Public Disclosure Authorized

Procurement of Goods 16.91 Organisation: Water Resources Bureau 17.3499 Project/Programme: MDTF (IDA/DFID) REVISED!! Loan #:

Public Disclosure Authorized Draft Bid Documents, Spec Proc BASIC DATA including specs and Notice Bidding Period Bid Evaluation Contract Finalization Contract Implementation

quantities, draft SPN Advert

Date

S. NoS.

Contract

Signature

of

of

Description*

Lot

Date

Date

US$

Date

Plan vs. Actual vs. Plan Final

Award

Goods Opening

Arrival

Pre-or Post Qual. Post Pre-or

Number

Package

in USin $ Contract

Number

Gateway Opening

Let of Credit

No-objection

Inspection

Prior or Post Review Postor Prior

Procurement Method Procurement

Submission Acceptance

BidClosing-

No-objection BidRptEval

byEx Agency

National Press National Actual vs. Plan

On-line UNDB On-line

Estimated Amount Estimated

Bid Invitation Date Bid Invitation

Prep & Submission&Prep Contract Amount Contract in List of Contracts A Regional Level

Public Disclosure Authorized Plan 20-Aug-10 NA NA 17-Sep-10 17-Oct-10 1-Nov-10 NA Plan 15-Sep-10 27-Nov-10 NA 5-Apr-11 15-Apr-11 Procurement of 38 OWRB/EME/ MDTF/01/1 1 441,000.00 NCB Post post Generators /2010 Actual 10-Sep-10 31-Oct-10 29-Dec-10 17-Jan-11 Actual 15-Sep-11 31-Oct-11 NA 28-Feb-12 29-Mar-12

Plan 20-Aug-10 NA NA 17-Sep-10 17-Oct-10 1-Nov-10 NA Plan 17-Nov-10 27-Nov-10 NA 5-Apr-11 15-Apr-11 Procurement of 41 OWRB/EME/ MDTF/02/ 2 487,877.00 NCB Post post Submersible/Surface Pumps 1/2010 Actual 10-Sep-10 31-Oct-10 29-Dec-10 17-Jan-11 Actual 319,092.04 27-Jan-11 5-Feb-11 NA 10-Aug-11 15-Sep-11

Plan 1-Apr-11 NA NA 16-Apr-11 21-May-11 31-May-11 NA Plan 17-Nov-10 27-Nov-10 NA 5-Apr-11 15-Apr-11 Procurement of 34 OWRB/EME/ MDTF/01/ 2010- Rev. Plan Rev.plan 15-Feb-12 NA 15-May-12 14-Jun-12 3 431,126.40 NCB Post post Generators Lot 1 Revised NA 11-Oct-12 31-Oct-12 Actual 12-Oct-11 NA NA 15-Oct-11 22-Nov-11 27-Dec-11 Actual 477,435.03 24-Jan-12 30-May-12 27-Sep-12 7-Oct-12

Plan 1-Apr-11 NA NA 16-Apr-11 21-May-11 31-May-11 NA Plan 17-Nov-10 27-Nov-10 NA 5-Apr-11 15-Apr-11 Procurement of 40 OWRB/EME/ MDTF/02/2010- 4 345,823.32 NCB Post post Revised 19-Jul-12 29-Jul-12 Public Disclosure Authorized Submersible/Surface Pumps Lot 2 Actual 12-Oct-11 15-Oct-11 22-Nov-11 27-Dec-11 Actual 312,231.77 24-Jan-12 20-Feb-12

Office furnitures and Plan 1-Oct-10 NA NA 16-Oct-10 26-Oct-10 1-Nov-10 NA Plan 15-Nov-10 17-Nov-10 NA 24-Nov-11 25-Nov-11 5 OWRB/MDTF/ OF/01/ 2010 13,701.03 NS Post post equipments Actual 10-Sep-11 19-Sep-11 30-Sep-11 8-Oct-11 Actual 13,701.03 15-Oct-11 18-Nov-11 30-Dec-10 10-Jan-11

Procurment of surveying Plan 1-Oct-10 NA NA 16-Oct-10 26-Oct-10 1-Nov-10 NA Plan 15-Nov-10 17-Nov-10 NA 24-Nov-10 25-Nov-10 6 OWRB/MDTF/ SE/03/ 2010 28,176.82 NS Post post equipment (2 total station) Actual 17-Oct-10 19-Oct-10 23-Nov-11 20-Dec-11 Actual 22-Dec-11 25-Dec-11 30-Dec-10

Office furnitures & Plan 1-Mar-11 NA NA 15-Mar-11 15-Apr-11 25-Apr-11 NA Plan 27-Apr-11 7-May-11 NA 6-Aug-11 10-Aug-11 7 OWRB/MDTF/ OF/02/ 2010 4,554.00 NS Post post equipments Actual 20-Apr-11 4-May-11 5-Jun-11 15-Jun-11 Actual 4,554.00 20-Jun-11 30-Jun-11 26-Jul-11 28-Jul-11 B Woreda Level Plan 1-Oct-10 NA NA 16-Oct-10 26-Oct-10 1-Nov-10 NA Plan 15-Nov-10 17-Nov-10 NA 24-Nov-10 25-Nov-10 1 Pocket GPS (84 units) OWRB/MDTF/ GPS/07/ 2010 61,596.69 NCB Post post Actual 1-Oct-10 19-Oct-10 19-Dec-10 20-Jan-11 Actual 61,145.40 23-Apr-11 25-Apr-11 15-Aug-11 16-Sep-11

Plan 1-Mar-11 NA NA 15-Mar-11 15-Apr-11 25-Apr-11 NA Plan 27-Apr-11 7-May-11 NA 6-Aug-11 10-Aug-11 2 Hand Pumps (400) OWRB/HP/ MDTF/04/ 2010 340,731.17 NCB Post post Actual 4-Nov-11 Actual 230,146.58 7-Nov-11 14-Nov-11 13-Mar-12 12-Apr-12

Water Qaulity Test Kits (84 OWRB/MDTF/WQTK/06/201 Plan 1-Oct-10 NA NA 30-Oct-10 30-Nov-10 15-Dec-10 NA Plan 1-Jan-11 1-Jan-11 NA 11-Apr-11 20-Apr-11 3 149,024.25 NCB Post post units) 0 Actual 1-Oct-10 19-Oct-10 19-Dec-10 20-Jan-11 Actual 104,534.61 25-Apr-11 25-Apr-11 21-Aug-11 25-Sep-11

Maintenance Tool Kits (Pipe Plan 1-Jul-11 NA NA 15-Jul-11 15-Aug-11 25-Aug-11 NA Plan 27-Aug-11 23-Feb-12 NA 23-Apr-12 23-May-12 4 Wrench, Cutter, Treader, OWRB/MDTF/MTK/05/2010 248,373.74 NCB Post post Revised 30-May-12 11-Oct-12 31-Oct-12 …etc) 84 sets Actual 5-Aug-11 13-Oct-11 21-Nov-11 27-Dec-11 Actual 97,992.50 24-Jan-12 20-Feb-12 19-Jun-12 29-Jun-12 Procurement Plan Works Country/Organization: Oromia National Rgional State Water, Mineral & Energy Bureau 1USD= 17.3499 birr Project/Programmed: IDA-DFID (MDTF) REVISED!!! Loan #: Draft Bid Documents, Spec Proc Basic Data including specs and Notice Bidding Period Bid Evaluation Contract Finalization Contract Implementation quantities, draft SPN Advert

Description*

Package

Number

Lot

Cost Cost

Date Date Date

US US $ Date

Final

Final

Plan vs. Actual Plan vs. Actual

in US$

Prep & Prep Award

Review

Method

Number

Contract

Contract

Opening

Gateway Advance Payment

Pre/Post

Signature

Estimated

Amount in Substantial

Acceptance

Submission Submission

Completion

Bid Closing-

Prior or Post Bid Eval Rpt

of Quantities Procurement No-objection No-objection Mobilization

Qualification

by Ex Agency

National Press

On-line UNDB

Lump sum or Bill Contract Amount Bid Invitation Date List of Contracts I. Deep Wells drilling (60 DWs) A. Completed projects (26 DWs) 4 - 7 wks 1 - 1.5 wks 1.5 - 2 wks 1.5 - 2 wks 6 to 12 wks 1.5 - 3 wks 1 wk 1.5-3 wks Plan 8-Apr-09 16-Apr-09 26-Apr-09 10-Jun-09 15-Jul-09 28-Jul-09 Plan 20-Jul-09 27-Jul-09 9-Sep-09 9-Sep-09 Drilling of 6 deep wells (Borena & Guji) ORWB/MDTF/DW/001/ 2008 BOQ NCB 155,096.01 Post Post Actual 11-Feb-09 19-Feb-09 1-Mar-09 30-May-09 25-Sep-09 30-Sep-09 Actual 96,967.37 07-Oct-09 20-Oct-09 20-Dec-10 20-Dec-11

Plan 8-Apr-09 16-Apr-09 26-Apr-09 10-Jun-09 15-Jul-09 28-Jul-09 Plan 20-Jul-09 27-Jul-09 9-Sep-09 9-Sep-09 Drilling of 2 deep wells (East & West Hararge) ORWB/MDTF/DW/002/ 2008 BOQ NCB 51,698.67 Post Post Actual 11-Feb-09 19-Feb-09 1-Mar-09 30-May-09 25-Sep-09 30-Sep-09 Actual 52,904.28 7-Oct-10 20-Oct-09 16-Jan-11 16-Jan-12

Plan 2-Nov-09 10-Nov-09 20-Nov-09 21-Dec-09 1-Jan-10 14-Jan-10 Plan 8-Jan-10 15-Jan-10 15-Apr-10 15-Apr-11 Drilling of 5 deep wells (S.W Showa & E/Wollega) ORWB/MDTF/RDW/001/ 2009 BOQ NCB 103,397.34 Post Post Actual 25-Nov-09 3-Dec-09 13-Dec-09 13-Jan-10 15-Jan-10 1-Feb-10 Actual 75,441.76 8-Feb-10 18-Feb-10 18-Jun-10 18-Jun-11

Plan 15-Mar-09 23-Mar-09 2-Apr-09 17-May-09 21-Jun-09 4-Jul-09 Plan 20-Jul-09 27-Jul-09 9-Sep-09 9-Sep-10 Drilling of 4 Deep wells (Arsi & Bale) ORWB/MDTF/DW/001/ 2008 BOQ NCB 77,548.01 Post Post Actual 11-Feb-09 19-Feb-09 1-Mar-09 30-May-09 25-Sep-09 30-Sep-09 Actual 111,447.88 7-Oct-10 17-Oct-10 14-Feb-11 14-Feb-12

Plan 15-Mar-09 23-Mar-09 2-Apr-09 17-May-09 21-Jun-09 4-Jul-09 Plan 26-Jun-09 3-Jul-09 2-Aug-09 2-Aug-10 Drilling of one deep well in Akaki (Abasamu'el) ORWB/MDTF/DW/001/ 2007 BOQ NCB 25,849.34 Post Post Actual 16-Feb-09 24-Feb-09 6-Mar-09 5-Apr-09 30-Apr-09 12-May-09 Actual 25,327.03 19-May-09 29-May-09 26-Sep-09 26-Sep-10

Plan 30-Aug-10 15-Sep-10 25-Sep-10 25-Oct-10 10-Nov-10 25-Nov-10 Plan 30-Nov-10 7-Dec-10 7-Jun-11 6-Jun-12 Drilling of 3 deep wells (W/Shoa, Nono & Chelia) OWRB/MDTF/DW/04/1/ 2010 BOQ NCB 48,415.26 Post Post Actual 20-Jul-10 25-Jul-10 26-Aug-10 26-Oct-10 10-Nov-10 15-Nov-10 Actual 769440.76 6-Dec-10 31-Dec-10 10-Jan-11 10-Jan-12

Plan 30-Aug-10 15-Sep-10 25-Sep-10 25-Oct-10 10-Nov-10 25-Nov-10 Plan 30-Nov-10 7-Dec-10 7-Jun-11 6-Jun-12 Drilling of 2 deep wells (Guji) OWRB/MDTF/DW/06/1/2/ 2010 BOQ NCB 48,415.26 Post Post Actual 20-Jan-11 25-Jan-11 5-May-11 27-May-11 1-Aug-11 10-Aug-11 Actual 41,163.64 27-May-11 22-Sep-11 8-Dec-11 8-Dec-11

Plan 30-Oct-10 15-Nov-10 25-Nov-10 25-Dec-10 10-Jan-11 25-Jan-11 Plan 30-Jan-11 7-Feb-11 7-Aug-11 1-Mar-12 Drilling of 1 deep well ( W/ Wellega, Kiltu Kara) OWRB/MDTF/DW/01/1/2010 BOQ NCB 24,207.63 Post Post Actual 20-Jan-11 25-Jan-11 12-Feb-11 14-Mar-11 30-Mar-11 16-May-11 Actual 32,661.96 23-May-11 28-Jun-11 9-Sep-11 8-Sep-12

Plan 8-Apr-09 16-Apr-09 26-Apr-09 10-Jun-09 15-Jul-09 28-Jul-09 Plan 20-Jul-09 27-Jul-09 15-Sep-09 15-Sep-10 Drilling of 2 deep wells (Jimma & West Wellega) OWRB/MDTF/DW&SW/ 01/ 2008 BOQ NCB 48,415.26 Post Post Actual 11-Feb-09 19-Feb-09 1-Mar-09 30-Mar-09 5-May-09 30-Apr-09 Actual 20012.10 07-May-09 9-Jun-09 12-May-11 11-May-12

B. Ongoing projects (30 DWs) Plan 30-Oct-10 15-Nov-10 25-Nov-10 25-Dec-10 10-Jan-11 Jan25,11 Plan 30-Jan-11 7-Feb-11 7-Aug-11 6-Aug-12 Drilling of 8 deep wells (Ilu Aba Bora & Jima) OWRB/MDTF/DW/02/ 2/2010 BOQ NCB 145,245.79 Post Post Actual 20-Jan-11 25-Jan-11 13-Feb-11 14-Mar-11 30-Mar-11 31-Mar-11 Actual 195,220.63 23-May-11 30-Jun-11 28-Oct-11 27-Oct-12

Plan 30-Aug-10 15-Sep-10 25-Sep-10 25-Oct-10 10-Nov-10 25-Nov-10 Plan 30-Nov-10 7-Dec-10 6-Apr-11 5-Apr-12 Drilling of 8 deep wells (Borena) OWRB/MDTF/DW/06/1/1/ 2010 BOQ NCB 193,661.06 Post Post Actual 20-Jan-11 25-Jan-11 5-May-11 27-May-11 1-Aug-11 10-Aug-11 Actual 207,007.16 15-Aug-11 01-Sep-11 20-Jun-11 19-Jun-12

Plan 30-Aug-10 15-Sep-10 25-Sep-10 25-Oct-10 10-Nov-10 25-Nov-10 Plan 30-Nov-10 7-Dec-10 7-Jun-11 6-Jun-12 Drilling of 10 deep wells (N/Shoa, W/Shoa, OWRB/MDTF/DW/04/2/ 2010 BOQ NCB 217,868.69 Post Post Actual 20-Jan-11 25-Jan-11 12-Feb-11 14-Mar-11 30-Mar-11 31-Mar-11 Actual 375,646.68 23-May-11 28-Jun-11 26-Oct-11 25-Oct-12 SW/Shoa) Plan 30-Aug-10 15-Sep-10 25-Sep-10 25-Oct-10 10-Nov-10 25-Nov-10 Plan 30-Nov-10 7-Dec-10 7-Aug-11 6-Aug-12 Drilling of 4 deep ( & shallow) wells (W/Hararge & OWRB/MDTF/DW/02/3/ 2010 BOQ NCB 96,830.53 Post Post Actual 20-Jan-11 25-Jan-11 01-Dec.11 28-Dec-11 5-Jan-12 8-Jan-12 Actual 207,845.29 03-Feb-12 13-Feb-12 12-Jun-12 12-Jun-13 E/Hararge)

C. New (4DW) Plan 15-Apr-12 16-Apr-12 20-Apr-12 25-May-12 1-Jun-12 2-Jun-12 Plan 7-Jun-12 17-Jun-12 15-Oct-12 15-Oct-13 Drilling of 4 deep wells OWRB/MDTF/DW/01/2012 BOQ NCB 96,830.53 Post Post Revised 20-Jan-11 25-Jan-11 10-Aug-12 9-Sep-12 29-Sep-12 4-Oct-12 11-Oct-12 21-Oct-12 19-Jan-13 19-Jan-14 Actual II. Shallow Wells drilling & construction (270 SHW) A. Completed projects (163 SHWs) Plan 30-Aug-10 15-Sep-10 5-Oct-10 5-Nov-10 15-Nov-10 5-Dec-10 Plan 10-Dec-10 20-Dec-10 20-Jun-11 19-Jun-12 Drilling of 10 Shallow wells (IluAba Bora, Jima) OWRB/MDTF/SHW/01/1/ 2010 BOQ NCB 44,957.03 Post Post Actual 20-Jul-10 25-Jul-10 26-Aug-10 26-Oct-10 10-Nov-10 15-Nov-10 Actual 53,916.03 6-Dec-10 17-Dec-10 11-Oct-11 10-Oct-12

Plan 30-Aug-10 15-Sep-10 5-Oct-10 5-Nov-10 15-Nov-10 5-Dec-10 Plan 30-Nov-10 7-Dec-10 7-Jun-11 6-Jun-12 Drilling of 12 Shallow wells (Guji; Odo Shakiso) OWRB/MDTF/SHW/03/2/2010 BOQ NCB 69,128.51 Post Post Actual 20-Jul-10 25-Jul-10 26-Aug-10 26-Oct-10 10-Nov-10 15-Nov-10 Actual 69,712.27 6-Dec-10 29-Dec-10 15-Jul-11 14-Jul-12

