The World Bank Report No: ISR8173
Implementation Status & Results Ethiopia ET: Agricultural Growth Program (P113032)
Operation Name: ET: Agricultural Growth Program (P113032) Project Stage: Implementation Seq.No: 4 Status: ARCHIVED Archive Date: 12-Nov-2012 Country: Ethiopia Approval FY: 2011
Public Disclosure Authorized Product Line:IBRD/IDA Region: AFRICA Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key Dates Board Approval Date 30-Sep-2010 Original Closing Date 30-Sep-2015 Planned Mid Term Review Date 01-May-2013 Last Archived ISR Date 28-Mar-2012 Public Disclosure Copy Effectiveness Date 16-Feb-2011 Revised Closing Date 30-Sep-2015 Actual Mid Term Review Date
Project Development Objectives ET: Agricultural Growth Program (P113032) Project Development Objective (from Project Appraisal Document) The PDO is to increase agricultural productivity and market access for key crop and livestock products in targeted woredas with increased participation of women and youth. Has the Project Development Objective been changed since Board Approval of the Program?
Public Disclosure Authorized Yes No Public Disclosure Authorized Public Disclosure Copy
Page 1 of 8 Public Disclosure Authorized The World Bank Report No: ISR8173
Component(s)
Component Name Component Cost 1.1 Institutional Strengthening and Development 36.70 1.2 Scaling Up Best Practices 28.20 1.3 Market and Agribusiness Development 50.80 2.1 Small-scale Agricultural Water Development and Management 80.30 2.2 Small-scale Market Infrastructure Development and Management 51.10 3.1 AGP Management at the Federal, Regional, Zonal, and Woreda levels 11.40 3.2 Monitoring and Evaluation 6.70 1.1 Institutional Strengthening and Development 36.70 Public Disclosure Copy 1.2 Scaling Up Best Practices 28.20 1.3 Market and Agribusiness Development 50.80 2.1 Small-scale Agricultural Water Development and Management 80.30 2.2 Small-scale Market Infrastructure Development and Management 51.10 3.1 AGP Management at the Federal, Regional, Zonal, and Woreda levels 11.40 3.2 Monitoring and Evaluation 6.70
Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating
Implementation Status Overview The first full year of implementation (Ethiopian Fiscal Year 2004 (July 2011 - July 2012)) has been completed. Implementation progress has been variable across components and activities, and across regions and woredas (districts). Overall, the ambitious targets set for the year were only partially met, signaling the need for more realistic targets in coming years and addressing key implementation bottlenecks, which include local capacity of implementation agencies, procurement, technical review and quality of investments, and coordination between components and implementation agencies. However, it should be noted that there was an acceleration in implementation towards the end of the FY, and evidence that capacity and local commitment to project implementation is growing. The EFY Annual Work Plan and Budget has been approved and the next Joint Review and Implementation Support mission is scheduled to be completed by end of October 2012. Overall Implementation Progress is rated Moderately Satisfactory, i.e., satisfactory with moderate shortcomings.
Locations Country First Administrative Division Location Planned Actual Ethiopia SSNPR Sidama Awraja Public Disclosure Copy Ethiopia Oromia Regional State Jarso
Page 2 of 8 The World Bank Report No: ISR8173
Country First Administrative Division Location Planned Actual Ethiopia Oromia Regional State Giyon
Ethiopia SSNPR Guraghe Zone
Ethiopia Oromia Regional State Arsi Kifle Hager
Ethiopia Oromia Regional State Oromiya Kilil
Ethiopia SSNPR Southern Nations, Nationalities, and People's Regional State Ethiopia Oromia Regional State Limmu Sakka Public Disclosure Copy Ethiopia Not Entered Decha
Ethiopia Oromia Regional State Hidabu Abote
Ethiopia Oromia Regional State Yaya Gulelena Debre Liban
Ethiopia Oromia Regional State Dendi
Ethiopia Oromia Regional State Ambo
Ethiopia Oromia Regional State Becho
Ethiopia Oromia Regional State Wonchi
Ethiopia Oromia Regional State Ada'a Chukala
Ethiopia Oromia Regional State Gimbichu
Ethiopia Oromia Regional State Diga Leka
Ethiopia Oromia Regional State Guduru
Ethiopia Oromia Regional State Gechi
Ethiopia Oromia Regional State Bedele
Ethiopia Oromia Regional State Didessa
Ethiopia Oromia Regional State Gomma
Ethiopia Oromia Regional State Gera
Ethiopia Oromia Regional State Sherka Public Disclosure Copy Ethiopia Oromia Regional State Munesa
Page 3 of 8 The World Bank Report No: ISR8173
Ethiopia Oromia Regional State Adaba
Ethiopia Oromia Regional State Dodola
Ethiopia Oromia Regional State Kofele
Ethiopia Oromia Regional State Sinanana Dinsho
Ethiopia Oromia Regional State Gaserana
Ethiopia Oromia Regional State Agarfa
Ethiopia Oromia Regional State Walmara Public Disclosure Copy Ethiopia Tigray Regional State Alamata
Ethiopia Tigray Regional State Raya Azebo
Ethiopia Tigray Regional State Ofla
Ethiopia Tigray Regional State Endamehoni
Ethiopia Tigray Regional State Tsegede
Ethiopia Tigray Regional State Wolqayt
Ethiopia Tigray Regional State Kafta Humera
Ethiopia Tigray Regional State Tahtay Adiyabo
Ethiopia The State of Amhara Jabi Tehnan
Ethiopia The State of Amhara Bahir Dar Zuria
Ethiopia The State of Amhara Dejen
Ethiopia The State of Amhara Enemay
Ethiopia The State of Amhara Ankesha
Ethiopia The State of Amhara Guangua
Ethiopia The State of Amhara Dangila
Ethiopia The State of Amhara Metemma
Ethiopia The State of Amhara Qwara Public Disclosure Copy Ethiopia The State of Amhara Alefa
Page 4 of 8 The World Bank Report No: ISR8173
