<<

Utility Scale Turbine Design Issues

Bruce Bailey, President AWS Truewind, LLC 255 Fuller Road Albany, NY 12203 [email protected]

Talk Topics

Components

 Wind Plant Components

 Wind Speed vs. Power Production

 Project Development Steps

 Agreements Needed To Develop

 Offshore Wind Energy

Wind Turbine Components

Composite Blades Gearbox, Generator and Power Electronics

Rotor Hub height Diameter 70-90 m 65-80 m

Rotor RPM ~10-20 Tubular Tower Automatic Pitch blade Control

steel tower

padmount transformer Inverted T-slab foundation Nacelle for 1.65-MW Turbine What’s Inside? Technology Trends

 Larger Rotors » 80-100 m  Higher Ratings » >2 MW on land » >4 MW offshore  Taller Towers » 80-100 m  Variable Speed  Direct Drive » No gearbox  Onboard Cranes  Climate Packages Wind Plant Components

Electrical Substation Wind Turbine

Underground electric system and fiber optic communications Service Road Crane Pad

11.5 MW Madison Plant Typical Wind Plant Layout On-Site (Residential) Wind Systems

10 kW Wind Turbine TYPICAL SMALL SYSTEM  10 kW (23 ft. Rotor Diameter)  Rural Site, 1 Acre or More

 Connected to Facility Wiring 24 m (80 ft) GuyedTower  Produces ~ 13,000 kWh per Year  Excess Power Sold to Utility

(PURPA) Safety Cummulative Switch Production Meter  Either Net Metering or Very Low Power Processing AC Load Buy-Back Rate Unit (Inverter) Center  Cost: ~ $45,000 - $60,000 Relationship of Wind Speed to Power Production

Rated Speed GE 1.5xle - 1.5 MW 1600

1400

1200 Wind Speed Power Output 1000

kW 800

600 Turbine Output(kW) Turbine 400

200

0 0.0 5.0 10.0 15.0 20.0 25.0 Wind Speed (m /s)

Cut-In Speed Cut-Out Speed 1 m/s = 2.24 mph 1 mph = .447 m/s Wind Plant Output & Maintenance

 Typical capacity factors are 30-40% at good wind sites  Wind speeds are above cut-in >85% of the time  Turbines are available to generate >97% of time  Scheduled maintenance occurs 1-2 times per year  ~1 skilled O&M job for every 10 turbines installed Project Development Steps

 Site Selection  Resource Definition  Project Design & Engineering  Permitting  Financing  Construction  Operations » 3-5 yr period from site selection to commissioning Land Acquisition

 Rule of thumb - about 50 acres to the MW  Usually Lease Agreement  Option on the land first (about $3 to $5 per acre?) Much land is currently optioned  Lease cost (~ $3000 - $5000 per turbine per year)  Can include royalty payment option Agreements Needed By Developer

 Land acquisition  Permits (local zoning & building; state)  Tax Payments  Turbine Purchase & Warranty  Interconnection  Power Purchase  Financing  Maintenance

Planning Uncertainties

 Permitting » visual (NIMBY) » bird & bat studies  » access & capacity constraints » interconnection study queue backlog  Schedule Delays » risk of missing incentive deadlines  Weather

Wind Forecasting

 Required for scheduling and dispatching of wind plant output in a growing number of energy markets  Adds costs to wind plant operations ($0.08-.20/MWh)  Reduces ancillary service costs to grid system operator  Reduces/eliminates risks of imbalance charges

California Independent System Operator Control Room Conclusions

• Wind technologies continue to mature and achieve acceptance • Costs are competitive • Optimization of component sizes • New techniques reduce uncertainty in siting and production forecasting • Large majority of public favors wind energy, but wider deployment is triggering NIMBY opposition • Transmission constraints & inconsistent government policies will limit rate of growth