June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR ,

CHAPTER 3: COMPLIANCE STATUS

A. General Condition 1. “Consent to Establish” shall be obtained from Haryana State Pollution Control Board under Air Water Act and a copy shall be submitted to the SEIAA, Haryana before the start of any construction work at site. Status “Consent to Establish” has been obtained from Haryana State Pollution Control Board under Water Act and Air Act and is attached as Annexure II. 2. A first aid room as proposed in the project will be provided in the project both during construction and operation phase of the project Status First aid room has been provided for safeguarding primary healthcare of the workers employed at the project site

First Aid Room

3. Adequate drinking water and sanitary facilities should be provided for construction workers at the site. Provision should be made for mobile toilets. Open defecation by the labours is strictly prohibited. The safe disposal of waste water and solid wastes generated during the construction phase should be ensured.

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

Status a) Adequate drinking water and sanitary facilities have been provided for construction workers at site. b) Sufficient arrangements for toilets and bathing have been provided on site and Fresh Water Tanker near the labour hutments. c) Safe disposal of wastewater and solid waste is being done. d) A temporary wash area has been constructed for labours and a good hygienic condition is being maintained. 4. All the top soil excavated during construction activities should be stored for use in horticulture / landscape development within the project site. Status The excavation work has been completed now. All the excavated top soil is being stored within the project premises for landscape development.

5. The project proponent shall ensure that the building material required during the construction phase is properly stored within the project area disposal of construction waste should not create any adverse effect on the neighboring communities and be

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

disposed of taking the necessary precautions for general safety and health aspects of people, only in approved sites with the approval of competent authority. Status The construction material is stored within the project area. No excavated muck has been disposed off outside the project premises and is stored at an assigned location within the site boundary. 6. Construction spoils, including bituminous material and other hazardous materials must not be allowed to contaminate water courses and dumpsites for such material must be secured so that they should not leach into ground water and any hazardous waste generated during construction phase, should be disposed of as per proper rules and norms with necessary approval of Haryana State Pollution Control Board. Status Construction spoils are being collected at an earmarked location & disposed of as per the Solid Waste Management Rules & guidelines, 2000 quite frequently such that that they do not contaminate with the ground water. This is a Group Housing Project. There is no source of hazardous waste generation. 7. The diesel generator sets to be used during construction phase should be of low Sulphur diesel type and should conform to Environment (Protection) Rules prescribed for air emission standards. Status Low Sulphur type diesel is being used during construction phase and purchased from IOCL/HPCL/BPCL Stations. The diesel generator sets comply with the Environment (Protection) Rules prescribed for air emission standards. 8. The diesel required for operating DG sets shall be stored in underground tanks and if required, clearance from Chief Controller of Explosives shall be taken. Status Two DG Sets (1 x 125 kVA + 1 x 380 kVA) have been installed on the site. Diesel for DG sets is being purchased on daily need basis hence no

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

diesel storage required. 9. Ambient noise levels should conform to the residential standards both during day and night. Incremental pollution loads on the ambient air and noise quality should be closely monitored during construction phase. Adequate measures should be taken to reduce ambient air and noise levels during construction phase, so as to conform the stipulated residential standards. Status Ambient air, soil & noise levels have been monitored and all the parameters are within the permissible limits. All the required measures are being taken during the construction phase to reduce noise levels. Environmental monitoring reports are attached as Annexure III. 1. Air Quality: Air Quality has been monitored in the month of March 2015. All the parameters are within the prescribed limits, set by CPCB.

Levels of PM10 & PM2.5 are high due to movement of trucks and other heavy vehicles in the site and their value is gradually declining as measures are being taken to control the fugitive dust emissions.

450 400 350 300 250 200 150 CPCB Standard 100 50 14-Mar 0

2. Noise Quality: Noise Quality has been monitored once in the month of March 2015. Noise level was observed within the permissible limit, set by CPCB. However, the noise level is little high due to ongoing construction activities on site.

