Agenda Item: 7.c.

TO: Chair and Members of the Joint Powers Authority Board FROM: Habib F. Balian, Foothill Gold Line Chief Executive Officer

DATE: June 10, 2021

SUBJECT: Receive and File Monthly Project Status Update as of May 2021

RECOMMENDATION: That the JPA Board receive and file Monthly Project Status Update as of May 2021.

Executive Officer:

Habib F. Balian Chief Executive Officer

______Foothill Gold Line Project ______

Monthly Project Status Report

May 2021

METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021

TABLE OF CONTENTS

FOOTHILL GOLD LINE PROJECT STATUS Project Description ...... 3

Glendora to Montclair Segment...... 4

Management Issues ...... 4

Key Activities Completed This Period ...... 6

Key Future Activities ...... 7

Baseline Schedule…………………………………………………………………………………………...... 8

Float Trend………………………………………………...…………………………………………………………...9

Alignment Contract Status……………………………………………………………………………………………10

Alignment Construction Progress - This Period……………………………………………………………………12

Alignment Construction Progress - Next Period…………………………………………………………...………13

Alignment Construction Images……………………………………………………………………………………..14

Alignment Change Management Log………………………………………………………………………………22

Financial Status……………………………………………………………………………………………………………….24

2 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021

FOOTHILL GOLD LINE PROJECT DESCRIPTION

The Foothill Gold Line Construction Authority (also known as the Metro Gold Line Foothill Extension Construction Authority) is an independent transportation agency created in 1998 by the California State Legislature to plan, design and build the Metro Gold Line light rail system from Union Station in Downtown Los Angeles to the Montclair TransCenter in San Bernardino County. The $3 billion, 37-mile program is being built in three segments and when completed will connect the cities of Los Angeles, South Pasadena, Pasadena, Arcadia, Monrovia, Duarte, Irwindale, Azusa, Glendora, San Dimas, La Verne, Pomona, Claremont and Montclair to the expanding network of rail lines throughout Los Angeles and San Bernardino Counties.

The first segment of the line from Union Station to Pasadena was completed in 2003, and the second segment from Pasadena to Azusa was completed in 2015. The third segment, from Glendora to Montclair (Figure 1) broke ground in December 2017 and is being mostly funded by Los Angeles County Measure M with additional funds coming from: residual Measure R funds not used for the Pasadena to Azusa segment, State of California Transit and Intercity Rail Capital Program funds (including SB1 funds), and funding from San Bernardino County. Four contracts are being used to build the 12.3-mile, six station segment which is anticipated to reach substantial completion by 2028, if additional funding is available to exercise the Montclair option.

3 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021

GLENDORA TO MONTCLAIR MANAGEMENT ISSUES

ADDITIONAL FUNDING FOR POMONA TO MONTCLAIR

Due to unfavorable economic conditions affecting bid prices, the alignment contract was restructured to terminate in Pomona with a two-year option to extend to Montclair. Approximately $550 million is needed to extend the project from Pomona to Montclair. Staff is working with Metro and other appropriate entities to secure the additional funds needed to complete to project to Montclair.

COVID-19 PANDEMIC

On March 19, 2020, the Governor issued Executive Order N-33-20, which mandates that all residents of the State shelter in place. That Order excepted individuals needed to maintain continuity of federal critical infrastructure sectors, as outlined at https://www.cisa.gov/identifying-critical-infrastructure-during- covid-19. Transportation, which includes the construction of light rail projects, is identified as an exempt critical infrastructure sector. As such, the project can continue to proceed during the ongoing pandemic. However, the pandemic has resulted in many project participants, including Construction Authority staff, to begin working from home, and has increased the risk of third parties not performing as agreed. Construction Authority staff has been proactively working with all third parties and project stakeholders to ensure the project continues during the pandemic. To date, all third parties and project stakeholders have performed as agreed and no significant disruption to the project has occurred. Staff will continue to do everything possible to keep the project on schedule. Any significant disruption to the project that may occur will be mitigated to the fullest extent possible.

