Dynamic Analysis of Large Diameter Piles Statnamic Load Test

Total Page:16

File Type:pdf, Size:1020Kb

Dynamic Analysis of Large Diameter Piles Statnamic Load Test Dynamic analysis of large diameter piles Statnamic load test K.J. Bakker Delft University of Technology, Delft, and WAD32 bv, IJsselstein, The Netherlands F.J.M. Hoefsloot Fugro Ingenieursbureau, Leidschendam, The Netherlands E. de Jong Volker Wessels Stevin Geotechniek bv, Woerden, The Netherlands ABSTRACT: To check for the bearing capacity of a newly introduced large diameter casing pile, both common type CPT analysis as well as static load testing was used. In addition to that two piles where tested using the Statnamic load testing technique. For the latter, in addition to the standard Unloading Point method by Middendorp (1992), a dynamic analysis with Plaxis was done. Further the static load test results were used to calibrate the soil parameters for the analysis. The numerical results were used to corroborate the physical test results. Comparing the Dynamic load testing results according to Middendorp with the Numerical results; it comes forward that some additional mass below the pile tip, more or less moving with the pile, needs to be taken into account. Further after Mullins (2002), the damping is calculated for the stationary part of track 4. This gives overall a better agreement with static numerical analysis for the bearing capacity. Based on an extrapolation of the physical test up to deformation required by NEN 6743-1 (2006), an ultimate load bearing capacity of 15.5MN was established. 1 INTRODUCTION Related to the city extension Leidsche Rijn near Utrecht, The Netherlands, and the extension of the railway between Utrecht and Gouda to four railway tracks, a total of 20 new viaducts need to be build. In order to improve the foundation concept of the classic multi pile pier foundation, an alternative was proposed that includes the use of bored casing piles with a diameter of 1.65m. This innovation reduces the original design of 48 prefab concrete piles to 6 large diameter casing piles only. Since the bridges are intended to support the railway track, the design requirements are very strict. On the one hand the piles should be capable to bear a design load of at the least 12,000 kN, on the other hand the deformation during train passing’s should be less than 10 mm. Since bored piles show a relatively less favourable load-displacement curve compared to driven piles, to improve the stiffness, the introduction of pile tip grouting device was adopted. Both the large diameter casing pile in combination with the grout injection device at the tip Figure 1 Stages in statnamic testing was a first time application in the Netherlands. For total of three piles were instrumented and tested on the evaluation of the bearing capacity, as a start site by means of a static load test and further the CPT’s after prestressing the grouting device, were deformation of all piles were monitored during taken and evaluated as a first step in checking the construction and the actual passing of the first trains influence of the installation procedure. In addition a in December 2007. Details are given in de Jong et al (2010). In addition, after that it became clear that a deformation rate was above 0.3mm/h up to a suitable testing device would be available, two maximum of 4 hours. At a load of 6,000kN the piles additional test piles were tested with a 16MN stat- were unloaded to 4,000kN and reloaded to 6,000kN namic device. in steps of 1,000kN. Only one of the piles was In addition to the standard procedure of checking loaded up to 8,000kN. these tests using the UPM (Unloading Point More details and results of the Static Pile test can Method), by Middendorp (1992), a dynamic axi- be found in de Jong et al (2010). symmetric Finite Element analysis of the load tests was performed. The result of the static load tests After that the Static load tests were done, the both with respect to load and deformation was used introduction of a 16MN Statnamic device in the to calibrate the soil parameters for the dynamic Netherlands by Fugro made it possible to test the numerical analysis. Further the dynamic response as piles to loads that would approach the ultimate calculated with Plaxis was put into the same UPM bearing capacity of the piles. evaluation procedure for further corroboration of the In addition to the field test it was decided to try method. for a dynamic finite element analysis to get a better understanding and to create added value to the field In this paper a comparison between the UPM test evaluation procedure by Middendorp and the The Statnamic load test were done not too far Numerical analysis with Plaxis will be described. from the site were the Static tests were done, and Attention shall be given to the effect of drained had a similar soil stratigraphy. Therefore the static bearing capacity for design and undrained behaviour test were used as an additional source of information during the test. for calibration of the soil parameters for the dynamic Some typical modelling issues such as mesh analysis. The static analysis was back-analysed and finesse at pile tip and dynamic effects in interface soil parameters were calibrated and applied for the elements will be discussed. first prediction of the Statnamic test. In addition to understanding the dynamic behaviour of the pile, the calibrated numerical model opens up the possibility to evaluate the equivalent 3 STATNAMIC TESTING static load