Plan 30-Aug-10 15-Sep-10 5-Oct-10 5-Nov-10 15-Nov-10 5-Dec-10 Plan 30-Nov-10 7-Dec-10 7-Jun-11 6-Jun-12 Drilling of 9 Shallow wells (Guji; Girja, Dama) OWRB/MDTF/SHW/03/4 2010 BOQ NCB 40,461.33 Post Post Actual 20-Jul-10 25-Jul-10 26-Aug-10 26-Oct-10 10-Nov-10 15-Nov-10 Actual 58,584.30 6-Dec-10 31-Dec-10 21-Oct-11 20-Oct-12

Plan 15-Mar-09 23-Mar-09 2-Apr-09 17-May-09 21-Jun-09 22-Jun-09 Plan 20-Jul-09 27-Jul-09 15-Sep-09 15-Sep-10 Drilling of 7 shallow wells (Bako & Mida Kegn) OWRB/MDTF/DW&SW/01/2008 BOQ NCB 35,672.00 Post Post Actual 11-Feb-09 19-Feb-09 1-Mar-09 30-Mar-09 5-May-09 15-May-09 Actual 24,442.45 07-may-09 9-Jun-09 10-Jul-09 10-Jul-10

Plan 30-Aug-10 15-Sep-10 25-Sep-10 25-Oct-10 10-Nov-10 25-Nov-10 Plan 30-Nov-10 7-Dec-10 7-Jun-11 6-Jun-12 Drilling of 18 Shallow wells ( South West Shoa, OWRB/MDTF/SHW/06/2/ 2010 BOQ NCB 80,922.66 Post Post Actual 20-Jan-11 25-Jan-11 12-Feb-11 14-Mar-11 30-Mar-11 20-Apr-11 Actual 99,702.59 9-Jun-11 14-Jul-11 5-Nov-11 4-Nov-12 Woliso) Plan 30-Aug-10 15-Sep-10 25-Sep-10 25-Oct-10 10-Nov-10 25-Nov-10 Plan 30-Nov-10 7-Dec-10 7-Jun-11 6-Jun-12 Drilling of 18 Shallow wells ( SW/ West Shoa, OWRB/MDTF/SHW/06/1 2010 BOQ NCB 80,922.66 Post Post Actual 20-Jan-11 25-Jan-11 12-Feb-11 14-Mar-11 30-Mar-11 20-Apr-11 Actual 99,702.59 9-Jun-11 14-Jul-11 8-Oct-11 7-Oct-12 Ameya) Plan 30-Aug-10 15-Sep-10 5-Oct-10 5-Nov-10 15-Nov-10 5-Dec-10 Plan 10-Dec-10 20-Dec-10 20-Jun-11 19-Jun-12 Drilling of 23 Shallow wells (I/A/Bora, Jima) OWRB/MDTF/SHW/01/2/ 2010 BOQ NCB 94,409.77 Post Post Actual 20-Jan-11 25-Jan-11 12-Feb-11 14-Mar-11 24-Mar-11 20-Apr-11 Actual 170,811.11 9-Jun-11 14-Jul-11 18-Oct-11 17-Oct-12

Plan 30-Aug-10 15-Sep-10 25-Sep-10 25-Oct-10 10-Nov-10 25-Nov-10 Plan 30-Nov-10 7-Dec-10 7-Jun-11 6-Jun-12 Drilling of 20 Shallow wells (West Shoa; Nono) OWRB/MDTF/SHW/09/2/ 2010 BOQ NCB 89,914.06 Post Post Actual 20-Jan-11 25-Jan-11 12-Feb-11 14-Mar-11 30-Mar-11 20-Apr-11 Actual 96,739.09 24-May-11 09-Jun-11 15-Dec-11 14-Dec-12

Plan 30-Aug-10 15-Sep-10 5-Oct-10 5-Nov-10 15-Nov-10 5-Dec-10 Plan 30-Nov-10 7-Dec-10 7-Jun-11 6-Jun-12 Drilling of 13 Shallow wells (Guji - Liban, Adola & OWRB/MDTF/SHW/03/1 /2010 BOQ NCB 58,444.14 Post Post Actual 20-Jul-10 25-Jul-10 26-Aug-10 26-Oct-10 10-Nov-10 15-Nov-10 Actual 67,570.70 6-Dec-10 31-Dec-10 25-Nov-11 24-Nov-12 Wadera) Plan 30-Aug-10 15-Sep-10 5-Oct-10 5-Nov-10 15-Nov-10 5-Dec-10 Plan 30-Nov-10 7-Dec-10 7-Jun-11 6-Jun-12 Drilling of 21 Shallow wells (Mulo, Degem, Berek, OWRB/MDTF/SHW/05/1/ 2010 BOQ NCB 85,418.36 Post Post Actual 20-Jul-10 25-Jul-10 26-Aug-10 26-Oct-10 10-Nov-10 15-Nov-10 Actual 84,569.57 6-Dec-10 17-Dec-10 24-Jun-11 23-Jun-12 Gimbichu, Aleltu)

Plan 30-Aug-10 15-Sep-10 5-Oct-10 5-Nov-10 15-Nov-10 5-Dec-10 Plan 30-Nov-10 7-Dec-10 7-Jun-11 6-Jun-12 Drilling of 9 Shallow wells (Borena- , OWRB/MDTF/SHW/03/3/2010 BOQ NCB 40,461.33 Post Post Actual 20-Jan-11 25-Jan-11 12-Feb-11 14-Mar-11 30-Mar-11 15-Nov-10 Actual 85170.09 6-Dec-10 9-Jun-11 10-Sep-11 9-Sep-12 D/Dawa, B/Hora, , ) Plan 8-Apr-09 16-Apr-09 26-Apr-09 10-Jun-09 15-Jul-09 20-Jul-09 Plan 20-Jul-09 27-Jul-09 15-Sep-09 15-Sep-10 Drilling of 3 shallow wells (Jimma, E & W OWRB/MDTF/DW&SW/ 01/ 2008 BOQ NCB 13,487.11 Post Post Actual 11-Feb-09 19-Feb-09 1-Mar-09 30-Mar-09 5-May-09 15-May-09 Actual 12016.44 07-May-09 9-Jun-09 20-May-10 20-May-11 Wellega)

B.Ongoing (85 shallow Wells) Plan 30-Aug-10 15-Sep-10 25-Sep-10 25-Oct-10 10-Nov-10 25-Nov-10 Plan 30-Nov-10 7-Dec-10 7-Apr-12 7-Apr-13 Drilling of 20 Shallow wells ( South West Shoa; OWRB/MDTF/SHW/06/3/2010 BOQ NCB 89,914.06 Post Post Actual 20-Jan-11 25-Jan-11 12-Feb-11 14-Mar-11 30-Mar-11 20-Apr-11 Actual 121,488.42 27-May-11 9-Jun-11 7-Oct-11 6-Oct-12 Goro, Wonchi & Tole) Draft Bid Documents, Spec Proc Basic Data including specs and Notice Bidding Period Bid Evaluation Contract Finalization Contract Implementation quantities, draft SPN Advert

Description*

Package

Number

Lot

Cost Cost

Date Date Date

US US $ Date

Final

Final

Plan vs. Actual Plan vs. Actual

in US$

Prep & Prep Award

Review

Method

Number

Contract

Contract

Opening

Gateway Advance Payment

Pre/Post

Signature

Estimated

Amount in Substantial

Acceptance

Submission Submission

Completion

Bid Closing-

Prior or Post Bid Eval Rpt

of Quantities Procurement No-objection No-objection Mobilization

Qualification

by Ex Agency National Press

Drilling of 20 Shallow wells ( South West Shoa; On-line UNDB

Lump sum or Bill Contract Amount

OWRB/MDTF/SHW/06/3/2010 BOQ NCB 89,914.06 Post Post Bid Invitation Date Goro, Wonchi & Tole) Plan 30-Aug-10 15-Sep-10 25-Sep-10 25-Oct-10 10-Nov-10 25-Nov-10 Plan 30-Nov-10 7-Dec-10 7-Apr-12 7-Apr-13 Drilling of 19 Shallow wells (North Shoa & west OWRB/MDTF/SHW/05/2/ 2010 BOQ NCB 85,418.36 Post Post Actual 20-Jan-11 25-Jan-11 12-Feb-11 14-Mar-11 30-Mar-11 20-Apr-11 Actual 131954.61 27-May-11 22-Jun-11 Shoa, OSZSF) Plan 30-Oct-10 15-Nov-10 25-Nov-10 25-Dec-10 10-Jan-11 25-Jan-11 Plan 30-Jan-11 7-Feb-11 7-Apr-12 7-Apr-13 Drilling of 10 Shallow wells (W/Arsi & Bale) OWRB/MDTF/SHW/02/1/ 2010 BOQ NCB 50,720.75 Post Post Actual 20-Jan-11 25-Jan-11 5-May-11 27-May-11 1-Aug-11 10-Aug-11 Actual 104,223.08 27-May-11 22-Sep-11

Plan 30-Oct-10 15-Nov-10 25-Nov-10 25-Dec-10 10-Jan-11 25-Jan-11 Plan 30-Jan-11 7-Feb-11 7-Apr-12 7-Apr-13 Drilling of 20 Shallow wells (East & West Wollega) OWRB/MDTF/SHW/07/1/2010 BOQ NCB 89,914.06 Post Post Actual 20-Jan-11 25-Jan-11 12-Feb-11 14-Mar-11 30-Mar-11 20-Apr-11 Actual 107041.42 24-May-11 09-Jun-11

Plan 30-Aug-10 15-Sep-10 5-Oct-10 5-Nov-10 15-Nov-10 5-Dec-10 Plan 30-Nov-10 7-Dec-10 7-Jun-11 6-Jun-12 Drilling of 13 Shallow wells (West Shoa, OWRB/MDTF/SHW/09/1/ 2010 BOQ NCB 58,444.14 Post Post Actual 20-Jul-10 25-Jul-10 26-Aug-10 26-Oct-10 10-Nov-10 15-Nov-10 Actual 57,677.97 6-Dec-10 17-Dec-10 28-Jun-11 27-Jun-12 E/Wollega)

Plan 30-Aug-10 15-Sep-10 25-Sep-10 25-Oct-10 10-Nov-10 25-Nov-10 Plan 30-Nov-10 7-Dec-10 7-Aug-11 6-Aug-12 Drilling of (deep &) 3 shallow wells (W/Hararge & OWRB/MDTF/DW/02/3/ 2010 BOQ NCB 13,487.11 Post Post Actual 20-Jan-11 25-Jan-11 01-Dec.11 28-Dec-11 5-Jan-12 8-Jan-12 Actual 03-Feb-12 13-Feb-12 12-Jun-12 12-Jun-13 E/Hararge) C.New projects (22 shallow Wells) Plan 15-Apr-12 16-Apr-12 20-Apr-12 25-May-12 1-Jun-12 2-Jun-12 Plan 7-Jun-12 17-Jun-12 15-Oct-12 15-Oct-13 Revised 29-Jun-12 7/14/2012 29-Jul-12 28-Aug-12 12-Sep-12 22-Sep-12 19-Sep-12 9-Oct-12 6-Feb-13 6-Feb-14 Drilling of 10 Shallow wells OWMEB/MDTF/SHW/01/ 2012 BOQ NCB 44,957.03 Post Post Actual Actual

Plan 15-Apr-12 16-Apr-12 20-Apr-12 25-May-12 1-Jun-12 2-Jun-12 Plan 7-Jun-12 17-Jun-12 15-Oct-12 15-Oct-13 Drilling of 12 Shallow wells OWMEB/MDTF/SHW/02/ 2012 BOQ NCB 53,948.44 Post Post Revised 29-Jun-12 19-Jul-12 7/14/2012 29-Jul-12 28-Aug-12 12-Sep-12 22-Sep-12 19-Sep-12 9-Oct-12 6-Feb-13 6-Feb-14 Actual Actual III. Rural Pipe System (137RPS) A. Completed Projects (17 RPS) Plan 16-Dec-08 21-Dec-08 - 26-Apr-08 10-Jun-08 30-Jun-08 15-Jul-08 Plan 23-Jul-08 3-Aug-08 14-Feb-09 14-Feb-10 Hopha (Geba Arba) water supply projects OWRB/CWC/002/1/39/2007 BOQ NCB 89,914.06 Post Post Actual 12-Jul-09 17-Jul-09 - 20-Nov-08 4-Jan-09 24-Jan-09 8-Feb-09 Actual 61,416.51 17-Feb-09 27-Feb-09 26-Nov-09 26-Nov-10

Plan 16-Dec-08 21-Dec-08 - 26-Apr-09 10-Jun-09 30-Jun-09 15-Jul-09 Plan 23-Jul-09 3-Aug-09 13-Dec-09 13-Dec-10 Koma & Gishe Luchine water supply projects OWRB/CWC/MDTF/001/1/2008 BOQ NCB 179,828.13 Post Post Actual - 1-Mar-09 30-Mar-09 8-Apr-09 1-May-09 Actual 110,997.89 19-May-09 1-Jun-09 8-Mar-10 08/Mar/11 Plan 16-Dec-08 21-Dec-08 - 26-Apr-09 10-Jun-09 30-Jun-09 15-Jul-09 Plan 23-Jul-09 3-Aug-09 3-Feb-10 03/Feb/11 Debel water supply project OWRB/CWC/MDTF/001/2/2008 BOQ NCB 85,591.27 Post Post Actual 14-Oct-08 19-Oct-08 - 22-Feb-09 8-Apr-09 28-Apr-09 13-May-09 Actual 65,429.53 22/May/09 1-Jun-09 10-Mar-10 10/Mar/11

Plan 16-Dec-08 21-Dec-08 - 26-Apr-09 10-Jun-09 30-Jun-09 15-Jul-09 Plan 23-Jul-09 3-Aug-09 3-Feb-10 03/Feb/11 Anfera water supply project OWRB/MDTF/CWC/01/3/ 2008 BOQ NCB 85,591.27 Post Post Actual 10-Nov-09 14-Nov-09 - 1-Mar-09 30-Mar-09 8-Apr-09 1-May-09 Actual 100,730.00 13-May-09 1-Jun-09 18-Nov-09 18/Nov/10

Plan 16-Dec-08 21-Dec-08 - 26-Apr-09 10-Jun-09 30-Jun-09 15-Jul-09 Plan 23-Jul-09 3-Aug-09 3-Feb-10 11-Oct-11 Hidha Korma water supply project OWRB/CWC/MDTF/001/5/ 2008 BOQ NCB 85,591.27 Post Post Actual 10-Nov-09 14-Nov-09 - 19-Aug-10 16-Sep-10 6-Oct-10 8-Oct-10 Actual 115,046.75 19-Nov-10 27-Dec-10 10-Jul-11 09/Jul/12

Plan 16-Sep-09 20-Sep-09 - 2-Nov-09 17-Dec-09 6-Jan-10 21-Jan-10 Plan 29-Jan-10 3-Feb-10 2-Jul-10 02/Jul/11 Wayu water supply project OWRB/MDTF/CWC/01/3/ 2009 BOQ NCB 85,591.27 Post Post Actual 10-Nov-09 14-Nov-09 - 27-Dec-09 10-Feb-10 2-Mar-10 17-Mar-10 Actual 76,220.65 20-Mar-10 30-Mar-10 11-Oct-10 11/Oct/11

Post Post Plan 16-Sep-09 20-Sep-09 - 2-Nov-09 17-Dec-09 6-Jan-10 21-Jan-10 Plan 29-Jan-10 3-Feb-10 2-Jul-10 02/Jul/11 Halako Wabe water supply project OWRB/MDTF/CWC/01/7/ 2009 BOQ NCB 89,914.06 Actual 12-Jun-09 16-Jun-09 - 29-Jul-09 12-Sep-09 2-Oct-09 25-Feb-10 Actual 71,804.90 28/Feb/10 10-Mar-10 21-Sep-10 21-Sep-11

Post Post Plan 16-Sep-09 20-Sep-09 - 2-Nov-09 17-Dec-09 6-Jan-10 21-Jan-10 Plan 29-Jan-10 3-Feb-10 2-Jul-10 02/Jul/11 Bole Roge water supply project OWRB/MDTF/CWC/01/08/ 2009 BOQ NCB 89,914.06 Actual 12-Jun-09 16-Jun-09 - 29-Jul-09 12-Sep-09 2-Oct-09 17-Oct-09 Actual 80,388.61 20-Oct-09 30-Oct-09 21-Sep-10 21-Sep-11

Post Post Plan 16-Sep-09 20-Sep-09 - 2-Nov-09 17-Dec-09 6-Jan-10 21-Jan-10 Plan 29-Jan-10 3-Feb-10 11-Oct-10 11-Oct-11 Damu Dhinbiba water supply project OWRB/MDTF/CWC/01/9/ 2009 BOQ NCB 89,914.06 Actual 12-Jun-09 16-Jun-09 - 29-Jul-09 12-Sep-09 2-Oct-09 17-Mar-10 Actual 124,133.07 20/Mar/10 30-Mar-10 31-Oct-10 31/Oct/11

Post Post Plan 16-Sep-09 20-Sep-09 - 2-Nov-09 17-Dec-09 6-Jan-10 21-Jan-10 Plan 29-Jan-10 3-Feb-10 13-May-10 13-May-11 Kelo Water Supply project ORWRB/MDTF/CWC/007/2009 BOQ NCB 89,914.06 Actual 12-Jun-09 16-Jun-09 - 29-Jul-09 12-Sep-09 2-Oct-09 17-Oct-09 Actual 53,770.07 23-Oct-09 30-Oct-09 11-Jun-10 11/Jun/11

