Utility Scale Wind Turbine Design Issues
Bruce Bailey, President AWS Truewind, LLC 255 Fuller Road Albany, NY 12203 [email protected]
Talk Topics
Wind Turbine Components
Wind Plant Components
Wind Speed vs. Power Production
Project Development Steps
Agreements Needed To Develop
Offshore Wind Energy
Wind Turbine Components
Composite Blades Gearbox, Generator and Power Electronics
Rotor Hub height Diameter 70-90 m 65-80 m nacelle
Rotor RPM ~10-20 Tubular Tower Automatic Pitch blade Control
steel tower
padmount transformer Inverted T-slab foundation foundation Nacelle for 1.65-MW Turbine What’s Inside? Technology Trends
Larger Rotors » 80-100 m Higher Ratings » >2 MW on land » >4 MW offshore Taller Towers » 80-100 m Variable Speed Direct Drive » No gearbox Onboard Cranes Climate Packages Wind Plant Components
Electrical Substation Wind Turbine
Underground electric system and fiber optic communications Service Road Crane Pad
11.5 MW Madison Wind Power Plant Typical Wind Plant Layout On-Site (Residential) Wind Systems
10 kW Wind Turbine TYPICAL SMALL SYSTEM 10 kW (23 ft. Rotor Diameter) Rural Site, 1 Acre or More
Connected to Facility Wiring 24 m (80 ft) GuyedTower Produces ~ 13,000 kWh per Year Excess Power Sold to Utility
(PURPA) Safety Cummulative Switch Production Meter Either Net Metering or Very Low Power Processing AC Load Buy-Back Rate Unit (Inverter) Center Cost: ~ $45,000 - $60,000 Relationship of Wind Speed to Power Production
Rated Speed GE 1.5xle - 1.5 MW 1600
1400
1200 Wind Speed Power Output 1000
kW 800
600 Turbine Output(kW) Turbine 400
200
0 0.0 5.0 10.0 15.0 20.0 25.0 Wind Speed (m /s)
Cut-In Speed Cut-Out Speed 1 m/s = 2.24 mph 1 mph = .447 m/s Wind Plant Output & Maintenance
Typical capacity factors are 30-40% at good wind sites Wind speeds are above cut-in >85% of the time Turbines are available to generate >97% of time Scheduled maintenance occurs 1-2 times per year ~1 skilled O&M job for every 10 turbines installed Project Development Steps
Site Selection Resource Definition Project Design & Engineering Permitting Financing Construction Operations » 3-5 yr period from site selection to commissioning Land Acquisition
Rule of thumb - about 50 acres to the MW Usually Lease Agreement Option on the land first (about $3 to $5 per acre?) Much land is currently optioned Lease cost (~ $3000 - $5000 per turbine per year) Can include royalty payment option Agreements Needed By Developer
Land acquisition Permits (local zoning & building; state) Tax Payments Turbine Purchase & Warranty Interconnection Power Purchase Financing Maintenance
Planning Uncertainties
Permitting » visual (NIMBY) » bird & bat studies Transmission » access & capacity constraints » interconnection study queue backlog Schedule Delays » risk of missing incentive deadlines Weather
Wind Forecasting
Required for scheduling and dispatching of wind plant output in a growing number of energy markets Adds costs to wind plant operations ($0.08-.20/MWh) Reduces ancillary service costs to grid system operator Reduces/eliminates risks of imbalance charges
California Independent System Operator Control Room Conclusions
• Wind technologies continue to mature and achieve acceptance • Costs are competitive • Optimization of component sizes • New techniques reduce uncertainty in siting and production forecasting • Large majority of public favors wind energy, but wider deployment is triggering NIMBY opposition • Transmission constraints & inconsistent government policies will limit rate of growth