Social Monitoring Report

Semiannual Monitoring Report October 2017-March 2018 July 2018

IND: Railway Sector Investment Program

Prepared by Ministry of Railways for the Government of and the Asian Development Bank.

This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Indian Government Ministry of Railways Asian Development Bank

Multitranche Financing Facility No. 0060‐IND Loans No. 2793‐IND, 3108‐IND Railway Sector Investment Program Track Doubling and Electrification on Critical Routes

Resettlement and Rehabilitation Implementation Status Semi Annual Report October 2017 ‐ March 2018

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

1. Introduction and Project Background ...... 1 2.Contents Legal and Policy Frame Work ...... 3 3. Insitutional arrangement and implementation mechanism ...... 4 4. Greivance Rederess Committee ...... 6 5. Progress on Subprojects...... 6 5.1 Global Progress ...... 6 5.2 Important events related to R&R from October to March 2018...... 6 5.3 NGO – Assistance to RVNL ...... 7 5.3.1 NGO contract for Sambalpur‐Titlagarh project ...... 7 5.3.2 NGO contract for Raipur‐Titlagarh project ...... 7 5.3.3 Assistance for ‐Tinaighat project ...... 7 5.4 General Consultant ...... 7 5.5 Daund‐Gulbarga (Maharashtra Section and Sections) ...... 8 5.6 Sambalpur–Titlagarh project ...... 8 5.7 Raipur‐Titlagarh project ...... 17 5.8 Hospet‐Tinaighat project ...... 17 5.9 Electrification of Pune‐Guntakal project ...... 24 6. Summary table ...... 25 Annexure I: LA Direct purchase Act Government of Karnataka ...... 33 Annexure II: Notification issued by Odisha Revenue Department ...... 35 Annexure III: Approved note for extension of R&R personals ...... 36 Annexure IV: R&R Sale Deed of registerd land under direct purchase Hospet‐Tinaighat project ...... 38 Annexure V: Direct purchase payment details of Gadag village in HT project ...... 43 Annexure VI: Roll Diagram of Sambalpur‐Titlagarh project ...... 44 Annexure VII: R&R photographs of landowners registration of Hospet‐Tinaighat project ...... 46 Annexure VIII: R&R photographs of ST project showing dismantling of TH structures ...... 47

Table 1: Payment details of ST and HT projects ...... 7 TableTable 2: Mobilization of GC Social Expert ...... 7 Table 3: Requirement of land acquisition as estimated under ST project ...... 10 Table 4: Land Acquisition issues of ST project ...... 14 Table 5: Land Acquisition issues of ST project ...... 15 ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND ii Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Table 6: Details of payment towards LA for Sambalpur‐Titlagarh ...... 16 Table 7: List of Land Owners compensated for Direct Purchase ...... 18 Table 8: Status of land acquisition in HT ...... 20 Table 9: Financial status of compensation in HT ...... 22 Table 10: Summary of Land Acquisition in HT ...... 23 Table 11: Status of land compensation in HT ...... 24 Table 12: Status of land Acquisition and Resettlement ...... 29 Table 13: Details regarding Rehabilitation and Resettlement ...... 32

Figure 1: Map of India showing track doubling and electrification projects ...... 2 Figure

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND iii Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Abbreviation

ADB Asian Development Bank BPL BelowPovertyLine CPM Chief Project Manager DG Daund – Gulbarga DGPS Differential Global Position System DM District Magistrate DPs Displaced Persons EA Executing Agency FHH Female Headed Household GAD General Arrangement Drawing GC General Consultant GCC General Conditions of Contract GRC Grievance Redressal Cell HT Hospet – Tinaighat HHs House Holders IA Implementing Agency India Indian Government INR Indian Rupees IP Indigenous People IPP Indigenous Peoples Plan IPPF Indigenous Peoples Planning Framework IR Inception Report LAO Land Acquisition Officer MOR Ministry of Railways NEFT National Electronic Funds Transfer NGO Non‐Governmental Organisation NTH Non‐Title Holder OSRC Orissa Space Applications Centre PAP/APs Project Affected Persons PG Pune – Guntakal PMC Project Management Consultant PWD Public Works Department RAP Resettlement Action Plan RFCTLARR Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act R&R Resettlement and Rehabilitation RO Resettlement Officer RP Resettlement Plan RT Raipur – Titlagarh RTGS Real Time Gross Settlement RVNL Rail Vikas Nigam Limited SC Scheduled Caste ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND iv Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

SIA Social Impact Assessment SLAO Special Land Acquisition Officer ST Scheduled Tribe ST Sambalpur – Titlagarh TH Title Holder USD United States Dollars

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND v Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

1. Introduction and Project Background 1.1 Introduction

A Framework Financing Agreement (FFA) was signed on 8 July 2011 between the Indian Government (India) and the Asian Development Bank (ADB) for the implementation, through the Ministry of Railways (MOR), of the Railway Sector Investment Program (RSIP) which is an integral part of the investment program of MOR. A Multi Tranche Financing Facility (MFF) has been approved by ADB on 31 August 2011; MFF is intended to finance individual projects of RSIP.

Railway improvement component of RSIP consist of doubling of about 840 km rail routes and electrification of 640 km rail route along high density corridors. The scope of projects is to provide a second line along the existing single line by constructing the roadbed and either extending or constructing new bridges, provision of facilities for passenger and staff, providing and laying track, signalling and telecommunications and general electrical works. The scope of the electrification project is to provide overhead Railway electrification in the Pune‐Wadi‐Guntakal double line section.

The purpose of the RSIP is to improve connectivity to the areas covered by the track doubling and electrification project. These areas are located in underdeveloped regions of the country, though rich in minerals and related industries. The projects will add to the capacity on these constrained routes. The lines carry heavy traffic such as ore, coal, and cement, which are best carried by rail instead of road. The modal shift of bulk goods from road to rail would also reduce carbon emissions.

The current report is the semiannual Social Safeguard Monitoring Report prepared to comply with the loan covenants covering the period from October to March 2018. As usual, this report covers resettlement and social safeguard monitoring results to comply with the spirit of ADB policy. 1.2 Project background

The projects which are financed by the present ADB loan, are located in the states of Chhattisgarh, Odisha, Maharashtra, Karnataka and Andhra Pradesh. These projects are shown in red and blue in the map here under:

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 1 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Figure 1: Map of India showing track doubling and electrification projects The following railway projects with approximate route Kms are part of the Railway Improvement Component:

Length Project S. No Project Name Location (State) (in Km.) components 1 Daund‐Gulbarga 225 Maharashtra and Karnataka Doubling 2 Sambalpur‐Titlagarh 182 Odisha Doubling 3 Raipur‐Titlagarh 203 Chhattisgarh and Odisha Doubling 4 Hospet‐Tinaighat 229 Karnataka Doubling Maharashtra, Karnataka, and 5 Pune‐Guntakal 641 Electrification Andhra Pradesh

In general, the resettlement planning documents related to above projects were disclosed in September 2011. Out of five projects only two, namely Sambalpur‐Titlagarh and Hospet‐Tinaighat doubling projects require land acquisition. The other two doubling projects (Daund‐ GulbargaandRaipur‐Titlagarh)involve resettlement of non‐titleholders only. In Pune‐Guntakal electrification project, there is no land acquisition or resettlement of Title holders (TH) and non Title holders (NTH).

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 2 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

2. Legal and Policy Frame Work The new bill ‘’The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (Amendment) Bill 2015’’, also known as Land Bill 2015 introduced by the new government in March 2015 to remove the consent clause for acquiring land for industrial corridor public‐private projects, several infrastructure, affordable housing and defence did not get approval in Parliament and was referred to a Joint Committee in May 2015 comprising Member of Parliament from both houses to make out a bill acceptable to all parties. However, Joint Parliamentary Committee is yet to give its recommendation on land bill 2015 even after getting series of extension of tme since its formation. Since new Land Acquisition Amendment Bill 2015 has not come in force with the act of parliament, the RFCTLARR Act, 2013 is still having legal validity. Also, Ministry of Railways has streamlined rules through circular for the acquisition of land through any existing law of State/Central Government, direct negotiation with landholders and Railways (Amendment) Act 2008.

