PRE FEASIBILITY REPORT

TABLE OF CONTENTS

S. No Particulars Page No. 1 Project Background 2 2 Project Description 3 3 Site Analysis 8 4 Rehabilitation & Resettlement 9 5 Proposed Infrastructure 9 6 Project Schedule & Cost Estimates 10 7 Analysis of proposal 10

1

1.0 PROJECT BACKGROUND

Jammu airport is located near Satwari, 6 km from Tawi railway station, 110 km away from Pathankot airport and 1 km from National Highway no. 1. There is consistent demand from all stakeholders to extend the runway to meet out the safety requirement. As per DGCA there are two safety issues at Jammu Airport and theses are pertaining to short runway length and provision of RESA for RWY 36. Due to vehicular traffic on civil road at a distance of 80 feet from runway 18 the threshold has been further displaced by 200 feet. The declared distances at Jammu Airport are as follows:

RWY TORA TODA ASDA LDA 36 6700 ft 6700 ft 6700 ft 6700 ft 18 6700 ft 6900 ft 6900 ft 6500 ft

Initially scope of work was prepared in year 1999 for extension of runway at Jammu Airport to cater for operation of A-321/B-737-800 type of aircraft. It was planned to extend runway 18 by 700ft. (i.e. towards runway 36 side) and runway 36 by 1300ft. (i.e. towards runway 18 side).

The extension of runway 18 by 700ft. was completed in year 2001-02; the extension of runway 36 by 1300ft could not be taken up due to non-availability of land (army land) & shifting of public roads and irrigation channels passing through the proposed extension area. Out of transfer of approx. 17.05 acres of land belonging to Army, till date army has given working permission to work in area of approx. 2.51 Acre. Further the handing over process is nearing completion and the board proceedings for final land transfer shall be completed by 30th june, 2018 as confirmed by DEO, jammu.

Hence to meet out the safety standards there is urgent need to extend the runway.

1.1 Project Proponent

Airports Authority of India (AAI) was constituted by an Act of Parliament and came into being on 1st April 1995. Currently, it manages a total of 125 Airports, which include 11 International Airports, 08 Customs Airports, 81 Domestic Airports and 25 Civil Enclaves at Defense Airfields. AAI also provides Air Traffic Management Services (ATMS) over entire Indian Air Space and adjoining oceanic areas with ground installations at all Airports and 25 other locations to ensure safety of Aircraft operations.

Purpose of Resubmission

TOR was accorded by MoEF&CC vide its letter no: F.No.10-19/2015-IA.III, dated: 14 th August, 2015. As per referred TORs, the validity of TORs is upto 14 th August, 2018. The purpose of resubmission is for extension of validity period of TOR for one more year ie; upto 14 th August, 2019 and to amend the TOR as it was observed the presence of Ramnagar Rakh Sanctuary and 4 archeological sites namely – Bahu fort,

2

Pirmitha Tomb at Pirmitha & Mast Garh Shahi, Masjid and Mubarak mandi heritage complex within study area representing 10 km study area.

1.2 Need for the Project

Jammu airport is located near Satwari, 6 km from Jammu Tawi railway station, 110 km away from Pathankot airport and 1 km from National Highway no. 1. There is consistent demand from all stakeholders to extend the runway to meet out the safety requirement. As per DGCA there are two safety issues at Jammu Airport and theses are pertaining to short runway length and provision of RESA for RWY 36. Due to vehicular traffic on civil road at a distance of 80 feet from runway 18 the threshold has been further displaced by 200 feet. The declared distances at Jammu Airport are as follows:

RWY TORA TODA ASDA LDA 36 6700 ft 6700 ft 6700 ft 6700 ft 18 6700 ft 6900 ft 6900 ft 6500 ft

Initially scope of work was prepared in year 1999 for extension of runway at Jammu Airport to cater for operation of A-321/B-737-800 type of aircraft. It was planned to extend runway 18 by 700ft. (i.e. towards runway 36 side) and runway 36 by 1300ft. (i.e. towards runway 18 side). The extension of runway 18 by 700ft. was completed in year 2001-02; the extension of runway 36 by 1300ft could not be taken up due to non-availability of land (army land) & shifting of public roads and irrigation channels passing through the proposed extension area. Out of transfer of approx. 17.05 acres of land belonging to Army, till date army has given working permission to work in area of approx. 2.51 Acre. Further the handing over process is nearing completion and the board proceedings for final land transfer shall be completed by 30th june, 2018 as confirmed by DEO, jammu

Hence to meet out the safety standards there is urgent need to extend the runway.