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

70 60 50 40 30 Value at site in dB 20 CPCB Standard in dB 10 0 Lday (6.0 AM Lnight (10.0 TO 10.0 PM TO PM) 6.0 AM)

3. Soil Quality Monitoring: Soil Quality has been monitored once in the month of March 2015. No significant observation was made during monitoring and analysis.

Value-Onsite 3000 2500 2000 1500 1000 500 Value-Onsite

0

Cation…

pH(1:5…

Electrical…

Zinc mg/kg

Phosphorus…

Porosity% by…

Potassium(as…

Silt % Silt mass by

Waterholding…

Magnesium(as…

Nitrogen by…%

Sodium(asNa)…

Clay% bymass

Calcium(as Ca)… Sandby % mass Bulk Densitygm… 10. Fly ash should be used as building material in the construction as per the provision of Fly Ash notification of September, 1999 and amended as on 27th August, 2003. Status First class bricks & fly ash is being used as building material in the construction as per the provision of Fly ash notification of September, 1999 and amended as on 27th August, 2003. 11. Storm water control and its re-use as per CGWB and BIS standards for various applications should be ensured. Status Storm water control and its re-use are being ensured for various

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

applications as per CGWB and BIS standards. There is a provision of 14 rain water harvesting pits for harnessing the storm water and to maintain the ground water recharge. 12. Water demand during construction should be reduced by use of pre- mixed concrete, curing agents and other best practices. Status Pre-mixed concretes and curing agents are being used during the construction phase to reduce water demand. 13. In view of the severe constrains in water supply augmentation in the region and sustainability of water resources, the developer will submit the NOC from CGWA specifying water extraction quantities and assurance from HUDA/utility provider indicating source of water supply and quantity of water with details of intended use of water- potable and non-potable. Assurance is required for both the construction and operation stages separately. It shall be submitted to the SEIAA and RO, MoEF, before the start of construction. Status No ground water extraction is being done during construction phase. The same will be followed during operation phase. Permission for water supply from HUDA will be submitted in forthcoming compliance report. 14. Roof should meet prescriptive requirement as per Energy Conservation Building Code by using appropriate thermal insulation material. Status Building is being designed & constructed using thermal insulating materials with the suitable R&U values as per the National Building Code & Energy Conservation Building Code. 15. Opaque walls should meet prescriptive requirement as per Energy Conservation Building Code which is proposed to be mandatory for all air and conditioned spaces while it is aspirational for non-air- conditioned spaces by using appropriate thermal insulation material. Status Opaque wall will meet prescriptive requirement of maximum U Factor

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

and minimum R factor for maximum insulation. 16. The approval of the competent authority shall be obtained for structural safety of the building on account of earthquake, adequacy of firefighting equipment, etc. as per National Building Code including protection measures from lightening etc. If any forest land is involved in the proposed site, clearance under Forest Conservation act shall be obtained from Competent Authority. Status a) To deal with any fire related accident, fire-fighting facility of single handed hydrant valve, long hose reel, and portable fire extinguisher is proposed. b) The project falls under seismic active Zone IV indicating high damage risk zone. The buildings are being designed as earthquake resistant and are complying with the required IS specifications, structural safety of the building due to earthquake, adequacy of firefighting equipment, etc. as per the National Building Code 2005 including protection measures from lightening etc. Structural safety certificate is attached as Annexure IV. c) No forest land is involved in the project site. 17. Overexploited groundwater and impending severe shortage of water supply in the region requires the developer to redraw the water and energy conservation plan. Developer shall reduce the overall footprint of the proposed development. Project proponent shall incorporate water efficiency/savings measures as well as water reuse/recycling within 3 months and before the start of construction to the SEIAA, Haryana and RO,MOEF,GOI, Chandigarh. Status Agreed. Water efficiency/ saving measures along with water balance diagram have already been submitted to SEIAA, Haryana. 18. The project proponent shall construct 14 rain water harvesting pits for recharging the ground water within the project premises. Rain water harvesting pits shall be designed to make provisions for silting chamber and removal of floating matter before entering

