Initial Environmental Examination

Document stage: Draft Project Number: 42486-016 February 2019

IND: Urban Services Improvement Program – Subproject of Water Supply Improvement in , Pichhore, Bairad, Vijaypur, Aron and Towns

Package No: MPUSIP-4D

Prepared by Project Management Unit, Madhya Pradesh Urban Development Company, Government of Madhya Pradesh for the Asian Development Bank.

This draft initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, management, or staff, and may be preliminary in nature. Your attention is directed to the ‘terms of use’ section on ADB’s website.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Initial Environmental Examination

February 2019

IND: Madhya Pradesh Urban Services Improvement Program – Subproject of Water Supply Improvement in Karera, Pichhore, Bairad, Vijaypur, Aron and Isagarh Towns (Package 4D)

Prepared by Project Management Unit, Madhya Pradesh Urban Development Company, Government of Madhya Pradesh for the Asian Development Bank CURRENCY EQUIVALENTS (As of 25th February 2019)

Currency Unit - Conversion INR 1.00 = $ 0.014 $ 1.00 = INR 69.52

Abbreviations

AC – Asbestos Cement ADB – Asian Development Bank ASI – Archeological Survey of ASO – Assistant Safeguards Officer CFE – Consent for Establishment CFO – Consent for Operation CPCB Central Pollution Control Board EA – Executing Agency EAC – Expert Appraisal Committee EC – Environmental Clearance EHS – Environmental Health & Safety EIA – Environmental Impact Assessment EMP – Environmental Management Plan; ESR – Elevated Service Reservoir GOI – Government of India GOMP – Government of Madhya Pradesh IA – Implementing Agency IEE – Initial Environmental Examination; KL - Kilo liter NP – Nagar Parishad LPCD – Liters per Capita per Day MFF – Multi trench financing facility MLD – Million Liters per Day MOEF – Ministry of Environment and Forest MPPCB – Madhya Pradesh Pollution Control Board MPUDC – Madhya Pradesh Urban Development Company MPUSIP – Madhya Pradesh Urban Services Improvement Program NOC – No Objection Certificate OHT – Over Head Tank PE – Polyethylene PHED – Public Health Engineering Department PIU – Project Implementation Unit; PMC – Project Management Consultant PMU – Project Management Unit PO – Project Officer PWD – Public Works Department REA – Rapid Environmental Assessment Checklist RoW – Right of Way SEIAA – State Environmental Impact Assessment Authority SPS – Safeguard Policy Statement, 2009 ToR – Term of Reference UDED – Urban Development & Environment Department ULB – Urban Local Body WHO – World Health Organization WRD – Water Resource Department WSS – Water Supply Scheme WTP – Water Treatment Plant

WEIGHTSAND MEASURES

˚C Degree Celsius km Kilo metre lpcd Litres per capita per day mm millimeter m Metre mld Million litres per day mm Milli metre Nos. Numbers sq.km Square Kilometer MCM Million cubic meter

Table of Contents I. EXECUTIVE SUMMARY ...... 11

II. INTRODUCTION ...... 20

A. Background ...... 20

B. Purpose of this IEE Report ...... 22

C. Report Structure ...... 22

III. DESCRIPTION OF THE SUBPROJECT ...... 23

A. Project Area ...... 23

B. Existing Water Supply Situation ...... 25

1. Karera Town ...... 25

2. PICHHORE ...... 25

3. ARON ...... 25

4. BAIRAD ...... 25

5. VIJAYPUR ...... 26

6. ISAGARH ...... 26

C. Proposed Project ...... 27

D. Implementation Schedule ...... 38

IV. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK ...... 60

A. ADB Policy ...... 60

B. National Environmental Laws ...... 60

V. DESCRIPTION OF THE ENVIRONMENT (BASELINE DATA) ...... 72

A. Methodology Used for Baseline Study ...... 72

B. Baseline Environmental Profile ...... 72

VI. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ...... 136

A. Introduction ...... 136

B. Pre-Construction Impacts – Design & Location ...... 137

C. CONSTRUCTION IMPACTS ...... 164 D. OPERATION & MAINTENANCE IMPACT ...... 171

VII. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE ...... 173

A. Overview ...... 173

B. PUBLIC CONSULTATION ...... 173

C. INFORMATION DISCLOSURE ...... 189

VIII. GRIEVANCE REDRESS MECHANISM ...... 190

A. PROJECTSPECIFICGRIEVANCE READRESSMECHANISM ...... 190

B. Purpose of the GRM Manual: ...... 190

C. Principles: ...... 190

D. Nature and scope of Grievance Redress Mechanism under MPUSIP ...... 191

E. Structure of GRM and its Functions ...... 191

F. Process of Grievance Redress Mechanism ...... 195

G. Monitoring and Evaluation systems of GRM ...... 198

H. Action Plan for the formation of the GRM ...... 199

IX. ENVIRONMENTAL MANAGEMENT PLAN ...... 200

A. Environmental Management Plan ...... 200

B. IMLEMENTATION ARRANGEMENT ...... 230

C. MONITORING AND REPORTING ...... 233

D. Training Needs ...... 234

E. EMP IMPLEMENTATION COST ...... 235

X. CONCLUSION AND RECOMMENDATION ...... 237

List of Tables Table 1: Proposed Water Supply Subproject Components under Package- 4D ...... 29 Table 2: Applicable Environmental Regulations ...... 61 Table 3: List of Activity Prohibited / Regulated Within The Eco-Sensitive Zone ...... 68 Table 4: WHO Ambient Air& Noise Quality Guidelines ...... 71 Table 5: Baseline Characteristics of Package 4D Towns ...... 73 Table 6: Site Environmental Features of Karera Town ...... 105 Table 7: Site Environmental Features of Pichhore Town ...... 115 Table 8: Site Environmental Features of Aron ...... 119 Table 9: Site Environmental Features of Bairad ...... 123 Table 10: Site Environmental Features of Vijaypur ...... 128 Table 11: Site Environmental Features of Isagarh ...... 133 Table 12: Hydraulic Design of Weir ...... 141 Table 13 :Salient Features of Pachipura Dam...... 150 Table 14: Analysis of River Flow Data - Kunwari ...... 151 Table 15: Existing Weir Recently Constructed by WRD at the proposed Intake Well Location ...... 152 Table 16: Surface Water Quality of Karera, pichhore , Aron, Bairad and Vijaypur Towns 153 Table 17: Details of Existing Tube Wells – Isagarh Town ...... 154 Table 18: Ground Water Source – Isagarh Block ...... 159 Table 19 : Ground Water Quality Isagarh Town ...... 161 Table 20: Summary of Stakeholder Consultation - Karera Town ...... 173 Table 21: Summary of Stakeholder Consultation - Pichhore Town ...... 176 Table 22: Summary of Stakeholder Consultation - Aron Town ...... 177 Table 23: Summary of Stakeholder Consultation - Bairad Town...... 179 Table 24: Summary of Stakeholder Consultation - Vijaypur Town ...... 183 Table 25: Summary of Stakeholder Consultation - Isagarh Town ...... 188 Table 26: DesignStage Environmental Management Plan ...... 201 Table 27: Environmental Management Plan of Anticipated Impacts during Pre-Construction ...... 206 Table 28: Environmental Management Plan of Anticipated Impacts during Construction .. 208 Table 29: Environmental Management Plan of Anticipated Impacts during Operation ...... 224 Table 30: Environmental Monitoring Plan of Anticipated Impacts during Construction ..... 226 Table 31: Environmental Monitoring Plan of Anticipated Impacts during Operation ...... 229 Table 32: Outline Capacity Building Program on EMP Implementation ...... 234 Table 33: Cost Estimates to Implement the EMP ...... 235

List of Figures Figure 1: Location of Project area ...... 24 Figure 2: Site Photograph Showing Recommended and Proposed New Location of Intake Well on Eastern Bank of Samoha Dam across Mahuar River at Village Khera Modi for Karera Town WSS after Joint Visit by PMC, PIU PMU/PMC & DBO Contractor on 24th January 2018 ...... 39 Figure 3: Proposed Water Supply Scheme & RWRM of Karera Town ...... 40 Figure 4: Layout Plan of WTP – Karera Town ...... 41 Figure 5:Schematic Diagram of Head work/Intake WellShowing All Arrangement- KareraTown ...... 42 Figure 6: Pichhore Water Supply Scheme Showing Proposed Subproject Components ...... 43 Figure 7: Layout Plan of Proposed WTP – Pichhore Town ...... 44 Figure 8: Aron WSS Showing Subproject Components ...... 45 Figure 9: Google Earth Map Showing Proposed Water Supply Subproject Components and Transmission System ...... 46 Figure 10 : Proposed Weir Details – Cross-Section and Elevation in Sindh River for Aron Town ...... 47 Figure 11:Typical Cross section and Plan with and without gate for Anicut on Sindh River– Aron town WSS ...... 48 Figure 12: Typical Cross-Section of Anicut – Aron Town WSS ...... 49 Figure 13: Details of Intake Well Arrangement in Sindh River for Aron Town .. 50 Figure 14: Layout Plan of WTP Aron Town ...... 51 Figure 15: Proposed Water Supply Zones and Transmission System –Bairad ...... 52 Figure 16: Proposed Intake Well Arrangement at Pachipura Dam for Bairad Town ...... 53 Figure 17: Layout Plan of WTP Bairad Town ...... 54 Figure 18: Proposed Water Supply Zones and Transmission System– Vijaypur ...... 55 Figure 19: Plan and Section of Intake – Vijaypur...... 56 Figure 20: Intake Arrangement – Vijaypur ...... 57 Figure 21: Layout Plan of Proposed WTP- Vijaypur ...... 58 Figure 22: Proposed Water Supply Zones and Transmission System –Isagarh Town ...... 59 Figure 23: Proposed WSS Components of Karera Town on Toposheet ...... 111 Figure 24: Google Map of Karera Wildlife Sanctuary and Subproject Town Karera-Showing the Boundaries of of Both Clearly Along with Location of Main Components (Source/Intake, RWRM, WTP, CWRM & OHTs etc.) as Per DBO Contractor ...... 112 Figure 25: Map Showing Karera Bird Sanctuary and Subproject Karera Town ...... 113 Figure 26: Proposed Component of Pichhore WSS on Topo Sheet ...... 118 Figure 27: Proposed Component of Aron WSS on Toposheet ...... 122 Figure 28: Proposed Component of Bairad WSS on Toposheet...... 126 Figure 29: Google Map of Kuno Wildlife Sanctuary and Subproject TownsBairad & Vijaypur-Showing the Boundaries of Both Clearly Alongwith Location of Main Components(Source/Intake, WTP and OHTs etc ...... 127 Figure 30:Subproject Area & Environs Showing Proposed WSS Components & Alighnment of Transmission Main– Vijaypur Town ...... 132 Figure 31: Project Area & Environ – Isagarh Town ...... 135 Figure 32: Proposed Weir Location on Sindh River Showing River Network...... 142 Figure 33: Veiw of River Network (Sindh River) Showing Proposed Weir Location ...... 143 Figure 34: Catchment Area of Well ...... 143 Figure 35: Weir Site C/S at Sindh River ...... 145 Figure 36: Contour Map of Sindh River ...... 145 Figure 37: Map of Submergence Area - Showing River Course and weir Location in Sindh River as the River Contour Plan Superimposed on Google Map ...... 147 Figure 38: View of Deep Vally of Sindh River from Proposed Intake Location ...... 148 Figure 39: Hydrology, Isagarh Block under District Ashok Nagar (M.P.) ...... 156 Figure 40: Depth of Water Level – Pre-Monsoon (May 2012) in District Ashok Nagar (M.P.) ...... 157 Figure 41: Depth of Water Level – Post-Monsoon (May 2012) in District Ashok Nagar (M.P.) ...... 158 Figure 42: Work Flow Diagram on GRM...... 194 Figure 43: Structure and Process of GRC ...... 198

List of Appendices Appendix 1: Rapid Environment Assessment Checklist – Package 4D ...... 241 Appendix 2: National Ambient Air Quality Standards ...... 246 Appendix 3: Vehicle Exhaust Emission Norms ...... 246 Appendix 4: National Ambient Air Quality Standards in Respect of Noise ...... 246 Appendix 5: Drinking Water Standards ...... 247 Appendix 6: Salient Features of Major Labour Laws Applicable to EstablishmentsEngaged in Construction of Civil Works ...... 250 Appendix 7: EXTRACT FROM CONSTRUCTION & DEMOLITION MANAGEMENT RULES, 2016 ...... 252 Appendix 8: Sample Outline Spoils (construction waste) Management Plan ...... 258 Appendix 9: Sample Outline Traffic Management Plan...... 259 Appendix 10: Summary of Stakeholder Consultation, Consultation Photographs & List of Participants- – Karera Town ...... 266 Appendix 11: Stakeholder Consultation Photographs & List of Participants – Madhva Natinal Park for Karera Wild Life Sanctuary for Karera Town on 10.05.2018 ...... 271 Appendix 12: Summary of Stakeholder Consultation, Photograph of Consultation and List of Participants – Pichhore Town ...... 272 Appendix 13: Summary of Stakeholder Consultation, Photograph of Consultation and List of Participants – Aron Town ...... 275 Appendix 14: Summary of Stakeholder Consultation, Photograph of Consultation and List of Participants – Vijaypur Town ...... 281 Appendix 15: Summary of Stakeholder Consultation, Photograph of Consultation and List of Participants – Bairad Town ...... 289 Appendix 16: Consultation with officials of Divisional Forest Officer, Kuno Wildlife Sanctuary, (Madhya Pradesh) Dated: 15.05.2018 For Bairad and Vijaypur Town WSS Projects ...... 297 Appendix 17: Summary of Stakeholder Consultation, Photograph of Consultation and List of Participants – Isagarh Town...... 299 Appendix 18: Surface Water Quality Analysis Report of Subproject Towns under Package- 4D ...... 302 Appendix 19: Yeild Test Report and Exisiting Tube Well Details for Isagarh Town ...... 310 Appendix 20: Salient Features of Dams/ Resrvores for Subproject Towns ...... 312 Appendix 21: Hydraulic Design Details & Drawing of Weir for Aron Town WS ...... 316 Appendix 22: Rainfall Data of Aron Town ...... 322 Appendix 23: Kunwari River Discharge Data for Vijaypur Town ...... 325 Appendix 24: NOC From WRD for Water Abstraction for Subproject Towns under Package- 4D ...... 330 Appendix 25: Final Notification Declaring Eco sensitive Zone around Karera Wildlife Sanctuary by MOEFCC, New on Dated 15.09.2017 ...... 335 Appendix 26: Minutes of 18th Meeting of the Standing Committee of NBWL Held on 12th April 2010 For Denotification & Rationalization of Boundaries of Karera Wildlife Sanctuary 346 Appendix 27: Draft Notification Declaring Eco sensitive Zone around Kuno-Palpur Wildlife Sanctuary by MOEFCC, on Dated 09.11.2017 ...... 350 Appendix 28: Sample Grievance Registration Form ...... 364 Appendix 29: Sample Environmental Site Inspection Report ...... 365 Appendix 30: Quarterly Reporting Format for Assistant Safeguards Officer ...... 367 Appendix 31: MOEF Letter Regarding No Prior Approval Required regarding Wildlife Clearance Within Eco Sensitive Zone of National Park & Wildlife Sanctuary as Honble Supreme Court Order Dated 04.12.2006...... 372

I. EXECUTIVE SUMMARY 1. Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as ‘the Project’. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Environment Department (UDED) shall be the executing agency for the Project.

2. The Project components are as follows:

(i) Component 1: Improvements to water supply and sewerage services in identified towns ➢ Continuous, pressurized, safe and sustainable drinking water through private household metered connections to 350,000 households with about 1.7million population resident in sixty-four towns in the State of Madhya Pradesh in Central India; and ➢ Sewage and storm water collection and treatment services proposed initially in two (2) identified towns (Khajuraho and Rajnagar) servicing about 42,000 population resident in 8000 households;

(ii) Component 2: Institutional Strengthening ➢ Capacity Building of implementing agencies (IAs), participating Urban Local Bodies (ULBs) and service utilities in contract management and service delivery for ensuring long term sustainability of services; ➢ Setting up of geographic information system (GIS) based water and sanitation asset management and service delivery monitoring; and ➢ Structured behavioral change campaigns to ensure the improvement in public health and cost recovery of service delivery.

(iii) Component 3: Project Management and Administration Support. This component will support the smooth and effective implementation and operation of the Project which includes expert support in Project design and implementation (design, procurement and Contract and Project Management, safeguards etc.), and project administration through Executing and Implementing Agencies.

3. The key outcome envisaged from the project is “effective urban water service delivery model rolled out in selective urban clusters of the State with the objective of achieving the following performance indicators by the year 2022.

4. The Subproject: This Initial Environmental Examination report deals with water supply scheme of Package 4D towns contains 6 towns; Karera, Pichhore and Bairad in district and Aron in , Isagarh in and Vijaypur in in Madhya Pradesh state. Improvement of water supply in these six towns is one of the projects proposed under the MPUSIP and will be implemented under a single Design-Build-Operate (DBO) contract package. The area of Karera town is 12 Sq. Km and population as per 2011 census is 28705. Pichhore town has an area of 8 Sqkm and population as per 2011 census is 18127. Aron town has an area of 20.1 Sq KM and population as per 2011 census is 28010. Isagarh has a population of 12583 as per 2011 census and has a geographical area of 18Ssq. km. Bairad has an area of 77 sq.km and population as per 2011 census is 18313.Vijaypur has an area of 3 sqkm and population as per latest census is 16,964. The objective of the subproject is to achieve safe and sustainable water services both in terms of services to customers, cost recovery and conservation of precious water resources. The subproject envisages providing 100% coverage of population with continuous, pressurized and safe drinking water services and achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency. The subproject includes civil works, project implementation and management, and non-physical investments. The physical investments include the following:

(A) Karera: The Karera WSS include (i) proposal of intake well of dia 6m and height 11.5m at Samoha Dam, which is constructed across Mahuwar near Khera Modi Village (ii) Water treatment plant of 5.7 MLD capacity; (iii) Construction of three new OHT of 1000 KL, 700KL and 500KL capacity; using of existing 200 KL OHT by reconditioning (iv) 13500 m of raw water rising mains and 4725 m clear water feeder mains (v) 52799 m of distribution lines proposed in Karera (B) Pichhore: The Pichhore WSS include (i)Utilization of existing jack well at Futiwar dam for water(ii) Water treatment plant of 3.0 MLD capacity; (iii) Proposal for utilization of existing GSR of capacity 200KL and 200 KL; construction of two new GSR of capacity 200KL and 250KL (iv) 3250 m of raw water rising mains and 2550 m of clear water feeder mains (v) 33125 m of distribution lines proposed in Pichhore. (C) Aron: The Aron WSS include (i) Construction of weir of length 50.0m and height 5.0m across the Sindh River (ii) proposal of jack well of dia 6m and height 20.0m at Sindh River (iii) Water treatment plant of 4.5 MLD capacity; (iv) Construction of new over head tank of capacity 700KL and utilization of existing 500 KL OHT by reconditioning (iv) 8680 m of raw water rising mains and 2550 m clear water feeder mains (v) 20559 m of distribution lines proposed in Aron. (D) Bairad: The Bairad WSS include (i)Intake cum pump house 5m dia, 11.36m height. Pumps 2 nos (1 working + 1 standby) of total 19 Kw (ii)Raw Water Rising Main- DI K9 790m length, 250mm dia. (iii)WTP 2.91 MLD (iv)Clear Water Rising Main-DI K9 including Feeder Mains 4.88km length with 150 and 200mm diameters. (v)Sump cum Pump House Pump room of 6m diameter and 4.5m height mounted on Sump of 90 KL Capacity. Pumps 4 nos (2working + 2 standby) of total 30 Kw. (vi)OHSRs (15m height)300 KL capacity in Zone-1 (15m height),300 KL capacity in Zone-2. (15m height),225 KL capacity in zone -3 (20m height) (vii)HDPE Pipes PE100 PN10 Class - Distribution system(km) 89.178(viii)Household Connections with flow meters 3,400 nos (ix)Bulk flow Maters 8 Nos. (E) Vijaypur: (i) Existing Weir of 4 m Height, 155 m length constructed by WRD (ii). Intake well cum pump house of 4.5m dia, 13 m height and Pumps 2 nos (1 working + 1 standby) of total 14 Kw, (iii) RWRM of 300 m length, 200mm dia. (iv). WTP of 1.56 MLD, (v). CWRM of 3.72 Km length with 150, 200 and 250 mm diameters, (vi). Sump cum pump house: Pump room of 5m diameter and 4.5m height mounted on Sump of 75 KL Capacity and Pumps 2 nos (1 working + 1 standby) of total 22.20Kw, (vii) HDPE Pipes PE100 PN10 Class -Distribution system of 31 km; and (viii). 8 nos Bulk flow meters and 3030 nos household connections. (F) Isagarh: The Isagarh WSS include (i) Proposed two Clear Water Sumps of 1.60 LL and 1.80 LL capacity with chlorinator Plant; (ii) Pumping Machinery at Tube Wells, 3.33 LPS discharge and 100.0 M head, Pumping Machinery at Proposed CWS, 8.79 LPS discharge and 32.0m head ( Working =1.0 Nos & Standby =1.0 Nos ) and Pumping Machinery at Proposed CWS at Ward-2 (Zone-2),9.0 LPS discharge and 33.0M head ( Working =1.0 Nos & Standby =1.0 Nos ); (iii) Feeder main of 3989 m length; (iv) Distribution Network of 22190 m length and 75 mm to 315 mm dia pipes.(v) bulk flow meters and (vi) house service connection including consumer meters

5. Screening and assessment of potential impacts. ADB requires the consideration of environmental issues in all aspects of the Bank’s operations, and the requirements for environmental assessment are described in ADB’s Safeguard Policy Statement (SPS), 2009. As per the GoI EIA Notification, 2006, this subproject does not require EIA study or environmental clearance. The potential environmental impacts of the subproject have been assessed using ADB Rapid Environmental Assessment Checklist for Water Supply. Then potential negative impacts were identified in relation to pre-construction, construction and operation of the improved infrastructure.

6. The subproject is unlikely to cause significant adverse impacts because: (i) the components will involve straightforward construction and operation, so impacts will be mainly localized; (ii) predicted impacts are site-specific and likely to be associated with the construction process and are produced because the process is invasive, involving excavation and earth movements; and (iii) being located mainly in an existing built-up area, will not cause direct impact on terrestrial biodiversity values. Potential negative impacts mainly arise from disturbance of residents, businesses, increase in traffic, increase in noise level and dusts, and the need to dispose moderate quantities of waste soil during construction phase and generation of sludge from the WTP during operation and maintenance phase. However, there are well- developed methods for mitigation of these impacts to acceptable levels.

7. Categorization. Based on results of the assessment and ADB SPS, the water supply subproject under package-4D is classified as environmental Category B, i.e., the subproject is judged to be unlikely to have significant adverse environmental impacts. Accordingly, this initial environmental examination (IEE) assesses the environmental impacts and provides mitigation and monitoring measures to ensure that there are no significant impacts as a results of the project.

8. This IEE aims to (i) provide critical facts, significant finding, and recommended actions; (ii) present the national and local legal and institutional framework within which the environmental assessment has been carried out; (iii) provide information on existing geographic, ecological, social and temporal context including associated facilities within the subproject’s area of influence; (iv) assess the subproject’s likely positive and negative direct and indirect impacts to physical, biological, socioeconomic, and physical cultural resources in the subproject’s area of influence; (v) identify mitigation measures and any residual negative impacts that cannot be mitigated; (vi) describe the process undertaken during project design to engage stakeholders and the planned information disclosure measures and the process for carrying out consultation with affected people and facilitating their participation during project implementation; (vii) describe the subproject’s grievance redress mechanism for resolving complaints about environmental performance; (viii) present the set of mitigation measures to be undertaken to avoid, reduce, mitigate, or compensate for adverse environmental impacts; (ix) to describe the monitoring measures and reporting procedures to ensure early detection of conditions that necessitate particular mitigation measures; and (x) identify indicative costs and who is responsible for carrying out the mitigation and monitoring measures. 9. Description of Environment: Most of the subprojects components locations are located in subproject towns of Karera, Pichhore, Bairad, Aron, Isagarh and Vijaypur and their surroundings. The immediate surroundings were converted into urban use for many years ago, and there is no natural habitat left at the subproject sites. There are no protected areas, forests and archaeological sites in the subprojects towns. Isagarh town water supply is based on ground water source. According to CGWB, ground water development in Isagarh block falls under safe zone. The proposed/existing intake structures will be located in river bed/ existing dams on government lands. Only for Aron town weir will be constructed across river Sindh, while the WTPs including clear water sumps will be also located close to the intakes where sufficient government land is available. These facilities are located outside the town, and are mostly surrounded by agricultural lands, forest areas and rivers/reservoirs. Nearest protected area from Vijaypur and Bairad towns is Kuno Wildlife Sanctuary which is also known as Palpur - Kuno Wildlife Sanctuary is situated at a distance of 24.0 km away from Vijaypur and about 10.0 km away from Bairad town. None of the subproject components of Bairad and Vijaypur towns are located in ecosensitive zone nor in sanctuary area of Kuno wildlife sanctuary. So there is impacts envisaged.

10. In Karera Town – As per DPR, source of water for subproject water supply town Karera was proposed on western bank of Samoha dam located at Jhanda village. Later on, it was come under notice that proposed location of intake as well as alignment of raw water rising main comes within the boundary of Karera Wildlife Sanctuary (also known as Son Chiraiya Bird Sanctuary).

11.

12. This sanctuary boundary is located about which is about 14 Kms. away from subproject town Karera and secondly proposed alignment passes through private land too. Taking into consideration, a joint visit of DBO Contractor, PMU- along with PMC was scheduled on 24th January 2018 to resolve this issue and new location has been identified and recommended unanimously by joint team.

13. Team has visited three different places to finalize the location of Intake well cum pump house namely i) Northern Side of village Khera Modi: this site was found not suitable as impounding water is quite away from the stream and water is shrinking about 250 metre away from intake location during summer as also confirmed by local people, apart from that silting and desilting will cause another obstacle. And secondly it may require acquisition of private land to reach at intake well. ii) at Samoha Dam: this site was technically suitable as enough water is available throughout the year but raw water raising main will pass through village Samoha. This village is located on the road and the road passes through the centre of village. A significant number of residential structures reported on both side of road, it is about 1.5 to 2 kms in length and congested too under village Samoha. Proposed raw water rising main will traverse through this road only. Therefore, proposed alignment is socially not acceptable due to its negative impact on road side structure and there might be chance to puncture the water pipeline. Apart from that this location is about 30 kms. away from subproject town. iii) Eastern Bank of Samoha Dam across Mahuwar river at village Khera Modi: Another new location as water source is identified on the eastern bank of Samoha dam which is located near a very small hamlet namely Khera Modi under Panchayat Machhawali. This new proposed site is about 13 - 14 Kms away from subproject town. Enough government land is available on the bank of Samoha dam (Mahubar river) which is required for proposed Intake well cum pump house and secondly no involuntary resettlement impact (both permanent and temporary) is envisaged. Among these three new locations as mentioned, joint team has unanimously recommended water source namely “eastern bank of Samoha Dam at village Khera Modi” as preliminary examine shows that newly recommended source is found socially & environment and technically acceptable. Refer Fig-2- Showing Site Photograph of Recommended & Proposed New Location of Intake Well on Eastern Bank of Samoha Dam. As per villagers, enough water is available throughout the year at proposed site of Intake well and enough government land is also available without any encroachment. This proposed location does not come under Son Chiraiya Bird Sanctuary, Karera. However as per mapping on google earth map, according to coordintes of prominent points of the boundary of Karera Bird sanctuary and coordinates of the boundary of Karera Bird sanctury Eco-sensitive zone as mentioned in MOEFCC Notification 15th September 2017, new recommended intake location comes under Eco-Sensitive Zone about 500 m away from the boundary of Karera Bird Sanctuary. No Flora and Fauna has been reported in and around the proposed site. Also no environment impact observed at site.

14. The boundary of Karera Wildlife Sanctuary is about 500 m away from the boundary of Karera municipal areas. All the proposed subproject components like Recommended & proposed new location of intake, WTP, OHTs, RWRM, CWRM & distribution networks are within the boundary of Eco-Sensitive Zone (ESZ) of Karera wildlife sanctuary. All the components like Intake, WTP & OHT are located about 500 m – 2 km away from the boundary of Karera wildlife sanctuary as shown on Google Map of Karera wildlife sanctuary and subproject town Karera; showing the boundaries of both clearly along with location of main components i.e. Source/intake, RWRM, WTP, CWRM & OHTs etc. which is appended as Fig – 24. Intake well is located around 13.2 km away from Karera town. Intake well is about 500 m away from boundary of Karera bird’s sanctuary and comes under Eco-Sensitive zone (ESZ). Extraction of surface water within Eco Sensitive Zone is regulated under applicable Law (Refer Table 3, S. No. 27 & Appendix 25, Para 4, S. No. 27- MOEFCC Notification). Also NoC from WRD for abstraction of water from Samoha dam and construction of intake already obtained (Refer Appendix 24). The raw water rising main, connecting intake and WTP, will be partly outside and partly within the towns, which will be laid partly within the Eco sensitive zone boundary and partly outside the ESZ boundary of Karera sanctuary. Raw water and clear water rising main will be laid underground from the intake to WTP and from WTP to OHTs site along an existing PWD road within ROW. WTP, OHTs and clear water rising main is located within the municipal limits of Karera Nagar Parishad, but it is within the boundary of ESZ of Karera bird sanctuary. WTP is about 500m and OHTs are about 1-2 km away from the boundary of Karera wildlife sanctuary, where there are no sensitive environmental features. Construction activities in Eco-Sensitive Zone is permitted as per building byelaws to meet the residential needs of the local residents such as construction and renovation of infrastructure and civic aminities (Refer Table 3, S. No. 14 & S. No. 20 and Refer Appendix 25, Para 4, S. No. 14 & S. No. 20- MOEFCC Notification). However, it will be done with mitigation measures, as per applicable laws, rules and regulation and available guidelines. Also Refer MOEF letter Appendix 31, which talks about non-applicability of wildlife clearance about the projects falling in ESZs which are not covered under EIA Notification and which do not require environmental clearances would aslo not required approval of standing committee of National Board of wild life.

15. Also consultation conducted with forest official on dated 10.05.2018 at Office of Chief Conservator of Forest & Director, , Shivpuri as Its management and control is under Field Director of Madhav National Park (Refer Appendix 7 & Appendix 10). Detailed discussions held and briefed about proposed components under water supply scheme for Karera town within eco-sensitive zone and its impact on Karera bird Sanctuary. They told that they have no objection as this project is to meet the daily residential needs of the local residents by providing with a constant supply of better quality water as the subproject will improve the overall environmental quality of the town and surrounding areas.

16. 17. Karera Wildlife sanctuary today has not a single bird species. Owing to villagers/public pressure and the extinction of the bird locally, the National Board for Wildlife and the Government of Madhya Pradesh have decided to denotify the sanctuary and is seeking the Centre's approval. The decision is now awaiting a final approval from the Supreme Court of India and should it come through, the sanctuary will become the country's first such reserve to lose its official recognition. (For Denotification Details Refer “Minutes of 18th Meeting of Standing Committee of NBWL annexed as Appendix 26.)

18. Since the proposed subprojects components such as Intake, RWRM, WTP, CWRM and OHTs works shall be limited to actual construction area and the access roads, but appropriate steps should be taken according to the nature of the risk. Precaution must be taken care to minimize the noise during construction work to avoid any negative impact on bird sanctuary. The impact will be only for limited time during construction work.

19. Apart from this, the forest namely “Karera Reserve forest” is only at a distance of 2 km from Karera town. Karera Reserved Forest is a forest reserve and is east of Māhuār Protected Forest, south of Bagedhri village and southeast of Langūri village. Karera Reserved Forest has an elevation of 282 metres. Local trees are similar to the regional flora. Domestic animals are abundantly found in the region. None of the subproject components are located in forest areas. Refer Google Map & SOI Map annexed as Fig- 23 & Fig- 25.

20. For Bairad & Vijaypur Towns - Kuno Wildlife Sanctury which is also known as Palpur - Kuno Wildlife Sanctuary is situated at a distance of 10 km away from Bairad and 24 km away from vijaypur town. None of the subproject components are located within the boundary of Kuno wildlife sanctuary nor in its ecosensitive zone. Refer Google Maps of Kuno wildlife sanctuary and subproject towns; showing the boundaries of both clearly alongwith location of main components i.e. Source/intake, WTP & OHTs etc. which is appended as Fig - 29

21. The subproject components of rest of the five towns – water tanks, distribution lines, connections etc. will be located within the urban areas. The raw water transmission pipes, connecting intake and WTP, will be essentially outside the town, and clear water transmission pipes, from WTP to distribution reservoirs, will be partly outside and partly within the towns. Project area experience a subtropical climate, typical to north India, hot summers, cold and dry winters and monsoon rains. There is no ecological sensitive feature like forest area in project area. Flora and fauna found of local species. Aquatic life in the project areas is not notable. Towns are densely populated in the core/old town areas with narrow lanes, and small and closely built houses, while most of the areas are undeveloped and are still under agricultural use. Commercial areas are along the main roads, which are mostly congested with activities, pedestrians and traffic. All the pipelines will be located along the public roads. In the wider roads, pipelines will be laid in the earthen shoulder along the tarmac within the RoW, and in narrow roads in central town area, pipelines will be laid within the road tarmac. Many wide roads are lines with trees, which will not be removed for laying of pipelines.

22. Environmental Management Plan: An environmental management plan (EMP) has been developed to provide mitigation measures to reduce all negative impacts to acceptable levels, which includes; (i) mitigation measures for environmental impacts during implementation; an environmental monitoring program, and the responsible entities for mitigating, monitoring, reporting; (ii) public consultation and information disclosure; and (iii) a grievance redress mechanism. Locations and sitting of the proposed infrastructures were considered to further reduce impacts. These include (i) locating facilities on government-owned land to avoid the need for land acquisition and relocation of people; and (ii) laying of pipes in RoW alongside main/access roads, to reduce acquisition of land and impacts on livelihoods specifically in densely populated areas of the town.

23. The EMP includes design measures such as (i) selection of construction methodology near protected area in discussion with the forest department (ii) Selection of sustainable water sources (iii) wash water recovery for the WTP to reduce effluent to be discharged; (iv) beneficial use of treated sludge; and (iv) quick leak detection and rectification to save the resources, etc. During construction, the EMP includes mitigation measures such as (i) implementation of traffic management plan in coordination with local traffic police to minimize traffic impacts; (ii) awareness campaigns and consultations to inform residents and businesses of potential disturbances; (iii) provision of walkways and planks over trenches to ensure access will not be impeded; (iv) appropriate scheduling of works to avoid peak tourist season in important places; (v) use of noise-dampening measures in areas with sensitive receptors such as hospitals, schools, places of worships and other silence-zones; (vi) use of dust-suppression methods such as watering and/or covering of stockpiles; and (vii) finding beneficial use of excavated materials to extent possible to reduce the quantity that will be disposed off. As for the O&M phase, all facilities and infrastructure will operate with routine maintenance, which should not affect the environment, facilities will need to be repaired from time to time, but environmental impacts will be much less than those of the construction period as the work will be infrequent, affecting small areas only. The design of the WTPs includes dewatering and drying areas as part of sludge management. The EMP includes mitigation measures and monitoring plan to ensure compliance to environmental standards during O&M phase.

24. The EMP will guide the environmentally-sound construction of the subproject and ensure efficient lines of communication between Madhya Pradesh Urban Development Company (MPUDC), project management unit (PMU), project implementing unit (PIU), consultants and contractors. The EMP will (i) ensure that the activities are undertaken in a responsible non- detrimental manner; (i) provide a pro-active, feasible and practical working tool to enable the measurement and monitoring of environmental performance on site; (ii) guide and control the implementation of findings and recommendations of the environmental assessment conducted for the subproject; (iii) detail specific actions deemed necessary to assist in mitigating the environmental impact of the subproject; and (iv) ensure that safety recommendations are complied with. The EMP includes a monitoring program to measure the environmental condition and effectiveness of implementation of the mitigation measures. It will include observations on- and off-site, document checks, and interviews with workers and beneficiaries.

25. The DBO contractor will be required to PMU, for review and approval, a site environmental plan (SEP) including(i) proposed sites/locations for a construction work camps, storage areas, haulaing roads, lay down areas, disposal areas for solid and hazardous wastes: (ii) specific mitigation measures following the approved EMP; (iii)monitoring program as per SEP; and (iv) budget for implementation. No works are allowed to commence prior to approval of SEP.

26. A copy of the EMP/approved SEP will be kept on site during the construction period at all times. The EMP included in the bid and contract documents. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance.

27. Consultation, disclosure and grievance redress mechanism. Public consultation was done in the preparation of the project and IEE report at town level and with people and residents residing near proposed subprojects components. Consultation were also held with the officials of Madhav National Park as the Karera wildlife sanctuary’s management and control is under them. They have no objection. Refer Appendix 10 to Appendix 11. Also consultation was conducted with the officials of Kuno wildlife sanctuary for Bairad & Vijaypur towns. Refer Appendix 14 to Appendix 16. The detailed of Public consultation meetings are given in Appendix 11 to Appendix 17. The stakeholders were involved in developing the IEE through discussions on-site and public consultation at several places in the town, after which views expressed were incorporated into the IEE and in the planning and development of the project. The IEE will be made available at public locations and will be disclosed to a wider audience via the ADB, MPUDC and PMU websites. The consultation process will be continued and expanded during project implementation to ensure that stakeholders are fully engaged in the project and have the opportunity to participate in its development and implementation. A grievance redress mechanism is described within the IEE to ensure any public grievances are addressed quickly.

28. Implementation Arrangements. Urban Development and Environment Department (UDED) of Government of Madhya Pradesh will be the Executing Agency. Implementing Agency will be Madhya Pradesh Urban Development Company (MPUDC), A central Project Management Unit (PMU) attached to MPUDC will be responsible for implementing the MPUSIP. The PMU will be supported by Program Implementation Units (PIUs). Several teams of Design Consultants, and a Program Management Consultant (PMC) centrally located in PMU and with field teams, will support PMU & PIUs. Infrastructure will be designed, built, and operated (DBO) by contractor for 10 years, after which it will be transferred to the ULB. Project Officer (Environment) at PMU and Assistant Safeguard Officer (ASO) at each of the PIU will be responsible for environment safeguards tasks, and will be supported by Environment Specialist of PMC Team. At PMC’s environmental safeguards staff include an Environmental Specialist Consultant located centrally in , and will be responsible for all safeguard tasks, and he/she is supported by an Environmental Engineer in each PIU. At the time of submission of this IEE, Environmental Specialist at Bhopal has been appointed in PMC, but Environmental Engineer is not appointed in PIU PMC - Gwalior. Environmental engineer is likely to appointed by PMC at the earliest. Contractor personnel will include an Environment, Health and Safety (EHS) supervisor.

29. Monitoring and Reporting. The PMU and PMC will be responsible for monitoring. The PMC will submit quarterly and semi-annual monitoring reports to PMU, and the PMU will review and send the semi-annual monitoring reports to ADB. ADB will post the environmental monitoring reports on its website.

30. Conclusions and Recommendations: The proposed project is therefore unlikely to cause significant adverse impacts. The potential impacts that are associated with design, construction and operation can be mitigated to standard levels without difficulty through proper engineering design and the incorporation or application of recommended mitigation measures and procedures. As per ADB SPS, the project is classified as environmental category B and does not require further environmental impact assessment. However, for Isagarh town, a groundwater sustainability plan should be prepared through a detailed groundwater study, and the measures of which are to be incorporated into the project to ensure the project sustainability. Project will require following government permission/approvals: (i) permission of WRD, GoMP for water abstraction for Karera, Pichhore, Aron, Bairad and Vijaypur (ii) consent for construction of WTP in government land and establishment and consent for operation for WTP from Madhya Pradesh Pollution Control Board. These permissions/approvals shall be obtained prior to invitation of bids (iv) For Isagarh a groundwater sustainability plan should be prepared through a detailed groundwater study, and the measures of which are to be incorporated into the project to ensure the project sustainability.

31. This IEE will be updated during the detailed design stage by the DBO contractor to reflect any changes, amendments and will be reviewed and approved by PMU.

II. INTRODUCTION

A. Background 1. Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as ‘the Project’. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Environment Department (UDED) shall be the executing agency for the Project.

2. The Project components are as follows:

(i) Component 1: Improvements to water supply and sewerage services in identified towns ➢ Continuous, pressurized, safe and sustainable drinking water through private household metered connections to 350,000 households with about 1.7million population resident in sixty-four towns in the State of Madhya Pradesh in Central India; and ➢ Sewage and storm water collection and treatment services proposed initially in two (2) identified towns (Khajuraho and Rajnagar) servicing about 42,000 population resident in 8000 households;

(ii) Component 2: Institutional Strengthening ➢ Capacity Building of implementing agencies (IAs), participating Urban Local Bodies (ULBs) and service utilities in contract management and service delivery for ensuring long term sustainability of services; ➢ Setting up of geographic information system (GIS) based water and sanitation asset management and service delivery monitoring; and ➢ Structured behavioral change campaigns to ensure the improvement in public health and cost recovery of service delivery.

(iii) Component 3: Project Management and Administration Support. This component will support the smooth and effective implementation and operation of the Project which includes expert support in Project design and implementation (design, procurement and Contract and Project Management, safeguards etc.), and project administration through Executing and Implementing Agencies.

3. The key outcome envisaged from the project is “effective urban water service delivery model rolled out in selective urban clusters of the State with the objective of achieving the following performance indicators by the year 2022.

(i) Access to piped water supply coverage increased to 95% of the households from 33% in 2015 in 64 towns; (ii) Women's drudgery for fetching water reduced by 80% (from spending an average of 55 minutes in 2015 to 10 minutes); (iii) Coverage of households with access to improved sanitation systems increased to 80% from 30% in 2015; (iv) Wastewater collection and/or safe sanitation service coverage increased to at least 80% of the households from 0% in 2015 in two towns; (v) Incidence of water logging/flooding reduced to two incidents per annum in four towns; and (vi) Women access to functioning sanitation systems increased to 95% from 25% in 2015 (in poor settlements) in four towns

4. The key outputs envisaged from the project are:

(i) Output 1: Water supply infrastructure improved in 64 project towns and flood and sanitation infrastructure improved in two project towns with the following measurable indicators: ➢ Improved water supply capacity of 135 MLD installed in 64 towns; ➢ 4,000 km water supply networks installed in 64 towns; ➢ 350,000 households provided with metered house connections including 100 government schools; ➢ 8 MLD sewage or septage treatment plants constructed; and ➢ Installation of 120 km sewer and drainage mains and networks.

(ii) Output 2: Sustained urban infrastructure operation and management

➢ 23 performance-based contract (PBC) operation and maintenance (O&M) water supply contracts for 64 ULBs signed and operated; ➢ ULBs institute volumetric water charges for recovery of water service O&M costs ➢ ULBs’ water tariff collection ratio improved to 90% from 50% in 2014 based on the water meters’ readings ➢ 100% operating cost recovery (excluding debt service) achieved; ➢ GIS system established for effective O&M of water services

5. The subproject towns Karera, Pichhore and Bairad in , Aron in Guna District, Isagarh in Ashoknagar District and Vijaypur in Sheopur District under package 4D, the improvement of water supply in these six towns is one of the subprojects proposed under MPUSIP. The objectives of proposed Water Supply System are to supply safe wholesome water in adequate quantity at convenient points and at reasonable cost to the users. In order to encourage personal and household hygiene, proper planning is necessary in the formulation and implementation of scheme. The objectives of proposing new Scheme for town are: (i) Long term sustainability and equity of water service provision (ii) Maintaining a balance between supply and demand (iii) Financing the rehabilitation of existing infrastructure and expansion of new infrastructure (iv) Appropriate institutional structures to provide autonomy, accountability and incentives (v) Operations& Maintenance (O&M), Cost Recovery and tariffs (vi) Human resources, systems, and equipment capacity building for efficient working environment. B. Purpose of this IEE Report 6. ADB requires the consideration of environmental issues in all aspects of the Bank’s operations, and the requirements for environmental assessment are described in ADB‟s Safeguard Policy Statement (SPS), 2009. The potential environmental impacts of the subproject have been assessed using ADB Rapid Environmental Assessment Checklist for Water Supply (Appendix 1). Then potential negative impacts were identified in relation to pre-construction, construction and operation of the improved infrastructure, and results of the assessment show that the subproject is unlikely to cause significant adverse impacts. Thus, this initial environmental examination (IEE) has been prepared in accordance with ADB SPS‟s requirements for environment category B projects.

7. This IEE report is based on detailed engineering report prepared by DPR Consultants and will be finalized during implementation stage by DBO contractor to reflect any changes and latest subproject designs. The IEE was based mainly on field reconnaissance surveys and secondary sources of information. No field monitoring (environmental) survey was conductedhowever, the environmental monitoring program developed as part of the environmental management plan (EMP) will require the contractors to establish the baseline environmental conditions prior to commencement of civil works. The results will be reported as part of the environmental monitoring report and will be the basis to ensure no degradation will happen during subproject implementation. An Environment Management Plan (EMP) includes mitigation measures for significant environmental impacts during implementation of the projects. Stakeholder consultation was an integral part of the IEE.

C. Report Structure 8. This Report contains the following nine (9) sections: (i) Executive summary; (ii) Introduction (iii) Description of the project (iv) Policy, legal and administrative framework (v) Description of the environment; (vi) Anticipated environmental impacts and mitigation measures; (vii) Public consultation and information disclosure; (viii) Grievance redress mechanism; (ix) Environmental management plan, and, (x) Conclusion and recommendation

III. DESCRIPTION OF THE SUBPROJECT

A. Project Area 9. This report presents the proposed water supply scheme under Package 4D comprising Karera, Pichhore, Aron, Bairad, Isagarh and Vijaypur towns. The distance between all the towns is around 50 to 150kms from each other.

10. Karera Town: Project area comprises of the urban area and surroundings of the Karera Municipal Boundary in Shivpuri District. Karera Town lies at a distance of about 85 km from Shivpuri and 60 km from Bhopal, in the heart of the Madhya Pradesh state. The Town serves as a Nagar Parishad in the Shivpuri district. The road network also shows organic growth with the linking road from NH-25 being the main road which has emerged as the main commercial spine of the town. The total area of town is 12 Sq Kms and population as per 2011 census is 28705.

11. Pichhore town is 77km from its district head quarter, Shivpuri. The road network also shows organic growth with the linking road from NH-25 being the main road which has emerged as the main commercial spine of the town. The only connectivity to Pichhore city is a road connecting which is approximately 25.6km long from NH-25. Nearest railway station is Basi which is 30 km from Pichhore and nearest airport is Gwalior. The area of Pichhore is 8 sq km and population as per 2011 census is 18127.

12. Aron Town lies at a distance of about 32km from Guna and 180 km from Bhopal. The Town serves as a Nagar Parishad in the Guna district. Aron is connected to the district via State Highway 23 which passes through the Aron and other major districts roads. Nearest railway station and airport is located at Guna which is 32 Km from Aron town. The total area of town is 20.10 Sq Kms and population as per 2011 census is 28010.

13. Bairad is town situated in Pohri Tehsil of Shivpuri district. It is located 57 KM towards North from District head quarters Shivpuri. 24 KM from Pohari. 318 KM from State capital Bhopal. It is recently declared as town i.e. in 07th January, 2015 and designated at Bairad Nagar Parishad from the village panchayat. Total population of the town as per 2011 census is 18313.There are total 15 wards with area under BNP jurisdiction is 27 sqkm.

14. Vijaypur is a Nagar Parishad in the Sheopur district of Madhya Pradesh. Vijaypur town is located 141 km away from district centre Sheopur. Total population of the town as per 2011 census is 16,964. Total area under Vijaypur jurisdiction is 3 sqkm with 15 nos of wards.

15. Isagarh: Project area comprises the urban area and surroundings of Isagarh Nagar Panchayat in Ashoknagar District, in central part of Madhya Pradesh State. Isagarh has a population of12583 (2011 census) and has a geographical area of 18sq. km. Isagarh is situated on SH - 10 connecting Gahora- Ashok Nagar. The nearest railway station is Ashok Nagar which is 35 km from the town. Isagarh is 33.7 km far from its District Main City Ashok Nagar. It is 182 km far from its State Main City Bhopal.

Figure 1: Location of Project area

Vijaypur

B. Existing Water Supply Situation

1. Karera Town 16. Presently water supply in Karera town depends upon surface source and ground water source. Major water supply of the town is done by surface source. Mahuar River and Dumghana dam are the major surface source available in the town. WTP of capacity 1.5 MLD is available in the town. Water from Dumghana dam is been came to Intake structure near Khairaghat near Military area then water is being pumped to WTP near highway.

17. Also there is an Intake well on Mahuar River from which water is also been pumped to WTP. Then water is pumped to 2 OHTs in the town, one at Nagar Parishad and another at Krishi Mandi. Water distribution system of ACP/PVC of approximate length 10km is laid in the town. The distribution in the town is laid in very haphazard manner which increases the water losses by 42%.

18. Present water supply arrangements are not adequate and ground water source level is depleting day by day, therefore water scarcity conditions are arising. Water supply losses during transmission are also very high i.e. more than42%, that leads to a high energy consumption and loss of ULB.

2. PICHHORE 19. Presently water supply system in Pichhore is based on ground water (6 Tube wells & 141 Hand pumps) as well as surface water. Presently only 40 LPCD water is being supplied to the town which is very less as per the norms of CPHEEO Manual. Since the water supply, distribution system is laid in parts and haphazard manner, which causes water supply losses at the rate of 40%. As per the Service Level Benchmarking (2008) of GoI, it is mandatory to supply 135 LPCD of treated (quality) water to the 100% population of town.

20. Water from all these ground water is pumped directly to town while the water from Futiwar dam is supplied to 400KL MBR near WTP. From the 400KL MBR water is been supplied to one Open well and to GSR near school. From open well water is being pumped to 200KL GSR behind Nagar Parishad and from sumpwell near school water is been pumped to another 200 KL GSR at Hazira Pahadi. Water supply distribution system is laid of diameters 63 / 75 / 100 / 150 mm PVC pipes. Total 18 Km water supply distribution system is laid in the Pichhore town. Thus total water supply to the Pichhore town made is 0.80 MLD i.e. 40 LPCD, which is below the guidelines given, as it should be 70 LPCD for town with population below 30000.

3. ARON 21. Presently water supply in Aron town depends upon ground water source. Major water supply of the town is done by Ground water. There are 29 Tube wells and 51 hand pump present in the town. From the tube wells water is pumped to 3 no. of OHTs in the town. From these OHTs water is distributed to whole town.