bearing capacity, which can be compared to the Dutch code for static load capacity NEN 6743 In November 2008 two Statnamic load tests were (2007). carried out on sacrificial test piles that had been installed in 2005. Originally it was intended to test these piles to refusal by means of a static load test. 2 STATIC LOAD TESTING AND SOIL Such a test would have required a load of PARAMETER ESTIMATION approximately 20,000kN, even though the piles have a limited length of 13m. Before it was decided to do statnamic testing a static In a Statnamic load test, pile loading is achieved pile test was done; although it was known in by launching a reaction mass. Due to the high advance that the limit load with respect to bearing acceleration of the reaction mass, the effectiveness capacity could not be reached.. of the load is increased by a factor of about twenty. At bridge number 6 a row of three, 17.85m long, The loading is perfectly axial, the pile and the soil 1.65m diameter piles at a centre to centre distance of are compressed as a single unit and the static load- 3.75m where individually tested. The goal of these displacement behaviour of the pile can be tests was verification of the load displacement determined if a series of tests is performed. behaviour up to 8,000 kN, i.e. the pile stiffness. Given the fact that the information of the static Strains were measured at three levels with load test up to a load of 8,000kN was already vibrating wire strain gauges, and a load cell was available, the two test piles were only tested once installed at the top. Further displacements were with the maximum Statnamic load of approximately measured at the pile head by high accuracy 16MN. The general description of the statnamic test levelling. In addition to the deadweight of 1,000kN has been given by Bermingham et al (1992). The test the reaction frame was anchored to the ground by 8 procedure itself is according to the draft European Gewi-anchors with a capacity of 1,250kN each. guideline (Hölsher and van Tol, 2009). Prior to pile installation one CPT was carried out at the centre of each pile. Based on the 3 CPT’s before pile installation the ultimate bearing capacity 4 EMPIRICAL EVALUATION OF BEARING of the piles was estimated to be about 20,000kN. CAPACITIY During the static test, the piles were loaded in steps of 1,000kN. The load was then kept constant According to Middendorp’s (1992) simplified for 1 hour, a time that was extended if the evaluation procedure, that dynamic force balance may be written as: displacement. It is customary to back analyse the damping for FtFtFtFtstat() u () v () a () (1) Where Fu (t) = static soil reaction (point and shaft) Fv(t) = damping force (depends on pile velocity) Fa(t) = Inertia force, depending on mass and acceleration Both Fstat(t) and Fa(t) have been measured or can be inferred from the measuring data. Whereas Fu(t) is the unknown soil resistance we want to establish and further Fv(t) is also relatively unknown and depends on the known pile velocity. However, as the loading time is relatively long compared to the velocity of pressure waves in the pile, which is in the order of 3,800m/s, whereas the loading time is in the order of 0,08s, pressure waves may travel up and down the pile, 12 times within this period. For that reason the load may be judged Figure 2 Soil resistance as back-analyzed from the Statnamic test, assuming averaged damping in track 4 of to act semi-static. The effect will be that the pile will the test; concave loading curve is found displace more or less as a rigid mass. For that reason it is assumed that the time of maximum this whole trajectory and taking the average value. displacement equals zero velocity of the pile. According to this standard interpretation method, the Realising that at this point; i.e. referred to as the Soil resistance can be back analysed and will result “Unloading Point” the damping is zero, the pile in the curve given in Figure 2.
Recommended publications
  • Post Grouting Drilled Shaft Tips Phase I
    Post Grouting Drilled Shaft Tips Phase I Principal Investigator: Gray Mullins Graduate Students: S. Dapp, E. Frederick, V. Wagner Department of Civil and Environmental Engineering December 2001 DISCLAIMER The opinions, findings and conclusions expressed in this publication are those of the authors and not necessarily those of the State of Florida Department of Transportation. ii CONVERSION FACTORS, US CUSTOMARY TO METRIC UNITS Multiply by to obtain inch 25.4 mm foot 0.3048 meter square inches 645 square mm cubic yard 0.765 cubic meter pound (lb) 4.448 Newtons kip (1000 lb) 4.448 kiloNewton (kN) Newton 0.2248 pound kip/ft 14.59 kN/meter pound/in2 0.0069 MPa kip/in2 6.895 MPa MPa 0.145 ksi kip-ft 1.356 kN-m kip-in 0.113 kN-m kN-m .7375 kip-ft iii PREFACE The investigation reported was funded by a contract awarded to the University of South Florida, Tampa by the Florida Department of Transportation. Mr. Peter Lai was the Project Manager. It is a pleasure to acknowledge his contribution to this study. The full-scale tests required by this study were carried out in part at Coastal Caisson’s Clearwater location. We are indebted to Mr. Bud Khouri, Mr Richard Walsh, and staff for providing this site and also for making available lifting, moving, and excavating equipment that was essential for this study. We thank Mr. Ron Broderick, Earth Tech, Tampa for donating his time, equipment and grout materials necessary for grouting shafts at Site I and II. We are indebted to Mr.
