur 3551 Cultivation 0.013 Sh. Chandrama Singh Sh. Brahm Singh 1069 Bihta Tarari Bhojpur 3550 Cultivation 0.011 Sh. Rajeshwar Singh Sh. Ramcharitar Singh 1070 Bihta Tarari Bhojpur 3549 Cultivation 0.01 Sh. Rajeshwar Singh Sh. Ramcharitar Singh 1071 Bihta Tarari Bhojpur 3548 Cultivation 0.02 Sh. Ram Briksha Singh Sh. Dulam Singh 1072 Bihta Tarari Bhojpur 3547 Cultivation 0.02 Sh. Viswanath Singh Sh. Ram Chandra Singh 1073 Bihta Tarari Bhojpur 3540 Cultivation 0.006 Sh. Ambika Singh Sh. Dhanuk Singh 1074 Bihta Tarari Bhojpur 3539 Cultivation Sh. Kalika Prashad Singh Sh. Thakur Singh 1075 Bihta Tarari Bhojpur 3538 Cultivation Sh. Bachu Singh Sh. Shyama Singh 1076 Bihta Tarari Bhojpur 1707 Cultivation Sh. Nirman Ahir Sh. Dhuman Ahir 1077 Bihta Tarari Bhojpur 5611 Cultivation Sh. Dhurphekan Ahir Sh. Balkesh 1078 Bihta Tarari Bhojpur 4945 Cultivation Sh. Jagdish Singh Sh. Brahm Dev Singh 1079 Bihta Tarari Bhojpur 4952 Cultivation Sh. Kalika Prashad Singh Sh. Thakur Singh 1080 Bihta Tarari Bhojpur 4685 Cultivation Musmat Bhikhoi niya kunwar Sh. Swarth Singh 1081 Bihta Tarari Bhojpur 4688 Cultivation Sh. Thakur Singh Sh. Shiv Ratan Singh 1082 Bihta Tarari Bhojpur 4687 Cultivation Sh. Suryadev Singh Sh. Baldev Singh 1083 Bihta Tarari Bhojpur 4660 Cultivation Sh. Katigan Ahir Sh. Vijadhar Ahir 1084 Bihta Tarari Bhojpur 5005 Cultivation Sh. Jagdish Singh Sh. Brahmdev Singh 1085 Bihta Tarari Bhojpur 5006 Cultivation Sh. Jagdish Singh Sh. Brahmdev Singh 1086 Bihta Tarari Bhojpur 5008 Sh. Jagdish Singh Sh. Brahmdev Singh

11 Name of Affected Area Sl. No. Name of the Village Name of Block Plot No. Use of Land Name of the Owner Father’s Name District (in Acre) 1087 Sawari Lakh Nasrigung Rohtas 344 Radha Singh Kritan Singh 1088 Sawari Lakh Nasrigung Rohtas 317 Badhanath Singh Bishundev Singh 1089 Sawari Lakh Nasrigung Rohtas 343 Badhanath Singh Bishundev Singh 1090 Sawari Lakh Nasrigung Rohtas 316 Ram Badan Singh Brahamdev Singh 1091 Sawari Lakh Nasrigung Rohtas 347 Ram Badan Singh Brahamdev Singh 1092 Sawari Lakh Nasrigung Rohtas 341 Bagawati Singh Shivenandan Singh 1093 Sawari Lakh Nasrigung Rohtas 329 Bhula Ram Pathi 1094 Sawari Lakh Nasrigung Rohtas 330 Bhula Ram Pathi 1095 Sawari Lakh Nasrigung Rohtas 335 Bhula Ram Pathi 1096 Sawari Lakh Nasrigung Rohtas 328 Kadhar Banshropan Singh 1097 Sawari Lakh Nasrigung Rohtas 325 Ishari Ram Lal 1098 Sawari Lakh Nasrigung Rohtas 326 Ishari Ram Lal 1099 Sawari Lakh Nasrigung Rohtas 313 Ram Sakal Ram Lakhan 1100 Sawari Lakh Nasrigung Rohtas 319 Saudagar Lal 1101 Sawari Lakh Nasrigung Rohtas 314 Saudagar Lal 1102 Sawari Lakh Nasrigung Rohtas 311 Saudagar Lal 1103 Sawari Lakh Nasrigung Rohtas 312 Saudagar Lal 1104 Sawari Lakh Nasrigung Rohtas 315 Ram Shakal Balamukhan 1105 Sawari Lakh Nasrigung Rohtas 306 Gharai kishun 1106 Sawari Lakh Nasrigung Rohtas 313 Ram Sakal Ram Lakhan 1107 Sawari Lakh Nasrigung Rohtas 246 Cultivation Mahavhir Singh Ram nath Singh 1108 Sawari Lakh Nasrigung Rohtas 72 Cultivation 0.027 Bajanath Singh Rang Lal Singh 1109 Sawari Lakh Nasrigung Rohtas 76 Cultivation 0.015 Dhashiy Mishra Prameswer Singh 1110 Sawari Lakh Nasrigung Rohtas 74 Cultivation 0.023 Dhashiy Mishra Prameswer Singh 1111 Sawari Lakh Nasrigung Rohtas 151 Cultivation 0.019 Nathuni Ram Tulashi Ram 1112 Sawari Lakh Nasrigung Rohtas 248 Cultivation 0.006 Dhashiy Mishra Prameswer Singh 1113 Sawari Lakh Nasrigung Rohtas 75 Cultivation 0.019 Lagana Kuwnar Brij Bihari Singh 1114 Sawari Lakh Nasrigung Rohtas 203 Residential Prabhurajawar Rajawar Singh 1115 Sawari Lakh Nasrigung Rohtas 204 Cultivation Prabhurajawar Rajawar Singh 1116 Sawari Lakh Nasrigung Rohtas 206 Cultivation Sita Rajawar Prameswer Singh 1117 Sawari Lakh Nasrigung Rohtas 1 Cultivation Ramdev Mothi 1118 Sawari Lakh Nasrigung Rohtas 161 Cultivation 0.036 Avadha Bihari Mahavhir Chobey 1119 Sawari Lakh Nasrigung Rohtas 162 Cultivation 0.024 Rama Dhar Ram Ram Aash Ram 1120 Sawari Lakh Nasrigung Rohtas 156 Cultivation 0.026 Lochi Dhobhi Raju Dhobhi 1121 Sawari Lakh Nasrigung Rohtas 157 Cultivation 0.014 Lochi Dhobhi Raju Dhobhi 1122 Sawari Lakh Nasrigung Rohtas 153 Cultivation Mungha Ram Shadhu Ram 1123 Sawari Lakh Nasrigung Rohtas 152 Cultivation 0.011 Ram nath Ram Tulashi Ram 1124 Sawari Lakh Nasrigung Rohtas 151 Cultivation 0.019 Nathuni Ram Tulashi Ram 1125 Sawari Lakh Nasrigung Rohtas 148 Cultivation 0.009 Ishari Ram Jemandar Ram 1126 Sawari Lakh Nasrigung Rohtas 143 Cultivation 0.006 Ram nath Ram Tulashi Ram 1127 Sawari Lakh Nasrigung Rohtas 643 Cultivation 0.019 Tajanaraian Singh Dineshwry Singh 1128 Sawari Lakh Nasrigung Rohtas 647 Cultivation Tajanaraian Singh Dineshwery Singh 1129 Sawari Lakh Nasrigung Rohtas 646 Cultivation Sita Ram Singh Parashuram Singh 1130 Sawari Lakh Nasrigung Rohtas 651 Cultivation Sita Ram Singh Parashuram Singh 1131 Sawari Lakh Nasrigung Rohtas 648 Cultivation Ram Badan Singh Brahamdev Singh 1132 Sawari Lakh Nasrigung Rohtas 649 Cultivation Brijbhushan Pd Jhogander Pd 1133 Sawari Lakh Nasrigung Rohtas 653 Cultivation Brijbhushan Pd Jhogander Pd 1134 Sawari Lakh Nasrigung Rohtas 652 Cultivation Kaleka Lal Davan Ram 1135 Sawari Lakh Nasrigung Rohtas 249 Residential 0.033 Iandu Mane Singh Lal Mame Singh 1136 Sawari Lakh Nasrigung Rohtas 644 Cultivation 0.016 Shivnaraian Sah Janaki Sah 1137 Sawari Lakh Nasrigung Rohtas 654 Cultivation Rampujan Tiwari Gupteshwer Tiwari 1138 Sawari Lakh Nasrigung Rohtas 655 Cultivation 0.059 Rampujan Tiwari Gupteshwer Tiwari 1139 Sawari Lakh Nasrigung Rohtas 246 Cultivation Mahavhir Singh Ram nath Singh 1140 Sawari Lakh Nasrigung Rohtas 243 Cultivation Jay Ram Singh Bilash Singh 1141 Sawari Lakh Nasrigung Rohtas 247 Cultivation 0.004 Chadhi Singh Suaraj Singh 1142 Sawari Lakh Nasrigung Rohtas 244 Cultivation Abadha Bihari Singh Radha Singh 1143 Sawari Lakh Nasrigung Rohtas 242 Cultivation Nake Dhari Mishra RamTahal Mishra 1144 Sawari Lakh Nasrigung Rohtas 241 Cultivation Nake Dhari Mishra Ram Tahal Mishra 1145 Sawari Lakh Nasrigung Rohtas 220 Cultivation Nathuni Ram Tulashi Ram 1146 Sawari Lakh Nasrigung Rohtas 227 Cultivation Nathuni Ram Tulashi Ram 1147 Sawari Lakh Nasrigung Rohtas 219 Residential Jamuna Ram Nathuni Ram 1148 Sawari Lakh Nasrigung Rohtas 230 Cultivation Shamshar Singh Baldave Ram 1149 Sawari Lakh Nasrigung Rohtas 228 Cultivation Shri Nath Ram Jamendar Ram 1150 Sawari Lakh Nasrigung Rohtas 318 Cultivation Radha Singh Kritan Singh 1151 Kaithi Nasrigung Rohtas 1263 Residential 0.014 Ganeshwar Singh Dhasmedan Singh 1152 Kaithi Nasrigung Rohtas 1264 Cultivation Nathuni Singh LDhakRaj Singh 1153 Kaithi Nasrigung Rohtas 710 Cultivation 0.024 Raghu Raj Singh Dev Raj Singh 1154 Kaithi Nasrigung Rohtas 249 Cultivation 0.013 Indramani Singh Suraj Singh 1155 Kaithi Nasrigung Rohtas 1462 Cultivation Shiv Pujan Singh Nanhaku Singh 1156 Kaithi Nasrigung Rohtas 1251 Cultivation Seerendar Singh Balkeshwar Singh 1157 Kaithi Nasrigung Rohtas 761 Cultivation 0.007 Sunil Singh Pati Ram Singh 1158 Kaithi Nasrigung Rohtas Cultivation Mahatam Singh Ashok Singh 1159 Kaithi Nasrigung Rohtas 749 Cultivation 0.022 Mahanand Singh Banka Bihceri Singh 1160 Kaithi Nasrigung Rohtas 1166 Residential Baliram Singh Dhani Singh 1161 Kaithi Nasrigung Rohtas 1449 Cultivation Mukhi Singh Ramvaran Singh 1162 Kaithi Nasrigung Rohtas 1452 Cultivation Sita Ram Singh Pasuram Singh 1163 Kaithi Nasrigung Rohtas 747 Cultivation Fagu Garedi Ram Brichh Gared 1164 Kaithi Nasrigung Rohtas 1451 Cultivation Brij Bhusan Pd Yogendra Pd 1165 Kaithi Nasrigung Rohtas 1305 Cultivation Ramjee Pd Singh Bhagirthi Pd Singh 1166 Kaithi Nasrigung Rohtas 1303 Residential Ramjee Pd Singh Bhagirthi Pd Singh 1167 Kaithi Nasrigung Rohtas 1232 Cultivation Gopal Singh Sat NaRaian Singh 1168 Kaithi Nasrigung Rohtas Cultivation Anil Singh Bhuneshwar Singh 1169 Kaithi Nasrigung Rohtas 1306 Cultivation Satan Pd Nihora Singh 1170 Kaithi Nasrigung Rohtas Cultivation StendranaRaian Singh Bindeshakri Singh 1171 Kaithi Nasrigung Rohtas 1450 Cultivation Narshig NaRaian Singh Awadhbihari Singh 1172 Kaithi Nasrigung Rohtas 1447 Cultivation Kaliakalal Devranian Lal 1173 Kaithi Nasrigung Rohtas 1448 Cultivation Hayari Singh Rambaran Singh 1174 Kaithi Nasrigung Rohtas 1316 Residential Nath Muni Choudhary Sukhdev Choudhary 1175 Kaithi Nasrigung Rohtas 1351 Cultivation Dilip Kumar Pandey Sanjan Pandey 1176 Kaithi Nasrigung Rohtas 1343 Cultivation Hari Kisuhan Choudhary Basudev Choudhary 1177 Medinipur Nasrigung Rohtas 320 Cultivation Kadam Mia Ismail Mia 1178 Medinipur Nasrigung Rohtas 135 Cultivation 0.014 Sambhu Prasad Singh Ramparwesh Singh 1179 Medinipur Nasrigung Rohtas 136 Cultivation 0.041 Suresh Singh Sadhu Singh 1180 Medinipur Nasrigung Rohtas 137 Cultivation 0.016 RamA parasa Singh Mosafir Singh 1181 Medinipur Nasrigung Rohtas 138 Cultivation 0.012 Janeshwar Singh Bhaiyya Singh 1182 Medinipur Nasrigung Rohtas 140 Cultivation 0.007 Lala Singh Dukhit Singh 1183 Medinipur Nasrigung Rohtas 141 Cultivation 0.028 Nirantar Singh Kirti Singh 1184 Medinipur Nasrigung Rohtas 142 Cultivation 0.026 Rama Prasad Mahto Brij Bihari Singh 1185 Medinipur Nasrigung Rohtas 319 Cultivation 0.046 Muneshwar Singh Kawal Nath Singh