Post Post Plan 16-Sep-09 20-Sep-09 - 2-Nov-09 17-Dec-09 6-Jan-10 21-Jan-10 Plan 29-Jan-10 3-Feb-10 13-May-10 13-May-11 Gaba Robi Water Supply project ORWRB/MDTF/CWC/006/2009 BOQ NCB 89,914.06 Actual 12-Jun-09 16-Jun-09 - 29-Jul-09 12-Sep-09 2-Oct-09 17-Oct-09 Actual 55,379.26 23-Oct-09 30-Oct-09 22-Jul-10 22/Jul/11

Post Post Plan 20-Aug-10 5-Sep-10 - 15-Sep-10 15-Oct-10 30-Oct-10 15-Nov-10 Plan 20-Nov-10 27-Nov-10 4-Jul-11 3-Jul-12 Fulo Romso WSP (Borena, ) OWRB/MDTF/RPS/03/ 2010 BOQ NCB 85,591.27 Actual 13-Sep-10 29-Sep-10 - 9-Oct-10 8-Nov-10 23-Nov-10 9-Dec-10 Actual 108,635.36 16-Dec-10 21-Dec-10 22-Aug-11 21/Aug/12

Post Post Plan 20-Aug-10 5-Sep-10 - 15-Sep-10 15-Oct-10 30-Oct-10 15-Nov-11 Plan 20-Nov-10 27-Nov-10 27-May-11 26-May-12 Lege Sure WSP (Borena; Moyale) OWRB/MDTF/RPS/63/2010 BOQ NCB 85,591.27 Actual 13-Sep-10 29-Sep-10 - 9-Oct-10 8-Nov-10 23-Nov-10 9-Dec-11 Actual 163,185.20 16-Dec-10 21-Dec-10 13-Aug-11 12-Aug-12

Post Post Plan 20-Aug-10 5-Sep-10 15-Sep-10 15-Oct-10 30-Oct-10 15-Nov-11 Plan 20-Nov-10 27-Nov-10 4-Jul-11 3-Jul-12 Dheru Denfile WSP (Borena; Dugda Dawa) OWRB/MDTF/RPS/65/2010 BOQ NCB 85,591.27 Actual 13-Sep-10 29-Sep-10 9-Oct-10 8-Nov-10 23-Nov-10 9-Dec-11 Actual 34,917.85 16-Dec-10 21-Dec-10 20-Apr-11 19/Apr/12

Post Post Plan 16-Sep-09 20-Sep-09 2-Nov-09 17-Dec-09 6-Jan-10 21-Jan-10 Plan 29-Jan-10 3-Feb-10 2-Jul-10 02/Jul/11 Lencha Lajo water supply project OWRB/MDTF/CWC/01/11/ 2009 BOQ NCB 89,914.06 Actual 17-Nov-09 21-Nov-09 3-Jan-10 17-Feb-10 9-Mar-10 24-Mar-10 Actual 178,634.65 6-Apr-10 18-Oct-10 18/Oct/11

Post Post Plan 16-Sep-09 20-Sep-09 2-Nov-09 17-Dec-09 6-Jan-10 21-Jan-10 Plan 29-Jan-10 3-Feb-10 13-May-10 13-May-11 Tusha supply project ORWRB/MDTF/CWC/009/2009 BOQ NCB 89,914.06 Actual 12-Jun-09 16-Jun-09 29-Jul-09 12-Sep-09 2-Oct-09 17-Oct-09 Actual 50,745.31 20-Oct-09 30-Oct-09 27-Feb-10 27/Feb/11

B. On going projects (110 RPS) Plan 16-Dec-08 21-Dec-08 26-Apr-09 10-Jun-09 30-Jun-09 5-Jul-09 Plan 13-Jul-09 3-Aug-09 14-Feb-10 14-Feb-11 Jarso Silase water supply projects OWRB/CWC/002/1/2007 BOQ NCB 89,914.06 Post Post Actual 23-Oct-06 28-Oct-06 3-Mar-07 17-Apr-07 7-May-07 12-May-07 Actual 75920.54 31-May-07 10-Jun-07 8-Oct-07 7-Oct-08

Plan 16-Dec-08 21-Dec-08 26-Apr-09 10-Jun-09 30-Jun-09 5-Jul-09 Plan 13-Jul-09 3-Aug-09 3-Feb-10 03/Feb/11 Revised plan Revised plan 5-Sep-12 5-Sep-13 Goda Arba & Ilala Jeba water supply projects OWRB/CWC/MDTF/001/4/2008 BOQ NCB 179,828.13 Post Post Actual 23-Oct-06 28-Oct-06 3-Mar-07 17-Apr-07 7-May-07 12-May-07 Actual 124,332.38 28-Apr-12 8-May-12

Plan 16-Dec-08 21-Dec-08 26-Apr-09 10-Jun-09 30-Jun-09 5-Jul-09 Plan 24/Jul/09 3-Aug-09 3-Feb-10 03/Feb/11 Revised plan 5-Sep-12 5-Sep-13 Geba Gudina water supply projects OWRB/MDTF/CWC/001/5/2008 BOQ NCB 43,804.29 Post Post Actual 23-Oct-06 28-Oct-06 1-Mar-09 30-Mar-09 8-Apr-09 Actual 15,409.18 28-Apr-12 8-May-12

Plan 16-Sep-09 20-Sep-09 2-Nov-09 17-Dec-09 6-Jan-10 11-Jan-10 Plan 19-Jan-10 3-Feb-10 19-Nov-12 19-Nov-13 Mariga Abeyi water supply project OWRB/MDTF/CWC/01/1/ 2009 BOQ NCB 89,914.06 Post Post Revised plan 5-Sep-12 5-Sep-13 Actual 28-Dec-11 1-Jan-12 13-Feb-12 29-Mar-12 18-Apr-12 Actual 156,822.79 28-Apr-12 8-May-12

Plan 16-Sep-09 20-Sep-09 2-Nov-09 17-Dec-09 6-Jan-10 11-Jan-10 Plan 19-Jan-10 3-Feb-10 2-Jul-10 2-Jul-11 Bili Malima water supply project OWRB/MDTF/CWC/01/2/ 2009 BOQ NCB 85,591.27 Post Post Revised plan 5-Sep-12 5-Sep-13 Draft Bid Documents, Spec Proc Basic Data including specs and Notice Bidding Period Bid Evaluation Contract Finalization Contract Implementation quantities, draft SPN Advert

Description*

Package

Number

Lot

Cost Cost

Date Date Date

US US $ Date

Final

Final

Plan vs. Actual Plan vs. Actual

in US$

Prep & Prep Award

Review

Method

Number

Contract

Contract

Opening

Gateway Advance Payment

Pre/Post

Signature

Estimated

Amount in Substantial

Acceptance

Submission Submission

Completion

Bid Closing-

Prior or Post Bid Eval Rpt

of Quantities Procurement No-objection No-objection Mobilization

Qualification

by Ex Agency

National Press

On-line UNDB

Lump sum or Bill Contract Amount

Bili Malima water supply project OWRB/MDTF/CWC/01/2/ 2009 BOQ NCB 85,591.27 Post Post Bid Invitation Date Actual 28-Dec-11 1-Jan-12 13-Feb-12 29-Mar-12 18-Apr-12 Actual 40,884.33 28-Apr-12 8-May-12

Plan 16-Sep-09 20-Sep-09 2-Nov-09 17-Dec-09 6-Jan-10 11-Jan-10 Plan 19-Jan-10 3-Feb-10 17-Aug-10 17-Aug-11 Haro Kono water supply project OWRB/MDTF/CWC/01/9/ 2009 BOQ NCB 89,914.06 Post Post Revised plan 5-Sep-12 5-Sep-13 Actual 28-Dec-11 1-Jan-12 13-Feb-12 29-Mar-12 18-Apr-12 Actual 92,724.06 28-Apr-12 8-May-12

Plan 16-Sep-09 20-Sep-09 2-Nov-09 17-Dec-09 6-Jan-10 11-Jan-10 Plan 19-Jan-10 3-Feb-10 2-Jul-10 18-Oct-11 Didibe Abado water supply project OWRB/MDTF/CWC/01/6/ 2009 BOQ NCB 89,914.06 Post Post Revised plan 11-Sep-12 11-Sep-13 Actual 28-Dec-11 1-Jan-12 13-Feb-12 29-Mar-12 18-Apr-12 Actual 112,816.47 28-Apr-12 14-May-12

Plan 16-Sep-09 20-Sep-09 2-Nov-09 17-Dec-09 6-Jan-10 11-Jan-10 Plan 19-Jan-10 3-Feb-10 13-Jul-00 13-Jul-01 Obenso Jello ORWRB/MDTF/CWC/001/2009 BOQ NCB 89,914.06 Post Post Revised plan 8-May-12 5-Sep-12 5-Sep-13 Actual 28-Dec-11 1-Jan-12 13-Feb-12 29-Mar-12 18-Apr-12 Actual 112,362.53 28-Apr-12

Plan 16-Sep-09 20-Sep-09 2-Nov-09 17-Dec-09 6-Jan-10 11-Jan-10 Plan 19-Jan-10 3-Feb-10 13-Jul-00 13-Jul-01 Tulu Hofi supply project ORWRB/MDTF/CWC/002/2009 BOQ NCB 89,914.06 Post Post Revised plan 8-May-12 5-Sep-12 5-Sep-13 Actual 28-Dec-11 1-Jan-12 13-Feb-12 29-Mar-12 18-Apr-12 Actual 87,108.93 28-Apr-12

Plan 16-Sep-09 20-Sep-09 2-Nov-09 17-Dec-09 6-Jan-10 11-Jan-10 Plan 19-Jan-10 3-Feb-10 13-Jul-00 13-Jul-01 Garbi Goba supply project ORWRB/MDTF/CWC/003/2009 BOQ NCB 89,914.06 Post Post Revised plan 8-May-12 5-Sep-12 5-Sep-13 Actual 28-Dec-11 1-Jan-12 13-Feb-12 29-Mar-12 18-Apr-12 Actual 83,001.31 28-Apr-12

Plan 16-Sep-09 20-Sep-09 2-Nov-09 17-Dec-09 6-Jan-10 11-Jan-10 Plan 19-Jan-10 3-Feb-10 13-Jul-00 13-Jul-01 Revised plan Revised plan 20-Apr-12 20-Apr-13 Soka supply project ORWRB/MDTF/CWC/004/2009 BOQ NCB 89,914.06 Post Post Revised plan 8-May-12 5-Sep-12 5-Sep-13 Actual 28-Dec-11 1-Jan-12 13-Feb-12 29-Mar-12 18-Apr-12 Actual 28-Apr-12

Plan 16-Sep-09 20-Sep-09 2-Nov-09 17-Dec-09 6-Jan-10 11-Jan-10 Plan 19-Jan-10 3-Feb-10 13-Jul-00 13-Jul-01 Revised plan Revised plan 15-Apr-12 15-Apr-13 Sefera Dayu supply project ORWRB/MDTF/CWC/005/2009 BOQ NCB 89,914.06 Post Post Revised plan 8-May-12 5-Sep-12 5-Sep-13 Actual 28-Dec-11 1-Jan-12 13-Feb-12 29-Mar-12 18-Apr-12 Actual 122,075.65 28-Apr-12

Plan 16-Sep-09 20-Sep-09 2-Nov-09 17-Dec-09 6-Jan-10 11-Jan-10 Plan 19-Jan-10 3-Feb-10 13-Jul-00 13-Jul-01 Revised plan Revised plan 15-May-12 15-May-13 Bola Roge supply project ORWRB/MDTF/CWC/008/2009 BOQ NCB 89,914.06 Post Post Revised plan 8-May-12 5-Sep-12 5-Sep-13 Actual 28-Dec-11 1-Jan-12 13-Feb-12 29-Mar-12 18-Apr-12 Actual 80,388.61 28-Apr-12

Plan 20-Aug-10 5-Sep-10 15-Sep-10 15-Oct-10 30-Oct-10 4-Nov-10 Plan 20-Nov-10 27-Nov-10 27-May-11 26-May-12 Revised plan Revised plan 20-Jun-12 20-Jun-13 Abasamu'el water supply project OWRB/MDTF/RPS/01/ 2010 BOQ NCB 85,591.27 Post Post Revised plan 8-May-12 5-Sep-12 5-Sep-13 Actual 28-Dec-11 1-Jan-12 13-Feb-12 29-Mar-12 18-Apr-12 Actual 72,643.44 28-Apr-12 26-May-11

Plan 20-Aug-10 5-Sep-10 15-Sep-10 15-Oct-10 30-Oct-10 4-Nov-10 Plan 20-Nov-10 27-Nov-10 27-May-11 26-May-12 Revised plan Revised plan 15-Apr-12 15-Apr-13 Kufa Kas water supply project OWRB/MDTF/RPS/02/ 2010 BOQ NCB 85,591.27 Post Post Revised plan 8-May-12 5-Sep-12 5-Sep-13 Actual 28-Dec-11 1-Jan-12 13-Feb-12 29-Mar-12 18-Apr-12 Actual 107,487.88 28-Apr-12

Plan 16-Dec-08 21-Dec-08 26-Apr-09 10-Jun-09 30-Jun-09 5-Jul-09 Plan 13-Jul-09 3-Aug-09 3-Feb-10 11-Oct-11 Revised plan Revised plan 30-May-12 30-May-13 Haleyo, Guro gudo & Jallo OWRB/CWC/MDTF/04/ 2010 BOQ NCB 107,487.89 Post Post Actual 10-Apr-10 15-Apr-10 19-Aug-10 16-Sep-10 6-Oct-10 Actual 131,882.49 5-Nov-10 22-Nov-10

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 4-Jan-11 Plan - 20-Jan-11 27-Jan-11 27-Jul-11 26/Jul/12 Revised plan Revised plan 30-May-12 30/May/13 Hinde WSP (East Wollega; Ebantu) OWRB/MDTF/RPS/15/2010 BOQ NCB 131882.495 Post Post Actual 28-Sep-10 14-Oct-10 24-Oct-10 23-Nov-10 8-Dec-10 13-Dec-10 Actual 109,508.25 21-Dec-10

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 4-Jan-11 Plan 20-Jan-11 27-Jan-11 27-Jul-11 26/Jul/12 Revised plan Revised plan 7-Feb-11 20-May-12 20/May/13 Korke WSP ( South West Shoa, Weliso) OWRB/MDTF/RPS/20/2010 BOQ NCB 85,591.27 Post Post Actual 12-Nov-10 28-Nov-10 8-Dec-10 7-Jan-11 22-Jan-11 27-Jan-11 Actual 46,388.23 31-Jan-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 4-Jan-11 Plan 20-Jan-11 27-Jan-11 27-Jul-11 26/Jul/12 Sombo-Disasa & Fechase WSPs ( West Shoa, Bako- Revised plan Revised plan 20-Jun-12 20/Jun/13 OWRB/MDTF/RPS/22/2010 BOQ NCB 179,828.13 Post Post Tibe) Actual 23-Aug-10 8-Sep-10 18-Sep-10 19-Oct-10 1-Nov-10 6-Nov-10 Actual 86,920.34 22-Nov-10 12-Dec-10

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 4-Jan-11 Plan 20-Jan-11 27-Jan-11 27-Jul-11 26/Jul/12 Revised plan Revised plan 20-May-12 20/May/13 Tose & Goben WSPs ( West Shoa, Cheliya) OWRB/MDTF/RPS/23/2010 BOQ NCB 129,395.56 Post Post Actual 23-Aug-10 8-Sep-10 18-Sep-10 19-Oct-10 1-Nov-10 6-Nov-10 Actual 82,309.97 22-Nov-10 12-Dec-10

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 4-Jan-11 Plan 20-Mar-11 27-Mar-11 8-Oct-11 7-Oct-12 Revised plan Revised plan 30-Jun-12 30-Jun-13 Chimo Negelle WSP (Arsi, Sude) OWRB/MDTF/RPS/55/2010 BOQ NCB 85,591.27 Post Post Actual 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 4-Jan-11 Actual 215,786.55 8-Nov-10 12-Nov-10

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 4-Jan-11 Plan 20-Mar-11 27-Mar-11 26-May-11 25-May-12 Revised plan Revised plan 25-Jun-12 25-Jun-13 Tedecha/Teji WSP (Arsi, Amigna) OWRB/MDTF/RPS/56/2010 BOQ NCB 85,591.27 Post Post Actual 22-Aug-10 7-Sep-10 17-Sep-10 17-Oct-10 1-Nov-10 6-Nov-10 Actual 94,992.13 8-Nov-10 12-Nov-10

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 4-Jan-11 Plan 20-Mar-11 27-Mar-11 27-Oct-11 26-Oct-12 Revised plan Revised plan 30-Apr-12 30-Apr-13 Wacho Mishirge WSP (Bale; Goba) OWRB/MDTF/RPS/57/2010 BOQ NCB 85,591.27 Post Post Actual 22-Aug-10 7-Sep-10 17-Sep-10 17-Oct-10 1-Nov-10 6-Nov-10 Actual 75,175.47 8-Nov-10 12-Nov-10

Plan 20-Aug-10 5-Sep-10 15-Sep-10 15-Oct-10 30-Oct-10 4-Nov-10 Plan 20-Nov-10 27-Nov-10 26-May-11 25-May-12 Revised plan Revised plan 20-Jun-12 20-Jun-13 Hache WSP (Borena; ) OWRB/MDTF/RPS/64/2010 BOQ NCB 85,591.27 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 58,450.13 8-Nov-10 12-Nov-10

Plan 20-Dec-10 5-Jan-11 15-Jan-11 15-Feb-11 2-Mar-11 7-Mar-11 Plan 20-Mar-11 27-Mar-11 8-Oct-11 7-Oct-12 Revised plan Revised plan 25-Jun-12 25-Jun-13 Buro Fincha'a WSP (OSZSF; Sebeta-Hawas) OWMEB/MDTF/RPS/53/2010 BOQ NCB 85,591.27 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 78,978.35 22-Jun-11 12-Nov-10