    [Show full text]
  • NCHRP Report 461: Static and Dynamic Lateral Loading of Pile Groups
    NATIONAL COOPERATIVE HIGHWAY RESEARCH NCHRP PROGRAM REPORT 461 Static and Dynamic Lateral Loading of Pile Groups TRANSPORTATION RESEARCH BOARD NATIONAL RESEARCH COUNCIL TRANSPORTATION RESEARCH BOARD EXECUTIVE COMMITTEE 2001 OFFICERS Chair: John M. Samuels, Senior Vice President-Operations Planning & Support, Norfolk Southern Corporation, Norfolk, VA Vice Chair: E. Dean Carlson, Secretary of Transportation, Kansas DOT Executive Director: Robert E. Skinner, Jr., Transportation Research Board MEMBERS WILLIAM D. ANKNER, Director, Rhode Island DOT THOMAS F. BARRY, JR., Secretary of Transportation, Florida DOT JACK E. BUFFINGTON, Associate Director and Research Professor, Mack-Blackwell National Rural Transportation Study Center, University of Arkansas SARAH C. CAMPBELL, President, TransManagement, Inc., Washington, DC JOANNE F. CASEY, President, Intermodal Association of North America JAMES C. CODELL III, Secretary, Kentucky Transportation Cabinet JOHN L. CRAIG, Director, Nebraska Department of Roads ROBERT A. FROSCH, Senior Research Fellow, John F. Kennedy School of Government, Harvard University GORMAN GILBERT, Director, Oklahoma Transportation Center, Oklahoma State University GENEVIEVE GIULIANO, Professor, School of Policy, Planning, and Development, University of Southern California, Los Angeles LESTER A. HOEL, L. A. Lacy Distinguished Professor, Department of Civil Engineering, University of Virginia H. THOMAS KORNEGAY, Executive Director, Port of Houston Authority BRADLEY L. MALLORY, Secretary of Transportation, Pennsylvania DOT MICHAEL
    [Show full text]
  • A Qljarter Century of Geotechnical Researcll
    A QlJarter Century of Geotechnical Researcll PUBLICATION NO. FHWA-RD-98-139 FEBRUARY 1999 1111111111111111111111111111111 PB99-147365 \c-c.J/t).:.. L~.i' . u.s. D~~~~~~~Co~~~~~erce~ Natronal_Tec~nical Information Service u.s. DepartillCi"li of Transportation Spnngfleld, Virginia 22161 Research, Development & Technology Turner-Fairbank Highway Research Center 6300 Georgetown Pike McLean, VA 22101-2296 FOREWORD This report summarizes Federal Highway Administration (FHW!\) geotechnical research and development activities during the past 25 years. The report incl!Jde~: significant accomplishments in the areas of bridge foundations, ground improvenl::::nt, and soil and rock behavior. A fourth category included important miscellaneous efrorts tl'12t did not fit the areas mentioned. The report vlill be useful to re~earchers and praGtitior,c:;rs in geotechnology. --------:"--; /~ /1 I~t(./l- /-~~:r\ .. T. Paul Teng (j Director, Office of Infrastructure Research, Development. and Technologv NOTiCE This document is disseminated under the sponsorship of the Department of Transportation in the interest of information exchange. The United States G~)\fernm8nt assumes no liahillty for its contt?!nts or use thereof. Thir. report dor~s not constiil)tl":: a standard, specification, or regu!p,tion. The; United States Government does not endorse products or n18;1ufaGturers, Traderrlc,rks or nianufacturers' narl1es appear in thi;-, report only bec:8'I)Se they arc considered essential to tile object of the document. Technical Report Documentation Page 1. Report No. 2. Government Accession No. 3. Recipient's Catalog No. FHWA-RD-98-139 4. Title and Subtitle 5. Report Date A Quarter Century of Geotechnical Research February 1999 6. Performing Organization Code ).