12 Name of Affected Area Sl. No. Name of the Village Name of Block Plot No. Use of Land Name of the Owner Father’s Name District (in Acre) 1186 Medinipur Nasrigung Rohtas 621 Cultivation Rama Prasad Singh Ramphal Singh 1187 Medinipur Nasrigung Rohtas 320/1130 Cultivation Kadam Mia Ismail Mia 1188 Sikariya Karakat Rohtas 402 Cultivation Kadam Mia Ikramul Mia 1189 Sikariya Karakat Rohtas 1587 Cultivation 0.008 Kamta Dusadh Sewak Dusadh 1190 Sikariya Karakat Rohtas 409 Cultivation 0.011 Durfekan Yadav Chutan Yadav 1191 Sikariya Karakat Rohtas 1588 Cultivation Kamta Dusadh Sewak Dusadh 1192 Sikariya Karakat Rohtas 802 Cultivation Lagan deep Halwai Ramjad Halwai 1193 Sikariya Karakat Rohtas 1007 Cultivation Bricha Sah Manik Sah 1194 Sikariya Karakat Rohtas 1586 Cultivation 0.008 Mahendra Singh Chandrika Singh 1195 Sikariya Karakat Rohtas 901 Cultivation Ramananda Yadav Asha Karan Yadav 1196 Sikariya Karakat Rohtas 1582 Cultivation 0.01 Siri Kishun Devnaraian 1197 Sikariya Karakat Rohtas 386 Cultivation Sri Yadav Chattu Yadav 1198 Sikariya Karakat Rohtas 407 Cultivation 0.022 Viswanath Singh Ramjanam Singh 1199 Sikariya Karakat Rohtas 283 Cultivation Sipahi Singh Ramjanam Singh 1200 Sikariya Karakat Rohtas 1681 Cultivation Jagdeep Halwai Ramjad Halwai 1201 Sikariya Karakat Rohtas 900 Cultivation Sis Prasad Singh Hari Prasad Singh 1202 Sikariya Karakat Rohtas 1004 Cultivation Nazir Mia Rahi Mia 1203 Sikariya Karakat Rohtas 1007 Cultivation Bricha Sah Manik Sah 1204 Sikariya Karakat Rohtas 1576 Cultivation 0.014 Chunuti Devpati Chauba Koiri 1205 Sikariya Karakat Rohtas 1583 Cultivation 0.019 Murti Devi Paltan Yadav 1206 Sikariya Karakat Rohtas 1584 Cultivation 0.045 Kehlawan Bansropan 1207 Sikariya Karakat Rohtas 1562 Cultivation Bricha Dusadh Sipahi Dusadh 1208 Sikariya Karakat Rohtas 1583 Cultivation 0.019 Murti Devi Paltan Yadav 1209 Gharwasdih Karakat Rohtas 731 Cultivation 0.048 Ramananda Yadav Loknath Yadav 1210 Gharwasdih Karakat Rohtas 733 Cultivation 0.079 Ramchandra Tiwari Teja Tiwari 1211 Gharwasdih Karakat Rohtas 765 Cultivation 0.038 Ramchandra Tiwari Teja Tiwari 1212 Gharwasdih Karakat Rohtas 826 Cultivation 0.011 Lalmuni Sah 1213 Gharwasdih Karakat Rohtas 768 Cultivation 0.015 Ram Chander Tiwary Teja Tiwari 1214 Gharwasdih Karakat Rohtas 823 Residential Kamlesh Pandey Mahendra Pandey 1215 Gharwasdih Karakat Rohtas 773 Cultivation 0.031 Jagdev Ram Gurudev Ram 1216 Gharwasdih Karakat Rohtas 879 Cultivation Nand Kishore Prasad Godhan Dhobi 1217 Gharwasdih Karakat Rohtas 813 Residential 0.027 RamSakal Singh Hari Charan Yadav 1218 Gharwasdih Karakat Rohtas 819 Residential 0.008 RamSakal Singh Hari Charan Yadav 1219 Gharwasdih Karakat Rohtas 820 Residential 0.006 Sanichal Mia Fakir Mia 1220 Gharwasdih Karakat Rohtas 821 Residential 0.023 Dev nath Tiwary Harkhu Tiwari 1221 Gharwasdih Karakat Rohtas 821 Residential 0.023 Sanichar Mia Fakir Mia 1222 Gharwasdih Karakat Rohtas 823 Residential Kamlesh Pandey Mahendra Pandey 1223 Gharwasdih Karakat Rohtas 823 Residential Bateshwar Singh Bali Ram yadav 1224 Gharwasdih Karakat Rohtas 825 Cultivation 0.04 Devendra Kumar Dubey Ram Prasad Dubey 1225 Gharwasdih Karakat Rohtas 827 Residential 0.012 Bimla Devi Sri Nath Dubey 1226 Gharwasdih Karakat Rohtas 836 Residential 0.015 Chandrahaas Tiwari Chandrabhan Tiwari 1227 Gharwasdih Karakat Rohtas 837 Residential 0.017 Venketeswar Tiwari Narmedeshwar Tiwari 1228 Gharwasdih Karakat Rohtas 852 Cultivation 0.015 Devraaj Tiwari Jaipal Tiwar 1229 Gharwasdih Karakat Rohtas 853 Residential 0.016 Laxman Sah Bhav Nath Sah 1230 Gharwasdih Karakat Rohtas 853 Residential 0.016 Jafar mia Piran Mia 1231 Gharwasdih Karakat Rohtas 853 Residential 0.016 Satya Narayan Sah Bishuni Sah 1232 Gharwasdih Karakat Rohtas 854 Cultivation 0.033 Rambachan Tiwari Ram kewal Tiwari 1233 Gharwasdih Karakat Rohtas 874 Cultivation 0.014 Ramakant Mishra Ashiyar Mishra 1234 Gharwasdih Karakat Rohtas 873 Cultivation 0.015 Kanhiya Tiwari Narad Muni Tiwari 1235 Gharwasdih Karakat Rohtas 826 Cultivation 0.011 Lalmuni Sah

13 Appendix 3 to Resettlement Plan (SH-81) LIST OF AFFECTED PROPERTIES - Encroachers

Distance from Chainage Sl. No. Road Side Village Name of Head of the Household Centerline Use of Structure Type of construction Km. (in mtrs.)