4. BAIRAD 22. Water supply in Bairad, responsibility of Nagar Parishad, is primarily dependent on sub- surface water sources. At present, water is drawn from 7 municipal tube wells located across the city. Apart from tube wells, town has 10 nos of hand pumps located at various locations as one of the source of water supply. Water is drawn from 07 municipal tube wells located across the town. the size of the tube wells is 6” diameter with depth of 600 ft. Ground water is available at 500ft. Tube wells are having submersible pumps with capacity of 15 HP each. Therefore, there is no water storage facility in the town. Water supply is facilitated directly from tube wells to the distribution system. At present Bairad town doesn’t have any water treatment plant.

23. At present, town is having two OHSR under its jurisdiction. OHSR is located in ward no 5 and was built in the year 1970. Hence it has become old and in dilapidated and can’t be used for the supply purpose. Other OHSR was built in year 1990; having capacity of 1.0 Lac liter &It is located in ward no.9. It covers an area under wards 8, 9 and 11.

24. The distribution system of Bairad town is very old with limited coverage. BNP has 5 km of distribution network of piped water supply. The material of pipe is in the form of GI pipe with size of 3” in diameter. It covers areas under Ward No. 5,7,8,9 and 11. BNP has two water tankers. In some of the area’s water supply is being done by water tankers. Presently the water tax is collecting in town at the rate of Rs.30/- per connection per month for domestic connections.

5. VIJAYPUR 25. Water supply in Vijaypur is primarily dependent on sub-surface water sources. At present, water is drawn from 22 municipal tube wells having sizes of 6” and 7” diameter, with yield of 10 to 15 KL/hour located across the town. Besides bore wells, water is extracted through 65 hand pumps (for daily usage) located across the city. At present there are 2 Over Head Tanks (OHTs) and One Sump for storage with a total capacity of 50000 gallons & 75000 gallons exist in the town. In the areas having OHT, water is supplied busing OHT as well as using bore wells. In rest of the wards, the tube wells are directly connected to the system without any storage or treatment. These results in uneven pressure across the network and some of the localities across the town have reported low pressure of water supply.

26. The entire Vijaypur being supplied from ground water source. The present distribution system was laid in 1974 and thereafter it was increased based on requirement and demand. These pipelines are old and dilapidated and need to be replaced. At present the town has around 4 Km length of distribution system of AC, GI pipes having 3 inch (80-90%) & 2 inch (10%) diameters. At present, the water supply is 0.85 MLD (after deducting losses & inadequacy). The water supply is approximately 50 lpcd which is low as per standards. At present water is being supplying from tube wells Vijaypur town doesn’t have any water treatment plant. The water from wells is directly supplied to the households through OHSRs. In 1974, VNP has constructed surface water based scheme with slow sand filter having a capacity of 200KL per day. However due lack of maintenance the system was abandoned. Presently the water tax is being collected in town at the rate of Rs.30/- per connection per month for domestic connections. There are total 1600 numbers of connections for water supply.

6. ISAGARH 27. In present situation most of the residents of the town obtain their water from an improved point source, such as a well or tube well. The water drawn from the tube wells is directly pumped to the existing tank and from tank distributed to the Nagar Parishad after initial disinfection. At present 0.9 MLD of water is being supplied in the Nagar Parishad from 16 tube wells functioning well in the Nagar Parishad. The quality of water is acceptable limit of IS-10500 for drinking purposed. The physico-Chemical characteristics of the analyzed water sample are well within the desirable standard limit.

28. The existing water supply pipe networks coverage is around 60%. From the collected Existing water supply map from ULB, it is reveal that from 12” dia to 3” dia AC pipes & PVC pipes are used in entire distribution networks section which is of around 15-year-old age. There are 16 Nos Tubewells, 3 Watertank, 60 Handpumps and 1 water tanker present in the town. As per the guide line AC pipes is no longer to be used for water supply project. Hence existing networks not incorporated &proposed in this DPR. There is no water treatment plant facility available in the Nagar Parishad area. Presently only primary informal treatment is being done at the source level (i.e. at the tube well points). In view of ensuring health safety of Nagar Parishad efforts must be made to ensure proper treatment of water to achieve drinking water standards. There is no water treatment plant facility available in the Nagar Parishad area. Presently only primary informal treatment is being done at the source level (i.e. at the tube well points). In view of ensuring health safety of Nagar Parishad efforts must be made to ensure proper treatment of water to achieve drinking water standards.

29. Overall, the current water supply systems in all these six towns suffer from unreliable sources, low coverage, inadequate storage, poor network efficiency, low management capability and heavy water losses.

C. Proposed Project 30. Proposed project Components: As part of this project, it is proposed to develop comprehensive water supply schemes in each of the six project towns. Proposals include new water sources, treatment facilities, storage reservoirs, pumping, transmission and distribution infrastructure. Project will also provide consumer connections with flow meters. Bulk flow meters are proposed at strategic locations to monitor the system performance efficiency.

31. Water Source: An alternative source analysis has been conducted to select a feasible and sustainable source of water supply to meet the ultimate design demand. Except Isagarh, surface water is taken as source for the proposed schemes in the five project towns. In case of ground water source for Isagarh, existing 16 tube wells are adopted as source for the systemand pumping into sumps, disinfection with chlorine, pumping to overhead tanks, and distribution from OHTs. In case of surface water source, it is proposed to withdraw water by intake constructed in the bed of the river/dams. From intake raw water is proposed to pump to WTP through raw water rising mains for the treatment. From WTP, the treated water is directly pumped to each OHSR in every water distribution zone of the town.

32. Following Table 1 shows the proposed water supply systems along with nature and size of components in six subproject towns. Figure 2 to Figure 22 show the proposed water systems, component layouts etc.

Table 1: Proposed Water Supply Subproject Components under Package- 4D S. No. Particulars Karera Pichhore Aron Bairad Vijaypur Isagarh I. Water Demand 1. Base year (2018) 5.40 MLD 1.8 MLD 2.7 MLD 1.75 MLD 1.61 MLD 1.14 MLD 2. Intermediate year 6.90 MLD 2.3 MLD 3.4 MLD 2.33 MLD 2.01 MLD 1.41 MLD (2033) 3. Design year 8.30 MLD 2.9 MLD 4.1 MLD 2.91 MLD 2.41 MLD 1.68 MLD (2048) II. Source 1. Alternatives 1. Ground Water 1. Ground Water 1. Ground water 1. Pachipura Kunwari River Existing source- 2. Existing source – 2. Futiwar Dam 2. Sindh River Dam (Existing Weir Ground water Samoha Dam 3. Nagada Dam 2. Bairad Talab recently 3. Dumghana Dam Constructed by WRD) 2. Selected source Samoha Dam at Jhadla Futiwar Dam Sindh River Pachipura Kunwari River Taking into Village Dam (Existing Weir consideration that Futiwar Dam of WRD is Sindh River is Constructed by there is no Samoha Damis situated in constructed in 1979 in situatedinGunaDis Pachipuradam WRD) at a dependable Pichhore, Dist - is situated at a distance of 1.7 surface water Shivpuri District 13.5 km trict9km away Shivpuri. It is around 4 distance of 5km km from source in the away from Karera town. from the Aron Samoha Dam is major Km from the town. from the town. Vijaypur town proximity of the town. irrigation project and Water supply scheme town (about 30 serves as a life line to the of capacity 1 MLD km), it is proposed nearby area. based on Futiwar dam to continue the has also been groundwater sanctioned in the year source from 16 1984 in the town. At Nos.of existing present some amount tube wells for of water i.e. 0.2 – 0.4 Isagarh water MLD water is been supply. supplied to the town. III. Proposed system 1. From source to Raw water abstraction Raw water abstraction Raw water Raw water Raw water It is proposed to consumer supply from Samoha Dam → from Futiwar Dam → abstraction from abstraction from abstraction from develop a raw water transmission raw water transmission Sindh River → raw Pachipura Proposed stop groundwater (pumping) → treatment (pumping)→ treatment water transmission dam/Intake - dam based water → clear water → clear water (pumping) → Raw Water constructed by supply system transmission (pumping) transmission → treatment→ clear Rising Main - WRD-Intake - consists of → storage → distribution storage → distribution water transmission WTP - Clear Raw Water abstraction of → house connections → house connections & (pumping) → Water Rising Rising Main - groundwater from with meters meters storage→ Main - OHTs - WTP - Clear 16 existing tube distribution → Distribution Water Rising wells and house connections System - Main - OHTs - pumping into with meters. Household Distribution sumps, Connection System - disinfection with Household chlorine, pumping Connection to overhead tanks, and distribution from OHTs. IV. Proposed Components 1. Water intake Water will be extracted Existing Jack Well: Water will be Water will be To withdraw Proposed two from the Samoha dam Water will be extracted from the extracted from water from the Clear Water river Kunwari Sumps of 1.60 LL which is constructed abstracted from Futiwar Sindh River by the reservoir across Mahuwar River by dam by existing jack construction of and to pump and 1.80 LL and to pump construction of intake well well. intake well of dia raw water. capacity with of dia 6.0m and height 6.0m and height raw water. Intake well of chlorinator Plant; 11.5. Approach bridge of 20.0 Approach Intake well of 4.5 m dia, 13 m height. length 100m is also bridge of length 5m dia, 11.36m propsed. Intake location 50m is also Location: In height.Pumps 2 comes under Eco- proposed. A weir the bed of sensitive zone of Karera of length 50m and nos (1 working Kunwari River wildlife sanctuary about height 5m is also + 1 standby) of near (Existing weir 500 m away from the proposed to store total 19 Kw. boundary of Karera the water in Sindh constructed by Location: In wildlife sanctuary. River. WRD), The land the bed of belongs to Note: - As per DPR, WRD, Govt of source of water for Pachipura MP. subproject water supply dam/reservoir,T town Karera was he land belongs proposed on western to WRD, Govt. bank of Samoha dam located at Jhanda village. Later on, it was come under notice that proposed location of water source as well as alignment of raw water rising main is likely to come under Son Chiraiya Bird Sanctuary, Karera which is about 14 Kms. away from subproject town and secondly proposed alignment passes through private land too. Taking into consideration, a joint visit of DBO Contractor, PMU- Gwalior along with PMC was scheduled on January 24th 2018 to resolve this issue and new location has been identified and recommended. Location: New Recommended & proposed location is on eastern bank of Samoha dam in River Mahuar at Village Khera Modi. 2. Raw water Pump house open top of VT Pumps Pump sets - Pump house open VT Pumps 2 Pumps 2 nos (1 Pump water from pumping station intake well 2 nos. (discharge27.78 top of intake well nos. (1 working working + 1 ground level VT pump sets -2 nos. LPS, head 41 m, and VT pump sets - 2 + 1 standby) of standby) of total reservoir to (discharge 83.33 LPS, Motor 25 HP) nos. (discharge total 19 14 overhead head 71 m, and Motor Land owned by GoMP 41.06 LPS, head Kw.(discharge Kw.(discharge reservoir Pumping 120 HP) (WRD) 72 m, and Motor 29.5 LPS, 25.4 LPS, head- Machinery at 60 HP) head- 26.3 m, 22.2 m, and Tube Wells: 5 Land owned by GoMP and Motor 13 Motor 10 HP) Nos. Working VT (WRD) Land owned by HP) Pumps –10 HP, GoMP (WRD) Location:Near 3.33 LPS Intake well at Location: At discharge and the above intake well In 100.0 M head mentioned Kunwari River, Pumping location. The At the above Machinery at land belongs to mentioned Proposed CWS at WRD, Govt of location. The Ward-12 (Zone- MP. land belongs to 1): 8.79 LPS WRD, Govt. of discharge and MP 32.0m head ( Working =1.0 Nos. & Standby =1.0 Nos. ) and Pumping Machinery at Proposed CWS at Ward-2 (Zone-2), 9.0 LPS discharge and 33.0 M head ( Working =1.0 Nos. & Standby =1.0 Nos.) 3. Raw water 13500 m length - 350 mm 3250 m length - 200 8680 m length - 790m length, To transport Rising Main from transmission dia DI pipe. mm dia DI pipe 250 mm dia DI 250mm dia. raw water from all Tube Well to From Intake to intake well to Proposed CWS From intake to WTP; From raw water pump pipe WTP WTP. (Zone-1 & Zone- RWRM will be laid under house to the WTP site; From intake to Pipeline will be 300m length, 2) is 3887 m ground along existing the pipe will be laid WTP; along Aron laid 200mm dia. Of length 80 mm PWD road known as along Pichhore road Road within the – underground to DI K-9 Pipe. DI-K9 pipe Karera Road within the within RoW. RoW; “ ” WTP site along Location: RoW; no encroachment the existing Pipeline will be into the adjacent forest road within laid boundary. The raw water ROW. underground to rising main, connecting WTP site along intake and WTP, will be main road partly outside and partly within ROW. within the towns, which will be laid partly within the ecosensitive zone boundary and partly outside the ESZ boundary of Karera birds sanctuary. 4. WTP Capacity:5.7 MLD Capacity:3.0 MLD Capacity: 4.5 Capacity:2.91 Capacity:2.65 Chlorination units MLD MLD MLD 2 nos. Clear water sumps and Process/components (same for all five towns): Coagulation &flocculation, sedimentation, rapid gravity filtration, chlorination, wash water recovery, sludge drying beds, tube settlers &miscellaneous infra (compound Electronically wall, landscaping, lighting, rest rooms, approach road etc) controlled chlorination units producing chlorine from common salt Location: On a Location: On a Location: On a Location: In the Location: WTP Chlorination units government land (owned government owned government land bed of land is located will be located in a by Revenure department, vacant land (2.0 ha) (owned by Pachipura near old pump small room at GoMP) of 2.55 ha at Behind MPEB Revenue dam/reservoir, house near sumps (ground Kunwari River. Existing WTP campus. substation near department, The land level reservoirs).

Proposed WTP comes Warehouse ward no. GoMP) on Barod belongs to Location: These Required land within the boundary of 13 road WRD, Govt of are government is 2 Acre; land Eco-Sensitive Zone of MP. owned lands, and is owned by Karera wildlife Sanctuary are currently ULB. about 500 m away from vacant

the boundary of Karera At present the wildlife sanctuary. WTP land is vacant. will be constructed within the limit of Karera municipal urban area. 5. Clear water Pump house within WTP. Pump house within Pump house within Pump room of To store Pumping pumping station Centrifugal pumps-4 nos. WTP. WTP. 6m diameter treated water Machinery at (2 no. of 50 HP of Centrifugal pumps -4 Centrifugal pumps- and 4.5m height and to build up Proposed CWS at (discharge 56.89 LPS, nos. (2 no. of 10HP of 2 nos. (1W+1S)- mounted on adequate Ward-12 (Zone- head-46 m) (discharge 12.39 LPS, (35 HP) of Sump of 90 KL pressure to 1): 8.79 LPS and 2 no. of 20 HP) of head-31 m) and 2 no. (discharge 39.01 Capacity. pump to OHTs. discharge and (discharge 22.27 LPS, of 12.5 HP) of LPS, head-46 m) Submersible Pump room of 32.0m head head-43.5 m), (discharge 13.99 LPS, Pumps 4 nos. 5m diameter (Working =1.0 head-45 m) (2working + 2 and 4.5m Nos.& Standby standby) of total height mounted =1.0 Nos. ). 30 Kw. on Sump 75 KL Submersible Capacity. Pumping pumps (2 no. of Pumps 2 nos. Machinery at 15HP of (1 working + 1 Proposed CWS at (discharge 21.4 standby) of Ward-2 (Zone-2), LPS, head- total 22.20 Kw. 9.0 LPS discharge 43.70 m) and 2 (discharge 25.4 and 33.0 M head no. of 5.0 HP) of LPS, head-35.6 ( Working =1.0 (discharge 8.1 m, and Motor Nos. & Standby LPS, head- 15 HP) =1.0 Nos.) 30.40m) Location: Near Proposed WTP as described above. 6. Clear water 4725 m – 100 to 250 mm 2550 m – 100 to 150 Total length of 4.88km length For Water Feeder main of transmission dia DI K9 pipe mm dia DI pipe 2550m DI pipe with 150 and transmission 3989 m length; from WTP to Rising Main from Alignment from the 200mm clear water sump diameters of DI- three OHSRs all Tube Well to 850m - 250 mm dia DI 2350m - 200 mm dia (at WTP) to the 2 K9 pipes 3.72 Km length Proposed CWS pipe , 200 m - 100 mm dia with 150, 200 (Zone-1 & Zone-2) OHTs, along the Water 3730m 200mm dia, and 250 mm is 3887 m length – main roads of dia transmission – diameter of DI 80 mm dia DI-K9 70m – 100mmdia and; From the clear water 150mm/ 200mm/ from WTP to K-9 pipe. pipe 250mm. three OHSRs 75m – 150mm dia DI sump (at WTP) to

pipe service reservoirs Location:

Alignment from the clear 350m - 250 mm Transmission Transmission Rising Main from Location: along the water sump (at WTP) to dia main from WTP Proposed CWS to public roads within pipelines will be the 4 OHTs, along the 1100 m - 200 mm to OHSRs will Existing OHT RoW will be laid mostly laid along main roads. dia be laid Ward-12 (Zone-1) underground. the main roads. The clear water rising 1100 m - 100 mm underground is 51 m length – main, connecting WTP dia Pipes will be laid along the 150 mm dia DI-K9 and OHTs, will be existing road. pipe underground. essentially laid within the town along an existing Rising Main from road within ROW. Clear Proposed CWS to water rising main will be Existing OHT laid within the boundary of Ward-2 (Zone-2) is eco-sensitive zone of 51 m length – 150 Karera bird sanctuary mm dia DI-K9 pipe. within ULB limit. Water transmission from tube wells to GLSRs to OHTs, and from OHTs to distribution network for supply to consumers

7. OHTs and Proposed OHT- 3 Nos. Proposed GSR – 2 Proposed OHT- 1 Proposed OHT- Proposed OHT- Existing OHT – 2 OHT 1 1000 KL near No. 2 Nos. Nos. each 500 KL GLSR – Nos. 3 Nos. in Zone PWD rest house OHT II 700 KL in OHT I 325 KL in Ward -12 (Zone 1. GSR I 200 KL at – 1, 2 & 3. – OHT 2 700 KL near – Ward No. 1 at old OHT site 1) and in Ward-2 ( – OHT 1 300 KL Nagar Parishad Office Hazira Pahadi, Existing OHT- 1 – in Ward No. 6 Zone 2) in ward no. 5 for OHT 3 500 KL near Kirsi Ward No. 13 No. – zone 1 Mandi OHT I – 500 KL OHT 2 – 240 KL 2. GSR III 200 KL at – near ULB office Kali Mata Mandir, Existing OHT – 1 No. OHT OHT 2 – 300 KL in Ward No. 12 4 - 200 KL Near Kirshi Ward No. 4 in ward no. 9 for Mandi. zone 2 Existing OHT- 1

No. of 340 KL All the OHTs site comes Existing GSR 2 Nos. capacity in ward – OHT 3 225 KL under Eco-Sensitive Zone – no. 15. 3. GSR II – 200 KL at in ward no. 15 of Karera wildlife sanctuary Hazira Pahadi, for zone 3 at a distance of around 1 Ward No. 13 km to 2 km from the boundary of Karera wildlife 4. GSR IV – 250 KL at sanctuary. Kali Mata Mandir, Ward No. 4

8. Distribution 52.8 km – 90 mm to 250 33.125 km -75 mm to 20559 m – 75 mm 89,177 m- For distribution Distribution network mm dia HDPE pipes and 280 mm dia of HDPE to 280mm dia of 75mm to 280 of water to Network of 22190 above 300 mm &400 mm pipe and 300mm – 315 HDPE pipes and mm dia of HDPE public. m length and 75 dia Di-K7 pipes mm of DI-K7 pipe 300 mm to 315 pipes and above mm to 315 mm Location: Along the Distribution Location: Along the mm dia of DI-K7 300mm dia of dia HDPE pipes public roads in the network of public roads in the entire pipes. DI-K7 pipes. entire town. 31097m length town. Location: Along Location: Along and 75 mm to the public roads in the public roads Dia of Length 280mm dia of the entire town. in the entire Pipe (m) HDPE pipes town.

(mm) Dia of Length Dia of Length Dia of Length Dia of Length Pipe (m) Pipe (m) Dia of Length Pipe (m) Pipe (m) 90 234 (mm) (mm) Pipe (m) (mm) (mm) 75 21126 75 12916 (mm) 75 20832 110 25183 90 1846 90 1425 75 60953 90 3849 75 10547 110 1816 110 1853 110 1880 90 2444 140 17001 140 3478 140 2041 90 9430 125 1892 110 2835 160 1574 160 339 110 5555 140 520 125 1205 160 1241 180 484 180 500 160 659 125 5275 140 2801 200 895 200 415 200 873 140 2938 160 657 180 1625 250 1579 250 349 225 221 160 943 180 518 280 63 280 228 250 148 200 590 180 620 200 913 300 90 300 224 280 192 225 247 315 174 315 269 200 491 Total 31099 250 98 225 247 Total 33125 Total 20559 225 1794 280 20 250 520 315 228 250 3679 Distribution network will Distribution 280 634 Distribution Total 22190 cover entire town, in network will cover 300 25 network will 300 2665 narrow roads, where entire town, in Total 89178 cover entire there is no place, the narrow roads, town, in narrow Pipes will be laid 400 263 pipeline will be laid where there is no roads, where underground within the tarmac. place, the pipeline Distribution there is no Total 52799 along the public will be laid within network will place, the roads, and public the tarmac. cover entire pipeline will be lands. Distribution network will town, in narrow laid within the Distribution cover entire town, in roads, where tarmac. narrow roads, where there is no network will cover there is no place, the place, the entire town, in pipeline will be laid within pipeline will be narrow roads, the tarmac. laid within the where there is no Most part of distribution tarmac. place, the pipeline network will be laid within the boundary of will be laid within ecosensitive zone of the the tarmac. Karera wildlife sanctuary Existing old pipes within municipal limit. will be left as it is in the ground untouched. 9. Bulk flow meters Will be installed as per Will be installed as per Will be installed as Will be installed For Fixed at strategic requirement; requirement; per requirement; as per measurement locations in at of quantity of source, OHTs, requirement; water. GLSRs, DMA

Fixed at strategic Fixed at strategic Fixed at strategic 8 Nos. inlets etc., bulk locations at source, locations at source, locations at Fixed at Location: meters will be OHTs, GLSR, DMA inlets OHTs, GLSR, DMA source, OHTs, strategic Intake, At WTP fixed with the pipe etc., bulk meters will be inlets etc., bulk meters GLSR, DMA inlets locations at on Delivery section fixed with the pipe section will be fixed with the etc., bulk meters source, OHTs, pipe of Clear pipe section will be fixed with GLSR, DMA Water, Feeder the pipe section inlets etc., bulk mains to OHTs, meters will be Delivery pipes fixed with the of OHTs, bulk pipe section meters will be fixed with the pipe section. 10. Consumer 6213 nos. – at each 4053 nos. – at each 5824 nos. – at 3400 nos. - at 3,030 nos. at 3554 Nos. at connects with house in the town house in the town each house in the each house in each house in each house in meters Water delivery pipe Water delivery pipe town. the town. the town. the town. (MPDE of dia 20 - 25 mm) (MPDE of dia 20 - 25 Water delivery Water delivery Water delivery Water delivery will be connected to mm) will be connected pipe (MPDE of dia pipe (MPDE of pipe (MPDE of pipe (MPDE of dia distribution lines and to distribution lines and 20 - 25 mm) will be dia 20 - 25 mm) dia 20 - 25 20 - 25 mm) will meters will be attached to meters will be attached connected to will be mm) will be be connected to the delivery pipe at each to the delivery pipe at distribution lines connected to connected to distribution lines house with a meter each house with a and meters will be distribution lines distribution and meters will be chamber meter chamber attached to the and meters will lines and attached to the delivery pipe at be attached to meters will be delivery pipe at each house with a the delivery pipe attached to the each house with a meter chamber at each house delivery pipe at meter chamber with a meter each house chamber with a meter chamber

33. Construction Works. Civil works in the project include linear excavation for laying pipes along the roads, placing pipes in the trench and refilling with the excavated soil. The trenches will be of 0.4 m – 0.7 m wide and 0.8 to 1 m depth. Subsequent to completion of works, road reinstatement will be undertaken by the contractor as part of the civil works. The roads in the core city area of the town is very narrow and congested with pedestrians and vehicles, while the roads in outer areas are wide. Other civil works in the subproject include construction of intake well, water treatment plant, water tanks, pumping stations, at the identified sites. These works will be confined to sites, and construction will include general activities like excavation for foundation, construction of foundations, columns, walls and roof in cement concrete and masonry, and fixing of mechanical and electrical fixtures, etc. Intake well cum pump house will involve construction within the water body. A temporary enclosed area (about 10 m dia) will be created using appropriate material and the water will be pumped out to make the area dry for construction. Once this is created, the rest of the construction will follow the general construction procedures to create a RCC well of size 6 m diameter. Once the work is over, the temporary structure will be removed.

34. Project benefits. The subproject aims to achieve safe and sustainable water services both in terms of services to customers, cost recovery and conservation of precious water resources. The subproject will provide continuous, pressurized and safe drinking water services to entire population of the towns (100% coverage). Besides achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency, the subproject will improve the overall environmental quality of the town. It will reduce the reduced time and costs of households in accessing alternative sources of water, and will lead to better public health particularly reduction in waterborne and infectious diseases.

D. Implementation Schedule

35. After the approval of the detailed project report, bid were prepared and tender has been invited and the contract has been awarded by to DBO Contractor “Rean Watertech” 10th August 2017. Stipulated date of completion is 8th December 2019.

Figure 2: Site Photograph Showing Recommended and Proposed New Location of Intake Well on Eastern Bank of Samoha Dam across Mahuar River at Village Khera Modi for Karera Town WSS after Joint Visit by PMC, PIU PMU/PMC & DBO Contractor on 24th January 2018 Figure 3: Proposed Water Supply Scheme & RWRM of Karera Town

Figure 4: Layout Plan of WTP – Karera Town

Figure 5:Schematic Diagram of Head work/Intake WellShowing All Arrangement- KareraTown

Figure 6: Pichhore Water Supply Scheme Showing Proposed Subproject Components

Figure 7: Layout Plan of Proposed WTP – Pichhore Town

Wash Water Tank

Sludge Drying Beds

Figure 8: Aron WSS Showing Subproject Components

Figure 9: Google Earth Map Showing Proposed Water Supply Subproject Components and Transmission System (Aron Town)

Figure 10 : Proposed Weir Details – Cross-Section and Elevation in Sindh River for Aron Town

Figure 11:Typical Cross section and Plan with and without gate for Anicut on Sindh River– Aron town WSS

Figure 12: Typical Cross-Section of Anicut – Aron Town WSS

Figure 13: Details of Intake Well Arrangement in Sindh River for Aron Town

Figure 14: Layout Plan of WTP Aron Town

Washwater Tank& Rcycling

Sludge Drying Beds

Figure 15: Proposed Water Supply Zones and Transmission System –Bairad

Figure 16: Proposed Intake Well Arrangement at Pachipura Dam for Bairad Town

Figure 17: Layout Plan of WTP Bairad Town

Figure 18: Proposed Water Supply Zones and Transmission System– Vijaypur

Figure 19: Plan and Section of Intake – Vijaypur

Figure 20: Intake Arrangement – Vijaypur

Figure 21: Layout Plan of Proposed WTP- Vijaypur

Figure 22: Proposed Water Supply Zones and Transmission System –Isagarh Town

IV. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK

A. ADB Policy 36. ADB requires the consideration of environmental issues in all aspects of ADB’s operations, and the requirements for environmental assessment are described in ADB SPS, 2009. This states that ADB requires environmental assessment of all ADB investments.

37. Screening and categorization. The nature of the environmental assessment required for a project depends on the significance of its environmental impacts, which are related to the type and location of the project; the sensitivity, scale, nature, and magnitude of its potential impacts; and the availability of cost-effective mitigation measures. Projects are screened for their expected environmental impacts, and are assigned to one of the following four categories:

(i) Category A. Projects could have significant adverse environmental impacts. An EIA is required to address significant impacts. (ii) Category B. Projects could have some adverse environmental impacts, but of lesser degree or significance than those in category A. An IEE is required to determine whether significant environmental impacts warranting an EIA are likely. If an EIA is not needed, the IEE is regarded as the final environmental assessment report. (iii) Category C. Projects are unlikely to have adverse environmental impacts. No EIA or IEE is required, although environmental implications are reviewed. (iv) Category FI. Projects involve a credit line through a financial intermediary or an equity investment in a financial intermediary. The financial intermediary must apply an environmental management system, unless all projects will result in insignificant impacts.

38. Environmental management plan. An EMP, which addresses the potential impacts and risks identified by the environmental assessment, shall be prepared. The level of detail and complexity of the EMP and the priority of the identified measures and actions will be commensurate with the project’s impact and risks.

39. Public disclosure. ADB will post the safeguard documents on its website as well as disclose relevant information in accessible manner in local communities:

(i) for environmental category A projects, draft EIA report at least 120 days before Board consideration; (ii) final or updated EIA and/or IEE upon receipt; and (iii) environmental monitoring reports submitted by the implementing agency during project implementation upon receipt.

B. National Environmental Laws 40. Environmental assessment. The GoI EIA Notification of 2006 (replacing the EIA Notification of 1994), sets out the requirement for Environmental Assessment in India. This states that Environmental Clearance (EC) is required for specified activities/projects, and ECmust be obtained before any construction work or land preparation (except land acquisition) may commence. Projects are categorized as A or B1 or B2 depending on the scale of the project and the nature of its impacts.

41. None of the components of this water supply subproject falls under the ambit of the EIA Notification 2006, and, therefore no category assigned, and thus no EIA study and EC required for the subproject

42. Applicable Environmental Regulations. Besides EIA Notification 2006, there are various other acts, rules, policies and regulations currently in force in India that deal with environmental issues that could apply to infrastructure development. The specific regulatory compliance requirements of the subproject are shown in Table 2.

Table 2: Applicable Environmental Regulations Law Description Requirement The EIA notification, 2006 This states that Environmental Not applicable. (and its subsequent Clearance (EC) is required for amendments in 2009) specified activities/projects, The sub-project is not included in provides for categorization of and this must be obtained schedule of environmental impact projects into category A and before any construction work assessment notification 2006 and B, based on extent of impact or land preparation (except its subsequent amendments till land acquisition) may date, so it is not categories as commence. Projects are either Category A or Category B. categorized as A or B As a result, environmental depending on the scale of the clearance is not required, either project and the nature of its from the state or the central impacts. Categories A projects Government. require Environmental Clearance from the National Ministry of Environment and Forests (MoEF). Category B projects require environmental clearance from the State Environment Impact Assessment Authority (SEIAA).

MadhyaPradesh Prepared in accordance with Permission of WRD, GoMP for StateWater the National Water Policy, it abstraction of water from Samoha Policy,2003 states that “for environmental dam, Futiwar dam, Pachipura balance, skillful and planned dam, existing stop dam/weir and management of all types of from Sindh river etc. for WSS developmental activities, subprojects towns; Karera, economic use on equitable Pichhore, Bairad, Vijaypur and basis and in view of the prime Aron etc. has been granted and importance of water for all NOCs has obtained. - Refer human and other living Appendix 24. beings, an effective and sound water policy is necessary”. Policy is detailed in 17 sections dealing with different aspects of water resources. No. 7 deals with Water Allocation Priorities, and according to which drinking water supply shall have the highest priority followed by irrigation, power, tourism, etc. Water Resource Department is nodal department for permitting different uses of water resources. Policy also states that “clear provision for reservation of drinking water shall be made in irrigation projects” Dam” Water (Prevention and Act was enacted to provide WTP requires CFE and CFO Control of Pollution) Act of for the prevention and control from MPPCB. 1974, Rules of 1975, and of water pollution and the amendments maintaining or restoring of wholesomeness of water, by Application has to be submitted Central and State Pollution online at Control Boards and for http://www.mppcb.nic.in/xgn.html conferring and assigning to CPCB/SPCBs powers &functions relating to water pollution control.

Control of water pollution is achieved through administering conditions imposed in consent issued under to this Act. These conditions regulate the quantity and quantity of effluent, the location of discharge and the frequency of monitoring of effluents. Any component of the subproject having the potential to generate sewage or trade effluent will come under its purview. Such projects have to obtain Consent to Establish (CTE) & Consent to Operate (CTO) under Section 25 from Madhya Pradesh Pollution Control Board (MPPCB) before starting implementation and Consent For Operate (CFO) before commissioning. Environment (Protection) Act, Emissions and discharges from Appendix 2 provides applicable 1986 and CPCB Environmental the facilities to be created or standards for ambient air quality. Standards. refurbished or augmented shall Appendix 3 provides vehicular comply with the notified emission norms standards Noise Pollution (Regulation and Rule 3 of the Act specifies Appendix 4 provides applicable Control) Rules, 2000 amended ambient air quality standards in noise standards up to 2010. respect of noise for different areas/zones. Municipal Solid Wastes Rules to manage municipal Solid waste generated at proposed Management Rules, 2016 solid waste generated; provides facilities shall be managed and rules for segregation, storage, disposed in accordance with the collection, processing and MSWM Rules disposal. Construction & Demolition Rules to manage construction & Construction & demolition waste Waste Management Rules, to waste resulting from generated from the project 2016 construction, remodeling, repair construction shall be managed and and demolition of any civil disposed as per the rules (Appendix structure. Rules define C&D 7) waste as waste comprising of building materials, debris resulting from construction, remodeling, repair and demolition of any civil structure. Indian Wildlife (protection) Act, Provides for the For Karera Town WSS – Karera 1972 amended 1993 and comprehensive protection of town is located about 14 km Rules 1995 Wildlife Wild animals, birds and plants away from Karera bird (Protection) Amendment Act, .This would cover matters sanctuary. As per mapping on 2002 concerning Appointment of google earth map, according to forest authorities, hunting of coordintes of prominent points of wild animals, protection of the boundary of Karera Bird specified plants, conservation sanctuary and coordinates of the of national parks and boundary of Karera Bird sanctury sanctuaries, trade commerce Eco-sensitive zone as given in in relation to plants and MOEFCC Notification 15th animals and prevention of any September 2017, the boundary of offences. Karera Wildlife Sanctuary is about Note: -All activities in the Eco 500 m away from the boundary of sensitive Zone shall be Karera municipal areas. All the governed by the provisions of subproject components like Intake, the Environment WTP, OHTs, RWRM, CWRM & (Protection) Act, 1986 (29 of distribution networks come within 1986) and the rules made the boundary of Eco-Sensitive there under including the Zone (ESZ) of Karera wildlife Coastal Regulation Zone 2011 sanctuary as shown on Google and the Environmental Impact Map of Karera wildlife sanctuary Assessment Notification, 2006 and subproject town Karera; and other applicable laws showing the boundaries of both including the Forest clearly alongwith location of (Conservation) Act, 1980 (69 main components i.e. of 1980), the Indian Forest Source/intake, WTP & OHTs etc. Act, 1927 (16 of 1927), the which is appended as Fig – 24. Wildlife (Protection) Act 1972 Also Refer Fig-2- Showing Site (53 of 1972), and Photograph of Final Selected amendments made thereto Location of Intake Well on and be regulated in the Estern Bank of Samoha Dam manner specified in the Table, across Mahuar River at Khera 3 namely:— List of Activity Modi Village. Prohibited & Regulated Karera Wildlife sanctuary today has not a single bird species. Owing to villagers/public pressure and the extinction of the bird locally, the National Board for Wildlife and the Government of Madhya Pradesh have decided to denotify the sanctuary and is seeking the Centre's approval. The decision is now awaiting a final approval from the Supreme Court of India (For Denotification Details Refer “Minutes of 18th Meeting of Standing Committee of NBWL annexed as Appendix 26.)

Karera wildlife sanctuary is spread over an area of 202 km2, of which as much as 146 km2 is privately owned land. The Eco-Sensitive Zone (ESZ) is spread over an area of 93.00square kilometres with an extant varying from 500 meter from notified urban and ‘abadi’ areas and 2 kilometers on the rest of area from the boundary of the Karera Wildlife Sanctuary.

All the components like Intake, WTP & OHT are located about a distance of 500m–2km away from the boundary of Karera wildlife sanctuary as mentioned above.

(i) Proposed Intake well is located around 13.2 km away from Karera town. Intake well is about a distance of 500 m away from boundary of Karera Bird’s Sanctuary and comes under Eco-Sensitive zone (ESZ). As per MOEFCC Notification; Commercial Extraction of Surface Water within Eco Sensitive Zone is Regulated under applicable Law. (Refer Table – 3, S. No. 27 & Refer Appendix 25, Para 4, S. No. 27- MOEFCC Notification). Also NoC from WRD for abstraction of water from Samoha dam and construction of intake already obtained (For NoC, Refer Appendix 24).

(ii) The raw water rising main, connecting intake and WTP, will be partly outside and partly within the towns, which will be laid partly within the ecosensitive zone boundary and partly away from the ESZ boundary of sanctuary (Refer google map annexed as Fig- 24). Raw water & clear water rising main will be laid underground from the intake well to WTP and from WTP to OHTs site along an existing road within ROW. WTP, OHTs and clear water rising main is located within the municipal limits of Karera Nagar Parishad, but it is within the boundary of ESZ of Karera bird sanctuary. WTP is about a distance of 500m and OHTs are about 1- 2 km away from the boundary of Karera wildlife sanctuary, where there are no sensitive environmental features.

(iii) Construction activities in Eco-Sensitive Zone is permitted as per building bye laws to meet the residential needs of the local residents such as construction and renovation of infrastructure and civic aminities (Refer Table 3, S. No. 14 & S. No. 20 and Refer Appendix 18, Para 4, S. No. 14 & S. No. 20- MOEFCC Notification). However, it will be done with mitigation measures, as per applicable laws, rules and regulation and available guidelines.

(iv) Also Refer Appendix 31, which talks about non- applicability of wildlife clearance about projects falling in Eco-Sensitive Zone which are not covered under EIA Notification and which do not require environmental clearances would aslo not required approval of standing committee of National Board of wild life. (v) Also consultation conducted with forest official on dated 10.05.2018 at Office of Chief Conservator of Forest & Director, Madhav National Park, Shivpuri as Its management and control is under Field Director of Madhav National Park (Refer Appendix 7 & Appendix 10). Detailed discussions held and briefed about proposed components under water supply scheme for Karera town within eco- sensitive zone and its impact on Karera bird Sanctuary. They told that they have no objection as this project is to meet the daily residential needs of the local residents by providing with a constant supply of better quality water as the subproject will improve the overall environmental quality of the town and surrounding areas.

Since the proposed subprojects components such as Intake, RWRM, WTP, CWRM and OHTs works shall be limited to actual construction area and the access roads, but appropriate steps should be taken according to the nature of the risk. Precaution must be taken care to minimize the noise during construction work to avoid any negative impact on bird sanctuary. The impact will be only for limited time during construction work.

Note: - As per Minutes of the 18th Meeting of the Standing Committee of National Board for Wildlife (NBWL) held on 12th April, 2010 in 403, Paryavaran Bhavan, CGO Complex, Lodi Road, New Delhi- 110003, With respect to, Karera Wildlife Sanctuary, Madhya Pradesh, the Member Secretary informed that Shri. Mahendra Vyas, Member of Rationalization Committee had inspected the site and submitted his report. In his report he had recommended for denotification of the sanctuary subject to the condition that the Government should find out the cause of disappearance of the Great Indian Bustard and also efforts should be made to declare the Dihaliya Lake as a Conservation Reserve. The Chief Wildlife Warden, Madhya Pradesh, informed that the bustards were not seen since 1995 and that most of the land inside the sanctuary was private land and people were facing lot of problems. After detailed discussions, the committee agreed to the proposal for denotification of Karera Wildlife Sanctuary, subject to following conditions. (For Minute of Meeting of NBWL Details Refer Appendix 26).

(vi) For Bairad & Vijaypur Towns: Kuno Wildlife Sanctury which is also known as Palpur - Kuno Wildlife Sanctuary is situated at a distance of 10 km away from Bairad and 24 km away from vijaypur town. None of the subproject components are located within the boundary of Kuno wildlife sanctuary nor in its ecosensitive zone. Refer Google Maps of Kuno wildlife sanctuary and subproject towns; showing the boundaries of both clearly alongwith location of main components i.e. Source/intake, WTP & OHTs etc. which is appended as Fig - 29

Kuno wildlife sanctuary is spread over an area of 344.686 sq. kms. The Eco-Sensitive Zone shall be of 207.451 square kilo meters with an extent up to two kilometers around the boundary of Kuno- palpur Sanctuary. Labor Laws The contractor shall not make Appendix 6 provides applicable employment decisions based labor laws including amendments upon personal characteristics issued from time to time applicable unrelated to job requirements. to establishments engaged in The contractor shall base the construction of civil works. employment relationship upon equal opportunity and fair treatment, and shall not discriminate with respect to aspects of the employment relationship, including recruitment and hiring, compensation (including wages and benefits), working conditions and terms of employment or retirement, and discipline. The contractor shall provide equal wages and benefits to men and women for work of equal value or type.

Table 3: List of Activity Prohibited / Regulated Within The Eco-Sensitive Zone

Source: MOEFCC Notification 15th September 2017

43. ADB SPS Requirements. During the design, construction, and operation of the project the PMU and PIUs are required to apply pollution prevention and control technologies and practices consistent with international good practice, as reflected in internationally recognized standards such as the World Bank Group’s Environment, Health and Safety Guidelines. (IFC’s General EHS Guidelines1 and Sector Specific (Water and Sanitation) Guidelines2). These standards contain performance levels and measures that are normally acceptable and applicable to projects. When Government of India regulations differ from these levels and measures, the PMU and PIUs will achieve whichever is more stringent. If less stringent levels or measures are appropriate in view of specific project circumstances, the PMU and PIUs will provide full and detailed justification for any proposed alternatives that are consistent with the requirements presented in ADB SPS. International acceptable air and noise quality guidelines are provided below:

Table 4: WHO Ambient Air& Noise Quality Guidelines

1 https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B- %2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 2 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B- %2BWater%2Band%2BSanitation.pdf?MOD=AJPERES

V. DESCRIPTION OF THE ENVIRONMENT (BASELINE DATA)

A. Methodology Used for Baseline Study 44. Data Collection and Stakeholder Consultations. Data for this study has been primarily collected through comprehensive literature survey, discussion with stakeholder agencies, and field visits to the proposed subproject sites.

45. The literature survey broadly covered the following:

(i) Project details, reports, maps, and other documents prepared by technical experts of the Design consultant (ii) Discussions with Technical experts of the design team, municipal authorities, relevant government agencies like WRD, Forest Department, MPPCB, etc. (iii) Secondary data from previous project reports and published articles, and (iv) Literature on land use, soil, geology, hydrology, climate, socioeconomic profiles, and other planning documents collected from Government agencies and websites.

46. Ocular inspection. Several visits to the project sites were made during IEE preparation period in 2016 to assess the existing environment (physical, biological, and socioeconomic) and gather information with regard to the proposed sites and scale of the proposed project. A separate socioeconomic study was conducted to determine the demographic information, existing service levels, stakeholder needs and priorities.

B. Baseline Environmental Profile 47. Following Table 5, presents the baseline environmental profile of subproject towns of Karera, Pichhore, Aron, Bairad, Isagarh and Vijaypur. It is organized in terms of physical, ecological, economical, and socio cultural resources. Baseline characteristics of Package 4D towns are givenbelow in Table 5:

Table 5: Baseline Characteristics of Package 4D Towns

S. Particulars Karera Pichhore Aron Bairad Vijaypur Isagarh No. 1. Location Karera is a municipality Located in Located in Located in Shivpuri Nagar Parishad in the Located in or Nagar Palika in Shivpuri District Guna District District Sheopur district of Ashoknagar the Shivpuri district of Latitude: 250 Latitude: 230 Latitude: 25.70°N Madhya Pradesh. District the Indian state 10’N 8’N Longitude: 77.46°E. Vijaypur is located at Latitude:24° 51' N of Madhya Pradesh. Longitude: 780 Longitude: 780 26° 3'10.75"N and Longitude :77º53' Karera is the second- 11’E 41’E 77°22'7.53"E. E largest city in the Vijaypur town is Shivpuri district after located 141 km away Shivpuri itself. Karera is from district centre located at 25.47°N, Sheopur. 78.15°E. It has an average elevation of 305 meters (1000 feet) 2. Connection Karera town is about 55 Pichhore town is Aron Town is Bairad does not have SH-23 connects Isagarh is situated km from its district head 77km from its Tehsil head any significant Vijaypur to Sheopur, on SH - 10 quarter, Shivpuri. district head quarter in Guna connectivity town lack Shivpuri. It is connecting Karera is the second- quarter, Shivpuri. District lies at a major national/state connected to Gwalior Gahora- Ashok largest city in the The road network distance of highway near to its (120 km), (94 Nagar. The Shivpuri district after also shows about 32 km proximity. It is km), Shivpuri (112 nearest railway Shivpuri itself. organic growth from district connected by district km), (34 station is Ashok Karera is connected with the linking head Quarter. road to the north of km) & Bhopal (420 Nagar which is 35 with neighboring cities road from NH-25 Aron is Pohari tehsil which km) through roads. km from the town. and other major cities of being the main connected to connects NH-3 located Nearest Railway Isagarh is 33.7 km India by road (NH-25), road which has the district via at 50 km to the north of Station is at far from its District shivpuri and (NH-27), emerged as the State Highway the town. Rampahari, which is Main City Ashok , Sagar, , main commercial 23 which Bairad town does not 25 km from the town. Nagar. It is 182 Dabra, , spine of the town. passes through have any railway The nearest airport is km far from its , Bhopal, Guna, The only the Aron and station. The nearest at Gwalior, which is State Main City Gwalior, Kota, , connectivity to other major railway station is around 120 km from Bhopal. Isagarh , Allahbad, Pichhore city is a districts roads. located at Shivpuri at 65 town was one of the , road connecting Nearest railway km away from the town. first districts of and Ahmadabad etc. which is station and Major nearest railway Madhya Pradesh approximately airport is station is Gwalior at in 1947-48. Later The road network also 25.6km long from located at Guna distance of 104Km. it was merging shows organic growth NH-25. Nearest which is 32 Km The nearest airport is at and became part with the linking road railway station is from Aron town Gwalior, which is of Ashok Nagar. from NH-25 being Basi which is 30 around 104km from Isagarh Nagar the main road which km from Pichhore town Parishad (INP) has emerged as the and nearest extends to an main commercial spine airport is Gwalior. area of about of the town. Daily buses 17.12sq. km services operate within characterized by a the city, with inter-city mix of urban and services also available few rural daily to many cities in settlements. The Madhya Pradesh, Uttar town is divided Pradesh and . into 15 municipal wards. Karera is not directly accessible by rail, with the nearest railway stations located in Jhansi 45 km to the east and Shivpuri 55 km west of the city. The nearest rail head to Karera is Pendra Road at a distance of 17 km from the heart of the city.