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

harvesting pit. Maintenance budget and persons responsible for maintenance must be provided. Care shall also be taken that contaminated water do not enter any RWH pit. Status 14 rain water harvesting pits have been proposed for ground water recharge. The rain water harvesting pits will be designed in such a way so as to make provisions for the silting chamber and removal of floating matter before storm water enters the pit. Care will be taken that the contaminated water does not enter the RWH pit. Proper budget and person responsible for the maintenance will be provided. 19. The project proponent shall provide minimum one hydraulic ladder of sufficient length for escape of people in case of fire. Status This will be followed. 20. The project proponent shall submit assurance from the DHBVN for supply of 4523 KW of power supply before the start of construction. In no case project will be operational solely on generators without any power supply from any external power utility. Status Power requirement is being supplied by DHBVN. Assurance as electricity bill from DHBVN is enclosed as Annexure-V. 21. Detail calculation of power load and ultimate power load of the project shall be submitted to DHBVN under intimation to SEIAA Haryana before the start of construction. Provisions shall be made for electrical infrastructure in the project area. Status Agreed. Detail calculation of power load has already been submitted to SEIAA 22. The project proponent shall obtain NOC from nearest fire station before the start of construction. Status Fire fighting scheme has been approved vide letter no. FS/MCG/2012/2498, dated: 26.09.2012 and copy of the same is attached as Annexure VI. 23. The project proponent shall not raise any construction in the nature land depression/Nallah/water course and shall ensure that

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

the natural flow from the nallah/water course is not obstructed. Status The project site is vacant land. The construction of the project is not obstructing any flow from the nallah/water course. 24. The project proponent shall keep the plinth level of the building blocks sufficiently above the level of the approach road to the Group Housing Project as per prescribed by-laws. Levels of the other areas in the Group Housing Projects shall also be kept suitably so as to avoid flooding. Status The plinth level of the building blocks has been kept well above the level of the approach road as per prescribed bye-laws. The plinth level is sufficiently kept above so as to avoid flooding. 25. Construction shall be carried out so that density of population does not exceed norms approved by Director General Town and Country Department Haryana. Status This will be followed. 26. The project proponent shall submit an affidavit with the declaration that the ground water will not be used for construction and only treated water should be used for construction. Status No ground water extraction is being done. STP treated water from Authority is being used for the construction phase. The affidavit regarding no ground water extraction during the construction phase is attached as Annexure VII. 27. The project proponent shall not cut any existing tree and project landscaping plan should be modified to include those trees in the green area. Status The project site was a vacant land. Hence, there has been no cutting of trees. 28. The project proponent shall provide helipad facility as required under NBC norms and shall seek permission of helipad from AAI. Status This will be followed. 29. The project proponent shall ensure that ECBC norms for composite climate zone are met. In particular building envelope, HVAC

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

service, water heating, pumping, lighting and electrical infrastructure must meet ECBC norms. Status Provisions will be made that HVAC services, water heating systems, pumping, lighting and electrical infrastructure will meet ECBC norms. 30. The project proponent shall provide 3 mtrs high barricade around the project area, dust screen for every floor above the ground, proper sprinkling and covering of stored material to restrict dust and air pollution during construction. Status This is being followed. Necessary measures are being taken and will be taken in future to control the dust generation during construction stage. 31. The project proponent shall construct a sedimentation basin in the lower level of the project site to trap pollutant and other wastes during rains. Status Provision of suitable sedimentation basin in the lower level will be made to trap the pollutants and other wastes during rainy days. 32. The project proponent shall provide proper rasta of proper width and proper strength for this project before the start of the construction. Status A proper rasta of 3 karam width and suitable width of setback was left before the commencement of construction. 33. The project proponent shall provide all the safety measures for the workers during construction phase of high rise building. Status The safety equipments such as nets, helmets etc. are being provided to laborers during the construction phase. Safety slogans have been provided on site. 34. The project proponent shall ensure plinth level of the building block is 1.5 mtrs above 100 years flood level of the said Najafgarh Jheel. Status The plinth level of the group housing project has been kept 1.5 mtrs above the 100 years flood level of the said Najafgarh Jheel. 35. The project proponent shall obtain NOC from HUDA as well as