2.0 PROJECT DESCRIPTION

2.1 Type of Project

The proposed project involves extension of runway to cater to the operations of critical aircraft of “C” category (i.e. B-321).

2.2 Location

Proposed expansion of Jammu airport will be within the existing airport premises. The airport is located within the Jammu city. The airport is located at latitude 32 041’18” N and longitude 74050’20”E. The proposed site falls in Survey of India Toposheet No. 43 L/9, 43 C/10, 43 L/13 and 43L/14. The 10 km radius study area map is given in Figure-1.

3

2.3 Details of Alternate Site

The proposed project involves extension of runway to cater to the operations of critical aircraft of “C” category. Hence, no alternative sites were examined.

2.4 Existing Project Features

Existing facilities includes:

Sr. No Particulars Details 1 Runway Orientation 18 and 36 end Dimension 2042 m x 45 m Apron 137 m x 76 m (PCN 38R/C/W/U) having capacity to park 03 no’s AB 320 + 150mx90m for another 3 nos. parking bays. Helipad 52mx56.50m 2 Terminal Building Plinth Area 14500 sqm Pax Capacity 360 Arrival + 360 Departure VIP Room Available Car Parking Available 3 Runway Light Facilities Available 4 Approach Lights Runway 36 Cat-I Lighting System Runway 18/36 PAPI 5 Navigation Aids DVOR Available DME Available 6 Landing Aids Visual & Instrumental Runway 36 Instrumental Approach Runway 18 Visual Approach 7 Residential Colony Available

4

5

FIGURE-1 STUDY AREA MAP

2.5 Proposed facilities

The proposed extension of runway involves the following civil works:

• Extension of runway 36 (i.e. towards 18 side) by 396 m x 45 m to make total length of 2438 m;

• Strengthening of the extended portion of the runway to handle critical aircraft of “C” category (i.e.B-321);

• Construction of new turn pad after extension of runway on the left hand side and the dimension of turn pad should be cater for maneuvering of D category of aircraft;

• Construction of blast pads of dimension 60 m x 60 m at the extreme of runway after extension;

• Provision of runway shoulders of 7.5 m width on either side on the extended portion of runway;

• Provision of RESA of dimension 240 m x 150 m;

• The profile correction of existing runway surface for aerodrome reference code 4C;

• Leveling and grading of runway strip on the extended portion, RESA & further grading up to boundary wall as per transitional surface & drainage requirement;

• Provision of visual markings on the extended portion of the runway and turn pad;

• 2-3 irrigation canals passing through the site have been diverted.

• Construction of boundary wall to be taken up at places where the area has been left uncovered in the area available for runway extension and or the land be handed over by army along with to provide appropriate number of security huts and perimeter lighting;

• Construction of perimeter road of 5 m width and of sufficient strength to with stand the crash fire tender, along the boundary wall and also on the land to be handed over by army;

• Demolition of boundary wall belonging to IAF behind runway 18;

6

• Provision of perimeter drainage in the runway extension area and pipe culvert to cross the runway for drainage work;

• Relocation of localizer and mounting of NF antenna in such a manner that the rod is frangible material and the platform flush with the surface along with dismantling of existing localizer building and boundary wall; and

• Leveling and grading for operational area.

2.5.1 Electrical/Electronic/Mechanical Works

• Provision of high intensity runway edge lights on the extended portion and relocation of threshold & runway end lights;

• Simple approach ligting system for runway 18;

• Relocation of PAPI units on Runway 18 approach;

• Relocation of lighted windsock. Provision of obstruction lights on significant identified obstacles in coordination with ATM Dte

• Provision of mandatory/information signages (airside) to be provided;

• Augmentation of power supply, if required;

• Electrical works such as providing Internal Electrical Installations, Air conditioning equipments and power supply to new glide path and localizer buildings;

• Provision of MIRL turning pad lights for the new turning pad on runway 18 beginning;

• Provision of perimeter lighting on the perimeter road on the acquired land and on the land to be handed over by Army to AAI;

• Provision of security huts along the perimeter road to be constructed on the acquired land.