The nearest major airport is located at Gwalior which operates flights to Delhi, Bhopal, Indore, Mumbai, Pune, , , Jaipur, and most large cities in India. 3. Area and Population The area of the town is The total area of Area of the Area of the town is Area : 3.00 Sq.km Area of the town spread over in 12 Sq the town is 8 sq town is 20.10 27Sqkm is 18 sqkm km (2011). Density of km having a sqkm and Population : 16,964 the town is increasing population of population is Population : 18,313 (2011 census) in 15 Population of the with the increase of 18127.The Nagar 28,010 as per (2011 census) in 15 wards town as per 2011 population. Future parishad is of 2011 census. wards censes is 12583 growth of the town is rural in nature as expected towards the it does depend highway or because of on agriculture. the high congestion on The town has the road side. agricultural based Population of the town economy. as per 2011census is 25705 4. Topography Topography of the Topography of Aron town is Topography of the Baira The terrain of the The topography project area is mostly the project area situated on firm town is almost plan. town is slopping terrain of the plan, except for few is mostly plan, ground. It is Bairad is situated in toward Kunwari town is flat. It isolated small range except for few situated on pohri tehsil of shivpuri River. The total has an average hills in Karera. Average isolated small semi-arid district. Located 57 km elevation difference elevation of elevation is 305 m from range hills in geological towards North from in Vijaypur is around 489 metres Mean Sea Level, and Pichhore. The formation. The district head quarters 25 meters and having (1604 feet). the area predominantly town is strata found are shivpuri. Bairad is highest contour value slopes from notheast to surrounded by - Hard Kopra located in at North West 210.0 mtr and lowest southwest. Karera is three hillocks and Red soil... of shivpuri and it has an contour value 185.0 mostly drains into a namely Hazira Topographical average elevation of mtr. river Mahuwar towards Pahadi, Galati features of the 480m above mean sea southwest. Mandir and Killa town explain level.(MSL). the elevation the variations differences from from RL highest of 226 m 516.06m to RL to 203 m 497.50 m. The accounted a elevation maximum differences difference of 23 from highest of m in the town. 516.06 m to Town is situated 497.50 m at an average accounted a Elevation of 225 maximum m from Mean difference of Sea Level. 18.56 m in the town. 5. Rainfall The average annual Average rainfall Average rainfall The district receives its The average rainfall The average rainfall in the town is in the town is in the town is rains from the Arabian of the town is 950- rainfall of entire about 750 mm. About 816mm. 1053mm. Sea. The rains are over 1000 mm. It is seen Isagarh town is 95% of the annual Monsoon season Monsoon generally by end of that rainfall in the around 864 mm rainfall is received start form late season start September. The district in general during the monsoon July to early form 15th June average annual rainfall increases from north- months, June to October and ends on of Bairad under Shivpuri west to south-west. September, July being 15th October. region for 30 years from About 90 percent of the rainiest month Maximum 1972 to 2002 is 871 the annual rainfall in rainfall occurs mm. the town is received during the during the south-west month of July monsoon season - and August. June - September, July being the rainiest month 6. Soil and Geology Majorly three types of Majorly three Majorly three Majorly three types of The soil type of the The soil is Black soil formations are types of soil types of soil soil formations are town is: Alluvial soils, in color and some observed in the area, formations are formations are observed in the area, Shallow and medium parts of hinterland Black cotton, Red loamy observed in the observed in the Black cotton, Red loamy black soils, are very fertile. soil and sand stone etc. area, Black area, Black soil. Limestone reserves Physiographical, cotton, Red cotton, Red are also seen in area. the major part loamy soil in loamy Deep medium Black soil exhibits a region pichhore . soil.Mixed red is present in the town. of low level and black soil is plateau plain of present in the extrusive origin town with terrace; rocky bench and floodplain (including infilled river bed) along the course of the rivers. The other landforms are low structural plateau & structural plains of Proterozoic rocks. 7. Climate The town has a humid The town has a Normal Bairad town comes is After February Climate plays a subtropical climate. The humid subtropical maximum under Shivpuri district temperature rises vital role in highest recorded climate. The temperature which has a cool and progressively to the determining the temperature was 46°C highest recorded during the dry climate. The hot maximum. May is landforms and the in May month.and the temperature was month of May is weather starts from generally the hottest productivity of lowest was 5°C. in 41.06°C. 41.3 °C. and about the middle of April month with mean ecosystems. January month. And the lowest minimum during and lasts up to mid of daily maximum Rainfall, was 6°C. January month May. The temperature temperature at about temperature and Winds are generally is 7.7°C. in June touches 42°C. 43 degree Celsius winds are the light in the city with By the end of June or and low to 29 degree principal climatic some strengthening in by the 1st week of July, Celsius. On individual factors that force during the late the monsoon breaks day temperature may significantly shape summer and monsoon. and the weather rise up to about 47 the physical setup In may the south-west becomes cool, through degree Celsius. The in this area. and north-west. Winds humid. relative humidity is Isagarh has are generally from high during the subtropical directions between monsoon season, it climate south-west and north- being generally characterized by west. above 70 percent. In hot summer, wet the rest of the year monsoon and dry the air is winter comparatively dry. The average The driest part of the maximum year is summer temperature season when the recorded during relative humidity is the summer is less than 20 percent 43.4⁰C, and in the afternoon. minimum is 7.2⁰C 8. Surface Water River Mahuar flows in There is one river There is no There is no water body There is no water Isagarh has a the south direction of body in river or any in the town. There is body other than network of lakes Karera town. Due to municipality water body in one irrigation canal Kunwari River in the and water bodies absence of sewage boundary named Aron passing from south to town. connected treatment plant and Moti Sagar Lake. municipality north of town. through natural wastewater treatment Area of the Moti boundary. Water Quality of drain system for plant most of the natural Sagar Lake is Kunwari River in the carrying the storm drains dispose waste around 0.5 ha. project area is tested. water discharge. directly into river Nagda Dam is There are Mahuar. situated adjacent The results are primarily three to Pichhore town, compared with the water bodies while Futiwar drinking water existing in the dam is 2km away standards. Owing to Nagarparishad from the town. presence of coliform area i.e. Singh in the range of 21 to Sagar, 25 nos against Nil, MotiJheelTalab, the surface water Bhojanatalab and needs to be treated other small water before supplying to bodies and small the public lakes.Singh Sagar lake is very bless for recharging and improving the ground water condition of the town.The area of this lake is about 53.40 hectare. 9. Ground water Karera and Pichhore blocks has high Ground Water As per Central Ground As per Central Hydrogeology of fluoride content in dug well and tube wells. quality in Guna Water Board report Ground Water Board the study area Due to the high content of the fluoride district is (2013) the project area report (2013) the comprises the ground water in these villages are not assessed by falling under safe zone project area comes whole area is suitable for the drinking purpose. The CGWB on the for ground availability under Vijaypur block covered by underground water level in both the town is basis of water with yield in the range of falling under safe Alluvium Deccan depleted from 5m to 9m from 2011 to 2014. samples 0.15 to 22lps yield and zone for ground Trap i.e. Basalt Granites are most extensive rock formation collected from the depth to average water availability with rock. From in the Karera and pichhore blocks. Ground twenty-five ground water table yield in the range of surface to 10 m to Water occurs in the weathered part and numbers of varies in the range of 25 0.5 to 14 lps and the 20 m depth vertical and horizontal joints. The yield of the hydrogen to 204m below ground depth to average weathered rock wells is restricted to the weathered mantle stations. level. ground water table found and there and ranges from less than one to 3 lps. Unit Ground water is The Water Quality of varies in the range of may be possibility draft of the wells in the formation varies from generally sub-surface water in the 105.71 to 200 m of water. After that 0.00075 to 0.0051 mcm/year. Under the medium to high project area is tested. below ground level. solid basalt rock Ground water Exploration programme saline as All the parameters are may found up to CGWB has constructed the exploratory electric within the permissible 45 m depth and wells & observation wells of 135 to 203 m conductivity limits. Found suitable there is no deep. The depth to water levels in these values vary for drinking purpose. possibility of wells varies from 2.65 to 12.98 m bgl and between 353 to water. Between discharge of the wells ranges from 0.2 to 5.4 2443 micro 45 m to 55 m lps with a draw down ranges from 36 to 65 mhos/cm. High depth m. The Ground water quality is same for EC of more intertrappean i.e. karera and pichhore as the distance than 1500 loose formation between the towns are under 50km. micro mhos/cm found that may be was found in collapsible so use three dug well over there casing of Barod (1704 for protection of micro bore. After that mhos/cm), solid basalt rock is Panchi (1709 found between micro mhos/cm) 100 m to 120 m and Khakariya depth fractured (2643 micro rock may be mhos/cm) found, there may villages. be possibility of Constituents water. The upper like Fluriode, kaimur formation sulphate; sandstone and Calcium and quartzite. Magnesium were within the Alluvium of safe limit for Quaternary age drinking water occurs as a as per BIS narrow belt along standards. the major rivers Nitrate in the like Sindh, Betwa, ground water Kethan& Orr. It varies from 6.4 comprises pebble to 332mg/l. beds, gravel, silt & Nitrate more sand. In the area than 100 mg/l occupied by was found at alluvium, the Husainpur (332 ground water mg/l) and Mau occurs under (313 mg/l) water table villages. condition. The High nitrate in granular portion of ground water this formation appears due to such as sand & the use of gravel forms good fertilizers etc. aquifers, but the The total thickness is hardness of shallow. The yield ground water is of the wells in this under safe limit formation ranges of BIS from 2 to 7 standards. High lps.The principle chloride of aquifers in the more than 250 area are mg/l was found constituted by at Barod, Vesicular Basalts Panchi & and fractured Khakariya zones in Basalts villages. and inferred Sedimentary at a depth and beyond, with varying thickness of 5 m onwards.

According to CGWB, ground water level in this region ranges from 4 to 16 m below ground level (bgl) during pre-monsoon (May 2012)In the post monsoon period (November 2012) the water level ranges between 5 to 10bgl. In terms of groundwater development, Isagarh block fall under safe category. The stage of ground water development has reached to 43 % in Isagarh block, in which the project town Isagrah is situated 10. Air Quality Air Quality data is not Air Quality data is Air Quality data There is no data on Particulate matter is There is no data available as town is not available as is not available. ambient air quality and likely to be high, on ambient air very small. While there town is very Air pollution in Noise levels in Bairad, particularly during quality in Isagarh is no air pollution in sub small. While sub project which are not subject to summer months. Town, which are project area due to there is no air area due monitoring by the Traffic is the only not subject to absence any industrial pollution in sub industrial Madhya Pradesh significant pollutant, monitoring by the activity as well as heavy project area due activity as well Pollution Control Board so levels of oxides of Madhya Pradesh vehicular movement. to absence any as heavy (MPPCB) as there are Sulphur and nitrogen Pollution Control Traffic is the only industrial activity vehicular no major industries. are likely to be well Board (MPPCB) significant pollutant, so as well as heavy movement. within the National as there are no levels of oxides of vehicular No field monitoring Ambient Air Quality major industries. sulphur and nitrogen movement. No field (environmental) survey Standards (NAAQS). are likely to be well monitoring was conducted The major traffic flow No field within the National No field (environmental) however, the is along MDR monitoring Ambient Air Quality monitoring survey was environmental towards Sabalgarh & (environmental) Standards (NAAQS). (environmental) conducted monitoring program Sheopur both inter survey was survey was however, the developed as part of the town and intra town. conducted No field monitoring conducted environmental environmental The noise levels were however, the (environmental) survey however, the monitoring management plan comparatively higher environmental was conducted environmental program (EMP) will require the along these transport monitoring however, the monitoring developed as contractors to establish corridors than the program environmental program part of the the baseline other roads and developed as part monitoring program developed as environmental environmental various commercial of the developed as part of the part of the management conditions prior to locations in the town. environmental environmental environmental plan (EMP) will commencement of civil Daytime and night management plan management plan management require the works. The results will time noise levels in (EMP) will require (EMP) will require the plan (EMP) will contractors to be reported as part of the town were found the contractors to contractors to establish require the establish the the environmental varying but are within establish the the baseline contractors to baseline monitoring report and the permissible limits; baseline environmental establish the environmental will be the basis to however the levels environmental conditions prior to baseline conditions prior ensure no degradation are reported well conditions prior to commencement of civil environmental to will happen during within the permissible commencement works. The results will conditions prior to commencement subproject limits by MPPCB for of civil works. The be reported as part of commencement of civil works. implementation. all categories in the results will be the environmental of civil works. The results will areas reported as part of monitoring report and The results will be reported as the environmental will be the basis to be reported as part of the monitoring report ensure no degradation part of the environmental and will be the will happen during environmental monitoring basis to ensure no subproject monitoring report report and will degradation will implementation. and will be the be the basis to happen during basis to ensure ensure no subproject no degradation degradation will implementation. will happen happen during during subproject subproject implementation. implementation.

No field monitoring (environmental) survey was conducted however, the environmental monitoring program developed as part of the environmental management plan (EMP) will require the contractors to establish the baseline environmental conditions prior to commencement of civil works. The results will be reported as part of the environmental monitoring report and will be the basis to ensure no degradation will happen during subproject implementation. 11. Ecology Project area mostly There is no any There is no Project area mostly Project area mostly The project area – comprises urban areas, ecological sensitive comprises urban areas, comprises urban municipal area of agricultural areas of sensitive feature environmental agricultural areas of areas, agricultural Isagarh Nagar Karera, which are inside the feature inside Bairad town, which are areas of Vijaypur Parishad, converted to human use Pichhore the Aron converted to human use town, which are comprises the many years back. There municipal Municipal many years back. There converted to human habitation areas is no ecological boundary. All the boundary. Flora is no forest area within use many years of Isagrah town, sensitive feature, such flora and fauna in and fauna in the limit of project area back. There is no Majority of the as forests, in the project Pichhore town the municipality and none of the project forest area within the area in the area and none of the are local. of local species. components are located limit of project area municipal project components are However, a in the forest areas. and none of the boundary is in located in the forest reserve forest project components agricultural use. areas. The forest named Guna Nearest Protected area are located in the There are no namely “Karera Reserve Forest is Kuno Wildlife forest areas. ecologically Reserve forest” & is situated more Sanctury which is also sensitive features Mahuar protected forest than 10km far known as Palpur - Kuno Kuno Wildlife like forest in the at a distance of 1.5 km from the Aron. Wildlife Sanctuary is Sanctury which is project area. to 2.0 km away from The forest has situated at a distance of also known as Palpur Streams are Karera town. (Refer very rich 10km away from Bairad - Kuno Wildlife seasonal, so there Google Map & SOI biodiversity. town and none of the Sanctuary is situated is no noticeable Map annexed as Fig- project components are at a distance of 24 aquatic life. Flora 23 & Fig-24). These located within the km away from and fauna found forest areas are boundary of sanctuary Vijaypur town. None in the area is of characterized by low or in its ecosensitive of the project local species. range hills, rugged zone. Refer the components are lands, rockly outcrops, boundary details of within the sanctuary. open forests and scrub Kunopalpur Wildlife or within the Eco- lands. Following type of Sanctuary and its eco- sensitive zone. All the tree species are found sensitive zone and components are in these areas: babul subproject town Bairad located at a distance (Acacia Nilotica), neem, showing the boundaries of around 24 km from khair (Acacia catechu), of both clearly along the Bounadary of palas (Butea with location of main ESZ of Kuno Wildlife monosperma), ber components (Source/ Sanctuary. Refer (Zizyphus varieties), intake, WTP and OHTs Map appended as tendu (Diospyros etc on google maps as Fig - 29. melanoxylon), mahua per coordinates of (Mahuca Indica), semal Boundary of Kuno (Salmalia malabarica) wildlife sanctuary & and kardhai Coordinates of ESZ of (Anogeissus pendula) Kuno wildlife sanctuary given in MOEFCC Karera Wildlife Notification 9th Sanctuary is situated November 2017) are about 14 km away from appended as Fig - 29. subproject town Karera. The proposed intake Kuno Wildlife Sanctury site is located in eastern spread over an area of bank of Samoha Dam 344.686 sq. km. The (constructed across Eco-Sensitive Zone Mahuwar River.) at spread over an area of Khera Modi Village, 207.451 square Proposed Intake well is kilometers with an located about 500 m extent up to two away from the boundary kilometers around the of Karera wildlife boundary of Kuno - sanctuary. The intake Palpur Wildlife site comes within the Sanctuary Eco-Sensitive Zone of Karera wildlife Fauna in Kuno sanctuary. As Sanctuary: All the preliminary examine faunal representatives shows that newly of the dry deciduous recommended source is forest of the Central found socially & India can be found in environment and Kuno, the sanctuary is technically acceptable. inhabited by all usual No Flora and Fauna has animals of the region, been reported in and such as leopard, jackal, around the proposed Wild Dog, Indian fox, site. Also no among carnivorous and environment impact Nilgai, four horn observed at site. Refer antelope, Wild pig Fig 2 - Showing Site amongst herbivores, Photograph of Chital, Sambhar, Black Recommended & Deer, Chinkara, Bear, Proposed New Blue bull, Chausingha, Location of Intake Jungle cat, Barking Well on Eastern Bank Deer, Monkey, Jackals, of Samoha Dam Hyena, Wild Boar, Fox, across Mahuar River. Kobra, Nag, Python, Peacock, Kala Teetar, The boundary of Karera Tree pie, Golden Wildlife Sanctuary is orioles, Drongo, Rollers, about 500 m away from Jangli, murgi, Phakta, the boundary of Karera Bhura, Teetar. municipal areas. However as per Flora in Kuno mapping on google Sanctuary: The Kuno earth map, according to sanctuary consists of coordinates as dry deciduous forests mentioned in MOEFCC interspersed with Notification 15th grasslands, consisting September 2017 of mainly of Anogeissus prominent points of the Pendula, Acacia boundary of Karera catechu and Boswellia wildlife sanctuary and serrate communities coordinates of the and their associated boundary of Eco- flora and is free from sensitive zone of Karera human habitation. The wildlife sanctuary. All Sanctuary area is rich in the proposed subproject biodiversity, 120 tree components like species, 71 herbs and Recommended & shrubs species, 32 proposed new location climbers of intake, WTP, OHTs, and parasites, 34 RWRM, CWRM & grasses and bamboo distribution networks species, 24 mammals, are within the boundary 206 birds, 14 fish, 33 of Eco-Sensitive Zone reptiles and 10 species (ESZ) of Karera wildlife of amphibians, sanctuary about 500m 15 species of butterfly to 2 km away from the have been recorded in boundary of Karera Kunopalpur Wildlife wildlife sanctuary as Sanctuary; shown on Google Map of Karera wildlife Tree : Kardhai, Gurjan, sanctuary and Kher, Kusum, Gurjan, subproject town Mahua, Guner, Haldoo, Karera; showing the Kullu, Kahua, Semal, boundaries of both Bahera, Tendu, Palas, clearly along with Bel, Chind, Anwala, location of main Harsingar, Chind, components i.e. Satawar; Parasites : Source/intake, RWRM, Bamdha, Amarbel; WTP, CWRM & OHTs Grasses : Doob, Lumpy, etc. which is Machai, Guner, Ponea, appended as Fig – 24. Phulara. Intake well is located The Kuno Wildlife around 13.2 km away Sanctuary was selected from Karera town. as the re Intake well is about 500 introduction site for m away from boundary the endangered Asiatic of Karera bird’s lion. In 2007, the sanctuary and comes protected area was under Eco-Sensitive ready to receive a first zone (ESZ). Extraction batch of lions from Gir of surface water Wildlife within Eco Sensitive sanctuary. where the Zone is regulated population is too big. under applicable Law There are large scale (Refer Table 3, S. No. deaths in the population 27 & Appendix 25, annually because of Para 4, S. No. 27- ever increasing MOEFCC Notification). competition due to Also NoC from WRD animal overcrowding. for abstraction of Asiatic lion prides water from Samoha require large territories dam and construction but there is limited of intake already space at Gir wildlife obtained (Refer sanctuary, which is Appendix 24). The raw boxed in on all sides by water rising main, heavy human connecting intake and habitation. The lions are WTP, will be partly to be reintroduced outside and partly within from Gir Wildlife the towns, which will be Sanctuary in the laid partly within the Eco neighboring Indian state sensitive zone boundary of Gujarat where they and partly outside the are currently ESZ boundary of Karera overpopulated. As the sanctuary. Raw water state government of and clear water rising Gujarat was refusing to main will be laid relocate the Asiatic lions underground from the to this sanctuary, this intake to WTP and from ensued a long battle. WTP to OHTs site along Finally on 18 April 2013, an existing PWD road the Supreme Court of within ROW. WTP, India gave a verdict that OHTs and clear water asked the Gujarat rising main is located government to complete within the municipal the translocation of the limits of Karera Nagar Asiatic lion within six Parishad, but it is within months. On 22 April the boundary of ESZ of 2015, the Union Karera bird sanctuary. government has WTP is about 500m and admitted that Madhya OHTs are about 1-2 km Pradesh will have to away from the boundary enlarge the wildlife of Karera wildlife sanctuary's size in order sanctuary, where there to translocate Asiatic are no sensitive lions to Palpur-Kuno environmental features. from Gujarat's Sasan Construction activities Gir, which is the first in Eco-Sensitive Zone time the government is permitted as per accepted the sanctuary building byelaws to needs to be enlarged. meet the residential However, that would needs of the local require relocating residents such as several big villagesAs of construction and now, Madhya Pradesh renovation of still has not received infrastructure and lions from Gujarat. For civic aminities (Refer this reason, it was Table 3, S. No. 14 & S. considered to turn Kuno No. 20 and Refer Wildlife Sanctuary into a Appendix 25, Para 4, protected area for tigers S. No. 14 & S. No. 20- instead, by bringing in MOEFCC Notification). tigers from other parts However, it will be done of Madhya Pradesh. with mitigation measures, as per applicable laws, rules and regulation and available guidelines. Also Refer MOEF letter Appendix 31, which talks about non-applicability of wildlife clearance about the projects falling in ESZs which are not covered under EIA Notification and which do not require environmental clearances would aslo not required approval of standing committee of National Board of wild life.

Karera Wildlife sanctuary today has not a single bird species. Owing to villagers / public pressure and the extinction of the bird locally, the National Board for Wildlife and the Government of Madhya Pradesh have decided to denotify the sanctuary and is seeking the Centre's approval. The decision is now awaiting a final approval from the Supreme Court of India and should it come through, the sanctuary will become the country's first such reserve to lose its official recognition. (For Denotification Details Refer “Minutes of 18th Meeting of Standing Committee of NBWL annexed as Appendix 26.)

Karera, wildlife sanctuary is situated on the way from Shivpuri to Jhansi in the Shivpuri district of Madhya Pradesh, India. It is situated at the western boundary of the Karera town. The sanctuary is at a distance of around 55 km from Shivpuri and around 14 km away from Karera town (Refer Google Map Annexed as Fig – 24). It was originally created with the aim of protecting the local population of the great Indian bustard. It is now in the process of being denotified due to opposition by the local people and the extinction of the bird locally. The Karera Sanctuary was notified in 1981 by the Government of Madhya Pradesh in accordance with the provisions of the Wild Life (Protection) Act, 1972. It is spread over an area of 202 km2, of which as much as 146 km2 is privately owned land. The Eco- Sensitive Zone (ESZ) is spread over an area of 93.00square kilometres with an extant varying from 500 meter from notified urban and ‘abadi’ areas and 2 kilometers on the rest of area from the boundary of the Karera Wildlife Sanctuary. Its management & control is under Field Director of Madhav National Park in Shivpuri district.

Fauna: Black Buck, Nilgai are found in large numbers in the sanctuary and the importantavifauna include Bar headed geese, paradise flycatcher, Demoiselle Grane, Darter, Dabchick, Grey partridge, Rosy pelican, white backed vulture, wiretaited swallow, Tailor bird, Pied Kingfisher, Black headed golden Oriole, white wagtail, white pelican, pintail, combduke, Shoveller, Gadwall, Jacana, Blossom headed parakeet, Mahratta, Woodpecker, Marsh Harrier, Pied Myna, Baya weaver, Grey Horbill, Red Turtle Dove, painted snipe, Purple moorhens and Red creasted pochard vulture etc; The sanctuary is famous for its celebrity inhabitant Indian bustard and is believed to be last refuge of this bird. The studies conducted on the Indian bustard here have revealed that there are three type of bustards found in sanctuary. The three types of bustards you may come across are Indian bustard, bearded bustard and colored bustard.The bustard, locally known as son chidiya or the golden bird and the blackbuck are the two important faunal species at the park, although bustards have not been spotted here since 1994. The Dihaliya lake within the park hosts migratory birds and the initial approval for denotification of the sanctuary required the establishment of a sanctuary consisting of the lake and the government land around it. Dilhaila Jheel(lake) in the Karera Sanctuary is the only water source for its inhabitants. Entirely rainfed, the size and depth of the lake depend on the monsoons each year. Across the waters lies the Dilhaila village whose inhabitants own and use the land forming the lakebed and whose crops have benefited from the guanodeposits of the birds. There are many migratory birds that settle here in the season. In fact, experts have recorded a total of 245 bird species in Karera. There are Barheaded Goose (Anser indicus), Shoveller (Anas lypeata); pintails (Anas acuta),, teals, and gadwalls snoozing in the sun or squatting meditatively in the mud. There are resident water birds too like the black-bellied river terns, egrets, and spoonbills. Other birds found here are herons, Indian robins, as also insects like dragonflies, damselflies, and butterflies. Paradise Flycatcher (Terpsiphone), Demoiselle crane (Anthropoides virgo), Darter (Anhinga rufa), Grey partridge (Perdix perdix), Rosy pelican (Pelecanus onocrotalus), White backed vultre (Gyps africanus), Tailor bird (Orthotomus), Pied kingfisher (Ceryle rudis), Baltimore Oriole (Icterus galbula), White wagtail (Motacilla alba), White pelican (Pelecanus erythrorhynchos), Combduke (Sarkidiornis melanotos), Gadwall (Anas strepera), Jacana (Jacanidae), Blossom headed (Psittacula roseata), Woodpecker (Picidae), Marsh harrier (Circus aeruginosus), Pied Myna (Gracupica contra), Baya weaver (Ploceus philippinus), Grey horbill (Tockus birostris), Red turtle Dove (Streptopelia tranquebarica), Pained snipe (Rostratulidae), Purple moorhens (Porphyrio porphyria);

Flora: The sanctuary contains mixed deciduous forests and acacia is the principal species. There are no trees except acacia throughout this forest. It also has riverine and swamp vegetation within its borders. Ber bushes and other wild plants are found in abundance.

Note: - As per Minutes of the 18th Meeting of the Standing Committee of National Board for Wildlife (NBWL) held on 12th April, 2010 in 403, Paryavaran Bhavan, CGO Complex, Lodi Road, New Delhi- 110003, With respect to, Karera Wildlife Sanctuary, Madhya Pradesh, the Member Secretary informed that Shri. Mahendra Vyas, Member of Rationalization Committee had inspected the site and submitted his report. In his report he had recommended for denotification of the sanctuary subject to the condition that the Government should find out the cause of disappearance of the Great Indian Bustard. The Chief Wildlife Warden, Madhya Pradesh, informed that the bustards were not seen since 1995 and that most of the land inside the sanctuary was private land and people were facing lot of problems. After detailed discussions, the committee agreed to the proposal for denotification of Karera Wildlife Sanctuary. (For MOM Details Refer Appendix 26). 12. Economic The workers Fairly connected Guna district is The gross population The economy of the Isagarh has only Development participation of the town to National rich in black density of Bairad Nagar town is based on some household is worked out to be highway-25 and cotton soil and Parishad is of 678 agriculture. Based on industries, around about 28.5% of the total NH-3, Pichhore is is generally persons per sqkm. As, 2001 census 31.51% 6% of working population in the year a small known as town does not have any workers are involved population is 2011. distribution centre granary of the City Development Plan in agriculture involved in in the region. All region. or master plan; the land household the commercial Economy is use details are not industrial activies. establishments majorly available for Bairad and shops are agrarian with town. However during Trade and located along the 75 percent of the site visit; the commerce: The main roads. The its population predominant landuse village which has informal on-street residing in rural activity is in the form of been very recently markets in the areas. The agriculture sector in upgraded to the town are main crops Bairad. town is increasing at a produced in the The economy of the predominanlty rapid pace. At district are rice, town is based on agricultural in present, they are sunflower, agriculture nature. The nagar functional in wheat, parishad caters to areas near Bus sugarcane, the trading and stand, and along oilseeds and other activities of both sides of maize. the surrounding major roads. Cultivation villages. Weekly Presence of such however is market is also markets leads to largely held in the town. congestion on depended upon streets and on the rainfall. Mandi: the city leaves no space has class D for parking mandi, the various crop produced here are the main source of economic growth of city. The various crops produced here are Sorghum, Wheat, Soyabean, Pulses and Gram crops. The city provides a platform for whole sell of agriculturally activity. These is very important activity of economic growth of town, since there are no major towns near Isagarh, the agricultural produce of there more town areas are brought into Isagarh for sell.

Spread over 17.12 sq. km area Isagarh is a small town, still in the transition phase from rural to urban. Large areas under municipal jurisdiction are still under agricultural use. According to the available land use details, nearly 49% land is under agricultural use 13. Land Use As in City Development Pichhore covers Residential As, town does not have Within the VNP area Spread over Plan the land use a total area of 8 land use in the any City Development agriculture use of 17.12 sq. km area details are not available sq km. owing it to town is Plan or master plan; the land is highest in the Isagarh is a small for Karera town. the fact that approximately land use details are not town i.e. 38.60% town, still in the However, during the site agriculture is a 432 Ha, which available for Bairad which depicts that transition phase visit; the predominant major economy is about town. However, during town is having a rural from rural to landuse activity is in the of the town, but 21.5percent of the site visit; the character. Area under urban. Large form of agriculture the largest the total area. predominant landuse commercial and areas under sector in Karera proportion (5.1 There is no activity is in the form of roads are 7.02% and municipal sqkm) of the total designated agriculture sector in 17.54% respectively. jurisdiction are still town area is area as Bairad. Public and semipublic under agricultural residential and commercial and use is 5.26% and use. According to commercial. use. About 442 area under water the available land Ha areas which bodies and parks is use details, nearly is around 22 3.51% 49% land is under percent area of agricultural use the town has been under transportation. The public semi public buildings take up almost 21 percent area of the town, as compared to recommended 6-8 percent.

14. Agriculture and Karera is mainly an Pichhore is Aron is rich in Agriculture is the main The economy of the Isagarh is an industry agricultural Area and so mainly an black cotton soil occupation of the town is based on agriculture based cultivation is the main agricultural Area and is generally people. The agriculture. Based on economy. It is a occupation of the and so cultivation known as dependence on 2001 census 31.51% local center for people. The is the main granary of the cultivation can be workers are involved agricultural dependence on occupation of the region. viewed from the fact in agriculture. marketing dealing cultivation can be people. The Economy is that 83.38 percent of in agriculture viewed from the fact dependence on majorly the total workers of produce. that 83.38 percent of cultivation can be agrarian with district are engaged in Agricultural lands the total workers of viewed from the 75 percent of agriculture either as are extensively district are engaged in fact that 83.38 its population cultivators (70.40%) or cultivated in the agriculture either as percent of the residing in rural as agriculture labourers area, and cultivators (70.40%) or total workers of areas. The (12.98%). Rice, Jowar, predominant as agriculture labourers district are main crops Bajra, Maize, Wheat crops are wheat, (12.98%). Rice engaged in produced in the and Barley are the main soybean, onion, agriculture either district are rice, cereal crops. Gram & pulses, etc. Main as cultivators sunflower, Tur (Arhar) are the main crop season is (70.40%) or as wheat, pulses grown in the Rabi, and agriculture sugarcane, district, Sugarcane, agricultural is fully labourers oilseeds and condiments and spices; dependent on the (12.98%). Rice, maize. sesamum (til) and monsoon. There Jowar, Bajra, Cultivation linseed are other crops is no canal Maize, Wheat however is of the district irrigation system and Barley are largely in Isagarh, and the main cereal depended upon farmers mainly crops. Gram & on the rainfall. irrigate using the Tur (Arhar) are groundwater with the main pulses their own tube grown in the wells. district, Sugarcane, condiments and spices; sesamum (til) and linseed are other crops of the district 15. Transport Karera town is Pichhore town is The town is well Bairad does not have Vijaypur town is The majority of connected to connected connected to any significant located in North- roads in the town neighboring districts to neighboring surrounding connectivity town lack Eastern part of is narrow and are and important cities by districts areas and rest major national/state District Sheopur. The of limited width of road only. Due to and important of the State by highway near to its town is traditionally less carriage construction of regional cities by road State Highway proximity. It is famous for its wood capacity. The total roads under PMGSY only. Due to 23. Settlements connected by district carving. It is located length of road scheme, accessibility to construction of neighboring the road to the north of on the boundary network in Isagarh city has increased. regional roads town are Pohari tehsil which between Rajasthan including B.T. However, there is no rail under PMGSY connected connects NH-3 located and MP states. roads, cement connectivity. Total road scheme, through major at 50 km to the north of Vijaypur is the concrete roads, length in Karera is accessibility to district roads the town. located near the rough stone 37km. Out of which, city has (MDRs). A total Bairad town does not boundary of paving, WBM 10km, Kacha 6km, increased. of 14.5 km of have any railway Rajasthan State and road, earthen Bituminous 7km, However, there is road length station. The nearest is well connected to road and nearby concrete 14km and no rail exists in the railway station is major towns and SH-10 roads is highway 5km connectivity. Due town. The main located at Shivpuri at 65 cities within 200 Km around 44.20 km. to absence of rail artery of the km away from the town. radius by Road and Traffic in the town connectivity town town is the SH- Major nearest railway Railways. is very limited, population is 23 which station is Gwalior at except on the depended on the passes through distance of 104Km. main highwaythat Jhansi for transit the settlement. The nearest airport is at carries requirement and No clear road Gwalior, which is considerable travelling. Total hierarchy can around 104km from through traffic. road length in be observed. town. Most of the roads Pichhore is About 75 are surfaced with 25km. Out of percent of the concrete, and which, WBM is roads have roads in the outer 3km, Kachha is carriageway areas are mostly 2km, Bituminous width of 3 m, unpaved. is 4km and and 25 percent concrete is 16km. have carriageway width of 2.75 m. The road density is just 0.72 km/sq.km of all types of roads. 16. Sewerage/Sanitation/ City has got open Pichhore town There is no There is no organized At present there is no There is no Drainage drainage system. lacks organized sewerage system in the sewage system in the sewerage Only25 per cent of the underground sewerage town, the present town. The untreated collection and town is covered by open sewerage system in the sewerage generated in or semi treated treatment system drains. During system. As per Aron town. town can be assumed sewage is disposed in the town. rainyseason, all types of common There exists, to be 80% of water into the storm water Households waste flows through the approach, total 1no of Public supplied (around 0.4 drains especially in mainly depend on drain due to which sewerage Toilets and 880 MLD per day) the core area of the individual drains get choked. generated is individual toilets As per information given town. Most of the sanitation Topography of the town nearly 80 % of in Nagar by municipal officials houses in town have systems like pit issuch that there is a water supplied. Parishad area and preliminary site their own flush type latrines, septic normal slope towards S- As per existing with septic visits, town does not latrines with septic tanks etc. Open E and S-W side, hence water supply tanks or soak have underground tank system. defecation is also all the storm water flows status, total pits sewerage network. Only There are number of prevalent in the towards Bus stand sewerage arrangement. 30% of the houses are small water channels project area. Most nallah through small generation by the having latrine facilities. that discharge run-off of the wastewater drains and ultimately town is 0.48mld. Open defication from the surrounding from households mixes with the River Sewage is practices are areas. The town does is let into open Mahuar. It is again a disposed directly predominant in bairad. not have an effective drains, roads and serious concern that into the existing Out of total population, drainage system. vacant sites, the present system of drains or in septic 68% of the population is Vijaypur storm water which ultimately drainage in city does tanks. In most of opting for open naturally drains enters local not segregate the the areas defecation. towards Kunwari stream. Waste sewerage and waste ultimate sewage River. Natural generated in the water line. Karera disposal takes Town doesnot have any drainage is very towns are Nagar Parishad keeps place into the public conveyance efficient due to more collected and on constructing c.c. road side drains. facilities in the form of than gentle slope. disposed by crude roads and drains but it Town mostly has public toilets or open dumping is mostly done in piece open drains and community toilets. method in the & parcels. the mixing of outskirts of the sewage with the towns. drain water is of serious environmental concern. There is no underground sewerage facility in the town. There are total 2280 septic tanks counted at individual level and no community septic tanks in the town. However, mixing of sewerage in to open drains is a wrong practice but it seems that it is socially acceptable here. 17. Solid Waste As per UDPFI As per UDPFI About 8.53 MT Bairad generates 3.5 As in 2011, total Open drainage Management guidelines, the per guidelines, the (approximate) MT of solid waste daily waste generation in system is capita solid waste for per capita solid of solid waste is of which almost 80% is the town is provided in towns the medium category waste for the being collected by the approximately 5.06 for collection and towns is 250gms/day medium category generated municipality and tonnes per day, conveyance of and considering this, towns is every day disposed off. however only 2.5 rain water from the total SW generation 250gms/day and within the tonnes per day is the town. Due to comes around 6.92 considering this, administrative There is no scientific collected by Nagar lack of sewerage tons per day. The the total SW jurisdiction of practice employed for Parishad officials. system, the drains collection coverage of generation Aron town in SWM. Current practice Remaining waste are presently waste in the town is 80 comes around the year 2011. is very primitive and remains uncollected carrying % i.e.5.53 tons of SW is 4.54 tons per The local unhygienic. The waste and is thrown on wastewater collected every day in day. The residents of the is thrown off on the road streets which create including sewage. the town. Out of the collection town generate from the establishment unhygienic condition Since rains are total6.92generated coverage of solid waste at is collected by the street in the town confined only to a waste, 50 per cent waste in the town the rate of sweepers employed by short duration in waste is domestic. is 80 % i.e.3.63 about 304 the Nagar parishad. The monsoon, the Other major waste tons of SW is grams per waste handling is drains mostly constituents are collected every capita per day completely manual and carry wastewater. commercial waste, day in the town. on an average, the sanitary workers Indiscriminate medical waste, There is no which is above have no access to any disposal of solid vegetable waste etc. scientific waste than the hygiene equipment like waste into drains However, chemical processing standard / norm masks or gloves. The is common, due to analysis of system in of 210 grams collected waste is which drains are generated waste yet Pichhore. per capita per disposed off in the often chocked, to be justified. The day (Population nearby open ground creating industrial waste in the range of less declared dumping site. unhygienic total waste generation is than one lakh) There is no waste conditions. almost negligible. There prescribed in processing facility is no scientific waste the manual of available for the city. processing system in Municipal Solid Karera. Waste Management, CPHEEO (Government of India). Since the town is not fully developed and there is no industry within it, presently solid waste generation is not very high. But it would increase in the future as the town is supposed to be developed with time. The scientific and systematic storage of waste at source is not in practice and in the absence of the desirable system of storage of waste at source. In Aron the system of collection of waste is still primitive. 18. Demography and The population trend of The population The population Population is increased Population has According to the literacy Ratio Karera town is given trend of Pichhore trend of Aron from 13,518 in 2001 to increased from 7,954 census, the below: town is given town is given 18,313 in 2011. 35.5% in 1981 to 10,680 in population of below: rate of increase in Isagarh was 1991: 17,000 below: 1991 to 14,556 in 1991: 14,747 population is observed 12,583 in 2011, 2001: 23,500 1991: 11,462 2001 and to 16,964 in 2001: 21,178 in the last decade. 2011. However, the increased from 2011: 28,705of which 2001: 14,891 2011: 28,010 As per the census 2011, rate of increase in 8,238 in 2001, 15,595 are males while 2011: 18,127 Sex Ratio of the sex ratio of Bairad is population is which shows an 13,110 are females as Sex Ratio of the Aron town was 900 is far below the sex fluctuating from increase of 27.7 per report released by Pichhore is found just 910females ratio of state of Madhya 34.27% in 1991 to % over the Census India 2011. 908 female per per 1000 Pradesh is 931. And the 36.29% in 2001 and decade, slightly 1000 male, less males, juvenile sex ratio (0-6 higher growth Sex Ratio of the Karera to 16.54% in 2011. than the state less than the year) is 928 which is rates than the is found 841female per This is because average of 931. state average more than to that of people are migrating previous decade 1000 male that is of 931. state which is 917. to urban areas for of 1991-2001 that considered very low in Literacy rate of Literacy rate of 66% of the total employment, experienced a comparison to state Pichhore city is Aron city is population is literates in livelihood etc. growth of 22%. average of 931 and 79.91 % higher 70.31 % higher the town. Among As per the census The sex ratio is national sex ratio than state than state literates, 60% males 2011, the sex ratio of 903 females per Literacy rate of Karera average of 69.32 average of and 40% females are Vijaypur is 852 is far 1000 males, much town is 80.85 % higher %. In Pichhore, 69.32 %. In literates. Number of below the sex ratio of lower than the Male literacy is Aron, Male literates is more in Ward state of Madhya state average of than state average of around 87.51 % literacy is 14 and less in Ward 6 Pradesh is 931. And 931.With an area 69.32 %. In Karera, while female around 78.69 % the juvenile sex ratio of 17.12 sq. km Male literacy is around literacy rate is while female (0-6 year) is 857 less under the 88.47 % while female 71.55 %. literacy rate is than to that of state municipal limits, literacy rate is 71.78 61.11 %. 917. gross population %. . density is v735 Literacy rate of persons/sq. km, Vijaypur city is 76.01 but this varies % higher than state across the area, average of 69.32 %. as most of this In Vijaypur, Male area is literacy is around undeveloped, and 86.74 % while female in the core area of literacy rate is 63.41 the town, %. Number of population is literates are more in dense. Ward 15 and less in Literacy rate of Ward 10 Isagarh city is 78.50 % higher than state average of 69.32 %. In Isagarh, Male literacy is around 87.74 % while female literacy rate is 68.17 %. 19. Culture and heritage Karera is one of the Pichhore town Aron Fort is an Some of the temples At the bank of Isagarh is very beautiful city of does not have ancient Hanuman temple, Kunwari River, there famous for Shri shivpuridist. Most any potential monument of Shitlamata Temple, stands a 16th century Anandpur Trust beautiful place in Karera heritage site. The the town. The Shiv temple, Kela Devi fort known as providing health is Karera Fort called town does have fort is situated Temple, Sri Krishan Majhola durg. Vijay cares for needy "Karera Ka Killa". A very Pichhore fort but in middle of the Temple, Thakurji Singh, the King of and poor and old temple Shiv temple due to negligence town Temple, Maa Kali , built it. There Isagrah is also and other one is in the past the surrounded by Temple, Thakurji is a two-storeyed famous for Sarbati Hanumaan temple present structure residential area Temple are found in the palace inside the fort, Wheat all over called "Bagicha" is in shows ruins only. and is an site visits. BadriNath which is a fine India.MatajiMandir Karera. There is India's There are several important and Baithamata temple example of of Kaday is very Biggest ITBP caint monuments and landmark. With are famous temple Rajasthani famous and it is support battalion in heritage the passage of exists in the town. architectural style. located at 16 km Karera. There are conserved by ASI time, it is Chhim Chhima from Isagarh and several monuments and in Shivpuri district getting There are several Hanuman Ji temple is other famous heritage conserved by located in Mahua, deteriorated. monuments and about 9 km from temples are ASI in Shivpuri district Surwaya and Conservation, heritage conserved by Vijaypur, on Vijaypur Sankat Maochan located in Mahua, Terahi towns preservation, ASI in Shivpuri district Shivpuri road. It has Hanuman Mandir Surwaya and Terahi which is more restoration located in Mahua, an ancient Hanuman and Kalimata towns which is more that 40 km away efforts need to Surwaya and Terahi Ji statue. In the Mandir. that 40 km away from from the project be planned for towns which is more month of Bhadon There are several the project town Karera. town pichhore this fort to that 40 km away from (August–September) monuments and develop it as a the project town Bairad . a one-day Fair is held heritage tourist attraction which attracts conserved by ASI point. There are thousands of in Ashoknagar number of devotees from nearby district located in Historical districts. town temples within Siddh baba hill, a which is more that the town limits. scenic place is about 43 km away from These are not 2 km from Vijaypur, the project town very famous but on Vijaypur Isagarh. are of religious Sabalgarh road. ASI Monuments importance at Every year in the like JAMA Masjid, regional level. month of January- kati ghati, Koshak These can be February a trade fair Mahal, Badal developed with is held. the initial part Mahal Gateway, associated of the fair is Bada Maarsa activities for dedicated to animal located in promoting fair, in which people chanderi district regional from nearby states 43 kms away from tourism. comes for selling and Isagarh. purchasing animals like Bull, cow, camel etc. in the fair cultural activities like Kavi Sammelan, folk songs, drama, nautanki also takes place. Table 6: Site Environmental Features of Karera Town

Infrastructure Location & Environmental Site Photograph Features Intake well An intake well of dia 6.0m and height 11.50 m is proposed at estern bank of Samoha dam in Mahuar River at Khera Modi Village to abstract the water. The land ownership is with water resource department. The distance of proposed water source is about 13.2 km away from the Karera town located in Khera Modi village on eastern bank of Samoha dam (constructed across Mahuwar River). Dam is used as feeder reservoir for irrigation purpose. Water level in the dam is usually high in the post monsoon season, and recedes with release of water in the period of October /November to January / February. As per local peoples, enough water is available throughout the year at proposed site of Intake well. The gross storage capacity of Samoha dam is 19.552 MCM and Live storage capacity is 18.533 MCM, while the water requirement for the project is 8.30 MLD or 3.03 MCM per year, which is about 16.35%, which is adequate to meet the project yearly demand of the design year.

Proposed intake location is within the boundary of eco sensitive zone, about a distance of around 500m away from the boundary of Karera wildlife Sanctuary as shown in google map annexed as Fig – 24. and as per Site Photograph showing- Final MOEFCC, New Delhi Notification selected location of Intake-well of dated 15th Septmber 2017, eastern bank of Samoha Dam across Commercial Extraction of Surface Mahuwar River at village Khaira Modi Water is regulated under applicable law and as per law NoC from WRD already obtained for water abstraction and construction of intake well on eastern bank of Samoha dam in River Mahuar, which is appended as Appendix 24. Also as per MOEFCC Notification- Construction activities within Eco- Sensitive Zone is permitted as per building bylaws to meet the residential needs of the local residents such as construction and renovation of infrastructure including civic aminities. (Refer Table 3, S. No. 14 & S. No. 20 & Refer MOEFCC Notification annexed as Appendix 25, Para 4, S.No. 14 & S. No. 20). However, it will be done with mitigation measures, as per applicable laws, rules and regulation and available guidelines.

Note: - As per DPR, source of water for subproject water supply town Karera was proposed on western bank of Samoha dam located at Jhanda village. Later on, it was come under notice that proposed location of intake as well as alignment of raw water rising main comes under ecological sensitive area known as Karera Wildlife Sanctuary or Son Chiraiya Bird Sanctuary, Karera which is about 14 Kms. away from subproject town and secondly proposed alignment passes through private land too. Taking into consideration, a joint visit of DBO Contractor, PMU-Gwalior along with PMC was scheduled on 24th January 2018 to resolve this issue and new location has been identified and recommended unanimously by joint team. As preliminary examine shows that newly recommended source is found socially & environment and technically acceptable. As per villagers, enough water is available throughout the year at proposed site of Intake well and enough government land is also available without any encroachment. No Flora and Fauna has been reported in and around the proposed site. Also no environment impact observed at site. Aquatic life in the reservoir is limited to local specifies of fishes, and aquatic plants. There are no notable sensitive features. Since the proposed subprojects components such as Intake, RWRM, works will be limited to actual construction area and the access roads within ROW, but appropriate steps will be taken according to the nature of the risk. Precaution must be taken care to minimize the noise during construction work to avoid any negative impact on bird sanctuary. The impact will be only for limited time during construction work WTP WTP of capacity of 5.7 MLD is proposed in Karera town at existing WTP campus. Proposed WTP site is located on western bank of river Mahuwar at town Karera. NH-27 is also traverses along with proposed site. The proposed location is under the custody of Revenue Department. Site is currently vacant, and covered with shrubs and bushes and sparse tree cover. Khasra No. of land is 1471. Land required for WTP is 0.6 Ha. Available land area is 2.55 Ha. The land is surrounded by the agricultural land. WTP is 500 m away from sanctuary boundary and comes under Eco-sensitive zone within limit of Karera municipal area. Refer google map annexed as Fig – 24. Since the proposed subprojects components such as RWRM, WTP, CWRM, works will be limited to actual construction area and the access roads within ROW, but appropriate steps will be taken according to the nature of the risk. Precaution must be taken care to minimize the noise during construction work to avoid any negative impact on bird sanctuary. The impact will be only for limited time during construction work. Raw water The rising mains of dia 350 mm will be rising mains laid along the RoW. The road is wide (13500 m) enough and of PWD department. There is agricultural land on both side of road. The raw water rising main, connecting intake and WTP, will be partly outside and partly within the town, which will be laid partly within the boundary of ecosensitive zone of Karera wildlife sanctuary and partly outside the ESZ boundary of sanctuary. The proposed RWRM, works will be laid underground and shall be limited to the access roads within ROW, but appropriate steps shall be taken according to the nature of the risk. Precaution must be taken care to minimize the noise during construction work to avoid any negative impact on bird sanctuary. The impact will be only for limited time during construction work. 1000 KL OHT One new 1000 KL OHT is proposed at Khasra No. 1521 in PWD rest house campus. Available land area is 0.648 ha. There is no tree near the site. Trees ar on the periphery of the site, which will not be removed during construction. So, no negative environmental impact. Land is under custody of revenue department and vacant. The land is surrounded by the residential area. The proposed OHT is within the boundary of ESZ of sanctuary within municipal limits. The proposedOHT works will be limited to actual construction area, but appropriate steps will be taken according to the nature of the risk. Precaution must be taken care to minimize the noise during construction work to avoid any negative impact on bird sanctuary. The impact will be only for limited time during construction work. 700 KL OHT One new 700 KL OHT is proposed near Nagar Parishad office. The proposed location is under the custody of Revenue Department. Site is vacant and barren land. Khasra no. of land is 1590/1.Available land area is 1.60 ha. Land is adjacent surrounded by agricultural land. No tree has been reported. Trees are on the periphery of site which will not be removed during construction.

The proposed OHT is within the boundary of ESZ of sanctuary within municipal limits. The proposedOHT works will be limited to actual construction area, but appropriate steps will be taken according to the nature of the risk. Precaution must be taken care to minimize the noise during construction work to avoid any negative impact on bird sanctuary. The impact will be only for limited time during construction work.

500 KL OHT One new 500 KL OHT is proposed near Krishi Mandi at existing OHT site. The proposed location is under the custody of Revenue Department. Site is vacant Khasra no. of land is 475. The land is surrounded by the residential area. The proposed OHT is within the boundary of ESZ of Karera bird sanctuary within municipal limits. The proposed OHT works will be limited to actual construction area, but appropriate steps will be taken according to the nature of the risk. Precaution must be taken care to minimize the noise during construction work to avoid any negative impact on bird sanctuary. The impact will be only for limited time during construction work.

Clear Water The feeder Mains will be laid on the Feeder Mains side of the road. The road in Karera is (Length 4725m) in custody of PWD and Nagar Parishad. There is residential area on both side of the road. CWFM will be laid underground within ROW of main existing road. The clear water rising main, connecting WTP and OHTs, will be essentialy laid within the town and will be within the boundary of ecosensitive zone of Karera bird sanctuary.

The proposedCWFM, works will be laid under ground and shall be limited to the access roads within ROW, but appropriate steps will be taken according to the nature of the risk. Precaution must be taken care to minimize the noise during construction work to avoid any negative impact on bird sanctuary. The impact will be only for limited time during construction work Distribution The distribution network will be laid on network the side of the road. The road in (52799m) Karera is in custody of PWD and ULB. There is residential area on both side of the road.

Pipes will be laid along the roads/streets in the towns within the road right of way (ROW). In wider roads pipes/sewers will be laid in the road shoulder, and in narrow roads, where there is no space, pipes/sewers will be laid in the road carriage. Roads in the old part of the town are quite narrow and pipes will be laid mostly in the centre of the road, which may affect the traffic.

Distribution networks line will be laid will be laid within the town and will be within the boundary of eco-sensitive zone of Karera bird sanctuary. Pipelines, works will be limited to the access roads. Appropriate steps will be taken according to the nature of the risk. Precaution must be taken care to minimize the noise during construction work to avoid any negative impact on bird sanctuary. The impact will be only for limited time during construction work

Figure 23: Proposed WSS Components of Karera Town on Toposheet

Old Location of intake at Jhanda Village as per DPR Proposed New Location of intake at Khera Modi Village

Old Alignment of RWRM as per DPR which comes within the boundary of Karera Bird Sanctuary

Figure 23-1: Proposed WSS Components of Karera Town on Toposheet

Figure 24: Google Map of Karera Wildlife Sanctuary and Subproject Town Karera-Showing the Boundaries of of Both Clearly Along with Location of Main Components (Source/Intake, RWRM, WTP, CWRM & OHTs etc.) as Per DBO Contractor ESZ Boundary of Karera Bird Sanctuary Boundary of Karera Bird Sanctuary

Intake Location 500m away from Boundary of Karra Sanctuary

Raw Water Rising Main

Karera Town boundary limits

WTP Location 500 m away from boundary of Karera Sanctuary

Figure 25: Map Showing Karera Bird Sanctuary and Subproject Karera Town

Table 7: Site Environmental Features of Pichhore Town Infrastructure Location & Environmental Site Photograph Features Raw Water Raw water rising mains of 200mm dia rising mains will be laid along the RoW. The raw (3250m) water rising mains is proposed from intake well to water treatment plant. The rising mains will be laid aling RoW of road. The road is under the custodian of PWD.There is agricultural land on both side of road.

Water Water Treatment Plant of capacity 3.0 Treatment Plant MLD is proposed behind MPEB substation near Warehouse ward no. 13 Khasra No.: 1639/3. Available land area is 2.00 ha and required land area is 0.49 ha. The land is under revenue department and vacant. There is no environmental and ecological feature at the area. Land is surrounded by agricultural land.

200KL GSR A GSR of capacity 200KL is proposed near Hazira Pahadi at Khasra No.: 437. Land area required is 0.09 ha and available land area is 2.10 ha. The land is under revenue department and vacant. There is no environmental and ecological feature at the area.Land is surrounded by agricultural land.Site is covered with shrubs and bushes and sparse tree cover.