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

Irrigation Department before the start of construction, regarding possible adverse effect of project proposal on the said Najafgarh Jheel. Status The Group Housing will be having STP of capacity 415 KLD to treat the waste water generated which will be fully recycled within the project premises. Therefore, no adverse impact is anticipated on Najafgarh Jheel. 36. The project proponent shall not restrict the entry of public in the revenue rasta or shall not encroach upon the same. Status The revenue Rasta will be kept at the minimum disturbance caused due to the construction activities such that neither the entry of common public in the revenue Rasta is restricted nor the encroachment is done upon the same. 37. The project proponent shall submit revised proper certificate of Tehsildar regarding non- applicability of MoEF GOI dated 07- 05- 1992 (Aravali Notification) before the start of construction. Status Aravali Clearance has been obtained and attached as Annexure VIII. 38. The project proponent shall submit certificate of DFO Gurgaon regarding non-applicability of MoEF GOI dated 07-05-1992 (Aravalli Notification) before the start of construction. Status The land schedule of the project site does not fall under Forest Land. The NOC from DFO, Gurgaon for the same is attached as Annexure IX. 39. The project proponent shall avoid construction noise at night time. Status Construction schedule has been planned such that maximum work will be done during the day time only. Operational Phase: 1. “Consent to Operate” shall be obtained from Haryana State Pollution Control Board under Air and Water Act and a copy of it shall be submitted to the SEIAA, Haryana.

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

Status Agreed. Consent to Operate will be obtained from Haryana State Pollution Control Board under Air and Water Act before offering possession. A copy of same will be submitted to the SEIAA, Haryana. 2. The Sewage Treatment Plant (STP) shall be installed for the treatment of the sewage generated to the prescribed standards including odour and treated effluent will be recycled. The installation of STP should be certified by an independent expert and a report in this regard should be submitted to the SEIAA, Haryana before the project is commissioned for operation. Tertiary treatment of waste water is mandatory. Discharge of treated sewage shall conform to the norms and standards of HSPCB Panchkula. Project proponent shall implement such STP technology which does not require filter backwash. Status The STP of capacity 415 KLD will be installed within the project premises to treat the wastewater generated in the Group Housing Colony till the tertiary level. The treated water will conform to the CPCB standards and will be recycled & reused in flushing and landscaping. The installation of STP will be certified by an independent expert and a report in this regard will be submitted to the SEIAA, Haryana before the project is commissioned for operation. 3. Separation of the grey and black water should be done by the use of dual, plumbing line. Treatment of 100% grey water by decentralized treatment should be done ensuring that the re- circulated water should have BOD maximum 10 ppm and the recycled water will be used flushing, gardening and DG set cooling etc to achieve zero exit discharge. Status a) Dual Plumbing System will be installed for separation of grey & black water. b) Treatment of 100% grey water will be done by decentralized treatment ensuring the recycled water shall have BOD maximum up to 10 mg/l. Dual Plumbing Plan has already been submitted in the previous compliance report.

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

c) The recycled water will be used for flushing, gardening and DG set cooling. 4. For disinfection of the treated wastewater ultra-violate radiation or ozonization process should be used. Status This will be used.

5. The solid waste generated should be properly collected and segregated. Biodegradable waste will be decomposed at site and dry/insert solid waste should be disposed of to approve sites for land filling after recovering recyclable materials. Status A separate area has been marked for temporary storage of solid waste. It will be disposed of as per the Municipal Solid Waste Handling Rules. Biodegradable waste will be decomposed at site and dry/insert solid waste will be disposed of to approve sites for land filling after recovering recyclable materials. 6. Diesel power generating sets proposed as source of backup power for lifts, common area illumination and for domestic use should be enclosed type and conform to rules made under the Environment (Protection) Act, 1986. Location of DG sets should be in the basement as promised by the project proponent with appropriate stack height proponent i.e., above the roof level as per the CPCB norms. The diesel used for DG sets should be of low sulphur content (maximum upto 0.25%). Status DG sets will be used only in case of power failure. To avoid noise pollution, acoustic enclosure over the DG Set has been placed as per rules made under the Environment (Protection) Act, 1986. The diesel used for DG sets will be of low Sulphur contents (maximum up to 0.25%). 7. Ambient noise level should be controlled to ensure that it does not exceed the prescribed standards both within and at the boundary of the proposed residential complex. Status Measures are being taken to reduce and control the ambient noise