In Sambalpur‐Titlagarh project, Odisha Government is acquiring land underact 2013 (RECTLARR) which is effective from 01/01/2014. In this regard, a notification was issued by Odisha Revenue and Disaster Management on 07/02/2014 clarifying award in LA cases initiated prior to 31/12/2013. According to above notification, LA proceedings initiated under the LA act 1894 in which 4(1) notification and 6(1) declaration have been issued but where no award has been passed as on 31/12/2013, the provision of the new act in relation to determination of compensation and award shall apply. A notification issued by Odisha Revenue and Disaster Management Departmet on 7th February 2015 for the new Land Acquisition Amendment Bill also has been inforce for land acquisition for Sambalpur‐Titlagarh project by Revenue Authority. (See Annexure‐II)

In Hospet‐Tinaighat project, Karnataka Government has partly acquired land under Land Acquisition Act 1894 for declaration 6(1) issued before enforcement of act RECTLARR, 2013. To speed up the progress of land acquisition, State Government has notified new act to go for direct purchase from land owners under section 107/108 of RECTLARR, 2013 by providing higher compensation and rehabilitation than stipulated in act. The new LA act (Karnataka) has come into force from 17/10/2015. Government of Karnataka has issued a order under new LA Direct Purchase Act letter no. 54/2014 under which government has permitted to direct purchase of the land for the following works, i.e for the construction of houses , Grave ‐ yard, multiple – village water supply , electrical grid, under – drainage, road construction or widening of roads, construction of over bridge/under bridge, construction of Railway tracks, Airport. And for all their needful –public‐works, the required land is limited to 100 Acres and can be purchased directly from the land owners. (See Annexure‐I).

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 3 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

3. Insitutional arrangement and implementation mechanism 3.1 Rail Vikas Nigam

Rail Vikas Nigam Limited (RVNL) is acting as Implementing Agency (IA) for execution of various doubling and electrification project including the resettlement and land acquisition activities under RSIP. The RVNL organisation has been fully set up for taking up RSIP programme. Five project implementation units (PIUs) have been established for managing a doubling or electrification work.Each PIU is headed by a CPM.The headquarters of CPMs are based in Mumbai, Waltair, Raipur, Bangalore and Pune. Further under CPM there is a project director for each package. Project management consultants(PMCs) have been engaged to support IA for construction supervision as the Engineer. One of the Project Director from each PIU has been entrusted with additional charge RP implementation for all packages of a subproject and is responsible for overseeing the LAR activities on behalf of each PIU.

The RVNL is responsible for the overall implementation of the social safeguard measures recommended as per the policy and monitoring of the resettlement plan. In implementing the resettlement plan, the RVNL conducts the following activities:

(i) Ensure that the resettlement plan process, policies and principles are disclosed to the affected communities (i.e. during resettlement plan preparation and periodically during resettlementimplementation) in order to maintain participation and transparency; (ii) Ensure that (a) compensation unit rates have been established at the prevailing local market value for all categories of lost assets, and (b) the appropriate rates are developed in full consultation and agreed with affected persons as estimated by the Revenue Department as per the policy in Sambalpur‐Titlagarh; (ii) Periodically supervise resettlement plan progress and activities; (iv) Coordinate and work with the Revenue Department and concerned government authorities; (v) Conduct consultation with affected persons and local communities in case of any doubt; (vi) Establish database for affected persons for Land Acquastion by Revenue Department; (vii) Have responsibility for internal monitoring, reporting and action in response; (viii) Provide assistance to affected persons during compensation and land replacement activities; (ix) Prepare reports regularly on progress and outstanding issues.

3.2 Land Commisioner–Revenue Deparment

The district commissioner is appointed as a administrator by state government for compensation, rehabilation and resettlement of PAPs in respective districts.The district commissioner/collector (who is also head of revenue department) is responsible for administrating the cash compensation under the law for title‐holders.

3.3 General Consultant

A General Consultant (GC) firm has been mobilized for the overall supervision, monitoring and reporting of the investment program. The Resettlement Expert of the General Consultant has been mobilized since June 2013 and is responsible for: ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 4 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

 Monitoring the LAR activities  verify data through random checking at the field level  Identify the strengths and weaknesses and suggest corrective action plans.  prepare semi‐annual monitoring reports for RVNL and ADB.  assess the adequacy of compensation and resettlement benefits given to the affected persons and whether these follow the approved entitlement matrix  assess the affected persons’ conditions of living post‐resettlement

3.4 RP Implementing NGO

M/S Sugam International Sansthan (NGO) based in Lucknow was appointed in 2011 to assist RVNL in land acquisition,resettlement and rehabilation activities in doubling projects of Daund‐ Gulbarga, Hospet‐Tinaighat, Sambalpur‐Titlagarh and Raipur‐Titlagarh project. The services of above NGO awarded with work of implementation of Resettlement Plan (RP) have not been extended after August 2016 in any of the project. There is no work of land acquisition involved in Daund–Gulbarga and Raipur‐Titlagarh projects and NGO has completed all the required resettlement activities related to NTHs at above projects. Now, RVNL is directly monitoring balance land acquisition and resettlement activities by Revenue Department at Sambalpur‐Titlagarh and Hospet‐Tinaighat projects and has hired individual Consultants to support the PIU staff dealing with R&R.

3.5 The Asian Development Bank  The ADB is monitoring the social and environmental safeguards through its Head quarter mission. One mission including safeguards specialists is usually conducted every year.

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 5 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

4. Greivance Rederess Committee Greivance Redressal Committee (GRC)has been formed under chairmanship of District collector in each district of the sub projects where land acquisition and Resettlement activities are involved.The objective of formation of GRC is to achieve and facilitate the resolution of DP’s any concerns, complaints or grievances related to compensation and rehabilation or any issue related to social safeguard. The other functions of the GRC are to (i) record, categorize and prioritize the grievances; (ii) settle the grievances in consultation with complaints and other stakeholders; (iii) informed the aggrieved parties about the solutions; and (iv)forward the unresolved cases to higher authorities.

5. Progress on Subprojects

5.1 Global Progress

The calculated global progress of implementation of R&R activities across the various projects at the end of March 2018 is as under: S. No Name of Project Global progress 1. Doubling of Daund‐Gulbarga 100% 2. Doubling of Hospet‐Tinaighat 45%* 3. Doubling of Sambalpur‐Titlagarh 25% 4. Doubling of Raipur‐Titlagarh 100% 5. Electrification of Pune‐Guntakal N/A *The revise percentage is because of disputed land records and for dispute in the family related to ownership.

5.2 Important events related to LA and R&R from October to March 2018.

For Sambalpur‐Titlagarh project

‐ For Sambalpur‐Titlagarh project, 222 nos (17%) of affected households (titled and non‐ titled) out of an estimated 1327 have received compensation and resettlement assistance for a total of INR 181,532,284. ‐ Total compensation paid against land acquisition as per old act + R&R = Rs 33,564,752 ‐ Total compensation paid against land acquisition as per new act + R&R = =106,158,562 + 41,808,970 = 147,967,532. ‐ 11(1) notification has been issued by Collector/Bolangir on 24.03.18. However, in Kerlidhua village 19(1) notification to be chased on priority for construction of approaches ROB No‐ 423A in Deogaon and Saintala section. ‐ Collector/Sambalpur issued demand note of Rs.35,347,950 for 12.059 acres of government land on 27.03.2018. ‐ Formation of Joint Survey Committee consisting of RVNL & E.Co Railway to access the impact on doubling work due to non‐availability of sufficient right of way (ROW).

For Hospet‐Tinaighat project

Two affected persons from village Betgeri in Gadag district have been compensated 26,46,353 INR on 28/2/2018 for direct purchase of 0.0293 acres of their land.

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 6 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Three affected persons from village Hosalli & Kampasagar in Koppal district and of village Betgeri in Gadag district have been compensated 2,619,000 INR during this reporting period. The total compensation amount for all the five affected persons has reached to 5,265,353 INR for acquisition of 1.38 acres through direct purchase during this reporting period.