EXTENDED WORK HOURS AT THE GRADE CROSSINGS

The Alignment design-builder, Kiewit Parson Joint Venture (KPJV), made the assumption based on some language in the cities’ MCAs that they could work double shifts (approximately 17-hour days) at the grade crossings in order to comply with the closure durations requirements for the grade crossings. The double shifts result in KPJV needing approval from all four cities for extended work hours beyond the standard work hours allowed in each city. KPJV has been able to obtain general approval for extended work hours from La Verne and Pomona but not Glendora or San Dimas. As a result, KPJV is likely to not

4 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021

GLENDORA TO MONTCLAIR MANAGEMENT ISSUES (cont’d.)

meet the grade crossing closure durations required by the contract. Furthermore, KPJV has notified the Construction Authority that it will incur additional costs as a result of them not receiving the approval for extended work hours in San Dimas and Glendora, and that KPJV expects the Construction Authority to pay for these additional costs. Staff has evaluated this issue and finds no merit to KPJV’s position that the Construction Authority is responsible for any costs associated with KPJV not receiving general approval from the Glendora or San Dimas for extended work hours. However, staff will continue to work with KPJV and all of the corridor cities to find practical solutions that will keep the duration of work at the grade crossings to a minimum and mitigate any additional costs incurred by KPJV.

5 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021

GLENDORA TO MONTCLAIR KEY ACTIVITIES COMPLETED THIS PERIOD

Completed full closure at Elwood Avenue for utility relocation and construction of grade crossing Completed closure at Lone Hill Avenue for utility relocation and freight track relocation Began full closure at Loraine Avenue for utility relocation and construction of grade crossing Began full closure at Pasadena Avenue for utility relocation and construction of grade crossing Continued full closure at E Street for utility relocation and construction of grade crossing Continued full closure at Vermont Avenue for utility relocation and construction of grade crossing Continued full closure at Eucla Avenue for utility relocation and construction of grade crossing Continued Glendora Station pedestrian undercrossing Continued construction of MSE retaining walls in Glendora Continued construction of FRT and LRT bridge structures at Big Dalton Wash Continued construction of FRT and LRT bridge structures at San Dimas Wash Completed construction of FRT and LRT structures at Puddingstone Channel Continued construction of FRT and LRT bridge structures at Live Oak Channel Continued construction of FRT and LRT bridge structures at Thompson Creek Continued old freight track removal Continued installing new freight track in multiple locations CPUC has approved 48 of 49 grade crossings submitted CPUC continued reviewing applications for one grade crossing, and modifications to two approved crossing applications Authority and City staff continued to hold coordination meetings to discuss the project Design-builder continues to hold design task force meetings Design packages continue to be submitted and reviewed Project management submittals continue to be submitted and reviewed

6 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021

GLENDORA TO MONTCLAIR KEY FUTURE ACTIVITIES

Begin full closure at D Street for utility relocation and construction of grade crossing Begin full closure at Walnut Avenue for utility relocation and construction of grade crossing Begin construction of Route 66 bridge and Glendora station Receive approval of remaining CPUC applications Complete design Approve contractor project management plans

7 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021

MONTHLY SCHEDULE UPDATE – Apr 2021

8 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021

FLOAT TREND

400

350

300

250

200

150

100

50

0

-50

Critical Path

The re-design of the Foothill/Grand and Bonita/Cataract Bridges – Post-Tensioning Duct Location Change was added into the previous Update Schedule. The AFC of this re-design drives the start of the of the submittals and procurement for Foothill Blvd/Grand Ave Bridge which in turn commences the start of the construction for the Foothill Blvd/Grade Ave LRT Bridge substructure work. This substructure work drives out the midblock work for Barranca Ave to Grande which in turn drives out the LRT track work that will continue to flow through OCS work into testing, that concludes at Substantial Completion. Due to adding this re-design into the previous Update Schedule, the redesign shifted the longest path that remains in this current Update Schedule.

Project Float

The project float is currently 64 calendar days ahead the January 4, 2025 substantial completion date, which is lost 2 days from the previous schedule update due to the delay of the re-design of the Foothill/Grand – Post-Tensioning Duct Location Change.