1 Right 2.000 Bhadwar Kisundev Roy 5.00 Residential Permanent

2 Right 2.010 Bhadwar Baijnath Ray 6.00 Residential Permanent

3 Right 2.020 Bhadwar Rameshwar Ray 6.00 Residential Permanent

4 Right 2.030 Bhadwar Sudarsan Ray 6.00 Residential Permanent

5 Right 2.140 Bhadwar Vijay Kumar Ray 6.00 Residential Permanent

6 Right 2.150 Bhadwar Motilal Yadav 6.00 Res-cum-Comm Permanent

7 Right 2.160 Bhadwar Hari Nanan Yadav 6.00 Residential Semi-Permanent

8 Right 2.170 Bhadwar Motilal Yadav 6.00 Residential Semi-Permanent

9 Right 2.180 Bhadwar Hiralal Yadav 3.50 Residential Semi-Permanent

10 Right 2.260 Bhadwar Sheo Shankar Sah 3.00 Commercial Semi-Permanent

11 Left 2.290 Bhadwar Surjoesh Shah 6.00 Residential Permanent

12 Left 2.300 Bhadwar Jagdew Ray 6.00 Residential Permanent

13 Left 2.320 Bhadwar Jaynath Ray 6.00 Residential Permanent

14 Left 2.330 Bhadwar Radhakrishna Ray 3.50 Residential Semi-Permanent

15 Left 2.340 Bhadwar Bealmel Lray 5.00 Residential Semi-Permanent

16 Left 2.370 Bhadwar Ramdav 4.00 Residential Permanent

17 Left 2.380 Bhadwar Anju Devi 5.00 Residential Semi-Permanent

18 Left 2.390 Bhadwar Shovenath Prashad 5.00 Residential Semi-Permanent

19 Left 2.400 Bhadwar Joshe Ray 3.00 Res-cum-Comm Permanent

20 Left 2.410 Bhadwar Bhawam Ray 5.00 Res-cum-Comm Semi-Permanent

21 Left 2.450 Bhadwar Motilal Shayal 3.00 Res-cum-Comm Permanent

22 Left 2.460 Bhadwar Devcham Saw 3.00 Res-cum-Comm Semi-Permanent

23 Left 2.480 Bhadwar Satiudhan Sah 3.00 Res-cum-Comm Semi-Permanent

24 Left 2.490 Bhadwar Ram Pravesh Sah 5.00 Res-cum-Comm Semi-Permanent

25 Right 5.200 Chandi Gunjan Kumar 5.50 Residential Semi-Permanent

26 Right 5.204 Chandi Mukhtar Ahmad 3.50 Residential Semi-Permanent

27 Right 5.208 Chandi Ajit Kumar 6.00 Residential Semi-Permanent

28 Right 5.216 Chandi Bisannath Shaw 5.00 Residential Permanent

29 Right 5.220 Chandi Bharates Shaw 5.50 Commercial Permanent

30 Right 5.232 Chandi Inder ;Dalal Pursade 6.00 Commercial Permanent

31 Right 5.236 Chandi Lalan Singh 5.00 Commercial Permanent

32 Right 5.240 Chandi Gopal Dee 5.00 Commercial Permanent

33 Right 5.244 Chandi Sunil Sharma Anil Sharma 5.50 Residential Semi-Permanent

34 Right 5.252 Chandi Krishna Thukar 6.00 Commercial Temporary

35 Right 5.264 Chandi Inderdawal Parsad 4.50 Residential Permanent

36 Left 5.268 Chandi Bhgwat Singh 6.00 Residential Semi-Permanent

37 Left 5.272 Chandi Bhajan Singh 6.00 Residential Semi-Permanent

38 Left 5.276 Chandi Ramjanam Lsingh 6.00 Residential Semi-Permanent

39 Left 5.280 Chandi Gyaneshwar Prasad 5.50 Commercial Permanent

40 Left 5.288 Chandi Muna Thakur 6.00 Commercial Temporary

41 Left 5.292 Chandi Sanjay Parsad 4.80 Commercial Temporary

42 Right 7.300 Rupchakia Sri Ramsurag Ray 5.00 Residential Semi-Permanent

43 Right 7.303 Rupchakia Ram Avata Singh 5.00 Residential Semi-Permanent

4 Distance from Chainage Sl. No. Road Side Village Name of Head of the Household Centerline Use of Structure Type of construction Km. (in mtrs.)

44 Right 7.330 Rupchakia Raj Kumar Singh 5.00 Residential Semi-Permanent

45 Left 7.363 Rupchakia Tan Singh 5.00 Residential Semi-Permanent

46 Left 7.381 Rupchakia Janardhan Yadav 5.00 Residential Semi-Permanent

47 Right 8.640 Lodipur Ram Baran Singh 4.00 Res-cum-Comm Semi-Permanent

48 Left 9.563 Kosiyan Prem Saw 3.00 Residential Permanent

49 Left 9.570 Kosiyan Ram Nanash 3.00 Residential Semi-Permanent

50 Left 9.584 Kosiyan Ram Kailash yadav 3.00 Residential Semi-Permanent

51 Left 9.591 Kosiyan Jagdesh Pandi 3.50 Residential Semi-Permanent

52 Left 9.598 Kosiyan Ramji Chaudhary 3.00 Residential Semi-Permanent

53 Left 9.633 Kosiyan Ramnath Shah 4.00 Residential Semi-Permanent

54 Left 9.647 Kosiyan Sangamram 4.30 Commercial Semi-Permanent

55 Left 9.654 Kosiyan Ram Yodha ram 4.30 Residential Semi-Permanent

56 Left 9.668 Kosiyan Shivji Chaudri 4.50 Residential Semi-Permanent

57 Left 9.696 Kosiyan Satya nand Matha 3.50 Residential Semi-Permanent

58 Left 9.710 Kosiyan Kakkter Das 6.00 Residential Semi-Permanent

59 Left 9.724 Kosiyan Sri Caran Chaudri 4.00 Residential Semi-Permanent

60 Left 9.787 Kosiyan Mashoodan Shah 3.50 Residential Semi-Permanent

61 Right 9.794 Kosiyan Kameer Chauhri 3.00 Commercial Permanent

62 Right 9.801 Kosiyan Birendra Sadhu 4.00 Residential Permanent

63 Right 9.808 Kosiyan Rinku Chaudri 5.00 Commercial Permanent

64 Right 9.815 Kosiyan Srimuckh Ramdas 6.00 Residential Permanent

65 Right 9.822 Kosiyan Sri Saheb Saran 3.00 Res-cum-Comm Permanent

66 Right 9.829 Kosiyan Akhilesh Pandit 3.00 Res-cum-Comm Semi-Permanent

67 Right 9.836 Kosiyan Ramlagan Chaudhri 4.00 Residential Permanent

68 Right 9.843 Kosiyan Arvind Chaudhri 5.00 Commercial Permanent

69 Right 9.850 Kosiyan Ravindra Kr. 6.00 Residential Permanent

70 Left 10.500 Bhagwatpur Bakesh Kumar 4.00 Res-cum-Comm Semi-Permanent

71 Left 10.520 Bhagwatpur Jodin Lal Rajak 6.00 Commercial Temporary

72 Left 10.528 Bhagwatpur Binod Kumar 4.00 Commercial Semi-Permanent

73 Right 10.532 Bhagwatpur Shikur Sao 5.00 Commercial Semi-Permanent

74 Right 10.536 Bhagwatpur Nand Kumar Shah 5.00 Commercial Semi-Permanent

75 Left 10.536 Bhagwatpur Naresh Singh 4.00 Residential Permanent

76 Right 10.540 Bhagwatpur Bhuletan Singh 4.00 Res-cum-Comm Semi-Permanent

77 Right 10.544 Bhagwatpur Arjun Singh 3.50 Commercial Temporary

78 Right 10.548 Bhagwatpur Gajadhr Tiwari 5.00 Residential Temporary

79 Right 10.552 Bhagwatpur Dev Kr. Singh 4.50 Res-cum-Comm Semi-Permanent

80 Right 12.793 Akhgaon Rajnath prasad 4.00 Res-cum-Comm Semi-Permanent

81 Right 14.705 Nasratpur Bajnath Sharma 6.00 Res-cum-Comm Semi-Permanent

82 Right 14.715 Nasratpur Ravindar Singh 6.00 Residential Semi-Permanent

83 Right 14.725 Nasratpur Tunwa Singh 3.00 Commercial Permanent

84 Right 14.720 Nasratpur Jitendra Singh 3.00 Commercial Permanent

85 Right 14.725 Nasratpur Shudir Singh 6.00 Residential Permanent

86 Right 14.730 Nasratpur Nagenarayan Singh 4.00 Residential Semi-Permanent

87 Right 14.735 Nasratpur Raj Kumar Singh 6.00 Res-cum-Comm Semi-Permanent

5 Distance from Chainage Sl. No. Road Side Village Name of Head of the Household Centerline Use of Structure Type of construction Km. (in mtrs.)

88 Right 14.745 Nasratpur Kasi Yadav 4.00 Residential Permanent

89 Right 14.750 Nasratpur Bhala Yadav 4.00 Residential Permanent

90 Right 14.765 Nasratpur Jaykrishna Yadav 4.00 Residential Semi-Permanent

91 Right 14.770 Nasratpur Radha Yadav 4.00 Residential Semi-Permanent

92 Right 14.775 Nasratpur Thakur Yadwa 4.00 Residential Semi-Permanent

93 Right 14.780 Nasratpur Jayprakash Yadwa 6.00 Residential Semi-Permanent

94 Right 14.785 Nasratpur Rannharish Yadwa 4.00 Residential Semi-Permanent

95 Right 14.790 Nasratpur Ram Kumar 5.00 Residential Semi-Permanent

96 Left 14.800 Nasratpur Chandi Yadav 4.00 Residential Semi-Permanent

97 Left 14.805 Nasratpur Shujee Yadav 4.00 Residential Semi-Permanent

98 Right 14.810 Nasratpur Birade Yadav 4.00 Residential Semi-Permanent

99 Right 14.815 Nasratpur Granath yadav 5.00 Residential Semi-Permanent

100 Right 14.820 Nasratpur Javer Yadav 5.00 Residential Semi-Permanent

101 Right 18.100 Chillosa Chandesh 3.50 Residential Semi-Permanent

102 Right 18.110 Chillosa Davanand Ram 6.00 Residential Semi-Permanent

103 Right 18.120 Chillosa Saraj Paswan 6.00 Residential Semi-Permanent

104 Left 18.150 Chillosa Banauri Shah 3.50 Commercial Permanent

105 Left 18.160 Chillosa Raguban Chaudri 6.00 Res-cum-Comm Permanent

106 Left 18.170 Chillosa Bijay Sharma 6.00 Residential Permanent

107 Left 18.190 Chillosa Rammurali Shah 6.00 Residential Semi-Permanent

108 Right 22.650 Sandesh Nagendra Sonar 6.00 Residential Permanent

109 Right 23.900 Kaji Chak Ravendar Parsad 6.00 Residential Semi-Permanent

110 Right 23.910 Kaji Chak Begender Prasad 6.00 Residential Semi-Permanent

111 Right 23.920 Kaji Chak Domo Shaw 6.00 Residential Semi-Permanent

112 Right 23.930 Kaji Chak Khalil 6.00 Residential Semi-Permanent

113 Right 23.940 Kaji Chak Md. Najam 6.00 Residential Semi-Permanent

114 Right 23.950 Kaji Chak Md. Kalm 6.00 Residential Semi-Permanent

115 Right 23.960 Kaji Chak Ajay Prasad 6.00 Residential Semi-Permanent

116 Right 23.970 Kaji Chak Chandar Deep Prasad 6.00 Residential Semi-Permanent

117 Right 24.000 Kaji Chak Md. Ramjan 6.00 Residential Semi-Permanent

118 Right 24.010 Kaji Chak Md. Kadis 6.00 Residential Semi-Permanent

119 Right 24.020 Kaji Chak Md. Butan 6.00 Residential Permanent

120 Right 24.040 Kaji Chak Jalim Singh 6.00 Residential Semi-Permanent

121 Right 24.050 Kaji Chak Gorkh 6.00 Commercial Permanent

122 Right 24.900 Saraya Daraukya Chaudry 6.00 Residential Semi-Permanent

123 Right 24.920 Saraya Kalmash Parsad 6.00 Residential Semi-Permanent

124 Right 24.930 Saraya Munna Sary Saw 6.00 Residential Semi-Permanent

125 Right 24.940 Saraya Shiv Lakhan Gupta 6.00 Residential Semi-Permanent

126 Right 24.950 Saraya Ram Narayan Gupta 6.00 Residential Semi-Permanent

127 Right 24.960 Saraya Amaria Chaudry 6.00 Residential Semi-Permanent

128 Right 24.970 Saraya Ratan Chaudry 6.00 Commercial Semi-Permanent

129 Right 25.000 Saraya Bisnath Chaudry 6.00 Residential Semi-Permanent

130 Right 25.020 Saraya Ladu Chaudry 6.00 Residential Semi-Permanent

131 Right 25.030 Saraya Chander Dev Chaudry 6.00 Residential Semi-Permanent

6 Distance from Chainage Sl. No. Road Side Village Name of Head of the Household Centerline Use of Structure Type of construction Km. (in mtrs.)