Subproject Name LA payments Resettlement assistance Total per payments (TH/NTH) subproject Sambalpur Titlagarh 323,493,477 3,340,643 (NTH) 326,834,120 Hospet‐Tinaighat 155,221,342 370,000 155,591,342 Total 478,714,819 2,623,766 481,338,585 Table 1: Payment details of ST and HT projects

5.3 NGO – Assistance to RVNL

5.3.1 NGO contract for Sambalpur‐Titlagarh project As stated in our previous report that Resettlement work for TH is being done directly by state Revenue department. As the contract services of NGO has expired in August 2016. NGO has completed all tasks related to compensation and training for all NTH identified in Sambalpur‐ Titlagarh during his contract period. Two retired persons from state Revenue Department appointed by PIU Sampalpur assisting the Revenue Department for land acquisition as required for laying of new tracks and construction of other facilities in station yards.

5.3.2 NGO contract for Raipur‐Titlagarh project As stated in our previous Reports that NGO has completed the entire pending task in August in 2016. No task is pending as per the safeguards policy of ADB.

5.3.3 Assistance for Hospet‐Tinaighat project Extension of two persons has been approved by CPM upto March 2018 (see Annexure‐III). The PIU may further extend the services of two land acquisition persons to assist the Revenue Department for acquiring balance land needed for laying new tracks and facilities in station yards.

5.4 General Consultant

A General Consultant (GC) firm has been mobilized for the overall supervision, monitoring and reporting of the investment program. The GC social expert has provided the following input man month for monitoring R&R issues on various subprojects.

Year Month Input (days) Input (man‐month) October ‐ ‐ November 12 .4 December ‐‐ 2017‐2018 January ‐ ‐ February 16 .53 March 13 .43 Total 41 1.37 Table 2: Mobilization of GC Social Expert

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 7 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

5.5 Daund‐Gulbarga (Maharashtra Section and Karnataka Sections)

No land acquisition in this section and all NTH have been compensated.

The NGO had completed the R&R activities as per the approved Micro plan for NTH. As suggested in our previous quarterly progress reports, the GC social expert recommends closing of this project with respect to R&R.

5.6 Sambalpur–Titlagarh project

Social impact assessment (SIA)

A State unit Nabakrushna Choudhury Centre for Development Studies (NCDS),Bhubaneswar has undertaken the Social Impact Assessment(SIA) in the state of Odisha for the project.

As social impact assessment (SIA) has been made mandatory in policy provisions of LA Act 2013. Social impact assessment (SIA) required in only two districts namely Bargarh and Bolangir.

The report has been submitted in 2017 to the Government for further processing as per the Act. The Revenue department is updating the land records as per section 11(5). The revenue department has to update and complete before declaration U/S 19. The GC is closely monitoring as no involuntary displacement will take place without completion of R&R.

Mitigation Measures: Since the project is a linear project and a very less quantity of land is going to be acquired, the risks and impacts may be less than the average.

Vulnerability Status of the household

Among the 539 affected households of Bolangir district 80 (14.84%) are headed by women, 9 (1.67%) are headed by physically handicapped persons and the balance 450 (83.49%) households are headed by men. 50 (9.28%) households among them are having BPL cards belonging to 32 villages.

Regarding vulnerability status of the affected household of Bargarh district are 1283 widows, 97 women headed households, 323 physically handicapped persons, 94 destitute, 103 divorcees and 23 orphans belonging to 26 villages.

All NTHs identified at Khetajpur, Guhratikra and Balangir in Sambalpur–Titlagarh project have been paid full compensation including training programme on income restoration and skill upgradation for affected PAPs during last year. The land is totally free from squatters for laying of new Railway track.

Joint Survey Committee General Manager, East Coast Railway had reviewe the progress of ongoing Sambalpur‐Titlagarh doubling project with Rail Vikas Nigam Limited (RVNL). RVNL informed that the progress has been hampered due to non‐availability of sufficient width of land for proposed doubling line, whereas Railways appraised that the sufficient railway land is available. Hence, a joint survey committee had been formed jointly by E.Co. Railway and RVNL to access the impact on doubling work due to non‐ availability of sufficient land width from Deogaon to Barapali station of ST‐02 package during

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 8 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

March 2018. The committee had visited the site and submitted the report and the same has been enclosed as Annexure VI. Sambalpur (SBP) District The private land of Title holders in Sambalpur district required 4.62 acres (1.869 Ha) in 5 villages. Full possession taken for 4.620 acres in 5 villages. The government land required at Sambalpur district is 21.517 acres in 5 villages, only 3.499 have been alienated or Record of Right (ROR) issued. For 5.885 acres payment of 21,627,375 INR has been deposited with FA&CAO (Construction)/E.Co.Railway, deposited on 23/03/2018. For 0.074 acres, payment of Rs. 955,375/‐ has been deposited with Tahasildar/Sadar/Sambalpur vide money receipt no. 0548539 dated 23/03/2018. Collector/SBP Vide letter no.1267/Rev dated 27/03/2018 clarified for payment of Rs. 3, 53, 47,950.00 towards capitalized value of land sanction vide their order no. 3276 dated 25/09/2017. Payment is under Process. The reserve forest land required at Sambalpur district is 25.317 acres (15.340+9.977) out of total land no possession taken till date. The observation of Additional PCCF, Odisha of Subarnapur division compiled and submitted to DFO on 19/03/2018. ORSAC officials observed that there is mismatch of area on 3 nos of plots which require carrying out of DGPS survey again on 17/04/2018. SM consultant has assured to start the DGPS survey WEF 18/04/2018. Bargarh (BRGA) District

Total 22.850 acres (9.247 Ha) of the private land in Bargarh district consisting of 26 villages is proposed to be acquired. Revenue Department has issued declaration u/s 8(2) under Vide letter no. 19343/R&DM Dtd. 16/06/2017. After recommendations and suggestion report of expert group/SIA received from Collector/BRGA in June 2017, SLAO/SBP has sent 11(1) proposal to State Government HQ in Bhuvneshwar on 16/09/2017 so that notification can be published as specified in LA act. Notification 11(1) issued by government of Odisha for 21.270 acres (24 villages) out of 22.850 acres (26 villages) on 31/10/17, 01/11/17, 02/11/17 and 09/11/17.

There is total requirement of 3.985 acres of Government land to be acquired at 26 villages in Bargarh district, only 1.921 acres of alienation/transfer of government land has been made up to this quarter. Balance transfer of 2.064 acres of land is pending with Tehsildars (local revenue officers at district level).

Bolangir District

Total 42.848 (17.340 Ha) acres of private land at 32 villages is required in Bolangir district. Public Hearing on SIA in all 32 villages of Bolangir district has been completed on 03/04/2017. Public hearing report has been prepared and submitted to Collector/BLGR.

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 9 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

11(1) notification issued by Collector/BLGR.on:24.03.18. However in Kerlidhua village 19(1) notification to be chased on priority for construction of ROB No‐423A.

Out of total requirement of 11.022 acres of government land in 31 villages, only 4.380 acres have been sanctioned/alienated up to this quarter. Balance acquisition of 6.642 acres is pending with Tehasildars.

Sonepur District

As per the survey details of the Title Holders of Sonepur district, 9.185 acres (3.717 Ha) of Private Land acquisition required is required in 8 villages. Total 5.183 acres of private land possession taken on 01/06/2017 and 06/06/2017. Handing over of balance land of 4.002 acres is pending with Tehasildar.

Out of 8 villages, the land owners of Sananuapali and Cherupali did not receive payment (seeking higher compensation) and since pending with Revenue department. Proposed enhanced rate is under process for village Cherupali and Sannupali.

There is total requirement of 1.781 acres of Government land to be acquired in 8 villages of Sonepur district, only 1.0571 acres of sanctioned/alienated of government land has been made up to this quarter. Balance transfer of 0.724 acres of land is pending with Tehsildars (local revenue officers at district level).

Total requirement of Land to be acquired is currently estimated is as tabulated herewith.

