AGENDA ITEM 5.1
DR/01/17
committee DEVELOPMENT & REGULATION date 27 January 2017
MINERALS AND WASTE DEVELOPMENT Proposal: For the northern quarry void and plant site including the restoration of the northern quarry void using inert materials to agriculture and nature conservation interest with new public rights of way, the installation and operation of an inert waste recycling facility in the plant site for the production of secondary aggregate followed by the restoration of the plant site to nature conservation interest and the creation of an area of biodiversity compensation habitat Location: Land at Sandon Quarry Molrams Lane, Sandon Ref: ESS/08/16/CHL Applicant: Brett Aggregates Limited Report by Acting Head of County Planning Enquiries to: Terry Burns Tel: 03330 136440 The full application can be viewed at www.essex.gov.uk/viewplanning
Reproduced from the Ordnance Survey Map with the permission of the Controller of Her Majesty’s Stationery Office, Crown Copyright reserved Essex County Council, Chelmsford Licence L000 19602
1. BACKGROUND & SITE
Sandon Quarry is a former sand and gravel site situated South East of Sandon Village and separated from it by the A12T.
Access to the quarry complex is taken off a junction with Church Street and Molrams Lane, these being a slip road onto the A1114. The A1114 itself is some 650 metres north west of its own access with the A12 (T) and A130. From the junction entrance an internal haul road runs eastwards for some 650 metres, crossing both formerly worked mineral land (part agriculture and part now designed to accommodate an area of biodiversity compensation habitat associated with the southern void workings referred to below) and the A12 (T) to then access the site areas identified above.
The Sandon Quarry complex can be considered to comprise a number of discrete areas these being referred to as:
• Northern quarry void – the subject of this application, and situated between the A12 (T) and Sandon Brook. This area is a former quarry extraction void that was then used for some silt disposal and is now partially filled with water. There is a 2 metre high soil bund extending around the north western perimeter of the void and a 5 metre high stockpile located adjacent the voids north eastern perimeter. Adjacent the A12 (T) the void perimeter is at about 27 – 28m Above Ordnance Datum (AOD) with water level maintained at around 10 m AOD. The base of the void is between 4 – 8 m AOD. Side slopes are
described as generally between 1 vertical (v) and 2-4 horizontal (h). Steeper slopes are located predominantly on the north, northeast and south. The applicant confirms that there have been signs of historic instability of the slopes and that during construction of the A12 (T) slope failure resulted in extensive slope remediation works and underdrainage provision. The applicant confirms that records from the Resident Engineer for the road construction indicated drainage measures being constructed from a bench about 19m AOD to below the base of the quarry floor which is anticipated has been partially filled to below -3m AOD and water levels of between -2m AOD to +2m AOD.
• This void is designated as a Local Wildlife Site (LoWS) due to its invertebrate interest and associated habitats established post mineral extraction. Land immediately to the north of the void and within the application boundary comprises grassland that was previously worked and restored. Within this grassland area, some ponds have previously been created for nature conservation translocation associated with the southern void permission. Water levels within the northern void are maintained, given proximity of the A12 (T), by pumping from the southern void into the eastern arm of the Sandon Brook that flows through the complex.
• Southern Void – A former quarry void separated from the northern void by the main site haul road. This area is subject to an extant permission for the infilling with inert materials under ESS/30/11/CHL with restoration scheduled to be completed by December 2017. The restored land would then accommodate agriculture and woodland together with public rights of way.
• Former processing plant and stockpiling area. Situated east of Sandon Brook and accessed via a bridge on the site access road. This area comprises some redundant plant, hardstandings two ponds formerly used for water management and the site security caravan. The land previously accommodated mineral stockpiling, silt lagoons as well as a concrete batching plant.
The above three areas are located within a generally agricultural landscape of hedgerows, fields and mature trees. The Sandon Brook which flows south to north approaches the Sandon complex from the south and at this point comprises an eastern and western arm. The eastern arm of the Sandon Brook approaches the quarry complex from the south east and forms the eastern boundary of the southern void then crosses through the application land dividing the northern void area from the processing plant area. The brook then continues north forming the north eastern boundary of the northern void area before exiting the application land and joining the western arm of the brook just before Woodhill Road. The western arm of Sandon Brook first encounters the Sandon Complex when if flows beneath the haul road near the site entrance onto Molram's Lane then flows north east to flow beneath the A12(T) emerging the other side to form the north western boundary of the northern void. The brook then continues north to join with its eastern arm. At its closest point the eastern arm of the Sandon Brook lies 30 metres from the eastern edge of the northern void. Between the two void areas is situated the site weighbridge and portacabin style site office and car parking area. Further north framing the complex beyond the nature conservation ponds and some fields is Woodhall Road linking Sandon Village with Danbury. Immediately east of the processing plant area lies a small industrial estate
that separates the plant area from Mayes Road that provides a link between Woodhall Road and Butts Green located south east of the quarry complex. A number of residential properties lie either side of Mayes Road separated by fields and hedgerows from the quarry complex.
Sandon Hall (c 250 m south of southern void) set in its own grounds forms the quarry complex’s southern boundary.
Nearest properties are some 120 metres to the north west beyond the A12 in Sandon. Sandon Lodge (c180 m) and Bridge Farm (c200 m) are located north and north east off Woodhall Road.
Bridge Cottage (20 m to south) and Brookside Diary (c40 m north) are located adjacent the site entrance on Molrams Lane.
The complex is affected by a number of public rights of way: Right of Way 232_7 passes through the site following the western bank of the eastern arm of the Sandon Brook crossing the haul road and continuing southwards to the east of the southern void and past Sandon Hall. Public Right of Way 232_5 approaches the Sandon complex from the west follows part of the site haul road before linking at the A12(T) overbridge with Right of Way 232_26 which follows the western boundary line of the A12(T) northwards to link with Sandon Village. Public Right of Way 232_5 continues over the bridge before turning southwards before skirting around Sandon Hall. Planning History
The Sandon Quarry complex has a long mineral and waste planning history. Still of relevance is an Interim Development Order (ref no: IDO/GHL/2/92A) known as an IDO. This Order covered most of the worked out site and also extended over the land identified as the plant processing area. The IDO permits mineral extraction until 2042 with restoration through infilling with inert materials to restore the land back to a grazing and amenity afteruse. The status of the land affected by the IDO is referred to in planning terms as currently being dormant.
Of the two void areas the applicant confirms that the northern void has no restoration commitment and therefore there is a necessity, given the proximity of the A12 (T), for continual dewatering to maintain water levels below natural ground levels. Currently water levels in the northern void are maintained by pumping from the southern void (so allowing natural flow through the intervening strata) and discharging into the eastern arm of the Sandon Brook.
Planning approval for infilling the southern void with restoration to agriculture and woodland under ESS/21/92/CHL was subsequently varied by ESS/30/11/CHL which extended the restoration date until 31 st December 2017. Traffic associated with the southern void development are subject to a HGV routeing agreement such that vehicles approaching from the south on the A1114 “ uses the northbound off slip and turns right into Southend Road to cross over the A1114 before travelling south down Molrams Lane and turning left into Sandon Quarry. Traffic arriving at Sandon Quarry from the north on the A1114 leaves on the southbound off slip before turning right onto Molrams Lane and immediately left into the site. All traffic leaving the site turns left onto the southbound slip road to the A1114. Vehicles leaving the site and needing to travel north use the A1114/A12(T)/A130 junction to turn around and travel north on
the A111 4”.
There are a number of ancillary permissions related to site fencing as well as the siting of a security caravan within the complex. The Essex and Southend Waste Local Plan Adopted September 2001 identifies the Sandon quarry as Site LNI.2 and WM6 these designations encompass the whole of the complex east of the A12 (T) (the present application footprint plus the southern void). The Plan identified the land as suitable for inert landfill as well as a permanent waste management facility.
Within the Essex County Council Replacement Waste Local Plan Pre Submission document June 2016; two land parcels within the Sandon Quarry complex have been put forward known as:
• Site L(i)6 identified on Map 16 in the plan as “West” comprising the northern and southern void areas although the Plan acknowledges the active southern void landfilling and identifies the northern void as suitable for inert infilling. • Site W7 known as Sandon East comprising the plant site area and identified as suitable for inert waste recycling capacity with a permanent lifespan.
The Pre Submission Plan identifies the following specific issues to be addressed for the Sandon West parcel as being:
• Filling of the northern void identified as a County Wildlife Site would require some form of biodiversity offsetting. • Dust mitigation, operating hour restrictions as well as noise generation. • Any extraction requirements taking place with regard to underground infrastructure.
As part of the applicant’s preparation for this application they undertook a Screening Request under the Town and Country Planning (Environmental Impact Assessment) (England and Wales) Regulations 2011. As a result, the Mineral Planning Authority issued a Screening Opinion in early 2015 to the effect that an Environmental Impact Assessment (EIA) was necessary. A request for a Scoping opinion was submitted by the applicant concurrently with the Screening Request. The Scoping Opinion response included in its contents that the applicant address in particular certain issues put forward during the consultation process.
As a result of the scoping exercise the EIA was prepared and provided the background information against which the Environmental Statement (ES) as referred to in this report, was prepared.
2. PROPOS AL
The application footprint of some 25.4 hectares comprises the haul road, northern void, including the pond area location, and the former processing plant area.
The application seeks to restore the northern void through infilling with inert materials and residues from inert waste recycling facility located within the former processing plant area. Restoration of the northern void would be to agriculture and nature conservation with establishment of new public rights of way.
