U.S. ARMY CORPS OF ENGINEERS CIVIL WORKS PROGRAM UPDATE

Waterways Council, Inc Washington DC February 13, 2019

Edward E. Belk, Jr PE Chief, Civil Works Programs Integration Division Headquarters, US Army Corps of Engineers World-Class Delivery… Real-World Impact! Army Civil Works National Leadership

Department of the Army

LTG Todd Semonite HON R.D. James Ryan Fisher Joe Bentz, SES David Leach, SES Deana Funderburk Chief of Engineers ASA(CW) PDASA DASA, Mgt/Budg DASA, Proj Review DASA, Policy/Leg

HQ, US Army Corps of Engineers MG Scott Spellmon James Dalton, SES Eddie Belk, SES Dr. Larry McCallister, SES Joe Redican DCG-Civil/Emerg Ops Director of Civil Works Chief, Programs Chief, Engineering & Const Acting Chief, Plng/Policy

Corps Enterprise Leadership

Brenda Johnson-Turner, SES Real Estate Karen Baker, SES Environmental Sally Pfenning, SES IIS Dr David Pittman, SES ERDC David Cooper, SES Chief Counsel BG Michael Hoskins Contracting Tom Smith, SES Ray Alexander, SES Dr. Joe Manous Chief, Ops/Reg Director, Contingency Ops Director Institute for Water Resources Army Civil Works RegionalLRD Leadership CG: MG Mark Toy NAD Alaska MVD PD: Steve Durrett CG: MG Jeffrey Milhorn CG: MG Rick Kaiser RBD: Phil Johnson (A) PD: Wes Coleman (A) PD: Jim Bodron NWD RBD: Rhino Reinhart RBD: Tom Holden CG: BG Peter Helmlinger PD: Dave Ponganis RBD: Eric Hansen Seattle North Atlantic Division (NAD) Great Lakes & New Walla England Portland Walla Ohio River St. Paul Division Northwestern (LRD) Division (NWD) Detroit Buffalo New York Rock Philadelphia Island Chicago Pittsburgh Omaha Cincinnati Baltimore Sacramento Hunting- Middle East San South Pacific ton (Winchester, VA) Francisco Division (SPD) Kansas City St. Norfolk Louis Louisville

Little Nashville Wilmington Los Tulsa Angeles Rock Memphis SPD Southwestern CO: COL Kimberly Colloton Albuquerque Division (SWD) Atlanta Charleston PD: Cheree Peterson RBD: John Moreno Vicks- Savannah burg Ft. Worth Mobile Jacksonville Honolulu New Orleans South Atlantic Pacific Ocean Galveston Division Division (POD) Mississippi (SAD) Valley Division (MVD) POD SWD CG: BG Tom Tickner SAD CG: BG Paul Owen CG: BG Diana Holland PD: Gene Ban PD: Mark Mazzanti RBD: Gary Kitkowski PD: Al Lee RBD: Pete Perez RBD: Tab Brown SECURING OUR NATION’S FUTURE THROUGH WATER Navigation - Commerce, Int’l Markets, Trade USACE Operates 25,000 miles of Commercial Waterways; Generates $18 B Annually;

370 + Million Visits Annually Supports 20% of US Jobs, 1/3 of GDP; Generate $16B in Economic Weather – Related Disasters Transportation = Decisive US Competitive Advantage 3X in Last 30 years Activity ∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙ Flood and Disaster Risk Reduction USACE Prevents ~ $10 in Flood Damages per $1 Invested; 14,700 Miles of Levees  12,700 Miles = Local O&M; 700 USACE Dams vs 87,000 National Inventory of Dams 2008-2017, Prevented ∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙ $873B in Total Damages Environment - Ecosystem Restoration and Environmental Stewardship ∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙ Hydropower - Inexpensive, Sustainable USACE is the Nation’s Largest Renewable Energy Producer 50% of Americans Live Move 98% US Imports and w/in of 25% of US Hydropower, 3% of Total US Electricity 50 Miles Coast ∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙ Exports @ $2T / Year Drinking Water USACE Produces 6.5 Billion Gallons per Day ∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙

404 Lakes / Rivers Quality of Life – Local Economic Engines Drinking Water for in 43 States USACE is Major Federal Provider of Outdoor 96 Million People Recreation, Contributing > $11 B to Local Economies ∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙ Disaster Preparation/Response ∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙∙ 20% US Jobs and 1/3 GDP 25% US Hydropower and in Waterborne Commerce Regulatory 3% Total US Electricity Civil Works Challenges & Opportunities

. Infrastructure Investment = Global Challenge

. Corps Civil Works Portfolio: 3,000+ Operational Projects, with Replacement Value of Approx $268B

. Expanding Demands for CW Infrastructure Maintenance, Operations, and Capital Investment − Civil Works New Construction Backlog  $ 76B − Dam Safety Backlog (DSAC 1 & 2)  $ 20B − Some Negative Perf Trends Across Portfolio − Aging CW Systems  Facing ReCap Phase of Lifecycle − $2.5B Deferred Maintenance Backlog

• Expanding Demands Serviced by ~$4.6B Annual Budget Nationally…..Requirements Significantly Outpacing Resources

Civil Works Investment Trends (Excludes Supplemental Funding)

$8,000 FY 2019 Historic Budget and Appropriations Trends Appropriation $6,998 M $7,000 Annual Resources that Help Service:

~$268B Portfolio of CW Operational Assets FY 2019 Budget $6,000 ~$ 96B CW Construction Portfolio $4,785M

$5,000

$4,000

Millions $3,000

$2,000

$1,000

$0 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019

INVESTIGATIONS CONSTRUCTION O&M MR&T REGULATORY GENERAL EXPENSE FC&CE FUSRAP ASA(CW) HISTORIC APPROPRIATIONS

FY19 Appropriation is ~46% Increase above FY19 Budget FY 2019 Appropriation ($ Millions) Total: $6.998 Billion

Flood & Coastal by Account by Business Line Emergencies $35 M Water Supply $12M FUSRAP $150 M

Navigation, CG GI Coastal Construction MR&T O&M $2,046 M $2,183M Operation & Flood Damage FUSRAP Reduction Maintenance Reg Navigation, 3,739M $1,965 MFCCE Exp Recreation Inland

$260 M $1,249 M

Investigations $125 M

Emergency Management $40 M ** Includes Office of Asst. SecArmy (Civil Works)

BUILDING STRONG® Major Construction Projects in FY19 13 Skokomish R. Mud Mtn. Dam Columbia R. 84 Work Plan (Over $10m) at Mouth 28 46 Columbia R. Fish Mitigation Fargo-Moorhead 35 Sault Ste. Marie Lock Replacement 32 Missouri R. Fish & Boston Hbr. Wildlife Recovery 30 Upper Mississippi 37 33 River Restoration Maywood East Br. 39 Yuba R. Basin 36 Clarion R. Lake Del. R. 29 Raritan Luckey 23 29 Scarmento R.Bank Protection 24 Sandy Hook Hamilton 20 La Grange 33 City 13 Monongahela 27 12 Great Egg 64 Natomas Basin Lock & Dam 57 R. L&D 2, 3 & 4 89 DuPont 21 Poplar Island Manhattan 18 St. Louis 33 96 E. St. Louis 118 Isabella Dam Olmsted Kentucky Lock & Dam Lock & Dam 50 44 15 Santa Ana River Mainstem 89 Chickamauga Lock Lower Miss. R. Revetments (MR&T) 71 41 Charleston Hbr. Lower Miss. R. Levees (MR&T) 40 Savannah Hbr. Flood Risk Management Lewisville Dam 55 111

Cedar Bayou Aquatic Ecosystem Restoration 10 46 Jacksonville Hbr. Brays Bayou & Tribs. 16 10 Calcasieu R. & Pass & Tribs. 18 Navigation 17 15 S.E. Louisiana Sabine- Neches Herbert Hoover Dike 96 FUSRAP Corpus Christi Waterway Ship Channel 71 S. Fla. Ecosystem Restoration 104

Navigation New Construction Start in FY 19 (3) Navigation New Construction Start in FY 18 (2) Major Construction Projects in FY 19 Budget (Over $10m)