Possession taken / SL.No. Type of land Required Area (Ac.) Permissive Possession Balance (Ac.) (Ac.) 1 Private LA 79.503 9.803 69.700 2 Govt. LA 38.301 28.714 9.587 3 Forest LA 15.340 Nil 15.340 4 Revenue Forest LA 09.977 Nil 9.977 TOTAL 143.121 38.517 104.604 Table 3: Requirement of land acquisition as estimated under ST project

The status of acquisition of private land, Government land and forest land as received from Project Implementation Unit (PIU) is reproduced as under:

Name of the Private Land District (a) 4.62 acres (1.869 Ha) Private Land acquisition required in 5 villages. Sambalpur (b) Full possession taken for 4.620 acres in 5 villages. (4.45 acres on: 28/02/2014 and 0.170 acres on: 08/11/2017 and 28/12/2017) (a) 22.850 acres (9.247 Ha) Private Land acquisition required in 26 villages. (b) Vide letter no.19343 /R&DM Dtd.16/06/2017 Government has issued Baragarh declaration u/s 8(2). (c) SLAO/SBP sent 11(1) proposal to Government on 16/09/2017 and pending in BBSR

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 10 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

(a) 42.848 acres (17.340 Ha) Private Land acquisition required in 32 villages. (b) Collector/BLGR send to Government for declaration U/s 8(2) and process Bolangir for notification U/s 11(1) vide memo no.737 Dtd. 01/08/2017 and pending in BBSR. (a) 9.185 acres (3.717 Ha) Private Land acquisition required in 8 villages. (b) U/s 19(1) declaration issued for 9.185 acres in 8 villages on 03/10/2016 by R & D.M. Department, Government of Odisha. (c) Out of 8 villages, the land owners of Sananuapali and Cherupali did not Sonepur receive payment seeking higher compensation and since pending with Revenue department. (d) Total 5.183 acres of private land possession taken on 01/06/2017 and 06/06/2017. Handover of balance land of 4.002 acres may please be expedited.

Government Land

Total Govt. Land required: 38.301 Acres (‘64’ villages) in 4 districts. Sambalpur District (05 Villages) (a) Total requirement‐21.517Acs (b) Possession taken ‐3.499Acs. (c) ROR issued /Possession taken=3.412(02 village i.e. Kalamati & Burla Town).On this possession taken land of 2.310 Ac, there are 03 encroachments. Letter given to Collector & Tahasildar/SBP on: 14.07.17 along with joint inspection report. Eviction of encroachments may be expedited. (d) Physical possession taken for 0.087 acres near JT‐25 in Bareipali on: 28.12.17 with eviction of encroachment. ROR to be corrected. (e) Permissive possession‐17.944Acs (04.10.17).However for payment as per latest policy guide lines of Govt. of Odisha, 12.059Ac has been reduced to 1.93Ac letter given to Tahasildar/SBP on: 16.10.17 & In response Tahasildar/SBP has given letter to Collector/SBP on: 27.10.17 for decision. (f) Collector/SBP Vide letter no.1267/Rev Dtd.27.03.18 clarified for payment of Rs.3, 53, 47,950.00 towards capitalized value of land sanction vide their order no.3276 Dtd.25.09.17. Payment is under Process.

Bargarh District (20 villages) Total requirement‐ 3.985 Ares Sanctioned/Alienated ‐1.921 Acres Balance‐2.064 Acres pending with Tahasildars.

Balangir District (31 villages) Total requirement‐ 11.022 acres Sanctioned/Alienated 4.380 acres Balance‐6.642Acs pending with Tahasildars

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 11 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Sonepur District (08 villages) Total requirement‐ 1.781Acs Sanctioned/Alienated ‐1.057Acs Balance‐0.724Acs pending with Tahasildar/Rampur

Forest Land (A) 15.340 Acres (6.208 Ha) of Forest Land diversion is required in ‘5’ villages for the entire Sambalpur – Titlagarh Doubling Railway Project.

(B) In compliance to observations made by Nodal/Officer of PCCF office, hard copies are submitted with concerned DFOs & District Collectors on 04.05.2016.

(C) RCCF/BWPN (DFO/BLGR) & (DFO/Sonepur)

(1) All the observations of DFO/BLGR & RCCF/BWPM are compiled since 11.1.2017.

2) As required DFO/Sonepur uploaded part‐II (nil statement) on 2.08.2017.

3) Part‐III uploaded by RCCF/BWPM on: 24.10.17 & hard copy submitted to PCCF on: 27.10.17 & Pending with PCCF/BBSR.

4) Additional PCCF raised some observations for compliance on 24/11/2017 and returned file.

5) FRA certificate issued by collector/BLGR on 08/12/2017 for 5.768 Hectres of forest land.

6) Letters has been issued to DFO’s & Tahasildar’s for joint TE on plots of Non forest land.

7) Tree enumeration completed in Bolangir & Sonepur District & obtained signature of all concerned authority.

08) Land schedule of Non forest Govt. land of Bolangir & Soenpur district (9 Tahasils) authenticated by Tahasildars.

9) The observation of Additional PCCF,Odisha of Subarnapur Division complied & submitted to DFO/ Subarnapur on:19.03.18.

10) The observation of Additional PCCF,Odisha of Balangir Division complied & submitted to DY CE/SBP on 19/03/2018 for signature.

11) Submitted to DFO/BLGR on: 31.03.2018.

(D) RCCF/SBP (DFO/BRGA) & (DFO/SBP)

(1) All the observations of DFO/BRGA & DFO/SBP have been complied on: 16.8.17& 14.09.2017.

(2) DFO/BRGA & DFO/SBP submitted the proposal to RCCF/SBP on: 28.08.17 & 9.10.17

(3) Part‐III uploaded by RCCF/SBP & hard copy submitted to PCCF on: 17.10.17

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 12 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

4) Additional PCCF raised some observations for compliance on 22/11/17 and returned file.

5) Gramsabha conducted on23/10/17.Collecter BRGA yet to issue FRA certificate in spite of regular follow up.

6) Tree enumeration completed in Sambalpur & Bargarh District. Signature of all concerned authority completed.

7) The observation of Additional PCCF,Odisha of Sambalpur Division complied & submitted to DY CE/SBP on:11.03.18 for signature. ) Submitted to DFO/SBP on: 30.03.2018.

(E) Revenue forest land

(1) 9.977 Acres of Revenue Forest Land diversion is required in ‘8’ villages of Balangir District for the entire Sambalpur – Titlagarh Doubling Railway Project.

(2) DGPS Survey completed. DFO/BLGR forwarded the same to ORSAC/BBS for authentication, on: 2.11.17.

(3) SM Consultant reported that ORSAC has issued new format for submission of Survey report. The same has been complied & submitted to ORSAC. Performance of Agency Sims to be very poor hence a letter has been issued on 05.02.2018 to expedite the work progress.

Section wise LA Issue (As on: 31.03.2018) RESERVE REVENUE SECTION PVT LAND ISSUE FOREST FOREST DISTRICT REMARKS LAND LAND

(1) 11(1) notification issued by 3103 m (Between Govt.of Odisha for 21.270 acres (24 Br. No. 152 to Br. 288 m (0.635 Villages) out of 22.850 acres (26 No. 153, Br. No. acres) Villages) on: 31.10.17, 1.11.17, 156 to Br. No. SUKTAPALI ‐ (Between Br. 2.11.17 & 09.11.17. (2) 11(1) 157, Br. No. 160 Nil BARGARH BARGARH No. 160 and notification for balance 02 villages to level crossing level crossing (Dhanger & Babupali =Ac 1.580 to no. JT ‐43 and Br. no. JT ‐43) be issued by Govt of Odisha. (3) No 171 to Br. No. 19(1) notification may be issued by 175) Collector/BRGA.

4496 m (Between (1) 11(1) notification issued by Br. No. 180 and Govt.of Odisha for Ac.21.270(24 Br. No. 186) , Villages) out of 22.850Ac Near Br. No. 192, (26Villages) on:31.10.17, 1.11.17, BARGARH ‐ (Between Br. No. 2.11.17 &09.11.17. (2) 11(1) Nil Nil BARGARH BARPALI 206 to Br. No. notification for balance 02 villages 208) and between (Dhanger & Babupali =Ac 1.580 to Br. No. 219 and be issued by Govt of Odisha. (3) level crossing no. 19(1) notification may be issued by JT‐60) Collector/BRGA.