250KL GSR A GSR of capacity 250KL is proposed near Kali Mata Mandir at Khasra No: 1650/1 adjacent to existing 200 KL GSR. Required land area is 0.09 ha. The land is under revenue department and vacant. There is no environmental and ecological feature at the area. Site is vacant and barren land. The Existing GSR is proposed to used in upcoming project.Land is surrounded by agricultural land.

Clear Water The feeder Mains will be laid on the side Feeder Mains of the road. The road in Pichhore is in (2450m) custody of Nagar Parishad and PWD. There is residential area on both side of road. CWFM will be mostly laid along the main roads. Pipes will be laid underground.

Distribution Distribution network will be laid along the network (33125 RoW. The road in under custody of PWD m) and Nagar Parishad. There is residential area on both side of road.

Pipes will be laid along the roads/streets in the towns within the road right of way (ROW). In wider roads pipes/sewers will be laid in the road shoulder, and in narrow roads, where there is no space, pipes/sewers will be laid in the road carriage. Roads in the old part of the town are quite narrow and pipes will be laid mostly in the centre of the road, which may affect the traffic.

There is no forest land within the prescribed limit of the town. Hence there is no involvement of Forest land or required any permission for implementing this project. There is no tree cutting involved during construction period.

Figure 26: Proposed Component of Pichhore WSS on Topo Sheet

Table 8: Site Environmental Features of Aron Infrastructure Location & Environmental Site Photograph Features Intake well cum A jack well of dia 6.0m and height jack well 20.00 m is proposed at Sindh River to abstract the water. A wier of length 50.0m and height 5.0m is also proposed to restore the water at the abstraction point. Height of weir is lower than the river banks, and the total storage is 1.50 MCM. Submergence/storage will be confined to river course itself. The banks of the river are much above the HFL, hence there will not be any submergence on the upstream. The overflow from the Weir will pass to the downstream without any hindrance. The land ownership is with water resource department. The distance of proposed water source is about 9km from the Aron town. There is no tree and vegetation at the location of proposed intake well. There is agricultural land adjacent to proposed structure. Aquatic life in the river is limited to local specifies of fishes, and aquatic plants. There are no notable sensitive features. Permission of WRD for abstraction of water and construction of intake well& weir already obtained Refer Appendix 24 WTP WTP of capacity of 4.5 MLD is proposed on Barod road in Aron town. The proposed land area is under the custody of Revenue Department underKhasra no. 950/952/954/955. Land requirement for WTP is 0.39 ha. Available land area is 0.78 ha. There is no tree and vegetation under proposed campus of WTP and land is vacant. Site is surrounded by agricultural land. No tree has been reported, So, there is no tree cutting involved during construction period.

Raw water The rising mains of dia 250mmof rising mains length 8680m will be laid along the (250 m) existing road within RoW. The road is wide enough and of PWD department. There is agricultural area on both side of road. Pipe will be laid underground.

700 KL OHT One new 700 KL OHT is proposed at Khasra No. 1216 in ward-1. There is no tree near the site. So, no negative environmental impact. Land is under custody of revenue department and vacant. Land area required for proposed OHT is 0.03 ha. Available area is 0.32 ha. There is agricultural land adjacent to proposed structure.

Clear Water The feeder Mains will be laid on the Feeder Mains side of the road of dia 150mm/ (Length : 200mm and 250mm. The road in 2550m) Aronis in custody of PWD and Nagar Parishad. There is residential area on both side of road. Clear water feeder main will be laid underground on main existing road within ROW.

Distribution The distribution network will be laid network on the side of the road. The road in (20559m) Aron is in custody of PWD and ULB. Pipes will be laid along the roads/streets in the towns within the road right of way (ROW). In wider roads pipes/sewers will be laid in the road shoulder, and in narrow roads, where there is no space, pipes/sewers will be laid in the road carriage. Roads in the old part of the town are quite narrow and pipes will be laid mostly in the centre of the road, which may affect the traffic.

There is no forest land within the prescribed limit of the town. Hence there is no involvement of Forest land or required any permission for implementing this project. There is no tree cutting involved during construction period.

Figure 27: Proposed Component of Aron WSS on Toposheet Table 9: Site Environmental Features of Bairad Infrastructure Location & Environmental Site Photograph Features Intake cum Reservoir. Land is outside the pump house town, surrounded by agricultural fields. Tree cutting is not involved during construction. Pachipura dam is located on south direction at a distance of around 5 km from Bairad town Land belongs to water resources department. Aquatic life in the location is limited to local species of fishes and aquatic plants. No notable sensitive features are found. Location: In the bed of Pachipura Dam reservoir near Pachipura Village at distance of 0.790 km from proposed WTP. Permission of WRD for water abstraction from Pachipura dam already obtaind which is appended as Appendix 24. WTP-3.17MLD Open field, at present no and OHT-3 of utilization. The site is outside the 225 KL town nearby Pachipura. Neighboring sites are sparsely residential plots and cultivation by farmers. Sufficient land is available for construction of WTP& OHT-3. There is no tree cutting involved during construction period. The land belongs to Revenue Department, Government of MP. Available land area is 12.43 ha. Location: in Pachipura Village, ward no. 15 at Khasra No. 398 around 4 km away from Bairad town..

OHT-2 of 300 Open land within the town, KL surrounded by residential area. Tree cutting is not involved during construction. Land belongs to Revenue Department, Government of MP Location Near Nagar Parishad, ward 9 at Khasra no. 861/1/2/3/4. Available area is 1.08 ha.

OHT-1 of 300 Proposed OHT-1 is located near KL old OHT site in ward no. 5 within the town under Khasra no. 268. Land belongs to Revenue Department, GoMP. Land area available is 0.09 ha. Site is surrounded by residential area. Site is vacant and barren land. Tree cutting is not involved during construction.

Transmission Transmission pipelines will be and distribution mostly laid along the main roads. network Pipes will be laid underground. Pipes will be laid along the roads/streets in the towns within the road right of way (ROW). In wider roads pipes will be laid in the road shoulder, and in narrow roads, where there is no space, pipes will be laid in the road carriage. There are no trees along the roads. In some areas pipes will be laid in the middle of the road, which may affect the traffic. Given the small diameter (about 100 mm) pipes, the trench excavation will be very minimal (0.4 x 0.7m). Tree cutting is not involved during construction.

Figure 28: Proposed Component of Bairad WSS on Toposheet

Figure 29: Google Map of Kuno Wildlife Sanctuary and Subproject TownsBairad & Vijaypur-Showing the Boundaries of Both Clearly Alongwith Location of Main Components(Source/Intake, WTP and OHTs etc Table 10: Site Environmental Features of Vijaypur Infrastructure Location & Site Photograph Environmental Features Proposed Kunwari • River. No utilization at Intake Well River present, only bushes near stop dam are found. Land belongs constructed by WRD to water resources department. • Intake well cum pump house will be built in near stop dam constructed by by WRD, Sheopur in Kunwari river, under the control of Water Resources Department, GoMP.

• Location is outside the town, in Kunwari River. • Aquatic life in the location is limited to local species of fishes, and aquatic plants. • No notable sensitive features are found

Photo of Stop dam Constructed by WRD at Kuwari River WTP - 2.65 On banks • Old pump-house and MLD of watchman shelter exist Kunwari river. in dilapidated condition Survey no within the site. : 22/1 • Small Neem trees exist within the site. Need to be cut for construction of WTP. At present no utilization. • Land is outside of the town, surrounded by agricultural fields. The land belongs to GoMP under possession of ULB and free from encroachment. • Total land area available is 1.223 ha under Khasra no. 22/1 and land area required for construction of WTP is 0.81 ha. Proposed site for WTP and sump well etc. is

located at one place which is adjacent to upstream of river Kunwari. No submergence is reported as proposed site is quite high from HFL of river Kunwari. Construction of Near Old • Land is within the town, OHT 2 with 325 OHT and surrounded by residential KL Capacity WTP, areas and old OHT & Ward-6 WTP premises. • The existing old OHT Survey and WTP will be No: 660 demolished. Debris will be used for reusage and filling low lying areas within the project area • Land belongs to ULB. Required land area is 900 Sqm for OHT construction

Construction of Near • Land is within the town, OHT 3 with Nagar surrounded by bus stand 240KL Capacity Parishad (150m) area on one side office, and vacant on other Ward-12 three sides. • Land belongs to Govt.of Survey MP. No: 57/1 • At present the land is vacant. No tree has been reported within the site.

Transmission In the • Transmission pipelines and town will be mostly laid along distribution the main roads. Pipes network will be laid underground. • Pipes will be laid along the roads/streets in the towns within the road right of way (ROW). In wider roads pipes will be laid in the road shoulder, and in narrow roads, where there is no space, pipes will be laid in the road carriage. There are no trees along the roads. In some areas pipes will be laid in the middle of the road, which may affect the traffic. Given the small diameter (about 100 mm) pipes, the trench excavation will be very minimal (0.4 x 0.7m)

Figure 30:Subproject Area & Environs Showing Proposed WSS Components & Alighnment of Transmission Main– Vijaypur Town

Table 11: Site Environmental Features of Isagarh Infrastructure Location & Environmental Site Photograph Features Clear Water Clear water sump is proposed in Sump the primises of exiting OHT campus. The land is under possession of ULB. Tree cutting is not involved during construction. The land is surrounded by the agricultural land.

Transmission Transmission pipelines will be line and mostly laid along the main roads. Distribution Pipes will be laid underground. network The transmission main leading to tube wells to Clear water sump, and Clear water sump to OHT, the land owned by Govt; this land is vacant, and pipeline will be laid with the permission of ULB. Water from this pipeline will also be provided to ULB premises.

There is no forest land within the prescribed limit of the town.

Distribution network: Pipes will be laid within the road right of way (ROW) - in road’s earthen shoulder in wider roads, and within the carriageway in narrow roads, where there is no space. Roads in the old part of the town are quite narrow and pipes will be laid mostly in the centre of the road. There is no tree cutting involved during construction period. There is residential area on both side of road

Figure 31: Project Area & Environ – Isagarh Town

VI. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

A. Introduction 48. A. Potential environmental impacts of the proposed infrastructure components are presented in this section. Measures to minimize/mitigate negative impacts, if any, are recommended along with the agency responsible for implementation. Monitoring actions to be conducted during the implementation phase is also recommended to reduce impact.

49. Screening of potential environmental impacts are categorized into four categories considering subproject phases: location impacts and design impacts (pre-construction phase), construction phase impacts and operations and maintenance phase impacts.

A. Location impacts include impacts associated with site selection and include loss of on- site biophysical array and encroachment either directly or indirectly on adjacent environments. It also includes impacts on people who will lose their livelihood or any other structures by the development of that site. B. Design impacts include impacts arising from Investment Program design, including technology used, scale of operation/throughput, waste production, discharge specifications, pollution sources and ancillary services. C. Construction impacts include impacts caused by site clearing, earthworks, machinery, vehicles and workers. Construction site impacts include erosion, dust, noise, traffic congestion and waste production. D. O&M impacts include impacts arising from the operation and maintenance activities of the infrastructure facility. These include routine management of operational waste streams, and occupational health and safety issues.

50. Screening of environmental impacts has been based on the impact magnitude (negligible/moderate/severe – in the order of increasing degree) and impact duration (temporary/permanent).

51. This section of the IEE reviews possible project-related impacts, in order to identify issues requiring further attention and screen out issues of no relevance. ADB SPS (2009) require that impacts and risks will be analyzed during pre-construction, construction, and operational stages in the context of the project’s area of influence.

52. The ADB Rapid Environmental Assessment Checklist in http://www.adb.org/documents/guidelines/environmental_assessment/eaguidelines002.aspis used to screen project for environmental impacts and to determine the scope of the IEE

53. In the case of this project (i) most of the individual elements are relatively small and involve straightforward construction and operation, so impacts will be mainly localized and not greatly significant;(ii) proposed water abstraction from the sources is very small compared to overall water availability, and necessary water allocations are being made from Water Resources Department(iii) most of the predicted impacts are associated with the construction process, and are produced because that process is invasive, involving excavation and earth movements; and some works are located in the reservoir and (iv) being mostly located in an urban area, will not cause direct impact on biodiversity values. The project will be in properties held by the local government and access to the project location is through public rights-of-way and existing roads hence, land acquisition and encroachment on private property will not occur. B. Pre-Construction Impacts – Design & Location 54. Design of the Proposed Components. Technical design of the (i) intake facilities for five subproject towns, including Weirat kunwari river for (Aron town only), (ii) water treatment plants; (iii) raw water and clear water mains, (iv) storage reservoirs, and (v) distribution network, connections, flow meters, etc., follows the relevant national planning and design guidelines, focusing on providing a robust system which is easy to operate, sustainable, efficient and economically viable. Besides, the project also included the following environmental considerations;

(i) Continuation of groundwater source for subproject town Isagarh (ii) Conducting a detailed groundwater study and preparation of a groundwater sustainability plan for Isagarh to address the groundwater sustainability issue. It is proposed that the implementation of Source Sustainability Plan will be part of the project and will inter alia include measures like sub-surface dykes; a combination of sub-surface dyke and check dam; check dam; recharge pits; recharge shafts, community roof top rainwater harvesting systems, etc. (iii) Discontinuation of current unsustainable groundwater source and creating a new comprehensive water supply system based on a nearest surface water source for five subproject towns except Isagarh town (iv) Limiting the height of water impounding structures (dams) in Aron to much below the height of the Sindh river banks so that the storage is limited to the river course (v) Recovering wash water from treatment process (vi) Treatment and reuse of sludge from treatment process (vii) Minimizing water losses from pipelines by perfect jointing and alignments using appropriate techniques (HDPE pipes upto150mm dia joined by electrofusion couplers usingon-site electrofusion welding, andall higherdia pipes byon site butt welding) (viii) Designing the entire system to maintain optimal flow and terminal pressure, and optimizing the overall energy usage (ix) Reducing the incidence of water borne diseases by providing100% Population including urban poor with potable waters upplies (x) Improve water use efficiency and reduce water wastage at house hold level by recording and monitoring the water usage, and charging the consumers as per usage; due consideration to urban poor (xi) Minimize unaccounted for water (UFW) losses using district metered area approach with flow meter and pressure logging arrangements to identify and rectify the leaks, and unauthorized connections (xii) Using low-noise and energy efficient pumping systems

55. Selection of water source, Source Sustanability & Impact Association with water Abstraction: Selection of water source is defined as below:

1. Karera: There is possible water source for Karera town:

(i) Extracting Ground Water (ii) Dumghana Dam (iii) Samoha Dam

56. Other than these three options, there is no water body nearby the Karera town to consider as a water source for proposed Water Supply Scheme of town. Ground water level in Karera is very low to supply the water in Town. Water quantity in Dumghana dam not sufficient to supply the water in Karera town for design year 2048. Samoha dam is found adequate source for Karera Water Supply Scheme due to its adequacy in terms of quality as well quantity. After water analysis of Samoha Dam, it is found that all the parameter is beyond the drinking water standard. Samoha Dam is situated in Shivpuri District in Samoha town. Samoha Dam is major irrigation project and serves as a lifeline to the nearby area. It is 13.2 Km from the Town. This is well within the reachable stretch of the town.

57. As per DPR, source of water for subproject water supply town Karera was proposed on western bank of Samoha dam located at Jhanda village. Later on, it was come under notice that proposed location of intake as well as alignment of raw water rising main comes under ecological sensitive area known as Karera Wildlife Sanctuary or Son Chiraiya Bird Sanctuary, Karera which is about 14 Kms. away from subproject town and secondly proposed alignment passes through private land too. Taking into consideration, a joint visit of DBO Contractor, PMU-Gwalior along with PMC was scheduled on 24th January 2018 to resolve this issue and new location has been identified and recommended unanimously by joint team.

58. Team has visited three different places to finalize the location of Intake well cum pump house namely i) Northern Side of Village Khera Modi: this site was found not suitable as impounding water is quite away from the stream and water is shrinking about 250 metre away from intake location during summer as also confirmed by local people, apart from that silting and desilting will cause another obstacle. And secondly it may require acquisition of private land to reach at intake well. ii) At Samoha dam: this site was technically suitable as enough water is available throughout the year but raw water raising main will pass through village Samoha. This village is located on the road and the road passes through the centre of village. A significant number of residential structures reported on both side of road, it is about 1.5 to 2 kms in length and congested too under village Samoha. Proposed raw water rising main will traverse through this road only. Therefore, proposed alignment is socially not acceptable due to its negative impact on road side structure and there might be chance to puncture the water pipeline. Apart from that this location is about 30 kms. away from subproject town. iii) Eastern Bank of Samoha Dam at Village Khera Modi: Another new location as water source is identified on the eastern bank of Samoha dam which is located near a very small hamlet namely Khera Modi under Panchayat Machhawali. This new proposed site is about 13 - 14 Kms away from subproject town. Enough government land is available on the bank of Samoha dam (Mahubar river) which is required for proposed Intake well cum pump house and secondly no involuntary resettlement impact (both permanent and temporary) is envisaged. Among these three new locations as mentioned, joint team has unanimously recommended water source namely “eastern bank of Samoha Dam across Mahuwar River at village Khaira Modi” as per preliminary examine shows that newly recommended source is found socially & environment and technically acceptable. Refer Fig-2- Showing Site Photograph of Recommended & Proposed New Location of Intake Well on Eastern Bank of Samoha Dam. As per villagers, enough water is available throughout the year at proposed site of Intake well and enough government land is also available without any encroachment. This proposed location does not come under Son Chiraiya Bird Sanctuary, Karera. However as per mapping on google earth mapas per available coordinates, new recommended location comes undr Eco-Sensitive Zone of Karera Sanctuary, which is about a distance of 500 m away from the boundary of Karera Bird Sanctuary. No Flora and Fauna has been reported in and around the proposed site. Also no environment impact observed at site.

59. Dam Water Sustainability and Environmental Considerations: The gross storage capacity of Samoha dam is 19.552MCM and Live storage capacity is 18.533 MCM, while the water requirement for the project is 8.30 MLD or 3.03 MCM per year, which is about 16.35%, which is adequate to meet the project yearly demand of the design year. Since Annual average recoupment of water in the tank every year is around 18.533 MCM. While the recoupment of water during rainy season is 19.552 MCM which is 6 times more than the annual water demand of Karera town. It is evident that the dam is full to its crest level at the end of monsoon season (September), which gradually reduced to its minimum in summer and up to the arrival of monsoon flows in June-July.Therefore, the abstraction of 16.35% of gross storage may not anyway effect the irrigation. Permission of WRD already obtained for Karera town which is appended as Appendix 24. So, there will not be any negative impact on Samoha dam due to water abstraction for water supply in Karera as the selected water source is sustainable in terms of quantity. But there will be some negative impact on water quality during the construction of intake well but the impact will be local and temporary.

2. Pichhore: There is there possible water source for Pichhore town • Extracting Ground Water • Futiwar Dam • Nagda Dam 60. Other than these three options, there is no water body nearby the Pichhore town to consider as a water source for proposed Water Supply Scheme of town. Futiwar Dam is selected as adequate source for supplying water in Pichhore town.

61. Ground water level in Pichhore is very low to supply the water in Town. Utavali river is generally dry in summer season, so found not adequate to as water source. At Futiwar Dam, jack well is already constructed to supply the water to Pichhore. So, it is found economic to use the already constructed jack at Futiwar dam.

62. Water Source Sustainability & Environmental Considerations: Subproject town Pichhore do not include development of any new water source or augmentation of the existing source. As per the project design, the existing Futiwar Dam source will be continued as a source for subproject town. Futiwar Dam is constructed across local River having catchment area of 6.37 sq. km and is for drinking and irrigation purpose. Futiwar dam is owned by the WRD.

63. The gross storage capacity of Futiwar dam is 9.24 MCM and Live storage capacity is 4.95 MCM, while the water requirement for the project is 2.90 MLD or 1.06 MCM per year, which is about 21.41%, which is adequate to meet the project yearly demand of the design year. Since annual average recoupment of water in the tank every year is around 4.95 MCM. While the recoupment of water during rainy season is 9.24 MCM which is 4.67/8.72 times more than the annual water demand of Pichhore town. It is evident that the dam is full to its crest level at the end of monsoon season (September), which gradually reduced to its minimum in summer and up to the arrival of monsoon flows in June-July.Therefore, the abstraction of 21.41% of live storage may not anyway effect the irrigation and adequate water is available for irrigation. Permission of WRD already obtained for Pichhore town WSS, which is appended as Appendix 24. There will not be any negative impact on Futiwar dam as no construction work at dam.

3. Aron: There are two possible water sources for Aron town • Underground water source • Sindh River by constructing weir 64. Presently only 0.95 MLD of water is being supplied through ground sources like 2 nos of tube wells, 5 nos of Hand Pumps & 2 nos of open well. These entire sources are giving very less yield. Based on the available data the present tube wells may supply water to the town at the tune of maximum 0.95 MLD. So, underground water to supply the water in Aron for design period. Since Aron town is currently depending on the groundwater, the continuation of same source with augmented supply was examined. As per the Central Ground Water Board (CGWB), groundwater utilization in Aron town is about 36% (of total utilizable resources), and the usage has been increasing rapidly in the recent past. Drying up of existing tube wells, in the summer months is a common feature in Aron. Groundwater therefore is not considered a sustainable source for meeting total projected demand.

65. Sindh River: Besides the existing groundwater source, Sindh River, flow at about 9 km from town, is another potential source of water for Aron. It is situated in Guna Disrtict.Sindh River is a Major river in the Guna District. The River proved to be a major watersource in the past years. Now the river Sindh is not the perennial river. The flow in the river reduced in the month of the November to December and gets dry after January. Rivers almost run dry during the months of February and up to the arrival of monsoon. Sindh River originates in Vidisha District. Total catchments area of the river in Madhya Pradesh is 26699 km² and total length is 470 km. A length of 461 km of the river falls in Madhya Pradesh and 9 km in . Major tributaries of Sindh are Mahuar, Parbati, Pahuj, and Kunwari etc.

66. Requirement of Weir: There are no flow gauging stations in and around 10 km of Sindh river, and therefore no flow records available. After PMC visit of weir location at river sindh, during summer, discussion with the WRD and municipal staff managing water supply, and the local people, indicate that Sindh River is seasonal, and flow for about 6-7 months a year, with very high flows during monsoon. Rivers almost run dry during the months of February – July, and up to the arrival of monsoon. Due to this, as the flow started to reduce from February, and up to the next monsoon season, raw water storage is required to meet the demand of this lean flow season. Hence it is proposed to create a storage in the Sindh river by constructing a small stop dam across the river. Water requirement for the project is 4.10 MLD or 1.50MCM per year, so the period for storage has been taken from February to July i.e. Six Month (180) days, and the storage requirement is estimated as 0.75 MCM.

Requirement of water for 365 days i.e. = 365 * 4.10 MLD 1st January to 31st December (12 months) = 1496 MLD = 1.50 MCM

Requirement of water for 180 days i.e. (06 months) = 1.50/2 = 0.75 MCM 67. For the construction of weir on Sindh River, Barod site near Barod village has been selected considering the distance and also the valley in the Sindh River is quite sufficient for construction of weir and to store the water. Barod village is located in Guna district around 9 Km away from Aron town. At Barod site, Bud River and One Nalla is confluence with Sindh River, getting total fetch (water storage) length is approximately 7.00 Km (3.62 Km of Sindh River, 3.32 Km of Bud River & Nalla). For the selected location of weir, the water catchment area is coming100.22 Sq. Km. and it is marked in Toposheet. The proposed length of weir is 50 m and height is 5 m. 68. Source Water Sustainability and Environmental Considerations: Although the Sindh River is non-perennial and two Streams/Nala i.e. Bud River and one Nala are separate and all are inter connected and main tributary of river Sindh in addition, Sindh River has its separate catchment. Catchment area of Sindh River at village Barod is 100.22 sq km and it is marked on Topo Sheet. (Refer Catchment Area Map & River Network map annxed as Fig - 32 to Fig - 34). With an average of 723.50 mm annual rainfall (75% dependable rainfall), the above catchment can generate significant quantities of runoff every year. The flow is considerable during the monsoon and post monsoon period of June-December/January, and therefore will be able to meet the demand. As the flow started to reduce from November to December and gets dry after January and up to the next monsoon season, raw water storage is required to meet the demand of this lean flow/no flow period. So, it is proposed to construct a weir across River Sindh, on the downstream side of the proposed intake to create a river ponding structure. Even though the river is shallow in many places but the site selected for the proposed weir have deep valley as well as have sufficient cross section to store the water. It is also considered that the dam height should be as low as possible so that the submergence is limited to the river course, and it is found that there shall be no any submergence when the height of weir (stop dam) is kept at 5 m at proposed site on River Sindh. On the basis of area basin survey, it is estimated that this dam will have a storage capacity of 1.26 MCM, which can meet 168% of the above lean period demand, and will be sufficient for about 180 days only. Refer Table –12, given below–Required storage capacity of weir for 06 months of water demand. (For Detailed Hydraulic Design & drawing/maps of Weir Refer Appendix -21)

Table 12: Hydraulic Design of Weir Node No. Length (m) Avg. width Average Storage Unit (Refer Fig- (m) Depth (m) Capacity 29) (m3)

A-D 1450 60 6.27 545490

D-E 2170 40 5 434000

B-C 2070 26 3.2 172224

D-F 1250 25 3.5 109375

Total Storage Capacity for 6940 m Length 1261089 M3

Total Storage Capacity for 6940 m Length 1.26 MCM

Water Demand for 2048 / Day 4.1 MLD

Water Demand for 2048 / Annum 1.5 MCM

Storage Capacity Required for 06 Month of Water Demand 0.75 MCM

Evaporation & Percolation Losses + Water Theft @ 40% 0.30 MCM Total Storage Capacity Required for 06 Month of Water 1.05 MCM

Demand & Losses + Theft

Height of Proposed Weir 5 M

Length of Proposed Weir 50 M

Catchment Area for Weir 100.22 Sq.km

Length of Water Spread Area 6940 M

Lowest Bed Level 464 M

H.F.L. of River from the Bed level of River 6.00 M

69. It is pertinent to mention here that design given in DPR is a tentative one and it has to be finalized based on detailed investigation by DBO contractor. Accordingly, IEE and EMP will be further modified and finalized. As the work has been awarded and contractor has been mobilized, but design & drawings/maps for weir height and capacity is awaited from contractor side. Yet to be submitted.

Figure 32: Proposed Weir Location on Sindh River Showing River Network

Figure 33: Veiw of River Network (Sindh River) Showing Proposed Weir Location

Figure 34: Catchment Area of Well

70. Impacts due to Weir on downstream users and ecosystem: As discussed above the river flow has very high seasonal variation, with significant flows in monsoon – post monsoon to very low flows in summer. The flow in the river reduced in the month of the Nov. to December and gets dry after January up to the next monsoon season. The proposed dam to store the water requirement for the low-flow period of six months is a small stop dam, height (5m from the bed level of the river) of which is lower than the river banks and much below the HFL of the River. The total storage capacity of weir is 1.26 MCM. The height of the dam (5m) to store required water is fixed in such way that top level of structure is well below the High Flood Level of the river as the HFL of the river is 6m from the bed level of river. The banks of the river are much above the H.F.L. of river, as the height of river bank is about 10 m from the bed level of the river (See photographs of River Sindh appended as Fig – 38) and as per contour survey of river Sindh, and map of submergence area, submergence is confined to river course itself. Submergence/storage will be confined to river course itself. (Refer Contour Map & Map of submergence area as the contour map is superimposed on google map of River Sindh annexed as Fig –36 & Fig-37), hence there will not be submergence on the upstream. Dam will be a vented concrete structure, with solid concrete foundation up to sill level, i.e. slightly (~0.1 m) above the river bed level, and above which it will have rectangular open vents with slots to place removable gates up to the required design height; gates will be placed prior to end of high monsoon flows, and will be removed after the onset next monsoon flows as shown in drawings annexed as Fig – 10 to Fig-12. This type of structure allows heavy monsoon flow freely without any obstruction, and also avoids dam silting. This structure impounds water during low or no flow period, and during heavy river flow, gates will be removed. Given very small storage, dam will be filled at the first monsoon flow itself, and will continue to be full throughout the year, and the water coming from the upstream will overflow freely, and flow downstream without any hindrance. Therefore, the change in flow regime due to this small dam will be negligible.

Figure 35: Weir Site C/S at Sindh River

Figure 36: Contour Map of Sindh River

Figure 37: Map of Submergence Area - Showing River Course and weir Location in Sindh River as the River Contour Plan Superimposed on Google Map

Figure 38: View of Deep Vally of Sindh River from Proposed Intake Location

71. There is no notable, protected or unique aquatic life in the river, and the fish is limited to local varieties (such as Dingra, Roh, Paril, and Loch and water snakes). There is no commercial fishing taking place in this stretch of the river. There are also no notable water abstraction points or users in the downstream of the dam. Two natural streams joins Sindh River within 1 to 2 KM in upstream from the proposed dam location. Out of two, one stream join from left side (i.e. B-C – Bud River) and other streams joins Sindh River from right side (i.e. D-F – Nalla) with respect to direction of flow of the river. All these streams are the natural drains that carry the runoff generated by the rainfall in this area. There is no such industry or town situated in this patch of river, only few agriculture fields are found. As there will be notable change in the river flow regime, no impacts envisaged on downstream users or river ecosystem. The proposed impoundment, in fact, is likely to benefit the environment through groundwater recharge and propagating aquatic life.

72. Sindh River Water Quality & Pollution Sources: Sampling has been done at the intake location for testing of water quality of source (Refer Table 16, below). The results are compared with the drinking water standards. Owing to presence of coliform (in the range of 46 to 49 nos against Nil), the surface water needs to be treated before supplying to the public. There are no notable pollution sources in the upstream of proposed dam. There are two natural streams join Sindh River with in the 1-2 km in upstream from the proposed intake location. All these two streams join Sindh River from left and right side with respect to direction of flow of the river. All these streams are naturally formed and flow with runoff form surrounding areas in the rainy season only. The water quality of these streams is quite good as there in no habitation nearby these streams. Besides, in this five kilometers stretch of river, neither tributary nor industry is found. Current water quality is suitable for drinking water after conventional treatment and disinfection, and as there are no notable pollution sources in the upstream near the intake, there is no likely risk of source contamination. However, there is a need to check on future development to avoid contamination of source.

4. Bairad Town: The following water sources are identified for water supply scheme for Bairad town. • Pachipura Dam • Bairad Talab 73. Bairad Talab is located at 1.5 km north of the Bairad town. It can also be one of the prominent source of water supply for Bairad Nagar Parishad. According to municipal officials, water availability is limited in Bairad Talab especially during summer season. Hence on priority and long term basis, therefore Bairad Talab is not considered a sustainable source for meeting total projected demand.

74. Pachipura Dam Water Sustainability and Environmental Considerations: Pachipura Dam is located at south direction of Bairad town. It is located at distance of 5 km from the town. Dam is constructed across Paar River having catchment area of 89.75 sq. km and is for drinking and irrigation purpose. Dam is owned by the WRD. The gross storage capacity of Pachipura dam is 10.47 MCM and Live storage capacity is 8.32 MCM, while the water requirement for the project is 2.91 MLD or 1.06 MCM per year, which is about 12.75%, which is adequate to meet the project yearly demand of the design year. Since live storage capacity is 7.85 times more than the annual water demand of Karera town. Therefore, the abstraction of 12.75% of live storage capacity may not anyway effect the irrigation. Permission of WRD already obtained for Bairad town which is appended as Appendix 24.

75. The following are the salient features of Pachipura Dam given in Table 13, below.

Table 13 :Salient Features of Pachipura Dam S. No Hydraulic Particulars Value

1 Tank Bund Level (TBL) 411.01 m 2 Maximum Water Level (MWL) 409.01 m 3 Full Tank Level (FTL) 407.75 m 4 Lowest Supply Level (LSL) 403.01 m 5 Catchment Area 89.75 Sqkm 6 Maximum Discharge 566.31 Cum/sec 7 Full Capacity of Reservoir 10.47 Million Cum 8 Live storage capacity 8.32 Million Cum 9 Dead storage 2.15 Million Cum

76. Water Quality of Pachipura Dam: The catchment area is mostly characterized by agricultural and barren lands, and forest areas. There are no polluting sources like industries or mining in the catchment areas. Habitations are limited to small villages, there is no major city located in the catchment. Conventional water treatment and disinfection which is proposed in the project is adequate to make the water usable for drinking purposes. A regular water quality regime needs to be established for checking the raw water quality. The water supplied to the consumers at all-time must meet the drinking water standards (Appendix 5). Water quality testing has been done at the proposed intake location in Pachipura Dam. The results are compared with the drinking water standards. The water needs to be treated before supplying to the public. For Water Quality Results Refer Table 16, given below.

5. Water source and source Sustainability- Vijaypur

77. Source Identification: Kunwari River is a river and surface water body passing through the Vijaypur town. On up stream of Vijaypur town, Water Resource Department (WRD) has been constructed a stop dam / river ponding structure for storage of water and it is completed. Earlier days during 1974s also Kunwari River was used as water supply source to town and built WTP due to lack of proper maintenance the scheme was discontinued. The same is proposed as source of water supply. Discussions were held with water resources department officials at Sheopur about the source of water supply scheme to the town. Officials informed and confirmed that a stop dam for storage of water so the same can be used as source of water and this proposal is accepted by officials.

78. Kunwari River: It flows through Sheopur Morena and districts of Madhya Pradesh in central India. The start or origin place of the river is located at Devpura village Sheopur.Kunwari is a tributary of Sindh River and joins it in Etawah District. Sindh River joins Yamuna River further down the stream at pachnada. The river flow is not fast. Towns like of Sheopur district and of are located along its bank.The River Sindh is originated in Malwa Plateau in Vidisha District of MP joins Yamuna River in Etawah District of UP. The river flows for a length of 470km, having catch ment of 26,699 Sqkm. River Flow: Discussion with the WRD and municipal staff managing water supply, and the local people, indicate that Kunwari River is with very high seasonable flow variations and flow ceases during summer season, passes through Vijaypur. The river flow is not fast. A river gauging station is located on this river at Budhara village, downstream of the proposed intake location. Observed Daily Discharge Data for Kunwari River was collected from WRD, Government of Madhya Pradesh for last 5 years from year 2011-12 to 2015-16 and analyzed. The summary is given below. Raw data received from WRD is attached as Appendix 23.

Table 14: Analysis of River Flow Data - Kunwari Flow (cumecs) June June 2012- June 2013- June 2014- June 2015- 2011-May May 2013 May 2014 May 2015 Dec 2015 2012

Minimum 0.76 3.19 1.11 1.98 0.63

Maximum 56.71 686.74 327.37 40.54 90.65

Ultimate demand of 2.65 the town (ML) Ultimate demand in 0.033(cumec) considering 22 hour pumping Source: Data from WRD, Government of Madhya Pradesh.

79. Finalization of Source: After discussion with Executive Engineers, Water Resources Department and it is observed that minimum flow in Kunwari River in last 5 years is 0.054MCM per day and the water required for Vijaypur town is 0.88MCM (2.41 MLD) for ultimate year 2048. Hence the Kunwari River is a sustainable water source for the proposed water supply scheme.

80. Location of Proposed Intake Well, Source Sustainability and Environmental Considerations: Water Resource Department has already constructed a river ponding structure at Vijaypur for water storage agricultural purposed having catchment area of 745 Sq.km.After discussion with WRD officials about the proposal of water supply scheme for Vijaypur and construction of Intake well at Kunwari River on upstream of the river ponding structure(having 4.0 m height and length 155 m recently constructed by WRD) for the ultimate year water demand to draw raw water from from the same and also Request for allotment of water for the proposed scheme was sent by Vijaypur ULB alongwith water allotment application form to WRD for their approval. NOC from WRD for abstraction of water and construction of intake well already obtaind which is appended as Appendix 24.

81. The live storage capacity of existing weir which is recently constructed by WRD is 0.93MCM, while the water requirement for the project is 2.41 MLD or 0.88MCM per year, which is about 94.62%. which is adequate is adequate to meet the project yearly demand of the design year and also from the river Discharge Gauge data analysis it is observed that the flow variation in the river is significant over the seasons. As presented in the above Table 14, in the last five years, the highest flow recorded was 687 cumecs (29th Aug 2012) while the lowest was 0.63 cumecs (On Sept 27th 2015). Considering minimum flow is higher than the ultimate requirement (0.033 cumecs with 22 hour pumping) of Vijaypur, Kunwai River is adopted as source of water for Vijaypur water supply scheme. Table 15: Existing Weir Recently Constructed by WRD at the proposed Intake Well Location Live Catchment River Ponding Height Storage Area (Sq. Over Length Width (m) Structure/ Stop (m) Capacity Km) River (m) Dam Location (MCM) Top Bottom Kuwari 0.93 745 Vijaypur River 155 1.5 7.4 4

82. Impacts on Downstream Users and Ecosystem: There is one dam ‘Barda Dam’ (at a distance of 10 km) on upstream of the proposed stop dam. River Bansral meet at a distance of approx. 5 km on upstream of the proposed stop dam. There are no notable downstream uses on the river as the river flows down and joins the River Sindh River, which again carries considerable flow, therefore impact of flow reduction will be negligible. The quantity of water abstraction from the river is insignificant compared to the availability of water. There is no notable, protected or unique aquatic life in the river, and the fish is limited to local species of fishes and aquatic plants. There is no commercial fishing taking place in this stretch of the river. Notable water abstraction points or users are not there in the downstream of existing dam. No natural stream/drain join Kunwari River within 5 km downstream/upstream stretch from the existing dam location. There is no industry or town (except villages Dulhawala, Barkheda, Aroda on bank of river on upstream side & Sunwai village on d/s side) situated in this stretch of river, some agricultural fields are found on both sides of the river. On left bank side of river. Open scrub is found both on u/s & d/s. While on right side, protected forest is there at a distance of approx. 6 km on downstream side. As there will not be any notable change in the river flow regime, Therefore, no impacts are envisaged on downstream users or river ecosystem or aquatic life.

83. Source water quality (Kunwari River) & pollution sources. Three days of sampling has been done at the intake location (Near old pump house) for testing of water quality of source. The results are compared with the drinking water standards. Owing to presence of coliform (in the range of 21 to 25 nos against Nil), the surface water needs to be treated before supplying to the public. The habitation on banks of river on u/s side might be the reason for presence of coliform & E-coli. Open scrub is found on left hand side of the river on upstream side. There are no notable pollution sources in the upstream of proposed dam. In site visit it is observed that no natural streams join Kunwari River on upstream & downstream side within the 5 km stretch from the proposed stop dam/ intake location. Besides, in this five kilometers stretch of river, neither any Nala nor Industry is found. It was observed that Gota protected forest is there approximately at a distance of 6 km on right side of the river (downstream side) & Open scrub is found on left side (both on u/s & d/s) of proposed stop dam. Currently water quality is suitable for drinking purpose after conventional treatment and disinfection, as there are no notable pollution sources in the upstream near the intake, there is no likely risk of source contamination. However, there is a need to check on future development to avoid contamination of source.

84. Surface Water Quality of Sources for Karera, Pichhore, Aron, Bairad & Vijupur Towns WSS Subprojects: The catchment areas of all the towns are mostly characterized by agricultural and barren lands. There are no polluting sources like industries or mining in the catchment areas. Habitations are limited to small villages, there is no major town located in the catchment. Water quality test report of Samoha Dam, Futiwar Dam and Pachipura Dam, Sindh River and Kunwari River are appended in Table 16 & Appendix 18. All the parameters of water quality in comparison with drinking water standards are well within the limits, hence Convention water treatment and disinfection, which is proposed in the project, is adequate to make the water usable for drinking purposes.

Table 16: Surface Water Quality of Karera, pichhore , Aron, Bairad and Vijaypur Towns Parameter Samoha Futiwar Sindh Pachipura Kunwari Drinking Dam for Dam for River Dam for River water Karera Pichhore for Bairad for standards* Aron Vijaypur 4.4 2.3 to 5-10 1. Turbidity, 1.8 1.5 1.6 NTU 2.7 Color, Hazen units 10.33 2.56 to 5-25 Nil Nil Nil 2.88 pH 8.19 8.22 to 6.5-8.5 7.29 7.45 7.5 8.66 Electrical conductivity 464.3 280 to 750 2000 262 323 Nil – (µs/cm) 295 Total dissolved solids 260 178 to 500-2000 138 184 Nil (mg/l) 188 Total alkalinity (mg/l) 98.7 62.1 to - 74 108 160 69.3 Chlorides as Cl (mg/l) 52.81 16.49 to 250-1000 10 18 26 21.49 Total hardness as 139.04 91.74 to 300-600 98 114 250 CaCO3 (mg/l) 96.74 Calcium (mg/l) 41.4 28.51 to 75-200 22.8 24.32 180 29.55 Magnesium (mg/l) 8.51 10.78 to 30-100 Nil 12.76 70 12.99 Iron (mg/l) 0.862 0.106 to 0.3 1 0.03 0.75 Nil – 0.116 Fluoride (mg/l) 0.744 0.41 to 1-1.5 0.20 0.04 Nil 0.51 Nitrate (mg/l) 5.17 2.88 to 45 1.0 1.2 1.2 3.44 Sulphates (mg/l) 16.78 28.37 to 200-400 12.8 26.3 50 32.27

6. Isagarh Town: Water source and source Sustainability

85. Selection of Water Source: To meet future requirements of water, the investigation works for surface source for the town is carried out by DPR Consultant with their field technical staff jointly with ULB local leaders and sub engineer on dated 28-11-2015.On local as well as through Google map inquiry It is come to know that there is neither perennial or non perennial river flowing within the vicinity of 30 km around this Town and hence there is no possibility of getting surface source from any river on technoechonomical basis and aspect. On further investigation it is found that there is a big lake adjoining to the town namely SING SAGAR UPPER LAKE as a surface source but it can not be adopted as a source for drinking purpose as it is a big lake to be conserved by the government. This lake is very blessing for recharging and improving the ground water condition. The area of this lake is about 53.40 hectare.

86. Taking into consideration that there is no dependable surface water source in the proximity of the town, it is proposed to continue the groundwater source for Isagarh water supply by utilizing existing Tube Wells which are seems to be very promising source.

87. Proposed Project Components: It is proposed to develop a groundwater based water supply system consists of abstraction of groundwater from 16 tube wells existing and pumping into sumps, disinfection with chlorine, pumping to overhead tanks, and distribution from OHTs

88. For finalizing source issue Geohydrologiest has been appointed by design consultant and after his thorough investigation and on receipt of final opinion, itis finally concluded only after Geological report for utilizing the underground source confirming with its reliability and sustainability for the Town. Ground water yield analysis is given in Table 17, below. Also Refer Appendix 19 for yield test report & existing tube wells details;

Table 17: Details of Existing Tube Wells – Isagarh Town Details of Existing Tube wells & Pumping Machine

Dated 29.11.2015 During Summer Minimum Discharge Consideraration

ULB ULB

Level Level

S. No. No. S.

Ultimate Ultimate

Ward No. No. Ward

Discharge Discharge

Flow test/ Flowtest/

prospective prospective

investigation investigation

Intermediate Intermediate

=1000Ltr/20Hr =1000Ltr/20Hr

=1000Ltr/16Hr =1000Ltr/16Hr

=1000Ltr/14Hr =1000Ltr/14Hr

machain of life life of machain

Pumping Water Water Pumping

Dia of Tube Well Well Tube of Dia

Installed Pumping Pumping Installed

1000Ltr/Hr. As per per As 1000Ltr/Hr.

Total Depth in Feet Feet in Depth Total

yearpumping hours hours yearpumping

yearpumping hours hours yearpumping

yearpumping hours hours yearpumping

Minimum Discharge Discharge Minimum 1000Ltr/Hr. given by by given 1000Ltr/Hr. a b c d e f g h i j k 1 1 350 6 270 12 1980 6 84 96 120 2 1 256 4 180 12 2003 6 84 96 120 3 2 305 6 205 12 2001 6 84 96 120 4 2 298 6 192 12 1985 6 84 96 120 5 2 271 6 206 12 1990 6 84 96 120 6 2 290 6 155 12 2008 6 84 96 120 7 2 288 6 190 12 2009 6 84 96 120 8 2 312 6 180 12 2010 6 84 96 120 9 5 307 8 146 12 1998 6 84 96 120 10 7 249 8 208 12 2001 6 84 96 120 11 11 258 6 210 12 1986 6 84 96 120 12 13 291 4 184 12 1986 6 84 96 120 13 13 285 4 225 12 1988 6 84 96 120 14 13 264 4 115 12 1990 6 84 96 120 15 13 230 6 101 12 2000 6 84 96 120 16 15 198 6 90 12 2007 6 84 96 120 Note: Reviewing of Existing Tube well data it is advisable to go for new tube wells replacing of Machinery older Total 1344 1536 1920 existing older than 1990.

a) For Normal condition ➢ Proposed Source calculation for Intermidiate year = Total -16 Tube well x 12000 lit./Hrs. Discharge (in summer) x 7hr =1344 M3 = 1.34 MLD ➢ Proposed Source calculation for prospective year = Total -16 Tube well x 12000 lit./Hrs. Discharge (in summer) x 8hr =1536 M3 = 1.54 MLD ➢ Proposed Source calculation for Ultimate year = Total -16 Tube well x 12000 lit./Hrs. Discharge (in summer) x 10hr =1920 M3 = 1.92 MLD b) For Critical condition in Summer

➢ Proposed Source calculation for Intermidiate year = Total -16 Tube well x 6000 lit./Hrs. Discharge (in summer) x 14hr =1344 M3 = 1.34 MLD ➢ Proposed Source calculation for prospective year = Total -16 Tube well x 6000 lit./Hrs. Discharge (in summer) x 16hr =1536 M3 = 1.54 MLD ➢ Proposed Source calculation for Ultimate year = Total -16 Tube well x 6000 lit./Hrs. Discharge (in summer) x 20hr =1920 M3 = 1.92 MLD

89. Groundwater Study Methodology: As per CGWB report 2013; study was conducted at two stages: one, to identify areas of interest (or target areas) in the study area, and two, to conduct detailed exploration of target areas. Groundwater behavior in the region is quite erratic and the distribution of groundwater resources is not uniform. Moreover, the areas of high groundwater potential are highly localized. Such areas are isolated on the basis of remote sensing studies and were subject to further detailed exploration by surface geophysical methods.

90. Ashok Nagar District is characterized by variety of geological formations representing vast period of geological time. Predominant Geological Formations are Granite, Vindhyan Sandstone & Shale and Deccan Trap is also encountered in the area. The hydrogeological map of the district is presented in figure 39. The hydrogeological properties of different formations are discussed hereunder

91. Hydrogeology of the study area comprises the whole area is covered by Alluvium Deccan Trap I.e. Basalt rock. From surface to 10 m to 20 m depth weathered rock found and there may be possibility of water. After that solid basalt rock may found up to 45 m depth and there is no possibility of water. Between 45 m to 55 m depth intertrappean i.e. loose formation found that may be collapsible so use over there casing for protection of bore. After that solid basalt rock is found between 100 m to 120 m depth fractured rock may be found, there may be possibility of water. The upper kaimur formation sandstone and quartzite.

92. Alluvium: Alluvium of Quaternary age occurs as a narrow belt along the major rivers like Sindh, Betwa, Kethan & Orr. It comprises pebble beds, gravel, silt & sand. In the area occupied by alluvium, the ground water occurs under water table condition. The granular portion of this formation such as sand & gravel forms good aquifers, but the thickness is shallow. The yield of the wells in this formation ranges from 2 to 7 lps. The principle aquifers in the area are constituted by Vesicular Basalts and fractured zones in Basalts and inferred Sedimentary at a depth and beyond, with varying thickness of 5 m onwards. 93. Deccan Trap: Deccan trap basalts of Malwa Group of Cretaceous to Paleozoic age occupy major part of the district. Intertrappean of lacustrine or fluviatile origin occur in the top part of each lava flow. Deccan trap consists of number of basaltic lava flows.

94. Water bearing capacities in Deccan trap formation differ from flow to flow. weathered basaltic layer is extensive, a continues aquifer can be traced to some distance, however due to low permeability of the weathered basalt the aquifer sustains limited ground water withdrawal. The groundwater at deeper levels occurs under semi confined to confined conditions in vesicular, jointed & fractured basalts. Unit draft of the wells varies from 0.001 to 0.008 m cm/year for dug wells & 0.005 – 0.017 m cm/yr

95. Vindhyan Formation: The Sandstone intercalated with Shale beds are exposed in the northeastern parts of the district (Isagarh Block). The rocks are hard & compact, but at places and at different depth it is fractured & jointed and forming potential aquifer at deeper levels. The ground water occurs under semi confined to confined conditions and are being exploited through bore wells. The yield of these bore wells is fairly good ranging between 1.0 to 4.9 lps. The depth to water level during pre monsoon period ranges from 3.70 to 22.10 m.bgl. with seasonal fluctuation of 0.07 to 9.98 m

96. Archeans: The Archeans rocks are represented by the Bundelkhand Granites in the district and occurring in northeastern portion of the Chanderi block. The intensity of the weathering is varying from place to place. The intensity of the weathering is high and formation of the deep residum or mantle overlying the hard granite in the low lying, intermountain & depressions. The weathered mantle of the granite forms sometimes-good aquifers at a shallow depth, where ground water occurs under water table condition. The yield of this formation ranges from less than one to 3 lps.

97. Under the Ground Water Exploration Programme CGWB has constructed the exploratory wells & observation wells of 96 to 201.30 m deep. The depth to water levels in these wells varies from 8.25 to 51.40 mbgl and discharge of the wells ranges from 0.5 to 11.5 lps with a drawdown of 28.00m. Figure 39: Hydrology, Isagarh Block under District Ashok Nagar (M.P.)

98. As per the CGWB Northern Central Region, Bhopal 2013 report it is reveal the Isagarh of Ashoknagar district is falls under Vindhyan Formation observed. Pre monsoon water level (May 2012) ranging from 12 to 16 mbgl and Post monsoon (Nov. 2012) ranging from 5 to 10 mtbgl as shown in Fig- 40 & Fig- 41. Long term water level trend in 10 years from 2003 to 2012; Rise is 0.01 to 0.05 m/year andFall - 0.01 to 0.14 m/year. Normal rain fall is 927.1 mm. Maximum rainfall received from June to Sept it is about 91.50 % of the annual rainfall. While 8.5 % received from Oct to May. The surplus water for ground water recharging is available during June to Sept. In this region expected yield of Tube wells is 1.0 to 4.90 lps.

Figure 40: Depth of Water Level – Pre-Monsoon (May 2012) in District Ashok Nagar (M.P.)

Figure 41: Depth of Water Level – Post-Monsoon (May 2012) in District Ashok Nagar (M.P.)