Columbia R. 25 Mud Mtn. Dam at Mouth 28 Columbia R. 46 Fish Mitigation

Missouri R. Fish & Boston Hbr. 15 Wildlife Recovery 10 Upper Mississippi 33 River Restoration Maywood 35 Yuba River Basin 37 Luckey 16 42 American River 14 15 E. Br. Clarion R. Lake DuPont 21 Poplar Island 26 St. Louis 118 Isabella Lake Olmsted 40 Rough R. Lake Lock & Dam 35 15 Santa Ana River 29 Center Hill Lake Lower Miss. R. Mainstem (MR&T) 109

Lewisville Dam Savannah Hbr. Flood Risk Management 55 60

Aquatic Ecosystem Restoration

Buffalo Bayou & Tribs. 12 Navigation Herbert Hoover Dike 96 FUSRAP 13 Corpus Christi Ship Channel S. Fla. Ecosystem Multipurpose Restoration 68 Key Budgeting Metrics • Construction • All – Meet Environmental, Legal, Mitigation Requirements • FRM, NAV, HYDRO – Benefit to Cost Ratio (BCR) • FRM, NAV – Dam Safety & Seepage Stability (Continuing DSAC 1 & 2) • FRM – Risk to Life Index (Warning Time, Flow, Depth, etc) • AER – Point Values for Loss Prevention of Significant Natural Resources

• Operation and Maintenance • FRM, NAV, HYDRO – Risk & Consequences Assessment • AER, ENS, FRM, NAV, HYDRO – Biological Opinion; Efficiency of habitat acres improved. • REC – Park Capacity and Facility Condition Index, Visitation … • NAV – Tonnage movements (Harbors: tons; Waterways: ton-miles)

• All Accounts • Continuing Work; New Work; Completing Work; Years to Complete • ESA & Regulatory Compliance • Health, Safety, Caretaker, Legal, Subsistence

BUILDING STRONG® BUILDING STRONG® FY18 EMERGENCY SUPPLEMENTAL: $17.4B

 Public Law 115-123, Bipartisan Act of 2018 (enacted 9 Feb 2018)  Investigations  $135M, 38 Study Activities (5 Ongoing; 33 Not-ongoing)  Initiate and/or Complete Current/Future Auth Studies, 100% Fed  $75M for HIM Impacted States (5 States/2 Territories) + Up to $60M for Other Impacted States (Total 33/3)  Construction  $15.1B, 58 Projects (32 Ongoing; 26 Not-ongoing)  $15B to Construct FRM Projects: Already Auth; Future Auth; Chief’s Report as of 9 Feb (not yet auth) w/ASA determination; Studied using PL 115-123 Investigations funds w/ASA determination  $10.4B for HIM Impacted States (5/2); $4.6B for Other Impacted States (Total 33/3)  Projects in PR/VI 100% Fed; Suppl $$ applied to ‘On-going const’ projects cost-shared at 100% Fed; other projects (NOT ongoing) - normal cost-share applies except that the non-Federal cash contributions may be financed payable option over a 30 year finance period upon project completion  Up to $50M for FRM CAP Projects - 7 Projects (5 Ongoing; 2 Not-Ongoing)  Mississippi Rivers & Tributaries  $770M Total - $400M, 2 Ongoing Long-term Projects (Channels/Levees) / $370M, 10 Short-term Projects  Already Auth and/or Auth after enactment for emergencies  Operations & Maintenance  $608M, 90 Projects (Short-term Emergency Repairs)  Dredge Fed Nav Channels and Repair Damages  Flood Control & Coastal Emergencies  $810M, 81 Projects (Short-term Emergency Repairs)  Includes Auth Shore Protection Projects to Full Project Profile at Full Federal Expense  Expenses  $20M