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 13 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

(1) 11(1) notification issued by Govt. of Odisha for Ac.21.270(24 Villages) out of 22.850Ac (26Villages) on:31.10.17, 1.11.17, 2.11.17 &09.11.17. (2) 11(1) Barpali to Km 635 BARGARH notification for balance 02 villages =2190 m BARPALI ‐ (Dhanger & Babupali =Ac 1.580 to Nil Nil DUNGIRIPALI be issued by Govt of Odisha. (3) 19(1) notification may be issued by Collector/BRGA.

19(1) notification issued on: 3.10.16. km : 635 To SONEPUR Partly possession given. Balance Dungripali =1705 m possession is Urgently required 19(1) notification issued on: 3.10.16. Dungripali‐KM : SONEPUR Partly possession given. Balance DUNGRIPALI‐ 647/5 =3150 m possession is Urgently required Nil Nil KHALIAPLI 647/5 to Khaliapli BALNGIR 1) 11(1) notification issued by = 715 m Collector/BLGR.on:24.03.18. 1) 11(1) notification issued by KHALIAPLI ‐ 0.244 acres Collector/BLGR.on:24.03.18.2)DGPS 2480 M Nil BALNGIR LOISINGA (Bendra) Survey in progress for revenue forest. 1) 11(1) notification issued by LOISINGA ‐ 0.107 acres Collector/BLGR.on:24.03.18.2)DGPS 4805 m Nil BALNGIR BALANGIR (Hirapur) Survey in progress for revenue forest. 210 mtr (0.534 Ac) (5.291 BALANGIR ‐ Mathakahi 1) 11(1) notification issued by 2160 m acres) 1240 BALNGIR DEOGAON Reserve Collector/BLGR.on:24.03.18.2)DGPS m, Raeipali Forest, Survey in progress for revenue Narayanpur forest. 125 m 1) 11(1) notification issued by DEOGAON ‐ (1.480 Collector/BLGR.on:24.03.18.2)DGPS 1700 m Nil BALNGIR SAINTALA acres)/ Survey in progress for revenue Ghuchepali forest. 30 m (1.625 1) 11(1) notification issued by SAINTALA‐ acres)/Karli Collector/BLGR.on:24.03.18.2)DGPS 70 m Nil BALNGIR BADMAL dhua & Survey in progress for revenue Saintala forest . 3350 m 1) 11(1) notification issued by (13.577 Collector/BLGR.on:24.03.18. BADMAL‐ 45 m acres)(Barnei Nil BALNGIR SIKIR RF in Badmal Village 85 1) 11(1) notification issued by 35 m (0.142 m/(1.414 Collector/BLGR.on:24.03.18.2)DGPS acres)/(Barne SIKIR‐ acres)/sikap Survey in progress for revenue 2155 m i RF in BALNGIR TITLAGARH atrapali,Ma forest. Badmal nigaon & Village) Sagadaghat Table 4: Land Acquisition issues of ST project

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 14 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Section wise LA Criticality (As on: 31.03.2018) Private Govt. Reserve Revenue Section District Remarks Land Land Forest Land Forest Land Sambalpur ‐ Hirakud Sambalpur Hirakud – Godbhaga Sambalpur Godbhaga – Attabira Bargarh Attabira – Deobahal Bargarh Deobahal – Bargarh Bargarh 3103m 288m Bargarh – Barpalli Bargarh 4496m Bargarh 2190m Barpalli ‐ Dungripalli Sonepur 1705m Dungripalli – Sonepur 3150m Khaliapali Balangir 715m Khaliapali – Loisinga Balangir 2480m Loisinga – Balangir Balangir 4805m 130m Balangir – Deogaon Balangir 2160m 210m 1240m Deogaon – Saintala Balangir 1700m 125m Saintala – Budmal Balangir 70m 30m Budmal – Sikir Balangir 45m 3350m Sikir ‐ Titlagarh Balangir 2155m 35m 85m

Not Required Possession Taken LA is in pipeline and progress of work will not hampered LA is in pipeline and progress of work will be hampered Table 5: Land Acquisition issues of ST project

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 15 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Table 6: Details of payment towards LA for Sambalpur‐Titlagarh

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 16 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

5.7 Raipur‐Titlagarh project

As stated in our previous Reports that NGO has completed the entire pending task in August in 2016. No task is pending as per the safeguards policy of ADB.

5.8 Hospet‐Tinaighat project

The total scope of land acquisition has been revised to 31.45 acres, out of which 18.95 acres was notified under clause 6(1) of old Land Acquisition Act and 12.50 acres proposed to be acquired through direct purchase. Again, out of 18.95 acres notified under 6(1) it was found after Joint Measures Survey (JMS) that 1.025 acres belongs to government land in Annigiri village. Now, 17.925 acres of private land to be acquired under 6(1) notification. Out of 17.925 acres, 13.330 acres belonging to 20 HHs has been compensated against land acquisition under 6(1) notification. For the remaining 4.625 acres, because of the dispute in ownership and family dispute of 6 HHs, no compensation could be settled during this reporting period. However, the Revenue Department with the help of revenue consultant of PIU Hospet is trying hard to settle their ownership and family dispute.

Out of 12.50 acres (56 HHs) required for land acquisition under direct purchase at Koppal, Gadag, Belgam and Dharwad district, 6.51 acres (19 HHs) has been finalized (in Koppal and Gadag) by Revenue Department. However, out of 6.50 acres, only 1.38 acres have been compensated during this reporting period for 5 HH and the remaining 14 HHs are under process by the Revenue Department. The delay for compensation to the remaining 14 HHs was because of the proposed assembly election in Karnataka during May 2018.

No NTH were found in this project. The Micro plan for resettlement allowance has been approved for 25 out of total 43 PAPs under clause 6(1) of Land Acquisition Act. An amount of 3,70,000 INR of entitlements has been disbursed in three stages to 25 PAPs/House Holders (HHs). For direct purchase 56 THs have been identified for compensation. So the revised total affected THs will be 82 PAPs (26 HHS 6(1) notification + 56 HHs for direct purchase). Further, 25 THs have been paid 12,945,065 INR against acquisition of 14.68 acres of land.

Two affected persons of village Betgeri in Gadag district have been compensated 26,46,353 INR on 28/2/2018 against direct purchase of 0.0293 acres of land during this quarter. Three affected persons from villages Hosalli and Kampasagar in Koppal district and village Betgeri in Gadag district have been compensated 2,619,000 INR during the December end quarter. Now, the total compensation amount for all the five affected persons has reached to 5,265,353 INR for acquisition of 1.38 acres through direct purchase during this quarter.

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 17 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

HT‐1 List of Land Owners for Direct Purchase as upto March‐2018 Registration S.No District Village Owner Name (TH) Sy .No Acre Gunta Anna Acres Amount in Rs Payment Remarks Date 1 Koppal HOSALLI Eshappa S/O Bharamappa horatnal 59/1 0 6 0 0.1500 10/31/2017 ₹ 285,000 Paid Total 2 TH in 2 Koppal HOSALLI Paravva W/O Ningappa Horatnal 59/2 0 10 0 0.2500 10/31/2017 ₹ 475,000 Paid HOSALLI Total 1 TH in 3 Koppal KAMPASAGAR T Kishor Kumar S/O JANARDHAN 190 0 38 0 0.9500 10/31/2017 ₹ 1,859,000 Paid KAMPASAGAR

Yellangouda S/0 Ramangouda 3999/B1‐ Total 1 TH in 4 Gadag Betgeri 0 0.743802 0 0.0186 2/28/2018 ₹ 1,547,137 Paid Hanumantagouda 2A Betgeri Dyamangouda S/0 Ramangouda 3999/B1‐ Total 1 TH in 5 Gadag Betgeri 0 0.429752 0 0.0107 2/28/2018 ₹ 1,099,216 Paid Hanumantagouda 2B Betgeri Total Amount paid five TH ₹ 5,265,353