99. Ground Water Resource for Isagarh: Block wise Groundwater Resources has been calculated for the base year 2011 on the basis of GEC’97. Over all ground water development of the Isagarh block is 43% and the Isagarh block fall in safe category of ground water development, in which the project town Isagrah is situated.Net Ground water availability is 103.01 MCM.Existing ground water draft for all uses is 43.99 MCM and allocation for the domestic and industrial use upto year ‘2033 are 6.07 MCM respectively. The Ground Water Resource for Isagarh block is given in Table-18, below.

Table 18: Ground Water Source – Isagarh Block Assessm Sub-unit Net Existin Gross Existin Provision Net Stage of ent Unit Command/ Annual g Gross Ground g for Ground Ground Non- Ground Ground Water Gross domestic, Water water Command/ Water Water Draft for Groun and Availability Developme Availabili Draft Domesti d industrial for future nt (%) ty (ham) for c & Water requireme irrigation d Irrigatio Industri Draft nt supply developme n (ham) al water for All to next 25 nt (ham) Supply uses year (ham) (ham) (2033) (ham)

Command ------Isagarh Block Non- 10301 3923 476 4399 607 5770 43 Command

Block 10301 3923 476 4399 607 5770 43 Total

Source: CGWB Report of Isagarh Block under Ashok Nagar District 2013

100. Groundwater Sustainability. As per CGWB report 2013, the net groundwater availability is 103.01 MCM and provision for domestic, and industrial requirement supply to next 25 years (2033) is 6.07 MCM, while the water requirement for the project upto design period is 1.68 MLD or 0.61 MCM per year, which is about 10.05%, which is adequate to meet the project yearly demand of the design year. Since provision for domestic and industrial use is 9.95 times more than the annual water demand of Isagarh town. Ground water is potable and sufficient to fulfill the demand of town upto year 2048, because natural recharging is available by means of lake namely “Sing Sagar Upper Lake” adjacent to the town. The area of this lake is about 53.40 hectare. This lake is very blessing for recharging and improving the ground water condition. Hence existing tube wells proposed as water source for water supply project up to year 2048.In the proposed project existing tube wells are sufficient for year 2048, hence on construction of tube well no any expenditure proposed.

101. Overexploitation of groundwater resources i.e. abstracting more than the net annual ground water available in the area will lead to several environmental and economic issues. Abstracting water from static water resources may lead to contamination due to geo-hydro chemical processes, and may also lead to land subsidence. Tube wells will dry up quickly, with falling water table pumping costs will go up, and the effect on competing uses can cause social conflicts.

102. Given that there is no reliable surface water source in the proximity of the town, even though groundwater development in the project area is already in safe stage as per the groundwater development, it is proposed to continue the groundwater as source of water supply. The present groundwater development is at 43%, and the groundwater is the only source of water in the region for agricultural and domestic purposes. CGWB cautions use of groundwater resource over 90% of net available resources, and recommends linking water abstraction in these areas to water conservation measures like augmenting groundwater recharge through artificial measures.

103. The location of tube wells are identified through a scientific groundwater study, and therefore it is most likely that the yield will be as estimated by the study. The groundwater yield will however depend solely on the annual rainfall. Given the climate change effects, the rainfall is becoming more erratic and unpredictable, combined with increasing frequency of extreme weather events. The project should therefore account for these.

104. The groundwater study recommends a further detailed study to look into groundwater sustainability and to suggest various measures as detailed above in the para. Implementation of these measures is crucial for sustainability of this water supply project and therefore should be integrated into the project implementation.

105. Besides the above, the following measures are suggested for consideration during the detailed study and implementation appropriately:

• Creation of artificial recharge pits in public places / public buildings. Local body can issue a notification to this effect. • Household level artificial recharge (like roof top rainwater harvesting) should be encouraged. • Groundwater regulation – all the tube wells in houses in Isagarh to be discontinued in a phased manner once the project is implemented.

106. Groundwater quality. The pH values of water samples varied in between 6.8 to 7.33 hence proved alkaline in nature and were within permissible limit. All the values are within the permissible limit (Refer Table 19, below). The existing groundwater shows the presence of (i) nitrates at a concentration nearing the prescribed limit (1.0 – 1.4 mgh/l while the prescribed limit is at 45 mg/l), and (ii) bacteriological contamination. Nitrate pollution can be attributed to sewage disposal including human excreta, animal wastes and runoff from agricultural areas. Bacteriological contamination can be directly linked to indiscriminate sewage disposal and the leaching of leachates from latrine pits, open defecation etc. Detailed study proposed in the above paragraph also includes a source protection plan. Measures as suggested by the study should be included in the project. Besides, the groundwater study also recommends the following measures for construction of tube wells, which needs to be included in the project design: • The annular space between the casing pipe and the wall of the bore well must be sealed with cement slurry in order to prevent groundwater contamination • A 1m x 1m x 1m concrete block is to be constructed around the exposed casing pipe above the surface. The block will be 50 cm above the ground and 50 cm below the ground to holdfast the casing pipe. • The top of the casing pipe should be at least 90 cm above the ground or above the reported HFL of the site, whichever is higher. • Suitable measures to be taken to prevent contamination of source since the water quality may be impacted by untreated sewage flowing nearby; suitable provisions should be made for lining of drains and prevention and chocking / overflow / lateral and vertical seepage. • In addition to the above, measures should be taken to control the open defecation, and to close all unsafe latrines (for example pit latrines). • Awareness programs shall be conducted regarding the sanitation practices and its effect on groundwater quality

Table 19 : Ground Water Quality Isagarh Town

Parameter Tube well Tube well- 2 Tube well- Tube well- 1. Drinking -1 3 4 water standar ds* Temperature, :C 27 27 27.5 26.9 - Turbidity, NTU 1.0 1.1 1.5 1.4 5-10 Color, Hazen units Nil Nil Nil Nil 5-25 pH 7.33 7.0 7.10 6.8 6.5-8.5 Electrical conductivity 750 2000 751 689 678 662 – (µs/cm) Total dissolved solids 500-2000 450 414 406 398 (mg/l) Total alkalinity (mg/l) 320 330 300 220 - Chlorides as Cl (mg/l) 60 54 110 40 250-1000 Total hardness as 300-600 360 320 390 280 CaCO3 (mg/l) Calcium (mg/l) 96 88 116 68 75-200 Magnesium (mg/l) 28.8 24 24 26.4 30-100 Iron (mg/l) 0.35 0.52 0.48 0.63 0.3 – 1 Fluoride (mg/l) 0.16 0.04 0.03 0.02 1-1.5 Nitrate (mg/l) 1.2 1.2 1.4 1.0 45 Sulphates (mg/l) 28.8 26.3 30.2 23.8 200-400 Total Coliform / 100ml Nil Nil Nil Nil 10 Thermo tolerant coliform - Nil Nil Nil Nil / 100 ml Source: Sampling survey 2015 by design consultant Team; samples collected from tube wells *standards prescribe lower and higher values for parameters, except pH; lower value is the ‘desirable limit’ while higher value is the ‘permissible limit in the absence of alternate source’; there is only lower value for parameters which have no relaxation

107. Use of Chlorine as disinfectant. It is proposed to use chlorine at WTP to disinfect the water prior to supply to consumers. There is invariably a safety risk when chlorine is handled. Although facilities are not located close to habitations, safety precautions are necessary to ensure the safety of workers and citizens. To avoid any risk, the chlorination facility will be provided with the following: • Chlorine neutralization pit with a lime slurry feeder • Proper ventilation, lighting, entry and exit facilities • Facility for isolation in the event of major chlorine leakage • Personal protection and safety equipment for the operators in the chlorine plant • Provide training to the staff in safe handling and application of chlorine; this shall be included in the contract of Chlorinator supplier • Supplier of Chlorinator equipment shall provide standard operating manual for safe operation and as well as maintenance and repairs; preferably these shall be provided both in English and Hindi Languages

108. Sensitive Project Locations– For Bairad and Vijaypur towns; Kuno Wildlife Sanctury which is also known as Palpur - Kuno Wildlife Sanctuary is situated at a distance of 10 km from Bairad and 24 km from vijaypur town. None of the proposed subproject components are located within the boundary of Kuno wildlife sanctuary nor in its ecosensitive zone. Refer Google Map of Kuno wildlife sanctuary and subproject towns; showing the boundaries of both clearly alongwith location of main components i.e. Source/intake, WTP & OHTs etc. which is appended as Fig – 29

109. For Karera Town - There is one ecological sensitive area known as Karera Wildlife Sanctuary of “Son Chiraiyya Bird Sanctuary”. It is approx. 14 km away from the Karera town. The boundary of Karera Wildlife Sanctuary is about a distance of 500 m away from the boundary of Karera municipal areas. All the proposed subproject components like intake, WTP, OHTs, RWRM, CWRM & distribution networks are within the boundary of Eco-Sensitive Zone (ESZ) of Karera wildlife sanctuary as shown on Google Map (as per coordinate given MOEFCC Notification 15th September 2017) of Karera wildlife sanctuary and subproject town Karera; showing the boundaries of both clearly along with location of main components i.e. Source/intake, WTP & OHTs etc. which is appended as Fig – 24. All the components like Intake, WTP & OHT are located about 500 m – 2 km away from the boundary of Karera wildlife sanctuary. Intake well is located around 13.2 km away from Karera town. Intake well is about 500 m away from boundary of Karera bird’s sanctuary and comes under Eco-Sensitive zone (ESZ). Commercial Extraction of surface water within Eco Sensitive Zone is regulated under applicable Law (Refer Table 3, S. No. 27). Also NoC from WRD for abstraction of water from Samoha dam and construction of intake already obtained (Refer Appendix 24). The raw water rising main, connecting intake and WTP, will be partly outside and partly within the town, which will be laid partly within the ecosensitive zone boundary and partly away from the ESZ boundary of sanctuary. Raw water & clear water rising main will be laid underground from the intake well intake to WTP and from WTP to OHTs site along an existing road within ROW. WTP, OHTs and clear water rising main is located within the municipal limits of Karera Nagar Parishad, but it is within the boundary of ESZ of Karera sanctuary, WTP is about 500 and OHTs are about 1km to 2km away from the boundary of Karera wildlife sanctuary, where there are no sensitive environmental features. Construction activities within the Eco-Sensitive Zone is permitted as per building byelaws to meet the residential needs of the local residents such as construction and renovation of infrastructure including civic aminities (Refer Table 3, S. No. 14 & S. No. 20 & Refer Appendix 18, Para 4, S. No. 14 & s. No. 20- MOEFCC Notification, New Delhi 15th Sep 2017). However, it will be done with mitigation measures, as per applicable laws, rules and regulation and available guidelines. Precaution must be taken care to minimize the noise during construction work to avoid any negative impact on bird sanctuary. The impact will be only for limited time during construction work.

110. Also consultation conducted with forest official on dated 10.05.2018 at Office of Chief Conservator of Forest & Director, Madhav National Park, Shivpuri as Its management and control is under Field Director of Madhav National Park (Refer Appendix 7 & Appendix 10). Detailed discussions held and briefed about proposed components under water supply scheme for Karera town within eco-sensitive zone and its impact on Karera bird Sanctuary. They told that they have no objection as this project is to meet the daily residential needs of the local residents by providing with a constant supply of better quality water as the subproject will improve the overall environmental quality of the town and surrounding areas.

111. Karera Wildlife sanctuary today has not a single bird species. Owing to villagers/public pressure and the extinction of the bird locally, the National Board for Wildlife and the Government of Madhya Pradesh have decided to denotify the sanctuary and is seeking the Centre's approval. The decision is now awaiting a final approval from the Supreme Court of India and should it come through, the sanctuary will become the country's first such reserve to lose its official recognition.

112. As per Minutes of the 18th Meeting of the Standing Committee of National Board for Wildlife (NBWL) held on 12th April, 2010 in 403, Paryavaran Bhavan, CGO Complex, Lodi Road, New Delhi-110003, With respect to, Karera Wildlife Sanctuary, Madhya Pradesh, the Member Secretary informed that Shri. Mahendra Vyas, Member of Rationalization Committee had inspected the site and submitted his report. In his report he had recommended for denotification of the sanctuary subject to the condition that the Government should find out the cause of disappearance of the Great Indian Bustard. The Chief Wildlife Warden, Madhya Pradesh, informed that the bustards were not seen since 1995 and that most of the land inside the sanctuary was private land and people were facing lot of problems. After detailed discussions, the committee agreed to the proposal for denotification of Karera Wildlife Sanctuary, subject to following conditions. (For Details of MOM of NBWL Refer Appendix 25).

113. Since the proposed subprojects components such as Intake, RWRM, WTP, CWRM, OHTs and Distribution Lines works will be limited to actual construction area and the access roads, but appropriate steps should be taken according to the nature of the risk. This should involve: • No construction material storage/ancillary works shall be conducted in the forest area; this shall be limited to actual construction area and the access roads • No labour camps shall be located near forests (maintain minimum 1km buffer) • Limit the work to daylight hours only; no work after sunset • No workers /personnel shall enter forest areas; it is the DBOC responsibility to take necessary precautions & prevent workers removing/damaging trees/vegetation, hunting animals • Create awareness among workers on environment & safety • No high noisy works shall be conducted • Barricade the construction area properly so that no wild animals entre the work area.

114. Utilities.Telephone lines, electric poles and wires, water lines within the proposed project locations may require to be shifted in few cases. To mitigate the adverse impacts due to relocation of the utilities, the contractor, in collaboration with ULBs will (i) identify the locations and operators of these utilities to prevent unnecessary disruption of services during construction phase; and (ii) instruct construction contractors to prepare a contingency plan to include actions to be done in case of unintentional interruption of services.

115. Site selection of construction work camps, stockpile areas, storage areas, and disposal areas: Priority is to locate these near the project location. However, if it is deemed necessary to locate elsewhere, sites to be considered will not promote instability and result in destruction of property, vegetation, irrigation, and drinking water supply systems. Residential areas will not be considered for setting up construction camps to protect the human environment (i.e., to curb accident risks, health risks due to air and water pollution and dust, and noise, and to prevent social conflicts, shortages of amenities, and crime). Extreme care will be taken to avoid disposals near forest areas, water bodies, or in areas which will inconvenience the community.

116. Site selection of sources of materials. Significant quantities of coarse aggregate and fine aggregate will be required for construction works. Requirement of gravel is limited. Contractor should procure these materials only from the quarries permitted/licensed by Mines and Geology Department. Contractor should, to the maximum extent possible, procure material from existing quarries, and creation of new quarry areas should be avoid as far as possible. It will be the construction contractor’s responsibility to verify the suitability of all material sources and to obtain the approval of Department of Mines & Geology and local revenue administration.

C. CONSTRUCTION IMPACTS 117. Pipeline laying works. Civil works in the project include linear excavation for laying pipes along the roads, placing pipes in the trench and refilling with the excavated soil. The trenches will be of 0.4 m – 0.7 m wide and 0.8 to 1.0 m depth. Subsequent to completion of works, road reinstatement will be undertaken by the contractor as part of the civil works. The roads in the core city area of both the towns are very narrow and congested with pedestrians and vehicles, while the roads in outer areas are wide.

118. Earth work excavation will be undertaken by mostly manually due to narrow roads. Pipe laying works will include laying pipes at required gradient, fixing collars, elbows, tees, bends and other fittings including conveying the material to work spot and testing for water tightness. Sufficient care will be taken while laying so that existing utilities and cables are not damaged and pipes are not thrown into the trenches or dragged, but carefully laid in the trenches. As trenches are a maximum of 1 m deep, there is no risk of collapse of trenches or risk to surrounding buildings. Once they are laid, pipes will be joined as per specification and then tested for any cracks of leakages. The minimum working hours will be 8 hours daily, the total duration of each stage depends on the soil condition and other local features. About 95% of the excavated soil will be used for refilling the refilling the trench after placing the pipe and therefore residual soil after pipe laying and refilling is not significant. This soil shall be used for construction work at other sites.

119. Although construction of these project components involves quite simple techniques of civil work, the invasive nature of excavation and the project locations in the built-up areas of the town where there are a variety of human activities, will result in impacts to the environment and sensitive receptors such as residents, businesses, and the community in general. These anticipated impacts are temporary and for short duration.

120. Other construction works. Other civil works in the subproject include construction of tube wells, water tanks, installation of chlorination units, pumping stations, at the identified sites. These works will be confined to sites, and construction will include general activities like excavation for foundation, construction of foundations, columns, walls and roof in cement concrete and masonry, and fixing of mechanical and electrical fixtures, etc. Tube wells will be constructed using a small drilling rig (mounted on mobile truck) to make small tunnel vertically down into the aquifer, into which lengths of 400-500 mm diameter PE pipe are gradually inserted. Jack well cum pump housewill involve construction within the water body. An enclosed area (about 10 m dia) will be created at the selected site using temporary barriers like sand bags or sheet piles and the water will be pumped out to make the area dry for construction. Once this is created, the rest of the construction will follow the general construction procedures to create a RCC well of size 6 m diameter. Once the work is over, the temporary barriers will be removed.

121. Sources of Materials. Significant amount of sand and coarse aggregate will be required for this project. The construction contractor will be required to: • Use material sources permitted by government; • Verify suitability of all material sources and obtain approval of PIU; and • Submit to PIU on a monthly basis documentation of sources of materials. 122. Air Quality. Emissions from construction vehicles, equipment, and machinery used for excavation and construction will induce impacts on the air quality in the construction sites. Anticipated impacts include dusts and increase in concentration of vehicle-related pollutants such as carbon monoxide, sulfur oxides, particulate matter, nitrous oxides, and hydrocarbons. These however will be temporary, limiting to construction activities only. To mitigate the impacts, construction contractors will be required to:

• Damp down exposed soil and any stockpiled material on site by water sprinkling; • Use tarpaulins to cover sand and other loose material when transported bytrucks; • Clean wheels and undercarriage of haul trucks prior to leaving construction site • Disallow access in the work area except workers to limit soil disturbance and prevent access by barricading and security personnel • Fit all heavy equipment and machinery with air pollution control devices which are operating correctly

123. Surface Water Quality: Run-off from stockpiled materials and chemical contamination from fuels and lubricants during construction works can contaminate downstream surface water quality of the streams. As the rainfall in the project areas is mostly confined to monsoon, these potential impacts are short-term and temporary. However, to ensure that these are mitigated, construction contractor will be required to:

• All earthworks be conducted during the dry season to prevent the problem of soil run-off during monsoon season; • Pipeline works along stream shall be conducted during the no flow period. All the works should be completed including proper refilling and consolidation of refilled trench and site restoration prior to onset of monsoon in June. • Avoid stockpiling of earth fill especially during the monsoon season unless covered by tarpaulins or plastic sheets; • Prioritize re-use of excess spoils and materials in the construction works. If spoils will be disposed, only designated disposal areas shall be used; • Install temporary silt traps or sedimentation basins along the drainage leading to the water bodies; • Place storage areas for fuels and lubricants away from any drainage leading to water bodies; • Dispose any wastes generated by construction activities in designated sites; and • Conduct surface quality inspection according to the Environmental Management Plan (EMP).

124. Construction of Anicut andintake well in the reservoir may lead degradation of water quality due to increase in turbidity and chemical contamination from fuels and lubricant used in construction work. Increase in silt content and water turbidity, chemical quality can affect the aquatic life, silting/chocking of spill ways/ canals etc., Though there are no notable aquatic life, to ensure that any negative impacts are mitigation, the contractor will be required to:

• Select a construction methodology that is least disturbing, and appropriate for the in-situ soil condition, and able to complete the construction work prior to onset of monsoon • Schedule the construction works during low water level period – late winter months to pre monsoon (February – June/July); ensure that works are completed during the same period to prior to onset of monsoon; confirm with dam authorities on release of water; avoid scheduling the works during water release period. • Erect temporary barriers to form enclosed construction area with least disturbance • Allow adequate time settle the distributed solids to prior to pumping out water; only clear/clarified water shall be pumped back into the reservoir; any silt laden water should be pumped to a silt pond • Avoid/minimize use of fuels, chemicals and lubricants; ensure no spillage

125. Generation of Construction Wastes. Solid wastes generated from the construction activities are excess excavated earth (spoils), discarded construction materials, cement bags, wood, steel, oils, fuels and other similar items. Domestic solid wastes may also be generated from the workers’ camp. Improper waste management could cause odor and vermin problems, pollution and flow obstruction of nearby watercourses and could negatively impact the landscape. The following mitigation measures to minimize impacts from waste generation shall be implemented by the contractor:

• Prepare and implement a Construction Waste Management Plan • Stockpiles, lubricants, fuels, and other materials should be located away from steep slopes and water bodies; • Avoid stockpiling any excess spoils. Excess excavated soils should be dispose to approved designated areas; • Domestic solid wastes should be properly segregated in biodegradable and non- biodegradable for collection and disposal to designated solid waste disposal site; • Residual and hazardous wastes such as oils, fuels, and lubricants shall be disposed in disposal sites approved by local authorities; • Prohibit burning of construction and domestic waste; • Ensure that wastes are not haphazardly dumped within the project site and adjacent areas. • Get approval of PIU in writing that the necessary environmental restoration work has been adequately performed before acceptance of work.

126. Noise and Vibration Levels.Except Tubewells in Isagarh, water intake and WTP, all the construction works will be conducted at selected sites and along the roads in all these six towns urban areas, where there are houses, schools and hospitals, religious & historical places and small-scale businesses. The sensitive receptors are the general population in these areas. Drilling tube wells will produce noise and vibration in considerable levels, the noise generation may be in the range of 85 – 98 dBA, which is damaging to human ear if experienced for long period. Increase in noise level may be also caused by excavation, particularly breaking of cement concrete or bitumen roads, operation of construction equipment like concrete mixers. Vibration generated from construction activity, for instance from the use of pneumatic drills, will have impact on nearby buildings and monuments. This impact is negative but short-term, and reversible by mitigation measures. The construction contractor will be required to:

• Plan activities in consultation with PIU so that activities with the greatest potential to generate noise are conducted during periods of the day which will result in least disturbance; • Horns should not be used unless it is necessary to warn other road users or animals of the vehicle’s approach; • Minimize noise from construction equipment by using vehicle silencers, fitting jackhammers with noise-reducing mufflers, and use portable street barriers to minimize sound impact to surrounding sensitive receptor; and • Maintain maximum sound levels not exceeding 80 decibels (dBA) when measured at a distance of 10 m or more from the vehicle/s. • Identify any buildings at risk from vibration damage and avoiding any use of pneumatic drills or heavy vehicles in the vicinity; • Provide personal protection equipment (ear plugs) to the rig operators and other staff engaged in supervision of rig

127. Surface and Groundwater Quality. Another physical impact that is often associated with excavation is the effect on drainage and the local water table if groundwater and surface water collect in the voids. In Isagarh groundwater is deeper than the proposed excavation depths, and rains are limited to monsoon. However, to ensure that water will not pond in pits and voids near project location, the construction contractor will be required to conduct excavation works in non-monsoon season to the maximum extent possible. Drilling operation for tube well construction will generate a slurry material (water mixed with clay/earth). This material should be disposed in the following manner:

• Hold the slurry material in a temporary ditch for some time to allow sedimentation of solids, and dispose the clear water in the stream. • Dispose appropriately or use the solid material in construction

128. Accessibility. Excavation along the roads, hauling of construction materials and operation of equipment on-site can cause traffic problems. Roads in the core/old town areas of Isagarh are very narrow. However, most of the roads are used by pedestrians, bicycles and two wheelers. Four wheelers vehicles are very limited. Potential impact is negative but short term and reversible by mitigation measures. The construction contractor will be required to:

• Confine work areas along the roads to the minimum possible extent; all the activities, including material & waste/surplus soil stocking should be confined to this area. Proper barricading should be provided; avoid material/surplus soil stocking in congested areas – immediately removed from site/ or brought to the as and when required • Leave spaces for access between mounds of soil; • Provide walkways and metal sheets where required to maintain access across for people and vehicles; • Plan transportation routes so that heavy vehicles do not use narrow local roads, except in the immediate vicinity of delivery sites; • Schedule transport and hauling activities during non-peak hours; • Locate entry and exit points in areas where there is low potential for traffic congestion; • Keep the site free from all unnecessary obstructions; • Drive vehicles in a considerate manner; • Coordinate with Traffic Police for temporary road diversions, where necessary, and for provision of traffic aids if transportation activities cannot be avoided during peak hours • Notify affected public by public information notices, providing sign boards informing nature and duration of construction works and contact numbers for concerns/complaints.

129. Wherever road width is minimal, there will be temporary loss of access to pedestrians and vehicular traffic including 2 wheelers during the laying of pipes. Under those circumstances, contractor shall adopt following measures:

• Inform the affected local population 1-week in advance about the work schedule • Plan and execute the work in such a way that the period of disturbance/ loss of access is minimum. • Provide pedestrian access in all the locations until normalcy is restored. Provide wooden/metal planks over the open trenches at each house to maintain the access.

130. Socio-Economic – Income. The project components will be located in government land and there is no requirement for land acquisition or any resettlement. Construction works will impede the access of residents to specific site in limited cases. The potential impacts are negative and moderate but short-term and temporary. The construction contractor will be required to: • Leave spaces for access between mounds of soil; • Provide walkways and metal sheets where required to maintain access across for people and vehicles; • Increase workforce in the areas with predominantly institutions, place of worship, business establishment, hospitals, and schools; • Consult businesses and institutions regarding operating hours and factoring this in work schedules; and • Provide sign boards for pedestrians to inform nature and duration of construction works and contact numbers for concerns/complaints. • Notify community/ water users in advance about likely interruptions in water supply. • Provide alternate sources of clean water until water supply is restored.

131. Socio-Economic – Employment. Manpower will be required during the 24-months construction stage. This can result in generation of temporary employment and increase in local revenue. Thus potential impact is positive and long-term. The construction contractor will be required to:

• Employ at least 50% of the labour force, or to the maximum extent; and

132. Occupational Health and Safety. Workers need to be mindful of the occupational hazards which can arise from working in height and excavation works. Potential impacts are negative and long-term but reversible by mitigation measures. The construction contractor will be required to:

• Comply with all national, state and local labour laws (see Appendix 6); • IFC’s General EHS Guidelines3 and Sector Specific (Water and Sanitation) Guidelines4

3 https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B- %2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES • Develop and implement site-specific occupational health and safety (OH&S) measures including: (a) prevent entry of public into construction sites; (b) ensue all workers are provided with and use personal protective equipment; (c) OH&S Training5 for all site personnel; (d) documented procedures to be followed for all site activities; and (e) documentation of work-related accidents; • Ensure that qualified first-aid is provided at all times. Equipped first-aid stations shall be easily accessible throughout the site; • Provide medical insurance coverage for workers; • Secure all installations from unauthorized intrusion and accident risks; • Provide supplies of potable drinking water; • Provide clean eating areas where workers are not exposed to hazardous or noxious substances; • Provide H&S orientation training to all new workers to ensure that they are apprised of the basic site rules of work at the site, personal protective protection, and preventing injuring to fellow workers; • Provide visitor orientation if visitors to the site can gain access to areas where hazardous conditions or substances may be present. Ensure also that visitor/s do not enter hazard areas unescorted; • Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas; • Ensure moving equipment is outfitted with audible back-up alarms; • Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and • Disallow worker exposure to noise level greater than 85 dBA for duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively.

133. Community Health and Safety. Hazards posed to the public, specifically in high- pedestrian areas may include traffic accidents and vehicle collision with pedestrians. Potential impact is negative but short-term and reversible by mitigation measures. The construction contractor will be required to:

• Plan routes to avoid times of peak-pedestrian activities. • Liaise with PIU in identifying risk areas on route cards/maps.

4 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B- %2BWater%2Band%2BSanitation.pdf?MOD=AJPERES

5 Some of the key areas that may be covered during training as they relate to the primary causes of accidents include (i) slips, trips and falls; (ii) personal protective equipment; (iii) ergonomics, repetitive motion, and manual handling; (iv) workplace transport; and (v) legislation and responsibilities. Training can provide the foundations of competence but it does not necessarily result in a competent worker. Therefore, it is essential to assess staff competence to ensure that the training provided is relevant and effective. Supervision and monitoring arrangements shall be in place to ensure that training has been effective and the worker is competent at their job. The level of supervision and monitoring required is a management decision that shall be based on the risks associated with the job, the level of competence required, the experience of the individual and whether the worker works as part of a team or is a lone worker. • Maintain regularly the vehicles and use of manufacturer-approved parts to minimize potentially serious accidents caused by equipment malfunction or premature failure. • Provide road signs and flag persons to warn of on-going trenching activities.

134. Central parts of the towns are characterized by narrow roads and some of which are accessible only by foot/two wheelers. Besides impeding the access, the trench excavation and pipe laying will pose safety risks to pedestrians, and the people living in these areas. Though the width (~400 mm) and depth (~700 mm) of trench is minimal, it will pose safety risk, especially for children and elders The construction contractor will be required to:

• Provide prior information to the local people about the nature and duration of work • Conduct awareness program on safety during the construction work • Undertake the construction work stretch-wise; excavation, pipe laying and trench refilling should be completed on the same day • Provide barricades, and deploy security personnel to ensure safe movement of people and also to prevent unnecessary entry and to avoid accidental fall into open trenches

135. Work Camps. Operation of work camps can cause temporary air and noise pollution from machine operation, water pollution from storage and use of fuels, oils, solvents, and lubricants. Potential impacts are negative but short-term and reversible by mitigation measures. The construction contractor will be required to:

• Consult PIU before locating project offices, sheds, and construction plants; • Minimize removal of vegetation and disallow cutting of trees; • Provide drinking water, water for other uses, and sanitation facilities for employees; • Ensure conditions of liveability at work camps are maintained at the highest standards possible at all times; • Prohibit workers from hunting wild animals and cutting of trees for firewood; • Train employees in the storage and handling of materials which can potentially cause soil contamination; • Recover used oil and lubricants and reuse or remove from the site; • Manage solid waste according to the following preference hierarchy: reuse, recycling and disposal to designated areas; • Remove all wreckage, rubbish, or temporary structures which are no longer required; and • Confirm to PMU report in writing that the camp has been vacated and restored to pre- project conditions before acceptance of work.

136. Debris disposal. Prior to the commencement of works, contractor shall identify a debris disposal site in consultation with the PIU and adhering to following criteria:

• The site shall be selected preferably from barren, infertile lands. In case agricultural land needs to be selected, top-soil stripping, stacking and preservation should be undertaken prior to initiation of any activities. • Debris disposal site shall be at least 200 m away from surface water bodies6.

6 In the absence of site meeting the stipulated criteria, an alternate site can be selected specifying the reasons. In such a case, the construction camp management plan should incorporate additional measures specific to the site as suggested by the Construction Manager. • No residential areas shall be located within 100 m downwind side of the site. • The site is minimum 250 m. away from sensitive locations like hospitals, religious places, ponds/lakes or other water bodies. • The local governing body and community shall be consulted while selecting the site.

137. Asbestos Materials.Existing water distribution network is mostly asbestos cement (AC) pipes, and because of the health risks these will be left in situ and replaced by new pipes. Plan pipeline alignments carefully to avoid any conflict or damage.

138. The above impacts are typical for construction in urban areas, and therefore are common to all the six subproject towns. These are negative but short-term and reversible by mitigation measures. There are well-developed and proven measures and construction practices to avoid, mitigate and/or minimize these impacts to acceptable levels. These measures are given in the construction phase EMP applicable to all six towns.

D. OPERATION & MAINTENANCE IMPACT 139. The DBO Contractor will carry out operation and Maintenance of the water supply system for 10 years, and after which the respective municipalities will operate and maintain the infrastructure. During the system design life (15/30years for mechanical/civil components),it shall not require major repairs or refurbishments and should operate with little maintenance beyond routine actions required to keep the equipment in working order. The stability and integrity of the system will be monitored periodically to detect any problems and allow remedial action if required. Any repairs will be small-scale involving manual, temporary, and short-term works involving regular checking and recording of performance for signs of deterioration, servicing and replacement of parts. 140. Recurrence of pipe bursting and leakage problems can be managed by the leak detection and water auditing surveys. The ULBs will be required to ensure that the leak detection and rectification time is minimized.

141. For Isagarh town - Regular groundwater monitoring to be conducted to ensure the quality of groundwater suitable for drinking after disinfection. If the groundwater quality is deteriorated, the immediate steps to be taken to change the source or creating appropriate treatment facilities.

142. Since back water is recovered and recirculate in the WTP, no wastewater will be generated from water treatment process. The sludge generated from the wash water storage tank, and sedimentation tanks

143. Provision for recirculation system for filter backwash – backwash water from filter beds will be sent to a storage tank, and after allowing adequate time for settlement of solids, clarified water will be pumped to WTP inlet. This arrangement will avoid pollution and also minimize wastage of water. Water treatment process will generate sludge from sedimentation of particulate matter in raw water, flocculated and precipitated material resulting from chemical coagulation, residuals of excess chemical dosage, plankton etc; and waste from rinsing and back washing of filter media containing debris, chemical precipitates, straining of organic debris and plankton. Accumulated sludge from Tube Settler, filter backwash etc., will be disposed-off at sludge drying beds for natural drying. Dried sludge will be disposed off in a land fill or used as soil conditioner if it is suitable

144. The citizens of the Karera, Pichhore, Aron, Vijaypur, Bairad and Isagarh Nagar Parishads will be the major beneficiaries of the improved water supply system, as they will be provided with a constant supply of better quality water, piped into their homes at an appropriate pressure. The project will improve the over-all health condition of the town as water borne diseases will be reduced, so people should spend less on healthcare and lose fewer working days due to illness, so their economic status should also improve, as well as their overall health. This should also improve the environment of these areas, should deliver major improvements in individual and community health and well-being

145. During the construction phase, there are likely to be positive impacts through employment generation, increase in local revenue from the project activities. During the operation phase also, there is potential for employment generation, though limited, as the improved and expanded water infrastructure requires additional workforce.

VII. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

A. Overview 146. The active participation of stakeholders including local community, NGOs, and the media in all stages of project preparation and implementation is essential for successful implementation of the project. It will ensure that the subprojects are designed, constructed, and operated with utmost consideration to local needs, ensures community acceptance, and will bring maximum benefits to the people. Public consultation and information disclosure is a must as per the ADB policy.

147. Most of the main stakeholders have already been identified and consulted during preparation of this IEE, and any others that are identified during project implementation will be brought into the process in the future. Primary stakeholders of the subproject are: residents, shopkeepers and businesspeople who live and work alongside the roads in which network improvements will be provided and near sites where facilities will be built (WTP and water tanks), and government and utility agencies responsible for provision of services in towns. Secondary stakeholder are: NGOs and CBOs working in the area, community representatives, beneficiary community in general, government agencies, the executing and implementing agencies (UDED, PMU and PIUs), Government of India and the ADB.

148. The public consultation and disclosure program is a continuous process throughout the project implementation, including project planning, design and construction.

B. PUBLIC CONSULTATION 149. The public consultation and disclosure program is a continuous process throughout the project implementation, including project planning, design and construction.

a) Consultation during Project Preparation:

Table 20: Summary of Stakeholder Consultation - Karera Town Date Locati No. of Participants Topic Discussed Issues/ concerned on Participant Raised s 16th at ULB Total = 34 CMO, • Water Supply Project • The area has Sep2 office, M=29, F=05 Chairman- Background, insufficient and ULB, Environmental, Social, inadequate drinking 015 Karera Elected GRM, traffic safety water resource. Water Representa issue and benefit from supply to the area is tives, ULB the project were done through tube Staff, Sub explained to the wells and untreated Engineer, Stakeholders. water supply to the Assistant • Location of community people. Revenue components of • People informed about Inspector proposed water very less water supply (ARI), Local Supply scheme has in town in comparison Leader and been finalized with to standard. Local identification of • All the existing water People government land. structure nearby town • Condition of all the has been identified and existing component of Samoha dam has been the water supply has selected for source of been reviewed for water supply in Karera. their further uses in • Funding and Tender proposed water supply Process of this Project. scheme. • Cost of this project; • Need for and project cost improvements to participation of Central present system; Govt. and State Govt. • Land use and area to in to the project. be covered under the • Implementing agency; project and better /improved • Relevant information service. of the upcoming • Operation and project and benefits of maintenance of the the project. facilities developed • Potential positive and under the project and negative impacts due community to project participation; implementation Ensuring no income • Probability of keeping loss the poor and the • Informed to the vulnerable out of the residents about the user charge. proposed 24 X 7 piped • People requested for water supply scheme selection of good including WTP and contractor to speed up water connections to the construction work. individual HHs in all the wards of town ensuring quality and reliability of services. 10th At Total = 10 Sub • About proposed water • Proposed component May Office M=10, F=00 Divisional supply subproject for (Intake well, RWRM, Officer town Karera - WTP & OHTs) being 2018 of (SDO), SDM, Background, its located in within ESZ of Chief Chief components, Karera bird sanctuary Conser Conservator locations, provisions, area. of Forest and timeline, est. cost, • The proposed vator of Director, probable component is located Forest Madhav NP, implementation out of bird sanctuary & Shivpuri, (i.e. procedures and also boundary but is in eco Karera Bird their roles in the Directo sensitive zone. Sanctuary’s project. • NOC from WRD for r, management • Discussion about abstraction of water and Madha & control is Karera Wildlife construction of Intake v under Field Sanctuary popularly has been obtained. Director of known as “Son • Construction Safety Nation Madhav Chiraiya Bird measures shall be al Park, National Park sanctuary”, Reserve taken to ensure they Shivpur in Shivpuri forest boundary and are protected and district), its Eco Sensitive conserved. i zone. • Barricade the CDO, PIU – • Proposed components construction area Gwalior under WSS and its properly so that no wild

Civil impact on Karera animals entre the work Engineer, wildlife sanctuary area PIU, Gwalior • Proposed Mitigation • No construction Measures material Senior • What are the storage/ancillary works Draftsman, guidelines of Wildlife shall be conducted in Madhav Sanctuary for water the forest area; this National supply project like shall be limited to actual Park, laying of pipelines and construction area and Shivpuri other structures like the access roads OHT proposed under • Limit the work to subproject? daylight hours only; no • Environmental, Social, work after sunset traffic safety issue and • No high noisy works benefit from the shall be conducted project were explained • No labour camps shall • The work Shall be be located near forests done with mitigation (maintain minimum 1km measures, as per buffer) applicable laws, rules • No workers /personnel and regulation and shall enter forest areas; available it is the DBOC guidelinesand all the responsibility to take rules lay down central necessary precautions and state government & prevent workers in respect of removing/damaging construction in trees/vegetation, protected areas will be hunting animals followed • Create awareness • Most of the among workers on subprojects environment & safety components like • Conduct awareness Intake, WTP and OHT among workers on for Karera town is environment & safety located within • Public notice to be ecosensitive zone circulated, construction boundary not in should be completed in sanctuary. the given time, • Precaution must be • All the rules laid down taken care to minimize by central and state the noise during government in respect construction work to of construction near avoid any negative sanctuary should be impact on bird followed. sanctuary. • Adequate provision for • The impact will be only minimizing the Dust and for limited time during Noise Pollution during construction work construction • Overall they told us that they have no objection as this project is to meet the daily residential needs of the local residents by providing with a constant supply of better quality water as the subproject will improve the overall environmental quality of the town and surrounding areas.

Table 21: Summary of Stakeholder Consultation - Pichhore Town Date Locati No. of Participants Topic Discussed Issues/ concerned on Participa Raised nts 28th at ULB Total = ULB • Water Supply Project • The area has Dec office, 20 Chairman, Background, insufficient and Local Environmental, Social, inadequate drinking 2015 Pichhor M=20, representative GRM, traffic safety water resource. e F=00 s, ULB staffs issue and benefit from • People complained and local the project were about the very poor people explained to the water supply in the Stakeholders. town in terms of • Existing scenario of quantity of water as well water supply & as connectivity of water Proposed water supply network in town. supply project • Condition of all the • Need for existing component of improvements to the water supply has present system; been reviewed for their • All the location of further uses in components of proposed water supply proposed water scheme. After Supply scheme has discussion and been finalized with analysis, it was found identification of the 2 number of existing government land. GSR can be used in • All the existing water proposed water supply structure nearby town scheme. has been identified • People requested for and Futiwar Dam has selection of good been selected for contractor to speed up source of water supply the construction work. in Pichhore Town. • Funding and Tender • Relevant information Process of this Project. of the upcoming • Cost of this project; and project and benefits of project cost the project. participation of Central • positive and negative Govt. and State Govt. in impacts due to project to the project. implementation • Implementing agency; Ensuring no income and better/improved loss service. • Operation and maintenance of the facilities developed under the project and community participation;

Table 22: Summary of Stakeholder Consultation - Aron Town Date Locati No. of Participants Topic Discussed Issues/ concerned on Participant Raised s 23th at ULB Total = 14 CMO, • Water Supply Project • People informed about Sep office, M=12, F=02 Chairman Background, very less water supply ULB, Elected Environmental, Social, in town as compared to 2015 Aron Representati GRM, traffic safety standard. ves and ULB issue and benefits • Condition of all the Staff from the project were existing component of explained to the the water supply has Stakeholders. been reviewed for their • Existing scenario of further uses in water supply & proposed water supply Proposed water scheme. supply project • People requested for • Need for selection of good improvements to contractor to speed up present system; the construction work. • All the existing water structure nearby town • Cost of this project; and has been identified project cost and Sindh River has participation of Central been selected for Govt. and State Govt. in source of water supply to the project. in Aron. • Implementing agency; • Location of all the and better /improved components of service. proposed water • Operation and Supply scheme has maintenance of the been finalized with facilities developed identification of under the project and government land. community • Relevant information participation; of the upcoming • Probability of keeping project and benefits of the poor and the the project. vulnerable out of the • Potential positive and user charge. negative impacts due to project implementation Ensuring no income loss • Informed to the residents about the proposed water supply scheme including WTP and water connections to individual HHs in all the wards of town ensuring quality and reliability of services. 23th Ward Total= 20, SC-ST • Status of existing • Majority were very Sep No. 10, M= 12, F= community drinking water supply excited about the People, ULB system of; scheme as either they 2015 (SC-ST 08 officials • Need for are fetching water from Commu improvements to far, or the quality is not nity) present system; good, children also • The Water Supply suffer as they also are Scheme, SHG (Self required to help. Help Group) • But at the same time Environmental, Social, they wanted the rates GRM, traffic safety not to be exuberantly issue and benefit from high. the project were • They aspired that the explained to the scheme should bring Stakeholders. them water ASAP. • Briefing on project • In one ward residents objectives probable told that quality of tube implementation well water is not good. procedures. • Whereas in some other ward females told that they and their children don’t like taste of river water as they are used to drink tube well water.

Table 23: Summary of Stakeholder Consultation - Bairad Town Date Locati No. of Participants Topic Discussed Issues/ concerned on Participa Raised nts 18th at ULB Total = Chairman ULB, • Consultant • Chairman welcomed Sep office, 12 Chief Municipal representatives visited the initiative taken by Officer (CMO), Bairad Nagar Parishad the MPUSIP for the 2015 Bairad M=10, Bairad Nagar along with UADD preparation of DPR for F=02 Parishad, Sub officials for Water Supply of Bairad Engineer- ULB, Stakeholders Meeting town. Assistant for preparation of • Chairman and CMO Engineer- Detailed Project discussed the problems UADD, ULB Report of Water in the Bairad related to Representatives Supply Scheme for Drinking Water Supply. , Reporter, Bairad under MPUSIP. • The socio economic (Dainik Bhaskar, • Water Supply Project profile of the Bairad Bairad), Civil Background, was explained by the Engineer Environmental, Social, Chairman. (Survey & and benefit from the • There is an immediate Mapping), project were explained need of improving the Darashaw& Co. to the Stakeholders. present water works Pvt. Ltd. • The present condition infrastructure in the of Water Supply town. Chairman including Source, explained the Distribution System, problematic areas (Low Zones where water is Pressure Zones, supplied, Supply Electricity Supply Hours & Frequency, Duration) related to the Water Tax, Staff for water supply. Water Works, etc. was • Consultant noted down collected. the problematic areas & • The need for the present situation of the project was discussed town and discussion with the Chairman of was held on the need. the Nagar Parishad. • Consultants carried out • Land use and area to the site visit to the be covered under the source of water like project Pachipura Dam, Bairad • Relevant information Talaab, existing of the upcoming Overhead Service project and benefits of Reservoirs (OHSRs) & the project. tube wells along with • Potential positive and the representative of negative impacts due Bairad Nagar Parishad. to project • All the data related to implementation the town like CDPs, Ensuring no income Ward wise population, loss Ward Map and • Informed to the information about residents about the existing Water Supply proposed water supply Scheme was collected. scheme including WTP and water connections to individual HHs in all the wards of town ensuring quality and reliability of services. 6th At Total =16 Chairman ULB, • Finalization of source • ULB officials informed June Differe M=13, Chief Municipal and land availability that Bairad Talab will Officer (CMO), details for preparation become dry during 2016 nt WSS F=03 Bairad Nagar of Detailed Project summer and informed Compo Parishad, Sub Report of Water not to consider as nents Engineer- ULB, Supply Scheme for source and finalized Assistant Bairad under MPUSIP Pachhipura Dam as a Engineer- • Consultants explained source of water supply. UADD, ULB the concept plan of • Discussed about Representatives water supply scheme problems facing and , Reporter, to CMO, Chairman shortage in water (Dainik Bhaskar, and Ward members. supply. Bairad), Civil • Discussed about • Commencement date of Engineer & sources considered project work and Water Supply during concept plan duration. Expert- preparation like • Water logging during Darashaw& Co. Pachhipura Dam and heavy monsoon. Pvt. Ltd. Bairad Talab and • Chances of damaging explained approximate the existing water project cost for each pipelines during project option. implementation. • Storage Details of • Lack of public Pachhipura Dam awareness in proper use of underground • Discussed and drainage system. confirmed about • Scarcity of drinking existing water supply water in the area. facilities and • Public sensitization infrastructure available on proper use of with ULB. OHT in underground sewerage ward no. 5 was system abandoned hence not • considered the same and OHT in ward no.9 is also not considered due to age and low staging height and discussed the same. • Consultants shown the base map of Bairad town prepared with help of topographical survey and CMO has given some comments regarding colony names, land moarks and leftout areas. Consultants noted down all points and assured to rectify the same. • Pachhipura Dam source visited along with CMO & Other Officials and finalized the route for laying of rising main from source to WTP. • Identified a location for construction of Intake well • Site visit done along with CMO & Other Officials to identify the land parcels available for proposed works like construction of WTP, OHT and Pump Rooms etc and Identified land parcels for the same. • Land for proposed WTP is identified nearby Pachhipura Village. 15th Office Total=0 DFO, Kuno • Briefing about • Possibility of proposed 7 Wildlife May, of the proposed water supply component (Intake well M = 07, F Sanctuary, subproject for town & RWRM) being 2018 Divisio Sheopur = 0 Bairad - Background, located in Kuno wildlife

nal its components, sanctuary reserved CDO, PIU – Forest Gwalior locations, provisions, area. timeline, est. cost, • The proposed officer, Civil Engineer, probable component for Bairad Kuno PIU, Gwalior implementation town are located out of

Wildlife procedures and also Kuno Wildlife sanctuary Field Engineer, their roles in the Sanctu PMC (PIU) boundary as well as Gwalior project. eco sensitive zone. So ary, • Proposed components no environment Impacts Sheop Draftsman, under WSS and its envisaged. Kuno Wildlife ur impact on Kuno • Bairad Town is located Sanctuary, wildlife sanctuary approx. 10km away Sheopur • Proposed Mitigation from the boundary of Computer Measures ecosensitive zone of Operator, Kuno • Discussion about, Kuno wildlife sanctuary Wildlife Kuno Wildlife • NOC from WRD for Sanctuary, Sanctuary, Reserve abstraction of water and Sheopur forest boundary and construction of Intake

its Eco Sensitive zone. has been obtained. Draftsman, Kuno Wildlife • Confirmation of Kuno • Create awareness Sanctuary, Wildlife Sanctuary, among workers on Sheopur Reserve forest environment & safety boundary • Public notice to be • What are the circulated, construction guidelines of Wildlife should be completed in Sanctuary for water the given time, supply project like • Adequate provision for laying of pipelines and minimizing the Dust and other structures like Noise Pollution during OHT proposed under construction subproject? • Environmental, Social, traffic safety issue and benefit from the project were explained • The work Shall be done with mitigation measures, as per applicable laws, rules and regulation and available guidelines and all the rules lay down central and state government in respect of construction in protected areas will be followed • None of the subproject components are located in ecosensitive zone or in sanctuaryarea

Table 24: Summary of Stakeholder Consultation - Vijaypur Town Date Location No. of Participants Topic Discussed Issues/ concerned Raised Participants 8th At ULB Total = 17 CMO, • Presentation on detailed • Consultants explained June office, M=08, F=09 Chairperson project report of proposed Detailed Project Report –ULB, Vice water supply for Vijaypur prepared for water supply 2016 Vijaypur Chairman- under MPUSIP. scheme to ULB officials & ULB, Elected • Water Supply Project Elected Ward Members. Ward Background, • Discussed about scheme members Environmental, Social, proposed from Kunwari GRM, EHSs, traffic safety River as a source by using issue and benefit from the under construction anicut by project were explained to WRD and proposed intake the Stakeholders. well. • Land use and area to be • Officials asked about covered under the project. location of proposed WTP • Consultants explained and OHT locations in the about positive impacts of town and explained and the scheme like 24x7 shown the same. water supply, area • Ward members enquired covered in ULB, adequate about material of pipes used pressure at user end etc. in the scheme and they were • Relevant information of informed that Ductile Iron the upcoming project and pipes are used for rising / benefits of the project. pumping mains and HDPE pipes for distribution system. • Potential positive and negative impacts due to • Elected Ward members project implementation enquired about land status Ensuring no income loss available for proposed • Informed to the all facilities and CMO explained the same and shown the members about the proposal sent to revenue proposed water supply department for allocation of scheme including WTP land. and water connections to • The chair person asked individual HHs in all the about the estimated project wards of town ensuring cost for the scheme and quality and reliability of they were informed about services. the funding pattern by consultant. • Consultants also explained about estimated O&M expenditure to run the scheme. • ULB officials and ward members enquired about tariff proposed for households and commercial connections and consultants furnish the same. • Elected members enquired about restoration of roads after laying of pipeline and alignment of pipelines. • ULB officials asked about probable commencement of the scheme and they were informed that by the end of 2017 execution of project will finished and 2018 is the commissioning year.