The applicant proposes:
• Replacement of the site offices and provision of additional car parking and possible second weighbridge. • Placement of inert waste recycling plant within the former processing plant area (referred to as the plant area in the rest of this report) including crusher and screener, stockpiling and creation of a screening bund. Products of the crushing/screening to produce secondary aggregate. • Secondary aggregate to be used off site or, subject to approval on a separate standalone planning application that would be submitted should planning approval be forthcoming for this present application, for onsite processing into concrete known as hydraulically bound material (HBM). Both the recycling plant and HBM plant, if forthcoming, would be removed at the cessation of infilling activities. • Inert residues from the inert recycling plant, together with non-recyclable imported material, to be deposited within northern void to achieve restoration. • The recycling plant would handle some 300,000 tonnes per annum of inert waste with an equal split of some 150,000 tonnes being recycled and the rest comprising non recoverable material being used in the infilling of the void. Restoration would be achieved in 8.5 years with operations commencing January 2018. • Traffic generation predicted at 164 HGV movements (82 in/82 out) per day. • Operating hours same as existing southern void operational hours of: 0700 – 1800 hours Mondays to Fridays 0700 – 1300 hours Saturdays.
A Biodiversity Compensation Area (BCA) would be prepared as soon after planning permission, and licencing from Natural England, was secured in order to allow translocation areas to establish allowing key habitats to be replaced in the BCA as restoration work progress and habitat in the northern void is lost. The applicant notes that the existing compensatory habitat in the Northern Void has established in a relatively short timescale and replacement habitat should therefore be achievable. The applicant proposes to adopt a limited management to speed up the process of habitat establishment.
The BCA would be located within the eastern half of the plant area. Any hardsurfacing would be broken up and removed from within the confines of the biodiversity area. The rest of the plant site (that land proposed to accommodate the recycling and HDM facilities) would be integrated into the biodiversity compensation area following removal of the infrastructure at the end of infilling activities. The mitigation area would be created a minimum of 12 months prior to the commencement of infilling with “ the creation of reed swamp, exposed substrates and exposures created by soil stripping and disturbance; species rich grassland, tall ruderal vegetation including species known to have associations with scarce invertebrates species recorded at the site. An area of existing sparse ephemeral over bare ground will be retained. Log piles and areas of shrub will be created in several locations. Areas of shallow pools and open water will also be created. Isolated trees within the biodiversity compensation area along with existing woodland, semi-improved grassland, ponds and associated vegetation will be retained as far as possible around the periphery of the area ”.
To achieve the aim of ceasing dewatering whilst infilling the applicant has identified the need for addressing the integrity of the remediated slope stability associated with the A12 (T).
The applicant has confirmed two main considerations arising from the proposal; the first being that complete dewatering of the northern void in reasonable timescales “may not allow pore water pressures within the slopes at the site including the A12 (T) to dissipate and may cause slope failure. The second is that filling the northern quarry void with low permeability inert materials may disrupt the pathways by which the existing A12 (T) slope drainage drains to the permeable strata underlying the site and allow groundwater pressures to build up behind the remediated A12 (T) slope which could possibly cause slope failure”. In order to mitigate potential slope failure the proposal would be to undertake controlled dewatering to maintain water level whilst infilling progressed into the water. Through the monitoring/pumping programme the mitigation measures would provide for a stable pore water pressure in the A12 (T) slope during infilling.
The applicant states that to mitigate potential slope instability caused by the build up of groundwater pressure behind the remediated A12(T) slope, the proposal would be to use granular material and a sump/dewatering system within the granular fill to allow dewatering as necessary. The granular material would allow a pathway for water to move away from the slope with the sump/dewatering system in place to control slope water levels. Once the western part of the void is filled above water level then general inert material would progress for the rest of the void. Ongoing monitoring would be put in place to confirm effectiveness.
Restoration of the void is proposed in four phases.
Phase 1- Granular fill to be placed within the western section of the water body as described above. The Phase 1 infilling to above water level would ensure a supported toe being created on the A12 (T) slope whilst allowing its dewatering. The A12 (T) slope gradient would be slackened through extending its toe. The point of change for Phase 1 to stop and Phase 2 use of general inert material would be agreed with Highways England given the slope proximity to the A12(T).
Phase 2 – The remaining area of the northern void would be infilled to a level above current water level and general infill material used given the already installed sump and dewatering system. Water levels would be determined in accordance with the monitoring programme once infilling reaches above water levels dewatering would no longer be necessary.
Phase 3 – Continued infilling and as elevation increases the proposal would see an extension of the sump by provision of a riser pipe up the A12(T) slope to provide for continued controlled dewatering to ensure control of potential water build up behind the slope. At the end of Phase 3 the mass of inert material should exceed the natural rebound groundwater pressures so removing further dewatering. Reaching this state would be agreed with Highways England.
Phase 4 – Would be the completion of the infilling to final restoration levels. The applicant acknowledges the potential for dust arising from the infilling activities and that provision of a water bower would be utilised.
Restoration of Northern Void
The proposal would seek to achieve a profile of landform approximately 32m AOD in the south to approximately 25m AOD in the north. Restoration levels being designed not only to reflect surrounding landform but also to address anticipated recovered groundwater levels of up to 25m AOD.
The applicant confirms that a fundamental objective of the restoration is to recreate habitats found within the Northern Void. Suitable clay and sands would be sourced from stockpiles to be used in recreating suitable substrates to be sown with species rich chalk grassland seed and subsequently managed by grazing. Shallow ponds and sandy substrate would be created. The existing 2 metre high bund would be partially used in restoration to recreate landform whilst a section of it would be retained in place to enable continued use by protected species. Existing trees along the eastern arm of Sandon Brook would be retained where possible, New hedgerows would be installed and natural regeneration of woodland and shrub encouraged.
The proposal would envisage natural colonisation of invertebrates from the BCA adjacent the restored Northern Void. Where possible progressive restoration planting would take place as restoration material becomes available. Following restoration, circular public rights of way would be provided both around and through the northern void footprint allowing connection to the existing rights of way network.
The plant site infrastructure would be removed and the land here restored into the BCA. The bailey bridge would be retained post infilling for future management access of the plant area.
[For clarity the originally submitted Restoration plan has been revised such that the latest revision Restoration Plan (1910/005 Rev: K) now clarifies the landuse within the northern void area as being species rich grazed grassland and not agriculture as was originally depicted on earlier plans. Use of the word “agriculture” remains in the application titling however, should planning approval be forthcoming, the above referred to restoration plan together with a recommended legal agreement would clarify the afteruse parcels of the land ]
The applicant has, in respect of justifying the application proposal stated that there is a need to maintain a low level of water in the void due to proximity of the A12 and so to avoid the pumping it is proposed to infill the void area.
The applicant refers to national and local planning policy supporting restoration and regeneration of former mineral workings where beneficial afteruse arises for environment, biodiversity and local communities. The applicant sees the restored land as achieving nature conservation and public amenity with new public rights of way. The recovery of secondary aggregate is supported in policy terms that recognise minerals are a finite resource and production and use of secondary aggregate is to be supported.
The applicant has considered the following alternatives and noted:
• Do nothing: The applicant notes that this would not deliver the proposed
comprehensive restoration and require continual dewatering that is not sustainable. Also would not provide opportunity for facilities to produce secondary aggregate which is supported in policy terms.
• Alternative locations: Application seeks to achieve the restoration of the void which cannot be down at alternative locations.
• Alternative methods of inert waste treatment: Applicant does not see practical alternative to use of recognised methods of producing secondary aggregate through use of mobile crusher/screening plant.
• Alternative restoration schemes: Proposed restoration scheme based on surrounding landuses, proximity of A12, ground water levels and need to deliver biodiverse habits and public access. Considered the scheme provides the optimum combination of such uses.
The Applicant considers that as the BCA and restoration of the plant site have been designed to be consistent with that habitat that would be lost then it is considered there are no alternatives “which will deliver the equivalent range of habitats which are appropriate for the site setting. The Biodiversity Impact Assessment Calculator demonstrates that that the scheme can reach a position of “no net loss” of biodiversity as per the guidance in the National Planning Policy Framework”. Overall there would be a small net biodiversity gain from the void restoration and BCA.
The applicant states that the timely determination of the present application would ensure continuity of infilling at the Sandon Quarry following the completion of the southern void and lead to the early restoration than currently consented for the plant processing area.
As part of the application the applicant undertook community engagement in the preparation of the application, including introductory talks with the local community and Sandon Parish Council that began in late 2014. Discussions have also taken place including requests for formal Screening and Scoping Opinions from Essex County Council as the application was recognised as exceeding the relevant thresholds of site hectares; proximity to controlled waters and type of development, for the application to be considered to require an Environmental Impact Assessment under the relevant Environmental Impact Assessment Regulations.
Details of the proposed development scheme were presented by the applicant to both Sandon Parish Council in February 2015 and the Local Community Liaison Group for the Sandon complex in May 2015 before the proposals were presented at a public exhibition on 12 th May 2015. The exhibition was advertised in the local newspaper, the Essex Chronicle, in April and May 2015; by way of site notices and directly with both Sandon Parish and neighbouring Parishes being notified.
The exhibition was attended by some 31 people with 22 leaving comments that were included in the application submission. These comments included:
• Would like to see reduced working timescale • Informative exhibition and information presented was useful in understanding proposal
• Clarified “disinformation” which may have appeared in local press. • Restoration seen as a community asset • An increase in public rights of way and upgrades to the bridleways. • Good use of land. • Post submission of the application and having reviewed consultees comments concerning the location of the proposed inert waste recycling facility (IWRF) the applicant proposed a re-siting of the plant. As part of the revision the applicant undertook meetings with the Waste Planning Authority, Sandon Parish Council and members of the local community to present the proposals before formal submission of the amendment.