Table 7: List of Land Owners compensated for Direct Purchase

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 18 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Land acquisition ‐ progress The present status of land acquisition in Hospet‐Tinaighat project after Joint Measurement Survey (JMS) is as follows:

LA progress upto March 2018 Direct purchase Amount Notification After Revised Direct purchase Notification Total Direct Finalised as Total land issued for (Till Direct Purchase Grand Total Amount Package 6(1) issued for Purchase as on Remarks as on on March NAME OF THE VILLAGE acquisition date Finalised as on (LA+ Direct Finalised and no Land March 2018 March‐ 2018 2018 by DC. scope notification March 2018 Purchase) as on given to TH's as acquisition Scope Railways 6(1) ) March 2018 on March‐2018 /RVNL Cheque given to DC. 1 2 3 4 5 6 7 8=5 + 6 9 10 11 Details HT A G a A G a A G a A G a A G a A G a Remarks Table 1 ANNIGERI (Darwad) HT‐2 1 22 0 1 22 0 1 22 0 0 0 0 0 0 0 1 22 0 ANNIGERI (Darwad Govt. HT‐2 1 1 0 1 1 0 0 0 0 Agriculture University) 1 1 0 0 0 0 1 1 0 Under DC 0 0 0 (Koppal) HT‐1 8 6 0 4 16 0 4 16 0 0 29 0 5 5 0 Negotiations Under DC 0 0 0 BHANAPUR (Koppal) HT‐1 3 32 0 1 31 0 1 31 0 0 34 0 2 25 0 Negotiations Land Owners HOSSALLI (Munirabad) given consent to Paid (Koppal) HT‐1 2 26 0 1 25 0 1 25 0 0 16 0 0 16 0 2 1 0 DC. ₹ 760,000 Land Owners given consent to KOPPAL (Koppal) HT‐1 13 3 0 6 14 0 6 14 0 4 18 0 4 18 0 10 32 0 DC. ₹ 83,684,830 TALABALA (Bhanapur) (Koppal) HT‐1 2 11 0 2 9 0 2 9 0 0 0 0 0 0 0 2 9 0 Land Owners KAMPASAGAR (Munirabad) 0 0 0 0 0 0 given consent to Paid (Koppal) HT‐1 2 19 0 0 38 0 0 38 0 0 38 0 DC. ₹ 1,859,000 Munirabad Additional Under DC (Koppal) HT‐1 0 22 0 0 0 0 0 0 0 0 20.95 0 0 0 0 0 20.950 0 negotiations Total as per March 2018 35 22 0 18 38 0 18 38 0 7 35.95 0 5 32 0 26 33.95 0

Total area in acres 35.5500 18.9500 18.9500 7.8988 5.8000 26.8488

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 19 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

New proposals

Table 2 ( New Proposals) HT A G a A G a A G a A G a A G a A G a Remarks

Finalised. Amount (Rs HT‐2 0 0 0 0 0 0 0 0 0 0 27 0 0 27 0 0 27 0 Land Owners 5,77,65,212/‐ given consent to ).Paid Two TH Betigri, Gadag (Gadag) DC. ₹ 57,765,212 (Rs 26,46,353/‐) Alnawar new proposal Under DC HT‐3 0 0 0 0 0 0 0 0 0 1 1 0 0 0 0 1 1 0 (Darwad DT ) Negotiations new proposal Under DC HT‐3 0 0 0 0 0 0 0 0 0 0 28 0 0 0 0 0 28 0 ( DT) Negotiations Khurdagosh Village Under DC HT‐3 0 0 0 0 0 0 0 0 0 0 12 0 0 0 0 0 12 0 new proposal(Belgaum DT) Negotiations Londa Village new proposal Under DC HT‐3 0 0 0 0 0 0 0 0 0 0 12 0 0 0 0 0 12 0 (Belgaum DT) Negotiations Akrali Village new proposal Under DC HT‐3 0 0 0 0 0 0 0 0 0 0 24 0 0 0 0 0 24 0 (Belgaum DT ) Negotiations Direct purchase negotiations HT‐1 0 0 0 0 0 0 0 0 0 1 0.140 0 0 0 0 1 0.140 0 failed, Due to the Ginigera new proposal huge gap in rates (Koppal D.T ) . Total as per new proposals as on March 0 0 0 0 0 0 0 0 0 4 24.14 0 0 27 0 4 24.14 0 2018 Total area in acres 0 0 0 4.6035 0.6750 4.6035

Table 8: Status of land acquisition in HT

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 20 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Financial status of compensation against land acquisition and resettlement/Direct Purchase upto March ‐2018 Total Resettlement Total Total compensation paid against land purchase to THs upto Allowance paid resettlement March‐ 2018 Total upto March‐ pending Total Total Land as 2018 Total Name of nos Nos on S No Name of village/station nos Total Remarks district of of March Paid of TH No. of Land PAPS NTH 2018 in Amount against Total No TH 6(1) Finalized No of acres Paid as per 6(1) and 6(1) in Amount of Amount Amount 6(1) and PAPs 6(1) and DP DP in Acres PAP paid DP in Acres acres.

Under 6(1) LA

1 Koppal Koppal/Koppal 6 0 3 6.350 1 ₹ 2,732,814 2.300 6.350 6.350 1 ₹ 8,000 5 ₹ 60,000 Finalised

2 Koppal HOSSALLI/Munirabad 4 0 7 1.625 7 ₹ 2,008,126 1.625 1.625 1.625 4 ₹ 62,000 0 ₹ 0 Finalised 3 Koppal SOMPUR/Sompur 7 0 4 4.400 4 ₹ 1,019,510 4.400 4.400 4.400 4 ₹ 62,000 3 ₹ 24,000 Finalised ₹ 4 Darwad ANNIGERI/Annigeri 11 0 4 1.550 3 ₹ 368,750 1.400 1.550 1.550 11 178,000 0 ₹ 0 Finalised ANNIGERI/Annigeri 4.a Darwad (Govt) 0 0 0 1.025 0 ₹ 0 0.000 1.025 1.025 0 ₹ 0 0 ₹ 0

5 Koppal TALABALA/Bhanapur 3 0 3 2.225 3 ₹ 1,182,099 2.225 2.225 2.225 2 ₹ 26,000 1 ₹ 8,000 Finalised ₹ 6 Koppal BHANAPUR/Bhanapur 12 0 5 1.775 2 ₹ 368,413 1.350 1.775 1.775 3 ₹ 34,000 9 102,000 Finalised Direct Purchase

Under DC 7 Koppal SOMPUR/Sompur 3 0.725 Negotiations Under DC 8 Koppal BHANAPUR/Bhanapur 4 0.850 Negotiations Finalised. Amount (Rs 9 Koppal HOSSALLI/Munirabad 2 0.400 ₹ 760,000 0.400 0.400 7,60,000/‐) . Finalised. Amount(Rs 10 Koppal Koppal 8 4.450 4.450 8,36,84,830/‐).

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 21 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Under DC 11 Koppal Munirabad Additional 3 0.52375 Negotiations Finalised. Kampasagar Amount (Rs 12 Koppal /Munirabad 1 0.950 ₹ 1,859,000 0.950 0.950 18,59,000/‐). Finalised. Amount (Rs 5,77,65,212/‐ ).Paid Two TH (Rs 13 Gadag Bettageri/Gadag 8 0.675 ₹ 2,646,353 0.029339 0.675 26,46,353/‐) Under DC 14 Darwad Alnawar new proposal 2 1.025 Negotiations Under DC 15 Belgaum Devarai new proposal 15 0.700 Negotiations Khurdagosh new Under DC 16 Belgaum proposal 1 0.300 Negotiations Under DC 17 Belgaum Londa new proposal 1 0.300 Negotiations Under DC 18 Belgaum Akrali new proposal 2 0.600 Negotiations DC Negotiations 19 Koppal Ginigera new proposal 6 1.00350 Failed. ₹ ₹ ₹ Total (in Acres ) 43 0 82 31.4523 20 14.68 18.950 25.4250 25 18 12,945,065 370,000 194,000

31‐ ₹ 17‐37.16‐ 18‐38‐ ₹ ₹ Total ( in A‐G‐a) 43 0 82 20 25‐17‐0 25 18 18.090‐0 12,945,065 0 0 370,000 194,000

Ginigera new proposal Direct purchase negotiations failed, Due to the huge gap between the rates offered. Therefore DC, Koppal suggested to revert back to New Land Note :‐ Acquisition Act‐2013.