132 Right 25.040 Saraya Rajendar Chaudry 6.00 Residential Semi-Permanent

133 Right 26.760 Fulari Bajari Saw 6.00 Residential Semi-Permanent

134 Right 26.780 Fulari Addheen Ray 5.00 Residential Semi-Permanent

135 Right 26.800 Fulari Ajay Sahkersi 5.00 Residential Semi-Permanent

136 Right 27.816 Nurpur Basdev Singh 6.00 Residential Semi-Permanent

137 Right 27.818 Nurpur Indrajit Singh 6.00 Residential Semi-Permanent

138 Right 27.834 Nurpur Om Prakash Choudhri 6.00 Commercial Semi-Permanent

139 Right 27.840 Nurpur Dileep Chaudhari 6.00 Residential Semi-Permanent

140 Right 30.500 Milkitola Yadunandra Yadav 5.00 Residential Semi-Permanent

141 Right 30.505 Milkitola Mugal Yadav 5.00 Residential Temporary

142 Right 30.510 Milkitola Vidyanand Yadav 5.00 Residential Semi-Permanent

143 Right 30.515 Milkitola Shujo Mahto 6.00 Residential Semi-Permanent

144 Right 31.505 Azimabad Mukti Narayan/ Bijendra Gupta 6.00 Commercial Permanent

145 Right 34.160 Mehandaura Sukhdev Shah 3.50 Residential Semi-Permanent

146 Right 34.170 Mehandaura Aitwar Shah 5.00 Residential Temporary

147 Right 34.180 Mehandaura harinath Shah 3.00 Residential Temporary

148 Right 34.210 Mehandaura Luxmina Kuwanr 4.50 Res-cum-Comm Semi-Permanent

149 Right 34.220 Mehandaura Chatisan Shah 6.00 Res-cum-Comm Semi-Permanent

150 Right 34.240 Mehandaura Badri yadav 3.00 Residential Semi-Permanent

151 Right 34.250 Mehandaura Ramanuj Rai 5.50 Residential Semi-Permanent

152 Right 34.260 Mehandaura Shivnarayan Sharma 4.50 Residential Semi-Permanent

153 Right 37.215 Nanaur Ram Gahan Saw 6.00 Res-cum-Comm Permanent

154 Right 37.230 Nanaur Bisnath Singh 4.00 Residential Permanent

155 Right 37.235 Nanaur Rudal Saw 3.50 Residential Semi-Permanent

156 Right 37.245 Nanaur Gham Narayan Saw 3.00 Residential Semi-Permanent

157 Right 37.250 Nanaur Jivan 6.00 Residential Semi-Permanent

158 Left 37.330 Nanaur Satender Singh 3.50 Residential Permanent

159 Left 37.335 Nanaur Satrudhan Singh 6.00 Residential Semi-Permanent

160 Left 37.340 Nanaur Lalan Chaudri 3.50 Residential Semi-Permanent

161 Left 37.345 Nanaur Fulchand Chaudri 4.50 Residential Temporary

162 Right 41.000 Baruhi Rambilay 6.00 Residential Temporary

163 Right 41.003 Baruhi NA 5.00 Residential Semi-Permanent

164 Right 41.009 Baruhi Rajshari Singh 3.00 Res-cum-Comm Permanent

165 Right 41.012 Baruhi Krishna Kr. 5.00 Res-cum-Comm Semi-Permanent

166 Right 41.015 Baruhi Kamlesh Mahto 4.00 Res-cum-Comm Semi-Permanent

167 Right 41.021 Baruhi Ralkanid Singh 5.00 Res-cum-Comm Semi-Permanent

168 Right 41.024 Baruhi Sanjay Singh 3.00 Residential Semi-Permanent

169 Right 41.027 Baruhi Ganauri 6.00 Residential Semi-Permanent

170 Left 41.033 Baruhi Ragrut Sharma 5.00 Commercial Semi-Permanent

171 Left 41.036 Baruhi Sidhar 3.00 Res-cum-Comm Permanent

172 Left 41.039 Baruhi Suhdheer 5.00 Res-cum-Comm Semi-Permanent

173 Right 45.625 Sahar Audesh Ram 5.00 Residential Semi-Permanent

174 Right 45.630 Sahar Kalicharan Ram 3.00 Residential Semi-Permanent

175 Right 45.635 Sahar Lakhan Saw 3.00 Residential Semi-Permanent

7 Distance from Chainage Sl. No. Road Side Village Name of Head of the Household Centerline Use of Structure Type of construction Km. (in mtrs.)

176 Right 45.640 Sahar Beslal Chaudhary 3.00 Residential Semi-Permanent

177 Right 45.645 Sahar Manjeet Chaudhary 3.00 Residential Semi-Permanent

178 Right 45.650 Sahar Rajmani Chaudhary 3.00 Residential Permanent

179 Right 45.655 Sahar Haridwar Chaudhary 3.00 Residential Permanent

180 Right 45.660 Sahar Manpato Kunwar 3.00 Residential Semi-Permanent

181 Right 45.665 Sahar Lakshmi Narayan Prasad 4.00 Residential Permanent

182 Right 45.670 Sahar Rajan Dhari Sharma 5.00 Res-cum-Comm Semi-Permanent

183 Right 45.675 Sahar Bijay Biru 3.00 Res-cum-Comm Permanent

184 Right 45.680 Sahar Narayan 4.00 Res-cum-Comm Semi-Permanent

185 Right 45.685 Sahar Hari Narayan Singh 5.00 Commercial Semi-Permanent

186 Right 45.690 Sahar Basudev Chaudhary 5.00 Res-cum-Comm Temporary

187 Right 45.695 Sahar Doma Chaudhary 4.00 Residential Semi-Permanent

188 Right 52.400 Dhauri Sipahi Singh 4.50 Residential Semi-Permanent

189 Right 52.405 Dhauri Kameshwar Singh 4.50 Residential Semi-Permanent

190 Right 52.410 Dhauri Indrajeet Singh 6.00 Residential Permanent

191 Right 52.415 Dhauri Birister Singh 5.50 Residential Permanent

192 Right 52.440 Dhauri Ram Bachan Chaudri 6.00 Residential Semi-Permanent

193 Right 52.445 Dhauri Bhaukhan Chaudry 5.50 Residential Semi-Permanent

194 Right 52.480 Dhauri Janeshwar Yadav 5.00 Residential Semi-Permanent

195 Right 52.485 Dhauri Naradmuni Singh 4.00 Res-cum-Comm Semi-Permanent

196 Right 52.500 Dhauri Sivpujan Singh 3.00 Residential Permanent

197 Right 52.505 Dhauri Janardan Singh 5.00 Commercial Permanent

198 Right 56.980 Chotki Khadao Shiv Magal Ram 3.00 Residential Semi-Permanent

199 Right 56.990 Chotki Khadao Dalarchand Ram 3.00 Residential Semi-Permanent

200 Right 57.010 Chotki Khadao Nand Kishor rai 3.00 Residential Semi-Permanent

201 Right 57.020 Chotki Khadao Braj Kishor rai' 4.00 Residential Semi-Permanent

202 Right 57.030 Chotki Khadao Pramod Rai 3.00 Residential Semi-Permanent

203 Right 57.040 Chotki Khadao Kamla rai 3.00 Residential Semi-Permanent

204 Right 57.050 Chotki Khadao Shivmangal Rai 3.00 Residential Semi-Permanent

205 Right 57.060 Chotki Khadao Kasi Sha 3.00 Residential Permanent

206 Right 57.070 Chotki Khadao Jainath ram 3.00 Residential Semi-Permanent

207 Right 57.080 Chotki Khadao Ramnath Rai 4.00 Residential Semi-Permanent

208 Right 57.090 Chotki Khadao barat ram 3.00 Res-cum-Comm Permanent

209 Right 57.100 Chotki Khadao Ramnath Rai 5.00 Residential Semi-Permanent

210 Right 57.120 Chotki Khadao Subash Ram 4.00 Residential Semi-Permanent

211 Right 57.130 Chotki Khadao Sukhal Ram 6.00 Residential Semi-Permanent

212 Left 57.140 Chotki Khadao Luxman Mushar 3.50 Residential Semi-Permanent

213 Left 57.150 Chotki Khadao Yamuna Mushar 3.50 Residential Semi-Permanent

214 Left 57.160 Chotki Khadao Nagendra Rai 3.50 Residential Semi-Permanent

215 Left 57.170 Chotki Khadao Ravi Kumar 3.50 Residential Semi-Permanent

216 Left 57.180 Chotki Khadao Radhy Shyam Rai 3.50 Residential Semi-Permanent

217 Left 57.190 Chotki Khadao Sashi Ranjan Rai 3.50 Residential Semi-Permanent

218 Left 57.200 Chotki Khadao Sudesar Rai 3.50 Residential Semi-Permanent

219 Right 62.505 Dhokraha Ajit Kumar 3.00 Residential Permanent

8 Distance from Chainage Sl. No. Road Side Village Name of Head of the Household Centerline Use of Structure Type of construction Km. (in mtrs.)