Plan 20-Dec-10 5-Jan-11 15-Jan-11 15-Feb-11 2-Mar-11 7-Mar-11 Plan 20-Mar-11 27-Mar-11 8-Oct-11 7-Oct-12 Revised plan Revised plan 20-Jun-12 20-Jun-13 Abebe Silase WSP (SW/Shoa; Tole) OWMEB/MDTF/RPS/48/2010 BOQ NCB 85,591.27 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 37,726.76 10-Aug-11 10-Aug-11

Plan 20-Dec-10 5-Jan-11 15-Jan-11 15-Feb-11 2-Mar-11 7-Mar-11 Plan 20-Mar-11 27-Mar-11 2-Jan-12 1-Jan-13 Revised plan Revised plan 20-Jun-12 20-Jun-13 Abado Lemen WSP (SW/Shoa; Weliso) OWMEB/MDTF/RPS/49/2010 BOQ NCB 85,591.27 Post Post Draft Bid Documents, Spec Proc Basic Data including specs and Notice Bidding Period Bid Evaluation Contract Finalization Contract Implementation quantities, draft SPN Advert

Description*

Package

Number

Lot

Cost Cost

Date Date Date

US US $ Date

Final

Final

Plan vs. Actual Plan vs. Actual

in US$

Prep & Prep Award

Review

Method

Number

Contract

Contract

Opening

Gateway Advance Payment

Pre/Post

Signature

Estimated

Amount in Substantial

Acceptance

Submission Submission

Completion

Bid Closing-

Prior or Post Bid Eval Rpt

of Quantities Procurement No-objection No-objection Mobilization

Qualification

by Ex Agency

National Press

On-line UNDB

Lump sum or Bill Contract Amount Abado Lemen WSP (SW/Shoa; Weliso) OWMEB/MDTF/RPS/49/2010 BOQ NCB 85,591.27 Post Post Bid Invitation Date Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 35,483.62 12-Jun-11 21-Jun-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 4-Jan-11 Plan 20-Jan-11 27-Jan-11 3-Jan-12 2-Jan-13 Hereri/Terara WSP (West Shoa; Abuna Revised plan Revised plan 20-Jun-12 20-Jun-13 OWMEB/MDTF/RPS/24/2010 BOQ NCB 89,914.06 Post Post Gindeberet) Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 57,944.13 12-Jun-11 22-Jun-11

Plan 20-Dec-10 5-Jan-11 15-Jan-11 15-Feb-11 2-Mar-11 7-Mar-11 Plan 20-Mar-11 27-Mar-11 4-Jan-12 3-Jan-13 Revised plan Revised plan 20-Jun-12 20-Jun-13 Chando WSP (W/Shoa; Nono) OWMEB/MDTF/RPS/50/2010 BOQ NCB 85,591.27 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 27,788.92 12-Jun-11 23-Jun-11

Plan 20-Dec-10 5-Jan-11 15-Jan-11 15-Feb-11 2-Mar-11 7-Mar-11 Plan 20-Mar-11 27-Mar-11 13-Mar-12 13-Mar-13 Revised plan Revised plan 20-Jun-12 20-Jun-13 Wine WSP (W/Shoa; Tikur Inchini) OWMEB/MDTF/RPS/51/2010 BOQ NCB 85,591.27 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 52,297.32 12-Jun-11 31-Aug-11

Plan 20-Dec-10 5-Jan-11 15-Jan-11 15-Feb-11 2-Mar-11 7-Mar-11 Plan 20-Mar-11 27-Mar-11 29-Dec-11 28-Dec-12 Revised plan Revised plan 20-Jun-12 20-Jun-13 Wakene WSP (N/Shoa; Debre Libanos) OWMEB/MDTF/RPS/52/2010 BOQ NCB 92,253.10 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 82,866.34 12-Jun-11 17-Jun-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 4-Jan-11 Plan 20-Jan-11 27-Jan-11 5-Jan-12 4-Jan-13 Revised plan Revised plan 20-Jun-12 20-Jun-13 Setema WSP (Jima; Setema) OWMEB/MDTF/RPS/26/2010 BOQ NCB 89,914.06 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 74,517.24 12-Jun-11 24-Jun-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 4-Jan-11 Plan 20-Jan-11 27-Jan-11 5-Jan-12 4-Jan-13 Revised plan Revised plan 20-Jun-12 20-Jun-13 Addis Limat WSP (Jima; Limu Kosa) OWMEB/MDTF/RPS/27/2010 BOQ NCB 89,914.06 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 103,951.23 12-Jun-11 24-Jun-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 4-Jan-11 Plan 20-Jan-11 27-Jan-11 29-Dec-11 28-Dec-12 Revised plan Revised plan 20-Jun-12 20-Jun-13 Mote WSP ( East Wollega, Wama Haglo) OWMEB/MDTF/RPS/16/2010 BOQ NCB 89,914.06 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 87,131.83 12-Jun-11 17-Jun-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 4-Jan-11 Plan 20-Jan-11 27-Jan-11 8-Jan-12 7-Jan-13 Revised plan Revised plan 20-Jun-12 20-Jun-13 Jangir WSP ( East Wollega; Gida Ayana) OWMEB/MDTF/RPS/17/2010 BOQ NCB 89,914.06 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 63,007.67 12-Jun-11 27-Jun-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 4-Jan-11 Plan 20-Jan-11 27-Jan-11 10-Aug-11 9-Aug-12 Revised plan Revised plan 20-Jun-12 20-Jun-13 Geba Defino WSP ( West Wollega; Kondala) OWMEB/MDTF/RPS/18/2/2010 BOQ NCB 89,914.06 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 89,260.38 12-Jun-11 24-Aug-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 4-Jan-11 Plan 20-Jan-11 27-Jan-11 28-Mar-12 28-Mar-13 Revised plan Revised plan 25-Jun-12 25-Jun-13 Wama Tobera WSP ( West Wollega; Menesibu) OWMEB/MDTF/RPS/18/1/2010 BOQ NCB 89,914.06 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 44,951.20 7-Jun-11 17-Jun-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 4-Jan-11 Plan 20-Jan-11 27-Jan-11 11-Jan-12 10-Jan-13 Revised plan Revised plan 20-Jun-12 20-Jun-13 Nunu WSP ( Kellem Wollega; Jima Horo) OWMEB/MDTF/RPS/19/1/2011 BOQ NCB 89,914.06 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 89,607.62 7-Jun-11 30-Jun-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 4-Jan-11 Plan 20-Jan-11 27-Jan-11 28-Dec-11 27-Dec-12 Revised plan Revised plan 20-Jun-12 20-Jun-13 Gorayi WSP ( Kellem Wollega; Gidami) OWMEB/MDTF/RPS/19/2/2011 BOQ NCB 89,914.06 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 106,824.80 7-Jun-11 16-Jun-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 4-Jan-11 Plan 20-Jan-11 30-Jul-11 10-Feb-12 9-Feb-13 Revised plan Revised plan 20-Jun-12 20-Jun-13 Addis Alem WSP (E /Hararge; Melka Belo) OWMEB/MDTF/RPS/04/2011 BOQ NCB 89,914.06 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 56,660.35 7-Jun-11 8-Jul-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 15-Jan-11 Plan 20-Jan-11 30-Jul-11 10-Feb-12 9-Feb-13 Revised plan Revised plan 20-Jun-12 20-Jun-13 Chela Negeya WSP (E /Hararge; Deder) OWMEB/MDTF/RPS/05/2011 BOQ NCB 89,914.06 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 50,597.02 7-Jun-11 14-Jul-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 15-Jan-11 Plan 20-Jan-11 27-Jan-11 2-Jan-12 1-Jan-13 Burka Gemechu, Umer & Elfeta WSP (E /Hararge; Revised plan Revised plan 20-Jun-12 20-Jun-13 OWMEB/MDTF/RPS/06/2011 BOQ NCB 89,914.06 Post Post Meta) Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 130,899.95 7-Jun-11 21-Jun-11

Plan 20-Aug-10 5-Sep-10 15-Sep-10 15-Oct-10 30-Oct-10 15-Nov-11 Plan 20-Nov-10 27-Nov-10 27-May-11 26-May-12 Revised plan Revised plan 20-Apr-12 20-Apr-13 Ledo WSP (Borena, Abaya) OWMEB/MDTF/RPS/66/2011 BOQ NCB 85,591.27 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 86,931.28 7-Jun-11 29-Jul-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 15-Jan-11 Plan 20-Jan-11 27-Jan-11 10-Jan-12 9-Jan-13 Revised plan Revised plan 20-Jun-12 20-Jun-13 Abure, Dilo &Bore WSPs (Arsi, Munesa) OWMEB/MDTF/RPS/10/2011 BOQ NCB 131,412.86 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 67,194.00 7-Jun-11 29-Jun-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 15-Jan-11 Plan 20-Jan-11 27-Jan-11 16-Jan-12 15-Jan-13 Gudina Adola, Lege Dana Gonjo, Lole & Kotile Revised plan Revised plan 20-Jun-12 20-Jun-13 OWMEB/MDTF/RPS/11/2011 BOQ NCB 175,217.15 Post Post WSPs (Arsi, Munesa) Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 67,586.49 7-Jun-11 5-Jul-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 15-Jan-11 Plan 20-Jan-11 27-Jan-11 27-Jul-11 26-Jul-12 Revised plan Revised plan 20-Jun-12 20-Jun-13 Malekicho Asendabo WSP (Arsi, Amigna) OWMEB/MDTF/RPS/11/2011 BOQ NCB 89,914.06 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 138,550.03 26-Jul-11 10-Aug-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 15-Jan-11 Plan 20-Jan-11 27-Jan-11 3-Jan-12 2-Jan-13 Revised plan Revised plan 20-Jun-12 20-Jun-13 Harbefano WSP (W/Hararge, Gemechis) OWMEB/MDTF/RPS/07/1/2010 BOQ NCB 89,914.06 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 37,832.26 7-Jun-11 22-Jun-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 15-Jan-11 Plan 20-Jan-11 27-Jan-11 27-Jul-11 26-Jul-12 Revised plan Revised plan 20-Jun-12 20-Jun-13 Goro Meta WSP (W/Hararge, Guba Koricha) OWMEB/MDTF/RPS/07/2/2010 BOQ NCB 89,914.06 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 64,368.17 7-Jun-11 14-Jul-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 15-Jan-11 Plan 20-Jan-11 27-Jan-11 2-Jan-12 1-Jan-13 Revised plan Revised plan 20-Jun-12 20-Jun-13 Kebeso WSP (W/Hararge, Mesela) OWMEB/MDTF/RPS/07/3/2010 BOQ NCB 89,914.06 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 95,184.49 7-Jun-11 21-Jun-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 15-Jan-11 Plan 20-Jan-11 27-Jan-11 11-Jan-12 10-Jan-13 Revised plan Revised plan 20-Jun-12 20-Jun-13 Fefate, Gelcha & Goda WSPs (East Shoa; Fentale) OWMEB/MDTF/RPS/25/1/2010 BOQ NCB 131,412.86 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 52,828.09 7-Jun-11 30-Jun-11 Draft Bid Documents, Spec Proc Basic Data including specs and Notice Bidding Period Bid Evaluation Contract Finalization Contract Implementation quantities, draft SPN Advert

Description*

Package

Number

Lot

Cost Cost

Date Date Date

US US $ Date

Final

Final

Plan vs. Actual Plan vs. Actual

in US$

Prep & Prep Award

Review

Method

Number

Contract

Contract

Opening

Gateway Advance Payment

Pre/Post

Signature

Estimated

Amount in Substantial

Acceptance

Submission Submission

Completion

Bid Closing-

Prior or Post Bid Eval Rpt

of Quantities Procurement No-objection No-objection Mobilization

Qualification

by Ex Agency National Press

Fefate, Gelcha & Goda WSPs (East Shoa; Fentale) OWMEB/MDTF/RPS/25/1/2010 BOQ NCB 131,412.86 Post Post On-line UNDB

Lump sum or Bill Contract Amount Bid Invitation Date

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 15-Jan-11 Plan 20-Jan-11 27-Jan-11 2-Jan-12 1-Jan-13 Revised plan Revised plan 20-Jun-12 20-Jun-13 Indode WSP(East Shoa; Gimbichu) OWMEB/MDTF/RPS/25/2/2010 BOQ NCB 43,804.29 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 26,101.93 7-Jun-11 21-Jun-11

Plan 20-Dec-10 5-Jan-11 15-Jan-11 15-Feb-11 30/2/2011 15-Jan-11 Plan 20-Mar-11 27-Mar-11 4-Jan-12 3-Jan-13 Revised plan Revised plan 20-Jun-12 20-Jun-13 Ilasa WSP (Bale; Goba) OWMEB/MDTF/RPS/58/2010 BOQ NCB 85,591.27 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 45,836.84 7-Jun-11 23-Jun-11

Plan 20-Oct-10 5-Nov-10 15-Nov-10 15-Dec-10 30-Dec-10 15-Jan-11 Plan 20-Jan-11 27-Jan-11 4-Jan-12 3-Jan-13 Revised plan Revised plan 20-Jun-12 20-Jun-13 Dirira WSP (Bale; Delo Mena) OWMEB/MDTF/RPS/13/2010 BOQ NCB 89,914.06 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 18,291.88 7-Jun-11 23-Jun-11

Plan 20-Aug-10 5-Sep-10 15-Sep-10 15-Oct-10 30-Oct-10 15-Nov-11 Plan 20/11/2010 27-Nov-10 3-Jan-12 2-Jan-13 Revised plan Revised plan 20-Jun-12 20-Jun-13 Beda Kesa WSP (Guji; Odo Shakiso) OWMEB/MDTF/RPS/67/2010 BOQ NCB 85,591.27 Post Post Actual 27-Jan-11 12-Feb-11 22-Feb-11 21-Mar-11 10-May-11 Actual 59,759.77 7-Jun-11 22-Jun-11

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 7-Sep-12 7-Sep-13 Galesa Negeso WSP (Borena, Bule Hora) OWMEB/MDTF/RPS/15-1/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 38,755.55 30-Apr-12 10-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 7-Sep-12 7-Sep-13 Arero Tune WSP (Borena, Arero) OWMEB/MDTF/RPS/15-2/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 74,464.49 30-Apr-12 10-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 7-Sep-12 7-Sep-13 Rare Beha WSP (Borena, Dire) OWMEB/MDTF/RPS/16/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 250,430.29 30-Apr-12 10-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 7-Sep-12 7-Sep-13 Dhokole WSP (Borena, Dire) OWMEB/MDTF/RPS/17/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 38,333.61 30-Apr-12 10-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 7-Sep-12 7-Sep-13 Kebena'a/Mega (Borena, Dire) OWMEB/MDTF/RPS/18/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 152,701.12 30-Apr-12 10-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 7-Sep-12 7-Sep-13 Birate Sayo (OSZSF, Sululta) OWMEB/MDTF/RPS/01/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 78,090.12 30-Apr-12 10-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 7-Sep-12 7-Sep-13 Roben Jirecha Tamse (OSZSF, Sebeta Hawas) OWMEB/MDTF/RPS/02/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 62,352.15 30-Apr-12 10-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 6-Sep-12 6-Sep-13 Chole Sokole (North Shoa, Aleltu) OWMEB/MDTF/RPS/03/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 74,921.18 30-Apr-12 9-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 6-Sep-12 6-Sep-13 Kura Kemele (OSZSF, Mulo) OWMEB/MDTF/RPS/04/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 84,142.19 30-Apr-12 9-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 7-Sep-12 7-Sep-13 Chabi Sire Goyo (OSZSF, Berek) OWMEB/MDTF/RPS/05/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 20,714.30 30-Apr-12 10-May-12 7-Sep-12 7-Sep-13

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 15-Oct-11 18-Oct-11 Plan 19-Oct-11 26-Oct-11 23-Feb-12 22-Feb-13 Revised 11-Sep-12 11-Sep-13 Menjikso Tede (East Shoa, Gimbichu) OWMEB/MDTF/RPS/06/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 78,159.32 30-Apr-12 14-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 9-Feb-12 10-Mar-12 25-Mar-12 30-Jul-12 19-Aug-12 29-Apr-00 29-Apr-01 Kiltu Kara (West Wollega, Kiltu kara) OWMEB/MDTF/RPS/22-1/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 8-Sep-12 8-Sep-13 Wama Tobera 2 (West Wollega, Menesibu) OWMEB/MDTF/RPS/22-2/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 20,714.30 1-May-12 11-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 27-Sep-12 27-Sep-13 Sardo (Ilu Aba Bora, Dega) OWMEB/MDTF/RPS/07/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 120,670.75 30-May-12 14-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 6-Sep-12 6-Sep-13 Ire Tokuma (East Hararge, Meta) OWMEB/MDTF/RPS/11/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 54,477.38 30-May-12 9-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 21-Sep-12 21-Sep-13 Kumuto (East Hararge, Melka Belo) OWMEB/MDTF/RPS/12-1/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 117,908.99 30-Apr-12 24-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 6-Sep-12 6-Sep-13 Goro Abu (East Hararge, Gola Oda) OWMEB/MDTF/RPS/12-2/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 104,192.63 30-Apr-12 9-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 14-Sep-12 14-Sep-13 Burka Bereka (East Hararge, Deder) OWMEB/MDTF/RPS/13/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 139,038.36 30-Apr-12 17-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Alentu Dobedo & Fifota Wesherbi Revised 7-Sep-12 7-Sep-13 OWMEB/MDTF/RPS/19/2011 BOQ NCB 118,273.21 Post Post (W/Arsi,Dodola) Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 161,945.12 30-Apr-12 10-May-12 Draft Bid Documents, Spec Proc Basic Data including specs and Notice Bidding Period Bid Evaluation Contract Finalization Contract Implementation quantities, draft SPN Advert