2.5.2 CNS Works

• Trans installation of LLZ after extension of runway and ascertaining the location of landing threshold with ATM Dte;

• Construction of huts for housing LLZ equipment including electrical and air conditioning equipments;

• Leveling and grading in front of the proposed LLZ area;

• Calibration of LLZ after completion of all works; and

• Installation of advanced lighting arrestor system in LLZ.

7

2.6 Water & Power Requirements

Water Requirement

The total water requirement for the entire airport is about 193 KLD. Out of this, about 30% is provided by Jammu Municipal Corporation (JMC) and the balance water requirement is met through two tube wells of AAI existing within the airport.

As part of the extension of the runway, only construction water will be required.

Power Requirement

It is estimated that about 700 KVA of power is being consumed. The power is taken from Power Distribution Department, J&K.

Existing standby source

• NDB : 2 x 380 KVA; and • Radar: 1 x 250 KVA and 1 x 125 KVA.

The fuel consumption is about 120 liters per day. The DG facility has a total storage capacity of 2000 liters.

2.7 Wastewater Generation & management

The wastewater generation mainly consists of sanitary waste, sewage from airport terminal, flight kitchen, effluent from the workshop etc. The sewage and sanitary waste from the buildings and airport terminal will be treated in Sewage Treatment Plant (STP) comprising primary, secondary and tertiary treatment facilities. The treated wastewater from the STP will be used for air conditioning, cooling water make-up and green belt development.

The 200 KLD of wastewater treatment plant have been operational at Jammu Airport. The entire wastewater that is generated from the airport is recycled and reused for non potable purposes.

2.8 Solid Waste Management

Solid waste generated from the proposed airport mainly comprises of food waste and garbage waste. Further, small quantities of sludge from STP, medical waste and other waste will be generated. Collection and handling of domestic solid waste would be done in line with the provisions of the Municipal Solid Waste Rules 2000 (as amended).

8

3.0 SITE ANALYSIS

3.1 Connectivity

The Jammu airport is located approximately at a distance of 3.5 km from Jammu railway station.

3.2 Land form, Land use & Land ownership

The total land required for developing the airport is about 152 acres, out of which about 17 acres of land need to be acquired from IAF. The remaining 135 acres of land is already under possession of Airports Authority of India (AAI). Presently the airport is in operation and currently operates about 30 operations per day (15 landings and 15 take-offs.

3.3 Topography

The airport facilities are already existing. There will not be any expansion in the passenger capacity and passenger terminal building.

3.4 Proposed Land use pattern

The land use pattern remains same.

3.5 Existing Infrastructure

Existing infrastructure details are given in section-2.4.

3.6 Social Infrastructure Available

The existing social infrastructure in the Jammu which is located at about 4.0 km from the site is:

• Hospital with ambulance; • Banks; • Post office; • Bus station; • Fire station; • Secondary school; • Police station; • Shopping complex; • Sports infrastructure (Stadium & Camps etc); • Community halls; • Cinema halls; and • Primary health care centres.

4.0 REHABILITATION & RESETTLEMENT 9

No resettlement and rehabilitation is involved as the proposed extension would take place within the existing airport premises.

5.0 PROPOSED INFRASTRUCTURE

The proposed project involves extension of runway to cater to the operations of critical aircraft of “C” category.

The details are discussed in Section-2.5.

6.0 PROJECT SCHEDULE & PRELIMINARY COST ESTIMATES

The approved cost of work for Development of Jammu Airport is worked out as Rs. 76.99 Crores (approx.)

7.0 ANALYSIS OF PROPOSAL

Jammu Airport serves the city of Jammu, in the northernmost Indian state of Jammu and Kashmir. Airports Authority of India operates the airport, which hosts five airlines operating domestic-only service to destinations in north and western India . There will be an increase in air traffic and more aircrafts would land if there were the required conveniences.

After completion of the extension, Jammu will be well connected to other cities and other states and will increase the tourist flow in this region.

10