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

levels so that it does not exceed the prescribed standards both within and at the boundary of the proposed residential complex. 8. The project proponent should maintain at least 20% as green cover area for tree plantation especially all around the periphery of the project and on the road sides preferably with local species which can provide protection against noise and suspended particulates matter. The 19.6% open spaces inside the plot should be preferably landscaped and covered with vegetation /grass, herbs & shrubs. Only locally available plant species shall be used. Status a) 20% green area will be maintained for tree plantation all around the periphery of the project and on the road sides with the local species with the modern attenuation capabilities. b) The 19.6% open spaces inside the plot will be landscaped and covered with vegetation/ grass, herbs & shrubs. Landscape plan has already been submitted in the previous compliance report. 9. The project proponent shall strive to minimize water in irrigation of landscape by minimizing grass area, using native variety, xeriscaping and mulching, utilizing efficient irrigation system, scheduling irrigation only after checking evapo-transpiration data. Status Use of water in irrigation of landscape will be minimized by minimizing grass area, using native variety, xeriscaping and mulching, utilizing efficient irrigation system and scheduling irrigation only after checking evapo-transpiration data. 10. Rain water harvesting for roof run- off as per plan submitted should be implemented. Before recharging the surface runoff, pre- treatment through sedimentation tanks must be done to remove suspended matter, oil and grease. The bore well for rainwater recharging should be kept at least 5 meters Above the highest ground water table. Care shall be taken that contaminated water do not enter any RWH pit. The project proponent shall avoid rain water harvesting of first 10 minutes of rainfall. Roof top of the building shall be without any toxic material or paint which can

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

contaminate rain water. Wire mess and filters should be used wherever required. Status a) Rainwater harvesting as per plan for roof run-off and surface run- off will be implemented. b) Suspended matter, oil and grease will be removed by treatment before recharging with surface run-off. The bore well for recharge will be kept 5 mtrs above the highest ground water table. c) Care will be taken so that contaminated water does not enter any RWH pit. d) For avoiding the ground water contamination, first 10 minutes of the rainfall will not be harvested. 11 The ground water level and its quality should be monitored regularly in consultation with Central Ground Water Authority. Status This will be followed. 12 There should be no traffic congestion near the entry and exit points from the roads adjoining the proposed project site. Parking should be fully internalized and no public space should be utilized. Status a) Parking will be provided in the basement and no public place will be utilized for the same. There will be no traffic congestion near the entry and exit points. b) Parking cum traffic circulation plan has already been submitted in the previous compliance report. 13 A report on the energy conservation measure conforming to energy conservation norms finalize by Bureau of Energy Efficiency should be prepared incorporating details about building materials and technology: R & U factors etc. and submit to the SEIAA, Haryana in three month time. Status Report on energy conservation measures has already been submitted to SEIAA, Haryana along with proposal. 14 Energy conservation measure like installation of CFLs/TFLs should be properly collected and disposed off/sent for recycling as per the prevailing guidelines/rules of the regularity authority to

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

avoid mercury contamination. Use of solar panels must be adapted to the maximum extent possible for energy conservation. Status a) LEDs will be used wherever possible as a measure of energy conservation. b) Use of T-5 and solar lighting in open spaces, common area, and landscape area for lighting outside the building will be integral part of the project design. c) Used CFLs and TFLs will be properly collected, disposed of and sent to authorized dealers/ recyclers so as to avoid mercury contamination. 15 The project proponent shall use zero ozone depleting potential material in insulation, refrigeration, air-conditioning and adhesive. Project proponent shall also provide halon free fire suppression system. Status It is assured that the halon free fire suppression system will be used. In addition to it; materials used in insulation, refrigeration and air- conditioning will have zero ozone depleting potential. 16 The solid waste generated should be properly collected and segregated as per the requirement of MSW Rules, 2000 and as amended from time to time. The Biodegradable waste should be composed by vermi-composting at the site ear marked within the project area and dry/insert solid waste should be disposed of to the approved sites for land filling after recovering recyclable material. Status During operation phase, solid waste generated will be collected temporarily at an earmarked location. It will be disposed of as per the Municipal Solid Waste Management Rules, 2000. Biodegradable waste will be composed by vermi-composting at the site ear marked within the project area and dry/insert solid waste will be disposed off to the approved sites for land filling after recovering recyclable material. 17 The provision of the solar water heating system shall be as norms specified by HAREDA and shall be made operational in each building block.