Description*

Package

Number

Lot

Cost Cost

Date Date Date

US US $ Date

Final

Final

Plan vs. Actual Plan vs. Actual

in US$

Prep & Prep Award

Review

Method

Number

Contract

Contract

Opening

Gateway Advance Payment

Pre/Post

Signature

Estimated

Amount in Substantial

Acceptance

Submission Submission

Completion

Bid Closing-

Prior or Post Bid Eval Rpt

of Quantities Procurement No-objection No-objection Mobilization

Qualification

by Ex Agency

National Press

On-line UNDB

Lump sum or Bill Contract Amount Bid Invitation Date Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Ititu Sura & Darole (Bale & Arsi; Goba & Bele Revised 13-Sep-12 13-Sep-13 OWMEB/MDTF/RPS/20-1/2011 BOQ NCB 118,273.21 Post Post Gesgar) Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 117,719.09 30-Apr-12 16-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 7-Jan-00 13-Sep-12 13-Sep-13 Chobi (Bale, Sawena) OWMEB/MDTF/RPS/20-2/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 215,178.82 30-Apr-12 16-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 7-Sep-12 7-Sep-13 Irba & Goro Uko (Bale, Delomena) OWMEB/MDTF/RPS/21-1/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 65709.08 30-Apr-12 10-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 15-Oct-11 18-Oct-11 Plan 19-Oct-11 26-Oct-11 23-Feb-12 22-Feb-13 Revised 7-Sep-12 7-Sep-13 Oda Dima (Bale, Delomena) OWMEB/MDTF/RPS/21-2/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 163991.40 30-Apr-12 10-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 8-Sep-12 8-Sep-13 Didibe Goro 2 (South West Shoa, Goro) OWMEB/MDTF/RPS/08/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 54,651.66 30-Apr-12 11-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 8-Sep-12 8-Sep-13 Echa (South West Shoa, Wonchi) OWMEB/MDTF/RPS/09/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 57,678.63 30-Apr-12 11-May-12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 5-Sep-12 5-Sep-13 Gulti Bola (South West Shoa, Ameya) OWMEB/MDTF/RPS/21/2010 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 74,353.03 30/Apr/12 08/May/12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 11-Sep-12 11-Sep-13 Malko (Jima, Seka Chokorsa) OWMEB/MDTF/RPS/14-1/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 67,107.22 30/Apr/12 14/May/12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 11-Sep-12 11-Sep-13 Sombo (Jima, Shabe Sombo) OWMEB/MDTF/RPS/14-2/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 136,444.37 30/Apr/12 14/May/12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 11-Sep-12 11-Sep-13 Dame (Jima, Lemu Seka) OWMEB/MDTF/RPS/14-3/2011 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 112,033.45 30/Apr/12 14/May/12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Ilala Chobi, Ilala Jeba 2 & Goda Arba 2 (West shoa, Revised 15-Sep-12 15-Sep-13 OWMEB/MDTF/RPS/10/2011 BOQ NCB 118,273.21 Post Post Mida Kegn) Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 9-Apr-12 12-Apr-12 Actual 221,189.93 30/Apr/12 18/May/12

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 17-Mar-12 20-Mar-12 Plan 21-Mar-12 28-Mar-12 26-Jul-12 26-Jul-13 Revised 5-Sep-12 5-Sep-13 Chando (West Shoa, Nono) OWMEB/MDTF/RPS/50/2010 BOQ NCB 118,273.21 Post Post Actual 15-Dec-11 20-Dec-11 9-Feb-12 7-Mar-12 Actual 46,163.97 30/Apr/12 08/May/12

C. New projects (10 RPS) Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 20-Oct-11 25-Oct-11 Plan 30-Oct-11 15-Nov-11 28-May-12 28-May-13 Revised 27-May-11 03-Jun-11 14-Jun-12 14-Jul-12 29-Jul-12 2-Aug-12 5-Aug-12 25-Aug-12 23-Dec-12 23-Dec-13 Construction of 5 RPS 5 contracts OWMEB/MDTF/RPS/1-5/2012 BOQ NCB 473,092.84 Post Post Actual Actual

Plan 20-Aug-11 25-Aug-11 5-Sep-11 5-Oct-11 20-Oct-11 25-Oct-11 Plan 30-Oct-11 15-Nov-11 28-May-12 28-May-13 Revised 27-May-11 03-Jun-11 14-Jun-12 14-Jul-12 29-Jul-12 2-Aug-12 5-Aug-12 25-Aug-12 23-Dec-12 23-Dec-13 Construction of 5 RPS, 5 contracts OWMEB/MDTF/RPS/6-10/2011 BOQ NCB 591,366.06 Post Post Actual Actual Procurement Plan Consultancy Country/Organization: Oromia National Regional State Water Resource Bureau Project/Programme: IDA-DFID (MDTF) Loan #: THE PROPER TEMPLATE!

Country/Organisation: For Contracts under projects approved after the May 2002 Guidelines Project/Programme: If Post-Review, No-objection Dates are not needed Loan #:

Contract Preparation Request for EOI Short Consultant Proposal Evaluation and Negotiation for Projects after May 2002 Draft Contract Contract Finalization Contract Implementation Type Request for Proposals (where required) List Proposals Technical (T) & Financial (F) and Negotions (N) Estimated On-line Description* Lumpsum Amount Prep & Lead-time Submission/ Submission No-objection Opening Preparation No- Contract Mobilization No-objection UNDB Submission No-objection Invitation Negotiations Plan vs. Submission Contract Contract Plan vs. Draft Final or in US$ Submission before Opening Evaluation Evaluation Financial Eval Report objection Amount in Advance

Date Gateway Date Date Date (N) Actual Date Award Signature Actual Report Report Plan vs. Actual

Time-Based by Ex Ag shortlist Plan vs. Actual Date Report (T) Report (T) Proposals (T) (F) Date US$ '000 Payment Selection Method Prior/Post Prior/Post Review Nat Press Norm Duration of Proc Steps Plan 3 - 6 wks 1 - 2 wks 1 - 1.5 wks 2 wks 1 - 2 wks Plan 4 to 12 wks 2 - 3 wks 0.5 - 2 wks 2 wks 1 - 2 wks 2 wks Plan 1 - 2 wks 1 - 2 wks 1 wk 1 - 3 wks Plan Actual Actual Actual Actual List of Contracts A. Woreda Support Groups

Plan 8-Aug-08 23-Aug-08 2-Sep-08 9-Sep-08 14-Sep-08 19-Sep-08 Plan 1-Oct-08 15-Dec-08 15-Mar-09 21-Mar-09 31-Mar-09 10-Apr-09 15-Apr-09 Plan 25-Apr-09 2-May-09 15-May-09 1-Dec-09 Plan 11-Dec-09 NA 28-Feb-11 Milkoftu Business and Development CQ LS& TB 129,265.00 Post Actual 30-Sep-08 10-Oct-08 20-Oct-08 24-Oct-08 1-Nov-08 Actual 10-Nov-08 23-Dec-08 24-Aug-09 30-Aug-09 9-Sep-09 19-Sep-09 24-Sep-09 Actual 4-Oct-09 11-Oct-09 116,189.07 5-Dec-09 15-Dec-09 Actual 20-Dec-09 19-Mar-11 PLC, OWRB/CS/WSG/01/09

Plan 8-Aug-08 23-Aug-08 2-Sep-08 9-Sep-08 14-Sep-08 19-Sep-08 Plan 1-Oct-08 15-Dec-08 15-Mar-09 21-Mar-09 31-Mar-09 10-Apr-09 15-Apr-09 Plan 25-Apr-09 2-May-09 15-May-09 1-Dec-09 Plan 11-Dec-09 NA 28-Feb-11 Abdi Jiregna PLC, CQ LS& TB 129,265.00 Post Actual 30-Sep-08 10-Oct-08 20-Oct-08 24-Oct-08 1-Nov-08 Actual 10-Nov-08 23-Dec-08 24-Aug-09 30-Aug-09 9-Sep-09 19-Sep-09 24-Sep-09 Actual 4-Oct-09 11-Oct-09 132,128.97 5-Dec-09 15-Dec-09 Actual 20-Dec-09 19-Mar-11 OWRB/CS/WSG/02/09

Plan 8-Aug-08 23-Aug-08 2-Sep-08 9-Sep-08 14-Sep-08 19-Sep-08 Plan 1-Oct-08 15-Dec-08 15-Mar-09 21-Mar-09 31-Mar-09 10-Apr-09 15-Apr-09 Plan 25-Apr-09 2-May-09 15-May-09 1-Dec-09 Plan 11-Dec-09 NA 28-Feb-11 Latinsa S.C, OWRB/CS/WSG/03/09 CQ LS& TB 129,265.00 Post Actual 30-Sep-08 10-Oct-08 20-Oct-08 24-Oct-08 1-Nov-08 Actual 10-Nov-08 23-Dec-08 24-Aug-09 30-Aug-09 9-Sep-09 19-Sep-09 24-Sep-09 Actual 4-Oct-09 11-Oct-09 110,530.80 5-Dec-09 15-Dec-09 Actual 20-Dec-09 19-Mar-11

Plan 8-Aug-08 23-Aug-08 2-Sep-08 9-Sep-08 14-Sep-08 19-Sep-08 Plan 1-Oct-08 15-Dec-08 15-Mar-09 21-Mar-09 31-Mar-09 10-Apr-09 15-Apr-09 Plan 25-Apr-09 2-May-09 15-May-09 1-Dec-09 Plan 11-Dec-09 NA 28-Feb-11 Awash Consult PLC, CQ LS& TB 129,265.00 Post Actual 30-Sep-08 10-Oct-08 20-Oct-08 24-Oct-08 1-Nov-08 Actual 10-Nov-08 23-Dec-08 24-Aug-09 30-Aug-09 9-Sep-09 19-Sep-09 24-Sep-09 Actual 4-Oct-09 11-Oct-09 126,338.63 5-Dec-09 15-Dec-09 Actual 20-Dec-09 19-Mar-11 OWRB/CS/WSG/04/09

Plan 8-Aug-08 23-Aug-08 2-Sep-08 9-Sep-08 14-Sep-08 19-Sep-08 Plan 1-Oct-08 15-Dec-08 15-Mar-09 21-Mar-09 31-Mar-09 10-Apr-09 15-Apr-09 Plan 25-Apr-09 2-May-09 15-May-09 1-Dec-09 Plan 11-Dec-09 NA 28-Feb-11 GAMI United Consultancy PLC, CQ LS& TB 129,265.00 Post Actual 30-Sep-08 10-Oct-08 20-Oct-08 24-Oct-08 1-Nov-08 Actual 10-Nov-08 23-Dec-08 24-Aug-09 30-Aug-09 9-Sep-09 19-Sep-09 24-Sep-09 Actual 4-Oct-09 11-Oct-09 103,350.44 5-Dec-09 15-Dec-09 Actual 20-Dec-09 19-Mar-11 OWRB/CS/WSG/05/09

Plan 8-Aug-08 23-Aug-08 2-Sep-08 9-Sep-08 14-Sep-08 19-Sep-08 Plan 1-Oct-08 15-Dec-08 15-Mar-09 21-Mar-09 31-Mar-09 10-Apr-09 15-Apr-09 Plan 25-Apr-09 2-May-09 15-May-09 1-Dec-09 Plan 11-Dec-09 NA 28-Feb-11 Fanta Feyisa RWaSH Consultancy CQ LS& TB 129,265.00 Post Actual 30-Sep-08 10-Oct-08 20-Oct-08 24-Oct-08 1-Nov-08 Actual 10-Nov-08 23-Dec-08 24-Aug-09 30-Aug-09 9-Sep-09 19-Sep-09 24-Sep-09 Actual 4-Oct-09 11-Oct-09 101,342.69 5-Dec-09 15-Dec-09 Actual 20-Dec-09 19-Mar-11 PLC, OWRB/CS/WSG/06/09

Plan 8-Aug-08 23-Aug-08 2-Sep-08 9-Sep-08 14-Sep-08 19-Sep-08 Plan 1-Oct-08 15-Dec-08 15-Mar-09 21-Mar-09 31-Mar-09 10-Apr-09 15-Apr-09 Plan 25-Apr-09 2-May-09 15-May-09 1-Dec-09 Plan 11-Dec-09 NA 28-Feb-11 Boneya PLC, OWRB/CS/WSG/07/09 CQ LS& TB 129,265.00 Post Actual 30-Sep-08 10-Oct-08 20-Oct-08 24-Oct-08 1-Nov-08 Actual 10-Nov-08 23-Dec-08 24-Aug-09 30-Aug-09 9-Sep-09 19-Sep-09 24-Sep-09 Actual 4-Oct-09 11-Oct-09 125,402.66 5-Dec-09 15-Dec-09 Actual 20-Dec-09 19-Mar-11

Consultancy service for capacity Plan 5-Jan-12 20-Jan-12 30-Jan-12 6-Feb-12 14-Sep-08 16-Feb-12 Plan 28-Feb-12 3-Apr-12 18-Apr-12 24-Apr-12 4-May-12 14-May-12 19-May-12 Plan 29-May-12 5-Jun-12 3-May-12 13-May-12 Plan 23-May-12 NA 8-Jan-13 building & data upadating works (2 Revised 1-May-12 11-May-12 18-May-12 28-May-12 24-Oct-08 5-Jun-12 17-Jun-12 22-Jul-12 6-Aug-12 12-Aug-12 22-Aug-12 1-Sep-12 6-Sep-12 16-Sep-12 23-Sep-12 3-Oct-12 10-Oct-12 23-Jan-13 7-Feb-13 QCBS LS& TB 138,336.50 Post teams), OWMEB/CS/WSG/01- Actual 6-May-12 16-May-12 23-May-12 2-Jun-12 Actual Actual Actual 02/2012

B. Capac ity Building at Wereda Level Plan 30-Jul-12 9-Aug-12 16-Aug-12 26-Aug-12 29-Aug-12 3-Sep-12 15-Sep-12 20-Oct-12 4-Nov-12 10-Nov-12 20-Nov-12 30-Nov-12 5-Dec-12 15-Dec-12 22-Dec-12 1-Jan-13 8-Jan-13 22-Feb-13 NA 9-Mar-13 WaSHCO, WaSH Vol and Care QCBS LS& TB 145253.33 Post Actual Takers Training

Plan 30-Jul-12 9-Aug-12 16-Aug-12 26-Aug-12 29-Aug-12 3-Sep-12 15-Sep-12 20-Oct-12 4-Nov-12 10-Nov-12 20-Nov-12 30-Nov-12 5-Dec-12 15-Dec-12 22-Dec-12 1-Jan-13 8-Jan-13 22-Feb-13 NA 9-Mar-13 Training on WQTK and Computer for CQ LS& TB 47933.60 Post Actual Weredas

1,236,378.43 Plan Total Cost Actual 815,283.26 Contract Implementation

Final Cost Procurement of Goods (Urban) Organisation: Oromia Towns Water Supply and Sewerage Service Entrprises 17.3499 Project/Programme: Urban Water Supply and Sanitation Project Loan No: IDA Credit 3901-ET and IDA Grant 085-ET

Draft Bid Documents, including BASIC DATA Spec Proc Contract Implementation specs and quantities, draft SPN Bidding Period Bid Evaluation Contract Finalization Notice Advert

Description

of of

USD

Date Date Date Date

USD

Final

Press

Qual.

Goods

Actual Actual

Award

Prep & UNDB

Arrival

Method Review On-line

Plan vs. Plan vs.