9 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021 Progress Completed This Period (May 2021) Progress Planned Next Period (June 2021)

• Design • Design  At-Grade Crossings - La Verne 3 (AFC)  Segment 2C Corridor/Mid-Block (E St. to Garey Ave)  At-Grade Crossings - Glendora 2 (AFC) 100%  Communications BOP - San Dimas  Caltrans Walls Drawings 2A (Gladstone to - 100% Canyon Rd.) - SR-57 100%  TPSS Location and Site Plan Drawings AFC  Stations Drawings 100%  Track Alignment Drawings - LRT/FRT AFC  Communications Drawings - LRT 100%  LRT Foothill Blvd./Grand Ave & Bonita Ave./Cataract Ave. 100% (CONFIRMATION SET) (PCO 17)  Pomona At-Grade Crossings Drawings 100%  Monte Vista Pedestrian Undercrossing AFC

• Construction • Construction  See “Construction Progress This Period”  See “Construction Progress Next Period”

Areas of Concern Areas of Concern (Continued)

• Foothill/Grand and Bonita/Cataract • Bridges Post-Tensioning Duct Location Change – To remove the post-tensioning ducts from the bottom slab of the Foothill/Grand and Bonita/Cataract Bridges and add one additional girder to each of the bridges to carry the posttensioning ducts. •

10 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021 Cost Summary (3/31/21): Cost Assessment: Million(s) CONTRACT The Design-Build Contractor has earned 251.7 Million and currently Contract Award: 805.6 31.2% completion at the end of March 2021. The progress currently Executed Change Orders: 1.04 7.9% behind the early planned curve, which is due to the progress of Potential Change Orders: 0.5 several design packages. However, it does not critically impact the Current Forecast: 806.7 construction related to. Earned Value/Actual Cost: 251.7

Progress Curve:

100%

90%

80%

70%

60% Percent Completion: 50% Planned (Early): 39.2% 40% Planned (Late): 24.7% 30% Actual: 31.2% 20%

10%

0%

Early Late Actual

Schedule Summary (4/30/21): Contract Milestones:

Original Current MS Description Forecast Variance Notice To Proceed (NTP): 10/07/19 Contract Contract

Original Contract Duration: 1915 1 Substantial Completion 1/3/25 1/3/25 10/31/24 64 Current Contract Duration: 1915 2 Punchlist Completion 9/30/25 9/30/25 7/28/25 64 3 Final Acceptance 12/29/25 12/29/25 10/26/25 64 Elapsed Time from NTP: 571

Schedule Assessment: The project float is currently 64 calendar days ahead the January 4, 2025 substantial completion date after the re- design of the Foothill/Grand and Bonita/Cataract Bridges – Post-Tensioning Duct Location Change was added into the previous Update Schedule.

11 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021 ALIGNMENT CONSTRUCTION PROGRESS THIS PERIOD (May 2021)

Seg 1A (Barranca to Glendora): APU/Citrus College Station • Barranca Grade Crossing – Bungalow, Gate, Flasher • MSE wall, Utility Relocation, FRT track • Glendora Grade Crossing – Punch List • Glendora Station PUC • Foothill/Grand Grade Crossing – FRT track tie-in • Vermont Grade Crossing Closure/Reconstruction Glendora Station

Seg 1B (Glendora to Route 66): • Glenwood Permanent Closure/Reconstruction • Utility Relocation, FRT Track • Big Dalton Wash FRT– Girder, Approach Slabs, Deck Drain, FRT Asphalt • Elwood Grade Crossing Closure/Reconstruction – Reopen to Public • Pasadena Grade Crossing Closure/Reconstruction • Lorraine Grade Crossing Closure/Reconstruction

Seg 1C (Route 66 to Gladstone):

• San Dimas Wash –FRT Structure, LRT Seg 2A (Gladstone to San Dimas Canyon): Abutment Backfill • Gladstone Grade Crossing Closure/Reconstruction • MSE wall, Utility Relocation, FRT track – Punch List • Lone Hill Grade Crossing Short Term • Eucla Grade Crossing Closure/Reconstruction Closure • Marshall Creek – Footing, Backwall, Lightweight Backfill • San Dimas / Commercial—Sidewalk / ADA ramps San Dimas Station • San Dimas / Bonita—Traffic signal

Seg 2B (San Dimas Canyon to E. St): • Wheeler Grade Crossing – Punch List • Live Oak Channel— Drilled Shafts