Table 9: Financial status of compensation in HT

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 22 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Table 10: Summary of Land Acquisition in HT

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 23 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Table 11: Status of land compensation in HT

5.9 Electrification of Pune‐Guntakal project

No land acquisition and no TH and NTH in this project.

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 24 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

6. Summary table Status of Land Acquisition with resettlement plan implementation of different projects is as follows:

Sections Item Indicators Raipur‐Titlagarh Sambalpur– Hospet–Tinaighat Daund–Gulbarga Daund–Gulbarga Raipur‐Titlagarh No project Titlagarh project* project * project project (Maharashtra project (Odisha (Chhattisgarh (Karnataka Section) Section) Section) Section) Appointment of the Contract of Manjula RP implementation Enterprises for End of contract on End of contract on End of contract on NGO supply of R&R expert End of contract on 1 31/08/2016. 31/08/2016. 31/08/2016 End of contract on extended for further 4/1/2016. 4/1/2016. six months upto 31/03/18 No. of displaced 2 23 238 1313 (14 NTH) 82 NIL 5 households 1313 (14 NTH) No. of displaced (number of TH 3 23 238 82 (under process) NIL 20 persons Displaced Persons under verification) No. of physically 4 displaced 23 151 14 NTH Under process NIL NIL households No. of physically 5 23 238 14 NTH Under process NIL NIL displaced persons

No. of economically 6 displaced 23 136 1327 TH & NTH 82 (Under process) NIL NIL households

7 No. of economically 23 238 Under process Under process NIL NIL

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 25 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Sections Item Indicators Raipur‐Titlagarh Sambalpur– Hospet–Tinaighat Daund–Gulbarga Daund–Gulbarga Raipur‐Titlagarh No project Titlagarh project* project * project project (Maharashtra project (Odisha (Chhattisgarh (Karnataka Section) Section) Section) Section) displaced persons Total number of 8 titleholders being NIL NIL Under process 82 (Under process) NIL NIL displaced

Total number of 9 non titleholders 23 238 14 NIL NIL 5 being displaced

Entitlement matrix 10 Yes Yes Yes Yes Yes Yes disclosed

Identity cards Number of identity Identity cards Identity cards Identity cards distributed to PAPs 11 cards issued to the released to 23 PAPs distributed to all distributed to all NA 5 of 5 villages (25 displaced persons in Kantabanji area PAPs 238 NTH PAPs PAPs)

After award by Revised corrected Micro plans Deputy Land micro plan has been 12 prepared for Not required Not required Not required Not required Acquisition Officer approved in May titleholders (DLAO). Not yet 2015.

Micro plans Completed and Completed and Completed and 13 prepared for non‐ submitted (238 submitted (14 NA NA Yes submitted (23 NTH) titleholders NTH) NTH)

Micro plans 14 NA NA NA NA NA NA prepared for CPRs

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 26 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Sections Item Indicators Raipur‐Titlagarh Sambalpur– Hospet–Tinaighat Daund–Gulbarga Daund–Gulbarga Raipur‐Titlagarh No project Titlagarh project* project * project project (Maharashtra project (Odisha (Chhattisgarh (Karnataka Section) Section) Section) Section) Micro plans 15 NA NA Not yet Approved NA NA approved for TH Micro plans 16 Approved Approved Approved NA Approved Approved approved for NTH

Micro plans 17 NA NA NA NA NA NA approved for CPRs

Quantum of private Now revised from 18 NIL NIL 79.503 acres NIL NIL land to be acquired 31.15 to 31.45 acres

Total scope of land= to 31.45 acres, Total 18.95 acres notified Requisition for LA under clause 6(1) of submitted and old LA act and 12.50 completed for acres proposed to be Government, forest acquired through 19 Progress on LA NA NA and private land for NIL NIL direct purchase. Out Sambalpur, of 12.50 acres, 6.48 Sonepur, Baragarh acres has been and Balangir finalized (in Koppal districts. and Gadag) for direct purchase)

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 27 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Sections Item Indicators Raipur‐Titlagarh Sambalpur– Hospet–Tinaighat Daund–Gulbarga Daund–Gulbarga Raipur‐Titlagarh No project Titlagarh project* project * project project (Maharashtra project (Odisha (Chhattisgarh (Karnataka Section) Section) Section) Section) Full and final Distributed to 12 1st installment of installment has PAPs under Phase‐I assistance has been been distributed to in December 2013. distributed on Full and final all 238 DPs of 24/12/12. Full and final installment of Mahasumund, Distributed to 8 PAPs 2nd/final installment Whether instalment of compensation has Parvati Nagar, under Phase II in has been distributed 20 compensation compensation paid NA been distributed to Chandi Nagar & Ekta April 2014. on 24/08/2013. Total distributed to DPs to 14 nos NTHs in all 23 nos DPs of Nagar area. 5 PAPs identified as April/August 2016. Kantabaji area Distributed to 5 PAPs Squatters has been under Phase‐III in compensated in two Sep 2015. installment for 858,037 INR. All the PAPs are working in nearby Whether assistance Cement factory‐Hotgi distributed to DPs and are getting 10,000 INR to 15,000

21 Yes Yes Yes Not yet INR per month, and NA they have given in writing that they don’t need any training as they are already employed. Special Land acquisition Officer GRC formed at 2 cum Assistant Whether GRC GRC formed at 1 district GRC formed in all 4 22 Commissioner has NA Yes formed district (Balangir) (Mahasumund and districts been nominated as a Raipur) Chairman of GRC and DGM/RVNL as

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 28 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Sections Item Indicators Raipur‐Titlagarh Sambalpur– Hospet–Tinaighat Daund–Gulbarga Daund–Gulbarga Raipur‐Titlagarh No project Titlagarh project* project * project project (Maharashtra project (Odisha (Chhattisgarh (Karnataka Section) Section) Section) Section) member of GRC from PIU

Complaints to GRC 23 NIL NIL NIL NIL received/ resolved NIL NIL

Consultations held 24 3 places 4 places 5 places 13 places NA Yes with DPs Completed at Mahasamund, Ekta Kantabaji 25 Relocation Nagar, Parwati Completed NA NA Completed completed Nagar and Chandi Nagar

Inventory of losses 26 of Displaced Completed Completed Completed Completed Completed Completed Persons (DPs)

Impact on Completed Completed Completed Completed Completed Completed 27 Indigenous People/STs with (STs not found) (STs not found) (STs not found) (STs not found) (STs not found) (STs not found) kind of impact

Table 12: Status of land Acquisition and Resettlement

*Impact reported by NGO/RVNL after verification may change after conducting social impact assessment study by Revenue Department or Joint Measurement Survey findings

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 29 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Details regarding status of R&R implementation upto March 2018

Length of Length Area of land section No. of S. No Name of Project of line to be Status of R&R implementation free from HHs/PAPs (in kms) acquired R&R