The application subject of this report is supported by an Environmental Statement (ES) that has been informed through a formal Screening process. The ES assessments addressed with a summary of their findings, predicted impacts and mitigation measures outlined are set out below. The ES also included reference and some assessment of a proposed future application for a facility to manufacture hydraulically bound materials (HDM). The HDM plant application would follow any approval of this present application subject of this report. The HDM plant would be proposed within the plant site area adjacent to the inert recycling plant. Reference in this report therefore to the HDM plant and its environmental assessments considered as part of the larger ES for this present application are included in this report for information purposes. Any future application for the HDM facility would be considered on its merits at that time.
Traffic and Transportation
The assessment considered the baseline as the present highway system with access to the application area from the A1114 slip road. The existing routeing of traffic to and from using the southern void has been described earlier in the report.
The assessment confirmed that traffic surveys were undertaken, in May 2015, with automatic traffic counters being placed at locations along the A1114 and fully attended traffic count surveys at junctions in the vicinity of the application site were also carried out in May 2015.
The assessment noted that previous mineral traffic generated by the site has been in the order of 220 daily HGV movements (110 in/110 out). The southern void generates some 80 daily HGV movements.
It was also confirmed that the existing site operations are subject to a HGV Routeing Plan.
An assessment of environmental effects confirmed the proposed daily HGV generation as 164 movements (82 in/82 out), that the routeing agreement would remain in place and that operating times would not change from those presently permitted.
The assessment whilst noting the anticipated tonnage removal equating to some 30,000 20 tonne HGV’s per annum, and 15,000 per annum for secondary aggregate the assessment assumed the latter arriving at the site empty. In reality a proportion
would likely be backhauling. Over a working day the vehicle movements would be an average 16 per hour (8 in/8 out).
The assessment confirmed that site vehicle generation would add between 0.3% and 6.3% in the AM peak hours and between 0.3 and 9.0% in the PM peak hours. The percentage impacts on the local highway network junctions are considered to cause minimal impact. It is noted that with backhauling this is likely to be an over estimation.
The assessment considered the most recent past accident data over a four year period and this did not identify any accidents attributable with quarry traffic movements.
The assessment considered that a routeing plan would be maintained for this proposal.
In terms of cumulative impact the assessment addressed the future HDM application as being a recipient of some 50,000 tonnes of the proposed secondary aggregate generated by the inert recycling plant. Importation of some 5,280 tonnes of cement per annum and 660 tonnes of lime would be required and this would generate some 594 HGV movements per annum. The HDM plant would produce some 66,000 tonnes of HDM (utilising some 9,000 tonnes of water annually and sourced onsite) and generate some 6,600 HGV movements per annum.
The assessment stated that taking account of reduced secondary aggregate exported, importation of cement and lime and export of HDM the HGV daily generation would be 170 movements (85 in/85 out). The production of the HDM generating some 6 additional daily HGV movements.
The assessment considered that: use of the existing access entrance and haul road were appropriate; that the HGV routeing plan that already exists for the southern void activities would remain in place for this new development and, that overall there would not be an unacceptable impact arising in terms of highway safety or traffic generation.
Landscape and Visibility
The assessment undertaken included a landscape and visual impact assessment (LVIA) of potential effects on the local landscape character and quality, together with an assessment of the sites visibility from the surrounding area.
The assessment considered the baseline with a description of the landscape noting the Natural England countryside character listing for the application footprint as being within National Character Area 111 – Northern Thames Basin. At the county level, the landscape character designation is identified as D3 Danbury Hills and at the District level the landscape character is recorded as F12 East Hanningfield Wooded Farmland Landscape Character Area.
The assessment noted that for the county designation the character is represented amongst others by wooded hill and ridge housing, linear settlements of Little Baddow and Danbury, enclosures and an intricate landscape pattern consisting of commons, pastures, heathland and wooded habitat and arable farming fringing outer edges of
woodland.
The assessment noted that for the field survey undertaken for the LVIA it was found that Sandon Quarry was not typical of the landscape character due to previous mineral extraction and ongoing restoration activities. The LVIA assessed the sensitivity of the landscape to accommodate changes in character and value as a result of the proposal. The LVIA assessed the sensitivity as moderate
The assessment noted that only broad judgements can be made on assessing receptor sensitivity given individual subjectivity. The landscape character of the area is recognised as being of a high landscape value and not within any nationally important landscape designations. Land to the south west of the site and west of the A1114 is Green Belt and as a result of the presence of the Grade II* and Grade II listed buildings there is a high-medium landscape value. Similarly the same value exists because of the nature conservation interest.
Visually the assessment noted that the Zone of Visual Significance (ZVS) for the application footprint is restricted to a very limited area. Visual receptors are considered to be where there are views of the site to be the occupiers of properties and users of both the public rights of way and road.
The LVIA considered a Zone of Theoretical Visibility to demonstrate how visible changes in the site would be from surrounding areas. This zoning supported a Zone of Significant Visibility (ZSV) which includes the northern void, plant site and immediate adjacent areas. Three categories of visual receptor identified, users of public rights of way, residential areas and occupiers of individual residential properties and users of local roads.
The assessment considered that within the ZSV views from public rights of way, roads and residential areas are often screened by combination of landform, vegetation and buildings. The ZSV would vary according to seasons.
In assessing the effects on the landscape character it was found that restoration would return the land to the typical surrounding landscape and with a rural character. It is considered there would be a low magnitude of change to the landscape character during restoration works and operation of the recycling facility. There is considered to be a long term benefit to the scenic value, tranquillity and leisure within the site.
In assessing landscape value, there would be no impact of the Green Belt, no impact on the Listed buildings setting as these are generally screened by existing vegetation or already overlook the ongoing restoration works. Whilst there would likely be an adverse effect on tranquillity and scenic quality during site activities, in the long term there would be beneficial impact.
The provision of the BCA and, after restoration, the rest of the land having new areas of key habitat created there would be overall a small biodiversity gain. Provision of public access would have a beneficial effect on leisure.
In terms of visual impacts the assessment noted that localised views would be
restricted to receptors on the site boundary immediately to the south. The assessment considered 21 viewpoints of which only 8 would experience adverse effects and only 2 would result in very substantial or substantial adverse effect. Both of these viewpoints are from public rights of way (one inside and one outside the site). The significance of the effect would decrease as restoration progressed.
In mitigation terms the assessment found the site already well screened by vegetation. A 3 metre high bund would be constructed on the eastern boundary of the IWRF site.
In cumulative impact terms the assessment addressed the proposed HDM plant finding that its provision would not add to the impact with its proposed siting being adjacent the recycling plant and screening provisions.
In conclusion there would, post restoration, be a long term beneficial landscape and visual aspect.
The LVIA was revisited to take account of the proposed re-siting of the IWRF and this identified that the revised siting location would not be visible from Mayes Lane. All other previously assessed landscape and visual effects were found to remain unchanged.
Water Resources
A hydrogeological and hydrological impact assessment was carried out which included a flood risk assessment.
As a baseline, the assessment viewed available maps from Envirocheck and the Environment Agency (EA) and the historical mapping showed the application land as being open fields until 1945. Quarries developed within the northern part of the plant site post 1945. The northern quarry void is shown as open fields until a gravel pit appears on the map dated 1967 and as a disused pit on a similar map dated 2006. A sand and gravel pit is shown south of the north void on a map dated 2006.
Two historic landfills show up on the EA website with the first identified as Southend Road landfill (inert materials between 1985 – 1991 and likely to have been the remediation activities associated with the A12 (T) slope) located in the western part of the northern void. The second identified as the Mayes Lane Landfill (commercial and household waste 1958 -1970) was located to the north east of the plant site and within the proposed BCA. This latter landfill would not be affected by any proposed recycling activities. A further landfill identified on the EA website is recorded as being located some 50 metres south of the northern void and is identified as the present southern void restoration activities.
The assessment confirmed that there are no recorded pollution incidents within 2km of the application site and no history of potentially contaminating activities.
The assessment confirmed the geology of the application footprint from British Geological Survey maps together with borehole data. Sandon quarry is identified as being located within a buried channel of superficial drift deposits underlain by Boulder Clay.
In terms of Hydrology the assessment noted the application site as being in the catchment of the River Chelmer with the Sandon Brook acting as a tributary.
There are 14 licensed surface water abstractions within approximately 2km and 37 Environment Permits for discharges in a similar radius. The closest is the southern void discharge point in the south east of the complexes boundary.
The assessment noted that the applicant undertook water quality monitoring at and around the site between 1997 and 2014 and no trends or conclusions are drawn from this data. The assessment notes that an Environmental Permit would be required for restoration of the northern void and that as part of this there would be surface quality water monitoring.
In respect of hydrogeology the assessment confirms the site as not being within a groundwater Source Protection Zone. The applicant has undertaken groundwater monitoring at 17 boreholes since 1998 with recorded levels ranging from around 1.68m AOD south west of plant site to 27.07m AOD further south west of plant site. In the vicinity of the northern void groundwater levels are around 12.1 and 21.8m AOD. Seasonal variations of 1 metre were experienced in the vicinity of the site.
The assessment confirmed that dewatering activities has had effects on groundwater levels. Groundwater flow in both void areas is towards the pumping location in the southern void. In the absence of pumping flow direction would be towards the north and north east in the direction of topographical fall; the direction of the buried channel and confluence of the Sandon Brook arms.