Ethiopia The State of Amhara Dera
Ethiopia The State of Amhara Efratana Gidim
Ethiopia The State of Amhara Antsokiyana Gemza
Ethiopia The State of Amhara Kewet
Ethiopia The State of Amhara Termaber
Ethiopia Not Entered Chena
Ethiopia Not Entered Enemorina Eaner Public Disclosure Copy Ethiopia Not Entered Shebedino
Ethiopia Not Entered Bule
Ethiopia Not Entered Yem
Ethiopia Not Entered Basketo
Ethiopia Not Entered West Shewa
Ethiopia Oromia Regional State East Shewa Zone
Ethiopia Oromia Regional State East Wellega Zone
Ethiopia The State of Amhara West Gojam
Ethiopia The State of Amhara East Gojam
Ethiopia The State of Amhara Awi
Ethiopia The State of Amhara North Gonder
Ethiopia SSNPR Siltie Zone
Ethiopia Not Entered Dawuro
Not Entered Not Entered Not Entered
Ethiopia Not Entered Gedeo
Results
Public Disclosure Copy Project Development Objective Indicators
Page 5 of 8 The World Bank Report No: ISR8173
Indicator Name Core Unit of Measure Baseline Current End Target Percentage increase in agricultural yield Percentage Value 9.90 11.50 (basket crops and livestock products). Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 Comments Value from 'rapid' baseline, to No further survey was be updated. undertaken since rapid baseline. Percentage increase in total real value of Number Value 7126.00 8731.00 marketed agricultural products (including Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 livestock) per household (in ETB). Comments Value from 'rapid' baseline, to No further survey was be updated. undertaken since rapid Public Disclosure Copy Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Farmers satisfied with quality of extension Percentage Value 79.00 87.00 services provided. Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 Comments No further survey was undertaken since 'rapid baseline'. Farm households who are members of Percentage Value 36.00 40.00 functional farmer organizations. Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 Comments No further survey was undertaken since 'rapid baseline'. Farm households with innovative best practices Number Value 0.00 126.00 (in 1000). Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 Comments No survey was undertaken yet. Sub-projects fully operational and sustainably Number Value 0.00 50.00 managed 2 years after initial investment (in Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 1000). Comments No survey was undertaken yet. Sales value of key selected value chain Percentage Value commodities supported at the end-of-the-value- Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 chain. Comments Baseline not yet available. No survey was undertaken yet.
Public Disclosure Copy Farmers benefiting from the investments of Number Value 0.00 72.00 sub-component 2.1 (in 1000). Date 31-Mar-2010 15-Nov-2010 30-Sep-2015
Page 6 of 8 The World Bank Report No: ISR8173
Comments Implementation has not yet started. Infrastructure (for agricultural water) used 1 Percentage Value 0.00 80.00 year after the investment is completed. Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 Comments Implementation has not yet started. Area under irrigation (percent of cultivated Percentage Value 4.50 6.10 land) Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 Comments No further survey was undertaken since 'rapid
Public Disclosure Copy baseline'. Increase in areas treated under sustainable Percentage Value 45.00 land management (in hectares). Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 Comments Baseline not yet available. No further survey was undertaken since 'rapid baseline'. Decrease in time for farmers to travel to Percentage Value 52.00 49.00 nearest market center. Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 Comments Users satisfied with the quality of market Percentage Value 66.20 76.00 infrastructure (roads and markets). Date 31-Mar-2010 30-Sep-2015 Comments No further survey was undertaken since 'rapid baseline'. Market infrastructure (roads and markets) Percentage Value 0.00 80.00 sustainably managed one year after the Date 31-Mar-2010 15-Nov-2010 30-Sep-2015 investment is completed. Comments
Data on Financial Performance (as of 23-May-2012)
Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P113032 IDA-47830 Effective 30-Sep-2010 19-Oct-2010 16-Feb-2011 30-Sep-2015 30-Sep-2015 P113032 IDA-H6000 Effective 30-Sep-2010 19-Oct-2010 16-Feb-2011 30-Sep-2015 30-Sep-2015 P127507 TF-11306 Effective 15-Feb-2012 15-Feb-2012 15-Feb-2012 30-Sep-2015 30-Sep-2015
Public Disclosure Copy P113032 TF-99729 Effective 12-Jul-2011 18-Jul-2011 18-Jul-2011 30-Sep-2015 30-Sep-2015
Disbursements (in Millions)
Page 7 of 8 The World Bank Report No: ISR8173
Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P113032 IDA-47830 Effective USD 108.40 108.40 0.00 19.68 90.16 18.00 P113032 IDA-H6000 Effective USD 41.60 41.60 0.00 11.78 30.46 28.00 P127507 TF-11306 Effective USD 50.00 50.00 0.00 1.84 48.16 4.00 P113032 TF-99729 Effective USD 6.20 15.48 0.00 11.30 4.18 73.00
Disbursement Graph Public Disclosure Copy
Key Decisions Regarding Implementation Key decisions: annual planning cycle (starting from local level) to commence earlier to ensure timeliness; quality enhancement to be made a priority, including continued support for technical review of small scale infrastructure design; institutional arrangements in place to improve coordination between components and implementing agencies.
Restructuring History There has been no restructuring to date.
Related Projects P127507-Agricultural Growth Project - Additional Financing Public Disclosure Copy
Page 8 of 8