KANNAUJ PARLIAMENTARY CONSTITUENCY , the most populous state of the nation, is served by North Central Railway along with Northern, North Vinay Kumar Tripathi Eastern and East Central Railways. Indian Railways (IR) plays a General Manager very important role in development of the state and provide North Central Railway connectivity for freight and passengers, including international tourists. IR has a history of more than 160 years in the state and has the highest route kilometers - 9100 route kilometers-with in it, which is 14% of entire Indian Railways network. IR has made Uttar Pradesh proud by giving it Nation's first semi high speed train Gatimaan Express, which initially ran between and . It has now been extended upto - a move that will boost tourism in Bundelkhand region of Uttar Pradesh. After Gatiman, the nation's first engineless semi high speed train set "Vande Bharat Express" which is running from New Delhi to Varanasi is also serving the state of Uttar Pradesh. Efforts for further development of railway infrastructure in Uttar Pradesh have been intensified in last seven years with 461% more investment in comparison to previous years. Results of such a massive investment are becoming visible with enhanced infrastructure and modern passenger amenities. Soon the era of congestion and inconvenience will be matter of past and a new Railway equipped with state-of-the art facilities will be able to serve the citizens in a better manner and provide them enhanced value for their money. The longest stretch of the under construction Eastern Dedicated Freight Corridor i.e. almost 57% of the entire length lies in Uttar Pradesh from Pt. Deen Dayal Upadhyaya Jn. to Ghaziabad. In this brochure, we have compiled the important contributions and achievements of Indian Railways in the development of the constituency of Uttar Pradesh in last seven years. I hope that it will serve as a ready reckoner for those eager to know about the role of Railways in the development of this constituency. It may be noted that the budgets allocated to various projects are not apportioned constituency wise but reflect the cost of the project. INPUTS BY RAILWAY IN KANNAUJ PARLIAMENTARY CONSTITUENCY KANNAUJ PARLIAMENTARY CONSTITUENCY

A. ASSEMBLY SEGMENTS Kannauj,Chhibramau, , Tirwa, Bidhuna

B. WORKS COMPLETED IN LAST SEVEN YEARS

GROB constructed at Level Crossing no. 101 & 102 at Ambiapur- section. GROB constructed at Level Crossing no. 02 at Jhinjhak-Kanchausi. GProvision of 350/200 mm dia tubewell, pump house, generator & chlorinator room at Kannauj at a cost of Rs. 60 Lakh. G60 Mark-II hand pump to fullfill the requirement of water supply at various stations of Izzatnagar Division at a cost of Rs. 31.00 Lakh. GPiped Water Supply at 'D' Category stations of Izzatnagar Division at a cost of Rs. 128.00 Lakh. GCGS Display Board for main Platform at Farrukhabad station & Train Indication Board, POET, Digital Clock & other shortlead amenities at 15 stations of Izzatnagar Division at a cost of Rs. 7.00 Lakh. G100 low cost PP shelters & RCC benches along with provision of international signages at 20 stations of Izzatnagar Division at a cost of Rs. 7.00 Lakh. GConstruction of toilets at Farrukhabad, Kasganj, Kannuaj, Mathura, Sikandra Rao, Daryaogonj, Rudain, , Bilhaur, Gursahaiganj, Kalianpur, Barrajpur & Patiali at a cost of Rs. 135.00 Lakh.

IMPROVEMENTS IN PASSENGERS AMENITIES G Train Display Board at Kannauj at a cost of Rs. 3.10 Lakh. G CCTV at Kannauj at a cost of Rs. 50 Lakh. G 100% LED light at Kannauj at a cost of Rs. 7.00 lakh. G01 Divyang Toilet at Jhinjhak has been provided. GRail level Platform extension work at Jhinjhak. GFOB surface has been improved at Jhinjhak. GPlatform AC sheet has been replaced with galvanized sheet at Jhinjhak. GTiles provided at Jhinjhak station. GFacade of Booking office improved at Jhinjhak. C. OTHER DEVELOPMENTS: New Trains introduced with stoppage over Kannauj Constituency. GTrain No. 19401/19402 Ahmedabad- weekly Express. GTrain No. 22443/22444 Central-Bandra T. weekly Express. D. ON-GOING WORKS

GROB at Level Crossing no. 01 at Jhinjhak station. GCoach guidance display system at platform no. 02 & 03 at Jhinjhak station. GTrain timing display board at Jhinjhak. GOne bay Platform shelters at 30 stations of Izzatnagar Division, 5 bay Platform shelters at Farrukhabad, 4 bay Platform shelters at Kannauj at a cost of Rs. 568.36 Lakh. GExtension of high level platforms for longest train at 12 stations of Izzatnagar Division at a cost of Rs. 1280.40 Lakh. GD clock, LED Display Board & speakers in Waiting Room of 8 stations & Auto announcement., Counter Communication and passenger operated enquiry terminal at all D category stations of Izzatnagar at a cost of Rs. 87.88 Lakh. GProvision of facilities for differently abled persons on 16 D class & 27 E Class stations of Izzatnagar Division at a cost of Rs. 262.87 lakh. ROB work near Jhinjhak station

Jhinjhak Station FOB at Kannauj

Station Name Board in LED & Stainless Steel Bench at Kannauj Station Circulating area at Kannauj