In assessing effects the assessment noted that the infilling would be undertaken in phases using granular material and dewatering. The assessment confirmed there is no groundwater level monitoring available in or around the void areas. It is assumed that groundwater levels in the northern void may recover to around 25m AOD whilst in the plant area levels are not considered to change given that the groundwater here already appears as surface water ponds.
Groundwater flows though the restored northern void are not considered to be affected given the remaining sand and gravel deposits and the use of granular fill that would allow the groundwater to equilibrate.
In terms of surface water runoff the assessment considered that surface water would naturally infiltrate ground in the restored northern void whilst in the plant area it would infiltrate the ground as occurs at present. It is not considered there would be significant impact on surface water drainage.
The assessment noted that both the proposed infilling and use of the recycling facility would require Environmental Permitting that would control the waste types to inert materials.
Conclusion was that it was considered unlikely that the proposal would result in unacceptable impacts
Flood Risk
The assessment considered the flood risk aspect of the proposal noting that the central and north western parts of the northern quarry void, together with the eastern arm of the Sandon Brook, main site haul road to the plant site, the pond on the western side of the plant site and part of the haul road where it crosses the western arm of the Sandon Brook are identified as being within Flood Zones 2 and 3. The remainder of the site is in Flood Zone 1. (Zone 1 is assessed as having less than a 1 in a 1000 annual probability of river flooding; Zone 2 is assessed as having between a 1 in 100 and 1 in 1000 annual probability and Zone 3 as having a 1 in 100 or greater annual probability of river flooding).
Based on a review of published Strategic Flood Risk Assessment the application area shown as Flood Zone 3 is categorised as Flood Zone 3a and therefore not the functional floodplain 3b (where water has to flow or be stored in times of flood).
A review of potential flooding from groundwater found that groundwater levels may recover to approximately 25m AOD and may result in more recharge of groundwater to nearby surface watercourses. However, given these watercourses are likely to be in low permeability alluvium any recharge is likely to be modest and would not significantly affect the flooding risk.
The assessment did not find the application land as likely to be affected by flooding from surface waters, sewers, drains or canals/reservoirs.
The assessment considered the Sequential and Exemption Test with the former seeking to steer new development to areas of low probability of flooding (Flood Zone 1). The assessment notes that the underlying principle of the application is to restore land to a sustainable use and as such no alternative locations exist. Where no alternative sites exist the flood risk vulnerability needs to be considered. Landfill is classed as more vulnerable and the assessment takes this heading noting that in reality the proposal is more one of a recovery process.
The Exceptions Test identifies the management aspects of flood risk to people and property whilst allowing development to go ahead where there are not available alternative less flood risk prone sites available.
The assessment finds that the Flood Zone 2 and 3 in the northern void exist only because of the pumping and that its recovery after pumping would allow it to rise so removing the flood storage capacity shown in the Strategic Flood Risk Assessment. The restoration of the northern void would not reduce the identified capacity any more than the situation where groundwater pumping ceases.
In terms of flood risk and the proposed development the assessment identified that the plant site is in Flood Zone 1 and has hardstanding existing and proposed. It is not considered that the development would increase surface water runoff. In the northern void, groundwater would be pumped during infilling as at present and no significant increase in flood risk is identified. On restoration any recharge of nearby watercourses is considered to be modest and not to significantly increase flooding risk.
In terms of mitigation the assessment notes that restoration and operation of the recycling plant would be subject to Environmental Permitting. That would also address ground and surface water monitoring.
In terms of cumulative impacts the assessment took on board the proposed HBM plant which it noted would be located within Flood Zone 1. As such the combined operation of the HBM and recycling plant and restoration of the void was not considered to result in additional impacts of surface water run-off, quality or flood risk. The conclusion was that the development would not increase significantly the risk of flooding at or in the sites vicinity.
The Flood Risk Assessment was revisited to take account of the proposed re-siting of the IWRF and it found that the revised location would not require a flood risk assessment being undertaken.
Ecology
The assessment confirmed that a range of ecological surveys have been carried out at the site including protected species and habitat surveys. The northern void area was acknowledged as being a Local Wildlife Site mainly due to invertebrate/reptiles/birds and protected species interests.
Surveys undertaken included:
1. Extended Phase 1 habitat survey 2. Bat Roosting 3. Protected species 4. Reptiles 5. Breeding birds 6. Invertebrates 7. Water Vole and Otter 8. Arborocultural.
The assessment considered mitigation measures including translocation.
An area of biodiversity compensation has been identified within the eastern part of the application land that would accommodate habitat replacement.
The nearest Site of Special Scientific Interest (SSSI) is located approximately 2.2 kilometres east of the application site. Two Local Nature Reserves (LNR’s) are located to the west of the application land the nearest being Chelmer Valley Riverside LNR at about 4.2 kilometres north west and Galleywood Common LNR approximately 4.2 kilometres south west.
There were 8 non statutory nature conservation designations within 2.5 kilometres. The northern void is designated a LoWS as described earlier in the report. The next closest site is just over 1 kilometre north east.
The assessment described the habitats present as being grassland and woodland, with the largest continuous piece of woodland being along the arm of the Sandon Brook. The application land exhibits scattered woodland and shrub areas. There are nine water bodies of various size present.
The assessment considered potential impacts on the statutory and non statutory sites
noting that for the statutory sites the application proposals would not result in a significant risk or direct/indirect impact on their interests.
In respect of non statutory sites; mitigation for the habitat interest within the northern void would be provided through the creation of the BCA described earlier in the report.
The assessment found that for the habitats present; the majority are common and widespread and of low ecological value. Land in the northern void and north of plant site are Biodiversity Action Plan (BAP) priority open mosaic habits on previously developed land. This habitat is one of the qualifying attributes for the LoWS designation as is some of the grassland present. The rough neutral grassland is of local importance. Secondary woodland and areas of swamp also qualify as national BAP habitats of principal importance.
Mature trees occur along the north and north eastern perimeter along the eastern and western arms of the Sandon Brook and along northern boundary of the BCA. Mature trees would not be affected by the proposals.
Ponds on the site qualify for national BAP habitat.
The assessment mitigation and compensation measures identified the provision of the BCA; a translocation programme for protected species under licence from Natural England; vegetation removal and site clearance outside of bird breeding season. A qualified ecologist would be used prior to any clearance works taking place outside of these times.
The assessment identified under cumulative impact that a separate application for the HDM plant would be forthcoming. Whilst the land area for this future application would mostly be on hardstanding; part of it would see the loss of some of the open mosaic habitat. The loss of this area is seen as being compensated through the provision of the BCA. The assessment confirmed that no significant cumulative impact from the HDM production alongside the inert waste recycling and restoration was anticipated.
Conclusion was that the ecology led restoration would provide further habitat consistent with the Local Wildlife Site. Overall the proposal was found to result in no net loss of biodiversity and would result in a small gain through the restoration programme.
The assessment was updated in respect of the revised location of the IWRF noting that the revised siting location would occupy some of the land previously identified for inclusion within the previously proposed BCA. The footprint of the revised IWRF was identified as having rough neutral grassland, tall ruderal vegetation, some individual trees, scrub and two small ponds previously identified as not having any protected species interest. A pond located to the south west of the proposed IWRF which had protected species interest would be unaffected although a ditch which had such interest would be removed. In compensation two new ditches would be proposed. The conclusion on the ecological impact was revisited and found that the biodiversity impact calculations showed the revised location would result in a small loss in biodiversity interest of 0.13% that was close to a position of no net loss of biodiversity and considered to be negligible in terms of biodiversity value for the application site.
Cultural Heritage
A Heritage Statement was prepared on designated cultural heritage assets. The assessment considered the baseline using the previously referred to Zone of Theoretical Visibility (ZTV) in the LVIA to identify the designated assets that could potentially be affected. In addition designated assets out to 500m were assessed for adverse impacts arising from noise and vehicle movements.
The assessment found no designated assets in the site and no scheduled monuments within 1km. There are 13 listed buildings within the ZTV and 500m of the site. Sandon Conservation Area is located some 300m north west and 400m north of the site haul road.
Around the site, the Historic Environment Record identifies 14 records of finds within 1km of the site.
The assessment confirms that site visits were undertaken and an assessment of environmental effects complied. It was found that the proposed development would be on land already disturbed by mineral extraction, manual process operations or by the main site haul road. There would not be direct impact on archaeology or heritage assets. The assessment went on to assess the indirect impacts that would result in alterations to the setting or context of the heritage asset or landscape. A number of assets were scoped out of the assessment as a result of intervening vegetation, development, topography or distance.
Two assets, The Rectory and Sandon Conservation Area were considered in more detail as a result of the consultant’s site visit and ZTV findings that indicated a potential susceptibility to adverse impact. The assessment concluded that from The Rectory although the site would be screened by topography and intervening vegetation there would be highly filtered views of the main site haul road during winter months from upstairs windows. The magnitude of change is considered negligible/imperceptible and the impact on view as negligible.
For the Conservation Area, views are screened by intervening vegetation, development, topography and the A12 (T). The assessment noted that the south western part of the Conservation Area is near the southern boundary of The Rectory garden. There could be highly filtered views of the main site haul road from this location. The magnitude of change is considered negligible.
In terms of noise and vehicle movements their potential impacts have been assessed as minimal in comparison to A12 (T) traffic movements and movements of vehicles in the broader landscape is considered to have an adverse effect of low magnitude. No specific mitigation measures are proposed.
In cumulative impact terms the proposed HBM plant has been assessed alongside the recycling plant and infilling operations. Given the HBM proposed closeness and similarity in operations it is considered that the combined operations would not result in any additional impacts on the setting of designated heritage assets.
Conclusion was that there would be no significant impacts on settings of designated heritage assets.