220 Right 62.510 Dhokraha Ani Roy 4.00 Residential Semi-Permanent

221 Right 62.515 Dhokraha Rakash Singh 6.00 Commercial Semi-Permanent

222 Right 62.520 Dhokraha Rana Ray' 6.00 Residential Semi-Permanent

223 Right 62.525 Dhokraha Sadhu 5.00 Commercial Permanent

224 Left 62.615 Dhokraha Rajaram 4.50 Residential Semi-Permanent

225 Left 62.620 Dhokraha Dukhit Bist 4.00 Residential Semi-Permanent

226 Left 62.625 Dhokraha Late Chandip 3.00 Residential Semi-Permanent

227 Left 62.640 Dhokraha Ramisum 3.00 Residential Semi-Permanent

228 Left 62.645 Dhokraha Jalrnani Singh 3.00 Residential Permanent

229 Left 62.650 Dhokraha Rajeswar Sha 5.00 Residential Permanent

230 Left 62.665 Dhokraha Janeshwar Singh 5.00 Residential Semi-Permanent

231 Left 64.406 Rajpur Kapil Pasran 6.00 Commercial Semi-Permanent

232 Left 64.409 Rajpur Kapil Paswan 5.00 Residential Semi-Permanent

233 Left 64.412 Rajpur Ramu Paswan 3.00 Residential Semi-Permanent

234 Left 64.415 Rajpur Nandu paswan 3.00 Residential Semi-Permanent

235 Left 64.418 Rajpur Ram Samuj Paswan 4.00 Residential Semi-Permanent

236 Left 64.421 Rajpur Nand Kishore 6.00 Residential Semi-Permanent

237 Left 64.427 Rajpur Sambhu Paswan 6.00 Residential Semi-Permanent

238 Left 64.430 Rajpur Suresh Paswan 4.00 Residential Semi-Permanent

239 Left 64.433 Rajpur Raml Paswan 3.00 Residential Semi-Permanent

240 Left 64.436 Rajpur Dayali Paswan 3.00 Residential Semi-Permanent

241 Left 64.439 Rajpur Jamuna Paswan 4.00 Residential Semi-Permanent

242 Left 64.442 Rajpur Mandip Paswan 3.00 Commercial Semi-Permanent

243 Left 64.445 Rajpur Rupan Sah 3.00 Commercial Permanent

244 Left 64.448 Rajpur Iswar Dayal Singh 3.00 Commercial Permanent

245 Left 64.451 Rajpur Sawkhin Mahto 4.00 Residential Permanent

246 Left 64.454 Rajpur Vijay mahto 3.00 Residential Permanent

247 Left 64.457 Rajpur Manohar Singh 5.00 Res-cum-Comm Semi-Permanent

248 Left 64.460 Rajpur Swith Tiwari 6.00 Commercial Semi-Permanent

249 Left 64.463 Rajpur Pramod Tiwari 3.00 Residential Semi-Permanent

250 Left 64.466 Rajpur Harakh mistri 3.00 Commercial Semi-Permanent

251 Left 64.469 Rajpur Muni Tiwari 3.00 Residential Semi-Permanent

252 Left 64.472 Rajpur Jay Prakash Tiwari 4.00 Residential Semi-Permanent

253 Right 64.478 Rajpur Ram Sunas Singh 6.00 Residential Permanent

254 Left 64.481 Rajpur Rameshwar Singh 3.00 Residential Semi-Permanent

255 Left 64.487 Rajpur Moti Chaudhari 3.00 Residential Semi-Permanent

256 Left 64.490 Rajpur Raj Kumar Yadav 3.00 Residential Semi-Permanent

257 Right 64.526 Rajpur Swru Paswan 3.00 Residential Semi-Permanent

258 Right 64.532 Rajpur Ram Sunder Yadav 3.00 Res-cum-Comm Semi-Permanent

259 Right 64.535 Rajpur Anurodh Tiwari 3.00 Residential Semi-Permanent

260 Right 64.538 Rajpur Sri Bijay Tiwari 3.00 Residential Permanent

261 Right 64.541 Rajpur Ramk Dev Tiwari 4.00 Residential Permanent

262 Right 64.544 Rajpur Rajeev Tiwari 3.00 Residential Semi-Permanent

263 Right 64.547 Rajpur Baikunth Yadav 3.00 Residential Semi-Permanent

9 Distance from Chainage Sl. No. Road Side Village Name of Head of the Household Centerline Use of Structure Type of construction Km. (in mtrs.)

264 Right 64.550 Rajpur Radhika 3.00 Residential Semi-Permanent

265 Left 67.460 Bihta Arjun singh 4.00 Residential Semi-Permanent

266 Left 67.464 Bihta Sukhalal lShaw 3.00 Res-cum-Comm Semi-Permanent

267 Left 67.468 Bihta tuni Shaw 4.00 Res-cum-Comm Semi-Permanent

268 Left 67.472 Bihta Siyaram Chaudhari 4.50 Res-cum-Comm Semi-Permanent

269 Left 67.476 Bihta Jairam Chaudri 4.50 Res-cum-Comm Semi-Permanent

270 Left 67.480 Bihta Shivkumar Chaudri 4.50 Res-cum-Comm Semi-Permanent

271 Left 67.484 Bihta Gorakh Chaudri 4.50 Res-cum-Comm Semi-Permanent

272 Right 67.504 Bihta Kedar Kumar 3.00 Residential Semi-Permanent

273 Right 67.512 Bihta Jagarnath 3.00 Residential Semi-Permanent

274 Right 67.520 Bihta Sipahee Yadav 5.50 Residential Semi-Permanent

275 Right 70.220 Sonitola Dinesh Ram 5.00 Residential Semi-Permanent

276 Right 70.250 Sonitola Ayodhya Ram 5.00 Residential Semi-Permanent

277 Right 72.306 Imbrahimpur Goput Gandhi 4.50 Res-cum-Comm Semi-Permanent

278 Right 72.309 Imbrahimpur Md. Bdre Alam 3.00 Commercial Permanent

279 Right 72.312 Imbrahimpur Dudhesar Chaudry 5.50 Residential Semi-Permanent

280 Right 72.315 Imbrahimpur Dineser Choudary 5.50 Residential Semi-Permanent

281 Right 72.324 Imbrahimpur Baleswar Sha 4.00 Residential Permanent

282 Right 72.327 Imbrahimpur Satnrayan Sha 4.00 Residential Permanent

283 Right 72.330 Imbrahimpur Suresh Sha 4.00 Residential Permanent

284 Right 72.333 Imbrahimpur Kardhani Sha 3.00 Residential Semi-Permanent

285 Right 72.336 Imbrahimpur Nand Kumar Shrma 3.00 Residential Permanent

286 Left 72.339 Imbrahimpur Ghanshyam Singh 3.00 Commercial Permanent

287 Left 72.342 Imbrahimpur Arvind Singh 3.00 Commercial Permanent

288 Left 72.345 Imbrahimpur Indrabhusan Lsingh 3.00 Commercial Permanent

289 Left 72.348 Imbrahimpur Ansu Singh 3.00 Commercial Permanent

290 Left 72.351 Imbrahimpur Bhikari Singh 4.00 Res-cum-Comm Semi-Permanent

291 Left 72.357 Imbrahimpur Avdhesh Singh 3.00 Res-cum-Comm Permanent

292 Left 72.360 Imbrahimpur Ramjee Singh 3.00 Res-cum-Comm Permanent

293 Left 72.363 Imbrahimpur Bihari Singh 3.00 Res-cum-Comm Semi-Permanent

294 Left 72.366 Imbrahimpur rajgeer Singh 4.00 Res-cum-Comm Permanent

295 Left 72.369 Imbrahimpur Jagdamba Singh 4.00 Res-cum-Comm Permanent

296 Left 72.372 Imbrahimpur Sarayu Singh 3.00 Res-cum-Comm Permanent

297 Left 72.375 Imbrahimpur Dilip Kumar Singh 3.00 Res-cum-Comm Permanent

298 Left 72.378 Imbrahimpur Sriganesh Kuswaha 3.00 Res-cum-Comm Permanent

299 Left 72.381 Imbrahimpur Rajiv Kushwaha 3.00 Res-cum-Comm Permanent

300 Left 72.384 Imbrahimpur Khuten MaHTO 3.00 Res-cum-Comm Permanent

301 Left 72.387 Imbrahimpur Sahebdayal Lsingh 3.00 Commercial Permanent

302 Left 72.402 Imbrahimpur Subhanmiya 4.00 Commercial Permanent

303 Left 72.405 Imbrahimpur Jalaludin 3.00 Commercial Permanent

304 Left 72.408 Imbrahimpur Munshi Choudary 3.00 Res-cum-Comm Permanent

305 Right 72.411 Imbrahimpur Tulshi Choudhary 3.00 Commercial Semi-Permanent

306 Right 72.414 Imbrahimpur Sultan Mi 3.00 Commercial Permanent

307 Left 72.420 Imbrahimpur Bhara Shah 5.50 Res-cum-Comm Semi-Permanent

10 Distance from Chainage Sl. No. Road Side Village Name of Head of the Household Centerline Use of Structure Type of construction Km. (in mtrs.)

308 Left 72.423 Imbrahimpur Hukum Chand 5.50 Commercial Semi-Permanent

309 Left 72.432 Imbrahimpur Sakrudi 5.00 Commercial Temporary

310 Left 72.435 Imbrahimpur Gonga Lchauchari 5.50 Commercial Permanent

311 Left 72.438 Imbrahimpur Ram Pravesh 5.50 Commercial Permanent

312 Left 72.441 Imbrahimpur Manoj Chaudhrari 5.50 Commercial Permanent

313 Left 72.444 Imbrahimpur Vijay Chaudhari 5.50 Res-cum-Comm Permanent

314 Left 72.447 Imbrahimpur Hajari Prasad 5.50 Res-cum-Comm Permanent

315 Left 72.450 Imbrahimpur Jagnarayan Pandit 5.50 Res-cum-Comm Permanent

316 Left 72.453 Imbrahimpur Rajbali Pandit 5.50 Residential Semi-Permanent

317 Left 72.456 Imbrahimpur Vishwanath Sah 5.50 Residential Semi-Permanent

318 Left 72.459 Imbrahimpur Gopal Sahu 5.50 Res-cum-Comm Permanent

319 Left 72.462 Imbrahimpur Krishna Sahu 5.50 Res-cum-Comm Permanent

320 Right 72.518 Kachwa Nandalal Shaw 6.00 Res-cum-Comm Semi-Permanent

321 Right 72.521 Kachwa Arjun singh 6.00 Residential Semi-Permanent

322 Right 72.527 Kachwa Tirbani Prasad 4.00 Res-cum-Comm Semi-Permanent

323 Right 72.536 Kachwa Dawarika Shaw 5.00 Commercial Semi-Permanent

324 Right 72.539 Kachwa Ramosu Shaw 6.00 Residential Semi-Permanent

325 Right 72.542 Kachwa Sarju Prasad 6.00 Res-cum-Comm Semi-Permanent

326 Right 72.545 Kachwa Lakman Shya 6.00 Residential Semi-Permanent

327 Left 72.650 Kachwa Mohamed Manish 4.50 Res-cum-Comm Semi-Permanent

328 Left 72.656 Kachwa Shunder Shan 4.50 Commercial Semi-Permanent

329 Left 73.348 Kaithi Pradeep Pandey 3.00 Residential Semi-Permanent

330 Left 73.354 Kaithi Ashok Pandey 3.00 Residential Semi-Permanent

331 Left 73.360 Kaithi Kameshwar Tiwario 5.00 Residential Semi-Permanent

332 Left 73.366 Kaithi Shri Bhagawan Bhat 3.00 Residential Semi-Permanent

333 Left 73.372 Kaithi Hari Kishan Chau 3.50 Residential Semi-Permanent

334 Right 73.402 Kaithi Mohan Singh 4.00 Residential Permanent

335 Right 73.408 Kaithi Mahanand Singh 4.00 Residential Permanent

336 Right 73.420 Kaithi Indradev Ram 4.00 Residential Semi-Permanent

337 Right 73.426 Kaithi Vinod Singh 3.00 Residential Semi-Permanent

338 Right 73.432 Kaithi Chunni Pandey 3.00 Residential Semi-Permanent

339 Right 73.438 Kaithi Hrshn ;Kumar Pandey 4.00 Residential Permanent

340 Right 73.444 Kaithi Sri Ram Pandey 4.00 Residential Semi-Permanent

341 Right 73.450 Kaithi Gupteshwar Tiwari 4.00 Residential Semi-Permanent

342 Right 73.456 Kaithi Ramishwar Mishra 3.00 Residential Permanent

343 Right 73.462 Kaithi Fagu Saw 3.00 Res-cum-Comm Semi-Permanent

344 Right 73.468 Kaithi Mahendra Prasad 5.00 Residential Semi-Permanent

345 Right 73.474 Kaithi Rajaram Saw 4.00 Residential Semi-Permanent

346 Right 73.480 Kaithi Ramkishor Bhagat 3.00 Residential Semi-Permanent

347 Right 73.486 Kaithi Ramamuni Pandey 4.00 Residential Semi-Permanent

348 Right 73.492 Kaithi Sunjay Pandy 4.00 Residential Semi-Permanent

349 Right 77.110 Maharajgunj Subhak Singh 5.00 Residential Permanent

350 Right 77.115 Maharajgunj Ram Bachan Shah 5.00 Residential Permanent

351 Right 77.130 Maharajgunj Dhaja Singh 5.00 Residential Permanent

11 Distance from Chainage Sl. No. Road Side Village Name of Head of the Household Centerline Use of Structure Type of construction Km. (in mtrs.)