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

Status This will be followed. 18 The traffic plan and the parking plan proposed by the PP should be adhered to meticulously with further scope of additional parking for future requirement. There should be no traffic congestion near the entry and exit point from the roads adjoining the proposed project site. Parking should be fully internalized and no public space should be used. Status Parking will be fully internalized and no public space will be utilized. There will be no traffic congestion near the entry and exit points from the roads adjoining the project site as bell shaped entry and exit points will be provided. Parking cum Traffic Circulation Plan has already been submitted in the last compliance report. 19 The project shall be operationalized only when HUDA/public authority will provide domestic water supply system in the area. Status Agreed. 20 Operation and maintenance of STP, solid waste management and electrical infrastructure, pollution control measures shall be ensured even after the completion of sale. Status All the sustainable activities like STP, solid waste management and electrical infrastructure, pollution control measures will be operated and maintained even after completion of sale. 21 Different types of wastes should be disposed off as per provisions of municipal solid waste, biomedical waste, hazardous waste, e- waste, batteries & plastic rules made under the Environment Act, 1986. Particularly e-waste and battery waste shall be disposed of as per E- waste management rules 2011 and Batteries Management Rules 2001. The project proponent should maintain a collection center for E- waste and it should be disposed of to only registered and authorized dismantler/recycler. Status Sufficient provisions will be made for segregating the waste generated within the Group Housing project. Disposal of e-waste and battery

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

waste will be made under the provisions of E-waste Management Rules 2011 and Batteries Management Rules 2001. Necessary agreements will be made with the registered and authorized dismantler/recycler for disposing E- waste. 22 Standards for discharge of environmental pollutants as enshrined in various schedules of rule 3 of Environment Protection Rule 1986 shall be strictly complied with. Status It is ensured that the standards for discharge of environmental pollutants will be strictly complied with that enshrined in various schedules of rule 3 of Environment Protection Rule 1986. 23 Water supply shall be metered to different residential units and different utilities. Status This will be followed. 24 The project proponent shall ensure that the stack height of DG sets is as per the CPCB guide lines and also ensure that the emission standards of noise and air are within the CPCB prescribed limits. Noise and emission level of DG sets greater than 800 kVA shall be as per CPCB latest standards for high capacity DG sets. Status Sufficient stack height of DG sets will be provided. Care will be taken so that the noise and emission level of high capacity DG sets will be kept within the CPCB prescribed limits. 25 All electric supply exceeding 100 amps, 3 phase shall maintain the power factor between 0.98 lag to 1 at the point of connection. Status This will be followed. 26 The project proponent shall use only treated water instead of fresh water for HVAC and DG cooling. The project proponent shall use evaporative cooling technology and double stage cooling system for HVAC in order to reduce water consumption. Further temperature, relative humidity during summer and winter seasons should be kept at optimal level. Variable speed drive, best co- efficient of performance, as well as optimal integrated point load

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

value and minimum outside fresh air supply may be resorted for conservation of power and water. Coil type cooling DG sets shall be used for saving cooling water consumption for water cooled DG sets. Status This will be followed. a) Treated water from STP will be reused in HVAC & DG Set cooling. b) Coil type cooling DG Sets will be used for saving cooling water consumption for water cooled DG Sets. PART-B GENERAL CONDITIONS