Traffic Air Quality and Amenity
The assessment reviewed the guidance in the Design Manuel for Roads and Bridges against the Manuel’s criteria in respect of impact of road projects on local and regional air quality. Under the criteria the assessment found the proposal would result in no changes to road alignments; no increase in the daily HGV traffic flows of 200 annual average daily traffic flows, nor would there be an increase in daily road speed. Traffic flows on the A12 (T) as a result of the proposal would not exceed regional air quality criteria. No further impact assessment on local or regional air quality was therefore considered.
In terms of amenity, the assessment considered the results of transport, processing and placement of the materials and operation of the recycling plant. Generation of mud and dust on the road was acknowledged and considered to have the most potential in the immediate vicinity of the site. It was noted that there have been no substantiated complaints related to these matters in relation to the site.
As a baseline local meteorological records were collected and identified prevailing wind as being south west and west south west.
In terms of mud on the road the experience of the southern void activities have not given rise to significant quantities of mud being carried out of the site and no history of local resident complaints. The haul road is concrete surfaced for its entire length to the weighbridge area.
In assessing environmental effects a qualitative assessment of dust has been undertaken and considered the particle sizes, topography, rainfall and perimeter vegetation. The consideration was that there was a low risk of dust impact from the infilling activities and good site management would be adopted.
In respect of the recycling activities the provision of water suppression would mitigate potential dust generation together with minimising drop heights. Appropriate management practices could control dust arising such that the proposal would not cause a significant impact.
The assessment confirms that dust emissions from the proposal would be controlled through the Environmental Permit.
Provision of a road sweeper and good management of the haul road would address the potential for mud and debris carry out.
In terms of cumulative impact the assessment considered the operation of the HBM plant alongside the other proposed site activities. It was considered that there would not be a significant increase in HGV movements and therefore no unacceptable cumulative impact on traffic. air quality, dust or mud associated with the combined HGV movements.
The proposed HBM plant would be designed and operated to control dust emissions. Overall operation of the HBM and recycling plant would not result in any additional dust emission impacts.
The assessments conclusion was that air quality would not be impacted through this application.
Noise and Vibration
The assessment calculated the predicted noise levels for the proposed development. A noise survey was undertaken to establish background baseline conditions at 6 locations. The recorded background sound levels identified road traffic, aircraft and natural noises such as birdsong. Operations in the southern void were taking place but did not contribute significantly to the recorded levels.
In assessing the environmental effects the assessment noted that in line with Planning Practice Guidance for Minerals that noise limits of 10dB(A) above background have been set to a maximum of 55 dB L Aeq 1h . The representative background levels during the weekday period between 0700 and 1800 hours was 47dB L A90,1h and for Saturday 45 dB L A90,1h .
The assessment confirmed that noise calculations took into account the proposed screening arrangements, and that plant would be maintained according to manufactures specifications. The highest predicted sound levels associated with bund construction are found to be below guidance levels at all six monitoring locations. For proposed site operations five, of the six, monitoring locations would receive noise within the predicted 55 dB L Aeq 1h whilst the sixth location would register 56 dB L Aeq 1h. The dominant noise source for this location would be site haul road traffic at Bridge Cottage. The assessment found that the dominant background noise at this location is vehicle movements along Molrams Land and the A1114. Sound from additional HGV’s associated with the proposal would not increase ambient sound at Bridge Cottage. It is considered that the noise impact from HGV’s along the haul road would be of negligible significance. The assessment considered that overall noise effects are of negligible significance.
Noise emissions of HGV’s on the public highway have been considered with calculations at four locations and the predicted change in noise level is assessed at less than 1 dB which is considered negligible.
Effects of vibration have been considered from mobile crushing and screening plant. It was considered that as receptors generally have to be very close to vibration sources and no plant would be located close to sensitive receptors vibration has been found to be insignificant. Vibration from offsite HGV movements are considered to be insignificant based on assumption of standard maintenance of both highway and main site haul road.
Mitigation – The assessment noted that all mobile site plant would have white noise alarms and there would be provision of the plant area screen bund. In terms of cumulative effects, the proposed noise generation from the HDM plant has been assessed along with the operation of the recycling plant at the six monitoring points.
In terms of cumulative impact the assessment found the levels of generated noise to be within the 55 dB L Aeq 1h level at 5 of the locations and for the sixth that the 1dB increase is due to HGV traffic on the haul road that is similar to the ambient sound
level already experienced at Bridge Cottage. It is not therefore considered that operation of the HDM plant, inert recycling plant and restoration works would result in significantly increased noise levels and therefore cumulative effects would be negligible.
The Noise assessment was revisited to take account of the proposed re-siting of the IWRF and the noise impacts previously assessed above were not found to be affected.
Stability Risk Assessment
A Stability Risk Assessment (SRA) was undertaken which included the restoration profile incorporating a sloping topography from the south west at an approximate elevation of 32m AOD to north east at approximately 25m AOD. The proposed slope gradient being from around 1v60h to 1v120h (v: vertical, h: horizontal). The restoration profile includes a south west slope of 1v10h 40m long with a 4 metre height. The SRA considered that the materials being used would comprise a range of cohesive and granular inert materials.
The SRA was carried out in accordance with British Standards and modelling software. A target factor of safety of 1.5 for the restoration profile has been chosen as this would reflect that the landform is stable in perpetuity.
The SRA considered the steepest proposed slope and analysis showed the factor of safety as 4.3 constructed with cohesive material and 5.4 if constructed with granular. In both case the factor of safety of 1.5 would be achieved.
In respect of infilling activities, the SRA considered the proposed infilling within the void and it is proposed that a detailed methodology be developed through discussion with Highways England and that this could be addressed through planning condition . In terms of mitigation, the proposal has considered the use of controlled dewatering and use of granular materials to the top of the current water levels.
Conclusion was that no infilling would take place until a final methodology had been agreed with Highways England.
3. POLICIES
Section 38 of the Planning and Compulsory Purchase Act 2004 requires that consideration be had to the development plan unless other material considerations indicate otherwise. Other material considerations include:
i) The National Planning Policy Framework (NPPF) March 2012. ii) The National Planning Policy for Waste October 2014. iii) Essex and Southend Waste Local Plan Adopted September 2001 iv) Essex County Council Replacement Waste Local Plan Pre Submission document June 2016 v) Chelmsford Borough Council Local Development Framework Core Strategy and Development Control Policies 2001-2021 Adopted February
2008. The following policies of the Essex and Southend Waste Local Plan Adopted September 2001 (WLPA); Essex County Council Replacement Waste Local Plan Submission document June 2016 (WLPS) the Chelmsford Borough Council Local Development Framework Core Strategy and Development Control Policies 2001-2021 Adopted February 2008 and Chelmsford City Council Core Strategy and Development Control Policies Focussed Review, Local Development Framework 2001 – 2021, Development Plan Document Adopted December 2013 (paraphrased or in quotation marks if set out in full) are of relevance to this application:
Relevant policies within the Essex and Southend Waste Local Plan Adopted September 2001 are:
Policy W3A (Best Practicable Environmental Option)
Requires that consideration be given to:
(a) The goals of sustainable development (b) Whether the proposal represents the best practicable environmental option for that particular waste stream (c) Whether the proposal conflicts with options further up the waste hierarchy. (d) Conformity with proximity principle.
Policy W4A (Water Pollution and Flood Control)
Would support waste management development where it would not present an unacceptable risk in respect of it impeding surface water flows; have an adverse effect on the water environment as a result of surface water runoff or existing and proposed flood defences are protected.
Policy W4B (Water Pollution and Flood Control)
Would restrict development where there would be an unacceptable risk to the quality of surface or groundwater.
Policy W8A (Criteria for waste management facilities)
Supports waste management facilities at specific locations provided relevant criteria are met including:
(a) There is a need for the facility to manage waste. (b) The proposal represents the Best Practicable Environmental Option. (c) The development complies with other relevant policies. (d) Adequate road access. (e) Integrated schemes for recycling, composting, materials recovery and energy recovery would be supported where there are shown to be benefits in the management of waste which would not otherwise be obtained.
Policy W8B (Location of waste management facilities).
Provides for waste management facilities to be provided at locations other than those
identified in the waste plan where relevant criteria identified in Policy W8A are met. Such other locations, of relevance to this application include existing general industrial areas and areas allocated for general industrial use in adopted local plans.
Policy W10A (Planning Conditions and Obligations)
Provides for the Waste Planning Authority to impose conditions as appropriate to ensure the development is operated in an acceptable manner and undertaken in accordance with approved details.
Policy W10B (Content of Planning Applications and Material Considerations)
Requires all proposals for waste management to be accompanied by full planning applications to include such aspects as “siting, design and external appearance of buildings, plant, equipment and storage facilities, landscaping and suitable measures to mitigate and control unacceptable adverse effects, including noise and artificial lighting”.
Policy W10E (Content of Planning Applications and Material Considerations)
(a) Supports applications for waste management development where provision is made to address, amongst other matters relevant to this application: (b) Effects on the amenity of neighbouring occupiers. (c) Effects on the landscape. (d) Impact on road traffic generation.
Policy W10F (Hours of Operation)
Provides for the WPA to impose operating hours in respect of safeguarding local amenity and the nature of the operations.
Policy W10G (Public Rights of Way)
Requires that applications include measures to both safeguard and where practicable improve rights of way provision and that such improvements take place prior to any development affecting such routes takes place.