La Verne Station

Seg 2C (E. St to Garey): • Fulton Grade Crossing Closure/Reconstruction – Punch List

• E St. – Traffic Signal • Thompson Creek —Backwall • Pomona Station FRT ductbank

12 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021 ALIGNMENT CONSTRUCTION PROGRESS PLANNED NEXT PERIOD (June 2021)

APU/Citrus College Station

Seg 1A (Barranca to Glendora): • Little Dalton Structure

Glendora Station

Seg 1B (Glendora to Route 66):

• None

Seg 1C (Route 66 to Gladstone): • Route 66 LRT structure

Seg 2A (Gladstone to San Dimas Canyon):

• Walnut Grade Crossing

San Dimas Station

Seg 2B (San Dimas Canyon to E. St):

• None

La Verne Station Seg 2C (E. St to Garey): • None

Pomona Station

13 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021 ALIGNMENT CONSTRUCTION IMAGES

Segment 1A

Barranca Crossing Systems Bungalow

Covina Irrigation Line—tie in

Glendora Pedestrian Undercrossing 14 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021

Glendora PUC

Vermont/ADA Grade Crossing

Big Dalton Wash Structure 15 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021

Big Dalton Wash FRT deck drains Segment 1B

Elwood Grade Crossing

Elwood Grade Crossing—Reopened

16 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021

Lorraine Grade Crossing

Lorraine to Big Dalton Wash—FRT Track

Pasadena Grade Crossing—Pothole for utilities

17 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021 Segment 1C

Lone Hill Grade Crossing - Paving

Lone Hill Grade Crossing Short Term Closure – Reopened

San Dimas Wash to Lone Hill—MSE Wall 18 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021

San Dimas Wash Bridge Structures Segment 2A

Eucla Grade Crossing

Eucla Systems Ductbank 19 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021

Bonita / Cataract—new curb & gutter Segment 2B

Marshall Creek FRT Structures

San Dimas/Commercial—Sidewalk ADA Ramp

20 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021

Segment 2C

Thompson Creek FRT Structure

Thompson Creek FRT Structure

21 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021

Metro Gold Line Foothill Extension Construction Authority 406 East Huntington Drive, Suite 202 Monrovia, CA 91016 Date: 5/24/2021 12:09:33 PM Change Management Log Pacific Daylight Time Page: 1 of 2

Project: Foothill Gold Line - Alignment Project (C2002)

Original Contract Value: $805,634,000 Approved Change Orders: $1,084,770 0.13% Pending Change Orders: $0 0.00% Current Contract Total: $806,718,770 Pending Contract Total: $806,718,770 0.13%

Change Orders

Number Title Time Extension Amount

EXECUTED Change Orders

CO-001 Authority Office Facilities Reduction 0 ($62,215) CO-002 Delete La Verne Station Pedestrian Undercrossing Design 0 ($50,717) CO-003 Johnstone Peak - Equipment Installation 0 $287,309 CO-004 Delete Power/Electrical Provisions for EV Bikes 0 ($9,738) CO-005 Delete Signalization at La Verne Ave / Arrow Hwy Intersection 0 ($390,447) CO-006 Eucla Bungalow Changes 0 $172,549 CO-007 TPSS 2, 3, and 7 Site Changes 0 $25,490 CO-008 Lone Hill Bridge Aesthetic Enhancements- Design 0 $83,320 CO-009 Wheeler Ave. Sanitary Sewer (SS) Betterment 0 $128,068 CO-010 A Street and E Street Sanitary Sewer (SS) Betterments 0 $184,851 CO-011 Gladstone St. Asbestos Pipe 0 $6,860 CO-012 Sound Wall No. 8 Configuration Change 0 ($306) CO-013 COVID-19 Pandemic Mitigation (7/13/20 to 10/18/20) 0 $39,758 CO-014 Delete Signalization at Foothill Blvd. / Elwood Ave. Intersection 0 ($448,534) CO-015 Incorporate Revised SCRRA MCA and Amendment into Contract Documents 0 $521,159 CO-016 Extend Paving Limits at Loraine/Lemon 0 $9,071 CO-017 Repair/Restore FRT Track after BNSF Derail on 12/2/20 0 $9,601 CO-018 SCRRA Rule Changes 0 $27,499 CO-019 Johnstone Peak Radio - RF Testing 0 $106,106 CO-020 Parallel Communications Design for Alternate Station Parking 0 $404,929 CO-021 (part 1) Special Trackwork Changes - No. 10 Turnouts (milling for guardrail plates) 0 $16,432 CO-021 (part 2) Special Trackwork Changes - No. 10 Turnouts (bolted heel blocks) 0 $23,725