20th At Total =07 Chairperson • Finalization of source and • Consultants and ULB Jan proposed M=07, F=00 –ULB, Chief land availability details for officials discussed and preparation of Detailed confirmed about existing 2016 Compon Municipal Project Report of Water water supply facilities and ent Officer Supply Scheme for infrastructure available with Location (CMO), Sub Vijaypur under MPUSIP. ULB and discussed about • Existing scenario of water problems facing and Engineer- supply & proposed water shortage in water supply. ULB, supply project. • Consultants shown the base Water Works map of Vijaypur town Inspector- • Present drinking water prepared with help of supply source and its topographical survey and ULB, Water condition CMO & Elected Members Supply Expert • Discussed about old have identified some and Civil system and reasons for mismatches about land failure and concluded that marks. Consultants noted Engineer due to lack of down all points and assured Darashaw & maintenance the old to rectify the same. Co. Pvt. Ltd. system was abandoned. • Consultants collected the • Need of improvement of ward boundary map to make

the present situation the ward boundaries on base map. • Consultants are explained the concept plan of Vijaypur water supply scheme to CMO, Chairman, Technical Officers and Elected Members. • Discussed about source considered during concept plant preparation i.e Kunwari River and explained the entire scheme of proposed water supply scheme including preliminary estimated project cost. And also explored probable other sources if any. • ULB officials agreed for Kunwari River as a source of water supply at the proposed stop dam site which is recently construted by WRD, and CMO requested to send a letter to WRD regarding water allotment. • NOC from WRD already obtained • Kunwari River source visited along with Chairman, CMO & technical officers and finalized the route for Laying of rising main from source to WTP and ULB. • Identified a location for construction of Intake well and also finalized land parcel for proposed water treatment plant.

• Site visit done along with Chairman, CMO & technical officers to identify the land available for proposed works like construction of WTP, sump, OHT and Pump Rooms etc and finalized and visited Tehsil office regarding land parcels available for proposed works.

18th At ULB Total= 06, Chairperson • Preparation of Detailed • Chairman welcomed the Sep office M= 06, F= 00 -ULB, Chief Project Report of Water initiative taken by the Supply Scheme for MPUSIP for the preparation 2015 Municipal Vijaypur under MPUSIP. of DPR for Water Supply of Officer • Status of existing drinking different towns of Madhya (CMO), Water water supply system of; Pradesh. • Chairman and CMO raised Works • Need for improvements to present system; the problems in the Vijaypur Inspector, • Briefing on project related to Drinking Water Assistant objectives probable Supply. Engineer, implementation • The socio economic profile procedures. of the Vijaypur was UADD, Civil • The need for the project explained by the Chairman. Engineer was discussed with the • There is an immediate need (Survey & Chairman of the Nagar of improving the present Parishad. water works infrastructure in Mapping) and the town. Chairman Graduate explained the problematic Trainee, areas (Low Pressure Zones, Darashaw & Electricity Supply Duration) related to the water supply. Co. Pvt. Ltd. • Consultant noted down the problematic areas & present situation of the town and discussion was held on the need. • Consultants carried out the site visit to the source of water like Kunwari River, existing Overhead Service Reservoirs (OHSRs) & tube wells along with the representative of Vijaypur Nagar Parishad.

15th Office of Total= 07 DFO, Kuno • Briefing about proposed • Possibility of proposed M = 07, F = 0 Wildlife May, the water supply subproject component (Intake well & Sanctuary, for town Vijay - RWRM) being located in 2018 Divisional Sheopur Background, its Kuno wildlife sanctuary

Forest components, locations, reserved area. CDO, PIU – officer, Gwalior provisions, timeline, est. • The proposed component

Kuno cost, probable for Vijaypur town are located Civil implementation out of Kuno Wildlife Wildlife Engineer, procedures and also their sanctuary boundary as well PIU, Sanctuary, Gwalior roles in the project. as eco sensitive zone Sheopur • Proposed components boundary. So no Field under WSS and its impact environment Impacts Engineer, on Kuno wildlife sanctuary envisaged. PMC (PIU) • Proposed Mitigation • Vijaypur Town is located Gwalior Measures approx. 24km away from the

Draftsman, • Discussion about, Kuno boundary of ecosensitive Kuno Wildlife Sanctuary, zone of Kuno wildlife Wildlife Reserve forest boundary sanctuary Sanctuary, and its Eco Sensitive • NOC from WRD for Sheopur zone. abstraction of water and

• Confirmation of Kuno construction of Intake has Computer Operator, Wildlife Sanctuary, been obtained. Kuno Reserve forest boundary • Create awareness among Wildlife • What are the guidelines of workers on environment & Sanctuary, Wildlife Sanctuary for safety Sheopur water supply project like • Public notice to be

laying of pipelines and circulated, construction Draftsman, Kuno other structures like OHT should be completed in the Wildlife proposed under given time, Sanctuary, subproject? • Adequate provision for Sheopur • Environmental, Social, minimizing the Dust and traffic safety issue and Noise Pollution during benefit from the project construction were explained • The work Shall be done with mitigation measures, as per applicable laws, rules and regulation and available guidelines and all the rules lay down central and state government in respect of construction in protected areas will be followed • None of the subproject components are located in ecosensitive zone or in sanctuary area •

Table 25: Summary of Stakeholder Consultation - Isagarh Town Date Locati No. of Participants Topic Discussed Issues/ concerned on Participa Raised nts Sep at ULB Total= CMO, • Water Supply Project • Consultants and ULB 2016 office, 06, Chairman Background, officials discussed and ULB, Elected Environmental, Social, confirmed about isagarh M=06, Representativ GRM, EHSs, traffic existing water supply F=00 es, Sub safety issue and facilities and Engineer, benefit from the infrastructure available project were explained with ULB and discussed to the Stakeholders. about problems facing • Finalization of source and shortage in water and land availability supply. details for preparation • CMO & Elected of Detailed Project Members have Report of Water identified some Supply Scheme for mismatches about land isagarh under marks. Consultants MPUSIP. noted down all points • Existing scenario of and assured to rectify water supply & the same. proposed water supply • Consultants collected project. the ward boundary map • Present drinking water to make the ward supply source and its boundaries on base condition map. • Discussed about old • Consultants are system and reasons explained the concept for failure and plan of Isagarh water concluded that due to supply scheme to CMO, lack of maintenance Chairman, Technical the old system was Officers and Elected abandoned. Members. • Need of improvement of the present situation

150. Institutional consultations were conducted with the Governmental Departments such as PMU, Pollution Control Board, Public Health Engineering Department, Water Resourced Department, Forest Department and ULB etc. The project proposal is formulated in consultation with Nagar Parishads and suit the requirements of the ULBs.

151. Focus-group discussions with affected persons and other stakeholders were conducted to learn their views and concerns. A socio economic household survey has been conducted in the town, covering sample households, to understand the household characteristics, health status, and the infrastructure service levels, and also the demand for infrastructure services. General public and the people residing along the project activity areas were also consulted during visits to the project sites. Consultation were also held with the officials of Madhav National Pacrk as the Karera wildlife sanctuary’s management and control is under them. Refer Appendix 10A2. Also consultation were conducted with the officials of Kuno wildlife sanctuary for Bairad & Vijaypur towns. Refer Appendix 10 to Appendix 11 & Appendix 14 to Appendix 16. The detailed of Public consultation meetings are given in Appendix 10 to Appendix 17.

152. It was observed that people are willing to extend their cooperation as the proposed activities are proposed to enhance the infrastructure service levels and the living standard of the public. The public expressed their concern regarding the nuisance and disturbance (dust, road closure and traffic management activities)

b) Consultation duringconstruction:

153. Prior to start of construction, ULB and PIU with the assistance of PDMC will conduct information dissemination sessions at various places and solicit the help of the local community, leaders/prominent for the project work. At each ward/neighborhood level, focus group meetings will be conducted to discuss and plan construction work with local communities to reduce disturbance and other impacts.

154. A constant communication will be established with the affected communities to redress the environmental issues likely to surface during construction phases and also regarding the grievance redress mechanism. ULB/PIU and PDMC will organize public meetings and will appraise the communities about the progress on the implementation of EMP. Meeting will also be organized at the potential hotspots/sensitive locations before and during the construction.

C. INFORMATION DISCLOSURE 155. Executive summary of the IEE will be translated in Hindi and made available at the offices of PMU, PIU, Nagar Parishad offices, and also displayed on their notice boards. Hard copies of the IEE will be accessible to citizens as a means to disclose the document and at the same time creating wider public awareness. Electronic version of the IEE in English and Executive Summary in Hindi will be placed in the official website of the UDED, PMU after approval of the IEE by Government and ADB. Stakeholders will also be made aware of grievance register and redress mechanism.

156. Public information campaigns to explain the project details to a wider population will be conducted. Public disclosure meetings will be conducted at key project stages to inform the public of progress and future plans. Prior to start of construction, the PMU/PIU will issue Notification on the start date of implementation in local newspapers A board showing the details of the project will be displayed at the construction site for the information of general public.

157. Local communities will be continuously consulted regarding location of construction camps, access and hauling routes and other likely disturbances during construction. The road closure together with the proposed detours will be communicated via advertising, pamphlets, radio broadcasts, road signage, etc.

VIII. GRIEVANCE REDRESS MECHANISM

A. PROJECTSPECIFICGRIEVANCE READRESSMECHANISM 158. Grievance Redress Mechanism (GRM) is a part of project management that is likely to increase accountability and responsiveness among service providers and provide a friendly environment to the beneficiaries of the project. GRM is considered a tool to measure efficiency and effectiveness of the project as it provides important feedback on the project management. Effectively addressing public grievances is a core component of managing risks under Asian Development Bank (ADB) projects according to the Safeguard Policy Statement (Safeguard Requirement 2: Involuntary Resettlement, Pages 49-50, June 2009) – “The borrower/client will establish a mechanism to receive and facilitate the resolution of affected persons’ concerns and grievances about physical and economic displacement and other project impacts, paying particular attention to the impacts on vulnerable groups. The grievance redress mechanism should be scaled to the risks and adverse impacts of the project. It should address affected persons’ concerns and complaints promptly, using an understandable and transparent process that is gender responsive, culturally appropriate, and readily accessible to the affected persons at no costs and without retribution. The mechanism should not impede access to the country’s judicial or administrative remedies. The borrower/client will inform affected persons about the mechanism”. The statement allows the formation of grievance redress committee in the project areas to facilitate the concerns of affected people under the project areas.

B. Purpose of the GRM Manual: 159. This document describes the procedure that shall be followed by the Madhya Pradesh Urban Development Company Limited (MPUDCL) under Madhya Pradesh Urban Services Improvement project (MPUSIP) to address complaints or concerns shared by people affected due to project related interventions.

160. The present document intends to provide clarity to project stakeholders on the grievance redress mechanism procedures to be followed under the project. The document provides clarity on how the complaint shall be received, registered, sorted, assessed, resolved and monitored under MPUSIP. This also includes action plans to be followed for effective implementation.

C. Principles: 161. The GRM is based on the following principles and the same shall be used to assess the GRM performance:

(a) Accessibility The GRM shall be accessible to all people residing in the project area. It shall be available and provide assistance to all project affected people irrespective of language, literacy level, or cost. Project affected people shall access the GRM without fear of reprisal.

Information on the GRM will be disseminated using various means to ensure people know about GRC, its members and procedures.

(b) Predictability The GRM shall offer clear procedures with time frames for each stage and clarity on the type of results it can and cannot deliver.

(c) Transparency The GRM shall operate in such a way that it is easy for others to see what actions are being performed. This will be undertaken through disclosure of all information to the public and affected people.

(d) Credibility The performance of the GRM shall enable affected people to accept and believe that the mechanism works, delivers results and is trustworthy.

(e) Fairness The GRM procedures shall be perceived as fair, especially in terms of access to information, and opportunities for meaningful participation in the final decision. Its outcome should be consistent with applicable national standards and should not restrict access to other redress mechanisms.

(f) Feedback The GRM shall serve as a means to channel citizen feedback to improve project outcomes for the people.

It is difficult to avoid Grievances totally but much can be done to minimize and manage complaints in order to reduce impacts.

D. Nature and scope of Grievance Redress Mechanism under MPUSIP 162. GRM aims to address complaints of local affected people because of project interventions in the selected towns (64 towns) of MPUSIP during the project period.

163. MPUSIP predicts public complaints because of the nature of the project during the design, implementation and operation & maintenance stage of the project. In the design phase, people are expected to raise inconveniences with regards to land acquisition, compensation amount, compensation procedure and environmental issues. During project implementation, grievances may come from individuals or a particular group of people in relation to construction related inconveniences such as dust, noise, blocking drainage, damage roads, walls/boundaries of property and its impact on their daily lives in addition to land acquisition, and compensation. Issues related to corruption shall not be considered by the Grievance Redress Committee (GRC). Corruption related issues shall be forwarded to the State GRC (PMU) directly by the Chairperson of town level GRC at the time of sorting of grievances. The structure, functions of GRC, monitoring & evaluation systems and action plan of its implementation is described below:

E. Structure of GRM and its Functions 164. The GRM will have a three- tier decision making process. The first tier which is at the town level aims to resolve all construction related grievances which require quick and efficient action. The second tier which is at the project implementation unit (PIU) will handle complaints that could not be resolved by the first- tier level and/or grievances related to land acquisition and compensation. The third tier which is at the project management unit (PMU) or state level will handle complaints which are over and above the scope for the first and second tier and/or complaints which could not be resolved by the first and second tier levels.

165. Contact numbers of GRC Chair-person and members, CDO and contractor’s focal person will be placed at appropriate locations like construction sites, ULB office etc.

166. The three-tier Grievance Redress Mechanism under MPUSIP is described below:

1st tier (At Town Level):

composition of the Grievance Redress Committee (GRC):

• A representative of Chief Municipal Officer associated with Urban Local Body, Chairperson; • CDO of ULB designated/nominated by ULB. • Field Engineer of Project Management Consultants; • Focal person (GRC Person) of DBO contractor of respective town; • Field Engineer of concerned ULB designated by the respective PIU, Secretary;

Major Functions: The major functions of town level GRC is as follows:

• Registration of Grievances by the Local person (GRC Person) of DBO contractor of respective townSorting of Grievances by Focal person (GRC Person) of DBO contractor of respective town and Chairperson; • Forwarding grievances to concerned authorities i.e. Site Engineer for resolution; • Information to the complainant on the decision taken to address registered complaint and expected time to resolve issue; • Resolution of issues emerged due to construction; • Feedback to the complainant on action completed against registered complaint and seeking complainant feedback on level of satisfaction; • Closure of grievances by CDO-ULB or forwarding of complaint to PIU GRC if grievance remains unresolved.

2nd Tier {At PIU Level}:

Composition of the PIU level GRC:

• Project Manager, associated with Project Implementation Unit (PIU) of Madhya Pradesh • Urban Development Company Limited - Chairperson • An elected member nominated by Mayor in Council/ President in Council of associated • Urban Local Body (ULB). • A Social Worker nominated by Mayor in Council/ President in Council of associated Urban • Local Body • Commissioner of associated Urban Local Body/Chief Municipal Officer or Community • Development Officer/Community Organizer of Urban Local Body. • Community Development Officer CDO-PIU - Secretary

Major Functions: The following functions will be performed by the PIU level GRC:

• Registration of complaints by CDO-PIU from the 1st tier GRC and/or affected people; • Eligibility assessment of grievances by the GRC Chairperson; • Information to the complainant about eligibility of the complaint; • Grievance Redress Committee meetings to discuss grievances and action required; • Ensuring collection of detailed information about the eligible complaint; • Assessment of complaint, draw conclusion from discussions and make recommendations; • Develop action plan outlining activities required to implement the recommendations; • Ensuring implementation of recommendations by stakeholders or concerned authorities; • Monitoring actions of the recommendations in view of timeline; • Feedback to the complainant on action completed against registered complaint and seeking complainant feedback on level of satisfaction; • Closure of grievances by CDO-PIU or forwarding of complaint to PMU GRC if grievance remains unresolved.

3rd Tier {At PMU-State Level}

Composition of State Level GRC:

• Engineer in Chief, MPUDC – Chairperson • Deputy Project Director (T) • Deputy Project Director (A) (Secretary) • Project Officer • Community Development Officer CDO-PMU • PMC TL or representative Advisor

Major Functions: The state level GRC will be responsible to performthe following functions:

• Registration of complaints received from GRC PIU and/or affected people; • Information to the complainant about eligibility of the complaint; • Eligibility assessment of grievances by the GRC PMU chairperson with support of the • Secretary of state GRC- – whether grievance is eligible for consideration or not at the state level; • Ensuring collection of required information about the eligible complaint; • Assessment of complaint to draw conclusion from discussions and make recommendations; • Develop action plan outlining activities required to implement the recommendations; • Ensuring implementation of recommendations by stakeholders or concerned authorities; • Monitoring actions of the recommendations in view of timeline; • Closing complaint after all actions taken as per recommendations and feedback to the complainant. • Advise to complainants about approach /appeal to the concerned department in case the complainant is not satisfied or complaint is beyond the scope of the GRC PMU.

Figure 42: Work Flow Diagram on GRM Step 8: Appeal to the Step 1: Receiving Grievances / State Level GRC Complaints and its Registration at town level (24 hours)

Step 2: Review of Grievances, Sorting, Information and Forwarding (1

Day)

Closure of the Closure

: :

Complaint Step 7 Step Grievance

Redress

Mechanism

GRC Meeting (3 Days) Meeting GRC

: Eligibility and Preparation Eligibility : for

(Monthly) (Monthly)

Step 3 Step

Monitoring and Reporting and Monitoring

: : Step 6 Step

Step 4: Assessment of the Grievance, Step 5: Implementation of Action Meeting and Plan of Action (7 Days)

(30 Days)

F. Process of Grievance Redress Mechanism 167. The following process shall be adopted for receiving complaints and addressing received complaints:

Step 1: Receiving Grievances/ Complaints and its Registration at town Level

• All grievances, complaints, concerns shall be submitted verbally or in writing to CDO contractor’s focal person or any GRC members – by filling the Complaint Registration Slip and putting into the complaint box placed at construction sites or ULB office. • Received complaints shall be recorded, compiled and Registered (Grievance Number) in a register (database) placed at the ULB by CDO with support of the contractor’s focal person on a daily basis (24 hours). Each grievance shall be given a number to track status.

Step 2: Review of Grievances, Sorting, Information and Forwarding (24 hours)

• Registered grievances shall be reviewed by the CDO with support of the contractor’s focal person. • Based on type of grievances, CDO shall sort out grievances with support of the contractor’s focal person. • CDO (ULB) shall inform the GRC Chairperson about all grievances either by phone or in writing. At that time, CDO may suggest grievances can be managed by the site engineer to the GRC Chairperson; • GRC Chairperson will determine eligibility of the complaints. Inconveniences caused by minor construction related issues shall be referred to the site engineer to resolve immediately or within 24 hours. For example -site engineer shall be instructed to resolve grievances associated with construction at the town such as restoration of road, obstruction in accessing house/shop or any place due to dumping of construction materials, dust etc. Site engineer will be responsible to respond to the complaints immediately. On the other hand, issues which cannot be resolved by the site engineer and if it is complex in nature shall be referred to GRC. • CDO shall receive acknowledgement from concerned authorities (site engineer) on receipt of the grievances shared with them. CDO shall inform complainants regarding eligibility of their complaint and action to be taken by the concerned authority (site engineer/ GRC) within (24 hours). If the grievance is ineligible, complainants should be informed of the reasons;

Step 3: Eligibility and Preparation for GRC meeting (3 days)

• GRC Chairperson shall receive eligible complaints (copy of written complaint document or verbally recorded messages) from the CDO (ULB) and review details; GRC Chairperson may ask to collect baseline information about the grievances registered, if required. • GRC Chairperson shall share list of documents with the GRC Secretary to collect baseline information on selected grievances to be addressed. • The GRC Secretary shall arrange all documents with the help of CDO-ULB, CDO-PIU or the contractor’s focal person in a proper way to present in front of GRC. • GRC Chairperson shall call a meeting as per convenient date and time of the committee members.

Step 4: Assessment of the Grievance, Meeting and Plan of Action (7 days)

• If necessary, the GRC shall consult and seek relevant information about complaint from the concerned parties. • On basis of the collected evidences, GRC shall draw conclusions and make recommendations for a solution. • GRC Secretary shall keep record of the proceedings and decisions taken by GRC members to further track the status as per decided time line. • The GRC shall agree on the action plan required to be implemented according to the recommendations made. The action plan shall include detailed activities along with timeline. • GRC Secretary shall inform to the complainant about the decisions taken by the committee members and expected date of resolution of the grievance. • If the complaint is complex, the GRC may request for additional time and resolution after proper assessment or refer the complaint to the GRC-PMU Level.

Step 5: Implementation of Action (30 days)

• The concerned parties shall be responsible to implement action plan according to recommendations of the GRC. • The GRC members may arrange field trip and interact with the concerned persons, if needed before reaching the conclusion.

Step 6: Monitoring and Reporting (Monthly)

• CDO (ULB) shall be responsible to track and record status of all complaints - whether forwarded to site engineer or GRC in the database as follows – Grievance registered, Grievance in process to be resolved, Grievance addressed and closed, and Grievance forwarded to concerned authorities. • CDO (ULB) shall be responsible to report/inform status of the complaints (received, addressed and forwarded) to the contractor for further reporting to respective PIU. • Overall GRC chairperson shall be responsible for effective management of complaints at the town level. Step 7: Closure of the Complaint

• GRC Secretary shall prepare a summary of the findings and share with GRC members. • On agreement of all GRC members, GRC Secretary shall provide information to the complainant about decisions taken in writing/verbal on the registered complaint and seek feedback of the complainant about the decisions taken. A copy of the letter shall be kept as record with GRC Secretary and CDO (ULB). • Complaint shall be considered closed if all actions have been taken and the complainant satisfied with the resolution. • GRC Secretary shall prepare a closure report of the grievances handled by GRC members and the closure shall be documented by the CDO (ULB) in his register.

Step 8: Appeal to the State level GRC

• In the event that GRC PIU cannot make a decision on how to resolve the complaint, or if a complainant is not satisfied with the actions taken to resolve the complaint by the GRC (PIU), an appeal can be made to state level GRC (PMU) either by the GRC Chairperson (PIU) or complainant directly. • GRC Chairperson (PIU) or complainant shall submit an appeal in writing to the state level GRC established at PMU. • The state GRC Secretary shall register the case in consultation with Chairperson and provide a number of the grievances to be tracked. • The state GRC Secretary shall acknowledge the registration of the grievance to the complainant in writing. • The Secretary of the GRC shall review the registered grievances and collect required evidences from relevant parties to present case to the GRC. • The state GRC Chairperson shall call a GRC meeting to review the complaint. GRC members shall get information about the meeting in advance to ensure their availability in the meeting. • The state GRC shall draw conclusions and recommendations based on the evidence in the meeting. At the same time an action plan shall be developed for implementation with a timeline. • The state GRC Secretary shall communicate decisions of the State GRC to the complainant in writing. The copy of the communication shall be kept with the state GRC Secretary as record. • The recommendations shall be implemented immediately • Upon completion of the recommended actions, the state GRC Secretary shall prepare a report on the closure of the complaint which will be signed by the complainant and state GRC Chairperson. A copy of the same shall be kept for record.

168. The structure and process of GRM is presented below for detailed understanding

Figure 43: Structure and Process of GRC

G. Monitoring and Evaluation systems of GRM All grievances, concerns and complaints received shall be recorded by concerned authorities to be tracked. The status of the grievances shall be discussed in the review meetings organized at PIU and PMU level. The following indicators shall be monitored and recorded - Number and type of complaints received; - Number and % of complaints that have been resolved; - Number and % of complaints that are unresolved;

The State GRC shall review grievance related data on monthly basis to evaluate the functionality of the system, as well as to note the followings: • Failures to follow GRM procedures; • Delays in complaint resolution, particularly those that can affect project construction; • Most frequent types of grievances and complaints; • Location(s) producing the most grievances and complaints;

H. Action Plan for the formation of the GRM S.No Action Plan Time Line

A Action required at PMU/PMC

A1 Letter for formation of GRC and follow up Pre -construction

A2 Development of GRM Manual Pre -construction

A3 Orientation of GRC members by integrating with Construction training/workshops/meetings

A4 Integration of GRC topic in BCC – like availability of GRC Construction and its procedure

A5 Review of functioning of GRC by integrating with meetings Construction and visits

B Action at Town level

B1 Formation of GRC at town level and inform to the PMU/PMC Pre -construction

B2 Information to All ULB Officials/Public about existence of Construction

GRC, its committee members and their function

B3 Orientation of all GRC members during visit of PMU and Construction PMC officials

B4 Tracking of complaint registered and its status Construction

B5 Sharing status of grievances with PIUs with the help of GRC Construction person

B6 Training of selected women to maintain grievances at Construction customer service center (Educated Prerak (Motivator) may be considered)

B7 Complaint management Operation and maintenance phase IX. ENVIRONMENTAL MANAGEMENT PLAN

A. Environmental Management Plan 169. An environmental management plan (EMP) has been developed to provide mitigation measures to reduce all negative impacts to acceptable levels

170. The EMP will guide the environmentally-sound construction of the subproject and ensure efficient lines of communication between MPUDC, project management unit (PMU), project implementing unit (PIU), consultants and contractors. The EMP will (i) ensure that the activities are undertaken in a responsible non-detrimental manner; (i) provide a pro-active, feasible and practical working tool to enable the measurement and monitoring of environmental performance on site; (ii) guide and control the implementation of findings and recommendations of the environmental assessment conducted for the subproject; (iii) detail specific actions deemed necessary to assist in mitigating the environmental impact of the subproject; and (iv) ensure that safety recommendations are complied with. The EMP includes a monitoring program to measure the environmental condition and effectiveness of implementation of the mitigation measures. It will include observations on- and off-site, document checks, and interviews with workers and beneficiaries.

171. The contractor will be required to submit to PIU, for review and approval, a site environmental plan (SEP) including (i) proposed sites/locations for construction work camps, storage areas, hauling roads, lay down areas, disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following the approved EMP; (iii) monitoring program as per SEP; and (iv) budget for SEP implementation. No works are allowed to commence prior to approval of SEP.

172. A copy of the EMP must be kept at work sites at all times. This EMP will be included in the bid documents and will be further reviewed and updated during implementation. The EMP will be made binding on all contractors operating on the site and will be included in the contractual clauses. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance.

173. For civil works, the contractor will be required to (i) carry out all of the mitigation and monitoring measures set forth in the EMP; and (ii) implement any corrective or preventative actions set out in safeguards monitoring reports that the employer will prepare from time to time to monitor implementation of this IEE and EMP. The contractor shall allocate budget for compliance with these EMP measures, requirements and actions.

174. The following tables show the potential environmental impacts, proposed mitigation measures and responsible agencies for implementation and monitoring.

Table 26: DesignStage Environmental Management Plan Field Anticipated Impact Mitigation Measures Responsible for Cost and Source Implementation/ of Funds Monitoring Design of Unsustainable source • Continuation of groundwater source for PMU to ensure compliances Project water supply – depleting resource subproject town Isagarh Costs system and source • Conduct a detailed groundwater study and These measures are already contamination prepare a groundwater sustainability plan for included in the preliminary Isagarh town to address the groundwater designs. sustainability issue. • Implementation of Source Sustainability Plan DBO Contractor (DBOC)to will be part of the project and will inter alia follow, enhance where possible include measures like sub-surface dykes; a combination of sub-surface dyke and check dam; recharge pits; community roof top rainwater harvesting systems, etc., • Creation of artificial recharge pits in public places / public buildings. Local body can issue a notification to this effect. • Household level artificial recharge (like roof top rainwater harvesting) should be encouraged. • Groundwater regulation – all the tube wells in houses in Isagarh to be discontinued in a phased manner once the project is implemented • Measures should be taken to control the open defecation, and to close all unsafe latrines (for example pit latrines). • Awareness programs shall be conducted regarding the sanitation practices and its effect on groundwater quality Design of Unsustainable source Following measures suggested: PMU to ensure compliances Project Costs water supply – depleting resource • Suitable measures for groundwater recharge system and source have to be taken up. These measures are already contamination • Create an inventory of all groundwater included in the preliminary sources in the municipality (existing and designs. proposed) • Suitable measures to be taken to prevent DBO Contractor (DBOC)to contamination of water sources; cement follow, enhance where possible sealing and length of casing pipe is to be included in the design. Suitable provisions should be made for lining of drains and prevention and chocking / overflow / lateral and vertical seepage. • Proper monitoring groundwater withdrawal to be conducted; all the tube wells should be fitted with flow meters. Piezometers should be constructed at suitable locations to identify ground water aquifer zones. • A detailed study of hydrogeology, land use and geomorphology of the region should be conducted and source sustainability plan should be prepared incorporating the water cycle of Isagarh Nagar Parishad area, the water budget, and the groundwater assessment. • Following sustainability structures are suggested: sub-surface dyke; a combination of sub-surface dyke and check dam; check dam; recharge pits; recharge shafts, community roof top rainwater harvesting systems. However, it is highly recommended that these structurers, their design and location, must be finalized after a thorough study of groundwater conditions of the area and must be as per the sustainability plan of the Isagarh Nagar Parishad. • Conjunctive use of ground and surface water must be promoted • The annular space between the casing pipe and the wall of the bore well must be sealed with cement slurry in order to prevent groundwater contamination • A 1m x 1m x 1m concrete block is to be constructed around the exposed casing pipe above the surface. The block will be 50 cm above the ground and 50 cm below the ground to holdfast the casing pipe. • The top of the casing pipe should be at least 90 cm above the ground or above the reported HFL of the site, whichever is higher. • Suitable measures to be taken to prevent contamination of source since the water quality may be impacted by untreated sewage flowing nearby; suitable provisions should be made for lining of drains and prevention and chocking / overflow / lateral and vertical seepage. Design of Unsustainable source; • Discontinuation of current unsustainable DBO Contractor / PMU Project Costs water supply resource & energy use groundwater source and creating new water system supply system based on a nearest surface water sources i.e. Samoha dam for Karera, Futiwar dam for Pichhore, Sindh River for Aron, Pachipura dam for Bairad and at Kunwari river existing stop dam for Vijaypur towns etc. • Recovering wash water from treatment process • Treatment and reuse of sludge from treatment process • Minimizing water losses from pipelines by perfect jointing and alignments using appropriate techniques (HDPE pipes up to 150 mm dia joined by electro fusion couplers using on-site electro fusion welding, and all higher dia pipes by on site butt welding) • Designing the entire system to maintain optimal flow and terminal pressure, and optimising the overall energy usage • Reducing the incidence of water borne diseases by providing 100% population including urban poor with potable water supplies • Improve water use efficiency and reduce water wastage at household level by recording and monitoring the water usage, and charging the consumers as per usage; due consideration to urban poor • Minimize unaccounted for water (UFW) losses using district metered area approach with flow meter and pressure logging arrangements to identify and rectify the leaks, and unauthorized connections • Using low-noise and energy efficient pumping systems • During the design, construction, and operation of the project, apply pollution prevention and control technologies and practices consistent with international good practice, as reflected in internationally recognized standards such as the World Bank Group’s Environment, Health and Safety Guidelines (IFC’s General EHS Guidelines7 and Sector Specific (Water and Sanitation) Guidelines8). Water Project sustainability • Obtain permission from Water resources PMU & ULBs and Project abstraction water use conflicts department, GoMP, prior to bid process DBOC to prepare application, Costs from and assist as required Samoha Dam for Karera, Futiwar Dam for Pichhore and Sindh river for Aron, Pachipura dam for Bairad and Kunwari River for

7 https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B- %2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 8 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B-%2BWater%2Band%2BSanitation.pdf?MOD=AJPERES

Vijaypur Waste PMU / Nagar Parishads; No costs; scope of generation Environmental • Obtain consent from MPPCB for WTPs DBOC to prepare application, IA & DBO from WTP pollution and assist as required operations

Chlorine usage Chlorine handling & Provide the following measure at the chlorine These measures are already Project as disinfectant application risk – health application unit: included in the preliminary Costs at WTPs and at & safety risk to workers • Chlorine neutralization pit with a lime slurry designs. sump for and general public feeder Isagarh town • Proper ventilation, lighting, entry and exit DBOC to follow, enhance where For towns facilities possible. • Facility for isolation in the event of major chlorine leakage • Personal protection and safety equipment for the operators in the chlorine plant • Provide training to the staff in safe handling and application of chlorine; this shall be included in the contract of Chlorinator supplier • Supplier of Chlorinator equipment shall provide standard operating manual for safe operation and as wellas maintenance and repairs; preferably these shall be provided both in English and Hindi Languages.

Table 27: Environmental Management Plan of Anticipated Impacts during Pre-Construction Field Anticipated Impact Mitigation Measures Responsible for Monitoring of Mitigation Cost and Source Implementation/ of Funds Monitoring EMP Unsatisfactory • Appoint EHS supervisor and DBO contractor Cost for Implementation compliance to EMP designate 1 EHS coordinator implementation & reporting (among the technical staff) in of mitigation each town measures • Ensure that all pre-construction responsibility of activities are complete prior to contractor. start of construction work • Ensure timely submission of monitoring reports

Utilities Telephone lines, • Identify and include locations of DBO Contractor in (i) List of affected Project costs – electric poles utilities in the detailed collaboration with PIU utilities and general and wires, water designs/drawings to prevent and with approval of operators; construction

PMU practice lines within unnecessary disruption of

proposed project services (ii)Bid document to • Prepare a contingency plan to area include requirement for include actions to be taken in case of unintentional interruption contingencyplanfor of services.. service interruptions Construction Disruption to • Prioritize barren, waste, infertile, DBO Contractor to List of selected Project costs – work traffic flow and vacant lands within the area, finalize locations in sites for general Camps, Sensitive receptors • Shall not be located in consultation and Construction work construction stockpile productive agricultural lands, approval of PIU camps, hot mix plants, practice areas, water bodies, natural drainage stockpile areas, storage channels, flood plains & storage areas, and areas, and groundwater recharge areas, disposal areas. disposal forests, vegetative lands, etc. areas. • Locate at sites that will not promote instability, flooding and result in destruction of natural drainage, vegetation, irrigation, & drinking water supply; • For private lands, obtain land owner‟s (not lessees) written consent; indicate the requirement for reinstatement to original • Site should have a minimum buffer of 0.5 – 1 km from all socially, environmentally sensitive areas (eg., residential, socio-cultural areas & water bodies (0.5 km), forests (1km), etc.,) • Take extreme care in selecting sites to avoid direct disposal to water body which will inconvenience the community. • Document site‟s pre-project conditions Sources of Extraction of • Obtain material only existing DBOC to identify (i)List of approved Part of project Materials materials can disrupt borrow sites/quarries already sources that have all quarry sites costs natural land permitted by the Department of permits, if required, And sources of contours and Mines and Geology; obtain permits, and materials; vegetation resulting • If new quarries sites/quarries are submit to PIU in accelerated necessary, contractor shall be (ii)Biddocumentto include erosion, disturbance obtain all necessary permissions PIU to check and requirementforverification in natural drainage as per the law in force. approve of suitability of patterns, ponding • Contractor to obtain construction sourcesandpermit and water logging, materials only after written foradditional quarry and water pollution. permission / approval of PIU for sitesif necessary. respective sources • Maintain a construction material register at the site Consents, Failure to obtain • Obtain all necessary consents, PMU / PIU to obtain Incorporated in final No cost required. permits, necessary permits, clearance, NOCs, etc project clearances; design and Cost of obtaining clearances, consents, permits, required for the project prior to DBOC to provide communicated to all consents, NOCs, etc. NOCs, etc. can award of contact or start of civil necessary assistance contractors. permits, clearance, result to design works, as necessary. NOCs, etc. prior to revisions and/or • Include in detailed designs, DBOC to obtain start of civil works stoppage of works drawings and documents all construction permits & responsibility of regulatory conditions and PIU to ensure PIU. provisions, where required • Contractor to identify & obtain all necessary approvals, including in compliance with labour laws, before start of construction; • Contractor to acknowledge in writing to PIU and provide copies of all obtained permits, clearance, NOCs, etc. • Obtain details from PHED/SMC DBOC in Detailed construction No cost Asbestos Health risk due to on location of underground AC coordination with PIU drawings showing required. Cement exposure to pipes and ULB alignment of AC pipes Pipes asbestos • Locate the new piper carefully to Mitigation materials avoid encountering AC pipes measures are • Leave the AC pipes undisturbed part of TOR of in the ground. PIU and PMDSC

Table 28: Environmental Management Plan of Anticipated Impacts during Construction Field Anticipated Impact Mitigation Measures Responsible for MonitoringofMitigation Cost and Source Implementation/ of Funds Monitoring EMP Irreversible impact to the • Project manager and DBO (i) Certificate of Completion Cost of EMP Implementation environment, workers, and all key workers will be Contractor (Safeguards Compliance Implementation Training community required to undergo Orientation) Orientation training on EMP Training to implementation (ii) Posting of EMP at contractor is including spoils/waste worksites responsibility management, of PMU. Standard operating Other costs procedures (SOP) for responsibility construction works; of contractor. occupational health and safety (OH&S), core labor laws, applicable environmental laws, etc.

Air Quality Emissionsfrom construction • Consult with PIU on DBOContractor (i) Location of stock Cost for vehicles, equipment, and the designated areas piles; implementation machineryusedfor excavation for stockpiling of clay, (ii)Complaints from sensitive of mitigation and construction resulting to soils, gravel, and receptors; measures dustsand increase in other construction (iii) Heavy equipment and responsibility concentrationof vehicle-related of contractor. materials; machinery with air pollution pollutants such as carbon • Damp down exposed control devices; monoxide, sulfur oxides, soil and any Air quality particulate matter, nitrous stockpiled on site by (iv)Ambient air for monitoring oxides, and hydrocarbons) spraying with water respirable particulate matter costs are when necessary (RPM) and suspended included in the during dry weather; particulate matter EMP costs of • Use tarpaulins to (SPM); project cover sand and other loose material when (v)Vehicular emissions such transported as sulphur dioxide(SO2), by trucks; and nitrous oxides (NOx),carbon • Clean wheels and monoxide (CO), and undercarriage of haul hydrocarbons trucks prior to leaving construction site • Disallow access in the work area except workers to limit soil disturbance and prevent access by barricading and security personnel • Fit all heavy equipment and machinery with air pollution control devices which are operating correctly;all the vehicle shall meet the emission norms and shall have valid pollution under control (PUC) certificate (Appendix 3) Surface water Mobilizationof settled silt • Avoid stockpiling of DBOContractor (i)Areas for stockpiles, Cost for quality materials, run-offfrom earth fill especially storage of fuels and implementation stockpiled materials, and during the monsoon lubricants and waste of mitigation chemical contamination from season unless materials; measures fuels and lubricants during covered by tarpaulins construction works can responsibility of or plastic sheets; (ii)Number of silt traps contaminate nearby surface contractor. • Prioritize re-use of installed along drainages water quality. excess spoils and leading to water bodies; materials in the Water quality construction works. If (iii) Recordsof surface water monitoring spoils will be quality inspection; costs are disposed, consult with included in the MPUDC/PMC on (iv) Effectiveness of water EMP costs of designated disposal management measures; areas; project

• Install temporary silt (v) For inland water: traps or sedimentation basins along the suspended solids,oil and drainage leading to grease, biological oxygen the water bodies; demand (BOD),and coliforms. • Place storage areas for fuels and lubricants away from any drainage leading to water bodies; • Dispose any wastes generated by construction activities in designated sites; and • Conduct surface quality inspection according to the Environmental Management Plan (EMP). Surface water Pollution of dam/River due to • Select a construction DBO (i) No visible degradation to Cost for quality jack well construction methodology that is Contractor nearby drainages, nallahs or implementation least disturbing, and water bodies due to civil of mitigation appropriate for the in- situ soil condition, and works measures able to complete the responsibility of construction work (ii) water quality monitoring contractor. prior to onset of results monsoon • Schedule the construction works during low water level period – late winter months to pre monsoon (February – June/July); ensure that works are completed during the same period to prior to onset of monsoon; confirm with dam authorities on release of water; avoid scheduling the works during water release period. • Erect temporary barriers to form enclosed construction area with least disturbance • Allow adequate time settle the distributed solids to prior to pumping out water; only clear/clarified water shall be pumped back into the reservoir; any silt laden water should be pumped to a silt pond • Avoid/minimize use of fuels, chemicals and lubricants; ensure no spillage

NoiseLevels Increase innoiseleveldueto • Plan activities in DBOContractor (i) Complaints from sensitive Cost for earth-moving and excavation consultation with PIU receptors; implementation equipment, and the so that activities with of mitigation transportation of the greatest potential (ii) Use of silencers in noise- measures to generate noise are equipment, producing equipment and responsibility of conducted during sound barriers; materials, and people periods of the day contractor.

which will result in least disturbance; (iii) Equivalent day and night time noise levels • Require horns not be used unless it is necessary to warn other road users or animals of the vehicle’s approach; • Minimize noise from construction equipment by using vehicle silencers, fitting jackhammers with noise- reducing mufflers, and portable street barriers the sound impact to surrounding sensitive receptor; and • Maintain maximum sound levels not exceeding 80 decibels (dbA) when measured at a distance of 10 m or more from the vehicle/s. • Identify any buildings at risk from vibration damage and avoiding any use of pneumatic drills or heavy vehicles in the vicinity; Existing Disruption of service and • Obtain from PIU/ULB DBOContractor Existing Utilities Cost for Infrastructure damage to existing the listof affected ContingencyPlan implementation and Facilities infrastructure at specified utilities and operators project location of mitigation if any; measures • Prepare a responsibility of contingency plan to include actions to be contractor. done in case of

unintentional interruption of service Landscape Solid wastes as well as excess • Prepare and DBO Contractor (i) Waste Management Plan; Cost for and construction materials implement Waste implementation Aesthetics Management Plan; (ii) Complaints from sensitive receptors; of mitigation • Avoid stockpiling of measures excess excavated (iii) Give PIU to report in responsibility of soils; writing that the necessary contractor. • Coordinate with environmental restoration AMC/PHED for work has been adequately beneficial uses of performed before acceptance excess excavated of work.

soils or immediately (iv) Worksite clear of dispose to hazardous wastes such as designated areas; oil/fuel • Recover used oil and lubricants and reuse (v) Worksite clear of any or remove from the excess excavated earth, sites; excess construction materials, and solid waste such as • Manage solid waste removed concrete, wood, according to the packaging materials, empty following preference containers hierarchy: reuse, recycling and disposal to designated areas; • Remove allwreckage, rubbish; and • Request PIU to report in writing that the necessary environmental restoration work has been adequately performed before acceptance of work. Accessibility Traffic problems and conflicts • Plan transportation DBO Contractor (i) Traffic Management Plan; Cost for near project locations and haul routes so that heavy implementation road vehicles do not use (ii) Complaints from sensitive of mitigation narrow local roads, receptors; measures except in the responsibility of immediate vicinity of (iii)Number of signages contractor. delivery sites; placed at subproject location. • Schedule transport and hauling activities during non-peak hours; • Locate entry and exit points in areas where there is low potential for traffic congestion; • Keep the site free from all unnecessary obstructions; • Drive vehicles in a considerate manner; • Coordinate with Local Traffic Office for temporary road diversions and with for provision of traffic aids if transportation activities cannot be avoided during peak hours; and • Notify affected sensitive receptors by providing sign boards informing nature and duration of construction works and contact numbers for concerns/complaints. Socio-Economic Impede the access of residents • Leave spaces for DBO Contractor (i) Complaints from sensitive Cost for –Income. And customers to nearby shops access between receptors; implementation mounds of soil; (ii)Number ofwalkways, of mitigation • Provide walkways and signages, and metal sheets measures metal sheets where placed at subproject location. responsibility of required for people; contractor. • Increase workforce in front of critical areas such as institutions, place of worship, business establishment, hospitals, and schools; • Consult businesses and institutions regarding operating hours and factoring this in work schedules; and • Provide sign boards for pedestrians to inform nature and duration of construction works and contact numbers for concerns / complaints. Socio-Economic Generation of contractual • Employ at least 50% DBO Contractor (i) Employmentrecords; Cost for - Employment employment and increase in of the labour force, or implementation to the maximum (ii) Records of sources localrevenue of materials of mitigation extent, local persons measures within the 2-km responsibility of immediate area if manpower is contractor. available; and • Secure construction materials from local market. Occupational Occupationalhazardswhichcan • Comply with all DBO Contractor (i) Site-specific Health Cost for Healthandsafety ariseduringwork national, state and and implementation local core labor laws safety(H&S) of mitigation Plan; (see Appendix 6of this measures IEE) responsibility of • Following (ii) Equippedfirst- internationally aidstations; contractor. recognized health and safety standards such (iii)Medicalinsurance as the World Bank coverage for workers; Group’s Environment, Health and Safety (iv) Guidelines (IFC’s Numberofaccidents; General EHS Guidelines 9 and (v)Supplies of potabledrinking Sector Specific water; (Water and Sanitation) (vi)Cleaneating areaswhere Guidelines10). workersare not exposed to • Develop and hazardous ornoxious implement site- substances; specific Health and safety (H&S) Plan (vii) record of H&S orientation which will include trainings measures such as: (a) excluding public from (viii) personal protective the site; (b) ensuring equipments; all workers are

9 https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B- %2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 10 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B- %2BWater%2Band%2BSanitation.pdf?MOD=AJPERES

provided with and use (ix) % of moving equipment Personal Protective outfitted with audible back-up Equipment like alarms; helmet, gumboot, safety belt, gloves, (xi) sign boardsfor hazardous nose musk and ear areassuch asenergized plugs; (c) H&S Training for all site electrical devices and lines, personnel; (d) servicerooms housing high documented voltage equipment, and areas procedures to be (xii) Compliance to core labor followed for all site laws (see Appendix 6 of this activities; and (e) IEE documentation of

work-related accidents; • Ensure that qualified first-aid can be provided at all times. Equipped first-aid stations shall be easily accessible throughout the site; • Provide medical insurance coverage for workers; • Secure all installations from unauthorized intrusion and accident risks; • Provide supplies of potable drinking water; • Provide clean eating areas where workers are not exposed to hazardous or noxious substances; • Provide H&S orientation training to all new workers to ensure that they are apprised of the basic site rules of work at the site, personal protective protection, and preventing injuring to fellow workers; • Provide visitor orientation if visitors to the site can gain access to areas where hazardous conditions or substances may be present. Ensure also that visitor/s do not enter hazard areas unescorted; • Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas; • Ensure moving equipment is outfitted with audible back-up alarms; • Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and • Disallow worker exposure to noise level greater than 85 dBA for a duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively.

Community Traffic accidents and vehicle • Plan routes to avoid DBO Contractor (i) Traffic Management Plan; (Cost for Healthandsafety. collisionwithpedestriansduring times of peak- implementation materialandwastetransportation Pedestrian activities. (ii) Complaints from sensitive of mitigation • Liaise with receptors measures MPUDC/PMC in responsibility of identifying high-risk areas on route contractor. cards/maps. • Maintain regularly the vehicles and use of manufacturer- approved parts to minimize potentially serious accidents caused by equipment malfunction or premature failure. • Provide road signs and flag persons to warn. Safety of Trench excavation in in narrow • Provide prior DBO Contractor Complaints from neighborhood (Cost for sensitive groups streets will pose high risk to information to the and monitoring of accidents implementation (children, elders children and elders in the locality local people about the of mitigation etc.) and others nature and duration of measures pedestrians in work responsibility of narrow streets • Conduct awareness program on safety contractor during the construction work • Undertake the construction work stretch-wise; excavation, pipe laying and trench refilling should be completed on the same day • Provide barricades, and deploy security personnel to ensure safe movement of people and also to prevent unnecessary entry and to avoid accidental fall into open trenches

Work Camps Temporary air and noise • Consult with PIU DBO Contractor (i) Complaints from sensitive (Cost for and worksites pollution frommachine before locating project receptors; implementation of mitigation operation, water pollution from offices, sheds, and (ii) Drinking water and measures storage and use of fuels, oils, construction plants; responsibility of • Minimize removal of sanitation facilities for solvents, and lubricants contractor vegetation and employees disallow cutting of Unsanitary and poor living trees; conditions for workers • Provide drinking water, water for other uses, and sanitation facilities for employees; • Ensure conditions of livability at work camps are maintained at the highest standards possible at all times; Prohibit employees from poaching wildlife and cutting of trees for firewood; • Train employees in the storage and handling of materials which can potentially cause soil contamination; • Recover used oil and lubricants and reuse or remove from the site; • Manage solid waste according to the preference hierarchy: reuse, recycling and disposal to designated areas; • Ensure unauthorized persons specially children are not allowed in any worksite at any given time. Ecological Loss of vegetation and tree cover • Avoid removal of DBO Contractor PIU to report in writing the no of Cost for Resources – vegetation / tree trees cut and planted. implementation Terrestrial cutting of mitigation measures • If unavoidable, responsibility of minimize as far as contractor possible, and obtain tree-cutting permit • Plant 3 trees for every one cut Land use Environmental Issues due to land • The impact due to Not applicable Not applicable Not applicable use change change in land use will be negligible due to this project.

Asbestos Cement Health risks associated with AC • leave AC pipes in-situ DBO Contractor On site observations & records Cost for (AC) Materials pipes untouched implementation of mitigation measures responsibility of contractor.

Submission of Unsatisfactory compliance to • Appointment of (I) DBO contractor Availability and competency of Cost for EMP EMP EHS Supervisor and appointed supervisor implementation of implementation Archeological Monthly report mitigation report supervisor to ensure measures EMP implementation responsibility of • Timely submission of contractor monitoring reports including pictures Post-construction Damage due to debris, spoils, • Remove all spoils DBO contractor PIU report in writing that (i) Cost for clean-up excess construction materials wreckage, rubbish, or worksite is restored to original implementation of temporary structures conditions; (ii) camp has been mitigation (such as buildings, vacated and restored to pre- measures shelters, and latrines) project conditions; (iii) all responsibility of which are no longer construction related structures contractor required; and not relevant to O&M are • All excavated roads removed; and (iv) worksite shall be reinstated to clean-up is satisfactory. original condition. • All disrupted utilities restored • All affected structures rehabilitated/compens ated • The area that previously housed the construction camp is to be checked for spills of substances such as oil, paint, etc. and these shall be cleaned up. • All hardened surfaces within the construction camp area shall be ripped, all imported materials removed, and the area shall be top soiled and regrassed using the guidelines set out in the revegetation specification that forms part of this document. • The contractor must arrange the cancellation of all temporary services. • Request PIU to report in writing that worksites and camps have been vacated and restored to pre- project conditions before acceptance of work.