In the Chelmsford Borough Council Local Development Framework Core Strategy and Development Control Policies 2001- 2021 Adopted February 2008 (CBC AP2008) the following policies are of relevance:
Policy CP9 – Protecting Areas of Natural and Built Heritage and Archaeological Importance – This policy seeks to “sustain biodiversity, historic landscape character, archaeological and geological conservation by ensuring sites of international, national, regional and local importance are protected and enhanced. The Borough Council will designate and keep under review Conservation Areas in order to protect or enhance their special architectural or historic interest and will seek to protect the character and setting of Listed Buildings, Historic Parks and Gardens and Protected Lanes”.
Policy CP10 - Protection from Flooding
This policy seeks to ensure that when considering proposals a sequential risk-based approach, including the application of the “exception test” where some continuing development is necessary for wider sustainable reasons would be required. The Borough Council would require that development is protected from flooding and that appropriate measures are implemented to mitigate flood risk.
Policy CP12 – Protecting and Enhancing Recreational Provision The policy seeks to maintain and enhance the provision of formal and informal recreation facilities, at appropriate locations, within the Borough including the designation of new local parks and gardens, country parks and other public open spaces.
Policy CP13 - Minimising Environmental Impact The policy seeks to ensure that development proposals minimise their impact on the environment and that they do not give rise to significant and adverse impacts on health, amenity including air quality, and the wider environment.
Policy CP14 – Environmental Quality and Landscape Character The policy seeks to promote and support the enhancement of the environmental quality of the countryside and settlements. The policy would be supported through the preparation of a Landscape Character Assessment.
Policy DC4 - Protecting Existing Amenity Seeks to safeguard the amenities of the occupiers of any nearby properties by ensuring that development would not result in excessive noise, activity or vehicle movements, overlooking or visual intrusion.
Policy DC13 - Sites of Biodiversity and Geological Value The policy seeks to restore, maintain and enhance biodiversity and geological conservation interests.” In determining planning applications appropriate weight will be attached to designated sites of international, national and local importance, protected species, and to biodiversity and geological interests within the wider environment which includes ancient woodlands other important woodland sites ..Within those sites, and subject to securing the wider objectives of sustainable development, planning permission will not be granted for development that would result in significant harm to biodiversity and geological conservation interests unless it can be clearly demonstrated that; i) there is no appropriate alternative site available; and ii) all statutory and regulatory requirements relating to any such proposal have been satisfied; and iii) appropriate mitigation and compensation measures are provided.
Where possible the Borough Council will expect development proposals to promote opportunities for the incorporation of beneficial biodiversity and geological features within the design of development. Development proposals must avoid any adverse effects on the integrity of European and Ramsar sites and where possible enhance the biodiversity interest of internationally designated sites for nature conservation”.
Policy DC14 - Protected Trees and Hedges The policy would seek refusal of development that would “cause demonstrable harm to protected woodland, trees and hedgerows, unless conditions can be imposed requiring the developer to take steps to secure their protection. Where the felling of a preserved tree or removal of a hedgerow is permitted a replacement tree or hedge of an appropriate type, size and in a suitable location, will usually be required”.
Policy DC16 - Development Adjacent to Watercourses States “Planning permission will be refused for development adjacent to rivers, the Chelmer and Blackwater Navigation and other watercourses where the design and layout of the proposed development fails to be sensitive to the landscape or fails to take full advantage of the development setting afforded by open water features and their margins. Where appropriate, development proposals adjoining the rivers will be required to incorporate riverside paths and open spaces”.
Policy DC18 - Listed Buildings Seeks to restrict approval where development or works affecting the exterior or interior of listed buildings, fail to preserve or enhance the special character and/or setting of those buildings.
Policy DC21 – Archaeology The policy states that “Planning permission will be granted for development affecting archaeological sites providing it protects, enhances and preserves sites of archaeological interest and their settings taking account of the archaeological importance of those remains, the need for the development, the likely extent of any harm, and the likelihood of the proposal successfully preserving the archaeological interest of the site by record”.
Policy DC22 - Areas of Flood Risk The policy requires Flood Risk Assessment on development within Flood Zone 2 and 3. Planning permission would only be granted for development providing existing flood defences or other satisfactory mitigation, including replacement flood storage capacity, provide adequate protection from flooding now and for the lifetime of the development. Outside of settlements permission would only be granted where that development is (amongst other criteria) primarily open in character.
Policy DC28 - Air Quality The policy requires that where air quality objectives are likely to be prejudiced or proposals fall within an Air Quality Management Area, “applicants will be required to submit a detailed specialist report which sets out the impact that the proposed development has upon air quality. Planning permission will not be granted for development where there is significant adverse impact upon air quality in the Air Quality Management Area”.
In the Chelmsford City Council Core Strategy and Development Control Policies Focussed Review, Local Development Framework 2001 – 2021, Development Plan Document Adopted December 2013 (CCS Adopted 2013) relevant policies are considered to be:
Policy DC2 - Managing Development in the Countryside Beyond the Metropolitan Green Belt – This policy seeks to support development within the Rural Area beyond the Metropolitan Green Belt provided that the intrinsic character and beauty of the countryside is not adversely impacted upon and provided it is for under criteria C of the policy “ the carrying out of an engineering or other operations, or the making of a material change to the use of land, where the works or use concerned would have no material effect on the appearance and character of the countryside in the Rural Area beyond the Metropolitan Green Belt”.
Policy DC29 - Amenity and Pollution The policy would seek to restrict development that “could potentially give rise to polluting emissions to land, air, and water by reason of noise, light, smell, fumes, vibration or other (including smoke, soot, ash, dust and grit) unless appropriate mitigation measures can be put in place and permanently maintained”.
Policy DC41 - Traffic Management Measures The policy requires ”all developments to include appropriate traffic management measures to facilitate the safe and efficient movement of people and goods by all modes whilst protecting and enhancing the quality of life within communities, facilitating the appropriate use of different types of road and environment, and achieving a clear, consistent and understandable road, cycle and pedestrian network. These measures will comprise, amongst others, reducing the impact of motorised traffic, traffic calming measures to assist public transport, cycling, and walking, horse riders, congestion relief and other speed and demand management measures”.
The Essex and Southend Replacement Waste Local Plan Submission document was submitted in June 2016 to the Secretary of State and is currently undergoing examination. The submitted policies, whilst at this juncture are unadopted, reflect the intention of the Waste Planning Authority towards waste related matters. The Proposed Modifications as recommended by the Secretary of State and approved by this Authority are at present being consulted upon. The policies referred to below should be considered as having weight and therefore remain material considerations in respect of applications of the nature being contemplated in this report.
Relevant policies within this document are:
(a) Policy 1 (Need for Waste Management Facilities).
Over the Plan period (up to 2032) the Plan identifies a shortfall in capacity of up to 1.5 million tonnes per annum by 20131/32 for the management of inert waste.
(b) Policy 3 (Strategic Site Allocations)
Supports waste management development at a list of sites including for inert waste recycling Site W7 Sandon East.
(c) Policy 6 (Open Waste Facilities)
This policy includes aggregate recycling activities and seeks to collocate such activities at mineral and waste landfill sites where such material is used in
conjunction with restoration works.
(d) Policy 10 (Development Management Criteria)
Provides support for waste management development where such development can be demonstrated not to have an unacceptable impact (including cumulative impact with other existing development) on a list of issues, where relevant to this application include:
(i) Local amenity (ii) Water quality (iii) Safety and capacity of road network (iv) Appearance quality and character of the landscape and visual environment. (v) Public open space, the definitive Public Rights of Way network (vi) The natural environment (vii) The historic environment (viii) The character and quality of the area through poor design. • (e) Policy 11 (Mitigating and Adapting to Climate Change)
Requires proposals for waste management development through their construction and operation are required “to minimise their potential contribution to climate change by reducing greenhouse gas emissions, incorporating energy and water efficient design measures and being adaptive to future climatic conditions”.
(f) Policy 12 (Transport and Access)
Provides support for waste management development where it would not have “an unacceptable impact on the efficiency and effective operation of the road network, including safety and capacity, local amenity and the environment.
Proposals for the transportation of waste by rail and/or water will be encouraged subject to other policies in this Plan. Where transportation by road is proposed. This will be permitted where the road network is suitable for use by Heavy Goods Vehicles or can be improved to accommodate such vehicles”.
Policy 12 sets a hierarchy for transport preference of the waste with the movement by rail or water at the top followed by access through an existing junction to the main road network via a suitable section of existing road. A final criterion for creation of a new road access is not relevant to this application.
National Policy Statements
The National Planning Policy Framework (NPPF), published in March 2012, sets out requirements for the determination of planning applications and is also a material consideration.
The NPPF sets the scene for placing sustainable development at the heart of the planning system. The Government sets a series of core planning principles to be applied at both plan making, as well as at decision making and that these include in relation to this application:
(i) Seek to secure high quality design and a good standard of amenity in relation to existing occupants of land and buildings. (ii) Supporting the transition to a low carbon future in a changing climate and encouraging the use of renewable resources. (iii) Contribute to conserving and enhancing the natural environment and reducing pollution.
The NPPF seeks the delivery of sustainable development through the planning system encouraging and supporting economic growth and that this is achieved through proactively meeting the needs of business.
The NPPF seeks to mitigate, through appropriate planning decisions, the potential for noise and other adverse impacts including air quality, arising from a development on health and quality of life.
National Planning Policy for Waste (NPPW)
The National Planning Policy for Waste was published October 2014 and sets out the national case for the management of wastes. The Introduction to this document states that it is “the Government’s ambition to work towards a more sustainable and efficient approach to resource use and management. Positive planning plays a pivotal role in delivering this country’s waste ambitions through: delivery of sustainable development and resource efficiency ..”