352 Right 77.140 Maharajgunj Bharat Paswan 5.00 Commercial Semi-Permanent

353 Right 77.155 Maharajgunj Shukla Pandit 5.00 Residential Semi-Permanent

354 Right 77.160 Maharajgunj Mahant Shah 4.00 Res-cum-Comm Semi-Permanent

355 Right 77.165 Maharajgunj Shambhu Paswan 5.00 Residential Semi-Permanent

356 Right 81.200 GharwasD Venkteshwar Tiwari 5.00 Residential Semi-Permanent

357 Right 81.210 GharwasD Ram Sumir Ram 4.00 Commercial Semi-Permanent

358 Right 81.220 GharwasD Satya Narayan Shah 4.00 Residential Semi-Permanent

359 Left 80.000 Osawan Hari Sharan Upadhyay 5.00 Residential Permanent

360 Left 80.010 Osawan Surendra Upadhyay 3.00 Residential Permanent

361 Right 80.020 Osawan Lt. Devlal Shah 4.00 Residential Semi-Permanent

362 Right 80.030 Osawan Gajadhar Shah 4.00 Residential Semi-Permanent

363 Left 80.040 Osawan Dudhnath Pandey 4.00 Residential Permanent

364 Right 80.050 Osawan Mritunjay Upadhyay 3.00 Residential Permanent

365 Left 80.060 Osawan Kedar Shah 4.00 Residential Semi-Permanent

366 Right 80.070 Osawan Manoj Upadhyay 4.00 Residential Semi-Permanent

367 Right 80.080 Osawan Biru Kanhar 4.00 Residential Semi-Permanent

368 Right 80.090 Osawan Ram Pati Shah 5.00 Residential Semi-Permanent

369 Right 80.100 Osawan Rasbihari Ram 4.00 Residential Semi-Permanent

370 Right 80.110 Osawan Raghupati Prasad 4.00 Residential Semi-Permanent

371 Right 80.120 Osawan Malik Ram 4.50 Residential Semi-Permanent

372 Left 80.130 Osawan Gorakh Singh 4.00 Residential Semi-Permanent

373 Left 80.140 Osawan Lather Ram 4.00 Residential Semi-Permanent

374 Left 80.150 Osawan Dilip Ram 5.00 Residential Semi-Permanent

375 Right 79.000 Tulsitola Mulla Rawani 3.00 Residential Semi-Permanent

376 Right 79.010 Tulsitola Algu Rawani 3.00 Residential Semi-Permanent

377 Left 79.020 Tulsitola Anil Gosai 5.00 Residential Semi-Permanent

378 Left 79.030 Tulsitola Amawas Gosai 3.00 Residential Semi-Permanent

379 Left 79.040 Tulsitola Sanjay Ram 3.00 Residential Semi-Permanent

380 Right 34.260 Mehandaura Shushila Kumar 3.00 Residential Semi-Permanent

381 Right 34.300 Mehandaura Lt.Bhikhari Shah 3.50 Residential Semi-Permanent

382 Right 34.320 Mehandaura Sudarshan Rai 4.00 Residential Permanent

383 Left 87.500 Bardiha Ram Vilash 3.50 Residential Semi-Permanent

384 Left 87.520 Bardiha Dina/ Jitendra 3.50 Residential Semi-Permanent

385 Left 87.540 Bardiha Yugal Bania 3.50 Residential Semi-Permanent

386 Left 87.560 Bardiha Manoj Bania 3.50 Residential Semi-Permanent

387 Left 87.580 Bardiha Jagat 3.00 Residential Semi-Permanent

388 Left 87.600 Bardiha Bhim Bania 3.00 Residential Semi-Permanent

389 Left 87.620 Bardiha Santoshi Bania 3.00 Residential Semi-Permanent

390 Left 87.640 Bardiha Latta Bania 3.00 Residential Semi-Permanent

391 Left 87.660 Bardiha Ram Ashish 4.00 Residential Semi-Permanent

392 Left 87.680 Bardiha Suresh Bania 3.50 Residential Semi-Permanent

393 Left 87.700 Bardiha Mukandan Bania 3.50 Residential Semi-Permanent

394 Right 87.720 Bardiha Pramod Paswan 3.00 Residential Semi-Permanent

395 Right 87.740 Bardiha Kunti Bania 4.00 Residential Semi-Permanent

12 Distance from Chainage Sl. No. Road Side Village Name of Head of the Household Centerline Use of Structure Type of construction Km. (in mtrs.)

396 Right 87.760 Bardiha Shiv Pujan Bhuiya 5.50 Residential Semi-Permanent

397 Right 87.780 Bardiha Mukhram Bhuiya 3.00 Residential Semi-Permanent

398 Right 87.800 Bardiha Yogendra Bhuiya 3.50 Residential Semi-Permanent

399 Right 87.820 Bardiha Lt.Nageshar Bhuiya 5.50 Residential Semi-Permanent

400 Right 87.840 Bardiha Kulbansh Bhuiya 5.50 Residential Semi-Permanent

401 Right 87.860 Bardiha Laxman Bhuiya 3.00 Residential Semi-Permanent

402 Right 87.880 Bardiha Ram Bachan Bhuiya 5.00 Residential Semi-Permanent

403 Left 56.500 Chotki Khadao Sigasan Rai 4.00 Residential Semi-Permanent

404 Left 56.530 Chotki Khadao Harendra Rai 4.00 Residential Permanent

405 Left 56.560 Chotki Khadao Umeshwar Rai 5.00 Residential Permanent

406 Left 56.590 Chotki Khadao Pankaj Rai 5.00 Residential Semi-Permanent

407 Left 56.620 Chotki Khadao Dinesh Rai 4.00 Residential Semi-Permanent

408 Left 56.650 Chotki Khadao Umeshwar Rai 5.00 Residential Semi-Permanent

409 Left 56.680 Chotki Khadao Mangal Rai 4.00 Residential Semi-Permanent

410 Left 56.710 Chotki Khadao Eqbal Saw 4.00 Residential Semi-Permanent

411 Left 56.740 Chotki Khadao Daroga Rai 4.00 Residential Permanent

412 Left 56.770 Chotki Khadao Bijaay Ram 5.00 Residential Semi-Permanent

413 Left 14.700 Narayanpur Satya Narayan Singh 3.50 Residential Permanent

414 Right 56.920 Chotki Khadao Tarkeshwar Singh 5.00 Residential Permanent

415 Left 56.940 Chotki Khadao Paramhans Singh 3.50 Residential Permanent

416 Left 56.960 Chotki Khadao Vinfhyachal Singh 5.30 Residential Permanent

417 Left 56.980 Chotki Khadao Raj Kumar Singh 3.00 Residential Permanent

418 Left 57.000 Chotki Khadao Daroga Singh 5.30 Residential Permanent

419 Left 2.000 Bhadwar Anju Devi 4.00 Residential Semi-Permanent

420 Right 56.960 Chotki Khadao Uday Singh 3.50 Residential Semi-Permanent

421 Right 49.600 Khaira Satya Narayan Chaudhari 5.00 Residential Semi-Permanent

422 Right 56.960 Chotki Khadao Guru Charan Chaudhari 4.50 Residential Semi-Permanent

423 Right 56.980 Chotki Khadao Jagdhari Chaudhari 3.50 Residential Semi-Permanent

424 Right 57.000 Chotki Khadao Ghura Pandit 5.00 Residential Semi-Permanent

425 Right 57.020 Chotki Khadao Nand Singh 5.00 Residential Semi-Permanent

426 Right 57.040 Chotki Khadao Madheshwar Singh 4.00 Residential Permanent

427 Right 57.060 Chotki Khadao Vanktesh Pandit 3.00 Residential Semi-Permanent

428 Right 57.080 Chotki Khadao Jhapari Ram 3.00 Residential Semi-Permanent

429 Right 57.100 Chotki Khadao Kamlesh Ram 6.00 Residential Semi-Permanent

430 Right 57.120 Chotki Khadao Raghu nath Ram 5.00 Residential Semi-Permanent

431 Right 57.140 Chotki Khadao Paradeep Ram 4.00 Residential Semi-Permanent

432 Right 57.160 Chotki Khadao Baijnath Ram 4.50 Residential Semi-Permanent

433 Right 57.180 Chotki Khadao Ramesh Ram 5.50 Residential Semi-Permanent

434 Right 57.200 Chotki Khadao Madan Ram 5.00 Residential Permanent

435 Right 57.220 Chotki Khadao Ravindra Ram 4.00 Residential Permanent

436 Right 57.240 Chotki Khadao Virendra Ram 3.50 Residential Semi-Permanent

437 Right 57.260 Chotki Khadao Kashinath Ram 4.50 Residential Permanent

438 Right 57.280 Chotki Khadao Shiv Datt Ram 5.00 Residential Semi-Permanent

439 Right 57.300 Chotki Khadao Binda Ram 3.50 Residential Semi-Permanent

13 Distance from Chainage Sl. No. Road Side Village Name of Head of the Household Centerline Use of Structure Type of construction Km. (in mtrs.)