Identification and verification of PAPs has been revised and completed and submitted. Joint Measure Survey (JMS) has also been completed. GRC formed. Valuation of structures have also been completed and micro plan has been prepared and has been submitted on 09/09/2013 by NGO at total rehabilitation cost of 87,386,088 INR for 681 HHs. However, R&R expert of GC advised to Raipur‐Titlagarh doubling 1. 99.94 98.85 kms Nil 261/261 minimize the Right of Way (ROW) and was agreed by PMC and project (Odisha section) RVNL. Actual COI (Corridor of Impact) was work out by NGO, RVNL and Revenue Officer. Micro plan has been revised and completed on 12/11/2013 at total R&R cost of 17,697,983.5 INR for 261 HHs based on actual COI. Micro plan approved and Identity cards distribution was started in Odisha section. Revised micro plans was approved in August 2015 for Mahasamund and Kantabanji areas bringing the new total to 261 HHs. Identity card distributed to 260 Raipur‐Titlagarh doubling PAPs in Mahasamund District in Chhattisgarh section, Parvati 2. project (Chhattisgarh 98.01 96.60 kms Nil 261/261 Nagar, Chandi Nagar and Ekta Nagar section. Bond paper of PAPs section) completed. Assistance distributed through RTGS. Paid in December 2015 to March 2018. Full and final installment have been paid. TH: Requisition for LA submitted for government and private land for Sambaplur, Sonepur Bargargh and Balangir Districts TH Sambalpur–Titlagarh NTH: Identification and verification and Joint measurement report 3. 182.00 125.00 kms 79.503 acres 1313/5252 doubling project completed on 02/07/2013. Micro Plan prepared on 27/09/2013 at NTH 14/14 total rehabilitation cost of 6,657,962 INR for 65 HHs. However, Revenue officer (RO) provided actual corridor of Impact (COI) and ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 30 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Length of Length Area of land section No. of S. No Name of Project of line to be Status of R&R implementation free from HHs/PAPs (in kms) acquired R&R

track plan which was reviewed by RVNL representative and NGO with GC. Micro plan was revised accordingly and completed and submitted on 28/10/2013 for a total R&R cost of 4,419,511 INR for 38 NTHs. Micro plan was reviewed on behalf of PIU Sambalpur. Rehabilitation cost of 4,419,511 INR for 38 NTHs reduced to 33,40,643 INR for 14 NTHs 1st instalment of compensation has been released to all 14 NTHs in April 2016. 2nd and final installment has been paid in August 2016. Identification and verification of PAPs has been completed and data updation work has also been completed and submitted Micro plan is finalized and Identity cards have been issued to PAPs of Koppal, Hosalli, Sompur and Annigeri villages. Disbursement of allowances to PAPs (12 Nos.) under phase ‐ I was Hospet–Tinaighat doubling conducted during 3rd week of December 2013 and (08 Nos) under 4. 201.31 195.31 kms 31.45 acres 82/308 project Phase – II during the first week of April 2014. 18.950 acres of land notified 6(1) for acquisition. 12.50 acres of land to be acquired through direct purchase. Three affected persons from district Koppal village Hosalli and Kampasagar has been compensated 5,265,353 INR for 1.38 acres through direct purchase during this quarter. Daund–Gulbarga doubling 5. 46 46 kms 0 0 NA project (Karnataka section) Daund–Gulbarga doubling Total 5 PAPs identified as Squatters has been compensated in two 6. project (Maharashtra 179 176 kms 0 5/20 installment of 858,037 INR. All the PAPs are found working in a section) nearby Cement factory‐Hotgi and are getting INR 10,000 to 15,000

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 31 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Length of Length Area of land section No. of S. No Name of Project of line to be Status of R&R implementation free from HHs/PAPs (in kms) acquired R&R

per month and they have given in writing that they don’t need any training. The GC social has collected all the relevant papers for final completion of this section. GC Social Expert recommends to close this project.

Table 13: Details regarding Rehabilitation and Resettlement

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 32 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Annexure I: LA Direct purchase Act Government of Karnataka

Government of Karnataka Orders

(L.A.Direct Purchase Act. Letter.No.54/2014)

Preamble:

Previously for the public/Govt/projects the the required land was use to acquire vide LA act 1894 and payment was use to make to the land owners according to the agreement made between both the parties. But since from 01.1.2014 new Act i.e. through the direct purchase of land process. In this Act – 2013 the transparency and appropriate value for the required land will be followed and there is no necessary for Re‐habilitation and Re construction. In this act, there is no provision to purchase the land as per the rates of the agreement made.

For the construction of public works like buildings, grave‐yard, water supply for multiple‐village water supply construction Electrical Grids, Under drainage, construction of Roads, and widening of Roads, construction of Railway Line, Railway under Bridge/over bridge, harbour, Airport and all other constructions of basic needs etc. the lands are required very very urgent. By this process the delay in land acquisition is avoided. There will be no delay in completing of the LA process. Because of this there will not be increase in the expenditure (Estimated Cost). So to avoid the delay in land acquisition, this Direct Land Purchase will be the good solution.

In continuation with this new Direct Land purchase Act, 2013, the provision are made to purchase of land directly from the Land‐Owner keeping transperencey and legestimatic rights for Re‐habilitation, and Re‐ construction (Karnataka) Act 2015.

This new LA Act (Karnataka) has come into force from 17.10.2015. According to this Act, for industrial purchase 500 Acre , for for other purpose 100 Acre, is the maximum limit for direct purchase , rehabilitation and re‐construction are exempted. Hence for the Government Projects the land can be purchased Directly from the land owners which will result not only the land availability for the projects but also the land comphensation will reach the land owner immediately and directly.

Consedering all these above considerations, the land required for the Projects can be purchased directly from the land owners. The following order is passed:

Government of Karnataka Orders Letter No. 54/LAQ/2014/BNG dtd:31.5.2016

Accoding to the subject discussed in the preamble, the Government has permitted to direct purchase of the land for the following works, i.e for the construction of houses , Grave ‐ yard, multiple – village water supply , electrical grid, under – drainage, road construction or widening of roads, construction of over bridge/under bridge, construction of Railway tracks, Airport. And for all their needful –public‐works, the required land is limited to 100 Acres and can be purchased directly from the land owners.

Under the Chairmanship of the District Collector, for fixing the Rate Price Advisory Committee can decide the Rates/Value for Lands. According to this rate / value will be fixed both to the purchaser and land seller(owner). Also the same rate/value of the Land can be accepted or denied to the both purchasing or selling party.

At the time of direct purchase of land, the beneficiary or the land buyer must submit yhe following details:

a) For which purpose the land is required direct purchase

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 33 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

b) Required area of the land c) Survey No. and details of the land proposed d) The R.T.C and map of the land required e) Agreement letter from the land owners f) Grant for Land Acquisition allowed by the purchasing body

If any objection for the rates or the decision of the Rates appraisal Committee’s, the objections may be raised /submit to the DC within the 30 days from the date of Advertisement.

For the proposed project only once the required limited land can be purchased.

At the time of fixing of Rates/Value for the land direct purchase the Rate appraisal Committee must consider all the considerations such as Transparency, Re‐ habilitation, Re‐construction Act‐2013. Also the limitation of land –limit etc.

As per order and in the Name of Governor of Karnataka

H.S.UdayKumar (Addl.Depty.Secretary) Revenue Dept(LandAcquitation) Government of Karnataka VidhanaSudha Bangalore

Copy to Gazett – Notification Copy to : 1) Chief Accounts Officer – Karnataka Banglore 2) Chief Secretary, Government of Karnataka VidhanaSoudha Bangalore 3) Addl.Chief Secretary , Government of Karnataka VidhanaSoudha Bangalore 4) Addl.Chief Secretary,Basic need and Development Secretary VidhanaSoudha Bangalore 5) Pinciple Secretary for Chief Minister VidhanaSoudha Bangalore 6) To all Principle Secretary, Government of Karnataka 7) Regional Commissioner Belgaum/Bangalore/Mysore 8) State Commissioner for Re‐habilitation, Re‐construction, Bangalore 9) To all DC and Land Acquisition Officers , Assistant Commssioner

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 34 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Annexure II: Notification issued by Odisha Revenue Department

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 35 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Annexure III: Approved note for extension of R&R personals

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 36 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 37 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Annexure IV: R&R Sale Deed of registerd land under direct purchase Hospet‐Tinaighat project

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 38 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 39 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 40 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 41 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 42 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Annexure V: Direct purchase payment details of Gadag village in HT project

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 43 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Annexure VI: Roll Diagram of Sambalpur‐Titlagarh project

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 44 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 45 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Annexure VII: R&R photographs of landowners registration of Hospet‐Tinaighat project

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 46 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

Annexure VIII: R&R photographs of ST project showing dismantling of TH structures

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 47 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes

Egis Rail – Egis India R&R Implementation Status No. 10 March 2018

ADB Loans No. 0060‐IND / 2793‐IND, 3108‐IND 48 Railway Sector Investment Program – Track Doubling and Electrification on Critical Routes