The NPPW sets out under the heading of identifying waste management facility needs that Waste Planning Authorities in their preparation of local plans identify such opportunities to meet identified needs of their area for the management of waste streams.
Waste planning authorities should also:
• “undertake early and meaningful engagement with local communities so that plans, as far as possible, reflect a collective vision and set of agreed priorities when planning for sustainable waste management, .; • drive waste management up the waste hierarchy .. recognising the need for a mix of types and scale of facilities, and that adequate provision must be made for waste disposal; • consider the need for additional waste management capacity of more than local significance and reflect any requirement for waste management facilities identified nationally; • take into account any need for waste management, including for disposal of the residues from treated wastes, arising in more than one waste planning authority area but where only a limited number of facilities would be required; • work collaboratively in groups with other waste planning authorities, and in two- tier areas with district authorities, through the statutory duty to cooperate, to provide a suitable network of facilities to deliver sustainable waste management; • consider the extent to which the capacity of existing operational facilities would satisfy any identified need ”.
For the determination of planning applications the policy statement requires waste planning authorities to amongst other matters
• “consider the likely impact on the local environment and on amenity against the criteria set out in Appendix B [this referred to appendix sets out locational criteria] and the locational implications of any advice on health from the relevant health bodies. Waste planning authorities should avoid carrying out their own detailed assessment of epidemiological and other health studies;
• ensure that waste management facilities in themselves are well-designed, so that they contribute positively to the character and quality of the area in which they are located;
• concern themselves with implementing the planning strategy in the Local Plan and not with the control of processes which are a matter for the pollution control authorities. Waste planning authorities should work on the assumption that the relevant pollution control regime will be properly applied and enforced ”
4. CONSULTATIONS
CHELMSFORD CITY COUNCIL – No objection. The City Council note the revised location of the recycling plant being further away from the Mayes Lane properties being designed to reduce potential impact on local residents amenity and that the revision would result in a small loss in biodiversity interest of 0.13%. The City Council state “ Overall, this Council remains of the view that the proposal is acceptable subject to compliance with “the issues and opportunities identified in Table 17 of Appendix B and other relevant polices of the Pre-Submission Waste Local Plan ”. [This referred to Table is set out in Appendix A of this report that contains the relevant extract from the Essex County Council Replacement Waste Local Plan Submission document referring to Sandon. The extract has been annotated in respect of the Issues and Opportunities items to clarify the present situation with comments added after each of the bullet points in “[ ]” brackets].
ENVIRONMENT AGENCY (EA) – No objection. The EA comment under specific headings:
(i) Environmental Permitting - that the recycling facility would require permitting as would discharges to the watercourse. (ii) Water Framework Directive – That the recycling plant would be Permitted and the proposal is not likely to result in deterioration of the Water Framework Directive status of the Sandon Brook. It is noted that planting/retention of vegetation along the Brook would have a positive impact keeping the brook cool and providing woody debris to help with habitat diversity. (iii) Flood Risk – No activities would be taking place in Flood Zones 2/3 and stockpiles should not be stored in Flood Zones 2/3.
ESSEX WILDLIFE TRUST – Objects. The Trust noted, on the original application, the Local Wildlife Status of the land and the Trusts preference for no tipping. Whilst supportive of the habitat creation measures the Trust was unsure how the proposed water areas in the restoration scheme were to be maintained.
Were planning approval to be forthcoming the Trust would wish in line with national guidance to see a long term management plan in place to address the creation and enhancement of biodiversity.
In relation to the amended details for the repositioning of the waste recycling plant the Trust notes that the scheme would impact on protected species and that further translocation is proposed for these interests. The Trust objects to these proposals.
FORESTRY COMMISSION – No objection and note that although the aftercare would not be eligible for grants the Commission would be happy to advise on planting stock and design.
HIGHWAYS ENGLAND No objection subject to a condition requiring a Method Statement to be agreed prior to development commencing as to how site activities are going to take place alongside Highway England interests.
HISTORIC ENGLAND (HE) – No objection, HE advises that the application be determined in specific accordance with national and local policy guidance and Essex County Council’s specialist officers.
NATURAL ENGLAND (NE) - No objection, NE state “ Natural England is generally supportive of the proposed ecological mitigation and biodiversity enhancement measures incorporated within the proposals and has no objection to the proposed development”.
In respect of other areas of interest, NE note:
(i) Wildlife and Countryside Act 1981 (as amended) – no objection – no conditions requested. NE confirms that the application is not near any Sites of Special Scientific Interest. (ii) In terms of Protected Species NE have made no comment noting they produce Standing Advice and such advice needs to be addressed against each application. (iii) Biodiversity enhancements – the application presents an opportunity to incorporate features beneficial to wildlife into its design.
NATIONAL PLANNING CASEWORK UNIT – Any comments received will be reported
NORTHUMBERLAND WATER PROPERTY SOLUTIONS - Do have apparatus in vicinity of the application land and draws attention to their advice to applicants in relation to working alongside such apparatus.
RAMBLERS (BOTH AREA FOOTPATHS OFFICER AND AREA COUNTRYSIDE OFFICER) – No comments received.
UTILITIES: BRITISH TELECOM OPEN REACH INSTALCOM; INTEROUTE ; NATIONAL GRID; NORTHUMBERLAND WATER PROPERTY SOLUTIONS and VODAFONE – Do have apparatus in vicinity of the application land and draws attention to their advice to applicants in relation to working alongside such apparatus.
COUNTY COUNCIL’S NOISE CONSULTANT (CNC) – No objection. The CNC has
been in close discussion with the applicants noise consultant and has confirmed: “With the additional assessment work undertaken, I am now satisfied that sufficient information has been provided and re-assessment work undertaken to demonstrate that noise and vibration emanating from the site are unlikely to exceed levels recommended by relevant guidance. This would be subject to conditions relating to compliance noise monitoring”.
Comment: Specific comments of the CNC have been incorporated into the appraisal section of the report. Should planning approval be forthcoming conditions addressing noise generation levels and monitoring would be recommended to ensure compliance.
COUNTY COUNCIL’S AIR QUALITY CONSULTANT (CAQC) – No objection noting: “I would suggest conditions along the following lines for dust associated with the construction phase:
The risk of dust soiling and effects on human health and ecological receptors associated with construction activities for this development shall be detailed in the dust assessment for the site. Standard good practice dust mitigation measures measures appropriate for the identified likely level of risk shall be included in the Construction Code of Practice for the site, which shall be agreed with the Essex County Council.
I did not suggest a dust risk assessment or mitigation for the operational phase as the site would have a permit, however if there are concerns of dust nuisance during the operational phase then an operational dust impact assessment should be requested. Where the assessment shows that there is the potential for a dust impact which is significant basic good practice and site specific mitigation measures should be implemented such as those outlined in the Institute of Air Quality Management (IAQM) Guidance on the Assessment of Mineral Dust Impacts for Planning (May 2016). Mitigation measures should be agreed with Essex County Council”.
Comments from the CQAC in respect of air quality aspects are awaited and any comments received will be reported.
COUNTY COUNCIL’S LIGHTING CONSULTANT – No Objection stating “It is considered that lighting is unlikely to result in adverse impacts to nearby receptors; however, insufficient information is available to be certain of this. Therefore to ensure potential lighting impacts are minimised I would recommend the following condition prior to installation of the lighting”.
HIGHWAY AUTHORITY (HA/Public Rights of Way) – No objection. The HA Officer notes that from a highway and transportation perspective the impact of the proposal is acceptable to the HA subject to the following comments and conditions:
i) Associated HGV movements and proposed traffic routeing are consistent with earlier planning approvals for the complex where larger vehicle movements have been generated.
ii) The present site traffic activities are subject to a vehicle routeing agreement.
iii) The existing haul road are to have chicanes to replace the sleeping policeman that will eliminate noise generated by HGV’s bumping over them.
“The Highway Authority has engaged with local stakeholders and the applicant regarding the future strategy for the Public Rights of Way (PRoW) within the Sandon Quarry site on land within the control of the applicant. The in principle details are shown on the Restoration Proposals drawing 1910/005K for creation of new PRoW permissive Footpaths and Permissive Bridleways within the application site boundary. The drawing shows connections to the existing PRoW Footpath Network outside the development site boundary on land in the applicants control and on third party land.
[1] The public’s rights and ease of passage over PRoW existing footpaths no. 232_26 [this footpath runs parallel to the west of the A12(T)] and 232_7 [this footpath lies on a north to south line east of the northern void] shall be maintained free and unobstructed at all times. However if it transpires that the works will affect the two footpaths and a diversion is required then no development shall be permitted to commence until such time as an Order securing the diversion of the existing definitive right of ways to a route to be agreed with the Local Planning Authority has been confirmed and the new route has been constructed to the satisfaction of the Local Planning Authority.
Reason: To ensure the continued safe passage of pedestrians on the public rights of way and accessibility in accordance with Policies DM1 and DM11.
[2] The developer shall be responsible for the construction and maintenance of the new PRoW Permissive Footpaths and Bridleways shown in principle in drawing no. 1910/005K. Details to be agreed in writing by the Highway Authority prior to construction.
Reason: To ensure the continued safe passage of the public on the public rights of way and accessibility in accordance with Policies DM1 and DM11.
[3] Where the permissive Bridleways are coincident with existing PRoW Footpaths numbers; 232_5 [adjacent site haul road], 232_7, 232_21, 232_22 and 232_26 [21 & 22 on land to the south of application footprint], the PRoW Footpath surfaces, shall be maintained to a condition suitable for walkers, cyclists and horse riders. Details to be agreed in writing by the Highway Authority prior to construction.