1 The Project Proponent shall ensure the commitments made in Form 1, Form 1A, EIA/EMP and other documents submitted to the SEIAA for the protection of environment and proposed environmental safeguards are complied with in letter and spirit. In case of contradiction between two or more documents on any point, the most environmentally friendly commitment on the point shall be taken as commitment by project proponent. Status Agreed. Commitments made in Form- 1, Form-1A, EIA/ EMP and other documents submitted to SEIAA will be complied with. 2 Six monthly monitoring reports should be submitted to the Haryana State Pollution Control Board and Regional Office, MOEF, GOI, Northern Region, Chandigarh and a copy to the SEIAA, Haryana. Status Six monthly compliance reports are being regularly submitted to Regional Office Haryana State Pollution Control Board, MoEF GOI Northern Region and SEIAA Panchkula, Haryana. 3 Noise, STP outlet and stack emission shall be monitored daily. Other environmental parameters shall be monitored on monthly basis. After every 3 months the project proponent shall conduct environmental audit and shall take corrective measure, if required, without delay. Status This will be followed.

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

4 The SEIAA Haryana reserves the right to add additional safeguard measure subsequently, if found necessary. Environmental Clearance granted will be revoked if it is found that false information has been given for getting approval of this project. SEIAA reserves the right to revoke the clearance if conditions stipulated are not implemented to the satisfaction of SEIAA/MoEF. Status Agreed. 5 The project proponent shall not violate any judicial orders/pronouncements issued by any Court/tribunal. Status Agreed. 6 All other statutory clearance such as approvals for storage of diesel from Chief Controller of Explosives, Fire Department, Civil Aviation Department, Forest Conservation Act, 1980 and Wildlife (Protection) Act, 1972, PLPA 1900, Forest Act, 1927 etc. shall be obtained, as applicable by project proponents from the respective authorities prior to construction of the project. Status Clearance has been obtained from Airport Authority of vide letter no.AAI/NOC/2011/458/3757, Dated: 28.11.2011. Copy of the same is attached as Annexure X. Aravali clearance is attached as Annexure VIII. Forest NOC is attached as Annexure IX. 7 The project proponent should inform the public that the project has been accorded Environmental Clearance by the SEIAA and copies of the clearances letter are available with the State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of Environment Clearance conditions shall also be put on project proponent’s web site for public awareness. Status This will be followed.

M/s Greatvalue HPL Infratech Pvt. Ltd. June 2015 [GROUP HOUSING PROJECT “ATS TRIUMPH” AT SECTOR - 104,VILLAGE DHANWAPUR GURGAON, HARYANA

8 Any appeal against this Environmental Clearance shall lie with the National Green Tribunal, if preferred, within period of 30 days as prescribed under Section 16 of the National Green Tribunal Act, 2010. Status Agreed 9 The project proponent shall put in place Corporate Environment Policy as mentioned in MoEF, GOI OM no. J-11013/41/2006-IA II (I) dated 26.4.2012 within 3 months period. Latest Corporate Environment Policy should be submitted to SEIAA within 3 months of issuance of this letter. Status The Corporate Environment Policy as mentioned in MoEF, GOI OM no. J- 11013/41/2006-IA-II (I) dated 26.4.2012 will be submitted in the forthcoming compliance report. 10 The fund ear-marked for environment protection measures should be kept in separate account and should not be diverted for other purposes and year wise expenditure shall be reported to the SEIAA/RO MoEF GOI under rules prescribed for Environment Audit. Status A separate fund ear-marked for environment protection measures and the year-wise expenditure will be reported to the SEIAA/RO MoEF GOI under rules prescribed for Environment Audit. 11. The project proponent shall obtain NOC under Aravali Notification from CEC of Hon’ble Supreme Court regarding coverage under Aravali Notification before start of construction. Status The NOC under Aravali Notification is attached as Annexure VIII. 12. The project proponent shall ensure that no vehicle during construction/operation phase enter the project premises without valid “Pollution Under Control” certificate from competent Authority. Status It is being ensured that all the vehicles hired during construction have PUC certificates. The same will be followed during operation phase.

M/s Greatvalue HPL Infratech Pvt. Ltd.