As of 15 Jan 2019 11 SUPPL CONSTRUCTION PROJECTS

13 Yuba R. Basin S. San Cedar Rapids Francisco 1566 American River 117 Shoreline IA - $0.12B 177 216 Folsom Dam Lower Mud R. 96 74 Tule R., L. Success KS - $0.5B Bluestone Lake Martin 80 574 Kansas City WV - $0.7B Isabella Dam 454 Johnson Co. 118 20 McDowell Co. 258 Bois Brule 11 KY - $.2B MO - $.01B Santa Ana River 16 Mill Creek 161 Mainstem CA - $2.5B Miss, R. Channel Improvement 99 TN - $.16B Pawleys Is 9 NM - $.09B Miss, R. Channel Improvement Folly Beach 2 Colleton Co. Edisto Is 22 Lewisville Lake 147 SC - $.03B 9 Alamogordo 92 Tybee Isl. 13 Dallas Floodway 223 GA - $.01B Nassau Co. Dallas Floodway Extension 53 2 Duval Co. Comite R. 2 Buf Bayou Grand 343 37 2 St. Johns Co. (2) & Tribs 1 Isle E. Baton 17 Flagler Co. Ala Wai Canal 345 Brays Bayou 75 255 15 760 Rouge Brevard Co. Hunting Bayou 2 65 20 St. Lucie Co. HI - $0.3B Clear Creek 3957 W. Shore L. TX - $4.9B 295 Pontchartrain Herbert Hoover Dike 25 2 Palm Beach Co. (2) to 514 60 Construction Projects (minus CAP) 73 45 LA - $1.4B Manatee Co. 14 2 Broward Co. Sarasota Co. Lower Colorado R. White Oak Bayou 2 158 Dade Co. * 34 Ongoing CN (PPA Amendments); Lee Co. 2 4 Executed; 8 Not Req’d; 9 in Field; 13 Left FL - $0.8B PR - $2.5B * 26 Not Ongoing CN (PPA Negotiations); Rio Puerto Nuevo 1552 1 Executed; 13 in Field; 12 Left Rio de la Plata 500 de Loiza 250 * Surveys/Design Underway Rio Guanajobo at Mayaguez 60 * Sponsors  ROW and Relocations Rio Grande de Arecibo 83 Rio Nigua at Salinas 60 Age of Corps Lock Portfolio in 2020

0-9 1 10-19 7 20-29 12

(Years) 30-39 15 40-49 38 2020 50-59 37 60-69 28 Age in 70-79 35 80+ 69

0 10 20 30 40 50 60 Number of Operational Lock Chambers *Includes All Operational Deep and Shallow Draft Corps and TVA Navigation Locks and Control Structures.

BUILDING STRONG® National Lock Portfolio Service Trends Main Chamber Mechanical Unavailable Hours (Events Longer than 1 Day) 1,200

1,000

800

600 Scheduled Hours Unscheduled

400

200

0 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Fiscal Year

Olmsted Locks and Dam US Army Corps of Engineers® Operational August 2018

What’s Next? US Army Corps of Engineers® Capital Investment Strategy….

Current Civil Works Realities • Traditional Funding and Delivery Models Increasingly Inadequate, More Agile Processes and Thinking Now Necessary

• Administration, Congress and Partners Increasingly Demanding Change in both Federal Permitting and Delivery of Federal Programs • Historic Level of Congressional Oversight Engagements • More Partners Turning to Alternative Delivery Models

• Significant Challenges and Opportunities • Historic FY18 and FY 19 Appropriation Levels • Historic Storm Supplemental ($17.4B) • Infrastructure Investment an Administration and Congressional Priority

• How is the Corps Responding? • Drive to Deliver on Projects, Programs, Commitments • Powering Down Decision-Making • Working Closely with and Listening to Partners • Revolutionizing Civil Works

BUILDING STRONG® Start and Finish Projects Faster Leverage New Tools/Processes Streamline; Eliminate Duplication Closing Thoughts • USACE Budget Continues to be Constrained, Addressing the Nation’s Infrastructure Investment Gap a Shared Federal, State and Local Responsibility

• The Corps Doesn’t Deliver Anything by Itself… Critical that we not Lose Focus on Our Partners, Stakeholders, and our Commitments

• Navigation Investment is Essential for the Nation’s Global Competiveness and Economic Security

• America’s Marine Transportation System Infrastructure Must be a National Priority to Assure Adequate Levels of Investment

• Navigation Investment is Key to National Economy, Jobs, and Exports

BUILDING STRONG® Thank You!!