Table 29: Environmental Management Plan of Anticipated Impacts during Operation Field Anticipated Impact Mitigation Measures Responsible for MonitoringofMitigation Cost and Source Implementation/ of Funds Monitoring Check for Loss of water, • Effective leak detection and water DBO Contractor PIU and Respective blockage and increased demand auditing to reduce the water losses Nagar Parishads Operating costs leakage and inconvenience problems to consumers & reducing the general public water losses

Water • Ensure protection of water source Nagar Parishads & PMU in coordination Operating costs contamination Impacts on public quality any entry of wastewater DBO Contractor with WRD – raw water health into the river upstream of contamination Dam/River sites should be PIU, ULBs at source and prevented. treated water • Contamination of treated water during during transmission and transmission distribution should be prevented by quickly identifying, isolating and repairing the leak section. Develop a system of leak detection and rectification. • Conduct regular monitoring of raw & treated water and ensure that water supplied at all times meets the drinking water standards (Appendix 5)

Discharge Pollution of streams • Backwash water will be recirculate DBO Contractor PIU and Respective Operating costs the impurities /drains so no wastewater generated from Nagar Parishads and other WTP solids • Maintain the mechanical parts as collected due per the maintenance plan to avoid to filtration any hazards and back wash

Sludge Land and water • Collect the sludge from WTP units, DBO Contractor PIU and Respective Operating costs generation pollution, impacts on dry in sludge drying beds, and Nagar Parishads health &environment reuse / dispose safely as per the design Increased in Water pollution, and • Sanitation facilities needs to be PIU and Nagar PMU To be identified - sewage impacts on public improved at community level and Parishads PIU, Nagar generation health and at the town level to meet the Parishads environment increased sewage demand Generation of Impacts on public • Collect solid wastes and dispose DBO Contractor PIU and Respective Operating costs waste health and to approved disposal yards Nagar Parishads materials environment Occupational Health, social and • Provide appropriate PPE to DBO Contractor PIU and Respective Operating costs health and economic impacts workers training on its proper use Nagar Parishads safety on the workers • Use fall protection equipment when working at heights. • Maintain work areas to minimize slipping and tripping hazards. • Implement a training program for operators who work with chlorine regarding safe handling practices and emergency response procedures. • Prepare escape plans from areas where there might be a chlorine emission. • Install safety showers and eye wash stations near the chlorine equipment and other areas where hazardous chemicals are stored or used. • Prohibit eating, smoking, and drinking except in designated areas.

Table 30: Environmental Monitoring Plan of Anticipated Impacts during Construction Monitoring field Monitoring Monitoring parameters Frequency Responsibility Cost & Source of Funds location Construction All work sites Implementation of dust Twice Supervising staff No costs required disturbances, control, noise control, Weekly during and safeguards nuisances, public& traffic management construction specialists worker safety, &safety measures. Regularly as required during construction; Site inspection checklist to checklist to be filled review implementation is monthly once appended at Appendix 22.

Air quality For Karera Town PM10, PM2.5 NO2, O2, Once before start of DBO Contractor Cost for implementation 4 locations (one CO construction of monitoring measures WTP site and 3 Quarterly (yearly 4- responsibility of OHT / distribution times) during contractor sites) construction (2 year (36 samples x 5000 per period considered) sample = 1,80,000)

For Pichhore PM10, PM2.5 NO2, O2, Once before start of DBO Contractor Cost for implementation Town CO construction of monitoring measures 4 locations (one Quarterly (yearly 4- responsibility of WTP site and 3 times) during contractor GSR/distribution construction (2 year (36 samples x 5000 per site) period considered) sample = 1,80,000)

For Aron town, 4 PM10, PM2.5 NO2, O2, Once before start of DBO Contractor Cost for implementation locations (one CO construction of monitoring measures WTP site and 3 Quarterly (yearly 4- responsibility of OHT/ distribution times) during contractor site) construction (2 year (36 samples x 5000 per period considered) sample = 1,80,000)

For Bairad town 4 PM10, PM2.5 NO2, O2, Once before start of DBO Contractor 36 samples x Rs 1500 per locations(one CO construction, sample = Rs 1,80,000 WTP site and 3 Quarterly (yearly 4- Project Cost OHT/ distribution times) during network in each construction (2 year zone) period considered) 4 locations for PM10, PM2.5 NO2, O2, Once before start of DBO Contractor Cost for implementation of Isagarh (OHT site CO construction monitoring measures near hospital responsibility of contractor compound and at Quarterly (yearly 4- (36 samples x 5000 per distribution sites times) during sample = Rs 1,80,000 construction (1.5 year period considered) For Vijaypur Town PM10, PM2.5 NO2, O2, Once before start of DBO Contractor 36 samples x Rs 5000 4 locations. 1 CO construction, Quarterly per sample = Rs 1,80,000 location; (i) at (yearly 4- times) during Project Cost WTP site, construction (2 year (ii)3 location at OHT/ distribution period considered) work site in Vijaypur town

Ambient Noise For Karera Town Day and Night Once before start of Cost for implementation Quality 4 locations (one construction of monitoring measures WTP site and 3 Quarterly (yearly 4- responsibility of OHT sites) times) during contractor construction (2 year (36 samples x 1500 per period considered) sample = 54000)

For Pichhore Day and Night Once before start of Cost for implementation Town construction of monitoring measures 4 locations (one Quarterly (yearly 4- responsibility of WTP site and 3 times) during contractor GSR/ distribution construction (2 year (36 samples x 1500 per site) period considered) sample = 54000)

For Aron, 4 Day and Night Once before start of Cost for implementation locations (one construction of monitoring measures WTP site and 3 Quarterly (yearly 4- responsibility of OHT & distribution times) during contractor sites) construction (2 year (36 samples x 1500 per period considered) sample = 54000) For Bairad 4 Day and Night Once before start of 36 samples x Rs 1500 locations; (i) at construction, per sample = Rs 54,000 WTP site, Quarterly (yearly 4- (ii)03 at OHT & times) during DBO Contractor distribution work construction (2 year site period considered)

For Isagarh 4 Day and Night Once before start of DBO Contractor Cost for implementation of locations construction monitoring measures responsibility of contractor Quarterly (yearly 4- (36 samples x 1500 per times) during sample = 54,000) construction (1.5year period considered) For Vijaypur 4 Day and Night Once before start of 36 samples x Rs 1500 per locations; (i) at construction, Quarterly sample = Rs 54,000 WTP site, (yearly 4- times) during (ii) 03 at OHT & DBO Contractor construction (2 year distribution work site period considered) Surface water quality 5 location (near pH, Oil & grease, Cl, F, Once before start of DBO Contractor 65 samples x Rs 4000 per intake well NO3, TC, FC,Hardness, construction monthly sample = Rs 2,60,000 construction site Turbidity, BOD,COD, DO, during construction (12 at water source) Total Alkalnity months period considered) Ground Water Quality 05 Sample from pH, Cl, F, NO3, TC, Once before start of DBO Contractor 25 samples x Rs 4000 per – Source 04 tube wells FC,Hardness, Total construction monthly sample = Rs 100,000 (Isagarhonly) randomly Alkalnity & Iron during construction (12

months period At each inlet of clear water sump considered) wells Surface Water Surface Water pH, Oil & grease, Cl, F, Once before start of Quality - Quality - NO3, TC, FC,Hardness, construction monthly 39 samples x Rs 4000 per Pond/stream/river in Pond/stream/river Turbidity, BOD,COD, DO, sample = Rs 1,56,000 during construction (12 DBO Contractor town in town Total Alkalnity months period Project Cost considered) Table 31: Environmental Monitoring Plan of Anticipated Impacts during Operation Monitoring Monitoringfield location Monitoringparameters Frequency Responsibility Cost & Source of Funds

Sourcewaterquality Samoha dam, Futiwar pH, Cl,F,NO3,TC,FC,Hardness,Turbidity Yearly Twice Respective ULBs Operating dam and Aron, bairad, ,DO,TotalAlkalnity ((pre monsoon costsof Vijaypur towns heavymetals&pesticides and post respective NPs And Ground water monsoon) quality for all tubewells in Isagarh

Groundwater quality All tube wells pH, Cl, F, NO3, TC, FC, Hardness, Turbidity BOD, Year twice Isagarh Nagar Operating costs of COD, DO, Total Alkalnity (pre monsoon Parishads respective NPs heavy metals & pesticides and post monsoon

Monitoringofquality Consumerend- pH, Nitrite, Nitrate, Turbidity, Total Monthly ULBs Operating ofwatersuppliedto randomsamplingin Alkalnity,TotalcoliformandFeacalcoliform and as once costsof consumers allzones per drinking water standard (IS-10500, 2004) respective NPs

Sludge Disposal Analysis for concentration of heavy metals and Yearly once ULBs Operating Management confirm that value are within the following limits costs of (all units are in mg/kg dry basis except pH) respective NPs • Arseic - 10.00 • Cadiu - 5.00 • Chroiu - 50.00 • Copper - 300.00 • Mercury - 0.15 • Nickel - 50.00 • Zic - 1000.00 • Lead - 100.00 • PH - 5.5-8.5

B. IMLEMENTATION ARRANGEMENT 175. Urban Development and Environment Department (UDED) of Government of Madhya Pradesh (GoMP) will be the Executing Agency for the Program, responsible for management, coordination and execution of all investment program activities. Implementing Agency will be the Madhya Pradesh Urban Development Company (MPUDC) of GoMP, which will implement this program via a Project Management Unit (PMU) at Bhopal, and Project Implementation Units (PIUs) at project towns. PMU will appoint contractors to build infrastructure and PIUs will coordinate the construction. PMU and PIUs will be assisted by Program Management Consultants (PMC).

176. The PMU and PIUs will be supported by several teams of Design Consultants in preparation of preliminary engineering designs.

177. Program Management Consultant (PMC) centrally located in PMU and with field teams located in PIUs shall be responsible for implementation of the Program. All infrastructure contracts will be procured through performance-based contracts (PBCs) and include buildoperate (BO) framework. Based on the preliminary designs prepared by Design Consultants, the DBO (design-build-operate) Contractor will design, construct, commission and operate for 10 years, after which it will be transferred to the respective ULB.

178. Water Resource Review Committee (WRRC) is constituted to undertake a thorough review of the source when recommended by the Design Consultant in regard to techno economic feasibility and sustainability especially ensuring climate change resilience, and Technical Review Committee (TRC) to review and approve the preliminary designs developed by the Design Consultants

179. Two Committees - an Empowered Committee cum Executive Committee and a Technical Clearance and Tender Committee have been constituted by the Government to be responsible for effective and timely implementation of the Program.

180. Safeguards Compliance Responsibilities. At PMU, there will be two safeguard specialists: (i) Project Officer (Environment) and (ii) Social & Gender Offer, who will responsible for compliance with the environmental and social safeguards in program implementation. PO (Environment) will have overall responsibility in implementation of the investment program as per the Environmental Assessment & Review Framework (EARF) agreed between ADB and the government. At individual subproject level, PO will ensure that environmental assessment is conducted, and a project-specific is prepared and implemented, and the compliance, and corrective actions, if any are reported as required.

181. Project Officer (Environment) at PMU and Assistant Safeguard Officer (ASO) at each of the PIU will be responsible for environment safeguards tasks and will be supported by PMC. At PMC’s environmental safeguards staff include an Environmental Specialist Consultant located centrally in Bhopal, and will be responsible for all safeguard tasks, and he/she is supported by an Environmental Engineer in each PIU. At the time of submission of this IEE, Environmental Specialist at Bhopal has been appointed in PMC, but Environmental Engineer is not appointed in PIU – Gwalior by PMC. Environmental engineer is likely to appointed by PMC at earliest. It is under process. Contractor personnel will include an Environment, Health and Safety (EHS) supervisor.

182. PMU Responsibilities: PO (Environment) will be supported by PMC, which will be staffed with an Environmental Specialist, and Environmental Coordinators. Key tasks and responsibilities of the PO (Environment) for this subproject include the following:

Bidding Stage:

(i) Priorto invitation of bids for civil works contract, ensure that ✓ Water Resources Department (WRD) permission is obtained for sourcing water from Reservoirs and to construct jack well cum pump house in the reservoir ✓ Consent for establishment(CFE) is obtained fromMPPCBfor WTP construction (ii) Ensure that EMPs are included in bidding documents and civil workscontracts (iii) Ensure that the bid/contract documents include specific provisions requiring contractors to comply with all applicable labor laws and core labor standards including: ✓ Labour welfare measures and provision of amenities ✓ prohibition of child labor as defined in national legislation for construction and maintenance activities ✓ equal pay for equal work of equal value regardless of gender, ethnicity, or caste ✓ elimination of forced labor ✓ The requirement to disseminate information on sexually transmitted diseases, including HIV/AIDS, to employees and local communities surrounding the project sites. (iv) Ensure that staff required for implementation of EMP (EHS officer for Townsis included in the bid requirements (v) Ensure that EMP cost is included in the project cost (vi) In the pre-bid meeting, provide insight into the EARF requirements, IEE update, EMP measures, and overall compliance requirementsto the bidders

Construction Stage:

(i) Facilitate and ensure that all necessary environmental clearances/permissions, including that of contractor’s are in place prior to start of construction (ii) Organize an induction course for the training of contractors, preparing them on EMP implementation, environmental monitoring, and on taking immediate action to remedy unexpected adverse impacts or ineffective mitigation measures found during the course of implementation. (iii) provide oversight on environmental management aspects of subprojects and ensure EMPs are implemented by PIU and contractors (iv) Supervise and provide guidance to the PIUs to properly carry out the environmental monitoring as per the EMP (v) Oversee grievance redress mechanism to address any grievances brought about in a timelymanner; ensurethat records areproperlymaintained (vi) Consolidate monthly environmental monitoring reports from PIU and submit semi-annual monitoring reportsto ADB (vii) Oversee site closures to ensure that all work / facility sites are restored properly prior to issuing work completion certificate to the contractor

Operation Stage:

(i) Ensure and consent for operation (CFO) is obtained from MPPCB for WTP prior to start of operation

183. PIU Responsibilities: PIU will be headed by a Project Manager and supported by PMC. An Assistant Project Manager of PIU will be given additional responsibilities of safeguard tasks and will be designated as Assistant Environmental Officer (ASO). ASO will be supported by PMC Environmental Specialist and Environmental Coordinator. Key tasks and responsibilities of the ASO for this subproject include the following: (i) Provide necessarysupport to PIU and Nagar Parishads in obtaining permission from WRD and MPPCB; liaison with PMU and regulatoryagencies (ii) Oversee day-to-day implementation of EMPs by contractors, including compliance with all government rules and regulations, take necessaryaction for obtaining rights of way (iii) Oversee environmental monitoring bycontractors (iv) Take corrective actionswhen necessaryto ensure no environmental impacts (v) Submit monthly environmental monitoring reports to PMU (vi) Conduct continuous public consultation and awareness (vii) Address any grievances brought about through the grievance redress mechanism in a timelymanner as per the EMP

184. Contractor’s responsibilities

Bidding Stage:

(i) Understand the EMP requirementsand allocate necessaryresources (budget, staff, etc (ii) Understand the regulatory compliance requirements related to labour welfare, safety, environment etc.,

Design Stage:

(i) Review the IEE Report including the REA checklist, category and the EMP, and conduct site visits to understand the environmental sensitivity of the project sites. (ii) Update the REA checklist, confirm the category, and update/revise the IEE Report of the project reflecting the changes /amendments /additions that are effected in the project during the detailed design (iii) Update / revise and finalize the EMP (iv) Provide all necessary technical assistance to PIU / ULB in obtaining regulatory clearances/approvals. (v) Ensure that Consent for establishment (CFE) is obtained from MPPCB for WTP construction prior to start of work (vi) Ensure that all design-related measures of the EMP, and conditions, if any, of government regulatory agencies (like MPPCB consent conditions) are duly included in the final designs. (vii) Ensure that all the measures, and improvement works required to ensure the compliance of the existing WTP with ADB SPS 2009 and government regulations are included

ConstructionStage:

(i) Obtain all necessary permissions/approvals (labour, pollution control, quarries, right of ways, etc.) priorto start of work (ii) Mobilize EHS officer & Archeological Superviser prior to start of work (iii) Confirm with PIU availability of rights of way at all project sites prior to start of work. (iv) Prepare and Submit: ✓ Construction wastemanagement (CWM). ✓ Trafficmanagement ™plan (v) Implement the mitigation measures as per the EMP including CWM & TM Plans (vi) Follow the EMP measures/guidelines for establishment of temporary construction camps, construction waste disposal sites, and material borrow areas, etc., (vii) Implement EMP and ensure compliance with all the mitigation and enhancement measures (viii) Conduct environmental monitoring (air, noise and water etc.) as per the EMP (ix) Undertake immediate action as suggested by PIU / PMU / PMC to remedy unexpected adverse impacts or ineffective mitigation measures found during the course of implementation (x) Submit monthlycompliance reportson EMP implementation (xi) Act promptly on public complaints and grievances related to construction work and redress in a timelymanner in coordination with PIU (xii) Comply with applicable government rules and regulations

Operation Stage:

(i) Obtain CFO from MPPCB in coordination with the ULB, and comply with MPPCB conditions, if any, during the operation phase (ii) Implement the operation phase EMP including the monitoring plan (iii) Submit quarterly EMP implementation report.

C. MONITORING AND REPORTING 185. During the detailed design stage, DBO Contractor should confirm PMU the mobilization of Environmental Expert for IEE update and integrating design stage EMP into designs.

186. Immediately after mobilization and prior to commencement of the works, the contractor will submit a compliance report to PIU that all identified pre-construction mitigation measures as detailed in the EMP are undertaken. Contractor should confirm that the staff for EMP implementation (EHS) is mobilized. PMU with the assistance of the PMC will review the report and permit commencement of works

187. During operation, the contractor will conduct management and monitoring actions as per the operation stage EMP, and submit to PMU and ULB a quarterly report on EMP implementation and compliance.

188. During construction, results from internal monitoring by the contractor will be reflected in their monthly EMP implementation reports to the PIU. ASO will review and advise contractors for corrective actions if necessary. Quarterly report summarizing compliance and corrective measures taken will be prepared by by PMC field team at PIU and submitted to PMU (Appendix 23).

189. Based on monthly & quarterly reports and measurements, PMU will draft, review, and submit to ADB, 6-monthly semi-annual Environmental Monitoring Report (EMR). Once concurrence from the ADB is received the report will be disclosed in the UDED and PMU websites. 190. ADB will review project performance against the MPUSIP commitments as agreed in the legal documents. The extent of ADB’s monitoring and supervision activities will be commensurate with the project’s risks and impacts. Monitoring and supervising of social and environmental safeguards will be integrated into the project performance management system

D. Training Needs 191. The following Table 32 presents the outline of capacity building program to ensure EMP implementation. The estimated cost (excluding trainings of contractors which will be part of EMP implementation cost during construction) to be covered by the project’s capacity building program. The detailed cost and specific modules will be customized for the available skill set after assessing the capabilities of the target participants and the requirements of the project by the ES of PDMC.

Table 32: Outline Capacity Building Program on EMP Implementation Description Target Estimate Cost and Source Participants& (INR) of Funds Venue 1. Introduction and Sensitization to All staff and - Included in the Environmental Issues (1 day) consultants involved overall program - ADB Safeguards Policy Statement in the project cost - Government of India and Rajasthan applicable safeguard laws, regulations and At PMU, Bhopal policies including but not limited to core labor (combined program standards, OH&S, etc. for all subprojects) - Incorporation of EMP into the project design and contracts - Monitoring, reporting and corrective action planning 2. EMP implementation (1/2 day) All PIU staff, INR Included in - EMP mitigation & monitoring measures contractor staff and 100,000 subproject cost -Roles and responsibilities consultants involved (Lump estimates - Public relations, - Consultations in subproject towns. sum) - Grievance redress - Monitoring and corrective action planning At PIU - Reporting and disclosure - Construction site standard operating procedures (SOP) - AC pipe protocol - Traffic management plan - Waste management plan - Site clean-up & restoration 3. Contractors Orientation to Workers (1/2 Once before start of - Contractors cost Description Target Estimate Cost and Source Participants& (INR) of Funds Venue day) work, and thereafter - Environment, health and safety in project regular briefing every construction month once. Daily briefing on safety prior to start of work

All workers (including unskilled laborers)

E. EMP IMPLEMENTATION COST 192. Most of the mitigation measures require the contractors to adopt good site practice, which should be part of their normal procedures already, so there are unlikely to be major costs associated with compliance. The costs which are specific to EMP implementation and are not covered elsewhere in the projects are given below.

Table 33: Cost Estimates to Implement the EMP Particulars Stages Unit Total Rate Cost Costs No. (INR) (INR) Covered By A. Implementation Staff 1 Environmental Design & Pre- per 0.5 150000 75,000 Civil works Specialist Construction month contractor

2. EHS Supervisor Construction per 24 50,000 12,00,000 Civil month works contractor Subtotal(A) 12,75,000 B. Mitigation Measures 1 Consent for Pre- Lump 3,00,000 Project costs establishments & Construction sum consent for operation from MPPCB 2 Provision for tree Construction Per 100 1000 1.00,000 Civil works cutting & tree contractor compensatory plantation measures 1 Trafficmanagement Construction Lump - - 3.00,000 Civil works at work sites sum contractor (Pavement Markings, Channelizing Devices, Arrow Panels and Warning Lights)

Subtotal(B) 7,00,000 C Monitoring Measures 1 Air quality Construction Per 216 5000 10,80,000 Civil works monitoring Sampl contractor 2 Noise level Construction Pere 216 1500 3,24,000 Civil works monitoring Sampl contractor 3 Surface water Construction Pere 104 4000 4,16,000 Civil works monitoring Sampl contractor 4 Ground water Construction Pere 25 4000 100,000 Civil works monitoring Sampl contractor Subtotal (C) e 19,20,000 D. CapacityBuilding 1. Trainingon EMP Pre- lump 1,25,000 PMU implementation constructi sum on 2 Preparation of plans Pre- Lump 2,50,000 Civil works And protocols (traffic construction sum contractor management plan, waste (spoils) management plan etc., chance find protocal 3. Contractors Priorto Lump 1,25,000 Civil works Orientation Dispatch to sum contractor To Workers on EMP worksite implementation Subtotal (D) 5,00,000

Total(A+B+C+D) INR 43,95,000

X. CONCLUSION AND RECOMMENDATION 193. The process described in this document has assessed the environmental impacts of all elements of the Package 4D towns Karera, Pichhore, Aron, Bairad, Isagarh and Vijaypur water supply improvement subproject. All potential impacts were identified in relation to pre- construction, construction, and operation phases. Planning principles and design considerations have been reviewed and incorporated into the site planning and design process wherever possible; thus, environmental impacts as being due to the project design or location were not significant.

194. There are Karera bird sanctuary in the Karera sub project town at the western side of the town. It is situated approx. 14 km away from Karera town. There will not be any negative impact due to proposed project as impact will be only from construction and for limited time frame. Karera Wildlife sanctuary today has not a single bird species. Owing to villagers/public pressure and the extinction of the bird locally, the National Board for Wildlife and the Government of Madhya Pradesh have decided to denotify the sanctuary and is seeking the Centre's approval (Refer Appendix 26). The decision is now awaiting a final approval from the Supreme Court of India and should it come through, the sanctuary will become the country's first such reserve to lose its official recognition

195. There are two important location and design aspects. First, the proposed water supply schemes include design of new water sources, that include construction of Weir (for Aron), and drawing of water from different dams for Karera, Pichhhore, Vijaypur and Bairad town.

196. As per salient features of the Dams, it is assessed to be unlikely to have any issue of source sustainability for the Karera, Pichhore, Vijaypur and Bairad towns, where as in Aron town small weir is proposed.

197. Although none of the components are located within the forest, conduct of construction works and presence of workers, vehicles may damage /disturb the sensitive areas. Necessary precautionary measures are suggested to avoid any impacts.

198. There are Karera bird sanctuary in the Karera sub project town at the western side of the town. Subproject components are mostly located in the urban areas of of subprojects towns, where there are no sensitive environmental features. The proposed subproject components are located out of Karera bird sanctuary boundary but all are within the boundary of eco sensitive zone within the municipal limit in urban areas at a distance of 0.5km to 2.0 km from the boundary of Karera wildlife sanctuary as shown in google map annexed as Fig-24. There will not be any negative impact due to proposed project as impact will be only from construction and for limited time frame. Raw water rising main will be laid under ground along main existing road within ROW. WRD permission for abstraction of surface water & construction of intake already obtained which is appended as Appendix 24. As per MOEFCC Notification New Delhi 15th September 2017 – Commercial Extraction of surface water Construction activities within the Eco-Sensitive Zone is permitted as per building byelaws to meet the residential needs of the local residents such as construction and renovation of infrastructure including civic aminities (Refer Table 3, S. No. 14, S. No. 20 & S. No. 27 and Refer Appendix 18, Para 4, S. No. 14 S. No. 20- MOEFCC Notification, New Delhi 15th Sep 2017). However, it will be done with mitigation measures, as per applicable laws, rules and regulation and available guidelines. Also consultation conducted with forest official on dated 10.05.2018 at Office of Chief Conservator of Forest & Director, Madhav National Park, Shivpuri as Its management and control is under Field Director of Madhav National Park (Refer Appendix 7 & Appendix 10). Detailed discussions held and briefed about proposed components under water supply scheme for Karera town within eco-sensitive zone and its impact on Karera bird Sanctuary. They told that they have no objection as this project is to meet the daily residential needs of the local residents by providing with a constant supply of better quality water, subproject will improve the overall environmental quality of the town and surrounding areas.

199. Precaution must be taken care to minimize the noise during construction work to avoid any negative impact on bird sanctuary. The impact will be only for limited time during construction work. Since the proposed subprojects components such as RWRM, CWRM, WTP and OHTs works shall be limited to actual construction area and the access roads, but appropriate steps should be taken according to the nature of the risk.

200. Kuno Wildlife Sanctury which is also known as Palpur - Kuno Wildlife Sanctuary is situated at a distance of 10 km from Bairad town and 24 km from vijaypur town. None of the components are located within the boundary of Kuno wildlife sanctuary or its ecosensitive zone.

201. Water source sustainability of Samoha Dam for Karera, Futiwar dam for Pichhore town and Sindh River for Aron town, Pachipura dam for Bairad town and Existing stop dam on Kunwari river recently constructed by WRD for Vijaypur town, has been reviewed based on the available data. Permission of water resources department for this project, has been obtained.

202. For the Karera town, the demand of water supply for the year 2018, 2033 & 2048 are estimated to the tune of 5.40 MLD, 6.90 MLD & 8.30 MLD respectively. Thus maximum of 8.30 MLD intake form the source per annum i.e. 3030 ML (3.03 MCM) of drawl of water is to be ensured. Annual average recoupment of water in the tank every year is around 18.533 MCM. While the recoupment of water during rainy season is 18.533 MCM which is 4 times than the annual water demand of Karera town.

203. For the Pichhore town, the demand of water supply for the year 2018, 2033 & 2048 are estimated to the tune of 1.80 MLD, 2.30 MLD & 2.90 MLD respectively. Thus maximum of 2.90 MLD intake form the source per annum i.e. 1058.50 ML (1.06 MCM) of drawl of water is to be ensured. The annual recuperation of Futiwar dam is 4.95 MCM. The required quantity of water for Pichhore WSS has been ensured from the WRD Department.

204. Sustainability of Sindh River for supplying water to Aron was critically analyzed and it is make sure that sufficient water is available in River to supply the water in Aron for 2048.

205. To the extent possible surface water sources are adopted. Water requirement for Bairad town in year 2048 is 2.91 MLD and total water requirement per annum in 2048 is 1.06 Million Cubic Meters. The total live storage of Pachipura dam is 8.32 Million Cubic meters. Hence, total requirement of water for Bairad is 12.75% of live storage capacity of the dam. Hence the same is adopted as source for Bairad water supply scheme. Permission of water resources department is a prerequisite for the project, and this needs to be obtained prior to invitation of bids for civil works.

206. For Vijaypur, the Gauge-Discharge data obtained from water resources department for Kunwari River and sustainability of river has been reviewed based on the available data with Water Resources Department. Source water quality for Vijaypur town has been tested and found all the parameters are within the limits as per standards except coli form. Hence WTP is proposed for to treat the water. 207. Source water quality of Samoha dam for Karera town, Futiwar dam for Pichhore town and Sindh river for Aron town, Pachipura dam for Bairad town and Kunwari River for Vijaypur town was critically analyzed during the study and it was found suitable in terms of quality and quantity for supplying water in respective towns (Refer Table 16 & Appendix18). Water quality is appropriate for drinking water supply after treatment and disinfection. There will not be any negative impact on environment during operation phase of project. During construction work of intake well at Samoha dam there will be some negative impact on dam. But, impact will be only duly construction work and limited.

208. There is an important design issue related to selection of groundwater as source. In the absence of any reliable surface water source in the proximity, it is proposed to continue groundwater source for Isagarh. Ground water is potable and sufficient to fulfill the demand of town upto year 2048, because natural recharging is available by means of Sing Sagar Lake around town. In the proposed project existing tube wells are sufficient for year. However, given the current safe stage of groundwater development, the abstraction should be combined with groundwater augmentation measures, and therefore it is proposed to undertake a detail study and include the recommendation of the study in the project implementation. This study will look into both groundwater sustainability and quality.

209. During the construction phase, impacts mainly arise from the construction dust and noise, the need to dispose of large quantities of waste soil and import a similar amount of sand to support the sewer in the trenches; and from the disturbance of residents, businesses, traffic and important buildings by the construction work. The social impacts (access disruptions) due to construction activities are unavoidable, as the residential and commercial establishments exist along the roads where pipes will be laid. Appropriate mitigation measures are suggested. Minimize tree cutting and vegetation removal at WTP, and proper erosion control measures. As a feeder main is proposed on the bank of Sing Sagar lake, there is a risk of water pollution. Appropriate measures are suggested for Isagarh.

210. Anticipated impacts of water supply during operation and maintenance will be related to detection and repair of leaks, pipe bursts. These are, however, likely to be minimal, as proper design and selection of good quality pipe material shall mean that leaks are minimal. Leak repair work will be similar to the pipe-laying work. Application and handling of chlorine gas will involve certain risks, and appropriate measures are suggested for safe application.

211. The public participation processes undertaken during project design ensured stakeholders are engaged during the preparation of the IEE. The planned information disclosure measures and process for carrying out consultation with affected people will facilitate their participation during project implementation.

212. The project’s grievance redressal mechanism will provide the citizens with a platform for redressal of their grievances, and describes the informal and formal channels, time frame, and mechanisms for resolving complaints about environmental performance

213. The EMP will assist the PMU, PIU, PDMC and contractors in mitigating the environmental impacts, and guide them in the environmentally sound execution of the proposed project.

214. A copy of the EMP shall be kept on-site during the construction period at all times. The EMP shall be made binding on all contractors operating on the site, and will be included in the contractual clauses. Non-compliance with, or any deviation from, the conditions set out in this document shall constitute a failure in compliance

215. The project will benefit the general public by contributing to the long-term improvement of water supply and sewerage systems and community livability in towns. The potential adverse environmental impacts are mainly related to the construction period, which can be minimized by the mitigating measures and environmentally sound engineering and construction practices.

216. Therefore, as per ADB SPS, the project is classified as environmental category B and does not require further environmental impact assessment. However, to conform to government guidelines projects require (i) permission of WRD, GoMP for water abstraction from water Reservoirs (ii) WTP requires Consent for Establishment (CFE) and Consent for Operation (CFO) from Madhya Pradesh Pollution Control Board. These permissions/approvals shall be obtained prior to invitation of bids for civil works.

217. IEE report shall be updated during design stage by DBO contractor to reflect any change, amendment and will be reviewed and approved by PMU.

Appendix 1: Rapid Environment Assessment Checklist – Package 4D

Country/ Project: India/ Madhya Pradesh Urban Service Improvement Program – Karera, Pichhore, Aron, Bairad, Vijaypur & Isagarh Water Supply Subproject under Package-4D

Sector/ Division: Urban Development and Environment Department/ UDED

SCREEINING QUESTION YES NO REMARKS A. Project Sitt ing Is the project area ▪ Densely populated?  Subproject activities extend to the entire town including the densely populated areas. There are no major negative impacts envisaged, because pipeline will be located in unused government lands alongside the existing roads and can be constructed without causing disturbance to, houses, and commercial establishments. In narrow streets, disruption to road users is likely, and measure like best activity scheduling, alternative routes, prior information to road users, houses and shops will minimize the impact to acceptable levels. ▪ Heavy with development activities?  No ▪ Adjacent to or within any  Boundary of Karera bird sanctuary is environmentally sensitive areas? located inat a distance of 500 m from boundary of Karera Nagar Parishad. But there will not be any negative impact on the bird sanctuary as the construction work will be limited time of frame. ▪ Cultural heritage site  No ▪ Protected Area  No ▪ Wetland  No ▪ Mangrove  No ▪ Estuarine  No ▪ Buffer zone of protected area  No ▪ Special area for protecting biodiversity  No ▪ Bay  No B. Potential Environmental Impacts

Will the Project cause… • Pollution of raw water supply from  There are no significant water pollution upstream wastewater discharge sources in the catchment. Raw water from quality is tested and found that it is • Communities, industries, suitable for Domestic use. agriculture, and soil erosion runoff? • Impairment of historical/cultural  Not applicable monuments/areas and loss/damage to these sites? • Hazard of land subsidence caused  Not applicable, in five subproject towns by excessive ground water does not involve groundwater pumping? abstraction. Only in Isagarh town ground water abstraction involve. The quantity of water is very less. As per the recommendation of ground water testing report, the pumping will be done. • Social conflicts arising from  Project does not involve land displacement of communities? acquisition /displacement. No social conflicts envisaged • Conflicts in abstraction of raw water  No, the water will be abstracted with for water supply with other due Permission of Water Resource beneficial water uses for surface Department. For ground water and ground waters? abstraction existing tubewell will be utilized. Drinking water is priority as per the MP water policy. • Unsatisfactory raw water supply  Raw water Quality is tested and found (e.g. excessive pathogens or that it is suitable for Domestic use. mineral constituents)? Water will be subjected for treatment prior to supply • Delivery of unsafe water to  Water will be treated and disinfected distribution system? prior to supply. • Inadequate protection of intake  There are no major polluting sources in works or wells, leading to pollution the catchment of water supply? • Over pumping of ground water,  No Ground water pumping is required leading to salinization and ground only for Isagarh town. As per the subsidence? recommendation of ground water testing report, the pumping will be done. for rest of the towns as Surface water source is selected for the project • Excessive algal growth in storage  Regular cleaning of storage tanks will reservoir? be conducted during operation. • Increase in production of sewage  As per CPHEEO manual the rate of beyond capabilities of community water supply is 70lpcd for the town facilities? where sewerage scheme is not anticipated • Inadequate disposal of sludge from  Appropriate provision for sludge drying water treatment plants? and disposal is included in the project • Inadequate buffer zone around  No pumping and treatment plants to alleviate noise and other possible nuisances and protect facilities? • Impairments associated with  No transmission lines and access roads? • Health hazards arising from  Measures for safe handling of Chlorine inadequate design of facilities for are included. Chlorine dosing will be receiving, storing, and handling of done through chlorinator. MSIHC rules chlorine and other hazardous will be followed chemicals. • Health and safety hazards to  Measures for safe handling of Chlorine workers from the management of are included. Training will be given to chlorine used for disinfection and worker on health and safety aspects of other contaminants? application of chlorine for treatment of water. BIS code of safety concerning hazards relating to chlorine is followed • Dislocation or involuntary  There is no resettlement of people for resettlement of people project implementation.WTP, Sump and OHTs are proposed in government land ,Water supply pipes will be layed along the ROW on government land and not impacting any structure , so no issue of R&R. • Social conflicts between  The contractor will be utilizing the local construction workers from other labour forces as far as possible; in areas and community workers? case if it is unavoidable, labour camps and facilities will be provided appropriately. No conflicts envisaged. • Noise and dust from construction  Yes. During civil work noise and dust activities? will be generated but it will be localized and short-term in nature.Dust suppression measures such as water sprinkling will be employed • Increased road traffic due to  Excavation & Laying pipelines along interference of construction public road will interfere with the traffic. activities? Construction material transport will increase traffic within city and dumping construction material on road cause traffic congestion. Proper traffic & Construction planning will be ensured to minimize the interference. • Continuing soil erosion/silt runoff  The proposed pipelines are from construction operations? underground .so there is no chance of soil erosion during operation. During laying of pipes trenched will be filled and compacted to resource original ground condition. Debris generated due to excavation will be disposed off in designated disposal site.. Construction work during monsoon shall be carried out with due care so that silt run off due to construction operation is prevented. • Delivery of unsafe water due to  Appropriate O&M will be conducted. poor O&M treatment processes Only disinfected water from the WTP (especially mud accumulations in will be supplied to the OHSR and to the filters) and inadequate chlorination distribution system. Training will be due to lack of adequate monitoring given to the staffs operating the plant of chlorine residuals in distribution and to collect water sample time to systems? time and to analyze the same to ensure the quality of the supplied water • Delivery of water to distribution  Not envisaged. DI and HDPE pipes system, which is corrosive due to has been proposed as a precautionary inadequate attention to feeding of measures. corrective chemicals? • Accidental leakage of chlorine gas?  Measures for safe handling of chlorine are included. Chlorine dosing will be done with the help of chlorinators. Adequate measures will be taken to prevent the exposure of workers to chlorine gas. • Excessive abstraction of water  No such impact is anticipated.Water affecting downstream water users? abstraction will be limited to allocate quantity for Karera the subproject towns; Karera, Pichhore, Aron, Bairad, Vijaypur and Isagarh etc. • Competing uses of water?  No such competition is envisaged. Water demand has been calculated considering all types of demand. Water abstraction will be limited to allocate quantity for the subproject towns; Karera. Pichhore, Aron, Bairad, Vijaypur and Isagarh etc. • Increased sewage flow due to  As per CPHEEO manual the rate of increased water supply water supply is 70lpcd for the town where sewerage scheme is not anticipated. Sewage volume will be definitely increased with the increase in water supply at new area. • Increased volume of sullage  No. The scope of the present work (wastewater from cooking and does not involve waste water treatment washing) and sludge from plant wastewater treatment plant ▪ Large population influx during project  Minimum influx of population during the construction and operation that causes construction and operation period. increased burden on social infrastructure Construction of WTP, Sump, OHSRs and services (such as water supply and and laying of distribution and rising sanitation systems)? mains are not a big construction. Hardly 30-40 labourers will be work during construction; therefore temporary burden to social infrastructure is anticipated. ▪ Risks to community health and safety  No such materials are used in project due to the transport, storage, and use so no risk to community health & and/or disposal of materials such as safety. Fuel and chemicals will be explosives, fuel, and other chemicals stored as per storage and import of during operation and construction? hazardous chemical rules 1989 and safety norms ▪ Community safety risks due to both  Proper safety measures would be accidental and natural hazards, ensured during the construction & especially where the structural elements operation and decommissioning. or components of the project are Construction of sumps and OHSRs are accessible to members of the affected planned at open isolated vacant area community or where their failure could therefore safety risk of community does result in injury to the community not arise. In case of pipe laying for throughout project construction, distribution and rising main community operation, and decommissioning? safety will be considered as per EMP All structural design will be as per standard design for earthquake hazard zone II

Climate Change and Disaster Risk Yes No Remarks Questions The following questions are not for environmental categorization.They are included in this checklist to help identify potential climate and disaster risks.

Is the Project area subject to hazards √ Semi-arid zone, unreliable rainfall, less such as earthquakes, vegetation cover. Promote more floods,landslides,tropical cyclone winds, efficient use of water by reducing stormsurges, tsunami or volcanic losses and wastage to counter eruptions and climate changes? increased demands due to higher temperatures.

Could changes in temperature, √ Reduction in rainfall may affect the precipitation, or extreme events patterns water availability from dam. Given the over the Project life span affect technical or priority for drinking water supply, dead financial Sustainability (e.g., changes in storagewill be utilized in case of low rainfall patterns disrupt reliability of water rainfall years supply; sea level rise creates salinity intrusion into proposed water supply source)? Are there any demographic or socio- √ No economic aspects of the Project area that are already vulnerable (e.g.,high incidence of marginalized populations, rural-urban migrants, illegal Settlements, ethnic minorities, women or children)?

Could the Project potentially increase the √ No climate or disaster vulnerability of the surrounding area (e.g.by using water from a vulnerable source that is relied upon by many user groups, or encouraging settlement in earthquake zones)?

Appendix 2: National Ambient Air Quality Standards

Appendix 3: Vehicle Exhaust Emission Norms

Appendix 4: National Ambient Air Quality Standards in Respect of Noise

Appendix 5: Drinking Water Standards Substance or Requirement Undesirable Permissible Remarks S. Characteristic Desirable limit effectoutside the limit inthe No. desirable absenceof alternate Source EssentialCharacteristic 1. Colour Hazen 5 Above 5,consumer 25 Extendedto 25only if Units,Max acceptance decreases toxic Substance arenot suspect inabsence of alternatesources 2. Odour Unobjectiona - - a) testcoldandwhen ble heated b) test areseveral dilutions 3. Taste Agreeable - - Testto beconducted onlyaftersafelyhas beenestablished 4. Turbidity(NTU 5 Above 5,consumer 10 - ) Max acceptance decreases

5. pH value 6.5 to8.5 Beyond thisrangethe Norelaxation - water will after themucous membraneand/or water supplysystem 6. Total 300 Encrustationinwater 600 - Hardnes supplystructure and s (mg/L) adverseeffectson CaCO3 domesticuse 7. Iron(mg/L,Fe) 0.3 Beyond thislimit 1.0 - Max taste/appearanceare affected;has adverse effectsondomesticuses andwater supplystructure and promotesironbacteria 8. Chlorides250 250 Beyond 1000 - (mg/L,Cl) effectsoutsidethe Max desirable limit 9. Residual free 0.2 - - To be applicable only Chlorine(mg/L) whenwater is , Max chlorinated.Tested at customer end.When protection againstviral infectionisrequired, it shouldbemin.0.5 mg/L.

DesirableCharacteristics 10. Dissolvedsolid 500 Beyond 2000 - s mg/L.Max this,palatability decreasesandmaycau se gastrointestinal irritation. 11. Calcium(mg/L 75 Encrustationinwater 200 - , Ca)Max. supplystructure and adverseeffectson domesticuse. 12. Magnesium(mg/ 30 Encrustationinwater 100 - L, Mg)Max supply structure and adverseeffectson domesticuse. 13. Copper 0.05 Astringenttastedis 1.5 - (mg/L,Cu) Max colorationandcorrosion of pipes fittingsandutensils will becausedbeyondthis. 14. Manganese 0.1 Beyond thislimit 0.3 - (mg/L,Mn)Max taste/appearanceare affected,has adverse effect on domesticuseandwater supplystructure 15. Sulphate 200 Beyond thiscauses 400 Maybe extendedupto (mg/L,SO4) Max. gastro intestinal 400 provided irritation when magnesium(asMg) magnesiumor doesnotexceed 30 sodiumare present 16. Nitrate(mg/L 45 Beyond this 100 - , NO3)Max. methaemoglobinemia takes place. 17. Fluoride(mg/L,F) 1.0 Fluoridemaybekeptas 1.5 - Max. lowas possible.High fluoridemaycause fluorosis.

18. Phenolic 0.001 Beyond 0.002 - Compounds(mg/ this,itmaycause L C6H5OH)Max. objectionabletasteand odour 19. Mercury(mg/LHg 0.001 Beyond thisthewater NoRelaxation. To be testedwhen ) Max becomes toxic pollutionissuspected

20 Cadmium 0.01 Beyond thisthewater NoRelaxation. To be testedwhen (mg/L,Cd) Max becomes toxic pollutionissuspected

21. Selenium 0.01 Beyond thisthewater NoRelaxation. To be testedwhen (mg/L,Se) Max becomes toxic. pollutionissuspected

22. Arsenic 0.05 Beyond thisthewater NoRelaxation To be testedwhen (mg/L,As) Max. becomes toxic pollutionissuspected

23. Cyanide 0.05 Beyond thisthewater NoRelaxation To be testedwhen becomes toxic pollutionissuspected

24. Lead(mg/LPb) 0.05 Beyond thisthewater NoRelaxation To be testedwhen Max. becomes toxic pollutionissuspected 25. Zinc(mg/L,Zn) 5 Beyond thislimititcan 15 To be testedwhen Max. causeastringenttastea pollutionissuspected nd an opalescence inwater 26. Anionicdetergents 0.2 Beyond thislimititcan 1.0 To be testedwhen (mg/L,MBAS causealightfrothinwate pollutionissuspected ) Max r 27. Chromium 0.05 Maybe - - (mg/L,Cr6+ carcinogenicabove thislimit 28. Polynuclear - Maybe carcinogenic - - Aromatic Hydrocarbons (mg/l,PAH)Max 29. Mineral oil 0.01 Beyond thislimit, 0.03 To be testedwhen (mg/L) undesirabletaste and pollutionissuspected odourafterchlorination takesplace

30. Pesticides(mg/L) Absent Toxic 0.001 - max Radioactivematerials 31. Alphaemitters - - 0.1 - Bq/LMax 32. Betaemitters - - 1.0 - Pci/LMax 33. Alkalinity(mg/L, 200 Beyond thislimit,taste 600 - ) Max becomes unpleasant

34. Aluminum(mg/L 0.03 Cumulative effectis 0.2 , Al) Max reported tocausedementia 35. Boron(mg/L) Max 1.0 - 5.0 -

Appendix 6: Salient Features of Major Labour Laws Applicable to EstablishmentsEngaged in Construction of Civil Works

Appendix 7: EXTRACT FROM CONSTRUCTION & DEMOLITION MANAGEMENT RULES, 2016

Appendix 8: Sample Outline Spoils (construction waste) Management Plan

Appendix 9: Sample Outline Traffic Management Plan

Figure A2 & A3: Work on shoulder or parking lane & Shoulder or parking lane closed on divided road

Figure A4 & A5: Work in Travel lane & Lane closure on road with low volume

Figure A6: Street closure with detour

Appendix 10: Summary of Stakeholder Consultation, Consultation Photographs & List of Participants- – Karera Town

1. Stakeholder Consultation – Karera Town

Date Locati No. of Participants Topic Discussed Issues/ concerned on Participa Raised nts 16th at ULB Total = 34 CMO, • Water Supply Project • The area has Sep2 office, M=29, Chairman- Background, insufficient and ULB, Elected Environmental, Social, inadequate drinking 015 Karera F=05 Representativ GRM, traffic safety water resource. Water es, ULB Staff, issue and benefit from supply to the area is Sub the project were done through tube Engineer, explained to the wells and untreated Assistant Stakeholders. water supply to the Revenue • Location of community people. Inspector components of • People informed about (ARI), Local proposed water very less water supply Leader and Supply scheme has in town in comparison Local People been finalized with to standard. identification of • All the existing water government land. structure nearby town • Condition of all the has been identified and existing component of Samoha dam has been the water supply has selected for source of been reviewed for water supply in Karera. their further uses in • Funding and Tender proposed water supply Process of this Project. scheme. • Cost of this project; • Need for and project cost improvements to participation of Central present system; Govt. and State Govt. • Land use and area to in to the project. be covered under the • Implementing agency; project and better /improved • Relevant information service. of the upcoming • Operation and project and benefits of maintenance of the the project. facilities developed • Potential positive and under the project and negative impacts due community to project participation; implementation Ensuring no income • Probability of keeping loss the poor and the • Informed to the vulnerable out of the residents about the user charge. proposed 24 X 7 piped • People requested for water supply scheme selection of good including WTP and contractor to speed up water connections to the construction work. individual HHs in all the wards of town ensuring quality and reliability of services. 10th At Total = 10 Sub Divisional • About proposed water • Possibility of proposed May Office M=10, Officer (SDO), supply subproject for component (Intake well, SDM, Chief town Karera - RWRM, WTP & OHTs) 2018 of F=00 Conservator of Background, its being located in Chief Forest and components, reserved bird sanctuary Conser Director, locations, provisions, area. Madhav NP, timeline, est. cost, • The proposed vator of Shivpuri, (i.e. probable component is located Forest Karera Bird implementation out of bird sanctuary & Sanctuary’s procedures and also boundary but is in eco management & their roles in the Directo sensitive zone of control is under project. Karera bird sanctuary. r, Field Director of • Discussion about • NOC from WRD for Madha Madhav Karera Wildlife abstraction of water and v National Park in Sanctuary popularly construction of Intake Shivpuri known as “Son has been obtained. Nation district), Chiraiya Bird • Construction Safety al Park, sanctuary”, Reserve measures shall be CDO, PIU – forest boundary and taken to ensure they Shivpur Gwalior its Eco Sensitive i are protected and Civil Engineer, zone. conserved.