    [Show full text]
  • Soils and Foundation Handbook”, a Minimum Core Barrel Size of 61 Mm (2.4”) I.D
    Soils and Foundations Handbook April 2004 State Materials Office Gainesville, Florida This page is intentionally blank. i Table of Contents Table of Contents ......................................................................................................... ii List of Figures ............................................................................................................. xi List of Tables.............................................................................................................xiii Chapter 1 ......................................................................................................................... 1 1 Introduction ............................................................................................................... 1 1.1 Geotechnical Tasks in Typical Highway Projects.................................................. 2 1.1.1 Planning, Development, and Engineering Phase ...................................... 2 1.1.2 Project Design Phase................................................................................. 2 1.1.3 Construction Phase.................................................................................... 2 1.1.4 Post-Construction Phase............................................................................ 3 Chapter 2 ......................................................................................................................... 4 2 Subsurface Investigation Procedures ........................................................................ 4 2.1
    [Show full text]
  • Appendix a Procedures & Commentary for Shaft 1-2-3
    APPENDIX A PROCEDURES & COMMENTARY FOR SHAFT 1-2-3 Nomenclature %R = percent recovery of rock coring (%) a = adhesion factor applied to Su (DIM) b = coefficient relating the vertical stress and the unit skin friction of a drilled shaft (DIM) bm = SPT N corrected coefficient relating the vertical stress and the unit skin friction of a drilled shaft (DIM) D = diameter of drilled shaft (FT) Db = depth of embedment of drilled shaft into a bearing stratum (FT) Dp = diameter of the tip of a drilled shaft (FT) f, ff = angle of internal friction of soil (DEG) fss , q = nominal unit shear resistance (TSF) g = unit weight (pcf) k = empirical bearing capacity coefficient (DIM) K = load transfer factor N = average (uncorrected) Standard Penetration Test blow count, SPT N (Blows/FT) Nc = bearing capacity factor (DIM) Ncorr = corrected SPT blow count qs = average splitting tensile strength of the rock core (TSF) qu = average unconfined compressive strength of the rock core (TSF) Su = undrained shear strength (TSF) s'v = vertical effective stress (TSF) A-1 Appendix A (continued) Procedures Commentary SECURITY NOTE: Microsoft XP users must set Security Level in Macro Security to Medium. This is done in Tools - Options - Macro Security - Security Level. General Worksheet Enter Job Name Job Name must be entered before analysis is run. Enter Job Location Job Location is optional. Enter Engineer Engineer is optional. Enter Boring Log Information The Boring Log worksheet can be displayed by clicking the Boring Log button or clicking on the Boring Log sheet tab at the bottom of Excel (see Procedures & Commentary for Boring Log Worksheet below).
    [Show full text]
  • Soils and Foundations Handbook 2016
    Soils and Foundations Handbook 2016 State Materials Office Gainesville, Florida This page is intentionally blank. i Table of Contents Table of Contents ......................................................................................................... ii List of Figures ............................................................................................................ xii List of Tables ............................................................................................................. xiv Chapter 1 1 Introduction ............................................................................................................... 1 1.1 Geotechnical Tasks in Typical Highway Projects.................................................. 1 1.1.1 Planning, Development, and Engineering Phase ...................................... 1 1.1.2 Project Design Phase ................................................................................. 2 1.1.3 Construction Phase .................................................................................... 2 1.1.4 Post-Construction Phase ............................................................................ 2 Chapter 2 2 Subsurface Investigation Procedures ........................................................................ 4 2.1 Review of Project Requirements ..................................................................... 4 2.2 Review of Available Data................................................................................ 4 2.2.1 Topographic Maps....................................................................................