Reason: To ensure the continued safe passage of the public on the public rights of way and accessibility in accordance with Policies DM1 and DM11.
[4]. The developer shall enter into a long term agreement (by planning obligation or otherwise) to ensure that the permissive Footpaths and Bridleways shown in principle in drawing no. 1910/005K are available and maintained by the developer or landowner at no cost to the Highway Authority and to a standard acceptable to the Highway Authority for the lifetime of the development and thereafter as part of the long term site management plan and subsequent after care arrangements for a period of 25 years.
The above conditions are to ensure that the proposal conforms to the relevant policies contained within the County Highway Authority’s Development Management Policies, adopted as County Council Supplementary Guidance in February 2011”.
LOCAL FLOOD AUTHORITY – No objection noting that a hydrogeological and hydrological impact assessment including a flood risk assessment for the proposed development, surface water quality and quantity appear to be appropriately managed given the restoration by infilling with inert materials and the need for environmental permits for the waste recycling facility.
PLACE SERVICES (ABOROCULTURE) ENVIRONMENT, SUSTAINABILITY AND HIGHWAYS – No objection subject to a condition for a scheme to address tree retention and protection.
PLACE SERVICES (ECOLOGY) ENVIRONMENT, SUSTAINABILITY AND HIGHWAYS No objection subject to conditions. The Ecology Officer (EO) notes “This development will involve the complete loss of the remaining areas of the Sandon Pit Local Wildlife Site (Ch104) which contains priority habitats.
The Local Wildlife Site (LoWS) is designated for its ‘brownfield’ habitats (also known as the priority habitat ‘Open Mosaic on Previously Developed Land’). The LoWS citation states: “Brown field sites such as this can be extremely important sites for a wide variety of invertebrates, including solitary bees and wasps, spiders, grasshoppers and bush-crickets. This site is one of the best examples of the vegetation types and associated fauna that can develop on such land.” It is the only site in mid-Essex to contain the nationally rare digger wasp (Cerceris quinquefasiata), a Red Data Book 3 and National BAP species.
Given that the proposal involves the complete loss of the remainder of the LoWS loss of priority habitats and some protected species are present, the planning application should firstly demonstrate that there is no alternative in order to avoid harm. The ‘mitigation hierarchy’ set out in Paragraph 118 of the NPPF states that, “..if significant harm resulting from a development cannot be avoided (through locating on an alternative site with less harmful impacts), adequately mitigated, or, as a last resort, compensated for, then planning permission should be refused;”.
Where a development cannot satisfy the requirements of the ‘mitigation hierarchy’, planning permission should therefore be refused. The following questions are relevant when applying the ‘mitigation hierarchy’ at paragraph 118 of the National Planning Policy Framework:
Information
• in cases where biodiversity may be affected, is any further information needed to meet statutory obligations as signposted in guidance published by Defra/Natural England • where an Environmental Impact Assessment has been undertaken, what evidence on ecological effects has already been provided in the Environmental Report and is this sufficient without having to undertake more work?
• is the significance of the effects clear? And • is relevant internal or external expertise available?
Avoidance – can significant harm to wildlife species and habitats be avoided for example through locating on an alternative site with less harmful impacts?
Mitigation – where significant harm cannot be wholly or partially avoided, can it be minimised by design or by the use of effective mitigation measures that can be secured by, for example, conditions or planning obligations?
Compensation – where, despite whatever mitigation would be effective, there would still be significant residual harm, as a last resort, can this be properly compensated for by measures to provide for an equivalent value of biodiversity?
Compensation should only be considered where it can be demonstrated that the development in that location is necessary and that it cannot be avoided or adequate mitigation provided. In case of this planning application, a comprehensive compensation scheme has been provided and I am broadly supportive of the approach taken, as it will be biodiversity led, providing that it is secured for the long term. In order to replace those habitats and species lost (including the Local Wildlife Site), the habitats to the east will be enhanced (called ‘Biodiversity compensation area’), and the northern void and plant site will also be restored to a mosaic of habitats, using the same guiding principles as the compensation area. Both areas should be considered to part of the final compensation scheme (including the Local Wildlife Site and priority habitats /species and protected species), the existing habitats to the east will be enhanced (called ‘Biodiversity Compensation Area’), and the northern void and plant site will also be restored to a mosaic of habitats, using the same guiding principles as the compensation area. All areas within the red line boundary should be considered to be part of the final compensation scheme.
Policy S12 of the Essex Minerals Local Plan 2014- ‘Mineral Site restoration and After- use’ - establishes the context for biodiversity- led restoration and is supported by the Mineral Site Restoration for Biodiversity Supplementary Planning Guidance (SPG), June 2016. This lists six priority habitats for the restoration of mineral sites in Essex; Open Mosaic on Previously Developed Land is one of these six habitats. Habitat Management relating to Sandon- and all Essex mineral sites- should be in line with the details set out in the SPG”.[Biodiversity Restoration Minerals Supplementary Planning Guidance (SPG)]
There is an intention to have a long-term management plan in place for the whole of the area within the red line. This should be set out within a legal agreement and should cover a minimum of 20 years after the 5 year aftercare period. The management plan- or Biodiversity Enhancement Plan- should be consistent with the requirements of the SPG; recommended content of a Biodiversity Enhancement Plan is set out on page 33 of the SPG.
As with the rest of the site, the northern void currently comprises a variety of habitats which collectively create “open mosaic habitat on previously developed land”, which is a priority habitat (and a Local Wildlife Site). The northern void habitats have naturally developed over time, with the previous phase 1 habitat survey from 2010 showing the site containing predominantly unimproved neutral grassland with secondary
woodland, open water, swamp and bare ground. The restoration habitat should ideally also comprise a mosaic of similar habitat types, essentially aiming to create ‘open mosaic habitat on previously developed land’ priority habitat. The biodiversity compensation area is described as needing to be created. However, it should be noted that open mosaic habitats have already developed in this area and the proposal will be to enhance them.
The dominant habitat proposed for the northern void is described as ‘species rich grassland’ (which is not priority habitat per se) and the intention is to probably graze it. I would draw your attention to the terminology within the Bioscan report (eg Vol 2 Bioscan report paragraph 7.3.20) and the ES, which proposes chalk grassland seeding for the northern void. I would have preferred to see a greater amount of natural regeneration for this area, in line with the advice within the Mineral Site Restoration for Biodiversity Supplementary Planning Guidance (SPG) for ‘Open Mosaic Habitats on Previously Developed Land’ and the method the existing habitats have developed. Please note that the biodiversity offsetting calculations have been amended through discussions with the applicant’s Ecologist from chalk grassland to reflect the existing open mosaic habitat on previously developed land priority habitat and the future restored habitat of a similar nature.
We have been advised by the applicant’s Ecologist that the reference to chalk grassland is a reference to use of a seed mix, not to the habitat that is intended to develop as a consequence of sowing that mix. There are no proprietary seed mixes fully reflective of the type of vegetation found on mixed substrates. However proprietary chalk grassland mixes share many of the same species, hence the suggestion that these are appropriate as a sowing resource.
As open mosaic habitat on previously developed land often develops as a result of natural regeneration, it does not require seeding at all (please see SPG for details). However, this difference in approach is not enough to object to the application and it is anticipated that the finer details can be agreed through management plan discussions, and prior to the implementation of the habitat creation.
The EO in considering the Environmental Statement noted under the Invertebrate and Great Crested Newt sections that
“The site contains low populations of GCNs and reptiles (grass snake, slow worms and common lizards) and it is proposed that they are translocated to an existing receptor site to the north, which is already being used for the previous GCN translocation relating to the southern void.
I agree that the work proposed in 7.3.4 Appendix ESG (December 2015) would be required. However, much of it should have been done under the existing GCN licence relating to development of the southern void. This licence is not being fully complied with and the habitat is not currently of an adequate standard. The applicant’s ecologist has provided assurance that this area will be improved for GCNs and reptiles, but it will need to be closely monitored. The grazing density must be specified prior to commencement, though it could be adjusted with the agreement of the MPA.
The receptor site would also need to be secured through a long term legal agreement (Section 106) and be managed appropriately according to the method statement
submitted with the licence. The current management of the area around the newt ponds shown as white space on the restoration plans (Figure S4) as it is part of the area under the existing GCN licence, within which maximum grazing stocking density is specified. It is proposed that, in the short-medium term, management will be addressed and secured through future GCN licences issued to cover implementation of the permission. The longer-term management of this area (i.e. beyond the term of the licences) is something that can be brought in to the aftercare management plan.
Despite the above concerns regarding the management of the existing receptor site, I would advise that this development is unlikely to affect the conservation status due to the relatively low numbers of GCNs affected by the current proposals and the mitigation proposed. Please see below for further details.
The species protection provisions of the Habitats Directive, as implemented by the Conservation of Habitats and Species Regulations 2010, contain three "derogation tests" which must be applied by Natural England when deciding whether to grant a licence to a person carrying out an activity which would harm a EPS [European Protected Species] . For development activities this licence is normally obtained after planning permission has been obtained. The three tests are that:
• the activity to be licensed must be for imperative reasons of overriding public interest or for public health and safety; • there must be no satisfactory alternative; and • Favourable conservation status of the species must be maintained.
Notwithstanding the licensing regime, the local planning authority (LPA) must also address its mind to these three tests when deciding whether to grant planning permission for a development which could harm a EPS. A LPA failing to do so would be in breach the 2010 Regulations which requires all public bodies to have regard to the requirements of the Habitats Directive in the exercise of their functions.
As GCNs are likely to be using the development site a derogation licence will be required which can only be obtained if planning permission has been granted ….