PIU, Gwalior • Proposed components • Barricade the under WSS and its construction area Senior impact on Karera properly so that no wild Draftsman, wildlife sanctuary animals entre the work Madhav • Proposed Mitigation area National Park, Measures • No construction Shivpuri • What are the material guidelines of Wildlife storage/ancillary works Sanctuary for water shall be conducted in supply project like the forest area; this laying of pipelines and shall be limited to actual other structures like construction area and OHT proposed under the access roads subproject? • Limit the work to • Environmental, Social, daylight hours only; no traffic safety issue and work after sunset benefit from the • No high noisy works project were explained shall be conducted • The work Shall be • No labour camps shall done with mitigation be located near forests measures, as per (maintain minimum 1km applicable laws, rules buffer) and regulation and • No workers /personnel available shall enter forest areas; guidelinesand all the it is the DBOC rules lay down central responsibility to take and state government necessary precautions in respect of & prevent workers construction in removing/damaging protected areas will be trees/vegetation, followed hunting animals • Most of the • Create awareness subprojects among workers on components like environment & safety Intake, WTP and OHT • Conduct awareness for Karera town is among workers on located within environment & safety ecosensitive zone • Public notice to be boundary not in circulated, construction sanctuary. should be completed in • Precaution must be the given time, taken care to minimize • All the rules laid down the noise during by central and state construction work to government in respect avoid any negative of construction near impact on bird sanctuary should be sanctuary. followed. • The impact will be only • Adequate provision for for limited time during minimizing the Dust and construction work Noise Pollution during construction • Overall they Forest official told that they have no objection as this project is to meet the daily residential needs of the local residents by providing with a constant supply of better quality water as the subproject will improve the overall environmental quality of the town and surrounding areas. Stakeholder Consultation Photographs & List of Participants – Karera Town

Photographs of Stakeholder Consultation with CMO, ULB Chairman and ULB Staff at ULB office and discussion with peopleduring transect walk

Attendance of Stakeholder Consultation with CMO, ULB Chairman and ULB Staff at ULB Office - Karera Town

Appendix 11: Stakeholder Consultation Photographs & List of Participants – Madhva Natinal Park for Karera Wild Life Sanctuary for Karera Town on 10.05.2018

Interaction with Mr. V.S. (SDO) Interaction with Mr. Vijay Kumar Yadav (SDM)

Photographs of Stakeholder consultation with Sub Divisional Officer (SDO) & Chief Conservator of Forest (CCF) at Office of Chief Conservator of Forest & Director,Madhav National Park, Shivpuri

List of Participants

Name Designation

Mr.V.S.Yadav SDO, Madhav National Park, Shivpuri

Mr.Umesh Kumar Singh CDO, PIU – Gwalior

Mr. Anshul Chaturvedi Civil Engineer, PIU, Gwalior Mr. Vijay Kumar Sharma Senior Draftsman, Madhav National Park, Shivpuri

Appendix 12: Summary of Stakeholder Consultation, Photograph of Consultation and List of Participants – Pichhore Town Date Locati No. of Participants Topic Discussed Issues/ concerned Raised on Participa nts 28th at ULB Total = ULB • Water Supply Project • The area has insufficient Dec office, 20 Chairman, Background, and inadequate drinking Local Environmental, Social, water resource. 2015 Pichhor M=20, representative GRM, traffic safety • People complained about e F=00 s, ULB staffs issue and benefit from the very poor water and local the project were supply in the town in people explained to the terms of quantity of water Stakeholders. as well as connectivity of • Existing scenario of water supply network in water supply & town. Proposed water • Condition of all the supply project existing component of the • Need for water supply has been improvements to reviewed for their further present system; uses in proposed water • All the location of supply scheme. After components of discussion and analysis it proposed water was found the 2 number Supply scheme has of existing GSR can be been finalized with used in proposed water identification of supply scheme. government land. • People requested for • All the existing water selection of good structure nearby town contractor to speed up has been identified the construction work. and Futiwar Dam has • Funding and Tender been selected for Process of this Project. source of water supply • Cost of this project; and in Pichhore Town. project cost participation • Relevant information of Central Govt. and of the upcoming State Govt. in to the project and benefits of project. the project. • Implementing agency; and • positive and negative better/improved service. impacts due to project • Operation and implementation maintenance of the Ensuring no income facilities developed under loss the project and community participation;

Stakeholder Consultation Photographs & List of Participants – Pichore Town

Photographs of Stakeholder Consultation with ULB Chairman and ULB officials at ULB office Pichhore

List of Participants of Stakeholder Consultation with ULB Chairman and ULBofficials at ULB office Pichhore

Appendix 13: Summary of Stakeholder Consultation, Photograph of Consultation and List of Participants – Aron Town

Date Locati No. of Participants Topic Discussed Issues/ concerned on Participants Raised 23th at ULB Total = 14 CMO, • Water Supply Project • People informed about Sep office, M=12, F=02 Chairman Background, very less water supply ULB, Elected Environmental, Social, in town as compared to 2015 Aron Representati GRM, traffic safety standard. ves and ULB issue and benefits • Condition of all the Staff from the project were existing component of explained to the the water supply has Stakeholders. been reviewed for their • Existing scenario of further uses in water supply & proposed water supply Proposed water scheme. supply project • People requested for • Need for selection of good improvements to contractor to speed up present system; the construction work. • All the existing water structure nearby town • Cost of this project; and has been identified project cost and Sindh River has participation of Central been selected for Govt. and State Govt. in source of water supply to the project. in Aron. • Implementing agency; • Location of all the and better /improved components of service. proposed water • Operation and Supply scheme has maintenance of the been finalized with facilities developed identification of under the project and government land. community • Relevant information participation; of the upcoming • Probability of keeping project and benefits of the poor and the the project. vulnerable out of the • Potential positive and user charge. negative impacts due to project implementation Ensuring no income loss • Informed to the residents about the proposed water supply scheme including WTP and water connections to individual HHs in all the wards of town ensuring quality and reliability of services. 23th Ward Total= 20, SC-ST • Status of existing • Majority were very Sep No. 10, M= 12, F= community drinking water supply excited about the People, ULB system of ; scheme as either they 2015 (SC-ST 08 officials • Need for are fetching water from Commu improvements to far, or the quality is not nity) present system; good, children also • The Water Supply suffer as they also are Scheme, SHG (Self required to help. Help Group) • But at the same time Environmental, Social, they wanted the rates GRM, traffic safety not to be exuberantly issue and benefit from high. the project were • They aspired that the explained to the scheme should bring Stakeholders. them water ASAP. • Briefing on project • In one ward residents objectives probable told that quality of tube implementation well water is not good. procedures. • Whereas in some other ward females told that they and their children don’t like taste of river water as they are used to drink tube well water.

Stakeholder Consultation Photographs & List of Participants – Aron Town

Photographs of Consultation with CMO and ULB Chairman at ULB office Aron Nagar Parishad

Attendance of Stakeholder Consultation with ULB Chairman and ULB officials at ULB office Aron Town

Photographs of Stakeholder Consultation with SC-ST community, at Ward No. 13, Aron

Attendance of Stakeholder Consultation with SC-ST community, at Ward No. 13, Aron

Appendix 14: Summary of Stakeholder Consultation, Photograph of Consultation and List of Participants – Vijaypur Town Date Locatio No. of Participant Topic Discussed Issues/ concerned Raised n Participant s s 8th At ULB Total = 17 CMO, • Presentation on detailed • Consultants explained June office, M=08, F=09 Chairperso project report of Detailed Project Report n –ULB, proposed water supply prepared for water supply 2016 Vijaypur Vice for Vijaypur under scheme to ULB officials & Chairman- MPUSIP. Elected Ward Members. ULB, • Water Supply Project • Discussed about scheme Elected Background, proposed from Kunwari Ward Environmental, Social, River as a source by members GRM, EHSs, traffic using under construction safety issue and benefit anicut by WRD and from the project were proposed intake well. explained to the • Officials asked about Stakeholders. location of proposed WTP • Land use and area to be and OHT locations in the covered under the town and explained and project. shown the same. • Consultants explained • Ward members enquired about positive impacts about material of pipes of the scheme like 24x7 used in the scheme and water supply, area they were informed that covered in ULB, Ductile Iron pipes are adequate pressure at used for rising / pumping user end etc. mains and HDPE pipes • Relevant information of for distribution system. the upcoming project and benefits of the • Elected Ward members project. enquired about land status available for • Potential positive and proposed facilities and negative impacts due to CMO explained the same project implementation and shown the proposal Ensuring no income loss sent to revenue • Informed to the all department for allocation members about the of land. proposed water supply • The chair person asked scheme including WTP about the estimated and water connections project cost for the to individual HHs in all scheme and they were the wards of town informed about the ensuring quality and funding pattern by reliability of services. consultant. • Consultants also explained about estimated O&M expenditure to run the scheme. • ULB officials and ward members enquired about tariff proposed for households and commercial connections and consultants furnish the same. • Elected members enquired about restoration of roads after laying of pipeline and alignment of pipelines. • ULB officials asked about probable commencement of the scheme and they were informed that by the end of 2017 execution of project will finished and 2018 is the commissioning year.

20th At Total =07 Chairperso • Finalization of source • Consultants and ULB Jan propose M=07, F=00 n –ULB, and land availability officials discussed and details for preparation of confirmed about existing 2016 d Chief Detailed Project Report water supply facilities and Compon Municipal of Water Supply infrastructure available ent Officer Scheme for Vijaypur with ULB and discussed under MPUSIP. about problems facing Location (CMO), Sub • Existing scenario of and shortage in water Engineer- water supply & supply. ULB, proposed water supply • Consultants shown the Water project. base map of Vijaypur town prepared with help Works • Present drinking water of topographical survey Inspector- supply source and its and CMO & Elected ULB, Water condition Members have identified • Discussed about old some mismatches about Supply system and reasons for land marks. Consultants Expert and failure and concluded noted down all points and Civil that due to lack of assured to rectify the same. Engineer maintenance the old system was abandoned. • Consultants collected the Darashaw & • Need of improvement of ward boundary map to Co. Pvt. Ltd. the present situation make the ward boundaries on base map. • Consultants are explained the concept plan of Vijaypur water supply scheme to CMO, Chairman, Technical Officers and Elected Members. • Discussed about source considered during concept plant preparation i.e Kunwari River and explained the entire scheme of proposed water supply scheme including preliminary estimated project cost. And also explored probable other sources if any. • ULB officials agreed for Kunwari River as a source of water supply at the proposed stop dam site which is recently construted by WRD, and CMO requested to send a letter to WRD regarding water allotment. • NOC from WRD already obtained • Kunwari River source visited along with Chairman, CMO & technical officers and finalized the route for Laying of rising main from source to WTP and ULB. • Identified a location for construction of Intake well and also finalized land parcel for proposed water treatment plant.

• Site visit done along with Chairman, CMO & technical officers to identify the land available for proposed works like construction of WTP, sump, OHT and Pump Rooms etc and finalized and visited Tehsil office regarding land parcels available for proposed works.

18th At ULB Total= 06, Chairperso • Preparation of Detailed • Chairman welcomed the Sep office M= 06, F= n -ULB, Project Report of Water initiative taken by the Supply Scheme for MPUSIP for the 2015 00 Chief Vijaypur under MPUSIP. preparation of DPR for Municipal • Status of existing Water Supply of different Officer drinking water supply towns of Madhya system of; Pradesh. (CMO), • Need for improvements • Chairman and CMO Water Works to present system; raised the problems in the Inspector, • Briefing on project Vijaypur related to Assistant objectives probable Drinking Water Supply. implementation • The socio economic Engineer, procedures. profile of the Vijaypur was UADD, Civil • The need for the project explained by the Engineer was discussed with the Chairman. Chairman of the Nagar • There is an immediate (Survey & Parishad. need of improving the Mapping) present water works and infrastructure in the town. Graduate Chairman explained the problematic areas (Low Trainee, Pressure Zones, Darashaw & Electricity Supply Co. Pvt. Ltd. Duration) related to the water supply.

• Consultant noted down the problematic areas & present situation of the town and discussion was held on the need. • Consultants carried out the site visit to the source of water like Kunwari River, existing Overhead Service Reservoirs (OHSRs) & tube wells along with the representative of Vijaypur Nagar Parishad. 15th Office of Total=07 DFO, • Briefing about proposed • Possibility of proposed M = 07,F = Kuno May, the water supply subproject component (Intake well & Wildlife 0 for town Vijay - RWRM) being located in 2018 Divisional Sanctuary, Background, its Kuno wildlife sanctuary Sheopur Forest components, locations, reserved area. officer, CDO, PIU provisions, timeline, est. • The proposed component Gwalior cost, probable for Vijaypur town are Kuno – implementation located out of Wildlife Civil procedures and also KunoWildlife sanctuary Engineer, Sanctuar their roles in the project. boundary as well as eco PIU, y, Gwalior • Proposed components sensitive zone boundary. under WSS and its So no environment Sheopur Field impact on Kuno wildlife Impacts envisaged. Engineer, sanctuary • Vijaypur Town is located PMC (PIU) • Proposed Mitigation approx. 24km away from Gwalior Measures the boundary of

Draftsman, • Discussion about, Kuno ecosensitive zone of Kuno Kuno Wildlife Sanctuary, wildlife sanctuary Wildlife Reserve forest • NOC from WRD for Sanctuary, boundary and its Eco abstraction of water and Sheopur Sensitive zone. construction of Intake has

• Confirmation of Kuno been obtained. Computer Operator, Wildlife Sanctuary, • Create awareness among Kuno Reserve forest workers on environment & Wildlife boundary safety Sanctuary, • What are the guidelines • Public notice to be Sheopur of Wildlife Sanctuary for circulated, construction water supply project like should be completed in Draftsman, laying of pipelines and the given time, Kuno Wildlife other structures like • Adequate provision for Sanctuary, OHT proposed under minimizing the Dust and Sheopur subproject? Noise Pollution during • Environmental, Social, construction traffic safety issue and benefit from the project were explained • The work Shall be done with mitigation measures, as per applicable laws, rules and regulation and available guidelines and all the rules lay down central and state government in respect of construction in protected areas will be followed • None of the subproject components are located in ecosensitive zone or in sanctuary area

Stakeholder Consultation Photographs & List of Participants – Vijaypur Town

Photograph of Stakeholder Consultation with ULB Chairman and CMO at ULB office, Vijaypur (08 June 2016)

Discussion at OHT in Ward No.15 (20 January Site Visit for Proposed OHT land at Ward No.12 2016) (20 January 2016) List of Participants – Vijaypur Town

Appendix 15: Summary of Stakeholder Consultation, Photograph of Consultation and List of Participants – Bairad Town

Date Locati No. of Participants Topic Discussed Issues/ concerned on Participant Raised s 18th at ULB Total = 12 Chairman • Consultant • Chairman welcomed the Sep office, M=10, ULB, Chief representatives visited initiative taken by the Municipal Bairad Nagar Parishad MPUSIP for the 2015 Bairad F=02 Officer along with UADD preparation of DPR for (CMO), Bairad officials for Stakeholders Water Supply of Bairad Nagar Meeting for preparation town. Parishad, Sub of Detailed Project • Chairman and CMO Engineer- Report of Water Supply discussed the problems ULB, Scheme for Bairad under in the Bairad related to Assistant MPUSIP. Drinking Water Supply. Engineer- • Water Supply Project • The socio economic UADD, ULB Background, profile of the Bairad was Representativ Environmental, Social, explained by the es, Reporter, and benefit from the Chairman. (Dainik project were explained to • There is an immediate Bhaskar, the Stakeholders. need of improving the Bairad), Civil • The present condition of present water works Engineer Water Supply including infrastructure in the (Survey & Source, Distribution town. Chairman Mapping), System, Zones where explained the Darashaw& water is supplied, Supply problematic areas (Low Co. Pvt. Ltd. Hours & Frequency, Pressure Zones, Water Tax, Staff for Electricity Supply Water Works, etc. was Duration) related to the collected. water supply. • The need for the project • Consultant noted down was discussed with the the problematic areas & Chairman of the Nagar present situation of the Parishad. town and discussion • Land use and area to be was held on the need. covered under the • Consultants carried out project the site visit to the • Relevant information of source of water like the upcoming project Pachipura Dam, Bairad and benefits of the Talaab, existing project. Overhead Service • Potential positive and Reservoirs (OHSRs) & negative impacts due to tube wells along with the project implementation representative of Bairad Ensuring no income loss Nagar Parishad. • Informed to the residents • All the data related to about the proposed the town like CDPs, water supply scheme Ward wise population, including WTP and water Ward Map and connections to individual information about HHs in all the wards of existing Water Supply town ensuring quality Scheme was collected. and reliability of services. 6th At Total =16 Chairman • Finalization of source • ULB officials informed June Differe M=13, ULB, Chief and land availability that Bairad Talab will Municipal details for preparation of become dry during 2016 nt WSS F=03 Officer Detailed Project Report summer and informed Compo (CMO), Bairad of Water Supply Scheme not to consider as nents Nagar for Bairad under source and finalized Parishad, Sub MPUSIP Pachhipura Dam as a Engineer- • Consultants explained source of water supply. ULB, the concept plan of • Discussed about Assistant water supply scheme to problems facing and Engineer- CMO, Chairman and shortage in water UADD, ULB Ward members. supply. Representativ • Discussed about • Commencement date of es, Reporter, sources considered project work and (Dainik during concept plan duration. Bhaskar, preparation like • Water logging during Bairad), Civil Pachhipura Dam and heavy monsoon. Engineer & Bairad Talab and • Chances of damaging Water Supply explained approximate the existing water Expert- project cost for each pipelines during project Darashaw& option. implementation. Co. Pvt. Ltd. • Storage Details of • Lack of public Pachhipura Dam awareness in proper use of underground drainage • Discussed and system. confirmed about existing • Scarcity of drinking water supply facilities water in the area. and infrastructure • Public sensitization on available with ULB. OHT proper use of in ward no. 5 was underground sewerage abandoned hence not system considered the same • and OHT in ward no.9 is also not considered due to age and low staging height and discussed the same. • Consultants shown the base map of Bairad town prepared with help of topographical survey and CMO has given some comments regarding colony names, land moarks and leftout areas. Consultants noted down all points and assured to rectify the same. • Pachhipura Dam source visited along with CMO & Other Officials and finalized the route for laying of rising main from source to WTP. • Identified a location for construction of Intake well • Site visit done along with CMO & Other Officials to identify the land parcels available for proposed works like construction of WTP, OHT and Pump Rooms etc and Identified land parcels for the same. • Land for proposed WTP is identified nearby Pachhipura Village. 15th Office Total=07 DFO, Kuno • Briefing about proposed • Possibility of proposed M = 07,F = Wildlife May, of the water supply subproject component (Intake well Sanctuary, 0 for town Bairad - & RWRM) being located 2018 Divisio Sheopur Background, its in Kuno wildlife

nal components, locations, sanctuary reserved CDO, PIU – Forest Gwalior provisions, timeline, est. area. cost, probable • The proposed officer, Civil implementation component for Kuno Engineer, procedures and also Bairadtown are located PIU, Gwalior Wildlife their roles in the project. out of KunoWildlife

Sanctu Field • Proposed components sanctuary boundary as Engineer, under WSS and its well as eco sensitive ary, PMC (PIU) impact on Kuno wildlife zone. So no Sheop Gwalior sanctuary environment Impacts

ur • Proposed Mitigation envisaged. Draftsman, Measures • Bairad Town is located Kuno Wildlife Sanctuary, • Discussion about, Kuno approx. 10km away from Sheopur Wildlife Sanctuary, the boundary of Reserve forest boundary ecosensitive zone of Computer and its Eco Sensitive Kuno wildlife sanctuary Operator, zone. • NOC from WRD for Kuno Wildlife Sanctuary, • Confirmation of Kuno abstraction of water and Sheopur Wildlife Sanctuary, construction of Intake Reserve forest boundary has been obtained. Draftsman, • What are the guidelines • Create awareness Kuno Wildlife of Wildlife Sanctuary for among workers on Sanctuary, water supply project like environment & safety Sheopur laying of pipelines and • Public notice to be other structures like OHT circulated, construction proposed under should be completed in subproject? the given time, • Environmental, Social, • Adequate provision for traffic safety issue and minimizing the Dust and benefit from the project Noise Pollution during were explained construction • The work Shall be done with mitigation measures, as per applicable laws, rules and regulation and available guidelines and all the rules lay down central and state government in respect of construction in protected areas will be followed • None of the subproject components are located in ecosensitive zone or in sanctuaryarea

Stakeholder Consultation Photographs & List of Participants – Bairad Town

Photograph of Stakeholders Consultation with CMO, ULB achairman, ULB Officials & Ward Members at ULB office Bairad

Photographs of Stakeholder Consultation during Transect Walk at different WSS Component of Bairad town

Photographs of Stakeholder Consultation during Transect Walk at different WSS Component of Bairad town

List of Participants of Consultation with CMO, ULB chairman and ULB staff – Bairad Town

Appendix 16: Consultation with officials of Divisional Forest Officer, Kuno Wildlife Sanctuary, Sheopur (Madhya Pradesh) Dated: 15.05.2018 For Bairad and Vijaypur Town WSS Projects

Consultation with Divisional Forest officer, Consultation with officials of Divisional Forest Kuno Wildlife Sanctuary, Sheopur officer, Kuno Wildlife Sanctuary, Sheopur

Consultation with officials of Divisional Forest Administrative Building of , Kuno Wildlife officer, Kuno Wildlife Sanctuary, Sheopur Sanctuary, Sheopur

List of Participants of Consultation With Official of Kuno Wildlife Sanctuary, Shepur, M.P.

Appendix 17: Summary of Stakeholder Consultation, Photograph of Consultation and List of Participants – Isagarh Town

Date Locati No. of Participants Topic Discussed Issues/ concerned on Participa Raised nts Sep at ULB Total= CMO, • Water Supply Project • Consultants and ULB 2016 office, 06, Chairman Background, officials discussed and ULB, Elected Environmental, Social, confirmed about isagarh M=06, Representativ GRM, EHSs, traffic existing water supply F=00 es, Sub safety issue and facilities and Engineer, benefit from the infrastructure available project were explained with ULB and discussed to the Stakeholders. about problems facing • Finalization of source and shortage in water and land availability supply. details for preparation • CMO & Elected of Detailed Project Members have Report of Water identified some Supply Scheme for mismatches about land isagarh under marks. Consultants MPUSIP. noted down all points • Existing scenario of and assured to rectify water supply & the same. proposed water supply • Consultants collected project. the ward boundary map • Present drinking water to make the ward supply source and its boundaries on base condition map. • Discussed about old • Consultants are system and reasons explained the concept for failure and plan of Isagarh water concluded that due to supply scheme to CMO, lack of maintenance Chairman, Technical the old system was Officers and Elected abandoned. Members. • Need of improvement of the present situation

Stakeholder Consultation Photographs & List of Participants – Isagarh Town

Photographs of Stakeholder Consultations at ULB office, Isagarh Town

Attendance of Stakeholder Consultation with ULB Chairman and Elected Representatives at ULB office Isagarh

Appendix 18: Surface Water Quality Analysis Report of Subproject Towns under Package- 4D 1. Water Quality Analysis Report of Samoha Dam Near Proposed Intake Site for Karera Town

2. Water Quality Analysis Report of Futiwar Dam for Pichhore Town

3. Water Quality Analysis Report of Sindh River- Aron Town

4. Water Quality Analysis Report of Pchipura Dam for Bairad Town WSS

5. Water Quality Analysis Report of Kunwari River for Vijaypur Town WSS

Appendix 19: Yeild Test Report and Exisiting Tube Well Details for Isagarh Town

Details of Existing Tube Well & Pumping As per summer minimum discharge Machine Date 29.11.2015 consideration

Minimum

Installed

Punpin prospective Total Dia of g Discharge Discharge Intermediate year year Ultimate year

Ward Depth 1000Ltr/Hr. As pumping hours Pumping Sl. No no in Tube Water 1000Ltr/Hr. per pumping hours = pumping hours =

machain given by feet wall Lavel ULB Flow test/ =1000Ltr/14Hr 1000Ltr/16Hr 1000Ltr/20Hr

of life

investigation

A b c d e f g h i J k

1 1 350 6 270 12 1980 6 84.0 96.0 120

2 1 256 4 180 12 2003 6 84.0 96.0 120

3 2 305 6 205 12 2001 6 84.0 96.0 120

4 2 298 6 192 12 1985 6 84.0 96.0 120

5 2 271 6 206 12 1990 6 84.0 96.0 120

6 2 290 6 155 12 2008 6 84.0 96.0 120

7 2 288 6 190 12 2009 6 84.0 96.0 120

8 2 312 6 180 12 2010 6 84.0 96.0 120

9 307 8 146 12 1998 6 84.0 96.0 120 5

10 7 249 8 208 12 2001 6 84.0 96.0 120

11 11 258 6 210 12 1986 6 84.0 96.0 120

12 13 291 4 184 12 1986 6 84.0 96.0 120

13 13 285 4 225 12 1988 6 84.0 96.0 120

14 13 264 4 115 12 1990 6 84.0 96.0 120

15 13 230 6 101 12 2000 6 84.0 96.0 120

16 15 198 6 90 12 2007 6 84.0 96.0 120

Note: Reviewing Existing Tube well data it is advisable to of go for new tube

Total 1344.0 1536.0 1920.0 wells replacing of Machinery older existing older than 1990.

Appendix 20: Salient Features of Dams/ Resrvores for Subproject Towns Under Package-4D

1. Salient Features of Samoha Dam for Karera Town WSS

Name of the Structure Samoha Weir

Nearest city Karera

District Shivpuri

State Madhya Pradesh

Name of River Mahuar

Basin Ganga

Purpose Irrigation Design flood (Cumec) 7425 Spillway capacity (Cumec) 7425 Heightupto crest(m) 17 Type o fspillway gate Falling Shutter Spillway gates- Number 27 Spillway gates-Size(m) 12X5 ThicknessofPier(m) 2.5 CrestLevel (m) 246.5 Pond level(m) ----- Storage capacity upto crest (MCM) 19.552 Storage Capacityat Pond level (MCM) 18.533 Status of BWA Construction Completed

2. Salient Features of Futiwar Dam for Pichhore Town WSS

Attribute Value Attribute Value Name of the Dam Futiwar Dam Dam Status Completed River Local Purpose Irrigation Nearest City Pichhore Commencement Year - District Shivpuri Completion Year 1979 State Madhya Pradesh Operating and Maintenance WRD,Govt. Agency of MP Basin Name Gang Max Height above Foundation(m) 13.51 Seismic Zone Seismic Zone-II Total Volume content of Dam - (TCM) Dam Type Earthen Type of Spillway Gates - Length of Dam (m) 129.57 Number of Spillway Gates - Type of Spillway - Size of Spillway Gates (m X m) - Length of Spillway (m) - Mode of Operation - Crest Level of Spillway - Size of Sluice(M X M) - Spillway Capacity (cumec) 58.34 Status - Design Flood (cumec) 58.34 Basin Ganga No. of River Sluice - Live Storage Capacity(MCM) 4.95 Sluice Purpose - Dead Storage Capacity(MCM) 0.3 Name of Reservoir Futiwar Submergence Area (Th.Ha.) 0.14944 Reservoir State Madhya Pradesh Catchment Area(Sq.Km.) 6.37 River Local Water Allocation - - Industrial(MCM) Maximum Water Level (m) - Water Allocation - Ecology(MCM) - Full Reservoir Level (m) - Water Allocation - Thermal(MCM) - Minimum Draw Down Level(m) - Towns and Villages Affected - Gross Storage Capacity(MCM) 5.25 Number of Families Affected - - Total Water Allocation - Irrigation(MCM) - Number of Families Affected - SC - Water Allocation - Hydroelectric - Number of Families Affected - ST - (MCM) Water Allocation - Drinking(MCM) - Recreation activities at Reservoir - Land Affected - Total (Th.Ha.) - Land Affected - Others (Th.Ha.) - Land Affected - Cultural (Th.Ha.) - Reservoir Sedimentation Survey - Done Land Affected - Forest (Th.Ha.) - Agreement on Sharing of Water -

3. Salient Features of Pachipura Dam for Bairad Town WSS

S. No Hydraulic Particulars Value 1 Tank Bund Level (TBL) 411.01 m 2 Maximum Water Level (MWL) 409.01 m 3 Full Tank Level (FTL) 407.75 m 4 Lowest Supply Level (LSL) 403.01 m 5 Catchment Area 89.75 Sqkm 6 Maximum Discharge 566.31 Cum/sec 7 Full Capacity of Reservoir 10.47 Million Cum 8 Live storage capacity 8.32 Million Cum 9 Dead storage 2.15 Million Cum

4. Salient Features of Stop Dam / Weir Constructed by WRD for Vijaypur Town WSS

Live Catchment Height Storage Area Width (m) (m) Capacity (Sq. Km) River Ponding (MCM) Over Length Structure/ Stop River (m) Dam Location Top Bottom

Kunwari 0.93 745 Vijaypur 155 1.5 7.4 4 River

Appendix 21: Hydraulic Design Details & Drawing of Weir for Aron Town WS

Details of Proposed Weir Across Sindh River – Aron Town WSS Length (m) Average Width Average Depth (m) Storage Capacity Unit (m) (m3)

A - D 1450 60 6.27 545490

D - E 2170 40 5 434000

B - C 2070 26 3.2 172224

D - F 1250 25 3.5 109375

Total Storage Capacity for 6940 m Length 1261089 m3

Total Storage Capacity for 6940 m Length 1.26 MCM

Water Demand for 2048 / Day 4.1 MLD

Water Demand for 2048 / Annum 1.50 MCM

Storage Capacity Required for 5 Month of Water Demand 0.75 MCM

Evaporation & Percolation Losses + Water Theft @ 40% 0.30 MCM

Total Storage Capacity Required for 5 Month of Water Demand & Losses + 1.05 MCM Theft

Height of Proposed Weir 5 m

Length of Proposed Weir 50 m

Catchment Area for Weir 100.22 Sq. Km.

Length of Water Spread Area 6940 m

Total Length of River 470 Km

Total Length of River in Madhya Pradesh 461 Km

Source Malwa Plateau

Mouth Yamuna River

Cordinates 260’’N 170’’ E

Appendix 22: Rainfall Data of Aron Town

Rainfall Dependibility for Aron Town

Appendix 23: Kunwari River Discharge Data for Vijaypur Town

Appendix 24: NOC From WRD for Water Abstraction for Subproject Towns under Package-4D 1. NoC From WRD for Water Abstraction for Karera Town

2. NoC from WRD for Water Abstraction for Aron Town

3. NOC from WRD for Water Abstraction for Bairad Town

4. NOC from WRD for Water Abstraction for Pichhore Town

5. NOC from WRD for Water Abstraction for Vijaypur Town

Appendix 25: Final Notification Declaring Eco sensitive Zone around Karera Wildlife Sanctuary by MOEFCC, New Delhi on Dated 15.09.2017

Appendix 26: Minutes of 18th Meeting of the Standing Committee of NBWL Held on 12th April 2010 For Denotification & Rationalization of Boundaries of Karera Wildlife Sanctuary

Appendix 27: Draft Notification Declaring Eco sensitive Zone around Kuno-Palpur Wildlife Sanctuary by MOEFCC, New Delhi on Dated 09.11.2017

Appendix 28: Sample Grievance Registration Form

Appendix 29: Sample Environmental Site Inspection Report Project Name Contract Number

NAME: ______DATE: ______TITLE: ______DMA: ______LOCATION: ______GROUP: ______

WEATHER: Project Survey Activity Stage Design Implementation Pre-Commissioning Guarantee Period

Monitoring Items Compliance Compliance marked as Yes / No / Not applicable (NA) / Partially Implemented (PI) EHS supervisor appointed by contractor and available on site Archaeological Supervisor appointed by contractor and available on site Construction site management plan (spoils, safety, schedule, equipment etc.,) prepared Traffic management plan prepared Dust is under control Excavated soil properly placed within minimum space Construction area is confined; no traffic/pedestrian entry observed Surplus soil/debris/waste is disposed without delay Construction material (sand/gravel/aggregate) brought to site as & when required only Tarpaulins used to cover sand & other loose material when transported by vehicles After unloading , wheels & undercarriage of vehicles cleaned prior to leaving the site No AC pipes disturbed/removed during excavation No chance finds encountered during excavation Work is planned in consultation with traffic police Work is not being conducted during heavy traffic Work at a stretch is completed within a day (excavation, pipe laying & backfilling) Pipe trenches are not kept open unduly Road is not completely closed; work is conducted on edge; at least one line is kept open Road is closed; alternative route provided & public informed, information board provided Pedestrian access to houses is not blocked due to pipe laying Spaces left in between trenches for access Wooden planks/metal sheets provided across trench for pedestrian No public/unauthorized entry observed in work site Children safety measures (barricades, security) in place at works in residential areas Prior public information provided about the work, schedule and disturbances Caution/warning board provided on site Guards with red flag provided during work at busy roads Workers using appropriate PPE (boots, gloves, helmets, ear muffs etc) Workers conducting or near heavy noise work is provided with ear muffs Contractor is following standard & safe construction practices Deep excavation is conducted with land slip/protection measures First aid facilities are available on site and workers informed Drinking water provided at the site Toilet facility provided at the site Separate toilet facility is provided for women workers Workers camps are maintained cleanly Adequate toilet & bath facilities provided Contractor employed local workers as far as possible Workers camp set up with the permission of PIU Adequate housing provided Sufficient water provided for drinking/washing/bath No noisy work is conducted in the nights Local people informed of noisy work No blasting activity conducted Pneumatic drills or other equipment creating vibration is not used near old/risky buildings

Signature ______

Sign off

______Name Name Position Position

Appendix 30: Quarterly Reporting Format for Assistant Safeguards Officer

1. Introduction • Overall project description and objectives • Description of sub-projects • Environmental category of the sub-projects • Details of site personnel and/or consultants responsible for environmental monitoring • Overall project and sub-project progress and status

Status of Sub-Project Sub-Project List of Progress of No. Design Pre- Construction Operational Name Works Works Construction Phase            

2. Compliance status with National/ State/ Local statutory environmental requirements No. Sub-Project Name Statutory Environmental Status of Compliance Action Required Requirements

3. Compliance status with environmental loan covenants No. (List schedule and Covenant Status of Compliance Action Required paragraph number of Loan Agreement)

4. Compliance status with the environmental management and monitoring plan • Provide the monitoring results as per the parameters outlined in the EMP. Append supporting documents where applicable, including Environmental Site Inspection Reports. • There should be reporting on the following items which can be incorporated in the checklist of routine Environmental Site Inspection Report followed with a summary in the semi-annual report send to ADB. Visual assessment and review of relevant site documentation during routine site inspection needs to note and record the following: o What are the dust suppression techniques followed for site and if any dust was noted to escape the site boundaries; o If muddy water was escaping site boundaries or muddy tracks were seen on adjacent roads; o adequacy of type of erosion and sediment control measures installed on site, condition of erosion and sediment control measures including if these were intact following heavy rain; o Are their designated areas for concrete works, and refuelling; o Are their spill kits on site and if there are site procedure for handling emergencies; o Is there any chemical stored on site and what is the storage condition? o Is there any dewatering activities if yes, where is the water being discharged; o How are the stockpiles being managed; o How is solid and liquid waste being handled on site; o Review of the complaint management system; o Checking if there are any activities being under taken out of working hours and how that is being managed. Summary Monitoring Table Impacts (List from Mitigation Parameters Monitored (As a Method of Location of Date of Name of Person IEE) Measures (List from minimum those identified in the Monitoring Monitoring Monitoring Who Conducted IEE) IEE should be monitored) Conducted the Monitoring Design Phase

Pre-Construction Phase

Construction Phase

Operational Phase

Overall Compliance with CEMP/ EMP No. Sub-Project Name EMP/ CEMP Part of CEMP/ EMP Being Status of Implementation (Excellent/ Action Proposed and Contract Documents Implemented (Y/N) Satisfactory/ Partially Satisfactory/ Additional Measures (Y/N) Below Satisfactory) Required

5. Approach and methodology for environmental monitoring of the project • Brief description on the approach and methodology used for environmental monitoring of each sub-project

6. Monitoring of environmental impacts on project surroundings (ambient air, water quality and noise levels) • Brief discussion on the basis for monitoring • Indicate type and location of environmental parameters to be monitored • Indicate the method of monitoring and equipment to be used • Provide monitoring results and an analysis of results in relation to baseline data and statutory requirements

As a minimum the results should be presented as per the tables below. Air Quality Results Parameters (Government Standards) Site No. Date of Testing Site Location 3 3 3 PM10 µg/m SO2 µg/m NO2 µg/m

Parameters (Monitoring Results) Site No. Date of Testing Site Location 3 3 3 PM10 µg/m SO2 µg/m NO2 µg/m

Water Quality Results Parameters (Government Standards) Site No. Date of Sampling Site Location pH Conductivity BOD TSS mg/L TN mg/L TP mg/L µS/cm mg/L

Parameters (Monitoring Results) Site No. Date of Sampling Site Location pH Conductivity BOD TSS mg/L TN mg/L TP mg/L µS/cm mg/L

Noise Quality Results

LAeq (dBA) (Government Standard) Site No. Date of Testing Site Location Day Time Night Time

LAeq (dBA) (Monitoring Results) Site No. Date of Testing Site Location Day Time Night Time

7. Summary of key issues and remedial actions • Summary of follow up time-bound actions to be taken within a set timeframe.

8. Appendixes • Photos • Summary of consultations • Copies of environmental clearances and permits • Sample of environmental site inspection report • Other

Appendix 31: MOEF Letter Regarding No Prior Approval Required regarding Wildlife Clearance Within Eco Sensitive Zone of National Park & Wildlife Sanctuary as Honble Supreme Court Order Dated 04.12.2006.

SAUW IEE Review - Information Log

Instructions: Provide information based on IEE submitted by Project Management Unit (PMU). This IEE log sheet will serve as record of the review findings, comments, and/or further actions required during implementation. A copy of the IEE log sheet should be (i) provided to PMU for their record and guidance on actions during implementation; (ii) attached in the cleared IEE to be disclosed; (iii) used as reference for review of updated/final IEE and (iv) inputted in the SARD Safeguards Compliance Tracking System.

Project: Madhya Pradesh Urban Services Improvement Project

Loan No.: 42486-IND Package No.: MPUSIP – 4D

Components: Water Supply improvement in Karera, Pichhore, Aron, Bairad, Vijayapur, and Isagarh Towns

Karera Town:

(i) Intake ( 6.0 m dia and 11.5 m Height) in Samoha Dam (ii) Raw water transmission – 13,500 m length, 350 mm diameter (iii) Water Treatment Plant (WTP) of 5.70 MLD (iv) 3 overhead tank (OHT, 1000 KL, 700 KL & 500 KL) (v) Clear water transmission – 4,725 m length, 100 - 250 mm diameter (vi) Distribution network – 5,2799 m length, 90 – 400 mm diameter (vii) Consumer connections: 6,213 numbers

Pichhore Town:

(i) Existing intake in Futiwar Dam (ii) Raw Water Transmission – 3,250 m length, 200 mm diameter (iii) WTP of 3.0 MLD; (iv) 2 GSR (200 KL each) (v) Clear water Transmission –2,550 m length, 100-150 mm diameter (vi) Distribution network – 33,125 m length, 75 – 315 mm diameter (vii) Consumer connections: 4,053 numbers

Aron Town:

(i) Weir (5 m height and 50 m long) across Sindh River and intake (ii) Raw water transmission – 8,680 m length, 200 mm diameter (iii) WTP of 4.50 MLD; (iv) Clear water Transmission –2,550 m length, 150-250 mm diameter (v) 1 OHT (700 KL) (vi) Distribution network – 20,559 m, 75 – 315 mm diameter (vii) Consumer connections: 5,824 numbers

Bairad Town:

(i) Intake (5.0 m dia and 11.36 m Height) in Pachipura Dam (ii) Raw water transmission – 790 m length, 250 mm diameter (iii) Water Treatment Plant (WTP) of 2.91 MLD (iv) 3 overhead tank (OHT, 2 Nos. 300 KL each and 1 No. 225 KL) (v) Clear water transmission – 4.88 km length, 150 - 200 mm diameter (vi) Distribution network – 89,177 m length, 75 – 300 mm diameter Consumer connections: 3,400 numbers

Vijaypur Town:

(i) intake (4.5 m dia and 13m height) in Kunwari River Near existing weir constructed by WRD across Kunwari River (ii) Raw water transmission – 300 m length, 200 mm diameter (iii) WTP of 2.65 MLD; (iv) Clear water Transmission – 3.72 km length, 150-250 mm diameter (v) 2 OHT (325 KL and 240 KL) (vi) Distribution network – 31,097 m, 75 – 280 mm diameter (vii) Consumer connections: 3,030 numbers

Isagarh Town:

(i) Existing Tube Wells – 16 Nos. (ii) Raw water transmission (from Tube Well to Sump) – 3,887 m length, 80 mm diameter (iii) 2 Sump ( 160 KL & 180 KL) with Chlorination plant (iv) Clear water Transmission (from Sump to existing OHT) – 102 m length, 150 mm diameter (v) Distribution network – 22,190 m, 75 – 315 mm diameter Consumer connections: 3,554 numbers Contract Type: NCB – DBO Contract package

Date of IEE: February 2019

Draft IEE? Updated/Revised IEE? Others Yes - -

Activity Status Detailed Comments and Further Actions Required 1. Environmental Yes No MPUSIP Cat B project. IEE is assessment has been √ required. This Draft IEE has been satisfactorily conducted prepared based on the preliminary based on ADB REA design. Checklist and scoping checklist.1 2. Environmental Yes No This package is under assessment based on √ implementation, and therefore this latest project components IEE needs immediate finalization and design based on the detailed design.

If design and construction is being taken up component-wise, phase- wise approach to be adopted for final IEE, which should include detailed implementation schedule showing timeline (completion of each component/chainage-wise detailed design and corresponding IEE submission). 3. Statutory Requirements2 - Forest Clearance Not applicable. None of the components are located in forest areas - No Objection Certificate Not applicable. - Site Location Clearance Not applicable. - Environmental Compliance Not applicable, the components Certificate are not listed in the Schedule 1 of the EIA Notification Act and its rules and regulations. √ Permit to Construct (or equivalent) Consent to establish (CTE) for WTPs in Karera, Bairad, Pichhore

1 ADB Rapid Environmental Assessment Checklist for screening and categorization. Scoping Checklist (“No Mitigation Scenario” Checklist) for scope of IEE, identification of impacts and development of environmental management plan. 2 If applicable, include date accomplished or obtained. Activity Status Detailed Comments and Further Actions Required Aron and Vijaypur from MPPCB. Applications submitted for CTE and is in process with MPPCB. √ Permit to Operate (or equivalent) Consent to operate (CTO) for WTP from MPPCB This is due prior to start of operation. Application will be submitted after completion of construction, and operation will be started only after obtaining CTO. √ Permit for water abstraction and Permission obtained from Water intake Resources Department (WRD) Karera, Bairad, Pichhore, Aron and Vijaypur towns. Not applicable to Isagarh Town (groundwater source) -- Others – Tree Cutting Permit Exact number of trees to be cut is not determined at this stage

Action Required: Include in the IEE: In the Final IEE, the following information will be included: (i) Exact number of tress to be cut should be reported in the Final IEE (ii) Contractor to obtain Tree Cutting Permit from the Forest Department Contractor allocate budget (INR 200,000) for the tree compensation/ replantation 5. Policy, legal, and Adequate Not Adequate Law on EIA not applicable. administrative framework √ Subproject/components are not Included discussions and requirements of listed in the Schedule 1 of the EIA the: Notification Act and its rules and √ National regulation/law on EIA regulations. √ Environmental agency Though equivalent environmental - Relevant international legislations (national and local) environmental agreements are adopted in this subproject, it is √ Environmental standards (IFC’s clearly mentioned in the Draft IEE, EHS Guidelines) that the PMU and PIU should adopt stringent measures as specified in the World Bank Group’s Environment, Health and Safety Guidelines. 6. Anticipated environmental assessed impacts and mitigation Draft IEEs assessed impacts on impacts and mitigation risks: measures physical, biological, social and measures included: cultural environment, and suggest Yes No n/a appropriate mitigation measures to avoid, minimize or mitigate the same. - Biodiversity √ Not applicable. Endangered conservation species and habitats not present in subproject area.

Karera bird sanctuary is located close to Karera town (500 m away). None of the components Activity Status Detailed Comments and Further Actions Required are located in the sanctuary, however, as part of the municipal boundary is within the eco- sensitive zone (2 km around the sanctuary), subproject components, including Karera water intake falls within eco sensitive zone. However, there are no eco sensitive features like forests in the identified sites, of which, except intake which is located outside the town, all the components are located within the urban area of Karera Town. Project do not envisage cutting of any trees. Construction of Infrastructure and civic amenities is permitted in eco-sensitive zone under applicable laws. Commercial extraction of surface / groundwater requires period permission of competent authority. Although it is not a commercial extraction, permission to abstract water is already obtained from WRD for Karera.

Moreover, this sanctuary at present do not have any notable birds. National Wildlife Board and Government Madhya Pradesh recommended in 2010 to Supreme Court for denotification of bird sanctuary. √ Pollution √ WTP generates sludge from prevention and sedimentation, chemical abatement flocculation, residuals of excess chemical dosage, plankton etc; and wastewater from rinsing and back washing of filter. IEE includes design measures for proper management of sludge and wastewater. Wastewater will be collected and recirculated, resulting in zero waste discharge, and settled sludge will be dewatered, dried, and disposed by land filling / reused in beneficial purposes. Various pollution prevention measures included in IEE for construction phase to control dust,noise, emissions from construction vehicles, silt-laden surface runoff during rains etc., Action required: The Final IEE and SEMP should show how (i) design provides for pollution prevention from WTP, Activity Status Detailed Comments and Further Actions Required and (ii) how dust noise, air emissions, and water pollution will be controlled during the construction. √ Health and √ The Final/updated IEE and SEMP safety includes information on implementation of health and safety by DBO contractor. SEMP includes EHS (environment- health- safety) implementation information. DBO Contractor has also appointed Site EHS supervisor. Detailed description of construction impacts and mitigation measures provided in the IEE /, EMP tables. Health and safety impacts, and appropriate mitigation measures included for operation stage. X Physical cultural √ Not applicable. There are no resources places of archeological / historical importance or protected monuments X Cumulative Not applicable. The subproject impacts will not add any incremental impacts to the environment. X Transboundary Not applicable. The subproject is impacts small-scale, site-specific and short in duration to have potential transboundary impacts. 7. Impacts from Associated Addressed Not Not Not applicable, there are no Facilities3 Addressed applicable associated facilities under this √ subproject/package. 8. Analysis of Alternatives Yes No Not required for Cat B and no √ need to include in IEE. 9. EMP budget included Yes No Included in provisional sums of √ the contract 10. EMP implementation Yes No (i) MPUSIP Phase 1 Project integrated in FAM/PAM √ Administration Manual (PAM) and bid documents includes sections on environmental safeguards. Information in the PAM has been referred in the preparation of the Draft IEE. (ii) MPUSIP Phase 1 EARF also provides detailed requirements on EMP implementation and necessary formats. These are included in the Draft IEE. (iii) Bid document mentions that IEE and EMP forms part of the bid document.

3 ADB SPS (Appendix 1 para 6) defines associated facilities as not funded as part of the project (funding may be provided separately by the borrower/client or by third parties), and whose viability and existence depend exclusively on the project and whose goods or services are essential for successful operation of the project. Activity Status Detailed Comments and Further Actions Required Action Required: Confirm that IEE and EMP provided to contractor after contract award. This will be confirmed by PMU in the environmental monitoring report to be submitted to ADB on a semi-annual basis. 11. Consultation and Yes No Included in IEE. As per the details Participation √ furnished in the Draft IEE, Stakeholder Consultations were held in respective municipal offices and at various locations in all six project towns in 2015, 2016 and 2018.

In all 166 stakeholders participated in the consultations (male =125, female = 41)

During the consultation/s, all the stakeholders very supportive of the project. Attention of stakeholders drawn to the EMP and explained to them how the construction issues will be managed by implementing mitigation measures. All necessary measures as per EMP will be taken by contractor to avoid/minimize construction disturbances. The following queries were raised by the local communities and it was responded by the PIU and Consultants.

• All stakeholders were very supporting of the project, and extended full cooperation during the works • Expressed concern regarding delay in construction works and requested to appoint a competent contractor to conduct and complete the works on schedule.

Action Required: The PIU and DBO Contractor will continue meaningful consultations and information disclosure during detailed design, construction and O&M stages. DBO Contractor will include records of consultations, issues/concerns, attendance sheets, and resolutions to the progress report to be submitted to PIU. This will be included by PMU in the environmental monitoring Activity Status Detailed Comments and Further Actions Required report to be submitted to ADB on a semi-annual basis. 12. Grievance Redress Yes No GRM established in MPUSIP 1. Mechanism √ Action Required: PIUs will establish GRM and with the help of DBO Contractor, will disseminate information on GRM during implementation. GRM Notification will be included by PMU in the environmental monitoring report to be submitted to ADB on a semi- annual basis. Description of GRM: GRM established in MPUSIP Phase 1 will be followed therefore applicable to this subproject/package. GRM description Included in IEE.

GRC members identified: Included in IEE.

Action Required: GRC composition will be included by PMU in the environmental monitoring report to be submitted to ADB on a semi-annual basis.

GRM established and notified? This will be included in final/updated IEE.

13. Disclosure Endorsement to disclose on ADB Pending. This will be requested website when the IEE has been cleared by ADB. Disclosed on project website Pending. This will be requested when the IEE has been cleared by ADB. Relevant information available to Pending. This will be requested stakeholders and affected people in when the IEE has been cleared by language and form they understand. ADB. 14. Mobilized PMU Yes No Mobilized Environment Specialist √ 15. Mobilized PIU Yes No An Assistant Project Manager Environment Specialist √ (APM) in PIU is designated for coordinating on safeguards at PIU level 16. Mobilized PMC Yes No Mobilized Environment Specialist at √ PMU level 17. Mobilized PMC Yes No Mobilized Environment Engineer at √ PIU level 18. Confirm bid and contract Yes No documents and/or EMP √ The Draft IEE includes EHS include requirement for supervisor requirement. Bid the contractor to appoint specifically does not include EHS EHS supervisor and/or supervisor requirement, but EMP nodal person for is part of the bid, which clearly environment safeguards specified EHS supervisor requirement. Activity Status Detailed Comments and Further Actions Required

Action Required: PIU to confirm qualifications of EHS supervisor to implement health and safety requirements in the SEMP. This will be included by PMU in the environmental monitoring report to be submitted to ADB on a semi-annual basis. 19. If contract awarded Yes No already, confirm √ EHS supervisor mobilized by the contractor’s appointment Contractor of EHS supervisor and/or nodal person for environmental safeguards 20. Awareness training on Yes No Conducted by PMU. The DBO compliance to safeguard √ Contractor is provided with requirements Safeguards Induction to discuss applicable environmental safeguards requirements. The environmental safeguards training/ workshop was conducted by the environmental officers of PMU/PIU and their consultants.

Action required. GRC members will be provided with workshops and training so they will be able to address project-related complaints/grievances. This will be included by PMU in the environmental monitoring report to be submitted to ADB on a semi- annual basis. 21. Monitoring and Reporting Yes No Sample monitoring checklists are included in the Draft IEE.

Action Required: The Final IEE and SEMP will include more detailed checklists such (i) contractors daily EHS Checklist; (ii) contractors monthly SEMP Implementation Report; and (iii) PIU environmental safeguards compliance report. √ 22. Others/Remarks This IEE report is under review, not yet approved by ADB

Specific comments for further follow up: - This IEE needs immediate update / finalization based on the detailed design; - CTE to be obtained prior to start of WTP construction in all five towns - The draft IEE for Package 4D is recommended for ADB Clearance for inclusion in bid and contract documents. - Cleared draft IEE to be disclosed on project website (PMU and PIU). If project website is not available, the summary of the draft IEE should be posted in public notice boards. - The relevant information in the draft IEE should also be disclosed to stakeholders and affected people in a timely manner in language/form they understand. Activity Status Detailed Comments and Further Actions Required - Continuous meaningful consultations including information dissemination on project-GRM should be conducted during detailed engineering design, construction and if required, until O&M. - PMU to submit to ADB the final IEE together with DBO contractor’s SEMP/s for review and disclosure. The final IEE should include detailed information on how the abovementioned further actions are conducted/met. - DBO contractor should submit to PMU and PIU the SEMP/s upon completion of the detailed engineering design. NO works should be allowed until the SEMP/s is/are cleared and confirmed to satisfactorily meet the requirements of Government of India laws, rules and regulations and ADB SPS. Reporting of SEMP/s implementation and environmental safeguards should be: (i) DBO contractor to PIU to be done on the monthly basis; (ii) PIU to PMU to be done every three months; and (iii) PMU to ADB every six months Prepared by: (name, Achyutha Rao Aleti, Safeguards Consultant, ADB designation and date) July 22, 2019 Noted and Checked By: (name, designation and date) Documents/References: Draft IEE for Package 4B – Submitted by Mr. Barange, Safeguards Officer, PMU to ADB (February 25, 2019)