    [Show full text]
  • Post Grouting Drilled Shaft Tips Phase II
    Post Grouting Drilled Shaft Tips Phase II Principal Investigator: Gray Mullins Research Associate: Danny Winters Department of Civil and Environmental Engineering June 2004 DISCLAIMER The opinions, findings and conclusions expressed in this publication are those of the authors and not necessarily those of the State of Florida Department of Transportation. ii CONVERSION FACTORS, US CUSTOMARY TO METRIC UNITS Multiply by to obtain inch 25.4 mm foot 0.3048 meter square inches 645 square mm cubic yard 0.765 cubic meter pound (lb) 4.448 Newtons kip (1000 lb) 4.448 kiloNewton (kN) Newton 0.2248 pound kip/ft 14.59 kN/meter pound/in2 0.0069 MPa kip/in2 6.895 MPa MPa 0.145 ksi kip-ft 1.356 kN-m kip-in 0.113 kN-m kN-m .7375 kip-ft iii PREFACE This research project was funded as a supplemental contract awarded to the University of South Florida, Tampa by the Florida Department of Transportation. Mr. Peter Lai was the Project Manager. Again, it is a pleasure to acknowledge his contribution to this study. This project was carried out in part with the cooperation and collaboration of Auburn University and the University of Houston. The contributions provided by these institutions are greatly appreciated with particular acknowledgment to Dr. Dan Brown and Dr. Michael O’Neill, respectively. Interest expressed by State and Federal Agencies such as Georgia DOT, Texas DOT, Mississippi DOT, South Carolina DOT, Arkansas DOT, Alabama DOT, Cal Trans, and the FHWA Eastern Federal Lands Bureau is sincerely appreciated. Likewise, the principal investigator is indebted to the vast interaction afforded by Applied Foundation Testing, Beck Foundation, and Trevi Icos South.
    [Show full text]
  • Item #0702768 Statnamic Axial Load Testing of Drilled Shaft
    Rev 4/09 ITEM #0702768 STATNAMIC AXIAL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting a Statnamic Load Test and reporting the results. The Contractor shall supply all material and labor as hereinafter specified and include prior to, during and after the load test. The test shaft shall be constructed at the location shown on the site plan and in accordance with the requirements of these special provisions and also as outlined elsewhere in project plans and/or contract documents. Materials: The Contractor shall furnish all materials required to install the Statnamic testing apparatus, conduct the load test, and remove the load test apparatus as required. The Statnamic testing apparatus to be provided shall have a load capacity as called for in the project plans and/or contract documents and shall be equipped with all necessary equipment, materials and instrumentation. Construction Methods: 1. Qualification of Stanamic Load Testing Personnel and Submittals: The Contractor shall employ a qualified Professional Engineer registered in the State of Connecticut and experienced in the conducting and reporting of a Statnamic load test to design, setup, perform and prepare a report of the Statnamic load test. The qualifications of the testing personnel shall be submitted to the Engineer for review and approval. The testing personnel shall have successfully completed and submit the names of no less than three (3) Stanamic load tests on drilled shafts of similar dimensions and capacities in the past three (3) years. The list of projects shall contain names and phone numbers of owner's representatives who can verify the testing personnel participation on those projects.
    [Show full text]
  • A.1 Statnamic the Statnamic Load Test
    A.1 Statnamic The Statnamic Load Test (STN) has been developed by TNO and Berminghammer Foundation Equipment. The principle of the test is based on the launching of a reaction mass by burning fuel in a closed pressure chamber. This reaction mass is only 5% of the weight needed for a static load test. Loading is perfectly axial. Figure A1-1 represents the successive stages of a Statnamic load test. Phase I is the situation just before launching. A cylinder with pressure chamber has been connected to the pile head and the reaction mass has been placed over the piston. In phase II the solid fuel propellant is ignited inside the pressure chamber, generating high-pressure gases and accelerating the reaction mass. At this stage the actual loading of the pile takes place, as an equal and opposite reaction force gently loads the pile. The applied pile force, displacement and acceleration are directly monitored. The upward movement of the reaction mass results in space, which is filled by the gravel (phase III). Gravity causes the gravel to flow over the pile head as a layer, catching the reaction mass and transferring impact forces to the subsoil (phase IV). Available device loads are 1, 2, 3, 4, 5, 8, 16, 20, 30, and 40 MN. The testing range is between 25% and 100% of the device load. Devices of 100MN are under design and will be manufactured.. During the test the reaction mass reaches a height between 2-3 m and then falls back. For high loads of 5-30 MN, gravel is used to catch the reaction mass.