440 Right 57.320 Chotki Khadao Ram Pravesh Ram 3.50 Residential Permanent

441 Right 57.340 Chotki Khadao Mina Devi 3.00 Residential Permanent

442 Right 57.360 Chotki Khadao Ayodhya Rai 3.00 Residential Permanent

443 Right 57.380 Chotki Khadao Suresh Rai 3.00 Residential Permanent

444 Right 57.400 Chotki Khadao Kashinath Shah 3.00 Residential Permanent

445 Right 57.420 Chotki Khadao Sigasan Mahto 4.00 Residential Semi-Permanent

446 Right 57.440 Chotki Khadao Janak Chaudhari 3.00 Residential Semi-Permanent

447 Right 57.460 Chotki Khadao Jaglal Chaudhari 5.00 Residential Semi-Permanent

448 Right 57.480 Chotki Khadao Bansi Chaudhari 4.50 Residential Semi-Permanent

449 Left 18.400 Chillosa Repura Garnauri Sah 5.00 Residential Permanent

450 Left 18.420 Chillosa Repura Lakshman Sah 4.00 Residential Permanent

451 Left 18.440 Chillosa Repura Mahendra Singh 4.00 Residential Permanent

452 Left 18.460 Chillosa Repura Suraj Nayan Sharma 4.00 Res-cum-Comm Semi-Permanent

453 Left 18.480 Chillosa Repura Omnath Sharma 4.00 Residential Semi-Permanent

454 Left 18.500 Chillosa Repura Gorakh Sharma 4.00 Residential Semi-Permanent

455 Right 31.540 Azimabad Sri Nivash Jiwari 6.00 Residential Permanent

456 Right 31.560 Azimabad Pyar Chand 5.00 Residential Permanent

457 Right 31.640 Azimabad Uttam Singh 6.00 Residential Permanent

458 Right 31.660 Azimabad Animal Hak 6.00 Residential Semi-Permanent

459 Right 31.680 Azimabad Md.Akula Huk 6.00 Residential Permanent

460 Left 67.400 Bihta Kapil Singh 4.00 Residential Semi-Permanent

461 Left 67.420 Bihta Wakil Baitha 3.00 Residential Semi-Permanent

462 Right 67.440 Bihta Sayashi Baitha 5.00 Residential Semi-Permanent

463 Left 67.460 Bihta Meena Singh 4.00 Residential Permanent

464 Right 67.480 Bihta Let.Babua Singh 5.00 Residential Permanent

465 Left 67.500 Bihta Yogendra Chaudhary 3.00 Residential Semi-Permanent

466 Left 67.520 Bihta Jitendra Singh 5.00 Residential Semi-Permanent

467 Left 67.540 Bihta Suraj Singh 3.00 Residential Semi-Permanent

468 Left 67.560 Bihta Dudhnath Ram 3.00 Residential Semi-Permanent

469 Left 67.580 Bihta Vijay Ram 3.00 Residential Semi-Permanent

470 Left 67.600 Bihta Pyarchand Ram 3.00 Residential Semi-Permanent

471 Left 67.620 Bihta Madan Singh/ Naresh 3.00 Residential Permanent

472 Left 67.640 Bihta Gopal Singh 3.00 Residential Permanent

473 Left 67.660 Bihta Baijnath Singh 5.00 Residential Permanent

474 Right 51.600 Dhauri Upendra Singh 5.50 Residential Permanent

475 Right 51.620 Dhauri Chanderwar Singh 5.50 Residential Permanent

476 Right 51.640 Dhauri Chanderwar Sarma 6.00 Residential Semi-Permanent

477 Right 51.660 Dhauri Jhagaru Chaudhri 6.00 Residential Semi-Permanent

478 Right 51.680 Dhauri Bhikhari Yadav 6.00 Residential Semi-Permanent

479 Right 51.720 Dhauri Ram Keshwar Yadav 6.00 Residential Semi-Permanent

480 Right 46.000 Sahar Khurshida Khatun 4.00 Commercial Permanent

481 Right 46.020 Sahar Sri Griwa Saw 6.00 Residential Permanent

482 Right 46.040 Sahar Rajmuna Devi 3.00 Residential Semi-Permanent

483 Right 46.060 Sahar Ram Pravesh Ram 3.00 Residential Semi-Permanent

14 Distance from Chainage Sl. No. Road Side Village Name of Head of the Household Centerline Use of Structure Type of construction Km. (in mtrs.)

484 Right 46.100 Sahar Ayodhya Chaudhari 6.00 Residential Semi-Permanent

485 Right 30.020 Baga Ram Ishwar Chaudhari 6.00 Residential Semi-Permanent

486 Right 30.030 Baga Ram Pyare Chauhari 6.00 Residential Semi-Permanent

487 Right 31.100 Milky Tola Nand Kumar Yadav 5.00 Residential Semi-Permanent

488 Right 18.400 Chillosa Repura Binesh Singh 4.30 Residential Permanent

489 Right 18.410 Chillosa Repura Narayan Singh 5.00 Residential Permanent

490 Right 18.420 Chillosa Repura Shiv Kumar Singh 4.00 Residential Permanent

491 Right 18.430 Chillosa Repura Sri Bhagwan Singh 4.00 Residential Permanent

492 Right 18.440 Chillosa Repura Biteshwar Singh 3.00 Residential Semi-Permanent

493 Right 18.450 Chillosa Repura Rameshwar Singh 3.50 Residential Permanent

494 Right 18.460 Chillosa Repura Ragnbir Singh 3.00 Res-cum-Comm Permanent

495 Right 18.470 Chillosa Repura Bansi dhar Singh 3.00 Residential Semi-Permanent

496 Right 18.480 Chillosa Repura Ram Bharosha Singh 3.00 Residential Permanent

497 Right 18.490 Chillosa Repura Ajay Singh 3.00 Residential Semi-Permanent

498 Right 18.500 Chillosa Repura Suresh Singh 3.00 Residential Permanent

499 Right 18.510 Chillosa Repura Ramdutt Singh 6.00 Res-cum-Comm Permanent

500 Right 18.520 Chillosa Repura Shivnath Chauhary 4.00 Commercial Permanent

501 Right 18.530 Chillosa Repura Rhandheswar 4.00 Residential Semi-Permanent

502 Right 18.540 Chillosa Repura Saroj Paswan 4.00 Residential Permanent

503 Right 18.550 Chillosa Repura Dnyali Saw 5.50 Commercial Permanent

504 Right 18.560 Chillosa Repura Baban Yadav 4.00 Residential Semi-Permanent

505 Right 18.570 Chillosa Repura Manju Devi 5.30 Residential Semi-Permanent

506 Right 18.580 Chillosa Repura Sanjay Chaudhary 4.30 Residential Semi-Permanent

507 Right 18.590 Chillosa Repura Dil Baso kuar 4.30 Residential Semi-Permanent

508 Left 18.600 Chillosa Repura Birja Saw 4.00 Residential Permanent

509 Left 18.610 Chillosa Repura Saroj Saw 4.00 Residential Semi-Permanent

510 Left 18.620 Chillosa Repura Saroj Saw 3.50 Residential Permanent

511 Left 18.630 Chillosa Repura Tej Narayan 4.00 Residential Permanent

512 Left 18.640 Chillosa Repura Rajeshwar Prasad 4.50 Residential Semi-Permanent

513 Left 18.650 Chillosa Repura Jugjivan Prasad 3.00 Residential Semi-Permanent

514 Left 18.660 Chillosa Repura Suresh Paswan 3.50 Commercial Permanent

515 Left 18.670 Chillosa Repura Tripurari Prasad 5.00 Residential Permanent

516 Left 18.680 Chillosa Repura Dayanand Ram 4.00 Residential Temporary

517 Left 18.690 Chillosa Repura Sudheswar Paswan 3.50 Residential Temporary

518 Left 18.700 Chillosa Repura Binod Saw 3.50 Residential Permanent

519 Left 18.710 Chillosa Repura Ram Lagan Saw 4.00 Residential Permanent

520 Left 18.720 Chillosa Repura Jawahar Prasad Gupta 3.50 Residential Permanent

521 Left 18.730 Chillosa Repura Kashi Nath Gupta 3.50 Commercial Permanent

522 Left 18.740 Chillosa Repura Raj Kumar Gupta 3.50 Residential Permanent

523 Left 18.750 Chillosa Repura Hari Narayan Singh 4.00 Residential Permanent

524 Left 18.760 Chillosa Repura Daroga Yadav 5.00 Residential Semi-Permanent

525 Right 22.040 Sandesh Mutur Saw 5.00 Commercial Permanent

526 Right 22.060 Sandesh Lal babu Singh 5.00 Commercial Semi-Permanent

527 Right 22.080 Sandesh Krisna Saw 6.00 Commercial Permanent

15 Distance from Chainage Sl. No. Road Side Village Name of Head of the Household Centerline Use of Structure Type of construction Km. (in mtrs.)

528 Right 22.100 Sandesh Chandrika Lal 5.00 Residential Permanent

529 Right 22.140 Sandesh Arvind Rajak 6.00 Commercial Permanent

530 Right 24.800 Saraiya Laxman Saw 6.00 Residential Permanent

531 Right 24.810 Saraiya Ramjee Saw 6.00 Residential Permanent

532 Right 24.820 Saraiya Prayag Saw 6.00 Residential Permanent

533 Right 24.830 Saraiya Laxman Chaudhari 6.00 Residential Semi-Permanent

534 Right 24.840 Saraiya Bhanjendra Singh 6.00 Residential Semi-Permanent

535 Right 24.850 Saraiya Surendra Chaudhari 6.00 Residential Semi-Permanent

536 Right 10.600 Bhagwatpur Jawahar Sharma 5.50 Residential Permanent

537 Right 10.610 Bhagwatpur Dr. S.N.Singh 5.50 Residential Permanent

538 Right 10.630 Bhagwatpur Surya Narayan Sah 3.50 Residential Permanent

539 Left 10.800 Bisunpur Shiv mangal Sah 3.50 Commercial Permanent

540 Left 10.810 Bisunpur Ramdev Yadav 4.50 Commercial Semi-Permanent

541 Left 10.820 Bisunpur Ramanand Singh 5.50 Res-cum-Comm Permanent

542 Right 15.900 Nusratpur Surendra Rajak 4.00 Residential Semi-Permanent

543 Right 15.910 Nusratpur Suman Singh 5.00 Residential Semi-Permanent

544 Right 15.920 Nusratpur Shiv Keshwar 4.50 Residential Semi-Permanent

545 Right 15.930 Nusratpur Ram Keshwar 3.50 Residential Semi-Permanent

546 Right 15.940 Nusratpur Laxmina Kunwar 4.00 Residential Semi-Permanent

547 Right 15.950 Nusratpur Rusha 5.00 Residential Semi-Permanent

548 Right 15.960 Nusratpur Jarban 5.00 Residential Semi-Permanent

549 Left 63.600 Dhokraha Nand Kumar Chaudhari 3.50 Residential Semi-Permanent

550 Left 63.610 Dhokraha Uday Sharma 4.00 Residential Permanent

551 Right 63.620 Dhokraha Gauri Shankar 3.00 Residential Semi-Permanent

552 Left 63.630 Dhokraha Dina Nath 4.00 Residential Permanent

553 Left 63.640 Dhokraha Ashok Kumar 3.00 Residential Semi-Permanent

554 Left 63.650 Dhokraha Tetari Kunwar 5.00 Residential Semi-Permanent

555 Right 63.660 Dhokraha Sunil Singh 3.00 Residential Semi-Permanent

556 Left 63.670 Dhokraha Mahendra Singh 3.00 Residential Semi-Permanent

557 Left 63.680 Dhokraha Ram Jivan 3.00 Residential Semi-Permanent

558 Right 63.690 Dhokraha Laxman Ram 4.00 Residential Semi-Permanent

559 Left 63.700 Dhokraha Indra Dev Singh 4.00 Residential Semi-Permanent

560 Right 62.300 Imadpur Ramdhin Mushar 4.00 Residential Semi-Permanent

561 Right 62.310 Imadpur Nakh Mushar 3.50 Residential Semi-Permanent

562 Right 62.320 Imadpur Kameshwar Mushar 4.00 Residential Semi-Permanent

563 Left 62.330 Imadpur Jay Kumar Mushar 3.00 Residential Semi-Permanent

564 Left 62.340 Imadpur Laxman Mushar 3.00 Residential Semi-Permanent

565 Left 62.350 Imadpur Radhika Devi 3.00 Residential Semi-Permanent

566 Right 62.360 Imadpur Fulguni Mushar 3.00 Residential Semi-Permanent

567 Right 62.370 Imadpur Ashok Mushar 4.00 Residential Semi-Permanent

568 Right 62.380 Imadpur Shivji Mushar 4.50 Residential Semi-Permanent

569 Right 62.390 Imadpur Tetari Mushar 4.00 Residential Semi-Permanent

570 Right 62.400 Imadpur Jai Kumar 4.00 Residential Semi-Permanent

571 Right 62.410 Imadpur Ramadhar 5.00 Residential Semi-Permanent

16 Distance from Chainage Sl. No. Road Side Village Name of Head of the Household Centerline Use of Structure Type of construction Km. (in mtrs.)