Number

Package

Opening

Opening

(Internal National Contract Contract

Contract Contract

Gateway

Signature

Estimated Estimated

Inspection

Amount in in Amount

Amount in in Amount

Pre-orPost

Submission Submission

NCB) Date NCB) Acceptance

Lot Number Lot

Procurement

Prioror Post

Bid Closing- Bid Letof Credit

Approvalfor

Bid Eval Rpt Bid

No-objection No-objection

Bid Invitation Invitation Bid by Ex Agency Ex by 4 - 7 wks 1 - 1.5 wks 1.5 - 2 wks 6 to 12 wks 1.5 - 3 wks 1 - 1.5 wks 1 wk 1.5-3 wks Plan 10-Feb-11 20-Feb-11 27-Feb-11 9-Mar-11 23-Apr-11 3-May-11 13-May-11 Plan 20-May-11 27-May-11 1-Jun-11 29-Sep-11 4-Oct-11 Supply of Pipe, fittings OWRB/UWS and Accessories for G/01/2010 1,554,116.77 ICB Post Prior Revised 3-Feb-12 13-Feb-12 20-Feb-12 1-Mar-12 15-Apr-12 25-Apr-12 5-May-12 12-May-12 19-May-12 29-May-12 26-Sep-12 6-Oct-12 Ambo Town Actual 3-Apr-11 13-Apr-11 20-Apr-11 30-Apr-11 14-Jun-11 17-Jul-11 09-Dec.-2011 Actual 1,314,667.03 15-Dec-11 23-Jan-12 29- Mar-12 27-Jul-12 6-Aug-12

Plan 10-Feb-11 20-Feb-11 27-Feb-11 9-Mar-11 23-Apr-11 3-May-11 13-May-11 Plan 20-May-11 27-May-11 1-Jun-11 29-Sep-11 4-Oct-11 Supply of Pipe, fittings OWRB/UWS and Accessories for Bule G/02/2010 2,148,157.96 ICB Post Prior Revised 3-Feb-12 13-Feb-12 20-Feb-12 1-Mar-12 15-Apr-12 25-Apr-12 5-May-12 12-May-12 19-May-12 29-May-12 26-Sep-12 6-Oct-12 Hora Town Actual 11-Jun-22 21-Jun-22 28-Jun-22 30-Apr-11 14-Jun-11 17-Jul-11 09-Dec.-2011 Actual 1,619,650.97 15-Dec-11 23-Jan-12 29- Mar-12 27-Jul-12 6-Aug-12

Plan 10-Feb-11 20-Feb-11 27-Feb-11 6-Mar-11 20-Apr-11 30-Apr-11 10-May-11 Plan 17-May-11 24-May-11 29-May-11 26-Sep-11 1-Oct-11 Supply of Pipe, fittings OWRB/UWS and Accessories for G/03/2010 902,282.94 ICB Post Prior Revised 19-May-12 29-May-12 26-Sep-12 6-Oct-12 Meki Town Actual 6-Apr-11 16-Apr-11 23-Apr-11 30-Apr-11 27-May-11 14-Jun-11 25-Nov-2011 Actual 480,430.33 7-Dec-11 23-Jan-12 29- Mar-12 27-Jul-12 6-Aug-12

Plan 15-Nov-11 25-Nov-11 2-Dec-11 9-Dec-11 23-Jan-12 2-Feb-12 12-Feb-12 Plan 19-Feb-12 26-Feb-12 2-Mar-12 30-Jun-12 5-Jul-12 Supply and Installation OWRB/UWS/ Revised 18-Mar-12 28-Mar-12 4-Apr-12 11-Apr-12 26-May-12 5-Jun-12 15-Jun-12 Revised 22-Jun-12 29-Jun-12 4-Jul-12 1-Nov-12 of Electro-mechanical EM/01/2010 1,372,708.13 ICB Post Prior equipment for Ambo Revised 26-Apr-12 3-Jul-12 10-Jul-12 24-Aug-12 13-Sep-12 23-Sep-12 Revised 30-Sep-12 20-Oct-12 25-Oct-12 22-Feb-13 4-Mar-13 Town Actual Actual

Plan 15-Aug-11 25-Aug-11 1-Sep-11 8-Sep-11 23-Oct-11 2-Nov-11 12-Nov-11 Plan 19-Nov-11 26-Nov-11 1-Dec-11 30-Mar-12 4-Apr-12 Supply and Installation OWRB/UWS/ Revised 15-Apr-12 25-Apr-12 2-May-12 9-May-12 23-Jun-12 3-Jul-12 13-Jul-12 Revised 20-Jul-12 27-Jul-12 1-Aug-12 29-Nov-12 of Electro-mechanical EM/02/2010 684,096.68 ICB Post Prior equipment for Bule Revised 15-Jun-12 30-Jun-12 7-Jul-12 21-Aug-12 10-Sep-12 20-Sep-12 Revised 27-Sep-12 17-Oct-12 22-Oct-12 19-Feb-13 1-Mar-13 Hora Town Actual Actual

Plan 15-Aug-11 20-Aug-11 27-Aug-11 3-Sep-11 18-Oct-11 28-Oct-11 7-Nov-11 Plan 14-Nov-11 21-Nov-11 26-Nov-11 25-Mar-12 30-Mar-12 Supply and Installation OWRB/UWS/ of Electro-mechanical Revised 18-Mar-12 28-Mar-12 4-Apr-12 11-Apr-12 26-May-12 5-Jun-12 15-Jun-12 Revised 22-Jun-12 29-Jun-12 4-Jul-12 1-Nov-12 EM/03/2010 387,599.60 NCB Post Post equipment for Meki Revised 15-Jun-12 30-Jun-12 7-Jul-12 6-Aug-12 26-Aug-12 26-Aug-12 Revised 2-Sep-12 22-Sep-12 27-Sep-12 25-Jan-13 4-Feb-13 Town Actual Actual

Plan 15-Aug-11 20-Aug-11 27-Aug-11 3-Sep-11 18-Oct-11 28-Oct-11 7-Nov-11 Plan 14-Nov-11 21-Nov-11 26-Nov-11 25-Mar-12 30-Mar-12 Supply and Installation OWRB/UWS/ of Electro-mechanical Revised 10-Jul-12 15-Jul-12 22-Jul-12 29-Jul-12 12-Sep-12 22-Sep-12 2-Oct-12 Revised 9-Oct-12 16-Oct-12 21-Oct-12 18-Feb-13 EM/04/2010 247,840.05 NCB Post Post equipment for Chiro Revised 15-Jun-12 30-Jun-12 7-Jul-12 6-Aug-12 26-Aug-12 26-Aug-12 Revised 2-Sep-12 22-Sep-12 27-Sep-12 25-Jan-13 4-Feb-13 Town Actual Actual

Plan 5-Jan-11 10-Jan-11 17-Jan-11 24-Jan-11 10-Mar-11 20-Mar-11 30-Mar-11 Plan 6-Apr-11 13-Apr-11 18-Apr-11 16-Aug-11 21-Aug-11 Supply and Installation OWRB/UWS/ Revised 10-Jul-12 15-Jul-12 22-Jul-12 29-Jul-12 12-Sep-12 22-Sep-12 2-Oct-12 Revised 9-Oct-12 16-Oct-12 21-Oct-12 18-Feb-13 of Electro-mechanical EM/05/2010 260,809.07 NCB Post Post equipment for Bishoftu Revised 15-Jun-12 30-Jun-12 7-Jul-12 6-Aug-12 26-Aug-12 26-Aug-12 Revised 2-Sep-12 22-Sep-12 27-Sep-12 25-Jan-13 4-Feb-13 Town Actual Actual

Plan 5-Jan-11 10-Jan-11 17-Jan-11 24-Jan-11 10-Mar-11 20-Mar-11 30-Mar-11 Plan 6-Apr-11 13-Apr-11 18-Apr-11 16-Aug-11 21-Aug-11 Supply and Installation OWRB/UWS/ Revised 10-Jul-12 15-Jul-12 22-Jul-12 29-Jul-12 12-Sep-12 22-Sep-12 2-Oct-12 Revised 9-Oct-12 16-Oct-12 21-Oct-12 18-Feb-13 of Electro-mechanical EM/06/2010 145,534.63 NCB Post Post equipment for Mojo Revised 15-Jun-12 30-Jun-12 7-Jul-12 6-Aug-12 26-Aug-12 26-Aug-12 Revised 2-Sep-12 22-Sep-12 27-Sep-12 25-Jan-13 4-Feb-13 Town Actual Actual Procurement of Works for Large Towns (Urban) Country/Organization: FDR of /OromiaTowns Water Supply and Sewerage Service Improvement and Expansion Project Project/Programmed: Urban Water Supply and Sanitation Project Loan #: IDA Credit 3901-ET and IDA Grant 085-ET

Basic Data

Number

Package

Description*

Lot

USD

Number

Quantities

Lump sum or Bill of of orsumBill Lump

Prior or Post Review orPost Prior

Estimated Amount in Amount Estimated

ProcurementMethod Pre/Post Qualification Pre/Post List of Contracts Test Water Well Drilling for OWRB\UP BOQ NCB 48,415.26 Post Post Bule Hora Town WD/01/2010

Test Water Well Drilling for OWRB\UP BOQ NCB 24,207.63 Post Post Meki Town WD/02/2010

Test Water Well Drilling for OWRB\UP BOQ NCB 57,637.22 Post Post Chiro & Shashemene WD/03/2010 Towns

Production Water Well OWRB\UP BOQ NCB 277,842.70 Post Post Drilling for Bule Hora Town WD/01/2010

Production Water Well OWRB\UP BOQ NCB 176,080.27 Post Post Drilling for Meki Town WD/02/2010

Production Water Well OWRB\UP BOQ NCB 186,386.72 Post Post Drilling for Bishoftu, WD/02/2010

Production Water Well OWRB\UP BOQ NCB 186,386.72 Post Post Drilling for Modjo WD/05/2010

Production Water Well OWRB\UP BOQ NCB 186,386.72 Post Post Drilling Chiro Towns WD/02/2010

Ambo Town Civil Work OWRB\UC BOQ NCB 2,282,402.37 Post Post Construction WC/01/2010

Bule Hora Town Civil Work OWRB\UC BOQ NCB 1,909,024.51 Post Post Construction WC/02/2010 Meki Town Civil Work OWRB\UC BOQ NCB 684,523.71 Post Post Construction WC/02/2010

Chiro Town Civil Work OWRB\UC BOQ NCB 1,824,133.16 Post Post Construction and Supply of WC/04/2010 Pipe and fittings

BishoftuTown Civil Work OWRB\UC BOQ NCB 2,901,127.63 Post Post Construction & supply of WC/05/2010 Pipe and Fittings

Modjo Town Civil Work OWRB\UC Construction ans Supply of BOQ NCB 1,720,772.34 Post Post WC/06/2010 Pipe & Fittings

NCB - Sebeta Town Water Well BOQ NCB 425,777.67 Post Post SWSSE/WD Drilling F/02/2010

NCB - Sebeta Town Civil Work BOQ NCB 1,954,957.94 Post Post SWSSE/WD Construction F/03/2010

Large towns Total Cost 14,846,062.56 Procurement of Works for Large Towns (Urban) FDR of Ethiopia/OromiaTowns Water Supply and Sewerage Service Improvement and Expansion Project Urban Water Supply and Sanitation Project IDA Credit 3901-ET and IDA Grant 085-ET For All Non ICB, No-objection will be requested from MOWR PMU Draft Bid Documents, including specs and Spec Proc quantities, draft SPN Notice Bidding Period Bid Evaluation

Advert

Plan vs. Actual vs. Plan

Date Date

Gateway

Submission

Bid Eval Rpt Eval Bid

No-objection No-objection

by Ex Agencyby Ex

On-lineUNDB

National PressNational

Bid Invitation Date Invitation Bid

Prep & Submission & Prep Bid Closing-Opening Bid 4 - 7 wks 1 - 1.5 wks 1.5 - 2 wks 1.5 - 2 wks 6 to 12 wks 1.5 - 3 wks Plan 15-Feb-11 20-Feb-11 27-Feb-11 6-Mar-11 5-Apr-11 15-Apr-11 18-Apr-11 Actual 27-Feb-11 4-Mar-11 11-Mar-11 18-Mar-11 7-Apr-11 20-Apr-11 25-Apr-11

Plan 15-Feb-11 20-Feb-11 27-Feb-11 6-Mar-11 5-Apr-11 15-Apr-11 18-Apr-11

Actual 27-Feb-11 4-Mar-11 11-Mar-11 18-Mar-11 7-Apr-11 20-Apr-11 25-Apr-11

Plan 15-Mar-11 20-Mar-11 27-Mar-11 3-Apr-11 3-May-11 13-May-11 16-May-11 Actual 27-Feb-11 4-Mar-11 11-Mar-11 18-Mar-11 7-Apr-11 20-Apr-11 25-Apr-11

Plan 15-Feb-11 20-Feb-11 27-Feb-11 6-Mar-11 5-Apr-11 15-Apr-11 18-Apr-11 Rev-2 Actual 24-May-11 27-May-11 25-Jul-11 26-Aug-11 16-Sep-11 NA

Plan 15-Feb-11 20-Feb-11 27-Feb-11 6-Mar-11 5-Apr-11 15-Apr-11 18-Apr-11 Actual 24-May-11 27-May-11 25-Jul-11 26-Aug-11 16-Sep-11

Plan 15-Feb-11 15-Feb-11 22-Feb-11 1-Mar-11 31-Mar-11 10-Apr-11 20-Apr-11 Revised 20-Feb-12 Rev-2 Actual 20-Sep-11 28-Sep-11 23-Dec-11 23-Jan-12 15-Feb-12

Plan 15-Feb-11 15-Feb-11 22-Feb-11 1-Mar-11 31-Mar-11 10-Apr-11 20-Apr-11 Revised 20-Feb-12 Rev-2 Actual 20-Sep-11 28-Sep-11 23-Dec-11 23-Jan-12 15-Feb-12

Revised 20-Feb-12 Rev-2 Actual 20-Sep-11 28-Sep-11 23-Dec-11 23-Jan-12 15-Feb-12

Plan 1-Oct-10 1-Oct-10 8-Oct-10 15-Oct-10 14-Nov-10 24-Nov-10 4-Dec-10 Rev-2 Actual 3-Feb-11 1-Apr-11 19-May-11

Plan 1-Mar-11 1-Mar-11 8-Mar-11 15-Mar-11 14-Apr-11 24-Apr-11 4-May-11 Rev-2 Actual 3-Feb-11 1-Apr-11 26-Apr-11

Plan 1-Mar-11 1-Mar-11 8-Mar-11 15-Mar-11 14-Apr-11 24-Apr-11 4-May-11 Rev-2 Actual 24-Mar-11 2-May-11 19-May-11

Plan 1-Apr-11 6-Apr-11 13-Apr-11 20-Apr-11 20-May-11 30-May-11 2-Jun-11 Revised 20-Feb-12 31-Mar-12 7-Apr-12 10-Apr-12 Rev-2 Actual

Plan 1-Apr-11 6-Apr-11 13-Apr-11 20-Apr-11 20-May-11 30-May-11 2-Jun-11 Revised 20-Feb-12 31-Mar-12 7-Apr-12 10-Apr-12 Rev-2 5-Jun-12 15-Jun-12 25-Jun-12 25-Jul-12 4-Aug-12 Actual

Plan 1-Apr-11 6-Apr-11 13-Apr-11 20-Apr-11 20-May-11 30-May-11 2-Jun-11 Revised 20-Feb-12 31-Mar-12 7-Apr-12 10-Apr-12 Rev-2 Actual

Plan 25-May-10 4-Jun-10 11-Jun-10 28-Jun-10 28-Jul-10 18-Aug-10 28-Aug-10 Revised plan Actual 2-Aug-11 5-Sep-11 15-Aug-10 22 Nov 11

Plan 15-Aug-10 25-Aug-10 1-Sep-10 1-Sep-10 1-Oct-10 22-Oct-10 1-Nov-10 Revised plan Actual 17.3499

For All Non ICB, No-objection will be requested from MOWR PMU

Contract Finalization Contract Implementation

USD Date Date

Final

Award

Plan vs. Actual vs. Plan

Contract Contract

Advance

Payment

Signature

Substantial

Completion

Acceptance

Mobilization Contract Amount in in Contract Amount 1 wk 1.5-3 wks Plan 23-Apr-11 28-Apr-11 8-May-11 7-Jul-11 27-Apr-12 Actual 44,957.03 2-Jul-10 30-Jul-10 9-Aug-10 7-Nov-10 30-Jul-11

Plan 23-Apr-11 28-Apr-11 8-May-11 7-Jul-11 6-Jul-12

Actual 18,545.81 2-Jul-10 30-Jul-10 9-Aug-10 28-Oct-10 30-Jul-11

Plan 21-May-11 26-May-11 5-Jun-11 4-Aug-11 3-Aug-12 Actual 71,397.64 2-Jul-10 30-Jul-10 9-Aug-10 28-Oct-10 29-Feb-11

Plan 23-Apr-11 28-Apr-11 8-May-11 7-Jul-11 17-Jul-11 Rev-2 15-Jun-12 14-Aug-12 24-Aug-12 Actual 207,065.62 06-Oct-11 21-Nov-11

Plan 23-Apr-11 28-Apr-11 8-May-11 7-Jul-11 17-Jul-11 Actual 92,907.61 6-10-11 28-Oct-11 7-Nov-11 26-Jan-12 25-Jan-13

Plan 25-Apr-11 30-Apr-11 10-May-11 9-Jul-11 8-Jul-12 Revised 24-Feb-12 15-Mar-12 25-Mar-12 24-May-12 3-Jun-12 Rev-2 29-Aug-12 29-Aug-13 Actual 948,354.46 26-Apr-12 9-may-12 19-May-12

Plan 25-Apr-11 30-Apr-11 10-May-11 9-Jul-11 8-Jul-12 Revised 24-Feb-12 15-Mar-12 25-Mar-12 24-May-12 24-May-13 Rev-2 29-Aug-12 29-Aug-13 Actual 948,354.46 26-Apr-12 9-May-12 19-May-12

Revised 24-Feb-12 15-Mar-12 25-Mar-12 24-May-12 24-May-13 Rev-2 10-Jun-12 15-Jun-12 30-Jun-12 29-Aug-12 8-Sep-12 Actual

Plan 9-Dec-10 14-Dec-10 24-Dec-10 16-Jun-12 13-Dec-12 Rev-2 10-Jun-12 15-Jun-12 30-Jun-12 29-Aug-12 8-Sep-12 Actual 2,459,650.61

Plan 9-May-11 14-May-11 24-May-11 17-Jun-12 14-Dec-12 Rev-2 10-Jun-12 9-Aug-12 19-Aug-12 Actual 1,909,024.51 15-Jul-11

Plan 9-May-11 14-May-11 24-May-11 17-Jun-12 14-Dec-12 Rev-2 10-Jun-12 15-Jun-12 30-Jun-12 29-Aug-12 8-Sep-12 Actual 684,523.71

Plan 7-Jun-11 12-Jun-11 22-Jun-11 15-Aug-12 11-Feb-13 20-Apr-12 30-Apr-12 15-May-12 10-Jan-13 10-Jan-14 Rev-2 30-Mar-14 Actual 2,910,896.99 30-May-12 8-Jun-2012 18-Jun-12 30-Mar-13

Plan 7-Jun-11 12-Jun-11 22-Jun-11 15-Aug-12 11-Feb-13 20-Apr-12 30-Apr-12 15-May-12 10-Jan-13 10-Jan-14 Rev-2 11-Aug-12 16-Aug-12 31-Aug-12 30-Oct-12 30-Oct-13 Actual

Plan 7-Jun-11 12-Jun-11 22-Jun-11 15-Aug-12 11-Feb-13 20-Apr-12 30-Apr-12 15-May-12 10-Jan-13 10-Jan-14 Rev-2 28-Mar-13 28-Mar-14 Actual 3,059,265.15 30-May-12 11-Jun-12 21-Jun-12

Plan 7-Sep-10 17-Sep-10 2-Oct-10 27-Sep-11 26-Sep-12 Revised 05 Dec 11 12/Dec/11 10-Apr-12 10-Apr-13 plan Actual 631,006.98 30/Nov/11

Plan 11-Nov-10 21-Nov-10 6-Dec-10 1-Dec-11 30-Nov-12 Revised 29/Sep/12 29/Sep/13 plan Actual 1,998,071.74 16-Mar-11 23-Mar-11 8-Apr-11

15,984,022.31 Contract Implementation Contract

Final Cost

Procurement of Consultancy Services (Urban) Country/Organization: FDR of Ethiopia/OromiaTowns Water Supply and Sewerage Service Improvement and Expansion Project 17.3499 Project/Programmed: Urban Water Supply and Sanitation Project

Loan #: IDA Credit 3901-ET and IDA Grant 085-ET

Date Date Date Cost

Final

Actual

Prep Prep & Report

(T) (F)/

in in USD

Agency

shortlist

Plan Plan vs.