    [Show full text]
  • Florida Department of Transportation District VI DESIGN-BUILD
    Florida Department of Transportation District VI DESIGN-BUILD REQUEST FOR PROPOSAL for SR 90 (Tamiami Trail) 2.6 mile Bridging From East of Osceola Camp to West of Airboat Association of Florida Financial Projects Number(s): 434922-1-52-01 Federal Aid Project Number(s): Contract Number: E6J69 DRAFT Request for Proposal (DRAFT) SR 90 (Tamiami Trail) 2.6 mile Bridging From East of Osceola Camp to West of Airboat Association of Florida July 20, 2015 Table of Contents I. Introduction. .......................................................................................................................1 A. Design-Build Responsibility....................................................................................... 4 B. Department Responsibility ........................................................................................ 4 II. Schedule of Events. .............................................................................................................5 III. Threshold Requirements. ..................................................................................................7 A. Qualifications .............................................................................................................. 7 B. Joint Venture Firm ..................................................................................................... 7 C. Price Proposal Guarantee .......................................................................................... 7 D. Pre-Proposal Meeting ................................................................................................
    [Show full text]
  • KL118 Case Study: Analysis of Different Bore Pile Testing Methods
    ctbuh.org/papers Title: KL118 Case Study: Analysis of Different Bore Pile Testing Methods Authors: Peter Ramstedt, Project Director, Turner International LLC David Terenzio, Design Manager, Turner International LLC Mathew Hennessy, Assistant Project Manager, Turner International LLC Chien Jou Chen, Project Manager, Turner International LLC Subjects: Building Case Study Structural Engineering Keywords: Belt Truss Concrete Foundation Mega Column Publication Date: 2016 Original Publication: Cities to Megacities: Shaping Dense Vertical Urbanism Paper Type: 1. Book chapter/Part chapter 2. Journal paper 3. Conference proceeding 4. Unpublished conference paper 5. Magazine article 6. Unpublished © Council on Tall Buildings and Urban Habitat / Peter Ramstedt; David Terenzio; Mathew Hennessy; Chien Jou Chen KL118 Case Study: Analysis of Different Bore Pile Testing Methods | KL118 案例研究:不同基桩试验方法之采用分析 Abstract | 摘要 Peter Ramstedt Project Director | 项目总监 In the construction of tall towers a variety of pile testing methodologies are used. Piles can be Turner International LLC 特纳国际有限公司 tested for many purposes including the optimization of pile design, operational verification, and quality assurance of completed piles or perhaps for design verification. The paper will provide Kuala Lumpur, Malaysia 吉隆坡,马来西亚 an overview of the three types of bore pile tests conducted for the KL118 tower. Because of the various desired test results and specific site conditions, this project has used three types of bore Peter Ramstedt is leading Turner’s Project Management Services for the Warisan Merdeka Development in Kuala pile testing methodologies: Statnamic, conducted on three of the 137 tower bore piles (each Lumpur, Malaysia which includes the iconic 118 story Merdeka pile being 2.2 meters in diameter, 60 meters deep) and four of the 427 car park bore piles; Bi- PNB118.
    [Show full text]
  • Statnamic Hoefsloot 270110
    Statnamic Pile Load Testing Flip Hoefsloot, Fugro The Netherlands January 2010 Date www.fugro.com www.fugro.fr Contents Menu Load Testing Methods Description Statnamic Video of Test Application Interpretation Guidelines Conclusion Date www.fugro.com www.fugro.fr Load Testing Methods STATIC HighHigh 100 % pressurepressure gasgas Load Displacement STATNAMIC DYNAMIC 5-10% 1-2 % Strain Load Acceleration Displacement Date www.fugro.com www.fugro.fr Description Stanamic A = Pile B = Load cell C = Cylinder D = Piston with chamber E = Platform F = Silencer 1 2 G = Reaction mass H = Gravel Container I = Gravel J = Laser K = Laser beam L = Laser sensor 3 4 Date www.fugro.com www.fugro.fr Description Stanamic Fugro Profound Clients Knowledge and experience Word wide Statnamic (Peter Middendorp) Date www.fugro.com www.fugro.fr Description Stanamic Hydraulic Catching Mechanism Containers filled with local material (gravel or equivalent) 4 test a day Simple inspection ignition system Transport on one trailer Date www.fugro.com www.fugro.fr Description Stanamic Equipment: 80 tons reaction mass 7 trailers for transport 2 to 3 days a test one cycle of testing Date www.fugro.com www.fugro.fr Video of Test Date www.fugro.com www.fugro.fr Application, Static Load Test Advantages: •Static behaviour •Separation of: •End Bearing •Shaft Friction Disadvantages: •Cost •Selection of Test Piles Date www.fugro.com www.fugro.fr Application, Dynamic Load Test Advantages: •Low Cost •Test on all Piles Disadvantages: •Dynamic Pile-Soil behaviour •High stresses in Pile
    [Show full text]