572 Right 83.500 Pahrma Lakh Yasvant Yadav 6.00 Commercial Permanent

573 Left 84.600 Sikariya Sambhu Ram 6.00 Residential Permanent

574 Left 84.610 Sikariya Harihar Singh 5.50 Residential Semi-Permanent

575 Left 84.620 Sikariya Mahngu Chaudhary 5.00 Residential Semi-Permanent

576 Left 84.630 Sikariya Rajindra Sah 5.00 Residential Semi-Permanent

577 Left 84.640 Sikariya Srinath Sah 5.00 Residential Semi-Permanent

578 Left 84.650 Sikariya Sashi dhar 5.00 Residential Semi-Permanent

579 Left 84.660 Sikariya Banshi Sah 6.00 Residential Semi-Permanent

580 Left 84.670 Sikariya Bisnath Sah 6.00 Residential Permanent

581 Left 84.680 Sikariya Nathuri Sah 6.00 Residential Semi-Permanent

582 Left 84.690 Sikariya Baijnath Sah 5.50 Residential Semi-Permanent

583 Left 84.700 Sikariya Ram Ekbal Paswan 5.00 Res-cum-Comm Semi-Permanent

584 Left 84.710 Sikariya Ramanand Yadav 6.00 Residential Semi-Permanent

585 Left 84.720 Sikariya Bhola Sah 5.00 Commercial Semi-Permanent

586 Right 84.730 Sikariya Rampali Sah 4.50 Commercial Semi-Permanent

587 Right 84.740 Sikariya Sanjay Sah 4.50 Residential Semi-Permanent

588 Right 84.750 Sikariya Nathuni Sah 4.50 Residential Semi-Permanent

589 Right 84.760 Sikariya Mahngu Chaudhary 4.50 Residential Semi-Permanent

590 Right 84.770 Sikariya Krishna Sah 5.50 Residential Semi-Permanent

591 Right 84.780 Sikariya Bablu Ram 5.50 Residential Semi-Permanent

592 Right 84.790 Sikariya Bhola Sah 5.50 Residential Semi-Permanent

593 Right 84.800 Sikariya Ramesh Sah 5.50 Residential Semi-Permanent

594 Right 84.810 Sikariya Kapil Thakur 5.00 Residential Semi-Permanent

595 Right 84.820 Sikariya Sunil Thakur 5.00 Residential Semi-Permanent

596 Left 86.300 Chanditola Ramvilash Mahto 5.50 Residential Semi-Permanent

597 Left 86.310 Chanditola Ram Asish 4.00 Residential Semi-Permanent

598 Left 86.320 Chanditola Babu lal 4.00 Residential Semi-Permanent

599 Left 86.330 Chanditola Ramjee Paswan 4.00 Residential Semi-Permanent

600 Right 86.340 Chanditola Kailash Ram 5.50 Residential Permanent

601 Right 86.350 Chanditola Indra Dev Singh 5.50 Residential Permanent

602 Right 21.900 Sandesh Sri Lakhan Roy 4.00 Residential Permanent

603 Right 21.920 Sandesh Ram pal Mahta 5.00 Residential Permanent

604 Right 21.940 Sandesh Let.Degree Saw 5.00 Res-cum-Comm Permanent

605 Right 21.960 Sandesh Shivjee Sharma 4.00 Res-cum-Comm Semi-Permanent

606 Right 21.980 Sandesh Shusheela Devi 6.00 Res-cum-Comm Permanent

607 Right 22.000 Sandesh Nand Kumar Singh 6.00 Res-cum-Comm Permanent

608 Right 22.020 Sandesh Doma Saw 6.00 Res-cum-Comm Permanent

609 Right 22.080 Sandesh Ramjeet 6.00 Residential Permanent

610 Right 22.120 Sandesh Chandra Kr. Singh 4.00 Commercial Semi-Permanent

611 Right 22.280 Sandesh Shivjee Prasad 6.00 Res-cum-Comm Semi-Permanent

612 Right 22.320 Sandesh Nalan Sah 6.00 Residential Permanent

613 Right 22.340 Sandesh Baban Saha 6.00 Residential Permanent

614 Right 22.360 Sandesh Lodhan Kuar 5.00 Residential Permanent

615 Right 22.420 Sandesh Rampyar 5.00 Residential Permanent

17 Distance from Chainage Sl. No. Road Side Village Name of Head of the Household Centerline Use of Structure Type of construction Km. (in mtrs.)

616 Right 22.500 Sandesh Nagendra Sonar 6.00 Residential Permanent

617 Right 9.100 Gopalpur RanKumari Tiwari 4.00 Commercial Semi-Permanent

618 Right 9.110 Gopalpur Sundar Singh 4.00 Commercial Semi-Permanent

619 Right 9.120 Gopalpur Anil Kumar Singh 5.00 Commercial Permanent

620 Right 9.130 Gopalpur Vijay Giuta 5.00 Residential Semi-Permanent

621 Right 9.140 Gopalpur Anadri Chaudhari 3.00 Residential Semi-Permanent

622 Right 9.150 Gopalpur Shivmandri Chaudhari 3.00 Residential Semi-Permanent

623 Right 9.160 Gopalpur Ganshwer Saw 3.00 Res-cum-Comm Permanent

624 Left 9.400 Kosihan Rajnarayan Sah 4.00 Residential Semi-Permanent

625 Left 9.410 Kosihan Shganbihari Sah 4.00 Residential Semi-Permanent

626 Left 9.420 Kosihan Basmoto Devi 5.50 Residential Permanent

627 Left 9.430 Kosihan SeoShankar Ram 3.50 Residential Permanent

628 Left 9.440 Kosihan Majetar Yadav 3.50 Residential Permanent

629 Left 9.450 Kosihan Sudesh Mishtri 5.00 Residential Permanent

630 Left 9.460 Kosihan Munmun Saw 3.50 Residential Semi-Permanent

631 Left 9.470 Kosihan Manadev Saw 3.50 Residential Semi-Permanent

632 Left 9.480 Kosihan Masudan Saw 4.50 Residential Semi-Permanent

633 Left 9.490 Kosihan Saryugsan 4.00 Residential Semi-Permanent

634 Left 9.500 Kosihan Tagdish Pandit 3.50 Residential Semi-Permanent

635 Left 9.510 Kosihan Ram Kabilash 3.00 Residential Semi-Permanent

636 Left 9.520 Kosihan Chandeswar 5.50 Residential Semi-Permanent

637 Left 68.700 Engleshpul Shadhu Shah 3.50 Residential Semi-Permanent

638 Left 69.000 Engleshpul Brij nandan Singh 3.50 Residential Semi-Permanent

639 Left 69.300 Engleshpul Hiralal Shah 3.50 Residential Semi-Permanent

640 Left 69.600 Engleshpul kamla Simgh 3.00 Residential Semi-Permanent

641 Left 70.200 Engleshpul Lt. Kishun Singh 5.00 Residential Semi-Permanent

642 Left 70.500 Engleshpul Amit Prasad 4.00 Residential Semi-Permanent

643 Left 70.800 Engleshpul Barhishth Singh 4.00 Residential Semi-Permanent

644 Left 71.100 Engleshpul Kesari Singh 4.00 Residential Semi-Permanent

645 Left 71.400 Engleshpul Moti Singh 5.00 Residential Semi-Permanent

646 Left 72.000 Engleshpul Shivraj Singh 3.00 Residential Semi-Permanent

647 Left 72.300 Engleshpul Lt.Adalat Singh 5.00 Residential Semi-Permanent

648 Left 72.600 Engleshpul Siyaram Singh 5.00 Residential Semi-Permanent Distance from Sl. No. Road Side Chainage Village Name of the Owner Centerline (in 649 Left 72.900 Engleshpul Amit Prasad 4.50 Residential Semi-Permanent

650 Left 73.200 Engleshpul Girija Singh 6.00 Residential Semi-Permanent

651 Left 73.500 Engleshpul Ram Ashiish Singh 6.00 Residential Semi-Permanent

652 Left 73.800 Engleshpul Girija Singh 6.00 Residential Semi-Permanent

653 Right 74.100 Engleshpul Girija Singh 5.00 Residential Semi-Permanent

654 Left 74.400 Engleshpul Sigasan Singh 4.00 Residential Semi-Permanent

655 Left 74.700 Engleshpul Hareram Singh 6.00 Residential Semi-Permanent

656 Left 75.000 Engleshpul Ram Dev Singh 5.50 Residential Semi-Permanent

657 Left 75.300 Engleshpul Yamuna Singh 6.00 Residential Permanent

658 Right 75.600 Engleshpul Sakaldev Singh 3.50 Residential Semi-Permanent

18 Appendix 3 to Resettlement Plan (SH-81) LIST OF AFFECTED PROPERTIES - Encroachers

Distance from Road Name of Head of the Sl. No. Chainage Km. Village Centerline Use of Structure T y pe of construction Side Household (in mtrs.) 1 Left 9.640 Kosiyan Ram Chapit 4.00 Commercial Temporary 2 Left 9.647 Kosiyan Kishan Mistri 4.00 Commercial Temporary 3 Left 10.516 Bhagwatpur Bhola 3.50 Commercial Permanent 4 Left 14.795 Nasratpur Gridha Yadav 3.00 Residential Semi-Permanent 5 Right 31.524 Azimabad Birendra Kr Singh 3.50 Commercial Permanent 6 Right 34.120 Mehandaura Dudhnath Rai 5.50 Residential Semi-Permanent 7 Right 34.130 Mehandaura Nand Kr. Chaudhary 5.00 Residential Semi-Permanent 8 Right 37.465 Nanaur Md. Tuntun 3.00 Commercial Semi-Permanent 9 Left 62.630 Dhokraha Mithu 3.00 Residential Semi-Permanent 10 Left 62.635 Dhokraha Droga Singh 3.00 Residential Semi-Permanent 11 Left 73.336 Kaithi Ram Narayan Chaudari 3.00 Residential Permanent 12 Left 73.342 Kaithi Sanjay Chaudari 3.00 Residential Semi-Permanent 13 Left 7.040 Rupchakia Sitaram Yadav 5.00 Residential Semi-Permanent 14 Left 7.050 Rupchakia KanhiaSingh 5.00 Residential Semi-Permanent

1