Opening Opening

Contract Contract Contract

Advance Payment

Financial

Gateway/

Signature

Proposals

Estimated

Report (T)

Evaluation Evaluation

Report (T)

Contract Id

Submission Submission

Time-Based Mobilization

Description* Submission/

Lumpsum or Draft Report Final Report

No-objection No-objection No-objection Negotiations

Report (T) (F)

Opening Opening Date

On-line On-line UNDB

Plan Plan Vs Actual Invitation Date

Plan Plan vs. Actual

National Press

Amount in USD Contract Award

Report (T) (F) &

Negotiated Draft Negotiated Draft

Submission Eval

Lead-time before

Contract Amount

Selection Method Evaluation (T) (F) No-objection Eval No-objection Eval

Prior/Post Review Submission by Ex List of Contracts 3 - 6 wks 1 - 2 wks 1 - 1.5 wks 2 wks 1 - 2 wks 4 to 12 wks 2 - 3 wks 0.5 - 2 wks 2 wks 1 - 2 wks 2 wks 1 - 2 wks 1 - 2 wks 1 wk 1 - 3 wks SABA+ARMA for Adama ICB-UWSSP- Plan 1-May-08 11-May-08 18-May-08 23-May-08 7-Jun-08 17-Jun-08 Plan 24-Jun-08 9-Jul-08 19-Jul-08 26-Jul-08 31-Jul-08 3-Aug-08 Plan 10-Aug-08 17-Aug-08 24-Aug-08 16-Sep-08 21-Sep-08 Plan 21-Jul-10 21-Jun-10 21-Jul-10 &Assela (to step 2a) and QCBS LT/06-4 LS & TB 178,675.38 Post Ambo & Bule Hora (to Step Actual 12-Mar-08 3-Apr-08 13-Apr-08 18-Apr-08 29-Apr-08 NA Actual 1-May-08 15-May-08 4-Jun-08 2-Jul-08 6-Jul-08 15-Jul-08 Actual 18-Jul-08 28-Jul-08 4-Aug-08 199,650.43 4-Aug-08 14-Aug-08 Actual 24-Aug-08 30- Mar-13 /S002/2009 3) Meteferia for Bishftu, Mojo ICB-UWSSP- Plan 1-May-08 11-May-08 16-May-08 6-Jun-08 21-Jun-08 1-Jul-08 Plan 8-Jul-08 5-Aug-08 15-Aug-08 22-Aug-08 29-Aug-08 8-Sep-08 Plan 18-Sep-08 23-Sep-08 28-Sep-08 16-Sep-08 5-Jan-00 Plan 20-Jan-00 15-Dec-00 14-Jan-01 & Chiro (to Step 2a) and for QCBS LT/06-4 LS 41,553.90 Post Actual 12-Mar-08 3-Apr-08 13-Apr-08 18-Apr-08 29-Apr-08 NA Actual 1-May-08 15-May-08 4-Jun-08 2-Jul-08 6-Jul-08 15-Jul-08 Actual 18-Jul-08 28-Jul-08 4-Aug-08 41,553.90 30-Jun-12 Actual 10-Jul-12 Meki (to Step 3) /S002/2009 Consultancy Service for Plan 21-Aug-10 31-Aug-10 5-Sep-10 26-Sep-10 11-Oct-10 21-Oct-10 Plan 28-Oct-10 25-Nov-10 5-Dec-10 12-Dec-10 19-Dec-10 29-Dec-10 Plan 8-Jan-11 13-Jan-11 18-Jan-11 25-Jan-11 30-Jan-11 Plan 9-Feb-11 7-Oct-11 6-Nov-11 step 2b and Step 3 for LCB-UWSSP- QCBS LS 163,799.91 Post Bishftu, Chiro and Mojo 1/2010 Actual 19-Jul-11 28-Jul-11 NA 20-Aug-11 10-Sep-11 NA Actual 22-Oct-11 15-Dec-11 10-Apr-12 30-Mar-12 8-Apr-12 9-Apr-12 Actual 15-Apr-12 30-Apr-12 10-May-12 189,369.97 20-Jun-12 30-June-12 Actual 10-Jul-12 28-Feb-13 30- Mar-13 towns Plan 7-Nov-11 17-Nov-11 24-Dec-11 12-Jan-12 28-Jan-12 11-Feb-12 Plan 18-Feb-12 17-Mar-12 27-Mar-12 3-Apr-12 10-Apr-12 20-Apr-12 Plan 30-Apr-12 5-May-12 10-May-12 17-May-12 22-May-12 Plan Environmental and Social LCB-UWSSP- Revised 10-Jun-12 10-Jul-12 25-Jul-12 1-Aug-12 9-Aug-12 24-Aug-12 Revised 8-Sep-12 23-Sep-12 30-Sep-12 20-Oct-12 10-Nov-12 8-Feb-13 10-Mar-13 Impact Assessment for QCBS LT/06- LS 8,645.59 Post Ambo town 04/SOO/2009 Actual 8-Dec-11 18-Dec-11 NA 15-Jan-12 1-Feb-12 NA Actual 21-Feb-12 21-Mar-12 30-Mar-12 2-May-12 5-May-12 7-May-12 Actual 23-Apr-12 8-May-12 13-May-12 11,815.63 16-May-12 24-May-12 Actual 29-May-12

Plan 7-Nov-11 17-Nov-11 24-Dec-11 12-Jan-12 28-Jan-12 11-Feb-12 Plan 18-Feb-12 17-Mar-12 27-Mar-12 3-Apr-12 10-Apr-12 20-Apr-12 Plan 30-Apr-12 5-May-12 10-May-12 17-May-12 22-May-12 Plan Environmental and Social LCB-UWSSP- Revised 10-Jun-12 10-Jul-12 25-Jul-12 1-Aug-12 9-Aug-12 24-Aug-12 Revised 8-Sep-12 23-Sep-12 30-Sep-12 20-Oct-12 10-Nov-12 8-Feb-13 10-Mar-13 Impact Assessment for Bule QCBS LT/06- LS 8,645.59 Post Hora 04/SOO/2009 Actual 8-Dec-11 18-Dec-11 NA 15-Jan-12 1-Feb-12 NA Actual 21-Feb-12 21-Mar-12 30-Mar-12 2-May-12 5-May-12 7-May-12 Actual 23-Apr-12 8-May-12 13-May-12 13,355.98 16-May-12 24-May-12 Actual 29-May-12 Procurement of Goods Organisation: Oromia Towns Water Supply and Sewerage Service Entrprises 17.3499 Project/Programme: Urban Water Supply and Sanitation Project 17.54 Loan No: IDA Credit 3901-ET and IDA Grant 085-ET REVISED!!! Draft Bid Documents, For All Non ICB, No-objection will be requested from MOWR PMU Spec Proc BASIC DATA including specs and Contract Implementation Notice Bidding Period Bid Evaluation Contract Finalization quantities, draft SPN

Advert

Description*

Date Date

USD

Final

Credit

Goods

Award

in USD

Method

Number

Package

Opening

Gateway

Signature

Arrival of Arrival

Inspection

Acceptance

Submission

Lot Lot Number

Procurement Procurement Bid Closing-

No-objection No-objection

Bid Eval Rpt

by by Ex Agency Contract Date Contract Date

On-line UNDB On-line Let Opening of

National National Press

Plan vs. Actual Plan vs. Actual

Pre-or PostPre-or Qual.

Estimated Estimated Amount

Bid Invitation Date

Prep Prep & Submission

Contract AmountContract in Prior Prior or Post Review 4 - 7 wks 1 - 1.5 wks 1.5 - 2 wks 6 to 12 wks 1.5 - 3 wks 1 - 1.5 wks 1 wk 1.5-3 wks Plan 5-Apr-11 15-Apr-11 22-Apr-11 29-Apr-11 29-May-11 13-Jun-11 23-Jun-11 Plan 30-Jun-11 15-Jul-11 14-Aug-11 12-Dec-11 17-Dec-11 OWMEB/UW Revised 25-Feb-12 Revised 3-Mar-12 18-Mar-12 17-Apr-12 15-Aug-12 20-Aug-12 Supply of Generating Sets for 8 small S/EM/01/2011 67,320.27 NCB Post Post Rev-2 2-Apr-12 9-Apr-12 9-May-12 24-May-12 3-Jun-12 Rev-2 10-Jun-12 20-Jun-12 20-Jul-12 17-Nov-12 27-Nov-12 Towns Actual 16-Nov-11 20-Nov-11 4-Dec-11 15-Jan-12 15-Feb-12 Actual 125,565.96 13-Mar-12 4-May-12 2-Aug-12 7-Aug-12

Plan 15-May-11 25-May-11 1-Jun-11 8-Jun-11 8-Jul-11 23-Jul-11 2-Aug-11 Plan 9-Aug-11 24-Aug-11 23-Sep-11 21-Jan-12 26-Jan-12 OWMEB/UW Revised 25-Feb-12 Revised 3-Mar-12 18-Mar-12 17-Apr-12 15-Aug-12 20-Aug-12 Supply of pumps for 16 small Towns S/EM/02/2011 128,185.18 NCB Post Post Rev-2 11-Mar-12 21-Mar-12 28-Mar-12 4-Apr-12 4-May-12 19-May-12 3-Jun-12 Rev-2 10-Jun-12 20-Jun-12 20-Jul-12 17-Nov-12 27-Nov-12 Actual 16-Nov-11 20-Nov-11 4-Dec-11 15-Jan-12 15-Feb-12 Actual 229,802.48 19-May-12 29-May-12 27-Aug-12 1-Sep-12

OWMEB/UW Plan 15-Jul-11 5-Jan-12 Plan 30-Feb-12 Revised 29-May-12 8-Jun-12 6/15/2012 15-Jul-12 25-Jul-12 Rev-2 1-Aug-12 11-Aug-12 26-Aug-12 24-Dec-12 3-Jan-13 Connection 8 small towns to EEPCO Grid S/EM/03/2011 75,158.93 NCB Post Post Actual Actual

OWMEB/UW Plan 15-Mar-12 25-Mar-12 24-Apr-12 9-May-12 Plan 16-May-12 30-May-12 29-Jul-12 Supply of compueters, laptop and printers S/OEQ/01/201 Revised 29-May-12 8-Jun-12 6/15/2012 15-Jul-12 25-Jul-12 Rev-2 1-Aug-12 11-Aug-12 26-Aug-12 24-Dec-12 3-Jan-13 32,839.22 NCB Post Post for 24 small towns 2 Actual Actual

OWMEB/UW Plan 20-Mar-12 30-Mar-12 29-Apr-12 14-May-12 Plan 21-May-12 4-Jun-12 19-Jun-12 3-Aug-12 13-Aug-12 Revised 29-May-12 8-Jun-12 15-Jun-12 15-Jul-12 25-Jul-12 Rev-2 1-Aug-12 11-Aug-12 26-Aug-12 24-Dec-12 3-Jan-13 Supply of motor bike for 24 small towns S/MB/02/2012 113,568.99 NCB Post Post Actual Actual

OWMEB/UW Plan 20-Mar-12 30-Mar-12 29-Apr-12 14-May-12 Plan 21-May-12 4-Jun-12 3-Aug-12 Supply of maintenance tools for 24 small Revised 29-May-12 8-Jun-12 15-Jun-12 15-Jul-12 25-Jul-12 Rev-2 1-Aug-12 11-Aug-12 26-Aug-12 24-Dec-12 3-Jan-13 S/MT/03/2012 95,781.07 NCB Post Post towns Actual Actual

Total Cost For Goods for Small Towns 512,853.67 355,368.44 Procurement of Works Country/Organization: FDR of Ethiopia/OromiaTowns Water Supply and Sewerage Service Improvement and Expansion Project 17.3499 Project/Programmed: Urban Water Supply and Sanitation Project Loan #: IDA Credit 3901-ET and IDA Grant 085-ET

Draft Bid Documents, Basic Data For All Non ICB, No-objection will be requested from MOWR PMU Contract Finalization Contract Implementation including specs and