Executed Subtotal: $1,084,770

PENDING Change Orders

Pending Subtotal:

Change Orders Total: $1,084,770 Open PCOs Open RFCs PCO Number Title RFC Number Title

Foothill/Grand and Bonita/Cataract - post-tensioning duct location PCO - 00017 RFC - 00008 RFC-0008-VE Marshall Creek change RFC - 00009 RFC-0009-COVID-19 Pandemic Mitigation Continued PCO - 00019 FRT Rehabilitation - Pasadena Subdivision RFC - 00010 RFC-0010-Stations Architectural Details PCO - 00021 Bonita/Cataract Detour/MOT Changes Parking Facilities Communications Design, Procurement, and RFC - 00011 RFC-0011- VE Foothill Grand PCO - 00022 Installation Change PCO - 00023 Delete Improvements at Santa Fe Street and Garey Avenue PCO - 00024 Fence Color Change PCO - 00025 Delete Permeable Pavers PCO - 00026 Station and Plaza Furnishings Change PCO - 00027 Design and Construct Parking Facilities

Open RFC Notices Number Title

RFC - 00006 RFC-0006-Work Hours in the City of Glendora and City of San Dimas RFC - 00014 RFC-0014-Unknown Asbestos E St and Arrow Hwy RFC - 00015 RFC-0015-Unknown Asbestos Caltrans Road RFC - 00016 RFC-0016-Unknown Obstruction at Little Dalton Wash

Change Management Risk Log

22 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021

Metro Gold Line Foothill Extension Construction Authority 406 East Huntington Drive, Suite 202 Monrovia, CA 91016 Date: 5/24/2021 12:09:33 PM Change Management Log Pacific Daylight Time Page: 2 of 2

Project: Foothill Gold Line - Alignment Project (C2002) Open RFC Notices Number Title

RFC - 00017 RFC-0017-Uncovered Hazardous Material at Eucla RFC - 00018 RFC-0018-COVID-19 Pandemic Mitigation

Change Management Risk Log

23 METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Monthly Project Status Report Period Ending: May 31, 2021

FOOTHILL GOLD LINE FINANCIAL STATUS Project Operating Budget Summary in Millions of Dollars May 31, 2021

( a ) ( b ) (c=a-b) ( d ) Funding Current Committed to Uncommitted Revenues FINANCIAL PLAN Budget Project Funds Received Cities 42.2 42.2 - - Measure R - 2B 96.5 96.5 - 96.5 SBCTA 94.4 44.5 49.9 2.9 Measure M 1,019.0 1,019.0 - 267.6 Other - Cap and trade 249.2 249.2 - - Other - Metro 126.0 126.0 - Other - Miscellaneous 449.6 - 449.6 - Total Revenues 2,076.9 1,577.4 499.5 367.0

( a ) ( b ) ( c ) (d=a-b) Current Current Current Current Budget Obligation Expenditures Available Balance EXPENSES Program Management and Admin - Pomona 196.0 50.0 38.2 146.0 Proram Management and Admin - Montclair 14.0 - - 14.0 Master Cooperative Agreements 55.0 5.0 2.8 50.0 ROW DB2 Alignment 87.0 30.0 12.4 57.0 ROW DB3 Parking 57.0 30.0 23.8 27.0 Construction DB2 Alignment - Pomona 807.7 805.6 264.9 2.1 Construction DB2 Alignment - Montclair 381.3 - - 381.3 Construction DB3 Parking 120.0 - - 120.0 MTA Project Costs 154.9 - - 154.9 Project Contingency 164.0 - - 164.0 Planning 40.0 40.0 40.0 - Total Project 2,076.9 960.6 382.1 1,116.3

24