Bidding Period Bid Evaluation

Number

Package

Description*

Lot

Date Date Date Cost

USD USD

Final Final Advert

Bid Submission Award

Number

Contract Contract

Advance

Payment

Signature Plan Plan vs. Actual

Quantities Bid Closing- No-objection

Substantial

Completion

Mobilization Acceptance

List of Contracts No-objection Invitation Bid Eval by Ex Agency

Opening Date Plan vs. Actual Spec Proc Notice

Prep &Prep Submission Date Rpt

Lump sum Lump Billor of Contract Amount in

Prior or Postor Prior Review

Procurement Method Procurement

Estimated Amount in Pre/Post Qualification A. Drilling A.1. Completed Plan 15-Sep-10 15-Sep-10 22-Sep-10 29-Sep-10 29-Oct-10 8-Nov-10 18-Nov-10 Plan 23-Nov-10 28-Nov-10 8-Dec-10 6-Feb-11 6-Feb-12 0.00 Production Water Well OWRB\MDTF\ BOQ NCB 176,178.48 Post Post Actual 2-Jan-10 4-Jan-10 12-Feb-11 14-Mar-11 8-Apr-11 18-Apr-11 Actual 38,386.58 24-May-11 28-Jun-11 25-Dec-11 24-Dec-12 Drilling for Guliso Town UDW/02/2010 Production Water Well Plan 1-Aug-10 1-Aug-10 8-Aug-10 15-Aug-10 14-Sep-10 24-Sep-10 4-Oct-10 Plan 9-Oct-10 14-Oct-10 24-Oct-10 ######## 2-Jan-11 0.00 OWRB\MDTF\ Drilling for Bokoji, Bake & BOQ NCB 72,622.90 Post Post Actual 20-Nov-09 22-Nov-09 13-Dec-09 13-Jan-10 25-Jan-10 27-Jan-10 Actual 122,091.60 08-Feb-10 19-Feb-10 18-May-10 18-May-11 UDW/01/2010 Hirna Towns Production Water Well Plan 15-Sep-10 15-Sep-10 22-Sep-10 29-Sep-10 29-Oct-10 8-Nov-10 18-Nov-10 Plan 23-Nov-10 28-Nov-10 8-Dec-10 6-Feb-11 16-Feb-11 0.00 OWRB/MDTF/ Drilling for Bure & Yanfa BOQ NCB 72,622.90 Post Post Actual 2-Jan-10 4-Jan-10 12-Feb-11 14-Mar-11 8-Apr-11 Actual 73,402.73 24-May-11 30-Jun-11 25-Dec-11 24-Dec-12 DW/02/2/2010 Town Production Water Well Plan 15-Sep-10 15-Sep-10 22-Sep-10 29-Sep-10 29-Oct-10 8-Nov-10 18-Nov-10 Plan 23-Nov-10 28-Nov-10 8-Dec-10 6-Feb-11 16-Feb-11 0.00 OWRB\MDTF\ Drilling for Olonkomi BOQ NCB 24,207.63 Post Post Actual 20-Nov-09 22-Nov-09 13-Dec-09 13-Jan-10 25-Jan-10 27-Jan-10 Actual 40,697.20 08-Feb-10 19-Feb-10 18-May-10 18-May-11 UDW/02/2010 Towns Plan 20-Feb-11 23-Feb-11 2-Mar-11 9-Mar-11 8-Apr-11 18-Apr-11 22-Apr-11 Plan 27-Apr-11 2-May-11 12-May-11 1-Jun-11 11-Jun-11 0.00 Production Water Well OWME/MDTF/ BOQ NCB 46,109.78 Post Post Actual 26-Feb-11 02-Mar-11 12-Feb-11 14-Mar-11 8-Apr-11 30-Dec-11 Actual 167,170.76 24-May-11 30-Jun-11 25-Dec-11 24-Dec-12 Drilling for Magado Town DW/06/1/2010 A.2. Ongoing Plan 20-Feb-11 23-Feb-11 2-Mar-11 9-Mar-11 8-Apr-11 18-Apr-11 22-Apr-11 Plan 27-Apr-11 10-Feb-12 20-Feb-12 11-Mar-12 21-Mar-12 0.00 OWME\MDTF\ Production Water Well Rev-2 20-Feb-11 23-Feb-11 2-Mar-11 12-Apr-12 12-May-12 22-May-12 26-May-12 Rev-2 31-May-12 10-Jun-12 20-Jun-12 10-Jul-12 30-Jul-12 DW&SHW/02/ BOQ NCB 57,637.22 Post Post Drilling for Dabaso Town Actual 26-Feb-11 02-Mar-11 1-Dec-11 28-Dec-11 05-Jan-12 08-Jan-12 Actual 57,637.22 03-Feb-12 03/2010 B. Civil Work B.1. Completed OWRB\UWSS Plan 1-Apr-09 11-Apr-09 18-Apr-09 25-Apr-09 25-May-09 4-Jun-09 14-Jun-09 Plan 19-Jun-09 13-Oct-09 23-Oct-09 21-Apr-10 21-Apr-11 91,066.81 Ali Town Civil Work CWC/005/7/20 BOQ NCB 91,066.81 Post Post Actual 13-May-09 1-Jun-09 20-Jun-09 21-Jul-09 28-Jul-09 28-Jul-09 Actual 64,285.38 31-Jul-09 13-Oct-09 12-May-11 11-May-12 Construction 08 OWRB\UWSS Plan 1-Apr-09 11-Apr-09 18-Apr-09 25-Apr-09 25-May-09 4-Jun-09 14-Jun-09 Plan 19-Jun-09 20-Aug-09 30-Aug-09 24-Oct-10 24-Oct-11 135,000.00 Atinago Town Civil Work CWC/005/1/20 BOQ NCB 135,000.00 Post Post Actual 13-May-09 1-Jun-09 20-Jun-09 21-Jul-09 28-Jul-09 28-Jul-09 Actual 23,496.86 31-Jul-09 20-Aug-09 17-Jan-10 17-Jan-11 Construction 08 OWRB\UWSS Plan 1-Apr-09 11-Apr-09 18-Apr-09 25-Apr-09 25-May-09 4-Jun-09 14-Jun-09 Plan 19-Jun-09 20-Aug-09 30-Aug-09 24-Oct-10 24-Oct-11 105,000.00 BaboTown Civil Work CWC/005/2/20 BOQ NCB 105,000.00 Post Post Actual 13-May-09 1-Jun-09 20-Jun-09 21-Jul-09 28-Jul-09 28-Jul-09 Actual 17,518.91 30-Jul-09 20-Aug-09 18-Sep-10 18-Sep-11 Construction 08 Plan 20-Jan-09 30-Jan-09 6-Feb-09 13-Feb-09 15-Mar-09 25-Mar-09 4-Apr-09 Plan 9-Apr-09 9-Apr-09 19-Apr-09 13-Jun-10 10-Dec-10 105,000.00 Busa Town Civil Work OWRB\UWSS BOQ NCB 105,000.00 Post Post Actual 13-May-09 1-Jun-09 20-Jun-09 21-Jul-09 28-Jul-09 28-Jul-09 Actual 62,834.68 31-Jul-09 9-Apr-09 07-Dec-09 7-Dec-10 Construction CWC/004/2008 Plan 20-Jan-09 30-Jan-09 6-Feb-09 13-Feb-09 15-Mar-09 25-Mar-09 4-Apr-09 Plan 9-Apr-09 9-Apr-09 19-Apr-09 13-Jun-10 13-Jun-11 105,000.00 Dilala Town Civil Work OWRB\UWSS BOQ NCB 105,000.00 Post Post Actual 06-Feb-09 14-Feb-09 02-Mar-09 3-Mar-09 18-Mar-09 19-Mar-09 Actual 62,834.68 25-Mar-09 9-Apr-09 07-Dec-09 7-Dec-10 Construction CWC/004/2008 OWRB\UWSS Plan 20-Mar-09 30-Mar-09 6-Apr-09 13-Apr-09 13-May-09 23-May-09 2-Jun-09 Plan 7-Jun-09 1-Jun-09 4-Sep-09 29-Oct-10 29-Oct-11 105,000.00 Ejere Town Civil Work CWC/005/4/20 BOQ NCB 105,000.00 Post Post Actual 13-May-09 1-Jun-09 20-Jun-09 21-Jul-09 28-Jul-09 28-Jul-09 Actual 31,320.14 30-Jul-09 25-Aug-09 24-Oct-10 24-Oct-11 Construction 08 OWRB\UWSS Plan 20-Mar-09 30-Mar-09 6-Apr-09 13-Apr-09 13-May-09 23-May-09 2-Jun-09 Plan 7-Jun-09 12-Jun-09 22-Jun-09 ######## 16-Aug-11 36,311.45 Kombolcha Town Civil CWC/005/5/20 BOQ NCB 36,311.45 Post Post Actual 13-May-09 1-Jun-09 20-Jun-09 21-Jul-09 28-Jul-09 28-Jul-09 Actual 42,281.47 30-Jul-09 28-Aug-09 12-Oct-10 12-Oct-11 Work Construction 08 OWRB\UWSS Plan 20-Mar-09 30-Mar-09 6-Apr-09 13-Apr-09 13-May-09 23-May-09 2-Jun-09 Plan 7-Jun-09 1-Jun-09 21-Aug-09 15-Oct-10 15-Oct-11 47,550.71 Segno Gabaya Town Civil CWC/005/6/20 BOQ NCB 47,550.71 Post Post Actual 16-Feb-09 29-Feb-09 01-Apr-09 05-My-09 28-May-09 06-Jun-09 Actual 77,108.80 30-Jul-09 11-Aug-09 22-Sep-10 22-Sep-11 Work Construction 08 OWRB\UWSS Plan 1-Apr-09 11-Apr-09 18-Apr-09 25-Apr-09 25-May-09 4-Jun-09 14-Jun-09 Plan 19-Jun-09 20-Aug-09 30-Aug-09 26-Feb-10 26-Feb-11 75,850.58 Solomo Town Civil Work CWC/005/7/20 BOQ NCB 75,850.58 Post Post Actual 16-Feb-09 29-Feb-09 01-Apr-09 05-My-09 28-May-09 06-Jun-09 Actual 37,006.21 30-Jul-09 20-Aug-09 09-Dec-10 9-Dec-11 Construction 08 Procurement of Works Country/Organization: FDR of Ethiopia/OromiaTowns Water Supply and Sewerage Service Improvement and Expansion Project 17.3499 Project/Programmed: Urban Water Supply and Sanitation Project Loan #: IDA Credit 3901-ET and IDA Grant 085-ET

Draft Bid Documents, Basic Data For All Non ICB, No-objection will be requested from MOWR PMU Contract Finalization Contract Implementation including specs and

Bidding Period Bid Evaluation

Number

Package Description*

B.2. Ongoing Lot

Date Date Date Cost

USD USD

Final Final

Advert Award

Number

Contract Contract Advance

Plan 25-Feb-11 28-Feb-11 7-Mar-11 14-Mar-11 13-Apr-11 23-Apr-11 27-Apr-11 Plan 2-May-11 7-May-11 10-Jul-11Payment 21-Jan-12 19-Jul-12 369,445.26

Signature

Plan Plan vs. Actual

Quantities

Substantial Completion

BakeTown Civil Work OWME\MDTF\ Mobilization

Acceptance No-objection

BOQ NCB 369,445.26 Post Post Actual 26-Feb-11by Ex Agency 02-Mar-11 19-Mar-11 25-Apr-11 24-May-11 26-May-11 Actual 196,918.23 02-Jun-11 30-Jun-11 10-Jul-11 21-Jan-12 19-Jul-12

Construction UCWC/01/2011 Plan vs. Actual

Spec Proc Notice

Prep &Prep Submission

Lump sum Lump Billor of Contract Amount in

Prior or Postor Prior Review

Procurement Method Procurement Estimated Amount in Pre/Post Qualification Plan 25-Feb-11 28-Feb-11 7-Mar-11 14-Mar-11 13-Apr-11 23-Apr-11 27-Apr-11 Plan 2-May-11 7-May-11 10-Jul-11 21-Jan-12 19-Jul-12 320,425.08 Olonkomi Town Civil Work OWME\MDTF\ BOQ NCB 320,425.08 Post Post Actual 26-Feb-11 02-Mar-11 19-Mar-11 25-Apr-11 24-May-11 26-May-11 Actual 148,708.35 02-Jun-11 30-Jun-11 10-Jul-11 21-Jan-12 19-Jul-12 Construction UCWC/02/2011 Plan 10-Mar-11 13-Mar-11 20-Mar-11 27-Mar-11 26-Apr-11 6-May-11 10-May-11 Plan 15-May-11 20-May-11 5-Aug-11 16-Feb-12 14-Aug-12 328,532.15 Bokoji Town Civil Work OWME\MDTF\ BOQ NCB 328,532.15 Post Post Actual 26-Feb-11 02-Mar-11 19-Mar-11 25-Apr-11 24-May-11 26-May-11 Actual 308,792.51 07-Jul-11 26-Jul-11 5-Aug-11 16-Feb-12 14-Aug-12 Construction UCWC/03/2011 Plan 1-Oct-10 4-Oct-10 11-Oct-10 18-Oct-10 17-Nov-10 27-Nov-10 1-Dec-10 Plan 6-Dec-10 11-Dec-10 1-Jul-11 12-Jan-12 10-Jul-12 417,167.35 Hirna Town Civil Work OWME\MDTF\ BOQ NCB 417,167.35 Post Post Actual 26-Feb-11 02-Mar-11 19-Mar-11 25-Apr-11 24-May-11 26-May-11 Actual 298,880.81 2-Jun-11 21-Jun-11 1-Jul-11 12-Jan-12 10-Jul-12 Construction UCWC/04/2011 Plan 1-Sep-10 4-Sep-10 11-Sep-10 18-Sep-10 18-Oct-10 28-Oct-10 1-Nov-10 Plan 6-Nov-10 11-Nov-10 6-Jul-11 17-Jan-12 15-Jul-12 516,160.80 Guliso Town Civil Work OWME\MDTF\ BOQ NCB 516,160.80 Post Post Actual 26-Feb-11 02-Mar-11 19-Mar-11 25-Apr-11 24-May-11 26-May-11 Actual 411,878.79 2-Jun-11 21-Jun-11 6-Jul-11 17-Jan-12 15-Jul-12 Construction UCWC/05/2011 Plan 1-Sep-10 4-Sep-10 11-Sep-10 18-Sep-10 18-Oct-10 28-Oct-10 1-Nov-10 Plan 6-Nov-10 11-Nov-10 21-Nov-10 ######## 14-May-12 383,339.31 Revised 19-Feb-12 22-Feb-12 Revised 27-Feb-12 3-Mar-12 13-Mar-12 8-Mar-13 4-Sep-13 383,339.31 Bure Town Civil Work OWME\MDTF\ BOQ NCB 383,339.31 Post Post Rev-2 2-Apr-12 5-Apr-12 12-Apr-12 19-Apr-12 19-May-12 29-May-12 1-Jun-12 Rev-2 5-Jun-12 15-Jun-12 25-Jun-12 ######## 22-Dec-13 Construction UCWC/06/2011 Actual 12-Dec-11 20-Dec-11 3-Dec-11 2-Jan-12 7-Feb-12 8-Mar-12 11-Mar-12 Actual 279,355.63 14-Mar-12 22 -Mar-12 1-Apr-12 ######## 17-Mar-13

Plan 1-Mar-11 4-Mar-11 11-Mar-11 18-Mar-11 7-Feb-12 17-Feb-12 21-Feb-12 Plan 26-Feb-12 2-Mar-12 12-Mar-12 7-Mar-13 3-Sep-13 386,169.37 Revised 19-Feb-12 22-Feb-12 Revised 27-Feb-12 3-Mar-12 13-Mar-12 8-Mar-13 4-Sep-13 Yanfa Town Civil Work OWME\MDTF\ BOQ NCB 386,169.37 Post Post Rev-2 2-Apr-12 5-Apr-12 12-Apr-12 19-Apr-12 19-May-12 29-May-12 1-Jun-12 Rev-2 5-Jun-12 15-Jun-12 25-Jun-12 ######## 22-Dec-13 Construction UCWC/07/2011 Actual 12-Dec-11 20-Dec-11 3-Dec-11 2-Jan-12 7-Feb-12 8-Mar-12 11-Mar-12 Actual 279,355.63 14-Mar-12 22 -Mar-12 1-Apr-12 ######## 17-Mar-13

Plan 1-Apr-11 4-Apr-11 11-Apr-11 18-Apr-11 18-May-11 28-May-11 1-Jun-11 Plan 6-Jun-11 11-Jun-11 4-Feb-12 ######## 13-Feb-13 239,194.46 Megado Town Civil Work OWME\MDTF\ BOQ NCB 239,194.46 Post Post Actual 06-Dec-11 10-Dec-11 25-Dec-11 28-Nov-11 05-Jan-12 06-Jan-12 Actual 235,673.95 13-Jan-12 25-Jan-12 4-Feb-12 7-Aug-12 3-Feb-13 Construction UCWC/08/2011 Plan 1-Apr-11 4-Apr-11 11-Apr-11 18-Apr-11 18-May-11 28-May-11 1-Jun-11 Plan 6-Jun-11 11-Jun-11 10-Jul-11 4-Jul-12 31-Dec-12 569,972.87 Surupha Town Civil Work OWME\MDTF\ BOQ NCB 569,972.87 Post Post Actual 26-Feb-11 02-Mar-11 19-Mar-11 25-Apr-11 24-May-11 26-May-11 Actual 571,975.27 2-Jun-11 30-Jun-11 10-Jul-11 11-Jan-12 9-Jul-12 Construction UCWC/09/2011 OWRB\UWSS Plan 5-Jun-10 15-Jun-10 22-Jun-10 29-Jun-10 29-Jul-10 8-Aug-10 18-Aug-10 Plan 23-Aug-10 28-Aug-10 7-Sep-10 30-Mar-12 26-Sep-12 267,248.63 Getema Town Civil Work CWC/005/8/20 BOQ NCB 267,248.63 Post Post Actual 01-Jun-10 10-Jun-10 20-Jun-10 24-Jul-10 11-Aug-10 21-Aug-10 Actual 175,014.85 18-Oct-10 28-Oct-10 ######## 7-Nov-11 Construction 08 OWRB\UWSS Plan 10-Jun-09 20-Jun-09 27-Jun-09 4-Jul-09 3-Aug-09 13-Aug-09 23-Aug-09 Plan 28-Aug-09 20-Aug-09 2-Feb-12 ######## 11-Feb-13 219,610.24 DabasoTown Civil Work CWC/005/3/20 BOQ NCB 219,610.24 Post Post Actual 06-Dec-11 10-Dec-11 25-Dec-11 28-Nov-11 05-Jan-12 06-Jan-12 Actual 688,769.00 13-Jan-12 23-Jan-12 2-Feb-12 5-Aug-12 1-Feb-13 Construction 08 Plan 1-Jan-09 11-Jan-09 18-Jan-09 25-Jan-09 24-Feb-09 6-Mar-09 16-Mar-09 Plan 17-May-09 22-May-09 1-Jun-09 26-Jul-10 22-Jan-11 922,195.52 Dhera Town Civil Work OWRB\UWSS BOQ NCB 922,195.52 Post Post Actual 13-May-09 1-Jun-09 20-Jun-09 21-Jul-09 28-Jul-09 28-Jul-09 Actual 875,756.92 31-Jul-09 22-May-09 1-Jun-09 13-Jul-00 9-Jan-01 Construction CWC/002/2008 Small towns Sub Total Cost for Work 6,018,441 5,389,153 5,745,240.60 Procurement of Consultancy Services

Country/Organization: FDR of Ethiopia/OromiaTowns Water Supply and Sewerage Service Improvement and Expansion Project 17.3499 Project/Programmed: Urban Water Supply and Sanitation Project Loan #: IDA Credit 3901-ET and IDA Grant 085-ET

If Post-Review, No-objection will be requested from MOWR PMU Negotiations Contract Finalization Contract Implementation Contract Type Preparation No- objectio Submission Contract n

Draft Amount in

Date Date Cost

Eval Final

(T) (F)/ (F)/ (T)

Prep &Prep

Review Plan Vs ActualVs Plan

Plan Vs ActualVs Plan Contract US$ '000

Amount

Plan vs. Actualvs. Plan

shortlist

ing Date ing Opening

Payment

Contract Contract Advance

by Ex AgEx by

Financial Financial

Gateway/

Signature

Estimated Prior/Post (T) Report

Proposals Report

Evaluation Evaluation (T) Report

ContractId Birr Eth. in

Eval ReportEval

Time-Based Submission Submission

Mobilization Mobilization

Final Report Final

Description* DraftReport

Lumpsum or Lumpsum

Negotiations

No-objection No-objection No-objection No-objection

On-line UNDB On-line

Submission of of Submission

Invitation Date Invitation

Plan vs. Actualvs. Plan National Press National

(T) (F) Contractaward

Negotiated Draft Negotiated

Lead-time beforeLead-time

Submission Date Submission (F) (T) Evaluation

Selection Method Selection Submission/Open List of Contracts 3 - 6 wks 1 - 2 wks 1 - 1.5 wks 2 wks 1 - 2 wks 4 to 12 wks 2 - 3 wks 0.5 - 2 wks2 wks 1 - 2 wks 1 - 1,5 wks Plan 15-Mar-12 25-Mar-12 30-Mar-12 20-Apr-12 5-May-12 15-May-12 Plan 22-May-12 19-Jun-12 29-Jun-12 6-Jul-12 13-Jul-12 23-Jul-12 Plan 28-Jul-12 2-Aug-12 7-Aug-12 14-Aug-12 19-Aug-12 Plan 29-Aug-12 27-Dec-12 11-Jan-13 Consultancy Service for OWRB/CS/ Lump QCBS 86,455.83 Post Rev-2 29-May-12 8-Jun-12 8-Jun-12 18-Jun-12 28-Jun-12 13-Jul-12 Rev-2 13-Jul-12 12-Aug-12 27-Aug-12 11-Sep-12 26-Sep-12 Rev-2 6-Oct-12 11-Oct-12 16-Oct-12 21-Oct-12 31-Oct-12 28-Feb-13 15-Mar-13 Step 3 for Towns Less 01/2012 sum Than 15000 Population Actual Actual Actual Actual

Total Cost For Consultancy Services 86,455.83 Plan Plan Plan Plan